Corihuarmi Gold Project National Instrument 43-101 Technical ...
Revised NI 43-101 Technical Report Pre-Feasibility Study ...
-
Upload
khangminh22 -
Category
Documents
-
view
0 -
download
0
Transcript of Revised NI 43-101 Technical Report Pre-Feasibility Study ...
NOTE TO READER
An out of date filing titled “NI 43-101 Technical Report Pre-Feasibility Study Marmato Project Colombia” was filed on August 17, 2020. The correct and current technical report titled “Revised NI 43-101 Technical Report Pre-Feasibility Study Marmato Project Colombia” is attached to this filing. The material changes are:
• Statements of mineral reserves and mineral resources have been updated to specify whether such estimates include or exclude the mineral reserve tonnage.
• Figure 17-2 (process flow sheet for the MDZ process plant), which was inadvertently omitted from the original report, is now included in this amended report.
Revised NI 43-101 Technical Report Pre-Feasibility Study Marmato Project Colombia
Effective Date: March 17, 2020 Report Date: September 18, 2020
Report Prepared for
Caldas Gold Corp. 401 Bay Street, Suite 2400
Toronto, Ontario, Canada M5H 2Y4
Report Prepared by
SRK Consulting (U.S.), Inc.
1125 Seventeenth Street, Suite 600
Denver, CO 80202
SRK Project Number: 557200.030
Signed by Qualified Persons:
Ben Parsons, MSc, MAusIMM (CP), Practice Leader/Principal Consultant (Resource Geology)
Eric J. Olin, MSc Metallurgy, MBA, SME-RM, MAusIMM, Principal Consultant (Metallurgy)
Fernando Rodrigues, BS Mining, MBA, MAusIMM, MMSAQP, Practice Leader/Principal Consultant (Mining)
Jeff Osborn, BEng Mining, MMSAQP, Principal Consultant (Mining)
Joanna Poeck, BEng Mining, SME-RM, MMSAQP, Principal Consultant (Mining)
Fredy Henriquez, MS Eng, SME, ISRM, Principal Consultant (Rock Mechanics)
Breese Burnley, P.E., Practice Leader/Principal Engineer (Tailings) Cristian A Pereira Farias, SME-RM, Principal Consultant (Hydrogeology)
David Hoekstra, BS, PE, NCEES, SME-RM, Principal Consultant (Hydrology)
David Bird, PG, SME-RM, Associate Consultant (Geochemistry)
Mark Allan Willow, MSc, CEM, SME-RM, Practice Leader/Principal Consultant (Environmental)
Tommaso Roberto Raponi, P.Eng, Principal Metallurgist (Ausenco)
Reviewed by:
Berkley J. Tracy, MSc Geology, PG, CPG, PGeo, Principal Consultant (Resource Geology)
Tim Olson, BSc Mining, J.D., FAusIMM, Principal Consultant (Mining)
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page ii
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table of Contents
1 Summary ....................................................................................................................... 1
1.1 Property Description and Ownership .................................................................................................. 1
1.2 Geology and Mineralization ................................................................................................................ 1
1.3 Status of Exploration, Development and Operations .......................................................................... 3
1.4 Mineral Processing and Metallurgical Testing .................................................................................... 4
1.5 Mineral Resource Estimate ................................................................................................................. 5
1.6 Mineral Reserve Estimate ................................................................................................................. 10
1.7 Mining Methods ................................................................................................................................. 11
1.8 Recovery Methods ............................................................................................................................ 16
1.9 Project Infrastructure ......................................................................................................................... 18
1.9.1 Tailing Management Facilities ............................................................................................... 19
1.10 Environmental Studies and Permitting .............................................................................................. 19
1.10.1 Environmental Studies and Management ............................................................................. 19
1.10.2 Permitting .............................................................................................................................. 20
1.10.3 Social or Community Related Requirements ........................................................................ 21
1.10.4 Community Relations ............................................................................................................ 21
1.10.5 Mine Closure, Remediation, and Reclamation ...................................................................... 22
1.11 Capital and Operating Costs ............................................................................................................. 22
1.11.1 Marmato UZ Capital Costs .................................................................................................... 22
1.11.2 MDZ Capital Costs ................................................................................................................ 23
1.11.3 Marmato Operating Costs ..................................................................................................... 25
1.12 Economic Analysis ............................................................................................................................ 26
1.13 Conclusions and Recommendations ................................................................................................ 28
1.13.1 Property Description and Ownership .................................................................................... 28
1.13.2 Geology and Mineralization ................................................................................................... 28
1.13.3 Status of Exploration, Development and Operations ............................................................ 29
1.13.4 Mineral Processing and Metallurgical Testing....................................................................... 29
1.13.5 Mineral Resource Estimate ................................................................................................... 29
1.13.6 Mining and Reserves ............................................................................................................. 30
1.13.7 Recovery Methods ................................................................................................................ 33
1.13.8 Project Infrastructure ............................................................................................................. 33
1.13.9 Environmental Studies and Permitting .................................................................................. 34
1.13.10 Capital and Operating Costs ............................................................................................. 36
1.13.11 Economic Analysis ............................................................................................................ 37
2 Introduction ................................................................................................................ 39
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page iii
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
2.1 Terms of Reference and Purpose of the Report ............................................................................... 39
2.2 Qualifications of Consultants (SRK) .................................................................................................. 39
2.3 Details of Inspection .......................................................................................................................... 41
2.4 Sources of Information ...................................................................................................................... 42
2.5 Effective Date .................................................................................................................................... 43
2.6 Units of Measure ............................................................................................................................... 43
3 Reliance on Other Experts ........................................................................................ 44
4 Property Description and Location .......................................................................... 45
4.1 Property Location .............................................................................................................................. 45
4.2 Mineral Titles ..................................................................................................................................... 45
4.2.1 Nature and Extent of Issuer’s Interest ................................................................................... 49
4.3 Royalties, Agreements and Encumbrances ...................................................................................... 49
4.4 Environmental Liabilities and Permitting ........................................................................................... 49
4.4.1 Environmental Liabilities........................................................................................................ 49
4.4.2 Required Permits and Status ................................................................................................ 50
4.5 Other Significant Factors and Risks .................................................................................................. 50
5 Accessibility, Climate, Local Resources, Infrastructure and Physiography ........ 51
5.1 Topography, Elevation and Vegetation ............................................................................................. 51
5.2 Accessibility and Transportation to the Property .............................................................................. 51
5.3 Climate and Length of Operating Season ......................................................................................... 53
5.4 Sufficiency of Surface Rights ............................................................................................................ 53
5.5 Infrastructure Availability and Sources.............................................................................................. 53
5.5.1 Power .................................................................................................................................... 53
5.5.2 Water ..................................................................................................................................... 53
5.5.3 Mining Personnel ................................................................................................................... 53
5.5.4 Potential Tailings Storage Areas ........................................................................................... 54
5.5.5 Potential Waste Disposal Areas ............................................................................................ 54
5.5.6 Potential Processing Plant Sites ........................................................................................... 54
6 History ......................................................................................................................... 55
6.1 Prior Ownership and Ownership Changes ....................................................................................... 55
6.2 Exploration and Development Results of Previous Owners ............................................................. 56
6.3 Historic Mineral Resource and Reserve Estimates .......................................................................... 56
6.4 Historic Production ............................................................................................................................ 58
7 Geological Setting and Mineralization ..................................................................... 60
7.1 Regional Geology .............................................................................................................................. 60
7.2 Local Geology ................................................................................................................................... 62
7.2.1 Graphitic-Sericite Schist (MSG) ............................................................................................ 64
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page iv
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
7.2.2 Amphibolites (MAB) ............................................................................................................... 64
7.2.3 Serpentinites (MSP) .............................................................................................................. 64
7.2.4 Basalts (VB) .......................................................................................................................... 64
7.2.5 Clastic Sedimentary Rocks (S) ............................................................................................. 64
7.2.6 Marmato Porphyry Stocks (P1 – P5) ..................................................................................... 65
7.2.7 Unconsolidated Quaternary Deposits (QC) ........................................................................... 65
7.3 Property Geology .............................................................................................................................. 65
7.3.1 Structure ................................................................................................................................ 69
7.3.2 Alteration ............................................................................................................................... 71
7.4 Significant Mineralized Zones ........................................................................................................... 74
8 Deposit Type .............................................................................................................. 79
8.1 Mineral Deposit ................................................................................................................................. 79
8.2 Geological Model .............................................................................................................................. 79
9 Exploration ................................................................................................................. 81
9.1 Relevant Exploration Work ............................................................................................................... 81
9.1.1 Topographic Surveys ............................................................................................................ 81
9.1.2 Surface Geochemistry ........................................................................................................... 83
9.1.3 Geophysics ............................................................................................................................ 83
9.1.4 Surface Geological Mapping ................................................................................................. 83
9.1.5 Underground Geological Mapping ........................................................................................ 84
9.2 Sampling Methods and Sample Quality ............................................................................................ 85
9.2.1 Mine Geology - Channel Sampling Procedure ...................................................................... 85
9.2.2 Channel Sampling – Exploration ........................................................................................... 87
9.2.3 SRK Opinion of Quality ......................................................................................................... 89
9.3 Significant Results and Interpretation ............................................................................................... 91
10 Drilling ......................................................................................................................... 93
10.1 Type and Extent ................................................................................................................................ 93
10.2 Procedures ........................................................................................................................................ 95
10.2.1 Core Storage ......................................................................................................................... 97
10.2.2 Collar Surveys Surface .......................................................................................................... 98
10.2.3 Collar Surveys Underground ................................................................................................. 98
10.2.4 Drilling Orientation ................................................................................................................. 98
10.3 Interpretation and Relevant Results ................................................................................................ 101
11 Sample Preparation, Analysis and Security .......................................................... 102
11.1 Security Measures .......................................................................................................................... 102
11.2 Sample Preparation for Analysis ..................................................................................................... 102
11.2.1 Historical Sample Preparation (Pre 2010) ........................................................................... 102
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page v
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
11.2.2 Sample Preparation Mine Sampling (2010 – 2017) ............................................................ 103
11.2.3 Sample Preparation ............................................................................................................. 105
11.3 Sample Analysis .............................................................................................................................. 106
11.4 Quality Assurance/Quality Control Procedures .............................................................................. 107
11.4.1 Standards ............................................................................................................................ 109
11.4.2 Blanks .................................................................................................................................. 111
11.4.3 Duplicates ............................................................................................................................ 115
11.4.4 Actions/Reassays ................................................................................................................ 118
11.4.5 Check Analysis Results ....................................................................................................... 119
11.5 Opinion on Adequacy ...................................................................................................................... 121
12 Data Verification ....................................................................................................... 122
12.1 Procedures ...................................................................................................................................... 122
12.1.1 Verifications by CGM ........................................................................................................... 122
12.1.2 Verifications by SRK ............................................................................................................ 123
12.2 Limitations ....................................................................................................................................... 125
12.3 Opinion on Data Adequacy ............................................................................................................. 126
13 Mineral Processing and Metallurgical Testing ...................................................... 127
13.1 Metallurgical Program – 2019 ......................................................................................................... 127
13.1.1 Metallurgical Sample Characterization ................................................................................ 127
13.1.2 Mineralogy ........................................................................................................................... 129
13.1.3 Comminution Testwork ........................................................................................................ 129
13.1.4 Whole-Ore Cyanidation ....................................................................................................... 129
13.1.5 Gravity Concentration .......................................................................................................... 131
13.1.6 Cyanidation of Gravity Tailing ............................................................................................. 131
13.1.7 Variability Composites ......................................................................................................... 133
13.1.8 Flotation from Gravity Tailing .............................................................................................. 134
13.1.9 Cyanide Detoxification ......................................................................................................... 135
13.1.10 Solid-Liquid Separation ................................................................................................... 137
13.2 Metallurgical Program – 2020 ......................................................................................................... 139
13.2.1 Metallurgical Sample Location ............................................................................................ 139
13.2.2 Head Analyses .................................................................................................................... 146
13.2.3 Mineralogy ........................................................................................................................... 148
13.2.4 Comminution ....................................................................................................................... 148
13.2.5 Gravity Recoverable Gold (E-GRG) Testwork .................................................................... 151
13.2.6 Gravity Separation Testwork ............................................................................................... 152
13.2.7 Gravity Concentrate Cyanidation ........................................................................................ 154
13.2.8 Gravity Tailing Cyanidation Versus Grind Size ................................................................... 154
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page vi
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
13.2.9 Cyanidation Versus Cyanide Concentration and Pulp Density ........................................... 156
13.2.10 Cyanidation Versus Preaeration and Air Versus Oxygen Injection ................................ 158
13.2.11 Cyanidation Versus Cyanide Attenuation and Pulp Density ........................................... 160
13.2.12 “Hard Stop” Retention Time Tests .................................................................................. 162
13.2.13 Carbon-In-Leach (CIL) Tests .......................................................................................... 163
13.2.14 Variability Tests ............................................................................................................... 163
13.2.15 CIP Modelling Testwork .................................................................................................. 165
13.2.16 Cyanide Destruction Testwork ........................................................................................ 169
13.2.17 Tailing Thickening ........................................................................................................... 170
13.2.18 Tailings Filtration ............................................................................................................. 172
13.3 Recovery Estimate .......................................................................................................................... 174
13.4 Significant Factors ........................................................................................................................... 175
14 Mineral Resource Estimate ..................................................................................... 177
14.1 Drillhole Database ........................................................................................................................... 178
14.2 Geologic Model ............................................................................................................................... 179
14.2.1 Fault Network ...................................................................................................................... 179
14.2.2 Topographic Wireframes ..................................................................................................... 182
14.2.3 Lithological Wireframes ....................................................................................................... 182
14.2.4 Veins Model ......................................................................................................................... 183
14.2.5 Disseminated Model ............................................................................................................ 185
14.2.6 Splays Model ....................................................................................................................... 186
14.2.7 Porphyry “Pocket” Model ..................................................................................................... 187
14.2.8 MDZ ..................................................................................................................................... 189
14.3 Domains .......................................................................................................................................... 191
14.4 Assay Capping and Compositing .................................................................................................... 193
14.4.1 Outliers ................................................................................................................................ 193
14.4.2 Compositing ........................................................................................................................ 208
14.5 Density ............................................................................................................................................ 211
14.6 Variogram Analysis and Modeling .................................................................................................. 214
14.7 Block Model ..................................................................................................................................... 221
14.8 Estimation Methodology .................................................................................................................. 222
14.8.1 Theoretical Analysis ............................................................................................................ 222
14.8.2 Dynamic Anisotropy ............................................................................................................ 226
14.8.3 Threshold Capping .............................................................................................................. 227
14.8.4 Final Parameters ................................................................................................................. 227
14.9 Model Validation .............................................................................................................................. 230
14.9.1 Visual Comparison .............................................................................................................. 230
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page vii
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
14.9.2 Comparative Statistics ......................................................................................................... 235
14.9.3 Swath Plots ......................................................................................................................... 240
14.10 Resource Classification .................................................................................................................. 248
14.10.1 Measure Mineral Resources ........................................................................................... 248
14.10.2 Indicated Mineral Resources .......................................................................................... 248
14.10.3 Inferred Mineral Resources ............................................................................................. 249
14.10.4 Final Classification .......................................................................................................... 249
14.11 Depletion ......................................................................................................................................... 250
14.12 Mineral Resource Statement .......................................................................................................... 250
14.13 Comparison to the Previous Estimate ............................................................................................. 253
14.14 Mineral Resource Sensitivity ........................................................................................................... 254
14.15 Relevant Factors ............................................................................................................................. 260
15 Mineral Reserve Estimate ........................................................................................ 261
15.1 Conversion Assumptions, Parameters and Methods ...................................................................... 262
15.1.1 Upper Zone - Dilution .......................................................................................................... 262
15.1.2 Upper Zone - Recovery ....................................................................................................... 263
15.1.3 Upper Zone - Additional Allowance Factors ........................................................................ 264
15.1.4 Upper Zone – Cutoff Grade Calculation .............................................................................. 264
15.1.5 MDZ Mine - Dilution ............................................................................................................. 265
15.1.6 MDZ – Recovery ................................................................................................................. 266
15.1.7 MDZ - Additional Allowance Factors ................................................................................... 266
15.1.8 MDZ – Cutoff Grade Calculation ......................................................................................... 266
15.2 Reserve Estimate ............................................................................................................................ 267
15.3 Relevant Factors ............................................................................................................................. 268
16 Mining Methods ........................................................................................................ 270
16.1 Current Mining Methods .................................................................................................................. 270
16.1.1 Mine Layout ......................................................................................................................... 272
16.1.2 Reconciliation ...................................................................................................................... 274
16.1.3 Dilution................................................................................................................................. 274
16.2 Geotechnical ................................................................................................................................... 275
16.2.1 Geotechnical Data Base ...................................................................................................... 276
16.2.2 Engineering-Geology ........................................................................................................... 277
16.2.3 Stope Stability Assessment ................................................................................................. 279
16.2.4 Dilution................................................................................................................................. 279
16.2.5 Paste Fill Strength Estimation ............................................................................................. 279
16.2.6 PFS Ground Support Requirements ................................................................................... 280
16.2.7 Sill Pillar design ................................................................................................................... 281
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page viii
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
16.2.8 Critical Infrastructure Stability Assessment ......................................................................... 281
16.2.9 Limitations and Gaps ........................................................................................................... 284
16.2.10 Feasibility Study Recommendations ............................................................................... 285
16.3 Hydrogeology and Mine Dewatering ............................................................................................... 286
16.3.1 Hydrogeological Conditions ................................................................................................ 286
16.3.2 Descriptions of Numerical Groundwater Model .................................................................. 293
16.3.3 Results of Predictions by Groundwater Model .................................................................... 297
16.3.4 Hydrogeological Uncertainties ............................................................................................ 301
16.4 Upper Zone Mining .......................................................................................................................... 302
16.4.1 Stope Optimization .............................................................................................................. 302
16.4.2 Mine Design ........................................................................................................................ 304
16.4.3 Production Schedule ........................................................................................................... 305
16.4.4 Mining Operations ............................................................................................................... 310
16.4.5 Ventilation ............................................................................................................................ 312
16.4.6 Mine Services ...................................................................................................................... 313
16.4.7 Recommendations .............................................................................................................. 315
16.5 MDZ Mining ..................................................................................................................................... 316
16.5.1 Stope Optimization .............................................................................................................. 316
16.5.2 Mine Design ........................................................................................................................ 319
16.5.3 Production Schedule ........................................................................................................... 326
16.5.4 Mining Operations ............................................................................................................... 333
16.5.5 Ventilation ............................................................................................................................ 338
16.5.6 Mine Infrastructure & Services ............................................................................................ 343
16.5.7 Mine Labor .......................................................................................................................... 345
16.5.8 Equipment ........................................................................................................................... 347
16.6 Combined UZ and MDZ Production Schedule ................................................................................ 350
17 Recovery Methods ................................................................................................... 352
17.1 Marmato Process Plant (Current Operations) ................................................................................ 352
17.1.1 Crushing Circuit ................................................................................................................... 355
17.1.2 Grinding and Gravity Concentration Circuit ......................................................................... 355
17.1.3 Flotation and Concentrate Regrind Circuit .......................................................................... 355
17.1.4 Cyanidation and Counter-Current-Decantation (CCD) Circuit ............................................ 355
17.1.5 Merrill-Crowe Circuit and Smelter ....................................................................................... 356
17.1.6 Process Plant Consumables ............................................................................................... 356
17.1.7 Operating Performance ....................................................................................................... 357
17.1.8 Operating Costs .................................................................................................................. 357
17.2 Expansion Plans ............................................................................................................................. 358
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page ix
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
17.3 MDZ Process Plant ......................................................................................................................... 359
17.3.1 Processing Methods ............................................................................................................ 359
17.3.2 Plant Design and Equipment Characteristics ...................................................................... 361
17.3.3 Process Plant Description ................................................................................................... 362
17.3.4 Primary/Secondary Crushing and Stockpile ........................................................................ 364
17.3.5 Grinding ............................................................................................................................... 365
17.3.6 Gravity Concentration and Intensive Cyanide Leach Circuit ............................................... 366
17.3.7 Leach and Adsorption Circuit .............................................................................................. 366
17.3.8 Carbon Elution and Regeneration Circuit ............................................................................ 367
17.3.9 Electrowinning and Gold Room ........................................................................................... 368
17.3.10 Cyanide Detoxification .................................................................................................... 368
17.3.11 Tailings Thickening and Filtration ................................................................................... 368
17.3.12 Reagents ......................................................................................................................... 370
17.3.13 Services and Utilities ....................................................................................................... 372
17.3.14 Water Supply ................................................................................................................... 372
17.3.15 Operating Costs .............................................................................................................. 372
18 Project Infrastructure............................................................................................... 376
18.1 General Site Access........................................................................................................................ 376
18.2 Marmato Existing UZ Operations Infrastructure ............................................................................. 377
18.2.1 Existing Project Access ....................................................................................................... 377
18.2.2 Existing Project Facilities ..................................................................................................... 378
18.2.3 Energy Supply and Distribution - Existing Marmato Project ............................................... 380
18.2.4 Site Water Supply ................................................................................................................ 382
18.3 MDZ Introduction ............................................................................................................................. 382
18.4 MDZ Process Plant Site Location ................................................................................................... 382
18.4.1 Site Geotechnical ................................................................................................................ 384
18.5 MDZ On-Site Roads and River Crossings ...................................................................................... 384
18.5.1 Site Access Road ................................................................................................................ 384
18.5.2 River Crossing ..................................................................................................................... 384
18.6 MDZ Water Supply .......................................................................................................................... 384
18.6.1 Water Requirements ........................................................................................................... 384
18.6.2 Run-Off Water Collection and Treatment System ............................................................... 385
18.6.3 River Water Collection and Treatment System for MDZ and UZ ........................................ 385
18.7 MDZ Power Supply ......................................................................................................................... 385
18.7.1 Electrical Power Source ...................................................................................................... 385
18.7.2 Electrical Distribution ........................................................................................................... 385
18.7.3 Electrical Rooms ................................................................................................................. 386
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page x
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
18.7.4 Transformers ....................................................................................................................... 386
18.7.5 Standby/Emergency Power Supply ..................................................................................... 386
18.7.6 Ball and SAG Mill Drives ..................................................................................................... 386
18.7.7 Redundancy ........................................................................................................................ 386
18.8 MDZ Mine Operations Support Facilities ........................................................................................ 387
18.8.1 Mine Administration and Dry Building ................................................................................. 387
18.8.2 General Maintenance Building ............................................................................................ 387
18.8.3 Truck Wash Facility ............................................................................................................. 387
18.8.4 Truck Fuel Facility and Equipment Ready Line................................................................... 387
18.8.5 Explosives Storage .............................................................................................................. 387
18.9 MDZ Process Support Facilities ...................................................................................................... 387
18.9.1 Mill Administration Office and First Aid Facility ................................................................... 387
18.9.2 Laboratory ........................................................................................................................... 387
18.9.3 Warehouse and Storage Yard ............................................................................................. 388
18.9.4 Gatehouse and Weigh-Scale .............................................................................................. 388
18.10 Common Support Facilities ............................................................................................................. 388
18.10.1 Man Camp ....................................................................................................................... 388
18.11 MDZ Support Facilities .................................................................................................................... 388
18.11.1 Communications ............................................................................................................. 388
18.11.2 Wastewater Treatment .................................................................................................... 388
18.11.3 Solid Waste Disposal ...................................................................................................... 389
18.12 MDZ Site Preparation...................................................................................................................... 389
18.12.1 Site Earthwork ................................................................................................................. 389
18.12.2 Site Foundations ............................................................................................................. 389
18.13 MDZ Cemented Paste Backfill Plant ............................................................................................... 389
18.14 Site Water Management ................................................................................................................. 392
18.14.1 Water Supply ................................................................................................................... 392
18.15 Tailings Management Area ............................................................................................................. 394
18.15.1 Existing Tailings Management Facilities ......................................................................... 395
18.15.2 New Tailings Storage Facility Siting Study ..................................................................... 396
18.15.3 New Dry Stack Tailings Storage Facility Design ............................................................. 397
18.15.4 Tailings Risks and Opportunities .................................................................................... 406
18.16 Off-Site Infrastructure and Logistics Requirements ........................................................................ 407
18.16.1 Port .................................................................................................................................. 407
18.16.2 Rail .................................................................................................................................. 407
19 Market Studies and Contracts ................................................................................ 409
19.1 Commodity Price Projections .......................................................................................................... 409
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page xi
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
19.2 Contracts and Status....................................................................................................................... 409
20 Environmental Studies, Permitting and Social or Community Impact ................ 410
20.1 Environmental Studies .................................................................................................................... 410
20.1.1 Environmental Setting ......................................................................................................... 410
20.1.2 Management Procedures and Baseline Studies ................................................................. 411
20.1.3 Geochemistry ...................................................................................................................... 412
20.1.4 Known Environmental Issues .............................................................................................. 412
20.2 Mine Waste Management and Monitoring ...................................................................................... 413
20.2.1 Waste Rock Management ................................................................................................... 413
20.2.2 Tailings Management .......................................................................................................... 413
20.2.3 Site Monitoring .................................................................................................................... 414
20.2.4 Environmental Procedures and Permissions ...................................................................... 415
20.2.5 General Water Management ............................................................................................... 417
20.2.6 Environmental Management Budget ................................................................................... 417
20.3 Project Permitting Requirements .................................................................................................... 417
20.3.1 General Mining Authority ..................................................................................................... 417
20.3.2 Environmental Authority ...................................................................................................... 418
20.3.3 Environmental Regulations and Impact Assessment .......................................................... 419
20.3.4 Water Quality and Water Concessions ............................................................................... 420
20.3.5 Air Quality and Emissions ................................................................................................... 421
20.3.6 Fauna and Flora Protection ................................................................................................. 421
20.3.7 Protection of Riparian Areas and Drainages ....................................................................... 422
20.3.8 Protection of Cultural Heritage or Archaeology ................................................................... 422
20.3.9 Marmato Permitting ............................................................................................................. 422
20.3.10 Performance and Reclamation Bonding ......................................................................... 423
20.4 Social or Community Related Requirements .................................................................................. 424
20.4.1 Social Investment ................................................................................................................ 424
20.4.2 Community Relations .......................................................................................................... 425
20.4.3 Employment ........................................................................................................................ 425
20.4.4 Artisanal and Small-Scale Mining Operations ..................................................................... 425
20.5 Mine Closure, Remediation, and Reclamation ............................................................................... 426
20.5.1 Reclamation and Closure Costs .......................................................................................... 427
21 Capital and Operating Costs ................................................................................... 429
21.1 Capital Cost Estimates .................................................................................................................... 429
21.1.1 Marmato Upper Zone .......................................................................................................... 429
21.1.2 MDZ ..................................................................................................................................... 431
21.2 Operating Cost Estimates ............................................................................................................... 438
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page xii
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
21.3 Basis for Operating Cost Estimates ................................................................................................ 439
21.3.1 Marmato UZ ........................................................................................................................ 439
21.3.2 MDZ ..................................................................................................................................... 440
22 Economic Analysis .................................................................................................. 442
22.1 External Factors .............................................................................................................................. 442
22.2 Production Assumptions ................................................................................................................. 442
22.3 Taxes, Royalties and Other Interests .............................................................................................. 453
22.4 Results ............................................................................................................................................ 453
22.5 Sensitivity Analysis .......................................................................................................................... 458
23 Adjacent Properties ................................................................................................. 459
24 Other Relevant Data and Information ..................................................................... 460
24.1 Project Execution Plan .................................................................................................................... 460
24.1.1 Project Objectives ............................................................................................................... 460
24.1.2 General Project Description ................................................................................................ 460
24.1.3 Site Preparation and Infrastructure ..................................................................................... 461
24.1.4 Underground Mine and Supporting Infrastructure ............................................................... 463
24.1.5 Process Plant ...................................................................................................................... 463
24.1.6 Project Delivery Approach ................................................................................................... 464
24.1.7 Project Team Organization.................................................................................................. 466
24.1.8 Project Execution Supporting Plans .................................................................................... 469
25 Interpretation and Conclusions .............................................................................. 470
25.1 Property Description and Ownership .............................................................................................. 470
25.2 Geology and Mineralization ............................................................................................................ 470
25.3 Status of Exploration, Development and Operations ...................................................................... 470
25.4 Mineral Processing and Metallurgical Testing ................................................................................ 471
25.5 Mineral Resource Estimate ............................................................................................................. 471
25.6 Mining & Reserves .......................................................................................................................... 472
25.7 Recovery Methods .......................................................................................................................... 476
25.8 Project Infrastructure ....................................................................................................................... 476
25.8.1 Water Supply ....................................................................................................................... 476
25.8.2 Tailings Management Facility .............................................................................................. 477
25.9 Environmental Studies and Permitting ............................................................................................ 477
25.10 Capital and Operating Costs ........................................................................................................... 479
25.11 Economic Analysis .......................................................................................................................... 479
26 Recommendations ................................................................................................... 481
26.1 Recommended Work Programs ...................................................................................................... 481
26.1.1 Property Description and Ownership .................................................................................. 481
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page xiii
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
26.1.2 Geology and Mineral Resources ......................................................................................... 481
26.1.3 Mineral Processing and Metallurgical Testing..................................................................... 482
26.1.4 Mining & Reserves .............................................................................................................. 482
26.1.5 Recovery Methods .............................................................................................................. 484
26.1.6 Project Infrastructure ........................................................................................................... 484
26.1.7 Environmental Studies and Permitting ................................................................................ 485
26.1.8 Capital, Operating Costs and Economic Analysis ............................................................... 486
26.2 Recommended Work Program Costs ............................................................................................. 486
27 References ................................................................................................................ 488
28 Glossary .................................................................................................................... 490
28.1 Mineral Resources .......................................................................................................................... 490
28.2 Mineral Reserves ............................................................................................................................ 490
28.3 Definition of Terms .......................................................................................................................... 491
28.4 Abbreviations .................................................................................................................................. 492
List of Tables
Table 1-1: Caldas Mineral Resource(1) Statement with an Effective Date of March 17, 2020 ........................... 9
Table 1-2: Caldas Mineral Reserve Estimate as of March 17, 2020 – SRK Consulting (U.S.), Inc. ................ 11
Table 1-3: 2015 to 2020* Production ................................................................................................................ 12
Table 1-4: Marmato UZ Sustaining Capital (LoM) ............................................................................................ 23
Table 1-5: Marmato UZ Sustaining Capital (2020 to 2026) (US$) ................................................................... 23
Table 1-6: Marmato UZ Sustaining Capital (2027 to 2034) (US$) ................................................................... 23
Table 1-7: MDZ Construction Capital (US$) ..................................................................................................... 24
Table 1-8: MDZ Sustaining Capital (LoM) ........................................................................................................ 24
Table 1-9: MDZ Sustaining Capital (2023 to 2027) (US$) ................................................................................ 25
Table 1-10: MDZ Sustaining Capital (2028 to 2033) ........................................................................................ 25
Table 1-11: UZ Operating Costs Summary ...................................................................................................... 25
Table 1-12: MDZ Operating Costs Summary ................................................................................................... 26
Table 1-13: Marmato Indicative Economic Results .......................................................................................... 27
Table 1-14: LOM All-in Sustaining Cost Breakdown ........................................................................................ 28
Table 1-15: LoM All-in Sustaining Cost Breakdown ......................................................................................... 36
Table 1-16: Marmato Indicative Economic Results .......................................................................................... 37
Table 2-1: Site Visit Participants ....................................................................................................................... 41
Table 6-1: Ownership History at Marmato ........................................................................................................ 55
Table 6-2: SRK Mineral Resource Statement for the Marmato Project, Dated July 31, 2019*, Within Zona Baja** ................................................................................................................................................... 58
Table 6-3: Gold Production from the Municipality of Marmato 2004 to December 2019 ................................. 59
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page xiv
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 10-1: Summary of Drilling Completed by Company ............................................................................... 93
Table 11-1: Summary Of QA/QC Sample Submissions During 2018 Submissions To SGS And ALS Laboratories ....................................................................................................................................... 108
Table 11-2: Summary Of QA/QC Sample Submissions During 2019 Submissions To SGS And ALS Laboratories ....................................................................................................................................... 108
Table 11-3: Summary Of QA/QC Sample Submissions During 2020 Submissions To SGS Laboratory (Up to SMT20-018) ....................................................................................................................................... 109
Table 11-4: Summary of CRM’s Submitted During Routine Assay Submissions .......................................... 109
Table 11-5: Summary Statistics for Field Duplicates (2019-2020) ................................................................. 115
Table 11-6: Summary Statistics for Coarse Duplicates to SGS and ALS Submissions (Au g/t), 2019-2020 117
Table 11-7: Summary Statistics for Coarse Duplicates to SGS and ALS Submissions (Au g/t), 2019-2020 118
Table 11-8: Summary Statistics for 2019 Reassays Program to SGS vs ALS Submissions (Au g/t) ............ 119
Table 12-1: Comparison of Mine Planned Grades (Assayed at Mine Laboratory) Versus Head-Grades ..... 124
Table 13-1: Drillholes and Intervals for MDZ Metallurgical Composites ................................................. 127
Table 13-2: Head Analyses for MDZ and Marmato Test Composites ............................................................ 128
Table 13-3: Comminution Test Results on MDZ and Marmato Test Samples ........................................ 129
Table 13-4: Whole-Ore Cyanidation Test Results on MDZ Test Composite .................................................. 130
Table 13-5: Summary of Gravity Concentration Testwork on MDZ and Marmato Composites (1) ................. 131
Table 13-6: MDZ Master Composite Gravity Tailing Leach Conditions ......................................................... 132
Table 13-7: Gravity Concentration + Gravity Tailing Cyanidation Test Results ............................................. 132
Table 13-8: Summary of Gravity Concentration + Gravity Tailing Cyanidation (Variability Composites) ...... 134
Table 13-9: Summary of Rougher Flotation Tests on Gravity Tailings from MDZ and Marmato Composites ........................................................................................................................................................... 134
Table 13-10: Summary of Flotation Concentrate Cyanidation Test Results .................................................. 135
Table 13-11: Summary of Cyanide Detoxification Testwork on MDZ Composite Leach Residue ........ 136
Table 13-12: Static Thickener Test Conditions .............................................................................................. 137
Table 13-13: Summary of Dynamic Thickener Test Results .......................................................................... 137
Table 13-14: Results of Rheology Testwork on MDZ Thickener Underflow Sample ..................................... 138
Table 13-15: Drill Holes and Intervals Used for the Low Grade MDZ Composite .......................................... 140
Table 13-16: Drill Holes and Intervals Used for the Medium Grade MDZ Composite ................................... 141
Table 13-17: Drill Holes and Intervals Used for the High Grade MDZ Composite ......................................... 143
Table 13-18: Drill Core Holes and Intervals Used for the MDZ Deep Composite .......................................... 144
Table 13-19: Drill Core Holes and Intervals Used for the Transition Composite............................................ 145
Table 13-20: Drill Core Holes and Intervals Used for Crushing (CWI) Testwork ........................................... 146
Table 13-21: Head Analyses for Key Elements .............................................................................................. 147
Table 13-22: Head Analyses and Multi-Element Scan on Each Test Composite .......................................... 147
Table 13-23: Summary of Comminution Test Results .................................................................................... 149
Table 13-24: Summary of SMC Test Results ................................................................................................. 149
Table 13-25: Summary of SPI Tests .............................................................................................................. 150
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page xv
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 13-26: Summary of Bond Ball Mill Work Index (BWI) Tests ................................................................. 150
Table 13-27: Summary of Bond Low Energy Crushing Tests ........................................................................ 151
Table 13-28: Summary of Abrasion Index Determinations ............................................................................. 151
Table 13-29: Summary of E-GRG Test on MDZ Master Composite .............................................................. 151
Table 13-30: Summary of E-GRG Modeling ................................................................................................... 152
Table 13-31: Summary of Gravity Concentration Testwork ........................................................................... 153
Table 13-32: Summary of Intensive Leach Test on Gravity Concentrate ...................................................... 154
Table 13-33: Summary of Cyanide Leach Test Gold Extractions Versus Grind Size .................................... 155
Table 13-34: Summary of Cyanide Leach Test Silver Extractions Versus Grind Size ................................... 156
Table 13-35: Gold Extraction Versus Cyanide Concentration and Slurry Density ......................................... 157
Table 13-36: Summary Cyanidation Tests with Preaeration and Air Versus Oxygen Injection ..................... 159
Table 13-37: Summary of Cyanide Attenuation and Slurry Density Tests ..................................................... 161
Table 13-38: Summary of Hard Stop Leach Retention Time Tests ............................................................... 163
Table 13-39: Summary of CIL Tests Versus Retention Time with Optimized Leach Conditions ................... 163
Table 13-40: Variability Composites – Gold Recovery Under Optimized Conditions .................................... 164
Table 13-41: Variability Composites – Silver Recovery Under Optimized Conditions ................................... 165
Table 13-42: Modeled Design Parameters for a Multi-stage CIP Adsorption Circuit ..................................... 168
Table 13-43: Modeled Gold Concentrations in Solids, Solution and Carbon in a Multi-Stage CIP Circuit .... 169
Table 13-44: Summary of Cyanide Destruction Tests Conducted on Master Composite Leach Residues ... 170
Table 13-45: Summary of High Rate Thickening Test on MDZ Master Composite Leached Tailing ............. 171
Table 13-46: Summary of High Rate Thickening Test on MDZ Transition Composite Leached Tailing ........ 171
Table 13-47: Pressure Filtration Test Results on the Master Composite Tailing Sample .............................. 172
Table 13-48: Pressure Filtration Test Results on the Transition Composite Tailing Sample ......................... 173
Table 13-49: Vacuum Filtration Test Results on the Master Composite Tailing Sample ............................... 173
Table 13-50: Vacuum Filtration Test Results on the Transition Composite Tailing Sample .......................... 173
Table 13-51: Estimated Gold and Silver Recoveries from the MDZ (PFS and PEA Metallurgical Programs) ........................................................................................................................................................... 174
Table 14-1: Summary of Number of Records for Each Exported .csv ........................................................... 178
Table 14-2: Summary of Geological Database Information for Drilling Reported by Company ..................... 178
Table 14-3: Summary of Geological Database Information for Channel Reported by Company .................. 179
Table 14-4: Summary of Leapfrog 0.7 g/t Indictor Grade Shell, ISO Value Sensitivity Study (MDZ Material) ........................................................................................................................................................... 191
Table 14-5: Summary of Domain Coding Used in the 2017 Mineral Resource Estimate .............................. 192
Table 14-6: Summary Raw Sample Statistics Based on Defined Geological Domains (Group) ................... 193
Table 14-7: Summary of Capping Sensitivity – MDZ Domain (Group 5000), Selected Capping Highlighted in Orange ............................................................................................................................................... 201
Table 14-8: Summary of Capping Sensitivity – MDZ Domain (Group 5000), selected capping highlighted in orange ................................................................................................................................................ 205
Table 14-9: Comparison Raw vs Composite Statistics .................................................................................. 207
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page xvi
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 14-10: Comparison Statistics ................................................................................................................ 211
Table 14-11: Summary of Density Statistics by Rock Type and Selected Density ........................................ 212
Table 14-12: Density assigned per rocktype in 2020 Mineral Resources ...................................................... 214
Table 14-13: Summary of Variogram Parameters per Group ........................................................................ 220
Table 14-14: Block Model Prototype (DatamineTM format) ............................................................................. 221
Table 14-15: Summary of Key Fields in Block Model ..................................................................................... 222
Table 14-16: Summary of Datamine Estimates by Search Volume and Validation by Estimation Type (OK, ID, NN)..................................................................................................................................................... 225
Table 14-17: Summary of Domains with Top Capping and Sliding Thresholds for Wider Search Volumes . 227
Table 14-18: Summary of Estimation Search Parameters Used in Estimation .............................................. 229
Table 14-19: Summary of Statistical Validation of Raw, Declustered, OK, ID2 and NN Block Estimates ..... 236
Table 14-20: Summary of CoG Assumptions at Marmato Based on Assumed Costs (Averaged for All Mining Styles) ................................................................................................................................................ 251
Table 14-21: Caldas Mineral Resource(1) Statement with Effective Date of March 17, 2020 ........................ 253
Table 14-22: Grade Tonnage Curve Measured and Indicated - Vein Domains (Group 1000 to 3000) ......... 255
Table 14-23: Grade Tonnage Curve Measured and Indicated - Porphyry Domain (Group 4000) ................. 255
Table 14-24: Grade Tonnage Curve Measured and Indicated - MDZ Domain (Group 5000) ........................ 256
Table 14-25: Grade Tonnage Curve Inferred - Vein Domains (Group 1000 - 3000) ..................................... 256
Table 14-26: Grade Tonnage Curve Inferred - Porphyry Domain (Group 4000) ........................................... 257
Table 14-27: Grade Tonnage Curve Inferred - MDZ Domain (Group 5000) .................................................. 257
Table 15-1: Dilution Assumption ..................................................................................................................... 263
Table 15-2: Mining Extraction/Recovery Assumptions ................................................................................... 263
Table 15-3: Cut-off Grade Parameters for Veins Material .............................................................................. 264
Table 15-4: Cut-off Grade Parameters for Transition Material ....................................................................... 264
Table 15-5: Dilution Assumptions ................................................................................................................... 265
Table 15-6: Additional Ramp Allowance Factors ........................................................................................... 266
Table 15-7: MDZ Underground Cut-off Grade Calculation ............................................................................. 267
Table 15-8: Caldas Mineral Reserve Estimate as of March 17, 2020 – SRK Consulting (U.S.), Inc. ............ 268
Table 16-1: 2015 to 2020* Production ............................................................................................................ 270
Table 16-2: Level Elevations and Description ................................................................................................ 273
Table 16-3: Summary of Structural Sets ........................................................................................................ 278
Table 16-4: Uniaxial Compressive Strength Test Results .............................................................................. 280
Table 16-5: Ground Support Requirements ................................................................................................... 281
Table 16-6: FS Geotechnical Drilling Plan (Tunnel Investigation) .................................................................. 283
Table 16-7: Measured Bedrock Hydraulic Conductivity Values at Depth ....................................................... 287
Table 16-8: Simulated Hydraulic Parameters ................................................................................................. 294
Table 16-9: Predictive Scenarios Evaluated by Groundwater Model ............................................................. 297
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page xvii
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 16-10: Predicted Maximum Mine Inflows and Reduction of Groundwater Discharge to the Rivers and Creeks Under Different Scenarios ..................................................................................................... 301
Table 16-11: Productivity Rates ..................................................................................................................... 305
Table 16-12: Marmato Upper Mine Total Production Schedule ..................................................................... 307
Table 16-13: Marmato Upper Mine Total Development Schedule ................................................................. 308
Table 16-14: Manpower by Department ......................................................................................................... 314
Table 16-15: Marmato Equipment List ........................................................................................................... 315
Table 16-16: Undiluted Stope Optimization Results for Varying Cut-off Grades ........................................... 318
Table 16-17: MDZ Mine Design Summary – by Activity Type ........................................................................ 325
Table 16-18: Productivity Rates ..................................................................................................................... 327
Table 16-19: Schedule Parameters for Underground Mining ......................................................................... 327
Table 16-20: Material Characteristics for Ore and Waste .............................................................................. 327
Table 16-21: Main Ramp Average Development Rate – Long Term Development Openings ...................... 328
Table 16-22: Footwall Access Development Rate – Medium Term Openings* ............................................. 329
Table 16-23: Drift Access Development Rate – Short Term Openings* ........................................................ 329
Table 16-24: Stope Production Rate .............................................................................................................. 330
Table 16-25: MDZ Production Schedule ........................................................................................................ 331
Table 16-26: Truck Hauling Speeds ............................................................................................................... 334
Table 16-27: Backfill Volume Summary – By Type ................................................................................... 336
Table 16-28: Recommended Maximum Air Velocities for Various Airway Types .......................................... 339
Table 16-29: Equipment List and Airflow Requirement .................................................................................. 339
Table 16-30: Auxiliary Ventilation Fan Summary ........................................................................................... 341
Table 16-31: Fan Operating Points* ............................................................................................................... 342
Table 16-32: MDZ Shift Schedule and Rotation ............................................................................................. 345
Table 16-33: MDZ Mining Labor Summary .................................................................................................... 345
Table 16-34: MDZ Mining Labor ..................................................................................................................... 346
Table 16-35: Mine Equipment by Period ........................................................................................................ 348
Table 17-1: Equipment List for Marmato Process Plant ................................................................................. 354
Table 17-2: Marmato Process Plant Consumables ................................................................................... 356
Table 17-3: Summary of Marmato Process Plant Operating Performance and Recovery Estimate ............. 357
Table 17-4: Marmato Process Plant Operating Costs: 2019 - 2020 (Jan-Apr) .............................................. 357
Table 17-5: Summary of Marmato Process Plant Expansion Capex ............................................................. 359
Table 17-6: Process Design Criteria Summary .............................................................................................. 361
Table 17-7: Operating Cost Summary ............................................................................................................ 373
Table 17-8: Operations and Maintenance Manpower Schedule .................................................................... 374
Table 17-9: Light Vehicles and Mobile Equipment Summary ......................................................................... 375
Table 18-1: DSTF Design Criteria .................................................................................................................. 399
Table 18-2: Stormwater Diversion Channel Summary ................................................................................... 403
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page xviii
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 19-1: Marmato Price Assumptions ....................................................................................................... 409
Table 19-2: Marmato Net Smelter Return Terms ........................................................................................... 409
Table 20-1: Water Discharges ........................................................................................................................ 415
Table 20-2: Stationary Emission Sources ...................................................................................................... 415
Table 20-3: Environmental Procedures .......................................................................................................... 416
Table 20-4: Surface Water Concessions ........................................................................................................ 420
Table 21-1: Marmato UZ Sustaining Capital (LoM) ........................................................................................ 429
Table 21-2: Marmato UZ Sustaining Capital (2020 to 2026) (US$) ............................................................... 430
Table 21-3: Marmato UZ Sustaining Capital (2027 to 2034) (US$) ............................................................... 430
Table 21-4: Marmato UZ Capital Development Unit Costs ............................................................................ 431
Table 21-5: Marmato UZ Capital Development Meters (2020 to 2023) ......................................................... 431
Table 21-6: MDZ Construction Capital (US$) ................................................................................................. 432
Table 21-7: MDZ Pre-Production Development Unit Costs ............................................................................ 433
Table 21-8: MDZ Pre-Production Development Meters ................................................................................. 433
Table 21-9: MDZ Processing Plant and Infrastructure Capital ....................................................................... 434
Table 21-10: MDZ Sustaining Capital (LoM) .................................................................................................. 435
Table 21-11: MDZ Sustaining Capital (2023 to 2027) (US$) .......................................................................... 435
Table 21-12: MDZ Sustaining Capital (2028 to 2033) (US$) .......................................................................... 435
Table 21-13: MDZ Development Sustaining Capital Unit Costs .................................................................... 436
Table 21-14: MDZ Development Sustaining Capital Meters (2023 to 2027) (US$) ....................................... 436
Table 21-15: MDZ Development Sustaining Capital Meters (2028 to 2032) .................................................. 436
Table 21-16: MDZ Mining Sustaining Capital (2023 to 2027) (US$) .............................................................. 437
Table 21-17: MDZ Mining Sustaining Capital (2028 to 2032) (US$) .............................................................. 437
Table 21-18: MDZ DSTF Sustaining Capital (2023 to 2027) (US$) ............................................................... 437
Table 21-19: MDZ DSTF Sustaining Capital (2028 to 2032) .......................................................................... 438
Table 21-20: MDZ Rio Sucio Power Line Sustaining Capital (2028 to 2032) ................................................ 438
Table 21-21: Marmato UZ Operating Costs Summary ................................................................................... 438
Table 21-22: Marmato MDZ Operating Costs Summary ................................................................................ 438
Table 21-23: Marmato UZ Operating Development Unit Costs ...................................................................... 439
Table 21-24: Marmato UZ Operating Development Meters (2020 to 2024) ................................................... 439
Table 21-25: Marmato UZ Mineral Processing Operating Costs .................................................................... 440
Table 21-26: Marmato UZ TSF And G&A Operating Costs (2020 to 2026) (US$) ........................................ 440
Table 21-27: Marmato UZ DSTF And G&A Operating Costs (2027 to 2033) (US$) ...................................... 440
Table 21-28: MDZ Mining Operating Costs (2023 to 2027) (US$) ................................................................. 440
Table 21-29: MDZ Mining Operating Costs (2028 to 2033) ........................................................................... 441
Table 21-30: MDZ Mineral Processing Cost ................................................................................................... 441
Table 21-31: MDZ DSTF And G&A Operating Costs (2023 to 2027) ............................................................ 441
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page xix
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 21-32: MDZ DSTF And G&A Operating Costs (2028 to 2033) ............................................................ 441
Table 22-1: Marmato Price Assumptions ....................................................................................................... 442
Table 22-2: Marmato NSR Terms .................................................................................................................. 442
Table 22-3: Marmato Production Summary .................................................................................................... 443
Table 22-4: Marmato Yearly (2020 to 2026) Mine Production Assumptions .................................................. 445
Table 22-5: Marmato Yearly (2027 to 2033) Mine Production Assumptions .................................................. 446
Table 22-6: Marmato Mill Production Assumptions ........................................................................................ 449
Table 22-7: Marmato Mill Production Schedule (2020 - 2026) ....................................................................... 450
Table 22-8: Marmato Mill Production Schedule (2027 - 2033) ....................................................................... 451
Table 22-9: Marmato UZ LoM Cash Flow Metrics .......................................................................................... 454
Table 22-10: MDZ LoM Cash Flow Metrics .................................................................................................... 455
Table 22-11: Marmato Indicative Economic Results (Combined UZ and MDZ) ............................................ 457
Table 22-12: Marmato LoM Annual Production and Revenues ..................................................................... 457
Table 22-13: LoM All-in Sustaining Cost Breakdown ..................................................................................... 458
Table 24-1: Project Work Breakdown Structure – Level 1 and Level 2 .......................................................... 466
Table 24-2: Owner’s Project Team with EPCM Supplements ........................................................................ 468
Table 25-1: LoM All-in Sustaining Cost Breakdown ....................................................................................... 479
Table 25-2: Marmato Indicative Economic Results ........................................................................................ 480
Table 26-1: Summary of Costs for Recommended Work ............................................................................... 487
Table 28-1: Definition of Terms ...................................................................................................................... 491
Table 28-2: Abbreviations ............................................................................................................................... 492
List of Figures Figure 1-1: Cross-Section Showing License Splits at Marmato ......................................................................... 8
Figure 1-2: UZ Production Schedule Colored by Time Period ......................................................................... 14
Figure 1-3: MDZ Mine Production Schedule Colored by Year ......................................................................... 15
Figure 1-4: Combined UZ and MDZ Mining Profile – Tonnes and Grade ........................................................ 16
Figure 1-5: Marmato After-Tax Free Cash Flow, Capital and Metal Production .............................................. 26
Figure 1-6: Marmato Operating Cost Break-Down ........................................................................................... 27
Figure 4-1: Location Map .................................................................................................................................. 45
Figure 4-2: Land Tenure Map(s) ....................................................................................................................... 46
Figure 4-3: Summary of Gap in Licenses Within the Current Operations, with Associated Applications ........ 48
Figure 5-1: Marmato Project, Looking Northwest Towards Cerro El Burro ...................................................... 52
Figure 7-1: Regional Geology Map ................................................................................................................... 61
Figure 7-2: Local Geology Map ........................................................................................................................ 62
Figure 7-3: Regional Geology with Gold Prospects in the Marmato Area ........................................................ 63
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page xx
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Figure 7-4: Photographs of the Different Porphyritic Intrusive Bodies that Make Up the Porphyry Stock Of Marmato ............................................................................................................................................... 67
Figure 7-5: Property Geology Map ................................................................................................................... 68
Figure 7-6: Cross-Section of the Marmato Gold Deposit Looking NW Showing the Intrusions P1 to P5 ........ 69
Figure 7-7: TCL Interpretation of Vein Orientations at Marmato ...................................................................... 71
Figure 7-8: Types of Alteration Found at Marmato ........................................................................................... 73
Figure 7-9: Structural Features Expected in a North-South Sinistral Riedel Fault System .............................. 75
Figure 7-10: Example of Epithermal Veins as Viewed in the Drilling Core at Marmato ................................... 76
Figure 7-11: Examples from Drill Core of the Different Mineralization Styles .................................................. 77
Figure 7-12: MDZ Mineralization Showing Veinlets Including Visible Gold (Au). BHID MND282-03-17 at a Depth of 1,010 masl, Sample of 1.20 m with 18.06 g/t Au and 2.5 g/t Ag ........................................... 78
Figure 9-1: Development of 3D Topography for the Project Showing LIDAR Survey Points, Shadow Model and 3D View of 1 m Resolution LIDAR Datapoints .................................................................................... 83
Figure 9-2: Example of Level Plan from CGM (Level 20) ................................................................................. 84
Figure 9-3: Channel Sample Marks in Marmato ............................................................................................... 85
Figure 9-4: Underground Workings Survey Using Total Station ...................................................................... 86
Figure 9-5: Sample Collection and Packing ..................................................................................................... 86
Figure 9-6: Distribution of Channel Sampling Along the Vein .......................................................................... 87
Figure 9-7: Channel Sample Cut Using Electrical Saw .................................................................................... 88
Figure 9-8: Identification Ticket and Bags Used to Pack the Channel Sample ................................................ 89
Figure 9-9: 2D Plan View of Sampling Data Versus Vein Interpretations, Showing New Sample Data Highlighted in Red, Versus Plan Section of Veins in Blue (Level 1250 M) ......................................... 92
Figure 10-1: Location Map Showing Drillholes Completed at Marmato by Company ...................................... 94
Figure 10-2: 3D View of Sampling Data, Showing New Exploration Drilling Data Highlighted in Red and Mine Drilling in Purple (Looking North) ......................................................................................................... 95
Figure 10-3: Core Photographs Before and After Making the Respective Cut and Sampling ......................... 96
Figure 10-4: Core Storage Facility at Marmato Constructed in 2010 and Current Status 2019 ...................... 97
Figure 10-5: Plan Showing Primary Drilling Orientation to the South and Southwest Relative to the Main Mineralization Orientation at Depth ..................................................................................................... 99
Figure 10-6: Cross Section (Orientated Looking Northeast), Showing Orientation of Drilling Relative to the Deep Mineralization, and Horizontal Drilling in the Current Operation .............................................. 100
Figure 11-1: Sample Preparation at Mine Laboratory Showing New Equipment (Crusher and Pulverizer) .. 104
Figure 11-2: Sample Preparation Facilities at ACME Laboratories in Medellín ............................................. 105
Figure 11-3: Summary of CRM Submissions to SGS In 2019/2020 Program ............................................... 110
Figure 11-4: Summary of CRM Submissions to ALS In 2019 Program ......................................................... 110
Figure 11-5: Example of Timeline Review Of CRM G914-6 (2019) and G315-2 (2020) Submissions .......... 111
Figure 11-6: SGS and ALS Coarse Blank Submissions 2019 ........................................................................ 112
Figure 11-7: SGS Coarse Blank Submissions 2020 ...................................................................................... 113
Figure 11-8: SGS and ALS Fine Blank Submissions 2019 ............................................................................ 114
Figure 11-9: SGS Fine Blank Submissions 2020 ........................................................................................... 115
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page xxi
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Figure 11-10: Summary of Field Duplicate 2019-2020 ................................................................................... 116
Figure 11-11: Summary of Coarse Duplicate Submissions to SGS (left) and ALS (right) for 2019-2020 ...... 117
Figure 11-12: Summary of Pulp Duplicate Submissions to SGS (left) and ALS (right), 2019 - 2020 ............ 118
Figure 11-13: Summary of 2019-2020 Reassay (Secondary Laboratory) ..................................................... 119
Figure 11-14: Summary of Check Assays Completed on Pulp Material (Quarterly Checks), Scatter Plot (Left) and Mean vs Relative Difference Plot (Right) ................................................................................... 120
Figure 11-15: Summary of Check Assays Completed on Reject Material (Quarterly Checks), Scatter Plot (Left) and Mean vs Relative Difference Plot (Right) ................................................................................... 120
Figure 12-1: Comparison of Planned Versus Actual Gold Grades at Marmato Mine..................................... 124
Figure 13-1: Drillhole Locations ...................................................................................................................... 128
Figure 13-2: Gold Extraction Versus Retention Time (MDZ Master Comp Gravity Tailings) ......................... 133
Figure 13-3: Yield Stress Versus Thickener Underflow Slurry Density .......................................................... 139
Figure 13-4: Drill Hole Locations Used for Metallurgical Composites ............................................................ 146
Figure 13-5: Gold Extraction Versus Leach Retention Time for Air and Oxygen Injection ............................ 160
Figure 13-6: Gold Extraction Versus Leach Retention Time .......................................................................... 162
Figure 14-1: Fault Network Compared to Mapping on Level 20 (1056 RL) ................................................... 181
Figure 14-2: Cross Section Showing SRK Revised Lithological Model ......................................................... 183
Figure 14-3: Level 20 Geological Mapping Versus Sampling Database and Veins Model, Showing the Level of Information Integrated into the Geological Model .............................................................................. 185
Figure 14-4: Level Plan (1065 RL), Showing Interaction Between Vein and Disseminated Vein Domains ... 186
Figure 14-5: Development of Porphyry Pockets Wireframe Methodology ..................................................... 188
Figure 14-6: Development of MDZ model ...................................................................................................... 190
Figure 14-7: Box Plot Showing Raw Sample Statistics Based on Defined Geological Domains (Group) ..... 192
Figure 14-8: Disintegration Analysis Au (g/t) – Veins, Group 1000 (Vein_N<9000) ...................................... 194
Figure 14-9: Disintegration Analysis Au (g/t) – Veins, Group 1000 (Vein_N>9000) ...................................... 195
Figure 14-10: Disintegration Analysis Au (g/t) – Disseminated Vein, Group 2000 (Vein_N<9000) ............... 196
Figure 14-11: Disintegration Analysis Au (g/t) – Disseminated Vein, Group 2000 (Vein_N>9000) ............... 197
Figure 14-12: Disintegration Analysis Au (g/t) – Splays, (Group 3000) ......................................................... 198
Figure 14-13: Percentile Analysis Au (g/t) – Porphyry Domain, (Group 4000) .............................................. 200
Figure 14-14: Percentile Analysis Au (g/t) – MDZ Domain, (Group 5000) ..................................................... 204
Figure 14-15: Summary Histograms and Cumulative Frequency of Raw Sample Lengths per Domain ....... 209
Figure 14-16: Log Probability Plot of Density Measurements Logged as Vein .............................................. 213
Figure 14-17: Omni Directional Variograms Defined for Au and Ag for Domains Group = 1000 – 4000 ....... 217
Figure 14-18: Group 5000 Au Directional Semi-Variograms .......................................................................... 218
Figure 14-19: Group 5000 Ag Directional Semi-Variograms .......................................................................... 219
Figure 14-20: Group 5000 (MDZ), KNA Analysis Using Snowden Supervisor .............................................. 223
Figure 14-21: Example of Default Search Orientations Used Within the MDZ High-Grade Domain ............. 226
Figure 14-22: Visual Validation of Selected Veins at Marmato ...................................................................... 232
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page xxii
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Figure 14-23: Visual Validation of Selected Disseminated Veins at Marmato ............................................... 233
Figure 14-24: Section and Level Plan Example of Visual Validation of MDZ (Group 1000) .......................... 234
Figure 14-25: Swath Analysis Group 1000 Au (g/t) ........................................................................................ 241
Figure 14-26:Swath Analysis Group 2000 Au (g/t) ......................................................................................... 242
Figure 14-27: Swath Analysis Group 3000 Au (g/t) ........................................................................................ 243
Figure 14-28: Swath Analysis Group 4000 Au (g/t) ........................................................................................ 244
Figure 14-29: Swath Analysis Group 5000 – INDZONE=0 (LG) Au (g/t) ....................................................... 245
Figure 14-30: Swath Analysis Group 5000 – INDZONE=1 (MG) Au (g/t) ...................................................... 246
Figure 14-31: Swath Analysis Group 5000 – INDZONE=2 (HG) Au (g/t) ....................................................... 247
Figure 14-32: Final Classification for the Marmato Project (Looking Northwest Bearing 305) ...................... 249
Figure 14-33: Final Classification for License #014-89m Marmato Project (Looking Northwest Bearing 305) ........................................................................................................................................................... 250
Figure 14-34: Cross-Section Showing License Splits at Marmato ................................................................. 252
Figure 14-35: Grade Tonnage Curves Showing Sensitivity to Changes in Cut-Off for Measured and Indicated Mineralized Material ........................................................................................................................... 258
Figure 14-36: Grade Tonnage Curves Showing Sensitivity to Changes in Cut-Off for Inferred Mineralized Material .............................................................................................................................................. 259
Figure 15-1: Marmato General Layout ........................................................................................................... 262
Figure 15-2: Veins Dilution ............................................................................................................................. 263
Figure 15-3: UZ Grade/Tonne Curve Based on Au Cut-Off ........................................................................... 265
Figure 15-4: MDZ Grade/Tonne Curve Based on Au Cut-Off ........................................................................ 267
Figure 15-5: License Gap ............................................................................................................................... 269
Figure 16-1: Typical Shrinkage Stoping Diagram ........................................................................................... 271
Figure 16-2: Conventional Cut and Fill Method Diagram ............................................................................... 272
Figure 16-3: Marmato Zona Baja Cross Section Looking NE with Active Levels ........................................... 273
Figure 16-4: Marmato Level 18 with Main Haulage (Mined Out Panels in Cyan) .......................................... 274
Figure 16-5: UZ Planned Dilution ................................................................................................................... 275
Figure 16-6: Location of Geotechnical Drill Holes (As-Builts and MDZ Design Shown) ................................ 276
Figure 16-7: Geotechnical Subdomains ......................................................................................................... 277
Figure 16-8: Structural Domains ..................................................................................................................... 278
Figure 16-9: Conveyor Tunnel Trajectory ....................................................................................................... 283
Figure 16-10: FS Drill Hole Location (Tunnel Investigation) ........................................................................... 284
Figure 16-11: Distribution of Measured Hydraulic Conductivity Values vs. Depth ......................................... 287
Figure 16-12: Estimated Water Table and Direction of Groundwater Flow .................................................... 289
Figure 16-13: Conceptual Hydrogeological Cross-Section ............................................................................ 290
Figure 16-14: Scheme of Current Dewatering System ................................................................................... 291
Figure 16-15: Measured Mine Water Discharge ............................................................................................ 292
Figure 16-16: Model Grid Discretization – Plan View ..................................................................................... 293
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page xxiii
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Figure 16-17: Modeled Cross-Section ............................................................................................................ 294
Figure 16-18: Simulated Rivers, Creeks and Groundwater Outflows ............................................................ 295
Figure 16-19: Simulated Developments and Stopes for Planned Mine ......................................................... 296
Figure 16-20: Predicted Mine Inflow During Years 2021 to 2032 (Base Case) ............................................. 298
Figure 16-21: Comparison of Total Predicted Dewatering Requirements for Base Case and Sensitivity Scenarios ........................................................................................................................................... 298
Figure 16-22: Predicted Water Table and Direction of Groundwater Flow at End of Mining Shown on West to East Cross-Section through Mine Area ............................................................................................. 299
Figure 16-23: Predicted Drawdown at End of Mining (Base Case, End of 2032) .......................................... 300
Figure 16-24: Stope Optimization results for the Veins (Section looking Northeast) ..................................... 302
Figure 16-25: Stope Optimization Results for the Transition (Section Looking Northeast) ............................ 303
Figure 16-26: Stope Optimization Results for the UZ Colored by Au Grade (Section Looking Northeast) .... 303
Figure 16-27: Transition Mining Method (Magenta is Primary and Cyan is Secondary) ................................ 304
Figure 16-28: Plan View of Transition Development ...................................................................................... 305
Figure 16-29: Production Schedule Colored by Time Period ......................................................................... 310
Figure 16-30: Marmato Hydraulic Backfill System ......................................................................................... 312
Figure 16-31: Level 21 Exhaust Collection Area ............................................................................................ 313
Figure 16-32: New Exhaust System ............................................................................................................... 313
Figure 16-33: Resource Model – AU blocks (g/t) above Mining CoG (Looking North) .................................. 317
Figure 16-34: Undiluted Stope Optimization Results for Varying Cut-off Grades .......................................... 318
Figure 16-35: Stope Cross Section ................................................................................................................ 319
Figure 16-36: Typical Level Section ............................................................................................................... 320
Figure 16-37: MDZ Mine Design (Rotated View Looking Southwest) ............................................................ 321
Figure 16-38: MDZ Main Decline Cross Section ............................................................................................ 322
Figure 16-39: MDZ Mine Design (Rotated View Looking Southwest) ............................................................ 323
Figure 16-40: MDZ Mine Design, Colored by Au Grade ................................................................................ 324
Figure 16-41: MDZ Design with Sur and Ines Faults (Rotated View - Looking Northwest) ........................... 326
Figure 16-42: Mine Production Schedule Colored by Year ............................................................................ 332
Figure 16-43: Haulage Distance – One Way Length ...................................................................................... 335
Figure 16-44: Haulage Cycle Time - Roundtrip .............................................................................................. 336
Figure 16-45: Marmato Project General Ventilation Scheme ......................................................................... 341
Figure 16-46: Estimated Fan Power Demand ................................................................................................ 342
Figure 16-47: Combined UZ and MDZ Mining Profile – Tonnes and Grade .................................................. 350
Figure 16-48: Combined UZ and MDZ Mining Profile - Contained Metal ....................................................... 351
Figure 17-1: Marmato Process Flowsheet.................................................................................................. 353
Figure 17-2: Proposed MDZ Process Flow Sheet .......................................................................................... 360
Figure 17-3: Mill/Leach/Reagents General Arrangement ............................................................................... 363
Figure 17-4: Primary/Secondary Crushing and Stockpile .............................................................................. 364
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page xxiv
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Figure 17-5: Grinding and Gravity Concentrate and Intensive Leach Area ................................................... 365
Figure 17-6: Pre-Aeration and Leach Tanks .................................................................................................. 366
Figure 17-7: CIP and Detoxification Tanks, Acid Wash and Elution Columns, Regeneration Kiln, and Gold Room Areas ....................................................................................................................................... 367
Figure 17-8: Tailings Thickener and Thickener Underflow Storage Tank Area ............................................. 369
Figure 17-9: Tailings Pressure Filter Plant Area ............................................................................................ 370
Figure 18-1: Marmato Project Location .......................................................................................................... 376
Figure 18-2: Marmato General Access and Major Facilities .......................................................................... 378
Figure 18-3: Marmato Existing Project Site Map ............................................................................................ 379
Figure 18-4: Marmato Electrical System Schematic ...................................................................................... 381
Figure 18-5: Overall Site Plan ........................................................................................................................ 383
Figure 18-6: Paste Plant General Arrangement ............................................................................................. 391
Figure 18-7: Paste Plant 3D Layout ............................................................................................................... 392
Figure 18-8: Makeup and Demand at the Upper Zone Process Plant ........................................................... 393
Figure 18-9: Makeup and Demand at the MDZ Process Plant ...................................................................... 394
Figure 18-10: Proposed Configurations of Cascabels 1 and 2....................................................................... 396
Figure 18-11: Potential DSTF Sites Identified Through Siting Study ............................................................. 397
Figure 18-12: Internal Drainage System ......................................................................................................... 401
Figure 18-13: Pre-Cast Concrete Span Channel Crossing ............................................................................ 402
Figure 18-14: Watersheds for DSTF 1 (Top) and DSTF 2 (Bottom) .............................................................. 404
Figure 18-15: DSTF Haul and Access Roads ................................................................................................ 405
Figure 22-1: Marmato UZ Mine Production Profile ......................................................................................... 447
Figure 22-2: MDZ Mine Production Profile ..................................................................................................... 447
Figure 22-3: Marmato Combined UZ and MDZ Mine Production Profile ....................................................... 448
Figure 22-4: Marmato UZ Processing Production Profile ............................................................................... 452
Figure 22-5: MDZ Processing Production Profile ........................................................................................... 452
Figure 22-6: Marmato Processing Production Profile ..................................................................................... 453
Figure 22-7: Marmato UZ Cash Flow Profile .................................................................................................. 454
Figure 22-8: MDZ Cash Flow Profile .............................................................................................................. 455
Figure 22-9: Marmato After-Tax Free Cash Flow, Capital and Metal Production .......................................... 456
Figure 22-10: Marmato Operating Cost Break-Down (Combined UZ and MDZ) ........................................... 456
Figure 22-11: Marmato NPV Sensitivity ......................................................................................................... 458
Figure 24-1: Project Execution Schedule ....................................................................................................... 465
Figure 24-2: MDZ Project Team ..................................................................................................................... 467
Figure 26-1: 2020 Exploration Plan Showing Phases A through C (Left to Right) ......................................... 482
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page xxv
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Appendices Appendix A: Certificates of Qualified Persons
Appendix B: MDZ Tailings Drawings
Appendix C: Economic Model Snapshots
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 1
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
1 Summary This report was prepared as a Pre-Feasibility Study (PFS) level Canadian National Instrument 43-101
(NI 43-101) Technical Report (Technical Report) for Caldas Gold Corp. (Caldas Gold) in respect of the
Marmato Project (Marmato Project) owned by Caldas Gold Marmato S.A.S. (CGM or the Company),
an indirect, wholly-owned subsidiary of Caldas Gold, by SRK Consulting (U.S.), Inc. (SRK).
1.1 Property Description and Ownership
The Marmato Project is located between latitudes and longitudes 5°28’24”N and 5°28’55”N, and
75°34’46”W and 75°37’80”W, respectively; with altitudes ranging from approximately 200 to 1,705
meters (m). What has been traditionally termed the Marmato Project was made up of three separate
areas within the historic Marmato mining district named Zona Alta (License #CHG_081), Zona Baja
(License #014-89m) and Echandia (License #RPP_357), of which Zona Baja is 100% owned by CGM
and Zona Alta and Echandia are owned indirectly, through other subsidiaries, by Gran Colombia Gold
Corp. (Gran Colombia). CGM is currently in the process of extending the duration of the Zona Baja
mining contract for which the current 30-year term expires in October 2021.
Notwithstanding the historical designation of the Marmato Project described above, in this report the
“Marmato Project” or “Project” refers to the mining assets (CGM Mining Assets) principally comprising
the existing producing underground gold mine (#014-89m), the existing 1,200 tonnes per day (t/d)
processing plant defined in this report as the Upper Zone, and the area encompassing the Marmato
Deep Zone (MDZ) mineralization, all located within the mining license area referred to as Zona Baja.
The CGM Mining Assets also include two contractual rights:
• One, granted by Minera Croesus, S.A.S. (Croesus), an indirect, wholly owned subsidiary of
Gran Colombia, to mine in the lower portion of the Echandia license (#RPP_357) area
• A second license in the process of being completed, to be granted by Minerales Andinos de
Occidente S.A.S. (MAO), an indirect, wholly owned subsidiary of Gran Colombia, to mine
portions of levels 16 and 17 of Zona Alta (License #CHG_081); this license represents a small
potential upside to add additional material via access from the current mine. This material is
currently excluded from the Mineral Resource Statement and mine plan.
SRK noted within the transfer of licenses from the previous owner a gap between the existing licenses
for Zona Baja (#014-89m) and Echandia (#RPP_357), and CGM applied to the Colombian government
for formal approval to continue mining in the identified gap. SRK has reviewed the application within
the government website and noted that the status is defined as “in progress”, which has been the
reported status since September 30, 2009. SRK understands that at the end of the pre-feasibility study
process (May 2020) the issue was resolved with the government determining that there is no gap and
that the area falls within the license for Zona Baja (#014-89m). As the license gap is no longer an
issue, there may be additional optimization opportunities for the Marmato Project that should be
explored during the next phase of work.
1.2 Geology and Mineralization
The local geology is dominated by porphyritic dacitic and andesitic intrusions, which host the
mineralization at Marmato. The intrusions are characterized by quartz, hornblende, biotite and zoned
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 2
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
plagioclase phenocrysts in a finely crystalline quartz-plagioclase groundmass, with variations in
phenocryst proportion and sizes between intrusions. A total of five different porphyry units have been
identified.
The Marmato gold deposit consists of a structurally controlled epithermal vein system with a mineral
assemblage dominated by pyrite, arsenopyrite, black iron (Fe) rich sphalerite, pyrrhotite, chalcopyrite
and electrum in the Upper Zone (UZ), and a mesothermal veinlet system with a mineral assemblage
dominated by pyrrhotite, chalcopyrite, bismuth minerals and visible gold in the MDZ.
The mineralization in the current mine consists of three distinct phases, a first phase characterized by
the mesothermal vein/veinlet mineralization, which defines the MDZ, followed by an epithermal low
sulfidation style, superimposed by an epithermal intermediate sulfidation phase. Gold‐silver
mineralization is mainly hosted by a pyrite+sphalerite vein to veinlet system fitting in a sinistral
transpressional shearing system, associated with intermediate argillic alteration within the host
porphyryitic rocks. Approximately 92% of the gold/silver-bearing particles are intergrown with sulfides
or occur at sulfide gangue grain boundaries. Current mining in the area is via narrow underground
stoping of the higher-grade vein mineralization.
The MDZ mineralization consists of a network of thin, less than 5 centimeters (cm), sulfide veinlets,
mainly pyrrhotite+chalcopyrite, hosted in weak argillic and deeper potassic alteration which is related
to a previous event and rimmed by a thin sodium-calcitic alteration halo, which is related to the
mineralization. Recent geological reports on MDZ (Sillitoe, 2019) concluded:
• Gold grade distribution in the Zona Baja (MDZ) mineralized orebody is unrelated to the
presence of distinct porphyry phases and is entirely dependent on the intensity of structurally
localized veinlets
• Potassic alteration, represented chiefly by biotite, is progressively better preserved at depth in
the Zona Baja, raising the possibility that early potassic alteration could also be gold bearing,
but further work is required to confirm this theory
• Gold distribution appears to be exclusively a product of veinlet intensity and orientation related
to structural controls during orogenesis. The veinlets responsible for much of the Zona Baja
gold are those containing quartz, pyrrhotite and traces of chalcopyrite and having prominent
albite alteration halos
• The presence of visible gold is also noted in the core and, as expected, relates to increased
assay values when present
Mineralization occurs in parallel, sheeted and anastomosing veins (vein domain), all of which follow a
regional structural control, with minor veins forming splays of the main structures (splays) which often
have limited strike or dip extent. The upper vein domain intersects broader zones of intense veinlet
mineralization (termed porphyry domain in this Technical Report) that is hosted by a lower grade
mineralized porphyry stock. In addition, a discrete, relatively high-grade core (feeder zone) to the main
deeper mineralization termed locally as the MDZ.
The upper portion of the MDZ has been exposed in Level 21 of the existing Caldas mining operations,
while deeper sections have been observed in drillcore, both of which have been confirmed as different
styles of mineralization. The lowest levels of the mine have currently intersected a combination of the
porphyry domain, where the gold is associated with pyrite veinlets, and the MDZ where gold is
associated with pyrrhotite. There is a transition zone existing between the two domains, which is
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 3
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
observed to some extent in the current mine workings with overprinting of the epithermal system on
the MDZ. The vertical extent of the transition is not clearly defined from the current drilling. Currently,
underground mining at the Caldas-operated mine remains focused on the vein structures located in
the central portion (Zona Baja) of the Marmato deposit.
Diamond drilling indicates that the veins typically range between 0.5 and 5 m wide and extend for 250
to 1,000 m along strike and 150 to 750 m down dip. These observations are supported by underground
mining which has confirmed that individual vein structures have good geological continuity and can
extend for 100 to 800 m along strike and 100 to at least 300 m down dip. Between 2017 and 2020,
CGM has worked on updating the quantity of the underground channel sampling captured in the
database, which has increased the information available to model the vein domains.
The broad zones of veinlet mineralization in the porphyry domain was modelled initially by SRK in
2017 and typically varied from 10 to 230 m wide, reaching up to 340 m wide in areas of significant
veinlet accumulation, while extending with good geological continuity for between 200 m and
approximately 950 m along strike and between 100 and 900 m down dip. SRK has updated these
domains during the 2019 geological modelling process using more discrete zones and application of
an indicator grade shell approach using a 0.5 grams per tonne (g/t) gold (Au) cut-off grade (CoG).
At depth within the central portion of the deposit, SRK has noted a zone of elevated grades which has
been referred to as the higher grade MDZ (more than 2 g/t Au). This zone is indicated to be continuous
along strike for approximately 500 m and has a confirmed down dip extent that reaches up to 800 m,
with a thickness that varies between 35 and 150 m. It is possible that the main MDZ mineralization is
bounded within a series of faults but limited drilling at the edges of the deposit make confirmation
difficult to assess at this stage. To avoid the potential for volumetric “blow-outs”, SRK has used the
faults as a hard boundary in the geological domaining process.
1.3 Status of Exploration, Development and Operations
The latest sampling has comprised selective infill drilling targeting the MDZ to a spacing of 50 to 100 m
and additional underground channel sampling within the CGM operated mine, which extends from
Levels 16 to 21.
A total of 1,357 drillholes have been used to inform the 2020 Marmato Mineral Resource Estimate
(MRE) including historic drilling and more recent drilling completed between the 2019 Preliminary
Economic Assessment (PEA) and this PFS. A total of 40 new drillholes from the exploration and mine
developed have been included since the 2019 PEA for a total of 12,555 m of new drilling.
In addition to the drilling information, CGM has captured information from the mine and exploration
channel sampling databases. Limited new sampling has been captured between the 2019 PEA and
the current study; in total, 26,307 channel samples exist in the database for a combined sample length
of 42,328 m. In CGM commissioned a detailed topographic map with 0.5 and 1 m resolution contour
intervals derived from LIDAR imagery, which was supplied to Datamine™ in 2020. The new
topographic map provides a detailed base map for improved accuracy when plotting the results of the
exploration programs, as well as a high-resolution satellite image. All data has been converted and
stored in the Magna Sirgas/Colombia West coordinate system (MSCW).
All samples were prepared, and fire assayed by SGS Laboratories at their facility in Medellin. CGM
has carried out routine Quality Control and Quality Assurance programs (QA/QC) to monitor the quality
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 4
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
during the process. The results of the drilling have validated aspects of the previous interpretation, but
also provided additional information
1.4 Mineral Processing and Metallurgical Testing
Metallurgical programs were conducted by SGS Lakefield (SGS) in 2019 and 2020 to evaluate the
processing requirements for the MDZ. The 2019 metallurgical program was conducted as part of the
2019 PEA that was prepared for the Project, and the 2020 metallurgical program was conducted to
support the current PFS. The 2020 metallurgical program was conducted to further define the process
parameters and design criteria for the selected flowsheet that includes gravity concentration followed
by cyanidation of the gravity tailings. The test program included gravity concentration, gravity
recoverable gold (E-GRG determination) cyanide leach optimization and carbon-in-pulp (CIP)
modelling, cyanide destruction (CND), solid/liquid separation and environmental testwork. The
optimization and metallurgical design tests were all completed using the MDZ master composite. Once
the optimized flowsheet had been selected, the variability test samples were tested under these
optimized gravity/cyanidation conditions.
Key findings from the 2020 metallurgical program include the following:
• The PFS metallurgical program was conducted on an MDZ master composite and on
variability composites representing low, medium and high grade MDZ ore, transition zone and
the MDZ deep zone.
• Native gold was by far the predominant gold carrier, and the majority (more than 99%) of the
gold particles occurred within mineral structures that would be readily accessible by leaching
solutions. Gold particles were not often in direct contact with sulfides, yet very commonly
pyrrhotite, chalcopyrite, and bismuth minerals were found in close vicinity to the gold
mineralization
• The metallurgical program optimized process parameters required to recover gold and silver
values from MDZ ore using a process flowsheet that includes gravity concentration followed
by cyanidation of the gravity tailing.
• Comminution tests were conducted on the MDZ master composite, MDZ deep zone
composite, three MDZ sub-composites (low grade, medium grade and high grade) and on the
Marmato mine composite. The comminution tests included SAG Mill Comminution (SMC),
SAG Mill Power Index (SPI) and Bond ball mill work index (BWI) tests. In addition, Bond Low
Impact Crushing work index (CWI) and abrasion (AI) tests were conducted on selected ½ HQ
drill core pieces.
o The results of the SMC (A x b) values ranged from 23 to 29, indicating the ore is hard with
respect to impact breakage.
o The BWI values for the MDZ composites range from 17.7 kilowatt hour per tonne (kWh/t)
to 19.8 kWh/t, which places them in the hard range of hardness.
• E-GRG testwork and modeling indicate that about 40% of the gold contained in the MDZ ore
can recovered into a gravity concentrate. Gold contained in the gravity tailing could be
recovered in a standard CIP cyanidation leach circuit.
• An intensive cyanide leach test on the gravity concentrate demonstrated that 99.7% of the
contained gold and 87.9% of the contained silver could be extracted from the gravity
concentrate without regrinding.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 5
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
• Based on the results of the PFS metallurgical program, overall gold recovery (gravity
concentration + gravity tailing cyanidation) is estimated at 95% and overall silver recovery is
estimated at 51%. This is very similar to the results from the PEA metallurgical program in
which gold recovery was estimated at 95% and silver recovery was 47%. There is little
difference in reported gold recoveries for the master and variability composites, and gold
recovery appears to be independent of ore grade over the range tested.
• Cyanide destruction tests demonstrated that weak acid dissociable cyanide (CNWAD) could be
reduced to less than 10 milligrams per liter (mg/L) with the SO2/air process. However, CNWAD
levels would further attenuate to less than 1 mg/L with time.
• Pressure filtration will be required to dewater thickened tailings in order to achieve less than
15% moisture content required for disposal in a dry stack tailings facility (DSTF).
1.5 Mineral Resource Estimate
The Mineral Resource model presented herein represents an updated resource evaluation prepared
for the Marmato Project. The resource estimation methodology involved the following procedures:
• Database compilation and verification
• Construction of wireframe models for the fault networks and centerlines of mining development
per vein
• Definition of resource domains
• Data conditioning (compositing and capping) for statistical and geostatistical analysis
• Variography
• Block modelling and grade interpolation
• Resource classification and validation
• Assessment of “reasonable prospects for economic extraction” and selection of appropriate
reporting cut-off grades (CoGs)
• Preparation of the Mineral Resource Statement
The resource evaluation work was completed by Mr. Benjamin Parsons, MAusIMM (CP#222568), with
assistance from Mr. Giovanny Ortiz, FAusIMM (#304612). The effective date of the Mineral Resource
Statement is March 17, 2020, which is the last date assays were provided to SRK.
The mineral resource estimation (MRE) process was a collaborative effort between SRK and CGM
staff. CGM provided SRK with an exploration database with flags of the main veins as interpreted by
CGM. In addition to the database, CGM has also supplied a geological interpretation comprising
preliminary three dimensional (3D) digital files (DXF) of the areas investigated by core drilling for each
of the main veins.
SRK imported the geological information into Seequent Leapfrog® Geo (Leapfrog®) to complete the
geological model. Leapfrog® has been selected due to the ability to rapidly create accurate geological
interpretations, which interact with a series of geological conditions and data types.
SRK has produced block models using Datamine™ Studio RM Software (Datamine™). The procedure
involved the import from Leapfrog™Geo of wireframe models for the fault networks, veins, definition
of resource domains (e.g. high-grade sub-domains), data conditioning (compositing and capping) for
statistical analysis, geostatistical analysis, variography, block modelling and grade interpolation
followed by validation.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 6
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Grade estimation for the veins has been based on block dimensions of 5 m by 10 m by 10 m. Sub-
blocking to 0.5 m by 1 m by 1 m has been allowed to reflect the narrow nature of the geological model.
The block size reflects the relatively close-spaced underground channel sampling and spacing within
veins compared to the wider drilling spacing, with the narrower block size used in the MDZ at depth to
reflect the proposed geometry of the mineralization (i.e. steeply dipping feeder zone).
SRK reviewed and updated the geostatistical properties of the domains. Gold grades have been
interpolated using nested three-pass estimates within Datamine™, using an Ordinary Kriging (OK)
routine. SRK has also run Inverse Distance Weighted (IDW2) and Nearest Neighbor (NN) estimates
for validation purposes.
The search ellipses follow the typical orientation of the mineralized structures and where appropriate,
were aligned along the mineralized veins, as detailed below:
• Dynamic searches were used for the vein mineralization domains. Within these domains, the
true dip and true dip direction has been calculated on a block by block basis
• In comparison, given the relatively short strike and dip of the splay, SRK has elected to use
an average dip and strike for each structure
• For the porphyry domain, SRK has generated a default dip and dip-direction to orientate the
search volume along the main regional trend
• For the MDZ, a single dip and strike has been used with the search ranges orientated along
the main dip and strike of the domain
• All contacts between the veins have been treated as hard boundaries for domaining with only
coded samples from any given vein used in the estimation of that domain
• Statistical characteristics such as search volume used, kriging variance, and number of
samples used in an estimate, were also computed and stored in each individual block for
descriptive evaluations
SRK has validated the block model using a combination of visual checks, statistical comparison of
composite grades to all three estimation methods and via swath plot analysis. SRK considered the
estimates to be representative of the underlying data.
Block model quantities and grade estimates for the Marmato Project were classified according to the
CIM Definition Standards for Mineral Resources and Reserves (CIM, 2014). SRK developed a
classification strategy which considers the confidence in the geological continuity of the mineralized
structures, the quality and quantity of exploration data supporting the estimates and the geostatistical
confidence in the tonnage and grade estimates. Data quality, drillhole spacing and the interpreted
continuity of grades controlled by the veins have allowed SRK to classify portions of the veins in the
Measured, Indicated and Inferred Mineral Resource categories.
Measured: Measured Resources are limited to vein material within the current levels being mined by
CGM and estimated within the first search volume, which required a minimum of five composites and
a maximum of 20 composites. These areas are considered to have strong geological knowledge as
they have been traced both down-dip and along strike via mapping, plus underground channel
samplings provided sufficient data populations to define internal grade variability.
Indicated: SRK has delineated Indicated Mineral Resources using two methods split by the material
types:
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 7
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
• Veins/Disseminated/Splays: Primarily between Level 16 to 21 currently in operation. Indicated
Mineral Resources have been given at the following approximate data spacing, as a function
of the confidence in the grade estimates and modelled variogram ranges. SRK has expanded
the limits of the Indicated resources to also cover areas within the licensed portion of Echandia
where:
o Spacing of 50 m by 50 m (XY) existed from the nearest drillhole
o Multiple holes were enabled to be used during the estimation process
o Support from both diamond drilling and channel sampling was present
• MDZ: Based primarily on 2018/2019 drilling with the following conditions:
o 50 by 50 m (XY) drillhole spacing (defined by a distance buffer of 25 m from drilling of
underground [UG] levels)
o Enabled multiple holes to be used during the estimation process
o Search volume less than 2 (i.e. volumes 1 and 2)
o Additional caution has been paid when classifying the dip extensions on the series of holes
drilled to the northeast as limited information is known up and down dip from the current
drilling
Inferred: In general, Inferred Mineral Resources have been limited to within areas of reasonable grade
estimate quality and sufficient geological confidence, and are extended no further than 150 m from
peripheral drilling on the basis of modelled variogram ranges.
SRK has defined the proportions of Mineral Resource to have potential for economic extraction for the
Mineral Resource based on different CoGs relating to the mineralization style (i.e. vein versus
porphyry) and potential differences in selective underground mining methods.
During the site inspection, SRK noted and discussed with the mine geologists that some mining has
been attempted within the porphyry “pockets”. SRK considers this to have uncertainty as no detailed
survey of mining volumes in the porphyry pockets is available. Based on the level of uncertainty, SRK
has downgraded areas identified as having potential historical mining to Inferred.
To assign the final classification, the mathematical criteria as defined has then been applied to the
block model, which is subsequently digitized on 50 m sections (across strike), with the final wireframe
based on interpretation of polylines in Leapfrog™ to smooth changes in interpretation between
sections.
To determine the potential for economic extraction, SRK used the following key assumptions for the
costing but notes that the deposit has variable mining costs depending on the mining types resulting
in a range of CoGs. A metallurgical recovery of 95% Au has been assumed for the MDZ and 90% for
the veins and porphyry material based on the current performance of the operating plant. Mining and
processing costs have been defined from aspects of the current study and historical production. The
initial cut-off is based on the mining of the veins using the current mining processes and assumed
costs, with a second method (longhole) defined for mining the MDZ and potentially areas of wider
porphyry mineralization in the upper levels.
SRK has reported the tonnage and grades associated with the current mine and the MDZ project,
which are the assets owned indirectly by CGM. As such, the Mineral Resource includes all material
within the #014-89m license and a sub-portion of the #RPP_357 (Echandia) below an elevation of
1,300 m, which can be accessed from the existing operation through an agreement with Gran
Colombia. SRK has also included the proportion of Mineral Resources currently under application
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 8
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
(Application #KIU-11401) within the Mineral Resources, but these have been excluded from the
Mineral Reserves as the timing on granting this license remained uncertain at the date of this report
(however, this license was recently confirmed as approved by the government; so will therefore be
included in future technical studies).
The proposed mining plan is predicated on splitting the above Mineral Resources into three styles of
mineralization within three distinct areas. These areas are referred to as the UZ (existing mine levels
16 through 21), the Transitional Zone (which includes mining of MDZ material to an elevation of 950
m) and the MDZ project (which includes all material below the 950 m elevation).
The three styles of mineralization are based on the key geological types defined in the Mineral
Resources of veins, porphyry, and MDZ. Therefore, the estimation domains for the Mineral Resource
Statement have been grouped into veins, porphyry and MDZ mineralization. The veins account for the
veins, halos and splay material and have used a 1.9 g/t Au cut-off. The porphyry material also uses a
cut-off of 1.9 g/t Au. As the potential mining method will require further investigation, the MDZ material
has used a lower cut-off of 1.3 g/t Au to account for the larger bulk mining methods involved.
SRK highlights that all Mineral Resources within #CHG_081 (yellow and orange) and the upper areas
of #RPP_357 (above 1,300 m) as highlighted in Figure 1-1 in light blue have not been reported and
are excluded from the current Mineral Resource statement herein for CGM because any Mineral
Resources that may occur in these areas have not been transferred from Gran Colombia to CGM.
Table 1-1 shows the Mineral Resource Statement for the Project, with an effective date of March 17,
2020.
Source: SRK, 2020
Figure 1-1: Cross-Section Showing License Splits at Marmato
Licence #014-89m
Licence #CHG-081 (above 1300)
RPP #357 -(above 1300)
RPP #357 -(below 1300)
Licence #CHG-081 (below 1300)
Area under applicationNo # KIU-11401Note: Included in Mineral Resources but excluded from Mineral Reserves
Upper Mine(above 950)
MDZ Projectbelow 950)
Transition Zone MDZ(above 950)
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 9
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 1-1: Caldas Mineral Resource(1) Statement with an Effective Date of March 17, 2020
Caldas Marmato Project - Effective Date March 17, 2020, Basis for MRE and PFS (CGM including RPP_357 less than 1,300 m)(1)
Category Quantity (Mt) Grade (g/t) Metal (kozs)
Au Ag Au Ag
Upper Mine (2)
Measured 2.1 5.65 27.0 387 1,853
Veins (5) 2.1 5.6 27.0 387 1,853
Porphyry (5) 0.0 0.0 0.0 0 0
Indicated 9.2 4.45 18.7 1,320 5,545
Veins 7.2 5.0 21.1 1,156 4,862
Porphyry 2.1 2.5 10.3 165 682
Measured and Indicated 11.4 4.67 20.2 1,707 7,397
Veins 9.3 5.2 22.4 1,543 6,715
Porphyry 2.1 2.5 10.3 165 682
Inferred 4.5 3.70 15.5 532 2,224
Veins 2.7 4.4 17.9 386 1,574
Porphyry 1.7 2.6 11.7 145 650
Transition Zone (3) (6)
Measured 0.0 0.0 0.0 0 0
Indicated 3.4 2.68 7.2 294 785
Measured and Indicated 3.4 2.68 7.2 294 785
Inferred 0.0 1.95 3.7 2 3
MDZ (4) (6)
Measured 0.0 0.0 0.0 0 0
Indicated 24.7 2.63 3.6 2,085 2,870
Measured and Indicated 24.7 2.63 3.6 2,085 2,870
Inferred 21.9 2.32 2.1 1,639 1,506
Combined
Measured 2.1 5.6 27.0 387 1,853
Indicated 37.3 3.1 7.7 3,699 9,200
Measured and Indicated 39.4 3.2 8.7 4,086 11,053
Inferred 26.4 2.6 4.4 2,172 3,733 (1) Mineral Resources are reported inclusive of the Mineral Reserve. Mineral resources are not mineral reserves and do not have demonstrated economic viability. All figures are rounded to reflect the relative accuracy of the estimate. All composites have been capped where appropriate. The Mineral Resources were estimated by Benjamin Parsons, MSc, MAusIMM #222568 of SRK, a Qualified Person pursuant to NI 43-101. (2) Upper Mine is defined as the current operating mines from levels 16 through 21 using existing mining methodology (cut and fill). (3) “Transition Zone” is defined as mining of MDZ above an elevation of 950 m (accessed from the current operations) using a modified longhole stoping method. (4) MDZ is defined as mining of MDZ below an elevation of 950 m using longhole open stope mining methods. (5) Porphyry and vein mineral resources are reported at a CoG of 1.9 g/t. CoGs are based on a price of US$1,500/oz Au and gold recoveries of 90% for underground resources without considering revenues from other metals. (6) MDZ mineral resources are reported at a CoG of 1.3 g/t. CoGs are based on a price of US$1,500/oz Au and gold recoveries of 95% for underground resources without considering revenues from other metals. Source: SRK, 2020
The 2020 Mineral Resource represents a number of changes in the defined Mineral Resource
compared to the 2019 PEA Mineral Resources, due to the following key factors:
• Infill drilling within the MDZ areas has increased the confidence in the estimates significantly
from the Inferred to Indicated category.
• Minor reduction in the vein domains as a result of additional depletion accounted for between
the PEA and PFS models, plus changes in the geological interpretation of veins and
disseminated material.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 10
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
SRK highlights that the current MDZ Mineralization represents a notable change in the style of
mineralization and considerations for mining methods at the Project and has maintained the use of a
high-grade core to the mineralization at depth.
The main changes in the Mineral Resource Statement since the previous estimate can be defined on
the combined Mineral Resource as follows:
• Increase in the Indicated MDZ material from 6.4 million tonnes (Mt) at 2.6 g/t Au, for 537
thousand ounces (koz), to 28.1 Mt at 2.6 g/t Au, for 2,379 koz, which is an increase of
1,842 koz within the MDZ. This is reflected in a reduction in the Inferred from 41.2 Mt at 2.1 g/t
for 2,812 koz to 22 Mt at 2.3 g/t for 1,640 koz, which is a reduction of 1,172 koz.
• Increase in the proportion of Measured and Indicated material within the vein domain from
9.2 Mt at an average grade of 4.6 g/t to 9.3 Mt at an average grade of 5.2 g/t Au, which is an
increase of 180 Koz or 13.2%.
• Reduction in the proportion of Inferred material within the veins from 3.3 Mt at 4.4 g/t Au for
466 koz, to 2.7 Mt at 4.4 g/t Au for 386 koz, which represents a difference of 80 koz.
• Minor increase in proportion for Indicated of porphyry (pockets) material of 25 koz.
• Increase in the Inferred portion of the porphyry material from 0.3 Mt at 3.1 g/t Au for 34 koz,
to 1.7 Mt at 2.6 g/t Au for 145 koz.
1.6 Mineral Reserve Estimate
The mine is currently developed to the 1,000 m elevation. A transition is occurring from narrow vein
mineralization to large porphyry mineralized areas (gold associated with pyrrhotite veinlets).
Mineralization is generally vertical with vein widths ranging from more than 1 m to several m. Porphyry
mineralized areas also have a vertical mineralization trend and can be up to approximately 100 m in
width. For this PFS, there are three different mining methods, separated into three distinct zones.
• The first zone is the mineralized vein material between 950 m elevation and 1,300 m elevation,
referred to as the Veins. This is the existing mine where conventional cut and fill stope methods
will continue to be used.
• The second zone is the wider porphyry material between 950 m elevation and 1,050 m
elevation, referred to as the Transition Area. A modified longhole stoping method will be used
in this area.
• The third zone is the porphyry material below 950 m elevation, referred to as MDZ. There is a
10m sill pillar left in-situ between the MDZ and the bottom of the Transition Area. The MDZ
material will be mined using a longhole stoping method. The MDZ area is currently not
developed.
The first two zones (Veins and Transition) are considered the Upper Mine, and the material is
processed in the existing processing facility. Material mined from the third zone (MDZ) will be sent to
a new processing facility to be constructed.
Mineral Reserves were classified using the 2014 CIM Definition Standards. Indicated Mineral
Resources were converted to Probable Mineral Reserves by applying the appropriate modifying
factors, as described herein, to potential mining shapes created during the mine design process. In
the same manner, Measured Mineral Resources were converted to Proven Mineral Reserves.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 11
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
A 3D design has been created representing the planned reserve mining areas. Dilution and recovery
have been included in the estimate, specific to each mining method. The underground mine design
process resulted in 19.7 Mt at an average grade of 3.19 g/t Au and 6.87 g/t Ag. Table 1-2 presents the
Mineral Reserve statement as of March 17, 2020.
Table 1-2: Caldas Mineral Reserve Estimate as of March 17, 2020 – SRK Consulting (U.S.), Inc.
Underground Mineral Reserves Cut-Off (1): 1.61 to 2.23 g/t
Area Category Tonnes
(kt) Au
(g/t) Ag
(g/t) Contained Au
(koz) Contained Ag
(koz)
Veins(2)
Proven 762 5.01 21.80 123 534
Probable 3,049 4.20 16.85 412 1,652
Veins Total 3,812 4.37 17.84 535 2,186
Transition(3)
Proven 40 7.63 28.16 10 36
Probable 1,293 3.43 7.92 143 329
Transition Total
1,333 3.56 8.52 152 365
MDZ(4)
Proven - - - - -
Probable 14,556 2.85 3.84 1,333 1,799
MDZ Total 14,556 2.85 3.84 1,333 1,799
Caldas Total
Proven 802 5.14 22.12 133 570
Probable 18,898 3.11 6.22 1,888 3,780
Total 19,700 3.19 6.87 2,021 4,350
Source: SRK, 2020 Notes: All figures are rounded to reflect the relative accuracy of the estimates. Totals may not sum due to rounding. Mineral Reserves have been stated on the basis of a mine design, mine plan, and economic model. Mineral Resources are reported inclusive of the Mineral Reserve. (1): Veins reserves are reported using a CoG of 2.23 g/t Au. The Veins CoG calculation assumes a US$1,400/oz Au price, 85% Au metallurgical recovery, US$49.45/t mining cost, US$13.63/t G&A cost, US$12.24/t processing cost, and US$8.96/t royalties. Transition reserves are reported using a CoG of 1.91 g/t Au. The Transition CoG calculation assumes a US$1,400/oz Au price, 95% Au metallurgical recovery, US$46/t mining cost, US$13.63/t G&A cost, US$12.24/t processing cost, and US$8.96/t royalties. MDZ reserves are reported using a CoG of 1.61 g/t Au. The MDZ CoG calculation assumes a US$1,400/oz Au price, 95% metallurgical recovery, US$42/t mining cost, US$14/t processing cost, US$6.75/t production taxes, US$3/t G&A cost, and US$3/t tailings cost. Note that costs/prices used here may be somewhat different than those in the final economic model. This is due to the need to make assumptions early on for mine planning prior to finalizing other items and using long-term forecasts for the life-of-mine plan. (2): The Veins area is currently mined using cut-and-fill methods. Mining dilution ranging from 20% - 55%, averaging 26%, is included in the reserves using a zero grade for dilution. A mining recovery of 90% is applied to stopes. The Veins Mineral Reserves were estimated by Fernando Rodrigues, BS Mining, MBA, MMSAQP #01405, MAusIMM #304726 of SRK, a Qualified Person. (3): The Transition area will be mined using a modified longhole stoping method. A mining dilution of 7% is included in the reserves using a zero grade for dilution. A mining recovery of 90% is applied to stopes. The Transition Mineral Reserves were estimated by Fernando Rodrigues, BS Mining, MBA, MMSAQP #01405, MAusIMM #304726 of SRK, a Qualified Person. (4): The MDZ portion of the Project will be mined by longhole open stoping mining methods. Mining dilution (internal and external) is included in the reserve. Stope dilution is 8%, and a portion of the stope dilution is applied using grade values based on average surrounding block information. A mining recovery of 92.5% is applied to stopes. The MDZ Mineral Reserves were estimated by Joanna Poeck, BEng Mining, SME-RM, MMSAQP #01387QP, a Qualified Person.
1.7 Mining Methods
Marmato has been in operation in various forms since the mid-1500s. Mineros Nacionales (MN) was
awarded the contract for the concessions in 1989. The Project was originally developed as a 300 t/d
underground mine in 1997 and has expanded through the years to the existing 1,200 t/d operation.
Table 1-3 shows the production from 2015 to May 2020.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 12
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 1-3: 2015 to 2020* Production
o Year o Unit 2015 2016 2017 2018 2019 2020*
o Ore Processed o t 303,279 341,309 365,119 338,902 370,245 119,069
o Au Grade o g/t 2.79 2.56 2.48 2.67 2.49 2.47
o Au Recovered o oz 23,954 23,449 25,163 24,909 25,750 8,318
*January through May of 2020 Source: CGM, 2020
Historically, shrinkage stoping was used to mine the Veins material as well as a caving method where
poor ground conditions were encountered. Currently, a conventional cut and fill (CaF) mining method
is used. Blasted material is either transferred down to Level 18 via ore passes or is transferred up via
the incline shaft (apiques) hoist, loaded into rail carts and hauled to the mill.
In the Transition area, a modified longhole stoping method will be used. The stope size is 15 m wide
by 15 m high with varying length of up to 26 m. These stopes are mined in a primary-secondary
sequence with paste backfill for the primary stopes and unconsolidated waste rockfill for the secondary
stopes. Where waste rock is unavailable, hydraulic sand fill will be used to fill the secondary stope.
Blasted material in the Transition area is also transported up to Level 18 via apiques and hauled to the
mill via rail carts.
The MDZ material is mined using a longhole stoping method with stope sizes that are 10 m wide by
30 m high, with varying lengths of up to 30 m. The MDZ area is currently not developed. The main
access will be a decline, hosting a conveyor from the plant area to the underground crusher area. A
dedicated ventilation drift will serve as secondary egress from the mine. Ventilation infrastructure
development underground was designed to support the mining method and was sized based on mining
equipment and production rate requirements. Trucks will dump into a surge bin at an elevation of 790
m. Material will go through the surge bin into the crusher and then be conveyed out of the mine.
Geotechnical
SRK and the Marmato exploration team collaborated on a geotechnical investigation program for the
MDZ from June 26, 2018 to March 4, 2020. The program was designed to characterize subsurface
geotechnical conditions to assist in the development of a PFS mine design. Based on the observed
ground conditions, SRK considers that the geotechnical investigation fulfills the industry standards to
support stope design and ground support requirements at a PFS project level. For a PFS project level,
SRK considers the proposed PFS mine design acceptable. The proposed stope designs, sill pillar
design, back filling specifications and ground support specification must be considered as PFS level
only and should not be implemented before an FS level investigation is conducted. Full geotechnical
investigation is described in the Marmato Geotechnical PFS Study (SRK, 2020).
Hydrogeology
The mine area is located in the hydrogeological regional area of Magdalena Cauca, specifically in the
Cauca River catchment (Caldas Department). The region is comprised of igneous and metamorphic
rocks with limited groundwater storage capacity and hydraulic conductivity (IDEAM, 2013). The
porphyry units represent the main hydrogeological units in the mine area, with a low hydraulic
conductivity and limited groundwater storage capacity. Groundwater flow is compartmentalized within
structural blocks with limited hydraulic communication across fault boundaries due to fault gouge,
weathering, or an offset of geological units (Knight Piésold, 2012).
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 13
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Previous field campaigns were performed by Knight Piesold (KP) in 2011 and 2012 (Knight Piésold,
2012) and currently by SRK starting in early 2020, primarily consisted of packer isolated interval
testing, monitoring well and Vibrating Wire Piezometer (VWP) installations in underground coreholes
or locations distal to the mine area.
The zone of enhanced hydraulic conductivity values at depths of 600 to 800 m below the ground
surface corresponds to fractured zones associated with Fault 2 and Fault 1-3 in the mine area.
Measured water levels show elevations from 661 to 2,022 m Magna Sirgas/Colombia West coordinate
system (EPSG 3115) (MSCW), following the topography at 100 m depth in most of the locations
outside the mine area. A depressurization zone was detected in the underground piezometers where
the water levels have a horizontal trend. The shape or extent of the depressurization zone is currently
unknown. On a regional scale, the groundwater flows west to east, following the topographical gradient
to the Cauca River, located at 692 m elevation, which represents the main discharge for the
hydrogeological system.
KP developed 172 packer tests, three underground piezometers and 11 piezometers at the surface
(Knight Piésold, 2012). In the 2020 field campaign, 70 packer tests and two multi-level VWP
installations were performed. As a result, the geometrical mean of hydraulic conductivity values ranges
from 1.1 by 10-3 meters per day (m/d) to 4 by 10-2 m/d in the porphyry units depending on the depth
intervals. The shallow zone (less than 200 m depth) corresponds to saprolite and more permeable
bedrock and the deep zone (more than 850 m depth) has less permeable conditions. However, it is
apparent that high-permeability zones (hydraulic conductivity greater than 0.1 m/d, which may be
associated with Fault 2 and Fault 1-3, were encountered in the vicinity of the planned mine at depths
of 600 to 800 m below ground surface (bgs), or at an elevation of 700-900 m MSCW.
Mine Dewatering
The measured monthly average total dewatering rate in the Marmato mine is 37 liters per second (L/s),
varying from 26.8 L/s to 46.4 L/s. Strong seasonal trends were not observed, however a decrease of
approximately 20 L/s can be observed in the last 12 months. A major structure zone with significant
water flow (7 to 8 L/s) was detected at levels 17 and 21 to the north of the Criminal Fault.
The dewatering rate is a combination of groundwater inflows and water content in the backfill material
(50% of water). According to Marmato operational personnel, the contribution of the backfill material
is 7 to 14 L/s, depending on the number of hydraulic backfill equipment units in operation. Therefore,
the average fresh groundwater inflow into the mine could vary from 23 to 30 L/s.
SRK developed a preliminary 3D numerical groundwater flow model using MODFLOW-USG code,
based on available climatic, geological and hydrogeological data. The majority of the predicted inflow
to the MDZ planned mine (up to 78 L/s with a possible range from 56 to 159 L/s) is expected from the
upper levels above 730 m where elevated hydraulic conductivity values of the bedrock groundwater
system were measured. Mine inflow to the lower planned mine below 730 m is predicted to be lower
(15 L/s with an upper limit of 34 L/s) due to reduced measured hydraulic conductivity with depth.
Total maximum discharge into the entire mine complex, including flow to existing mine levels, is
predicted to be up to 111 L/s with a possible range from 89 to 168 L/s.
The mine is 2.5 km to the west of the Cauca River with a proposed bottom of 212 m below the river
stage (or 480 m MSCW). There is a risk of surface-water inflow through the riverbed sediments and
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 14
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
fractured bedrock when hydraulic gradient will be reversed by mine dewatering. Structural features
similar to those detected to the north of the Criminal Fault could connect mine developments with the
river. In SRK’s opinion, this represents a medium risk for the Project. Further hydrogeological
investigations of this area are required to evaluate potential significant increments in groundwater
inflow.
Production Schedule
The production and development schedules were completed using iGantt software from Minemax. The
production schedule is based on the rate assumptions either from current mining practices or
developed from first principles.
The UZ production schedule targets a total ore production of 1,500 t/d or 525,000 tonnes per year (t/y)
(based on 350 days per year) to the mill. A gradual ramp up of 1,100 t/d (385,000 t/y) in 2020, 1,250 t/d
(437,500 t/y) in 2021, 1,400 t/d (490,000 t/y) in 2022 and 1,500 t/d in 2023. The Transition Zone
accounts for 400 t/d while the rest comes from the Veins. Life of Mine (LoM) for the Veins is 12 years
for a total production of 3.81 Mt at 4.37 g/t Au. LoM for the Transition Zone is 11 years for a total
production of 1.33 Mt at 3.56 g/t Au.
Combined UZ production is 5.14 Mt at 4.16 g/t Au. Figure 1-2 shows the UZ production schedule
colored by time period. Note that there is also a 2 Mt/y permit limit of moved material, which limits the
production of the UZ.
Source: SRK, 2020
Figure 1-2: UZ Production Schedule Colored by Time Period
The MDZ mining schedule is based on 365 days/year seven days/week, with three 8 hour shifts each
day. Actual operational mining days are 360. For simplicity the schedule has been completed
assuming 365 with pro-rated productivity rates. A production rate of 4,000 t/d (1.46 Mt/yr) was targeted
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 15
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
with ramp-up to full production as quickly as possible. The schedule timeframe is quarterly for four
years and annually for the remainder of the mine life.
Decline activities begin in October 2021 with initial mine development through Q4 2023. Stoping begins
in Q4 of 2024, with a one year ramp up period until the mine and plant are operating at full capacity.
Figure 1-3 shows the mine production schedule colored by year.
Source: SRK, 2020
Figure 1-3: MDZ Mine Production Schedule Colored by Year
Figure 1-4 summarizes the combined UZ and MDZ schedules. This combined schedule is used in the
economic model results shown in section 22.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 16
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SRK, 2020
Figure 1-4: Combined UZ and MDZ Mining Profile – Tonnes and Grade
Mining of the Veins in the UZ is with handheld pneumatic equipment (jacklegs and stopers) for
development and production. Blasted material is mucked using slushers, microscoops and skid steer
loaders into rail carts and hauled out to the mill.
The Transition Zone utilizes jumbo drills for lateral development. The same jumbo drills are used for
ore mining with a longhole drill attachment. Blasted material is loaded by 4 t load haul dumps (LHD)
to 10 t trucks (or to the orepass) and is then transferred to rail carts and transported out of the mine
via the apiques.
The UZ mine (Veins and Transition) is a producing mine and all infrastructure is already established.
The MDZ mine will utilize jumbo drills for lateral development and down-the-hole drills for vertical
development and production stoping. Mechanical bolters will be used for ground support. The mine
will operate a fleet of 45 t haul trucks being loaded by 17 t LHDs. The ore will be fed through a grizzly
with rock breaker into an underground crusher and conveyor system to the surface. The mine will have
full infrastructure underground, including; ventilation, cemented paste backfill booster pump and
distribution system, dewatering pumping system, electrical substation and distribution system, fuel
storage, warehousing, explosives storage, communications system, and maintenance shops. The
MDZ mine will have a staff of approximately 429 people at the peak of production. Owner mining has
been assumed for steady state with contractor mining development early in the mine life.
1.8 Recovery Methods
CGM operates a 1,200 t/d process plant to recover gold and silver values from material produced from
current Marmato mining operations in the UZ and plans to expand this facility to 1,500 t/d capacity in
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 17
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
2021. In addition, CGM is evaluating the development of the MDZ, which is below the current mining
operations and the construction of a new 4,000 t/d plant to process material solely from the MDZ.
Marmato Process Plant
The Marmato process plant flowsheet incorporates unit operations that are standard to the industry
and includes:
• Three-stage crushing
• Closed circuit ball mill grinding
• Gravity concentration
• Flotation
• Flotation and gravity concentrate regrind
• Cyanidation of the flotation and gravity concentrates
• Counter-current-decantation
• Merrill-Crowe zinc precipitation
• Smelting of precipitates to produce final doré product
During the period from 2013 to 2020 (Jan to May) ore processed through the Marmato plant has
increased from 274,191 to 370,245 tonnes per year (t/y) while grades have declined slightly from 2.90
g/t Au in 2013 to 2.49 g/t Au in 2019 and silver grades have ranged from 12.36 to 9.13 g/t Ag. Overall
gold recovery has ranged from 83.7 to 88.9% and has averaged about 87.1% during the period 2019
to 2020 (Jan to May). Silver recovery has ranged from 33 to 41.1% and has averaged 33.2% during
the period 2019 to 2020 (Jan to May). Annual gold production has increased from 22,566 ounces in
2013 to 25,750 ounces in 2019.
MDZ Process Plant
The MDZ process plant was designed by Ausenco and is based on the 2020 metallurgical program
conducted by SGS Lakefield, Ausenco’s industry experience and input from equipment suppliers. The
process plant is designed to process ore at a rate of 1,460,000 dry t/y (4,000 dry t/d) based on a 92%
plant availability and includes unit operations that are well proven and standard to the industry,
including:
• Crushing/Grinding
• Gravity concentration
• Cyanide leaching of the gravity tailings
• Carbon-in-pulp (CIP) gold adsorption
• Desorption/Electrowinning/Refining
• Cyanide detoxification
• Tailings thickening and filtration
The MDZ process plant will be located North-East of the town of Marmato, Colombia. Access to the
plant will be via the plant roads off National Route 25. The primary crusher will be located underground,
and the secondary crusher positioned at the surface near the entrance to the mine portal. The crushed
ore stockpile will be east of the main process plant. The main plant will be outdoors and will include
the grinding, gravity recovery, leach/CIP tanks, reagent, elution/carbon regeneration, cyanide
detoxification and tailings thickening circuits. The electrowinning and refining area will be located in a
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 18
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
separate building. Plant tailings will be thickened and pumped either to the mine backfill plant or to the
tailing filter plant, located next to the main plant. Filtered tailings will be hauled and stored in a DSTF.
1.9 Project Infrastructure
The existing Marmato Project has a mature and functioning infrastructure system including all the
necessary facilities and supporting utilities to produce at the planned production levels. The current
facilities include a security checkpoint that provides access to the office and administrative office area.
The facilities also include employee motorcycle parking, meeting area, cafeteria, multiple shops and
warehouses, a camp with cafeteria, exercise and sports field, equipment storage yards, compressor
station, welding shop, a 500 kilowatt (kW) backup generator, processing plant, underground mine,
explosives storage a short distance from the mine that is managed by the military, main power
substation and distribution powerlines with motor control centers at key loads. The site has three
portals that access the mine workings. Water Supply for the existing Marmato Project is provided by
mine dewatering and water reclaimed from the DSTF, Additional water supply from the Cauca River
to supplement the existing plant water availability during the dry season is planned to be in-place
before the MDZ project startup.
The MDZ project infrastructure will be developed on a separate greenfield site approximately 3
kilometers (km) north-east of the existing site by road. The new site will require new access roads off
the existing El Llano access to a new processing facility, camp area, and mine portal with access to
the MDZ.
The new infrastructure will include an additional transmission line from the 115 KV Salamina substation
to the new MDZ substation with local MDZ distribution to the mine substation and processing facility.
Surface facilities will include the mine portal, truck shop, processing facility, fuel storage and fuel
distribution system, paste backfill plant, shotcrete plant, processing plant facilities, a tailings filter plant,
a new water supply plant near the Cauca River, a new camp, offices, and a small temporary run of
mine (RoM) stockpile. Explosives storage is planned to be offsite.
The site will have a crushing area with a surge stockpile feeding the main processing plant. Support
facilities will include warehouses, shops, offices, a camp, administrative office, change house and
laydown yards. The camp and administrative facilities will be located at a separate location
approximately 300 m to the south from the processing plant. Parking will be provided near the entrance
to the MDZ site and at the camp location with a security gate for restricted access that will be
constructed at the entrance to the facility.
Water supply for the MDZ project will be supplied by mine dewatering, recycled water from the tailings
filter press and runoff and seepage collected from the DSTF, as well as from supplemental water
drawn from the Cauca River as needed.
The area already supports a significant mining population and skilled labor will be available from the
region.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 19
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
1.9.1 Tailing Management Facilities
SRK completed a study of potential options for DSTF siting in the vicinity of the existing Cascabel
tailings storage facility and the proposed portal and plant location. Factors considered in the siting
study included topography, permitting requirements for stream crossings, property ownership and
acquisition potential, and municipality boundaries. Also, as part of the study, SRK developed
conceptual designs for seven potential DSTF locations. From that analysis, only three locations, sites
1, 2 and 6, were identified within the area of study as potentially feasible for:
• Providing the capacity required through mine life
• Achieving global stability in the steep terrain in the site vicinity
Due to property access difficulties and travel restrictions because of the COVID-19 pandemic, SRK
and CGM were unable to complete a geotechnical investigation at any of the sites. All conclusions and
costs presented in this study related to DSTF design and operation are therefore based on necessary
assumptions that will require investigation and confirmation in the next phase of study. Where input
assumptions were required, SRK has attempted to use conservative inputs to arrive at a reasonable
but conservative estimate of costs, risks and potential opportunities associated with DSTF siting,
construction and operation.
Based on the results of an SRK trade-off study (ToS) evaluating major cost items for Sites 1, 2 and 6,
CGM indicated a preference to evaluate the feasibility of developing DSTF 2 and then DSTF 1 to
achieve the desired tailings storage capacity through the currently predicted mine life. The combination
of DSTF 2 and DSTF 1 provides sufficient capacity based on current projections. DSTF 6 provides
sufficient capacity on its own for the currently predicted mine life, although the distance to the plant
provides some additional planning and access complexities.
Operation of the current Cascabel 1 and 2 DSTFs is required to provide enough capacity and time to
begin phased construction of DSTF 2 to provide for uninterrupted tailings storage. A review of available
design and stability analyses of the Cascabel 1 and 2 configurations indicates they have not been
designed or evaluated in accordance with internationally accepted standards of practice. Engineering
consultants from Dynami recently completed a stability review of both the existing and expanded
Cascabel 1 and 2 designs and concluded there is not enough information currently available to
establish the current or future stability of the facility. Dynami recommended extensive characterization.
To achieve the timeline currently presented in the PFS, CGM has committed to immediate
implementation of Dynami’s recommendations and subsequent design and mitigation aimed at
ensuring the facility’s compliance with internationally accepted standards of practice. SRK
recommends that CGM identify other options for filtered tailings storage that may provide additional
interim storage capacity in the event Cascabel 1 and 2 cannot be shown to be stable to internationally
accepted standards.
1.10 Environmental Studies and Permitting
1.10.1 Environmental Studies and Management
The existing Marmato Project predates the regulatory requirements to prepare an environmental
impact assessment (EIA) as part of the permitting process. Instead, the operations were authorized
through the approval of an Environmental Management Plan (Planes de Manejo Ambiental or PMA).
The original PMA for Marmato was approved by the regional environmental authority (Corporación
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 20
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Autónoma Regional del Caldas or Corpocaldas) on October 29, 2001 under Resolution 0496, File No.
616. The site-specific PMA covers environmental studies and required management procedures and
practices. In addition, baseline data collection programs were initiated in 2019 to gather relevant and
appropriate site information with respect to both the existing Marmato Project and the proposed MDZ
expansion. The data was compiled and reported in Capítulo 20: Caracterización Ambiental y Social
del Proyecto, Caldas Gold Marmato S.A.S., Título Minero #014 – 89m (May 2020). The assessment
of potential impacts associated with the MDZ expansion project can only begin in earnest once the
PFS mine plan has been finalized, at which point, CGM will initiate engagement with Corpocaldas
(anticipated in Q1 2021).
SRK directed a sampling and analytical program to generate environmental geochemistry data for
tailings and waste rock for the existing operations and MDZ expansion project. Data from SRK’s
metallurgical program indicates that tailings will be discharged with a neutral to alkaline supernatant.
However, the tailings solids will be potentially acid generating (PAG) with the potential to eventually
exceed the alkaline supernatant and produce acidic drainage in the longer term. Detoxified cyanide
tailings are anticipated to have elevated concentrations of arsenic, sulfate, and total dissolved solids
in potential leachates. Testing on paste backfill tailings suggest that the material will be acid-
neutralizing in the short term, but in the long term, the material could become acidic. A waste rock
geochemical characterization program is in progress. An analytical program completed in 2012, in
support of the defunct open pit mine design, indicated that a significant fraction of waste rock could be
potentially acid generating. Effective management of both tailings and waste rock will be a critical issue
for success of the project.
Water balance modeling indicates the project is net positive and will continue to discharge excess
mine dewatering flows during some periods of the project. Infrequent discharges from facility surface
water management controls are also predicted. Based on water quality predictions and existing
infrastructure at the mine, additional water treatment facilities are not included in this study. However,
water treatment may be required dependent upon the outcome of ongoing geochemical studies.
SRK is not aware of any known environmental issues that could materially impact CGM’s ability to
extract the mineral resources or mineral reserves at the Marmato project. While there will be some
challenges associated with land acquisition and surface water control during operations, the Marmato
project has not had, nor does it currently have, any legal restrictions which affect access, title, mining
rights, or capacity to perform work on the property. Likewise, in regard to environmental compliance,
the operation is covered by the PMA and associated environmental permits, which further reduces
environmental risks.
1.10.2 Permitting
The Marmato Project is authorized under a number of resolutions issued by Corpocaldas in the name
of CGM’s predecessor, Mineros Nacionales S.A.S. These include, among others:
• Environmental Management Plan or PMA (Resolution No. 496)
• Various water concessions
• Discharge permits (Resolutions 270 modified by 254)
• Emissions permit (Resolution 270)
CGM is currently in the process of modifying the PMA to include a second DSTF area (Cascabel 2).
To this end, CGM has presented the impact assessment and technical documentation for this
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 21
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
modification to Corpocaldas for review. Corpocaldas has evaluated the request and is waiting for the
Ministry of the Interior to certify the presence, or not, of ethnic communities in the area of the new
facility in order to determine the need for prior consultations, before issuing its final decision. Once
Corpocaldas authorizes the Cascabel II modification, a new modification request will be submitted for
the phased construction of a DSTF2 to accommodate the UZ tailings during the development of the
full MDZ project and tailings capacity.
The PMA will require a major modification to allow for the proposed MDZ expansion project, which
envisions an increase in production in a second processing plant to be constructed. During
construction, Channel Occupancy Permits will need to be obtained for the new tailings site, the process
plant site, and the site of the underground portal (bocamina). Likewise, a Forest Exploitation Permit
will be needed for areas of proposed surface disturbance with trees.
The final environmental impact assessment deliverable includes the application for all the
environmental permits that will be required for the construction and operation phases of the project.
Once the EIA is officially delivered to Corpocaldas, the review process can begin based on the agreed-
upon terms of reference. CGM estimates that a minimum of six months will be required to review the
complete application and issuance of the Environmental License by Corpocaldas for the MDZ
expansion of the Marmato project. However, this process has been delayed as a result of the COVID-
19 pandemic and CGM does not anticipate fully reengaging Corpocaldas with the submittal of the EIA
in Q1 of 2021. The current timeline envisioned for the permitting of the project should be considered
to be aggressive and that permitting timeline expectations should be reviewed as the process begins.
In accordance with the terms and conditions of the PMA, CGM maintains an Environmental Insurance
Policy for the current operation. That policy is renewed annually with Corpocaldas as the beneficiary.
This policy is intended to cover the entire Marmato operations and all aspects of environmental
compliance. According to CGM, the current amount covered by the policy is COL$302,835,000
(USD$91,768). This amount will be reviewed and adjusted during the modification process of the PMA
for the MDZ expansion project.
1.10.3 Social or Community Related Requirements
The 2001 PMA for Marmato specifically requires the management of the social component of the
Project. Caldas is required to maintain records on all community activities (including number of
participants, topics, duration, etc.), which is to be turned over to Corpocaldas every six months as part
of the ongoing monitoring programs. As part of the social management and monitoring program, CGM
has developed a social investment model which seeks to promote the development of communities in
the area of influence, with the purpose of contributing to the consolidation of society and fostering
economic development (Economic Development), guaranteeing the care and respect for the
environment (Environmental Development) and supporting and participating in actions aimed at
improving the quality of life and well-being of its inhabitants (Social Development and Promotion of
Solidarity Actions).
1.10.4 Community Relations
Between 2014 and 2018, CGM developed and implemented a social engagement program at Marmato
specifically designed to focus on the well-being of the community and care for the environment. These
initiatives are incorporated in the Community Relations Plan (Plan de Relaciones con la Comunidad).
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 22
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
The Marmato Project currently operates with 152 administrative employees, 1,090 operating workers,
and 54 apprentice workers, most of whom are from the municipalities surrounding the project. With
the MDZ expansion, CGM anticipates hiring approximately 900 temporary workers during construction
and around 550 permanent employees as part of the new operations.
1.10.5 Mine Closure, Remediation, and Reclamation
Article 209 of Law 685 of 2001 requires that the concession holder, upon termination of the agreement,
shall undertake the necessary environmental measures for the proper reclamation and closure of the
mining operation. To ensure that these activities are carried out, the Environmental Insurance Policy
shall remain in effect for three years from the date of termination of the contract. While a formal closure
plan is not legally required at this stage of the operation, currently there is a closure plan for Marmato,
Plan de Cierre y Abandono de Mina La Maruja – Gran Colombia Gold Marmato S.A.S. (May 2019)
which discusses basic reclamation and closure actions including aspects of temporary, progressive,
and final closure. Reclamation and closure costs for the current operation provided in the closure plan
are based on percentages of costs to build the facilities. SRK did not independently calculate or
validate this estimate however, it is within keeping of other moderate-sized underground mining
operations in South America. The reclamation and closure cost for the existing mine plan is estimated
to be COL$20,128,000,000 (US$6.1 million based on exchange rate of 3,300 to 1). A requirement for
long-term post-closure water treatment, if deemed necessary, could increase this estimate.
Using first principles and the Nevada-developed Standardized Reclamation Cost Estimator, local
equipment and labor rates, and based on limited PFS engineering design information and drawings
for the MDZ expansion project, an additional cost of US$3.1 million was included in the technical
economic model to account for the increase in production anticipated for the new operations and the
construction of a new plant and tailings storage facilities. These are actual reclamation activity cost
estimates rather than percentages of construction costs. SRK strongly recommends that a more
detailed and thorough calculation of closure costs be prepared for the next level of study, looking at
both the existing facilities and planned expansion. Again, long-term post closure water treatment
requirements, if necessary, could significantly increase this estimate. This too should be more closely
examined during the next study phase.
1.11 Capital and Operating Costs
1.11.1 Marmato UZ Capital Costs
The Marmato UZ is a currently operating underground mine. The estimate of capital expenditures
(capex) includes expansion capex to increase the mineral processing capacity and sustaining capex
to maintain the equipment and all supporting infrastructure necessary to continue operations until the
end of the projected production schedule. The estimate conforms to Class 4 guidelines for a PFS level
estimate with a ±25% accuracy according to the Association for the Advancement of Cost Engineering
International (AACE International). The capital cost estimate is presented in Q2 2020 US Dollars
(US$). The estimate includes processing, maintenance, general and administration (G&A) and
accommodations costs.
The sustaining capital cost estimates developed for the UZ includes the costs associated with the
engineering, procurement, construction and commissioning. The cost estimate is based on budgetary
estimates prepared by Marmato and reviewed by SRK. The estimate indicates that the Project requires
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 23
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
sustaining capital of US$54.8 million to support the projected production schedule throughout the LoM.
Table 1-4 summarizes the LoM sustaining capital estimate, Table 1-5 and Table 1-6 present the same
estimate by year.
Table 1-4: Marmato UZ Sustaining Capital (LoM)
Description LoM (US$)
Upper Zone Infill Drilling 11,847,000
Upper Zone Development 6,396,225
Upper Zone Mine Sustaining 10,049,860
Upper Zone Plant Expansion 11,626,000
Upper Zone Plant Expansion Contingency 2,906,500
Upper Zone Plant Sustaining 3,600,000
Upper Zone Dewatering 2,275,706
Closure Costs 6,100,000
Total $54,801,292
Source: CGM/SRK, 2020
Table 1-5: Marmato UZ Sustaining Capital (2020 to 2026) (US$)
Description 2020 2021 2022 2023 2024 2025 2026
Infill Drilling 2,200,000 2,200,000 2,200,000 2,200,000 2,200,000 121,000 121,000
Development 1,187,325 2,998,025 1,986,625 224,250 - - -
Mine Sustaining 2,127,399 1,777,862 1,852,400 3,858,800 - 154,000 279,400
Plant Expansion 5,035,000 3,511,000 1,210,000 440,000 1,430,000 - -
Plant Expansion Contingency
1,258,750 877,750 302,500 110,000 357,500 - -
Plant Sustaining 300,000 300,000 300,000 300,000 300,000 300,000 300,000
Dewatering 135,000 713,569 1,427,137 - - - -
Closure Costs - - - - - - -
Total $12,243,474 $12,378,206 $9,278,662 $7,133,050 $4,287,500 $575,000 $700,400
Source: CGM/SRK, 2020
Table 1-6: Marmato UZ Sustaining Capital (2027 to 2034) (US$)
Description 2027 2028 2029 2030 2031 2032
Infill Drilling 121,000 121,000 121,000 121,000 121,000 -
Development - - - - - -
Mine Sustaining - - - - - -
Plant Expansion - - - - - -
Plant Expansion Contingency - - - - - -
Plant Sustaining 300,000 300,000 300,000 300,000 300,000 -
Dewatering - - - - - -
Closure Costs - - - - - 6,100,000
Total $421,000 $421,000 $421,000 $421,000 $421,000 $6,100,000
Source: CGM/SRK, 2020
1.11.2 MDZ Capital Costs
The MDZ is a lower part of the deposit that is undeveloped. Before CGM can exploit this part of the
deposit it will have to expand the existing operation. The expansion is planned to be executed between
the years of 2021 and 2023.
The capital cost estimates prepared for the expansion into the MDZ area also include estimates for
Engineering, Procurement and Construction Management (EPCM) and the Owner’s cost to manage
it. The cost estimate is based on cost models prepared by SRK and Ausenco with site specific inputs
from CGM. The estimate indicates that the expansion will require an investment of US$269.4 million,
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 24
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
this includes an estimated capital of US$237.2 million plus 13.6% contingency of US$32.2 million.
Table 1-7 summarizes the expansion capital estimate.
Table 1-7: MDZ Construction Capital (US$)
Description LoM 2020 2021 2022 2023
Development 19,719,753 - 2,279,534 10,343,401 7,096,818
Mining Equipment Purchases 52,430,929 - 16,868,012 15,295,229 20,267,688
Mining Services 11,589,225 - 1,288,744 6,206,511 4,093,970
Infrastructure 33,201,830 - 16,600,915 16,600,915 -
Process Plant 42,371,769 - 21,185,884 21,185,884 -
DSTF 19,660,473 - 17,212,986 1,279,528 1,167,958
Temporary Power Line 272,727 - 272,727 - -
Mining EPCM 9,276,559 - 2,883,922 4,999,126 1,393,512
Mining Owner's 15,721,708 - 3,978,018 7,881,638 3,862,053
Infrastructure + Plant EPCM 10,484,229 - 5,242,114 5,242,114 -
Infrastructure + Plant Owner's 13,602,581 1,087,625 4,663,472 5,298,567 2,552,917
Infrastructure + Plant Other Indirect 8,860,555 - 4,430,278 4,430,278 -
Sub-Total 237,192,337 1,087,625 96,906,605 98,763,190 40,434,916
Mining Contingency 15,091,967 - 2,508,648 5,950,365 6,632,954
Plant + Infrastructure Contingency 14,237,757 - 7,118,879 7,118,879 -
DSTF Contingency 2,871,944 - 2,581,948 191,929 98,067
Total Contingencies (13.6%) 32,201,668 - 12,209,474 13,261,173 6,731,021
Total $269,394,005 $1,087,625 $109,116,079 $112,024,363 $47,165,937
Source: CGM/Ausenco/SRK, 2020
The MDZ will require sustaining capital to maintain the equipment and all supporting infrastructure
necessary to continue operations until the end of its projected production schedule. The sustaining
capital cost estimate developed for this mining area includes the costs associated with the engineering,
procurement, construction and commissioning. The cost estimate is based on PFS designs and cost
models prepared by SRK with site specific inputs from CGM. The estimates indicate that the Project
requires sustaining capital of US$131.3 million to support the projected production schedule through
the LoM. Table 1-8 summarizes the LoM sustaining capital estimate and Table 1-9 and Table 1-10
present the same estimate by year.
Table 1-8: MDZ Sustaining Capital (LoM)
Description LoM (US$)
Drilling -
Development 34,285,846
Mine Equipment Purchases 17,166,844
Mine Equipment Rebuilds 26,862,004
Mining Owner's Cost 5,892,624
Mining Contingency 14,671,389
DSTF Sustaining 23,806,666
115kV Power Line 5,614,521
Closure Costs 3,000,000
Total $131,299,895
Source: CGM/SRK, 2019
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 25
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 1-9: MDZ Sustaining Capital (2023 to 2027) (US$)
Description 2023 2024 2025 2026 2027
Drilling - - - - -
Development 2,735,635 4,986,400 3,834,632 2,168,451 3,433,459
Mine Equipment Purchases 6,646,459 3,972,308 - - 1,186,305
Mine Equipment Rebuilds - 1,162,732 2,300,471 4,985,557 4,601,468
Mining Services - - - - -
Mining Owner's Cost 1,689,596 943,372 402,871 227,366 487,479
Mining Contingency 1,322,664 1,704,601 1,307,595 1,476,275 1,799,109
DSTF Sustaining 6,817,007 21,934 64,320 15,054 13,150,673
115kV Power Line 280,726 561,452 561,452 561,452 561,452
Closure Costs - - - - -
Total $19,492,087 $13,352,799 $8,471,341 $9,434,155 $25,219,945
Source: CGM/SRK, 2020
The sustaining capital cost estimate to support the 115kV power line was in fact estimated as a total
cost of US$3.24 million. This cost estimate was converted to a loan payment program that considers
a 10 year payment schedule and an 11.5% yearly interest rate. Each individual payment is calculated
to be approximately US$561,452.
Table 1-10: MDZ Sustaining Capital (2028 to 2033)
Description 2028 2029 2030 2031 2032 2033
Drilling - - - - - -
Development 6,412,653 3,918,836 3,897,980 2,467,849 429,949 -
Mine Equipment Purchases 208,000 4,232,979 920,793 - - -
Mine Equipment Rebuilds 681,459 4,291,695 2,278,851 6,399,725 160,047 -
Mining Services - - - - - -
Mining Owner's Cost 454,151 875,725 507,741 258,506 45,817 -
Mining Contingency 1,540,853 2,184,960 1,382,954 1,825,216 127,163 -
DSTF Sustaining 166,510 2,714,184 502,892 166,510 187,582 -
115kV Power Line 561,452 561,452 561,452 561,452 561,452 280,726
Closure Costs - - - - - 3,000,000
Total $10,025,079 $18,779,831 $10,052,664 $11,679,257 $1,512,011 $3,280,726
Source: CGM/SRK, 2020
1.11.3 Marmato Operating Costs
SRK, Ausenco and CGM prepared the estimate of operating costs for the PFS production schedule.
Marmato UZ LoM cost estimate is presented in Table 1-11 and MDZ LoM cost estimate is presented
in Table 1-12.
Table 1-11: UZ Operating Costs Summary
Description LoM (US$/t-Ore) LoM (US$000’s)
Mining 48.45 249,251
Process 12.07 62,082
G&A 13.82 71,086
Total Operating $74.33 $382,419
Source: CGM/SRK/Ausenco, 2020
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 26
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 1-12: MDZ Operating Costs Summary
Description LoM (US$/t-Ore) LoM (US$000’s)
Mining 35.19 512,288
Process 13.68 199,113
G&A 8.23 119,771
Total Operating $57.10 $831,173
Source: CGM/SRK/Ausenco, 2020
1.12 Economic Analysis
The valuation results of the Marmato Project indicate that is has an after-tax IRR of 19.5% and an
after-tax Net Present Value (NPV) of approximately US$256.1 million, based on a 5% discount rate
and gold and silver prices of US$1,400/oz and US$17.00/oz respectively. The cash flow profile also
shows a shorter payback for the investment when comparing to a stand-alone MDZ operation, to the
combine operations present a payback within the year of 2026, while a stand-alone MDZ operations
would present a payback in the year of 2027. The operation is projected to have negative cash flows
between the years 2020 and 2023, when the MDZ is installed, with payback for the expansion expected
by 2026. The annual free cash flow profile of the Project is presented in Figure 1-5.
Source: SRK, 2020
Figure 1-5: Marmato After-Tax Free Cash Flow, Capital and Metal Production
Indicative economic results are presented in Table 1-13. The Project can be considered a gold
operation with a sub-product of silver, where gold represents 99% of the total projected revenue and
silver the remaining 1%. The underground mining cost is the heaviest burden on the operation
representing 62% of the operating cost, as presented in Figure 1-6.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 27
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SRK, 2020
Figure 1-6: Marmato Operating Cost Break-Down
Table 1-13: Marmato Indicative Economic Results
LoM Cash Flow (Unfinanced)
Total Revenue USD 2,625,861,238
Mining Cost USD (761,539,531)
Processing Cost USD (270,396,073)
G&A Cost USD (190,857,579)
Total Opex USD (1,222,793,183)
Operating Margin USD 1,403,068,055
Operating Margin Ratio % 53%
Taxes Paid USD (210,374,619)
Free Cashflow (before initial capital) USD 760,268,116
Before Tax
Free Cash Flow USD 701,248,730
NPV @ 5% USD 396,654,830
NPV @ 8% USD 279,571,263
NPV @ 10% USD 219,652,793
IRR % 26%
After Tax
Free Cash Flow USD 490,874,111
NPV @ 5% USD 256,075,253
NPV @ 8% USD 167,009,205
NPV @ 10% USD 121,855,455
IRR % 19.5%
Payback Year 2026
Source: SRK, 2020
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 28
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
The estimated All-in Sustaining Costs (AISC), including sustaining capital, is US$880/Au-oz.
Table 1-14 presents the breakdown of the Marmato AISC.
Table 1-14: LOM All-in Sustaining Cost Breakdown
LOM All-in Sustaining Cost Breakdown
Mining US$/Au-oz 408
Processing US$/Au-oz 145
G&A US$/Au-oz 102
Refining US$/Au-oz 6
Royalty US$/Au-oz 130
Sustaining Capital US$/Au-oz 102
Silver Credit US$/Au-oz (14)
AISC US$/Au-oz 880
SRK’s standard Cash Cost reporting methodology for NI 43-101 reports includes smelting/refining costs; whereas CGM’s basis of reporting treats these costs as a reduction of realized gold price (the refinery discounts the selling price by a factor to cover these charges) and excludes them from its reported “total cash cost per ounce”. Source: SRK, 2020
1.13 Conclusions and Recommendations
1.13.1 Property Description and Ownership
SRK noted within the transfer of licenses from the previous owner there is a gap between the existing
licenses for #014-84M and RPP-357. This ground was under application from CGM with the Colombian
government for formal approval to continue mining. SRK reviewed the application within the
government website and noted that the status is defined as “in progress”, which has been the status
since September 30, 2009. The Company has taken steps to get the approval finalized. It is SRK’s
understanding that at the time of writing CGM has received notification (May 2020) to continue mining
in this area and that under the new Colombia mining license coding, the government does not consider
the gap to be present. SRK has not completed sufficient work to confirm this but would highlight that
it should be resolved and enable additional material to be used in mine plans for future studies.
In 2017 CGM began the process and submitted to the government the application for the license
extension to the current operation and future exploration for license #014-89, with the original license
currently held to October 2021. The process is expected to be completed in Q4 2020.
1.13.2 Geology and Mineralization
SRK produced an updated 3D geological model for the Marmato deposit as part of the current study.
SRK considers this to have increased the confidence in the spatial location of the various geological
units. CGM geologists as part of the on-going exploration continue to develop the geological
knowledge on the project and have supplied additional fault information which should be integrated
into further lithological models. SRK does not consider these faults to have a material impact on the
current mineral resource estimate but notes that it may impact future underground infrastructure (such
as a decline).
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 29
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
1.13.3 Status of Exploration, Development and Operations
The databases comprise a combination of historical and recent diamond core and underground
channel samples. In total, there are some 1,317 diamond drillholes for a combined length of
266,390 m; plus 24,824 individual underground channel samples, inclusive of current mine sampling
contained in the databases
SRK is of the opinion that the exploration and assay data is sufficiently reliable to support evaluation
and classification of Mineral Resources in accordance with generally accepted CIM Estimation of
Mineral Resource and Mineral Reserve Best Practices Guidelines (2014).
SRK notes that CGM exploration continues at the project throughout 2020 and SRK has reviewed the
2020/2021 drilling plan. The drilling is targeting mineralization in the hanging wall of the current
estimate which is referred to by CGM as the New Zone, which may impact on current mining
infrastructure if further mineralization is located, which may require modifications to the current mine
design. SRK therefore recommends that the geological model and mineral resource should be updated
to reflect the new drilling upon completion as the impact of these in future models may impact the
design prior to construction
1.13.4 Mineral Processing and Metallurgical Testing
Native gold is the predominant gold carrier and over 99% of the gold particles occurred within mineral
structures that would be readily accessible by leaching solutions.
The PFS metallurgical program optimized process parameters required to recover gold and silver
values from MDZ ore using a process flowsheet that includes gravity concentration followed by
cyanidation of the gravity tailing.
Comminution tests demonstrated that the MDZ ore is classified as hard with regard to impact breakage
and grinding characteristics.
Overall gold recovery is estimated at 95% and overall silver recovery is estimated at 51%. There is
little difference in reported gold recoveries for the master and variability composites and gold recovery
appears to be independent of ore grade over the range tested.
Cyanide destruction tests demonstrated that weak acid dissociable cyanide (CNWAD) could be reduced
to less than 10 mg/L with the SO2/air process. However, CNWAD levels will further attenuate to less
than 1 mg/L with time.
Pressure filtration will be required to dewater thickened tailings in order to achieve less than 15%
moisture content required for disposal in a DSTF.
1.13.5 Mineral Resource Estimate
The resource evaluation work was completed by Mr. Benjamin Parsons, MAusIMM (CP#222568). The
effective date of the Mineral Resource Statement is March 17, 2020, which is the last date assays and
the surveyed depletion outlines were provided to SRK.
SRK has produced block models using Datamine™. The procedure involved import from
Leapfrog™Geo of wireframe models for the fault networks, veins, definition of resource domains (high-
grade sub-domains), data conditioning (compositing and capping) for statistical analysis, geostatistical
analysis, variography, block modelling and grade interpolation followed by validation. Grade estimation
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 30
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
for the veins has been based on block dimensions of 5 m by 10 m by 10 m for the Porphyry and MDZ
units. Sub-blocking to 0.5 m by 1 m by 1 m has been allowed to reflect the narrow nature of the
geological model. The block size reflects the relatively close-spaced underground channel sampling
and spacing within veins compared to the wider drilling spacing, with the narrower block size used in
the MDZ at depth to reflect the proposed geometry of the mineralization (steeply dipping).
SRK is of the opinion that the MRE has been conducted in a manner consistent with industry best
practices and that the data and information supporting the stated mineral resources is sufficient for
declaration of Measured, Indicated and Inferred classifications of resources. SRK considers the veins
(including splays) and the MDZ to be of sufficient confidence for use in a mining study but recommends
further work on the short scale variability within the porphyry be completed to confirm the current
interpretation within areas of the existing mining infrastructure prior to use in any mining studies.
1.13.6 Mining and Reserves
UZ Mine Design
CaF is the current mining method used for the Veins and is appropriate for the deposit geometry. A
modified longhole stoping method will be used for the Transition zone to take advantage of the bulk
characteristics of the deposit.
Stope optimizations were run using a minimum CoG of 2.23 g/t Au for the Veins and 1.91 g/t Au for
the Transition zone.
Access to the Veins is already established. Primary haulage is on level 18 and material from levels
above is transferred down via existing ore passes. Material below level 18 is transported up via an
incline or via the apiques. The main production apique is at level 22, a secondary production apique
is at level 20 and will extend down to level 22.
The Transition zone is accessed via level 21 and level 22. A ramp will also connect the two levels as
a secondary egress and ventilation exhaust.
Tonnage and grades presented in the reserve include dilution and recovery. Productivities are based
on the current mine productivities
A quarterly/yearly production schedule was generated using iGantt software. The schedule targeted
1,500 t/d with a gradual ramp up to meet the upgraded mill capacity. There is also a 2 Mt/y permit limit
of moved material, which limits the production of the UZ.
MDZ Mine Design
Longhole stoping is an appropriate mining method for the deposit geometry. Stopes are sized to be
large enough to take advantage of bulk mining methods, yet small enough to maintain stability and
minimize dilution.
Optimizations were run using various CoG to identify higher grade mining areas and understand the
sensitivity of the deposit to CoG. Results show large quantities of lower grade material where a small
increase/decrease in CoG has a material impact on the quantity of economic material available for
design. A minimum CoG of 1.61 g/t Au was used for design/reserve. Higher grade stopes based on
3.5 g/t stope optimization results were designed as a first pass, with the lower grade stopes added as
separate stopes. This allowed for scheduling of higher grade stopes first.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 31
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
The MDZ is accessed through a decline drift with conveyor. Tonnage and grades presented in the
reserve include dilution and recovery and are benchmarked to other similar operations. Productivities
were generated from first principles with inputs from mining contractors, blasting suppliers, and
equipment vendors where appropriate. The productivities were also benchmarked to similar
operations. Equipment used in this study is standard equipment used world-wide with only standard
package/automation features.
A quarterly/yearly production schedule was generated using iGantt software. The schedule targeted
4,000 t/d.
Geotechnical
The geotechnical investigation, laboratory tests and design are suitable for a PFS project level design.
The proposed design parameters are acceptable for a PFS study only.
Empirical charts suggest that the side walls are located in unsupported transition zones, which could
require some spot ground support for potential wedge formations depending on discontinuity
persistence/continuity.
SRK used the Bieniawski, 1993, empirical chart to estimate the open stope stand-up time. A 10 m
span stope can likely be open for one to six months without ground support.
Dilution was estimated using the empirical Clark and Pakalnis (1997) method. The thickness of
external dilution is estimated as Equivalent Linear Overbreak/Slough (ELOS). The ELOS charts
indicate that significant dilution is unlikely due to the good rock mass quality (RMQ). Wall damage
would likely be associated with blasting overbreak. SRK considerers it relevant to conduct a blasting
study during the FS to evaluate the degree of overbreak.
To estimate the backfill strength requirements, SRK applied the Mitchell et al, 1982 analytic solution
which suggests that a backfill uniaxial compressive strength (UCS) of 1 megapascals (MPa) will be
adequate to maintain backfill stability and prevent backfill from sloughing into the open stope.
Negligible wall sloughing is anticipated.
Hydrogeology
The 3D groundwater flow model for the Marmato project was developed, reasonably calibrated to
available measured water level and groundwater flow data, and used to make predictive simulations
of:
• Passive inflow to the existing and planned deep underground mines
• Propagation of drawdown during proposed dewatering during mining
• Changes in groundwater discharge to rivers and creeks during mining
The model predicts that:
• The majority of inflow to the planned mine (up to 78 L/s with a possible range from 56 to
159 L/s) is expected from the upper levels above 730 m, where elevated hydraulic conductivity
values of bedrock groundwater system were measured.
• Mine inflow to the MDZ planned mine below 730 m is predicted to be lower (15 L/s with upper
limit of 34 L/s) due to reduced measured hydraulic conductivity with depth.
• The total maximum planned mine discharge is predicted to be up to 88 L/s, with a possible
range from 61 to 167 L/s.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 32
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
• Total maximum discharge into the entire mine complex, including flow to existing mine levels,
is predicted to be up to 111 L/s, with a possible range from 89 to 168 L/s.
• Major sources of mine inflow are depletion of groundwater storage and capturing of
groundwater discharge to surface water bodies (i.e., streams). The model does not predict
reversing of hydraulic gradient between the mine area and the Cauca River and does not
predict inflow to the mine from the river. However, further investigation of the structures and
their hydrogeological role are needed to verify this conclusion.
• Lowering of the water table in the mine area of up to 140 m and drawdown propagation of up
to 2 km away from the mine, assuming a 10-m drawdown extent
In SRK’s opinion, the completed predictions are conservative, given the following:
• The model is based on extrapolation of the measured hydraulic conductivity values in mine
area for entire model domain, including topographic highs areas outside of the mine area,
where measured water levels are high and hydraulic conductivity values are most likely lower
than in the mine area.
• The model uses high recharge from precipitation to calibrate the model to measured water
levels, combined with geomean hydraulic conductivity values in discrete depth intervals that
are derived from measured hydraulic conductivity values in the mine area.
• The model uses calibrated conductance values that reproduce measured inflow to the existing,
relatively shallow mine for simulation of groundwater inflow to the deep underground
developments of the planned mine.
• The model simulates no restriction of groundwater inflow to the backfilled stopes for Base
Case and Maximum Inflow scenarios.
The completed analysis of available hydrogeological data and numerical groundwater modeling
indicate that several uncertainties remain in understanding of the hydrogeology, including
hydrogeological role of the faults, hydraulic properties of bedrock outside of the mine area, recharge
estimates, spatial and vertical distribution of groundwater inflow to the current mine, water table
elevation, and water level changes due to passive mine dewatering and seasonal changes in
precipitation.
To reduce these uncertainties, SRK recommends completing the following additional hydrogeological
investigations/analyses for the FS:
• Structural analysis of the geological features and faults outside of the mining area, with
emphasis on potential connection to the Cauca River
• Detailed water balance and estimate of recharge from precipitation
• Detailed groundwater inflow mapping in existing developments
• Evaluation of the role of backfilling in reduction of groundwater inflow to the mine
• Improvement of mine discharge measurements at each level of the existing mine
• Re-survey existing monitoring locations, with emphasis on ground and collar elevations
• Installation of groundwater level monitoring network outside of mine area and along the river
valley, including hydrogeological testing during construction of monitoring wells
• Detailed water level measurements to observe:
o Drawdown propagation as result of mine dewatering
o Seasonal variation as result of precipitation
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 33
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
• Additional large-scale hydraulic testing to identify zone of enhanced permeability related to
Fault 2 (in areas where planned conveyor decline and egress ramp plan to intersect this fault
at multiple locations/elevations) and Fault 1-3 (intersects planned stopes in multiple
elevations). In addition, test the S. Ines Fault (intersects the planned stopes in the upper levels
and part of the egress ramp)
• Drilling and hydraulic testing of pilot holes in places where ventilation declines are planned
• Updates to the developed numerical groundwater model based on above items to improve its
predictability:
o Better calibration of the model to water levels for future pore pressure predictions
o Re-evaluation of pumping design based on updated inflow predictions
o Evaluation of flow-through hydrogeological conditions during post-mining
• Groundwater chemistry sampling
1.13.7 Recovery Methods
An ore processing plant has been designed to process MDZ ore at the rate of 4,000 t/d using
conventional processes that are standard to the industry including: primary and secondary crushing,
SAG/ball mill grinding, gravity concentration, agitated cyanide leaching, carbon-in-pulp (CIP), gold
elution, electrowinning and smelting to produce a final doré product.
1.13.8 Project Infrastructure
The existing infrastructure for the UZ operations is established and meets the project requirements.
The addition of the water supply pumping system from the Cauca River will address potential water
sourcing issues during drought seasons.
The new MDZ infrastructure includes the required access, power supply, water supply, tailings storage,
and support facilities to support the production of 4,000 t/d from the new plant and mine.
A full understanding of the mine water and DSTF water requirements and runoff will allow for
optimization of the site runoff pond and water treatment capacities.
Tailings Management Facility
SRK advanced the conceptual designs of DSTF 2 and DSTF 1 to a level sufficient for cost estimating.
The designs include consideration of the following specific elements:
• Subgrade preparation include topsoil salvaging, removal of unsuitable material and excavation
of stability benches and embankment keys
• Construction of rockfill starter embankments using a combination of imported and on-site
borrow
• Construction of underdrain network and underdrain flow management
• Construction of seepage collection drains on dry stack benches and seepage management
systems
• Construction of stormwater diversion and control channels
• Management of contact stormwater on dry stack top deck and return to process
• Access and haul roads between plant and DSTF 2 and DSTF 1
• Temporary storage area for filtered tailings
• Temporary holding pond for non-filtered tailings
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 34
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
• Topsoil and unsuitable soil stockpile area with underdrainage system
Currently identified risks and opportunities with respect to the costs developed for the PFS have been
identified in relation to the following:
• The inability to characterize the foundation conditions beneath the conceptual DSTF
footprints.
• Ongoing geochemical characterization of both waste rock and ore/tailings indicating some of
the waste rock and tailings may be acid generating and therefore require special management
considerations.
• Immediate characterization and analysis of Cascabels 1 and 2 to demonstrate compliance
with internationally accepted standards of practice and provide for tailings management
through commissioning of a new DSTF.
• More extensive testing of tailings to confirm tailings geotechnical characteristics and cement
addition requirements.
• Stormwater maintenance requirements at both DSTF 1 and DSTF 2 constitute higher costs
through operations and closure than is currently allowed for in the PFS costs.
1.13.9 Environmental Studies and Permitting
The following interpretations and conclusions have been drawn with respect to the currently available
information provided for the Marmato Project:
• Environmental Studies: Baseline studies have been completed or are currently underway
with respect to the existing facilities (additional tailings storage capacity request) and MDZ
proposed expansion. These resource studies will be used for impact analysis and the
development of mitigation actions and environmental management planning.
• Environmental and Social Management: Environmental and social issues are currently
managed in accordance with the approved PMA and will likely need to be updated and/or
modified for the proposed MDZ expansion project.
• Monitoring: Routine monitoring is currently conducted on seven domestic wastewater
discharges and three non-domestic (industrial) wastewater discharges. Air quality emissions
from the metallurgical laboratory and smelter are also monitored for: particulate matter (PM),
sulphur dioxide (SO2) nitrogen oxides (NOX) and lead (Pb). The tailings are infrequently
monitored for hazard classification purposes through a Corrosive, Reactive, Explosive, Toxic,
Inflammable, Pathogen [biological] (CRETIP) program. The results of the monitoring are
provided to Corpocaldas. This monitoring program will require significant modification to
include the facilities for the proposed MDZ expansion project, and to bring it up to international
best practice standards.
• Geochemistry: Acid-generating sulfide minerals identified in the deposit include pyrite,
arsenopyrite, iron-bearing sphalerite, pyrrhotite, and chalcopyrite (SRK, 2017). Samples of
groundwater discharging into the underground are predominantly acidic. The underground
water samples contain elevated metal(loid) concentrations. While the tailings will be
discharged with a neutral to alkaline supernatant, the tailings themselves will be potentially
acid generating (PAG) with the potential to eventually overwhelm the alkaline supernatant and
produce acid drainage in the long term. A waste rock analytical program completed in 2012 in
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 35
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
support of an open mine design indicated that a significant fraction of waste rock could be
potentially acid generating (KP, 2012).
• Permitting: Operations are permitted through the posting of an Environmental Management
Plan (PMA) and secondary permits for use of water abstraction, forest use, air emissions,
discharges and river course (channel) construction. The PMA for the current operations was
originally approved in 2001. Minor modification of the PMA (including and environmental
impact analysis) is currently underway as part of the request for additional tailings storage
areas. Major modification of the PMA will be required for the MDZ expansion project.
• Stakeholder Engagement: Company has conducted extensive stakeholder identification and
analysis programs and has set stakeholder engagement objectives and goals to develop
communications plans with government, community, media and small miners but the company
does not currently have a formal stakeholder engagement plan.
• Closure Costs: The reclamation and closure cost estimate provided for the current operations
is approximately US$6.1 million, though there is considerable uncertainty surrounding the
basis for this estimate. An additional US$3.1 million is estimated for the MDZ expansion
facilities (assuming concurrent taili8ngs reclamation), for a total of US$9.2 million. A
requirement for long-term post-closure water treatment, if any, could significantly increase this
estimate.
There do not appear to be any other known environmental issues that could materially impact CGM’s
ability to conduct mining and milling activities at the site. Preliminary mitigation strategies have been
developed to reduce environmental impacts to meet regulatory requirements and the conditions of the
PMA.
Recommendations
Environmental Studies and Permitting
The following recommendations are made with respect to environmental, permitting and social issues
regarding the Marmato Project:
Prepare a more detailed site-wide closure plan for the existing Marmato facilities, including building
plans and equipment inventories) from which a more accurate final closure cost estimate can be
developed.
Continue work on groundwater hydrogeology and surface water to better define the risk associated
with potential groundwater contamination and underground dewatering impacts. A detailed evaluation,
including a groundwater model, could provide information that would assist in forecasts of post-closure
mine water discharge and possible long-term water treatment requirements. Such an investigation
could also provide vital information on underground geotechnical stability, both during operations and
post closure.
Characterization work should be completed on artisanal tailings and waste rock to understand their
Acid Rock Drainage Medal Leaching (ARDML) potential and devise a long-term management plan.
A comprehensive baseline surface and groundwater sampling program will be important to establish
the baseline condition and try to quantify the contributions from artisanal or pre-mining conditions,
especially with respect to mercury from artisanal mining.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 36
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Substantial financial resources and technical specialist support will be required to implement the
environmental monitoring and mitigation measures likely to be presented in the updated PMA for the
expansion project.
1.13.10 Capital and Operating Costs
Marmato UZ is a currently operating underground mine, the estimate of capital includes some
expansion capex to increase the mineral processing capacity and sustaining capital to maintain the
equipment and all supporting infrastructure necessary to continue operations until the end of the
projected production schedule. The estimate prepared for this study indicates that the Project requires
a sustaining capital of US$54.8 million to support the projected production schedule throughout the
LoM.
The MDZ is a lower part of the deposit that is undeveloped. Before CGM can exploit this part of the
deposit it will have to expand the existing operation. The expansion is planned to be executed between
the years of 2021 and 2023. The cost estimate indicates that the expansion will require an investment
of US$269.4 million, this includes an estimated capital of US$237.2 million plus 13.6% contingency of
US$32.2 million.
Ausenco prepared a detailed cost estimate for the MDZ mineral processing facility and other mine
infrastructure but did not prepare an annual expenditure schedule for this capital.
SRK, Ausenco and CGM prepared the estimate of operating costs for the PFS’s production schedule.
The estimated operating cost for the Marmato UZ is US$76.12/t-ore and for the MDZ is US$57.10/t-
ore
The estimated AISC, including sustaining capital, is US$880/Au-oz. Table 1-15 presents the
breakdown of the Marmato AISC.
Table 1-15: LoM All-in Sustaining Cost Breakdown
LoM All-in Sustaining Cost Breakdown
Mining USD/Au-oz 408
Processing USD/Au-oz 145
G&A USD/Au-oz 102
Refining USD/Au-oz 6
Royalty USD/Au-oz 130
Sustaining Capital USD/Au-oz 102
Silver Credit USD/Au-oz (14)
AISC USD/Au-oz 880
SRK’s standard Cash Cost reporting methodology for NI 43-101 reports includes smelting/refining costs; whereas CGM’s basis of reporting treats these costs as a reduction of realized gold price (the refinery discounts the selling price by a factor to cover these charges) and excludes them from its reported “total cash cost per ounce”. Source: SRK, 2020
The following recommendations are made with respect to capital and operating costs of the Marmato
Project:
• Prepare first principles estimate of capital and operating costs with enough accuracy to
support future studies of the project, including:
o Prepare cash flow model based on shorter periods of production
o Prepare an expenditure curve for MDZ Mineral Processing and Site Infrastructure
construction costs
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 37
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
o Further detail the site-specific operating cost data and cost models to include fixed and
variable nature of costs and detail the cost models to include breakdown by area and
function
o Improve cost models to include currencies used to estimate each cost and prepare
sensitivity to currencies variability
1.13.11 Economic Analysis
The valuation results of the Marmato Project indicate that is has an after-tax IRR of 19.5% and an
after-tax NPV of approximately US$256.1 million, based on a 5% discount rate and gold and silver
prices of US$1,400/oz and US$17.00/oz respectively. The cash flow profile also shows a shorter
payback for the investment required for the MDZ, bringing it back about a year to 2026. The operation
is projected to have negative cash flows between the years 2020 and 2023, when the MDZ is installed,
with payback for the expansion expected by 2026. LoM is projected to end in 2033 resulting in a total
production of 1.87 Moz of gold and 1.57 Moz of silver in the form of doré bars containing both precious
metals. Indicative economic results are presented in Table 1-16.
Table 1-16: Marmato Indicative Economic Results
LoM Cash Flow (Unfinanced)
Total Revenue USD 2,625,861,238
Mining Cost USD (761,539,531)
Processing Cost USD (270,396,073)
G&A Cost USD (190,857,579)
Total Opex USD (1,222,793,183)
Operating Margin USD 1,403,068,055
Operating Margin Ratio % 53%
Taxes Paid USD (210,374,619)
Free Cashflow (before initial capital) USD 760,268,116
Before Tax
Free Cash Flow USD 701,248,730
NPV @ 5% USD 396,654,830
NPV @ 8% USD 279,571,263
NPV @ 10% USD 219,652,793
IRR % 26%
After Tax
Free Cash Flow USD 490,874,111
NPV @ 5% USD 256,075,253
NPV @ 8% USD 167,009,205
NPV @ 10% USD 121,855,455
IRR % 19.5%
Payback Year 2026
Source: SRK, 2020
The Project is a gold operation with a sub-product of silver, where gold represents 99% of the total
projected revenue and silver the remaining 1%. The underground mining cost is the heaviest burden
on the operation representing 62% of the operating cost, while processing costs represent 22% and
G&A costs the remaining 16%.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 38
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
The following recommendations are made with respect to the economic evaluation of the Marmato
Project:
• The schedule prepared for Marmato UZ doesn’t fully utilize its mineral processing capacity for
several years of the life of mine. Investigate the possibility to expand the total mine movement
permit to allow Marmato UZ to process its run of mine using its plant at full capacity, as this
will very likely improve the overall project economics.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 39
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
2 Introduction
2.1 Terms of Reference and Purpose of the Report
This report was prepared as a PFS Level Canadian National Instrument 43-101 (NI 43-101) Technical
Report (Technical Report) disclosing the findings for Caldas Gold Corp. (Caldas Gold), which indirectly
holds all of the shares of CGM, by SRK Consulting (U.S.), Inc. (SRK) on the Marmato Project, located
in Colombia. The Project consists of the current Marmato operating mine and the MDZ.
The quality of information, conclusions, and estimates contained herein is consistent with the level of
effort involved in SRK’s services, based on: i) information available at the time of preparation, ii) data
supplied by outside sources, and iii) the assumptions, conditions, and qualifications set forth in this
report. This report is intended for use by CGM subject to the terms and conditions of its contract with
SRK and relevant securities legislation. The contract permits CGM to file this report as a Technical
Report with Canadian securities regulatory authorities pursuant to NI 43-101, Standards of Disclosure
for Mineral Projects. Except for the purposes legislated under provincial securities law, any other uses
of this report by any third party is at that party’s sole risk. The responsibility for this disclosure remains
with CGM. The user of this document should ensure that this is the most recent Technical Report for
the property as it is not valid if a new Technical Report has been issued.
This report provides Mineral Resource and Mineral Reserve estimates, and a classification of
resources and reserves prepared in accordance with the Canadian Institute of Mining, Metallurgy and
Petroleum Standards on Mineral Resources and Reserves: Definitions and Guidelines, May 10, 2014
(CIM, 2014).
2.2 Qualifications of Consultants (SRK)
The Consultants preparing this technical report are specialists in the fields of geology, exploration,
Mineral Resource and Mineral Reserve estimation and classification, underground mining,
geotechnical, environmental, permitting, metallurgical testing, mineral processing, processing design,
capital and operating cost estimation, and mineral economics.
None of the Consultants or any associates employed in the preparation of this report has any beneficial
interest in CGM. The Consultants are not insiders, associates, or affiliates of CGM. The results of this
Technical Report are not dependent upon any prior agreements concerning the conclusions to be
reached, nor are there any undisclosed understandings concerning any future business dealings
between CGM and the Consultants. The Consultants are being paid a fee for their work in accordance
with normal professional consulting practice.
The following individuals, by virtue of their education, experience and professional association, are
considered Qualified Persons (QP) as defined in the NI 43-101 standard, for this report, and are
members in good standing of appropriate professional institutions. QP certificates of authors are
provided in Appendix A. All QP’s stated below are independent of the Company. The QP’s are
responsible for specific sections as follows:
• Ben Parsons, Principal Consultant (Resource Geologist) is the QP responsible for data
verification, preparation of the geological model and the mineral resource estimate. Sections
2 through 12 (except 4.4), 14, 23 and portions of Sections 1, 24, 25 and 26 summarized
therefrom, of this Technical Report.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 40
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
• Eric Olin, Principal Consultant (Metallurgy) is the QP responsible for Metallurgy Sections 13,
17.1 17.2 and the Upper Zone processing portion of Section 21 and portions of Sections 1,
24, 25 and 26 summarized therefrom, of this Technical Report.
• Robert Raponi, Principal Metallurgist at Ausenco Engineering Canada Inc., is the QP
responsible for the MDZ process plant and infrastructure engineering and related portions of
Sections 17.3, 18.3 through 18.12, and the MDZ processing and infrastructure portions of
21.1.2, 21.3.2 and portions of Sections 1, 24, 25 and 26 summarized therefrom, of this
Technical Report.
• Fernando Rodrigues, Principal Consultant (Mining Engineering) is the QP responsible for
Upper Zone Mining and Economics and related portions of Section 15.1.1 through 15.1.4, and
the portions of Sections 15.2 and 15.3 pertaining to the Upper Zone, and Sections 16.1, 16.4,
portions of 16.6 pertaining to the Upper Zone, 19 and 22, and portions of Sections 1, 24, 25
and 26 summarized therefrom, of this Technical Report.
• Jeff Osborn, Principal Consultant (Mining Engineering) is the QP responsible for Infrastructure
and Cost Estimation Sections 18.1, 18.2, 18.13,18.16, and 21 (excluding processing and
tailings portions of Section 21), and portions of Sections 1, 24, 25 and 26 summarized
therefrom, of this Technical Report.
• Joanna Poeck, Principal Consultant (Mining Engineering) is the QP responsible for the
opening statement in Section 15 and portions of Section 15.1.5 through 15.1.8, and the
portions of Sections 15.2 and 15.3 pertaining to the MDZ, and Section 16.5, portions of 16.6
pertaining to the MDZ and portions of Sections 1, 24, 25 and 26 summarized therefrom, of this
Technical Report.
• Fredy Henriquez, Principal Consultant (Geotechnical Engineering) is the QP responsible for
Geotechnical Section 16.2 and portions of Sections 1, 24, 25 and 26 summarized therefrom,
of this Technical Report.
• Breese Burnley, Principal Consultant (Geotechnical Engineering) is the QP responsible for
Tailings Section 18.15, and the tailings portions of Section 21, and portions of Sections 1, 24,
25 and 26 summarized therefrom, of this Technical Report.
• Cristian Pereira, Senior Consultant (Hydrogeology) is the QP responsible for Hydrogeology
Section 16.3, and portions of Sections 1, 24, 25 and 26 summarized therefrom, of this
Technical Report.
• David Hoekstra, Principal Consultant (Water Resource Engineering) is the QP responsible for
Section 18.14, Hydrology Section 20.2.5, and portions of Sections 1, 24, 25 and 26
summarized therefrom, of this Technical Report.
• David Bird, Associate Principal Consultant (Geochemistry) is the QP responsible for
Geochemistry Section 20.1.3, and portions of Sections 1, 24, 25 and 26 summarized
therefrom, of this Technical Report.
• Mark Willow, Principal Consultant (Environmental) is the QP responsible for Section 4.4,
Environmental Section 20 (except section 20.1.3), and portions of Sections 1, 24, 25 and 26
summarized therefrom, of this Technical Report.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 41
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
2.3 Details of Inspection
Table 2-1 presents a site visit summary. SRK was given full access to relevant data requested, and
conducted discussions with junior and senior CGM personnel regarding procedures and
interpretations.
Table 2-1: Site Visit Participants
Personnel Company Expertise Date(s) of Visit Details of Inspection
Ben Parsons SRK Mineral Resources
June 11 to June 13, 2019 August 17, 2017 and March 12 to March 14, 2012
Underground Site visit levels 18 – 21, review latest drilling intersections, Underground Site visit levels 17 – 20, review latest drilling intersections, Underground Site visit, review latest drilling intersections.
Eric Olin SRK Metallurgy December 17 and 18, 2019
Reviewed Marmato process operations and site locations for the MDZ process plant
Jeff Osborn SRK Mining/Infrastructure
July 16 to July 18, 2019 August 22 and 23, 2017
Surface Facilities and New MDZ location Underground and Surface Facilities including DSTF as well as core shack area
Fernando Rodrigues
SRK Mining/Reserves August 22 and 23, 2017
Underground and Surface Facilities including DSTF as well as core shack area
Fredy Henriquez SRK Geotechnical
January 8 and 11, 2020 July 16 to July 18, 2019
Underground Mine core shack area and the Tunnel proposed portal location
Mark Willow SRK Environmental December 1, 2016 Environmental Impact review
Cristian Pereira SRK Hydrogeology August 12 to August 13, 2019
Hydrogeology review
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 42
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Personnel Company Expertise Date(s) of Visit Details of Inspection
Giovanny Ortiz SRK Geology/Mineral Resources
September 30 to October 2, 2019 February 10 to February 21, 2020
Review Veins model with CGM team Review Underground Sampling Process and Mapping procedures
Breese Burnley SRK Tailings January 28, 2020
Existing tailings facilities, Site 6 and Site 2 proposed for MDZ.
Source: SRK, 2020
2.4 Sources of Information
SRK’s opinion contained herein is based on information provided to SRK by CGM throughout the
course of its investigations. SRK has relied upon the work of other consultants in the project areas in
support of this Technical Report.
The Consultants used their experience to determine if the information from previous reports was
suitable for inclusion in this technical report and adjusted information that required amending. This
report includes technical information, which required subsequent calculations to derive subtotals, totals
and weighted averages. Such calculations inherently involve a degree of rounding and consequently
introduce a margin of error. Where these occur, the Consultants do not consider them to be material.
This report is based in part on internal Company technical reports, previous technical studies, maps,
published government reports, Company letters and memoranda, and public information as cited
throughout this report and listed in the References Section 27.
SRK has been supplied with numerous technical reports and historical technical files. SRK’s report is
based upon:
• Numerous technical review meetings held at CGM’s offices in Medellín, Colombia
• Discussions with directors, employees and consultants of the Company
• Data collected by the Company from historical exploration on the Project
• Access to key personnel within the Company, for discussion and enquiry
• A review of data collection procedures and protocols, including the methodologies applied in
determining assays and measurements
• Gran Colombia Gold Marmato S.A.S. for the site-specific closure plan and cost estimate
presented in Plan de Cierre y Abandono de Mina La Maruja (May 2019)
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 43
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
• Site Environmental Manager, Ing. Adrián Quintero Jiménez, and corporate Environmental
Manager, Erwin Wolff Carreño, for information on permits, monitoring programs and data, and
the environmental management budget estimate
• Knight Piésold (2012) for information on the geochemistry of the deposit
• Marmato’s exploration team provided geotechnical core logging and laboratory tests results;
• Geology and major faults were provided by Marmato’s exploration team.
• Existing reports provided to SRK, as follows:
o NI 43-101 Mineral Resource Estimate on the Marmato Project, Colombia, June 21, 2012
o NI 43-101 Mineral Resource Estimate on the Marmato Project, Colombia, June 16, 2017
o NI 43-101 Technical Report Preliminary Economic Assessment Marmato Project
Colombia, February 6, 2020
o Geochronology, Geochemistry and Magmatic-Hydrothermal Oxide Characterization of the
Marmato Gold Deposit, Colombia,
o Lead isotopic compositions of the gold mineralization of Marmato, Colombia:
Characterization of the transition domain in epithermal - porphyry systems
o Further Geological Observations on The Lower Zone Gold Deposit at Marmato, Colombia,
Richard H Sillitoe, July 2019
o Marmato Structural Geology Review (Memorandum), SRK Consulting (Canada) Inc,
March 11, 2020
• Data files provided by the Company to SRK as follows:
o Topographic grid data in digital format
o Drillhole database, including collar, survey, geology, and assay
o QA/QC data including details on duplicates, blanks and certified reference material (CRM)
o DXF files, including geological interpretation, vein domain digitized 2D section
interpretations, stope outlines and mined depletions
2.5 Effective Date
The effective date of this report is March 17, 2020.
2.6 Units of Measure
The metric system has been used throughout this report. Tonnes are metric of 1,000 kg, or 2,204.6 lb.
All currency is in U.S. dollars (US$) unless otherwise stated.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 44
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
3 Reliance on Other Experts The Consultant’s opinion contained herein is based on information provided to the Consultants by
CGM throughout the course of the investigations.
SRK has not performed an independent verification of land title and tenure as summarized in Section 4
of this report. SRK did not verify the legality of any underlying agreement(s) that may exist concerning
the permits or other agreement(s) between third parties but have relied on the Company and its legal
advisor for land title issues. SRK has been supplied with a Legal Opinion by Dentons Cardenas and
Cardenas entitled “Legal_Opinion_Caldas_Finance_Corp”, which summarized the findings of their
review of CGM’s land title and tenure, upon which Dentons Cardenas and Cardenas have agreed SRK
can rely on for this disclosure.
These items have not been independently reviewed by SRK and SRK did not seek an independent
legal opinion of these items.
.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 45
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
4 Property Description and Location
4.1 Property Location
The Marmato Project is located in the Municipality of Marmato, Department of Caldas, Republic of
Colombia and is approximately 125 km due south of the city of Medellín, the capital of the Department
of Antioquia (Figure 4-1).
The property sits between latitudes and longitudes 5°28’24”N and 5°28’55”N, and 75°34’46”W and
75°37’80”W, respectively; with altitudes ranging from approximately 200 to 1,705 meters (m). The
Project can be accessed from Medellín via paved roads on the Medellín to Cali highway (Route 25)
which forms part of the Pan America Highway.
Source: SRK, 2012
Figure 4-1: Location Map
4.2 Mineral Titles
The Marmato project area has historically been divided into three main zones with numerous license
boundaries defined within. What has traditionally been termed the Marmato project was made up of
three separate concessions (Figure 4-2), named Zona Alta (#CHG_081), Zona Baja (#014-89m) and
Echandia (#RPP_357), of which Zona Baja is 100% owned by CGM and Zona Alta and Echandia are
owned indirectly, through other subsidiaries, by Gran Colombia.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 46
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
CGM currently holds the Zona Baja license (#014-89m) and has rights to continue mining the
neighboring Echandia license (#RPP_357) in which the Company conducts mining operations, and is
in the midst of completing a license to be granted by MAO, an indirect, wholly owned subsidiary of
Gran Colombia, to mine Levels 16 and 17 of Zona Alta (License #CHG_081). These are also referred
to as the CGM Mining Assets in this report.
Source: Mineros Nacionales, 2010
Figure 4-2: Land Tenure Map(s)
The horizontal division of mining rights at Marmato is unique in Colombia and was created in 1946 by
Law 66 to enable mining title contracts to be defined by horizontal mine levels. This is defined as an
Aporte Minero Mine (Mining Contribution 1017 for precious metals), which was granted in 1981. The
top of the Zona Baja is defined in Contract #014-89 with Mineros Nacionales S.A. (Mineros Nacionales)
and coincides with the road and varies from 1,207 m to 1,298.3 m in elevation.
The Zona Baja license lies below the Marmato Zona Alta property and is adjacent to Echandia. Zona
Baja extends east to the River Cauca. The license is bounded vertically by the Zona Alta and Cerro El
Burro in Marmato, but in the other parts it continues to surface. The license continues vertically to
depth in all parts.
The Zona Baja contract was owned by Mineros Nacionales, a private Colombian corporation which
was owned 94.5% by Mineros S.A. (Mineros), a Colombian corporation whose shares are traded on
the Colombian stock exchange (BVC – Bolsa de Valores de Colombia). The remaining 5.5% of
Mineros Nacionales was owned by a number of private and juridical persons. The contract registration
number is 014-89m and the mining title registration number is GAFL-11. It covers a surface area of
952.5830 hectares (ha). The Zona Baja contract was awarded to Mineros Nacionales, since renamed
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 47
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
CGM, in October 1991 and is valid for 30 years until October 2021. In October 2017, CGM commenced
the process to renew the contract for another 30-year term.
On February 15, 2010, Medoro Resources Ltd. (Medoro) acquired all of the issued and outstanding
ordinary shares of Mineros Nacionales S.A. from Mineros S.A., for total cash consideration of
US$35 million. With this acquisition, Medoro acquired 100% of Mineros Nacionales' interests in the
Zona Baja concession (the Zona Baja property). Medoro merged into Gran Colombia in 2011.
The Echandia property lies to the north east of the Zona Alta limit, and extends to depth. The Echandia
license has contract number RPP_357 and mining title registry number EDMN-01. The
Reconocimiento de Propiedad Privada (RPP) type of contract translates as Recognition of Private
Property. RPPs were created by Law 20 in 1969. The law respected prior mining and land rights and
required that proof be submitted of mining. Echandia is an old freehold property dating from the 19th
century. The RPP titles grant surface and subsurface rights in perpetuity.
Exploitation is required in order to maintain the validity of an RPP license. Mining on a relatively small
scale is being maintained in the area of contract number RPP 357 and the Company has an operating
contract permitting it to mine underground in this area.
Effective June 10, 2011, Gran Colombia completed a merger with Medoro and the combined company
continued under the name Gran Colombia. As a result, Gran Colombia acquired 100% of Medoro’s
interest in the Marmato project, including the Company’s license in Zona Baja.
On February 24, 2020, Caldas Gold completed its reverse takeover transaction (RTO Transaction)
with Caldas Finance Corp., an indirect wholly-owned subsidiary of Gran Colombia, pursuant to which
Caldas Gold, until then known as Bluenose Gold Corp., acquired the CGM Mining Assets through the
acquisition of all of the issued and outstanding shares of Gran Colombia’s newly incorporated, indirect
wholly-owned subsidiary, Caldas Finance Corp., which holds all of the issued and outstanding shares
of Caldas Gold Colombia Inc., a Panamanian company. Caldas Gold Colombia Inc. holds all of the
issued and outstanding shares of CGM, which in turn, holds all of the CGM Mining Assets included in
the RTO Transaction. The CGM Mining Assets principally comprise the existing producing
underground gold mine (#014-89m), the existing 1,200 t/d processing plant and the area
encompassing the MDZ mineralization, all located within the mining license area referred to as Zona
Baja. The CGM Mining Assets also include two contractual rights:
• One, granted by Croesus, an indirect, wholly owned subsidiary of Gran Colombia, to mine in
the lower portion of the Echandia license (#RPP_357) area
• Another, in the process of being completed, to be granted by MAO, an indirect, wholly owned
subsidiary of Gran Colombia, to mine Levels 16 and 17 of Zona Alta (License #CHG_081)
The CGM Mining Assets comprise the Marmato Project that is the subject of this report.
The purchase price for the CGM Mining Assets was CAD$57,500,200, satisfied through the issuance
to Gran Colombia (through an affiliate) of 28,750,100 common shares of Caldas Gold, CGM’s ultimate
parent, having a deemed price of CAD$2.00 per common share.
SRK noted within the transfer of licenses from the previous owner, there is a gap between the existing
licenses for #014-84M and RPP-357. This ground was under application from the CGM with the
Colombia government for formal approval to continue mining. SRK reviewed the application within the
government website and noted that the status is defined as “in progress”, which has been the status
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 48
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
since September 30, 2009. The Company has been taking steps to get the approval finalized. It is
SRK’s understanding that at the time of writing CGM has received notification (May 2020) to continue
mining in this area and that under the new Colombia mining license coding, the government does not
consider the gap to be present. SRK has not completed sufficient work to confirm this but would
highlight that it should be resolved and enable additional material to be used in mine plans for future
studies.
The exclusion zone (gap) was considered in the PFS where CGM ownership was not secured at the
beginning of the PFS work within the Mineral Resources. As the PFS was nearing completion CGM
informed SRK that the gap was no longer an issue, however a re-design to include the gap area was
not completed. For the reserves stated here, UZ development mining does go through the gap area.
A summary of the location of the area of concern is shown in Figure 4-3. It is expected that this will not
limit the current mining operation. SRK estimates within this area on a global basis for the Mineral
Resources approximately <5% of the Measured and Indicated Mineral Resources and approximately
3% of the Inferred material.
Level 1,050 m, area in green is under application but has been historically mined. Source: SRK, 2019
Figure 4-3: Summary of Gap in Licenses Within the Current Operations, with Associated Applications
Area under Application
No# KIU-11401 Original Application: 9/30/2009Status: Under Review RPP_357
014_89m
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 49
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
4.2.1 Nature and Extent of Issuer’s Interest
In regard to surface rights at the Project, CGM compiled a GIS database of surface rights ownership
within a 6 km radius of Marmato. Each of the properties was reviewed to determine discrepancies
between legal descriptions and actual ownership. The mining law allows for expropriation of land if
negotiations among subsurface and surface owners are unsuccessful.
As part of the mining licenses, CGM’s continuing obligations to maintain its mining concession in good
standing are:
• Conducting mining activities in the concession without interruptions. Any suspensions of
mining activities for more than six continuous months (save for force majeure) have to be
authorized by the Mining Authority
• Payment of the economic considerations based on production as set forth in the concession
contract (royalties, production taxes, and other economic consideration)
• Timely compliance of legal or contractual reporting obligations before the Mining Authority,
such as the annual and semi-annual filing of basic mining formats
• Compliance with relevant environmental laws and regulation, which includes obtaining and
complying with any permits that are required to carry out the corresponding mining activities
(such as water concession permits, discharge permits, Environmental Management Plans,
etc.)
• Maintaining insurance policies as required under the concession contract (civil liability policy,
contractual compliance policy, and compliance of labor obligations)
4.3 Royalties, Agreements and Encumbrances
In 1991, CGM (formerly Mineros Nacionales S.A.S.) entered into an agreement with Ecominas (a State
Industrial and Commercial Organization) for the exploration and exploitation of Mining Title No.014-
89M. The mentioned title was previously granted by the Colombian State to Ecominas. It was agreed
by the parties that CGM would pay a royalty to Ecominas (now referred to as Agencia Nacional de
Mineria) equal to 6% on gold revenue and 8% on silver revenue as economic compensation.
Additionally, CGM is bound by law to pay the Colombian State a 4% royalty.
CGM also pays a royalty of 4% on gold and silver revenue to an associated company owned by Gran
Colombia, Minera Croesus S.A.S. (Croesus), in respect of production sourced from the neighboring
Echandia mining title (#RPP_357) owned by Croesus. This royalty obligation remains in place.
4.4 Environmental Liabilities and Permitting
The main environmental details for the Project are covered in Section 19.1 of this report
4.4.1 Environmental Liabilities
The existing Marmato project is authorized through the approval of an Environmental Management
Plan (Planes de Manejo Ambiental or PMA). The PMA for Marmato was approved by the regional
environmental authority, Corpocaldas, on October 29, 2001 under Resolution 0496, File No. 616. The
PMA, and its requisite environmental management procedures and practices, amount to
approximately US$482,000 annually. This amount is likely to increase with the MDZ expansion project,
as additional monitoring and management will be required.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 50
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
The 2001 mining code requires the concession holder to obtain an Insurance Policy to guarantee
compliance with mining and environmental obligations which must be approved by the relevant
authority, renewed annually, and remain in effect during the life of the Project and for three years from
the date of termination of the concession contract. According to CGM, the current amount covered by
the policy is COL$302,835,000 (USD$91,768). This amount will be reviewed and adjusted during the
modification process of the PMA for the MDZ expansion project.
According to the Code, the concession holder is liable for environmental remediation and other
liabilities based on actions and/or omissions occurring after the date of the concession contract, even
if the actions or omissions occurred at a time when a third-party was the owner of the concession title.
The owner is not responsible for environmental liabilities which occurred before the concession
contract, from historical activities, or from those which result from non-regulated mining activity, as has
occurred on and around the Marmato Project site.
Current liabilities at the site are generally associated with the reclamation and closure of the mining
facilities and tailings disposal areas. Given the extensive impacts associated with artisanal mining in
the area, a clear delineation between possible environmental liabilities attributable to CGM and those
from unregulated mining activities is not possible; however, CGM has been making a concerted effort
to deal with legacy environmental issues in order to better make that separation. The social issues
related to mining in Colombia, especially the interactions between mining companies and artisanal
operators could continue for CGM employees and the neighboring communities.
4.4.2 Required Permits and Status
Discussion related to mining in Colombia, the Mining and Environmental Codes, as well as the permits
and authorizations necessary for mineral exploration and exploitation is provided in Section 20.3.
4.5 Other Significant Factors and Risks
There are no legal restrictions that affect access, title or right or ability to perform work on the property
with the exception of the pending license approval.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 51
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
5 Accessibility, Climate, Local Resources, Infrastructure and Physiography
5.1 Topography, Elevation and Vegetation
The Marmato project is located in an area of steep mountainous terrain with a relief of approximately
1,600 m (Figure 5-1). The Project is bound to the east by the Cauca River at 600 m elevation, and
otherwise surrounded by the peaks of the nearby mountains that reach up to 2,200 m elevation and
are commonly incised through landslide activity. Despite the abrupt relief, the landscape is in general
well vegetated and supports crop cultivation and livestock. The dominant land use in the area of
Marmato is cattle grazing, coffee, sugar cane, citrus fruit, bananas, and mining. The Middle Cauca
region, where Marmato is located, was occupied for two thousand years before the Spanish conquest
by farmers, potters, gold miners and goldsmiths of the Quimbaya culture (500 BC to 1600 AD).
The ecological zones defined on the Holdridge Life Zone climatic classification system are zoned by
elevation (Municipio de Marmato, 2004; Correa, 2006; Cia Minera de Caldas, 2008):
• Premontane (subtropical) wet forest transitional to tropical moist forest and dry forest; defined
as temperatures >24°C, annual rainfall of 1,500 to 2,800 mm, and elevation of 700 to 1,000
m. This area includes the Cauca River valley and the lower part of El Llano town.
• Premontane (subtropical) wet forest defined as temperatures of 18°C to 24°C, rainfall of 2,000
mm to 4,000 mm, and elevation of 1,000 to 1,900 m. The main areas of mining and exploration
are in this zone.
• Lower montane (warm temperate) wet forest defined as temperatures of 12°C to 18°C, rainfall
of 2,000 to 4,000 mm, and elevation of 1,900 m to 2,900 m.
Much of the original forest cover has been cleared for agriculture and grazing, especially at lower
elevations. Land is used for cattle grazing, coffee, sugar cane, citrus fruit, bananas, and mining in
Marmato.
5.2 Accessibility and Transportation to the Property
The Project is in the Municipality of Marmato in Caldas. The concessions of the Marmato Project are
located on the eastern side of the Western Cordillera (Cordillera Occidental) of Colombia on the west
side of the Cauca River.
Marmato is 200 km east of the Pacific Ocean and 300 km south of the Caribbean Sea and Atlantic
Ocean. The nearest port is Buenaventura on the Pacific Ocean (320 km by the Pan American Highway
to the south west).
The property is a three-hour drive from Medellín, via the Medellín to Cali highway which is part of the
Pan American Highway, National Route 25. The route from Medellín is via Itaguí (7 km), Caldas (12
km), Alto de Minas (13 km), Santa Barbara (27 km), La Pintada (26 km), La Guaracha del Rayo (32
km), and then a turn onto a secondary road to an 8 km long partially asphalted road to Marmato. There
is an international airport located in Medellín with flights to the USA, Panamá, Venezuela, Spain and
Peru, and a national airport in Manizales with flights to Medellín and Bogotá.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 52
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SRK, 2012
Figure 5-1: Marmato Project, Looking Northwest Towards Cerro El Burro
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 53
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
5.3 Climate and Length of Operating Season
Climate at the site is typical of the equatorial zone, with the region falling within the Köppen
classification zone of Am, described as moist tropical climates with high temperatures year-round and
short dry seasons in a monsoon cycle. Average annual precipitation was estimated as 1,889
millimeters per year (mm/y) (Knight Piésold, 2012) with two drier periods around January and July and
wetter periods around April-May and October-November. Temperatures are warm year-round, with
maximum temperatures ranging from 28.7 degrees Celsius (°C) to 31.6°C and minimum temperatures
in the range of 17.4°C to 18.7°C (Knight Piésold, 2012). Relative humidity at the site is typically in the
70 to 80% range. The climate allows year-round operations.
5.4 Sufficiency of Surface Rights
Refer to Section 4.2 of this report
5.5 Infrastructure Availability and Sources
5.5.1 Power
The power supply is well established for the operating Marmato UZ operations. Power is available
through the Colombian power supplier Central Hidroeléctrica de Caldas (CHEC), a subsidiary of
Empresas Públicas de Medellín (EPM) through existing local substations. Substantial transmission
capacity is available in the region around the Project, with energy provided over the transmission
system by the third largest electricity producer in Colombia, ISAGEN.
Major electrical power will be required at the new MDZ plant site as all process facilities and major
infrastructure buildings are located there. Electrical power to the MDZ plant is planned to be supplied
by Central Hidroeléctrica de Caldas S.A. (CHEC) from the 115 KV Salamina substation located 15 km
away.
Site power will be obtained from a 115 KV HV line that will be provided by the local power authority up
to the MDZ plant outdoor substation
5.5.2 Water
External water supplies are available from both groundwater and surface water sources. Dewatering
for the underground mine is currently being utilized as a water supply for the existing operations, and
withdrawals from the nearby Cascabel River have been utilized as well. Additional dewatering flows
are expected to be produced as a result of dewatering the MDZ Project. Water is also available from
the nearby Cauca River.
5.5.3 Mining Personnel
The region has currently and historically a strong mining presence with around 1,400 people working
at the current Marmato Project and a substantial number of artisanal miners in the area close to the
mine. Skilled personnel should be available from the local miners as well as supplemented from the
other nearby areas to support the workforce as needed.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 54
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Field personnel for the exploration program have been employed from the towns of Marmato and El
Llano and neighboring municipalities. In the long term, personnel currently working on the large
number of small-scale mines and from the surrounding region would be able to supply the basic
workforce for any future mining operation.
5.5.4 Potential Tailings Storage Areas
The existing processing plant has an active storage known as the Cascabel site. Three additional sites
were identified as potential tailings storage areas, DSTF 1, DSTF 2 and DSTF 6. DSTF 1 and 2 were
advanced to PFS level and were included in the PFS. DSTF 6 was identified as potential future
expansion.
5.5.5 Potential Waste Disposal Areas
Waste rock for the existing project is being used underground as backfill. The new project waste rock
will be used for construction purposes on the plant and tailings storage facilities (DSTF). Excess waste
rock will be placed in secondary stopes as backfill if not needed for other purposes.
5.5.6 Potential Processing Plant Sites
The existing project processing plant is established and operating at its current location. A viable site
has been identified for the new MDZ processing facility. The site is an undeveloped location
approximately 3 km east by road of the ore body and existing plant on a naturally occurring plateau.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 55
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
6 History Colombian gold production between 1514 and 1934 has been estimated at 49 million ounces (Moz)
which makes Colombia number one in South America with 38% of the total historical production
(Emmons, 1937). Two-thirds of the gold production was from placer deposits. Subsequent Colombian
production is estimated at 30 million ounces (Moz) by the Banco de la Republica (Shaw, 2000), which
gives Colombia a total recorded historical gold production of approximately 80 Moz. 75% of this
production came from the Departments of Antioquia and Caldas, with the Marmato Project located
near the border between the two departments.
6.1 Prior Ownership and Ownership Changes
Marmato is one of the most important historical gold properties in Colombia and lies in the heart of the
main historical gold producing region (dating back to 500 BC). The location name is derived from
“marmato” or “marmaja”, an old Spanish term for pyrite. The property has a long and complex
ownership history, summarized in Table 6-1.
Table 6-1: Ownership History at Marmato
Date Ownership History
1525 Colonization of Colombia and first references to Marmato
1634 First larger scale workings begin; and first gold mill
1798 Silver mines located at Echandia, with two near surface veins exploited
1819 to 1925 Various English companies mine gold at Marmato
1925 to 1938 Mines were expropriated and initially remained closed, then later leased to contractors
1946 Marmato was divided into two zones (law 66), Alta (Upper) and Baja (Lower)
1981 to 2004 Marmato becomes part of the Aporte Minero scheme and was managed by a succession of state mining companies
1984 to 1985 Minera Phelps Dodge de Colombia S.A. (Minera Phelps Dodge) explores the Zone Baja of Marmato
1991 Contract for the Zona Baja is awarded to Mineros Nacionales in October 1991 for a period of 30 years by the state entity Empresa Colombiana de Minas (Ecominas); the contract is now administered by Agencia Nacional de Mineria (National Mining Agency or ANM)
1996 to 2000
Conquistador Mines Ltd. (Conquistador), a Vancouver listed junior company (now called Orsa Ventures Corp), explored the Project through its Colombian subsidiary Corona Goldfields S.A. (Corona Goldfields). Conquistador had an option to explore the Zona Baja over 4 years and to acquire 50.1% of Mineros Nacionales (it bought 13.15% which it later sold in 2001), and acquired several mines in the Zona Alta.
1995 to 1997 Gran Colombia Resources Inc. (unrelated to GCM and now defunct) carried out exploration at Echandia and Chaburquia properties on the northern portion of the Marmato System
2005 - 2008 Minera de Caldas began exploration of Marmato and surrounding areas with the aim of identifying bulk mineable targets of low grade gold and silver. Colombia Goldfields Limited (CGL), began acquisition of property within Zona Alta, plus completed 46,000 m of drilling
2009 - 2010 Medoro purchased CGL (Zona Alta), Colombia Gold (Echandia) and Mineros Nacionales (Zona Baja), which consolidated the three primary gold properties at Marmato
2011 - 2019 Gran Colombia and Medoro Resources Ltd merged to create the largest underground gold and silver producer in Colombia, under the name of Gran Colombia Gold Corp.
2020 CGM acquires the current operating mine and the Marmato Deeps Project via the RTO Transaction (see section 4.2)
Source: SRK, 2020
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 56
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
6.2 Exploration and Development Results of Previous Owners
Modern exploration at Marmato began in the mid-1980s and has continued into the present day under
various entities. The exploration and development results of prior owners are listed below:
1984 to 1985: Minera Phelps Dodge explored the Zona Baja of Marmato, with the objective of defining
a 300 t/d underground operation. It completed surface and underground sampling and drilled seven
underground core holes and defined a Proven reserve of 102,900 t at 7.83 g/t gold and 24 g/t silver
and a total reserve (Proven, Probable and Possible) of 754,600 t at the same grade.
1993: Mineros Nacionales began mining the Maruja mine via a 300 t/d underground operation under
contract (No. 041-89M). Mineros S.A. acquired 51.75% of Mineros Nacionales and upgraded the mine
and mill. Mineros S.A. subsequently increased ownership of Mineros Nacionales to 94.5%. Further
exploration was completed through the 1990s with 24 underground core holes drilled and three reverse
circulation (RC) holes drilled. The plant was expanded to a capacity of 800 t/d.
1996 to 2000: Conquistador drilled 44 holes (14,873 m), 30 from surface (11,496 m) and 14
underground diamond holes (3,377 m), plus 1,147 channel samples totaling 2,847 m from surface
trenches and underground cross-cuts. Conquistador also commissioned MRDI to complete a resource
estimate and scoping study in 1998 but carried out no further work on the Project due to the expiration
of the option contract.
1995 to 1997: Gran Colombia Resources Inc. conducted soil surveys, surface magnetic and
geophysical surveys, channel samples (La Negra, La Felicia and La Palma adits) and completed 75
diamond drillholes (surface and underground) totaling 15,000 m. A scoping study was completed by
Geosystems International, Denver, in 1997 which concluded that there was not sufficient grade
continuity for a bulk-tonnage resource and mining operation, and no further work was carried out.
2005: Minera de Caldas began exploration of Marmato and surrounding areas with the aim of
identifying bulk mineable targets of low grade gold and silver. CGL carried out underground sampling,
surveying and mapping, preliminary metallurgical test work and diamond drilling to define a mineral
resource. CGL carried out 46,000 m of drilling in 2007 and 2008.
2010: Medoro commenced infill drilling of the project via surface and underground diamond drilling
with a view of producing a pre-feasibility study in 2011.
2011 to 2017: CGM completed further infill drilling from surface and underground locations, plus
channel sampling of existing cross-cuts.
2017 to 2020: CGM exploration has focused drilling on defining and infilling the MDZ, plus on-going
exploration within the current mining operations and cross-cuts on levels 20 and 21.
6.3 Historic Mineral Resource and Reserve Estimates
A number of different MREs have been completed on the property during the history of the project.
Between 2010 and 2019, SRK has produced several MREs for the Project. The most recent Mineral
Resource Statement for the Project has an effective date of July 31, 2019, which is the last date assays
were provided to SRK.
SRK has produced block models using Datamine™. The procedure involved import from
Leapfrog™Geo of wireframe models for the fault networks, veins, definition of resource domains (e.g.
high-grade sub-domains), data conditioning (compositing and capping) for statistical analysis,
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 57
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
geostatistical analysis, variography, block modelling and grade interpolation followed by validation.
Grade estimation for the veins has been based on block dimensions of 5 m by 5 m by 5 m for the
Porphyry and MDZ units. Sub-blocking to 0.5 m by 1 m by 1 m has been allowed to reflect the narrow
nature of the geological model. The block size reflects the relatively close-spaced underground
channel sampling and spacing within veins compared to the wider drilling spacing, with the narrower
block size used in the MDZ at depth to reflect the proposed geometry of the mineralization (i.e. steeply
dipping feeder zone).
SRK reviewed and updated the geostatistical properties of the domains. Gold grades have been
interpolated using nested three-pass estimates within Datamine™, using an OK routine. SRK has also
run IDW2 and NN estimates for validation purposes.
Block model quantities and grade estimates for the Marmato Project were classified according to the
CIM Definition Standards for Mineral Resources and Reserves (CIM, 2014). SRK developed a
classification strategy which considers the confidence in the geological continuity of the mineralized
structures, the quality and quantity of exploration data supporting the estimates, and the geostatistical
confidence in the tonnage and grade estimates. Data quality, drillhole spacing and the interpreted
continuity of grades controlled by the veins have allowed SRK to classify portions of the veins in the
Measured, Indicated and Inferred Mineral Resource categories.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 58
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 6-2: SRK Mineral Resource Statement for the Marmato Project, Dated July 31, 2019*, Within Zona Baja**
Category Quantity
Grade Metal
Au Ag Au Ag
Mt gpt gpt 000'oz 000'oz
Underground Vein***
Measured 2.1 4.9 23.2 325 1,543
Indicated 7.2 4.5 18.1 1,038 4,168
Measured and Indicated 9.2 4.6 19.2 1,363 5,711
Inferred 3.3 4.4 14.7 466 1,577
Underground Porphyry***
Measured
Indicated 1.6 2.7 10.1 140 527
Measured and Indicated 1.6 2.7 10.1 140 527
Inferred 0.3 3.1 9.6 34 107
Underground Deeps****
Measured
Indicated 6.4 2.6 4.7 537 978
Measured and Indicated 6.4 2.6 4.7 537 978
Inferred 41.2 2.1 2.7 2,812 3,609
Underground Combined
Measured 2.1 4.9 23.2 325 1,543
Indicated 15.2 3.5 11.6 1,714 5,674
Measured and Indicated 17.3 3.7 13.0 2,039 7,217
Inferred 44.9 2.3 3.7 3,312 5,293
* Mineral resources are not mineral reserves and do not have demonstrated economic viability. All figures are rounded to reflect the relative accuracy of the estimate. All composites have been capped where appropriate. ** Zona Baja defined as all material within License #014-89m and the portion of #RPP_357 below 1,340 masl pursuant to a current mining contract with Gran Colombia. *** Porphyry and Vein mineral resources are reported at a CoG of 1.9 g/t. CoGs based on a price of US$1,500 per ounce of gold, suitable benchmarked technical and economic parameters and gold recoveries of 95 percent for underground resources, without considering revenues from other metal. **** Deeps mineral resources are reported at a CoG of 1.3 g/t. CoGs based on a price of US$1,500 per ounce of gold, suitable benchmarked technical and economic parameters and gold recoveries of 95 percent for underground resources, without considering revenues from other metal.
The Mineral Resources quoted in Table 6-2 are no longer deemed current and should not be relied
on, and has been updated with the current Mineral Resource estimate defined in Section 14 of this
report.
No historical Mineral Reserves have been quoted for the Project.
6.4 Historic Production
Production has occurred from the Marmato property since pre-colonial times, but there are no
published historical records of the actual gold and silver production for all periods since mining
commenced, however sporadic records for different periods have been noted.
To give an indication of the current mining activity at the deposit SRK has reproduced a summary
(Table 6-3) of the total produced gold and silver at Marmato on an annual basis between 2004 and
2019. The figures also represent only the official declared gold recovered and does not include illegal
mining which persists at Marmato even to present times.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 59
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 6-3: Gold Production from the Municipality of Marmato 2004 to December 2019
Year Ore Tonnes (t) Grade Au (g/t) Au Produced (oz)
2004 186,330 3.60 21,583
2005 231,540 3.30 24,541
2006 262,517 3.10 26,171
2007 300,756 3.22 31,127
2008 254,474 2.95 24,138
2009 250,638 3.51 24,372
2010 252,136 3.39 23,318
2011 250,553 3.19 22,715
2012 268,137 2.85 21,717
2013 274,190 2.90 22,566
2014 295,023 2.85 24,116
2015 303,279 2.79 23,954
2016 341,308 2.55 23,447
2017 366,485 2.46 25,162
2018 340,052 2.67 24,951
2019 370,494 2.48 25,750
Source: CGM, 2020
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 60
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
7 Geological Setting and Mineralization
7.1 Regional Geology
The Colombian Andes are part of the Northern Andean Block which includes the Northern Volcanic
Zone of the Andes (Gansser, 1973; Shagam, 1975). They are formed of three N to NNE trending
mountain ranges, the Western, Central and Eastern Cordilleras, separated by two major intermontane
basins, the Cauca-Patía Depression and the Magdalena Depression, which represent terrane
boundaries. The Colombian Andes have a complex history of volcanism, subduction, accretion and
faulting, represented by the juxtaposition of metamorphic, igneous and sedimentary rocks of various
ages from the Precambrian to the present (Aspden et al., 1987; Restrepo and Toussaint, 1988). Cediel
et al. (2011) have defined nine principal tectonic terranes in Colombia which are:
• Guyana shield
• Maracaibo sub-plate
• Central continental sub-plate
• Pacific terranes
• Caribbean terranes
• Choco-Panama arc
• Guajira terrane
• Caribbean Plate
• Nazca Plate
Marmato is located on the eastern side of the Western Cordillera which is separated from the Central
Cordillera by the River Cauca. It lies within the Romeral terrane which is bounded by the Cauca Fault
on the west side and the Romeral Fault to the east and is part of the Pacific terranes realm. The recent
tectonic setting of the Colombian Andes is characterized by the subduction of young (less than 20
mega annum [Ma]) oceanic crust beneath relatively thin continental crust (less than 40 km; Cediel and
Caceres, 2000; Cediel et al., 2003). The Benioff zone is located at around 140 to 200 km depth below
the volcanic belt of the Colombian Andes which has slightly migrated to the east during the last 10 Ma
(Pennington, 1981; Vargas & Mann, 2013).
The Marmato stock is part of the Miocene magmatism characterized by calc-alkalic subvolcanic
intrusions and volcanic rocks of the Combia Formation. The Miocene magmatism cross-cuts the units
of the Romeral terrain, the plutonic units of the Albian and early Cenozoic, and the siliciclastic
sequences of the Amagá Formation (Cáceres et al. 2003; Tassinari et al, 2008). Miocene gold related
magmatism in Colombia has been well-recognized in the Western and Central cordilleras associated
with stocks (Sillitoe et al., 1982; Toussaint and Restrepo, 1988; Lodder et. al, 2010; Lesage et al.,
2013). In addition, late Miocene-Pliocene magmatism with gold mineralization has also been
recognized in the Santander Massif in the northern part of the Eastern Cordillera (Mantilla et al., 2009).
The regional geology is shown in Figure 7-1.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 61
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: Modified from the Geological Map of Colombia, 1:1 million scale, Colombian Geological Survey, 2015
Figure 7-1: Regional Geology Map
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 62
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
7.2 Local Geology
The Marmato gold deposit is hosted by the porphyritic andesitic to dacitic Marmato stock which is
18 km long and 3 to 6 km wide and is elongated north to south (Calle et al., 1984). It intrudes the
Arquía Complex and Amagá Formation on the east side in the Cauca Valley and the Combia Formation
on the west side. The Marmato gold deposit is hosted in a multiphase porphyry suite, the Marmato
Porphyry Suite, which is about 3 km long by 1.6 to 2.5 km wide and is located near the southern end
of the larger Marmato stock. Five main porphyry pulses have been identified in the Marmato Porphyry
Suite by cross-cutting relationships in core logging and named P1 to P5 from oldest to youngest,
respectively. The ages of the intrusions have been reported recently between 6.58 ± 0.07 Ma to 5.74
± 0.14 Ma by U-Pb LA-ICP-MS of zircon (Caldas, 2016, dating carried out by the Brasilia University
Isotope Geochronology Laboratory, Brasil). The Aguas Claras Porphyry Suite is located 3 km
southwest of the Marmato Porphyry Suite and also has five porphyry pulses identified from cross-
cutting relationships in core logging named AP1 to AP5 from oldest to youngest. Two intrusions of the
Marmato Porphyry Suite, P3 and P5, cross-cut the Aguas Claras Porphyry Suite as dikes. There is no
previous dating of the Aguas Claras Porphyry Suite. The local geology map is presented in Figure 7-2.
Source: Caldas, 2017
Figure 7-2: Local Geology Map
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 63
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: Modified from Caldas, 2018. Original Source in Figure
Figure 7-3: Regional Geology with Gold Prospects in the Marmato Area
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 64
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
The main rock types within the area are summarized below in Sections 7.2.1 to 7.2.7.
7.2.1 Graphitic-Sericite Schist (MSG)
They constitute the metamorphic units of the local area and appear as dark rocks, with schist texture,
demonstrating evidence of a ductile deformation crenulation cleavage, with predominant orientation in
NNW-SSE, and steeply dipping. Evidence exists of several metamorphic events. This lithology is found
as suspended ceilings towards the central and northwestern area of the title, as well as large xenoliths
(more than 20 m in diameter) within the bodies of the main porphyry, their best outcrops are observed
in the upper areas of the El Burro hills and the Echandía area.
7.2.2 Amphibolites (MAB)
This lithology is not present within the title in any significance. The metabasites of the Arquía Complex
correspond to green schists and amphibolites; they correspond to dark green to light green rocks,
interspersed with small bands of quartz-muscovitic schists with graphite. Petrographically they are
represented by quartz-chloritic schists with muscovite, chloritic schists, actinolite/horblende schist with
chlorite, quartz actinolytic schists, with a mineralogy composed of actinolite (24 to 45%), chlorite (8 to
35%), horblende (less than 5%), zoisite/clinozoisite (3 to 8%), quartz (5 to 37%), plagioclase (4 to 6%),
muscovite (1 to 4%). The most common accessory minerals are calcite, titanite, hematite, magnetite
and ilmenite; the characteristic textures are nematoblastic (actinolite), lepidoblastic (chlorite) and
porphyroblastic (epidote) (Moreno et al, 2012).
Amphibolites are dark green to light green rocks, with compositional banding of plagioclase and
horblende, occasionally with garnet, the modal composition is given by horblende (42 to 46%),
plagioclase (25 to 28%), garnet (15 to 17%), quartz (9 to 14%); the characteristic textures are
nematoblastic (horblende) and porphyroblastic (garnet).
7.2.3 Serpentinites (MSP)
This lithology is not present in the mining title area. The mafic and ultramafic rocks are represented by
an elongated strip in the North-South direction, corresponding to Gabros of fine to medium grain, dark
greenish-gray color, with a mottled appearance, exhibiting an incipient fluid texture, near the fault
zones it presents genesis textures being difficult to differentiate the primary foliation from the dynamics.
The essential components are plagioclase, horblende, pyroxene, sericite, clinozoisite, zoisite, chlorite,
calcite, epidote, biotite, sphene, apatite, magnetite-ilmenite. These rocks are associated with the
remains of an Ophiolithic Complex of presumably Pre-Jurassic age and that was located during the
Cretaceous (Gonzales, et. Al, 1982).
7.2.4 Basalts (VB)
They correspond to massive crystalline rocks, of aphanitic texture, dark (melanocratic) coloration,
slightly magnetic, composed of plagioclase, pyroxenes and amphiboles which are generally
chloritized. Its outcrops are located towards the southeast of the title on the Cascabel and Aguas
Claras ravines and is interpreted as roof pendants associated with the intrusion of the porphyritic stock.
7.2.5 Clastic Sedimentary Rocks (S)
The remnants of a clastic sedimentary sequence made up of quartz-lithic sandstones, from cream to
brown tones, with a medium to coarse grain size, friable, are observed in subtabular layers of varying
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 65
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
thicknesses, which are observed interstratified with clay. The units are characterized by presenting a
high state of weathering and have a preferred orientation of the stratification is N20-30W/30-50NE.
7.2.6 Marmato Porphyry Stocks (P1 – P5)
The porphyritic andesitic to dacitic Marmato stock which is 18 km long and 3 to 6 km wide and is
elongated north to south (Calle et al., 1984). It intrudes the Arquía Complex and Amagá Formation on
the east side in the Cauca Valley, and the Combia Formation on the west side.
The ages of intrusion, alteration, and mineralization are Late Miocene. The Marmato Stock has been
dated with 6.3+-0.7 Ma (K/Ar) porphyritic dacite (Sillitoe, 1982); 7.1+-0.2 Ma (K/Ar) in porphyritic
andesite biotite (Rossetti & Colombo, 1999); 6.7+-0.06 Ma (Ar/Ar) in porphyritic andesite biotite
(Vinasco, 2001); 5.6+-0.6 Ma (K/Ar) for sericitized plagioclase in porphytic dacite from the MDZ (R &
Tassinari, 2003), the latter is interpreted as the age of deposit formation being slightly younger than
the intrusions. Likewise, Santacruz (2016) finds two different ages and exposes the idea of two
magmatic events, the first one dated at 6.58-6.3 Ma (U/Pb in zircon) and a second event dated at 5.7
Ma (U/Pb in zircon)
The Marmato gold deposit is hosted in a multiphase porphyry suite, the Marmato Porphyry Suite, which
is about 3 km long by 1.6 to 2.5 km wide and is located near the southern end of the larger Marmato
stock. Five main porphyry pulses have been identified in the Marmato Porphyry Suite by cross-cutting
relationships in core logging and named P1 to P5 from oldest to youngest, respectively. The ages of
the intrusions have been reported recently between 6.58±0.07 Ma to 5.74±0.14 Ma by U-Pb LA-ICP-
MS of zircon (Caldas, 2016, dating carried out by the Brasilia University Isotope Geochronology
Laboratory, Brasil).
The Aguas Claras Porphyry Suite is located 3 km southwest of the Marmato Porphyry Suite and also
has five porphyry pulses identified from cross-cutting relationships in core logging named AP1 to AP5
from oldest to youngest. Two intrusions of the Marmato Porphyry Suite, P3 and P5, cross-cut the
Aguas Claras Porphyry Suite as dikes.
7.2.7 Unconsolidated Quaternary Deposits (QC)
Unconsolidated quaternary deposits are present within the mining areas, which include old landslide
bodies made up of alluvial gravels and the waste material extracted by artisanal miners that are
collected on the slopes of Cerro El Burro over the municipality of Marmato. There are also small
deposits of poorly calibrated gravels, with angular to sub-rounded clasts whose sizes vary from
pebbles to blocks, generally supported matrices, which do observe discordant outcropping lithologies
in the main stream gorges in the area.
7.3 Property Geology
The Marmato gold deposit consists of a structurally-controlled epithermal vein system with a mineral
assemblage dominated by pyrite, arsenopyrite, black Fe-rich sphalerite (the type locality for
“marmatite”, Boussingault, 1830), pyrrhotite, chalcopyrite and electrum in the UZ and a mesothermal
veinlet system with a mineral assemblage dominated by pyrrhotite, chalcopyrite, bismuth minerals and
visible gold in the MDZ.
Dacitic and andesitic intrusions at Marmato are characterized by quartz, hornblende, biotite and zoned
plagioclase phenocrysts in a finely crystalline quartz-plagioclase groundmass, with variations in
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 66
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
phenocryst proportion and sizes between intrusions. A total of five different porphyry units have been
identified which are summarized below:
Dacitic Porphyry (P1)
It is a compact, solid, granular rock characterized by the presence of large quartz phenocrystals
(5 millimeter [mm] diameter), hornblende, biotite and plagioclase phenocrystals zoned with a fine
granular matrix of quartz and plagioclase, with variations in sizes and percentages. The P1 intrusion
is the main Dacitic body of the Marmato Porphyritic Suite and therefore represents most of the geology
of the title, it is overlain by quartz-sericitic-graphite shales of the Arquía Complex and contains small
intrusions of the andesite P4 as well as the other porphyritic intrusive bodies.
Andesitic Porphyry (P4)
The P4 intrusion corresponds to an igneous, slightly equigranular, massive igneous rock, of grayish
hue, medium grain size, characterized by the scarce or almost null presence of quartz, accompanied
by abundant phenocrystals of coarse plagioclase with biotite, horblende and magnetite, the
amphiboles are generally chloritized. They represent the second body in terms of importance within
the suite since it also acts as a host to the mineralization.
An Andesite P4 forms a stock on the NW side of Cerro Los Novios and extends NE through Echandía;
It has a NE orientation with dimensions of approximately 1,600 m length and 750 m width; towards the
southeast there are numerous P4 dikes with a NW and E-W tendency.
Porphyritic Dacite (P2)
It appears as a smaller intrusion than the P1 and P4 intrusions and is characterized by being a solid,
hypocrystalline rock, with a medium grain size (finer than P1), light gray coloration, mineralogically
constituted by small sub-rounded quartz crystals, accompanied by mildly zoned and epidotic
plagioclase phenocrystals, biotite’s and euhedral and generally chloritized amphiboles. This intrusive
body has not been observed on the surface but exclusively logged in drill core.
Porphyritic Andesite (P3)
Porphyritic andesite dikes with a NW and EW tendency and 400 m in length have been observed in
contact with P1 in the Cascabel gorge and other occurrences in Echandía. The P3 units is
characterized by the presence of slightly zoned plagioclase euhedral megacrysts (15 mm long), with
small subhedral crystals of plagioclase, biotite, hornblende, and to a lesser extent quartz and
magnetite (Figure 7-4 photos of porphyry). At the drilling core level, it has been observed cutting the
P1 and P2 bodies.
Porphyritic Dacite (P5)
Porphyritic Dacite Dikes P5 have been observed cutting the P1 porphyry within the Cascabel gorge
and selected drilling cores. P5 is characterized by massive, uneven, hypocrystalline texture, with small
euhedral crystals of quartz and elongated plagioclase phenocrystals of up to 10 mm in length, with
additional, biotite and horblende crystals present. Mineralization is absent in this lithology and there is
dating that gave an age of 5.7 Ma (U/Pb in zircon) (Santacruz, 2016).
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 67
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: Caldas, 2020
Figure 7-4: Photographs of the Different Porphyritic Intrusive Bodies that Make Up the Porphyry Stock Of Marmato
The P1 Intrusion is a main dacitic porphyry stock in the Marmato Porphyry Suite and is characterized
by large β quartz phenocrysts more than 7 mm. It is cross-cut by intrusion P2 which corresponds to a
porphyry dacite intrusion with fewer and smaller phenocrysts. Intrusion P3 forms dikes of andesitic
porphyry with plagioclase megacrysts more than 10 mm, and cross-cuts intrusions P1 and P2 (Figure
7-5). Intrusion P4 is an andesitic porphyry stock which cross-cuts P1, P2 and P3, and is characterized
by smaller plagioclase phenocrysts. The youngest porphyry P5 is dacitic and forms dikes cross-cutting
P1. It is characterized by large quartz phenocrysts and elongate plagioclase phenocrysts.
Mineralization is hosted mainly by stocks P1 to P4, while is absent in P5.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 68
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SRK, 2020
Figure 7-5: Property Geology Map
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 69
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: CGM, 2019 The deposit outcrops on El Burro Hill and Echandía Hill
Figure 7-6: Cross-Section of the Marmato Gold Deposit Looking NW Showing the Intrusions P1 to P5
7.3.1 Structure
The dominant NW and E-W trends of the veins are interpreted to be due to regional tectonic forces
and may have formed as tension fractures related to NW-SE compression and sinistral strike-slip
movement on the N-S trending Cauca and Romeral Faults which lie on either side of the deposit.
In April 2010, the Company commissioned Telluris Consulting Ltd (TCL) to complete a review of the
local and regional geology to define a structural-hydrothermal model for the Marmato deposit. TCL
defined the Marmato deposit as a series of N-NW to E-W trending steep to moderately dipping, gold-
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 70
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
bearing, sulfide-rich veins hosted in a north-south trending late Miocene porphyry complex. TCL noted
that the porphyry complex was emplaced in folded and thrusted Paleozoic and Mesozoic metamorphic
and sedimentary sequences adjacent to the eastern margin of the broadly N-S trending Cauca-
Romeral terrane accompanied by east northeast to northwest-southeast compression. This resulted
in N-S trending thrust and transpressional structures along with steep NW and NE conjugate fault
zones.
Within the relatively young intrusive rocks of the Marmato deposit there are principally two deformation
stages recognized from the TCL study:
• Syn-mineralization W-NW-E-SE compression that reactivated some of the basement
structures as well as generating a range of second order shear and extensional structures
along N-NW to E-W trends as well as N-NE trending thrusts
• Continued post-mineralization compression into the late-Pliocene, (approximately 2 Ma) that
resulted in uplift due to renewed thrusting along the main terrane boundaries forming thrust-
bounded intermontane basins such as the Cauca-Patia depression
Within the Marmato area, there are four principal trends of mineralized structures:
• NW trending steep to sub-vertical faults/fractures (140° to 150°N)
• W-NW trending steep to moderately inclined structures (110° to 120°N)
• E-W trending structures (100° to 090°N) that tend to have moderate to relatively low-angle
dips
• E-NE to NE-trending structures (065° to 080°N) that show a range of dips
In addition to these ore-bearing structures, there is a set of N-NE trending structures of varying dips
that appear to represent different components of a reverse/thrust fault system. Both the W-NW and E-
W veins tend to splay from the main NW structures which is consistent with extensional and Riedel
shear components to a sinistral shear system. TCL reported that kinematic indicators show that
mineralization accompanied a phase of W-NW to E-SE orientated compression (Figure 7-7). The
north-northeast trending reverse faults and conjugate fractures reflect this compression component.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 71
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: TCL, 2010
Figure 7-7: TCL Interpretation of Vein Orientations at Marmato
Post-mineral failures of preferential trend N80E to E-W/60NE are observed in the margins of some
veins and veins with alteration to soft white clay gouge with ground pyrite registered as fault gouge,
(FLG). In some places, there is coarse euhedral pyrite in the clay gouge. Brittle fault gaps without clay
gouge (BXF) are also observed. In the mining works of the MDZ of CGM, it is observed that the N30-
40W trend veins rotate counterclockwise to the northwest at N50-60W. They have competent wall
rocks and do not require maintenance by the miners: while the veins that have an east-west tendency,
are faulted in the backing rock with soft clay gouge and require support from the miners.
Within the MDZ, mineralization is hosted within veinlets. These veinlets develop in tension fractures
that are arranged parallel to the main stress tensor which, as indicated before, is of the WNW-ESE
trend. Within a Riedel-type analysis, these are called "T" type fractures, do not show rotation or elapse,
and their deformation mechanism is exclusively traction opening perpendicular to compression σ1.
The veinlets on occasions have intersected the drilling core at high angles indicating the steep dip of
the mineralization.
After the mesothermal mineralization was placed in the "T" veinlets, these veinlets were reactivated
and affected by subsequent epithermal events. They can be observed in several drillholes as the
veinlets served to delimit the intensity of the alteration or to separate between type of alterations.
7.3.2 Alteration
Two stages of pervasive alteration have been recognized, early propylitic and later intermediate
argillic. These affect all types of porphyryitic rocks, although alteration is weak in P5. The propylitic
alteration is characterized by epidote replacement of plagioclase cores, albite replacement of
plagioclase rims and matrix, chlorite replacement of mafics, with disseminated pyrite and pyrrhotite,
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 72
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
and varies in intensity from veinlet-halo to pervasive. Calcite partially replaces plagioclase where
propylitic alteration is weakly developed. Cross-cutting relationships show evidence for multiple events
of propylitic alteration related to each phase of intrusion.
Intermediate argillic alteration overprints the propylitic alteration and varies in intensity from
vein/veinlet-halo to pervasive, associated to the intermediate sulfidation mineralization style and
replaces epidote, chlorite and albite. There is a strong but generally narrow halo of white to green illite
or sericite alteration related to veins and veinlets of the mesothermal mineralization event which grades
outwards to pervasive illite, with smectite in distal parts. The main disseminated sulfide is pyrite,
although pyrrhotite and iron-rich sphalerite also occur, which to some extent formed the basis for the
previous model domains.
Additionally, weak and patchy potassic alteration, represented chiefly by biotite occurs at depth in the
MDZ. Progressively better preservation of early potassic alteration at depth may indicate the possibility
of early gold-bearing phases.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 73
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
o Propylitic
o Sodium-Calcite
o Potassic
o Argilic
Source: CGM, 2020
Figure 7-8: Types of Alteration Found at Marmato
Chloritized Biotite and Hornblende
EpidoticPlagioclase
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 74
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
7.4 Significant Mineralized Zones
Gold mineralization occurs in veins and veinlets with dominant NW and W-NW trends. The deposit
mainly comprises sulfide-rich veinlets and veins composed of minor quartz, carbonate, pyrite,
arsenopyrite, Fe-rich sphalerite (i.e. marmatite), pyrrhotite, chalcopyrite and electrum in the epithermal
Upper Zone, quartz, pyrrhotite, chalcopyrite, bismuth sulfide, telluride minerals and free gold in the
mesothermal MDZ. Pervasive early propylitic alteration is over-printed principally by phyllic and
intermediate argillic alteration related to the gold mineralized veins of low to intermediate sulfidation
epithermal type, with weak and patchy potassic (biotite) alteration at depth.
The Marmato deposit lacks known surface epithermal features, such as lithocaps, sinters and
crustifome-banded streaks. The veins can be found from the surface (1,700 meters above sea level
[masl]) and there is evidence of their continuity up to the 900 masl, on course there is a continuity that
goes from 50 m for secondary veins or splays to 600 m for the main veins.
The current significant mineralized zones in title #014-89m, are located in the NW sector of the title,
covering an approximate area of 30 Ha, with a distribution towards depth, approximately from elevation
1,200 m to 600 m, emphasizing that gold mineralization remains open at depth.
The mineralization in the current mine consists of three distinct phases, a first phase characterized by
the mesothermal vein/veinlet mineralization which defines the MDZ, followed by an epithermal low to
(subsequent) intermediate sulfidation style generally found in the UZ (SRK, 2019).
TCL recognized two principal deformation stages within the Marmato stock (TCL, 2010):
• Syn-mineralization W-NW to E-SE compression that reactivated some basement structures
as well as generating a range of second-order shear and extensional structures along N-NW
to W trends, as well as N-NE trending thrust faults.
• Continued post-mineralization compression into the late-Pliocene, (approximately 2 Ma) that
resulted in uplift due to renewed thrusting along the main terrane boundaries, forming thrust
bounded intermontane basins such as the Cauca-Patia depression.
TCL outlined four principal trends of auriferous structures within the Marmato area:
• NW trending steep to sub-vertical faults/fractures.
• W-NW trending steep to moderately inclined structures.
• W trending structures that tend to have moderate to relatively low angle dips.
• E-NE to NE trending structures that show a range of dips.
TCL reported that kinematic indicators show that gold mineralization accompanied a phase of W-NW-
E-SE orientated compression. The N-NE trending reverse faults and conjugate fractures reflect this
compression component. Within this tectonic framework the E-W faults should be predominantly
dextral strike-slip and the W-NW faults should be predominantly sinistral strike-slip (Figure 7-9). CGM
interprets the rotation of some of these structures to be the result of rotation during progressive
compressional deformation event, however CGM also noted that there are pre-gold mineralization and
post-gold mineralization phases of fault movement on a number of faults and veins (J. Ceballos, 2019,
pers. comm.)
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 75
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: CGM, 2018 (based on sources listed in text)
Figure 7-9: Structural Features Expected in a North-South Sinistral Riedel Fault System
The epithermal mineralization occurs in parallel, sheeted and anastomosing veins, all of which follow
a regional structural control, with minor veins forming splays of the main structures which often have
limited strike or dip extent (Figure 7-10). The upper vein domain intersects broader zones of intense
veinlet mineralization that is hosted by a lower grade auriferous porphyry stock (which are termed
locally as “Porphyry Pockets” or “Porphyry” mineralization.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 76
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: Caldas, 2020
Figure 7-10: Example of Epithermal Veins as Viewed in the Drilling Core at Marmato
Gold mineralization occurs in veins and veinlets with dominant NW and W-NW trends. The deposit
mainly comprises sulfide-rich veinlets and veins composed of minor quartz, carbonate, pyrite,
arsenopyrite, Fe-rich sphalerite (i.e. marmatite), pyrrhotite, chalcopyrite and electrum in the epithermal
UZ, and quartz, pyrrhotite, chalcopyrite, bismuth sulfide and telluride minerals and free gold in the
mesothermal MDZ. Pervasive early propylitic alteration is over-printed principally by phyllic and
intermediate argillic alteration related to the gold mineralized veins of low to intermediate sulfidation
epithermal type, with weak and patchy potassic (biotite) alteration at depth (Figure 7-11).
Further detail on the length and size of the veins is defined in Section 14.2 of this report.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 77
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Low to intermediate sulfidation epithermal style mineralization
Mesothermal style mineralization Source: CGM, 2017
Figure 7-11: Examples from Drill Core of the Different Mineralization Styles
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 78
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
In addition, to the mineralization within the current mine (Levels 16 to 21), CGM has identified through
exploration a deeper mesothermal mineralization referred to as the MDZ. The deeper mineralization
is hosted primarily within the P1 porphyry unit and forms fine veinlet mineralization with a discrete,
relatively high-grade gold core to the main MDZ has been identified by CGM and delimited by SRK
with more than1.7 g/t Au iso-shell (SRK, 2019).
The MDZ type corresponds to several sets of N60-70W/90 veinlets that run parallel to each other as
sheeted veins, these are controlled by the main trend stress tensor WNW-ESE, as explained in the
chapters of regional and local structural geology. For this reason, these veinlets are considered to
represent stress fractures at a very early stage in the porphyritic intrusion, which may represent a
greater extension of this mineralization to that currently explored, modeled and estimated.
The MDZ gold mineralization consists of a network of thin, less than 5 cm thick sulfide veinlets, mainly
consisting of pyrrhotite+chalcopyrite, and typically rimmed by a thin sodium-calcitic alteration halo, all
hosted in weak argillic and deeper potassic alteration related to a pre-gold mineralization event (SRK,
2019).
The Mesothermal veinlets within the MDZ mineralization follow a standard pattern, presenting a
predominantly NW orientation between 40 to 62°, with steep dips (between 70 to 84°). Minor variations
in the trend from NNW to E-W have also been noted but are less common and within borehole MT-IU-
009, another family of mesothermal veins with an N10W tendency and a dip of 47° is identified.
Source: SRK, 2020
Figure 7-12: MDZ Mineralization Showing Veinlets Including Visible Gold (Au). BHID MND282-03-17 at a Depth of 1,010 masl, Sample of 1.20 m with 18.06 g/t Au and 2.5 g/t Ag
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 79
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
8 Deposit Type
8.1 Mineral Deposit
The alteration and mineralization in the UZ at Marmato evolved through early stage, higher-
temperature propylitic alteration to later, lower-temperature intermediate argillic alteration, with most
of the gold and silver being deposited in the later stage.
The gold-silver and base metal association in the UZ at Marmato is typical of the intermediate
sulfidation epithermal type. The veins lack distinctive epithermal textures and the mineralization has a
relatively high depth and temperature of formation, which straddles the deep epithermal to
mesothermal transition as defined by the original classification of Lindgren (1922) and by estimates of
formation temperature of 300°C (Heald et al., 1987). The Marmato deposit lacks known shallow and
surface epithermal features such as lithocaps, sinters and crustiform banded veins.
Mineralization is interpreted to be genetically related to the host porphyritic rocks, as shown by the
inter-mineral timing of the porphyry phases cross-cutting earlier stages of propylitic alteration, the late-
mineral timing of the final dacite P5, and miarolitic cavities lined with propylitic-stage minerals. The
veins and veinlets are structurally controlled and did not form a multi-directional porphyry stockwork
or breccia related to hydro-brecciation. In this model, the host stocks might be considered as late-
mineral intrusions with respect to a postulated porphyry gold-copper-molybdenum centers.
The upper portion of the MDZ has been exposed in Level 21 of the existing CGM mining operations
and is referred to as the Transitional Zone, while deeper sections have been observed in drillcore,
both of which have been confirmed as separate styles of mineralization. The lowest levels of the mine
have currently intersected a combination of the porphyry domain, where the gold is associated with
pyrite veinlets and the MDZ where gold is associated with pyrrhotite. Gold grade distribution in the
MDZ orebody is unrelated to the presence of distinct porphyry phases and is entirely dependent on
the intensity of structurally localized veinlets. Sillitoe (2019) concluded, that the only geological
parameter than can be used to constrain the grade model is veinlet intensity, although the presence
of visible native gold also acts as a useful grade indicator.
8.2 Geological Model
As part of the updated Mineral Resource, SRK initially focused on the creation of a lithological model
(i.e., one encompassing the major geological features inclusive of the current veins being mined). The
lithological database provided to SRK contained 64 separate logging codes, which has been refined
to 14 logging codes by SRK. The main geological features and units modelled by SRK were:
• Major Fault Network
• Porphyry (P1 – P5)
• Meta Schist
• Intrusive
• Volcanic
• Breccia
• Veins
• MDZ
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 80
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
In comparison to the PEA lithological model, SRK made additional definition of the units within the P4
and P5 dikes. The other key change is the definition of the breccia units which crosscut the MDZ and
may need consideration for geotechnical criteria prior to mining.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 81
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
9 Exploration
9.1 Relevant Exploration Work
9.1.1 Topographic Surveys
The Company commissioned a detailed topographic map with 0.5 and 1 m resolution contour intervals
derived from LIDAR imagery, which was supplied to Datamine™ in 2020. The new topographic map
provides a detailed base map for improved accuracy when plotting the results of the exploration
programs, as well as a high-resolution satellite image.
For exploration work and also for other infrastructure and mining operation works, the topographic
information has been extracted from different remote sensors (satellite, radar) seeking to optimize the
quality (resolution) of the information.
In early 2007, a high-resolution satellite image of Ikonos and a detailed topographic map with contour
lines every 2 m were obtained. This map provided a detailed basis that served to improve the accuracy
of the drilling programs and their results. The topography was converted to a solid model in Vulcan™
to limit the grade estimate to the surface. This model has been supplied to SRK by the Company.
In 2008, the image of Ikonos and the topographic map were expanded, which were joined to the
original map of 2007 to leave a seamless final product on which the infrastructure for the Marmato
Project could be located, such as rock waste storage areas, tailings and exploration.
In 2019, the ISATECH company carried out a geodetic control work with LIDAR technology producing
a detailed topographic map with 0.5 and 1 m resolution contour intervals, which was supplied to
Datamine™ in 2020. The new topographic map provides a detailed base map for improved accuracy
when plotting the results of the exploration programs, as well as a high-resolution satellite image. In
2019, in order to ensure that the project's coordinate system was adjusted to the national geodetic
network in the MAGNA SIRGAS system, in this work 10 points of control and 9 materialized GPS
points, the area in which the work was carried out is presented in Figure 9-1.
Due to the project having gone through several stages of development and with differences in the grid
systems being used between the mine and exploration (Arenas, UTM), the Company undertook a
study to validate the geometric transformation procedures that were developed between the
planimetric and altimetric reference systems. In addition to this study, it was sought to establish a
mechanism that would allow all areas of the company that generate geographic information to have a
guideline to work in the same coordinate system according to the national standard (defined by IGAC),
for this the company Geosoluciones DAJ was hired in February 2020. The study involved the validation
of the topographic survey carried out by ISATECH in the Magna Sirgas reference frame, Gauss-Krüger
projection, west origin, by tracking and processing data from the Global Navigation Satellite System
(GNSS) of the nine materialized GPS points (Figure 9-1). The study also included a surface-
underground mooring traverse of the La Maruja mine (six levels) so that the underground database
could be tied to the MAGNA SIRGAS reference grid. Using the information, the required geometric
coordinate transformation, between the ARENA and MAGNA SIRGAS reference framework has been
established as well as the use of the UTM (Universal Transversal Mercator) coordinate system. CGM
exploration geologist then adjusted the database and geological information into the standardized
system and supplied SRK with the converted database on March 17, 2020.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 82
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 83
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SRK, 2020
Figure 9-1: Development of 3D Topography for the Project Showing LIDAR Survey Points, Shadow Model and 3D View of 1 m Resolution LIDAR Datapoints
9.1.2 Surface Geochemistry
CGM collected 1,880 rock chip samples and 700 soil samples on surface in Echandia, for a total of
2,580 samples. The geochemical samples identified anomalies coincident with low magnetic
anomalies covering an area of about 800 m by 1,100 m in size.
9.1.3 Geophysics
During 2007 and 2008, a helicopter survey which included both magnetic and radiometrics was
completed.
9.1.4 Surface Geological Mapping
Geological mapping at 1:1,000 scale has been carried out on surface, although outcrop exposures are
limited away from the steep face of Cerro El Burro above Marmato.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 84
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
9.1.5 Underground Geological Mapping
CGM supplied AutoCAD drawings of mine level plans and sections for all veins currently being mined
(Levels 16 through 21). SRK has been supplied with this information for the current update and utilized
the information during the construction of the geological model. The level plans and information have
a degree of time lag as they are not updated on a routine basis (every six months) but based on the
current production levels at CGM. It is not anticipated that any changes will have a significant impact
on the MRE. SRK has used these underground level maps (Level 16 through Level 21) as the basis
for the current interpretation of the veins, which has been supplemented with information from mining
where available. An example of a level plan is shown in Figure 9-2.
Source: CGM, 2020
Figure 9-2: Example of Level Plan from CGM (Level 20)
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 85
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
9.2 Sampling Methods and Sample Quality
Two stages of exploration have been completed at Zona Alta (#CHG_081 license). The initial phase
used basic hammer and chisel techniques to cut channels 2 m long and 5 cm wide by 1 cm deep. Due
to the relatively poor quality of sampling, many of these samples were repeated during a second stage
of exploration using a hand-held core saw.
Where access was not possible due to poor ground conditions, the original hand-cut samples have
been retained in the database but are considered of lower quality for classification purposes. The Zona
Alta area is currently mined by multiple small-scale mining operations and the Company does not have
input into the sampling processes used by the miners, nor is an active database of any sampling
compiled within these areas. SRK highlights that these sample locations are within the Zona Alta
CHG_081 license which are not included in the current Mineral Resources and are deemed to have
no material impact on the current estimate.
The Company completes routine grade control sampling using channel sampling within the current
mining operation. The process is completed by both mine geologist as part of the routine grade control
process and exploration geologist for verification. Differences exist between the two procedures, as
summarized below.
9.2.1 Mine Geology - Channel Sampling Procedure
The CGM mine geologist collect channels samples as part of the routine grade control process within
the current mine. The following is description of the sampling procedure:
• Once the underground advance faces are cleaned, the geologist completes a brief mapping
and description rock face, including samples locations, lithology, alteration, structures and
mineralization (intensity, styles). The information is handwritten and stored in paper format.
• The geologists then mark the limits of the samples on faces using spray paint. The limits are
defined based on lithological and mineralization contacts, including intensity and style of
mineralization. The minimum and maximum length used are 0.5 m and 1.0 m. The channel is
marked perpendicular to the mineralized structures (Figure 9-3).
• The geologist locates the samples using tape and compass from the closer surveyed control
point. The survey of the underground workings is done using total station (Figure 9-4)
Source: SRK, 2020
Figure 9-3: Channel Sample Marks in Marmato
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 86
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SRK, 2020
Figure 9-4: Underground Workings Survey Using Total Station
The geology technicians clean the surface and collect rock chips using chisel and hammer with the
aim to construct a channel of 10 cm width and 2 to 5 cm depth. The rock chips are collected in a plastic
pan and then packed into plastic bags which are labelled and then closed with tape or ties. The
samples are identified using metal numbering plates. Figure 9-5 shows the helpers collecting the
samples and the packed sample. The final weight of each sample varies from 0.5 to 1 kilogram (kg).
Source: SRK, 2020
Figure 9-5: Sample Collection and Packing
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 87
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
The samples collected during the day are delivered to a company geologist, who reviews the samples
and personally delivers the samples to the onsite laboratory to provide a chain of custody. SRK noted
that internal quality controls are not included in the sample stream by the geologist and SRK has
recommended that insertion of samples should be completed to follow generally accepted best
practice. In the absence of quality control information SRK has relied upon reconciliation of the planned
versus head-grade from the grade control systems to determine if the performance of the channel
sampling is reasonable. A study of the planned versus head-grades for 2006 to 2019 (discuss further
in Section 12.1.2) shows the differences in the grades range between -10% to +8% on an annual basis
but the overall performance is in the order of 98% during this period, which SRK considers reasonable.
While the study add confidence to the mine sampling it should not replace the need for an industry
standard QA/QC protocol in future sampling.
The samples are collected approximately every 2 m along the vein according to the advance of the
underground working (Figure 9-6). The geologists try to maintain constant the distance from the floor
to the sample channel.
Source: CGM, 2019
Figure 9-6: Distribution of Channel Sampling Along the Vein
9.2.2 Channel Sampling – Exploration
The CGM exploration staff conduct channel sampling of the underground workings which have been
focused on crosscuts. The procedure differs to the one used by the mine geology department, with
more focus on the sample size quality. The following is the description of the procedure:
2m
2m
2m
2m
muestra 1
muestra 2
muestra 3
muestra 4
muestra 5
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 88
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
• The surface of the underground tunnel/crosscut is cleaned with water to expose fresh rock.
The geologist initially completed a geological description of the channel, with the samples
were logged using the same logging codes as utilized in the diamond drilling procedures
including the description of:
o Lithology (color, texture, grain size)
o Alteration (type, intensity and mineralogy)
o Mineralization (styles, intensity, mineralogy, quantification)
o Structures (description, Dip-Dip/Dip, size, width, mineralogy, counting)
• The geologist locates the start point of the channel using tape and compass from a reference
point previously surveyed with total station
• A photograph of each sample is taken and registered with the sampling information
• The geologist defines the interval length of the sample (minimum 0.5 m and maximum 2 m),
perpendicular to the mineralization trend and respecting the changes in lithology, alteration
and mineralization marking the limits of the samples with aerosol paint. The quality controls
are defined (Blanks, duplicates, reference materials) and their tickets and bags are marked
• The geology technicians delimit the channel using two parallel line guide marks separated
7 cm apart. Two cuts are made using a diamond saw following the parallel horizontal lines, at
an approximately depth of 3 cm along the line guides. To facilitate the collection of the sample,
a vertical cut is made with the diamond saw perpendicularly to the parallel line guides every 5
to 10 cm (Figure 9-7).
Source: CGM, 2019
Figure 9-7: Channel Sample Cut Using Electrical Saw
• The sample width and depth were designed to give a sample weight similar to a split HQ drill
core sample.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 89
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
• The surface is cleaned with water and a metallic brush and then the collection of the sample
is completed using hammer and chisel directly into the bag (canvas or plastic) where the
identification ticket had been introduced.
Source: CGM, 2019
Figure 9-8: Identification Ticket and Bags Used to Pack the Channel Sample
• Approximately 10 kg per 2 m of sample is collected.
• In selected samples a second channel is constructed above or below to collect a field
duplicate.
• Once the channel sample is taken a photograph is taken for record, which can also be used
to assess sampling quality.
• The geologist in charge of the QA/QC reviews the samples, photographs and inserts quality
controls as defined by the Company’s internal protocols which includes; duplicates, standards
and blanks.
• The collected samples are returned to surface by the Company geologist and packed in
batches of maximum 150 samples (minimum 20) including the controls for submission to the
laboratory. The bags with the samples are sent to an external commercial laboratory using
Company vehicles with a person who is responsible for the delivery of the shipment, and a
chain of custody maintained.
9.2.3 SRK Opinion of Quality
SRK reviewed the sampling locations of a large continuous exploration cross-cut during an
underground site visit and is satisfied that the sampling procedures used are in line with industry best
practice and no evidence of selective sampling of higher grade vein material was evident.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 90
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
In an underground operation, SRK recommends the use of routine sampling compared to selective
sampling as preferred to ensure the best confidence for the geological models, as it is just as important
to know where low grade exists for mine planning requirements.
Mr. Giovanny Ortiz of SRK completed a review of the mine geology grade control sampling in
September 2019 and February 2020. While SRK noted that the current procedures produced
reasonable samples, improvements in the procedure were recommended which included:
• By definition, sampling must be equi-probable and for this type of vein mineralization,
systematic sampling is used, taking samples every 2 m in channels perpendicular to the
direction of the vein.
• In each advance, sampling should be completed using consistent sampling procedure to limit
any potential sampling bias. Sample locations should be standardized and perpendicular to
the structure where possible. Sample lengths should be maintained where possible with
avoidance of multiple samples being taken in areas of potential high grades.
• The defined channels used for sample selection should be homogeneous in width and depth
in order to take all the components of the mineralization, avoiding the collection of a greater
quantity of softer material that may generate bias in the results of the sample towards the soft
material.
• The use of a diamond saw to make two cuts that delimit the channel as used by exploration is
preferred to manual sampling as it produces a more homogeneous sample, although the loss
of fine material must be avoided.
• The delimitation of the samples according to the geological contacts must always be respected
and the technicians must adhere with the sampling contacts set by the geologists.
• The weight of the sample should be a reflection of sample length, with the laboratory
procedures adjusted should additional splitting be required for sample sizes with greater
weight.
• To collect the rock sample, it is recommended to use a container that allows for cleaning to
avoid cross contamination. Direct packaging can also be done in the plastic bag, if it is possible
to capture the entire sample without sample loss.
• SRK recommends regular training of sampling assistants to keep protocols on track and to
raise awareness of the importance to CGM of good sampling methodology.
• In order to guarantee the quality of the results, SRK recommends that the mine geology
department implement a control program for quality of all chemical sample preparation and
analysis processes in the internal laboratory.
All CGM verification sample points were surveyed using either total station of theodolite. A total of
4,285 samples (over 6,699 m) have been taken over 1,431 channels. SRK has integrated these
channels into the database and treated them as horizontal drillholes, with samples cut to sufficient size
to relate to that of a diamond drillhole. SRK considers this approach to be acceptable and has used
this data in producing the resource estimates presented here.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 91
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
9.3 Significant Results and Interpretation
SRK has reviewed the sampling methods and sample quality for the Marmato Project and is satisfied
that the results are representative of the geological units seen and that acceptable minimal biases
have been identified. SRK has accepted the results from the channel sampling program as presented
for the definition of geological model and Mineral Resources at the Marmato Project.
In the updated database, SRK notes some channel samples from the mine have been limited to the
vein only and are not supported by other channels. In cases where this occurs SRK has selected
samples for use in the estimation process during the geological modelling stage. Using the
interpretation of veins and disseminated material surrounding the veins SRK has been able to account
for the vein sampling spatially. In areas with isolated grades or a lack of continuity, SRK assigns
geological coding to limit or remove the impact on the estimation process.
The impact of additional short samples that have been logged typically with the lithology “P1”, within
the larger indicator-based grade shells could potentially result in the over-estimation of grade and
therefore require further restriction. SRK tested a number of scenarios and has made additional
adjustments for the estimation procedures within the porphyry sampling by applying filters on the
information used during geological modelling and the estimation process. The adjustments have
resulted in a reduction of both tonnage and contained metal within this zone. SRK has discussed these
issues with the CGM geology team and will work on a method to improve the modelling of these
domains in future estimates.
SRK has reviewed the methods employed by the Company during the underground sampling of Zona
Baja which showed clearly marked sampling intervals and associated check sampling. It is SRK’s view
that the sampling intervals and density of samples are adequate for the definition of a compliant MRE.
SRK recommends the Company continue with the current underground sampling program on the lower
levels of the CGM mine as per the current exploration program.
There has been limited increase in the underground channel database between the PEA and PFS
geological models. A total of 272 new channels exist in the database all taken by the CGM geological
department. The total cumulative length of the channels is 796 m, but contains a combination of the
routine channel sampling in the veins which accounts for 262 channels ranging from 0.3 to 5.2 m, for
a total combined sampling length of 569.4 m. In addition to the routine vein channels, the mine has
conducted a series of channels (following exploration protocols), within the transitional areas of the
MDZ on level 21. These channel samples are taken from cross-cuts across the width of the
mineralization and range in length from 11.7 to 35.9 m, for a cumulative length of 226.6 m.
The results of the latest drilling have been compared to the geological mapping information to confirm
location of the veins, faults and potential transitional material with the MDZ (Figure 9-9).
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 92
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SRK, 2020
Figure 9-9: 2D Plan View of Sampling Data Versus Vein Interpretations, Showing New Sample Data Highlighted in Red, Versus Plan Section of Veins in Blue (Level 1250 M)
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 93
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
10 Drilling For the purpose of the Mineral Resources, the combined CGM and Gran Colombia database from all
licenses has been used inclusive of drilling and sampling information from Zona Alta (#CHG_081), and
Echandia (#RPP_357).
10.1 Type and Extent
The drillings performed vary in depth, inclination and direction depending on the objectives plotted in
the different drilling campaigns. The Company initially targeted a regular spacing of drilling of between
150 and 200 m for new mineralization targets, which are latter infilled to 50 to 75 m.
Drillholes, where regularly spaced, are inclined -60 and -75° predominantly to the southwest, with
occasional scissor holes towards the northeast. Fan drilling has been utilized both at surface and from
underground, which are also typically orientated towards the southwest, with a small number of less
extensive fans orientated towards the northeast.
In title #014-89m, different diamond drilling campaigns have been carried out with core recovery in
diameters from HQ to AW, the latter in rapid mineralization verification procedures adjacent to mining
areas; for HQ and NQ diameters are more specifically related to exploration-focused perforations.
A technical report completed by SRK on September 4, 2011, titled “A NI 43-101 Mineral Resource
Estimate on the Marmato Project, Colombia”, provides in-depth detail on the historic drilling programs
completed from surface.
Table 10-1: Summary of Drilling Completed by Company
Company Series Number of Holes Total (m)
Zona Alta
Compañía Minera de Caldas CMdC 205 46,377.8
Minerales Andinos de Occidente MAdO 146 45,095.0
Zona Alta Subtotal 351 91,472.9
Echandia
Colombia Gold CGD 20 5,933.4
Gran Colombia Resources CGD-GCL 75 11,184.7
Minerales Andinos de Occidente MAdO 88 37,588.0
Mineros Nacionales MNL 6 768.4
Echandia Subtotal 189 55,474.4
Zona Baja
Mineros Nacionales CNQ 47 14,873.0
Mineros Nacionales CNQ-MNL 25 1,803.4
Minera Phelps Dodge CNQ-PDG 6 696.0
Minerales Andinos de Occidente MAdO 108 38,967.3
Mineros Nacionales MNL 574 47,869.8
Gran Colombia Exploration CALDAS 57 27,788.6
Zona Baja Subtotal 817 131,997.9
Grand Total 1357 278,945.2
Source: SRK, 2020
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 94
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SRK, 2020
Figure 10-1: Location Map Showing Drillholes Completed at Marmato by Company
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 95
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SRK, 2020
Figure 10-2: 3D View of Sampling Data, Showing New Exploration Drilling Data Highlighted in Red and Mine Drilling in Purple (Looking North)
10.2 Procedures
All surface hole collars have been surveyed using a Differential Global Positioning System (DGPS)
and have been surveyed to a high degree of confidence in terms of the XY location. The Z locations
have been adjusted to the topography. Underground drilling collars have been surveyed by the mines
survey department and verified against existing development.
Drilling has been completed by various drilling contractors during the history of the project. While
different drilling contractors have been used over time the Company ensured that:
• A geologist is assigned to each drilling machine
• A trained technician was assigned to measure recovery and RQD measurements
• The transport of the drilling witnesses from the machine to the area of core shed is completed
by a Company employee
• Logging, core cutting and sampling is supervised by suitably trained employees
• Prior to sending samples to the laboratory, all sample bags and number strings were checked
for continuity and sample bag integrity
• All diamond cores were photographed as a routine documentation of samples
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 96
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
• Drill core was stored in locally constructed wooden core boxes with painted labels on the end
of each core box detailing box number, drillhole number and sampling intervals
Source: SRK, 2020
Figure 10-3: Core Photographs Before and After Making the Respective Cut and Sampling
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 97
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Once the initial transportation and documentation of the hole has been completed at the core shed,
the following processes are completed:
• Conduct a quick log of the geology (i.e. the rapid review of lithological contacts and the most
important information even with approximate depths based on the drill plugs)
• Documentation and measurement of recovery
• Complete a geotechnical log including lithology, recovery (%), RQD, fractures, Jn conditions
and weathering
• Complete a geological log including lithology, mineralization, alteration
• Definition sampling intervals (Minimum 50 cm; Maximum 200 cm)
• Mark the cutting line for core cutting
• Insertion of appropriate quality control standards
• Selection of samples, for petrographic, density and metallurgical testwork
10.2.1 Core Storage
CGM constructed a core storage facility at Marmato during 2010 (Figure 10-4), which acts as the main
exploration facility with logging and offices setup also located at the facility. The core facility has
approximate dimensions of 70 m wide and 90 m long; the capacity of the facility for the storage of the
drilling cores is approximately 350,000 m including the coarse and fine rejects of the samples sent to
the laboratory for geochemical analysis.
SRK has visited the core storage facility during multiple site visits and found the facility to be organized
and clean, with sufficient space for the ongoing exploration.
Source: SRK, 2019
Figure 10-4: Core Storage Facility at Marmato Constructed in 2010 and Current Status 2019
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 98
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
To confirm that no bias has been introduced, a test program was completed whereby samples of the
cuttings were taken from the core saw tray and sludge samples were taken from the sumps used to
settle out fine solids from the drill water. The settling tanks were installed as part of the environmental
management plan for drilling. The core intervals to which these samples correspond were recorded so
that the cuttings and sludge sample grades can be compared with the average grade for the interval.
10.2.2 Collar Surveys Surface
All surface drill hole collars have been surveyed using a DGPS and have been surveyed to a high
degree of confidence in terms of the XY location. Data has been provided to SRK in digital format
using UTM grid coordinates.
Drillhole collar elevations have been adjusted for errors based on projections on a digital terrain model
(dtm) surveys based on the Ikonos satellite imagery, which gives contour levels every 2 m. It is SRK’s
view that even given the extreme topography found at Marmato that the current procedures site the
collar locations with a sufficient degree of confidence.
10.2.3 Collar Surveys Underground
The collar for underground drillholes are defined using a differential GPS and total station measures.
The geologist adjusts the coordinates as required based on conditions underground. SRK notes that
in some cases the drilling is assumed to have occurred from a single location within an underground
drilling station but notes in reality there are likely adjustments for orientation and setup which have
occurred but not been accounted for in the final database. SRK does not consider these adjustments
to have a material impact on the estimation and modelling process.
Inside the mine, the topographic survey is used to verify the accuracy of the result of the calculations;
the adjustment of the points is performed by the Mine surveyors and the results of the measurements
are verified by a GIS Specialist.
10.2.4 Drilling Orientation
Down-hole directional surveys were conducted using a GyroSmart digital gyro tool, manufactured by
Flexit Navigation A.B. (Flexit) and Imego A.B. (Imego) of Sweden, which was purchased from Ingetrol.
Prior to the purchase of this instrument in 2007, down-hole directional surveys were conducted using
a Flexit Multishot tool supplied by Terramundo.
During the initial exploration, drillholes were regularly spaced and orientated -60 and -75°
predominantly to the SW, with occasional scissor holes towards the NE. More recently with the focus
on the MDZ, the Company has used fan drilling from underground adits, which are also typically
orientated towards the SW, with a smaller number of less extensive fans orientated towards the NE.
Drillholes have been drilled from four purpose-built underground drilling stations with two contractor
rigs being used to date. Three of the drilling stations are located on Level 20 with a single station
established on Level 21. Drillholes have been drilled in a fan pattern and dips ranging from -20 to -75°
predominantly to the southwest (ranging from 151º to 255º). Holes targeting the upper portions of the
MDZ have shallower angles while the deeper targeted holes longer (more than 400 m) and steeper
(Figure 10-5 and Figure 10-6).
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 99
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
In addition to the drilling completed by the CGM exploration team (MT-IU series), the current operating
mine has also completed routine exploration drilling ahead of mining. The routine exploration is
typically completed using horizontal drilling from the existing drives to aid in the mapping and
delineation of the known veins prior to mining.
Source: SRK, 2020
Figure 10-5: Plan Showing Primary Drilling Orientation to the South and Southwest Relative to the Main Mineralization Orientation at Depth
LegendVeinsFaultsHistorical DrillingNew Drilling (PEA and PFS)
Primary orientation of deep mineralization
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 100
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SRK, 2019
Figure 10-6: Cross Section (Orientated Looking Northeast), Showing Orientation of Drilling Relative to the Deep Mineralization, and Horizontal Drilling in the Current Operation
LegendVeinsFaultsHistorical DrillingNew Drilling
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 101
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
10.3 Interpretation and Relevant Results
The updated drilling database indicates that the veins typically range between 0.5 and 5 m wide and
extend for 250 to 1,000 m along strike, and 150 to 750 m down dip. This is supported by underground
mapping and mining which has confirmed that individual vein structures have good geological
continuity and can extend for 100 to 800 m along strike and 100 to at least 350 m down dip. Between
2017 and 2020, CGM has worked on updating the quantity of the underground channel sampling
captured in the database, which has increased the information available to model the vein domains in
greater detail, which has be integrated with detailed level mapping of the veins.
The broad zones of veinlet mineralization in the porphyry domain modelled initially by SRK in 2017
typically varied from 10 to 230 m wide, reaching up to 340 m wide in areas of significant veinlet
accumulation, while extending with good geological continuity for between 200 m and approximately
950 m along strike and between 100 and 900 m down dip. SRK has updated these domains during
the 2019 geological modelling process using more discrete zones and application of an indicator grade
shell approach using a 0.5 g/t Au CoG.
At depth within the central portion of the deposit, SRK has noted a zone of elevated grades which has
been referred to as the higher grade MDZ (more than 2 g/t Au). This zone is indicated to be continuous
along strike for approximately 500 m and has a confirmed down dip extent that reaches up to 800 m,
with a thickness that varies between 35 and 150 m. It is possible that the main MDZ mineralization is
bounded within a series of faults but limited drilling at the edges of the deposit make confirmation
difficult to assess at this stage. SRK notes that the sampling lengths are not perpendicular to the
defined steeply dipping structures but notes that access to ideal drilling locations is limited to current
underground drilling stations. Drilling of the deeper portions of the deposit will not produce ideal
intersections from the current stations, without considerations of directional drilling. The Company is
currently investigating the option to use directional drilling in future drilling programs.
In the QP’s opinion the drilling completed to date has produced reasonable intersection angles to
define the mineralization in three dimensions. In the case of intersections in the latest round of drilling
between the PEA and PFS, which identified additional mineralization in the hangingwall, SRK has
limited the spatial extents of the geological interpretations until further infill drilling establish continuity.
SRK considers the hangingwall mineralization to represent upside to the current model and additional
exploration is recommended prior to mining to ensure underground infrastructure is designed outside
of the mineralization.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 102
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
11 Sample Preparation, Analysis and Security
11.1 Security Measures
The Chain of Custody procedures for sample security were set up for the Company by Dr. Stewart
Redwood in December 2005 (with the latest update in August 2009). During the initial exploration
(2005 to 2006), sample numbers were created in the field based on a combination of the sample
location, sample type and sample point, with descriptions of each sample noted in a field book and
later transcribed. While providing useful information, the decision was taken in 2006 to change to a
sequential numbering system based on preprinted sample tickets. In both cases the sample numbers
have been transcribed on the sample bags to avoid errors (e.g. lost tickets).
At the drill rig, the drilling contractors are responsible for removing the core from the core barrel (using
manual methods) and placing the core in prepared core trays (3 m length). The core is initially cleaned
to remove drilling additives, but attempts are made to ensure fine material is not lost. Once completed,
the core tray is closed with a wooden lid, hammered shut, and CGM geologists or technicians take
possession. The drill core is then transported to the core shed for selection of sampling intervals and
initial sample preparation. On receipt at the core shed, CGM geologists and technicians follow the
logging and sampling procedures laid out in Section 11.2. Once completed and the half core has been
photographed, the core boxes are again sealed and then transported to the onsite core storage facility.
The core storage facility is within a secure area with a single access gate controlled by a 24-hour
security guard.
In preparation for shipment, samples were packed into nylon rice sacks with approximately five
samples per rice sack. The shipments were accompanied with the laboratory submittal forms and were
transported to Medellín. Samples were accumulated at sample dispatch (in the case of historical holes
this was a warehouse in Medellín) until a hole was completed. Drillholes were only submitted in their
entirety once sampling was completed. The samples were transported by CGM employees to the
preparation facilities. Upon reception at the sample preparation facility, the laboratory company
checked that the samples received matched the work order and signed that it had accepted the
samples.
Once the sample preparation was completed, the laboratory dispatched the sample pulps by courier
to selected overseas laboratories. The laboratories were instructed to retain excess sample pulps after
analysis which can be used in the event that check analyses are requested by CGM.
The coarse sample rejects and sample pulps from the preparation facilities in Medellín were picked up
by CGM technicians during routine sample shipments to the preparation facilities. The coarse rejects
and pulps were returned to the CGM core shed at Marmato for long-term storage.
11.2 Sample Preparation for Analysis
11.2.1 Historical Sample Preparation (Pre 2010)
Prior to the opening of the Inspectorate and SGS sample preparation laboratories in Medellín in
August 2006 and November 2007, respectively, there were no internationally certified sample
preparation laboratories for mineral exploration in Colombia. At the start of exploration work by CGM,
all samples had to be sent to other countries to be prepared and analyzed. Entire rock samples were
sent by air to Inspectorate in Sparks, Nevada (ISO 9001:2000 and ISO 9002:1994 certified) for
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 103
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
preparation and analysis, or to ALS Chemex in Quito, Ecuador (ISO 9001:2000 and ISO 17025:2005
certified) for preparation, with analysis by ALS Chemex in Lima. ALS Chemex in Reno, Nevada was
also used for some check analyses.
The Sparks analytical laboratory was used until late 2007; however, considerable QA/QC problems
were experienced during 2007 as well as long delays in turnaround time and from late 2007 to 2010
the Lima analytical laboratory was used. The analyses from Inspectorate’s Sparks laboratory which
failed QA/QC were repeated. Other samples analyzed initially at Inspectorate’s Sparks laboratory were
re-analyzed at Inspectorate’s Lima, Peru laboratory. Only sample batches that passed QA/QC were
accepted and stored in the final database.
The secondary laboratory used was SGS (ISO 9001 certified) at a sample preparation facility in
Medellín and at their analytical laboratory run by SGS del Perú S.A.C., El Callao, Lima. Inspectorate
is used as the laboratory for check on any SGS submissions and replicate assays of samples analyzed
initially at SGS del Peru S.A.C in Callao, Lima, Peru.
The sample preparation at the Inspectorate laboratory in Medellín consisted of drying the entire sample
and crushing it to more than 70% passing -10 mesh by jaw crusher and roll mill. This was later changed
to more than 85% passing -10 mesh using a TM Terminator Jaw Crusher. A split of 250 to 500 grams
(g) was then obtained using a Jones splitter and was pulverized to more than 80% passing -150 mesh
with Labtech LM2 pulverizing ring mill. Tested barren silica sand was used as a clean wash between
each sample in pulverization.
The sample preparation procedures at the SGS laboratory in Medellín and SGS Colombia S.A. facility
in Barranquilla, comprised drying the sample, crushing the entire sample in two stages to -6 mm and
-2 mm by jaw crusher (more than 95% passing), riffle splitting the sample to 250 to 500 g, and
pulverizing the split to more than 95% passing -140 mesh in 800 cubic centimeters (cm3) chrome steel
bowls in a Labtech LM2 pulverizing ring mill (preparation code 321).
The sample preparation method at the Inspectorate laboratory in Sparks, Nevada was to dry and crush
the entire sample to more than 85% passing -10 mesh by TM Terminator Jaw Crusher, spilt 250 g to
300 g using a Jones splitter and pulverize this to more than 90% passing -150 mesh with a Labtech
LM2 pulverizing ring mill. Tested barren silica sand was used as a clean wash between each sample
in pulverization (rock chip 0 to 10 pound (lb) method).
The sample preparation procedure at the ALS Chemex laboratory in Quito was to log the sample into
the tracking system, weigh, dry, crush the entire sample to more than 70% passing 2 mm, split off up
to 1.5 kg and then pulverize the split to more than 85% passing 75 microns (code PREP-32).
11.2.2 Sample Preparation Mine Sampling (2010 – 2017)
The sample preparation method at the internal CGM mine laboratory comprised of drying the sample,
crushing the entire sample to -5 mm by jaw crusher (more than 95% passing), riffle splitting a sub-
sample of 200 to 300 g and pulverizing the sub-sample in a disc mill to more than 80% passing -200
mesh. SRK visited the facility during the 2017 site inspection and noted new equipment had been
purchased and was not currently in use at the time of visit (Figure 11-1). The new equipment was
consistent with those used at the third-party commercial laboratory. One issue noted during the site
inspection is the stacking of sample trays (full) prior to pulverizing, which SRK does not consider to be
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 104
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
best practice as this could result in cross contamination of samples. Ideally sample should be stacked
on individual trays on a trolley as shown in Figure 11-1.
Source: SRK, 2017
Figure 11-1: Sample Preparation at Mine Laboratory Showing New Equipment (Crusher and Pulverizer)
Since January 2010, the primary laboratory used for the exploration samples in the drill and
underground sampling programs was ACME Laboratories for sample preparation in Medellín, and
analytical laboratories in Sparks, Nevada, USA and Lima, Peru. The 2011 drill program utilized the
ACME sample preparation laboratory in Medellín and the ACME assay laboratory in Santiago, Chile.
In addition, the SGS laboratory in Lima, Peru was used as a check laboratory.
SRK visited the ACME sample preparation facilities on November 4, 2010. The sample preparation
method at ACME, Medellín was to dry the sample in large controlled and crush the entire sample to
more than 85% passing -10 mesh by TM Terminator Jaw Crusher (Figure 11-2).
The sample is then spilt to 250 to 300 g using a Jones splitter and pulverized to more than 90% passing
-150 (75 µm) mesh with a Labtech LM2 pulverizing ring mill.
Tested barren silica sand was used as a clean wash between each sample in the crushing and
pulverization stages (rock chip 0 to 10 lb method).
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 105
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Showing: (a) Terminator Jaw Crusher (b) Jones Riffle Splitter (c) LM2 Mill (d) Final Bar-Coded Sample Pulp Source: SRK, 2010
Figure 11-2: Sample Preparation Facilities at ACME Laboratories in Medellín
11.2.3 Sample Preparation
Since 2017, CGM has used SGS Laboratories in Medellin is the primary laboratory for both sample
preparation and analyzing all exploration drilling core samples. All CGM mine drilling has undergone
preparation and analysis at ALS Laboratory, to ensure sample quality. CGM has incorporated routine
check analysis on each laboratory with secondary assays at ALS for the SGS submissions and vice-
versa.
(a) (b)
(c)
(d)
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 106
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Samples sent to SGS were prepared using method PRP93, which involved drying in oven at 100°C
followed by jaw crushing. The sample was crushed to 90% passing -10 mesh size. The crusher was
cleaned with compressed air between samples. A 250 g split, using a Jones splitter, was pulverized to
95% passing -140 mesh using a ring and puck pulverizer.
11.3 Sample Analysis
The ACME laboratory in Santiago analyzed the samples (from the 2010 to 2012 drill programs) for
gold by fire assay (FA) with atomic absorption spectrophotometer (AAS) finish. Samples over 10 g/t
Au were assayed by FA with gravimetric finish. Silver was assayed by aqua regia digestion and AAS
finish. Silver samples above 100 g/t were assayed by FA with gravimetric finish.
The historical samples by Conquistador (one of the previous owners) have been assayed by Barringer
for gold by FA with atomic absorption (AA) finish and checks by gravimetric finish for some high grade
samples. Silver was determined by acid digestion with AA finish.
A detailed description of the sample analytical procedure undertaken for the 2011 SRK MRE (January
2011) and is provided, given the incorporation of these samples in to the current estimate:
The Inspectorate laboratory in Lima analyzed the samples for gold by FA with an AA finish (detection
limits 0.005 parts per million [ppm] to 3 ppm, method FA/AAS). Silver was analyzed by aqua regia
digestion and AA finish (method AA, detection limits 0.2 to 200 ppm). Over-limit gold assays (above
3,000 parts per billion [ppb] or 3 ppm) were repeated by FA (1 assay ton, 29.2 g) with gravimetric finish
(method Au FA/GRAV). Samples above a 200 g/t silver upper limit of detection were repeated by FA
(1 assay ton, 29.2 g) with gravimetric finish (method Ag FA/GRAV). Samples were analyzed for
multiple elements by aqua regia digestion and inductively coupled plasma (ICP) finish (32 Element
ICP Package for Ag, Al*, As, Ba*, Bi, Ca*, Cd, Co, Cr*, Cu, Fe, Hg, K*, La*, Mg*, Mn, Mo, Na*, Ni, P,
Pb, S*, Sb*, Se, Sn*, Sr*, Te*, Ti, Tl*, V, W, Zn). Inspectorate states that for elements marked * the
digestion is partial in aqua regia in most silicate matrices and the analysis is partial. Over-limit zinc and
lead analyses (more than 10,000 ppm) were rerun by aqua regia digestion and AA. Multi-element
analyses were not carried out on the final batches of samples.
The Inspectorate laboratory in Sparks, Nevada analyzed samples for gold and silver by FA with an AA
finish for gold (detection limits 2 ppb to 3,000 ppb) and AA finish for silver (detection limits 0.1 ppm to
200 ppm) (method Au, Ag FA/AA/AAS). Over-limit gold assays (above 3,000 ppb or 3 g/t) were
repeated by FA with gravimetric finish (method Au FA/GRAV). Samples above a 200 ppm silver upper
limit of detection were repeated by FA with gravimetric finish (method Ag FA/GRAV). Samples were
analyzed for multi-elements by aqua regia digestion and ICP finish (30 Element ICP Package for Ag,
Al*, As, B*, Ba*, Bi, Ca*, Cd, Co, Cr*, Cu, Fe, Hg, K*, La*, Mg*, Mn, Mo, Na, Ni, P, Pb, Sb*, Se, Sr*,
Ti, Tl*, V, W, Zn). Inspectorate states that for elements marked * the digestion is partial in aqua regia
in most silicate matrices and the analysis is partial. Over-limit zinc and lead analyses (more than
10,000 ppm) were rerun by aqua regia digestion and AA.
SGS del Perú S.A.C. analyzed samples for gold by FA (30 g sample) with an AA finish (code FAA313;
detection limits 0.005 ppm to 10 ppm), and for silver with an aqua regia digestion and an AAS finish
(code AAS12CP), or three acid digestion with AAS finish (code AAS42C); detection limits in both are
0.3 ppm to 500 ppm). Multi-element geochemical analyses were done by two different methods. One
method (ICM40B) uses a four acid digestion and both ICP-AES and ICP-MS for 50 elements (Ag, Al,
As, Ba*, Be*, Bi, Ca*, Cd, Ce, Cr*, Co, Cs, Cu, Fe*, Ga*, Ge*, Hf*, In*, K*, La*, Li*, Lu*, Mg*, Mn*, Mo,
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 107
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Na*, Nb*, Ni*, P*, Pb, Rb*, S*, Sb, Sc*, Se, Sn*, Sr*, Ta*, Tb, Te*, Th*, Ti*, Tl*, U*, V*, W*, Y*, Yb*,
Zn*, Zr*), elements marked * the digestion is partial.
The second method (ICP12B) uses a two acid (HNO3 and HCl) digestion and both ICP-AES and ICP-
MS for 38 elements (Ag, Al, As, Ba*, Be*, Bi, Ca*, Cd, Co, Cr*, Cu, Fe*, Ga*, Hg, K*, La*, Mg*, Mn*,
Mo, Na*, Nb*, Ni*, P*, Pb, S*, Sb, Sc*, Sn*, Sr*, Ti*, Tl*, V*, W*, Y*, Zn*, Zr*), elements marked * the
digestion is partial. SGS indicates that the analysis is partial for elements marked * and depends on
the mineralogy. Over limit gold values were repeated by FA with a gravimetric finish (method FAG303)
and a lower limit of detection of 0.02 g/t. Silver grades above 100 ppm and zinc grades above 1% were
repeated by four acid digestion and AA (method AAS41B). Gold and silver for some samples was by
FA with gravimetric finish on 30 g (method FAG323 with lower limit of detection of 0.03 g/t Au and 0.03
g/t Ag).
Since 2017, Caldas has used SGS Laboratories in Medellin as the primary laboratory for both sample
preparation and analyzing all exploration drilling core samples. Samples have been analyzed at each
laboratory for gold and silver by FA. At SGS, the assaying using an Au 30 g AAS (method FAA313).
All CGM mine drilling have undergone preparation and analysis at ALS Laboratory, to ensure sample
quality. CGM has incorporated routine check analysis on each laboratory with secondary assays at
ALS for the SGS submissions and vice-versa.
The CGM channel samples have been assayed at an onsite internal mine laboratory for Au and Ag by
FA with gravimetric finish. SRK reviewed the laboratory and noted some areas of improvement relating
to the state of the equipment. The mine has recently purchased new sample preparation equipment,
which should result in improved assay quality. SRK recommends CGM complete routine check
analysis between the mine laboratory and an independent commercial laboratory in Medellín. SRK
recommends that all exploration samples are kept clear of the mine laboratory to avoid any potential
contamination.
11.4 Quality Assurance/Quality Control Procedures
SRK completed a detailed review of the QA/QC procedures and results as part of the 2012 MRE.
Limited drilling was completed between 2012 and 2017, and since 2018 to early 2020 the drilling was
increased to explore the mineralization at depth. The results are summarized in the current report.
The routine QA/QC program at Marmato comprises certified standard reference materials (CRM),
quartz blanks, preparation duplicates (PD), coarse duplicates (CD), field duplicates (FD) and check
and replicate assays. The CRM, quartz sand blanks and duplicate samples make up the portion of the
QA/QC program which provides ongoing monitoring of the geochemical laboratories. The check assay
and replicate assay samples are submitted at longer time intervals (less frequently) and provide a
secondary control on the accuracy of the geochemical data.
Sampling protocols suggest the following submission rates:
• For the CRM, five random numbers are generated between 1 and 100
• For the FD samples, two random numbers are generated between 1 and 100
• For the PD samples, two random numbers are generated between 1 and 100
• In contrast, the blanks are inserted at points within the sample stream where, based on the
geology, the geologist believes that there is a high likelihood of significant mineralization, and
therefore potential for contamination
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 108
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
CGM employed a database administrator for the QA/QC program at Marmato during this period. SRK
held discussions with the database administrator during the site visit to review how the data was
captured.
SRK has been supplied with a complete QA/QC assay database for the Project in separate excel files
which summarize the submissions in 2019 and 2020 (up to borehole SMT20-018). Within the 2018 to
2020 exploration period when the majority of the drilling has been completed by CGM, a total of 946
certified standards, 742 blanks and 1,096 duplicates, representing approximately 14% of total routine
sample submissions for the CGM drilling programs at Marmato to SGS have been completed.
Additionally, CGM has a total of 133 certified standards, 90 blanks and 87 duplicates, representing
approximately 18% of the total sample routine submissions for the CGM drilling programs at Marmato
to ALS. In addition to the duplicates a series of re-assays and check assays have been completed
using alternative laboratories (SGS vs ALS). In 2018, a total of 190 assays along with the associated
QA/QC were re-assayed from SGS submissions and 42 re-assays from ALS submissions. In 2019, a
total of 981 and 77 re-assays have been selected from SGS and ALS submissions respectively. In
2020, a total of 105 re-assays have been selected to date from SGS. SRK considers the level of
QA/QC submissions to be of acceptable levels for the current stage of the Project.
A summary of the breakdown per sample type and laboratory are shown in Table 11-1 (2018),
Table 11-2 (2019) and Table 11-3 (2020).
Table 11-1: Summary Of QA/QC Sample Submissions During 2018 Submissions To SGS And ALS Laboratories
Marmato Exploration
Original Shipments
Sent Shipments Received Analysis QA/QC
Laboratory Shipments Samples Shipments Samples Standard Blanks Duplicates
SGS 29 4530 29 4530 224 178 275
ALS 10 909 10 909 46 36 36
Re-Analysis Shipments
Sent Shipments Received Analysis QA/QC
Laboratory Shipments Samples Shipments Samples Standard Blanks Duplicates
SGS 6 203 6 203 12 0 1
ALS 3 46 3 46 3 0 1
Source: CGM, 2018
Table 11-2: Summary Of QA/QC Sample Submissions During 2019 Submissions To SGS And ALS Laboratories
Marmato Exploration
Original Shipments
Sent Shipments Received Analysis QA/QC
Laboratory Shipments Samples Shipments Samples Standard Blanks Duplicates
SGS 105 14,295 105 14,295 661 514 747
ALS 11 804 11 804 87 54 51
Re-Analysis Shipments
Sent Shipments Received Analysis QA/QC
Laboratory Shipments Samples Shipments Samples Standard Blanks Duplicates
SGS 18 1,086 18 1,086 58 0 47
ALS 6 86 6 86 6 1 2
Source: CGM, 2020
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 109
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 11-3: Summary Of QA/QC Sample Submissions During 2020 Submissions To SGS Laboratory (Up to SMT20-018)
Marmato Exploration
Original Shipments
Sent Shipments Received Analysis QA/QC
Laboratory Shipments Samples Shipments Samples Standard Blanks Duplicates
SGS 12 1225 12 1225 61 50 74
Re-Analysis Shipments
Sent Shipments Received Analysis QA/QC
Laboratory Shipments Samples Shipments Samples Standard Blanks Duplicates
SGS 4 105 1 15 58 0 47
Source: CGM, 2020
11.4.1 Standards
In the 2019 to 2020 program, 946 Certified Reference Material (Standards) were submitted during
routine submissions to SGS and 133 with ALS submissions.
A summary of the standard codes is shown in Table 11-4. In the submissions to SGS, SRK concluded
the majority of standards had a greater number of overestimations than underestimations. The
discrepancies noted are likely due to occasional laboratory issues, however this has not resulted in a
material bias overall.
SRK has reviewed the CRM results of the 2019 to 2020 program results provided by CGM and is
satisfied with the results and the failures management procedure, which give sufficient confidence in
the assays for these to be used to derive a MRE. CGM has utilized CRM from Geostats Pty Ltd.,
Rocklabs, and OREAS. In 2018-20, 24 different CRM’s were inserted into the sample stream.
Table 11-4: Summary of CRM’s Submitted During Routine Assay Submissions
STM_NAME Std Value SD1Low SD1High SD2Low SD2High SD3Low SD3High
G310-6 0.65 0.61 0.69 0.57 0.73 0.53 0.77
G312-4 5.3 5.08 5.52 4.86 5.74 4.64 5.96
G313-1 1 0.95 1.05 0.9 1.1 0.85 1.15
G313-2 2.04 1.97 2.11 1.9 2.18 1.83 2.25
G314-1 0.75 0.71 0.79 0.67 0.83 0.63 0.87
G314-5 5.29 5.12 5.46 4.95 5.63 4.78 5.8
G315-2 0.98 0.94 1.02 0.9 1.06 0.86 1.1
G914-6 3.21 3.09 3.33 2.97 3.45 2.85 3.57
G914-9 16.77 16.29 17.25 15.81 17.73 15.33 18.21
G915-5 17.95 17.09 18.81 16.23 19.67 15.37 20.53
G915-6 0.67 0.63 0.71 0.59 0.75 0.55 0.79
OREAS-15Pc 1.61 1.571 1.649 1.532 1.688 1.493 1.727
OREAS-60P 2.6 2.56 2.64 2.52 2.68 2.48 2.72
OREAS-62Pa 9.64 9.56 9.72 9.48 9.8 9.4 9.88
OREAS-67A 2.238 2.142 2.334 2.046 2.43 1.95 2.526
SH35 1.323 1.279 1.367 1.235 1.411 1.191 1.455
SH82 1.333 1.306 1.36 1.279 1.387 1.252 1.414
SJ80 2.656 2.599 2.713 2.542 2.77 2.485 2.827
SK94 3.899 3.815 3.983 3.731 4.067 3.647 4.151
SL76 5.96 5.768 6.152 5.576 6.344 5.384 6.536
SN91 8.679 8.485 8.873 8.291 9.067 8.097 9.261
SP73 18.17 17.75 18.59 17.33 19.01 16.91 19.43
SQ88 39.723 38.776 40.67 37.829 41.617 36.882 42.564
OREAS 62c 8.79 8.58 8.79 8.37 9.21 8.16 9.42
Source: SRK, 2020
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 110
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SRK, 2020
Figure 11-3: Summary of CRM Submissions to SGS In 2019/2020 Program
Source: SRK, 2020
Figure 11-4: Summary of CRM Submissions to ALS In 2019 Program
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 111
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: CGM, 2020
Figure 11-5: Example of Timeline Review Of CRM G914-6 (2019) and G315-2 (2020) Submissions
11.4.2 Blanks
Blanks are inserted at points within the sample stream where, based on the geology, the geologist
believes that there is a high likelihood of significant or high-grade mineralization and therefore potential
for contamination. Coarse and Fine blank samples are submitted (812 in total) to both SGS and ALS
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 112
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
between 2018 and early 2020 (Figure 11-6 to Figure 11-9) the results have been reviewed to check
for any potential evidence of contamination. SRK comments that no evidence has been noted with
limited samples reporting above a value of 0.025 g/t Au.
Source: SRK, 2020
Figure 11-6: SGS and ALS Coarse Blank Submissions 2019
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 113
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SRK, 2020
Figure 11-7: SGS Coarse Blank Submissions 2020
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 114
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SRK, 2020
Figure 11-8: SGS and ALS Fine Blank Submissions 2019
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 115
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SRK, 2020
Figure 11-9: SGS Fine Blank Submissions 2020
11.4.3 Duplicates
The Company has submitted three different types of duplicates during the routine sample submissions.
The three different types have been defined as field duplicates, coarse duplicates and pulp duplicates.
The field duplicates have only been submitted with the exploration drilling submitted to SGS with no
duplicates in the mine drilling programs to ALS. A total of 281 field duplicates have been analyzed
between 2019 and early 2020. The difference in the mean grades from the two data populations is 6%
higher in the duplicate dataset, which returned 1.25 g/t and 1.18 g/t Au respectively. A summary of the
results is shown in Table 11-5 and Figure 11-10. Many samples are outside of 30% of acceptability,
reflecting the heterogeneity of the mineralization but suggest as well that it is appropriate to review the
sampling procedures and carry out some additional training of the geology helpers.
Table 11-5: Summary Statistics for Field Duplicates (2019-2020)
Original Au (g/t) Duplicate Au (g/t)
Mean 1.18 1.25
Standard Deviation 1.79 2.48
Sample Variance 3.21 6.14
Range 10.84 21.46
Minimum 0.006 0.006
Maximum 10.85 21.47
Count 271 271
Source: SRK, 2020
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 116
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SRK, 2020
Figure 11-10: Summary of Field Duplicate 2019-2020
The coarse duplicates have been submitted in both exploration and mine drilling programs submitted
to SGS and ALS. A total of 274 coarse duplicates have been analyzed at SGS and 24 at ALS between
2019 and 2020. The difference in the mean grades from the two data populations is 5.6% higher in the
duplicate dataset, which returned 1.48 g/t and 1.58 g/t Au respectively at SGS. This is skewed by two
high-grade samples, which once removed reduces the difference to 1% in the mean grades. The
difference in the mean grades from the two data populations is 3.4% lower in the duplicate dataset,
which returned 2.39 g/t and 2.31 g/t Au respectively at ALS. A summary of the results is shown in
Table 11-6 and Figure 11-11. The correlation coefficient in each case is greater than R2> 0.9, which
indicates a strong correlation between the original and duplicate assays. Only a few samples are
outside of the acceptability range of 20% in the two set of samples.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 117
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 11-6: Summary Statistics for Coarse Duplicates to SGS and ALS Submissions (Au g/t), 2019-2020
SGS Submissions ALS Submissions
Original Au (g/t) Duplicate Au (g/t) Original Au (g/t) Duplicate Au (g/t)
Mean 1.48 1.56 2.39 2.31
Standard Deviation 3.54 3.95 2.43 2.18
Sample Variance 12.56 15.58 5.92 4.75
Range 47.60 45.72 9.23 7.83
Minimum 0.003 0.003 0.036 0.081
Maximum 47.60 45.72 9.27 7.91
Count 274 274 24 24
Source: SRK, 2019
Source: SRK, 2020
Figure 11-11: Summary of Coarse Duplicate Submissions to SGS (left) and ALS (right) for 2019-2020
The pulp duplicates have been submitted in both exploration and mine drilling programs submitted to
SGS and ALS. A total of 276 pulp duplicates have been analyzed at SGS and 27 at ALS between
2019 and 2020. The difference in the mean grades from the two data populations is 0.3% lower in the
duplicate dataset, which returned 1.332 g/t and 1.329 g/t Au respectively at SGS. The difference in the
mean grades from the two data populations is 5% lower in the duplicate dataset, which returned 1.39
g/t and 1.32 g/t Au respectively at ALS. A summary of the results is shown in Table 11-7 and Figure
11-12. It is observed that a high percentage of sample duplicates in ALS are not accomplishing the
acceptability range of 10%, that is an aspect to review with the laboratory.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 118
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 11-7: Summary Statistics for Coarse Duplicates to SGS and ALS Submissions (Au g/t), 2019-2020
SGS Submissions ALS Submissions
Original Au (g/t) Duplicate Au (g/t) Original Au (g/t) Duplicate Au (g/t)
Mean 1.332 1.329 1.39 1.32
Standard Deviation 2.59 2.50 2.19 2.00
Sample Variance 6.70 6.24 4.79 4.00
Range 25.55 22.51 9.52 9.13
Minimum 0.003 0.003 0.087 0.068
Maximum 25.55 22.51 9.61 9.20
Count 276 276 27 27
Source: SRK, 2020
Source: SRK, 2020
Figure 11-12: Summary of Pulp Duplicate Submissions to SGS (left) and ALS (right), 2019 - 2020
11.4.4 Actions/Reassays
The Company continued the reassay programs on the 2019 and 2020 submissions, respectively.
These represent resubmission of samples to a secondary laboratory (SGS to ALS and vice-versa).
From 2019 to 2020, a total of 1,076 sample pulps were reanalyzed (including reference materials)
which returned similar values across all grade ranges.
The difference in the mean grades from the two data populations is 0.2 % higher in the reassay dataset,
which returned 1.809 g/t and 1.812 g/t Au respectively in the original and reassays. The correlation
coefficient was R2>0.95, which is considered an indication of no bias during this period at SGS. A
number of points are outside of the 10% acceptance range that is an aspect to review with the lab. A
summary of the results are shown in Table 11-8 and Figure 11-13.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 119
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 11-8: Summary Statistics for 2019 Reassays Program to SGS vs ALS Submissions (Au g/t)
SGS Submissions (Primary)
Original Au (g/t) Duplicate Au (g/t)
Mean 1.809 1.812
Standard Deviation 3.00 3.14
Sample Variance 8.98 9.88
Range 45.13 47.33
Minimum 0.003 0.003
Maximum 45.13 47.33
Count 1,076 1,076
Source: SRK, 2020
Source: SRK, 2020
Figure 11-13: Summary of 2019-2020 Reassay (Secondary Laboratory)
11.4.5 Check Analysis Results
In addition to the re-assay program CGM also completed a check analysis on pulps and reject material
on a quarterly basis. From 2019 to 2020, a total of 249 sample pulp and rejects were reanalyzed from
SGS samples which returned similar values across all grade ranges.
The difference in the mean grades from check pulps is 4.4% lower in the check dataset, which returned
3.33 g/t and 3.19 g/t Au respectively in the original and check assays. Both results return very similar
high-grades (44.67 g/t Au versus 45.8 g/t Au), and the correlation coefficient was R2>0.71, which
shows slight bias towards the original pulps results. A summary of the results is shown in Figure 11-14.
It is noted that a number of points are outside of the 10% acceptance range, which is an aspect to
review with the laboratory. After completing this analysis SRK does not consider it to be material during
this time period.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 120
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
In comparison the difference in the mean grades from rejects is 7.9% lower in the check dataset, which
returned 3.33 g/t and 3.07 g/t Au respectively in the original and check assays. SRK notes that the
correlation coefficient is improved within the reject check analysis with R2>0.86, showing a slight bias
towards the original pulp values. A summary of the results is shown in Figure 11-15.
It is noted that for the pulps and rejects that a number of points are outside of the 10% and 20%
acceptance ranges, which is an aspect to review with the laboratory. After completing this analysis,
SRK does not consider it to be material during this time period.
Source: Gran Colombia, 2020
Figure 11-14: Summary of Check Assays Completed on Pulp Material (Quarterly Checks), Scatter Plot (Left) and Mean vs Relative Difference Plot (Right)
Source: SRK, 2020
Figure 11-15: Summary of Check Assays Completed on Reject Material (Quarterly Checks), Scatter Plot (Left) and Mean vs Relative Difference Plot (Right)
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 121
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
11.5 Opinion on Adequacy
It is the opinion of the QP that the frequency of QA/QC sample inserted in the 2018 and 2020 campaign
is at an acceptable rate as stipulated in the Company’s internal guidelines (approximately 14%).
In general, it is the opinion of SRK that the results of the QA/QC analysis display a reasonably good
correlation to the original assays and are acceptable for use in defining compliant MRE.
In the opinion of the QP, the sampling preparation, security and analytical procedures used by CGM
are consistent with generally accepted industry best practices and are therefore adequate.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 122
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
12 Data Verification
12.1 Procedures
12.1.1 Verifications by CGM
CGM has completed a number of verification sampling programs during the history of the Marmato
Project. The work completed has ensured sample integrity and allowed SRK to have confidence to
use the combined historical and CGM data as supplied by the Company. The work completed by CGM
can be sub-divided into the validation and verification of the on-going exploration drilling programs,
and the validation of underground channel sampling from the operating mine.
CGM employs a Database & GIS Manager who is responsible for tracking the samples through the
laboratory. The Sample Order Form is given to the Database Manager. A Microsoft® Excel
spreadsheet is used to track Company reference number, lab order number, date of delivery to lab,
date of receipt of assays by email, date of receipt of certificate and date of receipt of invoice.
The Database & GIS Manager is responsible for receiving the assay results and importing these into
the database. This is the only person with authority to do this in order to maintain integrity and quality
control of the database.
On receipt of each batch of assays for the exploration drilling, the QA/QC samples are checked to
accept or reject the batch. If there is a problem the Chief Geologist is notified and he requests that the
laboratory identify and solve the problem, if possible, or carry out re-analysis, as necessary. If re-assay
is required, either the whole batch or the sample tray between the good QC samples on either side is
re-analyzed. Microsoft® Excel or Access spreadsheets and graphs are used to check QC results and
update these with each batch so that the whole program is monitored progressively.
The laboratory also carries out its own internal QA/QC samples and the results for these are requested
and monitored on an ongoing basis by CGM.
On-going validation included a detailed survey of historical collar positions using a DGPS which
highlighted a number of minor discrepancies (typically less than 10 m). Based on the new survey data,
the database has been updated accordingly and the interpretations adjusted to the new drillhole
positions.
The on-going validation of the underground channel sampling database has been a considerable task,
which has required capture of the sampling information from the mines operating long-sections into a
3D database. The program continued between 2017 and 2019, which has resulted in an increase of
approximately 100% in the size of the channel sample database. To complete the task, CGM has
completed surveys of the existing development to ensure accuracy of the placement of sampling on
the main levels. CGM geologists have then created collar, survey and assay database for each sample
relative to the strike of the deposit using the assumption that sampling has been completed
perpendicular to the vein, as per the mines sampling procedure.
In 2020, CGM commissioned a separate study with WL Engineering (WLI) to review the Marmato
project for internal requirements as part of a license extension application to the Colombian National
Mining Association (NMA). As part of the study WLI completed a detailed validation of the data used
to generate the geological model and mineral resource. These studies included:
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 123
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
• Visiting Competent Person, Peter Bergsneider Serrano
• Visit by a Competent Person, Mauricio Castañeda Gómez
• Spatial verification of the geographic reference system for the topographic surface, and the
Marmato Project Database; Magna Sirgas, Origin West
• Spatial agreement between the surface collars and the surface topography of the Marmato
Project
• Validation of duplicate coordinates and/or anomalous height values outside the topographic
surface or underground work
• Verification of anomalous deviations from the survey table
• Consistency between the gold and silver data reported in the test table versus the laboratory
certificates
• Search for duplicate or abnormal records in the various tables of the Database, and QA/QC
• Verification of the reported values of gold and silver in the modeling compounds, and their
correspondence in the resource model
• Verification of the structural data reported in the various mineralization styles of the Marmato
Project
• Review and verification of available geotechnical data
• Visual verification of modeled solids versus database
12.1.2 Verifications by SRK
In accordance with NI 43-101 guidelines, Mr. Ben Parsons of SRK most recently visited the Marmato
Project on June 11, 2019. The main purpose of the site visit was to:
• Witness the extent of the exploration work completed to date
• Complete an underground site inspection to understand the changes in the geological settings
and possible exposure of the MDZ style mineralization
• Inspect core logging and sample storage facilities
• Discuss geological interpretation and inspect drill core
• Assess logistical aspects and other constraints relating to the exploration property
• Review data for the assay database
• Hold discussions with personnel involved in the current and historical exploration activities
SRK did not complete an independent visit to the SGS Laboratory facility during the recent site visit
but visited the facility previously during the November 2011 site visit also completed by Mr. Ben
Parsons.
In 2019, SRK undertook a number of site visits by specialized geological staff to review both the
structural model controls and implementation for the PFS model, and to witness the sampling
procedures for the mine. The site visits were completed by Mr. Blair Hrabi for the structural review and
by Mr. Giovanny Ortiz for the sampling and mapping review.
SRK has been working with the exploration team since 2017, when data has been captured from the
mine to generate a detailed geological model. For the most recent iteration of the database, in addition
to the site inspection, SRK has completed a series of technical meetings with CGM geologists to review
the on-going capture of the underground channel sampling program and integration into the database.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 124
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
SRK reviewed the capture and geo-referencing of the underground development with existing
geological maps for each of the mining levels.
SRK highlighted a lack of QA/QC in the operating mine channel sampling program. In the absence of
quality control information, SRK has relied upon reconciliation of the planned versus head-grade from
the grade control systems to determine if the performance of the channel sampling is reasonable. The
mine current run and annual study of the planned grade (based on channel samples and drilling
assayed at the mine laboratory) versus the reported grade (head-grade). A study of the planned versus
head-grades for 2006 to 2019 shows the differences in the grades range between -10.7% to + 8.6%
on an annual basis (Table 12-1) but the overall performance is in the order of 2.3% during this period,
when weighted for tonnage, which SRK considers reasonable, but notes a minor high-bias in results
since, which should be monitored via regular QA/QC.
Table 12-1: Comparison of Mine Planned Grades (Assayed at Mine Laboratory) Versus Head-Grades
Year Planned Grade Au (g/t) Head Grade Au (g/t) Comparison (%)
2006 3.59 3.64 -1.4%
2007 3.51 3.32 5.7%
2008 3.24 3.44 -5.8%
2009 3.24 3.51 -7.7%
2010 3.34 3.39 -1.5%
2011 3.31 3.19 3.8%
2012 3.02 2.84 6.2%
2013 2.94 2.83 3.7%
2014 2.91 2.85 2.0%
2015 2.95 2.79 5.8%
2016 2.83 2.56 10.7%
2017 2.69 2.48 8.6%
2018 2.60 2.67 -3.0%
2019 2.63 2.49 5.4%
Source: CGM, 2020
Source: CGM, 2020
Figure 12-1: Comparison of Planned Versus Actual Gold Grades at Marmato Mine
3.59
3.51
3.24 3.24
3.343.31
3.02
2.94 2.912.95
2.83
2.69
2.602.63
3.64
3.32
3.443.51
3.39
3.19
2.84 2.83 2.852.79
2.56
2.48
2.67
2.49
-15.0%
-10.0%
-5.0%
0.0%
5.0%
10.0%
15.0%
2.00
2.20
2.40
2.60
2.80
3.00
3.20
3.40
3.60
3.80
4.00
20
06
20
07
20
08
20
09
20
10
20
11
20
12
20
13
20
14
20
15
20
16
20
17
20
18
20
19
Diff
ere
nce (
%)
Gra
de A
u (
g/t)
Year
Comparison of Planned versus Actual Gold Grades (Au g/t)
Planned Grade Au (g/t) Head Grade Au (g/t) Comparison (%)
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 125
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
While the study adds confidence to the mine sampling, it should not replace the need for an industry
standard QA/QC protocol in future sampling.
SRK has undertaken basic validation for all tabulated data in both Leapfrog® and Datamine.
Additionally, in order to independently verify the information incorporated within the latest drill program,
SRK has:
• Completed a review of selected drill core for selected holes, to confirm both geological and
assay values stored in the database show a reasonable representation of the Project
• Verified the digital database against the original issued assay certificates
• Visited underground workings to check the continuity of vein and veinlet mineralization at
depth, including a site inspection to levels 19 through 21 to understand changes in the
mineralization styles
• Verified the quality of geological and sampling information and developed an interpretation of
gold grade distributions appropriate to use in the resource model
• Reviewed the QA/QC database for the recent drilling and channel sampling programs
12.2 Limitations
SRK has reviewed the data acquired for the Project and held a number of technical meetings at the
Company office in Medellín to review the progress on the data validation. The efforts should remain
ongoing and a lack of definition in portions of the 3D survey of the mines has limited the ability to
accurately place all the samples in their “true” location. SRK notes that the information for the raise
sampling shows the most significant variations from SRK geological interpretation using mapping
between levels.
SRK has highlighted to CGM that in the validation phase, there still remains a large number of data
points which contain significant mineralization that require constraining which lie outside of the revised
2019 vein interpretations. SRK noted a number of areas where, based on short channel samples, the
geological model would likely result in overstating the tonnage if left unconstrained. Additionally, where
these occur, the grade in any subsequent estimate will overstate grade locally with possible vein or
veinlet material being incorrectly projected into the lower grade porphyry style domains.
The current structure of the database and naming convention for the underground channel sampling
results in some limitations on generating an automated process to update the geological model.
Isolated sampling of veins without surrounding samples can led to overstating the tonnage when using
Leapfrog® and therefore caution has been required to review intersections on a case by case basis.
Additionally, in a number of cases long cross-cut drift sampling has been logged as individual
Hole_ID’s, so restrictions based on length cannot be applied.
Regarding the significant rise in the amount of channel sampling, some of which has not been captured
in the veins or splay model, it is the opinion of SRK that there is potential for over-estimation. SRK has
noted this risk and therefore applied filters to the database to minimize these risks in the porphyry
domain estimates. SRK considers this approach to be conservative, and it has resulted in a reduction
in the contained metal within the domains if estimated with no filter; however, these estimates provide
a more reasonable base case for classification. Further work is recommended between SRK and CGM
to improve the database structure and geological modelling of this domain, prior to any consideration
for use in a mining study.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 126
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
SRK completed a series of test models, which removed the influence of any of these samples from
the database, using filters on logging codes and channel length, which is considered a more
conservative approach by discounting the influence of short channel samples. The resultant
interpretation contained approximately half the volume of the optimistic scenario for the porphyry
mineralization. Due to the uncertainty in the impact of these domains, SRK has therefore excluded this
material from the current mining assessment. If a solution can be found in the short term to improve
the confidence in the geological continuity, this may represent upside potential. SRK recommends
follow-up work from CGM which includes mapping and verification of the presence of the porphyry-
style mineralization and additional sampling (drilling if required), prior to inclusion in the mine plan.
12.3 Opinion on Data Adequacy
Based on the validation work completed by SRK, the database has been accepted as provided by
CGM’s Resource Geologist. SRK is satisfied with the quality of assays returned from the laboratory
for the latest drilling program and that there is no evidence of bias within the current database which
would materially impact on the estimate.
While there are areas for potential improvement, SRK is of the opinion that the exploration and assay
data is sufficiently reliable to support evaluation and classification of Mineral Resources in accordance
with generally accepted CIM Estimation of Mineral Resources and Reserves: Definitions and
Guidelines (CIM, 2014).
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 127
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
13 Mineral Processing and Metallurgical Testing Metallurgical programs were conducted by SGS Lakefield (SGS) in 2019 and 2020 to evaluate
processing requirements for the MDZ. The 2019 metallurgical program was conducted as part of the
2019 PEA that was prepared for the Project and the 2020 metallurgical program was conducted to
support the current PFS. For ease of reference, the results of the 2019 metallurgical program are
briefly summarized in this section along with the results of the 2020 metallurgical program.
13.1 Metallurgical Program – 2019
The results of the 2019 metallurgical program are fully documented in SGS’s report, “The Recovery of
Gold from Marmato Deposit Samples” dated April 16, 2019. The metallurgical program included
comminution testwork, mineralogical studies and an evaluation of several different flowsheet options
including:
• Whole-ore cyanidation
• Gravity concentration followed by cyanidation of the gravity tailings
• Gravity concentration followed by gold flotation from the gravity tailing and cyanidation of the
flotation concentrate
13.1.1 Metallurgical Sample Characterization
The test program was conducted on test samples prepared from drill core from the East, West and
Central MDZ and a Master MDZ composite was formulated on a weighted basis from the East, West
and Central MDZ samples. In addition, a composite representing the current Marmato material was
also tested. The drill holes and intervals used to formulate the test composites are shown in Table
13-1 and the location of each drillhole is shown in Figure 13-1. Head analyses for each of the test
composites are shown in Table 13-2.
Table 13-1: Drillholes and Intervals for MDZ Metallurgical Composites
Location Drill Hole From (m) To (m)
East Zone
MT-IU-001 138.3 148
MT-IU-004 152.4 182.2
MT-1445 562 589
Central Zone
MT-IU-002 146 179.3
MT-IU-003 209.4 256.5
MT-IU-006 252.5 292.8
MT-1498 334 386
West Zone
MT-IU-007 159.4 173.7
MT-IU-008 251 266.6
MT-IU-011 129.3 144.6 Source: SGS Lakefield, 2019
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 128
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SRK, 2019
Figure 13-1: Drillhole Locations
Table 13-2: Head Analyses for MDZ and Marmato Test Composites
Element MDZ West MDZ Center MDZ East MDZ Master Marmato Comp
Au (S.M.) g/t 1.54 2.69 2.65 2.32 5.48
Au (Calc.) g/t 1.3 2.61 1.8 2.36 4.83
Ag g/t 0.9 3.9 6.7 4.2 19.6
S % 1.22 2.04 2.2 1.95 10.5
Te g/t <4 <4 <4 <4 <4
Hg g/t 0.3 <0.3 <0.3 <0.3 <0.3 Source: SGS, 2019 Au (S. M.) = average of screened metallic assay Au (Calc) = average from testwork
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 129
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
13.1.2 Mineralogy
A mineralogical evaluation was conducted on a single sample from the MDZ Center Zone by Terra
Mineralogical Services Inc. Key findings included the following:
• Native gold was by far the predominant gold carrier
• The majority (more than 99%) of the gold particles occurred in locations that would be readily
accessible by leaching solutions
• The gold grains were predominately associated with silicate gangue minerals. Gold particles
were not often in direct contact with sulfides, yet very commonly pyrrhotite, chalcopyrite, and
bismuth minerals were found in close vicinity to the gold mineralization
• The average grain size of the gold particle was very fine (<6 μm), however, a small amount of
coarse gold particles also identified.
13.1.3 Comminution Testwork
Comminution testwork included SMC (SAG mill comminution), BWI (Bond ball mill work index) and AI
(Abrasion index) index determinations and the results are shown in Table 13-3. The SMC tests were
conducted on the East, West and Center MDZ composites and the reported Axb values ranged from
28 to 31 and averaged 29, indicating that the material is very hard with respect to SAG mill impact
grinding. The BWI tests were conducted on all test composites using a 150 mesh (105 µm) closing
screen, the MDZ composites ranged from 19 to 20.7 kWh/t and averaged 19.8 kWh/t, indicating that
the MDZ material is very hard with respect to ball mill grinding. The AI tests on the MDZ composites
ranged from 0.626 to 0.731 indicating that the samples were very abrasive and high liner and grinding
media wear rates can be expected.
Table 13-3: Comminution Test Results on MDZ and Marmato Test Samples
Sample Relative Density JK Parameters
BWI (kWh/t) AI (g) A x b ta SCSE
Marmato Mine Comp - - - - 15.7 0.199
MDZ Comp - - - - 20.7 0.652
Center Zone Comp 2.65 31 0.30 11.0 19.0 0.704
East Zone Comp 2.64 28 0.27 11.6 20.3 0.626
West Zone Comp 2.69 28 0.27 11.7 19.0 0.731
Average 2.66 29 0.28 11.4 19.0 0.582
Source: SGS, 2019
13.1.4 Whole-Ore Cyanidation
Two whole-ore cyanidation tests were completed on the MDZ Master composite. The tests were
conducted at a grind size of 80% passing (P80) 60 µm with a maintained cyanide concentration of 1 g/L
sodium cyanide (NaCN) and evaluated the impact of pre-aeration and dissolved oxygen concentration
on gold extraction and leach kinetics. The results of these tests are summarized in Table 13-4. These
tests showed that without pre-aeration and only air injection to maintain the dissolved oxygen
concentration during leaching at 5 to 8 mg/L, 98% of the gold could be extracted after 72 hours of
leaching with sodium cyanide consumption reported at 1.83 kilograms per tonne (kg/t). However, with
inclusion of pre-aeration for two hours and oxygen injection sufficient to maintain the dissolved oxygen
concentration during leaching at 20 mg/L, sodium cyanide consumption was reduced to 0.66 kg/t and
leach kinetics were significantly increased with gold leaching complete after 24 to 48 hours.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 130
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 13-4: Whole-Ore Cyanidation Test Results on MDZ Test Composite
Grind Size (P80 µm)
Aeration Conditions Reagent Cons. kg/t of
CN Feed Au Extraction (%) Au Residue (g/t) Au Head (g/t)
Pre-air Leach NaCN CaO 8 h 24 h 48 h 72 h A B Avg. Calc. Direct
56 n/a Air, ~5-8 ppm 1.83 1.52 40 70.4 88.7 98.3 0.04 0.05 0.05 2.65 2.32
61 2 h O2 O2, ~20 ppm 0.66 1.29 93.5 95.6 ~99 98.2 0.04 0.04 0.04 2.26
Source: SGS, 2019
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 131
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
13.1.5 Gravity Concentration
Gravity concentration tests were conducted on the MDZ Master, West Zone, Center Zone, East Zone
and Marmato composites at grind sizes ranging from P80 70 to 223 µm with a Knelson MD-3 centrifugal
gravity concentrator followed by upgrading on a Mozley table. The results of these tests are shown in
Table 13-5. This testwork demonstrated that the MDZ material (including West, Center and East Zone
composites) is highly amenable to gravity concentration with gold recoveries ranging from 50.6 to 69%
and silver recoveries ranging from 14.6 to 24.7% into gravity concentrates containing 0.05 to 0.16
weight percent (wt%) and 1,575 to 2,494 g/t Au and 182 to 1,432 g/t Ag.
Table 13-5: Summary of Gravity Concentration Testwork on MDZ and Marmato Composites (1)
Test No.
Composite
Grind Size
Assay Head Calc. Head Gravity Concentrate Distribution
(%)
P80
µm Au
(g/t) Ag
(g/t) Au
(g/t) Ag
(g/t) Mass
(%) Au (g/t
Ag (g/t)
Au Ag
G-1 MDZ 223 2.32 4.2 2.31 3.9 0.07 1,815 1,006 55.1 17.9
G-3 MDZ 223 2.32 4.2 2.27 4.5 0.05 2,494 1,432 50.6 14.6
G-9 MDZ 112 2.32 4.2 2.51 4.0 0.10 1,575 921 63.7 23.6
G-6 West Zone 88 1.54 0.9 1.3 1.2 0.16 531 182 66.1 24.7
G-7 Center Zone 94 2.69 3.9 2.61 4.3 0.12 1,498 752 69.0 21.0
G-8 East Zone 99 2.65 6.7 1.8 8.1 0.11 831 1,149 51.7 15.9
G-4 Marmato 70 5.48 19.6 4.67 18.8 0.17 1,586 1,278 57.9 11.6
G4R Marmato 78 5.48 19.6 4.98 18.5 0.13 2,192 1,668 56.9 11.6
Note: (1) Marmato test G-2 not shown due to high variance between assay and calculated head Source: SGS Lakefield, 2019
13.1.6 Cyanidation of Gravity Tailing
MDZ Master Composite
Cyanidation tests were conducted on the gravity tailings from the MDZ Master Composite. The leach
conditions are shown in Table 13-6 and the test results are summarized in Table 13-7. Tests were
conducted over a range of grind sizes and cyanide concentrations, both with and without pre-aeration
and oxygen injection. These tests demonstrated that overall gold extractions
(gravity concentration + gravity tailing cyanidation) of about 97 to 98% could be achieved. A grind size
of about P80 100 µm appeared optimum with a cyanide concentration of 0.5 g/L NaCN. Preaeration
appears to be beneficial in reducing cyanide consumption. Gold extraction versus leach retention time
is shown in Figure 13-2.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 132
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 13-6: MDZ Master Composite Gravity Tailing Leach Conditions
CN Test No.
Feed Grind P80, µm
Aeration Conditions Lead Nitrate (100 g/t)
Cyanide (g/L
NaCN)
Reagent Addition
(kg/t)
Reagent Cons. (kg/t)
Pre-Air Leach NaCN CaO NaCN CaO
3 G-1 223 n/a Air, ~5-8
ppm N 1 1.65 1.09 0.83 1.09
4 G-1 70 n/a Air, ~5-8
ppm N 1 2.27 1.09 1.55 1.09
12 G-3 138 4 h, O2 O2, ~20
ppm N 1 1.23 1.22 0.24 1.18
13 G-3 96 4 h, O2 O2, ~20
ppm N 1 1.24 1.27 0.22 1.23
14 G-3 76 4 h, O2 O2, ~20
ppm N 1 1.24 1.32 0.25 1.30
15 G-3 80 2 h, O2 O2, ~20
ppm Y 1 1.24 1.20 0.28 1.17
21 G-3 99 4 h, O2 O2, ~20
ppm N 0.75 0.75 1.10 0.19 1.09
22 G-3 98 4 h, O2 O2, ~20
ppm N 0.50 0.50 1.11 0.16 1.08
23 G-3 97 4 h, O2 O2, ~20
ppm Y 0.50 0.50 1.13 0.14 1.11
Source: SGS Lakefield, 2019
Table 13-7: Gravity Concentration + Gravity Tailing Cyanidation Test Results
CN Test No.
Feed
Au Extraction/Recovery, % Residue (Au g/t) Calc. Head
(Au g/t) CN (Unit)
Grav Grav +
CN 8 h 24 h 48 h 72 h A B Avg.
3 G-1 58.6 79.9 85.8 55.1 93.6 0.12 0.18 0.15 1.06
4 G-1 88.2 95.6 55.1 98.0 0.07 0.06 0.07 1.48
12 G-3 87.3 93.8 93.2 93.3 50.6 96.7 0.08 0.08 0.08 1.19
13 G-3 89.8 96.1 94.7 95.1 50.6 97.6 0.06 0.05 0.06 1.13
14 G-3 87.8 95.6 95.2 95.0 50.6 97.5 0.05 0.06 0.06 1.10
15 G-3 90.7 95.1 97.0 95.9 50.6 98.0 0.04 0.05 0.05 1.08
21 G-3 80.3 90.1 92.6 93.1 50.6 96.6 0.08 0.07 0.08 1.08
22 G-3 83.1 93.3 92.9 93.4 50.6 96.7 0.07 0.07 0.07 1.06
23 G-3 91.5 95.9 95.2 95.4 50.6 97.7 0.05 0.06 0.06 1.21
Source: SGS Lakefield, 2019
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 133
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SGS Lakefield, 2019
Figure 13-2: Gold Extraction Versus Retention Time (MDZ Master Comp Gravity Tailings)
13.1.7 Variability Composites
The individual East, Center and West Zone composites and the Marmato composite were subjected
to gravity concentration followed by cyanidation of the gravity tailings using the following test
conditions:
• Grind size: ~ P80 of 100 μm
• Preaeration: 4 hours with oxygen
• Dissolved O2: 20 mg/L
• NaCN: 1.0 g/L (maintained)
• Retention Time: 48 hours
• Slurry Density: 50% solids
The results of these tests are summarized in Table 13-8, which show that overall gold recoveries for
the West, Center and East Zone composites were very similar to the results obtained from the MDZ
Master composite and ranged from 96.7 to 97.9% with cyanide consumption ranging from 0.19 to 0.34
kg/t. Overall gold recovery from the Marmato composite was about 92% with cyanide consumption at
about 0.50 kg/t.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 134
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 13-8: Summary of Gravity Concentration + Gravity Tailing Cyanidation (Variability Composites)
Gravity Test Cyanidation Test Composite Grind Size Au Distribution (%)
P80 µm Gravity Grav. + Cyan.
G-6 CN-18 West Zone 88 66.1 97.3
G-7 CN-19 Center Zone 94 69.0 97.9
G-8 CN-20 East Zone 99 51.7 96.7
G-4 CN-16 Marmato 70 57.9 92.0
G4R CN-16R Marmato 78 56.9 91.8
Source: SGS Lakefield, 2019
13.1.8 Flotation from Gravity Tailing
Rougher flotation tests were conducted on gravity tailings from the MDZ Master and Marmato
composites using flotation conditions provided by CGM. All tests were conducted at natural pH with
20 minutes of retention time and used potassium amyl xanthate (PAX) and MX5160 as the collectors,
copper sulfate as a sulfide mineral activator and Dowfroth 250 as the frother. The results of selected
tests are shown in Table 13-9. Overall gold recoveries (gravity concentration + rougher flotation) of
96% to 97% were reported for the MDZ Master composite and 97.4% for the Marmato composite.
Rougher flotation concentrate grades produced from the MDZ Master composite ranged from about
10 to 13 g/t Au. The rougher flotation concentrate produced from the Marmato composite contained
43.6 g/t Au. Although generally high overall gold recoveries were reported, it should be noted that the
gold grade of the final flotation tailing produced from the MDZ Master composite was significantly
higher than the cyanidation leach residues (0.09 g/t Au versus 0.06 g/t Au).
Table 13-9: Summary of Rougher Flotation Tests on Gravity Tailings from MDZ and Marmato Composites
Composite Test Grind P80 µm Au Recovery (%) Au Grade (g/t)
Grav Flot (unit) Flot + Grav Flot Conc Flot Tail
MDZ G1/F2 74 55.1 93.4 97.0 9.6 0.08
MDZ G1/F4 63 55.1 91.9 96.4 13.1 0.09
MDZ G1/F5 63 55.1 90.8 95.9 12.1 0.10
Average 67 55.1 92.0 96.4 11.6 0.09
Marmato G-2/F3 210 11.5 97.1 97.4 43.6 0.39
Source: SGS Lakefield, 2019
Cyanidation of Flotation Concentrates
Cyanidation tests were conducted on the rougher flotation concentrates that had been reground to
about 22 µm. Cyanidation tests were conducted at 1 g/L NaCN for 48 hours and the results are
summarized in Table 13-10. These tests demonstrated that about 98% of the gold contained in the
flotation concentrates could be extracted by cyanidation. It is important to note that 98% gold extraction
from the flotation concentrate implies an overall gold recovery of about 95% to 96% from a gravity +
flotation + cyanidation flowsheet. This is about 2% lower gold recovery than by the gravity + gravity
tailing cyanidation flowsheet.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 135
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 13-10: Summary of Flotation Concentrate Cyanidation Test Results
CN Test No.
Sample Feed
Au Extraction, % CN (Unit)
Au Residue (g/t) Au Calc. Head (g/t)
8 h 24 h 48 h A B Avg.
1 MDZ G-1/F-1 95.4 97.1 98.1 0.22 0.20 0.21 11.1
2 MDZ G-1/F-2 93.3 95.4 98.2 0.17 0.17 0.17 9.57
10 MDZ G-1/F-4 93.0 95.1 97.2 0.38 0.36 0.37 13.1
11 MDZ G-1/F-5 94.2 95.9 98.1 0.24 0.23 0.24 12.1
7 Marmato G-2/F-3 56.6 92.4 98.0 0.87 0.84 0.86 43.6
Source: SGS, 2019
13.1.9 Cyanide Detoxification
The cyanidation leach residue produced from the MDZ Master composite under optimized leach
conditions was subjected to cyanide detoxification testing using the industry-standard SO2/Air process
to reduce the weak acid dissociable cyanide (CNWAD) to less than 10 mg/L. The main parameters
adjusted during the testwork were sodium metabisulphite and copper addition rates. The results of the
detoxification testwork are shown in Table 13-11. The initial leach residue contained 151 mg/L CNWAD,
which was subsequently reduced to 8.95 CNWAD (Test 1-7) with the addition of 8.05 g SO2/g CNWAD
and 0.22 g Cu/g CNWAD. This testwork established that the following operating conditions will achieve
a discharge CNWAD concentration of <10 mg/L.
• Slurry density: 50% solids (w/w)
• SO2 addition: 8 g SO2 /g CNWAD
• Cu addition: 0.22 g Cu /g CNWAD
• pH: 8.5 (with lime added as needed (~0.5 kg/t)
• Retention time: 90 minutes
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 136
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 13-11: Summary of Cyanide Detoxification Testwork on MDZ Composite Leach Residue
Test
Test Duration
Reten. Time
Product (Solution Phase) Reagent Addition
Min Min pH
CNT CNWAD by Cu Fe g/g CN WAD g/L Feed Pulp kg/t Solids
mg/L Ana. Lab
mg/L
Picric Acid mg/L
Aged Picric Acid mg/L
mg/L mg/L SO2
Equiv. Lime Cu (1)
SO2 Equiv.
Lime Cu (1) SO2
Equiv. Lime Cu (1)
Feed (CN-24) … 10.6 150 151 … … 26.6 2.56 … … … … … … … … …
Batch Test
270 8.5 … … 1.12 … … … 11.1 9.71 0.070 1.23 1.08 0.007 1.67 1.46 0.011 CND 1
270
Continuous Tests 8.5 … … 55.6 … … … 6.98 0.54 0.000 0.78 0.061 0.000 1.05 0.081 0.000
1-1 94 60
1-2 90 55 8.7 5.7 <0.1 14.7 1.14* 0.70 1.7 6.12 0.11 0.070 0.68 0.013 0.007 0.92 0.02 0.011
1-3 90 60 8.5 … … 50.2 … 7.95 4.84 0.070 0.88 0.55 0.007 1.20 0.73 0.011
1-4 60 55 8.5 … … 30.5 … … … 7.31 3.60 0.130 0.81 0.41 0.015 1.10 0.54 0.020
1-5 115 59 8.5 2.5 <0.1 9.88 2.51** 4.3 1.2 7.57 2.19 0.220 0.88 0.26 0.025 1.14 0.33 0.033
1-6 120 59 8.5 … … 18.3 … … … 7.37 2.38 0.350 0.86 0.28 0.041 1.11 0.36 0.053
1-7 100 89 8.5 … … 8.95 … … … 8.05 3.62 0.220 0.94 0.43 0.026 1.21 0.55 0.033
1-8 170 91 8.5 <0.1 <0.1 6.45 … 14.7 <0.1 10.7 4.66 0.240 1.19 0.53 0.026 1.61 0.70 0.036
…No sample submitted for assays (1) Cu added using CuSO4, 5H2O, SO2 added using sodium metabisulphite * CND1-2 aged five-day sample ** CND1-5 aged one day sample Bold red values indicate a key parameter that has changed Source: SGS Lakefield, 2019
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 137
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
13.1.10 Solid-Liquid Separation
Thickening and rheological studies were conducted on a cyanidation leach residue at a P80 105 µm
grind size that had adjusted to pH 8.5 with lime to simulate the detoxified slurry pH.
Flocculant Screening
Flocculant screening tests identified BASF Magnafloc 10, which is a very high molecular weight,
slightly anionic polyacrylamide flocculant, as a suitable flocculant for this application at an application
rate of 40 g/t. Both static and dynamic thickening testwork were conducted with this flocculant.
Static Thickening
Preliminary static settling tests were performed in two-liter graduated cylinders which were fixed with
rotating picket-style rakes. Static settling test results were used to determine the starting conditions for
subsequent dynamic thickening tests. The selected conditions based on these tests are summarized
in Table 13-12, and indicated a specific thickener settling area of 0.11 square meters per tonne per
day (m2/[t/day]) with an underflow density of 62% solids and an overflow containing 61 mg/L of total
suspended solids (TSS).
Table 13-12: Static Thickener Test Conditions
o Sample ID o Flocculant Dose
(g/t) o Feed
%w/w o U/F
%w/w o Unit Area
m2/(t/day) o ISR
m3/m2/day o Supernatant
Clarity o TSS
mg/L
o MDZ Comp o 40 o 8 o 62 o 0.11 o 833 o Hazy o 61
Source: SGS Lakefield, 2019
Dynamic Thickening
Dynamic thickening testwork was initiated with a 50 g/t dosage of BASF Magnafloc 10 flocculant at a
feedwell slurry density of 8% (w/w) solids. The dynamic thickening test responded very differently to
the static thickening test under these conditions with a very turbid overflow with total suspended solids
(TSS) measured at 450 mg/L. In order to improve the overflow clarity, BASF Magnafloc 1687 coagulant
was applied to the diluted thickener feed prior to flocculant dosing. A series of additional tests
established a dosage of Magnafloc 1687 at 15 g/t followed by a dosage of 25 g/t of Magnafloc 10 as
optimal. The result of dynamic thickener tests conducted over a range of unit settling areas (m2/[t/d])
are summarized in Table 13-13.
Table 13-13: Summary of Dynamic Thickener Test Results
1687 Dosage (g/t)
10 Dosage (g/t)
Unit Area m2/(t/d)
Solids Loading (t/m2/h)
Net Rise Rate (m3/m2/d)
Underflow %w/w solids
Overflow TSS (mg/L)
Residence Time (h)
U/F Yield Stress (Pa)
15 25 0.13 0.32 84.2 64.1 54 1.36 60
15 25 0.11 0.38 99.5 62.9 57 1.15 49
15 25 0.09 0.46 121.7 61.7 43 0.94 52
15 25 0.07 0.60 156.4 59.5 58 0.73 38
Underflow extended for 30 minutes: 65.1 93
Note: Bed height was maintained around 160 mm Source: SGS Lakefield, 2019
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 138
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Rheology on Thickener Underflow
The results of rheology testwork on the thickener underflow are summarized in Table 13-14. A Critical
Solids Density (CSD) of approximately 61% solids was established, which corresponds to
approximately 20 pascals (Pa) on the unsheared yield test and 13 Pa on the sheared yield test. As
shown in Figure 13-3, CSD is the solids density at which a small increase of the solids density causes
a significant decrease of the flowability of the slurry. The CSD value is also predictive of the maximum
underflow solids density achievable in a commercial thickener.
Table 13-14: Results of Rheology Testwork on MDZ Thickener Underflow Sample
Test Code
Solids %w/w
Unsheared Sample Sheared Sample
Observations Ɣ ƮyВ ɳP Ɣ ƮyВ ɳP
Range, 1/s
Pa mPa.s Range,
1/s Pa mPa.s
CSD= ~61% solids, corresponding to ~20 Pa unsheared and 13 Pa sheared yield stress.
T1 65.8 Plug Flow 73 -- 200-400 26 50 Thixotropic
T2 64.2 200-400 50 3.9 200-400 20 36 Thixotropic
T3 62.1 200-400 28 15 200-400 15 24 Thixotropic
T4 60.3 200-400 17 16 200-400 12 17 Thixotropic
T5 58.3 200-400 12 15 200-400 8.9 15 Minor Thixotropic, minor settling
T6 54.2 200-400 5.1 13 200-400 4.8 13 Minor settling
T7 50.3 200-400 2.3 10 200-400 2.1 15 Moderate settling, dilatant after 425 1/s
Notes:
• The MDZ Comp underflow samples contained 15 g/t BASF Magnafloc 1687 coagulant and 25 g/t BASF Magnafloc 10 flocculant.
• The values are based on data produced by the unsheared and sheared slurry sample.
• Variable shearing was produced in the 0 to 600 s-1 range, increasing and decreasing (up and down curves).
• Constant shearing was produced by subjecting the slurry sample to a constant rotation at 300 1/s for 180 seconds.
• Bingham Plastic parameters: yield stress (ƮyВ) and plastic viscosity (ɳP) values, for the specified Ɣ range.
• Ɣ – Shear rate range at which the rheological parameters were calculated. Source: SGS Lakefield, 2019
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 139
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SGS, 2019
Figure 13-3: Yield Stress Versus Thickener Underflow Slurry Density
13.2 Metallurgical Program – 2020
The 2020 metallurgical program was conducted to further define the process parameters and design
criteria for the selected flowsheet that includes gravity concentration followed by cyanidation of the
gravity tailing. The test program included gravity concentration, gravity recoverable gold (E-GRG
determination) cyanide leach optimization and carbon-in-pulp (CIP) modelling. Cyanide destruction
(CND), solid/liquid separation, and environmental testwork was also completed. The optimization and
metallurgical design tests were all completed using the Master Composite. Once the optimized
flowsheet had been selected, the variability test samples were tested under these optimized
gravity/cyanidation conditions. The results of this program are fully documented in SGS’s report, “The
Recovery of Gold from Marmato MDZ Deposit Samples”, June 18, 2020.
13.2.1 Metallurgical Sample Location
The 2020 metallurgical program was conducted on an MDZ master composite and on variability
composites representing low, medium and high grade MDZ ore, transition zone and the MDZ Deep.
In addition, an ore sample from the existing Marmato mine was tested. The MDZ master and variability
composites were formulated from selected drill core holes and intervals. The master composite was
prepared from the low, medium and high grade MDZ variability composites on a weighted basis to
represent the average grade of the MDZ. In addition, selected core intervals from five different drill
holes were prepared for crushability testwork. The selected drill holes and core intervals used to
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 140
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
formulate each of the MDZ test composites are shown in Tables 13-15 through 13-20. Figure 13-4
shows the location of the selected drill holes and intervals.
Table 13-15: Drill Holes and Intervals Used for the Low Grade MDZ Composite
Hole Sample ID From (m) To (m) Metallurgy ID Weight (Kg)
MT-1445
D97563 546.0 548.0 001 1.90
D97564 548.0 550.0 002 1.90
D97565 550.0 552.0 003 1.90
D97566 552.0 554.0 004 1.90
D97568 554.0 556.0 005 2.00
D97569 556.0 558.0 006 2.00
D97570 558.0 560.0 007 2.00
MT-IU-021
D119582 169.4 170.6 008 2.04
D119583 170.6 171.7 009 1.78
D119584 171.7 172.9 010 1.90
D119585 172.9 174.0 011 2.08
D119586 174.0 175.2 012 2.14
D119587 175.2 176.4 013 2.08
D119588 176.4 177.7 014 1.80
D119589 177.7 179.2 015 2.08
D119591 179.2 180.7 016 2.52
MT-IU-006
D115349 184.2 185.2 017 2.04
D115350 185.2 185.9 018 1.00
D115351 185.9 187.4 019 2.96
D115352 187.4 188.9 020 3.24
D115353 188.9 189.9 021 2.08
D115355 189.9 191.2 022 2.72
D115356 191.2 192.6 023 2.64
D115357 192.6 193.3 024 1.50
D115358 193.3 194.8 025 1.68
D115359 194.8 196.3 026 1.64
D115360 196.3 197.3 027 1.14
D115361 197.3 198.3 028 1.18
D115362 198.3 199.1 029 0.54
D115365 199.1 200.6 030 1.50
D115366 200.6 202.1 031 1.72
D115367 202.1 203.8 032 1.52
D115368 203.8 204.8 033 0.62
D115370 204.8 205.6 034 0.74
D115371 205.6 207.1 035 1.56
D115372 207.1 208.6 036 1.50
MT-IU-015
D117573 294.0 295.2 037 1.76
D117574 295.2 296.0 038 1.28
D117575 296.0 297.0 039 1.56
D117577 297.0 298.2 040 1.50
D117579 298.2 299.4 041 1.60
D117580 299.4 300.9 042 2.34
D117581 300.9 302.4 043 2.34
D117582 302.4 303.9 044 2.58
D117583 303.9 305.4 045 2.52
D117584 305.4 306.9 046 2.36
Source: SRK, 2020
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 141
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 13-16: Drill Holes and Intervals Used for the Medium Grade MDZ Composite
Hole Sample ID From (m) To (m) Metallurgy ID Weight (Kg)
MT-1445
D97541 513.0 515.0 001 1.90
D97542 515.0 517.0 002 2.00
D97543 517.0 519.0 003 1.90
D97544 519.0 521.0 004 1.90
D97546 521.0 522.5 005 1.50
D97547 522.5 524.0 006 1.60
D97548 524.0 525.5 007 1.40
D97549 525.5 526.7 008 1.10
D97550 526.7 528.0 009 1.00
MT-1499-A
D105992 506.0 507.3 010 1.00
D105993 507.3 509.0 011 1.40
D105994 509.0 511.0 012 1.56
D105996 511.0 513.0 013 1.50
D105997 513.0 515.0 014 1.64
D105998 515.0 517.0 015 1.52
D105999 517.0 519.0 016 1.80
D106000 519.0 521.0 017 1.56
D107877 521.0 523.0 018 1.60
D107878 523.0 525.0 019 1.84
D107879 525.0 527.0 020 1.78
D107880 527.0 529.0 021 1.76
D107881 529.0 531.0 022 1.70
MT-1455-A
D93860 585.7 587.0 023 1.26
D93861 587.0 589.0 024 1.92
D93862 589.0 591.0 025 2.00
D93863 591.0 593.0 026 1.72
D93864 593.0 595.0 027 1.92
D93865 595.0 597.0 028 2.06
D93867 597.0 598.5 029 1.42
D93868 598.5 600.0 030 1.50
D93869 600.0 602.0 031 1.80
D93870 602.0 604.0 032 2.06
D93871 604.0 605.0 033 1.06
D93872 605.0 607.0 034 2.06
D93873 607.0 609.0 035 2.10
D93874 609.0 610.8 036 1.70
D93875 610.8 612.0 037 1.12
D93876 612.0 613.6 038 1.26
D93877 613.6 614.5 039 1.00
D93879 614.5 616.0 040 1.56
MT-IU-024
D120855 498.7 500.2 041 1.20
D120856 500.2 501.7 042 1.50
D120857 501.7 503.2 043 1.40
D120859 503.2 504.3 044 1.10
D120862 504.3 505.5 045 0.82
D120864 505.5 506.9 046 1.42
D120865 506.9 508.4 047 1.00
D120866 508.4 510.1 048 1.90
D120867 510.1 511.9 049 1.96
D120868 511.9 513.7 050 1.60
D120869 513.7 515.5 051 1.30
D120870 515.5 517.3 052 1.56
D120871 517.3 519.1 053 1.84
D120872 519.1 520.9 054 1.64
D120873 520.9 522.4 055 1.54
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 142
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Hole Sample ID From (m) To (m) Metallurgy ID Weight (Kg)
D120874 522.4 523.9 056 1.20
D120875 523.9 525.4 057 1.36
D120876 525.4 526.7 058 1.10
D120878 526.7 528.1 059 1.26
D120879 528.1 529.6 060 1.42
D120880 529.6 531.0 061 1.12
D120881 531.0 531.5 062 0.60
D120882 531.5 532.0 063 0.60
D120884 532.0 532.7 064 0.50
D120885 532.7 534.2 065 1.80
D120886 534.2 535.7 066 1.34
D120887 535.7 537.2 067 1.66
D120888 537.2 539.0 068 1.84
D120889 539.0 540.7 069 1.82
D120890 540.7 542.4 070 1.86
D120740 268.1 269.6 071 2.82
D120741 269.6 271.0 072 2.68
D120742 271.0 272.5 073 2.88
D120743 272.5 273.6 074 2.34
D120744 273.6 274.7 075 2.22
D120745 274.7 275.7 076 2.08
MT-IU-017
D120746 275.7 276.7 077 2.04
D120747 276.7 277.7 078 1.76
D120748 277.7 279.0 079 2.62
D120749 279.0 280.3 080 2.62
D120750 280.3 281.6 081 2.54
D120751 281.6 282.9 082 2.76
D118372 241.8 243.2 083 2.48
D118373 243.2 244.6 084 1.34
D118374 244.6 246.0 085 2.60
D118375 246.0 247.3 086 2.22
D118376 247.3 248.8 087 2.46
D118377 248.8 250.2 088 2.68
D118378 250.2 251.6 089 2.20
D118379 251.6 253.0 090 2.50
D118381 253.0 254.4 091 2.48
D118382 254.4 255.7 092 1.92
D118383 255.7 257.0 093 2.50
D118384 257.0 258.3 094 2.38
D118385 258.3 259.6 095 2.54
D118386 259.6 260.8 096 1.74
MT-IU-013
D116944 203.7 205.0 097 2.56
D116945 205.0 206.0 098 1.94
D116946 206.0 207.0 099 1.96
D116947 207.0 207.5 100 0.80
D116948 207.5 208.2 101 1.64
D116949 208.2 209.0 102 1.66
D116950 209.0 209.8 103 1.38
D116951 209.8 210.6 104 1.66
D116952 210.6 211.7 105 1.86
D116954 211.7 212.9 106 2.54
D116955 212.9 213.9 107 1.86
MT-IU-018
D118757 228.5 229.7 108 1.96
D118758 229.7 231.1 109 1.84
D118759 231.1 232.4 110 2.12
D118760 232.4 233.8 111 2.40
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 143
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Hole Sample ID From (m) To (m) Metallurgy ID Weight (Kg)
D118761 233.8 235.2 112 2.38
D118762 235.2 236.4 113 2.62
D118764 236.4 237.6 114 1.20
D118765 237.6 239.0 115 2.34
D118766 239.0 240.5 116 2.38
MT-IU-015
D117389 254.6 256.0 117 2.14
D117390 256.0 257.5 118 2.32
D117391 257.5 258.5 119 1.42
D117392 258.5 260.0 120 1.76
D117393 260.0 260.7 121 1.04
D117395 260.7 262.2 122 2.52
D117398 262.2 263.7 123 2.18
D117399 263.7 264.4 124 1.06
D117400 264.4 265.9 125 1.66
D117401 265.9 266.9 126 2.28
D117402 266.9 267.8 127 1.66
D117403 267.8 269.2 128 2.22
D117404 269.2 270.0 129 1.26
MT-IU-004
D115136 182.2 183.3 130 1.82
D115137 183.3 184.3 131 1.84
D115139 184.3 185.2 132 2.22
D115140 185.2 186.4 133 1.76
D115141 186.4 187.4 134 1.68
Source: SRK, 2020
Table 13-17: Drill Holes and Intervals Used for the High Grade MDZ Composite
Hole Sample ID From (m) To (m) Metallurgy ID Weight (kg)
MT-1499-A
D105948 428 430 001 2.00
D105949 430 432 002 2.02
D105950 432 434 003 2.00
D105952 434 436 004 2.04
D105953 436 438 005 1.72
D105954 438 440 006 1.90
D105955 440 442 007 2.10
D105956 442 444 008 2.10
D105957 444 446 009 1.90
D105959 446 448 010 2.00
D105960 448 450 011 1.72
D105961 450 452 012 2.12
D105893 335 337 013 1.86
D105894 337 339 014 1.90
D105896 339 341 015 1.84
D105897 341 343 016 1.92
D105898 343 345 017 2.00
D105899 345 347 018 1.80
D105900 347 349 019 1.94
D105901 349 351 020 1.92
D105903 351 353 021 1.62
D105904 353 355 022 1.84
D105905 355 357 023 1.82
D105906 357 359 024 1.80
D105907 359 361 025 1.90
D105908 361 363 026 1.92
D105914 371 373 027 2.02
D105915 373 374 028 1.18
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 144
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Hole Sample ID From (m) To (m) Metallurgy ID Weight (kg)
D105916 374 376 029 2.18
D105917 376 378 030 2.16
MT-1390
D83285 181.25 183.25 031 3.40
D83286 183.25 185.25 032 3.40
D83287 185.25 186.1 033 1.54
D83288 186.1 187.55 034 2.28
D83289 187.55 189.55 035 3.42
D83291 189.55 190.45 036 1.56
D83292 190.45 192.45 037 3.40
D83293 192.45 194.45 038 3.18
D83294 194.45 196.25 039 3.14
D83296 196.25 196.9 040 1.24
D83297 196.9 197.5 041 0.80
Source: SRK, 2020
Table 13-18: Drill Core Holes and Intervals Used for the MDZ Deep Composite
Hole Sample ID From (m) To (m) Metallurgy ID Weight (kg)
MT-IU-024
D120892 544.2 546.0 001 1.52
D120893 546.0 547.7 002 1.10
D120894 547.7 549.6 003 1.22
D120896 549.6 551.4 004 1.24
D120897 551.4 553.1 005 1.60
D120898 553.1 554.8 006 1.58
D120900 554.8 556.6 007 1.92
D120901 556.6 558.4 008 1.84
D120902 558.4 560.2 009 1.50
MT-IU-026
D122079 603.4 605.3 062 2.02
D122080 605.3 607.2 063 1.72
D122081 607.2 609.1 064 1.82
D122082 609.1 611.0 065 2.00
D122083 611.0 612.9 066 1.98
D122084 612.9 614.8 067 1.66
D122085 614.8 616.4 068 1.50
D122086 616.4 617.6 069 1.14
D122087 617.6 618.8 070 1.10
MT-IU-27
D122780 584.2 585.7 106 1.62
D122781 585.7 587.1 107 1.50
D122782 587.1 588.7 108 1.56
D122783 588.7 590.2 109 1.62
D122784 590.2 591.8 110 1.72
D122785 591.8 593.6 111 1.96
D122786 593.6 595.5 112 1.96
D122787 595.5 597.4 113 1.78
D122788 597.4 599.3 114 2.04
D122789 599.3 601.3 115 2.22
D122790 601.3 603.2 116 2.02
MT-IU-031
D124720 610.2 612.1 141 2.12
D124721 612.1 613.9 142 2.04
D124722 613.9 615.8 143 2.04
D124723 615.8 617.6 144 2.04
D124724 617.6 619.5 145 0.20
D124726 619.5 621.3 146 2.26
D124727 621.3 623.0 147 1.96
Source: SRK, 2020
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 145
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 13-19: Drill Core Holes and Intervals Used for the Transition Composite
Hole Sample ID From (m) To (m) Metallurgy ID Weight (kg)
MT-IU-035
D125952 185.3 186.3 006 2.08
D125953 186.3 187.5 007 2.20
D125954 187.5 189.5 008 3.66
D125955 189.5 190.7 009 2.12
D125957 190.7 191.9 010 2.22
D125960 191.9 193.5 011 2.98
D125961 193.5 194.4 012 1.46
D125963 194.4 196.0 013 2.88
MT-IU-001
D101771 237.3 238.0 028 0.62
D101772 238.0 239.7 029 1.56
D101773 239.7 241.0 030 1.12
D101774 241.0 243.0 031 1.52
D101775 243.0 244.0 032 0.98
D101776 244.0 244.8 033 0.68
D101778 244.8 245.3 034 0.64
D101779 245.3 245.9 035 0.46
D101780 245.9 247.8 036 1.70
D101781 247.8 248.8 037 0.82
D101782 248.8 250.6 038 1.54
D101783 250.6 252.0 039 1.44
D101784 252.0 254.0 040 1.66
D101785 254.0 255.3 041 1.34
D101787 255.3 257.0 042 1.42
MT-IU-05
D109789 206.2 207.7 043 1.98
D109790 207.7 208.9 044 2.14
D109791 208.9 210.0 045 1.98
D109792 210.0 211.1 046 1.89
D109793 211.1 212.2 047 1.80
D109795 212.2 213.0 048 1.24
D109796 213.0 214.0 049 1.34
D109797 214.0 215.4 050 2.26
D109798 215.4 216.8 051 2.16
D109799 216.8 218.2 052 2.32
D109800 218.2 219.5 053 2.08
D109801 219.5 220.7 054 1.36
D109802 220.7 221.9 055 2.38
D109803 221.9 223.0 056 1.79
D109807 223.0 224.0 057 1.76
D109808 224.0 224.7 058 1.36
D109809 224.7 226.3 059 2.36
MT-IU-013
D116922 188.0 188.8 100 1.58
D116923 188.8 189.8 101 1.78
D116924 189.8 190.8 102 2.14
D116925 190.8 191.8 103 1.78
D116926 191.8 192.9 104 2.22
D116927 192.9 194.0 105 2.08
D116928 194.0 195.0 106 2.20
D116932 195.0 196.1 107 1.56
D116934 196.1 197.0 108 1.76
Source: SRK, 2020
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 146
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 13-20: Drill Core Holes and Intervals Used for Crushing (CWI) Testwork
Hole From (m) To (m) Weight (Kg)
MT-IU-006 182.6 183.3 3.28
250.2 251.5 2.84
MT-IU-015 289.5 241.0 5.44
MT-IU-017 237.6 239.0 5.00
282.7 283.9 4.30
MT-IU-018 241.8 243.1 4.92
Source: SRK, 2019
Source: SRK, 2019
Figure 13-4: Drill Hole Locations Used for Metallurgical Composites
13.2.2 Head Analyses
Head analyses for each of the MDZ metallurgical composites are shown in Table 13-21. Direct and
calculated head analyses for both gold and silver are provided. Calculated gold and silver analyses
are based on the average of all relevant tests and are considered a better indication of actual grades
due to the test sample size and number of tests conducted. The calculated gold and silver grades for
the master composite were 2.99 g/t Au and 3.3 g/t Ag. Calculated gold grades for the variability
composites ranged from 1.8 to 4.52 g/t Au and calculated silver grades ranged from 1.1 to 5.6 g/t Ag.
Calculated gold and silver grades for the Marmato mine composite were 3.15 g/t Au and 10.1 g/t Ag.
Cyanide soluble copper, organic carbon, mercury and arsenic were low in all test composites and will
not present any problem during processing. Total sulfur and sulfide sulfur analyses show that sulfur
occurs primarily as sulfide sulfur. Sulfide sulfur in the MDZ composites ranged from 0.82 to 1.54% S⁼.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 147
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Sulfide sulfur in the Marmato mine composite was reported at 8.62% S⁼. A multi-element ICP scan of
each test composite is provided in Table 13-22 and shows that there are no elements in the test
composites that would present special processing challenges.
Table 13-21: Head Analyses for Key Elements
Composite
Direct Assay
Calculated(1) S
(%) S⁼
(%) Cu CN
Sol (%) Corg
Hg (ppm)
As (ppm) Au
(g/t) Ag
(g/t) Au
(g/t) Ag
(g/t)
Master 3.73 2.9 2.99 3.3 1.22 1.15 0.004 <0.05 <0.3 <60
Low Grade 1.95 2.8 1.80 3.1 1.12 1.09 0.002 <0.05 <0.3 <60
Medium Grade
3.27 2.4 2.58 2.9 1.32 1.21 0.003 <0.05 <0.3 <60
High Grade 3.58 3.6 3.99 3.8 0.89 0.82 0.004 <0.05 <0.3 <60
Transition 2.50 3.7 2.82 5.6 1.74 1.54 0.004 <0.05 <0.3 <30
Deep 4.70 0.8 4.52 1.1 1.34 1.22 0.002 <0.05 <0.3 <30
Marmato 4.18 10.3 3.15 10.1 9.27 8.62 0.005 <0.05 <0.3 <100
Note: (1) Calculated: Average of all relevant tests Source: SGS, 2020
Table 13-22: Head Analyses and Multi-Element Scan on Each Test Composite
o Element Master Comp
Low Grade Comp
Med Grade Comp
High Grade Comp
Transition Comp
Deep Comp
Marmato Comp
o Au (S.M.), g/t
3.74 1.97 3.62 3.53 2.67 5.33 3.13
o Au 1, g/t 5.05 2.05 3.01 3.22 2.60 5.23 2.87
o Au 2, g/t 2.93 1.93 2.58 3.69 2.89 4.18 3.38
o Au 3, g/t 3.21 1.87 4.23 3.84 2.01 4.68 6.30
o Au Avg, g/t 3.73 1.95 3.27 3.58 2.50 4.70 4.18
o Au Calc., g/t
2.99 1.80 2.58 3.99 2.82 4.52 3.15
o Ag 1, g/t 2.7 2.9 2.4 4.2 4.0 0.9 10.9
o Ag 2, g/t 3.6 3 2.6 3.7 3.5 0.6 10.2
o Ag 3, g/t 2.5 2.5 2.1 3 3.7 0.8 9.9
o Ag Avg, g/t 2.9 2.8 2.4 3.6 3.7 0.8 10.3
o Ag Calc, g/t 3.3 3.1 2.9 3.8 5.6 1.1 10.1
o AuCN, g/t 3.2 2 2.7 4 1 1.2 1.4
o Cu NaCN, %
0.004 0.002 0.003 0.004 0.003 0.002 0.005
o S, % 1.22 1.12 1.32 0.89 1.74 1.34 9.27
o S=, % 1.15 1.09 1.21 0.82 1.54 1.22 8.62
o SO4, % <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 0.2
o S(o), % <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05
o CT, % 0.12 0.11 0.14 0.09 0.17 0.15 0.58
o C(g), % <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05
o TOC, % <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 0.14
o CO3, % 0.8 0.75 0.84 0.55 0.88 0.84 2.31
o Hg, g/t <0.3 <0.3 <0.3 <0.3 <0.3 <0.3 <0.3
o SG 2.74 2.75 2.75 2.73 2.71 2.70 2.93
o AI, g/t 79,500 80,200 77,200 78,800 75,700 80,600 61,100
o As, g/t <60 <60 <60 <60 <30 <30 <100
o Ba, g/t 1,240 1,330 1,200 1,210 1,240 1,110 766
o Be, g/t 1.09 1.06 1.03 1.1 1.06 1.16 0.67
o Bi, g/t <30 <30 <30 <30 <20 <20 <20
o Ca, g/t 17,800 17,000 17,200 17,100 12,800 16,700 16,700
o Cd, g/t <2 <2 <2 <2 <2 <2 30
o Co, g/t <20 <20 <20 <20 <8 <8 13
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 148
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
o Element Master Comp
Low Grade Comp
Med Grade Comp
High Grade Comp
Transition Comp
Deep Comp
Marmato Comp
o Cr, g/t 24 31 22 16 65 71 94
o Cu, g/t 317 233 251 387 249 210 218
o Fe, g/t 36,800 35,400 36,000 32,400 43,300 34,000 107,000
o K, g/t 24,600 26,800 23,100 24,400 26,300 17,400 32,600
o Li, g/t 8 9 8 8 <20 <20 <5
o Mg, g/t 8,310 8,240 7,980 8,240 8,180 8,070 6,190
o Mn, g/t 226 236 209 245 266 101 856
o Mo, g/t <20 <20 <20 <20 <5 <5 <6
o Na, g/t 32,300 30,900 31,300 34,100 27,100 38,100 8,320
o Ni, g/t <20 <20 <20 <20 <20 <20 <20
o P, g/t 792 815 783 807 848 812 662
o Pb, g/t <20 <20 <20 <20 <20 <20 128
o Sb, g/t <20 <20 <20 <20 <20 <20 <10
o Se, g/t <30 <30 <30 <30 <30 <30 <30
o Sn, g/t <30 <30 <30 <30 <40 <40 <20
o Sr, g/t 625 621 584 647 543 589 210
o Ti, g/t 2,450 2,500 2,400 2,500 2,580 2,460 1,840
o Tl, g/t <30 <30 <30 <30 <30 <30 <30
o U, g/t <20 <20 <20 <20 <30 <30 <20
o V, g/t 65 65 65 66 61 61 47
o Y, g/t 7.5 7.2 7.2 7.9 6.5 7.6 3.7
o Zn, g/t 40 45 35 44 51 21 1,300
Au (S.M) = Screened Metallics Au and Ag (calc) = Calculated head from test program Source: SGS Metallurgical Report, 2020
13.2.3 Mineralogy
Mineralogical studies were performed by Terra Mineralogical Services Inc (Terra) on the Master
composite and three variability composites from the MDZ. The results of this mineralogical
investigation are presented in Terra’s report, “Determination of Gold Deportment in Four Master
Composite Samples from the Top of the Marmato Deep Zone”, November 8, 2016. Key findings were
similar to the 2019 investigation and include:
• Native gold is the predominant gold carrier.
• The great majority of gold grains occur in locations that would be readily accessible by leaching
solutions (more than 98%).
• Gold grains are predominantly associated with silicate gangue minerals. Gold particles are not
often in direct contact with sulfides, yet very commonly pyrrhotite, chalcopyrite and bismuth
minerals are found in close vicinity to the gold mineralization.
• Pyrrhotite, subordinate pyrite, and minor chalcopyrite are the predominant sulfide minerals
occurring alongside the gold, silver, tellurium, and bismuth mineralization in the quartz/ silicate
veinlets.
• The average grain size of the gold particles identified was very fine grained (less than 6
microns), however, a small population of coarse gold particles was also identified.
13.2.4 Comminution
Comminution tests were conducted on the MDZ master composite, MDZ deep zone composite, three
MDZ sub-composites (low grade, medium grade and high grade) and at the Marmato mine composite.
The comminution tests included SAG Mill Comminution (SMC), SAG Mill Power Index (SPI) and Bond
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 149
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
ball mill work index (BWI) tests. In addition, Bond low impact crushing work index (CWI) and abrasion
(AI) tests were conducted on selected 1/2 HQ drill core pieces. The results of these tests are
summarized in Table 13-23.
Table 13-23: Summary of Comminution Test Results
o Sample Name Relative Density
JK Parameters(1) SPI®
(Min) CWI
(kWh/t) BWI
(kWh/t) AI
(g) A x
b ta(2) SCSE
o Low Grade Comp 2.65 24.5 0.24 12.4 137 - 18.9 -
o Med Grade Comp 2.65 25.3 0.25 12.2 140 - 17.7 -
o High Grade Comp 2.65 22.8 0.22 12.9 154 - 18.6 -
o Master Comp 2.63 24.0 0.24 12.5 146 - 18.7
o Transition Comp 2.66 27.8 0.27 11.7 146 - 21.1 -
o Mine (Marmato) Comp 3.12 141 1.17 6.3 23.2 - 12.4 -
o Deep Zone Comp 2.67 28.8 0.28 11.5 178 - 19.8 -
o CWI #1 - - - - - 7.9 - 0.470
o CWI #2 - - - - - 13.9 - 0.644
o CWI #3 - - - - - 10.5 - 0.582
o CWI #4 - - - - - 12.2 - 0.527
o CWI #5 - - - - - 9.2 - 0.642
Note: (1) JK Parameters are the result of the SMC test procedure (2) The ta value reported as part of the SMC procedure is an estimate Source: SGS Metallurgical Report, 2020
SMC Test
The results of the SMC tests are summarized in Table 13-24. The samples (excluding the Marmato
composite) were characterized as hard with respect to resistance to impact breakage, with A x b values
ranging from 23 to 29. The Marmato composite was much softer with A x b value of 141 (lower A x b
values indicate harder material). The samples were also characterized as hard with respect to
resistance to abrasion breakage, with an average ta value of 0.27 (excluding the Marmato composite).
Table 13-24: Summary of SMC Test Results
Sample Name
A b A x b Hardness Percentile
ta(1) DWI
(kWh/m3) Mia
(kWh/t)
Mih
(kWh/t) Mic
(kWh/t) SCSE
(kWh/t) Relative Density
o Low Grade Comp
90.8 0.27 24.5 95 0.24 10.6 28.7 23.3 12 12.4 2.65
o Med Grade Comp
93.8 0.27 25.3 94 0.25 10.4 28.2 22.8 11.8 12.2 2.65
o High Grade Comp
99 0.23 22.8 97 0.22 11.5 30.6 25.2 13 12.9 2.65
o Master Comp
100 0.24 24.0 96 0.24 11.1 30 24.5 12.7 12.5 2.63
o Transition Comp
86.8 0.32 27.8 90 0.27 9.5 26.1 20.7 10.7 11.7 2.66
o Mine (Marmato) Comp
60.7 2.33 141 6 1.17 2.2 6.9 4.1 2.1 6.3 3.12
o Deep Zone Comp
92.9 0.31 28.8 87 0.28 9.4 25.8 20.4 10.6 11/5 2.67
(1) The ta value reported as part of the SMC procedures is an estimate Source: SGS Metallurgical Report, 2020
SAG Power Index (SPI) Test
The results of the SPI tests are summarized in Table 13-25 along with CEET Crusher Index (Ci)
measurements. The SPI was used to measure the hardness of the ore while the Ci was used to predict
the SAG feed size distribution of the ore. The SPI ranged from 137 to 178 minutes, except for the
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 150
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Marmato composite, which had an SPI value of 23.2 minutes. The Ci ranged from 1.7 to 3.1 for the
composites (excluding the Marmato composite).
Table 13-25: Summary of SPI Tests
o Sample Name SGS ID CEET Crusher Index (Ci) SPI (Minute) Hardness Percentile
o Low Grade Comp 1-20597 2.2 137 82
o Med Grade Comp 1-20598 3.2 140 83
o High Grade Comp 1-20599 3.1 154 87
o Master Comp 1-20600 2.5 146 84
o Transition Comp 1-20906 3.0 146 85
o Mine (Marmato) Comp 1-20907 27.7 23 9
o Deep Zone Comp 1-20908 1.7 178 91
Source: SGS metallurgical report 2020
Bond Ball Mill Grindability Test
The results of Bond ball mill work index (BWI) tests using a 120 mesh (125 µm) closing screen are
summarized in Table 13-26. The BWI values for the MDZ composites range from 17.7 kWh/t to 19.8
kWh/t, which places them in the hard range of hardness. The Marmato mine ore BWI value was much
lower at 12.4 kWh/t.
Table 13-26: Summary of Bond Ball Mill Work Index (BWI) Tests
o Sample Name Mesh of
Grind F80
(µm) P80
(µm) Gram per
Revolution Work Index
(kWh/t) Hardness Percentile
o Low Grade Comp
120 2,566 96 1.05 18.9 88
o Med Grade Comp
120 2,525 98 1.15 17.7 82
o High Grade Comp
120 2,450 99 1.10 18.6 87
o Master Comp 120 2,426 98 1.09 18.7 87
o Transition Comp 120 2,552 98 0.93 21.2 95
o Mine (Marmato) Comp
120 2,313 98 1.81 12.4 29
o Deep Zone Comp
120 2,586 99 1.01 19.8 92
Source: SGS Metallurgical Report, 2020
Crushing Work Index and Abrasion Index Tests
Bond low impact crushing work index (CWI) and Bond Abrasion Index (AI) tests were conducted on
drill core pieces selected to provide spatial representivity through the MDZ deposit. The results of CWI
tests are summarized in Table 13-27 and show that the average CWI was 10.7 kWh/t and the average
SGS hardness percentile was 56 (medium range of hardness). The results of Bond Abrasion (AI) tests
are summarized in Table 13-28. The AI’s ranged from 0.470 to 0.644, which would classify the MDZ
ore as abrasive and will result in relatively high wear rates for liners and grinding media.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 151
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 13-27: Summary of Bond Low Energy Crushing Tests
Sample Name
Number of Specimens
Average CWI (kWh/t)
Hardness Percentile
Min CWI (kWh/t)
Max CWI (kWh/t)
Std Dev (kWh/t)
Relative Density
CWI #1 9 7.9 37 2.7 13.4 3.4 2.68
CWI #2 20 13.9 74 6.2 22.5 3.9 2.66
CWI #3 16 10.5 53 5.7 17.6 3.3 2.65
CWI #4 15 12.2 66 6.4 26.4 4.8 2.62
CWI #5 13 9.2 47 3.5 16.3 3.4 2.67 Source: SGS Metallurgical Report, 2020
Table 13-28: Summary of Abrasion Index Determinations
Sample Name AI (g) Percentile of Abrasivity
CWI Rocks 1 0.470 78
CWI Rocks 2 0.644 89
CWI Rocks 3 0.582 86
CWI Rocks 4 0.527 82
CWI Rocks 5 0.642 89
Source: SGS Metallurgical Report, 2020
13.2.5 Gravity Recoverable Gold (E-GRG) Testwork
The MDZ master composite was submitted for an extended gravity recoverable gold (E-GRG) test.
The three stage gravity test was completed at the SGS facility in Lakefield, Ontario and the results
were forwarded to FLSmidth (Knelson) for analysis and modelling. The E-GRG test involved sequential
gravity separation tests at successively finer grinds (P80 659, 257 and 98 µm) and the results are
shown in Table 13-29. An E-GRG value of 78.1% was determined for the MDZ master composite.
Table 13-29: Summary of E-GRG Test on MDZ Master Composite
Stage Grind Size (P80 µm) Mass (%) Au (g/t) Au Dist. (%)
Conc. Tail Conc. Tail Conc. Tail
1 659 0.39 1.03 319.2 2.12 39.1 0.7
2 257 0.37 1.19 202.4 1.57 23.3 0.6
3 98 0.40 96.6 125.9 0.68 15.7 20.6
Total 1.16 98.82 215.6 0.71 78.1 21.9
Note: Calc. Head: 3.21 g/t Au Source: SGS Metallurgical Report, 2020
The E-GRG value determined by SGS was used by FLSmidth (Knelson) to model gold recovery in the
MDZ process under the following conditions:
• Plant feed: 116 tph
• Circulating load: 300%
• Grind size (P80 µm): 105
• Conc. cycle time (min): 40
Table 13-30 provides a summary of the modeling results under two scenarios. The first scenario
included processing 45% of the cyclone underflow with a single Knelson concentrator (model QS40)
followed by leaching in an Acacia intensive leach reactor (model CS2000) which would result in an
estimated recovery of 51% of the E-GRG (78.1% per SGS) and result in about 40% overall gold
recovery to the gravity circuit. The second scenario included processing 90% of the ball mill discharge
to two Knelson concentrators (model QS48) followed by leaching in an Acacia intensive leach reactor
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 152
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
(model CS4000) which would result in an estimated recovery of 67% of the E-GRG and result in about
52% overall gold recovery to the gravity circuit. Estimated gold recoveries include Acacia leach
recoveries and therefore represent gold recovery to doré.
Table 13-30: Summary of E-GRG Modeling
Concentrator % Circ.
Load Treated
Tonnes Treated
GRG (1) Recovery (%)
Total Au Recovery (%)
Upgrade Method
Acacia Size
QS40 45 225 51.0 39.7 Acacia CS2000
2 x QS48 90 600 67.3 52.4 Acacia CS4000
Note: (1) Value represents percentage of 78.1% GRG determined by SGS Source: FLSmidth, 2019
13.2.6 Gravity Separation Testwork
Gravity separation testwork was conducted using a Knelson MD-3 laboratory concentrator operated
under standard laboratory conditions. The Knelson gravity concentrate was upgraded on a Mozley
Laboratory Mineral Separator (model C-800) targeting recovery of 0.05 to 0.1 wt% into the final Mozley
concentrate. The Mozley tailing was recombined with the Knelson tailing and used for downstream
cyanidation testwork. The grind size of about P80 212 µm was used for the first test (G1) on the MDZ
Master composite. A target grind size of P80 105 µm was used for the remaining gravity separation
tests. The results of all gravity separation tests are summarized in Table 13-31. Gold recovery from
the Master composite averaged 58.5%. The percent mass pull to the gravity concentrate ranged from
about 0.07 to 0.09% in these tests. Silver recovery ranged from about 16 to 21%. Gravity gold
recoveries for the variability test composites ranged from about 49% to 82%. Gravity silver recoveries
ranged from about 9% to 34%. These results demonstrate that a gravity separation circuit should be
considered in the overall process flowsheet and will serve to significantly reduce carbon handling in
the downstream CIP or CIL circuit.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 153
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 13-31: Summary of Gravity Concentration Testwork
Source: SGS Metallurgical Report, 2020
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 154
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
13.2.7 Gravity Concentrate Cyanidation
An intensive cyanide leach (ICN) test was conducted on the gravity concentrate produced from a 30
kg gravity concentration test without regrinding and used standard ICN test conditions that included:
• Cyanide concentration: 20 g/L NaCN
• LeachAid: 100 kg/t conc (0.12 kg/t ore)
• Retention Time: 48 hours
• pH: 11 to 11.5
The results of this test are presented in Table 13-32 and show that 99.7% of gold and 87.9% of the
silver contained in the gravity concentrate were extracted. Sodium cyanide consumption was 26.4 kg/t
concentrate (0.032 kg/t ore). LeachAid addition was equivalent to 0.12 kg/t ore which has not been
optimized.
Table 13-32: Summary of Intensive Leach Test on Gravity Concentrate
CN Test No.
Reagent Cons. Kg/t of CN Feed
Extraction % Residue (g/t) Calc. Head (g/t)
Au Ag
NaCN CaO 24 h 48 h 24 h 48 h Au Ag Au Ag
56 26.4 ~0 94.4 99.7 76.4 87.9 4.53 73.5 1,615 609
Source: SGS Metallurgical Report, 2020
13.2.8 Gravity Tailing Cyanidation Versus Grind Size
Whole-ore and gravity tailing cyanidation tests versus grind size were conducted on the MDZ Master
composite. Five of the tests were conducted on whole-ore sample and five were conducted on the G-1
gravity tailing. The grind size P80 targets ranged from about 212 to 53 µm. Test conditions for this
series included:
• Grind size target P80’s: 212, 150, 100, 75, and 53 µm
• Pulp Density: 45% solids (w/w)
• No pre-aeration
• Dissolved oxygen: 7 to 8 mg/L (air sparged)
• Pulp pH: 10.5 to 11 (maintained with lime)
• Cyanide Concentration: 0.5 g/L NaCN (maintained)
• Retention Time: 48 hours (with kinetic subsampling)
The results of gold extraction versus grind size is shown in Table 13-33 and silver extraction test results
are shown in Table 13-34. Whole-ore leach results indicate that gold extractions of about 91 to 95%
could be achieved over the grind size range tested. Gold extractions from the gravity tailing increased
from 89.5 to 95.4% with decreasing grind size. Overall (gravity + cyanidation) gold recoveries
increased from about 96 to 98%.
Cyanidation test results on the gravity tailing indicated that there was a clear linear relationship
between grind size and residue grade. An engineering review of these test results was completed and
a grind size of P80 105 µm was selected and used for all remaining cyanidation tests. There was no
clear relationship versus grind size for the whole-ore leach tests, likely due to the presence of small
amounts of coarse free gold. The test results indicated that an additional 0.1 g/t to 0.15 g/t gold will be
recovered with gravity concentration included in the flowsheet. Overall silver recovery was about 61%
at the target grind size.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 155
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 13-33: Summary of Cyanide Leach Test Gold Extractions Versus Grind Size
CN Test No.
Feed Size P80, µm
Reagent Cons. kg/t of CN Feed
Au Extraction % Gravity
% Au O’All % Au
Au Residue (g/t) Au Head (g/t)
NaCN CaO 2 h 6 h 12 h 18 h 24 h 30 h 48 h A B Avg Calc. Grav +
CN Direct
Whole Ore Tests
1 216 0.77 0.78 14.2 28.5 44.2 57.0 67.3 73.9 91.2 … 91.2 … … 0.27* 3.09 … 3.74
2 155 0.94 0.77 8.9 26.2 45.1 60.1 71.6 79.9 95.2 … 95.2 … … 0.16* 3.42
3 108 1.01 0.80 5.4 23.3 43.2 59.4 71.2 78.3 93.7 … 93.7 … … 0.20* 3.17
4 72 1.10 0.87 3.5 20.2 39.1 55.6 67.2 75.7 94.0 … 94.0 … … 0.23* 3.88
5 49 1.20 0.92 2.3 19.3 36.1 50.7 62.1 71.3 93.7 … 93.7 … … 0.23* 2.61
Gravity Tailing Tests (G-1)
6 211 0.63 0.88 19.7 40.5 60.4 70.1 76.8 81.2 89.5 58.8 95.7 0.15 0.11 0.13 1.23 3.02
7 148 0.70 0.75 18.2 41.9 64.9 75.1 83.1 87.1 92.4 96.9 0.10 0.10 0.10 1.32
8 107 0.87 0.80 10.9 37.2 62.8 74.7 84.1 89.2 94.3 97.7 0.07 0.08 0.08 1.31
9 79 0.99 0.85 8.1 37.6 61.6 73.4 85.8 90.4 95.8 98.3 0.05 0.05 0.05 1.20
10 52 1.01 0.85 5.6 30.8 54.2 64.5 76.3 84.9 95.4 98.1 0.06 0.06 0.06 1.31
*Average of 4 or 14 cuts, depending on test (all 30 g FA to extinction) Source: SGS Metallurgical Report, 2020
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 156
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 13-34: Summary of Cyanide Leach Test Silver Extractions Versus Grind Size
CN Test No.
Ag Extraction (%) Gravity
% Ag O’All %
Ag
Ag Residue
(g/t) Avg Head (g/t)
2 h 6 h 12 h 18 h 24 h 30 h 48 h Calc Grav +
CN Direct
Whole Ore Tests
1 19 30.4 37.4 44.6 46.5 50.4 57.0 … 57.0 1.3 3 … 2.9
2 12.2 29.4 38.6 42.7 46.1 48.2 55.9 … 55.9 1.4 3.2
3 6.3 28.5 38.7 43.9 46.8 49.7 58.6 … 58.6 1.2 2.9
4 3.9 26.4 36.2 43.5 47.7 51.5 58.8 … 58.8 1.3 3.2
5 … 24 33.0 38.7 40.8 46.7 56.8 … 56.8 1.4 3.2
Gravity Tailing Tests (G-1)
6 25.5 36.3 41.7 46.5 47.0 48.3 50.9 16.5 59.0 1.7 3.5 3.8
7 23.1 36.3 42.9 46.0 48.2 50.0 52.7 60.5 1.7 3.6
8 14.8 36.2 44.9 47.8 49.6 51.3 54.4 61.9 1.6 3.5
9 8.7 34.9 42.2 47.0 48.4 50.4 53.4 61.1 1.7 3.7
10 4.8 31.4 38.8 41.9 43.6 47.1 50.7 58.8 2.0 4.1
Source: SGS Metallurgical Report, 2020
13.2.9 Cyanidation Versus Cyanide Concentration and Pulp Density
A series of cyanidation tests were conducted to evaluate cyanide concentration over the range from
0.25 to 1 g/L NaCN (maintained) and leach slurry densities over the range from 45 to 55% solids (w/w).
The results of this test series are shown in Table 13-35. Gold extraction and leach residue grade were
independent of cyanide concentration above 0.5 g/L NaCN. At 0.5 g/L NaCN, overall gold extraction
(gravity + cyanidation) as reported at 97.4% and cyanide consumption was reported at 0.88 kg/t.
Cyanidation tests versus slurry density demonstrated that a slurry density of 50% solids (w/w) was
optimum. Above 50% solids gold extraction decreased significantly, most likely due to the increased
viscosity of the slurry.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 157
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 13-35: Gold Extraction Versus Cyanide Concentration and Slurry Density
CN Test No.
Feed Size P80, µm
NaCN (g/L)
% Solids (w/w)
Reagent Cons. kg/t of
CN Feed Au Extraction % Gravity
% Au O’All % Au
Au Residue (g/t) Au Head (g/t)
NaCN CaO 2 h 6 h 12 h 24 h 30 h 48 h A B Avg Calc Grav+CN Direct
11 105 0.25 45 0.45 0.97 8.7 26.0 49.8 71.0 78.4 89.8
58.8
95.8 0.14 0.12 0.13 1.27
3.02 3.74
12 105 0.5 45 0.88 0.87 9.4 36.8 64.7 87.4 90.3 93.6 97.4 0.09 0.08 0.09 1.32
13 106 0.75 45 1.17 0.84 14.8 44.1 71.9 88.4 91.1 93.9 97.5 0.08 0.08 0.08 1.31
14 108 1 45 1.41 0.78 11.1 49.7 76.9 91.5 94.2 94.2 97.6 0.07 0.08 0.08 1.29
15 106 0.5 50 0.79 0.88 8.9 37.5 62.4 84.0 85.7 92.6 97.0 0.09 0.09 0.09 1.21
16 108 0.5 55 0.88 0.81 8.7 30.7 55.3 75.5 82.0 88.8 95.4 0.16 0.13 0.15 1.29
Source: SGS Metallurgical Report, 2020
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 158
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
13.2.10 Cyanidation Versus Preaeration and Air Versus Oxygen Injection
Cyanidation tests on the gravity tailing were conducted to evaluate the impact of pre-aeration and the
use of air versus oxygen injection. During tests with air injection, dissolved oxygen levels were reported
at about 7 to 9 mg/L while dissolved oxygen levels during tests with oxygen injection were reported at
about 21 to 25 mg/L. The results of these tests are presented in Table 13-36. Gold extractions were
about 95% and residue grades were 0.06 g/t Au for all tests. Overall gold extractions (gravity +
cyanidation) were consistently close to 98%. The impact of oxygen on cyanide and lime consumptions
was significant for each pre-aeration time that was tested. The cyanide consumptions in tests
conducted with oxygen injection were approximately half as much as those tests conducted with air
injection. Lime consumptions were about 25% less. This test series demonstrated that pre-aeration
and oxygen injection resulted in lower cyanide consumption and significantly reduced leach retention
time. Gold extraction versus leach retention time for each test is shown in Figure 13-5.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 159
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 13-36: Summary Cyanidation Tests with Preaeration and Air Versus Oxygen Injection
CN Test No.
Feed Size
P80,µm
Pre-Air
h
CN Air or O2
Reagent Cons. kg/t of CN Feed
Au Extraction (%)
Gravity % Au
O’All %
Au
Au Residue (g/t) Au Head (g/t)
NaCN CaO 2 h 4 h 8 h 24 h 30 h 48 h A B Avg Calc. Grav
+ CN
Direct
17 103 8 Air 0.40 1.18 42.0 60.0 75.8 91.5 94.3 94.4
58.8
97.7 0.09 0.05 0.07 1.26
3.02 3.74
18 104 8 O2 0.19 0.78 54.8 72.0 83.2 94.4 94.8 95.2 98.0 0.06 0.06 0.06 1.26
19 105 4 Air 0.35 1.04 37.5 55.9 74.1 92.4 93.7 95.5 98.1 0.06 0.05 0.06 1.21
20 107 4 O2 0.16 0.75 60.8 75.6 85.3 95.8 97.4 95.0 97.9 0.06 0.06 0.06 1.20
21 106 2 Air 0.37 0.94 33.4 52.3 71.0 92.6 94.6 95.0 97.9 0.06 0.06 0.06 1.21
22 104 2 O2 0.15 0.70 57.8 72.4 85.8 95.1 94.7 95.1 98.0 0.06 0.06 0.06 1.23
Source: SGS Metallurgical Report, 2020
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 160
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SGS Metallurgical Report, 2020
Figure 13-5: Gold Extraction Versus Leach Retention Time for Air and Oxygen Injection
13.2.11 Cyanidation Versus Cyanide Attenuation and Pulp Density
A series of leach tests were conducted at slurry densities of 45, 50 and 55% solids at an initial cyanide
concentration of 0.5 mg/L NaCN which was allowed to attenuate to 0.2 mg/L. Tests included pre-
aeration (4 hours) and oxygen injection to maintain dissolve oxygen levels at about 20 to 25 mg/L. The
results of these tests were similar and are summarized in Table 13-37. Gold extraction ranged from
94.7 to 95.6% and overall gold extractions (gravity + cyanidation) were about 98% for all tests. Gold
residue grades were 0.05 to 0.07 g/t. Allowing cyanide to attenuate throughout the test significantly
reduced sodium cyanide consumption to 0.13 to 0.15 kg/t. The leach kinetic results are shown in Figure
13-6 and demonstrate that gold extraction was complete after about 24 hours of leaching.
0
10
20
30
40
50
60
70
80
90
100
0 5 10 15 20 25 30 35 40 45 50
Au E
xtr
action,
%
Retention Time, h
CN-8, No PA, Air
CN-12, No PA, Air
CN-17, 8 h PA, Air
CN-18, 8 h PA, O2
CN-19, 4 h PA, Air
CN-20, 4 h PA, O2
CN-21, 2 h PA, Air
CN-22, 2 h PA, O2
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 161
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 13-37: Summary of Cyanide Attenuation and Slurry Density Tests
CN Test No.
Feed Size P80, µm
% Solids (w/w)
Reagent Cons. kg/t of CN Feed
Au Extraction (%) Gravity
% Au O’All % Au
Au Residue (g/t) Au Head (g/t)
NaCN CaO 2 h 4 h 8 h 24 h 30 h 48 h A B Avg Calc Grav +
CN Direct
23 107 45 0.13 0.76 67.0 76.1 86.1 95.4 96.5 95.6
58.8
98.2 0.05 0.06 0.06 1.25
3.02 3.74 24 104 50 0.15 0.76 66.9 76.6 85.7 95.4 95.8 95.6 98.2 0.05 0.05 0.05 1.25
25 103 55 0.15 0.74 63.8 73.0 83.4 94.5 95.0 94.7 97.8 0.07 0.06 0.07 1.24
Source: SGS Metallurgical Report, 2020
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 162
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SGS Metallurgical Report, 2020
Figure 13-6: Gold Extraction Versus Leach Retention Time
13.2.12 “Hard Stop” Retention Time Tests
“Hard stop” retention time tests were conducted at 18, 24, 30 and 36 hours. All tests were conducted
under the following conditions:
• Grind size P80: 105 µm
• Pulp density: 50% solids (w/w)
• Pre-aeration: 4 hours
• O2 injection: 20 to 25 mg/L dissolved O2
• Pulp pH: 10.5 to 11 (maintained with lime)
• Cyanide Conc: 0.5 g/L NaCN (allowed to attenuate to 0.2 g/L)
The results of these tests are shown in Table 13-38 and confirm that with the use of oxygen a retention
time of 24 hours is sufficient to achieve maximum gold extraction. Gold extractions ranged from about
93 to 94% with leach residues ranging from 0.07 to 0.08 g/t Au. Overall gold extraction (gravity +
cyanidation) was 97.7% after 24 hours and sodium cyanide consumption was reported at 0.08 kg/t.
An optimized leach retention time of 24 hours was selected based on these test results.
0
10
20
30
40
50
60
70
80
90
100
0 5 10 15 20 25 30 35 40 45 50
Au E
xtr
action,
%
Retention Time, h
CN-23
CN-24
CN-25
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 163
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 13-38: Summary of Hard Stop Leach Retention Time Tests
Source: SGS Metallurgical Report, 2020
13.2.13 Carbon-In-Leach (CIL) Tests
Carbon-in-leach (CIL) tests were conducted at leach retention times of 24, 30 and 36 hours to further
evaluate retention time. The results of these tests are summarized in Table 13-39 and confirmed that
the gold in solution will load onto activated carbon and that the MDZ ore is not preg-robbing. One gram
of activated carbon was added to each bottle and gold loadings of about 950 g/t Au onto the carbon
were reported.
Table 13-39: Summary of CIL Tests Versus Retention Time with Optimized Leach Conditions
Source: SGS Metallurgical Report, 2020
13.2.14 Variability Tests
Testwork to evaluate gravity concentration and cyanidation of the gravity tailing on each of the
variability composites was conducted under optimized conditions which included:
• Grind size P80: 105 µm
• Pulp density: 45% solids (w/w)
• Pre-aeration: 4 hours
• O2 injection: 20 to 25 mg/L dissolved O2
• Pulp pH: 10.5 to 11 (maintained with lime)
• Cyanide Conc: 0.5 g/L NaCN (allowed to attenuate to 0.2 g/L)
• Retention time: 24 hours
Tests were conducted in duplicate and the results of gold extraction are shown in Table 13-40 and the
results of silver extraction are shown in Table 13-41. Gold recovery into the gravity concentrate ranged
from 60.3 to 82% for the MDZ variability composites with the highest gravity gold recovery being
reported for the deeper MDZ Deep variability composite. Gold extraction from the MDZ gravity tailings
ranged from 91.4 to 92.8% and overall recovery (gravity + cyanidation) ranged from 97.4 to 98.5%
gold. Gold recovery from the Marmato mine variability composite into the gravity concentrate was
reported at 48.7% and gold extraction from the Marmato gravity tailing was 73.7% with an overall gold
CN Feed NaCN % Pre- Air Gravity O'All
Test Size g/L Solids Air or % % Grav
No. P80, µm (w/w) h O2 NaCN CaO Au Au A B Avg. +CN
27 105 0.5 - 0.2 50 4 O2 0.06 0.67 18 h 93.3 58.8 97.2 0.08 0.07 0.08 1.12 3.02 3.74
28 109 0.5 - 0.2 50 4 O2 0.08 0.72 24 h 94.3 97.7 0.07 0.07 0.07 1.23
29 104 0.5 - 0.2 50 4 O2 0.09 0.77 30 h 93.5 97.3 0.08 0.08 0.08 1.23
30 109 0.5 - 0.2 50 4 O2 0.09 0.78 36 h 94.1 97.6 0.07 0.08 0.08 1.26
%
Extraction
AuReagent Cons.Au Residue, g/t
Au Head, g/t
kg/t of CN Feed Calc. Direct
CN Feed NaCN % Pre- Air Gravity O'All
Test Size g/L Solids Air or % % Grav
No. P80, µm (w/w) h O2 NaCN CaO Au Au A B Avg. +CN
31 103 0.5 - 0.2 50 4 O2 0.08 0.70 24 h 92.0 58.8 96.7 0.08 0.10 0.09 1.13 3.02 3.74
32 110 0.5 - 0.2 50 4 O2 0.10 0.67 30 h 92.8 97.0 0.09 0.09 0.09 1.24
33 108 0.5 - 0.2 50 4 O2 0.10 0.76 36 h 92.3 96.8 0.08 0.09 0.09 1.17
Reagent Cons. AuAu Residue, g/t
Au Head, g/t
kg/t of CN Feed Extraction Calc. Direct
%
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 164
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
recovery of 86.5%. Overall silver recovery from the MDZ variability composites ranged from 47.4 to
56.4% and averaged 54.5%. Overall silver recovery from the Marmato mine composite was 70.1%.
Table 13-40: Variability Composites – Gold Recovery Under Optimized Conditions
Source: SGS Metallurgical Report, 2020
Sample CN Feed Au Gravity O'All
Test Size Extr'n % % % Calc. Grav Direct
No. P80, µm NaCN CaO 24 h Au Au A B Avg. +CN
Low Grade 34 104 0.09 0.78 91.4 61.5 96.7 0.06 0.06 0.06 0.70 1.80 1.97
Comp (G-3) 35 103 0.10 0.75 92.0 96.9 0.06 0.05 0.06 0.69
91.7 96.8 0.06 0.70
Med Grade 36 110 0.08 0.71 91.6 66.7 97.2 0.06 0.08 0.07 0.83 2.58 3.62
Comp (G-4) 37 114 0.09 0.70 92.7 97.6 0.07 0.06 0.07 0.89
92.2 97.4 0.07 0.86
High Grade 38 112 0.13 0.63 92.3 60.3 96.9 0.13 0.11 0.12 1.56 3.99 3.53
Comp (G-5) 39 114 0.14 0.62 91.3 96.5 0.17 0.11 0.14 1.61
91.8 96.7 0.13 1.59
Deep Zone 48 104 0.09 0.64 91.4 82.0 98.5 0.08 0.06 0.07 0.81 4.52 5.33
Comp (G-7) 49 107 0.09 0.61 91.4 98.5 0.06 0.08 0.07 0.82
91.4 98.5 0.07 0.82
Transition 50 105 0.09 1.00 92.5 63.2 97.2 0.06 0.09 0.08 1.02 2.77 2.67
Comp (G-8) 51 105 0.09 0.99 93.1 97.5 0.07 0.07 0.07 1.02
92.8 97.4 0.08 1.02
New Marmato 54 100 0.09 1.40 74.4 48.7 86.9 0.40 0.42 0.41 1.60 3.15 3.13
Comp (G-12) 55 98 0.12 1.46 72.9 86.1 0.42 0.47 0.45 1.64
73.7 86.5 0.43 1.62
Au Head, g/tReagent Cons.Au Residue, g/t
kg/t of CN Feed
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 165
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 13-41: Variability Composites – Silver Recovery Under Optimized Conditions
Source: SGS Metallurgical Report, 2020
13.2.15 CIP Modelling Testwork
Carbon-in-pulp (CIP) modeling was conducted by SGS in order to establish the design parameters
and predict operational performance for the CIP circuit. SGS’s approach to CIP modelling involves
conducting batch gold leaching and carbon adsorption tests with representative samples of ore or
concentrate in contact with commercially available activated carbon or plant carbon. The rate of
leaching is determined in a traditional bottle roll experiment, by taking timed samples of slurry from the
bottle (typically over a 72-hour period) and analyzing the solution phase for gold. The rate of absorption
of the leached gold onto activated carbon is then determined by adding carbon to the same leach
slurry and taking further timed samples of slurry over a further 72-hour period in the same rolling bottle
and analyzing the solution phase for gold. Gold on the carbon is determined by mass balancing the
solution phase, while gold in the leach residue is determined by analysis at the end of the test, to
produce an overall gold balance for the test. As a check, the final test carbon is also assayed for gold.
The leaching and carbon adsorption kinetic data were then fitted to carbon adsorption modeling
equations which generates profiles of gold in solution, on the carbon and in the leach residue across
a series of leaching and adsorption tanks in which carbon is advanced counter-current to the flow of
slurry. The CIP models allow a number of operating parameters to be varied systematically. This allows
the optimum design criteria for the plant to be established. CIP circuit parameters that were modeled
include:
CN Ag Gravity O'All Ag
Test Extr'n % % % Res. Calc. Grav Direct
No. 24 h Ag Ag g/t +CN
34 38.6 15.0 47.8 1.6 2.6 3.1 2.8
35 37.6 47.0 1.7 2.7
38.1 47.4 1.7 2.7
36 47.9 21.2 58.9 1.2 2.3 2.9 2.4
37 48.5 59.4 1.2 2.3
48.2 59.2 1.2 2.3
38 44.5 21.7 56.5 1.6 2.9 3.8 3.6
39 43.3 55.6 1.7 3.0
43.9 56.1 1.7 2.9
48 33.4 34.3 56.2 <0.5 0.8 1.1 0.8
49 34.0 56.6 <0.5 0.8
33.7 56.4 <0.5 0.8
50 41.8 17.0 51.7 2.0 3.4 4.5 3.7
51 45.9 55.1 2.2 4.1
43.9 53.4 2.1 3.8
54 37.8 8.7 72.3 5.6 9.0 10.1 10.3
55 35.5 67.9 6.1 9.5
36.7 70.1 5.9 9.3
Ag Head, g/t
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 166
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
• The percentage of the leachable gold that is in solution prior to the first carbon adsorption tank
(100% generally assumed for CIP designs)
• The number of carbon adsorption tanks
• The volume of the adsorption tanks and pulp residence time
• The amount and concentration of carbon in each adsorption tank
• The carbon advance rate through the CIP plant, which yields the target gold loading on the
carbon going to elution
• The target gold concentration in the solution exiting the last carbon adsorption tank
• The amount of gold remaining on the eluted carbon that is recycled to the last adsorption tank
Base-case circuit modeling included the following design parameters:
• Process plant feed rate: 181 tph
• Slurry feed rate: 288 m3/hr
• Leach retention time: 24 hours
• Number of Leach tanks: 3
• Adsorption tank size: 288 m3
• CIP stages: 6
• Au on stripped carbon: 50 g/t
• Carbon advance rate: 3 t/d
The results of the CIP modeling are presented in Table 13-42 and Table 13-43. Scenario 1 represents
the base-case and other scenarios show the impact of sequential changes in CIP circuit operating
parameters. The data shown in Table 13-42 presents all the key process operating parameters and
the red highlighted values indicate the parameter that has been changed in each scenario. The target
gold barren solution concentration is 0.01 mg/L or less. Key points from the CIP modeling include the
following:
• Scenario 1:
o In Scenario 1 (Base-case) the carbon inventory was 7.2 t per tank, which yielded a carbon
concentration of 25 g/L and the carbon advance rate was set at 3 t/day, which resulted in
a gold loading on the carbon of 1,673 g/t. Soluble gold losses of 0.004 mg/L were predicted
and gold extraction from solution onto the carbon was 99.5% with target barren solution
losses of about 0.01 mg/L achieved in the fifth CIP stage.
• Scenarios 2 to 5:
o Scenarios 2 to 5 illustrated the impact of varying the amount of carbon in the circuit over
the range from 15 to 40 g/L. The barren solution losses increased slightly when decreasing
the amount of carbon in the circuit, and as expected, the gold lock-up (kg of gold)
increased with higher carbon inventories.
• Scenario 6:
o Scenario 6 investigated the impact of decreasing the slurry retention time in each CIP tank
to 30 minutes. This increased the concentration of carbon in each stage to 40 g/L (same
as Scenario 5) but the amount of carbon in each stage was the same as Scenario 2. The
results from Scenario 6 and Scenario 2 were identical, which shows the performance in
CIP is controlled by the amount of carbon in each tank, not the carbon concentration.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 167
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
• Scenarios 7 and 8:
o Scenarios 7 and 8 were identical to Scenario 6, except that the amount of carbon
transferred to elution each day was decreased to about 2.3 to 2.6 tonnes. As a result, the
loading of gold on the carbon in the first CIP tank increased to 2,156 g/t and 1,923 g/t,
respectively This indicates the capacity of the elution and regeneration circuits could be
reduced from the current design of 3 t/day to 2 t/day with minimal impact on gold recovery.
• Scenarios 9 and 10:
o Scenarios 9 and 10 were run using a 4 t elution circuit since the design engineer (Ausenco)
had noted that a 4 t circuit may be considered in the design. The slurry residence times in
the CIP stages were set at 1 hour and 0.5 hours, respectively in these scenarios. Barren
solution losses were below 0.006 mg/L in both scenarios.
The results from the CIP modelling study were very positive and excellent results can be expected
when processing the Marmato MDZ ore in a standard CIP circuit design. The optimized circuit design
based on the results in this study were as follows:
• Leach retention time of 24 hours
• CIP retention time of six hours (one hour per stage)
• Carbon inventory 6 t/tank (36 t total)
• Elution/regeneration plant capacity 3 t/day. A smaller carbon throughput of 2 t/day could be
considered if there are no plans to increase plant capacity in the future
• Eluted carbon concentration target, 50 g/t
Silver and Copper Carbon Loading
The estimated silver and copper loadings were calculated by SGS using equilibrium isotherm data.
Silver loading is estimated at about 1,400 g/t and the loaded carbon would contain about 0.2% copper.
Based on an expected concentration of silver in solution in the feed to CIP of 1.0 to 1.5 mg/L and
barren solution losses of about 3 mg/L, the extraction efficiency of silver onto carbon is estimated at
about 70 to 80%. Although copper loading on the carbon could be significant and similar to gold and
silver loading on a g/t basis, the amount of leached copper that is extracted in CIP is trivial (less than
1%).
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 168
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 13-42: Modeled Design Parameters for a Multi-stage CIP Adsorption Circuit
* Ramp up time (days) = Gold lock-up (kg)/Gold Produced (kg/day) Source: SGS metallurgical report 2020
Different Scenarios 1 2 3 4 5 6 7 8 9 10
Inputs
Slurry feed rate (m3/h) 288 288 288 288 288 288 288 288 288 288
Solids (t/h) 181 181 181 181 181 181 181 181 181 181
Solution (m3/h) 221 221 221 221 221 221 221 221 221 221
Consider Leach after Carbon addition N N N N N N N N N N
Gold on stripped carbon, g/t 50 50 50 50 50 50 50 50 50 50
Adsorption tank(s) size, m3 288 288 288 288 288 144 144 144 288 144
Carbon frequency advance (% in 24 hours) 42% 52% 69% 35% 26% 52% 40% 45% 35% 69%
Leaching
Au leached before Carbon addition 93.9% 93.9% 93.9% 93.9% 93.9% 93.9% 93.9% 93.9% 93.9% 93.9%
Leach time before Carbon addition (h) 24 24 24 24 24 24 24 24 24 24
Leach only total tankage (m3) 6912 6912 6912 6912 6912 6912 6912 6912 6912 6912
Number of Leaching tanks 3 3 3 3 3 3 3 3 3 3
Volume of Leaching tanks (m3) 2304 2304 2304 2304 2304 2304 2304 2304 2304 2304
CIP/CIL
Leach Kinetic Constant (ks) 0.867 0.867 0.867 0.867 0.867 0.867 0.867 0.867 0.867 0.867
Model output kinetic constant (k) 0.003 0.003 0.003 0.003 0.003 0.003 0.003 0.003 0.003 0.003
Model output equilibrium constant (K) 20793 20793 20793 20793 20793 20793 20793 20793 20793 20793
Product of equilibrium and kinetic constants (kK) 69 69 69 69 69 69 69 69 69 69
Number of stages 6 6 6 6 6 6 6 6 6 6
Total CIP/CIL volume (m3) 1728 1728 1728 1728 1728 864 864 864 1728 864
Slurry residence time in each adsorption tank (h) 1.0 1.0 1.0 1.0 1.0 0.5 0.5 0.5 1.0 0.5
Gold grade in residue (g/t) 0.074 0.074 0.074 0.074 0.074 0.074 0.074 0.074 0.074 0.074
Gold in final barren solution (mg/L) 0.004 0.006 0.012 0.004 0.003 0.006 0.007 0.007 0.003 0.006
Gold in loaded carbon (g/t) 1673 1669 1660 1675 1676 1669 2156 1923 1269 1265
Carbon residence time/stage (h) 58 46 35 69 92 46 60 53 69 35
Carbon Concentration (g/L pulp) 25 20 15 30 40 40 40 40 40 40
Equivalent transferred carbon unit flowrate (kg/h) 125 125 125 125 125 125 96 108 167 167
Daily carbon transfer / batch elution capacity (kg/day) 3000 3000 3000 3000 3000 3000 2304 2592 4000 4000
Carbon Inventory per stage (kg) 7200 5760 4320 8640 11520 5760 5760 5760 11520 5760
Carbon inventory all stages (tons) 43 35 26 52 69 35 35 35 69 35
Gold Lock-Up on Carbon (kg) 20.4 17.3 14.0 23.5 29.5 17.3 22.5 20.0 22.6 13.2
CIP/CIL Gold recovery per day (g/day) 4869 4858 4829 4874 4877 4858 4853 4855 4878 4861
Overall Gold Leaching Efficiency 93.9% 93.9% 93.9% 93.9% 93.9% 93.9% 93.9% 93.9% 93.9% 93.9%
Overall Gold Adsorption Efficiency 99.5% 99.3% 98.7% 99.6% 99.7% 99.3% 99.2% 99.2% 99.7% 99.4%
Overall Gold Recovery 93.4% 93.2% 92.6% 93.5% 93.6% 93.2% 93.1% 93.1% 93.6% 93.3%
Upgrading ratio 1816 1812 1801 1817 1819 1812 2340 2087 1378 1373
Circuit filling time - slurry (days) 1.3 1.3 1.3 1.3 1.3 1.1 1.1 1.1 1.3 1.1
Ramp-up time (days) * 4.2 3.6 2.9 4.8 6.1 3.6 4.6 4.1 4.6 2.7
* Ramp-up time (days) = Gold lock-up (kg) / Gold Produced (kg/day)
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 169
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 13-43: Modeled Gold Concentrations in Solids, Solution and Carbon in a Multi-Stage CIP Circuit
Source: SGS Metallurgical Report, 2020
13.2.16 Cyanide Destruction Testwork
The cyanidation leach residue produced under optimized leach conditions from the MDZ Master
composite was used for cyanide destruction testwork using the industry-standard SO2/Air
detoxification process. The objective was to reduce weak acid dissociable cyanide (CNWAD) in the
residue from about 200 mg/L CNWAD to <1 mg/L CNWAD.
The chemical reaction for the oxidation of (CNWAD) using sodium metabisulphite (Na2S2O5) as the
source of SO2) and air (source of oxygen) is as follows:
2 CN + Na2S2O5 + 2 O2 + 2 OH→2 CNO + Na2SO4 + SO42 + H2O
This reaction is catalyzed by the presence of copper. The feed usually contains some copper (as the
copper cyano complex), and if required, additional copper is added as copper sulfate. Hydrated lime
is added to the reactor to provide the OH- ion for the above reaction. The cyanate ion (CNO-) is unstable,
and slowly hydrolyzes to ammonium and carbonate ions:
CNO- + 2 H2O→CO32- + NH4
+
The carbonate ion precipitates as calcium carbonate and a small amount of the ammonium ion is found
to form ammonia (NH3) which eventually escapes from the solution as NH3 gas.
The cyanide destruction tests were conducted on the leach residue at a slurry density of 45% solids
(w/w). The pH target for the tests was approximately 8.5. All tests were conducted at room temperature
with SO2 additions (as sodium metabisulphite) of 7 to 7.8 g SO2/g CNWAD and retention times that
ranged from about 60 to 90 minutes. The results of continuous detoxification tests are shown in Table
Interstage data 1 2 3 4 5 6 7 8 9 10
Scenario
Gold in ore/stage residues (g/t)
Feed head grade 1.200 1.200 1.200 1.200 1.200 1.200 1.200 1.200 1.200 1.200
Leach tank discharge 0.074 0.074 0.074 0.074 0.074 0.074 0.074 0.074 0.074 0.074
Adsorption stage 1 discharge 0.074 0.074 0.074 0.074 0.074 0.074 0.074 0.074 0.074 0.074
Adsorption stage 2 discharge 0.074 0.074 0.074 0.074 0.074 0.074 0.074 0.074 0.074 0.074
Adsorption stage 3 discharge 0.074 0.074 0.074 0.074 0.074 0.074 0.074 0.074 0.074 0.074
Adsorption stage 4 discharge 0.074 0.074 0.074 0.074 0.074 0.074 0.074 0.074 0.074 0.074
Adsorption stage 5 discharge 0.074 0.074 0.074 0.074 0.074 0.074 0.074 0.074 0.074 0.074
Adsorption stage 6 discharge 0.074 0.074 0.074 0.074 0.074 0.074 0.074 0.074 0.074 0.074
Gold on carbon (g/t)
Adsorption stage 1 discharge 1673 1669 1660 1675 1676 1669 2156 1923 1269 1265
Adsorption stage 2 discharge 642 712 803 588 511 712 944 831 375 531
Adsorption stage 3 discharge 264 318 397 227 180 318 425 372 137 238
Adsorption stage 4 discharge 126 156 205 107 86 156 203 179 73 122
Adsorption stage 5 discharge 75 89 114 68 60 89 108 98 56 76
Adsorption stage 6 discharge 57 61 71 54 52 61 67 64 51 57
Stripped carbon feed to last stage 50 50 50 50 50 50 50 50 50 50
Gold in solution (mg/L)
Leach tank discharge 0.921 0.921 0.921 0.921 0.921 0.921 0.921 0.921 0.921 0.921
Adsorption stage 1 discharge 0.339 0.380 0.438 0.308 0.263 0.380 0.395 0.388 0.248 0.368
Adsorption stage 2 discharge 0.126 0.158 0.208 0.104 0.076 0.158 0.170 0.164 0.068 0.148
Adsorption stage 3 discharge 0.047 0.066 0.100 0.036 0.023 0.066 0.074 0.070 0.020 0.060
Adsorption stage 4 discharge 0.019 0.028 0.048 0.013 0.008 0.028 0.033 0.031 0.007 0.025
Adsorption stage 5 discharge 0.008 0.013 0.024 0.006 0.004 0.013 0.015 0.014 0.004 0.011
Adsorption stage 6 discharge 0.004 0.006 0.012 0.004 0.003 0.006 0.007 0.007 0.003 0.006
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 170
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
13-44. The CNpicric assay in three of these four tests was less than 10 mg/L CNWAD. CNWAD
concentrations of less than 1 mg/L were only achieved after additional time (or aging) at the end of the
tests.
Upon completion of the program it was determined the following operating conditions will achieve a
discharge CNWAD concentration of less than10 mg/L.
• 45% solids (w/w)
• Approximately 7 g equivalent SO2 per gram CNWAD
• Approximately 20 mg/L copper addition
• pH 8.5 – lime added as needed (~1.5 kg/t)
• Approximately 80-minute retention time
In order to achieve a CNWAD concentration of <1 mg/L, the design will need to include holding (or aging)
the detoxified leach residue to achieve the discharge target.
Table 13-44: Summary of Cyanide Destruction Tests Conducted on Master Composite Leach Residues
… No Sample Submitted for Assays (1) Cu added using CuSO4 5H2O, SO2 Added Using Sodium Metabisulphite * 2 Stage Reactor Setup (2 x 60 Min Retention Time) ** 7 Day Aged Samples Rerun for Picric Acid in Lab Source: SGS Metallurgical Report, 2020
13.2.17 Tailing Thickening
Tailing thickening testwork was conducted by both SGS and Outotec. The process design engineer
(Ausenco, Section-17) used Outotec’s thickening testwork for process design purposes and, as such,
only Outotec’s test results are presented. Details of SGS’s thickener test results can be found in their
2020 report referenced earlier.
Outotec conducted high rate thickener testwork on detoxed leach tailings generated from MDZ master
and transition composites that were produced using optimized process parameters. The results of
Outotec’s thickener testwork are presented in their report No 32491 dated 2/21/2020. The testwork
was conducted using Outotec’s bench scale 99 mm diameter thickener test unit with Magnafloc 10 as
the flocculant which is a high molecular weight slightly anionic flocculant. All rheological measurements
were carried out using a Thermo Haake VT550 rheometer and an “OK600” 4 blade vane. A constant
Test Test Reten. Product (Solution Phase) Reagent Addition
Dur. Time pH CNT Cu Fe g/g CNWAD g/L Feed Pulp kg/t Solids
Ana. Picric Aged SO2 Lime Cu(1)SO2 Lime Cu(1)
SO2 Lime Cu(1)
Lab Acid Picric** Equiv. Equiv. Equiv.
min min mg/L mg/L mg/L mg/L mg/L mg/L
CND 3 180 60 8.5 … … 0.38 … … … 5.07 2.71 0.150 0.79 0.42 0.023 1.26 0.67 0.037
Continuous
3-1 60 60 8.5 … … 52.6 … … … 5.14 2.85 0.050 0.87 0.49 0.009 1.27 0.71 0.012
3-2 120 60 8.5 2.61 <0.1 12.5 <0.1 27 2.5 7.81 4.58 0.150 1.27 0.76 0.025 1.93 1.13 0.037
3-3 180 79 8.5 2.39 <0.1 7.86 <0.1 16 1.3 7.09 7.02 0.150 1.13 1.15 0.023 1.76 1.74 0.037
3-4 181 84 8.5 2.83 <0.1 8.34 <0.1 18 1.5 7.00 5.53 0.240 1.09 0.88 0.038 1.73 1.37 0.059
3-5* 240 58 8.5 0.27 <0.1 1.26 … 6.8 0.4 7.26 3.91 0.150 1.13 0.62 0.024 1.80 0.97 0.037
… No sample submitted for assays(1)Cu added using CuSO4 5H2O, SO2 added using sodium metabisulphite
* 2-Stage Reactor setup (2 x 60 min retention time)
** 7 day aged samples rerun for picric acid in lab
…
Batch
Feed (CN-47) … … … … … …… … 15.8 1.13 … …225 200
CNWAD by
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 171
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
shear rate of 0.1 sec-1 was used. For each dynamic test underflow sample, a simple un-sheared vane
yield stress was measured.
The tailings samples used for the tailing thickener testwork were characterized as follows:
Master Comp Transition Comp
Density (g/mL): 1.36 1.38
Solids SG (t/m3): 2.66 2.66
pH: 8.70 8.90
Particle size (P80 µm): 107.7 103.3
The results of high rate thickener tests conducted on the MDZ Master composite are summarized in
Table 13-45 and the results of thickener tests conducted on the MDZ Transition composite are
summarized in Table 13-46. An underflow density of 63.5% solids was achieved for the Master
composite tailing sample using Magnafloc10 at a dosage of 50 g/t, which resulted in a flux of 0.80 t/
(m2.h). An underflow density of 63% solids was achieved for the Transition composite tailing sample
using Magnfloc 10 at a dosage of 60 g/t, which resulted in a flux of 0.40 t/ (m2.h). Thickener overflows
were clear with suspended solids reported at less than 100 mg/L and were suitable for recycle back to
the process, although the target underflow density of 64% solids was not achieved in these tests.
Outotec concluded that based on their experience with their testwork and full-scale operation of
thickeners that an estimated 2 to 3% increase in thickener underflow density could be expected when
comparing the testwork to a full-size thickener.
Table 13-45: Summary of High Rate Thickening Test on MDZ Master Composite Leached Tailing
Run No.
Feed Flocculant Underflow Overflow
Flux (t/[m2·h])
Liquor RR (m/h)
Type Dose (g/t)
Meas. Solids (% [w/w])
YS (Pa)
Solids (mg/L)
1 0.80 2.70
Magnafloc 10
40 63.4 32 127
2 0.80 2.70 30 63.0 30 204
3 0.80 2.70 50 63.5 30 <100
4(1) 0.80 2.70 50 69.8 102 <100
5 1.00 3.37 50 62.7 42 <100
6 1.20 4.05 50 61.7 45 <100
Note: (1) Test 4 was run as a high compression test Source: Outotec Report 324931, 02/21/2020
Table 13-46: Summary of High Rate Thickening Test on MDZ Transition Composite Leached Tailing
Run No. Feed Flocculant Underflow Overflow
Flux (t/[m2·h]) Liquor RR (m/h) Type Dose (g/t) Meas. Solids (% [w/w]) YS (Pa) Solids (mg/L)
1 0.80 2.70
Magnafloc10
60 60.2 53 172
2 0.80 2.70 50 60.3 52 338
3 0.80 2.70 70 60.6 61 155
4 0.60 2.03 60 61.5 59 154
5(1) 0.60 2.03 60 69.3 188 154
6 0.40 1.35 60 63.0 21 155
Note: (1) Test 5 was run as a high compression test Source: Outotec Report 324931, 02/21/2020
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 172
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
13.2.18 Tailings Filtration
Outotec conducted filtration testwork on detoxed leach tailings generated from MDZ Master and
Transition composites that were produced using optimized process parameters. Filtration testing was
performed using Outotec’s Labox 100 bench-scale unit and Scanmec leaf dip test apparatus to
examine the filtering characteristics and process suitability. The filter cakes were required to have a
cake moisture of less than 15% and be suitable for dry stacking at the tailings storage facility. The
results of Outotec’s filtration testwork are presented in their report No 32491 dated 2/25/2020.
The thickened tailings samples used for the filtration testwork were characterized as follows:
Master Comp Transition Comp
Density (g/mL): 1.65 1.63
Slurry solids (% w/w): 65.0 62.0
pH: 8.9 8.7
Particle size (P80 µm): 107.7 103.3
Pressure filtration test results on the Master composite tailing sample are shown in Table 13-47 and
the results for the Transition composite tailing sample are shown in Table 13-48. The Master composite
tailing sample achieved 12% moisture contents over the range of cycle times tested (8.5 to 12
minutes). At the 8.5 minute cycle time, a filtration rate of 269.6 kg/m2.hour was reported. The transition
composite tailing sample achieved 14.6 to 15.8% moisture contents over the range of cycles times
tested (9 to 12 minutes). At the 10 minute cycle time, a cake moisture content of 14.6% and a filtration
rate of 214.9 kg/m2.hour were reported. Pressure filtration on both the master and transition composite
tailing samples achieved the required moisture content for disposal in a dry stack DSTF.
Table 13-47: Pressure Filtration Test Results on the Master Composite Tailing Sample
Parameters Units Run #1 Run #2 Run #3 Run #4
Feed Density % w/w 65.0 65.0 65.0 65.0
Filter Cloth Type AITE S400 AITE S400 AITE S400 AITE S400
Chamber Depth mm 50 50 50 50
Cycle time min 12.0 9.5 9.0 8.5
Pumping Pressure bar 6.0 6.0 6.0 6.0
Pressing Pressure bar 12.0 12.0 12.0 12.0
Air Drying bar 10 10 10 10
Cake Thickness mm 48.0 47.6 47.1 47.4
Cake Moisture % w/w 12.2 12.1 12.2 12.1
Filtration Rate D.S. kg/m2h 189.2 239.7 252.2 269.6
Source: Outotec report 324931, 02/25/2020
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 173
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 13-48: Pressure Filtration Test Results on the Transition Composite Tailing Sample
Parameters Units Run #1 Run #2 Run #3 Run #4 Run #5
Feed Density % w/w 62.0 62.0 62.0 62.0 62.0
Filter Cloth Type AITE S400 AITE S400 AITE S400 AITE S400 AITE S400
Chamber Depth mm 50 50 50 50 50
Cycle time min 12.0 11.0 10.0 9.0 10.5
Pumping Pressure Bar 6.0 6.0 6.0 6.0 6.0
Pressing Pressure bar 12.0 12.0 12.0 12.0 12.0
Air Drying bar 10 10 10 10 10
Cake Thickness mm 47.0 47.1 43.9 39.2 47.5
Cake Moisture % w/w 15.8 15.2 14.6 15.4 14.9
Filtration Rate D.S. kg/m2h 191.2 208.6 214.9 209.4 219.4
Source: Outotec report 324931, 02/25/2020
Vacuum filtration tests were conducted on the Master and Transition tailing composite samples using
the Scanmec Leaf Disc vacuum filtration apparatus. Vacuum filtration test results on the Master
composite tailing sample are shown in Table 13-49 and the results for the Transition composite tailing
sample are shown in Table 13-50. Tests on the Master composite tailing sample were conducted both
with and without filter aid and produced cake thicknesses ranging from 7 to 16 mm. Cake moisture
contents ranged from 17.5 to 22.4%. No vacuum filtration tests achieved the required 15% moisture
content. Tests on the Transition composite tailing sample were conducted both with and without filter
aid and produced cake thicknesses ranging from 3 to 8 mm. Cake moisture contents ranged from 20.7
to 21.7%. No vacuum filtration tests on the Transition composite tailing sample achieved the required
15% moisture content. Based on the results of these tests, vacuum filtration is not an option for filtering
thickened MDZ tailings for disposal in a DSTF.
Table 13-49: Vacuum Filtration Test Results on the Master Composite Tailing Sample
Solids (wt%)
Filter Aid (g/t)
Cycle Times (sec/cycle)
Cake Thickness (mm)
Filtration Capacity (kg/m2h)
Moisture (wt. %)
Cake Cracking
65 None 86 7 560 17.5 No
65 None 40 5 833 18.2 No
65 25 86 10 670 18.6 No
65 50 86 12 1,160 19.4 No
65 75 86 15 1,219 21.2 Yes
65 100 86 16 1,447 22.4 Yes
Source: Outotec report 324931, 02/25/2020
Table 13-50: Vacuum Filtration Test Results on the Transition Composite Tailing Sample
Solids (wt%)
Filter Aid (g/t)
Cycle Times (sec/cycle)
Cake Thickness (mm)
Filtration Capacity
(kg/m2h)
Moisture (wt. %)
Cake Cracking
62 None 86 3 200 20.7 No
62 None 40 2 431 20.0 No
62 25 86 4 234 20.2 No
62 50 86 5 334 20.2 No
62 75 86 7 351 21.0 No
62 100 86 8 556 21.7 No
Source: Outotec report 324931, 02/25/2020
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 174
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
13.3 Recovery Estimate
Table 13-51 provides an estimate of achievable gold and silver recoveries from the MDZ based on a
flowsheet that includes gravity concentration and cyanidation of the gravity tailing with optimized PFS
process parameters that include:
• Grind size P80: 105 µm
• Ret. Time: 24 hours
• Pulp density: 45 to 50% solids (w/w)
• Pre-aeration: 4 hours
• O2 injection: 20 to 25 mg/L dissolved O2
• Pulp pH: 10.5 to11 (maintained with lime)
• Cyanide Conc: 0.5 g/L NaCN (allowed to attenuate to 0.2 g/L)
SRK recommends discounting laboratory-reported gold recoveries by 2% and silver recoveries by 5%
to account for inherent plant inefficiencies. Based on the results of the PFS metallurgical program, the
average discounted gold recovery is estimated at 95% and the average discounted silver recovery is
estimated at 51%. This is very similar to the results from the PEA metallurgical program in which the
average discounted gold recovery was estimated at 95% and average discounted silver recovery was
47%. There is little difference in reported gold recoveries for the master and variability composites and
gold recovery appears to be independent of ore grade over the range tested.
Table 13-51: Estimated Gold and Silver Recoveries from the MDZ (PFS and PEA Metallurgical Programs)
Composites
Calc. Head (g/t)
Gravity Recovery (%)
Gravity + Cyan Recovery (%)
Adjusted Overall Recovery (%)
Au Ag Au Ag Au Ag Au Ag
PFS Composites
MDZ Master Comp 3.02 3.80 58.8 16.5 97.7 64.5 96 60
MDZ Variability Comp
Low Grade 1.80 3.10 61.5 15.0 96.8 47.4 95 42
Medium Grade 2.58 2.90 66.7 21.2 97.4 59.2 95 54
High Grade 3.99 3.80 60.3 21.7 96.7 56.1 95 51
Deep Zone 4.52 1.10 82.0 34.3 98.5 56.4 97 51
Transition Zone 2.77 4.50 63.2 17.0 97.4 54.8 95 50
Average Master + Variability Comp.
3.11 3.20 65.4 21.0 97.4 56.4 95 51
PEA Composites
MDZ Master 2.36 4.20 50.6 14.6 96.7 50.6 95 46
MDZ West Zone 1.30 0.90 66.1 24.7 97.3 58.7 95 54
MDZ Center Zone 2.61 2.39 69.0 21.0 97.9 51.6 96 47
MDZ East Zone 1.80 6.70 51.7 15.9 96.7 45.8 95 41
Average Master + Variability Comp.
2.02 3.55 59.4 19.1 97.2 51.6 95 47
Au Adjustment Factor 2
Ag Adjustment Factor 5
Source: SGS, 2019 and 2020
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 175
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
13.4 Significant Factors
The following significant metallurgical and mineral processing factors have been identified:
• The PFS metallurgical program was conducted on an MDZ master composite and on
variability composites representing low, medium and high grade MDZ ore, transition zone and
the MDZ deep zone.
• Native gold was by far the predominant gold carrier and the majority (more than 99%) of the
gold particles occurred within mineral structures that would be readily accessible by leaching
solutions. Gold particles were not often in direct contact with sulfides, yet very commonly
pyrrhotite, chalcopyrite, and bismuth minerals were found in close vicinity to the gold
mineralization
• The metallurgical program optimized process parameters required to recover gold and silver
values from MDZ ore using a process flowsheet that includes gravity concentration followed
by cyanidation of the gravity tailing. Optimized process conditions included:
o Grind size P80: 105 µm
o Pulp density: 45% solids (w/w)
o Pre-aeration: 4 hours
o O2 injection: 20-25 mg/L dissolved O2
o Pulp pH: 10.5-11 (maintained with lime)
o Cyanide Conc: 0.5 g/L NaCN (allowed to attenuate to 0.2 g/L)
o Retention time: 24 hours
• Comminution tests were conducted on the MDZ master composite, MDZ deep zone
composite, three MDZ sub-composites (low grade, medium grade and high grade) and on the
Marmato mine composite. The comminution tests included SAG Mill Comminution (SMC),
SAG Mill Power Index (SPI) and Bond ball mill work index (BWI) tests. In addition, Bond Low
Impact Crushing work index (CWI) and abrasion (AI) tests were conducted on selected ½ HQ
drill core pieces.
o The results of the SMC A x b values ranged from 23 to 29, indicating the ore is hard with
respect to impact breakage.
o The BWI values for the MDZ composites range from 17.7 kWh/t to 19.8 kWh/t, which
places them in the hard range of hardness.
• Gravity recoverable gold (E-GRG) testwork and modeling indicate that about 40% of the gold
contained in the MDZ ore can recovered into a gravity concentrate. Gold contained in the
gravity tailing would be recovered in a standard CIP cyanidation leach circuit.
• An intensive cyanide leach test on the gravity concentrate demonstrated that 99.7% of the
contained gold and 87.9% of the contained silver could be extracted from the gravity
concentrate without regrinding.
• Based on the results of the PFS metallurgical program, overall gold recovery (gravity
concentration + gravity tailing cyanidation) is estimated at 95% and overall silver recovery is
estimated at 51%. This is very similar to the results from the PEA metallurgical program in
which gold recovery was estimated at 95% and silver recovery was 47%. There is little
difference in reported gold recoveries for the master and variability composites and gold
recovery appears to be independent of ore grade over the range tested.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 176
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
• Cyanide destruction tests demonstrated that weak acid dissociable cyanide (CNWAD) could be
reduced to less than 10 mg/L with the SO2/air process. However, CNWAD levels would further
attenuate to less than 1 mg/L with time.
• Pressure filtration will be required to dewater thickened tailings in order to achieve less than
15% moisture content required for disposal in a DSTF.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 177
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
14 Mineral Resource Estimate The Mineral Resource Statement presented herein represents the latest mineral resource evaluation
prepared for the Marmato Project reported in accordance with the standard adopted for the reporting
of Mineral Resources of the CIM guidelines, and with NI 43-101 disclosure standards.
SRK has been supplied with electronic databases covering the sampling at the Project, all of which
have been validated by the Company. The databases comprise a combination of historical and recent
diamond core and underground channel samples. In total, there are 1,357 diamond drillholes for a
combined length of 278,945 m and 26,307 individual underground channel samples, inclusive of
current mine sampling contained in the databases. The database contains all the sampling within the
Marmato project and is not limited to license #014-89m, which is the focus of this report.
The resource estimation was completed by Ben Parsons, MSc, MAusIMM (CP), Membership Number
222568, an appropriate “independent qualified person” as this term is defined in NI 43-101. The
Effective Date of the resource statement is March 17, 2020, which is the date the database was
supplied.
The database used to estimate the Marmato Project mineral resources was audited by SRK. SRK is
of the opinion that the current drilling information is sufficiently reliable to interpret with confidence the
boundaries for gold and silver mineralization and that the assay data are sufficiently reliable to support
mineral resource estimation. The use of short channel sampling (sampling length, less than 5 m) has
been limited to the current underground mining domains, defined as the veins, disseminated and splay
domains.
Leapfrog® (version 5.0.4) was used to generate the geological and mineralization models used to
define Marmato model. Datamine™ (version 1.6.75.0) was used to construct the geological solids,
prepare assay data for geostatistical analysis, construct the block model, estimate metal grades and
tabulate mineral resources. Snowden Supervisor software (version 8.12.0) was used for the
statistical/geostatistical analysis and variography.
The estimation methodology involved the following procedures:
• Database compilation and verification
• Construction of wireframe models for the boundaries of the veins
• Construction of wireframe models for the boundaries of the main other domains including:
o Fault network
o Mineralized porphyry
o Low-grade porphyry
o Deeps/feeder structures
• Definition of resource domains
• Data conditioning (compositing and capping) for statistical analysis, geostatistical analysis,
and variography
• Block grade interpolation
• Resource classification and validation
• Assessment of “reasonable prospects for economic extraction” and selection of appropriate
reporting CoGs
• Preparation of the Mineral Resource Statement
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 178
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
14.1 Drillhole Database
SRK was supplied with ASCII files (.csv), extracted from the Company’s Structured Query Language
(SQL) database as seven comma-separated value (.CSV) files with collar, survey, geology, assay,
density, recovery and structure information exported. The exported information contains the latest
drilling and sampling information. These were subsequently imported into Datamine™ and Leapfrog®
for validation.
The database provided included all sampling from the combined drilling database and channel
sampling programs. A summary of the database used in the final estimate is detailed in Table 14-1
Table 14-1: Summary of Number of Records for Each Exported .csv
File Type Number of Records
Collar 27,650
Source 27,650
Survey 86,020
Lithology 159,118
AssayRaw 237,969
AssayLF 237,982
VeinCode 75,015
Density 3,370
Alternation 43,097
Mineralization 45,488
Source: SRK, 2020
A total of 1,357 drillholes has been used to inform the 2020 Marmato MRE including historic drilling
and more recent drilling completed between the 2019 PEA and this PFS (Table 14-2). A total of 40
new drillholes from the exploration and mine developed has been included since the 2019 PEA for a
total of 12,555 m of new drilling. A full description of drilling procedures, sample preparation, sample
analysis and QA/QC is presented in Sections 10 and 11 of this report. Information relating to data
management, and the validation of data is presented in Section 12.
Table 14-2: Summary of Geological Database Information for Drilling Reported by Company
Count Minimum Length (m) Maximum
Length (m)
Average Length
(m)
Sum Length (m)
Company
CGD 20 50.85 559.55 296.67 5,933.35
CGD-GCL 75 16.78 527.40 149.13 11,184.69
CMdC 205 1.20 587.25 226.23 46,377.82
CNQ 47 39.20 600.20 316.45 14,872.95
CNQ-MNL 25 14.00 180.00 72.13 1,803.37
CNQ-PDG
6 70.60 175.00 115.99 695.95
CALDAS 57 127.21 810.20 487.52 27,788.56
MAdO 342 12.00 1,012.10 355.70 121,650.34
MNL 580 4.03 400.35 83.86 48,638.18
Drillhole Subtotal 1,357 1.20 1,012.10 205.56 278,945.21
Grand Total 27,664 0.02 1,012.10 11.61 321,183.22
Source: SRK, 2020
In addition to the drilling information, CGM has captured information from the mine and exploration
channel sampling databases. Limited new sampling has been captured between the 2019 PFS and
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 179
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
the current study for a total of 26,307 channels in the database for a combined sample length of
42,328 m. A summary of the channel sampling programs by Company is shown in Table 14-3.
Table 14-3: Summary of Geological Database Information for Channel Reported by Company
Count Minimum Length
(m) Maximum Length
(m) Average
Length (m) Sum Length
(m)
Company
CGD 165 0.04 13.99 1.02 168.35
CMdC 918 0.03 58.23 3.00 2,749.64
CNQ 39 0.60 154.78 22.22 866.53
MAdO 308 0.50 102.19 9.46 2,912.85
MNL 24,877 0.02 122.21 1.43 35,540.64
Channel Subtotal 26,307 0.02 154.78 1.61 42,238.01
Source: SRK, 2020
14.2 Geologic Model
A 3D lithostratigraphic and structural framework model of the Marmato deposit has been developed.
Within the framework of that model, Resource wireframes have been constructed using Seequent’s
Leapfrog Geo™ v4.5 software. To construct the model, SRK has used a phased approach which
included review of the faults, lithology, and mineralization styles.
14.2.1 Fault Network
TCL recognized two principal deformation stages within the Marmato stock (TCL, 2010):
• Syn-mineralization west-northwest to east-southeast compression reactivated some
basement structures as well as generated a range of second-order shear and extensional
structures along north northwest to west trends, as well as north-northeast-trending thrust
faults.
• Continued post-mineralization compression into the late-Pliocene, (approximately 2 mega
annum [Ma]) that resulted in uplift due to renewed thrusting along the main terrane boundaries,
forming thrust bounded intermontane basins such as the Cauca-Patia depression.
TCL outlined four principal trends of auriferous structures within the Marmato area:
• Northwest-trending steep to sub-vertical faults/fractures
• West-northwest-trending steep to moderately inclined structures
• West-trending structures that tend to have moderate to relatively low angle dips
• East-northeast- to northeast-trending structures that show a range of dips
TCL reported that kinematic indicators show that gold mineralization accompanied a phase of W-NW-
E-SW orientated compression. The N-NE trending reverse faults and conjugate fractures reflect this
compression component. Within this tectonic framework the E-W faults should be predominantly
dextral strike-slip and the W-NW faults should be predominantly sinistral strike-slip. CGM interprets
the rotation of some of these structures to be the result of rotation during progressive compressional
deformation event; however, CGM also noted that there are pre-gold mineralization and post-gold
mineralization phases of fault movement on a number of faults and veins
SRK conducted a site visit to Marmato from December 9 to December 13, 2019. Mr. Blair Hrabi, SRK
Principal Consultant (Structural Geology) conducted the site visit with Dr. Julian Ceballos, CGM
Principal Geologist.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 180
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
SRK has extruded fault wireframes to surface using regional mapping and underground development
as a guide, and subsequently clipped these to the topography to create a fault network which has been
used to review the vein interpretations during the geological modelling (Figure 14-1). Where possible,
SRK has tied the fault interpretations into the latest geological logging and mapping on levels 16
through 19. During the site visit Mr. Hrabi and Dr. Ceballos visited the Marmato Mine including levels
18, 19, 20, and 21, and reviewed drill core or core photographs for the following drillholes:
• MT-1423
• MT-IU-002
• MT-IU-016
• MT-IU-041
• MT-1430
• MT-IU-009
• MT-IU-017
• MT-IU-045
• MT-1498
• MT-IU-011
• MT-IU-018
• MT-IU-050
• MT-1499-A
• MT-IU-014
• MT-IU-019
• MT-1500
• MT-IU-015
• MT-IU-036
The northwest-dipping Obispo reverse fault (approximately 70°/310°) defines the limit of the known
Marmato gold mineralization to the NW. The N dipping Fault Criminal (approximately 60°/355°) is
interpreted as a dextral strike-slip fault and is truncated to the W by the Fault Obispo. The moderately
W-SW dipping Fault Sur (approximately 50°/190°) cuts the UZ of the Zona Baja but approximately
bounds the southern margin of the MDZ.
Faults 2 (approximately 60°/050°) and 4 (approximately 85°/190°) are found between faults Criminal
and Sur. Fault 2 trends obliquely to, and is cut off by, faults Criminal and Sur. In addition, the composite
Vein (V.) Santa Ines was used in the modelling to define the up-dip extent of Fault Sur.
SRK principal geologist Mr. Giovanny Ortiz visited site on February 10 to 21, 2020 and worked with
both CGM’s exploration and mine geologist to refine the fault interpretation. During the site inspection
and based on mapping on levels 20-21, the decision was made to remove the previously modelled
Fault 4 and replace the structure with a combination of the new structure (Fault 1_3). This fault has
been interpreted to potential offset a portion of the footwall of the MDZ and therefore has been included
in the current estimate during the geological definition phase of the model. SRK and CGM geological
staff undertook a structural interpretation for the deposit using logged faults and breccia in drill core,
underground mapping and surface traces from the digital topography. A series of fault wireframes were
provided to SRK, which were generally localized around areas of structural data.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 181
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
The final fault network consists of five faults used in the geological model are named:
• Fault Obispo
• Fault Criminal
• Fault Sur
• Fault 2
• Fault 1_3
Source: SRK, 2020
Figure 14-1: Fault Network Compared to Mapping on Level 20 (1056 RL)
Additional faults are in the process of interpretation by CGM which may potentially extend to depth at
the Marmato Project. SRK did not consider these to have sufficient geological confidence to include in
the current estimate but notes that the work should be completed to increase the confidence in these
structures. The additional structures include:
• Cascabel Fault
• Pantanos (Primary)
• Pantanos (Secondary)
Criminal Fault
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 182
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
14.2.2 Topographic Wireframes
CGM commissioned a detailed topographic map with 0.5 and 1 m resolution contour intervals derived
from LIDAR imagery, which was supplied to Datamine™ in 2020. The new topographic map provides
a detailed base map for improved accuracy when plotting the results of the exploration programs, as
well as a high-resolution satellite image. The topography was converted to a solid model in Datamine™
which resulted in excessively large files (more than 2 gb), which was later filter to reduce the number
of points by 50% to enable rapid viewing in various technical software package. This model has been
supplied to SRK by the Company.
14.2.3 Lithological Wireframes
As part of the updated Mineral Resource, SRK initially focused on the creation of a lithological model
(i.e., one encompassing the major geological features inclusive of the current veins being mined). The
lithological database provided to SRK contained 64 separate logging codes, which has been refined
to 14 logging codes by SRK. The main geological features and units modelled by SRK were:
• Major Fault Network
• Porphyry (P1 – P5)
• Meta Schist
• Intrusive
• Volcanic
• Breccia
• Veins
• MDZ
During the definition of the lithological model, SRK noted conflicting interpretations between the
definition of P1 and P2 porphyry units between the mine and exploration teams. To avoid complex
geological coding or detailed relogging, SRK has removed the mine drilling from the lithological
models. SRK notes there are limited differences between the P1 and P2 units which are described as
a dacite porphyry (with Mega Hb-Bi) in P1 compared to a dacite porphyry (common) in P2. SRK does
not consider the removal of the mine drilling to have a material impact on the lithological model or the
associated mineral resource estimates.
The lithological model has been defined in Leapfrog by using the intrusion function within a model with
extents ranging from X: 1,162,550 – 1,166,350, Y: 1,096,350 – 1,099,150, and Z: 0 – 2,000, with the
surfaces clipped to the topography as defined in Section 14.2.2. The fault network has been defined
to generate a total of seven major fault blocks which are used to limit the geological model. A limiting
boundary of 275 m has been used to limit the projection of the geological units as significant areas at
depth still remain undrilled and therefore limit the extension of the veins to depth.
In comparison to the PEA lithological model, SRK has made additional definition of the units within the
P4 – P5 dikes which have been modelled using the vein system utility to form a consistent geological
unit. The other key change is the definition of the breccia units which crosscut the MDZ and may need
consideration for geotechnical criteria prior to mining.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 183
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SRK, 2020
Figure 14-2: Cross Section Showing SRK Revised Lithological Model
14.2.4 Veins Model
The vein models have been updated using a combination of the drillhole information, channel
sampling, geological mapping and the initial depletion shapes provided by CGM. The process has
been a collaboration between SRK and CGM to ensure accuracy of the geological conditions mapped
underground are considered. To complete the process CGM geologists supplied SRK with an updated
underground channel database based on the procedures discussed in Section 11.2 of this report.
Additionally, CGM created an initial stope model based on the average dip and strike taken from the
underground long-sections produced by the mine.
SRK imported all the available information into Leapfrog® to aid in the generation of the vein model.
The vein model was created via a staged process. SRK has made a number of modifications to the
geological modelling process in the 2019 update. The changes included combining the vein and halo
domains used during the 2017 process. The decision to combine these domains was based on the
mining methods, typically including both, and therefore a single domain will account for some of the
edge dilution, although not all due to minimum mining widths. Also, the incremental gain from the
model was not deemed to add value, and therefore a single pass combining both mineralization
domains was preferred.
Possibleextensions unknown
Veins extended could possibly be offset by Fault Sur
Extension of veins limited by sampling information
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 184
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
The position of the vein within the channel sampling was based on a combination of lithology logging,
gold grade, geological mapping and (base of) stope wireframe data, with interpretation for the vein in
less well-informed areas guided by visually evident step changes in the gold grade and characteristics
of the vein (i.e., position, thickness and grade continuity) shown in adjacent samples.
The new model includes the differentiation between vein material and disseminated material where
the information was available in the channel samples in the area of the mine. The images below show
the differences with the vein wireframes of the PEA. The impacts of this change include:
• Increased the Au grade and reduction in tonnage in the vein material (MINERALIZATION
STYLE CODES: VEM, VEA, VEN)
• In the previous model, part of the disseminated material (MINERALIZATION STYLE CODES:
VNS, VNA, DSM) was included in the vein wireframes, which could result in the smearing of
high grades
The process was initially completed on the areas with strong geological control in the mine and then
expanded into the upper and lower levels of the deposit which are predominantly supported by drilling
information only.
SRK has used all the available information to define the updated geological model, including mapping,
channel sampling and diamond drilling information. The additional channel (VEN) samples have been
sub-divided per Caldas ‘VEIN’ code:
• Vein samples that influence the wireframe. These were deemed by SRK to be visually spatially
positioned correctly with respect to geological mapping, mining development/stope data and
surrounding drillhole assays and logging and have the following ‘Veins’ code: ‘V_XXX’
• Vein samples that do not influence the wireframe, but have a code corresponding to the
relevant structure for use in statistics evaluation. These are visually spatially offset with respect
to other geological data (which if incorporated would result in ‘pull points’ to the vein
wireframes and potentially overstate the tonnage) and have the following ‘Veins’ code:
‘V_XXX_STM’
SRK has validated the vein model using a series of level plans from the current mining operation for
Levels 16 through 21 and reviewed by CGM geologists for approval. It is the QP opinion that by
combining the geological mapping and channel database from the mine, the lithological model has
been improved with strong controls on the mineralization styles. In the PEA model, the vein model was
combined based on grade with veinlet mineralization in the hangingwall and footwall of the veins which
is termed as the “Disseminated” veins. A summary of the level of information used to generate the
veins model is shown in Figure 14-3.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 185
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SRK, 2020
Figure 14-3: Level 20 Geological Mapping Versus Sampling Database and Veins Model, Showing the Level of Information Integrated into the Geological Model
14.2.5 Disseminated Model
The disseminated vein models exist surrounding the main structures and are focused around Levels
16 through 21 of the current mine. The mineralization occurs as veinlets or disseminated mineralization
directly in the hangingwall and footwall of the veins. The mineralization in the disseminated domain
(Coded as DISS) is not logged as VEN but more typically as P1, VNS or DSS in the more recent
drilling. SRK has used a combination of the lithological log and the assays to define the limits of the
disseminated material. The use of the disseminated domains will aid in the definition of diluting grades
surrounding the defined veins and, in some cases, represents higher grades than present within the
veins. The interaction of the veins and disseminated vein domains is shown in Figure 14-4.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 186
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SRK, 2020
Figure 14-4: Level Plan (1065 RL), Showing Interaction Between Vein and Disseminated Vein Domains
14.2.6 Splays Model
There are a number of intersections left after the definition of the veins, which still have the logging
code for “VEN”. SRK has reviewed these samples along with the geological mapping to identify a
number of small splays of the main structures. SRK identified a total of 103 structures which show
some degree of geological continuity to be able to define wireframes.
Vein samples were provided by CGM with a structure code but are (based on visual review) more
likely to be located in discontinuous splay veins in the HW or FW of the modelled vein. These are left
unassigned in the background veins coding and have been considered for the SPLAY domain. An
example of the splay is shown in Figure 14-4.
SRK considers the splays to have lower geological confidence to the main veins and further sampling
will be required to confirm potential prior to mining. The wireframe has been created using the vein
tools in Leapfrog®, the boundaries to limit the model are defined using polylines by SRK to crop the
veins as appropriate to the main structures. The extension of the wireframes in strike and dip were
limited to a maximum of 25 m beyond the data.
Group 1000 - Veins
Group 2000 – Disseminated Veins
Group 3000 – Splays
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 187
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
14.2.7 Porphyry “Pocket” Model
The modelling of the porphyry mineralization is hosted within the epithermal and transitional zones
with the mesothermal mineralization. The basis for the mineralization model remains consistent with
the methodology used in the previous model.
SRK generated a series of gold indicator grade shells using a 0.5 g/t Au CoG and an iso-value of 0.45
using 2 m composites. Indicator shells have been sub-divided into the major fault blocks, which have
been modelled independently. Due to the issue of the increase in the channel sampling database, with
many short channel samples located outside of the vein models, a restriction has been placed on the
samples used during the modelling process. The following criteria has been applied prior to modelling:
• Mineralization is flagged as being in the “Epithermal Zone” (not used in Group 5000)
• Vein_N = is null (not used in the vein model Group 1000)
• DISS = is null (not used in the disseminated model Group 2000)
• Splay = is null (not used in the splay model Group 3000)
• Length of hole is greater than 5 m (removes potential influence from narrow veins not
modelled)
• Lithology is not flagged as VEN, VNA, VNS or VOI
SRK has worked under the assumption that the porphyry mineralization will have a relationship to the
orientation of the epithermal vein systems which cross-cut the porphyry, any veinlets would likely be
structurally controlled. To apply this condition, SRK has used a structural trend within Leapfrog® when
generating the Indicator Grade Models. In order to generate the structural trends, SRK identified key
veins and orientations to avoid local variations in the overall trend. The structural trends are then based
on the orientations of these veins and structural orientations and are applied to new interpolants to
force anisotropy along these trends.
SRK ran a series of sensitivities and has monitored the levels of internal waste and the proportion of
samples above cut-off outside of the wireframes. Based on the study, SRK selected to use the
following criteria:
• Indicator Grade: 0.5 g/t
• Composite Length: 2 m with minimum length of 0.5 m (shorter lengths added to the previous)
• Structural Trend applied – with strongest anisotropy along the trend surfaces
• Spheroidal Interpolant, using a sill of 1 and nugget of 0.05
• Base range of 50 m
• Drift set to none
• ISO value of 0.45, with a surface resolution of 5 m
• Discarding any volumes less than 1,000 m3
A summary of the process and wireframe is shown in Figure 14-5.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 188
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SRK, 2020
Figure 14-5: Development of Porphyry Pockets Wireframe Methodology
Plan Section
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 189
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
14.2.8 MDZ
In the 2019 PEA geological model, the MDZ was modelled using a broad outline and an approximate
CoG of 0.7 g/t Au. This includes a restricted internal higher-grade core, typically associated with areas
of increased veinlet density, as highlighted by Sillitoe (2019), using a 1.7 g/t Au indicator shell.
SRK has reviewed the PEA mineralization model for the MDZ at routine intervals during the infill drilling
campaign and noted the model performed well in predicting the location of the mineralization. SRK
concluded that the approaches taken in the PEA model were therefore reasonable and applied a
similar process in the PFS updated model. The three step process is to initially define the limits of the
Mesothermal mineralization based on geological logging (using the table “minznMN_LF”) exported
from the database. The key parameters used to define the limit of the mineralization styles are the
Mineralization Zone (MZ1MineralZone) and mineral assemblages (MZ1Mineral, MZ2Mineral).
Internal to the Mesothermal Mineralization domain, SRK has generated a medium and higher grade
indicator defined grade shell. To create the indicator model, the following assumptions have been
used:
• Only drillholes have been used to define the domain to remove potential errors or overstating
tonnage related to isolated short channel sampling
• All holes have been composited to 3 m, with samples lengths less than 0.5 m at the end of
holes appended to the previous sample
• CoGs of 0.7 and 1.7 g/t were used to define the outer limit of the mineralization, which
represents 13.1% of the database being assigned an indicator value of 1, with all other values
assigned an indicator of 0
• SRK has made use of a structural trend to define the orientations for the search ranges during
the indicator estimation process. The structural trends have been defined using input from
televiewer logged geological criteria for VEN (three records), VNA (24 records) and VNS (245
records) and by sectional analysis following key trends. (Figure 14-6);
• A spherical model has been used with a sill of 0.25 and a nugget of 0.05, using a base range
of 100 m for the interpolant.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 190
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SRK, 2020
Figure 14-6: Development of MDZ model
VNS
VNA
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 191
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
To define the statistical parameters for the final indicator model, SRK completed a detailed study using
ISO (probability) values ranging from 0.40 to 0.60 at selected increments. SRK has monitored the
volumetric changes of the interpreted grade shells, the mean grade, the internal waste percentage
(samples<cut-off inside the wireframe) and the number of samples above cut-off outside the grade
shell.
Table 14-4: Summary of Leapfrog 0.7 g/t Indictor Grade Shell, ISO Value Sensitivity Study (MDZ Material)
Iso-Value 0.40 0.45 0.475 0.50 0.525 0.55 0.60
Total Samples Inside 75.2% 71.6% 69.7% 67.7% 65.7% 63.7% 59.6%
Internal Samples < cut-off 17% 14% 13% 11% 10% 9% 7%
Mean Grade 2.46 2.54 2.59 2.64 2.68 2.73 2.82
Volume (000 m3) 27,233 25,069 23,930 22,757 21,535 20,277 17,796
Volume % 100% 92% 88% 84% 79% 74% 65%
Source: SRK, 2020
SRK selected an ISO (probability) value of 0.475 for the final model in the 0.7 g/t indicator shell, with
a grid resolution of 5 m to define the wireframes. Upon review, SRK was concerned about potential
blow-outs within the 0.7 g/t indicator models at the edge of the model, where limited data exists. SRK
has utilized the use of control lines and minimum distances to restrict the high-grades from artificially
increasing the tonnage. These areas are also reviewed during the classification to limit the chances of
over estimation by applying a limit to the Inferred boundary. The same process has been used within
the high-grade 1.7 g/t domains to avoid overstating volume. The ISO value was increased to 0.50.
14.3 Domains
All geological surfaces were cut to the topography and the final geological model has been reviewed
by CGM and has been deemed acceptable by SRK for use in determining the MRE. Using the
wireframes, SRK has coded the drilling and block model information into five domains which are stored
in the block model under the field “GROUP”, for the main mineralization styles. A series of sub-codes
(VEIN_N, DISS, SPLAY and KZONE) have been used to distinguish between mineralization style and
individual mineralized structure. A list of the domains used is shown in Table 14-5 and in cross section
in Figure 14-7.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 192
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 14-5: Summary of Domain Coding Used in the 2017 Mineral Resource Estimate
Group No Subdomains Wireframe Domain Description
1000 95 Group1000.dxf Vein High grade sulfide veins
2000 73 Group2000.dxf Halo Disseminated veinlets and porphyry mineralization adjacent to the main vein structures
3000 103 Group3000.dxf Splays Splays of main structure within limited continuity
4000 7 Group4000.dxf- Grade Shell
Mineralized porphyry material (contained within veinlet), characterized by a mixed population of higher grade above an elevation of 850 m, low grade and barren material, marks the default unit for all material, split by fault domain
5000 3 Group5000.dxf Deeps
High grade core or feeder zone to the main mineralization. Located at depth within the porphyry system with limited veinlet mineralization, split into low, medium (0.7 g/t) and high (1.7 g/t).
Source: SRK, 2020
To validate the mineralization domains as defined, SRK completed a statistical review of the domained
data, which indicates independent populations for the five main domains (Figure 14-7 and Table 14-6).
Source: SRK, 2020
Figure 14-7: Box Plot Showing Raw Sample Statistics Based on Defined Geological Domains (Group)
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 193
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 14-6: Summary Raw Sample Statistics Based on Defined Geological Domains (Group)
Column Domain Field
Domain Count Weight Min Max Mean Total Variance St.
Dev CV
AU 245066 315816 0 1767 0.878 277201 35.98 5.998 6.83
AU GROUP 0 134901 237744 0 1425 0.201 47818 7.41 2.721 13.53
AU GROUP 1000 38996 18751 0 605.1 5.892 110478 180.7 13.44 2.28
AU GROUP 2000 27498 13435 0 947.1 2.349 31562 63.51 7.969 3.39
AU GROUP 3000 7762 3712 0 1767 4.852 18012 785.2 28.02 5.78
AU GROUP 4000 12724 14897 0 891 1.788 26635 78.44 8.856 4.95
AU GROUP 5000 23185 27276 0 345.9 1.565 42697 21.41 4.627 2.96
Source: SRK, 2020
14.4 Assay Capping and Compositing
14.4.1 Outliers
High grade capping is typically undertaken where data is no longer considered to be part of the main
population. Useful discussions on the need for and the application of capping of high grades are found
in Leuangthong and Nowak (2015). Capping is an appropriate technique for dealing with high-grade
outlier values, given that appropriate analysis is undertaken to validate the results of the
implementation of capping. The following procedure is recommended for treating outliers during
resource estimation:
• Determine data validity. Is the data free of sampling, handling, measurement and transfer
errors?
• Review geology logs for samples with high-grade assays. Capping may not be necessary for
assays where the logs clearly explain the presence of high-grade
• Capping should not be considered for deleterious substances that have negative impacts on
project economics
• Decide if capping should be considered before or after compositing
• If high-grade assays unduly affect overall grade average, cap them
• Restrict influence of very high-grade assays during the estimation process if required
Upon review of the domained samples, SRK elected to apply the capping pre-compositing for the
current estimate. To define the appropriate capping levels, SRK completed analysis of the grade
distributions using log probability plots and raw and log histograms Figure 14-8 to Figure 14-12 (with
the selected caps highlighted in yellow) to distinguish the grades at which samples have significant
impacts on the local estimation and whose effect is considered extreme.
SRK reviewed and updated the capping/composite strategy at Marmato as part of the PFS Mineral
Resource update. The updated capping has been based on a disintegration analysis of the log-
probability plots for the veins, disseminated and splay domains (Group 1000 to 3000), and using
percentile analysis of the Au and Ag log-probability plots for the porphyry and MDZ.
In the 2020 estimate, the selected capping limits are as follows:
• Veins: A 60 g/t Au cap in the major veins with large numbers of samples, dropping to 20 g/t
Au in veins with lower sampling density. A standard cap for all veins of 450 g/t Ag has been
selected. Additionally to limit the impact of potential high-grades within the channel sampling
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 194
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
from over-influencing the vein estimates, SRK has used a reduced cap in the second and third
search ranges which is discussed in more detail in Section 14.8.3
• Splay: A 30 g/t Au and 150 g/t silver (Ag) cap for all splays has been used
• Porphyry: Capping has been based on the variable grade profiles shown within the different
fault blocks. The capping values for gold vary from 4.5 g/t to 11.5 g/t Au. In comparison the
silver values were shown to demonstrate more variability across the various fault blocks with
the highest grades reported in the NE (Echandia Licence). The capping for silver therefore
varies from 23 g/t to 205 g/t Ag
• MDZ: Capping has been applied by Indicator grade shells used in the model ranging from 5.5
g/t Au and 25 g/t Ag, to 17.5 g/t Au and 25 g/t Ag, and 40 g/t Au cap and 50 g/t Ag, for the low,
medium and higher-grade components
VEIN_N< 9000
Column Cap Capped Percentile Capped% Lost Total
(%) Lost CV
(%) Count Weight Min Max Mean Variance CV
AU 35728 16849 0 605.1 6.293 194.3 2.22
AU 554.53 1 100% 0% 0.02% 0.40% 35728 16849 0 554.5 6.291 192.6 2.21
AU 493.18 2 99.99% 0.01% 0.08% 1.30% 35728 16849 0 493.2 6.288 188.9 2.19
AU 432.28 3 99.99% 0.01% 0.20% 2.30% 35728 16849 0 432.3 6.283 184.9 2.16
AU 300.02 10 99.98% 0.03% 0.50% 5.80% 35728 16849 0 300 6.263 171.0 2.09
AU 60 379 99.16% 1.10% 6.90% 31% 35728 16849 0 60 5.859 80.9 1.54
Source: SRK, 2020 Selected cap shown in orange
Figure 14-8: Disintegration Analysis Au (g/t) – Veins, Group 1000 (Vein_N<9000)
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 195
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
VEIN_N> 9000
Column Cap Capped Percentile Capped% Lost
Total (%) Lost CV
(%) Count Weight Min Max Mean Variance CV
AU 3221 1783 0 132 2.499 48.72 2.79
AU 103.72 3 99.88% 0.10% 0.90% 4.60% 3221 1783 0 103.7 2.476 43.55 2.66
AU 94.83 4 99.85% 0.10% 1.40% 6.90% 3221 1783 0 94.83 2.464 41.04 2.6
AU 81.44 6 99.78% 0.20% 2.50% 11% 3221 1783 0 81.44 2.436 36.32 2.47
AU 69.13 8 99.73% 0.20% 3.80% 16% 3221 1783 0 69.13 2.404 31.72 2.34
AU 54.44 12 99.64% 0.40% 5.80% 23% 3221 1783 0 54.44 2.355 25.92 2.16
AU 46.76 14 99.62% 0.40% 6.90% 26% 3221 1783 0 46.76 2.327 23.17 2.07
AU 28.92 30 99.26% 0.90% 11% 35% 3221 1783 0 28.92 2.227 16.3 1.81
AU 20 70 98.31% 2.20% 15% 42% 3221 1783 0 20 2.123 11.81 1.62
Source: SRK, 2020 Selected cap shown in orange
Figure 14-9: Disintegration Analysis Au (g/t) – Veins, Group 1000 (Vein_N>9000)
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 196
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
DISS < 9000
Column Cap Capped Percentile Capped% Lost Total (%)
Lost CV (%)
Count Weight Min Max Mean Variance CV
AU 26778 13090 0 947.1 2.375 64.5 3.38
AU 453.97 1 99.99% 0% 0.30% 9.10% 26778 13090 0 454 2.367 52.93 3.07
AU 268.4 2 99.99% 0.01% 0.70% 13% 26778 13090 0 268.4 2.36 47.64 2.92
AU 20 414 98.67% 1.50% 14% 53% 26778 13090 0 20 2.039 10.69 1.6
Source: SRK, 2020 Selected cap shown in orange
Figure 14-10: Disintegration Analysis Au (g/t) – Disseminated Vein, Group 2000 (Vein_N<9000)
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 197
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
DISS > 9000
Column Cap Capped Percentile Capped% Lost Total (%)
Lost CV (%)
Count Weight Min Max Mean Variance CV
AU 705 340.1 0 100.2 1.389 25.25 3.62
AU 53.52 1 99.85% 0.10% 4.70% 18% 705 340.1 0 53.52 1.323 15.27 2.95
AU 33.16 3 99.71% 0.40% 8.90% 30% 705 340.1 0 33.16 1.264 10.37 2.55
AU 26.32 4 99.62% 0.60% 11% 33% 705 340.1 0 26.32 1.239 8.91 2.41
AU 10 15 99.13% 2.10% 24% 53% 705 340.1 0 10 1.055 3.19 1.69
Source: SRK, 2020 Selected cap shown in orange
Figure 14-11: Disintegration Analysis Au (g/t) – Disseminated Vein, Group 2000 (Vein_N>9000)
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 198
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Column Cap Capped Percentile Capped% Lost Total (%)
Lost CV (%)
Count Weight Min Max Mean Variance CV
AU 7761 3712 0 1767 4.852 785.3 5.78
AU 927.29 2 99.98% 0.03% 2.20% 16% 7761 3712 0 927.3 4.747 527.2 4.84
AU 685.38 3 99.97% 0.04% 3.90% 26% 7761 3712 0 685.4 4.665 395.5 4.26
AU 405.62 4 99.95% 0.10% 6.70% 40% 7761 3712 0 405.6 4.525 243.8 3.45
AU 30 215 99.90% 2.80% 25% 71% 7761 3712 0 30 3.619 35.67 1.65
Source: SRK, 2020 Selected cap shown in orange
Figure 14-12: Disintegration Analysis Au (g/t) – Splays, (Group 3000)
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 199
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 200
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: Source: SRK, 2020
Figure 14-13: Percentile Analysis Au (g/t) – Porphyry Domain, (Group 4000)
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 201
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 14-7: Summary of Capping Sensitivity – MDZ Domain (Group 5000), Selected Capping Highlighted in Orange
Column _Filter Cap Capped Percentile Capped% Lost Total
(%) Lost CV
(%) Count Min Max Mean Variance CV
AU FBLOCK = 1 1377 0.001 306.4 1.914 73.36 4.48
AU FBLOCK = 1 20.911 15 98.90% 1.10% 15% 59% 1377 0.001 20.91 1.624 8.87 1.83
AU FBLOCK = 1 12.738 36 98% 2.60% 21% 65% 1377 0.001 12.74 1.509 5.44 1.55
AU FBLOCK = 1 10 45 97.40% 3.30% 25% 68% 1377 0.001 10 1.444 4.16 1.41
AU FBLOCK = 1 9 49 97.30% 3.60% 26% 70% 1377 0.001 9 1.417 3.72 1.36
AU FBLOCK = 1 7.895 56 96.60% 4.10% 28% 71% 1377 0.001 7.895 1.383 3.25 1.3
AU FBLOCK = 1 7.045 68 95.80% 4.90% 29% 72% 1377 0.001 7.045 1.35 2.85 1.25
AU FBLOCK = 1 6.085 83 95.10% 6% 32% 74% 1377 0.001 6.085 1.306 2.39 1.18
AU FBLOCK = 1 4.983 107 93.30% 7.80% 35% 76% 1377 0.001 4.983 1.241 1.84 1.09
AU FBLOCK = 1 4.387 123 92.10% 8.90% 37% 77% 1377 0.001 4.387 1.197 1.53 1.03
AU FBLOCK = 1 3.951 131 91.60% 9.50% 39% 78% 1377 0.001 3.951 1.161 1.32 0.99
AU FBLOCK = 1 - AU > 9
49 9.2 306.4 26.99 1992 1.65
AU FBLOCK = 1 - AU <= 9
1328 0.001 8.71 1.201 2.15 1.22
AU FBLOCK = 2 3095 0 61.1 1.459 8.81 2.03
AU FBLOCK = 2 38.421 7 99.90% 0.20% 1.10% 7.90% 3095 0 38.42 1.443 7.3 1.87
AU FBLOCK = 2 25 15 99.70% 0.50% 2.80% 16% 3095 0 25 1.418 5.84 1.7
AU FBLOCK = 2 15.7 40 99.30% 1.30% 5.80% 26% 3095 0 15.7 1.374 4.25 1.5
AU FBLOCK = 2 11.5 68 98.90% 2.20% 8.40% 33% 3095 0 11.5 1.337 3.34 1.37
AU FBLOCK = 2 9.6 78 98.70% 2.50% 9.90% 36% 3095 0 9.6 1.314 2.92 1.3
AU FBLOCK = 2 8.242 109 98.10% 3.50% 11% 39% 3095 0 8.242 1.292 2.59 1.25
AU FBLOCK = 2 6.92 135 97.30% 4.40% 13% 42% 3095 0 6.92 1.263 2.22 1.18
AU FBLOCK = 2 5.92 169 96.50% 5.50% 16% 45% 3095 0 5.92 1.232 1.91 1.12
AU FBLOCK = 2 4.98 221 95.30% 7.10% 18% 48% 3095 0 4.98 1.194 1.58 1.05
AU FBLOCK = 2 4 294 93.40% 9.50% 22% 52% 3095 0 4 1.138 1.22 0.97
AU FBLOCK = 2 - AU > 9.6
78 9.89 61.1 20.86 149.1 0.59
AU FBLOCK = 2 - AU <= 9.6
3017 0 9.6 1.206 2.05 1.19
AU FBLOCK = 3 226 0.04 53 1.564 18.91 2.78
AU FBLOCK = 3 10.79 4 99% 1.80% 18% 49% 226 0.04 10.79 1.287 3.36 1.42
AU FBLOCK = 3 8.84 7 98% 3.10% 20% 52% 226 0.04 8.837 1.257 2.85 1.34
AU FBLOCK = 3 7.65 9 97% 4% 22% 55% 226 0.04 7.649 1.222 2.36 1.26
AU FBLOCK = 3 5.06 14 96% 6.20% 28% 62% 226 0.04 5.055 1.132 1.43 1.06
AU FBLOCK = 3 4.64 16 95% 7.10% 29% 63% 226 0.04 4.635 1.111 1.28 1.02
AU FBLOCK = 3 3.60 21 94% 9.30% 33% 67% 226 0.04 3.601 1.051 0.91 0.91
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 202
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Column _Filter Cap Capped Percentile Capped% Lost Total
(%) Lost CV
(%) Count Min Max Mean Variance CV
AU FBLOCK = 3 3.44 23 93% 10.20% 33% 68% 226 0.04 3.44 1.041 0.86 0.89
AU FBLOCK = 3 3.19 25 92% 11.10% 35% 69% 226 0.04 3.192 1.022 0.78 0.86
AU FBLOCK = 3 2.83 28 91% 12.40% 37% 71% 226 0.04 2.826 0.991 0.65 0.81
AU FBLOCK = 3 2.54 32 90% 14.20% 38% 72% 226 0.04 2.544 0.964 0.56 0.77
AU FBLOCK = 3 - AU > 5.06
13 5.37 53 16.08 264.7 1.01
AU FBLOCK = 3 - AU <= 5.06
213 0.04 5.06 0.971 0.83 0.94
AU FBLOCK = 4 138 0.02 13.64 1.304 2.5 1.21
AU FBLOCK = 4 7.642 4 99% 2.90% 0.90% 2.90% 138 0.02 7.642 1.293 2.31 1.18
AU FBLOCK = 4 7.299 5 98% 3.60% 1.50% 4.50% 138 0.02 7.299 1.284 2.21 1.16
AU FBLOCK = 4 6.136 5 97% 3.60% 4.20% 11% 138 0.02 6.136 1.249 1.82 1.08
AU FBLOCK = 4 4.5 7 96% 5.10% 8.80% 20% 138 0.02 4.5 1.189 1.33 0.97
AU FBLOCK = 4 4.341 8 95% 5.80% 9.40% 21% 138 0.02 4.341 1.181 1.27 0.96
AU FBLOCK = 4 3.433 11 94% 8% 13% 27% 138 0.02 3.433 1.13 0.99 0.88
AU FBLOCK = 4 3.286 12 93% 8.70% 14% 28% 138 0.02 3.286 1.12 0.95 0.87
AU FBLOCK = 4 3.094 13 92% 9.40% 15% 30% 138 0.02 3.094 1.104 0.88 0.85
AU FBLOCK = 4 2.954 14 91% 10.10% 16% 31% 138 0.02 2.954 1.092 0.84 0.84
AU FBLOCK = 4 2.92 14 90% 10.10% 17% 31% 138 0.02 2.92 1.089 0.82 0.83
AU FBLOCK = 4 - AU > 4.5
7 4.61 13.64 6.929 3.53 0.27
AU FBLOCK = 4 - AU <= 4.5
131 0.02 4.44 1.024 0.81 0.88
AU FBLOCK = 5 622 0 47.91 1.787 11.03 1.86
AU FBLOCK = 5 11.87 13 99% 2.10% 7.70% 30% 622 0 11.87 1.65 4.62 1.3
AU FBLOCK = 5 9.732 18 98% 2.90% 9.50% 33% 622 0 9.732 1.617 4.03 1.24
AU FBLOCK = 5 9 20 97.30% 3.20% 10% 35% 622 0 9 1.6 3.76 1.21
AU FBLOCK = 5 6.962 32 96% 5.10% 14% 40% 622 0 6.962 1.536 2.95 1.12
AU FBLOCK = 5 6.13 37 95% 5.90% 16% 42% 622 0 6.13 1.498 2.57 1.07
AU FBLOCK = 5 5.365 45 94% 7.20% 19% 45% 622 0 5.365 1.454 2.2 1.02
AU FBLOCK = 5 5.164 49 93% 7.90% 19% 46% 622 0 5.164 1.441 2.09 1
AU FBLOCK = 5 4.767 57 92% 9.20% 21% 48% 622 0 4.767 1.411 1.88 0.97
AU FBLOCK = 5 4.199 64 91% 10.30% 24% 50% 622 0 4.199 1.363 1.58 0.92
AU FBLOCK = 5 3.891 72 90% 11.60% 25% 52% 622 0 3.891 1.333 1.42 0.89
AU FBLOCK = 5 - AU > 9
20 9.06 47.91 15.93 129.4 0.71
AU FBLOCK = 5 - AU <= 9
602 0 8.68 1.394 2.29 1.09
AU FBLOCK = 6 3651 0 344.4 1.712 64.29 4.68
AU FBLOCK = 6 54.754 7 99.90% 0.20% 8.50% 54% 3651 0 54.75 1.567 11.54 2.17
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 203
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Column _Filter Cap Capped Percentile Capped% Lost Total
(%) Lost CV
(%) Count Min Max Mean Variance CV
AU FBLOCK = 6 30 23 99.60% 0.60% 11% 61% 3651 0 30 1.519 7.8 1.84
AU FBLOCK = 6 20 40 99.50% 1.10% 14% 65% 3651 0 20 1.477 5.86 1.64
AU FBLOCK = 6 15 56 99.20% 1.50% 16% 68% 3651 0 15 1.443 4.8 1.52
AU FBLOCK = 6 11.5 91 98.70% 2.50% 18% 70% 3651 0 11.5 1.407 3.95 1.41
AU FBLOCK = 6 10 113 98.30% 3.10% 19% 71% 3651 0 10 1.385 3.55 1.36
AU FBLOCK = 6 9 134 97.90% 3.70% 20% 72% 3651 0 9 1.366 3.24 1.32
AU FBLOCK = 6 8 159 97.40% 4.40% 22% 73% 3651 0 8 1.343 2.9 1.27
AU FBLOCK = 6 7 193 96.70% 5.30% 23% 74% 3651 0 7 1.314 2.55 1.21
AU FBLOCK = 6 5 288 92.50% 7.90% 28% 77% 3651 0 5 1.228 1.75 1.08
AU FBLOCK = 6 - AU > 11.5
91 11.67 344.4 36.18 3849 1.72
AU FBLOCK = 6 - AU <= 11.5
3560 0 11.32 1.28 2.71 1.29
AU FBLOCK = 7 2394 0 116.3 1.744 12.44 2.02
AU FBLOCK = 7 18.73 41 99% 1.70% 5.20% 19% 2394 0 18.73 1.653 7.36 1.64
AU FBLOCK = 7 12.54 71 98.30% 3% 10% 29% 2394 0 12.54 1.57 5.06 1.43
AU FBLOCK = 7 10.00 84 97.90% 3.50% 13% 34% 2394 0 10 1.522 4.13 1.34
AU FBLOCK = 7 9.00 106 97.30% 4.40% 14% 36% 2394 0 9 1.497 3.73 1.29
AU FBLOCK = 7 8.00 122 96.80% 5.10% 16% 39% 2394 0 8 1.468 3.32 1.24
AU FBLOCK = 7 7.00 152 95.80% 6.30% 18% 41% 2394 0 7 1.432 2.89 1.19
AU FBLOCK = 7 6.00 179 94.90% 7.50% 21% 45% 2394 0 6 1.385 2.42 1.12
AU FBLOCK = 7 5.00 232 92% 9.70% 24% 48% 2394 0 5 1.325 1.92 1.05
AU FBLOCK = 7 4.17 290 91% 12.10% 28% 52% 2394 0 4.168 1.259 1.49 0.97
AU FBLOCK = 7 3.76 317 90% 13.20% 30% 54% 2394 0 3.758 1.219 1.27 0.93
AU FBLOCK = 7 - AU > 9
106 9.09 116.3 18.04 105 0.57
AU FBLOCK = 7 - AU <= 9
2288 0 8.82 1.286 2.21 1.16
Source: SRK, 2020 Selected cap shown in orange
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 204
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SRK, 2020
Figure 14-14: Percentile Analysis Au (g/t) – MDZ Domain, (Group 5000)
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 205
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 14-8: Summary of Capping Sensitivity – MDZ Domain (Group 5000), selected capping highlighted in orange
Column _Filter Cap Capped Percentile Capped% Lost Total
(%) Lost CV
(%) Count Min Max Mean Variance CV
AU
LG MDZ (KZONE 5000)
8157 0 65.54 0.547 3.1 3.22
AU 20 13 99.80% 0.20% 4.60% 27% 8157 0 20 0.522 1.51 2.35
AU 12 20 99.70% 0.20% 7.40% 37% 8157 0 12 0.507 1.04 2.02
AU 10 28 99.70% 0.30% 8.50% 40% 8157 0 10 0.501 0.92 1.92
AU 7 50 99.50% 0.60% 11% 46% 8157 0 7 0.487 0.7 1.72
AU 5.5 74 99.10% 0.90% 13% 50% 8157 0 5.5 0.476 0.58 1.60
AU 4 114 98.60% 1.40% 16% 56% 8157 0 4 0.458 0.43 1.43
AU 3 168 98% 2.10% 19% 60% 8157 0 3 0.441 0.33 1.30
AU 2.5 214 97.40% 2.60% 21% 62% 8157 0 2.5 0.43 0.27 1.22
AU 2 284 96.50% 3.50% 24% 65% 8157 0 2 0.415 0.22 1.13
AU 1.5 443 94.60% 5.40% 28% 68% 8157 0 1.5 0.393 0.16 1.02
AU 1 812 90% 10% 35% 73% 8157 0 1 0.356 0.1 0.88
AU INDZONE = 0 - AU > 5.5
74 5.52 65.54 13.36 139.9 0.88
AU INDZONE = 0 - AU <= 5.5
8083 0 5.49 0.43 0.35 1.37
AU
MG MDZ (KZONE 5001)
8413 0 345.9 1.548 26.43 3.32
AU 75.0 3 99.90% 0.04% 2.80% 35% 8413 0 75 1.505 10.46 2.15
AU 40.0 11 99.90% 0.10% 4.20% 42% 8413 0 40 1.483 8.07 1.92
AU 25.0 26 99.70% 0.30% 6.70% 50% 8413 0 25 1.445 5.79 1.66
AU 17.5 48 99.40% 0.60% 8.80% 55% 8413 0 17.5 1.411 4.48 1.50
AU 13.5 76 99.10% 0.90% 11% 58% 8413 0 13.5 1.381 3.65 1.38
AU 10.0 113 98.60% 1.30% 13% 62% 8413 0 10 1.342 2.83 1.25
AU 9.0 132 98.50% 1.60% 14% 63% 8413 0 9 1.327 2.59 1.21
AU 7.0 202 97.60% 2.40% 17% 66% 8413 0 7 1.289 2.09 1.12
AU 6.0 267 96.80% 3.20% 19% 68% 8413 0 6 1.262 1.8 1.06
AU 5.0 355 95.80% 4.20% 21% 70% 8413 0 5 1.225 1.49 1.00
AU 4.0 515 90% 6.10% 24% 72% 8413 0 4 1.174 1.16 0.92
AU INDZONE = 1 - AU > 17.5
48 18.4 345.9 41.46 2560 1.22
AU INDZONE = 1 - AU <= 17.5
8365 0 17.49 1.319 3.01 1.32
AU
HG MDZ (KZONE 5002)
6615 0.001 246.5 3.841 78.15 2.3
AU 100 10 99.80% 0.20% 2.70% 19% 6615 0.001 100 3.737 48.5 1.86
AU 62.5 20 99.70% 0.30% 4.80% 28% 6615 0.001 62.5 3.658 36.67 1.66
AU 45 38 99.40% 0.60% 6.70% 34% 6615 0.001 45 3.586 29.55 1.52
AU 40 48 99.30% 0.70% 7.50% 36% 6615 0.001 40 3.553 27.01 1.46
AU 35 56 99.20% 0.80% 8.50% 39% 6615 0.001 35 3.515 24.4 1.41
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 206
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Column _Filter Cap Capped Percentile Capped% Lost Total
(%) Lost CV
(%) Count Min Max Mean Variance CV
AU 30 72 98.90% 1.10% 9.70% 42% 6615 0.001 30 3.468 21.72 1.34
AU 25 89 98.70% 1.30% 11% 45% 6615 0.001 25 3.408 18.82 1.27
AU 20 136 97.90% 2.10% 13% 48% 6615 0.001 20 3.326 15.71 1.19
AU 15 218 96.70% 3.30% 17% 53% 6615 0.001 15 3.193 11.97 1.08
AU 12.5 290 95.60% 4.40% 19% 56% 6615 0.001 12.5 3.097 9.96 1.02
AU 10 438 90% 6.60% 23% 59% 6615 0.001 10 2.962 7.76 0.94
AU INDZONE = 2 - AU > 40
48 40.08 246.5 79.73 2637 0.64
AU INDZONE = 2 - AU <= 40
6567 0.001 38.92 3.287 17.43 1.27
Source: SRK, 2020
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 207
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Overall, these levels remain consistent with the capping levels used previously, with application of the
capping restrictions supported by improvements in the definition of the grade populations for the veins
from the channel sampling.
In general, SRK aims to limit the impact of the capping to less than 5% change in the mean value,
however in some cases with extreme outliers, the change in the mean exceeds 5%. The highly
positively skewed nature of the gold distributions and the very high values seen in the population result
in the significant changes in the mean values. A comparison of the raw versus capped values is shown
in Table 14-9.
Table 14-9: Comparison Raw vs Composite Statistics
Element KZONE Count Minimum
(g/t) Maximum
(g/t) Mean
(g/t) Variance
Standard Deviation
CoV
Samples
AU 1000 36,387 0 605.09 6.19 192.07 13.86 2.24
AU 1001 3,312 0 132.02 2.46 46.82 6.84 2.78
AU 2000 26,860 0 947.13 2.38 64.35 8.02 3.38
AU 2001 709 0 100.24 1.38 24.85 4.98 3.60
AU 3000 7,669 0 1,766.57 4.87 793.02 28.16 5.78
AU 4000 12,585 0 891.03 1.78 78.68 8.87 4.99
AU 5000 8,130 0 65.54 0.46 1.85 1.36 2.98
AU 5001 8,386 0 345.92 1.39 14.59 3.82 2.75
AU 5002 6,582 0.001 246.50 3.52 55.39 7.44 2.11
AG 1000 36,140 0 1,995.00 27.82 1,250.56 35.36 1.27
AG 1001 3,295 0 1,160.00 20.24 3,956.96 62.90 3.11
AG 2000 26,747 0 537.50 18.89 511.36 22.61 1.20
AG 2001 708 0 182.56 16.29 414.73 20.36 1.25
AG 3000 7,545 0 1,234.75 21.15 1,182.00 34.38 1.63
AG 4000 12,475 0 5,613.00 14.50 6,874.16 82.91 5.72
AG 5000 8,146 0 7,980.00 3.70 11,318.47 106.39 28.79
AG 5001 8,377 0 290.84 3.51 57.23 7.56 2.16
AG 5002 6,581 0 326.66 5.49 124.61 11.16 2.03
Element KZONE Count Minimum
(g/t) Maximum
(g/t) Mean
(g/t) Variance
Standard Deviation
CoV Difference
(%)
Comp
AU 1000 20,251 0.001 40.00 5.81 51.71 7.19 1.24 -6.1
AU 1001 1,240 0.001 15.00 2.00 8.02 2.83 1.42 -18.9
AU 2000 18,016 0.001 15.00 2.07 7.61 2.76 1.33 -13
AU 2001 347 0.001 7.00 0.96 1.81 1.34 1.40 -30.5
AU 3000 3,007 0.001 20.00 3.83 19.90 4.46 1.17 -21.4
AU 4000 7,708 0 11.50 1.39 2.19 1.48 1.07 -21.9
AU 5000 5,511 0 5.50 0.42 0.28 0.53 1.25 -8
AU 5001 5,114 0.001 17.50 1.32 1.69 1.30 0.98 -4.8
AU 5002 3,636 0.0267 40.00 3.34 12.19 3.49 1.05 -5.2
AG 1000 20,251 0.001 300.00 28.09 821.14 28.66 1.02 1
AG 1001 1,240 0.001 110.00 15.03 541.48 23.27 1.55 -25.7
AG 2000 18,016 0.001 300.00 18.90 426.21 20.64 1.09 0.1
AG 2001 347 0.001 80.00 15.42 321.34 17.93 1.16 -5.3
AG 3000 3,007 0.001 110.00 20.38 403.12 20.08 0.99 -3.6
AG 4000 7,654 0 205.00 10.78 387.59 19.69 1.83 -25.7
AG 5000 5,514 0 25.00 2.17 9.79 3.13 1.44 -41.4
AG 5001 5,113 0 30.00 3.27 17.64 4.20 1.29 -6.9
AG 5002 3,635 0 50.00 5.19 42.46 6.52 1.26 -5.5
Source: SRK, 2020
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 208
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
14.4.2 Compositing
Prior to the undertaking of grade interpolation, samples need to be composited to equal lengths for
constant sample volume, honoring sample support theories.
SRK has undertaken a sample composite analysis for gold in order to determine the optimal sample
composite length for grade interpolation. This investigated both changes in composite length and
minimum composite lengths for inclusion. The analysis compared the resultant mean grade against
the length weighted raw sample mean grades, and the percentage of samples excluded when applying
the minimum composite length. The results for the composite length analysis are summarized in Figure
14-15.
In addition to the analysis completed, SRK has reviewed the histograms of the raw sampling lengths
within the various domains (Figure 14-15). During the review SRK noted the following:
• A review of the sample lengths indicated that the mean sample length is approximately 0.5 m
veins, but 45% of the samples are between 0.5 to 1 m, with a further 5% between 1 and 2 m.
• The average length of the raw sampling in the porphyry and deep mineralization is 1 m, with
the majority of the samples ranging between 1 to 2 m.
Given the narrow nature of the veins, it is SRK’s view that increasing the sample lengths to 2 m is
preferred so only a single composite will exist across in the vein in narrow areas. SRK has elected to
also use the 2 m composite lengths for all other domains.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 209
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SRK, 2020
Figure 14-15: Summary Histograms and Cumulative Frequency of Raw Sample Lengths per Domain
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 210
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Summary descriptive statistics are provided in Table 14-10 for comparison of uncapped and capped
composited data for Au, and Ag. Overall, capping has reduced the highest yield outlier data while not
materially affecting the population of data. It is the opinion of the QP that capping has reduced the
effect of high-yield outlier values and should be considered during the estimation for selected domains,
to ensure there is not over influence of the high-grades beyond first search ranges. This restriction is
described in more detail in Section 14.8.3.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 211
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 14-10: Comparison Statistics
Field Group Wgt Field
Num Trace
Minimum Maximum Mean Variance Standard Deviation
Cov
Samples
AU 1000 Length 36387 0 605.09 6.19 192.07 13.86 2.24
AU 1001 Length 3312 0 132.02 2.46 46.82 6.84 2.78
AU 2000 Length 26860 0 947.13 2.38 64.35 8.02 3.38
AU 2001 Length 709 0 100.24 1.38 24.85 4.98 3.60
AU 3000 Length 7669 0 1,766.57 4.87 793.02 28.16 5.78
AU 4000 Length 12585 0 891.03 1.78 78.68 8.87 4.99
AU 5000 Length 8130 0 65.54 0.46 1.85 1.36 2.98
AU 5001 Length 8386 0 345.92 1.39 14.59 3.82 2.75
AU 5002 Length 6582 0.001 246.50 3.52 55.39 7.44 2.11
AG 1000 Length 36140 0 1,995.00 27.82 1,250.56 35.36 1.27
AG 1001 Length 3295 0 1,160.00 20.24 3,956.96 62.90 3.11
AG 2000 Length 26747 0 537.50 18.89 511.36 22.61 1.20
AG 2001 Length 708 0 182.56 16.29 414.73 20.36 1.25
AG 3000 Length 7545 0 1,234.75 21.15 1,182.00 34.38 1.63
AG 4000 Length 12475 0 5,613.00 14.50 6,874.16 82.91 5.72
AG 5000 Length 8146 0 7,980.00 3.70 11,318.4
7 106.39 28.79
AG 5001 Length 8377 0 290.84 3.51 57.23 7.56 2.16
AG 5002 Length 6581 0 326.66 5.49 124.61 11.16 2.03
Field Group Wgt Field
Num Trace
Minimum Maximum Mean Variance Standard Deviation
Cov
Composites
AU 1000 Length 20251 0.001 40.00 5.81 51.71 7.19 1.24
AU 1001 Length 1240 0.001 15.00 2.00 8.02 2.83 1.42
AU 2000 Length 18016 0.001 15.00 2.07 7.61 2.76 1.33
AU 2001 Length 347 0.001 7.00 0.96 1.81 1.34 1.40
AU 3000 Length 3007 0.001 20.00 3.83 19.90 4.46 1.17
AU 4000 Length 7708 0 11.50 1.39 2.19 1.48 1.07
AU 5000 Length 5511 0 5.50 0.42 0.28 0.53 1.25
AU 5001 Length 5114 0.001 17.50 1.32 1.69 1.30 0.98
AU 5002 Length 3636 0.0267 40.00 3.34 12.19 3.49 1.05
AG 1000 Length 20251 0.001 300.00 28.09 821.14 28.66 1.02
AG 1001 Length 1240 0.001 110.00 15.03 541.48 23.27 1.55
AG 2000 Length 18016 0.001 300.00 18.90 426.21 20.64 1.09
AG 2001 Length 347 0.001 80.00 15.42 321.34 17.93 1.16
AG 3000 Length 3007 0.001 110.00 20.38 403.12 20.08 0.99
AG 4000 Length 7654 0 205.00 10.78 387.59 19.69 1.83
AG 5000 Length 5514 0 25.00 2.17 9.79 3.13 1.44
AG 5001 Length 5113 0 30.00 3.27 17.64 4.20 1.29
AG 5002 Length 3635 0 50.00 5.19 42.46 6.52 1.26
Source: SRK, 2020
14.5 Density
Density measurements are made routinely by CGM geologists during core logging and sample
preparation. Each geologist tries to make one density measurement daily and to complete the
calculation the following procedure has been used:
• A piece of unbroken core is selected
• A 14 to 15 cm long piece of core from the interval of interest is cut
• As the core is cut, the geologist must ensure that the cut is perpendicular to the core axis and
does not result in the loss of any material along the cut line
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 212
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
• The length of the core is measured, and the diameter of the core is determined with a digital
caliper at 3 to 4 cm intervals and the average diameter is calculated
• The core is weighed on a digital balance and the density is calculated as follows:
o Pi * core diameter * core length = core volume
o Core weight/core volume = density
SRK completed a statistical review of the density measurements in the database provided up to
drillhole MT-IU-031. The database included a total of 3,370 samples with results ranging from 2.01 to
4.75 g/cm3. The majority of the samples have been taken within the various phases of porphyry
mineralization which have a range of 2.04 to 3.85 g/cm3. The highest measured density based on the
drillcore is taken from the vein material which returned an average of 3.39 g/cm3, but also contained
the highest variability. A summary of the measured density per major rock type is shown Table 14-11.
Table 14-11: Summary of Density Statistics by Rock Type and Selected Density
Rock Type Count Minimum Maximum Mean Std. Dev. Selected Density
BX 16 2.62 2.92 2.73 0.08 2.7
FLT 4 2.5 2.80 2.68 0.11
INT 46 2.42 2.80 2.71 0.07 2.71
METASED 99 2.235 3.44 2.82 0.17 2.8
P1 1840 2.1 3.42 2.67 0.10 2.67
P2 1007 2.04 3.85 2.68 0.11 2.68
P3 53 2.29 2.81 2.64 0.09 2.64
P4 200 2.18 3.18 2.70 0.09 2.7
P5 25 2.49 2.78 2.60 0.07 2.6
sap 1 2.92 2.92 2.92 0.00
sedt 12 2.63 2.93 2.77 0.09 2.77
ven 44 2.01 4.75 3.69 0.63 2.95
volc 23 2.4 2.91 2.79 0.10 2.79
Grand Total 3370 2.01 4.75 2.69 0.17
Source: SRK, 2020
SRK has elected to use a lower density for the veins than defined from a pure statistical basis. The
methodology behind the reduction, in conjunction with interviews with onsite personnel during the site
visit, are summarized from the PEA below:
In the 2017 Mineral Resource, the density has been grouped into three main units, which are
comprised of the porphyry, schist and vein rock types. SRK has compared these values to the 2017
model and discussed with the current mining operations team. The porphyry domain has been kept at
the same value as the 2017 block model which used an average density of 2.7 g/cm3. SRK still
considers this to be reasonable but comments that it could fluctuate between 2.65 to 2.70 g/cm3 and
should therefore be reviewed within the MDZ based on the results of the current on-going infill drilling
program being completed by the Company for preparation for a future PFS. If a lower density is
applied, it would impact the overall tonnage less than 2%.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 213
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
The mine reported that it currently uses a lower density for the vein material based on the feed at the
plant closer to 2.7 to 2.9 g/cm3 range and that there could be risk of overstating the tonnage using a
3.4 g/cm3 as shown from the statistical analysis. The basis for the lower density is likely due to
favorable sampling of higher sulfides in the core which do not reflect the mined stope widths. Therefore,
to provide a more realistic assessment of the density, SRK completed a statistical review of the vein
samples using histograms and log-probability plots which still indicates a density of over 3 g/cm3 and
is reasonable based even on extreme capping of values greater than 3.25 g/cm3.
Cap Capped Percentile Capped% Count Min Max Mean
71 2.01 4.75 3.386
4.622 1 99% 1.40% 71 2.01 4.622 3.384
4.549 2 98% 2.80% 71 2.01 4.549 3.383
4.516 3 97% 4.20% 71 2.01 4.516 3.382
4.495 3 96% 4.20% 71 2.01 4.495 3.381
4.485 4 95% 5.60% 71 2.01 4.485 3.38
4.475 5 94% 7.00% 71 2.01 4.475 3.38
4.461 5 93% 7.00% 71 2.01 4.461 3.379
4.453 6 92% 8.50% 71 2.01 4.453 3.378
4.407 7 91% 9.90% 71 2.01 4.407 3.374
4.336 8 90% 11.30% 71 2.01 4.336 3.366
3.25 33 53.50% 46.50% 71 2.01 3.25 3.029
DEN_MAJOR = VEN - DENSITY > 3.25 33 3.4 4.75 4.018
DEN_MAJOR = VEN - DENSITY <= 3.25 38 2.01 3.25 2.837
Source: SRK, 2019
Figure 14-16: Log Probability Plot of Density Measurements Logged as Vein
To reflect density values more consistent with the mining, SRK has updated the statistical analysis
using a sub-set of the density database and the veins wireframes, generated from the geological model
using a halo of 0.5 m on either side of the veins and re-ran the analysis. The results of the analysis
returned a mean density of 2.97 g/cm3 (rounded to 2.95 g/cm3). In discussion with the CGM geological
team it was felt this was a more reasonable representation of the density for the vein domain. In
summary, the final density values used in the 2020 Mineral Resources are presented in Table 14-12.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 214
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 14-12: Density assigned per rocktype in 2020 Mineral Resources
ROCK ROCKTYPE COUNT DENSITY
1 P1 1840 2.670
2 P2 1007 2.680
3 P3 53 2.640
4 P4 200 2.700
5 P5 25 2.600
6 METASED 99 2.800
7 BRECCIA 16 2.700
8 INT 46 2.710
9 VOLC 23 2.790
VEN 44 2.950
Source: SRK, 2020
14.6 Variogram Analysis and Modeling
The composite drillhole database was imported into Datamine™ (Groups 1000 to 3000) and Snowden
Supervisor (Groups 4000 to 5000) software for the geostatistical analysis. Semi-variograms have been
completed for both gold and silver values.
SRK tested both omni-directional and directional variograms for all domains and both key elements.
When considering the directional variograms, SRK rotated the key search orientations to be down dip
and strike of the main mineralization directions. Due to the variable directions associated with the
veins, this returned poor results for domains (Groups 1000 to 4000) and therefore an omni-directional
variogram was preferred in the final model (Figure 14-17). SRK considers the use of omni-directional
variograms on the veins to be appropriate as the mineralization has been limited across the width of
the veins by a hard boundary, this results in orientations more like a plate than a ball when used during
the estimation process.
In Group 4000, the mineralization is a result of multiple orientations from the vein models causing
fractures/pockets to host the mineralization. No single primary orientation exists which results in a
stable variogram during the analysis. In order to define variograms of sufficient clarity to be modelled,
the data has been calculated using omni variograms and normal scored transformed variograms
(which removes the influence of some of the variability to a degree).
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 215
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 216
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 217
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SRK, 2020
Figure 14-17: Omni Directional Variograms Defined for Au and Ag for Domains Group = 1000 – 4000
SRK utilized directional variography within domain 5000, which has been rotated to a dip of 80° to the
south west (azimuth 210), the modelled experimental semi-variograms are shown in Figure 14-18 and
Figure 14-19.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 218
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SRK 2020
Figure 14-18: Group 5000 Au Directional Semi-Variograms
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 219
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SRK, 2020
Figure 14-19: Group 5000 Ag Directional Semi-Variograms
Spatial continuity was calculated only for Au and Ag by domain as the primary economic variable of
interest. The modelled semi-variograms used in the estimation process are summarized in
Table 14-13.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 220
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 14-13: Summary of Variogram Parameters per Group
Group = 1000
Group = 2000 Disseminated
Group = 3000 Splays
Group = 4000 Porphyry
Group=5000 MDZ
VREFNUM 1001 1002 2001 2002 3001 3002 4001 4002 5001 5002 5003
VDESC Au Ag Au Ag Au Ag Au Ag Au
MDZ Ag
MDZ Au (LG)
MDZ
Rotation (Azi)
120 120 120
Rotation (dip)
-80 -80 -80
NUGGET 0.2 0.15 0.4 0.2 0.35 0.2 0.47 0.47 0.42 0.242 0.3
Range1 (X) 3 4.5 4 5 2 2 4 13 8 17 4
Range1 (Y) 3 4.5 4 5 2 2 4 13 5 10 5
Range1 (Z) 3 4.5 4 5 2 2 4 13 5 5 2
Sill 1 0.3 0.172 0.4 0.2 0.12 0.25 0.32 0.23 0.36 0.396 0.21
Range2 (X) 20 30.4 28 40 13 14.5 14 30 24 123 16
Range2 (Y) 20 30.4 28 40 13 14.5 14 30 12 32 33
Range2 (Z) 20 30.4 28 40 13 14.5 14 30 12 16 22
Sill 2 0.09 0.121 0.2 0.6 0.08 0.06 0.18 0.23 0.15 0.362 0.3
Range3 (X) 350 400 90 79.1 50 98 85 83
Range3 (Y) 350 400 90 79.1 50 98 60 115
Range3 (Z) 350 400 90 79.1 50 98 30 33
Sill 3 0.11 0.117 0.3 0.49 0.2 98 0.07 0.19
Source: SRK 2020 Note: All structures modelled using a spherical model
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 221
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
14.7 Block Model
SRK has produced a parent block model with block dimensions of 5 by 10 by 10 m (X, Y, Z), as a
function of the sample spacing within the veins. The block size represents a change in the 5 by 5
by 5 m block used in the PEA. Test work undertaken using the variograms for the MDZ looking at
the slope of regression and kriging efficiency suggested increasing the block size to 5 by 10 by
10 m block size was appropriate, the decision was taken to maintain the 5 m block size across
strike to reflect potential for selectivity for mining.
SRK acknowledges a larger block size could be more appropriate in areas of wider spaced drilling, but
the decision was taken to use a uniform block size across the deposit in conjunction with the mining
team. Sub-blocking has been allowed to a resolution 0.5 m along strike, 0.5 m across strike and 1 m
in the vertical direction to provide an appropriate geometric representation.
Given the orientation of the orebody striking to the NW, the decision was made to rotate the database
(for block model grade interpolation) from UTM coordinates through 55° into a N-S local grid
orientation, to enable an improved representation of grade continuity along strike. To rotate the
interpretation the “CDTRAN” Datamine™ command has been utilized. The details of the block model
origin, rotation and local dimensions are shown in Table 14-4.
Table 14-14: Block Model Prototype (DatamineTM format)
Dimension Origin (UTM)
Origin (Local)
Block Size
Number of Blocks
Rotation Min Sub-
blocking (m)
X 1,163,465 0 5 430 - 0.5
Y 1,096,426 0 10 175 - 0.5
Z 0 0 10 210 -55 1
Source: SRK, 2020
Using the wireframes created and described in Section 14.2 several codes have been developed to
describe each of the major geological properties of the rock types. Table 14-15 summarizes geological
fields created within the geological model and the codes used.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 222
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 14-15: Summary of Key Fields in Block Model
Field Name Description
SVOL Search Volume reference (range from 1 to 3)
KVAR Kriging Variance
MDIST Transformed distance to samples
NSAM Number of samples used to estimate the block
AU Final Gold Estimate using for Reporting
AG Final Silver Estimate using for Reporting
AUOK Gold Estimate using OK
AGOK Silver Estimate using OK
AUIDW Gold Estimate using IDW (Power 2)
AGIDW Silver Estimate using IDW (Power 2)
AUNN Gold NN Methodology
AGNN Silver NN Methodology
RESCAT Classification
GROUP Mineralized structures grouped by domain
VEIN_N Vein coding for individual mineralized structure GROUP1000 coding
DISS Vein coding for individual mineralized structure GROUP2000 coding
SPLAY Vein coding for individual mineralized structure GROUP3000 coding
DENSITY Density of the rock
DEPLETE Mined out areas
ROCK Coding for Major Rock type
LICENCE Mining Licence
MINZONE Mineralization Zone (Epithermal vs Mesothermal)
INDZONE Indicator domain used in MDZ domain
TRDIP Search Orientation information (True Dip)
TRDIPDIR Search Orientation information (True Dip Direction)
Source: SRK, 2020
14.8 Estimation Methodology
14.8.1 Theoretical Analysis
A Kriging Neighborhood Analysis (KNA) exercise has been completed for gold, in order to optimize
the parameters used in the estimation and kriging calculations. Initial grade estimation was undertaken
in Snowden Supervisor using the KNA utility. To complete the exercise, a number of scenarios were
tested using various estimation and kriging parameters. Different input parameters have been changed
and the differences in the slope of regression, kriging efficiency and impact on the negative kriging
weights. The following parameters were adjusted during the analysis:
• Block Size
• Minimum and maximum number of samples
• Search ellipse sizes
• Discretization
• Orientation of search ellipse
The results of the KNA analysis for the MDZ are shown in Figure 14-20. SRK selected to use a 5 by
10 by 10 m block based on the mean slope of regression (0.86) showing a minor improvement on the
10 by 10 by 10 m block (0.85), while still reflecting the potential across strike variability.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 223
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SRK, 2020
Figure 14-20: Group 5000 (MDZ), KNA Analysis Using Snowden Supervisor
Within the MDZ, SRK selected a theoretical minimum of five composites and maximum of 20
composites using the example shown. The maximum of 20 composites was selected as the number
of negative weights increased significantly at higher values, for relatively low increases in mean of the
slope of regression.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 224
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Once the theorical parameters were defined, SRK completed a number of initial estimates in order to
assess if suitable grade estimates were occurring using the selected parameters. Blocks estimates
were completed in Datamine™ and the following data fields were analyzed to assess quality: kriging
variance; number of samples; and proportion of blocks estimated in each search volume. Additional
fields monitored included the resultant grade in comparison with the sample data.
The Datamine™ block models have been estimated using a nested search format with three searches
used in all estimates. The first search represents an optimized search distance (selected from a kriging
sensitivity analysis), ensuring (in general) that block estimates use a minimum of two drillholes, while
the second and third search volumes use expansion factors that produce more smoothed block
estimates, appropriate to the limit of geological continuity. The third expansion volume was sufficient
to ensure that all appropriate blocks (in areas with reasonable geological confidence) were assigned
grade values. These blocks were generally classified with lower confidence, and in areas of uncertainty
trimmed out of the mineral resources due to a lack of strike or dip continuity.
The optimum parameters selected allowed an appropriate proportion of block estimates in the initial
search volumes, whilst achieving a reduction in variance and a relative increase in slope of regression
(in SVOL 1 and 2) without excessive smoothing. A summary of the analysis is shown in Table 14-16.
Based on the outcome of the validation process, SRK has selected to use either OK algorithm, or ID2
estimates to compile the final grade estimates. Typically zones with larger sample populations are
supported by OK, while zones with less data are supported by ID2 (splays).
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 225
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 14-16: Summary of Datamine Estimates by Search Volume and Validation by Estimation Type (OK, ID, NN)
Group SVOL Tonnes (t) %
Volume AUOK
(g/t) AUID (g/t)
AUNN (g/t)
AGOK (g/t)
AGID (g/t)
AGNN (g/t)
KVAR Transform DIST Number Samples
1000
1 1,571,645 13.0 5.95 5.89 5.66 28.09 27.95 26.97 0.17 0.08 6.5
2 6,106,968 50.6 3.48 3.38 3.20 18.66 18.25 17.42 0.20 0.07 6.4
3 4,399,720 36.4 2.58 2.49 2.45 15.72 15.55 15.24 0.24 0.03 5.6
2000
1 804,485 70.6 1.99 1.98 1.96 18.76 18.81 18.75 0.29 0.06 7.0
2 299,154 26.3 1.79 1.77 1.76 15.38 15.29 14.89 0.37 0.06 7.1
3 35,147 3.1 1.46 1.38 1.42 14.62 14.24 14.16 0.55 0.04 4.1
3000
1 338,954 42.4 3.89 3.89 3.78 20.12 20.15 19.70 0.21 0.05 5.8
2 336,578 42.1 3.09 3.03 2.83 15.24 15.16 14.81 0.33 0.05 5.8
3 124,717 15.6 3.39 3.35 3.49 21.21 21.28 22.42 0.50 0.05 2.6
4000
1 2,809,547 24.0 1.44 1.43 1.42 10.05 9.93 9.76 0.38 0.49 6.7
2 5,846,330 50.0 1.49 1.48 1.42 11.93 11.79 11.84 0.41 0.77 8.1
3 3,032,303 25.9 1.46 1.48 1.49 10.00 9.97 9.90 0.46 0.72 6.6
5000
1 12,087,681 16.5 1.28 1.28 1.27 3.25 3.22 3.21 0.35 0.49 10.4
2 43,481,638 59.3 1.03 1.03 1.00 2.05 2.05 2.09 0.43 1.05 11.8
3 17,698,965 24.2 1.15 1.16 1.13 1.77 1.77 1.86 0.58 1.56 7.0
Source: SRK, 2020
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 226
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
14.8.2 Dynamic Anisotropy
SRK concluded that within all domains there is the presence of multiple strike and dip directions which
could impact the search orientation and result in a bias could be introduced if a single search
orientation was selected per zone. To ensure the block model reflects the nature of the vein
mineralization as accurately as possible, SRK therefore utilized the wireframe interpretation to aid in
determining the search orientations used during the kriging equations on a block by block basis. This
has been done using the dynamic anisotropy function in Datamine™.
The dynamic search orientations have been generated from a series of planes (wireframes) within
DatamineTM, which are used to initially define the dip and dip direction of each planes triangles (used
to create the plane) on a 10 m resolution. These points are then estimated into the block model using
the “Estima” Process within DatamineTM, which is designed to recognize these criteria. In areas of
limited drilling or information SRK has defined a default orientation for the estimation process of dip
and dip direction, for example as shown for the MDZ high-grade wireframes in Figure 14-21.
Source: SRK, 2020
Figure 14-21: Example of Default Search Orientations Used Within the MDZ High-Grade Domain
N
100 m
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 227
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
14.8.3 Threshold Capping
The grade distributions within each of the defined domains can be described as positively skewed log-
normal distributions. When undertaking the capping analysis, SRK noted that high-grade values are
important to the deposit and that excessive capping will likely result in a reduction of metal that could
impact project economics. Counter to this point is that the use of higher capping could over-estimate
the metal for any given areas, which may be a concern especially within the vein domains, which are
more reliant on the channel sampling databases. To tackle this issue, SRK has introduced the use of
threshold capping (or sliding capping), which applies variable capping levels based on the distance
from the drilling. In simple terms, higher capping values are used in the first search volumes, and more
conservative capping values in the second and third volumes. A summary of the application of the
threshold capping strategy is shown in Table 14-17.
Table 14-17: Summary of Domains with Top Capping and Sliding Thresholds for Wider Search Volumes
Domain Capping Level Au (g/t) Capping Level Ag (g/t)
Vein Code Search 1 Search 2 & 3 Search 1 Search 2 & 3
VEINS (Group 1000) >9000 20 15 150 110
<9000 60 40 450 300
DISS (Group 2000) >9000 10 7 90 80
<9000 20 15 334 300
SPLAYS (Group 3000) 30 20 150 110
Porphyry
4001 9.0 No Change 205 No Change
4002 9.6 No Change 60 No Change
4003 5.0 No Change 35 No Change
4004 4.5 No Change 23 No Change
4005 9.0 No Change 27 No Change
4006 11.5 No Change 45 No Change
4007 9.0 No Change 50 No Change
5000 5.5 No Change 25 No Change
MDZ 5001 17.5 No Change 30 No Change
(Group 5000) 5002 40 No Change 50 No Change
Source: SRK, 2020
14.8.4 Final Parameters
The final kriging parameters selected for gold and silver are presented in Table 14-18. A discretization
grid of 3 by 3 by 3 m has been used within each parent block during the estimation within the Veins,
Disseminated and Splays domains (Group 1000 to 3000). A discretization grid of 4 by 5 by 4 m has
been used within each parent block during the estimation within the porphyry and MDZ domains
(Group 4000 to 5000). The discretization grid ensures that single blocks near the edge of each
estimation zone are assigned a grade that is characteristic of the modelled domain and not just those
values at the block midpoint.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 228
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Using the dynamic anisotropy to control the orientation of the searches and based on visual review
of the porphyry pockets, SRK has applied anisotropy to the search ranges within Group 4000. The
ability to vary the search ellipse accounts for the complex geology which could not be accounted for
in the variography for this domain. SRK considers this approach to best reflect the underlying
geological conditions.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 229
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 14-18: Summary of Estimation Search Parameters Used in Estimation
Group Group 1000 (Veins) Group 1000 (Disseminated) Group 3000 (Splays) Group 4000 (Porphyry) Group 5000 (MDZ)
Sub-Group 1000 1000 2000 2000 3000 3000 4000 4000 5000 5001 5002 5000-5002
SDESC Search
Volume (Au) Search
Volume (Ag) Search
Volume (Au) Search
Volume (Ag) Search
Volume (Au) Search
Volume (Ag) Search
Volume (Au) Search
Volume (Ag)
Search Volume Au
(LG)
Search Volume Au
(MG)
Search Volume Au
(HG)
Search Volume (Ag)
Rotation (Z) 0 0 0 0 0 0 15 15 120 120 120 120
Rotation (Dip) 0 0 0 0 0 0 -80 -80 -85 -85 -85 -85
X Range (m) 25 25 25 25 25 25 25 35 40 45 45 55
Y Range (m) 25 25 25 25 25 25 25 35 50 35 35 55
Z Range (m) 25 25 25 25 25 25 15 15 20 10 10 15
Minimum 4 4 4 4 4 4 4 4 5 5 5 5
Maximum 12 12 12 12 12 12 12 12 24 20 20 20
Dynamic Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes
Search Volume Factor
3 3 3 3 3 3 2 2 2 2.2 2.2 1.5
X Range (m) 75 75 75 75 75 75 50 70 80 99 99 82.5
Y Range (m) 75 75 75 75 75 75 50 70 100 77 77 82.5
Z Range (m) 75 75 75 75 75 75 30 30 40 22 22 22.5
Minimum 4 4 4 4 4 4 4 4 5 5 5 5
Maximum 12 12 12 12 12 12 12 8 24 20 20 20
Dynamic Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes No Yes
SVOLFAC3 6 6 6 6 6 6 4 4 3 3.3 3.3 3
X Range (m) 150 150 150 150 150 150 100 140 120 148.5 148.5 165
Y Range (m) 150 150 150 150 150 150 100 140 150 115.5 115.5 165
Z Range (m) 150 150 150 150 150 150 60 60 60 33 33 45
Minimum 1 1 1 1 1 1 1 1 3 3 3 3
Maximum 8 8 8 8 8 8 8 8 8 8 8 8
Dynamic Yes Yes Yes Yes Yes Yes Yes Yes No No No No
OCTMETH Yes No Yes No Yes No No No No No No No
MINOCT 1 1 1 1 1 1 2 2 2 2 2 2
MINPEROC 1 1 1 1 1 1 1 1 1 1 1 1
MAXPEROC 2 4 2 4 2 4 4 4 4 4 4 4
MAXKEY 2 2 2 2 2 2 3 3 4 4 4 4
SANGL1_F TRDIPDIR TRDIPDIR TRDIPDIR TRDIPDIR TRDIPDIR TRDIPDIR TRDIPDIR TRDIPDIR TRDIPDIR TRDIPDIR TRDIPDIR
SANGL2_F TRDIP TRDIP TRDIP TRDIP TRDIP TRDIP TRDIP TRDIP TRDIP TRDIP TRDIP
Estimation Method
OK OK OK OK ID2 ID2 OK OK OK OK OK OK
Source: SRK, 2020
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 230
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
14.9 Model Validation
SRK has undertaken a thorough validation of the resultant interpolated model in order to confirm the
estimation parameters, to check that the model represents the input data on both local and global
scales and to check that the estimate is not biased. SRK has undertaken this using a number of
different validation techniques:
• Visual inspection of block grades in comparison with drill hole data
• Inspection of block grades in plan and section and comparison with drillhole grades
• Statistical validation of declustered means versus block estimates
• Comparison of estimates using different estimation methods (NN, IDW, OK)
• Swath plots of the mean block and sample grades
The geology model, geostatistical analysis, variography, selection of resource estimation parameters,
and construction of the block model work were completed by SRK. The current drilling information is
sufficiently reliable to interpret with confidence the boundaries of the various veins, and the assaying
data is sufficiently reliable to support Mineral Resource estimation
14.9.1 Visual Comparison
Visual validation provides a local validation of the interpolated block model on a local block scale,
using visual assessments and validation plots of sample grades versus estimated block grades. A
thorough visual inspection of cross-sections, long-sections and bench/level plans, comparing the
sample grades with the block grades has been undertaken, which demonstrates good comparison
between local block estimates and nearby samples, without excessive smoothing in the block model.
Exploration NW
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 231
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Santa Ines
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 232
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Mezillos
Source: SRK, 2020
Figure 14-22: Visual Validation of Selected Veins at Marmato
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 233
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Disseminated Exploration NW
Disseminated Santa Ines Source: SRK, 2020
Figure 14-23: Visual Validation of Selected Disseminated Veins at Marmato
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 234
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SRK, 2020
Figure 14-24: Section and Level Plan Example of Visual Validation of MDZ (Group 1000)
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 235
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
14.9.2 Comparative Statistics
SRK has completed a statistical validation of the block estimates (NN, OK and ID2) versus the mean
of the composite samples per zone. In general, the results indicate a reasonable comparison
(Table 14-19) between the sample mean grades (declustered) and the block estimates.
SRK notes that the comparison between the mean grades and the raw samples often exceeds the
desired levels of error, but this is often a function of the clustering within the dataset from either channel
sampling, or the fan drilling. SRK has therefore focused on using a comparison to the declustered
mean grades, which have been determined within Snowden Supervisor, by testing multiple
declustering block sizes ranging between 0 to 50 m and selecting points where the mean stabilizes.
In the case of the higher grade domains such as the veins or the high-grades MDZ, this typically
represents a reduction in the average grades, while the lower grade domains have typically been under
sampled and therefore there is a slight increase in the average grades within these zones.
For the comparison, SRK has compared the grouped statistics for the veins, splays, and porphyry
material, but has broken out the MDZ into the three main sub-domains. The zones show satisfactory
correlations between the composite and block estimates, with the highest errors noted within the low-
grade MDZ domain, but a comparison between the OK vs NN returned acceptable results. This is
minor domain in terms of material above cut-off and therefore is not considered to be a material issue.
SRK notes the comparison of the NN and OK return good correlations, which adds support to the
estimates.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 236
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 14-19: Summary of Statistical Validation of Raw, Declustered, OK, ID2 and NN Block Estimates
Group = 1000 (Veins)
Element Statistic Sample
Data Declustered Sample Data
Block Data 1
OK
OK Vs Sample
% Diff
OK Vs Declustered
%Diff
Block Data 2
ID2
ID2 Vs Sample
% Diff
ID2 Vs Declustered
% Diff
Block Data 3
NN
NN Vs Sample
%Diff
NN Vs Declustered
% Diff
OK vs
NN
AU
Points 22018 22018
Mean 7.01 3.72 3.47 -50% -7% 3.38 -52% -9% 3.25 -54% -13% 6.9%
Std Dev 9.58 6.54 3.27 3.62 5.45
Variance 91.76 42.83 10.66 13.11 29.65
CV 1.37 1.76 0.94 1.07 1.68
Maximum 60.00 60.00 48.48 48.29 60.00
75% 8.40 8.40 4.77 4.58 3.83
50% 3.80 3.80 2.49 2.30 1.54
25% 1.60 1.60 1.40 1.21 0.55
AG
Points 22018 22018
Mean 32 22 19 -42% -13% 19 -43% -15% 18 -45% -18% 5.3%
Std Dev 34.0 33.2 17.0 19.7 27.9
Variance 1155 1103 288 390 780
CV 1.05 1.53 0.90 1.07 1.56
Maximum 450.0 450.0 226.7 288.6 450.0
75% 42.6 42.6 25.5 24.9 22.4
50% 23.6 23.6 14.2 13.0 8.8
25% 10.8 10.8 7.8 6.6 3.0
Group = 2000 (Disseminated)
Element Statistic Sample
Data Declustered Sample Data
Block Data 1 OK
OK Vs Sample
% Diff
OK Vs Declustered
% Diff
Block Data 2 ID2
ID2 Vs Sample
% Diff
ID2 Vs Declustered
% Diff
Block Data 3 NN
NN Vs Sample
% Diff
NN Vs Declustered
% Diff
OK vs
NN
AU
Points 18402 18402
Mean 2.02 1.84 1.96 -3% 6% 1.95 -3% 6% 1.95 -3% 6% 0.1%
Std Dev 3.05 2.81 1.43 1.59 2.87
Variance 9.31 7.88 2.06 2.53 8.25
CV 1.51 1.52 0.73 0.82 1.47
Maximum 20.00 20.00 12.48 14.82 20.00
75% 2.18 2.18 2.61 2.56 2.15
50% 1.00 1.00 1.62 1.54 1.03
25% 0.40 0.40 0.94 0.88 0.40
AG
Points 18402 18402
Mean 19 17 18 -7% 3% 18 -7% 3% 18 -7% 2% 0.6%
Std Dev 21.3 19.3 13.7 14.6 20.1
Variance 452 374 188 214 406
CV 1.11 1.12 0.77 0.82 1.14
Maximum 334.0 334.0 125.7 149.1 334.0
75% 24.1 24.1 21.7 21.4 21.5
50% 12.6 12.6 14.0 13.7 12.0
25% 6.0 6.0 9.2 8.8 5.6
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 237
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Group = 3000 (Splays)
Element Statistic Sample
Data
Declustered Sample
Data
Block Data 1
OK
OK Vs Sample
% Diff
OK Vs Declustered
% Diff
Block Data 2
ID2
ID2 Vs Sample
% Diff
ID2 Vs Declustered
% Diff
Block Data 3
NN
NN Vs Sample
% Diff
NN Vs Declustered
% Diff
OK vs
NN
AU
Points 2980 2980
Mean 4.33 3.77 3.47 -20% -8% 3.44 -20% -9% 3.33 -23% -12% 4.1%
Std Dev 5.78 5.63 3.04 3.27 4.77
Variance 33.38 31.72 9.27 10.68 22.78
CV 1.34 1.49 0.88 0.95 1.43
Maximum 30.00 30.00 27.05 27.87 30.00
75% 5.20 5.20 5.11 5.06 4.68
50% 2.34 2.34 2.90 2.76 1.79
25% 0.91 0.91 1.54 1.34 0.45
AG
Points 2980 2980 124391 124391 124391
Mean 22 18 18 -18% 2% 18 -18% 2% 18 -19% 1% 0.8%
Std Dev 23.8 22.2 16.0 16.8 21.9
Variance 566 492 256 282 479
CV 1.06 1.23 0.88 0.92 1.21
Maximum 150.0 150.0 146.4 146.8 150.0
75% 28.3 28.3 24.8 24.8 25.6
50% 15.6 15.6 13.7 13.6 10.8
25% 7.9 7.9 7.2 6.7 2.5
Group = 4000 (Porphyry Pockets)
Element Statistic Sample
Data Declustered Sample Data
Block Data1
OK
OK Vs Sample
% Diff
OK Vs Declustered
% Diff
Block Data 2 ID2
ID2 Vs Sample
% Diff
ID2 Vs Declustered
% Diff
Block Data 3 NN
NN Vs Sample
% Diff
NN Vs Declustere
d % Diff
OK vs
NN
AU
Points 7738 7738
Mean 1.39 1.40 1.47 6% 5% 1.47 5% 5% 1.43 3% 3% 2.4%
Std Dev 1.50 1.53 0.71 0.82 1.52
Variance 2.26 2.33 0.51 0.67 2.31
CV 1.08 1.09 0.49 0.56 1.06
Maximum 11.50 11.50 7.05 7.80 11.50
75% 1.69 1.67 1.81 1.81 1.73
50% 0.91 0.91 1.31 1.27 0.96
25% 0.54 0.56 0.97 0.91 0.58
AG
Points 7738 7738
Mean 1 1 1 6% 5% 1 5% 5% 1 3% 3% 2.4%
Std Dev 1.5 1.5 0.7 0.8 1.5
Variance 2 2 1 1 2
CV 1.08 1.09 0.49 0.56 1.06
Maximum 11.5 11.5 7.0 7.8 11.5
75% 1.7 1.7 1.8 1.8 1.7
50% 0.9 0.9 1.3 1.3 1.0
25% 0.5 0.6 1.0 0.9 0.6
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 238
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Group = 5000 (INDZONE = 0)
Element Statistic Sample
Data
Declustered Sample
Data
Block Data 1
OK
OK Vs Sample
% Diff
OK Vs Declustered
% Diff
Block Data 2
ID2
ID2 Vs Sample
% Diff
ID2 Vs Declustered
% Diff
Block Data 3
NN
NN Vs Sample
% Diff
NN Vs Declustered
% Diff OK vs NN
AU
Points 5518 5518
Mean 0.43 0.44 0.48 12% 10% 0.48 13% 11% 0.53 23% 21% -9.0%
Std Dev 0.55 0.56 0.25 0.27 0.65
Variance 0.30 0.31 0.06 0.07 0.42
CV 1.28 1.27 0.52 0.56 1.22
Maximum 5.50 5.50 2.60 3.24 5.50
75% 0.52 0.53 0.61 0.61 0.60
50% 0.28 0.29 0.43 0.42 0.31
25% 0.13 0.13 0.30 0.30 0.16
AG
Points 5518 5518
Mean 2 2 2 -32% -14% 2 -32% -14% 2 -30% -12% -2.1%
Std Dev 3.3 2.5 1.0 1.0 1.8
Variance 11 6 1 1 3
CV 1.47 1.41 0.67 0.69 1.15
Maximum 25.0 25.0 21.4 23.5 25.0
75% 2.2 1.9 1.8 1.8 1.8
50% 1.3 1.2 1.3 1.3 1.1
25% 0.9 0.7 0.9 0.9 0.7
Group = 5000 (INDZONE = 1)
Element Statistic Sample
Data
Declustered Sample
Data
Block Data 1
OK
OK Vs Sample
% Diff
OK Vs Declustered
% Diff
Block Data 2
ID2
ID2 Vs Sample
% Diff
ID2 Vs Declustered
% Diff
Block Data 3
NN
NN Vs Sample
% Diff
NN Vs Declustered
% Diff OK vs NN
AU
Points 5113 5113
Mean 1.32 1.26 1.27 -4% 1% 1.29 -2% 2% 1.24 -6% -2% 2.4%
Std Dev 1.33 1.23 0.47 0.53 1.24
Variance 1.76 1.52 0.22 0.28 1.55
CV 1.00 0.97 0.37 0.41 1.00
Maximum 17.50 17.50 5.03 6.35 17.50
75% 1.57 1.51 1.49 1.52 1.47
50% 0.97 0.95 1.18 1.18 0.88
25% 0.59 0.57 0.96 0.93 0.57
AG
Points 5113 5113
Mean 3 3 2 -39% -21% 2 -39% -21% 2 -38% -20% -1.1%
Std Dev 4.5 3.3 1.5 1.6 2.6
Variance 20 11 2 3 7
CV 1.31 1.25 0.74 0.77 1.24
Maximum 30.0 30.0 25.1 26.2 30.0
75% 3.4 2.7 2.5 2.5 2.3
50% 1.8 1.6 1.7 1.7 1.4
25% 1.2 1.1 1.2 1.2 1.0
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Page 239
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Group = 5000 (INDZONE = 2)
Element Statistic Sample
Data Declustered Sample Data
Block Data 1
OK
OK Vs Sample
% Diff
OK Vs Declustered
% Diff
Block Data 2 ID2
ID2 Vs Sample
% Diff
ID2 Vs Declustered
% Diff
Block Data 3 NN
NN Vs Sample
% Diff
NN Vs Declustered
% Diff
OK vs
NN
AU
Points 3635 3635
Mean 3.35 3.27 3.39 1% 4% 3.40 1% 4% 3.14 -6% -4% 7.8%
Std Dev 3.61 3.60 1.98 2.13 3.54
Variance 13.03 12.93 3.94 4.54 12.50
CV 1.08 1.10 0.59 0.63 1.13
Maximum 40.00 40.00 31.22 31.72 40.00
75% 4.02 3.87 3.70 3.75 3.63
50% 2.37 2.31 2.89 2.83 2.21
25% 1.34 1.33 2.31 2.23 1.24
AG
Points 3635 3635
Mean 5 4 4 -31% -10% 4 -31% -11% 4 -32% -12% 1.8%
Std Dev 6.9 5.4 2.7 2.9 4.8
Variance 48 29 7 9 23
CV 1.28 1.29 0.73 0.79 1.29
Maximum 50.0 50.0 27.9 31.4 50.0
75% 6.1 4.5 4.8 4.8 4.0
50% 2.9 2.4 2.9 2.7 2.2
25% 1.6 1.4 1.9 1.8 1.3
Source: SRK, 2020
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 240
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
14.9.3 Swath Plots
As part of the validation process, the input composite samples were compared to the block model
grades within a series of coordinates. The results of this were then displayed on graphs to check for
visual discrepancies between grades. Figure 14-25 through Figure 14-31 show the results for the gold
grades for the Marmato vein domain and MDZ high-grade domains respectively, based on all three
principal directions. The graph shows the block model grades (black line), ID2 (grey), NN (yellow) and
the declustered composite grades (blue line).
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 241
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SRK, 2020
Figure 14-25: Swath Analysis Group 1000 Au (g/t)
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 242
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SRK, 2020
Figure 14-26:Swath Analysis Group 2000 Au (g/t)
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 243
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SRK, 2020
Figure 14-27: Swath Analysis Group 3000 Au (g/t)
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 244
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SRK, 2020
Figure 14-28: Swath Analysis Group 4000 Au (g/t)
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 245
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SRK, 2020
Figure 14-29: Swath Analysis Group 5000 – INDZONE=0 (LG) Au (g/t)
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 246
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SRK, 2020
Figure 14-30: Swath Analysis Group 5000 – INDZONE=1 (MG) Au (g/t)
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 247
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SRK, 2020
Figure 14-31: Swath Analysis Group 5000 – INDZONE=2 (HG) Au (g/t)
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 248
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
14.10 Resource Classification
Block model quantities and grade estimates for the Marmato Project were classified according to the
CIM Definition Standards for Mineral Resources and Mineral Reserves (May 2014).
Mineral Resource classification is typically a subjective concept. Industry best practices suggest that
classification should consider the confidence in the geological continuity of the mineralized structures,
the quality and quantity of exploration data supporting the estimates, and the geostatistical confidence
in the tonnage and grade estimates. Appropriate classification criteria should aim to integrate both
concepts to delineate regular areas at similar resource classification.
Data quality, drillhole spacing and the interpreted continuity of grades controlled by the veins have
allowed SRK to classify portions of the veins in the Measured, Indicated and Inferred Mineral Resource
categories.
SRK’s classification system is consistent with those used in the 2019 PEA.
14.10.1 Measure Mineral Resources
Measured Resources are limited to vein material within the current levels being mined by Company.
These areas are considered to have strong geological knowledge as they have been traced both down-
dip and along strike via mapping, plus underground channel samplings provide sufficient data
populations to define internal grade variability.
• Vein and Diss material within the current levels being mined
• Blocks estimated within the first search volume of 25 m which required a minimum of 4
composites and maximum of 12
• Splays were not categorized as measured
14.10.2 Indicated Mineral Resources
SRK has delineated Indicated Mineral Resources using two methods split by the material types:
Veins/Disseminated/Splays
Primarily between Level 16 to 21 currently in operation. Indicated Mineral Resources have been given
at the following approximate data spacing, as function of the confidence in the grade estimates and
modelled variogram ranges. SRK has expanded the limits of the Indicated to also cover areas within
the licensed portion of Echandia where:
• Spacing of 50 m by 50 m (XY) existed from the nearest drillhole
• Multiple holes were enabled to be used during the estimation process
• Support from both diamond drilling and channel sampling was present
MDZ
• Based primarily on 2018 and 2019 drilling
• 50 x 50 m (XY) drillhole Spacing (defined by a distance buffer of 25 m from drilling of UG
levels)
• Enabled multiple holes to be used during the estimation process
• Search Volume less than 2 (i.e. volumes 1 and 2)
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 249
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
• Additional caution has been paid when classifying the dip extensions on the series of holes
drilled to the northeast as limited information is known up and down dip from the current drilling
14.10.3 Inferred Mineral Resources
Inferred Mineral Resources have been limited to within areas of reasonable grade estimate quality and
sufficient geological confidence and are extended no further than 150 m from peripheral drilling on the
basis of modelled variogram ranges.
Notes on Downgrade of Porphyry Pockets
During the site inspection SRK noted and discussed with the mine geologists that some mining has
been attempted within the porphyry pockets. SRK considers this to have uncertainty as no detailed
survey of mining volumes is available. Based on the level of uncertainty SRK has down-graded areas
identified as having potential mining to Inferred.
14.10.4 Final Classification
Mathematical criteria as defined has then been digitized on 50 m sections (across Strike), to smooth
the process with the final wireframe based on interpretation of polylines in Leapfrog to smooth changes
in interpretation between sections. A summary of the classification at Marmato is shown in Figure
14-32 and Figure 14-33.
Source: SRK, 2020
Figure 14-32: Final Classification for the Marmato Project (Looking Northwest Bearing 305)
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 250
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SRK, 2020
Figure 14-33: Final Classification for License #014-89m Marmato Project (Looking Northwest Bearing 305)
14.11 Depletion
To define the Mineral Resource SRK has created a block model to represent the depletion for the
veins. In order to complete this task SRK has used a combination of AutoCAD™ polylines provided by
CGM and generated Vulcan™ (.00t) files by projecting the strings in perpendicular to the strike. These
wireframes have subsequently been used to copy out the assigned vein. The process is manual and
labor intensive and requires each vein to be individually assessed.
This process may result in some errors of over or under depletion at the edges but given the size of
the deposits is not considered to be material. Once the block model has been established the model
has been combined with the final geological model to code all the blocks for depletion.
SRK and CGM have worked towards generating a 3D digital layout of the mine which has the depletion
assigned to each of the main structures, further work will be required to further validate the models
using underground surveys to improve confidence in the models, but the addition of approximately 18
months on additional depletion from the PEA model has increased confidence in the estimated
depletions for the PFS.
14.12 Mineral Resource Statement
Canadian Institute of Mining, Metallurgy and Petroleum’s (CIM) Definition Standards for Mineral
Resources and Mineral Reserves (May, 2014) defines a Mineral Resource as:
“(A) concentration or occurrence of diamonds, natural solid inorganic material, or natural solid
fossilized organic material including base and precious metals, coal, and industrial minerals in or on
the Earth’s crust in such form and quantity and of such a grade or quality that it has reasonable
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 251
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
prospects for economic extraction. The location, quantity, grade, geological characteristics and
continuity of a Mineral Resource are known, estimated or interpreted from specific geological evidence
and knowledge”.
The “reasonable prospects for eventual economic extraction” requirement generally implies that the
quantity and grade estimates meet certain economic thresholds and that the Mineral Resources are
reported at an appropriate CoG, taking into account extraction scenarios and processing recoveries.
In order to meet this requirement, SRK considers that portions of the vein system are amenable for
underground mining.
To determine the potential for economic extraction, SRK used the following key assumptions for the
costing but notes that the deposit has variable mining costs depending on the mining types resulting
in a range of CoGs (Table 14-20). A metallurgical recovery of 95% Au has been assumed for the MDZ
and 90% for the veins and porphyry material based on the current performance of the operating plant.
Table 14-20: Summary of CoG Assumptions at Marmato Based on Assumed Costs (Averaged for All Mining Styles)
Units Vein Mining
Averaged CoG Deeps Option (Longhole)
Averaged CoG
Assumptions
Gold Price US$/ounce (oz) $1,500 $1,500
Gold Price US$/gram (g) $48.23 $48.23
Au Recovery % 90% 95%
Operating Costs
Mining US$/tonne (t) mined $49.45 $35.00
Processing US$/t ore $13.63 $17.00
Royalties US$/t ore $8.96 $6.80
General and Administrative (G&A) and Other
US$/t ore $12.24 $3.00
Other US$/t ore $0.00 $0.00
Subtotal US$/t $84.28 $61.75
CoG - Head Grade grams per tonne (g/t) 1.9 1.3
Source: SRK, 2020
SRK has defined the proportions of Mineral Resource to have potential for economic extraction for the
Mineral Resource based on two separate CoGs, relating to the different mining methods involved. The
initial cut-off is based on the mining of the veins using the current mining processes and assumed
costs, with a second method (longhole) defined for mining the MDZ and potentially areas of wider
porphyry mineralization in the upper levels.
SRK has reported the tonnage and grades associated with current mine and the MDZ project, which
are the assets owned by CGM. As such, the Mineral Resource includes all material within the #014-
89m license and a sub-portion of the #RPP_357 (Echandia) below an elevation of 1,300 m, which can
be accessed from the existing operation through an agreement with Gran Colombia. SRK has also
included the proportion of Mineral Resources currently under application (Application #KIU-11401)
within the Mineral Resources, but these have been excluded from the Mineral Reserves as the timing
on granting this license remained uncertain at the date of this report (however, SRK understands that
the license was recently confirmed as approved by the Government so will therefore be included in
future technical studies).
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 252
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
The proposed mining plan is predicated on splitting the above Mineral Resources into three styles of
mineralization within three distinct areas. These areas are referred to as the UZ (existing mine levels
16 to 21), the Transition Zone (which includes mining of MDZ material to an elevation of 950 m), and
the MDZ project (which includes all material below the 950 m).
The three styles of mineralization are based on the key geological types defined in the Mineral
Resources of veins, porphyry, and MDZ. Therefore, the estimation domains for the Mineral Resource
Statement have been grouped into veins, porphyry and MDZ mineralization. The veins account for the
veins, halos, and splay material and have used a 1.9 g/t Au cut-off; the porphyry material has also
used a cut-off of 1.9 g/t Au, as the potential mining method will require further investigation; the MDZ
material has used a lower cut-off of 1.3 g/t Au to account for the larger bulk mining methods involved.
SRK highlights to the reader that all Mineral Resources within #CHG_081 (yellow) and upper areas of
*RPP_357 (above 1,300 m) as highlighted in Figure 14-34 in light blue have not been reported and
are excluded from the Mineral Resource statement as they were not transferred to CGM and therefore
are excluded from the Mineral Resources. Any Mineral Resources that may occur within these two
areas are currently held by Gran Colombia.
Source: SRK, 2020
Figure 14-34: Cross-Section Showing License Splits at Marmato
Table 14-21 shows the Mineral Resource Statement for the project, with an effective date of March
17, 2020.
Licence #014-89m
Licence #CHG-081 (above 1300)
RPP #357 -(above 1300)
RPP #357 -(below 1300)
Licence #CHG-081 (below 1300)
Area under applicationNo # KIU-11401Note: Included in Mineral Resources but excluded from Mineral Reserves
Upper Mine(above 950)
MDZ Projectbelow 950)
Transition Zone MDZ(above 950)
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 253
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 14-21: Caldas Mineral Resource(1) Statement with Effective Date of March 17, 2020
Caldas Marmato Project - Effective Date March 17, 2020, Basis for MRE and PFS (Caldas including RPP less than 1,300)(1)
Category Quantity (million tonnes [Mt]) Grade (g/t) Metal (kozs)
Au Ag Au Ag
Upper Mine (2)
Measured 2.1 5.65 27.0 387 1,853
Veins (5) 2.1 5.6 27.0 387 1,853
Porphyry (5) 0.0 0.0 0.0 0 0
Indicated 9.2 4.45 18.7 1,320 5,545
Veins 7.2 5.0 21.1 1,156 4,862
Porphyry 2.1 2.5 10.3 165 682
Measured and Indicated 11.4 4.67 20.2 1,707 7,397
Veins 9.3 5.2 22.4 1,543 6,715
Porphyry 2.1 2.5 10.3 165 682
Inferred 4.5 3.70 15.5 532 2,224
Veins 2.7 4.4 17.9 386 1,574
Porphyry 1.7 2.6 11.7 145 650
Transition Zone (3) (6)
Measured 0.0 0.0 0.0 0 0
Indicated 3.4 2.68 7.2 294 785
Measured and Indicated 3.4 2.68 7.2 294 785
Inferred 0.0 1.95 3.7 2 3
MDZ (4) (6)
Measured 0.0 0.0 0.0 0 0
Indicated 24.7 2.63 3.6 2,085 2,870
Measured and Indicated 24.7 2.63 3.6 2,085 2,870
Inferred 21.9 2.32 2.1 1,639 1,506
Combined
Measured 2.1 5.6 27.0 387 1,853
Indicated 37.3 3.1 7.7 3,699 9,200
Measured and Indicated 39.4 3.2 8.7 4,086 11,053
Inferred 26.4 2.6 4.4 2,172 3,733 (1) Mineral Resources are reported inclusive of the Mineral Reserve. Mineral resources are not mineral reserves and do not have demonstrated economic viability. All figures are rounded to reflect the relative accuracy of the estimate. All composites have been capped where appropriate. The Mineral Resources were estimated by Benjamin Parsons, MSc, MAusIMM #222568 of SRK, a Qualified Person pursuant to NI 43-101. (2) Upper Mine is defined as the current operating mines from levels 16-21 using existing mining methodology (cut and fill). (3) “Transition Zone” is defined as mining of MDZ above an elevation of 950 access from the current operations using a modified longhole stoping method. (4) MDZ is defined as mining of MDZ below an elevation of 950 using longhole open stope mining methods. (5) Porphyry and vein mineral resources are reported at a cut-off grade (“CoG”) of 1.9 g/t. CoGs are based on a price of US$1,500/oz Au and gold recoveries of 90% for underground resources without considering revenues from other metals. (6) MDZ mineral resources are reported at a CoG of 1.3 g/t. CoGs are based on a price of US$1,500.oz Au and gold recoveries of 95% for underground resources without considering revenues from other metals within a limiting pitshell.
14.13 Comparison to the Previous Estimate
The 2020 Mineral Resource represents a number of changes in the defined Mineral Resource
compared to the 2019 PEA Mineral Resources, due to the following key factors:
• Infill drilling within the MDZ areas has increased the confidence in the estimates significantly
from the Inferred to Indicated category.
• Minor reduction in the vein domains as a result of additional depletion accounted for between
the PEA and PFS models, plus changes in the geological interpretation of veins and
disseminated material.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 254
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
SRK highlights that the current MDZ Mineralization represents a notable change in the style of
mineralization and considerations for mining methods at the Marmato Project and has maintained the
use of a high-grade core to the mineralization at depth.
The main changes in the Mineral Resource Statement since the previous estimate can be defined on
the combined Mineral Resource as follows:
• Increase in the Indicated MDZ material from 6.4 Mt at 2.6 g/t Au, for 537 koz, to 28.1 Mt at 2.6
g/t Au, for 2,379 koz, which is an increase of 1,842 koz within the MDZ. This is reflected in a
reduction in the Inferred from 41.2 Mt at 2.1 g/t for 2,812 koz to 22.0 Mt at 2.3 g/t for 1,640
koz, which is a reduction of 1,172 koz.
• Increase in the proportion of Measured and Indicated material within the vein domain from
9.2 Mt at an average grade of 4.6 g/t to 9.3 Mt at an average grade of 5.2 g/t Au, which is an
increase of 180 Koz or 13.2%.
• Reduction in the proportion of Inferred material within the veins from 3.3 Mt at 4.4 g/t Au for
466 koz, to 2.7 Mt at 4.4 g/t Au for 386 koz, which represents a difference of 80 koz.
• Minor increase in proportion for Indicated of porphyry (Pockets) material of 25 koz.
• Increase in the Inferred portion of the porphyry material from 0.3 Mt at 3.1 g/t Au for 34 koz,
to 1.7 Mt at 2.6 g/t Au for 145 koz.
14.14 Mineral Resource Sensitivity
The mineral resource given above is sensitive to the selection of the reporting CoG. To illustrate the
sensitivity the block model quantities and grade estimates for the Marmato Project were classified
according to the CIM Definition Standards for Mineral Resources and Reserves (CIM, 2014).
The reader is cautioned that the figures presented in the tables should not be misconstrued with a
Mineral Resource Statement. Figure 14-35 and Figure 14-36 are only presented to show the sensitivity
of the block model estimates to the selection of cut-off grade. The following tables (Table 14-22 to
Table 14-27) have been split by the mineralization style and classification (Measured and Indicated
have been combined for ease of reporting).
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 255
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 14-22: Grade Tonnage Curve Measured and Indicated - Vein Domains (Group 1000 to 3000)
Cut-Off (Au g/t) Tonnes (kt) Au (g/t) Ag (g/t) Au (koz) Ag (koz)
0.00 14,688 3.72 18.18 1,758 8,584 0.50 14,023 3.89 18.75 1,752 8,453 1.00 12,516 4.26 19.91 1,715 8,011 1.20 11,821 4.45 20.44 1,690 7,769 1.30 11,449 4.55 20.73 1,675 7,631 1.50 10,727 4.76 21.32 1,643 7,355 1.70 10,004 4.99 21.93 1,605 7,054 1.80 9,651 5.11 22.25 1,586 6,904 1.90 9,312 5.23 22.55 1,565 6,752 2.00 8,978 5.35 22.91 1,545 6,612 2.20 8,292 5.62 23.63 1,498 6,299 2.50 7,460 5.99 24.48 1,436 5,871 2.70 7,460 5.99 24.48 1,436 5,871 3.00 6,359 6.55 25.74 1,339 5,262 3.50 5,424 7.12 27.04 1,241 4,716 4.00 4,617 7.71 28.48 1,144 4,228 4.50 3,967 8.27 29.91 1,055 3,815 5.00 3,418 8.84 31.24 972 3,433
Source: SRK, 2020
Table 14-23: Grade Tonnage Curve Measured and Indicated - Porphyry Domain (Group 4000)
Cut-Off (Au g/t) Tonnes (kt) Au (g/t) Ag (g/t) Au (koz) Ag (koz)
0.00 9,059 1.47 7.16 428 2,086
0.50 8,799 1.50 7.33 425 2,074
1.00 6,632 1.73 8.14 369 1,735
1.20 5,218 1.90 8.70 319 1,460
1.30 4,685 1.98 8.93 298 1,345
1.50 3,691 2.13 9.33 253 1,107
1.70 2,747 2.32 9.82 205 868
1.80 2,389 2.40 10.14 185 779
1.90 2,052 2.50 10.35 165 682
2.00 1,731 2.60 10.69 145 595
2.20 1,207 2.81 11.28 109 438
2.50 677 3.19 12.55 69 273
2.70 677 3.19 12.55 69 273
3.00 312 3.75 14.68 38 147
3.50 161 4.24 14.74 22 76
4.00 103 4.55 15.11 15 50
4.50 46 5.02 17.51 7 26
5.00 16 5.54 13.26 3 7
Source: SRK, 2020
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 256
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 14-24: Grade Tonnage Curve Measured and Indicated - MDZ Domain (Group 5000)
Cut-Off (Au g/t) Tonnes (kt) Au (g/t) Ag (g/t) Au (koz) Ag (koz)
0.00 86,787 1.29 2.79 3,606 7,785
0.50 60,574 1.71 3.17 3,329 6,182
1.00 41,281 2.15 3.60 2,860 4,779
1.20 31,695 2.47 3.90 2,522 3,974
1.30 28,050 2.63 4.04 2,375 3,647
1.50 23,049 2.90 4.29 2,152 3,178
1.70 20,181 3.09 4.44 2,005 2,882
1.80 19,016 3.17 4.51 1,940 2,758
1.90 18,067 3.24 4.57 1,883 2,655
2.00 17,127 3.31 4.63 1,824 2,550
2.20 15,419 3.45 4.75 1,709 2,353
2.50 12,888 3.66 4.95 1,518 2,051
2.70 12,888 3.66 4.95 1,518 2,051
3.00 8,583 4.12 5.36 1,138 1,478
3.50 5,416 4.64 5.71 809 994
4.00 3,321 5.22 6.05 557 646
4.50 2,048 5.84 6.47 384 426
5.00 1,316 6.45 6.74 273 285
Source: SRK, 2020
Table 14-25: Grade Tonnage Curve Inferred - Vein Domains (Group 1000 - 3000)
Cut-Off (Au g/t) Tonnes (kt) Au (g/t) Ag (g/t) Au (koz) Ag (koz)
0.00 6,664 2.37 12.51 508 2,681
0.50 5,702 2.72 13.89 498 2,546
1.00 4,652 3.17 15.12 473 2,262
1.20 4,136 3.42 15.74 455 2,093
1.30 3,928 3.54 16.01 447 2,022
1.50 3,485 3.81 16.62 427 1,863
1.70 3,115 4.07 17.15 408 1,718
1.80 2,926 4.22 17.51 397 1,647
1.90 2,741 4.38 17.87 386 1,574
2.00 2,604 4.51 17.99 378 1,506
2.20 2,341 4.78 18.62 360 1,402
2.50 2,020 5.17 19.43 336 1,262
2.70 2,020 5.17 19.43 336 1,262
3.00 1,612 5.78 20.44 300 1,060
3.50 1,319 6.35 21.42 269 909
4.00 1,067 6.97 22.41 239 769
4.50 889 7.53 23.33 215 667
5.00 722 8.16 22.52 189 523
Source: SRK, 2020
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 257
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 14-26: Grade Tonnage Curve Inferred - Porphyry Domain (Group 4000)
Cut-Off (Au g/t) Tonnes (kt) Au (g/t) Ag (g/t) Au (koz) Ag (koz)
0.00 7,626 1.50 8.11 368 1,988
0.50 7,541 1.51 8.17 367 1,981
1.00 5,556 1.77 9.21 316 1,644
1.20 4,449 1.93 9.86 276 1,410
1.30 3,883 2.03 10.26 254 1,281
1.50 2,944 2.24 10.79 212 1,022
1.70 2,293 2.42 11.43 178 842
1.80 1,984 2.52 11.61 161 741
1.90 1,725 2.62 11.71 145 650
2.00 1,516 2.71 11.82 132 576
2.20 1,155 2.91 11.87 108 441
2.50 707 3.27 12.59 74 286
2.70 707 3.27 12.59 74 286
3.00 335 3.91 11.93 42 128
3.50 188 4.47 11.75 27 71
4.00 119 4.93 10.85 19 41
4.50 85 5.24 7.56 14 21
5.00 54 5.60 6.06 10 11
Source: SRK, 2020
Table 14-27: Grade Tonnage Curve Inferred - MDZ Domain (Group 5000)
Cut-Off (Au g/t) Tonnes (kt) Au (g/t) Ag (g/t) Au (koz) Ag (koz)
0.00 108,152 0.94 1.69 3,268 5,876
0.50 67,414 1.30 1.83 2,824 3,965
1.00 32,941 1.93 2.02 2,044 2,139
1.20 25,465 2.17 2.09 1,781 1,709
1.30 21,964 2.32 2.14 1,640 1,509
1.50 16,952 2.60 2.22 1,415 1,208
1.70 13,286 2.87 2.31 1,227 988
1.80 12,052 2.99 2.35 1,158 911
1.90 10,620 3.14 2.42 1,072 827
2.00 9,784 3.24 2.44 1,020 766
2.20 8,069 3.49 2.45 904 634
2.50 6,171 3.83 2.42 761 480
2.70 6,171 3.83 2.42 761 480
3.00 3,630 4.59 2.44 536 285
3.50 2,035 5.67 2.38 371 156
4.00 1,468 6.43 2.23 303 105
4.50 1,071 7.23 2.23 249 77
5.00 812 8.02 2.20 209 57
Source: SRK, 2020
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 258
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SRK, 2019
Figure 14-35: Grade Tonnage Curves Showing Sensitivity to Changes in Cut-Off for Measured and Indicated Mineralized Material
0.00
1.00
2.00
3.00
4.00
5.00
6.00
7.00
8.00
9.00
10.00
0
2,000
4,000
6,000
8,000
10,000
12,000
14,000
16,000
0.00 0.50 1.00 1.50 2.00 2.50 3.00 3.50 4.00 4.50 5.00
Au
(g/
t)
TON
NES
(kt
)
Au Cut-Off (g/t)
Grade Tonnage Curve (Veins - M&I)
0.00
1.00
2.00
3.00
4.00
5.00
6.00
0
1,000
2,000
3,000
4,000
5,000
6,000
7,000
8,000
9,000
10,000
0.00 0.50 1.00 1.50 2.00 2.50 3.00 3.50 4.00 4.50 5.00
Gra
de
Au
(g/
t)
TON
NES
(kt
)
AU Cut-Off (g/t)
Grade Tonnage Curve (Porphyry M&I)
0.00
1.00
2.00
3.00
4.00
5.00
6.00
7.00
0
10,000
20,000
30,000
40,000
50,000
60,000
70,000
80,000
90,000
100,000
0.00 0.50 1.00 1.50 2.00 2.50 3.00 3.50 4.00 4.50 5.00
Gra
de
Au
(g/
t)
TON
NES
(kt
)
Au Cut-Off (g/t)
Grade Tonnage Curve (MDZ M&I)
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 259
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SRK, 2019
Figure 14-36: Grade Tonnage Curves Showing Sensitivity to Changes in Cut-Off for Inferred Mineralized Material
0.00
1.00
2.00
3.00
4.00
5.00
6.00
7.00
8.00
9.00
0
1,000
2,000
3,000
4,000
5,000
6,000
7,000
0.00 0.50 1.00 1.50 2.00 2.50 3.00 3.50 4.00 4.50 5.00
Au
(g/
t)
TON
NES
(kt
)
AU Cut-Off (g/t)
Grade Tonnage Curve (Veins - Inferred)
0.00
1.00
2.00
3.00
4.00
5.00
6.00
0
1,000
2,000
3,000
4,000
5,000
6,000
7,000
8,000
9,000
0.00 0.50 1.00 1.50 2.00 2.50 3.00 3.50 4.00 4.50 5.00
Gra
de
Au
(g/
t)
TON
NES
(kt
)
Tho
usa
nd
s
AU Cut-Off (g/t)
Grade Tonnage Curve (Porphyry - Inferred)
0.00
1.00
2.00
3.00
4.00
5.00
6.00
7.00
8.00
9.00
0
20,000
40,000
60,000
80,000
100,000
120,000
0.00 0.50 1.00 1.50 2.00 2.50 3.00 3.50 4.00 4.50 5.00
Gra
de
Au
(g/
t)
TON
NES
(kt
)
AU Cut-Off (g/t)
Grade Tonnage Curve (MDZ - Inferred)
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 260
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
14.15 Relevant Factors
SRK is not aware of any environmental, permitting, legal, title, taxation marketing or other factors that
could affect resources, however SRK considers that there may be some degree of sensitivity for the
potential to extract mineralization based on the various mining domains.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 261
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
15 Mineral Reserve Estimate The mine is currently developed to the 1,000 m elevation. A transition is occurring from narrow vein
mineralization to large porphyry mineralized areas (gold associated with pyrrhotite veinlets).
Mineralization is generally vertical with veins widths ranging from more than 1 m to several m. Porphyry
mineralized areas also have a vertical mineralization trend and can be up to approximately 100 m in
width. For this PFS, there are three different mining methods, separated into three distinct zones.
The first zone is the mineralized vein material between 950 m elevation to 1,300 m elevation, referred
to as the Veins. This is the current mine and will be mined using the current conventional cut and fill
stope method.
The second zone is the wider porphyry material between 950 m elevation and 1,050 m elevation,
referred to as the Transition Area. A modified longhole stoping method will be used in this area. The
stope size is 15 m wide by 15 m high with varying length of up to 26 m. These stopes will be mined in
a primary-secondary sequence with paste backfill for the primary stopes and unconsolidated waste
rockfill for the secondary stopes. Where waste rock is unavailable, hydraulic fill will be used to fill the
secondary stopes.
The third zone is the porphyry material below 950 m elevation, referred to as MDZ. There is a 10 m
sill pillar left in situ between the MDZ and the UZ. The MDZ material is mined using a longhole stoping
method with stope sizes that are 10 m wide by 30 m high, with varying lengths of up to 30 m. The MDZ
area is currently not developed.
The first two zones (veins and transition) are considered the UZ, and the material is processed in the
existing processing facility. The third zone is considered the MDZ and the material is envisioned to be
sent to a new processing facility. Separate mine plans are presented for the UZ area and MDZ area.
Figure 15-1 shows the general locations of the mining areas and process facilities.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 262
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SRK, 2020
Figure 15-1: Marmato General Layout
15.1 Conversion Assumptions, Parameters and Methods
Measured and Indicated Mineral Resources were converted to Proven and Probable Mineral Reserves
by applying the appropriate modifying factors, as described herein, to potential mining block shapes
created during the mine design process. Inferred material is treated as waste with zero grade. All
Mineral Reserve tonnages are expressed as "dry” tonnes (i.e., no moisture) and are based on the
density values stored in the block model.
15.1.1 Upper Zone - Dilution
The Veins dilution ranges from 20% to 55% with an average of 26%. Currently the mine has a higher
dilution (55%), however with better grade control practices, the dilution is expected to decrease to
20%. Figure 15-2 shows the change in dilution through the mine life. The Transition dilution is based
on typical dilution associated with the modified longhole mining method (Table 15-1).
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 263
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SRK, 2020
Figure 15-2: Veins Dilution
Table 15-1: Dilution Assumption
Mining Area Mining Method Dilution (%)
Veins Cut and Fill 20% - 55% (avg. 26%)
Deeps Modified Long Hole 7%
Source: SRK, 2020
15.1.2 Upper Zone - Recovery
Mining extraction ratios/recovery factors are applied to the mine design by area as shown in
Table 15-2. Items considered for the recovery include:
• Veins
o Material loss due to mucking equipment inefficiencies
o Drill and blast inefficiencies
o Geotechnical factors
• Transition Zone
o Mucking blind corners in the stopes
o Material lost into backfill
o Geotechnical factors
Table 15-2: Mining Extraction/Recovery Assumptions
Mining Area Mining Method Dilution (%)
Veins Cut and Fill 90%
Transition Modified Long Hole 90%
Source: SRK, 2020
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 264
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
15.1.3 Upper Zone - Additional Allowance Factors
An additional 5% allowance was applied to development due to overbreak. A 10% extra development
allocation is applied to the ramps in the Transition for items that were not included in the design, such
as muckbays, sumps, safety bays, etc.
15.1.4 Upper Zone – Cutoff Grade Calculation
CoG for Veins material is calculated based on the cost structure provided by Marmato as summarized
in Table 15-3. The Transition cost structure is developed based on the Veins cost as shown in Table
15-4.
Table 15-3: Cut-off Grade Parameters for Veins Material
Parameter Amount Unit
Mining Cost (1) 49.45 USD/t Process Cost 12.24 USD/t G&A 13.63 USD/t Royalties 8.96 USD/t
Total Cost (2) 84.28 USD/t
Gold Price 1,400 USD/oz Silver Price 17 USD/oz Gold Recovery 85 % Silver Recovery 65 %
CoG 2.23 g/t Au
Source: SRK (1) Includes Backfill (2) Values used here may differ from technical economic model, however SRK is of the opinion that the differences are not material.
Table 15-4: Cut-off Grade Parameters for Transition Material
Parameter Amount Unit
Mining Cost (1) 46.00 USD/t Process Cost 12.24 USD/t G&A 13.63 USD/t Royalties 8.96 USD/t
Total Cost (2) 80.83 USD/t
Gold Price 1,400 USD/oz Silver Price 17 USD/oz Gold Recovery 87 % Silver Recovery 40 %
CoG 1.91 g/t Au
Source: SRK (1) Includes Backfill (2) Values used here may differ from technical economic model, however SRK is of the opinion that the differences are not material.
A grade-tonne curve for the UZ veins area (950 m elevation and above) is shown in Figure 15-3. This
includes only Measured and Indicated material.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 265
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SRK, 2020
Figure 15-3: UZ Grade/Tonne Curve Based on Au Cut-Off
15.1.5 MDZ Mine - Dilution
The mining dilution estimate is based on ELOS (Clark, 1997). ELOS is an empirical design method
that is used to estimate the amount of overbreak/slough that will occur in an underground opening
based on rock quality and the hydraulic radius of the opening. ELOS was applied to in situ rock
exposed and to the paste backfill walls wherever mining will occur adjacent to a secondary stope. In
additional to the ELOS allowances, an additional allowance was used to account for backfill dilution
from the floor when mucking a stope.
Dilution assumptions are shown in Table 15-5.
Table 15-5: Dilution Assumptions
Type Value (m)
Sidewall ELOS (rock) 0.35
Sidewall ELOS (backfill) 0.15
Bottom (mucking backfill) 0.10
Back ELOS (rock) 0.35
Endwall ELOS (rock) 0.35
Endwall ELOS (backfill) 0.15
Source: SRK, 2020
The ELOS and floor dilution factors result in a total dilution of 8%. Backfill dilution is added using zero
grade. The rock portion of the dilution (approximately 4.5%) is expected to contain grade. The grade
applied to rock dilution is based on querying block model grades just outside the stope designs in a
representative area. This exercise showed that the dilution was approximately 50% of the stope grade,
and therefore for the reserves, the grade applied to the rock dilution is 50% of the stope grade.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 266
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
15.1.6 MDZ – Recovery
A stope recovery factor of 92.5% was used. The following items were used to calculate this factor:
• Material loss into backfill (floor) or 0.15 m
• Material loss to mucking along sides and in blind corners
• Additional loss factor due to rockfalls, misdirected loads, and other geotechnical reasons
A development recovery factor of 100% was used for all horizontal development.
15.1.7 MDZ - Additional Allowance Factors
Additional ramp allowance factors were used to account for additional excavations not included in the
PFS design. These items should be designed at the detailed planning stage. Items are summarized in
Table 15-6.
Table 15-6: Additional Ramp Allowance Factors
Type Units Conveyor
Ramp Truck Ramp
Ventilation Drifts
Footwall Accesses
>730 L
Footwall Accesses
<730 L
Average Length(1)
m 500 500 500 375 275
Muckbays m3 916 916 916 892 446
Drillbays m3 - - - - -
Electrical Bays m3 81 81 81 81 81
Pump Stations m3 324 324 - - -
Passing Bays m3 685 685 - - -
Total Additional Allowance
m3 2,006 2,006 997 973 527
Expressed as a % of Representative Length of Development
% 13.4 13.7 8.0 10.4 7.7
(1) Representative length of ramp that the listed allowances are applied to. Source: SRK
15.1.8 MDZ – Cutoff Grade Calculation
Current estimated project costs and the calculated Au CoG are shown in Table 15-7. For reporting
reserves within the design, a minimum cut-off of 1.61 g/t Au was used. A silver recovery of 50% is
expected however it was not used for the CoG calculation.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 267
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 15-7: MDZ Underground Cut-off Grade Calculation
Parameter Amount Unit
Mining cost (1) 42.00 US$/t
Process cost 14.00 US$/t
Tailings 3.00 US$/t
Production Taxes 6.75 US$/t
G&A, Other 3.00 US$/t
Total Cost (2) $68.75 US$/t
Gold price 1,400.00 US$/oz
Au Mill Recovery 95% CoG 1.61 g/t
Source: SRK (1) Includes backfill (2) Values used here may differ from the technical economic model, however SRK is of the opinion that the differences are
not material.
A grade-tonne curve for the MDZ area (950 m elevation and below) is shown in Figure 15-4. This
includes only Measured and Indicated material.
Figure 15-4: MDZ Grade/Tonne Curve Based on Au Cut-Off
15.2 Reserve Estimate
Mineral Reserves were classified using the 2014 CIM Definition standards. Indicated Mineral
Resources were converted to Probable Mineral Reserves by applying the appropriate modifying
factors, as described herein, to potential mining shapes created during the mine design process. In
the same manner, Measured Mineral Resources were converted to Proven Mineral Reserves.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 268
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
A 3D design has been created representing the planned reserve mining areas. The underground mine
design process resulted in 19.7 Mt at an average grade of 3.19 g/t Au and 6.87 g/t Ag. Table 15-8
presents the Mineral Reserve statement as of March 17, 2020.
Table 15-8: Caldas Mineral Reserve Estimate as of March 17, 2020 – SRK Consulting (U.S.), Inc.
Underground Mineral Reserves Cut-Off (1): 1.61 to 2.23 g/t
Area Category Tonnes
(kt) Au
(g/t) Ag
(g/t) Contained Au
(koz) Contained Ag
(koz)
Veins(2)
Proven 762 5.01 21.80 123 534
Probable 3,049 4.20 16.85 412 1,652
Veins Total 3,812 4.37 17.84 535 2,186
Transition (3)
Proven 40 7.63 28.16 10 36
Probable 1,293 3.43 7.92 143 329
Transition Total
1,333 3.56 8.52 152 365
MDZ(4)
Proven - - - - -
Probable 14,556 2.85 3.84 1,333 1,799
MDZ Total 14,556 2.85 3.84 1,333 1,799
Caldas Total
Proven 802 5.14 22.12 133 570
Probable 18,898 3.11 6.22 1,888 3,780
Total 19,700 3.19 6.87 2,021 4,350
Source: SRK, 2020 Notes: All figures are rounded to reflect the relative accuracy of the estimates. Totals may not sum due to rounding. Mineral Reserves have been stated on the basis of a mine design, mine plan, and economic model. Mineral Resources are reported inclusive of the Mineral Reserve. (1): Veins reserves are reported using a CoG of 2.23 g/t Au. The veins CoG calculation assumes a US$1,400/oz Au price, 85% Au metallurgical recovery, US$49.45/t mining cost, US$13.63/t G&A cost, US$12.24/t processing cost, and US$8.96/t royalties. Transition reserves are reported using a CoG of 1.91 g/t Au. The Transition CoG calculation assumes a US$1,400/oz Au price, 95% Au metallurgical recovery, US$46/t mining cost, US$13.63/t G&A cost, US$12.24/t processing cost, and US$8.96/t royalties. MDZ reserves are reported using a CoG of 1.61 g/t Au. The MDZ CoG calculation assumes a US$1,400/oz Au price, 95% metallurgical recovery, US$42/t mining cost, US$14/t processing cost, US$6.75/t production taxes, US$3/t G&A cost, and US$3/t tailings cost. Note that costs/prices used here may be somewhat different than those in the final economic model. This is due to the need to make assumptions early on for mine planning prior to finalizing other items and using long-term forecasts for the life-of-mine plan. (2): The Veins area is currently mined using cut-and-fill methods. Mining dilution ranges from 20% - 55%, averaging 26%, is included in the reserves using a zero grade for dilution. A mining recovery of 90% is applied to stopes. The Veins Mineral Reserves were estimated by Fernando Rodrigues, BS Mining, MBA, MMSAQP #01405, MAusIMM #304726 of SRK, a Qualified Person. (3): The Transition area will be mined using a modified longhole stoping method. A mining dilution of 7% is included in the reserves using a zero grade for dilution. A mining recovery of 90% is applied to stopes. The Transition Mineral Reserves were estimated by Fernando Rodrigues, BS Mining, MBA, MMSAQP #01405, MAusIMM #304726 of SRK, a Qualified Person. (4): The MDZ portion of the Project will be mined by longhole open stoping mining methods. Mining dilution (internal and external) is included in the reserve. Stope dilution is 8%, and a portion of the stope dilution is applied using grade values based on average surrounding block information. A mining recovery of 92.5% is applied to stopes. The MDZ Mineral Reserves were estimated by Joanna Poeck, BEng Mining, SME-RM, MMSAQP #01387QP, a Qualified Person.
15.3 Relevant Factors
An exclusion zone (gap) was considered in the PFS where CGM ownership was not secured at the
beginning of the PFS work. As the PFS was nearing completion CGM informed SRK that the gap was
no longer an issue; however a re-design to include the gap area was not completed. For the reserves
stated here, UZ development mining does go through the gap area. If the development material was
mineralized it is included in the Mineral Reserves. Vein mining for the UZ does not occur in the gap,
though there is mineralized material there that should be evaluated for reserves. The MDZ design
specifically avoided the gap completely. If gap ownership is no longer an issue, the UZ reserves in this
area should be updated and the development layout of the MDZ should be reviewed to ensure it is
optimal. Figure 15-5 shows the license gap.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 269
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SRK, 2020
Figure 15-5: License Gap
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 270
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
16 Mining Methods The Project has been in operations in various forms since the mid-1500s. Mineros Nacionales (MN)
was awarded the contract for the concessions in 1989. The Project was originally developed as a 300
t/d underground project in 1997 and has expanded through the years to the existing 1,200 t/d capacity
operation. Table 16-1 shows the production from 2015 to May 2020.
Table 16-1: 2015 to 2020* Production
Year Unit 2015 2016 2017 2018 2019 2020*
Ore Tonnes Processed t 303,279 341,309 365,119 338,902 370,245 119,069
Au Grade g/t 2.79 2.56 2.48 2.67 2.49 2.47
Au Recovered oz 23,954 23,449 25,163 24,909 25,750 8,318
*January through May of 2020 Source: CGM, 2020
16.1 Current Mining Methods
The mine is currently developed and mined to the 1,000 m elevation. A transition occurs from narrow
vein mineralization to large porphyry mineralized areas (gold associated with pyrrhotite veinlets).
Mineralization is generally vertical with veins widths ranging from more than 1 m to several m. Porphyry
mineralized areas also have a vertical mineralization trend and can be up to approximately 100 m in
width. For this PFS, there are three different mining methods, separated into three distinct zones as
follows:
• The first zone is the mineralized vein material between 950 m elevation to 1,300 m elevation,
referred to as the Veins. This is the current mine and will be mined using the current
conventional cut and fill stope method.
• The second zone is the wider porphyry material between 950 m elevation and 1,050 m
elevation, referred to as the Transition Zone. A modified longhole stoping method will be used
in this area. The stope size is 15 m wide by 15 m high with varying length of up to 26 m. These
stopes are mined in a primary-secondary sequence with paste backfill for the primary stopes
and unconsolidated waste rockfill for the secondary stopes. Where waste rock is unavailable,
hydraulic sand fill will be used to fill the secondary stopes.
• The third zone is the porphyry material below 950 m elevation, referred to as MDZ. There is a
10 m sill pillar left in situ between the MDZ and the UZ (Veins plus Transition area). The MDZ
material can be mined using a longhole stoping method with stope sizes that are 10 m wide
by 30 m high, with varying lengths of up to 30 m. The MDZ area is currently not developed.
The first two zones (Veins and Transition) are considered the UZ, and the material is processed in the
existing processing facility. The third zone is considered the MDZ and the material is envisioned to be
sent to a new processing facility. Separate mine plans are presented for the UZ area and MDZ area.
The UZ of Marmato consists mainly of mineralized veins with varying thickness and geotechnical
conditions. There have been several different mining methods used depending on the lithology and
ground conditions, such as shrinkage stoping, conventional cut-and-fill and caving.
Shrinkage Stoping
In the past, shrinkage stoping (Figure 16-1) is used for areas with high grade vertical veins and
competent backs. The stopes are generally 35 m long and 50 m high. Loading pockets are developed
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 271
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
on the extraction level with vertical raises on the extremity of the stopes for access and ventilation.
This is an overhand mining method using blasted ore left in the stope as a working floor. The blasted
muck also acts as support for the hangingwall and footwall. Marmato has moved away from this mining
method due to safety concerns and dilution control issues.
Source: Atlas Copco, 1980
Figure 16-1: Typical Shrinkage Stoping Diagram
Figure 16-2 shows the typical mining cycle of a CAF panel. The CAF panels are typically 35 m long by
50 m high, with varying thicknesses depending on the vein. The panels are accessed from 2.2 m by
2.2 m haulage levels on the top and bottom. Raises are developed along the vein to break the panel
into discreet mining stopes as well as to provide access and ventilation. Sub-levels are then driven
horizontally along strike. Once the sublevel is opened, vertical holes are drilled up at a length of
approximately 1.7 m to 2.3 m over the width of the vein. After blasting, the mineralized material is
mucked using either slushers, skid steer loaders or microscoops and loaded into trains and hauled
out. Once mucking is complete, concrete walls are built on either end of the stope and the stope is
filled with hydraulic sand fill. When the fill is sufficiently drained, the next slice of mineralized material
can be mined.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 272
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: Caldas, 2019
Figure 16-2: Conventional Cut and Fill Method Diagram
In areas where the ground condition is poor and does not support vertical blasting, a variant of the
CAF method, called breasting, is used. The backfill goes up to the back and mining advances
horizontally along strike. This method is slower but allows for better dilution control.
Caving
There are certain veins in the upper levels of the mine where a caving method is used. These veins
are typically in very poor ground conditions where the ore begins to cave when opened. The ore is
extracted from the drawpoint until it becomes waste, then mining moves to the level above and the
cycle repeats. While this method can provide ore at a low cost, there is no control for how much of the
vein is extracted, thus making it difficult to plan and schedule. Dilution control is also difficult as it
requires constant grade monitoring from geology.
16.1.1 Mine Layout
The current Zona Baja mining extends approximately 300 m vertically and approximately 900 m along
the vein structure. The mine has been developed with level accesses proceeding horizontally from the
main portal at the surface to horizontal cross cuts that provide access to the veins. There are currently
six production levels and one level in development, the highest production level is Level 16 and the
lowest production level is Level 21 (Figure 16-3). Each level is spaced 50 m apart vertically, with the
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 273
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
exception of Level 20, which is 60 m from Level 19. Table 16-2 lists the elevation of each level and a
brief description of the main activities on the level.
Source: SRK, 2020
Figure 16-3: Marmato Zona Baja Cross Section Looking NE with Active Levels
Table 16-2: Level Elevations and Description
o Level o Elevation o Description
o 16 o 1,260 o Production and ventilation exhaust
o 17 o 1,210 o Production and ventilation exhaust
o 18 o 1,160 o Main entrance/exit, main haulage
o 19 o 1,110 o Production and incline to Level 18
o 20 o 1,050 o Production
o 21 o 1,000 o Production and Transition Zone
o 22 o 950 o In development
Source: CGM, 2020
Level 18 is the main haulage level and the primary access for the mine and is shown in Figure 16-4.
A track drift provides the main haulage for all material. The trains exit via the south portal, unload at
the mill area and enter the mine via the north portal. Personnel and material enter via the north portal
only. All levels can be reached via ladder-ways, and a service and personnel cage hoist is nearing
completion that will provide cage access from levels 18 to 21. Level 16 and Level 17 also have adit
accesses from surface, mainly for ventilation. A rail decline from Level 18 to Level 19 provides the
ability to move material and supplies between levels. Levels below 18 are accessed by apique (vertical
shaft) hoists and skip system that allows transport of material. There are other apiques that transport
supplies to the lower levels.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 274
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SRK, 2020
Figure 16-4: Marmato Level 18 with Main Haulage (Mined Out Panels in Cyan)
16.1.2 Reconciliation
Reconciliation information was not provided to SRK and is not carried out on a regular basis. SRK
recommends that production information be reconciled to the mine plan on a regular basis to ensure
the mine plan is predicting appropriate tonnes/grades. Within a known mining area, the tonnes/grades
mined should be compared to the tonnes/grades in the block model. If there are continuous
discrepancies between the mined material and the predicted mine plan, modifications to the mine plan
process should be made to more accurately predict future mining.
16.1.3 Dilution
CGM calculates and tracks the planned dilution, which is calculated by the following formula:
𝑃𝑙𝑎𝑛𝑛𝑒𝑑 𝐷𝑖𝑙𝑢𝑡𝑖𝑜𝑛 = 𝐶𝑢𝑡𝑡𝑖𝑛𝑔 𝑊𝑖𝑑𝑡ℎ − 𝑉𝑒𝑖𝑛 𝑊𝑖𝑑𝑡ℎ
𝐶𝑢𝑡𝑡𝑖𝑛𝑔 𝑊𝑖𝑑𝑡ℎ× 100
Figure 16-5 shows the dilution as provided by CGM. The dilution has increased since 2009 due to a
shift towards higher production with a high of 31.6% dilution in 2017. CGM has introduced better drilling
practices and training to control dilution. Since 2017, the planned dilution has decreased to 20.2% in
2019.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 275
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: CGM, 2020
Figure 16-5: UZ Planned Dilution
16.2 Geotechnical
The geotechnical data base and stability approaches used at Marmato fulfill the PFS requirements.
The standards used by Marmato for data collection are broadly consistent with industry standards.
The PFS geotechnical field data collection program was developed for obtaining information for both
RMR (Bieniwasky,1989) and Barton Q’-systems (Barton,1974). Both rock mass characterization
methods were used to determine the MDZ rock mass quality (RMQ), which was used to support the
PFS underground mine design and define the type of ground support required for each underground
excavation. All mine design parameters are based on analytic empirical methods, which are
acceptable for a PFS project level design only. More detailed stability modeling should be implemented
at FS and prior to construction. SRK recommends conducting a 3D numerical modelling to determine
the effect of the mine sequence on the overall stope stability and underground infrastructure. Also,
special attention on the major fault interpretation needs to be considered as part of the FS
geotechnical drilling program.
The following sections summarize the key sections of the PFS Geotechnical Technical Report
(SRK, 2020).
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 276
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
16.2.1 Geotechnical Data Base
From June 26, 2018 to March 4, 2020 Marmato’s exploration team, under SRK guidance, conducted
a geotechnical diamond drill hole program composed of nine (NQ/HQ) drill holes totaling 4,505.9 m.
Each drill hole was designed to examine RMQ and structural features in and around the mineralized
zone at different depths and orientations. Drillholes were drilled at varying orientations into the
hangingwall, footwall and mineralized rock. The field investigation included the drilling of core,
structural feature measurements, geotechnical core logging and core sample collection for laboratory
strength testing. In addition to the geotechnical drilling program, a total of 12 exploration drill holes
(4,307 m) were validated and used to support the geotechnical domains. Figure 16-6, shows the MDZ
PFS stope designs and the geotechnical drill hole coverage.
Source: SRK, 2020
Figure 16-6: Location of Geotechnical Drill Holes (As-Builts and MDZ Design Shown)
As part of the geotechnical PFS program (SRK,2020) , Marmato carried out a laboratory testing
program which included 117 uniaxial compressive strength tests (UCS), 90 multiaxial compressive
strength tests (TCS), 46 direct shear tests applied to various discontinuities (DSS), 75 indirect tensile
strength test (BTS, Brazilian tests), 151 elastic constant measurement (Young’s modulus and
Poisson’s ratio) and 200 dry density tests.
To determine the PFS rock mass fabric, Marmato considered 564 valid data sets obtained from drill
holes MT-IU-002, MT-IU-009, MT-IU-015, MT-IU-017 and traverse mapping conducted at Level 21.
The collected data was plotted in a 2D stereogram using Dips, v.8.001 (RocscienceTM,2020).
Televiewer data obtained for drill hole MT-IU-053, was used for data validation only, and to confirm
the structural orientation obtained from traditional alpha and beta angles measurements.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 277
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
16.2.2 Engineering-Geology
Based on the geotechnical investigations, SRK observed that the Transition and MDZ is mostly
dominated by a unique lithology (P1 Porphyry). However, laboratory tests and RQD values showed
that P1 Porphyry can be subdivided into two geotechnical subdomains called P1A and P1B.
Figure 16-7 shows the location of the geotechnical subdomain and the Marmato Transition and MDZ
stopes locations.
Source: SRK, 2020
Figure 16-7: Geotechnical Subdomains
The geotechnical subdomain P1A, has been characterized as Good Rock Class II (Bieniawski, 1989).
Geotechnical logging showed RQD equal to 83% ± 4%, and a dominant spacing between 300 mm and
1,000 mm. Structural core logging indicates that most structures have joint apertures less than 1 mm
where the dominant wall strength can be considered as hard joint contacts. In terms of intact rock, field
estimated strength indicated that most of the core logging would be equivalent to R4 strength index
(50 MPa to 100 MPa), which was confirmed by laboratory tests (UCS of 80 ± 23 MPa). It was hard to
find a good correlation between intact rock strength and alteration. However, it was observed that most
of the failure mechanisms corresponded to splitting and multiple splitting associated to the micro
fracturing observed in the matrix of the intact rock. In terms of RMQ, SRK estimated the Bieniawski,
1989 RMR (RMR89) of 63 ± 7, which is equivalent to the geological strength index (GSI) equal to 58 ±
10. Based on Barton’s 1974 Q’ System, statistical assessment identified an average Q’ equal to 10.
The geotechnical subdomain P1B has been characterized as Very Good Rock Class I (Bieniawski,
1989). Geotechnical logging showed RQD values between 90% and 100% and spacing between 300
mm and 1,000 mm. Structural core logging indicates that most structures have joint apertures less
than 1 mm where the dominant wall strength can be considered as hard rough joint contacts. In terms
of intact rock, field estimated strength indicated that most of the core logging would be equivalent to
R5 strength index (100 MPa -200 MPa), which was confirmed by laboratory tests (UCS of 158 ± 19
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 278
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
MPa). SRK estimated the Bieniawski, 1989 RMR89 equal to 78 ± 17, which is equivalent to the
geological strength index (GSI) equal to 73 ± 20. Based on Barton’s 1974 Q’ System, statistical
assessment identified Q’ equal to 33.3.
In terms of rock mass fabric, SRK observed that there is not a significant structural set difference
between HW-FW and ore. SRK noted that there are no clear lithological, structural or RMQ boundaries.
Therefore, the structural domain has been considered as a unique structural domain for the MDZ,
which includes HW, FW and ore. This assumption is valid for a PFS project level. Future drilling
programs for FS-level design should confirm and/or adjust this assumption. Structural assessment
revealed the existence of three structural sets, as shown in Table 16-3. Figure 16-8 shows a plan view
of the mine layout and the PFS structural domains.
Table 16-3: Summary of Structural Sets
Domain Set Dip (°) Dip Direction (°) Variability Limit (°)
MDZ
Set 1A 76 034 15
Set 1B 80 202 20
Set 2A 70 350 12
Set 2B 75 170 10
Set 3 20 180 10
Source: SRK, 2020
(a) Structural sets Red lines: Major Faults
1: principal regional stress Source: SRK, 2020
Figure 16-8: Structural Domains
(
a
)
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 279
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
SRK observed that the structural sets orientations are well correlated with the major faults’ orientations.
For example, structural set 1B has a similar orientation to Pantano primary fault and set 2A can be
associated to Obispo faults. Set 1A is influenced by Cascabel, Criminal, Santa Ines and F2 faults.
16.2.3 Stope Stability Assessment
The design PFS stope is 30 m high, 30 m long and 10 m wide, and is located in the P1B geotechnical
subdomain. These dimensions provide acceptable stope stability for the PFS level design. Empirical
stability charts suggest that side walls are in the “unsupported transition zone”, which could involve
increased dilution from sidewalls when stopes are fully opened.
To determine the “effective unsupported span” SRK used the Bieniawski (1993) stand-up time
empirical method. Stand-up time is a function of rock mass properties and excavation technique. Two
geotechnical subdomains were assessed, P1A and P1B. SRK’s conclusion is that the stope span (10
m) is acceptable for stability in both subdomains P1A and P1B.
In term of stope ground support, the empirical stope design charts, indicate that the proposed PFS
stope dimensions will not require systematic ground support to maintain stability. Only spot bolting will
be required due to the formation of specific wedges. To determine technical specifications for ground
support, SRK completed a kinematic assessment using Unwedge 5.0 (Rocscience, 2019). Additional
refined assessments should be completed at the FS level design. SRK recommends that Marmato
perform numerical simulations for a better understanding of the potential for wedge formation during
mucking.
16.2.4 Dilution
Dilution was estimated using the Clark and Pakalnis (1992) method. This method predicts the quantity
of unstable wall rock for a given RMQ and stope size. The parameters plotted on the dilution chart are
the stability number N’ versus hydraulic radius based on case histories of dilution. The dilution is
estimated as an ELOS. The estimated ELOS indicates that MDZ is unlikely to have significant dilution
beyond blasting overbreak due to the good rock mass quality. This empirical approach is valid for PFS
design. Future FS level design should include a numerical simulation for adjusting the ELOS based
on the mine sequence.
16.2.5 Paste Fill Strength Estimation
To estimate the pastefill strength at a PFS level, SRK accepted the analytic solutions developed by
Mitchell et al, 1982. The model was developed to estimate the factor of safety (FoS) of a stope upon
exposure of unsupported backfill. Based on the Mitchell approach, SRK estimates a backfill UCS
strength of 1 MPa for single face fill exposure during mining of the adjacent secondary stope in high
stress conditions. To reach the required pastefill strength for primary and secondary stopes, laboratory
tests conducted by Paterson and Cooke indicted that 7% cement will be sufficient for obtaining high
strength pastefill in 7 days, and 4% cement will be sufficient for low strength pastefill.
At least one day of pastefill curing should be allowed to set the plug prior to completing stope filling. In
secondary stopes where the pastefill will never be exposed, sufficient binder is required to prevent
liquefaction of the pastefill during mining operations.
Based on the Paterson and Cooke test program, the majority of the tailings consist of the silicate
minerals Quartz (18.9%), and the Feldspars Albite (38.2%), Orthoclase (12.5%) and Anorthite (12.0%).
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 280
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
These minerals are inert and do not participate in the hydration dynamics of the cementitious reactions.
As such, they are considered good fillers for backfill material. The remaining tailings consist of the
phyllosilicate minerals Mica (Annite, 8.9%) and Chlorite (9.5%). Annite has weak bonds between the
internal sheet structures of the mineral allowing for failure planes and crack propagation pathways,
potentially lowering paste strength. The magnitude of this effect depends on the weathering of the
material as well as the size fraction of the particles. It has been observed that contents above 5% can
affect the strength of the backfill. The effect of Chlorite is also dependent on the formation of the
mineral, but the internal sheet structures are generally held together much more firmly than that of
Annite, and therefore is not usually an issue in backfill applications.
The water analysis shows that the decant water mainly contains trace amounts of alkali sulfates with
some alkali chlorides. The chloride content (49 mg/L) is within acceptable limits for concrete use and
will not delay the cement setting in the backfill.
There is no large presence of any other metals or problematic compounds reported in the water
analysis (Paterson and Cooke, 2020). As such, the process water is considered acceptable for backfill
purposes.
SRK requested Paterson and Cooke conduct the strength testwork with the objective of evaluating the
feasibility of using the tailings as a pastefill to reach the targeted values of 1.0 MPa for single face
exposure, and 0.5 MPa strengths for low stress conditions at 14-day cure dates. Table 16-4,
summarizes the UCS tests results.
Table 16-4: Uniaxial Compressive Strength Test Results
Mix Binder Content As-Cast Mass Concentration
W:B Ratio UCS (KPa)
7 days 14 days 28 days 56 days
1 11.5% 75.5%m 2.8 943 1,055 1,446 -
2 6.0% 75.7%m 5.6 - 510 621 TBD
3 4.5% 74.1%m 7.8 - 321 347 TBD
4 3.0% 74.1%m 11.7 132 192 230 -
Source: Paterson and Cooke, 2020
16.2.6 PFS Ground Support Requirements
To estimate the PFS ground support requirements SRK used the Norwegian Method of Tunneling
support techniques, modified by Grimstad and Barton (1993). Based on this method, SRK estimated
the PFS ground support for various excavations as shown in Table 16-5.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 281
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 16-5: Ground Support Requirements
Duration Excavation Type
Dimensions Ground Support type
Bolting spacing
(m)
Depth (m)
Width (m)
Height (m)
600 700 800 900 1000 1100
Long Term Excavations
Decline 5.5 5.6 Spot Bolting (20%, Total Excavation)
Systematic 25 mm Diameter Bolts That Are 2 m Long On 1.2 m Square Spacing and 15 by 15 Steel 5 mm Welded Wire Mesh
1.2
Ramps 5.5 5.5
Main Access 5.0 5.0
Shop Run Around Loops 5.5 5.5 Spot Bolting and Meshing as Needed (10% Of Excavations)
Main Conveyor Ramp 5.5 5.5
Medium Term (One Year)
Foot Wall Access/Haulage Drives
5.0 5.0
Spot Bolting (5% Of Excavations)
Spot Bolting (5% Of Excavations)
1.2 Cross Cuts (Option 1) 4.5 4.5
Cross Cuts (Option 2) 6.5 6.0 Spot Bolting and Meshing (10% Of Excavations)
Systematic Bolting (Above) Cross Cuts (Option 3) 6.5 7.0
Short Term (Less Than One Year)
Stope Access/In Stope Drifts
4.5 4.5 Spot Bolting (10% Of Excavations)
Stope Access/In Stope Drifts
5. 5.0 Spot Bolting (10% Of Excavations)
Production Shafts 5 Systematic Bolting (Above) 1.2
Raise Bore (No Access) 5
Spot Bolting (5% Of Excavations) 4.5
Blast Rise (No Access) 3 3
Emergency Access
5 Diameter
Spot Bolting (5% Of Excavation) Plus Systematic Fiber Reinforced Shotcrete 5 cm Thick
2 4.5
Diameter
Source: SRK, 2020
16.2.7 Sill Pillar design
To estimate the sill pillar dimension SRK used an analytic solution, which included the pillar dimensions
assuming the under-hand stope will have a backfill gap and provide no confinement to the sill pillar.
Based on analytic solution for a 30 m stope span, SRK estimates that a 9.5 m thick sill pillar in
necessary. The pillar is located approximately at 800 m depth and has a FoS of 1.5. The sill pillar could
be optimized and or recovered at the FS project level, which could result in a potential opportunity for
additional ore recovery by using numerical simulations, reducing the rock mass uncertainties and
accepting FoS of 1.3. For a FS level design, numerical simulation should consider the mine induced
stresses, which the analytic solutions have not considered.
16.2.8 Critical Infrastructure Stability Assessment
The stability study for critical infrastructure (e.g., crusher station, underground workshop, transfer
station, long term access and conveyor tunnel) were assessed at PFS level only and should not be
implemented without a more detailed investigation. A simple 2D numerical simulation indicates that
the average distance between stopes and the crusher station (approximately 40 m) does not affect the
stability of the crusher station. At PFS level, the proposed crusher dimension is acceptable. However,
more detailed studies should be implemented in the FS. SRK recommends the following activities:
• Conduct specific geotechnical drilling to characterize the rock mass and structural conditions
• Adjust the major fault model to confirm that no secondary or major fault will affect the crusher
station
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 282
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
• Conduct a 3D numerical simulation to study the effect of the mining induced stresses on
crusher station stability
• Define the required ground support before initiating the civil engineering
• Study the stability and required ground support of the bins
In terms of the underground workshop infrastructure, the stability assessment was conducted using a
tributary area method. The method assumed that the workshop station is located about 750 m deep
and assumed FoS of 1.5. The stability assessment indicates the following:
• Pillar width = 9 m
• Pillar height = 7 m
• Acceptable hydraulic radius (HR) depending of the pillar length
o HR (30 m pillar length) = 2.7
o HR (25 m pillar length) = 2.6
o HR (20 m pillar length) = 2.5
Assuming the maximum bay width is 7.5 m, SRK anticipates needing systematic bolting of 2 m long
bolts, 25 mm in diameter, and spaced 1.2 m. Also, 150 by 150 mm steel welded wire mesh (5 mm
diameter) with 5 cm fiber reinforced shotcrete.
The conveyor tunnel route selection was considered a key part of the PFS design. To select a suitable
tunnel route, high level geological, geotechnical, hydrological, hydrogeological and structural factors
were taken into consideration. Special attention was given to the effect of the modeled major faults on
the tunnel stability. To assess the potential effect of the major faults and expected rock mass quality,
SRK considered the following criteria:
• Reduce the exposure of the tunnel to major faults
• Tunnel trajectory should cross perpendicular to major faults
• Avoid faults shear zones
• Avoid crossing highly clayed materials
Based on these criteria, a feasible tunnel trajectory was identified as shown in Figure 16-9.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 283
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SRK, 2020
Figure 16-9: Conveyor Tunnel Trajectory
SRK identified six geotechnical drill hole locations, which should be drilled prior to tunnel construction
see (Table 16-6). Figure 16-10 shows a plan view with the tunnel trajectory, major faults and the FS
proposed geotechnical drilling program.
Table 16-6: FS Geotechnical Drilling Plan (Tunnel Investigation)
Hole ID Easting (m) Northing (m) Elev. (masl) Azimuth (°) Dip (°) Length (m)
MT_IU_CR 1,163,552 1,097,722 1,001 310 -68 280
MT_IU_T01 1,164,557 1,097,589 1,098 250 -85 180
MT_IU_T02 1,164,240 1,097,623 1,094 280 -78 230
MT_IU_T03 1,164,245 1,097,622 1,095 100 -75 220
MT_IU_T04 1,163,985 1,097,670 1,163 280 -85 350
MT_IU_PT01 1,164,854 1,097,822 1,008 230 -10 100
Source: SRK, 2020
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 284
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SRK
Figure 16-10: FS Drill Hole Location (Tunnel Investigation)
16.2.9 Limitations and Gaps
Although, the limitations described in this section are acceptable for a PFS level design, SRK
recommends addressing the geotechnical model’s limitations and updating the design approach for
FS level design. The main limitations and gaps are listed below:
• The structural domains were defined based on four oriented drill holes and limited structural
data obtained from the underground mine. SRK recommends that Marmato include acoustic
or optical televiewer in future exploration drill hole programs and acquire more structural data
from the underground excavations.
• The PFS major structural model should be updated based on specific drill holes and
underground mapping. Additional large-scale faults not included in the PFS geological model
which have been identified should also be considered. For a FS, shear zones and breccia
zones should be investigated.
• The empirical design charts do not include the effect of the induced stresses, due to the mine
extraction sequence. For FS, SRK recommends reviewing the PFS mine designs and with
further consideration given to mining sequences.
• The PFS ground support requirements are based on an empirical approach. SRK
recommends using a more detailed approach to determine the required ground support at an
FS level.
• The hydrogeological model has not been integrated into the geotechnical model; SRK
considers it important to include the potential pore pressure in future stability models.
• 3D numerical simulations should be conducted as part of FS study.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 285
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
• The crusher station and underground workshop stability has been defined based on empirical
approaches, which is acceptable at a PFS level. However, the PFS design should not be
implemented without a detailed engineering design.
• Long term access to critical infrastructure such as the crusher station and workshops, should
be investigated in more detail. Specific geotechnical drill holes and numerical simulations
should be considered for FS.
• Specific monitoring information from the current mine operations, such as excavation
displacements and excavation damage, should be collected to be used for future numerical
model calibrations.
16.2.10 Feasibility Study Recommendations
SRK’s opinion is that the current geotechnical data is adequate for a PFS-level design. However, to
advance the design to an FS level, additional characterization data will be required to reduce
uncertainty in the data variation. SRK provides the following recommended characterization activities
to advance the design to a final design level:
• Specific geotechnical drill holes to characterize the rock mass parameters around the critical
underground infrastructures should be drilled.
• Geotechnical core logging and televiewer data in specific exploration drill holes should be
collected and analyzed. The selection of exploration drill holes should be strategically placed
in footwall infrastructure areas and planned stope mining areas to provide sufficient data to
statistically verify the range of expected ground conditions. This includes:
o Collecting RMR/Q data
o Collecting structural orientation data
o Updating the structural model and geotechnical models
o Updating the mine design parameters
• Complete specific geotechnical drill holes to characterize the rock mass parameters around
the conveyor tunnel
• Update the major faults model
• Conduct pre-mining in situ stress measurements
• Collect tiltmeter measurements to confirm that there is minimal subsidence above the
transition zone
• Develop a Ground Control Management Plan with a Triggered Action Response Plan (TARP)
in case of excessive deformation or drift collapse or seepage inflows
• Perform mine scale stress analyses of the planned stoping sequence to evaluate:
o The appropriateness of infrastructure setback distances
o Anomalous stress conditions resulting from the stoping sequence
o Variations in stress and groundwater conditions
o Spatial variations in rock mass strength conditions
• A mine scale hydrogeological pore pressure model should be developed that considers
locations and hydraulic conductivity of specific fault structures as they intersect drifts and
stopes
• Long term access to critical infrastructure should be evaluated, such as the crusher station
and workshops. Specific geotechnical drill holes and numerical simulations should be
considered for the FS.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 286
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
• Specific monitoring information from the current mine operations should be reviewed for future
numerical simulations and calibrations, such as excavation displacements and excavation
damage. It is important to re-evaluate the ground support based on depth and mine
sequencing.
16.3 Hydrogeology and Mine Dewatering
16.3.1 Hydrogeological Conditions
The mine area is located in the hydrogeological regional area of Magdalena Cauca. The region is
comprised of igneous and metamorphic rocks with limited groundwater storage capacity and hydraulic
conductivity (IDEAM, 2013). The porphyry units represent the main hydrogeological units in the mine
area, with a low hydraulic conductivity and limited groundwater storage capacity. Groundwater flow is
compartmentalized within structural blocks with limited hydraulic communication across fault
boundaries due to fault gouge, weathering, or an offset of geological units.
Previous field campaigns were performed by KP in 2011 and 2012 (Knight Piésold, 2012). The current
field campaign is being performed by SRK, the program began in early 2020 and primarily consisted
of packer isolated interval testing, monitoring well and VWP installations in underground coreholes or
locations distal to the mine area.
SRK analyzed all available hydrogeological data, including:
• KP 172 packer tests, three piezometers installed underground, 11 piezometers installed from
ground surface
• SRK 70 packer tests completed in four coreholes (MT-IU-053, MT-IU-063, MT-IU-065 and MT-
IU-066) and VWP’s installed in MT-IU-063 and MT-IU-066
• SRK 2020 field campaign currently in progress focusing on underground targets from surface
locations
• Historic mine water discharge records in 2017 and 2019
• Historic water level measurements in the hydrogeologic study area
• Water level measurements in vibrating wire piezometers MT-IU-063 and MT-IU-066 installed
in 2020
Hydrogeological Units and Faults
Saprolitic coverage and intrusive fracture rock are the two major hydrogeological units defined in the
Marmato mine area. The saprolite is formed by clay material that has weathered on the top of intrusive
rock units. It can reach over 30 m in some locations and is usually dry in the mine area. The intrusive
fractured rock corresponds to dacite and andesite porphyry stocks and a sheeted pyrite veinlet system
associated with intermediate argillic and propylitic alteration.
The Amaga Formation is present E and SE of the mine area in disconnected pockets and more
extensively W of the mine within the Supia River Valley. The depths of the Supia formation are
unknown. Alluvial sediments are present along creeks and rivers.
The Criminal Fault, which is located to the N of Cerro los Burros and runs toward the Cauca River on
Quebrada Los Pantanes, appears to form compartmentalization of geological blocks with limited
communication across the fault (Knight Piésold, 2012). This fault represents a contact point between
the Dacite Porphyry P1 in Cerro Lo Burros and Dacite Porphyry P2 and Graphitic Schist exposed to
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 287
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
the N. The Criminal Fault is 15 to 20 m wide, has a clayey alteration and has a low water filtration flow.
However, to the north of this contact, horizontal boreholes produce water flow from 7 to 8 L/s in Level
17. Also, water flow has been reported in the same location on Level 21.
From the 2020 drilling program, it is apparent that high-permeability zones (hydraulic conductivity
greater than 0.1 m/d), which may be associated with Fault 2 and Fault 1-3, were encountered in the
vicinity of the planned mine at depths of 600 to 800 m below ground surface (bgs).
Hydraulic Parameters
Measured hydraulic conductivity of the bedrock groundwater system in the vicinity of the mine were
obtained from 2012 and 2020 investigations and are presented in Figure 16-11 and Table 16-7.
Table 16-7: Measured Bedrock Hydraulic Conductivity Values at Depth
Depth (m bgs) Number of Tests
Hydraulic Conductivity (K) (m/d)
Top Bottom Geometric Mean Minimum Maximum
0 200 73 4.05E-02 8.06E-04 8.49E+00
200 400 28 2.35E-02 6.38E-04 1.81E-01
400 850 127 1.30E-02 1.78E-04 1.18E+00
850 1,500 22 1.16E-03 1.12E-04 9.89E-03
Source: SRK, 2020
Source: SRK, 2020
Figure 16-11: Distribution of Measured Hydraulic Conductivity Values vs. Depth
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 288
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
These results indicate:
• Large variability (2 to 3 orders of magnitude)
• General trend of decreasing hydraulic conductivity with depth
• Very low permeability at approximately 850 m bgs where lower part and bottom of the deep
underground mine is planned.
The zone of enhanced hydraulic conductivity values at depths of 600 to 800 m below the ground
surface corresponds to fractured zones associated with Fault 2 and Fault 1-3 in the mine area. Based
on these findings, bedrock units were grouped into four hydrogeological units varying with depth. Base
Case distribution of hydraulic conductivities is based on geometric mean at discrete depth intervals
and was used to predict expected mine inflow.
Measured Water Levels and Direction of Groundwater Flow
Measured water levels show elevations from 661 to 2,022 m Magna Sirgas/Colombia West coordinate
system (MSCW), following the topography at 100 m depth in most of the locations outside the mine
area. Estimated water table and direction of groundwater flow for pre-mining conditions are shown in
Figure 16-12.
Water levels vs. depth and vertical hydraulic gradients were measured in two deep coreholes MT-IU-
063 and MT-IU-066 drilled in 2020 in the vicinity of the planned MDZ mine. Two strings of grouted-in
transducers were installed in these two coreholes, indicating:
• Water level elevations measured from 1,006 to 1,012 m MSCW in MT-IU-063
• Water level elevations measured from 1,065 to 1,072 m MSCW in MT-IU-066
• Mixture of upward and downward hydraulic gradients in both coreholes
Measured water levels and groundwater flow data that were used for model calibration are discussed
in Section 1.3.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 289
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SRK, 2020
Figure 16-12: Estimated Water Table and Direction of Groundwater Flow
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 290
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
A depressurization zone was detected in the underground piezometers where the water levels have a
horizontal trend. The shape or extent of the depressurization zone is currently unknown. On a more
regional scale, the groundwater flows W to E, following the topographical gradient to the Cauca River,
located at 692 m MSCW in the proximity of the mine. The Cauca River represents the main discharge
for the hydrogeological system. A conceptual hydrogeological cross-section is shown in Figure 16-13.
Source: SRK, 2020
Figure 16-13: Conceptual Hydrogeological Cross-Section
Current Mine Dewatering
The mine has a series of pumps and tanks from Level 22 to Level 19, where the water is pumped to
the processing plant to be used as makeup water. Each level collects the water produced in its
developments in addition to infiltration coming from levels above. The water is briefly stored in a tank
and pumped to the next level above. Water from Level 16 and Level 17 is collected by gravity and
discharges to Level 18 and through to the process plant. Figure 16-14 shows a simplified scheme of
the current dewatering system.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 291
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: CGM, 2019
Figure 16-14: Scheme of Current Dewatering System
Preliminary flow measurements were conducted at mine adits and are presented in the environmental
baseline report prepared by CGM (date unknown). The measurement values vary from a total of 6.3
to 15.9 L/s in summer and winter. However, there is no information about which mine levels were in
operation during the flow measurements.
A measurement record of total mine water discharge is available from January 2017. The measured
monthly average of total dewatering in Marmato mine is 37 L/s, varying from 26.8 to 46.4 L/s. Strong
seasonal trends were not observed; however, a decrease of approximately 16 L/s can be detected in
the last 12 months. Figure 16-15 shows the total water discharge from the Marmato mine.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 292
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: CGM, 2019 Data from July to December 2017 is not available.
Figure 16-15: Measured Mine Water Discharge
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 293
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
The dewatering flow is a combination of groundwater inflows and water content in the hydraulically
placed backfill material (60 to 65% of water). According to Marmato operational personnel, the
contribution of the backfill material is 7 to 14 L/s, depending on the number of hydraulic backfill
equipment in operation. Therefore, the average fresh groundwater inflow into the mine could vary from
23 to 30 L/s. A significant amount of groundwater flow comes from the north section of Level 17
(crossing the Criminal Fault) where horizontal boreholes contribute 7 to 8 L/s.
The existing dewatering system fits the current needs for the mine operations at Marmato mine.
16.3.2 Descriptions of Numerical Groundwater Model
SRK developed a preliminary 3D numerical groundwater flow model using the MODFLOW-USG code,
based on available climatic, geological and hydrogeological data. Historic and proposed underground
mine developments were incorporated into the model. Plan-view and modeled cross-section are
shown in Figure 16-16 and Figure 16-17.
Source: SRK, 2020
Figure 16-16: Model Grid Discretization – Plan View
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 294
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SRK, 2020
Figure 16-17: Modeled Cross-Section
The simulated hydrogeological units and their hydraulic parameters are shown in Table 16-8.
Table 16-8: Simulated Hydraulic Parameters
Hydrogeologic Unit
Horizontal Hydraulic
Conductivity
Vertical Hydraulic Conductivity
Specific Storage
Specific Yield
m/day 1/m (-)
Alluvium 5 1 1.00E-06 0.10
Amaga Formation 0.1 0.05 1.00E-06 0.05
Amaga Formation (SW of Domain) 0.5 0.01 1.00E-06 0.05
Saprolite 0.5 0.5 1.00E-06 0.05
Bedrock depth<200 m bgs 0.04 0.04 1.00E-06 0.01
Bedrock 200 to 400 m bgs 0.023 0.023 1.00E-06 0.01
Bedrock 400 to 850 m bgs 0.013 0.013 1.00E-06 0.01
Bedrock depth>850 m bgs 0.0012 0.0012 1.00E-06 0.01
Source: SRK, 2020
The World Climate dataset was used to define precipitation within the model domain. Mean annual
precipitation (MAP) varies from about 2,700 mm/yr in the mountains to 1,930 mm/yr in the vicinity of
the Cauca River, with values of 2,400-2,500 mm/yr in the mine area. The relationship between
recharge coefficient vs. ground surface elevation was established during the model calibration process
to match the measured water levels and groundwater flows. Within the mine area, the recharge
coefficient was calculated to be within the range of 0.35 to 0.45 (or from 35% to 45% of MAP).
The rivers, creeks, and groundwater outflows as simulated by the numerical model are shown in Figure
16-18.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 295
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SRK, 2020
Figure 16-18: Simulated Rivers, Creeks and Groundwater Outflows
Both historic and future underground developments (tunnels, drifts, declines, stopes, vents and ramps)
were simulated using drain cells, which extract groundwater from the model depending on the water
level elevation above the development and the assigned conductance. The elements of simulated
planned underground mine are shown in Figure 16-19.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 296
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SRK, 2020
Figure 16-19: Simulated Developments and Stopes for Planned Mine
The stopes were assumed as “non-restrictive” to groundwater inflow developments due to their size
(similar to the model cell) and this assumption was used for Base Case predictions; i.e., drain cell
conductance for the stope was kept unchanged throughout the LoM.
In SRK’s opinion, planned backfill of the stopes most likely will not restrict groundwater inflow, because
some empty space between the stope roof and backfill would exist due to backfill subsidence. The
Base Case used for predictive simulation does not consider the restrictive effect of the backfilling.
However, the potential of the backfill to restrict groundwater inflow was evaluated, in order to generate
a minimum mine inflow estimate, and was simulated as an additional sensitivity run. In this run, the
unrestrictive stope (drain) conductance of 10,000 m2/d was replaced by a restrictive conductance value
of 0.1 m2/day, six months after mining of the stope starts (six months was the stress period length set
in the model).
The groundwater model was calibrated to:
• Pre-mining water levels (2011 to 2012)
• Historic mine discharge rates (2017 to 2019)
• Water levels installed in piezometers installed recently (2020)
In SRK’s opinion, the developed preliminary groundwater model is conservatively calibrated to the
limited available flow and water level data and is suitable for predictive simulations of mine dewatering
requirements at the PFS level.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 297
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
16.3.3 Results of Predictions by Groundwater Model
The numerical model was used to predict:
• Passive inflow to the existing and planned underground mine
• Propagation of drawdown as the result of planned dewatering under mining conditions
• Changes in groundwater discharge to river and creeks under mining conditions
The model predictions were made under four scenarios shown in Table 16-9.
Table 16-9: Predictive Scenarios Evaluated by Groundwater Model
Scenario Bedrock Hydraulic Conductivity Inflow to Backfill
Base Case - Expected Inflow Geomean Unrestricted
Sensitivity Runs
Maximum Inflow Average Unrestricted
Minimum Inflow Geomean Restricted
Permeable Faults Geomean (separate for bedrock and faults) Unrestricted
Source: SRK, 2020
The first scenario, in SRK’s opinion, represents the Base Case or expected scenario, while the second,
third, and fourth scenarios were completed as sensitivity analyses to identify possible range of
groundwater inflow scenarios to existing and planned underground mines.
The model predicts:
• The majority of inflow to the planned mine (up to 78 L/s with a possible range from 56 to
159 L/s) is expected from the upper levels above 730 m where elevated hydraulic conductivity
values of the bedrock groundwater system were measured.
• Mine inflow to the MDZ planned mine below 730 m is predicted to be lower (15 L/s with an
upper limit of 34 L/s) due to reduced measured hydraulic conductivity with depth.
• Total maximum planned mine discharge is predicted to be up to 88 L/s with a possible range
from 61 to 167 L/s.
• Total maximum discharge into the entire mine complex, including flow to existing mine levels,
is predicted to be up to 111 L/s with a possible range from 89 to 168 L/s.
• The major sources of mine inflow are the depletion of groundwater storage and capturing of
groundwater discharge to surface water bodies (i.e. streams). The model does not predict the
reversing of hydraulic gradient between the mine area and the Cauca River and does not
predict inflow to the mine from the river. However, further investigation of the structures and
their hydrogeological role are needed to verify this conclusion.
Predicted expected groundwater inflows to the underground mine (Base Case) are shown in
Figure 16-20. Sensitivity runs (maximum inflow, minimum inflow, and inflow under permeable faults
scenarios) are summarized in Figure 16-21.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 298
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SRK, 2020
Figure 16-20: Predicted Mine Inflow During Years 2021 to 2032 (Base Case)
Source: SRK, 2020
Figure 16-21: Comparison of Total Predicted Dewatering Requirements for Base Case and Sensitivity Scenarios
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 299
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
In SRK’s opinion, completed predictions of mine inflow are conservative, given that the model:
• Is based on the extrapolation of the measured hydraulic conductivity values in mine areas for
the entire model domain, including topographic high areas outside of the mine area, where
measured water levels are high and hydraulic conductivity values are most likely lower than in
the mine area
• Use of high recharge from precipitation to calibrate the model to measured water levels,
combined with geomean K values in discrete depth intervals that are derived from measured
K values in the mine area
• Use of calibrated conductance values that reproduce measured inflow to the existing, relatively
shallow mine for the simulation of groundwater inflow to the deep underground developments
of the planned mine
• Simulate no restriction of groundwater inflow to the backfilled stopes for Base Case, maximum
inflow, and permeable fault scenarios
Predicted water table at the end of mining on the west to east cross-section through the mine area for
Base Case is shown in Figure 16-22. Predicted drawdown (water table changes) at end of the mining
in plan-view for Base Case is shown in Figure 16-23.
Source: SRK, 2020
Figure 16-22: Predicted Water Table and Direction of Groundwater Flow at End of Mining Shown on West to East Cross-Section through Mine Area
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 300
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SRK, 2020
Figure 16-23: Predicted Drawdown at End of Mining (Base Case, End of 2032)
The model predicts:
• The lowering of the water table in the mine area of up to 140 m and drawdown propagation of
up to 2 km away from the mine, assuming a 10-m drawdown extent.
• Creating of a “bulb” of depressurization around the planned underground mine.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 301
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
• Table 16-10 summarizes maximum mine inflows, reduction of groundwater discharge to the
rivers and creeks from the current conditions and potential inflow from the Cauca River.
Table 16-10: Predicted Maximum Mine Inflows and Reduction of Groundwater Discharge to the Rivers and Creeks Under Different Scenarios
Scenario
Predicted Maximum Inflow (L/s)(1)
Maximum Reduction of Groundwater Discharge to
Rivers and Creeks from Current Conditions (L/s)
Maximum Inflow from Cauca
River (L/s) Total Existing
Mine Planned
Mine
Expected Inflow - Base Case
111 40.5 88 74 0
Maximum Inflow Scenario
168 12.2 167 147 0
Minimum Inflow Scenario
90 40.5 61 49 0
Permeable Faults Scenario
150 35.6 138 117 0
Note: (1) Maximum Inflow is predicted at different time Source: SRK, 2020
16.3.4 Hydrogeological Uncertainties
The completed analysis of available hydrogeological data and numerical groundwater modeling
indicates that several uncertainties remain in the understanding of the hydrogeological conditions in
the proximity of the mine. These uncertainties include:
• Hydrogeological role of faults: Extend outside of the mine area and connect to the Cauca River
• Hydraulic properties of bedrock outside of the mine area (especially in areas of topographic
high, where shallow depth to water table has been measured)
• Nature of elevated hydraulic conductivity in the mine area at depth from about 600 to 800 m
bgs (elevation approx. between 700 and 900 m MSCW) in the vicinity of Fault 2 and Fault 1-3;
planned conveyor decline and egress ramp plan to intersect Fault 2 at multiple
locations/elevations
• Recharge estimates from direct precipitation and potential recharge enhancement in the mine
area as result of artisan mine developments
• Limited availability of hydrogeological data related to:
o Groundwater inflow to the current mine (changes in time, spatial and vertical distribution,
and water usage for mining)
o Water table elevation and water level changes due to passive mine dewatering and
seasonal changes in precipitation
• Hydrogeological role of backfill material and possibility to reduce groundwater inflow to mine
developments and stopes
• Groundwater chemistry with depth
Considering the hydrogeological uncertainties mentioned above, SRK recommends planning for a
mine pumping capacity of 168 L/s corresponding to the maximum inflow scenario.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 302
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
16.4 Upper Zone Mining
16.4.1 Stope Optimization
Stope optimization was completed using Maptek Vulcan’s implementation of Alford Mining Systems’
Stope Optimization program and the PFS block model. Optimization parameters are determined based
on the mineralization geometry, current equipment constraints and geotechnical constraints. These
parameters are listed below.
Veins Stope Optimization
Veins area optimization parameters are as follows:
• CoG of 2.23 g/t Au
• 1 m minimum mining width
• 5 m block heights
• 10 m block length along strike
• Angled stopes based on vein geology
• Elevation between 950 m and 1,300 m
Optimization results are assessed and combined to form 35 m long by 50 m high stopes. Figure 16-24
shows the results of the stope optimization.
Source: SRK, 2020
Figure 16-24: Stope Optimization results for the Veins (Section looking Northeast)
Transition Zone Stope Optimization
Transition Zone optimization parameters are as follows:
• Cut-off of 1.91 g/t Au
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 303
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
• 25 m mining length
• 15 m block heights
• 15 m block width
• Angled stopes based on vein geology
• Elevation 950 m to 1,050 m
Figure 16-25 shows the optimization results for the Transition Zone.
Source: SRK, 2020
Figure 16-25: Stope Optimization Results for the Transition (Section Looking Northeast)
Figure 16-26 shows the overall mine design based on the stope optimization results from the Veins
and the Transition (collectively, the UZ) colored by grade.
Source: SRK, 2020
Figure 16-26: Stope Optimization Results for the UZ Colored by Au Grade (Section Looking Northeast)
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 304
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
16.4.2 Mine Design
Veins Stope Design
The stopes generated from the stope optimizer were amalgamated into 35 m long by 50 m high blocks.
The minimum mining width is 1 m and the stope widths vary between 1 m and 3 m. This is consistent
with the stope size CGM is currently using to mine the veins. There are certain gaps in the blocks
generated by the optimizer, and these are not included as part of the mining plan. These gaps could
potentially be mined as marginal material.
Veins stopes are from Level 22 (950 m elev.) to Level 16 (1,300 m elev.).
Veins Development Design
2.2 m by 2.2 m drifts are designed to follow the veins where possible. A diluted grade was calculated
for this development material and tonnages/grades for development material are tracked separately
from stope material in the production schedule.
Sublevels are typically 1.4 mW x 2.2 mH and it is calculated into the production rate of the stopes.
Vertical raise development at the ends of the stopes is 1.4 mW x 1.4 mL and it is also calculated into
the production rate for the stopes.
Transition Stope Design
The Transition will use a modified long hole stoping method in a bottom up orientation. Stopes are 15
mW x 15 mH x 25 mL. Stopes are mined in a primary-secondary sequence with pastefill as the primary
backfill and waste rock as secondary backfill, as shown in Figure 16-27. Waste rock will primarily come
from development. Where waste rockfill is insufficient or unavailable, hydraulic sandfill will be used as
backfill. Top and bottom transverse access are driven into the stopes and the stopes are drilled down
using a jumbo fitted with a longhole drill (Figure 16-28). The stopes are mucked with an LHD and
loaded into trucks or an orepass. Rail carts haul the ore to the apiques on the main haulage levels. A
7 m sill pillar is left between Level 21 and 22. While pastefill is available, additional work is required in
the next level of study to explore the feasibility of recovering the pillar.
Source: SRK, 2020
Figure 16-27: Transition Mining Method (Magenta is Primary and Cyan is Secondary)
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 305
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SRK, 2020
Figure 16-28: Plan View of Transition Development
16.4.3 Production Schedule
The production schedule is based on the productivity rates shown in Table 16-11.
Table 16-11: Productivity Rates
Activity Type Dimension Rate
Veins Stopes 18 t/d
Veins Development 2.2 m x 2.2 m 1.19 m/d
Veins Level 2.2 m x 2.2 m 1.19 m/d
Transition Stopes 400 t/d
Transition Development (Access, Ramp and Crosscuts)
3.5 m x 3.5 m 4 m/d
Transition Backfill 220 m3/d
Apique 2 m x 4 m 0.6 m/d
Transition Vent Raise 3.5 m x 3.5 m 1 m/d
Source: SRK, 2020
Veins stope production rate includes the mining of the stope and backfilling. The production rate for
the Transition stopes includes the drilling and blasting of the stope. The backfill rate for the Transition
is 220 m3/d.
The apique development rate of 0.6 m/d assumes that the apiques are in use in the levels above.
The production schedule targets a total production of 1,500 t/d or 525,000 t/y (based on 350 days per
year) to the mill. A gradual ramp up is planned for 1,100 t/d (385,000 t/y) in 2020, 1,250 t/d (437,500
t/y) in 2021, 1,400 t/d (490,000 t/y) in 2022 and 1,500 t/d in 2023. The Transition accounts for 400 t/d
while the remaining UZ production comes from the veins. LoM for the Veins is 12 years for a total of
3.81 Mt at 4.37 g/t Au. LoM for the Transition zone is 11 years for a total of 1.33 Mt at 3.56 g/t Au.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 306
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
There is a 2 Mt/y permit limit to material moved for the mine. The production schedule prioritizes the
production of the MDZ, therefore the production in the UZ from 2024 onwards is reduced to respect
this limit.
Combined UZ production is 5.14 Mt at 4.16 g/t Au. The production schedule was completed using
iGantt scheduling software from Minemax. Table 16-12 shows the upper mine total production
schedule and Table 16-13 show the total development schedule. Figure 16-29 shows the production
schedule colored by time period.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 307
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 16-12: Marmato Upper Mine Total Production Schedule
PFS Schedule Unit
2020 2021 2022 2023 2024
Summary 1/1/2020 4/1/2020 7/1/2020 10/1/2020 1/1/2021 4/1/2021 7/1/2021 10/1/2021 1/1/2022 4/1/2022 7/1/2022 10/1/2022 1/1/2023 4/1/2023 7/1/2023 10/1/2023 1/1/2024 4/1/2024 7/1/2024 10/1/2024
Total Ore Tonnes t 30,179 63,460 96,282 96,251 109,369 109,373 109,375 109,370 122,529 122,503 122,512 122,506 131,252 131,247 131,253 131,251 121,935 123,194 123,204 123,202
Ore Au (g/t) g/t 3.73 3.70 3.61 3.65 3.90 3.98 4.05 4.02 3.97 3.96 3.76 4.13 3.97 3.88 4.09 3.96 3.84 3.78 4.07 4.14
Ore Ag (g/t) g/t 19.82 17.27 16.14 16.31 16.57 14.90 14.00 12.57 12.51 12.75 13.36 13.65 14.35 13.90 14.58 16.62 16.22 15.65 16.42 16.70
Au_Oz Oz 3,617 7,558 11,184 11,305 13,717 13,988 14,244 14,138 15,652 15,597 14,797 16,272 16,732 16,390 17,251 16,705 15,049 14,987 16,126 16,399
Ag Oz Oz 19,230 35,229 49,972 50,458 58,262 52,384 49,215 44,596 50,548 51,111 52,622 53,745 60,536 58,639 61,532 70,115 63,574 61,992 65,054 66,159
Waste Tonnes (t) t - 3,535 18,417 29,648 32,544 32,401 31,720 30,591 29,850 30,947 24,290 26,448 16,101 10,838 10,808 8,819 1,247 - - -
Total Development Length (m) m - 413 1,503 2,037 2,258 2,153 1,994 1,959 1,936 2,063 2,035 1,897 1,534 1,002 1,000 801 108 - - -
Total Material Moved t 30,179 66,994 114,699 125,899 141,914 141,774 141,095 139,961 152,378 153,450 146,802 148,954 147,353 142,086 142,062 140,070 123,182 123,194 123,204 123,202
Total Material to Surface t 30,179 66,994 107,770 125,899 134,663 141,774 141,095 133,503 135,130 135,625 137,607 148,954 147,353 134,862 136,780 128,507 123,182 123,194 123,204 123,202
Production Ore Breakout
All Stope Ore Tonnes t 30,179 60,136 85,539 80,601 93,568 98,383 100,025 101,482 112,666 109,901 106,108 110,930 117,717 127,775 127,784 128,639 121,640 123,194 123,204 123,202
All Stope Ore Au (g/t) g/t 3.73 3.75 3.64 3.63 3.80 3.98 4.10 4.02 3.92 3.96 3.89 4.21 4.05 3.91 4.12 3.96 3.84 3.78 4.07 4.14
All Stope Ore Ag (g/t) g/t 19.82 17.56 16.86 17.15 16.92 15.18 14.22 12.79 12.90 13.11 14.06 14.19 14.87 14.01 14.76 16.52 16.20 15.65 16.42 16.70
Veins Stope Tonnes t 30,179 60,136 76,853 78,218 68,141 68,316 71,740 69,987 85,072 84,790 83,110 86,938 91,999 92,878 92,652 93,472 86,594 88,269 88,079 88,071
Veins Stope Ore Au (g/t) g/t 3.73 3.75 3.68 3.64 3.78 4.12 4.18 4.16 4.17 4.16 4.00 4.33 4.16 4.05 4.22 4.10 4.07 4.10 4.34 4.37
Veins Stope Ore Ag (g/t) g/t 19.82 17.56 17.24 17.12 17.25 17.62 15.69 14.79 14.60 14.97 15.25 15.54 16.03 16.08 17.04 18.08 18.62 17.71 18.78 18.59
Trans Stope Tonnes t - - 8,685 2,383 25,427 30,067 28,284 31,495 27,595 25,112 22,997 23,992 25,718 34,896 35,132 35,167 35,045 34,925 35,124 35,131
Trans Stope Ore Au (g/t) g/t - - 3.27 3.33 3.83 3.66 3.91 3.72 3.12 3.27 3.48 3.79 3.63 3.53 3.83 3.61 3.27 2.97 3.41 3.57
Trans Stope Ore Ag (g/t) g/t - - 13.53 18.29 16.02 9.62 10.46 8.36 7.69 6.85 9.73 9.30 10.69 8.52 8.75 12.37 10.21 10.45 10.52 11.98
PFS Schedule Unit
2025 2026 2027 2028 2029 2030 2031 2032 Totals
Summary 1/1/2025 1/1/2026 1/1/2027 1/1/2028 1/1/2029 1/1/2030 1/1/2031 1/1/2032
Total Ore Tonnes t 388,538 452,030 409,596 351,864 386,605 388,893 445,183 91,713 5,144,667
Ore Au (g/t) g/t 4.40 4.30 4.34 4.38 4.30 4.18 4.43 4.22 4.16
Ore Ag (g/t) g/t 16.98 15.75 15.23 14.42 14.33 14.43 17.43 21.69 15.41
Au_Oz Oz 54,909 62,550 57,148 49,501 53,388 52,318 63,448 12,446 687,417
Ag Oz Oz 212,110 228,950 200,573 163,133 178,125 180,418 249,410 63,953 2,551,644
Waste Tonnes (t) t - - - - - - - - 338,205
Total Development Length (m) m - - - - - - - - 24,692
Total Material Moved t 388,538 452,030 409,596 351,864 386,605 388,893 445,183 91,713 5,482,872
Total Material to Surface t 388,538 452,030 409,596 351,864 386,605 388,893 445,183 5,302,186
Production Ore Breakout
All Stope Ore Tonnes t 388,538 452,030 409,596 351,864 386,605 388,893 445,183 91,713 4,997,095
All Stope Ore Au (g/t) g/t 4.40 4.30 4.34 4.38 4.30 4.18 4.43 4.22 4.17
All Stope Ore Ag (g/t) g/t 16.98 15.75 15.23 14.42 14.33 14.43 17.43 21.69 15.55
Veins Stope Tonnes t 287,393 335,352 292,553 259,173 246,341 248,792 402,365 91,713 3,749,179
Veins Stope Ore Au (g/t) g/t 4.51 4.54 4.51 4.65 4.86 4.68 4.57 4.22 4.37
Veins Stope Ore Ag (g/t) g/t 19.46 18.93 18.32 17.25 18.24 18.67 18.49 21.69 17.88
Trans Stope Tonnes t 101,145 116,678 117,043 92,691 140,264 140,100 42,819 - 1,247,916
Trans Stope Ore Au (g/t) g/t 4.06 3.62 3.92 3.60 3.31 3.30 3.14 - 3.56
Trans Stope Ore Ag (g/t) g/t 9.94 6.62 7.51 6.52 7.47 6.91 7.47 - 8.55
Source: SRK, 2020 Note: Numbers may not sum due to rounding.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 308
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 16-13: Marmato Upper Mine Total Development Schedule
PFS Schedule Unit
2020 2021 2022 2023 2024
Summary 1/1/2020 4/1/2020 7/1/2020 10/1/2020 1/1/2021 4/1/2021 7/1/2021 10/1/2021 1/1/2022 4/1/2022 7/1/2022 10/1/2022 1/1/2023 4/1/2023 7/1/2023 10/1/2023 1/1/2024 4/1/2024 7/1/2024 10/1/2024
Development Ore Breakout
All Development Ore Tonnes (t) t - 3,323 10,744 15,650 15,801 10,989 9,350 7,888 9,862 12,602 16,404 11,576 13,534 3,472 3,469 2,612 296 - - -
All Dev Ore Au (g/t) g/t - 2.97 3.38 3.77 4.52 3.94 3.53 3.97 4.63 3.96 2.92 3.33 3.25 3.03 3.08 3.79 4.84 - - -
All Dev Ore Ag (g/t) g/t - 11.94 10.42 11.93 14.50 12.41 11.65 9.65 7.96 9.55 8.85 8.42 9.82 9.54 8.01 21.25 23.81 - - -
Veins Development Ore Tonnes (t) t - 2,341 9,374 8,375 6,028 6,028 2,532 3,790 2,467 2,784 4,186 452 4,250 3,472 3,469 2,612 296 - - -
Veins Dev Ore Au (g/t) g/t - 2.83 3.35 4.11 6.89 4.66 3.50 3.34 3.89 3.92 2.66 2.62 3.10 3.03 3.08 3.79 4.84 - - -
Veins Dev Ore Ag (g/t) g/t - 8.84 10.45 13.39 22.86 15.50 16.47 13.14 14.24 19.53 10.84 24.08 17.11 9.54 8.01 21.25 23.81 - - -
Trans Development Ore Tonnes (t) t - 983 1,369 7,275 9,773 4,962 6,818 4,097 7,396 9,818 12,218 11,123 9,284 - - - - - - -
Trans Dev Ore Au (g/t) g/t - 3.31 3.57 3.39 3.05 3.07 3.54 4.55 4.87 3.97 3.00 3.36 3.32 - - - - - - -
Trans Dev Ore Ag (g/t) g/t - 19.34 10.20 10.25 9.34 8.65 9.86 6.43 5.87 6.72 8.17 7.78 6.47 - - - - - - -
Lateral Development Breakout
Veins Development -DEV-2.2x2.2 (m) m - 329 971 974 1,161 1,353 1,290 1,346 1,270 1,286 1,333 1,241 1,093 1,002 1,000 801 108 - - -
Trans Ramp Development -RMP-3.5x3.5 (m) m - - 59 59 183 318 299 49 - - - - - - - - - - - -
Veins Level -LVL-2.2x2.2 (m) m - - 31 135 109 - - - - - - - - - - - - - - -
Trans Level Access -ACC-3.5x3.5 (m) m - 1 135 258 187 - - 286 311 316 - - - - - - - - - -
Trans Ore Xcut -XCT2-4x3.5 (m) m - - 36 149 153 137 216 103 196 260 341 324 246 - - - - - - -
Trans Waste Xcut -XCT1-3x3 (m) m - 40 62 170 412 345 189 155 140 176 362 332 195 - - - - - - -
Ventilation Drift -VNT-3.5x3 (m) m - - 20 11 - - - 7 7 8 - - - - - - - - - -
Vertical Development Breakout
Apique Development (m) m - 18 78 64 - - - - - - - - - - - - - - - -
Ventilation Raise -RAR-3x3 (m) m - - 19 7 - - - 12 12 17 - - - - - - - - - -
Backfill Breakout
Veins Backfill (m3) m3 7,521 14,978 19,139 19,532 17,350 18,011 19,143 18,985 23,168 23,529 24,225 26,607 28,482 29,137 29,370 29,959 27,706 28,312 28,187 28,135
Trans Pastefill m3 - - - - 4,109 12,374 12,058 8,927 3,722 1,336 4,308 11,147 10,377 8,676 12,330 5,801 16,545 9,435 - 5,218
Trans Rockfill m3 - - 3,590 - 3,757 - - 3,346 8,937 9,236 4,764 - - 3,743 2,737 5,991 - 4,191 12,121 9,445
Others
Vent Alimak Project m 25 92 210 53
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 309
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
PFS Schedule Unit
2025 2026 2027 2028 2029 2030 2031 2032 Totals
Summary: 1/1/2025 1/1/2026 1/1/2027 1/1/2028 1/1/2029 1/1/2030 1/1/2031 1/1/2032
Development Ore Breakout:
All Development Ore Tonnes (t) t - - - - - - - 147,572
All Dev Ore Au (g/t) g/t - - - - - - - 3.68
All Dev Ore Ag (g/t) g/t - - - - - - - 10.75
Veins Development Ore Tonnes (t) t - - - - - - - 62,456
Veins Dev Ore Au (g/t) g/t - - - - - - - 3.88
Veins Dev Ore Ag (g/t) g/t - - - - - - - 14.34
Trans Development Ore Tonnes (t) t - - - - - - - 85,116
Trans Dev Ore Au (g/t) g/t - - - - - - - 3.53
Trans Dev Ore Ag (g/t) g/t - - - - - - 8.12
Lateral Development Breakout
Veins Development -DEV-2.2x2.2 (m) m - - - - - - - 16,559
Trans Ramp Development -RMP-3.5x3.5 (m) m - - - - - - - 966
Veins Level -LVL-2.2x2.2 (m) m - - - - - - - 274
Trans Level Access -ACC-3.5x3.5 (m) m - - - - - - - 1,494
Trans Ore Xcut -XCT2-4x3.5 (m) m - - - - - - - 2,160
Trans Waste Xcut -XCT1-3x3 (m) m - - - - - - - 2,579
Ventilation Drift -VNT-3.5x3 (m) m - - - - - - - 53
Vertical Development Breakout:
Apique Development (m) m - - - - - - 159
Ventilation Raise -RAR-3x3 (m) m - - - - - - 67
Backfill Breakout:
Veins Backfill (m3) m3 91,691 106,867 93,894 83,156 79,052 79,898 129,203 29,531 1,154,769
Trans Pastefill m3 33,698 33,201 28,972 25,839 31,331 34,946 4,592 - 318,941
Trans Rockfill m3 11,771 12,024 22,650 11,254 24,186 25,959 14,517 - 194,218
Others:
Vent Alimak Project m
Source: SRK, 2020 Note: Numbers may not sum due to rounding.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 310
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SRK, 2020
Figure 16-29: Production Schedule Colored by Time Period
16.4.4 Mining Operations
Stoping
CAF stopes are mined using stopers and jacklegs. Once the level access is driven, raises (tambores)
are driven on either side of the stope. A sublevel is driven laterally and used as a drilling platform,
where 1.7 m to 2.3 m slices are drilled up into the back. After blasting and bolting, the stope is mucked
out either using slushers for higher grade stopes or skid steer loaders/microscoops for lower grade
blocks. Once the stope is mucked out, concrete barricades are built on either side of the stope and
filled with unconsolidated hydraulic fill.
• Drilling and blasting
• Mucking or slushing to a raise and removing the mineralized material from the raise and
hauling by train along the production level
• Sand backfill
• Repeat the cycle on top of the sandfill
In stopes where the back is fractured and not amenable to vertical drilling and blasting, the slice is
mined horizontally along strike.
Transition stopes are 15 m by 15 m and will be mined using a modified longhole stoping method in
two sections. The first section is from Level 21 up to Level 20 and the second section is from Level 22
to Level 21 with a pillar in between. The Transition will be mined in a primary-secondary sequence.
The stope is drilled from a top access using a jumbo fitted with an adapter for long hole drilling. A slot
will first be drilled and blasted, before the rest of the stope is slashed into the slot. The material will be
mucked from the bottom using a remote scoop. The primary stopes will be backfilled using pastefill
and the secondary stopes are filled with waste rock.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 311
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Development
Development in the Veins is completed using jacklegs. Level accesses are 2.2 m by 2.2 m, sublevels
vary depending on the width of the vein. The apiques will be extended down to level 22.
A 3.5 m by 3.5 m ramp is used to access the Transition stopes. The level access and transverse drifts
are the same size as the ramp. Development for the Transition zone is done using a jumbo.
Haulage
All is hauled using rail haulage on the level. The main haulage level is Level 18. Material from Levels
16 and 17 is brought to Level 18 via an orepass. Material on Level 19 is hauled up using the incline
and material below Level 19 is brought up via the shaft hoist.
10 tonne trucks will be used in the transition zone to haul ore to the orepass, which is then loaded to
rail carts and brought to the apiques.
Backfilling
Backfilling is completed using unconsolidated hydraulic backfill from the plant. Currently,
approximately 55% of the mill tailings are returned to the mine as backfill. There are four tailings
pipelines going underground to different levels with each pipeline having a capacity of 290 m3/d. The
plant’s backfill capacity is 715 m3/d. One limitation of the backfill system is the lack of a surge tank, so
there is limited catch up possibility should a delay occur. Waste rock generated underground that is
not hauled out is used as backfill. The hydraulic backfill system is shown in Figure 16-30.
A paste plant is planned to be installed near the existing plant to provide cemented pastefill to the
Transition Zone. Engineering work is being done by Lara Consulting and is expected to be complete
by October 2020 and construction will begin thereafter.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 312
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: CGM, 2019
Figure 16-30: Marmato Hydraulic Backfill System
16.4.5 Ventilation
As the mining operations are below 1,500 masl, Colombian regulations state that the minimum airflow
for diesel equipment is 4 m3/min per horsepower (hp) which relates to 0.09 m3/s per kW of engine
power to ensure gaseous and aerosol contaminants from diesel equipment are sufficiently diluted
which is a typical minimum design value for many ventilation systems (although the typical dilution
rates are usually presented as between 0.06 m3/s per kW and 0.08 m3/s per kW). The value of 0.09
m3/s per kW has been used to determine the airflow in the ramps/haulage routes, and on the mining
levels where diesel equipment is used.
Colombian regulations also state that the minimum airflow per worker is at least 0.05 m3/s. This airflow
requirement is typically used in areas without diesel equipment, as the requirements for ventilating
diesel equipment will far exceed this value.
The ventilation system for the upper area draws approximately 139,000 cubic feet per minute (kCFM)
fresh air in from Level 18 and Level 17. Approximately 96 kCFM is exhausted from the portals on Level
16. There is a 43 kCFM difference in the intake and exhaust which CGM attributes to leakage in the
system and the artisanal mining above. For levels below 18, including Level 21, the fresh air is pulled
down the apiques using 30 hp fans onto the level. Secondary ventilation is provided by 15 hp fans and
vent tubing to the face. The flow in the level is mainly controlled by vent doors. In each level, the air
flows west to an exhaust raise, where the air goes up to Level 16. A portion of Level 21 will be an
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 313
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
exhaust collection area (Figure 16-31) that will draw exhaust toward the new exhaust raise and then
to the surface. Figure 16-32 shows the new ventilation system. A new exhaust fan system would be
installed within either the surface exhaust portal drift or on Level 21. The location of the exhaust fan
system would depend on the location of the electrical feed, and the competency of the rock in the area
of the installation.
Source: SRK, 2020
Figure 16-31: Level 21 Exhaust Collection Area
Source: SRK, 2020
Figure 16-32: New Exhaust System
16.4.6 Mine Services
Pumping
The mine has an operating system of ditches, sumps, and small pumps that control water on the
individual mine level and pump water to the main pump system.
The main pumping system used in the mine is a staged system of 10,000 to 15,000 liter sumps/tanks
and pumps that move water from lowest levels of the mine at Level 21 up to the mine portal where the
water is used in the mine processing plant. On Level 21, at the bottom of the currently developed mine,
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 314
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
there is a storage tank with three Krebs pumps that pump through two-4 inch and one-6 inch pipelines
up to Level 20. On Level 20, another tank and pump system with three pumps moves the water to
Level 19 to a concrete lined sump with two Goulds 5500 slurry pumps that pump through 4 inch
pipelines to the portal Level 18 to the process plant water tank. There is redundancy built into the
system with extra pumps on Level 19 and additional locations to place pumps on Level 20. The pump
system handles on average 37 L/s with a range from 26.8 L/s to 46.4 L/ s.
Electrical Supply
The existing project electrical system includes an 8.1 MVA main project substation with six
transformers that provide power to the mine and mill. The mine system power is provided at 33 kV
through transformers that transform power to feed the mine surface and underground facilities. The
three mine related transformers and loads they feed are summarized as follows:
• Transformer 1 (2,000 KVA) steps the 33kV power down to 13.2kV and feeds the three mine
substations that in turn feed the compressors, pumps and offices/shops at 440 VAC
• Transformer 2 (2,000 KVA) feeds the mine at 13.2kV through three separate mine
transformers that in turn feed the various mine levels, hoists, pumps, and mine equipment.
The equipment operates on 440 VAC
• Transformer 4 (1,250 KVA) and 5 (630 KVA) feed two compressors each at 440 VAC
The largest loads at the mine are the compressors, pumps, and hoists which account for approximately
65% percent of the mine load.
Health and Safety
The mine has a mine phone system and emergency egress is provided through stairs in the shaft
declines and a series of ladders to the surface portal level. The mine has a health and safety response
plan and miner safety training sessions for instruction on proper work procedures and safe work
activities.
Manpower
Currently there are 1,158 personnel working at the site; this includes underground staff, process plant
staff and other support staff. The mining staff is approximately 67% of the total staffing. CGM projects
an increase in manpower primarily in the mine underground operations over the next five years (Table
16-14).
Table 16-14: Manpower by Department
Department 2019 2020 2021 2022 2023
Underground Operations 777 868 890 910 910
Process Plant 34 34 34 34 34
Support 217 217 217 217 217
Administration 59 59 59 59 59
Others 71 71 71 71 75
Total 1158 1249 1271 1291 1295
Source: CGM, 2019
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 315
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Equipment
The mine utilizes a large number of jackleg drills and small electric and air operated equipment. There
are also small diesel microscoops and skid steer loaders. The mine is adding additional small drills
and microscoops in the future.
Development and production of the Transition Zone will be performed by contractors. Jumbos, LHDs
and trucks will be used in the Transition.
Table 16-15 shows the current equipment list as provided by CGM.
Table 16-15: Marmato Equipment List
Equipment Amount
Skid Steer Loaders 27 Jacklegs/Stopers 313 Microscoops 6 Locomotives 27 Mine Pumps 18 Hydraulic Fill Pump 18 Winches 5 Slushers 91 Fans 83 Railcars 215 Compressors 9 Pumps 33 Transformers 12 Electric Grid 6 Jumbo T1D 2 LHD ST2G 2 10t Truck 1
Total Equipment 868
Note: Some equipment is owned by contractors Source: CGM, 2020
16.4.7 Recommendations
SRK notes the following recommendations and opportunities for the UZ mine.
• The UZ mine is currently achieving mined grades that are lower than the grades predicted by
the model. This is due to the mining of veinlets and disseminated material instead of only the
vein. There are on average 50 to 60 panels in production at one time across six levels, but
only one geologist for every two levels. In SRK’s opinion, there are not enough geologists to
mark the face for development or production. Additionally, the turnaround time for assays has
been three to four days, which does not give the geologist time to make decisions on the
heading. The lab has recently moved to operating three shifts per day in an effort to reduce
the turnaround time and CGM has stated they are planning some upgrades to the lab. SRK
recommends that CGM prioritize grade control and mining discipline to improve performance
with regard to mined grades.
• Modified longhole stoping is a new mining method for the site. SRK recommends using a 3D
cavity scanning system to survey the completed Transition stopes. This will allow the site to
evaluate how closely the mined stope shapes align with the planned stope shapes, which is
information that necessary to complete meaningful stope reconciliations. 3D scans can also
be used in the veins for better grade control.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 316
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
• An opportunity to improve the current planning process is to use 3D modelling software and
block models. This will allow planners to identify additional veins in 3D space and will facilitate
reconciliation. SRK notes that CGM is in the process of transitioning to 3D modeling software.
Using a 3D Gantt type scheduling software to generate a mine plan will more accurately show
periods of potential higher and lower grade.
16.5 MDZ Mining
The MDZ area is currently in the exploration phase and has not been developed. Mineralization is
located approximately 600 to 1,200 m below the surface (480 masl to 1,100 masl). Based on
geomechanical information and mineralization geometry, an underground longhole stoping method
(LHS) is suitable for the deposit. Cut-and-fill vein mining will continue above the MDZ area, but it is not
a method that will be used in the MDZ area.
The MDZ deposit will be mined in blocks where mining within a block occurs from bottom to top with
the use of paste backfill. Sill pillars are left in situ between blocks. The backfill will have sufficient
strength to allow for mining adjacent to filled stopes without the need for dip pillars. The stopes will be
10 m wide and stope length will vary based on mineralization grade. A spacing of 30 m between levels
has been used. In the top mining block, a higher grade core is extracted first, mined from bottom to
top. Subsequently, additional stopes are mined from the bottom of the block up, mining adjacent to
(but not underneath) backfilled stopes.
The mine will be accessed by a decline drift with mineralization transported from stopes via truck to
an underground crusher and then to surface by conveyor. Internal intake and exhaust raises will be
developed using raisebore machines and air will flow into dedicated intake and exhaust ventilation
drifts to surface. A new 4,000 t/d process facility using gravity concentration and cyanidation of the
gravity tailings will be constructed to process material from the MDZ. In addition, a new DSTF will be
constructed to receive approximately 55% of the total LoM tailings from the plant. The other 45% of
tailings will go back underground into the mine as cemented paste backfill.
16.5.1 Stope Optimization
Based on geomechanical information and mineralization geometry an underground LHS method is
suitable for the deposit. Paste backfill will be used to allow for a high recovery of economic material.
Stopes are sized to be large enough to take advantage of bulk mining methods, yet small enough to
minimize dilution. A variety of stope sizes were evaluated using stope optimizer software to make this
determination.
Figure 16-33 shows the resource block model blocks above an Au CoG grade of 1.61 g/t which have
been classified as Measured and Indicated. There are pockets of higher grade material, particularly in
the upper portion of the deposit. Generally, the deposit is approximately 500 m along strike and 125
m in width. This model formed the basis of the stope design.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 317
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SRK, 2020
Figure 16-33: Resource Model – AU blocks (g/t) above Mining CoG (Looking North)
Stope optimization within Vulcan software was used to determine potentially economically minable
material. Stope walls were vertical and wall dilution was not applied at the optimization stage, however
the CoG used for design was elevated to account for the expected dilution.
Optimizations were run using various CoG to identify higher grade mining areas and understand the
sensitivity of the deposit to CoG. Results show large quantities of lower grade material where a small
increase/decrease in CoG has a material impact on the material available for design. Figure 16-34 and
Table 16-16 shows stope optimization results for various cut-off grades using a stope size of 10 m
wide by 30 m high.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 318
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SRK
Figure 16-34: Undiluted Stope Optimization Results for Varying Cut-off Grades
Table 16-16: Undiluted Stope Optimization Results for Varying Cut-off Grades
Cutoff (g/t)
Material Category
Au (g/t)
Ag (g/t)
Tonnes (kt)
Contained Au (Oz)
Contained Ag (Oz)
1.00 MI 2.04 3.16 37,173 2,441,304 3,771,621
1.50 MI 2.68 3.73 21,048 1,813,107 2,525,177
1.75 MI 2.89 3.93 17,572 1,632,289 2,218,412
2.00 MI 3.09 4.12 14,682 1,457,334 1,945,971
2.25 MI 3.28 4.29 12,217 1,288,234 1,686,879
2.50 MI 3.48 4.47 9,977 1,115,480 1,435,249
3.00 MI 3.94 4.85 6,051 765,529 944,312
3.50 MI 4.53 5.24 3,190 464,441 537,581
4.00 MI 5.15 5.67 1,732 286,498 315,559
4.50 MI 5.89 6.07 903 171,151 176,388
5.00 MI 6.67 6.46 509 109,229 105,757
Source: SRK
Stope optimization results as discussed above are undiluted.
Stope optimization results using a 1.75 g/t Au cutoff were targeted for design work. The reserves CoG
is 1.61 g/t. As stope optimization results did not consider dilution, 8% dilution was factored into the
optimization cutoff which results in a stope optimization cutoff of 1.75 g/t Au (i.e. A 1.7 g/t stope, diluted
by 8%, will give the reserves CoG of 1.61 g/t). Higher grade stopes using 3.5 g/t stope optimization
results were designed as a first pass, with the lower grade stopes added as separate stopes. This
allowed for scheduling of higher grade stopes first.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 319
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
16.5.2 Mine Design
Stopes are 10 m wide and 30 m high with varying length. Each stope has a 4.5 m by 4.5 m access
located at the bottom of the stope as shown in Figure 16-35. Top accesses are available on most
levels to give access to stopes on the next level and to allow for backfilling. For upper most stopes in
a block or where there is no mining above, it is assumed a hole can be drilled from adjacent
development into the stope for backfilling purposes. The stopes are drilled top down and rings are
blasted from the end of a stope toward the access. The blasted material is remotely mucked from the
stope access. A typical level is made up of approximately 40 stopes along strike.
Source: SRK
Figure 16-35: Stope Cross Section
A primary/secondary stoping sequence will be used, where on any given level, primary stopes must
be separated by a secondary stope. Extraction of the secondary stope can only occur after the two
immediately adjacent primary stopes have been mined, backfilled, and have had time to cure.
Backfilling will be an integral part of the LHS mining cycle, and a seven day cure time is planned.
The stope accesses are connected to a level access which is offset approximately 20 m away from
the end of the stopes. Each stope access typically connects to the level access except in cases where
stopes are small and long development is required to reach the stope. In those instances, a connection
from an adjacent stope is included in the design. This minimizes the amount of development; however,
it also limits the sequencing order.
The level accesses connect to the main ramp which is offset at least 75 m from stoping into the footwall.
The offset may be optimized during the FS, after numerical modelling. On the northeast side of each
level, the level access connects to an intake air ventilation raise and on the southeast side connects
to an exhaust air raise. Figure 16-36 shows a typical level section.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 320
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SRK, 2020
Figure 16-36: Typical Level Section
Access and infrastructure development underground was designed to support the mining method and
sized based on mining equipment and production rate requirements. The crusher area was designed
by Ausenco with SRK orienting the various specified sized openings in the design. Figure 16-37 shows
the location of the bin/crusher and their layouts. Trucks will dump into the crusher at an elevation of
790 m. Material will go through the bin into the crusher and then be conveyed out of the mine.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 321
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SRK, 2020
Figure 16-37: MDZ Mine Design (Rotated View Looking Southwest)
The decline from the plant site will be the main access to the MDZ for men/materials. This decline is
5.5 m wide by 5.6 m high, excavated at a grade of 17%. A schematic tunnel layout showing conveyor,
services, etc. in the decline is shown in Figure 16-38. There are two ventilation drifts (5 m by 5 m) near
the current UZ process facility. One of these ventilation drifts connects to the main ramp system and
will serve as secondary egress.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 322
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: Ausenco, 2020
Figure 16-38: MDZ Main Decline Cross Section
Tonnages/grades for the mine design were calculated based on the resource block model. Dilution
and recovery were added to the designed tonnage to account for unplanned stope dilution and
unrecoverable material within the stope as discussed in Section 15.
The MDZ design resulted in 14.6 Mt at an average grade of 2.85 g/t Au and 3.84 g/t Ag and is shown
in Figure 16-39. Figure 16-40 shows the stopes colored by Au grade. Table 16-17 summarizes the
mine design by activity type.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 323
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SRK, 2020
Figure 16-39: MDZ Mine Design (Rotated View Looking Southwest)
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 324
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SRK, 2020
Figure 16-40: MDZ Mine Design, Colored by Au Grade
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 325
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 16-17: MDZ Mine Design Summary – by Activity Type
Total Tonnes Moved (t) 16,362,907
Ore Breakout
Development Ore Tonnes (t) 1,044,054
Stope Ore Tonnes (t) 13,511,892
Development Breakout
Main Conveyor Ramp -RMC-5.5x5.6 (m) 1,680
Main Truck Ramp-RMT-5.5x5.5 (m) 3,650
Drift-FWA-5x5 (m) 7,116
Ventilation Drifts-VMR-5x5 (m) 2,202
Ventilation Connections-VCX-4.5x4.5 (m) 1,032
Stope Drifts Ore-DFA-4.5x4.5 (m) 19,285
Stope Drifts Waste-DFA-4.5x4.5 (m) 11,496
Vertical & Other Development Breakout
Raisebore 5m dia-RS1 (m) 437
Raisebore 5m dia-RS1 (count) 2
Raisebore 4.5m dia-RS2 (m) 403
Raisebore 4.5m dia-RS2 (count) 2
Blasted Raise-BRS-3x3 (m) 87
Blasted Raise-BRS-3x3 (count) 3
Bulk Excavation (m3) 16,570
Source: SRK, 2020
There are several known faults in the area, they range from several cm in width to several m in width.
The Sur and Ines faults impact the MDZ development design in several locations as shown in Figure
16-41. The development design is oriented to cross the faults as perpendicularly as possible. As faults
become more understood, appropriate measures should be taken to minimize the risk to the design in
terms of development rate and costs.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 326
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SRK, 2020
Figure 16-41: MDZ Design with Sur and Ines Faults (Rotated View - Looking Northwest)
16.5.3 Production Schedule
The production schedule is based on the mine design and reserves discussed in previous sections.
Productivities were developed from first principles. Input from mining contractors, blasting suppliers
and equipment vendors was considered for key parameters such as drilling penetration rates, blast
hole size and spacing, explosives loading time, bolt and mesh installation time, etc. The rates
developed from first principles were adjusted based on benchmarking and the experience and
judgment of SRK.
The productivity rates used for mine scheduling are shown in Table 16-18, followed by a description
of the general and activity-specific parameters upon which the productivity rates are based.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 327
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 16-18: Productivity Rates
Activity Type Heading Type Dimensions Rate (1)
Drifting
Main Conveyor Ramp Single 5.5 m x 5.6 m 4.3 m/d
Main Truck Ramp Single 5.5 m x 5.5 m 4.3 m/d
Footwall Accesses Multiple 5.0 m x 5.0 m 6.9 m/d
Ventilation Drifts Single 5.0 m x 5.0 m 5.2 m/d
Ventilation Connections Multiple 4.5 m x 4.5 m 6.6 m/d
Top/bottom stope accesses Multiple 4.5 m x4.5 m 6.6 m/d
Stoping Stoping (2) - 2,1421 t/d
Vertical Development
Ventilation Raise Upper Block 5.0 m diameter 2.8 m/d
Ventilation Raise Lower Block 4.5 m diameter 2.8 m/d
Blasted Raise with escape way 3.0 m x 3.0 m 8.4 m/d
Other Bulk Excavation Various 100 m3/d
Backfill Paste Backfill (3) - 123 m3/hr
(1) All rates are per face. Multiple areas/faces are mined together to generate the production schedule (2) Includes drilling, blasting, and mucking for the slot and the stope. (3) Includes pour time and 3 days of lag (for pouring plug, waiting 3 days for cure, and pouring remainder) Source: SRK, 2020
General schedule parameters applicable to all underground mining activities are presented in
Table 16-19.
Table 16-19: Schedule Parameters for Underground Mining
Schedule Parameters Units Value
Annual mining days(1) days/year 365 Mining days per week days/week 7 Shifts per day shifts/day 3 Scheduled shift length hrs/shift 8
Scheduled Deductions
Shift Change hrs/shift 0.25 Travel Time hrs/shift 0.42 Equipment Inspection hrs/shift 0.25 Lunch Break hrs/shift 0.50 Equipment Parking/Reporting hrs/shift 0.50 Total scheduled deductions hrs/shift 1.92 Operating time (scheduled shift length less scheduled deductions) hrs/shift 6.08 Effective time (operating time reduced to a 50-minute hour, i.e., multiplied by 83.3%) hrs/shift 5.07
Source: SRK, 2020 (1) Actual operational mining days are 360. For simplicity the schedule has been completed assuming 365 with pro-rated productivity rates.
Key assumptions regarding ore and waste material characteristics are detailed in Table 16-20.
Table 16-20: Material Characteristics for Ore and Waste
Characteristic Units Value
In situ density t/m3 2.70
Swell % 40
Loose density t/m3 1.93
Source: SRK, 2020
For the purposes of developing productivity estimates, the ground support requirements detailed in
Table 16-5 were used.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 328
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Drifts
The main ramps systems will be developed with a twin-boom jumbo drilling 41 mm diameter blast
holes and 102 mm relief holes. All jumbo holes will be drilled 4.24 m in length, which allows for an
effective advance rate of 4.02 m per round. The drill pattern provides for 51 charged blast holes and
two uncharged relief holes. Drilling times were calculated based on average penetration rates of 1.4
m/min for 41 mm charged holes and 0.4 m/min for 102 mm reamed relief holes. A 10% redrill factor
was assumed.
Use of a bulk emulsion explosive was assumed at a powder factor of 1.08 kg/t. The blasting cycle time
considered mobilization, charging and tying in of holes, clean-up, and demobilization.
Loading will be performed with a 7.3 m3 (17 t) LHD that will transport blasted rock to remuck bays that
are spaced 250 m apart. Load, maneuver and dump times were considered and a 85% bucket fill
factor was assumed. The time associated with loading haul trucks at the remuck bays was accounted
for as an activity that is separate from the main ramp development.
During the pre-production period and for a large portion of the mine life, development waste rock that
is placed in a remuck bay will be loaded into trucks and hauled to the surface for use in construction
of the DSTF. After the DSTF is constructed, development waste will be placed in empty secondary
stopes.
Ground support will be installed as specified in Table 16-5. Time allowances have been included for
mobilization and setup, scaling, bolting/meshing/shotcreting as required, and demobilization.
Utility installation includes piping lines, ventilation tube, electrical cable, messenger cable, and leaky
feeder. Piping, ventilation and electrical utilities will be installed at the end of every other round.
Table 16-21 shows the development rates for the three main ramp types, which are all considered
long term development openings.
Table 16-21: Main Ramp Average Development Rate – Long Term Development Openings
Task Units Conveyor Ramp
(5.5 x 5.6 m) Truck Ramp (5.5 x 5.5 m)
Ventilation Ramp (5x5 m)
Drilling hrs/round 2.67 2.67 2.77
Blasting hrs/round 3.03 3.03 3.33
Mucking hrs/round 2.90 2.85 2.62
Ground Support hrs/round 6.34 5.70 3.49
Utilities/Services hrs/round 1.71 2.11 1.19
Blasting Clear Time hrs/round 0.5 0.5 0.5
Total Cycle Time hrs/round 17.14 16.87 13.90
Total Advance Rate m/day 4.28 4.35 5.28
Source: SRK, 2020
The footwall access, medium term development openings, will be developed much in the same way
as the long-term openings. Table 16-22 shows the development rates for these.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 329
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 16-22: Footwall Access Development Rate – Medium Term Openings*
Task Units Footwall Access (5x5 m) Ventilation Connection Drifts (4.5x4.5 m)
Drilling hrs/round 3.17 3.23
Blasting hrs/round 3.67 3.86
Mucking hrs/round 2.50 2.57
Ground Support hrs/round 3.24 3.47
Utilities/Services hrs/round 1.26 0.78
Blasting Clear Time hrs/round 0.5 0.5
Total Cycle Time hrs/round 14.33 14.41
Total Advance Rate m/day 5.12 5.10
Source: SRK, 2020 *Advance shown is for a single heading environment. Multiple heading environment using the same assumptions gives a rate of 6.9 m/d for footwall access and 6.6 m/d for ventilation connections.
The drift access openings will be developed much in the same way as the long-term openings.
Table 16-23 shows the development rates for these openings.
Table 16-23: Drift Access Development Rate – Short Term Openings*
Task Units Drift Accesses (4.5x4.5 m)
Drilling hrs/round 3.23
Blasting hrs/round 3.86
Mucking hrs/round 2.57
Ground Support hrs/round 3.51
Utilities/Services hrs/round 1.26
Blasting Clear Time hrs/round 0.5
Total Cycle Time hrs/round 14.94
Total Advance Rate m/day 4.92
Source: SRK, 2020 *Advance shown is for a single heading environment. Multiple heading environment using the same assumptions gives a rate of 6.6 m/d.
Stopes
After top and bottom stope development drifts are established, a slot will be developed at the far end
of the stope. The slot consists of a conventionally blasted drop raise and 28 fan-drilled holes that will
be slashed into the void that is created by the drop raise. Including the fan-drilled holes, the overall
dimensions of the slot will be 15 m wide by 6 m long by 25 m high.
All blasthole drilling for the slot will be at a diameter of 114 mm (4.5 inches) using an in-the-hole (ITH)
drill. A total of 50 holes will be required for the slot (22 holes for the drop raise and 28 holes for
slashing). The estimated penetration rate for the ITH drill is 0.75 meters per minute (m/min) and the
total drilling requirement is 1,066 m (including 10% re-drill).
Stopes will be 30 m in height by 10 m in width and will have varying lengths. An ITH production drill
will be used to fan drill the stope from the upper access drift. Blast holes will be 114 mm (4.5 inches)
in diameter and the estimated drill penetration rate is 0.75 m/min. The total drilling requirement is 206
m per ring (including 10% redrill) and the ore blasted per ring is 2,226 t.
Stope blasting will average 1.8 rings per day, the number of which will be dictated by the length of the
stope. Each three-ring blast will have a total of 39 charged holes (13 holes per ring). A bulk emulsion
product will be used, and the powder factor will be 0.34 kg/t. The estimated blasting cycle time includes
travel/set up, charging and tying in of holes, clean up, and demobilization.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 330
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Stope ore will be mucked with a 7.3 m3 (17 t) LHD that will transport blasted ore to re-muck bays that
will be located, on average, 135 m from the stope. Load, maneuver and dump times were considered
and an 85% bucket fill factor was assumed. Ore that is placed in a re-muck bay will be loaded into
trucks and hauled to the grizzlies feeding the underground material handling system; however, the
time associated with loading haul trucks is accounted for as a separate activity.
As shown in Table 16-24, the stope production rate is 2,142 t/d.
Table 16-24: Stope Production Rate
Task Units Slot Stope Total
Drilling hrs 44.6 11.2 55.8
Blasting hrs 9.6 13.2 22.8
Mucking hrs 22.8 90.0 112.8
Total Cycle Time hrs 77.0 114.4 191.4
Days days 3.2 4.8 8.0
Total Production Rate t/d 1,177 2,694 2,142
Source: SRK, 2020
Raisebored Raises
Two 5 m diameter intake/exhaust ventilation raises will be raisebored early in the mine life. One raise
is 237 m and the second is 200 m. The raisebore average advance rate is 2.8 m/d. The rate includes
drilling the pilot hole and reaming the vent raise. Loading will be performed with a 7.3 m3 (17 t) LHD
that will transport cuttings to a re-muck bay that will be located 75 m from the bottom of the raise. Load,
maneuver and dump times were considered, and an 85% bucket fill factor was assumed. Raisebore
cuttings that are placed in a re-muck bay will be loaded into trucks and hauled to the surface during
preproduction. Two additional 4.5 m raises will be needed later in the mine life. The same productivities
are assumed with the same material handling scheme.
Drop Raise with Escapeway
The ventilation connections will be 3 m wide by 3 m long by 30 m high. The advance rate is 8.5 m/day.
All blast hole drilling for the ventilation connections will be at a diameter of 114 mm (4.5 inches) using
an ITH drill. A total of 22 holes will be required for the drop raise (16 charged blast holes and six
uncharged relief holes). The estimated penetration rate for the ITH drill is 0.75 m per minute and the
total drilling requirement is 605 m (including 10% re-drill).
The drop raise will be removed in a series of three blasts using a bulk emulsion product. The first two
blasts will remove the bottom 13 m of the drop raise. The third and final blast will remove the remaining
7.5 m at the top of the drop raise. The blasting cycle time includes travel/set up time, charging and
tying in of holes, clean up, and demobilization.
Development and Production Schedule
The production and development schedule were completed using iGantt software. The production
schedule is based on the rate assumptions shown Table 16-25.
A delay of seven days was used prior to driving on paste fill or mining adjacent to a paste filled stope
to account for curing time. A 45 day delay to install manways in ventilation raises was also assumed.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 331
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
The mining operation schedule is based on 365 days/year, seven days/week, with three eight hour
shifts each day. A production rate of 4,000 t/d (1.46 Mt/yr) was targeted with ramp-up to full production
as quickly as possible. The schedule timeframe is quarterly for four years and annually for the
remainder of the mine life.
Decline activities begin in October 2021 with mine development through Q4 2023. Stoping begins in
Q4 of 2024, with a one year ramp up period until the mine and plant are operating at full capacity.
Table 16-25 summarizes the MDZ production schedule.
Table 16-25: MDZ Production Schedule
Period Ore (t/d)
Ore Tonnes
(kt)
Ore Au
(g/t)
Ore Ag
(g/t) Au Oz Ag Oz
Waste Tonnes
(kt)
Development Length (m)
2021
Q1
Q2 - - - - - -
Q3 - - - - - -
Q4 - - - - - - 64 874
2022
Q1 - - - - - - 62 855
Q2 - - - - - - 63 865
Q3 - - - - - - 64 888
Q4 - - - - - - 95 1,129
2023
Q1 106 1,332
Q2 107 1,413
Q3 396 36 2.91 4.15 3,412 4,864 58 1,512
Q4 1,876 173 3.14 4.76 17,405 26,421 30 1,822
2024
Q1 2,716 247 3.18 4.57 25,233 36,300 62 1,815
Q2 3,597 327 3.20 4.68 33,718 49,242 36 1,797
Q3 3,997 368 3.01 4.01 35,625 47,357 56 1,833
Q4 4,005 368 3.24 4.52 38,426 53,587 43 1,820
2025 4,004 1,462 3.27 4.47 153,817 210,133 150 5,762
2026 4,002 1,461 3.41 4.85 160,364 227,629 87 2,857
2027 4,003 1,461 2.94 4.54 138,157 213,416 129 3,313
2028 4,003 1,465 2.77 4.04 130,637 190,383 183 3,375
2029 4,003 1,461 2.47 2.87 115,797 134,661 152 4,522
2030 4,001 1,460 2.33 3.11 109,494 146,203 151 4,827
2031 4,000 1,460 2.50 3.01 117,132 141,386 95 3,708
2032 4,000 1,464 2.79 3.22 131,138 151,494 16 1,068
2033 3,678 1,342 2.84 3.85 122,682 166,158 - -
Total - 14,556 2.85 3.84 1,333,037 1,799,234 1,807 47,388
Source: SRK, 2020
Figure 16-42 shows the mine production schedule colored by year.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 332
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SRK, 2020
Figure 16-42: Mine Production Schedule Colored by Year
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 333
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
16.5.4 Mining Operations
Stoping
Stopes will be mined using the longhole open stoping method. Individual stope blocks are designed to
be 10 m wide, up to 30 m long, and will have a transverse orientation. Levels are spaced 30 m apart
and each stope block will have a top and bottom access (4.5 m by 4.5 m flat back drifts).
Stopes will be drilled downward from the top access using 114 mm diameter holes (stope slots and
stope production rings will be drilled with an ITH drill). A bottom up, primary/secondary extraction
sequence will be followed. Primary stopes will be backfilled with high strength paste backfill and
secondary stopes will be backfilled with RoM waste from the underground operation and low strength
paste backfill as needed when waste rock is not available.
Stope extraction will occur in two steps. During the first step, a slot will be mined at the far end the
stope using a drop raise and 28 fan-drilled slash holes. The slot is required to create sufficient void
space for the remainder of the stope to be blasted. During the second step, production rings will be
blasted three rows at a time (13 blastholes per ring) until the stope is completely extracted. The number
of three-row blasts in a given stope will depend on the length of the stope. All blasting will be performed
with bulk emulsion.
Ore will be remotely mucked from the bottom stope access using a 7.3 m3 (17 t) LHD. The LHD will
transport the ore to a re-muck bay to maximize the efficiency of the stope mucking operations. A
second LHD and a fleet of 45 t haul trucks will be used to transport ore from the re-muck bays to the
grizzly feeding the underground material handling system. Multiple re-muck bays will be used on each
level to avoid interference between the stope loader and the haul trucks.
UG Material Handling System
The underground material handling system is designed to size the rock, provide surge and storage
capacity, and be an efficient, automated system for moving the rock to surface via conveyor.
During operations, ore will be brought to the dump point and fed via a rock-breaker protected grizzly
into an infeed ore pass that loads into the crusher station. The ore pass from the grizzly is sized to
hold approximately 2,000 t (approximately ½ half day mill feed). A feeder will load a vibratory grizzly
which will separate fine and coarse sections and feed the coarse (oversize) material into a jaw crusher.
Undersize will be fed to the main transfer conveyor and then onto the main conveyor to surface.
Development
Lateral development includes main conveyor ramp, interlevel truck ramps, ventilation drifts, level
accesses, stope accesses, and short connecting drifts for ventilation. The conveyor ramp system will
be 5.5 m wide by 5.6 m high with an arched back at a maximum 17% gradient. The interlevel truck
ramps will be 5.5 m wide by 5.5 m high with an arched back at a maximum 14% gradient. Level
accesses will be 5 m wide by 5.5 m high with a flat back and will be mined higher at the re-muck bays
to allow the haul trucks to be loaded by the LHD. Stope access drifts will be flat back 4.5 m wide by
4.5 m high.
Interlevel ramps and levels accesses will be located in the footwall and have been designed to avoid
crossing fault zones to the maximum extent possible. Stope accesses are oriented perpendicular to
the strike of the orebody.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 334
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
The lateral development is sized for the operation of the mining equipment fleet that has been selected
for the operation. The development profiles include allowances for ventilation ducting and services.
Conventional drop raising will be used for the two lowest levels to establish ventilation connection and
secondary egress.
Haulage
The mine plan assumes that 7.3 m3 (17 t) LHDs will load 45 t haul trucks from re-muck bays that will
be strategically located throughout the development workings. Ore and waste haulage distances and
cycle times were calculated using the haulage profile module in Vulcan and are based on estimated
underground truck speeds as shown in Table 16-26. The outputs from the Vulcan haulage profile
module are a one-way haulage distance and an average truck cycle time (round trip).
Table 16-26: Truck Hauling Speeds
Road Grade (%) Speed (1) (km/hr)
Loaded
0-2.5 11.0
2.5-5.0 10.5
5.0-7.5 10.3
7.5-10.0 10.2
10.0-12.5 10.1
12.5-15.0 7.4
15.0-20.0 7.4
Empty
0-2.5 11.0
2.5-5.0 10.5
5.0-7.5 10.5
7.5-10.0 10.5
10.0-12.5 10.5
12.5-15.0 9.0
15.0-20.0 7.5
Source: SRK, 2020 (1) Uphill and downhill assumed speeds the same.
The ore haulage distances were evaluated from the mine production schedule. Based on this
evaluation, ore haulage pathways were created to approximate the location of ore development and
stope mining in each time period. Vulcan haulage profile was then used to generate a one-way ore
haulage distance and an average cycle time (round trip) using the speed parameters shown in
Table 16-26.
All waste material mined through the end of 2028 is sent to surface for surface construction purposes.
In 2029, and through the end of the mine life, the availability of mined-out secondary stopes was
evaluated to determine haulage distances for waste material. These waste haulage pathways were
created to approximate the location of development waste mining and waste rock dumping for each
time period. Vulcan haulage profile was then used to generate a one-way waste haulage distance and
an average cycle time (round trip) using the speed parameters shown in Table 16-26.
The average one-way ore haulage distances are approximately 400 m early in the mine life through
2027 and increase to approximately 1,570 m later in the mine life. The LoM average is 732 m. Waste
haulage distances are approximately 2,000 m when hauling material to surface and 800 m thereafter.
At the peak, four haul trucks are required to transport the ore and waste. Figure 16-43 and Figure
16-44 show the haulage distance and cycle time by period. SRK notes the cycle times reflected in this
summary are indicative as there is a fixed component including the loading time, dumping time,
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 335
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
positioning time and additional delays that are included in the productivity and equipment quantity
determinations and not included in the information summarized in these figures.
Source: SRK, 2020
Figure 16-43: Haulage Distance – One Way Length
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 336
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SRK, 2020
Figure 16-44: Haulage Cycle Time - Roundtrip
A small bypass stockpile near the portal is available for short term storage if needed, but there is
limited stockpiling space on surface and as soon as ore material is produced it is expected to be
processed.
Backfilling
The mine production sequence includes the use of cemented paste backfill to fill the voids left by the
stopes to maintain the mine structural integrity. The mine utilizes a high strength backfill paste that has
a 7% cement content in the primary stopes. A lower strength paste with 4% cement is used to backfill
the secondary stopes. Section 18.13 discusses the surface plant and system to move the pastefill
underground to the stopes. A backfill operations crew installs barricades in the lower access drift to
the stopes, extends the pipe delivery system in the upper access drift into the stopes, and monitors
the backfill as the stope fills. Once the stope is filled the backfill is allowed to cure (seven days) to
design strength of over 1 MPa prior to blasting on the adjoining stope.
The LoM backfill breakdown by volume and type is shown in Table 16-27.
Table 16-27: Backfill Volume Summary – By Type
Backfill Type Volume (m3)
Total Backfill 5,429,425
Low Strength Backfill (Waste rock or 4% Cement Pastefill) 1,722,163
High Strength Backfill (7% Cement Pastefill) 3,707,262
Source: SRK, 2020
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 337
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Ground Support
The current knowledge of the geotechnical characteristics indicates that ground support will be
required in the ramps, in areas of faulting and in primary access drifts as well as the crusher and shop
areas. The stope access drifts will require minimum ground support except at brows of the stopes. The
ground support plan includes use of grouted rebar and split set style bolts as a standard. The bolting
will be supplemented with wire mesh, shotcrete and additional support where required. The plan
includes allowances for areas of full shotcrete, that will be used in longer term active mine areas. A
bolter will be utilized as normal practice and shotcrete equipment are included in the estimate.
Additionally, a cable bolter has been included in the equipment fleet to allow for cable bolting if
necessary, in intersections and at the stope brows.
Grade Control
As part of the routine mining sequence, CGM will conduct infill drilling on routine sampling grids, and
will execute a grade control program to monitor the mining production. The infill drilling will be
conducted from established drilling stations on each level, with underground diamond drilling using
NQ core diameter drilled across the width of the known mineralization. Drilling will be logged for basic
geological and geotechnical parameters and sampled using the current established protocols by CGM.
SRK envisions up to three holes in a fan pattern can be drilled from each station to gain knowledge for
levels above and below as required.
The aim of the grade control program is to deliver the most economic material to the mill via accurate
definition of “ore” and waste contacts. The basis of a successful program in an underground
environment will be completed via detailed geological mapping and grade sampling ahead of the
mining. Grade control strategy is related to mining method and orebody type. For underground
operations sampling methods include chip, channel and panel samples, grab/muck pile samples, and
drill-based samples.
The aim of the program will be to identify variations in dip, strike and width, impact on local scale from
faulting effects, and grade continuity/type. Variations in geometry at the edge of the mineralization will
require geological understanding to ensure optimum grade, minimal dilution and maximum mining
recovery.
The current proposed mining methods involve development cross-cuts at regular intervals across the
width of the mineralization at the top and bottom of a stope prior to mining. Samples should be taken
across the full width of the exposed mineralization via cut channel sampling (using the CGM
exploration protocols) with sufficient volume to ensure accurate assay. The aim of the sampling should
be to achieve a sample weight the equivalent of at minimum half NQ core for the sampling interval.
The samples should be logged geologically marking the width of the mineralization and any hanging
wall or footwall mineralization. The samples should be processed at an onsite facility to enable quick
turnaround, with sufficient QA/QC samples inserted to monitor the quality of the laboratory and routine
external laboratory checks to test for bias. Further to the channel sampling programs the mine
geologist will perform daily mapping, as well as define the ore/waste contact for the mining teams. The
mapping should be incorporated into a digital format to further improve the geological model and
enable the development of short term estimation.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 338
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Additionally, blasted material will be available for grab sampling to test grades, which should then be
input to a production database and be used to confirm head-grades and for reconciliation purposes.
Note that grab sampling can result in selection bias if not conducted following a routine defined
protocol.
SRK recommends that CGM create a series of protocols to cover all grade control tasks from mapping
to sampling and integration with the database. The local sampling should be used in the generation of
a short term grade estimation model for use in short term planning. The use of short-term models will
also aid CGM in the ability to complete routine reconciliation studies to monitor the performance of the
grade estimation and to identify any potential issues.
On-going quality assurance/quality control monitoring and review will allow protocols and staff to be
updated as required.
16.5.5 Ventilation
The ventilation configuration of the MDZ is considered best practice design as it is configured to
minimize series ventilation. The ventilation design for the project includes dedicated ventilation splits
for fixed facilities so that all air used in the shops and crusher dump areas is transferred directly to
exhaust and away from working levels. The design also provides fresh air to each active mining level.
Five stages of mine development were modeled. Each stage accounting for worst-case operating
conditions. The following sections provide an overview of the MDZ ventilation design.
Ventilation Modeling Criteria
Several factors were considered when determining the airflow requirements for the mine such as gas
dilution, diesel particulates, maintaining minimum air velocities and meeting government regulations.
These factors need to be applied to targeted areas to determine the total mine airflow requirement.
Fixed facilities underground (including shop and crusher area) will also demand a dedicated airflow
split. SRK applied general mine ventilation best practices to the ventilation design and the Colombian
Underground Mining Safety Code (UGMSC) for specific ventilation requirements for the project
location.
Gases can be broken down into three categories; strata gasses, exhaust fumes and blasting fumes.
Harmful strata gases such as methane, carbon dioxide and hydrogen sulfide are not projected to be
encountered at this mine and, therefore, the dilution of strata gasses is not included in this study.
The gaseous components of the equipment exhaust will need to meet the UGMSC. These values are
usually met if the standard airflow criteria are achieved in the individual mining areas for diesel
equipment dilution. However, if the airflow cannot be achieved at the mining areas then the gas
concentration will increase. This acts as an operational limitation and criteria.
Air velocity limitations vary according to airway type. In areas such as return airways and apiques
where personnel are not expected to work, higher velocities are acceptable. Airway velocities typically
used by SRK for various airway types are shown in Table 16-28. Air velocity limits and recommended
values for travelways are established to accommodate work and travel by people and equipment,
optimizing dust entrainment and temperature regulation.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 339
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 16-28: Recommended Maximum Air Velocities for Various Airway Types
Airway Type Air Velocity (m/s) Maximum
Travelways 6
Primary Ventilation Intake and Exhaust Entries 10
Primary Ventilation Raises 20
Ventilation Shaft With Conveyance or Escape 10
Conveyor 3
Source: SRK, 2020
Colombian mining regulations specify a minimum factor of 0.09 m³/s per kW of diesel engine power to
ensure gaseous and aerosol contaminants from diesel equipment are sufficiently diluted. This is the
recommended minimum airflow to ensure sufficient dilution of contaminants with new equipment.
There is no Colombian specific criteria or legislative limit for Diesel Particulate Matter (DPM).
The total number of equipment, motor power and a factor 0.09 m3/s/kW for dilution of diesel was used
to estimate the total required airflow in the mine. An airflow utilization factor was also incorporated.
Leakage through bulkheads and doors must also be accounted for. Airflow through facilities must also
be ventilated, this includes the underground shop and crusher area. The total minimum airflow for the
mine is estimated to be near 340 m3/s from the calculations in Table 16-29. A target airflow was also
developed for each scenario by zone and the maximum number of equipment to be utilized. This is
used as a guideline for the airflow distribution regime.
Table 16-29: Equipment List and Airflow Requirement
Equipment Type Qty Power
(kW)
Diesel Engine
Utilization (%)
Utilized Diesel Power
(kw)
Airflow Requirement
(m3/s)
Sandvik DD422i - Jumbo, 2 boom 3 119 20% 71 6.4
Sandvik DS411 - Mechanical Bolter 4 110 20% 88 7.9
Sandvik DU421 - Production Drill 4 130 20% 104 9.4
Orica MaxiCharger 5344 – Production 2 120 20% 48 4.3
Normet Spraymec 1050 - Shotcrete Sprayer 4 110 20% 88 7.9
Getman A64 HD R60 - Transmixer Truck 2 129 20% 52 4.6
Orica Handiloader 1120 – Development 2 120 20% 48 4.3
Sandvik LH517 - LHD, 7.3 m3, 17 t 4 256 75% 768 69.1
Sandvik LH307 - LHD, 3.7 m3, 7 t 1 160 70% 112 10.1
Sandvik TH545i - Haulage Truck, 45 t 4 450 70% 1260 113.4
CAT UG20M – Grader 1 105 20% 21 1.9
Getman A64 - Scissor Lift 2 129 10% 26 2.3
Getman A64 - Boom Truck 1 129 10% 143 12.9
Getman A64 - Flat Deck Truck 1 129 10% 13 1.2
4x4 Pickup - Light Vehicles 4 75 10% 30 2.7
4x4 Pickup - Light Vehicles 2 75 10% 15 1.4
Getman A64 - Fuel/Lube Truck 2 129 10% 26 2.3
Getman A64 - Personnel Carrier, 16 per. 1 129 10% 13 1.2
Kubota RTV 1120D - Personnel Carrier 3 19 10% 6 0.5
CAT 1255D - Forklift/Telehandler 1 106 10% 11 1.0
Getman A64 - Explosives Truck 2 129 10% 26 2.3
CAT 272D - Skid Steer 2 73 10% 15 1.3
Total Airflow Required for Diesel Dilution (0.09 m3/s/kW)
2982 268.4
Fixed Facilities 40.0
Leakage (10%) 30.8
Total Airflow Requirement 339
Source: SRK, 2020
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 340
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Ventilation Model Development
VentSIM Visual ventilation simulation software was used to generate the ventilation model. The
ventilation design is configured to intake air through the main decline, internal ramps, and intake raises
and exhaust air through the exhaust raise system. This setup allows the mine to use on-shift blasting
since blast fumes will be mainly isolated to each working level and directly exhausted instead of
contaminating the ramp.
There are two mining blocks to be ventilated: an upper block to be mined first and a lower block that
is mined later in the mine life.
• Upper Block- The main decline is to be developed initially to a raise bore to establish flow-
through ventilation in the mine. The conveyor decline is planned to connect at the midway
point in the orebody. From this point the upper block is developed with mining starting at the
bottom of the block (near the conveyor decline) and ending at 940 elevation.
• Lower Block—The lower mining block starts with developing the ramp down to the bottom
(480 elevation) and then mining up from the bottom to the main decline.
The mine is to be ventilated using a push-pull system with a primary fan at the surface exhaust portal
and a smaller fan at the intake portal. The conveyor decline is also to be an air intake into the mine.
Since the main decline is assumed to include a conveyor, velocities are to be limited by controlling the
flow through the intake fan such that airflow velocity in the conveyor is limited to 3 m/s to mitigate dust
creation. Plans are to have a single 5 m intake raise, a single 5 m return raise for the UZ, and 4.5 m
intake and return raises for the MDZ.
For the primary ventilation circuit, air enters the mine from the intake raise and is regulated across a
level to the return raise system where it is exhausted from the mine. In the secondary circuit, intake
air flows down the main decline into the mine. Part of this air is used to ventilate the shop and
underground crusher; the rest of this air is fed to the internal ramp and onto the working levels.
The crusher area requires dedicated ventilation because of the high generation of dust. 20 cubic
meters per second (m³/s) is used for dilution of heat and dust from the crusher area and provides
perceptible movement of air in the large galleries. Air is to flow over the crusher dump and down to the
crusher level. The crusher area is to have a regulated connection to the main exhaust raise.
An underground shop is also planned. A direct connection to exhaust is to be made at the back end
of the shop. A regulator will be used to limit the airflow to around 20 m3/s. This direct connection to
exhaust will ventilate the shop and help limit harmful fumes generated in the shop from entering the
mine.
Compressibility of air and leakage through stoppings and doors must also be accounted for in the total
mine flow. A general layout of the airflow distribution is shown in Figure 16-45.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 341
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SRK, 2020
Figure 16-45: Marmato Project General Ventilation Scheme
Auxiliary Ventilation
For auxiliary ventilation, a standard duct size of 1.2 m was used to provide enough clearance between
the ducting and equipment. Short headings on levels can be ventilated with 50 kW fans, while longer
development headings will require 75 kW fans. During development of the conveyor decline and lower
portion of the ramp, it will be challenging to provide the target airflow due to the length of duct (1.7 km)
and leakage. For these long drives it is recommended to use two 1.2 m ducts in parallel using 75 kW
fans in series. A summary of the ducting and fan requirements is provided in Table 16-30.
Table 16-30: Auxiliary Ventilation Fan Summary
Duct Dia. (m) Fan Pressure (kPa) Inlet Airflow (m³/s) Air Power (kW) Motor Power (kW)(¹)
1.2 1.4 26 35 46
1.2 2.4 23 54 72
Source: SRK (1) Assumes 75% fan efficiency
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 342
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Main Fans
Primary ventilation circuits are established with two main fan installations. The primary exhaust fan is
the main driver of air for the mine while an intake fan is used to balance the amount of airflow in the
conveyor decline and ramp system. Table 16-31 shows the operating point during the maximum power
outputs for each fan installation. The fans are assumed to be located underground near the surface
portals.
Table 16-31: Fan Operating Points*
Description Pressure
(kPa) Quantity
(m³/s) Motor Power
(kW)¹ Inlet Density
(kg/m³)
Main Intake Fan Installation 0.50 240 160 1.04
Main Exhaust Fan Installation 2.02 342 920 1.03
Source: SRK, 2020 (1) Assume 70% fan efficiency *based on the maximum motor power output for each fan
Fan Power Demand
Power demand from the main and auxiliary fans were estimated with a peak demand of 1,525 kW (the
highest amount of power expected to be used at one time) occurring in year 2031 as shown in Figure
16-46. The installed power is the total power of all the fan installations combined. The total installed
power is approximately 2,000 kW for two main fans and twelve auxiliary fans.
Source: SRK, 2020
Figure 16-46: Estimated Fan Power Demand
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 343
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
16.5.6 Mine Infrastructure & Services
The mine infrastructure includes a power distribution system, mine dewatering systems, underground
service water supply system, an underground paste backfill pumping system, an underground ore
handling system, diesel fueling system, an underground shop, warehouse and storage, offices,
explosives storage, and communications system. The major systems are described in the following
sections. Figure 16-25 shows the location of the major infrastructure systems.
Power Distribution
The main power for the MDZ mining area will be supplied by two 13.2 kV power lines down the decline
to the crusher area. The power then will be distributed through 13.2 kV power lines through the
remainder of the mine to stepdown portable substations at the shop, paste plant pump station, mine
pump stations and operating mining and development areas. The main ventilation fans will receive
power through the ventilation declines near the bottom of the UZ and will be fed from the existing
Marmato UZ substation. The mining connected loads, including the surface backfill plant, total 9.2 MW.
The average running load is approximately 5.3 MW. The major loads include mine ventilation and mine
pumping systems. The mine pumping system runs intermittently and is the main reason the connected
load and average running load are substantially different.
Backup generation of approximately 3.6 MW will be provided by the backup generator at the MDZ
plant. The fans will use the backup generation capacity at the existing Marmato UZ plant.
Mine Dewatering
The MDZ mine pumping system is developed in stages. Declines will be constructed at the MDZ and
UZ sites. Skid mounted pump systems (60 l/s capacity) will be installed in the active development
declines and will be staged to control water in the declines. Once the declines are completed the skid
mounted pump systems will be used on the development ramps as the mine is expanded.
At the 730 m level of the mine, a permanent pump station will be established with a sump and agitator
system. The pump system will include two pump trains of four 225 kW pumps in series with a capacity
of 177 l/s at a total dynamic head (TDH) of 270 m. One train will be operational with one on standby.
The pump discharges to a 30.5 cm steel pipe that carries mine water from the pump station to the
surface to the plant storage water tank. Based on the current knowledge of the hydrogeology, the
pump system is planned to operate at 60 l/s on average.
Later in the mine life, at the current planned bottom of the mine, a second permanent pump station will
be constructed at the 480 m level. The second permanent pump station will be a duplicate of the
system installed at the 730 m level and will operate in the same manner. The system will pump through
30.5 cm schedule 40 steel pipe to the pump station on the 730 m level where the 730 m level station
will pump to the surface. The 480 m level station will operate on average at 13 l/s.
The system is designed to handle maximum flows and operate at the much lower operational flow rate.
Underground Water Supply
Mine service water is supplied from the supply tank located at the surface backfill plant via 10.2 cm
HDPE pipeline down the MDZ decline to the mine operational areas.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 344
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Underground Backfill System
The surface portion of the cemented paste backfill system is described in Section 18.12. Cemented
paste is moved via 20.3 cm schedule 120 pipe from the surface plant to an underground booster pump
station that pumps the paste from the 730 m level to the stopes above this level. The booster pump
station includes a paste hopper and piston pump, pump hydraulic power unit, flush and clean up water
storage tank, and a high pressure flush pump and clean up pump. The booster pump station moves
the paste through the underground paste reticulation system to the stopes. For the stopes below the
730 m level, boreholes have been included to house the piping that will transport the paste to the lower
level stopes.
Ore Handling System
Ore is moved by 45 t truck from the stopes to a truck dump with grizzly and rock breaker that feeds
into an ore pass that feeds a jaw crusher. The ore is crushed and fed onto a conveyor that transports
the ore to the surface where it then crushed further in a secondary crusher feeding into the mill.
Additional detail is in Section 17.3.6.
UG Fuel Storage and Distribution
Fuel from the surface will be transported to the underground storage system via fuel trucks. One fuel
station is included in the design, located near the shop area. The station will be a bladder type, with
up to 150% containment, complete with the following safety functions; 4 hr rated UL approved roll up
door, thermal activated fuel shut off valve to dispensing system, anti-syphon valve, and a dry chemical
automatic fire suppression system with detection and actuation. The station should be alarmed, by
means of a PLC with level alarms, and a level switch.
Additionally, fusible link fire doors are also included in the underground layout, these twin fire doors,
upon actuation will isolate the fueling area from the main shops.
Underground Shop
The maintenance area consists of three large bays to accommodate vehicular traffic. A service trench
runs the length of each bay to allow access to the undercarriage of the vehicles. One wash bay is also
included in the workshop layout. A drainage trench with covering grating will run the length of the bay
to carry water to a nearby oil capture sump. Grading of the area will help reduce the possibility of oil
contamination. Each maintenance bay will also come equipped with an overhead crane to help
facilitate the maintenance work on vehicles.
Warehouse and tool cribs are also included within walking distance of the maintenance bays.
Three rollup doors will separate the two maintenance bays from the rest of the mine. An office will be
located at the end of a drift located in the maintenance area.
Explosives Storage
Underground powder and primer magazines are included in the mine design. The mine explosives will
be stored off site by the military and deliveries will be on as needed basis with the underground
magazines providing the capacity required for production needs.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 345
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Safety Infrastructure
The mine design includes portable and permanent refuge stations. The portable refuge stations will
be staged near the operating faces during development. An emergency hoist is included in the design
for the bottom section of the mine to allow emergency egress. A stench warning system through the
ventilation system will notify workers of emergency conditions.
Communications System
The mine will be equipped with a leaky feeder system that will allow internet, phone, and radio
communications underground. The mine will have standard underground call phones with intercom. A
control system will allow remote operation of the rock breaker and CCTV system to monitor dump
points, crusher, and key material handling locations.
16.5.7 Mine Labor
Labor levels are estimated based on the production schedule and equipment needs. The productivities
used reflect a mix of local and skilled labor with an experienced management team.
The personnel will work one of four rotations that are summarized in Table 16-32.
Table 16-32: MDZ Shift Schedule and Rotation
Roster Type Shift Area
6x2 Rotating 8 hour Underground
12x4 Rotating 8 hour Underground
14x7 Rotating 12 hour Surface
5x2 Days 9 hour Manager/Technical
Source: CGM, 2020
The estimate is based on owner mining using an operating schedule consisting of eight hours per shift
for underground workers, three shifts per day and seven days per week. The management and
technical team are planned to work five nine hour days per week. Surface personnel will work a 12
hour shift. The eight hour and 12 hour shifts are supported by a four crew rotation.
The overall mine staffing at full production is summarized in Table 16-33. The workforce will increase
over time through the addition of staff to operate additional equipment. The total number of personnel
ranges from eight in 2021 to the maximum of 429 in 2024.
Table 16-33: MDZ Mining Labor Summary
Total Mine Roster (On and Off Site) Maximum Staffing
Mine Technical Staff Roster 47
Mine Operations Labor Roster 256
Mine Maintenance Staff Roster 38
Mine Maintenance Labor Roster 88
Total Labor Roster 429
Source: SRK, 2020
Table 16-34 shows the required workforce at the maximum staffing level.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 346
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 16-34: MDZ Mining Labor
Department/Section Category Shift Hours Max Staff
Mine Technical Staff 47
Mine Superintendent Salary 9 1
Chief Mining Engineer Salary 9 1
Long Term Planning Engineer Salary 9 1
Stope Designer Engineer Salary 9 1
Production Reporting Supervisor Salary 9 1
Short Term Planning Salary 9 2
Grade Control Engineer Salary 9 2
Surveyors Salary 9 4
Technician Salary 9 2
Senior Geotechnical Engineer Salary 9 1
Geotechnical Engineer Salary 9 3
Geotechnical Technician Salary 9 2
Ventilation Engineer Salary 9 1
Ventilation Technician Salary 9 2
Backfill Engineer Salary 9 1
Backfill Technician Salary 9 2
Chief Mine Geologist Salary 9 1
Grade Control Geologist Salary 9 3
Infill Drilling Supervisor Salary 9 3
Backfill Coordinator Salary 9 1
Backfill Plant Supervisor Hourly 12 4
Senior Modelling Geologist Salary 9 1
Senior Field Logging Geologist Salary 9 1
Project Lead Salary 9 1
Mechanical Engineer Salary 9 1
Civil Engineer Salary 9 2
Clerk Salary 9 2
Mine Operations Labor 256
Shiftboss Development Hourly 8 4
Jumbo Operator Hourly 8 13
Bolter Operator Hourly 8 9
Cablebolter Operator Hourly 8 9
Shotcrete Operator Hourly 8 9
Crusher Operator Hourly 8 5
Production Drill Operator Hourly 8 18
Blaster Hourly 8 9
UG Explosive storage personnel Hourly 8 9
Blaster Helper Hourly 8 9
Crusher Helper Hourly 8 4
LHD Operator Hourly 8 18
Truck Driver Hourly 8 18
Transmixer Driver Hourly 8 5
Service Crew Hourly 8 9
Shotcrete Helper Hourly 8 9
Utility/Laborer/Nipper Hourly 8 13
Service Crew Helper Hourly 8 13
Conveyor System Operator Hourly 8 4
Production Driller Helper Hourly 8 18
Shiftboss Production Hourly 8 4
Shiftboss Stoping Hourly 8 4
Shiftboss Blasting Hourly 8 4
Infill Drilling Operator Hourly 8 9
Infill Drilling Operator Helper Hourly 8 9
Pastefill Piping Crew Hourly 8 18
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 347
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Department/Section Category Shift Hours Max Staff
Pastefill Barricade Crew Hourly 8 6
Pastefill Supervisor Hourly 8 1
Pastefill Pour Watcher Hourly 8 6
Pastefill Operations Crew Hourly 8 12
Mine Maintenance Staff 38
Maintenance Superintendent Salary 9 1
Maintenance General Foreman Salary 8 1
Maintenance Planning Supervisor Hourly 8 2
Maintenance Planning Engineer Hourly 8 2
Maintenance Planning Technician Hourly 8 5
UG Maintenance General Foreman Salary 8 3
UG Shop Shiftboss Hourly 8 5
Surface Truck Shop Shiftboss Hourly 12 5
Pastefill Plant Operator Hourly 12 7
Pastefill Plant Helper Hourly 12 7
Mine Maintenance Hourly Labor 88
UG Prod Mechanic Hourly 8 9
UG Prod Electrician Hourly 8 9
UG Prod Mechanic Helper Hourly 8 9
UG Prod Electrician Helper Hourly 8 9
UG Shop Mechanic Hourly 8 9
UG Shop Electrician Hourly 8 5
UG Shop Welder Hourly 8 5
UG Shop Mechanic Helper Hourly 8 9
UG Shop Electrician Helper Hourly 8 5
UG Shop Welder Helper Hourly 8 0
Surface Shop Mechanic Hourly 8 5
Surface Shop Electrician Hourly 8 5
Surface Shop Welder Hourly 8 5
Surface Shop Mechanic Helper Hourly 8 5
Surface Shop Electrician Helper Hourly 8 0
Surface Shop Welder Helper Hourly 8 0
Backfill Mechanic Hourly 12 3
Total Labor 429
*This value represents peak production staffing (max equipment) Source: SRK, 2020
16.5.8 Equipment
The underground equipment used, shown in Table 16-35, is typical for the sublevel stoping mining
method with the number of pieces of equipment calculated from the production rates and typical
availabilities for underground mines.
The estimate uses an equipment availability of 85%, a job efficiency factor of 83% (50 minute hour),
and an activity efficiency factor that varies by activity (85% to 100%). Each shift of eight hours is
reduced by 1.92 hours to represent shift change, breaks, lunch, fuel/grease/inspect time and travel to
and from working areas. This provides an equivalent working day of 15.21 hours or 5.07 hours per
shift. The resulting reductions result in 5,552 effective hours per year of mining time. It should be noted
that the layout of this mine and mining on multiple levels requires the addition of equipment to reduce
equipment move time. This reduces the overall utilization of the equipment fleet.
The equipment totals by pre-production and production year are summarized in Table 16-35.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 348
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 16-35: Mine Equipment by Period
Equipment Fleet Requirements Type Diesel
Engine (kW)
Electric Power
(kW)
Max Number
Date
Jan-21
Apr-21
Jul-21
Oct-21
Jan-22
Apr-22
Jul-22
Oct-22
Jan-23
Apr-23
Jul-23
Oct-23
Jan-24
Apr-24
Jul-24
Oct-24
Jan-25
Jan-26
Jan-27
Jan-28
Jan-29
Jan-30
Jan-31
Jan-32
Jan-33
Underground Mobile Equipment
Sandvik DD422iE - Jumbo, 2 boom DD422iE 119 180 3 0 0 0 2 2 2 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 2 1 1
Sandvik DS411 - Mechanical Bolter DS411 110 70 3 0 0 0 2 2 2 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 2 1 1
Sandvik DS422i - Cablebolter DS422i 120 75 1 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Sandvik DU411 ITH - Production Drill DU411 ITH 130 80 3 0 0 0 0 0 0 0 0 0 0 0 2 2 3 3 3 3 3 3 3 3 3 3 3 0
Getman Orica - Explosives Truck w/Orica MaxiCharger 5344 Orica 129 0 2 0 0 0 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Getman Orica - Getman Explosives Truck with Orica Handiloader Orica 129 0 1 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0 0
Getman SST Shotcrete Unit - Shotcrete Sprayer SST Shotcrete Unit
110 0 1 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0 0
Getman A64 HD R60 - Transmixer Truck A64 HD R60 129 0 2 0 0 0 1 1 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 0 0
Sandvik LH517i - LHD, 7.3 m3, 17 t LH517i 256 0 4 0 0 0 2 2 2 2 2 2 2 2 3 3 4 4 4 4 4 4 4 4 4 4 2 2
Sandvik TH545i - Haulage Truck, 45 t TH545i 515 0 4 0 0 0 2 2 2 2 2 2 2 2 2 3 3 4 4 4 4 4 4 4 4 4 2 2
Auxiliary Equipment
CAT UG20M - Grader UG20M 105 0 1 0 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Sandvik LH307 - LHD, 3.7 m3, 7 t LH307 160 0 1 0 0 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Getman A64 - Scissor Lift A64 129 0 2 0 0 0 0 0 0 0 0 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Getman A64 - Boom Truck A64 129 0 1 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Getman A64 - Flat Deck Truck A64 129 0 1 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
4x4 Pickup - Light Vehicles 4x4 Pickup 75 0 12 0 0 0 3 4 4 4 5 5 5 6 6 6 6 6 12 12 12 12 12 12 12 12 6 5
Getman A64 - Fuel Truck A64 129 0 2 0 0 0 1 1 1 1 1 1 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Getman A64 - Personnel Carrier, 16 per. A64 129 0 3 0 0 0 0 1 1 1 1 1 1 1 2 3 3 3 3 3 3 3 3 3 3 3 3 2
Kubota RTV 1120D - Personnel Carrier RTV 1120D 19 0 12 0 0 0 4 4 4 5 6 7 8 8 8 8 8 12 12 12 12 12 12 12 12 12 5 4
CAT 1255D - Forklift/Telehandler 1255D 106 0 1 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Getman A64 - Service Mechanic Truck A64 129 0 1 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
CAT 272D - Skid Steer 272D 73 0 2 0 0 0 1 1 1 1 1 1 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Sandvik DE142 - Underground Core Drill DE142 0 0 2 0 0 0 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
CAT 982M - Front End Loader - 6.7m3/8.75 yd3 982M 325 0 1 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Miller - Skid Mounted Pump system (each) - 7500gal tank, 2ea 112 kW (1op/1stby) pumps
0 0 143 6 0 0 0 0 2 4 6 6 6 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
Miller - 730 Level Sill Pump System - 8ea 400kW (4 op/4stby) pumps; VFD; 4 submersible 22kW pumps with 11kW starters (4 op)
0 0 293 1 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Miller - 480 Level Sill Pump System - 8ea 400kW (4 op/4stby) pumps; VFD; 4 submersible 22kW pumps with 11kW starters (4 op)
0 0 65 1 0 0 0 1 1 1 1
Getman A64 - Lube Truck A64 129 0 1 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Getman A64 - SLHanger Scissor Lift A64 129 0 1 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Getman A64 - SLWing Scissor Lift A64 129 0 1 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Getman A64 - Pallet Handler A64 129 0 1 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Atlas Copco XATS 400 - 350 CFM Mobile Compressor XATS 400 115 0 2 0 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Miscellaneous Equipment
Getman A64 - Flat Pallet for Pallet Handler 1 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Getman A64 - Personal Carrier for Pallet Handler 1 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Getman A64 - Water Sprayer for Pallet Handler 1 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Fans Main - 1500kVA XFMR & SWGR (VFD $ included with Fans)
1 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Surface Backfill - 2500kVA XFMR &SWGR 1 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Conveyor Decline Main PWR Feed - 13.2kV 2x3C#500MCM Cable, 15kV JBs - 2x1.7km
1 0 0.25 0.5 0.75 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Conveyor Decline Main PWR Feed - 13.2kV UG SWGR Skid 4 0 1 2 2 2 2 2 2 3 3 3 3 3 3 3 3 3 4 4 4 4 4
Crusher - 1000kVA XFMR & 5kV SWGR 1 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
UG Shop - 500kVA XFMR & MCC + Distribution 1 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Mobile Substation 1000kVA - 13.2kV:440V 4 0 1 1 1 1 2 2 3 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
Mobile Substation 750 KVA - 13.2kV:440V 8 0 2 2 2 2 2 3 4 6 6 6 8 8 8 8 8 8 8 8 8 8 8 8
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 349
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Equipment Fleet Requirements Type Diesel
Engine (kW)
Electric Power
(kW)
Max Number
Date
Jan-21
Apr-21
Jul-21
Oct-21
Jan-22
Apr-22
Jul-22
Oct-22
Jan-23
Apr-23
Jul-23
Oct-23
Jan-24
Apr-24
Jul-24
Oct-24
Jan-25
Jan-26
Jan-27
Jan-28
Jan-29
Jan-30
Jan-31
Jan-32
Jan-33
Pump Starter Box - 30hp 0 0
Pump Starter Box - 150hp 0 0
Pump Starter Box - 350Hp 0 0
MineArc - Refuge Chamber - 12 person 0 0
MineArc - Refuge Chamber - 8 person 3 0 1 2 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
MineArc - Refuge Chamber - 40 person built in 1 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Allowance - Underground Shop Tool and Equipment 1 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Allowance - Powder and Primer Magazines 1 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Allowance - Surface Shop Tool and Equipment 1 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Allowance - Engineering Tools and Software 1 0 0.25 0.5 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Allowance - Shipping Container Storage-2 ea 2 0 1 1 1 1 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Allowance - Communications Infrastructure and Mine Automation 1 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Allowance - Miscellaneous Lighting 1 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Fueling - UG Fueling System - supply lines, pump and storage 1 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Fueling - Surface Fuel Bay 1 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
MDZ - Conveyor Decline Portal 1 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
MDZ - Veins side - Vent Decline Portal 1 1 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
MDZ - Veins side - Vent Decline Portal 2 1 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Allowance - Underground Emergency Hoist 1 0 1 1 1 1
Surface Backfill - Tailings, water delivery, return water 1 0 0.5 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Surface Backfill - Surface paste plant 1 0 0.5 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Underground Backfill - UG Booster pump station 1 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Underground Backfill - UG Reticulation System (paste delivery) 1 0 0.5 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Surface Shotcrete - Modular Shotcrete Plant 1 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Surface Backfill - Earthworks Estimate for Surface Backfill Plant Pad
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Underground - Water Piping for 730 Level Sill Pump System - 2260 m
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Underground - Water Piping for 480 Level Sill Pump System - 270 m
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Allowance - Fault Mitigation in Declines (30m @US$2500/m) 1.262 0 0 0 0 0 0 0 0.73
8 1.26
2 1 0.29 0.71 1 1 0 0 0 0 0 0 0 0 0
Allowance - Mine Rescue Unit 1 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Ventilation Equipment
Howden 12300-AMF-8000 - Main Ventilation Exhaust Fan (1000 KW)
0 1000 1 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Howden 11200-AMF-6100 - Main Ventilation Intake Fan (200 KW) 0 200 1 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Fan 75 kW - Development Fan 0 75 8 0 4 4 4 6 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8
Fan 50 kW - Auxiliary Fan 0 50 4 0 2 2 2 2 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
Fan 25 kW - Auxiliary Fan 0 25 4 0 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
Ventilation - Single Equipment Door 0 0 9 0 4 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9
Source: SRK, 2020
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 350
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
16.6 Combined UZ and MDZ Production Schedule
Figure 16-47 and Figure 16-48 summarize the combined UZ and MDZ schedules. This combined
schedule is used in the economic model results shown in section 22.
Source: SRK, 2020
Figure 16-47: Combined UZ and MDZ Mining Profile – Tonnes and Grade
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 351
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SRK, 2020
Figure 16-48: Combined UZ and MDZ Mining Profile - Contained Metal
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 352
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
17 Recovery Methods CGM operates a 1,200 t/d process plant to recover gold and silver values from material produced from
current Marmato mining operations in the UZ and plans to expand this facility to a 1,500 t/d capacity
in the next couple of years. In addition, CGM is evaluating the development of the MDZ, which is below
the current mining operations and the construction of a new 4,000 t/d plant to process material solely
from the MDZ. Recovery methods currently in use for processing Marmato material and recovery
methods are being evaluated for processing the MDZ material and are presented and discussed in
this section.
17.1 Marmato Process Plant (Current Operations)
The Marmato process plant flowsheet incorporates unit operations that are standard to the industry
and include:
• Three-stage crushing
• Closed circuit ball mill grinding
• Gravity concentration
• Flotation
• Flotation and gravity concentrate regrind
• Cyanidation of the flotation and gravity concentrates
• Counter-current-decantation
• Merrill-Crowe zinc precipitation
• Smelting of precipitates to produce final doré product
The Marmato process plant flowsheet is shown in Figure 17-1 and a list of major equipment is shown
in Table 17-1. Each of the process unit operations is briefly described in this section.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 353
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Figure 17-1: Marmato Process Flowsheet
Source: CGM, 2020
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 354
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 17-1: Equipment List for Marmato Process Plant
Flowsheet No. Equipment Description Quantity Hp
1 Mine rail cars 1.5 t
2 Pre-hopper 100 t 1
3 Winch 2 60
4 Feed hopper 5 m x 7 m 1
5 Feed hopper with hydraulic gate 1
6 Vibrating grizzly 5 ft x 13 ft (5/16") 1 20
7 Primary jaw crusher 25" x 40" 1 125
8 Conveyor belt 30" 1 25
9 Vibrating screen (double-deck) 20 ft x 8 ft (7/8" x 3/8") 1 40
10 Conveyor belt 24" x 14 m 1 12
11 Secondary cone crusher Omincone -1352 1 250
12 Conveyor belt 24" x 14 m 1 12
13 Tertiary cone crusher HP300 1 300
14 Spiral Classifier 30" x 17 ft 1 7.5
15 Fine ore bin 7 m x 5.8 m 1
16 Conveyor belt 24" x 7 m 1 7
17 Conveyor belt (with belt scale) 24" x 9 m 1 7
18 Primary ball mill (Allis Chalmers) 9.5 ft x 14 ft 1 600
19 Tapezoidal jig 17 ft2 4 7
20 Cyclone feed pump 6" x6" 2 75
21 Hydrocyclone Gmax 20" 2
22 Flash flotation cell SK-80 1 20
23 Secondary ball mill 7.5 ft x 10 ft 1 300
24 Gravity concentrate pumps 3" x 3" 6 20
25 Flotation conditioner 12 ft x 12 ft 1 30
26 Rougher flotation cell KCF/KYF 30 2 75
27 Scavenger flotation cell (circular) 10 ft x 10 ft 3 30
28 Cleaner flotation cell 2 m x 2 m 2 7.5
29 Thickener 24 ft x 10 ft 5 3
30 Regrind cyclone feed pump Wilfley 5K 2 60
31 Regrind hydrocyclone 6" 4
32 Regrind ball mill Hardinge 7 ft x 5 ft 2 200
33 Pretreatment agitated tank 12 ft x 12 ft 2 12
34 Thickener 24 ft x 10 ft 4 3
35 Static Thickener 12 ft x 35 ft 1
36 Peristaltic pump Bredel SPX-65 1 1
37 Leach tank 20 ft x 20 ft 2 30
38 Thickener 30 ft x 10 ft 1 1
39 Leach tank 12 ft x 12 ft 6 12
40 PLS tank 12 ft x 12 ft 2
41 Clarifier 1
42 Deaeration tower 1
43 Vacuum pump Hydral 1 12
44 Zinc dust dosing cone feed pump Halberg Nowa 1 25
45 Zinc dust dosing cone 1
46 Filtro Press pump feed Halberg Nowa 1 25
47 Filtro Press 2
48 Precipitate receiving tray 1
49 Flux mixing tray 1
50 Precipitate smelting furnace 1
51 Ingot molds 2
52 Dore’
53 Barren solution tank 12 ft x 12 ft 1
Source: CGM, 2019
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 355
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
17.1.1 Crushing Circuit
RoM ore is hauled by rail from the mine and dumped into a hopper where a slusher is used to move
the material to a 5 m by 7 m feed hopper that feeds a vibrating grizzly to remove the -3/8 inch material,
prior to feeding the primary jaw crusher. The discharge from the jaw crusher is conveyed to a double-
deck vibrating screen fitted with a 7/8 inch upper deck and a 3/8 inch lower deck. The screen oversize
from the top deck is conveyed to a Nordberg 1352 Omnicone which is operated in closed circuit with
the vibrating double-deck screen. Ore retained on the second deck is conveyed to a Nordberg HP300
cone crusher, which is also operated in closed circuit with the vibrating screen. The -3/8 inch screen
undersize discharges to the fines bin. The -3/8 inch undersize from the vibrating grizzly is further
classified in a spiral classifier. The classifier oversize is fed directly into the primary ball mill and the
classifier undersize is thickened and then pumped to the primary hydrocyclones. The crushing circuit
has an operating capacity of 1,600 t/d.
17.1.2 Grinding and Gravity Concentration Circuit
Crushed ore (-3/8 inch) is fed from the fines bin and then transported on a conveyor fitted with a belt,
scale to the 9.5 ft by 14 ft primary ball mill (600 hp). The primary ball mill discharges to a Knelson
gravity concentrator (model QS-40) to recover coarse gravity recoverable gold. The tailings from the
gravity concentrator is pumped to the cyclones where a size separation at P50 75 µm is made. The
cyclone underflow discharges to the 7.5 ft by 10 ft secondary ball mill (300 hp), which is operated in
closed circuit with the cyclones and the overflow advances to the flotation circuit. The gravity
concentrate is combined with the flotation concentrates prior to advancing to the regrind and
cyanidation circuits.
17.1.3 Flotation and Concentrate Regrind Circuit
The cyclone overflow from the grinding circuit is advanced to the flotation circuit where it is first
conditioned with the required flotation reagents and then subjected to one stage of rougher flotation
followed by one stage of scavenger flotation, which provides a total flotation retention time of 40
minutes to recover the contained gold and silver values. The scavenger flotation concentrate is
upgraded in one stage of cleaner flotation and combined with the rougher flotation concentrate. The
rougher + scavenger cleaner flotation concentrates are combined with the gravity concentrate, and
then thickened to about 55% solids and reground to about 80% passing (P80) 44 µm. A portion of the
flotation tailings is pumped to an agitated storage tank and then pumped back underground with a
positive displacement pump for use as hydraulic backfill in the mine.
17.1.4 Cyanidation and Counter-Current-Decantation (CCD) Circuit
The reground gravity and flotation concentrates are re-thickened and then advanced to a conventional
two-stage cyanidation circuit, which provides a total of 30 hours of leach retention time. The first stage
of leaching consists of two 20 ft by 20 ft agitated leach tanks operated in series at a cyanide
concentration of 700 mg/L NaCN and at a pH of 10.5 adjusted with lime. The second-stage leach
circuit consists of six 12 ft by 12 ft agitated leach tanks in which the cyanide concentration is allowed
to attenuate through the circuit from 700 to 400 mg/L NaCN. The leached slurry is then passed through
a counter-current-decantation circuit (CCD) which serves to wash the pregnant leach solution (PLS)
from the leached solids. The leached solids are discharged from the last CCD thickener and then
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 356
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
pumped to the DSTF. The PLS is processed in the Merrill-Crowe circuit to recover the solubilized gold
and silver values.
17.1.5 Merrill-Crowe Circuit and Smelter
The PLS is pumped to the Merrill-Crowe circuit where it is first clarified to remove any remaining
suspended solids and then de-aerated to less than 1 mg/L dissolved oxygen in a vacuum tower. Zinc
dust is then added to the de-aerated PLS in a controlled manner which results in the precipitation of
the gold and silver values, which are then recovered in a filter press. The resulting gold and silver
precipitate are removed from the filter press on a scheduled basis and then smelted using a flux with
the following composition:
• Borax: 40%
• Sodium nitrate: 30%
• Soda ash: 20%
• Silica: 10%
Approximately 600 kg of flux is blended with 600 kg of precipitate and smelted in a diesel-fired furnace
to produce a final doré product.
17.1.6 Process Plant Consumables
Process plant consumables are shown in Table 17-2 and includes grinding media, wear materials and
process reagents. Consumable costs during 2019 (Jan to July) averaged US$3.05/t processed.
Table 17-2: Marmato Process Plant Consumables
Item kg/t US$/Kg US$/t
Grinding Balls (1.5 inch) 0.165 1.13 0.19
Grinding Balls (2 inch) 0.312 1.15 0.36
Grinding Balls (3 inch) 0.392 1.15 0.45
Wear Liners 0.32
Sodium Cyanide 0.370 2.48 0.92
Zinc Dust 0.020 5.03 0.10
Lime 0.625 0.18 0.11
Copper Sulfate 0.015 2.35 0.04
Xanthate (Z-11) 0.011 3.58 0.04
Aerofroth (A65) 0.028 5.56 0.16
Collector MX 5160 0.005 11.12 0.06
Aero AR1404 0.003 11.22 0.03
Lead Acetate 0.002 6.49 0.01
Flocculant (EGA 1203) 0.015 5.09 0.08
Silica 0.095 1.17 0.11
Borax 0.015 0.74 0.01
Soda Ash 0.008 0.60 0.00
Potassium Carbonate 0.001 1.65 0.00
Soloun K 0.015 1.37 0.02
ACPM 0.017 2.47 0.04
Total Consumables 3.05 Source: CGM, 2019
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 357
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
17.1.7 Operating Performance
The current Marmato process plant performance is summarized in Table 17-3 for the period from 2013
to 2020 (Jan to May). During this period mineralized tonnes processed has increased from 274,191 to
370,245 t/y while grades have declined slightly from 2.90 g/t Au in 2013 to 2.49 g/t Au in 2019 and
silver grades have ranged from 12.36 to 9.13 g/t Ag. Overall gold recovery has ranged from 83.7 to
88.9% and has averaged about 87.1% during the period 2019 to 2020 (Jan to May). Silver recovery
has ranged from 33 to 41.1 and has averaged 33.2% during the period of 2019 to 2020 (Jan to May).
Annual gold production has increased from 22,566 ounces in 2013 to 25,750 ounces in 2019.
Table 17-3: Summary of Marmato Process Plant Operating Performance and Recovery Estimate
Parameter 2013 2014 2015 2016 2017 2018 2019 2020 (Jan-May)
Ore Tonnes 274,191 295,023 303,279 341,309 365,119 338,902 370,245 119,069
Ore Grade
Au (g/t) 2.90 2.85 2.79 2.56 2.48 2.67 2.49 2.47
Ag (g/t) 12.36 9.13 9.33 9.24 9.61 10.53 9.98 9.49
Metal Recovery
Au (%) 88.6 89.0 88.0 83.7 86.8 85.5 87.1 88.9
Ag (%) 36.6 41.1 37.9 35.8 34.9 33.2 33.0 33.3
Metal Produced
Au (Ounces) 22,566 24,113 23,954 23,449 25,163 24,909 25,750 8,318
Ag (Ounces) 39,916 34,753 34,490 36,318 39,524 37,522 39,558 11,972
Source: CGM, 2020
17.1.8 Operating Costs
The Marmato process plant operating costs reported for 2019 and 2020 (Jan to May) are summarized
in Table 17-4. During 2019, operating costs were reported at US$12.25/t of ore processed and during
2020 (Jan to May) plant operating costs were reported at US$13.09/t. For the period 2019 to 2020
(Jan to May) plant operating costs have averaged US$12.43. The exchange rate has averaged 3,345
COL per US$1.00 during this period.
Table 17-4: Marmato Process Plant Operating Costs: 2019 - 2020 (Jan-Apr)
Production Total (2019) Total 2020 (Jan-Apr) Total 2019 -2020 (Jan-Apr)
Au Oz 25,750 7,104 32,854
Ore Tonnes 370,495 100,608 471,103
Process Cost (COP)
Crushing 3,147,524,778 1,057,755,849 4,205,280,627
Grinding 5,316,634,662 1,655,877,068 6,972,511,730
Flotation 2,394,649,787 792,698,640 3,187,348,427
Cyanidation & Merrill-Crowe 3,517,471,235 1,076,654,318 4,594,125,553
Refining 485,287,000 143,020,457 628,307,457
Total Process Cost (COP) 14,861,567,462 4,726,006,332 19,587,573,794
Total Process Cost (US$) 4,538,616 1,316,963 5,855,579
US$/Oz 176 185 178
US$/tonne 12.25 13.09 12.43
Exchange Rate (COP/US$) 3,275 3,621 3,345
Source: CGM, 2020
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 358
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
17.2 Expansion Plans
CGM plans to expand the Marmato process plant capacity to 1,500 t/d over the next two years
(complete by Q4 2021), which represents approximately a 35% increase in capacity. The incremental
improvements to the existing process plant would include:
• Install a refurbished 15.5 ft by 22 ft ball mill (3000 hp) to replace the current primary ball mill
(600 hp) and secondary ball mill (300 hp)
• Install new 15 inch hydrocyclones in the upgraded grinding circuit
• Increase flotation circuit capacity by 50% with the installation of an 80 m3 flotation cell
• Install a new Knelson gravity concentrator (QS-40), which would replace the existing jigs
• Recommission an existing Hardinge regrind ball mill
• Increase leach circuit volume to 800 m3 (35% increase) by replacing two leach tanks with two
5.9 m diameter by 6 m high leach tanks
• Install two new thickeners (30 ft diameter)
• Upgrade the Merrill-Crowe circuit
• Install new water tank
• Upgrade fresh water supply system
CGM’s capital cost estimate to complete the Marmato plant expansion is summarized in Table 17-5,
which shows a total capital expenditure of US$11.6 million over the next four years. SRK has applied
a 25% contingency, which brings the total capex estimate to US$14.5 million over this period.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 359
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 17-5: Summary of Marmato Process Plant Expansion Capex
Equipment 2020 2021 2022 2023 2024 Total
New Apron Feeder 440,000 440,000
Replace Secondary Cone Crusher
550,000 550,000
Replace Tertiary Cone Crusher
770,000 770,000
New Samplers 55,000 55,000
Install Refurbished Ball Mill (15.5 ft by 22 ft)
2,640,000 2,200,000 4,840,000
New Primary Mill Pumps and Piping
180,000 180,000
Upgrade Concentrate Pumps and Piping
50,000 50,000
New Hydrocyclones (15 Inch) 77,000 77,000
New Linear Trash Screen (Delkor 20 M2)
88,000 88,000
New Flotation Cell (80 M3) 250,000 250,000
Knelson Concentrator (QS40) 660,000 660,000
Recommission Hardinge Regrind Mill
120,000 120,000
Install Two New Leach Tanks (5.9 m Diameter by 6 m High)
275,000 275,000 550,000
Install New Thickeners (30 ft Diameter)
660,000 660,000 660,000 1,980,000
New Merrill-Crowe Filter Presses
132,000 132,000
PLS Clarifier 66,000 66,000
New Merrill-Crowe Deaeration Tower
44,000 44,000
New Water Tank (150 M3) 110,000 110,000
New Water Supply System 220,000 444,000 664,000
Subtotal 5,035,000 3,511,000 1,210,000 440,000 1,430,000 11,626,000
Contingency (@25%) 1,258,750 877,750 302,500 110,000 357,500 2,906,500
Total 6,293,750 4,388,750 1,512,500 550,000 1,787,500 14,532,500
Source: CGM, 2020
17.3 MDZ Process Plant
17.3.1 Processing Methods
The process plant for the MDZ Project is based on a flowsheet with unit operations that are well proven.
The proposed flow sheet uses standard processes for:
• Crushing/Grinding
• Gravity/Leach/Adsorption
• Desorption/Electrowinning/Refining
• Cyanide Detoxification
• Tailings Thickening/Filtration
Metallurgical test programs involved SGS Lakefield, Ausenco’s industry experience, and input from
equipment suppliers and were contemplated in the design of the overall proposed flowsheet diagram
shown in Figure 17-2.
ELUTIONELECTROWINNING
CELL
GOLD SLUDGEFILTER PRESS
ACIDWASH
COLUMN
ELUTIONCOLUMN
CARBONDEWATERING
SCREEN
CARBONREGENERATION KILNPROPANE
DRYING OVEN
BARRINGFURNACE
SLUDGETROLLEY
CASCADEPOURING TABLE
DORECARBONQUENCH
TANK
ELUTIONPROPANE HEATER
RECOVERYHEAT
EXCHANGER
HCLWATER
STRIPELUATE TANK
KILN FEEDHOPPER
ICUELECTROWINNING
CELL
CIP TANKS (X6)
BL
PRIMARYCRUSHER
TRASHSCREEN
LEACH TANKS (X4)
TO PLANT
LIMECYANIDE
DETOX TANKS
CARBONSAFETYSCREEN
CARBON SIZINGSCREEN
LOADED CARBONSCREEN
WATER
CuSO4SMBSLIME
CONTINUOUS FLOW INTERMITTENT FLOW
FUTURE
LEGEND
EQUIPMENT
PRE-AERATION TANK
GRAVITYSCREEN
GRAVITYCONCENTRATOR INTENSIVE
LEACHINGFEED TANK
ICU PREGNANTSOLUTION TANK
INTENSIVE LEACHINGREACTOR
ROM ORE
BALL MILL
CYCLONE FEEDHOPPER
U/F
O/FCYCLONECLUSTER
OXYGEN OXYGEN OXYGEN
FLOCCULANT
O/F
THICKENER
PROCESSWATER TANK
OXYGEN OXYGEN
FILTER 2
CHAIN GATE
BACKFILL(BY OTHERS)
FILTER 1
SAG MILL
CuSO4SMBSLIME
SAG MILLFEED CONVEYOR
CRUSHED ORESTOCKPILE
SECONDARYCRUSHERSURGE BIN
SECONDARYCRUSHER
STOCKPILEFEED CONVEYOR
PRIMARY CRUSHERDISCHARGE CONVEYOR
UNDERGROUND
BELTFEEDERS
SCATS BUNKER
SECONDARYCRUSHER
PAN FEEDER
TAILINGS FILTERFEED TANK
FILTRATE TANK
SECONDARY CRUSHERSURGE BIN
CONVEYOR No. 2
PRE-SOAKTANK
TO TAILINGS
NaOHNaCN
WATER
SECONDARYCRUSHERSCREEN
WATER
OXYGEN
METALDETECTOR
AusencoCOPYRIGHT c
A1Ausenco
Toronto, Ontario,
Canada
T +1 416 363 6518
W www.ausenco.com
Jun
23,20
20 -
6:48p
m C:
\Use
rs\luc
y.liu\
Desk
top\10
4317
Mar
mato\
1043
17-0
000-
F-00
1.dwg
- luc
y.liu
THE DRAWING AND ITS CONTENTS ARE CONFIDENTIAL FOR THEPRIVATE INFORMATION OF MARATHON GOLD INC. FOR USEONLY FOR THE PROJECT IT WAS PREPARED AND NOT TO BERELIED UPON OR USED IN WHOLE OR IN PART FOR OTHERPURPOSES OR BY OR FOR THE BENEFIT OF OTHERS WITHOUTPRIOR ADAPTATION AND SPECIFIC WRITTEN VERIFICATION BYAUSENCO.
PRELIMINARY
VIBRATINGGRIZZLY FEEDER
TRAMP METALMAGNET
SELF CLEANINGMAGNET
SECONDARYCRUSHER
DIVERSION CHUTE
TRASHBIN
SCATS BUNKER
HIGH ANGLEPEBBLE CONVEYOR
PEBBLE CRUSHERDIVERSIONCHUTE No.1
PEBBLE CRUSHERDIVERSIONCHUTE No.2(FUTURE)
PEBBLECRUSHER(FUTURE)
TRASHMAGNET
BL
OXYGEN
LIMELIME
BL
TAILINGS FILTER CAKE TAILINGS FILTER CAKE
POLISHING PONDSITE RUNOFF POND
WATERTREATMENT
PLANT
BL
TO ENVIRONMENT
WASHWATER TANK
SECONDARY CRUSHERSURGE BIN
CONVEYOR No. 1
PLANT SITERUN-OFF
Figure 17-2
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 361
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
17.3.2 Plant Design and Equipment Characteristics
The MDZ process plant has a design for an ore treatment of 1,460,000 dry t/y or 4,000 dry t/d based
on a plant availability of 8,059 h/y, or 92%. The process design criteria summary is provided in
Table 17-6.
Table 17-6: Process Design Criteria Summary
o Description o Units o Value
o Ore Throughput o Dry t/a o 1,460,000
o Operating Schedule
o Crusher Availability o % o 67
o Plant Availability o % o 92
o Crusher Operating Time o h/a o 5,869
o Plant Operating Time o h/a o 8,059
o Throughput, Daily - Average o Dry t/d o 4,000
o Plant Capacity, Hourly o Dry t/h o 181
o Gold Grade - Design Mill Head o g/t o 3.48
o Overall Gold Recovery o % o 95.4
o Silver Grade – Design Mill Head o g/t o 5.19
o Overall Silver Recovery o % o 57.8
o Crushing (Two Stage)
o Primary Crusher o Type o Jaw Crusher
o Secondary Crusher o Type o Cone Crusher
o Impact Crushing Work Index (75th Percentile)
o kWh/t o 23.4
o Crushed Ore Stockpile Residence Time (live)
o H o 24
o Crushing Product Size, F80 o Mm o 32
o Grinding
o Circuit Type o o 2C-SAB with Hydrocyclones
o Axb (75th Percentile) o o 24.5
o Bond Ball Mill Work Index (75th Percentile) o kWh/t o 19.0
o Product Particle Size, P80 – Equipment Design
o µm o 105
o Pebble Recirculating Load o % of Fresh Feed o 37
o Gravity Concentration
o Overall Gravity Gold Recovery o % o 35
o Intensive Leaching Batches per Week o # o 7
o Leach-Adsorption
o Leach o o
o Total Leach + Adsorption Time o H o 24
o Number of Pre-aeration Tank o # o 1
o Number of Leach Tanks o # o 4
o Leach Operating Density o % w/w o 43.2
o Cyanide Addition to Leach o kg/t o 0.61
o Pre-aeration + Leach pH Target o o 10.5-11
o Pre-aeration + Leach DO Target o mg/L o 20-25
o CIP
o Number of Carbon-in-Pulp Tanks o # o 6
o Carbon Concentration o g/L o 25
o Overall Leach Gold Extraction o % o 95.1
o Gold Losses
o Soluble o mg/L o <0.015
o Carbon o % o 0.08
o Desorption and Carbon Regeneration
o Desorption o o
o Elution Method o o AARL
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 362
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
o Description o Units o Value
o Carbon Batch Size o T o 4
o Elution Cycles per Week o # o 7
o Electrowinning (EW) o o
o Gravity EW Cathode Type o o Stainless Steel
o Gravity EW Number of Cells o # o 1
o Gravity EW Number of Cathodes/Cell o # o 12
o Elution EW Cathode Type o o Stainless Steel
o Elution EW Number of Cells o # o 1
o Elution EW Number of Cathodes/Cell o # o 24
o Cyanide Destruction
o Method o o SO2/ Oxygen
o Number of Tanks, Parallel o # o 2
o Residence Time, Each o Min o 60
o Detoxification Feed CNWAD o mg/L o 200
o Detoxification Discharge Target CNWAD o mg/L o < 1.0
o SO2 Addition o SO2:g CNWAD o 7.81
o Oxygen Addition o g O2/ g CNWAD o 3
o Lime Addition o g CaO/g SO2 o 0.58
o Tailings Thickening
o Tailings Thickener Underflow Density o % w/w o 60
o Flocculant Addition o g/t o 50
o Tailings Filtering o o
o Tailings Filtration Rate o kg/m2h o 181
o Tailings Filter Cake Moisture Target o % w/w o <15
o Tailings Filter Type o o Horizontal Plate and Frame Pressure
Filter
o Number of Units o # o 2
o Plate Size o Mm o 2640 x 3050
o Effective Filtration Area o m2 o 811
o Number of Chambers per Unit o # o 87
o Chamber Depth o Mm o 50
o Filter Plate Material of Construction o o Polypropylene
Source: Ausenco, 2020
17.3.3 Process Plant Description
The MDZ process plant is located NE of the town of Marmato, Colombia. Access to the plant will be
via the plant roads off National Route 25. The primary crusher is located underground, and the
secondary crusher positioned at the surface near the entrance to the tunnel portal. The crushed ore
stockpile is located east of the main plant. The main plant is outdoors and contains the grinding, gravity
recovery, leach/CIP tanks, reagent, elution/carbon regeneration, cyanide detoxification, and tailings
thickening. The electrowinning and refining area are in a separate building to the south section of the
main process plant layout. The thickened tailings are pumped to a filter plant, located next to the main
plant, to be filtered and transferred to the tailings storage facility. Figure 17-3 shows the
mill/leach/reagents general arrangement in plan view.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 363
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Figure 17-3: Mill/Leach/Reagents General Arrangement
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 364
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
17.3.4 Primary/Secondary Crushing and Stockpile
RoM ore is transported to the primary crusher located underground and dumped into a RoM bin. The
RoM bin has a 600 mm by 600 mm static grizzly installed to keep large oversize from plugging the
primary crusher feed cavity, and rock breaker to treat any oversize. A vibrating grizzly feeder with 100
mm bar spacing ahead of the of the primary jaw crusher is used to screen out the finer material and
feed the jaw crusher the grizzly oversize material. The jaw crusher will produce a product with an 80%
passing size of 128 mm. The crushing circuit is designed for an annual operating time of 5869 h/a or
67% availability.
The primary crusher product along with the grizzly feeder undersize is conveyed along a short sacrificial belt and transferred to a longer conveyor to the surface and discharge into a surge bin for the secondary crusher. A pan feeder will feed the secondary crusher screen, with the oversize fed to a secondary cone crusher, which produces a product with an 80% passing size of 36 mm. The screen undersize and the secondary cone crusher discharge (fine ore product) are combined and conveyed to the crushed ore stockpile. The stockpile allows for 24 hours of continuous milling operation at the nominal feed rate. Crushed ore is 100% passing 65 mm and 80% passing 32 mm. The crushing and grinding circuits are configured in a 2C-SAB circuit, which is two stage crushing followed by SAG (semi-autogenous grinding mill) and ball mill.
Figure 17-4 shows the primary and secondary crushing arrangement and the stockpile.
Figure 17-4: Primary/Secondary Crushing and Stockpile
Crushed ore will be withdrawn from the stockpile by two variable speed belt feeders. The belt feeders
are sized such that during maintenance, one of the feeders can provide the full mill-feed capacity of
181 tonnes per hour (t/h).
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 365
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
17.3.5 Grinding
Crushed ore from the stockpile is transferred to the SAG mill via the mill feed conveyor. The conveyor
is equipped with a belt scale to provide feed rate data for feed control to the SAG mill.
A SAG mill media bin located adjacent to the mill will add media to the mill on a pre-set scheduled
basis. A similar media bin is located adjacent to the ball mill to add media to the mill at a determined
charging schedule.
Primary grinding is provided by a 6 m diameter by 3.6 m EGL SAG mill, with an installed pinion power
of 2 MW. The SAG mill trommel undersize will report to the cyclone feed hopper, with the oversize
recirculated back to the SAG mill feed conveyor by means of a high-angle pebble conveyor. There is
a contingency for a future pebble crusher installation at the head end of the high-angle pebble
conveyor. Secondary grinding is provided by a 4.9 m diameter by 7.3 m ball mill, with an installed
pinion power of 3.1 MW and operated in closed circuit with hydrocyclones. The classification circuit
will operate at a nominal circulating load of 300% which is a typical for ore of similar characteristics
and target grind size of 80% passing 105 µm. To avoid damage to the cyclone feed pumps and cyclone
clusters, ball mill discharge is screened through a trommel screen to scalp off oversized particles and
broken grinding media. The trommel screen undersize slurry from the ball mill discharges to the
cyclone feed hopper. The slurry is pumped by the cyclone feed pump to the classification cyclone
cluster.
Slurry from the cyclone cluster underflow launders is split, with 40% of the flow feeding the gravity
concentration and intensive cyanide leach circuit and 60% of the flow returning directly back to the ball
mill. The tails of the gravity concentration and intensive cyanide leach circuit return to the ball mill. The
cyclone overflow slurry from the cyclone cluster gravity flows to a trash screen, with the screen
undersize reporting to the pre-aeration tank prior to leaching. Trash screen oversize discharges to a
collection area for removal. A sump pump will be provided in the grinding area to facilitate clean-up.
The pump will discharge into the cyclone feed hopper. Figure 17-5 shows the SAG, ball mill and the
high-angle pebble conveyor, along with the future pebble crusher location.
Figure 17-5: Grinding and Gravity Concentrate and Intensive Leach Area
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 366
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
17.3.6 Gravity Concentration and Intensive Cyanide Leach Circuit
A portion of the cyclone underflow reports to the gravity circuit scalping screen with an aperture of 2
mm. The scalping screen oversize returns to the ball mill feed. The scalping screen undersize reports
to the centrifugal concentrator, which is operated in a semi-batch process. The gravity concentrate is
collected in the concentrate storage cone and is flushed into the intensive cyanidation leach reactor
for leaching. The tails of the centrifugal concentrator reports to the ball mill feed.
The intensive cyanidation leach unit (ICU) extracts the contained gold in the gravity concentrate by
intensive cyanidation. The leach solution from the ICU, containing a mixture of NaCN, NaOH, and
Leach Aid, is prepared in a heated ICU reactor vessel feed tank. The leached residue from the reaction
vessel is washed and returned to the cyclone feed hopper. The pregnant solution from the ICU is sent
to the ICU pregnant solution tank in the gold room for electrowinning and smelting. Figure 17-5 shows
the gravity & intensive leach area adjacent to the grinding area.
17.3.7 Leach and Adsorption Circuit
The leach and adsorption circuit consists of a pre-aeration tank, four leach tanks, and six CIP tanks.
The circuit is gravity fed from the trash screen undersize to the pre-aeration tank. The pre-aeration
and leach tanks are the same dimensions, providing a total residence time of 18 hours at 43% solids
slurry density in the leach tanks. Pre-aeration passivates reactive sulphides such as pyrrhotite and
pyrite, which increases available oxygen and improves cyanide consumption in the leach stage. The
leach tanks allow the gold-bearing solids to encounter cyanide and oxygen, dissolving the gold from
the ore into solution in the form of stable gold-cyanide complex. The tanks are oxygen sparged to
maintain elevated dissolved oxygen levels up to 20 mg/L. Hydrated lime is added to the pre-aeration
tank and first leach tank to reach the target pH range of 10.5 to 11. The discharge of the leach tanks
gravity flows to the first CIP tank. Figure 17-6 shows the aeration and leach tanks in series.
Figure 17-6: Pre-Aeration and Leach Tanks
The six CIP tanks provide a total residence time of 6 hours at 43.2% w/w density. Carbon from the
carbon regeneration circuit is returned to the last CIP tank. The carbon is then circulated counter
current to the slurry flow with carbon transfer pumps. Carbon is maintained at a concentration of 25 g/l
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 367
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
of slurry. Mechanically swept carbon retention screens in each CIP tank keeps carbon in the tank,
while allowing slurry to continue to flow by gravity downstream. The carbon in the first CIP tank is
pumped to the loaded carbon screen in the carbon acid wash, elution, and regeneration circuit. The
slurry from the last CIP tank gravity feeds to the cyanide detoxification tanks. Figure 17-7 shows the
CIP tanks, along with the detoxification tanks, acid wash & elution columns, regeneration kiln and gold
room areas.
Figure 17-7: CIP and Detoxification Tanks, Acid Wash and Elution Columns, Regeneration Kiln, and Gold Room Areas
17.3.8 Carbon Elution and Regeneration Circuit
Slurry from the first CIP tank is pumped to the loaded carbon screen. The oversize from the loaded
carbon screen flows by gravity and is directed to the acid wash column with 4 t carbon capacity. Screen
undersize is returned to the No. 1 CIP tank. Prior carbon elution, acid soluble foulants that have loaded
onto the carbon surface are dissolved in a dilute acid washing stage. Hydrochloric acid is diluted with
fresh water in an in-line mixer to provide the required acid wash solution concentration and injected
into the acid wash column. Acid solution is circulated through the acid wash column and then rinsed
with fresh water, prior to transfer to the elution column. The spent acid solution and rinse water are
drained to the acid wash area sump and transferred to the cyanide detoxification tanks.
The Anglo American Research Laboratory (AARL) process is used for the gold stripping (elution) from
loaded carbon. The elution system comprises an elution column, strip eluate tank, strip eluate pump,
and an elution heater package. This equipment operates in a closed loop with the electro-winning cell
located inside the gold room.
The elution process begins with filling the elution column with a set volume of water, along with cyanide
and sodium hydroxide to obtain a strong NaCN and NaOH solution. The strong solution is heated to
120°C, and allowed to-soak in the column for 30 minutes.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 368
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
The pre-soak solution is transferred to the pregnant eluate tank. Elution water is heated to 120°C and
pumped through the heat exchanger and elution heater. The heated water is then cycled through the
elution column to the pregnant eluate tank.
After completion of the elution process, stripped carbon is transferred from the elution column to the
carbon dewatering screen. The screened carbon is fed into the kiln feed hopper and a screw feeder
meters the carbon into the carbon regeneration kiln. The carbon regeneration kiln is propane-fired,
and is a horizontal, rotary unit designed to regenerate 100% of the stripped carbon at a temperature
between 700-750°C.
Regenerated carbon discharges by gravity from the kiln to a quench tank to cool down and is then
transferred to the carbon sizing screen. The barren carbon is screened and the oversize carbon reports
to the last tank in the adsorption circuit. Fine carbon is discarded to the cyanide detoxification tanks.
17.3.9 Electrowinning and Gold Room
Gold recovery is performed by electrowinning pregnant solutions from the ICU and the elution circuits
and smelted into doré bars. The process takes place within the gold room, a secure area that is
equipped with access control, intruder detection, and closed-circuit television equipment.
The pregnant solution from ICU and elution are each processed in dedicated electrowinning cells, with
their own pregnant solution tanks and pumps recirculating the solution through the electrowinning cells
fitted with stainless steel mesh cathodes. Gold is deposited onto the cathodes and the resulting barren
solution is pumped to the first leach tank.
Gold flake washed from the cathodes and cell floor sludge are drained from the electrowinning cell to
a sludge hopper. The sludge is then pumped to a plate and frame filter. The filter cake (gold/silver
sludge) is loaded from the sludge filter into trays on the electrowinning sludge trolley. The sludge is
then oven dried, combined with fluxes, and smelted in a barring furnace to produce gold doré bars.
17.3.10 Cyanide Detoxification
The CIP tails gravity flows to the cyanide detoxification distribution box, which is combined with
washdown water from different areas in the plant and feeds two detoxification tanks in parallel. The
tanks provide a total residence time of one hour each to reduce the weak acid dissociable cyanide
(CNWAD) concentration from 200 mg/L to less than 1 mg/L to comply with the environmental
requirements prior to deposition in the tailing storage facility.
The cyanide detoxification method used is the SO2/O2 process. The process requires the use of
oxygen, lime, copper sulphate, and sodium metabisulphite (SMBS) as the SO2 source. Oxygen is
sparged into each tank bottom and the tanks have intensive agitation to ensure completion of the
reactions. Once the slurry is treated, the tailings gravitate to the carbon safety screen. The carbon
safety screen oversize is collected into a carbon bag for re-use or disposal, while the screen undersize
transfers to the tailings thickener distribution box.
17.3.11 Tailings Thickening and Filtration
Prior to deposition to the DSTF, the tailings must be thickened and filtered to achieve the 15% w/w
moisture content for dry stacked tailings. The tailings thickening occurs at the MDZ process plant, with
the combination of the tailings slurry, returning filter press filtrate water, and any other washdown water
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 369
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
from the plant areas in the tailings thickener distribution box. Flocculant is added to improve settling
rates and achieve an underflow density of 60% w/w solids. The tailings thickener overflow gravity feeds
to the process water tank for recirculation back into the process. The thickened tailings report to the
filter feed tank for pumping to either the paste backfill plant or the tailings filter plant located next to the
main plant. Figure 17-8 shows the tailings thickener and the thickener underflow storage tank area.
Figure 17-8: Tailings Thickener and Thickener Underflow Storage Tank Area
The tailings filter plant receives thickened tailings in the filter feed tank. Two horizontal plate and frame
pressure filters are used to treat the tailings and reduce the moisture content below the 15% w/w target
for dry stacked tailings. The filters are situated to allow the filter cake to drop below the filter floor to a
filter cake loadout bunker and transferred by a front-end loader to the DSTF equipment. Figure 17-9
shows the tailings pressure filter plant area.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 370
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Figure 17-9: Tailings Pressure Filter Plant Area
17.3.12 Reagents
Lime
The hydrated lime is supplied in bulk bags and is lifted using a frame and the mobile crane onto the
bag splitter located above the lime mix/storage tank. The tank will be partially filled with process water
at the beginning of the mixing sequence to achieve a slurry concentration of 20% w/w. The lime slurry
is used as a pH modifier and is pumped by the lime distribution pumps to the various locations in the
plant through a ring main. Unused lime returns to the lime mix/storage tank. Spillage in the lime area
is collected in the lime sump and pumped to the cyanide detoxification distribution box.
Sodium Cyanide
Sodium cyanide is used as a gold lixiviant and will be supplied in briquette form in 1 t bulk bags shipped
in boxes. The boxes will be offloaded by forklift and stored in a limited access cyanide storage facility
that is part of the cyanide mixing area. The sodium cyanide will be dissolved into a 20% w/w solution.
Sodium cyanide is in briquettes and is pre-buffered with sodium hydroxide to ensure high solution pH
and prevent hydrogen cyanide formation in the mixing system.
The mixed solution gravitates to the cyanide holding tank that is sitting under the mix tank. The cyanide
solution is pumped by the sodium cyanide pumps to dosing points in leaching and elution. Spillage in
the sodium cyanide area is collected in the sodium cyanide sump and pumped to the cyanide
detoxification distribution box.
Copper Sulphate
Copper Sulphate is used as a catalyst for the cyanide detoxification process and will be supplied in 25
kg bags. The copper sulphate mixing tank will be partially filled with process water and the copper
sulphate will be manually loaded into the tank by way of a bag splitter. The copper sulphate will be
dissolved into 20% w/w solution concentration and then gravitates to the copper sulphate storage tank
under the mixing tank. The copper sulphate solution is distributed by the copper sulphate distribution
pump to the cyanide detoxification distribution box. Spillage in the copper sulphate area is collected in
the copper sulphate sump and pumped to the cyanide detoxification distribution box.
Sodium Metabisulphite (SMBS)
SMBS is the source of SO2 in the SO2/O2 process for cyanide detoxification and will be supplied in
bulk bags. The SMBS mixing tank will be filled with process water and the SMBS will be lifted by mobile
crane on to the bag splitter above the mixing tank. The SMBS will be dissolved into a 20% w/w solution
concentration and the solution will be transferred to the SMBS storage tank by the SMBS transfer
pump. The SMBS solution is pumped by the SMBS dosing pump to the cyanide detoxification
distribution box. Spillage in the SMBS area is collected in the SMBS sump and pumped to the cyanide
detoxification distribution box.
Sodium Hydroxide
Sodium hydroxide is used as a pH modifier and will be supplied in liquid bulk containers at a
concentration of 50% w/w. A sodium hydroxide container and dosing pump will be located at the
intensive cyanide leach area to dose directly to the ICU. A second container will be located at the
reagent area for dosing to the pregnant elution and ICU solution tanks in the electrowinning & gold
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 371
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
room area and to the sodium cyanide mixing tank. Spillage in the intensive cyanide leach area is
collected in the intensive cyanide leach sump and pumped to the first leach tank. Spillage in the sodium
hydroxide area is collected in the sodium cyanide sump.
Hydrochloric Acid
Hydrochloric acid is used in the acid wash cycle to remove any foulants that may be present on the
carbon surface prior to elution. The hydrochloric acid will be supplied in liquid bulk containers at a
concentration of 33% w/w and will be dosed to the acid wash column. Spillage in the hydrochloric acid
area is collected in the hydrochloric acid sump trap.
Sulphamic Acid
Sulphamic acid is used in the strip elution to remove calcium carbonate scale from heat exchangers.
The sulphamic acid will be supplied in liquid bulk containers at a concentration of 33% w/w. Spillage
in the sulphamic acid area is collected in the sulphamic acid sump trap.
Flocculant
Flocculant is used to help improve the settling of solids in the tailings thickener and will be supplied in
a powder form in bulk bags. A self-contained flocculant metering and mixing system will be installed
for controlled batch mixing at a solution strength of 0.5% w/w using process water. The mixed
flocculant solution will be piped to the flocculant storage tank below and dosed to the tailings thickener
distribution box, where it will be further diluted at a ratio of 1:10 flocculant to process water to aid in
flocculant dispersion. Spillage in the flocculant area is collected in the flocculant sump and pumped to
the tailings thickener distribution box.
Gold Room Fluxes
Borax, Nitre, Silica, and Sodium Carbonate are the fluxes used in the gold room and will be supplied
as dry solids in 25 kg bags.
Anti-Scalant
Anti-Scalant is used to inhibit scale build-up in the process water lines and will be supplied in liquid
form in drums. The drum will be located beside the process water tank and dosed into the process
water tank by metering pump.
Activated Carbon
Activated carbon will be supplied in solid granular form in bulk bags. The activated carbon will be
added to the carbon quench tank, by way of bag breaker, when needed to make up any carbon losses.
Oxygen
Oxygen is injected into the pre-aeration and leach tanks to help enhance the cyanide reaction with the
slurry and improve the dissolution of gold. Oxygen is also used in the cyanide detoxification to react
with SO2 and cyanide to breakdown the cyanide compounds. Oxygen is supplied in liquid form and
delivered to the oxygen storage tanks. The liquid oxygen flows through a vaporizer to transform the
liquid to gas for distribution. Dosing is done through spargers to the bottom of the pre-aeration, leach,
and cyanide detoxification tanks.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 372
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
17.3.13 Services and Utilities
Process/Instrument Air
High-pressure air is produced by compressors and is stored in an air receiver tank to meet the plant
requirements. A portion of the high-pressure plant air is passed through an air dryer to supply
instrument air to the various field instruments in the plant. The primary crusher is equipped with a local
air compressor and air receiver tank to provide the underground installation with compressed air. The
tailings filter plant is equipped with high- and low-pressure air compressors and receivers to provide
the necessary air for diaphragm pressing and air blowing cycles for the vertical plate pressure filters.
Diesel Fuel
The diesel storage area is supplied and maintained by the supplier. The diesel is used in various
mobile equipment and vehicles related to operations and maintenance in the process plant.
Propane Gas
The propane storage area is supplied and maintained by the supplier. The propane gas is used as the
energy source for the elution column heating and the kiln heater.
17.3.14 Water Supply
Fresh Water Supply System
Fresh water is supplied to the process plant fresh/fire water tank. The fresh water is used in various
reagent areas and locations in the process that require low suspended solids and salt content. The
fresh/fire water tank also provides emergency fire water. A freshwater truck supplies the tailings filter
plant with makeup water for the gland, fire, and potable water needs.
Process Water Supply System
Process water is mainly supplied from the tailings thickener overflow launder, with makeup water being
provided by the site runoff pond and/or the fresh water tank. Process water is used throughout the
plant, mostly in the grinding circuit for pulping the ore to allow for transport, pumping, and classification.
A dedicated process water pump provides the tailings filter plant with process water for cloth wash and
washdown water.
Gland Water Supply System
Gland water is used to keep all slurry pump glands clean from abrasive solids. A dedicated pump is
used to provide most of the slurry pumps, with an additional booster pump for the tailings pipeline
pumps to achieve the higher operating pressure required for the pump application. The tailings filter
plant has a separate gland water pump to provide water to the filter feed slurry pumps
17.3.15 Operating Costs
Summary
The operating cost estimates for the process is presented in Q2 2020 US Dollars (USD or $). The
estimate was developed to have an accuracy of 25%. An additional operating cost of $6.38/oz Au sold
will be applied in the financial model for the refining and transportation charges, based on the current
rates applicable to the client from their existing operation in the area.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 373
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
The operating cost estimates for the life of mine are included in Table 15.1. The overall life-of-mine
operating cost is $16.8M over 16 years, or $11.51/t of ore milled.
Basis of Estimate
The assumptions made in developing the operating costs include:
• Cost estimates are based on Q2 2020 pricing without allowances for inflation.
• For material sourced in Colombian Pesos (COP), an exchange rate of 3300 COP per USD
was assumed.
• Fuel costs were provided by the client based on the contracts for the client’s existing plant.
The diesel cost used was $0.63/L and propane cost used was $0.90/Kg.
• The power costs were provided by the client based on the contacts for the client’s existing
plant. The unit price of $0.09/kWh is from the hydro provider (285 COP/kWh).
• The labor is assumed to primarily come from the local region around Marmato
Processing Operations
The costs for processing are generated from the labor, power, reagents and consumables,
maintenance, laboratory and assays. An overall average annual cost was estimated to be $18M/y or
$12.31/t milled.
A breakdown of the Opex and unit costs are presented below in Table 17-7.
Table 17-7: Operating Cost Summary
Cost Center US$M US$/t
Reagents & Consumables 10.1 6.95
Plant Maintenance 0.86 0.59
Power 5.34 3.66
Laboratory 0.23 0.16
Labor (O&M) 1.30 0.89
Vehicles 0.10 0.07
Total 18.0 12.31
Source: Ausenco, 2020
Consumables
The consumables were based on reagent consumptions, process consumables, and propane utilities
for heating, using nominal consumption rates. Individual reagent costs were obtained through existing
pricing from the client’s operation and alternative sources. The total consumables costs are $10.1M/y
or $6.95/t milled.
Maintenance
The maintenance costs for the process were calculated based on process capital costs for each area
using a factor between 4 and 5%. The total maintenance costs are $0.86M/y or $0.59/t.
Power
The power consumption was estimated from the average power utilization of all major equipment
included in the process. The annual power usage was calculated at 61,562.3 MWh/y at a unit cost of
$0.09/kWh (285 COP/kWh) based on the current utility rates provided to the client from the energy
provider ISAGEN. The total power costs are $5.34M/y or $3.66/t.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 374
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Laboratory
The laboratory costs were based on client and in-house data. The costs do not include the mine
samples or labor to operate the laboratory. The total laboratory costs are $0.23M/y or $0.16/t.
Labor (Operation & Maintenance)
The process labor requirements for the operation are 107 employees over multiple shifts. Most of the
workers will be local, with specialized positions potentially drawing from other regions in Colombia. For
the purpose of the labor costs, the compensation used was a salary rate with a 60% burden.
An organizational roster listing the labor requirements for the process operation and maintenance is
shown in Table 17-8. The total labor costs are $1.3M/y or $0.89/t.
Table 17-8: Operations and Maintenance Manpower Schedule
Labor/Contractor Summary Rotation #/Shift # Shifts Quantity
Total Process Labor 36 76 107
Process Upper Management
Mill Manager 10.5-hour shifts 1 1 1
Mill Maintenance Superintendent 10.5-hour shifts 1 1 1
Mill Chief Metallurgist 10.5-hour shifts 1 1 1
Mill Administrative Assistant 10.5-hour shifts 1 1 1
Subtotal 4 4 4
Mill Operations
Gold Room Supervisor 12 hour shifts 1 3 3
Gold Room Operator 12 hour shifts 1 3 3
Shift Supervisors 12 hour shifts 1 3 3
ROM / Crushing Operator 12 hour shifts 1 3 3
ROM / Crushing Assistant Operator 12 hour shifts 2 3 6
Control Room Operator 12 hour shifts 1 3 3
Grinding / Gravity Operator 12 hour shifts 1 3 3
Tailings Operator 12 hour shifts 2 3 6
CIP Operator 12 hour shifts 1 3 3
Reagent Operator 12 hour shifts 1 3 3
Subtotal 12 30 36
Technical Services
Junior Metallurgical Engineer 10.5 hour shifts 1 1 1
Metallurgical Technician 10.5 hour shifts 2 1 2
Chemist 10.5 hour shifts 2 1 2
Sample Preparers 12 hour shifts 2 3 6
Analytical Technicians 12 hour shifts 2 3 6
Subtotal 9 9 17
Mill Maintenance
Maintenance Planner 10.5 hour shifts 2 1 2
Maintenance Foreman 12 hour shifts 1 3 3
Mechanics 12 hour shifts 3 3 9
Welders 12 hour shifts 1 2 2
Electricians 12 hour shifts 2 3 6
Instrument Technician 12 hour shifts 1 3 3
Trades Assistants 12 hour shifts 1 3 3
Subtotal 11 18 28
Source: Ausenco, 2020
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 375
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Vehicles
The vehicle costs are based on a scheduled number of light vehicles and mobile equipment, including
fuel, maintenance, replacement parts, and annual insurance fees. Fuel costs were established based
on utilization and a diesel cost of $0.55/L. A breakdown of the vehicles and equipment is shown in
Table 17-9.
Table 17-9: Light Vehicles and Mobile Equipment Summary
Category Vehicle Type Number Utilization
Light Vehicles
4 X 4 Crew Cab 1 2h/d 5 days per week
4 X 4 Pickup 1 2h/d 7 days per week
4 X 4 Crew Cab 1 2h/d 5 days per week
4 X 4 Pickup 1 2h/d 7 days per week
Mobile Equipment
Skid Steer Loader 1 5h/d 7 days per week
3 t All Terrain Forklift 1 5h/d 7 days per week
35 t All Terrain Crane 1 0.5h/d 5 days per week
It 30 Front End Loader 1 5h/d 5 days per week
Elevated Work Platform 1 3h/d 7 days per week
5t Hiab Flat Bed Truck 1 3h/d 7 days per week
Source: Ausenco, 2020
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 376
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
18 Project Infrastructure
18.1 General Site Access
The Project is in the Municipality of Marmato in Caldas. The Marmato Project is located on the eastern
side of the Western Cordillera (Cordillera Occidental) of Colombia on the west side of the Cauca River.
The Marmato Project is located approximately 125 km south of Medellín, the capital of the department
of Antioquia, Colombia. Medellín is the second largest city in Colombia with a population of
approximately 2.5 million. The Project is located in the department of Caldas near El Llano.
Figure 18-1 shows the location of the Project.
Source: CGM, 2017
Figure 18-1: Marmato Project Location
Primary access to the site is via the Pan American Highway, Colombia Highway 25. The road is a
paved two lane improved highway that winds through the mountainous area south of Medellín and
then follows the Cauca River to the turn off to the Project. The route from Medellín is via Itaguí (7 km),
Caldas (12 km), Alto de Minas (13 km), Santa Barbara (27 km), La Pintada (26 km), La Guaracha del
Rayo (32 km), and then a turn onto a secondary road to the community of El Llano that is the
community closest to the Project. From El Llano, the road is paved but partially single lane another 2
km to the site security gate. An improved dirt road continues up the mountain another 4 km to the
community of Marmato, where the artisanal miners are working the Zona Alta portion owned by Gran
Colombia. Approximately 40% of the 1,200 employees currently employed by the Project live in El
Llano, with the remainder traveling to work from various communities in the area.
The Pan American Highway continues south and east 90 km to another large regional city, Manizales,
and then on another 270 km to Bogotá, the capital of Colombia. Air access through international and
regional airports is available in Medellín, Manizales, and Bogotá.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 377
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Field personnel for the exploration program have been employed from the towns of Marmato and El
Llano and neighboring municipalities. In the long term, personnel currently working on the large
number of small scale mines and from the surrounding region would be able to supply the basic
workforce for any future mining construction and operation.
18.2 Marmato Existing UZ Operations Infrastructure
The existing operating Marmato UZ operations have fully developed site infrastructure. The UZ
operations have an access road, onsite roads to access facilities, mine portals, processing facility,
administrative and offices, shops, warehousing, electrical maintenance buildings, helicopter pad, camp
facility, compressed air systems, ventilation systems, sand backfill system for underground, tailings
storage facilities, water supply, mine pumping systems, electrical supply and distribution, solid waste
handling facilities, septic systems, security, and communications systems.
18.2.1 Existing Project Access
The general Marmato Project access is described in section 18.1. The secondary road to the existing
operation and the general layout of the facilities is shown in Figure 18-2.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 378
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SRK, 2019
Figure 18-2: Marmato General Access and Major Facilities
18.2.2 Existing Project Facilities
The UZ operations have a fully developed infrastructure and facilities that include a security checkpoint
that provides access to the office and administrative office area. The facilities include employee
motorcycle parking, meeting area, multiple shops and warehouses, a camp with cafeteria, exercise
and sports field, equipment storage yards, compressor station, welding shop, a 500 kW backup
generator, processing plant, underground mine, explosives storage a short distance from the mine that
is managed by the military, main power substation and distribution powerlines with motor control
centers at key loads. The site has three portals that access the mine workings. A yard that has rail
through it near the portal allows servicing of the mine cars and locomotives. Figure 18-3 shows the
overall plant and camp area.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 379
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: CGM, Modified by SRK, 2019
Figure 18-3: Marmato Existing Project Site Map
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 380
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
18.2.3 Energy Supply and Distribution - Existing Marmato Project
Power to the site is provided through the Colombian power company Central Hidroeléctrica de Caldas
(CHEC), a subsidiary of Empresas Públicas de Medellín (EPM) through existing local substations.
Substantial transmission capacity is available in the region around the Project, with energy provided
over the transmission system by the third largest electricity producer in Colombia, ISAGEN.
The main substation feeding the Project has a capacity of 40 MVA and supplies the Project at 33 kV
through the El Dorado substation to the CGM principal substation. The 8.1 MVA main CGM substation
has six transformers that provide power to the mine, mill, and other facilities.
The loads supported by each transformer are provided as follows:
• Transformer 1 (2,000 KVA) steps the 33 kV power down to 13.2 kV and feeds the three mine
substations that in turn feed the compressors, pumps and offices/shops at 440 VAC
• Transformer 2 (2,000 KVA) feeds the mine at 13.2 kV through three separate mine
transformers that in turn feed the various mine levels, hoists, pumps, and mine equipment.
The equipment operates on 440 VAC
• Transformer 3 (600 KVA) feeds the ball mill at the processing plant at 4,160 VAC
• Transformer 4 (1,250 KVA) and 5 (630 KVA) feeds two compressors each at 440 VAC
• Transformer 6 (1,600 KVA) provides 440 VAC for the beneficiation plant
The Project one-line electrical diagram is shown in Figure 18-4.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 381
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: CGM, 2019
Figure 18-4: Marmato Electrical System Schematic
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 382
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
18.2.4 Site Water Supply
Water supply for the existing Marmato mining activities is currently provided by a combination of
underground dewatering and reclaim from the existing DSTF. The current Project has adequate water
supplies but can be challenged during dry portions of the year. The Project has contingency plans to
draw water from either the Cascabel or Cauca River, with the Cauca River being the preference and
a water supply pumping system is included in future plans for the MDZ that will support the existing
UZ operations too.
18.3 MDZ Introduction
The overall site plan can (Figure 18-5) shows the major project facilities, such as underground crusher,
underground portal, stockpiles, process plant, DSTF, mining services, accommodations, access
roads, and office buildings.
18.4 MDZ Process Plant Site Location
Process plant site is located about 3 km west by road of the ore body, on a naturally occurring plateau
having 30% east‐west and 15% north-south grade slope.
The location of the plant was selected based on the following factors:
• Proximity to the Marmato deposit, resulting in shortest length of the decline
• Utilizing a naturally occurring plateau, relatively flat comparing to surrounding terrain
• Ground stability for process plant foundations and avoiding fluvial deposit
• Minimizing upstream watershed and land slide risk
• Land availability and land agreement
The proposed plant site location was visited on Dec 5, 2019 during a site visit to the existing operation.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 383
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: Ausenco, 2020
Figure 18-5: Overall Site Plan
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 384
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
18.4.1 Site Geotechnical
At the time of completion of this report, there is no site-specific geotechnical investigation report
available for the proposed plant site. A bore hole and test pit plan were prepared based on the
proposed PFS process plant layout and location of major structures and foundations. For field
geotechnical drilling and investigation, a campaign by the geotechnical consultant is planned to be
carried out in the coming months. The PFS level design of the foundations was based on preliminary
recommendations received from IRYS Ingeniería de Rocas y Suelos S.A.S., which relied on local
geotechnical knowledge and nearby historic drillings.
Based on previous geotechnical investigations by KP (Project No. EL202-00153/07) in 2012, west of
the process plant, the ground geology consists of
• Clay/silt, some sand, medium plasticity, brown and speckled red and white, residual soil, some
visible rock over burden at varying thickness
• Rock, intrusive igneous, moderately to highly weathered, moderate to highly fractured, weak
to moderately strong, white and brown, oxidized mostly feldspar and quartz fabric
18.5 MDZ On-Site Roads and River Crossings
18.5.1 Site Access Road
The access to the process plant site will be possible via three new access roads:
• A new 400 m long, 8 m wide, E-W gravel road connecting the process plant lowest bench to
the Marmato public road will be constructed. This road will be constructed at the start of
construction to access the site.
• A new 750 m long, 8 m wide, N-S gravel road connecting the process plant lowest bench to
the camp and administration area located SW of the process plant will be constructed,
adjacent to the town of El Llano.
• A new 400 m long, 8 m wide, E-W gravel road connecting the Marmato public road the 750 m
long camp access road described above. This road will be the main access to the site.
Designed access roads incorporate use of Mechanically Stabilized Earth (MSE) retaining walls,
Gabion basket retaining walls, soil nailing and slope stabilization.
18.5.2 River Crossing
The new site access roads are crossing seasonal streams and creeks at several locations. Corrugated
steel culverts will be placed at water crossing. The culverts are sized to accommodate the peak flow
of water during a storm event.
18.6 MDZ Water Supply
18.6.1 Water Requirements
Overflow from the tailings thickener and site runoff pond decant water meet the main process water
requirements. Fresh water provides any additional make-up water requirements.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 385
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
18.6.2 Run-Off Water Collection and Treatment System
Process plant surface water will be graded to naturally drain water to connection swells and ditches
through the plant. The collected water from drainage ditches will be discharged to a 6,000 m3 capacity
lined storm water management pond (SWMP) located to the west of the plant. Water quality in the
SWMP will be monitored and tested for compliance with local environmental discharge requirements.
A Water Treatment Plant (WTP) will be placed adjacent to the SWMP to treat the water, if required,
prior to discharge to environment.
18.6.3 River Water Collection and Treatment System for MDZ and UZ
A new water collection and pumping facility designed by CGM will be constructed to remove water
from the Cauca River from a basin with a floating suction and pump into two separate systems that
will feed the UZ plant and the MDZ plant. Each of the separate systems include a raw water tank, a
sand filter, and pumps capable of pumping water from the tank through two separate pipelines, one to
the MDZ and one to the UZ. The pumps will operate at 35 L/s. The dynamic head on the UZ system
will be 207 m and the MDZ system is 294 m.
18.7 MDZ Power Supply
18.7.1 Electrical Power Source
Major electrical power will be required at the MDZ plant as all process facilities and major infrastructure
buildings are situated there. Electrical power to the MDZ plant is planned to be supplied by Central
Hidroeléctrica de Caldas S.A. (CHEC) from the Salamana 115 KV substation located 15 km away.
Site power will be obtained from a 115 KV HV line that will be provided by the local power authority up
to the MDZ plant outdoor substation. A peak demand of 28 MW is required for the facility, of which
approximately 12 MW are required for the process plant and 16 MW are required for the mining loads.
18.7.2 Electrical Distribution
The plant electrical system is based on a 4.16 kV, 60 Hz distribution. The 115 kV feed from the local
power authority will be stepped down to a 4.16 kV by 2 x 10/13.3 MVA ONAN/ONAF transformers at
the plant main substation and will supply the plant main 4.16 kV switchgear housed in the switch room
next to the plant main substation through a 4.16 kV cable bus.
For the mining load substation, the 115 kV feed from the local power authority will be stepped down
to a 13.2 kV by 1 x 25/33.25 MVA ONAN/ONAF transformer and will supply the mining substation
through a 13.2 KV overhead line.
The following substations/electrical rooms will be provided:
• Plant main HV switchyard (outdoor substation)
• Process Plant E-Room
• Grinding Plant E-Room
• Primary Crusher E-Room
• Secondary Crusher E-Room
• Reagents & Process plant E-Room
• Tailings & Filtration E-Room
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 386
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Electrical rooms will house the 4.16 KV switchgear, MV VFDs, 440 V motor control centers (MCCs),
LV VFDs, plant control system cabinets, lighting transformers, various distribution boards and UPS
power distribution.
Overhead power lines of 4.16 kV will provide power to various remote facilities, ancillary buildings and
camp. Pole mounted and/or pad mounted transformers will step down the voltage at each location,
and supply 440V to the respective remote facilities, ancillary buildings and camp.
18.7.3 Electrical Rooms
Electrical buildings will be prefabricated panel buildings to minimize installation time on site. The
buildings will be installed on a structural framework over 2 m above ground level to allow for bottom
entry of cables into electrical switchboards, panels, MCCs and cabinets. The electrical buildings will
be installed with HVAC units and suitably sealed to prevent ingress of dust. They will be in the process
plant area and as close as possible to the main load points, to reduce cost. In order to reduce the size
of the E-Rooms and avoid heat issues, the transformers for each electrical room will be oil natural air
natural (ONAN) type and installed just outside each electrical room.
18.7.4 Transformers
The main power transformers are 115 kV/13.2 kV and 115 kV/4.16 kV and will be ONAN, with
provisions for future oil natural air forced (ONAF), cooling configuration and will have either OLTC (on-
line tap changer) or external voltage regulators. All plant 4.16 kV/440 V distribution transformers will
be ONAN, with provisions for future ONAF, cooling configuration and will have a de-energized tap
changer.
18.7.5 Standby/Emergency Power Supply
The site is provided with a 1 MW standby diesel generator sized to supply critical process loads and
life safety systems. The standby diesel generator is located close to the process plant main substation
and connected to the 4.16 kV main substation switchgear. In this way, a single generator set can
supply standby power to all facilities using the normal power distribution system.
18.7.6 Ball and SAG Mill Drives
In this study, the SAG and ball mill motors are equipped with liquid rheostat and use a slip energy
recovery starting method to minimize voltage drop impact on the utility supply system during motor
start-up. A PWM-based slip energy recovery system on the SAG mill motor will provide variable speed
and energy recovery.
Two 1 MVAR harmonic filters and capacitor banks have been added on the 4.16 kV main busbars to
achieve a 0.95 PF at the supply end, to minimize harmonic impact on the power distribution system.
18.7.7 Redundancy
Redundancy for the site electrical power distribution system has been minimized to optimize capital
costs. Warehouse spare transformers are being carried to minimize long shutdowns in the unlikely
event of transformer failure, rather than installing standbys.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 387
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
18.8 MDZ Mine Operations Support Facilities
18.8.1 Mine Administration and Dry Building
The main mine administration building will be a two-story modular construction building, 850 m² each
floor, located at the camp and administration area. 50% of the ground floor will be used as the mess
hall, and the balance of the first floor and second floor will house cubical, shared and private offices
for mine administrative personnel.
The mine dry building will be a single-story modular construction building with a 550 m² footprint,
located at the camp and administration area. This building is used primarily by the local workforce
employed as miners and plant operators. The workforce will arrive to this facility at the beginning of
each shift and will be transported from the dry facility to the work area (process plant and mine portal)
by bus. This is intended to limit traffic of private vehicles and motor vehicles within the process facility.
18.8.2 General Maintenance Building
The general maintenance building is a 20 m wide, 50 m long, and 12 m high, pre-engineered (metal)
building with 20 tonne capacity overhead crane. All the process plant and mine equipment repair and
maintenance will be performed in this facility.
18.8.3 Truck Wash Facility
The underground mining trucks will be washed on a designated truck wash pad area adjacent to the
general maintenance building. The pad consists of concrete slab-on-grade with a water collection
sump.
18.8.4 Truck Fuel Facility and Equipment Ready Line
The area in front of the general maintenance shop will be the designated ready line parking for mobile
equipment.
The diesel fuel storage and dispensing facility will be located in this area, with adequate fire separation
to comply with NFPA and local fire code.
18.8.5 Explosives Storage
The explosive storage shed will be placed at an isolated secure area located between the process
plant and camp/administration area.
18.9 MDZ Process Support Facilities
18.9.1 Mill Administration Office and First Aid Facility
The mill administration office and first aid facility will be a single-story modular construction building,
with a 250 m² footprint, located near the process plant.
18.9.2 Laboratory
The laboratory will be an assortment of prefabricated, single-story, modular buildings on precast
concrete blocks, with a 140 m² footprint. It will house the equipment for typical site assays.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 388
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
18.9.3 Warehouse and Storage Yard
The warehouse building is a 16 m wide, 28 m long and 12 m high, pre-engineered (metal) building
with a 10 t capacity overhead crane. This building will be used for the storage of process reagents,
consumables and sensitive equipment that require storage indoors.
The area south of the future pebble crusher structure is designated as an outdoor storage yard which
will be used as a laydown area during construction.
18.9.4 Gatehouse and Weigh-Scale
The security and gatehouse building are a 12 m wide, 3 m long and 3 m high, prefabricated building
located near the process plant at the main entry to the process area.
18.10 Common Support Facilities
18.10.1 Man Camp
The camp will be located south of the process plant, and north of the town of El Llano. The camp will
comprise a three-story modular construction building which will house construction personnel during
construction and will transition to housing plant operation personal after commissioning.
The camp is sized for a total of 466 personnel. There will be 58 personnel in single-bed rooms, 18 in
two-bed rooms and 390 in six-bed rooms. The camp facility also includes a kitchen and recreation
area.
18.11 MDZ Support Facilities
18.11.1 Communications
All PLCs within the plant will be linked to a common ethernet communications network, where practical.
The backbone of the communications network will be via fiber optic cabling, with spare cores provided
for future use. Copper CAT 6 cabling will be used for the final connection to individual points.
The main hub for all PLC communication will be installed in the plant services switchroom. Fiber optic
breakout boxes, ethernet switches, media converters and power supplies will be provided and installed
wherever required.
All I/O signals for the PLCs will be via standard digital and analog modules. The PLC equipment
installed within each area will function autonomously, such that a failure of the PLC in one plant area
will not affect the other areas.
18.11.2 Wastewater Treatment
Two modular containerized sewage treatment plants will be collecting and treating the sanitary sewage
for the project. One at an average 50 m3/day processing capacity located in the camp/admin area and
one at an average 10 m3/day located at the process plant.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 389
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
18.11.3 Solid Waste Disposal
Solid wastes will be separated at the site by type and stored in a designated waste storage area for
disposal in regulatory approved disposal sites. Underground waste rock will be utilized for construction
of the DSTF facilities (see section 18.13). All other waste rock will be used for backfill in secondary
stopes underground.
18.12 MDZ Site Preparation
18.12.1 Site Earthwork
The process plant area will be graded to five cascading benches following the natural topography as
described in section 18.4:
• Bench 1: Filtration plant
• Bench 2: Process plant
• Bench 3: Reclaim tunnel and future pebble crusher
• Bench 4: Secondary Crusher
• Bench 5: Mine Portal
The pads will be mainly cut in west of each pad and filled in east of each pad. The transition between
each pad will be constructed of 1V:1.5H sloped grade, soil nailed stabilized slopes and Mechanically
Stabilized Earth (MSE) retaining wall as required, following the footprint for process plant layout.
The pads are accessed via plant roads at the south edge of the process plant pads. The in-plant roads
have a slope of 10% to 14% max.
18.12.2 Site Foundations
The grading of the process plant benches is designed to have all major foundations placed in cut,
allowing the foundation to rest on undisturbed competent ground or bed rock. Only light foundations
are placed on compacted fill.
All foundations are designed as shallow foundations. No deep foundation (piles) or rock are considered
in the design. Suitability of shallow foundations shall be confirmed based on the findings of the field
geotechnical investigations
18.13 MDZ Cemented Paste Backfill Plant
The mining method selected for the MDZ requires the use of cemented paste backfill to support the
stopes and achieve the required mineralized material recovery. The paste backfill plant is located on
the surface of a bench near the portal of the MDZ. The paste backfill is made from a combination of
tailings, water and cement binder.
Agitated tailings from the filtered tailings feed tanks at the MDZ plant are pumped approximately 400 m
by two 6 by 4 centrifugal transfer slurry pumps in series to the agitated paste filter feed tank at the
paste plant through a 200 mm NB HDPE DR9 overland pipeline.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 390
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
The thickened tailings are dewatered in vacuum disc filters using a flocculant as a filter aid. The filter
cake is weighed and transferred to the paste backfill continuous twin-shaft mixer. The filter cake, water,
and cement binder (either 4% for low strength or 7% for high strength paste) are combined in the mixer
and then a hydraulic piston pump pumps it underground through a pipeline down the MDZ decline to
the underground booster pump station discussed in Section 16.5.6.
The plant has a process water tank, a freshwater tank and two 170 m3 binder (cement) storage silos
that store approximately 24 hours of cement required for the operation. Cement is delivered in 25 t
bulk cement trucks that are available seven days per week and 24 hours per day from a local supplier.
A shotcrete plant is located at the south end of the pad adjacent to the paste plant.
The plant general arrangement is shown in Figure 18-6. The surface plant 3D layout can be seen in
Figure 18-7.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 391
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: Paterson & Cooke, 2020
Figure 18-6: Paste Plant General Arrangement
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 392
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: Paterson & Cooke, 2020
Figure 18-7: Paste Plant 3D Layout
18.14 Site Water Management
Water supply for the existing Marmato mining activities is currently provided by a combination of
underground dewatering and reclaim from the existing DSTF. During the wet season, water from the
existing tailings and excess mine dewatering flows are discharged to the Cascabel River under existing
permits. Additionally, water from the flotation tailings is recovered and used as part of the water supply
for the existing UZ mine. The current operation has adequate water supplies but can be challenged
during dry portions of the year.
Additional water management infrastructure is planned to be in-place prior to the start of the MDZ
project, including additional pumping from the UZ in the short term, a pumping station on the Cauca
River to supply both the UZ and the MDZ, and a water treatment plant to be constructed in 2021/2022
to manage tailings discharges.
Site water management for water discharges from the DSTF are discussed in detail in the DSTF design
section (Section 18.15.3), but in general have been developed to collect seepage water and retain
runoff within the DSTF footprint for reuse in the process and divert run-on to the facility from upgradient
areas around the DSTF. Concurrent reclamation of the DSTF surface will allow non-contact runoff
from the facility to be discharged to the downstream drainages.
18.14.1 Water Supply
The water for the MDZ plant and mine will be supplied by a combination of groundwater from the mine,
recycled water from the existing DSTF and planned DSTF, and fresh water from the Cauca River.
Water Balance Modeling
The water balance was developed to produce a makeup demand for water at the existing UZ
processing plant and the proposed MDZ processing plant. Water to meet the demands could be
sourced from excess water at the existing DSTF, contact water produced by the planned DSTF,
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 393
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
expected underground dewatering as described in Section 16.3 or an external freshwater source,
prioritized in that order. The model also estimated if excess water would result from the existing DSTF
or planned DSTF contact water and/or the underground dewatering exceeding the makeup demand.
SRK assumed that discharges from the underground can be discharged if monitored, and discharges
from the DSTFs can be discharged with monitoring and control of suspended solids and cyanide. This
is further addressed in Section 20, Environmental Studies.
The model assumes that tailings from the MDZ Plant will be dewatered using filters and the resulting
water recirculated into the process. Conversely, once the DSTF are operating, tailings from the UZ
plant will be delivered to the existing DSTF sites, drained and dried before being re-handled to the
planned DSTF. The resulting moisture content delivered to the DSTF will be roughly similar for both
streams of tailings.
The water balance indicated that the water produced at the existing DSTF, either during operations of
the existing DSTF or during the re-handling stage, will be consumed at the UZ Plant during operations,
but discharges will be required after the UZ plant operations have ceased. Drain down from the
planned DSTFs will also be consumed at the process plants, but surface water runoff from the planned
DSTF during large storm events will occasionally exceed the makeup demand at the process plants.
With limited storage available at site, excess water from the planned DSTF would need to be
discharged during unusually wet periods.
Source: SRK, 2019
Figure 18-8: Makeup and Demand at the Upper Zone Process Plant
0
500
1000
1500
2000
2500
2020 2022 2024 2026 2028 2030 2032 2034 2036 2038
Flo
ws (
m3
/da
y)
Time
Water Supply and Demand at the Upper Zone Plant
Mean
Upper Zone Plant Water Demand Reclaim from Existing DSTF to UZ PlantReclaim from DSTF to UZ Plant Dewatering to UZ PlantFreshwater to UZ Plant
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 394
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SRK, 2019
Figure 18-9: Makeup and Demand at the MDZ Process Plant
The projected underground dewatering flows (3,500 to 7,500 m3/day) consistently exceed the total
demand for water at the plant (500 to 3,600 m3/day) by a factor of two or more and excess underground
dewatering is expected to be discharged at rates of 3,000 to 7,500 m3/day. Makeup demand vs
available water from the existing DSTF, planned DSTF and underground dewatering predicted by the
model at the UZ and MDZ plants are shown in Figure 18-8 and Figure 18-9 respectively.
Overall, the water balance model indicates a net surplus of water for the Project due largely to an
overall increase in available water from the MDZ dewatering and a decrease in makeup demand
resulting from the lower moisture contents in the dewatered tailings.
Although the water balance does not indicate there will be a need for additional water supply sources,
during dry periods the underground dewatering will be the only available source of water. A back-up
supply from the nearby Cauca River is recommended as a secondary supply source for time when
underground dewatering flows are unavailable.
18.15 Tailings Management Area
The following sections summarize reasonably available information regarding existing tailings
generation and management and describe the conceptual design and operation of new DSTFs for
filtered (dewatered) tailings. Conceptual design details for DSTF 2 and DSTF 1 are shown on the
drawing set in Appendix B.
If the existing Cascabel 1 and 2 tailings management facilities can be proven or redesigned to meet
internationally accepted standards of practice, they may be able to provide between one and two years
0
200
400
600
800
1000
1200
1400
1600
2020 2022 2024 2026 2028 2030 2032 2034 2036 2038
Flo
ws (
m3
/da
y)
Time
Water Supply and Demand at the MDZ Plant
Realization #200
MDZ Plant Water Demand Reclaim from DSF to MDZ PlantDewatering to MDZ Plant Freshwater to MDZ Plant
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 395
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
of additional capacity, after which a new DSTF(s) would need to be commissioned to accommodate
tailings through the currently-estimated 16-year LoM. Where appropriate, recommendations for
additional investigations or expansion of existing baseline data collection programs are provided.
On January 27th, 2020, Breese Burnley, a Qualified Person in accordance with Companion Policy 43-
101CP to NI 43-101, conducted a personal inspection of the Marmato site under Section 6.2 of the
Instrument. This inspection was intended to familiarize Mr. Burnley with the conditions at the mine site
and any potentially available material information that could affect mine development/expansion in this
location. Information collected on site in 2020 was supplemented by CGM during 2020, as necessary.
In addition, SRK contracted with in-country geotechnical consulting company Dynami Geoconsulting
SAS (Dynami) to perform site reconnaissance, assist with slope stability and hydrological modeling,
participate in the geotechnical site investigation and coordinate with site personnel.
The following sections describe the existing operation and the conceptual design of new DSTFs
required to provide for tailings management through the LoM.
18.15.1 Existing Tailings Management Facilities
The processing plant currently sends tailings slurry from the cyanide leach circuit to unlined settling
ponds located on deposited tailings within the footprint of Cascabel 1. The draindown flows from the
ponds are directed via a gabion wall and drain system to small collection basins downgradient of the
tailings disposal piles. Clarified overflow water is pumped back to the plant for use in the process.
Excess water not needed at the plant is discharged under permit to the adjacent stream, Quebrada
(Qda.) Cascabel. Once sufficiently dewatered to allow for mechanical handling, the tailings are
excavated from the ponds and transported via truck to existing Cascabel 1 and placed and compacted.
Cascabel 2 is a lateral expansion of the existing operation into a separate natural drainage channel
north of Cascabel, as shown on Figure 18-10 below.
At the time of report preparation, CGM was expediting the additional characterization and analysis of
Cascabels 1 and 2 recommended by Dynami (Dynami, 2020c) with the short-term goal of bringing the
design of both Cascabels 1 and 2 up to internationally accepted standards of practice. For the
purposes of PFS tailings management, it was assumed that the design of Cascabels 1 and 2 could
either be shown to meet internationally accepted standards of practice, or could be redesigned to do
so, such that the final design configuration would provide sufficient additional capacity until a new
DSTF could be commissioned. These assumptions must be reviewed following completion of the
recommended additional characterization and analyses and the results used to update or revise the
plan and costs for tailings management for the next level of study. SRK recommends that CGM identify
other options for filtered tailings storage that may provide additional interim storage capacity in case
Cascabel 1 and 2 cannot be shown to be stable to internationally accepted standards of practice.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 396
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: IRYS, 2018
Figure 18-10: Proposed Configurations of Cascabels 1 and 2
18.15.2 New Tailings Storage Facility Siting Study
SRK completed a siting study of potential options for tailings management facility siting in the vicinity
of the existing Cascabel 1 tailings storage facility and the proposed portal and plant location. Factors
considered in the siting study included such considerations as topography, permitting requirements for
stream crossings, property ownership and acquisition potential, distances between the proposed
process plant location and the prospective DSTFs and municipality boundaries.
Conventional slurry DSTFs typically required very large areas to achieve a reasonable rate of rise and
corresponding deposited tailings dry density. A suitable slurry tailings management site could not be
identified in the steep and incised terrain around the project site. Based on this and the relatively high
precipitation in the area, SRK concluded that a DSTF would be a more favorable tailings management
method for the Marmato site. Recent advances in tailings filtration technology and performance favors
tailings filtration and dry stacking for this project. Maximizing process water recycling and minimizing
makeup water requirements was also considered an additional benefit of the DSTF method.
As part of the siting study, SRK developed conceptual designs for seven potential DSTF locations.
From that analysis, only three locations, sites 1, 2 and 6, were identified within the area of study as
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 397
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
potentially feasible for providing the capacity required through the mine life and achieving global
stability in the steep terrain in the site vicinity. The locations of the feasible DSTF locations are shown
on Figure 18-11 relative to the proposed process plant location. A trade-off study (SRK, 2020a) was
prepared to facilitate a comparison of high-level costs for each of the three sites for only major cost
items.
Based on the results of the SRK trade-off study (ToS) for sites 1, 2 and 6, CGM indicated a preference
to evaluate the feasibility of developing DSTF 2 and then DSTF 1 to achieve the desired tailings
storage capacity through the currently predicted mine life. The combination of DSTF 2 and DSTF 1
provides just enough capacity based on current projections. DSTF 6 provides sufficient capacity on its
own for the currently predicted mine life, although the distance to the plant adds some additional
planning and access complexities.
Source: SRK, 2020
Figure 18-11: Potential DSTF Sites Identified Through Siting Study
18.15.3 New Dry Stack Tailings Storage Facility Design
Under the PFS scenario using both DSTF 1 and DSTF 2, DSTF 2 would be constructed first and
receive dewatered and dried tailings from the UZ and filtered tailings from the MDZ after Cascabel 1
and 2 reach capacity. Current assumptions allow for between one and two years of additional capacity
at the Cascabel sites, as described above.
UZ tailings are assumed to be dewatered as described above at Cascabel 1, hauled to a designated
drying area and disked to a target moisture content of 15% by weight, then hauled to the planned
DSTF (DSTF 2 or DSTF 1) and placed, amended with cement and compacted. MDZ tailings will be
routed through a new filter plant to a target moisture content of 15% by weight. The filtered tailings will
be hauled directly to DSTF 2 or DSTF 1, placed, amended with cement and compacted.
Current calculations consider DSTF 2 is in operation by early-2021 and operational through 2027.
DSTF 1 construction is completed in 2026 and commissioned in 2027 and receives the balance of the
tailings through the end of the projected 13-year mine life in 2033. Construction of DSTF 1 would
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 398
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
commence one year prior to reaching capacity in DSTF 2 to ensure the availability of tailings disposal
capacity is uninterrupted.
Design Criteria
Conceptual designs for both DSTF 2 and DSTF 1 are based on an assumed 13-year LoM with a total
mined tonnage of 26 Mt and a maximum annual mining rate of 2 Mt/y for 13 years. Of the tailings
produced, approximately 9.4 Mt (approximately 48% of total mill throughput) would be mixed with
cement and sent back to underground workings as paste backfill. The remaining 10.3 Mt
(approximately 52% of total mill throughput) of tailings would be dewatered at the Cascabel site and
drying area or using filter presses to a target moisture content of 15%, then trucked to the DSTFs,
mixed with 1% cement by weight and placed and compacted in controlled lifts to a specified minimum
compacted density. The dry density of the placed tailings was assumed to be 1.8 t/m3 for volumetric
calculations. Key DSTF design criteria are summarized in Table 18-1 below.
For the purposes of the PFS, the outer slope for DSTF 2 was designed at a 2.5H:1V
(horizontal:vertical) slope, while the outer slope of DSTF 1 was designed at 2H:1V. Cement addition
is assumed to be required to achieve global stability of the tailings mass at both sites. For the purposes
of PFS cost estimating, cement amendment at 1% by weight was assumed. The actual required
amount of cement addition must be determined through a detailed laboratory testing program. Overall
slope angles should be revised for global stability in the next stage of the Project based on the results
of cement/tailings admixture testing.
Due to the tailings being filtered and placed and compacted with cement amendment, it is not
anticipated that an appreciable amount of draindown from the tailings will contribute flows to the
underdrain. However, the global stability of the DSTFs will depend on the ability to prevent the
development of elevated pore pressures within each stack. The DSTFs are therefore assumed to be
unlined but with an internal drain system designed to prevent the development of elevated pore
pressures within the tailings mass. Both sites are also assumed to require an underdrain system in the
natural drainage bottoms designed to intercept any potential upwelling groundwater or spring/seep
flows.
Conceptual design details for both DSTF 2 and DSTF 1 are shown on the drawing set in Appendix B.
Each DSTF is designed with a rock starter embankment designed with 2H:1V upstream and
downstream slopes and constructed from a combination of imported rock and non-potentially acid
generating (non-PAG) waste rock from underground workings or an approved on-site borrow source.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 399
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 18-1: DSTF Design Criteria
Criteria Units Description
General
Total Annual Mined Tonnes tpy 2,000,000
Total Mineralization Mined t 26,000,000
Life of Mine yr 13
Paste Backfill - percent of total tailings generated % ~48
Required Tailings Storage Capacity t 10,300,000
m3 5,700,000
100-year 24-hour Storm Event mm 143
Filtered Tailings
Placed Dry Density t/ m3 1.8
Target Moisture Content w/w 15%
Tailings Acid Generation Potential PAG/NAG NAG
Tailings Transport and Stacking System
Tailings Transport System from Filter to DSTF Truck
Tailings Spreading within DSTF - Dozer
Tailings Cement Amendment - Tractor with Discs
Compaction of Tailings - Dozer and Vibrating Smooth Drum Roller
Overall Slope Angle XH:1V DSTF-1 – 2H:1V
DSTF-2 – 2.5H:1V
Rock Starter Embankment
Rock Source Imported Rock, Waste Rock or Local
Borrow
Downstream/Upstream Slopes XH:1V 2H:1V
Source: SRK, 2019
Rock Starter Embankments and Foundation Preparation
For the PFS, it was assumed that phased construction of the DSTF 2 rockfill starter embankment
would require approximately 100,000 m3 of imported rock before the first waste rock arrives from MDZ
development in late 2021. It was also assumed that the waste rock from the underground would be
non-PAG and suitable for rockfill starter embankment construction. The rockfill embankments would
be constructed between abutting ridges that form the primary valleys within which the DSTFs would
be located. These ridges should consist of bedrock and constitute solid foundations for embankment
foundations, and unsuitable soils should be removed from the embankment footprints. A geotechnical
site investigation must be completed as part of the next phase of study to confirm suitable foundation
conditions and adjust the costs described herein.
The main features of the rock starter embankments are as follows:
DSTF 1 Rock Starter Embankment:
• Crest Elevation: 800 m
• Crest Width: 20 m
• Upstream Slope: 2H:1V
• Downstream Slope: 2H:1V
• Maximum Starter embankment Height at Centerline: 35.3 m
• Maximum Starter embankment Height from Toe: 58.9 m
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 400
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
DSTF 2 Rock Starter Embankment:
• Crest Elevation: 940 m
• Crest Width: 20 m
• Upstream Slope: 2H:1V
• Downstream Slope: 2H:1V
• Maximum Starter embankment Height at Centerline: 27.2 m
• Maximum Starter embankment Height from Toe: 46.9 m
The rockfill embankment footprints will require foundation preparation prior to placement of the rock
fill materials, to include clearing and grubbing and removal and stockpiling of salvaged topsoil for later
use in reclamation, removal of unsuitable foundation materials, and excavation of a foundation key for
embankment stability. For PFS costing, it was assumed that the unsuitable material requiring removal
would be removed to an average depth of 2m over the footprint of the rock starter embankment, and
the foundation key would be 20 percent of the rockfill embankment at both DSTFs.
A similar approach was taken for the foundation of the filtered tailings. An average topsoil thickness of
1m over the footprint of the proposed filtered tailings placement area was considered as an initial
capital cost. Excavation of benches into the prepared foundation slope to key in filtered tailings and
construct perimeter drains was considered an operational cost.
DSTF Slope Stability
Due to the COVID-19 virus and associated restrictions on international travel, SRK was unable to
execute the originally planned geotechnical site investigation prior to preparation of the PFS study.
This inability to characterize the foundation conditions beneath the conceptual DSTF footprints means
the designs for those facilities could change significantly during the next phase of study, with possible
resulting recommendations ranging from a redesign of required foundation preparation measures to
recommendations against development at the selected sites. In addition, it could be determined that
more cement is required to achieve global stability than has been provided for in the PFS cost estimate,
resulting in significantly different operating costs than considered herein.
In the absence of detailed testing and characterization data for both the foundation and the tailings
and tailings/cement admixtures, Dynami (Dynami, 2020b) prepared slope stability analyses under
SRK’s direction that started with reasonably achievable strength and material properties developed
based on SRK’s experience with recent dry-stack projects in similar geological and climatic
environments. The goal of the analyses was to determine what minimum material strength parameters
would be required to achieve global stability of the conceptual DSTF configurations, and those
numbers were evaluated relative to reasonably achievable values. The PFS designs currently reflect
the results of these analyses and SRK’s experience at similar sites, however a complete slope stability
study must be completed as part of the next phase of study and prior to construction and must consider
the results of the site geotechnical investigation and tailings characterization. The results of that study
must be used to revise the PFS design to demonstrate stability in accordance with internationally
accepted standards of practice.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 401
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
DSTF Water Management
Underdrain System
Seeps, springs or upwelling groundwater within the DSTF footprint would be controlled by the
installation of an underdrain system consisting of perforated central header pipes placed in channels
in the base of existing natural drainages with connecting perforated transverse drains in smaller
tributaries to the main drainages. Any seepage that is intercepted by the underdrain would be
considered non-contact water and routed to tanks of the natural channels below each DSTF’s rock
starter embankment for release to the natural drainage downstream. If routed to the tanks, the
captured fluids would be periodically sampled and tested to confirm suitable chemistry for discharge
and either allowed to overflow into the natural channel downstream or pumped back to the process
water tank for incorporation back into the process circuit.
For the purposes of PFS costing, the underdrain was considered to consist of a network of 0.6m
diameter perforated and solid wall pipes surrounded by a 6 m2 cross section of drain gravel, wrapped
in a geotextile with a layer of filter sand between the underdrain and filtered tailings.
The underdrain system would be installed in phases as the DSTF advances up the slopes and
drainages with temporary stormwater controls in place to ensure that contact or upgradient stormwater
is not allowed to enter the underdrain system.
Internal Drainage System
A system of inter-bench drains would be installed within the placed tailings to prevent the development
of elevated pore pressures within the tailings mass. The drains would consist of 100 mm perforated
pipes installed in gravel-filled drains wrapped in geotextile on 10 m centers and routed to the closest
underdrain at the back of each DSTF (Figure 18-12). The drainpipes would be connected via a series
of solid pipes through the underdrain system that would route collected seepage flows into the water
management tanks at the toe of the rockfill embankment. The described internal drainage system
would be constructed every 10 m vertically as the DSTF advances. PFS costs for drain construction
were considered as part of DSTF operating costs.
Source: SRK, 2020
Figure 18-12: Internal Drainage System
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 402
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Stormwater Management
The upper operational deck surface would be graded so that contact runoff reports to a lined
operational pond at the back of the DSTF (i.e. as far as possible from the outer slope crest) to facilitate
pumping back to the plant site process water tank for reuse. Contact stormwater must be managed on
the DSTF top deck and not allowed to enter the underdrain system. As the filtered tailings surface
progresses up the slope at the back of each DSTF, the lined operational pond would be relocated to
the lowest point on each lift.
Concrete-lined diversion channels must be constructed around the DSTFs before any other
construction is started. Reinforced concrete cutoff walls are recommended where natural channels
intersect each concrete channel. The diversion channels would route non-contact stormwater run-on
around the DSTFs and back into natural drainages downstream. Conceptual channel alignments are
shown in Figure 18-11 above. The possible channel alignments are significantly affected by current
permitting limitations which prohibit rerouting flows from one watershed into an adjacent watershed.
The ability to do so would result in a much more feasible diversion channel west and south of DSTF 2
and should be further explored.
A combination of reinforced concrete energy dissipation structures or a stilling basin and riprap aprons
would be constructed to slow the flow down before being discharged into the natural drainages. Interim
diversion channels were included in PFS operating costs to minimize the amount of run-on reporting
to the topdeck stormwater management system during operations.
The concrete-lined diversion channel around the west and south side of the process plant intersects
the haul road from the plant to DSTF 1 and the municipal road to Marmato. To manage stormwater
flows at these intersections, pre-cast concrete spans with wingwalls from Contech were included in
PFS costing (Figure 18-13). Estimated costs include demolition of the existing public road, reinforced
concrete footings, installation of pre-cast arches and reconstruction of public road to local standards.
Source: Comtech/SRK, 2020
Figure 18-13: Pre-Cast Concrete Span Channel Crossing
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 403
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Reclamation of the outer face of the DSTFs should be carried out concurrently during active operations
per Section 18.4.9 and, therefore, stormwater contacting the downstream face would be non-contact
stormwater that could be discharged into the natural channel downstream. A non-contact stormwater
collection system was designed to collect and direct non-contact stormwater from the face of each
DSTF with a series of riprap-lined channels on benches routed to perimeter downslope diversion
channels. The channels were classified into three groups as shown:
• Bench channels (or ditches): Drain from the DSTF towards the northern or southern perimeter
downslope channels.
• Perimeter downslope channels: north and south channels running along the intersection of
the tailings outer slope and native ground.
• Temporary channel above active tailings bench to drain runoff from the area below the
upgradient diversion channel.
Dynami conducted preliminary hydrologic and hydraulic analyses (Dynami, 2020a) for each of the
conceptual DSTF The diversion channels dimensions used in PFS costing are summarized in Table
18-2. Watersheds for each DSTF are shown in Figure 18-14.
Table 18-2: Stormwater Diversion Channel Summary
Location Return Period
Ditch Slope Min. (%)
Bottom Width (m)
Depth (m)
Sideslope (m)
DSTF-1
Bench Channel-1 1:100 2% 1 0.35 05H:1V
Bench Channel-2 1:100 2% 0.5 0.3 05H:1V
Perimeter Channel South 1:100 2% 1.5 1 05H:1V
Perimeter Channel North 1:100 2% 1.5 1 05H:1V
Diversion Channels PMP 2% 4 0.6 05H:1V
DSTF-2
Bench Channel-1 1:100 2% 0.6 0.6 05H:1V
Bench Channel-2 1:100 2% 0.6 0.6 05H:1V
Perimeter Channel South 1:100 2% 1 1 05H:1V
Perimeter Channel North 1:100 2% 1 1 05H:1V
Diversion Channel around Plant PMP 2% 4.5 1.5 05H:1V
Diversion Channel above DSTF PMP 2% 4.5 1.3 05H:1V
Source: Dynami, 2020b
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 404
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: Dynami, 2020
Figure 18-14: Watersheds for DSTF 1 (Top) and DSTF 2 (Bottom)
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 405
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
As described above, a significant design limitation requires that water from one watershed cannot be
diverted into an adjacent watershed. The southern diversion channel alignment attempts to
accommodate this limitation; however, the alignment will be difficult to construct and likely expensive
to maintain. SRK recommends moving ahead with an application for permission to divert water from
the Los Indios Creek watershed into the channel immediately south of the plan area to eliminate a
significant portion of the southern diversion channel. The flows from both channels terminate at the
Caucas River and discharge very close to each other, so the cumulative impacts of the diversion are
not anticipated to be significant.
Access and Haul Roads
The DSTFs would be accessed by dedicated haul and access roads (Figure 18-15) that include
additional width to support stormwater management and safety berms. For the purposes of PFS cost
estimation, the platform for both the road and drainage channels was assumed to be 15 m wide with
a maximum grade of 12%.
The DSTF-1 access road is currently routed from the filter plant to the bottom of the rockfill
embankment and to the portal. The road will be adjusted as deposition advances up the valley to
maintain access.
The DSTF-2 access road is currently routed from the filter plant to about mid height up DSTF-1 and
then to the base of the rock embankment. Stormwater culverts with riprap at the entrance and exits
were incorporated into the design. Additional methods of road stability were assumed to be needed
for about 20% of the access roads linear length.
Source: SRK 2020
Figure 18-15: DSTF Haul and Access Roads
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 406
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Tailings Stacking
Trucks would be used to transport the dried tailings from the UZ or filtered MDZ tailings from the filter
plant to either of the DSTFs via dedicated haul roads, as shown in (Figure 18-15). The tailings would
be end dumped, spread in approximately 30 cm-thick loose lifts with a dozer, mixed with cement using
a disc harrow or similar equipment, and compacted using a vibrating smooth drum roller or sheepsfoot
compactor, as appropriate. It is currently anticipated that the cement amendment would be required to
achieve global slope stability at the currently proposed design slopes. For the purposes of PFS costing,
it was assumed that a 1% amendment of cement by weight will be required to achieve global stability.
Global slope stability should be evaluated in detail following completion of the geotechnical site
investigation and tailings materials characterization programs.
Temporary Stockpile and Tailings Storage
Temporary stockpiles for topsoil, removed unsuitable soils, and imported or waste rock for rock starter
embankment construction were assumed to be located southwest of the plant site. For PFS costing,
these areas were assumed to require foundation preparation and underdrain construction to manage
existing drainages and ensure stockpile stability. Costs were developed based on assumed lengths of
0.6 m diameter HDPE culverts and gravel-filled underdrains wrapped in geotextile. Because
geotechnical foundation information was not available at the time of PFS report preparation, as
described above, the foundation areas for all stockpiles should be evaluated in the next phase of study
to ensure stockpile stability.
A temporary filtered tailings storage area was assumed to be incorporated into the final plant layout to
accommodate up to three days of filtered tailings storage during periods of excess precipitation when
placement and compaction of tailings to the minimum specified relative density is not feasible. For PFS
costing, SRK included costs for a sprung structure (high-tension fabric building).
Finally, a temporary holding pond for slurry tailings storage was assumed to be required but a suitable
site was not identified. Given the current plans for two filter presses, and assuming at least one should
be operational at any given time, the potential need for a slurry holding pond should be evaluated at
the next phase of study. For PFS costing, a placeholder cost was included in the initial capital costs.
Closure and Reclamation
Reclamation of the outer slopes of the DSTFs would be undertaken concurrent with DSTF
construction. As successive lifts of dewatered tailings are placed and compacted, the outer slope face
would be covered with rock cladding, topsoil, and vegetated. The final top surface of the DSTF would
be graded back to the natural slope and stormwater diversion channels at not less than 2%, covered
with topsoil and revegetated.
18.15.4 Tailings Risks and Opportunities
Currently identified risks and opportunities with respect to the costs developed for the PFS include the
following:
• The inability to characterize the foundation conditions beneath the conceptual DSTF footprints
means the designs for those facilities could change significantly during the next phase of
study, with possible resulting recommendations ranging from a complete redesign of required
foundation preparation measures to recommendations against development at the selected
sites.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 407
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
• Geochemical characterization of both waste rock and ore/tailings was ongoing at the time of
preparation of the PFS. Preliminary indications are that at least a portion of the waste rock
and tailings may be acid generating. If acid generation potential turns out to be significant,
there may be additional costs incurred to import suitable rock for rockfill starter embankment
construction and for operational and long-term water management.
• SRK understands that CGM is expediting the characterization and analysis of Cascabels 1
and 2 recommended by Dynami in 2020. If the facility cannot be demonstrated to be stable
with respect to internationally accepted standards of practice, CGM will need an alternative
site for interim storage of UZ tailings until a new DSTF is ready to accept tailings.
• Only a very small amount of tailings was available for testing during the preparation of the
PFS. More extensive testing should be performed at the next level of study to confirm tailings
geotechnical characteristics and cement addition requirements. The results of that testing
should be used to evaluate the final configuration of each DSTF in accordance with
internationally accepted standards of practice. The results may indicate that more or less
cement is required to achieve the stability requirements than were assumed for PFS costing.
• Stormwater maintenance requirements at both DSTF 1 and DSTF 2 may constitute higher
costs through operations and closure than is currently allowed for in the PFS costs given the
regulatory limitations on stormwater routing between adjacent watersheds and the size of the
contributing watershed at DSTF 2. The actual development and operation of DSTF 6 could
ultimately be comparable or less expensive in cost through the life of the mine to develop and
operate given the more amenable site topography and lower stormwater management
requirements.
• Several geological faults crossing the tailings facilities are identified in available geological
studies (IRYS, 2019). The information indicates that the majority of the footprint area for the
three DTSFs corresponds to Miocene age rocks and residual soils, except for a colluvial
deposit on DTSF-2. SRK recommends a trenching study within DTSF-2’s footprint to assess
the activity of the faults crossing this quaternary unit.
18.16 Off-Site Infrastructure and Logistics Requirements
The Project has no significant off-site infrastructure needs and this section is provided for reference
only.
18.16.1 Port
Marmato is 200 km east of the Pacific Ocean and 300 km south of the Caribbean Sea and Atlantic
Ocean. The nearest port is Buenaventura on the Pacific Ocean (320 km by the Pan American Highway
to the south west). The port will not be used for the Project other than as support for delivery of out of
country equipment.
18.16.2 Rail
There is an abandoned railway cutting along the east side of the Cauca River opposite Marmato, which
previously formed part of a railway network between the Pacific and Atlantic Oceans which ran
between Buenaventura and Puerto Berrio on the navigable Magdalena River. The middle section
between Medellín and La Felisa (Caldas, 10 km south of Marmato) was completed in 1942 and closed
in 1972. Ferrocarriles del Suroeste S. A. (Southwestern Railways) applied for a concession to rebuild
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 408
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
this 185 km line between La Felisa and Envigado, near Medellín, in November 2007, at a cost of
US$140 million. This would become integrated with the national railway network. Ferrocarriles del
Oeste S. A. (Western Railways) were awarded the contract to operate the 499 km Buenaventura to
La Felisa railway in November 2007. The concession is in two stages. In July 2009 the 388 km railway
between Buenaventura and Cartago and La Tebaida which has been rehabilitated was opened. In the
second stage the new concessionaire will take over operation of the 119 km section between Cartago
and La Felisa once this has been rebuilt by Tren de Occidente (Western Train). Currently the
concession contractor (Western Railway) is in liquidation, so another company would have to develop
the rail if needed for the Project. Currently there are no plans to use the rail.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 409
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
19 Market Studies and Contracts
19.1 Commodity Price Projections
Gold and silver markets are mature, global markets with reputable smelters and refiners located
throughout the world. Demand is presently high with prices for gold showing an increase during the
past year. Markets for doré are readily available. Marmato possess a gold room for the production of
doré.
Assumed prices are based on the long-term outlook for gold and silver. This projection is well below
the current spot prices and the long-term views of relevant market analysts in the precious metal
sector. Table 19-1 presents the prices used for the cash flow modelling and resources estimation.
Table 19-1: Marmato Price Assumptions
Description Value Unit
Gold 1,400 US$/oz
Silver 17.00 US$/oz
Source: CGM, 2020
19.2 Contracts and Status
CGM currently has a long-term supply agreement for the sale of its products to an international refinery
who take delivery of doré from the mine at designated transfer points in Colombia. The refinery is
responsible for shipping the products abroad. The refining costs and discounts associated with the
sales of the products are based on this agreement. This study was prepared under the assumption
that the Project will sell doré containing gold and silver.
Treatment charges and NSR terms are summarized in Table 19-2.
Table 19-2: Marmato Net Smelter Return Terms
Description Value Units
Payable Gold 100%
Doré Smelting & Refining Charges 6.38 US$/oz-Au
Source: CGM, 2020
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 410
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
20 Environmental Studies, Permitting and Social or Community Impact The following section discusses reasonably available information on environmental, permitting and
social or community factors related to the Marmato Mine (Upper Zone) and the proposed MDZ
expansion. Where appropriate, recommendations for additional investigation(s), or expansion of
existing baseline data collection programs, are provided.
On December 1, 2016, Mark Willow, a QP in accordance with Companion Policy 43-101 to NI 43-101
– Standards of Disclosure for Mineral Projects, conducted a personal inspection of the Marmato site
under Section 6.2 of that Instrument. This inspection was intended to familiarize Mr. Willow with the
conditions on the properties, and any potentially available material information that could affect mine
development/expansion in this location. Information collected on site was supplemented by CGM
during 2019/2020, as necessary.
20.1 Environmental Studies
20.1.1 Environmental Setting
The Marmato Project is located in the Municipality of Marmato, Department of Caldas, Republic of
Colombia, and is approximately 125 km due south of the city of Medellín, the capital of the Department
of Antioquia. The town of Marmato was founded in 1540 and has a population of approximately 10,000
people. It is one of the most historic gold-mining regions of the hemisphere. The Marmato Project has
excellent infrastructure, being located along the Pan American Highway with access to Medellín to the
north and Manizales (the capital of Caldas) to the south and has access to the national electricity grid
which runs near the property.
The west central Colombian Department of Caldas is situated in the Cordillera Central of the Andes
Mountains and is bounded by the Magdalena River on the east and the Cauca River on the west.
Marmato lies at an elevation of 1,050 masl, just west of Río Cauca, which joins the Magdalena River
near Magangué in Bolívar Department, before eventually flowing out into the Caribbean Sea.
The local topography is characterized by steep, incised valleys. The climate is tropical with an annual
average temperature of 21°C, that typically varies from 14°C to 24°C, and average annual rainfall of
approximately 2,162 mm/y, predominantly falling between April and November, with a negligible
difference of 153 mm of precipitation between the driest and wettest months. The drainage pattern
across Marmato is dendritic; the license area drains east into the Cauca River, which is heavily
influenced by artisanal mining operations. The vegetative cover across the landscape consists of
disturbed grassland (used mainly for mining and livestock rearing activities) interspersed with
fragmented forest patches, mainly along drainage lines within the incised valleys. Forest patches
provide important habitat for wildlife.
The operations are located within the town of Marmato, which has been a center for gold mining for
more than 500 years and the environmental and social setting is strongly influenced by this. Mining,
both formal and informal, is the main economic activity in Marmato and the neighboring towns of El
Llano and La Garrucha. Artisanal mining with informal processing operations using basic technology
has resulted in poor health and safety conditions and widespread water contamination from discharge
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 411
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
of tailings and waste directly into the environment. This has led to a prevalence of mercury-related
health problems in the local populations. Health issues related to population influx are also common.
20.1.2 Management Procedures and Baseline Studies
The existing Marmato Project predates the regulatory requirements to prepare an environmental
impact assessment as part of the permitting process. Instead, the operations were authorized through
the approval of an Environmental Management Plan (Planes de Manejo Ambiental or PMA). The PMA
for Marmato was approved by the regional environmental authority (Corporación Autónoma Regional
del Caldas or Corpocaldas) on October 29, 2001 under Resolution 0496, File No. 616. The site-specific
PMA covers environmental studies and required management procedures and practices associated
with:
• Reclamation in the area of the production plant
• Reclamation and closure of the tailings settling ponds
• Management of unstable zones (including erosion control)
• Water management in the mines
• Management of stormwater runoff
• Management and protection of watersheds
• Control planning and use of explosives
• Reforestation and revegetation programs
• Reclamation and closure planning
• Management of tailings
• Containment structures
• Cyanide destruction (detoxification)
• Management of wastewater (domestic)
• Water usage
• Air resource management
• Physical risk management measures (including toxic substances)
• Social management
• Biological management (i.e., biodiversity)
In addition, a comprehensive baseline data collection program was initiated in 2019 to gather relevant
and appropriate site information with respect to the existing Marmato Project and the proposed MDZ
expansion. The study area for these investigations covered the underground portal, and processing
plant site, as well as all of the proposed tailings disposal areas. The data was compiled and reported
in Capítulo 20: Caracterización Ambiental y Social del Proyecto, Caldas Gold Marmato S.A.S., Título
Minero #014 – 89m (May 2020). Included in this up-to-date report is:
• Comprehensive soil characterization of the study area, including surface uses, chemical
characteristics, and agronomic properties
• Hydrology of the study area, including flows and quality
• Climatology gathered from 10 regional stations which include winds, temperature,
precipitation, relative humidity, cloudiness (solar radiation), and evapo-transpiration potential
• Air quality from stations in El Llano, El Atrio, and La Plaza recording particulate matter (PM10),
sulfur oxides (SOx), nitrogen oxides (NOx), carbon monoxide (CO), volatile organic carbons
(VOCs), and ozone (O3)
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 412
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
• Climatology and meteorology
• Ambient noise levels from seven monitoring locations
• Baseline ecological data, including ecosystems and cover types, flora, and fauna resources
• Archeological and cultural resource assessment of the surrounding areas using personnel
from the Archeology Laboratory at the University of Caldas
• An assessment of the current socioeconomic situation within the study area, including
demographics, sanitation conditions, energy/power infrastructure and usage, and education
The report goes on to describe the environmental management programs employed by the current
operations (including costs) and provides an overview of the closure plan and costs for the mine and
its associated infrastructure (i.e., tailings, plant, etc.). Assessment of potential impacts associated with
the MDZ expansion project can only begin in earnest once the PFS mine plan has been finalized, at
which point, CGM will initiate engagement with Corpocaldas (anticipated in Q3 2020).
20.1.3 Geochemistry
SRK directed a sampling and analytical program to generate environmental geochemistry data for
tailings and waste rock for the existing operations and MDZ expansion project. Samples of future
tailings were collected from the PFS metallurgical program, and two samples of existing tailings were
collected from site (one consisting of conventional tailings, and one of cyanide tailings). 60 samples of
future waste rock were collected from exploration drill core. As of this writing, the waste rock and
existing tailings samples are still undergoing analysis at the laboratory.
Data from SRK’s metallurgical program indicates that tailings will be discharged with a neutral to
alkaline supernatant. However, the tailings solids will be PAG with the potential to eventually exceed
the alkaline supernatant and produce acidic drainage in the longer term. Detoxified cyanide tailings
are anticipated to have elevated concentrations of arsenic, sulfate, and total dissolved solids in
potential leachates. Testing on paste backfill tailings suggest that the material will be acid-neutralizing
in the short term, but in the long term, the material could become acidic.
A waste rock analytical program completed in 2012 in support of the defunct open pit mine design
indicated that a significant fraction of waste rock could be potentially acid generating (KP, 2012).
Effective management of both tailings and waste rock will be a critical issue for success of the project.
20.1.4 Known Environmental Issues
SRK is not aware of any known environmental issues that could materially impact CGM’s ability to
extract the mineral resources or mineral reserves at the Marmato Project. While there will be some
challenges associated with land acquisition and surface water control during operations, the Marmato
Project has not had, nor does it currently have any legal restrictions which affect access, title, mining
rights, or capacity to perform work on the property. Likewise, in regard to environmental compliance,
the operation is covered by the PMA and associated environmental permits, which further reduces
environmental risks.
Informal processing operations related to artisanal mining in this location using basic technology (many
of which are unpermitted), has resulted in poor health and safety conditions and widespread water
contamination from discharge of tailings and waste directly into the environment. This has led to a
prevalence of mercury-related health problems in the local populations. These operations may also
increase the potential for environmental risk in terms of soil stability impacts to other associated
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 413
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
resources. There are periodic review protocols which allow CGM to identify potential damages by third
parties and report them to Corpocaldas. The operational areas are generally protected to prevent
access by unauthorized third parties and their activities to protect against risks and environmental
liabilities.
20.2 Mine Waste Management and Monitoring
20.2.1 Waste Rock Management
Very little waste rock is generated by the underground operations at Marmato, and this is expected to
continue with the MDZ expansion. What little waste rock is generated is used as backfill in the
underground workings or on the surface for construction projects, such as maintenance of roads. As
part of the MDZ expansion, some of this waste rock will be needed for construction of the starter
embankment(s) for the proposed tailings disposal areas.
A preliminary study conducted by Knight Piésold (2012) suggested that approximately two-thirds of
the waste rock would likely have to be treated as PAG for conservative waste rock handling purposes.
Additional testing is currently underway to better refine this prediction, but some of the waste rock may
have the potential for Acid Rock Drainage and Metal Leaching (ARDML) and may not be suitable for
surface disposal/construction. However, since so little waste rock is brought to the surface, only
opportunistic sampling and testing of construction materials is probably necessary. At the moment,
Corpocaldas does not require the testing of mine waste materials; only effluent discharges. This is
likely to change in the future, as source control becomes more of the norm in this jurisdiction.
20.2.2 Tailings Management
The current gold processing plant at Marmato is fed with mill feed which is milled and processed
through a cyanide (CN) leach circuit using underground dewatering water, minimal water recycled from
the tailings facilities and fresh make-up water from the surface. Approximately 55% of the tailings from
the operations is returned to the underground workings as sand fill. The remaining approximately 45%
(including fines) are slated for surface disposal. The MDZ expansion will use a similar processing
methodology.
The CN leach circuit includes a hydrogen peroxide (H2O2) and copper sulfate (CuSO4) destruction unit
on the tail end to reduce CN concentrations to below the Colombian mine effluent discharge limit of
1 mg/L (Article 10 of Resolution 0631, dated March 17, 2015) before sending the residual tailings to
the unlined settling ponds (Cascabel 1 and Cascabel 2). Alternatively, hydrogen peroxide and copper
sulfate may be used in conjunction with ultraviolet (UV) treatment, if deemed prudent and economical.
The underdrain water from these ponds is directed to small collection basins downgradient of the
tailings surface disposal piles. Flocculant is added to this water on an as-needed basis to remove
residual suspended solids; the underflow (solids) from this process is directed back to the tailings
settling ponds, while the clarified overflow water is pumped back to the plant for use in the process.
Excess water, not needed at the plant, is discharged under permit to the adjacent stream, Quebrada
(Qda.) Cascabel.
Once sufficiently dewatered to allow mechanical handling, the tailings are excavated from the ponds
and transported via truck to the final disposal location. Monitoring of the residual tailings to determine
whether or not they are classifiable as ‘hazardous’ is accomplished through Corrosive, Reactive,
Explosive, Toxic, Inflammable, Pathogen (biological) (CRETIP) analyses. Toxicity analyses were
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 414
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
carried out by the Universidad Pontificia Bolivariana on cyanides and metals (chromium, mercury and
lead). The results support the classification of the tailings as non-toxic for the metals based on
comparisons to the maximum concentration thresholds established by Decree 4741 of 2005. The
analyses also showed that Total CN was below the threshold allowed in Decree 1594 of 1984 for water
discharges. SRK did not perform a comprehensive audit of all testing data; however, given the vintage
of these results, SRK suggests that more frequent sampling and analysis be conducted by the
operation going forward, and especially for the expansion project.
Based on the mineralogy of the orebody, process methodology, and limited analytical testing, SRK
anticipates that the Marmato tailings could be acid generating and will require appropriate
management during operations and post closure.
For the MDZ expansion of the Marmato Project, CGM intends to continue with a similar approach to
tailings and tailings water management. However, rather than using less efficient settling ponds, the
tailings will be filter pressed. The dry stack tailings will be transported to the new disposal facility, mixed
with cement, and stacked in a configuration that minimizes surface runoff. To the extent practicable,
contact water collected on the deck of the DSTF will be reused in the process; excess water will be
discharged under permit.
A critical driver of environmental impacts from tailings is whether contact water will be contained. The
current and predicted future quality of contact water needs to be determined. Two components of
potential chemical loading need to be estimated:
• Loading to surface water due to tailings runoff
• Loading to groundwater through seepage from the base of the tailings facilities
Current metallurgical testing includes geochemical characterization to provide data that will assist in
forecasting tailings solids and potential runoff chemistry. Water re-use/recycling is recommended to
the extent feasible. The operation will seek to maximize water recycling and minimize treatment and
discharge.
20.2.3 Site Monitoring
Various mitigation and monitoring programs are discussed in the approved PMA. Additional monitoring
will likely be requested by Corpocaldas as part of the permitting of the MDZ expansion. CGM routinely
verifies their compliance with provisions of the environmental mining guide adopted by Resolution 18-
0861 of 2002 by the Ministry of Mines and Energy, for activities associated with underground mining
and exploration.
Water Quality and Monitoring
As part of the current operations, CGM has seven domestic wastewater discharges and three non-
domestic wastewater discharges for which monitoring is conducted. Table 20-1 lists each discharge
point with its respective analytical parameters to be measured. The results of the monitoring are
provided to the regional environmental authority (Corpocaldas).
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 415
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 20-1: Water Discharges
o ID o Wastewater
Discharge o Discharge
Point o Parameters
o 1
o Non-Domestic
o Tailings dam o Turbidity, pH, temperature, total solids, total suspended solids, DB05, DQ0, grease and oils, flow, conductivity, sedimentary solids (for treatment systems – bulk tails, if total cyanide and lead are taken into account).
o 2 o Thickener
o 3 o Sedimentation
Ponds
o 4
o Domestic
o Camp 1
o pH, temperature, total solids, total suspended solids, DB05, DQ0, grease and oils, flow, fecal coliform and total coliform.
o 5 o Camp 2
o 6 o Camp 3
o 7 o Offices
o 8 o Mines
o 9 o Mine Dry
o 10 o Contractor
Lodging
Source: Mineros Nacionales S.A.S., 2017
CGM anticipates requiring additional wastewater discharge points at the proposed Main Camp,
Offices, Process Plant, Raw Water Pump station, and possibly at the DSTF facilities.
Air Quality and Monitoring
Air quality emissions from stationary sources at Marmato are currently regulated and monitored by the
Air Pollution Unit (Unidad de Contaminación Atmosférica or UCA) according to Table 20-2.
Table 20-2: Stationary Emission Sources
Unit Parameter UCA Degree of Significance
Monitoring Frequency
Metallurgical Laboratory
Particulate matter (PM)
0.01 Very low 3 years
Sulphur dioxide (SO2) 0.00 Very low 3 years
Nitrogen oxides (NOX)
0.04 Very low 3 years
Lead (Pb) 0.014 Very low 3 years
Smelter/Foundry
Particulate matter (PM)
0.05 Very low 3 years
Sulphur dioxide (SO2) 0.37 Low 2 years
Nitrogen oxides (NOX)
0.21 Very low 3 years
Lead (Pb) 0.47 Low 2 years
Source: Mineros Nacionales S.A.S., 2017
To date, CGM does not have any have any additional defined air quality monitoring points as part of
the MDZ expansion project but is anticipating the need to install points at the Mine Portal and around
the DSTF facilities. The precise locations will depend upon the results of the environmental impact
analysis.
20.2.4 Environmental Procedures and Permissions
Environmental protection measures and procedures followed by CGM at the Marmato operations
include those shown in Table 20-3.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 416
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 20-3: Environmental Procedures
ID Resource Environmental Procedure
Location Approval
Current State of Process
Competent Authority New Valid
Valid for
(years)
Renewal or Modification
Filing Date
1 Air Atmospheric emission permit
Smelter
Resolution 270 of April 27, 2009
5 ×
February 21, 2014. Renewal awaiting Ministry Indigenous Peoples determination before Corpocaldas renews permit.
Corpocaldas
Laboratory furnace
Shedding filter bag
2 Water
Surface water concession
La Maruja portal
× 5
Corpocaldas
Aguas Claras
Resolution 0046 of March 09, 2004, amended by Resolution 127 of May 5, 2004
×
February 07, 2014 Renewal awaiting Ministry Indigenous Peoples determination before Corpocaldas renews permit.
Zaparillo
Guineo
Domestic water discharge permit
Camp 1
Resolution 270 of April 27, 2009 amended by resolution 254 of February 28, 2014
× February 21, 2014
Camp 2
Camp 3
Office
Mine
Contractor
Mine dry
Non-domestic water discharge permit (industrial)
Tailings
Thickener
Sediment ponds
Channel Occupation
Charco Hondo
Resolution 0062 of February 15, 2006
Corpocaldas
Source: Mineros Nacionales S.A.S., 2017
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 417
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
CGM will need to request an additional surface water concession for the Cauca River as part of the
MDZ expansion project
20.2.5 General Water Management
Operational water for the existing Marmato operation is provided through a combination of
underground mine dewatering water, reclaim water from the existing DSTF, and several surface
freshwater sources. Even with the high precipitation experienced by the site, only nominal effort
appears to be directed toward stormwater management and the prevention of contact with mine
equipment and facilities at the existing operations. Some concrete channels and energy dissipation
structures for the management of run-off are already constructed, and some others are being
considered.
The MDZ expansion includes long-term stormwater diversion structures designed to convey 2/3 of the
Probable Maximum Precipitation (PMP) event, while internal (operational) conveyances are designed
to 100-year event requirements.
Surface water runoff control represents a significant water management challenge to the Project
considering the difficulties in distinguishing between the impacts from the artisanal mining activities
and those of the Project. The geochemical and hydrogeological/hydrological impacts should be
evaluated prior to closure, when dewatering ceases and water levels rebound within the mine
workings. Of critical importance is the possibility of mine water discharging to surface water or
groundwater and potentially impacting users. There are reports that dewatering effluent carries
elevated concentrations of metals. The water quality of dewatering effluent must be well characterized
in the event that treatment is needed before it is used or discharged. A forecast of closure water quality
is needed.
20.2.6 Environmental Management Budget
The operational costs for environmental management for the remainder of 2020, as provided by CGM,
are COL$1,591,779,394 (US$482,357). With respect to the MDZ expansion, CGM notes that the
environmental impact analysis and its requisite environmental management programs have not yet
been completed, from which the revised management budget will need to be developed covering the
larger operation.
20.3 Project Permitting Requirements
20.3.1 General Mining Authority
Since 1940, the Ministry of Mines and Energy (MME), formerly the Mines and Petroleum Ministry, has
been the main mining authority with the legal capacity to regulate mining activities in accordance with
the laws issued by the Colombian Congress. The MME can delegate its mining related powers to other
national and departmental authorities. Mining regulations in Colombia follow the principle that (except
for limited exceptions) all mineral deposits are the property of the state and, therefore, may only be
exploited with the permission of the relevant mining authority, which may include the MME, the
National Agency for Mining or the regional governments designated by law.
In 2001, the Congress issued Law 685 (the Mining Code). This law established that the rights to
explore and exploit mining reserves would only be granted through a single mining concession
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 418
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
agreement (the 2001 Concession Agreement). This new form of contracting did not affect the pre-
existing mining titles (licenses, ‘aportes’, and concessions) which continue to be in force until their
terms lapse. The 2001 Concession Agreement includes the exploration, construction, exploitation, and
mine closure phases and are granted for periods of up to 30 years. This term may be extended upon
request by the title holder for an additional 30-year term. According to the Mining Code, the initial term
was divided into three different phases:
• Exploration – During the first three years of the concession agreement, the title holder will
have to perform the technical exploration of the concession area. This term may be extended
for two additional years upon request;
• Construction – Once the exploration term lapses, the title holder may begin the construction
of the necessary infrastructure to perform exploitation and related activities. This phase has
an initial three-year term which may be extended for one additional year; and
• Exploitation – During the remainder of the initial term minus the two previous phases, the title
holder will be entitled to perform exploitation activities.
20.3.2 Environmental Authority
In 1993, Law 99 created the Environmental Ministry and then in 2011 the Decree 3570 modified its
objectives and structure and changed the name to Environment and Sustainable Development
Ministry. The Ministry is responsible for the management of the environment and renewable natural
resources and regulates the environmental order of the territory. Also, the Ministry defines policies and
regulations related to rehabilitation, conservation, protection, order, management, use, sustainable
use of natural resources. Article 33 of the same Law created the regional environmental authorities
(including Corpocaldas) with the responsibility to manage the environment and renewable natural
resources. Under this same law, Regional Autonomous Corporations were created and others, which
preceded the law, were ratified. These regional authorities function in the same way as the Ministry,
but with jurisdiction over specific territories.
In 2011, Decree 3533 created the National Authority of Environmental Licenses (Autoridad Nacional
de Licencias Ambientales, ANLA). ANLA is responsible to ensure all project, works or activities subject
to licensing, permit or environmental procedures comply with the environmental regulations and
contribute to the sustainable development of the country. ANLA will approve or reject licenses, permits
or environmental procedures according to the law and regulations, and will enforce compliance with
the licenses, permits and environmental procedures.
With regard to the licensing process of mining projects, the competence of either ANLA or Corpocaldas
is determined by the annual volume of material to be exploited. For projects exploiting more than 2
Mt/y the responsibility will be with ANLA. Both ANLA and Corpocaldas can enforce project compliance
with the terms of their licenses or permits. Up to now and in the foreseeable future, based on the
annual production and transport of materials at Marmato, the environmental authority that controls
operations is Corpocaldas.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 419
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
20.3.3 Environmental Regulations and Impact Assessment
Colombian laws have distinguished between the environmental requirements for exploration activities,
and those that have to be fulfilled for construction and exploitation works. During the exploration phase,
the concession holder is not required to obtain an environmental license, for now. However, the
concession holder requires environmental permits which will be obtained from the regional
environmental authority. The concession holder will have to comply with the mining and environmental
guidelines issued by the MME and the Environmental Ministry.
In order to begin and perform construction and exploitation operations, the concession holder must
obtain an environmental license or the approval of an existing PMA either from ANLA if the Project
exploits more than 2 Mt/y or from the regional environmental authority (Corpocaldas) if the mineral
exploitation is less than 2 Mt/y.
The approval process begins with the request for Terms of Reference (ToR) to prepare an
Environmental Impact Statement (EIS) or update an existing PMA. The approval of the EIS and PMA
by the jurisdictional environmental authority includes all environmental permits, authorizations and
concessions for the use, exploitation or affectation, or all of the above, of natural resources necessary
for the development and operation of the Project, work or activity. Additionally, other permits and
requirements (non-environmental) are required in order to begin construction and operation of the
Project.
Non-Governmental Organizations (NGOs) and the local communities have the opportunity to
participate in the environmental administrative procedures leading up to the issuance of an
environmental license. The environmental process will include participation of, and information to, all
communities in the project area including indigenous communities and Afro-descendant communities.
To date, the Marmato Project has removed less than 2 Mt/y; therefore, the environmental authority
responsible for issuing environmental licenses and permits, as well as for monitoring and controls, is
the Autonomous Regional Corporation of Caldas – Corpocaldas. Corpocaldas has approved the site’s
Environmental Management Plan under Resolution 496 of 2001, and has issued environmental
permits for the use of natural resources.
CGM maintains internal management files to identify environmental impacts associated with
exploration activities, which are not covered under the mining management plan, but which are also
addressed for its control, mitigation, and correction (if needed). Management files include resources
such as water, air, soil, flora and fauna, waste management, hazardous materials, socio-economic
components in terms of employment and economic transformation due to the demand for goods and
services. In accordance with the provisions of the environmental mining guidelines, impacts associated
with the biotic, abiotic, and socio-economic components which the activity may generate, or cause
have been identified, as well as the different measures which have been established to address these
impacts.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 420
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
20.3.4 Water Quality and Water Concessions
The Colombian regulations that principally govern water quality, including discharge permitting and
requirements, are Decree 2811 of 1974, Decree 1541 of 1978, Decree 1594 of 1984, Decree 3930 of
2010 and Resolution 631 of 2015, that establish the maximum permissible limits for discharges to
surface water.
Resolution 631 of 2015 (new parameters and maximum limits on point discharges) is being used as a
guideline for this project. The regional environmental authority (Corpocaldas) enforces compliance
with these regulations.
In preparation for the construction of a new CGM workers camp, the Company is carrying out the
necessary studies to file for an additional wastewater discharge point. The camp will be built with a
capacity for 150 people with a total of 10 sanitary units. A single point of domestic wastewater
discharge is currently being considered, which will be treated by a domestic wastewater treatment
system prior to being discharged into the Marmato stream. The domestic wastewater treatment system
would consist of a grease trap, an integrated septic system with a capacity of 15,000 liters and two
inspection boxes for the tributary and the effluent.
Water rights for mining activities are granted by means of a water concession which is granted by
Corpocaldas and which is independent of the mining concession or to land ownership. The water rights
related to mining activities are included in the environmental licenses or in the approved PMA and are
normally granted for five years. The terms and conditions under which a water concession is granted
may depend, amongst others, on the amount of water available in the specific region, the possible
environmental impact of the concession, water demand, the ecological flow and the different users
that the water source services. The water concession is accompanied with a discharge permit.
Water concessions held by CGM for the Marmato Project are shown in Table 20-4.
Table 20-4: Surface Water Concessions
Location Approval Term
(Years) Renewal of
Modification Filing Date
Competent Authority
Bocamina La Maruja
Resolution 345 of March 17, 2014
5 ×
January 29, 2019 (In process extension request)
Corpocaldas Aguas Claras
Resolution 0046 of March 9, 2004 (Amended by Resolution 127 of May 5, 2004)
10 ×
February 7, 2014 (In process extension request)
Zaparillo
Guineo
Source: CGM, 2019
Renewal or extension requests of these water concessions are currently under review by Corpocaldas
but are expected to be re-issued. Under the provisions of Article 35 of Decree Law 019 of 2012, the
environmental permits issued to the Marmato Project are automatically extended until Corpocaldas
officially acts on the request, and the originally terms and conditions of the permit remain in effect in
accordance with the provisions of Decrees 948 of 1995, 3930 of 2010 and 1541 of 1978, compiled in
Decree 1076 of 2015.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 421
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
A new water concession and impoundment on the Cauca River are being considered to capture 50
liters of water per second to cover the MDZ expansion project. The mine’s perched aquifers, which
have served as the main water supply for current operations, are experiencing low water levels
resulting from long periods of drought and anthropogenic pressures.
20.3.5 Air Quality and Emissions
Decree 948 of 1995, Resolution 650 of 2010 and Resolution 2154 of 2010 provide the main regulations
on protection and control of air quality. These regulations set forth the general principles and
regulations for the atmospheric protection, prevention mechanisms, control and attention of pollution
episodes from fixed, mobile or diffused sources. These regulations also provide emission levels or
standards. Among the emission sources regulated are:
• Controlled open burnings
• Discharge of fumes, gases, vapors
• Dust or particles through stacks or chimneys
• Fugitive emissions or dispersion of contaminants by open pit mining exploitation activities
• Solid, liquid and gas waste incineration
• Operation of boilers or incinerators by commercial or industrial establishments, etc.
Also, Resolution 627 of 2006 regulates noise emissions in terms of ambient noise. The parameters
regulated are
• SO2
• NO2
• CO
• TSP
• PM10
• O3
• Noise
CGM enforces compliance with these regulations at Marmato.
20.3.6 Fauna and Flora Protection
The main regulations for the protection of fauna and flora are contained in the Natural Resources Code
and the Agreement about Biological Diversity entered into in Rio de Janeiro on June 5, 1992, within
the framework of the Rio Convention. Also, forest management and use is regulated by Decree 1791
of 1996 and the compensation for biodiversity loss is regulated by Resolution 1517 of 2012. In addition,
there are other important regulations on the matter such as the Cartagena Protocol on Biotechnology
Security of the Agreement about Biological Diversity entered into in Montreal on January 29, 2000,
and the Convention on International Trade of Threatened Wild Fauna and Flora Species (CITES).
Endangered species are protected by environmental and criminal law.
In order to perform biodiversity studies, a permit for scientific investigation must first be obtained from
Corpocaldas.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 422
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
20.3.7 Protection of Riparian Areas and Drainages
Resolution No. 077 of March 2, 2011, regarding riparian and water channel protection, strictly prohibits
the filling of perennial water courses except under very specific terms: road and pipeline crossings,
bank and slope protection measures, and installation of public service networks (Title III, Article 9).
The backfilling of intermittent or ephemeral channels can be authorized under permit by Corpocaldas,
provided that the design is appropriate for the conditions, and that surface water and groundwater are
properly managed. Application of this prohibition directly influenced the siting of the future tailings
disposal areas, in that it (they) cannot be located in perennial drainages.
20.3.8 Protection of Cultural Heritage or Archaeology
Cultural and natural heritage protection in Colombia is stated in the political constitution and developed
through several international treaties and laws of the state. There are strict legal provisions, such as
Law 397 of 1997 and Decree 763 of 2009, whereby the heritage is safeguarded and protected. For
example, if a citizen finds an archeological specimen, he or she must inform the Ministry of Culture of
the discovery within 24 hours; otherwise he or she could be sanctioned by the competent authority.
20.3.9 Marmato Permitting
The Marmato Project is authorized under a number of resolutions issued by Corpocaldas in the name
of CGM’s predecessor, Mineros Nacionales S.A.S. These are identified in the Environmental Studies
and Management section (above), and include, among others:
• Environmental Management Plan or PMA (Resolution No. 496)
• Various water concessions
• Discharge permits (Resolutions 270 modified by 255)
• Air emissions (Resolution 270)
CGM is currently in the process of modifying the PMA to include a second DSTF disposal area
(Cascabel 2). To this end, CGM has presented the impact assessment and technical documentation
for this modification to Corpocaldas for review. Corpocaldas has evaluated the request and is waiting
for the Ministry of the Interior to certify the presence, or not, of ethnic communities in the area of the
new facility prior to issuing its final decision. Once Corpocaldas authorizes the Cascabel 2 modification,
a new modification request will be submitted for the construction of a third tailings disposal facility (El
Guaico) for agency approval.
The PMA will require a major modification to allow for the proposed MDZ expansion project, which
envisions an increase in production in a second processing plant to be constructed. By regulation, the
total of mined material (including waste and material) cannot exceed 2 Mt/y in order for Corpocaldas
(Regional Environmental Authority) to remain as the permitting authority. If more than 2 Mt/y is mined,
then the PMA will need to be submitted to, and authorized by, the national authority, ANLA
(Environmental License National Authority). At this time, CGM does not propose a combined
excavation rate of greater than 2 Mt/y between the existing and MDZ expansion operations, thus
maintaining Corpocaldas as the permitting authority.
During construction, Channel Occupancy Permits will need to be obtained for the new tailings site, the
process plant site, and the site of the underground portal (bocamina). Likewise, a Forest Exploitation
Permit will be needed for areas of proposed surface disturbance with trees (Diameter at Breast Height
or DBH more than 10 cm).
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 423
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
These new facilities and operation will be subject to the environmental licensing process described
above, which will require the submittal of comprehensive design reports, hydraulic and hydrogeological
investigation reports, geotechnical reports on stability, and an environmental impact assessment will
need to be prepared. This will require that adequate baseline data be collected from which the
significance of potential impacts can be assessed. Much of this information has been collected and
reported in the Capítulo 20: Caracterización Ambiental y Social del Proyecto, Caldas Gold Marmato
S.A.S., Título Minero #014 – 89m (May 2020). Initiation of the environmental impact assessment will
begin upon finalization of this PFS, detailing the proposed expansion facilities and operations.
Operationally, the existing discharge, emissions (if applicable), and water concession permits may
also require modification to suit the new mining conditions. As with the minor modifications discussed
above, the Ministry of the Interior will again need to be engaged with respect to the certification of the
presence of ethnic communities to ascertain if the MDZ project modification and expansion will require
special consultation.
The final environmental impact assessment deliverable includes the application for all the
environmental permits that will be required for the construction and operation phases of the project.
Once the EIA is officially delivered to Corpocaldas, the review process can begin based on the agreed-
upon terms of reference. This review process can take anywhere from six to 24 months to complete,
depending on the complexity of the project and the quality of the information provided. An incomplete
application is immediately rejected. CGM estimates that a minimum of six months will be required for
review of the complete application and issuance of the Resolution by which Corpocaldas approves the
modification requested for the MDZ expansion of the Marmato Project. However, this process has
been delayed as a result of the COVID-19 pandemic, and CGM does not anticipate fully reengaging
Corpocaldas with the submittal of the EIA until Q1 of 2021. Optimistically, permissions to initiate
construction could be received by Q3 2021.
20.3.10 Performance and Reclamation Bonding
The termination of a mining concession can happen for several reasons: resignation, mutual
agreement, and expiration of the term, the concession holder’s death, free revocation and reversion.
In all cases, the concession holder is obliged to comply or guarantee the environmental obligations
payable at the time the termination becomes effective.
The 2001 Mining Code requires the concession holder to obtain an Insurance Policy to guarantee
compliance with mining and environmental obligations which must be approved by the relevant
authority, annually renewed, and remain in effect during the life of the Project and for three years from
the date of termination of the concession contract. The value to be insured will be calculated as follows:
• During the exploration phase of the Project, the insured value under the policy must be 5% of
the value of the planned annual exploration expenditures
• During the construction phase, the insured value under the policy must be 5% of the planned
investment for assembly and construction
• During the exploitation phase, the insured value under the policy must be 10% of the value
resulting from the estimated annual production multiplied by the pithead price established
annually by the government
According to the Law, the concession holder is liable for environmental remediation and other liabilities
based on actions and or omissions occurring after the date of the concession contract, even if the
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 424
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
actions or omissions are by an authorized third-party operator on the concession. The owner is not
responsible for environmental liabilities which occurred before the concession contract, from historical
activities, or from those which result from non-regulated mining activity, as has occurred on and around
the Marmato Project site.
In accordance with the terms and conditions of the PMA, CGM maintains an Environmental Insurance
Policy for the current operation. That policy is renewed annually with Corpocaldas as beneficiary. This
policy is intended to cover the entire Marmato operations and all aspects of environmental compliance.
According to CGM, the current amount covered by the policy is COL$302,835,000 (USD$91,768). This
amount will be reviewed and adjusted during the modification process of the PMA for the MDZ
expansion project.
20.4 Social or Community Related Requirements
The 2001 PMA for Marmato specifically requires the management of the social component of the
Project through two programs (MM17 and PGS1, see section 4.5). CGM is required to maintain records
on all community activities (including number of participants, topics, duration, etc.), which is to be
turned over to Corpocaldas every six months as part of the ongoing monitoring programs.
20.4.1 Social Investment
As part of the social management and monitoring program, CGM has developed a social investment
model which seeks to promote the development of communities in the area of influence, with the
purpose of contributing to the consolidation of society and fostering economic development (Economic
Development), guaranteeing the care and respect for the environment (Environmental Development),
and supporting and participating in actions aimed at improving the quality of life and well-being of its
inhabitants (Social Development and Promotion of Solidarity Actions). Activities in 2017 included,
among others (for example):
• Direct economic compensation in excess of COL$3,850,000,000 (US$1.17 million) (including
state royalties and a payment of COL$2,079,000,000 (US$630,000) to the municipality of
Marmato)
• Support of education programs, such as Mining Training School with the National Learning
Service (Servicio Nacional de Aprendizaje) (SENA), Mine Rescue Training, Nutrition and
Safety Training, etc.
• Support for traditional festivities of local municipalities like Ferias de El Oro and Fiesta of El
Barequero
• Support for the Afro-Colombian meeting
• Inauguration of the C.E.S. San Antonio hospital and other health programs, including
vaccination days, sexual education workshops, drug addiction prevention workshops, etc.
• Leisure activities with educational institutions
• Music school educational programs
• A film exhibition of Marmato
• Employee human resource initiatives, such as the Bono Social and Novenas de navidad
programs
According to CGM, the company has a complaints and petitions handling procedure to record
grievances both at the Company offices and community office in El Llano. The grievance recording
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 425
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
and response procedures follow international good practices. SRK was not made aware of any current
or ongoing complaints in need of resolution.
20.4.2 Community Relations
Between 2014 and 2018, CGM developed and implemented a social engagement program at Marmato
specifically designed to focus on the well-being of the community and care for the environment. These
initiatives are incorporated in the Community Relations Plan (Plan de Relaciones con la Comunidad),
and include:
• Biodiversity and water for the future
• Education for development
• Protection of culture
• Health and well-being
• Productive chains of small mining in our value chain
• Women leaders and entrepreneurs
• Eradication of child labor
• Infrastructure for development
These initiatives are a collaborative effort within CGM and not necessarily the responsibility of
individual departments or organizations.
20.4.3 Employment
The Marmato Project currently operates with 152 administrative employees, 1,090 operating workers
and 54 apprentice workers, most of whom are from the municipalities surrounding the project, including
Supía, Riosucio, La Pintada, and Marmato. Skilled labor, such as engineers, geologists, surveyors,
some supervisors, and mechanics are from the cities of Medellín, Pereira, Manizales, Cartago, and
some from areas of the Department of Boyacá.
With the MDZ expansion, CGM anticipates hiring approximately 900 temporary workers during
construction and around 350 permanent employees as part of the new operations.
20.4.4 Artisanal and Small-Scale Mining Operations
The area has been exploited since pre-Colonial times by the Quimbaya people. The Spanish colonists
assumed control of the Marmato mines in 1527 and the area has been in almost continuous production
ever since. This majority of the mining is informal/artisanal in nature (sometimes referred to as
“traditional”), which is the general characteristic of the mining sector in Colombia. A recent census
revealed that 72% of all mining operations in Colombia are classed as ‘artisanal and small-scale
mining’ (ASM), and 63% are ‘informal’, lacking a legal mining concession or title. Large-scale mining
(LSM) only accounts for 1% of operations. Over 340,000 Colombians depend directly on ASM and
medium-scale mining (MSM) for their income. This informality deprives the state of important financial
resources, while the current poor conditions (environmental, social, health and safety, labor, technical
and trading) prevent the sector from delivering on important social objectives, such as generating
formal employment and improving the quality of life in mining communities (Echavarria 2014).
In 2013, a decree (933) was enacted to address the legal void for almost 4,000 requests for
formalization from Law 1382 of 2010, which was promulgated, in part, with the objective of combating
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 426
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
illegal mining, while recognizing the traditional nature of informal ASM. This decree redefined
traditional mining as a form of informal mining. It set out formalization procedures for ASM in LSM
mining concessions and titles, notably including procedures for concession-owners to cede areas to
ASM, and included tax incentives. For the first time, it also provided options for areas returned to the
state to be reserved for ASM formalization. In addition, Mercury Law No. 1658 of 2013, introduced
incentives for the formalization of ASM such as: granting of soft credits and financing programs to
facilitate access to resources; and created a sub-contract intended to formalize illegal mining activities
with the registered license-holder. Under Article 11 of Law 1658, concession owners can sign
subcontracts with ASM operating in their concessions without the liability associated with normal
operating contracts. These subcontracts will legally allow these ASM to operate in an agreed upon
area with no oversight by the concession owner. Instead these ASM will be under the control of the
Colombian mining and environmental authorities.
20.5 Mine Closure, Remediation, and Reclamation
Article 209 of Law 685 of 2001 requires that the concession holder, upon termination of the agreement,
shall undertake the necessary environmental measures for the proper reclamation and closure of the
mining operation. To ensure that these activities are carried out, the Environmental Insurance Policy
(see above) shall remain in effect for three years from the date of termination of the contract. Little else
regarding the specifics of mine closure is provided in the Law. Decree 2820 Article 40 Paragraph 2 of
2010 specifically indicates that the concession holder must submit a plan for dismantling and
abandonment of the Project.
While a formal closure plan is not legally required at this stage of the operation, currently there is a
closure plan for Marmato, Plan de Cierre y Abandono de Mina La Maruja – Gran Colombia Gold
Marmato S.A.S. (May 2019) which discusses basic reclamation and closure actions including aspects
of temporary, progressive, and final closure. More detailed, site-wide closure actions have not yet been
defined, as these will be developed through five-year updates to help identify potential closure risks
that CGM may need to manage and finalize closer to the end of operations. The below discussion
focuses on final closure and post-closure.
Some surface facilities (e.g., tailings storage facility) will be progressively reclaimed over the duration
of the mine site operations, albeit on a limited basis, as there are relatively few surface facilities suitable
for concurrent reclamation and closure. In addition, progressive reclamation and closure can result in
the development of expertise on the most appropriate reclamation methods. Progressive reclamation
and closure will be undertaken, however, without posing impediments on day-to-day operations of the
site. Final closure of the mine site will be undertaken following completion of all mining operations.
Final closure of the Marmato facilities and MDZ expansion facilities will entail the following activities, if
not undertaken during progressive closure phases:
• Reclamation of tailings storage facilities:
o The DSTF will be covered with growth media and revegetated.
o Concrete structures will be properly decommissioned.
o Metal fences will be removed.
• Underground workings:
o All equipment with resale value will be removed and salvaged.
o All portals, ventilation apiques, etc., will be sealed to exclude public access.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 427
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
• Plant and other buildings:
o Plant equipment will be decommissioned and removed for transportation to, and storage
in, Medellín.
o Buildings will be demolished.
• Erosion control measures will be taken where there is evidence of erosion.
• Human resources: mine workers’ contracts will not be renewed (no extra costs to be included
in the reclamation and closure cost estimate) or the contracts will be terminated (which would
incur additional costs).
The May 2019 closure plan discusses post-closure activities which include monitoring for physical and
chemical stability. Physical stability monitoring will include monitoring for ground movements which
would indicate subsidence. The plan currently assumes monitoring of physical stability twice annually
for three years and then annually for three years if no movement is detected. Chemical stability will
include monitoring of water quality of mine effluent as well as tailings draindown. Monitoring of water
quality will continue twice a year for the first three years and then once annually for at least three years
afterwards until such time that permissible limits are met, or flows diminish (in the case of draindown
from tailings).
20.5.1 Reclamation and Closure Costs
Reclamation and closure costs for the current operation are provided in the May 2019 reclamation and
closure plan. These costs are based on percentages of costs to build the facilities. The plan does not
provide the basis for the percentages, and SRK did not independently calculate or validate this
estimate; however, the amount is in keeping with the closure of other moderate-sized underground
mining operations in South America. The reclamation and closure cost estimate provided totals
COL$20,128,000,000 (US$6.1 million based on exchange rate of 3,300 to 1). A requirement for long-
term post-closure water treatment, if deemed necessary, could significantly increase this estimate.
Based on limited PFS design information for the MDZ expansion project, an additional cost of US$3.1
million was included in the technical economic model (for a total of US$9.2 million) to account for the
increase in production anticipated for the new operations and the construction of a new plant and
tailings storage facilities. The lower additional costs can be attributed to the requirement for concurrent
reclamation of the tailings disposal facility, which, due to the construction method, requires reclamation
during operations as opposed to post closure. Numerous assumptions were used in order to calculate
a reasonable estimate, though a more robust assessment of the facilities is recommended as part of
any FS of the project:
• The river water pumping station was assumed to remain post closure for use by the
community.
• The structures and facilities associated with the main camp were also assumed to remain post
closure for use by the community. This includes the domestic wastewater package plant. No
costs were included for demolition and removal.
• Most of the newly created roads servicing the mine would remain post closure to facilitate
access to the portal area, tailings, and stormwater diversion structures, all of which are likely
to require inspection, and possibly care and maintenance in the future. All process-related
equipment and structures would be dismantled and removed from site. No salvage value is
given.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 428
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
• Roads from each DSTF to the borrow area will be reclaimed.
• No new stormwater diversion structures are expected to be constructed post closure. Those
used during operations will remain.
• The portal conveyor system would be dismantled and removed, but the underground crusher
is expected to be left in place. While this equipment may have salvage value, no credit was
included in the closure cost estimate.
• Both ventilation drives and primary portal entry will be sealed.
• Regrading, placement of growth media and seeding costs for the portal and process areas is
included.
The costs for placement of cover material on the tailings storage facilities was calculated for the entire
surface of each facility, assuming that limited concurrent reclamation had occurred during operations.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 429
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
21 Capital and Operating Costs SRK visited Marmato’s mine site and office in early 2020; during these visits SRK reviewed budget
estimates and site-specific cost data, this review included data regarding both capital and operating
costs. These reviewed budgets and site-specific cost data are the base support for the capital and
operating cost models prepared for this PFS.
The cost models prepared for the Marmato UZ operation are mostly based on the reviewed budgets,
as this will be a continuation of the current operation. The MDZ cost estimates are based on cost
models prepared by SRK and Ausenco and are based on PFS level designs, estimates and site-
specific data provided by Marmato’s staff.
The mine is currently owner operated and the projections prepared for this PFS assume that this will
be maintained. Common prices for consumables, labor, fuel, lubricants and explosives were used by
all engineering disciplines to derive capital and operating costs. Included in the labor costs are shift
differentials, vacation rotations, all taxes and the payroll burdens.
21.1 Capital Cost Estimates
21.1.1 Marmato Upper Zone
The Marmato UZ is a currently operating underground mine; the estimate of capital includes some
expansion capex to increase the mineral processing capacity and sustaining capital to maintain the
equipment and all supporting infrastructure necessary to continue operations until the end of the
projected production schedule.
The sustaining capital cost estimate developed for this mining area includes the costs associated with
the engineering, procurement, construction and commissioning. The cost estimate is based on
budgetary estimates prepared by CGM and reviewed by SRK. The estimate indicates that the Project
requires a sustaining capital of US$59.5 million to support the projected production schedule
throughout the LoM. Table 21-1 summarizes the LoM sustaining capital estimate and Table 21-2 and
Table 21-3 present the same estimate by year.
Table 21-1: Marmato UZ Sustaining Capital (LoM)
Description LoM (US$)
Infill Drilling 11,847,000
Development 6,396,225
Mine Sustaining 10,049,860
Plant Expansion 11,626,000
Plant Expansion Contingency 2,906,500
Plant Sustaining 3,600,000
Dewatering 2,275,706
DTSF 4,744,900
Closure Costs 6,100,000
Total 59,546,192
Source: CGM/SRK, 2020
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 430
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 21-2: Marmato UZ Sustaining Capital (2020 to 2026) (US$)
Description 2020 2021 2022 2023 2024 2025 2026
Infill Drilling 2,200,000 2,200,000 2,200,000 2,200,000 2,200,000 121,000 121,000
Development 1,187,325 2,998,025 1,986,625 224,250 - - -
Mine Sustaining 2,127,399 1,777,862 1,852,400 3,858,800 - 154,000 279,400
Plant Expansion 5,035,000 3,511,000 1,210,000 440,000 1,430,000 - -
Plant Expansion Contingency 1,258,750 877,750 302,500 110,000 357,500 - -
Plant Sustaining 300,000 300,000 300,000 300,000 300,000 300,000 300,000
Dewatering 135,000 713,569 1,427,137 - - - -
TSF 1,032,700 2,792,200 170,200 170,200 239,200 42,550 42,550
Closure Costs - - - - - - -
Total 13,276,174 15,170,406 9,448,862 7,303,250 4,526,700 617,550 742,950
Source: CGM/SRK, 2020
Table 21-3: Marmato UZ Sustaining Capital (2027 to 2034) (US$)
Description 2027 2028 2029 2030 2031 2032
Infill Drilling 121,000 121,000 121,000 121,000 121,000 -
Development - - - - - -
Mine Sustaining - - - - - -
Plant Expansion - - - - - -
Plant Expansion Contingency - - - - - -
Plant Sustaining 300,000 300,000 300,000 300,000 300,000 -
Dewatering - - - - - -
TSF 42,550 42,550 42,550 42,550 42,550 42,550
Closure Costs - - - - - 6,100,000
Total 463,550 463,550 463,550 463,550 463,550 6,142,550
Source: CGM/SRK, 2020
Most of this sustaining capital estimate is supported by a budget forecast prepared by CGM and
reviewed by SRK; the following items are covered by this budget:
• A yearly infill drilling expenditure of US$2,200,000
• Mine equipment maintenance and replacement schedule
• Other mine sustaining capital includes improvements and maintenance of existing mine
infrastructure and stationary equipment
• Surface sustaining capital includes improvements and maintenance of infrastructure located
at surface, such as the camp, laboratory, filter presses, detox system, etc.
• Plant expansion capital
• Plant sustaining capital is an estimate of a yearly maintenance cost
• Dewatering structures developed by CGM
• DTSF costs prepared by SRK
• Closure costs estimate prepared by CGM
Development costs are derived from the mining schedule prepared by SRK. The prepared mining
schedule includes meters of development in waste, this schedule of meters was combined with unit
costs, based on site specific data, to estimate the cost of this development operation. This cost was
then capitalized into the sustaining capital.
Table 21-4 presents the assumed unit costs for this development, while Table 21-5 presents the yearly
schedule of capital development meters.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 431
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 21-4: Marmato UZ Capital Development Unit Costs
Description US$/m
Trans Ramp Development -RMP-3.5x3.5 (m) 1,200
Veins Level -LVL-2.2x2.2 (m) 1,050
Trans Level Access -ACC-3.5x3.5 (m) 1,200
Trans Waste Xcut -XCT1-3x3 (m) 1,150
Ventilation Drift -VNT-3.5x3 (m) 1,175
Apique Development (m) 3,071
Ventilation Raise -RAR-3x3 (m) 1,900
Source: CGM/SRK, 2020
Table 21-5: Marmato UZ Capital Development Meters (2020 to 2023)
Description 2020 2021 2022 2023
Trans Ramp Development -RMP-3.5x3.5 (m) 118 849 - -
Veins Level -LVL-2.2x2.2 (m) 166 109 - -
Trans Level Access -ACC-3.5x3.5 (m) 394 473 627 -
Trans Waste Xcut -XCT1-3x3 (m) 272 1,101 1,010 195
Ventilation Drift -VNT-3.5x3 (m) 31 7 15 -
Apique Development (m) 160 - - -
Ventilation Raise -RAR-3x3 (m) 26 12 29 -
Source: CGM/SRK, 2020
21.1.2 MDZ
The MDZ is a lower part of the deposit that is undeveloped. Before CGM can exploit this part of the
deposit it will have to expand the existing operation. The expansion is planned to be executed between
the years of 2021 and 2023.
The capital cost estimates prepared for the expansion into this mining area also include estimates for
EPCM and the Owner’s cost to manage it. The cost estimate is based on cost models prepared by
SRK and Ausenco with site specific inputs from CGM. The estimate indicates that the expansion will
require an investment of US$269.4 million; this includes an estimated capital of US$237.2 million plus
13.6% contingency of US$32.2 million. Table 21-6 summarizes the expansion capital estimate.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 432
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 21-6: MDZ Construction Capital (US$)
Description LoM 2020 2021 2022 2023
Development 19,719,753 - 2,279,534 10,343,401 7,096,818
Mining Equipment Purchases 52,430,929 - 16,868,012 15,295,229 20,267,68
8 Mining Services 11,589,225 - 1,288,744 6,206,511 4,093,970 Infrastructure 33,201,830 - 16,600,915 16,600,915 - Process Plant 42,371,769 - 21,185,884 21,185,884 - DSTF 19,660,473 - 17,212,986 1,279,528 1,167,958 Temporary Power Line 272,727 - 272,727 - - Mining EPCM 9,276,559 - 2,883,922 4,999,126 1,393,512 Mining Owner's 15,721,708 - 3,978,018 7,881,638 3,862,053 Infrastructure + Plant EPCM 10,484,229 - 5,242,114 5,242,114 -
Infrastructure + Plant Owner's 13,602,581 1,087,62
5 4,663,472 5,298,567 2,552,917
Infrastructure + Plant Other Indirect
8,860,555 - 4,430,278 4,430,278 -
Sub-Total 237,192,33
7 1,087,62
5 96,906,605 98,763,190
40,434,916
Mining Contingency 15,091,967 - 2,508,648 5,950,365 6,632,954 Plant + Infrastructure Contingency 14,237,757 - 7,118,879 7,118,879 - DSTF Contingency 2,871,944 - 2,581,948 191,929 98,067
Total Contingencies (13.6%) 32,201,668 - 12,209,474 13,261,173 6,731,021
Total 269,394,00
5 1,087,62
5 109,116,07
9 112,024,36
3 47,165,93
7
Source: CGM/Ausenco/SRK, 2020
The MDZ construction capital is supported by a mix of a PFS study prepared by Ausenco, budgetary
estimates and cost models developed for the installation of the new operation. Budget estimates were
prepared by CGM and reviewed by SRK and cost models were prepared by SRK and Ausenco. The
following items are covered by this budget:
• Schedule of mine equipment purchases prepared from SRK
• Cost model estimate from SRK to install surface facilities like portal, ventilation system, power
distribution, ancillary building, etc.
• Cost model estimate from SRK to install underground facilities like shops, ventilation systems,
refuge chambers, pumping systems, paste distribution, fuel distribution, ancillary equipment,
etc.
• Cost model from Ausenco to install other infrastructure including power supply, access road,
camp and pumping station
• Cost model estimate from Ausenco to install mineral processing plant, including EPCM and
Owner’s costs
• A PFS study prepared by SRK build a tailings storage facility
Development costs are derived from the mining schedule prepared by SRK. The prepared mining
schedule includes meters of development during pre-production, this schedule of meters was
combined with unit costs, based on site specific data, to estimate the cost of this development
operation. Table 21-7 presents the assumed development unit costs and Table 21-8 presents the
scheduled meters for the pre-production period.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 433
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 21-7: MDZ Pre-Production Development Unit Costs
Description US$/m
Lateral Development
Main Conveyor Ramp -RMC-5.5x5.6 (m) 2,998
Main Truck Ramp-RMT-5.5x5.5 (m) 2,599
Drift-FWA-5x5 (m) 2,050
Ventilation Drifts-VMR-5x5 (m) 2,286
Ventilation Connections-VCX-4.5x4.5 (m) 1,557
Bulk excavation equivalent meters (m) 7,724
Vertical Development
Blasted Raise-BRS-3x3 (m) 1,570
Raisebore 5m dia-RS1 (m) 4,755
Source: CGM/SRK, 2020
Table 21-8: MDZ Pre-Production Development Meters
Description LoM 2020 2021 2022 2023
Lateral Development
Main Conveyor Ramp -RMC-5.5x5.6 (m) 1,680 - 396 1,284 -
Main Truck Ramp-RMT-5.5x5.5 (m) 1,608 - - 440 1,167
Drift-FWA-5x5 (m) 1,307 - - 68 1,239
Ventilation Drifts-VMR-5x5 (m) 2,202 - 478 1,724 -
Ventilation Connections-VCX-4.5x4.5 (m) 171 - - 44 126
Bulk excavation equivalent meters (m) - - - - -
Vertical Development
Blasted Raise-BRS-3x3 (m) 6 - - 6 -
Raisebore 5m dia-RS1 (m) 383 - - 154 229
Source: CGM/SRK, 2020
Ausenco prepared an engineering study at a PFS level to design the mineral processing facilities and
other supporting infrastructure at the mine site. The resulting cost estimate is presented in Table 21-9.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 434
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 21-9: MDZ Processing Plant and Infrastructure Capital
Description Value (US$)
Buildings (Non Process) 2,475,260
Site Development 6,517,067
Plant Roads 1,460,997
Camp 4,538,557
Administration 2,021,881
Off Site Infrastructure Site Development 313,695
Backfill Paste Plant 505,855
U/G Conveying 4,470,587
U/G Power Generation / Distribution 4,029,202
Sewer (incl WWT plant, ponds) 1,859,489
Power 5,009,239
Total Infrastructure Direct $33,201,830
Crushing/Conveying 7,652,569
Milling 12,079,464
Leach/CIP 6,273,515
Detox 1,068,900
ADR/Elution 1,995,010
Goldroom 1,215,914
Reagents 1,832,347
Air/ Water 1,676,444
Tailings Thickening 2,667,196
Tailings Filter 5,910,410
Total Process Plant Direct $42,371,769
EPCM Cost 10,484,229
Contractor Indirect 4,518,958
Freight 2,378,746
Vendor Representatives 255,305
Pre-Commissioning/Commissioning (Craft Support) 20,095
Spares/First Fills 1,687,451
Total Indirect Cost $19,344,784
Total Project Cost Ausenco Scope 94,918,382
Owner's Cost -
Contingency 14,237,757
Total Project Cost Ausenco Scope incl Contingency $109,156,139
Source: Ausenco, 2020
Ausenco did not provide SRK with an expenditure curve associated with its capital estimate. SRK
applied this capex evenly thorough the quarters of year 2021 to be conservative.
The MDZ will require sustaining capital to maintain the equipment and all supporting infrastructure
necessary to continue operations until the end of its projected production schedule. The sustaining
capital cost estimate developed for this mining area includes the costs associated with the engineering,
procurement, construction and commissioning. The cost estimate is based on PFS designs and cost
models prepared by SRK with site specific inputs from CGM. The estimate indicates that the Project
requires sustaining capital of US$131.3 million to support the projected production schedule through
the LoM. Table 21-10 summarizes the LoM sustaining capital estimate and Table 21-11 and
Table 21-12 present the same estimate by year.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 435
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 21-10: MDZ Sustaining Capital (LoM)
Description LoM (US$)
Drilling -
Development 34,285,846
Mine Equipment Purchases 17,166,844
Mine Equipment Rebuilds 26,862,004
Mining Services -
Mining Owner's Cost 5,892,624
Mining Contingency 14,671,389
DSTF Sustaining 23,806,666
Rio Sucio Power Line 5,614,521
Closure Costs 3,000,000
Total $131,299,895
Source: CGM/SRK, 2020
Table 21-11: MDZ Sustaining Capital (2023 to 2027) (US$)
Description 2023 2024 2025 2026 2027
Drilling - - - - -
Development 2,735,635 4,986,400 3,834,632 2,168,451 3,433,459
Mine Equipment Purchases 6,646,459 3,972,308 - - 1,186,305
Mine Equipment Rebuilds - 1,162,732 2,300,471 4,985,557 4,601,468
Mining Services - - - - -
Mining Owner's Cost 1,689,596 943,372 402,871 227,366 487,479
Mining Contingency 1,322,664 1,704,601 1,307,595 1,476,275 1,799,109
DSTF Sustaining 6,817,007 21,934 64,320 15,054 13,150,673
Rio Sucio Power Line 280,726 561,452 561,452 561,452 561,452
Closure Costs - - - - -
Total $19,492,087 $13,352,799 $8,471,341 $9,434,155 $25,219,945
Source: CGM/SRK, 2020
Table 21-12: MDZ Sustaining Capital (2028 to 2033) (US$)
Description 2028 2029 2030 2031 2032 2033
Drilling - - - - - -
Development 6,412,653 3,918,836 3,897,980 2,467,849 429,949 -
Mine Equipment Purchases 208,000 4,232,979 920,793 - - -
Mine Equipment Rebuilds 681,459 4,291,695 2,278,851 6,399,725 160,047 -
Mining Services - - - - - -
Mining Owner's Cost 454,151 875,725 507,741 258,506 45,817 -
Mining Contingency 1,540,853 2,184,960 1,382,954 1,825,216 127,163 -
DSTF Sustaining 166,510 2,714,184 502,892 166,510 187,582 -
Rio Sucio Power Line 561,452 561,452 561,452 561,452 561,452 280,726
Closure Costs - - - - - 3,000,000
Total $10,025,079 $18,779,831 $10,052,664 $11,679,257 $1,512,011 $3,280,726
Source: CGM/SRK, 2020
In the case of development sustaining capital, these costs are derived from the mining schedule
prepared by SRK. The prepared mining schedule includes meters of development in waste; this
schedule of meters was combined with unit costs, based on site specific data, to estimate the cost of
this development operation. The development in waste costs assumes that this operation will be
performed by a mix of contractors and the owner. Table 21-13 presents the assumed development
unit costs and Table 21-14 and Table 21-15 present the scheduled meters for the sustaining period.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 436
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 21-13: MDZ Development Sustaining Capital Unit Costs
Description US$/m
Lateral Development
Main Truck Ramp-RMT-5.5x5.5 (m) 2,158
Drift-FWA-5x5 (m) 2,301
Ventilation Connections-VCX-4.5x4.5 (m) 1,903
Stope Drifts Waste-DFA-4.5x4.5 (m) 2,640
Vertical Development
Blasted Raise-BRS-3x3 (m) 2,292
Raisebore 5m dia-RS1 (m) 7,618
Raisebore 4.5m dia-RS2 (m) 5,184
Source: CGM/SRK, 2020
Table 21-14: MDZ Development Sustaining Capital Meters (2023 to 2027) (US$)
Description 2023 2024 2025 2026 2027
Lateral Development
Main Truck Ramp-RMT-5.5x5.5 (m) - - - - 861
Drift-FWA-5x5 (m) 396 793 492 374 213
Ventilation Connections-VCX-4.5x4.5 (m) 23 69 109 98 -
Stope Drifts Waste-DFA-4.5x4.5 (m) 501 1,149 945 425 411
Vertical Development
Blasted Raise-BRS-3x3 (m) 21 - - - -
Raisebore 5m dia-RS1 (m) 54 - - - -
Raisebore 4.5m dia-RS2 (m) - - - - -
Source: CGM/SRK, 2020
Table 21-15: MDZ Development Sustaining Capital Meters (2028 to 2032)
Description 2028 2029 2030 2031 2032
Lateral Development
Main Truck Ramp-RMT-5.5x5.5 (m) 1,136 23 - - -
Drift-FWA-5x5 (m) 433 534 438 264 -
Ventilation Connections-VCX-4.5x4.5 (m) 73 83 84 26 -
Stope Drifts Waste-DFA-4.5x4.5 (m) 265 926 1,034 686 163
Vertical Development
Blasted Raise-BRS-3x3 (m) 17 17 - - -
Raisebore 5m dia-RS1 (m) - - - - -
Raisebore 4.5m dia-RS2 (m) 403 - - - -
Source: CGM/SRK, 2020
SRK prepared a schedule of required mining equipment and services and estimated mining sustaining
capital including equipment replacements, rebuilds and related services and administration
(Table 21-16 and Table 21-17).
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 437
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 21-16: MDZ Mining Sustaining Capital (2023 to 2027) (US$)
Description 2023 2024 2025 2026 2027
Lateral Capital Development 2,276,490 4,986,400 3,834,632 2,168,451 3,433,459
Vertical Capital Development 459,145 - - - -
Mining Equipment 5,346,144 2,941,369 - - -
Auxiliary Equipment 1,092,315 418,689 - - 1,186,305
Miscellaneous Equipment 208,000 612,250 - - -
Ventilation Equipment - - - - -
Mining Equipment Rebuilds - 347,627 949,777 1,104,952 3,470,255
Auxiliary Equipment Rebuilds - 815,105 1,244,014 1,983,045 1,131,213
Miscellaneous Equipment Rebuilds - - - - -
Ventilation Equipment Rebuilds - - 106,680 1,897,560 -
Mine Services - - - - -
Owner's Cost 1,689,596 943,372 402,871 227,366 487,479
Sub-Total 11,071,691 11,064,812 6,537,974 7,381,375 9,708,711
Mining Contingency (17.4%) 1,322,664 1,704,601 1,307,595 1,476,275 1,799,109
Total $12,394,354 $12,769,413 $7,845,569 $8,857,650 $11,507,820
Source: CGM/SRK, 2020
Table 21-17: MDZ Mining Sustaining Capital (2028 to 2032) (US$)
Description 2028 2029 2030 2031 2032
Lateral Capital Development 4,284,988 3,878,792 3,897,980 2,467,849 429,949
Vertical Capital Development 2,127,666 40,044 - - -
Mining Equipment - 2,762,379 920,793 - -
Auxiliary Equipment - 1,380,600 - - -
Miscellaneous Equipment 208,000 90,000 - - -
Ventilation Equipment - - - - -
Mining Equipment Rebuilds 552,476 2,540,692 1,340,827 3,867,556 -
Auxiliary Equipment Rebuilds 128,983 1,751,002 938,024 2,385,168 160,047
Miscellaneous Equipment Rebuilds - - - - -
Ventilation Equipment Rebuilds - - - 147,000 -
Mine Services - - - - -
Owner's Cost 454,151 875,725 507,741 258,506 45,817
Sub-Total 7,756,264 13,319,234 7,605,365 9,126,079 635,814
Mining Contingency (17.4%) 1,540,853 2,184,960 1,382,954 1,825,216 127,163
Total $9,297,116 $15,504,194 $8,988,320 $10,951,295 $762,976
Source: CGM/SRK, 2020
SRK prepared PFS level DSTF designs to support the MDZ operation. The yearly capital cost
estimates for the DSTF infrastructure is presented in Table 21-18 and Table 21-19.
Table 21-18: MDZ DSTF Sustaining Capital (2023 to 2027) (US$)
Description 2023 2024 2025 2026 2027
Earthworks, Direct - 14,672 - - 7,734,609
Supervision/Overheads/Profit - 4,402 - - 2,320,383
Equipment - - 55,930 13,090 1,380,376
SubTotal - 19,073 55,930 13,090 11,435,368
Contingency (15%) - 2,861 8,390 1,964 1,715,305
Total - 21,934 64,320 15,054 13,150,673
Source: CGM/SRK, 2020
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 438
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 21-19: MDZ DSTF Sustaining Capital (2028 to 2032)
Description 2028 2029 2030 2031 2032
Earthworks, Direct 111,378 111,378 130,421 111,378 115,404
Supervision/Overheads/Profit 33,413 33,413 39,126 33,413 34,621
Equipment - 2,215,369 267,750 - 13,090
SubTotal 144,791 2,360,160 437,297 144,791 163,115
Contingency (15%) 21,719 354,024 65,595 21,719 24,467
Total 166,510 2,714,184 502,892 166,510 187,582
Source: CGM/SRK, 2020
Additional power requirements to support MDZ will be provided by the Rio Sucio Power infrastructure.
An estimate was prepared by CGM and a 10 year payment schedule is included in the sustaining
capital. Table 21-20 presents the assumptions of this payment schedule.
Table 21-20: MDZ Rio Sucio Power Line Sustaining Capital (2028 to 2032)
Description Value Unit
Rio Sucio S/S 115 kV 1,314,324 US$
15 km Lines 115kV 1,315,387 US$
MDZ S/S 115 kV 608,617 US$
HV - Total Capex 3,238,328 US$
Year Interest 11.50 %
Period 10 Years
Starting Year 2,023 US$
Down-Payment - US$
Yearly Payment 561,452 US$/year
Source: CGM, 2020
Project closure costs are based on a budget estimate prepared by CGM and reviewed by SRK.
21.2 Operating Cost Estimates
SRK, Ausenco and CGM prepared the estimate of operating costs for the PFS production schedule.
Marmato UZ LoM cost estimate is presented in Table 21-21 and MDZ LoM cost estimate is presented
in Table 21-22
Table 21-21: Marmato UZ Operating Costs Summary
Description LoM (US$/t-Ore) LoM (US$000’s)
Mining 48.45 249,251
Process 13.86 71,283
G&A 13.82 71,086
Total Operating 76. 12 391,620
Source: CGM/SRK/, 2020
Table 21-22: Marmato MDZ Operating Costs Summary
Description LoM (US$/t-Ore) LoM (US$000’s)
Mining 35.19 512,288
Process 13.68 199,113
G&A 8.23 119,771
Total Operating $57.10 $831,173
Source: CGM/SRK/Ausenco, 2020
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 439
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
21.3 Basis for Operating Cost Estimates
The prepared estimates that compose the operating costs consist of domestic and international
services, equipment, labor, etc. Where required, the following were included:
• Value added tax
• Freight
• Duty
It was assumed that the mill operates 350 days per year under a daily schedule of two shifts of 12
hours.
The operating cost estimates are based on the quantities associated with the production schedule,
including the following:
• Development meters
• Stope ore tonnage
• Ore tonnage
All operating costs include supervision staff, operations labor, maintenance labor, consumables,
electricity, fuels, lubricants, maintenance parts and any other operating expenditure identified by
contributing engineers.
21.3.1 Marmato UZ
Site-specific 2019 budget estimates were used to estimate the LoM operating costs of the Marmato
UZ. The following costs were used to estimate the operating cost of this mining area:
• Vein mining: US$47.00/t-stope, which includes backfill costs
• Transition mining: US$42.00/t-stope, which includes backfill costs
Additionally, development operating costs are derived from the mining schedule prepared by SRK.
The prepared mining schedule includes meter of development in ore, this schedule of meters was
combined with unit costs, based on site specific data, to estimate the cost of this development
operation. The development in ore costs assume that this operation will be performed by the owner.
Table 21-23 presents the assumed development unit cost, while Table 21-24 presents the scheduled
meters for the operating years.
Table 21-23: Marmato UZ Operating Development Unit Costs
Description US$/m
Veins Development -DEV-2.2x2.2 (m) 1,050
Trans Ore Xcut -XCT2-4x3.5 (m) 1,500
Source: CGM/SRK, 2020
Table 21-24: Marmato UZ Operating Development Meters (2020 to 2024)
Description LoM 2020 2021 2022 2023 2024
Veins Development -DEV-2.2x2.2 (m) 16,558 2,274 5,150 5,130 3,896 108
Trans Ore Xcut -XCT2-4x3.5 (m) 2,161 185 609 1,121 246 -
Source: CGM/SRK, 2020
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 440
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
The Marmato UZ mineral processing costs were modeled with fixed and variable components. These
are based on the recent years of operation and are presented in Table 21-25.
Table 21-25: Marmato UZ Mineral Processing Operating Costs
Description Value Unit
Fixed Processing Cost 1,801,402 US$/year
Variable Processing Cost 7.29 US$/t
Source: CGM/SRK, 2020
Marmato’s UZ tailings and G&A costs were modeled as fixed costs. Table 21-26 and Table 21-27
present the estimated yearly costs.
Table 21-26: Marmato UZ TSF And G&A Operating Costs (2020 to 2026) (US$)
Description 2020 2021 2022 2023 2024 2025 2026
TSF 778,882 1,550,161 1,756,531 1,523,013 1,234,802 899,824 1,081,687
G&A 5,468,187 5,468,187 5,468,187 5,468,187 5,468,187 5,468,187 5,468,187
Source: CGM/SRK, 2020
Table 21-27: Marmato UZ DSTF And G&A Operating Costs (2027 to 2033) (US$)
Description 2027 2028 2029 2030 2031 2032
TSF 1,010,560 845,920 991,408 974,133 1,087,847 211,547
G&A 5,468,187 5,468,187 5,468,187 5,468,187 5,468,187 5,468,187
Source: CGM/SRK, 2020
21.3.2 MDZ
Cost models prepared by SRK and Ausenco based on site-specific inputs from CGM were used to
estimate the LoM operating costs of the MDZ.
SRK prepared a cost model to estimate the mining operating costs associated with the MDZ mining
schedule. This model estimates the cost associated with each operation that composes the mining
area and the estimated yearly costs by process are presented in Table 21-28 and Table 21-29.
Table 21-28: MDZ Mining Operating Costs (2023 to 2027) (US$)
Description 2023 2024 2025 2026 2027
Operating Development 2,895,921 5,819,528 4,707,591 2,056,179 2,063,319
Production Drilling 293,228 3,109,452 3,650,647 3,921,192 3,922,850
Production Blasting 675,392 7,162,013 8,408,547 9,031,694 9,035,514
Production Mucking 87,085 923,466 1,084,194 1,164,542 1,165,034
Production Backfill 677,230 7,881,996 8,930,047 9,733,981 9,476,936
Hauling 659,658 3,085,207 3,106,364 2,933,110 3,330,938
Mine Services and Maintenance 4,225,975 9,522,563 7,581,680 7,699,826 7,845,331
Rehabilitation - 52,500 140,000 140,000 210,000
Definition Drilling 316,817 600,000 600,000 600,000 600,000
Operating and Maintenance Hourly 3,321,537 6,934,112 6,934,112 6,934,112 6,934,112
Operating and Maintenance Staff 1,527,717 3,055,433 3,055,433 3,055,433 3,055,433
Sub-Total 14,680,559 48,146,271 48,198,615 47,270,068 47,639,468
Contingency 835,612 3,589,613 3,749,438 3,823,601 3,803,514
Total $15,516,171 $51,735,884 $51,948,053 $51,093,669 $51,442,981
Source: CGM/SRK, 2020
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 441
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 21-29: MDZ Mining Operating Costs (2028 to 2033)
Description 2028 2029 2030 2031 2032 2033
Operating Development 830,800 2,811,103 3,262,893 3,044,206 1,156,400 -
Production Drilling 4,061,297 3,845,843 3,797,217 3,818,841 4,024,168 3,799,470
Production Blasting 9,354,399 8,858,144 8,746,142 8,795,950 9,268,879 8,751,332
Production Mucking 1,206,151 1,142,164 1,127,723 1,134,145 1,195,124 1,128,392
Production Backfill 9,827,813 7,805,596 8,022,274 8,044,576 9,683,728 9,118,607
Hauling 3,624,384 3,459,024 4,000,399 3,925,646 3,419,127 1,837,274
Mine Services and Maintenance 7,881,397 7,917,462 7,838,608 7,838,608 6,875,608 6,610,040
Rehabilitation 280,000 280,000 280,000 280,000 280,000 280,000
Definition Drilling 685,648 605,100 450,000 - - -
Operating and Maintenance Hourly 6,934,112 6,787,922 6,681,992 6,681,992 5,709,442 4,221,780
Operating and Maintenance Staff 3,055,433 3,055,433 3,055,433 2,843,575 2,075,173 1,801,518
Sub-Total 47,741,435 46,567,791 47,262,682 46,407,538 43,687,649 37,548,413
Contingency 3,861,244 3,499,229 3,566,475 3,527,063 3,636,942 3,245,212
Total $51,602,678 $50,067,020 $50,829,157 $49,934,601 $47,324,590 $40,793,625
Source: CGM/SRK, 2020
Ausenco estimated the MDZ mineral processing operating cost as part of the PFS. This cost was
considered entirely variable and its detail is presented in Table 21-30.
Table 21-30: MDZ Mineral Processing Cost
Processing US$/t-milled
Labor 0.89
Comminution Consumables 2.69
Reagents/Consumables 4.25
Power 3.66
Maintenance & Lubrication Supplies 0.59
Laboratory 0.16
Vehicles 0.07
Water Treatment 0.09
Total Process Operating Costs 12.40
Source: CGM/Ausenco, 2020
MDZ tailings and G&A costs were modeled as fixed costs. Table 21-26 and Table 21-27 present the
estimated yearly costs.
Table 21-31: MDZ DSTF And G&A Operating Costs (2023 to 2027)
Description 2023 2024 2025 2026 2027
DSTF 509,413 1,718,748 1,820,976 1,690,050 1,721,338
G&A 7,370,93 12,880,949 11,551,961 11,551,974 11,551,974
Source: CGM/SRK, 2020
Table 21-32: MDZ DSTF And G&A Operating Costs (2028 to 2033)
Description 2028 2029 2030 2031 2032 2033
DSTF 1,745,584 2,029,329 2,057,835 1,991,088 1,741,293 1,593,741
G&A 11,552,136 1,546,385 11,540,807 11,345,639 10,855,370 8,023,006
Source: CGM/SRK, 2020
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 442
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
22 Economic Analysis SRK prepared a cash flow model to evaluate Marmato’s ore reserves. This model was prepared in
quarterly periods from the beginning of the year 2020 to the end of 2024, after which it was modeled
in yearly periods. This section presents the main assumptions used in this cash flow model and its
outcomes. All financial data is first quarter 2020 and currency is in U.S. dollars (US$), unless otherwise
stated.
22.1 External Factors
Assumed prices are based on the long-term outlook for gold and silver. This projection is well below
the current spot prices and the long-term views of relevant market analysis in the precious metal sector.
Table 22-1 presents the prices used for the cash flow modelling and resources estimation.
Table 22-1: Marmato Price Assumptions
Description Value Unit
Gold 1,400 US$/oz
Silver 17.00 US$/oz
Source: CGM, 2020
All cost inputs prepared for the cash flow model used a mixture of costs estimated in U.S. Dollars and
in Colombian Pesos. All cost estimates that were denominated in Colombian Pesos were converted
to US Dollars using a foreign exchange conversion rate of 3,300 Colombian Pesos per U.S. Dollars.
Marmato currently has a long-term supply agreement for the sale of its products to an international
refinery who take delivery of doré from the mine at designated transfer points in Colombia. The refinery
is responsible for shipping the products abroad. The refining costs and discounts associated with the
sales of the products are based on this agreement. This study was prepared under the assumption
that the Project will sell doré containing gold and silver.
Treatment charges and NSR terms are summarized in Table 22-2.
Table 22-2: Marmato NSR Terms
Description Value Units
Doré
Payable Gold 100%
Doré Smelting & Refining Charges 6.38 US$/oz-Au
Source: CGM, 2020
22.2 Production Assumptions
Marmato’s operation is supported by the production of doré bars containing gold and silver. The doré
bars result from the mineral processing of RoM containing gold and silver from an underground mining
operation. Table 22-3 presents this PFS’s life of mine production summary.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 443
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 22-3: Marmato Production Summary
LoM
Marmato Upper Zone
Stope Ore (t) 4,997,091
Dev Ore (t) 147,572
Total Ore (t) 5,144,663
Au Head Grade (g/t) 4.16
Ag Head Grade (g/t) 15.41
Au Contained (oz) 687,339
Ag Contained (oz) 2,549,213
Waste (t) 338,204
Total Material Mined (t) 5,482,867
Marmato Deeps Zone
Stope Ore (t) 13,511,892
Dev Ore (t) 1,044,054
Total Ore (t) 14,555,946
Au Head Grade (g/t) 2.85
Ag Head Grade (g/t) 3.84
Au Contained (oz) 1,332,795
Ag Contained (oz) 1,799,022
Waste (t) 1,806,960
Total (t) 16,362,906
Total Mine Production
Stope Ore Tonnes (t) 18,508,983
Dev Ore Tonnes (t) 1,191,626
Total Ore Tonnes 19,700,609
Au Head Grade (g/t) 3.19
Ag Head Grade (g/t) 6.87
Au Contained (oz) 2,020,134
Ag Contained (oz) 4,348,236
Waste (t) 2,145,164
Total Material Mined (t) 21,845,773
Source: SRK, 2020
The Marmato operation is composed of two major mining areas, namely the Marmato UZ and the
MDZ.
The Marmato UZ is a mining operation that exploits the upper portion of the mineral deposit, it is
represented by the current operation, which is composed by an underground mining operation and an
existing mineral processing plant. The production schedule prepared for the Marmato UZ does not
consider a pre-production period, as this part of the operation is currently producing. The production
schedule assumes an expansion of the mining and mineral processing operations starting in 2021.
This expansion is planned to ramp-up in the years of 2021 and 2022 and reach full capacity in the year
2023.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 444
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
The MDZ is a future mining operation that will exploit the lower portion of the deposit that will support
an expansion of the Marmato operation. This will require the installation of a mining operation and a
mineral processing facility dedicated to this area of the mineral deposit. The mineral processing circuit
will also extract doré bars containing gold and silver from run of mine from the MDZ. The mine schedule
for the MDZ assumes a pre-production period of three and a half years, which consists of a delay of
six months followed by a construction period of another three years.
The Marmato UZ mine production is based on a LoM assumed average mining rate of 1,155 t/d and
maximum mining rate of 1,648 t/d, including movement of both ore and waste and based on a
denominator of 365 days per year. The MDZ mine production is based on a LoM assumed average
mining rate of 4,115 t/d and maximum mining rate of 4,515 t/d, this includes movement of both ore and
waste and is based on a denominator of 365 days per year. The combined total mine movement is
limited to a maximum of 2 Mt/y.
The mine schedule does not include any stockpiling, all of the blending of RoM is done in the mine or
in a designated area before the plant feed. Table 22-4 and Table 22-5 presents the yearly LoM mine
production assumptions by area.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 445
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 22-4: Marmato Yearly (2020 to 2026) Mine Production Assumptions
2020 2021 2022 2023 2024 2025 2026
Marmato UZ
Stope Ore (t) 256,454 393,457 439,606 501,914 491,238 388,538 452,030
Dev Ore (t) 29,717 44,028 50,444 23,087 296 - -
Total Ore (t) 286,171 437,485 490,050 525,001 491,534 388,538 452,030
Au Head Grade (g/t) 3.66 3.99 3.95 3.97 3.96 4.39 4.30
Ag Head Grade (g/t) 16.83 14.51 13.06 14.86 16.25 16.98 15.75
Au Contained (oz) 33,668 56,077 62,288 67,074 62,579 54,875 62,529
Ag Contained (oz) 154,890 204,032 205,843 250,803 256,794 212,132 228,933
Waste (t) 51,600 127,256 111,535 46,566 1,247 - -
Total Material Mined (t) 337,771 564,741 601,585 571,567 492,781 388,538 452,030
MDZ
Stope Ore (t) - - - 103,599 1,098,587 1,289,794 1,385,379
Dev Ore (t) - - - 105,415 212,080 171,776 75,270
Total Ore (t) - - - 209,014 1,310,667 1,461,570 1,460,649
Au Head Grade (g/t) - - - 3.10 3.15 3.27 3.41
Ag Head Grade (g/t) - - - 4.65 4.43 4.47 4.85
Au Contained (oz) - - - 20,831 132,913 153,659 160,137
Ag Contained (oz) - - - 31,272 186,520 210,048 227,761
Waste (t) - 63,504 284,055 299,957 196,560 149,907 87,318
Total (t) - 63,504 284,055 508,971 1,507,227 1,611,477 1,547,967
Total
Stope Ore Tonnes (t) 256,454 393,457 439,606 605,513 1,589,825 1,678,332 1,837,409
Dev Ore Tonnes (t) 29,717 44,028 50,444 128,502 212,376 171,776 75,270
Total Ore Tonnes 286,171 437,485 490,050 734,015 1,802,201 1,850,108 1,912,679
Au Head Grade (g/t) 3.66 3.99 3.95 3.72 3.37 3.51 3.62
Ag Head Grade (g/t) 16.83 14.51 13.06 11.95 7.65 7.10 7.43
Au Contained (oz) 33,668 56,077 62,288 87,905 195,492 208,534 222,666
Ag Contained (oz) 154,890 204,032 205,843 282,075 443,314 422,180 456,694
Waste (t) 51,600 190,760 395,590 346,523 197,807 149,907 87,318
Total Material Mined (t) 337,771 628,245 885,640 1,080,538 2,000,008 2,000,015 1,999,997
Source: SRK, 2020
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 446
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 22-5: Marmato Yearly (2027 to 2033) Mine Production Assumptions
2027 2028 2029 2030 2031 2032 2033
Marmato UZ
Stope Ore (t) 409,596 351,864 386,605 388,892 445,184 91,713 -
Dev Ore (t) - - - - - - -
Total Ore (t) 409,596 351,864 386,605 388,892 445,184 91,713 -
Au Head Grade (g/t) 4.34 4.37 4.30 4.18 4.43 4.22 -
Ag Head Grade (g/t) 15.23 14.42 14.33 14.43 17.43 21.69 -
Au Contained (oz) 57,171 49,475 53,418 52,299 63,442 12,443 -
Ag Contained (oz) 200,574 163,168 178,148 180,463 249,477 63,956 -
Waste (t) - - - - - - -
Total Material Mined (t) 409,596 351,864 386,605 388,892 445,184 91,713 -
MDZ
Stope Ore (t) 1,385,965 1,434,879 1,358,758 1,341,578 1,349,218 1,421,761 1,342,374
Dev Ore (t) 75,157 30,299 102,341 118,804 110,823 42,089 -
Total Ore (t) 1,461,122 1,465,178 1,461,099 1,460,382 1,460,041 1,463,850 1,342,374
Au Head Grade (g/t) 2.94 2.77 2.47 2.33 2.50 2.79 2.84
Ag Head Grade (g/t) 4.54 4.04 2.87 3.11 3.01 3.22 3.85
Au Contained (oz) 138,110 130,485 116,029 109,399 117,354 131,308 122,570
Ag Contained (oz) 213,272 190,311 134,819 146,022 141,294 151,546 166,160
Waste (t) 129,281 182,953 152,291 150,710 94,775 15,649 -
Total (t) 1,590,403 1,648,131 1,613,390 1,611,092 1,554,816 1,479,499 1,342,374
Total
Stope Ore Tonnes (t) 1,795,561 1,786,743 1,745,363 1,730,470 1,794,402 1,513,474 1,342,374
Dev Ore Tonnes (t) 75,157 30,299 102,341 118,804 110,823 42,089 -
Total Ore Tonnes 1,870,718 1,817,042 1,847,704 1,849,274 1,905,225 1,555,563 1,342,374
Au Head Grade (g/t) 3.25 3.08 2.85 2.72 2.95 2.87 2.84
Ag Head Grade (g/t) 6.88 6.05 5.27 5.49 6.38 4.31 3.85
Au Contained (oz) 195,281 179,960 169,447 161,698 180,795 143,751 122,570
Ag Contained (oz) 413,846 353,478 312,968 326,485 390,770 215,502 166,160
Waste (t) 129,281 182,953 152,291 150,710 94,775 15,649 -
Total Material Mined (t) 1,999,999 1,999,995 1,999,995 1,999,984 2,000,000 1,571,212 1,342,374
Source: SRK, 2020
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 447
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Marmato UZ is burdened by development waste only during its first four years of production, its gold
and silver grades are mostly stable through the life of the mining area. MDZ presents more
development in waste between the years of 2021 and 2023 to open the mining area for production.
Once ore production ramps-up the waste development is mostly stable throughout the life of the mining
area; its gold and silver grades present a slight decline as the production advances.
The resulting combined mine production profile presents modestly increasing ore production between
the years of 2020 and 2023 and a large expansion in the production capacity once the MDZ ramps-up
in 2024. The silver grade declines through the life of mine, which is related to MDZ having a much
lower silver grade than Marmato UZ. The gold grade declines from around 4 g/t down to around 3 g/t
over the course of the production life.
Figure 22-1 and Figure 22-2 show each mine area’s RoM ore production, while Figure 22-3
consolidates the two mining operations into a single production profile.
Source: SRK, 2020
Figure 22-1: Marmato UZ Mine Production Profile
Source: SRK, 2020
Figure 22-2: MDZ Mine Production Profile
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 448
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SRK, 2020
Figure 22-3: Marmato Combined UZ and MDZ Mine Production Profile
The Marmato operation’s doré production is supported by two mineral processing facilities, a plant that
beneficiates the run of mine from Marmato UZ and a second plant that will beneficiate the run of mine
from MDZ.
The Marmato UZ is currently producing and is supported by an existing mineral processing plant. The
mineral processing production schedule assumes an expansion of the mineral processing operations
starting in 2021. This expansion is planned to ramp-up in the years of 2021 and 2022 and reach full
capacity in the year of 2023.
The processing of the MDZ run of mine will require the installation of a mineral processing facility
dedicated to this area of the mineral deposit. The mineral processing circuit will also extract doré bars
containing gold and silver from run of mine from MDZ.
The Marmato UZ mineral processing production is based on a LoM assumed average processing rate
of 1,084 t/d and maximum ore mining rate of 1,438 t/d, based on a denominator of 365 days per year.
The MDZ mineral processing production is based on a LoM assumed average processing rate of 3,677
t/d and maximum ore mining rate of 4,014 t/d, based on a denominator of 365 days per year
Table 22-6 presents the projected LoM plant production for the Marmato UZ, MDZ and the combined
mineral processing throughput.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 449
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 22-6: Marmato Mill Production Assumptions
LoM
Marmato UZ
Ore Feed (t) 5,144,663
Ore Feed Au Head Grade (g/t) 4.16
Ore Feed Ag Head Grade (g/t) 15.41
Ore Feed Contained Au (oz) 687,339
Ore Feed Contained Ag (oz) 2,549,213
Gold Recovery (%) 87%
Silver Recovery (%) 33%
Recovered Gold (oz) 598,939
Recovered Silver (oz) 846,780
MDZ
Ore Feed (t) 14,555,946
Ore Feed Au Head Grade (g/t) 2.85
Ore Feed Ag Head Grade (g/t) 3.84
Ore Feed Contained Au (oz) 1,332,795
Ore Feed Contained Ag (oz) 1,799,022
Gold Recovery (%) 95%
Silver Recovery (%) 40%
Recovered Gold (oz) 1,266,155
Recovered Silver (oz) 719,609
Total
Ore Feed (t) 19,700,609
Ore Feed Au Head Grade (g/t) 3.19
Ore Feed Ag Head Grade (g/t) 6.87
Ore Feed Contained Au (oz) 2,020,134
Ore Feed Contained Ag (oz) 4,348,236
Gold Recovery (%) 92%
Silver Recovery (%) 36%
Recovered Gold (oz) 1,865,094
Recovered Silver (oz) 1,566,389
Source: SRK, 2020
Table 22-7 and Table 22-8 present the projected yearly plant production for Marmato UZ, MDZ and
the combined mineral processing throughput.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 450
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 22-7: Marmato Mill Production Schedule (2020 - 2026)
2020 2021 2022 2023 2024 2025 2026
Marmato UZ
Ore Feed (t) 286,171 437,485 490,050 525,001 491,534 388,538 452,030
Ore Feed Au Head Grade (g/t) 3.66 3.99 3.95 3.97 3.96 4.39 4.30
Ore Feed Ag Head Grade (g/t) 16.83 14.51 13.06 14.86 16.25 16.98 15.75
Ore Feed Contained Au (oz) 33,668 56,077 62,288 67,074 62,579 54,875 62,529
Ore Feed Contained Ag (oz) 154,890 204,032 205,843 250,803 256,794 212,132 228,933
Gold Recovery (%) 87% 87% 87% 87% 87% 87% 87%
Silver Recovery (%) 33% 33% 33% 33% 33% 33% 33%
Recovered Gold (oz) 29,338 48,865 54,277 58,448 54,531 47,817 54,487
Recovered Silver (oz) 51,450 67,774 68,375 83,310 85,300 70,465 76,045
MDZ
Ore Feed (t) - - - 209,014 1,310,667 1,461,570 1,460,649
Ore Feed Au Head Grade (g/t) - - - 3.10 3.15 3.27 3.41
Ore Feed Ag Head Grade (g/t) - - - 4.65 4.43 4.47 4.85
Ore Feed Contained Au (oz) - - - 20,831 132,913 153,659 160,137
Ore Feed Contained Ag (oz) - - - 31,272 186,520 210,048 227,761
Gold Recovery (%) 0% 0% 0% 95% 95% 95% 95%
Silver Recovery (%) 0% 0% 0% 40% 40% 40% 40%
Recovered Gold (oz) - - - 19,789 126,268 145,976 152,130
Recovered Silver (oz) - - - 12,509 74,608 84,019 91,104
Total
Ore Feed (t) 286,171 437,485 490,050 734,015 1,802,201 1,850,108 1,912,679
Ore Feed Au Head Grade (g/t) 3.66 3.99 3.95 3.72 3.37 3.51 3.62
Ore Feed Ag Head Grade (g/t) 16.83 14.51 13.06 11.95 7.65 7.10 7.43
Ore Feed Contained Au (oz) 33,668 56,077 62,288 87,905 195,492 208,534 222,666
Ore Feed Contained Ag (oz) 154,890 204,032 205,843 282,075 443,314 422,180 456,694
Gold Recovery (%) 87% 87% 87% 89% 92% 93% 93%
Silver Recovery (%) 33% 33% 33% 34% 36% 37% 37%
Recovered Gold (oz) 29,338 48,865 54,277 78,237 180,798 193,793 206,617
Recovered Silver (oz) 51,450 67,774 68,375 95,819 159,908 154,484 167,150
Source: SRK, 2020
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 451
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 22-8: Marmato Mill Production Schedule (2027 - 2033)
2027 2028 2029 2030 2031 2032 2033
Marmato UZ
Ore Feed (t) 409,596 351,864 386,605 388,892 445,184 91,713 -
Ore Feed Au Head Grade (g/t)
4.34 4.37 4.30 4.18 4.43 4.22 -
Ore Feed Ag Head Grade (g/t)
15.23 14.42 14.33 14.43 17.43 21.69 -
Ore Feed Contained Au (oz) 57,171 49,475 53,418 52,299 63,442 12,443 -
Ore Feed Contained Ag (oz) 200,574 163,168 178,148 180,463 249,477 63,956 -
Gold Recovery (%) 87% 87% 87% 87% 87% 87% 0%
Silver Recovery (%) 33% 33% 33% 33% 33% 33% 0%
Recovered Gold (oz) 49,818 43,112 46,548 45,573 55,282 10,843 -
Recovered Silver (oz) 66,625 54,200 59,176 59,945 82,869 21,244 -
MDZ
Ore Feed (t) 1,461,12
2 1,465,17
8 1,461,09
9 1,460,38
2 1,460,04
1 1,463,85
0 1,342,37
4 Ore Feed Au Head Grade (g/t)
2.94 2.77 2.47 2.33 2.50 2.79 2.84
Ore Feed Ag Head Grade (g/t)
4.54 4.04 2.87 3.11 3.01 3.22 3.85
Ore Feed Contained Au (oz) 138,110 130,485 116,029 109,399 117,354 131,308 122,570
Ore Feed Contained Ag (oz) 213,272 190,311 134,819 146,022 141,294 151,546 166,160
Gold Recovery (%) 95% 95% 95% 95% 95% 95% 95%
Silver Recovery (%) 40% 40% 40% 40% 40% 40% 40%
Recovered Gold (oz) 131,204 123,961 110,228 103,929 111,486 124,743 116,441
Recovered Silver (oz) 85,309 76,124 53,928 58,409 56,517 60,618 66,464
Total
Ore Feed (t) 1,870,71
8 1,817,04
2 1,847,70
4 1,849,27
4 1,905,22
5 1,555,56
3 1,342,37
4 Ore Feed Au Head Grade (g/t)
3.25 3.08 2.85 2.72 2.95 2.87 2.84
Ore Feed Ag Head Grade (g/t)
6.88 6.05 5.27 5.49 6.38 4.31 3.85
Ore Feed Contained Au (oz) 195,281 179,960 169,447 161,698 180,795 143,751 122,570
Ore Feed Contained Ag (oz) 413,846 353,478 312,968 326,485 390,770 215,502 166,160
Gold Recovery (%) 93% 93% 93% 92% 92% 94% 95%
Silver Recovery (%) 37% 37% 36% 36% 36% 38% 40%
Recovered Gold (oz) 181,023 167,073 156,776 149,502 166,768 135,586 116,441
Recovered Silver (oz) 151,934 130,324 113,104 118,354 139,387 81,863 66,464
Source: SRK, 2020
The Marmato UZ presents a steady ramp-up in throughput capacity between 2020 and 2023. However,
after reaching its maximum capacity in 2023 the schedule does not use the full plant capacity in the
subsequent years. The reduction in plant throughput is related to a maximum total mine movement
permit that will only allow CGM to mine a total of 2 Mt/y of combined ore and waste. Gold and silver
production present a slight decrease.
The mineral processing facility supporting MDZ ramps up between 2023 and 2025. Once mineral
processing production ramps-up, the facility is run at a stable capacity until the end of mine life. Gold
and silver production decline slightly due to declining gold and silver grades.
The resulting combined mineral production profile presents a modest increase of plant capacity
between 2020 and 2023 and a large expansion in plant capacity once the MDZ ramps-up in 2024.
MDZ silver and gold production increases significantly in 2024 and then gradually decreases over the
remaining mine life.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 452
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Figure 22-4 and Figure 22-5 show the production profiles for the two mineral processing plants.
Figure 22-6 consolidates the two mineral processing operations into a single production profile.
Source: SRK, 2020
Figure 22-4: Marmato UZ Processing Production Profile
Source: SRK, 2020
Figure 22-5: MDZ Processing Production Profile
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 453
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SRK, 2020
Figure 22-6: Marmato Processing Production Profile
22.3 Taxes, Royalties and Other Interests
The analysis of the Marmato Project includes an effective corporate income tax rate of 30%. A
depreciation schedule was calculated by SRK assuming a 10 year straight-line depreciation.
Royalties are also deductible from taxable income. The Project includes payment of governmental
production royalties on both gold and silver sales as outlined in Section 4.3. The total royalty due,
excluding the related party royalty to Croesus, is calculated as 9.2% of gross metal sales deducted by
the costs of transportation and metal refining.
22.4 Results
SRK evaluated the Marmato Operation’s cash flow with three separate cash flows. One for each major
mining area, Marmato UZ and MDZ and one for the entirety of the Marmato Operation combining both
mining areas. This was done to confirm that the mineral reserves for each area are economic on a
stand-alone basis as well as on a combined basis.
The Marmato UZ economic modeling presents a healthy cash flow that doesn’t include any negative
periods. The first two years are close to break even, which is related to the investment to expand the
mineral processing plant and the development in waste to prepare the mining areas. The Marmato UZ
is projected to produce a pre-tax cash flow of US$319.8M over its life. Table 22-9 and Figure 22-7
present the LoM cash flow metrics and the UZ mining area’s cash flow profile respectively.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 454
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 22-9: Marmato UZ LoM Cash Flow Metrics
LoM
Marmato UZ
Gold Revenue (US$) 838,514,585
Silver Revenue (US$) 14,395,253
Doré Refining Charges (US$) (3,821,231)
Net Revenue 849,088,606
Mining Operating Costs (249,251,102)
Processing Operating Costs (71,282,947)
Other Operating Costs (71,086,437)
Total Operating Costs (391,620,486)
Royalties (78,116,152)
Sustaining Capital (59,546,192)
Working Capital -
Pre-Tax Cash Flow 319,805,777
Source: SRK, 2020
Source: SRK, 2020
Figure 22-7: Marmato UZ Cash Flow Profile
The cash flow prepared for the MDZ indicates that this mining area also projects good profitability. The
MDZ requires significant capital investment between the years of 2021 and 2023. Commercial
production starts in 2024 and this year already shows a positive cash flow, all subsequent periods also
present positive cash flows. Payback is projected to happen sometime in the year 2027 and the area
is projected to generate a pre-tax cash flow of US$381.4M through its life. Table 22-10 and Figure 22-8
present the LoM cash flow metrics and the MDZ’s cash flow profile respectively.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 455
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 22-10: MDZ LoM Cash Flow Metrics
LoM
MDZ
Gold Revenue (US$) 1,772,617,350
Silver Revenue (US$) 12,233,353
Doré Refining Charges (US$) (8,078,070)
Net Revenue 1,776,772,632
Mining Operating Costs (512,288,429)
Processing Operating Costs (199,113,126)
Other Operating Costs (119,771,142)
Total Operating Costs (831,172,697)
Royalties (163,463,082)
Initial Capital (269,394,005)
Sustaining Capital (131,299,895)
Working Capital -
Pre-Tax Cash Flow 381,442,953
Source: SRK, 2020
Source: SRK, 2020
Figure 22-8: MDZ Cash Flow Profile
When both mining areas are combined to calculate the operation’s cash flow the results indicate an
after-tax IRR of 19.5% and an after-tax NPV of approximately US$256.1 million, based on a 5%
discount rate and gold and silver prices of US$1,400/oz and US$17.00/oz respectively. The cash flow
profile also shows a shorter payback for the investment required by the MDZ, bringing it back about a
year to 2026. The operation is projected to have negative cash flows between the years 2020 and
2023, when the MDZ is installed, with payback for the expansion expected by 2026. The annual free
cash flow profile of the Project is presented in Figure 22-9. The full annual technical economic model
(TEM) is in Appendix D.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 456
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: SRK, 2020
Figure 22-9: Marmato After-Tax Free Cash Flow, Capital and Metal Production
Indicative economic results are presented in Table 22-11. The Project can be considered a gold
operation with a sub-product of silver, where gold represents 99% of the total projected revenue and
silver the remaining 1%. The underground mining cost is the heaviest burden on the operation
representing 62% of the operating cost, as presented in Figure 22-10.
Source: SRK, 2020
Figure 22-10: Marmato Operating Cost Break-Down (Combined UZ and MDZ)
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 457
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 22-11: Marmato Indicative Economic Results (Combined UZ and MDZ)
LoM Cash Flow (Unfinanced)
Total Revenue USD 2,625,861,238
Mining Cost USD (761,539,531)
Processing Cost USD (270,396,073)
G&A Cost USD (190,857,579)
Total Opex USD (1,222,793,183)
Operating Margin USD 1,403,068,055
Operating Margin Ratio % 53%
Taxes Paid USD (210,374,619)
Free Cashflow (before initial capital) USD 760,268,116
Before Tax
Free Cash Flow USD 701,248,730
NPV @ 5% USD 396,654,830
NPV @ 8% USD 279,571,263
NPV @ 10% USD 219,652,793
IRR % 26%
After Tax
Free Cash Flow USD 490,874,111
NPV @ 5% USD 256,075,253
NPV @ 8% USD 167,009,205
NPV @ 10% USD 121,855,455
IRR % 19.5%
Payback Year 2026
Source: SRK, 2020
Table 22-12 shows annual production and revenue forecasts for the life of the Project. All production
forecasts, material grades, plant recoveries and other productivity measures were developed by SRK
and CGM.
Table 22-12: Marmato LoM Annual Production and Revenues
Year Ore Tonnes
(t) Au Head
Grade (g/t) Ag Head
Grade (g/t) Recovered Gold
(oz) Recovered Silver
(oz) Pre-Tax FCF
(US$) After-Tax FCF
(US$)
2020 286,171 3.66 16.83 29,338 51,450 (3,281,096) (3,281,096)
2021 437,485 3.99 14.51 48,865 67,774 (98,299,718) (102,103,013)
2022 490,050 3.95 13.06 54,277 68,375 (92,164,816) (99,585,569)
2023 734,015 3.72 11.95 78,237 95,819 (42,309,756) (50,319,350)
2024 1,802,201 3.37 7.65 180,798 159,908 89,076,640 84,113,531
2025 1,850,108 3.51 7.10 193,793 154,484 126,352,678 102,380,468
2026 1,912,679 3.62 7.43 206,617 167,150 137,823,352 107,759,629
2027 1,870,718 3.25 6.88 181,023 151,934 95,751,085 61,799,556
2028 1,817,042 3.08 6.05 167,073 130,324 94,527,940 70,071,282
2029 1,847,704 2.85 5.27 156,776 113,104 71,792,907 52,619,644
2030 1,849,274 2.72 5.49 149,502 118,354 70,195,721 55,471,500
2031 1,905,225 2.95 6.38 166,768 139,387 87,200,108 75,778,198
2032 1,555,563 2.87 4.31 135,586 81,863 78,614,272 60,602,811
2033 1,342,374 2.84 3.85 116,441 66,464 85,969,414 76,398,172
2034 - - - - - - (831,650)
Total 19,700,609 3.19 6.87 1,865,094 1,566,389 701,248,730 490,874,111
Source: SRK, 2020
The estimated AISC, including sustaining capital, is US$880/Au-oz. Table 22-13 presents the
breakdown of the Marmato AISC.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 458
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 22-13: LoM All-in Sustaining Cost Breakdown
LoM All-in Sustaining Cost Breakdown
Mining USD/Au-oz 408
Processing USD/Au-oz 145
G&A USD/Au-oz 102
Refining USD/Au-oz 6
Royalty USD/Au-oz 130
Sustaining Capital USD/Au-oz 102
Silver Credit USD/Au-oz (14)
AISC USD/Au-oz 880
SRK’s standard Cash Cost reporting methodology for NI 43-101 reports includes smelting/refining costs; whereas CGM’s basis of reporting treats these costs as a reduction of realized gold price (the refinery discounts the selling price by a factor to cover these charges) and excludes them from its reported “total cash cost per ounce”. Source: SRK, 2020
22.5 Sensitivity Analysis
A sensitivity analysis on variation of Project costs, both capital and operating, and metal prices
indicated that cash generation is most sensitive to reduction in metal prices, or possibly loss on metal
recovery, and secondly to an increase in operating costs.
Source: SRK, 2020
Figure 22-11: Marmato NPV Sensitivity
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 459
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
23 Adjacent Properties SRK highlights to the reader as discussed in Section 14.12 that all Mineral Resources within
#CHG_081 (yellow) and upper areas of #RPP_357 (above 1,300 m MSCW) have been excluded from
the Mineral Resource statement as they were not transferred to CGM and therefore are excluded from
the Mineral Resources. These Mineral Resources are currently held by Gran Colombia which is listed
on the TSX.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 460
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
24 Other Relevant Data and Information
24.1 Project Execution Plan
This PFS project execution plan focuses on the construction of the MDZ Project. It is not intended to
discuss the UZ project ongoing operations. The development of the MDZ Project will include all
activities to support the permitting, design, procurement, and construction of the MDZ project. The
project will include a new MDZ site access, plant site and processing facility, a new MDZ mine access
to a new mining area below the existing UZ mine, MDZ tailings storage facilities, and support facilities
including a new camp and administrative area. Caldas has engaged Pathfinder, LLC to develop the
detailed project execution plan.
24.1.1 Project Objectives
The new MDZ facilities will meet all Colombian federal, provincial, state, and district design,
construction, and operating requirements, and be compliant with the Company's design standards.
The Project objectives in order of priority are:
• Achieve the highest safety, health, and environmental standards during construction and start-
up with no fatalities, no lost-time injuries, and a total recordable incident rate (TRIR) that is
less than 0.20
• Minimize the total Project investment cost
• Achieve high operational reliability for the overall facility
• Achieve the Project schedule start-up target of 2nd quarter 2023
• Apply Project development and execution best practices to achieve the Project objectives
24.1.2 General Project Description
The MDZ project is envisioned as an underground gold operation accessed by decline with
underground crushing and conveyance to the surface that will mine and process 1.46 Mt/a of ore
through a carbon-in-pulp plant to produce doré bars on-site. Tailings are disposed of in a new dry stack
facility near the process plant. Project life is currently expected to be slightly over 10 years.
The general layout of the project is presented in Figure 18-2. The new mine facilities are described in
detail in Sections 16.5, 17.3, and 18.3-18.15.
The overall MDZ Mine Project scope is generally described by the summary below:
• Exploration Drilling
• Mine Development
• Mining Equipment
• Surface Facilities and Equipment (including the new Standard Processing Facility - MDZP)
• Underground Facilities and Equipment
• Power Supply
• Access Road
• Camp
• Other Supporting Infrastructure
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 461
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
• Mineral Processing Plant
• DSTF
The Marmato Process Plant (MDZP), 4,000 t/d, is standard to the industry and includes:
• Primary crushing
• SAG/ball mill grinding
• Gravity concentration
• CIP cyanidation of the gravity tailings
• Gold elution and electrowinning
• Intensive cyanide leaching of the gravity concentrate followed by electrowinning
• Detoxification of the cyanide leach residues
• Smelting of cathode precipitates to produce final doré products
The MDZ site infrastructure includes:
• The new access road to the MDZ plant site
• The security access point at the main road
• Parking and administrative (office) area
• Plant area with crusher, crushed ore storage, reagent storage, and processing plant
• Mine truck shop, fueling system, and change house with ROM pile
• The new portal, mine waste rock storage, and mine access decline
• Paste backfill plant
• Power substation and distribution system
• Water supply from Cauca River supplementing mine dewatering and tailings water recycle
• Pump station and pipeline for tailings management
• DSTF and press filter system
24.1.3 Site Preparation and Infrastructure
Site Preparation
The project is a greenfield development and will require full development access and earthworks for
the processing site, portal location, and administrative camp area. Site prep will include clearing and
grubbing, site grading, pad preparation, and access road construction. Topsoil will be segregated and
stockpiled for closure. The site will be fenced and controlled access through a guard gate will be
established. Early works include providing access to the portal location so that the portal can be
prepared for construction of the decline to the MDZ. The process plant area will be graded to five
cascading benches following the natural topography as described in section 8.2:
• Bench 1: Filtration plant
• Bench 2: Process plant
• Bench 3: Reclaim tunnel and future pebble crusher
• Bench 4: Secondary Crusher
• Bench 5: Mine Portal
The pads will be mainly cut in west of each pad and filled in east of each pad. The transition between
each pad will be constructed of 1V:1.5H sloped grade, soil nailed stabilized slopes and Mechanically
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 462
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Stabilized Earth (MSE) retaining wall as required, following the required footprint for process plant
layout.
The pads are accessed via in plant roads at the south edge of the process plant pads. The in-plant
roads have a slope of 10% to 14% max.
Additionally, the DSTF construction prep work and initial cell construction will be conducted with the
process site preparation.
Offsite Infrastructure
The project will include a new overhead 115kV powerline to be installed by a third party from the
Salamina substation. The powerline will be financed by the third party and costs recovered through
fees during operations.
A new pumping station near the Cauca River is being designed by the Owner team and will be
constructed to provide water to both the existing mine/plant (UZ) and the MDZ project.
Onsite Facilities and Infrastructure
The site will be fenced and controlled access through a guard gatehouse with a weigh-scale will be
established. Temporary power will be provided by diesel generator supplied by contractors until line
power is available.
A second new overhead 115kV powerline will be constructed from the local utility substation to a new
MDZ substation that will be constructed at the process plant site. The MDZ substation will feed the
mine portal substation and the underground. The substation will also feed the process plant facilities
as well as the new administrative and camp area. Construction power will be provided by the individual
contractors until line power is available.
The mine pad at the portal will also provide staging for construction of the portal and decline.
Temporary fans will be installed for the mine development. Two second accesses for ventilation will
be developed near the UZ plant site and will be developed at the same time as the MDZ decline.
A pad will also be developed near the portal pad to provide future siting of the underground backfill
plant and shotcrete plant. This location could be considered for cement/concrete batch plan during the
construction development.
Water will be supplied by truck during the construction phase. A permanent feedwater tank will be
constructed at the paste backfill pad to support the mine and backfill plant. The final water supply will
be from the new water pumping station to a water tank at the process plant that will then feed the paste
plant/mine water tank.
The tailings area will be constructed using waste rock from the mine portal development and will be
concurrent with decline development.
The administrative area development will include an access road, administrative buildings and camp.
The administrative area will provide a location for staging and will provide housing during the
construction effort.
Other facilities are included in the plant discussion in Section 17 of this report.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 463
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
24.1.4 Underground Mine and Supporting Infrastructure
Once the mine bench (Bench 5) portal area is established, the MDZ decline will be developed. Mine
access will occur via a single main decline ramp that houses the conveyor from the underground
crusher to the plant. The portal is located next to the plant site, and the main conveyor decline
intersects the orebody at the midpoint of the expected mining area, dividing the orebody into an upper
and lower block. Maintenance shops, the paste backfill plant booster pump area, miscellaneous
underground support facilities, and the crusher cavity will be located on or near this level.
Two ventilation declines as the main mine access will also be constructed during the same period.
These declines are located near the existing Marmato mine.
The stope accesses are connected to a level access, which is offset approximately 20 m away from
the ends of the stopes. Each stope access typically connects to the level access, except in cases
where stopes are small and long development is required to reach the stope. In those instances, a
connection from an adjacent stope is included in the design. The level accesses connect to the main
ramp, which is offset at least 75 m from stoping into the footwall. On the northeast side of each level,
the level access connects to an intake air ventilation raise. On the southeast side, the level access
connects to an exhaust air raise.
The construction effort will build out the underground infrastructure and tie the ventilation drifts to the
MDZ mine workings. The effort will include installation of services for power, water, paste backfill,
communications, and ventilation.
24.1.5 Process Plant
The processing facilities will be constructed on multiple pads downgrade from the portal location. The
proposed flow sheet uses standard processes for:
• Crushing/Grinding
• Gravity/Leach/Adsorption
• Desorption/Electrowinning/Refining
• Cyanide Detoxification
• Tailings Thickening/Filtration
The crusher will be constructed underground and will feed a conveyor that will move the RoM material
to the surface. At the surface the material is deposited into a surge bin with feeders that feed the
secondary cone crusher. The secondary crusher discharge is conveyed to the 24-hour open air
stockpile. Crushed ore from the stockpile will feed the SAG mill via conveyor. The SAG mill material
discharges to a cyclone feed hopper and is then fed to a ball mill. The ball mill discharges to a trommel
screen that allows the undersize to feed the classification cyclone feed pumps. Cyclone underflow
slurry, after screening, is then gravity fed to an aeriation tank prior the leach circuits. A portion of the
cyclone underflow reports to a gravity concentrate and intensive leach circuit. The pregnant leach
solution is sent to the gold room for electrowinning and smelting. The other portion of the underflow
reports to the leach and adsorption circuit that then discharges to the CIP tanks. The slurry is eventually
fed to the cyanide detoxification tanks. A carbon acid wash, elution, and the regeneration circuit
remove the gold from the carbon and regenerates the barren carbon. Gold is recovered in the
electrowinning room and then smelted to produce doré.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 464
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Tailings material is processed through a tailings thickener where the underflow is moved by pump to
a filter plant where the tailings paste is filtered in two horizontal plate and frame pressure filters to
product a cake for deposit in the dry stack tailings facility. Slurry tailings also can be pumped to the
paste backfill plant and combined with cement to create backfill used in the underground mine. Filtered
tailings are removed from the loadout bunker by loader to trucks that place the material in the DSTF.
Additional facilities at the plant site include:
• Reagent storage area
• Compressed air system
• Diesel storage and fueling facility
• Propane storage
• Water systems including fresh water, process water, gland water, and firewater systems
• Maintenance shops for the surface and underground equipment
• Laboratory
• Water treatment facilities and water collection ponds
• Truck wash facility
• Explosives storage
• Mill administrative office and first aid station
• Warehouse and storage yard
• Wastewater treatment plan
24.1.6 Project Delivery Approach
EPCM/EPC Approach
The Project will be delivered through the CGM Owner’s team and an EPCM contractor that will manage
the development of a final design exercise that will develop a final cost estimate and schedule that will
lead to an EPC construction phase.
The Owner’s team will manage the offsite third-party transmission line and the water supply system
scopes.
The EPCM contractor will provide a FEL3/FEED to prepare a +/-10% cost estimate and a level 3
resource loaded project schedule for an EPC construction phase. The EPCM project will include the
mine, mill, and associated infrastructure including the DSTF.
The EPCM contractor will further develop the following: detailed design deliverables; procurement
activities; subcontractor identification and selection with Owner; develop construction contracts,
request for proposals, contract with qualified bidders, conduct bid evaluations, negotiate contracts,
and recommend contractors/contracts for Owner’s review and approval.
The EPCM contractor will also: oversee, manage, coordinate, and report on all supervised contractors
throughout the EPC phase. The EPCM contractor will also support the Owner in determining whether
each contractor is performing in accordance with the terms of its respective contract, and work to guard
the Company against defects and deficiencies in the work performed.
The EPCM contractor will be responsible for placing all material/equipment orders and management
for those third parties engaged during the EP stage of the project. As described above, the EPCM
contractor will lead the contracting program to screen construction (supervised) contractors, evaluate
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 465
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
and condition bids, and prepare an award recommendation for the Company. However, the
construction (supervised) contract(s) will be placed on the Company's paper, in Company's name, and
paid directly by the Company, after the EPCM contractor's review/verification/endorsement of the
construction (supervised) contractor's invoices. The EPCM contractor will be responsible to manage
and coordinate the construction (supervised) contractor on the Company's behalf through Project
completion and facility start-up.
Project Schedule
The Project completion date is projected to be in the second quarter of 2023. The high level schedule
is shown in Figure 24-1.
Source: CGM, 2020
Figure 24-1: Project Execution Schedule
WBS Structure
A work breakdown structure (WBS) was developed by CGM and is used for the project. The WBS is
summarized at the highest level in Table 24-1.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 466
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 24-1: Project Work Breakdown Structure – Level 1 and Level 2
WBS Description
0000 Mine & Infrastructure
0100 Exploration - Capitalized
0200 Above-ground Mining / Geology
0300 On-Site Infrastructure - Plant
0400 Off-Site Infrastructure - Excludes Plant & Mine
0500 Heap Leach
0600 Underground Mining / Geology
1000 Process Plant
1100 Crushing / Conveying
1200 Milling
1300 Flotation / Concentrate Handling
1400 Leach / Ore Separation / Sulfide Ore Processing
1500 CN Destruction
1600 Recovery
1700 Solvent Extraction / Electrowinning
1800 Reagents
1900 Plant Services
2000 Residue Management/Tailings
3000 Power
4000 Port
5000 Airport
6000 Water Management
7000 Indirect Cost
8000 Other Project Cost
9000 Owner's Cost
Source: CGM, 2020
24.1.7 Project Team Organization
The CGM Project Team will include approximately 50 individuals. The team will report through a Senior
Project Manager that reports directly to the President of the Company. The team has a number of
people in place today with the staffing schedule established. The team includes personnel for the key
functions of engineering, construction management, plant development, mine development,
commissioning, operational readiness, procurement, project controls, and health and safety. The
corporate team includes geology, environmental, security, community relations, finance, and IT. The
overall organization chart for CGM is presented in Figure 24-2. The EPCM team will report to the CGM
Senior Project Manager.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 467
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Source: CGM, 2020
Figure 24-2: MDZ Project Team
The Owner’s team with their EPCM supplements and target staffing dates is provided in Table 24-2.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 468
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 24-2: Owner’s Project Team with EPCM Supplements
Position Qty Owner Team (OT)/EPCM
Appearance Date in Org Chart
Senior Project Manager 1 OT 8/29/19
Engineer Manager 1 OT 8/29/19
Surface Infrastructure Coordinator 1 OT 6/24/20
High Voltage Coordinator - Connection 1 OT 6/24/20
Water Works Coordinator 1 OT 5/17/20
Civil Works Coordinator 1 OT 5/17/20
SME - Senior Mechanical Engineer 1 OT 5/17/20
SME - Senior Electrical Engineer 1 OT 6/24/20
SME - Senior Instrumentation and Control Engineer 1 OT 6/24/20
QA/QC Superintendent 1 OT 6/24/20
Permits 1 OT 5/17/20
Junior Engineer 2 OT 6/24/20
Construction Manager 1 OT 6/24/20
Plant Superintendent 1 OT 8/29/19
Bulk Earthworks/Tailings 1 EPCM 6/24/20
Mechanical Engineer 1 EPCM 6/24/20
Electrical Engineer 1 EPCM 6/24/20
Instrumentation and Control Engineer 1 EPCM 6/24/20
Civil Works Coordinator 1 EPCM 6/24/20
Plant Manager 1 OT 8/29/19
Metallurgical Superintendent 1 OT 6/24/20
Structural Mechanical Piping 1 OT 6/24/20
Mining Manager 1 OT 8/29/19
Horizontal Development Coordinator 1 OT 8/29/19
Vertical Development Coordinator 1 OT 6/24/20
Underground Infrastructure Coordinator 1 OT 8/29/19
Mechanical Engineer (Conveyor) 1 OT 6/24/20
Electrical Engineer (Substation) 1 OT 6/24/20
Commissioning Manager 1 EPCM 6/24/20
Readiness Manager 1 OT 6/24/20
Procurement Manager 1 OT 8/29/19
Purchases 2 OT 5/17/20
Site Administrator 1 OT 6/24/20
Logistics 1 OT 8/29/19
Project Controls Manager 1 OT 8/29/19
Document Controls 1 OT 8/29/19
Scheduler 1 OT 8/29/19
Costs Control 1 OT 8/29/19
Estimator 1 OT 5/17/20
Contracts 1 OT 8/29/19
Geology/Geotech 1 OT 8/29/19
Environmental 1 OT 8/29/19
OH&S 1 OT 8/29/19
Finance 1 OT 8/29/19
Community Relations 1 OT 8/29/19
Security Superintendent 1 OT 6/24/20
Security Coordinator 1 OT 6/24/20
Labor Total 49
Source: CGM, 2020
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 469
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
24.1.8 Project Execution Supporting Plans
As the project is advanced, the EPCM and Owner’s team will further develop plans, consistent with
CGM existing corporate structure and organization for the overall control and management of the
project that will include:
• Project Governance
• Health, Safety and Environment
• Social Responsibility
• Permitting and Regulatory
• Project Management
• Quality Management
• Constructability Management
• Human Resources Management
• Project Controls
• Document Controls and Data Management
• Engineering
• Supply Chain Management
• Construction Management
• Operational Readiness
• Commissioning
• Ramp-Up
• Project Closeout
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 470
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
25 Interpretation and Conclusions
25.1 Property Description and Ownership
SRK notes within the transfer of licenses from the previous owner, a gap between the existing licenses
for #014-89m and #RPP_057 was identified and CGM applied to the Colombian government for formal
approval to continue mining in the identified gap. SRK has reviewed the application within the
government website and notes that the status is defined as “in progress”, which has been the reported
status since September 30, 2009. The Company has been taking steps to get the approval finalized.
SRK understands that at the time of writing the issue has been resolved, with the government
determining that there is no gap and that the area falls within the license for Zona Baja (#014-89m).
SRK has not completed sufficient work to confirm this but highlights that it should be resolved and
enable additional material to be used in mine plans for future studies.
In 2017 CGM began the process and submitted to the government the application for the license
extension to the current operation and future exploration for license #014-89m, with the original license
currently held to October 2021. The process is expected to be completed in Q4 2020.
25.2 Geology and Mineralization
SRK produced an updated 3D geological model for the Marmato deposit as part of the current study.
SRK considers this to have increased the confidence in the spatial location of the various geological
units. CGM geologists as part of the on-going exploration continue to develop the geological
knowledge on the project and have supplied additional fault information which should be integrated
into further lithological models. SRK does not consider these faults to have a material impact on the
current mineral resource estimate but notes that it may impact future underground infrastructure (such
as a decline). SRK therefore recommends that the geological model be updated to reflect the impact
of these in future models and prior to construction.
25.3 Status of Exploration, Development and Operations
SRK has been supplied with electronic databases covering the sampling at the Project, all of which
have been validated by the Company. The databases comprise of a combination of historical and
recent diamond core and underground channel samples. In total, there are some 1,317 diamond
drillholes for a combined length of 266,390 m, plus 24,824 individual underground channel samples,
inclusive of current mine sampling contained in the databases. Isolated historical channel samples in
the upper portion of the mines have a degree of uncertainty on spatial location and quality as they
have not been independently verified by SRK during site visits. SRK has excluded these samples from
estimation of the porphyry units but has used them to guide the geological interpretation of the veins
at higher elevations.
Historic underground channel samples are typically taken across the width of the vein, with limited
sampling into the hanging-wall and footwall where possible. CGM geologists have made great efforts
to position the sampling as accurately as possible, but SRK has noted some limitations still exist.
These samples have been allocated separate geological codes in the modelling process as to not
influence the geological model.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 471
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
SRK is of the opinion that the exploration and assay data is sufficiently reliable to support evaluation
and classification of Mineral Resources in accordance with generally accepted CIM Estimation of
Mineral Resource and Mineral Reserve Best Practices Guidelines (2014).
SRK notes that CGM exploration continues at the project throughout 2020 and SRK has reviewed the
2020/2021 drilling plan. The drilling is targeting mineralization in the hangingwall of the current
estimate (named the New Zone), which may impact on current mining infrastructure if further
mineralization is located, which may require modifications to the current mine design. SRK therefore
recommends that the geological model and mineral resource be updated to reflect the new drilling
upon completion as the impact of these in future models may impact the design prior to construction.
25.4 Mineral Processing and Metallurgical Testing
Native gold is the predominant gold carrier and over 99% of the gold particles occurred within mineral
structures that would be readily accessible by leaching solutions.
The PFS metallurgical program optimized process parameters required to recover gold and silver
values from MDZ ore using a process flowsheet that includes gravity concentration followed by
cyanidation of the gravity tailing.
Comminution tests demonstrated that the MDZ ore is classified as hard with regard to impact breakage
and grinding characteristics.
Overall gold recovery is estimated at 95% and overall silver recovery is estimated at 51%. This is very
similar to the results from the PEA metallurgical program in which gold recovery was estimated at 95%
and silver recovery was 47%. There is little difference in reported gold recoveries for the master and
variability composites and gold recovery appears to be independent of ore grade over the range tested.
Cyanide destruction tests demonstrated that weak acid dissociable cyanide (CNWAD) could be reduced
to less than 10 mg/L with the SO2/air process. However, CNWAD levels will further attenuate to less
than 1 mg/L with time.
Pressure filtration will be required to dewater thickened tailings in order to achieve less than 15%
moisture content required for disposal in a DSTF.
25.5 Mineral Resource Estimate
The mineralization occurs in parallel, sheeted and anastomosing veins (vein domain), all of which
follow a regional structural control, with minor veins forming splays of the main structures (splays)
which often have limited strike or dip extent. The vein domain intersects broader zones of intense
veinlet mineralization (termed “porphyry domain” for the purpose of this report) and is hosted by a
lower grade mineralized porphyry. In addition, a discrete, relatively high-grade core, or feeder zone, to
the main mineralization (MDZ), has been identified at depth by CGM geologists.
The lowest levels of the mine (level 21) have currently intersected a combination of the porphyry
domain which is where the gold is associated with veinlets with pyrite, and the MDZ where gold (Au)
is associated with pyrrhotite. There is a small transition between the two domains, which is observed
to some extent in the current mine workings but is not clearly defined from the current drilling.
Underground mining remains focused on the vein structures located in the central portion (Zona Baja)
of the Marmato deposit.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 472
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Stillitoe (2019) concluded the only geological parameter than can be used to constrain the grade model
is veinlet intensity, although the presence of visible native gold also acts as a useful grade indicator.
SRK has used this assumption as the basis for the mineralization model, by using an indicator gold
(1.7 g/t) grade to act as a proxy to higher grades of vein density (which have been logged consistently
in older holes in the area).
SRK has produced block models using Datamine™. The procedure involved import from
Leapfrog™Geo of wireframe models for the fault networks, veins, definition of resource domains (high-
grade sub-domains), data conditioning (compositing and capping) for statistical analysis, geostatistical
analysis, variography, block modelling and grade interpolation followed by validation. Grade estimation
for the veins has been based on block dimensions of 5 m by 10 m by 10 m for the porphyry and MDZ
units. Sub-blocking to 0.5 m by 1 m by 1 m has been allowed to reflect the narrow nature of the
geological model. The block size reflects the relatively close-spaced underground channel sampling
and spacing within veins compared to the wider drilling spacing, with the narrower block size used in
the MDZ at depth to reflect the proposed geometry of the mineralization (steeply dipping feeder zone).
SRK is of the opinion that the MRE has been conducted in a manner consistent with industry best
practices and that the data and information supporting the stated mineral resources is sufficient for
declaration of Measured, Indicated and Inferred classifications of resources. SRK considers currently
the veins (including splays) and the MDZ to be of sufficient confidence for use in the PFS but
recommends further work on the short scale variability within the porphyry be completed to confirm
the current interpretation within areas of the existing mining infrastructure prior to completing a FS.
The exclusive structural control of the MDZ orebody implies that additional examples could exist
elsewhere within the P1 stock and that they represent a priority exploration target, but further
exploration will be required to test this theory and there is no guarantee of exploration success.
25.6 Mining & Reserves
UZ Mine Design
CAF is the current mining method used for the veins and is appropriate for the deposit geometry. A
modified longhole stoping method is envisioned for the Transition zone to take advantage of the bulk
characteristics of the deposit.
Optimizations were run using a minimum cut-off of 2.23 g/t Au for the Veins and 1.91 g/t Au for the
Transition zone.
Access to the Veins is already established. The primary haulage level is 18 and material from levels
above is brought down via existing orepasses. Material below level 18 is transported up an incline or
in the apiques. The main production apique is at level 22, a secondary production apique is at level 20
and will extend down to level 22.
The Transition zone is accessed via level 21 and level 22. A ramp will also connect the two levels as
a secondary egress and ventilation exhaust.
Tonnage and grades presented in the reserve include dilution and recovery. Productivities are based
on the current mine productivities
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 473
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
A quarterly/yearly production schedule was generated using iGantt software. The schedule targeted
1,500 t/d with a gradual ramp up. There is also a 2 Mt/y limit for total moved material, which will limit
the production from the UZ.
MDZ Mine Design
Longhole stoping is an appropriate mining method for the deposit geometry. Stopes are sized to be
large enough to take advantage of bulk mining methods, yet small enough to minimize dilution.
Optimizations were run using various CoG to identify higher grade mining areas and understand the
sensitivity of the deposit to CoG. Results show large quantities of lower grade material where a small
increase/decrease in CoG has a material impact on the material available for design. A minimum cut-
off of 1.61 g/t Au was used for design/reserve. Higher grade stopes using 3.5 g/t stope optimization
results were designed as a first pass, with the lower grade stopes added as separate stopes. This
allowed for scheduling of higher grade stopes first.
The MDZ is accessed through a decline drift with conveyor. Tonnage and grades presented in the
reserve include dilution and recovery and are benchmarked to other similar operations. Productivities
were generated from first principles with inputs from mining contractors, blasting suppliers, and
equipment vendors where appropriate. The productivities were also benchmarked to similar
operations. Equipment used in this study is standard equipment used world-wide with only standard
package/automation features.
A quarterly/yearly production schedule was generated using iGantt software. The schedule targeted
4,000 t/d.
Geotechnical
From the PFS geotechnical investigation, SRK concludes:
• The geotechnical investigation, laboratory tests and design are suitable for a PFS. The
proposed design parameters are acceptable for a PFS study only and should not be fully
implemented before the FS is completed.
• The proposed stope design consists of maximum stope dimensions of 30 m high, 30 m long
and 10 m wide to maintain stability. Empirical charts suggest that the side walls are located in
unsupported transition zones, which could require some spot ground support for potential
wedge formations depending on discontinuity persistence/continuity.
• The empirical chart for estimating the open stope stand-up time was accepted for the PFS.
The results indicate that a 10 m span stope can likely be open for one to six months without
ground support.
• Dilution was estimated using the empirical Clark and Pakalnis (1997) method. The thickness
of external dilution is estimated as ELOS. The ELOS charts indicate significant dilution is
unlikely due to the good rock mass quality. Wall damage would likely be associated with
blasting overbreak. SRK recommends that CGM conduct a blasting study during the FS to
evaluate the degree of overbreak.
To estimate the backfill strength requirements, SRK applied the Mitchell et al, 1982 analytic solution.
The analytic solution results for the case when secondary stopes are open (after mucking), suggests
that:
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 474
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
• A backfill UCS strength of 1 MPa will be adequate to maintain backfill stability and prevent
backfill from sloughing into the open stope.
• Negligible wall sloughing is anticipated.
SRK estimated a sill pillar height equal to 9.5 m, considering an FoS of 1.5 based on the empirical
method proposed by Potvin el al.,1989. A simple 2D numerical simulation indicates that the average
distance between stopes and the crusher station (approximately 40 m) does not affect the stability of
the crusher station. At PFS level, the crusher dimensions are acceptable. However, more detailed
studies should be implemented in the FS.
In terms of the underground workshop infrastructure, the stability assessment was conducted using a
tributary area method. The method assumed that the workshop station is about 750 m deep and
requires a FoS of 1.5, which resulted in a 9 m pillar width and a 7 m pillar height.
Assuming a maximum bay width of 7.5 m, SRK anticipates needing systematic bolting of 2 m long
bolts, 25 mm in diameter and spaced 1.2 m apart. 150 by 150 mm steel welded wire mesh (5 mm
diameter) with 5 cm fiber reinforced shotcrete is also anticipated.
The decline route selection was considered a key part of the PFS during design. High-level geological,
geotechnical, hydrological, hydrogeological and structural factors were taken into consideration to
select the suitable decline route. Special attention was paid to the effect of the modeled major faults
on the drift stability. SRK considered the effect of the major fault location and the RMQ using the
following criteria:
• Reduce the exposure of the decline to major faults
• Decline trajectory should cross perpendicular to major faults
• Avoid faults shear zones
• Avoid crossing highly clayed materials
The full SRK geotechnical report (SRK, 2020) has detailed conclusions regarding the rock mass fabrics
and geotechnical domains
Hydrogeological
The 3D groundwater flow model for the Marmato project was developed, reasonably calibrated to
available measured water level and groundwater flow data, and used to make predictive simulations
of:
• Passive inflow to the existing and planned deep underground mines.
• Propagation of drawdown during proposed dewatering during mining.
• Changes in groundwater discharge to rivers and creeks during mining.
The model predicts that:
• The majority of inflow to the planned mine (up to 78 L/s with a possible range from 56 to
159 L/s) is expected from the upper levels above 730 m, where elevated hydraulic conductivity
values of bedrock groundwater system were measured.
• Mine inflow to the MDZ planned mine below 730 m is predicted to be lower (15 L/s with upper
limit of 34 L/s) due to reduced measured hydraulic conductivity with depth.
• The total maximum planned mine discharge is predicted to be up to 88 L/s, with a possible
range from 61 to 167 L/s.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 475
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
• Total maximum discharge into the entire mine complex, including flow to existing mine levels,
is predicted to be up to 111 L/s, with a possible range from 89 to 168 L/s.
• Major sources of mine inflow are depletion of groundwater storage and capturing of
groundwater discharge to surface water bodies (i.e., streams). The model does not predict
reversing of hydraulic gradient between the mine area and the Cauca River and does not
predict inflow to the mine from the river. However, further investigation of the structures and
their hydrogeological role are needed to verify this conclusion.
• Lowering of the water table in the mine area of up to 140 m and drawdown propagation of up
to 2 km away from the mine, assuming a 10-m drawdown extent
In SRK’s opinion, the completed predictions are conservative, given the following:
• The model is based on extrapolation of the measured hydraulic conductivity values in mine
area for entire model domain, including topographic highs areas outside of the mine area,
where measured water levels are high and hydraulic conductivity values are most likely lower
than in the mine area.
• The model uses of high recharge from precipitation to calibrate the model to measured water
levels, combined with geomean hydraulic conductivity values in discrete depth intervals that
are derived from measured hydraulic conductivity values in the mine area.
• The model uses calibrated conductance values that reproduce measured inflow to the existing,
relatively shallow mine for simulation of groundwater inflow to the deep underground
developments of the planned mine.
• The model simulates no restriction of groundwater inflow to the backfilled stopes for Base
Case and Maximum Inflow scenarios.
The completed analysis of available hydrogeological data and numerical groundwater modeling
indicate that several uncertainties remain in understanding of the hydrogeology, including
hydrogeological role of the faults, hydraulic properties of bedrock outside of the mine area, recharge
estimates, spatial and vertical distribution of groundwater inflow to the current mine, water table
elevation, and water level changes due passive mine dewatering and seasonal changes in
precipitation.
To reduce these uncertainties, SRK recommends CGM complete the following additional
hydrogeological investigations/analyses for the FS:
• Structural analysis of the geological features and faults outside of the mining area, with
emphasis on potential connection to the Cauca River
• Detailed water balance and estimate of recharge from precipitation
• Detailed groundwater inflow mapping in existing developments
• Evaluation of the role of backfilling in reduction of groundwater inflow to the mine
• Improvement of mine discharge measurements at each level of the existing mine
• Re-survey existing monitoring locations, with emphasis on ground and collar elevations
• Installation of groundwater level monitoring network outside of mine area and along the river
valley, including hydrogeological testing during construction of monitoring wells
• Detailed water level measurements to observe:
o Drawdown propagation as a result of mine dewatering
o Seasonal variation as a result of precipitation
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 476
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
• Additional large-scale hydraulic testing to identify zone of enhanced permeability related to
Fault 2 (in areas where planned conveyor decline and egress ramp plan to intersect this fault
at multiple locations/elevations) and Fault 1-3 (intersects planned stopes in multiple
elevations). In addition, test the S. Ines Fault (intersects the planned stopes in the upper levels
and part of the egress ramp)
• Drilling and hydraulic testing of pilot holes in places where ventilation declines are planned
• Updates to the developed numerical groundwater model based on above items to improve its
predictability:
o Better calibration of the model to water levels for future pore pressure predictions
o Re-evaluation of pumping design based on updated inflow predictions
o Evaluation of flow-through hydrogeological conditions during post-mining
• Groundwater chemistry sampling
25.7 Recovery Methods
An ore processing plant has been designed to process MDZ ore at the rate of 4,000 t/d using
conventional processes that are standard to the industry including: primary and secondary crushing,
SAG/ball mill grinding, gravity concentration, agitated cyanide leaching, carbon-in-pulp (CIP), gold
elution, electrowinning and smelting to produce a final doré product.
25.8 Project Infrastructure
The existing infrastructure for the UZ project is established and meets the operational requirements.
The addition of the water supply pumping system from the Cauca River will address potential water
sourcing issues during drought seasons.
The new MDZ infrastructure includes the required access, power supply, water supply, tailings storage,
and support facilities to support the production of 4,000 t/d from the new plant and mine.
A full understanding of the mine water and DSTF water requirements and runoff will allow for
optimization of the site runoff pond and water treatment capacities.
25.8.1 Water Supply
The water balance indicates that adequate water supply is available from the underground dewatering
flows and additional water supply will be available from contact water runoff and seepage flows from
the planned DSTF. Additionally, short term pumping from the UZ is being implemented to support
current mine activities. During development of the MDZ, contact water supply from the planned DSTF
will be erratic and uncertain and should not be considered a steady water supply, and the underground
dewatering flows represent a single source for a reliable water supply, thus a backup supply is
recommended. CGM is currently designing a new Cauca River pumping system to provide separate
water supplies for both the existing UZ and the MDZ. This system will provide a redundant water supply
for both the UZ and MDZ in addition to any water that will be available from existing DSTF or planned
DSTF recovery.
The water balance of the Project indicated that both contact water from the planned DSTF and
underground dewatering flows are likely to exceed the makeup requirements at the processing plant
at certain times in the LoM. Discharges from both water sources are expected and should be
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 477
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
addressed with appropriate discharge structures as part of general infrastructure, including a water
treatment plant expected to be completed in 2021/2022. Additionally, discharges of contact water
should be monitored to ensure environmental compliance is maintained.
25.8.2 Tailings Management Facility
SRK advanced the conceptual designs of DSTF 2 and DSTF 1 to a level sufficient for cost estimating.
The designs include consideration of the following specific elements:
• Subgrade preparation include topsoil salvaging, removal of unsuitable material and excavation
of stability benches and embankment keys
• Construction of rockfill starter embankments using a combination of imported and on-site
borrow
• Construction of underdrain network and underdrain flow management
• Construction of seepage collection drains on dry stack benches and seepage management
systems
• Construction of stormwater diversion and control channels
• Management of contact stormwater on dry stack top deck and return to process
• Access and haul roads between plant and DSTF 2 and DSTF 1
• Temporary storage area for filtered tailings
• Temporary holding pond for non-filtered tailings
• Topsoil and unsuitable soil stockpile area with underdrainage system
Currently identified risks and opportunities with respect to the costs developed for the PFS have been
identified in relation to the following:
• The inability to characterize the foundation conditions beneath the conceptual DSTF
footprints.
• Ongoing geochemical characterization of both waste rock and ore/tailings indicating some of
the waste rock and tailings may be acid generating and therefore require special management
considerations.
• Immediate characterization and analysis of Cascabels 1 and 2 to demonstrate compliance
with internationally accepted standards of practice and provide for tailings management
through commissioning of a new DSTF.
• More extensive testing of tailings to confirm tailings geotechnical characteristics and cement
addition requirements.
25.9 Environmental Studies and Permitting
The following interpretations and conclusions have been drawn with respect to the currently available
information provided for the Marmato Project:
• Environmental Studies: Baseline studies have been completed or are currently underway
with respect to the existing facilities (additional tailings storage capacity request) and MDZ
proposed expansion. These resource studies will be used for impact analysis and the
development of mitigation actions and environmental management planning.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 478
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
• Environmental and Social Management: Environmental and social issues are currently
managed in accordance with the approved PMA and will likely need to be updated and/or
modified for the proposed MDZ expansion project.
• Monitoring: Routine monitoring is currently conducted on seven domestic wastewater
discharges and three non-domestic (industrial) wastewater discharges. Air quality emissions
from the metallurgical laboratory and smelter are also monitored for: particulate matter (PM),
sulphur dioxide (SO2) nitrogen oxides (NOx) and lead (Pb). The tailings are infrequently
monitored for hazard classification purposes through a Corrosive, Reactive, Explosive, Toxic,
Inflammable, Pathogen [biological] (CRETIP) program. The results of the monitoring are
provided to Corpocaldas. This monitoring program will require significant modification to
include the facilities for the proposed MDZ expansion project, and to bring it up to international
best practice standards.
• Geochemistry: Acid-generating sulfide minerals identified in the deposit include pyrite,
arsenopyrite, iron-bearing sphalerite, pyrrhotite, and chalcopyrite (SRK, 2017). Samples of
groundwater discharging into the underground are predominantly acidic. The underground
water samples contain elevated metal(loid) concentrations. While the tailings will be
discharged with a neutral to alkaline supernatant, the tailings themselves will be PAG with the
potential to eventually overwhelm the alkaline supernatant and produce acid drainage in the
long term. SRK’s waste rock characterization program is in progress and will be reported in a
separate report. A waste rock analytical program completed in 2012 in support of an open pit
mine design indicated that a significant fraction of waste rock could be potentially acid
generating (KP, 2012).
• Permitting: Operations are permitted through the posting of an Environmental Management
Plan (PMA) and secondary permits for use of water abstraction, forest use, air emissions,
discharges and river course (channel) construction. The PMA for the current operations was
originally approved in 2001. Minor modification of the PMA (including and environmental
impact analysis) is currently underway as part of the request for additional tailings storage
areas. Major modification of the PMA will be required for the MDZ expansion project.
• Stakeholder Engagement: CGM has conducted extensive stakeholder identification and
analysis programs and has set stakeholder engagement objectives and goals to develop
communications plans with government, community, media and small miners but the
Company does not currently have a formal stakeholder engagement plan.
• Closure Costs: The reclamation and closure cost estimate provided for the current operations
is approximately US$6.1 million, though there is considerable uncertainty surrounding the
basis for this estimate. An additional US$3.0 million is estimated for the MDZ expansion
facilities (assuming concurrent tailings reclamation), for a total of US$9.1 million. A
requirement for long-term post-closure water treatment, if any, could significantly increase this
estimate.
There do not appear to be any other known environmental issues that could materially impact CGM’s
ability to conduct mining and milling activities at the site. Preliminary mitigation strategies have been
developed to reduce environmental impacts to meet regulatory requirements and the conditions of the
PMA.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 479
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
25.10 Capital and Operating Costs
Marmato UZ is a currently operating underground mine, and the estimate of capital includes some
expansion capex to increase the mineral processing capacity and sustaining capital to maintain the
equipment and all supporting infrastructure necessary to continue operations until the end of the
projected production schedule. The estimate prepared for this study indicates that the Project requires
sustaining capital of US$59.5 million to support the projected production schedule throughout the LoM.
The MDZ is a lower part of the deposit that is undeveloped. Before CGM can exploit this part of the
deposit it will have to expand the existing operation. The expansion is planned to be executed between
2021 and 2023. The cost estimate indicates that the expansion will require an investment of US$269.4
million, this includes an estimated capital of US$237.2 million plus 13.6% contingency of US$32.2
million.
Ausenco prepared a detailed cost estimate for MDZ mineral processing facility and other mine
infrastructure but did not prepare an expenditure estimate for this capital.
SRK, Ausenco and CGM prepared the estimate of operating costs for the PFS’s production schedule.
The estimated operating cost for Marmato UZ is US$76.12/t-ore and for MDZ is US$57.10/t-ore
The estimated AISC, including sustaining capital, is US$880/Au-oz. Table 22-13 presents the
breakdown of the Marmato AISC.
Table 25-1: LoM All-in Sustaining Cost Breakdown
LoM All-in Sustaining Cost Breakdown
Mining USD/Au-oz 408
Processing USD/Au-oz 145
G&A USD/Au-oz 102
Refining USD/Au-oz 6
Royalty USD/Au-oz 130
Sustaining Capital USD/Au-oz 102
Silver Credit USD/Au-oz (14)
AISC USD/Au-oz 880
SRK’s standard Cash Cost reporting methodology for NI 43-101 reports includes smelting/refining costs; whereas CGM’s basis of reporting treats these costs as a reduction of realized gold price (the refinery discounts the selling price by a factor to cover these charges) and excludes them from its reported “total cash cost per ounce”. Source: SRK, 2020
25.11 Economic Analysis
The valuation results of the Marmato Project indicate that is has an after-tax IRR of 19.5% and an
after-tax NPV of approximately US$256.1 million, based on a 5% discount rate and gold and silver
prices of US$1,400/oz and US$17.00/oz respectively. The cash flow profile also shows a shorter
payback when comparing to a stand-alone MDZ operation to the combined operations, which present
a payback within the year of 2026, while a stand-alone MDZ operations would present a payback in
the year of 2027. The operation is projected to have negative cash flows between 2020 and 2023,
when the MDZ is installed, with payback for the expansion expected by 2026. LoM is projected to end
in 2033 resulting in a total production of 1.87 Moz of gold and 1.57 Moz of silver in the form of doré
bars containing both precious metals. Indicative economic results are presented in Table 25-2.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 480
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 25-2: Marmato Indicative Economic Results
LoM Cash Flow (Unfinanced)
Total Revenue USD 2,625,861,238
Mining Cost USD (761,539,531)
Processing Cost USD (270,396,073)
G&A Cost USD (190,857,579)
Total Opex USD (1,222,793,183)
Operating Margin USD 1,403,068,055
Operating Margin Ratio % 53%
Taxes Paid USD (210,374,619)
Free Cashflow (before initial capital) USD 760,268,116
Before Tax
Free Cash Flow USD 701,248,730
NPV @ 5% USD 396,654,830
NPV @ 8% USD 279,571,263
NPV @ 10% USD 219,652,793
IRR % 26%
After Tax
Free Cash Flow USD 490,874,111
NPV @ 5% USD 256,075,253
NPV @ 8% USD 167,009,205
NPV @ 10% USD 121,855,455
IRR % 19.5%
Payback Year 2026
Source: SRK, 2020
The Project is a gold operation with a sub-product of silver, where gold represents 99% of the total
projected revenue and silver the remaining 1%. The underground mining cost is the heaviest burden
on the operation representing 62% of the operating cost, while processing costs represent 22% and
G&A costs the remaining 16%.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 481
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
26 Recommendations
26.1 Recommended Work Programs
26.1.1 Property Description and Ownership
CGM has two key aspects of the property ownership that are currently in progress. CGM has submitted
the relevant documentation to the Colombian Government to extend the current 30-year term on the
#014-089m (Zona Baja) license.
Follow-up on the gap highlighted between the licenses needs clarification prior to mining. It is SRK’s
understanding that initial feedback from the Government has been received at the time of writing but
has not been accounted for in the PFS. Clarification on the criteria will likely result in upside of
additional material being available for future mine planning, within the existing infrastructure.
26.1.2 Geology and Mineral Resources
Additional ongoing recommendations for the Mineral Resource studies on this project, to be done prior
to the FS, should include:
• A detailed review of the geological model with CGM geologists to ensure geological continuity
is suitably modelled. This should include incorporation of a number of additional faults which
have been identified by CGM as having potential impact and controls on the system. These
faults also should be considered prior to the final underground decline design as it may have
geotechnical implications
• It is recommended that CGM develop a system to flag channel samples in the database taken
from the working stopes (vein channels), compared to more detailed exploration channel
samples taken from cross-cuts and exploration development where possible. Any updates in
the database will need to be completed prior to the FS update, and SRK will work with the
geological team to ensure the best solution can be found in the time available. The aim will
be to identify areas for potential mining targets to provide additional feed to the current
operation and plant
• Continual monitoring of the MDZ drilling program with regular updates on the Leapfrog Model
• Richard H. Sillitoe concluded that the 500 m long, west-northwest-striking MDZ orebody is
entirely controlled by a veinlet array developed during dextral transpression raises the
possibility that one or more look-alike deposits could be present elsewhere within the 6 km by
5 km P1 stock. They could be exposed at lower elevations than Marmato (such as less than
900 masl) as a result of greater degrees of erosion or, as in the case of the MDZ itself, remain
concealed beneath and partly overprinted by a swarm of ‘epithermal’ massive base-metal
sulfide veins. Either possibility would represent an attractive exploration opportunity, which it
is considered worth pursuing. SRK considers this an important consideration for future
exploration upon completion of the current drilling program.
SRK is currently working with CGM’s geologists to optimize the remainder of the 2020 drilling program.
The 2020 drilling program will have three main areas of focus (Figure 26-1) which includes:
• Phase A: Drilling the hangingwall of the MDZ to test for extensions to the northern limb of the
MDZ, which potentially hosts mineralization within the areas of the current mine design
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 482
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
presented in this technical report. This should be considered high priority as it may require
changes to the underground infrastructure locations moving them further to the north.
• Phase B: Increasing the confidence in the MDZ at depth to potentially add additional years to
the life of mine. The aim is to infill the drilling spacing to a 50 by 50 m grid in the upper portions
of the MDZ, and potentially increase the Inferred Resources at the end. CGM has planned to
make use of directional drilling from a series of mother-holes to complete the deep drilling
while access to favourable intersection angles from the current underground locations is
limited.
• Phase C: Exploration into the hangingwall to test for similar structures located below other
major features.
Source: SRK, 2020
Figure 26-1: 2020 Exploration Plan Showing Phases A through C (Left to Right)
26.1.3 Mineral Processing and Metallurgical Testing
Confirmatory metallurgical testwork should be conducted on material from new ore zones as they are
identified.
Additional testwork should be conducted to further assess cyanide destruction process parameters
required to reduce weak acid dissociable cyanide (CNWAD) in the leach residue to <1 ppm CNWAD.
26.1.4 Mining & Reserves
UZ Mine
It is recommended that CGM work to improve grade control practices and minimize dilution in the UZ
mine. SRK further recommends that CGM transition to using 3D mine design for better planning and
scheduling. (US$270,000)
For the Transition zone, additional geotechnical work is needed to recover the 7 m pillar between Level
21 and Level 22. (US$75,000)
??
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 483
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
MDZ
Continue to monitor costs and CoG. Small changes in CoG can have a material impact to the mine
design. Similarly continue to look at optimizing the sequence to mine higher grade material earlier in
the mine life in the next level of study. Develop the mine design to FS level design. (US$350,000
includes the mine design through faults)
The design crosses through several known faults, however, little is understood about these faults in
the location of the development. Additional drilling/testwork is necessary to understand this prior to
development. (Included in geotechnical estimate)
In the following paragraphs, recommended actions to be completed for the FS are provided. SRK
notes that some of the recommended activities have started.
Update the hydrogeologic information available and revisit the pumping system design to optimize the
system to the updated hydro information. Refine the pump sizing and consider an updated risk profile
to match the pump system sizing to actual expected inflows. This evaluation could lead to a reduced
pump size and lower power requirements including sizing of substation and electrical infrastructure.
(US$30,000 for FS Pump Design Optimization)
Evaluate the ventilation standard applied with respect to diesel dilution to consider whether a variance
to NA standards would allow a more optimized ventilation fan sizing that would potentially reduce
ventilation capital cost, operating cost, power system distribution size and infrastructure dimension.
(US$50,000 for ventilation standard evaluation)
Geotechnical
• Complete a major fault model update.
• Specific geotechnical drill holes to characterize the rock mass parameters around the critical
underground infrastructure should be drilled.
• Geotechnical core logging and televiewer data in specific exploration drill holes should be
collected and analyzed.
• Complete specific geotechnical drill holes to characterize the rock mass parameters around
the conveyor tunnel.
• Conduct pre-mining situ stress measurements.
• Collect tiltmeter measurements to confirm that there is minimal subsidence above the
transition zone.
• Perform mine scale stress analyses of the planned stoping sequence.
• A mine scale hydrogeological pore pressure model should be developed that considers
locations and hydraulic conductivity of specific fault structures as they intersect drifts and
stopes.
• Long term access to critical infrastructures should be evaluated, such as the crusher station
and workshops. Specific geotechnical drill holes and numerical simulations need to be
considered for the FS.
• 3D numerical modeling to determine the mining sequence effect on the mine stability
SRK estimates that the full FS geotechnical program will cost about US$400,000, which includes
laboratory testing, stress measurements, numerical simulations and geological engineering works.
The total cost does not include drilling activities.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 484
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Hydrogeology
To reduce these uncertainties, SRK recommends CGM complete the following additional
hydrogeological investigations/analyses for the FS:
• Structural analysis of the geological features and faults outside of the mining area, with
emphasis on potential connection to the Cauca River
• Detailed water balance and estimate of recharge from precipitation
• Detailed groundwater inflow mapping in existing developments
• Evaluation of the role of backfilling in reduction of groundwater inflow to the mine
• Improvement of mine discharge measurements at each level of the existing mine
• Re-survey existing monitoring locations, with emphasis on ground and collar elevations
• Installation of groundwater level monitoring network outside of mine area and along the river
valley, including hydrogeological testing during construction of monitoring wells
• Detailed water level measurements to observe:
o Drawdown propagation as result of mine dewatering
o Seasonal variation as result of precipitation
• Additional large-scale hydraulic testing to identify zone of enhanced permeability related to
Fault 2 (in areas where planned conveyor decline and egress ramp plan to intersect this fault
at multiple locations/elevations) and Fault 1-3 (intersects planned stopes in multiple
elevations). In addition, test the S. Ines Fault (intersects the planned stopes in the upper levels
and part of the egress ramp)
• Drilling and hydraulic testing of pilot holes in places where ventilation declines are planned
• Updates to the developed numerical groundwater model based on above items to improve its
predictability:
o Better calibration of the model to water levels for future pore pressure predictions
o Re-evaluation of pumping design based on updated inflow predictions
o Evaluation of flow-through hydrogeological conditions during post-mining
• Groundwater chemistry sampling
26.1.5 Recovery Methods
During the next phase of study additional process design work should be conducted in order to achieve
a definitive capital cost estimate with an accuracy of +/-15%.
26.1.6 Project Infrastructure
UZ Project
The UZ project electrical system should be further reviewed during the next phase of study to confirm
the impacts of adding the MDZ fan loads to the system and optimize backup generation. Evaluate the
interconnection of the UZ electrical system to the MDZ system to establish a loop for reliability
purposes. (US$25,000)
Refine and further develop the water supply system to detailed engineering level and confirm in more
detail the costs. (US$50,000)
Develop a full understanding of the mine water and DSTF water requirements and runoff will allow for
optimization of the site runoff pond and water treatment capacities
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 485
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
MDZ Project
Due to lack of site-specific geotechnical investigations at the process plant site, several assumptions
have been made on ground bearing capacity, ground stability, depth of bed rock, suitability and
availability of general fill and granular material, borrow source for granular material. These
assumptions should be verified in the next phase of the project. (Work in progress by CGM)
Further develop the water supply system to feasibility level and review the overall site water balance
to confirm sizing requirements. (US$25,000)
Carry out an overall review of all the electrical loads in the mine and mill areas once additional precision
is available with all equipment loads to assess if main transformers can be reduced. (US$50,000)
Update the paste backfill plant design and costing to feasibility level. (US$350,000)
Tailings Management Facilities
For the next phase of study, SRK makes the following recommendations related to DSTF design and
costing:
• Detailed geotechnical site investigations should be completed at each proposed DSTF site
and stockpile locations, a thorough program of foundation, tailings and cement amendment
geotechnical testing should be completed and the conceptual designs, stability analyses and
costs updated to reflect the results. The geotechnical investigation should also include a
trenching study within DTSF-2’s footprint to assess the activity of known faults in the area.
(US$700,000)
• Geochemical characterization of waste rock and ore/tailings should be completed and the
conceptual DSTF designs and associated borrow source, operating, and closure requirements
should be updated accordingly, including the potential additional requirement of water
treatment prior to discharge. (US$100,000)
• The detailed characterization of Cascabel 1 and 2 recommended by Dynami in 2020 should
be expedited and the results incorporated into a stability analysis prepared in accordance with
internationally accepted standards of practice. If the facility cannot be shown to be sufficiently
stable, or if mitigating measures or design revisions cannot be identified to bring the facility up
to those standards, CGM should identify an alternative option for tailings storage until a new
DSTF can be constructed and operational. (US$2.6 million)
• A more thorough evaluation of DSTF 6 acquisition, permitting, development, operating and
closure requirements should be completed based on more favorable topography and
stormwater management requirements than either DSTF-1 or DSTF-2. (US$150,000)
26.1.7 Environmental Studies and Permitting
The following recommendations are made with respect to environmental, permitting and social issues
regarding the Marmato Project:
• Prepare a more detailed site-wide closure plan for the existing Marmato facilities, including
building plans and equipment inventories) from which a more accurate final closure cost
estimate can be developed.
• Continue work on groundwater hydrogeology and surface water to better define the risk
associated with potential groundwater contamination and underground dewatering impacts. A
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 486
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
detailed evaluation, including a groundwater model, could provide information that would
assist in forecasts of post-closure mine water discharge and possible long-term water
treatment requirements. Such an investigation could also provide vital information on
underground geotechnical stability, both during operations and post closure.
• Characterization work should be completed on artisanal tailings and waste rock to understand
their ARDML potential and devise a long-term management plan.
• A comprehensive baseline surface and groundwater sampling program will be important to
establish the baseline condition and try to quantify the contributions from artisanal or pre-
mining conditions, especially with respect to mercury from artisanal mining.
Substantial financial resources and technical specialist support will be required to implement the
environmental monitoring and mitigation measures likely to be presented in the updated PMA for the
expansion project.
26.1.8 Capital, Operating Costs and Economic Analysis
The following recommendations are made with respect to capital and operating cost and economic
evaluation of the Marmato Project:
• Prepare first principles estimate of capital and operating costs with enough accuracy to
support a future FS study of the project, including:
o Prepare cash flow model based on shorter periods of production.
o Prepare an expenditure curve for MDZ mineral processing and site infrastructure
construction costs.
o Further detail site-specific operating cost data and cost models to include fixed and
variable nature of costs and detail cost models to include breakdown by area and function.
o Improve cost models to include currencies used to estimate each cost and prepare
sensitivity to currencies variability.
• The schedule prepared for Marmato UZ doesn’t fully utilize its mineral processing capacity for
several years of the LoM. Investigate the possibility to expand the total mine movement permit
to allow Marmato UZ to process its run of mine using its plant full capacity, as this will very
likely improve the overall project economics.
26.2 Recommended Work Program Costs
Table 26-1 summarizes the costs for recommended work programs.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 487
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Table 26-1: Summary of Costs for Recommended Work
Discipline Program Description Cost (US$) No Further Work is Recommended Reason:
Property Description and Ownership N/A
Geology and Mineralization Captured in next line item.
Status of Exploration, Development and Operations Complete Infill Drilling $6,500,000
Mineral Processing and Metallurgical Testing Conduct confirmatory testing on material from new ore zones as they are developed
$200,000
Mineral Resource Estimate
Mineral Reserve Estimate
Mining Methods As Detailed in Section 26 $775,000
Recovery Methods FS engineering during next phase of study to bring process plant capex to a +/-15% level of accuracy
$750,000
Project Infrastructure As Detailed in Section 26 $4,550,000
Geotechnical As described in Section 26.1.4 $400,000
Exploration team will continue conducting geotechnical core logging as part of its in fill drilling programs, This information will be useful for further rock mechanics model update
Hydrogeology As Detailed in Section 26 Drilling and equipment included.
1,600,000
Environmental Studies and Permitting
Site Wide Detailed Closure Plan $50,000
Forecast Post-Closure Mine Water Discharges
$75,000
Characterize Artisanal Mine Wastes $100,000
Capital and Operating Costs Updated analysis resulting from new information
US$200,000
Economic Analysis Updated analysis resulting from new information
US$25,000
Total US$ $15,225,000
Source: SRK, 2020
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 488
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
27 References Barton, N. (1974). A review of the Shear Strength of Filled Discontinuities in Rock. Norwegian
Geotechnical Institute publication no. 105.
CIM (2014). Canadian Institute of Mining, Metallurgy and Petroleum Standards on Mineral Resources
and Reserves: Definitions and Guidelines, May 10, 2014.
Clark and Pakalnis (1997). An empirical design approach for estimating unplanned dilution from open
stope hangingwalls and footwalls. 99th CIM Annual General Meeting, Vancouver, British
Columbia.
Dynami (Dynami, 2020a). TSF 1 and TSF 2 Hydrologic and Hydraulic conceptual analyses
Memorandum, July 24 2020, Colombia.
Dynami (Dynami, 2020b). TSF 1 and TSF 2 Slope Stability Analyses Memorandum, August 10 2020,
Colombia.
Dynami (Dynami, 2020c). Analisis De Estabilidad Relaveras Cascabel 1 & 2, Caldas Gold Marmato,
Proyecto Marmato, May 2020, Colombia.
Telluris Consulting Ltd. (2010). Structural study of the Marmato District, Colombia. Unpublished report
for Medoro Resources/Minerales Andinos del Occidente S.A., 22p.
Gran Colombia Gold (Caldas). Lead Isotopic Compositions of the Gold Mineralization of Marmato,
Colombia: Characterization of the Transition Domain in Epithermal – Porphyry Systems.
Grimstad, E & Barton, N (1993), ‘Updating the Q-system for NMT’, in C Kompen, SL Opsahl & SL Berg
(eds), Proceedings of the International Symposium on Sprayed Concrete, Norwegian
Concrete Association, 21 p.
IDEAM, (2013). Aguas Subterraneas en Colombia: Una Vision General, Instituto de Hidrología,
Meteorología y Estudios Ambientales de Colombia, Bogota D.C., 2013.
Knight Piésold Consulting, (2012a). Marmato Mine, Pre-Feasibility Study Hydrogeology Report, April
12, 2012.Hatch, 2012.
Mitchel et. al (1982) Stability Analysis of Paste Fill as Stope Wall using Analytical Method and
Numerical Modeling in The Kencana Underground Gold Mining with Long Hole Stope Method.
Pinzón, F. D. & Tassinari, C. C. G., (2003), Ages and Sources of the Gold Mineralizations from
Marmato Mining District, NW Colombia: Based on Radiogenic Isotope Evidences. IV South
American Symposium on Isotope Geology. IRD (Institut de recherche pour le development).
Salvador, Bahia, Brazil, 24–27 August 2003, p. 758 to 761.
Potvin and Milne (1992). A Critical Review of the Stability Graph Method for Open Stope Design.
Proceedings MassMin 2012, Sudbury, Ontario, Canada.
Rocscience (2016). DIPS v 7.0. – program for the projection of joint and discontinuity data on a
sterographic projection. Version 7.0, Rocscience Inc., Toronto.
Rocscience (2019). UnWedge, 2019. – program for underground excavation stability assessment
Rocscience Inc., Toronto.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 489
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Rossetti, P. & Colombo, F. (1999). Adularia-sericite gold deposits of Marmato (Caldas, Colombia):
field and petrographical data. Geological Society, London, Special Publications 155, 167-182.
Sillitoe, R. H., Jaramillo, L., Damon, P. E., Shafiqullah, M. & Escovar, R., (1982), Setting,
Characteristics, and Age of the Andean Porphyry Copper Belt in Colombia. Economic
Geology, 77, p. 1837 to 1850.
SRK (2020). Pre-Feasibility Geotechnical Study Marmato Deep Zone, Colombia.
SRK (SRK, 2020a). Marmato DSTF Siting Study Memorandum, May 21 2020, Reno Nevada.
Vinasco, C. J., (2001). A utilização da metodologia 40Ar-39Ar para o estudo de reativações tectônicas
em zonas de cisalhamento. Paradigma: O Falhamento de Romeral nos Andes Centrais da
Colômbia. Masters dissertation. Institute of Geosciences. University of Sao Paulo.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 490
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
28 Glossary The Mineral Resources and Mineral Reserves have been classified according to CIM (CIM, 2014).
Accordingly, the Resources have been classified as Measured, Indicated or Inferred, the Reserves
have been classified as Proven and Probable based on the Measured and Indicated Resources as
defined below.
28.1 Mineral Resources
A Mineral Resource is a concentration or occurrence of solid material of economic interest in or on
the Earth’s crust in such form, grade or quality and quantity that there are reasonable prospects for
eventual economic extraction. The location, quantity, grade or quality, continuity and other geological
characteristics of a Mineral Resource are known, estimated or interpreted from specific geological
evidence and knowledge, including sampling.
An Inferred Mineral Resource is that part of a Mineral Resource for which quantity and grade or
quality are estimated on the basis of limited geological evidence and sampling. Geological evidence
is sufficient to imply but not verify geological and grade or quality continuity. An Inferred Mineral
Resource has a lower level of confidence than that applying to an Indicated Mineral Resource and
must not be converted to a Mineral Reserve. It is reasonably expected that the majority of Inferred
Mineral Resources could be upgraded to Indicated Mineral Resources with continued exploration.
An Indicated Mineral Resource is that part of a Mineral Resource for which quantity, grade or quality,
densities, shape and physical characteristics are estimated with sufficient confidence to allow the
application of Modifying Factors in sufficient detail to support mine planning and evaluation of the
economic viability of the deposit. Geological evidence is derived from adequately detailed and reliable
exploration, sampling and testing and is sufficient to assume geological and grade or quality continuity
between points of observation. An Indicated Mineral Resource has a lower level of confidence than
that applying to a Measured Mineral Resource and may only be converted to a Probable Mineral
Reserve.
A Measured Mineral Resource is that part of a Mineral Resource for which quantity, grade or quality,
densities, shape, and physical characteristics are estimated with confidence sufficient to allow the
application of Modifying Factors to support detailed mine planning and final evaluation of the economic
viability of the deposit. Geological evidence is derived from detailed and reliable exploration, sampling
and testing and is sufficient to confirm geological and grade or quality continuity between points of
observation. A Measured Mineral Resource has a higher level of confidence than that applying to
either an Indicated Mineral Resource or an Inferred Mineral Resource. It may be converted to a Proven
Mineral Reserve or to a Probable Mineral Reserve.
28.2 Mineral Reserves
A Mineral Reserve is the economically mineable part of a Measured and/or Indicated Mineral
Resource. It includes diluting materials and allowances for losses, which may occur when the material
is mined or extracted and is defined by studies at Pre-Feasibility or Feasibility level as appropriate that
include application of Modifying Factors. Such studies demonstrate that, at the time of reporting,
extraction could reasonably be justified.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 491
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
The reference point at which Mineral Reserves are defined, usually the point where the ore is delivered
to the processing plant, must be stated. It is important that, in all situations where the reference point
is different, such as for a saleable product, a clarifying statement is included to ensure that the reader
is fully informed as to what is being reported. The public disclosure of a Mineral Reserve must be
demonstrated by a Pre-Feasibility Study or Feasibility Study.
A Probable Mineral Reserve is the economically mineable part of an Indicated, and in some
circumstances, a Measured Mineral Resource. The confidence in the Modifying Factors applying to a
Probable Mineral Reserve is lower than that applying to a Proven Mineral Reserve.
A Proven Mineral Reserve is the economically mineable part of a Measured Mineral Resource. A
Proven Mineral Reserve implies a high degree of confidence in the Modifying Factors.
28.3 Definition of Terms
The following general mining terms may be used in this report.
Table 28-1: Definition of Terms
Term Definition
Assay The chemical analysis of mineral samples to determine the metal content.
Capital Expenditure All other expenditures not classified as operating costs.
Composite Combining more than one sample result to give an average result over a larger distance.
Concentrate A metal-rich product resulting from a mineral enrichment process such as gravity concentration or flotation, in which most of the desired mineral has been separated from the waste material in the ore.
Crushing Initial process of reducing ore particle size to render it more amenable for further processing.
Cut-off Grade (CoG) The grade of mineralized rock, which determines as to whether or not it is economic to recover its gold content by further concentration.
Dilution Waste, which is unavoidably mined with ore.
Dip Angle of inclination of a geological feature/rock from the horizontal.
Fault The surface of a fracture along which movement has occurred.
Footwall The underlying side of an orebody or stope.
Gangue Non-valuable components of the ore.
Grade The measure of concentration of gold within mineralized rock.
Hangingwall The overlying side of an orebody or slope.
Haulage A horizontal underground excavation which is used to transport mined ore.
Hydrocyclone A process whereby material is graded according to size by exploiting centrifugal forces of particulate materials.
Igneous Primary crystalline rock formed by the solidification of magma.
Kriging An interpolation method of assigning values from samples to blocks that minimizes the estimation error.
Level Horizontal tunnel the primary purpose is the transportation of personnel and materials.
Lithological Geological description pertaining to different rock types.
LoM Plans Life-of-Mine plans.
LRP Long Range Plan.
Material Properties Mine properties.
Milling A general term used to describe the process in which the ore is crushed and ground and subjected to physical or chemical treatment to extract the valuable metals to a concentrate or finished product.
Mineral/Mining Lease A lease area for which mineral rights are held.
CGM Mining Assets The Material Properties and Significant Exploration Properties.
Ongoing Capital Capital estimates of a routine nature, which is necessary for sustaining operations.
Ore Reserve See Mineral Reserve.
Pillar Rock left behind to help support the excavations in an underground mine.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 492
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Term Definition
RoM Run-of-Mine.
Sedimentary Pertaining to rocks formed by the accumulation of sediments, formed by the erosion of other rocks.
Shaft An opening cut downwards from the surface for transporting personnel, equipment, supplies, ore and waste.
Sill A thin, tabular, horizontal to sub-horizontal body of igneous rock formed by the injection of magma into planar zones of weakness.
Smelting A high temperature pyrometallurgical operation conducted in a furnace, in which the valuable metal is collected to a molten matte or doré phase and separated from the gangue components that accumulate in a less dense molten slag phase.
Stope Underground void created by mining.
Stratigraphy The study of stratified rocks in terms of time and space.
Strike Direction of line formed by the intersection of strata surfaces with the horizontal plane, always perpendicular to the dip direction.
Sulfide A sulfur bearing mineral.
Tailings Finely ground waste rock from which valuable minerals or metals have been extracted.
Thickening The process of concentrating solid particles in suspension.
Total Expenditure All expenditures including those of an operating and capital nature.
Variogram A statistical representation of the characteristics (usually grade).
28.4 Abbreviations
The following abbreviations may be used in this report.
Table 28-2: Abbreviations
Abbreviation Unit or Term
A Ampere
AA atomic absorption
A/m2 amperes per square meter
ANFO ammonium nitrate fuel oil
Ag Silver
Au Gold
AuEq gold equivalent grade
°C degrees Centigrade
CCD counter-current decantation
CIL carbon-in-leach
CoG cut-off grade
Cm centimeter
cm2 square centimeter
cm3 cubic centimeter
Cfm cubic feet per minute
ConfC confidence code
CRec core recovery
CSS closed-side setting
CTW calculated true width
° degree (degrees)
dia. diameter
EIS Environmental Impact Statement
EMP Environmental Management Plan
FA fire assay
Ft foot (feet)
ft2 square foot (feet)
ft3 cubic foot (feet)
g Gram
Gal Gallon
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 493
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Abbreviation Unit or Term
g/L gram per liter
g-mol gram-mole
Gpm gallons per minute
g/t grams per tonne
Ha hectares
HDPE Height Density Polyethylene
hp horsepower
HTW horizontal true width
ICP induced couple plasma
ID2 inverse-distance squared
ID3 inverse-distance cubed
IFC International Finance Corporation
ILS Intermediate Leach Solution
kA kiloamperes
kg kilograms
km kilometer
km2 square kilometer
koz thousand troy ounce
kt thousand tonnes
kt/d thousand tonnes per day
kt/y thousand tonnes per year
kV Kilovolt
kW Kilowatt
kWh kilowatt-hour
kWh/t kilowatt-hour per metric tonne
Liter
L/sec liters per second
L/sec/m liters per second per meter
Lb Pound
LHD Long-Haul Dump truck
LLDDP Linear Low Density Polyethylene Plastic
LOI Loss On Ignition
LoM Life-of-Mine
m Meter
m2 square meter
m3 cubic meter
masl meters above sea level
mg/L milligrams/liter
mm millimeter
mm2 square millimeter
mm3 cubic millimeter
MME Mine & Mill Engineering
Moz million troy ounces
Mt million tonnes
MTW measured true width
MW million watts
m.y. million years
NGO non-governmental organization
NI 43-101 Canadian National Instrument 43-101
OSC Ontario Securities Commission
oz troy ounce
% Percent
PLC Programmable Logic Controller
PLS Pregnant Leach Solution
PMF probable maximum flood
ppb parts per billion
ppm parts per million
QA/QC Quality Assurance/Quality Control
RC rotary circulation drilling
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Project Page 494
MMS/KD Marmato_PFS_NI43-101_557200-030_Rev09.docx August 2020
Abbreviation Unit or Term
RoM Run-of-Mine
RQD Rock Quality Description
SEC U.S. Securities & Exchange Commission
sec Second
SG specific gravity
SPT standard penetration testing
st short ton (2,000 pounds)
t tonne (metric ton) (2,204.6 pounds)
t/h tonnes per hour
t/d tonnes per day
t/y tonnes per year
TSF tailings storage facility
TSP total suspended particulates
µm micron or microns
V Volts
VFD variable frequency drive
W Watt
XRD x-ray diffraction
y Year
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Appendices
MMS/KD August 2020
Appendices
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Appendices
MMS/KD August 2020
Appendix A: Certificates of Qualified Persons
SRK Consulting (U.S.), Inc.
Suite 600
1125 Seventeenth Street
Denver, CO 80202
T: 303.985.1333
F: 303.985.9947
www.srk.com
U.S. Offices:
Anchorage 907.677.3520
Clovis 559.452.0182
Denver 303.985.1333
Elko 775.753.4151
Reno 775.828.6800
Tucson 520.544.3688
Canadian Offices:
Saskatoon 306.955.4778
Sudbury 705.682.3270
Toronto 416.601.1445
Vancouver 604.681.4196
Yellowknife 867.873.8670
Group Offices:
Africa
Asia
Australia
Europe
North America
South America
CERTIFICATE OF QUALIFIED PERSON
I, David Bird, MSc., PG, RM-SME, do hereby certify that:
1. I am an Associate Principal Consultant (Geochemistry) of SRK Consulting (U.S.), Inc., 1125 Seventeenth Street, Suite 600, Denver, CO, USA, 80202.
2. This certificate applies to the technical report titled “Revised NI 43-101 Technical Report Pre-Feasibility Study Marmato Project Colombia” with an Effective Date of March 17, 2020 (the “Technical Report”).
3. I graduated with Bachelor’s Degrees in Geology and Business Administration Management from Oregon State University in 1983. In addition, I obtained a Master’s Degree in Geochemistry/Hydrogeology from the University of Nevada-Reno in 1993. I am a Registered Member of the Society for Mining, Metallurgy, and Exploration (SME). I am a certified Professional Geologist in the State of Oregon (G1438). I have worked full time as a Geologist and Geochemist for a total of 32 years. My relevant experience includes design, execution, and interpretation of mine waste geochemical characterization programs in support of open pit and underground mine planning and environmental impact assessments, design and supervision of water quality sampling and monitoring programs, geochemical modeling, and management of the geochemistry portion of numerous PEA, PFS and FS-level mine projects in the US and abroad.
4. I have read the definition of “qualified person” set out in National Instrument 43-101 (NI 43-101) and certify that by reason of my education, affiliation with a professional association (as defined in NI 43-101) and past relevant work experience, I fulfill the requirements to be a “qualified person” for the purposes of NI 43-101.
5. I have not visited the Marmato property.
6. I am responsible for Geochemistry Section 20.1.3, and portions of Sections 1.10.1, 25 and 26.
7. I am independent of the issuer applying all of the tests in section 1.5 of NI 43-101.
8. I have had prior involvement with the property that is the subject of the Technical Report. The nature of my prior involvement is acting as QP on Bluenose Gold Corporation’s Marmato Project report titled “NI 43-101 Technical Report Preliminary Economic Assessment Marmato Project Colombia” with an effective date of July 31, 2019 and a report date of December 19, 2019.
9. I have read NI 43-101 and Form 43-101F1 and the sections of the Technical Report I am responsible for have been prepared in compliance with that instrument and form.
10. As of the aforementioned Effective Date, to the best of my knowledge, information and belief, the sections of the Technical Report I am responsible for contains all scientific and technical information that is required to be disclosed to make the Technical Report not misleading.
Dated this 18th Day of September, 2020.
_______Signed_________________________ Sealed
David Bird, MSc, PG, RM-SME
U.S. Offices:
Anchorage 907.677.3520
Clovis 559.452.0182
Denver 303.985.1333
Elko 775.753.4151
Reno 775.828.6800
Tucson 520.544.3688
Canadian Offices:
Saskatoon 306.955.4778
Sudbury 705.682.3270
Toronto 416.601.1445
Vancouver 604.681.4196
Yellowknife 867.873.8670
Group Offices:
Africa
Asia
Australia
Europe
North America
South America
SRK Consulting (U.S.), Inc.
5250 Neil Road, Suite 300
Reno, Nevada 89502
T: (775) 828-6800
F: (775) 828-6820
www.srk.com
CERTIFICATE OF QUALIFIED PERSON
I, R. Breese Burnley, PE do hereby certify that:
1. I am Practice Leader/Principal Engineer of SRK Consulting (U.S.), Inc., 5250 Neil Road, Reno, Nevada 89502.
2. This certificate applies to the technical report titled “Revised NI 43-101 Technical Report Pre-Feasibility Study Marmato Project Colombia” with an Effective Date of March 17, 2020 (the “Technical Report”).
3. I graduated with a B.Sc. degree in in Geology in 1991 from the University of Nevada, Reno. In addition, I obtained an M.Sc. in Geological Engineering in 1993, also from the University of Nevada, Reno.
4. I am a registered Professional Engineer in the State of Nevada (PE No. 16225). I have worked as an engineer for a total of 27 years since my graduation from university. My relevant experience includes site investigations, conceptual and detailed design, construction supervision, management and operational assessments, mine reclamation permitting and closure design and permitting at numerous industrial and mining properties throughout the western United States and South and Central America.
5. I have read the definition of “qualified person” set out in National Instrument 43-101 (NI 43-101) and certify that by reason of my education, affiliation with a professional association (as defined in NI 43-101) and past relevant work experience, I fulfill the requirements to be a “qualified person” for the purposes of NI 43-101.
6. I have visited the Marmato property. I visited the Marmato property on January 28, 2020 for 1 day.
7. I am responsible for Tailings Section 18.15, and the tailings portions of Section 21, and portions of Sections 1, 24, 25 and 26.
8. I am independent of the issuer applying all of the tests in section 1.5 of NI 43-101.
9. I have not had prior involvement with the property that is the subject of the Technical Report.
10. I have read NI 43-101 and Form 43-101F1 and the sections of the Technical Report I am responsible for have been prepared in compliance with that instrument and form.
11. As of the aforementioned Effective Date, to the best of my knowledge, information and belief, the sections of the Technical Report I am responsible for contains all scientific and technical information that is required to be disclosed to make the Technical Report not misleading.
Dated this 18th Day of September, 2020.
_______Signed_________________________ Sealed
R. Breese Burnley, PE
SRK Consulting (U.S.), Inc.
Suite 600
1125 Seventeenth Street
Denver, CO 80202
T: 303.985.1333
F: 303.985.9947
www.srk.com
U.S. Offices:
Anchorage 907.677.3520
Clovis 559.452.0182
Denver 303.985.1333
Elko 775.753.4151
Reno 775.828.6800
Tucson 520.544.3688
Canadian Offices:
Saskatoon 306.955.4778
Sudbury 705.682.3270
Toronto 416.601.1445
Vancouver 604.681.4196
Yellowknife 867.873.8670
Group Offices:
Africa
Asia
Australia
Europe
North America
South America
CERTIFICATE OF QUALIFIED PERSON
I, Fredy Henriquez, MSc Eng, SME, ISRM do hereby certify that:
1. I am Principal Consultant (Rock Mechanics) of SRK Consulting (U.S.), Inc., 1125 Seventeenth Street, Suite 600, Denver, CO, USA, 80202.
2. This certificate applies to the technical report titled “Revised NI 43-101 Technical Report Pre-Feasibility Study Marmato Project Colombia” with an Effective Date of March 17, 2020 (the “Technical Report”).
3. I graduated with a degree in Civil Mine Engineer from University of Santiago, Chile in 2000. In addition, I have obtained a Masters degree (MSc) in Engineering (Rock Mechanics) from WASM, Curtin University, Australia (2011). I am a Registered Member of the Society for Mining, Metallurgy, and Exploration (SME, register number 4196405RM). I have worked as a geotechnical engineer for a total of 25 years since my graduation from university. My relevant experience includes civil and mining geotechnical projects ranging from conceptual through feasibility design levels and operations support. I am skilled in both soil and rock mechanics engineering and specialize in the design and management of mine excavations. My primary areas of expertise include mine operations, mine planning, hard rock and soft rock characterization, underground and open pit stability analysis, database management, geotechnical data collection, probabilistic analysis, risk assessment, slope monitoring, modeling and pit wall pore pressure reductions. I have undertaken and managed large geotechnical projects for the mining industry throughout North, Central, South America, Australia and South Africa.
4. I have read the definition of “qualified person” set out in National Instrument 43-101 (NI 43-101) and certify that by reason of my education, affiliation with a professional association (as defined in NI 43-101) and past relevant work experience, I fulfill the requirements to be a “qualified person” for the purposes of NI 43-101.
5. I visited the Marmato property on January 8, 2020 for 4 days and July 16, 2019 for 3 days.
6. I am responsible for geotechnical Section 16.4 of the Technical Report.
7. I am independent of the issuer applying all of the tests in section 1.5 of NI 43-101.
8. I have not had prior involvement with the property that is the subject of the Technical Report.
9. I have read NI 43-101 and Form 43-101F1 and the sections of the Technical Report I am responsible for have been prepared in compliance with that instrument and form.
10. As of the aforementioned Effective Date, to the best of my knowledge, information and belief, the sections of the Technical Report I am responsible for contains all scientific and technical information that is required to be disclosed to make the Technical Report not misleading.
Dated this 18th Day of September, 2020.
_______Signed_________________________ Sealed
Fredy Henriquez, MSc Eng, SME, ISRM Principal Consultant (Rock Mechanics)
SRK Consulting (U.S.), Inc.
Suite 600
1125 Seventeenth Street
Denver, CO 80202
T: 303.985.1333
F: 303.985.9947
www.srk.com
U.S. Offices:
Anchorage 907.677.3520
Clovis 559.452.0182
Denver 303.985.1333
Elko 775.753.4151
Reno 775.828.6800
Tucson 520.544.3688
Canadian Offices:
Saskatoon 306.955.4778
Sudbury 705.682.3270
Toronto 416.601.1445
Vancouver 604.681.4196
Yellowknife 867.873.8670
Group Offices:
Africa
Asia
Australia
Europe
North America
South America
CERTIFICATE OF QUALIFIED PERSON
I, David Hoekstra, BSc Civil Engineering, P.E, do hereby certify that:
1. I am Principal Consultant (Civil Engineer) of SRK Consulting (U.S.), Inc., 1125 Seventeenth Street, Suite 600, Denver, CO, USA, 80202.
2. This certificate applies to the technical report titled “Revised NI 43-101 Technical Report Pre-Feasibility Study Marmato Project Colombia” with an Effective Date of March 17, 2020 (the “Technical Report”).
3. I graduated with a degree in Civil Engineering from Colorado State University in 1986. I am a Professional Engineer of the States of Alaska, Colorado, Montana, South Carolina, and Wyoming. I have worked as an Engineer for a total of 33 years since my graduation from university. My relevant experience includes the design and implementation of mine water management systems and storm water controls for numerous PEA, PFS, FS-level and operating mine projects in the US and abroad.
4. I have read the definition of “qualified person” set out in National Instrument 43-101 (NI 43-101) and certify that by reason of my education, affiliation with a professional association (as defined in NI 43-101) and past relevant work experience, I fulfill the requirements to be a “qualified person” for the purposes of NI 43-101.
5. I have not visited the Marmato property.
6. I am responsible for Section 18.14, Hydrology Section 20.2.5, and portions of Sections 1, 24, 25 and 26.
7. I am independent of the issuer applying all of the tests in section 1.5 of NI 43-101.
8. I have had prior involvement with the property that is the subject of the Technical Report. The nature of my prior involvement is acting as QP on the Bluenose Gold Corporation’s Marmato Project report titled “NI 43-101 Technical Report Preliminary Economic Assessment Marmato Project Colombia” with an effective date of July 31, 2019 and a report date of December 19, 2019.
9. I have read NI 43-101 and Form 43-101F1 and the sections of the Technical Report I am responsible for have been prepared in compliance with that instrument and form.
10. As of the aforementioned Effective Date, to the best of my knowledge, information and belief, the sections of the Technical Report I am responsible for contains all scientific and technical information that is required to be disclosed to make the Technical Report not misleading.
Dated this 18th Day of September, 2020.
_______Signed_________________________ Sealed
David Hoekstra, BS, PE, NCEES, SME-RM
SRK Consulting (U.S.), Inc.
Suite 600
1125 Seventeenth Street
Denver, CO 80202
T: 303.985.1333
F: 303.985.9947
www.srk.com
U.S. Offices:
Anchorage 907.677.3520
Clovis 559.452.0182
Denver 303.985.1333
Elko 775.753.4151
Reno 775.828.6800
Tucson 520.544.3688
Canadian Offices:
Saskatoon 306.955.4778
Sudbury 705.682.3270
Toronto 416.601.1445
Vancouver 604.681.4196
Yellowknife 867.873.8670
Group Offices:
Africa
Asia
Australia
Europe
North America
South America
CERTIFICATE OF QUALIFIED PERSON
I, Eric Olin, MSc, MBA, RM-SME do hereby certify that:
1. I am a Principal Process Metallurgist of SRK Consulting (U.S.), Inc., 1125 Seventeenth Street, Suite 600, Denver, CO, USA, 80202.
2. This certificate applies to the technical report titled “Revised NI 43-101 Technical Report Pre-Feasibility Study Marmato Project Colombia” with an Effective Date of March 17, 2020 (the “Technical Report”).
3. I graduated with a Master of Science degree in Metallurgical Engineering from the Colorado School of Mines in 1976. I am a Registered Member of The Society for Mining, Metallurgy and Exploration, Inc. I have worked as a Metallurgist for a total of 40 years since my graduation from the Colorado School of Mines. My relevant experience includes extensive consulting, plant operations, process development, project management and research & development experience with base metals, precious metals, ferrous metals and industrial minerals. I have served as the plant superintendent for several gold and base metal mining operations. Additionally, I have been involved with numerous third-party due diligence audits, and preparation of project conceptual, pre-feasibility and full-feasibility studies.
4. I have read the definition of “qualified person” set out in National Instrument 43-101 (NI 43-101) and certify that by reason of my education, affiliation with a professional association (as defined in NI 43-101) and past relevant work experience, I fulfill the requirements to be a “qualified person” for the purposes of NI 43-101.
5. I have visited the Marmato property. I visited the property on December 17, 2019 for 2 days.
6. I am responsible for the preparation of Metallurgy Sections 13, 17.1 17.2 and Upper Zone processing portion of Section 21, portions of Sections 1, 24, 25 and 26 of the Technical Report.
7. I am independent of the issuer applying all of the tests in section 1.5 of NI 43-101.
8. I have had prior involvement with the property that is the subject of the Technical Report. The nature of my prior involvement is acting as QP on the Bluenose Gold Corporation’s Marmato Project report titled “NI 43-101 Technical Report Preliminary Economic Assessment Marmato Project Colombia” with an effective date of July 31, 2019 and a report date of December 19, 2019.
9. I have read NI 43-101 and Form 43-101F1 and the sections of the Technical Report I am responsible for have been prepared in compliance with that instrument and form.
10. As of the aforementioned Effective Date, to the best of my knowledge, information and belief, the sections of the Technical Report I am responsible for contains all scientific and technical information that is required to be disclosed to make the Technical Report not misleading.
Dated this 18th Day of September, 2020.
_______Signed_________________________ Sealed
Eric Olin, MSc, MBA, RM-SME
SRK Consulting (U.S.), Inc.
Suite 600
1125 Seventeenth Street
Denver, CO 80202
T: 303.985.1333
F: 303.985.9947
www.srk.com
U.S. Offices:
Anchorage 907.677.3520
Clovis 559.452.0182
Denver 303.985.1333
Elko 775.753.4151
Reno 775.828.6800
Tucson 520.544.3688
Canadian Offices:
Saskatoon 306.955.4778
Sudbury 705.682.3270
Toronto 416.601.1445
Vancouver 604.681.4196
Yellowknife 867.873.8670
Group Offices:
Africa
Asia
Australia
Europe
North America
South America
CERTIFICATE OF QUALIFIED PERSON
I, Jeff Osborn, BEng Mining, MMSAQP do hereby certify that:
1. I am a Principal Consultant (Mining Engineer) of SRK Consulting (U.S.), Inc., 1125 Seventeenth, Suite 600, Denver, CO, USA, 80202.
2. This certificate applies to the technical report titled “Revised NI 43-101 Technical Report Pre-Feasibility Study Marmato Project Colombia” with an Effective Date of March 17, 2020 (the “Technical Report”).
3. I graduated with a Bachelor of Science Mining Engineering degree from the Colorado School of Mines in 1986. I am a Qualified Professional (QP) Member of the Mining and Metallurgical Society of America. I have worked as a Mining Engineer for a total of 32 years since my graduation from university. My relevant experience includes responsibilities in operations, maintenance, engineering, management, and construction activities.
4. I have read the definition of “qualified person” set out in National Instrument 43-101 (NI 43-101) and certify that by reason of my education, affiliation with a professional association (as defined in NI 43-101) and past relevant work experience, I fulfill the requirements to be a “qualified person” for the purposes of NI 43-101.
5. I visited the Marmato property on July 16, 2019 for 3 days and on August 22, 2017 for 2 days.
6. I am responsible for Infrastructure and portions of the Cost Estimation Sections 18.1, 18.2, 18.13,18.16, and 21 (excluding processing and tailings portions of Section 21), and portions of Sections 1, 24, 25 and 26.
7. I am independent of the issuer applying all of the tests in section 1.5 of NI 43-101.
8. I have had prior involvement with the property that is the subject of the Technical Report. The nature of my prior involvement is acting as QP on the Bluenose Gold Corporation’s Marmato Project report titled “NI 43-101 Technical Report Preliminary Economic Assessment Marmato Project Colombia” with an effective date of July 31, 2019 and a report date of December 19, 2019.
9. I have read NI 43-101 and Form 43-101F1 and the sections of the Technical Report I am responsible for have been prepared in compliance with that instrument and form.
10. As of the aforementioned Effective Date, to the best of my knowledge, information and belief, the sections of the Technical Report I am responsible for contains all scientific and technical information that is required to be disclosed to make the Technical Report not misleading.
Dated this 18th Day of September, 2020.
_______Signed_________________________ Sealed
Jeff Osborn, BEng Mining, MMSAQP [01458QP] Principal Consultant (Mining Engineer)
SRK Consulting (U.S.), Inc.
Suite 600
1125 Seventeenth Street
Denver, CO 80202
T: 303.985.1333
F: 303.985.9947
www.srk.com
U.S. Offices:
Anchorage 907.677.3520
Clovis 559.452.0182
Denver 303.985.1333
Elko 775.753.4151
Reno 775.828.6800
Tucson 520.544.3688
Canadian Offices:
Saskatoon 306.955.4778
Sudbury 705.682.3270
Toronto 416.601.1445
Vancouver 604.681.4196
Yellowknife 867.873.8670
Group Offices:
Africa
Asia
Australia
Europe
North America
South America
CERTIFICATE OF QUALIFIED PERSON
I, Benjamin Parsons, MSc, MAusIMM (CP) do hereby certify that:
1. I am a Principal Consultant (Resource Geology) of SRK Consulting (U.S.), Inc., 1125 Seventeenth Street, Suite 600, Denver, CO, USA, 80202.
2. This certificate applies to the technical report titled “Revised NI 43-101 Technical Report Pre-Feasibility Study Marmato Project Colombia” with an Effective Date of March 17, 2020 (the “Technical Report”).
3. I graduated with a degree in Exploration Geology from Cardiff University, UK in 1999. In addition, I have obtained a Masters degree (MSc) in Mineral Resources from Cardiff University, UK in 2000 and have worked as a geologist for a total of 19 years since my graduation from university. I am a member of the Australian Institution of Materials Mining and Metallurgy (Membership Number 222568) and I am a Chartered Professional.
4. I have read the definition of “qualified person” set out in National Instrument 43-101 (NI 43-101) and certify that by reason of my education, affiliation with a professional association (as defined in NI 43-101) and past relevant work experience, I fulfill the requirements to be a “qualified person” for the purposes of NI 43-101.
5. I visited the Marmato property on June 11, 2020 for 3 days, August 17, 2017 for 1 day and March 12, 2012 for three days.
6. I am responsible for Sections 2 through 12 (except 4.4), 14, 23 and portions of Sections 1, 24, 25 and 26.
7. I am independent of the issuer applying all of the tests in section 1.5 of NI 43-101.
8. I have had prior involvement with the property that is the subject of the Technical Report. The nature of my prior involvement is acting as QP on the Bluenose Gold Corporation’s Marmato Project report titled “NI 43-101 Technical Report Preliminary Economic Assessment Marmato Project Colombia” with an effective date of July 31, 2019 and a report date of December 19, 2019.
9. I have read NI 43-101 and Form 43-101F1 and the sections of the Technical Report I am responsible for have been prepared in compliance with that instrument and form.
10. As of the aforementioned Effective Date, to the best of my knowledge, information and belief, the sections of the Technical Report I am responsible for contains all scientific and technical information that is required to be disclosed to make the Technical Report not misleading.
Dated this 18th Day of September, 2020.
_______Signed_________________________ Sealed
Benjamin Parsons, MSc, MAusIMM Principal Consultant (Resource Geology)
SRK Consulting (U.S.), Inc.
Suite 600
1125 Seventeenth Street
Denver, CO 80202
T: 303.985.1333
F: 303.985.9947
www.srk.com
U.S. Offices:
Anchorage 907.677.3520
Clovis 559.452.0182
Denver 303.985.1333
Elko 775.753.4151
Reno 775.828.6800
Tucson 520.544.3688
Canadian Offices:
Saskatoon 306.955.4778
Sudbury 705.682.3270
Toronto 416.601.1445
Vancouver 604.681.4196
Yellowknife 867.873.8670
Group Offices:
Africa
Asia
Australia
Europe
North America
South America
CERTIFICATE OF QUALIFIED PERSON
I, Cristian A. Pereira Farias, SME-RM, do hereby certify that:
1. I am Principal Consultant (Hydrogeologist) of SRK Consulting (U.S.), Inc., 1125 Seventeenth Street, Suite 600, Denver, CO, USA, 80202.
2. This certificate applies to the technical report titled “Revised NI 43-101 Technical Report Pre-Feasibility Study Marmato Project Colombia” with an Effective Date of March 17, 2020 (the “Technical Report”).
3. I graduated with a degree in Bachelors of Science in Geology from Universidad de Chile in 1999. I am a registered member of the Society for Mining, Metallurgy, and Exploration. I have worked as a hydrogeologist for a total of 19 years since my graduation from university. My relevant experience includes the developing conceptual and numerical hydrogeological models, the evaluation of groundwater resources, mine dewatering requirements, environmental impacts of mining, pit lake infilling, brine extraction, and pore pressure analyses.
4. I have read the definition of “qualified person” set out in National Instrument 43-101 (NI 43-101) and certify that by reason of my education, affiliation with a professional association (as defined in NI 43-101) and past relevant work experience, I fulfill the requirements to be a “qualified person” for the purposes of NI 43-101.
5. I visited the Marmato property on August 12, 2019 for 2 days.
6. I am responsible for Hydrogeology Sections 16.3, and portions of Sections 1, 24, 25 and 26.
7. I am independent of the issuer applying all of the tests in section 1.5 of NI 43-101.
8. I have had prior involvement with the property that is the subject of the Technical Report. The nature of my prior involvement is acting as QP on the Bluenose Gold Corporation’s Marmato Project report titled “NI 43-101 Technical Report Preliminary Economic Assessment Marmato Project Colombia” with an effective date of July 31, 2019 and a report date of December 19, 2019.
9. I have read NI 43-101 and Form 43-101F1 and the sections of the Technical Report I am responsible for have been prepared in compliance with that instrument and form.
10. As of the aforementioned Effective Date, to the best of my knowledge, information and belief, the sections of the Technical Report I am responsible for contains all scientific and technical information that is required to be disclosed to make the Technical Report not misleading.
Dated this 18th Day of September, 2020.
_______Signed_________________________ Sealed
Cristian A. Pereira Farias, SME-RM
SRK Consulting (U.S.), Inc.
Suite 600
1125 Seventeenth Street
Denver, CO 80202
T: 303.985.1333
F: 303.985.9947
www.srk.com
U.S. Offices:
Anchorage 907.677.3520
Clovis 559.452.0182
Denver 303.985.1333
Elko 775.753.4151
Reno 775.828.6800
Tucson 520.544.3688
Canadian Offices:
Saskatoon 306.955.4778
Sudbury 705.682.3270
Toronto 416.601.1445
Vancouver 604.681.4196
Yellowknife 867.873.8670
Group Offices:
Africa
Asia
Australia
Europe
North America
South America
CERTIFICATE OF QUALIFIED PERSON
I, Joanna Poeck, BEng Mining, SME-RM, MMSAQP, do hereby certify that:
1. I am a Principal Mining Engineer of SRK Consulting (U.S.), Inc., 1125 Seventeenth Street, Suite 600, Denver, CO, USA, 80202.
2. This certificate applies to the technical report titled “Revised NI 43-101 Technical Report Pre-Feasibility Study Marmato Project Colombia” with an Effective Date of March 17, 2020 (the “Technical Report”).
3. I graduated with a degree in Mining Engineering from Colorado School of Mines in 2003. I am a Registered Member of the Society of Mining, Metallurgy & Exploration Geology. I am a QP member of the Mining & Metallurgical Society of America. I have worked as a Mining Engineer for a total of 15 years since my graduation from university. My relevant experience includes open pit and underground design, mine scheduling, pit optimization and truck productivity analysis.
4. I have read the definition of “qualified person” set out in National Instrument 43-101 (NI 43-101) and certify that by reason of my education, affiliation with a professional association (as defined in NI 43-101) and past relevant work experience, I fulfill the requirements to be a “qualified person” for the purposes of NI 43-101.
5. I have not visited the Marmato property.
6. I am responsible for the opening statement in Section 15, Section 15.1.5 through 15.1.8, portions of Sections 15.2 and 15.3 pertaining to the MDZ, Section 16.5, portions of 16.6 pertaining to the MDZ, and portions of Sections 1, 24, 25 and 26.
7. I am independent of the issuer applying all of the tests in section 1.5 of NI 43-101.
8. I have had prior involvement with the property that is the subject of the Technical Report. The nature of my prior involvement is acting as QP on the Bluenose Gold Corporation’s Marmato Project report titled “NI 43-101 Technical Report Preliminary Economic Assessment Marmato Project Colombia” with an effective date of July 31, 2019 and a report date of December 19, 2019.
9. I have read NI 43-101 and Form 43-101F1 and the sections of the Technical Report I am responsible for have been prepared in compliance with that instrument and form.
10. As of the aforementioned Effective Date, to the best of my knowledge, information and belief, the sections of the Technical Report I am responsible for contains all scientific and technical information that is required to be disclosed to make the Technical Report not misleading.
Dated this 18th Day of September, 2020.
_______Signed_________________________ Sealed
Joanna Poeck, BEng Mining, SME-RM[4131289RM], MMSAQP[01387QP] Principal Consultant (Mining Engineer)
SRK Consulting (U.S.), Inc.
Suite 600
1125 Seventeenth Street
Denver, CO 80202
T: 303.985.1333
F: 303.985.9947
www.srk.com
U.S. Offices:
Anchorage 907.677.3520
Clovis 559.452.0182
Denver 303.985.1333
Elko 775.753.4151
Reno 775.828.6800
Tucson 520.544.3688
Canadian Offices:
Saskatoon 306.955.4778
Sudbury 705.682.3270
Toronto 416.601.1445
Vancouver 604.681.4196
Yellowknife 867.873.8670
Group Offices:
Africa
Asia
Australia
Europe
North America
South America
QP_Cert_Rodrigues.docx
CERTIFICATE OF QUALIFIED PERSON
I, Fernando Rodrigues, BS Mining, MBA, MMSAQP do hereby certify that:
1. I am Practice Leader and Principal Consultant (Mining Engineer) of SRK Consulting (U.S.), Inc., 1125 Seventeenth Street, Suite 600, Denver, CO, USA, 80202.
2. This certificate applies to the technical report titled “Revised NI 43-101 Technical Report Pre-Feasibility Study Marmato Project Colombia” with an Effective Date of March 17, 2020 (the “Technical Report”).
3. I graduated with a Bachelors of Science degree in Mining Engineering from South Dakota School of Mines and Technology in 1999. I am a QP member of the MMSA. I have worked as a Mining Engineer for a total of 21 years since my graduation from South Dakota School of Mines and Technology in 1999. My relevant experience includes mine design and implementation, short term mine design, dump design, haulage studies, blast design, ore control, grade estimation, database management.
4. I have read the definition of “qualified person” set out in National Instrument 43-101 (NI 43-101) and certify that by reason of my education, affiliation with a professional association (as defined in NI 43-101) and past relevant work experience, I fulfill the requirements to be a “qualified person” for the purposes of NI 43-101.
5. I visited the Marmato property on August 22, 2017 for 2 days, January 7, 2020 for 4 days, February 2, 2020 for 4 days.
6. I am responsible for Upper Zone Mining and Economics and related portions of Section 15.1.1 through 15.1.4, portions of Sections 15.2 and 15.3 pertaining to the Upper Zone, the opening statement in Section 16, Sections 16.1, 16.4, portions of 16.6 pertaining to the Upper Zone, 19 and 22, and portions of Sections 1, 24, 25 and 26 summarized therefrom, of this Technical Report.
7. I am independent of the issuer applying all of the tests in section 1.5 of NI 43-101.
8. I have had prior involvement with the property that is the subject of the Technical Report. The nature of my prior involvement is acting as QP on the Bluenose Gold Corporation’s Marmato Project report titled “NI 43-101 Technical Report Preliminary Economic Assessment Marmato Project Colombia” with an effective date of July 31, 2019 and a report date of December 19, 2019.
9. I have read NI 43-101 and Form 43-101F1 and the sections of the Technical Report I am responsible for have been prepared in compliance with that instrument and form.
10. As of the aforementioned Effective Date, to the best of my knowledge, information and belief, the sections of the Technical Report I am responsible for contains all scientific and technical information that is required to be disclosed to make the Technical Report not misleading.
Dated this 18th Day of September, 2020.
_______Signed_________________________ Sealed
Fernando Rodrigues, BS Mining, MBA, MMSAQP [01405QP]
U.S. Offices:
Anchorage 907.677.3520
Clovis 559.452.0182
Denver 303.985.1333
Elko 775.753.4151
Reno 775.828.6800
Tucson 520.544.3688
Canadian Offices:
Saskatoon 306.955.4778
Sudbury 705.682.3270
Toronto 416.601.1445
Vancouver 604.681.4196
Yellowknife 867.873.8670
Group Offices:
Africa
Asia
Australia
Europe
North America
South America
SRK Consulting (U.S.), Inc.
5250 Neil Road, Suite 300
Reno, Nevada 89502
T: (775) 828-6800
F: (775) 828-6820
www.srk.com
CERTIFICATE OF QUALIFIED PERSON
I, Mark Allan Willow, MSc, CEM, SME-RM do hereby certify that:
1. I am Practice Leader/Principal Environmental Scientist of SRK Consulting (U.S.), Inc., 5250 Neil Road, Reno, Nevada 89502.
2. This certificate applies to the technical report titled “Revised NI 43-101 Technical Report Pre-Feasibility Study Marmato Project Colombia” with an Effective Date of March 17, 2020 (the “Technical Report”).
3. I graduated with Bachelor's degree in Fisheries and Wildlife Management from the University of Missouri in 1987 and a Master's degree in Environmental Science and Engineering from the Colorado School of Mines in 1995. I have worked as Biologist/Environmental Scientist for over 25 years since my graduation from university. My relevant experience includes environmental due diligence/competent persons evaluations of developmental phase and operational phase mines through the world, including small gold mining projects in Panama, Senegal, Peru, Ecuador, Philippines, and Colombia; open pit and underground coal mines in Russia; large copper and iron mines and processing facilities in Mexico and Brazil; bauxite operations in Jamaica; and a coal mine/coking operation in the People's Republic of China. My Project Manager experience includes several site characterization and mine closure projects. I work closely with the U.S. Forest Service and U.S. Bureau of Land Management on permitting and mine closure projects to develop uniquely successful and cost-effective closure alternatives for the abandoned mining operations. Finally, I draw upon this diverse background for knowledge and experience as a human health and ecological risk assessor with respect to potential environmental impacts associated with operating and closing mining properties and have experience in the development of Preliminary Remediation Goals and hazard/risk calculations for site remedial action plans under Superfund activities according to current U.S. EPA risk assessment guidance.
4. I am a Certified Environmental Manager (CEM) in the State of Nevada (#1832) in accordance with Nevada Administrative Code 459.970 through 459.9729. Before any person consults for a fee in matters concerning: the management of hazardous waste; the investigation of a release or potential release of a hazardous substance; the sampling of any media to determine the release of a hazardous substance; the response to a release or cleanup of a hazardous substance; or the remediation soil or water contaminated with a hazardous substance, they must be certified by the Nevada Division of Environmental Protection, Bureau of Corrective Action;
5. I am a Registered Member (No. 4104492) of the Society for Mining, Metallurgy & Exploration Inc. (SME).
6. I have read the definition of “qualified person” set out in National Instrument 43-101 (NI 43-101) and certify that by reason of my education, affiliation with a professional association (as defined in NI 43-101) and past relevant work experience, I fulfill the requirements to be a “qualified person” for the purposes of NI 43-101.
7. I visited the Marmato property on December 1, 2016 for 1 day.
8. I am responsible for Section 4.4, Environmental Section 20 (except section 20.1.3), and portions of Sections 1, 24, 25 and 26.
9. I am independent of the issuer applying all of the tests in section 1.5 of NI 43-101.
10. I have had prior involvement with the property that is the subject of the Technical Report. The nature of my prior involvement is acting as QP on Bluenose Gold Corporation’s Marmato Project report titled “NI 43-101 Technical Report Preliminary Economic Assessment Marmato Project Colombia” with an effective date of July 31, 2019 and a report date of December 19, 2019.
SRK Consulting Page 2
QP_Cert_Willow.docx
11. I have read NI 43-101 and Form 43-101F1 and the sections of the Technical Report I am responsible for have been prepared in compliance with that instrument and form.
12. As of the aforementioned Effective Date, to the best of my knowledge, information and belief, the sections of the Technical Report I am responsible for contains all scientific and technical information that is required to be disclosed to make the Technical Report not misleading.
Dated this 18th Day of September, 2020.
_______Signed_________________________ Sealed
Mark Allan Willow, MSc, CEM, SME-RM SME-RM# 4104492
CERTIFICATE OF QUALIFIED PERSON
Tommaso Roberto Raponi, P. Eng.
To Accompany the Report entitled, “Revised NI 43-101 Technical Report Pre-Feasibility Study
Marmato Project Colombia” prepared for Caldas Gold Corp. effective date March 17, 2020 and
dated September 18, 2020.
I, Tommaso Roberto Raponi, P. Eng., do hereby certify:
1. I am a Principal Metallurgist at Ausenco Engineering Canada Inc., 11 King St West, Suite
1550, Toronto, ON, M5H 4C7.
2. I hold a Bachelor's degree in Geological Engineering from University of Toronto, Toronto,
Ontario, Canada.
3. I am registered as a Professional Engineer in Ontario and British Columbia. I have worked for
more than 36 years in the mining industry in various positions continuously since my
graduation from university. I have worked as an independent consultant since 2016.
4. I have read the definition of "qualified person" set out in National Instrument 43‐101 (NI 43‐
101) and certify that by reason of my education, affiliation with a professional association (as
defined by NI 43‐101) and past relevant work experience, I fulfill the requirements to be a
"qualified person" for the purposes of NI 43‐101.
5. I have not visited site.
6. I am responsible for the MDZ process plant and infrastructure engineering and related
portions of Sections 17.3, 18.3 through 18.12, MDZ processing and infrastructure portions of
21.1.2 and 21.3.2 and portions of Sections 1, 24, 25 and 26 of the Technical Report.
7. I have not had prior involvement with the property that is the subject of the Technical Report.
8. I am independent of the issuer applying all of the tests in section 1.5 of NI 43‐101.
9. I have read NI 43‐101 and Form 43‐101F1 and the sections of the Technical Report I am
responsible for have been prepared in compliance with that instrument and form.
10. As of the aforementioned Effective Date, to the best of my knowledge, information and belief,
the sections of the Technical Report I am responsible for contains all scientific and technical
information that is required to be disclosed to make the Technical Report not misleading.
Dated this 18th day of September 2020
“Signed” “Sealed” Tommaso Roberto Raponi, P. Eng.
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Appendices
MMS/KD August 2020
Appendix B: MDZ Tailings Drawings
DSTF 6(SITE 6)
ROCK STARTER EMBANKMENT
ROCKSTARTER
EMBANKMENT
DSTF 1
DSTF 2
CAUCA RIVER
ROCK STARTER EMBANKMENT
ROCK STARTER EMBANKMENT
STORMWATERDIVERSION CHANNELS
PROCESS PLANT
PORTAL
EXISTING TSF
HIGH VOLTAGEPOWERLINES (230Kv)
LOW VOLTAGEPOWERLINES
HIGH VOLTAGE POWERTOWER (TYP.)
MARMATO RIVER
CAMP
DSTF 1 ACCESS/ HAUL ROAD
FILTER PLANT
MARMATO MUNICIPAL ROAD
NATIONAL HIGHWAY
STORMWATERDIVERSIONCHANNELS
EXISTING PLANT AND PORTAL
EL LLANO TOWNSHIP
TEMPORARYSTOCKPILE AREA
CONCEPTUAL TAILINGS FACILITY SITE PLAN
A
N
FILE NAME: 100-SitePlan_544400.020_20200729.dwg
DRAWING TITLE:
consultingPROJECT:
PREPARED BY:
CALDAS GOLD CORPORATION
544400.070-800
DRAWING NO.DATE:
SRK JOB NO.:
C:\Users\jsames\Documents\SRK\GCG\544400-020_Marmato_PEA_PFS\040_Drafting\Task_810_PFS_Design\100-SitePlan_544400.020_20200729.dwg
8.12.2020IF THE ABOVE BARDOES NOT MEASURE 20mm,
THE DRAWING SCALE IS ALTERED
DESIGN: JS/ RBBDRAWN: JSREVIEWED: RBB
APPROVED: RBBPROJECT:
REV. NO.:
MARMATO PRE-FEASIBILITY STUDY
1000m
METERS
100m 200m 300m
(SCALE - 1:100)
MARMATO PRE-FEASIBILITY STUDY
DRAFT
ROCK STARTER EMBANKMENT
STORMWATER DIVERSIONCHANNEL AROUND PLANT
(REF. DETAIL 7-104)
FILTER PLANT
A'
AB'
B
PORTAL
STILLING BASIN
PRECAST CONCRETE BRIDGE(REF. DETAIL 5-104)
DSTF 1 ACCESS/ HAUL ROADCENTERLINE (REF. DETAIL 6-104)
MARMATO MUNICIPALROAD
STORMWATER DIVERSIONCHANNEL ABOVE DSTF
(REF. DETAIL 7-104)
5%
STORMWATER DITCH (TYP.)(REF. DETAIL 7-104)
BENCH DETAIL (TYP.)(REF. DETAIL 2-103)TEMPORARY TOP
DECK STORMWATERMANAGEMENT PONDS
TRANSMISSION TOWER (TYP.)
HIGH VOLTAGEPOWER LINE (TYP.)
PRECAST CONCRETEBRIDGE (REF. DETAIL 8-104)
5%
DSTF 2
2.5:12.5:1
2.5:1
2:1
2:1
2.5:12.5:1
1000
1010
980
990950
960
970
920930
940
1010
1010
980
9901000
UNDERDRAIN (TYP.)(REF. DETAIL 4-103)
COLLECTION TANKS(REF. DETAIL 5-104)
EXISTING MUNICIPAL ROAD
EXISTING STRUCTURE (TYP.)
TRAFFIC CONTROLS
PROCESSPLANT
1100
1125
1150
1175
1200
1050 975
1000
1025
1050
1075
850
875
900
925
950
975
1000
1025
975
1000
10251050
10751100
1100
1075
1100
10251050
1200
1225
1250
1275
1300
1075
1100
1125
1150
900
925
950
90092
5
900
925
950
970
980990
980
ACCESS ROAD TOPORTAL BOUNDARY(REF. DETAIL 6-104)
CAMPPADSCAMP ACCESS ROADBY OTHERS
Elev
atio
n (m
, am
sl)
Station (m)
850
900
950
1000
1050
1100
1150
850
900
950
1000
1050
1100
1150
-0+100 0+000 0+100 0+200 0+300 0+400 0+500 0+600 0+700
Elev
atio
n (m
, am
sl)
Station (m)
900
950
1000
1050
1100
1150
1200
900
950
1000
1050
1100
1150
1200
-0+100 0+000 0+100 0+200 0+300 0+400 0+500
STORMWATER DIVERSION CHANNEL ABOVE DSTF(REF DETAIL 7-104)
DSTF 2: COMPACTED CEMENTAMENDED FILTERED TAILINGS
ROCK STARTER EMBANKMENT
EXISTING GROUND
BENCH (TYP).(REF. DETAIL 2-103)
12.5
5%
COLLECTION TANK(REF. DETAIL 5-104)
KEY SUBGRADE FOUNDATIONWITH BENCHES
(REF. DETAIL 1-103)
LINED TOP DECK STORMWATER MANAGEMENT POND
BENCH (TYP).(REF. DETAIL 2-103)
DSTF 2: COMPACTED CEMENTAMENDED FILTERED TAILINGS
LINED TOP DECK STORMWATERMANAGEMENT POND
KEY SUBGRADE FOUNDATIONWITH BENCHES
(REF. DETAIL 1-103)UNDERDRAIN (TYP).(REF. DETAIL 4-103)
12.5
PLANT
EXISTINGGROUND
5%
CONCEPTUAL DSTF PLAN VIEW AND SECTIONS
A
N
FILE NAME: 101-DSTSF-2_544400.020_20200729.dwg
DRAWING TITLE:
consultingPROJECT:
PREPARED BY:
CALDAS GOLD CORPORATION
544400.070-800
DRAWING NO.DATE:
SRK JOB NO.:
C:\Users\jsames\Documents\SRK\GCG\544400-020_Marmato_PEA_PFS\040_Drafting\Task_810_PFS_Design\101-DSTSF-2_544400.020_20200729.dwg
8.12.2020IF THE ABOVE BARDOES NOT MEASURE 20mm,
THE DRAWING SCALE IS ALTERED
DESIGN: JS/ RBBDRAWN: JSREVIEWED: RBB
APPROVED: RBBPROJECT:
REV. NO.:
MARMATO PRE-FEASIBILITY STUDY
1010m
METERS
50m 100m 150m
DSTF 2 PLAN VIEW AND SECTIONS(SCALE - 1:5)
DSTF 2: SECTION A(SCALE - 1:5)
DSTF 2: SECTION B(SCALE - 1:5)
CAU
CA
RIV
ER
MARMATO RIVERNATIONAL HIGHWAY
C'
CD'
ROCK STARTER EMBANKMENT
RIPRAP APRON
DSTF-1 ACCESS ROADCENTERLINE (REF. DETAIL 6-104)
STORMWATER DIVERSION CHANNELSOUTH (REF. DETAIL 7-103)
STORMWATER DITCH (TYP.)(REF. DETAIL 7-104)
BENCH DETAIL (TYP.)(REF DETAIL 2-103)
TRANSMISSION TOWER (TYP.)
HIGH VOLTAGE POWER LINE (TYP.)
UNDERDRAIN (TYP.)(REF DETAIL 4-103)
COLLECTION TANK(REF. DETAIL 5-104)
DTEMPORARY TOP DECK
STORMWATERMANAGEMENT POND
STORMWATER DIVERSIONCHANNEL NORTH (REF. DETAIL
7-104)
DSTF 1
4x1m CULVERTSTORMWATERCROSSING
RIPRAP APRON
EL LLANOTOWNSHIP
2:1
2.5:1
2.5:1
2:12:1
2:1
-5%
-5%
-5%
86087
0870
83084
0850
810
820
86087
0
83084
0850
800810820
870
900925950
775
800
825
700
725
750 750
750
775
800
800
825
850
875
900
900
825
850
875
900
900
925
850
875
850
875
900
725
750775800
825
700
725750
775
800
Elev
atio
n (m
, am
sl)
Station (m)
700
750
800
850
900
950
1000
700
750
800
850
900
950
1000
0+000 0+100 0+200 0+300 0+400 0+500 0+600 0+700 0+750
Elev
atio
n (m
, am
sl)
Station (m)
700
750
800
850
900
950
1000
1050
700
750
800
850
900
950
1000
1050
-0+100 0+000 0+100 0+200 0+300 0+400 0+500
STORMWATER DIVERSION CHANNEL SOUTH(REF DETAIL 7-104)
DSTF 2: COMPACTED CEMENTAMENDED FILTERED TAILINGS
ROCK STARTER EMBANKMENTEXISTING GROUND
BENCH (TYP).(REF. DETAIL 2-103)
12
5%
COLLECTION TANK(REF. DETAIL 5-103)
KEY SUBGRADE FOUNDATIONWITH BENCHES
(REF. DETAIL 1-103)
LINED TOP DECK STORMWATER MANAGEMENT POND
STORMWATER DIVERSION CHANNEL NORTH(REF DETAIL 7-104)
EXISTING GROUND
12.5
12
12.5
DSTF 2: COMPACTED CEMENTAMENDED FILTERED TAILINGS
BENCH (TYP).(REF. DETAIL 2-103)
KEY SUBGRADE FOUNDATIONWITH BENCHES
(REF. DETAIL 1-103)
UNDERDRAIN (TYP).(REF. DETAIL 4-103)
CONCEPTUAL DSTF 1 PLAN VIEW AND SECTIONS
A
N
FILE NAME: 101-DSTSF-2_544400.020_20200729.dwg
DRAWING TITLE:
consultingPROJECT:
PREPARED BY:
CALDAS GOLD CORPORATION
544400.070-800
DRAWING NO.DATE:
SRK JOB NO.:
C:\Users\jsames\Documents\SRK\GCG\544400-020_Marmato_PEA_PFS\040_Drafting\Task_810_PFS_Design\101-DSTSF-2_544400.020_20200729.dwg
8.12.2020IF THE ABOVE BARDOES NOT MEASURE 20mm,
THE DRAWING SCALE IS ALTERED
DESIGN: JS/ RBBDRAWN: JSREVIEWED: RBB
APPROVED: RBBPROJECT:
REV. NO.:
MARMATO PRE-FEASIBILITY STUDY
1020m
METERS
50m 100m 150m
DSTF 1 PLAN VIEW AND SECTIONS(SCALE - 1:5)
DSTF 1: SECTION C(SCALE - 1:5)
DSTF 1: SECTION D(SCALE - 1:5)
TOP DECK 5% MIN. SLOPE
BENCH (TYP.)(REF. DETAIL 2-103)
ROCK STARTER EMBANKMENT
HORIZ. DRAIN 5% MIN SLOPE
UNDER DRAIN
EXISTING GROUND
SHEAR KEY
COLLECTION TANK(REF. DETAIL 5-104)
EMERGENCYOVERFLOW
TOP DECK CONTACT WATER STORAGE
FILTERED TAILINGS
SUBGRADE BENCHING
10.0m
FILTEREDTAILINGS
5.0m
VARIES
CLOSURE COVER
HORIZONTAL DRAIN EVERY 10m VERTICAL
100mm PERF. COLLECTION DRAIN
SUBGRADE BENCHING EXISTING GROUND
GRADE BENCH TO NEARESTUNDERDRAIN AT 2% MIN.
4.0m
12
12
1.0m
5% MIN.
1m CLOSURE COVER
FILTERED TAILINGS
6.5m
STORMWATERDITCH
(REF. DETAIL 7)
1m Min.
1.5m Min.
MIN. AREA 7m2FILTER SAND COVER
EXISTING GROUND
FILTER FABRIC
600mm PERF. PIPE
100mm MINUSDRAIN ROCK
0.25m0.25m
0.25m
DRAIN ROCK FILTER FABRIC
FILTER TAILINGS
100mm PERFORATED PIPE
FILTER SAND COVER
CONCEPTUAL DSTF DETAIL SHEET 1
A103
FILE NAME: 103-Detials-2_544400.020_20200729.dwg
DRAWING TITLE:
consultingPROJECT:
PREPARED BY:
CALDAS GOLD CORPORATION
544400.070-800
DRAWING NO.DATE:
SRK JOB NO.:
C:\Users\jsames\Documents\SRK\GCG\544400-020_Marmato_PEA_PFS\040_Drafting\Task_810_PFS_Design\103-Detials-2_544400.020_20200729.dwg
8.12.2020IF THE ABOVE BARDOES NOT MEASURE 20mm,
THE DRAWING SCALE IS ALTERED
DESIGN: JS/ RBBDRAWN: JSREVIEWED: RBB
APPROVED: RBBPROJECT:
REV. NO.:
MARMATO PRE-FEASIBILITY STUDY
SCALE - 1:2000DSTF TYPICAL SECTION1
SCALE - 1:100DSTF BENCH TYPICAL SECTION2
SCALE - N.T.SHORIZONTAL DRAIN - TYPICAL SECTIONS3
SCALE - N.T.SUNDERDRAIN TYPICAL SECTION4
12
12
10.0m
2.9mVOL = 40,000 LITERS
INFLOW
EMERGENCYOUTFLOW
PUMP TO PLANT
INFLOW
EMERGENCYOUTFLOW
PUMP TO PLANT
PRECAST CONCRETE TANK
CL
SAFETY BERM15.5m
STORMWATERDITCH
EXISTING GROUND
1.5
1
10.5
300mm ROAD WEARING LAYER
SLOPE STABILITY ANCHOR(ASSUMED 15 OF ROAD)
Xm
Hm
CL
EXISTING GROUND
CONCRETE LINED
1
1
0.5
1
Xm
Hm
CL
EXISTING GROUNDRIPRAP LINED
1
0.5
1
0.51
0.5
1
0.5
CL
CONCEPTUAL DSTF DETAIL SHEET 2
A104
FILE NAME: 103-Detials-2_544400.020_20200729.dwg
DRAWING TITLE:
consultingPROJECT:
PREPARED BY:
CALDAS GOLD CORPORATION
544400.070-800
DRAWING NO.DATE:
SRK JOB NO.:
C:\Users\jsames\Documents\SRK\GCG\544400-020_Marmato_PEA_PFS\040_Drafting\Task_810_PFS_Design\103-Detials-2_544400.020_20200729.dwg
8.12.2020IF THE ABOVE BARDOES NOT MEASURE 20mm,
THE DRAWING SCALE IS ALTERED
DESIGN: JS/ RBBDRAWN: JSREVIEWED: RBB
APPROVED: RBBPROJECT:
REV. NO.:
MARMATO PRE-FEASIBILITY STUDY
SCALE - 1:100CONTACT WATER TRANSFER TANK5
SCALE - 1:200ACCESS/ HAUL ROAD TYPICAL SECTION6
SCALE - 1:100STORMWATER MANAGMENT CHANNELS/ DITCHES7
SCALE - N.T.S.PRE-CAST CONCRETE SPAN BRIDGE8
CONCRETE LINED DIVERSION CHANNEL(REF. DETAIL 7-104)
WINGWALLSPAN
CONCRETE FOOTING
SRK Consulting (U.S.), Inc. NI 43-101 Technical Report – Marmato Appendices
MMS/KD August 2020
Appendix C: Economic Model Snapshots
Period Start 1‐Jan‐20 1‐Jan‐21 1‐Jan‐22 1‐Jan‐23 1‐Jan‐24 1‐Jan‐25 1‐Jan‐26 1‐Jan‐27 1‐Jan‐28Period End 31‐Dec‐19 31‐Dec‐20 31‐Dec‐21 31‐Dec‐22 31‐Dec‐23 31‐Dec‐24 31‐Dec‐25 31‐Dec‐26 31‐Dec‐27 31‐Dec‐28
Total0 4 8 12 16 20 21 22 234 4 4 4 4 1 1 1 1
Gold Price US$/oz 1,400 1,400 1,400 1,400 1,400 1,400 1,400 1,400 1,400 Silver Price US$/oz 17.00 17.00 17.00 17.00 17.00 17.00 17.00 17.00 17.00
Upper ZoneTonnes milled tonnes 5,144,663 286,171 437,485 490,050 525,001 491,534 388,538 452,030 409,596 351,864 Head grade (g/t Au) g/t 4.16 3.66 3.99 3.95 3.97 3.96 4.39 4.30 4.34 4.37 Contained gold (ozs) ounces 687,339 33,668 56,077 62,288 67,074 62,579 54,875 62,529 57,171 49,475 Gold Recovery % 87% 87% 87% 87% 87% 87% 87% 87% 87% 87%Gold produced (ozs) ounces 598,939 29,338 48,865 54,277 58,448 54,531 47,817 54,487 49,818 43,112 Silver produced (ozs) ounces 846,780 51,450 67,774 68,375 83,310 85,300 70,465 76,045 66,625 54,200
Revenue (net of refining) US$ 849,088,606 41,760,769 69,251,505 76,804,266 82,870,375 77,444,895 67,836,735 77,227,101 70,560,392 61,002,941 Opex US$ (391,620,486) (24,798,781) (36,247,543) (39,831,170) (40,016,749) (34,589,723) (28,758,672) (32,310,055) (29,933,224) (26,755,887) Royalties US$ (78,116,152) (3,841,991) (6,371,138) (7,065,993) (7,624,075) (7,124,930) (6,240,980) (7,104,893) (6,491,556) (5,612,271) Sustaining Capital US$ (59,546,192) (13,276,174) (15,170,406) (9,448,862) (7,303,250) (4,526,700) (617,550) (742,950) (463,550) (463,550) Working capital adjustments US$ ‐ (2,037,295) (646,058) (598,695) (262,565) (251,342) 584,058 (479,916) 352,593 532,084 Pre‐tax Cashflow US$ 319,805,777 (2,193,471) 10,816,361 19,859,547 27,663,737 30,952,201 32,803,591 36,589,286 34,024,655 28,703,317
AISC US$/oz 866
MDZTonnes milled tonnes 14,555,946 ‐ ‐ ‐ 209,014 1,310,667 1,461,570 1,460,649 1,461,122 1,465,178 Head grade (g/t Au) g/t 2.85 ‐ ‐ ‐ 6.05 12.63 3.27 3.41 2.94 2.77 Contained gold (ozs) ounces 1,332,795 ‐ ‐ ‐ 20,831 132,913 153,659 160,137 138,110 130,485 Gold Recovery % 10 ‐ ‐ ‐ 95% 95% 95% 95% 95% 95% Gold produced (ozs) ounces 1,266,155 ‐ ‐ ‐ 19,789 126,268 145,976 152,130 131,204 123,961 Silver produced (ozs) ounces 719,609 ‐ ‐ ‐ 12,509 74,608 84,019 91,104 85,309 76,124
Revenue (net of refining) US$ 1,776,772,632 ‐ ‐ ‐ 27,791,633 177,237,280 204,863,671 213,560,206 184,299,357 174,048,543 Opex US$ (831,172,697) ‐ ‐ ‐ (25,988,296) (82,587,852) (83,444,458) (82,447,740) (82,834,207) (83,068,605) Royalties US$ (163,463,082) ‐ ‐ ‐ (2,556,830) (16,305,830) (18,847,458) (19,647,539) (16,955,541) (16,012,466) Initial Capital US$ (269,394,005) (1,087,625) (109,116,079) (112,024,363) (47,165,937) ‐ ‐ ‐ ‐ ‐ Sustaining Capital US$ (131,299,895) ‐ ‐ ‐ (19,492,087) (13,352,799) (8,471,341) (9,434,155) (25,219,945) (10,025,079) Working capital adjustments US$ ‐ ‐ ‐ ‐ (2,561,975) (6,866,359) (551,328) (796,706) 2,436,766 882,229 Pre‐tax Cashflow US$ 381,442,953 (1,087,625) (109,116,079) (112,024,363) (69,973,493) 58,124,440 93,549,086 101,234,066 61,726,430 65,824,623
AISC US$/oz 886
Combined
Tonnes milled tonnes 19,700,609 286,171 437,485 490,050 734,015 1,802,201 1,850,108 1,912,679 1,870,718 1,817,042 Head grade (g/t Au) g/t 3.19 3.66 3.99 3.95 3.72 3.37 3.51 3.62 3.25 3.08 Contained gold (ozs) ounces 2,020,134 33,668 56,077 62,288 87,905 195,492 208,534 222,666 195,281 179,960 Gold Recovery % 13 87% 87% 87% 89% 92% 93% 93% 93% 93%Gold produced (ozs) ounces 1,865,094 29,338 48,865 54,277 78,237 180,798 193,793 206,617 181,023 167,073 Silver produced (ozs) ounces 1,566,389 51,450 67,774 68,375 95,819 159,908 154,484 167,150 151,934 130,324
Cash cost/oz US$/ozAISC/oz US$/oz
Revenue (net of refining) US$ 2,625,861,238 41,760,769 69,251,505 76,804,266 110,662,008 254,682,175 272,700,406 290,787,307 254,859,749 235,051,483 Opex US$ (1,222,793,183) (24,798,781) (36,247,543) (39,831,170) (66,005,045) (117,177,575) (112,203,130) (114,757,795) (112,767,430) (109,824,492) Royalties US$ (241,579,234) (3,841,991) (6,371,138) (7,065,993) (10,180,905) (23,430,760) (25,088,437) (26,752,432) (23,447,097) (21,624,736) Income taxes paid US$ (210,374,619) ‐ (3,803,295) (7,420,753) (8,009,594) (4,963,110) (23,972,210) (30,063,723) (33,951,529) (24,456,658)
Period Start 1‐Jan‐20 1‐Jan‐21 1‐Jan‐22 1‐Jan‐23 1‐Jan‐24 1‐Jan‐25 1‐Jan‐26 1‐Jan‐27 1‐Jan‐28Period End 31‐Dec‐19 31‐Dec‐20 31‐Dec‐21 31‐Dec‐22 31‐Dec‐23 31‐Dec‐24 31‐Dec‐25 31‐Dec‐26 31‐Dec‐27 31‐Dec‐28
TotalWorking capital adjustments US$ ‐ (2,037,295) (646,058) (598,695) (2,824,539) (7,117,701) 32,730 (1,276,622) 2,789,358 1,414,313 Operating cash flow US$ 951,114,202 11,082,703 22,183,472 21,887,657 23,641,924 101,993,029 111,469,359 117,936,734 87,483,052 80,559,910 Sustaining Capital US$ (190,846,086) (13,276,174) (15,170,406) (9,448,862) (26,795,337) (17,879,499) (9,088,891) (10,177,105) (25,683,495) (10,488,629) Free cash flow US$ 760,268,116 (2,193,471) 7,013,066 12,438,795 (3,153,413) 84,113,531 102,380,468 107,759,629 61,799,556 70,071,282
495,563,815 Expansion capex US$ (269,394,005) (1,087,625) (109,116,079) (112,024,363) (47,165,937) ‐ ‐ ‐ ‐ ‐
Project cash flow US$ 490,874,111 (3,281,096) (102,103,013) (99,585,569) (50,319,350) 84,113,531 102,380,468 107,759,629 61,799,556 70,071,282
Project NPV @ 5% US$ 256,075,253
Project IRR % 19.5%
Cash Cost per Ounce US$/oz 777 953 855 849 959 769 701 678 745 780 AISC US$/oz 880 1,405 1,165 1,023 1,302 868 748 727 886 843
Period StartPeriod End
Gold Price US$/ozSilver Price US$/oz
Upper ZoneTonnes milled tonnesHead grade (g/t Au) g/tContained gold (ozs) ouncesGold Recovery %Gold produced (ozs) ouncesSilver produced (ozs) ounces
Revenue (net of refining) US$Opex US$Royalties US$Sustaining Capital US$Working capital adjustments US$Pre‐tax Cashflow US$
AISC US$/oz
MDZTonnes milled tonnesHead grade (g/t Au) g/tContained gold (ozs) ouncesGold Recovery %Gold produced (ozs) ouncesSilver produced (ozs) ounces
Revenue (net of refining) US$Opex US$Royalties US$Initial Capital US$Sustaining Capital US$Working capital adjustments US$Pre‐tax Cashflow US$
AISC US$/oz
Combined
Tonnes milled tonnesHead grade (g/t Au) g/tContained gold (ozs) ouncesGold Recovery %Gold produced (ozs) ouncesSilver produced (ozs) ounces
Cash cost/oz US$/ozAISC/oz US$/oz
Revenue (net of refining) US$Opex US$Royalties US$Income taxes paid US$
1‐Jan‐29 1‐Jan‐30 1‐Jan‐31 1‐Jan‐32 1‐Jan‐33 1‐Jan‐3431‐Dec‐29 31‐Dec‐30 31‐Dec‐31 31‐Dec‐32 31‐Dec‐33 31‐Dec‐34
24 25 26 27 28 291 1 1 1 1 1
1,400 1,400 1,400 1,400 1,400 1,400 17.00 17.00 17.00 17.00 17.00 17.00
386,605 388,892 445,184 91,713 ‐ ‐ 4.30 4.18 4.43 4.22 ‐ ‐
53,418 52,299 63,442 12,443 ‐ ‐ 87% 87% 87% 87% 0% 0%
46,548 45,573 55,282 10,843 ‐ ‐ 59,176 59,945 82,869 21,244 ‐ ‐
65,876,165 64,529,962 78,451,441 15,472,058 ‐ ‐ (28,549,711) (28,657,425) (30,512,417) (10,659,130) ‐ ‐ (6,060,607) (5,936,757) (7,217,533) (1,423,429) ‐ ‐ (463,550) (463,550) (463,550) (6,142,550) ‐ ‐ (260,792) 119,500 (991,766) 3,940,194 ‐ ‐
30,541,505 29,591,730 39,266,176 1,187,143 ‐ ‐
1,461,099 1,460,382 1,460,041 1,463,850 1,342,374 ‐ 2.47 2.33 2.50 2.79 2.84 ‐
116,029 109,399 117,354 131,308 122,570 ‐ 95% 95% 95% 95% 95% ‐
110,228 103,929 111,486 124,743 116,441 ‐ 53,928 58,409 56,517 60,618 66,464 ‐
154,532,483 145,830,586 156,329,699 174,874,555 163,404,620 ‐ (81,760,362) (82,536,536) (81,375,837) (78,072,993) (67,055,810) ‐ (14,216,988) (13,416,414) (14,382,332) (16,088,459) (15,033,225) ‐
‐ ‐ ‐ ‐ ‐ ‐ (18,779,831) (10,052,664) (11,679,257) (1,512,011) (3,280,726) ‐ 1,476,102 779,020 (958,341) (1,773,963) 7,934,554 ‐
41,251,403 40,603,991 47,933,932 77,427,129 85,969,414 ‐
1,847,704 1,849,274 1,905,225 1,555,563 1,342,374 ‐ 2.85 2.72 2.95 2.87 2.84 ‐
169,447 161,698 180,795 143,751 122,570 ‐ 93% 92% 92% 94% 95% 0%
156,776 149,502 166,768 135,586 116,441 ‐ 113,104 118,354 139,387 81,863 66,464 ‐
220,408,648 210,360,548 234,781,140 190,346,613 163,404,620 ‐ (110,310,074) (111,193,962) (111,888,253) (88,732,123) (67,055,810) ‐ (20,277,596) (19,353,170) (21,599,865) (17,511,888) (15,033,225) ‐ (19,173,263) (14,724,222) (11,421,910) (18,011,461) (9,571,242) (831,650)
Period StartPeriod End
Working capital adjustments US$Operating cash flow US$Sustaining Capital US$Free cash flow US$
Expansion capex US$
Project cash flow US$
Project NPV @ 5% US$
Project IRR %
Cash Cost per Ounce US$/ozAISC US$/oz
1‐Jan‐29 1‐Jan‐30 1‐Jan‐31 1‐Jan‐32 1‐Jan‐33 1‐Jan‐3431‐Dec‐29 31‐Dec‐30 31‐Dec‐31 31‐Dec‐32 31‐Dec‐33 31‐Dec‐34
1,215,310 898,520 (1,950,107) 2,166,231 7,934,554 ‐ 71,863,025 65,987,713 87,921,005 68,257,372 79,678,898 (831,650) (19,243,381) (10,516,214) (12,142,807) (7,654,561) (3,280,726) ‐ 52,619,644 55,471,500 75,778,198 60,602,811 76,398,172 (831,650)
‐ ‐ ‐ ‐ ‐ ‐
52,619,644 55,471,500 75,778,198 60,602,811 76,398,172 (831,650)
827 866 793 780 702 ‐ 950 936 865 836 730 ‐