KANSAI INTERNATIONAL AIRPORT
Transcript of KANSAI INTERNATIONAL AIRPORT
KANSAI INTERNATIONAL AIRPORT
Submitted by:ABHISEK PANDA
8th Sem, CIVIL Engg.ORISSA ENGINEERING COLLEGE
CONTENT• OVERVIEW• CONSTRUCTION• TECHNICAL & ENGINEERING ISSUES• AIRPORT ISSUES• OPERATION• AWARDS• CONCLUSION
OVERVIEW• Name: Kansai
International Airport• Place: Osaka
prefecture, Japan• Area: 10 km2 (4 km
2.5 km)• Total cost: $20
billion (including both phases)
• Commencement of project: 1986
• Public opening: 4th September, 1994
• Terminals: 2• Runways: 2
• Flight Information: Weekly International Flights: 815
Weekly Domestic Flights: 493
CONSTRUCTION• Man made Island:
Sea wall construction with 48K tetrahedral blocks and rocks
21 million m3 of land fill
1 million workers 10 million work hours
Over 3 years Eighty ships 30 meter height sea wall
• Sky Gate Bridge: 3 km in length $1 billion
TECHNICAL AND ENGINEERING ISSUES
•Seawall Construction
•Airplane Landing
•Sinking of the Island
•Severe Earthquake and Typhoons
BREAK WATER/SEAWALL CONSTRUCTION
• Up to 40ft above sea level• Took nearly 2 years for completion
• Tripod blocks on sea ward side for wave energy dissipation
• Application sand drains for improvement of subsoil
MECHANISM OF SAND DRAIN• The weight of the piled sand forces the water in the clay to move outward along the sand pile
• Equal strain case was adopted over free strain case near terminals
APPLICATION OF ONE MILLION SAND PILES
• Time rate of consolidation (as per Terzaghi’s consolidation) in radial direction:
• Consolidation settlement is given by,
2
21
vu u uCt r r r
0
'log1 'CHCe
AIRPLANE LANDING• Airplane landing is the major problem for the designers : Yasunari Harada
• The spongy soft clay of sea bed tries to deform the runway
• Create imbalance tending to topple the airport
PRECAUTIONS • Usage of steel structure : makes the runway flexible; causing uniform stress distribution
• Large amount of sand piles closely spaced
SINKING OF THE ISLAND• Practical settlement was 8.2 m (27ft) in the year 1999 against calculated settlement 5.7m (19ft)
• The settlement continued @ 2’’ (5 cm)/month
• The sinking fell to 2’’ (5 cm)/year by the year 2008 as per “Yasunari Harada”- Manager, planning dept.
• Additional 11.6ft of land fill was added in the year 1990 to account for settlement
REASONS OF WRONG PREDICTION• Un-conservative estimation of consolidation settlement
• Wrong estimate of the time required for completion of consolidation settlement
• Ineffectiveness of the sand drains in achieving the required success as 100%
• Excavation of bore holes up to 250m and in rare case up to 400m; which led to vague information regarding soil strata
GRAPPLING WITH CONTINUED SETTLEMENT
• Usage of high amount of iron ore Faster sinking of Island than the supported building
• Installation of hydraulic jacks under the columns Result: No differential settlement between columns and entire buildings
• Terminal design: Limit State Method
LEARNING FROM MISTAKES• Using actual settlement data in phase-II construction
• Analysis of bore hole up to 900 m and over 400m in most of the cases
• Expected settlement is conservative i.e. 18m (60 ft) against 12m
EARTHQUAKE• Kansai airport is in the middle of pacific rim of fire
• Japan is the land of earthquakes; approximately 1500 per year
• Major earthquake: Kobe earthquake (17th January, 1995) Epicenter: 20km (12 miles) from KIA Death no. : 6,434
TYPHOONS• On an average Japan faces 9-10 Typhoons per year
• The airport survived against two major typhoons: In the year 1998, wind speed: 200 kmph
In the year 2004, wind speed: 172 kmph
• Sea waves up to 6 m high were generated due to Typhoons
COPING WITH EARTHQUAKES & TYPHOONS
• Up to 12m (40 ft) high sea wall: Neutralizes the tidal effect
• Usage of sliding joints instead of rigid joints
• Preferring steel structure over R.C.C structures
• Wing shape
terminal designed by Renzo Piano
CYLINDRICAL JOINT
PRISMATIC JOINT
SOCIAL & ECONOMICAL PROBLEMS
• Second most expensive airport• Local problems of fisherman; silenced by hefty compensation package
• $20 billion dollar expenditure• High landing fees: $7500 for Boing 747
• Onsite concession operation cost: $10 per coffee cup
• Airport debt: $560 million interest per year
POLICY CHALLENGES• Noise pollution:
Noise due to air crafts Transportation noise
• Traffic amount Increase Increasing traffic @ 5% per annum Other traffics like carriers, rails and ships etc.
• Air quality and climate NOx, SOx, CO, CFC, Ox, HC, wind direction and wind speed
• Water/Sediment Quality: Turbidity, pH level etc.
• Marine life & Land Dwelling creatures: Plankton, roe, fish, bottom dwellers etc. Flight and nesting of birds Migration of eagles, hawks & cold climate birds
OPERATION• Kansai international airport co. ltd. is the company founded in 1984 for this purpose
• Joint investment of National, Local and Private organizations
• 6 subsidiaries specialized in individual fields
• 36.54 m high control tower located at the
middle• Over 250 cameras and infrared bars for security
• 24 hours shield from Japan coast guard
Control Tower
AWARDS & NOMINATIONS• Ranked 4th overall in the Airport of the Year 2006 awards; named by Skytrax
• On April 19, 2001, the airport was one of the "Civil Engineering Monument of the millennium by the American Society of Civil Engineers
• “Civil Engineering Monument of the Year – 2001”-American Society of Civil Engineers
CONCLUSION• Osaka is a business hub today in Japan• Initial loss has turned to profit making business : approx. 1.8 billion$/year
• Relaxation of over burden on Kobe and New Tokyo airport
• One of the busiest airport in East-Asia• Serves as guide for other similar mega structures: Hong Kong International Airport, Kitakyushu Airport etc.
BIBLIOGRAPHY AND REFERENCES• KANSAI INTERNATIONAL AIRPORT (PHASE-I)
FOUNDATION CASE STUDY, BY RAJUL TEREDESAI, CE 5333-FOUNDATION ENGINEERING SPRING, 2005
• WIKOPEDIA.ORG• OFFCIAL WEBSITE OF KIA• A REPORT ON FOUNDATION STUDIES OF KANSAI INTERNATIONAL AIRPORT, BY JUSTIN PHALEN. UC-DAVIS, 2002