Author's personal copy Power generation from geothermal resources in Turkey
Geothermal Power Generation Project: Environmental Monitoring ...
-
Upload
khangminh22 -
Category
Documents
-
view
7 -
download
0
Transcript of Geothermal Power Generation Project: Environmental Monitoring ...
Environmental Monitoring Report
Project Number: 52282-001 Semestral Report July to December 2021 April 2022
Indonesia: Geothermal Power Generation Project
Prepared by PT Geo Dipa Energi (Persero) for the Asian Development Bank.
This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.
In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
INO: Geothermal Power Generation Project
Semi-Annual Environmental Monitoring Report
INDONESIA
PT Geo Dipa Energi (Persero)
ADB Loan No. 33928 INO
Geothermal Power Generation Project
Reporting Period: 1 July 2021 to 31 December 2021
Date: 31 January 2022
SEMR Report Number: 02
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
i
VALIDITY SHEET
Position Signature
Prepared by
Health and Safety Assistant
Manager
Date:
Environment Safeguard
Assistant Manager
Date:
Approved by
HSE and Safeguard
Manager
Date:
Project General Manager
Date:
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
ii
TABLE OF CONTENT VALIDITY SHEET .................................................................................................................................... i
TABLE OF CONTENT ............................................................................................................................ ii
LIST OF TABLES .................................................................................................................................... iii
LIST OF FIGURES .................................................................................................................................. iii
LIST OF APPENDICES ......................................................................................................................... iv
1 ENVIRONMENTAL SAFEGUARDS SUMMARY ........................................................................ 1
1.1 Summary of Project Progress ................................................................................................. 1
1.2 Summary of EMP Implementation ........................................................................................ 12
Dieng-2 Sub-Project ...................................................................................................... 12
Patuha-2 Sub-Project .................................................................................................... 13
1.3 Summary of EMP Monitoring ................................................................................................ 16
1.4 Summary of Complaints, Issues and Corrective Action ........................................................ 16
Dieng-2 Sub Project ...................................................................................................... 16
Patuha-2 Sub Project .................................................................................................... 16
2 SAFEGUARDS STAFF, TRAINING AND DOCUMENTATION ................................................ 15
2.1 Implementation Arrangements .............................................................................................. 15
2.2 Training and Capacity Building ............................................................................................. 16
2.3 ADB Approvals ...................................................................................................................... 20
2.4 National Approvals ................................................................................................................ 20
2.5 Construction Environmental Management Plan (CEMP) Approvals..................................... 22
3 EMP IMPLEMENTATION .................................................................................................... 23
3.1 Environmental Performance .................................................................................................. 23
Environmental Performance of Dieng-2 Sub Project .................................................... 23
Environmental Performance of Patuha-2 Sub Project .................................................. 47
3.2 Health and Safety Performance ............................................................................................ 97
Health and Safety Compliance of Dieng-2 Sub Project ................................................ 97
Health and Safety Compliance of Patuha-2 Sub Project ............................................ 109
Further Actions To be Taken ....................................................................................... 140
3.3 Biodiversity Action Plan Implementation ............................................................................. 141
4 EMP MONITORING ................................................................................................................ 143
4.1 Environmental Quality Monitoring ....................................................................................... 143
Summary of Results - Noise ....................................................................................... 151
Summary of Results – Surface Water Quality. ........................................................... 152
Summary of Results – Groundwater Quality. .............................................................. 153
Summary of Results – Air Quality. .............................................................................. 153
Environmental Quality Monitoring Requirements of Patuha-2 .................................... 154
4.2 Construction Phase Affected People Consultation ............................................................. 157
5 COMPLAINTS, ISSUES, CORRECTIVE ACTION ................................................................. 162
5.1 Information Disclosure ........................................................................................................ 162
5.2 Grievance Redress Mechanism .......................................................................................... 163
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
iii
5.3 Corrective Actions ............................................................................................................... 177
6 CONCLUSION and RECOMMENDATION ............................................................................. 178
6.1 Conclusion ........................................................................................................................... 178
6.2 Recommendations .............................................................................................................. 178
APPENDICES ..................................................................................................................................... 179
LIST OF TABLES
Table 1. Project Progress Summary ....................................................................................................... 1
Table 2 Summary of EMP Monitoring ................................................................................................... 16
Table 3 Summary of Complaint and Issue Dieng-2 Sub Project .......................................................... 16
Table 4 Summary of Complaint and Issue Patuha-2 Sub Project ........................................................ 17
Table 5 Status of Environmental Safeguard Roles ............................................................................... 15
Table 6 Training Framework and Agenda for Introductory Training on ADB’s Environmental and Social Saeguard ............................................................................................................................................... 17
Table 7 Status of Environmental Safeguard Documents ...................................................................... 20
Table 8 Status of National Approvals for Environmental Documents ................................................... 20
Table 9 CEMP Approval Status ............................................................................................................ 22
Table 10 Status of EMP Compliance Dieng-2 ...................................................................................... 23
Table 11 EMP Actions Needed for Compliance – Dieng-2 ................................................................... 46
Table 12 EMP Compliance Outstanding Issues from Previous Report – Dieng-2 ............................... 47
Table 13 Status of EMP Compliance at Patuha-2 ................................................................................ 47
Table 14. EMP– Actions Needed for Compliance – Patuha-2 .............................................................. 96
Table 15 EMP Compliance Outstanding Issues from Previous Report – Patuha-2 ............................. 96
Table 16 Status of Health and Safety Compliance All Subproject Dieng-2 ......................................... 97
Table 17 Status of Health and Safety Compliance of Patuha-2 (Drilling) ........................................... 109
Table 18 Status of Health and Safety Actions Needed for Compliance - All subprojects .................. 140
Table 19 EMP Compliance Outstanding Issues from Previous Report(s) – All subprojects .............. 140
Table 20 Biodiversity Action Plan Implementation .............................................................................. 141
Table 21 Status of Biodiversity Actions Needed for Compliance - All subprojects ............................. 142
Table 22 Implemented EMP Environmental Quality Monitoring ......................................................... 143
Table 23 Monitoring Biodiversity Action Plan Requirement ................................................................ 149
Table 24 EMP Environmental Quality Monitoring Implementation (Civil Work) .................................. 154
Table 25 Construction Phase Affected People Consultation Dieng-2 Sub Project............................. 157
Table 26 Construction Phase Affected People Consultation Patuha-2 Sub Project........................... 159
Table 27 Information Disclosure ......................................................................................................... 162
Table 28 Grievance Redress Committee ............................................................................................ 164
Table 29 List of Complaint(s) Received in January to December 2021 periods for Dieng-2 Sub-Project ............................................................................................................................................................ 166
Table 30 List of Complaint(s) Received in January to December 2021 periods for Patuha-2 Sub-Project ............................................................................................................................................................ 170
Table 31 Project Complaints or Issues – Not resolved from previous reports .................................... 176
Table 32 Corrective Actions Issued .................................................................................................... 177
LIST OF FIGURES Figure 1 Temporary Dumping Area for Drill Cutting ............................................................................. 14
Figure 2 Maintenance of Sewage Treatment Plant .............................................................................. 15
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
iv
LIST OF APPENDICES Appendix A Introductory Training on ADB’s Environmental and Social Saeguard
Appendix B Environmental Quality Monitoring Result
Appendix C HSE Join Inspection Report
Appendix D ACM Demolishing Report
Appendix E Revegetation in Patuha
Appendix F Sidendang Spring Water Analysis Result
Appendix G Socialization to the Workers prior to Drilling Activity
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
1
1 ENVIRONMENTAL SAFEGUARDS SUMMARY
1.1 Summary of Project Progress
The second Semi-annual Environmental Monitoring Report (SEMR) covers the working period from 1
July to 31 December 2021 for ADB Loan No. 33928 INO: Geothermal Power Generation Project.
1. The SEMR is prepared to fulfil the safeguard policy requirement of ADB;
2. The SEMR is prepared by PMU (Geodipa) and PMC (AECOM); and
3. Table 1 briefly summarises the project progress for contract award; briefly summarises the project
progress for contract award, construction, and critical activities in this reporting period.
Table 1. Project Progress Summary
Safeguards Category Environment B
Reporting Period: July to December
2021 Date Last Report Issued: January to June 2021
Contracts Awarded to
Date:
No Work Contract Contractor Instruction
to Perform
End of
Contract
1 Civil Work for Dieng
and Patuha
PT Supraco 27 July 2021 26 May 2022
2 Rig Bundling Dieng PT Plumpang
Raya Anugrah
11 October
2021
2 April 2024
3 Rig Bundling Patuha JV PT Air
Drilling – PT
Asia Petrocom
Services
07
September
2021
07
September
2023
4 Cementing Dieng PT Halliburton
LSI
15 October
2021
21 May 2024
5 Cementing Patuha PT Halliburton
LSI
15 October
2021
21 November
2023
6 Directional Drilling
Dieng
PT Halliburton
LSI
15 October
2021
21 May 2024
7 Directional Drilling
Patuha
PT Halliburton
LSI
15 October
2021
21 November
2023
8 Mud Engineering
Dieng
PT Baker
Hughes Ind.
29 October
2021
14 May 2024
9 Mud Engineering
Patuha
PT Prima
Hidrokarbon
Indonesia
29 October
2021
22 November
2023
10 Aerated Drilling PT Aerated
Drilling
1 October
2021
25 March
2024
11 Fishing and Milling PT Baker
Hughes Ind.
NA 05 May 2024
12 Wireline Logging JV Tiger and
NPS Bahrain
03 November
2021
05 March
2024
13 Well Testing PT
Depriwangga
15 October
2021
1 April 2024
14 PMC Sub Surface PT Jacobs
Group
Indonesia
30
September
2021
01 November
2024
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
2
15 PMC General PT Aecom
Indonesia
05 July 2021 05 October
2025
Construction Progress to
Date:
As of 31 December 2021, during this reporting period, construction
activities covered 4 main activities in Dieng and Patuha sites included:
1. Field Activities in Dieng
2. Driling in Dieng
3. Field Activities in Patuha
4. Drilling in Patuha
Project progress as of 31 December 2021 was 19.21% for Dieng and
13.44% for Patuha.
Key Sub-project
Activities in this
Reporting Period:
Dieng-2
1. Dieng Field Activities
Dieng's field activities comprised well pad alignment, demolition and
removal of asbestos-containing materials (ACM) from ex PLN mess
building, draining silica from the pond and pond revitalization, road and well
pad preparation and operation and maintenance activities to support drilling
Dieng-2. Due to the incomplete land acquisition and asset removal process
in Pad 9, the geomembrane installation was postponed, and the contract
has been extended until October 2022. For the long lead items (components
which the GDE has given the contractor written approval to purchase in
advance of the date of execution of the contract), the drilling casing was
delivered in August 2021, while 4/5 batches of wellhead were delivered to
Dieng and Patuha on December 2021. The remaining will be provided in
January 2022.
Summary of Dieng Field Activities
No Task Key Activities Status Next Step
1 Installation
Geomembrane
work for Water
Pond and Mud
Pond Project
Dieng-2 Patuha-2
1. Material Mobilization and
Unloading
2. Preparation work and
fabrication of material
onsite
3. Installation
Geomembrane at Pad 15
4. Installation
Geomembrane at Pad 14
5. Installation
Geomembrane at WPS
Kalitulis
6. Installation
Geomembrane at TPS
Sileri
7. Installation
Geomembrane at Pad 29
8. Installation
Geomembrane at Pad 31
9. Installation
Geomembrane at Pad 30
10. Installation
Geomembrane at Pad 09
11. Installation
Geomembrane at Pad 07
12. Installation
Geomembrane at Pad 38
1. Installation
Geomembrane
at Pad 15:
COMPLETED
2. Installation
Geomembrane
at Pad 14:
COMPLETED
3. Installation
Geomembrane
at Pad 31:
COMPLETED
4. Installation
Geomembrane
at TPS Sileri:
COMPLETED
5. Installation
Geomembrane
at Pad 29:
COMPLETED
6. Installation
Geomembrane
at Pad 32:
COMPLETED
7. Installation
Geomembrane
Installation
Geomembra
ne at pad 30
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
3
13. Installation
Geomembrane at Pad 32
at Pad 14:
COMPLETED
2 Construction Work
of Supporting
Facilities for Drilling
Project Dieng-2
• Revitalization of the
explosive area pad 12
• Cutting Storage at Pad 33
• Water Inlet and Outlet
Siterus
• Revitalization
of the
Explosive
Area pad 12
(Finished)
• Cutting
Storage at
Pad 33
(Finished)
• Water Inlet
and Outlet
Siterus (In
Progress)
Installation
Sluice Gate
(sliding water
gate) at
Siterus
3 Well pad
Alignment, Draining
Silica and Pond
Revitalization
• Preparation
• Draining and Silica and
Pond Revitalization at
Pad 7, Pad 29
• Ex Mess PLN Demolition
• Well pad Alignment at
WPS Siterus, Pad 7, Pad
38, Pad 9, Pad 30
• Preparation
- Well pad
Alignment at
WPS Siterus
- Draining And
Silica Pond
Revitalization
at Pad 29 (On
Progress)
- Well pad
Alignment at
Pad 38
- Excavation at
Mud Pond
Wellpad 38
- Excavation For
Drainage
- Well pad
Alignment at
Pad 38
- Hole at Mud
Pond
Wellpad 38
- Excavation
Water Pond
Area
4 Road and Wellpad
Preparation Dieng-
2
- Work Preparation
- Well pad Preparation
- Work of BRC Fence
- Concrete Panel Fence
Work
- Well pad Slope Geotextile
Work
- Cellar Box Work
- Installation Pipe
Conductor
- Pad 31
- Clearing and
Excavation
Access Road
Wellpad area
- Quality
Concrete
Testing (K
250)
- Geotextile
Installation
- Soil
Excavation for
Fence BRC
sloop
COMPLETED
- Material
Onsite for
BRC Fence:
COMPLETED
- Concrete
Sloop of BRC
fence:
COMPLETED
- Pad 09
- Finishing
Cellar
- Leveling area
rig footprint
- Geotextile
Installation
Pad 31
- Material on
site for
BRC fence
work
- Concrete
Sloop of
BRC fence
Pad 09
- Quality
Concrete
Testing
K250
- Clearing
Area
Wellpad
- Soil
Excavation
for Panel
Fence
sloop
(COMPLE
TED)
Pad 38
- Preparing
for clearing
and
levelling
well pad
area
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
4
- Quality
Concrete
Testing K250:
completed
- Clearing area
Wellpad:
completed
- Soil
Excavation for
panel fence
Sloop:
COMPLETED
- Pad 38
- Survey and
Measurement
area for well
pad Pavement
5 Operation and
Maintenance
activities to Suppor
Drilling Dieng-2
- Supporting Well test
- Maintenance Electrical
Project Facilities
- Maintenance of new well
valve after drilling
- Maintenance Civil
- Well pad Repair
- Install- remove water
supply pipe
- Maintenance Water
Supply pipe
- Cleaning
Sediment at
Pond 31
- Dewatering At
Pond 29 and
Sileri
- Leveling WPS
Sidolok
- Repairing
Wellpad 31
- Greasing
valve waterline
- Dewatering at
pond 09
- Clearing
Drainage at
Pad 38 and
Temporary
Office
- Uninstall pilot
plant and
Clearing area
pad 07
- Repairing
PPDU fence at
Pad 38
- Cleaning
Sediment at
Pond 31
- Dewatering
at Pond 29
and Sileri
- Clearing
area at pad
14
- Leveling
Booster and
Electrical
check at
Karang
Tengah
- Dewatering
at pond 31
- Landslide
Prevention
at Sileri
6 Demolishing
Asbestos
Containing Material
(ACM) from Ex
Mess PLN building
(PAD 38)
- Installing scaffolding
- Installing cover terpaulin
- Demolishing ACM
- Packaging and wrapping
ACM
- Dismantling scaffolding
and cover tarpaulin
- Sampling asbestos by
LPPKM FKM UI
- Transporting ACM to
PPLI
- Demolished
ACM
(COMPLETED)
- Packaging and
Wrapping ACM
(COMPLETED)
- Transporting
ACM to PPLI
(COMPLETED)
COMPLETED
7
Two flowmeters
installation for
water utilization
SIPA permit permit
(Izin Pengusahaan
Sumber Daya Air)
(Sidolok and Kali
Tulis)
- Select suitable flowmeter
with pump specification
- Purchasing flowmeter
- Installing flowmeter
- Function test /
commissioning
- Inspection by BBWSSO
(Balai Besar Wilayah
Sungai Serayu dan Opak)
- Selected
suitable
flowmeter with
pump
specification
(completed)
- Purchased
flowmeter
(completed)
COMPLETED
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
5
- Installed
flowmeter
(completed)
- Function test /
commissioning
(completed)
- Inspection by
BBWSSO
(Balai Besar
Wilayah Sungai
Serayu dan
Opak)
(completed)
2. Drilling Activities in Dieng
Before rigs and crews were moved into place to start drilling, the
management and planning team performed a ‘Drill Well On Paper’ (DWOP). All technical decision-makers and stakeholders brainstormed
and anticipated well drilling and completion. Attendees represented at
least all drilling services companies and they conducted a detailed review
of the current plans and determine potential pitfalls and design choices
that affect efficiency. ‘The team created a comprehensive set of policies
and procedures for the rig, with implementation procedures and potential
contingency action points. ‘Drill Well On Paper’ (DWOP) have conducted for Patuha on 2-5 November 2021 and Dieng on 12-15 November 2021.
ITP Mobilization of Rig Bundling Contractor (PRA) for Dieng was issued
on 13 October 2021. First Spud In Well SLR-Q-31A has conducted on 24
November 2021; the update of drilling activities up to the end of December
is as follow:
Dieng Drilling Activities Status Well Name Key Activity Status Progress
SLR-Q-31A 1. Mobilization/Mov
ing/Skidding
2. Drill 26" Section
3. Run 20" Casing,
Cementing, N/D
Diverter and N/U
BOP
4. Drill 17-1/2"
Section
5. Run 13-3/8"
Liner,
Cementing, N/D
BOP, Run 13-
3/8" Tie Back,
Cementing, N/U
MV and BOP
6. Drill 12-1/4"
Section
7. Coring, Logging,
Wiper Trip, Run
10-3/4" Liner
and Finishing
8. Drill 9-7/8"
Section
9. Wiper Trip, Run
8-5/8" Liner and
Finishing
1. Mobilization has
been completed
2. Drilling 26” Section 321 of
500 m
3. Run 20” casing 144 of 500 m
4. Aerated Drilling
12-1/4" Hole At
1812 Mmd/
1736 Mtvd (Tlc)
1. 100.00%
2. 100.00%
3. 100.00%
4. 100.00%
5. 100.00%
6. 64.00%
7. 0%
8. 0%
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
6
10. Demobilisasi
Tools and
Personel
Permits related to the Dieng-2 project that has been submitted and issued
are detailed in the following table:
Permit/Consent Key Activity Status Progress
Water Utilization
Permit 1. Public
consultation
2. Technical
Recommendation
(REKOMTEK)
Document issued
by BBWSSO
3. Water Extraction
Permit issued by
Directorate
General of Water
Source of Ministry
of Public Works
and Housing
(PUPR)
COMPLETED
Technically, water
utilization permit
has already been
issued on 24 May
2021, but the
document was
received on 2 July
2021 (due to
administration
checking by Dirjen
SDA PUPR)
Water utilization
permit Sidolok
Water utilization
permit Kali Tulis
Current progress is
100%
Environmental
Permit
Addendum AMDAL
Document process
1. 1st document
assistance with
MoEF has been
held on 30 March
2021
2. The revised
document was
submitted to
KLHK on 19 May
2021
3. 2nd document
Assistance with
MoEF has been
carried on 24 June
2021
The current
progress is 100%.
The Approval of
Environmental
Eligibility Decree
(SKKLH /
Environmental
Permit) by the
Minister of
Environmental and
Forestry was
obtained on
December 31st,
2021.
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
7
4. AMDAL
Addendum
revision according
to 2nd Document
Assistance was
submitted to MoEF
on 15 September
2021.
5. The finalization
and routing
document
approval process
in the internal
MoEF.
6. Approval from
Minister of
Environmental and
Forestry.
IMB (Building
Permit) NA IMB was issued with
an existing Power
Plant.
The Project
Manager needs to
confirm with Legal
HO regarding the
possibility of using
the existing IMB.
Izin Lokasi
(Location Permit)
NA Izin lokasi (location
permit) was issued
with the existing
Power Plant.
PM needs to confirm
with Legal HO
regarding the
possibility of using
the existing permit.
Izin Pembuangan
Limbah B3
(Hazardous Waste
Transport and
Dsiposal Permit)
Coordination with
Dieng Unit
Health and safety
A.M. consulted with
the Dieng unit, and
it will be under the
existing contract of
Dieng Unit and will
use Dieng Unit and
PMU Budget.
Current progress is
100%
Patuha-2
3. Patuha Field Activities
Temporary Office and Warehouse Construction for Project Patuha-2
started on January 4th, 2021. The project activity includes Topography
surveys, excavations, formwork, columns, sloop, wall installation, roof
installation for Temporary Warehouse, Temporary Office, Mess Hall,
Generator room, and post-security. Primary activities for temporary office
and warehouse construction have been done, and currently, work
continues to minor repairs.
Geomembrane Installation works started on March 8th, 2021. The project
activity includes delivering and unloading the Geomembrane at PPL 2, 4
and 6; preparation works; fabrication material on-site; installing the geo-
membrane at the pond, and pressure test at each weld joint. The next step
is to Install the Geomembrane at PPL 21. PT Supraco conducted the
Activity for Road and Well pad preparation. These activities were carried
out at PPL 7, PPL 6, PPL 2, PPL 4, and Loc. BB. The work progress
included topographic surveys, auger boring, cellar box construction,
1 Patuha Power Limited Company
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
8
installation of drainage pipes, rig foot construction, and BRC fence
installation. PT Anugerah Mulya Perkasa has been assigned for the
Construction Work of Separation Installation for Warehouse and Mess Hall
Patuha-2.
PT Wira Cipta Perkasa has been assigned as a Contractor for the Operating,
Maintenance, and Utilities Service Project Patuha-2. The activities include
Stringing and connecting of water line pipe, Electrical work in the temporary
office, logistic activities, Maintenance services for civil facilities,
maintenance service for water line pipe, Water Supply Drilling Operation and
Well Test Operation. Aecom – PT Dago Energi Nusantara has been
assigned for Topographic, Surveying, Geotechnical Investigation, and
Testing Services. The activities were carried out at PPL 7, PPL 6, PPL 2,
PPL 4, Location BB, SAGS Corridors, Cipaku area to Pond J, Temporary
Office, and Laydown area.
Summary of Patuha Field Activities
No Task Key Activities Status Next Step
1 Temporary
Office and
Warehouse for
Project Dieng-2
Patuha-2
- Preparation
- Warehouse
Construction
- Mess hall
Construction
- Office Construction
- Security Pos
Construction
- Generator House
Const.
KSO PT Intan
Prima
Kalorindo –
PT Anugerah
Setiya Buana
already
started this
project from
January 4,
2020.
Current
progress is
98.75%
Issuance
IMB (Izin
Mendirikan
Bangunan/
Building
Permit)
2 Installation
Geo-membrane
work for Water
Pond and Mud
Pond Project
Patuha-2
1. Mobilization and
Unloading Material
2. Preparation work and
fabrication of material
onsite
3. Installation Geo-
membrane at PPL 2
4. Installation Geo-
membrane at PPL 4
5. Installation Geo-
membrane at PPL 6
6. Installation Geo-
membrane at BB
Location
PT Elmoz
Geo Solution
has already
started this
project
started from
March 8th,
2021
Current
progress is
74.52%
• Th
e
installation
geo-
membrane
for PPL 4
and PPL 6
is already
finished.
- The next
step is
preparati
on for
water
and mud
pond
PPL 2.
3 Road and Well
Pad preparation
for Dieng-2 and
Patuha-2
Drilling
Campaign
Road and Well Pad
preparation.
1. Completed
installation
for BRC
Fence at
PPL 6
Finishing
Installation
of BRC
Fence at
PPL 4.
Preparation
for cut and
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
9
2. Topographic
survey at
Loc. BB
3. BRC Fence
installation at
PPL 4 is still
in progress
Current
progress is
35.46%
fill BB
location.
Continued
for the
topographic
survey.
4 Construction
work of
Separation
Installation for
Warehouse and
Mess hall
Patuha-2
Separation Installation
for Warehouse and
mess hall
Construction
work for
separation for
Messhall and
Warehouse
Current
progress is
80.21%
Installation
of the gate
for
Warehous
e and door
installation
for a mess
hall
4. Drilling Activities in Patuha
ITP Mobilization of Rig Bundling Contractor for Patuha (JV ADA-APS) for
Patuha was issued on 7 September 2021. First Spud In Well PTH-V-7C
conducted on 23 November 2021; the updated drilling activity up to end of
December 2021 is as follows:
Patuha Drilling Activities Status
Well Name Key Activity Status Progress
PTH-V-7A 1. Mobilization
2. Drill 26"
Section
3. Run 20"
Casing,
Cementing,
N/D Diverter
and N/U
BOP
4. Drill 17-1/2"
Section
5. Run 13-3/8"
Liner,
Cementing,
N/D BOP,
Run 13-3/8"
Tie Back,
Cementing,
N/U MV and
BOP
6. Drill 12-1/4"
Section
7. Coring,
Logging,
Wiper Trip,
Run 10-3/4"
1. Mobilization
has been
done
2. Drilling 26” Section 400
of 400 m
3. Run 20” casing 41 of
400 m
4. Run in hole
12-1/4" bit +
BHA#13 at
462 mMD
1. 100.00%
2. 100.00%
3. 100.00%
4. 100.00%
5. 100.00%
6. 61.58%
7. 0%
8. 0%
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
10
Liner and
Finishing
8. Demobilisasi
Tools and
Personel
Permits related to the Patuha-2 project that has been submitted and issued
are detailed in the following table:
Permit/Consent Key Activity Status Progress
Water Utiization
Permit Propose extension
of SIPA Permit to
DMPPTSP West
Java (One Door
Integrated Service
Investment Office)
Amendment of
Water Utilization
Permit already
obtained from
DPMPTSP on
August 3, 2020
Completed
IPPKH (Borrow and
Use Forest Area
Permit)
1. Pertek Perhutani
(Technical
Approval from
Forestry Agency)
2. Governor
recommendation
3. Izin Pemanfaatan
Kawasan Hutan
by KLHK (Forest
Area Utilization
Permit from
Ministry of
Forestry and
Environment)
4. Area
measurement
(FEED Civil)
Izin Pemanfaatan
Kawasan Hutan by
KLHK (Forest Area
Utilization Permit
from Ministry of
Forestry and
Environment)was
already established
on January 18th,
2021, with
document Number
SK.32/1/KLHK/2021
Completed
The next step is the
finalization area for
pad BB and access
road.
Area measurement
by Perum Perhutani
(Forestry Agency).
IPPKH Compliance 1. Complete the
demarcation of
the IPPKH area
in accordance
with laws and
regulations
under the
supervision of
Balai
Pemantapan
Kawasan Hutan
(BPKH) Wilayah
XI Yogyakarta
1. MoEF approved
the demarcation
report on
November 10th,
2021.
2. Tree inventory
activity was
conducted on 19-
20 May 2021
with supervision
by BPHP
Lampung. BPHP
has provided a
Current progress is
30%
The next step will
be:
1. Completing the
technical and
legal feasibility
survey proposal
to the Forestry
Service (Dinas
Kehutanan) of
West Java
Province.
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
11
2. Provide the land
compensation to
MoEF with a
ratio of 1:2 as
stated in Minutes
of Land
Compensation
Handover
3. Submit a
statement in the
notarial deed
willing to
reimburse the
investment cost
for forest
management to
Perum Perhutani
tree inventory
report on May
21, 2021.
3. The
compensation
fee for
investment value
in the IPPKH
area was paid in
June 2020 to
Perum Perhutani.
4. GDE is in the
process of
providing land
compensation.
The
recommendation
letter from the
Regent of
Bandung
Regency was
obtained on
October 27th,
2021
2. Propose the land
compensation to
MoEF.
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
12
1.2 Summary of EMP Implementation
Project EMP was adapted to CEMP and implemented by the contractor during construction activities.
GDE continuously monitor CEMP implementation by the contractor through site inspection, regular
reporting (daily, weekly and monthly) by the contractor to PMU and PMC and consultation with affected
people. List of CEMP document approval status is detailed in Table 9.
Dieng-2 Sub-Project
The contractor implements mitigation measures defined in the CEMP; some minor commitments are
not implemented where not yet applicable.
During this reporting period from July to December 2021, drilling activities have been carried out in the
site, starting from the mobilization of equipment, material, and personnel. The current activity is drilling
at well pad 31.
In general, EMP is well implemented, and contractor performance is acceptable; however, contractor
performance still needs to be improved. The main issue in Dieng was noise from drilling activity and
booster pump. Due to the settlement area being very close to the drilling site, it is unavoidable that the
settlement area is impacted by drilling activity. However, mitigation measures are already in place and
go beyond the requirements stated in the EMP. Regarding the noise from the booster pump, the
contractor has installed a noise barrier and acoustic foam to absorb noise generated. In addition to that,
currently, only 1 (one) is operated, and another pump is as a backup. Some corrective actions have
been developed by contractor including; covering the pump by metal sheet and modifying rock muffler
by inserting muffler into the drum filled with water and the result is vibration caused by booster pump
decreased significantly (please see figure below). After additional measures and corrective actions
conducted noise level was decreased and fulfills the standard.
GDE has also conducted noise measurement on a daily and monthly basis to monitor noise in nearby
booster pump area to prevent any new complaint from community.
Pump Cover
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
13
Muffler Modification Figure 1. Additional Measures to Reduce Noise Level
Patuha-2 Sub-Project
Progress of drilling activity at well PPL 7 Patuha is fasterd than in Dieng, there was total loss during
drilling activity in Dieng which caused a delay.
Drilling contractors have consistently implemented CEMP in the field. However, there are several
findings and corrective actions that the contractor must carry out:
1. The handling of drilling cutting and temporary dumping area of drilling cutting shall be maintained
regularly. Due to frequent heavy rain in Patuha, the temporary dumping area was muddy, and drill
cutting scattered in the area
2. Housekeeping issue was occasionally reported that contractor dump the waste, not in the proper
area
3. Domestic wastewater treatment, current treatment is not optimum need to be improved. Corrective
action has been recommended to the contractor.
When this report was prepared there are some immediate action have been implemented by GDE
regarding these finding.
1. Temporary Dumping Area has been restored filled by sand and gravel, current condition is as
shown in the pictures below.
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
14
Figure 2 Temporary Dumping Area for Drill Cutting
2. Housekeeping issue was continuously monitored, Project Implementing Unit (PIU/personnel in site)
undertakesdaily check and monitors house keeping activity.
3. Domestic wastewater treatment has been maintained and the waste has been removed and will
be removed regularly by third party Contractor, Following is pictures of maintenance activity of
waste water treatment.
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
15
Figure 3 Maintenance of Sewage Treatment Plant
PMC and PMU have carried out joint inspections at drilling sites; findings and a corrective action list
can be seen in Appendix C. PMU regularly supervises this drilling activity, and the drilling contractor
regularly reports on CEMP implementation every month.
In general, the contractor's performance in implementing the CEMP can be accepted; however, the
contractor is expected to continue to improve their performance on CEMP implementation. Details of
CEMP implementation is discussed in Chapter 3.
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
16
1.3 Summary of EMP Monitoring
Completed EMP monitoring program is summarised in Table 2 for this reporting period
Table 2 Summary of EMP Monitoring
No Criteria Dieng Patuha Remarks
1 Number of a visit by PMC and PMU 2 2 Conducted during Joint Site
Inspection PMU & PMC the
report is attached in
Appendix C
2 Number of a visit by PIU Daily Daily Project Implementing Unit in
Dieng & Patuha monitor the
project in daily basis
3 Number of the visit by GDE management - - -
4 Number of air quality samples tested 12 10 Monitoring conducted
quarterly and semesterly,
the result is attached in
Appendix B
5 Number of noise measurement 2 10
6 Number of surface water samples tested 2 3
7 Number of groundwater samples tested - 2
8 Number of traffic monitoring 1 1 Traffic Monitoring conducted
semesterly the result is
attached in Appendix B
1.4 Summary of Complaints, Issues and Corrective Action
Dieng-2 Sub Project
Table 3 summarizes complaints and issues received for Dieng-2 Sub Project; detailed complaints and
their resolution progress are presented in Chapter 5.
Table 3 Summary of Complaint and Issue Dieng-2 Sub Project
Complaint/
Grievance Topic(s)
Number of Complaint/
Grievance Received Status of Grievance(s)
Number of complaints
received within this
monitoring period
Resolved Ongoing Remark
Water pollution 1 1
Noise 1 1
Affected-village status 1 - 1 Waiting
decision
from ADB
Electricity blackout 1 1 -
Traffic disturbance 2 2 -
Patuha-2 Sub Project
Table 4 summarizes complaints and issues received for Patuha-2 Sub Project; detailed complaints and
their resolution are presented in Chapter 5.
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
17
Table 4 Summary of Complaint and Issue Patuha-2 Sub Project
Complaint/
Grievance Topic(s)
Number of
Complaint/
Grievance
Received
Status of Grievance(s)
Resolved Ongoing Remark
Traffic disruption 4 4 - -
Compensation (due to
mobilization)
9 9 - -
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
15
2 SAFEGUARDS STAFF, TRAINING AND DOCUMENTATION
2.1 Implementation Arrangements
The EMP defines the Environmental Safeguards roles and responsibilities during implementation; the status of key roles is indicated in Table 5.
Table 5 Status of Environmental Safeguard Roles
Safeguards Role Status and Comment
GDE PMU – HSE
Date Started: Various Full Time/ Part Time 11 FT
Comment
1. PMU Head Office
2. HSE and Safeguards Manager - Hefi Hendri
3. Health and Safety Assistant Manager - Ray Armand
4. Health and Safety Staff - Sannita Debora Ambaritha
5. Environment Safeguards Assistant Manager - Sari Ramadhani Putri
B. PMU Dieng-2
6. HSE and Safeguard Superintendent – Sigit Dwi Pamungkas
7. Health and Safety Supervisor – Solimin
8. Environment Safeguards Supervisor – Dian Nur Febrianto
C. PMU Patuha-2
9. HSE and Safeguard Superintendent - Aditya Rahman
10. Health and Safety Supervisor - Bambang Umbara
11. Environment Safeguard Supervisor - Rista Jayanti
PMC Environmental Safeguards Team
Date Started: 5 August 2021 Full Time/ Part Time 2 FT
Comment
1. International Environmental Specialist - Virza Sasmitawidjaja
2. Environmental Specialist - Hasbullah Hasan
3. Biodiversity Specialist - Novianto Hadi
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
16
Safeguards Role Status and Comment
Environmental Monitoring Firm (Sucofindo)
Date Started: January 2021 Full Time/ Part-Time 18 PT
Comment 1. Sucofindo Bandung - 9 Staff
2. Sucofindo Semarang - 9 Staff
PMU GRM Focal Point
Date Started: Various Full Time/ Part Time 4 FT
Comment
1. Dieng-2 – Slamet Riyadi
2. Dieng-2 – Himawan
3. Patuha-2 – Ananda Riana
4. Patuha-2 – Viosy Tederickbrata
Contractor Environment Health and Safety Staff at
Dieng Unit 2 (each company will appoint one
staff for GRM representative)
Date Started: March 2021 Full Time/ Part-Time 2 FT
Comment 1. PT Wirana - 1 HSE Staff
2. PT Elmoz - 1 HSE Staff
Contractor Environment Health and Safety Staff at
Patuha Unit 2 Date Started: March 2021 Full Time/ Part-Time 4 FT
Comment
1. Kalorindo - 1 HSE Staff
2. GTU - 1 HSE Staff
3. PT Elmoz - 1 HSE Staff
4. Wirana - 0 HSE Staff
5. Catur - 0 HSE Staff
6. Paradise/SSL - 0 HSE Staff
7. Citra Turbindo - 1 HSE Staff
The project concludes that the environmental safeguards roles are building sufficient staff members and specialists.
2.2 Training and Capacity Building
PMC has conducted ADB SPS Requirement Training to PMU and all Contractor as part of the overall Capacity Development Program, which includes further
enhancement of the Projects’ (PMU) environmental and social (E&S) management capacity. The Training cover all ADB E&S Policy Requirements at an
introductory level, with more depth when focusing on the key Projects’ issues which have been assessed in the previous safeguard studies (including potential
impacts/issues reported in the IEE and also in the RP).
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
17
The training sessions are expected to result in improved knowledge and understanding of the rationale, requirements and approaches to safeguard compliance,
with an emphasis on ADB SPS. The program will also produce:
− A set of ADB safeguard policy focused materials in MS Power Point (PPT);
− Overview of participant’s self-assessment of knowledge and applicability to their work (to inform a need assessment); and
− Summary of the program effectiveness by session and overall, completed by trainers and participants.
Considering the current COVID-19 pandemic situation whilst PMC personnel and the Project Team are located across different areas, the E&S safeguard
introductory training program was mainly conducted online, with a mix offline where some of the participants to be joining offline in Soreang Office.
There was a total of 5 sessions of 2 hours each which were completed within few weeks, with combined of on-offline sessions, within 29 November to 14
December 2021. The training followed a program set out in the Table 6 below, with material taken from ADB documents as a key source, as well as GDE
documents and case study/ examples from the trainer team experiences working in other relevant/similar projects. There were different themes of each session
that defined the key questions addressed, namely: What is this? Why is it important? What is required? How is it done? What can go wrong/what can be done
(lesson learned and discussion on implementation strategy for the GDE Project)? Complete training report including participants, training notes and photograph
are presented in Appendix A.
Table 6 Training Framework and Agenda for Introductory Training on ADB’s Environmental and Social Saeguard
No Dates/ Time Topics/ Session Descriptions/ Training Outline Targeted Participants Notes
1 Monday, 29 November 2021 2-4pm (Offline at Soreang Office: Novianto, and Online: Agni)
Overview of ADB safeguards requirements and application on the Projects
Objective: To provide context to the existence and application of safeguards and build understanding of the generic processes related to safeguard policy implementation
a. Pre-Test on safeguards knowledge
b. Overview of safeguards as an approach
c. ADB Safeguards and E&S policies, instruments and
guidelines
d. Role of screening, studies, monitoring, reporting,
audits
a. PMU Team Organization for
Dieng 2 and Patuha 2:
− Project Manager
− Manager: Drilling and
Engineering
− Assistant Manager: Drilling
and Engineering
b. General Support Organization:
− General Support Manager
− Human Capital and
General Affair Staff
− PMC Team Manager
− PMC Training Coordinator
c. HSE & Safeguard
All E&S-related unit, as relevant
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
18
No Dates/ Time Topics/ Session Descriptions/ Training Outline Targeted Participants Notes
Organization:
− HSE and Safeguard
Manager
− Government Relation and
Social Safeguard
− Health and Safety
− Environmental Safeguard
d. Main Contractors’ HSE & Social-related personnel
from JV ADA-APS, PRA and
Supraco
2. Tuesday, 30 November 2021 10am - 12pm (Offline at Soreang Office: Hasbullah, Novianto, and Online: Agni)
ADB SPS 2 on involuntary resettlement
Objective: To develop understanding of the land acquisition, resettlement and related requirements for ADB supported projects, how these are to be met and increase awareness of pitfalls and opportunities Resettlement Plan (RP)
- Displacement, Access restrictions
- ADB IR principles
- Inventory of Losses (IOL) and Social Economic
Survey
- Livelihood Restoration Program
- Monitoring and Completion Audits
a. General Support Manager
b. Human Capital and General
Affair Staff
c. Government Relation and
Social Safeguard
d. Health and Safety Officer
e. Contractors Social-related
personnel from JV ADA-
APS, PRA and Supraco.
Assuming land acquisition and livelihood restoration responsibility conducted under the General Support Organization.
3. Thursday, 2 December 2021 2-4pm (Offline at Soreang Office: Iwan and Christine,
ADB SPS 1 on Social and its dimensions issues (GRM, labour, and gender)
Objective: To develop understanding of the social and labor requirements for ADB supported projects, how these are to be met and increase awareness of pitfalls and opportunities Potential Social Impacts and IEE requirements for management of social and labour impacts
− Grievance mechanism
a. General Support Manager
b. Human Capital and General
Affair Staff
c. Government Relation and
Social Safeguard
d. Health and Safety Officer
e. Contractors Social-related
personnel from JV ADA-
APS, PRA and Supraco
Social-related unit mainly
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
19
No Dates/ Time Topics/ Session Descriptions/ Training Outline Targeted Participants Notes
and Online: Agni)
− Strategic communication and stakeholder
engagement plan
− Health and safety impact management plan
− Management of potential impacts on Physical
Cultural Resources (PCR) and Chance Find
Procedure (CFP)
− Labour standard
− Gender and development (GAD)
4 Monday, 13 December 2021 2-4pm (Offline at Soreang Office: Neneng, and Online: Agni)
ADB SPS 1 on HSE and Biodiversity
Objective: To develop understanding of the health, safety and environment requirements for ADB supported projects, how these are to be met and increase awareness of pitfalls and opportunities Potential HSE Impacts and IEE requirements for management of environment and OHS impacts
− Environmental Management Plan
− OHS Management Plan
− Biodiversity Action Plan
a. HSE and Safeguard Manager
b. HSE Supervisor
c. Health and Safety Officer
d. Environmental Safeguard
e. Contractors HSE-related
personnel from JV ADA-APS,
PRA and Supraco
HSE-related unit mainly
5 Tuesday, 14 December 2021 10am - 12pm (Offline at Soreang Office: Pak Novianto, and Online: Agni)
Training evaluation Objective: To review training process and results and provide feedback for improvement and next steps in related capacity building activities
- Discussion and feedback session
- Next steps
- Training post-evaluation
All (as defined in the Session 1) All E&S-related unit, as relevant
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
20
2.3 ADB Approvals
Information on the status of the safeguards documents is presented in Table 7.
Table 7 Status of Environmental Safeguard Documents
Safeguards Documents Update Issued (Latest Version) Disclosure date
Geothermal Power Generation Project: Dieng
Unit 2 Project Component Draft Initial
Environmental Examination
https://www.adb.org/projects/documents/ino-
52282-001-iee
November 2019 November 2019
Geothermal Power Generation Project: Dieng
Unit 2 Project Component Draft Initial
Environmental Examination
https://www.adb.org/sites/default/files/project-
documents/52282/52282-001-iee-en_0.pdf
October 2019 October 2019
EMP for Dieng-2
https://www.adb.org/sites/default/files/project-
documents/52282/52282-001-iee-en_1.pdf
November 2019 November 2019
EMP for Patuha-2
https://www.adb.org/sites/default/files/project-
documents/52282/52282-001-iee-en_2.pdf
October 2019 October 2019
2.4 National Approvals
Table 8 updates the necessary national approvals required for the project to proceed.
Table 8 Status of National Approvals for Environmental Documents
Documents Submitted to MoEF Approved By
MoEF
Status – if not
approved Comment
SIPPA (Water Extraction
Permit) Dieng-2 N.A. N.A.
Approved (date is
TBC)
Approved for Sungai Sidolok by Kabupaten
Banjamegara, Propinsi Jawa Tengah, 24 May
2024.
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
21
Documents Submitted to MoEF Approved By
MoEF
Status – if not
approved Comment
AMDAL Addendum for
Dieng-2 1 November 2021 December 31, 2021 Approved Completed.
Waste Management
Proposal of Used Mud
and Drilling Cuttings for
Dieng-2
N.A. N.A. Not approved
The proposal was submitted to the Directorate of
New and Renewable Energy (EBTKE) on 14 June
2021. Based on communication with EBTKE, there
will be no formal approval on the proposal. EBTKE
instructed GDE to follow Ministry of Energy &
Mineral Resources No 21/2017 decree regarding
Drilling waste and dril cutting management in
Geothermal activity, then EBTKE will evaluate
implementation of drilling waste and drill cutting
management performed by GDE.
Coordinatiom meeting with EBTKE has been
conducted in Dieng at 11 – 14 August 2021
Borrowing and Use of
Forest Area Permits
(IPPKH) – Patuha-2
April 2020 18 January 2021 Approved Izin Pemanfaatan Kawasan Hutan was granted.
SIPPA (Water Extraction
Permit) Patuha-2 N.A. N.A. Approved
Completed In 2020
AMDAL Addendum for
Patuha-2 November 2009 17 February 2010 Approved
The scope of this Amdal Addendum covered units 1
to 7 and is still valid for development; therefore,
GDE did not apply new Amdal.
Waste Management
Proposal of Used Mud
and Drilling Cuttings for
Patuha-2
N.A. N.A. N/A
The proposal was submitted to the Directorate of
New and Renewable Energy (EBTKE) on 14 June
2021.
EBTKE will not approve this subject. This proposal
will be a document base for the monitoring program
of EBTKE.
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
22
2.5 Construction Environmental Management Plan (CEMP) Approvals
In the second semester of 2021, 12 CEMPs have received approval, while 2 CEMPs are still under review. CEMP completion percentage of this period is 8%.
CEMP approval status is summarized in Table 9.
Table 9 CEMP Approval Status
No Contractor Work Contract CEMP Status
1 PT Plumpang Raya Anugrah Rig Bundling (Lot Dieng) Dieng: Approved by GDE - 17 October 2021
2 JV PT Air Drilling Associate - PT Asia Petrocom
Services Rig Bundling (Lot Patuha) Patuha: Approved by GDE- 8 November 2021
3 PT Air Drilling Aerated Patuha and Dieng: Approved by GDE - 3
November 2021
4 PT Halliburton Logging Services Indonesia Cementing and Casing (lot Dieng) Dieng: Approved by GDE- 8 November 2021
5 PT Halliburton Logging Services Indonesia Cementing and Casing (lot Patuha) Patuha: Approved by GDE- 8 November 2021
6 PT Halliburton Logging Services Indonesia Directional Drilling (Lot Dieng) Dieng: Approved by GDE- 9 November 2021
7 PT Halliburton Logging Services Indonesia Directional Drilling (Lot Patuha) Patuha: Approved by GDE- 9 November 2021
8 JV PT Tiger Energy Services and NPS Bahrain for
Oil and Gas Well Services Wireline Logging Services
Patuha: Approved by GDE - 3 November 2021
Dieng: Approved by GDE - 3 November 2021
9 PT Baker Hughes Indonesia Fishing Milling Patuha and Dieng: Approved by GDE - 19
November 2021
10 PT Baker Hughes Indonesia Mud Engineering (Lot Dieng) Dieng: Approved by GDE - 19 November 2021
11 PT Prima Hidrokarbon Internusa Mud Engineering (Lot Patuha) Patuha: Approved by GDE- 3 November 2021
12 PT Depriwangga Well testing Patuha Approved, and Dieng: waiting for final
version submission
13 PT Supraco Indonesia Civil Work Patuha: Approved by GDE- 9 November 2021
Dieng: Approved by GDE 22 November 2021
14 NMS Wellhead Patuha and Dieng: The document has been
reviewed and is waiting for final version submission
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
23
3 EMP IMPLEMENTATION
3.1 Environmental Performance
Table 10 to Table 15 provide detailed information on implementing environmental impact mitigation measures outlined in EMP and the correlated CEMP during
the July - December period. Some mitigation measures that were already conducted during the preparation stage were reported in the previous semiannual
report. Some mitigation measures in the EMP and correlated CEMP are not included in the report due to the activity not starting yet when this report is prepared,
i. e well-testing activity. Meanwhile, mitigation measures were defined in Biodiversity Action Plan (BAP) is detailed in a separate table.
The evidence for the compliance of EMP implementation is through a combination of:
● Site visits to observe site practices;
● Consultation with affected people;
● Regular environmental reporting form;
● Documentation
Environmental Performance of Dieng-2 Sub Project
Table 10 Status of EMP Compliance Dieng-2
No Key
Activities/Environmental
Impact
EMP Requirement
(Mitigation Measure)
Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
1 Secure necessary permits B.7 Secure water
utiliation permit or
surface water extraction
Yes comply Water utilization permits have been approved No.
642/KPTS/M/2021 tentang “Pemberian Izin Pengusahaan Sumber Daya Air kepada Perseroan Terbatas Geo Dipa
Energi (Persero) Unit Dieng untuk Operasional
Pengeboran Sumur Panas Bumi Unit Dieng-2 di Sungai
Sidolok Kabupaten Banjarnegara Provinsi Jawa Tengah” on May 24th of 2021
None
2 Readiness of contractors B.15 Develop and
submit to PMU for
Yes Comply 8 CEMPs out of 10 have been approved; the remaining 2
CEMPs are under review.
None
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
24
No Key
Activities/Environmental
Impact
EMP Requirement
(Mitigation Measure)
Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
to adhere to
environmental
management equirements
approval a contractor
environmental
management plan
(CEMP).
3 Deconstruction/demolition
of existing structures (old
buildings at the side of
powerplant unit 2), with
the potential presence of
asbestos-
containing materials
C.1. Qualified 3rd party
(through PMU) to
conduct a rapid
assessment for
the existence of
asbestos as the basis to
develop a demolition
plan
Yes Comply
None
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
25
No Key
Activities/Environmental
Impact
EMP Requirement
(Mitigation Measure)
Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
C.2. Contractor to
implement a demolition
plan following health,
safety, and environment
(HSE) requirements of
Indonesia, IFC-WB EHS
General Guidelines,
WHO, and ADB
Yes Comply
C.3. Demolition Plan to
be approved by
regulatory authorities
and PMU
Yes Comply PMU has approved the Demolition Plan; Final Report is
attached in Appendix D.
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
26
No Key
Activities/Environmental
Impact
EMP Requirement
(Mitigation Measure)
Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
C.4. Conduct
environmental
monitoring during
demolition works
Yes Comply
3 Orientation of workers,
contractors and staff on
the responsibility for
compliance to ADB and
GOI requirements
C.5. Conduct routine
environment and safety
training for workers,
including induction
training and annual
refresher training.
Yes Comply GDE and contractor routinely conducted environment and
safety training to all workers, including basic safety training
to all workers before construction activity. With regards to
ADB requirement, PMC completed ADB SPS
Requirements Training to PMU and all contractor
None
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
27
No Key
Activities/Environmental
Impact
EMP Requirement
(Mitigation Measure)
Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
4 Generation of dust and
vehicular emissions from
earthworks and movement
of vehicles to and from
the construction sites
C.6. Regularly inspect
and maintain heavy
equipment
Yes Comply None
C.7. Use of high-
occupancy service
vehicles to transport
workers
Yes Comply Vehicles used for transport workers are multi-passenger
vehicles such as minibuses and MPV cars.
C.8. Emissions testing
certificate of service
vehicles will be required
and monitored by PMU
Yes Comply
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
28
No Key
Activities/Environmental
Impact
EMP Requirement
(Mitigation Measure)
Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
C.9. Install temporary
fencing and/or
enclosures at least 3-m
high at construction
sites
NA The drilling site is located in the existing well pad, which is
already equiped with a fence
None
C.10. Water will be
sprayed daily in opened
land areas or in other
areas where dust is
generated
Yes Comply
C.11. Stockyard will be
covered during non-
working hours
Yes Comply
C.12. Vehicles and
equipment will not be
allowed to sit and idle
for more than 30
minutes
NA The drilling site is located in an existing well pad; vehicles
are not possibly parked on-site due to the limited space
area. After unloading, material/equipment vehicles shall
leave the location
C.13. Cover trucks that
deliver dust-generating
construction materials
NA The current activities not involving any truck that delivering
dust-generating construction materials
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
29
No Key
Activities/Environmental
Impact
EMP Requirement
(Mitigation Measure)
Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
C.14. No burning of
solid or liquid wastes
and other combustible
materials will be allowed
within the construction
sites and labour camps
Yes comply There is no burning activity on site
C.15. Provide PPE to
operators of heavy
equipment
Yes Comply
Safety instruction to the heavy equipment operator
C.16. Limit noise-
generating activities
during the daytime and
provide temporary
enclosures to stationary
noise sources
Yes Comply
Temporary enclosure for stationary noise source
C.17. Drivers and
operators must strictly
Yes Comply The contractor has developed Journey Management Plan
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
30
No Key
Activities/Environmental
Impact
EMP Requirement
(Mitigation Measure)
Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
follow road regulations
particularly speed and
excessive blowing of
horns will not be allowed
C.18. Provide
earplugs/muffs to
workers exposed to
high-level noise and
rotate the schedule of
these workers every two
hours
Yes comply
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
31
No Key
Activities/Environmental
Impact
EMP Requirement
(Mitigation Measure)
Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
5 Generation of waste -
Improper
handling and disposal of
waste
generated may affect
water quality
and cause soil
contamination
C.22. Contractor to
prepare a waste
management plan, to be
approved by
PMC ( as part of CEMP)
Yes Comply
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
32
No Key
Activities/Environmental
Impact
EMP Requirement
(Mitigation Measure)
Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
C.23. Contractor to
provide adequate
garbage bins to all
construction sites and
workers’ camps
Yes Comply
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
33
No Key
Activities/Environmental
Impact
EMP Requirement
(Mitigation Measure)
Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
C.24. Heavy equipment
and machinery
workshops will be
bunded or lined with
impermeable material to
prevent spills directly on
land
Yes Comply
C.25. Contractor to
provide an oil-water
separator for oily
washings
NA Oil-water separator for oily washing is already in place; GDE
provides it for well pad
6 Impact on biodiversity and
precious ecology
C.26. Revegetate to
improve aesthetics and
create a green buffer
NA/To be
conducted later
In this reporting period, civil work has not been conducted
yet
None
C.27. Land clearance
and sourcing of
construction materials
will not take place within
the IBA
NA/To be
conducted later
In this reporting period, civil work has not been conducted
yet
None
C.28. Sourcing of all
construction materials
such as wood, sand or
NA/To be
conducted later
In this reporting period, civil work has not been conducted
yet
None
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
34
No Key
Activities/Environmental
Impact
EMP Requirement
(Mitigation Measure)
Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
gravel should be from
outside of the IBA
C.29. Use of
underground cable
transmission line to
completely avoid
collision risks to
migrating birds, showing
GDE world-leading best-
practice.
NA/To be
conducted later
In this reporting period, civil work has not been conducted
yet
None
7 Operation of drilling rig
causing the intermittent
release of H2S
C.39. Provide workers
with masks
Yes Comply
The worker provided with a mask and SCBA
None
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
35
No Key
Activities/Environmental
Impact
EMP Requirement
(Mitigation Measure)
Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
C.40. Conduct ambient
air quality monitoring
quarterly
Yes, Comply,
the result of air
quality
monitoring is
attached in
Appendix B. In
addition, the
contractor is
regularly
conducting H2S
monitoring in
the surrounding
drilling site
None
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
36
No Key
Activities/Environmental
Impact
EMP Requirement
(Mitigation Measure)
Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
C.41. Provide adequate
ventilation in confined
spaces
Yes Comply
Bug blower to provide adequate ventilation in confined
spaces
None
8 Operation of drilling rig
and equipment generating
noise
C.42. Use of mobile
rock muffler or silencer
during well venting
NA/To be
conducted later
Well venting has not been conducted yet during this
reporting period
None
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
37
No Key
Activities/Environmental
Impact
EMP Requirement
(Mitigation Measure)
Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
C.43. provide workers
with earplug/muffs
Yes Comply None
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
38
No Key
Activities/Environmental
Impact
EMP Requirement
(Mitigation Measure)
Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
C.44. rotate workers
every two hours to
prevent discomfort
Yes Comply Work
schedule in a noisy area
None
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
39
No Key
Activities/Environmental
Impact
EMP Requirement
(Mitigation Measure)
Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
C.45. Inform nearby
communities of well
drilling schedule
Communities
were informed
through public
consultation
and spud in
ceremony
before drilling
activity was
conducted.
Spud in
ceremony in
Dieng was
conducted on
24 November
2021, attended
by community
representatives
and local
authorities.
None
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
40
No Key
Activities/Environmental
Impact
EMP Requirement
(Mitigation Measure)
Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
9 Waste generated from
drilling
activities
C.46. Construct sump to
hold produced water
and waste drilling fluids
Yes Comply
None
C.47. The sumps should
be lined with
impermeable material to
prevent soil and water
contamination.
Yes Comply As ilustrated in the picture above
C.48. Oil-water
separator shall be
provided for oily
washings in the drilling
equipment and trucks
Yes Comply An oil-water separator already exists in the well pad area None
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
41
No Key
Activities/Environmental
Impact
EMP Requirement
(Mitigation Measure)
Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
C.49. Provide garbage
bins at basecamp
Yes Comply
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
42
No Key
Activities/Environmental
Impact
EMP Requirement
(Mitigation Measure)
Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
C.50. Contractor to
prepare waste
management plan (as
part of CEMP),
approved by PMU
Yes Comply
10 Water requirements for
drilling
C.51. Use of
condensate from Unit 1
during the dry season
as the primary source
with an average flow
rate of 30 L/s
To be
conducted later
GDE has conducted Water Management and Water Supply
Study, conducted by Gajah Mada University (UGM).This
study is aimed to ensure the sustainability of drilling water
supply throughout the year. The study examined 4 (four)
scenario as follows:
CASE 1. This scenario relies only on surface water
collected in several large ponds during the rainy season
and used as the main source of water during the dry
season with additional condensate water.
CASE 2. In this scenario, the main water source is a brine
that is treated first in a brine treatment pond in PAD 29.
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
43
No Key
Activities/Environmental
Impact
EMP Requirement
(Mitigation Measure)
Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
CASE 3. In this case, the water requirements for surface
drilling, cementing, and intermediate drilling are met from
surface water, while the need for production zone drilling is
obtained from fresh brines in the brine pond in each PAD.
CASE 4. This case combines case 1 and case 2 with some
modifications. POND 14, POND 17, and POND Siterus are
still designed as in Case 1. However, the alteration was
made in POND 29 by splitting the area into 3 areas,
namely brine treatment pond, treated-brine pond, and
freshwater storage.
Based on the recommendation of the study, during dry
season scenario of Case 4 must be applied which is
combination of Case 1 and Case 2 (water from the pond
combine with brine water)
GDE has provided infrastructure such as pipeline and
pump to utilize condensate for drilling during the dry
season
C.52. Use existing
pipelines in the Sikidang
area to convey the
condensate to Pad 24,
where a pond of about
1,800 m3 capacity is
available but requires
rehabilitation
To be
conducted later
C.53. Reuse water-
bentonite based mud to
Yes comply Water containing bentonite is recycled and used in drilling
activity
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
44
No Key
Activities/Environmental
Impact
EMP Requirement
(Mitigation Measure)
Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
reduce water
requirement
C.54. Use aerated fluid
drilling (clay-free) for the
production zone of the
wells
Yes Comply GDE has contracted PT Air Drilling to provide Aerated
Drilling Services
C.55. No water
extraction during the dry
season (July to
September) so that
irrigation of agricultural
land by farmers will not
be affected
To be
conducted later
GDE has provided infrastructure such as pipeline and
pump to utilize condensate for drilling during the dry
season
C.56. Construction of
additional reservoir at
new power plant site
(Unit 2) of 5,000 m3 to
supply peak water
demand (including the
construction of power
plant)
No Comply It was planned to construct the additional reservoir in
wellpad 38, however, considering the current situation and
condition in Dieng, it was not possible to construct a new
reservoir at the new power plant site
It will be
regarded as
later during
the next well
drilling
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
45
No Key
Activities/Environmental
Impact
EMP Requirement
(Mitigation Measure)
Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
C.57. Drilling services
contractors to keep a
record of daily
operations to include the
volume of water used
segregated by the
source of water
Yes Comply
C.58. Drill only 1 well at
once (only 1 rig will be
installed)
Yes comply Only 1 rig was installed on-site
C.59. Ensure sufficient
flows (e-flows) remain in
any stream where water
abstraction occurs to
minimize impacts to the
freshwater snail,
(Gyraulus terraesacrae).
Yes comply The contractor is monitors regularly streamflow of the river
Sikidang and Siterus
11 Discharge of steam during
well testing - release of
H2S higher than the
occupational limit of 150
C.60. Workers assigned
will be provided with
PPE such as earplugs,
To be reported
later Well testing has not been conducted yet
None
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
46
No Key
Activities/Environmental
Impact
EMP Requirement
(Mitigation Measure)
Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
µg/m3 set by WHO
Elevated noise may affect
the hearing of workers
during well testing
mask and H2S detector,
and personal H2S
dosimeter with alarm
system
C.61. Install mobile rock
muffler as the silencer
To be reported in the next SEMR
C.62. Use of SCBA’s in the immediate area of
well testing
To be reported in the next SEMR
C.63. Conduct regular
calibration of monitoring
equipment to ensure
accurate readings of
H2S
To be reported in the next SEMR
C.64. Safety and
medical personnel will
be available on-site.
To be reported in the next SEMR
For all ‘Partial’ or ‘No’ compliance issues in the table above, the actions needed to solve the compliance issues are summarized in Table 11.
Table 11 EMP Actions Needed for Compliance – Dieng-2
No EMP Requirement Further Action to Take Date for Action Who will Implement Action
01
C.56. Construction of additional
reservoir at new power plant site
(Unit 2) of 5,000 m3 to supply peak
Conduct a feasibility study to construct an
additional reservoir at a new power plant site End of February 2022 PMU
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
47
water demand (including the
construction of power plant)
Table 12 provides information on environmental performance issues from previous Environmental Monitoring Reports. This table confirms that the action was
completed or that the step is outstanding.
Table 12 EMP Compliance Outstanding Issues from Previous Report – Dieng-2
No EMP Requirement Further Action to
Take
Responsibility and
Timing
Resolution Required Action
1 A.7 Include silica management in the SOP
of hazardous material waste management.
Develop Silica
management
Dieng 2, after the silica
test results, is released.
On progress None
2 A.8 Improve access control to existing
wells pads 7, 9, 30 and 31, including
fencing, gate and security guard.
Install fencing, gate
and security guard in
Pad 9
GDE, end of February
2022
On progress None
Environmental Performance of Patuha-2 Sub Project
Summary of environmental performances of Patuha 2 sub project is presented inTable 13.
Table 13 Status of EMP Compliance at Patuha-2
No Key
Activities/Environmental
Impact
EMP Requirement
(Mitigation Measure)
Compliance and
Description
(Yes, No, Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
1 Secure necessary permits B.7 Secure water
utilization permit for
surface water extraction
Yes comply SIPPA has been approved No.
593.3/KEP.25/03.1.04.2/DPMPTSP/2020 tentang
“Perpanjangan Izin Pengambilan dan Pemanfaatan Air Permukaan” on 3rd August 2020
None
B.8 Secure Forestry-
Borrow-to-Use Permit
(IPPKH) from MoEF
Yes comply Izin Pemanfaatan Kawasan Hutan (Permit for
use Forestry Area) by KLHK was already granted
None
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
48
No Key
Activities/Environmental
Impact
EMP Requirement
(Mitigation Measure)
Compliance and
Description
(Yes, No, Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
on January 18th, 2021 with document Number
SK.32/1/KLHK/2021
2 Land Acquisition for new
well pad
B.9 Acquire land for the
new well pad, additional
area (150 m x 120 m),
pipeline and access road
from Loc G to Loc BB of
about 8,000 m2 (800 m
long and 10 m wide)
following LARP and SPS
2009.
Yes comply Land for the new well pad, pipeline and access
road is located in the forest area that already
obtained the permit for use from MoEF
None
3 Readiness of contractors
to adhere to
environmental
management
requirements
B.15 Develop and submit
to PMC for approval a
contractor environmental
management plan
(CEMP).
Yes Comply 12 CEMPs out of 14 have been approved; the
remaining 2 CEMPs is under review
None
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
49
No Key
Activities/Environmental
Impact
EMP Requirement
(Mitigation Measure)
Compliance and
Description
(Yes, No, Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
4 Potential damage to public
roads within the villages of
Panundaan, Alam Endah,
and Sugih Mukti to the
project site
B.16 Pre-construction
survey of the route will be
conducted to assess if
adequate corridor or space
is available, load capacity
of bridges, the condition of
the public roads including
the buildings and/or
houses
located close to the roads
(~ 100 m) to serve as the
baseline for road
rehabilitation and property
damages (if any)
B.17 The Patuha HSE staff
always join in the
assessment of vehicle and
rig movement to the
project site
Yes Comply, GDE
has accompanied
drilling contractor
and transporter to
conduct a final
evaluation on-road
lane and road
condition for
mobilization of
drilling material and
equipment
None
5 Increased vehicular
emissions and noise due
to mobilization of
equipment and materials
C.1 Truck that will deliver
dust-generating
construction materials will
be covered with canvas or
other suitable material to
minimize dust
dispersion
Yes comply
None
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
50
No Key
Activities/Environmental
Impact
EMP Requirement
(Mitigation Measure)
Compliance and
Description
(Yes, No, Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
C.2 Contractor will ensure
regular maintenance and
inspection of
construction vehicles,
including emissions testing
certificate
Yes, complied GDE
and the drilling
contractor has
inspected the
vehicles that will be
used during
mobilization and
drilling operation
All vehicles used for
mobilization have
certificate emission
testing
None
C.3 Use multi-passenger
vehicles to transport
workers to and from the
well sites
Yes Comply Vehicles used for transport workers are multi-
passenger vehicles such as minibuses and MPV
cars.
None
C.4 Stockyard will be
covered during the non-
working period.
Yes Comply None
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
51
No Key
Activities/Environmental
Impact
EMP Requirement
(Mitigation Measure)
Compliance and
Description
(Yes, No, Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
C.5 Vehicles and
equipment will not be
allowed to sit and idle for
more than 30 minutes
Yes Comply Due limited area of the drilling site, vehicles are
not allowed to park in the drilling site. Vehicles
enter the drilling site only for loading and
unloading material.
None
6 Increased dust in the form
of PM10 and PM2.5 may
come from excavations in
the new wells, other
construction support
facilities like the
basecamp
C.6 Install temporary
fencing and/or enclosures
at construction sites to
contain dust levels
Yes Comply The drilling site is located in the existing well pad;
the fence is already in place, the area of a drilling
site is in the allowable distance from the
settlement area
None
C.7 Spray water in dusty
areas, where applicable
Yes Comply
Currently, the weather in Patuha is rain almost
every day; spraying water is implemented
situationally if posible
None
7 Increased level of noise
during well drilling and
testing
C.8 Inform staff and
communities before well
drilling.
Yes, Comply,
general induction
(Basic Safety
Training/BST) was
conducted for all
workers before the
drilling activity
started. BST was
conducted on 11
and 12 November
2021. Photograph
and attendance list
have been
archived.
Communities were
informed through
public consultation
and spud in
ceremony before
None
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
52
No Key
Activities/Environmental
Impact
EMP Requirement
(Mitigation Measure)
Compliance and
Description
(Yes, No, Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
drilling activity was
conducted. Spud in
ceremony in Patuha
was conducted on
18 November 2021,
attended
by community
representatives and
local authorities.
C.9 Use of mobile rock
muffler or silencer during
well venting
NA Well venting/well testing is not carried out yet, will
be reported in the next reporting period
None
C.10 Provide workers with
earplug/muffs
Yes Comply Safety devices are provided for all workers,
including earplugs/earmuffs for those who work
in a noisy area
C.11 Rotate workers every
two hours to prevent
discomfort
Not Comply The Contractor provides safety devices for the
worker working in a noisy area.
Due to the
limited
competence
operator on
site, it is
impossible to
rotate the
operator every
two hours.
However, the
Contractor
allowed the
operator who
was working in
a noisy area to
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
53
No Key
Activities/Environmental
Impact
EMP Requirement
(Mitigation Measure)
Compliance and
Description
(Yes, No, Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
take a break
every two
hours if
possible
8 Use of water for drilling C.16 Reuse water-
bentonite based mud on
reducing water
requirement
Yes Comply, water
containing
bentonite from well
pumped to the
water pond then
water from water
pond utilize for
drilling
None
C.17 Use aerated fluid
drilling (clay-free) for the
production zone of the
wells.
Yes Comply GDE has contracted PT Air Drilling to provide
Aerated Drilling Services
None
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
54
No Key
Activities/Environmental
Impact
EMP Requirement
(Mitigation Measure)
Compliance and
Description
(Yes, No, Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
C.18 Drilling services
contractors to keep a
record of daily operations
to
include the volume of
water used segregated by
the source of water
Yes Comply None
C.19 Secure water use
permit for use of surface
water
Yes Comply SIPPA (water use permit) has been approved
No. 593.3/KEP.25/03.1.04.2/DPMPTSP/2020
tentang “Perpanjangan Izin Pengambilan dan Pemanfaatan Air Permukaan” on 3rd August 2020
None
9 Generation of waste C.20 Construct sump/pond
to hold produced water
and waste drilling fluids
Yes Comply
None
C.21 The sumps should be
lined with impermeable
material to prevent soil and
water contamination.
Yes Comply
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
55
No Key
Activities/Environmental
Impact
EMP Requirement
(Mitigation Measure)
Compliance and
Description
(Yes, No, Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
C.22 Oil-water separator
shall be provided for oily
washings in the drilling
equipment and trucks
N The drilling
site is located
in the existing
well pad. Due
to limited area,
there is no oily
washing of the
truck in drilling
site.
C.23 Provide garbage bins
at basecamp
Yes Comply
None
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
56
No Key
Activities/Environmental
Impact
EMP Requirement
(Mitigation Measure)
Compliance and
Description
(Yes, No, Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
C.24 Contractor to prepare
waste management plan
(as part of CEMP),
approved by PMC
Yes Comply, GDE
has appointed a
waste management
company (PT
Enviromate
Technology
International) to
handle waste
management of
drilling activities.
Waste
Management Plan
has been provided
and approved by
GDE
None
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
57
EMP Compliance of Civil Work (Based on EMP and CEMP)
No. Key Activities
or Environmental
Impact
EMP Requirement
(Mitigation
Measure)
Reference Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
General
Mobilization and Demobilization
1 Increased
vehicular
emissions and
noise due to
mobilization of
equipment and
materials
C.1 Truck that will
deliver dust-
generating
construction
materials will be
covered with canvas
or other suitable
material to minimize
dust dispersion
IEE, CEMP Yes Delivery trucks are covered with a tarp
None
2 Increased
vehicular
emissions and
noise due to
mobilization of
equipment and
materials
C.2 Contractor will
ensure regular
maintenance and
inspection of
construction
vehicles, including
emissions testing
certificate
IEE, CEMP Yes Inspection of vehicle and equipment was
conducted prior to commencement of work.
None
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
58
No. Key Activities
or Environmental
Impact
EMP Requirement
(Mitigation
Measure)
Reference Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
Vehicle and equipment checklist
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
59
No. Key Activities
or Environmental
Impact
EMP Requirement
(Mitigation
Measure)
Reference Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
Example of HDE checklist
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
60
No. Key Activities
or Environmental
Impact
EMP Requirement
(Mitigation
Measure)
Reference Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
61
No. Key Activities
or Environmental
Impact
EMP Requirement
(Mitigation
Measure)
Reference Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
Examples of gas emission testing certificates:
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
62
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
63
No. Key Activities
or Environmental
Impact
EMP Requirement
(Mitigation
Measure)
Reference Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
3 Increased
vehicular
emissions and
noise due to
mobilization of
equipment and
materials
C.3. Use multi-
passenger vehicles
to transport workers
to and from the well
sites
IEE, CEMP Yes
None
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
64
No. Key Activities
or Environmental
Impact
EMP Requirement
(Mitigation
Measure)
Reference Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
4 Increased
vehicular
emissions and
noise due to
mobilization of
equipment and
materials
C.4. Stockyard will
be covered during
the
non-working period
IEE, CEMP Yes
None
5 Increased
vehicular
emissions and
noise due to
mobilization of
equipment and
materials
C.5 Vehicles and
equipment will not be
allowed to sit and
idle for more than 30
minutes
IEE, CEMP Yes Briefing for drivers and co-drivers before the
commencement of work. Discussion not allowing
the vehicle to idle for 30 minutes is included in
the briefing.
None
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
65
No. Key Activities
or Environmental
Impact
EMP Requirement
(Mitigation
Measure)
Reference Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
Waste Management
1 Generation of
waste
C.23. Provide
garbage bins at
basecamp
IEE, CEMP Yes Waste segregation at site office and basecamp
None
2 Generation of
waste
C.24. Contractor to
prepare waste
management plan
(as part of CEMP),
approved by PMC
IEE Yes Waste Management Sub-Plan has been
developed and attached as a supplementary
document in the SPC CEMP. PMU has approved
waste MPS.
None
Soil Drilling with Auger
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
66
No. Key Activities
or Environmental
Impact
EMP Requirement
(Mitigation
Measure)
Reference Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
1 Generation of
waste
Soil waste will be
disposed of at
designated areas
Utilize drilled soil for
backfilling
CEMP Yes
None
2 Erosion and
sedimentation
control
Make bund wall at
the surrounding of
the soil waste
disposal area
CEMP Yes
None
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
67
No. Key Activities
or Environmental
Impact
EMP Requirement
(Mitigation
Measure)
Reference Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
3 Erosion and
sedimentation
control
Maintenance of bund
wall
CEMP Yes
None
Cementing
1 Chemical spills and
wastewater
discharge the
environment
Chemical handling
and storage refers to
MSDS. MSDS of
chemicals to be
available
CEMP Yes Examples of MSDS of chemicals onsite None
Bund Wall Maintenance
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
68
No. Key Activities
or Environmental
Impact
EMP Requirement
(Mitigation
Measure)
Reference Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
69
No. Key Activities
or Environmental
Impact
EMP Requirement
(Mitigation
Measure)
Reference Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
70
No. Key Activities
or Environmental
Impact
EMP Requirement
(Mitigation
Measure)
Reference Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
2 Chemical spills
and wastewater
discharge the
environment
Install tarpaulin and
bund wall as the
ground
mat to avoid
chemical spill to the
environment
CEMP Yes
None
3 Chemical spills
and wastewater
discharge the
environment
Chemical spill kit to
be made ready
within the working
location
CEMP Yes
None
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
71
No. Key Activities
or Environmental
Impact
EMP Requirement
(Mitigation
Measure)
Reference Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
4 Chemical spills and
wastewater
discharge the
environment
Excavate sump
pit(s) temporarily as
ground mat to avoid
chemical spill to the
accommodate
wastewater
environment
generated during the
mixer washing
activity
CEMP Yes
None
5 Chemical spills and
wastewater
discharge the
environment
Install whip check on
hose connection
CEMP Yes
None
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
72
No. Key Activities
or Environmental
Impact
EMP Requirement
(Mitigation
Measure)
Reference Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
6 Poor
housekeeping on
waste generation
from cement
package or
grouting
additive bucket
Re-Use bucket
refers to waste
management Sub-
plan
CEMP Yes
None
7 Poor
housekeeping on
waste generation
from cement
package or
grouting
additive bucket
Segregate waste of
cement package
CEMP Yes
None
Access Road work and Preparation Well Pad (Cut and Fill Activity)
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
73
No. Key Activities
or Environmental
Impact
EMP Requirement
(Mitigation
Measure)
Reference Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
1 Erosion / landslide
(sediment
run-off) due to cut
and fill land
clearing pad
BB
Mapping area for
land clearing plan
CEMP Yes
None
2 Erosion / landslide
(sediment
run-off) due to cut
and fill land
clearing pad
BB
Conduct EHS
Induction specifically
designed for
Loc BB works
CEMP Yes
None
3 Erosion / landslide
(sediment
run-off) due to cut
and fill land
clearing pad BB
Install bund wall on
the slope (especially
at the extreme pitch)
CEMP Not
applicable
Installation of geotextile to cover the extreme
slope at Well Pad-31 Dieng site. Patuha-2 has
not yet started the work at the severe slope.
None
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
74
No. Key Activities
or Environmental
Impact
EMP Requirement
(Mitigation
Measure)
Reference Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
4 Land clearing
waste
management
Land clearing waste
(e.g., tree logs) will
be utilized as bund
wall construction
CEMP Yes
None
5 Erosion / landslide
(sediment
run-off) due to
exposed soil
Maintenance of
sediment trap
CEMP Yes A sediment trap is installed at three locations:
1. Upstream of Cipadaruum River
2. STA200 of Cipadaruum River (within the
boundary)
3. Downstream of Cipadaruum River
None
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
75
No. Key Activities
or Environmental
Impact
EMP Requirement
(Mitigation
Measure)
Reference Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
(1) Sediment trap at upstream of
Cipadaruum River
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
76
No. Key Activities
or Environmental
Impact
EMP Requirement
(Mitigation
Measure)
Reference Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
(2) Sediment trap at downstream of
Cipadaruum River
6 Water
contamination due
to erosion and
sedimentation
Propose Silt Fence
installation
(Polypropylene
Geotextile, 30cm
above ground, 15cm
inside the ground,
steel wire strap) on
runoff track
downstream
CEMP Yes
None
7 Water
contamination due
to erosion and
sedimentation
Propose to construct
control box for
monitoring
sedimentation
(Permit to local
government by
GDE)
Install bund wall filter
on runoff track
downstream
CEMP Yes The control box is installed downstream to
accommodate the runoff. The size of the control
box is 2mx2m
None
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
77
No. Key Activities
or Environmental
Impact
EMP Requirement
(Mitigation
Measure)
Reference Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
8 Water
contamination due
to erosion and
sedimentation
Construction of
temporary ditch at
Loc BB to
accommodate runoff
and flow it to the
sediment trap
CEMP Yes
None
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
78
No. Key Activities
or Environmental
Impact
EMP Requirement
(Mitigation
Measure)
Reference Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
79
No. Key Activities
or Environmental
Impact
EMP Requirement
(Mitigation
Measure)
Reference Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
9 Forest fire
Mortality of
individuals,
from poaching by
construction
workers.
Install a sign of no
burning waste and
open fire at all
construction sites
and porta camp.
Install signage of no
hunting/poaching of
wildlife.
IEE, CEMP Yes
None
10 Mortality of
individuals
from poaching by
construction
workers.
Implement a strict
code of conduct
forbidding
hunting/trapping and
the purchase of
wildlife, with
IEE, CEMP Yes None
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
80
heavy penalties.
Train all personnel
on this code of
conduct and its
justification.
Delivery of
biodiversity induction
to all personnel
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
81
No. Key Activities
or Environmental
Impact
EMP Requirement
(Mitigation
Measure)
Reference Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
82
11 Mortality of wildlife
due to construction
works
Delivery of special
induction for work at
Pad BB to all
personnel
Implement a strict
code of conduct
forbidding
hunting/trapping and
the purchase of
wildlife, with
heavy penalties.
Train all personnel
on this code of
conduct, and its
justification
CEMP Yes None
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
83
No. Key Activities
or Environmental
Impact
EMP Requirement
(Mitigation
Measure)
Reference Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
12 Biodiversity loss Propose additional
free space from
boundary area to
slope bottom
normally 20 m space
CEMP No Contractor needs to confirm to GDE regarding
this measure due to it is out of scope of the
contract
Contractor
has not
confirm yet
this task to
GDE
13 Mortality of
individuals,
owing to induced
access for
poachers/hunters
via project roads
Propose
construction of
temporary fence
using zinc and wood
frame along the
boundary
IPPKH to protect
IEE, CEMP Complete IPPKH boundary is marked by rope and safety
line.
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
84
No. Key Activities
or Environmental
Impact
EMP Requirement
(Mitigation
Measure)
Reference Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
the working area
from unauthorized
person entrance
Zinc fence to mark the boundary of pad area
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
85
No. Key Activities
or Environmental
Impact
EMP Requirement
(Mitigation
Measure)
Reference Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
14 Loss of vegetation
cover in specific
areas of the
project.
Follow existing
documents,
including IPPKH and
map, vegetation
inventory,
conceptual
design, etc.
CEMP Yes
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
86
No. Key Activities
or Environmental
Impact
EMP Requirement
(Mitigation
Measure)
Reference Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
15 Loss of vegetation
cover in specific
areas of the project
Joint survey
with relevant
PMU's
representative
and Perhutani
to identify
IPPKH
boundary and
demarcate
working area
before
construction
commencement
CEMP Yes
16 Mortality of
individuals,
owing to induced
access for
poachers/hunters
via project roads
Do not trespass
IPPKH boundary
barricade lines and
sign this information
will be included in
the HSE Induction
IEE, CEMP Yes
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
87
No. Key Activities
or Environmental
Impact
EMP Requirement
(Mitigation
Measure)
Reference Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
17 Loss of vegetation
cover in specific
areas of the
project.
Providing for
pre-clearing surveys
to be undertaken by
a suitably qualified
ecologist to mark
and map hollow-
bearing trees,
logs, and existing
nest boxes that
would require
fauna management
during removal.
IEE, CEMP Yes
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
88
No. Key Activities
or Environmental
Impact
EMP Requirement
(Mitigation
Measure)
Reference Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
18 Modification and
fragmentation of
habitat
due to loss of
vegetation
cover.
Vegetation removal
works during land
clearing
should be
supervised by
a suitably qualified
ecologist for
native or endemic
species to West
Java. Coordination
and communication
with personnel
involved (Contractor,
LH, GDE)
CEMP Yes
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
89
No. Key Activities
or Environmental
Impact
EMP Requirement
(Mitigation
Measure)
Reference Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
19 Displacement of
species due to
noise from normal
traffic, operation or
maintenance
activities.
Should any
wildlife encounter
during the
land clearing
process, wildlife
shepherding
refers to Biodiversity
Action Plan
CEMP Yes
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
90
No. Key Activities
or Environmental
Impact
EMP Requirement
(Mitigation
Measure)
Reference Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
20 Mortality of wildlife
due to construction
works
A hollow tree fell,
shall not be cut,
removed or piled for
another 24 hours to
provide chance for
animals to move
away. The hollow
trees shall then be
placed in the area of
habitat or the
substitute habitats.
CEMP Yes
21 Mortality of
individuals,
because of
induced access for
poachers/ hunters
via project roads
Set up boundary
/marking area
using a safety line
IEE, CEMP Yes
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
91
No. Key Activities
or Environmental
Impact
EMP Requirement
(Mitigation
Measure)
Reference Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
22 Mortality of wildlife
due to construction
works
Found a cave at the
STA 200 access
road to BB. SPC
team reported
directly to PMU and
recorded the finding
in the available form.
CEMP Yes
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
92
No. Key Activities
or Environmental
Impact
EMP Requirement
(Mitigation
Measure)
Reference Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
23 Mortality of wildlife
due to construction
works
Found the footprint
animal (leopard) at
PPL 04. SPC team
reported directly to
PMU and recorded
the finding in the
available form.
CEMP Yes
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
93
No. Key Activities
or Environmental
Impact
EMP Requirement
(Mitigation
Measure)
Reference Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
24 Land clearing
activity
Land clearing to
follow the approved
IPPKH boundary
CEMP Yes
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
94
25 Land clearing
activity
Topsoil was
collected and stored
at a designated soil
disposal storage
area at PPL 04.
CEMP Yes
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
95
No. Key Activities
or Environmental
Impact
EMP Requirement
(Mitigation
Measure)
Reference Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
96
For all ‘Partial’ or ‘No’ compliance issues in the table above, the actions needed to solve the compliance issues are summarized in Table 14.
Table 14. EMP– Actions Needed for Compliance – Patuha-2
No EMP Requirement Further Action to Take Date for Action Who will Implement Action
01 C.11 Rotate workers every two
hours to prevent discomfort
Develop plan and procedure on how to
rotate workers who assigned to high-level
noise-generating works (100 dB(A)
End of February 2022 Contractors
02
C.22 Oil-water separator shall be
provided for oily washings in the
drilling equipment and trucks
Provide oil water separator (sump pit) in
drilling site End of February 2022 PMU
03
Label the waste container to help
identify the appropriate waste type
and promote segregation.
Contractor to attach a label on each waste
container to place the waste type 31 January 2022 Civil Contractor
04
Propose additional free space from
boundary area to slope bottom
normally 20 m space
Contractor confirm to GDE regarding this
mitigation measure End of February 2022 Civil Contractor
Table 15 provides information on environmental performance issues from previous Environmental Monitoring Reports. This table confirms that the action was
completed or that the step is outstanding.
Table 15 EMP Compliance Outstanding Issues from Previous Report – Patuha-2
No EMP Requirement Further Action to
Take
Responsibility and
Timing
Resolution Required Action
1 A.1 Optimization of community
counselling/ simulation to handling H2S
exposure by GDE Peduli (CSR) or third
party
The H2S ERP drilling
with Community plans
to be conducted after
no covid- 19 activity
restriction
PMU, before drilling
activity
COMPLETED- the
action was taken
October 8, 2021, and
participated by 26
female and 26 male
community members.
NA
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
97
3.2 Health and Safety Performance
To manage the COVID-19 risk during the project implementation, GDE and PMU have developed a COVID-19 Standard Operational Procedure
(GDE/PST/HSE/SOP/006-R1 for Head Office, GDE.PTH/HSE/SOP.041 for Patuha, GDE/DIENG/EN/MEN 001 for Dieng, GDE/PMU/HSS/SOP/014 for Project)
and assessment and monitoring tools (sacovid.geodipa.co.id). PMU also makes sure that every contractor must submit HSE Plan that includes COVID-19
Procedure before doing an activity at the project site.
Health and Safety Compliance of Dieng-2 Sub Project
Table 16 outlines the Health and Safety impact mitigation measures in the EMP and how the project implements the mitigation measures for all subprojects.
Table 16 Status of Health and Safety Compliance All Subproject Dieng-2
No Key
Activities/Environmental
Impact
EMP Requirement
(Mitigation
Measure)
Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
1 Potential transport-related
and road accidents
(movement of
construction and service
vehicles)
C.19. Contractor to
assign staff
continuously to
manage traffic and to
ensure public safety
dissemination to
affected people in the
villages/sub-villages
Yes Comply It is stated in Journey Management Plan approved by PMU
Road traffic arrangements involving residents/locals hire an
escort by Police
None
C.20. Temporary
public crossing points
will be provided
accommodating
children, the elderly,
and persons with
disabilities
NA Mobilization is mostly carried out at night when there is no
public activity, so Temporary public crossings are not
provided to accommodate children, the elderly, and persons
with disabilities. but if anyone wants to cross, they will be
guided by an appointed officer
None
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
98
No Key
Activities/Environmental
Impact
EMP Requirement
(Mitigation
Measure)
Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
C.21. Clear and
visible traffic warning
signs will be installed,
and adequate lighting
will be provided.
Yes Comply
Warning sign
None
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
99
No Key
Activities/Environmental
Impact
EMP Requirement
(Mitigation
Measure)
Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
2 Occupational health risks C.30. Conduct
training on safety and
health hazards at
least monthly
Yes Comply,
attendance list
and photograph
have been
recorded and
archived.
None
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
100
No Key
Activities/Environmental
Impact
EMP Requirement
(Mitigation
Measure)
Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
C.31. Provide
sanitary facilities and
safe drinking water at
the construction site
and the workers’ camp
Yes Comply,
Contractor has
developed
Hygiene and
Sanitation
Procedure to be
implemented for
this project
Clean water trucks for sanitary facilities and defecation area
None
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
101
No Key
Activities/Environmental
Impact
EMP Requirement
(Mitigation
Measure)
Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
C.32. Provide
workers with PPEs
such as goggles,
safety shoes, etc.,
and its use will be
mandatory
Yes Comply,
Contractor has
provided
distributed PPE
to all workers
involved in this
project and
monitor PPE
Compliance
Distribution of PPE to workers
None
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
102
No Key
Activities/Environmental
Impact
EMP Requirement
(Mitigation
Measure)
Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
C.33. Workers who
will be assigned to
high-level noise-
generating works
(100 dB(A) will be
rotated every two
hours aside from
wearing of
PPEs.
Yes Comply None
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
103
No Key
Activities/Environmental
Impact
EMP Requirement
(Mitigation
Measure)
Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
C.34. Conduct daily
toolbox meetings to
emphasize safety
and health
procedures
Yes Comply None
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
104
No Key
Activities/Environmental
Impact
EMP Requirement
(Mitigation
Measure)
Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
C.35. Site Engineers
to encourage brief
exercise routine to
highlight the value of
health in the
workplace
Yes Comply,
there is a
routine briefing
on safety issues
to all workers,
i.e. briefing on
H2S issue,
briefing on
safety lesson
learned, etc
None
C.36. Employees of
the contractor(s) will
be required to have
an annual physical
and medical
examination. Health
records will be kept
confidential in the
employee file.
Yes Comply
All workers involved in the drilling activities have been
screened on their health condition by medical check-up.
Workers medical check-up data have been reviewed, and
GDE keeps the result
None
C.37. Install clear and
visible warning signs
Yes Comply None
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
105
No Key
Activities/Environmental
Impact
EMP Requirement
(Mitigation
Measure)
Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
as well as sufficient
lighting
Warning sing at the drilling site
C.38. Contractors will
be required to follow
relevant HSE SOPs
of GDE and relevant
IFC-EHS General
Guidelines 2007
(Section 2)
Yes Comply
.
GDE has established an Occupational Health and Safety
Management System consisting of policy, manual, plan, and
procedure. These OHS-MS requirements, including ADB
Safeguard requirements, are mandated to all Contractors in
the construction contract documents.
None
3 Occupational health risks
during drilling works
C.65. Base camp to
be provided with
sanitary facilities,
wash areas, safe
Yes compy Evidence has been attached in number C31 None
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
106
No Key
Activities/Environmental
Impact
EMP Requirement
(Mitigation
Measure)
Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
drinking water, and
garbage bins to
contain waste
generated by
workers
C.66. Location of the
base camp shall not
be close to
settlements and
water bodies
Yes Comply Most workers are live-in homestay in Dieng area, some of
them live in base camp
None
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
107
No Key
Activities/Environmental
Impact
EMP Requirement
(Mitigation
Measure)
Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
C.67. Local hiring
shall be a priority to
minimize the number
of workers in
base camp
Yes Comply Crew Local Hire Rig PRA 09 None
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
108
No Key
Activities/Environmental
Impact
EMP Requirement
(Mitigation
Measure)
Compliance
and
Description
(Yes, No,
Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
C.68. Fuel
requirements in
onsite fuel tanks and
generators shall be
located in designated
contained areas to
prevent leaks
Yes Comply
Pre Determined Fuel Storage Area
None
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
109
Health and Safety Compliance of Patuha-2 Sub Project
3.2.2.1 Drilling Work Activity
Table 17 Status of Health and Safety Compliance of Patuha-2 (Drilling)
No Key
Activities/Environmental
Impact
EMP Requirement
(Mitigation Measure)
Compliance and
Description
(Yes, No, Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
1 Increased community
health and safety risks,
i.e.,
contact with vehicles and
equipment, increased
access to restricted sites,
increased dust and gas
exposure
B.14 Develop occupational
and community health and
safety management
plan for subsequent
dissemination at the EHS
induction and
dissemination to affected
people in the villages/sub-
villages
Partially Comply
GDE has
established an
Occupational
Health and Safety
Management
System consisting
of policy, manual,
plan, and
procedure.
However, related to
community safety,
particularly safety
risk due to Patuha
Unit 2 project, there
is no document
Available
GDE has carried out EHS induction to the
affected village through the Socialization of
Masyarakat Tanggap Bencana (Community
Responsive Disaster) to increase community
awareness of disasters and emergencies.
Socialization was held on 17 December 2021 in
Kendeng Sub-Village, Sugihmukti Village.
In Addition to that, GDE also has conducted
Socialization and Simulation of Handling Hazard
of H2S Gas to Community of Kendeng Sub-
Village, Sugihmukti Village on 7 and 8 October
2021
Need to establish Community Health and Safety
Management Plan
In fact, there is
no evidence
that
community
health and
safety risks
increased due
to contact with
vehicles and
equipment
and dust and
gas exposure
as well.
However,
GDE realizes
that the
community
need to
educate and
familiarize
themselves
with the
Geothermal
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
110
No Key
Activities/Environmental
Impact
EMP Requirement
(Mitigation Measure)
Compliance and
Description
(Yes, No, Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
process and
the risks.
2 Occupational health risks C.25. Conduct training on
safety and health hazards
at least monthly
Yes Comply,
attendance list and
photograph have
been recorded and
archived.
C.26. Provide sanitary
facilities and safe drinking
water at the construction
site and the workers’ camp
Yes Comply,
Contractor has
developed Hygiene
and Sanitation
Procedure to be
implemented for
this project
None
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
111
No Key
Activities/Environmental
Impact
EMP Requirement
(Mitigation Measure)
Compliance and
Description
(Yes, No, Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
C.27. Provide workers with
PPEs such as gogles,
safety shoes, etc., and its
use will be mandatory
Yes Comply,
Contractor has
provided
distributed PPE to
all workers involved
in this project and
monitor PPE
Compliance
None
C.28. Workers who will be
assigned to high-level
noise-generating works
(100 dB(A) will be rotated
every two hours aside from
wearing of
PPEs.
N For the worker who was working in a noisy area,
the Contractor provided safety devices
Due to the
limited
competence
operator on
site, it is
impossible to
rotate the
operator every
two hours.
However, the
Contractor
allowed the
operator who
was working in
a noisy area to
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
112
No Key
Activities/Environmental
Impact
EMP Requirement
(Mitigation Measure)
Compliance and
Description
(Yes, No, Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
take a break
every two
hours if
possible
C.29. Conduct daily
toolbox meetings to
emphasize safety and
health procedures
Yes Comply
None
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
113
No Key
Activities/Environmental
Impact
EMP Requirement
(Mitigation Measure)
Compliance and
Description
(Yes, No, Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
C.30. Site Engineers to
encourage brief exercise
routine to highlight the
value of health in the
workplace
Yes Comply, there
is a routine briefing
on safety issues to
all workers, i.e.
briefing on H2S
issue, briefing on
safety lesson
learned, etc
C.31. Employees of the
contractor(s) will be
required to have an annual
physical and medical
examination. Health
records will be kept
confidential in the
employee file.
Yes Comply
All workers involved in the drilling activities have
been screened on their health condition by
medical check-up. Workers medical check-up
data have been reviewed, and GDE keeps the
result
None
C.32. Install clear and
visible warning signs as
well as sufficient lighting
Yes Comply None
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
114
No Key
Activities/Environmental
Impact
EMP Requirement
(Mitigation Measure)
Compliance and
Description
(Yes, No, Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
C.33. Contractors will be
required to follow relevant
HSE SOPs of GDE and
relevant IFC-EHS General
Guidelines 2007 (Section
2)
Yes Comply
.
GDE has established an Occupational Health
and Safety Management System consisting of
policy, manual, plan, and procedure. These
OHS-MS requirements, including ADB Safeguard
requirements, are mandated to all Contractors in
the contract document.
None
3 Community safety risk
during equipment
mobilization
C.34. Clear and visible
danger and warning
signs/posters will be
installed temporarily in
areas affected by
mobilization (i.e.,
Kampung Alam Endah,
Sugih Mukti, and
Panundaan)
Yes Comply,
Contractor already
developed Journey
Management Plan
before mobilization
activity and
implemented during
mobilization activity.
Journey
Management Plan
is included in
CEMP
None
C.35. Provide temporary
crossing that will
accommodate women,
children and persons with
disabilities
N/A. Mobilization is
mostly conducted
during the night; no
need to provide
quick crossing
None
C.36. Will coordinate with
village head on the
schedule of mobilization of
heavy equipment and
machinery
Yes Comply,
Contractor
submitted
information letter to
the village head.
Documentation of
communication with
None
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
115
No Key
Activities/Environmental
Impact
EMP Requirement
(Mitigation Measure)
Compliance and
Description
(Yes, No, Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
village head is
recorded in JMP
C.37. Staff/workers will be
assigned to manage traffic
within the communities
affected
Yes Comply None
C.38. Emergency system
and equipment such as
fire-fighting, ambulance,
etc., will be made available
during mobilization along
Kampung Alam Endah and
Panundaan, including the
provincial road in Bandung
that will be used during
mobilization in case of an
accident
Yes comply None
4 Disruption to local traffic C.39. Contractor will be
required to prepare a
traffic management plan in
consultation with local
authorities in Panundaan,
Sugih Mukti, and Alam
Endah and the provincial
agency in Bandung
Yes Comply Contractor already developed Journey
Management Plan and implemented during
mobilization activity
None
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
116
No Key
Activities/Environmental
Impact
EMP Requirement
(Mitigation Measure)
Compliance and
Description
(Yes, No, Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
C.40. Conduct public
consultations on the route
that will be taken for
mobilization
Yes Comply, a
public consultation
was held on 21
September 2021
None
C.41. Conduct a pre-
mobilization survey of the
route to be taken to assess
if adequate space or
corridor is available, load
capacity of bridges, the
condition of public roads
including buildings/houses
close to the roads (~100
m), the situation of public
roads and dwellings along
the routes as the baseline
for road rehabilitation or
damage claims
Yes Comply Contractor conduct pre-mobilization survey prior
to developing Journey Management Plan/JMP
and survey result recorded in JMP
None
C.42. Staff will be
designated to manage
Yes Comply It is stated clearly in JMP None
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
117
No Key
Activities/Environmental
Impact
EMP Requirement
(Mitigation Measure)
Compliance and
Description
(Yes, No, Partial)
Comment or Further Explanation if Needed Reasons for
Not Full
Compliance
traffic along the route for
mobilization
5 The influx of workers in
the
Sugih Mukti may cause
social conflicts with local
people
C.77. Inform workers
during orientation of their
responsibility in observing
proper behaviour in
dealing with local residents
and the consequence of
non-compliance
Yes Comply It was informed during general induction for all
workers before drilling activity on 11 and 12
November 2021
None
C.78. Provide workers with
a list of “do’s and don’t’s” to prevent potential
conflicts with residents
Yes Comply It was informed during general induction for all
workers before drilling activity on 11 and 12
November 2021
None
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
118
3.2.2.2 Civil Work
No. Key Activities or Environmental Impact
EMP Requirement (Mitigation Measure)
Reference Compliance & Description (Yes, No, Partial)
Comment or Further Explanation if Needed Reasons for Not Full Compliance
General
1 Occupational health risks
C.25. Conduct training on safety and health hazards at least monthly
IEE, CEMP Yes First Aid training for construction worker
None
2 Occupational health risks
C.26 Provide sanitary facilities and safe drinking water at the construction site and the workers’ camp
IEE, CEMP Yes Bottled water is provided at the basecamp and construction site
None
3 Occupational health risks
C.28. Workers who will be assigned to high-level noise-generating works
IEE Not applicable No noise generation works (including machinery, equipment, etc.) were observed from July to December 2021. Despite of this condition, the hearing protection (earplugs) are provided onsite for use.
None
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
119
No. Key Activities or Environmental Impact
EMP Requirement (Mitigation Measure)
Reference Compliance & Description (Yes, No, Partial)
Comment or Further Explanation if Needed Reasons for Not Full Compliance
(100 dB(A) will be rotated every two hours aside from wearing of PPEs.
4 Occupational health
risks C.30. Site Engineers to encourage brief exercise routine to highlight the value of health in the workplace
IEE, CEMP Yes Routine briefing of site engineers for occupational health and safety training
None
5 Occupational health risks
C.31. Employees of the contractor(s) will be required to have an annual physical and medical examination. Health records will be kept confidential in the employee file.
IEE, CEMP Yes An annual medical check-up is conducted for all personnel
None
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
120
No. Key Activities or Environmental Impact
EMP Requirement (Mitigation Measure)
Reference Compliance & Description (Yes, No, Partial)
Comment or Further Explanation if Needed Reasons for Not Full Compliance
6 Occupational health
risks C.33. Contractors will be required to follow relevant HSE SOPs of GDE and applicable IFC-EHS General Guidelines 2007 (Section 2
IEE Yes CEMP of SPC was developed following the IEE, ADB SPS, and relevant regulatory frameworks (IFC HSE Guidelines, etc.). PMU has approved the CEMP.
None
Mobilization and Demobilization
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
121
No. Key Activities or Environmental Impact
EMP Requirement (Mitigation Measure)
Reference Compliance & Description (Yes, No, Partial)
Comment or Further Explanation if Needed Reasons for Not Full Compliance
1 Occupational health risk
C.27. Provide workers with PPEs such as goggles, safety shoes, etc. and its use will be mandatory
IEE, CEMP Yes
None
2 Occupational health risk
C.29. Conduct daily toolbox meetings to emphasize safety and health procedures
IEE, CEMP Yes Briefing for drivers and co-drivers before the commencement of work. This item was included in the briefing.
None
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
122
No. Key Activities or Environmental Impact
EMP Requirement (Mitigation Measure)
Reference Compliance & Description (Yes, No, Partial)
Comment or Further Explanation if Needed Reasons for Not Full Compliance
3 Occupational health
risk Drivers and equipment should have licenses and certificates
CEMP Yes Copy of license and certificates of equipment and driver
None
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
123
No. Key Activities or Environmental Impact
EMP Requirement (Mitigation Measure)
Reference Compliance & Description (Yes, No, Partial)
Comment or Further Explanation if Needed Reasons for Not Full Compliance
4 Community safety risk during equipment
C.34. Clear and visible danger and warning signs/posters
IEE, CEMP Yes Installation of signage and installation of safety lines along the mobilization access route.
None
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
124
No. Key Activities or Environmental Impact
EMP Requirement (Mitigation Measure)
Reference Compliance & Description (Yes, No, Partial)
Comment or Further Explanation if Needed Reasons for Not Full Compliance
mobilization will be installed temporarily in areas affected by mobilization (i.e., Kampung Alam Endah, Sugih Mukti, and Panundaan)
5 Community safety risk during equipment mobilization
C.35. Provide temporary crossing that will accommodate women, children and persons with disabilities
IEE, CEMP Not applicable No temporary crossing will be installed. Mobilization is conducted predominantly during the nighttime. In addition, police and POKJA will assist the mobilization process in ensuring the safety of the adjacent community
Police and POKJA will assist in the mobilization process
6 Community safety risk during equipment mobilization
C.36. Coordinate with village head on the schedule of mobilization of heavy equipment and machinery
IEE, CEMP Yes Communication and Permission with Stakeholder (Desa Alam Endah, Pokja, Ormas, and other impacted villages)
None
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
125
No. Key Activities or Environmental Impact
EMP Requirement (Mitigation Measure)
Reference Compliance & Description (Yes, No, Partial)
Comment or Further Explanation if Needed Reasons for Not Full Compliance
7 Community safety risk during equipment mobilization
C.37. Staff/workers will be assigned to manage traffic within the affected communities
IEE, CEMP Yes Mobilization is assisted by police & POKJA (Paguyuban).
None
8 Community safety risk during equipment mobilization
C.38. Emergency system and equipment such as firefighting, ambulance, etc., will be made available during mobilization along with Kampung Alam Endah and Panundaan, including the provincial road in Bandung that will be used during mobilization in case of an accident
IEE, CEMP Not applicable The ambulance will be based on contract and arranged by PMU. However, nearest hospitals, police, and firefighting contact numbers are available in all vehicles.
None
9 Disruption to local traffic
C.39. Contractor will be required to prepare traffic management plan in consultation
IEE, CEMP Yes JMP has been established and approved by PMU prior to conducting mobilization and demobilization
None
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
126
No. Key Activities or Environmental Impact
EMP Requirement (Mitigation Measure)
Reference Compliance & Description (Yes, No, Partial)
Comment or Further Explanation if Needed Reasons for Not Full Compliance
with local authorities in Panundaan, Sugih Mukti, and Alam Endah and the provincial agency in Bandung
10 Community safety risk during equipment mobilization
C.40. Conduct public consultations on the route taken for mobilization.
IEE, CEMP Yes Public consultation at Desa Alam Endah, Pokja, Ormas, and other impacted villages
None
11 Disruption to local traffic
C.41. Conduct a pre-mobilization survey of the route to be taken to assess if adequate space or corridor is available, load capacity of bridges, the condition of public roads, including
IEE, CEMP Yes A Pre-mobilization survey had been conducted in the early stage of JMP development. JMP has been approved by PMU.
None
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
127
No. Key Activities or Environmental Impact
EMP Requirement (Mitigation Measure)
Reference Compliance & Description (Yes, No, Partial)
Comment or Further Explanation if Needed Reasons for Not Full Compliance
buildings/houses close to the roads (~100 m) the state of public roads and dwellings along the routes as the baseline for road rehabilitation or damage claims
12 Disruption to local traffic
C.42. Staff will be designated to manage traffic along the route for mobilization
IEE, CEMP Yes
None
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
128
No. Key Activities or Environmental Impact
EMP Requirement (Mitigation Measure)
Reference Compliance & Description (Yes, No, Partial)
Comment or Further Explanation if Needed Reasons for Not Full Compliance
Pipe Conductor Installation (Welding)
1 Occupational health issue (respiratory and eyes health-related problem)
Using a respiratory and a welding mask for all personnel performing welding task
IEE, CEMP Yes
None
2 Hazardous waste management
Waste segregation of hazardous waste Hazardous waste will be collected in a
IEE, CEMP Yes A dedicated container for hazardous waste is available at the construction site. Hazardous waste will be kept at existing place which covered by Temporary Hazarodus Waste Permit No. 658.31/03/V/BPMP. Symbol and labelling of
None
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
129
No. Key Activities or Environmental Impact
EMP Requirement (Mitigation Measure)
Reference Compliance & Description (Yes, No, Partial)
Comment or Further Explanation if Needed Reasons for Not Full Compliance
closed container and will be stored temporarily at the designated area An information signage will be installed at the hazardous waste temporary storage GDE has granted a permit for Hazardous Waste Temporary Storage form Bandung Regent No 658.31/03/V/BPMP
hazardous waste storage refer to PermenLH No. 14 of 2013
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
130
No. Key Activities or Environmental Impact
EMP Requirement (Mitigation Measure)
Reference Compliance & Description (Yes, No, Partial)
Comment or Further Explanation if Needed Reasons for Not Full Compliance
3 Hazardous waste management
Hazardous waste will be transported offsite regularly by a licensed third party
IEE, CEMP Yes
None
4 Hazardous material management
An information signage will be installed at the hazardous material storage area
CEMP Yes Hazard and safety awareness signs have been installed at the temporary storage. Temporary storage is also equipped with secondary containment, APAR, and chemical spill kit.
None
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
131
No. Key Activities or Environmental Impact
EMP Requirement (Mitigation Measure)
Reference Compliance & Description (Yes, No, Partial)
Comment or Further Explanation if Needed Reasons for Not Full Compliance
Hazardous material storage is equipped with a cover and secondary containment. An information sign is also available.
APAR is readily available at the hazardous material storage area.
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
132
No. Key Activities or Environmental Impact
EMP Requirement (Mitigation Measure)
Reference Compliance & Description (Yes, No, Partial)
Comment or Further Explanation if Needed Reasons for Not Full Compliance
5 Hazardous material management
Hazardous material containers will be equipped with symbol and label
CEMP Yes Symbol and label are attached to the solar container. Symbol and labelling of hazardous waste storage refer to PermenLH No. 3 of 2008
None
6 Hazardous material management
Chemical handling and storage refer to MSDS. MSDS of
CEMP Yes MSDS is made available onsite. MSDS is kept in the container next to the hazardous material storage.
None
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
133
No. Key Activities or Environmental Impact
EMP Requirement (Mitigation Measure)
Reference Compliance & Description (Yes, No, Partial)
Comment or Further Explanation if Needed Reasons for Not Full Compliance
chemicals to be available
Pipe Conductor Installation (Lifting and Rigging)
1 Occupational health risk
C.27. Provide proper PPEs
IEE, CEMP Yes
None
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
134
No. Key Activities or Environmental Impact
EMP Requirement (Mitigation Measure)
Reference Compliance & Description (Yes, No, Partial)
Comment or Further Explanation if Needed Reasons for Not Full Compliance
2 Occupational Incident and Property Damage
Develop lifting plan prior commencement of work
CEMP Yes
None
3 Occupational Incident and Property Damage
Conduct pre-use inspection
IEE, CEMP Yes
None
4 Occupational Incident and Property Damage
Crane Operator should have a valid Surat Izin Operator (SIO)
CEMP Yes Example of a valid SIO by a crane operator None
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
135
No. Key Activities or Environmental Impact
EMP Requirement (Mitigation Measure)
Reference Compliance & Description (Yes, No, Partial)
Comment or Further Explanation if Needed Reasons for Not Full Compliance
5 Occupational
Incident and Property Damage
Crane (equipment) should have a valid Surat Izin Laik Operasi (SILO)
CEMP Yes Example of a valid SILO of one of the equipment
None
6 Occupational Rigger should CEMP Yes Example of a valid lifting and rigging certificate None
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
136
No. Key Activities or Environmental Impact
EMP Requirement (Mitigation Measure)
Reference Compliance & Description (Yes, No, Partial)
Comment or Further Explanation if Needed Reasons for Not Full Compliance
Incident and Property Damage
have a valid lifting and rigging certificate
7 Occupational
Incident and Property Damage
Ensure the clearance of the working area
CEMP Yes
None
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
137
No. Key Activities or Environmental Impact
EMP Requirement (Mitigation Measure)
Reference Compliance & Description (Yes, No, Partial)
Comment or Further Explanation if Needed Reasons for Not Full Compliance
Signage to inform personnel about the operation of heavy-duty equipment.
8 Grievance Redress
Mechanism Use the established Grievance Mechanism to address and solve as personnel working on site related to occupational incident
IEE, CEMP Yes GRM Form provided in the SOP of Grievance Mechanism
None
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
138
No. Key Activities or Environmental Impact
EMP Requirement (Mitigation Measure)
Reference Compliance & Description (Yes, No, Partial)
Comment or Further Explanation if Needed Reasons for Not Full Compliance
Cementing
1 Occupational health risk
C.27. Provide proper PPE (body harness and raincoat) for personnel performing cement Mixing
IEE, CEMP Yes
None
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
139
No. Key Activities or Environmental Impact
EMP Requirement (Mitigation Measure)
Reference Compliance & Description (Yes, No, Partial)
Comment or Further Explanation if Needed Reasons for Not Full Compliance
2 Occupational health risk
MSDS socialization CEMP Yes
None
Access Road work and Preparation Well Pad (Cut and Fill Activity)
1 Occupational health risk
C.27. Rotate worker every 2 hours (maximum time allowed to perform task)
IEE, CEMP Yes
None
2 Occupational health risk
C.32. Install clear and visible warning signs as well as sufficient lighting
IEE, CEMP Not applicable Night-time work was not allowed.
3 Community safety risk during construction
Limit noise-generating activities during daytime periods
IEE, CEMP Not applicable Not applicable since no works identified with potential noise generation
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
140
Further Actions To be Taken
For all ‘Partial’ or ‘No’ compliance issues in the table above (applicable for drilling and civil works), the actions needed to solve the compliance issues are summarized in Table 18.
Table 18 Status of Health and Safety Actions Needed for Compliance - All subprojects
No Health and Safety Requirement Further Action to Take Date for Action Who will Implement Action
1 B.14 Develop occupational and community health and
safety management plan for subsequent
dissemination at the EHS induction and dissemination
to affected people in the villages/sub-villages
Develop Community Health
and Safety Plan End of February 2022 PMU
2 C.28. Workers who will be assigned to high-level
noise-generating works (100 dB(A) will be rotated
every two hours aside from wearing of
PPEs.
Develop plan and procedure
on how to rotate workers
who assigned to high-level
noise-generating works (100
dB(A)
End of February 2022 PMU
There were no outstanding health and safety issues in the previous SEMR; therefore, no actions needed to be taken from the last SEMR reports are reported.
Table 19 EMP Compliance Outstanding Issues from Previous Report(s) – All subprojects
Issue Required Action Responsibility and Timing Resolution Required Action
N.A. N.A. N.A. N.A. N.A.
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
141
3.3 Biodiversity Action Plan Implementation
Table 20 Biodiversity Action Plan Implementation
No. Impact Mitigation Measure Compliance and Description (Yes, No, Partial)
Comment or Further Explanation if Needed
Reasons for Not Full Compliance
1 Loss of vegetation cover in specific areas of the project.
Minimise forest clearance alongside the right of way and around well pads.
Yes, Complete forest clearance performed by GANIS (Tenaga Teknis or technical professional) from the forestry department. Tree cutting was performed based on a plan defined by GANIS
None None
Source construction materials from outside of forested areas.
Yes Comply
Currently, the material used is soil for access road filling. The soil was carried from the outside forest area
None
2
Modification and fragmentation of habitat due to loss of vegetation cover
Retain tree canopy connectivity over the new road wherever possible.
NA To be conducted later None
Install appropriate canopy bridges to increase connectivity over the road for primates.
NA To be conducted later
3 Introduction of invasive alien species.
Regularly maintain and inspect/certificate all vehicles, equipment and machinery to ensure that noise levels conform to prescribed standards.
Yes Comply
All vehicles are checked before use, including the build year, regular service evidence and emission test.
None
4 Mortality of individuals from poaching by construction workers.
Mortality of individuals from poaching by construction workers. Mortality of individuals from poaching by construction workers.
NA
Poaching is prohibited, and the Contractor has declared poaching policy and socialized to all workers
None None
5
Displacement of
species
due to noise,
presence
Regularly maintain and inspect/certificate all vehicles, equipment and machinery to ensure that noise levels conform to prescribed standards.
Yes Comply
All vehicles are checked before use, including the build year, regular service evidence and emission test.
None
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
142
No. Impact Mitigation Measure Compliance and Description (Yes, No, Partial)
Comment or Further Explanation if Needed
Reasons for Not Full Compliance
of machinery and
equipment and
presence
of staff.
Table 21 Status of Biodiversity Actions Needed for Compliance - All subprojects
No. Key Activities or
Environmental Impact EMP Requirement
Further Action to Take
Corrective Action Plan
Date for
Action
Who Will
Implement
Action
1 Forest Damage Propose additional free space from
boundary area to slope bottom normally
20m space
PMU will determine if this mitigation
measure is relevant and implemented by
the Contractor.
TBD PMU
2 Habitat fragmentations
due to land clearing
• Retain tree canopy connectivity over the new road wherever possible.
• Install appropriate canopy bridges to increase connectivity over the road for
primates.
PMU will determine if this mitigation
measure is relevant and implemented by
the Contractor.
TBD PMU
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
143
4 EMP MONITORING
4.1 Environmental Quality Monitoring
Environmental quality monitoring requirements are discussed in Section 9.5 of EMP. Table 22 summarises the environmental quality monitoring requirements
for each subproject.
The following table gives information on the environmental quality monitoring implemented during this reporting period. Maps, photos and detailed results
compared to relevant national and/or international standards are presented in Appendix B.
Table 22 Implemented EMP Environmental Quality Monitoring
Subproject Environmental Issue Monitored Location Monitoring
Period
Monitoring
Status/Progress
Responsible
Organisation
Dieng-2
Sub-Project
Visual confirmation of necessary
repairs/improvements to existing
facilities in measures A.1. to A.8.
Well pads 7, 9, 10, 30, 31 During DED and
initial stage of
construction
Completed PMU
DED includes measures B.4. – B.10 Power Plant Unit 2 After the EPC
contract awarded
To be conducted EPC Contractor
Working GRM, information centre
set up, updated GDE website,
availability of project-related flyers
and other social media (measures
B.11. – B.13.)
Power Plant Unit 2 Before the start of
construction works
Completed PMC and PMU
Site-specific EMP prepared by
contractors reflecting requirements
as defined in measure B.15.
N/A Before the start of
construction works
Completed PMC and PMU
Ocular inspection of road condition,
temporary enclosures along the
affected road
Road intersection at
Kejajar market and
transport station,
and Garung, Dieng
Wetan and Dieng
Kulon intersection
Quarterly during
well development
Conducted before
mobilization on
September 2021
Certificate of service vehicles on
emissions testing
Completed PMC and PMU
Conducted regular ambient air
quality monitoring: NO2, PM10, PM2.5
Monitoring points defined
in the EMP report’s Figure Quarterly during
well development
Conducted on July
and October 2021
PMU and
Sucofindo
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
144
Subproject Environmental Issue Monitored Location Monitoring
Period
Monitoring
Status/Progress
Responsible
Organisation
Conduct ambient noise monitoring
in settlements along the affected
roads
4.3 (or Appendix B -
Figure 1 in Appendix B)
Quarterly during
well development
Conducted on July
and October 2021
PMU and
Sucofindo
Record of a road accident, number
and type of vehicles, and damages
to road and associated
infrastructure
Road intersection at
Dieng Kulon, Bakal,
Karang Tengah,
Once before the
start of
mobilization
Conducted before
mobilization on
September 2021
Contractor
Ocular inspection of transportation
routes to confirm the adequacy of
temporary road crossings, traffic
warning signs, Presence of
designated staff to manage traffic
Road intersection at Dieng
Kulon, Bakal, Karang
Tengah, Kepakisan, Dieng
Wetan
Quarterly during
well development
Conducted before
mobilization on
September 2021
Contractor
Contractor’s documents on payment for damages to affected people (if
any).
Road intersection at
Karang Tengah, Bakal,
Dieng Kulon -
Quarterly during
well development
Conducted before
mobilization on
September 2021
Contractor
Ocular inspection of availability of
garbage bins; condition of location
of temporary collection area;
disposal method, MSDS, etc
Pad #7, Pad #9,
Pad#10, Pad #30,
Pad #31, Loc I
Once a month
Conducted on 6
December 2021
PMC and PMU
Drilling contractors’ list of chemicals, paints, lubricants, etc.
used
Conducted on 6
December 2021
PMC and PMU
Ocular inspection of working
condition and maintenance of
sump/pond
Pad #7, Pad #9, Pad#10,
Pad #30, Pad #31, Loc I
Twice a month Conducted on 6
December 2021
PMC and PMU
Record of workers that attended
orientation on environmental
requirements of GOI and ADB;
workers attended HSE orientation
and training (if any)
Pad #7, Pad #9, Pad#10,
Pad #30, Pad #31, Loc I
Start of drilling
Conducted on
December 2021
PMC and PMU
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
145
Subproject Environmental Issue Monitored Location Monitoring
Period
Monitoring
Status/Progress
Responsible
Organisation
Availability of emergency power
and safety kit.
Conducted before
mobilization
PMC and PMU
Ocular inspection of workers wearing
PPE; Availability of PPE and first aid
kits (hard hats, safety shoes, masks,
H2S detectors and alarms, etc.);
Presence and condition of sanitary
facilities; Clear signs and safety
warnings; Housekeeping at base
camp
Weekly Conducted weekly
by Drilling
Contractor
Contractor
Record of water quantity used for
drilling
Tulis River, Sidolok River,
Urang River (as relevant)
Daily Conducted daily by
Drilling Contractor
(Note: Currently only
water from Sidolok
River used for
drilling
Contractor
Ocular inspection of river condition
(e.g., muddy)
Upstream and
downstream of water
extraction point at Tulis
River, Cidolog River,
Urang River (as relevant)
Weekly Conducted weekly
by Drilling
Contractor
Contractor
Surface water quality (pH, H2S,
BOD, COD)
Upstream and
downstream of water
extraction point at Tulis
River, Cidolog River,
Urang River (as relevant)
Quarterly Completed
Conducted on July
and October 2021
PMU and
Sucofindo
Ambient H2S monitoring Pad #7, Pad #9, Pad#10,
Pad #30, Pad #31, Loc I
Quarterly Completed
Conducted on July
and October 2021
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
146
Subproject Environmental Issue Monitored Location Monitoring
Period
Monitoring
Status/Progress
Responsible
Organisation
Patuha-2
Sub-Project
Record on community
counseling/simulation to handling
H2S (measure A.1)
GDE Patuha Conducted before
drilling activity
Socialization and
simulation of H2S
gas handling were
held on October 8,
2021, and
participated by 26
females and 26
male community
members.
PMC and PMU
DED includes measures B.1. – B.6 PP Unit 2 After EPC
Contract awarded
To be conducted EPC Contractor
Working GRM, information centre
set up, updated GDE website,
availability of project-related flyers
and other social media (measures
B.10. – B.13.)
PP Unit 2 Before drilling
activity
B.10 – B.13
measures has been
established
PMC and PMU
Site-specific EMP prepared by
contractors, reflecting requirements
as defined in measure B.15.
N/A Before field
activity
Site-specific EMP
(CEMP) has been
approved (12 out of
14 CEMP, 2 are still
under review)
Contractor
Ocular inspection of road condition,
temporary enclosures along the
affected road
Road intersection at
Panundaan, Sugihmukti,
and Alamendah to the
the project site, and with
the main Ciwidey-
Rancabali
(provincial road).
Quarterly during
well development
Conducted on July
and October 2021
Contractor
Certificate of service vehicles on
emissions testing
N/A NA Certificates of
emission testing
Contractor
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
147
Subproject Environmental Issue Monitored Location Monitoring
Period
Monitoring
Status/Progress
Responsible
Organisation
have been recorded
and archived
Conduct regular ambient air quality
monitoring: NO2, PM10, PM2.5 Monitoring points defined
in the EMP report’s Figure 4.4 and Table 4.5 (AQ) (or
Appendix B - Figure 5 in
Appendix B)
Quarterly during
well development
Conducted on July
27-30th (TW III) and
October 2021 (TW
IV)
PMU and
Sucofindo
Conduct ambient noise monitoring
in settlements along the affected
roads
Quarterly during
well development
Conducted on July
and October 2021
PMU and
Sucofindo
Record of a road accident, number
and type of vehicles, and damages
to the road and associated
infrastructure Road intersection at
Panundaan, Sugihmukti,
and Alamendah to the
the project site, and with
the main Ciwidey-
Rancabali
(provincial road).
• Once before
the start of
mobilization
• Quarterly
during well
development
Conducted before
mobilization of
material and
equipment for
drilling
Contractor
Ocular inspection of transportation
routes to confirm the adequacy of
temporary road crossings, traffic
warning signs, Presence of
designated staff to manage traffic
Conducted before
mobilization of
material and
equipment for
drilling
Contractor
Contractor’s documents on payment for damages to affected people (if
any).
NA Contractor
Ocular inspection of availability of
garbage bins; condition of location of
the temporary collection area;
disposal method, MSDS, etc.
PTH-1C, PTH-4B, PTH-
4C, PTH-4D, PTH-5A,
PTH-6A, PTH-6B, PTH-
7A, PTH-7B, PTH-9, PTH-
9B, PTH-9A
Once a month Conducted in PTH
7A on 1 December
2021
PMC and PMU
Drilling contractors’ list of chemicals, paints, lubricants, etc. used
Conducted in PTH
7A on 1 December
2021
PMC and PMU
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
148
Subproject Environmental Issue Monitored Location Monitoring
Period
Monitoring
Status/Progress
Responsible
Organisation
Ocular inspection of working
condition and maintenance of sump
(pond) for drilling
PTH-1C, PTH-4B, PTH-
4C, PTH-4D, PTH-5A,
PTH-6A, PTH-6B, PTH-
7A, PTH-7B, PTH-9, PTH-
9B, PTH-9A
Twice a month Conducted in PTH
7A on 1 December
2021
PMC and PMU
Record of workers that attended
orientation on environmental
requirements of GOI and ADB;
workers attended HSE orientation
and training (if any)
PTH-1C, PTH-4B, PTH-
4C, PTH-4D, PTH-5A,
PTH-6A, PTH-6B, PTH-
7A, PTH-7B, PTH-9, PTH-
9B, PTH-9A
Once at the start
of construction,
then quarterly
Conducted on 11
and 12 November
2021 attended by all
workers
Contractor
Availability of emergency power and
safety kit
N/A Before field
activity
Has been provided
Ocular inspection of workers wearing
PPE; Availability of PPE and first aid
kits (hard hats, safety shoes, masks,
H2S detectors and alarms, etc.);
Presence and condition of sanitary
facilities; Clear signs and safety
warnings; Housekeeping at base
camp
PTH-1C, PTH-4B, PTH-
4C, PTH-4D, PTH-5A,
PTH-6A, PTH-6B, PTH-
7A, PTH-7B, PTH-9, PTH-
9B, PTH-9A
Weekly Conducted every
week by Contractor
Record of water quantity used for
drilling
Rivers: Cipaku,
Citiis, Cipadarum,
Ciputri (as relevant)
Daily Water usage is
recorded daily by
the drilling
contractor
Drilling
Contractor
Ocular inspection of river condition
(e.g., muddy)
Upstream and
downstream of water
extraction point at Cipaku,
Citiis, Cipadarum, Ciputri
river (as relevant)
Weekly To be conducted in
early February 2022
PMU
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
149
Subproject Environmental Issue Monitored Location Monitoring
Period
Monitoring
Status/Progress
Responsible
Organisation
Surface water quality (pH, H2S,
BOD, COD)
Upstream and
downstream of water
extraction point at Cipaku,
Citiis, Cipadarum, Ciputri
river (as relevant)
Quarterly To be conducted in
early February 2022
PMU and
Sucofindo
Ambient H2S monitoring PTH-1C, PTH-4B, PTH-
4C, PTH-4D, PTH-5A,
PTH-6A, PTH-6B, PTH-
7A, PTH-7B, PTH-9, PTH-
9B, PTH-9A
Quarterly To be conducted in
early February 2022
PMU and
Sucofindo
Besides environmental, health and safety aspects, this report also includes Biodiversity Action Plan Monitoring requirements related to civil work activities. The
following table summarizes the Monitoring of Biodiversity Action Plan Requirement.
Table 23 Monitoring Biodiversity Action Plan Requirement
Impact Mitigation action Parameter to be
monitored
Location Monitoring
Procedure
Frequency Monitoring
Status/Progress
Responsible
Organisation
Loss of
vegetation
cover in
specific areas
of the project
Minimise forest
clearance alongside
rights of way and
around well pads.
Vegetation
clearance by
Project staff and
contractors is as
minimal as legally
and technically
necessary
Project
Area of
Influence
Review of
Project incident
logbook; visual
inspection
Unannounced
inspections at
least quarterly,
during
preparation and
construction
phases
To be conducted
in early February
2022
PMC and PMU
Source construction
materials from
outside of forested
areas.
Sourcing of
materials
Project
Area of
Influence
Review of
records for
sourcing of
Unannounced
inspections at
least quarterly,
during
To be conducted
in early February
2022
PMC and PMU
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
150
Impact Mitigation action Parameter to be
monitored
Location Monitoring
Procedure
Frequency Monitoring
Status/Progress
Responsible
Organisation
materials;
inspections
preparation and
construction
phases
Introduction of
invasive alien
species
Take care to avoid
the introduction of
new invasive species
to, and spread of
existing invasive
species within the
Project area through:
- washing of vehicles,
equipment and
supplies before entry
to the Project area;
- monitoring for
invasive species; and
- control/eradication
of invasive species
where found.
Washing of
vehicles,
equipment and
supplies before
entry to Project
area
Transit site
outside
Project
Area of
Influence
Inspections Unannounced
inspections at
least quarterly
during
preparation and
construction
phases
To be conducted
in early February
2022
PMC and PMU
Abundance/spread
of invasive alien
species in Project
area
Project
Area of
Influence
Surveys by
specialist sub-
contractor
Annually, in
summer, during
preparation and
construction
phases
To be conducted
in early February
2022
PMC and PMU
Control of
new/spreading
areas of invasive
alien species in
Project area
Project
Area of
Influence
Records of
invasive species
control;
inspections
Quarterly, during
preparation and
construction
phases
To be conducted
in early February
2022
PMC and PMU
Modification
and
fragmentation
of habitat due
to loss of
vegetation
cover.
Retain tree canopy
connectivity over the
new road wherever
possible.
Canopy
connectivity along
the proposed RoW
is identified, options
for preservation
identified, and
connectivity
preserved
wherever possible
Project
area
Review of
Project incident
logbook; visual
inspection
Unannounced
inspections at
least quarterly,
during
preparation and
construction
phases
To be conducted
in early February
2022
PMC and PMU
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
151
Impact Mitigation action Parameter to be
monitored
Location Monitoring
Procedure
Frequency Monitoring
Status/Progress
Responsible
Organisation
Install appropriate
canopy bridges to
increase connectivity
over the road for
primates.
Appropriate canopy
bridges installed
over the new road
within one month of
clearance of RoW
Project
area
Inspections Unannounced
inspections at
least quarterly
during
preparation and
construction
phases, until
complete
To be conducted
in early February
2022
PMC and PMU
Displacement
of species due
to noise,
machinery and
equipment and
presence of
staff.
Regularly maintain
and inspect/certificate
all vehicles,
equipment and
machinery to ensure
that noise levels
conform to prescribed
standards
Noise levels of
Project vehicles,
equipment and
machinery against
prescribed
standards
Project
area
Review of
certificates;
inspections
Unannounced
inspections
quarterly during
preparation and
construction
phases
To be conducted
in early February
2022
PMC and PMU
Mortality of
individuals
from poaching
by construction
workers.
Implement a strict
code of conduct
forbidding
hunting/trapping and
purchasing wildlife,
with heavy penalties.
Train all personnel on
this code of conduct,
and its justification
Staff adherence to
best practice
Project
area
Review of
training records;
review of Project
incident
logbook;
inspections
Unannounced
inspections
quarterly during
preparation and
construction
phases
To be conducted
in early February
2022
PMC and PMU
Summary of Results - Noise
4.1.1.1 Dieng Unit 2
For sub-project Dieng Unit 2, according to the monitoring activity conducted by PT Sucofindo Semarang, 4th quarters (Q4), measurement results of noise levels
were found that exceeded the noise threshold in several sampling locations: 1, Simpang Pawuhan (Intersection Pawuhan Village), 2. Simpang Terminal Dieng
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
152
(Intersection Dieng Terminal), 3. Simpang Dieng (Dieng Intersection). Considering those locations are close to heavy traffic, the source of high-level noise could
be from transportation in the locations.
4.1.1.2 Patuha Unit 2
For sub-project Patuha Unit 2, based on the noise level measurements at 10 sampling points in October - December 2021, some areas exceeded the
environmental noise level standards required during 24-hour activity (LSM) at the sampling points K- 6 (settlement area Cibodas Village), K-8 (resettlement
Area Citiwu Village), K-9 (Ciwidey - Rancabali Road), and K-10 (connecting road from the project area to Ciwidey – Rancabali road). All locations that exceed
the limit are residential areas far from the project location. It can be concluded that noise intensity exceeded the threshold caused by anthropometric activities
such as resident vehicles passing around the monitoring locations, weather conditions (wind blowing), or other community activity that can cause high noise
intensity. Overall, the noise quality around the Patuha Unit 2 project area is of good quality, except for the areas around the sampling points mentioned. The
result of noise monitoring is presented in Appendix B.
Summary of Results – Surface Water Quality.
4.1.2.1 Dieng Unit 2
For sub-project Dieng Unit 2, the water quality of the Sidandang River and Situlu River were monitored regarding Government Regulation no. 22 of 2021
concerning Water Quality Management and Water Pollution Control Class II - Water Quality Standards for Recreation, Freshwater Fish Cultivation, Cultivation,
Vegetation Irrigation, and Other Needs Requiring the Same Standard. According to laboratory analysis results for Situlu River and Sidandang River water quality
conducted by PT Sucofindo Semarang, the surface water quality is poor of quality. Parameter that exceeded the limit are nitrate and nitrite. It is estimated that
due to agricultural activity that use exceesive fertilizer, resulting in pollution to the surface water. Comparing to the previous monitoring result, surface water
quality is still in the same condition, several parameter are fluctuation such as TSS, pH and BOD. Complete results are in Appendix B.
4.1.2.2 Patuha Unit 2
For sub-project Patuha Unit 2, surface water quality monitoring was conducted in 3 rivers, Citiis River (S-1), Cipadaruum River (S-2), dan Ciputri River (S-3).
The monitoring results for the fourth quarter of 2021 show that all parameters meet the quality standards of Government Regulation No. 22 of 2021 concerning
the Implementation of Environmental Protection and Management, Appendix VI concerning National Water Quality Standards.
The result of surface quality monitoring is presented in Appendix B.
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
153
Summary of Results – Groundwater Quality.
4.1.3.1 Dieng Unit 2
During this period, there is no measurement of groundwater quality for Dieng Unit 2
4.1.3.2 Patuha Unit 2
Groundwater quality monitoring is carried out on Cidamar (S-4) and Cihaliwung (S-5) springs. The monitoring results for the fourth quarter of 2021 show that
all groundwater parameters still meet the quality standards required by the Minister of Health Regulation No. 32 of 2017 concerning Environmental Health
Quality Standards and Water Health Requirements for Sanitary Hygiene Needs. In general groundwater quality in Patuha 2 are in good and steady condition
comparing to the previous monitoring result. The result of groundwater quality monitoring is presented in Appendix B.
Summary of Results – Air Quality.
4.1.4.1 Dieng Unit 2
For sub-project Dieng Unit 2, air quality monitoring conducted in 9 location (Q3) and 3 location (Q4). Following is monitoring location of air quality:
Q3 Monitoring: 1. Sikunang, 2. Ngandam, 3. Power Plant, 4. Geodipa Office, 5. Simpangan Village, 6. Kepakisan Village, 7.Karangsari Village, 8. Pawuhan
Village, 9. Karang Tengah Village
Q4 Monitoring: 1. Pad 31, 2. Pad 31, Ex Mess PLN (Pad 38)
Based on monitoring results conducted by a 3rd party accredited laboratory (Sucofindo), all ambient air quality parameters meet the standard limit, according to
Government Regulation No 22 the year 2021 concerning Environmental Protection and Management Implementation, Appendix VII Ambient Air Quality
Standards. In comparison, odour measurement was conducted in 6 locations (Q3 and Q4). Based on the monitoring, odour results in all locations are meet the
standard limit set by Ministry of Environment Decree No 50/1996 regarding Odor Standard. Based on the result of quarterly monitoring, air quality condition
relatively stable/steady
4.1.4.2 Patuha Unit 2
For sub-project Patuha Unit 2, ambient air quality quarterly monitoring was conducted by PT Sucofindo Bandung during the second semester of 2021 at 10
sampling locations around the project area. Results for all parameters in all sampling stations still meet the required environmental quality standards based on
Government Regulation Number 22 of 2021, concerning Implementation of Environmental Protection and Management, Appendix VII concerning Ambient Air
Quality Standards, while odour level referring to Ministry of Environment Decree No. 50 of 1996 concerning Odor Level Standards. Overall, the air quality around
the Patuha project area is of good quality and relatively stable compare to the previous monitoring result.
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
154
Environmental Quality Monitoring Requirements of Patuha-2
Table 24 EMP Environmental Quality Monitoring Implementation (Civil Work)
Environmental Issue Monitoring Plan
Location Parameter Responsible Organization
Frequency Monitoring Date
Regular maintenance and inspection of equipment/vehicle
Vehicle parking area and equipment storage area
The machinery works properly, and no damage was identified
Supraco Weekly for routine operational equipment/vehicle and monthly for idle equipment/vehicle
2021:
July: 23 July 2021
August: 13 August 2021
September: 14 September 2021
October: No heavy vehicle and HDE
mobilized to the site
November: No heavy vehicle and HDE
mobilized to the site
December: 27 December 2021
2022:
January: 08 January 2022
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
155
Environmental Issue Monitoring Plan
Location Parameter Responsible Organization
Frequency Monitoring Date
Inspection of
availability of
garbage bins;
condition of location
of the
temporary collection area; disposal method, MSDS, etc
Basecamp and construction site
Visual inspection of waste management at the construction site and basecamp
Supraco Monthly 2021:
August: 31 August 2021
September: 30 September 2021
October: 31 October 2021
November: 30 November 2021
December: 23 December 2021
Premobilization
inspection of
equipment/vehicle by Client
Vehicle parking area and equipment storage area
The machinery works properly, and no damage was identified
Supraco Initial prior mobilization
The inspection was conducted two days prior to equipment/vehicle mobilization to the site. The joint inspection was conducted by PMU and SPC
Mapping area for
land clearing plan,
socialization to
personnel involved,
and monitoring
Site office Approved of land clearing map is available (by PMU) and has been communicated to personnel conducting the works
Supraco Initial prior land clearing
The land clearing area is communicated at daily toolbox meetings.
Ocular inspection of river condition
1. Upstream
boundary
(adjacent to GOA)
2. Within the
boundary
(Adjacent to the
bridge)
3. Downstream the
boundary
(Approximately 5
meters
Ocular inspection of turbidity
Supraco Weekly 2021:
August to November 2021: no sampling
was conducted since these months had
commenced no works.
The inspection was commenced in
December 2021. Sampling is conducted
weekly on Thursday.
Inspection schedule:
09 December 2021
16 December 2021
23 December 2021
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
156
Environmental Issue Monitoring Plan
Location Parameter Responsible Organization
Frequency Monitoring Date
downstream of
the boundary
Biodiversity loss Construction site Loss of vegetation,
Invasive alien,
Displacement of species due to noise, presence of machinery and equipment, and a company of the staff
Supraco Weekly (if applicable) A biodiversity-related report is conducted if
applicable. Previous wildlife encounters
included:
- Identification of cave (upstream
Cipadaruum River)
- The footprint of the leopard was
identified at PPL04
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
157
4.2 Construction Phase Affected People Consultation
During the construction phase, the following table gives information on the consultations undertaken to understand the impact of the project on Affected People
and how effective the EMP Mitigation measures are for residents, businesses, and other affected people around the construction sites.
PMU Social Safeguard team has conducted numerous consultations by socialization, and direct approaches regarding Land Acquisition, RP Implementation,
Grievance Redress Mechanism, Project Updates, Local Worker, Occupational Discussion, Occupational Community Development, etc. The following table
summarized the consultation conducted during the July to December 2021 period.
Table 25 Construction Phase Affected People Consultation Dieng-2 Sub Project
No Date Topic Key Issues Meeting Type /
Method Venue
Participants Key Person Present
(PMU/PMC/Stakeholders) M F
1 09/07/21 Recruitment
Consolidation
Workforce recruitment
mechanism Consultation
Dieng Temporary
Office 6
GDE, Paguyuban
Koordinator Pelayanan
Barang dan Jasa (PKPBJ)
2 15/07/21 Drilling Socialization
Socialization the drilling
activities plan and local
workforce
Socialization GDE, The affected villages
representatives
3 24-
25/08/2021
Test Results
Announcement
Local Workforce
Recruitment Socialization
PMU, Forkompinca,
Disnaker
4 26/08/21
Local Workforce
Recruitment
Committee
coordination
Consultation Ballroom Dafam
Hotel Wonosobo 16 5
GDE, Forkompinca,
Disnaker, Contractors
5 01/09/21
Local Workforce
Recruitment
Committee
coordination
Submission of
administrative selection
results to the local labor
committee
Consultation 17 5 GDE, Forkompinca,
Disnaker, Contractors
6 06/09/21 Recruitment Data
Finalization
Coordination related to
the Local Workforce Consultation
GDE Soreang
Office 6 1 GDE, Contractors
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
158
No Date Topic Key Issues Meeting Type /
Method Venue
Participants Key Person Present
(PMU/PMC/Stakeholders) M F
7 12/10/21
Coordination and
Presentation MCU
result
Presentation Medical
Check-up Results Consultation
Dieng Temporary
Office 16 3
8 14/10/21
Service Company
Mobilization
Socialization
Coordination related to
Local Workforce,
discussion of
administrative selection
results in Socialization of
Service Company Rig to
Forkompinca
Socialization Dieng Temporary
Office 24 1
GDE, Contractors,
Forkompinca
9 05/11/21
Batch 2 Local
workforce
recruitment
socialization
H2S Drilling for
Karangengah community Socialization
Dieng Temporary
Office
PMU, PMC Drilling,
Karangtengah community
10 16/11/21
Project
Socialization and
Consultation with
Dieng Wetan
Community
Socialization about a
geothermal project for the
community and the
assessment for affected
village status
Socialization and
Consultation
Dieng Wetan
Village Hall 22 11
PMU, PMC, Stakeholders
(Dieng Community and
village officers)
11 29/11/21
Drill H2S
Evacuation Area
Project Dieng Unit 2
Socialization about H2S
Hazards and drilling H2S
Evacuation
Socialization
Karangtengah
Village Office Hall
and Karang
Tengah Field
27 2 GDE, Karangtengah
community
12 06/12/21
Project
Coordination (Batur
Area)
Coordination related to
the Project and Local
Workforce
Consultation Dieng Temporary
Office 43 4
GDE, Contractors,
Forkompinca Batur
13 06/12/21 Dieng-2 Project
Socialization
Socialization about the
geothermal project for the
community
Socialization Pawuhan
Madrasah Hall
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
159
No Date Topic Key Issues Meeting Type /
Method Venue
Participants Key Person Present
(PMU/PMC/Stakeholders) M F
14 14/12/21
Socialization of
Sendang Water
source Lab Results
Socialization about the
laboratory result on
Sendang water source
Socialization Simpangan
Madrasah Hall 7 1
Table 26 Construction Phase Affected People Consultation Patuha-2 Sub Project
No Date Topic Key Issues Venue Meeting Type /
Method
Participants Key Person Present
(PMU/PMC/Stakeholders) F M
1 8 October
2021
Drill H2S
Evacuation Area
Project Patuha
Unit 2
Socialization about
H2S Hazards and
drilling H2S
Evacuation
Patuha site Socialization and
simulation
26 26 Local communities around the
project site
2 21 October
2021
Local Workforce
Recruitment
Committee
coordination
Local Workforce
Recruitment
Soreang Office Consultation 20 5 PMU, Forkompinca, Disnaker
3 28 October
2021
FGD
Environmental
Management
inland clearing
plan, IPPKH Area
Patuha-2
Environmental
Management
On land clearing
plan in IPPKH Area
Patuha-2
Patuha Resort FGD 8 32 PMU, PMC, Vice Perthutani
Jabar, Local NGO.
4 4
November
2021
Public
awareness-
raising activity on
the management
of environmental
impacts in the
IPPKH 2
This is expected to
be a means of
communication and
community control of
the Patuha Unit 2
project, especially
Patuha Resort Public expose 6 79 PMU, PMC, GDE were also
attended by environmental
activists, Deputy Perhutani,
Representatives from
BBKSDA, Camat and
representatives of the police
and TNI.
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
160
No Date Topic Key Issues Venue Meeting Type /
Method
Participants Key Person Present
(PMU/PMC/Stakeholders) F M
environmental
aspects.
5 15
November
2021
Coordinate with
the Sugihmukti
Village
Government to
acquire
compensation
land for IPPKH
2.
Part of the
preparation to
provide
replacement land in
accordance with the
recommendations of
the Forest Service
in the Sugihmukti
Village area
Head office
Sugihmukti
village.
Discussion 2 4 PMU, PMC and Head Village
6 17
December
2021
Mapping the most
common natural
activities that
could be changed
as disasters in
the area, and the
activity
Identify the potential
disasters around
Kampung Kendeng,
both natural, non-
natural and human-
caused disasters.
Kampung
Kendeng
FGD 7 15 PMU, PMC and local
community.
7 22
December
2021
The induction on
gender
perspectives in
the project.
the definition and
gender concept in
general
Laydown Area,
Patuha site
Socialization 0 15 Workers (supraco), PMC,
PMU.
8 23
December
2021
Socialization of
Gender
Guidelines
This activity also
aims to socialize
corporate gender
mainstreaming in
the project.
Patuha site
(powerplan
area)
Socialization 75 0 PMU, GDE Staff and the local
community.
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
161
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
162
5 COMPLAINTS, ISSUES, CORRECTIVE ACTION
5.1 Information Disclosure
From July to December 2021, some meetings with the local community and leader have been conducted. The meeting was aimed to disclose project information
to the stakeholders. The meeting topics were various, including project updates, recruitment, land acquisition, community development programs, safety drilling,
and grievances. The socialization regarding Dieng-2 Land Expansion Planning was conducted on 16 November 2021. GDE explained and discussed land
expansion plans with the Karangtengah community on this occasion.
Table 27 gives information on disclosure activities on environmental aspects that have been conducted:
Table 27 Information Disclosure
Topic / Reason
for Information
Disclosure
Date
Method of
Disclosure Outcome / Results
Participants Key Person Present
(PMU/PMC/Stakeholders) M F
Dieng-2
Drilling
Socialization 15 July 2021 Socialization
Affected people are
aware of the plan of
drilling activity
NA NA GDE, The affected villages
representatives
Socialization
about H2S
Hazards and
drilling H2S
Evacuation
29
November
2021
Socialization
Affected people are
aware of H2S
hazards and how to
handle and manage
the situation if it
occurs
27 2 GDE, Karangtengah community
Socialization
about the
geothermal
project for the
community
6 December
2021 Socialization
Affected people are
aware of the
geothermal project
NA NA GDE, PMC, Karangtengah community,
village government
Patuha-2
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
163
Topic / Reason
for Information
Disclosure
Date
Method of
Disclosure Outcome / Results
Participants Key Person Present
(PMU/PMC/Stakeholders) M F
Socialization
about H2S
Hazards and
drilling H2S
Evacuation
8 October
2021 Socialization
Affected people are
aware of H2S
hazards and how to
handle and manage
the situation if it
occurs
26 26 PMC, GDE and Kendeng Village
community
FGD
Environmental
Management
inland clearing
plan, IPPKH Area
Patuha-2
28 October
2021 FGD
Stakeholders are
aware of
environmental
management on land
clearing activity
32 8 PMU, PMC, Vice Perthutani Jabar, Local
NGO.
Public awareness-
raising activity on
the management
of environmental
impacts in the
IPPKH 2
4 November
2021
Public expose
79 6 PMU, PMC, GDE were also attended by
environmental activists, Deputy
Perhutani, Representatives from
BBKSDA, Camat and representatives of
the police and TNI.
5.2 Grievance Redress Mechanism
GDE has established a Standard Operation Procedure for its Grievance Redress Mechanism since 10 September 2020 with GDE’s Decree No. 034.SK/PST.00-
GDE/IX/2020. This SOP includes step-by-step instructions and specific time and workflows to handle stakeholder complaints effectively. The scope is divided
into (i) Information, (ii) Consultation, and (iii) Mediation. A grievance log has been established. When relevant, the receipt and resolution of all grievances are
reported here on a semi-annual basis and in the Semi-Annual Environmental Monitoring Report.
For Dieng-2 Sub-Project (HALO DIENG 2), the communication media being used are:
a. Hotline : +62 812 – 10000 – 630
b. E-mail : [email protected]
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
164
c. Office : PT Geo Dipa Energi (Persero) Unit Dieng, Jl. Raya Dieng-Batur, Banjarnegara
For Patuha-2 Sub-Project (HALO PATUHA 2), the communication media for grievances are as follows:
a. Hotline :+62 812 – 30000 – 630
b. E-mail : [email protected]
c. Office : PT Geo Dipa Energi (Persero) Unit Patuha, Jl. Rancabolang Km. 14, Desa Sugihmukti, Kec. Pasirjambu, Bandung
GDE has also established a Grievance Redress Committee referring to GDE’s Decree No. 015.SK/PST.00-GDE/IV/2021 dated 15 April 2021. GDE conducted
the first initial meeting of the Grievance Redress Committee in July-August 2021. GDE has intensified the Grievance Redress Mechanism
disclosure/dissemination to stakeholders. Each local (village/sub-district) government office has a banner/leaflet/etc. related to GDE Grievance Redress
Mechanism provided.
Table 28 Grievance Redress Committee
No Role/Institution Position within Team
COMMITTEE
PT Geo Dipa Energi (Persero) – Project Head Office
1 Project General Manager Head of Committee
2 HSE and Safeguard Division / Manager Member
Government Relations and Social Safeguard Assistant Manager
Environment Safeguard Assistant Manager
Health and Safety Assistant Manager
Representatives of sub-district level communication forum (Forkompinca)
3 Head of Sub-District (Kecamatan) Member
4 Head of Police Sector (Polsek) Member
5 Head of Military Area Command (Koramil) Member
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
165
No Role/Institution Position within Team
TECHNICAL TEAM
PT Geo Dipa Energi (Persero) – Project Site Office
6 Project Manager (Dieng-2/Patuha-2) Head of Technical Team
7 HSE and Safeguard Superintendent (Dieng-2/Patuha-2) Member
8 Social Safeguard and Public Relation Supervisor (Dieng-2/Patuha-2) Member
9 Social Safeguard and Public Relation Staff (Dieng-2/Patuha-2) Member
Representatives of village government and community
10 Head of Villages Member
11 Community Leaders Member
12 Women Representatives Member
Others
13 Environmental and Social Safeguard Specialist
(Project Management Consultant) Member
14 Contractor Representatives Member
In the June to December 2020 period, in Dieng, complaints were about the inventory of losses in the land clearing process. Eleven AHs (tenant farmers) raised
objections to the head of the village (as a member of the Integrated Team), requesting a correction to the losses data since some of their crops had not been
included/identified as their affected asset. The complaints were formally forwarded/submitted to the Head of Integrated Team through the GDE’s letter No. 421.1/DNG.1.00-GDE/VII/2020 (dated 10 August 2021). Verification of data was held on 11-12 August 2020. As a result, the objections have been
accommodated and approved. The summary of grievances/complaints about Dieng-2 and Patuha-2 is detailed below.
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
166
Table 29 List of Complaint(s) Received in January to December 2021 periods for Dieng-2 Sub-Project
No Complaint/
Grievance
Category of
Complaint
The date
that
Complaint
was
Received
Location of
Impact
Name of
Aggrieved
Address/
Affiliation
Status of
Complaint
Follow up Action
01 Some of the
people that
farming close to
the power plant
site state that
their access has
been limited due
to the
development of
the power plant
area, i.e. due to
the fence
surrounding the
power plant site;
requesting GDE
to give alternative
access road to
the farmers
Traffic
Disruption
10-June-
21
Karangtengah
village (power
plant location)
Slamet
Mardiatmoko
Kalibening RT
01/RW 01,
Kec.
Kalibening,
Banjarnegara
Village
Government
GDE has
responded (sent
letter) stating that
temporary access
road was prepared
for the farmers as
long as pre-
construction
period;
Furthermore, GDE
plans another
alternatives access
road outside the
surrounding fences
and in the progress
of
feasibility/technical
study for some
aspects
On going, once the
design of power plant
ready and pre
construction will be
started GDE shall
conduct
socialization/consultation
to the community
02 Report from the
villagers
concerning GDE's
operational
activities causing
several impacts
Air Pollution,
Vibration,
Water
Pollution,
Labour
Relation,
Labour
10-June-
21
Karangtengah
village
Slamet
Mardiatmoko
Kalibening RT
01/RW 01,
Kec.
Kalibening,
Banjarnegara/
Karangtengah
GDE has received
the complaint and
clarified its follow-
up-plan; GDE also
states its
communication/
socialization
On going, GDE shall
regularly socialize the
project to the community
to give them
understanding about the
project, what are the
positive and negative
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
167
No Complaint/
Grievance
Category of
Complaint
The date
that
Complaint
was
Received
Location of
Impact
Name of
Aggrieved
Address/
Affiliation
Status of
Complaint
Follow up Action
(as stated in
categories)
Standard,
Compensation
Village
Government
activities that have
been conducted
periodically about
its operational
activities
impact and what are the
mitigation measures
prepared
03 Rig mobilization
process caused
dust pollution at
Merah Putih yard
and forced nearby
groceries to
close.
Air Pollution 24-
October-
21
Ngampel,
Wonorejo. Kec.
Selomerto,Kab.
Wonosobo
Retno Ngampel,
Wonorejo. Kec.
Selomerto,Kab.
Wonosobo
GDE has
communicated with
contractor and
complainant; the
contractor
committed to
having regular
road-washing until
the mobilization is
finished
Resolved, the
complainant accepted
the offered solution.
04 Trailer for
mobilization
process causing
damages to the
electricity line,
causing a
blackout.
Blackout
(Broken
Cable)
27-
October-
21
Wadasputih RT
3/RW 3,
Parikesit,
Kec.kejajar,
Kab.
Wonosobo
Yusup Wadasputih RT
3/RW 3,
Parikesit,
Kec.kejajar,
Kab.
Wonosobo
GDE has
communicated with
contractor and
complainant, the
contractor then
asked assistance
from PT PLN UPJ
Wonosobo, the
blackout was fixed
at 16.23 WIB
Resolved
05 The single
accident occured
near Merah Putih
Traffic
Disturbance
30-
October-
21
Ngampel,
Wonorejo. Kec.
Selomerto,
Sartini Desa Singkir,
RT: 5 RW: 9,
Kasiran, Kec.
GDE has
communicated with
contractor and
Resolve, the
complainant agreed with
the solution. Corrective
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
168
No Complaint/
Grievance
Category of
Complaint
The date
that
Complaint
was
Received
Location of
Impact
Name of
Aggrieved
Address/
Affiliation
Status of
Complaint
Follow up Action
yard, caused by
improper
(slippery) road
condition; it was
identified as an
effect of mud on
trailer tire
Kab.
Wonosobo
Selomerto,
Kab.
Wonosobo
complainant; the
contractor then
commited to cover
the loss from the
complainant, such
as motorbike
damage and cost
of injury care
is all the trailer and truck
shall be gather in Merah
Putih yard before travel
to Dieng and all the tires
shall be sprayed with
water to remove the mud
from tire.
06 Clarification of
affected village
status
Clarification 13-
November-
21
Dieng (Wetan) Mardiyuwono Dieng (Wetan) GDE committed to
having an
assessment on
Dieng (Wetan) and
planned to have
socialization on
17/11/2021
07 Exceedance of
ambient noise
standards caused
by drilling
activities
Noise 26-
November-
21
Karangtengah Goris Karangtengah
RT 4 RW 4
Batur,
Banjarnegara
GDE has
communicated with
the complainant
and commited to
having proper
socialization/
discussion in early
December 2021 at
Madrasah
Simpangan
Resolve, after receive
complain GDE stop
drilling operation and
change the program,
then measured noise in
5 location. At the time
noise in 5 location was
measured below the
standard. Corrective
action is GDE measure
noise in surrounding
village location in daily
basis witnessed and
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
169
No Complaint/
Grievance
Category of
Complaint
The date
that
Complaint
was
Received
Location of
Impact
Name of
Aggrieved
Address/
Affiliation
Status of
Complaint
Follow up Action
acknowledge by villager,
to prevent any new
complaint.
08 Suspected water
pollution in
Simpangan
spring,
Karangtengah
caused by drilling
activities
Water
Pollution
28-
November-
21
Karangtengah Mahudi Simpangan,
Karangtengah
Village
GDE asked
assistance from PT
Sucofindo to
conduct water
quality
measurement;
GDE committed to
having intense
coordination
related to the
issue; furthermore,
a water distribution
system was
planned from
Simpangan water
well as additional/
emergency water
source
Resolve, based on
laboratory result,
Sidendang spring water
quality is good, except
for nitrate and nitrite,
exceeded the limit. It is
suspected that farming
activity which use
excessive fertilizer
causing nitrate and
nitrite pollution to the
spring water. Laboratory
analysis of Sidendang
Spring Water is attached
in Appendix F
09 Exceedance of
ambient noise
standards caused
by drilling
activities
Noise 28-
November-
21
Karangtengah Badiono Karangtengah,
Batur,
Banjarnegara
GDE has
communicated with
contractor and
complainant
regarding noise
issue from booster
area
Resolved, GDE have
conducted several
corrective action to
handle noise issue
caused by booster pump
as follows:
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
170
No Complaint/
Grievance
Category of
Complaint
The date
that
Complaint
was
Received
Location of
Impact
Name of
Aggrieved
Address/
Affiliation
Status of
Complaint
Follow up Action
1. Install iron sheet
2. Install acoustic foam
3. Covering pump (noise
source) by metal
sheet
4. Modify muffler to
reduce noise &
vibration
Complainant has
accepted the solution
and there is no more
complaint
Table 30 List of Complaint(s) Received in January to December 2021 periods for Patuha-2 Sub-Project
No Complaint/
Grievance
Category of
Complaint
The date
that
Complaint
was
Received
Location of
Impact
Name of
Aggrieved Address/ Affiliation
Status of
Complaint
Follow up Action
001 A Cement Truck
(Transporter)
night-passing
through
Sugihmukti Village
Traffic
Disruption
22-April-21 Sugihmukti
road
Laju Babinsa Sugihmukti,
Pasirjambu Military
Area of Command
"Koramil"
GDE has committed
to have proper
coordination with
Koramil Pasirjambu
concerning every
Resolved
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
171
No Complaint/
Grievance
Category of
Complaint
The date
that
Complaint
was
Received
Location of
Impact
Name of
Aggrieved Address/ Affiliation
Status of
Complaint
Follow up Action
was considered
not to have proper
coordination with
local communities
and/or authorities
transporting-
activities
002 Compensation of
bus-rent that being
restrained by
activity in
Alamendah road
Km-5
Traffic
Disruption
24-April-21 Alamendah
road Km-5
Ir. Iwan
Hartadi
Wibawa
PTPN VIII
Rancabolang
GDE has
communicated with
the transporter
concerning the bus-
rent compensation;
The transporter has
also paid it
Resolved
003 Clarification
concerning
activities in Pad
BB location
Others 23-April-21 Location of
Pad BB
H. Arif
Widodo, S.
Hut
PT Perhutani GDE has clarified
about Pad BB
status (if there was
no activity
conducted yet); and,
as requested,
committed to
formally inform
Perhutani
concerning activity
in Pad BB and also
about casing
delivery
Resolved
004 Disinformation
about the
recruitment
Others 2-June-21 Sugihmukti
and
H.
Ruswan,
H. Awan
Village Government GDE has clarified
the misleading
information that
Resolve,
disinformation has
been fixed
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
172
No Complaint/
Grievance
Category of
Complaint
The date
that
Complaint
was
Received
Location of
Impact
Name of
Aggrieved Address/ Affiliation
Status of
Complaint
Follow up Action
process in GDE
Patuha
Alamendah
Village
circulates in
communities
005 Disappointment
from NGO about
cooperation
proposal,
specifically about
local hire
recruitment
Others 27-July-21 Sugihmukti Soni F-MANDAPA GDE has clarified
the mechanism of (i)
GDE procurement,
(ii) community
development
program
arrangement, and
(iii) local hire
recruitment
committee
006 Trailers
demobilization
process causing
damage to water
distribution pipe in
2 (two) locations:
Kampung Cibodas
and Kampung
Pasir Cupu
Traffic
Disruption
19-August-
21
Alamendah Ade
Suprianto
RW07 Langkob,
Desa Alamendah /
Ketua Kelompok
Kerja Alur Lintas
(Pokja)
GDE has
communicated with
the contractor and
complainant
concerning the
solution; Damaged
pipes were
rehabilitated on 21
and 22-August-21
for Kampung
Cibodas and
Kampung Pasir
Cupu, respectively.
Resolved, water
pipe has been
repaired
007 Trailer for rig
mobilization
process causing
Compensation 28-
September-
21
Alamendah Hj. Kokom
Komala
RW08 Kp. Sindur,
Desa Alamendah
GDE has
communicated with
the contractor and
Resolved, On 20th
October 2021, the
contractor
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
173
No Complaint/
Grievance
Category of
Complaint
The date
that
Complaint
was
Received
Location of
Impact
Name of
Aggrieved Address/ Affiliation
Status of
Complaint
Follow up Action
damages to roof
and wall from a
house
complainant
concerning the
solution; Damaged
roof and wall are
commited to being
rebuilt after the
mobilization process
has finished
completed repairing
the damages. PMC
has verified that this
action has been
completed.
008 Trailer for rig
mobilization
process causing
damages to the
water distribution
pipe
Compensation 28-
September-
21
Alamendah Asep
Wahyu
Kp. Cibodas RT04
RW05, Alamendah
GDE has
communicated with
contractor and
complainant; the
damaged pipe has
been replaced;
safety line barricade
then prepared as
mitigation action
Resolved
009 Trailer for rig
mobilization
process causing
damages to store
terrace and
graveyard wall
Compensation 28-
September-
21
Panundaan Ika Suryati Kp. Simpang RT03
RW16, Panundaan
GDE has
communicated with
the contractor and
complainant
damaged terrace
and wall were
committed to be
rebuilt maximal in 2
days after the
mobilization process
has finished
Resolved, On 20th
October 2021, the
contractor
completed repairing
the damages. PMC
has verified that this
action has been
completed.
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
174
No Complaint/
Grievance
Category of
Complaint
The date
that
Complaint
was
Received
Location of
Impact
Name of
Aggrieved Address/ Affiliation
Status of
Complaint
Follow up Action
010 Trailer for rig
mobilization
process breaking
the private internet
line
Compensation 4-October-
21
Alamendah Yadi
Mulyadi
Kp. Cipanawa RW
06, Alamendah
GDE has
communicated with
contractor and
complainant, the
contractor then
asked assistant
from Telkom; the
internet line has
been replaced
Resolved
011 Trailer for rig
mobilization
process causing
damages to the
electricity line,
driving a blackout
of 9 (nine) houses
Compensation 4-October-
21
Alamendah Asep
Wahyu
Kp. Cibodas RT04
RW05, Alamendah
GDE has
communicated with
contractor and
complainant, the
contractor then
asked to assist from
PLN; the damaged
electricity line and
the blackout have
been solved
Resolved
012 Trailer for rig
mobilization
process breaking
the private internet
line
Compensation 7-October-
21
Alamendah Samsul
Marif
Kp. Cibodas RT03
RW 05, Alamendah
GDE has
communicated with
contractor and
complainant, the
contractor then
asked assistant
from Telkom; the
internet line has
been replaced
Resolved
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
175
No Complaint/
Grievance
Category of
Complaint
The date
that
Complaint
was
Received
Location of
Impact
Name of
Aggrieved Address/ Affiliation
Status of
Complaint
Follow up Action
013 Access road
blockage caused
by base coarse
material delivery
from BUMDes to
PT Supraco
Indonesia
Traffic
Disruption
16-
October-21
Sugihmukti Nikhi Heru Jl. Pintasari,
Pekanbaru, Riau
GDE has
communicated with
the contractor and
complainant; the
blockage has been
removed
Resolved
014 Disturbance in tea
production caused
by trailer
mobilization
Traffic
Disruption
29-
October-21
Cipaku,
Sugihmukti
Iwan
Hartadi
Rancabolang Tea
Plantation
GDE has clarified
and stated
commitment toward
the complainant (tea
plantation), such as
more intense
coordination and
supervision about
the activities
Resolved, GDE has
sent formal letter to
Tea Plantation
Company, no need
compensation
015 Clarification of
broken
telecommunication
cable, presumably
to be caused by
trailer mobilization
Compensation 2-
November-
21
Mekar
Rasa,
Pasirjambu
Village
Euis
Rohayati,
Fajar
Rizky
Pasirjambu GDE has
communicated with
contractor and
complainant, broken
cable line was
stated as not
caused by trailer
mobilization
Resolved
016 Trailer for rig
mobilization
process causing
damages to roof
Compensation 5-
November-
21
Ciasin
RT02/RW09
Alamendah
Village
Ajat Ciasin RT02/RW09
Alamendah Village
GDE has
communicated with
the contractor and
complainant broken
Resolved
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
176
No Complaint/
Grievance
Category of
Complaint
The date
that
Complaint
was
Received
Location of
Impact
Name of
Aggrieved Address/ Affiliation
Status of
Complaint
Follow up Action
and wall from a
house
roof, and the wall
has been fixed
017 Trailer for crane
demobilization
process causing
damages to the
water distribution
pipe
Traffic
Disruption
16-
November-
21
Cibodas
and Pasir
Cupu,
Alamendah
Village
Ade
Suprianto
RW07
Langkob,Alamendah
Village / Head of
Kelompok Kerja Alur
Lintas (Pokja)
GDE has
communicated with
the contractor and
complainant.
Broken water pipes
have been fixed
Resolved
018 Trailer for rig
mobilization
process causing
damages to
advertising board
and
telecommunication
cable
Compensation 27-
November-
21
Citiwu RT02
RW014,
Panundaan
Village
Dedi
Mulyadi
Citiwu RT02
RW014, Panundaan
Village
GDE has
communicated with
the contractor and
complainant broken
advertising board,
and cable has been
fixed
Resolved
There were no issues raised in the previous SEMRs which have not yet been resolved.
Table 31 Project Complaints or Issues – Not resolved from previous reports
Details of Complaint Detail of Person (Date,
Name, Contact Details) Action Needed and Date The reason this is still not resolved
N.A. N.A. N.A. N.A.
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
177
5.3 Corrective Actions
The following table gives information on any formal corrective action that has been issued to the contractor to improve environmental performance:
Table 32 Corrective Actions Issued
Reason for Corrective Action Date Issued Outcome Comment / Follow Up
Noise generated from booster pump
complained by Karangtengah
community
Early December 2021
Install noise barrier and noise
absorption. Only 1 (one) pump to
be operated during drilling
activity
Noise can be reduced, and complaints have
been responded. GDE have conducted several
corrective action to handle noise issue caused by
booster pump as follows:
1. Install iron sheet
2. Install acoustic foam
3. Covering pump (noise source) by metal sheet
4. Modify muffler to reduce noise & vibration
5. Conduct regular noise monitoring
Complainant has accepted the solution and there
is no more complaint
Water requirement for drilling activity Early December 2021
Use condensate from Dieng Unit
1 and install pipeline for
condensate transfer from Pad 14,
15 and 17 to the well pad
Water transmission system for drilling activity will
be monitored and modified if necessary during
drilling activity. Water Management & Water
Supply Study has been conducted and strategy
has been formulated (explained in the previous
table)
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
178
6 CONCLUSION and RECOMMENDATION
6.1 Conclusion
EMP of the project (GDE) has been utilized as a reference to develop the Contractor’s specific CEMP.
As a part of their commitment, all contractors shall make a CEMP implementation report to PMU and
PMC every month. PMC and PMU have made a regular schedule to inspect CEMP implementation by
contractors. The first inspection was conducted on 1 December 2021 for Patuha Unit 1 and 6 December
2021 for Dieng Unit 2. The report of the joint inspection is attached in Appendix C.
There were no major non-compliance issues reported during July to December 2021 period. Regular
environmental monitoring programs for ambient noise, air and water quality were carried out and
showed no significant exceedances associated with project activities for the environmental parameters
measured.
Several complaints at both locations were recorded, mainly due to traffic disruptions and other issues
such as noise and water quality, but the GDE has resolved the issue as explained in the previous
chapter
6.2 Recommendations
Currently, the project is in the construction phase with works for a well developed civil position.
Implementation of site-specific construction environmental management plans (CEMPs) must be
monitored and reported regularly every month. Considering the current situation and condition in the
site that dynamically changes, CEMP needs to be refined to accommodate the current state and lessons
learnt from current CEMP implementation.
For Patuha-2, a land clearing management plan is recommended to describe the detailed procedures
(including stage approvals) and sequencing of land clearing activities for the well development at
location BB. This plan shall be well-coordinated with the existing Biodiversity Action Plan (BAP) and
detailed in biodiversity protection procedures by PMU and PMC for the contractor to follow.
It is also important for the contractors to implement combined occupational and community health and
safety plans addressing community health issues during the construction phase. The Grievance
Redress Mechanism (GRM) shall be further operationalized next semester with GRC dissemination,
kick-off meetings, and GRC monitoring.
It is further recommended to assess the potential impacts of drilling and powerplant development on
noise and ambient air quality at nearby environmental sensitive receptors, such as the communities
living close to the proposed plant locations (i.e. for Dieng-2). These predictive assessments provide
more opportunities for impact mitigation success if conducted early in the design process, i.e. during
initial plant layout conceptualization and planning and selection of plant technologies. This is expected
during the Front-End-Engineering-Development (FEED) phase, rather than the Detailed Engineering
Design (DED) only. However, predictive assessment findings from the FEED can be re-evaluated and
refined during the DED by the EPC contractor.
GDE Semi-Annual Environmental Monitoring Report of Second Semester of 2021
INO: Geothermal Power Generation Project
179
APPENDICES
Appendix A Introductory Training on ADB’s Environmental and Social Saeguard
Appendix B Environmental Quality Monitoring Result
Appendix C HSE Join Inspection Report
Appendix D ACM Demolishing Report
Appendix E Revegetation in Patuha
Appendix F Sidendang Spring Water Analysis Result
Appendix G Socialization to the Workers prior to Drilling Activity