UPDATED FORM I - Environmental Clearance

39
PASHAMYLARAM COMMON INFRASTRUCTURE PVT. LTD. SY. NO. 236 (Part), 237 (Part) AND 242 (Part), PHASE II, IDA, PASHAMYLARAM, PATANCHERU MANDAL, MEDAK DISTRICT, TELANGANA UPDATED FORM I Project No. 03162102 March 2016 Pashamylaram Common Infrastructure Pvt. Ltd., TSIIC Admn. Building, Phase I,IDA, Pashamailaram (V), Patancheru (M), Medak (Dist.)502 307 Phone: +91 08455226590/244489, 9393117750 Email ID: [email protected] STUDIES AND DOCUMENTATION BY TEAM Labs and Consultants B115117 & 509, Annapurna Block, Aditya Enclave, Ameerpet, Hyderabad500 038. Phone: 04023748 555/23748616, Telefax: 04023748666 SUBMITTED TO STATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY, TELANGANA, GOVERNMENT OF INDIA

Transcript of UPDATED FORM I - Environmental Clearance

PASHAMYLARAM COMMON INFRASTRUCTURE PVT. LTD. SY. NO. 236 (Part), 237 (Part) AND 242 (Part),  

PHASE II, IDA, PASHAMYLARAM, PATANCHERU MANDAL,  MEDAK DISTRICT, TELANGANA 

 

      

UPDATED FORM I 

  

   

 

 

  

    

Project No. 0316‐21‐02March 2016 

 

Pashamylaram Common Infrastructure Pvt. Ltd.,  TSIIC Admn. Building, Phase I,IDA, Pashamailaram (V), Patancheru (M), Medak (Dist.)‐ 502 307  Phone: +91 08455‐226590/244489, 9393117750 E‐mail ID: [email protected] 

STUDIES AND DOCUMENTATION BY TEAM Labs and Consultants B‐115‐117 & 509, Annapurna Block,  Aditya Enclave, Ameerpet,  Hyderabad‐500 038. Phone: 040‐23748 555/23748616, Telefax: 040‐23748666      

SUBMITTED TO STATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY, 

TELANGANA, GOVERNMENT OF INDIA 

Pashamylaram Common Infrastructure Pvt. Ltd.  

Form I        Page 1 

APPENDIX – I (See Paragraph – 6) 

FORM I I)  Basic Information 

S.No.  Item   Details  1  Name of the Project/s  Pashamylaram Common Infrastructure Pvt. Ltd. 2  S. No in the Schedule 7(h) –Category B & 1(d) –Category B 3  Proposed capacity/area/length/tonnage 

to be handled/command area/lease area/number of wells to be drilled 

Area:5 Acres The  present  proposal  is  for  Amendment  of  our  existing Environmental Clearance. Order No. SEIAA/TS/MDK‐82/2016 dated: 03.10.2016 

Amendment  S.No

Description  As Mentioned  To be Corrected 

1  Condition No. (ii)  of  A. Specific Condition 

Common  Effluent Conveyance  System should  be constructed  / Commissioned /maintained  by  the CETP Operator.   Separate  pipelines are  to  be  laid  for transport of  influents from  the  member industries  to  CETP and  to  convey  the treated  effluents  to the  member industries  for recycling.  

Common  Effluent Conveyance  System should  be  operated by CETP Operator.  

The  effluents  from the  individual  units, will  be  transferred after  primary treatment  within  the individual  units,  by dedicated GPS tagged tank trucks.  

The  treated wastewater  will  be sent  to  the contributing individual  units  by dedicated  tank  trucks for reuse. 

Capacity: 480 KLD and 2.5MW CPP. Cost of the project: 30.0 Crores 

4  New/Expansion/Modernization  New 5  Existing Capacity/Area etc.  Not Applicable 6  Category of Project i.e 'A' or 'B'  “A” 7  Does  it  attract  the  general  condition?  If 

yes, please specify Yes. The Unit is Located in Notified Industrial Estate / Area. Critically Polluted Area of Pattancheru and Bollaram are located at a distance of 5.5 KM’s from the Site. 

8  Does  it  attract  the  Specific  condition?  If yes, please specify. 

No 

9  Location    Plot/Survey/Khasra No.  Phase II, IDA   Village  Phashamylaram   Tehsil  Patancheru Mandal   District  Sangareddy District   State  Telangana

Pashamylaram Common Infrastructure Pvt. Ltd.  

Form I        Page 2 

10  Nearest  railway  station/airport  along with distance in kms. 

Nagulapalli Railway Station – 9.8Km – SE, Shamshabad Airport – 42Km ‐ SE 

11  Nearest Town, City, District Headquarters along with distance in kms. 

Patancheru – 9.3Km ‐ SE 

12  Village  Panchayats,  Zilla  Parishad, Municipal  Corporation,  Local  body (complete postal address with telephone nos. to be given) 

Phashamylaram  

13  Name of the Applicant  M.Narasimha Reddy 14  Registered Address   15  Address for Correspondence:  TSIIC Admn. Building, Phase – I, IDA, Pashamylaram, 

Sangareddy District.   Name  M.Narasimha Reddy   Designation(Owner/Partner/CEO)  Director & CEO   Address  TSIIC Admn. Building, Phase – I, IDA, Pashamylaram, 

Sangareddy District.   Pin Code  502 307   E‐mail  [email protected]   Telephone Number  9393117750   Fax No.   

16  Details  of  alternative  Sites  examined,  if any.  Location  of  these  sites  should  be shown on a topo sheet. 

‐NA‐ 

17  Interlinked Projects  ‐NA‐ 18  Whether  separate  application  of 

interlinked project has been submitted?  No 

19  If yes, date of submission    20  If no, reason    21  Whether the proposal involves 

approval/clearance under: if yes, details of the same and their status to be given.     (a) The Forest (Conservation) Act, 1980?      (b) The Wildlife (Protection) Act, 1972?        (c) The C.R.Z Notification, 1991? 

‐NA‐ 

22  Whether  there  is  any  Government Order/Policy  relevant/relating  to  the site? 

 No 

23  Forest land involved (hectares)  No24  Whether there is any location pending 

against the project and /or land in which the project is propose to be set up?              (a) Name of the Court                                       (b) Case No                                                         (c) Orders/directions of the Court, if any and its relevance with the proposed project. 

 No 

 

Pashamylaram Common Infrastructure Pvt. Ltd.  

Form I        Page 3 

(II)  Activity  1.  Construction,  operation  or  decommissioning  of  the  Project  involving  actions,  which  will  cause  physical changes in the locality (topography, land use, changes in water bodies, etc.) S.No.  Information/Checklist confirmation   Yes/No  Details thereof (with approximate quantities 

/rates, wherever possible) with source of information data 

1.1  Permanent or temporary change in land use, land cover or topography including increase in    intensity of land use (with respect to local land use plan)   

NO  The proposal  is for a green field project. The  land area used  for  the proposed plant  is 5  acres.  The land  is  plain  and  does  not  involve  much  of leveling/excavation.   

1.2  Clearance of existing land, vegetation and buildings? 

NO  The  land  area  is  plain  and  is  not  used  for  any agricultural activity 

1.3  Creation of new land uses?  NO   1.4  Pre‐construction investigations e.g. bore 

houses, soil testing? YES  Soil  test  done  and  soil  load  bearing  capacity 

established. 1.5  Construction works? 

 NO  Construction  activity  involves  plant  construction, 

erection only.1.6  Demolition works?  NO   

1.7  Temporary sites used for construction works or housing of construction workers? 

NO  Construction  labor  from  local  villages  shall  be employed. 

1.8  Above ground buildings, structures or earthworks including linear structures, cut and fill or excavations 

YES  Office buildings, Storage  facilities for raw effluent and  treated  effluent  shall  be  constructed.      No major cut and fill or excavation is anticipated. 

1.9  Underground works including mining or     tunneling? 

NO   

1.10  Reclamation works?  NO   1.11  Dredging?   NO   1.12  Offshore structures?  NO   1.13  Production and manufacturing 

processes? NA   

1.14  Facilities for storage of goods or materials? 

NO   

1.15  Facilities for treatment or disposal of solid waste or liquid effluents? 

YES  Solid  waste  shall  be  disposed  to  end users/recyclers  or  sent  to  incineration.  Effluent generated from the plant are treated and reused. Details presented in Annexures   

1.16  Facilities for long term housing of operational workers? 

NO  Local people shall be employed. 

1.17   New road, rail or sea traffic during construction or operation? 

YES  Construction materials shall be transported to the site.   The traffic density of the existing connecting road is negligible. 

1.18   New road, rail, air waterborne or other transport infrastructure including new or altered routes and stations, ports, 

NO   

Pashamylaram Common Infrastructure Pvt. Ltd.  

Form I        Page 4 

airports etc? 1.19   Closure or diversion of existing transport 

routes or infrastructure leading to changes in traffic movements? 

NO   

1.20  New or diverted transmission lines or pipelines? 

NO   

1.21  Impoundment, damming, culverting, realignment or other changes to the hydrology   of watercourses or aquifers? 

NO   

1.22  Stream crossings?  NO   1.23  Abstraction or transfers of water form 

ground or surface waters? YES  Total water required shall be 250.9 KLD out of 

which 218.9 KLD shall be drawn from TSIIC and the balance shall be recycled water. 

1.24  Changes in water bodies or the land surface affecting drainage or run‐off? 

NO   

1.25  Transport of personnel or materials for construction, operation or decommissioning? 

YES  The  construction  material  shall  be  drawn  from local  sources  within  10  –  15  km.    There  is  no transport  of  personnel,  as  the  construction workers shall be drawn from local villages.

1.26  Long‐term dismantling or decommissioning or restoration works? 

NO   

1.27  Ongoing activity during decommissioning which could have an impact on the environment? 

NO   

1.28  Influx of people to an area in either temporarily or permanently? 

YES  The  proposed  project  shall  increase  the employment  potential  and  hence  may  lead  to migration to surrounding villages. 

1.29  Introduction of alien species?  NO   1.30  Loss of native species or genetic 

diversity? NO  There are no major losses of tree/shrub species. 

1.31  Any other actions?  NO    

Pashamylaram Common Infrastructure Pvt. Ltd.  

Form I        Page 5 

2.   Use  of Natural  resources  for  construction  or  operation  of  the  Project  (such  as  land, water, materials  or energy, especially any resources which are non‐renewable or in short supply): S.No.  Information/checklist confirmation   Yes/No  Details thereof (with approximate quantities 

/rates, wherever possible) with source of information data 

2.1  Land especially undeveloped or agricultural land (ha) 

YES  5  acres.  Located  Phase  II  IDA,  Phashamylaram, Sangareddy District, Telangana. 

2.2   Water (expected source & competing users) unit: KLD 

YES  Total  water  required  shall  be  250.9  KLD  which shall  be  drawn  from  TSIIC.  (Water  Balance Enclosed in Annexure) 

2.3  Minerals (MT)  NA   2.4  Construction material – stone, 

aggregates, sand / soil (expected source – MT) 

YES Shall be sourced from the local villages. 

2.5  Forests and timber (source – MT)  NO   2.6  Energy including electricity and fuels 

(source, competing users) Unit: fuel (MT), energy (MW) 

YES  The  required  energy  shall  be  drawn  from TSTRANSCO.   Backup DG sets of 2 x 500 KVA shall be provided to cater to energy requirement during load shut downs.   The other energy source is Coal fired boiler of 25TPH. The required quantity of fuel is 18.5TPD. 

2.7  Any other natural resources (use appropriate standard units) 

NA   

 

Pashamylaram Common Infrastructure Pvt. Ltd.  

Form I        Page 6 

3.   Use,  storage,  transport, handling or production of  substances       or materials, which  could be harmful  to human health or the environment or raise concerns about   actual or perceived risks to human health. S.No.  Information/Checklist confirmation 

Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data 

3.1  Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and  water supplies) 

No 

 

3.2  Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases). 

NO  

3.3  Affect the welfare of people e.g. by changing living conditions?  YES 

Shall increase the employment potential for locals and affect the living conditions for betterment. 

3.4  Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc.,  NO 

No  sensitive  receptors  are  present  in  the immediate  vicinity  of  the  site.  The  project  shall not  have  any  significant  impact  on  vulnerable groups of people.  

3.5  Any other causes  NO      

4. Production of solid wastes during construction or operation or decommissioning (MT/month) S.No.  Information/Checklist confirmation  Yes/No  Details thereof (with approximate 

quantities/rates, wherever possible) with source of information data 

4.1  Spoil, overburden or mine wastes  NO   4.2  Municipal waste (domestic and or 

commercial        wastes) NO  Wastes  from  canteen,  other  commercial  wastes 

like  paper,  empty  containers  etc.      The  canteen wastes  and  commercial  wastes  shall  be  in  the range of 15 kg/day 

4.3  Hazardous wastes (as per Hazardous Waste  Management Rules) 

YES  The  quantity  of  hazardous  wastes  generated during  construction  contains  waste  oils  and batteries from DG set.   The quantity of hazardous waste generated during operation  contain  stripper  distillate,  ATFD  salts and ETP sludge etc. enclosed in Annexure 

4.4  Other industrial process wastes  YES  Enclosed at Annexure 

4.5  Surplus product  NO   4.6  Sewage sludge or other sludge from 

effluent  treatment YES  Sludge from Effluent treatment plant and Salts 

from MEE & ATFD shall be sent to TSDF. 

4.7  Construction or demolition wastes  NO  Construction activity involves creation of treatment facilities, Utility and Co‐Generation Power Plant.   

Pashamylaram Common Infrastructure Pvt. Ltd.  

Form I        Page 7 

4.8  Redundant machinery or equipment  NO   

4.9  Contaminated soils or other materials  NO   

4.10  Agricultural wastes  NO   

4.11  Other solid wastes  NO  Enclosed at Annexure 

 5. Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr) S.No.  Information/Checklist confirmation  Yes/No  Details thereof (with approximate 

quantities/rates, wherever possible) with source of information data 

5.1  Emissions from combustion of fossil fuels from stationary or mobile sources 

YES  Coal Shall be used as fuel. Quantity of fuel and emissions details are enclosed in Annexure 

5.2  Emissions from production processes  NO   5.3  Emissions from materials handling 

including storage or transport NO  Material transfer takes place in closed pipeline 

systems. 5.4  Emissions from construction activities 

including plant and equipment YES  Dust  may  rise  during  transport  of  material  and 

construction activity.   The dust emissions shall be mitigated by water  spraying on  the  roads within the premises.  

5.5  Dust or odors from handling of materials including construction materials, sewage and  waste 

NO   

5.6  Emissions from incineration of waste  NO5.7  Emissions from burning of waste in open 

air (e.g. slash materials, construction debris) 

NO   

5.8  Emissions from any other sources  NO    

Pashamylaram Common Infrastructure Pvt. Ltd.  

Form I        Page 8 

6. Generation of Noise and Vibration, and Emissions of Light and Heat: S.No.  Information/Checklist confirmation Yes/No  Details thereof (with approximate quantities/rates, 

wherever possible) with source of information data with source of information data 

6.1  From operation of equipment e.g. engines, ventilation plant, crushers 

YES  Material transport and construction equipment shall be source  of  noise,  while  transfer  pumps,  vacuum systems,  DG  sets  are  the  sources  of  noise  during operation.   

6.2  From industrial or similar processes  YES  From DG sets, and controlled by providing Acoustic Enclosures. 

6.3  From construction or demolition  YES  Noise during construction shall be due to construction equipment and emergency DG sets.    

6.4  From blasting or piling  NO   

6.5  From construction or operational traffic 

NO  The increased traffic shall not have any significant impact.  

6.6  From lighting or cooling systems  NO   

6.7  From any other sources  NO   

  

 7.Risks of contamination of land or water from releases of    pollutants into the ground or into sewers,   surface     waters, groundwater, coastal waters or the sea: S.No.  Information/Checklist confirmation Yes/No  Details thereof (with approximate quantities/rates, 

wherever possible) with source of information data 7.1  From handling, storage, use or 

spillage of hazardous materials NO  All the hazardous materials will be stored in MS drums, 

in  a  covered  shed  and    no  contamination  of  soil  is expected

7.2  From discharge of sewage or other effluents to water or the land (expected mode and place of discharge) 

NO  All  the wastes  from  domestic  operations  are  sent  to biological treatment system. 

7.3  By deposition of pollutants emitted to air into the land or into water 

NO  Air  Pollutants  generated  are  let  out  into  atmosphere after meeting the prescribed standards. 

7.4  From any other sources  NO   7.5  Is there a risk of long term build up 

of pollutants in environment from these     sources? 

NO   

 

Pashamylaram Common Infrastructure Pvt. Ltd.  

Form I        Page 9 

8.Risk of  accidents during  construction or operation of  the Project, which  could  affect human health or  the environment S.No.  Information/Checklist confirmation  Yes/No  Details thereof (with approximate 

quantities/rates, wherever possible) with source of information data 

8.1  From explosions, spillages, fires etc from storage, handling, use or production of hazardous substances 

YES  All  Inbuilt  Safety  precautions  will  be adopted  and  there  will  not  be  any damage  to  environment  or  human health 

8.2  From any other causes  NA   

8.3  Could the project be affected by natural disasters causing environmental damage (e.g?     Floods, earthquakes, landslides, cloudburst etc)? 

NO   

  

9.Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts  with  other existing or planned activities in the locality S. No.  Information/Checklist confirmation  Yes/No  Details thereof (with approximate 

quantities/rates, wherever possible) with source of information data  

9.1  Lead to development of supporting.   facilities, ancillary development or development stimulated by the project which could have impact on the environment e.g.: • Supporting infrastructure (roads, power supply, waste or waste water treatment, etc.) •      housing development •      extractive industries •      supply industries •      other 

YES  The  project  shall  enhance  the  socio economic  status  of  the  area  by increasing  the  demand  for  housing, improving  the  employment.  There  are no  major  support  industries  required for this plant.  

9.2  Lead to after‐use of the site, which could haven impact on the environment 

NO   

9.3  Set a precedent for later developments  NO   

9.4  Have cumulative effects due to proximity to other existing or planned projects with similar    effects 

NO  The  baseline  environmental  status  of the  surrounding  areas  is  within  the prescribed  limits as observed  from the primary data. 

        

Pashamylaram Common Infrastructure Pvt. Ltd.  

Form I        Page 10 

(III)  Environmental Sensitivity S.No.  Areas  Name/ 

Identity Aerial distance (within 15 km.) Proposed project location boundary 

1   Areas protected under international conventions,   national or local legislation for their ecological,    landscape, cultural or other related value

NA   

2  Areas which are important or sensitive for ecological reasons ‐ Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests 

YES  Isnapur Cheru– North– 0.3 Km,  Kotta Cheru – Northwest – 1.97 Km  Pedda Cheru – North – 3.6 Km Lakdaram Cheru – North ‐  4.9 Km Nakkavagu – Northeast – 5.8 Km 

3  Areas used by protected, important or sensitive   species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration 

NA     

4   Inland, coastal, marine or underground waters  NO   5   State, National boundaries  NO   6   Routes or facilities used by the public for access to 

recreation or other tourist, pilgrim areas NO   

7   Defense installations  NO   8   Densely populated or built‐up area  YES  Phashamylaram is at a distance of 2.54 

Km in Southeast. 

9   Areas occupied by sensitive man‐made land uses    (hospitals, schools, places of worship, community facilities) 

NA  2.8 Km from the site 

10  Areas containing important, high quality or scarce resources (ground water resources, surface resources, forestry, agriculture, fisheries, tourism, minerals) 

NO   

11  Areas already subjected to pollution or      environmental damage. (those where existing legal environmental standards     are exceeded) 

NO   

12   Areas susceptible to natural hazard which could      cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) 

NO       

      

    

Pashamylaram Common Infrastructure Pvt. Ltd.  

Form I        Page 11 

 (IV) Proposed Terms of Reference for EIA studies      Scope of Work of EIA “...The EIA shall cover the following: Description of the proposed project: The  first  task:”  Description  of  the  proposed  project”  forms  a  vital  component  of  the  Environmental  Impact Assessment (EIA) as it provides the basis for evaluating the likely causes of Environmental Impacts.     

Existing Environment and Baseline Conditions: The baseline assessment will be carried out to identify potentially sensitive and critical areas that may be affected by  the project  in  an area of 10  km  surrounding  the project  location.   The  critical  and  sensitive  targets  shall be plotted  on  land  use map  of  project  impact  area.  The  existing  environment  and  baseline  conditions  should  be established from:‐ Analysis of existing information published and secondary data. ‐Consultation with relevant statutory authorities, and Field visits for supplementation of missing gaps. 

The key subject areas which the EIA shall address include Ecology and Nature conservation, Air quality, surface and water quality in project impact area, soil quality, cultural heritage, landscape, land use, noise quality, etc.  Natural habitats  like national parks, wildlife reserves, sanctuaries, sacred grove, protected areas, forests, wetlands, major rivers and waterways if any, shall also be identified and marked. 

Assessment of Environmental Impacts: Based upon the results from the review of existing information, field visits, site data collection and consultation, for each  component  of  environment  (physical,  biological  and  socio  economic)  the  positive,  negative,  direct  and indirect, temporary and permanent impacts will be evaluated along with an indication of the degree of impact, i.e., whether the impact is significant, moderate, minor or negligible.   The degree of impact shall also be quantified by using state of the art air quality impact prediction models based on ISCST3 algorithms. 

Environment Management Plan And Mitigation Plan: For each  significant negative  impact  identified,  specialist  shall work  closely with  the engineering  team/technical consultants  to  suggest practicable measures  to  avoid or mitigate  the  impact.    The mitigation of  environmental impacts will be by three mechanisms. =>Introduction of mitigation features through the engineering practices. =>Implementation of environmental controls during construction and operation. =>Legislative control involving compliance with Indian environmental laws. The  Environmental  management  plan  shall  include  an  estimate  of  capital  and  recurring  costs  of  mitigation measures and will identify the institutional framework for implementation. 

Monitoring Plan: Having  identified the significant environmental  impact that  is  likely to arise as a result of the project, the project team shall specify what monitoring is required during the various phases of the project cycle.  The monitoring plan will identify parameters and frequency of monitoring and responsible organization. 

 

Pashamylaram Common Infrastructure Pvt. Ltd.  

Form I        Page 12 

I hereby give the undertaking that data and  information given  in the application and enclosures are true to the best of my knowledge and belief and I am aware that if any part of the data and information submitted is found to be false or misleading at any stage, the project will be rejected and clearance given,  if any to the project will be revoked at our risk and cost. Date:   Place: 

Signature of the applicant With Name and Full Address 

 (Project Proponent/Authorized Signatory)  

 M.Narasimha Reddy 

Director & CEO TSIIC Admn. Building, Phase – I, IDA,  Pashamylaram, Sangareddy District. 

PASHAMYLARAM COMMON INFRASTRUCTURE PVT. LTD. SY. NO. 236 (Part), 237 (Part) AND 242 (Part),  

PHASE II, IDA, PASHAMYLARAM, PATANCHERU MANDAL,  MEDAK DISTRICT, TELANGANA 

 

        

 ANNEXURES 

      

   

    

Project No. 0316‐21‐02March 2016 

 

Pashamylaram Common Infrastructure Pvt. Ltd.,  TSIIC Admn. Building, Phase I,IDA, Pashamailaram (V), Patancheru (M), Medak (Dist.)‐ 502 307  Phone: +91 08455‐226590/244489, 9393117750 E‐mail ID: [email protected] 

STUDIES AND DOCUMENTATION BY TEAM Labs and Consultants B‐115‐117 & 509, Annapurna Block,  Aditya Enclave, Ameerpet,  Hyderabad‐500 038. Phone: 040‐23748 555/23748616, Telefax: 040‐23748666      

 

SUBMITTED TO STATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY, 

TELANGANA, GOVERNMENT OF INDIA 

Pashamylaram Common Infrastructure Pvt. Ltd. TOR Annexures

Team Labs and consultants 1‐1

ANNEXURE – I

Plant Location & Layout

The project site is located at Sy. No. 23 (Part), 237 (Part) and 242 (Part), Phase II, IDA,

Pashamylaram, Patancheru Mandal, Medak District, Telangana. The site is situated at 170

10’48.95” (N) latitude and 780 32’ 33.85” (E) longitude. Site is surrounded by internal IDA roads

in all directions except west, open plot in west direction. The nearest village from the site is

Pashamylaram located at a distance of 0.9 Km to the industrial estate premises. The main

approach road is NH9 (Hyderabad – Mumbai) passing at a distance of 2.3 km in north

direction. The nearest railway station is Lingampally at a distance of 17.3 km in southeast

direction and Shamshabad airport is located at a distance of 41 km in southeast direction. The

distance from Isnapur pedda cheru is 0.5 km in east direction, Nakkavagu stream is at a

distance of 6.2 km in northeast direction, flowing from north to south, Kotta cheruvu is at a

distance of 2 km in northwest direction, Lakdaram cheruvu is at a distance of 4.1 km in north

direction and Pedda cheruvu is at a distance of 4 km in northeast direction. There are no

Reserve forests, National parks, sanctuaries and ecologically sensitive areas within the impact

area of 10 km. The location map and site layout is as shown in Fig 1.1 and Fig 1.2.

Pashamylaram Common Infrastructure Pvt. Ltd. TOR Annexures

Team Labs and consultants 1‐2

Fig 1.1 Location of M/s. Pashamylaram Common Infrastructure Pvt. Ltd.,

Pashamylaram Common Infrastructure Pvt. Ltd. TOR Annexures

Team Labs and consultants 1‐3

Fig 1.2 Plant Layout of M/s. Pashamylaram Common Infrastructure Pvt. Ltd.

SE

WN

50 KL 50 KL

50 KL 50 KL

50 KL 50 KL

50 KL 50 KL

50 KL

50 KL 50 KL

50 KL

50 KL

50 KL

50 KL

50 KL

Pashamylaram Common Infrastructure Pvt. Ltd. Environmental Impact Assessment Report  

A-4 Team Labs and Consultants  

ANNEXURE – II

The technoeconomic feasibility considers the quantity of effluents generated in the member

units of Pashamylaram IDA and proposes to establish a Common Effluent Treatment Plant of

capacity 480 KLD and 2.5MW Co-generation power plant in an area of 5 acres located at Sy.

No. 23 (Part), 237 (Part) and 242 (Part), Phase II IDA, Pashamylaram, Patancheru Mandal, Medak

District, Telangana. The estimated cost of the Project is Rs. 30 Crores. The co-operative

consists of 23 members. List of member units and quantity of effluent from member units is

presented in Table 1.1.

Table 1.1 List of Member Units and Quantity of Effluent S.No Name of the Industry Type of products Location of the Plant Quantity

(KLD) 1 Sri Chaitanya Chlorides Pvt

Ltd API Intermediates Plot no:30-33, Phase

II,IDA, Phashamylaram 20

2 Lakshmi Sars Chem Tech Pvt Ltd

API Intermediates Plot no:276 c, Phase III,IDA, Phashamylaram

15

3 Arene Life Sciences Limited Bulk Drugs (API) and Intermediates

Plot no:48-50, Phase II,IDA, Phashamylaram

15

4 Satyadeva Pharmaceuticals Pvt Ltd

API Intermediates Plot no: 19,20,28 Phase II,IDA, Phashamylaram

15

5 Viraprakasha organics Pvt Ltd,Unit -II

API Intermediates Plot no:30-33, Phase I,IDA, Phashamylaram

40

6 Ogene Sysyems Bulk Drugs (API) and Intermediates

Plot no:218 and 219, Phase II,IDA, Phashamylaram

15

7 Piyanshu Chemicals API Intermediates Plot no:200 and 201, Phase II,IDA, Phashamylaram

12

8 Usha vital Care Pvt Ltd API Intermediates Plot no:190, Phase II,IDA, Phashamylaram

10

9 Venkar chemicals Pvt Ltd API Intermediates Plot no:64-67, Phase II,IDA, Phashamylaram

28.5

10 R.R Labs API Intermediates Plot no: 206, Phase II,IDA, Phashamylaram

10

11 Laasya Laboratories API Intermediates Plot no:24, Phase II,IDA, Phashamylaram

10

12 Nitya Labs API Intermediates Plot no:272 & 280 Phase II,IDA, Phashamylaram

30

13 Salubrious Laboratories pvt Ltd

API Intermediates Plot no:118 and 119, Phase II,IDA, Phashamylaram

8

14 Micro molecules(P)Ltd API Intermediates Phase II,IDA, Phashamylaram

5

Pashamylaram Common Infrastructure Pvt. Ltd. Environmental Impact Assessment Report  

A-5 Team Labs and Consultants  

15 Rantus Pharma Pvt Ltd Bulk Drugs (API) and Intermediates

Plot no:29, Phase II,IDA, Phashamylaram

20

16 Astha Labs Pvt Ltd Bulk Drugs (API) and Intermediates

Plot no:278, Phase II,IDA, Phashamylaram

15

17 MSN Labs Bulk Drugs (API) and Intermediates

Plot no:212 B,C,D, Phase II,IDA, Phashamylaram

20

18 Chromo labs Pvt Ltd Bulk Drugs (API) and Intermediates

Plot no:43, Phase II,IDA, Phashamylaram

15

19 Gensynth fine chemicals Intermediates Plot no:220 and239, Phase II,IDA, Phashamylaram

15

20 AVR Organics Pvt Ltd Intermediates Yahvapur village, Sadashivapet , Medak District

20

21 Reddy Industries Intermediates Plot no:180 -186, Phase II,IDA, Phashamylaram

10

22 Srinivasa Pharma Intermediates Plot no:228, Phase II,IDA, Phashamylaram

15

23 Suven Life sciences Bulk Drugs (API) and Intermediates

Plot no:262and270, Phase II,IDA, Phashamylaram

30

1.2 Process Description

The proposal has an objective of establishing effluent treatment system based on zero liquid

discharge to provide common effluent treatment facility for member units, which are mainly

involved in manufacturing synthetic organic chemicals. The treated wastewater is proposed

to be returned to member units for reuse. The steam requirement is met by installing a 25

TPH coal fired boiler. It is also envisaged to optimize the energy consumption, by installing

a co-generation unit of 2.5 MW, The schematic diagram of the proposed operations with

steam consumtption at the CETP facility is presented in Fig.1.3.

Pashamylaram Common Infrastructure Pvt. Ltd. Environmental Impact Assessment Report  

A-6 Team Labs and Consultants  

Fig 1.3 Schematic Diagram of Unit Operation at CETP

1.3 Effleunt Transfer and Storage

The effluents in the order of 475 KLD from the individual units, which are mostly located

within the industrial area shall be transfered after primary treatment within the individual

units, by dedicated GPS tagged tank trucks. A dedicated GPS tagged tank truck shall be used

to transfer effluent by the industrial unit ie., AVR Organics Pvt. Ltd., located outside the

estate.

The wastewater after reaching the CETP shall be transferred to a closed storage tank which

shall have a number of compartments. The effluents from each unit are tested on arrival to

ensure that there are no toxics like cyanides, bromides, fluorides etc, in addition to other

parameters like pH, TDS, COD, Suspended solids, oil and grease to make sure that effluents

are within the Inlet effluent quality standards of Common Effluent Treatment plant.

Effluents which are above the inlet standards shall be returned to member units for further

pre-treatment. These effluents after the statutory tests are trasnferred to the main storage

tank, which is covered with the vent connected to scrubber. These effluents are subjected to

Coal Fired Boiler 25 TPH @ 67 Kg/cm2(g)

Turbine for High Pressure Steam

21.25 TPH @ 67 Kg/cm2(g)

Stripper6 TPH @ 5 Kg/cm2(g)

Step-Down Steam @ 5 Kg/cm2(g) Step-Down Steam @ 5 Kg/cm2(g)

MEE12 TPH @ 5 Kg/cm2(g)

ATFD0.5 TPH @ 5 Kg/cm2(g)

Fuel DetailsCoal Cal. Value: 4800 K.calBoiler Efficiency: 85%

Biological Treatment Plant

RO Plants

Pashamylaram Common Infrastructure Pvt. Ltd. Environmental Impact Assessment Report  

A-7 Team Labs and Consultants  

treatment based on zero liquid discharge principle. The treated wastewater in the order of

460 KLD shall be sent to the contributing individual units by dedicated tank trucks for reuse

in cooling towers and or boilers. Inlet effluent quality standars of Common Effluent

Treatment Plant are presented in Table 1.2.

Table 1.2 Inlet Effluent standards of Common Effluent Treatment Plant S.No Parameter Concentration (mg/l)

1 pH 5.5 - 9.0 2 Temeprature OC 45 3 Oil & Grease 20 4 Phenolic Compounds (as C6H5OH) 5 5 Ammonical Nitrogen (as N) 50 6 Cyanide (as CN) 2 7 Chromium Hexavalent (as Cr6+) 2 8 Chromium (Total) (as Cr) 2 9 Copper (as Cu) 3 10 Lead (as Pb) 1 11 Nickel (as Ni) 3 12 Zinc (as Zn) 15 13 Arsenic (as As) 0.2 14 Mercury (as Hg) 0.01 15 Cadmium (as Cd) 1 16 Selenium (as Se) 0.05 17 Fluoride (as F) 15 18 Boron (as B) 2 19 Alpha emitters, Hc/ml 10 - 7 20 Beta emitters, He/ml 10 - 8

1.4 Process Description and Technical Specification of Effluent Treatment System

The Effluent management system is developed to ensure `Zero Liquid Discharge’. The

total effluents from member units are considered as High COD/ TDS effluents with

concentrations ranging from 20,000 to 50,000 mg/l of COD and 35,000 to 80,000 mg/l of

TDS. List of CETP facilities are presented below;

Collection Tanks Multiple Effect Evaporator (MEE) Neutralization Tanks Agitated Thin Film Dryer (ATFD) Setting Tanks Biological Treatment Plant Stripper RO System Step Down Turbine

Pashamylaram Common Infrastructure Pvt. Ltd. Environmental Impact Assessment Report  

A-8 Team Labs and Consultants  

The treatment system consists of collection tanks, Equalization, Neutralization, Settling

tank, Stripper, Multiple Effect Evaporator (MEE) followed by Agitated Thin Film Dryer

(ATFD). The organic distillate from the stripper is sent to cement plants for co-incineration

and aqueous bottom from stripper is sent to MEE followed by ATFD for evaporation. The

condensate from MEE and ATFD are sent to ETP (Biological). Salts from ATFD are disposed

to TSDF.

Condensate from MEE, ATFD, blow downs from utilities and wastewater from domestic

usage are treated in primary treatment consisting of equalization, neutralization, and

primary sedimentation followed by secondary biological treatment consisting of aeration

tank and clarifier.

The treated effluents after biological treatment are subjected to tertiary treatment in reverse

osmosis (Double RO) system. Permeate from RO returned to the member units for reuse

and rejects are sent to MEE followed by ATFD. Sludge from various units of Biological

treatment are thickened in sludge handling system and sent to TSDF. Schematic diagram of

effluent treatment system is presented in Fig 1.4. Technical specifications of effluent

treatment system are presented in Table 1.3 and 1.4 respectively.

Pashamylaram Common Infrastructure Pvt. Ltd. Environmental Impact Assessment Report  

A-9 Team Labs and Consultants  

Fig 1.4 Schematic Diagram of Zero Liquid Discharge System

Strip

per

Multip

le Effec

t Ev

apor

ator

Agita

ted Th

in 

Film Dryer

Salts to TSD

F

Settlin

g tank

Equa

lization 

Neu

tralization

Org

. Dist

illate 

to 

Cemen

t Ind

./TSD

F

Org

anic 

Distillate

High TD

S & 

COD

Condensate

Low TDS & 

Low COD

Scre

enCh

ambe

r

Slud

ge 

Drying B

ed

Oil

Skim

mer

Equa

lization 

Neu

tralization

Aeratio

nTa

nkClarifier

Holding

Tank

Filte

rs

Trea

ted W

ater 

Stor

age Ta

nk

Filte

r Pre

ss

Slud

ge Cak

e to 

TSDF

RO Plant

Recy

cle W

ater 

Colle

ction 

Sump

To  C

oolin

g To

wer

s

Rejects

Scru

bber Effluen

t & 

RO Rejec

ts

ToMEE

Pashamylaram Common Infrastructure Pvt. Ltd. Environmental Impact Assessment Report  

A-10 Team Labs and Consultants  

Table 1.3 Technical Specifications of Effluent Treatment System Data Capacity : 600 m3/day Flow (Process + washings) : 485 m3/day BOD : 24758 mg/l COD : 49515 mg/l Total Dissolved Solids : 79196 mg/l BOD load : 12008 kg/day COD load : 24015 kg/day Total Dissolved Solids : 38410 kg/day 1. Bar Screen Chamber Flow rate : 75.00 m3/hr Peak factor : 3.00 Peak flow : 225.00 m3/hr Velocity through screen : 0.80 m/hr Clear area through rack opening : 281.25 Gross area : 1.20 times net area Gross area : 337.50 m Assuming the inclination of screen of 60° to horizontal. Gross area of screen needed would be 2.0X2.5 Mt. for ease of maintenance. 2. Oil & Grease Trap (O&G) Flow Rate : 25 Kg/hr Flow Rate in min : 0.417 m3/min Resident Time : 30.00 min Depth from inlet : 1.00 m Volume of the tank : 12.50 m3 Area : 12.50 m2 length of the tank (l=b) : 3.54 m (Say 4.0 m) Width of the tank : 3.54 m (Say 4.0 m) 3. Equalization tank Average flow : 50.0 m3/hr Peak flow : 175.00 Hydraulic retention time : 8 hrs. at peak flow Volume of the tank : 1400.0 m3 Assuming depth : 3 m Area : 466.7 m2 Assuming length to width ratio (1:1) ; l=b length of the tank : 21.6 m (Say 22.0 m) width of the tank : 21.6 m (Say 22.0 m) Air required for agitation : 0.01 m3/ m2 min Total air required : 1.05 m3/hr Air blower required : 3 m3/hr @ 3.8 mwc 4. Neutralization Tank Average flow : 50.0 m3/hr Hydraulic retention time : 12 hrs. at peak flow Volume : 600 m3 Tank : 2 no. Proposed based on Daily flow.

Pashamylaram Common Infrastructure Pvt. Ltd. Environmental Impact Assessment Report  

A-11 Team Labs and Consultants  

S.No Description Unit Capacity

Stripper for Process and Washings 1 Design Capacity KLD 600 2 Feed Rate Kg/hr 20-28 3 Specific Gravity of Feed ≈ 1.03 4 Initial Feed COD mg/l 20000-50000 5 Feed Total Solid % 1.5-2.0 6 High Heating Temperature OC 95 – 100 7 High COD Condensate recovery Kl/hr 0.5-2.0 8 Dry Saturated Steam at 5.0Kg/cm2 (g) Pressure TPH 4.0-6.0 9 Material of Construction (MOC) SS316 10 Cooling Water circulation rate for condenser m3/hr 500 11 Cooling Water Inlet Temperature OC 30 – 32 12 Cooling Water Outlet Temperature OC 38 – 40 13 Operating Condition Atmospheric

Multiple Effect Evaporator (MEE) 1 Design Capacity KLD 700 2 Feed Rate Kl/hr 25-30 3 Feed Concentration mg/l 35000 - 80000 4 Feed Temperature OC 30 5 Initial Solids % 5.0-10.0 6 Solids in Concentrate % 35 - 40 7 Concentrate Output Kl/hr 5.0-6.5 8 Water Evaporation Rate Kl/hr 20-25 9 Designed Water Evaporation Rate Kl/hr 22.5 10 Dry Saturated Steam at 5.0Kg/cm2 (g) Pressure TPH 10.0-12.0 11 Steam Economy (Kg Water Evaporation/Kg of Steam) 700 12 Cooling Water Circulation Rate at 30 – 32OC m3/hr 5.0-6.0 13 Cooling Water Inlet Temperature OC 30 – 32 14 Cooling Water Outlet Temperature OC 38 – 40

Agitated Thin Film Dryer (ATFD) 1 Design Capacity KLD 150 2 Feed Rate Kl/hr 5.0-6.5 3 Initial Feed Solid Content % 35 - 40 4 Final Moisture in Dry Bag-gable Product % 3.0-5.0 5 Water Evaporation Rate Kl/hr 4.0-5.0 6 Designed Water Evaporation Kl/hr 4.5 7 Solid Output in Bag-gable form at 5 – 10% moisture Kl/hr 1.5-2.0 8 Dry Saturated Steam at 5.0Kg/cm2 (g) Pressure TPH 0.3-0.5 9 Cooling Water Circulation Rate at 30 – 32OC m3/hr 300 10 Cooling Water Inlet Temperature OC 30 – 32 11 Cooling Water Outlet Temperature OC 38 – 40

Pashamylaram Common Infrastructure Pvt. Ltd. Environmental Impact Assessment Report  

A-12 Team Labs and Consultants  

Table 1.4 Technical Specifications of Biological Treatment Plant Biological Treatment Data Flow from MEE + ATFD : 547.4 KLD Boiler Blow down : 4.0 KLD Cooling Tower Blow down : 30.8 KLD Scrubbers : 2 KLD Domestic : 2 KLD Total Flow to Neutralization tank : 586.7 KLD Design Capacity : 750 m3/day Flow : 586.7 m3/day Peak flow : 1173.4 m3/day BOD : 4918 mg/l COD : 12295 mg/l Total Dissolved Solids : 297 mg/l BOD load : 2885 kg/day COD load : 7213 kg/day Total Dissolved Solids : 174 kg/day Neutralization Tank Average flow : 62.5 m3/hr Hydraulic retention time : 12 hrs. at peak flow Volume : 750 m3 Tank : 2 no. Proposed based on Daily flow. Aeration Tank - 16 BOD(yo) : 4918 mg/l % of BOD removed : 80 BOD Load : 2885.4 kg/day COD : 12295 mg/l COD Load : 7213 kg/day Outlet BOD : 984 mg/l MLSS : 6000 mg/l F/M ratio : 0.2 Flow : 750 m3/day Volume of the Tank : 678.4 m3 Check for Detention time : 21.7 Hours (12 - 24) Assuming depth : 3.5 m (4.0+0.5 F.B) Area of the tank : 193.82 m2 Width of the tank : 13.92 m Length of the Tank : 6.96 m BOD5 load in the aeration tank : 2885.37 Oxygen is required for every Kg of BOD5 to be removed : 2.00 kgs Oxygen requirement for areation : 5770.73 kg/day O2 in Air % : 0.21 % Density of Air : 1.20

Pashamylaram Common Infrastructure Pvt. Ltd. Environmental Impact Assessment Report  

A-13 Team Labs and Consultants  

Oxygen requirement : 50.00 m3/kg O2/day Air Required : 288536.64 m3/day : 7089.35 cfm Consider 35% excess considering the air required in the equalization tank. Total air required : 9570.63 Kg O2/day Clarifier - 2 Design quantity : 750 m3/m2-day Surface loading rate of average flow : 12 m2 Surface area provided : 62.5 m length of the tank (2l=b) : 7.91 m (Say 8.0 m) Width of the tank : 3.95 m (Say 4.0 m) Aeration Tank - 2 BOD(yo) : 323 mg/l % of BOD removed : 80 BOD Load : 189.4 kg/day COD : 1291 mg/l COD Load : 757 kg/day Outlet BOD : 65 mg/l MLSS : 5500 mg/l F/M ratio : 0.1 Flow : 750.0 m3/day Volume of the Tank : 516.4 m3 Check for Detention time : 16.5 Hours (12 - 24) Assuming depth : 3.5 m (4.5+0.6 F.B) Area of the tank : 147.55 m2 Width of the tank : 12.15 m Length of the Tank : 6.07 m BOD5 load in the aeration tank : 189.35 Oxygen is required for every Kg of BOD5 to be removed : 2.00 kgs Oxygen requirement for aeration : 378.70 kg/day O2 in Air % : 0.21 % Density of Air : 1.20 Oxygen requirement : 50.00 m3/kg O2/day Air Required : 18935.22 m3/day : 465.24 cfm Consider 35% excess considering the air required in the equalization tank. Total air required : 628.07 Kg O2/day Clarifier - 2 Design quantity : 750 m3/m2-day Surface loading rate of average flow : 12 m2 Surface area provided : 62.5 m length of the tank (2l=b) : 7.91 m (Say 2.0 m) Width of the tank : 3.95 m (Say 1.0 m)

Pashamylaram Common Infrastructure Pvt. Ltd. Environmental Impact Assessment Report  

A-14 Team Labs and Consultants  

Holding tank The flow from the each individual settling tank i.e., the supernatant liquid is let into the respective Pre-Filtration Tank, which has a minimum 8 hours holding capacity. This tank is provided to hold the treated effluent and give an even flow to the pressure sand filter. Average flow : 62.5 m3/hr Peak factor : 2 m3/hr Peak flow : 125.0 m3/hr Provide min 1.5 hours holding capacity. Hence required volume of the tank : 187.5 m3 Pressure Sand Filter: Vertical down flow type with graded/sand bed under drain plate with polysterene strains. Flow : 750 m3/day Rate of filtration assumed as : 15 m3/m2/hr Requirement of treated water for usage in 20 hrs : 37.5 m3/hr Dia of filter of 1 nos. : 1784.58 mm Provide a Pressure Sand filter of 400 mm say 550 mm dia with sand as media over layer, under drain pipe, laterals face piping etc., Activated Carbon Filter: Vertical down flow type with graded/sand bed under drain plate with polysterene strains. Flow : 750 m3/day Rate of filtration assumed as : 15 m3/m2/hr Requirement of treated water for usage in 20 hrs : 37.5 m3/hr Dia of filter of 1 nos. : 1784.58 mm Provide activated carbon filter of 400 mm say 550 mm dia with sand as media over layer, under drain pipe, laterals face piping etc., Reverse Osmosis -1: Design Capacity : 750 KLD Operating capacity : 587 KLD Recovery : 60% RO Permeate : 352.0 KLD RO rejects : 234.7 KLD Reverse Osmosis - 2: Design Capacity : 280 KLD Operating capacity : 235 KLD Recovery : 60% RO Permeate : 140.8 KLD RO rejects : 93.9 KLD

Pashamylaram Common Infrastructure Pvt. Ltd. Environmental Impact Assessment Report  

A-15 Team Labs and Consultants  

1.5 Process Description of Co-generation Power Plant

The steam required for the abvoe mentioned ZLD system is in the order of 18.5 TPH,

requiring a 25 TPH capacity boiler. It is proposed to utilize the steam initally for a power

plant of 2.5 MW capacity and the steam after step down shall be utilized for ZLD system.

The operational details of co-generation plant are presented as follows;

Using steam turbines, the cogeneration plant generates power. A 25 TPH @ 67 Kg/Cm2 (a)

pressure boiler will be installed to cater to the steam requirement of the turbine and for

process requirements. The electricity generated in the cogeneration plant will be used for

plant operations.

The fuel requirement of the imported / local coal is approx. 5.0 T/hrs. Fuel will be brought

by covered trucks and unloaded at site in covered shed. The fuel will be conveyed to the

boiler by conveyor system and fed to the boiler by Rotary feeders.

AFBC Atmospheric Fluidized Bed Combustion type boiler is chosen considering imported

coal and good combustion efficiency. Water is heated in the boiler to generate high pressure

super-heated steam at 67 Kg/Cm2 (a) at 485OC. The boiler capacity is 25TPH with thermal

efficiency of the boiler is 85%. The boiler will have Economizer, Air pre-heater to recover

maximum heat from the boiler flue gases. The boiler shall have standard accessories such as

Feed water pumps, Soot blowers, Dosing system, safety valves and cut offs .

Fresh air for fuel combustion will be supplied by FD fans. Pre heated hot air will be supplied

at combustion zone as secondary air through PA fans. ID fan will be used to exhaust the

waste flue gasses through a stack of adequate height as per PCB norms.

Air cooled condenser is selected considering the minimum usage of water. For auxiliary

cooling requirements of Generator, cooler, GVC etc, modular type FRP induced draft

auxiliary cooling tower will be provided. The balance steam from the turbine exhaust will be

condensed in an air cooled condenser and pumped back by CEP to the De-aerator and

Pashamylaram Common Infrastructure Pvt. Ltd. Environmental Impact Assessment Report  

A-16 Team Labs and Consultants  

further to the boiler. Turbine will have Turbovisory, safety devices, instrumentation, controls

and interlocks as per standard engineering practice.

The Generator is driven by the Turbine at 1500 rpm through reduction gear box. The

generator will have brushless Excitation system and closed circuit indirect water cooling

system. Power will be generated at 11kV, 3phase, 50cps frequency. The Generator will be

provided with HT breaker, LASCPT, NGR, AVR, Metering & Synchronization panels as per

standard engineering practices and protective measures.

The power produced at 11kV will be taken to plant's HT yard through cabling. All necessary

protections are incorporated such that power plant is protected from any electrical faults.

1.5.1 Process Description of Main equipment:

I. Boiler

The type of boiler used is AFBC boiler. The plant proposes to utilize Imported/Domestic

coal. Boiler feed water is supplied by a closed cycle system of evaporation through De-

aerators and boiler feed water pumps. The pressurized feed water will pass through the de-

aerator and economizer before reaching the boiler drum. The evaporated steam is separated

in a steam drum and further super-heated in super heater coils before supplying to turbine

for expansion and condensation of thermal energy to mechanical work. The turbine is

coupled to electric generator through gear box where the mechanical energy is converted to

electric energy.

The Saturated steam from the steam drum is led in to 2 stage super heater section mounted

at convective zone of the boiler. The super heater system will have two stages of super

heaters to achieve the rated steam outlet temperature of 485°C from 80% to 100% MCR load.

Intermediate spray type de-super heaters will be provided between the two stages of super

heater to control the steam temperature over the control load range. The unit will include an

economizer encased in the ducting after the boiler bank.

Pashamylaram Common Infrastructure Pvt. Ltd. Environmental Impact Assessment Report  

A-17 Team Labs and Consultants  

Technical Specification of AFBC Boiler Installation Outdoor Fuel Size 0 -6 mm Fuel Imported/Indian coal Type of Boiler Atmospheric fluidized bed Combustion Method of control of fuel feed By varying the speed of fuel feeding drives Fuel quantity (100% MCR)(Kg/hr.) 5000 Boiler Thermal efficiency on GCV basis 85+/-1% Rated capacity of Steam boiler (Kg/hr.) 25,000 Steam pressure (Ata) 45 Steam temperature (°C) 485 Boiler outlet Flue gas temp. (°C) 160 Feed Water inlet temperature at the inlet (°C) 30 Ambient temp. (°C) 40 Relative Humidity (%) 60 Ambient temp. (°C)

- Efficiency 40 - Insulation 50 - Electrical 50

Electrical Data -LT Volt (V) 415 + 10% - Control Volt (V) 110 + 10% - Frequency (HZ) 50

Compressed Air pressure (Kg/cm2) 5

II. Steam turbine generator The medium pressure and medium temperature steam generated in boiler will enter a multi-

stage turbine and will cause the turbine shaft to rotate. In this process, the steam will lose its

temperature and pressure. As the pressure is coming down volume will increase, thereby

increasing velocity of flow in the turbine. This thermal energy getting converted to mechanical

energy will rotate the turbine shaft which is rigidly coupled to generator. An electrical generator

coupled to the steam turbine shaft will rotate in a magnetic field and generate electrical power of

2.5 MW at voltage of 11 KV. A small percentage of electrical power thus produced will be used

in the power plant itself to energies the rotating equipment like the FD fan and ID fan of boiler,

the feed water pumps, lighting etc.

Pashamylaram Common Infrastructure Pvt. Ltd. Environmental Impact Assessment Report  

A-18 Team Labs and Consultants  

Technical Specifications of Turbine Parameter Specification No. of Turbines 1 (one) Type Multi stage, horizontal split casing, high speed with

gear box, impulse type, extraction cum Condensing with air cooled condenser

Rated Output 2.5 MW @ 25 TPH, process steam @ 67 Kg/cm2(g) Speed of Turbine Shaft 1500 RPM Speed of Generator Shaft 1500 RPM Gear box Provided with SF 1.3, Double helical single reduction

(Air breather ) Rotation (Viewed from turbine front) Clock Wise Main steam conditions at stop valve Inlet steam pressure

67 ATA, 485 C, 25tph

Type of Governing Electronic ( Wood ward)

Technical Specifications of Generator Parameter Specification No. Of generators 1(One) Type Three phase synchronous generator, totally enclosed air cooled

with air to water heat exchanger, horizontal and indoor. Output 2.5 MW Voltage 11 KV Frequency 50 Hz Speed 1500 RPM Power Factor 0.8 No. of Poles 4 Inlet cooling water temp 34°C Excitation Brushless Excitation system

1.5.2 Fuel Requirement

The proposed 25 TPH boiler will use imported / domestic coal as the main fuel. The

imported/ domestic coal consumption per hour is 5 MT. DG set operation during regular

power supply breakdown period only.

Pashamylaram Common Infrastructure Pvt. Ltd. Environmental Impact Assessment Report  

A-19 Team Labs and Consultants  

Characteristics of Proposed Fuels Fuel Quantity

(T/hr.) Properties

Moisture Volatile matter

Fixed Carbon

Ash% dry Basis

Gross heat Kcal/kg Dry basis

Proximate Analysis Imported Coal 3 30-32% 43.07 48.37 9.37 4500 Indian Coal 2 8-10% 43.07 39.9 42 3800

Fuel Quantity (T/hr.)

Carbon Content

Hydrogen Content

Nitrogen Content

Oxygen Content

Sulfur Content

Phosphorous Content

Ultimate Analysis Imported Coal 3 48.37% 2.51% 0.8% 8.56% 0.39% 0.07% Indian Coal 2 39.9% 2.48% 0.48% 6.76% 0.38% 0.07%

Pashamylaram Common Infrastructure Pvt. Ltd. Environmental Impact Assessment Report  

A-20 Team Labs and Consultants  

ANNEXURE – III

Water Requirement

Water is required for R&D, cooling tower makeup, steam generation and domestic purposes

within the CETP. The total water requirement shall be 250.9 KLD, out of which 218.9 KLD

shall be fresh water and balance 32 KLD shall be recycled water mainly to operate the co-

generation plant and utilities. The required water shall be drawn from ground water/TSIIC

(Industrial supply) in addition to reuse of treated wastewater. It may be noted that the

facility is meant for treating wastewater/effluents from various industries located within

the industrial area to the tune of 475 KLD. The wastewater meant for treatment is not

reflected in the water balance, as the treated wastewater is returned to the individual units

to the tune of 460 KLD.

Total Water Balance Purpose INPUT (KLD) OUTPUT (KLD)

Fresh Water Recycled Water Loss Effluent Boiler Feed 126 122 4 Cooling Tower 83.4 32 94.6 20.8 R&D Lab 5 5 Scrubbers 2 2 Domestic 2.5 0.5 2 Gross Total 218.9 32 217.1 33.8 Total 250.9 250.9

Pashamylaram Common Infrastructure Pvt. Ltd. Environmental Impact Assessment Report  

A-21 Team Labs and Consultants  

ANNEXURE – IV

Water Pollution:

Effluents from member units, CETP, R&D, utility blow downs and domestic wastewater

will be sent to the effluent treatment system. The treated effluent will be reused for cooling

towers makeup in the individual units.

Total Effluent Generated and Mode of Treatment Description Quantity

(KLD) Mode of Treatment

HTDS Effluents (TDS & COD> 15000 mg/l) Process Effluent (From Member Units)

475 Sent to Stripper followed by MEE and ATFD. Stripper Condensate sent to Cement Plants for Co-Incineration. MEE and ATFD Condensate sent to Biological treatment plant followed by RO. RO rejects sent to MEE. Permeate from RO is returned to individual units for reuse.

CETP R&D 5

Total - I 480 LTDS Effluents (TDS & COD< 15000 mg/l)

Boiler Blow downs 4 Sent to Biological Treatment System followed by RO. RO permeate reused for co-generation power plant cooling tower makeup. RO rejects sent to MEE.

Cooling Tower Blow downs 20.8 Scrubbers 2 Domestic 2 Total - II 28.8 Grand Total (I+II) 508.8

Treated Effluent Standards

Description Parametr Concentration (mg/l) Treated Effluent TDS < 50 mg/l

TSS < 10 mg/l COD < 20 mg/l

Pashamylaram Common Infrastructure Pvt. Ltd. Environmental Impact Assessment Report  

A-22 Team Labs and Consultants  

ANNEXURE – V

Emissions from Utilities

The sources of air pollution are 25 TPH Coal fired boiler and backup DG sets of 2 x 500 KVA.

The proposed air pollution control equipment for Coal fired boiler is Bag Filter. DG sets shall

be provided with stack heights based on the CPCB formula for effective stack height. The

emission rates of SO2, NOx and PM from each stack are presented in Table below

Emission Details of Pollutants from Stack S.

No Stack Connected to Stack

Ht (m)

Dia of stack

at top(m)

Temp. of exhaust

gases (OC)

Exit Velocity (m/sec)

Pollutant Emission Rate (g/sec)

PM SO2 NOx

1 25 TPH Coal fired Boiler 40 1.8 180 15 1.8 3.2 4.6 2 2 x 500 KVA DG Sets 5 0.2 200 6.8 0.002 0.025 0.04

* DG sets stack heights are above the roof level.

Technical Specifications of Bag Filter – 25 TPH Coal Fired Boiler

S.No Application Unit Value 1 Boiler Capacity TPH 25

Fuel Coal 2 Gas Volume m3/hr@170 degC 38500

Gas Temperature Deg C 200 Outlet emission mg/Nm3 <50 Flange to flange pr. drop mmWC 150 Maximum oxygen in flue gases Vol % 8.7 Model FGF3MFV10018FB No. of Bags 504 Filter area per bag m² 1.86 Total filter area m² 937.5 Air to cloth ratio m³/min/m² 1.5 Outlet Emission

3 Bags Diameter ID, mm 160 Length mm 3660 Material Nomex Max. operating temp. degC 200 Weight gm/m² 500-550 Permeability L/dm².min 150 to 180

4 Bag Cleaning Compressed air required Nm3/Hr 46 at 6-8 kg/cm2 No. pulse cum solenoid valve 15 Size of pulse valve NB 40

Pashamylaram Common Infrastructure Pvt. Ltd. Environmental Impact Assessment Report  

A-23 Team Labs and Consultants  

5 Material of Construction Casing MS

a Tube Sheet MS Cage MS Hopper MS

7 Terminal Points Dirty air Inlet of Poppet Valve, Flanged end Clean air Outlet of Bag Filter, Flanged end Dust discharge RALV Compressed air Inlet of Air Header Electricals Power Supply for Timer 230 V Ac

Diffuse Emissions

Emissions released from operations like distillation etc. Emissions from stripping of

effluents mainly contain low volatile organics. These emissions are passed through double

condensers followed by vacuum pump before releasing into atmosphere to mitigate odour.

Effluent transfer pumps shall be provided with mechanical seals. The transfer of effluents

shall be mainly by closed pipeline systems. Stripped low volatile organics are stored in

storage tank with condenser.. The influent storage tank is a major source of diffuse VOC

emissions, and it is proposed to provide a closed tank for initial storage of untreated

effluents, with scrubbers connected to the storage tank vent.

Fugitive Emissions

Fugitive emissions are anticipated from equipment leakage and transfer spills. The

periodic maintenance program shall ensure integrity of equipment mitigating the

equipment leakage. The fugitive emissions shall be reduced by closed transfer and handling

of all effluents.

Pashamylaram Common Infrastructure Pvt. Ltd. Environmental Impact Assessment Report  

A-24 Team Labs and Consultants  

ANNEXURE – VI

Solid Waste

Solid wastes are generated from wastewater treatment and utilities. The effluent treatment

system generates, stripper distillate, ATFD salts and ETP sludge. Coal fired boiler generate

ash while DG sets generate waste oil and used batteries. All the wastes except coal ash are

considered hazardous. The hazardous wastes of stripper distillate are sent to cement plants

for co-incineration, thereby reducing the load on TSDF facility and reducing consumption of

non renewable resource of coal in cement plant kilns. The inorganic wastes, salts from ATFD,

and ETP sludge are sent to TSDF facility located at Dundigal, Ranga Reddy district or to

cement plants contingent on acceptability. The waste oil and used batteries are sold to

authorized recyclers. Coal ash is sold to brick manufacturers in the local area. .

Total Solid Waste Generated and Mode of Disposal S.No Description Units Quantity Mode of Disposal

1 Ash from Boiler TPD 65 Sold to Brick manufactures 2 Stripper Distillate KLD 20 Sent to TSDF/Cement Industries for

Co-incineration. 3 Evaporation salts TPD 38.3 Sent to TSDF/Cement Plants for

blending. 4 ETP Sludge TPD 12 Sent to TSDF /Cement plants for

blending. 5 Waste oil LPM 110 Sent to Authorized Recyclers 6 Used batteries No.s/Yr 4 Sent to Authorized Recyclers

Ash Handling System

Ash will be of two types’ viz., bottom ash and fly ash. The bed ash will be about 20% of the

total ash and the remaining 80% of the total ash will be fly ash. Bag Filter (dust collector)

will separate all the fine ash particles. The efficiency of Bag Filter will be 90%. The bed ash

will be in loose lump farm and is collected in wet form on a submerged ash conveyor. The

conveyor discharges in to a hopper and can be loaded in to a trailer for disposal. The fly ash

collected at air pre heater, economizer and bag filter will be conveyed to an ash silo by a

network of screw conveyors and bucket elevator. The fly ash from the silo will be

conditioned with water before discharging on a truck for final disposal.

PASHAMYLARAM COMMON INFRASTRUCTURE PVT. LTD. SY. NO. 236 (Part), 237 (Part) AND 242 (Part),  

PHASE II, IDA, PASHAMYLARAM, PATANCHERU MANDAL,  MEDAK DISTRICT, TELANGANA 

   

  

    

 

   

    

  

 

 

 

 

 

 

STUDIES AND DOCUMENTATION BY TEAM Labs and Consultants   QCI: MoE&F OM, List A‐1, S.No.25.   (An ISO 9001:2008, ISO 14001:2004 &  OHSAS 18001:2007 Certified Organization) B‐115, Annapurna Block, Aditya Enclave Ameerpet, Hyderabad‐500 038. Phone: 040‐23748 555/616, Telefax: 040‐23748666 Email: [email protected]