Infrastructures Assessment for Solid Waste Fund, Water ...

266
Infrastructures Assessment for Solid Waste Fund, Water Supply and Sewage Institutions in Aden City September 2019 By: Dr. Eng. Mohammed Almughalles Environmental Expert

Transcript of Infrastructures Assessment for Solid Waste Fund, Water ...

Infrastructures Assessment for Solid

Waste Fund, Water Supply and Sewage

Institutions in Aden City

September 2019

By:

Dr. Eng. Mohammed Almughalles

Environmental Expert

- 1 -

- 2 -

Table of Contents

1. Introduction .................................................................................................. - 6 -

2. Methodology ................................................................................................ - 7 -

2.1. Gathering information ........................................................................................................ - 7 -

2.2. Analysing ......................................................................................................................... - 10 -

2.3. Approved projects ............................................................................................................ - 12 -

3. Cleaning Fund ........................................................................................... - 13 -

3.1. Introduction ...................................................................................................................... - 13 -

3.2. Organizational Structure of the CF .................................................................................. - 14 -

3.3. Current Situation and Required Intervention ................................................................... - 15 -

3.4. Main Headquarter ............................................................................................................ - 18 -

3.5. Training and Environment Awareness Centers. ............................................................... - 20 -

3.6. Cleaning Administrations in the Directorates .................................................................. - 21 -

3.7. Al-Mansoora Transfer Station ......................................................................................... - 32 -

3.8. Al-Hiswa Temporary Dump Site ..................................................................................... - 37 -

3.9. The Dump Site ................................................................................................................. - 39 -

3.10. Administration of Afforestation and Public Parks ........................................................... - 44 -

3.11. Administration of Sand and Construction Waste ............................................................. - 47 -

3.12. Maintenance Workshops .................................................................................................. - 48 -

3.13. Capacity Building ............................................................................................................ - 54 -

3.14. Recommendations ............................................................................................................ - 57 -

4. Public Corporation of Water and Sewage ............................................. - 58 -

4.1. Headquarters .................................................................................................................... - 60 -

4.2. Administration Buildings ................................................................................................. - 62 -

4.3. Maintenance Workshops .................................................................................................. - 62 -

4.4. Occupational Safety Management ................................................................................... - 65 -

5. Water System ............................................................................................. - 66 -

5.1. Wellfields ......................................................................................................................... - 66 -

5.2. Reservoirs ........................................................................................................................ - 70 -

5.3. Water Supply Network..................................................................................................... - 73 -

5.4. Central Laboratory ........................................................................................................... - 75 -

- 3 -

5.5. Disinfection Units ............................................................................................................ - 77 -

5.6. Water Pumping Stations................................................................................................... - 78 -

5.7. Operation and Maintenance Materials ............................................................................. - 79 -

6. Sanitation System ..................................................................................... - 80 -

6.1. Sewer Network's pipes ..................................................................................................... - 82 -

6.2. Manholes .......................................................................................................................... - 90 -

6.3. Pumping Stations ............................................................................................................. - 91 -

6.4. Treatment Plants ................................................................................................................. 104

6.5. Operation and Maintenance Materials ................................................................................ 112

7. Urgent Interventions for Cleaning Fund ................................................ 114

8. Urgent Intervention for Water Supply System ...................................... 160

9. Urgent Intervention for Sanitation System ............................................ 193

10. Summary of Total Cost for Aden's Intervention ................................... 215

- 4 -

Executive Summary

This assessment study aims to illustrate the severity of damage and destruction caused to the assets and infrastructure of the Cleaning Fund (CF) and the Public Corporation of Water and Sewage (PCWS) in Aden during the conflict period which started in 2015. In addition, the study provides the required interventions and the most urgent needs for both corporations.

Regarding the CF, most of the damage occurred to the vehicles and equipment. About 60% of the CF's equipment and assets were permanently destroyed, while the remainder 40% were left in very poor conditions. The transfer station and the dump sites require rehabilitation works and more vehicles to become able to restore their total abilities. Moreover, the maintenance workshops need rehabilitation works and lack many equipment, tools and spare parts. Besides that, buildings of the administrations in directorates need to be rehabilitated.

Therefore, the current priorities for CF are to supply new garbage containers, garbage collecting vehicles, dumpsite's vehicles (bulldozer and compactor) and mobile maintenance workshops. Furthermore, rehabilitation interventions for the buildings in directorates, maintenance workshops, transfer station and dumpsite are considered as high priorities for the CF.

In regard to the PCWS, old office buildings in the wellfields, headquarter, pumping stations and some other facilities of PCWS have been partially damaged. About forty well bores, three reservoirs, the central laboratory, the three disinfection units, and 2 main transmission pipelines in Bir Nasser wellfield have all been worn-out or partially destroyed. The sewage pumping stations were also damaged. Al-Arish, Kubota and Salah Al-Dain wastewater treatment plants with their office buildings and laboratories have been partially damaged. In addition, operation and maintenance equipment, tools, and vehicles, spare parts and occupational health and safety tools were damaged and looted.

Consequently, rehabilitating the wellfields and supplying suitable pumps to increase the wells' yield, conducting maintenance interventions for reservoirs, carrying out complete rehabilitation for sewage pumping stations, constructing new office buildings, renovating the wastewater treatment plants and supplying required O&M tools and equipment are the main priorities for the PCWS currently.

Besides the direct damages, the CF and PCWS faced indirect damages mostly through the electricity cuts, economic crisis, and rising prices leading to financial constraints.

Although some of the damaged facilities and infrastructure of both institutions have already been rehabilitated with support from the humanitarian organizations, such as UNOPS, Mercy Corps, UNICEF, Arab Fund, etc., there is still an urgent necessity for many interventions and projects to be done in order to aid these two local corporations to continue serving the local citizens in Aden city.

- 5 -

Based on the findings of the assessment study, UNDP requirements, the available fund and the coordination with stakeholders and other humanitarian organizations, the following interventions were chosen as the most urgent projects.

Summary of Total Cost for Aden's Interventions 1 Cleaning Fund 1.1 Rehabilitation Interventions 1.1.1 Rehabilitate the buildings and facilities in Bair Na’ama’s dump 3,329 1.1.2 Rehabilitate Khormaksar and Al-Mansoora Maintenance Workshops 15,609.5 1.1.3 Rehabilitate administration office buildings in directorates 111,363.18 Sub-Total 130,301.68 1.2 Supporting Assets and Supplying Vehicles Intervention 1.2.1 Supply Required Vehicles and Containers for Cleaning Administrations in Directorates 830,000 1.2.2 Supply Required vehicles for Bir Na'ama Dumpsite 740,000 1.2.3 Supply Mobile Maintenance Workshops 220,000 Sub-Total 1,790,000 Total Cost of Cleaning Fund's Interventions 1,920,301.68 2 Public Corporation of Water and Sewage 2.1 Rehabilitation Interventions 2.1.1 Replace the western north pipeline in Bir Nasser wellfield 387,714 2.1.2 Rehabilitate buildings 183,776.6 2.1.3 Rehabilitate Fuqum mountain reservoirs No.2 (4,500 m3) 103,005 2.1.4 Rehabilitate sewage pumping stations 561,838 Sub-Total 1,236,333.6 2.2 Supporting Assets and Supplying Vehicles Intervention 2.2.1 Supply and install submersible pumps for wells 250,000 2.2.2 Supply vehicles, O&M tools and spare parts 370,834 2.2.3 Supply OHS equipment, tools and spare parts 136,825 Sub-Total 757,659 Total Cost of PCWS's Interventions 1,993,992.6 Total Cost of All Interventions 3,914,294.28

- 6 -

1. Introduction

The city of Aden is one of the most important and vital cities in the republic of Yemen. Located in the furthest southwestern part of the country, the city is considered as one of the most beautiful touristic attraction in the region. Previously, the city was widely known for its beauty, cleanliness and the high level of services in the development sector compared to the rest of the governorates in the country. The cleaning fund (CF) as well as the public corporation of water and sewage (PCWS) played a significant role in raising the urbane level the city has attained. Unfortunately, the crisis which started in 2011 along with the armed conflict the city witnessed in 2015 caused massive destruction and damage to a lot of the city's assets and infrastructure. Needless to say, the CF and the PCWS were among the most affected government agencies, which sustained severe damage and destruction in their assets and infrastructure.

The acts of destruction and damage to which these two agencies were subjected, contributed largely to the decline in the level of hygiene, cleanliness and water and sewer services in the city. Consequently, problems such as accumulation of waste around the city's streets and neighborhoods, severe shortage in water services in several areas, overflow of sanity sewer and the discharge of sewage into the see without any treatment started to emerge. All these problems caused many diseases and illnesses to breakout as well as pollution of the environment which left the city in a catastrophic condition.

In response to this catastrophe, several humanitarian organizations leapt to offer a helping hand in a rapid and urgent manner in order to save the city from this situation. Most of the aid provided focused on the field of wash, in which the CF and the PCWS received many aid projects. The efforts are still in progress regarding supporting these two agencies in order to enable them to substitute for the assets they lost and to rehabilitate their damaged infrastructure thus allowing these two agencies to regain the roles they played before the crisis. The following chapters in the study explain the current condition of the CF's and the PCWS's infrastructure and the projects needed in order to rehabilitate their infrastructure.

- 7 -

2. Methodology

This part demonstrates the followed procedures during the infrastructure assessment for solid waste fund, water supply and sewage institutions in Aden city. It aims to sum up the carried-out steps for gathering information, analyzing data and shortlisting the required interventions. It also contains some of the main observations and initial findings that were taken while collecting and analyzing information. Furthermore, it includes the remaining work tasks that will be taken to finalize the assessment study.

2.1. Gathering information

Preparing: as a first step, the assessment began with a desk research which included an overlook of the project's documents and existing reports and data concerning the infrastructure and assets capacities of CF and PCWS. By the end of the desk review, a work plan was designed illustrating the methodology that would be followed to implement the assessment. Along with designing the work plan, surveys and questionnaires targeting local communities, beneficiaries, senior managers and technical staff in CF and PCWS were formulated1.

Field Work: the field work started by preliminary meetings with administrations of CF and PCWS discussing the work plan and surveys prepared by the consultant, reviewing the current condition of both institutions, existing challenges and requirements and planning the timeline of consultant's field visits. By the end of these meetings, the consultant was given a long list drafts containing the requirements and needs of both institutions.

The preliminary meeting with the administration of the CF attended by

- CEO of the CF (Eng. Qa’ed Rashed Ana’am)

- Deputy GM of cleaning and hygiene affairs (Eng. Farooq Mohammed Zaid)

- Chief of studies and design department (Eng. Mohammed Handhal)

- Int’l and local organizations coordinator at the CF (Waleed Alhakimi)

1 Surveys and questionnaires are attached in Appendix (8)

- 8 -

Preliminary meeting with the administration of the PCWS, attended by

- GM of PCWS (Eng. Alawi Al-Mehdhar)

- Deputy GM of sanitation department (Eng. Zaki Al-Haddad)

- Consultant of GM for technical affairs (Eng. Kamel Alhamami)

- Chief of projects’ management (Eng. Hamdan Al-Hakami)

- Chief of coordination with the organizations (Eng. Angela Abdulrahman)

After conducting the preliminary meetings, the consultant with his team initiated the field visits and survey activities.

i. Cleaning Fund

For the sake of assessing the infrastructure of the CF, almost all administrations and facilities within CF were visited. The current situation and requirements of each administration/facility were considered during the field visits. A quick brief of the main observations taken during field visits can be illustrated as:

As a result of the conflict the country witnessed, Aden became the political capital of the country which resulted in the increase of population, consequently causing larger amounts of waste to be produced by the city of Aden to the point where the amounts of waste produced surpasses current capacity and capability of the CF.

Low earnings obtained by the CF currently has created a lot of financial difficulties and challenges, which prevented the CF from carrying out many of its activities.

A large number of the equipment and machines formerly owned by the CF were subjected to acts of robbery and destruction due to the conflict the city witnessed. Nearly 60% of the CF’s equipment and machines were damaged as a result of military operations during the conflict period.

- 9 -

The CF arranged for a makeshift transfer dump site in Al-Hiswa, Al-Mansoora to replace the transfer station in Al-Mansoora which stopped working because of infrastructure damage and loss of trailers which were used for transportation of waste to the dump site. Due to the shortage in equipment and machines at the temporary dump site, waste started to pile up and accumulate posing serious threats to the environment and general health. Moreover, the proximity of Al-Hiswa natural preserve to the temporary dump site, made things significantly worse.

Administration of afforestation and public parks’ incapability to oversee and monitor watering and irrigation of nurseries and parks caused trees in public parks and nurseries to die. In addition, the conflict in the city contributed to the destruction of a number of intersections, water fountains and corniches.

As a result of the theft and robbery to which the dump site was subjected, disposing of solid waste brought in from all directorates became very difficult.

The CF’s maintenance workshops were also robbed and lost many of the equipment and tools which were used to repair and maintain equipment and machines owned by the CF.

Exhaustion and fatigue to which a number of the CF’s machines and equipment were subjected and which the CF was incapable to repair because of its inability to provide spare parts.

ii.Water Supply System

The consultant with the help of his team visited the wellfields, main pumping stations, reservoirs, elevated tanks, workshops, central lab and disinfection units. Main observations taken during field visits are outlined as:

Number of bore wells stopped due to the malfunction of their pumps leading to reduce in the water production capacity.

The Water Central Laboratory and its equipment, including the chemical and bacteriological analysis devices, were damaged and looted.

All disinfection facilities were also destroyed causing a real threat from spreading water related diseases.

Due to illegal connections and leakages from worn out parts of the transmission and distribution, PCWS lost large amount of water and money.

The corporation’s inability to make up for the losses of operation and maintenance equipment.

- 10 -

iii. Sanitation System

The field visits covered main treatment plants, laboratories, main and sub pumping stations, main manholes and maintenance workshops. From the field visits and surveys the following were observed:

Clogging and eroding parts of the main and lateral sewer network (pipelines and manholes) leading to sewer overflows in some areas.

Some pumping station are out of service causing more burden on still operating stations.

Efficiency of WWTPs is under accepted limits, which means the sea is being contaminated by sewerage of Aden city.

Severe damage sustained by the corporation’s laboratories.

Immense losses in operation and maintenance equipment which rendered the corporation unable to carry out its tasks.

Finalizing: all collected information during meetings, interviews, field visits, and survey activities were classified and rearranged to be ready for analysing.

2.2. Analysing

Initial Findings: by analyzing the observations and gathered information during field visits, interviews and survey activities. The following main initial findings were concluded:

Necessity of providing the minimum number of containers and vehicles which commensurate with the amount of solid waste generated in Aden city to prevent wastes pilling up causing the spread of diseases.

Rehabilitation of Al-Mansoora transfer station should be considered as a high priority intervention, since rehabilitation of the station will lead to a number of positive results.

While the CF is suffering from financial difficulties, rehabilitation of the recycling hangar in the dumpsite can assist the CF in generating revenue which can be used in funding other activities.

The amount of water production from wellfields (well yield) can be increased by replacing the malfunctioning pumps in the wells.

Rehabilitation of the water supply network will reduce the loss caused by leakages in the dilapidated network.

- 11 -

Rehabilitation of the disinfection units and the central lab should be considered as a high priority project due to the impact of this project on reducing the infection of water related diseases.

Importance of rehabilitating the worn-out sewer network especially in the areas facing frequent sewer overflows, giving that sewer overflow is one of the main reasons of spreading waste water related diseases.

Supplying the PCWS with the appropriate tools and equipment for unclogging manholes should be considered as a priority.

Rehabilitation of the pumping stations will reduce the overflows of sanitation network in Aden city.

Rehabilitation of the WWTPs should be given a high priority since currently the sewerage is conveyed directly to the sea causing a contamination problem.

Classifying: second step was classifying the requirements and needs of CF and PCWS into sub-projects. The CF's required interventions were sorted into 9 modules (Cleaning Fund Headquarter, Cleaning Fund Administrations in Directorates, Transfer Stations, Dumpsite, Maintenance Workshops, Afforestation and Parks Administration, Sand and Construction Waste Management, Capacity Building and Environmental Awareness Center). Whereas water supply system required interventions that were sorted into 7 modules (Wellfields, Reservoirs and Tanks, Water Network, Pump Stations, Central Laboratory, Disinfection Units and O&M Materials). However, the sanitation system necessary requirements were classified into 6 modules (Wastewater Network, Manholes, Pump Stations, WWTP, O&M Materials and Maintenance Workshops). Then, each module was classified into sub-projects based on the requirements for each module.

Shortlisting: sub-projects were rated as urgent, medium priority, low priority. Along with considering the initial findings mentioned above, the main criteria considered while rating sub-projects were as follows:

Impact of sub-project on reducing solid waste related diseases.

No. of beneficiaries.

Necessity of sub-project to local community.

Impact of sub-project on rising and improving the overall performance of CF & PCWS.

Expected Sustainability of the sub-project.

Impact of sub-project on reducing the expenditures of CF & PCWS

Impact of sub-project on the social and economic situation and peace building efforts.

- 12 -

Before submitting the shortlist to PWP and UNDP, a second meeting with administrations of CFs and PCWS was conducted to discuss and approve the shortlist (urgent) sub-projects.

The shortlist should be approved by PWP and UNDP taking into account the budget limits and available funds.

2.3. Approved projects

Project concepts will be conducted for the sub-projects that will be approved by stakeholders and UNDP. Project concepts will include the following for each approved intervention:

- Project title

- Project location

- Project rational

- Estimated budget (BoQ)

- Implementation duration

- Expected impact of intervention, potential risks, and beneficiaries

- 13 -

3. Cleaning Fund

3.1. Introduction

Since the establishment of the Cleaning Fund in 1999 under cleanliness law number 20, the CF has carried out many environmental and health-oriented activities and practices that presented the city in a light fitting with its political, economic and historical status. According to the cleanliness law, the CF is considered to be financially and directorially independent, where activities and practices carried out by the CF are financed by fees mandated by the CF. These fees are explained as follows: - Cleaning fees obtained from stores and other facilities. - Development fees obtained as a rate for services offered by the CF. - Revenues made from advertisement billboards spread around the city. - Specified amounts from the national budget. - Donations and offers from international and local associates.

By the same law, the following responsibilities are placed upon the CF:

- Daily collection of residential trash and waste from streets and neighborhoods around the city followed by transportation of waste to a lawful place (normally outside the city).

- Final disposal of waste in a proper way so as to prevent pollution and damage to the environment of the city.

- Emphasis on the importance of carrying out cleaning services by adopting modern ways and technologies that aim to preserve health and safety of the city and prevent environmental pollution.

- Afforestation and tree-planting activities on the side of roads and on median strips and organizational irrigation of these plants in order to preserve their greenness.

- Periodic maintenance for locations heavily populated with trees and plants through trimming of trees, painting and cleaning of tree basins and application (Spraying) of pesticides on trees and plants in order to get rid of harmful insects.

- Construction of aesthetic sites and architectural structures that are representative of the city and its history.

- Rehabilitation and maintenance of historical statues and sites and prevention of their removal. - Studies and designs for future development and betterment projects. - Following up and obtaining of fees and revenues as described in the cleanliness law and ensuring

procurement of these income resources as to become able to finance activities and works carried out by the CF.

- 14 -

3.2. Organizational Structure of the CF

The CF is divided into a number of administrations such that each administration is assigned with certain responsibilities as shown in the structure below

The CF is run by a board of directors and is considered as the highest authority for the CF. It is led by the governor of the governorate in which the CF is located and has full authority to observe, direct, make up policies and decide on programs and plans corresponding with the purposes for which the CF was founded.

The CF is headed by a Chief Executive Officer (CEO) whose responsibilities include management and leadership of operations carried out by all administrations and departments at the CF. There are three deputies for the CEO and are assigned based on duties and responsibilities as follows:

Deputy Director of Administrative and Financial Affairs: responsible for management of financial and administrative affairs and aspects of the CF.

Deputy General Manager of Hygiene Affairs: responsible for following up on daily cleaning activities, performance levels, amounts of transported waste to the dump site – located in Bair Na'ama, Al-Boraiqa. Additionally, is supervisor of Heads of Hygiene Departments in the directorates.

Deputy General Manager of Technical Affairs: responsible for all technical activities and follow-up of maintenance workshops and supervision of daily monitoring activities of the condition of the cleaning processes in the city and reporting technical needs and necessities that would ensure continuous technical maintenance of machines and equipment.

Aden Governor

CEO

Administration and Financial

Affairs Legal Affairs Procurements

Cleaning Affairs Technical Affairs

Cleaning Administrations

Dump Sites

M&E

EAC

Transporting

Advertising

Maintenance Workshops

Khormaksar Maintenance Workshop

Al-Mansoora Maintenance Workshop

Dar Sa'ad Maintenance Workshop

Revenue

Reviewing

Monitoring

Parks & Afforestation

Employees Affairs

Accounting

Purchase

Stores

- 15 -

3.3. Current Situation and Required Intervention:

Ever since the establishment in 1999, the Cleaning Fund has invested massive efforts in improving cleanliness levels and standards in the city, a mission accomplished by overcoming struggles and challenges the CF faced, resulting in a number of consecutive achievements. In addition, during the period from 1999 to 2010, the CF succeeded in gaining a fleet of vehicles and equipment enabled it to perform cleaning activities effectively and professionally.

In 2009, Ade city won first place in the environmental contest held by the Environmental Protection Agency, which included aspects of cleanliness and afforestation. However, since the beginning of the political crisis in 2011, which affected the progress of the CF negatively, evident through receding levels of cleanliness. Moreover, and due to robbery and vandalism of CF-owned assets and equipment, the CF was rendered incapable of removing waste off streets and neighborhoods around the city, causing waste to pile in large amounts and for long periods of time which resulted in the spread of dangerous diseases and having citizens resort to burning these wastes in order to get rid of them.

- 16 -

The situation in Aden continued to deteriorate reaching its worst during the armed conflict which took place in 2015, which added additional burdens and difficulties causing the CF's infrastructure to worsen significantly. About 60% of the CF's assets and equipment were permanently lost, while the remainder 40% were left in very poor conditions to the point where previous cleaning and waste-collecting activities have dropped massively causing waste and sand to pile up around the city in an undesirable manner. These piled up wastes which increased quickly started to pose serious danger to the health of citizens and environment alike. Luckily enough, the CF in cooperation with influential local and international organizations formed rapid interventions which contributed to alleviation of the threats caused by these diseases and reducing the magnitude of catastrophes that would have otherwise ensued such as the cholera outbreak. In addition, the CF's income was seriously affected due to these conflicts, where services normally carried out by the CF have largely dropped because of its incapability to manage between its limited operating costs and hygiene related duties. With that said, the CF was faced with many difficulties and challenges surmised in the following points:

1- Incapability of CF's machines and equipment to remove waste accumulated in large amounts estimated at (750 tons/day) and which is expected to grow because of the increase in the population the city witnessed as a result of displacements of large numbers of people because of the conflict as well as the raise in the number of diplomatic delegations accompanied with the reassignment of Aden as the country's capital city. All these factors made it very challenging to remove waste off the streets causing the problem of accumulated waste to grow largely especially given the CF's loss of more than 60% of its assets and equipment because of the conflict. With that said, it has become rather urgent that the CF

- 17 -

receives the necessary funds and support it can use to obtain new equipment instead of the current renting policy it carries which is very costly.

2- Significant increase in the amounts of construction waste around the city's streets and neighbourhoods which is roughly estimated to be about (2,470,000 cubic meters) according to the latest statistics carried out by the CF's administration of sand and construction waste.

3- The CF's inability to afford large daily rental costs of machines and equipment. 4- Shortage in the CF's financial resources which renders it unable to afford costs of operations carried

out in high levels. 5- The CF's inability to steadily secure cleaning workers' salaries, which are estimated to be around (3900

employees) due to lack in financial resources.

However, and in light of all these difficulties and challenging times, the CF, and to its best ability manages to perform periodic cleaning campaigns aimed at cleaning the streets and neighborhoods of the country's temporary capital, Aden.

Unfortunately, these cleaning campaigns are temporary solutions that come at very great costs. Therefore, permanent and constant solutions to the cleaning and hygiene issue in Aden need to be made. These solutions are best simplified in the providing and supplementation of machines and equipment that can cover the amounts of waste produced by the city of Aden.

Following is a detailed study of the current condition of the CF's infrastructure and needs that must be provided for the CF to be able to carry out its duties to the required levels of efficiency.

- 18 -

3.4. Main Headquarter

The CF's headquarters main building is located in Khormaksar directorate. It is a one-storey building located on one of the lands owned by the CF and it holds many of the administrative offices as well as the hall used for conferences and meetings. In addition, CF is planning to use this hall as a training centre. Although the building is in an excellent condition where no rehabilitation works are required, there is a space problem in regard to administrative offices that is serious enough to the point where multiple administrations are located within one office. Therefore, there is a need for building an additional floor which should allow for more office space that could solve the current problem.

- 19 -

Additionally, a number of these administrations are in need for certain office-related equipment and necessities, which are shown in the table below.

Administrations within Headquarter Building

Qty Required Equipment Qty Available Equipment No. of Female Employees

No. of Male Employees

Administration NO.

1 Desktop computer 1 Desktop computer 3 4

Procuring and Tendering

1 1 Colourful EPSON printer (A3) 1 Old Printer 1 Air conditioner 2 Desktop computer

2 1 Statistics 2 2 Printer 1 Desktop computer

2 3 Legal Affairs 3 1 EPSON printer (A4) 1 Photocopier 1 Desktop computer

2 3 Advertising 4 1 EPSON printer (A4) 1 Photocopier 1 Printer (A3 or A1) 1 Desktop computer

1 3 Studies 5 1 Printer (A4) 1 Printer (A1) 1 Desktop computer

4 Parks and Afforestation

6 1 Printer (A4) 1 Colourful EPSON printer (A3) 2 Desktop computer

3 6 Employees Affairs

7 1 Photocopier 1 Printer (A4) 1 Desktop computer

5 Cornices 8 1 Printer (A4) 1 Photocopier 6 Desktop computer

3 6 Accounting and Expenses

9 1 Printer (A4)

2 Desktop computer 15 Revenue 10 1 Photocopier

1 Printer (A4) 1 Desktop computer

3 2 Public Relation 11 2 Printer (A4)

2 Desktop computer 3 11 Markets 12

1 Printer (A4) 2 Desktop computer

9 7 Monitoring

and Collection 13 2 Printer (A4)

1 Photocopier

- 20 -

3.5. Training and Environment Awareness Centers.

Despite specifying a hall as training center, the center does not own enough equipment or tools which enable training sessions to be carried out. In addition, CF has an environment awareness center, which requires the suitable equipment to conduct awareness campaigns effectively.

For both centers to be able to carry out their duties, the following equipment and tools are required.

Environmental Awareness Centers Qty Required Equipment NO Qty Required Equipment No

1 Computer station with full options 11 1 Digital Camera video 1 1 Compact DVCAM Video Recorder 12 2 External Microphone 2 1 DVD Recorder Recording 13 1 Rechargeable Battery 3 1 Portable Recorder DSR 14 1 Battery Light Kit 4 1 Mini DV Camcorder 15 1 AC Adaptor/ Charger 5 1 Data show Projector 16 1 Portable Diversity Tuner 6 1 Laptop 17 1 Carrying Case for Camera 7 1 LCD 40'' 18 1 Tripod for Camera 8 1 Car 19 20 Digital Mini cassette Tape 9 1 Advertising Screen 20 3 UHF Synthesized Wireless Microphone 10

Training Centers Qty Required Equipment NO Qty Required Equipment No

1 Data show projector 4 2 Microphones 1 1 Printer (A4) 5 4 Speakers 2 1 LCD (42 inches) 6 1 Desktop computer 3

- 21 -

3.6. Cleaning Administrations in the Directorates

Because of the recent urban sprawl the city of Aden witnessed, where growth in many urban areas as well as the inhabitation of previously uninhabited regions progressed rapidly, the CF was left with new burdens with which it is not entirely able of tackling. Moreover, the period of time whereupon the country suffered from the political conflict caused the population in Aden to grow leading to an increase in the amounts of waste produced by the city which require significant resources in order to have it removed off the city's streets and neighborhoods. However, given the limited resources of the CF's which became more prominent since more services have become required due to this increase in the amounts of waste, the burdens on the CF's administration grew exponentially. Therefore, the CF resorted to dividing highly populated directorates onto less populated areas that would be capable of containing this expansion in population and waste alike, thus minimizing and allowing for distributing of large amounts of work among these areas, which include ( Al-Boraiqa – Inma' and Al-Sha'b) and (Al-Mansoora – Abdulaziz and Al-Qahera) which brought the number of cleaning administrations in the directorates up to ten administration, where each one of these administrations is in charge and owns its own separate equipment, machines and workforce. The 10 administrations are listed as follows:

Al-Mansoora (Al-Qahera) 6. Al-Tawahi 1. Sheikh Othman 7. Al-Mu'alla 2. Dar Sa'd 8. Crater 3. Al-Boraiqa (Al-Sha'b) 9. Khormaksar 4. Al-Boraiqa (Inma') 10. Al-Mansoora (Abdulaziz) 5.

- 22 -

These administration branches are included within the general administration of cleaning affairs, each of which is responsible for following up and carrying out cleaning activities (mainly collecting waste and cleaning of streets) in its own region as well as monitoring performance levels of workers and documenting amounts of waste transported to the dump site in Bair Na'ama on a daily basis. In order to run smooth operations, these administration branches were constructed based on the editorial structure shown in the following figure.

3.6.1. Buildings and Facilities

Each administration owns its building which is used for management of cleaning activities and practices, organizing and storing of editorial documents, reports and statistics as well as storing of equipment and machines with the exception of Al-Mansoora – Al-Qahera and Al-Boraiqa – Inma' as these two administrations do not yet own their administrative buildings.

The data collected during the field visits to these administrations show how severe the damage sustained by these buildings is, which was primarily caused by acts of robbery and vandalism. Additionally, some of these buildings were totally damaged as a result of the military operations that happened inside the city. Projects concepts comprises more details and a number of pictures that illustrate the severity of the damage sustained by the administrative buildings in the different directorates.

Given the importance of the cleaning administrations in the directorates is, the CF is hoping of sponsors and humanitarian organizations to foster rehabilitation and renovation works of partially destroyed facilities and the construction of new buildings in areas where totally destroyed buildings and areas that do not own their administrative buildings. Current condition and needs of each administration have been explained as follows:

Director of Directory

Vehicles Officer Waste Officer Sweeping Officer

Blocks Observers

Workers

Collection Vehicles

Drivers

Workers

- 23 -

Cleaning Administration in Al-Tawahi

Cleaning Administration in Al-Mu'alla

Required Work Type of damage Damages No building work is required Building

Supplement 6 doors are missing/damaged

Doors

Supplement 3 windows are missing/damaged

Windows

Supplement and installation

Missing/destroyed Electrical appliances and wiring

Supplement and installation

Toilet, syphon, sinks, taps and tank are missing/damaged

Bathrooms

Supplement Missing Furniture Painting Old Painting

Required Work Type of damage Damages Construct new building

The building is colonized.

Building

Satellite photo of Al-Tawahi

Administration Building

Satellite photo of Al-Mu'alla

- 24 -

Cleaning Administration in Crater

Cleaning Administration in Khormaksar

Required Work Type of damage Damages Build roofs for bathrooms

The roof of the bathroom is not completed

Building

Supplement 10 doors are missing/damaged

Doors

Supplement 12 windows are missing/damaged

Windows

Supplement and installation

Missing/damaged Electrical appliances and wiring

Supplement and installation

Toilet, sinks, taps and tank are missing/damaged

Bathrooms

Supplement Missing Furniture New painting Old Painting

Required Work Type of damage Damages Construct a small room

There is no warehouse

Building

Supplement Only 1 door requires replacement

Doors

- - Windows Supplement and installation

Missing/damaged Electrical appliances and wiring

- - Bathrooms Supplement Missing Furniture New painting Old Painting

Satellite photo of Crater

Administration Building

Satellite photo of Khormaksar

Administration Building

- 25 -

Cleaning Administration in Al-Mansoora

Cleaning Administration in Al-Sheikh Othman

Required Work Type of damage Damages Re-construct the roofs of the building

Roofs are damaged

Building

Supplement 3 doors are missing

Doors

Supplement 7 windows are missing/damaged

Windows

Supplement and installation

Missing/damaged Electrical appliances and wiring

- - Bathrooms Supplement Missing Furniture New painting Old Painting

Required Work Type of damage Damages Reconstruct the roof of the bathroom

The roof of the bathroom is not destroyed

Building

Supplement 3 doors are missing

Doors

Supplement 7 windows are missing/damaged

Windows

Supplement and installation

Missing/damaged Electrical appliances and wiring

Supplement and installation

Toilet, taps and tank are missing

Bathrooms

Supplement Missing Furniture New painting Old Painting

Satellite photo of Al-Mansoora

Administration Building

Aerial photo of Al-Sheikh Othman

Administration Building

- 26 -

Cleaning Administration in Dar Sa'd

Cleaning Administration in Al-Boraiqa

Required Work Type of damage Damages Reconstruct the damaged wall

One of the walls is damaged

Building

Supplement 6 doors are missing/damaged

Doors

Supplement 8 windows are missing/damaged

Windows

Supplement and installation

Missing/damaged Electrical appliances and wiring

- - Bathrooms Supplement Missing Furniture New painting Old Painting

Required Work Type of damage Damages Reconstruct the building completely

Severely damaged

Building

Satellite photo of Dar Sa'd

Administration Building

Satellite photo of Al-Boraiqa

مبن

- 27 -

3.6.2. Vehicles and Equipment

For the cleaning administrations in the directorates to be able to perform their duties efficiently, the CF provides the necessary equipment and tools for each directorate based on population density and amounts of waste produced by each of these directorates. Therefore, each administration has its own specified share of equipment and machines separately from the other administrations.

A. Containers Normally are metal or plastic boxes of various capacities (1 m which are the most common type, 1.1 m and 3 m). Cleaning and hygiene administrations in the directorates distributed these containers around Aden’s streets and neighborhoods, and they are used specifically for collecting waste and trash bags in order to have waste and trash collected and transported using specific machines and vehicles in a periodic fashion. The containers are considered among the most damaged equipment in a constant manner, caused mainly by increase in humidity in the city, which causes corrosion of metal containers rather quickly. Additionally, burning waste inside containers which results in damage of plastic containers. Despite the support and sponsorship, the CF received from humanitarian organizations, such as Emirate Crescent, UNICEF, UNOPS, Ark Assistant and others, which mostly included supplying containers of different capacities, thus improving the practices and activities of the CF, yet administrations of the CF still need large numbers of waste containers. As a result of this shortage in containers, citizens in several areas started to throw waste and trash on the streets and around the neighborhoods of the city leading to real and serious health and environmental issues. The number of containers currently used in Aden is estimated to be around 800 containers of 1 cubic meter in addition to 50 containers of 3 cubic meters, most of which obtained through support the CF received from humanitarian organizations. However, estimations put the number of needed containers at (1600 – 2000) of 3 cubic meters in capacity in order to cover the demand mandated by the amounts of waste produced by the city.

Plastic Containers from Emirate Crescent Metal Containers from UNICEF

Metal Containers from UNOPS Metal Containers from ARK ASSIST

- 28 -

B. Vehicles Each of the administrations in the directorates uses its own waste collecting equipment in order to collect waste from the different neighborhoods and streets in the city after which have it transported to one of the transfer station in Al-Mansoora directorate or to the dump site in Bair Na’ama in Al-Boraiqa directorate. Two types of these machines are used for this purpose, either ordinary waste collecting vehicles or waste collecting vehicles equipped with compactors.

However, due to acts of robbery and theft that started in the last months of 2011 reaching the conflict period which started in March of 2015, the administration of the CF lost more than 60% of its equipment, which the CF could not recover while the remainder 40% are severely damaged due to overuse of these equipment in order to make up for the loss in equipment.

Damaged Plastic Containers

- 29 -

The following table illustrates current condition of the remaining vehicles at the CF, used by administrations of the CF

For administrations of the CF to become able to carry out its practices and activities in the desirable manner without much difficulties and obstacles, the loss of equipment must be substituted in proportion with the amounts of waste produced by Aden’s various directorates. The CF’s urgent needs of vehicles are listed as follows:

Total Amount of Waste

(tons/day)

Total No. of Vehicles

Collection Vehicles with Compactor

Collection Vehicles

Directorate NO

60 6 2 4 Al-Tawahi 1 60 6 2 4 Al-Mu'alla 2 65 7 5 2 Crater 3 50 7 2 5 Khormaksar 4 65 6 3 3 Al-Mansoora – A. Al-Aziz 5 60 5 2 3 Al-Mansoora – Al-Qahera 6 75 8 3 5 Al-Sheikh Othman 7 65 6 3 3 Dar Sa'd 8 40 3 1 2 Al-Boraiqa – Inma' 9

250 4 2 2 Al-Boraiqa – Al-Sha'b 10 790 58 25 33 Total

Costal Sweepers

Main Street

Sweepers

Collection Vehicles with Compactor

Collection Vehicles

Directorate NO

12 m3 15 m3 18 m3 3 1 2 2 1 2 Al-Tawahi 1

2 2 1 2 Al-Mu'alla 2 1 2 2 1 2 Crater 3

2 2 1 2 Khormaksar 4 1 2 2 1 2 Al-Mansoora – A. Al-Aziz 5

2 2 2 Al-Mansoora – Al-Qahera 6 2 2 1 2 Al-Sheikh Othman 7

1 2 2 1 2 Dar Sa'd 8 2 2 1 2 Al-Boraiqa – Inma' 9 2 2 2 Al-Boraiqa – Al-Sha'b 10

3 4 20 20 8 20 Total

- 30 -

3.6.3. Periodic Operation Tools

Administrations of cleaning require yearly supplementation of operation tools that enable them practicing their daily activities related to street sweeping. The following table shows the CF’s administrations’ yearly needs of operation tools:

Outdoor garbage

with wheels Trash cans U

niforms

Barrels D

ustpans Trash bags W

heeled Barrels G

ypsum Rakes Swift Broom

s Rough Broom

s Directorate NO

300 200 450 200 540 720 60 360 240 600 1,200 Al-Tawahi 1

300 200 450 200 540 720 60 360 240 600 1,200 Al-Mu'alla 2

300 200 450 200 540 720 60 360 240 600 1,200 Crater 3

300 200 450 200 540 720 60 360 240 600 1,200 Khormaksar 4

300 200 450 200 540 720 60 360 240 600 1,200 Al-Mansoora – A.

Al-Aziz

5

300 200 450 200 540 720 60 360 240 600 1,200 Al-Mansoora – Al-

Qahera

6

300 200 450 200 540 720 60 360 240 600 1,200 Al-Sheikh

Othman

7

300 200 450 200 540 720 60 360 240 600 1,200 Dar Sa'd 8

300 200 450 200 540 720 60 360 240 600 1,200 Al-Boraiqa –

Inma'

9

300 200 450 200 540 720 60 360 240 600 1,200 Al-Boraiqa – Al-

Sha'b

10

3,000 2,000 4,500 2,000 5,400 7,200 600 3,600 2,400 6,000 12,000 Total

- 31 -

3.6.4. Field Workforce:

The CF strived to provide a workforce capable of fulfilling it capacities in order to improve the hygiene’s level in the directorates regarding sweeping works, waste collecting, afforestation and maintenance workers (engineers and technicians), the table below shows how the workforce is distributed among the city’s directorates

As shown in the tables above, numbers of field, editorial and technical workers vary among directorates, caused by the nature of each directorate in terms of area, location, population and nature of dominant activity (economical/residential). The CF considered the previous factors upon assignment of workforce and number of machines and tools in accordance with the previously mentioned factors.

Total Administrators Drivers Observers Operators Sweepers Directorates NO 271 5 14 39 26 187 Al-Tawahi 1 245 7 13 32 33 160 Al-Mu'alla 2 372 7 22 28 48 267 Crater 3 241 8 10 33 28 162 Khormaksar 4 211 16 20 21 31 123 Al-Mansoora – A. Al-Aziz 5 187 3 11 22 28 123 Al-Mansoora – Al-Qahera 6 426 8 38 66 53 261 Al-Sheikh Othman 7 196 10 17 21 43 105 Dar Sa'd 8 88 5 9 9 19 46 Al-Boraiqa – Inma' 9 196 9 6 18 41 122 Al-Boraiqa – Al-Sha'b 10 2433 78 160 289 350 1556 Total

- 32 -

3.7. Al-Mansoora Transfer Station

Given how far away and remote the Bair Na'ama's dump site – where the final stage of solid waste disposal occurs – is located, the process of transporting the collected waste from all areas in Aden to the dump site location is rather inefficient and causes fatigue to waste collecting machines, longer journeys and leads to significantly higher consumption of fuel. With the purpose of making the disposal of solid waste more efficient, the CF established a transfer station in Al-Mansoora directorate. Located next to Express Petrol Station, the transfer station is one of the most important assets owned by the CF. The station is designed to receive solid waste brought in by collecting and compacting machines from all directorates in Aden, this waste is unloaded into large truck trailers (load 40 tons). Upon reaching the specified load of these truck trailers, solid waste is transported to the dump site Bair Na'ama in Al-Boraiqa directorate.

Al-Mansoora's transfer station is one of the assets owned by the CF which was severely affected during the conflict the city of Aden witnessed. The station lost most of its equipment which prevented the formerly normal activity of receiving and transporting solid waste produced by Aden city, estimated at about (750 tons/day). Because it became nearly impossible to work within the capacity expected from the station, a temporary dump site was set up (Al-Hiswa Dump Site) in Al-Mansoora directorate. Additionally, necessary equipment and machines were rented and paid for on a daily basis, which has strained the CF's very limited budget.

The station is made up of a number of machines and facilities designed to serve the purpose for which the station was established. Following, is a detailed explanation of the main components of the station

3.7.1. Equipment and Tools

i. Truck Heads and Trailers Since the establishment of the station in 2014, it was in possession of the necessary equipment suitable for the station's type of work. The equipment the station owned were four truck heads and six trailers (load 40 tons) used for periodic transportation of waste from Aden's different parts to the station and later on to the dump site in Bair Na'ama. Only two of the four trailer heads are left and of these two, one is in a poor condition. Five of the truck containers were damaged beyond repair, which leaves a single functioning trailer. Currently, the station is stopped and unable to conduct the role for which it was established.

- 33 -

ii. The Transfer Station Scale

The station owns a truck scale (capacity 40 tons) for weighing waste collecting vehicles coming from Aden's directorates. The weighing process is carried out in order to confirm whether the allowable load has been reached as well as account for the amount of waste collected daily and having it compared against the number of functioning equipment and the amount of gas and oil necessary for operating this equipment. Even though the scale is in a good and working condition, it requires constant and periodic maintenance. Additionally, the scale is connected to a computer that monitors and documents the trips in order to construct periodic reports on the total number of trips carried out classified based on equipment and region.

- 34 -

3.7.2. Structural Facilities

i. The Dumping Hill The dumping hill is used for allowing the waste collecting vehicles to unload the waste through a metal funnel – located at the top of the hill – into the trailers which are located below the funnel. The hill simplifies the process of unloading garbage collecting vehicles significantly, which is why it is very important to carryout rehabilitation and maintenance works on the rail alongside the hill (shown in the picture). In addition, the metal funnel, which has started to corrode as a result of rust needs to be replaced. Also, the upper part of the funnel, through which garbage passes, should operate as a closed system in order to prevent garbage from flying around causing pollution to the surrounding area of the station.

- 35 -

ii. Fuel Station: Given the importance of the station's location, as it is a connecting point where vehicles collecting waste as well as waste transporting vehicles passes through, a fuel station was provided for the station in order to supply vehicles with the necessary amounts of fuel to operate according to their designated roles. Fortunately, the fuel station was left unharmed and is in a good working condition.

iii. Surrounding Fence of the Transfer Station The northern part of the fence surrounding the station was damaged, raising security-related concerns in regards to having the transfer station and its assets secured and safe, which dictates the need for rehabilitation works on the damaged parts of the transfer station.

- 36 -

The table below shows the remainder of damaged machines and equipment, some of which were temporarily and urgently rehabilitated in order to perform a few crucial tasks at the station.

Notes Current Condition Qty Type of Asset NO Destroyed Partially Damaged Good

One of the destroyed has burned and the another is out of service

2 2 4 Truck heads – Load 40 tons 1

5 1 6 Truck containers – Load 40 tons

2

Periodic Check-ups are required 1 1 Truck scale – 40 tons 3 Old but still work 1 1 Desktop computer 4 1 1 Administration building 5 1 1 Diesel station 6 1 1 Diesel generator 7

Given the important role the transfer station plays in management of solid waste, it has become very urgent to rehabilitate it and put it back in service as it is a crucial part in the cycle of solid waste disposal. For that to happen, the following needs must be provided

Type of Work Qty Requirements NO

Supplement

4 Truck heads – load 40 tons 1 8 Truck containers – load 40 tons 2 1 Additional diesel generator 3 1 Desktop computer 4

Periodic maintenance - Truck scale- load 40 tons 5

Civil work

- Rehabilitate the dumping hill 6 - Rehabilitate the metal funnel 7

- Build the damaged part of the fence of the transfer station

8

- 37 -

3.8. Al-Hiswa Temporary Dump Site

Due to the sever lack of equipment and machinery at Al-Mansoora's transfer station which has rendered the station incapable of receiving and transporting all the waste produced from all areas in Aden to the dump site in Bair Na'ama and because the dump site in Bair Na'ama was forced to shut down after four in the afternoon due to security concerns given the closeness of the dump site from the coalition's forces camp, the CF resorted to contrive a temporary transfer dump site in Al-Hiswa area in Al-Mansoora directorate. The aim of this temporary transfer dump site was to receive the waste brought by the CF's equipment during the afternoon period – at which time the dump site in Bair Na'ama was closed – and then have the waste transported during the morning of the following day to the dump site in Bair Na'ama, using the CF's available equipment as well as the equipment rented from private parties, in order to prevent the accumulation of waste at the temporary dump site.

The CF was able to manufacture a sufficient setup for the temporary dump site through surrounding the location with sand and large trees in order to preserve a healthy and environmentally friendly setting within the surrounding area and to protect the area from flying sand and plastic bags. Despite the precaution measures the CF took, the location of the temporary dump site is rather unsuitable considering that it’s located within the Hiswa natural reserve. The negative effect the temporary dump site has on the Hiswa natural reserve is too significant, which commands a need to have both Al-Mansoora's transfer station and the dump site in Bair Na'ama

reactivated full time and completely shut down the temporary dump site in order to protect the Hiswa natural reserve healthy, clean and free of any pollutants that could cause serious harm.

What makes the situation at Al-Hiswa temporary dump site worse is the lack of any treatment procedures that could dispose of the accumulated waste which the CF cannot – with its current

- 38 -

resource – transport to the dump site in Bir Na'ama, leading to increase in the amounts of accumulated waste day in day out causing a major environmental catastrophe in the area.

The Table below listing the existing equipment in Al-Hiswa station

Notes Current Condition Qty Type of Asset NO Destroyed Partially Damaged Good

6 6 Truck containers – Load 12 tons

1

1 1 Wheel loader 2

- 39 -

3.9. The Dump Site

The dump site, located in Bair Na'ama in Al-Boraiqa directorate behind Bazar'a Steel Factory is an asset owned by the Cleaning Fund where the final stage of solid waste disposal occurs. The location of the dump site was carefully chosen as to be far-removed from residential areas and ground water sources; where the nearest ground water well is about 60Km away whereas the nearest residential compound is located at a distance of 1.5Km from the dump site. This suitably distant location of the dump site prevented any negative effects from harming citizens and water sources.

The area of the dump site is estimated to be around 4Km2, which requires a security fence in order to protect the dump and the equipment and machines from robbery and damage to which the dump site was exposed during the recent conflict.

In 2010 the dump site used to receive about 450 tons/day of solid waste; however, this number has risen and reached what is roughly estimated to be 650 tons/day of solid waste delivered from Aden's eight directorates. This increase in the amount of solid waste is due to the large increase in the population in the city of Aden caused by declaring Aden as the capital of the country as well as the increase in the number of refugees from neighboring governorates where conflicts are still ongoing.

Solid waste in the dump used to be disposed of by burial, a modern method that complies with the international environment standards 3-5-meter-deep layered holes that are covered with sand and after which they are compacted using proper equipment, such as bulldozers, compactors and wheel loaders. Unfortunately, all these machines and equipment were either robbed or damaged during the conflict.

- 40 -

Currently, the collected waste is spread over large areas within the dump site and is left to be exposed under the sun rays in order to get rid of the leachate; where strong sun rays dry off a big part of the leachate and the remainder is absorbed by the sandy soil of the dump site. After that, solids are compacted until 50-60% of the initial size has shrunk, which is accomplished using a wheel loader and a newly obtained bulldozer from UNOPS. Even with the aid of this new equipment, the work load is still too great to be fully covered, especially since the formerly used wheel loaders and bulldozers are now in Dar Sa'd's central maintenance workshop as they are in a bad shape and require full maintenance. Previously, waste used to be covered after compacted with a layer of sand, which used to be transported from a site 300 meters away from the dump site using dump trucks, that are currently non-functional, causing waste to be left uncovered and exposed leading to unfinished disposal of solid waste, which renders the dump site a source of air pollution.

Additionally, the proximity of the dump site to the coalition's military campground, and due to security concerns, the dump site is forced to shut down all its operations after four o'clock in the afternoon, which is one of the problems that caused the CF to resort to using Al-Hiswa temporary transfer dump site despite its negative effects on the environment.

The dump site consists of a number of machines and facilities designed to serve the purpose for which it was established.

Following, is a detailed explanation of the main components of the dump site:

3.9.1. Bulldozers and Wheel Loaders

In the past, the dump site owned two bulldozers that were used for compacting solid waste and three wheel-loaders and two dump trucks used for loading and transporting waste and sand into the dump site. However, due to the theft and damage to which the dump was exposed, one of the bulldozers is currently out of service (found at Dar Sa'd's maintenance workshop) and the other one while is in a working condition, it requires extensive maintenance. As for the wheel loaders, they are all at Dar Sa'd's maintenance workshop as they require extensive maintenance. One of the dump trucks is at Dar Sa'd's maintenance workshop as it requires extensive maintenance, while the other one is still in a working condition. Given the state of the dump's equipment, the UNPOS has provided the dump with urgent and new equipment: bulldozer, wheel-loader and wheel-tractor scraper.

- 41 -

Nevertheless, compared with workload the dump site receives (750tons/day), the number of equipment is still insufficient, which commands supplying the dump site with the necessary equipment for it to fully carry out its duties.

3.9.2. Scale

The dump site owns a German made scale (capacity 80 tons), which has been out of service since 2015 and is need of maintenance works to operate again. Also, the dump owns a Chinese made scale (100 tons) that was provided by the UNOPS. In order to smooth the dump's work, the CF's management found it crucial to rehabilitate the old scale.

- 42 -

3.9.3. Structural Facilities

i. Administrative Buildings: There is one administrative building equipped with facilities, such as bathrooms and security rooms that are in a poor shape and require rehabilitation, renovation and lightening works.

ii. Recycling Hangar: The dump site used to own a recycling hanger where waste made out of paper used

to be recycled by a private investor. However, the recycling hanger was put out of work due to the conflict in the city. The CF is working to rehabilitate the recycling hanger in order to put it back in service to recycle glass, plastic and paper waste. Additionally, it is expected that the rehabilitation of the recycling hanger could bring investments in the waste recycling field and the revenues could benefit the CF's greatly given its dire need for means through which rehabilitation works can be accomplished.

iii. The Fence: Building a fence surrounding the dump site is a crucial need in order to protect the site and the equipment it owns from any robbery or destruction. It also will allow monitoring of incoming and outgoing waste, management of waste that is being recycled and/or disposed of in an effective way.

- 43 -

The table below summarizes the current condition of the dump site and all its parts.

In order to have the dump site regain its ability to compact and bury the waste it receives daily to completely dispose of solid waste; it requires to be provided with the machines and equipment it lost and to have its damaged pieces repaired. These needs can be summarized in the table below.

Type of Work Qty Requirements NO

Supplement

1 Bulldozer 1 1 Compactor 2 2 Dump truck (12 tons) 3 2 Wheel loader 4

Civil works - Rehabilitate the recycling hangar 5 - Rehabilitate the administration buildings 6 - Build a fence for the dumpsite 7

Maintenance - Rehabilitate the old truck scale (80 tons) 8

Notes Current Condition Qty Type of Asset NO Destroyed Partially Damaged Good

1 1 (needs maintenance) 1 (New) 3 Bulldozer 1 1 1 Compactor 2 3 1 (New) 4 Wheel loader 3 1 1 (needs maintenance) 1 (New) 3 Dump truck 4 Used for monitoring dumpsite

1 1 Pick-up (Nissan) 5

1 1 Tractor scraper 6 1 (80 tons) 1 (New-100 tons) 2 Truck scale 7 Rehabilitation is required

1 1 Recycling hangar 8

Rehabilitation is required

3 1 (New) 5 Administration buildings

9

- 44 -

3.10. Administration of Afforestation and Public Parks

The CF has a special administration which falls under the technical administration and which is called Administration of afforestation and public parks. Through this administration, the CF aims to increase green lands in the city of Aden, a goal to be achieved through monitoring parks and following up on tree planting activities in parks, corniches, streets and neighborhoods of the city of Aden. In order to achieve such purpose, the CF established nurseries. The CF also specified a crew consisting of workers, machines and drew up strategies that would enable administration of afforestation and public parks to carry its duties to the highest standards.

However, with the beginning of the military operations in the city, which led to the loss of several afforestation machines and equipment as well as exposing parks, water fountains and nurseries to acts of vandalism and robbery because of the administration’s incapability of monitoring and watering these plants throughout the conflict’s duration which the city witnessed. Consequently, administration of parks and afforestation is currently struggling with extreme difficulties which prevents the administration from carrying out activities in a steady manner.

- 45 -

Despite the dire situation with which the administration struggles and the severe shortage in resources, it still managed to reconstruct several parks and corniches and plant trees in several intersections and median strips The estimated area of public parks monitored by the administration of parks and afforestation is nearly 604800 square meters, total area of afforestation sites in median strips is 315900 square meters, for afforestation sites in intersections is 21682 square meters. The total estimated area of tree planting activities in corniches is around 46000 square meters. The table below shows the current infrastructure of administration of afforestation and public parks:

There are still many tasks which the administration of afforestation and parks must accomplish and monitor. For this administration to be able to improve its afforestation activities and rehabilitation of tree-planting locations in the city, it is necessary to take into account the supplementation of tree-planting tools, equipment and strategies as well as these related to the rehabilitation and watering of nurseries in order to restore the green cover which contributes to improving the city's humid and rather hot weather.

No. Current Condition Needs Notes Public Parks 10 Rehabilitated by the

administration

8 Rented by the private sector

Tending and monitoring areas specified for tree planting

The private sector does not tend to these parks as required

12 Unplanted lands Full rehabilitation (fencing, paving and planting)

Plans for these parks are ready as follows: 1. Aden's Large Park 2. Aden's amusement park

Median Strips 32 Rehabilitated by the administration

Intersections 22 Rehabilitated by the administration

8 New intersections built by the administrations which it also oversees.

6 Destroyed Require rehabilitation (building and planting)

Fountains 5 Damaged Require maintenance works (building and plumping)

Corniches 5 Rebuilt by the administration

5 Damaged Require rehabilitation and maintenance works

Structures 6 Rehabilitated by the administration

Metal structures which represent Aden's heritage and environment.

- 46 -

The table below shows the necessary needs for the administration of afforestation and parks to operate properly:

Notes Qty Requirements NO 4 Pesticides sprayer pumps 1 20 Carry-on pesticides containers- Capacity 20L 2 200 litres Malathion (Pesticides) 3 200 litres Superacid (Pesticides) 4 200 litres Dursban (Pesticides) 5 6 Fountain pumps 6 120 Large farming scissors 7 300 Small farming scissors 8 400 Manual tree-cutting saws 9 4 Lawn mowing vehicles 10 8 Manual lawn mowers 11 8 Tree-cutting machines 12 8 Fence-clippers 13 8 Suction pumps- 2inch 14 16 Garden water pumps 15 8 Water pumps - 2inch 16 2 Ground water pumps (Grundfos) 17 2 Unused water pumps for garden irrigation 18 500 Kg Bermuda grass seeds 19 1000 Packets Seeds of different flowers for seashore areas 20 4 Packets Field packages for soil inspection 21 800 Kg NPK fertilizer 22 400 Kg Pitmous fertilizer 23 Networks with an area of 50 m2 500 Networks Large moving irrigation system with sprinklers (Pop-

up) 24

1 Tower platform of 16M high 25 8 Flat dump trucks for parks 26 8 Trees cutters Vehicles 27

- 47 -

3.11. Administration of Sand and Construction Waste

The administration of sand and construction waste at the CF is one of the most effective administration whose main mission is removing sand waste caused by construction activities which pose difficulties for cleaning workers. During the military operations the city witnessed, a large number of the administration's equipment was damaged and stolen such as large vehicles and wheel loaders which were used in the fights that happened in the city. The remainder of the equipment was in a very bad condition that won't suffice for the kind of work the administration carries out. The table below shows the condition of the equipment and machines currently owned by the administration of sand waste:

Notes Current Condition Qty Type of Asset NO Destroyed Partially

Damaged Good

1 1 CAT 0914 1 1 1 Collection Vehicle-Hyundai 2

From the previous table, it has become obvious how crucial it is to make up for the loss in equipment in order for the administration of sand and construction waste to be able to perform its duties successfully and contribute to accomplishing the CF's goal in achieving high levels of cleanliness in the city of Aden. The table below shows the needs of the administration of sand and construction waste:

Notes Qty Requirements NO 4 Skid steer loader CAT 216 1 2 Wheel loader CAT 59 2 2 Wheel loader CAT 914 3 12 Dump trucks (12 tons) 4 8 Dump trucks (3 tons) 5

- 48 -

3.12. Maintenance Workshops

Given the fact that the CF owns machines and equipment of various sizes and shapes that are prone to constantly break down and malfunction which mandates a need to perform maintenance works on these machines in order to have them available whenever needed, the CF established three maintenance workshops upon which befalls the task of performing periodic maintenance works on machines and equipment owned by the CF. Exemplary works of these workshops include oil, filters, tires and batteries changing, repair of any out of service machines or equipment owned by the CF. The work amongst these three workshops was assigned as follows:

i. Central Maintenance Workshop in Khormaksar: Responsible for maintenance and repair works for CF-owned machines and equipment operating within the first main area: Khormaksar, Al-Tawahi, Al-Mu'alla and Crater.

ii. Central Maintenance Workshop in Al-Mansoora: Responsible for maintenance and repair works for CF-owned machines and equipment operating within the second main area: Al-Mansoora, Al-Sheikh Othman, Dar Sa'd and Al-Boraiqa.

- 49 -

iii. Productive Maintenance Workshop in Dar Sa'd: Responsible for maintenance and repair works on heavy and large machinery and equipment.

Despite the CF's great efforts in providing all necessary needs for the maintenance workshops, the financial challenges with which the CF struggles, especially low income, have caused the CF to become unable to perform rehabilitations works, such as renovation of buildings, supplying necessary tools, equipment and spare parts used in maintenance works on broken down machines, on these workshops.

The three maintenance workshops were severely affected during the recent conflict in the city. Acts such as robbery and vandalism reached all three workshops. Below, is a detailed explanation of the current condition of the workshops:

3.12.1. Buildings and Infrastructure

Despite everything that has happened to the maintenance workshops, possible maintenance works are being carried out using available tools. However, main buildings of the workshops were partially damaged, bathrooms require urgent maintenance, and the workshops also require installing proper lightening.

Khormaksar Maintenance Workshop

- 50 -

3.12.2. Tools and Equipment

Because the CF's budget has become very limited which has caused the inability to provide maintenance workshops with the necessary tools and equipment, as the majority was lost due to the conflict. Because of the importance of the work carried out by these workshops, the following tools and equipment are very necessary for the workshops to perform their duties:

o Maintenance tools and equipment of various machines (Technicians Maintenance Kits)

o Electricity generators to ensure continuous work during power blackouts.

o Tools and equipment for welding machines.

o Car washing tools to ensure these vehicle's safety and waste-free status.

o Mobile maintenance workshops equipped with all field maintenance and welding tools.

Periodic Maintenance Requirements (Annual Needs of Maintenance Workshops)

The CF requires yearly supply of necessities for machines and equipment, such as oils, tires, filters, etc. The table below shows these requirements.

Qty Annual Requirements for Maintenance Workshops NO Tyres

400 16*825 1 40 20x900 2 600 16 x 750 3 330 20 x 1100 4

Al-Mansoora Maintenance Workshop

Dar Sa’d Maintenance Workshop

- 51 -

36 25 x 23.5 5 40 25 x 20.5 6 200 12 x 16.5 7 120 24 x 1200 8 150 22.5 x 12 9 20 R20 x 1200 10 100 R17.5 x 900 11 36 R25 x 23.5 12 200 R12 x 16.5 13 150 R22.5 x 1200 14 50 R25 x 20.5 15 200 R24 x 1200 16

Tubes for Tyres 200 R20 x 1100 17 20 R20 x 900 18 310 R16 x 750 19 250 R16 x 825 20 20 R17.5 x 900 21

Batteries 130 Batteries (150 Ah) 22 120 Batteries (120 Ah) 23 100 Batteries (100 Ah) 24 250 Batteries (70 Ah) 25 30 Batteries (50 Ah) 26 310 Batteries' acid (Bottles - 5 litres) 27

Oils & Fluids 180 Diesel engine oil 50 (Barrels) 28 50 Diesel engine oil 40 15w (Barrels) 29 13 Petrol engine oil (Barrels) 30 280 Hydraulic oil 68 (Barrels) 31 30 Gear oil 140 (Barrels) 32 200 Brake fluid (Cartoons) 33 10 Lubricating grease (Cartoons) 34

3.12.3. Spare Parts

The loss of about 60% of the CF's machines and equipment has caused more stress to be directed towards available machines in aims of substituting for the shortage in the number of machines and equipment, which has caused fatigue to a number of these machines and being out of service. Currently distributed among the three workshops, these machines urgently require spare parts to be provided. The table below shows the number of machines existing currently at the three workshops and the requirements of each of these machines.

- 52 -

Notes Required Spare Parts Location Vehicles NO Khormaksar Maintenance Workshop

Hyundai Engine and radiator tank Khormaksar Collection Vehicle 1 Hyundai Engine and radiator tank Al-Tawahi Collection Vehicle Hyundai 2 Hyundai Engine and radiator tank Al-Mu'alla Collection Vehicle Hyundai 3 ISUZU Engine and radiator tank Al-Mu'alla Collection vehicle with internal compactor 4 ISUZU Engine and radiator tank Crater Collection vehicle with internal compactor 5 ISUZU Engine and cabinet Crater Collection vehicle with internal compactor 6 ISUZU Engine and radiator tank Khormaksar Collection Vehicle 7

Al-Mansoora Maintenance Workshop ISUZU Engine, radiator tank and

air system Al-Mansoora Collection Vehicle 8

ISUZU Engine and clutch Al-Qahera Collection vehicle with internal compactor 9 ISUZU Engine and clutch Al-Sheikh Collection vehicle with internal compactor 10 ISUZU Engine and clutch Dar Sa'd Collection vehicle with internal compactor 11 ISUZU Engine and clutch Al-Mansoora Collection vehicle with internal compactor 12 Hyundai Engine and clutch Al-Mansoora Collection vehicle with internal compactor 13 Hyundai Engine, clutch, gearbox

and radiator tank Al-Mansoora Collection Vehicle 14

Hyundai Engine and radiator tank Dar Sa'd Collection Vehicle 15 Hyundai Engine and radiator tank Enma' Collection Vehicle 16 Hyundai Engine Al-Sheikh Collection Vehicle 17 Hyundai Engine Al-Qahera Collection Vehicle 18 Hyundai Engine Al-Mansoora Collection Vehicle 19

Dar Sa'ad Maintenance Workshop CAT Engine Dump site Wheel loader CAT 938G 20 JCB Engine, radiator tank,

brake discs, filters Dump site Wheel loader JCB 436Z 21

CAT Engine, filters, radiator tank

Dump site Wheel loader CAT 0914 22

Hyundai Engine, gear system, filters Soil Waste Collection Vehicle 23 CAT Engine Dump site Wheel loader CAT 938G 24

Khormaksar Maintenance Workshop

- 53 -

Dar Sa’d Maintenance Workshop

Al-Mansoora Maintenance Workshop

- 54 -

3.13. Capacity Building

The CF aims to improve the levels of skills and abilities of its technicians and workers especially the youth through training courses in the various fields the CF's activities include. The training program aims to:

Build a highly capable crew that is able to perform its tasks professionally.

Raise efficiency levels of all administrations of the CF.

Make up for lack of experience which usually causes waste of money and time, an issue with which few of the CF's departments struggle, especially maintenance.

The training program the CF needs to implement includes the following courses:

i. Training course on financial management and improving income: The course aims to:

Improve financial resources and finding new income sources.

Organize and improve the process of revenue collection.

Develop the work of revenue departments and update them using new statistical systems. 10 technicians and workers from financial affairs are to be trained for two weeks.

ii. Training course on evaluating and monitoring:

The course aims to:

Introduce evaluation and monitoring employees to the cleaning blocks in each directorate and ways and methods of evaluating and monitoring works assigned to workers at the cleaning and hygiene administration.

Improve works of monitoring and evaluating, adopt new relevant methods, identifying and treatment of faults immediately and writing reports more professionally. 8 employees from evaluation and monitoring are to be trained for two weeks.

iii. Training course on workshops and vehicle maintenance:

The course aims to:

Improve workshops and update them according to the latest applied standards.

Train workers and technicians on various vehicles and machines maintenance works.

Improve performance of the workshop's administration in order to accomplish works in record time. 10 technicians and workers are to be trained for two weeks.

iv. Training course on environmental awareness:

The course aims to:

Improve skills of employees of environmental awareness on ways and methods regarding environmental awareness as well as modern and effective communication methods.

Train employees of environmental awareness on modern ways to spread awareness regarding environment among the public.

v. Training courses on nurseries and the production of saplings: The course aims to:

- 55 -

Improve quality of plant types.

Train workers and technicians on the ways applied to produce saplings as well as methods to increase production rates of plants. 10 technicians and workers from the nurseries are to be trained for two weeks.

vi. Training course on irrigation systems:

The course aims to:

Educate and train workers and technicians regarding irrigation systems and their main parts.

Train workers and technicians on the way irrigation systems operate.

Train workers and technicians on maintenance of irrigation systems. 8 workers and technicians are to be trained for two weeks.

vii. Training course on the art of ornamentals:

The course aims to:

Train workers and technicians on the ways and methods of trimming and cutting plants and trees in an ornamental way. 10 workers and technicians are to be trained for 10 days.

viii. Training course on public parks planning:

The course aims to:

Improve skills of engineers and department heads in the field of public parks planning and coordinating according to global standards.

Introduce engineers and department heads to live examples of well-planned public parks. 8 engineers and technicians are to be trained for 10 days.

ix. Training course on pest control:

The course aims to:

Introduce workers and technicians of the pest control department to the types of pesticides used in fighting insects and the right way of using these pesticides.

Improve skills of workers and technicians of the pest control department regarding understanding and recognizing types of harmful insects and pest control. 5 workers and technicians of the protection department are to be trained for 10 days.

- 56 -

The following table summarizes the training courses the CF needs in order to improve efficiency levels of workers and technicians:

Notes NO of Employees Required Training Courses NO 10 Employees Training course on financial management and improving

income 1

8 Employees Training course on evaluation and monitoring 2 10 Technicians Training course on workshops and vehicle maintenance 3 Training course on nurseries 4 10 Workers Training course on environmental awareness 5 8 Workers Training course on irrigation systems 6 10 Workers Training course on the art of beauty plants 7 8 Engineers Training course on public gardens planning 8 5 Workers Training course on pest control 9

- 57 -

3.14. Recommendations

i. The rehabilitation of Al-Mansoora transfer station must be viewed as a highly urgent intervention, which upon completion, the expected positive outcome can be summarized as follows:

Increase the number of transportation trips. Due to the current condition of the station where it is unable to receive waste from all directorates, the CF resorted to transport waste using waste collecting vehicles to the dump site in Bair Na'ama which is 35 Km away from some of the directorates, which takes around 2 hours to make the trip back and forth to the dump site. Therefore, vehicles are not able to make more than three trips every day. However, in case the station was rehabilitated, the number of trips for each vehicle is expected to reach 6-9 trips daily.

Quick performance and transportation of more amounts of waste. With the increase in the number of trips for each vehicle, the amount of waste transported will definitely increase which helps with the problem of lack of equipment with which the CF struggles.

Shutdown of Al-Hiswa temporary station Upon rehabilitation of Al-Mansoora transfer station, Al-Hiswa temporary station will no longer be needed, which has become a site where large amounts of waste accumulate causing health threats for the region especially Al-Hiswa natural reserve.

ii. In 2016, the CF was given around 1500 plastic containers from Emirates Red Crescent. However, due to misuse of these containers especially when the citizens burned the waste inside these plastic containers leading to damaging a large number of these containers. The pictures below show a number of the damaged plastic containers.

Therefore, it is recommended that instead of providing plastic containers, metal containers should be considered as they are less likely to get damaged.

iii. Due to the financial challenges with which the CF struggles, it is recommended that humanitarian organizations and other sponsoring partners foster and support projects that would enable the CF from earning a financial revenue which it can use to manage and run more of its activities. With that said, it was found more effective if the recycling unit at the Bair Na'ama dump site is to be activated and rehabilitated, from which the CF could benefit by either recycling waste directly or renting the recycling unit to a private investor, which was the case in the past.

- 58 -

4. Public Corporation of Water and Sewage

The public corporation of Water and Sewage was established under republic decision number 267 in 2000 as a government agency responsible for water and sewer services. Since its establishment, the corporation aims to provide water and sewer services in a way that protects the public's health and the environment and which is satisfactory for the beneficiaries. Similar to the CF, the PCWS is financially and editorially independent, where it mainly depends on revenue and income earned through collecting on water and sewer services bills to provide its operation costs and finance development projects. The corporation is headed by a board of directors made up of 8 members as follows:

1. Aden Governor 2. General Director 3. Director of Water Resources (Aden-Lahj-Abin) 4. General Director of Planning and International Cooperation 5. Director of Finance Office Aden 6. Citizen Representative 7. Private Sector Representative 8. Director of the Board Secretariat

The board of director is seconded by the general manager who is responsible for all editorial and financial departments and administrations within the corporation. Headed by the general managers are two deputies one is Deputy GM for Water Affairs who is responsible for management of operation activities, overseeing and treatment of malfunctions in the water department in the city and monitoring administrations of wellfields control and maintenance of electro-water equipment and workshops. Whereas the other deputy is Deputy GM for Sewer Affairs who is responsible for management of operation activities of the sewer department in city of Aden as well as management of treatment plants and laboratories. The following figure shows the hierarchy structure of the PCWS.

BoD Secretary

General Manager IT Specialist

Control, Audit

& Inspecti

on

Secret

ary IT

Public

Relatio

Legal Affairs

Finance, Management&

Training

Finance

Management Affairs

Warehouse & Procurement

Consumers

Rehab &Training

Office

Planning, Statistics & Investment

Management

Planning & Statistics

Investment Projects

Studies & Information

Central Control

Deputy GM for

Water Affairs

Workshops

Operation & Troubleshooting

Sector One Operation &

Troubleshooting Sector Two

Operation & Troubleshooting

Sector Three Operation &

Troubleshooting Sector Four

Electromech. Workshop

Deputy GM for

Sanitation Affairs

Workshops

Operation & Troubleshooting

Sector One Operation &

Troubleshooting Sector Two

Operation & Troubleshooting

Sector Three Operation &

Troubleshooting Sector Four Lab. &Pools

Management

Drawing & Technical

Documentations

- 59 -

Since the establishment in 2000, the corporation was able to provide water and sewer services in a manner that preserved the cleanliness of the environment and satisfied the citizens. During this period, the corporation carried out several projects through which it was able to improve and better its services as well as deliver these services to most of the areas in Aden city. The water services reached about 86% of the population whereas sewer services reached 69%. The corporation continued to provide constantly good level of services until 2011 when the political crises began and adversely affected the PCWS. Matters only grew worse in 2015 when the armed conflict started. Due to these crises and conflicts, the corporation was severely affected and lost a lot of the income resources upon which it depended to finance its activities. Additionally, the corporation lost many of its assets and things continued to worsen to the point where the corporation became unable to perform necessary maintenance works to maintain and keep the equipment and machines that got worn-out and went out of service.

Within this destruction and damage of the corporation's assets and equipment, the population in Aden witnessed a huge increase, resulting from declaring Aden as a temporary capital of the country, which caused to overload assets of the corporation which were still in service. Facing all these challenges, the corporation was rendered incapable of providing the citizens with clean water and sanity sewer overflow became a recurrent problem, which caused Aden city to suffer from several serious problems that endanger the safety of the people and the environment alike.

In order to save the city from the catastrophic condition it reached, several humanitarian organizations offered significant help. However, despite the support and help the corporation received, the repair and replacement of all that was damaged in the crisis of 2011 and the conflict of 2015 still requires extensive efforts that would enable the corporation to resume its ability to carry out its operation activities and projects.

- 60 -

4.1. Headquarters

The headquarters of Water and Sewage is located in Crater directorate. It is made up of a building of two floors and includes many administrative offices. PCWS needs to expand the headquarter building to add new offices.

Although the existing building is rather old, it is still in a good enough condition and no maintenance or rehabilitation works are required excluding offices of deputy of general manager of sanitation affairs, secretary and administration of technical studies and documentation.

The table below shows the needs the three offices.

Qty Unit Type of Work Required Equipment/Rehabilitation Administration No Civil Work Complete rehabilitation for the bathroom Deputy of general

manager office 1

Rehabilitation of mosque 2 Painting the office 3 Replacing the windows 4 Supplying new curtains 5 Replacing the doors 6 Maintenance Maintenance of electricity and lightening 7 Maintenance of interior phone network 8 Installation ADSL connection 9 1 No Supplement Chairs 10 1 No A3 Printer 3in1 (printer, scanner &photocopier) 11

- 61 -

8 No Printers inks (bottles) 12 1 No UPS for desktop computer 13 1 No Air conditioner 14 1 No Water cooler 15 2 No Wooden cupboards with glass fronts for files

keeping 16

Civil works Painting the office Secretary office 17 Replacing the windows 18 Supplying new curtains 19 Replacing the doors 20 Maintenance Renovate the lightening and wiring system 21 Maintenance of interior phone network 22 Installation ADSL connection 23 Supplement Supplying new curtains 24 6 No Chairs 25 1 No Laptop 26 1 No Desktop computer 27 1 No Colourful printer (A4) 28 1 No UPS for desktop computers 29 8 No Ink for printers (bottles) 30 1 No Air conditioner 31 1 No Water cooler 32 3 No Wooden cupboards with glass fronts for files

keeping 33

Civil works Replacing doors Technical studies and documentation administration (two offices)

34 Replacing wooden windows by aluminium

windows 35

Painting the office 36 Office ceramics 37 Maintenance Renovate the lightening and wiring system 38 Renovate the phone local network 39 Installation ADSL connection 40 12 No Supplement Stationary chairs 41 1 No LaserJet colourful printer (A4) 42 1 No A3 printer 3in1 (printer, scanner photocopier) 43 1 No Plotter (A0) 44 12 No Printer inks (cartridge) 45 3 No Laptops 46 4 No Desktop computers 47 1 No Hard disk (1 Tera) 48 10 No UPS for desktop computers 49 1 No Air conditioner 50 6 No Wooden cupboards with glass fronts for files

keeping 51

- 62 -

1 No Water cooler 52 4 No Original copies for engineering software (GIS,

AutoCAD, Sewer CAD, Antivirus) 53

1 No Satellite Images for Aden city (soft and hard copies) 54

4.2. Administration Buildings

Due to expansion in works and tasks in the departments of water and sanitation, administrations were constructed in every directorate in order to closely monitor works and tasks, manage operations, ease the process of income collecting and sort out complaints and problems. These administrations lack several office tools that are necessary for carrying out their duties. Additionally, office buildings in both Al-Mansoora and Al-Sheikh Othman require rehabilitation works. The table below shows the needs of the administrations in the directorates:

Location Qty Unit Type of Work Required Equipment/Rehabilitation

No

Al-Mansoora & Al-Sheikh Othman

Civil Work Complete rehabilitation for the buildings

1

5 for each directorate 40 No Supplement Desk 2 1 for each directorate 8 No Desktop computer 3 1 for each directorate 8 No Laptop 4 1 for each directorate 8 No Colorful printer (A3) 5 4 for each directorate 32 No Air conditioner 6 6 for each directorate 48 No Chairs 7 1 for each directorate 8 No Water cooler 8

4.3. Maintenance Workshops

Given the fact that the PCWS owns machines, motors, pumps and equipment of various sizes and shapes that are prone to constantly break down and malfunction which mandates a need to perform maintenance works on these machines in order to have them available whenever needed, the PCWS established four maintenance workshops upon which befalls the task of performing periodic maintenance works on machines and equipment owned by the PCWS. Exemplary works of these workshops include oil, filters, tires and batteries changing, repair of any out of service machines or equipment owned by the PCWS. The work amongst these four workshops was assigned as follows:

Welding Maintenance Workshop: responsible for maintenance and repair works related to steel parts, welding and turnery works

Electrical Maintenance Workshop: responsible for maintenance and repair works related to electrical works such as fixing motors, pumps, generators, etc.

Mechanical Maintenance Workshop: responsible for maintenance and repair works related to mechanical works such as fixing vehicles, trucks, mechanical equipment, etc.

General Maintenance Workshop: this workshop is responsible for maintenance and repair works for all sewerage machines and equipment.

- 63 -

Despite the PCWS's great efforts in providing all necessary needs for the maintenance workshops, the financial challenges with which the PCWS struggles, especially low income, have caused the PCWS to become unable to perform rehabilitations works, such as renovation of buildings, supplying necessary tools, equipment and spare parts used in maintenance works on broken down machines, on these workshops.

In order to enabling the four maintenance workshops, the following requirements need to be supplied.

Notes Qty Unit Requirements No.

More derails are mentioned in 9-Maintenance workshops

1 No Air compressor with air dryer, air filter, regulator and auto drainer

1.

1 No Air compressor with diesel engine (12 bar)

2.

No Grinding machine 3. No Automatic hose reel 5. No Air Coupler kit 6. No Heavy vehicle engine and

transmission repair stand (1.5-4 tons)

7.

- 64 -

No Engine crane stand (2 tons) 8. Pneumatic tool kits 9. Mechanical tool kits 10. Electrical tool kits 11. 1 No Truck crane (5 tons) 12

In addition, maintenance workshops require annual needs such as oils, tiers, filters, etc. the table below shows the annual needs of maintenance workshops.

Qty Annual Requirements for Maintenance Workshops NO Tires

400 315/80 – Front 1 40 315/80 – Back 2 600 1200 R 20 3 330 1100 R 20 4 36 1000 R 20 5 40 900 R 20 6 200 750 R 16 7 120 700 R 16 8 150 Polygon tires (900 R 20) 9 20 Polygon tires (1100 R 20) 10 100 205/70 R15 11 36 205/70 R16 12 200 700 R16 13 150 195 R14 14 50 165 R13 15 200 235/80 R16 16 200 23.5 R25 17 20 16/70 R20 18 310 13 R22.5 19 250 1200 R24 20 20 325/95 R24 21

Batteries 20 Batteries (150 Ah) 22 16 Batteries (120 Ah) 23 4 Batteries (100 Ah) 24 43 Batteries (70 Ah) 25 22 Batteries (50 Ah) 26 8 Batteries (40 Ah) 27

Oils & Fluids 37 Diesel engine oil 50 (Barrels) 28 14 Diesel engine oil 40 15w (Barrels) 29 4 Diesel engine oil 50 20w (Barrels) 30 10 Hydraulic oil 37 (Barrels) 31

- 65 -

2 Gear oil 140 (Barrels) 32 2 Gear oil 90 (Barrels) 33 2 Radiator engine coolant 34 1 Brake fluid (Barrels) 35 100 Lubricating grease (Bottles) 36

Filters 26 Engine air filter 37 111 Diesel filter 38 64 Oil filter 39 12 Hydraulic filter 40 10 Compressor air filter 41

4.4. Occupational Safety Management

The corporation of water and sewer has a specialized department for occupation safety upon which falls the responsibility to provide safety equipment and tools as well as monitoring and observation of workers regarding following safety precautions and wearing safety gear. This department has several vehicles used for distributing safety equipment, tools and clothes and monitor the workers' commitment in this regard. Additionally, the department has many equipment and necessities designed to protect the workers upon performing highly risky jobs. Due to the damage of most of this department's equipment and tools, it urgently requires maintenance works for its vehicles and safety equipment that have been damaged. Moreover, due to the department's incapability to purchase safety equipment and clothes and distribute them among the workers, it has become rather urgent to provide safety equipment and clothes that are enough to cover all workers who practice activities that require wearing/using these equipment and/or clothes. The table below shows the needs for the occupational safety management

NO Requirements Unit Qty Notes 1. Spare parts for vehicles No 4 Four vehicles need spare parts (Hilux98, Isuzo2004,

Shemco motorbike and Suzuki carry 99) 2. Spare parts for safety equipment No 4 Parts 3. OHS Equipment and Tools

- 66 -

5. Water System

5.1. Wellfields

Well water (underground water) is considered the main water source for the city of Aden. The corporation of water owns 116 underground wells distributed among three main fields: Al-Manasera field with 29 wells, Bir Nasser's field with 46 well and Bir Ahmed's field with 41 wells

However, during the conflict period in the city, several of these wells have stopped working and the actual working number of wells that are currently in service is 106 wells with a well yield estimated at 123933 cubic meters daily.

The table below shows wells' details according to the corporation's records:

Bir Nasser Wellfield Borehole data Pump data

Item Well No /ID

Physical status

Depth (m)

Diameter (mm)

Static water level (m)

Dia. of riser pipe

(mm)

Installation depth (m)

Head H (m)

Quantity Q (m/h)

Power P

(KW)

Power Source

1 BN1 Good 300 300 80-85 100 100 120-140 54 30 Public grid & generator 2 BN2 Good 140 300 80-85 100 100 120-140 47 37 Public grid & generator 3 BN3 Good 170 300 80-85 100 100 120-140 50 37 Public grid & generator 4 BN4 Good 180 300 80-85 100 100 120-140 50 26 Public grid & generator 5 BN5 Good 180 300 80-85 100 100 120-140 50 26 Public grid & generator 6 BN6 Stopped 7 BN7 Stopped 8 BN8 Good 300 300 80-85 100 100 120-140 61 45 Public grid & generator 9 BN9 Good 300 300 80-85 100 100 120-140 65 45 Public grid & generator 10 BN10 Good 300 300 80-85 100 100 120-140 76 45 Public grid & generator 11 BN11 Good 300 300 80-85 100 100 120-140 54 30 Public grid & generator 12 BN12 Good 300 300 80-85 100 100 120-140 65 37 Public grid & generator 13 BN13 Good 300 300 80-85 100 100 120-140 61 45 Public grid & generator 14 BN14 Good 300 300 80-85 100 100 120-140 54 56 Public grid & generator 15 BN15 Good 189 250 80-85 100 100 120-140 50 37 Public grid & generator 16 BN16 Good 300 300 80-85 100 100 120-140 61 37 Public grid & generator 17 BN17 Good 300 300 80-85 100 100 120-140 65 56 Public grid & generator 18 BN18 Good 187 300 80-85 100 100 120-140 54 22 Public grid & generator 19 BN19 Good 189.4 300 80-85 100 100 120-140 47 22 Public grid & generator

Administration Office in Bir Nasser wellfield Administration Office in Bir Ahmed wellfield

- 67 -

20 BN20 Good 300 300 80-85 100 100 120-140 50 37 Public grid & generator 21 BN21 Good 300 300 80-85 100 100 120-140 68 45 Public grid & generator 22 BN22 Good 189 300 80-85 100 100 120-140 50 37 Public grid & generator 23 BN23 Good 185 300 80-85 100 100 120-140 50 30 Public grid & generator 24 BN24 Good 300 300 80-85 100 100 120-140 58 37 Public grid & generator 25 BN25 Good 300 300 80-85 100 100 120-140 58 37 Public grid & generator 26 BN26 Good 300 300 80-85 100 100 120-140 58 30 Public grid & generator 27 BN27 Good 300 300 80-85 100 100 120-140 54 45 Public grid & generator 28 BN28 Good 190 300 80-85 100 100 120-140 47 26 Public grid & generator 29 BN29 Good 300 300 80-85 100 100 120-140 58 45 Public grid & generator 30 BN30 Good 170 300 80-85 100 1000 120-140 54 45 Public grid & generator 31 BN31 Good 179.41 300 80-85 100 100 120-140 50 30 Public grid & generator 32 BN32 Good 180.69 300 80-85 100 100 120-140 54 45 Public grid & generator 33 BN33 Good 300 300 80-85 100 100 120-140 58 45 Public grid & generator 34 BN34 Good 300 300 80-85 100 100 120-140 43 26 Public grid & generator 35 BN35 Good 190 300 80-85 100 100 120-140 50 26 Public grid & generator 36 BN36 Good 180 300 80-85 100 100 120-140 50 30 Public grid & generator 37 BN37 Good 300 300 80-85 100 100 120-140 50 37 Public grid & generator 38 BN38 Stopped Public grid & generator 39 BN39 Good 300 300 80-85 100 100 120-140 65 45 Public grid & generator 40 BN40 Good 300 300 80-85 100 100 120-140 68 45 Public grid & generator 41 BN41 Good 300 300 80-85 100 100 120-140 61 45 Public grid & generator 42 BN42 Good 300 300 80-85 100 100 120-140 61 45 Public grid & generator 43 BN43 Good 175 300 80-85 100 100 120-140 54 45 Public grid & generator 44 BN44 Good 190 250 80-85 100 100 120-140 50 45 Public grid & generator 45 BN45 Good 190 300 80-85 100 100 120-140 54 45 Public grid & generator 46 BN46 Good 300 300 80-85 100 100 120-140 54 45 Public grid & generator 47 BN47 Good 300 300 80-85 100 100 120-140 65 45 Public grid & generator 48 BN48 Good 300 300 80-85 100 100 120-140 58 45 Public grid & generator 49 BN49 Good 300 300 80-85 100 100 120-140 65 45 Public grid & generator

Bir Ahmed Wellfield Borehole data Pump data Item Well

No /ID Physical status

Depth (m)

Diameter (mm)

Static water level (m)

Dia. of riser pipe (mm)

Installation depth (m)

Head H (m)

Quantity Q (m/h)

Power P (KW)

Power Source

1 BA14 Good 150 300 48 100 80 65 45 30 Public grid & generator 2 BA15 Good 120 300 50-55 100 80 65 45 30 Public grid & generator 3 BA16 Good 120 300 50-55 100 80 65 45 30 Public grid & generator 4 BA17 Good 120 300 50-55 100 80 65 45 30 Public grid & generator 5 BA18 Good 120 300 50-55 100 80 65 45 30 Public grid & generator 6 BA19 Good 120 300 50-55 100 80 65 45 30 Public grid & generator 7 BA20 Good 120 300 50-55 100 80 65 45 30 Public grid & generator 8 BA21 Good 120 300 50-55 100 80 65 45 30 Public grid & generator 9 BA22 Good 120 300 50-55 100 80 65 45 30 Public grid & generator 10 BA23 Good 120 300 50-55 100 80 65 45 30 Public grid & generator 11 BA24 Good 120 300 50-55 100 80 65 45 30 Public grid & generator 12 BA25 Stopped 13 BA26 Good 150 300 50-55 100 80 70 60 30 Public grid & generator 14 BA27 Good 150 300 50-55 100 80 70 60 30 Public grid & generator 15 BA28 Good 150 300 50-55 100 80 70 60 30 Public grid & generator

- 68 -

The corporation has been determinedly working to increase the well yield of underground wells, a matter regarding which, noticeable results have been observed in recent years. In 2014, the actual well yield reached 114931 cubic meters daily, whereas it has now become 123933 cubic meters daily. This increase in the productivity rate is attributed to the number of wells established and rehabilitated by the corporation during the period from 2015 until now. Additionally, assistance offered by organizations which included providing the corporation with the fuel to operate the wells' pumps contributed in raising the productivity rate.

Despite the recent increase in the productivity rates of water, the administration of wells' fields is still facing many challenges and problems in more than one aspect, which can be surmised as follows:

Several wells went out of service due to the failure of more than 10 pumps as well as the malfunction of more than 15 step down transformers that are responsible for operating the pumps.

The corporation's incapability to perform maintenance works on the pumps as there are not any workshops that specialize in well pumps' maintenance.

Electricity related problems due to the weak power grid in the three fields. Therefore, it is very important to rehabilitate the power network in three fields in order to guarantee constant operation of the fields and minimize the loss in energy caused by the currently weak power network.

16 BA29 Good 150 300 50-55 100 80 70 60 30 Public grid & generator 17 BA30 Good 150 300 50-55 100 80 70 60 30 Public grid & generator 18 BA31 Good 150 300 50-55 100 80 70 60 30 Public grid & generator 19 BA32 Good 150 300 50-55 100 80 70 60 30 Public grid & generator 20 BA33 Good 150 300 50-55 100 80 70 60 30 Public grid & generator 21 BA34 Good 150 300 50-55 100 80 70 60 30 Public grid & generator 22 BA35 Good 150 300 50-55 100 80 70 60 30 Public grid & generator 23 BA36 Good 150 300 50-55 100 80 70 60 30 Public grid & generator 24 BA37 Good 150 300 50-55 100 80 70 60 30 Public grid & generator 25 BA38 Good 150 300 50-55 100 80 70 60 30 Public grid & generator 26 BA39 Good 150 300 50-55 100 80 70 60 30 Public grid & generator 27 BA40 Good 150 300 50-55 100 80 70 60 30 Public grid & generator 28 BA41 Good 150 300 50-55 100 80 70 60 30 Public grid & generator 29 BA42 Good 150 300 50-55 100 80 70 60 30 Public grid & generator 30 BA43 Good 150 300 50-55 100 80 70 60 30 Public grid & generator 31 BA44 Good 150 300 50-55 100 80 70 60 30 Public grid & generator 20 BA45 Good 150 300 50-55 100 80 70 60 30 Public grid & generator 33 BA46 Good 150 300 50-55 100 80 70 60 30 Public grid & generator 34 BA47 Good 250 300 50-55 100 80 70 60 30 Public grid & generator 35 BA48 Good 250 300 50-55 100 80 70 60 30 Public grid & generator 36 BA49 Good 250 300 50-55 100 80 70 60 30 Public grid & generator 37 BA50 Good 250 300 50-55 100 80 70 60 30 Public grid & generator 38 BA51 Good 250 300 50-55 100 80 70 60 30 Public grid & generator 39 BA52 Good 250 300 50-55 100 80 70 60 30 Public grid & generator 40 BA53 Good 250 300 50-55 100 80 70 60 30 Public grid & generator 41 BA54 Good 250 300 50-55 100 80 70 60 30 Public grid & generator 42 BA55 Good 250 300 50-55 100 80 70 60 30 Public grid & generator 43 BA56 Good 250 300 50-55 100 80 70 60 30 Public grid & generator

- 69 -

Many of the pipes used in pumping and lifting in the wellfields are damaged and ruined, especially in Bir Nasser wellfield.

Incapability of the wellfield's management to monitor and account for the produced amounts of water and consumed power for each well.

The table below show the needs which will enable the administration of wellfields to overcome the aforementioned problems and challenges.

Notes Qty Requirements NO To operate the stopped wells and rehabilitate the defective pumps

40 Supplying submersible pump set 1

15 Supply step-down transformers (100KVA)

2

3 Rehabilitate the electrical grid in the wellfields

3

Supply 4'' UPVC riser pipes 4 Supply 5'' UPVC riser pipes 5 The force lines connecting the wells with the reservoirs

Rehabilitate the force lines in Bir Nasser

6

To repair and maintain defective pumps 1 Construct a new maintenance workshop

7

15000 m Supply 120 mm Aluminum wires 8 15000 m Supply 50 mm Copper wires 9 To monitor the production capacity for each well

1 Supply and install a complete water monitoring system

10

To monitor electrical consumption for each well

1 Supply and install monitoring system for electricity consumption

11

Three new buildings are required. One building for each wellfield.

3 Expand the administrative buildings in the three wellfields

12

Reservoirs in Bir Nasser Wellfield

- 70 -

5.2. Reservoirs

The corporation has 34 tanks; 30 are underground while the remainder 4 are elevated tanks. Some of these tanks are very old and require rehabilitation and there are these which sustained significant damage during the armed conflict in the city.

Three underground tanks were completely destroyed and five of them were partially destroyed. Whereas all four elevated tanks were partially destroyed. The table below shows in detail the condition of all the tanks owned by the corporation.

NO

Reservoir name

Type Material Year of construction

Operational Non-Operational

General Condition

Area Serves Comments

1 Ahmed-01 Circular Steel 1955 1000 Bad Abandoned 2 Ahmed-02 Circular Steel 1965 4500 Leakage,

URGENT Rehab Well Collection In use but

leaking 3 Ahmed Circular 2010 2,250 New-good Well Collection 4 Slaughter

House-01 Circular Steel 1965 4,500 Collection

5 Slaughter Hose-02

Circular Steel 1965 4,500 Collection

6 Hiswa-01 Rectangular RCC 6000 7 Hiswa-02 Rectangular RCC 6000 8 Cathedral

Hill-01 Circular Steel 1954 4,500 Little Aden and

surrounding area

9 Cathederal-02

Circular Steel 1954 4,500 Little Aden and surrounding area

10 Nasser Collection-01

Circular Steel 1987 7,500 Good Collection

11 Nasser Collection-02

Circular Steel 1987 7,500 Good Collection

12 Nasser Collection-03

Circular Steel 1967 4,500 Abandoned

13 Nasser Distribution

Elevated Tank

Steel panels

1954 450 Abandoned Upstream Dar Sa'd

Out of service

14 Isthmus-01 Circular Steel 1958 22,500 Good Area 1

Reservoirs in Bir Ahmed Wellfield

- 71 -

15 Isthmus-02 Circular Steel 1959 22,500 URGENT REHAB-Roof fall down

Area1 Out of service

16 Main Pass-01

Rectangular Masonry 1930 5,400 Good Crater

17 Main Pass-02

Rectangular Masonry 1930 6,700 Good Mualla &Tawahi

18 Jebal Hadid-01

Rectangular Steel Panels

1958 2,250 Khormaksar Out of service

19 Jebal Hadid-02

Rectangular Steel Panels

1958 2,250 Khormaksar Out of service

20 Mansura Elevated Tank

Steel Panels

1998 2000 Good West Hashid

21 Abdul-Aziz Elevated Tank

Steel Panels

1958 2,400 Old Housing complexes

Out of service

22 Caltex Circular Steel 1964 4,500 Ships supplies Believed to be privatized

23 Al Shaab Elevated Tank

Steel Panels

1998 1000 Good Madinat Al Shaab Not fully utilized

24 Al Rawdha Circular Steel 1967 4,500 Good Al Rawdha Out of service

25 Gold Mohur

Rectangular Steel Panels

1985 1,250 Good

26 Holkat Rectangular RCC 1990 2,200 Good Presidential property

27 Aroosa Rectangular RCC 1990 2,200 Good Presidential property

28 Moat Rectangular Masonry 1930 899 Old Rock House PS 29 Barrak Hill

(Hospital) Rectangular Masonry 1930 450 Old Barrak Hill

neighborhood

30 Chapel Hill Rectangular Masonry 1930 240 Old Chapel Hill neighborhood

31 Ras Boradli Rectangular Masonry 1930 90 Old Ras Boradli neighborhood

32 Fort Tarshyne

Rectangular Masonry 1930 27 Good Presidential Property

32 Fort Morbut Rectangular Masonry 1930 27 Marine Naval Property

Naval Forces Out of service

33 Ras Marshog

Rectangular Masonry 1930 50 Good Presidential Property

The corporation in cooperation with several humanitarian organizations rehabilitated a number of the partially damaged tanks and built new tanks in place of the completely destroyed ones. Currently, the corporation needs to rehabilitate and rebuild the following tanks:

i. Rehabilitation of Mountain Fuqum reservoir It is one of the old tanks located in Al-Boraiqa directorate – refineries area. The tank is currently out of service and requires immediate rehabilitation. Due to security concerns, accessing the refineries area where the tank is located was not possible.

- 72 -

ii. Rebuilding Abdullatif reservoir on Hadid

mountain Two tanks, each with a capacity of 5000 cubic meters used to reside on Mt. Iron. Both tanks were bombarded during the armed conflict in the city. The corporation needs to build a new tank with a capacity of 5000 cubic meters to substitute the two destroyed tanks.

iii. Rebuilding Al-Barzakh tank The Al-Barzakh station has two tanks with a capacity of 22500 cubic meters. One of these two tanks was partially damaged which the corporation was able to rehabilitate and put it back in service. As for the second tank which was totally destroyed, it has to be entirely rebuilt. The corporation is currently seeking the necessary funding to build a new tank with a capacity of 9000 cubic meters to replace the destroyed tank.

- 73 -

5.3. Water Supply Network

Aden's water supply network is estimated to be 1111 Km long, covers around 86% of the city and involves 128850 connections. The water supply network was constructed over many years during which pipes were selected in accordance with the corporation's budget.

The table below gives a more detailed image about the water network in Aden.

Total length (m) Material Size DN (mm) Transmission (T) or Distribution (D) No

<DN50 Distribution 1 24,038 PE Distribution 1.1 24,203 PVC Distribution 1.2 1,182 AC Distribution 1.3 1,216 CI Distribution 1.4 4,676 GI Distribution 1.5

115 DI Distribution 1.6 87 St Distribution 1.7

DN50 Distribution 2 52,477 PE Distribution 2.1

147,632 PVC Distribution 2.2 3,249 AC Distribution 2.3 8,812 CI Distribution 2.4 4,320 GI Distribution 2.5 177 DI Distribution 2.6

DN80 Distribution 3 8,993 PE Distribution 3.1

67,754 PVC Distribution 3.2 6,032 AC Distribution 3.3 18,357 CI Distribution 3.4 1,002 GI Distribution 3.5 158 Distribution 3.6

DN100 Distribution 4 14,376 PE Distribution 4.1 70,041 PVC Distribution 4.2 81,434 AC Distribution 4.3 20,424 CI Distribution 4.4 1,069 GI Distribution 4.5 543 DI Distribution 4.6

DN150 Distribution 5 23,712 PE Distribution 5.1 45,699 PVC Distribution 5.2 73,183 AC Distribution 5.3 22,664 CI Distribution 5.4

778 GI Distribution 5.5 DN200 Distribution &Transmission 6

1,301 PE Distribution &Transmission 6.1 4,672 PVC Distribution &Transmission 6.2 3,281 AC Distribution &Transmission 6.3 8,080 CI Distribution &Transmission 6.4

42 DI Distribution &Transmission 6.5

- 74 -

DN225 Distribution &Transmission 7 49 PVC Distribution &Transmission 7.1

20,794 AC Distribution &Transmission 7.2 6,359 CI Distribution &Transmission 7.3

DN250 Distribution &Transmission 8 912 PE Distribution &Transmission 8.1

6,263 AC Distribution &Transmission 8.2 2,659 St Distribution &Transmission 8.3

DN300 Distribution &Transmission 9 3,196 PE Distribution &Transmission 9.1 1,650 PVC Distribution &Transmission 9.2

34,234 AC Distribution &Transmission 9.3 8,648 CI Distribution &Transmission 9.4 4,201 Distribution &Transmission 9.5 376 CI DN350 Transmission 10

DN400 Transmission 11 36,088 PE Transmission 11.1 9,051 AC Transmission 11.2 1,593 CI Transmission 11.3 11,514 DI Transmission 11.4

651 St Transmission 11.5 DN500 Transmission 12

3,638 AC Transmission 12.1 215 CI Transmission 12.2

8,229 DI Transmission 12.3 4,578 AC DN525 Transmission 13

DN600 Transmission 14 25,055 PE Transmission 14.1

4 PVC Transmission 14.2 55,345 AC Transmission 14.3

62 DI Transmission 14.4 DN700 Transmission 15

6,985 AC Transmission 15.1 1,230 DI Transmission 15.2

DN800 Transmission 16 121 AC Transmission 16.1

9,534 DI Transmission 16.2 1,009,009 Total

The corporation is currently struggling with many problems, the most important of which is the losses in water distribution networks. Due to damage of some parts of the network, water leakage occurs which requires the corporation to replace these damaged parts. Moreover, illegal and random connections as well as defected meters which deprive the corporation from earning income it needs desperately. Therefore, the corporation is working to replace old and damaged meters and disconnect all illegal connections. Additionally, the corporation aims to expand the water network in order to deliver water services to all parts of Aden.

- 75 -

5.4. Central Laboratory

The water department at the corporation has a specialized central laboratory (located at Al-Barzakh station) for running analysis and tests to monitor the quality of the water and whether it is viable for human use. Unfortunately, the water central laboratory with all its equipment and tools, including the chemical and bacteriological analysis devices were either stolen or damaged during the conflict the city witnessed. As a result, the laboratory no longer performed any analytical tests to monitor the quality of drinking water due to lack of equipment and tools. The laboratory was out of service for a while until it recently received several grants from various humanitarian organizations and local associates which rehabilitated the laboratory and provided the necessary tools and equipment. The table below shows the tools and equipment the laboratory has recently received.

Notes Department Supplied Equipment No chemical department DR3000 Device 1. PH meter 2. Water Salinity meter 3. Water Turbidity 4. bacteriological department Autoclave 5. Samples' incubator 6. Electronic scale 7. Microscope 8. Old oven 9. Devices used in collecting

samples from wells 10.

New equipment for the bacteriological department

- 76 -

However, the central laboratory still needs a Mercury Analyzer device with spare parts in addition to other necessary devices and furniture

Notes Qty Requirements for disinfection units NO Supply one DMA-8242 device 1 DMA-80 Direct Mercury Analyzer Wide Range (DMA8242) 1 More details in Appendix 6 - DMA-80 Wide Range with Large terminal 1660 2 More details in Appendix 6 Laboratorial devices 3 2 Desktop computer (Lenovo) + LaserJet printer (hp) 4 2 Seven Drawer Computer desk 5 4 Fixed Chairs with arm 6 2 Revolving chairs 7 4 Cupboard Iron and Glass cupboard with Tow openings 8

New equipment for the chemical department

- 77 -

5.5. Disinfection Units

In addition to the central laboratory, there are three disinfection units. One of them at the central laboratory and the other units are in the wellfields (Bir Ahmed wellfield and Bir Nasser wellfield). These units used to add chlorine compounds to the water before it is pumped and distributed in the network. Similar to the central laboratory, these units also went out of service since the beginning of the conflict in the city. These units were out of service until Mercy Cure organization provided temporary disinfection units that add chlorine to drinking water; however, these units are only a temporary solution that does not carry out water chlorination within the required amounts, which is why the disinfection units are still in need for three complete disinfection units along with their analysis devices as shown in the table below:

Notes Qty Requirements for disinfection units NO Supply and install three chlorine injection system

3 V notch chlorine injection system to inject chlorine gas to potable water (human use), max. Dose 500 grams per hour. Horizontal pumps to inject chlorine solution to network, 100 m head, 10 m³/h operate by 3 - phase, 415 volts, 50 Hz, power supply with all protection system needs (2) inch pump outlet. pump body stainless steel. All technical documents, operation manual & spare part list must include.

1

3 Replace the current pipes, since these pipes are not suitable for chlorine systems

2

3 Alarming devices 3 3 Fans for sucking gases 4

Disinfection units supplied by Mercy Cure

- 78 -

5.6. Water Pumping Stations

There are eight pumping stations in Aden city that supply water in the water network, one of which is a main station while the rest are substations.

Al-Barzakh Main Pumping Station

Slaughter house Minor Pumping Station

Al-Rawdhah Minor Pumping Station

Al Fatah Minor Pumping Station

Al Tahliah (Al Hiswa) Minor Pumping Station

Al Rowa Minor Pumping Station

Lahej-Tuban Minor Pumping Station

Al Aidroos Minor Pumping Station

The serviced areas in Aden city are supplied by the PCWS using the pressurized water distribution system as follows:

From Al-Manasera and Bir Nasser wellfields

Water is pumped from the wells located in Al-Manasera and Bir Nasser wellfields directly into two steel reservoirs, each with a capacity of 7500 cubic meters which are located in Bir Nasser wellfield. The water in these tanks is then pumped into one of these paths:

Directly into the distribution network which covers (Dar Sa'd, Al-sheikh Othman and some parts of Al-Mansoora)

Al-Barzakh station

From Bir Ahmed wellfields:

Water is pumped form the wells located in Bir Ahmed wellfields directly into two steel reservoirs, each with a capacity of 7500 cubic meters located within the same wellfield. The water in these tanks is then pumped into one of these paths:

Directly into the distribution network which covers some parts of Al-Mansoora.

The slaughterhouse station

From the slaughterhouse station:

The station receives water discharged from the reservoirs in Bir Ahmed wellfields and pumps it through eight different pumps into either the distribution network which covers Al-Sha'b city and some parts in Al-Boraiqa or Al-Barzakh station.

- 79 -

From Al-Barzakh station:

The station receives water from two main lines:

The steel reservoirs in Bir Nasser wellfield

The slaughterhouse station

The station pumps the water through six pumps into distribution reservoirs that cover the first region, which includes Khormaksar, Al-Tawahi, Al-Mu'alla and Crater.

The map in (Appendix 2) shows the water flow from the wellfields to the water distribution network passing through the pumping stations.

Due to the financial challenges with which the corporation has been struggling in recent years, it was not able to perform periodic maintenance on the main pumping stations and substation. This caused severe damage to the pumps and equipment at the pumping stations. As a result, the pumping stations need to obtain the spare parts necessary to maintain the pumps and equipment and have them back in service.

5.7. Operation and Maintenance Materials

Due to how various the operation and maintenance activities of the water department are, maintenance and operation tools and materials are of the most important assets on which the water sector depends to finish its tasks. Unfortunately, the water sector has lost a lot of its operation and maintenance tools and equipment, rendering it incapable of performing maintenance works, such as maintenance of wells pumps, generators, pumping stations, water network, reservoirs, etc. which caused many wells and pumping stations to go out of service. Additionally, the loss of operation tools caused the department of water to become unable to provide constant water supply; the corporation is not able to provide water supply for more than 3 days/week in some areas. On top of all that, this shortage in operation and maintenance tools and equipment prevented the corporation from being able to expand the water network and reach the deprived areas.

In order for the department of water to become able to perform its duties and provide satisfactory water services, the needs listed in Appendix 6.

Notes Qty Requirements No Impeller, Pump repair kit & stator

- Spare parts and maintenance parts 1.

50 Rehabilitate interior and exterior lightening in pumping stations

2.

- 80 -

6. Sanitation System

The establishment of the sewer system in Aden city went through many phases. Following is a brief illustration of each of these phases.

First Phase (Earlier than 1940): Sewage was discharged through canals which were constructed on the backways of the buildings. After that, sewage coming from these backways would reach manholes put at the end of each backway as shown in the figure.

Backway Backway

Sewage gathered at the manholes would then flow into lateral, secondary and main waterways until it reaches sea coast. Seeing as how much see water pollution this system caused, the authorities decided to alter it. Building owners were committed to build basic screening chambers, each building had to have one, the outcome of these screening chambers would then flow across the canals which discharge water into the manholes.

Second Phase (1940-1963): In this stage, the use of Asbestos pipes began with pipes of no more than 24 inches as a replacement of canals. Also, main manholes were rebuilt using concrete as opposed to the masonry used in the old manholes. Additionally, stations of pumping and collecting sewage were established.

Third Phase (1980 – 1985): This stage is known for the establishment of the Kubota's project which improved the sewer network in the second region. The Kubota's project included rehabilitation of the old sewer network, the establishment of a new network for several areas which were denied sanitation services, rehabilitation and establishment of a few pumping stations and the establishment of the first treatment plant which received sewage from the second region and then treated it. It was in this stage that use of main pumping lines made from Ductile Iron with large diameters (200 – 800mm) began.

Fourth Phase (1985 – 1994): Adoption of clay pipes with diameters of 110, 160, 200, 250, and 300mm began in this stage. These pipes were used in all sanitation works of the sewer network, including new connections or replacement of damaged old connections which were made of Asbestos in all areas of Aden.

Fifth Phase (1994 – 2002): During this phase, several projects were carried out that improved the sewer network in Aden, including rehabilitation and expansion of the network in the first region and Al-Boraiqa, construction of Al-Areesh treatment plant which treats sewage coming from the first region as well as Salahuddin treatment plant for treating sewage of Al-Boraiqa and rehabilitation and establishment of several pumping stations.

Manhole

- 81 -

Regarding plastic pipes (UPVC & HDPE), which were first used in 1994 and are still used today, the following provides the specifications of these pipes:

Specifications of polyethylene pipes of various diameters for sewer network UPVC sewer pipes 200 mm C/W Rubber ring jointed socket and spigot with min . PN 10, wall thickness 9.6 mm. (according to DIN 8062, Length (5.8-6) m, (SAS 14&15 / 1996.)

2 UPVC sewer pipes 160 mm. C/W Rubber ring jointed socket and spigot with min. PN 10, wall thickness 7.7 mm. (according to DIN 8062, Length (5.8-6) m, (SAS 14&15 / 1996.)

1

Specifications of HDPE pipes of various diameters for sewer network HDPE PIPES Suitable for Butt fusion welding. - Dia. 600 mm - PN 10. - PE.100. - SDR 17. - Pipe Length 12 m. - Wall Thickness 37.3 mm

5 HDPE PIPES Suitable for Butt fusion welding . - Dia. 250 mm - PN 10. - PE.100 . - SDR 17. - Pipe Length 12 m . - Wall Thickness 14.8 mm

1

HDPE PIPES Suitable for Butt fusion welding. - Dia. 500 mm - PN 10. - PE.100. - SDR 17. - Pipe Length 12 m. - Wall Thickness 29.6 mm

6 HDPE PIPES Suitable for Butt fusion welding. - Dia. 200 mm - PN 10. - PE.100. - SDR 17. - Pipe Length 12 m. - Wall Thickness 11.9 mm

2

HDPE PIPES Suitable for Butt fusion welding. - Dia. 400 mm - PN 10. - PE.100. - SDR 17. - Pipe Length 12 m. - Wall Thickness 23.7 mm

7 HDPE PIPES Suitable for Butt fusion welding. - Dia. 150 mm - PN 10. - PE.100. - SDR 17. - Pipe Length 12 m. - Wall Thickness 9.50 mm

3

HDPE PIPES Suitable for Butt fusion welding - Dia. 300 mm - PN 16. - PE 100 . - SDR 17. - Pipe Length 12 m . - Wall Thickness 28.6 mm

8 HDPE PIPES Suitable for Butt fusion welding. - Dia. 100 mm - PN 10. - PE.100. - SDR 17. - Pipe Length 12 m. - Wall Thickness 6.50 mm

4

- 82 -

6.1. Sewer Network's pipes

The sewer network in Aden is currently estimated to be 391 Km in length, including main, secondary pumping lines as well as the down-sloping-due-to-gravity lines. The following table gives a general idea about the length, size and material of the current sewer network:

No Size Material Total length (mm) (m)

1 DN100 1.1 UPVC 23,497.95 1.2 VC 416 1.3 AC 4819.14 2 DN150 2.1 UPVC 21,451.86 2.2 VC 14125.69 2.3 AC 2170.68 3 DN160 3.1 UPVC 38,839.16 3.2 DCI 18,540.00 3.3 VC 7182.67 3.4 AC 6528.77 4 DN200 4.1 UPVC 58,347.24 4.2 DCI 3,275.00 4.3 VC 31218.09 4.4 AC 25023.6 5 DN225 5.1 UPVC 2,535.75 5.2 DCI 754.00 5.3 VC 5738 5.4 AC 10339.12 6 DN250 6.1 UPVC 18,131.96 6.2 DCI 1,889.00 6.3 VC 8123.02 6.4 AC 623.54 7 DN300 7.1 UPVC 9,941.14 7.2 DCI 1,810.00 7.3 VC 9056.79 7.4 AC 107.71 8 DN350 8.1 UPVC 20.95 8.2 DCI 3,882.00 8.3 VC 2073.76

- 83 -

9 DN400 9.1 UPVC 3,703.59 9.2 VC 5303.25 10 DN500 10.1 UPVC 68.35 10.2 VC 2200.82 11 DN600 11.1 UPVC 1,695.13 11.2 VC 1905.58 12 DN700 12.1 UPVC 1041.38 13 DN800 13.1 UPVC 3,194.17 14 DN900 14.1 VC 1749 15 DN1000 15.1 UPVC 42.00 15.2 DCI 9,504.00 Total 358,869.89

Whereas main force lines are shown as follows:

Main Force Lines Size DN Pipe material Length M From Al-Tawahi to Al- Mu'alla

400 HDPE 2281

From Al-Mu'alla to Khormaksar

630 HDPE 4300

From Crater to Khormaksar

500 HDPE 3780

From Khormaksar to Al-Arish WWTP

1000 HDPE 5000

From Al-sha'ab to Kubota WWTP

400 D.I 4981

From Industrial Area to Kubota WWTP

400 UPVC 2671.5

From Al-Mansoora to Kubota WWTP

800 D.I 3072

- 84 -

The sewer network in Aden is currently struggling with many problems due to several reasons. The most important of these reasons are:

1. Damage of sewer network pipes as they have exceeded their expiration date and due to increase in amounts of wastewater discharged into these pipes as a result of the increase in population.

2. Misuse of sewer network by citizens, as is the case of disposing of kitchens' waste (grease) and sometimes some plastic-made objects through the sewerage both of which can lead to clogging and damage to the pipes and pumps of the network.

Since the crisis of 2011, not only was the corporation negatively affected, but also several equipment and maintenance and operation tools owned by the corporation were damaged. Additionally, the corporation underwent a financial crisis which rendered it unable to provide needs and costs of maintenance and operation.

All these factors caused the network to weaken to the point where sanity sewer overflow became a recurrent problem in some areas of the network. Following is a list containing areas where the network is most damaged and where sanity sewer overflow most occurs as well as areas the sewer network does not cover:

Damaged areas within the sewer network Notes Areas

Crater Old lines for which a study has been made. Old sewerage network 1 1 Old lines for which a study has been made. Old sewerage network 2 2 Old lines for which a study has not been made. She'b Al-Aidaroos neighbourhood 3 Old lines for which a study has not been made. At-Taweela neighbourhood 4 Old lines for which a study has not been made. Al-Harish neighbourhood 5 Old lines for which a study has not been made. Police Station neighbourhood 6 Old lines for which a study has not been made. Queen Arwa St. 7 Old lines for which a study has not been made. Al-Bomees neighbourhood 8 Old lines for which a study has not been made. Central market neighbourhood 9

Al-Mu'alla Old lines for which a study has not been made. Mountainous area near governor office 10 Old lines for which a study has not been made. Radfan mountain neighbourhood 11 Old lines for which a study has not been made. Castro neighbourhood 12 Old lines for which a study has not been made. Issac neighbourhood 13 Old lines for which a study has not been made. Qwareer mountain neighbourhood 14 Old lines for which a study has not been made. Shihab St. 15 Old lines for which a study has not been made. Stadium neighbourhood 16 Old lines for which a study has not been made. Al-Reel neighbourhood 17 Old lines for which a study has not been made. Health center neighbourhood 18 Old lines for which a study has not been made. Al-Kabsa neighbourhood 19 Old lines for which a study has not been made. Hafoon neighbourhood – against Hafoon clinic 20 Old lines for which a study has not been made. October neighbourhood – behind central market 21

Al-Tawahi

- 85 -

Old lines for which a study has not been made. Al-Shawla neighbourhood 22 Old lines for which a study has not been made. Al-Mashala neighbourhood – near the church 23 Old lines for which a study has not been made. Mount. Basuhaib area - separated parts. (Al-

Benjsar slopes & Al-Tawahi slopes) 24

Old lines for which a study has not been made. Discharge line near Al-Tawahi tunnel 25 Old lines for which a study has not been made. Discharge line near Al-Qas Mosque 26 Old lines for which a study has not been made. Al-Rusafi neighbourhood 27 Old lines for which a study has not been made. Al-Rowaimi neighbourhood 28 Old lines for which a study has not been made. The mountainous area on both sides of Al-Qallo'a

tunnel 29

Khormaksar Old lines for which a study has been made. (Study has been handed out to more than one association)

Jamal neighbourhood 30

Old lines for which a study has not been made. Al-Sa'ada neighbourhood 31 Old lines for which a study has not been made. Doctors neighbourhood 32 Old lines for which a study has not been made. Ba Adeeb street 33 Old lines for which a study has not been made. Trading neighbourhood 34

Al-Mansoora Old lines for which a study has not been made. Al-Sisban sewerage network 35 Old lines for which a study has not been made. Department B network 36 Old lines for which a study has not been made. Abdulqawi neighbourhood 37 Old lines for which a study has not been made. Al-Mmdara network 38

Al Sheik Othman Requires expansion (study has been handed out to Oxfam organization)

Technical city 39

Old lines for which a study has not been made. Wadee' Haddad neighbourhood 40 Old lines for which a study has not been made. Pilots neighbourhood 41

Dar-Sa'd Old lines for which a study has not been made. Al-Saila area 42 Old lines for which a study has not been made. Al-Basateen neighbourhood (Block No 21,22&23) 43 Old lines for which a study has not been made. Al-Subaihi area 44 Old lines for which a study has not been made. Embadi's old network 45 Old lines for which a study has not been made. Sameeh's old network 46

Al-Boraiqa Old lines for which a study has not been made. Al-Subaihi's network 47 Old lines for which a study has not been made. Embadi's network 48 Old lines for which a study has not been made. Sameeh's network 49

- 86 -

Areas within the network where sanity sewer overflow occurs the most Notes Areas

Crater She'b Al-Aidaroos neighborhood 1 Bazar'a school 2

Central Bank line 3 Al-Qatee' residential area 4 Al-Khosaf area (Al-Kassara) 5 Al-Khosaf area (Al-Banajel) 6 Al-Aidroos's mosque area 7 Al-Tawaeela St. – from the cisterns to Zakko 8 Al-Tawaeela St. – Al-Ma'sara 9 Saylan St. 10 Al-Sakran St. 11 Al-Sheikh Abdullah St. 12 Al-Haraeesh line 13 Hasan Sa'eed neighbourhood 14 Yemenia airways neighbourhood 15

Al- Mu'alla Issac neighbourhood 16 Al-Deka area 17 Al-Sa'eedi neighborhood – back street 18 Mt. Radfan area – ring street 19

Al-Tawahi Al-Shawla neighborhood 20 Breesly area – Al-Fath 21 Al-Rusafi neighborhood – Al-Zaytoon 22

Khormaksar Airport road – near the aluminum store 23 Al-Salam neighborhood -slaughterhouse 24 Al-Thaybani hotel 25 Dunb' intersection 26 Near Souk Al-Qat 27

Al-Salam neighborhood – Main street 28 Between German embassy and department of

investigation 29

Near MALI institute 30 Near Al-Andalus building 31

Al-Mansoora Backways of all the blocks in Al-Mansoora 32 Old line for the residential blocks – block no.

50 33

Suzuki intersection with the corniche 34 Al-Saysaban neighbourhood 35

- 87 -

Abdulqawi neighbourhood 36 Al-Sheik Othman

Central market 37 Al-Hashemi market 38 Al-Shayla market 39

Dar-Sa'ad Eastern region – Al-Dhale'i neighborhood 40 Blocks no. 1, 2, 3& 4 41 Al-Basateen neighborhood (blocks no. 21-23) 42 Behind the community college 43

Al-Boraiqa Intersection of Osama St. and Al-Rasheed St. 44 Al-Sddeek St. 45 Ba Nafe' line 46 Al-Khaisa area 47 Salahuddin area 48 Inma' area – Towers main line 49 Bilal St. – The large mosque 50

As for areas that are off the network and which sanitations services does not cover, they are as mentioned below:

Deprived areas Notes Areas

Crater No study has been made. Behind Crater main pump 1

Al-Mu'alla No study has been made. Mountain Radfan area 2 No study has been made. Behind the governorate's building – unplanned residential area 3 No study has been made. Al-Aqaba chalets – near oil company's petrol station 4 No study has been made. Mt. Radfan – ring road 5

Al-Tawahi No study has been made. Al-Ayn mountain – western region 6 No study has been made. Aajora area – Hadjiv 7 There is a study has been made Gold Mohur area 8 No study has been made. Mt. Hadjiv– near Al-Jarabi's buildings 9 No study has been made. Fish neighborhood – the mountainous area 10 No study has been made. Fish neighborhood – near Al-Basha'er school 11

Khormaksar No study has been made. Old Nasr area (1) 12 No study has been made. Old Nasr area (2) 13 No study has been made. New Nasr area 14 No study has been made. Al-Areesh area (1) 15 No study has been made. Al-Areesh area (2) 16

- 88 -

No study has been made. Al-Sawlaban area 17 No study has been made. Al-Majdla area 18 No study has been made. Al-Zera'a neighborhood 19 No study has been made. Residential blocks 20 No study has been made. University road 21

Al-Mansoora No study has been made. Fadhl's well area – block no. 10 22 There is a study has been made Fadhl's well area – blocks no. 5-6 23 No study has been made. Al-Kathiri camp 24

Al-Sheik Othman No study has been made. Blocks no. 4, 5, 6, 7 & 8 25 No study has been made. Al-Mmdara – Al-Mahareeq neighborhood 26

Dar-Sa'ad No study has been made. Al-Ribat neighborhood 27 No study has been made. Naser's well area 28 There is a study has been made Ma'sbaeen area 29 There is a study has been made Eastern area – Ghaleel 30

Al-Boraiqa There is a study has been made Al-Hiswa area 31 There is a study has been made Ahmed's well area 32 No study has been made. Al-Farsi neighborhood 33 There is a study has been made Al-Khaisa area 34 No study has been made. Faqm's well area 35 There is a study has been made Al-Kassarat area 36 No study has been made. Al-Roos residential neighborhood 37 No study has been made. Abu-Harba area 38 There is a study has been made The refineries area – residential compound of government

employees 39

No study has been made. Oil's harbor's deck 40

PCWS aims to finish studies regarding damaged areas, areas where sanity sewer overflow occurs the most and deprived areas which the current network does not cover.

Currently, there are several rehabilitation projects targeting damaged areas within the network as well as expansion projects of the current network to cover deprived areas, which the corporation aims to accomplish. These projects are listed in the following table.

Notes Type of intervention Location Qty Unit Required Interventions No Rehabilitation Main region

one 15.3 Km Rehabilitation of all force lines

in the four following Directorates (Crater, Al-Mu’alla, Khormaksar and Al-Tawahi)

1.

- 89 -

Rehabilitation Khormaksar 4 Km Rehabilitation of lateral force lines

2.

Expansion Al-Boraiqa 10.45 Km Construction of a sewage network in the Bair Ahmed region

3.

Expansion Al-Tawahi 4 Km Construction of a sewage network - Gold Mohur

4.

Expansion Al-Mansoora 4 Km Construction of a substitute force line – from Kaltex to Al-Mansoora Main PS then to Kubota's basins

5.

Expansion Al-Boraiqa 2.85 Km Construction of a sewage network, Al-Khaisa (1) - Al-Boraiqa

6.

Expansion Al-Boraiqa 0.5 Km Construction of a sewage network, Al-Khaisa (2) - Al-Boraiqa

7.

Expansion Al-Boraiqa 3.4 Km Construction of a sewage network in Al-Mhram region - Al-Sha'b City

8.

Expansion Al-Sheikh Othman

2.9 Km Construction of a sewage network for blocks 5,6,7,8 - Al-Memdara

9.

Rehabilitation Khormaksar 1.1 Km A sewage network from the Airport intersection, Khormaksar to Alma'asheq – Aden

10.

4 sub-projects

Expansion Dar Sa’d 1.45 Km Construct a sewage network for Dar Sa'd region.

11.

Rehabilitation Al-Boraiqa Replace a pumping line from Al-Shorta's pump station to Code Al-Namer's pump station.

12.

- 90 -

6.2. Manholes

The current sewer network comprises two types of manholes:

1. Main manholes

On the main lines of the network, main manholes are constructed. They are built using reinforced concrete and are isolated from the inside with a rubber layer in order to protect the concrete from the gases that erupt from the sewer water and are also isolated from the outside with a thick layer of tarmac.

2. Sub manholes

Whereas on the sub lines of the network, it is enough to construct manholes that are build using regular concrete and which are isolated from the inside with epoxy and from the outside with a thick layer of tarmac.

As for the manholes' steps, it was found that all the steps used are made of aluminum coated with a layer of zinc and are 185mm in length, which complies with the British specifications BS 1247 part 1.

Lastly, manholes' covers: two types of manholes' covers are used depending on their location:

On roads and public areas, heavy covers with the following specifications are used Heavy Duty Ductile Iron Manhole covers double triangular/circular ventilated cover with security screws. The depth not less than 150mm, clear opening 675x675mm, total mass not less than 150 Kg, the test load 40 tons. All the inspected covers are manufactured according to (BS EN124 Class-A D400-H).

On backways and interior areas, medium covers with the following specifications are used

Medium Duty Ductile Iron Manhole covers: square opening 600x600mm, integral seal provides odor-proof, the covers are secured using 4 screws and Push-fit seal plate, the depth 70mm, total mass not less than 110kg, the test load 25 tons. All the inspected covers are according to (BS EN124).

- 91 -

6.3. Pumping Stations

The city of Aden has 64 pumps; 36 of these pumps are in the first region while the second region has 28. The stations receive sewage from the network, which is later pumped to other main pump stations or directly into the treatment plants. Most these pumping stations were visited as part of the field assessment. Following are detailed assessments of the most important pumping stations the visits included:

Al-Tawahi Main Pumping Station

This station was established in April 2002. The station receives sewage from Al-Tawahi area and then pumps it across a pumping line into Al-Mu'alla main station. The station has 3 dry pumps 65 KW in power. The station is in a good condition, but requires a new generator to operate the pumps during grid blackouts. A specific room has been set up for the generator as the station had received initial approval from several organizations regrading providing a new generation. The station also requires rehabilitation works to be carried out on its administrative building which has become old and damaged.

- 92 -

Al-Mu'alla Main Station

This station was also established in April 2002 as part of Aden's sanitation project. The station receives sewage from Al-Mu'alla as well as sewage delivered from Al-Tawahi main station which it then pumps across a pumping line into Khormaksar main station. Al-Mu'alla station has 3 dry pumps 205 KW in power. Social Fund for Development (SFD) performed rehabilitation works on the station and provided it with its needs in 2018, and the current condition of the station is considered very good. However, the station struggles with electricity blackouts, more so since the backup generator requires maintenance works. Additionally, the basin of the station requires cleaning.

- 93 -

Crater Main Station

Crater main station was established in 2002 as part of Aden's sanitation project. The station receives sewage coming from Crater, which it later pumps across a pumping line into Khormaksar main station. The station has 3 dry pumps 90 KW in power. The station is currently out of service and has been so for longer than 5 years due to damage in the pumping line that delivers to Khormaksar main station. Details regarding the pumping line were included within the needs of Crater station.

- 94 -

Khormaksar Main Station

The Khormaksar station is considered the largest in the first region. It was established in 2002 and receives sewage delivered from all four directorates, which it later pumps into Al-Areesh treatment plant. Khormaksar main station has 3 dry pumps, two of which are 590 KW and the third is 132 KW in power. The station is in a very good condition.

- 95 -

Dar Sa'd Pumping Station

The station was established in January 1986 as part of the Kubota's project. The station receives sewage from the northern part of the Dar Sa'd sewage network and it then pumps it into college pumping station. The station has 3 dry pumps 150 KW in power. The overall condition of the station is very poor and it requires rehabilitation works as well as replacement of the pumps.

College Pumping Station:

The station was established in 1986 as part of the Kubota's project. The station receives sewage coming from some parts in Dar Sa'd directorate as well as sewage delivered from Dar Sa'd old station which it later pumps into Omar Al-Mokhtar station. The station has 3 dry pumps 200 KW in power. The station was rehabilitated in 2013 where one of the station's pumps was replaced. The station has been recently totally rehabilitated by the Emirates Red Crescent and is currently in a very good condition

- 96 -

Omar Al-Moktar Station

The station was established in 1986 as part of the Kubota's project. The station receives sewage from Al-Sheikh Othman as well as sewage delivered from College pumping station, which it later pumps into Al-Mansoora main station. The station has 4 dry pumps 250 KW in power. The station requires rehabilitation works for the building and the bathrooms as well as for the electrical wiring inside the station.

- 97 -

Hadjiv Station – Al-Mu'alla

The station was established in 2006. The station pumps sewage from the Hadjiv area into a down-sloping line – due to gravity – into Al-Mu'alla main station. The station has two small submersible pumps 16 KW in power. The station was rehabilitated by the SFD during the end of 2018.

Al-Fath Station – Al-Tawahi

The station was established in 2006. The station struggles with a major problem caused by the amounts of grease coming from the kitchens of the engineering provision services. The accumulated grease causes a lot of clogging and damage to the screen. The station pumps sewage of the Special Forces area into Al-Tawahi main station using two small submersible pumps of 9 KW in power. In addition to the rehabilitation works the station needs, it must be redesigned in proportion with the amounts of grease it receives.

- 98 -

Al-Kahraba neighborhood Station – Al-Mu'alla

The station is considered as one of the oldest pumping stations in Aden. It is currently out of service and has been so for over 5 years. The station requires full rehabilitation, including replacement of the old pump that is 2.2 KW in power.

99

The table below shows detailed descriptions of all pumping stations in Aden city.

District One Terminal Data Pump Data

No Pumping Station Location PS in operation

Productivity (m/day)

Energy consumption kw/month

Pump type No. of pumps

Pump flow(L/s)

Pump Head(m)

Power (kw)

Pumps Operating hours per day

1 The main station Crater Apr.2002 4608 - Subm.vert.dry 3 160 20 90 8 2 AL-Aidaroos Crater 2003 680.4 301 Wet Well Subm 1 27 8 3 7 3 AL-Bomess Crater 2008 264.9 - Wet Well Subm. 2 35 18 6 8 4 Huqaat Crater 2008 280.8 884 Wet Well Subm. 2 40 18 5 6 5 Seera Crater 2007 414 2007 Wet Well Subm. 2 30 11 4 5

6 The main station Khormaksar Apr.2002

17640 - Subm.vert.dry 2 700 38 540

7 Replacement Subm. vert.dry 1 375 26 132

7 White City (B) Khormaksar Sep2006 1618.5 Wet Well Subm. 2 69 15 6 8 8 H Khormaksar Sep2006 604.8 338 Wet Well Subm. 1 14 8 2 12 9 Administrative base(15) Khormaksar Sep2006 403.2 127 Wet Well Subm. 2 16 8 2 7 10 School (16) Khormaksar Sep2006 216 Wet Well Subm. 1 15 17 7 5 11 October (J) Khormaksar Sep2006 1562.4 1.461 Wet Well Subm. 2 110 10 16 14 12 AL-Muror (10) Khormaksar Sep2006 180 208 Wet Well Subm. 1 10 11.5 6 5 13 AL-Nagda (11) Khormaksar Sep2006 57.6 Wet Well Subm. 2 4 8 2.2 4 14 Hospital republican (OLD) Khormaksar Sep2006 188.8 541 Wet Well Subm. 1 30 8 3 4 15 Gamal (P) Khormaksar Sep2006 737.28 1.800 Wet Well Subm. 1 131 14 22 16 16 Bader camp (OLD) Khormaksar Sep2006 374.4 Wet Well Subm. 1 20 8 2.2 8 17 C Khormaksar Sep2006 1584 835 Wet Well Subm. 1 100 13 16 8 18 Omar-ALmuktar (G) Khormaksar Sep2006 2462.4 2.442 Wet Well Subm. 2 75 17.3 16 12 19 M Khormaksar Sep2006 567 Wet Well Subm. 1 45 8 4 7

100

20 L Khormaksar Sep2600 518.4 854 Wet Well Subm. 1 40 16 9 8 21 Suqatra (E) Khormaksar Sep2006 594 739 Wet Well Subm. 1 35 9 3 10 22 Hai-Alsalam (06) Khormaksar Sep2006 132.5 397 Wet Well Subm. 2 20 7 1.3 8 23 Hai -Alsalam (07) Khomaksar Sep2006 702.7 Wet Well Subm. 2 50 15 6 16 24 Hai-Alsalam (08) Kormaksar Sep2006 127 193 Wet Well Subm. 2 20 7 1.3 7 25 Faculty of Arts Khormaksar Sep2006 270 Wet Well Subm. 2 30 14 6 5 26 Airport (1) Khormaksar Sep2006 180 Wet Well Subm. 1 30 10 2.2 5 27 Airport (2) Khormaksar Sep2006 144 Wet Well Subm. 1 30 10 2.2 4 28 The main station Al- Mu'alla Al-Mu'alla Apr2002 9396 59.400 Sub.vert.dry 3 350 40 205 9 29 Hadjiv (HU) Al-Mu'alla Sep2006 1287.5 228 Wet Well Subm. 2 40 9 16 12 30 Pepsi (OB) Al-Mu'alla Sep2006 174.09 662 Wet Well Subm. 2 20 8 7 6 31 Electricity (OLD) Al-Mu'alla OLD 181.4 Wet Well Subm. 1 170 23 2.2 4 32 The main station Tawahi Apr2002 2937.6 100.000 Sub.vert.dry 3 40 17 65 8 33 AL-Fateh (03) Tawahi Sep2006 1084.3 2.300 Wet Well Subm. 2 20 7 9 12 34 Arosa (02) Tawahi Sep2006 151.2 268 Wet Well Subm. 2 35 10 1.3 8 35 AL-Asmaak (OLD) Tawahi OLD 648 268 Wet Well Subm. 1 30 10 6 6 36 SOUTH AREA Tawahi OLD 151.2 - Wet Well Subm. 1 5.25 13 1.3 8

101

District Two Terminal Data Pump Data

No Pumping Station

Location PS in operation Productivity (m/day)

Energy consumption kw/month

Pump type No. of pumps

Pump flow(L/s)

Pump Head(m)

Power (kw)

Pumps Operating hours per day

1 Al-Mansoora Main S.

Al-Mansoora Rehb.Kubota project Jan 1986 20160 89380

Ver, dry with universal joint shaft

2 280 28 150 20

Replacement Abs. Subm. ver dry 1 160 25.1 132 2 Abbas Al-Mansoora 2009 8640 22969 Abs. Subm. ver dry 2 200 16 48 12

3 Omar Al-Mukhtar

Al-Sheikh Othman

Rehb.Kubota project Jan 1986

6544.8 18781 Ver, dry with universal joint shaft

4 101 8.9 22 18

4 Collage Dar Sa'd

Rehb.Kubota project Jan 1986

4612 10325

Ver, dry with universal joint shaft

3 91.5 5.6 15 14

Replacement Grandfos Subm. Vert. dry

1 166.7 10 27.4

5 Al-Memdara (old)

Al- sheikh Othman

Rehb.Kubota project Jan 1986

1700 37448

Ver, dry with universal joint shaft

2 29.5 11 15 16

Replacement Grandfos Subm. Vert. dry

1 166.7 10 27.4

6 Al-Durian Al-Mansoora Rehb.Kubota project Jan 1986

857 2008 Ver, dry with universal joint shaft

3 17 10 7.5 14

7 Dar Sa'd (Old)

Dar Sa'd Rehb.Kubota project Jan 1986

1350 1842 Ver, dry with universal joint shaft

3 25 8 7.5 15

8 Al-Teqania Khormaksar Sep2006 216 Wet Well Subm. 15 17 7 18

9 Kubota Old P.S..

3240 7003 Wet Well Subm. 1 50 20 18.5

18 Rehb. New P.S. ABS Wet Well Subm. 2 - - -

10 Al-Burayhi Al-Mansoora 2005 151 195 Wet Well Subm. 1 7 14 3 6

102

11 Al-Memdara (New)

Al-Sheikh Othman

2005 1008 1915 Wet Well Subm. 1 20 17.5 6 14

12 Dar Sa'd Dar Sa'd 2005 432 982 Wet Well Subm. 2 15 7.4 2.2 8

13 Al-Sha'b Main S.

Al-Sha'b Old 2520 2583 Wet Well Subm. 2 50 25 18.5 14

14 Abu-Harba Al-Sha'b 2005 1296 6265 Wet Well Subm. 2 70 36 18.5 12

15 Al-Sakania Area

Al-Sha'b Old 216 94 Wet Well Subm. 2 20 10 3 6

16 University Al-Sha'b 2004 259 252 Subm. Vert. dry 2 12 13 11 6

17 Class A Main S.

Al-Boraiqa 2004 3180 - Wet Well Subm. 3 73.6 12 30 12

18 B -Class Al-Boraiqa 2004 259 - Wet Well Subm. 1 12 13.6 3 6

19 The – Market C- Class

Al-Boraiqa V. Old

1836 - Subm. Vert. dry 1 30 12 9

17 Renovation Wet Well Subm. 1 60 16 18.8

20 Police Area Al-Boraiqa V. Old 567 - Wet Well Subm. 1 20 15 13 8

21 Al-Sheikh Bander

Al-Boraiqa V. Old 302 - Wet Well Subm. 1 20 18 9 7

22 Salah Aldien 1

Al-Boraiqa 2003 126 - Wet Well Subm. 1 20 14 3 5

23 Salah Aldien 2

Al-Boraiqa 2003 252 - Wet Well Subm. 1 20 14 3 10

24 Salah Aldien 3

Al-Boraiqa 2003 196 - Wet Well Subm. 1 30 10 2.2 8

25 Salah Aldien 4

Al-Boraiqa 2003 1296 - Wet Well Subm. 2 50 24 9 12

103

From field visits and interviews with technicians and engineers at the pumping stations, operation problems of pumping stations which cause sanity sewer overflow in some areas can be surmised as follows:

1. Adoption of submersible pumps at many of the pumping stations as a modern system instead of using dry pumps, which turned out to be incompatible considering the conditions under which these pumps operate. Submersible pumps are used when the water being pumped is clear of any sediments or residues which tend to obstruct these pumps from operating properly, unlike how the water in the tanks at the pumping stations was found.

2. The absence of screening chambers at some of the stations, which are used to prevent sediments from flowing with the sewage, thus causing constant malfunctions of the pumps and sometimes leading to failure of the engines of the pumps.

3. Due to constant malfunctions of pumps as well as going many pumps out of service, backup pumps and spare parts became needs of great urgency.

4. Damage of some of the sensitive electrical spare parts on the operating panels due to humidity and gases erupting from the open tanks of the stations.

5. The absence of backup pumping lines at the sub pumping stations to discharge in emergencies.

The table below shows the needs of the pumping stations:

Type of work Location Requirements No Rehabilitation Al-Mu’alla Complete rehabilitation for Al-Kahraba' (Hadjiv) PS 1 Rehabilitation Al-Tawahi Complete rehabilitation for Al -Fateh PS 2 Rehabilitation Al-Mansoora Complete rehabilitation for Al -Mansoora main P.S 3 Rehabilitation Al-Mansoora Complete rehabilitation for Abbas P.S. 4 Civil work Crater Construct a fence and replace the main gate for Crater MPS 5 Civil work Khormaksar Construct a fence with gates for L PS 6 Civil work Khormaksar Rehabilitate the buildings of old pumping stations (M, Al-

Salam6&8, October, Soqatra, L, Badr, Jamal, Omar Al-Mukhtar and C)

7

Supplement 8 directories Supply screen chambers for all vert. pumps 8 Civil work Khormaksar Rehabilitate the tank of Bader PS 9 Supplement Khormaksar Supplying centrifugal pumps (October, Omar Al -

Mukhtar, Soqatra, Al -Salam 7, Jamal) 10

Supplement 8 directories Supply submersible pumps with various capacities 11

104

6.4. Treatment Plants

Up until the mid-eighties of the past century, sewage of the city used to be discharged through the main pumping stations directly into the sea causing significant harm to the marine environment. Consequently, the corporation started implementing effective measures of positive impacts on the environment, which included establishing treatment plants. This step did not only ensure against damaging the marine environment, but it was also beneficial in terms of providing irrigation sources for trees and plants in afforestation sites inside the city, which require treatment of sewage water per Yemeni and international specifications for treated wastewater used in irrigation purposes.

There are currently three treatment plants in Aden that receive and treat sewage coming from the sewer network and pumping stations and according to which the sewer network in Aden was divided into three areas as follows:

The north western area, which encompasses part of Al-Boraiqa directorate (Al-Sha'b city), Al-Sheikh Othman, Dar Sa'd and Al-Mansoora directorates. The sewage coming from these areas is discharged into Kubota's treatment plant.

The eastern area of Aden reaching the airport of Aden, which encompasses Crater, Al-Mu'alla, Al-Tawahi and Khormaksar directorates. The sewage coming from these areas is discharged into Al-Areesh treatment plant.

Sewage coming from Al-Boraiqa is discharged directly into the sea, except sewage that is brought in from Salah Aldien which is treated at Salah Aldien treatment plant.

All three treatment plants share the same operation method, which is explained as follows:

Screen: to separate large solids. Grit chamber is not applied because no mechanical parts exist and therefore no harm of accumulation of sand is expected at the anaerobic pond.

Anaerobic pond: acts in both ways, as a primary settling tank and for anaerobic treatment with a retention time that should not be higher than 5 days. In addition, the pond acts as a sludge digester through the anaerobic bacteria with a retention time of at least 2 months. The settled sludge at the anaerobic ponds is transferred to the drying beds.

Facultative ponds with 18 days retention times. BOD load is degraded by means of aerobic bacteria grown at the upper part of facultative ponds. BOD concentration at the outlet is expected to be further decreased in the maturation ponds which will also decrease the pathogen bacterial and helminth eggs.

Screen Anaerobic

Ponds Facultative

Ponds Maturation

Ponds Inlet Effluent

Sludge drying beds

105

The table below shows the actual and design capacity of the three treatment plants:

Q in m3/day Treatment System WWTP Current Estimated Design 18,000 70,000 Waste Stabilization

Pond Al Arish

35,000 25,000 Kubota (Al Shaab) 5,000 5,000 Salah Aldien 58,000 100,000 Total

6.4.1. Al-Mansoora Treatment Plant – Kubota

Established in 1985, Kubota's treatment plant is considered the first treatment plant to have been built in the city by the Japanese company Kubota. It receives sewage coming from the second region which is pumped through the main pumping station, the station in the industrial area in Al-Mansoora and the station in Al-Sha'b city, while the treated water is pumped into the neighboring natural reserve of Al-Hiswa.

The table below shows design details of Kubota's treatment plant

Value Unit Elements No 25,375 m3/day Hydraulic Load 1 5,535 kg/day Organic Load 2 123,000 No. Beneficiaries 3 360 mg/l BOD5 4 288 g/m3/day Volumetric Loading 5 290 kg/ha.day Surface Loading 6

106

The plant was designed in the early eighties of the past century with an allowable capacity of 20000 cubic meters based on the urban sprawl and growth standards determined then. However, the unexpected rise in population and structures which occurred after 1990 caused the volumetric and specific loads of wastewater brought into the treatment plant to grow exponentially, where the current actual load on the station is estimated to be around 35000 cubic meters, which means the station is overloaded with 140% of its design capacity. In addition, acts of robbery and theft of all editorial offices and laboratory's equipment during the last conflict the city of Aden witnessed caused the treatment plant to deteriorate and lessen its efficiency by 40%.

Following are detailed explanations of the current problems with which Kubota's treatment plant struggles

The absence of protection around the plant and weakness of the main gates which allows some animal and/or unauthorized personnel to enter to the basins area, which could pose danger to their lives.

The volumetric loading of anaerobic bonds is overloaded with 125% of the rated capacity.

Increase in the surface loading of facultative bonds is overloaded with 240% of the rated capacity which leads to: - Increase the growth of anaerobic bacteria - Decrease the efficiency of maturation bonds - Pollute the effluent of the plant.

107

Damage of the laboratory and editorial offices buildings at the plant and loss of all necessary tools and equipment.

In order to increase the plant's efficiency and improve the quality of the treated water used in irrigation and water of Al-Hiswa natural reserve, the plant requires the following needs shown in the table below:

Notes Type of Work Requirements No

Civil Works

Construct a fence with gate 1 Rehabilitate the administration office 2 Rehabilitate the laboratory 3 Rehabilitate the damaged part of the ponds 4

Supplement Equip the laboratory with necessary devices 5

Furnish the administration 6 Install flow rate measuring devices 7 Maintenance Clean the screen, basins and bonds of the plant 8

108

6.4.2. Al-Arish Treatment Plant

In 2000, as part of Aden's sanitation project – the first phase treatment ponds were constructed for the second treatment plant in Aden located in Al-Arish area with an allowable capacity of 70000 cubic meters and receives sewage from the first region, which include Crater, Khormaksar, Al-Mu'alla and Al-Tawahi directorates. Sewage from these areas is pumped into Khormaksar main pumping station, which in turns pumps the sewage of the first region into Al-Areesh treatment plant.

The plant was designed in 1996 to receive sewage coming from the first region's directorates for 15 years (1998-2013) with the following design specifications:

The plant is made up of two operation lines. Each line consists of anaerobic pond, facultative pond and a maturation pond. Only one line is operated with a 35000 m3/day flowrate, 10920 Kg/day organic load and 312mg/l BOD5.

Value Unit Elements No 70,000 m3/day Hydraulic Load 1 21,840 kg/day Organic Load 2 240,480 No. Beneficiaries 3 312 mg/l BOD5 4 113 g/m3/day Volumetric Loading 5 382 kg/ha.day Surface Loading 6

109

The WWTP was totally damaged during the conflict where both the editorial offices building and laboratory were targeted by air force.

The plant was also neglected which caused ponds and canals to become clogged.

Currently, the treatment plant is out of service and the sewage it receives, it discharges directly into the sea without any treatment. With that said, the seawater is contaminated with 20000 cubic meters of sewage every day, which makes rehabilitation of the treatment plant extremely urgent.

110

In order to rehabilitate the plant and improve the quality of the water the plant discharges into the sea which could be used in irrigation of afforestation sites, the plant requires the needs shown in the table below

Notes Type of Work Requirements No

Civil Works Re-construct the administration building 1

Re-construct the laboratory building 2

Supplement Equip the laboratory with necessary devices 3

Furnish the administration building 4 Install flow rate measuring devices 5 Maintenance Clean the screen, basins and bonds of the plant 6

6.4.3. Salah Aldien Treatment Plant – Al-Boraiqa

After the establishment of both Kubota and Al-Areesh treatment plants, Al-Boraiqa became the only area where sewage was directly discharged into the sea. Therefore, the LCWS in cooperation with the SFD as the financer of the project established a treatment plant that would lessen the amount of wastewater being discharged into the sea. In 2002, Salah Aldien treatment plant was established which serves part of Al-Boraiqa directorate (Salah Aldien District) with an allowable capacity of 5000 cubic meters. This plant is considered as the last treatment plant to have been established in Aden city.

Salah Aldien treatment plant was designed in a basic manner where it contains only 3 ponds as follows:

Two anaerobic ponds with depth of 2.5m and capacity of 600 cubic meters.

Facultative pond with depth of 1.5m and capacity of 4000 cubic meters.

111

The plant does not own any editorial offices or laboratories. It also faces many problems, such as the unplanned urban sprawl on account of the area surrounding the ponds as well as clogging of ponds and canals as a result of not cleaning the ponds, which also lowered the plant's efficiency.

Because of the current condition of the plant, it has become surrounded with residential blocks from all sides causing the current location of the plant to become unsuitable and it is recommended that the plant is relocated somewhere away from the residential blocks and that it should be equipped with its own editorial offices and laboratory.

However, for purposes of rehabilitation the plant and having it back in service, the following needs are required:

Notes Type of Work Requirements No Supplement Install flow rate measuring devices 1 Maintenance Clean the screen, basins and bonds of the plant 2

Satellite photos of the treatment plants

Kubota WWTP Al-Arish WWTP Salah Aldien WWTP

112

6.5. Operation and Maintenance Materials

The department of sanitation lost a lot of its operation and maintenance tools during the period from 2011 until now. Due to the limited income the corporation manages to earn, it was not able to make up for this severe loss in equipment and machines.

The sanitation department has 12 sewage pumping stations and 17 sewage trucks most of which have become damaged and out of service. In addition, spare parts and backup pumps previously owned by the department of sanitation were subjected to acts of robbery and theft during the conflict the city witnessed. the table below shows the necessary equipment and machines for the corporation to become able to perform its operation and maintenance works successfully.

Notes Type of intervention

Location Qty Unit Required Interventions No

Supplement 8 Directorates 5000 NO Supplying drain rods used for clearing clogged manholes

1.

3-meter-long excavators

3 NO Provide urgent vehicles and equipment required to implement sewerage network works

2.

6-meter-long excavators

3

Bobcat 3 Loaders 5 4-meter-long dump trucks

8

113

3-meter-long dump trucks

8

Hilux - single cabin 16 4 No Supplying vacuum sewage

suction trucks 12,000 Lit. 3.

10 No Supplying mobile pump units of 6" and 8"

4.

Supplement 8 Directorates 20 Km Supplying pipes of various diameters (160, 200, 250, 300)

5.

Supplement 8 Directorates - - Supplying spare parts (various pulleys, bumpers, elbows) made from cast iron

6.

114

7. Urgent Interventions for Cleaning Fund

No Sub-Project Name Estimated Cost ($)

First: Rehabilitation Intervention

1 The Dump Site in Bair Na’ama - Al-Boraiqa

1.1 Rehabilitate the buildings and facilities in Bair Na’ama’s dump 3,329

2 Khormaksar and Al-Mansoora Maintenance Workshops

2.1 Rehabilitate Khormaksar Maintenance Workshop 8,654.5

2.2 Rehabilitate Al-Mansoora Maintenance Workshop 6,955

3 Cleaning Administrations in Directorates

3.1 Rehabilitate Cleaning Administration in Al-Tawahi 7,784

3.2 Construct a New Building for Cleaning Administration in Al-Mu'alla 25,651

3.3 Rehabilitate Cleaning Administration in Crater 12,863.5

3.4 Rehabilitate Cleaning Administration in Khormaksar 10,374.9

3.5 Rehabilitate Cleaning Administration in Al-Mansoora 11,525.68

3.6 Reconstruct the building of Cleaning Administration in Al-Boraiqa 25,651

3.7 Rehabilitate Cleaning Administration in Al-Sheikh Othman 8,222.6

3.8 Rehabilitate Cleaning Administration in Dar Sa'd 9,290.5

Sub-Total 130,301.68

No Sub-Project Name Estimated Cost ($)

Second: Supporting Assets and Supplying Vehicles Intervention

1 Support and Improve Cleaning Fund operations in Aden City

1.1 Supply Required Vehicles and Containers for Cleaning Administrations in Directorates

830,000

1.2 Supply Required equipment for Bir Na'ama Dumpsite 740,000

1.3 Supply Mobile Maintenance Workshops 220,000

Sub-Total 1,790,000

Total 1,920,301.68

115

First: Rehabilitation Interventions

1. The Dump Site in Bair Na’ama - Al-Boraiqa

BoQ for rehabilitate the buildings and facilities in Bair Na’ama’s dump

No Description Unit Qty Unit Cost ($)

Total Cost ($)

Notes

1 Building

No building work is required

2 Windows

2.1 Wooden windows (2.3m X 1.5m) No 4 180 720

2.2 Wooden windows (1.5m X 0.6m) No 1 75 75

2.3 Wooden windows (1.1m X 1.36m) No 2 140 280

Sub-Total 1,075

Buildings and other facilities, such as administration, bathroom and security room require

rehabilitation and renovation works.

The recycling hangar in the dump site is out of service and needs to be completed.

116

3 Doors

3.1 Wooden doors No 4 220 880

Sub-Total 880

4 Electricity

4.1 Ceiling fans No 1 30 30

4.2 Twin fluorescent lamps with fixture base

No 6 7 42

4.3 Cable (1.5 mm) Roll 3 9 27

4.4 Cable (4mm) Roll 3 20 60

4.5 Plugs (2 lines) No 4 1.5 6

4.6 Switches No 6 1.5 9

4.7 Trunking No 5 1.5 7.5

4.8 Labor's cost LS 100 100

Sub-Total 281.5

5 Plumbing

5.1 Squat toilet with its accessories No 1 40 40

5.2 Face wash sink No 1 40 40

5.3 Sink tap No 1 12 12

5.4 Taps No 2 3 6

5.5 Shower No 1 3.5 3.5

5.6 Pipes (0.5 inches) m 6 2.5 15

5.7 Elbows (0.5 inches) No 10 0.6 6

5.8 T-joint pipes (0.5 inches) No 5 0.6 3

5.9 Water Tank (1000 liters) No 1 82 82

5.10 Labor's cost LS 150 150

Sub-Total 357.5

6 Painting

6.1 Water paint (Crown) Bucket 5 42 210

117

6.2 Labor's cost LS 150 150

Sub-Total 360

7 Occupational Health and Safety

Wor

kers

Builders Painters Plumbers Electricians Mechanics Other Total

0 2 1 1 0 0 4

OHS Tools and Requirements

No Description Unit Qty Unit Cost Total Cost Notes

7.1 Climbing shoes for electrical works No 1 50 50

7.2 High quality safety gloves suitable for electrical works

No 1 15 15

7.3 High quality long neck rubber Safety shoes suitable for labors who works in sewage

No 1 35 35

7.4 High quality safety rubber gloves suitable for labors who works in sewage (long to over the elbow and close from top)

No 1 25 25

7.5 Face mask for work in dust and smoky areas

No 2 25 50

7.6 High quality rubber safety shoes short neck

No 2 30 60

7.7 High quality safety gloves suitable for building works

No 2 20 40

7.8 High quality safety helmet with eye protection

No 4 15 60

7.9 High quality safety vest (can be used by day time and night)

No 4 10 40

Sub-Total 375

Total Cost 3,329

118

2. Maintenance Workshops

Khormaksar Maintenance Workshop

Al-Mansoora Maintenance Workshop

Main buildings of the workshops are partially damaged and bathrooms require urgent

maintenance.

119

BoQ for rehabilitate the buildings and bathrooms in Khormaksar Maintenance Workshop

No Description Unit Qty Unit Cost ($)

Total Cost ($)

Notes

1 Building (renovate the roof of replacing oils chamber)

1.1 Zinc sheets (4m X 2m) No 5 20 100

1.2 Wooden posts (3cm X 3cm X 4m) No 8 18.5 148

1.3 Wooden posts (3cm X 3cm X 2.5m) No 24 15 360

1.4 Nails Packet 1 1.5 1.5

1.5 Labor's Cost LS 120 120

Sub-Total 729.5

2 Windows

2.1 Wooden windows (80cm X 80cm) No 2 100 200

2.2 Aluminum windows (60cm X 40cm) No 1 80 80

2.3 Wooden windows (1.1m X 1.36m) No 2 140 280

Sub-Total 560

3 Doors

3.1 Wooden doors No 5 220 880

3.2 Iron doors (2m X 1.5m) Pair 1 450 450

Sub-Total 1,330

4 Electricity

4.1 Ceiling fans No 4 30 120

4.2 Twin fluorescent lamps with fixture base

No 50 7 350

4.3 Cable (1.5 mm) Roll 12 9 108

4.4 Cable (4mm) Roll 3 20 60

4.5 Plugs (2 lines) No 5 1.5 7.5

4.6 Plugs (3 lines) No 5 1.7 8.5

4.7 Plugs (4 lines) No 5 2.3 11.5

4.8 Switches No 50 1.5 75

120

4.9 Trunking No 6 1.5 9

4.10 Labor's cost LS 500 500

Sub-Total 1,249.5

5 Plumbing

5.1 Squat toilet with its accessories No 1 40 40

5.2 Face wash sink No 1 40 40

5.3 Sink tap No 1 12 12

5.4 Taps No 2 3 6

5.5 Shower No 1 3.5 3.5

5.6 Pipes (0.5 inches) m 6 2.5 15

5.7 Elbows (0.5 inches) No 10 0.6 6

5.8 T-joint pipes (0.5 inches) No 5 0.6 3

5.9 Water Tank (1000 liters) No 1 82 82

5.10 Labor's cost LS 150 150

Sub-Total 357.5

6 Painting

6.1 Water paint (Crown) Bucket 8 42 336

6.2 Labor's cost LS 250 250

Sub-Total 586

7 Office furniture

7.1 Sliding iron cupboards No 2 140 280

7.2 Swivel chairs No 2 90 180

7.3 Desk No 2 180 360

7.4 Desktop computer (Lenovo) + Printer (hp)

No 1 1600 1600

7.5 Stationary chairs No 3 88 264

7.6 Hard disk (1 Tera) No 1 100 100

7.7 USB flash memories No 5 10 50

121

7.8 Software for managing stores No 1 300 300

Sub-Total 3,134

8 Occupational Health and Safety

Wor

kers

Builders Painters Plumbers Electricians Mechanics Other Total

3 2 1 1 0 0 7

OHS Tools and Requirements

No Description Unit Qty Unit Cost Total Cost Notes

8.1 Climbing shoes for electrical works No 1 50 50

8.2 High quality safety gloves suitable for electrical works

No 1 15 15

8.3 High quality long neck rubber Safety shoes suitable for labors who works in sewage

No 1 35 35

8.4 High quality safety rubber gloves suitable for labors who works in sewage (long to over the elbow and close from top)

No 1 25 25

8.5 Face mask for work in dust and smoky areas

No 2 25 50

8.6 High quality rubber safety shoes short neck

No 2 30 60

8.7 High quality safety gloves suitable for building works

No 5 20 100

8.8 High quality safety shoes suitable for labors who work in workshops, buildings… etc.

No 3 50 150

8.9 High quality safety helmets No 7 15 105

8.10 High quality safety vest (can be used by day time and night)

No 4 10 40

8.11 High quality safety cloths suitable for electrical works, mechanical works, building works… etc.

No 3 20 60

8.12 High quality First Aid Kit No 1 25 25

Sub-Total 715

Total Cost 8,654.5

122

BoQ for rehabilitate the buildings and bathrooms in Al-Mansoora Maintenance Workshop

No Description Unit Qty Unit Cost ($)

Total Cost ($)

Notes

1 Building

No building work is required

Sub-Total

2 Doors

2.1 Wooden doors No 2 220 440

2.2 Iron doors (2m X 1.5m) Pair 1 450 480

Sub-Total 920

3 Electricity

3.1 Ceiling fans No 4 30 120

3.2 Twin fluorescent lamps with fixture base

No 50 7 350

3.3 Cable (1.5 mm) Roll 12 9 108

3.4 Cable (4mm) Roll 3 20 60

3.5 Plugs (2 lines) No 5 1.5 7.5

3.6 Plugs (3 lines) No 5 1.7 8.5

3.7 Plugs (2 lines) No 5 2.3 11.5

3.8 Switches No 50 1.5 75

3.9 Trunking No 6 1.5 9

3.10 Labor's cost LS 500 500

Sub-Total 1,249.5

4 Plumbing

4.1 Squat toilet with its accessories No 1 40 40

4.2 Face wash sink No 1 40 40

4.3 Sink tap No 1 12 12

4.4 Taps No 2 3 6

4.4 Shower No 1 3.5 3.5

123

4.5 Pipes (0.5 inches) m 6 2.5 15

4.6 Elbows (0.5 inches) No 10 0.6 6

4.7 T-joint pipes (0.5 inches) No 5 0.6 3

4.8 Water Tank (1000 liters) No 1 82 82

4.9 Labor's cost LS 150 150

Sub-Total 357.5

5 Painting

5.1 Water paint (Crown) Bucket 8 42 336

5.2 Labor's cost LS 250 250

Sub-Total 586

6 Office furniture

6.1 Sliding iron cupboards No 2 140 280

6.2 Swivel chairs No 2 90 180

6.3 Desk No 2 180 360

6.4 Desktop computer (Lenovo) + Printer (hp)

No 1 1600 1600

6.5 Stationary chairs No 3 88 264

6.6 Hard disk (1 tera) No 1 100 100

6.7 USB flash memories No 5 10 50

6.8 Software for managing stores No 1 300 300

3,134

7 Occupational Health and Safety

Wor

kers

Builders Painters Plumbers Electricians

Mechanics Other Total

3 2 1 1 0 0 7

OHS Tools and Requirements

No Description Unit Qty Unit Cost Total Cost Notes

7.1 Climbing shoes for electrical works No 1 50 50

7.2 High quality safety gloves suitable for electrical works

No 1 15 15

124

7.3 High quality long neck rubber Safety shoes suitable for labors who works in sewage

No 1 35 35

7.4 High quality safety rubber gloves suitable for labors who works in sewage (long to over the elbow and close from top)

No 1 25 25

7.5 Face mask for work in dust and smoky areas

No 2 25 50

7.6 High quality rubber safety shoes short neck

No 2 30 60

7.7 High quality safety gloves suitable for building works

No 5 20 100

7.8 High quality safety shoes suitable for labors who work in workshops, buildings… etc.

No 3 50 150

7.9 High quality safety helmets No 7 15 105

7.10 High quality safety vest (can be used by day time and night)

No 4 10 40

7.11 High quality safety cloths suitable for electrical works, mechanical works, building works… etc.

No 3 20 60

7.12 High quality First Aid Kit No 1 25 25

Sub-Total 715

Total Cost 6,955

125

3. Cleaning Administrations in Directorates

3.1. Cleaning Administration in Al-Tawahi

Bathrooms need rehabilitation and plumping works

Doors, windows and electrical wiring must be installed. Also, painting work is required

Florescent

lamps are

missed

126

BoQ

No Description Unit Qty Unit Cost ($)

Total Cost ($)

Notes

1 Building

No building work is required

2 Windows

2.1 Aluminum casement windows (60cm X 60cm)

No 1 90 90

2.2 Aluminum sliding windows with mosquito net (1m X 1m)

No 2 100 200

Sub-Total 290

3 Doors

3.1 Wooden doors No 2 240 480

3.2 Aluminum doors (0.8m X 2.1m) No 3 160 480

3.3 Peppeled iron doors (1m X 2.1m) No 1 160 160

Sub-Total 1,120

4 Electricity

4.1 Ceiling fans No 5 30 150

4.2 Twin fluorescent lamps with fixture base

No 5 7 35

4.3 Cable (1.5 mm) Roll 9 9 81

4.4 Cable (4mm) Roll 3 21 63

4.5 Plugs (2 lines) No 2 1.5 3

4.6 Plugs (3 lines) No 3 1.7 5.1

4.7 Plugs (4 lines) No 1 2.3 2.3

4.8 45A switch (for air conditioners) No 1 5 5

4.9 Air conditioner (1.5 tons) No 1 480 480

4.10 Switches No 12 1.5 18

4.11 Trunking No 20 1.5 30

127

4.12 12W light bulbs No 7 1.6 11.2

4.13 Labor's cost LS 400 400

Sub-Total 1,283.6

5 Plumbing

5.1 Squad toilet with its accessories No 2 40 80

5.2 Sink No 1 40 40

5.3 Sink tap No 1 12 12

5.4 Taps No 2 3 6

5.5 Shattaf No 2 4 8

5.6 Shower No 1 4 4

5.7 Pipes (0.5 inches) m 6 2.4 14.4

5.8 Elbows (0.5 inches) No 10 0.6 6

5.9 T-joint pipes (0.5 inches) No 5 0.6 3

5.10 Water tank (1000 liters) No 1 90 90

5.11 Labor's cost LS 300 300

Sub-Total 563.4

6 Painting

6.1 Water paint (Crown) Bucket 8 46 368

6.2 Labor's cost LS 360 360

Sub-Total 728

7 Office Furniture

7.1 Sliding iron cupboards No 5 140 700

7.2 Swivel chairs No 4 90 360

7.3 Desk No 4 180 72

7.4 Desktop computer (Lenovo) + Printer (hp)

No 1 1600 1600

7.5 Stationary chairs No 4 88 352

Sub-Total 3,084

128

8 Occupational Health and Safety W

orke

rs Builders Painters Plumbers Electricians Mechanics Other Total

3 2 1 1 0 0 7

OHS Tools and Requirements

No Description Unit Qty Unit Cost Total Cost Notes

8.1 Climbing shoes for electrical works No 1 50 50

8.2 High quality safety gloves suitable for electrical works

No 1 15 15

8.3 High quality long neck rubber Safety shoes suitable for labors who works in sewage

No 1 35 35

8.4 High quality safety rubber gloves suitable for labors who works in sewage (long to over the elbow and close from top)

No 1 25 25

8.5 Face mask for work in dust and smoky areas

No 2 25 50

8.6 High quality rubber safety shoes short neck

No 2 30 60

8.7 High quality safety gloves suitable for building works

No 5 20 100

8.8 High quality safety shoes suitable for labors who work in workshops, buildings… etc.

No 3 50 150

8.9 High quality safety helmets No 7 15 105

8.10 High quality safety vest (can be used by day time and night)

No 4 10 40

8.11 High quality safety cloths suitable for electrical works, mechanical works, building works… etc.

No 3 20 60

8.12 High quality First Aid Kit No 1 25 25

Sub-Total 715

Total Cost 7,784

129

3.2. Cleaning Administration in Al-Mu’alla

The building is seized. Currently, the building become residential facility

BoQ

No Description Unit Qty Unit Cost ($)

Total Cost ($)

Notes

1 Building (Construct new building (10m X 4m + 10m X 4m) – L shape

Excavation

1.1 Excavation (72 lm X 0.5m X 0.3m) m3 11 LS 100

1.2 Volcanic sand m3 48 2.5 120

1.3 Labor's cost LS 216

Casting and cleaning for the entire area

1.4 Building stones m3 1 50 50

1.5 Tar Barrel 1 160 160

1.6 Cement (Sesco) Bag 20 5.2 104

1.7 Gravel m3 3 25 75

1.8 Sand m3 3 15 45

Floor casting (8 m3)

1.10 Cement Bag 40 5.2 208

1.11 Gravel m3 6 25 150

1.12 Sand m3 6 15 90

1.13 Labor's cost LS 240 240

Construction (216 m2)

1.14 Building blocks (20cm X 20cm X 40cm) No 3000 0.6 1800

1.15 Cement (Sesco) Bag 75 5.2 390

1.16 Sand m3 8 15 120

1.17 Labor's cost LS 432 432

Concrete Beams (72 lm X 0.2m X 0.3m)

1.18 Cement (Sesco) Bag 35 5.2 182

130

1.19 Gravel m3 3 25 75

1.20 Sand m3 3 15 45

1.21 Reinforcement steel (14 mm) No 32 10 320

1.22 Reinforcement steel (8 mm) No 30 2.8 84

1.23 Labor's cost LS 400 400

Roofs

1.24 Wooden posts (3cm X 6cm X 12ft) No 66 15 990

1.25 Malaysian triply (15 mm) No 36 29 1,044

1.26 Roofing felt (1X20) No 4 24 96

1.27 Building blocks (30cm X 10cm X 20cm) No 132 0.3 39.6

Floor casting (10 m3)

1.28 Cement (Sesco) Bag 75 5.2 390

1.29 Gravel m3 6 25 150

1.30 Sand m3 6 15 90

1.31 Labor's cost LS 1,000 1,000

Plaster (460 m2)

1.32 Cement (Sesco) Bag 100 5.2 520

1.33 Sand m3 12 15 180

1.34 Volcanic sand m3 12 7.5 30

1.35 Labor's cost LS 920 920

1.36 Ceramic tiles m2 80 6.4 512

1.37 Cement (Sesco) Bag 30 5.2 156

1.38 Sand m3 4 15 60

1.39 Volcanic sand m3 12 2.5 30

1.40 White Cement Bag 1 6 6

1.41 Labor's cost LS 300 300

Sub-Total 12,319.6

131

2 Windows

2.1 Aluminum windows (1m X 1m) No 10 160 1600

2.2 Window guard No 10 80 800

Sub-Total 2,400

3 Doors

3.1 Wooden doors (2.1m X 0.8m) No 6 240 1,440

3.2 Aluminum doors (2.1m X 0.8m) No 1 160 160

Sub-Total 1,600

4 Electricity

4.1 Ceiling fans No 6 30 180

4.2 Twin fluorescent lamps with fixture base No 6 7 42

4.3 Cable (1.5 mm) Roll 12 9 108

4.4 Cable (4mm) Roll 3 21 63

4.5 Plugs (2 lines) No 1 1.5 1.5

4.6 Plugs (3 lines) No 6 1.7 10.2

4.7 Plugs (including charging ports) No 8 2.4 19.2

4.8 45A switch (for air conditioners) No 1 5 5

4.9 Air conditioner (1.5 tons) No 1 480 480

4.10 Switches No 16 1.5 24

4.11 Trunking No 25 1.5 37.5

4.12 12W light bulbs No 10 1.6 16

4.13 Labor's cost LS 400 400

Sub-Total

1,386.4

5 Plumbing

5.1 Squad toilet with its accessories No 1 40 40

5.2 Sink No 1 40 40

5.3 Sink tap No 1 12 12

132

5.4 Taps No 1 4 4

5.5 Shattaf No 1 3 3

5.6 Shower No 1 4 4

5.7 Waterproof tape No 10 0.6 6

5.8 Glue (1 Kg) Can 1 10 10

5.9 Pipes (4 inches) m 2 18 36

5.10 Pipes (0.5 inches) No 3 2.4 7.2

5.11 Elbows (0.5 inches) No 4 0.6 2.4

5.12 T-joint pipes (0.5 inches) No 2 0.6 1.2

5.13 Water tank (1000 liters) No 1 90 90

5.14 Labor's cost LS 300 300

Sub-Total 555.8

6 Painting

6.1 Water paint (Crown) Bucket 10 46 460

6.2 Plaster Bucket 12 14 168

6.3 Paint thinner Bag 6 10 60

6.4 Hand polishing pads No 6 1 6

6.5 Polishing papers No 24 0.3 7.2

6.6 Labor's cost LS 600 600

Sub-Total 1,301.2

7 Office Furniture

7.1 Sliding iron cupboards No 6 140 840

7.2 Swivel chairs No 6 90 540

7.3 Desk No 6 180 1,080

7.4 Desktop computer (Lenovo) + Printer (hp)

No 1 1600 1600

7.5 Stationary chairs No 6 88 528

Sub-Total 4,588

133

8 Occupational Health and Safety W

orke

rs Builders Painters Plumbers Electricians Mechanics Other Total

8 2 1 1 0 0 12

OHS Tools and Requirements

No Description Unit Qty Unit Cost

Total Cost Notes

8.1 Climbing shoes for electrical works No 1 50 50

8.2 High quality safety gloves suitable for electrical works

No 1 15 15

8.3 High quality long neck rubber Safety shoes suitable for labors who works in sewage

No 1 35 35

8.4 High quality safety rubber gloves suitable for labors who works in sewage (long to over the elbow and close from top)

No 1 25 25

8.5 Face mask for work in dust and smoky areas

No 8 25 200

8.6 High quality rubber safety shoes short neck

No 2 30 60

8.7 High quality safety gloves suitable for building works

No 10 20 200

8.8 High quality safety shoes suitable for labors who work in workshops, buildings… etc.

No 8 50 200

8.9 High quality safety helmets No 12 15 180

8.10 High quality safety vest (can be used by day time and night)

No 3 10 30

8.11 High quality safety cloths suitable for electrical works, mechanical works, building works… etc.

No 9 20 180

8.12 High quality First Aid Kit No 1 25 25

8.13 Managing OHS system L/S 100 100

Sub-Total 1,500

Total Cost 25,651

134

3.3. Cleaning Administration in Crater

Main door requires renovation Bathrooms need rehabilitation and plumping works

As shown, doors, windows, electrical wiring, and furniture are missing.

135

BoQ

No Description Unit Qty Unit Cost ($)

Total Cost ($)

Notes

1 Building

1.1 Wooden posts (3 X 6 X 10) No 9 13.6 122.4

1.2 Malaysian triply (15 mm) No 2 29 58

1.3 Roofing felt (1 X 20) No 1 24 24

1.4 Gravel m3 0.5 25 12.5

1.5 Sand m3 0.5 15 7.5

1.6 Cement (Sesco) Bag 5 5.2 26

1.7 Labor's cost LS 200 200

Sub-Total 450.4

2 Windows

2.1 Aluminum windows (0.44m X 0.6m) No 2 80 160

2.2 Wooden windows (1.5m X 2.3m) No 4 200 800

2.3 Wooden windows (1.4m X 1.08m) No 3 200 600

2.4 Wooden windows (1.1m X 1.36m) No 3 140 420

Sub-Total 1,980

3 Doors

3.1 Wooden doors No 6 240 1,440

3.2 Aluminum doors No 3 160 480

3.3 Iron doors No 1 200 200

Sub-Total 2,120

4 Electricity

4.1 Ceiling fans No 7 30 210

4.2 Twin fluorescent lamps with fixture base

No 12 7 84

4.3 Cable (1.5 mm) Roll 6 9 54

4.4 Cable (4mm) Roll 3 21 63

136

4.5 Plugs (2 lines) No 3 1.5 4.5

4.6 Plugs (3 lines) No 3 1.7 5.1

4.7 Plugs (4 lines) No 3 2.3 6.9

4.8 Plugs (including charging ports) No 8 2.4 19.2

4.9 45A switch (for air conditioners) No 2 5 10

4.10 Air conditioner (1.5 tons) No 2 480 960

4.11 12W light bulbs No 5 1.6 8

4.12 Trunking No 20 1.5 30

4.13 Switches No 18 1.5 27

4.14 Labor's cost LS 500 500

Sub-Total 1,981.7

5 Plumbing

5.1 Squad toilet with its accessories No 3 40 120

5.2 Sink No 1 40 40

5.3 Sink tap No 1 12 12

5.4 Tap No 3 4 12

5.6 Pipes (0.5 inches) m 3 2.4 7.2

5.7 Elbows (0.5 inches) No 8 0.6 4.8

5.8 T-joint pipes (0.5 inches) No 4 0.6 2.4

5.9 Water tank (1000 liters) No 1 90 90

5.10 Labor's cost LS 400 400

Sub-Total 688.4

6 Painting

6.1 Water paint (Crown) Bucket 8 46 368

6.2 Labor's cost LS 400 400

Sub-Total 768

7 Office Furniture

137

7.1 Sliding iron cupboards No 4 140 560

7.2 Swivel chairs No 5 90 450

7.3 Desk No 5 180 90

7.4 Desktop computer (Lenovo) + Printer (hp)

No 1 1600 1600

7.5 Stationary chairs No 5 88 440

Sub-Total 3,950

8 Occupational Health and Safety

Wor

kers

Builders Painters Plumbers Electricians Mechanics Other Total

5 2 1 1 0 0 9

OHS Tools and Requirements

No Description Unit Qty Unit Cost Total Cost Notes

8.1 Climbing shoes for electrical works No 1 50 50

8.2 High quality safety gloves suitable for electrical works

No 1 15 15

8.3 High quality long neck rubber Safety shoes suitable for labors who works in sewage

No 1 35 35

8.4 High quality safety rubber gloves suitable for labors who works in sewage (long to over the elbow and close from top)

No 1 25 25

8.5 Face mask for work in dust and smoky areas

No 2 25 50

8.6 High quality rubber safety shoes short neck

No 2 30 60

8.7 High quality safety gloves suitable for building works

No 7 20 140

8.8 High quality safety shoes suitable for labors who work in workshops, buildings… etc.

No 5 50 250

8.9 High quality safety helmets No 9 15 135

8.10 High quality safety vest (can be used by day time and night)

No 4 10 40

138

8.11 High quality safety cloths suitable for electrical works, mechanical works, building works… etc.

No 5 20 100

8.12 High quality First Aid Kit No 1 25 25

Sub-Total 925

Total Cost 12,863.5

3.4. Cleaning Administration in Khormaksar

No rehabilitation works are required, however, there is no warehouse in Khormaksar cleaning

administration

BoQ

No Description Unit Qty Unit Cost ($)

Total Cost ($)

Notes

1 Building (Construct new building as a warehouse) – 6m X 4m

Casting and cleaning for the entire area

1.1 Building blocks m3 2 50 100

1.2 Tar Barrel 1 160 160

1.3 Roofing felt (1 X 20) No 2 24 48

1.4 Cement (Sesco) Bag 30 5.2 156

1.5 Gravel m3 4 25 100

1.6 Sand m3 4 15 30

1.7 Labor's cost LS 300 300

Construction

1.8 Building blocks (20cm X 20cm X 40cm) No 750 0.6 450

1.9 Cement (Sesco) Bag 20 5.2 104

1.10 Sand m3 2 15 30

1.11 Labor's cost LS 120 120

Concrete Beams (20 lm X 0.2m X 0.3m)

1.12 Cement (Sesco) Bag 10 5.2 52

139

1.13 Gravel m3 0.5 25 12.5

1.14 Sand m3 0.5 15 7.5

1.15 Reinforcement steel (14 mm) No 28 10 280

1.16 Reinforcement steel (8 mm) No 18 2.8 50.4

1.17 Labor's cost LS 200 200

Roof

1.18 Wooden posts (3cm X 6cm X 14ft) No 20 18.4 368

1.19 Malaysian triply (15 mm) No 8 29 232

1.20 Roofing felt (1 X 20) No 2 24 48

1.21 Building blocks (30cm X 10cm X 20cm) No 40 0.3 12

Roof Casting

1.22 Cement (Sesco) Bag 20 5.2 104

1.23 Gravel m3 2 25 50

1.24 Sand m3 2 15 30

1.25 Labor's cost LS 800 800

Sub-Total 3,844.4

2 Doors

2.1 Iron doors (1.4m X 2m) No 1 280 280

Sub-Total 280

3 Electricity

3.1 Ceiling fans No 1 30 30

3.2 Twin fluorescent lamps with fixture base No 2 7 14

3.3 Cable (1.5 mm) Roll 3 9 27

3.4 Cable (4mm) Roll 3 21 63

3.5 Plugs (4 lines) No 1 2.3 2.3

3.6 45A switch (for air conditioners) No 1 5 5

3.7 Air conditioner (1.5 tons) No 1 480 480

140

3.8 12W light bulbs No 2 1.6 3.2

3.9 Trunking No 6 1.5 9

4.12 Switches No 5 1.5 6

4.13 Labor's cost LS 300 300

Sub-Total 939.5

5 Painting

5.1 Water paint (Crown) Bucket 4 46 184

5.2 Labor's cost LS 120 120

Sub-Total 304

6 Office Furniture

6.1 Sliding iron cupboards No 4 140 560

6.2 Swivel chairs No 4 90 360

6.3 Desk No 4 180 720

6.4 Desktop computer (Lenovo) + Printer (hp)

No 1 1600 1600

6.5 Stationary chairs No 4 88 352

Sub-Total 3,592

7 Occupational Health and Safety

Wor

kers

Builders Painters Plumbers Electricians Mechanics Other Total

8 2 0 1 0 0 11

OHS Tools and Requirements

No Description Unit Qty Unit Cost Total Cost Notes

7.1 Climbing shoes for electrical works No 1 50 50

7.2 High quality safety gloves suitable for electrical works

No 1 15 15

7.3 Face mask for work in dust and smoky areas

No 8 25 200

7.4 High quality rubber safety shoes short neck

No 2 30 60

7.5 High quality safety gloves suitable for building works

No 10 20 200

141

7.6 High quality safety shoes suitable for labors who work in workshops, buildings… etc.

No 8 50 400

7.7 High quality safety helmets No 11 15 165

7.8 High quality safety vest (can be used by day time and night)

No 2 10 20

7.9 High quality safety cloths suitable for electrical works, mechanical works, building works… etc.

No 9 20 180

7.10 High quality First Aid Kit No 1 25 25

7.11 Managing OHS system L/S 100 100

Sub-Total 1,415

Total Cost 10,374.9

142

3.5. Cleaning Administration in Al-Mansoora

BoQ

No Description Unit Qty Unit Cost ($)

Total Cost ($)

Notes

1 Building (Renovate the building's roofs)

1.1 Wooden posts (3cm X 6cm X 20ft) No 20 26 520

1.2 Wooden posts (3cm X 6cm X 16ft) No 30 21 630

As shown, doors, windows, electrical wiring, and furniture are missing/destroyed. Moreover, building’s

roofs are in bad condition and must be reconstructed.

143

1.3 Malaysian triply (15 mm) No 36 29 1,044

1.4 Roofing felt (1 X 20) No 10 24 240

1.5 Nails (2 inches) Packet 5 1 5

1.6 Building blocks (30cm X 10xm) No 100 0.3 30

1.7 Gravel m3 8 25 200

1.8 Sand m3 8 15 120

1.9 Cement (Sesco) Bag 65 5.2 338

1.7 Labor's cost LS 800 800

Sub-Total 3,927

2 Windows

2.1 Aluminum windows (0.6m X 0.6m) No 1 90 90

2.2 Aluminum windows (1.2m X 1m) No 2 140 280

2.3 Aluminum windows (1.9m X 0.3m) No 2 100 200

2.4 Wooden windows (1m X 1m) No 2 160 320

Sub-Total 890

3 Doors

3.1 Peppled iron doors No 2 200 400

3.2 Iron doors (1.4m X 2.1m) No 1 240 240

Sub-Total 640

4 Electricity

4.1 Ceiling fans No 3 30 90

4.2 Twin fluorescent lamps with fixture base

No 4 7 28

4.3 Cable (1.5 mm) Roll 9 9 81

4.4 Cable (4mm) Roll 3 21 63

4.5 Plugs (2 lines) No 2 1.5 3

4.6 Plugs (3 lines) No 3 1.7 5.1

4.7 Plugs (including charging ports) No 6 2.4 14.4

144

4.8 45A switch (for air conditioners) No 1 5 6

4.9 Air conditioner (1.5 tons) No 1 480 480

4.10 12W light bulbs No 3 1.6 4.8

4.11 Trunking No 15 1.5 22.5

4.13 Switches No 8 1.5 12

4.14 Labor’s cost LS 400 400

Sub-Total 1208.68

5 Painting

5.1 Water paint (Crown) Bucket 5 46 230

5.2 Labor's cost LS 200 200

Sub-Total 430

6 Office Furniture

6.1 Sliding iron cupboards No 4 140 560

6.2 Swivel chairs No 3 90 270

6.3 Desk No 3 180 540

6.4 Desktop computer (Lenovo) + Printer (hp)

No 1 1600 1600

6.5 Stationary chairs No 3 88 264

Sub-Total 3,234

7 Occupational Health and Safety

Wor

kers

Builders Painters Plumbers Electricians Mechanics Other Total

5 2 1 1 0 0 9

OHS Tools and Requirements

No Description Unit Qty Unit Cost Total Cost Notes

7.1 Climbing shoes for electrical works No 1 50 50

7.2 High quality safety gloves suitable for electrical works

No 1 15 15

7.3 High quality long neck rubber Safety shoes suitable for labors who works in sewage

No 1 35 35

145

7.4 High quality safety rubber gloves suitable for labors who works in sewage (long to over the elbow and close from top)

No 1 25 25

7.5 Face mask for work in dust and smoky areas

No 2 25 50

7.6 High quality rubber safety shoes short neck

No 2 30 60

7.7 High quality safety gloves suitable for building works

No 7 20 140

7.8 High quality safety shoes suitable for labors who work in workshops, buildings… etc.

No 5 50 250

7.9 High quality safety helmets No 9 15 135

7.10 High quality safety vest (can be used by day time and night)

No 4 10 40

7.11 High quality safety cloths suitable for electrical works, mechanical works, building works… etc.

No 5 20 100

7.12 High quality First Aid Kit No 1 25 25

Sub-Total 925

Total Cost 11,525.68

3.6. Cleaning Administration in Al-Boraiqa

The building of Al-Boraiqa’s cleaning administration is totally damaged. Thus, a new

building is required.

BoQ

No Description Unit Qty Unit Cost ($)

Total Cost ($)

Notes

1 Building (Construct new building (10m X 4m + 10m X 4m) – L shape

Excavation

1.1 Excavation (72 lm X 0.5m X 0.3m) m3 11 LS 100

1.2 Volcanic sand m3 48 2.5 120

1.3 Labor's cost LS 216

Casting and cleaning for the entire area

146

1.4 Building stones m3 1 50 50

1.5 Tar Barrel 1 160 160

1.6 Cement (Sesco) Bag 20 5.2 104

1.7 Gravel m3 3 25 75

1.8 Sand m3 3 15 45

Floor casting (8 m3)

1.10 Cement Bag 40 5.2 208

1.11 Gravel m3 6 25 150

1.12 Sand m3 6 15 90

1.13 Labor's cost LS 240 240

Construction (216 m2)

1.14 Building blocks (20cm X 20cm X 40cm) No 3000 0.6 1800

1.15 Cement (Sesco) Bag 75 5.2 390

1.16 Sand m3 8 15 120

1.17 Labor's cost LS 432 432

Concrete Beams (72 lm X 0.2m X 0.3m)

1.18 Cement (Sesco) Bag 35 5.2 182

1.19 Gravel m3 3 25 75

1.20 Sand m3 3 15 45

1.21 Reinforcement steel (14 mm) No 32 10 320

1.22 Reinforcement steel (8 mm) No 30 2.8 84

1.23 Labor's cost LS 400 400

Roofs

1.24 Wooden posts (3cm X 6cm X 12ft) No 66 15 990

1.25 Malaysian triply (15 mm) No 36 29 1,044

1.26 Roofing felt (1X20) No 4 24 96

1.27 Building blocks (30cm X 10cm X 20cm) No 132 0.3 39.6

147

Floor casting (10 m3)

1.28 Cement (Sesco) Bag 75 5.2 390

1.29 Gravel m3 6 25 150

1.30 Sand m3 6 15 90

1.31 Labor's cost LS 1,000 1,000

Plaster (460 m2)

1.32 Cement (Sesco) Bag 100 5.2 520

1.33 Sand m3 12 15 180

1.34 Volcanic sand m3 12 7.5 30

1.35 Labor's cost LS 920 920

1.36 Ceramic tiles m2 80 6.4 512

1.37 Cement (Sesco) Bag 30 5.2 156

1.38 Sand m3 4 15 60

1.39 Volcanic sand m3 12 2.5 30

1.40 White Cement Bag 1 6 6

1.41 Labor's cost LS 300 300

Sub-Total 12,319.6

2 Windows

2.1 Aluminum windows (1m X 1m) No 10 160 1600

2.2 Window guard No 10 80 800

Sub-Total 2,400

3 Doors

3.1 Wooden doors (2.1m X 0.8m) No 6 240 1,440

3.2 Aluminum doors (2.1m X 0.8m) No 1 160 160

Sub-Total 1,600

4 Electricity

4.1 Ceiling fans No 6 30 180

148

4.2 Twin fluorescent lamps with fixture base No 6 7 42

4.3 Cable (1.5 mm) Roll 12 9 108

4.4 Cable (4mm) Roll 3 21 63

4.5 Plugs (2 lines) No 1 1.5 1.5

4.6 Plugs (3 lines) No 6 1.7 10.2

4.7 Plugs (including charging ports) No 8 2.4 19.2

4.8 45A switch (for air conditioners) No 1 5 5

4.9 Air conditioner (1.5 tons) No 1 480 480

4.10 Switches No 16 1.5 24

4.11 Trunking No 25 1.5 37.5

4.12 12W light bulbs No 10 1.6 16

4.13 Labor's cost LS 400 400

Sub-Total

1,386.4

5 Plumbing

5.1 Squad toilet with its accessories No 1 40 40

5.2 Sink No 1 40 40

5.3 Sink tap No 1 12 12

5.4 Taps No 1 4 4

5.5 Shattaf No 1 3 3

5.6 Shower No 1 4 4

5.7 Waterproof tape No 10 0.6 6

5.8 Glue (1 Kg) Can 1 10 10

5.9 Pipes (4 inches) m 2 18 36

5.10 Pipes (0.5 inches) No 3 2.4 7.2

5.11 Elbows (0.5 inches) No 4 0.6 2.4

5.12 T-joint pipes (0.5 inches) No 2 0.6 1.2

5.13 Water tank (1000 liters) No 1 90 90

149

5.14 Labor's cost LS 300 300

Sub-Total 555.8

6 Painting

6.1 Water paint (Crown) Bucket 10 46 460

6.2 Plaster Bucket 12 14 168

6.3 Paint thinner Bag 6 10 60

6.4 Hand polishing pads No 6 1 6

6.5 Polishing papers No 24 0.3 7.2

6.6 Labor's cost LS 600 600

Sub-Total 1,301.2

7 Office Furniture

7.1 Sliding iron cupboards No 6 140 840

7.2 Swivel chairs No 6 90 540

7.3 Desk No 6 180 1,080

7.4 Desktop computer (Lenovo) + Printer (hp)

No 1 1600 1600

7.5 Stationary chairs No 6 88 528

Sub-Total 4,588

8 Occupational Health and Safety

Wor

kers

Builders Painters Plumbers Electricians Mechanics Other Total

8 2 1 1 0 0 12

OHS Tools and Requirements

No Description Unit Qty Unit Cost

Total Cost Notes

8.1 Climbing shoes for electrical works No 1 50 50

8.2 High quality safety gloves suitable for electrical works

No 1 15 15

8.3 High quality long neck rubber Safety shoes suitable for labors who works in sewage

No 1 35 35

150

8.4 High quality safety rubber gloves suitable for labors who works in sewage (long to over the elbow and close from top)

No 1 25 25

8.5 Face mask for work in dust and smoky areas

No 8 25 200

8.6 High quality rubber safety shoes short neck

No 2 30 60

8.7 High quality safety gloves suitable for building works

No 10 20 200

8.8 High quality safety shoes suitable for labors who work in workshops, buildings… etc.

No 8 50 200

8.9 High quality safety helmets No 12 15 180

8.10 High quality safety vest (can be used by day time and night)

No 3 10 30

8.11 High quality safety cloths suitable for electrical works, mechanical works, building works… etc.

No 9 20 180

8.12 High quality First Aid Kit No 1 25 25

8.13 Managing OHS system L/S 100 100

Sub-Total 1,500

Total Cost 25,651

3.7. Cleaning Administration in Al-Sheikh Othman

Doors, windows, electrical wiring, and furniture are missing/destroyed. In addition, bathrooms need

renovation and plumping works.

151

BoQ

No Description Unit Qty Unit Cost ($)

Total Cost ($)

Notes

1 Building (Renovate the bathroom's roofs) – 2.5m X 2m

1.1 Wooden posts (3cm X 6cm X 7ft) No 7 10 70

1.2 Malaysian triply (15 mm) No 2 29 58

1.3 Roofing felt (1 X 20) No 1 24 24

1.4 Nails (2 inches) Packet 1 1 1

1.5 Gravel m3 0.5 25 12.5

1.6 Sand m3 0.5 15 7.5

1.9 Cement (Sesco) Bag 7 5.2 36.4

1.7 Labor's cost LS 200 200

Sub-Total 409.4

2 Windows

2.1 Aluminum casement windows (0.4m X 0.4m) No 1 100 100

2.2 Aluminum casement windows (0.6m X 0.6m) No 4 100 400

2.3 Aluminum sliding windows with mosquito net (1m X 1m)

No 2 160 320

Sub-Total 820

3 Doors

3.1 Peppeled iron doors No 2 200 400

3.2 Aluminum doors (1m X 2.1m) No 1 160 160

Sub-Total 560

4 Electricity

4.1 Ceiling fans No 4 30 120

4.2 Twin fluorescent lamps with fixture base No 4 7 28

4.3 Cable (1.5 mm) Roll 9 9 81

4.4 Cable (4mm) Roll 3 21 63

152

4.5 Plugs (2 lines) No 2 1.5 3

4.6 Plugs (3 lines) No 3 1.7 5.1

4.7 Plugs (4 lines) No 2 2.3 4.6

4.8 Plugs (including charging ports) No 6 2.4 14.4

4.9 45A switch (for air conditioners) No 1 5 5

4.10 Air conditioner (1.5 tons) No 1 480 480

4.11 12W light bulbs No 5 1.6 8

4.12 Trunking No 15 1.5 22.5

4.13 Switches No 10 1.5 15

4.14 Labor's cost LS 20 240

Sub-Total 1,089.6

5 Plumping

5.1 Squad toilet with its accessories No 1 40 40

5.2 Taps No 2 4 8

5.3 Pipes (0.5 inches) M 3 2.4 7.2

5.4 Elbows (0.5 inches) No 6 0.6 3.6

5.5 T-joint pipes (0.5 inches) No 3 0.6 1.8

5.6 Water tank (1000 liters) No 1 90 90

5.7 Labor's cost LS 160 160

Sub-Total 310.6

6 Painting

6.1 Water paint (Crown) Bucket 6 46 276

6.2 Labor's cost LS 240 240

Sub-Total 516

7 Office Furniture

7.1 Sliding iron cupboards No 4 140 560

7.2 Swivel chairs No 4 90 360

153

7.3 Desk No 4 180 720

7.4 Desktop computer (Lenovo) + Printer (hp) No 1 1600 1600

7.5 Stationary chairs No 4 88 352

Sub-Total 3,592

8 Occupational Health and Safety

Wor

kers

Builders Painters Plumbers Electricians Mechanics Other Total

5 2 1 1 0 0 9

OHS Tools and Requirements

No Description Unit Qty Unit Cost Total Cost

Notes

8.1 Climbing shoes for electrical works No 1 50 50

8.2 High quality safety gloves suitable for electrical works

No 1 15 15

8.3 High quality long neck rubber Safety shoes suitable for labors who works in sewage

No 1 35 35

8.4 High quality safety rubber gloves suitable for labors who works in sewage (long to over the elbow and close from top)

No 1 25 25

8.5 Face mask for work in dust and smoky areas No 2 25 50

8.6 High quality rubber safety shoes short neck No 2 30 60

8.7 High quality safety gloves suitable for building works

No 7 20 140

8.8 High quality safety shoes suitable for labors who work in workshops, buildings… etc.

No 5 50 250

8.9 High quality safety helmets No 9 15 135

8.10 High quality safety vest (can be used by day time and night)

No 4 10 40

8.11 High quality safety cloths suitable for electrical works, mechanical works, building works… etc.

No 5 20 100

8.12 High quality First Aid Kit No 1 25 25

Sub-Total 925

Total Cost 8,222.6

154

3.8. Cleaning Administration in Dar Sa’d

BoQ

No Description Unit Qty Unit Cost ($)

Total Cost ($)

Notes

1 Building (Reconstruct the damaged wall shown in photos above)

1.1 Building blocks (20cm X 20cm X 40cm) No 160 0.6 96

1.2 Sand m3 2 15 30

1.3 Cement (Sesco) Bag 20 5.2 104

1.4 Labor's cost LS 500 500

Sub-Total 730

Photos above illustrate the severe damages in the building of cleaning administration in Dar Sa’d.

Some parts need to be reconstructed.

155

2 Windows

2.1 Aluminum sliding windows with mosquito net (1m X 1m)

No 8 160 1,280

Sub-Total 1,280

3 Doors

3.1 Peppeled iron doors (0.9m X 2.1m) No 5 160 800

3.2 Aluminum doors (1m X 2.1m) No 1 200 200

Sub-Total 1,000

4 Electricity

4.1 Ceiling fans No 4 30 120

4.2 Twin fluorescent lamps with fixture base No 4 7 28

4.3 Cable (1.5 mm) Roll 9 9 81

4.4 Cable (4mm) Roll 3 21 63

4.5 Plugs (2 lines) No 2 1.5 3

4.6 Plugs (3 lines) No 3 1.7 5.1

4.7 Plugs (4 lines) No 2 2.3 4.6

4.8 Plugs (including charging ports) No 6 2.4 14.4

4.9 45A switch (for air conditioners) No 1 5 5

4.10 Air conditioner (1.5 tons) No 1 480 480

4.11 12W light bulbs No 4 1.6 6.4

4.12 Trunking No 20 1.5 30

4.13 Switches No 10 1.5 15

4.14 Labor's cost LS 300 300

Sub-Total 1,155.5

5 Painting

5.1 Water paint (Crown) Bucket 8 46 368

5.2 Labor's cost LS 240 240

Sub-Total 608

156

6 Office Furniture

6.1 Sliding iron cupboards No 4 140 560

6.2 Swivel chairs No 4 90 360

6.3 Desk No 4 180 720

6.4 Desktop computer (Lenovo) + Printer (hp)

No 1 1600 1600

6.5 Stationary chairs No 4 88 352

Sub-Total 3,592

7 Occupational Health and Safety

Wor

kers

Builders Painters Plumbers Electricians Mechanics Other Total

5 2 1 1 0 0 9

OHS Tools and Requirements

No Description Unit Qty Unit Cost

Total Cost Notes

8.1 Climbing shoes for electrical works No 1 50 50

8.2 High quality safety gloves suitable for electrical works

No 1 15 15

8.3 High quality long neck rubber Safety shoes suitable for labors who works in sewage

No 1 35 35

8.4 High quality safety rubber gloves suitable for labors who works in sewage (long to over the elbow and close from top)

No 1 25 25

8.5 Face mask for work in dust and smoky areas

No 2 25 50

8.6 High quality rubber safety shoes short neck

No 2 30 60

8.7 High quality safety gloves suitable for building works

No 7 20 140

8.8 High quality safety shoes suitable for labors who work in workshops, buildings… etc.

No 5 50 250

8.9 High quality safety helmets No 9 15 135

8.10 High quality safety vest (can be used by day time and night)

No 4 10 40

157

8.11 High quality safety cloths suitable for electrical works, mechanical works, building works… etc.

No 5 20 100

8.12 High quality First Aid Kit No 1 25 25

Sub-Total 925

Total Cost 9,290.5

158

Second: Equipment and Assets

Old and destroyed vehicles, trucks and containers.

159

BoQ

No Description Unit Qty Unit Cost ($)

Total Cost ($)

Notes

1 Cleaning Administrations in Directorates - Metal Containers

1.1 Garbage containers made of galvanized iron with capacity of 1m3

No 500 350 175,000

1.2 Garbage containers made of galvanized iron with capacity of 3m3

No 80 1,500 120,000

Sub-Total 295,000

2 Cleaning Administrations in Directorates – Vehicles

2.1 Garbage collecting vehicles (Tippers – 3 tons)

No 5 35,000 175,000

2.2 Garbage collecting vehicles with internal compactors (12 tons)

No 3 120,000 360,000

Sub-Total 535,000

3 Bir Na'ama Dumpsite

3.1 Bulldozer No 1 390,000 390,000

3.2 Landfill compactor No 1 350,000 350,000

Sub-Total 740,000

4 Maintenance Workshops

4.1 Mobile maintenance workshop – Khormaksar maintenance workshop

No 1 110,000 110,000

4.2 Mobile maintenance workshop – Al-Mansoora maintenance workshop

No 1 110,000 110,000

Sub-Total 220,000

Total Cost 1,790,000

160

8. Urgent Intervention for Water Supply System

No Sub-Project Name Estimated Cost ($)

First: Rehabilitation Intervention

1 Wellfields

1.1 Replace the western north pipeline in Bir Nasser wellfield 387,714.05

1.2 Expand administrative building in Al-Manasera wellfield 42,143.5

1.3 Expand the administrative building in Bir Ahmed wellfield 33,768.2

1.4 Expand the administrative building in Bir Nasser wellfield 33,768.2

2 Reservoirs and Tanks

2.1 Rehabilitate Fuqum mountain reservoirs No.2 (4,500 m3) 103,005

3 Pumping Station

3.1 Renovate lightening systems and supply celling fans for all pumping stations 9,592

Sub-Total 609,990.95

No Sub-Project Name Estimated Cost ($)

Second: Supplying Vehicles, Machines and Tools

1 Wellfields

1.1 Supply and install ten submersible pumps with motors 250,000

2 Water Supply Network

2.1 Supply water leakage monitoring system 12,400

2.2 Supply operation tools and equipment for rehabilitate and expand network 125,000

3 Pumping Station

3.1 Supply spare parts 50,000

4 Maintenance Workshops

4.1 Supply truck crane (5 tons) 110,000

Sub-Total 547,400

Total 1,157,390.95

161

First: Rehabilitation Interventions

i. Wellfields 1. Replace the western north pipeline in Bir Nasser wellfield

The north wester pipeline (12 inches asbestos pipeline) is too old and must be replaced by a new 16 inches HDPE pipeline.

The blue line in the above layout shows the pipeline that must be replaced. The length of the pipeline is about 2Km.

162

BoQ for replace the western north pipeline in Bir Nasser wellfield

No Description Unit Qty Unit Cost ($)

Total Cost ($)

Notes

Materials

1 HDPE Pipes (PN 16) PE. 100 SDR11 in (12m Pipe Length)

1.1 Ø 400 mm No 174 1,200 208,800

1.2 Ø 160 mm No 20 206.1 4,120.2

Sub-Total 212,920.2

2 Ductile iron fittings (PN16) Class K12

2.1 Flanges equal tee (400 mm) No 3 1,155.33 3,465.99

2.2 Flanges equal tee with 45 angles No 8 1,225.22 9,801.76

Sub-Total 13,258.75

3 D.I All flange reducer Taper

3.1 400 X 300 mm No 3 1,308 3,924

3.2 400 X 200 mm No 1 872 872

3.3 400 X 150 mm No 1 654 654

Sub-Total 5,450

4 Flexible Grip Flange Adaptor

4.1 Ø 400 mm No 6 2,146 12,876

4.2 Ø 160 mm No 16 466 7,456

Sub-Total 20,332

5 Double Flange Gate Valve (Soft Sealing)

5.1 Ø 400 mm Dia. No 2 4,846.3 9,692.6

5.2 Ø 160 mm Dia. No 8 202.14 1,617.12

Sub-Total 11,309.72

6 Flange double air valve

6.1 Ø150mm No 1 865.4 865.4

Sub-Total 865.4

163

7 Stub end with packing flange Suitable for PE

7.1 Ø 400 mm No 1 134.63 134.63

Sub-Total 134.63

8 Bolt and NUTS

8.1 Ø 400 mm No 96 9.2 883.2

8.2 Ø 150 mm No 100 4.6 460

Sub-Total 1,343.2

9 Rubber Packing (Gasket)

9.1 Ø 400 mm Dia. No 16 435 6,960

9.2 Ø 160 mm Dia. No 30 191 5,730

Sub-Total 12,690

Civil Works

1 Fill and Cut Works

1.1 Cutting – width of 50cm and depth of 100cm

M.L 2,300 20 46,560

1.2 Filling above and below the pipe with a 10cm thick layer of soft sand, and then finishing filling using normal sand.

Sub-Total 46,560

2 Installing pipeline

2.1 Constructing polyethylene pipes and accessories for pipes with diameters of larger than 400mm

M.L 2.3Km 15 34,920

Sub-Total 34,920

3 Constructing Valves Rooms (Detain + Fire + Air) Diameter 150mm

3.1 Cut and fill works in a sand soil

No 9 500 4,500

3.2 Casting of regular concrete for floor with a thickness of 10cm and the following mix ratio 1:3:6

3.3 Building walls using cast blocks (8"×8"×16") and concrete mortar (1:3)

164

3.4 Casting the inside with a thickness of 2cm using concrete mortar (1:3)

3.5 Cover using reinforced concrete with thickness of 20cm and 16mm steel bars (two layers) every 12cm radially

Sub-Total 4,500

4 Constructing Valves Rooms (Detain) Diameter 400mm

4.1 Cut and fill in normal soil clay/sand and removal of excess soil outside of site

No 2 1,500 3,000

4.2 Placing down a 10cm layer of crushed stone

4.3 Casting regular concrete for floor with thickness of 5cm and mix ratio of 1:3:6 and using salt-resistant cement

4.4 Casting of regular concrete for floor with thickness of 30cm and mix ratio of 1:2:4 and using salt-resistant cement

4.5 Building walls using reinforced concrete with thickness of 25cm and mix ratio of 1:2:4 and using salt-resistant cement and reinforcing steel

4.6 Casting the inside with thickness of 2cm using concrete mortar 1:3 and salt-resistant cement

4.7 Roof using reinforced concrete with thickness of 20cm and mix ratio of 1:2:4 and using salt-resistant cement

4.8 Casting of regular concrete supports with mix ratio of 1:3:6 and using salt-resistant cement

4.9 Supply and placement of a heavy iron cover (60cm ×60cm ×15cm) along with the frame and installed within the roof's concrete

4.10 Supply and placement of a heavy iron cover (20cm ×20cm ×15cm) along with the frame and installed within the roof's concrete

165

4.11 Supply and placement of iron ladder (2" ×2" ×5mm) with width of 40cm and spacing between steps of 35cm and installed between the wall and floor of the room and is coated with a layer of primer and a layer of silver oily paint

4.12 Painting of outer walls with a layer of tar along with foundation

Sub-Total 3,000

5 Cut and removal and replacement of asphalt

M.L 20 70 1,400

6 Connecting the new line with the old one

No 1 1,000 1,000

7 Filling, sanitizing and testing the network

M.L 2,300 0.6 1,396.68

8 Additional unforeseen works LS 10% 9,277.68

9 Occupational Safety and Health

Wor

kers

Builders Painters Plumbers Electricians Mechanics Other Total

20 2 10 2 5 0 39

OHS Tools and Requirements

No Description Unit Qty Unit Cost

Total Cost Notes

9.1 Climbing shoes for electrical works No 2 50 100

9.2 High quality safety gloves suitable for electrical works

No 2 15 30

9.3 High quality long neck rubber Safety shoes suitable for labors who works in sewage

No 10 35 350

9.4 High quality safety rubber gloves suitable for labors who works in sewage (long to over the elbow and close from top)

No 10 25 250

9.5 Face mask for work in dust and smoky areas

No 25 25 625

9.6 High quality rubber safety shoes short neck

No 2 30 60

9.7 High quality safety gloves suitable for building works

No 35 20 700

166

9.8 High quality safety shoes suitable for labors who work in workshops, buildings… etc.

No 35 50 1,750

9.9 High quality safety helmets No 39 15 585

9.10 High quality safety vest (can be used by day time and night)

No 12 10 120

9.11 High quality safety cloths suitable for electrical works, mechanical works, building works… etc.

No 27 20 540

9.12 High quality First Aid Kit No 1 25 25

9.13 Managing OHS system L/S 1,000 1,000

Sub-Total 6,135

Total 387,714.05

2. Expand administration buildings in wellfields

New buildings are required in the three wellfields (Al-Manasera, Bir Ahmed and Bir Nasser) as an expansion,

since, the existing buildings are small and don't have enough space anymore for new offices. The required specifications and designs of the new buildings are attached in Appendix (7).

BoQ for construct new building in Al-Manasera wellfield

No Description Unit Qty Unit Cost ($)

Total Cost ($)

Notes

1 Civil works

1.1 Soil drilling for the foundation with width of 80cm and depth of 95cm,

m3 41.1 5 205.5

Administration building in Bir Ahmed wellfield Administration building in Bir Nasser wellfield

167

along with cleaning, compacting (if necessary) and removal of soil according to supervisor engineer's instructions

1.2 Placing a layer of crushed stones with thickness of 15cm and width of 60cm below the rock foundation

m3 32.4 16 518.4

1.3 Laying a concrete layer with a mix ratio of (1:3:6) using salt-resistant cement with thickness of 10cm and width of 60cm below the rock foundation

m3 32.4 10 324

1.4 Constructing of foundation using hard rock with width of 40cm and height of 60cm using a concrete mortar with a mix ratio of (1:3) and using a salt-resistant cement as well as filling the gaps between the rocks from the inside and outside according to supervisor engineer's instructions

m3 13 14 182

1.5 Ground beams using reinforced concrete with a mix ratio of (1:2:4) and dimensions of (20cm ×40cm) above the rock foundation. Reinforcement steel is as shown in the drawings and using salt-resistant cement.

m2 4.32 100 432

1.6 Hot tar painting specified for construction works to be used in rock foundation’s surfaces and ground beams’ faces buried underground.

m2 64.8 7 453.6

1.7 Refilling of soil around the rock foundation and the rooms floor using the soil excavated from drilling, good spraying and compacting every 20cm

m3 22 5 110

1.8 Spraying insecticide on the building's floor and inside the foundation's trench

LS 200 200

1.9 Laying a 15cm crushed stone layer on the floors

m3 66 160 10,560

168

1.10 Laying a 10cm concrete layer over rooms' floor with a mix ratio of (1:2:4)

m3 66 60 3,960

1.11 Laying two layers of humidity isolation felt with hot tar on the rooms' floor and making the necessary protruding along the walls

m2 66 6 396

1.12 Supplying and installing good quality tiles for the building's floor using concrete mortar with a mix ratio of (1:3) according to supervisor engineer's instructions

m2 66 8 528

1.13 Supplying and constructing ceramic protruding for the building's floor according to supervisor engineer's instructions

m2 58 4 232

1.14 Building the interior walls with height of (2.7m) using hollow blocks (20cm X 20cm X 40cm) and concrete mortar with a mix ratio of (1:3)

m2 150 8 1,200

1.15 Reinforced concrete for the roof's lab thickness of 15cm, beams' dimensions (20cm X 30cm), columns' dimensions (20cm X 30cm), doors and windows' frames with a mix ratio of (1:2:4). Reinforcement steel should be according to drawings and supervisor engineer's instructions

ML 22.6 150 3,390

1.16 Laying two crossing layers of felt for the rooms' roof along with hot tar provided that it should rise about 10cm into the extension's wall

m3 260 6 1,560

1.17 Laying of inclination layer from ordinary concrete with thickness of (7cm) and mix ration of (1:2:4) according to the drawings and supervisor engineer’s instructions.

m3 260 6 1,560

1.18 Supply and construction of rain water drains on the building’s roof and connecting these drains to a

No 2 160 320

169

high-pressure plastic pipe of 3 inches diameter.

1.19 Plastering all inside and outside walls and the sides of the extensions using concrete mortar with a mix ratio of (1:3) according to the supervisor engineer’s instructions.

m2 490 9 4,410

1.20 Constructing a pavement around the building 1m wide and is made of crushed stones with thickness of 15cm and laying of a 10cm ordinary concrete with a mix ratio of (1:2:4) and adding tiles as well as rocks surrounding the pavement.

m2 31 10 310

Sub-Total 30,851.5

2 Painting

2.1 Painting the inside walls with a layer of foundation water paint, two layers of plaster and two layers of good quality oil paint. Colors to be determined by the supervisor engineer.

m2 115 9 1,035

2.2 Painting the inside of the room’s roof with a layer of foundation water paint, two layers of plaster and three layers of good quality oil paint. Colors to be determined by the supervisor engineer.

m2 66 9 594

2.3 Painting the outside of the extension’s walls with a layer of foundation water paint and three layers of good quality water paint. Colors to be determined by the supervisor engineer.

m2 309 9 2,781

Sub-Total 4,410

3 Doors and Windows

3.1 Supplying and constructing aluminum sliding windows equipped with a 6mm thick glass with a

No 5 90 450

170

mosquito net + steel net (squares of 1cm) as a protection from the outside of good quality and painting it with an anti-corrosion paint and two layers of oil paint. Dimensions of windows (1.5m ×1.4m). Shape is to be determined by the supervisor engineer.

3.2 Supplying and constructing aluminum sliding windows equipped with a 6mm thick glass with a mosquito net + steel net (squares of 1cm) as a protection from the outside of good quality and painting it with an anti-corrosion paint and two layers of oil paint. Dimensions of windows (0.6m ×0.6m). Shape is to be determined by the supervisor engineer.

No 2 80 160

3.3 Supplying and constructing a steel door with 3mm pebbles one side with dimensions of (1m ×2.2m) and thickness of 5cm with a high-quality lock and all necessary accessories according to the supervisor engineer’s instructions.

No 3 160 480

Sub-Total 1,090

4 Electrical Wiring

4.1 Distribution panel (12 lines) No 1 200 200

4.2 Ceiling fan with speed controller No 6 160 960

4.3 Florescent lamps (4 ft) No 14 30 420

4.4 Plugs (5 Amperes) No 22 16 352

4.5 Plugs (15 Amperes) No 4 30 120

4.6 Telephone plugs No 4 60 240

4.7 Air conditioner (1.5 tons) No 4 500 2,000

Sub-Total 4,292

171

5 Occupational Health and Safety W

orke

rs Builders Painters Plumbers Electricians Mechanics Other Total

8 2 1 1 0 0 12

OHS Tools and Requirements

No Description Unit Qty Unit Cost Total Cost Notes

5.1 Climbing shoes for electrical works No 1 50 50

5.2 High quality safety gloves suitable for electrical works

No 1 15 15

5.3 High quality long neck rubber Safety shoes suitable for labors who works in sewage

No 1 35 35

5.4 High quality safety rubber gloves suitable for labors who works in sewage (long to over the elbow and close from top)

No 1 25 25

5.5 Face mask for work in dust and smoky areas

No 8 25 200

5.6 High quality rubber safety shoes short neck

No 2 30 60

5.7 High quality safety gloves suitable for building works

No 10 20 200

5.8 High quality safety shoes suitable for labors who work in workshops, buildings… etc.

No 8 50 400

5.9 High quality safety helmets No 12 15 180

5.10 High quality safety vest (can be used by day time and night)

No 3 10 30

5.11 High quality safety cloths suitable for electrical works, mechanical works, building works… etc.

No 9 20 180

5.12 High quality First Aid Kit No 1 25 25

5.13 Managing OHS system L/S 100 100

Sub-Total 1,500

Total Cost 42,143.5

172

BoQ for construct new building in Bir Ahmed wellfield

No Description Unit Qty Unit Cost ($)

Total Cost ($)

Notes

1 Civil works

1.1 Soil drilling for the foundation with width of 80cm and depth of 95cm, along with cleaning, compacting (if necessary) and removal of soil according to supervisor engineer's instructions

m3 41.1 4 164.4

1.2 Placing a layer of crushed stones with thickness of 15cm and width of 60cm below the rock foundation

m3 32.4 4 129.6

1.3 Laying a concrete layer with a mix ratio of (1:3:6) using salt-resistant cement with thickness of 10cm and width of 60cm below the rock foundation

m3 32.4 10 324

1.4 Constructing of foundation using hard rock with width of 40cm and height of 60cm using a concrete mortar with a mix ratio of (1:3) and using a salt-resistant cement as well as filling the gaps between the rocks from the inside and outside according to supervisor engineer's instructions

m3 13 14 182

1.5 Ground beams using reinforced concrete with a mix ratio of (1:2:4) and dimensions of (20cm ×40cm) above the rock foundation. Reinforcement steel is as shown in the drawings and using salt-resistant cement.

m2 4.32 100 432

1.6 Hot tar painting specified for construction works to be used in rock foundation’s surfaces and ground beams’ faces buried underground.

m2 64.8 4 259.2

1.7 Refilling of soil around the rock foundation and the rooms floor using

m3 22 3 66

173

the soil excavated from drilling, good spraying and compacting every 20cm

1.8 Spraying insecticide on the building's floor and inside the foundation's trench

LS 200 200

1.9 Laying a 15cm crushed stone layer on the floors

m3 66 160 10,560

1.10 Laying a 10cm concrete layer over rooms' floor with a mix ratio of (1:2:4)

m3 66 60 3,960

1.11 Laying two layers of humidity isolation felt with hot tar on the rooms' floor and making the necessary protruding along the walls

m2 66 6 396

1.12 Supplying and installing good quality tiles for the building's floor using concrete mortar with a mix ratio of (1:3) according to supervisor engineer's instructions

m2 66 8 528

1.13 Supplying and constructing ceramic protruding for the building's floor according to supervisor engineer's instructions

m2 58 4 232

1.14 Building the interior walls with height of (2.7m) using hollow blocks (20cm X 20cm X 40cm) and concrete mortar with a mix ratio of (1:3)

m2 150 8 1,200

1.15 Reinforced concrete for the roof's lab thickness of 15cm, beams' dimensions (20cm X 30cm), columns' dimensions (20cm X 30cm), doors and windows' frames with a mix ratio of (1:2:4). Reinforcement steel should be according to drawings and supervisor engineer's instructions

ML 22.6 150 3,390

1.16 Laying two crossing layers of felt for the rooms' roof along with hot tar provided that it should rise about 10cm into the extension's wall

m3 260 5 1,300

1.17 Laying of inclination layer from ordinary concrete with thickness of

m3 260 3 780

174

(7cm) and mix ration of (1:2:4) according to the drawings and supervisor engineer’s instructions.

1.18 Supply and construction of rain water drains on the building’s roof and connecting these drains to a high-pressure plastic pipe of 3 inches diameter.

No 2 160 320

1.19 Plastering all inside and outside walls and the sides of the extensions using concrete mortar with a mix ratio of (1:3) according to the supervisor engineer’s instructions.

m2 490 4 1,960

1.20 Constructing a pavement around the building 1m wide and is made of crushed stones with thickness of 15cm and laying of a 10cm ordinary concrete with a mix ratio of (1:2:4) and adding tiles as well as rocks surrounding the pavement.

m2 31 5 155

Sub-Total 26,538.2

2 Painting

2.1 Painting the inside walls with a layer of foundation water paint, two layers of plaster and two layers of good quality oil paint. Colors to be determined by the supervisor engineer.

m2 115 6 690

2.2 Painting the inside of the room’s roof with a layer of foundation water paint, two layers of plaster and three layers of good quality oil paint. Colors to be determined by the supervisor engineer.

m2 66 6 396

2.3 Painting the outside of the extension’s walls with a layer of foundation water paint and three layers of good quality water paint. Colors to be determined by the supervisor engineer.

m2 309 6 1,854

175

Sub-Total 2,940

3 Doors and Windows

3.1 Supplying and constructing aluminum sliding windows equipped with a 6mm thick glass with a mosquito net + steel net (squares of 1cm) as a protection from the outside of good quality and painting it with an anti-corrosion paint and two layers of oil paint. Dimensions of windows (1.5m ×1.4m). Shape is to be determined by the supervisor engineer.

No 5 70 350

3.2 Supplying and constructing aluminum sliding windows equipped with a 6mm thick glass with a mosquito net + steel net (squares of 1cm) as a protection from the outside of good quality and painting it with an anti-corrosion paint and two layers of oil paint. Dimensions of windows (0.6m ×0.6m). Shape is to be determined by the supervisor engineer.

No 2 70 140

3.3 Supplying and constructing a steel door with 3mm pebbles one side with dimensions of (1m ×2.2m) and thickness of 5cm with a high-quality lock and all necessary accessories according to the supervisor engineer’s instructions.

No 3 120 360

Sub-Total 850

4 Electrical Wiring

4.1 Distribution panel (6 lines) No 1 160 160

4.2 Ceiling fan with speed controller No 6 160 960

4.3 Florescent lamps (4 ft) No 14 30 420

4.4 Plugs (5 Amperes) No 22 10 220

176

4.5 Plugs (15 Amperes) No 3 20 60

4.6 Telephone plugs No 3 40 120

Sub-Total 1,940

5 Occupational Health and Safety

Wor

kers

Builders Painters Plumbers Electricians Mechanics Other Total

8 2 1 1 0 0 12

OHS Tools and Requirements No Description Unit Qty Unit Cost Total Cost Notes

5.1 Climbing shoes for electrical works No 1 50 50

5.2 High quality safety gloves suitable for electrical works

No 1 15 15

5.3 High quality long neck rubber Safety shoes suitable for labors who works in sewage

No 1 35 35

5.4 High quality safety rubber gloves suitable for labors who works in sewage (long to over the elbow and close from top)

No 1 25 25

5.5 Face mask for work in dust and smoky areas

No 8 25 200

5.6 High quality rubber safety shoes short neck

No 2 30 60

5.7 High quality safety gloves suitable for building works

No 10 20 200

5.8 High quality safety shoes suitable for labors who work in workshops, buildings… etc.

No 8 50 400

5.9 High quality safety helmets No 12 15 180 5.10 High quality safety vest (can be used

by day time and night) No 3 10 30

5.11 High quality safety cloths suitable for electrical works, mechanical works, building works… etc.

No 9 20 180

5.12 High quality First Aid Kit No 1 25 25

5.13 Managing OHS system L/S 100 100

Sub-Total 1,500 Total Cost 33,768.2

177

BoQ for construct new building in Bir Nasser wellfield

No Description Unit Qty Unit Cost ($)

Total Cost ($)

Notes

1 Civil works

1.1 Soil drilling for the foundation with width of 80cm and depth of 95cm, along with cleaning, compacting (if necessary) and removal of soil according to supervisor engineer's instructions

m3 41.1 4 164.4

1.2 Placing a layer of crushed stones with thickness of 15cm and width of 60cm below the rock foundation

m3 32.4 4 129.6

1.3 Laying a concrete layer with a mix ratio of (1:3:6) using salt-resistant cement with thickness of 10cm and width of 60cm below the rock foundation

m3 32.4 10 324

1.4 Constructing of foundation using hard rock with width of 40cm and height of 60cm using a concrete mortar with a mix ratio of (1:3) and using a salt-resistant cement as well as filling the gaps between the rocks from the inside and outside according to supervisor engineer's instructions

m3 13 14 182

1.5 Ground beams using reinforced concrete with a mix ratio of (1:2:4) and dimensions of (20cm ×40cm) above the rock foundation. Reinforcement steel is as shown in the drawings and using salt-resistant cement.

m2 4.32 100 432

1.6 Hot tar painting specified for construction works to be used in rock foundation’s surfaces and ground beams’ faces buried underground.

m2 64.8 4 259.2

1.7 Refilling of soil around the rock foundation and the rooms floor using

m3 22 3 66

178

the soil excavated from drilling, good spraying and compacting every 20cm

1.8 Spraying insecticide on the building's floor and inside the foundation's trench

LS 200 200

1.9 Laying a 15cm crushed stone layer on the floors

m3 66 160 10,560

1.10 Laying a 10cm concrete layer over rooms' floor with a mix ratio of (1:2:4)

m3 66 60 3,960

1.11 Laying two layers of humidity isolation felt with hot tar on the rooms' floor and making the necessary protruding along the walls

m2 66 6 396

1.12 Supplying and installing good quality tiles for the building's floor using concrete mortar with a mix ratio of (1:3) according to supervisor engineer's instructions

m2 66 8 528

1.13 Supplying and constructing ceramic protruding for the building's floor according to supervisor engineer's instructions

m2 58 4 232

1.14 Building the interior walls with height of (2.7m) using hollow blocks (20cm X 20cm X 40cm) and concrete mortar with a mix ratio of (1:3)

m2 150 8 1,200

1.15 Reinforced concrete for the roof's lab thickness of 15cm, beams' dimensions (20cm X 30cm), columns' dimensions (20cm X 30cm), doors and windows' frames with a mix ratio of (1:2:4). Reinforcement steel should be according to drawings and supervisor engineer's instructions

ML 22.6 150 3,390

1.16 Laying two crossing layers of felt for the rooms' roof along with hot tar provided that it should rise about 10cm into the extension's wall

m3 260 5 1,300

1.17 Laying of inclination layer from ordinary concrete with thickness of

m3 260 3 780

179

(7cm) and mix ration of (1:2:4) according to the drawings and supervisor engineer’s instructions.

1.18 Supply and construction of rain water drains on the building’s roof and connecting these drains to a high-pressure plastic pipe of 3 inches diameter.

No 2 160 320

1.19 Plastering all inside and outside walls and the sides of the extensions using concrete mortar with a mix ratio of (1:3) according to the supervisor engineer’s instructions.

m2 490 4 1,960

1.20 Constructing a pavement around the building 1m wide and is made of crushed stones with thickness of 15cm and laying of a 10cm ordinary concrete with a mix ratio of (1:2:4) and adding tiles as well as rocks surrounding the pavement.

m2 31 5 155

Sub-Total 26,538.2

2 Painting

2.1 Painting the inside walls with a layer of foundation water paint, two layers of plaster and two layers of good quality oil paint. Colors to be determined by the supervisor engineer.

m2 115 6 690

2.2 Painting the inside of the room’s roof with a layer of foundation water paint, two layers of plaster and three layers of good quality oil paint. Colors to be determined by the supervisor engineer.

m2 66 6 396

2.3 Painting the outside of the extension’s walls with a layer of foundation water paint and three layers of good quality water paint. Colors to be determined by the supervisor engineer.

m2 309 6 1,854

180

Sub-Total 2,940

3 Doors and Windows

3.1 Supplying and constructing aluminum sliding windows equipped with a 6mm thick glass with a mosquito net + steel net (squares of 1cm) as a protection from the outside of good quality and painting it with an anti-corrosion paint and two layers of oil paint. Dimensions of windows (1.5m ×1.4m). Shape is to be determined by the supervisor engineer.

No 5 70 350

3.2 Supplying and constructing aluminum sliding windows equipped with a 6mm thick glass with a mosquito net + steel net (squares of 1cm) as a protection from the outside of good quality and painting it with an anti-corrosion paint and two layers of oil paint. Dimensions of windows (0.6m ×0.6m). Shape is to be determined by the supervisor engineer.

No 2 70 140

3.3 Supplying and constructing a steel door with 3mm pebbles one side with dimensions of (1m ×2.2m) and thickness of 5cm with a high-quality lock and all necessary accessories according to the supervisor engineer’s instructions.

No 3 120 360

Sub-Total 850

4 Electrical Wiring

4.1 Distribution panel (6 lines) No 1 160 160

4.2 Ceiling fan with speed controller No 6 160 960

4.3 Florescent lamps (4 ft) No 14 30 420

4.4 Plugs (5 Amperes) No 22 10 220

181

4.5 Plugs (15 Amperes) No 3 20 60

4.6 Telephone plugs No 3 40 120

Sub-Total 1,940

5 Occupational Health and Safety

Wor

kers

Builders Painters Plumbers Electricians Mechanics Other Total

8 2 1 1 0 0 12

OHS Tools and Requirements No Description Unit Qty Unit Cost Total Cost Notes

5.1 Climbing shoes for electrical works No 1 50 50

5.2 High quality safety gloves suitable for electrical works

No 1 15 15

5.3 High quality long neck rubber Safety shoes suitable for labors who works in sewage

No 1 35 35

5.4 High quality safety rubber gloves suitable for labors who works in sewage (long to over the elbow and close from top)

No 1 25 25

5.5 Face mask for work in dust and smoky areas

No 8 25 200

5.6 High quality rubber safety shoes short neck

No 2 30 60

5.7 High quality safety gloves suitable for building works

No 10 20 200

5.8 High quality safety shoes suitable for labors who work in workshops, buildings… etc.

No 8 50 400

5.9 High quality safety helmets No 12 15 180 5.10 High quality safety vest (can be used

by day time and night) No 3 10 30

5.11 High quality safety cloths suitable for electrical works, mechanical works, building works… etc.

No 9 20 180

5.12 High quality First Aid Kit No 1 25 25

5.13 Managing OHS system L/S 100 100

Sub-Total 1,500 Total Cost 33,768.2

182

ii. Rehabilitate Fuqum reservoir No.2 (4,500 m2)

It is one of the old tanks located in Al-Boraiqa directorate – refineries area. The tank is partially damaged (leaking) and requires immediate rehabilitation. Due to security concerns, taking pictures for the tank was not possible.

BoQ

No Description Unit Qty Unit Cost ($)

Total Cost ($)

Notes

1 Materials

1.1 Tanks welding Kg 100 15 1,500

1.2 Paintings (Sigma guard CSF 858) Liter 1,600 25 40,000

1.3 Paintings (Sigma - Aluminum) Liter 1,000 15 15,000

1.4 Paintings (Sigma cover 280) Liter 1,000 20 20,000

1.5 Paint thinner (Sigma 35-90) Liter 300 10 3,000

1.6 Paint thinner (Sigma 90- 91) Liter 200 10 2,000

1.7 Paint thinner (Sigma – Aluminum)

Liter 200 10 2,000

1.8 Welding torch with 30m pipes (including pressure gauges)

No 4 300 1,200

1.9 Angel grinder machine (9 inches) No 3 250 750

1.10 Cutting grinder wheels (9 inches) No 100 3 300

1.11 Grinding grinder wheels (9 inches)

No 100 3 300

Sub-Total 86,050

2 Works

2.1 Site preparation

LS 13,950

2.2 Opening holes in the tank's wall to allow maintenance works

2.3 Cleaning the tank's floor from sand and dirt

183

2.4 Cutting old layers of the tank's floor and replacing with new ones and welding works

2.5 Cutting the tank's ring and having it replaced with new one and welding works

2.6 Cleaning the tank's roof using paint and sand plus

2.7 Cleaning the tank's wall from the inside using sand plus and paint

2.8 Cleaning the tank's floor from the inside using sand plus and paint

2.9 Final cleaning, filling and sanitizing

Sub-Total 13,950

3 Occupational Health and Safety

Wor

kers

Builders Painters Plumbers Electricians

Mechanics Other Total

8 2 1 1 0 0 12

OHS Tools and Requirements

No Description Unit Qty Unit Cost

Total Cost Notes

3.1 High quality safety helmet with eye protection for welding works.

No 5 15 75

3.2 High quality safety helmet with eye protection for grinding works.

No 5 15 75

3.3 Ear protection mufflers No 10 6 60

3.4 Powder fire extinguisher (1Kg) No 2 20 40

3.5 Face mask for work in dust and smoky areas

No 5 25 125

3.6 High quality rubber safety shoes short neck

No 10 30 300

3.7 High quality safety gloves suitable for building works

No 11 20 220

3.8 High quality safety shoes suitable for labors who works in workshops, buildings… etc.

No 6 50 300

3.9 High quality safety gloves suitable for welding and grinding works

No 5 30 150

184

3.10 High quality safety helmet No 11 15 165

3.11 High quality safety vest (can be used by day time and night)

No 10 10 100

3.12 High quality safety cloths suitable for electrical work, mechanical works, building works…etc.

No 6 20 120

3.13 Safety belts No 5 50 250

3.14 High quality First Aid kit No 1 25 25

3.15 Managing OHS system L/S 1,000 1,000

Sun-Total 3,005

Total Cost 103,005

iii. Renovate lightening systems and supply celling fans Some pumping stations and other administration buildings require renovation for electrical wiring system, this include replacing old lamps and supplying new celling fans. The most urgent buildings requiring immediate renovation works are:

- Bir Nasser administration building

- Bir Ahmed administration building

- Al Fatah Minor Pumping Station

- Al Tahliah (Al Hiswa) Minor Pumping Station

- Slaughter house Minor Pumping Station

- Headquarter building

- Al Aidroos Minor Pumping Station

- Al Rowa Minor Pumping Station

- Al-Rawdhah Minor Pumping Station

185

BoQ

1 Materials and Works

No Description Unit Qty Unit Cost ($)

Total Cost ($)

Notes

1.1 Energy saving lamp 100W OR 125W with holder

No 200 14 2,800

1.2 Twin flex wire 1.5 mm SAUDI ORIGIN Role

Roll 108 24 2,592

1.3 Celling fans No 50 30 1,500

1.4 Labor's Cost LS 1,800

Sub-Total 8,692

2 OHS tools and requirements

Wor

kers

Builders Painters Plumbers Electricians Mechanics Other Total

0 0 0 9 0 0 9

OHS Tools and Requirements

No Description Unit Qty Unit Cost Total Cost Notes

2.1 Climbing shoes for electrical works No 9 50 450

2.2 High quality safety gloves suitable for electrical works

No 9 15 135

2.3 High quality safety helmets No 9 15 135

2.4 High quality safety cloths suitable for electrical works, mechanical works, building works… etc.

No 9 20 180

Sub-Total 900

Total Cost 9,592

186

Second: Equipment, Vehicles and Machines

1. Supply ten submersible pumps with motors

In order to increase the yield of wells, around forty submersible pumps need to be supplied and installed as a substitution for the out of service pumps. Currently, supplying ten pumps only is considered as high priority. Thus, it is recommended to supply and install the needed 40 pumps in four-phases project. In each phase, ten pumps with all accessories can be supplied and installed. Pumps, motors and all required accessories should be compatible with the following specifications:

No Item Specification

1 The Submersible Pump

1.1 Origin European union or equivalent

1.2 Capacity 20 L/s

1.3 Head 120 m

1.4 Pump Max Dia. 200 mm

1.5 Pump efficiency at duty point More than 75%

1.6 Clearance (well Dia. Pump max Dia.) 40 mm

1.7 Power 37 Kw

1.8 Casing (Pump bowl) CAST STEEL EN. 1.4308/AISI316

1.9 Impeller CAST STEEL EN. 1.4308/AISI316

1.10 Wear ring POM

1.11 Shaft and coupling EN. 1.4057&1.4462

1.12 Shaft sleeve EN. 1.4462/ AISI316

1.13 Bearing bush, Guide bearing EPDM

1.14 Pump delivery and housing EN. 1.4308/ AISI316

1.15 Check valve (none return valve) EN. 1.4308/ AISI316

1.16 Inlet strainer EN. 1.4301/ AISI316

1.17 Screw, studs, nuts, washers, etc. AISI 316

1.18 Installation type Vertical

2 The Submersible Motor

2.1 Origin European union or equivalent

187

2.2 Frame Rewind able

2.3 Rate power KW 37 KW

2.4 Service factors 1.15

2.5 The overall diameter (inches) 8

2.6 Rated speed (R.P.M) > 2850

2.7 Frequency (Hz) 50 +/- 1

2.85 Wire winding insulation material PE2 – PA

2.9 Motor winding insulation class V

2.10 Ambient water temp. (C) 45

2.11 Flow velocity (m/s) 0.5

2.12 Heavy duty thrust bearing (KN) >50

2.13 Phase 3

2.14 No. of starts per hours (cold / hot) >10/8

2.15 Voltage system (V) 380 – 400

2.16 Motor efficiency at duty point (%) 80 %

2.17 Motor speeds at duty point 2885

2.18 Voltage tolerance -/+ 10 %

2.19 Flange standard NEMA

2.20 IP 68

2.21 Shaft material EN. 1.4462

2.22 Shaft seal (mechanical seal) Silicon carbide

2.23 Motor sleeve EN 1.4404/ AISI 316

2.24 Motor housing Cast steel 316/ 1.4408 or superior

2.25 Diaphragm EPDM / N. R

2.26 Radial Bearing (Guide Bearing) Kingsbury or higher

2.27 Axial Bearing (thrust bearing) Graphite / S.S pads

2.28 Diaphragm cover Cast steel 316/ 1.4408

188

2.29 Rubber Parts NBR

2.30 Bolts, nuts, washers, etc. AISI 316

2.31 Filling cooling liquid Water

2.32 Overall efficiency at duty point 85%

2.33 Motor cable Copper motor cable at least 6 meters long, streamline cable, according VDE or KTW standards, plug – in type

3 The Control Panel

3.1 Voltage (V) 380 – 400

3.2 Starting type Soft start

3.3 Shaft seal (mechanical seal) Silicon carbide

3.4 Minimum output of the switchboard

At least 20% above the maximum required power of the motor

3.5 Control Panel should be provided with motor Electronic monitoring and protection unit such as (MP 204)

MP 204

3.6 Protection Control panel must provide with all protections and monitoring device such as

- Over load

- Thermostat motor protection relay for PT 100 , to protect the motor , starter winding from over heating

- Phase sequence and reverse protection

- Dry running protection

- Pressure protection

- Excess starting time protection

- Earth fault protection

- Gauge indication for volts, Ampere (with selector switches for both volts & amp. And 3 phase)

- Running hours counter

- Operation switch (manual – automatic and neutral)

- Emergence stop switch

189

Emergence system

4 The Submersible Cable

4.1 Size 4 × 25 mm2

4.2 Length 1300 M

4.3 Insulation type Double insulation

4.4 Heat resistant insulation Heat resistant insulation with a thick flame retardant sheath

4.5 Voltage test (V) 750/1200

4.6 Conductor 99% COPPER

4.7 Flexibility CLASS 5

4.8 Insulation Black poly chloroprene or equivalent material

5 The Riser Pipe

UPVC Riser pipe with All Accessories Required for Installation Pump According to the technical specification.

- Specially designed square threads have very high load holding capacity and their thread s do not corrode or rust or deteriorate.

- Special rubber seals are provided with the thread to ensure 100% leak proof at high pressure.

- Do not react with acidic or alkaline water.

- Socket type pipe.

- CLASS Heavy duty.

- Working pressure 26 BAR.

- Nominal length 3 M.

- Outside dia. 140 mm.

- Well thickness barrel min/max = 12/14 mm.

- Well thickness END min/max = 15/18 mm.

- Thickness portion of BOTH side = 250/250 mm. 6 The Step-down Transformer

6.1 Power 100 KVA

6.2 Ratio 11 KV – 0.4 KV

Total 250,000

190

2. Water Supply Network

PCWS intends to install leakages monitoring system. This will help in indicating leakage spots in the network and fixing these leakages as fast as possible. In addition, PCWS requires operational tools for maintenance and expansion works in the network. The following table is the BoQ for leakage monitoring system and the required operational tools.

BoQ

No Description Unit Qty Unit Cost ($)

Total Cost ($)

Notes

1 Leakage monitoring system

1.1 Pressure gauges with data logger No 8 350 2,800

1.2 Pipe locater No 2 1,500 3,000

1.3 Acoustic leak sounding system No 2 300 600

1.4 Portable ultrasonic flow meter No 2 750 1,500

1.5 Valve Cap Locator No 2 598 1,196

1.6 Detecting leaks device No 3 1,100 3,300

Sub-Total 12,396

2 Operation tools and equipment

2.1 Manual pipes cutting machine operated by petrol

No 6 2,000 12,000

2.2 Asphalt cutting machine No 4 2,100 8,400

2.3 Cement crushing hammer No 4 2,000 8,000

2.4 Manual electric drill (Hilti) for walls – 13mm bit

No 7 3,000 21,000

2.5 Manual electric drill (Hilti) for steel – 13mm bit

No 7 180 1,260

2.6 Complete Mechanical tool box (large) No 7 1,350 9,450

2.7 Complete Electrical tool box (large) No 7 600 4,200

2.8 Iron hammers (5 pounds) No 60 30 1,800

2.9 Iron hammers (1 Kg) No 60 25 1,500

2.10 Iron hammers (500 g) No 100 20 2,000

2.11 Shovels and the wooden stick No 600 10 6,000

191

2.12 Shovel-Axe combo with the stick No 600 10 6,000

2.13 Pipe wrench (8 inches) No 300 15 4,500

2.14 Pipe wrench (10 inches) No 300 18 5,400

2.15 Pipe wrench (12 inches) No 300 20 6,000

2.16 Pipe wrench (18 inches) No 300 25 7,500

2.17 Pipe wrench (24 inches) No 300 30 9,000

2.18 Pipe wrench (32 inches) No 70 55 3,850

2.19 Iron saw No 400 7 2,800

2.20 Iron chainsaw wrench No 1 1,000 1,000

2.21 Block chain (3 tons) No 8 150 1,200

2.22 Boxes for tools keeping No 90 23 2,070

Sub-Total 122,930

Total Cost 135,326

3. Pumping Stations

BoQ

No Description Unit Qty Unit Cost ($)

Total Cost ($)

Notes

1 Magnetic contactor No 1 2,000 2,000

2 4 core cables (20 m) No 500 8,500

3 Manual changeover switches (200A) No 10 200 2,000

4 Manual changeover switches (100A) No 10 140 1,400

5 Hydrostatic level sensor (0-20mA) with cable (10m)

No 40 600 24,000

6 Timer on delay 220V AC No 50 40 2,000

7 Thermal-magnetic motor circuit breakers

No 50 200 10,000

Total Cost 49,900

192

4. Maintenance workshops

BoQ

No Description Unit Qty Unit Cost ($)

Total Cost ($)

Notes

1 Truck crane (5 tons) No 1 110,000 110,000

Total Cost 110,000

193

9. Urgent Intervention for Sanitation System

No Sub-Project Name Estimated Cost ($)

First: Rehabilitation Intervention

1 Building

1.1 Expand headquarter building 34,968.2

1.2 Construct new administrative building in Al-Boraiqa 29,536.5

2 Pumping Station

2.1 Complete rehabilitation for Al-Mansoora main pumping station 305,068

2.2 Complete rehabilitation for Abbas pumping station in Al-Mansoora 256,770

Sub-Total 626,342.7

No Sub-Project Name Estimated Cost ($)

Second: Supplying Vehicles, Machines and Tools

1 Offices and Buildings

1.1 Furnishing administrative buildings in directories 37,104

2 Maintenance Workshops

2.1 Mechanical and pneumatic tools and equipment 31,606

2.2 Spare parts for cars and vehicles 4,724

3 Occupational Health and Safety Management

3.1 Spare parts for fixing OHS equipment 36,000

3.2 OHS equipment and tools 100,825

Sub-Total 210,259

Total 836,601.7

194

First: Rehabilitation Innervation

Rehabilitation pumping stations are considered as the most urgent interventions to improve the sewage infrastructure in Aden city. Currently, rehabilitation Al-Mansoora main pumping station and Abbas minor pumping station are the most two stations need immediate maintenance works.

BoQ for Al-Mansoora pumping station

No Description Unit Qty Unit Cost ($)

Total Cost ($)

Notes

1 Pumps & Panels (400L/S) @ 32m No 3 71,666 214,998 Vert. dry well

2 Gate valves (400mm) No 4 2,000 8,000

3 NRV (400mm) No 3 2,300 6,900

4 Discharge line valves (800mm) No 1 1,100 1,100

5 Penstock No 2 2,000 4,000

6 Electrical overhead crane (5 tons) Set 1 6,000 6,000 Rent

7 Mechanical screen for wastewater No 1 50,000 50,000 Size depends on inlet tank’s depth

8 Gate valves (450mm) No 4 2,300 9,200

9 Portable diesel pump (250mm Dia) No 1 80,000 80,000

Sub-Total 300,198

10 Occupational Health and Safety

Wor

kers

Builders Painters Plumbers Electricians Mechanics Other (Crane driver)

Total

10 0 5 5 5 1 20

OHS Tools and Requirements

No Description Unit Qty Unit Cost Total Cost Notes

10.1 Climbing shoes for electrical works No 5 50 250

10.2 High quality safety gloves suitable for electrical works

No 5 15 75

195

10.3 High quality long neck rubber Safety shoes suitable for labors who works in sewage

No 5 35 175

10.4 High quality safety rubber gloves suitable for labors who works in sewage (long to over the elbow and close from top)

No 5 25 125

10.5 Full Face mask with all accessories from BULLARD company that can be used in sewage

No 2 350 700

10.6 Face mask for work in dust and smoky areas

No 20 25 500

10.7 High quality rubber safety shoes short neck

No 5 30 150

10.8 High quality safety gloves suitable for building works

No 16 20 320

10.9 High quality safety shoes suitable for labors who works in workshops, buildings… etc.

No 16 50 800

10.10 High quality safety helmet No 26 15 390

10.11 High quality safety vest (can be used by day time and night)

No 10 10 100

10.12 High quality safety cloths suitable for electrical work, mechanical works, building works…etc.

No 10 20 200

10.13 High quality First Aid kit No 1 25 25

10.14 Managing OHS system L/S 1,000 1,000

Sub-Total 4,870

Total 305,068

BoQ for Abbas pumping station

No Description Unit Qty Unit Cost ($)

Total Cost ($)

Notes

1 Materials and works

1.1 Pumps & Panels (210L/S) @ 25m No 2 40,000 80,000 Vert. dry well

1.2 Gate valves (200mm) No 6 1,500 9,000

1.3 NRV (200mm) No 3 1,800 5,400

196

1.4 Discharge line valves (400mm) No 1 2,500 2,500

1.5 Penstock No 2 2,000 4,000

1.6 Electrical overhead crane (5 tons) Set 1 6,000 6,000 Rent

1.7 Mechanical screen for wastewater No 1 70,000 70,000 Size depends on inlet tank’s depth

1.8 Portable diesel pump (200mm Dia) No 1 75,000 75,000

Sub-Total 251,900

2 Occupational Health and Safety

Wor

kers

Builders Painters Plumbers Electricians Mechanics Other (Crane driver)

Total

10 0 5 5 5 1 20

OHS Tools and Requirements

No Description Unit Qty Unit Cost Total Cost Notes

2.1 Climbing shoes for electrical works No 5 50 250

2.2 High quality safety gloves suitable for electrical works

No 5 15 75

2.3 High quality long neck rubber Safety shoes suitable for labors who works in sewage

No 5 35 175

2.4 High quality safety rubber gloves suitable for labors who works in sewage (long to over the elbow and close from top)

No 5 25 125

2.5 Full Face mask with all accessories from BULLARD company that can be used in sewage

No 2 350 700

2.6 Face mask for work in dust and smoky areas

No 20 25 500

2.7 High quality rubber safety shoes short neck

No 5 30 150

2.8 High quality safety gloves suitable for building works

No 16 20 320

2.9 High quality safety shoes suitable for labors who works in workshops, buildings… etc.

No 16 50 800

197

2.10 High quality safety helmet No 26 15 390

2.11 High quality safety vest (can be used by day time and night)

No 10 10 100

2.12 High quality safety cloths suitable for electrical work, mechanical works, building works…etc.

No 10 20 200

2.13 High quality First Aid kit No 1 25 25

2.14 Managing OHS system L/S 1,000 1,000

Sub-Total 4,870

Total 256,770

BoQ for expand headquarter building

No Description Unit Qty Unit Cost ($)

Total Cost ($)

Notes

1 Civil works

1.1 Soil drilling for the foundation with width of 80cm and depth of 95cm, along with cleaning, compacting (if necessary) and removal of soil according to supervisor engineer's instructions

m3 41.1 4 164.4

1.2 Placing a layer of crushed stones with thickness of 15cm and width of 60cm below the rock foundation

m3 32.4 4 129.6

1.3 Laying a concrete layer with a mix ratio of (1:3:6) using salt-resistant cement with thickness of 10cm and width of 60cm below the rock foundation

m3 32.4 10 324

1.4 Constructing of foundation using hard rock with width of 40cm and height of 60cm using a concrete mortar with a mix ratio of (1:3) and using a salt-resistant cement as well as filling the gaps between the rocks from the inside and outside according to supervisor engineer's instructions

m3 13 14 182

198

1.5 Ground beams using reinforced concrete with a mix ratio of (1:2:4) and dimensions of (20cm ×40cm) above the rock foundation. Reinforcement steel is as shown in the drawings and using salt-resistant cement.

m2 4.32 100 432

1.6 Hot tar painting specified for construction works to be used in rock foundation’s surfaces and ground beams’ faces buried underground.

m2 64.8 4 259.2

1.7 Refilling of soil around the rock foundation and the rooms floor using the soil excavated from drilling, good spraying and compacting every 20cm

m3 22 3 66

1.8 Spraying insecticide on the building's floor and inside the foundation's trench

LS 200 200

1.9 Laying a 15cm crushed stone layer on the floors

m3 66 160 10,560

1.10 Laying a 10cm concrete layer over rooms' floor with a mix ratio of (1:2:4)

m3 66 60 3,960

1.11 Laying two layers of humidity isolation felt with hot tar on the rooms' floor and making the necessary protruding along the walls

m2 66 6 396

1.12 Supplying and installing good quality tiles for the building's floor using concrete mortar with a mix ratio of (1:3) according to supervisor engineer's instructions

m2 66 8 528

1.13 Supplying and constructing ceramic protruding for the building's floor according to supervisor engineer's instructions

m2 58 4 232

1.14 Building the interior walls with height of (2.7m) using hollow blocks (20cm X 20cm X 40cm) and concrete mortar with a mix ratio of (1:3)

m2 150 8 1,200

1.15 Reinforced concrete for the roof's lab thickness of 15cm, beams'

ML 22.6 150 3,390

199

dimensions (20cm X 30cm), columns' dimensions (20cm X 30cm), doors and windows' frames with a mix ratio of (1:2:4). Reinforcement steel should be according to drawings and supervisor engineer's instructions

1.16 Laying two crossing layers of felt for the rooms' roof along with hot tar provided that it should rise about 10cm into the extension's wall

m3 260 5 1,300

1.17 Laying of inclination layer from ordinary concrete with thickness of (7cm) and mix ration of (1:2:4) according to the drawings and supervisor engineer’s instructions.

m3 260 3 780

1.18 Supply and construction of rain water drains on the building’s roof and connecting these drains to a high-pressure plastic pipe of 3 inches diameter.

No 2 160 320

1.19 Plastering all inside and outside walls and the sides of the extensions using concrete mortar with a mix ratio of (1:3) according to the supervisor engineer’s instructions.

m2 490 4 1,960

1.20 Constructing a pavement around the building 1m wide and is made of crushed stones with thickness of 15cm and laying of a 10cm ordinary concrete with a mix ratio of (1:2:4) and adding tiles as well as rocks surrounding the pavement.

m2 31 5 155

Sub-Total 26,538.2

2 Painting

2.1 Painting the inside walls with a layer of foundation water paint, two layers of plaster and two layers of good quality oil paint. Colors to be

m2 115 6 690

200

determined by the supervisor engineer.

2.2 Painting the inside of the room’s roof with a layer of foundation water paint, two layers of plaster and three layers of good quality oil paint. Colors to be determined by the supervisor engineer.

m2 66 6 396

2.3 Painting the outside of the extension’s walls with a layer of foundation water paint and three layers of good quality water paint. Colors to be determined by the supervisor engineer.

m2 309 6 1,854

Sub-Total 2,940

3 Doors and Windows

3.1 Supplying and constructing aluminum sliding windows equipped with a 6mm thick glass with a mosquito net + steel net (squares of 1cm) as a protection from the outside of good quality and painting it with an anti-corrosion paint and two layers of oil paint. Dimensions of windows (1.5m ×1.4m). Shape is to be determined by the supervisor engineer.

No 5 70 350

3.2 Supplying and constructing aluminum sliding windows equipped with a 6mm thick glass with a mosquito net + steel net (squares of 1cm) as a protection from the outside of good quality and painting it with an anti-corrosion paint and two layers of oil paint. Dimensions of windows (0.6m ×0.6m). Shape is to be determined by the supervisor engineer.

No 2 70 140

3.3 Supplying and constructing a steel door with 3mm pebbles one side with

No 3 120 360

201

dimensions of (1m ×2.2m) and thickness of 5cm with a high-quality lock and all necessary accessories according to the supervisor engineer’s instructions.

Sub-Total 850

4 Electrical Wiring

4.1 Distribution panel (6 lines) No 1 160 160

4.2 Ceiling fan with speed controller No 6 160 960

4.3 Florescent lamps (4 ft) No 14 30 420

4.4 Plugs (5 Amperes) No 22 10 220

4.5 Plugs (15 Amperes) No 3 20 60

4.6 Telephone plugs No 3 40 120

4.7 Air conditioner (1.5 tons) No 3 400 1,200

Sub-Total 3,140

5 Occupational Health and Safety

Wor

kers

Builders Painters Plumbers Electricians Mechanics Other Total

8 2 1 1 0 0 12

OHS Tools and Requirements

No Description Unit Qty Unit Cost Total Cost Notes

5.1 Climbing shoes for electrical works No 1 50 50

5.2 High quality safety gloves suitable for electrical works

No 1 15 15

5.3 High quality long neck rubber Safety shoes suitable for labors who works in sewage

No 1 35 35

5.4 High quality safety rubber gloves suitable for labors who works in sewage (long to over the elbow and close from top)

No 1 25 25

5.5 Face mask for work in dust and smoky areas

No 8 25 200

5.6 High quality rubber safety shoes short neck

No 2 30 60

202

5.7 High quality safety gloves suitable for building works

No 10 20 200

5.8 High quality safety shoes suitable for labors who works in workshops, buildings… etc.

No 8 50 400

5.9 High quality safety helmet No 12 15 180

5.10 High quality safety vest (can be used by day time and night)

No 3 10 30

5.11 High quality safety cloths suitable for electrical work, mechanical works, building works…etc.

No 9 20 180

5.12 High quality First Aid kit No 1 25 25

5.13 Managing OHS system L/S 100 100

Sub-Total 1,500

Total Cost 34,968.2

BoQ for construct a new administrative building in Al-Boraiqa

No Description Unit Qty Unit Cost ($)

Total Cost ($)

Notes

1 Civil works

1.1 Soil drilling for the foundation with width of 60cm and depth of 95cm, along with cleaning, compacting (if necessary) and removal of soil according to supervisor engineer's instructions

m3 41.1 5 205.5

1.2 Placing a layer of crushed stones with thickness of 15cm and width of 60cm below the rock foundation

m3 32.4 10 324

1.3 Laying a concrete layer with a mix ratio of (1:3:6) using salt-resistant cement with thickness of 10cm and width of 60cm below the rock foundation

m3 32.4 10 324

1.4 Constructing of foundation using hard rock with width of 40cm and height of 60cm using a concrete mortar with a mix ratio of (1:3) and

m3 13 50 650

203

using a salt-resistant cement as well as filling the gaps between the rocks from the inside and outside according to supervisor engineer's instructions

1.5 Ground beams using reinforced concrete with a mix ratio of (1:2:4) and dimensions of (20cm ×40cm) above the rock foundation. Reinforcement steel is as shown in the drawings and using salt-resistant cement.

m2 4.32 260 1,123.2

1.6 Hot tar painting specified for construction works to be used in rock foundation’s surfaces and ground beams’ faces buried underground.

m2 64.8 6 388.8

1.7 Refilling of soil around the rock foundation and the rooms floor using the soil excavated from drilling, good spraying and compacting every 20cm

m3 22 4 88

1.8 Spraying insecticide on the building's floor and inside the foundation's trench

LS 200 200

1.9 Laying a 15cm crushed stone layer on the floors

m3 66 8 528

1.10 Laying a 10cm concrete layer over rooms' floor with a mix ratio of (1:2:4)

m3 66 9 594

1.11 Laying two layers of humidity isolation felt with hot tar on the rooms' floor and making the necessary protruding along the walls

m2 66 10 660

1.12 Supplying and installing good quality tiles for the building's floor using concrete mortar with a mix ratio of (1:3) according to supervisor engineer's instructions

m2 66 16 1,056

1.13 Supplying and constructing ceramic protruding for the building's floor according to supervisor engineer's instructions

m2 60 8 480

204

1.14 Building the interior walls with height of (2.7m) using hollow blocks (20cm X 20cm X 40cm) and concrete mortar with a mix ratio of (1:3)

m2 155 14 2,170

1.15 Reinforced concrete for the roof's lab thickness of 15cm, beams' dimensions (20cm X 30cm), columns' dimensions (20cm X 30cm), doors and windows' frames with a mix ratio of (1:2:4). Reinforcement steel should be according to drawings and supervisor engineer's instructions

ML 23 260 5,980

1.16 Laying two crossing layers of felt for the rooms' roof along with hot tar provided that it should rise about 10cm into the extension's wall

m3 260 10 2,600

1.17 Laying of inclination layer from ordinary concrete with thickness of (7cm) and mix ration of (1:2:4) according to the drawings and supervisor engineer’s instructions.

m3 260 8 2,080

1.18 Supply and construction of rain water drains on the building’s roof and connecting these drains to a high-pressure plastic pipe of 3 inches diameter.

No 2 40 80

1.19 Plastering all inside and outside walls and the sides of the extensions using concrete mortar with a mix ratio of (1:3) according to the supervisor engineer’s instructions.

m2 490 6 2,940

1.20 Constructing a pavement around the building 1m wide and is made of crushed stones with thickness of 15cm and laying of a 10cm ordinary concrete with a mix ratio of (1:2:4) and adding tiles as well as rocks surrounding the pavement.

m2 32 10 320

Sub-Total 22,791.5

205

2 Painting

2.1 Painting the inside walls with a layer of foundation water paint, two layers of plaster and two layers of good quality oil paint. Colors to be determined by the supervisor engineer.

m2 115 4 460

2.2 Painting the inside of the room’s roof with a layer of foundation water paint, two layers of plaster and three layers of good quality oil paint. Colors to be determined by the supervisor engineer.

m2 66 3.4 224.4

2.3 Painting the outside of the extension’s walls with a layer of foundation water paint and three layers of good quality water paint. Colors to be determined by the supervisor engineer.

m2 309 3.4 1,050.6

Sub-Total 1,735

3 Doors and Windows

3.1 Supplying and constructing aluminum sliding windows equipped with a 6mm thick glass with a mosquito net + steel net (squares of 1cm) as a protection from the outside of good quality and painting it with an anti-corrosion paint and two layers of oil paint. Dimensions of windows (1.5m ×1.4m). Shape is to be determined by the supervisor engineer.

No 5 160 800

3.2 Supplying and constructing aluminum sliding windows equipped with a 6mm thick glass with a mosquito net + steel net (squares of 1cm) as a protection from the outside of good quality and painting it with an anti-corrosion paint and two layers of oil paint. Dimensions of

No 2 70 140

206

windows (0.6m ×0.6m). Shape is to be determined by the supervisor engineer.

3.3 Supplying and constructing a steel door with 3mm pebbles one side with dimensions of (1m ×2.2m) and thickness of 5cm with a high-quality lock and all necessary accessories according to the supervisor engineer’s instructions.

No 3 200 600

Sub-Total 1,540

4 Electrical Wiring

4.1 Distribution panel (12 lines) No 2 240 480

4.2 Ceiling fan with speed controller No 8 50 400

4.3 Florescent lamps (4 ft) No 20 30 600

4.4 Plugs (5 Amperes) No 22 10 220

4.5 Plugs (15 Amperes) No 5 30 150

4.6 Telephone plugs No 4 30 120

Sub-Total 1,970

5 Occupational Health and Safety

Wor

kers

Builders Painters Plumbers Electricians Mechanics Other Total

8 2 1 1 0 0 12

OHS Tools and Requirements

No Description Unit Qty Unit Cost Total Cost Notes

5.1 Climbing shoes for electrical works No 1 50 50

5.2 High quality safety gloves suitable for electrical works

No 1 15 15

5.3 High quality long neck rubber Safety shoes suitable for labors who works in sewage

No 1 35 35

5.4 High quality safety rubber gloves suitable for labors who works in sewage (long to over the elbow and close from top)

No 1 25 25

207

5.5 Face mask for work in dust and smoky areas

No 8 25 200

5.6 High quality rubber safety shoes short neck

No 2 30 60

5.7 High quality safety gloves suitable for building works

No 10 20 200

5.8 High quality safety shoes suitable for labors who works in workshops, buildings… etc.

No 8 50 400

5.9 High quality safety helmet No 12 15 180

5.10 High quality safety vest (can be used by day time and night)

No 3 10 30

5.11 High quality safety cloths suitable for electrical work, mechanical works, building works…etc.

No 9 20 180

5.12 High quality First Aid kit No 1 25 25

5.13 Managing OHS system L/S 100 100

Sub-Total 1,500

Total Cost 42,143.5

208

Second: Equipment, Vehicles and Machines

BoQ

No Description Unit Qty Unit Cost ($)

Total Cost ($)

Notes

1 Furnishing administrative buildings in the directories

1.1 Desks No 40 180 7,200 5 for each

1.2 Desktop computer (Lenovo) + (hp) printers

No 8 1,600 12,800 1 for each

1.3 Laptops No 8 500 4,000 1 for each

1.4 Air conditioner No 16 480 7,680 2 for each

1.5 Chairs No 48 88 4,224 6 for each

1.6 Water coolers No 8 200 1,600 1 for each

Sub-Total 37,504

2 Maintenance Workshops

4.1 Equipment and tools

2.1

2.1.1 Geared head lathe machine with the following specifications:

- Max turning diameter over bed:450mm - Max swing over gap: 685mm - Max length of work: 900/1500mm - Main drive motor: 4KW

No 1 9,000

2.1.2 Hydraulic hose crimping machine with the following specifications:

- Able to press hydraulic flexible rubber hose terminal with sleeve joint - Diameter range: 1/4'' to 4'' or 6mm to 100mm

No 1 1,000

2.1.3 Electric hand drill with the following specifications: - Max. diameter of drilling 13mm - Power:600W, 250V, 50Hz

No 3 420

209

2.1.4 Assorted mechanical hand tools for vehicles maintenance consist of: - Open end spanner set from small size to big size - Adjustable open end spanner set from small size to big size - Adjustable open end spanner (for pipe use) set from small size to big size - Pin spanner set from small size to big size - Box spanner set from small size to big size

No 3 3,000

2.1.5 Complete aluminum air compressor with the following specification: - Inlet pressure: 7.5 bar - Discharge capacity of Air: 1m3/min - Suitable tank of air with Auto condensate drainage system - Power:12KW,3¬phase 380V, 50Hz

No 1 5,000

2.1.6 Portable air compressor with diesel engine (15¬20 Kw) mounted on two wheels trolley

No 1 4,000

2.1.7 Galvanized steel pipe 1/2 X 20m No 20 100

2.1.8 Filter-regulator-lubricator 1919F 1/4''-3/8''-1/2'' No 1 40

2.1.9 Filter-regulator-lubricator 1919FE1/4'' No 3 8,400

2.1.10 Mini lubricators Ø1/4'' No 3 21

2.1.11 Mini water separator Ø1/4'' No 3 30

2.1.12 ISO 32 lubricating oil No 3 15

2.1.13 Mini grease gun No 1 10

2.1.14 Quick couplings Italian Ø1/4'' No 4 20

2.1.15 Quick couplings euro Ø1/4'' No 4 20

2.1.16 Universal ball quick couplers, shockproof rubber Ø1/4'' Male threaded

No 2 10

210

2.1.17 Universal ball quick couplers, shockproof rubber Ø1/4'' Female threaded

No 2 10

2.1.18 Rotary universal coupler Ø1/4'' No 2 6

2.1.19 Compact reversible impact wrench bolt capacity (M16-24mm), (M14- 21mm)

No 1 200

2.1.20 Compact reversible impact wrench bolt capacity (M24-36mm), (M20- 30mm)

No 1 200

2.1.21 Impact reversible ratchet wrench bolt capacity (M10-16mm), (M8- 13mm) No 1 15

2.1.22 Reversible air screwdriver bit holder 1/4'' No 1 80

2.1.23 Reversible drill, made from composited material (Chuck capacity 1/10mm) (380watt)

No 1 80

2.1.24 Reversible drill Chuck capacity 1.5/13 (550watt) (Spindle thread 1/2'' - 20Unc

No 1 100

2.1.25 Angle grinders (10.5 free speed RPM) (Grinding disc size 125mm) (700Watt) No 1 120

2.1.26 Multi use sander with accessories (3.5 free speed RPM) (340watt) (1/4'' air inlet GAS)

No 1 100

2.1.27 Air hammer strokes/min 3500 chisel inlet (1/4'' air inlet GAS) No 1 160

2.1.28 Blow and tire inflators No 2 24

2.1.29 Polyurethane recoil hoses, 95shore, extendable up to 15m. (BSP Ø1/4''', 8mm*12mm)

No 5 150

2.1.30 Braided polyurethane hose, 95shore, 12 m long (BSP Ø1/4'', 8mm*12mm) No 5 150

211

2.1.31 Braided polyurethane hose, 95shore, 50 m long (BSP Ø1/4'', 8mm*12mm) No 5 125

Sub-Total 31,606

2.2

Spare parts for cars

2.2.1 Hilux98 single cabinet, Diesel Engine (spare parts): - Engine with all accessories - Front glass - Radiator tank

1,896

2.2.2 Isuzo2004 single cabinet, Diesel (spare parts): - Engine with all accessories - Radiator tank - 70Ah battery - Tires (195 X 14)

1,464

2.2.3 Shemco motorbike, 3 tires (spare parts): - Motorbike engine 200 CC - Gearbox - Gearbox shaft - Brake discs - Tires (155 X 12)

444

2.2.4 Suzuki carry 99 (spare parts): - Engine with all accessories - Radiator tank - Tires (165 X 13)

920

Sub-Total

4,724

3 Occupational Health and Safety Management

3.1

Spare parts

3.1.1 Electronic compressor control/Complete display unit, Model Number: MSA280EF-Low noise

No

2 3,000 6,000

3.1.2 Full face mask from BULLARD Company-Spectrum-PD (Breathing

No 10 350 3,500

212

system) with all accessories for sewage

3.1.3 Filters for MSA280EF-Low noise No 20 45 900

3.1.4 Oil for Compressor L 200 13 26,000

Sub-Total 36,000

3.2

OHS equipment and tools

3.2.1 Air portable ventilation with ducting 8m x 200mm (SVB-G8)

No 2 4,500 9,000

3.2.2 High pressure breathing air compressors (MAS 280EF LOW NOISE)

No 1 25,000 25,000

3.2.3 Respiratory system (MP - 2300ENB) with cylinders and hoses

No 2 2,900 5,800

3.2.4 Insulated box fan No 2 25,000 5,000

3.2.5 Hydraulic Manhole cover lifter No 2 900 1,800

3.2.6 Air supply hose 10m No 8 50 400

3.2.7 Full Face mask with all accessories from BULLARD company that can be used in sewage

No 4 350 1,400

3.2.8 Face mask for work in dust and smoky areas

No 25 25 625

3.2.9 Safety belt for electrical works No 5 50 250

3.2.10 Climbing shoes for electrical works No 5 50 250

3.2.11 Tripod with Chain hoist (for lifting labor)

No 5 3,000 15,000

3.2.12 High quality Portable Extension Ladder

No 2 100 200

3.2.13 Head Lamps (water proof) No 20 60 1,200

3.2.14 High quality safety helmet with eye protection for welding works.

No 10 15 150

3.2.15 High quality safety helmet with eye protection for grinding works.

No 10 15 150

213

3.2.16 Sound proofing for pumping station labor

No 50 6 300

3.2.17 Earing protection from sewage water No 2 250 500

3.2.18 Powder fire extinguisher (6Kg) 20 50 1,000

3.2.19 Powder fire extinguisher (1Kg) 20 20 400

3.2.20 High quality long neck rubber Safety shoes suitable for labors who works in sewage (long to over the knee and close from top)

100 35 3,500

3.2.21 High quality rubber safety shoes short neck

No 100 30 3,000

3.2.22 High quality safety shoes suitable for labors who works in workshops, buildings… etc.

No 50 50 2,500

3.2.23 High quality safety rubber gloves suitable for labors who works in sewage (long to over the elbow and close from top)

No 100 25 2,500

3.2.24 High quality safety gloves suitable for electrical works

20 30 600

3.2.25 High quality safety gloves suitable for welding and grinding works

50 30 1,500

3.2.26 High quality safety gloves suitable for building works

20 20 400

3.2.27 High quality safety gloves suitable for mechanic works

20 25 500

3.2.28 High quality safety gloves suitable for laboratory works

20 20 400

3.2.29 High quality safety cloths suitable for sewage works

16 500 8,000

3.2.30 High quality safety vest (can be used by day time and night)

200 10 2,000

214

3.2.31 High quality safety cloths suitable for electrical work, mechanical works, building works…etc.

200 20 4,000

3.2.32 High quality First Aid kit (can be fixed horizontally or vertically in the cars)

100 25 2,500

3.2.33 High quality First Aid kit for pumping stations, work shop, laboratory, main office, …etc.

25 40 1,000

Sub-Total 100,825

Total Cost 136,825

215

10. Summary of Total Cost for Aden's Intervention

No TOTAL COST FOR INTERVENTIONS IN ADEN Estimated Cost ($)

1 Cleaning Fund

1.1 Rehabilitation Intervention 130,301.68

1.2 Supporting Vehicles, Machines, and Tools 1,790,000

Sub-Total 1,920,301.68

2 Water Supply System

2.1 Rehabilitation Intervention 609,990.95

2.2 Supporting Vehicles, Machines, and Tools 547,400

Sub-Total 1,157,390.95

3 Sanitation System

3.1 Rehabilitation Intervention 626,342.7

3.2 Supporting Vehicles, Machines, and Tools 210,259

Sub-Total 836,601.7

Total 3,914,294.33

216

Appendices

217

Appendix 1: Aden Map

218

Appendix 2: Overview Map of the Water Supply System

219

Appendix 3: Overview Map of the Sewerage System

220

Appendix 4: Projects by Other Organizations/Parties

First: Cleaning Fund

No Project Description Location Funding Agency Status Notes

1 Supplying 10 Isuzu vehicles with internal compactor (8 tons) 8 directorates UNOPS Completed 2019

2 Supplying 14 Isuzu tippers (4 tons) 8 directorates UNOPS Completed 2019

3 Supplying 1 loader for the dumpsite Dumpsite UNOPS Completed 2018

4 Supplying 600 metal containers (1.1 m3) 8 directorates UNOPS Completed 2019

5 Supply 1 bulldozer Dumpsite UNOPS Completed 2019

6 Supply and install a new truck scale (100 tons) Dumpsite UNOPS Completed 2019

7 Construct a new building for managing the new scale Dumpsite UNOPS Completed 2019

8 Supply 3 Hino tippers (8 tons) 8 directorates UNHCR Completed 2019

9 Supply small (Bobcat) Dar Sa'd – Basateen Area

UNHCR Completed 2019

10 Rehabilitate the transfer station Al-Mansoora UNOPS Future -

11 Rehabilitate the maintenance workshop in Dar Sa'd Dar Sa'd UNOPS Future -

Second: Public Corporation for Water and Sewage

No Project Description Location Funding Agency Status Notes

1 Rehabilitate the disinfection units Wellfields and Al-Barzakh St.

Mercy Corps Future -

2 Central Laboratory Al-Barzakh St. Mercy Corps Future -

3 Rehabilitate all waste water treatment plants Al-Mansoora, Khormaksar and Al-Boraiqa

Arab Fund Future -

4 Rehabilitate fuel tanks in Al-Barzakh station Al-Barzakh St. UN Habitat Future -

221

Appendix 5: Required Interventions for the Infrastructure Rehabilitation and Restoration of Cleaning Fund Services

Part One: Civil works on rehabilitating/reconstruction buildings and facilities

No Project Description Priority Cost

(USD) Notes

1 Al-Mansoora transfer station

1.1 Rehabilitate the dumping hill Urgent - Negotiations with UNOPS to carry out this project

1.2 Rehabilitate the metal funnel Urgent -

1.3 Reconstruct the damaged part of the fence Medium -

1.4 Overhaul the truck scale Urgent -

2 Bir Na'ama dumpsite

2.1 Rehabilitate the buildings in the dumpsite Urgent 2,900

2.2 Complete the construction of the recycling hangar Medium -

2.3 Build a fence surrounding the dumpsite Medium -

3 Cleaning administrations in directorates

3.1 Rehabilitate administration building in Al-Tawahi Urgent 7,069

3.2 Construct a new building for cleaning administration in Al-Mu'alla Urgent 24,151

3.3 Rehabilitate administration building in Crater Urgent 11,938.5

3.4 Construct a new warehouse for the cleaning administration in Khormaksar Urgent 8,959.9

3.5 Rehabilitate administration building in Al-Mansoora Urgent 10,329.68

3.6 Rehabilitate administration building in Al-Sheikh Othman Urgent 7,297.6

3.7 Rehabilitate administration building in Dar Sa'd Urgent 8,365.5

3.8 Construct a new building for cleaning administration in Al-Boraiqa Urgent 24,151

4 Maintenance workshops

4.1 Rehabilitate buildings and facilities in Khormaksar maintenance workshop Urgent 7,069

4.2 Rehabilitate buildings and facilities in Al-Mansoora maintenance workshop Urgent 5,790

4.3 Rehabilitate buildings and facilities in Dar Sa'd maintenance workshop Urgent - Negotiations with UNOPS to

222

carry out this project

4.4 Build a ground reservoir (10,000 liters) for each maintenance workshop Low 15,000

4.5 Rehabilitate the warehouses in the three maintenance workshops Medium 45,000

4.6 Rehabilitate the fences surrounding maintenance workshops Low -

5 Afforestation and Parks Administration

5.1 Build eight elevated water tanks (8,000 liters) Medium 14,400

Part Two: Vehicles, machines and tools

No Project Description Qty Priority Cost (USD)

Notes

1 Cleaning administrations in directorates

1.1 Metal garbage containers (1m3) 1,500 Urgent 525,000 Three phases

1.2 Metal garbage containers (3m3) 100 Urgent 150,000 Two Phases

1.3 Truck tippers with internal compactor (18m3) 8 Medium 1,680,000 Four phases

1.4 Truck tippers with internal compactor (15m3) 20 Medium 3,600,000 Four phases

1.5 Truck tippers with internal compactor (12m3) 20 Medium 2,400,000 Four phases

1.6 Truck tippers (3 tons) 20 Urgent 700,000 Four phases

1.7 Costal Sweeper 3 Medium 510,000 Three phases

1.8 Main street sweeper 4 Medium 400,000 Four phases

2 Al-Mansoora transfer station

2.1 Truck heads (40 tons) 4 Urgent 236,000 Negotiations with UNOPS to carry out this project

2.2 Truck trailers (40 tons) 8 Urgent 800,000

2.3 Diesel Generator (5 KW) 1 Medium 1,000

3 Bir Na'ama dumpsite

3.1 Landfill compactor 1 Urgent 350,000

3.2 Bulldozer 1 Urgent 390,000

223

3.3 Truck tippers (12 tons) 2 Medium 120,000

4 Maintenance workshops

4.1 Mobile maintenance workshops 3 Urgent 330,000

4.2 Powder fire extinguishers weight 6 Kg 15 Urgent 750

4.3 Diesel generators (50 KW) 3 Medium 30,000

4.4 Welding machines 3 Medium -

4.5 Towing truck 3 Medium 15,000

4.6 Truck washing machines 3 Medium -

4.7 Air compressor machines 3 Medium -

4.8 Lubricating machines 3 Medium -

4.9 Maintenance tool kits 6 Medium 12,000

5 Afforestation and Parks Administration

5.1 Lawn mowing vehicles 4 Low -

5.2 Tree-cutting machines 8 Low -

5.3 Moving irrigation networks with sprinklers 500 Low -

6 Sand and construction administration

6.1 Loader (CAT 910) 4 Medium 250,000 Four phases

6.2 Bobcat 8 Medium - Four phases

6.3 Truck tippers (12 tons) 4 Low -

224

Part Three: O&M Materials

No Project Description Qty Priority Cost

(USD) Notes

1 Cleaning administrations in directorates

1.1 Rough brooms 12,000 Medium 24,000

1.2 Swift Brooms 6,000 Medium 9,000

1.3 Rakes 2,400 Medium 12,000

1.4 Gypsum (50kg bags) 3,600 Low 7,200

1.5 Wheeled barrels 600 Low 42,000

1.6 Plastic trash bags (packets) 7,200 Low 252,000

1.7 Metal dustpans 5,400 Medium 21,600

1.8 Plastic barrels (1m3) 2,000 Medium 20,000

1.9 Cleaning worker's uniforms 4,500 Low 49,500

1.10 Small trash baskets 2,000 Low 16,000

2 Maintenance workshops

2.1 Spare parts to overhaul and fix vehicles - Medium -

For more details, review 3.12.2 &

3.12.3

2.2 Tires 2,672 Low 712,240

2.3 Tubes 800 Low 13,670

2.4 Batteries 940 Low 102,650

2.5 Oils and fluids 736 Low 359,470

3 Afforestation and Parks Administration

3.1 Pesticides sprayer pumps 4 Medium -

For more details, review 3.10

3.2 Fountain pumps 6 Low -

3.3 Water pumps 32 Medium -

3.4 Carry-on pesticides containers (20 L) 20 Medium -

3.5 Pesticides 600 L Medium -

225

3.6 Fertilizers 1200 kg Medium -

3.7 Seeds 1000 Packets Medium -

3.8 Operating tools (scissors, mowers, clippers, saws, etc.) - Medium -

Part Four: Requirements of Offices

No Project Description Qty Priority Cost

(USD) Notes

1 Headquarter Offices

1.1 Desktop computers (Lenovo) 8 Low 9,900

For more details, review 3.4

1.2 Printers (A1) 2 Low 1,000

1.3 Printers - colors (A3) 2 Low 6,00

1.4 Printer – colors (A4) 6 Low 1,500

1.5 Photocopiers 5 Low -

1.6 Air conditioner 1 Low 480

2 Training Center

2.1 Microphones 2 Low 100

2.2 Speakers 4 Low 1,000

2.3 Desktop computer + printer 1 Low 1,600

2.4 Data show projector 1 Low 400

2.5 LCD (42 inches) 1 Low 1,000

2.6 Labor's cost (installing and wiring audio system) - Low 100

3 Environmental Awareness Center

3.1 Digital video camera 1 Low 300

3.2 External microphone 2 Low 100

3.3 Rechargeable battery 1 Low -

3.4 Battery light kit 1 Low -

3.5 AC adapter/charger 1 Low -

226

3.6 Portable diversity tuner 1 Low -

3.7 Carrying case for camera 1 Low -

3.8 Tripod for camera 1 Low -

3.9 Digital mini cassette tape 20 Low -

3.10 UHF synthesized wireless microphone 3 Low -

3.11 Computer station with accessories 1 Low 1,300

3.12 Compact DVCAM video recorder 1 Low -

3.13 DVD recorder 1 Low -

3.14 DSR portable recorder 1 Low -

3.15 Mini DVD camcorder 1 Low -

3.16 Data show projector 1 Low 400

3.17 Laptop 1 Low 1,500

3.18 LCD (42 inches) 1 Low 1,000

3.19 Vehicle (Van) 1 Low -

3.20 Advertising screen 1 Low -

Part Five: Capacity Building

No Project Description Trainees Priority Cost

(USD) Notes

1 Financial management and improving income 10 Low -

For more details, review 3.13

2 Monitoring and evaluation 8 Low -

3 Workshops and vehicles maintenance 10 Low -

4 Environmental awareness - Low -

5 Nurseries 10 Low -

6 Irrigation systems 8 Low -

7 Art of pruning forming plant 10 Low -

8 Public gardens planning 8 Low -

9 Pest control 5 Low -

227

Part Six: Studies and Researches

No Project Description Priority Cost

(USD) Notes

1 Feasibility of investments in recycling solid wastes in Aden Medium 6,000

2 Develop a comprehensive organizational structure Low 2,000

228

Appendix 6: Required Interventions for the Infrastructure Rehabilitation and Restoration of Public Corporation of Water and Sewage Services

First: Water Supply System

Part One: Civil works on rehabilitating/reconstruction buildings and facilities

No Project Description Priority Cost

(USD) Notes

1 Wellfields

1.1 Replace the western north pipeline in Bir Nasser wellfield Urgent 381,579

1.2 Expand the administrative building in Al-Manasera wellfield Urgent 42,143.5

1.3 Expand the administrative building in Bir Ahmed wellfield Urgent 33,088.2

1.4 Expand the administrative building in Bir Nasser wellfield Urgent 33,088.2

1.5 Rehabilitate all pipelines from boreholes to reservoirs in Bir Nasser wellfield

Medium 3,097528

1.6 Rehabilitate the electrical grid in the wellfields Medium 200,000

2 Reservoirs and Tanks

2.1 Rehabilitate Fuqum mountain reservoirs No.2 (4,500 m3) Urgent 103,000

2.2 Rehabilitate Aden gate reservoir Urgent 800,000

2.3 Re-construct damaged reservoir in Hadid mountain (5,000 m3) Medium 1,500,000

2.4 Rehabilitate damaged reservoir in Al-Barzakh station (22500 m3) Medium 1,500,000

2.5 Asphalting the road toward Aden gate reservoir Medium 300,000

2.6 Paving the road toward Fuqum reservoirs and build a room for guards Medium 80,000

3 Water Supply Network

3.1

Rehabilitate worn-out parts of the water supply network (Phase I)

Urgent 3,115,843 PCWS has

detailed studies for each sub-

project

3.1.1 From Fuqum mountain reservoirs to Slaughter House P.S

3.1.2 Water supply network in Aden gate hill

3.1.3 From Government's headquarter to Imro'o Al-Qais St.

3.2 Rehabilitate worn-out parts of the water supply network (Phase II) Medium 370,000

229

3.2.1 Al-memdara – Insha'at neighborhood

3.2.2 Al-Basateen neighborhood

3.2.3 Bir Fadhl neighborhood

3.2.4 Al-Rasheed neighborhood

3.2.5 Al-Bomess neighborhood

3.2.6 Al-Hiswa neighborhood

3.2.7 Code Al-Namer neighborhood

3.3

Rehabilitate worn-out parts of the water supply network (Phase III)

Low 13,000,000

3.3.1 Bir Ahmed neighborhood

3.3.2 Al-Qahera neighborhood

3.3.3 From Al-Tahlia station to Caltex

3.3.4 From Bir Ahmed wellfield to Al-Tahlia station

3.3.5 Al-Daka neighborhood in Al-Mu'alla

3.3.6 From police station to airport – Khormaksar

3.3.7 The Main pipelines in Al-Tawahi

4 Pumping Station

4.1 Renovate lightening systems in all pumping stations Urgent 15,000

4.2 Paving the road toward Al-Barzakh pumping station Medium 150,000

5 Costumer Centers and Offices in Directories

5.1 Construct 3 hangars in Al-Sheikh Othman facility (Al-Bouring) Medium 200,000 Three Phases

5.2 Paving paths in Al-Sheikh Othman facility (Al-Bouring) Medium 150,000

5.3 Rehabilitate and furnishing costumer centers in Al-Mansoora and Khormaksar

Medium 200,000

230

Part Two: Vehicles, machines and tools

No Project Description Qty Priority Cost

(USD) Notes

1 Wellfields

1.1 Supply and install submersible pumps with motors 40 Urgent 1,000,000 Four phases

1.2 Supply step-down transformers (100KVA) 15 Low 75,000

1.3 Supply and install boreholes monitoring system 1 Low 315,000 To monitor wells yield

1.4 Supply and install power monitoring system 1 Low 108,000 To monitor electrical power consumption for each well

1.5 Supply and install new maintenance workshop 1 Medium 120,000 To fix defective pumps

2 Water Supply Network

2.1 Supply and install Main water meters 3 Medium 45,000

2.2 Supply demotic water meters (1/2 inches – class A) 8 Medium 4,750,000

3 Maintenance Workshops

3.1 Truck crane (5 tons) 2 Urgent 220,000 Two phases

3.2 Truck tippers (4 m3) 6 Medium 102,000

3.3 Small cars 10 Low 170,000

3.4 Portable generators 20 Low 900,000

231

Part Three: O&M Materials

No Project Description Qty Priority Cost

(USD) Notes

1 Wellfields

1.1 UPVC rising pipelines (5 inches) - Medium 116,200

1.2 UPVC rising pipelines (4 inches) - Medium 101,000

1.3 Aluminum cables (120 mm) 15 Km Low 37,500

1.4 Copper cables (50 mm) - Low 108,000

1.5 Clips (4inches diameter and 18inches length) 12 Medium 9,000 To connect the new wells

1.6 Galvanized pipes (4inches diameter and 3meters length)

60 Medium 2,400 For installing well pumps

1.7 Galvanized pipes (3/2inches diameter and 3meters length)

240 Medium 6,000 For maintenance works (cleaning of wells)

1.8 Galvanized iron nipples (4 inches) 20 Medium 400

1.9 Over-headed HV lines clips (120 mm) 60 Medium 300

1.10 Galvanized iron flanges (4 inches) 40 Medium 400

1.11 Weather resistance tapes 240 m Medium 6,000

1.12 Hot sticks to connect over-headed HV lines (120mm)

60 Medium 1,200

1.13 Hot sticks (9 meters) to replace HV fuses 4 Medium 1,000

1.14 High quality aluminum ladders 8 Medium 3,200

1.15 HV fuse holder (11KV) with 5Amps fuses 300 Medium 18,000 For wellfields electricity

1.16 Water pressure gauges (from 0 – 5 bars) ½ inches diameter

50 Medium 2,500

1.17 Insulated cables (2.5 mm) 2.5 Km Medium 20,000 To operate gauges of collective wellfields

1.18 Lifting pulleys 12 Medium 420 To lift pumps in the wells

232

1.19 Power supply (1A – 3.6 V) 60 Medium 1,800 To operate out of service gauges of the wellfields

1.20 Cater Pillar control panel pearls (EMCP 4.4 Generator set control – Type: Cater Pillar)

2 Medium 3,600 To operate generators in Al-Manasera wellfield

1.21 Radiator (Perkins) 1 Medium 25,000 For generators

1.22 MP 204 Starter 20 Medium 26,000 Soft-starter for pumps

2 Water Supply Network

2.1 Pressure gauges with data logger 8 Urgent 2,800

2.2 Pipe locater 2 Urgent 3,000

2.3 Acoustic leak sounding system 2 Urgent 1,200

2.4 Portable ultrasonic flow meter 2 Urgent 600

2.5 Valve Cap Locator 2 Urgent 1,196

2.6 Detecting leaks device 3 Urgent 3,300

3 Pumping Station

3.1 Magnetic contactor 1 Urgent 2,000

3.2 4 cores cables (20m) 500 Urgent 8,500

3.3 Manual changeover switches 200 A 10 Urgent 2,000

3.4 Manual changeover switches 100 A 10 Urgent 1,400

3.5 Hydrostatic level sensor (0-20mA) with cable (10m) 40 Urgent 24,000

3.6 Timer on delay 220V AC 50 Urgent 2,000

3.7 Thermal-magnetic motor circuit breakers 50 Urgent 10,000

4 Operation Tools and Equipment

4.1 Manual pipes cutting machine operated by petrol 6 Medium 12,000

4.2 Asphalt cutting machine 4 Medium 8,400

4.3 Cement crushing hammer 4 Medium 8,000

4.4 Manual electric drill (Hilti) for walls – 13mm bit 7 Medium 21,000

4.5 Manual electric drill (Hilti) for steel – 13mm bit 7 Medium 1,260

4.6 Complete Mechanical tool box (large) 7 Medium 9,450

233

4.7 Complete Electrical tool box (large) 7 Medium 4,200

4.8 Iron hammers (5 pounds) 60 Medium 1,800

4.9 Iron hammers (1 Kg) 60 Medium 1,500

4.10 Iron hammers (500 g) 100 Medium 2,000

4.11 Shovels and the wooden stick 600 Medium 6,000

4.12 Shovel-Axe combo with the stick 600 Medium 6,000

4.13 Pipe wrench (8 inches) 300 Medium 4,500

4.14 Pipe wrench (10 inches) 300 Medium 5,400

4.15 Pipe wrench (12 inches) 300 Medium 6,000

4.16 Pipe wrench (18 inches) 300 Medium 7,500

4.17 Pipe wrench (24 inches) 300 Medium 9,000

4.18 Pipe wrench (32 inches) 70 Medium 3,850

4.19 Iron saw 400 Medium 2,800

4.20 Iron chainsaw wrench 1 Medium 1,000

4.21 Block chain (3 tons) 8 Medium 1,200

4.22 Boxes for tools keeping 90 Medium 2,070

5 Stationary and portable communication devices

5.1 Portable handy VHF/UHF FM Radio 10 Low 1,880

5.2 VHF/UHF FM Radio for cars 15 Low 8,625

5.3 Stationary VHF/UHF FM Radio 20 Low 14,960

6 Disinfection Units

6.1

V notch chlorine injection system to inject chlorine gas to potable water (human use), max. Dose 500 grams per hour. Horizontal pumps to inject chlorine solution to network, 100 m head, 10 m³/h operate by 3 - phase, 415 volts, 50 Hz, power supply with all protection system needs (2) inch pump outlet. pump body stainless steel. All technical documents, operation manual & spare part list must include.

3 Urgent - Mercy Corps will implement this project

234

6.2 Replace the current pipelines, since these pipelines are not suitable

3 Urgent -

6.3 Alarming device 3 Urgent -

6.4 Fans for sucking gases 3 Urgent -

7 Central Laboratory

7.1 DMA-80 Direct Mercury Analyzer Wide Range (DMA8242)

1 Urgent 26,850

Mercy Corps will implement this project

7.2

DMA-80 Wide Range with Large terminal 1660 spare parts

7.2.1 Quartz Catalyst tube complete 1 Urgent 263.22

7.2.2 Tube with amalgamator for Dma-80 wide

range Quartz, φ 9/7*52ml

1 Urgent 436.58

7.2.3 Sample metal boats (set of 40 pieces) 1 Urgent 86.18

7.2.4 Quartz sample boats for DMA-80, set of 10 pcs - 1.5 ml

1 Medium 311.2

7.2.5 Hg Tran 1 Medium 183.44

7.2.6 DMA-80 air compressor 1 Medium 1962.75

7.2.7 Sample additive "A" (bottle of 200 gram) 1 Medium 54.22

7.2.8 Sample additive "B" (bottle of 200 gram) 1 Medium 34.59

7.2.9 Double sorbent trap (silicon joints and container included)

1 Medium 71.37

235

Second: Sanitation System

Part One: Civil works on rehabilitating/reconstruction buildings and facilities

No Project Description Priority Cost

(USD) Notes

1 Buildings and administration offices

1.1 Expand the headquarter building Urgent 34,968.2

1.2 Construct new administrative building in Al-Boraiqa Urgent 28,531

2 Sewerage Pumping Stations

2.1 Rehabilitate Al-Mansoora main P.S. Urgent 250,000

2.2 Rehabilitate Abbas P.S. Medium 200,000

2.3 Rehabilitate Al-Kahraba area (Hadjiv) P.S. in Al-Mu'alla Medium 100,000

2.4 Rehabilitate Al-Fateh P.S in Al-Tawahi Medium 50,000

2.5 Build a fence and replace the main gate for Crater main P.S. Low -

2.6 Build a fence with gates for L P.S in Khormaksar Low -

2.7 Rehabilitate the buildings of old pumping stations in Khormaksar (M, Al-Salam6, Al-Salam7, October, Soqatra, L, Badr, Jamal)

Low -

2.8 Rehabilitate the tanks in Badr P.S. Low -

3 Sewerage Network

3.1 Rehabilitate main force lines in district one (Khormaksar, Crater, Al-Mu'alla, Al-Tawahi)

20,469,060

3.2 Rehabilitate lateral force lines in Khormaksar (4Km) 1,030,000

3.3 Construct a sewage network in the region of Bair Ahmed, which is 10,452 longitudinal meters in length (Al-Boraiqa)

5,301,644

3.4 Constructing a new sewage network in the Gold Moore region, which is 4km in length with building two small pumping stations

1,161,562

3.5 Construct a substitute force line, using PE pipes in Al-Mansoora (4.1Km) 1,682,040

3.6 Construct a new sewage network, Al-Khaisa (1) in Al-Boraiqa (2.85Km) 686,861

3.7 Construct a new sewage network, Al-Khaisa (2) in Al-Boraiqa (506 m) 134,365

3.8 Construct a sewage network in Al-Mhram region - Al-Sha'b City (3.4Km) 546,375

236

3.9 Construction of a sewage network for blocks 5,6,7,8 in Al-Mimdara (3Km) 1,355,463 Four Phases

3.10 Rehabilitate a sewage network from the Airport intersection, Khormaksar to Alma'asheq (1.1Km)

3,009,050

3.11 construct a sewage network for the Dar Sa'd region. (1.5Km) 173,034 Four Phases

3.12 Replace a pumping line from Al-Shorta's pump station to Code Al-Namer's pump station.

201,137

4 Wastewater Treatment Plant (WWTP)

4.1 Cleaning treatment basins 5,000

4.2 Construct new building and laboratory for Al-Areesh WWTP 1,460,895

4.3 Rehabilitate Kubota WWTP 610,689

4.4 Rehabilitate Salah Aldien WWTP 18,950

5 Rehabilitate and furnishing offices in headquarter building

5.1 Deputy of general manager office - For more details, review 4.1

5.2 Secretary office -

5.3 Technical studies and documentation administration (Two offices) -

5.4 Administrative buildings in directorates Urgent 37,104

237

Part Two: Vehicles, machines and tools

No Project Description Qty Priority Cost

(USD) Notes

1 Sewerage Network

1.1 Drain rods used for clearing clogged manholes 5,000 Urgent 40,000

1.2 Iron covers (heavy, medium) for manholes 7,000 Low 1,915,000

1.3 Steps to be used for going up/down manholes 2,000 Low 20,000

1.4 Long excavators – 3 meters 3 Medium 900,000 Three Phases

1.5 Long excavators – 6 meters 3 Medium 1,800,000

1.6 Small loaders 3 Low 810,000

1.7 Large loaders 3 Low 1,080,000

1.8 Tippers 16 Low 5,000,000

1.9 Vacuum sewage suction trucks with the following description: Vacuum Sewage Suction Trucks 12,000 Lit. with accessories and spare part

4 Medium 5,000,000

1.10 Mobile pump units 4 Urgent 800,000 Four Phases

2 Sewerage Pumping station

2.1 Centrifugal pumps for old stations in Khormaksar (Pump: October, Omar Al-Mukhtar, Soqatra, Al-Salam 7, Jamal)

12 Medium 677,000

2.2 Submersible pumps of various capacities 64 Low 640,000

2.3 Various sewage pump stations along with control panels

70 Low 16,800,000

2.4 Multi-purpose generators 20 Low 3,200,000

3 Wastewater Treatment Plants (WWTP)

3.1 Laboratory equipment for the three WWTPs 3 Medium -

238

Part Three: O&M Materials

No Project Description Qty Priority Cost

(USD) Notes

1 Sewerage Network

1.1 pipes of various diameters (160, 200, 250, 300) mm 20 Km Medium 312,750

1.2 Spare parts (various pulleys, bumpers, elbows) made from cast iron

- Low 1,500,000

2 Sewerage Pumping Station

2.1 Mechanical spare parts and valves for pumps Low 64,510

3 Maintenance Workshops

3.1 Mechanic and pneumatic equipment and tools Urgent 31,606 For more details, review 9-Maintenance Workshops

3.2 Tires of different sizes 3,500 Low - For more details, review 4.3

3.3 Batteries 113 Low -

3.4 Oils and fluids (barrels) 172 Low -

3.5 Filters 223 Low -

3.6 Hilux98 single cabinet, Diesel Engine (spare parts): - Engine with all accessories - Front glass - Radiator tank

Urgent 1,896

3.7 Isuzo2004 single cabinet, Diesel (spare parts): - Engine with all accessories - Radiator tank - 70Ah battery - Tires (195 X 14)

- Urgent 1,464

3.8 Shemco motorbike, 3 tires (spare parts): - Motorbike engine 200 CC - Gearbox - Gearbox shaft

- Urgent 444

239

- Brake discs - Tires (155 X 12)

3.9 Suzuki carry 99 (spare parts): - Engine with all accessories - Radiator tank - Tires (165 X 13)

- Urgent 920

4 Occupational and Safety Management

4.1 Spare parts for safety equipment - Urgent 36,000

4.2 General safety equipment and tools - Urgent 100,825

Part Four: Capacity Building

No Project Description Trainees Priority Cost

(USD) Notes

1 Fundamental courses for sanitary workers 50 Low -

2 Courses on controlling electricity in sanitary pumps 10 Low -

3 Courses on controlling electrical panels especially (Soft Starter)

6 Low -

4 Courses on maintenance of perpendicular and submersible pumps

6 Low -

5 Courses on maintenance of mechanical spare parts 4 Low -

6 Courses on electrical wiring - single and three phase 4 Low -

7 Fundamental courses for Sanitary Engineers 20 Low -

8 Courses on Hydraulics (pumps, networks and basins) 30 Low -

9 GIS course for Sanitary Engineers 8 Low -

10 AutoCAD (latest version) course - M&E designs 8 Low -

11 Basic computers skills (Excel, Word) courses 20 Low -

240

Appendix 7: Drawings and Designs for Administration Buildings in the Wellfields, Headquarter and Administration in Al-Boraiqa

PLAN

241

LAYOUT DETAILS

242

SIDE VIEW

243

A-A Section

244

REAR VIEW WITHOUT DOORS

245

REAR VIEW WITH DOORS

246

Appendix 8: Questionnaires and Surveys

Cleaning Fund - Aden

Infrastructure Assessment – Assets, Equipment and Needs

Names of directorates where waste is collected:

Al-Mu'alla Al-Tawahi Al-Boraiqa Crater

Al-Sheikh Othman Dar Sa'd Al-Mansoora Khormaksar

1.

Total population in the targeted areas.

…………………………….

2.

Are there waste collecting containers?

Yes No

3.

Which way is used to collect waste?

Waste Piles Waste Baskets Other

No 4.

How many containers are there in each governorate?

Al-Mu'alla………… Al-Tawahi………… Al-Boraiqa……. Crater………

Al-Sheikh Othman… Dar Sa'd…….. Al-Mansoora…..… Khormaksar……..

Yes 5.

Type of container used to collect waste

6.

Size of container used to collect waste

7.

Is the number of containers enough?

Number of containers is enough There is a shortage by……………

8.

Other

Notes

Do vehicles

get periodic

maintenance?

Shortage

(number)

Condition Capacity No. Waste collecting vehicles 9.

Ordinary vehicles

Vehicles with compressor

Longest path for waste collecting vehicles

10.

Is there a chart of the route for the waste collecting vehicles?

Yes (copies of the chart have been obtained) No

11.

Is there a feasibility problem with providing fuel for the waste collecting vehicles?

Yes No

12.

How severe is the feasibility problem?

Constant Rare

Yes 13.

Number of times waste is collected throughout the day.

…………………………….

14.

Manner of emptying the waste from containers into waste collecting vehicles

Manual Mechanical

15.

Workers (waste collecting workers on the streets) 16.

Daily rate Level of efficiency No. of workers

247

Tools and equipment used by workers

Shovels Brooms Wheeled containers Others……….

17.

Current condition of the tools

18.

Is there a shortage in tools used by workers?

Shovels…………….. Brooms…………. Wheeled containers………… Others ……………

19.

Amount of waste produced daily

…………………….. ton/day ……………………CM/day

20.

Amount of waste collected daily

…………………….. ton/day ……………………CM/day

21.

Components of waste

Organic substances………….% Plastic……………% Glass……………%

Metal…………………………% Paper……………% Others………….%

22.

Does any of the waste get recycled?

Yes No

23.

Description

of the

recycling

procedure

Metal

Recycling

Yes

Plastic

Recycling

Glass

Recycling

Paper

Recycling

Organic

Material

Recycling

Is the location of the dump suitable?

Yes. For the following reasons

No. For the following reasons

24.

What are the current in-service equipment? 25.

Shortage (Number) Number Current Condition Equipment

248

Is there a fence surrounding the dump area?

Yes No

26.

Does the dump contaminate any of the following?

Air

Surface Water

Ground Water

27.

How far is the nearest ground water well used for drinking?

………………. Meters.

28.

Does the water from the wells closer to the dump get tested?

Yes No

29.

Does the surface water closer to the dump run away from the dump?

Yes No

30.

How far is the nearest residential compound from the dump?

………………meters.

31.

Are there any complaints from the residents in the compounds near the dump?

Yes No

32.

Health problems Traffic obstruction Annoying smells

Noise Air Pollution Spreading of insects and dogs

Others

Yes

Are there special facilities for dangerous waste and/or medical waste?

Yes No

33.

Describe these facilities

Yes 34.

How is the leachate collected?

35.

Thickness of waste layers

Before compaction…………….. After compaction …………………………

36.

Equipment used for compaction

37.

Condition of the equipment used for compaction

38.

Density of waste after compaction

39.

Thickness of soil layers used for covering waste

40.

Type of soil used for covering waste

41.

Is the soil used for covering waste extracted from the same site of the dump?

Yes No

42.

249

How far the site where the soil used for covering waste from the dump is?

No 43.

How many daily workers are there working at the dump?

44.

What is the daily rate for each worker? And do they get paid in a systematic way?

45.

Are there any formerly conducted studies to assess the current condition of the management of solid

waste in Aden?

Yes No

46.

Are there any formerly conducted studies to find out the specification of solid waste such as:

-Volumetric or weight ratios of the different components of waste. Yes No

- Physical properties of waste such as density and moisture content. Yes No

- Chemical properties of waste such as chemical content and energy content. Yes No

47.

250

Public Corporation of Water and Sewage - Aden

Assessment of infrastructure – Assets, Equipment and Needs

Buildings and facilities of PCSW

1. PCSW's Headquarters

Define the current condition of the headquarters.

What are PCSW's headquarters essential needs?

Department No. of male

employees

No. of

female

employees

Assets and

equipment Needs NO

1

2

3

4

5

6

7

8

2. Training Center

Define the current condition of the building specified for training center.

251

Is there a necessity to do rehabilitation work for the training center?

Yes No

What maintenance and rehabilitation works are necessary for the training center?

If

Yes

Is the center equipped with all the necessary tools and equipment?

Yes No

What are the necessary tools and equipment for the center?

If

No

Water

3. Maintenance Workshop

What is the current condition of the building specified for the maintenance workshop?

Is there a necessity to do rehabilitation work for the maintenance workshop?

Yes No

What maintenance and rehabilitation works are necessary for the maintenance

workshop?

If

Yes

Is the maintenance workshop equipped with all the necessary tools and equipment?

Yes No

What are the necessary tools and equipment for the maintenance workshop?

If

No

What is the number of the maintenance team members?

Describe the level of efficiency and skill of the maintenance team.

252

Does the team require any training courses to improve their skill level?

What essential needs are required to carry out the training courses?

4. Laboratory

Define the current condition of the building specified for the PCWS's laboratory.

Is there a necessity to do rehabilitation work for the laboratory?

Yes No

What maintenance and rehabilitation works are necessary for the laboratory?

If

Yes

Is the laboratory equipped with all the necessary tools and equipment?

Yes No

What are the necessary tools and equipment for the laboratory?

If

No

5. Main tanks and towers

Define the current condition of main tanks.

Notes Needs Tank's

Condition Tank's

Capacity Tank's

Type Tank's

Location No

1

253

2

3

4

How many towers are specified for water?

……………………………….. tower.

Define the current condition of towers.

Notes Needs Tower's

Condition

Tower's

Capacity

Tower's

Type

Tower's

Location NO

1

2

3

4

5

Are chlorine tablets being added to the water to fight Cholera?

Yes No

How much Chlorine is added to the water?

………………tablet for each ……………….. liter

If Yes

6. Wells

How many wells are there?

…………………….. wells. Define the current condition of the wells.

254

Notes Needs Well's

condition

Serviceability's

age Production

Rate (L/day)

Well's

Location NO

1

2

3

4

5

7. Water Network

Are there any damaged parts in the network?

Yes No

What parts of the network are damaged? If

Yes

Length of

pipes

requiring

replacement

Length of

pipes requiring

maintenance Pipes Diameter Pipes Type

Pipes

Age

Damaged

Parts No

1

2

3

4

255

5

Does the water network reach all regions in Aden?

Yes No

Name the region which the network does not reach.

1……………………… 2………………

3……………………… 4……………

5…………………… 6…………………

7………………… 8…………………

If

No

8. Pumping Stations

Define the current condition of the pumping stations.

Notes Intervention Pump's

Condition Pump's

Capacity Pump's

Location NO

Maintenance Replacement

1

2

3

4

5

6

7

8

256

9. Electricity Generators

Shortage

(Number)

No. of gen.

requiring

replacement

No. of gen.

requiring

maintenance

No. of gen.

in good

condition

Power

(kw)

No. of

Generators NO

1

2

3

4

5

6

7

8

9

10

Is there a difficulty in providing the fuel for the generators?

Yes No

How severe is it?

Constant Rare

If

Yes

10. Pumping rates and beneficiaries

What is the daily flow rate in the network?

…………………………………. Cubic meters per day.

Total number of beneficiaries in all regions.

…………………………….

11. Safety Procedures

Does PCWS own safety tools and equipment? Is it enough?

Yes No

257

What are the missing needs? If No

Need Number Need Number

Are workers committed to safety precautions and/or wearing safety gear?

Yes No

Are workers fully aware of the importance of committing to safety precautions and wearing

safety gear?

Yes No

Do workers receive courses regarding the importance of safety precautions and how to

implement them?

Yes No

What are the necessary needs for providing the workers with courses

regarding the importance of safety precautions?

If No

12. Former Studies

Are there any formerly conducted studies to assess the current condition of the water

network in Aden?

Yes (copies have been received) No

13. Urgent Needs

What are the needs that are necessary and most prioritized from the PCWS's senior,

engineers and technicians?

258

Sanitation

14. Maintenance Workshop

What is the current condition of the building specified for the maintenance workshop of the

sanitation?

Is there a necessity to do rehabilitation work for the maintenance workshop?

Yes No

What maintenance and rehabilitation works are necessary for the

maintenance workshop?

If Yes

Is the maintenance workshop equipped with all the necessary tools?

Yes No

What are the necessary tools and equipment for the maintenance workshop?

If No

What is the number of the maintenance team members?

Describe the level of efficiency and skill of the maintenance team.

Does the team require any training courses to improve their skill level?

What essential needs required to carry out the training courses?

259

15. Laboratories

Define the current condition of the building specified for the sanitation's laboratory.

Is there a necessity to do rehabilitation work for the laboratory?

Yes No

What maintenance and rehabilitation works are necessary for the laboratory?

If

Yes

Is the laboratory equipped with all the necessary tools?

Yes No

What are the necessary tools and equipment for the laboratory?

16. Sewage's Network

Are there any damaged parts in the network?

Yes No

What parts of the network are damaged? If

Yes

Length of

pipes

requiring

replacement

Length of

pipes requiring

maintenance

Pipes Diameter Pipes Type Pipes

Age

Damaged

Parts No

1

2

3

260

4

5

Does the sewage network reach all regions in Aden?

Yes No

Name the region which the network does not reach.

1……………………… 2………………

3……………………… 4……………

5…………………… 6…………………

7………………… 8…………………

If

No

Are there any damaged manholes in the network?

No Yes

No. of

manholes

requiring

replacement

No. of

manholes

requiring

maintenance

Age of

damaged

manholes

No. of

damaged

manholes

Location Yes NO

1

2

3

4

5

6

7

Is there a leakage caused by damages in the sewage network?

Yes No

How does this leakage affect the general health?

If Yes

What diseases could spread and harm citizen because of this leakage?

261

What is the environmental effect of this leakage?

Does it reach or affect the water network?

Yes No

Describe its impact on the water network. If

Yes

Does PCWS own suction vehicles to treat sanitary networks manholes from when

clogged?

Yes No

Describe the current condition of the vehicle.

If

Yes

Does the vehicle get maintenance work?

Yes No

Does it work efficiently?

Yes No

How can better efficiency be accomplished? If No

17. Pumping Stations

Define the current condition of the pumping stations.

Notes Intervention Pump's

Condition

Pump's

Capacity

Pump's

Location NO

Maintenance Replacement

1

2

3

4

262

5

6

7

8

9

10

18. Electricity Generators

Shortage

(Number)

No. of gen.

requiring

replacement

No. of gen.

requiring

maintenance

No. of

gen. in

good

condition

Power

(kw)

No. of

Generators NO

1

2

3

4

5

6

7

8

9

Is there a difficulty in providing the fuel for the generators?

Yes No

How severe is it?

Constant Rare

If

Yes

19. Sewage Water Treatment Plants

Define the current condition of the treatment plants.

263

Plant's Location Plant's Type Plant's Age Plant's Capacity

(CM/day)

Location of the final dump? Last use of the treated water from the plant?

Is there a necessity for maintenance work or replacement to some parts of the plants?

Yes No

What are the essential needs for the treatment plant? What needs does the plant's

laboratory require?

If

Yes

Laboratories Needs Plant's Needs Treatment Plant's

Location NO

1

2

3

Are there lab results for the incoming and outgoing water from the plant?

Yes (This month's results were taken) No

How much do the samples of this month contain the following?

Treatment

Plant's

Location

(TSS )

(mg/L)

(BOD)

(mg/L)

(FC )

(CFU/mL)

Incoming Outgoing Incoming Outgoing Incoming Outgoing

264

20. Safety Procedures

Does PCWS own safety tools and equipment? Is it enough?

Yes No

What are the missing needs? If No

Need Number Need Number

Are workers committed to safety precautions and/or wearing safety gear?

Yes No

Are workers fully aware of the importance of committing to safety precautions and wearing

safety gear?

Yes No

Do workers receive courses regarding the importance of safety precautions and how to

implement them?

Yes No

What are the necessary needs for providing the workers with courses

regarding the importance of safety precautions?

If No

Do maintenance workers receive enough information regarding the dangers of Sulphur

Hydrogen gas when opening manholes? Especially since there have been a number of death

occurrences in Aden because of this gas?

Yes No

21. Former Studies

Are there any formerly conducted studies to assess the current condition of the sewage

network in Aden?

Yes (copies have been received) No

265

22. Urgent Needs

What are the needs that are necessary and most prioritized from the PCWS's senior,

engineers and technicians?