01.Project feasibility report - Environmental Clearance
-
Upload
khangminh22 -
Category
Documents
-
view
0 -
download
0
Transcript of 01.Project feasibility report - Environmental Clearance
1
PRE FEASIBILITY REPORT
FOR
PROPOSED BULK DRUGS AND BULK DRUG INTERMEDIATES
MANUFACTURING PLANT IN EXISTING PREMISES
of
M/s. SWARAJ LIFE SCIENCES
Plot No. 906/18, GIDC Industrial Estate,
Panoli-394 116, Tal: Ankleshwar,
Dist: Bharuch, Gujarat
2
CONTENTS
Sr.
No.
Description Page No.
1. Executive Summary 3
2. Introduction of the Project/Background information 7
3. Project Description 9
4. Site Analysis 14
5. Planning Brief 15
6. Proposed Infrastructure 15
7. Rehabilitation and resettlement (R & R) Plan 17
8. Project Schedule & Cost Estimates 17
9. Analysis of Proposal (Final Recommendations) 17
3
1.0 EXECUTIVE SUMMARY
1.1 Company Profile
Introduction
M/s. Swaraj Life Sciences proposes Bulk Drugs and Bulk Drug Intermediates manufacturing
plant at Plot No. 906/18, GIDC Industrial Estate, Panoli-394116, Dist: Bharuch, GUJARAT.
1.2 Project Details
SR.
NO.
PRODUCTS PRODUCTION CAPACITY (MT/MONTH)
EXISTING PROPOSED
EXPANSION
TOTAL
1 Sodium Thiosulphate 60 -- 60
2 Soidum Sulfite
3 Sodium Bisulfite
4 Potassium Chloride
5 Sodium Acetate
6 Recovered Piperazine Anhydrous 10 -- 10
7 Lamotrigine & Intermediates -- 5 5
8 Citrizine Dihydrochloride &
Intermediates
9 Levocitrizine & Intermediates
10 Clopidogrel Bisulphate & Intermediates
11 Glimepiride & Intermediates
12 Sodium Valporate & Intermediates
13 Riboflavine B2 Phosphate &
Intermediates
14 Fenofibarte & Intermediates
15 Diclofenac Sodium & Intermediates
16 Aceclofenac & Intermediates
17 Dexametharan & Intermediates
18 Tramadol & Intermediates
19 Atorvastatin & Intermediates
20 Pregabaline & Intermediates
Total 70 5 75
4
1.3 Green Belt Development
Company has developed green belt within the factory and on periphery of the factory. In addition to
this, majority of the vacant land shall be planted with trees, shrubs and grasses.
1.4 Power & Fuel Requirement
Power requirement:
100 KVA (Existing)
150 KVA (Additional)
D.G. Set (100 KVA) will be kept for emergency power back up
Source: DGVCL
Fuel Requirement:
Natural Gas: 200 M3/Hr (Existing)
Agro waste: 4 MT/Day (Additional)
HSD: 15 Liter/Hr (Additional)
1.5 Water Requirement and Wastewater Generation & Treatment
Source of water will be met through GIDC Water Supply. Total water requirement will be 24
m3/day). Total 7.27 m3/day (5.67 m
3/day Industrial + 1.6 m
3/day domestic) of effluent shall be
generated, 5 m3/day = low COD stream will be treated in ETP then sent it to CETP, Panoli for further
treatment and disposal and 0.67 m3/day = High COD & High TDS stream will be neutralized & then
sent to Common Spray Dryer for further treatment & disposal.
1.6 Air Pollution Source and Control Management
The source of air pollution due to the project will be Flue gas emission & Process Vents.
5
DETAILS OF PROCESS VENT AND BOILER STACK
PARTICULARS FUEL Fuel Quantity Stack
height
Emission
Norms
APCM
Existing scenario
Boiler (1000
kg/hr)
Natural Gas 200 SCM/Day 11 M PM<150 mg/Nm3
SO2< 100 PPM
NOX< 50 PPM
--
Proposed Scenario after expansion (Flue Gas Emission)
Boiler (1500
kg/hr)
Agro Waste 2 MT/Day 30 M PM<150 mg/Nm3
SO2< 100 PPM
NOX< 50 PPM
Cyclone
Separator
With Bag
Filter
TFH (2 lakh
kcal/hr)
Agro Waste 2 MT/Day 30 M
D.G. Set (100
KVA)
Diesel 15 Lit/Hr 11 M PM<150 mg/Nm3
SO2< 100 PPM
NOX< 50 PPM
--
Proposed Scenario (Process Gas Emission)
Process Vent* -- -- 11M HCL < 20 mg/Nm3 Two Stage
Scrubber
Process Vent* -- -- 11M SO2 < 40 mg/Nm3 Two Stage
Scrubber
6
1.7 Hazardous Waste Management
TYPE OF WASTE &
CATEGORY
SOURCE EXISTING Additional
Total DISPOSAL METHOD
ETP SLUDGE
(Cat. 35.3)
ETP --
2 MT/Month
2 MT/Month COLLECTION, STORAGE,
TRANSPORTATION AND
DISPOSE TO TSDF OF M/S.
PSWML, PANOLI OR M/S.
SEPPL, BHARUCH
DISCARDED DRUMS
/CONTAINERS
(CAT. 33.1)
PROCESS 100
NOS/MONTH
50
NOS/MONTH
150
NOS/MONTH
COLLECTION, STORAGE,
TRANSPORTATION,
DECONTAMINATION &
DISPOSAL BY SELLING TO
REGISTERED RECYCLER
DISCARDED LINER/BAG
(CAT. 33.1)
PROCESS 500
NOS/MONTH
100
NOS/MONTH
600
NOS/MONTH
DISTILLATION RESIDUE
(CAT. 28.1)
DISTILLATION -- 1
MT/MONTH
1 MT/MONTH COLLECTION, STORAGE,
TRANSPORTATION AND
DISPOSE TO COMMON
INCINERATION SITE OR CO-
PROCESSING IN CEMENT
INDUSTRIES
PIPERAZINE ML PROCESS -- 20
MT/MONTH
20
MT/MONTH
COLLECTION, STORAGE
AND RECOVERED IN
PREMISE
SULPHURIC ACID PROCESS -- 7
MT/MONTH
7
MT/MONTH
COLLECTION, STORAGE,
TRANSPORTATION AND
SELL TO END USER
SPENT CATALYST (CAT.
28.2)
PROCESS -- 0.5
MT/MONTH
0.5
MT/MONTH
COLLECTION, STORAGE,
TRANSPORTATION AND
SEND TO RECYCLER
SPENT CARBON (CAT.
28.3)
PROCESS -- 0.5
MT/MONTH
0.5
MT/MONTH
COLLECTION, STORAGE,
TRANSPORTATION AND
DISPOSE TO COMMON
INCINERATION SITE OR CO-
PROCESSING IN CEMENT
INDUSTRIES
USED OIL (CAT. 5.1) PROCESS 20
LITERS/YEAR
30
LITERS/YEAR
50
LITERS/YEAR
COLLECTION, STORAGE,
TRANSPORTATION,
DISPOSAL BY SELLING TO
REGISTERED RECYCLER OR
RE-USE AS LUBRICANT
PROCESS WASTE (CAT-
26.1)
PROCESS 3
MT/MONTH
-- 3 MT/MONTH COLLECTION, STORAGE,
TRANSPORTATION AND
DISPOSAL AT TSDF SITE OF
M/S. PSWML, PANOLI OR
M/S. SEPPL, BHARUCH.
CAUSTIC LYE (HYDRIDE)
(CAT-B14)
PROCESS 40
MT/MONTH
-- 40
MT/MONTH
COLLECTION, STORAGE,
TRANSPORTATION AND
SELL TO END USER
7
2.0 INTRODUCTION OF THE PROJECT/BACKGROUND INFORMATION
2.1 Identification of the project and project proponent. In case of mining project, a copy of mining
lease/letter of intent should be given.
Identification of the project
Proposed Bulk Drugs and Bulk Drug Intermediates manufacturing plant in Existing plant
Identification of the project proponent
Presently following are the Partners of the company:-
1. Mrs. Shilpaben Pankajbhai Mangroliya
2. Mrs. Rashmitaben Kamleshbhai Savaliya
3. Mrs. Sonalben Vipulbhai Mangroliya
4. Mrs. Alpaben Dharmeshbhai Savaliya
2.2 Brief description of nature of the Project
Proposed Bulk Drugs and Bulk Drug Intermediates manufacturing plant in Existing plant
2.3 Need for the project and its importance to the country and or region
The objective is to be achieved by:
• Consolidating Business.
• By constantly upgrading the product range.
• Continuously reducing the Costs & improving Quality.
• To generate local employment
2.4 Demands-Supply Gap
Based on our informal survey of the market with our current customers and various traders, we have
found that there is a big potential for the range of the products we are planning. These products will
be an addition to the current range of our products.
2.5 Imports vs. Indigenous production
Based on the current cost of indigenous raw materials and the non availability of some materials, we
will have to import some of the key raw materials as they are not available indigenously. This will
make us very competitive against imported finished products and we will be able to increase the
export of our finished products.
2.6 Export possibility
There is export potential of our proposed products.
8
2.7 Domestic/Export Markets
There is export potential as well as demand in local market.
2.8 Employment Generation (Direct and Indirect) due to project.
Employment would be as per prevailing norms of state government for skilled and unskilled people
for the proposed expansion project.
3.0 Project Description
3.1 Type of Project including interlinked and interdependent projects, if any.
Proposed Bulk Drugs and Bulk Drug Intermediates manufacturing plant in Existing plant
Category: A-5(f)
9
3.2 Location (map showing general location, specific location and project boundary & project site
layout) with coordinates.
Map showing general location
11
3.3 Details of alternate sites considered and the basis of selecting the proposed site, particularly
the environmental considerations gone into should be highlighted.
Major factors involved in the selection of site are listed below:
• Existing & operational unit
• Site is very well connected by road
• Proximity to Raw Material suppliers
• Availability of sufficient land free from cultivation
• Availability of power evacuation facilities
• Availability of water for industrial use
Modern infrastructure support and amenities at par with industrial estates in other global markets,
including:
� Efficient transport facilities within the industrial estate and to & fro the city area.
� Environment-friendly zone.
� Uninterrupted power supply.
3.4 Size or Magnitude of Operation
Please refer Annexure-I of Form-I.
3.5 Project Description with process details (a schematic diagram/flow chart showing the project
layout, components of the project etc. should be given)
Please refer Annexure-III in Form-I.
3.6 Raw material required along with estimated quantity, likely source, marketing area of final
products. Mode of transport of raw materials and finished products.
Please refer Annexure-I in Form-I
3.7 Resource optimization/recycling and reuse envisaged in the project, if any, should be briefly
outlined.
Company will explore the possibility of reuse.
12
3.8 Availability of water its source, energy/power requirement and source should be given.
Power & Fuel Requirement
Power requirement:
100 KVA (Existing)
150 KVA (Additional)
D.G. Set (100 KVA) will be kept for emergency power back up
Source: DGVCL
Fuel Requirement:
Natural Gas: 200 M3/Hr (Existing)
Agro waste: 4 MT/Day (Additional)
HSD : 15 Liter/Hr (Additional)
Water Source
The entire water requirement will be met through GIDC Water Supply.
3.9 Quantity of wastes to be generated (liquid and solid) and scheme for their
management/disposal.
Liquid Waste:
Source of water will be met through GIDC Water Supply. Total water requirement will be 24
m3/day). Total 7.27 m3/day (5.67 m
3/day Industrial + 1.6 m
3/day domestic) of effluent shall be
generated, 5 m3/day = low COD stream will be treated in ETP then sent it to CETP, Panoli for further
treatment & disposal and 0.67 m3/day = High COD & High TDS stream will be neutralized & then sent
to Common Spray Dryer for further treatment & disposal.
Solid Waste:
Please Annexure- VI in Form-I.
13
3.10 Schematic representations of the feasibility drawing which give information of EIA purpose.
RECONNAISSANCE SURVEY OF EXISTING PLANT ANNUAL REPORT
MARKET ASSESSMENT
FINANCIAL REPORT
PROJECT REPORT
INTRODUCTION
MONITORING OF AIR, WATER & SOIL QUALITY & NOISE
LEVELS. DATA ON METEOROLOGY SOCIO-ECONOMIC
STATUS & BASIC AMENITIES. SITE VISITS BY AND
INTERVIEWS WITH LOCALS
BASELINE
ENVIRONMENTAL
STATUS
ENVIRONMENTAL INFORMATION CENTRE
CENTRAL GROUND WATER BOARD
GUJARAT POLLUTION CONTROL BOARD (GPCB)
PUBLIC HEALTH ENGINEERING DEPT.
AGRICULTURE DEPARTMENT
FOREST DEPARTMENT
IRRIGATION DEPARTMENT
EMPLOYMENT EXCHANGE
HEALTH CENTER
CENSUS DEPT.
INDIAN METEOROLOGICAL DEPT.
SOCIOECONOMIC
STATUS &
INFRASTRUCTURE
PROPOSED
EXPANSION PLANT
FACILITY DESCRIPTION
IMPACTS
METHODOLOGY OF
IMPACT
ASSESSMENT
IDENTIFICATION & ASSESSMENT OF IMPACTS
EVALUATION OF IMPACTS BY MATRIX METHOD
SOURCE OF INFORMATION OVERVIEW OF
E. I. A. STUDIES
ACTIVITIES
ENVIRONMENTAL
MANAGEMENT PLAN
DESCRIPTION OF EFFLUENT TREATMENT PLAN, AIR
POLLUTION CONTROL, HAZARDOUS WASTE
MANAGEMENT, GREEN BELT DEVELOPMENT
MONITORING PROGRAM
RISK ANALYSIS
STUDIES &
DISASTER
MANAGEMENT PLAN
SAFETY, HEALTH & ENVIRONMENTAL POLICY, GUIDELINES BY
DIRECTOR GENERAL OF FACTORY SAFETY, MINISTRY OF LABOR. CONSEQUENCE ANALYSIS
PREPARATION OF DISASTER MANAGEMENT PLAN
14
4.0 Site Analysis
4.1 Connectivity
• Site is very well connected by road & rail
• Availability of power evacuation facilities
• Availability of water for industrial use
4.2 Land Form, Land Use and Land Ownership
It will be incorporated in EIA Studies.
4.3 Topography (along with map)
We will incorporate topography in EIA Studies.
4.4 Existing land use pattern (agriculture, non-agriculture, forest, water bodies (including area
under CRZ)), shortest distances from the periphery of the project to periphery of the forests,
national park, wild life sanctuary, eco sensitive areas, water bodies (distance from HFL of the
river), CRZ. In case of the notified industrial area, a copy of the Gazette notification should be
given.
It will be incorporated in EIA Studies.
4.5 Existing Infrastructure
Existing Infrastructures facilities are listed below:
Site is very well connected by road
Proximity to Raw Material suppliers
Availability of CETP and common TSDF in the estate
Availability of sufficient land free form cultivation.
Availability of power evacuation facilities
4.6 Soil Classification
It will be incorporated in EIA Studies.
4.7 Climatic data from secondary sources.
Primary source: our own weather station & Secondary Sources: Indian Meteorological Department,
Ahmedabad.
15
4.8 Social infrastructure available.
Depending on the growth of the company the required social infrastructure will be provided.
5.0 Planning Brief
5.1 Planning Concept (type of industries, facilities, transportation etc) Town and Country
planning/Development authority classification.
Type of Industry: Proposed bulk drugs and bulk drug intermediates manufacturing plant in Existing
Premises
5.2 Population Projection
It will be incorporated in EIA Studies.
5.3 Land use planning (breakup along with green belt etc.)
Plot Area: 1,315 m2
Total Plant area: 300 m2
Administration Building: 100 m2
Total Utility Area: 200 m2
ETP Area: 100 m2
Raw Material and Product storage area: 200 m2
Green belt area: 150 m2
Open & Road Area: 265 m2
5.4 Assessment of Infrastructure Demand (Physical & Social)
It will be incorporated in EIA Studies.
5.5 Amenities/Facilities
It will be incorporated in EIA Studies.
6.0 Proposed Infrastructure
6.1 Industrial Area (Processing Area)
Processing Area (Processing Zone, ETP Area and Utility Area): 600 m2
16
6.2 Residential Area (Non Processing Area)
Non Processing Area (Green belt, Raw material storage area, Finished storage area, road, Open
Area): 715 m2
6.3 Green Belt
Company has developed green belt within the factory and on periphery of the factory. In addition to
this, majority of the vacant land shall be planted with trees, shrubs and grasses.
6.4 Social Infrastructure
Depending on the growth of the company the required social infrastructure will be provided.
6.5 Connectivity (Traffic and Transportation Road/ Rail/Metro/ Water ways etc)
Site is very well connected by road & railway.
6.6 Drinking water Management (Source & Supply of water)
Water requirement will be met through GIDC Water Supply
6.7 Sewerage System
Sewage pipes are laid in entire company for the removal and disposal of mainly non-harmful liquid
wastes from the offices, canteen and domestic waste coming from different sections. These liquid
wastes is treated and disposed by septic tank and soak pit.
6.8 Solid Waste Management
Please refer Section 1.7, Page No. 7 in Pre-Feasibility Report.
6.9 Power Requirement & Supply/Source
Power requirement:
100 KVA (Existing)
150 KVA (Additional)
D.G. Set (100 KVA) will be kept for emergency power back up
Source: DGVCL
17
7.0 Rehabilitation and Resettlement (R & R) Plan
7.1 Policy to be adopted (central/state) in respect of the project affected including home ousters,
land ousters and landless laborers (a brief outline to be given)
There is no habitation on the proposed expansion project area and it is industrial land which is
purchased by company for development of Company, so that R & R policy is not applicable to this
project. There shall be no displacement of any population in project area.
8. Project Schedule & Cost Estimates
8.1 Likely date of start of construction and likely date of completion (Time schedule for the project
to be given).
We shall start construction after getting environmental clearance. We shall start production upon
making application for CCA.
8.2 Estimated Project cost along with analysis in terms of economic viability of the project.
Total costs of the project will Rs. 2.5 Crore. Capital cost of air & water pollution control system and
environmental monitoring equipments will be Rs. 40 Lakhs.
9. Analysis of Proposal (Final Recommendations)
9.1 Financial and social benefits with special emphasis on the benefit to be local people including
tribal population, if any, in the area.
• Employment would be as per prevailing norms of state government for skilled and unskilled
people for the proposed project.
• Social Welfare shall be done.
• Cordial relation with the industry shall be established and representation shall be made to
villagers for help for creation of facilities related to health, education, etc.