APPLICATION FOR EC (FORM-1) M/s. SARAVANA SELVARATHNAM RETAIL PRIVATE LIMITED, JAMIN PALLAVARAM, KANCHEEPURAM FORM 1 I. Basic Information S.No Item Details 1 Name of the Project/s : Proposed Commercial Development ‘SARAVANA STORES” by Saravana Selvarathnam Retail Private Limited. 2 S.No. in the Schedule : 8(a) of EIA Notification 3 Proposed Capacity/area/length/tonnage to be handled/command area/lease area/number of wells to be drilled : Total Plot Area –20,695.06 Sq.m Built up area – 89,907.02 Sq.m 4 New/Expansion/Modernization : New 5 Existing Capacity/Area etc., : - 6 Category of Project i.e. ‘A’ or ‘B’ : Category “B” 7 Does it attract the general condition? If yes, please specify : No 8 Does it attract the Specific condition? If yes, please specify : No 9 Location : Plot/Survey/Khasra No. : 39/10-1B, 11, 42/1, 2, 43/1, 2, 3, 4, 5, 6, 7, 8, 10, 11, 12, 13, 14, 46/2, 3, 6-3, 10-2, Old S. Nos. 263/1, 2A, 2B, 3, 4, 5, 6, 7, 9, 10, 11, 12, 13, 264/2, 3, 5A, 6, 270/1, 2, 278/1B & 12B Village : Jamin Pallavaram Tehsil : Pallavaram District : Kancheepuram State : Tamil Nadu 10 Nearest Railway Station/Airport along with distance in KMS : Airport Mono Rail Station - 3 Km 11 Nearest Town, City, District Headquarters along with distance in KMS : Within Chennai City Corporation Limits 12 Village Panchayats Zilla Parishad, Municipal Corporation, Local body (complete postal address with telephone) : Greater Chennai Corporation, Ripon Building, Chennai – 600 003 Ph: 044 – 2538 1330 13 Name of the Applicant : Saravana Selvarathnam Retail Private Limited 14 Registered Address : #14, Ranganathan Street, T.Nagar, Chennai – 600 017 15 Address for Correspondence: : Name : Mr. S.R. Saravana Arul Designation (Owner/Partner/CEO) : Managing Director Address : #14, Ranganathan Street, T.Nagar, Chennai Pin Code : 600017 E-mail : [email protected] Telephone No. : 044 2434 7710 044 2431 5550 Fax No. :

Transcript of FORM 1 I. Basic Information - Environmental Clearance

APPLICATION FOR EC (FORM-1)

M/s. SARAVANA SELVARATHNAM RETAIL PRIVATE LIMITED, JAMIN PALLAVARAM, KANCHEEPURAM

FORM 1 I. Basic Information

S.No Item Details

1 Name of the Project/s : Proposed Commercial Development ‘SARAVANA STORES” by Saravana Selvarathnam Retail Private Limited.

2 S.No. in the Schedule : 8(a) of EIA Notification

3 Proposed Capacity/area/length/tonnage to be handled/command area/lease area/number of wells to be drilled

: Total Plot Area –20,695.06 Sq.m Built up area – 89,907.02 Sq.m

4 New/Expansion/Modernization : New

5 Existing Capacity/Area etc., : -

6 Category of Project i.e. ‘A’ or ‘B’ : Category “B”

7 Does it attract the general condition? If yes, please specify

: No

8 Does it attract the Specific condition? If yes, please specify

: No

9 Location :

Plot/Survey/Khasra No. : 39/10-1B, 11, 42/1, 2, 43/1, 2, 3, 4, 5, 6, 7, 8, 10, 11, 12, 13, 14, 46/2, 3, 6-3, 10-2, Old S. Nos. 263/1, 2A, 2B, 3, 4, 5, 6, 7, 9, 10, 11, 12, 13, 264/2, 3, 5A, 6, 270/1, 2, 278/1B & 12B

Village : Jamin Pallavaram

Tehsil : Pallavaram

District : Kancheepuram

State : Tamil Nadu

10 Nearest Railway Station/Airport along with distance in KMS

: Airport Mono Rail Station - 3 Km

11 Nearest Town, City, District Headquarters along with distance in KMS

: Within Chennai City Corporation Limits

12 Village Panchayats Zilla Parishad, Municipal Corporation, Local body (complete postal address with telephone)

: Greater Chennai Corporation, Ripon Building, Chennai – 600 003 Ph: 044 – 2538 1330

13 Name of the Applicant : Saravana Selvarathnam Retail Private Limited

14 Registered Address : #14, Ranganathan Street, T.Nagar, Chennai – 600 017

15 Address for Correspondence: :

Name : Mr. S.R. Saravana Arul

Designation (Owner/Partner/CEO) : Managing Director

Address : #14, Ranganathan Street, T.Nagar, Chennai

Pin Code : 600017

E-mail : [email protected]

Telephone No. : 044 2434 7710 044 2431 5550

Fax No. :

APPLICATION FOR EC (FORM-1)

M/s. SARAVANA SELVARATHNAM RETAIL PRIVATE LIMITED, JAMIN PALLAVARAM, KANCHEEPURAM

16 Details of Alternative Sites examined, if any Location of these sites should be shown on a TOPO Sheet

: No alternative site examined

17 Interlinked Projects : Nil

18 Whether separate application of interlinked project has been submitted?

: No

19 If yes, date of submission : Not Applicable

20 If no, reason : Not Applicable

21 Whether the proposal involves approval/clearance under: if yes, details of the same and their status to be given.

(a) The Forest (Conservation) Act, 1980?

(b) The Wildlife (Protection) Act, 1972?

(c) The C.R.Z Notification, 1991?

: Nil. As the Site is not falling within the 10 Km radius of any Notified Reserve Forest or located nearby the Coast / Estuaries to attract CRZ Notification any sort of Clearance from the said Statutory Authorities is warranted

22 Whether there is any Government Order/Policy relevant/relating to the site?

: Nil

23 Forest land involved (hectares) : Nil

24 Whether there is any litigation pending against the project and/or land in which the project is propose to be set up?

(a) Name of the Court (b) Case No. (c) Orders/Directions of the Court, if

any and its relevance with the proposed project

: No

25 Cost of the Project : 378.7805 Crores

(II) Activity

1. Construction, Operation or Decommissioning of the Project involving actions,

which will cause physical changes in the locality (topography, land use, changes in

water bodies, etc.):

S.No. Information/Checklist

confirmation

Yes /

No

Details thereof (with approximate

quantities /rates, wherever possible) with

source of information data

1.1

Permanent or temporary change

in land use, land cover or

topography including increase in

intensity of land use (with

respect to local land use plan)

No

The site is classified as Mixed Residential Use Zone as per CMA 2026 and the proposed development is a Commercial / Retail development and is in line with the Land Use with prior permission from CMDA and the same is under process.

1.2 Clearance of existing land,

vegetation and buildings? No

The site is a barren land with few Shrubs and bushes all around which will be cleared during construction. There are few trees present, which shall be retained to the maximum extent possible

APPLICATION FOR EC (FORM-1)

M/s. SARAVANA SELVARATHNAM RETAIL PRIVATE LIMITED, JAMIN PALLAVARAM, KANCHEEPURAM

1.3 Creation of new land uses? Yes

The land is classified as Mixed Residential Use Zone and with the proposed Commercial Activity, the land use will be revised to Commercial Use Zone with prior permission from CMDA

1.4 Pre-construction investigations

e.g. bore houses, soil testing ? Yes

The Soil Investigation and other perquisite activities shall be carried out prior to Construction as the same forms the basis of the Structural Design and Rain Water Harvesting / Management Activities

1.5 Construction works? Yes

Proposed project intends to construct Commercial / Retail Development with Pile / Column foundations, concrete shear wall and finishing work as per the Plan enclosed

1.6 Demolition works? No Not Envisaged

1.7

Temporary sites used for

Construction works or housing

of construction workers?

No

Temporary Shed for about 50 Nos. of Workers will be made within the Site with all the basic amenities will be provided Moreover, there is no bulk storage of goods and raw materials envisaged as Just In Time supply is planned

1.8

Above ground buildings,

structures or earthworks

including linear structures, cut

and fill or excavations

Yes As per Building plan

1.9 Underground works including

mining or tunneling? Yes

The proposed building involves Double

Basement for which there shall be excavation for

the Structural Works as per the Plan enclosed

1.10 Reclamation works? No Not Applicable

1.11 Dredging? No Not Applicable

1.12 Offshore structures? No Not Applicable

1.13 Production and manufacturing

processes? No

Proposed project is a Retail Showroom /

Commercial development and does not involve

production or manufacturing activities

1.14 Facilities for storage of goods or

materials? Yes

Temporary Storage of Construction Materials

shall be made available at site as Just in Time

Supply of materials is envisaged

1.15

Facilities for treatment or

disposal of solid waste or liquid

effluents?

Yes

During Construction Phase, Temporary Mobile

Toilets will be provided with Septic Tank which

will be cleaned periodically through Septic Tank

Cleaners. And the Solid Waste generated will be

disposed through Authorized Waste Handlers /

Recyclers

During Operational Phase, Wastewater from the

Development shall be treated in Sewage

Treatment Plant of 100 KLD capacity. The treated

water will be utilized for toilet flushing,

APPLICATION FOR EC (FORM-1)

M/s. SARAVANA SELVARATHNAM RETAIL PRIVATE LIMITED, JAMIN PALLAVARAM, KANCHEEPURAM

gardening and HVAC within the Facility.

The Solid Waste shall be segregated as Organic

and Inorganic Solid Waste and disposed through

Authorized Waste Handlers / Recyclers as the

Site is well within the Corporation Limits.

1.16 Facilities for long term housing

of operational workers? No

Not Envisaged.

Temporary Settlements with all the necessary

amenities will be made available for the

Constructional Workers at site

Being a Commercial Development, the influx of Visitors and Staffs will also be Temporary and doesn’t require any long term housing facilities

1.17

New road, rail or sea traffic

during construction or

operation?

No

The existing transportation infrastructure will be

made use during construction and operational

phase

1.18

New road, rail, air waterborne or

other transport infrastructure

including new or altered routes

and stations, ports, airports etc?

No The existing transportation infrastructure will be

made use

1.19

Closure or diversion of existing

transport routes or

infrastructure leading to

changes in traffic movements?

No There will not be any closure or diversion of

existing transportation routes

1.20 New or diverted transmission

lines or pipelines? No Not envisaged

1.21

Impoundment, damming,

culverting, realignment or other

changes to the hydrology of

watercourses or aquifers?

No Not envisaged

1.22 Stream crossings? No Not envisaged

1.23 Abstraction or transfers of water

form ground or surface waters? No

The Development being a Commercial Complex

the requirement of Water is mainly towards the

Domestic and Flushing Activities. Most

importantly the site is located within the

CMWSSB Zone and the required Fresh Water will

be supplied through CMWSSB. Also with the STP

being proposed, the recycled Water will be

utilized for Flushing Requirements thereby the

Effective Net Water Consumption within the

Development will be less than the Total Water

Requirement

1.24 Changes in water bodies or the No The required Fresh Water will be sourced

APPLICATION FOR EC (FORM-1)

M/s. SARAVANA SELVARATHNAM RETAIL PRIVATE LIMITED, JAMIN PALLAVARAM, KANCHEEPURAM

land surface affecting drainage

or run-off?

through CMWSSB and there shall be no

abstraction of Ground Water.

Further, Rain Water Harvesting is proposed in

addition to the Ground Water Recharging

through Percolation Pits, which shall have a

positive impact on Ground Water Potential.

Also with the Development is located in the

CMWSSB coverage area with a structured Fresh

Water Supply, Drainage and Storm Water Line in

place. The excess Storm Water from the Facility

will be routed to the external drain

1.25

Transport of personnel or

materials for construction,

operation or decommissioning?

Yes

The existing transportation infrastructure shall be made use of to transport Construction Materials and Personnel to the project site. Being a Commercial Development, the same

modus will be made use of during the

Operational Phase

1.26

Long-term dismantling or

decommissioning or restoration

works?

No Not envisaged

1.27

Ongoing activity during

decommissioning which could

have an impact on the

environment?

No Not envisaged

1.28

Influx of people to an area in

either temporarily or

permanently?

Yes

Being a Commercial Development there will be a

Temporary Influx of workers / Staffs / Visitors

during the Construction and Operational Phase of

the Development.

1.29 Introduction of alien species? No Not envisaged

1.30 Loss of native species or genetic

diversity? No Not envisaged

1.31 Any other actions? Yes

Greenbelt development in an area of about

3120.40 sq.mt (15.08%) shall be developed

within the Site

APPLICATION FOR EC (FORM-1)

M/s. SARAVANA SELVARATHNAM RETAIL PRIVATE LIMITED, JAMIN PALLAVARAM, KANCHEEPURAM

2. Use of Natural resources for construction or operation of the Project (such as land,

water, materials or energy, especially any resources which are non-renewable or

in short supply):

S. No Information/checklist

confirmation

Yes/

No

Details thereof (with approximate quantities

/ rates, wherever possible) with source of

information data

2.1 Land especially undeveloped

or agricultural land (ha) No

The Site is classified as Commercial Use Zone as per CMDA Land Use Map and is in line with the proposed development.

2.2 Water (expected source &

competing users) unit: KLD Yes

Total water requirement - 100 KLD

Total Fresh water requirement – 36.4 KLD

Treated STP water (Flushing) – 63.6 KLD

Source: CMWSSB

2.3 Minerals (MT) No Not envisaged

2.4

Construction material –

Cement, steel, sand, blue metal

and bricks

Yes Building materials as such will be sourced from indigenous supply

2.5 Forests and timber (source –

MT) No

The project shall make use of new wood

wherever application and only Certified wood

will be used where wood is essentially required

2.6

Energy including electricity

and fuels (source, competing

users)

Yes

Electricity: 5.2 MW

Source: Tamil Nadu Generation & Distribution

Corporation (TANGEDCO)

DG Sets: 2 Nos.

2000 KVA X 2 Nos., for the overall facility

2.7

Any other natural resources

(use appropriate standard

units)

No Not envisaged

3. Use, storage, transport, handling or production of substances or materials, which

could be harmful to human health or the environment or raise concerns about

actual or perceived risks to human health:

S. No. Information/Checklist confirmation Yes/

No

Details thereof (with approximate

quantities/ rates, wherever possible)

with source of information data

3.1

Use of substances or materials,

which are hazardous (as per MSIHC

rules) to human health or the

environment (flora, fauna, and

water supplies)

Yes

Handling of diesel will be strictly

restricted to the concrete area to avoid

Soil contamination

Spent oil from DG sets will be collected

periodically, temporarily stored and

handed over to authorized recyclers

APPLICATION FOR EC (FORM-1)

M/s. SARAVANA SELVARATHNAM RETAIL PRIVATE LIMITED, JAMIN PALLAVARAM, KANCHEEPURAM

3.2

Changes in occurrence of disease or

affect disease vectors (e.g. insect or

water borne diseases)

No

No Impact envisaged

3.3 Affect the welfare of people e.g. by

changing living conditions? Yes

Direct and Indirect employment

opportunities during construction and

operation phase of the project

3.4

Vulnerable groups of people who

could be affected by the project e.g.

hospital patients, children, the

elderly etc.,

No

The project in its total effort shall only

aid in bringing positive harmony with the

neighbors

3.5 Any other causes No Not envisaged

4. Production of solid wastes during construction or operation or decommissioning

(MT/month):

S. No. Information/Checklist

confirmation

Yes/

No

Details thereof (with approximate

quantities / rates, wherever possible)

with source of information data

4.1 Spoil, overburden or mine

wastes No Not envisaged

4.2 Municipal waste (domestic and

or commercial wastes) Yes

During the construction and operational

phase of the project, collection and

handling of solid would be done as per

provisions of the municipal Solid Waste

Rules, 2016.

The estimated solid waste generation from

the Retail development : 2.4 MT/day

Organic Waste : 1.74 MT/day

Inorganic Waste : 0.66 MT/day

4.3

Hazardous wastes (as per

Hazardous Waste Management

Rules)

Yes

Spent Oil being the only Hazardous Waste

envisaged at site. The same shall be

collected and periodically disposed

through Authorized Waste Recyclers

4.4 Other industrial process

wastes No

The proposed project being a Commercial

Development with Retail and Multiplexes

there would be no process waste

4.5 Surplus product No Not Envisaged

4.6 Sewage sludge or other sludge

from effluent treatment Yes

Bio sludge of quantity 10 kg/day will be

dewatered and used as manure for

gardening within the premises.

4.7 Construction or demolition Yes Construction waste will be used in road

APPLICATION FOR EC (FORM-1)

M/s. SARAVANA SELVARATHNAM RETAIL PRIVATE LIMITED, JAMIN PALLAVARAM, KANCHEEPURAM

wastes pavements

Wood and paper waste will be disposed

through Authorized Recyclers

Other Construction Waste / Debris will be disposed with prior permission from Local Authority

4.8 Redundant machinery or

equipment No Not Envisaged

4.9 Contaminated soils or other

materials No Not Envisaged

4.10 Agricultural wastes No Not Envisaged

4.11 Other solid wastes No Not Envisaged

5. Release of pollutants or any hazardous, toxic or noxious substances to air (kg/hr):

S. No. Information/Checklist

confirmation

Yes/

No

Details thereof (with approximate

quantities/rates, wherever possible)

with source of information data

5.1

Emissions from combustion of

fossil fuels from stationary or

mobile source

Yes

Emissions from DG Sets. DG sets of

capacity 2000 KVA (2 Nos.) will be used

during power failure for limited use only.

DG sets shall be Installed with with a Stack

Height of 48 mts.

5.2 Emissions from production

processes No

Not Applicable, since the proposed project

is a Commercial Development and no

production is envisaged within the

development

5.3

Emissions from materials

handling including storage or

transport

Yes

Movement of heavy vehicles transporting

construction materials will contribute to

dust emission

The impact will be temporary and

confined locally to the construction site by

adopting dust suppression technique such

as sprinkling of water, barricading the site

etc.,

During Operational Phase the movement

of trucks for transportation of Retail

Products and visitor movements to and fro

the site is envisaged which also contribute

towards Air / Dust Emission, which is

temporary & intermittent. Also adaptation

of internal circulation pattern will avoid

APPLICATION FOR EC (FORM-1)

M/s. SARAVANA SELVARATHNAM RETAIL PRIVATE LIMITED, JAMIN PALLAVARAM, KANCHEEPURAM

traffic congestion which in turn avoids Air

Emission

5.4

Emissions from construction

activities including plant and

equipment

Yes

Apart from dust emissions, there will be

emissions from concrete mixers, dosers,

diesel pumps etc., during construction

Construction equipments will be

periodically overhauled / maintained in

good working condition to reduce

emission

5.5

Dust or odours from handling

of materials including

construction materials, sewage

and waste

Yes

Though the impact will be temporary and

restricted to the construction phase

handling of construction materials like

cement, fine and coarse aggregates will

contribute to dust but confined within the

project area

Mobile Toilets will be provided with

periodical cleaning thereby avoiding

odour problem causing health hazards.

During Operational Phase the sewage is

treated through In-House treatment

methodologies with adequate ventilation

facilities. Hence no dust or odour will

emanate from the proposed project site

Solid Wastes during Construction Phase

will be segregated and disposed through

Authorized Recyclers

During Operation Phase the solid wastes

will be segregated at site and disposed

through Authorized Waste Handlers /

Recyclers

5.6 Emissions from incineration of

waste No Not Envisaged

5.7

Emissions from burning of

waste in open air (e.g. slash

materials, construction debris)

No

As it is a Commercial Development the

Recyclable Wastes such as Packing

Materials will be off higher quantity than

the regular Food Wastes. These shall be

collected, segregated and disposed off

through Authorized Waste Handlers /

Recyclers

5.8 Emissions from any other

sources No Not Envisaged

APPLICATION FOR EC (FORM-1)

M/s. SARAVANA SELVARATHNAM RETAIL PRIVATE LIMITED, JAMIN PALLAVARAM, KANCHEEPURAM

6. Generation of Noise and Vibration and Emissions of Light and Heat:

S.No. Information/Checklist

confirmation

Yes/

No

Details thereof (with approximate

quantities/rates, wherever possible)

with source of information data with

source of information data

6.1

From operation of equipment

e.g. engines, ventilation plant,

crushers

Yes

During Construction Phase

Proper measures will be adopted to

reduce impact of noise generated during

operation of vibrators used in concreting

During Operation Phase

There will be no impact

anticipated on the ambient noise from

the occasionally operated D.G. Sets as

these sets shall be housed in acoustic

enclosures

6.2 From industrial or similar

processes No No manufacturing process involved

6.3 From construction or

demolition Yes

Noise at site will be generated by machineries employed, but will be controlled within the site. No heat or light emissions envisaged. Noise due to construction activities shall be temporary in nature.

6.4 From blasting or piling No

Not Envisaged

6.5 From construction or

operational traffic Yes

Noise will be generated from the

movement of heavy vehicles transporting

construction materials during

construction phase and regular vehicular

traffic intended for commuting staffs and

visitors during operation phase;

however, the level of noise shall be

restricted through efficient internal

traffic control.

The noise levels will be <75 – dBA> due

to operation of Machinery and

equipment during Construction and

Operation phase. Workers will be

provided with protective equipment such

as earmuffs etc.,

APPLICATION FOR EC (FORM-1)

M/s. SARAVANA SELVARATHNAM RETAIL PRIVATE LIMITED, JAMIN PALLAVARAM, KANCHEEPURAM

Also the Operation Traffic leads to Noise

Emission, however the same shall be

mitigated by regulating within the site to

avoid Traffic congestion and the Entry /

Exit will be of Bell Mouthed Shape to ease

out Traffic Flow

6.6 From lighting or cooling systems Yes

No significant emission anticipated

The operation of the HVAC System will

lead to Noise Emission due to the

operation of Motors. However, the same

will be located on the Roof Top and

isolated from the regular Operational

Workers

6.7 From any other sources No Not Envisaged

7. Risks of contamination of land or water from releases of pollutants into the

ground or into sewers, surface waters, groundwater, coastal waters or the sea:

S.No. Information/Checklist

confirmation

Yes/

No

Details thereof (with approximate

quantities/rates, wherever possible)

with source of information data

7.1 From handling, storage, use or

spillage of hazardous materials Yes

Proper handling of HSD required for the

operation of DG sets and spent oil will be

adhered to eliminate contamination of

soil / water

Hazardous wastes generated during

construction phase, such as paints,

solvents and wood preservatives will be

stored in sealed containers, labeled and

disposed–off as required by the

Hazardous Wastes Management and

Handling Act Amendment Rules, 2016.

The spillages/sludge if any will be

collected and supplied to CPCB / TNPCB

approved agencies as per HWMH Rules.

The Hazardous Wastes envisaged during

the Operational Phase of the Project will

be disposed off as directed by the TNPCB

in line with the HWMH Rules, 2016

APPLICATION FOR EC (FORM-1)

M/s. SARAVANA SELVARATHNAM RETAIL PRIVATE LIMITED, JAMIN PALLAVARAM, KANCHEEPURAM

7.2

From discharge of sewage or

other effluents to water or the

land (expected mode and place

of discharge)

Yes

Sewage shall be treated in an In-House

STP of 100 KLD capacity and will be

reused for flushing, gardening and HVAC

within the premises maintaining Zero

Liquid Discharge

Sludge @ 10 kg/day will be used in

gardening as a manure

7.3

By deposition of pollutants

emitted to air into the land or

into water

Yes

Emissions from DG Sets will be minimal

and would be let out into the atmosphere

through Stacks of adequate height

thereby avoiding increase in Pollutants at

Ground Level Concentration.

7.4 From any other sources No Not envisaged

7.5

Is there a risk of long term build

up of pollutants in the

environment from these

sources?

No

There would be no build up of pollutants

in the environment since they are treated

before being let out in the environment

8. Risk of accidents during construction or operation of the Project, which could

affect human health or the environment:

S. No. Information/Checklist

confirmation

Yes/

No

Details thereof (with approximate

quantities/rates, wherever possible)

with source of information data

8.1

From explosions, spillages,

fires etc from storage,

handling, use or production of

hazardous substances

Yes

Adequate safety measures to mitigate all

risks anticipated out of fire in diesel will

be taken care of by installing suitable fire

fighting system in place

8.2 From any other causes No Not envisaged

8.3

Could the project be affected

by natural disasters causing

environmental damage (e.g.

floods, earthquakes,

landslides, cloudburst etc)

Yes

The structural design shall conform to

certified IS code 875 and IS-1893-2002

for Seismic Zone 3

The project falls under seismic zone – III

as per IS 1893 (part-1): 2002. The site is

demarcated by boundary walls and

structured Storm Water Drain will

ensure that water is not stagnated /

flooded within the site due to rain during

operational phase. Also the site is not

prone to landslide. However due to

heavy rain as envisaged during 2015, the

area envisages Flood. However, with

APPLICATION FOR EC (FORM-1)

M/s. SARAVANA SELVARATHNAM RETAIL PRIVATE LIMITED, JAMIN PALLAVARAM, KANCHEEPURAM

proper Storm Water Management, the

same enables to drain the stagnated

water at the earliest.

Hence, no risk due to natural hazards is

envisaged

9. Factors which should be considered (such as consequential development) which

could lead to environmental effects or the potential for cumulative impacts with

other existing or planned activities in the locality:

S. No.

Information/Checklist

confirmation

Yes/

No

Details thereof (with approximate

quantities/rates, wherever possible)

with source of information data

9.1

Lead to development of

supporting facilities, ancillary

development or development

stimulated by the project which

could have impact on the

environment e.g.,

• Supporting infrastructure

(roads, power supply, waste

or wastewater treatment,

etc.)

No

Though there will be marginal increase

in terms of traffic, power supply and

solid wastes disposal however the

existing infrastructure would suffice the

requirement.

Waste water will be fully treated in an

In-House STP and be reused within the

facility

The project is located within the City

limits, with all the basic amenities been

made available

• Housing development No

Lead to an Organized Infrastructure

Development leading to housing

developments in and around the site

area

The Development is taken up in the

designated Mixed Residential Use Zone

with many Commercial Developments

around. The development shall lead to

Housing Developments nearby in

addition to the existing facilities as the

site is within the City Limits with all

infrastructures in place

APPLICATION FOR EC (FORM-1)

M/s. SARAVANA SELVARATHNAM RETAIL PRIVATE LIMITED, JAMIN PALLAVARAM, KANCHEEPURAM

• Extractive industries No Not Envisaged

• Supply industries No Supply Industries will be supported

directly/indirectly.

• Others No Not Envisaged

9.2

Lead to after-use of the site,

which could have an impact on

the environment

No Nil

9.3 Set a precedent for later

developments No

As such the Development is taken up in

the designated residential Area within

the Chennai City

9.4

Have cumulative effects due to

proximity to other existing or

planned projects with similar

effects

No Not envisaged.

(III) Environmental Sensitivity

S. No. Areas Name/

Identity

Aerial distance (within 15 km)

Proposed project location

boundary

1

Areas protected under

international conventions,

national or local legislation for

their ecological, landscape,

cultural or other related value

Guindy

National Park Aerial Distance – 8.50 Km

Pallikaranai

Marsh Aerial Distance – 6.61 Km

Arignar Anna

Zoological park Aerial Distance – 10.35 Km

Nanmangalam

reserved forest Aerial Distance – 3.13 Km

2

Areas which are important or

sensitive for ecological

reasons - Wetlands,

watercourses or other water

bodies, coastal zone,

biospheres, mountains, forests

Guindy

National Park Aerial Distance – 8.50 Km

Pallikaranai

Marsh Aerial Distance – 6.61 Km

APPLICATION FOR EC (FORM-1)

M/s. SARAVANA SELVARATHNAM RETAIL PRIVATE LIMITED, JAMIN PALLAVARAM, KANCHEEPURAM

3

Areas used by protected,

important or sensitive species

of flora or fauna for breeding,

nesting, foraging, resting, over

wintering, migration

Pallikaranai

Marsh Aerial Distance – 6.61 Km

4 Inland, coastal, marine or

underground waters

Adyar River Aerial Distance – 3.59 km

Bay of Bengal Aerial Distance – 10.90 Km

5 State, National boundaries - Not Envisaged

6

Routes or facilities used by the

public for access to recreation

or other tourist, pilgrim areas

SH 48 –

Chennai Trichy

Highway

Aerial Distance – 1.47 Km

7 Defence Installation

Indian Air

Force -

Tambaram

Aerial Distance – 5.50 Km

8 Densely populated area Chennai Within Chennai City

9

Areas occupied by sensitive

man-made land uses

(hospitals, schools, places of

worship, community facilities)

PCMC Hospital Aerial Distance – 275m

Vels university Aerial Distance – 750 m

10

Areas containing important,

high quality or scarce

resources ground water

resources, surface resources,

forestry, agriculture, fisheries,

tourism, minerals)

Adyar River Aerial Distance – 3.59 m

Guindy

National Park Aerial Distance – 8.50 Km

Pallikaranai

Marsh Aerial Distance – 6.61 Km

Nanmangalam

Reserve Forest Aerial Distance – 3.13 Km

11

Areas already subjected to

pollution or environmental

damage. (those where existing

legal environmental standards

are exceeded)

- Not Envisaged

12

Areas susceptible to natural

hazard which could cause the

project to present

environmental problems

(earthquakes, subsidence,

landslides, erosion, flooding

for extreme or adverse

climatic conditions)

-

Earthquake, the area falls under

Seismic Zone 3.

The structural design shall

conforms to IS code 875 and IS –

1893-2002

APPLICATION FOR EC (FORM-1)

M/s. SARAVANA SELVARATHNAM RETAIL PRIVATE LIMITED, JAMIN PALLAVARAM, KANCHEEPURAM

(IV) Proposed Terms of Reference for EIA Studies

The proposed project involves construction of Commercial Complex Building, with Builtup Area of 89,907.02 Sq.m which comes under Item “8(a)” of Schedule of “EIA Notification 2006” Dated: 14.09.2006 and Category B. Hence it will not require any scoping exercise or EIA Report. So no Terms of Reference [ToR] is proposed for this Project.

I hereby give undertaking that the data and information given in the application and enclosures are true to the best of my knowledge and belief and I am aware that if any part of the data and information submitted is found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost.

Date : Signature of the Applicant

Place : Chennai Mr. S.R. Saravana Arul

Managing Director / Authorized Signatory

NOTE:

1. The project involving clearance under Coastal Regulation Zone Notification, 1991

shall submit with the application a C.R.Z. map duly demarcated by one of the

authorized agencies, showing the project activities, w.r.t. C.R.Z (at the stage of

TOR) and the recommendations of the State Coastal Zone Management Authority

(at the stage of EC). Simultaneous action shall also be taken to obtain the requisite

clearance under the provisions of the C.R.Z Notification, 1991 for the activities to

be located in the CRZ.

NOT APPLICABLE

2. The projects to be located within 10 km of the National Parks, Sanctuaries,

Biosphere Reserve, Migratory Corridors of wild Animals, the project proponent

small submit the duly authenticated by Chief Wildlife Warden showing there

features vis-à-vis the project location and the recommendations or comments of

the Chief Wildlife Warden thereon (at the stage of EC).

NOT APPLICABLE

3. All correspondence with the Ministry of Environment & Forests including

submission of application for TOR/Environmental Clearance, subsequent

clarifications, as may be required from time to time, participation in the EAC

Meeting on behalf of the project proponent shall be made by the authorized

signatory only. The authorized signatory should also submit a document in

support of his claim of being an authorized signatory for the specific project.

ENCLOSED