t SREEVALSAM - Environmental Clearance

368
Reg No 53/2010, Kololambu.P.O, Naduvattom, Edappal - Malapuram - 679576, Kerala Ph:0494 2661144,2661000 E-mail: [email protected] www.sreevalsam.in EDUCATIONAL TRUST The Member Secretary, Dt. 06-09-2019 State Environment lmpact Assessment Authority (SEIAA), Thiruvananthapuram, Ke ra la. Ref.:-1. Proposal no. lA/KL/NCPl70246l20'1'7 dt. 11-10'2017 & F.No.23-89/2018-lA-lll 2.ToR Approval letter dt. 22-06-2018 3. Notification dt. 14-03-2017 Sub.:- Environment Clearance - Expansion of Hospital cum Medical College Campus Project at Edappal Village, Ponnani Taluk, Malappuram District, Kerala - Submission of EIA/EMP Report - Reg. Respected Sir, For the purposes of obtaining Environmental Clearance for the above mentioned project, we submitted application along with draft Terms of Reference (ToR) at MoEF&CC on 11-10-2017 under the provisions of Notification dl. 14-03-2017. The draft ToR was considered and approved by EAC in its 6th meeting held on 19/20 April, 2018 and the approved ToR letter was communicated to us by MoEF&CC vide letter dt. 22-06-2018. The EIA study was conducted as per the approved Terms of Reference. Now, we hereby submit the EIA/EMP report in compliance to the ToR letter dt.22-06-2018 for obtaining Environmental Clearance for our project. It may be kindly noted that the project has applied under the provisions of Notification dated 14-03-2017 (a Notif ication providing a one time opportunity to the project proponent who have not taken prior Environment Clearance before the commencement of construction / activity). An amount equivalent to Rs. 57.44 Lakhs is set apart based on the damage assessment and its remediation plan, natural and community resources augmentation plan. This amount is over and above the CER component and the EMP component. Please note that the processing fees of Rs. 2 Lakhs was submitted at SEIAA, Kerala on 16-03-2017 vide D.D. no. 525773 dt. 08-03-2017, lndian Overseas Bank. The copy of the said acknowledgment received from SEIAA, Kerala vide letter dated 12-O1-2017 is attached at Annexure No. 1. ln view of the above submissions, we humbly request you to consider our application and accord Environmental Clearance to our project at the earliest. Thanking yo u, Yours res pectfu lly, For Sreevalsam E Raja n Ac h uthan (Secretary & Au E ncl. :- As abov duca Na tho ional I r t e 6,t SREEVALSAM

Transcript of t SREEVALSAM - Environmental Clearance

Reg No 53/2010, Kololambu.P.O, Naduvattom, Edappal - Malapuram - 679576, Kerala

Ph:0494 2661144,2661000 E-mail: [email protected] www.sreevalsam.inEDUCATIONAL TRUST

The Member Secretary, Dt. 06-09-2019State Environment lmpact Assessment Authority (SEIAA),Thiruvananthapuram, Ke ra la.

Ref.:-1. Proposal no. lA/KL/NCPl70246l20'1'7 dt. 11-10'2017 & F.No.23-89/2018-lA-lll2.ToR Approval letter dt. 22-06-20183. Notification dt. 14-03-2017

Sub.:- Environment Clearance - Expansion of Hospital cum Medical CollegeCampus Project at Edappal Village, Ponnani Taluk, Malappuram District,Kerala - Submission of EIA/EMP Report - Reg.

Respected Sir,

For the purposes of obtaining Environmental Clearance for the above mentionedproject, we submitted application along with draft Terms of Reference (ToR) atMoEF&CC on 11-10-2017 under the provisions of Notification dl. 14-03-2017. The draftToR was considered and approved by EAC in its 6th meeting held on 19/20 April, 2018and the approved ToR letter was communicated to us by MoEF&CC vide letterdt. 22-06-2018.

The EIA study was conducted as per the approved Terms of Reference. Now, wehereby submit the EIA/EMP report in compliance to the ToR letter dt.22-06-2018 forobtaining Environmental Clearance for our project.

It may be kindly noted that the project has applied under the provisions of Notificationdated 14-03-2017 (a Notif ication providing a one time opportunity to the projectproponent who have not taken prior Environment Clearance before the commencementof construction / activity). An amount equivalent to Rs. 57.44 Lakhs is set apart basedon the damage assessment and its remediation plan, natural and community resourcesaugmentation plan. This amount is over and above the CER component and the EMPcomponent.

Please note that the processing fees of Rs. 2 Lakhs was submitted at SEIAA, Keralaon 16-03-2017 vide D.D. no. 525773 dt. 08-03-2017, lndian Overseas Bank. The copyof the said acknowledgment received from SEIAA, Kerala vide letter dated 12-O1-2017is attached at Annexure No. 1.

ln view of the above submissions, we humbly request you to consider our applicationand accord Environmental Clearance to our project at the earliest.

Thanking yo u,Yours res pectfu lly,For Sreevalsam E

Raja n Ac h uthan(Secretary & Au

E ncl. :- As abov

duca

Natho

ional Irt

e

6,t

SREEVALSAM

ENVIRONMENT IMPACT ASSESSMENT (EIA) REPORT &

ENVIRONMENT MANAGEMENT PLAN (EMP),

Prepared

for

M/s SREEVALSAM EDUCATIONAL TRUST Expansion of existing Hospital cum Medical College Campus Project

at

Edappal Village & Panchayat, Ponnani Taluk, Malappuram District, Kerala

Submitted

by

M/s Sreevalsam Educational Trust Reg. No. 53/2010, Regd. Office : Thekke Mdhom Road,

Thrissur, Kerala-680001.

Studies and Documentation

by

M/s Environmental Engineers & Consultants Pvt. Ltd. A1-198, Janak Puri, New Delhi – 110 058.

(NABET Accredited Consultancy Organization) Certif icate No. NABET/EIA/1720/SA 92 Dated 14-06-2019

Name of NABL Laboratory : M/s Standards Environmental & Analytical Laboratories, Kochi, Kerala NABL Acc. # : TC-5402 Monitoring Period : November & December, 2018.

Submitted To:

STATE ENVIRONMENT IMPACT ASSESSMENT AUTHORITY, KERALA

(September, 2019)

Project no. 050919-554-01 September, 2019

Declaration by experts contributing to the EIA of M/s Sreevalsam Educational Trust at Edappal Vil lage, Ponnani Taluk, Malappuram District , Kerala for proposed expansion of existing hospital cum medical college campus project.

I , hereby cer t ify that I was a part of the team in the following capacity that developed the above EIA. EIA Coordinator : P.Z. Thomas Name (ACO) : M/s Environmental Engineers & Consultants Pvt. Ltd. Signature & Date : 27-08-2019 Period of involvement : September, 2017 to September, 2019 Contact information : A1-198, Janakpuri, New Delhi-110058. Ph. no. 011-25507190 / 25622604. Branch of f ice :- C-306, Kanchanjunga Apartments, Palar ivattom P.O., Kochi, Kerala-682025. Functional Area Experts :

S.

N. Functional Areas Name of the expert Signature and Date

1. AP, WP, SHW & LU P.Z. THOMAS 27t h

Aug. , 2019

2. SE JOMON M.C. 17t h

Aug. , 2019

3. EB & SC Dr. RINOY VARGHESE

18t h

Aug. , 2019

MUKESH SUROLIYA 22

t h Aug. ,

2019

4. HG & Geo

AKHIL CHANDRAN (AFAE)

18t h

Aug. , 2019

5. AQ & NV MOHAN A. PATIL

22t h

Aug. , 2019

6. RH S.C. GUPTA 24

t h Aug. ,

2019

Declaration by the Head of the Accredited Consultant Organizat ion / Authorized person I , P.Z. THOMAS, hereby, conf irm that the above mentioned experts prepare the EIA of

M/s Sreevalsam Educational Trust. I also conf irm that the consultant organizat ion

shall be ful ly accountable for any mis- leading information mentioned in this statement.

Signature : DDDDDDDDDD. Name : P.Z. THOMAS Designation : EIA Coordinator & Managing Director Name of the EIA Consultant Organizat ion : M/s Environmental Engineers & Consultants Pvt. Ltd. NABET Certif icate No. & Issue Date : NABET/EIA/1720/SA 92 Dated 14-06-2019

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

i

TABLE OF CONTENTS

CHAPTER 1 INTRODUCTION

1.1 Purpose of the report 1-1 1.2 Identif ication of project & project proponent 1-3 1.2.1 - Identif ication of project 1-3 1.2.2 - Identif ication of the project proponent 1-3 1.3 Brief descript ion of nature, size, locat ion of the project

and its importance to the country, region 1-4

1.3.1 - Nature and size of the project 1-4 1.3.2 - Location of the project 1-5 1.3.3 - Importance of the project to the country and to the

region 1-8

1.4 Scope of the study 1-8 1.4.1 - Terms of Reference (ToR) and Scope of the study 1-8 1.4.2 - Scope of the study and compliance to "Terms of

Reference" in the EIA report 1-9

1.4.3 - The applicable regulatory framework 1-9 1.4.4 - Status of various statutory approvals / permissions 1-12 1.4.5 - Court case / Lit igat ion pending 1-14 1.4.6 - Structure of EIA report 1-15

CHAPTER 2 PROJECT DESCRIPTION

2.1 Descript ion of the project 2-1 2.1.1 - Est imated project cost 2-13 2.1.2 - Employment details 2-13 2.1.3 - Machinery details & building materials 2-14 2.2 Type of project 2-15 2.3 Need for the project 2-16 2.4 Location 2-16 2.5 Geology 2-22 2.5.1- Regional Geology 2-22 2.5.2 - Local Geology 2-23 2.6 Topography 2-23 2.7 Size or magnitude of the project 2-25 2.8 Design Considerat ion 2-28 2.8.1 Site history 2-32 2.9 Parking 2-32 2.10 Descript ion of mitigat ion measures incorporated into the

project to meet environmental standards 2-32

2.10.1 - Water supply and sewage disposal during construction phase

2-32

2.10.1.1 - Source of Water during construction phase 2-32

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

i i

2.10.1.2 - Daily Water Requirement during construction phase

2-33

2.10.1.3 - Sewage disposal during construction phase 2-33 2.10.2.1 - Source of water during operat ion phase 2-33 2.10.2.2 - Daily water requirement during operation

phase 2-33

2.10.2.3 - Sewage disposal during operation phase 2-37 2.11.1 - Storm water management (surface water

drainage) and rain water harvesting 2-42

2.11.2 - Solid Waste Management 2-43 2.11.3 - Green area development 2-47 2.11.4 - Air pollut ion control 2-51 2.11.5 - Noise pollut ion control & vibrat ion 2-52 2.11.6 - Vehicular traff ic density 2-53 2.11.6.1 - Interpretat ion 2-54 2.11.7 - Fire Fighting System 2-54 2.11.8 - Project implementat ion schedule 2-55

CHAPTER 3 DESCRIPTION OF THE ENVIRONMENT 3.1 Introduct ion / approach 3-1 3.2 Study area, period, components 3-1 3.2.1 - Study area 3-1 3.2.2 - Study period 3-1 3.2.3 - Components of study 3-2 3.2.4 - Sampling, frequency & method of baseline

environment monitoring 3-2

3.3 Meteorological parameters 3-4 3.3.1 - Temperature 3-4 3.3.2 - Rainfall 3-4 3.3.3 - Humidity 3-4 3.3.4 - Wind 3-4 3.3.4.1 - Wind rose diagram 3-5 3.3.4.2 - Inference 3-7 3.4 Air Environment 3-7 3.4.1 - Introduct ion 3-7 3.4.2 - Selection and number of sampling locat ions for

ambient air quali ty monitoring as per CPCB norms 3-7

3.4.3 - Sampling and analysis results 3-10 3.4.4 - Ambient air quality index 3-12 3.4.5 - Inference 3-12 3.5 Noise Environment 3-12 3.5.1 - Introduct ion 3-12 3.5.2 - Protocols followed for ambient noise level 3-12

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

i i i

monitoring & methodology 3.5.3 - Ambient noise level results 3-15 3.5.4 - Inference 3-15 3.6 Land Environment 3-16 3.6.1 - Introduct ion 3-16 3.6.2 - Land use / land cover 3-16 3.6.2.1 - Interpretation 3-16 3.6.3 - Soil 3-19 3.6.3.1 - Introduct ion 3-19 3.6.3.2 - Protocols for soil sampling methodology 3-19 3.6.3.3 - Soil sampling results 3-19 3.6.3.4 - Interpretation 3-20 3.7 Water Environment 3-20 3.7.1 - Introduct ion 3-20 3.7.2 - Water consumption and sources 3-20 3.7.3 - Ground water 3-21 3.7.3.1 - Ground water table identif ication 3-21 3.7.3.2 - Interpretation 3-22 3.7.3.3 - Protocols for water sampling methodology 3-22 3.7.4 - Water sampling results 3-24 3.7.5 - Interpretat ion of results 3-25 3.8 Ecological Environment 3-26 3.8.1 - Introduct ion 3-26 3.8.2 - Methodology 3-26 3.8.3 - Findings 3-27 3.8.4 - Interpretat ion of ecological assessment 3-48 3.9 Socio Economic Environment 3-48 3.9.1 - Introduct ion 3-48 3.9.2 - Approach adopted 3-49 3.9.3 - Stake holders 3-49 3.9.4 - Edappal grama panchayat 3-49 3.9.5 - Basic details of Edappal grama panchayat 3-50 3.9.6 - Edappal census town 3-50 3.9.7 - Demographics 3-51 3.9.8 - Caste wise male female population 2011 - Edappal 3-51 3.9.9 - Religion wise distribut ion of population 3-51 3.9.10 - Religion wise population 2011 - Edappal 3-52 3.9.11 - Grown of populat ion 3-52 3.9.12 - Growth of populat ion (percent) 2001 to 2011 -

Edappal 3-53

3.9.13 - Sex rat io - females per 1000 male 3-53 3.9.14 - Change in sex rat io 2001 to 2011 - Edappal 3-54 3.9.15 - Literacy 3-54

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

iv

3.9.16 - Change in l iteracy rate 2001 to 2011 - Edappal 3-55 3.9.17 - Workers prof i le 3-55 3.9.18 - Percentage of working populat ion - Edappal 3-56 3.9.19 - Demographics 3-56 3.9.20 - Interpretat ion of present socio-economic status of

the area 3-57

CHAPTER 4 ANTICIPATED ENVIRONMENTAL IMPACTS 4.1 Introduct ion 4-1 4.1.1 - Area for identif ication of Environmental aspects

and impacts 4-1

4.2 Detai ls of ant icipated environmental impacts due to the proposed project and the mit igat ion measures for minimizing and / or offsett ing adverse impacts identif ied

4-2

4.2.1 - Air Environment 4-2 4.2.2 - Noise Environment 4-5 4.2.3 - Land Environment 4-6 4.2.4 - Water Environment 4-6 4.2.5 - Biological Environment 4-8 4.2.6 - Socio-Economic environment 4-8 4.2.7 - Other environmental aspects 4-9 4.3 Identif ied environmental impacts from various aspects 4-9 4.4 Select ion criteria for evolving signif icant impacts 4-15 4.5 The marking for various criteria 4-16 4.6 Scores of all ant icipated environmental impacts after

applying the marking criteria 4-17

4.7 List of signif icant environmental impacts 4-23 4.8 Mit igation measures for the signif icant impacts identif ied 4-24

CHAPTER 5 ANALYSIS OF ALTERNATIVES (TECHNOLOGY AND SITE)

5.1 Introduct ion 5-1 5.2 Alternat ive sites 5-1 5.3 Alternat ives in technology 5-2 CHAPTER 6 ENVIRONMENT MONITORING PROGRAM

6.1 Introduct ion 6-1 6.1.1 - Performance indicators (Pls) 6-1 6.1.1.1 - Water quality monitoring 6-1 6.1.1.2 - Ambient air quality (AAQ) monitoring 6-2 6.1.1.3 - Noise level monitoring 6-2

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

v

6.1.1.4 - Success of vegetation 6-2 6.2 Data management 6-9 6.3 Report ing schedule 6-9 6.4 Emergency 6-9 CHAPTER 7 ADDITIONAL STUDIES

7.1 Introduct ion 7-1 7.2 Risk Assessment and Disaster Management Plan 7-1 7.2.1 - Need and plans 7-1 7.2.2 - Response in case of earthquake 7-2 7.2.3 - Status on natural disaster w.r.t. site and

surroundings 7-3

7.2.4 - Response of LPG leakage 7-3 7.2.5 - Response in case of f ire 7-4 7.3 Resource conservation 7-9 7.3.1 - General approach 7-9 7.3.2 - Water resources 7-9 7.3.3 - Construction materials 7-10 7.3.4 - Top soi l as a resource 7-10 7.3.5 - Energy as a resource 7-10 7.4 Traff ic impact assessment 7-11 7.5 Social impact assessment 7-13 7.5.1 - Introduct ion - Corporate Environment

Responsibi l ity 7-13

7.5.2 - Suggested sectors to perform act ivit ies under CER

7-14

7.5.3 - Approach adopted for assessment 7-15 7.5.4 - Stake holders 7-15 7.5.5 - Proposed CER act ivit ies 7-15 7.5.5.1 - Summary of CER activit ies 7-18 7.5.5.2 - Time frame (tentat ive) for execution of CER

act ivit ies 7-18

7.6 Rehabil itat ion & Resettlement (R&R) Action plan 7-18 7.7 Public hearing 7-18 CHAPTER 8 PROJECT BENEFITS 8.1 Introduct ion 8-1 8.2 Physical infrastructure 8-1 8.3 Social infrastructure 8-1 8.4 Economic benefits 8-1 8.5 Importance of the present project 8-2

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

v i

CHAPTER 9 ENVIRONMENT COST BENEFIT ANALYSIS 9.1 Introduct ion 9-1 CHAPTER 10 ENVIRONMENT MANAGEMENT PLAN 10.1 Introduct ion 10-1 10.2 Environmental Management System (EMS) 10-1 10.3 Environmental pol icy 10-1 10.4 Environment Management Cell (EMC) 10-3 10.5 Other management aspects of the Environmental Cell 10-4 10.6 Standard operat ion procedures (SOP) 10-4 10.7 Cost est imation for environment management system 10-5

CHAPTER 11 SUMMARY 1.0 Introduct ion 11-1 2.0 Project description 11-2 3.0 Descript ion of the Environment 11-4 4.0 Anticipated Environmental impacts & mitigation measures 11-7 5.0 Environmental monitoring program 11-13 6.0 Additional studies 11-13 7.0 Project benefits 11-14 8.0 Environment Management plan 11-14 9.0 Ecological damage & Remediat ion plan, Natural & Community

resources augmentat ion plan 11-15

CHAPTER 12 DISCLOSURE OF ACO CONSULTANT

12.1 The name of consultants engaged with their brief resume 12-1 12.2 Prof ile of ACO 12-2

CHAPTER 13 ECOLOGICAL DAMAGE ASSESSMENT & REMEDIATION PLAN, NATURAL & COMMUNITY RESOURCES AUGMENTATION PLAN 13.1 Introduct ion 13-1 13.2 Damage assessment & Remediat ion plan 13-3 13.3 Summary of Remediation plan - 3 years plan 13-14 13.4 Natural resources augmentation plan - 3 years plan 13-15 13.5 Community resources augmentat ion plan - 3 years plan 13-16 13.6 Summary of remediation, natural resources & community

augmentation plan 13-17

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

v i i

LIST OF FIGURES

Fig. No.

Description

Page Nos.

1.1 Key map showing the location of the project area 1-7

2.1 Conceptual plan of the project 2-12

2.2 Route map of the project area 2-17

2.3 Satell ite map within 10 km radius 2-18

2.4 Satell ite map superimposed with the project boundary 2-19

2.5 Toposheet of the study area 2-20

2.6 Vicinity map showing 10 km radius of the project site 2-21

2.7 Topographical contour map of the project site 2-24

2.8 Time series satel l ite image - January, 2008 2-28

2.9 Time series satel l ite image - December, 2009 2-29

2.10 Time series satel l ite image - December, 2012 2-29

2.11 Time series satel l ite image - Apri l, 2013 2-30

2.12 Time series satel l ite image - December, 2013 2-30

2.13 Time series satel l ite image - December, 2018 2-31

2.14 Time series satel l ite image - Current image, August, 2019

2-31

2.15 Daily water consumption balance chart 2-36

2.16 Sewage Treatment Plant (STP) diagram 2-40

2.17 Water Treatment Plant (WTP) diagram 2-42

3.1 Wind rose diagram 3-6

3.2 Ambient air quality monitoring locat ion map 3-9

3.3 Ambient noise monitoring location map 3-14

3.4 Land use map within 10 km radius of the project site 3-18

3.5 Categorizat ion of blocks of Malappuram distr ict 3-21

3.6 Water sampling locat ion map 3-24

7.1 Flow chart of Disaster Management Authority (DDMA) 7-6

7.2 Flow chart of Action plan for crisis management in the district

7-7

7.3 Flow chart of incident response team 7-7

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

v i i i

LIST OF TABLES

Table Nos.

Description Page Nos.

2.1 Project features & Environmental Sett ing 2-1

2.2 Immediate site surrounding features 2-17

2.3 Plot area break-up 2-25

2.4 Built-up area break-up 2-25

2.5 Building block details along with status of construct ion 2-26

2.6 List of tree species already planted within the campus 2-47

3.1 Environmental attributes 3-2

3.2 Frequency distr ibut ion of wind speed & wind direction 3-7

3.3 Ambient Air Quality locat ion detai ls 3-9

3.4 Ambient Air Quality analysis results 3-11

3.5 National Ambient Air Quali ty Standards 3-12

3.6 Ambient air quality index 3-12

3.7 Noise monitoring locat ion details 3-14

3.8 Noise level monitoring results 3-15

3.9 National ambient noise level standard 3-15

3.10 Land use / land cover classif icat ion system 3-16

3.11 Soil sampling locat ion details 3-19

3.12 Chemical properties of analyzed soil samples 3-19

3.13 Water consumption details for various purposes 3-20

3.14 Ground water sampling locat ion 3-23

3.15 Surface water sampling locat ion 3-24

3.16 Ground water analysis results 3-25

3.17 Surface water analysis results 3-25

3.18 List of f loral species observed in the site area (trees, tree

saplings, shrubs, herbs, cl imbers, ferns)

3-28

3.19 List of faunal species observed in the site area (mammals, 3-43

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

ix

repti les, birds, Amphibian, Odonates, Butterf l ies,

Mill ipedes and Centipedes, Ants, Spiders)

3.20 Detai ls of stake holder 3-49

4.1 Matrix of identif ied Environmental Aspects & their

ant icipated impacts from the project

4-11

4.2 Criteria for evolving signif icant impacts 4-16

4.3 Marking for various criteria 4-17

4.4 Matrix showing the scores of al l environmental impacts as per the criteria

4-18

4.5 List of Signif icant impacts identif ied 4-23

4.6 Mit igation measures for the signif icant impacts identif ied during construction phase

4-25

4.7 Mit igation measures for the signif icant impacts identif ied during operation phase

4-27

6.1 Environment Monitoring Action Plan 6-3

6.2 Environment Monitoring Plan with Budgetary Allocation 6-8

10.1 Environmental Management Cell 10-3

10.2 Cost Estimation of Environmental Management Plan during Construct ion phase

10-5

10.3 Cost Estimation of Environmental Management Plan during Operation phase

10-6

13.1 Damage Assessment & Remediat ion Plan 13-3

13.2 Summary of remediat ion plan for 3 years 13-14

13.3 Natural resources augmentation plan for 3 years 13-15

13.4 Community Resources Augmentat ion Plan for 3 years 13-16

13.5 Summary of Remediation, Natural Resource & Community Augmentat ion Plan

13-17

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

x

LIST OF PLATES

Plate

No. Description

Page

Nos.

2.1 Site Photographs showing current status of the site 2-11

2.2 Photographs of existing STP 2-41

2.3 Photographs of existing Bio-gas generat ion plant 2-45

2.4 Photographs of the plant species / tree species already

planted within the campus

2-49

2.5 Photographs of the road side plantat ion within the

campus

2-50

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

x i

LIST OF ANNEXURES

Annexure

No.

Description

1.1 Notif icat ion dated 14/03/2017 (Notif ication No. S.O. 804 (E)

1.2 A f low chart showing the procedure as per Notif icat ion dated

14/03/2017

1.3 Copy of the minutes of meeting of 06 t h meeting of EAC

1.4 Copy of ToR approval letter issued vide Letter No. 23-89/2018-IA.III

dated 22/06/2018.

1.5 Copy of Possession cert if icate

1.6A

&

1.6B

Copy of Land Use Certif icate and Land Conversion Certif icate

issued by Tahsildar, Ponnani on 31-03-2014 stat ing that the land is

"do not fall under Agricultural use and this land can be used for

Education purpose to establ ish Education Inst itutions".

1.7 Copy of the resolution passed by the Trust in favour of Mr. Rajan

Achuthan Nair

1.8 Detai ls regarding Scope of the study and compliance to the

approved "Terms of Reference" (ToR) in the EIA report

1.9 Copy of Init ial Building Permit granted by Edappal Grama

Panchayat for the Hospital project with built -up area 5,783.7 sq.m.

1.10 Copy of Renewal of Building Permit granted by Edappal Grama

Panchayat for the Hospital project with built -up area 32,160 sq.m.

1.11 Copy of Renewal of Building Permit granted by Edappal Grama

Panchayat for the project with addit ional built -up area of 42,636.4

sq.m.

1.12 Copy of Integrated “Consent to Establish” f rom Kerala State

Pollut ion Control Board dt. 06.07.2012 val idity upto 30.11.2014

1.13 Copy of Init ial “Consent to Operate” from Kerala State Pollut ion

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

x i i

Control Board dt. 19.06.2015 Validity upto 30.09.2016

1.14 Copy of Renewal of “Consent to Operate” from Kerala State

Pollut ion Control Board dt. 27/11/2017 Validity upto 30/09/2019

1.15 Copy of Init ial NOC from Fire & Rescue Services for Hospital

Building dt. 21.01.2012

1.16 Copy of NOC from Fire & Rescue Services for Hospital Building

6(B+G+4) storeyed 22.30 m. height dt. 11.03.2013

1.17 Copy of NOC from Fire & Rescue Services for 9 storeyed

Residential Building (G+8) 28.80 M. height dt. 25.10.2013

1.18 Copy of Approval of Buildings layout and land use from Town

Planner, Off ice of the Chief Town Planer, Thiruvananthapuram vide

Order NO. C1/9579/13/DDS dt. 18.02.2014

1.19 Copy of Approval from Kerala State Electr icity Board for power

supply dt. 06.11.2013

2.1 Copy of the MoU between IMAGE & the project proponent

3.1 Copy of analysis reports of all ambient air quality stat ions

3.2 Copy of analysis report of al l ambient noise level stations

3.3 Copy of analysis report of soil sampling station

3.4 Copy of soi l investigat ion report

3.5 Copy of the analysis report of water sampling station (Ground water)

(bore well)

3.6 Copy of the analysis report of water sampling stat ion (Surface water

- Ayarichira)

12.1 Copy of the accreditat ion certif icate of the ACO from NABET / QCI

12.2 Copy of the accreditation certif icate along with the scope of work of

the laboratory

CHAPTER – 1

INTRODUCTION

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 1 In t roduct i on Page 1 - 1

1.0 INTRODUCTION

1.1 Purpose of the Report

M/s Sreevalsam Educational Trust proposed an expansion of exist ing

Hospital cum Medical College project at Survey Nos. 157/2, 159/3, 158/1,

157/0, 158/1, 159/3, 158/2, 158/5, 159/1, 159/2, 157, 159/3, 164/3, 164/7,

164/4, 163/3, 158/7, 158/3, 158/4, 166/2, 166/1, 156/3, 164/1, 156/3,

164/1, 164/2, 156/4, Edappal Vil lage, Ponnani Taluk, Malappuram District,

Kerala. The plot area of the Hospital cum Medical College Project is

9.4534 ha (94,534.56 sq. m.) and the total built -up area is 1,38,937.50

sq. m. (exist ing 53,889.72 sq.m. + proposed 85,047.78 sq.m.).

Building construction of 53,889.72 sq.m. of the hospital cum medical

college is already completed. The teaching hospital component is for a

built -up area of 32,160 sq.m. and the educational component is with

built -up area of 21,729.72 sq.m. It is proposed to construct addit ional

built -up area of 85,047.78 sq.m and the total cumulative built -up area wil l

be 1,38,937.5 sq.m.

The land was purchased and registered between the year of 2010 to 2011

and started the construct ion work of Teaching Hospital in 2011 as per the

Building permit vide permit no. 224/11-12 dated 03-11-2011 obtained from

Edappal Grama Panchayat for a built-up area of 5,783.70 sq.m.

Subsequently, the expansion of the building was carried out with the

renewal of building permit vide permit no. B2-224/11-12 dated 27-06-2012

valid upto 26-06-2015 issued by the Panchayat for a cumulat ive built -up

area of 32,160 sq.m. in 2012. This work was carried out without pr ior

Environmental Clearance and the construction of this building is

completed. Further, renewal of building permit vide permit

no. A5-365/14-14 dated 24-03-2014 was issued for Academic block,

Hostels with a cumulative buil t-up area of 43,636 sq.m. and construct ion

of 21,729.72 sq.m. is completed. Educat ional insti tut ions are exempted

from the purview of EIA Notif icat ion vide Notif ication dt. 22-12-2014. For

the f irst t ime, the requirement of prior Environmental Clearance was

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 1 In t roduct i on Page 1 - 2

inserted in Kerala Municipal ity Building Rules (KMBR) by an amendment

of KMBR made in 05/02/2013.

Therefore, the project proponent was not aware of the requirement of

prior Environmental Clearance and constructed the Teaching Hospital

building without obtaining prior Environmental Clearance and hence the

violated the provisions of Environment Protect ion Act, 1986.

Ministry of Environment, Forests & Climate Change (MoEF & CC) issued a

Notif icat ion dated 14/03/2017 (Notif icat ion No. S.O. 804 (E)) and gave

one time opportunity to the projects who have commenced their activity

without taking prior Environmental Clearance violated the EIA Notif ication,

2006. The copy of the Notif ication is attached as Annexure No. 1.1. A

f low chart showing the procedure as per the said Notif icat ion is provided

at Annexure No. 1.2.

An application with draft Terms of Reference (ToR) for EIA Study and for

obtaining Environmental Clearance under the provision of MoEF&CC

Notif icat ion dt. 14/03/2017 was submitted at MoEF&CC on 23/06/2017

vide File No. 23-89/2018-IA-III (V).

Thereafter, the proposal was considered in the 06 t h meeting of Expert

Appraisal Committee (EAC) at MoEF&CC on 19 t h - 20 t h , Apri l, 2018 vide

agenda item No. 6.3.7 for grant of Terms of Reference (ToR) for

undertaking Environment Impact Assessment (EIA) studies and

preparation of Environment Management (EMP).

The EAC recommended the project for grant of “ToR” for undertaking

Environment Impact Assessment (EIA) study and preparation of

Environment Management Plan (EMP). The copy of the minutes of

meeting of 06 t h meeting of EAC is attached as Annexure No. 1.3. The

Ministry accepted the recommendations of EAC and the “ToR” was

approved and issued vide Letter No. 23-89/2018-IA.I II dated 22/06/2018.

The copy of the “ToR” Letter is attached as Annexure No. 1.4.

With a view to assess the environmental impacts due to the construct ion

act iv it ies, to suggest the mitigat ion measures, to assess the ecological

damage due to the i l legal construction, to prepare remediation plan and

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 1 In t roduct i on Page 1 - 3

the natural and community resource augmentat ion plan as per the

approved ToR granted, the project proponent has engaged the services

of M/s Environmental Engineers & Consultants Pvt. Ltd., New Delhi (an

MoEF & CC accredited Consultancy Organizat ion under QCI / NABET

Scheme).

1.2 Identification of project & project proponent

1.2.1 Identification of project

In order to faci li tate the medical and medical education requirement in the

project vicinity and in Ponnani Taluk of Malappuram District, Kerala M/s

Sreevalsam Educational Trust constructed a hospital cum medical col lege

project at Edappal Vil lage, Ponnani Taluk, Malappuram Distr ict, Kerala in

Plot area of 9.4534 ha and constructed of buildings with built -up area

53,889.72 sq. m. and due to increase in demand the project proponent is

going for expansion of the exist ing campus with addit ional built -up area of

85,047.78 sq.m. After the proposed expansion the cumulat ive built -up

area of the hospital cum medical college wil l be 1,38,937.50 sq. m.

(existing bui lt-up area 53,889.72 sq. m. + 85,047.78 sq.m.)

The land for the project is under the possession of M/s Sreevalsam

Education Trust and the possession certif icate issued by the Vil lage

Off ice, Edappal is attached at Annexure No. 1.5.

Also, the Land Use Certi f icate and Land Conversion Certi f icate issued by

Tahsildar, Ponnani on 31-03-2014 stat ing that the land is "do not fal l

under Agricultural use and this land can be used for Educat ion purpose to

establish Education Institut ions". The copy of the said Land Conversion

Cert if icate is attached at Annexure No. 1.6A & 1.6B.

1.2.2 Identification of project proponent

M/s Sreevalsam Educational Trust establishing a public charitable trust

for establishing a centre for professional medical educat ion by promoting

medical, para-medical, nursing and other medical services along with a

super specialty hospital for health promotion. As per the trust deed made

in January, 2010, the fol lowing are the members of the trust :-

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 1 In t roduct i on Page 1 - 4

SN Name & Designation Address of member

1. Dr. V.P. Gopinathan,

Chairman

Thrissur Corporation, House No. 23/338,

Anchery Kizhakke Pisharam, Ollur Village,

Anchery Desom, P.O. Anchery, Thrissur

Taluk & District, Kerala-680006.

2. K.R. Raju, Vice

Chairman

Thrissur Corporation, House No. 36/361/1,

"Omkaram", Kottapuram Road, Thrissur

Vil lage, Punkunna Desom, P.O Punkunnam,

Thrissur Taluk & District, Kerala-680002.

3. K. Vijayan, Secretary Thrissur Corporation, House No. 5/50/3,

Kunnathu Mana, Ollukkara Village,

Kalathode Desom, P.O. Ollukkara, Thrissur

Taluk & District, Kerala-680655.

The contact detai ls of the applicant is given below :-

Name of Authorized Signatory : Mr. Rajan Achuthan Nair

(Secretary)

Registered Address &

Correspondence Address

: M/s Sreevalsam Educational Trust,

Thekke Madhom Road,

Thrissur, Kerala-680001

Contact No. : 0487-2430114 / 09539641006

E-mail : [email protected]

The copy of the resolution passed by the Trust in favour of Mr. Rajan

Achuthan Nair is attached at Annexure No. 1.7.

1.3 Brief description of nature, size, location of the project and its importance to the country, region. 1.3.1 Nature and size of the project

M/s Sreevalsam Educational Trust is involving in development of hospital,

medical colleges and inst itutional projects in Kerala. The educat ional trust

is having good experience in medical and insti tut ional projects especially

in Kerala.

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 1 In t roduct i on Page 1 - 5

M/s Sreevalsam Educational Trust constructed a hospital cum medical

college project at Edappal Vil lage, Ponnani Taluk, Malappuram District,

Kerala in plot area of 9.4534 ha and total built -up area of the hospital cum

medical college wil l be 1,38,937.50 sq. m. (exist ing bui lt-up area

53,889.72 sq. m. + 85,047.78 sq.m.). The estimated cost of the project

is about Rs. 180 Crores. The project is expected to employ about 1,000

direct job opportunit ies which includes medical & non-medical staff .

1.3.2 Location of the project

The project site is within the Panchayat l imits of Edappal Grama

Panchayat. The nearest town is Edappal town which is about 2 km away

(N) from the site and the nearest city is Kozhikode city and is located

about 60 km (NW ).

The access road to the project site is from 10 m wide & 8 m wide road in

the northern side which is connected to Naduvattom-Karinkal lthani Road

which is located at 0.5 km towards north direction from the site.

The nearest National Highway is N.H. 17 (Edappally-Panvel Highway) at

about 2 km towards North direction (at Edappal Town). The nearest

rai lway stat ion (Kutt ipuram Railway Station) is about 10 km (NE) and

Calicut International Airport , Karipur is about 40 Km (NW) away from the

project s ite.

Particulars Details

Geographical

Locat ion

Lat itude (N) 10046‘00.86“ to 100 45’48.56“

Longitude (E) 76000’36.45” to 760 00’23.53” Local name of the

project area

Edappal

Project Site

Toposheet No.

58B/4

(old toposheet no.)

Name of Vi llage Edappal

Name of

Panchayats

Edappal

Nearest Town Edappal town - about 2 km away (N)

Name of Taluk Ponnani

Name of District Malappuram

Name of State Kerala

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 1 In t roduct i on Page 1 - 6

The key map showing the locat ion of the project area is provided at

Figure 1.1.

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 1 In t roduct i on Page 1 - 7

Figure 1.1 - Key Map

(Source :- Google map) (Vintage 2019)

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 1 In t roduct i on Page 1 - 8

1.3.3 Importance of the project to the country and to the region.

M/s Sreevalsam Educational Trust has developed the hospital cum

medical col lege with a vision to “Provide quality healthcare with

exceptional service and compassion at affordable cost". Due to the rapid

development in Kerala there are lots of residential, commercial and off ice

building construct ion projects are introduced and thereby the f loat ing of

populat ion from their native place to their working place / urban area is

going on. Due to the high rate of population shif t ing there is an increase

in burden on the infrastructure and medical faci l it ies of an area. To

accommodate the same the medical hospital wi th high patient

management capacity with quality services is must in every districts of the

State. In order to overcome this problem, M/s Sreevalsam Educational

Trust decide the expansion of their exist ing hospital cum medical col lege

project in Edappal Vil lage, Ponnani Taluk, Malappuram Distr ict, Kerala.

There is an urgent requirement for the construction of hospital cum

medical col lege with associated activit ies in the area as per the faci lit ies

to be provided to the nearby people to facil itate on easy and quick

medical facil it ies and thereby the hospital/healthcare services in a very

easy way as per the needs.

The medical healthcare of hospital and associated act ivit ies bring about

gains in Gross Domestic Product (GDP). The project will create direct

employment opportunit ies for about 1,000 persons and indirect

employment opportuni ties for about 3,000 persons.

Direct and indirect taxes wil l also be paid by the project proponent to the

Local Self Government, State Government and to the Central Government.

These are the sources of revenue for the Government. The public revenue

wi ll be uti l ized by Government for development of various infrastructural

faci l i t ies for the public in the f ield of health, educat ion and social welfare

etc.

1.4 Scope of the study.

1.4.1 Terms of Reference (ToR) and Scope of the study

The project proposal underwent the scoping exercise through the Expert

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 1 In t roduct i on Page 1 - 9

Appraisal Committee at MoEF & CC. the scope of study was approved

through “ToR” and the same was communicated to the project proponent

vide letter dated 22-06-2018.

This EIA report has been prepared based on the above approved ToR.

1.4.2 Scope of the study and compliance to "Terms of Reference" in the EIA report

The detai ls regarding Scope of the study and compliance to the approved

"Terms of Reference" (ToR) in the EIA report is provided at Annexure

No. 1.8.

1.4.3 The applicable regulatory frame work

The following Acts, Rules, Govt. Orders / Polic ies are to be fol lowed by

the project proponent in the operation of all buildings :-

���� The Environment Protection Act, 1986

An Act to provide for the protection and improvement of environment

and for matters connected there with. Introduction of this statute was

due to a decision taken at United Nation Conference on the Human

Environment held at Stockholm in June, 1972. This is an umbrella Act

and project proponent is required to comply with the provisions of the

Act. A few of these are summarized below :-

���� The EIA Notification, 2006 & the subsequent amendments.

EIA Notif ication, 2006 was issued under Sect ion 3 of the Environment

Protect ion Act, in supersession of EIA Notif ication, 1994. Through this

Notif icat ion, the Central Governments directs that before the

commencement of any activity or modernization of exist ing activity

l isted in the "Schedule" to the Notif icat ion, prior Environment

Clearance is mandatory. Prior Environment Clearance is required for

expansion, modernizat ion, change in project area, product mix etc.

���� Manual on norms and standards for environment clearance of large

construction projects issued by MoEF, mentions the applicable

standards and norms to ensure sustainable construction activ ity.

���� The Water Pollution (Prevention & Control) Act, 1974

An Act to provide the prevention and control of water pollut ion and the

maintaining or restoring of wholesomeness of water, for the

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 1 In t roduct i on Page 1 - 10

establishment, with a view to carrying out the purposes of aforesaid, of

Boards for the prevention and control of water pollution, for conferring

on and assigning to such Boards powers and functions relating thereto

and for matters connected therewith. Any activity before its

establishment needs to take Consent to Establish and Consent to

Operate from the concerned Pollution Control Board.

���� The Air Pollution (Prevention & Control) Act, 1981

An Act to provide for the prevention, control and abatement of air

pol lut ion for the establishment, with a view to carrying out the aforesaid

purposes, of Boards, for conferring on and assigning to such Boards

powers and funct ions relat ing thereto and for matters connected

therewith. Any act ivity before its establishment needs to take Consent

to Establish and Consent to Operate from the concerned Pollut ion

Control Board.

���� The Forest (Conservation) Act, 1988

An Act to provide for the conservation of forests and for matters

connected therewith or ancillary or incidental thereto. Forest Clearance

is required from MoEF&CC, if Forest land is found in the project s ite.

���� The Wildlife (Protection) Act, 1972

An Act to provide for the protection of W ild animals, birds and

plants and for matters connected therewith or ancil lary or incidental

thereto. W ildl ife Conservat ion Plan is to be prepared, approved by the

Wildl ife W arden and implemented, if Wildlife is affected by the proposed

project.

���� The Noise Pollution (Regulation and Control) Rules, 2000.

This Rule is issued under Sect ion 3 of Environment Protection Act.

Through this Rule, four categories areas / zone as per the Schedule is

provided in respect of "Ambient Air Quality Standards in respect of

Noise" if sensit ive receptors in the project area are affected by the noise

created by the project, necessary mitigat ive measures are to be

proposed in EIA report.

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 1 In t roduct i on Page 1 - 11

���� The National Green Tribunal Act, 2010

An Act to provide for the establishment of a National Green Tribunal for

the effective and expedit ious disposal of cases relat ing to

environmental protect ion and conservat ion of forests and other natural

resources including enforcement of any legal r ight relat ing to

environment and giving rel ief and compensation for damage to persons

and property and for matters connected therewith or incidental thereto.

���� The Kerala Promotion of Tree Growth in Non-Forest Areas

(Amendment) Act, 2007.

An Act expedient to amend the Kerala Promotion of Tree Growth in Non-

Forest Areas Act, 2005. As per the said Act, no permission is necessary

for cutt ing and removal of trees provided in the Schedule.

���� The Hazardous and Other Wastes (Management and Transboundary

Movement) Rules, 2016.

Hazardous W aste (Management, Handl ing & Transboundary) Rules,

2016 prescribing measures and procedures for storage, transport

treatment and disposal of hazardous waste and the present project

act ivity generates hazardous waste which requires obtain authorization.

���� The Solid Waste Management Rules, 2016 - Details the procedures for

generators and processors of sol id waste. The present act iv ity has to

implement the measures mentioned in the above Rule .

���� The Bio-medical Waste Management Rules, 2016 - Detai ls the

procedures for generators and processors of bio-medical waste. The

present activity has to implement the measures mentioned in the above

Rule.

���� The E-Waste Management Rules, 2016 - Details the procedures for

generators and processors of e-waste. The present activity has to

implement the measures mentioned in the above Rule.

���� The Construction & Demolition Waste Management Rules, 2016 -

Mandates safer disposal of construction & demolition waste and the

responsibi l ity of local bodies in this regard the present act ivity has to

implement the measures mentioned in the above Rule.

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 1 In t roduct i on Page 1 - 12

���� Plastic Waste Management Rules, 2016 - Detai ls the procedures for

generators and processors of plast ic waste. The present activ ity has to

implement the measures mentioned in the above Rule.

���� National Building Code (NBC) of India - Mentions the standards and

norms for construct ion materials and construct ion pract ices.

���� The Indian Electricity Rules, 1956 - Mandates the user to obtained

approval for instal lation of transformers, generator, cabling, electr ical

sub-stat ion etc.

���� Bureau of Energy Efficiency - Norms to provide minimum requirements

for the energy eff icient design and construct ion of buildings.

���� Norms issued by Fire & Rescue Department, Govt. of Kerala to take

approvals for al l commercial buildings and to follow the f ire f ighting

capabil ity guideline within those commercial buildings before the

commercial building is put to use.

���� Kerala Municipality Building Rules, 2009 / 2012 and its subsequent

amendments mandate obtaining development permit for all construction

projects.

1.4.4 Status of various statutory approvals / permissions

The project has obtained the fol lowing mandatory approvals / permissions

from various statutory agencies. The details are given below :-

S.N. Activity Period

1. Land Purchased (Private Owned Land )

Date of Registrat ion 18-08-2010,

16-08-2010, 21-08-2010, 31-08-

2010, 20-12-2010, 21-05-2010,

20-09-2010, 23-04-2011,

24-09-2011

2.

In it ial Bui lding Perm it granted by

Edappal Gram a Panchayat for the

Hospita l project with bui l t-up area

5,783.7 sq.m . (Annexure No. 1.9)

No. 224/11-12

dt. 03-11-2011

3. Renewal of Bui lding Perm it granted by

Edappal Gram a Panchayat for the

No. B2-224/11-12

dt.27-06-2012

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 1 In t roduct i on Page 1 - 13

Hospita l project with bui l t-up area

32,160 sq.m . (Annexure No. 1.10)

Validity upto 26-06-2015

4.

Renewal of the Build ing Perm it granted

by Edappal Gram a Panchayat for the

project with addit ional bui l t-up area of

42,636.4 sq.m . (Annexure No. 1.11)

No. A5-365/14-14

dt.24-03-2014

Validity upto 23-03-2017

5.

Integrated “Consent to Establ ish” f rom

Kerala State Pol lution Control Board

(Annexure No. 1.12)

No.

PCB/HQ/MLPM//IC/6164/2012

dt. 06.07.2012 valid i ty upto

30.11.2014

6.

In it ial “Consent to Operate” from

Kerala State Pol lution Control Board

(Annexure No. 1.13)

No. PCB/HO/MLPM/IC/6164/2012

dt. 19.06.2015

Val idity upto 30.09.2016

7.

Renewal of “Consent to Operate” f rom

Kerala State Pol lution Control Board.

(Annexure No. 1.14)

No. PCB/HO/MLPM/IC/6:64/2012

dt. 27/11/2017

Val idity upto 30/09/2019

9

In i t ial NOC from Fire & Rescue

Services for Hospita l Bui ld ing

(Annexure No. 1.15)

No. G2-12372/2011

dt. 21.01.2012

10

NOC from Fire & Rescue Services for

Hospita l Bui ld ing 6(B+G+4) storeyed

22.30 M. height (Annexure No. 1.16)

No. G1-12977/12

dt. 11.03.2013

11

NOC from Fire & Rescue Services for 9

storeyed Residential Bui lding (G+8)

28.80 M. height (Annexure No. 1.17)

No. G1-12587/2013

dt. 25.10.2013

12

Approval of Bui ld ings layout and land

use f rom Town Planner, Of f ice of the

Chief Town Planer,

Thiruvananthapuram. (Annexure No.

1.18)

Order NO. C1/9579/13/DDS

dt. 18.02.2014

13

Approval f rom Kerala State Electr ic ity

Board for power supply.

(Annexure No. 1.19)

No.

DB.17/HT.SC/Sreevalsam /2013-

2014/3108

dt. 06.11.2013

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 1 In t roduct i on Page 1 - 14

1.4.5 Court Case / Litigation pending

There is no court case / l it igation pending against the land or the project

proponent with respect to the project.

1.4.6 Structure of EIA Report

The generic structure of Environmental Impact Assessment (EIA) study for

the project is as fol lows:

Chapter 1 : Introduct ion

Chapter 2 : Project Descript ion Chapter 3 : Descript ion of the Environment Chapter 4 : Ant ic ipated Environmental Impacts & Mitigation Measures Chapter 5 : Analysis of Alternatives (Technology & Site) Chapter 6 : Environmental Monitor ing Program. Chapter 7 : Additional Studies. Chapter 8 : Project Benefits Chapter 9 : Environmental Cost Benefit Analysis. Chapter 10 : Environmental Management Plan Chapter 11 : Summary & Conclusion. Chapter 12 : Disclosure of Consultant Chapter 13 : Ecological damage assessment and Remediation plan,

Natural and community resources augmentation plan.

*****************************************************************************

CHAPTER – 2

PROJECT DESCRIPTION

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 2 Pro ject Descr ip t ion Page 2 - 1

2.0 PROJECT DESCRIPTION

2.1 Description of the project

In order to faci li tate the medical and medical education requirement in the

project vicinity and in Ponnani Taluk of Malappuram District, Kerala M/s

Sreevalsam Educational Trust constructed a hospital cum medical col lege

project at Edappal Vil lage, Ponnani Taluk, Malappuram Distr ict, Kerala in

Plot area of 9.4534 ha and constructed of buildings with built -up area

53,889.72 sq. m. and due to increase in demand the project proponent is

going for expansion of the exist ing campus with addit ional built -up area of

85,047.78 sq.m. After the proposed expansion the cumulat ive built -up

area of the hospital cum medical col lege wi ll be 1,38,937.50 sq.m.

(existing bui lt-up area 53,889.72 sq. m. + 85,047.78 sq.m.) with number of

hospital beds of 1,170 beds.

The detai ls regarding the project features and environmental sett ings are

provided at Table 2.1.

Table 2.1 – Project features and Environmental Settings

Particulars Details

Total Plot Area 9.4534 ha. (94,534.56 sq. m)

Total Built -up Area 1,38,937.50 sq. m.

(Exist ing 53,889.72 sq.m +

proposed 85,047.78 sq.m)

Object ive of the project Expansion of existing Hospital cum Medical

College Project with supporting addit ional

infrastructure faci li t ies.

Project cost Rs. 180 Crores

Total Number of beds 1,170 beds

(Exist ing 570 beds + Proposed 600 Beds)

No. of Students in the medical

col lege 750 Students

Max. height 30 m

Power requirement 2,250 kVA

Source of power & back-up KSEB & D. G. Sets (standby arrangement)

D.G. sets Capacity Exist ing - 500 kVA x 1 no. + 625 kVA x 1 no.

Proposed - 500 kVA x 1 no. + 625 kVA x 1 no.

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 2 Pro ject Descr ip t ion Page 2 - 2

Use of Solar energy Proposed 200 KW solar l ighting and

5,000 Ltrs solar water heaters

Employees in the facil ity

About 1000 Direct Jobs

(Doctors, nurses, medical staff , security,

Group- D housekeeping staff etc.)

Parking Provided 1,184 Cars + 1,409 Two Wheelers

Daily maximum population About 11,000 Persons

(Patients + Visitors + Hospital Staff )

Daily Water consumption 1,328 KL/day (Fresh water 677 KL + Recycled

water reused 651 KL)

Sources of Water Ground water, Stored rain water & Recycled

water

Domestic sewage generation &

its disposal 696 KL/day & treated through STP & recycled

Eff luent generation from

Laboratory & Laundry & its

disposal

27 KL/day & treated through ETP & recycled

Rain water storage tank

capacity provided About 5,000 KL storage capacity

Solid Waste Generation 2,093 kg/day

Solid Waste Disposal Facil ity

Bio-gas generation plant for biodegradable

waste & non-biodegradable waste sent to the

vendors.

Bio-medical Waste Generation

& its disposal

About 819 kg/day segregated at source & sent

to the authorized agency M/s IMAGE

Nearest town Edappal town - about 2 km away (N)

Nearest City Kozhikode city - about 60 km (NW)

Distr ict Headquarter Civi l Station, Malappuram - about 32 km (NE)

Access Road to the project

site 10 m & 8 m in the northern direction of the site.

Nearest State Highway SH-69 (Thrissur-Kuttippuram Rd.) at

(Kaladithara) about 0.7 km (E)

Nearest National Highway NH-17 (Edappally-Panvel Highway) at (at

Edappal Town) about 2 km (N)

Nearest Fire station Ponnani Fire Stat ion - about 9 km, W

Nearest Railway stat ion Kuttipuram Railway Stat ion - about 10 km (NE)

Nearest Airport Calicut Intl . Airport , Karipur - about 42 km (NW)

Nearest water bodies • Ponnani Lake - about 1 km, (NW)

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 2 Pro ject Descr ip t ion Page 2 - 3

• Drain / thodu - about 0.5 km (S)

• Beeyam Kayal - about 5 km (NW)

• Naranipuzha river - about 5.5 km (SW)

• Kolanchiri Padam - about 4 km (SW)

• Bharathapuzha - about 7 km (NW)

• Manoor Kayal - about 3 km (N)

• Lakshadweep Sea - about 9 km (SW)

• Kunthi River - about 13 km (NE)

• Valiyaparappur Thamara Kayal (Lotus lake) -

about 12 km (NW)

• Pallat kayal - about 13 km (NW)

Ecological sensit ive zones

(National Park / Wild l i fe

sanctuary / Protected areas)

None within the study area

Forest area None within the study area

Interstate boundary None within the study area

Critical ly pol luted area as

identif ied by CPCB None within the study area

Archeological Features None within the study area

Defense instal lat ions None within the study area

Climate zone Warm-Humid Zone

Seismic zone Zone-III

*Study area is 10 km radius from the project s ite. AREAS OCCUPIED BY SENSITIVE MAN-MADE LAND USES* 1. Educational Institutions

SN Name Approx.

distance & direction

1 AMLP School, Pokkarathara 800m, NW

2 GUPS, Kololamba 1.4km, SW

3 Ansar English School Kololamba 1.7km, SW

4 AMLP School Ayilakkad 2 km, NW

5 Darul Hidaya Orphanage Higher Secondary School, Edappal

1.3 km, NW

6 MH English School, Edappal 1.7km, NW

7 Janatha LP School, Alamcode 2.5km, SE

8 Irshad English School, Alamcode 2.5km, SE

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 2 Pro ject Descr ip t ion Page 2 - 4

9 Sree Narayana Central School, Changaramkulam 3.4km, SE

10 Darussalam Engl ish School, Changaramkulam 4.2km, SE

11 MVMR Higher Secondary School, Valayamkulam 5.6km, SE

12 Assabah Arts and Science Collage, Kokkur 6.1km, SE

13 Govt. Technical High School, Kokkur 6.3km, SE

14 Royal Dental College, Chal issery 7.3km, SE

15 GHSS, Kokkur 6.8km, SE

16 AMLP School, Othaloor South 6.85km, SE

17 PCNG Higher Secondary School, Mookkuthala 3.6km, SE

18 GLPS, Mookkuthala 3.6km, SE

19 LP School, Veliancode 5.6km, SW

20 Azar English medium school, Maranchery 4.8km, SW

21 GHSS , Maranchery 4.8km, SW

22 Crescent English School, Maranchery 5.3km, SW

23 Panampad School, Maranchery 4.5km, SW

24 P.N.U.P. School, Ayinichira 4.3km, NW

25 Shaikh Saeed Islamic & Arts College, Ayilakkad 2.3km, NW

26 Kamb& M Internat ional School, Ayilakkad 2.4km, NW

27 Blossom Public School, Polpakkara 4.8km, NW

28 Government Lower Primary School,Perumparamba 4.2km, NW

29 Govt. LP School, Edappal 2.8km, NW

30 GHSS Edappal 2.4km, NW

31 DarulHidaya Higher Secondary School, Edappal 1.7km, NE

32 AUPS, Verur 3.2km, N

33 VidhyaPeedam UP School, Kandanakam 5.2km, NE

34 Distr ict Insti tute of Educat ion and Training, Anakkara 6.4km, NE

35 GHSS, Anakkara 6.2km, NE

36 GHSS, Kumaranellur 5.3KM, NE

37 Govt. School, Vattamkulam 2.9km, NE

38 Technical Higher Secondary School, Vattamkulam 2km, NE

39 IHRD College of Applied Science, Vattamkulam 2km, E

40 Al-Falah AMM English School, Alamcode 2.2km, SE

41 KVUP School, Alamcode 3.2km, SE

42 Samskruthi School Kakkidippuram 3.45km, SE

43 Bharathiya Vidya Bhavan, Manoor 6.35km, SE

44 M E S School of Architecture, Thrikkannapuram 7km, NE

45 MES College of Engineering, Thrikkannapuram 7.3km, NE

46 GUPS, Tavanur 8.9km, NE

47 GUPS Vallanchery 9.6km, N

48 GHSS, Kutt ippuram 9.5km, NE

49 GVHSS, Kutt ippuram 9.4km, NE

50 Technical High School, Kuttippuram 9.4km, NE

51 NIA UP School, Kuttippuram 10.5km, NE

52 KMCT Polytechnic College, Kuttippuram 12.3km, NE

53 KMCT Law College Kutt ippuram 12.6km, NE

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 2 Pro ject Descr ip t ion Page 2 - 5

54 GHS, Kudal lur 11.1km, NE

55 Government Arts and Science College, Thrithala 12.9km, NE

56 Dr. KBMM HSS, Thrithala 12.75km, NE

57 Engl ish Medium School, Thrithala 14.5km, NE

58 Aspire College, Thrithala 14.6km, NE

59 GVHSS, Vattenad 11.9km, SE

60 GHSS, Chal issery 8.6km, SE

61 GHSS, Kadavallur 8.8km, SE

62 Ansar Women's Col lege, Perumpilavu 11.3km, SE

63 Ansar Training College, Perumpilavu 11.6km, SE

64 Ansar English Medium, Perumpilavu 11.6km, SE

65 Mar Osthatheos College, Perumpilavu 12.1km, SE

66 TM VHSS ,Perumpi lavu 12.1km, SE

67 Sree Vivekananda College, Kunnamkulam 12.4km, SE

68 St. Mary’s college, Akkikkavu 12.4km, SE

69 P.S.M. Col lege of Dental Science & Research, Akkikkavu

12.6km, SE

70 MKM UP School, Porkulam 12.5km, SE

71 GVHSS, Pazhanji 9.69km, SE

72 M D College, Pazhanji 10.7km, SE

73 Thiruvalayannur Higher Secondary School, Vadakekkad 12.3km, SW

74 GHSS, Kadikkad 10.4km, SW

75 Thaqva Afzal Ullama Arabic College, Andathode 10.4km, SW

76 KMM English School, Perumbadappu 7.2km, SW

77 GHS, Palapetty 8.8km, SW

78 AMLPS, Puthiyiruthi 8.2km, SW

79 MI Arabic College, Puthuponnani 8.5km, SW

80 MI Girls Higher Secondary School, Puthuponnani 8.6km, SW

81 MES Higher Secondary School, Ponnani 8.9km, SW

82 MES College Ponnani 8.8km, SW

83 MIHSS Ponnani 8.8km, NW

84 AV Higher Secondary School Ponnani 7.5km, NW

85 ALP School, Ponnani 7.5km, NW

86 GHSS, Thrikkavu 8.4km, NW

87 Makhdoomiyya English School Ponnani 9.3km, NW

88 TIUP School, Ponnani 9.5km, NW

89 Kelappaji College of Agricultural Engineering and Technology, Tavanur

10km, NW

90 Government Upper Primary School, Purathur 10.3km, NW

91 UP School, Padinjarekara 11.7km, NW

92 K H M Higher Secondary School, Alathiyoor 13.3km, NW

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 2 Pro ject Descr ip t ion Page 2 - 6

2. Hospitals

SN Name Approx.

distance & direction

1 Sudinaprabha Inst itute of l i festyle Diseases, Vattamkulam

550m, N

2 Prakrithe Ayurveda Hospital, Edappal 1.4km, N

3 Sukapuram Hospital, Edappal 1.5km, NE

4 Edappal Hospitals Pvt. Ltd., Edappal 1.9km, NE

5 Mother And Child Hospital, Changaramkulam 3.9km, SE

6 Sunrise Hospital, Changaramkulam 4.4km, SE

7 Alankode Govt. PHSC, Changaramkulam 4.2km, SE

8 PHC Maranchery 6.2km, SW

9 Karuna Pain and Pall iative Care, Maranchery 5.4km, SW

10 Govt. Hospital, Maranchery 5.1km, SW

11 Veterinary dispensary, Kanhiramukku 4.9km, NW

12 Govt. Hospital, Edappal 2.1km, NW

13 Family Health center, Vattamkulam 3.9km, NE

14 Amana Medical Institute Pvt Ltd, Kuttippuram 9.2km, NE

15 Shafi Ayurveda Nursing Home, Kutt ippuram 9.55km, NE

16 Taluk Hospital, Kuttippuram 10.3km, NE

17 ThithimuUmma Memorial Ayurveda Hospital, Kudallur

11.1km, NE

18 Pall ippuram Government Hospital, Parudur 13.6km, NE

19 Govt. Hospital, Thrithala 14.1km, NE

20 Modern Hospital, Koottanad 12.1km, SE

21 Govt. Hospital, Chalissery 9.4km SE

22 Ansar Hospital Perumpilavu 11.3km, SE

23 PSM Super Special ity Dental Hospital, Akkikkavu 12.55km, SE

24 Santhi Nursing Home, Punnayurkulam 9.5km, SE

25 Primary Health Center, Palappetty 9km, SE

26 TB Hospital, Ponnani 9.1km, NW

27 Women & Children Hospital, Ponnani 9.1km, NW

28 Imbichibava Memorial Taluk Hospital, Ponnani 9.3km, NW

29 CHC, Thavanur 10km, NW

3. Places of worships

SN Name Approx.

distance & direction

1 Manal iyarkave Temple, Vattamkulam 500m, E

2 Odakkuzhiyi lBagavathi Temple, Vattamkulam 740m, NE

3 Pall iyal i lMurukan Temple, Vattamkulam 860m, NE

4 Badar Masjid, Vattamkulam 1.3km, SE

5 Kalachal Masjid, Kalachal 1km, SE

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 2 Pro ject Descr ip t ion Page 2 - 7

6 NarasimhaMoorthi Temple, Alamcode 1.8km, SE

7 Panthavoor Town Juma Masjid, Alamcode 1.7km, SE

8 AryankavuBhagavathi Temple, Alamcode 3km, SE

9 Hilal Masjid Manthadam, Alamcode 3.25km, SE

10 Masj id, Changaramkulam 4.3km, SE

11 Velayattu Narasimha Moorthi Temple, Nannammukku 4.7km, SE

12 Town Masjid, Valayamkulam 5.8km, SE

13 Masj id, Kokkur 6km, SE

14 Melekkavu Bhagavathi Temple, Mookkuthala 4km, S

15 KannenkavuBhagavathy Temple, Nannammukku 4.1km, S

16 Raktheswaram Siva Temple, Nannammukku 3.4km, SW

17 Juma Masjid, Thamalassery 4.3km, SW

18 Central masjid, Panampad 4.6km, SW

19 Thonnikurumbakkavu Temple, Kanhiramukku 4.6km, W

20 Juma masjid, Kololamba 2.3km, SW

21 Kolath Vishnu Temple, Kololamba 1.4km, SE

22 Juma Masjid, Pokkarathara 0.8 km, W

23 Thali Siva Temple, Pokkarathara 1.1km, NW

24 Juma masjid, Ayilakkad 2.3km, NW

25 ThottuMugham Temple, Kanhiramukku 5.5km, NW

26 Juma masjid, Kanhiramukku 5km, NW

27 ValiyapalamJuma Masjid, Thuyyam 4.1km, NW

28 Thattanpadi Masjid 2.9km, NW

29 Kanayampath Temple, Ponnazhikkara 3.1km, NW

30 Pall iyi l Temple, Ponnazhikkara 3.7km, NW

31 JumaMusjid, Perumparamba 4.4km, NW

32 Mookambika Temple, Perumparamba 4.2km, NW

33 PorookkaraBhagavathy Temple, Ponnazhikkara 3.2km, NW

34 Masj id, Edappal 2.45km, NW

35 Masj id, Naduvattam 1km, NE

36 Mahavishnu Temple, Edappal 1.5km, NW

37 Edappal Chungam Juma Masj id 2km, NE

38 Juma Masjid, Anakkara 6km, NE

39 Potturkavu Ayyappa, Temple 5.5km, NE

40 Sukapuram Dakshinamurthy Temple, Edappal 1.9km, NE

41 Chambramanam TempleVattamkulam 1.6km, NE

42 PilakkalJuma Masjid, Vattamkulam 1.1km, NE

43 ManoorJuma masjid 6.15km, NE

44 ThrikkanapuramJuma Masjid 7.3km, NE

45 Trikkanapuram Sri Narashimhamoorthi Temple 7.4km, NE

46 Town masjid, Kutt ippuram 9.35km, NE

47 St. Joseph's Cathol ic ChurchKuttippuram 10.8km, NE

48 Town masjid Kumbidi 8.6km, NE

49 Panniyur Sri Varahamurthy Temple, Kumbidi 8.5km, NE

50 Shiva temple, Thirthala 14.4km, NE

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 2 Pro ject Descr ip t ion Page 2 - 8

51 Mulayamparambathukavu, Temple, Chalissery 10km, SE

52 St Peters & St. Pauls Orthodox Syrian Church, Chalissery

9km, SE

53 St Mary's Orthodox Syrian Church, Akkikkavu 12.3km, SE

54 Akkikkavu Bhagavathy Temple, Akkikkavu 12.3km, SE

55 Kakkad Mahaganapathi Temple, Kunnamkulam 13.4km, SE

56 St. Mary's Syrian Orthodox Cathedral, Pazhanji 9.7km, SE

57 Mannalamkunnu Juma, Masj id 12km, SW

58 St. Antony's Syro Malabar Catholic Church, Attupuram

10.8km, SW

59 Govindapuram Temple, Kadikkad 10.3km, SW

60 PuthanpallyJuma Masjid Perumbadappu 7.4km, SW

61 SreeBhagavathy Temple, Palappetty 8.6km, SW

62 Masj id Puthiyiruthi 8.4km, SW

63 Eramangalam Juma, Masjid 6.7km, SW

64 ValiyaJuma Masjid, Ponnani 9.2km, NW

4. Community facilities

SN Name Approx.

distance & direction

1 Ration Shop, Vattamkulam 0.72 km, E

2 Post off ice, Alamcode 1.7km, SE

3 Police Station, Changaramkulam 3.6km, SE

4 KSEB, Changaramkulam 3.4km, SE

5 AlamcodeGrama Panchayat Office, Changaramkulam

4km, SE

6 Malappuram District Co-operative Bank, Changaramkulam

4km, SE

7 Gramin Bank, Changaramkulam 4km, SE

8 Galaxy convention Centre, Changaramkulam 4km, SE

9 BSNL Exchange, Changaramkulam 4.6km, SE

10 Mars Cinemas, Changaramkulam 4.9km, SE

11 Post Off ice, Kokkur 6km, SE

12 Nannamukku, Vil lage off ice 3.8km, SE

13 Gramapanchayath, Nannamukku 5.5km, SE

14 Vil lage off ice, Maranchery 5.3km, SW

15 Post off ice, Maranchery 5.1km, SW

16 Panchayat Off ice, Maranchery 5km, SW

17 Federal Bank, Maranchery 4.8km, SW

18 BSNL Telephone Exchange, Maranchery 4.8km, SW

19 Mother Plaza Convention Center, Athani 4.3km, SW

20 Post off ice, Perumparamba 4km, NW

21 Vil lage off ice, Edappal 2.4km, NW

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 2 Pro ject Descr ip t ion Page 2 - 9

22 Post off ice, Edappal 2.4km, NW

23 BP Pump, Edappal 2km, NW

24 SIB,Edappal 2.2km, NE

25 SBI, Edappal 2.5km, NE

26 AEO off ice, Edappal 2.2km, NE

27 Govinda Movies, Edappal 2.65km, NE

28 Saradha theater, Edappal 2.7km, NE

29 KSEB, Edappal 3.8km, NE

30 Panchayat off ice, Vattamkulam 2.6km, NE

31 Ponnani Block Panchayat off ice 2km, NE

32 Vil lage Off ice, Vattamkulam 3.7km, NE

33 Old age Home, Tavanur 8.2km, NE

34 Central Prison, Tavanur 8.3km, NE

35 Post Off ice, Kuttippuram 9.3km, NE

36 Mini Civi l Station, Kuttippuram 9.5km, NE

37 Railway Station, Kutt ippuram 9.4km, NE

38 Fujairah Palace Auditorium, Kuttippuram 9.4km, NE

39 Police Station, Kutt ippuram 10.3km, NE

40 Aanakkara Panchayat Off ice, Kumbidi 8.6km, NE

41 Post off ice, Kumbidi 8.7km, NE

42 Thrithala Block Panchayath Off ice 12.5km, SE

43 Nagalassery Village Panchayath Off ice 12.5km, SE

44 Post Off ice, Koottanad 12.4km, SE

45 Kadavalloor Grama Panchayat Off ice 11.8km, SE

46 Porkulam Panchayat Off ice, Kunnamkulam 12.7km, SE

47 Sub Court, Kunnamkulam 13.6km, SE

48 Vil lage Off ice, Kunnamkulam 13.5km, SE

49 Police Station, Kunnamkulam 14.6km, SE

50 Municipality, Kunnamkulam 14.7km, SE

51 Post Off ice, Punnayurkulam 10.3km, SW

52 Grama Panchayat, Punnayurkulam 10.2km, SW

53 Police Station, Vadakkekkad 10.9km, SW

54 Police Station, Perumbadappu 8.1km, SW

55 Gramapanchayath, Perumbadappu 7.6km, SW

56 Post off ice, Palappetty 8.8km, SW

57 Police Station, Ponnani 8.6km, SW

58 Municipal Off ice, Ponnani 8.9km, NW

59 SBI, Ponnani 8.9km, NW

60 Mini Civi l Station, Ponnani 9.7km, NW

61 Court Ponnani 9.8km, NW

62 Harbour, Ponnani 9.9km, NW

63 Triprangode Vil lage Off ice 13.2km, NW

The site photographs of the existing campus is provided at Plate 2.1.

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 2 Pro ject Descr ip t ion Page 2 - 10

The Conceptual plan showing the salient features of the project viz.

building blocks, locat ion of ut il i t ies, landscape area, pavement area,

internal roads, entries & exits to the site, approach road to the site etc.

and the Conceptual plan of the project is provided as Figure 2.1.

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 2 Pro ject Descr ip t ion Page 2 - 11

FRONT VIEW

REAR VIEW

Plate 2.1 – Current Site Photographs

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 2 Pro ject Descr ip t ion Page 2 - 12

Figure 2.1 : Conceptual plan of the project (Source :- Project proponent)

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 2 Pro ject Descr ip t ion Page 2 - 13

2.1.1 Estimated project cost

The total project cost of the project is about Rs. 180 Crores which

includes the land, bui lding & uti l i t ies etc.

2.1.2 Employment details

The employment detai ls of the exist ing campus is given below :-

Sr.

No.

Description Nos.

1. Total no. of staff expected in the campus

(without accommodation) (l ike faculty, doctors, nurses,

group-IV staff etc.)

290

2. Total no. of staff in the campus (with family

accommodation) ( l ike faculty, doctors, nurses, group-

IV staff etc.)

81

Total 371

The employment detai ls for the new facil ity is given below :-

Sr.

No.

Description Nos.

1. Total no. of staff expected in the campus

(without accommodation)

(l ike faculty, doctors, nurses, group-IV staff etc.)

(210 medical staff & 10 maintenance staff)

220

2. Total no. of staff in the campus

(with accommodation)

(l ike faculty, doctors, nurses, group-IV staff etc.)

155

Total 375

After the proposed expansion the total employment opportunit ies will be

of about 1000 persons (371 nos. + 375 nos. = 746 say 1,000).

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 2 Pro ject Descr ip t ion Page 2 - 14

As a responsible corporate, the proponent shall comply with al l applicable

Acts related to employees’ service and their welfare of the Government of

India in terms of working hours, basic amenit ies and welfare faci l it ies

such as given below:

• Minimum Wages Act, 1948,

• Contract Labour (Regulation & Abolit ion) Act, 1970,

• Inter-State Migrant Workmen (Regulat ion of Employment & Condit ions

of Services) Act,1979,

• The Building and other Construction Workers (Regulat ion and

Employment of Service) Act, 1996,

• The Building and other construct ion workers Welfare Cess Act, 1996.

All workers and technicians wil l be provided with clean drinking water,

sheds for rest ing and sanitary facil it ies as mobile toi lets/ toi lets

connected to sewage treatment plant. Camps shall also be organized for

health check up every six months. No child shall be employed in the

process.

2.1.3 Machinery details & Building materials

The l ist of major machinery used during construction phase is given below :-

i. Dumper Shal l be used for mud and material handling

ii . Concrete mixer with hopper For RCC work

ii i . JCB Shal l be used for digging and earth work

iv. Concrete Batching Plant Will be used for concrete mixing

v. Cranes For lif t ing and moving of materials

vi. Road roller For compacting the earth

vi i . Bulldozer For dismantl ing

List of building materials to be used at site is as fol lows:

• Coarse sand

• Fine sand

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 2 Pro ject Descr ip t ion Page 2 - 15

• Stone aggregate

• Stone for masonry work

• Stone for under f loor soling

• Cement

• Reinforcement steel

• Plywood & steel shuttering

• Pipe scaffolding (cup lock system)

• Bricks

• Crazy (white marble) in grey cement

• P.V.C. conduit

• Indo-Asian MCBs

• PVC overhead water tanks

• 2 1/2'’ thick red colour paver t i les

• ‘B’ class GI pipe (ISI marked)

• PVC waste water l ines

• S.W. sewer l ine upto main sewer

• PVC rain water down take

• Stainless steel s ink in kitchen

• 5mm thick plane glass

• 3mm thick ground glass in toilets

• Joinery hardware- ISI marked

2.2 Type of project

The proposed project is a Hospital cum Medical campus project in the

name of "Sreevalsam Inst itute of Medical Sciences".

The proposed project is an expansion of building construction project. The

exist ing project was construct buildings with buil t-up area of 53,889.72

sqm and the addit ional construction of 85,047.78 sqm wil l be construct

within the exist ing campus.

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 2 Pro ject Descr ip t ion Page 2 - 16

2.3 Need for the project

Due to the rapid development in Kerala there are lots of resident ial,

commercial and off ice building construction projects are introduced and

thereby the f loat ing of populat ion from their nat ive place to their working

place / urban area is going on. Due to the high rate of populat ion shif t ing

there is an increase in burden on the infrastructure and medical faci l it ies

of an area. To accommodate the same the medical hospital with high

patient management capacity with quality services is must in every

districts of the State. In order to overcome this problem, M/s Sreevalsam

Educational Trust decide the expansion of their existing hospital cum

medical college project in Edappal Vil lage, Ponnani Taluk, Malappuram

Distr ict, Kerala.

There is an urgent requirement for the construction of hospital cum

medical col lege with associated activit ies in the area as per the faci lit ies

to be provided to the nearby people to facil itate on easy and quick

medical faci l it ies and thereby the hospital/healthcare and medical

educat ional services in a very easy way as per the needs.

2.4 Location

The project site is within the Panchayat l imits of Edappal Grama

Panchayat. The nearest town is Edappal town which is about 2 km away

(N) from the site and the nearest city is Kozhikode city and is located

about 60 km (NW). The Ponnani taluk is located about 9 km in west

direction. The route map to the project site is provided at Figure 2.2.

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 2 Pro ject Descr ip t ion Page 2 - 17

Figure 2.2 – Route map to the project site

(Source :- Google Earth) (Vintage : 2019)

Table 2.2 - Immediate site surrounding features

Direction Features existing

North Connecting road, Individual houses and others’ property

South Others’ property with coconut plantation and agricultural area

East Others’ property with coconut plantation and agricultural area

West Individual houses, others’ property with coconut plantat ion

The satel li te map showing the important environmental features within

10 km. radius of the project site is given in Figure 2.3 & Satell ite map of

the project s ite superimposed with project boundary is given in Figure 2.4.

The toposheet of the study area is given in Figure 2.5. The vicinity map

of the study area is given in Figure 2.6.

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 2 Pro ject Descr ip t ion Page 2 - 18

Fig. 2.3 Satellite map showing important environmental features within 10 km. radius

(Source :- Google Earth) (Vintage : 2011)

SN Important environmental features Aerial Distance & Direction

1. Ponnani Lake about 1 km, (NW)

2. Drain / thodu about 0.5 km (S)

3. Beeyam Kayal about 5 km (NW)

4. Naranipuzha river about 5.5 km (SW)

5. Kolanchiri Padam about 4 km (SW)

6. Bharathapuzha about 7 km (NW)

7. Manoor Kayal about 3 km (N)

8. Lakshadweep Sea about 9 km (SW)

9. SH-69 (Thrissur-Kuttippuram Rd.) (Kaladithara) about 0.7 km (E)

10. NH-17 (Edappally-Panvel Highway) (at Edappal Town) about 2 km (N)

1

2

3

4

5

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 2 Pro ject Descr ip t ion Page 2 - 19

Figure 2.4 – Satell ite image superimposed with project boundary

(Source :- Google Earth) (Vintage : 2011)

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 2 Pro ject Descr ip t ion Page 2 - 20

Figure 2.5 - Toposheet of SOI showing 10 km radius of the project site -

(Source : Extracted from Survey of India, Topo Map) (Vintage : 2011)

SN Important environmental features Aerial Distance & Direction

1. Ponnani Lake about 1 km, (NW)

2. Drain / thodu about 0.5 km (S)

3. Beeyam Kayal about 5 km (NW)

4. Naranipuzha river about 5.5 km (SW)

5. Kolanchiri Padam about 4 km (SW)

6. Bharathapuzha about 7 km (NW)

7. Manoor Kayal about 3 km (N)

8. Lakshadweep Sea about 9 km (SW)

9. SH-69 (Thrissur-Kuttippuram Rd.) (Kaladithara) about 0.7 km (E)

10. NH-17 (Edappally-Panvel Highway) (at Edappal Town) about 2 km (N)

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 2 Pro ject Descr ip t ion Page 2 - 21

Figure 2.6 - Vicinity map showing 10 km. radius of the project site

(Source :- Google Earth) (Vintage : 2011)

1

2

3

4

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 2 Pro ject Descr ip t ion Page 2 - 22

2.5 Geology

2.5.1 Regional Geology

From the exposure pattern of the rock types, the district can be divided

into two geological belts: ( i) Charnockite group of rocks covering a major

part and (i i) Migmatite Complex towards the east. Wayanad group is

represented by small bodies of metaultramafites (tal-tremolite schist, talc-

pyroxene-garnet schist, banded magnetite quartzite) and high-grade

schist and gneiss (hornblende-bioti te schist and gneiss+garnet with

amphiboli te band) which extends into Tamil Nadu where it is known as

Sathyamangalam Group. The rocks of Peninsular Gneissic Complex,

represented by granite gneiss and hornblende-biot ite gneiss, form the

next younger sequence. They have a very limited distribut ion near the

eastern boundary. They have a very l imited

distribut ion near the eastern boundary, extending into the adjacent district

where they are known as Bhawani Group. A l inear band of granite gneiss

NE of Perinthalmanna and a large body of hornblende-bioti te gneiss east

of Manjeri are prominent units. Charnockit Group includes charnockite /

charnockite gneiss, having the largest areal distr ibut ion, fol lowed in

decreasing order of abundance by banded magnetite quartzite, pyroxene

granulite, amphibolite/hornblende granul ite and pyroxenite, which occur

as concordant as well as discordant bands, lenses, layers and enclaves

both within charnockite as well as within gneisses of Migmatite Complex.

The Migmatite Complex is represented by biot ite-hornblende gneiss (or

hornblende-biot ite gneiss) and quartzo-feldspathic gneiss/garnet-bioti te

gneiss with enclaves of garnet-sil l imanite gneiss + graphite distr ibuted

mostly in the central and northeastern part. Pegmatite and quartz veins

constitute the acid intrusives, whereas gabbro and dolerite are basic

intrusives. Near the coast, isolated cappings of Neogene Warkal l i

sediments comprising grit and clay beds are noticed. Laterit isat ion is

widespread, at places attaining a thickness of more than 10m. Extensive

plateaus with later ite ‘mesas’ are common in the area. Angadipuram (west

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 2 Pro ject Descr ip t ion Page 2 - 23

of Perinthalmanna), the type locality of later ite falls in this district.

Quaternary unconsolidated sediments are restricted to the coastal plain.

They have been classif ied into dif ferent morpho-stratigraphic units based

on their l i thic content and environment of formation. Guruvayur Formation

(palaeo-marine), Periyar Formation (f luvial), Viyyam Formation (f luvio-

marine) and Kadappuram Formation (marine).

(Source - District Survey Report, Malappuram District published by Mining

& Geology Department, Govt. of Kerala).

2.5.2 Local Geology

The local geology belongs to the regional geology. The site is exist ing

hospital cum institutional buildings with coconut t rees.

2.6 Topography

This is an exist ing hospital cum medical col lege project and there are

exist ing buildings with nat ive tree species of coconut plants with other

species of shrub, herbs, grass in that area. Some of the buildings are

under construction and some of the buildings are to be proposed. As per

the topographical contour survey map, the highest level is 100 m in the

northern direct ion and lowest elevation is 88 m in the southern direction.

The drainage of the site area is towards north to south direct ion. The

topographical contour map of the project site is provided at Figure 2.7.

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 2 Pro ject Descr ip t ion Page 2 - 24

Figure 2.7 - Topographical contour map of the project site (Source :- Project proponent) (Vintage : 2011)

1

2

3

4

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 2 Pro ject Descr ip t ion Page 2 - 25

2.7 Size or Magnitude of the project

The plot area break-up detail is given at Table 2.3 below :-

Table 2.3 - Plot area break-up

Description Area (in sqm) %

Total Green Area (A) 35,308.66 (37.35%)

Ground Coverage of buildings (B) 37,813.82 (40%)

Area under roads / services (C) 21,412.08 (22.65%)

Total Plot Area (E=A+B+C) 94,534.56 (100%)

The buil t-up area break-up detai l is given at Table 2.4 below :-

Table 2.4 - Built-up area break-up

Description Area (in sqm)

FAR Area 1,10,480.22 sq.m.

Non FAR Area 28,457.28 sq.m.

Total Built-up Area 1,38,937.5 sq.m.

The building block detai l with its status of construct ion is given at table

2.5.

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 2 Project Descr ipt ion Page 2 - 26

Table 2.5 - Building block detail with its construction status

Building Block nos. & Name

Max. No. of Floors

Max. Height

Total Built-up

area (sq.m)

Status of Construction with Built-up area (sq.m)

Building permit no. & date

224/11-12 (BF + GF.)

03-11-2011

B2-224/11-12 (1,2,3&4 Floors)

27-06-2012

Hospital building B+G+5 24.45 38896 38118.08 Constructed

A5 -365/13-14 5th floor hospital

24-03-2014

Academic building G+3 15 16907.95 6594.10 Constructed

Auditorium building G+Balcony Flr

11.94 1715.95 Proposed

Doctor Quarters (total of 3 quarters)

G+8 28 10350.39

3622.63 Constructed

Staff Quarters (total of 2 quarters)

G+2 9.45 2504.44

1252.22 Constructed

Hostels (ladies & Gents hostels each)

G+2 10.35 5843.44

1168.68 Constructed

Canteen / special Residential bui lding

G+2 13.15 1026.6 1026.6 Constructed

Doctor's residence Vil las (type 1) (Total of 3 vil las)

G+1 6.45 750.03

Proposed

Doctor's residence Vil las (type 2) (Total of 8 vil las)

G+1

6.45 1566.88

Proposed

Nurses G+2 11.85 540.99 411.15

A5-365/13-14 24-03-2014

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 2 Project Descr ipt ion Page 2 - 27

accommodation / manifold room

Constructed

Non teaching staff Quarters / Electrical room

G+2

10.95 1432.52 1432.52 Constructed

Teaching hospital B+G+5 24.45 32506 Proposed

Nursing school B+G+4 19.35 22358 Proposed

Commercial complex

B+G+2 13 2210 Proposed

Laundry G 3 175.19 166.43 Constructed

Animal house G 4.6 153.12 97.23 Constructed

Total 1,38,937 53,889.72 Completed

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 2 Pro ject Descr ip t ion Page 2 - 28

2.8 Design Consideration

The project was constructed in conformity with the Kerala Municipal

Building Rules (KMBR). As per seismic zone classif icat ion, the project

site fal ls in Zone-II I. The construction of buildings structures proposed in

the existing campus wil l be designed after due study of the local

architecture.

Further, as per the google images of the site prior to the site development

in January, 2008, December, 2009, it can be observed that the site area

is with part ial ly vacant land and partially coconut plantat ion and the

google images is provided at Figure 2.8, Figure 2.9. The satel lite image

of the site area after the commencement of construction act iv ity

(December, 2012, Apri l, 2013, December, 2013 & December, 2018 &

Current image of August, 2019) is provided at Figure 2.10 to Figure 2.14.

Figure 2.8 - Time series Satellite image of the site area prior to the commencement of construction activity - January, 2008

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 2 Pro ject Descr ip t ion Page 2 - 29

Figure 2.9 - Time series Satellite image of the site area prior to the commencement of construction activity - December, 2009

Figure 2.10 - Time series Satellite image of the site area hospital block under construction - December, 2012

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 2 Pro ject Descr ip t ion Page 2 - 30

Figure 2.11 - Time series Satell ite image of the site area hospital block & non-teaching staff quarter under construction - April , 2013

Figure 2.12 - Time series Satell ite image of the site area hospital block & other buildings under construction - December, 2013

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 2 Pro ject Descr ip t ion Page 2 - 31

Figure 2.13 - Time series Satell ite image of the site area - December, 2018

Figure 2.14 - Time series Satell ite image of the site area -

Current image - August, 2019

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 2 Pro ject Descr ip t ion Page 2 - 32

2.8.1 Site History

Before the site development the si te is used as agricultural purposes and

with coconut plantat ion. There were about 100 coconut trees existing at

site which was cut for development of the site. The construct ion of the

buildings at site was done as per the building permit issued by the

Regulatory Authority i .e. Edappal Grama Panchayat.

2.9 Parking

The project would provide vehicle parking facil it ies within the project

premises. The parking plan for this project would follow KPBR guidel ines.

The total number of parking provided wil l be 1,184 Cars + 1,409

Two-wheelers within the site. There are provision of two separate wide

entry / exit point for the project for easy & smooth vehicular movement.

The suff icient parking provisions are made with the complex so that the

patient, students, vis itors & staff in hospital cum medical col lege wi ll not

disturb due to vehicular movement / parking.

The access to the project si te is from 10 m wide & 8 m wide road in the

northern direction of the site which are well connected to Thrissur-

Kutt ippuram Road located at about 1 km from the site in northern

direction.

2.10 Description of mitigation measures incorporated into the project to meet environmental standards. 2.10.1 Water supply and sewage disposal during construction phase

2.10.1.1 Source of Water during construction phase

The sources of water for construction purposes wil l be from exist ing well

water, stored rain water in pond and recycled water from existing STP.

For domestic purposes, the sources of water wil l be from well water.

There are open wel l (1 no.) and tube well (5 nos.) existing at “Sreevalsam

Institute of Medical Sciences” campus.

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 2 Pro ject Descr ip t ion Page 2 - 33

2.10.1.2 Daily Water Requirement during construction phase

The daily water requirement for construct ion activit ies is about 312 KL

(for 48 months) (1.1 KL x 85,047.78 sqm of built -up area = 93,552 KL i.e.

312 KL/day) and for meeting domestic requirement is about 27 KL

(250 workers at site, avg.) (for 48 months).

2.10.1.3 Sewage disposal during construction phase

The sewage generat ion from the labourers during construct ion phase is

expected to be about 27 KL/day which wi ll be disposed through STP

within the site. The treated water from the mobile STP wil l be used for

wetting of dust suppression and for landscaping purposes within the site.

2.10.2.1 Source of Water during operation phase

The sources of water for meeting the domestic requirement as well as

other requirements during operation phase of the proposed hospital cum

medical col lege project wil l be from exist ing wells, stored rain water and

recycled water from STP / ETP.

There are open wel l (1 no.) and tube well (5 nos.) existing at “Sreevalsam

Institute of Medical Sciences” campus.

2.10.2.2 Daily Water Requirement during operation phase

The total daily water consumption for the proposed project would be

about 1,328 KL (fresh water 677 KL + recycled water 651 KL). The f irst

day fresh water requirement is 1,328 KL and subsequent days, the daily

fresh water requirement is 677 KL. The daily domestic water consumption

is 870 KL (f lushing purposes 647 KL + non-f lushing purposes 223 KL).

Water is an essential component of the basic infrastructure for urban

sett lements. Besides domestic use, water is also required for f ire f ight ing

and other miscel laneous purposes. The occupier, patients, v is itors & staff

need water for domestic purposes and for miscellaneous purposes. The

water requirements have been calculated as per National Building Code,

2016 of India and “Manual on norms and standards for environment

clearance of large construct ion projects” by Ministry of Environment &

Forests, Govt. of India considering the requirements of water for the

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 2 Pro ject Descr ip t ion Page 2 - 34

faci l ity. The daily water consumption calculation for the project is given

below :

Operation phase – Existing Campus

Non-Flushing Requirement

Flushing Requirement

Total SN

Description

In KL / Day

1 In Patients ( No. of Beds ) = 570 Beds

( Including Laundry ) 570 x 405 Ltr. = 230.85

570 x 45 Ltr. = 25.65

256.5

2 Visitors / bye-standers inpatients = 1,140

Persons ( 2 Persons / Bed ) 1140 x 5 Ltr. = 5.70

1140 x 10 Ltr. = 11.40

17.10

3 Out Patients = 1140 Persons 1140 x 5 Ltr. = 5.70

1140 x 10 Ltr. = 11.40

17.10

4 Visitor / bye-standers with OPD patient = 1140 Persons ( 1 Person / Out Patient )

1140 x 5 Ltr. = 5.70

1140 x 10 Ltr. = 11.40

17.10

5 Total staff in the campus (without

accommodation) (like faculty, doctors, nurses, group-IV staff etc.) = 290 Persons

290 x 15 Ltr. = 4.35

290 x 30 Ltr. = 8.7

13.05

6

Total no. of staff in the campus (with family accommodation) (like faculty, doctors, nurses,

group-IV staff etc.) = 81 staff (81 staff x 5 person = 405 persons)

405 x 90 Ltr. = 36.45

405 x 45 Ltr. = 18.225

54.675

TOTAL 288.75 86.775 375.525

Operation Phase – Proposed facilities in the campus

Non-Flushing Requirement

Flushing Requirement

Total Sr. No.

Description

In KL / Day

1 In Patients ( No. of Beds ) = 600 Beds

( Including Laundry ) 600 x 405 Ltr. = 243.00

600 x 45 Ltr. = 27.00

270.00

2 Visitors / bye-standers inpatients = 1200

Persons ( 2 Persons / Bed ) 1200 x 5 Ltr. = 6.00

1200 x 10 Ltr. = 12.00

18.00

3 Out Patients = 1200 Persons 1200 x 5 Ltr. = 6.00

1200 x 10 Ltr. = 12.00

18.00

4 Visitor / bye-standers with OPD patient = 1200 Persons (1 Person / Out Patient )

1200 x 5 Ltr. = 6.00

1200 x 10 Ltr. = 12.00

18.00

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 2 Pro ject Descr ip t ion Page 2 - 35

5

Total no. of staff expected in the campus (without accommodation) (like faculty, doctors, nurses, group-IV staff etc.)

(210 medical staff & 10 maintenance staff) = 220 staff

220 x 15 Ltr. = 3.30

220 x 30 Ltr. = 6.6

9.9

6

Total no. of staff in the campus (with family accommodation) (like faculty, doctors, nurses, group-IV staff etc.) = 155 staff (155 staff x 5 person = 775 persons)

775 x 90 Ltr. = 69.75

775 x 45 Ltr. = 34.875

104.625

7 Total no. of students expected in the

campus (without accommodation facility) = 174 students

174 x 15 Ltr. = 2.61

174 x 30 Ltr. = 5.22

7.83

8 Total no. of students expected in the

campus (without accommodation facility) = 576 students

576 x 90 Ltr. = 51.84

576 x 45 Ltr. = 25.92

77.76

TOTAL 388.50 135.615 524.115

Total Water Requirement after the proposed expansion (Existing + Proposed facility)

Non-Flushing

Requirement

Flushing

Requirement Total Sr.

No. Description

In KL / Day

1. EXISTING CAMPUS 288.75 86.775 375.525

2. PROPOSED CAMPUS 388.50 135.615 524.115

TOTAL POPULATION = 10,630 Persons

(on full occupancy after the proposed

expansion) (fixed/floating)

677.26

Say 677 KL

222.39

Say 223 KL

899.64

Say 900 KL

The daily water consumption balance chart for the ent ire campus (exist ing

+ proposed faci l ity) is provided at Figure 2.15

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 2 Pro ject Descr ip t ion Page 2 - 36

Figure 2.15 - Daily water consumption balance chart

The specif ic water consumption for various purposes is worked out and is

given below:-

S.

N.

Particulars

Daily Requirement

(in KL) Sources of water

1. Domestic Water Requirement

( Non-Flushing purposes ) 647

Fresh water (Stored Rain

water and Ground water)

2. Domestic Water Requirement

( Flushing purposes ) 223 Recycled water from STP

3. Hort iculture Water Requirement 55 Recycled water from STP

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 2 Pro ject Descr ip t ion Page 2 - 37

4. Boiler water requirement 20 Recycled water from STP

4.

Make-up Water Requirement for

Cooling Towers attached with

air condit ioning system

353 Recycled water from

STP/ETP

5. Laboratory & Laundry

requirement 30

Fresh water (Stored Rain

water and Ground water)

2.10.2.3 Sewage disposal during operation phase

The sewage generat ion from the proposed hospital cum medical campus

during operation phase is expected to be about 696 KL/day which wil l be

disposed through STP within the site. The treated water from STP wil l be

used for f lushing purposes, landscaping purposes, boiler requirement and

make-up water requirement for cooling towers attached with the HVAC

system within the site.

The treatment scheme proposed for the domestic sewage is MBBR

treatment and Tertiary Treatment with UV method for disinfect ion and ultra

f i ltrat ion (UF).

The sewage treatment plant (STP) with the fol lowing treatment units:-

� Grit Chamber.

� Oil separator

� Grit chamber

� Equalizat ion tank

� Reactor

� Sett l ing tank

� Aeration tank-I

� Aeration tank-I I

� Clarif ier -I

� Clarif ier-II

� Fi lter feed tank

� PSF

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 2 Pro ject Descr ip t ion Page 2 - 38

� PCF

� Final storage tank

� Sludge holding tank

� Soak pit

� Sept ic tank

The schematic diagram of the STP is provided in Figure 2.16.

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 2 Pro ject Descr ip t ion Page 2 - 39

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 2 Pro ject Descr ip t ion Page 2 - 40

Figure 2.16 - Sewage Treatment Plant diagrams

The photographs of the sewage treatment plant is provided at Plate 2.2

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 2 Pro ject Descr ip t ion Page 2 - 41

Photo-1 - Existing Sewage Treatment Plant (STP)

Photo-2 - Existing Sewage Treatment Plant (STP)

Plate 2.2 - Photographs of the STP installed within the site

Also, for treatment of eff luent from the laundry & laboratory area, i t is

proposed to sett ing up of a Eff luent Treatment Plant (ETP) for an capacity

of about 33 KL capacity. The treated water from the ETP would be

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 2 Pro ject Descr ip t ion Page 2 - 42

recycled to meet the water requirement of make-up water requirement for

cooling towers attached with HVAC system.

It is proposed to install a water treatment plant of capacity consists of

pressure sand f ilter-1, iron removal f i l ter, activated carbon f i l ter, water

softener and pressure sand f il ter-2 wil l be proposed apart from other

treatment units. The water treatment plant diagram is provided in Figure

2.17.

Figure 2.17 - Water Treatment Plan diagram

2.11.1 Storm water management (surface water drainage) and rain water harvesting

During construction phase :

The storm water within the site wil l be part ial ly channelized to the rain

water storage tank. Appropriate de-sil t ing and oi l removal will be provided

so that the storm water wil l not contaminate the land and aquifer.

During operation phase :

To conserve water, rainwater storage capacity of 5,000 KL is provided at

the site. It is provided that roof rain water wi l l be directed to rain

harvest ing tanks after de-si ltation, the removal of oi l and grease through

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 2 Pro ject Descr ip t ion Page 2 - 43

a trap within site. This water wi ll be used for dai ly requirement after

suitable treatment. Excess rain water shall be lead to storm water drain

available near the site.

� The annual runoff f rom the site before site development is calculated

as fol lows :-

• Site area = 9.4534 ha = 94,534 sqm

• Annual rainfal l = 3.677 m

• Run-off co-eff icient = 0.5

• Annual runoff = 94,534 x 3.677 x 0.5

= 1,73,800 Mill ion l iters.

� After the development of the project site:-

Descript ion Ground coverage

Hard surface + Green area

Area (in sq.m.) 37,813.82 56,720.18

Annual rainfal l (in m.) 3.169 3.169

Run-off co-eff icient 0.8 0.3

Peak annual run-off (in KL) 95,865 53,924

� Total annual run-off f rom the site = 1,49,789 KL (95,865 + 53,924)

� Capacity of rain water storage tanks/pond = 5,000 KL (concurrent use and post rainy use) � After development of the site, net run-off f rom the site = 53,924 KL

� The proposed development does not affect the drainage pattern of the

site and surroundings. The topographical contour map of the site is

provided at Figure 2.7 above.

2.11.2 Solid Waste Management

Construction phase

There wil l be about 80 kg/day of municipal sol id waste will be generated

from the labourers during construct ion phase which wil l be disposed to the

exist ing bio-gas generation plant. An equivalent quantity (80 kg/day) of

other solid waste wil l be generated from the construct ion site which wil l be

disposed as per Solid Waste Management Rules, 2016. Also, Construct ion

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 2 Pro ject Descr ip t ion Page 2 - 44

& Demolit ion Waste Management Rules, 2016 will be fol lowed for handling

of waste during construct ion phase.

Operation phase

Municipal Solid waste

After the proposed expansion of hospital cum medical college campus

wi ll generate 2,093 Kg/day of sol id waste.

The Solid Waste Management Rules, 2016 wil l be fol lowed in the Solid

Waste management at the site.

Collect ion & segregation within the site (bio-degradable waste ( in green

bins), non-biodegradable waste (in blue bins) and domestic hazardous

waste (in yellow bins).

The recyclable waste like packaging material, paper etc. would be sold

through vendors. The Bio-degradable waste would be disposed through

the bio-gas generation plant to be instal led within the site. The project

has earmarked an area of about 250 sq m for storage of segregated

recyclable solid waste within the project s ite. The manure generated wil l

be ut il ized for green area development within the premises.

The photograph of the existing bio-gas generat ion plant is given at Plate

2.3.

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 2 Pro ject Descr ip t ion Page 2 - 45

Photo-1 - Exist ing Bio-gas Generat ion Plant

Photo-2 - Exist ing Bio-gas Generat ion Plant

Plate 2.3 - Photographs of the Existing Bio-gas Generation Plant instal led within the site

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 2 Pro ject Descr ip t ion Page 2 - 46

The domestic hazardous waste which includes discarded painted drums,

pest ic ide cans, CFL bulbs, tube lights, expired medicines, broken mercury

thermometers, used batteries, used needles and syringes and

contaminated gauge etc. generated at site wi ll be collected in yellow bins

and to be handed over to authorized waste pickers or waste collectors.

Bio-Medical Waste:-

� From the proposed hospital cum medical college campus, bio-medical

waste (819 Kg/day) like infectious beddings, cotton, swabs, used

syringes, discarded medicines, etc. would be generated.

� The bio-medical waste would be segregated at source by providing

appropriate colour coded bins / containers as per the colour coding

provided in the Bio-Medical Waste (Management & Handling) Rules, 2016.

About 150 sq m of area is earmarked for the storage of bio-medical waste.

� The Bio-medical waste from the existing hospital cum medical college is

outsourced through Kerala State Pollution Control Board authorized

agency (M/s Indian Medical Association Goes Eco Friendly, IMAGE) and

the same arrangement will be continued for expansion facility also. The

copy of the MoU between IMAGE & the project proponent was made and

the copy of the same is attached as Annexure No. 2.1.

Hazardous Waste :-

� As per Hazardous Waste (Management & Handling Rules), 2016, the

hazardous waste i.e., the used oil f rom D.G. sets, discarded oi l f i l ters

and discarded batteries and stored separately and wil l be disposed to

CPCB / SPCB authorized vendors only.

� Some of the approved recyclers l ike M/s Perfect Alloys, Chengannur,

M/s Peejay Enterprises, Thiruvalla, M/s Excel Petrochemicals, Kochi

and M/s Cee Jee Lubricants, Aluva are the approved recyclers for

discarded batter ies & used oi l located in Kerala.

e-WASTE :-

� Discarded computer parts, monitor, key boards etc. const itutes e-waste

and this waste wi ll be stored in an earmarked area.

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 2 Pro ject Descr ip t ion Page 2 - 47

� E-waste wi ll be generated after 4-5 years latency period. Separate

earmarked space wil l be provided for e-waste storage.

� E-waste wil l be disposed as per E Waste (Management & Handling) Rules.

2.11.3 Green Area Development

As part of the landscape development for the project, the measures to

minimize the impacts as given below:-

About 37% (35,308.66 sq.m.) of total land area is developed as part of

green belt, it is recommended that plantat ion is done along the peripheral

areas and open spaces of the project site. The roof garden is also

maintained on the terrace. This wil l help to reduce the noise levels, dust

spread and also enhances the aesthet ic value of the project site.

The l ist of tree already planted within the campus is given at table 2.6.

Table 2.4 - List of tree species already planted within the campus

Sr. No. Name of tree species Numbers

1 Palm trees 74

2 Mango trees 8

3 Ashoka trees 20

4 Graviola 35

5 Jack fruit tree 4

6 Guava tree 10

7 Coconut tree 367

8 Other trees 22

9 Banyan 3

10 Amla 4

11 Golden shrum tree 7

12 Bullet wood tree 10

13 Papaya 10

14 Catharanitur roses 25

15 Thulsi 20

16 Coleus ambolnicus 4

17 Geranium plant 15

18 Pinwheel f lower 250

19 Teale wood 12

Total 900

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 2 Pro ject Descr ip t ion Page 2 - 48

The photographs of the plant species / tree species already planted within

the campus is given at Plate 2.4.

The photographs of the road side plantat ion within the campus is given at

Plate 2.5.

Photo 1 - Bullet wood tree Photo 2 - Jack fruit tree

Photo 3 - Ashoka tree Photo 4 - Purple feabane plant

Photo 5 - Pappaya tree Photo 6 - Catharanthus Roseus

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 2 Pro ject Descr ip t ion Page 2 - 49

Photo 7 - Thulasi Photo 8 - Coleus Amboinicus

Photo 9 - Palm tree Photo 10 - Teak tree

Plate 2.4 - Photographs of the plant species / tree species already planted within the campus

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 2 Pro ject Descr ip t ion Page 2 - 50

Plate 2.5 - Photographs of the road side plantat ion within the campus

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 2 Pro ject Descr ip t ion Page 2 - 51

2.11.4 Air pollution control

Construction phase

To minimize the impact on the pat ients / occupiers in the exist ing campus,

residents in the vicinity and the ecological environment due to increase in

air pol lution levels caused by various construction activit ies and vehicular

emissions, emissions from construction equipments and D.G. sets. The

following mitigat ive measures would be adopted :-

� The construct ion site wil l be isolated from the exist ing Hospital cum

Medical College campus through wind barr iers of 30 feet height.

� No loose soil or sand or construct ion waste or any other

construction material wil l be left uncovered.

� Water sprinkling during summer days in the unpaved areas.

� Grinding and cutt ing of t i les / stones wil l be carried out in

enclosures.

� Wet jet shall be provided for gr inding, stone cutt ing and dri l l ing

areas.

� The roads within the construction site will be black top.

� Loose construction materials l ike sand, gravel wil l be stored within

earmarked area only and regular wett ing of the same. Before the

unloading of these materials, wetting wil l be carried out.

� Special care wil l be taken to avoid spil lage of loose construction

materials.

� The loose construction materials will be covered with tarpaulin

during transportation.

� The DG Set (100 kVA x 2 nos.) used wil l be with adequate stack

height as per CPCB guidel ines.

� All construction machinery wil l be in good working condit ions and

regular maintenance wi ll be ensured.

� All construction workers wi ll be provided with dust masks / PPEs.

� Ready mix concrete wi ll be used to avoid the use of loose

construction materials at s ite to reduce dust emissions.

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 2 Pro ject Descr ip t ion Page 2 - 52

Operation phase

To minimize the impact on pat ients / occupiers in the exist ing Medical

College campus and ecological environment due to increased air pollut ion

levels caused by vehicular emissions and D.G. set emissions. The

following mitigat ive measures would be adopted :-

� The stack height of DG sets (Existing - 500 kVA x 1 no. + 625 kVA x

1 no. and Proposed - 500 kVA x 1 no. + 625 kVA x 1 no.) would be

as per the CPCB standards and it would be roof of the building.

� Landscaping wil l be done with suitable nat ive species within the

earmarked site.

2.11.5 Noise pollution control & vibration

Construction phase

To minimize the impact on the pat ients in the hospital and on human

health and ecological environment in the vicinity due to increased noise

levels caused by various construction activ it ies and by vehicular

movements, construct ion equipments and D.G. set (100 kVA x 2 nos.) and

Impact on exist ing structures due to increased vibration levels caused by

operation of D.G. Sets. The following mit igat ive measures would be

adopted :-

� The construction site wil l be isolated from the exist ing buildings

through noise barriers.

� High noise generation act iv it ies wi ll not be carried out during OP

consultation hours.

� Use of D.G. Sets (100 kVA x 2 nos.) with acoust ic enclosures.

� Wind breakers / acoustic enclosures made of gunny bags f i l led with

sand or earth and stacked up to a height of about 7-8 feet at the stone

cutt ing & grinding area.

� Regular maintenance of construct ion equipments and machinery.

� All construct ion workers to be provided with PPEs.

� All construct ion / demolit ion activit ies will be restr icted to day t ime only.

� Use of ant i vibrat ion pads for the DG sets to reduce vibrat ions

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 2 Pro ject Descr ip t ion Page 2 - 53

Operation phase

To minimize the impact on the pat ients in the hospital and on human

health and ecological environment in the vicinity due to increased noise

levels caused by cooling towers and D.G. sets and Impact on structures

due to increased vibrat ion levels caused by operation of D.G. Sets. The

following mitigat ive measures would be adopted :-

� All the DG Sets (Exist ing - 500 kVA x 1 no. + 625 kVA x 1 no. and

Proposed - 500 kVA x 1 no. + 625 kVA x 1 no.) of the project s ite

are attached with acoustic enclosures and ant i v ibrat ion pads.

� The cooling towers wil l be located in an isolated area.

� Green belt development.

2.11.6 Vehicular traffic density

Vehicular traff ic density survey was carried out on 19-11-2018 on

Thrissur-Kuttippuram Road and the survey report is provided below :-

Date :- 19-11-2018 (Thrissur to Kuttippuram)

TIME Cars Two

Wheelers Three

Wheelers Buses LCV Trucks

8am – 9pm 30 24 9 8 6 17

9am – 10am 24 21 15 9 9 7

10am – 11am 15 27 10 4 18 12

11am – 12Noon 21 30 17 6 17 34

12Noon – 1pm 30 51 12 5 5 10

1pm – 2pm 15 39 19 6 6 14

2pm – 3pm 24 33 9 8 16 19

3pm – 4pm 6 39 15 9 30 21

4pm – 5pm 30 15 9 12 14 Ni l

5pm - 6pm 8 51 14 5 6 24

6pm-7pm 12 36 12 3 8 17

7pm – 8pm 12 48 15 6 8 Ni l

Total Volume 227 414 156 81 143 175

In PCU* 227 207 125 284 315 613

Date :- 19-11-2018 (Kuttippuram to Thrissur)

TIME Cars Two

Wheelers Three

Wheelers Buses LCV Trucks

8am – 9pm 34 27 29 12 7 Ni l

9am – 10am 20 29 40 10 12 7

10am – 11am 17 38 26 6 21 4

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 2 Pro ject Descr ip t ion Page 2 - 54

11am – 12Noon 18 28 28 5 24 28

12Noon – 1pm 32 44 18 8 9 34

1pm – 2pm 17 46 24 9 8 24

2pm – 3pm 20 40 28 12 19 26

3pm – 4pm 7 46 29 8 34 20

4pm – 5pm 34 24 7 17 19 11

5pm - 6pm 9 55 16 4 8 10

6pm-7pm 17 39 19 6 11 Ni l

7pm – 8pm 14 55 24 8 10 Ni l

Total Volume 239 471 288 105 182 164

In PCU* 239 236 230 368 400 574

*Values of PCU

Car 1.0

Motorcycle 0.5

LCV 2.2

Bus, Truck 3.5

3-wheeler 0.8

2.11.6.1 Interpretation

The above traff ic volume is within carrying capacity of road as per Indian

Road Congress (IRC) standards.

2.11.7 Fire Fighting System

Following provisions are required to be made according to National

Building Code 2005 with its subsequent amendments. The f ire f ighting

system has been designed considering the fol lowing codes, manual and

guidelines;

• National Building Code of India (NBC);

• Latest relevant NFPA codes, USA, in particular NFPA – 13, 14, 20 & 22;

• IRI guidelines;

• As per requirement of f ire off icer/ local f ire approving authorit ies; and

• As per Indian Standard Code for Fire Protect ion (IS Codes)

Following items are envisaged for f ire f ighting:-

• Fire-Water Connect ions;

• Firewater inlet and outlet connections shall be provided to the water

storage tanks;

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 2 Pro ject Descr ip t ion Page 2 - 55

• External main f ire ring, having 150 mm diameter and hydrants @ 45

m3 /s spacing shall be provided. This external f ire ring shall be

separated from the Sprinkler Main Systems;

• All f low switches, test valves, drain pipes etc. shal l be provided as per

NFPA guidelines on the sprinkler system;

• All pump instal lat ion and arrangements shall be in accordance with IRI

guidelines and NFPA-20;

• All pumps and accessories and electrical controllers shall be as per

UL/FM l ists, tested, approved and certi f ied; and

• By-pass arrangements shal l to be provided (150 mm diameter nominal

bore) with NRV and gate valve and bulk f low meter on the discharge

header of each pump to check the duties of pumps.

The f ire extinguishers provided should be in conformance with Ozone

Deplet ing Substances (Regulat ion and Control) Rules.

2.11.8 Project implementation schedule

The proposed project is an expansion of the existing hospital cum medical

college building construct ion project and the total implementation /

completion period for the construction is about 48 months from the start of

the construction. To achieve a t imely completion of the project

construction the project proponent fol lowed the construction schedule of

the project.

*******************************************************************************

CHAPTER – 3

DESCRIPTION OF THE

ENVIRONMENT

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 3 Description of the Environment

Page 3 - 1

3.0 DESCRIPTION OF THE ENVIRONMENT

3.1 Introduction / Approach

The objective of Environmental Impact Assessment (EIA) is to ascertain

the baseline environmental condit ions and then assess the impacts as a

result of the present development project during operation phases of the

project cycle. Identif ication of environmental parameters, data collection

and impacts prediction form the core of Environmental Assessment

process. The baseline information is required to know the current

environment condit ion in relation with (a) land (b) air (c) noise (d) water

(e) biological (f) Socio-economic (g) solid waste and (h) traff ic

management from the site where existing project is established.

3.2 Study Area , Period, Components

3.2.1 Study Area

As specif ically mentioned in EIA Noti f ication and as wel l as on the basis

of "Environmental Impact Assessment Guidance Manual for Building,

construction, township and Area Development Projects" published by

Ministry of Environment & Forests, February, 2010, for carrying out an

EIA study of a bui lding construct ion project, the project area is called as

"core zone" and 10 km radius from the boundary l imits of the project area

is called as "buffer zone". The study area includes the "core zone" and

"buffer zone".

The project site is within the Panchayat l imits of Edappal Grama

Panchayat and is about 2 km away from Edappal Town.

3.2.2 Study period

The study period was November & December, 2018 which is other than

the monsoon season. The samples were collected and analysed for

various parameters through an National Accredited Board for Laboratories

(NABL), accredited laboratory and also by the ecological & social experts

approved by QCI/NABET.

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 3 Description of the Environment

Page 3 - 2

3.2.3 Components of Study

The environmental baseline study includes inventory of physical,

ecological and socio-economic parameters. The data has been compiled

for the following :

• Air Environment: air qual ity with respect to signif icant parameters,

• Noise Environment: noise levels covering resident ial , commercial,

industrial and sensit ive zones,

• Land Environment: land use / land cover, topography, drainage

pattern, geology and soil characterist ics,

• Water Environment: water consumption and sources, ground water,

surface water, characterist ics.

• Ecological Environment: ident if ication and enumeration of f lora &

fauna (terrestr ial and aquatic) and analysis of its importances to the

habitat of the study area.

• Socio-Economic Environment: demography, amenities, infrastructural

faci l it ies, employment and income, public health, including the support

the area could provide to the proposed project.

3.2.4 Sampling, Frequency & Method of Baseline Environment Monitoring

The Environmental attributes of the baseline monitoring is provided in

table 3.1.

Table 3.1 - Environmental Attributes

Attributes Sampling Measurement

Method

A. Air Environment Network Frequency

Meteorological � Temperature � Rainfal l � Wind (velocity &

direction)

Based on the IMD data of

Thiruvananthapuram (Secondary data)

Once

Pollutants � PM1 0

� PM2 .5

� SO2

� NO2

� CO

� One in project site

� One in upwind direction

� Two in downwind direction

� One in sensit ive receptors

24 hourly Twice a

week

As per CPCB guidelines

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 3 Description of the Environment

Page 3 - 3

B. Noise � Hourly equivalent noise

levels

� One in project site

� One in upwind direction

� Two in downwind direction

� One in sensit ive receptors

Once in month for

each location

Noise level meter

C. Water

Parameters for water quality (Ground water) � pH � Total Dissolved Solids � Total Hardness (as

CaCO3) � Chloride (as Cl) � Total Suspended Solids � Lead (as Pb) � Fluoride (as F) � Total Coliform Bacteria � E Coli Parameters for water quality (Surface water) � pH � Chemical Oxygen

Demand � Biochemical Oxygen

Demand (3 days at 270C) � Dissolved Oxygen � Total Coliform Bacteria � E Coli

Set of grab samples for ground

(Bore well ) and surface water (Ayarichira)

Once in season for

each location

Samples for water quality is collected

and analysed as per IS:

10500

D. Land Environment

Soil � pH � Conductivity � Total Kjeldahl Nitrogen

(as N) � Available Potassium � Total Phosphorous (as P)

Sample collected for core zone

One in season

Collected and analysed as

per soil analysis

reference

E. Ecological Environment � Flora Fauna Enumeration

and Biodiversity

Within the core zone

One season

F. Socio-economic Environment � Socio-economic survey, � Need assessment survey

Within the buffer zone.

One season

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 3 Description of the Environment

Page 3 - 4

3.3 Mateorological parameters :

3.3.1 Temperature

The cl imate is generally hot and humid. March and Apri l months are the

hottest and January and February months are the coldest. The maximum

temperatures ranges from 28.9 to 36.2°C and the minimum temperatures

range from 17.0 to 23.4°C. The temperature starts r ising from January

and reaches the peak in the month of March and Apri l and then decreases

during the monsoon month and again rising from September onwards.

3.3.2 Rainfall

The distr ict has more or less the same climatic condit ions prevalent

elsewhere in the State viz. dry season from December to February and

hot season from March to May, the South-West monsoon from June to

September and the North-East monsoon from October to December. The

normal rainfal l of the district is 2793.3 mm. Out of this, major rainfal l

contr ibution is from SW monsoon fol lowed by the NE monsoon. The South

West monsoon is usually very heavy and nearly 73.5% of the rainfall is

received during this season. NE monsoon contr ibutes nearly 16.4% and

March to May summer rain contributes nearly 9.9% and the balance 0.2%

is accounted for during January and February months.

3.3.3 Humidity

The relative humidity ranges from 84 to 94 % during morning hours. The

humidity is more during the peak monsoon months from June to

September.

3.3.4 Wind

The wind is predominant from east as well as west during morning and

evening hours. The wind speed is more during December to February

months. It ranges from 2.9 to 7.2 km per hour.

(Source & vintage : Ground Water Information Booklet, Malappuram District, 2013) (for temperature, rainfall & wind data)

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 3 Description of the Environment

Page 3 - 5

3.3.4.1 Wind Rose Diagram

The wind rose diagram was prepared to analysed the predominent wind

direction at the project site. The wind rose diagram was prepared during

the period of November 1 to November 30, 2018. The wind rose diagram

is provided as Figure 3.1. The frequency distribution of Wind Speeds and

Wind Direct ions is provided at Table 3.2.

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 3 Description of the Environment

Page 3 - 6

Figure 3.1 : Wind Rose Diagram of the project site

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 3 Description of the Environment

Page 3 - 7

Table 3.2 - Frequency Distribution of Wind Speeds and Wind Directions

SN Wind Directions 0 - 5 5 - 10 10 - 15 >= 15 Total (%)

1 N 0.97 3.62 2.36 0.42 7.37

2 NNE 0.56 2.36 3.62 0.00 6.54

3 NE 0.14 1.67 0.97 0.00 2.78

4 ENE 0.00 1.53 0.70 0.00 2.23

5 E 0.00 1.11 0.00 0.00 1.11

6 ESE 0.14 0.83 0.00 0.00 0.97

7 SE 0.28 1.95 0.56 0.00 2.78

8 SSE 0.70 5.56 1.81 0.70 8.76

9 S 1.11 6.26 4.31 3.48 15.16

10 SSW 0.70 7.09 2.09 2.92 12.80

11 SW 0.28 4.45 2.64 1.67 9.04

12 WSW 0.70 4.45 0.97 1.25 7.37

13 W 0.56 4.73 0.83 0.97 7.09

14 WNW 0.14 4.45 1.11 0.97 6.68

15 NW 0.14 3.34 0.97 0.28 4.73

16 NNW 0.42 2.78 1.11 0.28 4.59

Sub-Total 6.82 56.19 24.06 12.93 100.00

Monitoring period: November 1 to November 30, 2018

3.3.4.2 Inference

As per the wind rose diagram, the pre-dominent wind direct ion is from

south direct ion.

3.4 Air Environment

3.4.1 Introduction

The exist ing ambient air quali ty of the project area is very important for

evaluating the impact of the construct ion act ivit ies on air environment.

3.4.2 Selection and number of sampling locations for Ambient Air Quality monitoring as per CPCB norms :

As per CPCB Guidelines for Ambient Air Qual ity Monitor ing for sett ing up

of any ambient air qual ity monitor ing station, the most important thing to

be considered prior to the commencement of actual monitoring is to

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 3 Description of the Environment

Page 3 - 8

collect background information about sources of Emissions and

Meteorological condit ions of the study area.

Number of monitoring stations : The number of monitoring stat ions is

selected based on the background information collected on sources and

emissions, populat ion f igures which can be used as indicators of region

variabil ity of the pollutants concentrat ion as given in CPCB guidelines.

Selection of locations for ambient air quality monitoring

The study of baseline status of air environment includes reconnaissance,

select ion of monitoring locat ions was considered based on meteriological

condit ions, as per the elevation / topographic profi le as well as nearest

IMD station. The wind rose was drawn for the select ion of monitoiring

location considering the meteorological station covering the study area.

The monitoring and concentrat ion levels of specif ic air quality parameters

were carried out to assess the status of existing ambient air quality in the

study area.

Sampling locations were selected, one in the project site, one in upwind

direction, two in downwind direct ions, one in sensit ive receptor.

The Ambient Air Quality monitoring locat ions are l isted in Table 3.3 and the

map showing the locat ions is provided Figure 3.2.

For ambient air quali ty monitoring, the services of M/s Standard

Laboratory, Kochi (a NABL accredited laboratory) was taken.

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 3 Description of the Environment

Page 3 - 9

Table 3.3 : Ambient Air Monitoring Locations

Sr. No.

Location Station Code

Distance & Direction from the

project site

Zone (core / buffer)

Remarks

1. Project Site AAQ1 ---- Core Within the site

2. Near Vallyad Mosque

AAQ2 2 km (SW) Buffer Sensit ive receptor

3. Near Kololamba Rural Co-operat ive Society

AAQ 3 1.5 km (SW) Buffer Upwind direction

4. Near Amana Mall, Edappal

AAQ 4 2 km (N) Buffer Downwind direction

5. Near Badar Mosque, Nel liserry

AAQ 5 2.5 km (NE) Buffer Downwind direction

Figure 3.2 - Location map of Ambient Air Quality Monitoring Station

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 3 Description of the Environment

Page 3 - 10

Sampling methodology followed for Ambient Air Quality monitoring as per CPCB norms :

1. Ambient air quali ty sampl ing was done as per CPCB / NABL

guidelines.

2. High volume sampler Inlet height was kept minimum 3 mtr above

ground level.

3. Sampler was kept suff icient ly away from any obstructions l ike building

or trees etc.

4. Sampl ing f low rate of about 1.1 cu m/min. is maintained.

5. Init ial and f inal weight of two f i lter papers are included in the report.

6. Field data collected was reported in the attached data sheet along with

monitoring report.

7. Field sampling dates were informed well in advance to depute experts

at site during the f ield sampling / measurement.

8. Hourly reading of f low rate & rota meter % was taken during the

sampl ing.

9. Laboratory analysis of the sample was done as per the CPCB / NABL

guidelines with the properly cal ibrated instruments only and calibrat ion

chart was provided for the instruments used.

10. Trained & competent manpower with adequate numbers was provided

on site for sampling.

3.4.3 Sampling and Analysis results

The ambient air samples were collected in presence of the functional area

expert (AP) and analysed by NABL accredited laboratory, the results are

given in Table 3.4.

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 3 Description of the Environment

Page 3 - 11

Table 3.4 : Ambient Air Quality Monitoring Results

PM10 ( µg/m3 )

Monitoring stations (R,I ,S)

Category of station

Maximum Minimum

Core Zone AAQ1 67.2 59.8

Sensit ive receptor AAQ2 49.2 42.8

Upwind direct ion AAQ3 78.3 69.8

Downwind direction AAQ4 80.6 74.5

Downwind direction AAQ5 54.1 48.6

PM2 .5 ( µg/m3 )

Monitoring stations (R,I ,S)

Category of station

Maximum Minimum

Core Zone AAQ1 25.3 23.1

Sensit ive receptor AAQ2 21.3 19.8

Upwind direct ion AAQ3 41.9 38.7

Downwind direction AAQ4 43.5 40.6

Downwind direction AAQ5 23.6 20.6 SO2 ( µg/m3 )

Monitoring stations (R,I ,S)

Category of station

Maximum Minimum

Core Zone AAQ1 <2.00 <2.00

Sensit ive receptor AAQ2 <2.00 <2.00

Upwind direct ion AAQ3 <2.00 <2.00

Downwind direction AAQ4 <2.00 <2.00

Downwind direction AAQ5 <2.00 <2.00 NO2 ( µg/m3 )

Monitoring stations (R,I ,S)

Category of station

Maximum Minimum

Core Zone AAQ1 4.26 2.80

Sensit ive receptor AAQ2 3.2 2.16

Upwind direct ion AAQ3 3.57 2.67

Downwind direction AAQ4 4.91 3.27

Downwind direction AAQ5 5.14 3.14

CO ( mg/m3 )

Monitoring stations (R,I ,S)

Category of station

Maximum Minimum

Core Zone AAQ1 2.63 1.49

Sensit ive receptor AAQ2 2.75 1.49

Upwind direct ion AAQ3 3.12 2.64

Downwind direction AAQ4 3.96 2.15

Downwind direction AAQ5 2.40 1.83

*R : Residential area *I : Industrial Area *S : Senstive area

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 3 Description of the Environment

Page 3 - 12

The analysis reports of all ambient air quality stations is provided at

Annexure No. 3.1.

Table 3.5 : National Ambient Air Quality Standards

Parameters Standards

PM1 0 100 µg/m3

PM2 .5 60 µg/m3

SO2 80 µg/m3

NO2 80 µg/m3

CO 4 mg/m3 3.4.4 Ambient Air Quality Index

The baseline ambient air quality results & air quality index is givne at

Table 3.6 .

Table 3.6 - Baseline ambient air quality results & air quality index

Pollutant Value (µg/m3)

Permissible Limits

(µg/m3)

Air Quali ty Index

PM10 80.6 100 Good

PM2 .5 43.5 60 Good

SO2 <2.00 80 Good

NO2 5.14 80 Good

CO 3.96 4 Good

3.4.5 Inference

All the analyzed values of all parameters are well within the National

Ambient Air Quality Standards.

3.5 Noise Environment

3.5.1 Introduction

The noise level monitoring in the study area is carried out at sensit ive

receptors l ike mosque, Cooperat ive Society off ice, Shopping mall within 1

to 2.5 km area. The monitor ing is done on hourly equivalent noise levels

in the study area. The sound level monitor ing data is presented below.

3.5.2 Protocols followed for Ambient Noise Level Monitoring & methodology

1. The microphone of instrument was kept clean & free from any dust.

2. The equipment used was properly calibrated and calibration status of

equipment to be used for monitoring.

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 3 Description of the Environment

Page 3 - 13

3. The CPCB methodology was used for monitoring.

4. Only Type-II noise level monitor ing instrument (Sound level meter) was

used for monitor ing.

5. The laboratory personnel were competent to carryout spot calibrat ion.

6. The f ield sampling dates were informed well in advance to depute

experts at site during the f ield measurement.

7. Trained & competent manpower with adequate numbers were provided

on site for f ield measurement.

The Ambient Noise level locations are listed in Table 3.7 and the map

showing the locat ions is provided Figure 3.3.

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 3 Description of the Environment

Page 3 - 14

Table 3.7 : Ambient Noise Monitoring Locations

Sr. No.

Location Station Code

Distance & Direction from the

project site

Zone (core / buffer)

Remarks

1. Project Site N1 ---- Core Within the site

2. Near Vallyad Mosque

N2 2 km (SW) Buffer Sensit ive receptor

3. Near Kololamba Rural Co-operat ive Society

N3 1.5 km (SW) Buffer Upwind direction

4. Near Amana Mall, Edappal

N4 2 km (N) Buffer Downwind direction

5. Near Badar Mosque, Nel liserry

N5 2.5 km (NE) Buffer Downwind direction

Figure 3.3 - Location of Ambient Noise Level Monitoring Stations

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 3 Description of the Environment

Page 3 - 15

3.5.3 Ambient Noise levels results

The ambient Noise level samples were collected in presence of the

funct ional area experts (noise) and analysed by NABL accredited

laboratory, the results are given in Table 3.8.

Table 3.8 : Ambient Noise Monitoring Results

S. N.

Location Environmental

Setting*

Day time Average

noise level (dBA)

Night time Average

noise level (dBA)

1. Project Site Project site (core zone)

50.1 37.7

2. Near Vallyad Mosque Buffer area 49.1 38.0

3. Near Kololamba Rural Co-operative Society

Buffer area 48.7 36.9

4. Near Amana Mall, Edappal

Buffer area 50.4 38.6

5. Near Badar Mosque, Nelliserry

Buffer area 49.3 37.9

*Industrial Area / Commercial Area / Residential area / Silence Zone

The analysis report of all ambient noise level stat ions is provided at

Annexure No. 3.2.

Table 3.9 : National Ambient Noise Level Standards

Area Code

Category of Area Limits in dB (A) Leq

Day time Night Time

A Industr ial Area 75 70

B Commercial Area 65 55

C Resident ial area 55 45

D Silence Zone 50 40

3.5.4 Inference

The analyzed results of Noise levels are given in the above table, and it

can be observed from the results that the noise values are much below

the prescribed l imits for Industrial, Commercial, Resident ial, and Silence

zone. Proposed project are not l ikely to cause any increase in 'noise'

levels at the monitoring locat ions (sensit ive receptors) which are located

more than a ki lometer away from the project s ite.

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 3 Description of the Environment

Page 3 - 16

3.6 Land Environment

3.6.1 Introduction

Since the building construction project have excavation of earth, removal

of top soi l and disturbance of land result in the land environment wil l

af fected.

3.6.2 Land use / land cover

The exist ing land use / land cover pattern in the study area for a 10 km

radius from the project site is developed and is provided at Figure 3.4 and

Table 3.10.

Table 3.10 - Land Use / Land Cover Classification System

Land Use Class Area (in Sq km)

Wetland 5.49

Plantation 198.9818

Reservoir/Lakes/Ponds 0.0628

River/Stream / Canals 22.2312

Rural Area 1.691

Sandy Area 3.3598

Scrub land 3.9564

Urban 4.02

Cropland 74.575

Fallow land 0.2512

3.6.2.1 Interpretation

As per the Land Use / Land Cover Classif icat ion System, the exist ing land

use within the buffer zone is about 63% of the land is Plantation area,

about 7% land is River/Stream / Canal and about 24% of the land is Crop

land and remaining land is covered with other land use / land cover. The

soil in core area is not good in nutrients values and not productive from

agriculture view point.

Proposed project is an expansion of exist ing hospital cum medical col lege

project and new buildings wil l be construct ing within the exit ing plot area.

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 3 Description of the Environment

Page 3 - 17

Therefore, the land use / land cover of study area is not l ikely to get

affected adversely due to proposed project.

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 3 Description of the Environment

Page 3 - 18

Figure 3.4 - Land use map of the project site (2004-05) (10 km. radius)

Source :- Thematic Map from Bhuvan Indian Geo-Platform of ISRO, Govt. of India

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 3 Description of the Environment

Page 3 - 19

3.6.3 Soil

3.6.3.1 Introduction

Since the building construction project have excavation of earth, removal

of top soil and disturbance of nutr ients of the soi l result in the soil quality

wi ll af fected.

3.6.3.2 Protocols for Soil sampling methodology

The soil sample is collected from the core zone since the project is not

l ikely to affect the land use outside core zone. Samples are col lected

through hand auger boring upto a depth of 15 to 30 cm.

The locat ion of soi l sampling points are presented in Table 3.11.

Table 3.11 - Soil Sampling Locations

Station

no.

Location Distance & Direction

from project area

Project area /

Study area

1. Within the project

area

Within the project area Project area

(Core Zone)

3.6.3.3 Soil sampling results

The soil sample was collected in presence of the functional area experts

and analysed by NABL accredited laboratory, twice during November,

2018 the results are given in Table 3.12.

Table 3.12 - Chemical Properties of Soil Sample

Sr.

No. Parameters Unit

Samples

Core Zone

1. pH -- 6.18

2. Conductivity µS/cm 36.0

3. Total Kjeldahl Nitrogen (as N) % 0.16

4. Available Potassium % 0.09

5. Total Phosphorous (as P) % 0.22

The analysis report of soil sampling stat ion is provided at

Annexure No. 3.3.

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 3 Description of the Environment

Page 3 - 20

3.6.3.4 Interpretation

The soil in core area is not good in nutrients values and not productive

from agriculture view point.

3.7 Water Environment

3.7.1 Introduction

For the purposes of construction of building and associated act ivit ies are

required huge quantity of water for various purposes and also affect the

hydrological regime of the area. The water quality of the region is also

likely to get affected through runoff and leachate. Therefore, baseline

information on ground and surface water regime is very important. Water

availabil ity and water qual ity are the two major aspects to be considered

for baseline status of water environment.

3.7.2 Water consumption and sources

The specif ic water consumption for various purposes is worked out and is

given in table 3.13.

Table 3.13 - Water consumption details for various purposes

S. N.

Particulars

Daily Requirement

(in KL) Sources of water

1. Domestic Water Requirement

( Non-Flushing purposes ) 647

Fresh water (Stored Rain

water and Ground water)

2. Domestic Water Requirement

( Flushing purposes ) 223 Recycled water from STP

3. Hort iculture Water Requirement 55 Recycled water from STP

4. Boiler water requirement 20 Recycled water from STP

4.

Make-up Water Requirement for

Cooling Towers attached with

air condit ioning system

353 Recycled water from

STP/ETP

5. Laboratory & Laundry

requirement 30

Fresh water (Stored Rain

water and Ground water)

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 3 Description of the Environment

Page 3 - 21

3.7.3 Ground Water

3.7.3.1 Ground water table identification

The pre-construction soil invest igat ion has been carr ied out (M/s

Associated Bore Tech, Ernakulam) during November, December, 2013 at

the site. The soil investigat ion report is attached at Annexure No. 3.4. I t

is observed that the ground water level is encountered about 1 m from the

exist ing ground level.

As per the Ground Water information Booklet, CGWB on the stage of

ground water development and the long term trend of water levels, 3

blocks namely Kondotty, Tirurangadi and Vengara have been categorized

as ‘Semi-Crit ical ’ and the remaining blocks are categorized as ‘Safe ’ . The

proposed project area is located within the Ponnani block which is

categorized as 'Safe' zone.

The categorizat ion of blocks of Malappuram district is provided in Figure 3.5.

Figure 3.5 - Categorizationof blocks of Malappuram distr ict

(Source : Ground Water information Booklet, CGWB) (Vintage : Dec., 2013)

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 3 Description of the Environment

Page 3 - 22

3.7.3.2 Interpretation

As per the Ground Water information Booklet, CGWB, the proposed

project is categorized as 'Safe' zone and hence the ground water

available in the region is ensure and to use of domestic purposes.

3.7.3.3 Protocols for Water sampling methodology

Sampling Methodolgy:

• Sampling of water was done as per CPCB/NABL guidel ines.

• CPCB guidel ines followed for locat ion identif icat ion

The guidelines / protocols fol lowed in the water sample collection,

preservation & transporation is discussed below :-

Surface Water Sampling

• Ensuring the water samples collected from well-mixed section of the

water body 30 cm. below the water surface using a water sampler.

(Nishkin type).

• DO is determined in a sample collected in a DO bott le. The DO in the

sample was f ixed immediately after collect ion, f ixing chemical reagents.

DO concentrat ion was then determined in the laboratory.

Ground Water Sampling

• Samples for groundwater qual ity monitoring was collected from the

following types of wel l:

� Open dug wel l

• The open dug well, which is in use in the site considered as water

quality monitoring station.

• The weighted sample bott le was used to collect sample from an open

well about 30 cm below the surface of the water.

• For bacteriological samples, when collected from tube-wells/hand

pump, the spout/outlet of the pump was steri l ized under f lame by spir it

lamp before collect ion of sample in container.

Sample Labelling Guidelines:-

The label of the sample container was properly, preferably attached

with a water-proof label. Information on the sample container includes:

• Sample code number ( identifying locat ion)

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 3 Description of the Environment

Page 3 - 23

• Date and time of sampling

• Source and type of sample

• Pre-treatment or preservat ion carried out on the sample

• Any special notes for the analyst

• Sampler’s name

Sample Preservation and Transport

• The samples collected for BOD and bacteriological analyses should be

stored at a temperature below 4oC and in the dark as soon as possible

after sampling. In the f ield this usually means placing them in an

insulated cool box together with ice or cold packs.

• Once the samples were collected and brought to the laboratory,

samples were transferred to a refrigerator. Samples collected for

chemical oxygen demand (COD) analysis were analyzed on the day of

collection, after preserving below pH2 by addit ion of concentrated

sulphuric acid.

• The samples which were to be analyzed for the presence of metals,

were acidif ied to below pH2 with concentrated nitr ic acid.

• The samples were transported to concened laboratory as soonas

possible, preferably within 48 hours.

• The analysis of bacteriological samples were analysed within 24 hours

of col lection.

The water sampling locat ions (ground water & surface water) are listed in

Table 3.14 & Table 3.15. The water sampling location map is given in

Figure 3.6.

Table 3.14 - Description of Ground Water Sampling Location

Station

no.

Location Distance &

Direction from

project area

Project area

/ study area

Environmental

Setting

1. Within the

project site

- Project area Bore well within

the exist ing

campus

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 3 Description of the Environment

Page 3 - 24

Table 3.15 - Description of Surface Water Sampling Location

Station

no.

Location Distance &

Direction from

project area

Project

area /

study area

Environmental

Setting

1. Ayarichira

(Water

body)

about 3 km (W) and

downstream

Study area Surface water

Figure 3.6 - Water Sampling Location Map

3.7.4 Water sampling results

The water sampling are collected from ground water (Bore well) within the

exist ing campus and surface water from Ayinichira within the study area.

The ground water analysis results are given below at table 3.16. Also, the

surface water (Ayarichira) analysis results are given below at table 3.17.

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 3 Description of the Environment

Page 3 - 25

Table 3.16 - Analysis of Ground Water (Open well) Results

Sr.

No. Parameters Unit Result Standards

1 pH -- 6.28 6.50 - 8.50

2 Total Dissolved

Solids

mg/L 872 500 (max)

3 Total Hardness (as

CaCO3)

mg/L 366 200 (max)

4 Chloride (as Cl) mg/L 426 250 (max)

5 Total Suspended

Solids

mg/L 10.60 --

6 Lead (as Pb) mg/L <0.01 0.01 (max)

7 Fluoride (as F) mg/L 0.48 1.00 (max)

8 Total Coliform

Bacteria

-- Absent/100 ml Absent/100 ml

9 E Coli -- Absent/100 ml Absent/100 ml

The analysis report of water sampling station (ground water) (bore well) is

provided at Annexure No. 3.5.

Table 3.17 - Analysis of Surface Water (Ayarichira)

Sr.

No. Parameters Unit Result

1 pH -- 6.88

2 Chemical Oxygen Demand mg/L 312

3 Biochemical Oxygen Demand

(3 days at 270 C)

mg/L 3.00

4 Dissolved Oxygen mg/L 8.13

5 Total Coliform Bacteria -- Present/100 ml

6 E col i -- Absent/100 ml

The analysis report of water sampling station (Surface water - Ayarichira)

is provided at Annexure No. 3.6.

3.7.5 Interpretation of results

Ground Water

All the parameters except pH level, i ron content, hardness, chlor ides are

within the standards as per IS:10500 (Ground Water - Bore well). It is

recommended that appropriate treatment wil l be done before its

consumption for domestic purposes.

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 3 Description of the Environment

Page 3 - 26

The present project is an expansion of existing hospital cum medical

college campus. The construction of new buildings are within the exist ing

plot area.

The excavation of earthwork wil l be done for the foundation of structures.

The total excavated of earth is 7,300 cum. The top soi l (730 cum) which is

fert i le wil l be kept at site for landscaping work. Part of the excavated soi l

wi ll be used for back f i l l ing work (4,380 cum) for site level ing and the

remaining quantity of 2190 cum will be used for internal road construct ion

work.

3.8 Ecological Environment

3.8.1 Introduction

The construction activity affects the terrestrial ecological environment.

Therefore, a primary survey on the ecological assessment of the site

(f lora and fauna) is required to be carr ied out.

3.8.2 Methodology

Flora

The study on the f loral assessment for the proposed project act ivity was

based on extensive f ield survey of the area.

The Qualitat ive Assessment was done by transect method covering the

entire area in to Grids of 90m x 90m. From the total grids, 12 grids were

selected at random and, the density, dominance and frequency were

calculated by using quadrate method. The quadrate method includes lying

down of a square sample plot of suitable size for detailed analysis of

vegetat ion. It may be a single sample plot or may be divided into several

subplots. Quadrates of 20m x 20m, 5m x5m and 1m x1m were used for

trees, shrubs and herbaceous communities respectively.

Co-existence and competit ion amongst various species are affected

directly by the number of individuals in the community. Therefore,

knowing the quantitat ive structure of the community becomes essential.

Various diversity indices including Shannon-Weaver (1963) Index of

Diversity give a comparat ive and quantitative picture of the community

exist ing in the study area.

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 3 Description of the Environment

Page 3 - 27

Fauna

Birds, Butterf l ies, Dragon Fl ies: Line Transect & Point count method

Mammals: Line Transect method, Consultat ion with local people

Amphibians: Transect and Patch Sampling

Spiders: Searching and Direct Observat ions

3.8.3 Findings

Flora

Analysis of the f lora revealed that, in the proposed project site there are

90 plant species fal l ing under 48 plant families. Angiosperms forms 86

species with 25 species of trees including saplings, 18 species of shrubs,

28 species of herbs and 15 species of cl imbers. There are four

Pteridophytes (ferns) fal l ing under three famil ies. The Site has 90 species

of plants. I t consists of:

Trees : 25 species

Tree saplings : 18 species

Shrubs : 18 species

Herbs : 28 species

Cl imbers : 15 species

Ferns : 4 species

The l ist of f loral species (trees, tree sapl ings, shrubs, herbs, cl imbers,

ferns) observed in the site area is provided at table 3.18.

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 3 Description of the Environment

Page 3 - 28

Table 3.18 - List of floral species observed in the site area (trees, tree saplings, shrubs, herbs, climbers, ferns)

List of trees

SN Botanical Name Common Name Family Habitat Distribution Nos. Status

1 Saraca asoca Ashokam Fabaceae Evergreen forests. Also

grown as ornamental. 4

2 Mimusops elengi

L.

Elenji/ Asian

bullet wood Sapotaceae

Semi evergreen and

evergreen forest, also

grown in homestead

Indo-Malaysia 3

3 Anacardium

occidentale L. Kasumavu Anacardiaceae Cultivated

Native of South America;

now widely cultivated in

Asia and Africa

6 Exotic

4 Ficus racemosa L. Aththi Moraceae

Semi-evergreen and

deciduous forests, also in

the plains

Indo-Malesia to Australia 1

5 Trema orientalis

(L.) Bl. Pottaama Ulmaceae

Dry and moist deciduous

forests, also in the plains 21

6 Ficus hispida L.f.

Erumanakku/

Parakam/

Thonditherakam

Moraceae

Moist deciduous and

semi-evergreen forests,

also in the plains

Indo-Malesia to Australia 38

7 Morinda coreia

Buch.-Ham. Manjanathi Rubiaceae

Moist and dry deciduous

forests, also in the plains 2

8 Albizia saman Mazha Leguminosae Cultivated as avenue tree Native of Central and South 2

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 3 Description of the Environment

Page 3 - 29

(Jacq.) Merr. maram/rain tree America

9 Mangifera indica

L. Mavu Anacardiaceae

Evergreen and semi-

evergreen forests and

also widely cultivated

Indo-Malaysia 40

10

Averrhoa bilimbi Irumbanpuli Oxalidaceae

Cultivated. Native of

Malaysia 2

11 Tamarindus indica

L. Valampuli Leguminosae Cultivated

Native of Tropical Africa;

introduced and widely

grown in India and other

parts of tropics

2

12 Leucaena

leucocephala Subaabul Fabaceae 2

13 Caryota urens L. Choonda/

Choondappana Arecaceae

Evergreen forests, also

in the plains Indo-Malaysia 12

14 Macaranga peltata

(Roxb.) Müll.Arg. Vatta Euphorbiaceae

Moist deciduous and

secondary forests, also in

the plains

India, Sri Lanka and

Andamans 6

15 Cassia fistula L. Kanikkonna Caesalpiniaceae

Found in deciduous

forests from plains to

1400m. often planted

along the roadsides.

Indo-Malesia 4

16 Artocarpus

hirsutus Lam. Anjili Moraceae

Semi-evergreen and

moist deciduous forests, Southern Western Ghats 2

Endemic to

Southern

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 3 Description of the Environment

Page 3 - 30

also in the plains Western

Ghats

17 Carica papaya L. Papaya Caricaceae Cultivated Native of Tropical America 8 Exotic

18 Gliricidia sepium

(Jacq.) Walp. Seemakonna Leguminosae

Cultivated in fields and

along fences

Native of South America;

introduced and widely

grown in India

85

19

Lannea

coromandelica

(Houtt.)Merr.

Uthi/ Karayam Anacardiaceae Deciduous forest, also in

the plains Indo- Malaysia and China 1

20

Acacia

auriculiformis

Benth.

Acacia Leguminosae Cultivated Native of Tropical Australia 3 Exotic

21

Artocarpus

heterophyllus

Lam.

Plavu Moraceae

Evergreen and semi-

evergreen forests, also

widely cultivated

Widely cultivated in the

tropics, origin is probably

South India

11

22 Psidium guajava

L. Pera Myrtaceae Cultivated

Originally from Tropical

America; now naturalised in

the tropics

2 Exotic

23 Coccos nucifera L. Thengu /

Coconut Arecaceae Cultivated

Cultivated throughout the

tropics

1500

aprx.

24 Terminalia

catappa L. Badam Combretaceae Plains, Cultivated

Malesia to North Australia

and Polynesia, Commonly

planted in the tropics

35

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 3 Description of the Environment

Page 3 - 31

25 Ficus religiosa L. Arayal Moraceae

Plains from the coast up

to 1200m. Often planted

around temples

1

List of tree saplings

SN

Botanical Name Common Name Family Habitat Distribution Status

1 Mimusops elengi L. Elenji/ Asian

bullet wood Sapotaceae

Semi evergreen and

evergreen forest, also

grown in homestead

Indo-Malaysia

2 Trema orientalis (L.)

Bl. Pottaama Ulmaceae

Dry and moist

deciduous forests, also

in the plains

3 Macaranga peltata

(Roxb.) Müll.Arg. Vatta Euphorbiaceae

Moist deciduous and

secondary forests, also

in the plains

India, Sri Lanka and Andamans

4 Artocarpus

heterophyllus Lam. Plavu Moraceae

Evergreen and semi-

evergreen forests, also

widely cultivated

Widely cultivated in the tropics, origin

is probably South India

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 3 Description of the Environment

Page 3 - 32

5 Ficus religiosa L. Arayal Moraceae

Plains from the coast

up to 1200m. Often

planted around temples

6 Terminalia catappa

L. Badam Combretaceae Plains, Cultivated

Malesia to North Australia and

Polynesia, Commonly planted in the

tropics

7 Anacardium

occidentale L. Kasumavu Anacardiaceae Cultivated

Native of South America; now widely

cultivated in Asia and Africa

8 Cassia fistula L. Kanikkonna Caesalpiniaceae

Found in deciduous

forests from plains to

1400m. often planted

along the roadsides.

Indo-Malesia

9 Caryota urens L. Choonda/

Choondappana Arecaceae

Evergreen forests, also

in the plains Indo-Malaysia

10

Gliricidia sepium

(Jacq.) Walp. Seemakonna Leguminosae

Cultivated in fields and

along fences

Native of South America; introduced

and widely grown in India

11 Carica papaya L. Papaya Caricaceae Cultivated Native of Tropical America

12 Mangifera indica L. Mavu Anacardiaceae

Evergreen and semi-

evergreen forests and

also widely cultivated

Indo-Malaysia

13 Albizia saman

(Jacq.) Merr.

Mazha

maram/rain tree Leguminosae

Cultivated as avenue

tree Native of Central and South America

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 3 Description of the Environment

Page 3 - 33

14 Alstonia scholaris

(L.) R. Br.

Ezhilampala/

Devil Tree Apocynaceae

Moist deciduous

forests and sacred

groves, also in the

plains

South and South East Asia to

Australia

15 Acacia auriculiformis

Benth. Acacia Leguminosae Cultivated Native of Tropical Australia Exotic

16 Ficus hispida L.f.

Erumanakku/

Parakam/

Thonditherakam

Moraceae

Moist deciduous and

semi-evergreen

forests, also in the

plains

Indo-Malesia to Australia

17 Artocarpus hirsutus

Lam. Anjili Moraceae

Semi-evergreen and

moist deciduous

forests, also in the

plains

Southern Western Ghats

Endemic to

Southern

Western

Ghats

18 Psidium guajava L. Pera Myrtaceae Cultivated Originally from Tropical America;

now naturalised in the tropics

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 3 Description of the Environment

Page 3 - 34

List of Shrubs

Sl.

No Botanical Name Common Name Family Habitat Distribution Status

1 Pandanus odorifer

(Forssk.) Kuntze.

Pookaitha/

Thazhambu/Thala Pandanaceae Mangrove forests and sea coasts

Tropical and subtropical

Asia

2 Solanum torvum Sw. Anachunda Solanaceae

Found along the roads and

wastelands from plains to 700m.

Sometimes cultivated in kitchen

gardens.

Throughout the tropics

3 Lantana camara L. Kongini Verbenaceae Most aggresive weed of disturbed

ground from plains to the hills.

Native of tropical

America, widely

naturalised in tropics

and subtropics.

Exotic/

Invasive

Species

4 Ziziphus oenoplia Thudaly Rhamnaceae It grows along roadside forests and

thickets

Tropical and subtropical

Asia and Australasia.

5 Brineya retusa Aattacherukola, Phyllanthaceae Dry Evergreen to Dry Deciduous

Forests Sri Lanka to Indo-China

6 Bambusa bambos (L.)

Voss. Mula Poaceae

Deciduous forests, also grown in

homesteads India and Sri Lanka

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 3 Description of the Environment

Page 3 - 35

7 Ziziphus rugosa Lam. Kottamullu Rhamnaceae

Common on exposed and dry

slopes and forest edges from 900-

1500m. Peninsular India.

India, Sri Lanka,

Bangladesh and

Myanmar

8 Ixora coccinea L. Thechi/ Chethi Rubiaceae In the plains, also grown in

homesteads

Peninsular India and Sri

Lanka

9 Melastoma

malabathricum L. Athirani Melastomataceae Stream banks and marshy areas South East Asia

10 Clerodendrum

infortunatum L. Perivelam Verbenaceae

Degraded forest areas and also in

the plains Indo-Malesia Exotic

11 Sida rhombifolia L. Kurunthotti Malvaceae Wastelands, also in degraded

forest areas Pantropical

12

Chromolaena odorata

(L.) R.M.King &

H.Rob.

Communist-pacha Compositae A weed in all terrestrial habitats

Native of America;

naturalised in Tropical

Asia

Exotic/

Invasive

Species

13 Urena lobata L. Uram Malvaceae Moist deciduous forests and in the

plains Pantropical

14 Hibiscus hispidissimus

Griff. Matthippuli Malvaceae

Dry and moist deciduous forests,

also in the plains Paleotropics

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 3 Description of the Environment

Page 3 - 36

15 Sauropus andogynus

(L.) Merr. Velicheera Euphorbiaceae

Evergreen and semievergreen forest

and also grown in homesteads Indo-Malesia

16 Calotropis gigantea

(L.) R. Br. Erikku Asclepiadaceae Wastelands Tropical Asia

17 Clerodendrum

paniculatum L.

Krishnakireedam/Ha

numankireedam Lamiaceae Cultivated/Naturalized

Native of Malaysian

Region

18 Mussaenda frondosa L. Vellila Rubiaceae Moist deciduous and semi-

evergreen forests, also in the plains Peninsular India

List of Herbs

SN Botanical Name Common Name Family Habitat Distribution Status

1 Dactyloctenium aegyptium

(L.) Willd. Kakkakalan pullu Poaceae Marshy lands and open areas

Native of South

America, naturalised in

Paleotropics

2 Elephantopus scaber L. Aanachuvadi Compositae Moist deciduous forests, also in

the plains Pantropical

3 Axonopus compressus

(Sw.) P.Beauv.

Kaalappullu/

Carpet Grass Poaceae

Dry and moist deciduous forests,

waste lands and paddy fields Tropics and subtropics

4 Acmella paniculata (Wall.

ex DC.) R.K.Jansen Compositae

Frequently found in boggy

ground, margins of ponds,

Indo-Malesia, America

and New Guinea

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 3 Description of the Environment

Page 3 - 37

marshes, along water courses

and in rice fields.

5 Sida acuta Burm.f. Kurunthotti Malvaceae Dry and moist deciduous forests,

also in the plains Pantropical

6 Colocasia esculenta (L.)

Schott Chembu Araceae

Waterlogged ditches and

streamside Pantropical

Invasive

Species

7 Pennisetum orientale Rich. Poaceae Cultivated as fodder grass, often

found running wild

Central Asia and North

Africa

8 Centella asiatica (L.) Urb. Kodangal Apiaceae Deciduous forests, also in wet

places in the plains Tropical Asia and Africa Medicinal

9 Euphorbia hirta L. Nilappaala Euphorbiaceae Degraded forest areas and forest

plantations, also in the plains Pantropical.

10 Boerhavia diffusa L. Thazhuthama Nyctaginaceae

Found by the waysides,

wastelands, river banks and

hedges

Pantropical

11 Brachiaria ramosa (L.)

Stapf Chamapothaval Gramineae

Grasslands and moist deciduous

forests, roadsides and

wastelands

Africa and Tropical Asia

12 Musa paradisiaca L. Vazha Musaceae Cultivated Cultivated throughout

the tropics

13 Mimosa pudica L. Thottavadi Leguminosae Common on moist and ungrazed

places. Near riverbanks, bunds

Native of South

America, now Exotic

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 3 Description of the Environment

Page 3 - 38

of arable lands, fallow lands and

water courses.

pantropical.

14 Alternanthera sessilis (L.)

R.Br. Kozhuppa Amaranthaceae

Along sides of water courses &

marshy areas Pantropical

15 Scoparia dulcis L. Kallurukki Plantaginaceae Wasteplaces

Native of Tropical

America; now

Pantropical

Exotic

16 Ruellia prostrata Poir Irula Acanthaceae Found in the disturbed areas,

foot paths and agricultural lands India

17 Ageratum conyzoides L. Appa Compositae

Most abundant weed of

disturbed ground and fallows,

damp places and forest

undergrowth.

Pantropical Invasive

Species

18 Tragia involucrata Choriyanam Euphorbiaceae Wastelands India and Sri Lanka

19 Kyllinga nemoralis

(J.R.Forst. & G.Forst.)

Vallimuthanga/

Whitehead

spikesedge

Cyperaceae Waste places, degraded forest

areas and grasslands Pantropical

20 Phyllanthus amarus

Schum. & Thonn.

Keezharnelli/Phyll

anthus Phyllanthaceae

Degraded moist deciduous,

forest plantations and also in

plains

Tropics Medicinal

21 Peperomia pellucida (L.)

Kunth. Mashitandu Chedi Piperaceae

Degraded forest areas and

wastelands

Native of Tropical

America; now Exotic

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 3 Description of the Environment

Page 3 - 39

Pantropical

22 Tridax procumbens L. Odiyancheera Asteraceae Deciduous forests, also waste

lands in the plains

Native of Tropical

America; now

widespread throughout

tropics and subtropics

Exotic

23 Emilia sonchifolia (L.) DC. Muyalchevian compositae Dry and moist deciduous forests,

also in the plains

Tropical and Subtropical

Africa and Asia Exotic

24 Pilea microphylla (L.) Liebm. Gunpowder

Plant/Rockweed Urticaceae

Grown as garden plant, often

found as an escape

South America; now

introduced into other

tropical regions

Exotic

25 Desmodium triflorum Cherupalladi Fabaceae Grasslands and moist deciduous

forests, also in plains

Indo-Malesia and

Australia

26 Cleome rutidosperma DC. Neelavela Cleomaceae In coastal areas Pantropical

27 Synedrella nodiflora (L.)

Gaertn. Mudianpacha Compositae

Deciduous forests, also in the

plains

Native of West Indies;

naturalised in India,

China, Malesia and

Polynesia

Invasive

Species

28 Vernonia cinerea (L.) Less. Puvankurunal Compositae Deciduous forests, also in the

plains Pantropics Exotic

List of Climbers

SN Botanical Name Common Name Family Habitat Distribution Status

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 3 Description of the Environment

Page 3 - 40

1 Centrosema pubescens

Benth. Kattupayar Leguminosae

Forest plantations and

Deciduous forests, also in the

plains

Native of America;

introduced in India

2 Wattakaka volubilis (L.f.)

Stapf. Vattakakkakkoti Aslepiadaceae

Moist deciduous forests and

scrub jungles Indo-Malesia and China

3 Cyclea peltata (Lam.)

Hook. f. & Thoms. Padathali Menispermaceae

Semi-evergreen and

evergreen forests, also in the

plains

India and Sri Lanka

4 Ipomoea cairica (L.)

Sweet. Kolambipoo Convolvulaceae

Moist & Dry deciduous forests,

also in the plains Paleotropics

5 Calycopteris floribunda

(Roxb.) Lam. ex Poir. Pullani Combretaceae

Moist deciduous forest, also in

the plains Indo-Malesia

6 Cucurbita maxima

Duchesne. Mathan Cucurbitaceae Cultivated as vegetable

Cosmopolitan, mostly

cultivated

7 Mukia maderaspatana (L.)

M.Roem. Kasappuchedi Cucurbitaceae

Deciduous forests, also in the

plains Paleotropics

8 Passiflora foetida L. Poodapazham Passifloraceae

Very common along roadsides,

thickets and water courses

from plains

Native of tropical

America, now widely

naturalized the tropics

Exotic

9 Dendrophthoe falcata (L.f.)

Ettingsh. Ittikkanni Loranthaceae

Found in foothill scrub jungles

and deciduous forests from

plains to 1000m.

India, Sri Lanka,

Thailand, Indo-China and

Australia.

10 Merremia vitifolia (Burm. f.) Manja kolambi Convolvulaceae Degraded forest areas and Indo-China and China Invasive

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 3 Description of the Environment

Page 3 - 41

Hallier f. valli also in the plains species

11 Ichnocarpus frutescens (L.)

R.Br. Palvalli Apocynaceae

Moist and dry deciduous

forests, also in the plains

Indo-Malesia and

Australia

12 Pothos scandens L. Paruvakodi Araceae Evergreen forests, waste

places and sacred groves

India to Malesia and

Madagascar

13 Tylophora indica (Burm.f.)

Merr. Vallippala Asclepiadaceae

Common along the wayside

thickets, scrub jungles and

wastelands

India to South east Asia,

Sri Lanka, Malaysia

14 Mikania micrantha Kunth Vayara Compositae

Common along foothills, lower

slopes, scrub jungles even in

poor soils, on bare exposed

slopes.

Tropical and subtropical

regions of the world. Invasive

15 Asparagus racemosus

Willd. Sathavari Liliaceae

All forest types, also in the

plains Paleotropics

List of Ferns

SN Botanical Name Common Name Family Habitat Distribution

1 Drynaria quercifolia (L.) J.

Sm.

Basket fern,

Oak-leaf fern Polypodiaceae

Basket ferns are grown on trees or grown

on rocks. They can also sometimes be

found in man-made structures like brick

walls. They are found in wet tropical

environments.

Native to tropical Africa,

South Asia, East Asia,

Southeast Asia, Australia,

and Oceania

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 3 Description of the Environment

Page 3 - 42

2 Pityrogramma calomelanos

(L.) Link Silver fern Adiantaceae

Common on open ground in fairly exposed

places

American origin,now widely

distributed in pan-tropics

3 Selaginella delicatula Selaginellaceae Terrestrial in shaded areas Widely cultivated

4 Adiantum latifolium Lam. Adiantaceae Disturbed open areas. Native to tropical America

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 3 Description of the Environment

Page 3 - 43

Fauna

The fol lowing l ists of faunal elements were observed from the site:

Birds : 26 species

Mammals : 10 species

Butterf l ies : 24 species

Odonates : 12 species

Amphibians : 6 species

Repti les : 10 species

Spiders : 11 species

Ants : 6 species

The l ist of faunal species (mammals, rept i les, birds, Amphibian,

Odonates, Butterf l ies, Mil l ipedes and Centipedes, Ants, Spiders) observed

in the site area in table 3.19.

Table 3.19 - List of faunal species observed in the site area (mammals, reptiles, birds, Amphibian, Odonates, Butterflies,

Millipedes and Centipedes, Ants, Spiders)

List of Mammals (In and around the project site)

SN Common Name Scientific Name IUCN Status IW(P)A (Schedule)

1 Indian Hare Lepus nigricollis Least Concern

2 Lesser Woolly Horseshoe Bat Rhinolophus beddomei Least Concern

3 Common House Rat Rattus rattus Least Concern V

4 House Mouse Mus musculus Least Concern V

5 Indian Flying Fox Pteropus giganteus Least Concern V

6 Indian Grey Mongoose Herpestes edwardsii Least Concern III

7 Pig Rat Bandicota indica Least Concern V

8 Three striped Palm Squirrel Funambulus palmarum Least Concern V

9 Palm civet/Toddy Cat Paradoxurus hermaphroditus

Least Concern II

10 Greater Short-nosed Fruit Bat Cynopterus sphinx Least Concern V

* IW(P)A -The Indian Wildlife (Protection) Act, 1972.

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 3 Description of the Environment

Page 3 - 44

List of Reptiles

SN Scientific Name Common Name IUCN Status

1 Xenochrophis piscator Checkered Keel-back Least Concern

2 Bungarus caeruleus Common Krait Least Concern

3 Calotes versicolor Oriental Garden Lizard Least Concern

4 Eutropis carinata Keeled Indian Mabuya Least Concern

5 Naja naja Indian Cobra Least Concern

6 Hemidactylus mabouia House gecko Least Concern

7 Daboia russelii Russell's viper Least Concern

8 Dendrelaphis tristis Common Bronzeback Tree Snake Least Concern

9 Lycodon aulicus Common Wolf Snake Least Concern

10 Ptyas mucosa Oriental Rat Snake Least Concern

List of Birds

SN Scientific Name Common Name IUCN Status

1 Casmerodius albus Large Egret Least Concern

2 Alcedo atthis Small Blue Kingfisher Least Concern

3 Psittacula krameri Rose ringed parakeet Least Concern

4 Loriculus vernalis Indian Hanging Parrot Least Concern

5 Turdoides striatus Jungle Babbler Least Concern

6 Dendrocitta vagabunda Indian Treepie Least Concern

7 Columba livia Blue Rock Pigeon Least Concern

8 Egretta garzetta Little Egret Least Concern

9 Corvus splendens House Crow Least Concern

10 Centropus sinensis Greater Coucal Least Concern

11 Dicaeum erythrorhynchos Pale billed Flowerpecker Least Concern

12 Dicrurus macrocercus Black Drongo Least Concern

13 Copsychus saularis Oriental magpie robin Least Concern

14 Haliastur indus Brahminy kite Least Concern

15 Dicrurus paradiseus Racket tailed Drongo Least Concern

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 3 Description of the Environment

Page 3 - 45

16 Megalaima viridis White cheeked barbet Least Concern

17 Halcyon smyrnensis White Throated Kingfisher Least Concern

18 Hierococcyx varius Common Hawk Cuckoo Least Concern

19 Bubulcus ibis Cattle Egret Least Concern

20 Accipiter badius Shikra Least Concern

21 Nectarinia zeylonica Purple-rumped Sunbird Least Concern

22 Glaucidium radiatum Jungle Owlet Least Concern

23 Pitta brachyura Indian Pitta Least Concern

24 Ardeola grayii Indian Pond Heron Least Concern

25 Acridotheres tristis Common Myna Least Concern

26 Nectarinia lotenia Loten’s Sunbird Least Concern

List of Amphibians

SN Scientific Name Common Name IUCN Status

1 Rhacophorus malabaricus Malabar gliding frog Least Concern

2 Euphlyctis hexadactylus Green Pond Frog Least Concern

3 Pseudophilautus kani Kani Bush Frog Least Concern

4 Polypedates leucomystax Common Tree Frog Least Concern

5 Duttaphrynus melanostictus Indian common toad Least Concern

6 Hoplobatrachus tigerinus Indian bullfrog Least Concern

List of Odonates

SN Scientific Name Common Name

1 Ceriagrion coromandelianum Coromandel Marsh Dart

2 Urothemis signata Greater Crimson Glider

3 Ceriagrion cerinorubellum Orange-Tailed Marsh Dart

4 Pantala flavescens Wandering Glider

5 Diplacodes trivialis Ground Skimmer

6 Rhyothemis vareiegata Common Picture Wing

7 Potamarcha congener Yellow-Tailed Ashy Skimmer

8 Ictinogomphus rapax Common Clubtail

9 Neurothemis tullia Pied Paddy Skimmer

10 Aethriamanta brevipennis Scarlet Marsh Hawk

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 3 Description of the Environment

Page 3 - 46

11 Rhodothemis rufa Rufous Marsh Glider

12 Orthetrum sabina Green Marsh Hawk

List of Butterflies

SN Common Name Scientific Name Status

Papilionidae

1 Crimson Rose Pachliopta hector Linnaeus

2 Common Mormon Papilio polytes Linnaeus

3 Southern Birdwing Troides minos Cramer Endemic to W. Ghats

4 Common Rose Pachliopta aristolochiae Fabricius

5 Blue Mormon Papilio polymnestor Cramer

Pieridae

6 Common Jezebel Delias eucharis Drury

7 Common Emigrant Catopsilia Fabricius

8 Great Orange Tip Hebemoia glaucippe Linnaeus

9 Common Grass Yellow Eurema hecabe Linnaeus

Nymphalidae

10 Chocolate Pansy Junonia iphita Cramer

11 Great Eggfly Hypolimnas bolina Linnaeus

12 Clipper Parthenos sylvia Cramer

13 Common Sailor Neptis hylas Linnaeus

14 Common Four-ring Ypthima huebneri Kirby

15 Nigger Orsotriaena medus Fabricius

16 Common Crow Euploea core Stoll

17 Common Palmfly Elymnias hypermnestra Linnaeus

Lycaenidae

18 Yamfly Loxura atymnus

19 Tiny Grass Blue Zizula hylax Fabricius

20 Common Pierrot Castalius rosimon Fabricius

Hesperidae

21 Chestnut Bob Iambrix salsala Moore

22 Bush Hopper Ampittia dioscorides Fabricius

23 Grass Demon Udaspes folus Cramer

24 Pygmy Grass Hopper Aeromachus pygmaeus Fabricius

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 3 Description of the Environment

Page 3 - 47

List of Millipedes and Centipedes

SN Scientific Name Common Name IUCN Status

1 Trigoniulus corallinus Rusty millipede Least Concern

2 Anoplodesmus saussurii Least Concern

3 Leptogoniulus sorornus Least Concern

List of Ants

SN Common Name Scientific Name

1 Weaver Ant Oecophylla smaragdina

2 Black Crazy Ant Paratrechina longicornis

3 Yellow crazy Ant Anoplolepis gracilipes

4 Army Ant Leptogenys sp.

5 Red fire Ant Solenopsis geminata

6 Common Godzilla Ant Camponotus compressus

List of Spiders

SN Family Scientific Name

1 Araneidae Argiope pulchella

2 Araneidae Argiope anasuja

3 Salticidae Plexippus paykulli

4 Oxyopidae Oxyopes biramanicus

5 Pholcidae Crossopriza lyoni

6 Pisauridae Pardosa psedoannulata

7 Salticidae Plexippus petersi

8 Lycosidae Hippasa agelenoides

9 Araneidae Eriovixia laglaisei

10 Hersilidae Hersilia savignyi

11 Sparassidae Hetropoda venatoria

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 3 Description of the Environment

Page 3 - 48

3.8.4 Interpretation of Ecological Assessment

Flora

The most dominant plant family is Compositae with 8 plant species

followed by Leguminosae, Moraceae Euphorbiaceae, and Malvaceae. One

tree species namely Artocarpus hirsutus is endemic to Southern Western

Ghats.

Fauna

Regarding the conservat ion status of the fauna, none of the animal

species ident if ied from the site belonged to the threatened categories

identif ied by the International Union for Conservation of the Nature and

Natural Resources (IUCN). Most of them are common and widely

distributed and the range of occurrence extended to wide geographical

area. One species of butterf ly namely Southern Birdwing (Troides minos)

and one species of amphibian viz. Rhacophorus malabaricus reported

f rom the site are endemic to W. Ghats.

The present project is an expansion of exist ing hospital cum medical

college campus. The construct ion of new buildings are within the existing

plot area. Therefore, the proposed construct ion act iv ity wi ll have minimal

impact on the local f loral and faunal species. Due to the construct ion

act iv ity, there wil l be minimal loss of habitat to faunal species specially to

avifauna.

3.9 Socio Economc Environment

3.9.1 Introduction

The present project is an expansion of exist ing hospital cum medical

college campus and the construction of new buildings are within the

exist ing plot area.

The construction act iv ity has long term irreverisble impact on local,

sociological, cultural and economical situat ion. In order to evaluate socio-

economical impact of the project, an extensive study on the existing

socio-economic status is carr ied out. Since the project area is in pr ivate

land and devoid of any habitat ion, therefore, there is no displacment of

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 3 Description of the Environment

Page 3 - 49

people and loss of l ivelihood due to the proposed activity in the core

zone.

3.9.2 Approach adopted

To conduct the study, pr imary and secondary data were used.

Primary Data: Stake holder Consultat ion, unstructured interview, f ield

observat ion, and telephonic survey.

Secondary data: Yearly project document and Development Charter of

the Panchayat.

3.9.3 Stake Holders

As part of study the Socio Economic expert conducted interviews with

different stakeholders of the Panchayat. The detai ls of stake holders are

given below table 3.20.

Table 3.20 - Details of Stake Holder

Sl. No Name Designation Phone Number

01 M P Venugopalan Secretory, Edappal

Grama panchayath

8606339116

02 K Sathi Devi HM, Govt. U P

School,Pulikkad

9495805752

03 T P Surendran Polit ician 9048101990

04 K Bhavadasan Polit ician 8921195046

3.9.4 Edappal Gama Panchayath

The Edappal Gama Panchayath came in to exist in 1956. It is a town in

Malappuram district, Kerala state, India. Edappal is at a junction of two

roads Thrissur-Kutt ippuram and Palakkad-Ponnani state highways located

45 km from Malappuram.Edappal l ies in two panchayaths The fi rst notable

public inst i tut ion in Edapal was the Government High School (now higher

secondary school). The school was established in 1957 when the f irst

Communist ministry of EMS Namboodiripad had quickly sanct ioned 65

high schools in the then educat ionally backward Malabar region. Though

the high school was sanctioned, there was no suff icient fund or

infrastructure in order to start the high school. Hence the Namboothiris of

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 3 Description of the Environment

Page 3 - 50

Naarayanamangalathu Mana graciously donated the land where the high

school now stands.

3.9.5 Basic details of Edappal Grama panchayath

Name of Panchayat Edappal

Geographical area 22.28 Sq. Km

No. of wards 19

Vil lage Edappal and Kolollab

Distr ict Malappuram

Boundary North – Kalady Grama panchayath

East – Vattomkulam and Alamkode Grama

Panchayats

South – Nannamukku, Maranchery and

Veliyamkode panchayath

West –Ponnani Municipality and Maramcheri

Gramam Panchayath

3.9.6 Edappal Census Town

Edappal Census Town, with population of about 33 thousand is Ponnani

sub district 's the 2nd least populous census town located in Ponnani sub

district of Malappuram district in the state Kerala in India. Total

geographical area of Edappal census town is 22 km2 and it is the biggest

census town by area in the sub district. Populat ion density of the census

town is 1465 persons per km2. There is only one ward in this census town

which is Edappal Ward No 01 and the populat ion of Edappal Ward No 01

is about 33 thousand.

Nearest rai lway stat ion is Kutt ippuram which is 10 km far from here.

Ponnani is the sub district head quarter and the distance from the census

town is 12 km. District head quarter of the census town is Malappuram

which is 65 km away. Thiruvananthapuram is the state head quarter of the

census town and is 350 km far from here. Yearly average rainfall of the

census town is 2200 mm. Maximum temperature here reaches up to 30°C

and minimum temperature goes down to 24°C.

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 3 Description of the Environment

Page 3 - 51

3.9.7 Demographics

The census town is home to about 33 thousand people, among them about

15 thousand (46%) are male and about 17 thousand (54%) are female.

88% of the whole population are from general caste, 12% are from

schedule caste and 0% are schedule tribes. Child (aged under 6 years)

populat ion of Edappal census town is 12%, among them 50% are boys

and 50% are girls. There are 6684 households in the census town and an

average 5 persons l ive in every family.

3.9.8 Caste wise male female population 2011 - Edappal

Total General Schedule

Caste

Schedule

Tribe Child

Total 32,550 28,668 3,821 61 4,032

Male 15,113 13,235 1,848 30 2,004

Female 17,437 15,433 1,973 31 2,028

3.9.9 Religion wise distribution of population

Hindus contribute 57% of the total population and are the largest rel igious

community in the census town followed by Muslims which contr ibute 42%

of the total population. Female Sex ratio per 1000 male in Hindus are

1120 in Muslims are 1203.

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 3 Description of the Environment

Page 3 - 52

3.9.10 Religion wise population 2011 - Edappal

Total Hindu Muslim Christian Sikh Buddhist Jain Others Not

Sta ted

Total 32,550 18,716 13,603 161 1 0 0 1 68

Male 15,113 8,828 6,174 73 0 0 0 1 37

Female 17,437 9,888 7,429 88 1 0 0 0 31

3.9.11 Growth of population

Population of the census town has increased by 7.5% in last 10 years. In

2001 census total population here were about 30 thousand. Female

populat ion growth rate of the census town is 9.8% which is 4.9% higher

than male populat ion growth rate of 4.9%. General caste population has

increased by 7.6%; Schedule caste populat ion has increased by 4.9%;

Schedule Tribe population has increased by 1933.3% and child population

has increased by 4.8% in the census town since last census.

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 3 Description of the Environment

Page 3 - 53

3.9.12 Growth of population (percent) 2001 to 2011 - Edappal

Total General Schedule

Caste

Schedule

Tribe

Child

Total 7.5% 7.6% 4.9% 1933.3% 4.8%

Male 4.9% 4.8% 4.1% 1400% 3.7%

Female 9.8% 10.1% 5.7% 3000% 6%

3.9.13 Sex Ratio - Females per 1000 Male

As of 2011 census there are 1154 females per 1000 male in the census

town. Sex ratio in general caste is 1166, in schedule caste is 1068 and in

schedule tr ibe is 1033. There are 1012 girls under 6 years of age per

1000 boys of the same age in the census town. Overall sex rat io in the

census town has increased by 52 females per 1000 male during the years

from 2001 to 2011. Child sex rat io here has increased by 22 girls per

1000 boys during the same t ime.

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 3 Description of the Environment

Page 3 - 54

3.9.14 Change in sex ratio 2001 to 2011 - Edappal

Total General SC ST Child

Change 52 56 17 533 22

2011 1154 1166 1068 1033 1012

2001 1102 1110 1051 500 990

3.9.15 Literacy

Total about 27 thousand people in the census town are literate, among

them about 13 thousand are male and about 14 thousand are female.

Literacy rate (children under 6 are excluded) of Edappal is 95%. 97% of

male and 94% of female populat ion are l i terate here. Overall l iteracy rate

in the census town has increased by 4%. Male literacy has gone up by 2%

and female li teracy rate has gone up by 6%.

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 3 Description of the Environment

Page 3 - 55

3.9.16 Change in l iteracy rate 2001 to 2011 - Edappal

Total Male Female

Change 4.0% 2.0% 5.9%

2011 95% 96.6% 93.6%

2001 91% 94.6% 87.7%

3.9.17 Workers profile

Edappal has 28% (9131) populat ion engaged in either main or marginal

works. 48% male and 11% female population are working populat ion. 40%

of total male populat ion are main (full t ime) workers and 9% are marginal

(part t ime) workers. For women 7% of total female population are main

and 3% are marginal workers.

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 3 Description of the Environment

Page 3 - 56

3.9.18 Percentage of working population - Edappal

Worker

(Among total

populat ion)

MainWorker

(Among

workers)

Marginal Worker

(Among workers)

Non Worker

(Among total

populat ion)

Total 28.1% 22.2% 5.8% 71.9%

Male 48.2% 39.5% 8.7% 51.8%

Female 10.5% 7.2% 3.3% 89.5%

3.9.19 Demographics

Population 32550

Population density 1465 per km2

Growth of Populat ion 7.5%

Sex Ratio 1154

Sex Ratio Child 1012

Literacy Rate 95%

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 3 Description of the Environment

Page 3 - 57

3.9.20 Interpretation of present socio-economic status of the area

The density of population in the buffer zone is about 1465 persons per

sq km. The project area is in a rural vi l lage.

Majority of the population in the study area are engaged in agriculture and

cult ivation. There is no major industry in the area. The proposed project is

l ikely to generate direct and indirect employment. Economic growth is

expected in the area due to construction boom and al lied industry like

transport, mini hotels and restaurants and enhanced commercial activit ies

(markets, shops, real estate etc.).

Also, the healthcare faci l it ies wil l be increase due to the sett ing up of

medical col lege in the vic inity.

*******************************************************************************

CHAPTER – 4

ANTICIPATED ENVIRONMENTAL

IMPACTS

&

MITIGATION MEASURES

M/s SREEV ALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 4 Ant ic ipated Envi ronmenta l Impacts & Mit igat ion Measures

Page 4 - 1

4.0 ANTICIPATED ENVIRONMENTAL IMPACTS & MITIGATION MEASURES

4.1 Introduction

The previous chapter dealt with the Descript ion of the Environment

surrounding the project area.

The present project is an expansion of exist ing hospital cum medical

college campus. The construct ion of new buildings are within the existing

plot area. Therefore, the proposed construction activity will have minimal

impacts on the dif ferent facets of the environment.

The ambient air quality and ambient noise level of the core zone and

buffer zone is within the permissible standards. The water quality

assessment (ground water and surface water) is sat isfactory. The

proposed construction act ivity wil l not disturb the ground water quality.

The land use land cover of the buffer zone is predominantly with

plantations. There is some endemic f loral & faunal species. There are no

species belonging to Rare, Endangered and Threatened (RET) species.

The project area is in a rural area and the nearest town (urban area) is

Edappal which is located at about 2 km towards north direction from the

project s ite.

4.1.1 Areas for identification of Environmental aspects and impacts.

Proposed project wil l be constructed and developed gradually in the t ime

span of 5 years (approx.). The overall project wil l have two phases i.e.

construction phase and operat ion phase. In construction phase, basic

infrastructure faci l it ies l ike internal roads, water supply, sewerage

system, storm water drainage, street l ight ing, construction of dif ferent

buildings, up-gradat ion of sewage treatment plant, eff luent treatment

plant, up-gradation of solid waste disposal & treatment arrangement

system, rain water harvest ing systems etc. wil l be developed.

The proposed project is an expansion of exist ing hospital cum medical

college campus, therefore, most of the infrastructure faci l it ies are already

developed within the site.

During operation phase, the developed infrastructure wil l be in operation

and wil l have environmental aspects l ike vehicular movement, operat ion

M/s SREEV ALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 4 Ant ic ipated Envi ronmenta l Impacts & Mit igat ion Measures

Page 4 - 2

of D.G. sets, eff luent & sewage generation, generation of MSW & bio-

medical waste, e-waste, hazardous waste etc. The areas of environmental

concerns for which the impacts and their predict ions are taken into

consideration are :-

• Air Environment

• Noise Environment

• Water Environment

• Land Environment

• Biological Environment

• Socio-Economic Environment

• Aesthet ics

• Building Materials

• Energy Conservation

4.2 Details of anticipated environmental impacts due to the proposed project and the mitigation measures for minimizing and / or offsetting adverse impacts identified.

4.2.1 Air Environment

Impacts on the Air Environment:

Prediction of Impact during Construction Phase

Impact of construction activit ies on air quali ty is a cause for concern

mainly in the dry months due to sett l ing of dust particles. The main

sources of emission during the construct ion period are the movement of

equipment at site and dust emitted during the level l ing, grading,

earthworks, foundation works and other construction related act iv it ies.

The impact is l ikely to be for short duration and conf ined locally to the

construction site i tself . The impact will , be marginal, and temporary in

nature.

Prediction of Impact during Operation Phase

The source of gaseous pollutants within the proposed expansion project

are from DG sets. The emissions of Sulphur Dioxide (SO2) and Oxides of

Nitrogen (NOx) wil l be due to operat ion of DG sets (Existing - 500 kVA x

1 no. + 625 kVA x 1 no. and Proposed - 500 kVA x 1 no. + 625 kVA x

M/s SREEV ALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 4 Ant ic ipated Envi ronmenta l Impacts & Mit igat ion Measures

Page 4 - 3

1 no.), only in case of the fai lure of the power grid.

In order to control emission of particulates during operation of the DG

sets, adequate stack height is provided as per CPCB norms.

Air Modelling Studies

The mathematical Model ISCST-3, was used for predicting the GLCs,

which is entirely in l ine with the requirement of Central Pollut ion Control

Board (CPCB), New Delhi.

Anticipated Impacts during construction phase

Environmental aspects during Construction Phase

The potential sources of air emissions during the construct ion phase of

the project wil l be as fol lows:

• Dust from earth works (during si te clearance and preparat ion for

construction of new buildings);

• Emissions from diesel generators at site;

• Emissions from the operation of construct ion equipments and

machineries.

• Fugit ive emissions from vehicles running to site;

• Fugit ive emissions during the unloading of loose construction materials

at site;

• Fugit ive emissions during mixing of cement with other building

materials during construct ion act ivit ies;

• Air emissions other than dust ar ise from combustion of hydrocarbons.

The pollutants of concerns are NOx, SOx, CO, particulate etc.

• Use of f ire wood, coal etc as fuel for domestic cooking etc in labour

sheds.

Ambient air quali ty effects are normally assessed in relat ion to their

potent ial to cause health deteriorat ion and nuisance in local communities ,

health deteriorat ion amongst onsite workers etc.

During the excavation of foundations, unloading of loose construction

materials, cement bags and mixing of cement with other building materials

such as brick and stone dust, sand, aggregates, fugit ive dust emissions

M/s SREEV ALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 4 Ant ic ipated Envi ronmenta l Impacts & Mit igat ion Measures

Page 4 - 4

may be emitted at construction site. It may be noted that these emissions

wi ll be in the form of coarse particulate matter and sett le down ult imately

in closed vicinity of construction site.

Emissions from the D.G. sets during construct ion phase may cause some

local ized impact on ambient air quality for short duration, as it wil l be

operated during power fai lure only. It may be noted that the D.G. set

power will be used to operate construct ion equipment only if required.

Adequate height of stacks and Acoust ic enclosures wi ll be provided to the

D.G. set as per guidelines of CPCB to facil i tate the dispersion of f lue

gases into the atmosphere.

Environmental Aspects during operation phase

During the operation phase, cars, scooter/motorcycle will be owned by the

occupiers of proposed project. Also, the vehicles and the transport system

for staff in dif ferent bui ldings of hospital cum medical col lege campus wil l

be at site. Vehicular emissions wil l be major source of air pollution.

Quantum and dispersion of pol lutants form vehicular emission wil l depend

upon the fol lowing:

• Volume of traff ic on the roads,

• Meteorological condit ions.

• Emission sources from D.G. Sets

From vehicular emissions, SOx, NOx and CO are pol lutants of primary

concern. The dispersion of vehicular emissions wi l l be conf ined upto

100 m from the road and concentration will decrease with the increase in

distance from road. It is ant icipated that the contribution of vehicular

emissions in ambient air quali ty wil l be marginal but well within the

stipulated National Ambient Air Quality standards. At higher wind speed,

dispersion wil l be faster.

D.G. Sets wil l be provided for back up electric ity supply during power

failure. This wi ll cause emission of SPM, SOx, NOx and CO. However,

since the D.G. Sets wil l be operational only during power fai lure, the

emissions wil l also be limited.

M/s SREEV ALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 4 Ant ic ipated Envi ronmenta l Impacts & Mit igat ion Measures

Page 4 - 5

Improper disposal of sewage and municipal sol id waste in the land also

causes nuisance in the operation phase of the project.

4.2.2 Noise Environment

Environmental aspects during construction phase

During the construction phase of project, noise will be generated from the

various sources. Some major sources of noise generation at project site

are l isted here under:

• Generation of noise during movement of vehicles carrying materials

and also during loading & unloading activ it ies.

• Generation of noise from excavation machines, concrete mixer and

other construction machines,

• Generation of noise during the operat ion of D.G. Sets,

• Generation of noise during concret ing, hammering, dri l l ing, stone

cutt ing etc.

All the above-mentioned sources of construction activit ies at proposed

expansion project would be intermittent and experienced occasionally. It

may also be noted that the most of the construct ion activ it ies would be

carried out only during the daytime.

The expected noise levels from various activit ies are given hereunder:

From vehicles bringing materials to the site 70 dB(A)

D.G. Set 85 dB(A)

Excavat ion 80 dB(A)

Concrete Mixtures 80 dB(A)

Hammering 85 dB(A)

The sound level generated by noise source decreases with increasing

distance from the source due to wave divergence. An addit ional decrease

in sound pressure level from the source is expected due to atmospheric

effect or i ts interaction with objects in the transmission path.

The noise produced during construction phase will have temporary

impacts on the existing, ambient noise levels at project site but restricted

to small distance and only during dayt ime.

M/s SREEV ALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 4 Ant ic ipated Envi ronmenta l Impacts & Mit igat ion Measures

Page 4 - 6

Environmental aspects during operation phase

The main sources of noise from the project are running of D.G. Sets,

HVAC system and vehicular traff ic. D.G. Sets installed in the proposed

project wi ll provide emergency electr icity supply during power fai lure. This

wi ll be intermittent and for short durations. The vehicles plying within the

site wil l be mainly of the occupiers and hence not expected to cause

unnecessary noise. Hence, during this phase, no major impact on noise

environment is ant icipated.

4.2.3 Land Environment

Environmental Aspects during Construction phase

Environmental aspects during construction phase in the land environment

are: -

• Infrastructure development

• Site clearance & excavation

• Excavated earth & loose construction materials

• Loss of topsoil due to storm water

• Labour colony & generation of sewage and municipal solid waste

• Construct ion waste generation and disposal

Environmental Aspects during Operation phase

During the operation phase of the project, the soi l may get polluted /

contaminated from lit ter ing of various kinds of wastes generated within

the site such as food items, paper, wood pieces, paints, pesticides, oi l &

grease etc.

4.2.4 Water Environment

Environmental Aspects of Surface Water during construction phase

The primary concerns relat ing to surface water associated with

construction activit ies are pointed out below:-

• Consumption of large quantity of water for site preparat ion &

development.

• Loose excavated earth and loose construction material at site & runoff

related to unpaved and excavated / exposed areas during rainy days.

M/s SREEV ALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 4 Ant ic ipated Envi ronmenta l Impacts & Mit igat ion Measures

Page 4 - 7

• Sediments transported along with the runoff f rom the construct ion site.

• Run off related to area where lubricant, fuel other construct ion

materials are stored, used and disposed, off .

• Water consumption in labour colony (temporary accommodation area

for laborers) and generation of sewage & MSW from the colony.

Large quantity of water required for site preparation & development also

water consumption in labour colony during construct ion phase. Surface

water quality may be affected with the discharge of the runoff f rom the

project site. The impact to the surface water bodies could arise from the

increased soil erosion from excavated site / exposed soil causing

increase in the suspended part ic les and turbidity of runoff water from the

site. Also the non-point sources of pollut ion can affect the surface water

body. Also, the municipal solid waste and the sewage generation from the

labour colony wi ll af fect the water quality for a shorter period. Therefore,

the surface water quality during rains will be impacted marginally for very

short duration.

Environmental Aspects of Surface Water during operation phase

During the operational phase, large quantity of water consumption for the

occupier of dif ferent buildings, make-up water to the HVAC units can have

impact on competing users. The generation of sewage & MSW, bio-

medical waste from the hospital, e-waste from institutional buildings,

hazardous waste from hospital cum medical college campus can have

impact on the surface water body.

Environmental Aspects of Ground Water during construction phase

Due to the presence of high ground water table within the project site, the

excavat ion during construction phase for below ground level structures if

carried out wil l lead to dewatering and deplet ion of ground water and wil l

have impact for a longer duration. Consumption of ground water for

construction activit ies and for labour colony will have impact on

competing users for a shorter duration. Discharge of sewage & MSW to

land can contaminate ground water for a shorter duration.

M/s SREEV ALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 4 Ant ic ipated Envi ronmenta l Impacts & Mit igat ion Measures

Page 4 - 8

Environmental Aspects of Ground Water during Operation phase

Consumption of ground water for domestic purposes for occupiers of the

different bui ldings of hospital cum medical college & make-up water for

HVAC units will have impact on competing users for a longer durat ion.

Discharge of sewage & MSW to land can contaminate ground water for a

longer duration.

As per the Ground Water information Booklet, CGWB, the proposed

project is categorized as 'Safe' zone and hence the ground water

available in the region is ensure and to use of domestic purposes.

4.2.5 Biological Environment

Environmental aspects during construction phase

The biological environment can have impact due to the fol lowing

environmental aspects during construction phase: -

• Site clearance & excavation

• Various construct ion act ivit ies

• Labour colony (temporary accommodation of laborers) and

procurement of f ire wood for domestic purposes.

Environmental aspects during operation phase

The biological environment can have impact due to the fol lowing

environmental aspects during operation phase: -

• Vehicular movement

• Generation of Municipal sol id waste & its improper disposal.

4.2.6 Socio-Economic Environment

Environmental aspects during construction phase

The socio-economic environment can have impact due to the following

environmental aspects are: -

• Labour colony & the migrant labours and the related cultural &

social issues

• Unhygienic site sanitation facil it ies may cause health damage to the

workers.

M/s SREEV ALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 4 Ant ic ipated Envi ronmenta l Impacts & Mit igat ion Measures

Page 4 - 9

Environmental aspects during Operation phase

All the environmental aspects during operat ion phase of the proposed

expansion of existing campus can lead to posit ive impacts only. During

operational phase of proposed expansion of existing hospital cum medical

college campus project, about 1,000 persons will get direct employment

opportunit ies as staff in the inst i tut ional building, management staff ,

maintenance, housekeeping and security. As an est imate, during

operation phase, about 100 persons wil l get marginal employment

opportunit ies from the proposed project who would work as domestic

helpers. This wi ll help in improving the qual ity of l i fe of economically

weaker sect ions of the local area.

4.2.7 Other environmental aspects

The other identif ied environmental aspects which can have impact during

construction phase & operation phase are: -

• Un-aesthetic Labour colony for the workers

• In-eff icient building design and high consumption of energy

• In-eff icient building materials and high consumption of energy

• Improper f ire & other emergency preparedness during natural and

man-made activit ies.

4.3 Identified Environmental impacts from various aspects

The above discussed environmental aspects during construct ion &

operation of the project have been analyzed to identify the possible

environmental impacts on air, noise & vibration, water, land environment,

biological & socio economic environment, building materials, energy etc.

Various impacts during the construction phase and operation phase on

the environmental parameters have been studied to est imate the impact

on environment.

The impact identif icat ion and predict ion process aims to:

• Ident ify potential source or cause of impact throughout the l i fe of

project.

• Characterize the potent ial impacts affect ing a target or receptor

(physical, human and socio-economic).

M/s SREEV ALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 4 Ant ic ipated Envi ronmenta l Impacts & Mit igat ion Measures

Page 4 - 10

• Assess the potential of changing likely-hood of impact through

Environmental Management Plan (EMP)

Prediction of the impacts due to the construct ion and operat ional

act iv it ies encompass the developmental processes to be undertaken

during construct ion and operational phases. For each category of

environmental receptor (such as ambient air quality, water quali ty, soil,

land, biological environment, noise level, socio economic aspects etc.)

the potent ial impacts of activit ies during construct ion and operational

phases have been identif ied.

The generat ion of pollut ion could be cont inuous, periodic or accidental,

sources of pollutants and their characteristics during the construction and

operational phases. Similarly, the consumption / loss of natural resources

could be cont inuous, periodic or accidental.

The Identif ied Impacts are broadly divided into two segments.

1. Impacts due to pollutants generated in the development of the

proposed project during both the construction and operat ional phases

are solid, l iquid and gaseous in nature.

2. The consumption / loss of natural resources l ike water, top-soi l, current

ecology of the site etc.

In al l, 35 Environmental aspects have been ident if ied from various areas

during construction phase and 29 during operation phase.

The identif ied environmental aspects & their ant ic ipated impacts are

presented in the table 4.1.

M/s SREEV ALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 4 Ant ic ipated Envi ronmenta l Impacts & Mit igat ion Measures

Page 4 - 11

Table 4.1- Matrix of identified Environmental Aspects & their Anticipated Impacts from the project

CONSTRUCTION PHASE:-

S.

No.

Impact on

Environment Act ivi ty / Aspect Ant icipated Impacts

AIR ENVIRONMENT

1 Air

Si te Clearances &

preparat ion, excavat ion &

infrastructure development

Dust emissions.

2 Air Construc t ion Act ivi t ies** Dust Emissions from construct ion act iv i t ies

3 Air Point source emissions f rom

operat ion of DG Sets

Part icu la te Matter & Gaseous emissions

( including worst condit ion of operat ing a l l

DG sets)

4 Air

L ine source emissions from

movement of construct ion &

other vehic les, machiner ies.

Fugi t ive dust & gaseous emissions f rom vehic les exhaust

5 Air Temporary stay of construct ion workers

Impact on ambient a ir due to use of f i re

wood, coal, e tc. as fue l for domest ic

cook ing etc.

WATER ENVIRONMENT

1 Water Si te preparat ion &

infrastructure development

Use of large quant ity of water for dust

suppress ion, consol idat ion & compaction.

2 Water Excavat ion for below ground

leve l structures Impacts on Hydrology due to dewater ing

3 Water Construc t ion Act ivi t ies**

Impact on compet ing users due to large

consumpt ion of water for cur ing, dust

suppress ion, construct ion, domest ic use

etc.

4 Water

Loose excavated ear th &

loose construct ion mater ials

at s i te

Contaminat ion of surface water body &

aquat ic l i fe

5 Water Storm water f rom the s ite

Improper channel izat ion may lead to

contaminat ion of sur face water & ground

water by non-point sources of po l lu t ion

l ike l i t ter , o i l & grease, loose earth

6 Water Storm water f rom the s ite

Clogging of storm water drainage system

by s i l t & other mater ia ls may lead to

f looding condit ions

7 Water

Temporary stay of construct ion workers generat ion of sewage & MSW

Impact on surface / ground water qual it y

due to untreated discharge of sewage &

so l id waste from the labor colony

8 Water

Temporary stay of

construct ion workers & the ir

domest ic water consumpt ion

Impact on compet ing users due to

consumpt ion of publ ic supply / ground

water ( resource loss)

NOISE ENVIRONMENT

M/s SREEV ALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 4 Ant ic ipated Envi ronmenta l Impacts & Mit igat ion Measures

Page 4 - 12

1 Noise Movement of construct ion

equipments & machiner ies.

Noise due to heavy machinery for

excavation

2 Noise Construct ion Act ivi t ies** Noise & vibrat ion due to construct ion

Act iv i t ies

3 Noise Operat ion of DG Sets

Noise & Vibrat ion from DG Sets due to

inadequate acoust ic enclosure ( including

worst condi t ion of operat ing al l DG sets)

LAND ENVIRONMENT

1 Soi l In frastructure development Compact ion of so i l by ear th moving

vehic les

2 Soi l Si te Clearance & excavat ion Erosion & modif icat ion of surface

3 Soi l excavated earth & loose

construct ion mater ials Loss of topsoi l ( resource loss)

4 Soi l Storm water f rom the s ite

Improper channel izat ion may lead to loss

of fer t i le top so i l a long with sur face run-of f

and subsequent loss of water ho lding and

inf i l t rat ion capaci ty of so i l

5 Soi l Temporary stay of

construct ion workers

Impact due to untreated d ischarge of

sewage & MSW into the land

6 Soi l Construc t ion waste Improper d isposal o f construct ion waste

into the land

BIOILOGICAL ENVIRONMENT

1 B io log ica l Si te Clearances &

Excavat ion

Loss of vegetat ion and loss of habi ta t of

faunal species (resource loss)

2 B io log ica l Construc t ion Act ivi t ies** Vibrat ion due to movement / operat ion of

heavy machinery

3 B io log ica l Temporary stay of construct ion workers

Cutt ing of trees, shrubs etc. for procur ing

f i re wood by construct ion workers.

( resource loss)

SOCIO-ECONOMIC

1 Socio

Economic Temporary stay of construct ion workers

Impact on nat ive socia l fabr ic o f the si te

surroundings l ike cu l tural d ivers i t y,

possib le increase in ant i-socia l act iv i t ies

etc.

2 Socia l

Responsibi l i t y Construc t ion workers

Unhygien ic s i te sanita t ion faci l i t ies may

cause heal th damage to construct ion

workers

OTHERS

1 Aesthet ics Temporary stay of construct ion workers

Construct ion of Improper / unaesthet ic

labor sheds/shel ters may impact aesthet ic

appearance of the s i te surroundings.

2 Energy

Conservat ion Energy Consumpt ion

Use of energy in-ef f ic ient bu ild ing

mater ia ls may lead to h igher consumpt ion

of e lectr ic i t y in air condit ioned bui ld ings.

3 Energy

Conservat ion Energy Consumpt ion

Adopt ion of energy in-ef f icient vehic les, appl iances, l ights etc. may lead to wastage of energy

M/s SREEV ALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 4 Ant ic ipated Envi ronmenta l Impacts & Mit igat ion Measures

Page 4 - 13

4 Energy

Conservat ion Energy Consumpt ion

Improper or ientat ion of the bu i ld ing may lead to h igh energy consumpt ion due to high heat ga in to the bu i ld ing, dark zone & improper vent i la t ion

5

Bui ld ing Mater ial

Resource Conservat ion

Bui ld ing Mater ia l

consumpt ion

Use of far fetched construct ion mater ia ls

than the local ly avai lab le construct ion

mater ia ls may lead to over explo i tat ion of

natura l resources & increase in carbon

footpr int

6 Disaster

Management Fire & other hazards

Absence of proper f ire protect ion sys tems

may lead to f i re hazards

7 Disaster

Management Fire & other hazards

Absence of s ignages, mock dr i l ls &

assembly points

8 Disaster

Management Fire & other hazards

Absence of relevant st ructura l safety

measures dur ing bui ld ing design may lead

to damage to bu i ld ings dur ing the natura l

calamit ies

OPERATION PHASE:-

S.

No.

Impact on

Environment Act ivi ty / Aspect Ant icipated Impacts

AIR ENVIRONMENT

1 Air On s i te Vehic le Movement Dust & gaseous emissions from vehic les

exhaust

2 Air Point Source emissions

f rom operat ion of DG Sets

Part icula te Mat ter & Gaseous emissions

( includ ing worst condi t ion of operat ing a l l

DG sets)

3 Air Sewage & Munic ipa l Solid

Waste

Improper d isposal of sewage and MSW

may lead to odour & generat ion of gases

due to de-composi t ion

WATER ENVIRONMENT

1 Water Water consumpt ion

Impact on compet ing users due to

consumpt ion of publ ic supply / ground

water ( resource loss)

2 Water Operat ion of HVAC Plant

Impact on compet ing users due to

consumpt ion of publ ic supply / ground

water as make-up water ( resource loss)

3 Water Sewage

Improper d ischarge of untreated sewage

may lead to impact on sur face / ground

water qual it y.

4 Water Munic ipa l Sol id W aste &

Medica l W aste from

Hospita l

Improper d isposal of so l id waste may

at tract scavenger avi fauna which may

lead to d isser tat ions of nat ive avi fauna

5 Water e-waste

Improper storage & d isposal may lead to

leaching of heavy metals leading to

contaminat ion

M/s SREEV ALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 4 Ant ic ipated Envi ronmenta l Impacts & Mit igat ion Measures

Page 4 - 14

6 Water Hazardous W aste

Improper storage & d isposal may lead to

leaching of hazardous waste leading to

contaminat ion

7 Water storm water

Improper channel izat ion may lead to

contaminat ion of water body & c logging of

drain may lead to f looding

NOISE ENVIRONMENT

1 Noise Vehic le Movement Increase in Noise & Vibrat ion in

surrounding area

2 Noise Operat ion of DG Sets Noise & Vibrat ion from DG Sets due to

inadequate acoust ic enclosure

3 Noise Operat ion of HVAC Plant Noise & vibrat ion from HVAC Plant

LAND ENVIRONMENT

1 Soi l Munic ipal Sol id W aste Improper disposal of munic ipal sol id

waste may lead to impact on land.

2 Soi l sewage Improper d ischarge of unt reated sewage

may lead to impact on land.

3 Soi l e-waste

Improper storage & d isposal may lead to

leaching of heavy metals leading to

contaminat ion

4 Soi l Hazardous W aste

Improper storage & d isposal may lead to

leaching of hazardous waste leading to

contaminat ion

5 Soi l Storm water Non-point sources of po l lut ion l ike l i t ter ,

o i l & grease, loose ear th

6 Soi l Storm water

Clogging of storm water dra inage system

by s i l t & other mater ia l may lead to

f looding

BIOLOGICAL ENVIRONMENT

1 Biologica l Vehic le Movement Increase in Noise & Vibrat ion in

surrounding area

2 Biologica l Munic ipa l Sol id Waste &

B io-medical waste

Improper disposal of MSW & BMW may

at tract scavenger avi fauna which may

lead to disser tat ions of nat ive avi fauna

OTHERS

1 Aesthet ics Munic ipa l Sol id Waste &

Bio-Medica l Waste

Improper disposal of MSW & BMW may

lead to un-aesthet ic condit ions

2 Energy

Conservat ion Consumption of Energy

Adopt ion of energy in-ef f icient vehic les,

HVAC system, appl iances, l ights etc may

lead to wastage of energy

3 Energy

Conservat ion Consumption of Energy

Non adopt ion of renewable sources of

energy l ike solar energy may lead to

increase dependency on publ ic supply

may lead to consumpt ion of energy by

compet ing users

M/s SREEV ALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 4 Ant ic ipated Envi ronmenta l Impacts & Mit igat ion Measures

Page 4 - 15

4 Disaster

management Fire & other hazards

Absence of trained personnel & mock

dr i l ls may lead to major f i re accidents &

non maintenance of system

SOCIO- ECONOMIC (ALL POSITIVE IMPACTS)

1 Socio Economic bus iness act iv it ies

Increased revenue to the State & Local

Sel f Government by way of taxes and

dut ies leading to inf rast ructure

development & better c iv ic amenit ies

2 Socio Economic bus iness act iv it ies

New business act iv i t ies may lead to

increase in employment opportun ity /

new job creat ion (d irect & ind irect ) for

the local community

3 Socio Economic bus iness act iv it ies

Increased business act iv i t ies at s i te may

lead to improved public t ranspor t

infrastructure in the region may improve

the l i fe st yle and connect iv it y o f the loca l

communit y

4 Socio Economic Medica l faci l i t ies

Avai lab i l i t y of bet ter medica l treatment

faci l i t y w i th in the v ic ini ty to the loca l

populat ion.

4.4 Selection criteria for evolving significant impacts

The signif icance of the impact is decided based on the fol lowing criteria.

� Whether the environmental aspects have potent ial to cause direct

impact or indirect impacts?

� Whether the environmental aspects would violate legal / mandatory

requirement if uncontrol led?

� Whether the l ikely environmental impact will be l imited to local

surroundings or it would be wide spread?

� Whether the likely environmental impact would be of a temporary

nature or permanent nature depending on the toxicity levels?

� Whether the occurrence of the environmental aspects and its l ikely

environmental impact wil l be of long term nature or short term

nature?

� Whether mit igation measures available and can be adopted to

minimize the signif icance of the impacts to permissible l imits?

The above criteria has been shown in the table 4.2 below.

M/s SREEV ALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 4 Ant ic ipated Envi ronmenta l Impacts & Mit igat ion Measures

Page 4 - 16

Table 4.2 - Criteria for Evolving Significant Impacts

Sr.

No.

Criteria Classif icat ion

1. Whether the environmental aspects has potential

to cause direct impact or indirect impact. Direct Indirect

2. Whether the environmental aspects would v iolate

legal / mandatory requirement if uncontrol led Mandatory

Not

Mandatory

3. Whether the l ikely environmental impact wi l l be

limited to local surroundings or i t would be wide

spread.

Local W ide

spread

4. Whether the l ikely environmental impact would be

of a temporary nature or permanent nature

depending on the toxicity levels.

Temporary Permanent

5 Whether the occurrence of the environmental

aspects and i ts l ikely environmental impact wi l l

be of long durat ion in nature or short durat ion.

Long Term Short Term

6 Whether mitigation measures avai lable and can

be adopted to minimize the signif icant of the

impacts to permissible l im its.

Yes No

4.5 The marking for various criteria

For the purpose of comparing the weightage of signif icance of the above

criteria, marks are given to each cr iter ia. Mult ipl ication of marks of al l the

six criter ia is made to arrive at the f inal score of each identif ied impact.

The maximum score would be 64 (2 x 2 x 2 x 2 x 2 x 2) and the minimum

score would be 1 (1 x 1 x 1 x 1 x 1 x 1).

A cut off of 16 marks is assumed to decide the signif icance of

environmental impacts.

The impacts having less than 16 marks are considered as insignif icant.

The impacts having 16 or more marks are considered as signif icant

environmental impacts. The weighted criteria is given in the table 4.3.

M/s SREEV ALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 4 Ant ic ipated Envi ronmenta l Impacts & Mit igat ion Measures

Page 4 - 17

Table 4.3 - Marking for Various Criteria

Sr.

No.

Criteria Classif icat ion

Type Marks Type Marks

1. Whether the environmental aspect

has potential to cause direct impact

or indirect ly.

Indirect 1 Direct 2

2. Whether the environmental aspect

would v io late legal / mandatory

requirement if uncontrol led

Not

Mandatory 1 Mandatory 2

3. Whether the l ikely environmental

impact wi l l be l imited to local

surroundings or i t would be wide

spread.

Local 1 W ide

spread 2

4. Whether the l ikely environmental

impact would be of a temporary

nature or permanent nature

depending on the toxic ity levels.

Temporary 1 Permanent 2

5 Whether the occurrence of the

environmental aspect and i ts l ikely

environmental impact wil l be of long

term durat ion or short term duration.

Short term 1 Long term 2

6 Whether mitigat ion measures

avai lable and can be adopted to

minimize the s ignif icant of the

impacts to permissible l imits.

Yes 1 No 2

4.6 Scores of all anticipated Environmental impacts after applying the marking criteria

The above criteria has been applied for al l the 64 numbers of identif ied

environmental impacts and the impact classif ication based on the criteria

is provided in the table 4.4.

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 4 Ant ic ipated Environmental Impacts & Mit igat ion Measures Page 4 - 18

Table 4.4: Matrix showing the scores of all Environmental impacts as per the criteria

CONSTRUCTION PHASE: -

S.

N.

Impact on

Environment Act ivity / Aspect Anticipated Impacts

Impact Classif ication

Total Marks M1 X

M2..XM6

Whether Signif icant Y/N

Direct (D) / Indirect ( ID)

Mandatory (M) / Not

Mandatory (NM)

Local(L)/ Widespread

(W)

Temporary(T)/ Permanent (P)

Long Term (LT) / short term

(ST)

Mit igation available

( Yes / No)

Marks Marks Marks Marks Marks Marks

D/ID M1 M/NM

M2 L/W M3 T/P M4 LT/ST

M5 Y/N M6

AIR ENVIRONMENT

1 Air

Site Clearances &

preparat ion, excavat ion

& inf ras truc ture

development

Dust emissions. D 2 NM 1 L 1 T 1 ST 1 Y 1 2 N

2 Air Construc t ion Act ivi t ies** Dust Emiss ions f rom construct ion act iv i t ies D 2 NM 1 L 1 T 1 ST 1 Y 1 2 N

3 Air

Point source emiss ions

f rom operat ion of DG

Sets

Part icu late Matter & Gaseous emissions

( including worst condit ion of operat ing a l l

DG sets)

D 2 M 2 W 2 T 1 LT 2 Y 1 16 Y

4 Air

L ine source emissions

f rom movement of

construct ion & other

vehic les, machiner ies.

Fugi t ive dust & gaseous emissions f rom vehic les exhaust

D 2 NM 1 W 2 T 1 LT 2 Y 1 8 N

5 Air Temporary s tay of construct ion workers

Impact on ambient a ir due to use of f i re

wood, coal, e tc. as fuel for domest ic

cook ing etc .

D 2 NM 1 L 1 T 1 ST 1 Y 1 2 N

WATER ENVIRONMENT

1 W ater

Site preparat ion &

inf rastruc ture

development

Use of large quant i ty of water for dust

suppress ion, consol idat ion & compact ion. D 2 NM 1 L 1 P 2 LT 2 Y 1 8 N

2 W ater Excavat ion for below

ground level structures Impacts on Hydrology due to dewater ing D 2 NM 1 L 1 P 2 LT 2 Y 1 8 N

3 W ater Construc t ion Act ivi t ies**

Impact on compet ing users due to large

consumpt ion of water for cur ing, dust

suppress ion, construct ion, domestic use

etc .

D 2 NM 1 W 2 P 2 LT 2 Y 1 16 Y

4 W ater

Loose excavated ear th

& loose construc t ion

mater ia ls at s i te

Contaminat ion of surface water body &

aquat ic l i fe D 2 NN 1 L 1 T 1 ST 1 Y 1 2 N

5 W ater storm water f rom the

s ite

Improper channel izat ion may lead to

contaminat ion of surface water & ground

water by non-point sources of pol lu t ion l ike

l i t ter , o i l & grease, loose earth

D 2 NM 1 L 1 T 1 ST 1 Y 1 2 N

6 W ater storm water f rom the

s ite

Clogging of storm water dra inage system

by s i l t & other mater ia ls may lead to

f looding condit ions

D 2 NM 1 L 1 T 1 ST 1 Y 1 2 N

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 4 Ant ic ipated Environmental Impacts & Mit igat ion Measures Page 4 - 19

7 W ater Temporary s tay of construct ion workers

Impact on surface / ground water qual i t y

due to untreated discharge of sewage &

sol id waste f rom the labor colony

D 2 M 2 L 1 T 1 ST 1 Y 1 4 N

8 W ater Temporary s tay of

construct ion workers

Impact on compet ing users due to

consumpt ion of publ ic supply / ground

water (resource loss)

D 2 NM 1 W 2 T 1 ST 1 Y 1 4 N

NOISE ENVIRONMENT

1 Noise

Movement o f const ruct ion

equipments &

machiner ies .

Noise due to heavy machinery for excavat ion D 2 M 2 L 1 T 1 ST 1 Y 1 4 N

2 Noise Construct ion Act iv i t ies** Noise & vibra t ion due to construct ion Act i v i t ies D 2 M 2 L 1 T 1 ST 1 Y 1 4 N

3 Noise Operat ion of DG Sets

Noise & Vibrat ion f rom DG Sets due to

inadequate acoust ic enc losure ( inc lud ing wors t

condi t ion of operat ing a l l DG sets)

D 2 M 2 W 2 T 1 LT 2 Y 1 16 Y

LAND ENVIRONMENT

1 Soi l In f ras t ructure

development Compact ion of so i l by ear th moving vehic les D 2 NM 1 L 1 T 1 ST 1 Y 1 2 N

2 Soi l S i te Clearance &

excavat ion Eros ion & modi f ica t ion o f sur face D 2 NM 1 L 1 T 1 ST 1 Y 1 2 N

3 Soi l excavated ear th & loose

construct ion mater ia ls Loss of topsoi l ( resource loss) D 2 NM 1 L 1 T 1 LT 2 Y 1 4 N

4 Soi l s torm water

Improper channel i zat ion may lead to loss of

fer t i le top so i l a long wi th sur face run-o f f and

subsequent loss of wate r ho ld ing and

in f i l t ra t ion capac i ty o f so i l

D 2 NM 1 L 1 T 1 LT 2 Y 1 4 N

5 Soi l Temporary s tay of

construct ion workers

Impact due to unt reated d ischarge of sewage &

Sol id waste in to the land D 2 NM 1 L 1 T 1 LT 2 Y 1 4 N

6 Soi l Construct ion waste &

MSW

Improper d isposal o f construct ion waste &

MSW into the land D 2 M 2 L 1 T 1 LT 2 Y 1 8 N

BIOILOGICAL ENVIRONMENT

1 Bio log ica l Si te Clearances &

Excavat ion

Loss of vegetat ion and loss of habi ta t o f faunal

spec ies ( resource loss) D 2 NM 1 L 1 P 2 LT 2 Y 1 8 N

2 Bio log ica l Construct ion Act iv i t ies** Vibrat ion due to movement / operat ion of heavy

machinery D 2 NM 1 L 1 T 1 ST 1 Y 1 2 N

3 Bio log ica l Temporary s tay of construct ion workers

Cut t ing of t rees, sh rubs etc . for procur ing f i re

wood by construct ion workers . ( resource loss) D 2 NM 1 L 1 P 2 LT 2 Y 1 8 N

SOCIO-ECONOMIC

1 Socio

Economic Temporary s tay of construct ion workers

Impact on nat i ve soc ia l fabr ic o f the s i te

surroundings l ike cu l tura l d ivers i t y, poss ib le

increase in ant i -soc ia l ac t iv i t ies etc .

D 2 NM 1 L 1 T 1 ST 1 Y 1 2 N

2 Socia l

Respons ib i l i ty Construct ion workers

Unhygienic s i te sani ta t ion fac i l i t ies may cause

heal th damage to construct ion workers D 2 M 2 W 2 T 1 LT 2 Y 1 16 Y

OTHERS

1 Aesthet ics Temporary s tay of construct ion workers

Construct ion of Improper / unaesthet ic labor

sheds/shel ters may impact aesthet ic

appearance of the s i te surroundings.

D 2 NM 1 L 1 P 2 ST 1 Y 1 4 N

2 Energy

Conservat ion Energy Consumpt ion

Use of energy in-ef f ic ien t bu i ld ing mater ia ls

may lead to h igher consumpt ion of e lec t r ic i t y in

a i r condi t ioned bui ld ings .

D 2 NM 1 W 2 P 2 LT 2 Y 1 16 Y

3 Energy

Conservat ion Energy Consumpt ion

Adopt ion of energy in-ef f ic ient vehic les , appl iances, l ights etc . may lead to wastage of energy

D 2 NM 1 L 1 T 1 ST 1 Y 1 2 N

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 4 Ant ic ipated Environmental Impacts & Mit igat ion Measures Page 4 - 20

4 Energy

Conservat ion Energy Consumpt ion

Improper or ien tat ion of the bui ld ing may lead to h igh energy consumpt ion due to h igh hea t ga in to the bui ld ing, dark zone & improper vent i la t ion

D 2 NM 1 L 1 T 1 ST 1 Y 1 2 N

5

Bui ld ing Mater ia l

Resource Conservat ion

Bui ld ing Mater ia l

consumpt ion

Use of far fe tched construct ion mater ia ls than

the loca l ly avai lab le construct ion mater ia ls may

lead to over explo i ta t ion of natura l resources &

increase in carbon foo tp r in t

D 2 NM 1 W 2 P 2 LT 2 Y 1 16 Y

6 Disaster

Management F i re & other hazards

Absence of proper f i re p rotect ion systems may

lead to f i re hazards D 2 NM 1 L 1 T 1 ST 1 Y 1 2 N

7 Disaster

Management F i re & other hazards

Absence of s ignages, mock dr i l ls & assembly

po ints D 2 NM 1 L 1 T 1 ST 1 Y 1 2 N

8 Disaster

Management F i re & other hazards

Absence of re levant s t ruc tura l safety measures

dur ing bui ld ing des ign may lead to damage to

bu i ld ings dur ing the na tura l ca lami t ies

D 2 NM 1 L 1 P 2 LT 2 Y 1 8 N

** Construction Activities (Foundation, Columns, beams, slab casting, brick work, plastering, flooring, electrical & plumbing works, painting & finishing) OPERATION PHASE: -

S

N

Impact on

Environment

Act ivity /

Aspect

Anticipated Impacts

Impact Classif ication

Direct (D) / Indirect ( ID)

Mandatory (M) / Not

Mandatory (NM)

Local(L)/ Widespread

(W)

Temporary(T)/ Permanent (P)

Long Term (LT) / short

term (ST)

Mit igation available

( Yes / No)

Total Marks

Obtained

Whether Signif ican

t or not

D/ID

Marks

M/NM

Marks

L/W

Marks

T/P

Marks

LT/ST

Marks

Y/N

Marks M1 X

M2..XM6 M1 M2 M3 M4 M5 M6

AIR ENVIRONMENT

1 Air On s i te Vehic le

Movement

Dust & gaseous emissions f rom vehic les

exhaust D 2 NM 1 L 1 P 2 LT 2 Y 1 8 N

2 Air

Point Source

emissions f rom

operat ion of DG

Sets

Part icu late Matter & Gaseous emissions

( including wors t condi t ion of operat ing a l l

DG sets)

D 2 M 2 W 2 T 1 LT 2 Y 1 16 Y

3 Air Munic ipal Sol id

W aste

Improper d isposal of sewage and MSW

may lead to odour & generat ion of gases

due to de-composi t ion

D 2 NM 1 L 1 P 2 LT 2 Y 1 8 N

WATER ENVIRONMENT

1 W ater water

consumpt ion

Impact on competing users due to

consumpt ion of publ ic supply / ground

water (resource loss)

D 2 NM 1 W 2 P 2 LT 2 Y 1 16 Y

2 W ater Operat ion of

HVAC Plant

Impact on competing users due to

consumpt ion of publ ic supply / ground

water as make-up water ( resource loss)

D 2 NM 1 W 2 P 2 LT 2 Y 1 16 Y

3 W ater sewage

Improper d ischarge of untreated sewage

may lead to impact on surface / ground

water qual i t y.

D 2 M 2 W 2 P 2 LT 2 Y 1 32 Y

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 4 Ant ic ipated Environmental Impacts & Mit igat ion Measures Page 4 - 21

4 W ater Munic ipal Sol id

W aste & Bio-

Medical W aste

Improper d isposal of MSW & BMW may

at trac t scavenger avifauna which may lead

to d issertat ions of nat ive avifauna

D 2 M 2 L 1 T 1 ST 1 Y 1 4 N

5 W ater e-waste

Improper storage & d isposal may lead to

leaching of heavy metals leading to

contaminat ion

D 2 M 2 W 2 P 2 LT 2 Y 1 32 Y

6 W ater Hazardous

W aste

Improper storage & d isposal may lead to

leaching of hazardous waste leading to

contaminat ion

D 2 M 2 W 2 P 2 LT 2 Y 1 32 Y

7 W ater storm water

Improper channel izat ion may lead to

contaminat ion of water body & c logging of

dra in may lead to f looding

D 2 NM 1 L 1 P 2 LT 2 Y 1 8 N

NOISE ENVIRONMENT

1 Noise Vehic le

Movement

Increase in Noise & Vibrat ion in

surrounding area D 2 NM 1 L 1 P 2 LT 2 Y 1 8 N

2 Noise Operat ion of

DG Sets

Noise & Vibrat ion f rom DG Sets due to

inadequate acoust ic enc losure D 2 M 2 L 1 T 1 ST 1 Y 1 4 N

3 Noise Operat ion of

HVAC Plant Noise & vibrat ion f rom HVAC Plant D 2 NM 1 L 1 P 2 LT 2 Y 1 8 N

LAND ENVIRONMENT

1 Soi l Munic ipal Sol id

W aste & Bio-Medical W aste

Improper d isposal of MSW & BMW may

lead to impact on land. D 2 M 2 L 1 P 2 LT 2 Y 1 16 Y

2 Soi l sewage Improper d ischarge of untreated sewage

may lead to impact on land. D 2 M 2 L 1 P 2 LT 2 Y 1 16 Y

3 Soi l e-waste

Improper storage & disposal may lead to

leaching of heavy metals leading to

contaminat ion

D 2 M 2 W 2 P 2 LT 2 Y 1 32 Y

4 Soi l Hazardous

W aste

Improper storage & disposal may lead to

leaching of hazardous waste leading to

contaminat ion

D 2 M 2 W 2 P 2 LT 2 Y 1 32 Y

5 Soi l Storm water Non-point sources of pol lu t ion l ike l i t ter ,

o i l & grease, loose ear th D 2 NM 1 L 1 P 2 LT 2 Y 1 8 N

6 Soi l s torm water

Clogging of storm water dra inage system

by s i l t & other mater ia l may lead to

f looding

D 2 NM 1 L 1 T 1 ST 1 Y 1 2 N

BIOLOGICAL ENVIRONMENT

1 Bio logical Vehic le

Movement

Increase in Noise & Vibrat ion in

surrounding area D 2 NM 1 L 1 T 1 ST 1 Y 1 2 N

2 Bio logical Munic ipal Sol id

W aste & Bio-

Medical W aste

Improper d isposal of MSW & BMW may

at trac t scavenger avifauna which may lead

to d issertat ions of nat ive avifauna

D 2 M 2 L 1 P 2 LT 2 Y 1 16 Y

OTHER ASPECTS

1 Aesthet ics Munic ipal Sol id

W aste & Bio-

Medical W aste

Improper d isposal of MSW & BMW may

lead to un-aesthet ic condit ions D 2 M 2 L 1 P 2 LT 2 Y 1 16 Y

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 4 Ant ic ipated Environmental Impacts & Mit igat ion Measures Page 4 - 22

2 Energy

Conservat ion Consumption of

Energy

Adopt ion of energy in-ef f ic ient vehic les ,

HVAC system, appl iances, l ights etc may

lead to wastage of energy

D 2 NM 1 W 2 P 2 LT 2 Y 1 16 Y

3 Energy

Conservat ion Consumption of

Energy

Non adopt ion of renewable sources of

energy l ike solar energy may lead to

increase dependency on publ ic supply may

lead to consumpt ion of energy by

compet ing users

D 2 NM 1 W 2 P 2 LT 2 Y 1 16 Y

4 Disaster

management Fire & other

hazards

Absence of tra ined personnel & mock dr i l ls

may lead to major f i re acc idents & non

maintenance of sys tem

D 2 NM 1 L 1 P 2 LT 2 Y 1 8 N

SOCIO- ECONOMIC ( ALL POSITIVE IMPACTS)

S.

No

.

Impact on

Environment

Activity /

Aspect

Anticipated Impacts

Impact Classif ication

Direct (D) / Indirect ( ID)

Posit ive (P) / Negative (N)

Local(L)/ Widespread

(W)

Temporary(T)/ Permanent (P)

Long Term (LT) / short

term (ST)

Mit igation available

( Yes / No)

Total Marks

Obtained

D/ID Marks

P/N Marks

L/W Marks

T/P Marks

LT/ST Marks

Y/N Marks M1 X

M2..XM6 M1 M2 M3 M4 M5 M6

1 Socio

Economic bus iness

act iv i t ies

Increased revenue to the State & Local Self

Government by way of taxes and dut ies leading to

inf rastruc ture development & bet ter c iv ic ameni t ies

D 2 P 1 W 2 P 2 LT 2 Y 1 16

2 Socio

Economic bus iness

act iv i t ies

Expans ion of ex ist ing hospita l ac t iv i t ies may lead to

increase in employment oppor tuni ty / new job creat ion

(d irec t & indirect) for the local community

D 2 P 1 L 1 P 2 LT 2 Y 1 8

3 Socio

Economic bus iness

act iv i t ies

Increased bus iness act iv i t ies at s i te may lead to

improved publ ic transport inf rastructure in the region

may improve the l i fe s tyle and connect iv i t y o f the local

community

D 2 P 1 W 2 P 2 LT 2 Y 1 16

4 Socio

Economic Medical

Fac i l i t y

Due to the development of hospi ta l project , the bet ter

medical t reatment fac i l i t y wi l l be avai lable to the local

populat ion

D 2 P 1 W 2 P 2 LT 2 Y 1 16

M/s SREEV ALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 4 Antic ipated Environmenta l Impacts & Mit igat ion Measures Page 4 - 23

4.7 List of significant Environmental impacts

Based on the cr iter ia of cut-off of 16 marks, the impacts having less than

16 marks are considered as insignif icant impact and the impacts having

16 or more marks are considered as signif icant environmental impacts.

Out of the total number of 64 Environmental impacts identif ied

(construct ion & operation phase together), after applying the above

mentioned signif icance criteria, 20 Nos. (6 environmental impacts during

construction phase & 14 environmental impacts during operation phase)

are considered to be signif icant impacts.

The l ist of signif icant impact is given below :-

Table 4.5 : List of significant impacts identified

Construction Phase

S.

No.

Impact on

Environment Act ivi ty / Aspect Ant icipated Impacts

1 A ir

Point source emissions

from operat ion of DG

Sets

Part icu la te Mat ter & Gaseous emissions

( includ ing wors t condit ion of operat ing al l DG

sets)

2 Water Construct ion Act ivi t ies**

Impact on compet ing users due to large

consumpt ion of water for cur ing, dust

suppression, construct ion, domest ic use etc.

3 Noise Operat ion of DG Sets

Noise & Vibrat ion f rom DG Sets due to

inadequate acoust ic enclosure ( inc lud ing

worst condit ion of operat ing al l DG sets)

4 Social

Responsib i l i ty Construc t ion workers

Unhygien ic s i te sani tat i on f ac i l i t i es may cause

heal th damage to construc t ion workers

5 Energy

Conservat ion Energy Consumpt ion

Use of energy in-eff ic ient bu i ld ing mater ia ls

may lead to h igher consumpt ion of e lect r ic i t y

in a ir condit ioned bui ld ings.

6

Bui ld ing Mater ia l

Resource Conservat ion

Bui ld ing Mater ial

consumpt ion

Use of far fe tched construct ion mater ia ls than

the loca l ly avai lab le construct ion mater ia ls

may lead to over explo itat ion of natura l

resources & increase in carbon footpr in t

** Construction Activities (Foundation, Columns, beams, slab casting, brick work, plastering, flooring, electrical & plumbing works, painting & finishing)

M/s SREEV ALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 4 Antic ipated Environmenta l Impacts & Mit igat ion Measures Page 4 - 24

Operation Phase: -

S.

N.

Impact on

Environment Activi ty / Aspect Ant icipated Impacts

1. Air Point Source

emissions f rom

operat ion of DG Sets

Part icu la te Mat ter & Gaseous emissions ( includ ing

worst condit ion of operat ing al l DG sets)

2. Water water consumpt ion Impact on compet ing users due to consumption of

publ ic supply / ground water ( resource loss)

3. Water Operat ion of HVAC

Plant

Impact on compet ing users due to consumption of

publ ic supply / ground water as make-up water

( resource loss)

4. Water sewage Improper d ischarge of untreated sewage may lead

to impact on sur face / ground water qual it y.

5. Water e-waste Improper storage & d isposal may lead to leaching

of heavy meta ls leading to contaminat ion

6. Water Hazardous W aste Improper storage & d isposal may lead to leaching

of hazardous waste leading to contaminat ion

7. Soi l Munic ipa l Sol id W aste & B io-Medical Waste

Improper disposal of munic ipa l so l id waste & bio-

medica l waste may lead to impact on land.

8. Soi l sewage Improper d ischarge of untreated sewage may lead

to impact on land.

9. Soi l e-waste Improper storage & d isposal may lead to leaching

of heavy meta ls leading to contaminat ion

10. Soi l Hazardous W aste Improper storage & d isposal may lead to leaching

of hazardous waste leading to contaminat ion

11. Biologica l Munic ipa l Sol id W aste

& B io-Medical Waste

Improper d isposal o f MSW & BMW may at t ract

scavenger avi fauna which may lead to

d isser ta t ions of nat ive avi fauna

12. Aesthet ics Munic ipa l Sol id W aste Improper d isposal o f MSW may lead to un-

aesthet ic condit ions

13.Energy

Conservat ion Consumption of

Energy

Adopt ion of energy in-eff ic ient vehic les, HVAC

system, appl iances, l ights e tc may lead to

wastage of energy

14.Energy

Conservat ion Consumption of

Energy

Non adopt ion of renewable sources of energy l ike

so lar energy may lead to increase dependency on

publ ic supply may lead to consumpt ion of energy

by compet ing users

4.8 Mitigation measures for the significant impacts identified

The mitigation measures for the signif icant impacts identif ied during

construction and operation phase are summarized in the Table 4.6 &

Table 4.7.

M/s SREEV ALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 4 Antic ipated Environmenta l Impacts & Mit igat ion Measures Page 4 - 25

Table 4.6 - Mitigation measures for the significant impacts identified during Construction Phase

Sr. No

Impact on Envir.

Anticipated Impacts Mitigation Measures

1 Air Particulate Matter & Gaseous emissions from DG Sets.

� Stack height as per CPCB Standards. � Promotion of use of cleaner fuel � All DG set should comply emissions

norms noti f ied by MoEF / CPCB.

2 Water

Impact on competing users due to large consumption of water for curing, dust suppression, construction, domestic use etc.

� To avoid wastage of cur ing water , following procedures are suggested: -

• Curing water should be sprayed on concrete structures: f ree f low of water should not be al lowed for cur ing.

• Af ter l iberal cur ing on the f irst day, al l concrete structures should be painted with curing chemical to save water . This wil l s top dai ly water curing.

• Concrete structures should be covered with thick c loth / gunny bags and then water should be sprayed on them. This would avoid water rebound and wi l l ensure sustained and complete curing.

• Ponds should be made using cement and sand mortar to avoid water f lowing away f rom the f lat surface while curing.

• Water ponding should be done on al l sunken slabs, th is would also highl ight the importance of having an impervious formwork.

� Estimation of daily water consumption based on the population, reuse and recycled options, quanti f icat ion of waste water , requirement of construction water, etc.

� Moni tor ing water use: Use of water meter conforming to ISO Standards would be insta l led at the inlet point of water uptake and at the discharge point to monitor the dai ly water consumption.

� Use of rain water for domestic purposes in the labour colony & for construction purposes.

� Use of treated water f rom STP of labour colony for construction purposes.

3 Noise

Noise & Vibrat ion from DG Sets due to inadequate acoustic enclosure

� Use of DG Sets wi th appropriate acoustic enclosures

� Use of ant i v ibrat ion pads

M/s SREEV ALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 4 Antic ipated Environmenta l Impacts & Mit igat ion Measures Page 4 - 26

4 Socio

Economic

Unhygienic s ite sanitat ion facil i t ies may cause health damage to construction workers

The objective is to ensure health and safety of the workers with ef fective provis ions for the basic faci l i t ies of sanitat ion, dr inking water , safety of equipments or machinery etc. Fol lowing are some of the recommendations:- � Comply with the safety procedures, norms

and guidel ines (as appl icable) as outl ined in the National Bui ld ing Code of India, Bureau of Indian Standards.

� Provide c lean dr inking water to a ll workers.

� Provide adequate number of decentral ized latr ines and ur inals.

� Guarding al l parts of dangerous machinery.

� Precautions for working on machinery. � Maintaining hoists and l if ts , l i f t ing

machines, chains, ropes and other l i f t ing tackles in good condition.

� Durable and reusable formwork systems to replace timber formwork and ensure that formwork where used is proper ly maintained.

� Ensuring that walk ing surfaces or boards at height are of sound construct ion and are provided wi th safety rai ls or belts.

� Provide measures to prevent f ires. F ire f ight ing ext inguishers and buckets of sand to be provided in the f ire prone area and elsewhere.

� Provide suff ic ient and suitable l ight for working during night t ime.

5 Energy

Conservat i on

Use of energy in-eff ic ient bui lding materia ls may lead to higher consumption of electr ici ty in a ir conditioned buildings.

� Use of bui ld ing materia l for roof , wal ls & glass ( R & U values) as per BEE for less heat gain in air conditioned buildings.

6

Bui lding Mater ia l

Resource Conservat i o

n

Use of farfetched construction materia l than local ly avai lable construction materia l may lead to over explo itat ion of natural resources & increase in carbon footprint

� Use of local ly avai lable construct ion materia ls.

** Construction Activit ies (Foundation, Columns, beams, slab casting,

brick work, plaster ing, f looring, electrical & plumbing works, paint ing &

finishing).

M/s SREEV ALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 4 Antic ipated Environmenta l Impacts & Mit igat ion Measures Page 4 - 27

Table 4.7 - Mitigation measures for the significant impacts identified during Operation Phase

Sr. No.

Impact on Env.

Anticipated Impacts Mitigation Measures

1 Air

Particulate Matter & Gaseous emissions ( including worst condition of operating al l DG sets)

� Stack height as per CPCB Standards. � Development of a dense belt (vegetat ion

buffer) in the project s ite. � Promotion of use of cleaner fuel � All DG set should comply emissions norms

noti f ied by MoEF / CPCB.

2 Water

Impact on competing users due to consumption of publ ic supply / ground water (resource loss) for domestic consumption in the campus

� Estimation of dai ly water consumption based on the populat ion, reuse and recycled options, quantif icat ion of waste water etc.

� Moni tor ing water use: Use of water meter conforming to ISO Standards would be instal led at the in let point of water uptake and at the discharge point to monitor the dai ly water consumption.

� Use of water saving devices / f ixtures: Low water consumption f ix tures l ike low f low f lushing systems, sensor based f ixtures, water less ur inals, tap aerators etc. to reduce the water usage.

� Instal lat ion of dual plumbing for using recycled water.

� Use of rain water

3 Water

Impact on competing users due to consumption of publ ic supply / ground water as make-up water for HVAC in the campus (resource loss)

� Estimation of dai ly water consumption based on the HVAC losses, reuse and recycled options.

� Moni tor ing water use: Use of water meter conforming to ISO Standards would be instal led at the in let point of water uptake and at the discharge point to monitor the dai ly water consumption in HVAC unit .

� Use of treated water for STP as make-up water in HVAC system.

� Use of rain water

4 Water

Improper discharge of untreated sewage may lead to impact on surface / ground water quali ty

� Treatment of sewage and recycl ing of the treated sewage and ensuring zero discharge.

� Sewage treatment p lant proposed. � Treatment unit with primary, secondary

and terr i tory treatment proposed

5 Water

Improper storage & disposal of e-waste may lead to leaching of heavy metals leading to contamination

� Storage of e-waste as per Rules and in an isolated area.

� Disposal of e- waste only to the author ized agency

� MoU with the approved agency to be made.

M/s SREEV ALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 4 Antic ipated Environmenta l Impacts & Mit igat ion Measures Page 4 - 28

6 Water

Improper storage & disposal may lead to leaching of hazardous waste leading to contamination

� Development of leachate proof intermediate hazardous storage facil i ty.

� Outsourcing of the hazardous waste to the Kerala Pollution Control Board approved agency & MoU to be made wi th the approved agency.

7 Soi l Improper disposal of MSW & BMW waste may lead to impact on land.

� Segregation of waste at source into medical, b iodegradable and non biodegradable waste by providing colored bins.

� Medical waste wil l be disposed of f through KSPCB approved vendors

� Disposal of biodegradable Munic ipal Sol id Waste by bio gas uni t .

� Disposal of non biodegradable recyclable waste to vendors.

� Disposal of iner t waste by land f i l l ing / back f i l l ing.

� For Bio-medical waste - Col lect ion & segregation at source by provid ing appropriate colour coded bins / containers as per the colour coding provided in the Bio-Medical Waste (Management & Handl ing) Rules.

� The Bio-medical waste f rom the proposed hospital would be outsourced through a Kerala State Pollut ion Control Board author ized agency (M/s Indian Medical Associat ion Goes Eco Fr iendly, IMAGE)

8 Soil Improper discharge of untreated sewage may lead to impact on land.

� Treatment of sewage and recycl ing of the treated sewage and ensuring zero discharge.

9 Soi l

Improper storage & disposal of e-waste may lead to leaching of heavy metals leading to contamination

� Storage of e-waste as per Rules and in an isolated area.

� Disposal of e- waste only to the author ized agency & MoU to be made wi th the agency.

10 Soil

Improper storage & disposal of hazardous waste may lead to leaching of waste leading to contamination

� Development of leachate proof intermediate hazardous storage facil i ty.

� Outsourcing of the hazardous waste to the Kerala Pollution Control Board approved agency & MoU to be made wi th the concerned agency.

M/s SREEV ALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 4 Antic ipated Environmenta l Impacts & Mit igat ion Measures Page 4 - 29

11 Biological

Improper disposal of MSW & BMW may attract scavenger avifauna which may lead to dissertat ions of nat ive avifauna

� Segregation of waste at source into medical, b iodegradable and non biodegradable waste by providing colored bins.

� Disposal of biodegradable Munic ipal Sol id Waste by bio gas uni t & bio-bin system.

� Disposal of non biodegradable recyclable waste to vendors.

� Disposal of iner t waste by land f i l l ing / back f i l l ing.

� Plantation of nat ive species of trees / shrubs / herbs / grass for enhancement of avifauna

� Conservation of the exist ing trees wherever possible.

� Plantation of f ruit bearing trees to enhance the avifauna.

� For Bio-medical waste - Col lect ion & segregation at source by provid ing appropriate colour coded bins / containers as per the colour coding provided in the Bio-Medical Waste (Management & Handl ing) Rules.

� The Bio-medical waste f rom the exist ing hospital outsourced through a Kerala State Pollution Control Board author ized agency (M/s Indian Medical Association Goes Eco Friendly, IMAGE) and the same arrangement wil l be continue for expansion facil i ty also.

12 Aesthet ics Improper disposal of MSW may lead to un-aesthetic condit ions

� Segregation of waste at source into biodegradable and non biodegradable waste by provid ing colored bins.

� Disposal of biodegradable Munic ipal Sol id Waste by bio gas uni t .

� Disposal of non biodegradable recyclable waste to vendors.

� Disposal of iner t waste by land f i l l ing / back f i l l ing.

13 Energy

Conservation

Adoption of energy in-eff ic ient vehic les, HVAC system, appliances, l ights etc may lead to wastage of energy

� Use of Euro-II I Standard vehic les. � HVAC system and appl iances with 5 Star

Rating as per BEE.

M/s SREEV ALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 4 Antic ipated Environmenta l Impacts & Mit igat ion Measures Page 4 - 30

14 Energy

Conservation

Non adoption of renewable sources of energy l ike solar energy may lead to increase dependency on publ ic supply may lead to consumption of energy by competing users

� Use of Solar energy for water heating � Use of solar energy for common area

light ing in parks and in streets. � Use of solar power plant for common area

light ing in campus.

*******************************************************************************

CHAPTER – 5

ANALYSIS OF ALTERNATIVES

(TECHNOLOGY AND SITE)

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 5 Analysis of Al ternat ives (Technology and Site) Page 5 - 1

5.0 ANALYSIS OF ALTERNATIVES (TECHONOLOGY AND SITE)

5.1 Introduction

M/s Sreevalsam Educational Trust proposed an expansion of exist ing

Hospital cum Medical Col lege project at Edappal Vil lage, Ponnani Taluk,

Malappuram District, Kerala. The plot area of the Hospital cum Medical

College Project is 9.4534 ha (94,534.56 sq. m.) and the total built -up

area is 1,38,937.50 sq. m. (exist ing 53,889.72 sq.m. + proposed

85,047.78 sq.m.). The building construct ion of 53,889.72 sq.m. of the

project is already completed.

The present project is one of the more proactive side of environmental

assessment – enhancing the project through examining opt ions instead of

only focusing on the more defensive task of reducing adverse impacts of a

single opt ion of the project. This requires systematic comparison of the

feasible alternat ives for technology and operat ional alternatives.

Alternat ives are compared in terms of their potential environmental

impacts, capital and recurring costs, suitabi lity under local condit ions etc.

For examining the alternatives for carrying out a project, the following

aspects should be kept into consideration:

(i) Type of the alternatives.

(i i) Environment impacts associated with each alternative.

(i i i ) Rationale for select ing the preferred alternative.

This Chapter deals with the analysis of alternat ives (technology and site)

( if any).

5.2 Alternative Sites

The construct ion of new buildings are within the existing plot area of

9.4534 hectares.

The project proponent considering the need of the project at that area,

hence no alternat ive site is required for the project. The reasons

favorable for sett ing-up this project is located at Edappal Vil lage, Ponnani

Taluk, Malappuram District, Kerala are :

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 5 Analysis of Al ternat ives (Technology and Site) Page 5 - 2

� The project wil l cater to the demand for economical and better

hospital and inst itutional faci l ity.

� The site is located in high medical services demand area.

� There wil l be easy access to the patients / staff / local populat ion

for fulf i l l ing their medical demand being near to the residence /

off ice / work station to avail the facil i ty.

� The proposed site is found to be away from any ecologically

sensit ive / protected areas.

Owing to the various above advantages, the site was selected for the

development of facil i t ies / act iv it ies.

There are no archaeological, historical, cultural or defense instal lations

within 10 km from the project boundary. There is no national park or

wi ldl i fe sanctuary / ecologically sensit ive area within 10 km from the

project boundary. The site area is not part of any f lood plain nor in the

land sl ide vulnerable zone as per the hazard zonation map published by

State Disaster Management Authority. The proposed project is an

expansion of exist ing hospital cum medical col lege. There is no resident /

human sett lement within the site and hence there is no rehabili tation. Due

to the above mentioned reasons, there is no need for alternative site.

5.3 Alternatives in Technology

The project relates the construct ion and development of hospital cum

medical college project with supporting infrastructural facil it ies for

creat ing faci l it ies with an easy access to the people as there is high

demand of medical cum institutional building in the area. The project

proponent has adopted state-of-the-Art Technology considering the

requirement of the project and environmental aspects related to the

construction and operation of the project.

*******************************************************************************

CHAPTER – 6

ENVIRONMENTAL MONITORING

PROGRAM

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 6 Environment Monitor ing Program Page 6 - 1

6.0 ENVIRONMENT MONITORING PROGRAM

6.1 Introduction

The purpose of the monitor ing program is to ensure that the specif ied

mitigative measures are performing well and leading to the desired

benefits for the target area and its populat ion. To ensure the effective

implementat ion of the EMP and gauge the eff iciency of the mitigat ive

measures, monitor ing shall be undertaken both during the construction

and operation phase of the proposed expansion of hospital project.

6.1.1 Performance Indicators (PIs)

The physical, biological and social indicators are generally particular

signif icance to the construction projects are:-

• Air quality

• Water quali ty

• Noise levels

• Solid Waste Management

• Replantat ion success / survival rate

The Indicators that are found to be signif icant for the assessment study of

this development are as follows:-

• Water Quality

• Air Quali ty

• Noise levels

• Flora

To ensure the effect ive implementat ion of the mit igation measures and

environmental management during construction and operation phase of

project, it is essential that an effective Environmental Monitoring Plan be

designed.

6.1.1.1 Water Quality Monitoring

The physical, chemical & biological parameters recommended for analysis

of water qual ity relevant to the proposed expansion project as per the

required parameters. The locations, duration and the pollution parameters

to be monitored are detai led in the Environmental Monitor ing Plan. The

results of analysis are to be compared against IS 10500 for ground water

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 6 Environment Monitor ing Program Page 6 - 2

samples, and general standards of discharge or as per SPCB

specif icat ions for STP treated water.

6.1.1.2 Ambient Air Quality (AAQ) Monitoring

Ambient air quality parameters recommended for monitoring with regard

to constructional activ it ies are PM10 & PM2 .5, SO2 , NO2 & CO. Monitoring

shall be carr ied out once in a seasons in accordance to the National

Ambient Air Quantity Standards. The locations with the pol lution

parameters to be monitored are detailed out in the Environmental

Monitoring Plan.

6.1.1.3 Noise Level Monitoring

The measurements of noise levels wil l be carried out at al l designated

locations in accordance to the ambient Noise Standards formulated by

MoEF as given. Noise level wil l be monitored on twenty-four hourly basis.

Noise should be recorded at “A” weighted frequency using a slow t ime

response mode of the measuring instrument.

6.1.1.4 Success of Vegetation

To ensure the proper maintenance and monitoring of the proposed

plantation act ivit ies, a regular survey of the survival rate of the planted /

transplanted trees is being proposed up-to a period of 5-7 years from the

start of operat ion of the project.

The measurement location, durat ion and the pollution parameters to be

monitored are detailed in the Environmental Monitoring Plan (Table 6.1

& 6.2).

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 6 Environment Monitor ing Program Page 6 - 3

Table 6.1 - Environment Monitoring Action Plan

Sr.

No.

Potential

impacts Action

Parameters for

monitoring

I. Construction Phase

1.

Air Emissions

All equipments to be operated

within specif ied design

parameters

Random checks of

equipment logs/manuals

Vehic le tr ips to be minimized to

the extent possible

Vehic le logs

Any dry, dusty materia ls to be

stored in sealed containers or

prevented f rom blowing.

Absence of stockpiles or

open containers of dusty

materials.

Compaction of soi l dur ing various

construction act iv i t ies

Construction logs

Ambient air quali ty wi thin the

premises of the proposed unit to

be monitored.

The air qual i ty wi l l

conform to the standards

for PM1 0 , PM2 .5 , SO2 and

NO2 , CO

2.

Noise

List of a ll noise generat ing

machinery onsite along with age

to be prepared. Equipment to be

maintained in good working order.

Equipment logs, noise

reading

Night working is to be minimized. Working hour records

Generation of vehicular noise Maintenance records of

vehic les

Implement good working practices

(equipment select ion and s it t ing)

to minimize noise and also reduce

i ts impacts on human heal th (ear

muffs, safe distances, and

enclosures).

Site working practices

records, noise reading

No machinery running when not

required.

Acoustic muff lers / enclosures to Muff lers / enclosures in

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 6 Environment Monitor ing Program Page 6 - 4

Sr.

No.

Potential

impacts Action

Parameters for

monitoring

be provided in large engines place

Noise to be monitored in ambient

air within the plant premises.

Noise reading

The noise level wi l l not exceed

the permissible l im it both during

day and night t imes.

All equipments operated with in

specif ied design parameters.

Random checks of

equipment logs / manuals

Vehic le tr ips to be minimized to

the extent possible

Vehic le logs

3.

Waste water

Discharge

No treated or untreated discharge

to be made to surface water,

ground water or soi l

No discharge hoses in

vic ini ty of watercourses

4.

Soil Erosion

Minimize area extent of s i te

c learance, by staying with in the

def ined boundaries and to avoid

steep s lopes

Site boundaries not

extended / breached as

per plan document

Protect topsoi l s tockpi le where

possible at edge of s i te

Effective cover in p lace

5.

Drainage and

eff luent

Management

Ensure drainage system &

specif ic design measures are

working ef fectively. The design to

incorporate exist ing drainage

pattern and avoid any disturbing.

Visual inspection of

drainage and records

thereof

6.

Waste

Management

Implement waste management

plan that identif ies and

character izes every waste ar ising

associat ing wi th proposed

activi t ies and which identif ies the

procedures for collection handling

& disposal of each waste arising.

Comprehensive waste

management plan in

place and avai lable for

inspection on s ite.

Compliance with MSW

Rules and Hazardous

Waste (Management and

Handling Rules), 2016.

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 6 Environment Monitor ing Program Page 6 - 5

Sr.

No.

Potential

impacts Action

Parameters for

monitoring

The construction &

demoli t ion waste

management ru les, 2016

wi l l be follow during

construction phase.

7. Non-rout ine

events and cool

dental releases

Plan to be drawn considering

likely emergencies and steps

required to prevent / l imit

consequences

Mock dr i l ls and records

of the same

8.

Environmental

Management

Cell /Unit

The Environmental Management

Cell / Unit is to be set up to

ensure implementat ion and

monitor ing of environmental

safeguards.

Formation of

Environment

Management Cell by the

project proponent

I I. Operat ional Phase

1.

Air Emissions Stack emissions f rom DG set to

be optimized and monitored

The ambient air qual i ty

wi l l conform to the

standard for PM1 0 &

PM2 . 5 SO2 , and NOx, CO

Ambient air quali ty wi thin the

premises of the proposed unit to

be monitored.

Exhaust f rom vehic les to be

minimized by use of fuel ef f ic ient

vehic les and well maintained

vehic les having PUC cert i f icate.

The ambient air qual i ty

wi l l conform to the

standards for PM1 0 &

PM2 . 5 as given by PCC*

Vehic les logs to be

maintained

Promotion of cycle tracks Providing eff ic ient cyc les

to the staf f & vis i tors by

the proponent.

Promotion of water transport Scheduled maintenance

Promotion of pedestr ian walkways

& pathways

Scheduled maintenance

of pedestr ian walkways &

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 6 Environment Monitor ing Program Page 6 - 6

Sr.

No.

Potential

impacts Action

Parameters for

monitoring

pathways

Vehic le tr ips to be minimized to

the extent possible

Vehic le logs

2. Noise Noise generated f rom operation

of DG set to be optimized and

monitored DG sets to generate

less than 75 dB(A) Leg at 1.0 m

f rom the source DG sets are to be

provided at service bui lding with

a acoustic enclosures with height

of chimney above roof level or as

specif ied by SPCB

Maintain records of

vehic les

Generation of vehicular noise Maintain records of

vehic les

3. Wastewater

Discharge

No untreated discharge to be

made to surface water,

groundwater or soi l

No discharge hoses in

vic ini ty of watercourses

4.

Storm water

Drainage

Management

Ensure storm water drainage

system and specif ic design

measures are working ef fect ively.

Design to incorporate exist ing

natural drainage pattern and

avoid disturbing the same.

Visual inspection of

drainage and records

thereof

5.

Indoor a ir

contamination

Contaminants such as CO, CO2

and VOCs to be reduced by

providing adequate venti lat ion.

Monitor ing of indoor air

contaminants such as

CO, CO2 and VOCs

6.

Energy Usage

Energy usage for air -condit ioning

and other activi t ies to be

minimized Conduct annual energy

audit for the bui ldings

Findings of energy audi t

report

7.

Emergency

Fire protection and safety

measures to take care to f ire and

Mock dr i l l records, on

site emergency plan,

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 6 Environment Monitor ing Program Page 6 - 7

Sr.

No.

Potential

impacts Action

Parameters for

monitoring

preparedness,

such as f ire

f ight ing

explosion hazards to be assessed

and steps taken for their

prevention.

evacuation plan

8.

Environment

Management

Cell /Unit

The Environment Management

Cell /Unit to be set up to ensure

implementat ion and monitor ing of

Environmental safeguards

Formation of

Environment

Management Cell by the

project proponent

9 Waste

Management

Implement waste management

plan that identif ies and

character izes every waste ar ising

associat ing wi th proposed

activi t ies and which identif ies the

procedures for collection handling

& disposal of each waste arising.

Comprehensive waste

management plan in

place and avai lable for

inspection on s ite.

Compliance with MSW

Rules and Hazardous

Waste (Management and

Handling Rules), 2016.

Being a hospi tal project,

the project wil l fol low the

compliance wi th Bio-

medical waste

(Management and

Handling Rules).

Also, fol low the E-waste

Management Rules for

the disposal of E-waste

from the s ite.

*especial ly at locat ion AQL (where maximum GLC concentrat ion was

predicted through AAQ modeling).

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 6 Environment Monitor ing Program Page 6 - 8

Table 6.2: Environment Monitoring Plan with Budgetary Allocation

CONSTRUCTION PHASE

Sr.

No. Particulars Parameters Frequency

Approx.

Recurring cost

/ Annum

(Rs. In Lacs)

1. Ambient Air

(5 locations)

PM1 0 & PM2 . 5 ,

SO2 , NO2 , CO

Once in a

season 2.0

2. Pond water & Well water As per IS :

10500

Once in a

season 3.0

3. Noise Level

(5 locations)

24 Hrs. Noise

Level

Once in a

season 0.8

TOTAL 5.80

OPERATION PHASE

Sr.

No. Particulars Parameters Frequency

Approx.

Recurring

Cost / Annum

(Rs. In Lacs)

1. Ambient Air

(5 locations)

PM1 0 & PM2 .5 ,

SO2 , NO2 , CO

Once in a

season 2.00

2. Stack Emission

of D.G. sets SPM, SO2 , NOx

Once in a

year 0.5

3. Treated Water

f rom STP / ETP

pH, BOD, COD, Oil &

Grease, TSS,

bacter iological

parameters

Once in a

month 1.0

4. Stored rain water

& Well water As per IS : 10500

Once in a

season 3.0

5. Noise Level 24 Hrs. Noise Level Once in a

season 0.8

6. Ecological

monitor ing

Floral & faunal

species

Once in

three years 2.0

TOTAL 9.30

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 6 Environment Monitor ing Program Page 6 - 9

6.2 Data Management

The monitoring shall be carried out through MoEF / NABL approved

laboratory. All results shall be maintained at the project s ite.

6.3 Reporting Schedule

The environment management cell shall be responsible for t imely conduct

of the monitor ing activit ies. The results of the analysis shall be intimated

to the project head. Any anomaly in test results shall be investigated into

and proper correct ive actions shall be undertaken.

A complaint register shall also be maintained to note any complaints from

the Sreevalsam Educational Trust or any other stakeholder. Corrective

act ions taken against the complaints shall also be noted.

6.4 Emergency

Alarming levels of pollutants in any of the monitored component may raise

alarm in the hospital campus. However, such information should be made

available to the occupants through not ices and with the help of Project

Management Cell. The latter may also be consulted on necessary steps to

be taken on an immediate and long term basis to t ide over the problem.

*******************************************************************************

CHAPTER – 7

ADDITIONAL STUDIES

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 7 Addit ional Studies Page 7 - 1

7.0 ADDITIONAL STUDIES

7.1 Introduction

This chapter broadly looks at various aspects related to Risk & Disaster

Management, Resource & Energy Conservation and Traff ic Impact

Assessment Study, Social Impact, Corporate Environment Responsibi l ity

(CER) activit ies, Rehabil i tat ion & Resett lement (R&R) Action Plan and

Public Hearing.

7.2 Risk Assessment and Disaster Management Plan

7.2.1 Need and Plans

The instant project is expansion of existing hospital cum medical col lege

project encompasses the staff / patient / visiting, medical students of a

large number of people in it . The development project also involves

instal lat ion of various structures and machineries that meet the comfort

and need of its populat ion but may also pose serious threat to the

occupants in case of accidents. It is thus considered necessary to carry

out a risk assessment and prepare a disaster management plan for the

project.

The planning and construct ion of the buildings fol low all the safety norms,

it may not be always possible to total ly el iminate the risks of eventuali t ies

and fai lures of equipment or human errors. An essential part of major

hazard control has therefore, to be concerned with mit igat ing the effects

of such emergency and restoration of normalcy at the earliest.

The overall object ive of an Emergency Response Plan (ERP) is to make

uses of combined resources at s ite and outside to achieve the following:

1. To localize the emergency and if possible el iminate it ;

2. To minimize the effects of the accident on people and property;

3. Effect the rescue and medical treatment of casualt ies;

4. Safeguard other people;

5. Evacuate people to safe areas;

6. Informing and collaborating with statutory authorit ies;

7. Init ial ly contain and ult imately bring the incident under control;

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 7 Addit ional Studies Page 7 - 2

8. Preserve relevant records and equipment for the subsequent enquiry

into the cause and circumstances of the emergency;

9. Investigat ing and taking steps to prevent reoccurrence

The ERP is therefore related to identif ication of sources from which

hazards can arise and the maximum credible loss scenario that can take

place in the concerned area. The plan taken into account the maximum

credible loss scenario - act ions that can successfully mitigate the effects

of losses/ emergency need to be well planned so that they would require

less effort and resources to control and terminate emergencies, should

the same occur. Main hazards ident if ied for the project include hazards

pertaining to f ires in buildings and f ire in diesel storage areas, earthquake

and LPG leakage and an ERP pertaining to these is described in the

following sect ion.

7.2.2 Response in Case of Earthquake

Response Procedures for Occupants

If indoors:

1. Take cover under a piece of heavy furniture or against an inside wall

and hold on.

2. Stay inside: The most dangerous thing to do during the shaking of an

earthquake is to try to leave the building because objects can fal l on

you.

If outdoors:

Move into the open, away from buildings, street lights and ut il i ty wires.

Once in the open, stay there unti l the shaking stops.

If in a moving vehicle:

Stop quickly and stay in the vehicle. Move to a clear area away from

buildings, trees, overpasses, or ut i l ity wires. Once the shaking has

stopped, proceed with caut ion. Avoid bridges or ramps that might have

been damaged by the quake.

After the quake

1. After the quake be prepared for aftershocks.

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 7 Addit ional Studies Page 7 - 3

2. Although smaller than the main shock, aftershocks cause addit ional

damage and may bring weakened structures down. Aftershocks can

occur in f irst hours, days, weeks, or even months after the quake.

Help injured or trapped persons.

1. Give f irst aid where appropriate. Do not move seriously injured

persons unless they are in immediate danger of further injury. Call for

help.

2. Remember to help those who may require special assistance-- infants,

the elderly, and people with disabi lit ies.

3. Stay out of damaged buildings.

4. Use the telephone only for emergency calls.

Response Procedure for Emergency Team

1. Formulate an Emergency Response Team for earthquake response

2. Using the public address system, inform occupiers of response

procedures discussed above.

3. Inform the necessary authorit ies for aid

4. Ensure no residents are stuck beneath any debris, in case of a

structural fai lure.

5. Ensure that all residents standing outside near the buildings are taken

to open areas.

6. Ensure that the f irst aid ambulance and f ire tender vehicles are

summoned if necessary.

7. Inform the nearby hospitals if there are any injur ies.

8. Check the ut i l i t ies and storage tanks for any damage.

7.2.3 Status on natural disasters w.r.t. site and surroundings

There is no reported incident of any landslide, earthquake, cloud burst in the

project v icinity.

7.2.4 Response for LPG Leakage

1. The affected area should be evacuated and cordoned off immediately

2. Init iate an Emergency Response Team for LPG leakage.

3. Shut down the main valves in the gas bank, i f any in the kitchen etc.

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 7 Addit ional Studies Page 7 - 4

4. Ensure that only concerned personnel are present in the affected area

and al l other personnel and visitors are moved to the nearest assembly

points.

5. Rescue trapped personnel, also check if any personnel are

unconscious in the area and immediately move them outside and

provide f irst aid. Ambulance should be summoned to take injured

personnel to the hospital.

6. Personnel in the nearby buildings to close al l doors and windows to

prevent entry of the leaked gas.

7. Source of leakage to be traced and isolated from all other areas. And if

required use pedestal fans to bring down the gas concentration.

8. In case of a f ire fol low the instructions prescribed in case of f ire.

7.2.5 Response in case of Fire

1. Required response during in the event of a f ire should be described in

signs located in the lobby.

2. On sighting f ire, it should be immediately informed to the environment

manager giving the exact location and type of f ire in detail .

3. Init iate the Emergency Response Team for f ires.

4. If the f ire is small, engage in extinguishing the f ire using the nearest

f ire extinguisher.

5. Guide the Emergency Response Team staff to the emergency

assembly point.

6. The Emergency Response Team should immediately inform the nearest

dispensary and security force. If required a f ire tender should be

summoned.

7. The response team should immediately move to the point of f ire and

take al l necessary steps to stop the f i re. If the f ire is not control lable

and spreads then the manager in charge should inform the district

authorit ies and call for external help.

8. The Emergency Response Team wil l provide immediate rel ief to the

injured residents at the scene of incident. Any injured persons should

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 7 Addit ional Studies Page 7 - 5

be evacuated on priority to the dispensary or one of the nearest

hospitals based on their condit ion.

Instructions for Occupants

1. Get out of buildings as quickly and as safely as possible.

2. Use the stairs to escape. When evacuating, stay low to the ground.

3. If possible, cover mouth with a cloth to avoid inhaling smoke and

gases.

4. Close doors in each room after escaping to delay the spread of the f ire.

5. If in a room with a closed door.

6. If smoke is pouring in around the bottom of the door or if i t feels hot,

keep the door closed.

7. Open a window to escape or for fresh air while await ing rescue.

8. If there is no smoke at the bottom or top and the door is not hot, then

open the door slowly.

9. If there is too much smoke or f ire in the hall , slam the door shut.

10. Stay out of damaged buildings.

11. Check that al l wiring and ut il i t ies are safe.

A state of the art f ire f ighting system is proposed for the project to

prevent and control f ire outbreaks. The f ire f ight ing system wil l consist of

portable f ire ext inguishers, hose reel, wet riser, yard hydrant, automatic

sprinkler system, and manual f ire alarm system. The buildings wil l also be

provided with automatic f ire detection and alarm system. The format for

contact detai ls during emergency is given below :-

Sr. No. Name of agency Contact nos.

1. Police Station

2. Nearest other Medical Col lege / Hospital

3. Fire Station

4. Distr ict Collector, Malappuram

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 7 Addit ional Studies Page 7 - 6

In the event of occurrence of any such situat ion or condit ion in

Malappuram District, the Distr ict Collector, inter alia the chairman of the

Distr ict Disaster Management Authority (DDMA), has the authority to

exercise al l of the powers or any of the powers vested upon on him for

disaster preparedness /mit igation / or any such other activit ies as per the

DM ACT 2005 (District Disaster Management Authority, (DDMA) has the

authority to conceive, test and implement a District Disaster Management

Plan in accordance with the section 30 (2) I , i i & i i i of the DM act 2005 to

ensure effective management and response to any disaster.)

The structure of f low chart of Distr ict Disaster Management Authority

(DDMA) is given below Figure 7.1. The Act ion plan for crisis management

in District is provided in Figure 7.2. The l ist of names of various

funct ionaries with designation and telephone numbers shall be provided

as depicted in Figure 7.3,

Figure 7.1 Flow Chart of District Disaster Management Authority (DDMA)

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 7 Addit ional Studies Page 7 - 7

Figure 7.2 – Flow chart of Action plan for crisis management in District

Figure 7.3 : Flow chart of Incident Response Team

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 7 Addit ional Studies Page 7 - 8

Manmade disaster management of f ire :-

Description Details

No. of l if ts with capacity 4 nos X 15 passengers

= 60 Passengers

8 nos X 6 Passengers

= 48 Passengers

No. of stretcher l if ts with capacity 4 nos. x 20 Passengers = 80

passengers

No. of Fire exists with width of f ire exits 4 nos with 1.2 m wide

Distance from the farthest point to the

nearest f ire exit

33 m

No. of assembly points with area and no.

of persons the assembly point can

accommodate

788 sq.m assembly area to

accommodate about 2364

persons

Total no. of automatic sprinklers 1925

Total no. of f ire detectors / alarms 1370

Total no. of hooters 72

Name of nearest f i re stat ion

(Name & aerial distance)

Ponnani f ire stat ion

(about 9 km, W)

Relevant NBC code to be fol lowed NBC – Part 4

The project has obtained Fire NOC from the Fire & Rescue Department,

Govt. of Kerala and follow the norms.

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 7 Addit ional Studies Page 7 - 9

7.3 Resource Conservation

7.3.1 General approach

The proposed project is an expansion of exist ing hospital cum medical

college campus project will lead to uti l izat ion of various natural resources.

As an environmentally responsible corporate, the project proponent

endeavor to conserve these resources by judicious management and

recycling and strive to build up these resources where possible.

7.3.2 Water Resources – The project will use water supply and the stored

rain water tanks / ponds with total cumulat ive storage capacity of about

5,000 KL for of the project. Following means are proposed to be adopted

for conservat ion of this life sustaining resource:

• Minimum Ground water withdrawal: As informed, the present

project is a multi-storied resident ial building project. The exist ing

buildings as well as for proposed buildings have provision of storage of

rain water through tanks, therefore the water requirement of the site wil l

have minimal dependency of water from groundwater abstraction. As per

the classif icat ion by the CGWA, Ponnani Block in Malappuram district is

declared as “Safe Zone”. Hence the ground water available in the region

is ensure and to use of domestic purposes.

• Reduced use of water: To further minimize the use of avai lable

freshwater, various water eff icient f ixtures low f low f ixtures may be

provided such as Low f low f lushing systems, sensor based f ixtures,

waterless urinals, tap aerators.

• Treatment and Recycling: The wastewater generated from the

project site will be treated through Sewage Treatment Plant upto tert iary

level. This wil l enable the treated water from STP will be used for

f lushing, landscaping, boiler & for make-up water for cooling towers

attached with HVAC system requirements thereby reducing the

requirement of freshwater for these purposes.

• Rainwater harvesting: The increased hard surface of the proposed

project increases the runoff as compared to the otherwise vacant land. I t

is proposed to harvest this rainwater runoff while reducing the burden of

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 7 Addit ional Studies Page 7 - 10

storm water management of the project site. The stored rain water (in

tanks and pond) after treatment will be used to meet Non-f lushing

requirement. Also rain water harvest ing pits are constructed within the

site to recharge the ground water level.

7.3.3 Construction materials: As informed earl ier, the construction work

for the building was part ial ly completed. For the expansion purposes, the

project wil l require various kinds of natural construction materials such as

sand, gravel etc. These materials will procured from local market as per

requirement. This will also result in cost-eff iciency. Excavated soil from

the project s ite wil l used within the site. Country made bricks replaced

with cement blocks / hollow blocks. River sand replaced with

manufacturing sand from crusher.

7.3.4 Top soil as a resource: The top soil f rom the site was conserved.

The top soil from the areas where excavation carried out used for

landscaping within the site. There is exposed soil without vegetative cover

so as to prevent top soil erosion due to wind or by run-of f . The excavat ion

of earthwork wil l be done for the foundation of structures. The total

excavated of earth is 7,300 cum. The top soil (730 cum) which is fert i le

wi ll be kept at site for landscaping work. Part of the excavated soil will be

used for back f i l l ing work (4,380 cum) for site leveling and the remaining

quantity of 2190 cum wil l be used for internal road construct ion work.

Country made bricks replaced with cement blocks / hollow blocks

7.3.5 Energy as a resource: To conserve the energy resources, good

pract ices wil l be followed during the operation phase such as turning off

l ights and equipments when not in use, ensuring fuel eff iciency of motors

and vehicles through proper maintenance and minimal work at night. The

principles of energy conservation wil l also be embedded in the building

through use of energy eff icient f ixtures, maximum availabil ity of natural

l ight and use of solar energy.

It is proposed to install 200 KW solar l ight ing, 5000 Ltrs solar water

heaters.

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 7 Addit ional Studies Page 7 - 11

• Energy saving details from LED l ightings :-

Particulars Qty Energy Requirement as per Conventional l ight ing (100 watt)

Energy Requirement as per CFL/ LED

light ing (15 watt)

Total Energy Savings / day

Lighting Points

1036 1450 kWh/day 217 kWh/day 1233 kWh/day (85% saving)

• Solar l ight ing in green areas and in open parking :-

Particulars Qty Energy Requirement as per Conventional Systems (24 Nos.)

Energy Requirement after solar

l ight ing (24 nos.)

Total Energy Savings / day

Total no. of l ight ing points

60 144 kWh/day (@200 watts, 12 hrs. operation)

Nil 144 kWh/day (100 % saving)

• Other energy saving items :-

Roof (Area-3200M2) RCC with Thermal insulat ion

Saving 0.3 2lakhs kWh per year

Roof (Area 2500M2) Double glass with air cavity

Saving 2.5akhs kWh per year

High eff iciency Transformers Savings 2.2 lakhs kWh per year

7.4 Traffic Impact Assessment

Traffic and Access

The project site is within the Panchayat l imits of Edappal Grama

Panchayat. The nearest town is Edappal town which is about 2 km away

(N) from the site and the nearest city is Kozhikode city and is located

about 60 km (NW). The Ponnani taluk is located about 9 km in west

direction.

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 7 Addit ional Studies Page 7 - 12

The project would provide vehicle parking facil it ies within the project

premises. The parking plan for this project would follow KPBR guidel ines.

The total number of parking provided wil l be 1,184 Cars + 1,409

Two-wheelers within the site. There are provision of two separate wide

entry / exit point for the project for easy & smooth vehicular movement.

The suff icient parking provisions are made with the complex so that the

patient, students, vis itors & staff in hospital cum medical col lege wi ll not

disturb due to vehicular movement / parking.

The access to the project si te is from 10 m wide & 8 m wide road in the

northern direction of the site which are well connected to Thrissur-

Kutt ippuram Road located at about 1 km from the site in northern

direction.

The nearest National Highway is NH-17 (Edappally-Panvel Highway) at

about 2 km towards North direction and nearest State Highway is SH-69

(Thrissur-Kutt ippuram Rd.) at (Kaladi thara) about 0.7 km (E) away from

the site.

The nearest railway stat ion (Kutt ipuram Railway Stat ion) is about 10 km

(NE) and Calicut International Airport , Karipur is about 42 km (NE) away

from the project site.

Thereby, the road and by air connect ivity to the project is good.

Traffic study :-

Vehicular traff ic density survey was carried out on 19-11-2018 on

Thrissur-Kuttippuram Road and the survey report is provided below :-

Date :- 19-11-2018 (Thrissur to Kuttippuram)

TIME Cars Two

Wheelers

Three

Wheelers Buses LCV Trucks

8am – 9pm 30 24 9 8 6 17

9am – 10am 24 21 15 9 9 7

10am – 11am 15 27 10 4 18 12

11am – 12Noon 21 30 17 6 17 34

12Noon – 1pm 30 51 12 5 5 10

1pm – 2pm 15 39 19 6 6 14

2pm – 3pm 24 33 9 8 16 19

3pm – 4pm 6 39 15 9 30 21

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 7 Addit ional Studies Page 7 - 13

4pm – 5pm 30 15 9 12 14 Ni l

5pm - 6pm 8 51 14 5 6 24

6pm-7pm 12 36 12 3 8 17

7pm – 8pm 12 48 15 6 8 Ni l

Total Volume 227 414 156 81 143 175

In PCU* 227 207 125 284 315 613

Date :- 19-11-2018 (Kuttippuram to Thrissur)

TIME Cars Two

Wheelers

Three

Wheelers Buses LCV Trucks

8am – 9pm 34 27 29 12 7 Ni l

9am – 10am 20 29 40 10 12 7

10am – 11am 17 38 26 6 21 4

11am – 12Noon 18 28 28 5 24 28

12Noon – 1pm 32 44 18 8 9 34

1pm – 2pm 17 46 24 9 8 24

2pm – 3pm 20 40 28 12 19 26

3pm – 4pm 7 46 29 8 34 20

4pm – 5pm 34 24 7 17 19 11

5pm - 6pm 9 55 16 4 8 10

6pm-7pm 17 39 19 6 11 Ni l

7pm – 8pm 14 55 24 8 10 Ni l

Total Volume 239 471 288 105 182 164

In PCU* 239 236 230 368 400 574

*Values of PCU

Car 1.0

Motorcycle 0.5

LCV 2.2

Bus, Truck 3.5

3-wheeler 0.8

The above traff ic volume is within carrying capacity of road as per Indian

Road Congress (IRC) standards.

7.5 Social Impact Assessment

7.5.1 Introduction - Corporate Environment Responsibility

Community need assessments seek to gather accurate information

representative of the needs of a community. Assessments are performed

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 7 Addit ional Studies Page 7 - 14

prior to taking act ion and are used to determine current situat ions and

identify issues for act ion, establ ishing the essential foundation for vital

planning. The process is an invaluable tool for involving the public in

solving problems and developing goals.

To gather accurate information and ident ify the needs of the nearby

community to the project site, a community need assessment study was

carried out by Socio – Economic Expert, accredited by NABET in Edappal

Grama Panchayat. The main purpose of the study is to assist the project

proponent in delivering their Corporate Environmental Responsibi l ity

(CER) as per OM No. 22-65/2017-IA.III dt. 01-05-2018 issued by

MoEF&CC Notif ied by Ministry of Environment & Forests, states that

every green f ield project having capital investment under Rs. 100 crores

need to allocate 1.5% of its project cost (capital investment) for act ivit ies

under Corporate Environment Responsibi l i ty (CER). The instant project is

a Greenfield project and its capital investment is Rs. 180 crores.

Therefore the project has to spend an amount of Rs. 2.7 Crores under

CER in the surrounding vil lages. The project proponent has set apart an

amount of Rs. 2.7 Crores (about 1.5% of the project cost) to carry out

CER act iv it ies The objective is to obtain a social l icense from the stake

holders who are l ikely to be affected due to the proposed project.

7.5.2 Suggested Sectors to Perform Activities under CER:

1. Drinking water supply,

2. Sanitation,

3. Health,

4. Educat ion,

5. Skil l development,

6. Roads,

7. Cross drains,

8. Electrif icat ion including solar power,

9. Solid waste management faci l it ies,

10. Scient if ic support and awareness to local farmers to increase

yield of crop and fodder,

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 7 Addit ional Studies Page 7 - 15

11. Rain water harvesting,

12. Soil moisture conservat ion works,

13. Avenue plantation,

14. Plantation in community areas etc.

7.5.3 Approach adopted for assessment

To conduct the assessment, primary & secondary data were used.

Primary Data: Stake holder interviews, unstructured interview, f ield

observat ion, and telephonic survey.

Secondary data: Yearly Project Document and Development Charter of

the Panchayat, Census Report 2011.

7.5.4 Stake Holders

As part of study the Socio Economic expert conducted interviews with

different stakeholders of the Panchayat. The detai ls of stake holders are

given below.

Sl. No Name Designation Phone Number

01 M P Venugopalan Secretory, Edappal Grama

panchayath

8606339116

02 K Sathi Devi HM, Govt. U P

School,Pulikkad

9495805752

03 T P Surendran Polit ician 9048101990

04 K Bhavadasan Polit ician 8921195046

7.5.5 Proposed CER activities:

a) Health care

1. The project can provide 2000 dialysis to economically back ward

patients as free of cost. The patients from Edappal grama panchayth wil l

be given priority.

Particulars Basis of calculat ion Total ( in Rs.)

Dialysis Rs.1200 x 2000 Dialysis 24,00,000

Total 24,00,000

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 7 Addit ional Studies Page 7 - 16

2. The project can provide discount of Rs. 50,000 to 100 patients from

economical ly back ward famil ies for major surgeries.

Particulars Basis of calculat ion Total (in Rs.)

Discount of Major

surgeries

Rs.50,000 x 100 patients 50,00,000

Total 50,00,000

3. The project can provide the treatment of Rs. 1 lakh to the 60 pat ients,

those who are undergone organ transplantation in this hospital. The

beneficiar ies wil l be from economically back ward famil ies.

Particulars Basis of calculat ion Total (in Rs.)

Support to organ

transplantation

Rs.1,00,000 x 45 pat ients 45,00,000

Total 45,00,000

4. The project can provide Rs. 10,000 discount in the treatment of

500 pat ients from economically backward famil ies.

Particulars Basis of calculat ion Total (in Rs.)

Discount in treatment Rs.10,000 x 500 patients 50,00,000

Total 50,00,000

5. The project can provide scholarship of Rs. 1 Lakh to 50 el igible

students, those whol are studying in the proposed project.

Particulars Basis of calculat ion Total (in Rs.)

Scholarship Rs.1,00,000 x 50 Students 50,00,000

Total 50,00,000

6. The project will conduct Medical camp in various f ields l ike

Orthopaedics, Nephrology Gastroenterology and General medicine. The

project is intending to conduct 30 camps in the community.

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 7 Addit ional Studies Page 7 - 17

Particulars Basis of calculat ion Total (in Rs.)

Medical Camp Rs 50,000 x 30 camps 15,00,000

Total 15,00,000

7. The project wil l provide First Aid Training to people from various

category like Drivers, college Students, Kudumbasree members, Porters,

Construct ion labours, Students etc. The training programme wil l be free.

Maximum 30 persons can participate in a training programme.

Particulars Basis of calculation Total (in Rs.)

First aid Training

programme

Rs 20,000 x 50 programmes 10,00,000

Total 10,00,000

b) Rain Water Harvesting

The project can start a well recharge program by harvesting roof top rain

water. A f i ltrat ion tank wil l instal l near to the wel l and al l col lected water

channelized to well af ter f i l trat ion. This will be executed in associat ion

with NGOs in consultation with Local Self Government.

Particulars Basis of calculat ion Total (in Rs.)

Well Recharge Program Rs 15,000 x 100 wells 15,00,000

Total 15,00,000

c) Promotion of Renewable Energy

The project proponent can instal l solar panels of 4 KW to two Govt.

Schools and one PHC namely Govt. H S School, Edappal and Govt. U P

School, Pulikkad. In addit ion to this the project proponent can instal l solar

street l ights in consultation with Local Self Government.

Particulars Basis of calculat ion Total (in Rs.)

Solar Panel Rs. 3,50,000 x 3 Solar panels 10,50,000

Solar Streetl ight Rs. 20,000 x 23 Solar Street light 4,60,000

Total 15,10,000

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 7 Addit ional Studies Page 7 - 18

7.5.5.1 Summary of CER Activities

The summary of the CER activit ies are given below :-

Sr.

No. Areas of Intervention

No. of

Intervention

Expenses

(in Rs.)

01 Health Care 07 2,44,00,000

02 Rain Water Harvest ing 01 15,00,000

03 Promotion of renewable energy 01 15,10,000

Total 09 2,74,10,000

7.5.5.2 Time frame (Tentative) for execution of CER activities

Sr. No.

Activities Ist year IInd year III rd year

1 Health Care

2 Rain Water Harvest ing

3 Promotion of renewable energy

7.6 Réhabilitation & Resettlement (R & R) Action Plan

There is no displacement of people from the core zone of the project,

hence Réhabil itat ion & Resett lement (R & R) is not applicable to the

instant project.

7.7 Public Hearing

As per the Terms of Reference provided by the MoEF&CC vide letter

dated 22-06-2018, public hearing is to be conducted for the instant project.

Thereafter, v ide O.M. F.No.Z-11013/22/2017-IA.II(M) dated 16-03-2018

issued by MoEF&CC, no public hearing is required for building

construction projects.

*******************************************************************************

CHAPTER – 8

PROJECT BENEFITS

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 8 Project Benef i ts Page 8 - 1

8.0 PROJECT BENEFITS

8.1 Introduction

Any developmental project is conceived and executed with benefits to

various social groups. The any development projects also cater to the

needs of various sect ions of the society ranging from necessity to

recreation. The benefits from the proposed project are discussed below.

8.2 Physical Infrastructure

The proposed project is an expansion of exist ing hospital cum medical

college project which is planned to meet the model of a hospital /

healthcare sector. Overall development of the area including public

transport, water supply, sewage treatment, sol id waste treatment facil i ty,

telecommunications etc. are inclusive in the proposal.

8.3 Social Infrastructure

The project of large scale sets in an overall development of the region,

with construction of new or maintenance and widening of exist ing roads,

power supply and water supply, since a hospital building generally brings

the focus of the development authorit ies in the locali ty.

8.4 Economic Benefits

The project wil l entai l posit ive impact on the local economy in a mult i-

dimensional way.

The local market wil l also receive an impetus to grow in meeting the daily

need goods for the operational workers as well as in meeting day-to-day

odd job requirements of the proposed act iv it ies.

During the operat ion phase, it is proposed to employ mainly local

populat ion for various maintenance related activit ies after impart ing

adequate training. It is also proposed to engage in arrangements with

local faci l i t ies for maintenance and related procurement of spare parts

etc. of machineries / equipments used in the hospital.

In meeting the day-to-day and recreational demands of the occupants of

the site, the region is also l ikely to develop a number of shopping,

inst itutional and amusement faci lit ies within the vicinity thereby, further

stimulat ing the local economy.

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 8 Project Benef i ts Page 8 - 2

The proposed project is an expansion of exist ing hospital cum medical

college building project and thereby the living index of the people around

the project s ite will definitely improve.

Also there wil l be various ancil lary activit ies l ike convenient shops,

medical shop, food courts, and restaurants, transport facil it ies etc.

attached to the project which wil l benef it the local people and change

their l iving condit ion. Other benefits are :-

� Expansion of businesses with increased local spending on goods and

services;

� An increase in business and community conf idence in the continuing of

prosperity for the project area;

� Financial contr ibution to the State government through the payment of

taxes and duties thus enabling the State to invest in infrastructure

development.

� The present project would provide better healthcare related faci l it ies

with support ing infrastructure faci lit ies in the vicinity.

� Direct (about 1000 nos.) and indirect employment (about 3,000 nos.)

opportunit ies. The potential for employment and access to new

services may draw people to the area around the project. There will be

an increase in economic activity and employment for the local

community, local ski l ls development.

� Revenue ( GST) to the State & Central Government.

� The project proponent has carried out charity act ivit ies (Corporate

Social Responsibi l i ty) for on various developmental activit ies for the

local community.

8.5 Importance of the present project

Medical tourism is a fast becoming a multi-mill ion dol lar industry in the

country. The fact was further strengthened by Chief Secretary’s of Govt.

of Kerala statement at the inaugural funct ion of the f i f th edit ion of Kerala

Health Tourism. The current market size of the medical tourism sector in

the country is expected to grow from the current $3 bil l ion to $7-8 bi l l ion

by 2020.

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 8 Project Benef i ts Page 8 - 3

Medical tourism can be broadly def ined as provision of 'cost effective'

private medical care in col laboration with the tourism industry for patients

needing surgical and other forms of special ized treatment. This process is

being faci l itated by the corporate sector involved in medical care as well

as the tourism industry - both private and public.

Medical or Health tourism has become a common form of vacationing, and

covers a broad spectrum of medical services. It mixes leisure, fun and

relaxation together with wellness and healthcare.

The health holiday is an opportunity to get away from the dai ly rout ine

and come into a dif ferent relaxing surrounding. Here anyone can enjoy

being close to the beach and the mountains. At the same t ime you are

able to receive an orientat ion that wil l help you improve your life in terms

of your health and general well-being. It is l ike rejuvenation and clean-up

process on al l levels - physical, mental and emotional.

Many people from the developed world come to India for the rejuvenation

promised by yoga and Ayurvedic massage, but many consider it a

dest ination for hip replacement, Kidney & Liver problems or brain surgery,

cancer treatment etc. However, a nice blend of top-class medical

expert ise at attractive prices is helping a growing number of Indian

corporate hospitals lure foreign patients, including from developed nations

such as the UK and the US. As more and more pat ients from Europe, the

US and other aff luent nat ions with high medicare costs look for effective

options:

Apart from the benefits incurred through the project, there wil l be

environmental benefits through the project. This includes benefits

occurring to the locality neighborhood, and region as a whole. The

foremost benefits are l isted as fol lows:

A. Socio-Economy

� During the construction phase, there was growth in indirect jobs and

business opportunit ies to the local and nearby people such as

contractors, transporters and row material suppliers etc.

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 8 Project Benef i ts Page 8 - 4

� Due to this project, there is posit ive impact on the economic

development of the region in terms of employment opportunit ies.

� Post project wil l generate long term addit ional employment in

bui lding maintenance and ancillary services for local population.

B. Tree Plantat ion and Landscaping

� Trees plantat ion on ground levels (as already planted / to be

planted) helps reducing energy use by reducing heat island effect.

� Pleasing aesthetic and visual impact.

� Trees act as natural noise buffers.

� Provide tolerance to air pollutants l ike PM1 0, PM2.5, SO2, NOx & CO.

C. Water Saving and waste water Management

� The construction activ it ies are already completed. During operat ion

phase, the raw water requirement wil l be reduced by using treated

domestic waste for plantation and flushing purposes, horticulture,

boiler and make-up water for cooling purposes and no l iquid

discharge outside the project premises.

� By using various water saving pract ices l ike use of water eff icient

plumbing f ixtures, dual f luxing cisterns etc. and use of rain water for

domestic purposes bringing down the per capita water consumption

compared to the present use.

� Reducing storm water runoff by collecting the rain water from

terraces and to store in tanks as well as in pond and reducing the

load on storm water drains.

D. Energy Saving

� Provision of solar panels for external l ighting for proposed project.

� Maintenance of energy saving measures using conventional

measures.

� Various energy saving measures to save energy through

conventional and non-conventional method (Solar panels).

E. Solid and Hazardous & Bio-medical Waste Management

� Provision of dedicated space for solid waste management & bio-gas

generation plant for disposal of municipal solid waste. Also the bio-

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 8 Project Benef i ts Page 8 - 5

medical waste would be segregated as per the guidelines and wil l

be sent to the authorized agency i.e. IMAGE. The manure from

biodegradable waste is being used for plantation.

� Provision for separate storage for E-Waste. E-Waste is being

handed over to authorized recyclers, non-biodegradable waste shall

be handed over to approved vendors.

F. Environmental Monitoring & Environmental Management Plan

� Environmental monitor ing as mentioned in Chapter 6 wil l be carried

out regularly ensuring the baseline quality, implementat ion of

mitigation measures and control of environmental pollution.

� Environmental Management Plan and its judicious implementat ion

with operation and maintenance of environmental facil it ies and

insurance of proper budgetary allocations for a long term benefits to

project and surrounding areas.

*******************************************************************************

CHAPTER – 9

ENVIRONMENTAL COST BENEFIT

ANALYSIS

M/s SREEV ALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 9 Environmenta l Cost Benef it Analysis Page 9 - 1

9.0 ENVIRONMENTAL COST BENEFIT ANALYSIS

9.1 Introduction

Appendix-I II of EIA Notif ication, 2006 (Generic Structure of Environmental

Impact Assessment Document), states that "Environmental Cost Benefit

Analysis" is to be elaborated in the EIA report provided such a study is

mandated by the Expert Appraisal Committee (EAC) / State Expert

Appraisal Committee (SEAC) at the scoping stage of the proposal. In the

instant project, s ince the EAC has not prescribed for such a study during

the scoping stage and hence not part of the approved "ToR" and

therefore, there is no descript ion of "Environmental Cost Benefit

Analysis".

*******************************************************************************

CHAPTER – 10

ENVIRONMENTAL MANAGEMENT

PLAN

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 10 Environmental Management Plan Page 10 - 1

10.0 ENVIRONMENTAL MANAGEMENT PLAN

10.1 Introduction

This chapter deals with the descript ion of administrat ive aspects of

ensuring the mit igat ive measures proposed for the impacts identif ied in

Chapter 4 due to the construction activit ies during construct ion phase and

operation phase on each facets of environment viz. Air Environment,

Noise Environment, Land Environment, Water Environment, Ecological

Environment and Socio-economic Environment.

10.2 Environmental Management System (EMS)

The project proponent wil l adopt Environmental Management System

(EMS) which will assist project management to meet both current and

future environmental requirements and challenges. EMS wil l provide a

structural view and control of the organization's environmental

performance that wil l be applied from planning and exploration to the

proposed project during construction phase & in operation phase.

The following components are being taken to establish an EMS;

Organizational Commitment, Environmental Policy, Environmental Impact

Assessment, Objectives and Targets, Environmental Management Plan

(EMP), Documentat ion, Responsibi l it ies and Reporting Structure,

Training, Environmental Review Audits and Emission and performance

monitoring.

The project management will fol low a comprehensive and systematic

health and safety funct ion which involves al l personnel seeking to ident ify

hazards and assessing risk to prevent and el iminate all accidents/injur ies.

The project management wil l prepare a detai led Environment Management

Plan for sustainable development of the project.

10.3 Environmental Policy

In order to protect environment and for sustainable development, an

Environmental Policy wil l be adopted by the project proponent as fol lows:

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 10 Environmental Management Plan Page 10 - 2

"Environment, Health, Safety and Quality (EHSQ) Policy"

We, Sreevalsam Educational Trust, driven by our core values and beliefs

are committed to our stakeholders and meet customer / patient

sat isfaction through integrated EHSQ management system to achieve

sustainabil ity, in al l our exist ing and future healthcare services.

To attain this objective, we shall : -

• Implement and maintain an integrated EHSQ management system to

achieve sustainable performance.

• Adopt and sustain a Business Excellence framework for continual

business process improvement.

• Protect Environment, conserve natural resources, reduce energy

consumption, improve occupational health and safety performance and

mitigate risks by adopting optimal product ion processes and services,

driven by environment friendly technologies.

• Comply and endeavor to exceed all applicable legal and other

requirements.

• Continuously str ive to achieve satisfaction of all stakeholders through

contr ibution to social development.

• Communicate effectively about the EHSQ system and create awareness

and increase the competency of all employees through training.

• Establish specif ic organizat ional structure for guidance,

implementat ion and regular review of EHSQ management system.

Responsibil ity

The Environmental Off icer is responsible for maintaining ecological

balance by adequate environmental protection and environment

improvement works. In the event of observat ion of non compliance by any

employee, the same is informed by the Environmental Off icer to the

project manager and to the project proponent. These three wi ll ident ify the

cause and implement the mitigat ion measures or engineering controls or

work practices required. The Environmental Officer will monitor the

environmental performance and guide the project manager and the

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 10 Environmental Management Plan Page 10 - 3

employees for maintaining good environmental practices and to adopt

newer, safe and cleaner technologies.

10.4 Environment Management Cell (EMC)

A Cell for Environment Management within the site, will take overall

responsibi l ity for co-ordination of the act ions required for environmental

management and mitigation, and to monitor progress of the mit igative

measures and actions to be taken by the project proponent i.e.

Sreevalsam Educational Trust. The Cell wil l be under the overall

supervision of the Environmental Off icer, and will be responsible for

monitoring of the implementation of the various measures as mentioned in

Chapter 4. The Environmental Cell wil l report on a regular basis to the

project proponent.

The Environmental Management Cell is responsible for overseeing;

supervision, during collection of water and air samples within and outside

the core zone by NABL accredited laboratory; implementation of the

pollut ion control and protective measures; eco-restoration and green area

development; co-ordinat ion of the environment related act iv it ies;

collection of the statistics of health of workers; implementing safety

programs; and monitor ing progress of implementat ion of EMP during

construction phase & operation phase. The structure of the Environmental

Cell is given at Table 10.1.

Table 10.1 - Environmental Management Cell

Sr. No. Members Role

1. Secretary of the trust Chairman

2. Project Manager Member

3. Environmental Off icer Convener

4. Safety and Health Off icer Member

5. Representat ive of NABL accredited laboratory Member

6. Representat ive of NABET accredited Environmental Consultant

Member

Frequency of Meeting – Once In three months

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 10 Environmental Management Plan Page 10 - 4

10.5 Other Management Aspects of the Environmental Cell.

Records wi ll be maintained of the analysis reports of ambient air quality,

water quali ty, and noise levels and to observe variat ions (i f any). These

records are not only required for the perusal of the statutory authorit ies

but for the management also. The records as per the hazardous waste

regulat ions, 2016 and EPA regulations, 1986 are to be maintained.

Obtaining the Authorization for the intermediate storage of hazardous

waste as per the Hazardous Waste (Handling & Management) Rules and

its renewal. The project shall obtain the Consent to Establish (CTE) and

Consent to Operation (CTO) as required under Section 25/26 of the Water

Act, 1974 and under Section 21/22 of Air Act, 1981, before the

commencement of activity from Kerala State Pollution Control Board. The

CTO will be renewed as per the KSPCB guidelines by the management.

The project proponent wil l submit environmental statement every year

before September 30. The management ensures that i t wil l comply with all

the direct ions and regulat ions issued by the Ministry of Environment,

Forests & Climate Change (MoEF&CC), New Delhi, State and Centre

Pollut ion Control Boards. The "Consent to Establ ish", "Consent to

Operate", authorizat ion of Bio-medical Waste (Management & Handling)

Rules and al l other statutory approvals wil l be displayed in a conspicuous

location in the off ice of the Sreevalsam Educational Trust for the

information of the inspect ing authori ties of dif ferent departments and al l

stake holders.

10.6 Standard Operating Procedures (S.O.P.)

The Environment Management Cell wil l develop standard operating

procedures for the following :-

• Compliance to the condit ions of Environment Clearance (EC) and the

submission of six monthly compliance report of the E.C. condit ions.

• Compliance to the condit ions of "Consent to Establish" (CTE)

• Compliance to the condit ions of "Consent to Operate" (CTO)

• Compliance to the condit ions of Authorization of Bio-medical Waste

(Management & Handling) Rules

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 10 Environmental Management Plan Page 10 - 5

• Implementat ion of Remediation plan as approved by the regulatory authority

• Compliance to the condit ions of al l statutory approvals.

• Renewal of approvals before the expiry of the approvals.

• Implementat ion of the Corporate Environment Responsibi l ity act ivit ies.

• Compliance to the accreditat ion with NABH (National Accreditation

Board for Hospitals & Healthcare Providers) and other regulat ions

updated t ime to t ime.

10.7 Cost Estimate for Environment Management Systems

During Construction phase

The overall investment on the environmental safeguards and measures for

successful monitor ing and implementation of pollution control measures is

presented in Table 10.2.

Table 10.2 : Cost Estimation of Environmental Management Plan during Construction phase

Particulars

Approx. Recurring

Cost / Annum

Approx. Capital Cost

Rs. In Lacs

Medical cum First Aid facil ity with a trained person with f irst aid kit.

3.0 15.0

Mobile Toilets with STP in the labor colony 1.0 5.0

Supply of drinking water for the labourers from existing wells

3.0 5.0

Wind Breakers at the site in the side where it is abutt ing and other vulnerable

areas. 5.0 10.0

Sprinklers for suppression of dust (Sprinklers, pipeline network, online micro

f i lters and pressure pumps) 1.5 3.0

Solid Waste from labour camp & construction site

(Segregation & disposal with exist ing bio-gas plant)

0.5 2.0

TOTAL 16.0 50.0

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 10 Environmental Management Plan Page 10 - 6

During Operation phase

The overall investment on the environmental safeguards and measures for

successful monitor ing and implementation of pollution control measures is

presented in Table 10.3.

Table 10.3 : Cost Estimation of Environmental Management Plan during Operation phase

SN Particulars

Approx.

Recurring

Cost / Annum

Approx.

Capital Cost

Rs. In Lacs

1. Sewage Treatment Plant (STP) sewage

from domestic consumption of the campus 4 20

2.

Eff luent Treatment plant (ETP), waste

water from laundry / laboratory area of the

hospital

5.0 20.0

3. Solid Waste Management Plan including

sett ing up of a bio-gas generation plant 2.0 10.0

4. Bio-medical waste segregation & disposal

through IMAGE 4.0 40.0

5. Sett ing up of an intermediate hazardous

waste storage faci li ty 1.5 15.0

6. Noise Control for D.G. Sets 3.0 26.0

7. D.G. Sets Emission stacking & sampling 0.5 4.0

8. Green Area development 8.0 30.0

9. Construct ion of rain water collect ion tanks 5.0 45.0

10. Solar power & other solar energy operated

equipments 4.0 28.0

TOTAL 37 238

Note :- The cost should include the civ il construction + machinery +

electrical + plumbing + automation (if any).

*******************************************************************************

CHAPTER – 11

SUMMARY AND CONCLUSION

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 11 Summary & Conc lusion Page 11 - 1

EXECUTIVE SUMMARY

1.0 Introduction

M/s Sreevalsam Educational Trust proposed an expansion of exist ing

Hospital cum Medical College project at Survey Nos. 157/2, 159/3, 158/1,

157/0, 158/1, 159/3, 158/2, 158/5, 159/1, 159/2, 157, 159/3, 164/3, 164/7,

164/4, 163/3, 158/7, 158/3, 158/4, 166/2, 166/1, 156/3, 164/1, 156/3,

164/1, 164/2, 156/4, Edappal Vil lage, Ponnani Taluk, Malappuram District,

Kerala. The plot area of the Hospital cum Medical College Project is

9.4534 ha (94,534.56 sq. m.) and the total buil t-up area is 1,38,937.50 sq.

m. (existing 53,889.72 sq.m. + proposed 85,047.78 sq.m.).

Building construction of 53,889.72 sq.m. of the hospital cum medical

college is already completed. The teaching hospital component is for a

built -up area of 32,160 sq.m. and the educat ional component is with built -

up area of 21,729.72 sq.m. It is proposed to construct addit ional bui lt-up

area of 85,047.78 sq.m and the total cumulat ive built -up area will be

1,38,937.5 sq.m.

The land was purchased and registered between the year of 2010 to 2011

and started the construct ion work of Teaching Hospital in 2011 as per the

Building permit vide permit no. 224/11-12 dated 03-11-2011 obtained from

Edappal Grama Panchayat for a built-up area of 5,783.70 sq.m.

Subsequently, the expansion of the building was carried out with the

renewal of building permit vide permit no. B2-224/11-12 dated 27-06-2012

valid upto 26-06-2015 issued by the Panchayat for a cumulat ive built -up

area of 32,160 sq.m. in 2012. This work was carried out without pr ior

Environmental Clearance and the construct ion of this bui lding

is completed. Further, renewal of building permit vide permit no.

A5-365/14-14 dated 24-03-2014 was issued for Academic block, Hostels

with a cumulat ive built-up area of 43,636 sq.m. and construction of

21,729.72 sq.m. is completed. Educat ional institutions are exempted from

the purview of EIA Notif ication vide Notif icat ion dt. 22-12-2014. For the

f irst t ime, the requirement of prior Environmental Clearance was inserted

in Kerala Municipal ity Building Rules (KMBR) by an amendment of KMBR

made in 05/02/2013.

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 11 Summary & Conc lusion Page 11 - 2

Therefore, the project proponent was not aware of the requirement of

prior Environmental Clearance and constructed the Teaching Hospital

building without obtaining prior Environmental Clearance and hence the

violated the provisions of Environment Protect ion Act, 1986.

Ministry of Environment, Forests & Climate Change (MoEF & CC) issued a

Notif icat ion dated 14/03/2017 (Notif icat ion No. S.O. 804 (E)) and gave

one time opportunity to the projects who have commenced their activity

without taking prior Environmental Clearance violated the EIA Notif ication,

2006.

An application with draft Terms of Reference (ToR) for EIA Study and for

obtaining Environmental Clearance under the provision of MoEF&CC

Notif icat ion dt. 14/03/2017 was submitted at MoEF&CC on 23/06/2017

vide File No. 23-89/2018-IA-III (V).

Thereafter, the proposal was considered in the 06 th meeting of Expert

Appraisal Committee (EAC) at MoEF&CC on 19 t h - 20 th , Apri l, 2018 vide

agenda item No. 6.3.7 for grant of Terms of Reference (ToR) for

undertaking Environment Impact Assessment (EIA) studies and

preparation of Environment Management (EMP).

The EAC recommended the project for grant of “ToR” for undertaking

Environment Impact Assessment (EIA) study and preparation of

Environment Management Plan (EMP). The Ministry accepted the

recommendations of EAC and the “ToR” was approved and issued vide

Letter No. 23-89/2018-IA.III dated 22/06/2018.

With a view to assess the environmental impacts due to the construct ion

act iv it ies, to suggest the mitigat ion measures, to assess the ecological

damage due to the i l legal construct ion, to prepare remediation plan and

the natural and community resource augmentat ion plan as per the

approved ToR granted, the project proponent has engaged M/s

Environmental Engineers & Consultants Pvt. Ltd., (an MoEF & CC

accredited Consultancy Organizat ion under QCI / NABET Scheme).

2.0 Project description

In order to faci li tate the medical and medical education requirement in the

project vicinity and in Ponnani Taluk of Malappuram District, Kerala M/s

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 11 Summary & Conc lusion Page 11 - 3

Sreevalsam Educational Trust constructed a hospital cum medical col lege

project at Edappal Vil lage, Ponnani Taluk, Malappuram Distr ict, Kerala in

Plot area of 9.4534 ha and constructed of buildings with built -up area

53,889.72 sq. m. and due to increase in demand the project proponent is

going for expansion of the exist ing campus with addit ional built -up area of

85,047.78 sq.m. After the proposed expansion the cumulat ive built -up

area of the hospital cum medical col lege wi ll be 1,38,937.50 sq.m.

(existing bui lt-up area 53,889.72 sq. m. + 85,047.78 sq.m.) with number of

hospital beds of 1,170 beds.

The estimated cost of the project is about Rs. 180 Crores. The project is

expected to employ about 1,000 direct job opportunit ies which includes

medical & non-medical staff .

During construct ion phase, the daily water requirement for construction

act iv it ies is about 312 KL (for 48 months) and for meeting domestic

requirement is about 27 KL (250 workers at site, avg.) (for 48 months).

The sewage generat ion from the labourers during construct ion phase is

expected to be about 27 KL/day which wi ll be disposed through STP

within the site. The treated water from the mobile STP wil l be used for

wetting of dust suppression and for landscaping purposes within the site.

During operat ion phase, the sources of water for meeting the domestic

requirement as well as other requirements of the proposed hospital cum

medical col lege project wil l be from exist ing wells, stored rain water and

recycled water from STP / ETP.

The total daily water consumption for the proposed project would be about

1,328 KL (fresh water 677 KL + recycled water 651 KL). The f irst day

fresh water requirement is 1,328 KL and subsequent days, the daily fresh

water requirement is 677 KL. The daily domestic water consumption is

870 KL (f lushing purposes 647 KL + non-f lushing purposes 223 KL).

The sewage generat ion from the proposed hospital cum medical campus

during operation phase is expected to be about 696 KL/day which wil l be

disposed through STP within the site. The treated water from STP wil l be

used for f lushing purposes, landscaping purposes, boiler requirement and

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 11 Summary & Conc lusion Page 11 - 4

make-up water requirement for cooling towers attached with the HVAC

system within the site.

During construction phase, the storm water within the site wil l be partially

channelized to the rain water storage tank. Appropriate de-si lt ing and oi l

removal wil l be provided so that the storm water wil l not contaminate the

land and aquifer.

During operation phase, to conserve water, rainwater storage capacity of

5,000 KL is provided at the site. It is provided that roof rain water wil l be

directed to rain harvest ing tanks after de-siltat ion, the removal of oi l and

grease through a trap within si te. This water wil l be used for daily

requirement after suitable treatment. Excess rain water shall be lead to

storm water drain available near the site.

There is no Ecologically sensit ive zone (National Park, Sanctuary, Habitat

for Migratory Birds, Tiger Reserve) within the 10 km radius. Also, there is

no forest are within 10 km radius from the site.

As per the Land Use Cert if icate and Land Conversion Cert if icate issued

by Tahsildar, Ponnani on 31-03-2014 stating that the land is "do not fal l

under Agricultural use and this land can be used for Educat ion purpose to

establish Education Institut ions".

3.0 Description of the Environment

Study Area : As specif ical ly mentioned in EIA Notif icat ion and as well as

on the basis of "Environmental Impact Assessment Guidance Manual for

Building, Construction, Township and Area Development Projects"

published by Ministry of Environment & Forests, February, 2010, for

carrying out an EIA study of a building construction project, the project

site is called as "core zone" and 10 km radius from the boundary l imits of

the project site is called as "buffer zone". The study area includes the

"core zone" and "buffer zone".

Study period : The study period was November & December, 2018 which

is other than the monsoon season. The samples were collected and

analysed for various parameters through an National Accredited Board for

Laboratories (NABL), accredited laboratory and also by the ecological &

social experts approved by QCI/NABET.

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 11 Summary & Conc lusion Page 11 - 5

Meteorological parameters :

Temperature - The maximum temperatures ranges from 28.9 to 36.2°C

and the minimum temperatures range from 17.0 to 23.4°C.

Rainfall - The normal rainfal l of the district is 2793.3 mm.

Humidity -The relative humidity ranges from 84 to 94 % during morning

hours. The humidity is more during the peak monsoon months from June

to September.

Wind rose - As per the wind rose diagram, the pre-dominent wind

direction is from south direction.

Air Environment - All the analyzed values of al l parameters are well

within the National Ambient Air Quality Standards.

Noise Environment - I t can be observed from the results that the noise

values are much below the prescribed l imits for Industr ial, Commercial,

Resident ial, and Silence zone. Proposed project are not l ikely to cause

any increase in 'noise' levels at the monitoring locat ions (sensit ive

receptors) which are located more than a kilometer away from the project

site.

Land Environment - As per the Land Use / Land Cover Classif icat ion

System, the exist ing land use within the buffer zone is about 63% of the

land is Plantation area, about 7% land is River/Stream / Canal and about

24% of the land is Crop land and remaining land is covered with other

land use / land cover. The soil in core area is not good in nutr ients values

and not product ive from agriculture view point.

Proposed project is an expansion of exist ing hospital cum medical col lege

project and new buildings wil l be construct ing within the exit ing plot area.

Therefore, the land use / land cover of study area is not l ikely to get

affected adversely due to proposed project.

Water Environment - I t is observed that the ground water level is

encountered about 1 m from the existing ground level.

As per the Ground Water information Booklet, CGWB, the proposed

project is categorized as 'Safe' zone and hence the ground water

available in the region is ensure and to use of domestic purposes.

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 11 Summary & Conc lusion Page 11 - 6

All the parameters except pH level, i ron content, hardness, chlor ides are

within the standards as per IS:10500 (Ground Water - Bore well). It is

recommended that appropriate treatment wil l be done before its

consumption for domestic purposes.

Ecological Environment - Analysis of the f lora revealed that, in the

proposed project s ite there are 90 plant species fal l ing under 48 plant

families. Angiosperms forms 86 species with 25 species of trees including

saplings, 18 species of shrubs, 28 species of herbs and 15 species of

climbers. There are four Pteridophytes (ferns) fal l ing under three families.

The Site has 90 species of plants. I t consists of Trees 25 species, Tree

saplings 18 species, Shrubs 18 species, Herbs 28 species,

Cl imbers 15 species, Ferns 4 species,

The most dominant plant family is Compositae with 8 plant species

followed by Leguminosae, Moraceae Euphorbiaceae, and Malvaceae. One

tree species namely Artocarpus hirsutus is endemic to Southern Western

Ghats.

The fol lowing lists of faunal elements were observed from the site :

Birds 26 species, Mammals 10 species, Butterf l ies 24 species, Odonates

12 species, Amphibians 6 species, Repti les 10 species, Spiders 11

species, Ants 6 species,

Regarding the conservat ion status of the fauna, none of the animal

species ident if ied from the site belonged to the threatened categories

identif ied by the International Union for Conservation of the Nature and

Natural Resources (IUCN). Most of them are common and widely

distributed and the range of occurrence extended to wide geographical

area. One species of butterf ly namely Southern Birdwing (Troides minos)

and one species of amphibian viz. Rhacophorus malabaricus reported

f rom the site are endemic to W. Ghats.

The present project is an expansion of exist ing hospital cum medical

college campus. The construct ion of new buildings are within the existing

plot area. Therefore, the proposed construct ion act iv ity wi ll have minimal

impact on the local f loral and faunal species. Due to the construct ion

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 11 Summary & Conc lusion Page 11 - 7

act iv ity, there wil l be minimal loss of habitat to faunal species specially to

avifauna.

Socio-economic Environment - The density of populat ion in the buffer

zone is about 1465 persons per sq km. The project area is in a rural

vil lage. Majority of the populat ion in the study area are engaged in

agriculture and cult ivat ion. There is no major industry in the area. The

proposed project is l ikely to generate direct and indirect employment.

Economic growth is expected in the area due to construct ion boom and

al l ied industry like transport, mini hotels and restaurants and enhanced

commercial act iv it ies (markets, shops, real estate etc.).

Also, the healthcare faci l it ies wil l be increase due to the sett ing up of

medical col lege in the vic inity.

4.0 Anticipated Environmental Impacts & Mitigation Measures.

The mitigation measures for the signif icant impacts identif ied during

construction and operation phase are summarized below.

CONSTRUCTION PHASE:-

SN

Impact on

Envir . Anticipated Impacts Mitigation Measures

1 Air Particulate Matter & Gaseous emissions f rom DG Sets.

� Stack height as per CPCB Standards. � Promotion of use of c leaner fuel � Al l DG set should comply emissions norms

notif ied by MoEF / CPCB.

2 Water

Impact on competing users due to large consumption of water for cur ing, dust suppression, construction, domestic use etc.

� To avoid wastage of cur ing water, following procedures are suggested: -

• Curing water should be sprayed on concrete structures: f ree f low of water should not be al lowed for curing.

• Af ter l iberal cur ing on the f irst day, al l concrete structures should be painted with curing chemical to save water. This wil l s top dai ly water curing.

• Concrete structures should be covered with thick cloth / gunny bags and then water should be sprayed on them. This would avoid water rebound and wi l l ensure sustained and complete cur ing.

• Ponds should be made using cement and sand mortar to avoid water f lowing away f rom the f lat surface while curing.

• Water ponding should be done on all sunken slabs, th is would also highl ight the importance of having an impervious formwork.

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 11 Summary & Conc lusion Page 11 - 8

� Estimation of dai ly water consumption based on the population, reuse and recycled options, quantif icat ion of waste water, requirement of construction water , etc.

� Monitor ing water use: Use of water meter conforming to ISO Standards would be insta l led at the inlet point of water uptake and at the discharge point to monitor the dai ly water consumpt ion.

� Use of rain water for domestic purposes in the labour colony & for construct ion purposes.

� Use of treated water f rom STP of labour colony for construction purposes.

3 Noise

Noise & Vibrat ion f rom DG Sets due to inadequate acoustic enclosure

� Use of DG Sets with appropriate acoustic enclosures

� Use of ant i vibrat ion pads

4 Socio Economic

Unhygienic si te sanitat ion faci l i t ies may cause heal th damage to construction workers

� The object ive is to ensure health and safety of the workers with effective provis ions for the basic facil i t ies of sani tat ion, dr inking water , safety of equipments or machinery etc. Fol lowing are some of the recommendations:-

� Comply with the safety procedures, norms and guidel ines (as appl icable) as outl ined in the National Building Code of India, Bureau of Indian Standards.

� Provide c lean dr inking water to a l l workers. � Provide adequate number of decentra l ized

latr ines and ur inals. � Guarding al l parts of dangerous machinery. � Precautions for working on machinery. � Maintaining hoists and l if ts , l i f t ing machines,

chains, ropes and other l if t ing tackles in good condit ion.

� Durable and reusable formwork systems to replace timber formwork and ensure that formwork where used is properly maintained.

� Ensuring that walk ing surfaces or boards at height are of sound construction and are provided with safety rai ls or belts.

� Provide measures to prevent f ires. Fire f ight ing ext inguishers and buckets of sand to be provided in the f ire prone area and elsewhere.

� Provide suff ic ient and suitable l ight for working during night t ime.

5 Energy Conservation

Use of energy in-eff ic ient building materia ls may lead to higher consumption of electr ic i ty in air

� Use of bui lding materia l for roof , wal ls & glass ( R & U values) as per BEE for less heat gain in a ir conditioned buildings.

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 11 Summary & Conc lusion Page 11 - 9

condi tioned bui ldings.

6

Building

Mater ial

Resource

Conservation

Use of farfetched construction materia l than locally available construction materia l may lead to over explo itat ion of natural resources & increase in carbon footpr int

� Use of local ly avai lable construct ion materials.

** Construction Activities (Foundation, Columns, beams, slab casting,

brick work, plastering, flooring, electrical & plumbing works, painting

& finishing).

OPERATION PHASE:-

Sr. No.

Impact on Env. Anticipated Impacts Mitigation Measures

1 Air

Particulate Matter & Gaseous emissions (including worst condit ion of operat ing al l DG sets)

� Stack height as per CPCB Standards. � Development of a dense belt

(vegetat ion buffer) in the project site. � Promotion of use of cleaner fuel � All DG set should comply emissions

norms notif ied by MoEF / CPCB.

2 Water

Impact on competing users due to consumption of public supply / ground water (resource loss) for domestic consumption in the campus

� Estimation of daily water consumption based on the population, reuse and recycled options, quantif icat ion of waste water etc.

� Monitoring water use: Use of water meter conforming to ISO Standards would be instal led at the inlet point of water uptake and at the discharge point to monitor the daily water consumption.

� Use of water saving devices / f ixtures: Low water consumption f ixtures like low f low f lushing systems, sensor based f ixtures, waterless urinals, tap aerators etc. to reduce the water usage.

� Instal lation of dual plumbing for using recycled water.

� Use of rain water

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 11 Summary & Conc lusion Page 11 - 10

3 Water

Impact on competing users due to consumption of public supply / ground water as make-up water for HVAC in the campus (resource loss)

� Estimation of daily water consumption based on the HVAC losses, reuse and recycled opt ions.

� Monitoring water use: Use of water meter conforming to ISO Standards would be instal led at the inlet point of water uptake and at the discharge point to monitor the daily water consumption in HVAC unit.

� Use of treated water for STP as make-up water in HVAC system.

� Use of rain water

4 Water

Improper discharge of untreated sewage may lead to impact on surface / ground water quality

� Treatment of sewage and recycling of the treated sewage and ensuring zero discharge.

� Sewage treatment plant proposed. � Treatment unit with pr imary, secondary

and territory treatment proposed

5 Water

Improper storage & disposal of e-waste may lead to leaching of heavy metals leading to contamination

� Storage of e-waste as per Rules and in an isolated area.

� Disposal of e- waste only to the authorized agency

� MoU with the approved agency to be made.

6 Water

Improper storage & disposal may lead to leaching of hazardous waste leading to contamination

� Development of leachate proof intermediate hazardous storage faci li ty.

� Outsourcing of the hazardous waste to the Kerala Pol lut ion Control Board approved agency & MoU to be made with the approved agency.

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 11 Summary & Conc lusion Page 11 - 11

7 Soil

Improper disposal of MSW & BMW waste may lead to impact on land.

� Segregation of waste at source into medical, biodegradable and non biodegradable waste by providing colored bins.

� Medical waste wi ll be disposed off through KSPCB approved vendors

� Disposal of biodegradable Municipal Solid Waste by bio gas unit.

� Disposal of non biodegradable recyclable waste to vendors.

� Disposal of inert waste by land f i l l ing / back f i l l ing.

� For Bio-medical waste - Collect ion & segregation at source by providing appropriate colour coded bins / containers as per the colour coding provided in the Bio-Medical Waste (Management & Handling) Rules.

� The Bio-medical waste from the proposed hospital would be outsourced through a Kerala State Pollut ion Control Board authorized agency (M/s Indian Medical Associat ion Goes Eco Friendly, IMAGE)

8 Soil Improper discharge of untreated sewage may lead to impact on land.

� Treatment of sewage and recycling of the treated sewage and ensuring zero discharge.

9 Soil

Improper storage & disposal of e-waste may lead to leaching of heavy metals leading to contamination

� Storage of e-waste as per Rules and in an isolated area.

� Disposal of e- waste only to the authorized agency & MoU to be made with the agency.

10 Soil

Improper storage & disposal of hazardous waste may lead to leaching of waste leading to contamination

� Development of leachate proof intermediate hazardous storage faci li ty.

� Outsourcing of the hazardous waste to the Kerala Pol lut ion Control Board approved agency & MoU to be made with the concerned agency.

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 11 Summary & Conc lusion Page 11 - 12

11 Biologica

l

Improper disposal of MSW & BMW may attract scavenger avifauna which may lead to dissertat ions of nat ive avifauna

� Segregation of waste at source into medical, biodegradable and non biodegradable waste by providing colored bins.

� Disposal of biodegradable Municipal Solid Waste by bio gas unit & bio-bin system.

� Disposal of non biodegradable recyclable waste to vendors.

� Disposal of inert waste by land f i l l ing / back f i l l ing.

� Plantation of native species of trees / shrubs / herbs / grass for enhancement of avifauna

� Conservation of the existing trees wherever possible.

� Plantation of fruit bearing trees to enhance the avifauna.

� For Bio-medical waste - Collect ion & segregation at source by providing appropriate colour coded bins / containers as per the colour coding provided in the Bio-Medical Waste (Management & Handling) Rules.

� The Bio-medical waste from the exist ing hospital outsourced through a Kerala State Pollut ion Control Board authorized agency (M/s Indian Medical Association Goes Eco Friendly, IMAGE) and the same arrangement will be cont inue for expansion facil ity also.

12 Aesthet ic

s

Improper disposal of MSW may lead to un-aesthet ic condit ions

� Segregation of waste at source into biodegradable and non biodegradable waste by providing colored bins.

� Disposal of biodegradable Municipal Solid Waste by bio gas unit.

� Disposal of non biodegradable recyclable waste to vendors.

� Disposal of inert waste by land f i l l ing / back f i l l ing.

13 Energy Conserva

tion

Adoption of energy in-eff icient vehicles, HVAC system, appliances, l ights etc may lead to wastage of energy

� Use of Euro-III Standard vehicles. � HVAC system and appl iances with 5

Star Rating as per BEE.

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 11 Summary & Conc lusion Page 11 - 13

14 Energy Conserva

tion

Non adoption of renewable sources of energy like solar energy may lead to increase dependency on public supply may lead to consumption of energy by competing users

� Use of Solar energy for water heating � Use of solar energy for common area

light ing in parks and in streets. � Use of solar power plant for common

area l ighting in campus.

5.0 Environmental Monitoring Program

The budget for environmental monitoring for the parameters is calculated

on the basis of CPCB not if ication of charges for environmental monitoring

and analysis. The cost est imate for environmental monitor ing. The total

cost of Environmental Monitor ing Budget during construction phase wil l be

of Rs. 5,80,000/- and operation phase wi ll be of Rs. 9,30,000/-.

6.0 Additional Studies

Risk & Disaster Management - The project proponent has prepared a

well maintained Risk and Disaster Management Plan with regard to

manmade disaster l ike f ire etc as well as natural disaster etc.

Resource & Energy Conservation -The proposed project is an expansion

of existing hospital cum medical college campus project will lead to

ut il izat ion of various natural resources like water resources, construct ion

materials, top soil conservat ion, use of solar energy. As an

environmentally responsible corporate, the project proponent endeavor to

conserve these resources by judicious management and recycling and

strive to build up these resources where possible.

Traffic Impact Assessment Study - As per the traff ic analysis data, the

traff ic volume is within carrying capacity of road as per Indian Road

Congress (IRC) standards.

Social Impact Assessment - Community Need Assessments seek to

gather accurate information representat ive of the needs of a community.

Assessments are performed prior to taking act ion and are used to

determine current situations and ident ify issues for action, establishing

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 11 Summary & Conc lusion Page 11 - 14

the essential foundation for vi tal planning. The process is an invaluable

tool for involving the public in solving problems and developing goals

The project proponent has set apart an amount of Rs. 2.7 Crores (about

1.5% of the project cost) to carry out CER activit ies.

Réhabilitation & Resettlement (R & R) Action Plan - There is no

displacement of people from the core zone of the project, hence

Réhabil itat ion & Resettlement (R & R) is not applicable to the instant

project.

Public Hearing - As per the Terms of Reference provided by the

MoEF&CC vide letter dated 22-06-2018, public hearing is to be conducted

for the instant project.

Thereafter, v ide O.M. F.No.Z-11013/22/2017-IA.II(M) dated 16-03-2018

issued by MoEF&CC, no public hearing is required for building

construction projects.

7.0 Project Benefits - Due to the proposed expansion of exist ing

hospital cum medical col lege project, there wil l be improvement in the

Physical Infrastructure, Improvement in the Social Infrastructure, Increase

in Employment Potent ial to the tune of about 1000 persons direct

employment and about 3,000 persons indirect employment. The operation

of the project also results in addit ional GST and State by way of taxes

and duties. The Govt. Authorities can ut il ize this amount for development

of infrastructure. Due to the sustainable development of the proposed

act iv it ies, the project wil l benef it to the environment.

8.0 Environment Management Plan - The project proponent wil l make

the Environment Cell. A Cell for Environment Management within the

project site, wil l take overall responsibil i ty for co-ordination of the act ions

required for environmental management and mit igation, and to monitor

progress of the mitigat ive measures and actions to be taken by the project

proponent.

The capital cost for environmental management plan during construction

phase will be about Rs. 16 lakhs and recurring cost per annum will be

about Rs. 50 Lakhs.

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 11 Summary & Conc lusion Page 11 - 15

During operat ion phase, the capital cost for environmental management

plan wil l be about Rs. 37 lakhs and recurr ing cost per annum wi ll be

about Rs. 238 Lakhs.

9.0 Ecological Damage & Remediation Plan, Natural & Community

Resources Augmentation Plan - The project proponent wil l spend an

amount of Rs 57,44,000/- (Rupees Fif ty Seven Lakhs Forty Four

Thousand only) on account of Remediation, Natural Resource &

Community Augmentation Plan for 3 years. A bank guaranty for an amount

of Rs. 57,44,000/- will be submitted to the Kerala State Pollut ion Control

Board valid for a period of 3 years. On successful completion of the

remediation plan, natural and community augmentation plan and

verif ication of the same by the Pollut ion Control Board, the bank guaranty

wi ll be released to the project proponent. In case, if the project proponent

failed to implement the remediat ion plan, natural and community

augmentation plan as committed, the bank guaranty wil l be forfeited

*******************************************************************************

CHAPTER – 12

DISCLOSURE OF CONSULTANTS

M/s SREEV ALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 12 Disclosure of ACO Page 12 - 1

12.0 DISCLOSURE OF CONSULTANT

12.1 The name of consultants engaged with their brief resume.

The team involved in the conduct ion of EIA study and preparat ion of the

EIA report is provided below: -

Name of consultant /

expert

Role in the preparation of EIA report

Qualification & Experience in brief

P. Z. THOMAS EIA Coordinator & *FAE for

Land Use, Air Pollution, Water

Pollution, Solid & Hazardous

Waste.

B.Tech in Civil Engineering with

specialization in industrial waste

engineering.

Working in the Environment field for the

last 29 years.

Jomon M C *FAE – Socio Economic Masters in Social Work (MSW).

Working in the Environment field for the

last 6 years.

Dr. Renoy

Varghese

*FAE - Ecology & Biodiversity,

Soil Conservation

Masters in Zoology. Working in the

Environment field for the last 12 years.

Akhil Chandran V **AFAE - Hydrogeology,

Ground Water & Water

Conservation, Geology .

Masters in Geology.

Working in the Environment field for the

last 2 years.

Mukesh Suroliya

*FAE – Hydrogeology, Ground

Water & Water Conservation,

Geology

Masters in Geology.

Working in the Environment field for the

last 12 years.

Mohan A. Patil *FAE – Air Quality Modeling &

Prediction, Noise & Vibration

M.Tech in Energy Management.

Working in the Environment field for the

last 30 years.

Sunil Gupta *FAE – Risk & Hazard

Management

M.Tech in Chemical Engineering.

Working in the Environment field for the

last 28 years.

*FAE - Functional Area Expert &

AFAE** - Associated Functional Area Expert

M/s SREEV ALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 12 Disclosure of ACO Page 12 - 2

12.2 Profile of Accredited Environmental Consultancy Organization (ACO)

We, M/s ENVIRONMENTAL ENGINEERS & CONSULTANTS PVT. LTD. is

a professionally managed accredited consultancy organizat ion with

Ministry of Environment, Forest and Climate Change, Govt. of India under

the National Accreditation Board for Education and Training (NABET,

QCI) scheme. The ACO is in operat ion for the last 25 years.

We assist our cl ients in obtaining Environmental Clearance under EIA

Notif icat ion, 2006 and CRZ Clearance under CRZ Notif icat ion, 2011 from

the Ministry and various State Level Authorit ies across the country.

We conduct and prepare Environmental Impact assessment (EIA) studies,

Environment Management Plan (EMP), Disaster Management Plan and

Environmental Audit (EA) in area development and townships projects,

large building construction projects, mining projects etc.

We also design, fabricate, instal l and commission various pollut ion control

equipments (both l iquid and air) for various industries in the country on

turnkey basis.

We have more than 1,000 sat isf ied customers in the building construction,

township and mining sector for whom we have provided our services in

preparation of EIA / EMP reports and technical assistance in gett ing

Environmental Clearance and CRZ Clearance across the country. Also, in

the series of our achievements, the success story of M/s Lavasa

Corporation Ltd. (M/s LCL) ( a hil l stat ion township near Pune & LCL is

an enterprise of M/s Hindustan Construct ion Company Ltd., Mumbai )

spread on an area of 5,000 ha., about 12,500 acres ( 2,000 ha. – 1s t

Phase + 3,000 ha. – 2nd Phase ) and M/s Smart City Kochi Infrastructure

Pvt. Ltd., Kochi, Kerala (an IT/ITES SEZ township project) spread on an

area of 100 hectares.

M/s SREEV ALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 12 Disclosure of ACO Page 12 - 3

UNIQUE FEATURES OF THE ACO

� Accredited Environment Consultancy Organization by NABET /

QCI with the fol lowing sectors :-

Sector

Nos.

Name of Sector

1 Mining of mineral – Opencast only

38 Building and large construction projects including shopping

malls, mult iplexes, commercial complexes, housing estates,

hospitals, insti tutions

39 Townships and Area development Project

� Turnkey supply of Air Pollution Control System to USA: Supplied

a “Fume extract ion cum Scrubber System” to M/s Jindal United

Steel Corporation , Texas, USA ( USA’s largest Steel Plate Mil l

Company ). System meets USEPA & OSHA standards of US

Government (Stringent than Indian Standards).

� All Air / Water Pollut ion Control systems supplied t i l l date are

approved and accepted by concerned State Pollut ion Control

Boards / Ministry of Environment & Forests al l over India since it

meets compliance requirements.

� Designed and supplied ful l proof smoke free “Dust / Fume

Extraction cum Bag f ilter type Air Pollut ion Control cum dust

recovery system” for highly polluting secondary Lead furnaces

( Payback less than a year ensured ).

� Turnkey Systems instal led all over the country and operating

sat isfactori ly in various states (Delhi, Punjab, Haryana,

Uttaranchal, UP, Chattisgarh, J & K, Andhra Pradesh, Tamil Nadu,

Karnataka, Kerala, Gujrat, Rajasthan etc.)

� Eff luent Treatment Plants designed with an object ive of Recycling

the treated eff luents to conserve water.

M/s SREEV ALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 12 Disclosure of ACO Page 12 - 4

� Dust / Fume extraction cum Bag Fil ter type Air Pollut ion Control

Systems have been tested by the reputed Environmental

Laboratory of National Productivity Council, Delhi and evaluated

as satisfactory.

� Approved Vendor for a FORTUNE 500 Indian Publ ic Sector

Undertaking Oil Company (Indian Oil Corporation) for Pollut ion

Control Equipments.

� Head Office :-

P. Z. THOMAS ( Managing Director )

M/s Environmental Engineers & Consultants Pvt. Ltd.

A1 – 198, Janak Puri, New Delhi – 110058.

Ph. No. 011-25507190 Telefax No. 011-25622604

E-mail :- [email protected] & [email protected]

Mobile No. 9350873385, 9811080469

� Branch Office Address: -

M/s Environmental Engineers & Consultants Pvt. Ltd.

Apartment No. C-306, Kanchanjunga Apartments,

Palarivattom, Kochi, Ernakulam, Kerala-682025.

E-mail :- [email protected]

Ph. 0484-4034320.

The copy of the accreditation certi f icate of the ACO from NABET / QCI is

provided at Annexure No. 12.1.

*******************************************************************************

CHAPTER – 13

ECOLOGICAL DAMAGE &

REMEDIATION PLAN,

NATURAL

&

COMMUNITY RESOURCES

AUGMENTATION PLAN

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 13 Damage Assessment & Remediat ion P lan

Page 13 - 1

13.0 ECOLOGICAL DAMAGE & REMEDIATION PLAN, NATURAL & COMMUNITY RESOURCES AUGMENTATION PLAN 13.1 Introduction

M/s Sreevalsam Educational Trust proposed an expansion of exist ing

Hospital cum Medical College project at Survey Nos. 157/2, 159/3, 158/1,

157/0, 158/1, 159/3, 158/2, 158/5, 159/1, 159/2, 157, 159/3, 164/3, 164/7,

164/4, 163/3, 158/7, 158/3, 158/4, 166/2, 166/1, 156/3, 164/1, 156/3,

164/1, 164/2, 156/4, Edappal Vil lage, Ponnani Taluk, Malappuram District,

Kerala. The plot area of the Hospital cum Medical College Project is

9.4534 ha (94,534.56 sq. m.) and the total buil t-up area is 1,38,937.50 sq.

m. (existing 53,889.72 sq.m. + proposed 85,047.78 sq.m.).

Building construction of 53,889.72 sq.m. of the hospital cum medical

college is already completed. The teaching hospital component is for a

built -up area of 32,160 sq.m. and the educational component is with

built -up area of 21,729.72 sq.m. It is proposed to construct addit ional

built -up area of 85,047.78 sq.m and the total cumulative built -up area wil l

be 1,38,937.5 sq.m.

The land was purchased and registered between the year of 2010 to 2011

and started the construct ion work of Teaching Hospital in 2011 as per the

Building permit vide permit no. 224/11-12 dated 03-11-2011 obtained from

Edappal Grama Panchayat for a built-up area of 5,783.70 sq.m.

Subsequently, the expansion of the building was carried out with the

renewal of building permit vide permit no. B2-224/11-12 dated 27-06-2012

valid upto 26-06-2015 issued by the Panchayat for a cumulat ive built -up

area of 32,160 sq.m. in 2012. This work was carried out without pr ior

Environmental Clearance and the construct ion of this bui lding

is completed. Further, renewal of building permit vide permit no.

A5-365/14-14 dated 24-03-2014 was issued for Academic block, Hostels

with a cumulat ive built-up area of 43,636 sq.m. and construction of

21,729.72 sq.m. is completed. Educat ional institutions are exempted from

the purview of EIA Notif ication vide Notif icat ion dt. 22-12-2014. For the

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 13 Damage Assessment & Remediat ion P lan

Page 13 - 2

f irst t ime, the requirement of prior Environmental Clearance was inserted

in Kerala Municipal ity Building Rules (KMBR) by an amendment of KMBR

made in 05/02/2013.

Therefore, the project proponent was not aware of the requirement of

prior Environmental Clearance and constructed the Teaching Hospital

building without obtaining prior Environmental Clearance and hence the

violated the provisions of Environment Protect ion Act, 1986.

Ministry of Environment, Forests & Climate Change (MoEF & CC) issued a

Notif icat ion dated 14/03/2017 (Notif icat ion No. S.O. 804 (E)) and gave

one time opportunity to the projects who have commenced their activity

without taking prior Environmental Clearance violated the EIA Notif ication,

2006.

An application with draft Terms of Reference (ToR) for EIA Study and for

obtaining Environmental Clearance under the provision of MoEF&CC

Notif icat ion dt. 14/03/2017 was submitted at MoEF&CC on 23/06/2017

vide File No. 23-89/2018-IA-III (V).

Thereafter, the proposal was considered in the 06 th meeting of Expert

Appraisal Committee (EAC) at MoEF&CC on 19 t h - 20 th , Apri l, 2018 vide

agenda item No. 6.3.7 for grant of Terms of Reference (ToR) for

undertaking Environment Impact Assessment (EIA) studies and

preparation of Environment Management (EMP).

The EAC recommended the project for grant of “ToR” for undertaking

Environment Impact Assessment (EIA) study and preparation of

Environment Management Plan (EMP). The Ministry accepted the

recommendations of EAC and the “ToR” was approved and issued vide

Letter No. 23-89/2018-IA.III dated 22/06/2018.

With a view to assess the environmental impacts due to the construct ion

act iv it ies, to suggest the mitigat ion measures, to assess the ecological

damage due to the i l legal construct ion, to prepare remediation plan and

the natural and community resource augmentat ion plan as per the

approved ToR granted.

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 13 Damage Assessment & Remediat ion Plan

Page 13 - 3

13.2 Damage Assessment & Remediation Plan

The damage assessment & remediation plan is prepared for each environmental facets l ike air,

noise, land, water, ecology & socio-economic and the same is provided at table 13.1 below.

Table 13.1 - Damage Assessment & Remediation Plan

Air Environment

Activities which caused damage

Concern Issues / impacts

Damage Assessment

Remediation Plan Budgetary Estimate (in Rs.)

1. Site Clearance

2. Excavation

3. Infrastructure

development .

4. Transportation

of materials

5. Operation of

D.G. sets and

other construction

equipments /

machinery.

6.Construction

activity.

1. Dust generation

2. Gases emissions

3. Vehicle exhaust

4. Emissions from fire

wood and cooking

gas.

1. Air Pollution due

to particulates

and gases

2. Change in water

quality due to

dust

3. Emission of VOC

from wood work

and painting.

1. Dust suppression and Water

sprinkling system at construction

sites outside the project site

where there is no requirement of

E.C.

2. Conduction of a vehicle check up

camp in consultation with the

motor vehicle Department once

in 6 months.

3. Providing enclosures / wind

breakers (shade nets) at

construction sites within the

panchayat (public work places)

1. The dust suppression and

water sprinkling system

consists of water

sprinkler nozzles (about

½ dozen @ Rs. 1,000

per nozzle i.e. Rs.

6,000), Online twin

filtration system (Rs.

15,000), Booster pump

(1 HP (@ Rs. 10,000),

Water distribution

pipeline (LS Rs. 10,000)

and water storage tank

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 13 Damage Assessment & Remediat ion Plan

Page 13 - 4

7. Temporary stay

of construction

workers.

where loose construction

materials are stored outside the

project site.

4. Regular monitoring of ambient air

quality near sensitive locations (2

locations) in the panchayat (once

in 3 months) in consultation with

local panchayat.

5. Providing Personnel protection

equipments to the health

department of the panchayat for

supply the same to the

construction workers engaged in

construction sites

6. Regular wetting of loose

construction materials at sites

(public work places) outside the

project.

(5,000 ltr @ Rs.

25,000.). Labour cost of

Rs. 10,000. The total

cost on water sprinkling

and dust suppression

system is

Rs. 76,000/-

2. Wind breakers /

barricades in the

periphery of project site

(3 m. height GI sheet)

(Rs. 1,00,000/-)

3. Vehicle check up camp (@Rs. 10,000 per camp and Rs. 20,000 annual)

4. Ambient air quality monitoring in sensitive areas (@Rs. 5,000 per month x 12 months i.e. Rs. 60,000 x 2 locations = Rs. 1,20,000 ).

Total cost on remediation measures on Air Environment is Rs. 3,16,000/-

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 13 Damage Assessment & Remediat ion Plan

Page 13 - 5

Noise Environment

Activities which

caused damage

Concern Issues /

impacts

Damage

Assessment Remediation Plan

Budgetary Estimate

(in Rs.)

1. Movement of

construction

equipments and

machineries.

2. Construction

activities

3. Operation of D.G.

set of 100 kVA

capacity.

1. Noise generation &

increase in noise level.

2. Noise & vibration due

to construction activity

and operation of D.G.

set of 62.5 KVA

capacity.

1.Health issue due

to increase in

noise level to

construction

workers

1. Providing Personnel protective

equipments (PPE) to the to the

Health Department of the

panchayat

Rs. 50,000/- (LS.)

Total cost on remediation measures on Noise Environment is Rs. 50,000/-

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 13 Damage Assessment & Remediat ion Plan

Page 13 - 6

Land Environment

Activities which

caused damage

Concern Issues /

impacts Damage Assessment Remediation Plan

Budgetary Estimate

(in Rs.)

1. Excavation 1. Un-manage / un-

control storage of

excavated soil,

2. Loosing its texture,

productivity and

fertility status,

3. Chocking of drains

due to surface runoff

during rainy season.

4. Change in topography

and drainage pattern

1. Change in soil quality

(texture, productivity

and fertility status)

(Excavation of top soil)

2. Soil degradation,

overflow of drains due

to chocking with soil

during rainy season,

dust pollution in dry

season

1. Assistance to the panchayat

in storage of excavated top

soil in a designated place

and consume it for the

common greenery

development.

Rs. 50,000/- for creating

barriers to avoid erosion and

to maintain its integrity so as

to use it further for

landscaping.

2. Solid waste

generation during

construction activity

1. Un-managed disposal

of domestic solid

waste without

1. Contamination or

degradation of soil /

water quality.

1. Printing & distributing

leaflets on proper

segregation (degradable

Rs. 10,000 (LS) for printing &

distribution of leaflets.

Rs. 30,000/- for 10 bins

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 13 Damage Assessment & Remediat ion Plan

Page 13 - 7

segregation.

2. Un-managed disposal

of construction wastes

2. Effect on plant growth

3. Nuisance due to un-

managed disposal or

storage of MSW and

construction wastes.

and non-biodegradable at

source itself)

2. Proving colour coded bins

in the panchayat building,

school, etc. (10 bins).

(@Rs. 3,000 per bin).

Total Rs. 40,000/-

3. Generation of

hazardous wastes

like empty cans of

varnish , paints etc.

during construction

activity

1. Un-managed

dumping, nuisance

creation, toxicity

generation, health

effect

1. Contamination of soil /

water

2. Effect on flora / fauna,

3. Health effect on

workers handling

chemicals / paints etc.

1. Providing a isolated leachet

proof storage facility for

hazardous waste within the

panchayat in consultation

with the panchayat.

1. Secured intermediate

leachate proof facility for

storage (LS. Rs. 50,000)

Total cost on remediation measures on Land Environment is Rs. 1,30,000/-

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 13 Damage Assessment & Remediat ion Plan

Page 13 - 8

Water Environment

Activities which caused damage

Concern Issues / impacts Damage Assessment Remediation Plan Budgetary Estimate

(in Rs.)

A. Fresh water

1. Site preparation

& infrastructure

development.

2. Construction

activities.

3. Temporary stay

of construction

workers (domestic

consumption).

1. Utilization of large quantity of

water for dust suppression,

consolidation and compaction.

2. Impact on competing users

due to large consumption of

water for various construction

activities (@1.10 KL per sq.m.

of built-up area for the

following activities : Ready mix

concrete (RMC) production,

Cement block / brick

production, Curing, Bricks /

block soaking, concrete curing,

masonry and cement

plastering curing, flooring

works etc.). total water

consumed is about 59,000 KL

1.The rain water stored

at site was used for

construction

purposes.

2.Through tankers from

Kerala Water

Authority water

Supply Scheme for

domestic

consumption.

1.Restoration of 5

abandoned wells within

the panchayat including

the half yearly water

sampling & monitoring.

2. Rehabilitation of village

pond by providing soft

landscaping around the

pond and cleaning.

Rs. 50,000/- (A )for

restoration of abandoned

wells (Rs. 10,000 x

5 wells) + Rs. 50,000/-

(B) for water sampling and

monitoring (Rs. 5,000 x 10

samples).

Total (A +B)= Rs. 1,00,000/-

and Rs. 4,00,000/- for

Rehabilitation of village

Pond.

Total = Rs. 5,00,000/-

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 13 Damage Assessment & Remediat ion Plan

Page 13 - 9

(A).

3.Domestic water consumption

of about 27 KL/day (About 200

labour x 135 ltr = 27 KLD) for

about 1,000 days (over a

period of 8 years) i.e. 27,000

KL (B).

The total fresh water consumed

is 86,000 KL (A+B).

B. Waste water 1. Waste water generation from

cleaning machinery,

equipments and vehicles,

2. Domestic waste water

generation from workers

1. Discharge of

contaminated water

to the land and to the

water channel /

drainage .

2. Discharge of

domestic sewage to

the project site.

1. Setting up of mobile

toilets for the workers in

public works (panchayat

development works)

outside the project site

2. Setting up of a STP for

the treatment of sewage

from the panchayat

school

1. Rs. 80,000/- towards set

up of 2 units of portable

toilet at site (1 for male and

1 for female)

2. Rs. 6,50,000 on setting up

of an STP of 5 KLD

capacity.

Total cost on remediation

measures is Rs. 7,30,000/-

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 13 Damage Assessment & Remediat ion Plan

Page 13 - 10

C. Storm water

runoff 1. Sediment load 2. Contamination of run off due

to non-point source pollution.

1. Deterioration of the

water channel / drain

and impact on

aquatic life.

1. Proper channalization of

storm water with

intermediate grit

chambers (0.5 km.) in the

public drain within the

panchayat. 2. The vicinity of the project

site is frequently cleaned

to remove all non-point

sources before monsoon.

1. Chanalization of storm

water (Rs. 4,00,000/-). 2 Frequent cleaning of the

vicinity of site before

monsoon (Rs. 50,000/-). Total cost on remediation

measures is Rs. 4,50,000/-

(L.S. estimated)

Total cost on remediation measures on Water Environment is Rs. 16,80,000/-

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 13 Damage Assessment & Remediat ion Plan

Page 13 - 11

Ecological Environment

Activities which

caused damage

Concern Issues /

impacts

Damage

Assessment Remediation Plan

Budgetary Estimate

(in Rs.)

1. Site clearance

2. Cutting of

existing trees

1. Loss of vegetation in

the project site (about

100 trees were existing

at site)

2. Habitat loss to fauna

specially avi-fauna.

Loss of native flora

and aesthetic view

1. Plantation of native species as per

the guidelines (@1:10) to

compensate the cutting trees and

vegetation to regenerate the

aesthetic view.

2. Development of eco-friendly

situation in the project site to

welcome to faunal species again

at the project site

3. Development of butterfly garden

within the site.

4. Development of medicinal garden

within the site.

5. About 900 trees are already

existing / planted at site.

1. Plantation with native

species of flowering and

fruit bearing trees to

compensate the removal of

trees. About 1000 trees

within the surrounding area

are proposed for plantation

at a cost of @ Rs. 1,100

per plant which includes

maintenance for three

years. The total cost

estimate for tree plantation

is 1,000 trees x Rs. 1100 =

Rs. 11,00,000/-.

2.Cost of development of

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 13 Damage Assessment & Remediat ion Plan

Page 13 - 12

butterfly garden is

Rs. 2,00,000/- (L.S.

estimate)

3.Cost of development of

medicinal garden is Rs.

1,50,000/- (L.S. estimate)

4.Rs. 1,00,000/- for

development of panchayat

park / avenue plantation

towards habitat

compensation.

Total Rs. 13,50,000/-

Total cost on remediation measures on Ecological Environment is Rs. 13,50,000/-

M/s SREEVALSAM EDUCATIONAL TRUST EIA/EMP Report

Chapter 13 Damage Assessment & Remediat ion Plan

Page 13 - 13

Socio Economic Environment

Activities which

caused damage

Concern Issues /

impacts

Damage

Assessment

Remediation Plan Budgetary Estimate

(in Rs.)

Occupational Health

and amenities

1. Health aspects of the

construction workers

and facilities related to

hygiene and

sanitation.

2. Pressure on the

existing infrastructure

1. Secure facilities

to the construction

workers

1. Providing first aid kits (20

nos.) to the construction

sites (public works within

the panchayat).

2. Providing a wheel chair

(10 nos.) to the primary

health centre within the

panchayat and in

consultation.

Rs. 40,000/- (@Rs. 2,000 per

kit)

Rs. 1,20,000 (@Rs. 12,000

per wheel chair)

Total = Rs. 1,60,000/-

Total cost estimate on remediation measures on Socio Economic Environment is Rs. 1,60,000/-

M/s Sreevalsam Educational Trust EIA/EMP Report

Chapter 13 Damage Assessment & Remediat ion Plan Page 13 - 14

13.3 Summary of Remediation Plan – 3 Year Plan

The summary of remediation plan for 3 years is given in table 13.2 below.

Table 13.2 - Summary of remediation plan for 3 years

SN Activities Proposed 1st year 2nd Year 3rd Year Total

( in Rs.)

1. Remediation measures

on Air Environment 1,20,000 1,20,000 76,000 3,16,000

2. Remediation measures

on Noise Environment 20,000 20,000 10,000 50,000

3. Remediation measures

on Land Environment 50,000 45,000 35,000 1,30,000

4. Remediation measures

on Water Environment 6,80,000 6,50,000 3,50,000 16,80,000

5. Remediation measures

on Ecology Environment 5,40,000 5,50,000 2,60,000 13,50,000

6. Remediation measures

on Socio Environment 50,000 60,000 50,000 1,60,000

Annual total 14,60,000 14,45,000 7,81,000 36,86,000

M/s Sreevalsam Educational Trust EIA/EMP Report

Chapter 13 Damage Assessment & Remediat ion Plan Page 13 - 15

13.4 Natural Resources Augmentation Plan – 3 Year Plan

The natural resources augmentation plan for 3 years is prepared and is

provided at table 13.3 below.

Table 13.3 - Natural resources augmentation plan for 3 years

SN

Activities Proposed 1st year 2nd Year 3rd Year Total

( in Rs.)

1. Development of greenery in the surrounding area and road s ide plantation (along the approach road near to the project s i te, about 0.5 km in the northern direct ion of the project s ite)

50,000 50,000 60,000 1,60,000

2.

Provis ion of dr inking water facil i t ies through construction of open wells. 2 wells in each year in Edappal v i l lage and i ts maintenance

50,000 50,000 50,000 1,50,000

3.

Maintenance (patch work of pot holes) of approach road near to the project s i te, about 0.5 km in the northern direction of the project s i te in consultat ion with the public works department (PWD).

1,00,000 1,50,000 1,80,000 4,30,000

4.

Maintenance of water pipel ine network in Edappal town in consultat ion wi th Kerala Water Author ity (KWA).

40,000 40,000 40,000 1,20,000

5.

Providing solar street l ight in Darul Hidaya Orphanage Higher Secondary School, Edappal ( located at about 1.5 km toward north west d irect ion of the proposed project) for common area l ight ing in consultat ion wi th the school administrat ion

30,000 30,000 35,000 95,000

6.

Providing roof rain water storage tank (capacity of 5,000 li teres) with pipel ine for LP School located about 0.5 km toward south east direct ion.

50,000 50,000 55,000 1,55,000

7.

Maintenance of storm water drainage in the Govt. Higher Secondary School, Edappal located at about 2.5 km in nor th direct ion

18,000 20,000 45,000 83,000

Annual total 3,38,000 3,90,000 4,65,000 11,93,000

M/s Sreevalsam Educational Trust EIA/EMP Report

Chapter 13 Damage Assessment & Remediat ion Plan Page 13 - 16

13.5 Community Resources Augmentation Plan - 3 Year Plan

The Community Resources Augmentat ion Plan for 3 years is prepared and

is provided at table 13.4 below.

Table 13.4 - Community Resources Augmentation Plan for 3 years

Sr. No.

Activities Proposed 1st year 2nd Year 3rd Year Total

( in Rs.)

1. Maintenance of irr igat ion facil i t ies to the small farmers in Edappal vi l lage (support for irr igation in consultat ion with Irr igat ion Dept., Govt. of Kerala)

40,000 40,000 30,000 1,10,000

2.

Maintenance of k itchen and providing LPG for 3 years (noon meal preparation) in Govt. school located in Edappal vi l lage in consultat ion with school author it ies

20,000 40,000 80,000 1,40,000

3.

Periodic medical check-up camp for eyes, skin, dental twice in a year in consul tation with Edappal Vi l lage Panchayat / Health Department, Govt. of Kerala

50,000 50,000 50,000 1,50,000

4.

Distr ibut ion of medic ine to the needy patients and distr ibut ion of blood sugar check up k it in the Panchayats area of Edappal Vi l lage in consultat ion wi th Health Department, Govt. of Kerala.

50,000 40,000 30,000 1,20,000

5.

Providing health care to the farmers in Edappal vi l lage on consultat ion wi th the Heal th Dept. of Govt. of Kerala.

25,000 30,000 40,000 95,000

6.

Assistance in development of technical skil ls and tra in ing for f i rst aid to the emergency casualty to the youth of farmers in Edappal vi l lage

20,000 35,000 45,000 1,00,000

7.

Assistance in providing study materia ls, uniform, books to the poor students (50 students) of Govt. School , Edappal

20,000 25,000 30,000 75,000

8.

Scholarship to the br i l l iant students (10 students) of h igher secondary school / vocational higher secondary (100 students), Edappal for support to their higher education

30,000 25,000 20,000 75,000

ANNUAL TOTAL 2,55,000 2,85,000 3,25,000 8,65,000

M/s Sreevalsam Educational Trust EIA/EMP Report

Chapter 13 Damage Assessment & Remediat ion Plan Page 13 - 17

13.6 Summary of Remediation, Natural Resource & Community Augmentation Plan

Table 13.5 - Summary of Remediation, Natural Resource & Community Augmentation Plan

Sr.

No.

Activities

Proposed

1st year 2

nd Year 3

rd Year Total

(in Rs.)

1. Remediation plan 12,00,000 14,00,000 10,86,000 36,86,000

2. Natural Resource

plan 4,00,000 4,40,000 3,53,000 11,93,000

3. Community

Augmentation plan 3,00,000 3,20,000 2,45,000 8,65,000

Total 19,00,000 21,60,000 16,84,000 57,44,000

The project proponent wil l spend an amount of Rs 57,44,000/- (Rupees

Fifty Seven Lakhs Forty Four Thousand only) on account of

Remediation, Natural Resource & Community Augmentat ion Plan for 3

years. A bank guaranty for an amount of Rs. 57,44,000/- wil l be submitted

to the Kerala State Pollut ion Control Board valid for a period of 3 years.

On successful completion of the remediation plan, natural and community

augmentation plan and verif icat ion of the same by the Pollution Control

Board, the bank guaranty wil l be released to the project proponent. In

case, if the project proponent failed to implement the remediat ion plan,

natural and community augmentat ion plan as committed, the bank

guaranty will be forfeited.

*******************************************************************************

ANNEXURES

Appraisal by SEAC with a view to assess that the construction at the site

which under prevailing laws is permissible and which can be run sustainably

under compliance of environmental norms with adequate environmental safe

guards.

Closure of the project along

with other actions under law The project will be prescribed the appropriate Terms of

Reference for undertaking Environment Impact

Assessment and provision of Environment

Management Plan. The SEAC will prescribe a specific

Terms of Reference for the project on assessment of

ecological damage, remediation plan & natural and

community resource augmentation plan.

Application to be submitted by PP at SEIAA

Findings of SEACNEGATIVE AFFIRMATIVE

Preparation & submission of Environment Impact

Assessment and Environment Management Plan

which includes assessment of ecological damage,

remediation plan and natural and community resource

augmentation plan by PP at SEIAA.

The SEAC will stipulate the implementation of

Environmental Management Plan, comprising

PROCEDURE AS PER NOTIFICATION dt.14.03.2017 AND dt. 08.03.2018Annexure No. 1.2

Environmental Management Plan, comprising

remediation plan and natural and community resource

augmentation plan corresponding to the ecological

damage assessed as a condition of environmental

clearance.

The SEAC will quantify the amount of remediation plan

and Natural and Community Resource Augmentation

Plan which will be finalized by SEIAA.

PP need to submit bank guaranty equivalent to the

amount finalized by SEIAA to the State Pollution

Control Board.

After receipt of the acknowledgement of submission of

bank guaranty, SEIAA shall grant Environmental

Clearance to PP.

Successful implementation of the remediation plan and

Natural and Community Resource Augmentation Plan

by PP.

After the recommendation, (on the successful

implementation), by the Regional Office of the Ministry

and SEAC and after approval of the same by SEIAA,

the bank guaranty will be released to PP.

1

SCOPE OF THE STUDY AND COMPLIANCE TERMS OF REFERENCE IN THE EIA REPORT

Sr. No.

Terms of Reference Brief of the Compliance to the ToR Condition Reference in

the EIA report

1. Project description, its importance and the benefits

Chapter 1, Chapter 2 & Chapter 8

2. Project site details (location, toposheet of the study area of 10 km, coordinates, google map, layout map, land use, geological features and geo-hydrological status of the study area, drainage)

Project site details & Location

M/s Sreevalsam Educational Trust proposed an expansion of exist ing Hospital cum Medical College project at Survey Nos. 157/2, 159/3, 158/1, 157/0, 158/1, 159/3, 158/2, 158/5, 159/1, 159/2, 157, 159/3, 164/3, 164/7, 164/4, 163/3, 158/7, 158/3, 158/4, 166/2, 166/1, 156/3, 164/1, 156/3, 164/1, 164/2, 156/4, Edappal Vil lage, Ponnani Taluk, Malappuram District, Kerala. The plot area of the Hospital cum Medical College Project is 9.4534 ha (94,534.56 sq. m.) and the total buil t -up area is 1,38,937.50 sq. m. (existing 53,889.72 sq.m. + proposed 85,047.78 sq.m.).

Toposheet of the study area of 10 km

Toposheet of the study area is provided in Figure 2.5

Coordinates Latitude (N) - 10046‘00.86“ to 100 45’48.56“ Longitude (E) - 76000’36.45” to 760 00’23.53” (Refere Chapter-1, Page 1-5)

Google map Google map superimposed with project boundary is provided at Figure 2.4

Chapter 1, Chapter 2, Chapter 3

Annexure No. 1.8

2

Layout map Layout map (Conceptual plan) is provided at Figure 2.1

Land use Land use map is provided at Figure 3.4

Geological features & Geo-hydrological status of the study area

Details of Geological features are provided at Item 2.5 in Chaper-2 and Item no. 3.7.3 in Chapter-3

3. Land use as per the approved Master plan of the area, Permission / approvals required from the land owning agencies, Development Authorit ies, Local Body, Water supply & Sewerage Board etc.

The Land Use Certif icate and Land Conversion Cert if icate issued by Tahsildar, Ponnani on 31-03-2014 stat ing that the land is "do not fal l under Agricultural use and this land can be used for Education purpose to establish Education Institut ions". The copy of the said Land Conversion Cert if icate is attached at Annexure No. 1.6A & 1.6B

Chapter 1

4. Land acquisit ion status, R & R details

There is no displacement of people from the core zone of the project, hence Réhabil itat ion & Resett lement (R & R) is not applicable to the instant project.

Chapter 7

5. Forest and Wildli fe and eco-sensit ive zones, if any in the study area of 10 km - Clearance required under the Forest (Conservation) Act, 1980, the Wildl ife (Protection) Act, 1972 and /or the Environment (Protect ion) Act, 1986.

There is no Forest and Wildl ife and eco-sensit ive zones within the study area of 10 km. radius.

Chapter 2

6. Baseline environmental study for ambient air (PM10, PM2.5, SO2, NOx & CO), water (both surface and ground), noise and soil for one month

The Baseline environmental study for ambient air (PM10, PM2.5, SO2, NOx & CO), water (both surface and ground), noise and soil was carried out and the detai ls are provided in Chapter 3

Chapter 3

3

(except monsoon period) as per the MoEF&CC/CPCB guidelines at minimum 5 locations in the study area of 10 km.

7. Detai ls on f lora and fauna and socio-economic aspects in the study area

Details on f lora and fauna and socio-economic aspects in the study area is provided in Chapter 3

Chapter 3

8. Likely impact of the project on the environmental parameters (ambient air, surface and ground water, land, f lora and fauna and socio-economic etc.)

The likely impact of the project on the environmental parameters (ambient air, surface and ground water, land, f lora and fauna and socio-economic etc.) is described in Chapter 4.

Chapter 4

9. Source of water for dif ferent identif ied purposes with the permissions required from the concerned authorit ies, both for surface water and the ground water (by CGWA) and the case may be, Rain water harvesting etc.

Source of Water during construction phase

The sources of water for construct ion purposes wil l be from exist ing well water, stored rain water in pond and recycled water from existing STP. For domestic purposes, the sources of water will be from well water. There are open well (1 no.) and tube well (5 nos.) existing at “Sreevalsam Inst itute of Medical Sciences” campus. Source of Water during operation phase

The sources of water for meeting the domestic requirement as well as other requirements during operation phase of the proposed hospital cum medical col lege project will be from exist ing wells, stored rain water and recycled water from STP / ETP. Daily Water Requirement during operation phase The total daily water consumption for the proposed project would be about 1,328 KL (fresh water 677 KL + recycled water 651 KL). The f irst day fresh water requirement is 1,328 KL and subsequent days, the daily fresh water requirement is 677 KL. The daily domestic water consumption is 870 KL (f lushing purposes 647 KL + non-

Chapter 2

4

flushing purposes 223 KL). The details are given below :-

S. N.

Particulars Daily

Requirement (in KL)

Sources of water

1.

Domestic Water Requirement (Non-Flushing purposes )

647

Fresh water (Stored Rain

water and Ground water)

2. Domestic Water Requirement (Flushing purposes)

223 Recycled water

from STP

3. Hort iculture Water Requirement

55 Recycled water

from STP

4. Boiler water requirement

20 Recycled water

from STP

4.

Make-up Water Requirement for Cooling Towers attached with air conditioning system

353 Recycled water from STP/ETP

5. Laboratory & Laundry requirement

30

Fresh water (Stored Rain

water and Ground water)

10. Waste water management (treatment, reuse and disposal) for the project and also in the study area

The water balance chart showing the waste water management details and is provided in Figure 2.15 in Chapter 2

Chapter 2

11. Management of solid waste and the construct ion & demolition waste for the project vis-a-vis the Solid Waste Management Rules, 2016 and the Construction &

The Management of solid waste and the construction & demolit ion waste for the project vis-a-vis the Solid Waste Management Rules, 2016 and the Construction & Demolit ion Rules, 2016

Chapter 2

5

Demolit ion Rules, 2016

12 Energy eff icient measures (LED l ights, solar power etc.) during construction as well as during operational phase of the project

The details are elaborated in Chapter 7 Chapter 7

13 Assessment of ecological damage with respect to air, water, land and other environmental attributes. The collection and analysis of data shall be done by an environmental laboratory duly not if ied under the Environment (Protection) Act, 1986, or an environmental laboratory accredited by NABL, or a laboratory of a Counci l of Scientif ic and Industrial Research (CSIR) inst itution working in the field of environment.

The baseline monitoring on air, water, noise & soil was carried out through NABL accredited laboratory.

Chapter 3

14 Preparation of EMP comprising remediat ion plan and natural and community resource augmentat ion plan corresponding to the ecological damage assessed and economic benefits derived due to violat ion.

Details are provided in Chapter 13 Chapter 13

15 The remediation plan and the natural and community resource augmentat ion plan to be prepared as an

Details are provided in Chapter 13 Chapter 13

6

independent chapter in the EIA Report by the accredited consultants.

16 Public hearing As per the Terms of Reference provided by the MoEF&CC vide letter dated 22-06-2018, public hearing is to be conducted for the instant project. Thereafter, vide O.M. F.No.Z-11013/22/2017-IA.II(M) dated 16-03-2018 issued by MoEF&CC, no public hearing is required for building construction projects.

Chapter 7

**************************

Annexure No. 12.1