Laser-pumped paraffin-coated cell rubidium frequency standard
PUMPED STORAGE HYDRO PLANTS IN BALANCING POWER FLOW
-
Upload
independent -
Category
Documents
-
view
0 -
download
0
Transcript of PUMPED STORAGE HYDRO PLANTS IN BALANCING POWER FLOW
PUMPED STORAGE HYDRO PLANTS IN BALANCING POWER FLOW
Authors: * Pranab K. Bhaduri; ** Amit K. Gangulee
Session Title: 15A – Renewable Energy Storage Systems: Enabling the Grid of the Future;
Track: Utility Integration;
Presentation Date: 09 December 2014; Time: 1:30 PM – 3:30 PM;
Session Chair Karen Bertram
Integrated Energy Services
*Senior Executive Director: Development Consultants Private Limited, Kolkata, India
** Executive Vice President: The Kuljian Corporation, Philadelphia, PA, USA
1
1.0.0 Preamble
Pumped Storage Hydro Plant – an essential component of electricity network – acts by way of balancing power flow in the grid i.e. as peaking stations. During low power demand periods, water is pumped from lower reservoir to the upper one; that subsequently generates hydro power by releasing the water into the lower reservoir, running through reversible turbines/motors and sending the energy back to the grid during peak energy demands.
increased wind and solar capacity, would significantly improve grid reliability while
reducing the need for construction of additional coal, oil and gas based generation.
Underground pumped storage, using flooded mine shafts or other cavities, are
also technically possible.
Pumped storage plants are, however, high capital-intensive, ecology-sensitive and
also require long implementation times. Nevertheless, with rising electricity prices and
an increasing use of intermittent energy sources, it can be very economical to store
electricity for later use.
USD 600 million Purulia Pumped Storage Plant (4 units of 224 MW each) at Ayodhya Hill in
Purulia District of West.Bengal state, in India, is one such plant that has been commissioned in
the recent past.
The paper primarily deals with Pre-feasibility Study based on high level field
reconnaissance, Survey of India topographic sheets and various desk studies – power
scenario, hydrologic& water availability, geologic, etc., and initial field Survey& Field
Investigation – in order to establish the phase-wise development of the project, jointly
by Development Consultants, India, and Harza Engineering, USA, in the year 1979-80.
Pumped storage – a renewable
green energy portfolio - is a
proven grid-scale energy
storage technology; and, can
also run on other renewable
energy sources like wind, during
off-peak periods, for pumping up
the water. Developing additional
hydropower pumped storage,
particularly in areas with recently
2
Amongst others, initial field survey & investigation works, studies/ analyses, designs &
engineering covering the paper are:
Demand & Supply Scenario of Power in India, Peak hour Power Deficit:
Pattern of Peak Demand and Energy Requirement;
The Project, Site Visit, High level Reconnaissance and Initial Investigations;
Hydrologic Studies and Water Availability;
Project Components – Sizing & Layout;
Environmental & Social Impact Studies;
Project Cost Estimates and Implementation Schedule;
Detailed Field Surveys and Investigations;
Project Development & Economics
2.0.0 Demand & Supply Scenario of Power in India, Peak hour Power Deficit 2.1.0 Variation in Power Demand
We are aware, every power system displays variability in demand between Seasons and various hours of a day. There are also considerable variations in electricity demand between weekdays, weekends or holidays. In India, in 2010-11 peak demand in the power system was 122 GW, while the average demand was only 98 GW. The minimum demand in the system was of the order of 75 GW. 2.2.0 Eastern Region of India Scenario
Again, in the Eastern Region of the country, where the state of West Bengal
is a part, shows the variation in demand (MW)/ availability(MU) in last several years: (Ref. Load Generation Balance Report 2014-15 (CEA))
3
2.3.0 Peak Demand Power Scenario in West Bengal
The states in India are reeling under pressure to solve the peak demand of electricity; and, are trying out various options to tie up with the situation. In the first quarter of the year 2008, West Bengal State Electricity Distribution Corporation
18,000
17,000
16,000
15,000
14,000
13,000
12,000
11,000
10,000
Peak Demand (MW)
Energy Requirement (MU)
11,000
10,500
10,000
9,500
9,000
8,500
8,000
7,500
7,000
6,500
6,000
2010-11
2011-12
2012-13
2013-14
2014-15
(projected)
2010-11
2011-12
2012-13
2013-14
2014-15
(projected)
4
Limited (WBSEDCL) commissioned the Purulia Pumped Storage Power Project (PPSP) as a step forward in the direction to meet the peak hour demand. As per Central Electricity Authority (CEA), Government of India report, the peak hour demand for March 2008 in the state of West Bengal was 5,379 MW and supply was 4,754MW. Despite the commissioning of the PPSP, the overall peak hour power deficit was 625 MW (about 12% deficit).
The scenario would have been more critical in the event of more power-intensive industrialization in the region, less captive power facilities in industrial units, and more domestic consumption as happens in sustainable economic growth of the region, warranting more buying power of the citizens.
The per capita annual Energy Consumption in combined rural & urban India is, again, much lower than other industrialized and high income countries, as evident from the following table:
YEAR PER CAPITA ANNUAL CONSUMPTION (KWH)
INDIA * CHINA FRANCE PAKISTAN UK USA
2005-06 631.4
2006-07 671.9
2007-08 717.1
2008-09 733.5
2009-10 778.6
3,298 7,292 449 5472 13,246 2010-11 818.8
2011-12 883.63
2012-13 917.8
Basis: * (GrossGen.+ Net Import) / mid-year Population
Ref.India:Power Sector Report (Feb 2014) - CEA, GoI;Others: World Bank Data
2.4.0 Pumped Storage Hydro
Pumped storage provides vital support to the national or regional electricity grid(s), helping to balance the flow of power across transmission networks by absorbing excess when electricity demand is low and releasing it when demand increases. With an ability to respond almost instantaneously to changes in the amount of electricity running through the grid, pumped storage is an essential component of the nation’s electricity network. Pumped storage is a proven grid-scale energy storage technology that can also enable India to grow its renewable energy portfolio. Moreover, the impact of construction of such projects on the environment is quite low. There is hardly any impact on flora and fauna.
5
3.0.0 The Project, Site Visit & high level Reconnaissance, Initial Investigations 3.1.0 Project Inception
In the year 1979, Central Electricity Authority (CEA), Government of India (GoI), initiated the scheme of Purulia Pumped Storage Hydel, by way of preparing an assessment report. This was followed up West Bengal State Electricity Board (WBSEB), thru’ conducting a reconnaissance survey and preparing a project profile, based on four streams/ nullah on Ayodhya Hills in Purulia Dist. of W. Bengal State – Kistobazar, Turga, Kathlajal, and Bandhunala. Development Consultants Private Limited (DCPL), an India based consulting engineering firm, was then commissioned by WBSEB to prepare a Pre-feasibility report (in association with Harza Engineering, Chicago, USA), and instructed to submit the report in early January 1980, for onward submission to GoI, for funding.
Subsequently, DCPL had been instructed to carry out topographic survey, geotechnical and hydrological investigations and studies. This was supplemented by the state irrigation and waterways directorate for hydrological observation work in 1982. The project had been held up for several years in want of fund and decisions for investment.
3.2.0 The Project
Purulia Pumped Storage project is located in Baghmundi Village on
Ayodhya Hills under the district of Purulia, West Bengal, on Kistobajar Nullah /
stream(a tributary of Shaba nullah that drains into Subarnarekha River).
6
3.3.0 Survey, Investigation, Desk Studies, Design & Engineering
For good engineering practice and statutory requirements (CWC and CEA, GoI), the following field survey & investigation works, desk studies, designs, cost estimates, etc. had been carried out, for preparing/ submitting the report:
Site Visit, High level Reconnaissance Survey & Invetigation (approach to site / availability & adequacy of roads & rail links; nearby towns, bank, post office, market; topographic, hydrologic incl. river/ stream regimes, geologic, soil/rock characteristics, flora & fauna, wild life, and catchment area visualization – survey & initial Investigations);– one week duration, by a team of engineers & scientists in the disciplines of civil engineering, applied geology, hydrology/ water resource engineering, hydro project expert; and, led by the Technical Director of the consultant;
Hydrologic Studies & Water Availability (based on Survey of India Topo - graphic Sheets, Field Data & Historical Data from Water Resources Dept (GoWB), Meteorological Data, Soil & Geologic characteristics at site);
Geo-technical Studies; Power Potential Studies (with 90% and 75% dependability on water
availability assessment); Evaluation of Reservoir Volumes & Water Levels;
Sedimentation Studies and Remedial Measures; Assessment & Preliminary Designs of upper & lower Reservoirs and
Dams; Intake Structures & gates; Penstocks & Tail Race Tunnels; Surge Tank(s); Power House: Hydro-Mechanical Equipment; Transmission lines/ Switch yard; Telecommunication system;
Assessment and Specifying Hydro-Mechanical and Electrical Equip-ment and ancillaries;
Construction Materials/ Quarries; Site Infrastructures and Construction Enabling Works; Project Implementation Plan, Program/ Schedules; Cost Estimate (local & foreign; applicable taxes, duties & levies); Cost-Benefit Analysis; and, Commercial Viability; Requirement of Essential/ Detailed Field Survey & Investigation works,
to be taken up in the next stage, like – Detailed topographical survey of reservoir area, project area, township,
roads & approaches; Survey of India Topographic Sheets; Procurement of satellite imageries
including aerial maps; Geo-physical surveys comprising seismic and resistivity tests, etc; Hydro-meteorological observations; Geo-technical exploration comprising surface mapping, drilling, drifting
and their logging; Laboratory Tests; Collection of Silt data & its analysis; Construction material survey- quantitative and qualitative;
7
NOTE:
An over estimate of water availability may lead to larger investment and project
may become costlier resulting in a higher installation. On the other hand, a lower
estimate of water availability may result in a wastage of some hydro potential and
non- utilization of selected site optimally. Hydrological studies include assessment
of quantities of available water at the project site and time variation, estimation.
Planning of Hydro Projects is carried out based on 90% dependability
criteria. For determination of 90% dependable year, the total energy generation in
all the years for which hydrological data is available (say, N year) is arranged in
descending order and the (N+1) x 0.9 th year would represent the 90 per cent
dependable year. The 90 per cent dependable year is thus, termed as the year in
which the annual generation has the probability of being equal to or exceed 90 per
cent of the time on annual basis during the expected period of operation of the
scheme.For example, if inflow data is available for a period of 20 years (N=20),
then, 90% Dependable year = (20+1)*0.9= 18.9 = 19th year
Power Potential studies had been carried out for assessment of available Power
Potential of the stream based on a set of inflows and available head conditions
under various operating policies. (Such studies play an important role in the
optimization and design of new hydro facilities. They are used for examination of
various configurations and their integration into existing networks)s.
The detailed investigation was taken up
under loan assistance of 629 Million Yen
from Overseas Economic Co-operation
Fund, Japan and through Electric Power
Development Corporation, Japan, as
foreign consultant along with Central
Electricity Authority, Central Water
Commission; and, Water &Power
Consultancy Services) as local consultants.
The detailed project report was submitted
to CEA by WBSEB in 1992. The techno
economic clearance was accorded by
CEA in 1992. In February 1994, clearance
from the Ministry of Forest and
Environment (MoEF) received.
8
In case of Pumped Storage Hydro Plants, however, the capacity of upper/lower reservoirs, availability of surplus off-peak energy, intended operating pattern of the pumped storage scheme determines its installed capacity. The procedure for optimization of the installed capacity and deciding the number of units is same as applied for run-of-river schemes/ storage based schemes.
The units size had been determined depending upon transportation constraints,
flexibility of operation and system considerations and geological constraints like permissible cavern size (underground power house, in this project).
4.0.0 Project Components – Sizing & Layout
Installed capacity 900 MW (4 x 225)
Peak operation duration 6 hours
Maximum power discharge 600 cum/sec
Effective head 177 m
Upstream reservoir
Catchment area 9.50 sqkm
Full reservoir level (FRL) 516 m
Minimum draw down level (MDDL) 494 m
** Dam height from rock foundation 71 m
Dam crest length 1.50 km
Reservoir area at FRL 1.00 sqkm
Total storage capacity 16.50 mil. cum
(a) Live storage 13.00 mil. cum
(b) Dead storage 3.50 mil. cum
9
Downstream reservoir
Catchment area 9.50 sqkm
Full reservoir level 337 m
Minimum draw down level 300 m
** Dam height from rock foundation 95 m
Dam crest length 310 m
Reservoir area at FRL 0.53 sqkm
Total storage capacity 16.00 mil cum
(a) Live storage 13.00 mil cum
(b) Dead storage 3.00 mil. cum
Headrace intake tunnel 7.7 m diameter x 2
Penstock 7.7 - 7.3 m diameter x 2
4.3 m x 4
Tailrace 8.7 m diameter x 2
5.6m diameter x 4
Sedimentation rate 950m3 per ha/year
Powerhouse: underground powerhouse – 157 x 22.5 x 47.7 m (size), housing 4-vertical shaft, Francis reversible turbine-generator units of 225MW each.
Pump/ Turbine 230MW/250MW x 4, Francis
type
Reversible pump turbine, 250rpm
10
Generator/motor 250MVA/255MW x 4,
Synchronous, 3 phase,
50Hz, pf. 0.9/1.0, 24 poles
Unit space 25.5m
Transformer capacity 280MVA, 16.5kV/400kV
Generation voltage 16.5kV
Transmission voltage 400kV
Construction cost (latest approved cost) Approx. US$665M
** Rockfill dams with central clay-core;
++ Two 400 kV double circuit transmission lines connecting Durgapur and
Arambag 400 KV S/S with PPSP have been constructed for transmitting/ receiving
power from PPSP.
5.0.0 Project Development and Economics
5.1.0 Project Development
In February 1994, clearance from the Ministry of Forest and Environment (MoEF), Government of India, had been received. 5.2.0 Economics
Pumping requires more power than the power that the same quantity of water can generate. Why then, we recommend installing pump storage hydro stations? The reasons can be attributed to: Make use of the difference between power pricing during peak & off peak
hours; Generally, the peak hour power price is higher than the off-peak;
The pumped water is used to produce power in the peak (evening) when it is costly. This helps to meet the extra power demand in eve.
Stabilize power distribution system for smooth running of industrial units
Improves the poor thermal-hydel mix ratio of the region to a great extent
11
5.3.0 Project Benefits
Peak demand can be met instantly
Plant load factor of thermal power stations can be improved
Results in grid frequency stabilization of the region
Utilizes surplus grid power to pump water from lower reservoir to upper one at lean hours
Environmental Impact is Low
But, current market structures and regulatory frameworks in developing
countries, however, do not present an effective means of achieving this
goal. Policy changes and stream-lined licensing process are needed to
support the timely development of additional grid-scale energy storage.
A California Public Utilities Commission (CPUC) study (2010) identifies the following factors that contribute to economic development through the use of pumped storage technology: a) reduced need for peak generation capacity; b) employment and other economic growth; c) reliable and cleaner back-up power; d) transmission support and congestion relief; e) more efficient use of renewable and off-peak generation capacity; f) Reduced need for transmission and distribution capacity upgrades; and, g) Increased and improved availability of ancillary services.
The hydroelectric plants in the Columbia River basin in the Pacific Northwest generate 22,000 MW in output. In the photo: a dam wall in the many-branched dam system. (Credit: Fraunhofer IOSB)
12
5.4.0 Further Initiatives by the State Utility
The State utility – WBSEDCL - has planned a detailed survey and project report for Turga Pumped Storage project (1,000 MW) and Bandhu Pumped Storage project (900 MW) in Purulia District. Detail Project Report (DPR) for both the schemes are likely to be completed by the fiscal: 2015 -16.
6.0.0 Policies, Regulatory Framework and Pricing Model
Policy till date has only articulated the objectives of peak demand being
met and spinning reserves created, but (unlike for baseload generation)
not the mechanisms to build or procure peaking power.
Peaking Power projects must be specifically identified. Trying to meet
peaking power needs from base load projects is bad economics, even if
optically cheap
Peaking Power must be an integral part of the perspective plans and the
five year planning process.
7.0.0 WAY TO GO:
A comprehensive Clean Energy Portfolio Obligation (CEPO) for utilities and users that combines Renewable Portfolio Obligations (RPO) to ensure renewable energy development; with,
Capacity Portfolio Obligations (CPO) to ensure that demand and supply
are balanced and peaking demand is served; and,
Energy Efficiency Portfolio Obligations (EEPO) - to ensure that utilities do the needful on energy efficiency and demand side management as well.
8.0.0 Acknowledgement:
Renewable Energy World Conference & Expo North America 2014
Central Electricity Authority (CEA), Government of India – Min. of Power
Planning Commission, Government of India
Geological Survey of India/ Survey of India/ I&W Dept (GoWB)
13
WBSEB/ WBSEDCL/ NHPC/ ALSTOM
Foundation of Infrastructure Research Studies Training
Water Power and Dam Construction magazine
EPRI, 2002. Handbook for Energy Storage for Transmission or
Distribution Applications. Report No. 1007189. Technical Update
December 2002.
CPUC, 2010. Electric Energy Storage: An Assessment of Potential
Barriers and Opportunities. A Policy and Planning Division White Paper of
the California Public Utilities Commission.
Schoenung, S., M., & Hassenzahn, W., V., 2002. Long- vs Short-Term
Energy Storage Technology Analysis: A life cycle cost study
Taylor, R. (2007), Hydropower Potentials, International Hydropower Assoc
National Hydropower Association (NHA)
Anish De : AF-Mercados EMI - Peaking Power – Imperatives for the Indian
Power System
Development Consultants, India; The Kuljian Corporation, USA
---------------------------------------------------------------------------------------------------------------------