t SREEVALSAM - Environmental Clearance
-
Upload
khangminh22 -
Category
Documents
-
view
1 -
download
0
Transcript of t SREEVALSAM - Environmental Clearance
Reg No 53/2010, Kololambu.P.O, Naduvattom, Edappal - Malapuram - 679576, Kerala
Ph:0494 2661144,2661000 E-mail: [email protected] www.sreevalsam.inEDUCATIONAL TRUST
The Member Secretary, Dt. 06-09-2019State Environment lmpact Assessment Authority (SEIAA),Thiruvananthapuram, Ke ra la.
Ref.:-1. Proposal no. lA/KL/NCPl70246l20'1'7 dt. 11-10'2017 & F.No.23-89/2018-lA-lll2.ToR Approval letter dt. 22-06-20183. Notification dt. 14-03-2017
Sub.:- Environment Clearance - Expansion of Hospital cum Medical CollegeCampus Project at Edappal Village, Ponnani Taluk, Malappuram District,Kerala - Submission of EIA/EMP Report - Reg.
Respected Sir,
For the purposes of obtaining Environmental Clearance for the above mentionedproject, we submitted application along with draft Terms of Reference (ToR) atMoEF&CC on 11-10-2017 under the provisions of Notification dl. 14-03-2017. The draftToR was considered and approved by EAC in its 6th meeting held on 19/20 April, 2018and the approved ToR letter was communicated to us by MoEF&CC vide letterdt. 22-06-2018.
The EIA study was conducted as per the approved Terms of Reference. Now, wehereby submit the EIA/EMP report in compliance to the ToR letter dt.22-06-2018 forobtaining Environmental Clearance for our project.
It may be kindly noted that the project has applied under the provisions of Notificationdated 14-03-2017 (a Notif ication providing a one time opportunity to the projectproponent who have not taken prior Environment Clearance before the commencementof construction / activity). An amount equivalent to Rs. 57.44 Lakhs is set apart basedon the damage assessment and its remediation plan, natural and community resourcesaugmentation plan. This amount is over and above the CER component and the EMPcomponent.
Please note that the processing fees of Rs. 2 Lakhs was submitted at SEIAA, Keralaon 16-03-2017 vide D.D. no. 525773 dt. 08-03-2017, lndian Overseas Bank. The copyof the said acknowledgment received from SEIAA, Kerala vide letter dated 12-O1-2017is attached at Annexure No. 1.
ln view of the above submissions, we humbly request you to consider our applicationand accord Environmental Clearance to our project at the earliest.
Thanking yo u,Yours res pectfu lly,For Sreevalsam E
Raja n Ac h uthan(Secretary & Au
E ncl. :- As abov
duca
Natho
ional Irt
e
6,t
SREEVALSAM
ENVIRONMENT IMPACT ASSESSMENT (EIA) REPORT &
ENVIRONMENT MANAGEMENT PLAN (EMP),
Prepared
for
M/s SREEVALSAM EDUCATIONAL TRUST Expansion of existing Hospital cum Medical College Campus Project
at
Edappal Village & Panchayat, Ponnani Taluk, Malappuram District, Kerala
Submitted
by
M/s Sreevalsam Educational Trust Reg. No. 53/2010, Regd. Office : Thekke Mdhom Road,
Thrissur, Kerala-680001.
Studies and Documentation
by
M/s Environmental Engineers & Consultants Pvt. Ltd. A1-198, Janak Puri, New Delhi – 110 058.
(NABET Accredited Consultancy Organization) Certif icate No. NABET/EIA/1720/SA 92 Dated 14-06-2019
Name of NABL Laboratory : M/s Standards Environmental & Analytical Laboratories, Kochi, Kerala NABL Acc. # : TC-5402 Monitoring Period : November & December, 2018.
Submitted To:
STATE ENVIRONMENT IMPACT ASSESSMENT AUTHORITY, KERALA
(September, 2019)
Project no. 050919-554-01 September, 2019
Declaration by experts contributing to the EIA of M/s Sreevalsam Educational Trust at Edappal Vil lage, Ponnani Taluk, Malappuram District , Kerala for proposed expansion of existing hospital cum medical college campus project.
I , hereby cer t ify that I was a part of the team in the following capacity that developed the above EIA. EIA Coordinator : P.Z. Thomas Name (ACO) : M/s Environmental Engineers & Consultants Pvt. Ltd. Signature & Date : 27-08-2019 Period of involvement : September, 2017 to September, 2019 Contact information : A1-198, Janakpuri, New Delhi-110058. Ph. no. 011-25507190 / 25622604. Branch of f ice :- C-306, Kanchanjunga Apartments, Palar ivattom P.O., Kochi, Kerala-682025. Functional Area Experts :
S.
N. Functional Areas Name of the expert Signature and Date
1. AP, WP, SHW & LU P.Z. THOMAS 27t h
Aug. , 2019
2. SE JOMON M.C. 17t h
Aug. , 2019
3. EB & SC Dr. RINOY VARGHESE
18t h
Aug. , 2019
MUKESH SUROLIYA 22
t h Aug. ,
2019
4. HG & Geo
AKHIL CHANDRAN (AFAE)
18t h
Aug. , 2019
5. AQ & NV MOHAN A. PATIL
22t h
Aug. , 2019
6. RH S.C. GUPTA 24
t h Aug. ,
2019
Declaration by the Head of the Accredited Consultant Organizat ion / Authorized person I , P.Z. THOMAS, hereby, conf irm that the above mentioned experts prepare the EIA of
M/s Sreevalsam Educational Trust. I also conf irm that the consultant organizat ion
shall be ful ly accountable for any mis- leading information mentioned in this statement.
Signature : DDDDDDDDDD. Name : P.Z. THOMAS Designation : EIA Coordinator & Managing Director Name of the EIA Consultant Organizat ion : M/s Environmental Engineers & Consultants Pvt. Ltd. NABET Certif icate No. & Issue Date : NABET/EIA/1720/SA 92 Dated 14-06-2019
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
i
TABLE OF CONTENTS
CHAPTER 1 INTRODUCTION
1.1 Purpose of the report 1-1 1.2 Identif ication of project & project proponent 1-3 1.2.1 - Identif ication of project 1-3 1.2.2 - Identif ication of the project proponent 1-3 1.3 Brief descript ion of nature, size, locat ion of the project
and its importance to the country, region 1-4
1.3.1 - Nature and size of the project 1-4 1.3.2 - Location of the project 1-5 1.3.3 - Importance of the project to the country and to the
region 1-8
1.4 Scope of the study 1-8 1.4.1 - Terms of Reference (ToR) and Scope of the study 1-8 1.4.2 - Scope of the study and compliance to "Terms of
Reference" in the EIA report 1-9
1.4.3 - The applicable regulatory framework 1-9 1.4.4 - Status of various statutory approvals / permissions 1-12 1.4.5 - Court case / Lit igat ion pending 1-14 1.4.6 - Structure of EIA report 1-15
CHAPTER 2 PROJECT DESCRIPTION
2.1 Descript ion of the project 2-1 2.1.1 - Est imated project cost 2-13 2.1.2 - Employment details 2-13 2.1.3 - Machinery details & building materials 2-14 2.2 Type of project 2-15 2.3 Need for the project 2-16 2.4 Location 2-16 2.5 Geology 2-22 2.5.1- Regional Geology 2-22 2.5.2 - Local Geology 2-23 2.6 Topography 2-23 2.7 Size or magnitude of the project 2-25 2.8 Design Considerat ion 2-28 2.8.1 Site history 2-32 2.9 Parking 2-32 2.10 Descript ion of mitigat ion measures incorporated into the
project to meet environmental standards 2-32
2.10.1 - Water supply and sewage disposal during construction phase
2-32
2.10.1.1 - Source of Water during construction phase 2-32
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
i i
2.10.1.2 - Daily Water Requirement during construction phase
2-33
2.10.1.3 - Sewage disposal during construction phase 2-33 2.10.2.1 - Source of water during operat ion phase 2-33 2.10.2.2 - Daily water requirement during operation
phase 2-33
2.10.2.3 - Sewage disposal during operation phase 2-37 2.11.1 - Storm water management (surface water
drainage) and rain water harvesting 2-42
2.11.2 - Solid Waste Management 2-43 2.11.3 - Green area development 2-47 2.11.4 - Air pollut ion control 2-51 2.11.5 - Noise pollut ion control & vibrat ion 2-52 2.11.6 - Vehicular traff ic density 2-53 2.11.6.1 - Interpretat ion 2-54 2.11.7 - Fire Fighting System 2-54 2.11.8 - Project implementat ion schedule 2-55
CHAPTER 3 DESCRIPTION OF THE ENVIRONMENT 3.1 Introduct ion / approach 3-1 3.2 Study area, period, components 3-1 3.2.1 - Study area 3-1 3.2.2 - Study period 3-1 3.2.3 - Components of study 3-2 3.2.4 - Sampling, frequency & method of baseline
environment monitoring 3-2
3.3 Meteorological parameters 3-4 3.3.1 - Temperature 3-4 3.3.2 - Rainfall 3-4 3.3.3 - Humidity 3-4 3.3.4 - Wind 3-4 3.3.4.1 - Wind rose diagram 3-5 3.3.4.2 - Inference 3-7 3.4 Air Environment 3-7 3.4.1 - Introduct ion 3-7 3.4.2 - Selection and number of sampling locat ions for
ambient air quali ty monitoring as per CPCB norms 3-7
3.4.3 - Sampling and analysis results 3-10 3.4.4 - Ambient air quality index 3-12 3.4.5 - Inference 3-12 3.5 Noise Environment 3-12 3.5.1 - Introduct ion 3-12 3.5.2 - Protocols followed for ambient noise level 3-12
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
i i i
monitoring & methodology 3.5.3 - Ambient noise level results 3-15 3.5.4 - Inference 3-15 3.6 Land Environment 3-16 3.6.1 - Introduct ion 3-16 3.6.2 - Land use / land cover 3-16 3.6.2.1 - Interpretation 3-16 3.6.3 - Soil 3-19 3.6.3.1 - Introduct ion 3-19 3.6.3.2 - Protocols for soil sampling methodology 3-19 3.6.3.3 - Soil sampling results 3-19 3.6.3.4 - Interpretation 3-20 3.7 Water Environment 3-20 3.7.1 - Introduct ion 3-20 3.7.2 - Water consumption and sources 3-20 3.7.3 - Ground water 3-21 3.7.3.1 - Ground water table identif ication 3-21 3.7.3.2 - Interpretation 3-22 3.7.3.3 - Protocols for water sampling methodology 3-22 3.7.4 - Water sampling results 3-24 3.7.5 - Interpretat ion of results 3-25 3.8 Ecological Environment 3-26 3.8.1 - Introduct ion 3-26 3.8.2 - Methodology 3-26 3.8.3 - Findings 3-27 3.8.4 - Interpretat ion of ecological assessment 3-48 3.9 Socio Economic Environment 3-48 3.9.1 - Introduct ion 3-48 3.9.2 - Approach adopted 3-49 3.9.3 - Stake holders 3-49 3.9.4 - Edappal grama panchayat 3-49 3.9.5 - Basic details of Edappal grama panchayat 3-50 3.9.6 - Edappal census town 3-50 3.9.7 - Demographics 3-51 3.9.8 - Caste wise male female population 2011 - Edappal 3-51 3.9.9 - Religion wise distribut ion of population 3-51 3.9.10 - Religion wise population 2011 - Edappal 3-52 3.9.11 - Grown of populat ion 3-52 3.9.12 - Growth of populat ion (percent) 2001 to 2011 -
Edappal 3-53
3.9.13 - Sex rat io - females per 1000 male 3-53 3.9.14 - Change in sex rat io 2001 to 2011 - Edappal 3-54 3.9.15 - Literacy 3-54
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
iv
3.9.16 - Change in l iteracy rate 2001 to 2011 - Edappal 3-55 3.9.17 - Workers prof i le 3-55 3.9.18 - Percentage of working populat ion - Edappal 3-56 3.9.19 - Demographics 3-56 3.9.20 - Interpretat ion of present socio-economic status of
the area 3-57
CHAPTER 4 ANTICIPATED ENVIRONMENTAL IMPACTS 4.1 Introduct ion 4-1 4.1.1 - Area for identif ication of Environmental aspects
and impacts 4-1
4.2 Detai ls of ant icipated environmental impacts due to the proposed project and the mit igat ion measures for minimizing and / or offsett ing adverse impacts identif ied
4-2
4.2.1 - Air Environment 4-2 4.2.2 - Noise Environment 4-5 4.2.3 - Land Environment 4-6 4.2.4 - Water Environment 4-6 4.2.5 - Biological Environment 4-8 4.2.6 - Socio-Economic environment 4-8 4.2.7 - Other environmental aspects 4-9 4.3 Identif ied environmental impacts from various aspects 4-9 4.4 Select ion criteria for evolving signif icant impacts 4-15 4.5 The marking for various criteria 4-16 4.6 Scores of all ant icipated environmental impacts after
applying the marking criteria 4-17
4.7 List of signif icant environmental impacts 4-23 4.8 Mit igation measures for the signif icant impacts identif ied 4-24
CHAPTER 5 ANALYSIS OF ALTERNATIVES (TECHNOLOGY AND SITE)
5.1 Introduct ion 5-1 5.2 Alternat ive sites 5-1 5.3 Alternat ives in technology 5-2 CHAPTER 6 ENVIRONMENT MONITORING PROGRAM
6.1 Introduct ion 6-1 6.1.1 - Performance indicators (Pls) 6-1 6.1.1.1 - Water quality monitoring 6-1 6.1.1.2 - Ambient air quality (AAQ) monitoring 6-2 6.1.1.3 - Noise level monitoring 6-2
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
v
6.1.1.4 - Success of vegetation 6-2 6.2 Data management 6-9 6.3 Report ing schedule 6-9 6.4 Emergency 6-9 CHAPTER 7 ADDITIONAL STUDIES
7.1 Introduct ion 7-1 7.2 Risk Assessment and Disaster Management Plan 7-1 7.2.1 - Need and plans 7-1 7.2.2 - Response in case of earthquake 7-2 7.2.3 - Status on natural disaster w.r.t. site and
surroundings 7-3
7.2.4 - Response of LPG leakage 7-3 7.2.5 - Response in case of f ire 7-4 7.3 Resource conservation 7-9 7.3.1 - General approach 7-9 7.3.2 - Water resources 7-9 7.3.3 - Construction materials 7-10 7.3.4 - Top soi l as a resource 7-10 7.3.5 - Energy as a resource 7-10 7.4 Traff ic impact assessment 7-11 7.5 Social impact assessment 7-13 7.5.1 - Introduct ion - Corporate Environment
Responsibi l ity 7-13
7.5.2 - Suggested sectors to perform act ivit ies under CER
7-14
7.5.3 - Approach adopted for assessment 7-15 7.5.4 - Stake holders 7-15 7.5.5 - Proposed CER act ivit ies 7-15 7.5.5.1 - Summary of CER activit ies 7-18 7.5.5.2 - Time frame (tentat ive) for execution of CER
act ivit ies 7-18
7.6 Rehabil itat ion & Resettlement (R&R) Action plan 7-18 7.7 Public hearing 7-18 CHAPTER 8 PROJECT BENEFITS 8.1 Introduct ion 8-1 8.2 Physical infrastructure 8-1 8.3 Social infrastructure 8-1 8.4 Economic benefits 8-1 8.5 Importance of the present project 8-2
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
v i
CHAPTER 9 ENVIRONMENT COST BENEFIT ANALYSIS 9.1 Introduct ion 9-1 CHAPTER 10 ENVIRONMENT MANAGEMENT PLAN 10.1 Introduct ion 10-1 10.2 Environmental Management System (EMS) 10-1 10.3 Environmental pol icy 10-1 10.4 Environment Management Cell (EMC) 10-3 10.5 Other management aspects of the Environmental Cell 10-4 10.6 Standard operat ion procedures (SOP) 10-4 10.7 Cost est imation for environment management system 10-5
CHAPTER 11 SUMMARY 1.0 Introduct ion 11-1 2.0 Project description 11-2 3.0 Descript ion of the Environment 11-4 4.0 Anticipated Environmental impacts & mitigation measures 11-7 5.0 Environmental monitoring program 11-13 6.0 Additional studies 11-13 7.0 Project benefits 11-14 8.0 Environment Management plan 11-14 9.0 Ecological damage & Remediat ion plan, Natural & Community
resources augmentat ion plan 11-15
CHAPTER 12 DISCLOSURE OF ACO CONSULTANT
12.1 The name of consultants engaged with their brief resume 12-1 12.2 Prof ile of ACO 12-2
CHAPTER 13 ECOLOGICAL DAMAGE ASSESSMENT & REMEDIATION PLAN, NATURAL & COMMUNITY RESOURCES AUGMENTATION PLAN 13.1 Introduct ion 13-1 13.2 Damage assessment & Remediat ion plan 13-3 13.3 Summary of Remediation plan - 3 years plan 13-14 13.4 Natural resources augmentation plan - 3 years plan 13-15 13.5 Community resources augmentat ion plan - 3 years plan 13-16 13.6 Summary of remediation, natural resources & community
augmentation plan 13-17
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
v i i
LIST OF FIGURES
Fig. No.
Description
Page Nos.
1.1 Key map showing the location of the project area 1-7
2.1 Conceptual plan of the project 2-12
2.2 Route map of the project area 2-17
2.3 Satell ite map within 10 km radius 2-18
2.4 Satell ite map superimposed with the project boundary 2-19
2.5 Toposheet of the study area 2-20
2.6 Vicinity map showing 10 km radius of the project site 2-21
2.7 Topographical contour map of the project site 2-24
2.8 Time series satel l ite image - January, 2008 2-28
2.9 Time series satel l ite image - December, 2009 2-29
2.10 Time series satel l ite image - December, 2012 2-29
2.11 Time series satel l ite image - Apri l, 2013 2-30
2.12 Time series satel l ite image - December, 2013 2-30
2.13 Time series satel l ite image - December, 2018 2-31
2.14 Time series satel l ite image - Current image, August, 2019
2-31
2.15 Daily water consumption balance chart 2-36
2.16 Sewage Treatment Plant (STP) diagram 2-40
2.17 Water Treatment Plant (WTP) diagram 2-42
3.1 Wind rose diagram 3-6
3.2 Ambient air quality monitoring locat ion map 3-9
3.3 Ambient noise monitoring location map 3-14
3.4 Land use map within 10 km radius of the project site 3-18
3.5 Categorizat ion of blocks of Malappuram distr ict 3-21
3.6 Water sampling locat ion map 3-24
7.1 Flow chart of Disaster Management Authority (DDMA) 7-6
7.2 Flow chart of Action plan for crisis management in the district
7-7
7.3 Flow chart of incident response team 7-7
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
v i i i
LIST OF TABLES
Table Nos.
Description Page Nos.
2.1 Project features & Environmental Sett ing 2-1
2.2 Immediate site surrounding features 2-17
2.3 Plot area break-up 2-25
2.4 Built-up area break-up 2-25
2.5 Building block details along with status of construct ion 2-26
2.6 List of tree species already planted within the campus 2-47
3.1 Environmental attributes 3-2
3.2 Frequency distr ibut ion of wind speed & wind direction 3-7
3.3 Ambient Air Quality locat ion detai ls 3-9
3.4 Ambient Air Quality analysis results 3-11
3.5 National Ambient Air Quali ty Standards 3-12
3.6 Ambient air quality index 3-12
3.7 Noise monitoring locat ion details 3-14
3.8 Noise level monitoring results 3-15
3.9 National ambient noise level standard 3-15
3.10 Land use / land cover classif icat ion system 3-16
3.11 Soil sampling locat ion details 3-19
3.12 Chemical properties of analyzed soil samples 3-19
3.13 Water consumption details for various purposes 3-20
3.14 Ground water sampling locat ion 3-23
3.15 Surface water sampling locat ion 3-24
3.16 Ground water analysis results 3-25
3.17 Surface water analysis results 3-25
3.18 List of f loral species observed in the site area (trees, tree
saplings, shrubs, herbs, cl imbers, ferns)
3-28
3.19 List of faunal species observed in the site area (mammals, 3-43
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
ix
repti les, birds, Amphibian, Odonates, Butterf l ies,
Mill ipedes and Centipedes, Ants, Spiders)
3.20 Detai ls of stake holder 3-49
4.1 Matrix of identif ied Environmental Aspects & their
ant icipated impacts from the project
4-11
4.2 Criteria for evolving signif icant impacts 4-16
4.3 Marking for various criteria 4-17
4.4 Matrix showing the scores of al l environmental impacts as per the criteria
4-18
4.5 List of Signif icant impacts identif ied 4-23
4.6 Mit igation measures for the signif icant impacts identif ied during construction phase
4-25
4.7 Mit igation measures for the signif icant impacts identif ied during operation phase
4-27
6.1 Environment Monitoring Action Plan 6-3
6.2 Environment Monitoring Plan with Budgetary Allocation 6-8
10.1 Environmental Management Cell 10-3
10.2 Cost Estimation of Environmental Management Plan during Construct ion phase
10-5
10.3 Cost Estimation of Environmental Management Plan during Operation phase
10-6
13.1 Damage Assessment & Remediat ion Plan 13-3
13.2 Summary of remediat ion plan for 3 years 13-14
13.3 Natural resources augmentation plan for 3 years 13-15
13.4 Community Resources Augmentat ion Plan for 3 years 13-16
13.5 Summary of Remediation, Natural Resource & Community Augmentat ion Plan
13-17
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
x
LIST OF PLATES
Plate
No. Description
Page
Nos.
2.1 Site Photographs showing current status of the site 2-11
2.2 Photographs of existing STP 2-41
2.3 Photographs of existing Bio-gas generat ion plant 2-45
2.4 Photographs of the plant species / tree species already
planted within the campus
2-49
2.5 Photographs of the road side plantat ion within the
campus
2-50
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
x i
LIST OF ANNEXURES
Annexure
No.
Description
1.1 Notif icat ion dated 14/03/2017 (Notif ication No. S.O. 804 (E)
1.2 A f low chart showing the procedure as per Notif icat ion dated
14/03/2017
1.3 Copy of the minutes of meeting of 06 t h meeting of EAC
1.4 Copy of ToR approval letter issued vide Letter No. 23-89/2018-IA.III
dated 22/06/2018.
1.5 Copy of Possession cert if icate
1.6A
&
1.6B
Copy of Land Use Certif icate and Land Conversion Certif icate
issued by Tahsildar, Ponnani on 31-03-2014 stat ing that the land is
"do not fall under Agricultural use and this land can be used for
Education purpose to establ ish Education Inst itutions".
1.7 Copy of the resolution passed by the Trust in favour of Mr. Rajan
Achuthan Nair
1.8 Detai ls regarding Scope of the study and compliance to the
approved "Terms of Reference" (ToR) in the EIA report
1.9 Copy of Init ial Building Permit granted by Edappal Grama
Panchayat for the Hospital project with built -up area 5,783.7 sq.m.
1.10 Copy of Renewal of Building Permit granted by Edappal Grama
Panchayat for the Hospital project with built -up area 32,160 sq.m.
1.11 Copy of Renewal of Building Permit granted by Edappal Grama
Panchayat for the project with addit ional built -up area of 42,636.4
sq.m.
1.12 Copy of Integrated “Consent to Establish” f rom Kerala State
Pollut ion Control Board dt. 06.07.2012 val idity upto 30.11.2014
1.13 Copy of Init ial “Consent to Operate” from Kerala State Pollut ion
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
x i i
Control Board dt. 19.06.2015 Validity upto 30.09.2016
1.14 Copy of Renewal of “Consent to Operate” from Kerala State
Pollut ion Control Board dt. 27/11/2017 Validity upto 30/09/2019
1.15 Copy of Init ial NOC from Fire & Rescue Services for Hospital
Building dt. 21.01.2012
1.16 Copy of NOC from Fire & Rescue Services for Hospital Building
6(B+G+4) storeyed 22.30 m. height dt. 11.03.2013
1.17 Copy of NOC from Fire & Rescue Services for 9 storeyed
Residential Building (G+8) 28.80 M. height dt. 25.10.2013
1.18 Copy of Approval of Buildings layout and land use from Town
Planner, Off ice of the Chief Town Planer, Thiruvananthapuram vide
Order NO. C1/9579/13/DDS dt. 18.02.2014
1.19 Copy of Approval from Kerala State Electr icity Board for power
supply dt. 06.11.2013
2.1 Copy of the MoU between IMAGE & the project proponent
3.1 Copy of analysis reports of all ambient air quality stat ions
3.2 Copy of analysis report of al l ambient noise level stations
3.3 Copy of analysis report of soil sampling station
3.4 Copy of soi l investigat ion report
3.5 Copy of the analysis report of water sampling station (Ground water)
(bore well)
3.6 Copy of the analysis report of water sampling stat ion (Surface water
- Ayarichira)
12.1 Copy of the accreditat ion certif icate of the ACO from NABET / QCI
12.2 Copy of the accreditation certif icate along with the scope of work of
the laboratory
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 1 In t roduct i on Page 1 - 1
1.0 INTRODUCTION
1.1 Purpose of the Report
M/s Sreevalsam Educational Trust proposed an expansion of exist ing
Hospital cum Medical College project at Survey Nos. 157/2, 159/3, 158/1,
157/0, 158/1, 159/3, 158/2, 158/5, 159/1, 159/2, 157, 159/3, 164/3, 164/7,
164/4, 163/3, 158/7, 158/3, 158/4, 166/2, 166/1, 156/3, 164/1, 156/3,
164/1, 164/2, 156/4, Edappal Vil lage, Ponnani Taluk, Malappuram District,
Kerala. The plot area of the Hospital cum Medical College Project is
9.4534 ha (94,534.56 sq. m.) and the total built -up area is 1,38,937.50
sq. m. (exist ing 53,889.72 sq.m. + proposed 85,047.78 sq.m.).
Building construction of 53,889.72 sq.m. of the hospital cum medical
college is already completed. The teaching hospital component is for a
built -up area of 32,160 sq.m. and the educational component is with
built -up area of 21,729.72 sq.m. It is proposed to construct addit ional
built -up area of 85,047.78 sq.m and the total cumulative built -up area wil l
be 1,38,937.5 sq.m.
The land was purchased and registered between the year of 2010 to 2011
and started the construct ion work of Teaching Hospital in 2011 as per the
Building permit vide permit no. 224/11-12 dated 03-11-2011 obtained from
Edappal Grama Panchayat for a built-up area of 5,783.70 sq.m.
Subsequently, the expansion of the building was carried out with the
renewal of building permit vide permit no. B2-224/11-12 dated 27-06-2012
valid upto 26-06-2015 issued by the Panchayat for a cumulat ive built -up
area of 32,160 sq.m. in 2012. This work was carried out without pr ior
Environmental Clearance and the construction of this building is
completed. Further, renewal of building permit vide permit
no. A5-365/14-14 dated 24-03-2014 was issued for Academic block,
Hostels with a cumulative buil t-up area of 43,636 sq.m. and construct ion
of 21,729.72 sq.m. is completed. Educat ional insti tut ions are exempted
from the purview of EIA Notif icat ion vide Notif ication dt. 22-12-2014. For
the f irst t ime, the requirement of prior Environmental Clearance was
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 1 In t roduct i on Page 1 - 2
inserted in Kerala Municipal ity Building Rules (KMBR) by an amendment
of KMBR made in 05/02/2013.
Therefore, the project proponent was not aware of the requirement of
prior Environmental Clearance and constructed the Teaching Hospital
building without obtaining prior Environmental Clearance and hence the
violated the provisions of Environment Protect ion Act, 1986.
Ministry of Environment, Forests & Climate Change (MoEF & CC) issued a
Notif icat ion dated 14/03/2017 (Notif icat ion No. S.O. 804 (E)) and gave
one time opportunity to the projects who have commenced their activity
without taking prior Environmental Clearance violated the EIA Notif ication,
2006. The copy of the Notif ication is attached as Annexure No. 1.1. A
f low chart showing the procedure as per the said Notif icat ion is provided
at Annexure No. 1.2.
An application with draft Terms of Reference (ToR) for EIA Study and for
obtaining Environmental Clearance under the provision of MoEF&CC
Notif icat ion dt. 14/03/2017 was submitted at MoEF&CC on 23/06/2017
vide File No. 23-89/2018-IA-III (V).
Thereafter, the proposal was considered in the 06 t h meeting of Expert
Appraisal Committee (EAC) at MoEF&CC on 19 t h - 20 t h , Apri l, 2018 vide
agenda item No. 6.3.7 for grant of Terms of Reference (ToR) for
undertaking Environment Impact Assessment (EIA) studies and
preparation of Environment Management (EMP).
The EAC recommended the project for grant of “ToR” for undertaking
Environment Impact Assessment (EIA) study and preparation of
Environment Management Plan (EMP). The copy of the minutes of
meeting of 06 t h meeting of EAC is attached as Annexure No. 1.3. The
Ministry accepted the recommendations of EAC and the “ToR” was
approved and issued vide Letter No. 23-89/2018-IA.I II dated 22/06/2018.
The copy of the “ToR” Letter is attached as Annexure No. 1.4.
With a view to assess the environmental impacts due to the construct ion
act iv it ies, to suggest the mitigat ion measures, to assess the ecological
damage due to the i l legal construction, to prepare remediation plan and
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 1 In t roduct i on Page 1 - 3
the natural and community resource augmentat ion plan as per the
approved ToR granted, the project proponent has engaged the services
of M/s Environmental Engineers & Consultants Pvt. Ltd., New Delhi (an
MoEF & CC accredited Consultancy Organizat ion under QCI / NABET
Scheme).
1.2 Identification of project & project proponent
1.2.1 Identification of project
In order to faci li tate the medical and medical education requirement in the
project vicinity and in Ponnani Taluk of Malappuram District, Kerala M/s
Sreevalsam Educational Trust constructed a hospital cum medical col lege
project at Edappal Vil lage, Ponnani Taluk, Malappuram Distr ict, Kerala in
Plot area of 9.4534 ha and constructed of buildings with built -up area
53,889.72 sq. m. and due to increase in demand the project proponent is
going for expansion of the exist ing campus with addit ional built -up area of
85,047.78 sq.m. After the proposed expansion the cumulat ive built -up
area of the hospital cum medical college wil l be 1,38,937.50 sq. m.
(existing bui lt-up area 53,889.72 sq. m. + 85,047.78 sq.m.)
The land for the project is under the possession of M/s Sreevalsam
Education Trust and the possession certif icate issued by the Vil lage
Off ice, Edappal is attached at Annexure No. 1.5.
Also, the Land Use Certi f icate and Land Conversion Certi f icate issued by
Tahsildar, Ponnani on 31-03-2014 stat ing that the land is "do not fal l
under Agricultural use and this land can be used for Educat ion purpose to
establish Education Institut ions". The copy of the said Land Conversion
Cert if icate is attached at Annexure No. 1.6A & 1.6B.
1.2.2 Identification of project proponent
M/s Sreevalsam Educational Trust establishing a public charitable trust
for establishing a centre for professional medical educat ion by promoting
medical, para-medical, nursing and other medical services along with a
super specialty hospital for health promotion. As per the trust deed made
in January, 2010, the fol lowing are the members of the trust :-
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 1 In t roduct i on Page 1 - 4
SN Name & Designation Address of member
1. Dr. V.P. Gopinathan,
Chairman
Thrissur Corporation, House No. 23/338,
Anchery Kizhakke Pisharam, Ollur Village,
Anchery Desom, P.O. Anchery, Thrissur
Taluk & District, Kerala-680006.
2. K.R. Raju, Vice
Chairman
Thrissur Corporation, House No. 36/361/1,
"Omkaram", Kottapuram Road, Thrissur
Vil lage, Punkunna Desom, P.O Punkunnam,
Thrissur Taluk & District, Kerala-680002.
3. K. Vijayan, Secretary Thrissur Corporation, House No. 5/50/3,
Kunnathu Mana, Ollukkara Village,
Kalathode Desom, P.O. Ollukkara, Thrissur
Taluk & District, Kerala-680655.
The contact detai ls of the applicant is given below :-
Name of Authorized Signatory : Mr. Rajan Achuthan Nair
(Secretary)
Registered Address &
Correspondence Address
: M/s Sreevalsam Educational Trust,
Thekke Madhom Road,
Thrissur, Kerala-680001
Contact No. : 0487-2430114 / 09539641006
E-mail : [email protected]
The copy of the resolution passed by the Trust in favour of Mr. Rajan
Achuthan Nair is attached at Annexure No. 1.7.
1.3 Brief description of nature, size, location of the project and its importance to the country, region. 1.3.1 Nature and size of the project
M/s Sreevalsam Educational Trust is involving in development of hospital,
medical colleges and inst itutional projects in Kerala. The educat ional trust
is having good experience in medical and insti tut ional projects especially
in Kerala.
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 1 In t roduct i on Page 1 - 5
M/s Sreevalsam Educational Trust constructed a hospital cum medical
college project at Edappal Vil lage, Ponnani Taluk, Malappuram District,
Kerala in plot area of 9.4534 ha and total built -up area of the hospital cum
medical college wil l be 1,38,937.50 sq. m. (exist ing bui lt-up area
53,889.72 sq. m. + 85,047.78 sq.m.). The estimated cost of the project
is about Rs. 180 Crores. The project is expected to employ about 1,000
direct job opportunit ies which includes medical & non-medical staff .
1.3.2 Location of the project
The project site is within the Panchayat l imits of Edappal Grama
Panchayat. The nearest town is Edappal town which is about 2 km away
(N) from the site and the nearest city is Kozhikode city and is located
about 60 km (NW ).
The access road to the project site is from 10 m wide & 8 m wide road in
the northern side which is connected to Naduvattom-Karinkal lthani Road
which is located at 0.5 km towards north direction from the site.
The nearest National Highway is N.H. 17 (Edappally-Panvel Highway) at
about 2 km towards North direction (at Edappal Town). The nearest
rai lway stat ion (Kutt ipuram Railway Station) is about 10 km (NE) and
Calicut International Airport , Karipur is about 40 Km (NW) away from the
project s ite.
Particulars Details
Geographical
Locat ion
Lat itude (N) 10046‘00.86“ to 100 45’48.56“
Longitude (E) 76000’36.45” to 760 00’23.53” Local name of the
project area
Edappal
Project Site
Toposheet No.
58B/4
(old toposheet no.)
Name of Vi llage Edappal
Name of
Panchayats
Edappal
Nearest Town Edappal town - about 2 km away (N)
Name of Taluk Ponnani
Name of District Malappuram
Name of State Kerala
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 1 In t roduct i on Page 1 - 6
The key map showing the locat ion of the project area is provided at
Figure 1.1.
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 1 In t roduct i on Page 1 - 7
Figure 1.1 - Key Map
(Source :- Google map) (Vintage 2019)
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 1 In t roduct i on Page 1 - 8
1.3.3 Importance of the project to the country and to the region.
M/s Sreevalsam Educational Trust has developed the hospital cum
medical col lege with a vision to “Provide quality healthcare with
exceptional service and compassion at affordable cost". Due to the rapid
development in Kerala there are lots of residential, commercial and off ice
building construct ion projects are introduced and thereby the f loat ing of
populat ion from their native place to their working place / urban area is
going on. Due to the high rate of population shif t ing there is an increase
in burden on the infrastructure and medical faci l it ies of an area. To
accommodate the same the medical hospital wi th high patient
management capacity with quality services is must in every districts of the
State. In order to overcome this problem, M/s Sreevalsam Educational
Trust decide the expansion of their exist ing hospital cum medical col lege
project in Edappal Vil lage, Ponnani Taluk, Malappuram Distr ict, Kerala.
There is an urgent requirement for the construction of hospital cum
medical col lege with associated activit ies in the area as per the faci lit ies
to be provided to the nearby people to facil itate on easy and quick
medical facil it ies and thereby the hospital/healthcare services in a very
easy way as per the needs.
The medical healthcare of hospital and associated act ivit ies bring about
gains in Gross Domestic Product (GDP). The project will create direct
employment opportunit ies for about 1,000 persons and indirect
employment opportuni ties for about 3,000 persons.
Direct and indirect taxes wil l also be paid by the project proponent to the
Local Self Government, State Government and to the Central Government.
These are the sources of revenue for the Government. The public revenue
wi ll be uti l ized by Government for development of various infrastructural
faci l i t ies for the public in the f ield of health, educat ion and social welfare
etc.
1.4 Scope of the study.
1.4.1 Terms of Reference (ToR) and Scope of the study
The project proposal underwent the scoping exercise through the Expert
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 1 In t roduct i on Page 1 - 9
Appraisal Committee at MoEF & CC. the scope of study was approved
through “ToR” and the same was communicated to the project proponent
vide letter dated 22-06-2018.
This EIA report has been prepared based on the above approved ToR.
1.4.2 Scope of the study and compliance to "Terms of Reference" in the EIA report
The detai ls regarding Scope of the study and compliance to the approved
"Terms of Reference" (ToR) in the EIA report is provided at Annexure
No. 1.8.
1.4.3 The applicable regulatory frame work
The following Acts, Rules, Govt. Orders / Polic ies are to be fol lowed by
the project proponent in the operation of all buildings :-
���� The Environment Protection Act, 1986
An Act to provide for the protection and improvement of environment
and for matters connected there with. Introduction of this statute was
due to a decision taken at United Nation Conference on the Human
Environment held at Stockholm in June, 1972. This is an umbrella Act
and project proponent is required to comply with the provisions of the
Act. A few of these are summarized below :-
���� The EIA Notification, 2006 & the subsequent amendments.
EIA Notif ication, 2006 was issued under Sect ion 3 of the Environment
Protect ion Act, in supersession of EIA Notif ication, 1994. Through this
Notif icat ion, the Central Governments directs that before the
commencement of any activity or modernization of exist ing activity
l isted in the "Schedule" to the Notif icat ion, prior Environment
Clearance is mandatory. Prior Environment Clearance is required for
expansion, modernizat ion, change in project area, product mix etc.
���� Manual on norms and standards for environment clearance of large
construction projects issued by MoEF, mentions the applicable
standards and norms to ensure sustainable construction activ ity.
���� The Water Pollution (Prevention & Control) Act, 1974
An Act to provide the prevention and control of water pollut ion and the
maintaining or restoring of wholesomeness of water, for the
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 1 In t roduct i on Page 1 - 10
establishment, with a view to carrying out the purposes of aforesaid, of
Boards for the prevention and control of water pollution, for conferring
on and assigning to such Boards powers and functions relating thereto
and for matters connected therewith. Any activity before its
establishment needs to take Consent to Establish and Consent to
Operate from the concerned Pollution Control Board.
���� The Air Pollution (Prevention & Control) Act, 1981
An Act to provide for the prevention, control and abatement of air
pol lut ion for the establishment, with a view to carrying out the aforesaid
purposes, of Boards, for conferring on and assigning to such Boards
powers and funct ions relat ing thereto and for matters connected
therewith. Any act ivity before its establishment needs to take Consent
to Establish and Consent to Operate from the concerned Pollut ion
Control Board.
���� The Forest (Conservation) Act, 1988
An Act to provide for the conservation of forests and for matters
connected therewith or ancillary or incidental thereto. Forest Clearance
is required from MoEF&CC, if Forest land is found in the project s ite.
���� The Wildlife (Protection) Act, 1972
An Act to provide for the protection of W ild animals, birds and
plants and for matters connected therewith or ancil lary or incidental
thereto. W ildl ife Conservat ion Plan is to be prepared, approved by the
Wildl ife W arden and implemented, if Wildlife is affected by the proposed
project.
���� The Noise Pollution (Regulation and Control) Rules, 2000.
This Rule is issued under Sect ion 3 of Environment Protection Act.
Through this Rule, four categories areas / zone as per the Schedule is
provided in respect of "Ambient Air Quality Standards in respect of
Noise" if sensit ive receptors in the project area are affected by the noise
created by the project, necessary mitigat ive measures are to be
proposed in EIA report.
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 1 In t roduct i on Page 1 - 11
���� The National Green Tribunal Act, 2010
An Act to provide for the establishment of a National Green Tribunal for
the effective and expedit ious disposal of cases relat ing to
environmental protect ion and conservat ion of forests and other natural
resources including enforcement of any legal r ight relat ing to
environment and giving rel ief and compensation for damage to persons
and property and for matters connected therewith or incidental thereto.
���� The Kerala Promotion of Tree Growth in Non-Forest Areas
(Amendment) Act, 2007.
An Act expedient to amend the Kerala Promotion of Tree Growth in Non-
Forest Areas Act, 2005. As per the said Act, no permission is necessary
for cutt ing and removal of trees provided in the Schedule.
���� The Hazardous and Other Wastes (Management and Transboundary
Movement) Rules, 2016.
Hazardous W aste (Management, Handl ing & Transboundary) Rules,
2016 prescribing measures and procedures for storage, transport
treatment and disposal of hazardous waste and the present project
act ivity generates hazardous waste which requires obtain authorization.
���� The Solid Waste Management Rules, 2016 - Details the procedures for
generators and processors of sol id waste. The present act iv ity has to
implement the measures mentioned in the above Rule .
���� The Bio-medical Waste Management Rules, 2016 - Detai ls the
procedures for generators and processors of bio-medical waste. The
present activity has to implement the measures mentioned in the above
Rule.
���� The E-Waste Management Rules, 2016 - Details the procedures for
generators and processors of e-waste. The present activity has to
implement the measures mentioned in the above Rule.
���� The Construction & Demolition Waste Management Rules, 2016 -
Mandates safer disposal of construction & demolition waste and the
responsibi l ity of local bodies in this regard the present act ivity has to
implement the measures mentioned in the above Rule.
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 1 In t roduct i on Page 1 - 12
���� Plastic Waste Management Rules, 2016 - Detai ls the procedures for
generators and processors of plast ic waste. The present activ ity has to
implement the measures mentioned in the above Rule.
���� National Building Code (NBC) of India - Mentions the standards and
norms for construct ion materials and construct ion pract ices.
���� The Indian Electricity Rules, 1956 - Mandates the user to obtained
approval for instal lation of transformers, generator, cabling, electr ical
sub-stat ion etc.
���� Bureau of Energy Efficiency - Norms to provide minimum requirements
for the energy eff icient design and construct ion of buildings.
���� Norms issued by Fire & Rescue Department, Govt. of Kerala to take
approvals for al l commercial buildings and to follow the f ire f ighting
capabil ity guideline within those commercial buildings before the
commercial building is put to use.
���� Kerala Municipality Building Rules, 2009 / 2012 and its subsequent
amendments mandate obtaining development permit for all construction
projects.
1.4.4 Status of various statutory approvals / permissions
The project has obtained the fol lowing mandatory approvals / permissions
from various statutory agencies. The details are given below :-
S.N. Activity Period
1. Land Purchased (Private Owned Land )
Date of Registrat ion 18-08-2010,
16-08-2010, 21-08-2010, 31-08-
2010, 20-12-2010, 21-05-2010,
20-09-2010, 23-04-2011,
24-09-2011
2.
In it ial Bui lding Perm it granted by
Edappal Gram a Panchayat for the
Hospita l project with bui l t-up area
5,783.7 sq.m . (Annexure No. 1.9)
No. 224/11-12
dt. 03-11-2011
3. Renewal of Bui lding Perm it granted by
Edappal Gram a Panchayat for the
No. B2-224/11-12
dt.27-06-2012
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 1 In t roduct i on Page 1 - 13
Hospita l project with bui l t-up area
32,160 sq.m . (Annexure No. 1.10)
Validity upto 26-06-2015
4.
Renewal of the Build ing Perm it granted
by Edappal Gram a Panchayat for the
project with addit ional bui l t-up area of
42,636.4 sq.m . (Annexure No. 1.11)
No. A5-365/14-14
dt.24-03-2014
Validity upto 23-03-2017
5.
Integrated “Consent to Establ ish” f rom
Kerala State Pol lution Control Board
(Annexure No. 1.12)
No.
PCB/HQ/MLPM//IC/6164/2012
dt. 06.07.2012 valid i ty upto
30.11.2014
6.
In it ial “Consent to Operate” from
Kerala State Pol lution Control Board
(Annexure No. 1.13)
No. PCB/HO/MLPM/IC/6164/2012
dt. 19.06.2015
Val idity upto 30.09.2016
7.
Renewal of “Consent to Operate” f rom
Kerala State Pol lution Control Board.
(Annexure No. 1.14)
No. PCB/HO/MLPM/IC/6:64/2012
dt. 27/11/2017
Val idity upto 30/09/2019
9
In i t ial NOC from Fire & Rescue
Services for Hospita l Bui ld ing
(Annexure No. 1.15)
No. G2-12372/2011
dt. 21.01.2012
10
NOC from Fire & Rescue Services for
Hospita l Bui ld ing 6(B+G+4) storeyed
22.30 M. height (Annexure No. 1.16)
No. G1-12977/12
dt. 11.03.2013
11
NOC from Fire & Rescue Services for 9
storeyed Residential Bui lding (G+8)
28.80 M. height (Annexure No. 1.17)
No. G1-12587/2013
dt. 25.10.2013
12
Approval of Bui ld ings layout and land
use f rom Town Planner, Of f ice of the
Chief Town Planer,
Thiruvananthapuram. (Annexure No.
1.18)
Order NO. C1/9579/13/DDS
dt. 18.02.2014
13
Approval f rom Kerala State Electr ic ity
Board for power supply.
(Annexure No. 1.19)
No.
DB.17/HT.SC/Sreevalsam /2013-
2014/3108
dt. 06.11.2013
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 1 In t roduct i on Page 1 - 14
1.4.5 Court Case / Litigation pending
There is no court case / l it igation pending against the land or the project
proponent with respect to the project.
1.4.6 Structure of EIA Report
The generic structure of Environmental Impact Assessment (EIA) study for
the project is as fol lows:
Chapter 1 : Introduct ion
Chapter 2 : Project Descript ion Chapter 3 : Descript ion of the Environment Chapter 4 : Ant ic ipated Environmental Impacts & Mitigation Measures Chapter 5 : Analysis of Alternatives (Technology & Site) Chapter 6 : Environmental Monitor ing Program. Chapter 7 : Additional Studies. Chapter 8 : Project Benefits Chapter 9 : Environmental Cost Benefit Analysis. Chapter 10 : Environmental Management Plan Chapter 11 : Summary & Conclusion. Chapter 12 : Disclosure of Consultant Chapter 13 : Ecological damage assessment and Remediation plan,
Natural and community resources augmentation plan.
*****************************************************************************
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 2 Pro ject Descr ip t ion Page 2 - 1
2.0 PROJECT DESCRIPTION
2.1 Description of the project
In order to faci li tate the medical and medical education requirement in the
project vicinity and in Ponnani Taluk of Malappuram District, Kerala M/s
Sreevalsam Educational Trust constructed a hospital cum medical col lege
project at Edappal Vil lage, Ponnani Taluk, Malappuram Distr ict, Kerala in
Plot area of 9.4534 ha and constructed of buildings with built -up area
53,889.72 sq. m. and due to increase in demand the project proponent is
going for expansion of the exist ing campus with addit ional built -up area of
85,047.78 sq.m. After the proposed expansion the cumulat ive built -up
area of the hospital cum medical col lege wi ll be 1,38,937.50 sq.m.
(existing bui lt-up area 53,889.72 sq. m. + 85,047.78 sq.m.) with number of
hospital beds of 1,170 beds.
The detai ls regarding the project features and environmental sett ings are
provided at Table 2.1.
Table 2.1 – Project features and Environmental Settings
Particulars Details
Total Plot Area 9.4534 ha. (94,534.56 sq. m)
Total Built -up Area 1,38,937.50 sq. m.
(Exist ing 53,889.72 sq.m +
proposed 85,047.78 sq.m)
Object ive of the project Expansion of existing Hospital cum Medical
College Project with supporting addit ional
infrastructure faci li t ies.
Project cost Rs. 180 Crores
Total Number of beds 1,170 beds
(Exist ing 570 beds + Proposed 600 Beds)
No. of Students in the medical
col lege 750 Students
Max. height 30 m
Power requirement 2,250 kVA
Source of power & back-up KSEB & D. G. Sets (standby arrangement)
D.G. sets Capacity Exist ing - 500 kVA x 1 no. + 625 kVA x 1 no.
Proposed - 500 kVA x 1 no. + 625 kVA x 1 no.
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 2 Pro ject Descr ip t ion Page 2 - 2
Use of Solar energy Proposed 200 KW solar l ighting and
5,000 Ltrs solar water heaters
Employees in the facil ity
About 1000 Direct Jobs
(Doctors, nurses, medical staff , security,
Group- D housekeeping staff etc.)
Parking Provided 1,184 Cars + 1,409 Two Wheelers
Daily maximum population About 11,000 Persons
(Patients + Visitors + Hospital Staff )
Daily Water consumption 1,328 KL/day (Fresh water 677 KL + Recycled
water reused 651 KL)
Sources of Water Ground water, Stored rain water & Recycled
water
Domestic sewage generation &
its disposal 696 KL/day & treated through STP & recycled
Eff luent generation from
Laboratory & Laundry & its
disposal
27 KL/day & treated through ETP & recycled
Rain water storage tank
capacity provided About 5,000 KL storage capacity
Solid Waste Generation 2,093 kg/day
Solid Waste Disposal Facil ity
Bio-gas generation plant for biodegradable
waste & non-biodegradable waste sent to the
vendors.
Bio-medical Waste Generation
& its disposal
About 819 kg/day segregated at source & sent
to the authorized agency M/s IMAGE
Nearest town Edappal town - about 2 km away (N)
Nearest City Kozhikode city - about 60 km (NW)
Distr ict Headquarter Civi l Station, Malappuram - about 32 km (NE)
Access Road to the project
site 10 m & 8 m in the northern direction of the site.
Nearest State Highway SH-69 (Thrissur-Kuttippuram Rd.) at
(Kaladithara) about 0.7 km (E)
Nearest National Highway NH-17 (Edappally-Panvel Highway) at (at
Edappal Town) about 2 km (N)
Nearest Fire station Ponnani Fire Stat ion - about 9 km, W
Nearest Railway stat ion Kuttipuram Railway Stat ion - about 10 km (NE)
Nearest Airport Calicut Intl . Airport , Karipur - about 42 km (NW)
Nearest water bodies • Ponnani Lake - about 1 km, (NW)
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 2 Pro ject Descr ip t ion Page 2 - 3
• Drain / thodu - about 0.5 km (S)
• Beeyam Kayal - about 5 km (NW)
• Naranipuzha river - about 5.5 km (SW)
• Kolanchiri Padam - about 4 km (SW)
• Bharathapuzha - about 7 km (NW)
• Manoor Kayal - about 3 km (N)
• Lakshadweep Sea - about 9 km (SW)
• Kunthi River - about 13 km (NE)
• Valiyaparappur Thamara Kayal (Lotus lake) -
about 12 km (NW)
• Pallat kayal - about 13 km (NW)
Ecological sensit ive zones
(National Park / Wild l i fe
sanctuary / Protected areas)
None within the study area
Forest area None within the study area
Interstate boundary None within the study area
Critical ly pol luted area as
identif ied by CPCB None within the study area
Archeological Features None within the study area
Defense instal lat ions None within the study area
Climate zone Warm-Humid Zone
Seismic zone Zone-III
*Study area is 10 km radius from the project s ite. AREAS OCCUPIED BY SENSITIVE MAN-MADE LAND USES* 1. Educational Institutions
SN Name Approx.
distance & direction
1 AMLP School, Pokkarathara 800m, NW
2 GUPS, Kololamba 1.4km, SW
3 Ansar English School Kololamba 1.7km, SW
4 AMLP School Ayilakkad 2 km, NW
5 Darul Hidaya Orphanage Higher Secondary School, Edappal
1.3 km, NW
6 MH English School, Edappal 1.7km, NW
7 Janatha LP School, Alamcode 2.5km, SE
8 Irshad English School, Alamcode 2.5km, SE
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 2 Pro ject Descr ip t ion Page 2 - 4
9 Sree Narayana Central School, Changaramkulam 3.4km, SE
10 Darussalam Engl ish School, Changaramkulam 4.2km, SE
11 MVMR Higher Secondary School, Valayamkulam 5.6km, SE
12 Assabah Arts and Science Collage, Kokkur 6.1km, SE
13 Govt. Technical High School, Kokkur 6.3km, SE
14 Royal Dental College, Chal issery 7.3km, SE
15 GHSS, Kokkur 6.8km, SE
16 AMLP School, Othaloor South 6.85km, SE
17 PCNG Higher Secondary School, Mookkuthala 3.6km, SE
18 GLPS, Mookkuthala 3.6km, SE
19 LP School, Veliancode 5.6km, SW
20 Azar English medium school, Maranchery 4.8km, SW
21 GHSS , Maranchery 4.8km, SW
22 Crescent English School, Maranchery 5.3km, SW
23 Panampad School, Maranchery 4.5km, SW
24 P.N.U.P. School, Ayinichira 4.3km, NW
25 Shaikh Saeed Islamic & Arts College, Ayilakkad 2.3km, NW
26 Kamb& M Internat ional School, Ayilakkad 2.4km, NW
27 Blossom Public School, Polpakkara 4.8km, NW
28 Government Lower Primary School,Perumparamba 4.2km, NW
29 Govt. LP School, Edappal 2.8km, NW
30 GHSS Edappal 2.4km, NW
31 DarulHidaya Higher Secondary School, Edappal 1.7km, NE
32 AUPS, Verur 3.2km, N
33 VidhyaPeedam UP School, Kandanakam 5.2km, NE
34 Distr ict Insti tute of Educat ion and Training, Anakkara 6.4km, NE
35 GHSS, Anakkara 6.2km, NE
36 GHSS, Kumaranellur 5.3KM, NE
37 Govt. School, Vattamkulam 2.9km, NE
38 Technical Higher Secondary School, Vattamkulam 2km, NE
39 IHRD College of Applied Science, Vattamkulam 2km, E
40 Al-Falah AMM English School, Alamcode 2.2km, SE
41 KVUP School, Alamcode 3.2km, SE
42 Samskruthi School Kakkidippuram 3.45km, SE
43 Bharathiya Vidya Bhavan, Manoor 6.35km, SE
44 M E S School of Architecture, Thrikkannapuram 7km, NE
45 MES College of Engineering, Thrikkannapuram 7.3km, NE
46 GUPS, Tavanur 8.9km, NE
47 GUPS Vallanchery 9.6km, N
48 GHSS, Kutt ippuram 9.5km, NE
49 GVHSS, Kutt ippuram 9.4km, NE
50 Technical High School, Kuttippuram 9.4km, NE
51 NIA UP School, Kuttippuram 10.5km, NE
52 KMCT Polytechnic College, Kuttippuram 12.3km, NE
53 KMCT Law College Kutt ippuram 12.6km, NE
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 2 Pro ject Descr ip t ion Page 2 - 5
54 GHS, Kudal lur 11.1km, NE
55 Government Arts and Science College, Thrithala 12.9km, NE
56 Dr. KBMM HSS, Thrithala 12.75km, NE
57 Engl ish Medium School, Thrithala 14.5km, NE
58 Aspire College, Thrithala 14.6km, NE
59 GVHSS, Vattenad 11.9km, SE
60 GHSS, Chal issery 8.6km, SE
61 GHSS, Kadavallur 8.8km, SE
62 Ansar Women's Col lege, Perumpilavu 11.3km, SE
63 Ansar Training College, Perumpilavu 11.6km, SE
64 Ansar English Medium, Perumpilavu 11.6km, SE
65 Mar Osthatheos College, Perumpilavu 12.1km, SE
66 TM VHSS ,Perumpi lavu 12.1km, SE
67 Sree Vivekananda College, Kunnamkulam 12.4km, SE
68 St. Mary’s college, Akkikkavu 12.4km, SE
69 P.S.M. Col lege of Dental Science & Research, Akkikkavu
12.6km, SE
70 MKM UP School, Porkulam 12.5km, SE
71 GVHSS, Pazhanji 9.69km, SE
72 M D College, Pazhanji 10.7km, SE
73 Thiruvalayannur Higher Secondary School, Vadakekkad 12.3km, SW
74 GHSS, Kadikkad 10.4km, SW
75 Thaqva Afzal Ullama Arabic College, Andathode 10.4km, SW
76 KMM English School, Perumbadappu 7.2km, SW
77 GHS, Palapetty 8.8km, SW
78 AMLPS, Puthiyiruthi 8.2km, SW
79 MI Arabic College, Puthuponnani 8.5km, SW
80 MI Girls Higher Secondary School, Puthuponnani 8.6km, SW
81 MES Higher Secondary School, Ponnani 8.9km, SW
82 MES College Ponnani 8.8km, SW
83 MIHSS Ponnani 8.8km, NW
84 AV Higher Secondary School Ponnani 7.5km, NW
85 ALP School, Ponnani 7.5km, NW
86 GHSS, Thrikkavu 8.4km, NW
87 Makhdoomiyya English School Ponnani 9.3km, NW
88 TIUP School, Ponnani 9.5km, NW
89 Kelappaji College of Agricultural Engineering and Technology, Tavanur
10km, NW
90 Government Upper Primary School, Purathur 10.3km, NW
91 UP School, Padinjarekara 11.7km, NW
92 K H M Higher Secondary School, Alathiyoor 13.3km, NW
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 2 Pro ject Descr ip t ion Page 2 - 6
2. Hospitals
SN Name Approx.
distance & direction
1 Sudinaprabha Inst itute of l i festyle Diseases, Vattamkulam
550m, N
2 Prakrithe Ayurveda Hospital, Edappal 1.4km, N
3 Sukapuram Hospital, Edappal 1.5km, NE
4 Edappal Hospitals Pvt. Ltd., Edappal 1.9km, NE
5 Mother And Child Hospital, Changaramkulam 3.9km, SE
6 Sunrise Hospital, Changaramkulam 4.4km, SE
7 Alankode Govt. PHSC, Changaramkulam 4.2km, SE
8 PHC Maranchery 6.2km, SW
9 Karuna Pain and Pall iative Care, Maranchery 5.4km, SW
10 Govt. Hospital, Maranchery 5.1km, SW
11 Veterinary dispensary, Kanhiramukku 4.9km, NW
12 Govt. Hospital, Edappal 2.1km, NW
13 Family Health center, Vattamkulam 3.9km, NE
14 Amana Medical Institute Pvt Ltd, Kuttippuram 9.2km, NE
15 Shafi Ayurveda Nursing Home, Kutt ippuram 9.55km, NE
16 Taluk Hospital, Kuttippuram 10.3km, NE
17 ThithimuUmma Memorial Ayurveda Hospital, Kudallur
11.1km, NE
18 Pall ippuram Government Hospital, Parudur 13.6km, NE
19 Govt. Hospital, Thrithala 14.1km, NE
20 Modern Hospital, Koottanad 12.1km, SE
21 Govt. Hospital, Chalissery 9.4km SE
22 Ansar Hospital Perumpilavu 11.3km, SE
23 PSM Super Special ity Dental Hospital, Akkikkavu 12.55km, SE
24 Santhi Nursing Home, Punnayurkulam 9.5km, SE
25 Primary Health Center, Palappetty 9km, SE
26 TB Hospital, Ponnani 9.1km, NW
27 Women & Children Hospital, Ponnani 9.1km, NW
28 Imbichibava Memorial Taluk Hospital, Ponnani 9.3km, NW
29 CHC, Thavanur 10km, NW
3. Places of worships
SN Name Approx.
distance & direction
1 Manal iyarkave Temple, Vattamkulam 500m, E
2 Odakkuzhiyi lBagavathi Temple, Vattamkulam 740m, NE
3 Pall iyal i lMurukan Temple, Vattamkulam 860m, NE
4 Badar Masjid, Vattamkulam 1.3km, SE
5 Kalachal Masjid, Kalachal 1km, SE
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 2 Pro ject Descr ip t ion Page 2 - 7
6 NarasimhaMoorthi Temple, Alamcode 1.8km, SE
7 Panthavoor Town Juma Masjid, Alamcode 1.7km, SE
8 AryankavuBhagavathi Temple, Alamcode 3km, SE
9 Hilal Masjid Manthadam, Alamcode 3.25km, SE
10 Masj id, Changaramkulam 4.3km, SE
11 Velayattu Narasimha Moorthi Temple, Nannammukku 4.7km, SE
12 Town Masjid, Valayamkulam 5.8km, SE
13 Masj id, Kokkur 6km, SE
14 Melekkavu Bhagavathi Temple, Mookkuthala 4km, S
15 KannenkavuBhagavathy Temple, Nannammukku 4.1km, S
16 Raktheswaram Siva Temple, Nannammukku 3.4km, SW
17 Juma Masjid, Thamalassery 4.3km, SW
18 Central masjid, Panampad 4.6km, SW
19 Thonnikurumbakkavu Temple, Kanhiramukku 4.6km, W
20 Juma masjid, Kololamba 2.3km, SW
21 Kolath Vishnu Temple, Kololamba 1.4km, SE
22 Juma Masjid, Pokkarathara 0.8 km, W
23 Thali Siva Temple, Pokkarathara 1.1km, NW
24 Juma masjid, Ayilakkad 2.3km, NW
25 ThottuMugham Temple, Kanhiramukku 5.5km, NW
26 Juma masjid, Kanhiramukku 5km, NW
27 ValiyapalamJuma Masjid, Thuyyam 4.1km, NW
28 Thattanpadi Masjid 2.9km, NW
29 Kanayampath Temple, Ponnazhikkara 3.1km, NW
30 Pall iyi l Temple, Ponnazhikkara 3.7km, NW
31 JumaMusjid, Perumparamba 4.4km, NW
32 Mookambika Temple, Perumparamba 4.2km, NW
33 PorookkaraBhagavathy Temple, Ponnazhikkara 3.2km, NW
34 Masj id, Edappal 2.45km, NW
35 Masj id, Naduvattam 1km, NE
36 Mahavishnu Temple, Edappal 1.5km, NW
37 Edappal Chungam Juma Masj id 2km, NE
38 Juma Masjid, Anakkara 6km, NE
39 Potturkavu Ayyappa, Temple 5.5km, NE
40 Sukapuram Dakshinamurthy Temple, Edappal 1.9km, NE
41 Chambramanam TempleVattamkulam 1.6km, NE
42 PilakkalJuma Masjid, Vattamkulam 1.1km, NE
43 ManoorJuma masjid 6.15km, NE
44 ThrikkanapuramJuma Masjid 7.3km, NE
45 Trikkanapuram Sri Narashimhamoorthi Temple 7.4km, NE
46 Town masjid, Kutt ippuram 9.35km, NE
47 St. Joseph's Cathol ic ChurchKuttippuram 10.8km, NE
48 Town masjid Kumbidi 8.6km, NE
49 Panniyur Sri Varahamurthy Temple, Kumbidi 8.5km, NE
50 Shiva temple, Thirthala 14.4km, NE
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 2 Pro ject Descr ip t ion Page 2 - 8
51 Mulayamparambathukavu, Temple, Chalissery 10km, SE
52 St Peters & St. Pauls Orthodox Syrian Church, Chalissery
9km, SE
53 St Mary's Orthodox Syrian Church, Akkikkavu 12.3km, SE
54 Akkikkavu Bhagavathy Temple, Akkikkavu 12.3km, SE
55 Kakkad Mahaganapathi Temple, Kunnamkulam 13.4km, SE
56 St. Mary's Syrian Orthodox Cathedral, Pazhanji 9.7km, SE
57 Mannalamkunnu Juma, Masj id 12km, SW
58 St. Antony's Syro Malabar Catholic Church, Attupuram
10.8km, SW
59 Govindapuram Temple, Kadikkad 10.3km, SW
60 PuthanpallyJuma Masjid Perumbadappu 7.4km, SW
61 SreeBhagavathy Temple, Palappetty 8.6km, SW
62 Masj id Puthiyiruthi 8.4km, SW
63 Eramangalam Juma, Masjid 6.7km, SW
64 ValiyaJuma Masjid, Ponnani 9.2km, NW
4. Community facilities
SN Name Approx.
distance & direction
1 Ration Shop, Vattamkulam 0.72 km, E
2 Post off ice, Alamcode 1.7km, SE
3 Police Station, Changaramkulam 3.6km, SE
4 KSEB, Changaramkulam 3.4km, SE
5 AlamcodeGrama Panchayat Office, Changaramkulam
4km, SE
6 Malappuram District Co-operative Bank, Changaramkulam
4km, SE
7 Gramin Bank, Changaramkulam 4km, SE
8 Galaxy convention Centre, Changaramkulam 4km, SE
9 BSNL Exchange, Changaramkulam 4.6km, SE
10 Mars Cinemas, Changaramkulam 4.9km, SE
11 Post Off ice, Kokkur 6km, SE
12 Nannamukku, Vil lage off ice 3.8km, SE
13 Gramapanchayath, Nannamukku 5.5km, SE
14 Vil lage off ice, Maranchery 5.3km, SW
15 Post off ice, Maranchery 5.1km, SW
16 Panchayat Off ice, Maranchery 5km, SW
17 Federal Bank, Maranchery 4.8km, SW
18 BSNL Telephone Exchange, Maranchery 4.8km, SW
19 Mother Plaza Convention Center, Athani 4.3km, SW
20 Post off ice, Perumparamba 4km, NW
21 Vil lage off ice, Edappal 2.4km, NW
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 2 Pro ject Descr ip t ion Page 2 - 9
22 Post off ice, Edappal 2.4km, NW
23 BP Pump, Edappal 2km, NW
24 SIB,Edappal 2.2km, NE
25 SBI, Edappal 2.5km, NE
26 AEO off ice, Edappal 2.2km, NE
27 Govinda Movies, Edappal 2.65km, NE
28 Saradha theater, Edappal 2.7km, NE
29 KSEB, Edappal 3.8km, NE
30 Panchayat off ice, Vattamkulam 2.6km, NE
31 Ponnani Block Panchayat off ice 2km, NE
32 Vil lage Off ice, Vattamkulam 3.7km, NE
33 Old age Home, Tavanur 8.2km, NE
34 Central Prison, Tavanur 8.3km, NE
35 Post Off ice, Kuttippuram 9.3km, NE
36 Mini Civi l Station, Kuttippuram 9.5km, NE
37 Railway Station, Kutt ippuram 9.4km, NE
38 Fujairah Palace Auditorium, Kuttippuram 9.4km, NE
39 Police Station, Kutt ippuram 10.3km, NE
40 Aanakkara Panchayat Off ice, Kumbidi 8.6km, NE
41 Post off ice, Kumbidi 8.7km, NE
42 Thrithala Block Panchayath Off ice 12.5km, SE
43 Nagalassery Village Panchayath Off ice 12.5km, SE
44 Post Off ice, Koottanad 12.4km, SE
45 Kadavalloor Grama Panchayat Off ice 11.8km, SE
46 Porkulam Panchayat Off ice, Kunnamkulam 12.7km, SE
47 Sub Court, Kunnamkulam 13.6km, SE
48 Vil lage Off ice, Kunnamkulam 13.5km, SE
49 Police Station, Kunnamkulam 14.6km, SE
50 Municipality, Kunnamkulam 14.7km, SE
51 Post Off ice, Punnayurkulam 10.3km, SW
52 Grama Panchayat, Punnayurkulam 10.2km, SW
53 Police Station, Vadakkekkad 10.9km, SW
54 Police Station, Perumbadappu 8.1km, SW
55 Gramapanchayath, Perumbadappu 7.6km, SW
56 Post off ice, Palappetty 8.8km, SW
57 Police Station, Ponnani 8.6km, SW
58 Municipal Off ice, Ponnani 8.9km, NW
59 SBI, Ponnani 8.9km, NW
60 Mini Civi l Station, Ponnani 9.7km, NW
61 Court Ponnani 9.8km, NW
62 Harbour, Ponnani 9.9km, NW
63 Triprangode Vil lage Off ice 13.2km, NW
The site photographs of the existing campus is provided at Plate 2.1.
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 2 Pro ject Descr ip t ion Page 2 - 10
The Conceptual plan showing the salient features of the project viz.
building blocks, locat ion of ut il i t ies, landscape area, pavement area,
internal roads, entries & exits to the site, approach road to the site etc.
and the Conceptual plan of the project is provided as Figure 2.1.
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 2 Pro ject Descr ip t ion Page 2 - 11
FRONT VIEW
REAR VIEW
Plate 2.1 – Current Site Photographs
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 2 Pro ject Descr ip t ion Page 2 - 12
Figure 2.1 : Conceptual plan of the project (Source :- Project proponent)
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 2 Pro ject Descr ip t ion Page 2 - 13
2.1.1 Estimated project cost
The total project cost of the project is about Rs. 180 Crores which
includes the land, bui lding & uti l i t ies etc.
2.1.2 Employment details
The employment detai ls of the exist ing campus is given below :-
Sr.
No.
Description Nos.
1. Total no. of staff expected in the campus
(without accommodation) (l ike faculty, doctors, nurses,
group-IV staff etc.)
290
2. Total no. of staff in the campus (with family
accommodation) ( l ike faculty, doctors, nurses, group-
IV staff etc.)
81
Total 371
The employment detai ls for the new facil ity is given below :-
Sr.
No.
Description Nos.
1. Total no. of staff expected in the campus
(without accommodation)
(l ike faculty, doctors, nurses, group-IV staff etc.)
(210 medical staff & 10 maintenance staff)
220
2. Total no. of staff in the campus
(with accommodation)
(l ike faculty, doctors, nurses, group-IV staff etc.)
155
Total 375
After the proposed expansion the total employment opportunit ies will be
of about 1000 persons (371 nos. + 375 nos. = 746 say 1,000).
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 2 Pro ject Descr ip t ion Page 2 - 14
As a responsible corporate, the proponent shall comply with al l applicable
Acts related to employees’ service and their welfare of the Government of
India in terms of working hours, basic amenit ies and welfare faci l it ies
such as given below:
• Minimum Wages Act, 1948,
• Contract Labour (Regulation & Abolit ion) Act, 1970,
• Inter-State Migrant Workmen (Regulat ion of Employment & Condit ions
of Services) Act,1979,
• The Building and other Construction Workers (Regulat ion and
Employment of Service) Act, 1996,
• The Building and other construct ion workers Welfare Cess Act, 1996.
All workers and technicians wil l be provided with clean drinking water,
sheds for rest ing and sanitary facil it ies as mobile toi lets/ toi lets
connected to sewage treatment plant. Camps shall also be organized for
health check up every six months. No child shall be employed in the
process.
2.1.3 Machinery details & Building materials
The l ist of major machinery used during construction phase is given below :-
i. Dumper Shal l be used for mud and material handling
ii . Concrete mixer with hopper For RCC work
ii i . JCB Shal l be used for digging and earth work
iv. Concrete Batching Plant Will be used for concrete mixing
v. Cranes For lif t ing and moving of materials
vi. Road roller For compacting the earth
vi i . Bulldozer For dismantl ing
List of building materials to be used at site is as fol lows:
• Coarse sand
• Fine sand
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 2 Pro ject Descr ip t ion Page 2 - 15
• Stone aggregate
• Stone for masonry work
• Stone for under f loor soling
• Cement
• Reinforcement steel
• Plywood & steel shuttering
• Pipe scaffolding (cup lock system)
• Bricks
• Crazy (white marble) in grey cement
• P.V.C. conduit
• Indo-Asian MCBs
• PVC overhead water tanks
• 2 1/2'’ thick red colour paver t i les
• ‘B’ class GI pipe (ISI marked)
• PVC waste water l ines
• S.W. sewer l ine upto main sewer
• PVC rain water down take
• Stainless steel s ink in kitchen
• 5mm thick plane glass
• 3mm thick ground glass in toilets
• Joinery hardware- ISI marked
2.2 Type of project
The proposed project is a Hospital cum Medical campus project in the
name of "Sreevalsam Inst itute of Medical Sciences".
The proposed project is an expansion of building construction project. The
exist ing project was construct buildings with buil t-up area of 53,889.72
sqm and the addit ional construction of 85,047.78 sqm wil l be construct
within the exist ing campus.
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 2 Pro ject Descr ip t ion Page 2 - 16
2.3 Need for the project
Due to the rapid development in Kerala there are lots of resident ial,
commercial and off ice building construction projects are introduced and
thereby the f loat ing of populat ion from their nat ive place to their working
place / urban area is going on. Due to the high rate of populat ion shif t ing
there is an increase in burden on the infrastructure and medical faci l it ies
of an area. To accommodate the same the medical hospital with high
patient management capacity with quality services is must in every
districts of the State. In order to overcome this problem, M/s Sreevalsam
Educational Trust decide the expansion of their existing hospital cum
medical college project in Edappal Vil lage, Ponnani Taluk, Malappuram
Distr ict, Kerala.
There is an urgent requirement for the construction of hospital cum
medical col lege with associated activit ies in the area as per the faci lit ies
to be provided to the nearby people to facil itate on easy and quick
medical faci l it ies and thereby the hospital/healthcare and medical
educat ional services in a very easy way as per the needs.
2.4 Location
The project site is within the Panchayat l imits of Edappal Grama
Panchayat. The nearest town is Edappal town which is about 2 km away
(N) from the site and the nearest city is Kozhikode city and is located
about 60 km (NW). The Ponnani taluk is located about 9 km in west
direction. The route map to the project site is provided at Figure 2.2.
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 2 Pro ject Descr ip t ion Page 2 - 17
Figure 2.2 – Route map to the project site
(Source :- Google Earth) (Vintage : 2019)
Table 2.2 - Immediate site surrounding features
Direction Features existing
North Connecting road, Individual houses and others’ property
South Others’ property with coconut plantation and agricultural area
East Others’ property with coconut plantation and agricultural area
West Individual houses, others’ property with coconut plantat ion
The satel li te map showing the important environmental features within
10 km. radius of the project site is given in Figure 2.3 & Satell ite map of
the project s ite superimposed with project boundary is given in Figure 2.4.
The toposheet of the study area is given in Figure 2.5. The vicinity map
of the study area is given in Figure 2.6.
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 2 Pro ject Descr ip t ion Page 2 - 18
Fig. 2.3 Satellite map showing important environmental features within 10 km. radius
(Source :- Google Earth) (Vintage : 2011)
SN Important environmental features Aerial Distance & Direction
1. Ponnani Lake about 1 km, (NW)
2. Drain / thodu about 0.5 km (S)
3. Beeyam Kayal about 5 km (NW)
4. Naranipuzha river about 5.5 km (SW)
5. Kolanchiri Padam about 4 km (SW)
6. Bharathapuzha about 7 km (NW)
7. Manoor Kayal about 3 km (N)
8. Lakshadweep Sea about 9 km (SW)
9. SH-69 (Thrissur-Kuttippuram Rd.) (Kaladithara) about 0.7 km (E)
10. NH-17 (Edappally-Panvel Highway) (at Edappal Town) about 2 km (N)
1
2
3
4
5
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 2 Pro ject Descr ip t ion Page 2 - 19
Figure 2.4 – Satell ite image superimposed with project boundary
(Source :- Google Earth) (Vintage : 2011)
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 2 Pro ject Descr ip t ion Page 2 - 20
Figure 2.5 - Toposheet of SOI showing 10 km radius of the project site -
(Source : Extracted from Survey of India, Topo Map) (Vintage : 2011)
SN Important environmental features Aerial Distance & Direction
1. Ponnani Lake about 1 km, (NW)
2. Drain / thodu about 0.5 km (S)
3. Beeyam Kayal about 5 km (NW)
4. Naranipuzha river about 5.5 km (SW)
5. Kolanchiri Padam about 4 km (SW)
6. Bharathapuzha about 7 km (NW)
7. Manoor Kayal about 3 km (N)
8. Lakshadweep Sea about 9 km (SW)
9. SH-69 (Thrissur-Kuttippuram Rd.) (Kaladithara) about 0.7 km (E)
10. NH-17 (Edappally-Panvel Highway) (at Edappal Town) about 2 km (N)
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 2 Pro ject Descr ip t ion Page 2 - 21
Figure 2.6 - Vicinity map showing 10 km. radius of the project site
(Source :- Google Earth) (Vintage : 2011)
1
2
3
4
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 2 Pro ject Descr ip t ion Page 2 - 22
2.5 Geology
2.5.1 Regional Geology
From the exposure pattern of the rock types, the district can be divided
into two geological belts: ( i) Charnockite group of rocks covering a major
part and (i i) Migmatite Complex towards the east. Wayanad group is
represented by small bodies of metaultramafites (tal-tremolite schist, talc-
pyroxene-garnet schist, banded magnetite quartzite) and high-grade
schist and gneiss (hornblende-bioti te schist and gneiss+garnet with
amphiboli te band) which extends into Tamil Nadu where it is known as
Sathyamangalam Group. The rocks of Peninsular Gneissic Complex,
represented by granite gneiss and hornblende-biot ite gneiss, form the
next younger sequence. They have a very limited distribut ion near the
eastern boundary. They have a very l imited
distribut ion near the eastern boundary, extending into the adjacent district
where they are known as Bhawani Group. A l inear band of granite gneiss
NE of Perinthalmanna and a large body of hornblende-bioti te gneiss east
of Manjeri are prominent units. Charnockit Group includes charnockite /
charnockite gneiss, having the largest areal distr ibut ion, fol lowed in
decreasing order of abundance by banded magnetite quartzite, pyroxene
granulite, amphibolite/hornblende granul ite and pyroxenite, which occur
as concordant as well as discordant bands, lenses, layers and enclaves
both within charnockite as well as within gneisses of Migmatite Complex.
The Migmatite Complex is represented by biot ite-hornblende gneiss (or
hornblende-biot ite gneiss) and quartzo-feldspathic gneiss/garnet-bioti te
gneiss with enclaves of garnet-sil l imanite gneiss + graphite distr ibuted
mostly in the central and northeastern part. Pegmatite and quartz veins
constitute the acid intrusives, whereas gabbro and dolerite are basic
intrusives. Near the coast, isolated cappings of Neogene Warkal l i
sediments comprising grit and clay beds are noticed. Laterit isat ion is
widespread, at places attaining a thickness of more than 10m. Extensive
plateaus with later ite ‘mesas’ are common in the area. Angadipuram (west
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 2 Pro ject Descr ip t ion Page 2 - 23
of Perinthalmanna), the type locality of later ite falls in this district.
Quaternary unconsolidated sediments are restricted to the coastal plain.
They have been classif ied into dif ferent morpho-stratigraphic units based
on their l i thic content and environment of formation. Guruvayur Formation
(palaeo-marine), Periyar Formation (f luvial), Viyyam Formation (f luvio-
marine) and Kadappuram Formation (marine).
(Source - District Survey Report, Malappuram District published by Mining
& Geology Department, Govt. of Kerala).
2.5.2 Local Geology
The local geology belongs to the regional geology. The site is exist ing
hospital cum institutional buildings with coconut t rees.
2.6 Topography
This is an exist ing hospital cum medical col lege project and there are
exist ing buildings with nat ive tree species of coconut plants with other
species of shrub, herbs, grass in that area. Some of the buildings are
under construction and some of the buildings are to be proposed. As per
the topographical contour survey map, the highest level is 100 m in the
northern direct ion and lowest elevation is 88 m in the southern direction.
The drainage of the site area is towards north to south direct ion. The
topographical contour map of the project site is provided at Figure 2.7.
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 2 Pro ject Descr ip t ion Page 2 - 24
Figure 2.7 - Topographical contour map of the project site (Source :- Project proponent) (Vintage : 2011)
1
2
3
4
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 2 Pro ject Descr ip t ion Page 2 - 25
2.7 Size or Magnitude of the project
The plot area break-up detail is given at Table 2.3 below :-
Table 2.3 - Plot area break-up
Description Area (in sqm) %
Total Green Area (A) 35,308.66 (37.35%)
Ground Coverage of buildings (B) 37,813.82 (40%)
Area under roads / services (C) 21,412.08 (22.65%)
Total Plot Area (E=A+B+C) 94,534.56 (100%)
The buil t-up area break-up detai l is given at Table 2.4 below :-
Table 2.4 - Built-up area break-up
Description Area (in sqm)
FAR Area 1,10,480.22 sq.m.
Non FAR Area 28,457.28 sq.m.
Total Built-up Area 1,38,937.5 sq.m.
The building block detai l with its status of construct ion is given at table
2.5.
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 2 Project Descr ipt ion Page 2 - 26
Table 2.5 - Building block detail with its construction status
Building Block nos. & Name
Max. No. of Floors
Max. Height
Total Built-up
area (sq.m)
Status of Construction with Built-up area (sq.m)
Building permit no. & date
224/11-12 (BF + GF.)
03-11-2011
B2-224/11-12 (1,2,3&4 Floors)
27-06-2012
Hospital building B+G+5 24.45 38896 38118.08 Constructed
A5 -365/13-14 5th floor hospital
24-03-2014
Academic building G+3 15 16907.95 6594.10 Constructed
Auditorium building G+Balcony Flr
11.94 1715.95 Proposed
Doctor Quarters (total of 3 quarters)
G+8 28 10350.39
3622.63 Constructed
Staff Quarters (total of 2 quarters)
G+2 9.45 2504.44
1252.22 Constructed
Hostels (ladies & Gents hostels each)
G+2 10.35 5843.44
1168.68 Constructed
Canteen / special Residential bui lding
G+2 13.15 1026.6 1026.6 Constructed
Doctor's residence Vil las (type 1) (Total of 3 vil las)
G+1 6.45 750.03
Proposed
Doctor's residence Vil las (type 2) (Total of 8 vil las)
G+1
6.45 1566.88
Proposed
Nurses G+2 11.85 540.99 411.15
A5-365/13-14 24-03-2014
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 2 Project Descr ipt ion Page 2 - 27
accommodation / manifold room
Constructed
Non teaching staff Quarters / Electrical room
G+2
10.95 1432.52 1432.52 Constructed
Teaching hospital B+G+5 24.45 32506 Proposed
Nursing school B+G+4 19.35 22358 Proposed
Commercial complex
B+G+2 13 2210 Proposed
Laundry G 3 175.19 166.43 Constructed
Animal house G 4.6 153.12 97.23 Constructed
Total 1,38,937 53,889.72 Completed
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 2 Pro ject Descr ip t ion Page 2 - 28
2.8 Design Consideration
The project was constructed in conformity with the Kerala Municipal
Building Rules (KMBR). As per seismic zone classif icat ion, the project
site fal ls in Zone-II I. The construction of buildings structures proposed in
the existing campus wil l be designed after due study of the local
architecture.
Further, as per the google images of the site prior to the site development
in January, 2008, December, 2009, it can be observed that the site area
is with part ial ly vacant land and partially coconut plantat ion and the
google images is provided at Figure 2.8, Figure 2.9. The satel lite image
of the site area after the commencement of construction act iv ity
(December, 2012, Apri l, 2013, December, 2013 & December, 2018 &
Current image of August, 2019) is provided at Figure 2.10 to Figure 2.14.
Figure 2.8 - Time series Satellite image of the site area prior to the commencement of construction activity - January, 2008
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 2 Pro ject Descr ip t ion Page 2 - 29
Figure 2.9 - Time series Satellite image of the site area prior to the commencement of construction activity - December, 2009
Figure 2.10 - Time series Satellite image of the site area hospital block under construction - December, 2012
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 2 Pro ject Descr ip t ion Page 2 - 30
Figure 2.11 - Time series Satell ite image of the site area hospital block & non-teaching staff quarter under construction - April , 2013
Figure 2.12 - Time series Satell ite image of the site area hospital block & other buildings under construction - December, 2013
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 2 Pro ject Descr ip t ion Page 2 - 31
Figure 2.13 - Time series Satell ite image of the site area - December, 2018
Figure 2.14 - Time series Satell ite image of the site area -
Current image - August, 2019
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 2 Pro ject Descr ip t ion Page 2 - 32
2.8.1 Site History
Before the site development the si te is used as agricultural purposes and
with coconut plantat ion. There were about 100 coconut trees existing at
site which was cut for development of the site. The construct ion of the
buildings at site was done as per the building permit issued by the
Regulatory Authority i .e. Edappal Grama Panchayat.
2.9 Parking
The project would provide vehicle parking facil it ies within the project
premises. The parking plan for this project would follow KPBR guidel ines.
The total number of parking provided wil l be 1,184 Cars + 1,409
Two-wheelers within the site. There are provision of two separate wide
entry / exit point for the project for easy & smooth vehicular movement.
The suff icient parking provisions are made with the complex so that the
patient, students, vis itors & staff in hospital cum medical col lege wi ll not
disturb due to vehicular movement / parking.
The access to the project si te is from 10 m wide & 8 m wide road in the
northern direction of the site which are well connected to Thrissur-
Kutt ippuram Road located at about 1 km from the site in northern
direction.
2.10 Description of mitigation measures incorporated into the project to meet environmental standards. 2.10.1 Water supply and sewage disposal during construction phase
2.10.1.1 Source of Water during construction phase
The sources of water for construction purposes wil l be from exist ing well
water, stored rain water in pond and recycled water from existing STP.
For domestic purposes, the sources of water wil l be from well water.
There are open wel l (1 no.) and tube well (5 nos.) existing at “Sreevalsam
Institute of Medical Sciences” campus.
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 2 Pro ject Descr ip t ion Page 2 - 33
2.10.1.2 Daily Water Requirement during construction phase
The daily water requirement for construct ion activit ies is about 312 KL
(for 48 months) (1.1 KL x 85,047.78 sqm of built -up area = 93,552 KL i.e.
312 KL/day) and for meeting domestic requirement is about 27 KL
(250 workers at site, avg.) (for 48 months).
2.10.1.3 Sewage disposal during construction phase
The sewage generat ion from the labourers during construct ion phase is
expected to be about 27 KL/day which wi ll be disposed through STP
within the site. The treated water from the mobile STP wil l be used for
wetting of dust suppression and for landscaping purposes within the site.
2.10.2.1 Source of Water during operation phase
The sources of water for meeting the domestic requirement as well as
other requirements during operation phase of the proposed hospital cum
medical col lege project wil l be from exist ing wells, stored rain water and
recycled water from STP / ETP.
There are open wel l (1 no.) and tube well (5 nos.) existing at “Sreevalsam
Institute of Medical Sciences” campus.
2.10.2.2 Daily Water Requirement during operation phase
The total daily water consumption for the proposed project would be
about 1,328 KL (fresh water 677 KL + recycled water 651 KL). The f irst
day fresh water requirement is 1,328 KL and subsequent days, the daily
fresh water requirement is 677 KL. The daily domestic water consumption
is 870 KL (f lushing purposes 647 KL + non-f lushing purposes 223 KL).
Water is an essential component of the basic infrastructure for urban
sett lements. Besides domestic use, water is also required for f ire f ight ing
and other miscel laneous purposes. The occupier, patients, v is itors & staff
need water for domestic purposes and for miscellaneous purposes. The
water requirements have been calculated as per National Building Code,
2016 of India and “Manual on norms and standards for environment
clearance of large construct ion projects” by Ministry of Environment &
Forests, Govt. of India considering the requirements of water for the
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 2 Pro ject Descr ip t ion Page 2 - 34
faci l ity. The daily water consumption calculation for the project is given
below :
Operation phase – Existing Campus
Non-Flushing Requirement
Flushing Requirement
Total SN
Description
In KL / Day
1 In Patients ( No. of Beds ) = 570 Beds
( Including Laundry ) 570 x 405 Ltr. = 230.85
570 x 45 Ltr. = 25.65
256.5
2 Visitors / bye-standers inpatients = 1,140
Persons ( 2 Persons / Bed ) 1140 x 5 Ltr. = 5.70
1140 x 10 Ltr. = 11.40
17.10
3 Out Patients = 1140 Persons 1140 x 5 Ltr. = 5.70
1140 x 10 Ltr. = 11.40
17.10
4 Visitor / bye-standers with OPD patient = 1140 Persons ( 1 Person / Out Patient )
1140 x 5 Ltr. = 5.70
1140 x 10 Ltr. = 11.40
17.10
5 Total staff in the campus (without
accommodation) (like faculty, doctors, nurses, group-IV staff etc.) = 290 Persons
290 x 15 Ltr. = 4.35
290 x 30 Ltr. = 8.7
13.05
6
Total no. of staff in the campus (with family accommodation) (like faculty, doctors, nurses,
group-IV staff etc.) = 81 staff (81 staff x 5 person = 405 persons)
405 x 90 Ltr. = 36.45
405 x 45 Ltr. = 18.225
54.675
TOTAL 288.75 86.775 375.525
Operation Phase – Proposed facilities in the campus
Non-Flushing Requirement
Flushing Requirement
Total Sr. No.
Description
In KL / Day
1 In Patients ( No. of Beds ) = 600 Beds
( Including Laundry ) 600 x 405 Ltr. = 243.00
600 x 45 Ltr. = 27.00
270.00
2 Visitors / bye-standers inpatients = 1200
Persons ( 2 Persons / Bed ) 1200 x 5 Ltr. = 6.00
1200 x 10 Ltr. = 12.00
18.00
3 Out Patients = 1200 Persons 1200 x 5 Ltr. = 6.00
1200 x 10 Ltr. = 12.00
18.00
4 Visitor / bye-standers with OPD patient = 1200 Persons (1 Person / Out Patient )
1200 x 5 Ltr. = 6.00
1200 x 10 Ltr. = 12.00
18.00
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 2 Pro ject Descr ip t ion Page 2 - 35
5
Total no. of staff expected in the campus (without accommodation) (like faculty, doctors, nurses, group-IV staff etc.)
(210 medical staff & 10 maintenance staff) = 220 staff
220 x 15 Ltr. = 3.30
220 x 30 Ltr. = 6.6
9.9
6
Total no. of staff in the campus (with family accommodation) (like faculty, doctors, nurses, group-IV staff etc.) = 155 staff (155 staff x 5 person = 775 persons)
775 x 90 Ltr. = 69.75
775 x 45 Ltr. = 34.875
104.625
7 Total no. of students expected in the
campus (without accommodation facility) = 174 students
174 x 15 Ltr. = 2.61
174 x 30 Ltr. = 5.22
7.83
8 Total no. of students expected in the
campus (without accommodation facility) = 576 students
576 x 90 Ltr. = 51.84
576 x 45 Ltr. = 25.92
77.76
TOTAL 388.50 135.615 524.115
Total Water Requirement after the proposed expansion (Existing + Proposed facility)
Non-Flushing
Requirement
Flushing
Requirement Total Sr.
No. Description
In KL / Day
1. EXISTING CAMPUS 288.75 86.775 375.525
2. PROPOSED CAMPUS 388.50 135.615 524.115
TOTAL POPULATION = 10,630 Persons
(on full occupancy after the proposed
expansion) (fixed/floating)
677.26
Say 677 KL
222.39
Say 223 KL
899.64
Say 900 KL
The daily water consumption balance chart for the ent ire campus (exist ing
+ proposed faci l ity) is provided at Figure 2.15
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 2 Pro ject Descr ip t ion Page 2 - 36
Figure 2.15 - Daily water consumption balance chart
The specif ic water consumption for various purposes is worked out and is
given below:-
S.
N.
Particulars
Daily Requirement
(in KL) Sources of water
1. Domestic Water Requirement
( Non-Flushing purposes ) 647
Fresh water (Stored Rain
water and Ground water)
2. Domestic Water Requirement
( Flushing purposes ) 223 Recycled water from STP
3. Hort iculture Water Requirement 55 Recycled water from STP
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 2 Pro ject Descr ip t ion Page 2 - 37
4. Boiler water requirement 20 Recycled water from STP
4.
Make-up Water Requirement for
Cooling Towers attached with
air condit ioning system
353 Recycled water from
STP/ETP
5. Laboratory & Laundry
requirement 30
Fresh water (Stored Rain
water and Ground water)
2.10.2.3 Sewage disposal during operation phase
The sewage generat ion from the proposed hospital cum medical campus
during operation phase is expected to be about 696 KL/day which wil l be
disposed through STP within the site. The treated water from STP wil l be
used for f lushing purposes, landscaping purposes, boiler requirement and
make-up water requirement for cooling towers attached with the HVAC
system within the site.
The treatment scheme proposed for the domestic sewage is MBBR
treatment and Tertiary Treatment with UV method for disinfect ion and ultra
f i ltrat ion (UF).
The sewage treatment plant (STP) with the fol lowing treatment units:-
� Grit Chamber.
� Oil separator
� Grit chamber
� Equalizat ion tank
� Reactor
� Sett l ing tank
� Aeration tank-I
� Aeration tank-I I
� Clarif ier -I
� Clarif ier-II
� Fi lter feed tank
� PSF
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 2 Pro ject Descr ip t ion Page 2 - 38
� PCF
� Final storage tank
� Sludge holding tank
� Soak pit
� Sept ic tank
The schematic diagram of the STP is provided in Figure 2.16.
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 2 Pro ject Descr ip t ion Page 2 - 40
Figure 2.16 - Sewage Treatment Plant diagrams
The photographs of the sewage treatment plant is provided at Plate 2.2
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 2 Pro ject Descr ip t ion Page 2 - 41
Photo-1 - Existing Sewage Treatment Plant (STP)
Photo-2 - Existing Sewage Treatment Plant (STP)
Plate 2.2 - Photographs of the STP installed within the site
Also, for treatment of eff luent from the laundry & laboratory area, i t is
proposed to sett ing up of a Eff luent Treatment Plant (ETP) for an capacity
of about 33 KL capacity. The treated water from the ETP would be
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 2 Pro ject Descr ip t ion Page 2 - 42
recycled to meet the water requirement of make-up water requirement for
cooling towers attached with HVAC system.
It is proposed to install a water treatment plant of capacity consists of
pressure sand f ilter-1, iron removal f i l ter, activated carbon f i l ter, water
softener and pressure sand f il ter-2 wil l be proposed apart from other
treatment units. The water treatment plant diagram is provided in Figure
2.17.
Figure 2.17 - Water Treatment Plan diagram
2.11.1 Storm water management (surface water drainage) and rain water harvesting
During construction phase :
The storm water within the site wil l be part ial ly channelized to the rain
water storage tank. Appropriate de-sil t ing and oi l removal will be provided
so that the storm water wil l not contaminate the land and aquifer.
During operation phase :
To conserve water, rainwater storage capacity of 5,000 KL is provided at
the site. It is provided that roof rain water wi l l be directed to rain
harvest ing tanks after de-si ltation, the removal of oi l and grease through
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 2 Pro ject Descr ip t ion Page 2 - 43
a trap within site. This water wi ll be used for dai ly requirement after
suitable treatment. Excess rain water shall be lead to storm water drain
available near the site.
� The annual runoff f rom the site before site development is calculated
as fol lows :-
• Site area = 9.4534 ha = 94,534 sqm
• Annual rainfal l = 3.677 m
• Run-off co-eff icient = 0.5
• Annual runoff = 94,534 x 3.677 x 0.5
= 1,73,800 Mill ion l iters.
� After the development of the project site:-
Descript ion Ground coverage
Hard surface + Green area
Area (in sq.m.) 37,813.82 56,720.18
Annual rainfal l (in m.) 3.169 3.169
Run-off co-eff icient 0.8 0.3
Peak annual run-off (in KL) 95,865 53,924
� Total annual run-off f rom the site = 1,49,789 KL (95,865 + 53,924)
� Capacity of rain water storage tanks/pond = 5,000 KL (concurrent use and post rainy use) � After development of the site, net run-off f rom the site = 53,924 KL
� The proposed development does not affect the drainage pattern of the
site and surroundings. The topographical contour map of the site is
provided at Figure 2.7 above.
2.11.2 Solid Waste Management
Construction phase
There wil l be about 80 kg/day of municipal sol id waste will be generated
from the labourers during construct ion phase which wil l be disposed to the
exist ing bio-gas generation plant. An equivalent quantity (80 kg/day) of
other solid waste wil l be generated from the construct ion site which wil l be
disposed as per Solid Waste Management Rules, 2016. Also, Construct ion
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 2 Pro ject Descr ip t ion Page 2 - 44
& Demolit ion Waste Management Rules, 2016 will be fol lowed for handling
of waste during construct ion phase.
Operation phase
Municipal Solid waste
After the proposed expansion of hospital cum medical college campus
wi ll generate 2,093 Kg/day of sol id waste.
The Solid Waste Management Rules, 2016 wil l be fol lowed in the Solid
Waste management at the site.
Collect ion & segregation within the site (bio-degradable waste ( in green
bins), non-biodegradable waste (in blue bins) and domestic hazardous
waste (in yellow bins).
The recyclable waste like packaging material, paper etc. would be sold
through vendors. The Bio-degradable waste would be disposed through
the bio-gas generation plant to be instal led within the site. The project
has earmarked an area of about 250 sq m for storage of segregated
recyclable solid waste within the project s ite. The manure generated wil l
be ut il ized for green area development within the premises.
The photograph of the existing bio-gas generat ion plant is given at Plate
2.3.
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 2 Pro ject Descr ip t ion Page 2 - 45
Photo-1 - Exist ing Bio-gas Generat ion Plant
Photo-2 - Exist ing Bio-gas Generat ion Plant
Plate 2.3 - Photographs of the Existing Bio-gas Generation Plant instal led within the site
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 2 Pro ject Descr ip t ion Page 2 - 46
The domestic hazardous waste which includes discarded painted drums,
pest ic ide cans, CFL bulbs, tube lights, expired medicines, broken mercury
thermometers, used batteries, used needles and syringes and
contaminated gauge etc. generated at site wi ll be collected in yellow bins
and to be handed over to authorized waste pickers or waste collectors.
Bio-Medical Waste:-
� From the proposed hospital cum medical college campus, bio-medical
waste (819 Kg/day) like infectious beddings, cotton, swabs, used
syringes, discarded medicines, etc. would be generated.
� The bio-medical waste would be segregated at source by providing
appropriate colour coded bins / containers as per the colour coding
provided in the Bio-Medical Waste (Management & Handling) Rules, 2016.
About 150 sq m of area is earmarked for the storage of bio-medical waste.
� The Bio-medical waste from the existing hospital cum medical college is
outsourced through Kerala State Pollution Control Board authorized
agency (M/s Indian Medical Association Goes Eco Friendly, IMAGE) and
the same arrangement will be continued for expansion facility also. The
copy of the MoU between IMAGE & the project proponent was made and
the copy of the same is attached as Annexure No. 2.1.
Hazardous Waste :-
� As per Hazardous Waste (Management & Handling Rules), 2016, the
hazardous waste i.e., the used oil f rom D.G. sets, discarded oi l f i l ters
and discarded batteries and stored separately and wil l be disposed to
CPCB / SPCB authorized vendors only.
� Some of the approved recyclers l ike M/s Perfect Alloys, Chengannur,
M/s Peejay Enterprises, Thiruvalla, M/s Excel Petrochemicals, Kochi
and M/s Cee Jee Lubricants, Aluva are the approved recyclers for
discarded batter ies & used oi l located in Kerala.
e-WASTE :-
� Discarded computer parts, monitor, key boards etc. const itutes e-waste
and this waste wi ll be stored in an earmarked area.
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 2 Pro ject Descr ip t ion Page 2 - 47
� E-waste wi ll be generated after 4-5 years latency period. Separate
earmarked space wil l be provided for e-waste storage.
� E-waste wil l be disposed as per E Waste (Management & Handling) Rules.
2.11.3 Green Area Development
As part of the landscape development for the project, the measures to
minimize the impacts as given below:-
About 37% (35,308.66 sq.m.) of total land area is developed as part of
green belt, it is recommended that plantat ion is done along the peripheral
areas and open spaces of the project site. The roof garden is also
maintained on the terrace. This wil l help to reduce the noise levels, dust
spread and also enhances the aesthet ic value of the project site.
The l ist of tree already planted within the campus is given at table 2.6.
Table 2.4 - List of tree species already planted within the campus
Sr. No. Name of tree species Numbers
1 Palm trees 74
2 Mango trees 8
3 Ashoka trees 20
4 Graviola 35
5 Jack fruit tree 4
6 Guava tree 10
7 Coconut tree 367
8 Other trees 22
9 Banyan 3
10 Amla 4
11 Golden shrum tree 7
12 Bullet wood tree 10
13 Papaya 10
14 Catharanitur roses 25
15 Thulsi 20
16 Coleus ambolnicus 4
17 Geranium plant 15
18 Pinwheel f lower 250
19 Teale wood 12
Total 900
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 2 Pro ject Descr ip t ion Page 2 - 48
The photographs of the plant species / tree species already planted within
the campus is given at Plate 2.4.
The photographs of the road side plantat ion within the campus is given at
Plate 2.5.
Photo 1 - Bullet wood tree Photo 2 - Jack fruit tree
Photo 3 - Ashoka tree Photo 4 - Purple feabane plant
Photo 5 - Pappaya tree Photo 6 - Catharanthus Roseus
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 2 Pro ject Descr ip t ion Page 2 - 49
Photo 7 - Thulasi Photo 8 - Coleus Amboinicus
Photo 9 - Palm tree Photo 10 - Teak tree
Plate 2.4 - Photographs of the plant species / tree species already planted within the campus
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 2 Pro ject Descr ip t ion Page 2 - 50
Plate 2.5 - Photographs of the road side plantat ion within the campus
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 2 Pro ject Descr ip t ion Page 2 - 51
2.11.4 Air pollution control
Construction phase
To minimize the impact on the pat ients / occupiers in the exist ing campus,
residents in the vicinity and the ecological environment due to increase in
air pol lution levels caused by various construction activit ies and vehicular
emissions, emissions from construction equipments and D.G. sets. The
following mitigat ive measures would be adopted :-
� The construct ion site wil l be isolated from the exist ing Hospital cum
Medical College campus through wind barr iers of 30 feet height.
� No loose soil or sand or construct ion waste or any other
construction material wil l be left uncovered.
� Water sprinkling during summer days in the unpaved areas.
� Grinding and cutt ing of t i les / stones wil l be carried out in
enclosures.
� Wet jet shall be provided for gr inding, stone cutt ing and dri l l ing
areas.
� The roads within the construction site will be black top.
� Loose construction materials l ike sand, gravel wil l be stored within
earmarked area only and regular wett ing of the same. Before the
unloading of these materials, wetting wil l be carried out.
� Special care wil l be taken to avoid spil lage of loose construction
materials.
� The loose construction materials will be covered with tarpaulin
during transportation.
� The DG Set (100 kVA x 2 nos.) used wil l be with adequate stack
height as per CPCB guidel ines.
� All construction machinery wil l be in good working condit ions and
regular maintenance wi ll be ensured.
� All construction workers wi ll be provided with dust masks / PPEs.
� Ready mix concrete wi ll be used to avoid the use of loose
construction materials at s ite to reduce dust emissions.
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 2 Pro ject Descr ip t ion Page 2 - 52
Operation phase
To minimize the impact on pat ients / occupiers in the exist ing Medical
College campus and ecological environment due to increased air pollut ion
levels caused by vehicular emissions and D.G. set emissions. The
following mitigat ive measures would be adopted :-
� The stack height of DG sets (Existing - 500 kVA x 1 no. + 625 kVA x
1 no. and Proposed - 500 kVA x 1 no. + 625 kVA x 1 no.) would be
as per the CPCB standards and it would be roof of the building.
� Landscaping wil l be done with suitable nat ive species within the
earmarked site.
2.11.5 Noise pollution control & vibration
Construction phase
To minimize the impact on the pat ients in the hospital and on human
health and ecological environment in the vicinity due to increased noise
levels caused by various construction activ it ies and by vehicular
movements, construct ion equipments and D.G. set (100 kVA x 2 nos.) and
Impact on exist ing structures due to increased vibration levels caused by
operation of D.G. Sets. The following mit igat ive measures would be
adopted :-
� The construction site wil l be isolated from the exist ing buildings
through noise barriers.
� High noise generation act iv it ies wi ll not be carried out during OP
consultation hours.
� Use of D.G. Sets (100 kVA x 2 nos.) with acoust ic enclosures.
� Wind breakers / acoustic enclosures made of gunny bags f i l led with
sand or earth and stacked up to a height of about 7-8 feet at the stone
cutt ing & grinding area.
� Regular maintenance of construct ion equipments and machinery.
� All construct ion workers to be provided with PPEs.
� All construct ion / demolit ion activit ies will be restr icted to day t ime only.
� Use of ant i vibrat ion pads for the DG sets to reduce vibrat ions
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 2 Pro ject Descr ip t ion Page 2 - 53
Operation phase
To minimize the impact on the pat ients in the hospital and on human
health and ecological environment in the vicinity due to increased noise
levels caused by cooling towers and D.G. sets and Impact on structures
due to increased vibrat ion levels caused by operation of D.G. Sets. The
following mitigat ive measures would be adopted :-
� All the DG Sets (Exist ing - 500 kVA x 1 no. + 625 kVA x 1 no. and
Proposed - 500 kVA x 1 no. + 625 kVA x 1 no.) of the project s ite
are attached with acoustic enclosures and ant i v ibrat ion pads.
� The cooling towers wil l be located in an isolated area.
� Green belt development.
2.11.6 Vehicular traffic density
Vehicular traff ic density survey was carried out on 19-11-2018 on
Thrissur-Kuttippuram Road and the survey report is provided below :-
Date :- 19-11-2018 (Thrissur to Kuttippuram)
TIME Cars Two
Wheelers Three
Wheelers Buses LCV Trucks
8am – 9pm 30 24 9 8 6 17
9am – 10am 24 21 15 9 9 7
10am – 11am 15 27 10 4 18 12
11am – 12Noon 21 30 17 6 17 34
12Noon – 1pm 30 51 12 5 5 10
1pm – 2pm 15 39 19 6 6 14
2pm – 3pm 24 33 9 8 16 19
3pm – 4pm 6 39 15 9 30 21
4pm – 5pm 30 15 9 12 14 Ni l
5pm - 6pm 8 51 14 5 6 24
6pm-7pm 12 36 12 3 8 17
7pm – 8pm 12 48 15 6 8 Ni l
Total Volume 227 414 156 81 143 175
In PCU* 227 207 125 284 315 613
Date :- 19-11-2018 (Kuttippuram to Thrissur)
TIME Cars Two
Wheelers Three
Wheelers Buses LCV Trucks
8am – 9pm 34 27 29 12 7 Ni l
9am – 10am 20 29 40 10 12 7
10am – 11am 17 38 26 6 21 4
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 2 Pro ject Descr ip t ion Page 2 - 54
11am – 12Noon 18 28 28 5 24 28
12Noon – 1pm 32 44 18 8 9 34
1pm – 2pm 17 46 24 9 8 24
2pm – 3pm 20 40 28 12 19 26
3pm – 4pm 7 46 29 8 34 20
4pm – 5pm 34 24 7 17 19 11
5pm - 6pm 9 55 16 4 8 10
6pm-7pm 17 39 19 6 11 Ni l
7pm – 8pm 14 55 24 8 10 Ni l
Total Volume 239 471 288 105 182 164
In PCU* 239 236 230 368 400 574
*Values of PCU
Car 1.0
Motorcycle 0.5
LCV 2.2
Bus, Truck 3.5
3-wheeler 0.8
2.11.6.1 Interpretation
The above traff ic volume is within carrying capacity of road as per Indian
Road Congress (IRC) standards.
2.11.7 Fire Fighting System
Following provisions are required to be made according to National
Building Code 2005 with its subsequent amendments. The f ire f ighting
system has been designed considering the fol lowing codes, manual and
guidelines;
• National Building Code of India (NBC);
• Latest relevant NFPA codes, USA, in particular NFPA – 13, 14, 20 & 22;
• IRI guidelines;
• As per requirement of f ire off icer/ local f ire approving authorit ies; and
• As per Indian Standard Code for Fire Protect ion (IS Codes)
Following items are envisaged for f ire f ighting:-
• Fire-Water Connect ions;
• Firewater inlet and outlet connections shall be provided to the water
storage tanks;
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 2 Pro ject Descr ip t ion Page 2 - 55
• External main f ire ring, having 150 mm diameter and hydrants @ 45
m3 /s spacing shall be provided. This external f ire ring shall be
separated from the Sprinkler Main Systems;
• All f low switches, test valves, drain pipes etc. shal l be provided as per
NFPA guidelines on the sprinkler system;
• All pump instal lat ion and arrangements shall be in accordance with IRI
guidelines and NFPA-20;
• All pumps and accessories and electrical controllers shall be as per
UL/FM l ists, tested, approved and certi f ied; and
• By-pass arrangements shal l to be provided (150 mm diameter nominal
bore) with NRV and gate valve and bulk f low meter on the discharge
header of each pump to check the duties of pumps.
The f ire extinguishers provided should be in conformance with Ozone
Deplet ing Substances (Regulat ion and Control) Rules.
2.11.8 Project implementation schedule
The proposed project is an expansion of the existing hospital cum medical
college building construct ion project and the total implementation /
completion period for the construction is about 48 months from the start of
the construction. To achieve a t imely completion of the project
construction the project proponent fol lowed the construction schedule of
the project.
*******************************************************************************
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 3 Description of the Environment
Page 3 - 1
3.0 DESCRIPTION OF THE ENVIRONMENT
3.1 Introduction / Approach
The objective of Environmental Impact Assessment (EIA) is to ascertain
the baseline environmental condit ions and then assess the impacts as a
result of the present development project during operation phases of the
project cycle. Identif ication of environmental parameters, data collection
and impacts prediction form the core of Environmental Assessment
process. The baseline information is required to know the current
environment condit ion in relation with (a) land (b) air (c) noise (d) water
(e) biological (f) Socio-economic (g) solid waste and (h) traff ic
management from the site where existing project is established.
3.2 Study Area , Period, Components
3.2.1 Study Area
As specif ically mentioned in EIA Noti f ication and as wel l as on the basis
of "Environmental Impact Assessment Guidance Manual for Building,
construction, township and Area Development Projects" published by
Ministry of Environment & Forests, February, 2010, for carrying out an
EIA study of a bui lding construct ion project, the project area is called as
"core zone" and 10 km radius from the boundary l imits of the project area
is called as "buffer zone". The study area includes the "core zone" and
"buffer zone".
The project site is within the Panchayat l imits of Edappal Grama
Panchayat and is about 2 km away from Edappal Town.
3.2.2 Study period
The study period was November & December, 2018 which is other than
the monsoon season. The samples were collected and analysed for
various parameters through an National Accredited Board for Laboratories
(NABL), accredited laboratory and also by the ecological & social experts
approved by QCI/NABET.
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 3 Description of the Environment
Page 3 - 2
3.2.3 Components of Study
The environmental baseline study includes inventory of physical,
ecological and socio-economic parameters. The data has been compiled
for the following :
• Air Environment: air qual ity with respect to signif icant parameters,
• Noise Environment: noise levels covering resident ial , commercial,
industrial and sensit ive zones,
• Land Environment: land use / land cover, topography, drainage
pattern, geology and soil characterist ics,
• Water Environment: water consumption and sources, ground water,
surface water, characterist ics.
• Ecological Environment: ident if ication and enumeration of f lora &
fauna (terrestr ial and aquatic) and analysis of its importances to the
habitat of the study area.
• Socio-Economic Environment: demography, amenities, infrastructural
faci l it ies, employment and income, public health, including the support
the area could provide to the proposed project.
3.2.4 Sampling, Frequency & Method of Baseline Environment Monitoring
The Environmental attributes of the baseline monitoring is provided in
table 3.1.
Table 3.1 - Environmental Attributes
Attributes Sampling Measurement
Method
A. Air Environment Network Frequency
Meteorological � Temperature � Rainfal l � Wind (velocity &
direction)
Based on the IMD data of
Thiruvananthapuram (Secondary data)
Once
Pollutants � PM1 0
� PM2 .5
� SO2
� NO2
� CO
� One in project site
� One in upwind direction
� Two in downwind direction
� One in sensit ive receptors
24 hourly Twice a
week
As per CPCB guidelines
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 3 Description of the Environment
Page 3 - 3
B. Noise � Hourly equivalent noise
levels
� One in project site
� One in upwind direction
� Two in downwind direction
� One in sensit ive receptors
Once in month for
each location
Noise level meter
C. Water
Parameters for water quality (Ground water) � pH � Total Dissolved Solids � Total Hardness (as
CaCO3) � Chloride (as Cl) � Total Suspended Solids � Lead (as Pb) � Fluoride (as F) � Total Coliform Bacteria � E Coli Parameters for water quality (Surface water) � pH � Chemical Oxygen
Demand � Biochemical Oxygen
Demand (3 days at 270C) � Dissolved Oxygen � Total Coliform Bacteria � E Coli
Set of grab samples for ground
(Bore well ) and surface water (Ayarichira)
Once in season for
each location
Samples for water quality is collected
and analysed as per IS:
10500
D. Land Environment
Soil � pH � Conductivity � Total Kjeldahl Nitrogen
(as N) � Available Potassium � Total Phosphorous (as P)
Sample collected for core zone
One in season
Collected and analysed as
per soil analysis
reference
E. Ecological Environment � Flora Fauna Enumeration
and Biodiversity
Within the core zone
One season
F. Socio-economic Environment � Socio-economic survey, � Need assessment survey
Within the buffer zone.
One season
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 3 Description of the Environment
Page 3 - 4
3.3 Mateorological parameters :
3.3.1 Temperature
The cl imate is generally hot and humid. March and Apri l months are the
hottest and January and February months are the coldest. The maximum
temperatures ranges from 28.9 to 36.2°C and the minimum temperatures
range from 17.0 to 23.4°C. The temperature starts r ising from January
and reaches the peak in the month of March and Apri l and then decreases
during the monsoon month and again rising from September onwards.
3.3.2 Rainfall
The distr ict has more or less the same climatic condit ions prevalent
elsewhere in the State viz. dry season from December to February and
hot season from March to May, the South-West monsoon from June to
September and the North-East monsoon from October to December. The
normal rainfal l of the district is 2793.3 mm. Out of this, major rainfal l
contr ibution is from SW monsoon fol lowed by the NE monsoon. The South
West monsoon is usually very heavy and nearly 73.5% of the rainfall is
received during this season. NE monsoon contr ibutes nearly 16.4% and
March to May summer rain contributes nearly 9.9% and the balance 0.2%
is accounted for during January and February months.
3.3.3 Humidity
The relative humidity ranges from 84 to 94 % during morning hours. The
humidity is more during the peak monsoon months from June to
September.
3.3.4 Wind
The wind is predominant from east as well as west during morning and
evening hours. The wind speed is more during December to February
months. It ranges from 2.9 to 7.2 km per hour.
(Source & vintage : Ground Water Information Booklet, Malappuram District, 2013) (for temperature, rainfall & wind data)
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 3 Description of the Environment
Page 3 - 5
3.3.4.1 Wind Rose Diagram
The wind rose diagram was prepared to analysed the predominent wind
direction at the project site. The wind rose diagram was prepared during
the period of November 1 to November 30, 2018. The wind rose diagram
is provided as Figure 3.1. The frequency distribution of Wind Speeds and
Wind Direct ions is provided at Table 3.2.
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 3 Description of the Environment
Page 3 - 6
Figure 3.1 : Wind Rose Diagram of the project site
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 3 Description of the Environment
Page 3 - 7
Table 3.2 - Frequency Distribution of Wind Speeds and Wind Directions
SN Wind Directions 0 - 5 5 - 10 10 - 15 >= 15 Total (%)
1 N 0.97 3.62 2.36 0.42 7.37
2 NNE 0.56 2.36 3.62 0.00 6.54
3 NE 0.14 1.67 0.97 0.00 2.78
4 ENE 0.00 1.53 0.70 0.00 2.23
5 E 0.00 1.11 0.00 0.00 1.11
6 ESE 0.14 0.83 0.00 0.00 0.97
7 SE 0.28 1.95 0.56 0.00 2.78
8 SSE 0.70 5.56 1.81 0.70 8.76
9 S 1.11 6.26 4.31 3.48 15.16
10 SSW 0.70 7.09 2.09 2.92 12.80
11 SW 0.28 4.45 2.64 1.67 9.04
12 WSW 0.70 4.45 0.97 1.25 7.37
13 W 0.56 4.73 0.83 0.97 7.09
14 WNW 0.14 4.45 1.11 0.97 6.68
15 NW 0.14 3.34 0.97 0.28 4.73
16 NNW 0.42 2.78 1.11 0.28 4.59
Sub-Total 6.82 56.19 24.06 12.93 100.00
Monitoring period: November 1 to November 30, 2018
3.3.4.2 Inference
As per the wind rose diagram, the pre-dominent wind direct ion is from
south direct ion.
3.4 Air Environment
3.4.1 Introduction
The exist ing ambient air quali ty of the project area is very important for
evaluating the impact of the construct ion act ivit ies on air environment.
3.4.2 Selection and number of sampling locations for Ambient Air Quality monitoring as per CPCB norms :
As per CPCB Guidelines for Ambient Air Qual ity Monitor ing for sett ing up
of any ambient air qual ity monitor ing station, the most important thing to
be considered prior to the commencement of actual monitoring is to
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 3 Description of the Environment
Page 3 - 8
collect background information about sources of Emissions and
Meteorological condit ions of the study area.
Number of monitoring stations : The number of monitoring stat ions is
selected based on the background information collected on sources and
emissions, populat ion f igures which can be used as indicators of region
variabil ity of the pollutants concentrat ion as given in CPCB guidelines.
Selection of locations for ambient air quality monitoring
The study of baseline status of air environment includes reconnaissance,
select ion of monitoring locat ions was considered based on meteriological
condit ions, as per the elevation / topographic profi le as well as nearest
IMD station. The wind rose was drawn for the select ion of monitoiring
location considering the meteorological station covering the study area.
The monitoring and concentrat ion levels of specif ic air quality parameters
were carried out to assess the status of existing ambient air quality in the
study area.
Sampling locations were selected, one in the project site, one in upwind
direction, two in downwind direct ions, one in sensit ive receptor.
The Ambient Air Quality monitoring locat ions are l isted in Table 3.3 and the
map showing the locat ions is provided Figure 3.2.
For ambient air quali ty monitoring, the services of M/s Standard
Laboratory, Kochi (a NABL accredited laboratory) was taken.
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 3 Description of the Environment
Page 3 - 9
Table 3.3 : Ambient Air Monitoring Locations
Sr. No.
Location Station Code
Distance & Direction from the
project site
Zone (core / buffer)
Remarks
1. Project Site AAQ1 ---- Core Within the site
2. Near Vallyad Mosque
AAQ2 2 km (SW) Buffer Sensit ive receptor
3. Near Kololamba Rural Co-operat ive Society
AAQ 3 1.5 km (SW) Buffer Upwind direction
4. Near Amana Mall, Edappal
AAQ 4 2 km (N) Buffer Downwind direction
5. Near Badar Mosque, Nel liserry
AAQ 5 2.5 km (NE) Buffer Downwind direction
Figure 3.2 - Location map of Ambient Air Quality Monitoring Station
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 3 Description of the Environment
Page 3 - 10
Sampling methodology followed for Ambient Air Quality monitoring as per CPCB norms :
1. Ambient air quali ty sampl ing was done as per CPCB / NABL
guidelines.
2. High volume sampler Inlet height was kept minimum 3 mtr above
ground level.
3. Sampler was kept suff icient ly away from any obstructions l ike building
or trees etc.
4. Sampl ing f low rate of about 1.1 cu m/min. is maintained.
5. Init ial and f inal weight of two f i lter papers are included in the report.
6. Field data collected was reported in the attached data sheet along with
monitoring report.
7. Field sampling dates were informed well in advance to depute experts
at site during the f ield sampling / measurement.
8. Hourly reading of f low rate & rota meter % was taken during the
sampl ing.
9. Laboratory analysis of the sample was done as per the CPCB / NABL
guidelines with the properly cal ibrated instruments only and calibrat ion
chart was provided for the instruments used.
10. Trained & competent manpower with adequate numbers was provided
on site for sampling.
3.4.3 Sampling and Analysis results
The ambient air samples were collected in presence of the functional area
expert (AP) and analysed by NABL accredited laboratory, the results are
given in Table 3.4.
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 3 Description of the Environment
Page 3 - 11
Table 3.4 : Ambient Air Quality Monitoring Results
PM10 ( µg/m3 )
Monitoring stations (R,I ,S)
Category of station
Maximum Minimum
Core Zone AAQ1 67.2 59.8
Sensit ive receptor AAQ2 49.2 42.8
Upwind direct ion AAQ3 78.3 69.8
Downwind direction AAQ4 80.6 74.5
Downwind direction AAQ5 54.1 48.6
PM2 .5 ( µg/m3 )
Monitoring stations (R,I ,S)
Category of station
Maximum Minimum
Core Zone AAQ1 25.3 23.1
Sensit ive receptor AAQ2 21.3 19.8
Upwind direct ion AAQ3 41.9 38.7
Downwind direction AAQ4 43.5 40.6
Downwind direction AAQ5 23.6 20.6 SO2 ( µg/m3 )
Monitoring stations (R,I ,S)
Category of station
Maximum Minimum
Core Zone AAQ1 <2.00 <2.00
Sensit ive receptor AAQ2 <2.00 <2.00
Upwind direct ion AAQ3 <2.00 <2.00
Downwind direction AAQ4 <2.00 <2.00
Downwind direction AAQ5 <2.00 <2.00 NO2 ( µg/m3 )
Monitoring stations (R,I ,S)
Category of station
Maximum Minimum
Core Zone AAQ1 4.26 2.80
Sensit ive receptor AAQ2 3.2 2.16
Upwind direct ion AAQ3 3.57 2.67
Downwind direction AAQ4 4.91 3.27
Downwind direction AAQ5 5.14 3.14
CO ( mg/m3 )
Monitoring stations (R,I ,S)
Category of station
Maximum Minimum
Core Zone AAQ1 2.63 1.49
Sensit ive receptor AAQ2 2.75 1.49
Upwind direct ion AAQ3 3.12 2.64
Downwind direction AAQ4 3.96 2.15
Downwind direction AAQ5 2.40 1.83
*R : Residential area *I : Industrial Area *S : Senstive area
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 3 Description of the Environment
Page 3 - 12
The analysis reports of all ambient air quality stations is provided at
Annexure No. 3.1.
Table 3.5 : National Ambient Air Quality Standards
Parameters Standards
PM1 0 100 µg/m3
PM2 .5 60 µg/m3
SO2 80 µg/m3
NO2 80 µg/m3
CO 4 mg/m3 3.4.4 Ambient Air Quality Index
The baseline ambient air quality results & air quality index is givne at
Table 3.6 .
Table 3.6 - Baseline ambient air quality results & air quality index
Pollutant Value (µg/m3)
Permissible Limits
(µg/m3)
Air Quali ty Index
PM10 80.6 100 Good
PM2 .5 43.5 60 Good
SO2 <2.00 80 Good
NO2 5.14 80 Good
CO 3.96 4 Good
3.4.5 Inference
All the analyzed values of all parameters are well within the National
Ambient Air Quality Standards.
3.5 Noise Environment
3.5.1 Introduction
The noise level monitoring in the study area is carried out at sensit ive
receptors l ike mosque, Cooperat ive Society off ice, Shopping mall within 1
to 2.5 km area. The monitor ing is done on hourly equivalent noise levels
in the study area. The sound level monitor ing data is presented below.
3.5.2 Protocols followed for Ambient Noise Level Monitoring & methodology
1. The microphone of instrument was kept clean & free from any dust.
2. The equipment used was properly calibrated and calibration status of
equipment to be used for monitoring.
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 3 Description of the Environment
Page 3 - 13
3. The CPCB methodology was used for monitoring.
4. Only Type-II noise level monitor ing instrument (Sound level meter) was
used for monitor ing.
5. The laboratory personnel were competent to carryout spot calibrat ion.
6. The f ield sampling dates were informed well in advance to depute
experts at site during the f ield measurement.
7. Trained & competent manpower with adequate numbers were provided
on site for f ield measurement.
The Ambient Noise level locations are listed in Table 3.7 and the map
showing the locat ions is provided Figure 3.3.
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 3 Description of the Environment
Page 3 - 14
Table 3.7 : Ambient Noise Monitoring Locations
Sr. No.
Location Station Code
Distance & Direction from the
project site
Zone (core / buffer)
Remarks
1. Project Site N1 ---- Core Within the site
2. Near Vallyad Mosque
N2 2 km (SW) Buffer Sensit ive receptor
3. Near Kololamba Rural Co-operat ive Society
N3 1.5 km (SW) Buffer Upwind direction
4. Near Amana Mall, Edappal
N4 2 km (N) Buffer Downwind direction
5. Near Badar Mosque, Nel liserry
N5 2.5 km (NE) Buffer Downwind direction
Figure 3.3 - Location of Ambient Noise Level Monitoring Stations
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 3 Description of the Environment
Page 3 - 15
3.5.3 Ambient Noise levels results
The ambient Noise level samples were collected in presence of the
funct ional area experts (noise) and analysed by NABL accredited
laboratory, the results are given in Table 3.8.
Table 3.8 : Ambient Noise Monitoring Results
S. N.
Location Environmental
Setting*
Day time Average
noise level (dBA)
Night time Average
noise level (dBA)
1. Project Site Project site (core zone)
50.1 37.7
2. Near Vallyad Mosque Buffer area 49.1 38.0
3. Near Kololamba Rural Co-operative Society
Buffer area 48.7 36.9
4. Near Amana Mall, Edappal
Buffer area 50.4 38.6
5. Near Badar Mosque, Nelliserry
Buffer area 49.3 37.9
*Industrial Area / Commercial Area / Residential area / Silence Zone
The analysis report of all ambient noise level stat ions is provided at
Annexure No. 3.2.
Table 3.9 : National Ambient Noise Level Standards
Area Code
Category of Area Limits in dB (A) Leq
Day time Night Time
A Industr ial Area 75 70
B Commercial Area 65 55
C Resident ial area 55 45
D Silence Zone 50 40
3.5.4 Inference
The analyzed results of Noise levels are given in the above table, and it
can be observed from the results that the noise values are much below
the prescribed l imits for Industrial, Commercial, Resident ial, and Silence
zone. Proposed project are not l ikely to cause any increase in 'noise'
levels at the monitoring locat ions (sensit ive receptors) which are located
more than a ki lometer away from the project s ite.
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 3 Description of the Environment
Page 3 - 16
3.6 Land Environment
3.6.1 Introduction
Since the building construction project have excavation of earth, removal
of top soi l and disturbance of land result in the land environment wil l
af fected.
3.6.2 Land use / land cover
The exist ing land use / land cover pattern in the study area for a 10 km
radius from the project site is developed and is provided at Figure 3.4 and
Table 3.10.
Table 3.10 - Land Use / Land Cover Classification System
Land Use Class Area (in Sq km)
Wetland 5.49
Plantation 198.9818
Reservoir/Lakes/Ponds 0.0628
River/Stream / Canals 22.2312
Rural Area 1.691
Sandy Area 3.3598
Scrub land 3.9564
Urban 4.02
Cropland 74.575
Fallow land 0.2512
3.6.2.1 Interpretation
As per the Land Use / Land Cover Classif icat ion System, the exist ing land
use within the buffer zone is about 63% of the land is Plantation area,
about 7% land is River/Stream / Canal and about 24% of the land is Crop
land and remaining land is covered with other land use / land cover. The
soil in core area is not good in nutrients values and not productive from
agriculture view point.
Proposed project is an expansion of exist ing hospital cum medical col lege
project and new buildings wil l be construct ing within the exit ing plot area.
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 3 Description of the Environment
Page 3 - 17
Therefore, the land use / land cover of study area is not l ikely to get
affected adversely due to proposed project.
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 3 Description of the Environment
Page 3 - 18
Figure 3.4 - Land use map of the project site (2004-05) (10 km. radius)
Source :- Thematic Map from Bhuvan Indian Geo-Platform of ISRO, Govt. of India
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 3 Description of the Environment
Page 3 - 19
3.6.3 Soil
3.6.3.1 Introduction
Since the building construction project have excavation of earth, removal
of top soil and disturbance of nutr ients of the soi l result in the soil quality
wi ll af fected.
3.6.3.2 Protocols for Soil sampling methodology
The soil sample is collected from the core zone since the project is not
l ikely to affect the land use outside core zone. Samples are col lected
through hand auger boring upto a depth of 15 to 30 cm.
The locat ion of soi l sampling points are presented in Table 3.11.
Table 3.11 - Soil Sampling Locations
Station
no.
Location Distance & Direction
from project area
Project area /
Study area
1. Within the project
area
Within the project area Project area
(Core Zone)
3.6.3.3 Soil sampling results
The soil sample was collected in presence of the functional area experts
and analysed by NABL accredited laboratory, twice during November,
2018 the results are given in Table 3.12.
Table 3.12 - Chemical Properties of Soil Sample
Sr.
No. Parameters Unit
Samples
Core Zone
1. pH -- 6.18
2. Conductivity µS/cm 36.0
3. Total Kjeldahl Nitrogen (as N) % 0.16
4. Available Potassium % 0.09
5. Total Phosphorous (as P) % 0.22
The analysis report of soil sampling stat ion is provided at
Annexure No. 3.3.
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 3 Description of the Environment
Page 3 - 20
3.6.3.4 Interpretation
The soil in core area is not good in nutrients values and not productive
from agriculture view point.
3.7 Water Environment
3.7.1 Introduction
For the purposes of construction of building and associated act ivit ies are
required huge quantity of water for various purposes and also affect the
hydrological regime of the area. The water quality of the region is also
likely to get affected through runoff and leachate. Therefore, baseline
information on ground and surface water regime is very important. Water
availabil ity and water qual ity are the two major aspects to be considered
for baseline status of water environment.
3.7.2 Water consumption and sources
The specif ic water consumption for various purposes is worked out and is
given in table 3.13.
Table 3.13 - Water consumption details for various purposes
S. N.
Particulars
Daily Requirement
(in KL) Sources of water
1. Domestic Water Requirement
( Non-Flushing purposes ) 647
Fresh water (Stored Rain
water and Ground water)
2. Domestic Water Requirement
( Flushing purposes ) 223 Recycled water from STP
3. Hort iculture Water Requirement 55 Recycled water from STP
4. Boiler water requirement 20 Recycled water from STP
4.
Make-up Water Requirement for
Cooling Towers attached with
air condit ioning system
353 Recycled water from
STP/ETP
5. Laboratory & Laundry
requirement 30
Fresh water (Stored Rain
water and Ground water)
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 3 Description of the Environment
Page 3 - 21
3.7.3 Ground Water
3.7.3.1 Ground water table identification
The pre-construction soil invest igat ion has been carr ied out (M/s
Associated Bore Tech, Ernakulam) during November, December, 2013 at
the site. The soil investigat ion report is attached at Annexure No. 3.4. I t
is observed that the ground water level is encountered about 1 m from the
exist ing ground level.
As per the Ground Water information Booklet, CGWB on the stage of
ground water development and the long term trend of water levels, 3
blocks namely Kondotty, Tirurangadi and Vengara have been categorized
as ‘Semi-Crit ical ’ and the remaining blocks are categorized as ‘Safe ’ . The
proposed project area is located within the Ponnani block which is
categorized as 'Safe' zone.
The categorizat ion of blocks of Malappuram district is provided in Figure 3.5.
Figure 3.5 - Categorizationof blocks of Malappuram distr ict
(Source : Ground Water information Booklet, CGWB) (Vintage : Dec., 2013)
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 3 Description of the Environment
Page 3 - 22
3.7.3.2 Interpretation
As per the Ground Water information Booklet, CGWB, the proposed
project is categorized as 'Safe' zone and hence the ground water
available in the region is ensure and to use of domestic purposes.
3.7.3.3 Protocols for Water sampling methodology
Sampling Methodolgy:
• Sampling of water was done as per CPCB/NABL guidel ines.
• CPCB guidel ines followed for locat ion identif icat ion
The guidelines / protocols fol lowed in the water sample collection,
preservation & transporation is discussed below :-
Surface Water Sampling
• Ensuring the water samples collected from well-mixed section of the
water body 30 cm. below the water surface using a water sampler.
(Nishkin type).
• DO is determined in a sample collected in a DO bott le. The DO in the
sample was f ixed immediately after collect ion, f ixing chemical reagents.
DO concentrat ion was then determined in the laboratory.
Ground Water Sampling
• Samples for groundwater qual ity monitoring was collected from the
following types of wel l:
� Open dug wel l
• The open dug well, which is in use in the site considered as water
quality monitoring station.
• The weighted sample bott le was used to collect sample from an open
well about 30 cm below the surface of the water.
• For bacteriological samples, when collected from tube-wells/hand
pump, the spout/outlet of the pump was steri l ized under f lame by spir it
lamp before collect ion of sample in container.
Sample Labelling Guidelines:-
The label of the sample container was properly, preferably attached
with a water-proof label. Information on the sample container includes:
• Sample code number ( identifying locat ion)
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 3 Description of the Environment
Page 3 - 23
• Date and time of sampling
• Source and type of sample
• Pre-treatment or preservat ion carried out on the sample
• Any special notes for the analyst
• Sampler’s name
Sample Preservation and Transport
• The samples collected for BOD and bacteriological analyses should be
stored at a temperature below 4oC and in the dark as soon as possible
after sampling. In the f ield this usually means placing them in an
insulated cool box together with ice or cold packs.
• Once the samples were collected and brought to the laboratory,
samples were transferred to a refrigerator. Samples collected for
chemical oxygen demand (COD) analysis were analyzed on the day of
collection, after preserving below pH2 by addit ion of concentrated
sulphuric acid.
• The samples which were to be analyzed for the presence of metals,
were acidif ied to below pH2 with concentrated nitr ic acid.
• The samples were transported to concened laboratory as soonas
possible, preferably within 48 hours.
• The analysis of bacteriological samples were analysed within 24 hours
of col lection.
The water sampling locat ions (ground water & surface water) are listed in
Table 3.14 & Table 3.15. The water sampling location map is given in
Figure 3.6.
Table 3.14 - Description of Ground Water Sampling Location
Station
no.
Location Distance &
Direction from
project area
Project area
/ study area
Environmental
Setting
1. Within the
project site
- Project area Bore well within
the exist ing
campus
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 3 Description of the Environment
Page 3 - 24
Table 3.15 - Description of Surface Water Sampling Location
Station
no.
Location Distance &
Direction from
project area
Project
area /
study area
Environmental
Setting
1. Ayarichira
(Water
body)
about 3 km (W) and
downstream
Study area Surface water
Figure 3.6 - Water Sampling Location Map
3.7.4 Water sampling results
The water sampling are collected from ground water (Bore well) within the
exist ing campus and surface water from Ayinichira within the study area.
The ground water analysis results are given below at table 3.16. Also, the
surface water (Ayarichira) analysis results are given below at table 3.17.
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 3 Description of the Environment
Page 3 - 25
Table 3.16 - Analysis of Ground Water (Open well) Results
Sr.
No. Parameters Unit Result Standards
1 pH -- 6.28 6.50 - 8.50
2 Total Dissolved
Solids
mg/L 872 500 (max)
3 Total Hardness (as
CaCO3)
mg/L 366 200 (max)
4 Chloride (as Cl) mg/L 426 250 (max)
5 Total Suspended
Solids
mg/L 10.60 --
6 Lead (as Pb) mg/L <0.01 0.01 (max)
7 Fluoride (as F) mg/L 0.48 1.00 (max)
8 Total Coliform
Bacteria
-- Absent/100 ml Absent/100 ml
9 E Coli -- Absent/100 ml Absent/100 ml
The analysis report of water sampling station (ground water) (bore well) is
provided at Annexure No. 3.5.
Table 3.17 - Analysis of Surface Water (Ayarichira)
Sr.
No. Parameters Unit Result
1 pH -- 6.88
2 Chemical Oxygen Demand mg/L 312
3 Biochemical Oxygen Demand
(3 days at 270 C)
mg/L 3.00
4 Dissolved Oxygen mg/L 8.13
5 Total Coliform Bacteria -- Present/100 ml
6 E col i -- Absent/100 ml
The analysis report of water sampling station (Surface water - Ayarichira)
is provided at Annexure No. 3.6.
3.7.5 Interpretation of results
Ground Water
All the parameters except pH level, i ron content, hardness, chlor ides are
within the standards as per IS:10500 (Ground Water - Bore well). It is
recommended that appropriate treatment wil l be done before its
consumption for domestic purposes.
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 3 Description of the Environment
Page 3 - 26
The present project is an expansion of existing hospital cum medical
college campus. The construction of new buildings are within the exist ing
plot area.
The excavation of earthwork wil l be done for the foundation of structures.
The total excavated of earth is 7,300 cum. The top soi l (730 cum) which is
fert i le wil l be kept at site for landscaping work. Part of the excavated soi l
wi ll be used for back f i l l ing work (4,380 cum) for site level ing and the
remaining quantity of 2190 cum will be used for internal road construct ion
work.
3.8 Ecological Environment
3.8.1 Introduction
The construction activity affects the terrestrial ecological environment.
Therefore, a primary survey on the ecological assessment of the site
(f lora and fauna) is required to be carr ied out.
3.8.2 Methodology
Flora
The study on the f loral assessment for the proposed project act ivity was
based on extensive f ield survey of the area.
The Qualitat ive Assessment was done by transect method covering the
entire area in to Grids of 90m x 90m. From the total grids, 12 grids were
selected at random and, the density, dominance and frequency were
calculated by using quadrate method. The quadrate method includes lying
down of a square sample plot of suitable size for detailed analysis of
vegetat ion. It may be a single sample plot or may be divided into several
subplots. Quadrates of 20m x 20m, 5m x5m and 1m x1m were used for
trees, shrubs and herbaceous communities respectively.
Co-existence and competit ion amongst various species are affected
directly by the number of individuals in the community. Therefore,
knowing the quantitat ive structure of the community becomes essential.
Various diversity indices including Shannon-Weaver (1963) Index of
Diversity give a comparat ive and quantitative picture of the community
exist ing in the study area.
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 3 Description of the Environment
Page 3 - 27
Fauna
Birds, Butterf l ies, Dragon Fl ies: Line Transect & Point count method
Mammals: Line Transect method, Consultat ion with local people
Amphibians: Transect and Patch Sampling
Spiders: Searching and Direct Observat ions
3.8.3 Findings
Flora
Analysis of the f lora revealed that, in the proposed project site there are
90 plant species fal l ing under 48 plant families. Angiosperms forms 86
species with 25 species of trees including saplings, 18 species of shrubs,
28 species of herbs and 15 species of cl imbers. There are four
Pteridophytes (ferns) fal l ing under three famil ies. The Site has 90 species
of plants. I t consists of:
Trees : 25 species
Tree saplings : 18 species
Shrubs : 18 species
Herbs : 28 species
Cl imbers : 15 species
Ferns : 4 species
The l ist of f loral species (trees, tree sapl ings, shrubs, herbs, cl imbers,
ferns) observed in the site area is provided at table 3.18.
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 3 Description of the Environment
Page 3 - 28
Table 3.18 - List of floral species observed in the site area (trees, tree saplings, shrubs, herbs, climbers, ferns)
List of trees
SN Botanical Name Common Name Family Habitat Distribution Nos. Status
1 Saraca asoca Ashokam Fabaceae Evergreen forests. Also
grown as ornamental. 4
2 Mimusops elengi
L.
Elenji/ Asian
bullet wood Sapotaceae
Semi evergreen and
evergreen forest, also
grown in homestead
Indo-Malaysia 3
3 Anacardium
occidentale L. Kasumavu Anacardiaceae Cultivated
Native of South America;
now widely cultivated in
Asia and Africa
6 Exotic
4 Ficus racemosa L. Aththi Moraceae
Semi-evergreen and
deciduous forests, also in
the plains
Indo-Malesia to Australia 1
5 Trema orientalis
(L.) Bl. Pottaama Ulmaceae
Dry and moist deciduous
forests, also in the plains 21
6 Ficus hispida L.f.
Erumanakku/
Parakam/
Thonditherakam
Moraceae
Moist deciduous and
semi-evergreen forests,
also in the plains
Indo-Malesia to Australia 38
7 Morinda coreia
Buch.-Ham. Manjanathi Rubiaceae
Moist and dry deciduous
forests, also in the plains 2
8 Albizia saman Mazha Leguminosae Cultivated as avenue tree Native of Central and South 2
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 3 Description of the Environment
Page 3 - 29
(Jacq.) Merr. maram/rain tree America
9 Mangifera indica
L. Mavu Anacardiaceae
Evergreen and semi-
evergreen forests and
also widely cultivated
Indo-Malaysia 40
10
Averrhoa bilimbi Irumbanpuli Oxalidaceae
Cultivated. Native of
Malaysia 2
11 Tamarindus indica
L. Valampuli Leguminosae Cultivated
Native of Tropical Africa;
introduced and widely
grown in India and other
parts of tropics
2
12 Leucaena
leucocephala Subaabul Fabaceae 2
13 Caryota urens L. Choonda/
Choondappana Arecaceae
Evergreen forests, also
in the plains Indo-Malaysia 12
14 Macaranga peltata
(Roxb.) Müll.Arg. Vatta Euphorbiaceae
Moist deciduous and
secondary forests, also in
the plains
India, Sri Lanka and
Andamans 6
15 Cassia fistula L. Kanikkonna Caesalpiniaceae
Found in deciduous
forests from plains to
1400m. often planted
along the roadsides.
Indo-Malesia 4
16 Artocarpus
hirsutus Lam. Anjili Moraceae
Semi-evergreen and
moist deciduous forests, Southern Western Ghats 2
Endemic to
Southern
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 3 Description of the Environment
Page 3 - 30
also in the plains Western
Ghats
17 Carica papaya L. Papaya Caricaceae Cultivated Native of Tropical America 8 Exotic
18 Gliricidia sepium
(Jacq.) Walp. Seemakonna Leguminosae
Cultivated in fields and
along fences
Native of South America;
introduced and widely
grown in India
85
19
Lannea
coromandelica
(Houtt.)Merr.
Uthi/ Karayam Anacardiaceae Deciduous forest, also in
the plains Indo- Malaysia and China 1
20
Acacia
auriculiformis
Benth.
Acacia Leguminosae Cultivated Native of Tropical Australia 3 Exotic
21
Artocarpus
heterophyllus
Lam.
Plavu Moraceae
Evergreen and semi-
evergreen forests, also
widely cultivated
Widely cultivated in the
tropics, origin is probably
South India
11
22 Psidium guajava
L. Pera Myrtaceae Cultivated
Originally from Tropical
America; now naturalised in
the tropics
2 Exotic
23 Coccos nucifera L. Thengu /
Coconut Arecaceae Cultivated
Cultivated throughout the
tropics
1500
aprx.
24 Terminalia
catappa L. Badam Combretaceae Plains, Cultivated
Malesia to North Australia
and Polynesia, Commonly
planted in the tropics
35
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 3 Description of the Environment
Page 3 - 31
25 Ficus religiosa L. Arayal Moraceae
Plains from the coast up
to 1200m. Often planted
around temples
1
List of tree saplings
SN
Botanical Name Common Name Family Habitat Distribution Status
1 Mimusops elengi L. Elenji/ Asian
bullet wood Sapotaceae
Semi evergreen and
evergreen forest, also
grown in homestead
Indo-Malaysia
2 Trema orientalis (L.)
Bl. Pottaama Ulmaceae
Dry and moist
deciduous forests, also
in the plains
3 Macaranga peltata
(Roxb.) Müll.Arg. Vatta Euphorbiaceae
Moist deciduous and
secondary forests, also
in the plains
India, Sri Lanka and Andamans
4 Artocarpus
heterophyllus Lam. Plavu Moraceae
Evergreen and semi-
evergreen forests, also
widely cultivated
Widely cultivated in the tropics, origin
is probably South India
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 3 Description of the Environment
Page 3 - 32
5 Ficus religiosa L. Arayal Moraceae
Plains from the coast
up to 1200m. Often
planted around temples
6 Terminalia catappa
L. Badam Combretaceae Plains, Cultivated
Malesia to North Australia and
Polynesia, Commonly planted in the
tropics
7 Anacardium
occidentale L. Kasumavu Anacardiaceae Cultivated
Native of South America; now widely
cultivated in Asia and Africa
8 Cassia fistula L. Kanikkonna Caesalpiniaceae
Found in deciduous
forests from plains to
1400m. often planted
along the roadsides.
Indo-Malesia
9 Caryota urens L. Choonda/
Choondappana Arecaceae
Evergreen forests, also
in the plains Indo-Malaysia
10
Gliricidia sepium
(Jacq.) Walp. Seemakonna Leguminosae
Cultivated in fields and
along fences
Native of South America; introduced
and widely grown in India
11 Carica papaya L. Papaya Caricaceae Cultivated Native of Tropical America
12 Mangifera indica L. Mavu Anacardiaceae
Evergreen and semi-
evergreen forests and
also widely cultivated
Indo-Malaysia
13 Albizia saman
(Jacq.) Merr.
Mazha
maram/rain tree Leguminosae
Cultivated as avenue
tree Native of Central and South America
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 3 Description of the Environment
Page 3 - 33
14 Alstonia scholaris
(L.) R. Br.
Ezhilampala/
Devil Tree Apocynaceae
Moist deciduous
forests and sacred
groves, also in the
plains
South and South East Asia to
Australia
15 Acacia auriculiformis
Benth. Acacia Leguminosae Cultivated Native of Tropical Australia Exotic
16 Ficus hispida L.f.
Erumanakku/
Parakam/
Thonditherakam
Moraceae
Moist deciduous and
semi-evergreen
forests, also in the
plains
Indo-Malesia to Australia
17 Artocarpus hirsutus
Lam. Anjili Moraceae
Semi-evergreen and
moist deciduous
forests, also in the
plains
Southern Western Ghats
Endemic to
Southern
Western
Ghats
18 Psidium guajava L. Pera Myrtaceae Cultivated Originally from Tropical America;
now naturalised in the tropics
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 3 Description of the Environment
Page 3 - 34
List of Shrubs
Sl.
No Botanical Name Common Name Family Habitat Distribution Status
1 Pandanus odorifer
(Forssk.) Kuntze.
Pookaitha/
Thazhambu/Thala Pandanaceae Mangrove forests and sea coasts
Tropical and subtropical
Asia
2 Solanum torvum Sw. Anachunda Solanaceae
Found along the roads and
wastelands from plains to 700m.
Sometimes cultivated in kitchen
gardens.
Throughout the tropics
3 Lantana camara L. Kongini Verbenaceae Most aggresive weed of disturbed
ground from plains to the hills.
Native of tropical
America, widely
naturalised in tropics
and subtropics.
Exotic/
Invasive
Species
4 Ziziphus oenoplia Thudaly Rhamnaceae It grows along roadside forests and
thickets
Tropical and subtropical
Asia and Australasia.
5 Brineya retusa Aattacherukola, Phyllanthaceae Dry Evergreen to Dry Deciduous
Forests Sri Lanka to Indo-China
6 Bambusa bambos (L.)
Voss. Mula Poaceae
Deciduous forests, also grown in
homesteads India and Sri Lanka
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 3 Description of the Environment
Page 3 - 35
7 Ziziphus rugosa Lam. Kottamullu Rhamnaceae
Common on exposed and dry
slopes and forest edges from 900-
1500m. Peninsular India.
India, Sri Lanka,
Bangladesh and
Myanmar
8 Ixora coccinea L. Thechi/ Chethi Rubiaceae In the plains, also grown in
homesteads
Peninsular India and Sri
Lanka
9 Melastoma
malabathricum L. Athirani Melastomataceae Stream banks and marshy areas South East Asia
10 Clerodendrum
infortunatum L. Perivelam Verbenaceae
Degraded forest areas and also in
the plains Indo-Malesia Exotic
11 Sida rhombifolia L. Kurunthotti Malvaceae Wastelands, also in degraded
forest areas Pantropical
12
Chromolaena odorata
(L.) R.M.King &
H.Rob.
Communist-pacha Compositae A weed in all terrestrial habitats
Native of America;
naturalised in Tropical
Asia
Exotic/
Invasive
Species
13 Urena lobata L. Uram Malvaceae Moist deciduous forests and in the
plains Pantropical
14 Hibiscus hispidissimus
Griff. Matthippuli Malvaceae
Dry and moist deciduous forests,
also in the plains Paleotropics
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 3 Description of the Environment
Page 3 - 36
15 Sauropus andogynus
(L.) Merr. Velicheera Euphorbiaceae
Evergreen and semievergreen forest
and also grown in homesteads Indo-Malesia
16 Calotropis gigantea
(L.) R. Br. Erikku Asclepiadaceae Wastelands Tropical Asia
17 Clerodendrum
paniculatum L.
Krishnakireedam/Ha
numankireedam Lamiaceae Cultivated/Naturalized
Native of Malaysian
Region
18 Mussaenda frondosa L. Vellila Rubiaceae Moist deciduous and semi-
evergreen forests, also in the plains Peninsular India
List of Herbs
SN Botanical Name Common Name Family Habitat Distribution Status
1 Dactyloctenium aegyptium
(L.) Willd. Kakkakalan pullu Poaceae Marshy lands and open areas
Native of South
America, naturalised in
Paleotropics
2 Elephantopus scaber L. Aanachuvadi Compositae Moist deciduous forests, also in
the plains Pantropical
3 Axonopus compressus
(Sw.) P.Beauv.
Kaalappullu/
Carpet Grass Poaceae
Dry and moist deciduous forests,
waste lands and paddy fields Tropics and subtropics
4 Acmella paniculata (Wall.
ex DC.) R.K.Jansen Compositae
Frequently found in boggy
ground, margins of ponds,
Indo-Malesia, America
and New Guinea
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 3 Description of the Environment
Page 3 - 37
marshes, along water courses
and in rice fields.
5 Sida acuta Burm.f. Kurunthotti Malvaceae Dry and moist deciduous forests,
also in the plains Pantropical
6 Colocasia esculenta (L.)
Schott Chembu Araceae
Waterlogged ditches and
streamside Pantropical
Invasive
Species
7 Pennisetum orientale Rich. Poaceae Cultivated as fodder grass, often
found running wild
Central Asia and North
Africa
8 Centella asiatica (L.) Urb. Kodangal Apiaceae Deciduous forests, also in wet
places in the plains Tropical Asia and Africa Medicinal
9 Euphorbia hirta L. Nilappaala Euphorbiaceae Degraded forest areas and forest
plantations, also in the plains Pantropical.
10 Boerhavia diffusa L. Thazhuthama Nyctaginaceae
Found by the waysides,
wastelands, river banks and
hedges
Pantropical
11 Brachiaria ramosa (L.)
Stapf Chamapothaval Gramineae
Grasslands and moist deciduous
forests, roadsides and
wastelands
Africa and Tropical Asia
12 Musa paradisiaca L. Vazha Musaceae Cultivated Cultivated throughout
the tropics
13 Mimosa pudica L. Thottavadi Leguminosae Common on moist and ungrazed
places. Near riverbanks, bunds
Native of South
America, now Exotic
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 3 Description of the Environment
Page 3 - 38
of arable lands, fallow lands and
water courses.
pantropical.
14 Alternanthera sessilis (L.)
R.Br. Kozhuppa Amaranthaceae
Along sides of water courses &
marshy areas Pantropical
15 Scoparia dulcis L. Kallurukki Plantaginaceae Wasteplaces
Native of Tropical
America; now
Pantropical
Exotic
16 Ruellia prostrata Poir Irula Acanthaceae Found in the disturbed areas,
foot paths and agricultural lands India
17 Ageratum conyzoides L. Appa Compositae
Most abundant weed of
disturbed ground and fallows,
damp places and forest
undergrowth.
Pantropical Invasive
Species
18 Tragia involucrata Choriyanam Euphorbiaceae Wastelands India and Sri Lanka
19 Kyllinga nemoralis
(J.R.Forst. & G.Forst.)
Vallimuthanga/
Whitehead
spikesedge
Cyperaceae Waste places, degraded forest
areas and grasslands Pantropical
20 Phyllanthus amarus
Schum. & Thonn.
Keezharnelli/Phyll
anthus Phyllanthaceae
Degraded moist deciduous,
forest plantations and also in
plains
Tropics Medicinal
21 Peperomia pellucida (L.)
Kunth. Mashitandu Chedi Piperaceae
Degraded forest areas and
wastelands
Native of Tropical
America; now Exotic
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 3 Description of the Environment
Page 3 - 39
Pantropical
22 Tridax procumbens L. Odiyancheera Asteraceae Deciduous forests, also waste
lands in the plains
Native of Tropical
America; now
widespread throughout
tropics and subtropics
Exotic
23 Emilia sonchifolia (L.) DC. Muyalchevian compositae Dry and moist deciduous forests,
also in the plains
Tropical and Subtropical
Africa and Asia Exotic
24 Pilea microphylla (L.) Liebm. Gunpowder
Plant/Rockweed Urticaceae
Grown as garden plant, often
found as an escape
South America; now
introduced into other
tropical regions
Exotic
25 Desmodium triflorum Cherupalladi Fabaceae Grasslands and moist deciduous
forests, also in plains
Indo-Malesia and
Australia
26 Cleome rutidosperma DC. Neelavela Cleomaceae In coastal areas Pantropical
27 Synedrella nodiflora (L.)
Gaertn. Mudianpacha Compositae
Deciduous forests, also in the
plains
Native of West Indies;
naturalised in India,
China, Malesia and
Polynesia
Invasive
Species
28 Vernonia cinerea (L.) Less. Puvankurunal Compositae Deciduous forests, also in the
plains Pantropics Exotic
List of Climbers
SN Botanical Name Common Name Family Habitat Distribution Status
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 3 Description of the Environment
Page 3 - 40
1 Centrosema pubescens
Benth. Kattupayar Leguminosae
Forest plantations and
Deciduous forests, also in the
plains
Native of America;
introduced in India
2 Wattakaka volubilis (L.f.)
Stapf. Vattakakkakkoti Aslepiadaceae
Moist deciduous forests and
scrub jungles Indo-Malesia and China
3 Cyclea peltata (Lam.)
Hook. f. & Thoms. Padathali Menispermaceae
Semi-evergreen and
evergreen forests, also in the
plains
India and Sri Lanka
4 Ipomoea cairica (L.)
Sweet. Kolambipoo Convolvulaceae
Moist & Dry deciduous forests,
also in the plains Paleotropics
5 Calycopteris floribunda
(Roxb.) Lam. ex Poir. Pullani Combretaceae
Moist deciduous forest, also in
the plains Indo-Malesia
6 Cucurbita maxima
Duchesne. Mathan Cucurbitaceae Cultivated as vegetable
Cosmopolitan, mostly
cultivated
7 Mukia maderaspatana (L.)
M.Roem. Kasappuchedi Cucurbitaceae
Deciduous forests, also in the
plains Paleotropics
8 Passiflora foetida L. Poodapazham Passifloraceae
Very common along roadsides,
thickets and water courses
from plains
Native of tropical
America, now widely
naturalized the tropics
Exotic
9 Dendrophthoe falcata (L.f.)
Ettingsh. Ittikkanni Loranthaceae
Found in foothill scrub jungles
and deciduous forests from
plains to 1000m.
India, Sri Lanka,
Thailand, Indo-China and
Australia.
10 Merremia vitifolia (Burm. f.) Manja kolambi Convolvulaceae Degraded forest areas and Indo-China and China Invasive
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 3 Description of the Environment
Page 3 - 41
Hallier f. valli also in the plains species
11 Ichnocarpus frutescens (L.)
R.Br. Palvalli Apocynaceae
Moist and dry deciduous
forests, also in the plains
Indo-Malesia and
Australia
12 Pothos scandens L. Paruvakodi Araceae Evergreen forests, waste
places and sacred groves
India to Malesia and
Madagascar
13 Tylophora indica (Burm.f.)
Merr. Vallippala Asclepiadaceae
Common along the wayside
thickets, scrub jungles and
wastelands
India to South east Asia,
Sri Lanka, Malaysia
14 Mikania micrantha Kunth Vayara Compositae
Common along foothills, lower
slopes, scrub jungles even in
poor soils, on bare exposed
slopes.
Tropical and subtropical
regions of the world. Invasive
15 Asparagus racemosus
Willd. Sathavari Liliaceae
All forest types, also in the
plains Paleotropics
List of Ferns
SN Botanical Name Common Name Family Habitat Distribution
1 Drynaria quercifolia (L.) J.
Sm.
Basket fern,
Oak-leaf fern Polypodiaceae
Basket ferns are grown on trees or grown
on rocks. They can also sometimes be
found in man-made structures like brick
walls. They are found in wet tropical
environments.
Native to tropical Africa,
South Asia, East Asia,
Southeast Asia, Australia,
and Oceania
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 3 Description of the Environment
Page 3 - 42
2 Pityrogramma calomelanos
(L.) Link Silver fern Adiantaceae
Common on open ground in fairly exposed
places
American origin,now widely
distributed in pan-tropics
3 Selaginella delicatula Selaginellaceae Terrestrial in shaded areas Widely cultivated
4 Adiantum latifolium Lam. Adiantaceae Disturbed open areas. Native to tropical America
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 3 Description of the Environment
Page 3 - 43
Fauna
The fol lowing l ists of faunal elements were observed from the site:
Birds : 26 species
Mammals : 10 species
Butterf l ies : 24 species
Odonates : 12 species
Amphibians : 6 species
Repti les : 10 species
Spiders : 11 species
Ants : 6 species
The l ist of faunal species (mammals, rept i les, birds, Amphibian,
Odonates, Butterf l ies, Mil l ipedes and Centipedes, Ants, Spiders) observed
in the site area in table 3.19.
Table 3.19 - List of faunal species observed in the site area (mammals, reptiles, birds, Amphibian, Odonates, Butterflies,
Millipedes and Centipedes, Ants, Spiders)
List of Mammals (In and around the project site)
SN Common Name Scientific Name IUCN Status IW(P)A (Schedule)
1 Indian Hare Lepus nigricollis Least Concern
2 Lesser Woolly Horseshoe Bat Rhinolophus beddomei Least Concern
3 Common House Rat Rattus rattus Least Concern V
4 House Mouse Mus musculus Least Concern V
5 Indian Flying Fox Pteropus giganteus Least Concern V
6 Indian Grey Mongoose Herpestes edwardsii Least Concern III
7 Pig Rat Bandicota indica Least Concern V
8 Three striped Palm Squirrel Funambulus palmarum Least Concern V
9 Palm civet/Toddy Cat Paradoxurus hermaphroditus
Least Concern II
10 Greater Short-nosed Fruit Bat Cynopterus sphinx Least Concern V
* IW(P)A -The Indian Wildlife (Protection) Act, 1972.
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 3 Description of the Environment
Page 3 - 44
List of Reptiles
SN Scientific Name Common Name IUCN Status
1 Xenochrophis piscator Checkered Keel-back Least Concern
2 Bungarus caeruleus Common Krait Least Concern
3 Calotes versicolor Oriental Garden Lizard Least Concern
4 Eutropis carinata Keeled Indian Mabuya Least Concern
5 Naja naja Indian Cobra Least Concern
6 Hemidactylus mabouia House gecko Least Concern
7 Daboia russelii Russell's viper Least Concern
8 Dendrelaphis tristis Common Bronzeback Tree Snake Least Concern
9 Lycodon aulicus Common Wolf Snake Least Concern
10 Ptyas mucosa Oriental Rat Snake Least Concern
List of Birds
SN Scientific Name Common Name IUCN Status
1 Casmerodius albus Large Egret Least Concern
2 Alcedo atthis Small Blue Kingfisher Least Concern
3 Psittacula krameri Rose ringed parakeet Least Concern
4 Loriculus vernalis Indian Hanging Parrot Least Concern
5 Turdoides striatus Jungle Babbler Least Concern
6 Dendrocitta vagabunda Indian Treepie Least Concern
7 Columba livia Blue Rock Pigeon Least Concern
8 Egretta garzetta Little Egret Least Concern
9 Corvus splendens House Crow Least Concern
10 Centropus sinensis Greater Coucal Least Concern
11 Dicaeum erythrorhynchos Pale billed Flowerpecker Least Concern
12 Dicrurus macrocercus Black Drongo Least Concern
13 Copsychus saularis Oriental magpie robin Least Concern
14 Haliastur indus Brahminy kite Least Concern
15 Dicrurus paradiseus Racket tailed Drongo Least Concern
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 3 Description of the Environment
Page 3 - 45
16 Megalaima viridis White cheeked barbet Least Concern
17 Halcyon smyrnensis White Throated Kingfisher Least Concern
18 Hierococcyx varius Common Hawk Cuckoo Least Concern
19 Bubulcus ibis Cattle Egret Least Concern
20 Accipiter badius Shikra Least Concern
21 Nectarinia zeylonica Purple-rumped Sunbird Least Concern
22 Glaucidium radiatum Jungle Owlet Least Concern
23 Pitta brachyura Indian Pitta Least Concern
24 Ardeola grayii Indian Pond Heron Least Concern
25 Acridotheres tristis Common Myna Least Concern
26 Nectarinia lotenia Loten’s Sunbird Least Concern
List of Amphibians
SN Scientific Name Common Name IUCN Status
1 Rhacophorus malabaricus Malabar gliding frog Least Concern
2 Euphlyctis hexadactylus Green Pond Frog Least Concern
3 Pseudophilautus kani Kani Bush Frog Least Concern
4 Polypedates leucomystax Common Tree Frog Least Concern
5 Duttaphrynus melanostictus Indian common toad Least Concern
6 Hoplobatrachus tigerinus Indian bullfrog Least Concern
List of Odonates
SN Scientific Name Common Name
1 Ceriagrion coromandelianum Coromandel Marsh Dart
2 Urothemis signata Greater Crimson Glider
3 Ceriagrion cerinorubellum Orange-Tailed Marsh Dart
4 Pantala flavescens Wandering Glider
5 Diplacodes trivialis Ground Skimmer
6 Rhyothemis vareiegata Common Picture Wing
7 Potamarcha congener Yellow-Tailed Ashy Skimmer
8 Ictinogomphus rapax Common Clubtail
9 Neurothemis tullia Pied Paddy Skimmer
10 Aethriamanta brevipennis Scarlet Marsh Hawk
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 3 Description of the Environment
Page 3 - 46
11 Rhodothemis rufa Rufous Marsh Glider
12 Orthetrum sabina Green Marsh Hawk
List of Butterflies
SN Common Name Scientific Name Status
Papilionidae
1 Crimson Rose Pachliopta hector Linnaeus
2 Common Mormon Papilio polytes Linnaeus
3 Southern Birdwing Troides minos Cramer Endemic to W. Ghats
4 Common Rose Pachliopta aristolochiae Fabricius
5 Blue Mormon Papilio polymnestor Cramer
Pieridae
6 Common Jezebel Delias eucharis Drury
7 Common Emigrant Catopsilia Fabricius
8 Great Orange Tip Hebemoia glaucippe Linnaeus
9 Common Grass Yellow Eurema hecabe Linnaeus
Nymphalidae
10 Chocolate Pansy Junonia iphita Cramer
11 Great Eggfly Hypolimnas bolina Linnaeus
12 Clipper Parthenos sylvia Cramer
13 Common Sailor Neptis hylas Linnaeus
14 Common Four-ring Ypthima huebneri Kirby
15 Nigger Orsotriaena medus Fabricius
16 Common Crow Euploea core Stoll
17 Common Palmfly Elymnias hypermnestra Linnaeus
Lycaenidae
18 Yamfly Loxura atymnus
19 Tiny Grass Blue Zizula hylax Fabricius
20 Common Pierrot Castalius rosimon Fabricius
Hesperidae
21 Chestnut Bob Iambrix salsala Moore
22 Bush Hopper Ampittia dioscorides Fabricius
23 Grass Demon Udaspes folus Cramer
24 Pygmy Grass Hopper Aeromachus pygmaeus Fabricius
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 3 Description of the Environment
Page 3 - 47
List of Millipedes and Centipedes
SN Scientific Name Common Name IUCN Status
1 Trigoniulus corallinus Rusty millipede Least Concern
2 Anoplodesmus saussurii Least Concern
3 Leptogoniulus sorornus Least Concern
List of Ants
SN Common Name Scientific Name
1 Weaver Ant Oecophylla smaragdina
2 Black Crazy Ant Paratrechina longicornis
3 Yellow crazy Ant Anoplolepis gracilipes
4 Army Ant Leptogenys sp.
5 Red fire Ant Solenopsis geminata
6 Common Godzilla Ant Camponotus compressus
List of Spiders
SN Family Scientific Name
1 Araneidae Argiope pulchella
2 Araneidae Argiope anasuja
3 Salticidae Plexippus paykulli
4 Oxyopidae Oxyopes biramanicus
5 Pholcidae Crossopriza lyoni
6 Pisauridae Pardosa psedoannulata
7 Salticidae Plexippus petersi
8 Lycosidae Hippasa agelenoides
9 Araneidae Eriovixia laglaisei
10 Hersilidae Hersilia savignyi
11 Sparassidae Hetropoda venatoria
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 3 Description of the Environment
Page 3 - 48
3.8.4 Interpretation of Ecological Assessment
Flora
The most dominant plant family is Compositae with 8 plant species
followed by Leguminosae, Moraceae Euphorbiaceae, and Malvaceae. One
tree species namely Artocarpus hirsutus is endemic to Southern Western
Ghats.
Fauna
Regarding the conservat ion status of the fauna, none of the animal
species ident if ied from the site belonged to the threatened categories
identif ied by the International Union for Conservation of the Nature and
Natural Resources (IUCN). Most of them are common and widely
distributed and the range of occurrence extended to wide geographical
area. One species of butterf ly namely Southern Birdwing (Troides minos)
and one species of amphibian viz. Rhacophorus malabaricus reported
f rom the site are endemic to W. Ghats.
The present project is an expansion of exist ing hospital cum medical
college campus. The construct ion of new buildings are within the existing
plot area. Therefore, the proposed construct ion act iv ity wi ll have minimal
impact on the local f loral and faunal species. Due to the construct ion
act iv ity, there wil l be minimal loss of habitat to faunal species specially to
avifauna.
3.9 Socio Economc Environment
3.9.1 Introduction
The present project is an expansion of exist ing hospital cum medical
college campus and the construction of new buildings are within the
exist ing plot area.
The construction act iv ity has long term irreverisble impact on local,
sociological, cultural and economical situat ion. In order to evaluate socio-
economical impact of the project, an extensive study on the existing
socio-economic status is carr ied out. Since the project area is in pr ivate
land and devoid of any habitat ion, therefore, there is no displacment of
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 3 Description of the Environment
Page 3 - 49
people and loss of l ivelihood due to the proposed activity in the core
zone.
3.9.2 Approach adopted
To conduct the study, pr imary and secondary data were used.
Primary Data: Stake holder Consultat ion, unstructured interview, f ield
observat ion, and telephonic survey.
Secondary data: Yearly project document and Development Charter of
the Panchayat.
3.9.3 Stake Holders
As part of study the Socio Economic expert conducted interviews with
different stakeholders of the Panchayat. The detai ls of stake holders are
given below table 3.20.
Table 3.20 - Details of Stake Holder
Sl. No Name Designation Phone Number
01 M P Venugopalan Secretory, Edappal
Grama panchayath
8606339116
02 K Sathi Devi HM, Govt. U P
School,Pulikkad
9495805752
03 T P Surendran Polit ician 9048101990
04 K Bhavadasan Polit ician 8921195046
3.9.4 Edappal Gama Panchayath
The Edappal Gama Panchayath came in to exist in 1956. It is a town in
Malappuram district, Kerala state, India. Edappal is at a junction of two
roads Thrissur-Kutt ippuram and Palakkad-Ponnani state highways located
45 km from Malappuram.Edappal l ies in two panchayaths The fi rst notable
public inst i tut ion in Edapal was the Government High School (now higher
secondary school). The school was established in 1957 when the f irst
Communist ministry of EMS Namboodiripad had quickly sanct ioned 65
high schools in the then educat ionally backward Malabar region. Though
the high school was sanctioned, there was no suff icient fund or
infrastructure in order to start the high school. Hence the Namboothiris of
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 3 Description of the Environment
Page 3 - 50
Naarayanamangalathu Mana graciously donated the land where the high
school now stands.
3.9.5 Basic details of Edappal Grama panchayath
Name of Panchayat Edappal
Geographical area 22.28 Sq. Km
No. of wards 19
Vil lage Edappal and Kolollab
Distr ict Malappuram
Boundary North – Kalady Grama panchayath
East – Vattomkulam and Alamkode Grama
Panchayats
South – Nannamukku, Maranchery and
Veliyamkode panchayath
West –Ponnani Municipality and Maramcheri
Gramam Panchayath
3.9.6 Edappal Census Town
Edappal Census Town, with population of about 33 thousand is Ponnani
sub district 's the 2nd least populous census town located in Ponnani sub
district of Malappuram district in the state Kerala in India. Total
geographical area of Edappal census town is 22 km2 and it is the biggest
census town by area in the sub district. Populat ion density of the census
town is 1465 persons per km2. There is only one ward in this census town
which is Edappal Ward No 01 and the populat ion of Edappal Ward No 01
is about 33 thousand.
Nearest rai lway stat ion is Kutt ippuram which is 10 km far from here.
Ponnani is the sub district head quarter and the distance from the census
town is 12 km. District head quarter of the census town is Malappuram
which is 65 km away. Thiruvananthapuram is the state head quarter of the
census town and is 350 km far from here. Yearly average rainfall of the
census town is 2200 mm. Maximum temperature here reaches up to 30°C
and minimum temperature goes down to 24°C.
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 3 Description of the Environment
Page 3 - 51
3.9.7 Demographics
The census town is home to about 33 thousand people, among them about
15 thousand (46%) are male and about 17 thousand (54%) are female.
88% of the whole population are from general caste, 12% are from
schedule caste and 0% are schedule tribes. Child (aged under 6 years)
populat ion of Edappal census town is 12%, among them 50% are boys
and 50% are girls. There are 6684 households in the census town and an
average 5 persons l ive in every family.
3.9.8 Caste wise male female population 2011 - Edappal
Total General Schedule
Caste
Schedule
Tribe Child
Total 32,550 28,668 3,821 61 4,032
Male 15,113 13,235 1,848 30 2,004
Female 17,437 15,433 1,973 31 2,028
3.9.9 Religion wise distribution of population
Hindus contribute 57% of the total population and are the largest rel igious
community in the census town followed by Muslims which contr ibute 42%
of the total population. Female Sex ratio per 1000 male in Hindus are
1120 in Muslims are 1203.
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 3 Description of the Environment
Page 3 - 52
3.9.10 Religion wise population 2011 - Edappal
Total Hindu Muslim Christian Sikh Buddhist Jain Others Not
Sta ted
Total 32,550 18,716 13,603 161 1 0 0 1 68
Male 15,113 8,828 6,174 73 0 0 0 1 37
Female 17,437 9,888 7,429 88 1 0 0 0 31
3.9.11 Growth of population
Population of the census town has increased by 7.5% in last 10 years. In
2001 census total population here were about 30 thousand. Female
populat ion growth rate of the census town is 9.8% which is 4.9% higher
than male populat ion growth rate of 4.9%. General caste population has
increased by 7.6%; Schedule caste populat ion has increased by 4.9%;
Schedule Tribe population has increased by 1933.3% and child population
has increased by 4.8% in the census town since last census.
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 3 Description of the Environment
Page 3 - 53
3.9.12 Growth of population (percent) 2001 to 2011 - Edappal
Total General Schedule
Caste
Schedule
Tribe
Child
Total 7.5% 7.6% 4.9% 1933.3% 4.8%
Male 4.9% 4.8% 4.1% 1400% 3.7%
Female 9.8% 10.1% 5.7% 3000% 6%
3.9.13 Sex Ratio - Females per 1000 Male
As of 2011 census there are 1154 females per 1000 male in the census
town. Sex ratio in general caste is 1166, in schedule caste is 1068 and in
schedule tr ibe is 1033. There are 1012 girls under 6 years of age per
1000 boys of the same age in the census town. Overall sex rat io in the
census town has increased by 52 females per 1000 male during the years
from 2001 to 2011. Child sex rat io here has increased by 22 girls per
1000 boys during the same t ime.
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 3 Description of the Environment
Page 3 - 54
3.9.14 Change in sex ratio 2001 to 2011 - Edappal
Total General SC ST Child
Change 52 56 17 533 22
2011 1154 1166 1068 1033 1012
2001 1102 1110 1051 500 990
3.9.15 Literacy
Total about 27 thousand people in the census town are literate, among
them about 13 thousand are male and about 14 thousand are female.
Literacy rate (children under 6 are excluded) of Edappal is 95%. 97% of
male and 94% of female populat ion are l i terate here. Overall l iteracy rate
in the census town has increased by 4%. Male literacy has gone up by 2%
and female li teracy rate has gone up by 6%.
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 3 Description of the Environment
Page 3 - 55
3.9.16 Change in l iteracy rate 2001 to 2011 - Edappal
Total Male Female
Change 4.0% 2.0% 5.9%
2011 95% 96.6% 93.6%
2001 91% 94.6% 87.7%
3.9.17 Workers profile
Edappal has 28% (9131) populat ion engaged in either main or marginal
works. 48% male and 11% female population are working populat ion. 40%
of total male populat ion are main (full t ime) workers and 9% are marginal
(part t ime) workers. For women 7% of total female population are main
and 3% are marginal workers.
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 3 Description of the Environment
Page 3 - 56
3.9.18 Percentage of working population - Edappal
Worker
(Among total
populat ion)
MainWorker
(Among
workers)
Marginal Worker
(Among workers)
Non Worker
(Among total
populat ion)
Total 28.1% 22.2% 5.8% 71.9%
Male 48.2% 39.5% 8.7% 51.8%
Female 10.5% 7.2% 3.3% 89.5%
3.9.19 Demographics
Population 32550
Population density 1465 per km2
Growth of Populat ion 7.5%
Sex Ratio 1154
Sex Ratio Child 1012
Literacy Rate 95%
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 3 Description of the Environment
Page 3 - 57
3.9.20 Interpretation of present socio-economic status of the area
The density of population in the buffer zone is about 1465 persons per
sq km. The project area is in a rural vi l lage.
Majority of the population in the study area are engaged in agriculture and
cult ivation. There is no major industry in the area. The proposed project is
l ikely to generate direct and indirect employment. Economic growth is
expected in the area due to construction boom and al lied industry like
transport, mini hotels and restaurants and enhanced commercial activit ies
(markets, shops, real estate etc.).
Also, the healthcare faci l it ies wil l be increase due to the sett ing up of
medical col lege in the vic inity.
*******************************************************************************
M/s SREEV ALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 4 Ant ic ipated Envi ronmenta l Impacts & Mit igat ion Measures
Page 4 - 1
4.0 ANTICIPATED ENVIRONMENTAL IMPACTS & MITIGATION MEASURES
4.1 Introduction
The previous chapter dealt with the Descript ion of the Environment
surrounding the project area.
The present project is an expansion of exist ing hospital cum medical
college campus. The construct ion of new buildings are within the existing
plot area. Therefore, the proposed construction activity will have minimal
impacts on the dif ferent facets of the environment.
The ambient air quality and ambient noise level of the core zone and
buffer zone is within the permissible standards. The water quality
assessment (ground water and surface water) is sat isfactory. The
proposed construction act ivity wil l not disturb the ground water quality.
The land use land cover of the buffer zone is predominantly with
plantations. There is some endemic f loral & faunal species. There are no
species belonging to Rare, Endangered and Threatened (RET) species.
The project area is in a rural area and the nearest town (urban area) is
Edappal which is located at about 2 km towards north direction from the
project s ite.
4.1.1 Areas for identification of Environmental aspects and impacts.
Proposed project wil l be constructed and developed gradually in the t ime
span of 5 years (approx.). The overall project wil l have two phases i.e.
construction phase and operat ion phase. In construction phase, basic
infrastructure faci l it ies l ike internal roads, water supply, sewerage
system, storm water drainage, street l ight ing, construction of dif ferent
buildings, up-gradat ion of sewage treatment plant, eff luent treatment
plant, up-gradation of solid waste disposal & treatment arrangement
system, rain water harvest ing systems etc. wil l be developed.
The proposed project is an expansion of exist ing hospital cum medical
college campus, therefore, most of the infrastructure faci l it ies are already
developed within the site.
During operation phase, the developed infrastructure wil l be in operation
and wil l have environmental aspects l ike vehicular movement, operat ion
M/s SREEV ALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 4 Ant ic ipated Envi ronmenta l Impacts & Mit igat ion Measures
Page 4 - 2
of D.G. sets, eff luent & sewage generation, generation of MSW & bio-
medical waste, e-waste, hazardous waste etc. The areas of environmental
concerns for which the impacts and their predict ions are taken into
consideration are :-
• Air Environment
• Noise Environment
• Water Environment
• Land Environment
• Biological Environment
• Socio-Economic Environment
• Aesthet ics
• Building Materials
• Energy Conservation
4.2 Details of anticipated environmental impacts due to the proposed project and the mitigation measures for minimizing and / or offsetting adverse impacts identified.
4.2.1 Air Environment
Impacts on the Air Environment:
Prediction of Impact during Construction Phase
Impact of construction activit ies on air quali ty is a cause for concern
mainly in the dry months due to sett l ing of dust particles. The main
sources of emission during the construct ion period are the movement of
equipment at site and dust emitted during the level l ing, grading,
earthworks, foundation works and other construction related act iv it ies.
The impact is l ikely to be for short duration and conf ined locally to the
construction site i tself . The impact will , be marginal, and temporary in
nature.
Prediction of Impact during Operation Phase
The source of gaseous pollutants within the proposed expansion project
are from DG sets. The emissions of Sulphur Dioxide (SO2) and Oxides of
Nitrogen (NOx) wil l be due to operat ion of DG sets (Existing - 500 kVA x
1 no. + 625 kVA x 1 no. and Proposed - 500 kVA x 1 no. + 625 kVA x
M/s SREEV ALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 4 Ant ic ipated Envi ronmenta l Impacts & Mit igat ion Measures
Page 4 - 3
1 no.), only in case of the fai lure of the power grid.
In order to control emission of particulates during operation of the DG
sets, adequate stack height is provided as per CPCB norms.
Air Modelling Studies
The mathematical Model ISCST-3, was used for predicting the GLCs,
which is entirely in l ine with the requirement of Central Pollut ion Control
Board (CPCB), New Delhi.
Anticipated Impacts during construction phase
Environmental aspects during Construction Phase
The potential sources of air emissions during the construct ion phase of
the project wil l be as fol lows:
• Dust from earth works (during si te clearance and preparat ion for
construction of new buildings);
• Emissions from diesel generators at site;
• Emissions from the operation of construct ion equipments and
machineries.
• Fugit ive emissions from vehicles running to site;
• Fugit ive emissions during the unloading of loose construction materials
at site;
• Fugit ive emissions during mixing of cement with other building
materials during construct ion act ivit ies;
• Air emissions other than dust ar ise from combustion of hydrocarbons.
The pollutants of concerns are NOx, SOx, CO, particulate etc.
• Use of f ire wood, coal etc as fuel for domestic cooking etc in labour
sheds.
Ambient air quali ty effects are normally assessed in relat ion to their
potent ial to cause health deteriorat ion and nuisance in local communities ,
health deteriorat ion amongst onsite workers etc.
During the excavation of foundations, unloading of loose construction
materials, cement bags and mixing of cement with other building materials
such as brick and stone dust, sand, aggregates, fugit ive dust emissions
M/s SREEV ALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 4 Ant ic ipated Envi ronmenta l Impacts & Mit igat ion Measures
Page 4 - 4
may be emitted at construction site. It may be noted that these emissions
wi ll be in the form of coarse particulate matter and sett le down ult imately
in closed vicinity of construction site.
Emissions from the D.G. sets during construct ion phase may cause some
local ized impact on ambient air quality for short duration, as it wil l be
operated during power fai lure only. It may be noted that the D.G. set
power will be used to operate construct ion equipment only if required.
Adequate height of stacks and Acoust ic enclosures wi ll be provided to the
D.G. set as per guidelines of CPCB to facil i tate the dispersion of f lue
gases into the atmosphere.
Environmental Aspects during operation phase
During the operation phase, cars, scooter/motorcycle will be owned by the
occupiers of proposed project. Also, the vehicles and the transport system
for staff in dif ferent bui ldings of hospital cum medical col lege campus wil l
be at site. Vehicular emissions wil l be major source of air pollution.
Quantum and dispersion of pol lutants form vehicular emission wil l depend
upon the fol lowing:
• Volume of traff ic on the roads,
• Meteorological condit ions.
• Emission sources from D.G. Sets
From vehicular emissions, SOx, NOx and CO are pol lutants of primary
concern. The dispersion of vehicular emissions wi l l be conf ined upto
100 m from the road and concentration will decrease with the increase in
distance from road. It is ant icipated that the contribution of vehicular
emissions in ambient air quali ty wil l be marginal but well within the
stipulated National Ambient Air Quality standards. At higher wind speed,
dispersion wil l be faster.
D.G. Sets wil l be provided for back up electric ity supply during power
failure. This wi ll cause emission of SPM, SOx, NOx and CO. However,
since the D.G. Sets wil l be operational only during power fai lure, the
emissions wil l also be limited.
M/s SREEV ALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 4 Ant ic ipated Envi ronmenta l Impacts & Mit igat ion Measures
Page 4 - 5
Improper disposal of sewage and municipal sol id waste in the land also
causes nuisance in the operation phase of the project.
4.2.2 Noise Environment
Environmental aspects during construction phase
During the construction phase of project, noise will be generated from the
various sources. Some major sources of noise generation at project site
are l isted here under:
• Generation of noise during movement of vehicles carrying materials
and also during loading & unloading activ it ies.
• Generation of noise from excavation machines, concrete mixer and
other construction machines,
• Generation of noise during the operat ion of D.G. Sets,
• Generation of noise during concret ing, hammering, dri l l ing, stone
cutt ing etc.
All the above-mentioned sources of construction activit ies at proposed
expansion project would be intermittent and experienced occasionally. It
may also be noted that the most of the construct ion activ it ies would be
carried out only during the daytime.
The expected noise levels from various activit ies are given hereunder:
From vehicles bringing materials to the site 70 dB(A)
D.G. Set 85 dB(A)
Excavat ion 80 dB(A)
Concrete Mixtures 80 dB(A)
Hammering 85 dB(A)
The sound level generated by noise source decreases with increasing
distance from the source due to wave divergence. An addit ional decrease
in sound pressure level from the source is expected due to atmospheric
effect or i ts interaction with objects in the transmission path.
The noise produced during construction phase will have temporary
impacts on the existing, ambient noise levels at project site but restricted
to small distance and only during dayt ime.
M/s SREEV ALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 4 Ant ic ipated Envi ronmenta l Impacts & Mit igat ion Measures
Page 4 - 6
Environmental aspects during operation phase
The main sources of noise from the project are running of D.G. Sets,
HVAC system and vehicular traff ic. D.G. Sets installed in the proposed
project wi ll provide emergency electr icity supply during power fai lure. This
wi ll be intermittent and for short durations. The vehicles plying within the
site wil l be mainly of the occupiers and hence not expected to cause
unnecessary noise. Hence, during this phase, no major impact on noise
environment is ant icipated.
4.2.3 Land Environment
Environmental Aspects during Construction phase
Environmental aspects during construction phase in the land environment
are: -
• Infrastructure development
• Site clearance & excavation
• Excavated earth & loose construction materials
• Loss of topsoil due to storm water
• Labour colony & generation of sewage and municipal solid waste
• Construct ion waste generation and disposal
Environmental Aspects during Operation phase
During the operation phase of the project, the soi l may get polluted /
contaminated from lit ter ing of various kinds of wastes generated within
the site such as food items, paper, wood pieces, paints, pesticides, oi l &
grease etc.
4.2.4 Water Environment
Environmental Aspects of Surface Water during construction phase
The primary concerns relat ing to surface water associated with
construction activit ies are pointed out below:-
• Consumption of large quantity of water for site preparat ion &
development.
• Loose excavated earth and loose construction material at site & runoff
related to unpaved and excavated / exposed areas during rainy days.
M/s SREEV ALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 4 Ant ic ipated Envi ronmenta l Impacts & Mit igat ion Measures
Page 4 - 7
• Sediments transported along with the runoff f rom the construct ion site.
• Run off related to area where lubricant, fuel other construct ion
materials are stored, used and disposed, off .
• Water consumption in labour colony (temporary accommodation area
for laborers) and generation of sewage & MSW from the colony.
Large quantity of water required for site preparation & development also
water consumption in labour colony during construct ion phase. Surface
water quality may be affected with the discharge of the runoff f rom the
project site. The impact to the surface water bodies could arise from the
increased soil erosion from excavated site / exposed soil causing
increase in the suspended part ic les and turbidity of runoff water from the
site. Also the non-point sources of pollut ion can affect the surface water
body. Also, the municipal solid waste and the sewage generation from the
labour colony wi ll af fect the water quality for a shorter period. Therefore,
the surface water quality during rains will be impacted marginally for very
short duration.
Environmental Aspects of Surface Water during operation phase
During the operational phase, large quantity of water consumption for the
occupier of dif ferent buildings, make-up water to the HVAC units can have
impact on competing users. The generation of sewage & MSW, bio-
medical waste from the hospital, e-waste from institutional buildings,
hazardous waste from hospital cum medical college campus can have
impact on the surface water body.
Environmental Aspects of Ground Water during construction phase
Due to the presence of high ground water table within the project site, the
excavat ion during construction phase for below ground level structures if
carried out wil l lead to dewatering and deplet ion of ground water and wil l
have impact for a longer duration. Consumption of ground water for
construction activit ies and for labour colony will have impact on
competing users for a shorter duration. Discharge of sewage & MSW to
land can contaminate ground water for a shorter duration.
M/s SREEV ALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 4 Ant ic ipated Envi ronmenta l Impacts & Mit igat ion Measures
Page 4 - 8
Environmental Aspects of Ground Water during Operation phase
Consumption of ground water for domestic purposes for occupiers of the
different bui ldings of hospital cum medical college & make-up water for
HVAC units will have impact on competing users for a longer durat ion.
Discharge of sewage & MSW to land can contaminate ground water for a
longer duration.
As per the Ground Water information Booklet, CGWB, the proposed
project is categorized as 'Safe' zone and hence the ground water
available in the region is ensure and to use of domestic purposes.
4.2.5 Biological Environment
Environmental aspects during construction phase
The biological environment can have impact due to the fol lowing
environmental aspects during construction phase: -
• Site clearance & excavation
• Various construct ion act ivit ies
• Labour colony (temporary accommodation of laborers) and
procurement of f ire wood for domestic purposes.
Environmental aspects during operation phase
The biological environment can have impact due to the fol lowing
environmental aspects during operation phase: -
• Vehicular movement
• Generation of Municipal sol id waste & its improper disposal.
4.2.6 Socio-Economic Environment
Environmental aspects during construction phase
The socio-economic environment can have impact due to the following
environmental aspects are: -
• Labour colony & the migrant labours and the related cultural &
social issues
• Unhygienic site sanitation facil it ies may cause health damage to the
workers.
M/s SREEV ALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 4 Ant ic ipated Envi ronmenta l Impacts & Mit igat ion Measures
Page 4 - 9
Environmental aspects during Operation phase
All the environmental aspects during operat ion phase of the proposed
expansion of existing campus can lead to posit ive impacts only. During
operational phase of proposed expansion of existing hospital cum medical
college campus project, about 1,000 persons will get direct employment
opportunit ies as staff in the inst i tut ional building, management staff ,
maintenance, housekeeping and security. As an est imate, during
operation phase, about 100 persons wil l get marginal employment
opportunit ies from the proposed project who would work as domestic
helpers. This wi ll help in improving the qual ity of l i fe of economically
weaker sect ions of the local area.
4.2.7 Other environmental aspects
The other identif ied environmental aspects which can have impact during
construction phase & operation phase are: -
• Un-aesthetic Labour colony for the workers
• In-eff icient building design and high consumption of energy
• In-eff icient building materials and high consumption of energy
• Improper f ire & other emergency preparedness during natural and
man-made activit ies.
4.3 Identified Environmental impacts from various aspects
The above discussed environmental aspects during construct ion &
operation of the project have been analyzed to identify the possible
environmental impacts on air, noise & vibration, water, land environment,
biological & socio economic environment, building materials, energy etc.
Various impacts during the construction phase and operation phase on
the environmental parameters have been studied to est imate the impact
on environment.
The impact identif icat ion and predict ion process aims to:
• Ident ify potential source or cause of impact throughout the l i fe of
project.
• Characterize the potent ial impacts affect ing a target or receptor
(physical, human and socio-economic).
M/s SREEV ALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 4 Ant ic ipated Envi ronmenta l Impacts & Mit igat ion Measures
Page 4 - 10
• Assess the potential of changing likely-hood of impact through
Environmental Management Plan (EMP)
Prediction of the impacts due to the construct ion and operat ional
act iv it ies encompass the developmental processes to be undertaken
during construct ion and operational phases. For each category of
environmental receptor (such as ambient air quality, water quali ty, soil,
land, biological environment, noise level, socio economic aspects etc.)
the potent ial impacts of activit ies during construct ion and operational
phases have been identif ied.
The generat ion of pollut ion could be cont inuous, periodic or accidental,
sources of pollutants and their characteristics during the construction and
operational phases. Similarly, the consumption / loss of natural resources
could be cont inuous, periodic or accidental.
The Identif ied Impacts are broadly divided into two segments.
1. Impacts due to pollutants generated in the development of the
proposed project during both the construction and operat ional phases
are solid, l iquid and gaseous in nature.
2. The consumption / loss of natural resources l ike water, top-soi l, current
ecology of the site etc.
In al l, 35 Environmental aspects have been ident if ied from various areas
during construction phase and 29 during operation phase.
The identif ied environmental aspects & their ant ic ipated impacts are
presented in the table 4.1.
M/s SREEV ALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 4 Ant ic ipated Envi ronmenta l Impacts & Mit igat ion Measures
Page 4 - 11
Table 4.1- Matrix of identified Environmental Aspects & their Anticipated Impacts from the project
CONSTRUCTION PHASE:-
S.
No.
Impact on
Environment Act ivi ty / Aspect Ant icipated Impacts
AIR ENVIRONMENT
1 Air
Si te Clearances &
preparat ion, excavat ion &
infrastructure development
Dust emissions.
2 Air Construc t ion Act ivi t ies** Dust Emissions from construct ion act iv i t ies
3 Air Point source emissions f rom
operat ion of DG Sets
Part icu la te Matter & Gaseous emissions
( including worst condit ion of operat ing a l l
DG sets)
4 Air
L ine source emissions from
movement of construct ion &
other vehic les, machiner ies.
Fugi t ive dust & gaseous emissions f rom vehic les exhaust
5 Air Temporary stay of construct ion workers
Impact on ambient a ir due to use of f i re
wood, coal, e tc. as fue l for domest ic
cook ing etc.
WATER ENVIRONMENT
1 Water Si te preparat ion &
infrastructure development
Use of large quant ity of water for dust
suppress ion, consol idat ion & compaction.
2 Water Excavat ion for below ground
leve l structures Impacts on Hydrology due to dewater ing
3 Water Construc t ion Act ivi t ies**
Impact on compet ing users due to large
consumpt ion of water for cur ing, dust
suppress ion, construct ion, domest ic use
etc.
4 Water
Loose excavated ear th &
loose construct ion mater ials
at s i te
Contaminat ion of surface water body &
aquat ic l i fe
5 Water Storm water f rom the s ite
Improper channel izat ion may lead to
contaminat ion of sur face water & ground
water by non-point sources of po l lu t ion
l ike l i t ter , o i l & grease, loose earth
6 Water Storm water f rom the s ite
Clogging of storm water drainage system
by s i l t & other mater ia ls may lead to
f looding condit ions
7 Water
Temporary stay of construct ion workers generat ion of sewage & MSW
Impact on surface / ground water qual it y
due to untreated discharge of sewage &
so l id waste from the labor colony
8 Water
Temporary stay of
construct ion workers & the ir
domest ic water consumpt ion
Impact on compet ing users due to
consumpt ion of publ ic supply / ground
water ( resource loss)
NOISE ENVIRONMENT
M/s SREEV ALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 4 Ant ic ipated Envi ronmenta l Impacts & Mit igat ion Measures
Page 4 - 12
1 Noise Movement of construct ion
equipments & machiner ies.
Noise due to heavy machinery for
excavation
2 Noise Construct ion Act ivi t ies** Noise & vibrat ion due to construct ion
Act iv i t ies
3 Noise Operat ion of DG Sets
Noise & Vibrat ion from DG Sets due to
inadequate acoust ic enclosure ( including
worst condi t ion of operat ing al l DG sets)
LAND ENVIRONMENT
1 Soi l In frastructure development Compact ion of so i l by ear th moving
vehic les
2 Soi l Si te Clearance & excavat ion Erosion & modif icat ion of surface
3 Soi l excavated earth & loose
construct ion mater ials Loss of topsoi l ( resource loss)
4 Soi l Storm water f rom the s ite
Improper channel izat ion may lead to loss
of fer t i le top so i l a long with sur face run-of f
and subsequent loss of water ho lding and
inf i l t rat ion capaci ty of so i l
5 Soi l Temporary stay of
construct ion workers
Impact due to untreated d ischarge of
sewage & MSW into the land
6 Soi l Construc t ion waste Improper d isposal o f construct ion waste
into the land
BIOILOGICAL ENVIRONMENT
1 B io log ica l Si te Clearances &
Excavat ion
Loss of vegetat ion and loss of habi ta t of
faunal species (resource loss)
2 B io log ica l Construc t ion Act ivi t ies** Vibrat ion due to movement / operat ion of
heavy machinery
3 B io log ica l Temporary stay of construct ion workers
Cutt ing of trees, shrubs etc. for procur ing
f i re wood by construct ion workers.
( resource loss)
SOCIO-ECONOMIC
1 Socio
Economic Temporary stay of construct ion workers
Impact on nat ive socia l fabr ic o f the si te
surroundings l ike cu l tural d ivers i t y,
possib le increase in ant i-socia l act iv i t ies
etc.
2 Socia l
Responsibi l i t y Construc t ion workers
Unhygien ic s i te sanita t ion faci l i t ies may
cause heal th damage to construct ion
workers
OTHERS
1 Aesthet ics Temporary stay of construct ion workers
Construct ion of Improper / unaesthet ic
labor sheds/shel ters may impact aesthet ic
appearance of the s i te surroundings.
2 Energy
Conservat ion Energy Consumpt ion
Use of energy in-ef f ic ient bu ild ing
mater ia ls may lead to h igher consumpt ion
of e lectr ic i t y in air condit ioned bui ld ings.
3 Energy
Conservat ion Energy Consumpt ion
Adopt ion of energy in-ef f icient vehic les, appl iances, l ights etc. may lead to wastage of energy
M/s SREEV ALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 4 Ant ic ipated Envi ronmenta l Impacts & Mit igat ion Measures
Page 4 - 13
4 Energy
Conservat ion Energy Consumpt ion
Improper or ientat ion of the bu i ld ing may lead to h igh energy consumpt ion due to high heat ga in to the bu i ld ing, dark zone & improper vent i la t ion
5
Bui ld ing Mater ial
Resource Conservat ion
Bui ld ing Mater ia l
consumpt ion
Use of far fetched construct ion mater ia ls
than the local ly avai lab le construct ion
mater ia ls may lead to over explo i tat ion of
natura l resources & increase in carbon
footpr int
6 Disaster
Management Fire & other hazards
Absence of proper f ire protect ion sys tems
may lead to f i re hazards
7 Disaster
Management Fire & other hazards
Absence of s ignages, mock dr i l ls &
assembly points
8 Disaster
Management Fire & other hazards
Absence of relevant st ructura l safety
measures dur ing bui ld ing design may lead
to damage to bu i ld ings dur ing the natura l
calamit ies
OPERATION PHASE:-
S.
No.
Impact on
Environment Act ivi ty / Aspect Ant icipated Impacts
AIR ENVIRONMENT
1 Air On s i te Vehic le Movement Dust & gaseous emissions from vehic les
exhaust
2 Air Point Source emissions
f rom operat ion of DG Sets
Part icula te Mat ter & Gaseous emissions
( includ ing worst condi t ion of operat ing a l l
DG sets)
3 Air Sewage & Munic ipa l Solid
Waste
Improper d isposal of sewage and MSW
may lead to odour & generat ion of gases
due to de-composi t ion
WATER ENVIRONMENT
1 Water Water consumpt ion
Impact on compet ing users due to
consumpt ion of publ ic supply / ground
water ( resource loss)
2 Water Operat ion of HVAC Plant
Impact on compet ing users due to
consumpt ion of publ ic supply / ground
water as make-up water ( resource loss)
3 Water Sewage
Improper d ischarge of untreated sewage
may lead to impact on sur face / ground
water qual it y.
4 Water Munic ipa l Sol id W aste &
Medica l W aste from
Hospita l
Improper d isposal of so l id waste may
at tract scavenger avi fauna which may
lead to d isser tat ions of nat ive avi fauna
5 Water e-waste
Improper storage & d isposal may lead to
leaching of heavy metals leading to
contaminat ion
M/s SREEV ALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 4 Ant ic ipated Envi ronmenta l Impacts & Mit igat ion Measures
Page 4 - 14
6 Water Hazardous W aste
Improper storage & d isposal may lead to
leaching of hazardous waste leading to
contaminat ion
7 Water storm water
Improper channel izat ion may lead to
contaminat ion of water body & c logging of
drain may lead to f looding
NOISE ENVIRONMENT
1 Noise Vehic le Movement Increase in Noise & Vibrat ion in
surrounding area
2 Noise Operat ion of DG Sets Noise & Vibrat ion from DG Sets due to
inadequate acoust ic enclosure
3 Noise Operat ion of HVAC Plant Noise & vibrat ion from HVAC Plant
LAND ENVIRONMENT
1 Soi l Munic ipal Sol id W aste Improper disposal of munic ipal sol id
waste may lead to impact on land.
2 Soi l sewage Improper d ischarge of unt reated sewage
may lead to impact on land.
3 Soi l e-waste
Improper storage & d isposal may lead to
leaching of heavy metals leading to
contaminat ion
4 Soi l Hazardous W aste
Improper storage & d isposal may lead to
leaching of hazardous waste leading to
contaminat ion
5 Soi l Storm water Non-point sources of po l lut ion l ike l i t ter ,
o i l & grease, loose ear th
6 Soi l Storm water
Clogging of storm water dra inage system
by s i l t & other mater ia l may lead to
f looding
BIOLOGICAL ENVIRONMENT
1 Biologica l Vehic le Movement Increase in Noise & Vibrat ion in
surrounding area
2 Biologica l Munic ipa l Sol id Waste &
B io-medical waste
Improper disposal of MSW & BMW may
at tract scavenger avi fauna which may
lead to disser tat ions of nat ive avi fauna
OTHERS
1 Aesthet ics Munic ipa l Sol id Waste &
Bio-Medica l Waste
Improper disposal of MSW & BMW may
lead to un-aesthet ic condit ions
2 Energy
Conservat ion Consumption of Energy
Adopt ion of energy in-ef f icient vehic les,
HVAC system, appl iances, l ights etc may
lead to wastage of energy
3 Energy
Conservat ion Consumption of Energy
Non adopt ion of renewable sources of
energy l ike solar energy may lead to
increase dependency on publ ic supply
may lead to consumpt ion of energy by
compet ing users
M/s SREEV ALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 4 Ant ic ipated Envi ronmenta l Impacts & Mit igat ion Measures
Page 4 - 15
4 Disaster
management Fire & other hazards
Absence of trained personnel & mock
dr i l ls may lead to major f i re accidents &
non maintenance of system
SOCIO- ECONOMIC (ALL POSITIVE IMPACTS)
1 Socio Economic bus iness act iv it ies
Increased revenue to the State & Local
Sel f Government by way of taxes and
dut ies leading to inf rast ructure
development & better c iv ic amenit ies
2 Socio Economic bus iness act iv it ies
New business act iv i t ies may lead to
increase in employment opportun ity /
new job creat ion (d irect & ind irect ) for
the local community
3 Socio Economic bus iness act iv it ies
Increased business act iv i t ies at s i te may
lead to improved public t ranspor t
infrastructure in the region may improve
the l i fe st yle and connect iv it y o f the loca l
communit y
4 Socio Economic Medica l faci l i t ies
Avai lab i l i t y of bet ter medica l treatment
faci l i t y w i th in the v ic ini ty to the loca l
populat ion.
4.4 Selection criteria for evolving significant impacts
The signif icance of the impact is decided based on the fol lowing criteria.
� Whether the environmental aspects have potent ial to cause direct
impact or indirect impacts?
� Whether the environmental aspects would violate legal / mandatory
requirement if uncontrol led?
� Whether the l ikely environmental impact will be l imited to local
surroundings or it would be wide spread?
� Whether the likely environmental impact would be of a temporary
nature or permanent nature depending on the toxicity levels?
� Whether the occurrence of the environmental aspects and its l ikely
environmental impact wil l be of long term nature or short term
nature?
� Whether mit igation measures available and can be adopted to
minimize the signif icance of the impacts to permissible l imits?
The above criteria has been shown in the table 4.2 below.
M/s SREEV ALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 4 Ant ic ipated Envi ronmenta l Impacts & Mit igat ion Measures
Page 4 - 16
Table 4.2 - Criteria for Evolving Significant Impacts
Sr.
No.
Criteria Classif icat ion
1. Whether the environmental aspects has potential
to cause direct impact or indirect impact. Direct Indirect
2. Whether the environmental aspects would v iolate
legal / mandatory requirement if uncontrol led Mandatory
Not
Mandatory
3. Whether the l ikely environmental impact wi l l be
limited to local surroundings or i t would be wide
spread.
Local W ide
spread
4. Whether the l ikely environmental impact would be
of a temporary nature or permanent nature
depending on the toxicity levels.
Temporary Permanent
5 Whether the occurrence of the environmental
aspects and i ts l ikely environmental impact wi l l
be of long durat ion in nature or short durat ion.
Long Term Short Term
6 Whether mitigation measures avai lable and can
be adopted to minimize the signif icant of the
impacts to permissible l im its.
Yes No
4.5 The marking for various criteria
For the purpose of comparing the weightage of signif icance of the above
criteria, marks are given to each cr iter ia. Mult ipl ication of marks of al l the
six criter ia is made to arrive at the f inal score of each identif ied impact.
The maximum score would be 64 (2 x 2 x 2 x 2 x 2 x 2) and the minimum
score would be 1 (1 x 1 x 1 x 1 x 1 x 1).
A cut off of 16 marks is assumed to decide the signif icance of
environmental impacts.
The impacts having less than 16 marks are considered as insignif icant.
The impacts having 16 or more marks are considered as signif icant
environmental impacts. The weighted criteria is given in the table 4.3.
M/s SREEV ALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 4 Ant ic ipated Envi ronmenta l Impacts & Mit igat ion Measures
Page 4 - 17
Table 4.3 - Marking for Various Criteria
Sr.
No.
Criteria Classif icat ion
Type Marks Type Marks
1. Whether the environmental aspect
has potential to cause direct impact
or indirect ly.
Indirect 1 Direct 2
2. Whether the environmental aspect
would v io late legal / mandatory
requirement if uncontrol led
Not
Mandatory 1 Mandatory 2
3. Whether the l ikely environmental
impact wi l l be l imited to local
surroundings or i t would be wide
spread.
Local 1 W ide
spread 2
4. Whether the l ikely environmental
impact would be of a temporary
nature or permanent nature
depending on the toxic ity levels.
Temporary 1 Permanent 2
5 Whether the occurrence of the
environmental aspect and i ts l ikely
environmental impact wil l be of long
term durat ion or short term duration.
Short term 1 Long term 2
6 Whether mitigat ion measures
avai lable and can be adopted to
minimize the s ignif icant of the
impacts to permissible l imits.
Yes 1 No 2
4.6 Scores of all anticipated Environmental impacts after applying the marking criteria
The above criteria has been applied for al l the 64 numbers of identif ied
environmental impacts and the impact classif ication based on the criteria
is provided in the table 4.4.
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 4 Ant ic ipated Environmental Impacts & Mit igat ion Measures Page 4 - 18
Table 4.4: Matrix showing the scores of all Environmental impacts as per the criteria
CONSTRUCTION PHASE: -
S.
N.
Impact on
Environment Act ivity / Aspect Anticipated Impacts
Impact Classif ication
Total Marks M1 X
M2..XM6
Whether Signif icant Y/N
Direct (D) / Indirect ( ID)
Mandatory (M) / Not
Mandatory (NM)
Local(L)/ Widespread
(W)
Temporary(T)/ Permanent (P)
Long Term (LT) / short term
(ST)
Mit igation available
( Yes / No)
Marks Marks Marks Marks Marks Marks
D/ID M1 M/NM
M2 L/W M3 T/P M4 LT/ST
M5 Y/N M6
AIR ENVIRONMENT
1 Air
Site Clearances &
preparat ion, excavat ion
& inf ras truc ture
development
Dust emissions. D 2 NM 1 L 1 T 1 ST 1 Y 1 2 N
2 Air Construc t ion Act ivi t ies** Dust Emiss ions f rom construct ion act iv i t ies D 2 NM 1 L 1 T 1 ST 1 Y 1 2 N
3 Air
Point source emiss ions
f rom operat ion of DG
Sets
Part icu late Matter & Gaseous emissions
( including worst condit ion of operat ing a l l
DG sets)
D 2 M 2 W 2 T 1 LT 2 Y 1 16 Y
4 Air
L ine source emissions
f rom movement of
construct ion & other
vehic les, machiner ies.
Fugi t ive dust & gaseous emissions f rom vehic les exhaust
D 2 NM 1 W 2 T 1 LT 2 Y 1 8 N
5 Air Temporary s tay of construct ion workers
Impact on ambient a ir due to use of f i re
wood, coal, e tc. as fuel for domest ic
cook ing etc .
D 2 NM 1 L 1 T 1 ST 1 Y 1 2 N
WATER ENVIRONMENT
1 W ater
Site preparat ion &
inf rastruc ture
development
Use of large quant i ty of water for dust
suppress ion, consol idat ion & compact ion. D 2 NM 1 L 1 P 2 LT 2 Y 1 8 N
2 W ater Excavat ion for below
ground level structures Impacts on Hydrology due to dewater ing D 2 NM 1 L 1 P 2 LT 2 Y 1 8 N
3 W ater Construc t ion Act ivi t ies**
Impact on compet ing users due to large
consumpt ion of water for cur ing, dust
suppress ion, construct ion, domestic use
etc .
D 2 NM 1 W 2 P 2 LT 2 Y 1 16 Y
4 W ater
Loose excavated ear th
& loose construc t ion
mater ia ls at s i te
Contaminat ion of surface water body &
aquat ic l i fe D 2 NN 1 L 1 T 1 ST 1 Y 1 2 N
5 W ater storm water f rom the
s ite
Improper channel izat ion may lead to
contaminat ion of surface water & ground
water by non-point sources of pol lu t ion l ike
l i t ter , o i l & grease, loose earth
D 2 NM 1 L 1 T 1 ST 1 Y 1 2 N
6 W ater storm water f rom the
s ite
Clogging of storm water dra inage system
by s i l t & other mater ia ls may lead to
f looding condit ions
D 2 NM 1 L 1 T 1 ST 1 Y 1 2 N
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 4 Ant ic ipated Environmental Impacts & Mit igat ion Measures Page 4 - 19
7 W ater Temporary s tay of construct ion workers
Impact on surface / ground water qual i t y
due to untreated discharge of sewage &
sol id waste f rom the labor colony
D 2 M 2 L 1 T 1 ST 1 Y 1 4 N
8 W ater Temporary s tay of
construct ion workers
Impact on compet ing users due to
consumpt ion of publ ic supply / ground
water (resource loss)
D 2 NM 1 W 2 T 1 ST 1 Y 1 4 N
NOISE ENVIRONMENT
1 Noise
Movement o f const ruct ion
equipments &
machiner ies .
Noise due to heavy machinery for excavat ion D 2 M 2 L 1 T 1 ST 1 Y 1 4 N
2 Noise Construct ion Act iv i t ies** Noise & vibra t ion due to construct ion Act i v i t ies D 2 M 2 L 1 T 1 ST 1 Y 1 4 N
3 Noise Operat ion of DG Sets
Noise & Vibrat ion f rom DG Sets due to
inadequate acoust ic enc losure ( inc lud ing wors t
condi t ion of operat ing a l l DG sets)
D 2 M 2 W 2 T 1 LT 2 Y 1 16 Y
LAND ENVIRONMENT
1 Soi l In f ras t ructure
development Compact ion of so i l by ear th moving vehic les D 2 NM 1 L 1 T 1 ST 1 Y 1 2 N
2 Soi l S i te Clearance &
excavat ion Eros ion & modi f ica t ion o f sur face D 2 NM 1 L 1 T 1 ST 1 Y 1 2 N
3 Soi l excavated ear th & loose
construct ion mater ia ls Loss of topsoi l ( resource loss) D 2 NM 1 L 1 T 1 LT 2 Y 1 4 N
4 Soi l s torm water
Improper channel i zat ion may lead to loss of
fer t i le top so i l a long wi th sur face run-o f f and
subsequent loss of wate r ho ld ing and
in f i l t ra t ion capac i ty o f so i l
D 2 NM 1 L 1 T 1 LT 2 Y 1 4 N
5 Soi l Temporary s tay of
construct ion workers
Impact due to unt reated d ischarge of sewage &
Sol id waste in to the land D 2 NM 1 L 1 T 1 LT 2 Y 1 4 N
6 Soi l Construct ion waste &
MSW
Improper d isposal o f construct ion waste &
MSW into the land D 2 M 2 L 1 T 1 LT 2 Y 1 8 N
BIOILOGICAL ENVIRONMENT
1 Bio log ica l Si te Clearances &
Excavat ion
Loss of vegetat ion and loss of habi ta t o f faunal
spec ies ( resource loss) D 2 NM 1 L 1 P 2 LT 2 Y 1 8 N
2 Bio log ica l Construct ion Act iv i t ies** Vibrat ion due to movement / operat ion of heavy
machinery D 2 NM 1 L 1 T 1 ST 1 Y 1 2 N
3 Bio log ica l Temporary s tay of construct ion workers
Cut t ing of t rees, sh rubs etc . for procur ing f i re
wood by construct ion workers . ( resource loss) D 2 NM 1 L 1 P 2 LT 2 Y 1 8 N
SOCIO-ECONOMIC
1 Socio
Economic Temporary s tay of construct ion workers
Impact on nat i ve soc ia l fabr ic o f the s i te
surroundings l ike cu l tura l d ivers i t y, poss ib le
increase in ant i -soc ia l ac t iv i t ies etc .
D 2 NM 1 L 1 T 1 ST 1 Y 1 2 N
2 Socia l
Respons ib i l i ty Construct ion workers
Unhygienic s i te sani ta t ion fac i l i t ies may cause
heal th damage to construct ion workers D 2 M 2 W 2 T 1 LT 2 Y 1 16 Y
OTHERS
1 Aesthet ics Temporary s tay of construct ion workers
Construct ion of Improper / unaesthet ic labor
sheds/shel ters may impact aesthet ic
appearance of the s i te surroundings.
D 2 NM 1 L 1 P 2 ST 1 Y 1 4 N
2 Energy
Conservat ion Energy Consumpt ion
Use of energy in-ef f ic ien t bu i ld ing mater ia ls
may lead to h igher consumpt ion of e lec t r ic i t y in
a i r condi t ioned bui ld ings .
D 2 NM 1 W 2 P 2 LT 2 Y 1 16 Y
3 Energy
Conservat ion Energy Consumpt ion
Adopt ion of energy in-ef f ic ient vehic les , appl iances, l ights etc . may lead to wastage of energy
D 2 NM 1 L 1 T 1 ST 1 Y 1 2 N
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 4 Ant ic ipated Environmental Impacts & Mit igat ion Measures Page 4 - 20
4 Energy
Conservat ion Energy Consumpt ion
Improper or ien tat ion of the bui ld ing may lead to h igh energy consumpt ion due to h igh hea t ga in to the bui ld ing, dark zone & improper vent i la t ion
D 2 NM 1 L 1 T 1 ST 1 Y 1 2 N
5
Bui ld ing Mater ia l
Resource Conservat ion
Bui ld ing Mater ia l
consumpt ion
Use of far fe tched construct ion mater ia ls than
the loca l ly avai lab le construct ion mater ia ls may
lead to over explo i ta t ion of natura l resources &
increase in carbon foo tp r in t
D 2 NM 1 W 2 P 2 LT 2 Y 1 16 Y
6 Disaster
Management F i re & other hazards
Absence of proper f i re p rotect ion systems may
lead to f i re hazards D 2 NM 1 L 1 T 1 ST 1 Y 1 2 N
7 Disaster
Management F i re & other hazards
Absence of s ignages, mock dr i l ls & assembly
po ints D 2 NM 1 L 1 T 1 ST 1 Y 1 2 N
8 Disaster
Management F i re & other hazards
Absence of re levant s t ruc tura l safety measures
dur ing bui ld ing des ign may lead to damage to
bu i ld ings dur ing the na tura l ca lami t ies
D 2 NM 1 L 1 P 2 LT 2 Y 1 8 N
** Construction Activities (Foundation, Columns, beams, slab casting, brick work, plastering, flooring, electrical & plumbing works, painting & finishing) OPERATION PHASE: -
S
N
Impact on
Environment
Act ivity /
Aspect
Anticipated Impacts
Impact Classif ication
Direct (D) / Indirect ( ID)
Mandatory (M) / Not
Mandatory (NM)
Local(L)/ Widespread
(W)
Temporary(T)/ Permanent (P)
Long Term (LT) / short
term (ST)
Mit igation available
( Yes / No)
Total Marks
Obtained
Whether Signif ican
t or not
D/ID
Marks
M/NM
Marks
L/W
Marks
T/P
Marks
LT/ST
Marks
Y/N
Marks M1 X
M2..XM6 M1 M2 M3 M4 M5 M6
AIR ENVIRONMENT
1 Air On s i te Vehic le
Movement
Dust & gaseous emissions f rom vehic les
exhaust D 2 NM 1 L 1 P 2 LT 2 Y 1 8 N
2 Air
Point Source
emissions f rom
operat ion of DG
Sets
Part icu late Matter & Gaseous emissions
( including wors t condi t ion of operat ing a l l
DG sets)
D 2 M 2 W 2 T 1 LT 2 Y 1 16 Y
3 Air Munic ipal Sol id
W aste
Improper d isposal of sewage and MSW
may lead to odour & generat ion of gases
due to de-composi t ion
D 2 NM 1 L 1 P 2 LT 2 Y 1 8 N
WATER ENVIRONMENT
1 W ater water
consumpt ion
Impact on competing users due to
consumpt ion of publ ic supply / ground
water (resource loss)
D 2 NM 1 W 2 P 2 LT 2 Y 1 16 Y
2 W ater Operat ion of
HVAC Plant
Impact on competing users due to
consumpt ion of publ ic supply / ground
water as make-up water ( resource loss)
D 2 NM 1 W 2 P 2 LT 2 Y 1 16 Y
3 W ater sewage
Improper d ischarge of untreated sewage
may lead to impact on surface / ground
water qual i t y.
D 2 M 2 W 2 P 2 LT 2 Y 1 32 Y
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 4 Ant ic ipated Environmental Impacts & Mit igat ion Measures Page 4 - 21
4 W ater Munic ipal Sol id
W aste & Bio-
Medical W aste
Improper d isposal of MSW & BMW may
at trac t scavenger avifauna which may lead
to d issertat ions of nat ive avifauna
D 2 M 2 L 1 T 1 ST 1 Y 1 4 N
5 W ater e-waste
Improper storage & d isposal may lead to
leaching of heavy metals leading to
contaminat ion
D 2 M 2 W 2 P 2 LT 2 Y 1 32 Y
6 W ater Hazardous
W aste
Improper storage & d isposal may lead to
leaching of hazardous waste leading to
contaminat ion
D 2 M 2 W 2 P 2 LT 2 Y 1 32 Y
7 W ater storm water
Improper channel izat ion may lead to
contaminat ion of water body & c logging of
dra in may lead to f looding
D 2 NM 1 L 1 P 2 LT 2 Y 1 8 N
NOISE ENVIRONMENT
1 Noise Vehic le
Movement
Increase in Noise & Vibrat ion in
surrounding area D 2 NM 1 L 1 P 2 LT 2 Y 1 8 N
2 Noise Operat ion of
DG Sets
Noise & Vibrat ion f rom DG Sets due to
inadequate acoust ic enc losure D 2 M 2 L 1 T 1 ST 1 Y 1 4 N
3 Noise Operat ion of
HVAC Plant Noise & vibrat ion f rom HVAC Plant D 2 NM 1 L 1 P 2 LT 2 Y 1 8 N
LAND ENVIRONMENT
1 Soi l Munic ipal Sol id
W aste & Bio-Medical W aste
Improper d isposal of MSW & BMW may
lead to impact on land. D 2 M 2 L 1 P 2 LT 2 Y 1 16 Y
2 Soi l sewage Improper d ischarge of untreated sewage
may lead to impact on land. D 2 M 2 L 1 P 2 LT 2 Y 1 16 Y
3 Soi l e-waste
Improper storage & disposal may lead to
leaching of heavy metals leading to
contaminat ion
D 2 M 2 W 2 P 2 LT 2 Y 1 32 Y
4 Soi l Hazardous
W aste
Improper storage & disposal may lead to
leaching of hazardous waste leading to
contaminat ion
D 2 M 2 W 2 P 2 LT 2 Y 1 32 Y
5 Soi l Storm water Non-point sources of pol lu t ion l ike l i t ter ,
o i l & grease, loose ear th D 2 NM 1 L 1 P 2 LT 2 Y 1 8 N
6 Soi l s torm water
Clogging of storm water dra inage system
by s i l t & other mater ia l may lead to
f looding
D 2 NM 1 L 1 T 1 ST 1 Y 1 2 N
BIOLOGICAL ENVIRONMENT
1 Bio logical Vehic le
Movement
Increase in Noise & Vibrat ion in
surrounding area D 2 NM 1 L 1 T 1 ST 1 Y 1 2 N
2 Bio logical Munic ipal Sol id
W aste & Bio-
Medical W aste
Improper d isposal of MSW & BMW may
at trac t scavenger avifauna which may lead
to d issertat ions of nat ive avifauna
D 2 M 2 L 1 P 2 LT 2 Y 1 16 Y
OTHER ASPECTS
1 Aesthet ics Munic ipal Sol id
W aste & Bio-
Medical W aste
Improper d isposal of MSW & BMW may
lead to un-aesthet ic condit ions D 2 M 2 L 1 P 2 LT 2 Y 1 16 Y
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 4 Ant ic ipated Environmental Impacts & Mit igat ion Measures Page 4 - 22
2 Energy
Conservat ion Consumption of
Energy
Adopt ion of energy in-ef f ic ient vehic les ,
HVAC system, appl iances, l ights etc may
lead to wastage of energy
D 2 NM 1 W 2 P 2 LT 2 Y 1 16 Y
3 Energy
Conservat ion Consumption of
Energy
Non adopt ion of renewable sources of
energy l ike solar energy may lead to
increase dependency on publ ic supply may
lead to consumpt ion of energy by
compet ing users
D 2 NM 1 W 2 P 2 LT 2 Y 1 16 Y
4 Disaster
management Fire & other
hazards
Absence of tra ined personnel & mock dr i l ls
may lead to major f i re acc idents & non
maintenance of sys tem
D 2 NM 1 L 1 P 2 LT 2 Y 1 8 N
SOCIO- ECONOMIC ( ALL POSITIVE IMPACTS)
S.
No
.
Impact on
Environment
Activity /
Aspect
Anticipated Impacts
Impact Classif ication
Direct (D) / Indirect ( ID)
Posit ive (P) / Negative (N)
Local(L)/ Widespread
(W)
Temporary(T)/ Permanent (P)
Long Term (LT) / short
term (ST)
Mit igation available
( Yes / No)
Total Marks
Obtained
D/ID Marks
P/N Marks
L/W Marks
T/P Marks
LT/ST Marks
Y/N Marks M1 X
M2..XM6 M1 M2 M3 M4 M5 M6
1 Socio
Economic bus iness
act iv i t ies
Increased revenue to the State & Local Self
Government by way of taxes and dut ies leading to
inf rastruc ture development & bet ter c iv ic ameni t ies
D 2 P 1 W 2 P 2 LT 2 Y 1 16
2 Socio
Economic bus iness
act iv i t ies
Expans ion of ex ist ing hospita l ac t iv i t ies may lead to
increase in employment oppor tuni ty / new job creat ion
(d irec t & indirect) for the local community
D 2 P 1 L 1 P 2 LT 2 Y 1 8
3 Socio
Economic bus iness
act iv i t ies
Increased bus iness act iv i t ies at s i te may lead to
improved publ ic transport inf rastructure in the region
may improve the l i fe s tyle and connect iv i t y o f the local
community
D 2 P 1 W 2 P 2 LT 2 Y 1 16
4 Socio
Economic Medical
Fac i l i t y
Due to the development of hospi ta l project , the bet ter
medical t reatment fac i l i t y wi l l be avai lable to the local
populat ion
D 2 P 1 W 2 P 2 LT 2 Y 1 16
M/s SREEV ALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 4 Antic ipated Environmenta l Impacts & Mit igat ion Measures Page 4 - 23
4.7 List of significant Environmental impacts
Based on the cr iter ia of cut-off of 16 marks, the impacts having less than
16 marks are considered as insignif icant impact and the impacts having
16 or more marks are considered as signif icant environmental impacts.
Out of the total number of 64 Environmental impacts identif ied
(construct ion & operation phase together), after applying the above
mentioned signif icance criteria, 20 Nos. (6 environmental impacts during
construction phase & 14 environmental impacts during operation phase)
are considered to be signif icant impacts.
The l ist of signif icant impact is given below :-
Table 4.5 : List of significant impacts identified
Construction Phase
S.
No.
Impact on
Environment Act ivi ty / Aspect Ant icipated Impacts
1 A ir
Point source emissions
from operat ion of DG
Sets
Part icu la te Mat ter & Gaseous emissions
( includ ing wors t condit ion of operat ing al l DG
sets)
2 Water Construct ion Act ivi t ies**
Impact on compet ing users due to large
consumpt ion of water for cur ing, dust
suppression, construct ion, domest ic use etc.
3 Noise Operat ion of DG Sets
Noise & Vibrat ion f rom DG Sets due to
inadequate acoust ic enclosure ( inc lud ing
worst condit ion of operat ing al l DG sets)
4 Social
Responsib i l i ty Construc t ion workers
Unhygien ic s i te sani tat i on f ac i l i t i es may cause
heal th damage to construc t ion workers
5 Energy
Conservat ion Energy Consumpt ion
Use of energy in-eff ic ient bu i ld ing mater ia ls
may lead to h igher consumpt ion of e lect r ic i t y
in a ir condit ioned bui ld ings.
6
Bui ld ing Mater ia l
Resource Conservat ion
Bui ld ing Mater ial
consumpt ion
Use of far fe tched construct ion mater ia ls than
the loca l ly avai lab le construct ion mater ia ls
may lead to over explo itat ion of natura l
resources & increase in carbon footpr in t
** Construction Activities (Foundation, Columns, beams, slab casting, brick work, plastering, flooring, electrical & plumbing works, painting & finishing)
M/s SREEV ALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 4 Antic ipated Environmenta l Impacts & Mit igat ion Measures Page 4 - 24
Operation Phase: -
S.
N.
Impact on
Environment Activi ty / Aspect Ant icipated Impacts
1. Air Point Source
emissions f rom
operat ion of DG Sets
Part icu la te Mat ter & Gaseous emissions ( includ ing
worst condit ion of operat ing al l DG sets)
2. Water water consumpt ion Impact on compet ing users due to consumption of
publ ic supply / ground water ( resource loss)
3. Water Operat ion of HVAC
Plant
Impact on compet ing users due to consumption of
publ ic supply / ground water as make-up water
( resource loss)
4. Water sewage Improper d ischarge of untreated sewage may lead
to impact on sur face / ground water qual it y.
5. Water e-waste Improper storage & d isposal may lead to leaching
of heavy meta ls leading to contaminat ion
6. Water Hazardous W aste Improper storage & d isposal may lead to leaching
of hazardous waste leading to contaminat ion
7. Soi l Munic ipa l Sol id W aste & B io-Medical Waste
Improper disposal of munic ipa l so l id waste & bio-
medica l waste may lead to impact on land.
8. Soi l sewage Improper d ischarge of untreated sewage may lead
to impact on land.
9. Soi l e-waste Improper storage & d isposal may lead to leaching
of heavy meta ls leading to contaminat ion
10. Soi l Hazardous W aste Improper storage & d isposal may lead to leaching
of hazardous waste leading to contaminat ion
11. Biologica l Munic ipa l Sol id W aste
& B io-Medical Waste
Improper d isposal o f MSW & BMW may at t ract
scavenger avi fauna which may lead to
d isser ta t ions of nat ive avi fauna
12. Aesthet ics Munic ipa l Sol id W aste Improper d isposal o f MSW may lead to un-
aesthet ic condit ions
13.Energy
Conservat ion Consumption of
Energy
Adopt ion of energy in-eff ic ient vehic les, HVAC
system, appl iances, l ights e tc may lead to
wastage of energy
14.Energy
Conservat ion Consumption of
Energy
Non adopt ion of renewable sources of energy l ike
so lar energy may lead to increase dependency on
publ ic supply may lead to consumpt ion of energy
by compet ing users
4.8 Mitigation measures for the significant impacts identified
The mitigation measures for the signif icant impacts identif ied during
construction and operation phase are summarized in the Table 4.6 &
Table 4.7.
M/s SREEV ALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 4 Antic ipated Environmenta l Impacts & Mit igat ion Measures Page 4 - 25
Table 4.6 - Mitigation measures for the significant impacts identified during Construction Phase
Sr. No
Impact on Envir.
Anticipated Impacts Mitigation Measures
1 Air Particulate Matter & Gaseous emissions from DG Sets.
� Stack height as per CPCB Standards. � Promotion of use of cleaner fuel � All DG set should comply emissions
norms noti f ied by MoEF / CPCB.
2 Water
Impact on competing users due to large consumption of water for curing, dust suppression, construction, domestic use etc.
� To avoid wastage of cur ing water , following procedures are suggested: -
• Curing water should be sprayed on concrete structures: f ree f low of water should not be al lowed for cur ing.
• Af ter l iberal cur ing on the f irst day, al l concrete structures should be painted with curing chemical to save water . This wil l s top dai ly water curing.
• Concrete structures should be covered with thick c loth / gunny bags and then water should be sprayed on them. This would avoid water rebound and wi l l ensure sustained and complete curing.
• Ponds should be made using cement and sand mortar to avoid water f lowing away f rom the f lat surface while curing.
• Water ponding should be done on al l sunken slabs, th is would also highl ight the importance of having an impervious formwork.
� Estimation of daily water consumption based on the population, reuse and recycled options, quanti f icat ion of waste water , requirement of construction water, etc.
� Moni tor ing water use: Use of water meter conforming to ISO Standards would be insta l led at the inlet point of water uptake and at the discharge point to monitor the dai ly water consumption.
� Use of rain water for domestic purposes in the labour colony & for construction purposes.
� Use of treated water f rom STP of labour colony for construction purposes.
3 Noise
Noise & Vibrat ion from DG Sets due to inadequate acoustic enclosure
� Use of DG Sets wi th appropriate acoustic enclosures
� Use of ant i v ibrat ion pads
M/s SREEV ALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 4 Antic ipated Environmenta l Impacts & Mit igat ion Measures Page 4 - 26
4 Socio
Economic
Unhygienic s ite sanitat ion facil i t ies may cause health damage to construction workers
The objective is to ensure health and safety of the workers with ef fective provis ions for the basic faci l i t ies of sanitat ion, dr inking water , safety of equipments or machinery etc. Fol lowing are some of the recommendations:- � Comply with the safety procedures, norms
and guidel ines (as appl icable) as outl ined in the National Bui ld ing Code of India, Bureau of Indian Standards.
� Provide c lean dr inking water to a ll workers.
� Provide adequate number of decentral ized latr ines and ur inals.
� Guarding al l parts of dangerous machinery.
� Precautions for working on machinery. � Maintaining hoists and l if ts , l i f t ing
machines, chains, ropes and other l i f t ing tackles in good condition.
� Durable and reusable formwork systems to replace timber formwork and ensure that formwork where used is proper ly maintained.
� Ensuring that walk ing surfaces or boards at height are of sound construct ion and are provided wi th safety rai ls or belts.
� Provide measures to prevent f ires. F ire f ight ing ext inguishers and buckets of sand to be provided in the f ire prone area and elsewhere.
� Provide suff ic ient and suitable l ight for working during night t ime.
5 Energy
Conservat i on
Use of energy in-eff ic ient bui lding materia ls may lead to higher consumption of electr ici ty in a ir conditioned buildings.
� Use of bui ld ing materia l for roof , wal ls & glass ( R & U values) as per BEE for less heat gain in air conditioned buildings.
6
Bui lding Mater ia l
Resource Conservat i o
n
Use of farfetched construction materia l than local ly avai lable construction materia l may lead to over explo itat ion of natural resources & increase in carbon footprint
� Use of local ly avai lable construct ion materia ls.
** Construction Activit ies (Foundation, Columns, beams, slab casting,
brick work, plaster ing, f looring, electrical & plumbing works, paint ing &
finishing).
M/s SREEV ALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 4 Antic ipated Environmenta l Impacts & Mit igat ion Measures Page 4 - 27
Table 4.7 - Mitigation measures for the significant impacts identified during Operation Phase
Sr. No.
Impact on Env.
Anticipated Impacts Mitigation Measures
1 Air
Particulate Matter & Gaseous emissions ( including worst condition of operating al l DG sets)
� Stack height as per CPCB Standards. � Development of a dense belt (vegetat ion
buffer) in the project s ite. � Promotion of use of cleaner fuel � All DG set should comply emissions norms
noti f ied by MoEF / CPCB.
2 Water
Impact on competing users due to consumption of publ ic supply / ground water (resource loss) for domestic consumption in the campus
� Estimation of dai ly water consumption based on the populat ion, reuse and recycled options, quantif icat ion of waste water etc.
� Moni tor ing water use: Use of water meter conforming to ISO Standards would be instal led at the in let point of water uptake and at the discharge point to monitor the dai ly water consumption.
� Use of water saving devices / f ixtures: Low water consumption f ix tures l ike low f low f lushing systems, sensor based f ixtures, water less ur inals, tap aerators etc. to reduce the water usage.
� Instal lat ion of dual plumbing for using recycled water.
� Use of rain water
3 Water
Impact on competing users due to consumption of publ ic supply / ground water as make-up water for HVAC in the campus (resource loss)
� Estimation of dai ly water consumption based on the HVAC losses, reuse and recycled options.
� Moni tor ing water use: Use of water meter conforming to ISO Standards would be instal led at the in let point of water uptake and at the discharge point to monitor the dai ly water consumption in HVAC unit .
� Use of treated water for STP as make-up water in HVAC system.
� Use of rain water
4 Water
Improper discharge of untreated sewage may lead to impact on surface / ground water quali ty
� Treatment of sewage and recycl ing of the treated sewage and ensuring zero discharge.
� Sewage treatment p lant proposed. � Treatment unit with primary, secondary
and terr i tory treatment proposed
5 Water
Improper storage & disposal of e-waste may lead to leaching of heavy metals leading to contamination
� Storage of e-waste as per Rules and in an isolated area.
� Disposal of e- waste only to the author ized agency
� MoU with the approved agency to be made.
M/s SREEV ALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 4 Antic ipated Environmenta l Impacts & Mit igat ion Measures Page 4 - 28
6 Water
Improper storage & disposal may lead to leaching of hazardous waste leading to contamination
� Development of leachate proof intermediate hazardous storage facil i ty.
� Outsourcing of the hazardous waste to the Kerala Pollution Control Board approved agency & MoU to be made wi th the approved agency.
7 Soi l Improper disposal of MSW & BMW waste may lead to impact on land.
� Segregation of waste at source into medical, b iodegradable and non biodegradable waste by providing colored bins.
� Medical waste wil l be disposed of f through KSPCB approved vendors
� Disposal of biodegradable Munic ipal Sol id Waste by bio gas uni t .
� Disposal of non biodegradable recyclable waste to vendors.
� Disposal of iner t waste by land f i l l ing / back f i l l ing.
� For Bio-medical waste - Col lect ion & segregation at source by provid ing appropriate colour coded bins / containers as per the colour coding provided in the Bio-Medical Waste (Management & Handl ing) Rules.
� The Bio-medical waste f rom the proposed hospital would be outsourced through a Kerala State Pollut ion Control Board author ized agency (M/s Indian Medical Associat ion Goes Eco Fr iendly, IMAGE)
8 Soil Improper discharge of untreated sewage may lead to impact on land.
� Treatment of sewage and recycl ing of the treated sewage and ensuring zero discharge.
9 Soi l
Improper storage & disposal of e-waste may lead to leaching of heavy metals leading to contamination
� Storage of e-waste as per Rules and in an isolated area.
� Disposal of e- waste only to the author ized agency & MoU to be made wi th the agency.
10 Soil
Improper storage & disposal of hazardous waste may lead to leaching of waste leading to contamination
� Development of leachate proof intermediate hazardous storage facil i ty.
� Outsourcing of the hazardous waste to the Kerala Pollution Control Board approved agency & MoU to be made wi th the concerned agency.
M/s SREEV ALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 4 Antic ipated Environmenta l Impacts & Mit igat ion Measures Page 4 - 29
11 Biological
Improper disposal of MSW & BMW may attract scavenger avifauna which may lead to dissertat ions of nat ive avifauna
� Segregation of waste at source into medical, b iodegradable and non biodegradable waste by providing colored bins.
� Disposal of biodegradable Munic ipal Sol id Waste by bio gas uni t & bio-bin system.
� Disposal of non biodegradable recyclable waste to vendors.
� Disposal of iner t waste by land f i l l ing / back f i l l ing.
� Plantation of nat ive species of trees / shrubs / herbs / grass for enhancement of avifauna
� Conservation of the exist ing trees wherever possible.
� Plantation of f ruit bearing trees to enhance the avifauna.
� For Bio-medical waste - Col lect ion & segregation at source by provid ing appropriate colour coded bins / containers as per the colour coding provided in the Bio-Medical Waste (Management & Handl ing) Rules.
� The Bio-medical waste f rom the exist ing hospital outsourced through a Kerala State Pollution Control Board author ized agency (M/s Indian Medical Association Goes Eco Friendly, IMAGE) and the same arrangement wil l be continue for expansion facil i ty also.
12 Aesthet ics Improper disposal of MSW may lead to un-aesthetic condit ions
� Segregation of waste at source into biodegradable and non biodegradable waste by provid ing colored bins.
� Disposal of biodegradable Munic ipal Sol id Waste by bio gas uni t .
� Disposal of non biodegradable recyclable waste to vendors.
� Disposal of iner t waste by land f i l l ing / back f i l l ing.
13 Energy
Conservation
Adoption of energy in-eff ic ient vehic les, HVAC system, appliances, l ights etc may lead to wastage of energy
� Use of Euro-II I Standard vehic les. � HVAC system and appl iances with 5 Star
Rating as per BEE.
M/s SREEV ALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 4 Antic ipated Environmenta l Impacts & Mit igat ion Measures Page 4 - 30
14 Energy
Conservation
Non adoption of renewable sources of energy l ike solar energy may lead to increase dependency on publ ic supply may lead to consumption of energy by competing users
� Use of Solar energy for water heating � Use of solar energy for common area
light ing in parks and in streets. � Use of solar power plant for common area
light ing in campus.
*******************************************************************************
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 5 Analysis of Al ternat ives (Technology and Site) Page 5 - 1
5.0 ANALYSIS OF ALTERNATIVES (TECHONOLOGY AND SITE)
5.1 Introduction
M/s Sreevalsam Educational Trust proposed an expansion of exist ing
Hospital cum Medical Col lege project at Edappal Vil lage, Ponnani Taluk,
Malappuram District, Kerala. The plot area of the Hospital cum Medical
College Project is 9.4534 ha (94,534.56 sq. m.) and the total built -up
area is 1,38,937.50 sq. m. (exist ing 53,889.72 sq.m. + proposed
85,047.78 sq.m.). The building construct ion of 53,889.72 sq.m. of the
project is already completed.
The present project is one of the more proactive side of environmental
assessment – enhancing the project through examining opt ions instead of
only focusing on the more defensive task of reducing adverse impacts of a
single opt ion of the project. This requires systematic comparison of the
feasible alternat ives for technology and operat ional alternatives.
Alternat ives are compared in terms of their potential environmental
impacts, capital and recurring costs, suitabi lity under local condit ions etc.
For examining the alternatives for carrying out a project, the following
aspects should be kept into consideration:
(i) Type of the alternatives.
(i i) Environment impacts associated with each alternative.
(i i i ) Rationale for select ing the preferred alternative.
This Chapter deals with the analysis of alternat ives (technology and site)
( if any).
5.2 Alternative Sites
The construct ion of new buildings are within the existing plot area of
9.4534 hectares.
The project proponent considering the need of the project at that area,
hence no alternat ive site is required for the project. The reasons
favorable for sett ing-up this project is located at Edappal Vil lage, Ponnani
Taluk, Malappuram District, Kerala are :
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 5 Analysis of Al ternat ives (Technology and Site) Page 5 - 2
� The project wil l cater to the demand for economical and better
hospital and inst itutional faci l ity.
� The site is located in high medical services demand area.
� There wil l be easy access to the patients / staff / local populat ion
for fulf i l l ing their medical demand being near to the residence /
off ice / work station to avail the facil i ty.
� The proposed site is found to be away from any ecologically
sensit ive / protected areas.
Owing to the various above advantages, the site was selected for the
development of facil i t ies / act iv it ies.
There are no archaeological, historical, cultural or defense instal lations
within 10 km from the project boundary. There is no national park or
wi ldl i fe sanctuary / ecologically sensit ive area within 10 km from the
project boundary. The site area is not part of any f lood plain nor in the
land sl ide vulnerable zone as per the hazard zonation map published by
State Disaster Management Authority. The proposed project is an
expansion of exist ing hospital cum medical col lege. There is no resident /
human sett lement within the site and hence there is no rehabili tation. Due
to the above mentioned reasons, there is no need for alternative site.
5.3 Alternatives in Technology
The project relates the construct ion and development of hospital cum
medical college project with supporting infrastructural facil it ies for
creat ing faci l it ies with an easy access to the people as there is high
demand of medical cum institutional building in the area. The project
proponent has adopted state-of-the-Art Technology considering the
requirement of the project and environmental aspects related to the
construction and operation of the project.
*******************************************************************************
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 6 Environment Monitor ing Program Page 6 - 1
6.0 ENVIRONMENT MONITORING PROGRAM
6.1 Introduction
The purpose of the monitor ing program is to ensure that the specif ied
mitigative measures are performing well and leading to the desired
benefits for the target area and its populat ion. To ensure the effective
implementat ion of the EMP and gauge the eff iciency of the mitigat ive
measures, monitor ing shall be undertaken both during the construction
and operation phase of the proposed expansion of hospital project.
6.1.1 Performance Indicators (PIs)
The physical, biological and social indicators are generally particular
signif icance to the construction projects are:-
• Air quality
• Water quali ty
• Noise levels
• Solid Waste Management
• Replantat ion success / survival rate
The Indicators that are found to be signif icant for the assessment study of
this development are as follows:-
• Water Quality
• Air Quali ty
• Noise levels
• Flora
To ensure the effect ive implementat ion of the mit igation measures and
environmental management during construction and operation phase of
project, it is essential that an effective Environmental Monitoring Plan be
designed.
6.1.1.1 Water Quality Monitoring
The physical, chemical & biological parameters recommended for analysis
of water qual ity relevant to the proposed expansion project as per the
required parameters. The locations, duration and the pollution parameters
to be monitored are detai led in the Environmental Monitor ing Plan. The
results of analysis are to be compared against IS 10500 for ground water
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 6 Environment Monitor ing Program Page 6 - 2
samples, and general standards of discharge or as per SPCB
specif icat ions for STP treated water.
6.1.1.2 Ambient Air Quality (AAQ) Monitoring
Ambient air quality parameters recommended for monitoring with regard
to constructional activ it ies are PM10 & PM2 .5, SO2 , NO2 & CO. Monitoring
shall be carr ied out once in a seasons in accordance to the National
Ambient Air Quantity Standards. The locations with the pol lution
parameters to be monitored are detailed out in the Environmental
Monitoring Plan.
6.1.1.3 Noise Level Monitoring
The measurements of noise levels wil l be carried out at al l designated
locations in accordance to the ambient Noise Standards formulated by
MoEF as given. Noise level wil l be monitored on twenty-four hourly basis.
Noise should be recorded at “A” weighted frequency using a slow t ime
response mode of the measuring instrument.
6.1.1.4 Success of Vegetation
To ensure the proper maintenance and monitoring of the proposed
plantation act ivit ies, a regular survey of the survival rate of the planted /
transplanted trees is being proposed up-to a period of 5-7 years from the
start of operat ion of the project.
The measurement location, durat ion and the pollution parameters to be
monitored are detailed in the Environmental Monitoring Plan (Table 6.1
& 6.2).
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 6 Environment Monitor ing Program Page 6 - 3
Table 6.1 - Environment Monitoring Action Plan
Sr.
No.
Potential
impacts Action
Parameters for
monitoring
I. Construction Phase
1.
Air Emissions
All equipments to be operated
within specif ied design
parameters
Random checks of
equipment logs/manuals
Vehic le tr ips to be minimized to
the extent possible
Vehic le logs
Any dry, dusty materia ls to be
stored in sealed containers or
prevented f rom blowing.
Absence of stockpiles or
open containers of dusty
materials.
Compaction of soi l dur ing various
construction act iv i t ies
Construction logs
Ambient air quali ty wi thin the
premises of the proposed unit to
be monitored.
The air qual i ty wi l l
conform to the standards
for PM1 0 , PM2 .5 , SO2 and
NO2 , CO
2.
Noise
List of a ll noise generat ing
machinery onsite along with age
to be prepared. Equipment to be
maintained in good working order.
Equipment logs, noise
reading
Night working is to be minimized. Working hour records
Generation of vehicular noise Maintenance records of
vehic les
Implement good working practices
(equipment select ion and s it t ing)
to minimize noise and also reduce
i ts impacts on human heal th (ear
muffs, safe distances, and
enclosures).
Site working practices
records, noise reading
No machinery running when not
required.
Acoustic muff lers / enclosures to Muff lers / enclosures in
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 6 Environment Monitor ing Program Page 6 - 4
Sr.
No.
Potential
impacts Action
Parameters for
monitoring
be provided in large engines place
Noise to be monitored in ambient
air within the plant premises.
Noise reading
The noise level wi l l not exceed
the permissible l im it both during
day and night t imes.
All equipments operated with in
specif ied design parameters.
Random checks of
equipment logs / manuals
Vehic le tr ips to be minimized to
the extent possible
Vehic le logs
3.
Waste water
Discharge
No treated or untreated discharge
to be made to surface water,
ground water or soi l
No discharge hoses in
vic ini ty of watercourses
4.
Soil Erosion
Minimize area extent of s i te
c learance, by staying with in the
def ined boundaries and to avoid
steep s lopes
Site boundaries not
extended / breached as
per plan document
Protect topsoi l s tockpi le where
possible at edge of s i te
Effective cover in p lace
5.
Drainage and
eff luent
Management
Ensure drainage system &
specif ic design measures are
working ef fectively. The design to
incorporate exist ing drainage
pattern and avoid any disturbing.
Visual inspection of
drainage and records
thereof
6.
Waste
Management
Implement waste management
plan that identif ies and
character izes every waste ar ising
associat ing wi th proposed
activi t ies and which identif ies the
procedures for collection handling
& disposal of each waste arising.
Comprehensive waste
management plan in
place and avai lable for
inspection on s ite.
Compliance with MSW
Rules and Hazardous
Waste (Management and
Handling Rules), 2016.
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 6 Environment Monitor ing Program Page 6 - 5
Sr.
No.
Potential
impacts Action
Parameters for
monitoring
The construction &
demoli t ion waste
management ru les, 2016
wi l l be follow during
construction phase.
7. Non-rout ine
events and cool
dental releases
Plan to be drawn considering
likely emergencies and steps
required to prevent / l imit
consequences
Mock dr i l ls and records
of the same
8.
Environmental
Management
Cell /Unit
The Environmental Management
Cell / Unit is to be set up to
ensure implementat ion and
monitor ing of environmental
safeguards.
Formation of
Environment
Management Cell by the
project proponent
I I. Operat ional Phase
1.
Air Emissions Stack emissions f rom DG set to
be optimized and monitored
The ambient air qual i ty
wi l l conform to the
standard for PM1 0 &
PM2 . 5 SO2 , and NOx, CO
Ambient air quali ty wi thin the
premises of the proposed unit to
be monitored.
Exhaust f rom vehic les to be
minimized by use of fuel ef f ic ient
vehic les and well maintained
vehic les having PUC cert i f icate.
The ambient air qual i ty
wi l l conform to the
standards for PM1 0 &
PM2 . 5 as given by PCC*
Vehic les logs to be
maintained
Promotion of cycle tracks Providing eff ic ient cyc les
to the staf f & vis i tors by
the proponent.
Promotion of water transport Scheduled maintenance
Promotion of pedestr ian walkways
& pathways
Scheduled maintenance
of pedestr ian walkways &
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 6 Environment Monitor ing Program Page 6 - 6
Sr.
No.
Potential
impacts Action
Parameters for
monitoring
pathways
Vehic le tr ips to be minimized to
the extent possible
Vehic le logs
2. Noise Noise generated f rom operation
of DG set to be optimized and
monitored DG sets to generate
less than 75 dB(A) Leg at 1.0 m
f rom the source DG sets are to be
provided at service bui lding with
a acoustic enclosures with height
of chimney above roof level or as
specif ied by SPCB
Maintain records of
vehic les
Generation of vehicular noise Maintain records of
vehic les
3. Wastewater
Discharge
No untreated discharge to be
made to surface water,
groundwater or soi l
No discharge hoses in
vic ini ty of watercourses
4.
Storm water
Drainage
Management
Ensure storm water drainage
system and specif ic design
measures are working ef fect ively.
Design to incorporate exist ing
natural drainage pattern and
avoid disturbing the same.
Visual inspection of
drainage and records
thereof
5.
Indoor a ir
contamination
Contaminants such as CO, CO2
and VOCs to be reduced by
providing adequate venti lat ion.
Monitor ing of indoor air
contaminants such as
CO, CO2 and VOCs
6.
Energy Usage
Energy usage for air -condit ioning
and other activi t ies to be
minimized Conduct annual energy
audit for the bui ldings
Findings of energy audi t
report
7.
Emergency
Fire protection and safety
measures to take care to f ire and
Mock dr i l l records, on
site emergency plan,
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 6 Environment Monitor ing Program Page 6 - 7
Sr.
No.
Potential
impacts Action
Parameters for
monitoring
preparedness,
such as f ire
f ight ing
explosion hazards to be assessed
and steps taken for their
prevention.
evacuation plan
8.
Environment
Management
Cell /Unit
The Environment Management
Cell /Unit to be set up to ensure
implementat ion and monitor ing of
Environmental safeguards
Formation of
Environment
Management Cell by the
project proponent
9 Waste
Management
Implement waste management
plan that identif ies and
character izes every waste ar ising
associat ing wi th proposed
activi t ies and which identif ies the
procedures for collection handling
& disposal of each waste arising.
Comprehensive waste
management plan in
place and avai lable for
inspection on s ite.
Compliance with MSW
Rules and Hazardous
Waste (Management and
Handling Rules), 2016.
Being a hospi tal project,
the project wil l fol low the
compliance wi th Bio-
medical waste
(Management and
Handling Rules).
Also, fol low the E-waste
Management Rules for
the disposal of E-waste
from the s ite.
*especial ly at locat ion AQL (where maximum GLC concentrat ion was
predicted through AAQ modeling).
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 6 Environment Monitor ing Program Page 6 - 8
Table 6.2: Environment Monitoring Plan with Budgetary Allocation
CONSTRUCTION PHASE
Sr.
No. Particulars Parameters Frequency
Approx.
Recurring cost
/ Annum
(Rs. In Lacs)
1. Ambient Air
(5 locations)
PM1 0 & PM2 . 5 ,
SO2 , NO2 , CO
Once in a
season 2.0
2. Pond water & Well water As per IS :
10500
Once in a
season 3.0
3. Noise Level
(5 locations)
24 Hrs. Noise
Level
Once in a
season 0.8
TOTAL 5.80
OPERATION PHASE
Sr.
No. Particulars Parameters Frequency
Approx.
Recurring
Cost / Annum
(Rs. In Lacs)
1. Ambient Air
(5 locations)
PM1 0 & PM2 .5 ,
SO2 , NO2 , CO
Once in a
season 2.00
2. Stack Emission
of D.G. sets SPM, SO2 , NOx
Once in a
year 0.5
3. Treated Water
f rom STP / ETP
pH, BOD, COD, Oil &
Grease, TSS,
bacter iological
parameters
Once in a
month 1.0
4. Stored rain water
& Well water As per IS : 10500
Once in a
season 3.0
5. Noise Level 24 Hrs. Noise Level Once in a
season 0.8
6. Ecological
monitor ing
Floral & faunal
species
Once in
three years 2.0
TOTAL 9.30
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 6 Environment Monitor ing Program Page 6 - 9
6.2 Data Management
The monitoring shall be carried out through MoEF / NABL approved
laboratory. All results shall be maintained at the project s ite.
6.3 Reporting Schedule
The environment management cell shall be responsible for t imely conduct
of the monitor ing activit ies. The results of the analysis shall be intimated
to the project head. Any anomaly in test results shall be investigated into
and proper correct ive actions shall be undertaken.
A complaint register shall also be maintained to note any complaints from
the Sreevalsam Educational Trust or any other stakeholder. Corrective
act ions taken against the complaints shall also be noted.
6.4 Emergency
Alarming levels of pollutants in any of the monitored component may raise
alarm in the hospital campus. However, such information should be made
available to the occupants through not ices and with the help of Project
Management Cell. The latter may also be consulted on necessary steps to
be taken on an immediate and long term basis to t ide over the problem.
*******************************************************************************
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 7 Addit ional Studies Page 7 - 1
7.0 ADDITIONAL STUDIES
7.1 Introduction
This chapter broadly looks at various aspects related to Risk & Disaster
Management, Resource & Energy Conservation and Traff ic Impact
Assessment Study, Social Impact, Corporate Environment Responsibi l ity
(CER) activit ies, Rehabil i tat ion & Resett lement (R&R) Action Plan and
Public Hearing.
7.2 Risk Assessment and Disaster Management Plan
7.2.1 Need and Plans
The instant project is expansion of existing hospital cum medical col lege
project encompasses the staff / patient / visiting, medical students of a
large number of people in it . The development project also involves
instal lat ion of various structures and machineries that meet the comfort
and need of its populat ion but may also pose serious threat to the
occupants in case of accidents. It is thus considered necessary to carry
out a risk assessment and prepare a disaster management plan for the
project.
The planning and construct ion of the buildings fol low all the safety norms,
it may not be always possible to total ly el iminate the risks of eventuali t ies
and fai lures of equipment or human errors. An essential part of major
hazard control has therefore, to be concerned with mit igat ing the effects
of such emergency and restoration of normalcy at the earliest.
The overall object ive of an Emergency Response Plan (ERP) is to make
uses of combined resources at s ite and outside to achieve the following:
1. To localize the emergency and if possible el iminate it ;
2. To minimize the effects of the accident on people and property;
3. Effect the rescue and medical treatment of casualt ies;
4. Safeguard other people;
5. Evacuate people to safe areas;
6. Informing and collaborating with statutory authorit ies;
7. Init ial ly contain and ult imately bring the incident under control;
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 7 Addit ional Studies Page 7 - 2
8. Preserve relevant records and equipment for the subsequent enquiry
into the cause and circumstances of the emergency;
9. Investigat ing and taking steps to prevent reoccurrence
The ERP is therefore related to identif ication of sources from which
hazards can arise and the maximum credible loss scenario that can take
place in the concerned area. The plan taken into account the maximum
credible loss scenario - act ions that can successfully mitigate the effects
of losses/ emergency need to be well planned so that they would require
less effort and resources to control and terminate emergencies, should
the same occur. Main hazards ident if ied for the project include hazards
pertaining to f ires in buildings and f ire in diesel storage areas, earthquake
and LPG leakage and an ERP pertaining to these is described in the
following sect ion.
7.2.2 Response in Case of Earthquake
Response Procedures for Occupants
If indoors:
1. Take cover under a piece of heavy furniture or against an inside wall
and hold on.
2. Stay inside: The most dangerous thing to do during the shaking of an
earthquake is to try to leave the building because objects can fal l on
you.
If outdoors:
Move into the open, away from buildings, street lights and ut il i ty wires.
Once in the open, stay there unti l the shaking stops.
If in a moving vehicle:
Stop quickly and stay in the vehicle. Move to a clear area away from
buildings, trees, overpasses, or ut i l ity wires. Once the shaking has
stopped, proceed with caut ion. Avoid bridges or ramps that might have
been damaged by the quake.
After the quake
1. After the quake be prepared for aftershocks.
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 7 Addit ional Studies Page 7 - 3
2. Although smaller than the main shock, aftershocks cause addit ional
damage and may bring weakened structures down. Aftershocks can
occur in f irst hours, days, weeks, or even months after the quake.
Help injured or trapped persons.
1. Give f irst aid where appropriate. Do not move seriously injured
persons unless they are in immediate danger of further injury. Call for
help.
2. Remember to help those who may require special assistance-- infants,
the elderly, and people with disabi lit ies.
3. Stay out of damaged buildings.
4. Use the telephone only for emergency calls.
Response Procedure for Emergency Team
1. Formulate an Emergency Response Team for earthquake response
2. Using the public address system, inform occupiers of response
procedures discussed above.
3. Inform the necessary authorit ies for aid
4. Ensure no residents are stuck beneath any debris, in case of a
structural fai lure.
5. Ensure that all residents standing outside near the buildings are taken
to open areas.
6. Ensure that the f irst aid ambulance and f ire tender vehicles are
summoned if necessary.
7. Inform the nearby hospitals if there are any injur ies.
8. Check the ut i l i t ies and storage tanks for any damage.
7.2.3 Status on natural disasters w.r.t. site and surroundings
There is no reported incident of any landslide, earthquake, cloud burst in the
project v icinity.
7.2.4 Response for LPG Leakage
1. The affected area should be evacuated and cordoned off immediately
2. Init iate an Emergency Response Team for LPG leakage.
3. Shut down the main valves in the gas bank, i f any in the kitchen etc.
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 7 Addit ional Studies Page 7 - 4
4. Ensure that only concerned personnel are present in the affected area
and al l other personnel and visitors are moved to the nearest assembly
points.
5. Rescue trapped personnel, also check if any personnel are
unconscious in the area and immediately move them outside and
provide f irst aid. Ambulance should be summoned to take injured
personnel to the hospital.
6. Personnel in the nearby buildings to close al l doors and windows to
prevent entry of the leaked gas.
7. Source of leakage to be traced and isolated from all other areas. And if
required use pedestal fans to bring down the gas concentration.
8. In case of a f ire fol low the instructions prescribed in case of f ire.
7.2.5 Response in case of Fire
1. Required response during in the event of a f ire should be described in
signs located in the lobby.
2. On sighting f ire, it should be immediately informed to the environment
manager giving the exact location and type of f ire in detail .
3. Init iate the Emergency Response Team for f ires.
4. If the f ire is small, engage in extinguishing the f ire using the nearest
f ire extinguisher.
5. Guide the Emergency Response Team staff to the emergency
assembly point.
6. The Emergency Response Team should immediately inform the nearest
dispensary and security force. If required a f ire tender should be
summoned.
7. The response team should immediately move to the point of f ire and
take al l necessary steps to stop the f i re. If the f ire is not control lable
and spreads then the manager in charge should inform the district
authorit ies and call for external help.
8. The Emergency Response Team wil l provide immediate rel ief to the
injured residents at the scene of incident. Any injured persons should
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 7 Addit ional Studies Page 7 - 5
be evacuated on priority to the dispensary or one of the nearest
hospitals based on their condit ion.
Instructions for Occupants
1. Get out of buildings as quickly and as safely as possible.
2. Use the stairs to escape. When evacuating, stay low to the ground.
3. If possible, cover mouth with a cloth to avoid inhaling smoke and
gases.
4. Close doors in each room after escaping to delay the spread of the f ire.
5. If in a room with a closed door.
6. If smoke is pouring in around the bottom of the door or if i t feels hot,
keep the door closed.
7. Open a window to escape or for fresh air while await ing rescue.
8. If there is no smoke at the bottom or top and the door is not hot, then
open the door slowly.
9. If there is too much smoke or f ire in the hall , slam the door shut.
10. Stay out of damaged buildings.
11. Check that al l wiring and ut il i t ies are safe.
A state of the art f ire f ighting system is proposed for the project to
prevent and control f ire outbreaks. The f ire f ight ing system wil l consist of
portable f ire ext inguishers, hose reel, wet riser, yard hydrant, automatic
sprinkler system, and manual f ire alarm system. The buildings wil l also be
provided with automatic f ire detection and alarm system. The format for
contact detai ls during emergency is given below :-
Sr. No. Name of agency Contact nos.
1. Police Station
2. Nearest other Medical Col lege / Hospital
3. Fire Station
4. Distr ict Collector, Malappuram
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 7 Addit ional Studies Page 7 - 6
In the event of occurrence of any such situat ion or condit ion in
Malappuram District, the Distr ict Collector, inter alia the chairman of the
Distr ict Disaster Management Authority (DDMA), has the authority to
exercise al l of the powers or any of the powers vested upon on him for
disaster preparedness /mit igation / or any such other activit ies as per the
DM ACT 2005 (District Disaster Management Authority, (DDMA) has the
authority to conceive, test and implement a District Disaster Management
Plan in accordance with the section 30 (2) I , i i & i i i of the DM act 2005 to
ensure effective management and response to any disaster.)
The structure of f low chart of Distr ict Disaster Management Authority
(DDMA) is given below Figure 7.1. The Act ion plan for crisis management
in District is provided in Figure 7.2. The l ist of names of various
funct ionaries with designation and telephone numbers shall be provided
as depicted in Figure 7.3,
Figure 7.1 Flow Chart of District Disaster Management Authority (DDMA)
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 7 Addit ional Studies Page 7 - 7
Figure 7.2 – Flow chart of Action plan for crisis management in District
Figure 7.3 : Flow chart of Incident Response Team
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 7 Addit ional Studies Page 7 - 8
Manmade disaster management of f ire :-
Description Details
No. of l if ts with capacity 4 nos X 15 passengers
= 60 Passengers
8 nos X 6 Passengers
= 48 Passengers
No. of stretcher l if ts with capacity 4 nos. x 20 Passengers = 80
passengers
No. of Fire exists with width of f ire exits 4 nos with 1.2 m wide
Distance from the farthest point to the
nearest f ire exit
33 m
No. of assembly points with area and no.
of persons the assembly point can
accommodate
788 sq.m assembly area to
accommodate about 2364
persons
Total no. of automatic sprinklers 1925
Total no. of f ire detectors / alarms 1370
Total no. of hooters 72
Name of nearest f i re stat ion
(Name & aerial distance)
Ponnani f ire stat ion
(about 9 km, W)
Relevant NBC code to be fol lowed NBC – Part 4
The project has obtained Fire NOC from the Fire & Rescue Department,
Govt. of Kerala and follow the norms.
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 7 Addit ional Studies Page 7 - 9
7.3 Resource Conservation
7.3.1 General approach
The proposed project is an expansion of exist ing hospital cum medical
college campus project will lead to uti l izat ion of various natural resources.
As an environmentally responsible corporate, the project proponent
endeavor to conserve these resources by judicious management and
recycling and strive to build up these resources where possible.
7.3.2 Water Resources – The project will use water supply and the stored
rain water tanks / ponds with total cumulat ive storage capacity of about
5,000 KL for of the project. Following means are proposed to be adopted
for conservat ion of this life sustaining resource:
• Minimum Ground water withdrawal: As informed, the present
project is a multi-storied resident ial building project. The exist ing
buildings as well as for proposed buildings have provision of storage of
rain water through tanks, therefore the water requirement of the site wil l
have minimal dependency of water from groundwater abstraction. As per
the classif icat ion by the CGWA, Ponnani Block in Malappuram district is
declared as “Safe Zone”. Hence the ground water available in the region
is ensure and to use of domestic purposes.
• Reduced use of water: To further minimize the use of avai lable
freshwater, various water eff icient f ixtures low f low f ixtures may be
provided such as Low f low f lushing systems, sensor based f ixtures,
waterless urinals, tap aerators.
• Treatment and Recycling: The wastewater generated from the
project site will be treated through Sewage Treatment Plant upto tert iary
level. This wil l enable the treated water from STP will be used for
f lushing, landscaping, boiler & for make-up water for cooling towers
attached with HVAC system requirements thereby reducing the
requirement of freshwater for these purposes.
• Rainwater harvesting: The increased hard surface of the proposed
project increases the runoff as compared to the otherwise vacant land. I t
is proposed to harvest this rainwater runoff while reducing the burden of
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 7 Addit ional Studies Page 7 - 10
storm water management of the project site. The stored rain water (in
tanks and pond) after treatment will be used to meet Non-f lushing
requirement. Also rain water harvest ing pits are constructed within the
site to recharge the ground water level.
7.3.3 Construction materials: As informed earl ier, the construction work
for the building was part ial ly completed. For the expansion purposes, the
project wil l require various kinds of natural construction materials such as
sand, gravel etc. These materials will procured from local market as per
requirement. This will also result in cost-eff iciency. Excavated soil from
the project s ite wil l used within the site. Country made bricks replaced
with cement blocks / hollow blocks. River sand replaced with
manufacturing sand from crusher.
7.3.4 Top soil as a resource: The top soil f rom the site was conserved.
The top soil from the areas where excavation carried out used for
landscaping within the site. There is exposed soil without vegetative cover
so as to prevent top soil erosion due to wind or by run-of f . The excavat ion
of earthwork wil l be done for the foundation of structures. The total
excavated of earth is 7,300 cum. The top soil (730 cum) which is fert i le
wi ll be kept at site for landscaping work. Part of the excavated soil will be
used for back f i l l ing work (4,380 cum) for site leveling and the remaining
quantity of 2190 cum wil l be used for internal road construct ion work.
Country made bricks replaced with cement blocks / hollow blocks
7.3.5 Energy as a resource: To conserve the energy resources, good
pract ices wil l be followed during the operation phase such as turning off
l ights and equipments when not in use, ensuring fuel eff iciency of motors
and vehicles through proper maintenance and minimal work at night. The
principles of energy conservation wil l also be embedded in the building
through use of energy eff icient f ixtures, maximum availabil ity of natural
l ight and use of solar energy.
It is proposed to install 200 KW solar l ight ing, 5000 Ltrs solar water
heaters.
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 7 Addit ional Studies Page 7 - 11
• Energy saving details from LED l ightings :-
Particulars Qty Energy Requirement as per Conventional l ight ing (100 watt)
Energy Requirement as per CFL/ LED
light ing (15 watt)
Total Energy Savings / day
Lighting Points
1036 1450 kWh/day 217 kWh/day 1233 kWh/day (85% saving)
• Solar l ight ing in green areas and in open parking :-
Particulars Qty Energy Requirement as per Conventional Systems (24 Nos.)
Energy Requirement after solar
l ight ing (24 nos.)
Total Energy Savings / day
Total no. of l ight ing points
60 144 kWh/day (@200 watts, 12 hrs. operation)
Nil 144 kWh/day (100 % saving)
• Other energy saving items :-
Roof (Area-3200M2) RCC with Thermal insulat ion
Saving 0.3 2lakhs kWh per year
Roof (Area 2500M2) Double glass with air cavity
Saving 2.5akhs kWh per year
High eff iciency Transformers Savings 2.2 lakhs kWh per year
7.4 Traffic Impact Assessment
Traffic and Access
The project site is within the Panchayat l imits of Edappal Grama
Panchayat. The nearest town is Edappal town which is about 2 km away
(N) from the site and the nearest city is Kozhikode city and is located
about 60 km (NW). The Ponnani taluk is located about 9 km in west
direction.
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 7 Addit ional Studies Page 7 - 12
The project would provide vehicle parking facil it ies within the project
premises. The parking plan for this project would follow KPBR guidel ines.
The total number of parking provided wil l be 1,184 Cars + 1,409
Two-wheelers within the site. There are provision of two separate wide
entry / exit point for the project for easy & smooth vehicular movement.
The suff icient parking provisions are made with the complex so that the
patient, students, vis itors & staff in hospital cum medical col lege wi ll not
disturb due to vehicular movement / parking.
The access to the project si te is from 10 m wide & 8 m wide road in the
northern direction of the site which are well connected to Thrissur-
Kutt ippuram Road located at about 1 km from the site in northern
direction.
The nearest National Highway is NH-17 (Edappally-Panvel Highway) at
about 2 km towards North direction and nearest State Highway is SH-69
(Thrissur-Kutt ippuram Rd.) at (Kaladi thara) about 0.7 km (E) away from
the site.
The nearest railway stat ion (Kutt ipuram Railway Stat ion) is about 10 km
(NE) and Calicut International Airport , Karipur is about 42 km (NE) away
from the project site.
Thereby, the road and by air connect ivity to the project is good.
Traffic study :-
Vehicular traff ic density survey was carried out on 19-11-2018 on
Thrissur-Kuttippuram Road and the survey report is provided below :-
Date :- 19-11-2018 (Thrissur to Kuttippuram)
TIME Cars Two
Wheelers
Three
Wheelers Buses LCV Trucks
8am – 9pm 30 24 9 8 6 17
9am – 10am 24 21 15 9 9 7
10am – 11am 15 27 10 4 18 12
11am – 12Noon 21 30 17 6 17 34
12Noon – 1pm 30 51 12 5 5 10
1pm – 2pm 15 39 19 6 6 14
2pm – 3pm 24 33 9 8 16 19
3pm – 4pm 6 39 15 9 30 21
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 7 Addit ional Studies Page 7 - 13
4pm – 5pm 30 15 9 12 14 Ni l
5pm - 6pm 8 51 14 5 6 24
6pm-7pm 12 36 12 3 8 17
7pm – 8pm 12 48 15 6 8 Ni l
Total Volume 227 414 156 81 143 175
In PCU* 227 207 125 284 315 613
Date :- 19-11-2018 (Kuttippuram to Thrissur)
TIME Cars Two
Wheelers
Three
Wheelers Buses LCV Trucks
8am – 9pm 34 27 29 12 7 Ni l
9am – 10am 20 29 40 10 12 7
10am – 11am 17 38 26 6 21 4
11am – 12Noon 18 28 28 5 24 28
12Noon – 1pm 32 44 18 8 9 34
1pm – 2pm 17 46 24 9 8 24
2pm – 3pm 20 40 28 12 19 26
3pm – 4pm 7 46 29 8 34 20
4pm – 5pm 34 24 7 17 19 11
5pm - 6pm 9 55 16 4 8 10
6pm-7pm 17 39 19 6 11 Ni l
7pm – 8pm 14 55 24 8 10 Ni l
Total Volume 239 471 288 105 182 164
In PCU* 239 236 230 368 400 574
*Values of PCU
Car 1.0
Motorcycle 0.5
LCV 2.2
Bus, Truck 3.5
3-wheeler 0.8
The above traff ic volume is within carrying capacity of road as per Indian
Road Congress (IRC) standards.
7.5 Social Impact Assessment
7.5.1 Introduction - Corporate Environment Responsibility
Community need assessments seek to gather accurate information
representative of the needs of a community. Assessments are performed
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 7 Addit ional Studies Page 7 - 14
prior to taking act ion and are used to determine current situat ions and
identify issues for act ion, establ ishing the essential foundation for vital
planning. The process is an invaluable tool for involving the public in
solving problems and developing goals.
To gather accurate information and ident ify the needs of the nearby
community to the project site, a community need assessment study was
carried out by Socio – Economic Expert, accredited by NABET in Edappal
Grama Panchayat. The main purpose of the study is to assist the project
proponent in delivering their Corporate Environmental Responsibi l ity
(CER) as per OM No. 22-65/2017-IA.III dt. 01-05-2018 issued by
MoEF&CC Notif ied by Ministry of Environment & Forests, states that
every green f ield project having capital investment under Rs. 100 crores
need to allocate 1.5% of its project cost (capital investment) for act ivit ies
under Corporate Environment Responsibi l i ty (CER). The instant project is
a Greenfield project and its capital investment is Rs. 180 crores.
Therefore the project has to spend an amount of Rs. 2.7 Crores under
CER in the surrounding vil lages. The project proponent has set apart an
amount of Rs. 2.7 Crores (about 1.5% of the project cost) to carry out
CER act iv it ies The objective is to obtain a social l icense from the stake
holders who are l ikely to be affected due to the proposed project.
7.5.2 Suggested Sectors to Perform Activities under CER:
1. Drinking water supply,
2. Sanitation,
3. Health,
4. Educat ion,
5. Skil l development,
6. Roads,
7. Cross drains,
8. Electrif icat ion including solar power,
9. Solid waste management faci l it ies,
10. Scient if ic support and awareness to local farmers to increase
yield of crop and fodder,
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 7 Addit ional Studies Page 7 - 15
11. Rain water harvesting,
12. Soil moisture conservat ion works,
13. Avenue plantation,
14. Plantation in community areas etc.
7.5.3 Approach adopted for assessment
To conduct the assessment, primary & secondary data were used.
Primary Data: Stake holder interviews, unstructured interview, f ield
observat ion, and telephonic survey.
Secondary data: Yearly Project Document and Development Charter of
the Panchayat, Census Report 2011.
7.5.4 Stake Holders
As part of study the Socio Economic expert conducted interviews with
different stakeholders of the Panchayat. The detai ls of stake holders are
given below.
Sl. No Name Designation Phone Number
01 M P Venugopalan Secretory, Edappal Grama
panchayath
8606339116
02 K Sathi Devi HM, Govt. U P
School,Pulikkad
9495805752
03 T P Surendran Polit ician 9048101990
04 K Bhavadasan Polit ician 8921195046
7.5.5 Proposed CER activities:
a) Health care
1. The project can provide 2000 dialysis to economically back ward
patients as free of cost. The patients from Edappal grama panchayth wil l
be given priority.
Particulars Basis of calculat ion Total ( in Rs.)
Dialysis Rs.1200 x 2000 Dialysis 24,00,000
Total 24,00,000
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 7 Addit ional Studies Page 7 - 16
2. The project can provide discount of Rs. 50,000 to 100 patients from
economical ly back ward famil ies for major surgeries.
Particulars Basis of calculat ion Total (in Rs.)
Discount of Major
surgeries
Rs.50,000 x 100 patients 50,00,000
Total 50,00,000
3. The project can provide the treatment of Rs. 1 lakh to the 60 pat ients,
those who are undergone organ transplantation in this hospital. The
beneficiar ies wil l be from economically back ward famil ies.
Particulars Basis of calculat ion Total (in Rs.)
Support to organ
transplantation
Rs.1,00,000 x 45 pat ients 45,00,000
Total 45,00,000
4. The project can provide Rs. 10,000 discount in the treatment of
500 pat ients from economically backward famil ies.
Particulars Basis of calculat ion Total (in Rs.)
Discount in treatment Rs.10,000 x 500 patients 50,00,000
Total 50,00,000
5. The project can provide scholarship of Rs. 1 Lakh to 50 el igible
students, those whol are studying in the proposed project.
Particulars Basis of calculat ion Total (in Rs.)
Scholarship Rs.1,00,000 x 50 Students 50,00,000
Total 50,00,000
6. The project will conduct Medical camp in various f ields l ike
Orthopaedics, Nephrology Gastroenterology and General medicine. The
project is intending to conduct 30 camps in the community.
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 7 Addit ional Studies Page 7 - 17
Particulars Basis of calculat ion Total (in Rs.)
Medical Camp Rs 50,000 x 30 camps 15,00,000
Total 15,00,000
7. The project wil l provide First Aid Training to people from various
category like Drivers, college Students, Kudumbasree members, Porters,
Construct ion labours, Students etc. The training programme wil l be free.
Maximum 30 persons can participate in a training programme.
Particulars Basis of calculation Total (in Rs.)
First aid Training
programme
Rs 20,000 x 50 programmes 10,00,000
Total 10,00,000
b) Rain Water Harvesting
The project can start a well recharge program by harvesting roof top rain
water. A f i ltrat ion tank wil l instal l near to the wel l and al l col lected water
channelized to well af ter f i l trat ion. This will be executed in associat ion
with NGOs in consultation with Local Self Government.
Particulars Basis of calculat ion Total (in Rs.)
Well Recharge Program Rs 15,000 x 100 wells 15,00,000
Total 15,00,000
c) Promotion of Renewable Energy
The project proponent can instal l solar panels of 4 KW to two Govt.
Schools and one PHC namely Govt. H S School, Edappal and Govt. U P
School, Pulikkad. In addit ion to this the project proponent can instal l solar
street l ights in consultation with Local Self Government.
Particulars Basis of calculat ion Total (in Rs.)
Solar Panel Rs. 3,50,000 x 3 Solar panels 10,50,000
Solar Streetl ight Rs. 20,000 x 23 Solar Street light 4,60,000
Total 15,10,000
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 7 Addit ional Studies Page 7 - 18
7.5.5.1 Summary of CER Activities
The summary of the CER activit ies are given below :-
Sr.
No. Areas of Intervention
No. of
Intervention
Expenses
(in Rs.)
01 Health Care 07 2,44,00,000
02 Rain Water Harvest ing 01 15,00,000
03 Promotion of renewable energy 01 15,10,000
Total 09 2,74,10,000
7.5.5.2 Time frame (Tentative) for execution of CER activities
Sr. No.
Activities Ist year IInd year III rd year
1 Health Care
2 Rain Water Harvest ing
3 Promotion of renewable energy
7.6 Réhabilitation & Resettlement (R & R) Action Plan
There is no displacement of people from the core zone of the project,
hence Réhabil itat ion & Resett lement (R & R) is not applicable to the
instant project.
7.7 Public Hearing
As per the Terms of Reference provided by the MoEF&CC vide letter
dated 22-06-2018, public hearing is to be conducted for the instant project.
Thereafter, v ide O.M. F.No.Z-11013/22/2017-IA.II(M) dated 16-03-2018
issued by MoEF&CC, no public hearing is required for building
construction projects.
*******************************************************************************
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 8 Project Benef i ts Page 8 - 1
8.0 PROJECT BENEFITS
8.1 Introduction
Any developmental project is conceived and executed with benefits to
various social groups. The any development projects also cater to the
needs of various sect ions of the society ranging from necessity to
recreation. The benefits from the proposed project are discussed below.
8.2 Physical Infrastructure
The proposed project is an expansion of exist ing hospital cum medical
college project which is planned to meet the model of a hospital /
healthcare sector. Overall development of the area including public
transport, water supply, sewage treatment, sol id waste treatment facil i ty,
telecommunications etc. are inclusive in the proposal.
8.3 Social Infrastructure
The project of large scale sets in an overall development of the region,
with construction of new or maintenance and widening of exist ing roads,
power supply and water supply, since a hospital building generally brings
the focus of the development authorit ies in the locali ty.
8.4 Economic Benefits
The project wil l entai l posit ive impact on the local economy in a mult i-
dimensional way.
The local market wil l also receive an impetus to grow in meeting the daily
need goods for the operational workers as well as in meeting day-to-day
odd job requirements of the proposed act iv it ies.
During the operat ion phase, it is proposed to employ mainly local
populat ion for various maintenance related activit ies after impart ing
adequate training. It is also proposed to engage in arrangements with
local faci l i t ies for maintenance and related procurement of spare parts
etc. of machineries / equipments used in the hospital.
In meeting the day-to-day and recreational demands of the occupants of
the site, the region is also l ikely to develop a number of shopping,
inst itutional and amusement faci lit ies within the vicinity thereby, further
stimulat ing the local economy.
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 8 Project Benef i ts Page 8 - 2
The proposed project is an expansion of exist ing hospital cum medical
college building project and thereby the living index of the people around
the project s ite will definitely improve.
Also there wil l be various ancil lary activit ies l ike convenient shops,
medical shop, food courts, and restaurants, transport facil it ies etc.
attached to the project which wil l benef it the local people and change
their l iving condit ion. Other benefits are :-
� Expansion of businesses with increased local spending on goods and
services;
� An increase in business and community conf idence in the continuing of
prosperity for the project area;
� Financial contr ibution to the State government through the payment of
taxes and duties thus enabling the State to invest in infrastructure
development.
� The present project would provide better healthcare related faci l it ies
with support ing infrastructure faci lit ies in the vicinity.
� Direct (about 1000 nos.) and indirect employment (about 3,000 nos.)
opportunit ies. The potential for employment and access to new
services may draw people to the area around the project. There will be
an increase in economic activity and employment for the local
community, local ski l ls development.
� Revenue ( GST) to the State & Central Government.
� The project proponent has carried out charity act ivit ies (Corporate
Social Responsibi l i ty) for on various developmental activit ies for the
local community.
8.5 Importance of the present project
Medical tourism is a fast becoming a multi-mill ion dol lar industry in the
country. The fact was further strengthened by Chief Secretary’s of Govt.
of Kerala statement at the inaugural funct ion of the f i f th edit ion of Kerala
Health Tourism. The current market size of the medical tourism sector in
the country is expected to grow from the current $3 bil l ion to $7-8 bi l l ion
by 2020.
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 8 Project Benef i ts Page 8 - 3
Medical tourism can be broadly def ined as provision of 'cost effective'
private medical care in col laboration with the tourism industry for patients
needing surgical and other forms of special ized treatment. This process is
being faci l itated by the corporate sector involved in medical care as well
as the tourism industry - both private and public.
Medical or Health tourism has become a common form of vacationing, and
covers a broad spectrum of medical services. It mixes leisure, fun and
relaxation together with wellness and healthcare.
The health holiday is an opportunity to get away from the dai ly rout ine
and come into a dif ferent relaxing surrounding. Here anyone can enjoy
being close to the beach and the mountains. At the same t ime you are
able to receive an orientat ion that wil l help you improve your life in terms
of your health and general well-being. It is l ike rejuvenation and clean-up
process on al l levels - physical, mental and emotional.
Many people from the developed world come to India for the rejuvenation
promised by yoga and Ayurvedic massage, but many consider it a
dest ination for hip replacement, Kidney & Liver problems or brain surgery,
cancer treatment etc. However, a nice blend of top-class medical
expert ise at attractive prices is helping a growing number of Indian
corporate hospitals lure foreign patients, including from developed nations
such as the UK and the US. As more and more pat ients from Europe, the
US and other aff luent nat ions with high medicare costs look for effective
options:
Apart from the benefits incurred through the project, there wil l be
environmental benefits through the project. This includes benefits
occurring to the locality neighborhood, and region as a whole. The
foremost benefits are l isted as fol lows:
A. Socio-Economy
� During the construction phase, there was growth in indirect jobs and
business opportunit ies to the local and nearby people such as
contractors, transporters and row material suppliers etc.
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 8 Project Benef i ts Page 8 - 4
� Due to this project, there is posit ive impact on the economic
development of the region in terms of employment opportunit ies.
� Post project wil l generate long term addit ional employment in
bui lding maintenance and ancillary services for local population.
B. Tree Plantat ion and Landscaping
� Trees plantat ion on ground levels (as already planted / to be
planted) helps reducing energy use by reducing heat island effect.
� Pleasing aesthetic and visual impact.
� Trees act as natural noise buffers.
� Provide tolerance to air pollutants l ike PM1 0, PM2.5, SO2, NOx & CO.
C. Water Saving and waste water Management
� The construction activ it ies are already completed. During operat ion
phase, the raw water requirement wil l be reduced by using treated
domestic waste for plantation and flushing purposes, horticulture,
boiler and make-up water for cooling purposes and no l iquid
discharge outside the project premises.
� By using various water saving pract ices l ike use of water eff icient
plumbing f ixtures, dual f luxing cisterns etc. and use of rain water for
domestic purposes bringing down the per capita water consumption
compared to the present use.
� Reducing storm water runoff by collecting the rain water from
terraces and to store in tanks as well as in pond and reducing the
load on storm water drains.
D. Energy Saving
� Provision of solar panels for external l ighting for proposed project.
� Maintenance of energy saving measures using conventional
measures.
� Various energy saving measures to save energy through
conventional and non-conventional method (Solar panels).
E. Solid and Hazardous & Bio-medical Waste Management
� Provision of dedicated space for solid waste management & bio-gas
generation plant for disposal of municipal solid waste. Also the bio-
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 8 Project Benef i ts Page 8 - 5
medical waste would be segregated as per the guidelines and wil l
be sent to the authorized agency i.e. IMAGE. The manure from
biodegradable waste is being used for plantation.
� Provision for separate storage for E-Waste. E-Waste is being
handed over to authorized recyclers, non-biodegradable waste shall
be handed over to approved vendors.
F. Environmental Monitoring & Environmental Management Plan
� Environmental monitor ing as mentioned in Chapter 6 wil l be carried
out regularly ensuring the baseline quality, implementat ion of
mitigation measures and control of environmental pollution.
� Environmental Management Plan and its judicious implementat ion
with operation and maintenance of environmental facil it ies and
insurance of proper budgetary allocations for a long term benefits to
project and surrounding areas.
*******************************************************************************
M/s SREEV ALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 9 Environmenta l Cost Benef it Analysis Page 9 - 1
9.0 ENVIRONMENTAL COST BENEFIT ANALYSIS
9.1 Introduction
Appendix-I II of EIA Notif ication, 2006 (Generic Structure of Environmental
Impact Assessment Document), states that "Environmental Cost Benefit
Analysis" is to be elaborated in the EIA report provided such a study is
mandated by the Expert Appraisal Committee (EAC) / State Expert
Appraisal Committee (SEAC) at the scoping stage of the proposal. In the
instant project, s ince the EAC has not prescribed for such a study during
the scoping stage and hence not part of the approved "ToR" and
therefore, there is no descript ion of "Environmental Cost Benefit
Analysis".
*******************************************************************************
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 10 Environmental Management Plan Page 10 - 1
10.0 ENVIRONMENTAL MANAGEMENT PLAN
10.1 Introduction
This chapter deals with the descript ion of administrat ive aspects of
ensuring the mit igat ive measures proposed for the impacts identif ied in
Chapter 4 due to the construction activit ies during construct ion phase and
operation phase on each facets of environment viz. Air Environment,
Noise Environment, Land Environment, Water Environment, Ecological
Environment and Socio-economic Environment.
10.2 Environmental Management System (EMS)
The project proponent wil l adopt Environmental Management System
(EMS) which will assist project management to meet both current and
future environmental requirements and challenges. EMS wil l provide a
structural view and control of the organization's environmental
performance that wil l be applied from planning and exploration to the
proposed project during construction phase & in operation phase.
The following components are being taken to establish an EMS;
Organizational Commitment, Environmental Policy, Environmental Impact
Assessment, Objectives and Targets, Environmental Management Plan
(EMP), Documentat ion, Responsibi l it ies and Reporting Structure,
Training, Environmental Review Audits and Emission and performance
monitoring.
The project management will fol low a comprehensive and systematic
health and safety funct ion which involves al l personnel seeking to ident ify
hazards and assessing risk to prevent and el iminate all accidents/injur ies.
The project management wil l prepare a detai led Environment Management
Plan for sustainable development of the project.
10.3 Environmental Policy
In order to protect environment and for sustainable development, an
Environmental Policy wil l be adopted by the project proponent as fol lows:
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 10 Environmental Management Plan Page 10 - 2
"Environment, Health, Safety and Quality (EHSQ) Policy"
We, Sreevalsam Educational Trust, driven by our core values and beliefs
are committed to our stakeholders and meet customer / patient
sat isfaction through integrated EHSQ management system to achieve
sustainabil ity, in al l our exist ing and future healthcare services.
To attain this objective, we shall : -
• Implement and maintain an integrated EHSQ management system to
achieve sustainable performance.
• Adopt and sustain a Business Excellence framework for continual
business process improvement.
• Protect Environment, conserve natural resources, reduce energy
consumption, improve occupational health and safety performance and
mitigate risks by adopting optimal product ion processes and services,
driven by environment friendly technologies.
• Comply and endeavor to exceed all applicable legal and other
requirements.
• Continuously str ive to achieve satisfaction of all stakeholders through
contr ibution to social development.
• Communicate effectively about the EHSQ system and create awareness
and increase the competency of all employees through training.
• Establish specif ic organizat ional structure for guidance,
implementat ion and regular review of EHSQ management system.
Responsibil ity
The Environmental Off icer is responsible for maintaining ecological
balance by adequate environmental protection and environment
improvement works. In the event of observat ion of non compliance by any
employee, the same is informed by the Environmental Off icer to the
project manager and to the project proponent. These three wi ll ident ify the
cause and implement the mitigat ion measures or engineering controls or
work practices required. The Environmental Officer will monitor the
environmental performance and guide the project manager and the
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 10 Environmental Management Plan Page 10 - 3
employees for maintaining good environmental practices and to adopt
newer, safe and cleaner technologies.
10.4 Environment Management Cell (EMC)
A Cell for Environment Management within the site, will take overall
responsibi l ity for co-ordination of the act ions required for environmental
management and mitigation, and to monitor progress of the mit igative
measures and actions to be taken by the project proponent i.e.
Sreevalsam Educational Trust. The Cell wil l be under the overall
supervision of the Environmental Off icer, and will be responsible for
monitoring of the implementation of the various measures as mentioned in
Chapter 4. The Environmental Cell wil l report on a regular basis to the
project proponent.
The Environmental Management Cell is responsible for overseeing;
supervision, during collection of water and air samples within and outside
the core zone by NABL accredited laboratory; implementation of the
pollut ion control and protective measures; eco-restoration and green area
development; co-ordinat ion of the environment related act iv it ies;
collection of the statistics of health of workers; implementing safety
programs; and monitor ing progress of implementat ion of EMP during
construction phase & operation phase. The structure of the Environmental
Cell is given at Table 10.1.
Table 10.1 - Environmental Management Cell
Sr. No. Members Role
1. Secretary of the trust Chairman
2. Project Manager Member
3. Environmental Off icer Convener
4. Safety and Health Off icer Member
5. Representat ive of NABL accredited laboratory Member
6. Representat ive of NABET accredited Environmental Consultant
Member
Frequency of Meeting – Once In three months
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 10 Environmental Management Plan Page 10 - 4
10.5 Other Management Aspects of the Environmental Cell.
Records wi ll be maintained of the analysis reports of ambient air quality,
water quali ty, and noise levels and to observe variat ions (i f any). These
records are not only required for the perusal of the statutory authorit ies
but for the management also. The records as per the hazardous waste
regulat ions, 2016 and EPA regulations, 1986 are to be maintained.
Obtaining the Authorization for the intermediate storage of hazardous
waste as per the Hazardous Waste (Handling & Management) Rules and
its renewal. The project shall obtain the Consent to Establish (CTE) and
Consent to Operation (CTO) as required under Section 25/26 of the Water
Act, 1974 and under Section 21/22 of Air Act, 1981, before the
commencement of activity from Kerala State Pollution Control Board. The
CTO will be renewed as per the KSPCB guidelines by the management.
The project proponent wil l submit environmental statement every year
before September 30. The management ensures that i t wil l comply with all
the direct ions and regulat ions issued by the Ministry of Environment,
Forests & Climate Change (MoEF&CC), New Delhi, State and Centre
Pollut ion Control Boards. The "Consent to Establ ish", "Consent to
Operate", authorizat ion of Bio-medical Waste (Management & Handling)
Rules and al l other statutory approvals wil l be displayed in a conspicuous
location in the off ice of the Sreevalsam Educational Trust for the
information of the inspect ing authori ties of dif ferent departments and al l
stake holders.
10.6 Standard Operating Procedures (S.O.P.)
The Environment Management Cell wil l develop standard operating
procedures for the following :-
• Compliance to the condit ions of Environment Clearance (EC) and the
submission of six monthly compliance report of the E.C. condit ions.
• Compliance to the condit ions of "Consent to Establish" (CTE)
• Compliance to the condit ions of "Consent to Operate" (CTO)
• Compliance to the condit ions of Authorization of Bio-medical Waste
(Management & Handling) Rules
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 10 Environmental Management Plan Page 10 - 5
• Implementat ion of Remediation plan as approved by the regulatory authority
• Compliance to the condit ions of al l statutory approvals.
• Renewal of approvals before the expiry of the approvals.
• Implementat ion of the Corporate Environment Responsibi l ity act ivit ies.
• Compliance to the accreditat ion with NABH (National Accreditation
Board for Hospitals & Healthcare Providers) and other regulat ions
updated t ime to t ime.
10.7 Cost Estimate for Environment Management Systems
During Construction phase
The overall investment on the environmental safeguards and measures for
successful monitor ing and implementation of pollution control measures is
presented in Table 10.2.
Table 10.2 : Cost Estimation of Environmental Management Plan during Construction phase
Particulars
Approx. Recurring
Cost / Annum
Approx. Capital Cost
Rs. In Lacs
Medical cum First Aid facil ity with a trained person with f irst aid kit.
3.0 15.0
Mobile Toilets with STP in the labor colony 1.0 5.0
Supply of drinking water for the labourers from existing wells
3.0 5.0
Wind Breakers at the site in the side where it is abutt ing and other vulnerable
areas. 5.0 10.0
Sprinklers for suppression of dust (Sprinklers, pipeline network, online micro
f i lters and pressure pumps) 1.5 3.0
Solid Waste from labour camp & construction site
(Segregation & disposal with exist ing bio-gas plant)
0.5 2.0
TOTAL 16.0 50.0
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 10 Environmental Management Plan Page 10 - 6
During Operation phase
The overall investment on the environmental safeguards and measures for
successful monitor ing and implementation of pollution control measures is
presented in Table 10.3.
Table 10.3 : Cost Estimation of Environmental Management Plan during Operation phase
SN Particulars
Approx.
Recurring
Cost / Annum
Approx.
Capital Cost
Rs. In Lacs
1. Sewage Treatment Plant (STP) sewage
from domestic consumption of the campus 4 20
2.
Eff luent Treatment plant (ETP), waste
water from laundry / laboratory area of the
hospital
5.0 20.0
3. Solid Waste Management Plan including
sett ing up of a bio-gas generation plant 2.0 10.0
4. Bio-medical waste segregation & disposal
through IMAGE 4.0 40.0
5. Sett ing up of an intermediate hazardous
waste storage faci li ty 1.5 15.0
6. Noise Control for D.G. Sets 3.0 26.0
7. D.G. Sets Emission stacking & sampling 0.5 4.0
8. Green Area development 8.0 30.0
9. Construct ion of rain water collect ion tanks 5.0 45.0
10. Solar power & other solar energy operated
equipments 4.0 28.0
TOTAL 37 238
Note :- The cost should include the civ il construction + machinery +
electrical + plumbing + automation (if any).
*******************************************************************************
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 11 Summary & Conc lusion Page 11 - 1
EXECUTIVE SUMMARY
1.0 Introduction
M/s Sreevalsam Educational Trust proposed an expansion of exist ing
Hospital cum Medical College project at Survey Nos. 157/2, 159/3, 158/1,
157/0, 158/1, 159/3, 158/2, 158/5, 159/1, 159/2, 157, 159/3, 164/3, 164/7,
164/4, 163/3, 158/7, 158/3, 158/4, 166/2, 166/1, 156/3, 164/1, 156/3,
164/1, 164/2, 156/4, Edappal Vil lage, Ponnani Taluk, Malappuram District,
Kerala. The plot area of the Hospital cum Medical College Project is
9.4534 ha (94,534.56 sq. m.) and the total buil t-up area is 1,38,937.50 sq.
m. (existing 53,889.72 sq.m. + proposed 85,047.78 sq.m.).
Building construction of 53,889.72 sq.m. of the hospital cum medical
college is already completed. The teaching hospital component is for a
built -up area of 32,160 sq.m. and the educat ional component is with built -
up area of 21,729.72 sq.m. It is proposed to construct addit ional bui lt-up
area of 85,047.78 sq.m and the total cumulat ive built -up area will be
1,38,937.5 sq.m.
The land was purchased and registered between the year of 2010 to 2011
and started the construct ion work of Teaching Hospital in 2011 as per the
Building permit vide permit no. 224/11-12 dated 03-11-2011 obtained from
Edappal Grama Panchayat for a built-up area of 5,783.70 sq.m.
Subsequently, the expansion of the building was carried out with the
renewal of building permit vide permit no. B2-224/11-12 dated 27-06-2012
valid upto 26-06-2015 issued by the Panchayat for a cumulat ive built -up
area of 32,160 sq.m. in 2012. This work was carried out without pr ior
Environmental Clearance and the construct ion of this bui lding
is completed. Further, renewal of building permit vide permit no.
A5-365/14-14 dated 24-03-2014 was issued for Academic block, Hostels
with a cumulat ive built-up area of 43,636 sq.m. and construction of
21,729.72 sq.m. is completed. Educat ional institutions are exempted from
the purview of EIA Notif ication vide Notif icat ion dt. 22-12-2014. For the
f irst t ime, the requirement of prior Environmental Clearance was inserted
in Kerala Municipal ity Building Rules (KMBR) by an amendment of KMBR
made in 05/02/2013.
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 11 Summary & Conc lusion Page 11 - 2
Therefore, the project proponent was not aware of the requirement of
prior Environmental Clearance and constructed the Teaching Hospital
building without obtaining prior Environmental Clearance and hence the
violated the provisions of Environment Protect ion Act, 1986.
Ministry of Environment, Forests & Climate Change (MoEF & CC) issued a
Notif icat ion dated 14/03/2017 (Notif icat ion No. S.O. 804 (E)) and gave
one time opportunity to the projects who have commenced their activity
without taking prior Environmental Clearance violated the EIA Notif ication,
2006.
An application with draft Terms of Reference (ToR) for EIA Study and for
obtaining Environmental Clearance under the provision of MoEF&CC
Notif icat ion dt. 14/03/2017 was submitted at MoEF&CC on 23/06/2017
vide File No. 23-89/2018-IA-III (V).
Thereafter, the proposal was considered in the 06 th meeting of Expert
Appraisal Committee (EAC) at MoEF&CC on 19 t h - 20 th , Apri l, 2018 vide
agenda item No. 6.3.7 for grant of Terms of Reference (ToR) for
undertaking Environment Impact Assessment (EIA) studies and
preparation of Environment Management (EMP).
The EAC recommended the project for grant of “ToR” for undertaking
Environment Impact Assessment (EIA) study and preparation of
Environment Management Plan (EMP). The Ministry accepted the
recommendations of EAC and the “ToR” was approved and issued vide
Letter No. 23-89/2018-IA.III dated 22/06/2018.
With a view to assess the environmental impacts due to the construct ion
act iv it ies, to suggest the mitigat ion measures, to assess the ecological
damage due to the i l legal construct ion, to prepare remediation plan and
the natural and community resource augmentat ion plan as per the
approved ToR granted, the project proponent has engaged M/s
Environmental Engineers & Consultants Pvt. Ltd., (an MoEF & CC
accredited Consultancy Organizat ion under QCI / NABET Scheme).
2.0 Project description
In order to faci li tate the medical and medical education requirement in the
project vicinity and in Ponnani Taluk of Malappuram District, Kerala M/s
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 11 Summary & Conc lusion Page 11 - 3
Sreevalsam Educational Trust constructed a hospital cum medical col lege
project at Edappal Vil lage, Ponnani Taluk, Malappuram Distr ict, Kerala in
Plot area of 9.4534 ha and constructed of buildings with built -up area
53,889.72 sq. m. and due to increase in demand the project proponent is
going for expansion of the exist ing campus with addit ional built -up area of
85,047.78 sq.m. After the proposed expansion the cumulat ive built -up
area of the hospital cum medical col lege wi ll be 1,38,937.50 sq.m.
(existing bui lt-up area 53,889.72 sq. m. + 85,047.78 sq.m.) with number of
hospital beds of 1,170 beds.
The estimated cost of the project is about Rs. 180 Crores. The project is
expected to employ about 1,000 direct job opportunit ies which includes
medical & non-medical staff .
During construct ion phase, the daily water requirement for construction
act iv it ies is about 312 KL (for 48 months) and for meeting domestic
requirement is about 27 KL (250 workers at site, avg.) (for 48 months).
The sewage generat ion from the labourers during construct ion phase is
expected to be about 27 KL/day which wi ll be disposed through STP
within the site. The treated water from the mobile STP wil l be used for
wetting of dust suppression and for landscaping purposes within the site.
During operat ion phase, the sources of water for meeting the domestic
requirement as well as other requirements of the proposed hospital cum
medical col lege project wil l be from exist ing wells, stored rain water and
recycled water from STP / ETP.
The total daily water consumption for the proposed project would be about
1,328 KL (fresh water 677 KL + recycled water 651 KL). The f irst day
fresh water requirement is 1,328 KL and subsequent days, the daily fresh
water requirement is 677 KL. The daily domestic water consumption is
870 KL (f lushing purposes 647 KL + non-f lushing purposes 223 KL).
The sewage generat ion from the proposed hospital cum medical campus
during operation phase is expected to be about 696 KL/day which wil l be
disposed through STP within the site. The treated water from STP wil l be
used for f lushing purposes, landscaping purposes, boiler requirement and
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 11 Summary & Conc lusion Page 11 - 4
make-up water requirement for cooling towers attached with the HVAC
system within the site.
During construction phase, the storm water within the site wil l be partially
channelized to the rain water storage tank. Appropriate de-si lt ing and oi l
removal wil l be provided so that the storm water wil l not contaminate the
land and aquifer.
During operation phase, to conserve water, rainwater storage capacity of
5,000 KL is provided at the site. It is provided that roof rain water wil l be
directed to rain harvest ing tanks after de-siltat ion, the removal of oi l and
grease through a trap within si te. This water wil l be used for daily
requirement after suitable treatment. Excess rain water shall be lead to
storm water drain available near the site.
There is no Ecologically sensit ive zone (National Park, Sanctuary, Habitat
for Migratory Birds, Tiger Reserve) within the 10 km radius. Also, there is
no forest are within 10 km radius from the site.
As per the Land Use Cert if icate and Land Conversion Cert if icate issued
by Tahsildar, Ponnani on 31-03-2014 stating that the land is "do not fal l
under Agricultural use and this land can be used for Educat ion purpose to
establish Education Institut ions".
3.0 Description of the Environment
Study Area : As specif ical ly mentioned in EIA Notif icat ion and as well as
on the basis of "Environmental Impact Assessment Guidance Manual for
Building, Construction, Township and Area Development Projects"
published by Ministry of Environment & Forests, February, 2010, for
carrying out an EIA study of a building construction project, the project
site is called as "core zone" and 10 km radius from the boundary l imits of
the project site is called as "buffer zone". The study area includes the
"core zone" and "buffer zone".
Study period : The study period was November & December, 2018 which
is other than the monsoon season. The samples were collected and
analysed for various parameters through an National Accredited Board for
Laboratories (NABL), accredited laboratory and also by the ecological &
social experts approved by QCI/NABET.
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 11 Summary & Conc lusion Page 11 - 5
Meteorological parameters :
Temperature - The maximum temperatures ranges from 28.9 to 36.2°C
and the minimum temperatures range from 17.0 to 23.4°C.
Rainfall - The normal rainfal l of the district is 2793.3 mm.
Humidity -The relative humidity ranges from 84 to 94 % during morning
hours. The humidity is more during the peak monsoon months from June
to September.
Wind rose - As per the wind rose diagram, the pre-dominent wind
direction is from south direction.
Air Environment - All the analyzed values of al l parameters are well
within the National Ambient Air Quality Standards.
Noise Environment - I t can be observed from the results that the noise
values are much below the prescribed l imits for Industr ial, Commercial,
Resident ial, and Silence zone. Proposed project are not l ikely to cause
any increase in 'noise' levels at the monitoring locat ions (sensit ive
receptors) which are located more than a kilometer away from the project
site.
Land Environment - As per the Land Use / Land Cover Classif icat ion
System, the exist ing land use within the buffer zone is about 63% of the
land is Plantation area, about 7% land is River/Stream / Canal and about
24% of the land is Crop land and remaining land is covered with other
land use / land cover. The soil in core area is not good in nutr ients values
and not product ive from agriculture view point.
Proposed project is an expansion of exist ing hospital cum medical col lege
project and new buildings wil l be construct ing within the exit ing plot area.
Therefore, the land use / land cover of study area is not l ikely to get
affected adversely due to proposed project.
Water Environment - I t is observed that the ground water level is
encountered about 1 m from the existing ground level.
As per the Ground Water information Booklet, CGWB, the proposed
project is categorized as 'Safe' zone and hence the ground water
available in the region is ensure and to use of domestic purposes.
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 11 Summary & Conc lusion Page 11 - 6
All the parameters except pH level, i ron content, hardness, chlor ides are
within the standards as per IS:10500 (Ground Water - Bore well). It is
recommended that appropriate treatment wil l be done before its
consumption for domestic purposes.
Ecological Environment - Analysis of the f lora revealed that, in the
proposed project s ite there are 90 plant species fal l ing under 48 plant
families. Angiosperms forms 86 species with 25 species of trees including
saplings, 18 species of shrubs, 28 species of herbs and 15 species of
climbers. There are four Pteridophytes (ferns) fal l ing under three families.
The Site has 90 species of plants. I t consists of Trees 25 species, Tree
saplings 18 species, Shrubs 18 species, Herbs 28 species,
Cl imbers 15 species, Ferns 4 species,
The most dominant plant family is Compositae with 8 plant species
followed by Leguminosae, Moraceae Euphorbiaceae, and Malvaceae. One
tree species namely Artocarpus hirsutus is endemic to Southern Western
Ghats.
The fol lowing lists of faunal elements were observed from the site :
Birds 26 species, Mammals 10 species, Butterf l ies 24 species, Odonates
12 species, Amphibians 6 species, Repti les 10 species, Spiders 11
species, Ants 6 species,
Regarding the conservat ion status of the fauna, none of the animal
species ident if ied from the site belonged to the threatened categories
identif ied by the International Union for Conservation of the Nature and
Natural Resources (IUCN). Most of them are common and widely
distributed and the range of occurrence extended to wide geographical
area. One species of butterf ly namely Southern Birdwing (Troides minos)
and one species of amphibian viz. Rhacophorus malabaricus reported
f rom the site are endemic to W. Ghats.
The present project is an expansion of exist ing hospital cum medical
college campus. The construct ion of new buildings are within the existing
plot area. Therefore, the proposed construct ion act iv ity wi ll have minimal
impact on the local f loral and faunal species. Due to the construct ion
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 11 Summary & Conc lusion Page 11 - 7
act iv ity, there wil l be minimal loss of habitat to faunal species specially to
avifauna.
Socio-economic Environment - The density of populat ion in the buffer
zone is about 1465 persons per sq km. The project area is in a rural
vil lage. Majority of the populat ion in the study area are engaged in
agriculture and cult ivat ion. There is no major industry in the area. The
proposed project is l ikely to generate direct and indirect employment.
Economic growth is expected in the area due to construct ion boom and
al l ied industry like transport, mini hotels and restaurants and enhanced
commercial act iv it ies (markets, shops, real estate etc.).
Also, the healthcare faci l it ies wil l be increase due to the sett ing up of
medical col lege in the vic inity.
4.0 Anticipated Environmental Impacts & Mitigation Measures.
The mitigation measures for the signif icant impacts identif ied during
construction and operation phase are summarized below.
CONSTRUCTION PHASE:-
SN
Impact on
Envir . Anticipated Impacts Mitigation Measures
1 Air Particulate Matter & Gaseous emissions f rom DG Sets.
� Stack height as per CPCB Standards. � Promotion of use of c leaner fuel � Al l DG set should comply emissions norms
notif ied by MoEF / CPCB.
2 Water
Impact on competing users due to large consumption of water for cur ing, dust suppression, construction, domestic use etc.
� To avoid wastage of cur ing water, following procedures are suggested: -
• Curing water should be sprayed on concrete structures: f ree f low of water should not be al lowed for curing.
• Af ter l iberal cur ing on the f irst day, al l concrete structures should be painted with curing chemical to save water. This wil l s top dai ly water curing.
• Concrete structures should be covered with thick cloth / gunny bags and then water should be sprayed on them. This would avoid water rebound and wi l l ensure sustained and complete cur ing.
• Ponds should be made using cement and sand mortar to avoid water f lowing away f rom the f lat surface while curing.
• Water ponding should be done on all sunken slabs, th is would also highl ight the importance of having an impervious formwork.
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 11 Summary & Conc lusion Page 11 - 8
� Estimation of dai ly water consumption based on the population, reuse and recycled options, quantif icat ion of waste water, requirement of construction water , etc.
� Monitor ing water use: Use of water meter conforming to ISO Standards would be insta l led at the inlet point of water uptake and at the discharge point to monitor the dai ly water consumpt ion.
� Use of rain water for domestic purposes in the labour colony & for construct ion purposes.
� Use of treated water f rom STP of labour colony for construction purposes.
3 Noise
Noise & Vibrat ion f rom DG Sets due to inadequate acoustic enclosure
� Use of DG Sets with appropriate acoustic enclosures
� Use of ant i vibrat ion pads
4 Socio Economic
Unhygienic si te sanitat ion faci l i t ies may cause heal th damage to construction workers
� The object ive is to ensure health and safety of the workers with effective provis ions for the basic facil i t ies of sani tat ion, dr inking water , safety of equipments or machinery etc. Fol lowing are some of the recommendations:-
� Comply with the safety procedures, norms and guidel ines (as appl icable) as outl ined in the National Building Code of India, Bureau of Indian Standards.
� Provide c lean dr inking water to a l l workers. � Provide adequate number of decentra l ized
latr ines and ur inals. � Guarding al l parts of dangerous machinery. � Precautions for working on machinery. � Maintaining hoists and l if ts , l i f t ing machines,
chains, ropes and other l if t ing tackles in good condit ion.
� Durable and reusable formwork systems to replace timber formwork and ensure that formwork where used is properly maintained.
� Ensuring that walk ing surfaces or boards at height are of sound construction and are provided with safety rai ls or belts.
� Provide measures to prevent f ires. Fire f ight ing ext inguishers and buckets of sand to be provided in the f ire prone area and elsewhere.
� Provide suff ic ient and suitable l ight for working during night t ime.
5 Energy Conservation
Use of energy in-eff ic ient building materia ls may lead to higher consumption of electr ic i ty in air
� Use of bui lding materia l for roof , wal ls & glass ( R & U values) as per BEE for less heat gain in a ir conditioned buildings.
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 11 Summary & Conc lusion Page 11 - 9
condi tioned bui ldings.
6
Building
Mater ial
Resource
Conservation
Use of farfetched construction materia l than locally available construction materia l may lead to over explo itat ion of natural resources & increase in carbon footpr int
� Use of local ly avai lable construct ion materials.
** Construction Activities (Foundation, Columns, beams, slab casting,
brick work, plastering, flooring, electrical & plumbing works, painting
& finishing).
OPERATION PHASE:-
Sr. No.
Impact on Env. Anticipated Impacts Mitigation Measures
1 Air
Particulate Matter & Gaseous emissions (including worst condit ion of operat ing al l DG sets)
� Stack height as per CPCB Standards. � Development of a dense belt
(vegetat ion buffer) in the project site. � Promotion of use of cleaner fuel � All DG set should comply emissions
norms notif ied by MoEF / CPCB.
2 Water
Impact on competing users due to consumption of public supply / ground water (resource loss) for domestic consumption in the campus
� Estimation of daily water consumption based on the population, reuse and recycled options, quantif icat ion of waste water etc.
� Monitoring water use: Use of water meter conforming to ISO Standards would be instal led at the inlet point of water uptake and at the discharge point to monitor the daily water consumption.
� Use of water saving devices / f ixtures: Low water consumption f ixtures like low f low f lushing systems, sensor based f ixtures, waterless urinals, tap aerators etc. to reduce the water usage.
� Instal lation of dual plumbing for using recycled water.
� Use of rain water
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 11 Summary & Conc lusion Page 11 - 10
3 Water
Impact on competing users due to consumption of public supply / ground water as make-up water for HVAC in the campus (resource loss)
� Estimation of daily water consumption based on the HVAC losses, reuse and recycled opt ions.
� Monitoring water use: Use of water meter conforming to ISO Standards would be instal led at the inlet point of water uptake and at the discharge point to monitor the daily water consumption in HVAC unit.
� Use of treated water for STP as make-up water in HVAC system.
� Use of rain water
4 Water
Improper discharge of untreated sewage may lead to impact on surface / ground water quality
� Treatment of sewage and recycling of the treated sewage and ensuring zero discharge.
� Sewage treatment plant proposed. � Treatment unit with pr imary, secondary
and territory treatment proposed
5 Water
Improper storage & disposal of e-waste may lead to leaching of heavy metals leading to contamination
� Storage of e-waste as per Rules and in an isolated area.
� Disposal of e- waste only to the authorized agency
� MoU with the approved agency to be made.
6 Water
Improper storage & disposal may lead to leaching of hazardous waste leading to contamination
� Development of leachate proof intermediate hazardous storage faci li ty.
� Outsourcing of the hazardous waste to the Kerala Pol lut ion Control Board approved agency & MoU to be made with the approved agency.
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 11 Summary & Conc lusion Page 11 - 11
7 Soil
Improper disposal of MSW & BMW waste may lead to impact on land.
� Segregation of waste at source into medical, biodegradable and non biodegradable waste by providing colored bins.
� Medical waste wi ll be disposed off through KSPCB approved vendors
� Disposal of biodegradable Municipal Solid Waste by bio gas unit.
� Disposal of non biodegradable recyclable waste to vendors.
� Disposal of inert waste by land f i l l ing / back f i l l ing.
� For Bio-medical waste - Collect ion & segregation at source by providing appropriate colour coded bins / containers as per the colour coding provided in the Bio-Medical Waste (Management & Handling) Rules.
� The Bio-medical waste from the proposed hospital would be outsourced through a Kerala State Pollut ion Control Board authorized agency (M/s Indian Medical Associat ion Goes Eco Friendly, IMAGE)
8 Soil Improper discharge of untreated sewage may lead to impact on land.
� Treatment of sewage and recycling of the treated sewage and ensuring zero discharge.
9 Soil
Improper storage & disposal of e-waste may lead to leaching of heavy metals leading to contamination
� Storage of e-waste as per Rules and in an isolated area.
� Disposal of e- waste only to the authorized agency & MoU to be made with the agency.
10 Soil
Improper storage & disposal of hazardous waste may lead to leaching of waste leading to contamination
� Development of leachate proof intermediate hazardous storage faci li ty.
� Outsourcing of the hazardous waste to the Kerala Pol lut ion Control Board approved agency & MoU to be made with the concerned agency.
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 11 Summary & Conc lusion Page 11 - 12
11 Biologica
l
Improper disposal of MSW & BMW may attract scavenger avifauna which may lead to dissertat ions of nat ive avifauna
� Segregation of waste at source into medical, biodegradable and non biodegradable waste by providing colored bins.
� Disposal of biodegradable Municipal Solid Waste by bio gas unit & bio-bin system.
� Disposal of non biodegradable recyclable waste to vendors.
� Disposal of inert waste by land f i l l ing / back f i l l ing.
� Plantation of native species of trees / shrubs / herbs / grass for enhancement of avifauna
� Conservation of the existing trees wherever possible.
� Plantation of fruit bearing trees to enhance the avifauna.
� For Bio-medical waste - Collect ion & segregation at source by providing appropriate colour coded bins / containers as per the colour coding provided in the Bio-Medical Waste (Management & Handling) Rules.
� The Bio-medical waste from the exist ing hospital outsourced through a Kerala State Pollut ion Control Board authorized agency (M/s Indian Medical Association Goes Eco Friendly, IMAGE) and the same arrangement will be cont inue for expansion facil ity also.
12 Aesthet ic
s
Improper disposal of MSW may lead to un-aesthet ic condit ions
� Segregation of waste at source into biodegradable and non biodegradable waste by providing colored bins.
� Disposal of biodegradable Municipal Solid Waste by bio gas unit.
� Disposal of non biodegradable recyclable waste to vendors.
� Disposal of inert waste by land f i l l ing / back f i l l ing.
13 Energy Conserva
tion
Adoption of energy in-eff icient vehicles, HVAC system, appliances, l ights etc may lead to wastage of energy
� Use of Euro-III Standard vehicles. � HVAC system and appl iances with 5
Star Rating as per BEE.
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 11 Summary & Conc lusion Page 11 - 13
14 Energy Conserva
tion
Non adoption of renewable sources of energy like solar energy may lead to increase dependency on public supply may lead to consumption of energy by competing users
� Use of Solar energy for water heating � Use of solar energy for common area
light ing in parks and in streets. � Use of solar power plant for common
area l ighting in campus.
5.0 Environmental Monitoring Program
The budget for environmental monitoring for the parameters is calculated
on the basis of CPCB not if ication of charges for environmental monitoring
and analysis. The cost est imate for environmental monitor ing. The total
cost of Environmental Monitor ing Budget during construction phase wil l be
of Rs. 5,80,000/- and operation phase wi ll be of Rs. 9,30,000/-.
6.0 Additional Studies
Risk & Disaster Management - The project proponent has prepared a
well maintained Risk and Disaster Management Plan with regard to
manmade disaster l ike f ire etc as well as natural disaster etc.
Resource & Energy Conservation -The proposed project is an expansion
of existing hospital cum medical college campus project will lead to
ut il izat ion of various natural resources like water resources, construct ion
materials, top soil conservat ion, use of solar energy. As an
environmentally responsible corporate, the project proponent endeavor to
conserve these resources by judicious management and recycling and
strive to build up these resources where possible.
Traffic Impact Assessment Study - As per the traff ic analysis data, the
traff ic volume is within carrying capacity of road as per Indian Road
Congress (IRC) standards.
Social Impact Assessment - Community Need Assessments seek to
gather accurate information representat ive of the needs of a community.
Assessments are performed prior to taking act ion and are used to
determine current situations and ident ify issues for action, establishing
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 11 Summary & Conc lusion Page 11 - 14
the essential foundation for vi tal planning. The process is an invaluable
tool for involving the public in solving problems and developing goals
The project proponent has set apart an amount of Rs. 2.7 Crores (about
1.5% of the project cost) to carry out CER activit ies.
Réhabilitation & Resettlement (R & R) Action Plan - There is no
displacement of people from the core zone of the project, hence
Réhabil itat ion & Resettlement (R & R) is not applicable to the instant
project.
Public Hearing - As per the Terms of Reference provided by the
MoEF&CC vide letter dated 22-06-2018, public hearing is to be conducted
for the instant project.
Thereafter, v ide O.M. F.No.Z-11013/22/2017-IA.II(M) dated 16-03-2018
issued by MoEF&CC, no public hearing is required for building
construction projects.
7.0 Project Benefits - Due to the proposed expansion of exist ing
hospital cum medical col lege project, there wil l be improvement in the
Physical Infrastructure, Improvement in the Social Infrastructure, Increase
in Employment Potent ial to the tune of about 1000 persons direct
employment and about 3,000 persons indirect employment. The operation
of the project also results in addit ional GST and State by way of taxes
and duties. The Govt. Authorities can ut il ize this amount for development
of infrastructure. Due to the sustainable development of the proposed
act iv it ies, the project wil l benef it to the environment.
8.0 Environment Management Plan - The project proponent wil l make
the Environment Cell. A Cell for Environment Management within the
project site, wil l take overall responsibil i ty for co-ordination of the act ions
required for environmental management and mit igation, and to monitor
progress of the mitigat ive measures and actions to be taken by the project
proponent.
The capital cost for environmental management plan during construction
phase will be about Rs. 16 lakhs and recurring cost per annum will be
about Rs. 50 Lakhs.
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 11 Summary & Conc lusion Page 11 - 15
During operat ion phase, the capital cost for environmental management
plan wil l be about Rs. 37 lakhs and recurr ing cost per annum wi ll be
about Rs. 238 Lakhs.
9.0 Ecological Damage & Remediation Plan, Natural & Community
Resources Augmentation Plan - The project proponent wil l spend an
amount of Rs 57,44,000/- (Rupees Fif ty Seven Lakhs Forty Four
Thousand only) on account of Remediation, Natural Resource &
Community Augmentation Plan for 3 years. A bank guaranty for an amount
of Rs. 57,44,000/- will be submitted to the Kerala State Pollut ion Control
Board valid for a period of 3 years. On successful completion of the
remediation plan, natural and community augmentation plan and
verif ication of the same by the Pollut ion Control Board, the bank guaranty
wi ll be released to the project proponent. In case, if the project proponent
failed to implement the remediat ion plan, natural and community
augmentation plan as committed, the bank guaranty wil l be forfeited
*******************************************************************************
M/s SREEV ALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 12 Disclosure of ACO Page 12 - 1
12.0 DISCLOSURE OF CONSULTANT
12.1 The name of consultants engaged with their brief resume.
The team involved in the conduct ion of EIA study and preparat ion of the
EIA report is provided below: -
Name of consultant /
expert
Role in the preparation of EIA report
Qualification & Experience in brief
P. Z. THOMAS EIA Coordinator & *FAE for
Land Use, Air Pollution, Water
Pollution, Solid & Hazardous
Waste.
B.Tech in Civil Engineering with
specialization in industrial waste
engineering.
Working in the Environment field for the
last 29 years.
Jomon M C *FAE – Socio Economic Masters in Social Work (MSW).
Working in the Environment field for the
last 6 years.
Dr. Renoy
Varghese
*FAE - Ecology & Biodiversity,
Soil Conservation
Masters in Zoology. Working in the
Environment field for the last 12 years.
Akhil Chandran V **AFAE - Hydrogeology,
Ground Water & Water
Conservation, Geology .
Masters in Geology.
Working in the Environment field for the
last 2 years.
Mukesh Suroliya
*FAE – Hydrogeology, Ground
Water & Water Conservation,
Geology
Masters in Geology.
Working in the Environment field for the
last 12 years.
Mohan A. Patil *FAE – Air Quality Modeling &
Prediction, Noise & Vibration
M.Tech in Energy Management.
Working in the Environment field for the
last 30 years.
Sunil Gupta *FAE – Risk & Hazard
Management
M.Tech in Chemical Engineering.
Working in the Environment field for the
last 28 years.
*FAE - Functional Area Expert &
AFAE** - Associated Functional Area Expert
M/s SREEV ALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 12 Disclosure of ACO Page 12 - 2
12.2 Profile of Accredited Environmental Consultancy Organization (ACO)
We, M/s ENVIRONMENTAL ENGINEERS & CONSULTANTS PVT. LTD. is
a professionally managed accredited consultancy organizat ion with
Ministry of Environment, Forest and Climate Change, Govt. of India under
the National Accreditation Board for Education and Training (NABET,
QCI) scheme. The ACO is in operat ion for the last 25 years.
We assist our cl ients in obtaining Environmental Clearance under EIA
Notif icat ion, 2006 and CRZ Clearance under CRZ Notif icat ion, 2011 from
the Ministry and various State Level Authorit ies across the country.
We conduct and prepare Environmental Impact assessment (EIA) studies,
Environment Management Plan (EMP), Disaster Management Plan and
Environmental Audit (EA) in area development and townships projects,
large building construction projects, mining projects etc.
We also design, fabricate, instal l and commission various pollut ion control
equipments (both l iquid and air) for various industries in the country on
turnkey basis.
We have more than 1,000 sat isf ied customers in the building construction,
township and mining sector for whom we have provided our services in
preparation of EIA / EMP reports and technical assistance in gett ing
Environmental Clearance and CRZ Clearance across the country. Also, in
the series of our achievements, the success story of M/s Lavasa
Corporation Ltd. (M/s LCL) ( a hil l stat ion township near Pune & LCL is
an enterprise of M/s Hindustan Construct ion Company Ltd., Mumbai )
spread on an area of 5,000 ha., about 12,500 acres ( 2,000 ha. – 1s t
Phase + 3,000 ha. – 2nd Phase ) and M/s Smart City Kochi Infrastructure
Pvt. Ltd., Kochi, Kerala (an IT/ITES SEZ township project) spread on an
area of 100 hectares.
M/s SREEV ALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 12 Disclosure of ACO Page 12 - 3
UNIQUE FEATURES OF THE ACO
� Accredited Environment Consultancy Organization by NABET /
QCI with the fol lowing sectors :-
Sector
Nos.
Name of Sector
1 Mining of mineral – Opencast only
38 Building and large construction projects including shopping
malls, mult iplexes, commercial complexes, housing estates,
hospitals, insti tutions
39 Townships and Area development Project
� Turnkey supply of Air Pollution Control System to USA: Supplied
a “Fume extract ion cum Scrubber System” to M/s Jindal United
Steel Corporation , Texas, USA ( USA’s largest Steel Plate Mil l
Company ). System meets USEPA & OSHA standards of US
Government (Stringent than Indian Standards).
� All Air / Water Pollut ion Control systems supplied t i l l date are
approved and accepted by concerned State Pollut ion Control
Boards / Ministry of Environment & Forests al l over India since it
meets compliance requirements.
� Designed and supplied ful l proof smoke free “Dust / Fume
Extraction cum Bag f ilter type Air Pollut ion Control cum dust
recovery system” for highly polluting secondary Lead furnaces
( Payback less than a year ensured ).
� Turnkey Systems instal led all over the country and operating
sat isfactori ly in various states (Delhi, Punjab, Haryana,
Uttaranchal, UP, Chattisgarh, J & K, Andhra Pradesh, Tamil Nadu,
Karnataka, Kerala, Gujrat, Rajasthan etc.)
� Eff luent Treatment Plants designed with an object ive of Recycling
the treated eff luents to conserve water.
M/s SREEV ALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 12 Disclosure of ACO Page 12 - 4
� Dust / Fume extraction cum Bag Fil ter type Air Pollut ion Control
Systems have been tested by the reputed Environmental
Laboratory of National Productivity Council, Delhi and evaluated
as satisfactory.
� Approved Vendor for a FORTUNE 500 Indian Publ ic Sector
Undertaking Oil Company (Indian Oil Corporation) for Pollut ion
Control Equipments.
� Head Office :-
P. Z. THOMAS ( Managing Director )
M/s Environmental Engineers & Consultants Pvt. Ltd.
A1 – 198, Janak Puri, New Delhi – 110058.
Ph. No. 011-25507190 Telefax No. 011-25622604
E-mail :- [email protected] & [email protected]
Mobile No. 9350873385, 9811080469
� Branch Office Address: -
M/s Environmental Engineers & Consultants Pvt. Ltd.
Apartment No. C-306, Kanchanjunga Apartments,
Palarivattom, Kochi, Ernakulam, Kerala-682025.
E-mail :- [email protected]
Ph. 0484-4034320.
The copy of the accreditation certi f icate of the ACO from NABET / QCI is
provided at Annexure No. 12.1.
*******************************************************************************
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 13 Damage Assessment & Remediat ion P lan
Page 13 - 1
13.0 ECOLOGICAL DAMAGE & REMEDIATION PLAN, NATURAL & COMMUNITY RESOURCES AUGMENTATION PLAN 13.1 Introduction
M/s Sreevalsam Educational Trust proposed an expansion of exist ing
Hospital cum Medical College project at Survey Nos. 157/2, 159/3, 158/1,
157/0, 158/1, 159/3, 158/2, 158/5, 159/1, 159/2, 157, 159/3, 164/3, 164/7,
164/4, 163/3, 158/7, 158/3, 158/4, 166/2, 166/1, 156/3, 164/1, 156/3,
164/1, 164/2, 156/4, Edappal Vil lage, Ponnani Taluk, Malappuram District,
Kerala. The plot area of the Hospital cum Medical College Project is
9.4534 ha (94,534.56 sq. m.) and the total buil t-up area is 1,38,937.50 sq.
m. (existing 53,889.72 sq.m. + proposed 85,047.78 sq.m.).
Building construction of 53,889.72 sq.m. of the hospital cum medical
college is already completed. The teaching hospital component is for a
built -up area of 32,160 sq.m. and the educational component is with
built -up area of 21,729.72 sq.m. It is proposed to construct addit ional
built -up area of 85,047.78 sq.m and the total cumulative built -up area wil l
be 1,38,937.5 sq.m.
The land was purchased and registered between the year of 2010 to 2011
and started the construct ion work of Teaching Hospital in 2011 as per the
Building permit vide permit no. 224/11-12 dated 03-11-2011 obtained from
Edappal Grama Panchayat for a built-up area of 5,783.70 sq.m.
Subsequently, the expansion of the building was carried out with the
renewal of building permit vide permit no. B2-224/11-12 dated 27-06-2012
valid upto 26-06-2015 issued by the Panchayat for a cumulat ive built -up
area of 32,160 sq.m. in 2012. This work was carried out without pr ior
Environmental Clearance and the construct ion of this bui lding
is completed. Further, renewal of building permit vide permit no.
A5-365/14-14 dated 24-03-2014 was issued for Academic block, Hostels
with a cumulat ive built-up area of 43,636 sq.m. and construction of
21,729.72 sq.m. is completed. Educat ional institutions are exempted from
the purview of EIA Notif ication vide Notif icat ion dt. 22-12-2014. For the
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 13 Damage Assessment & Remediat ion P lan
Page 13 - 2
f irst t ime, the requirement of prior Environmental Clearance was inserted
in Kerala Municipal ity Building Rules (KMBR) by an amendment of KMBR
made in 05/02/2013.
Therefore, the project proponent was not aware of the requirement of
prior Environmental Clearance and constructed the Teaching Hospital
building without obtaining prior Environmental Clearance and hence the
violated the provisions of Environment Protect ion Act, 1986.
Ministry of Environment, Forests & Climate Change (MoEF & CC) issued a
Notif icat ion dated 14/03/2017 (Notif icat ion No. S.O. 804 (E)) and gave
one time opportunity to the projects who have commenced their activity
without taking prior Environmental Clearance violated the EIA Notif ication,
2006.
An application with draft Terms of Reference (ToR) for EIA Study and for
obtaining Environmental Clearance under the provision of MoEF&CC
Notif icat ion dt. 14/03/2017 was submitted at MoEF&CC on 23/06/2017
vide File No. 23-89/2018-IA-III (V).
Thereafter, the proposal was considered in the 06 th meeting of Expert
Appraisal Committee (EAC) at MoEF&CC on 19 t h - 20 th , Apri l, 2018 vide
agenda item No. 6.3.7 for grant of Terms of Reference (ToR) for
undertaking Environment Impact Assessment (EIA) studies and
preparation of Environment Management (EMP).
The EAC recommended the project for grant of “ToR” for undertaking
Environment Impact Assessment (EIA) study and preparation of
Environment Management Plan (EMP). The Ministry accepted the
recommendations of EAC and the “ToR” was approved and issued vide
Letter No. 23-89/2018-IA.III dated 22/06/2018.
With a view to assess the environmental impacts due to the construct ion
act iv it ies, to suggest the mitigat ion measures, to assess the ecological
damage due to the i l legal construct ion, to prepare remediation plan and
the natural and community resource augmentat ion plan as per the
approved ToR granted.
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 13 Damage Assessment & Remediat ion Plan
Page 13 - 3
13.2 Damage Assessment & Remediation Plan
The damage assessment & remediation plan is prepared for each environmental facets l ike air,
noise, land, water, ecology & socio-economic and the same is provided at table 13.1 below.
Table 13.1 - Damage Assessment & Remediation Plan
Air Environment
Activities which caused damage
Concern Issues / impacts
Damage Assessment
Remediation Plan Budgetary Estimate (in Rs.)
1. Site Clearance
2. Excavation
3. Infrastructure
development .
4. Transportation
of materials
5. Operation of
D.G. sets and
other construction
equipments /
machinery.
6.Construction
activity.
1. Dust generation
2. Gases emissions
3. Vehicle exhaust
4. Emissions from fire
wood and cooking
gas.
1. Air Pollution due
to particulates
and gases
2. Change in water
quality due to
dust
3. Emission of VOC
from wood work
and painting.
1. Dust suppression and Water
sprinkling system at construction
sites outside the project site
where there is no requirement of
E.C.
2. Conduction of a vehicle check up
camp in consultation with the
motor vehicle Department once
in 6 months.
3. Providing enclosures / wind
breakers (shade nets) at
construction sites within the
panchayat (public work places)
1. The dust suppression and
water sprinkling system
consists of water
sprinkler nozzles (about
½ dozen @ Rs. 1,000
per nozzle i.e. Rs.
6,000), Online twin
filtration system (Rs.
15,000), Booster pump
(1 HP (@ Rs. 10,000),
Water distribution
pipeline (LS Rs. 10,000)
and water storage tank
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 13 Damage Assessment & Remediat ion Plan
Page 13 - 4
7. Temporary stay
of construction
workers.
where loose construction
materials are stored outside the
project site.
4. Regular monitoring of ambient air
quality near sensitive locations (2
locations) in the panchayat (once
in 3 months) in consultation with
local panchayat.
5. Providing Personnel protection
equipments to the health
department of the panchayat for
supply the same to the
construction workers engaged in
construction sites
6. Regular wetting of loose
construction materials at sites
(public work places) outside the
project.
(5,000 ltr @ Rs.
25,000.). Labour cost of
Rs. 10,000. The total
cost on water sprinkling
and dust suppression
system is
Rs. 76,000/-
2. Wind breakers /
barricades in the
periphery of project site
(3 m. height GI sheet)
(Rs. 1,00,000/-)
3. Vehicle check up camp (@Rs. 10,000 per camp and Rs. 20,000 annual)
4. Ambient air quality monitoring in sensitive areas (@Rs. 5,000 per month x 12 months i.e. Rs. 60,000 x 2 locations = Rs. 1,20,000 ).
Total cost on remediation measures on Air Environment is Rs. 3,16,000/-
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 13 Damage Assessment & Remediat ion Plan
Page 13 - 5
Noise Environment
Activities which
caused damage
Concern Issues /
impacts
Damage
Assessment Remediation Plan
Budgetary Estimate
(in Rs.)
1. Movement of
construction
equipments and
machineries.
2. Construction
activities
3. Operation of D.G.
set of 100 kVA
capacity.
1. Noise generation &
increase in noise level.
2. Noise & vibration due
to construction activity
and operation of D.G.
set of 62.5 KVA
capacity.
1.Health issue due
to increase in
noise level to
construction
workers
1. Providing Personnel protective
equipments (PPE) to the to the
Health Department of the
panchayat
Rs. 50,000/- (LS.)
Total cost on remediation measures on Noise Environment is Rs. 50,000/-
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 13 Damage Assessment & Remediat ion Plan
Page 13 - 6
Land Environment
Activities which
caused damage
Concern Issues /
impacts Damage Assessment Remediation Plan
Budgetary Estimate
(in Rs.)
1. Excavation 1. Un-manage / un-
control storage of
excavated soil,
2. Loosing its texture,
productivity and
fertility status,
3. Chocking of drains
due to surface runoff
during rainy season.
4. Change in topography
and drainage pattern
1. Change in soil quality
(texture, productivity
and fertility status)
(Excavation of top soil)
2. Soil degradation,
overflow of drains due
to chocking with soil
during rainy season,
dust pollution in dry
season
1. Assistance to the panchayat
in storage of excavated top
soil in a designated place
and consume it for the
common greenery
development.
Rs. 50,000/- for creating
barriers to avoid erosion and
to maintain its integrity so as
to use it further for
landscaping.
2. Solid waste
generation during
construction activity
1. Un-managed disposal
of domestic solid
waste without
1. Contamination or
degradation of soil /
water quality.
1. Printing & distributing
leaflets on proper
segregation (degradable
Rs. 10,000 (LS) for printing &
distribution of leaflets.
Rs. 30,000/- for 10 bins
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 13 Damage Assessment & Remediat ion Plan
Page 13 - 7
segregation.
2. Un-managed disposal
of construction wastes
2. Effect on plant growth
3. Nuisance due to un-
managed disposal or
storage of MSW and
construction wastes.
and non-biodegradable at
source itself)
2. Proving colour coded bins
in the panchayat building,
school, etc. (10 bins).
(@Rs. 3,000 per bin).
Total Rs. 40,000/-
3. Generation of
hazardous wastes
like empty cans of
varnish , paints etc.
during construction
activity
1. Un-managed
dumping, nuisance
creation, toxicity
generation, health
effect
1. Contamination of soil /
water
2. Effect on flora / fauna,
3. Health effect on
workers handling
chemicals / paints etc.
1. Providing a isolated leachet
proof storage facility for
hazardous waste within the
panchayat in consultation
with the panchayat.
1. Secured intermediate
leachate proof facility for
storage (LS. Rs. 50,000)
Total cost on remediation measures on Land Environment is Rs. 1,30,000/-
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 13 Damage Assessment & Remediat ion Plan
Page 13 - 8
Water Environment
Activities which caused damage
Concern Issues / impacts Damage Assessment Remediation Plan Budgetary Estimate
(in Rs.)
A. Fresh water
1. Site preparation
& infrastructure
development.
2. Construction
activities.
3. Temporary stay
of construction
workers (domestic
consumption).
1. Utilization of large quantity of
water for dust suppression,
consolidation and compaction.
2. Impact on competing users
due to large consumption of
water for various construction
activities (@1.10 KL per sq.m.
of built-up area for the
following activities : Ready mix
concrete (RMC) production,
Cement block / brick
production, Curing, Bricks /
block soaking, concrete curing,
masonry and cement
plastering curing, flooring
works etc.). total water
consumed is about 59,000 KL
1.The rain water stored
at site was used for
construction
purposes.
2.Through tankers from
Kerala Water
Authority water
Supply Scheme for
domestic
consumption.
1.Restoration of 5
abandoned wells within
the panchayat including
the half yearly water
sampling & monitoring.
2. Rehabilitation of village
pond by providing soft
landscaping around the
pond and cleaning.
Rs. 50,000/- (A )for
restoration of abandoned
wells (Rs. 10,000 x
5 wells) + Rs. 50,000/-
(B) for water sampling and
monitoring (Rs. 5,000 x 10
samples).
Total (A +B)= Rs. 1,00,000/-
and Rs. 4,00,000/- for
Rehabilitation of village
Pond.
Total = Rs. 5,00,000/-
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 13 Damage Assessment & Remediat ion Plan
Page 13 - 9
(A).
3.Domestic water consumption
of about 27 KL/day (About 200
labour x 135 ltr = 27 KLD) for
about 1,000 days (over a
period of 8 years) i.e. 27,000
KL (B).
The total fresh water consumed
is 86,000 KL (A+B).
B. Waste water 1. Waste water generation from
cleaning machinery,
equipments and vehicles,
2. Domestic waste water
generation from workers
1. Discharge of
contaminated water
to the land and to the
water channel /
drainage .
2. Discharge of
domestic sewage to
the project site.
1. Setting up of mobile
toilets for the workers in
public works (panchayat
development works)
outside the project site
2. Setting up of a STP for
the treatment of sewage
from the panchayat
school
1. Rs. 80,000/- towards set
up of 2 units of portable
toilet at site (1 for male and
1 for female)
2. Rs. 6,50,000 on setting up
of an STP of 5 KLD
capacity.
Total cost on remediation
measures is Rs. 7,30,000/-
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 13 Damage Assessment & Remediat ion Plan
Page 13 - 10
C. Storm water
runoff 1. Sediment load 2. Contamination of run off due
to non-point source pollution.
1. Deterioration of the
water channel / drain
and impact on
aquatic life.
1. Proper channalization of
storm water with
intermediate grit
chambers (0.5 km.) in the
public drain within the
panchayat. 2. The vicinity of the project
site is frequently cleaned
to remove all non-point
sources before monsoon.
1. Chanalization of storm
water (Rs. 4,00,000/-). 2 Frequent cleaning of the
vicinity of site before
monsoon (Rs. 50,000/-). Total cost on remediation
measures is Rs. 4,50,000/-
(L.S. estimated)
Total cost on remediation measures on Water Environment is Rs. 16,80,000/-
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 13 Damage Assessment & Remediat ion Plan
Page 13 - 11
Ecological Environment
Activities which
caused damage
Concern Issues /
impacts
Damage
Assessment Remediation Plan
Budgetary Estimate
(in Rs.)
1. Site clearance
2. Cutting of
existing trees
1. Loss of vegetation in
the project site (about
100 trees were existing
at site)
2. Habitat loss to fauna
specially avi-fauna.
Loss of native flora
and aesthetic view
1. Plantation of native species as per
the guidelines (@1:10) to
compensate the cutting trees and
vegetation to regenerate the
aesthetic view.
2. Development of eco-friendly
situation in the project site to
welcome to faunal species again
at the project site
3. Development of butterfly garden
within the site.
4. Development of medicinal garden
within the site.
5. About 900 trees are already
existing / planted at site.
1. Plantation with native
species of flowering and
fruit bearing trees to
compensate the removal of
trees. About 1000 trees
within the surrounding area
are proposed for plantation
at a cost of @ Rs. 1,100
per plant which includes
maintenance for three
years. The total cost
estimate for tree plantation
is 1,000 trees x Rs. 1100 =
Rs. 11,00,000/-.
2.Cost of development of
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 13 Damage Assessment & Remediat ion Plan
Page 13 - 12
butterfly garden is
Rs. 2,00,000/- (L.S.
estimate)
3.Cost of development of
medicinal garden is Rs.
1,50,000/- (L.S. estimate)
4.Rs. 1,00,000/- for
development of panchayat
park / avenue plantation
towards habitat
compensation.
Total Rs. 13,50,000/-
Total cost on remediation measures on Ecological Environment is Rs. 13,50,000/-
M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report
Chapter 13 Damage Assessment & Remediat ion Plan
Page 13 - 13
Socio Economic Environment
Activities which
caused damage
Concern Issues /
impacts
Damage
Assessment
Remediation Plan Budgetary Estimate
(in Rs.)
Occupational Health
and amenities
1. Health aspects of the
construction workers
and facilities related to
hygiene and
sanitation.
2. Pressure on the
existing infrastructure
1. Secure facilities
to the construction
workers
1. Providing first aid kits (20
nos.) to the construction
sites (public works within
the panchayat).
2. Providing a wheel chair
(10 nos.) to the primary
health centre within the
panchayat and in
consultation.
Rs. 40,000/- (@Rs. 2,000 per
kit)
Rs. 1,20,000 (@Rs. 12,000
per wheel chair)
Total = Rs. 1,60,000/-
Total cost estimate on remediation measures on Socio Economic Environment is Rs. 1,60,000/-
M/s Sreevalsam Educational Trust EIA/EMP Report
Chapter 13 Damage Assessment & Remediat ion Plan Page 13 - 14
13.3 Summary of Remediation Plan – 3 Year Plan
The summary of remediation plan for 3 years is given in table 13.2 below.
Table 13.2 - Summary of remediation plan for 3 years
SN Activities Proposed 1st year 2nd Year 3rd Year Total
( in Rs.)
1. Remediation measures
on Air Environment 1,20,000 1,20,000 76,000 3,16,000
2. Remediation measures
on Noise Environment 20,000 20,000 10,000 50,000
3. Remediation measures
on Land Environment 50,000 45,000 35,000 1,30,000
4. Remediation measures
on Water Environment 6,80,000 6,50,000 3,50,000 16,80,000
5. Remediation measures
on Ecology Environment 5,40,000 5,50,000 2,60,000 13,50,000
6. Remediation measures
on Socio Environment 50,000 60,000 50,000 1,60,000
Annual total 14,60,000 14,45,000 7,81,000 36,86,000
M/s Sreevalsam Educational Trust EIA/EMP Report
Chapter 13 Damage Assessment & Remediat ion Plan Page 13 - 15
13.4 Natural Resources Augmentation Plan – 3 Year Plan
The natural resources augmentation plan for 3 years is prepared and is
provided at table 13.3 below.
Table 13.3 - Natural resources augmentation plan for 3 years
SN
Activities Proposed 1st year 2nd Year 3rd Year Total
( in Rs.)
1. Development of greenery in the surrounding area and road s ide plantation (along the approach road near to the project s i te, about 0.5 km in the northern direct ion of the project s ite)
50,000 50,000 60,000 1,60,000
2.
Provis ion of dr inking water facil i t ies through construction of open wells. 2 wells in each year in Edappal v i l lage and i ts maintenance
50,000 50,000 50,000 1,50,000
3.
Maintenance (patch work of pot holes) of approach road near to the project s i te, about 0.5 km in the northern direction of the project s i te in consultat ion with the public works department (PWD).
1,00,000 1,50,000 1,80,000 4,30,000
4.
Maintenance of water pipel ine network in Edappal town in consultat ion wi th Kerala Water Author ity (KWA).
40,000 40,000 40,000 1,20,000
5.
Providing solar street l ight in Darul Hidaya Orphanage Higher Secondary School, Edappal ( located at about 1.5 km toward north west d irect ion of the proposed project) for common area l ight ing in consultat ion wi th the school administrat ion
30,000 30,000 35,000 95,000
6.
Providing roof rain water storage tank (capacity of 5,000 li teres) with pipel ine for LP School located about 0.5 km toward south east direct ion.
50,000 50,000 55,000 1,55,000
7.
Maintenance of storm water drainage in the Govt. Higher Secondary School, Edappal located at about 2.5 km in nor th direct ion
18,000 20,000 45,000 83,000
Annual total 3,38,000 3,90,000 4,65,000 11,93,000
M/s Sreevalsam Educational Trust EIA/EMP Report
Chapter 13 Damage Assessment & Remediat ion Plan Page 13 - 16
13.5 Community Resources Augmentation Plan - 3 Year Plan
The Community Resources Augmentat ion Plan for 3 years is prepared and
is provided at table 13.4 below.
Table 13.4 - Community Resources Augmentation Plan for 3 years
Sr. No.
Activities Proposed 1st year 2nd Year 3rd Year Total
( in Rs.)
1. Maintenance of irr igat ion facil i t ies to the small farmers in Edappal vi l lage (support for irr igation in consultat ion with Irr igat ion Dept., Govt. of Kerala)
40,000 40,000 30,000 1,10,000
2.
Maintenance of k itchen and providing LPG for 3 years (noon meal preparation) in Govt. school located in Edappal vi l lage in consultat ion with school author it ies
20,000 40,000 80,000 1,40,000
3.
Periodic medical check-up camp for eyes, skin, dental twice in a year in consul tation with Edappal Vi l lage Panchayat / Health Department, Govt. of Kerala
50,000 50,000 50,000 1,50,000
4.
Distr ibut ion of medic ine to the needy patients and distr ibut ion of blood sugar check up k it in the Panchayats area of Edappal Vi l lage in consultat ion wi th Health Department, Govt. of Kerala.
50,000 40,000 30,000 1,20,000
5.
Providing health care to the farmers in Edappal vi l lage on consultat ion wi th the Heal th Dept. of Govt. of Kerala.
25,000 30,000 40,000 95,000
6.
Assistance in development of technical skil ls and tra in ing for f i rst aid to the emergency casualty to the youth of farmers in Edappal vi l lage
20,000 35,000 45,000 1,00,000
7.
Assistance in providing study materia ls, uniform, books to the poor students (50 students) of Govt. School , Edappal
20,000 25,000 30,000 75,000
8.
Scholarship to the br i l l iant students (10 students) of h igher secondary school / vocational higher secondary (100 students), Edappal for support to their higher education
30,000 25,000 20,000 75,000
ANNUAL TOTAL 2,55,000 2,85,000 3,25,000 8,65,000
M/s Sreevalsam Educational Trust EIA/EMP Report
Chapter 13 Damage Assessment & Remediat ion Plan Page 13 - 17
13.6 Summary of Remediation, Natural Resource & Community Augmentation Plan
Table 13.5 - Summary of Remediation, Natural Resource & Community Augmentation Plan
Sr.
No.
Activities
Proposed
1st year 2
nd Year 3
rd Year Total
(in Rs.)
1. Remediation plan 12,00,000 14,00,000 10,86,000 36,86,000
2. Natural Resource
plan 4,00,000 4,40,000 3,53,000 11,93,000
3. Community
Augmentation plan 3,00,000 3,20,000 2,45,000 8,65,000
Total 19,00,000 21,60,000 16,84,000 57,44,000
The project proponent wil l spend an amount of Rs 57,44,000/- (Rupees
Fifty Seven Lakhs Forty Four Thousand only) on account of
Remediation, Natural Resource & Community Augmentat ion Plan for 3
years. A bank guaranty for an amount of Rs. 57,44,000/- wil l be submitted
to the Kerala State Pollut ion Control Board valid for a period of 3 years.
On successful completion of the remediation plan, natural and community
augmentation plan and verif icat ion of the same by the Pollution Control
Board, the bank guaranty wil l be released to the project proponent. In
case, if the project proponent failed to implement the remediat ion plan,
natural and community augmentat ion plan as committed, the bank
guaranty will be forfeited.
*******************************************************************************
Appraisal by SEAC with a view to assess that the construction at the site
which under prevailing laws is permissible and which can be run sustainably
under compliance of environmental norms with adequate environmental safe
guards.
Closure of the project along
with other actions under law The project will be prescribed the appropriate Terms of
Reference for undertaking Environment Impact
Assessment and provision of Environment
Management Plan. The SEAC will prescribe a specific
Terms of Reference for the project on assessment of
ecological damage, remediation plan & natural and
community resource augmentation plan.
Application to be submitted by PP at SEIAA
Findings of SEACNEGATIVE AFFIRMATIVE
Preparation & submission of Environment Impact
Assessment and Environment Management Plan
which includes assessment of ecological damage,
remediation plan and natural and community resource
augmentation plan by PP at SEIAA.
The SEAC will stipulate the implementation of
Environmental Management Plan, comprising
PROCEDURE AS PER NOTIFICATION dt.14.03.2017 AND dt. 08.03.2018Annexure No. 1.2
Environmental Management Plan, comprising
remediation plan and natural and community resource
augmentation plan corresponding to the ecological
damage assessed as a condition of environmental
clearance.
The SEAC will quantify the amount of remediation plan
and Natural and Community Resource Augmentation
Plan which will be finalized by SEIAA.
PP need to submit bank guaranty equivalent to the
amount finalized by SEIAA to the State Pollution
Control Board.
After receipt of the acknowledgement of submission of
bank guaranty, SEIAA shall grant Environmental
Clearance to PP.
Successful implementation of the remediation plan and
Natural and Community Resource Augmentation Plan
by PP.
After the recommendation, (on the successful
implementation), by the Regional Office of the Ministry
and SEAC and after approval of the same by SEIAA,
the bank guaranty will be released to PP.
1
SCOPE OF THE STUDY AND COMPLIANCE TERMS OF REFERENCE IN THE EIA REPORT
Sr. No.
Terms of Reference Brief of the Compliance to the ToR Condition Reference in
the EIA report
1. Project description, its importance and the benefits
Chapter 1, Chapter 2 & Chapter 8
2. Project site details (location, toposheet of the study area of 10 km, coordinates, google map, layout map, land use, geological features and geo-hydrological status of the study area, drainage)
Project site details & Location
M/s Sreevalsam Educational Trust proposed an expansion of exist ing Hospital cum Medical College project at Survey Nos. 157/2, 159/3, 158/1, 157/0, 158/1, 159/3, 158/2, 158/5, 159/1, 159/2, 157, 159/3, 164/3, 164/7, 164/4, 163/3, 158/7, 158/3, 158/4, 166/2, 166/1, 156/3, 164/1, 156/3, 164/1, 164/2, 156/4, Edappal Vil lage, Ponnani Taluk, Malappuram District, Kerala. The plot area of the Hospital cum Medical College Project is 9.4534 ha (94,534.56 sq. m.) and the total buil t -up area is 1,38,937.50 sq. m. (existing 53,889.72 sq.m. + proposed 85,047.78 sq.m.).
Toposheet of the study area of 10 km
Toposheet of the study area is provided in Figure 2.5
Coordinates Latitude (N) - 10046‘00.86“ to 100 45’48.56“ Longitude (E) - 76000’36.45” to 760 00’23.53” (Refere Chapter-1, Page 1-5)
Google map Google map superimposed with project boundary is provided at Figure 2.4
Chapter 1, Chapter 2, Chapter 3
Annexure No. 1.8
2
Layout map Layout map (Conceptual plan) is provided at Figure 2.1
Land use Land use map is provided at Figure 3.4
Geological features & Geo-hydrological status of the study area
Details of Geological features are provided at Item 2.5 in Chaper-2 and Item no. 3.7.3 in Chapter-3
3. Land use as per the approved Master plan of the area, Permission / approvals required from the land owning agencies, Development Authorit ies, Local Body, Water supply & Sewerage Board etc.
The Land Use Certif icate and Land Conversion Cert if icate issued by Tahsildar, Ponnani on 31-03-2014 stat ing that the land is "do not fal l under Agricultural use and this land can be used for Education purpose to establish Education Institut ions". The copy of the said Land Conversion Cert if icate is attached at Annexure No. 1.6A & 1.6B
Chapter 1
4. Land acquisit ion status, R & R details
There is no displacement of people from the core zone of the project, hence Réhabil itat ion & Resett lement (R & R) is not applicable to the instant project.
Chapter 7
5. Forest and Wildli fe and eco-sensit ive zones, if any in the study area of 10 km - Clearance required under the Forest (Conservation) Act, 1980, the Wildl ife (Protection) Act, 1972 and /or the Environment (Protect ion) Act, 1986.
There is no Forest and Wildl ife and eco-sensit ive zones within the study area of 10 km. radius.
Chapter 2
6. Baseline environmental study for ambient air (PM10, PM2.5, SO2, NOx & CO), water (both surface and ground), noise and soil for one month
The Baseline environmental study for ambient air (PM10, PM2.5, SO2, NOx & CO), water (both surface and ground), noise and soil was carried out and the detai ls are provided in Chapter 3
Chapter 3
3
(except monsoon period) as per the MoEF&CC/CPCB guidelines at minimum 5 locations in the study area of 10 km.
7. Detai ls on f lora and fauna and socio-economic aspects in the study area
Details on f lora and fauna and socio-economic aspects in the study area is provided in Chapter 3
Chapter 3
8. Likely impact of the project on the environmental parameters (ambient air, surface and ground water, land, f lora and fauna and socio-economic etc.)
The likely impact of the project on the environmental parameters (ambient air, surface and ground water, land, f lora and fauna and socio-economic etc.) is described in Chapter 4.
Chapter 4
9. Source of water for dif ferent identif ied purposes with the permissions required from the concerned authorit ies, both for surface water and the ground water (by CGWA) and the case may be, Rain water harvesting etc.
Source of Water during construction phase
The sources of water for construct ion purposes wil l be from exist ing well water, stored rain water in pond and recycled water from existing STP. For domestic purposes, the sources of water will be from well water. There are open well (1 no.) and tube well (5 nos.) existing at “Sreevalsam Inst itute of Medical Sciences” campus. Source of Water during operation phase
The sources of water for meeting the domestic requirement as well as other requirements during operation phase of the proposed hospital cum medical col lege project will be from exist ing wells, stored rain water and recycled water from STP / ETP. Daily Water Requirement during operation phase The total daily water consumption for the proposed project would be about 1,328 KL (fresh water 677 KL + recycled water 651 KL). The f irst day fresh water requirement is 1,328 KL and subsequent days, the daily fresh water requirement is 677 KL. The daily domestic water consumption is 870 KL (f lushing purposes 647 KL + non-
Chapter 2
4
flushing purposes 223 KL). The details are given below :-
S. N.
Particulars Daily
Requirement (in KL)
Sources of water
1.
Domestic Water Requirement (Non-Flushing purposes )
647
Fresh water (Stored Rain
water and Ground water)
2. Domestic Water Requirement (Flushing purposes)
223 Recycled water
from STP
3. Hort iculture Water Requirement
55 Recycled water
from STP
4. Boiler water requirement
20 Recycled water
from STP
4.
Make-up Water Requirement for Cooling Towers attached with air conditioning system
353 Recycled water from STP/ETP
5. Laboratory & Laundry requirement
30
Fresh water (Stored Rain
water and Ground water)
10. Waste water management (treatment, reuse and disposal) for the project and also in the study area
The water balance chart showing the waste water management details and is provided in Figure 2.15 in Chapter 2
Chapter 2
11. Management of solid waste and the construct ion & demolition waste for the project vis-a-vis the Solid Waste Management Rules, 2016 and the Construction &
The Management of solid waste and the construction & demolit ion waste for the project vis-a-vis the Solid Waste Management Rules, 2016 and the Construction & Demolit ion Rules, 2016
Chapter 2
5
Demolit ion Rules, 2016
12 Energy eff icient measures (LED l ights, solar power etc.) during construction as well as during operational phase of the project
The details are elaborated in Chapter 7 Chapter 7
13 Assessment of ecological damage with respect to air, water, land and other environmental attributes. The collection and analysis of data shall be done by an environmental laboratory duly not if ied under the Environment (Protection) Act, 1986, or an environmental laboratory accredited by NABL, or a laboratory of a Counci l of Scientif ic and Industrial Research (CSIR) inst itution working in the field of environment.
The baseline monitoring on air, water, noise & soil was carried out through NABL accredited laboratory.
Chapter 3
14 Preparation of EMP comprising remediat ion plan and natural and community resource augmentat ion plan corresponding to the ecological damage assessed and economic benefits derived due to violat ion.
Details are provided in Chapter 13 Chapter 13
15 The remediation plan and the natural and community resource augmentat ion plan to be prepared as an
Details are provided in Chapter 13 Chapter 13
6
independent chapter in the EIA Report by the accredited consultants.
16 Public hearing As per the Terms of Reference provided by the MoEF&CC vide letter dated 22-06-2018, public hearing is to be conducted for the instant project. Thereafter, vide O.M. F.No.Z-11013/22/2017-IA.II(M) dated 16-03-2018 issued by MoEF&CC, no public hearing is required for building construction projects.
Chapter 7
**************************