APPEProject - Environmental Clearance

39
Environment Clearance of Proposed Office Building “Shalimar Iridium ”, At TC/G-1/1, Vibhuti Khand, Gomti Nagar, Lucknow, U.P. --------------------------------------------------------------------------------------------------------------------- www.dasindia.org Page 1 FORM-1 A (Only for construction projects listed under item 8 of the Schedule) CHECK LIST OF ENVIRONMENTAL IMPACTS Name of the Project/s: Environment Clearance of Proposed Office Building “Shalimar Iridium”, At TC/G-1/1, Vibhuti Khand, Gomti Nagar, Lucknow, U.P. LAND ENVIRONMENT (Panoramic View of the Project site are attached) 1.1 Will the existing landuse get significantly altered from the project that is not consistent with the Surroundings? (Proposed landuse must conform to the approved Master Plan / Development Plan of the area. Change of landuse if any and the statutory approval from the competent authority is submitted). Attach Maps of (i) site location, (ii) Surrounding features of the proposed site (within 500 meters) and (iii) The site (indicating levels & contours) to appropriate scales. If not available attach only conceptual plans. The Proposed Office Building “Shalimar Iridium”, At TC/G-1/1, Vibhuti Khand, Gomti Nagar, Lucknow, U.P. The existing land use will not get altered from the project as the current land use of the project area is Commercial as per the proposed LDA Plan 2031 and the site has been approved by Lucknow Development Authority. The proposed development will be as per the approval of the local authority and building bye-laws. Site is open land and does not involve activities of any type. It is anticipated that the construction activities of the proposed project would not have any adverse effect on the land use as it is already defined by the concerned authorities. The development of the green belt and other landscape would enhance the visual aesthetics of the area.

Transcript of APPEProject - Environmental Clearance

Environment Clearance of Proposed Office Building “Shalimar Iridium ”, At TC/G-1/1,Vibhuti Khand, Gomti Nagar, Lucknow, U.P.

---------------------------------------------------------------------------------------------------------------------

www.dasindia.org Page 1

FORM-1 A

(Only for construction projects listed under item 8 of the Schedule)

CHECK LIST OF ENVIRONMENTAL IMPACTS

Name of the Project/s: Environment Clearance of Proposed Office Building“Shalimar Iridium”, At TC/G-1/1, Vibhuti Khand,Gomti Nagar, Lucknow, U.P.

LAND ENVIRONMENT

(Panoramic View of the Project site are attached)

1.1 Will the existing landuse get significantly altered from the project that is not consistent with the

Surroundings? (Proposed landuse must conform to the approved Master Plan / Development

Plan of the area. Change of landuse if any and the statutory approval from the competent

authority is submitted). Attach Maps of (i) site location, (ii) Surrounding features of the

proposed site (within 500 meters) and (iii) The site (indicating levels & contours) to appropriate

scales. If not available attach only conceptual plans.

The Proposed Office Building “Shalimar Iridium”, At TC/G-1/1, Vibhuti Khand,Gomti Nagar, Lucknow, U.P.

The existing land use will not get altered from the project as the current land use of the project area is

Commercial as per the proposed LDA Plan 2031 and the site has been approved by Lucknow

Development Authority. The proposed development will be as per the approval of the local authority

and building bye-laws. Site is open land and does not involve activities of any type. It is anticipated

that the construction activities of the proposed project would not have any adverse effect on the land

use as it is already defined by the concerned authorities. The development of the green belt and other

landscape would enhance the visual aesthetics of the area.

Environment Clearance of Proposed Office Building “Shalimar Iridium ”, At TC/G-1/1,Vibhuti Khand, Gomti Nagar, Lucknow, U.P.

---------------------------------------------------------------------------------------------------------------------

www.dasindia.org Page 2

FIGURE 1: LOCATION MAP

Project Site

Environment Clearance of Proposed Office Building “Shalimar Iridium ”, At TC/G-1/1,Vibhuti Khand, Gomti Nagar, Lucknow, U.P.

---------------------------------------------------------------------------------------------------------------------

www.dasindia.org Page 3

Figure 2: Google Image Showing Location of Proposed Mix Use Project

Figure 3: Google Image Showing Co-ordinates of Proposed Mix Use Project

N

N

Point 1: 26°52'5.02"N,81° 0'30.59"E

Point 2: 26°52'3.28"N,81° 0'29.89"E

Point 3: 26°52'2.65"N,81° 0'32.06"E

Point 4: 26°52'4.96"N,81° 0'32.80"E

Project SiteHigh Court

Indira GandhiPrsatishthaan

Am

ar Shaheed Path

Environment Clearance of Proposed Office Building “Shalimar Iridium ”, At TC/G-1/1,Vibhuti Khand, Gomti Nagar, Lucknow, U.P.

---------------------------------------------------------------------------------------------------------------------

www.dasindia.org Page 4

1.2 List out all the major project requirements in terms of the land area, built up area, waterconsumption, power requirement, connectivity, community facilities, parking needs etc.

Area Statement of proposed project is given in Table-2 and project specific details are provided in

table 1:

Table 1: Site Specific Details

Particulars Details

Location Environment Clearance of Proposed Office Building“Shalimar Iridium ”, At TC/G-1/1, Vibhuti Khand,Gomti Nagar, Lucknow, U.P.

Type of Industry Building & Large Construction Project

Category B, Type- 8(a)

Latitude & Longitude Point 1: 26°52'5.02"N, 81° 0'30.59"EPoint 2: 26°52'3.28"N, 81° 0'29.89"EPoint 3: 26°52'2.65"N, 81° 0'32.06"EPoint 4: 26°52'4.96"N, 81° 0'32.80"E

Elevation (m) amsl 122 m

Current status of land Commercial Landuse as per Lucknow Master Plan, 2021

Type of facilities Office Complex

Nearest Highway Faizabad Road NH- 28: 460 m (N)Shaheed path: 200 m (E)

Nearest railway station Gomti Nagar Railway Station: 1.5 km (SW)Charbagh Railway Station: 10 km (SW)

Nearest airport Amausi International Airport: 17 km (SW)

Protected areas as per WildlifeProtection Act, 1972 (Tiger reserve,Elephant reserve, Biospheres,National parks, Wildlife sanctuaries,community reserves and conservationreserves)

None

Reserved/Protected Forests None

Rivers/Lakes Gomti River: 4.5 km (SW)Katautha Lake: 2.0 km (SE)

Archaeological important places None

Seismic zone Seismic Zone III

Defense installations Lucknow Cantt. Area: 6 km (SW)Air Force Station Bakshi ka Talaab: 16.5 km (NW)

Environment Clearance of Proposed Office Building “Shalimar Iridium ”, At TC/G-1/1,Vibhuti Khand, Gomti Nagar, Lucknow, U.P.

---------------------------------------------------------------------------------------------------------------------

www.dasindia.org Page 5

Table - 2: Area StatementS.NO Description Area(m2) Percentage

1. Plot Area 5439.0

2. Achieved Ground Coverage 1733.33 31.86%

3. Permissible FAR 10878 @2.0

4. Purchased FAR 3296.82 @0.61

5. Total achievable FAR 14174.82 @2.61

6. Proposed FAR 14174.82 @2.61

7. Total Open Area(Plot Area- GroundCoverage)

3705.67 68.13%

8. Basement (Upper + Lower)

Total Non-Far Area

6280.28

6280.28

9. Built up Area 20455.10

10. Area of road and internal circulationOther Services/(Paved Area)/boundary area

3154.67 58.00%

11. Green area achieved 551.00 10.13%

Table – 3: Salient Feature of the projectParticulars Proposed

Area Utilization 1 tower (2 B + G +9 floors)

Height of Building 35 m (G+9)

Estimated Employee Population(@ 1 person per 10 m2 )

1420 persons / day

Parking Required (1 ECS/ 50 m2 of permissibleFAR)

284 ECS

Provided no. of parkingUpper Basement (mechanized)Lower Basement (mechanized)OpenTotal Parking Provided

15019244

386 ECSPower requirement& source 2000 KW

Source: U.P Power CorporationLtd. (UPPCL)

Power backup (DG Sets) 2 x 250 KVA

Environment Clearance of Proposed Office Building “Shalimar Iridium ”, At TC/G-1/1,Vibhuti Khand, Gomti Nagar, Lucknow, U.P.

---------------------------------------------------------------------------------------------------------------------

www.dasindia.org Page 6

Number of trees required(1 tree @80m2 of openarea)

46

Number of trees proposed 60

Sewage Generation Amount of waste water generated :61 KLDSTP Capacity: 80 KLD (20%higher capacity)Technology: MBBR

Solid waste Domestic waste : 378 kg/dayHorticultural waste : 2 kg/dayE- waste : <1 kg/daySTP Sludge: 3 kg/day

Land Use Break upLand use Type Area (in m2)Ground Coverage 1733.33Green Area (Reserved green) 551.0Road+ Fire Tender Path 3154.67open for services & hardscape 5439.0

Figure 4 : Pie Chart representing Landuse

Development Mix

Towers Area in m2

Ground floor 1732.58First Floor 1522.78

Second Floor 1356.76

Road+ FireTender Path

58%

Land Use distribution

Environment Clearance of Proposed Office Building “Shalimar Iridium ”, At TC/G-1/1,Vibhuti Khand, Gomti Nagar, Lucknow, U.P.

---------------------------------------------------------------------------------------------------------------------

www.dasindia.org Page 6

Number of trees required(1 tree @80m2 of openarea)

46

Number of trees proposed 60

Sewage Generation Amount of waste water generated :61 KLDSTP Capacity: 80 KLD (20%higher capacity)Technology: MBBR

Solid waste Domestic waste : 378 kg/dayHorticultural waste : 2 kg/dayE- waste : <1 kg/daySTP Sludge: 3 kg/day

Land Use Break upLand use Type Area (in m2)Ground Coverage 1733.33Green Area (Reserved green) 551.0Road+ Fire Tender Path 3154.67open for services & hardscape 5439.0

Figure 4 : Pie Chart representing Landuse

Development Mix

Towers Area in m2

Ground floor 1732.58First Floor 1522.78

Second Floor 1356.76

GroundCoverage

32%

Green Area(Reserved

green)10%

Road+ FireTender Path

58%

Land Use distribution

Environment Clearance of Proposed Office Building “Shalimar Iridium ”, At TC/G-1/1,Vibhuti Khand, Gomti Nagar, Lucknow, U.P.

---------------------------------------------------------------------------------------------------------------------

www.dasindia.org Page 6

Number of trees required(1 tree @80m2 of openarea)

46

Number of trees proposed 60

Sewage Generation Amount of waste water generated :61 KLDSTP Capacity: 80 KLD (20%higher capacity)Technology: MBBR

Solid waste Domestic waste : 378 kg/dayHorticultural waste : 2 kg/dayE- waste : <1 kg/daySTP Sludge: 3 kg/day

Land Use Break upLand use Type Area (in m2)Ground Coverage 1733.33Green Area (Reserved green) 551.0Road+ Fire Tender Path 3154.67open for services & hardscape 5439.0

Figure 4 : Pie Chart representing Landuse

Development Mix

Towers Area in m2

Ground floor 1732.58First Floor 1522.78

Second Floor 1356.76

Green Area(Reserved

green)10%

Environment Clearance of Proposed Office Building “Shalimar Iridium ”, At TC/G-1/1,Vibhuti Khand, Gomti Nagar, Lucknow, U.P.

---------------------------------------------------------------------------------------------------------------------

www.dasindia.org Page 7

Third Floor 1421.72Fourth Floor 1421.72Fifth Floor 1421.72Sixth Floor 1421.72Seventh Floor 1290.5Eight Floor 1290.5Ninth Floor 1294.82Total area 14174.82

1.3 What are the likely impacts of the proposed activity on the existing facilities adjacent to theproposed site? (Such as open spaces, community facilities details of the existing landusedisturbance to the local ecology).

Table 4: Infrastructure in different directions of the projectDirection FacilitiesEast UP Power corporation, Shalimar Park

North Lucknow High Court, Indira GandhiPratishthan, Pic up Bhawan Road

West Fairfield By Marriot Lucknow

South Tata Consultancy Services

There will not be any significant impacts from the proposed activity on the existing facilities adjacent

to the proposed site, as the Lucknow Development Authority has developed all the facilities such as

connectivity, roads, open space, drainage, sewer and water supply etc. keeping in view the land use

as per proposed Master Plan 2031.

Anticipated Negative Impacts: All construction activities will be confined within the project area.

There will be no physical changes outside the project boundary. Development and Construction of

proposed project will be done as per applicable norms/byelaws. Hence, negative impacts on adjacent

existing facilities would be minimal, if any.

Anticipated Positive Impacts: There will not be any disturbance to the local ecology as the selected

site for the construction is predefined with the commercial land, use as per Lucknow Master Plan

2031. The land is already in possession of the applicant organization. Moreover, landscaping with

local plant species in post construction phase will restore the existing ecological condition in near

future. So there will be no permanent adverse impact on existing ecological conditions due to

proposed project.

About 551.0 m2 area will be developed as dedicated soft green and plantation area and will have

positive impact on the surrounding.

Proposed project will require manpower during construction phase and operation phase thereby

creating job opportunities and improving the socio-economic conditions of the area.

No fauna species are present in the area. Care will be taken to minimize the disturbance to the local

ecology.

Environment Clearance of Proposed Office Building “Shalimar Iridium ”, At TC/G-1/1,Vibhuti Khand, Gomti Nagar, Lucknow, U.P.

---------------------------------------------------------------------------------------------------------------------

www.dasindia.org Page 8

1.4 Will there be any significant land disturbance resulting in erosion, subsidence & instability?(Details of soil type, slope analysis, vulnerability to subsidence, seismicity etc may be given).There will be some land disturbance due to the upcoming project as the project will involvesite preperation, grading and construction of impervious surfaces.Following mitigation measures will be used to mitigate the same:

Construction planning will be done to minimize exposed soil during times of the year whenthe potential for erosion is high, for example during rains.

Site will be stabilized and erosion control measures will be adopted during any pause inconstruction.

Suppression measures, such as promptly watering exposed area will be taken in accountwhen visible dust is observed.

Stockpiles will be located with the slope not greater than 2:1 (horizontal to vertical).

Size and number of stockpiles will be kept minimum and will be located away from drainageline.

Dug pits will be prepared around the construction area to minimize the soil run off from theproject area.

Soil Type:

Type of soil: Sandy Loam

There will be no land disturbance resulting in erosion, subsidence or instability. The area is

fairly plain and subsoil strata are alluviums deposited by water courses, geologically the litho

log sections show dominant of sand percentage.

Slope Analysis:

The topography of the site area is mostly flat with slope tending towards Gomti River which

is 4.5 km south-west of the project site. The highest elevation at site is 122 above MSL and

the lowest elevation is 121 above MSL. In post construction phase the direction of the

natural drainage will be maintained.

Erosion / Subsidence: Project will provide ample green space. Therefore, it will not cause any soil erosion,

subsidence or instability problems.

Seismicity:According to the Indian Standard Seismic Zoning Map, the area under study falls in Zone-III (refer Figure 5). Suitable seismic coefficients in horizontal and vertical directions will beadopted while designing the structures.

Environment Clearance of Proposed Office Building “Shalimar Iridium ”, At TC/G-1/1,Vibhuti Khand, Gomti Nagar, Lucknow, U.P.

---------------------------------------------------------------------------------------------------------------------

www.dasindia.org Page 9

Fig. 5: Map Showing Seismic Zones in India, 2002

1.5 Will the proposal involve alteration of natural drainage systems? (Give details on a contourmap showing the natural drainage near the proposed project site).

The area is fairly plain and LDA has constructed system of drains. Contour map shows the Elevation

levels of proposed site as 122 m and drainage flow is towards Gomti River, south of the project site.

The project will not impact any drainage pattern in the vicinity. Therefore, there will be no alteration

of natural Drainage System, except the runoff from the site will increase during rains due to increase

in paved area.

The runoff generated from roof top area will be used for ground water recharging through rain water

harvesting system, whereas the runoff collected from open, green and paved areas will be discharged

into municipal storm water drains.

1.6 What are the quantities of earthwork involved in the construction activity cutting, filling,reclamation etc. (Give details of the quantities of earthwork involved, transport of fill materialsfrom outside the site etc).

It is estimated that approximately 40,000 m3 of earth material will be excavated during initialconstruction phase for foundations & 2 layer basement. The top soil excavated during construction

SITE

Environment Clearance of Proposed Office Building “Shalimar Iridium ”, At TC/G-1/1,Vibhuti Khand, Gomti Nagar, Lucknow, U.P.

---------------------------------------------------------------------------------------------------------------------

www.dasindia.org Page 10

will be first temporarily stored in earmarked area. Almost all the soil will be reutilized intobackfilling, leveling and filling of low lying area for development of landscape.

1.7 Give details regarding water supply, waste handling etc. during the construction period. Water Requirement (Construction Phase): ~10 KLD

Construction waste generated

Table 5: Details of Construction Waste Material Generated

Construction waste material Total construction wastegenerated @ 40 Kg/sq.mof builtup area

818 (MT)

soil, sand & Gravel 0.35 286

bricks & Masonry 0.3 245

Concrete 0.25 204

Metal 0.05 40

Bitumen 0.0204 17

Wood 0.0204 17

Other 0.01 8

Source: TIFAC

Source of water: Municipal water tankers will be the primary source of water requirement

during construction phase.

Construction Debris (Bricks, Cement, Concrete and Mortar) generated will be reused in road

construction, backfilling and leveling, spare debris (if any) will be disposed off as per the

norms.

Ready mix concrete will be used.

The fertile top soil will be reused for horticultural purpose.

Spillage of oil from the machineries will be properly collected and disposed off.

Proper Sanitary facilities and wash area will be provided and good hygienic conditions will

be maintained throughout the construction phase.

Septic tank with soak pit or mobile toilets with municipal sewer shall be provided to take care

of waste water generated from site (labor camps and site office)

Domestic solid waste generated will be managed as per MSW (M & H) Rule, 2016.

Litter bins will be provided in the open area.

1.8 Will the low-lying areas & wetlands get altered? (Provide details of how low lying and wetlandsare getting modified from the proposed activity).

Site is fairly plain and already developed by LDA with an altitude 122 m above mean sea level.

Drainage pattern and slope of proposed site is toward south of site and ultimately meets Gomti River.

No wetland or low lying area within project site.

Environment Clearance of Proposed Office Building “Shalimar Iridium ”, At TC/G-1/1,Vibhuti Khand, Gomti Nagar, Lucknow, U.P.

---------------------------------------------------------------------------------------------------------------------

www.dasindia.org Page 11

1.9 Whether construction debris & waste during construction cause health hazard? (Givequantities of various types of wastes generated during construction including the constructionlabour and the means of disposal)

Wastes which will be generated during the construction phase include the following:

Excavated materials from earthworks (e.g. cuttings, basement excavation, foundation etc),

General construction waste (e.g. wood, packing material, scrap metal, concrete and empty

cement bags);

Hazardous wastes generated by general site practices and paint and thinner residues, etc.

Municipal wastes generated by site workers. Most of the construction waste will be reused in

road construction and surplus will be sold to recyclers.

Excavated Materials from Earthworks

It is estimated that approx.40,000 m3 of earth material will be excavated during initial construction

for foundations & basement etc. Maximum percentage of excavated material will be re-used within

premises for different purposes. The excess earth would only be the construction wastes and will not

cause any health hazards.

Municipal Waste & Other wasteMunicipal wastes comprise kitchen wastes, packaging and waste paper. Generation rate of solid

waste from labour colony will vary from place to place due to habits and living condition.

Approximately 0.25Kg/capita/day of municipal waste may be expected during construction phase.

The domestic waste water generated from construction camps shall be disposed off through septic

tank / soak pit or mobile toilets with STP/ municipal sewer.

Some amount of debris, cuttings and construction materials may be observed at construction site.

Details of construction waste are discussed in Table 5. However the quantity of their waste materials

would be very small and limited up to the construction site only. Contamination by these wastes

would be negligible and would be collected time to time during construction phase and disposed off

accordingly. The Impact on soil during construction phase will be marginal and reversible in nature.

2.0 WATER ENVIRONMENT

2.1 Give the total quantity of water requirement for the proposed project with the breakup ofrequirements for various uses. How will the water requirement met? State the sources &quantities and furnish a water balance statement.

Water Requirement, Source and Water Balance

Environment Clearance of Proposed Office Building “Shalimar Iridium ”, At TC/G-1/1,Vibhuti Khand, Gomti Nagar, Lucknow, U.P.

---------------------------------------------------------------------------------------------------------------------

www.dasindia.org Page 12

A provision of 45 lpcd (liters per capita per day), & 15 lpcd for water requirements shall be made for

employee/staff & visitors respectively. This in accordance with the MoEF’s Construction Manual

&Manual of Water Supply, Central Public Health and Environmental Engineering Organization

(CPHEEO), Ministry of Housing, Government of India (GOI), hence the total water requirements

shall be:

Table 6: Water Calculations for the proposed residential complex

Particulars Population Rate of

Fresh

water

LPCD

Fresh water

required in

(KLD)

Rate of

Flushing

water

LPCD

Flushing/

Recycled

water

(KLD)

Total

water

(KLD)

Population1420

30 43 15 22 65

Visitors (10%) 150 5 1 10 2 3

44 24 68

Horticulture (@ 5litre /Sqm) 551.0 m2 3 3

Total Water Requirement 44 27 71

Fresh Water 44 KLD

HORTICULTURE3 KLD

DOMESTICWATER68 KLD

RECYCLEDWATER27 KLD

FLUSHING 24 KLD

MunicipalDrains

WASTEWATERGENERATED

= 61 KLDSTP = 80 KLD

@90% of domesticwater

27 KLD TertiaryTreated water

34 KLDsecondaryTreated water

Figure 6a : water balance during non-monsoon season

Environment Clearance of Proposed Office Building “Shalimar Iridium ”, At TC/G-1/1,Vibhuti Khand, Gomti Nagar, Lucknow, U.P.

---------------------------------------------------------------------------------------------------------------------

www.dasindia.org Page 13

Fresh Water 44 KLD

DOMESTICWATER68 KLD

RECYCLEDWATER24 KLD

FLUSHING 24 KLD

MunicipalDrains

WASTEWATERGENERATED

=61 KLDSTP=80 KLD

@90% of domesticwater

24 KLD TertiaryTreated water

37 KLDsecondaryTreated water

Figure 6b : water balance during monsoon season/rains

2.2 What is the capacity (dependable flow or yield) of the proposed source of water?

The proposed sources of water are:

1. Municipal Supply

2. Recycling of treated effluent from STP

Lucknow City Water Supply:

No. of groundwater structures (Lucknow city)

Jal Sansthan Tubewells More than 350Handpumps (Public) >6000Mini tube wells/Borings 300-400Tube wells : Government /Private establishments >150Tube wells : Private colonies/multi story buildings >400Private domestic borings Innumerable (no inventory)Tentative withdrawals 550 MLD or even more

Ground Water: Ground water is a natural occurrence. Ground water supply is met through deep,

shallow tubewells, Indiamark II Handpumps & Indira wells through Jal Sansthan as follows:

Supply through more than 350 tubewells - 185 MLD

Supply through 5000 India Mark II Handpumps - 25 MLD

Supply through 55 Indira wells - 28 MLD.

Environment Clearance of Proposed Office Building “Shalimar Iridium ”, At TC/G-1/1,Vibhuti Khand, Gomti Nagar, Lucknow, U.P.

---------------------------------------------------------------------------------------------------------------------

www.dasindia.org Page 14

Total Ground water supply - 238 MLD.

Thus the total supply for entire Lucknow city at present is 480 MLD out of which surface contributes

242 MLD and Ground water contributes 238 MLD.

Aquifer Group Depth range (mbgl)First Aquifer Group 00.00-150.00Second Aquifer Group 160.00-240.00Third Aquifer Group 260.00-370.00Fourth Aquifer Group 380.00-480.00Fifth Aquifer Group 483.00-680.00

Hydrogeological details of tubewells of Lucknow

Aquifergroup

Depth range ofaquifer group in

mbglWater Level mbgl Discharge

range (lpm)Draw-downrange (m)

specificcapacity(lpm/m)

1 2 3 4 5 6

I 00.00 - 150.00 20-26 1100-1700 4-10 150-325II 160.00 - 240.00 17-27 300-600 23-31 13-19III 260.00 - 370.00 20-22 1000-1500 25-33 40-50

IV 380.00 - 480.00 10-13 1400-1600 18-33 40-100V 483.00 - 680.00 11-12 - - -

I+II 00.00 - 250.00 15-30 1100-1600 4-10 130-320I+II+III 00.00 - 300.00 20-35 700-1600 7-33 50-250

III+IV 300.00 - 474.00 8.00 2300 24 96

2.3 What is the quality of water required, in case, the supply is not from a municipal source?(Provide physical, chemical, biological characteristics with class of water quality).The supply is through Municipal Water.

2.4 How much of the water requirement can be met from the recycling of treated wastewater?(Give the details of quantities, sources and usage).

About 38% of total water demand i.e. 27 KLD will be met from recycling of treated wastewater forFlushing, and Horticulture etc. Details of water usages are as follows:

Table 7: Water/ Waste water Details

Environment Clearance of Proposed Office Building “Shalimar Iridium ”, At TC/G-1/1,Vibhuti Khand, Gomti Nagar, Lucknow, U.P.

---------------------------------------------------------------------------------------------------------------------

www.dasindia.org Page 15

2.5 Will there be diversion of water from other users? (Please assess the impacts of the project onother existing uses and quantities of consumption).

There is no diversion of water from other users, as the fresh water supplies are provided by theMunicipal Authorities as per norms.

2.6 What is the incremental pollution load from wastewater generated from the proposed activity?(Give details of the quantities and composition of wastewater generated from the proposedactivity).

61 KLD will be the total waste water generated, which will be treated in the STP of 80 KLD out ofwhich, 27 KLD tertiary treated water will be recycled for various uses including Flushing,Horticulture and the spare 34 KLD (in non monsoon) and 37 KLD (in monsoon) will be treated up tosecondary treatment before its disposal in Municipal Sewers.No increase in pollution load expected.

Table8: Characteristics of Raw Sewage& Treated SewageParameter Raw Sewage

(Influent)Treated Sewage

(After SecondaryTreatment)

Treated Sewage(After Tertiary

Treatment)pH 7.5 – 8.5 6.5- 8.5 6- 8

BOD3 at 270C (mg/l) 250 - 350 < 30 < 10

COD (mg/l) 400 - 500 < 100 < 10

Suspended solids (mg/l) 250 - 450 < 100 < 5

Oil and Grease (mg/l) 30 < 10 < 1

2.7 Give details of the water requirements met from water harvesting? Furnish details of thefacilities created.

Rain water harvesting pits have been proposed for augmentation of ground water. The rainwater

collected from the rooftop will be conveyed into the rainwater harvesting system consisting of

Desilting-cum-filter chamber and borewells for recharge into the ground water. The rain water

Fresh Water 44 KLD

Flushing (Recycled water) 24 KLD

Horticulture / Landscape 3 KLD

Total Water Requirement 71 KLD

Source of water – Municipal Supply

STP capacity : 80KLD

Environment Clearance of Proposed Office Building “Shalimar Iridium ”, At TC/G-1/1,Vibhuti Khand, Gomti Nagar, Lucknow, U.P.

---------------------------------------------------------------------------------------------------------------------

www.dasindia.org Page 16

collected from Paved and Green area will percolate naturally in to ground. No demand will be met

from the process.

Analysis of the observed data on intensity duration of rainfall of past records over a period of years

in the area is necessary to arrive at a fair estimate of intensity-duration for given frequencies. The

longer the record available, the more dependable is the forecast. In Indian conditions, intensity of

rainfall adopted in design is usually in the range of 15 mm/hr to 40 mm/hr. The intensity of

precipitation for design of drainage scheme has been taken 40 mm/hr for the project.

Table 9: Storm Water CalculationPeak Run off

Max, Rainfall Intensity 40 mm/hr

Location RunoffCoefficient

Area m2 Rainfallintensity

Peak Runoff inm3/hr

(in m)Roof Area 0.8 1733.33 0.04 55Paved area 0.6 3154.67 0.04 75

Green Area 0.2 551.0 0.04 4Total Runoff m3/hr 134

Runoff Potential

Total Runoff = 134 m3/hr

Roof top runoff= 55 m3/hr

Taking 15 minutes Retention Time, Total volume of storm water = 134/4= 33.5 m3

Particular Size Volume

Desilting Chamber 2.0 m x 2.0 m x 1.5 m 6 m3

Recharge Pit 2.5 m x 2.5m x 3 m 18.75 m3

Total Effective Volume 24.75 m3

Hence No. of pits required = 33.5 / 24.75 = 1.35 pits or 2 pits

No. of Pits Required for Roof top rainwater harvesting:

Roof top Runoff = 196 m3/hr

Taking 15 minutes Retention Time, Total volume of storm water = 55/4= 13.75 m3

Hence No. of pits required =13.75 / 24.75 = 0.5 pits or 1 pits

Total No. of pits Proposed: 2

Environment Clearance of Proposed Office Building “Shalimar Iridium ”, At TC/G-1/1,Vibhuti Khand, Gomti Nagar, Lucknow, U.P.

---------------------------------------------------------------------------------------------------------------------

www.dasindia.org Page 17

Note: RWH will be initially done only from the roof top. Runoff from green and other open areas will

be done only after permission from CGWB.

2.8 What would be the impact of the land use changes occurring due to the proposed project on therunoff characteristics (quantitative as well as qualitative) of the area in the post constructionphase on a long-term basis? Would it aggravate the problems of flooding or water logging inany way?

Since this is a mix use project, the paved area will increase thus the land surface will change thereby

increasing the run off during rains. Maximum storm rainfall of 40 mm has been assumed on the past

experience. No adverse impacts are envisaged due to proposed project on the run off characteristics

of the area as adequate arrangements have been made to trap the rainwater and suitable storm water

drainage system has been provided.

There will be change in the surface run off coefficient in the pre construction phase and post

construction phase. The surface run off will be captured and used for harvesting so that the ground

water level is consistent. The storm water drains will be cleaned in the pre-monsoon phase so that the

water logging will be avoided.

During the post-construction phase, runoff from the project shall not be allowed to stand and create

water logging or enter into the road side or nearby drain. Adequate measures shall be taken to collect

such run off and either shall be reused or stored in recharging pits. Suitable garlanding drain as per

the existing contours of the plot will be developed. There is no landscape change planned. The

project will not aggravate the problems of flooding or water logging in any way, as the topography is

plain.

2.9 What are the impacts of the proposal on the ground water? (Will there be tapping of groundwater; give the details of ground water table, recharging capacity, and approvals obtainedfrom competent authority, if any).

Fresh water shall be supplied through Municipal water supply. The groundwater will be augmented

through proposed rainwater harvesting. The rain water collected from Roof top will be sent for

ground water recharging through 2 nos. of RWH pits. 134 m3/hr of water is available for ground

water recharge which will be recharged through RWH pits. A major part of the area is under green

or open land which will percolate naturally and augment the ground water. Therefore, most of the

rain water will be directly infiltrated through these open/green areas. Hence no adverse impacts are

envisaged due to the project on the ground water quality and the level. Maximum recharging of the

underground aquifer will be done.

Environment Clearance of Proposed Office Building “Shalimar Iridium ”, At TC/G-1/1,Vibhuti Khand, Gomti Nagar, Lucknow, U.P.

---------------------------------------------------------------------------------------------------------------------

www.dasindia.org Page 18

2.10 What precautions/measures are taken to prevent the run-off from construction activitiespolluting land & aquifers? (Give details of quantities and the measures taken to avoid theadverse impacts).

Effective measures will be adapted to reduce the storm water run-off from the construction site- Ensuring vehicles stick to the access track.

Cleaning all mud and dirt deposited on roads from construction-related activities. Excavation work will not be carried out during monsoon season.

Constructing a fence around the site to trap sediment whilst allowing water to flow through. Diverting up-slope water with turf and not mixing mortar in locations that will drain into

storm water system.

Preventing wastewater from brick cutting activities and stockpiles entering the storm watersystem.

Construction material will be stored in temporary shed at the earmarked place and will becovered ensuring that no leachate or spoilage of land occurs.

Curing water will be sprayed and, after liberal curing, all concrete structures will be paintedwith curing compound & covered with gunny bags, then the water will be sprayed.

Plantation of trees will start from construction phase. No runoff will be disposed outside the project boundary.

2.11 How is the storm water from within the site managed? (State the provisions made to avoidflooding of the area, details of the drainage facilities provided along with a site layoutindication contour levels).

Since the existing topography is congenial to surface disposal, a network of storm water pipe drains

has been planned adjacent to roads. All building roof water will be brought down through drain water

pipes. The drain sizes and sections will be designed in such a way that they can take the load of the

peak rainfall period. Proposed storm water system consists of pipe drains, catch basins and seepage

pits at regular intervals for rain water harvestings and ground water recharging. All the surface drains

will be covered by gratings and proper land gradient will be provided so that water logging inside the

site does not occur. Collected rain water will be recharge into ground water. The storm rainfall of 40

mm/hr. has been considered for designing the storm water drainage system.

A detailed storm water management plan will be developed which considers the source of storm

water. The plan incorporates the best management practices which include the following:

Regular inspection and cleaning of storm water drains.

Cover waste storage area.

Avoid excavation during monsoon season.

2.12 Will the deployment of construction labourers particularly in the peak period lead tounsanitary conditions around the project site (Justify with proper explanation).

Environment Clearance of Proposed Office Building “Shalimar Iridium ”, At TC/G-1/1,Vibhuti Khand, Gomti Nagar, Lucknow, U.P.

---------------------------------------------------------------------------------------------------------------------

www.dasindia.org Page 19

The workers from nearby localities and villages will be employed during construction. There will

be no stagnant water at site, as the run-off from the relevant areas will be systematically drained.

The civil contractor will be made responsible for site sanitation and will be bound by the

management to adhere to healthy level of sanitation. Temporary septic-tank followed by soak-pit

will be constructed for effluent treatment. All sanitary and hygienic measures will be provided and

maintained through out the construction phase such as:

• Provision of separate toilets for the construction workers.

• Temporary septic-tank followed by soak-pit will be provided for effluent treatment.

2.13 What on-site facilities are provided for the collection, treatment & safe disposal of sewage?(Give details of the quantities of wastewater generation, treatment capacities with technology &facilities for recycling and disposal).

During the construction phase, on-site sanitation facilities will be provided (Septic tanks and soak

pits). During the operational phase, the waste water generated from residential complex (i.e.61 KLD)

will be treated in the STP of 80 KLD. Out of total amount waste water, 27 KLD shall be treated up-to

tertiary level and recycled for various low end uses including toilet flushing, horticulture and other

low end uses. Spare secondary treated wastewater (34 KLD in non monsoon and 37 KLD during

monsoons) shall be discharged into municipal sewer line.

2.14 Give details of dual plumbing system, if treated waste is used for flushing of toilets or any otheruse.

Dual Plumbing will be provided for utilization of recycled water for flushing of toilets. Differentcolor pipes will be used for this purpose.

3.0 VEGETATION3.1 Is there any threat of the project to the biodiversity? (Give a description of the local ecosystem

with its unique features, if any).

No, the project will not pose any threat to the biodiversity of the locality. The project site was an

open agricultural land. As the project site do not contain any water body, therefore, no scope of

disturbance to the aquatic flora will be involved. Moreover, quite a number of trees will be planted.

The species will be predominantly native in nature so that they merge with the local ecosystem. Flora

and fauna of the study area is mentioned in section 3 of conceptual plan.

All the waste (liquid/solid/gases) will be managed onsite as per Rules. The impact due to proposed

project will be minimal.

3.2 Will the construction involve extensive clearing or modification of vegetation? (Provide adetailed account of the trees & vegetation affected by the project).

Environment Clearance of Proposed Office Building “Shalimar Iridium ”, At TC/G-1/1,Vibhuti Khand, Gomti Nagar, Lucknow, U.P.

---------------------------------------------------------------------------------------------------------------------

www.dasindia.org Page 20

There are no significant vegetation, except some ground cover within the site thus no extensive

clearance or modification of vegetation.

3.3 What are the measures proposed to be taken to minimize the likely impacts on important sitefeatures? (Give details of proposal for tree plantation, landscaping, creation of water bodies etcalong with a layout plan to an appropriate scale).

Due care will be taken to protect the important site features:

Tree plantation will be done to protect the site features such as topsoil erosion, ground water

attenuation and avoiding contamination by leachate.

The excavated soil will be stored at earmarked places protected from contamination and from

polluting the existing features and will be used for surface leveling and for creation of

landscaped areas.

Adequate measures will be taken to minimize the likely impacts of the proposed project on the

surrounding as well as the project site itself and documented in the Environmental Management Plan.

General principles in greenbelt design considered for this study area:

Type of pollution likely air, noise, and water and land pollution generated from the activities at

the site.

Agro-climatic zone and sub-zone where the greenbelt is located

Water quantity and quality available in the area

Soil quality in the area.

Total no. of trees required: 1 Tree/80sqm of open area=3705.07/80= 46

Proposed: 60Trees

Total soft green area proposed for project is 551.0 m2 (10.13% of plot area). A combination of

evergreen and ornamental flowering trees, palms, shrubs and ground covers will be planted along the

sides of the roads and in open spaces & setback area within the complex.

Landscaping is an important element in altering the microclimate of a place. Proper landscaping

reduces direct sun from striking the buildings and heating up building Surfaces, prevents reflected

light carrying heat into a building from the ground or surfaces, creates different airflow patterns and

can be used to direct or divert the wind advantageously by causing a pressure difference. Shade

created by trees and the effects of grass and shrubs reduce air temperature adjoining the building and

provide evaporative cooling. A study shows that the ambient air under a tree is 20C to 2.50C lower

than that for adjacent un-shaded areas.

Environment Clearance of Proposed Office Building “Shalimar Iridium ”, At TC/G-1/1,Vibhuti Khand, Gomti Nagar, Lucknow, U.P.

---------------------------------------------------------------------------------------------------------------------

www.dasindia.org Page 21

Parks & Avenue Plantation

Ornamental trees with spreading branches, shade giving with colorful flowers for people to relax and

suitable patches of lawns, rockery with cactus and other small flowering xerophytic plants shall be

planted.

The plants should exhibit the following desirable characteristic in order to be selected for plantation.

a. Trees with colonial canopy with attractive flowering.

b. Trees with branching at 10 feet and above.

c. Trees with medium spreading branches to avoid obstruction to the traffic, fruit trees to be

avoided because children may obstruct traffic and general movement of public.

The selection of plant species for the development depends on various factors such as climate,

elevation and soil. The criteria are based on pollution mitigation capacity (including Particulate

matter), large leaf surface area, deep root system and less litter fall. Faster growing trees with lighter

canopy will be planted alternatively with relatively slow growing trees with wider canopy. Trees of

will be planted at 4.5 m intervals, 2.5 m away from the road curbing as per CPCB guidelines. Trees

will be planted along the periphery and roadside of the project. The list of plant species, which can be

suitably planted, and having significant importance are provided in Table-10.

Table-10: List of Plant Species to be planted in the Green AreaS. No. Scientific Name Standard

NameTime when

flowering/FruitingOccurs

1 Ailanthus excelsa Maharuk January- March2 Albizialabbeck Sirish January- March3 Alibiziaprocera SafedSirish January- March4 Alstoniascholaris Chitwan January- April5 Anthocephaluscadamba Kadamb August-October6 Azadirachtaindica Neem June-July7 Bauhinia variegata Kanchan May-June8 Buteamonosperma Palash February-April9 Cassia Fistula Amaltas March-June10 Emblicaofficinalis Amla January11 Erythurinaindica Dadap July-August12 DelonexRagia Gulmohar February-June13 Mangiferaindica Aam April-July14 Nyctanthesarbortristis Harsingar Throughout the year

4.0 FAUNA

4.1 Is there likely to be any displacement of fauna- both terrestrial and aquatic or creation ofbarriers for their movement? Provide the details.

Environment Clearance of Proposed Office Building “Shalimar Iridium ”, At TC/G-1/1,Vibhuti Khand, Gomti Nagar, Lucknow, U.P.

---------------------------------------------------------------------------------------------------------------------

www.dasindia.org Page 22

There is no displacement of fauna or creation of barriers for their movement

4.2 Any direct or indirect impacts on the avifauna of the area? Provide details.

There will be a positive impact on the avifauna of the area. Due to the provision of plantation on theproject site it is expected that site will attract avian fauna, bees, butterflies etc.

4.3 Prescribe measures such as corridors, fish ladders etc to mitigate adverse impacts on fauna.

As there is no displacement of fauna, no mitigation measures are required and provided.

5. AIR ENVIRONMENT

5.1 Will the project increase atmospheric concentration of gases & result in heat islands? (Givedetails of background air quality levels with predicted values based on dispersion modelstaking into account the increased traffic generation as a result of the proposed constructions).

Increased traffic generation due to project is not going to cause significant increase inatmospheric concentration of gases and will not result in heat island formation. The minorimpacts of emissions from traffic will be neutralized by developing a thick green belt alongthe periphery and internal road side.

During construction phase, dust emissions will be the main pollutants associated within on-site roads, (paved and unpaved), stockpiles and material handling.

Regular water sprinkling will be done and construction material will be transferred in truckscovered with tarpaulin.

The other major source of pollution during operational phase will be emissions from DG sets.

Adequate height of stacks will be provided to the DG sets as per guidelines of MoEF(as per

the Gazette of India Part II, Section 3, Sub-section (I) No. 318, dated July 11, 2002, is

given below, refer table no. 11) to facilitate the dispersion of flue gases into the atmosphere.

Table11: DG set Stack height Rule, as per MoEF

Environment Clearance of Proposed Office Building “Shalimar Iridium ”, At TC/G-1/1,Vibhuti Khand, Gomti Nagar, Lucknow, U.P.

---------------------------------------------------------------------------------------------------------------------

www.dasindia.org Page 23

Table 12: DG set Stack height (Provided)Nos. Capacity of DG set (KVA) Stack Height Provided

(m)2 250 kVA 6.0 m + Building Height

Low Sulphur diesel (LSD) will be used which will result in lower emissions and increasedefficiency.

Detailed air quality monitoring will be discussed in conceptual plan.

5.2 What are the impacts on generation of dust, smoke, odorous fumes or other hazardous gases?Give details in relation to all the meteorological parameters.

The impacts of dust and gaseous pollutants due to different construction activities will be localized.

All necessary measures will be taken.

I. Dust:

Sources: Site preparation, excavation, construction, traffic.

Type: Area Source, Line Source

Extent: Localized

• Water spraying at dust generation sources/area.

• All transportation vehicles will be suitably covered to prevent dust from the trucks,

overloading of the vehicles shall be avoided and all vehicles employed will be PUC certified.

II. Smoke:

Sources: vehicular exhaust, DG Set

Type: Line sources, Point Sources

Extent: Localized

Mitigation:

• D.G. set will be provided with adequate safe stack-height above the terrace level of the

building to regulate the emission within the permissible norms.

• Low-sulphur-content fuel will be used which will help to contain the emissions within the

permissible range.

III. Odorous fumes:

Sources: Unsanitized conditions, indoor finishing

Type: Gases, vapors, fumes, dusts, fibres, mists.

Extent: localized

Environment Clearance of Proposed Office Building “Shalimar Iridium ”, At TC/G-1/1,Vibhuti Khand, Gomti Nagar, Lucknow, U.P.

---------------------------------------------------------------------------------------------------------------------

www.dasindia.org Page 24

Mitigation:

• Avoid un sanitized conditions

• VOC free paints will be used

• Properly ventilated work spaceNo negative impact outside of site. Dust emissions from excavation, air emission from machinery

and other construction activities. Dust reduction measures such as road watering and periodic

maintenance of road, effective use of personal protective equipment. Most of the concrete to be used

at site, will be ready mix concrete available from nearby factories.

5.3 Will the proposal create shortage of parking space for vehicles? Furnish details of the presentlevel of transport infrastructure and measures proposed for improvement including the trafficmanagement at the entry & exit to the project site.

The project complex will have a bell mouth traffic entry/exit through 30 m wide road on north. All

internals roads are 7.2 m wide and 6m wide fire tender path. The entry/exit points have been marked

on the layout plan. Fire tender pathways shall be provided as per local bye laws. The entry/exit points

have been marked on the layout plan. The project site is well connected to network of roads leading

from various parts of the city.

Table 13: Parking CalculationsRequired Parking

According to State norms:

Commercial- 2 ECS per 100 m2 of FAR= {(14174/100)

x2}= 284 ECS

Total Required Parking 284 ECS

Parking Provided 386 Parking spaces

Parking ProvidedLocation General (ECS) Mechanized (ECS) Two WheelerUpper Basement - 150 60Lower Basement - 192 95Ground/ Surface - 44 45Total 386 ECS 200 Two-wheelerTotal 386 Parking Spaces

Environment Clearance of Proposed Office Building “Shalimar Iridium ”, At TC/G-1/1,Vibhuti Khand, Gomti Nagar, Lucknow, U.P.

---------------------------------------------------------------------------------------------------------------------

www.dasindia.org Page 25

5.4 Provide details of the movement patterns with internal roads, bicycle tracks, pedestrianpathways, footpaths etc., with areas under each category.

The site layout plan showing movement pattern is enclosed as Annexure.

5.5 Will there be significant increase in traffic noise & vibrations? Give details of the sources andthe measures proposed for mitigation of the above.

During the construction phase, some noise will be generated through the operation of construction

machines, excavators, construction vehicles, etc.

Following measures should be taken into consideration to mitigate the noise at construction site:

Efforts shall be made to the extent feasible not to use such excavation/ construction

machines, which generate noise levels much more than 85 dB (A),

Silencers shall be fitted on construction machines

Earmuff and other protecting, devices shall be provided to labour working in high noise

generation machines.

During post construction phase, not much noise is anticipated, on account of project being a mix use

complex. However, noise generated due to vehicular movement, operation and maintenance will be

mitigated by adopting following measures.

DG set will be silent type with anti vibration pads.

Administrative control by display of slogans and sinages

Green belt/plantation along the internal roads will also work as noise barriers.

5.6 What will be the impact of DG sets & other equipment on noise levels & vibration in &ambient air quality around the project site? Provide details.

Impacts on Air Quality due to DG Sets and construction equipments: Noise will be emitted during construction due to operation of construction machinery like

batching plant, concrete pumps, tower cranes, DG set, Air compressors etc.

Impact on onsite workers are expected to be highest. One of the major sources of noise during

operational phase will also be the diesel based generator.

Impacts on ambient air during operation phase would be due to emissions from the stacks

attached to stand by DG sets.

Mitigation Measures Workers shall be provided with PPE such as ear muffs, helmets, anti-vibration boots etc.

DG sets will comply with the applicable emission norm.

Adequate stack height for DG sets will be provided as per norms.

Environment Clearance of Proposed Office Building “Shalimar Iridium ”, At TC/G-1/1,Vibhuti Khand, Gomti Nagar, Lucknow, U.P.

---------------------------------------------------------------------------------------------------------------------

www.dasindia.org Page 26

Acoustic enclosures DG set with anti-vibration pad shall be used

Back up DG sets will be used only during power failure.

Monitoring of emissions from DG sets and ambient air quality will be carried out as per

norm.

6. AESTHETICS

6.1 Will the proposed constructions in any way result in the obstruction of a view, scenic amenityor landscapes? Are these considerations taken into account by the proponents?

The proposed construction in any way will not result in the obstruction of a view, scenic amenity or

landscapes, which has already been considered during planning.

The architecture of the proposed project will be in accordance with the architecture of the residential

buildings in the area. The project will have world-class ambience and state of art infrastructures.

The planning has been done in a way to present the best aesthetic view of the area with due

consideration that the project does not cause any obstruction of the natural beauty of the area.

6.2 Will there be any adverse impacts from new constructions on the existing structures? What arethe considerations taken into account?

There will be no impact on the existing structures in the vicinity. The development in the project-influenced area is as per the development plan. Hence, no adverse impacts are anticipated from newconstructions on the existing structures in this area.

6.3 Whether there are any local considerations of urban form & urban design influencing thedesign criteria? They may be explicitly spelt out.

The architectural design of the project is in accordance with the guidelines of local developmentauthority i.e. LDA and National Building Code of India.

6.4 Are there any anthropological or archaeological sites or artifacts nearby? State if any othersignificant features in the vicinity of the proposed site have been considered.

There is no anthropological or archaeological site within 5 km of the site. Few anthropological orarchaeological sites or artifacts are present in the city but not within 5 km radius. (as per ASI):Dilkusha Garden: 6.5 km (SW)

La Martiniere College: 6 km (SW)

Residency: 8.5 km (W)

Bada Imambara: 10 km (W)

Chota Imambara: 11 km (W)

7.0 SOCIO-ECONOMIC ASPECTS

Environment Clearance of Proposed Office Building “Shalimar Iridium ”, At TC/G-1/1,Vibhuti Khand, Gomti Nagar, Lucknow, U.P.

---------------------------------------------------------------------------------------------------------------------

www.dasindia.org Page 27

7.1 Will the proposal result in any changes to the demographic structure of local population?Provide the details.

As most of the workers/staff in construction as well as operation stages will be from the nearby

localities, villages and township, no significant change in the local demographic structure is

envisaged from the project. The complex decongests the adjoining cities to some extent and

redistributes the existing population of the city. Escalation in land price and increased job

opportunities will result in socio economic development of the area.

7.2 Give details of the existing social infrastructure around the proposed project.

The area is earmarked for Mix Use Development.

Infrastructure Services in the RegionEducational Facilities: Approx. Distance & DirectionSKD Academy 500 m (NE)IIM Lucknow 13.5 km (NW)Lucknow University 7.5 km (W)Integral University 10 km (N)Jaipuria School 2 km (S)City Montessori School 3.5 km (SW)KendriyaVidyalaya, Gomti Nagar 2.5 km (SW)Medical Facilities: Approx. Distance & DirectionSahara Hospital 2.3 km (SE)RML Hospital 825 m (W)SGPGI Hospital 15 km (S)KGMU 9 km (W)Balrampur Hospital 8.5 km (W)Vivekananda Hospital 7 km (W)Mayo Hospital 2.5 km (SW)Ford Hospital 2.5 km (SW)Villages: Approx. Distance & DirectionUttardhauna: 5 km (NE)Shahpur: 3.8 km (NE)Sarai Sheikh: 4 km (E)Malhaur: 3km (SE)Recreational Areas: Approx. Distance & DirectionDr. Ambedkar Park 4 km (SW)Lohiya Park 3 km (SW)Janeshwar Mishra Park 4 km (S)Lucknow Zoo 6 km (SW)Waves Mall 1.5 km (W)

Environment Clearance of Proposed Office Building “Shalimar Iridium ”, At TC/G-1/1,Vibhuti Khand, Gomti Nagar, Lucknow, U.P.

---------------------------------------------------------------------------------------------------------------------

www.dasindia.org Page 28

Patrakarpuram Market 2 km (SW)

7.3 Will the project cause adverse effects on local communities, disturbance to sacred sites or othercultural values? What are the safeguards proposed?

The project will provide employment to people from all walks of life: Construction, Construction

related materials, Engineering, Medicine, Landscapists, Animal Husbandry, Facility Management,

Education, Information Technology, Administration etc. Better job opportunity for men and women,

better utilization of land, preservation of environment, and infrastructure development. All the

sacred sites or cultural values will not be affected by any means during or after construction but it

will enhance the values of sacred places. The project will not have any adverse effect on the local

communities. Since the project related activities are confined within the premises no adverse

impacts on the surrounding features are envisaged. Detailed project benefits are mentioned in

Section 6 of conceptual plan.

Safeguards

The social management plan has been designed to take proactive steps and adopt best practices, which

are sensitive to the socio-cultural setting of the region.

8. BUILDING MATERIALS

8.1 May involve the use of building materials with high-embodied energy. Are the constructionmaterials produced with energy efficient processes? (Give details of energy conservationmeasures in the selection of building materials and their energy efficiency).

The major materials required for construction of the proposed project will be steel, cement, bricks,

metal, flooring tiles/stones, sanitary and hardware items, electrical fittings, water, etc.

Conventional construction material will be used outsourced from authorized vendors/sellers.

All items to be used in the proposed project will be as per the National Building Code

specification. If the building materials with high-embodied energy are locally available, it

will be used in construction.

Low embodied energy material like ready mix concrete, fly ash bricks will be used in

construction.

8.2 Transport and handling of materials during construction may result in pollution, noise &public nuisance. What measures are taken to minimize the impacts?

Mitigation Measures for Air Pollution (Construction Stage)To minimize the adverse impact due to air pollution during construction following measures will be

taken.

Environment Clearance of Proposed Office Building “Shalimar Iridium ”, At TC/G-1/1,Vibhuti Khand, Gomti Nagar, Lucknow, U.P.

---------------------------------------------------------------------------------------------------------------------

www.dasindia.org Page 29

Transportation of construction material will be provided with suitable covering like tarpaulin

cover.

Water sprinkling shall be done at the location where dust generation is anticipated.

Raw material handling yard will be enclosed from all sides.

To minimize the occupational health hazard, proper personal protective gears i.e. mask shall

be provided to the workers who are engaged in dust generation activity.

The trucks used for transport will be thoroughly checked for emission parameters and

properly maintained.

The raw materials transport will be avoided during the peak hours to reduce traffic load.

Mitigation measures for Noise Pollution (Construction Stage)

Administrative as well as engineering control of noise will be implemented. To prevent

occupational hazard earmuffs / earplugs shall be given to the workers working around the

operating plant and machinery emitting high noise levels.

Use of such plant or machinery shall not be allowed during night hours.

Careful planning of machinery operations and scheduling of operations shall be done to

minimize such impacts.

8.3 Are recycled materials used in roads and structures? State the extent of savings achieved?

Waste from construction like excavated earth, empty cement bags, paper, cartoon and iron rods etc

will be reused/ recycled as far as possible. Empty plastic cement bags and other plastic waste will be

used in road construction. The waste generated as brick bats, plaster cement, reinforcement steel,

concrete falls, ceramic tiles, etc will be used as a construction material.

8.4 Give details of the methods of collection, segregation & disposal of the garbage generatedduring the operation phases of the project.

The philosophy of solid waste management will be to encourage the four R’s of waste i.e. wastereduction, reuse, recycling, and recovery (materials & energy). Regular public awareness meetingswill be conducted to involve the residents in the proper solid waste management plan, options andtechniques.

Estimation of solid Waste

On the basis of the solid waste being collected in different cities, the per capita rate of solid waste

generation has been adopted as 0.25 kg per day per person for staff/employee and 0.15 kg per day per

person for visitors, Horticulture waste @ 0.0037 kg/m2/day, and e-waste @ 0.15kg/capita/year. Thus

the anticipated municipal solid waste worked out as below:

Environment Clearance of Proposed Office Building “Shalimar Iridium ”, At TC/G-1/1,Vibhuti Khand, Gomti Nagar, Lucknow, U.P.

---------------------------------------------------------------------------------------------------------------------

www.dasindia.org Page 30

Table 14: Solid waste generationS.No. Particulars Population Waste generated in

kg/day

1. Employee/Staff (@0.25 kg/day) 1420 355

2. Visitors (@0.15kg/day) 150 22.5

Total Solid waste generated Approx. 378 kg/day

Horticulture Waste (@ .0037/m2/day) 2Kg/Day

E-Waste (0.15 kg/C/year) <1 Kg/Day

STP sludge (dry weight) 3 kg/day

Segregation & Collection of waste

A floor to floor collection system through service lifts shall be provided for collection of solidwaste generated.

Adequate number of colored bins (green and Blue - separate for Bio-degradable and Non Bio-degradable) are proposed to be provided

Recyclable waste will be sold to authorized agencies. Hazardous waste (Spent Oil) & e-waste will be stored at separate place and handover to

authorized dealers of CPCB.

Litter bin will also be provided in open areas like parks & play grounds etc.

Transportation, Treatment & Disposal

Generated Solid waste shall be segregated & collected on common solid waste collection center at

site, and handed over to authorized recyclers for treatment and disposal.

Following steps have been proposed for collection, treatment and disposal of MSW:

Step 1: Segregation of MSW at source and collection from the premises

Step 2: Transportation of MSW

Step 3: Segregation of MSW for processing

Step 4: Shredding of the compostable waste to desired particle size

Step 5: Treatment of biodegradable waste through composting.

Step 6: Disposal of non biodegradable waste through authorized dealers.

Environment Clearance of Proposed Office Building “Shalimar Iridium ”, At TC/G-1/1,Vibhuti Khand, Gomti Nagar, Lucknow, U.P.

---------------------------------------------------------------------------------------------------------------------

www.dasindia.org Page 31

Fig 7: Waste Management Flow Diagram (Construction Phase)

Hazardouswaste

Fig 8: Waste Management Flow Diagram (Operational Phase)

Environment Clearance of Proposed Office Building “Shalimar Iridium ”, At TC/G-1/1,Vibhuti Khand, Gomti Nagar, Lucknow, U.P.

---------------------------------------------------------------------------------------------------------------------

www.dasindia.org Page 32

Hazardous WasteThe Project is a Building Construction Project in which no storage of hazardous chemicals (as per

MSIHC rules) will be done, except HSD (low sulphur variety) required to run standby DG sets.

Also, the quantity to be stored will be below the threshold limit specified in the MSIHC rules.

During construction paints, solvents, thinner, oil and lubricants will be stored for use which is

hazardous to health.

E-Waste

E-Waste (Management & Handling Rule, 2016) Electronic waste, popularly known as ‘e-waste’

can be defined as waste electrical and electronic equipments whole or in part or reject (such as

CDs, floppies, keyboards, monitors, power plug, bulbs, batteries, etc.) which have become

obsolete due to:

Advancement in technology

Changes in fashion, style and status

Nearing the end of their useful life.

Responsibility of Consumer or Bulk Consumer

According to E-Waste (Management & Handling Rule, 2016) responsibility of Consumer or

Bulk Consumer is given below:

Consumer or Bulk Consumer of electrical and electronic equipment shall ensure that e-waste

generated by them is channelized to authorized collection centers or registered dismantlers or

recyclers or is return back to the pick-up or take back services provided by the producers.

Bulk consumers shall maintain records of e-waste generated by them in Form-2 and make

records available to UPPCB.

The e-waste generated from the proposed project would be suitably managed through

assistance from e-waste handling agency.

The mantra of "Reduce, Reuse, and Recycle" applies here also.

Reduce generation of e-waste through smart procurement and good maintenance.

Reuse still functioning electronic equipment by donating or selling it to someone who can

still use it.

Recycle those components that cannot be repaired. To identify organizations who reuse orrecycle electronics.

9. ENERGY CONSERVATION

9.1 Give details of the power requirements, source of supply, backup source etc. What is the energyconsumption assumed per square foot of built-up area? How have you tried to minimize energyconsumption?The details of power requirement, source, and backup power arrangements are given below:

Environment Clearance of Proposed Office Building “Shalimar Iridium ”, At TC/G-1/1,Vibhuti Khand, Gomti Nagar, Lucknow, U.P.

---------------------------------------------------------------------------------------------------------------------

www.dasindia.org Page 33

Table 15: Power Requirement, Source and Backup ArrangementPower Requirement 2000 KVA

Source UPPCLBackup power supply arrangement 2 DG sets of 250 kVA

Total: 500 kVA

Stack Height 6.0 m above highest building

Energy Conservation Measures & Management Plan:In the Operational Phase, appropriate energy conservation measures & management plan will be

adopted in order to minimize the consumptions of non-renewable energy. The following practices

will be adopted:

Sl. Energy Efficient Features

1. Maximum utilization of natural light

2. CFL in the common areas

3. Use of solar lights in open areas and landscaped area with 50% dual lighting system.

4. All openings are shaded to reduce heat loss

6. U-values of roof, external wall and fenestration will meet requirements as specified in the

Energy Conservation Building Code (ECBC)

7. The water supply pumping system will be provided with variable speed drive to conserve

energy at part load.

8. Compliance for Window glazing U-values if window to wall ratio is more than 30%

9. Application of Day light sensor, motion sensor and timers.

10. Use of BEE 4-star rated or equivalent appliances

11. Orientation of building towards north, appropriately designed windows, and double light

roof so that maximum day lightening to all spaces is achieved

12. Minimum glazing factor in regularly occupied spaces

Permissible U-values (W/m2°C) as per ECBC:

Roof: 0.409, External wall: 0.44, Fenestration: 3.3

9.2 What type of and capacity of power back up to you plan to provide?

Backup power supply arrangement 2DG sets of 250 kVATotal: 500 kVA

Backup power units will be provided for the following emergency power back-up requirement:

Staircase, common area lighting and elevators of individual building.

Environment Clearance of Proposed Office Building “Shalimar Iridium ”, At TC/G-1/1,Vibhuti Khand, Gomti Nagar, Lucknow, U.P.

---------------------------------------------------------------------------------------------------------------------

www.dasindia.org Page 34

Receiving station and substation lighting. Sewage treatment plant. Firefighting equipment. Telltale lights in common amenity building.

9.3 What are the characteristics of the glass you plan to use? Provide specifications of itscharacteristics related to both short wave and long wave radiation?

This is a Mix Use project where the use of glass would be very less, i.e. for windows etc. Plain glass

will be used for fenestration purposes only. Characteristics are as under*:

Parameters 5 mm clear 8 mm clear

Light transmission 90% 88%

Light reflectance 8% 8%

Solar factor 85% 81%

Shading coefficient 0.97 0.94

Solar energy:

Transmission 82% 77%

Reflectance 8% 7%

Absorption 10% 16%

U –value 5.8 W/m2K 5.7 W/m2K

*Source: www.sunguardglass.com

9.4 What passive solar architectural features are being used in the building? Illustrate theapplications made in the proposed project.

Building design and envelope may be optimized through selection of appropriate wall and

roof construction and through adoption of solar passive measures after studying the sun path analysis

to provide shading devices for windows and roof which would reduce energy demand.

Components of the solar architectural features in the proposed building:

• Adequate natural cross-ventilation.

• Sufficient day-lighting with direct heat gains

• Adequate shading devices

• Natural cross ventilation: There will be adequate open able windows and doors in the living

spaces, kitchens & bathrooms.

• Window: The major expanse of windows in a passive solar energy structure will be south facing

solar windows. Whole design planning includes following considerations: the impact of heat

gain in the summer; views; natural lighting; and privacy requirements in determining the

placement and size of windows in the structure. For the most part, window areas on East

Environment Clearance of Proposed Office Building “Shalimar Iridium ”, At TC/G-1/1,Vibhuti Khand, Gomti Nagar, Lucknow, U.P.

---------------------------------------------------------------------------------------------------------------------

www.dasindia.org Page 35

and West facing walls will be kept as small and as minimal as will be consistent with

interior requirements.

Shading: South facing glass can be a source of overheating during summer months.

The potential for overheating will be controlled by roof over carefully designed to shade the

glass during the summer (sun higher in the sky) but not block sunlight during the winter (lower in the

sky).

9.5 Does the layout of streets & buildings maximize the potential for solar energy devices? Haveyou considered the use of street lighting, emergency lighting and solar hot water systems foruse in the building complex? Substantiate with details.

Yes, the layout of streets & buildings has been designed to maximize the potential for solar

energy. Solar energy will be used for street lighting. 50% of street lights will be powered by solar

lighting. Also automatic light sensors will be installed to facilitate automatic off-on action resulting

in significant amount of energy saving. Projections, shades, façade elements will reduce the summer

heating of the building. Green areas and open spaces will achieve a reduction in heating in summer.

9.6 Is shading effectively used to reduce cooling/heating loads? What principles have been used tomaximize the shading of Walls on the East and the West and the Roof? How much energysaving has been effected?

Shading options wherever feasible will be used for energy saving. Roofs will be painted with

reflective, aluminum based paints with solar reflectance ranging from 0.3-0.6. This will result in less

absorption of sunlight causing 40% back reflection and less heating of building structures during

summer season. This will effectively reduce the heat load of the building envelope. Projections,

shades and façade elements will reduce the summer heating of the building. Green areas and open

spaces will achieve a reduction in heating in summer.

9.7 Do the structures use energy-efficient space conditioning, lighting and mechanical systems?

Provide technical details. Provide details of the transformers and motor efficiencies, lighting

intensity and air-conditioning load assumptions? Are you using CFC and HCFC free chillers?

Provide specifications.

Suitable energy optimization will be adopted during the calculation of energy load of the proposed

project. Compact fluorescent lamps (CFL) will be used in place of incandescent and halogen lamps

in all common areas and basement parking.

Energy Efficient Features:

Maximum utilization of natural light.

Environment Clearance of Proposed Office Building “Shalimar Iridium ”, At TC/G-1/1,Vibhuti Khand, Gomti Nagar, Lucknow, U.P.

---------------------------------------------------------------------------------------------------------------------

www.dasindia.org Page 36

CFL& T-5 lighting fixtures in the common areas and Truelite fluorescent lamps inbasements.

Use of solar lights partly in open areas and landscaped area. Appropriate thermal insulation in walls and roofs to reduce heat gain and loss.

Glazing glass: to keep the U value as per ECBC. External glazing will be below 40% of the total vertical Surface as per ECBC.

9.8 What are the likely effects of the building activity in altering the microclimates? Provide a self-assessment on the likely impacts of the proposed construction on creation of heat island &inversion effects?

Heat emission from the proposed project can be from the following sources:• Heat absorbed and radiated from the paved and concrete structures.

• Increased population for a particular stretch of land.

Any building activity would alter the microclimate of a site and it is inevitable that wind patterns and

thermal gain patterns on a site would be changed. But the proposed building has been carefully

designed to modify the microclimate so as to improve overall thermal comfort and reduce energy

consumption. Hard paving onsite has been reduced to the extent possible to reduce the heat island

effects (surface). The project will have good tree plantation which will further help to reduce the heat

island effect.

To reduce the heat load reflective insulated glass shall be used in fenestrations to cut on heat loads

and subsequently capital and operating cost of air conditioning.

Shade giving trees will be planted near the east and west side windows which will affect the

microclimate and will provide cooling effect in summers.

The building will use energy efficient and environmental friendly designs that will control

formulation of heat island effect. There will also be sufficient green cover at the site to reduce

formation of heat island.

9.9 What are the thermal characteristics of the building envelope? (a) Roof; (b) external walls; and(c) fenestration? Give details of the material used and the U-values or the R-values of theindividual components.

The U-values of the roof, external wall and fenestration of the building will meet the requirements asspecified in the Energy

Table 16: Conservation Building Code (ECBC)S.No. Component Material Used Permissible U-Value as per ECBC

(W/m2-0C)1 Roof Concrete 0.409

Environment Clearance of Proposed Office Building “Shalimar Iridium ”, At TC/G-1/1,Vibhuti Khand, Gomti Nagar, Lucknow, U.P.

---------------------------------------------------------------------------------------------------------------------

www.dasindia.org Page 37

2 External wall Brick 0.443 Fenestration Glass Facade 3.3

Heat transfer co-efficient (in Btu/hr. sq.ft.Deg F) are as under:

• Exposed brick wall: 0.07• Shaded slab (non insulated): 0.40• Insulated shaded slab: 0.12• Ceiling (non insulated): 0.48• Ceiling (insulated): 0.12• Floor (insulated): 0.12• Floor (non insulated): 0.48

9.10 What precautions & safety measures are proposed against fire hazards? Furnish details ofemergency plans.

Adequate fire protection facilities will be installed including fire detectors, fire alarm and fire

fighting system to guard the building against fires. All fire protection facilities are designed as per the

latest National Building Code. The approvals in this regard have been obtained.

Fire Fighting System

The basic system for Fire Fighting shall be designed as per the provisions of the National Building

Code

Overhead water storage tank of capacity 25 KL will be proposed to made. Water from thesereserve tanks will be drawn by electrically driven fire pump of capacity 900 LPM andsupplied into hydrant ring main and wet riser system. The system will be kept pressurized atall times in order to ensure instant availability of water at all points.

Fire SafetyThe building materials shall be of appropriate fire resistance standard. Further, design of building

will be as per NBC, 2005, which include following provisions:

The electrical systems shall be provided with automatic circuit breakers activated by the rise

of current as well as activated by over current.

Fire detection systems

Manual operated Fire Alarm systems at appropriate places

Double door and Double stairs in building will be provided

Bell Mouth traffic entry/exit through service road

Access for fireman

Provision of Mechanical ventilation for air conditioned room will be made.

Adequate fire fighting requirement shall be taken into account while designing the electrical

distribution system

Environment Clearance of Proposed Office Building “Shalimar Iridium ”, At TC/G-1/1,Vibhuti Khand, Gomti Nagar, Lucknow, U.P.

---------------------------------------------------------------------------------------------------------------------

www.dasindia.org Page 38

Sprinkler system The Basements will be equipped with sprinkler system of fire fighting and the sprinkler heads

shall be distributed as per the National Building Code. The sprinkler pump will be suitable for

automatic operation when there is a drop of pressure in the system. Sprinklers shall be

provided throughout the basement area with separate sprinkler risers as required. All the

risers shall be provided with installation control valves and a hydraulic alarm. An electrical

sensor flow switch will be provided on each floor and connected to the fire control panel in

the security room, to identify the affected floor immediately.

The building will conform to the provisions of National Building Code as well as the

provisions of State Fire Safety by Laws and will be provided with adequate arrangement to

overcome fuel hazards to the satisfaction of authority.

9.11 If you are using glass as wall material provides details and specifications including emissivityand thermal characteristics.

Glass will not be used as wall material except in windows as it is a housing project.

9.12 What is the rate of air infiltration into the building? Provide details of how you are mitigatingthe effects of infiltration.

The project will not be centrally air-conditioned. Hence, air infiltration will not cause any energy loss

or undue load as would have been possible in case of air-conditioned units. Besides this, adequate

provisions will be made to mitigate the effects of air infiltration.

Infiltration has been minimized through the use of EPDM gaskets in structural glazing and weather

seals in the case of windows.

9.13 To what extent the non-conventional energy technologies are utilized in the overall energyconsumption? Provide details of the renewable energy technologies used.

Solar Energy will be used for external lighting as far as possible and economical viable. No other

technologies are viable in the case. Solar Water Heating Systems may be used, if possible. There is

no wind energy available nearby. As regards to biogas, it is financial not viable for as the organic

waste generated isn’t too high.

10. Environment Management Plan

The Environment Management Plan would consist of all mitigation measures for each item-

wise activity to be undertaken during the construction, operation and the entire life cycle to

minimize adverse environmental impacts as a result of the activities of the project. It would also

Environment Clearance of Proposed Office Building “Shalimar Iridium ”, At TC/G-1/1,Vibhuti Khand, Gomti Nagar, Lucknow, U.P.

---------------------------------------------------------------------------------------------------------------------

www.dasindia.org Page 39

delineate the environmental monitoring plan for compliance of various environmental regulations. It

will state the steps to be taken in case of emergency such as accidents at the site including fire.

Environment Management Plan is discussed in Conceptual Plan.