INDO ENERGY INTERNATIONAL LTD.

465
INDO ENERGY INTERNATIONAL LTD. 10 th May, 2021 Ministry of Environment, Forest and Climate Change Indira Paryavaran Bhavan, Jor Bagh Aliganj, New Delhi – 110 003 [F.No.10-34/2015-IA.III], IA/MH.MIS/335872015 Subject: Development of Deep Water Jetty Facility and Capacity expansion at existing Inland Water Jetty Facility on Kandalika river, Village Korlai, District Raigad, Maharashtra - submissions in response to additional information requisitioned, 49 th EAC meeting, EAC Infra – 2, 25 th February, 2020 Dear Sir With reference to the above mentioned Minutes of the EAC Meeting, we are furnishing herewith additional information as sought. We are sorry for the delay in submission of reply which was partly due to delay in obtainment of requisite clarifications and NOC/clarification from the respective offices due to lockdown for Covid19 pandemic for perusal and record of your good office. The compliance of the recommendations are hereby attached as per the below table of contents. We humbly request the esteemed Ministry for condoning the delay in submission of the documents, and to re- consider our case for hearing before the EAC, and oblige. Thanking you Yours faithfully Capt. RK Karnal Director Indo Energy International Ltd.

Transcript of INDO ENERGY INTERNATIONAL LTD.

INDO ENERGY INTERNATIONAL LTD.

10th May, 2021

Ministry of Environment, Forest and Climate Change Indira Paryavaran Bhavan, Jor Bagh Aliganj, New Delhi – 110 003

[F.No.10-34/2015-IA.III], IA/MH.MIS/335872015

Subject: Development of Deep Water Jetty Facility and Capacity expansion at existing Inland Water

Jetty Facility on Kandalika river, Village Korlai, District Raigad, Maharashtra - submissions in response to additional information requisitioned, 49th EAC meeting, EAC Infra – 2, 25th February, 2020

Dear Sir With reference to the above mentioned Minutes of the EAC Meeting, we are furnishing herewith additional information as sought. We are sorry for the delay in submission of reply which was partly due to delay in obtainment of requisite clarifications and NOC/clarification from the respective offices due to lockdown for Covid19 pandemic for perusal and record of your good office. The compliance of the recommendations are hereby attached as per the below table of contents. We humbly request the esteemed Ministry for condoning the delay in submission of the documents, and to re-consider our case for hearing before the EAC, and oblige. Thanking you Yours faithfully

Capt. RK Karnal Director Indo Energy International Ltd.

Table of Contents

Sr.No Details sought Compliance

i. Upload copy of updated EIA/EMP Report along with point-wise ToR Compliance and Annexures.

Page No: 3 to 409

ii. Upload copy of CZMA recommendations given by Maharashtra CZMA

Page No: 411 to 418

iii. Certificate from Chief Wild Life Warden regarding permissibility and distance of the project from Phansad Wildlife Sanctuary.

Page No: 419 to 420

iv. Certificate from Archaeological Survey of India regarding permissibility and distance of the project from Korlai Fort.

Page No: 421 to 422

v. Impacts of the proposed project on crocodiles present in the upstream of the Kundalika estuary

Page No: 423 to 426

vi. A study on impacts of accidental spillage due to ship grounding or collision through model and its mitigation.

Page No: 427 to 453

vii. Point-wise details of each of the issues raised during public hearing and commitments made by the project proponent with EMP.

Page No: 454 to 460

viii. Details of EIA Consultant along with Accreditation Certificate

NABET Certificate: Page No: 6 Consultant details:Page No:246-247

ix. Plan for Corporate Environment Responsibility (CER) as specified under Ministry’s Office Memorandum issued vide letter F.No. 22-65/2017-IA.III dated 01.05.2018.

Page No: 462 to 465

ENVIRONMENTAL IMPACT ASSESSMENT REPORT

PROJECT

DEVELOPMENT OF “DEEP WATER JETTY” FACILITY ON KUNDALIKA RIVER, VILLAGE-

KORLAI, DITRICT-RAIGAD, MAHARASHTRA & CAPACITY EXPANSION OF EXISTING

INLAND WATER JETTY FACILITY, ON KUNDALIKA RIVER, VILLAGE-SANEGAON,

DISTRICT-RAIGAD, MAHARASHTRA

PROJECT PROPONENT

INDO ENERGY INTERNATIONAL PVT. LTD.

Submitted by

IETINDO ENERGY INTERNATIONAL LTD.

UNDERTAKING BY THE PROJECT PROPONENT

This is to certify that:

I, N'lr. Deepak Kumar Sai8al IDirector') ol Indo Enc] g,v Interlrationnl Ltd. 0EILI do herebj,solemnly state about EIA report to develop "Dcep Watcr Jett-v f:lcility on Kundalika

River, village 1(orlai and capacity expansion at existing Inland Water Jetty l.acilit,,, on

Kunclalika River at village Sanegaon, districl Raigad, Nl.harashtra" as follours:

. No nodcrnization activity has been undertaken in violation ol the provision olEIA notificalion.

. I hereby undeft.ke thnt the data and lnlbrnation givcn in thc application,enclosure and olher documents ale true to tlrc best of my knorvlerlge ancl belieland I arn a$/are that ifeny part ofthe data and infol-mation subnlitled is Found to

be false and misleading at any stage, the proj-.ct will be relected and clearancegiven, if anv to the Project will be revoked at our own risk ancl cost.

. I hereby subnlit this underlaking as part of the EIA report, orr/ing the content

[inlorDraLion and dala] olthe EIA Reltort.

. There is no lltigation pcnding against the projecl and/or land in ll,hich theploject is ploposcd to be set up and that for alrv suclt litigation \,vhatsoever thesole responsibilily r'!,ill bc borne by the "Project Proponent".

For Indo IFlernational Ltd. (tElL),

Deepal( I(un_i

Director

Place: X'lumbaiDare 21l04/2021

6x"r1*:..r\!( rer ;5(\#v

TERRACON ECOTECH PVT.LTD. 202, Kingston, Tejpal Road, Vile Parle (East), Mumbai-400057. INDIA Tel: 91.22.20863940/41/42

CIN: U74140MH2008PTC188663; GST no. 27AADCT0972A1ZN Email: [email protected]. Website : www.terraconindia.com

UNDERTAKING BY EIA CONSULTING ORGANIZATION

This is to certify that: -

I, Pravin Shinde, Environmental Coordinator for submission of the project report for obtaining Environmental & CRZ Clearance to develop “Deep Water Jetty facility on Kundalika River, village Korlai and capacity expansion at existing Inland Water Jetty Facility, on Kundalika River at village Sanegaon, district Raigad, Maharashtra” coordinated by Deepak Kumar Saigal (Director).

The information contained in this report is based on the scientific analysis of data, information and drawings provided by Project Proponent (IEIL) and from authentic sources and nodal agencies during the time of the study.

No any violation of provisions of EIA Notification Date: 14.09.2006, and amendments made thereafter, circulars and OM issued their under.

Date: 08.05.2021 Name & Sign: Dr. Pravin Shinde

Place: Mumbai Designation: Asst. General Manager (Environmental Coordinator)

Declaration by Experts contributing to the EIA

I hereby certify that I was part of the EIA team in the following capacity that developed this

EIA report to develop “Deep Water Jetty facility on Kundalika River, village Korlai and

capacity expansion at existing Inland Water Jetty Facility, on Kundalika River at village

Sanegaon, district Raigad, Maharashtra”.

EIA Coordinator: Dr. Pravin Shinde

Signature & Date:

Period of involvement: May 2021 till final clearance

S. No. Name of Expert Functional

Area Period of involvement Signature

Functional Area Experts (FAE)

1. Pravin Shinde EB April 2021 to

final clearance

2. Rupa Shah SHW April 2021

3. Smita Patil WP & SC April 2021 to

final clearance

4. Prasanta Das SE April 2021

5. Ravindra Kode RH April 2021

6. Manish Sharma GEO & HG April 2021

7. Neha Sharma AP April 2021

Functional Area Associates (FAA)

8. Abhijeet Jagtap EB April 2021

Mentor

9. Monowar Khalid EB April 2021

Team Members

10. Akshay Nachane April 2021

11. Shrutika Pandit April 2021 to

final clearance

S. No. Name of Expert Functional

Area Period of involvement Signature

12. Ashok Yashwant April 2021 to

final clearance

Declaration by the Head of the Accredited Consultant Organization/authorized person

I Ashok Jain, hereby confirm that the above-mentioned experts prepared the EIA Report to

develop “Deep Water Jetty facility on Kundalika River, village Korlai and capacity expansion

at existing Inland Water Jetty Facility, on Kundalika River at village Sanegaon, district

Raigad, Maharashtra”. I also confirm that the consultant organization shall be fully

accountable for any miss-leading information mentioned in this report.

Signature with date:

8th May2021

Name: Mr. Ashok Jain

Name of the EIA Consultant Organization: Terracon Ecotech Pvt. Ltd.

NABET Certificate No: NABET/EIA/1922/RA 0147 valid till Jan 20, 2022.

EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy International Ltd. 

 

TEPL/ENV/CBS/2021‐05  I  

ExecutiveSummary

    

EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy International Ltd. 

 

TEPL/ENV/CBS/2021‐05  II  

EXECUTIVE SUMMARY 

INTRODUCTION 

Indo  Energy  International  Limited  (IEIL)  is  a  company  in  the  sector  of  Infrastructure Development and Power. Set up in 1999, it is promoted by Esquire Shipping Pvt. Ltd. To cargo by sea, train or road, and also clearance, cargo handling, warehousing and distribution. Some of the services are chartering and brokerage, ship agency management, shipping consulting and multi modal transport.  IEIL  has  an  operational  multipurpose  jetty  at  Sanegaon  since  2009.  The  jetty  has  been approved by Customs, through their notification dated 2 Feb 2010, for unloading of imported goods  namely  Iron,  Iron  ore  pellets,  Iron  ore  concentrate,  Coal,  Dolomite/Limestone, Petroleum Gas, Steel melting scrap, HDI chips/fines, Pulp, Magnesite, Sulphur. The jetty has also been approved by customs for loading of export goods namely Sponge Iron, rejects of Iron Ore chips and Bauxite. IEIL has 6000 m2 of notified unloading/loading area (200 m x 30 m) at Sanegaon and has a custom bonded area of around 40,000 m2.  The  IEIL  proposes  to  develop  Deep Water  Jetty  facility  on  Kundalika  River,  village  Korlai, district Raigad, Maharashtra and capacity expansion at existing Inland Water Jetty Facility, on Kundalika River at village Sanegaon, district Raigad, Maharashtra. The proposed port will be developed  in  3  phases,  at  Korlai  Phase  I‐9.25 MMT,  Phase  II‐16.75 MMT,  Phase  III‐23.50. Geographical coordinates of project is 18° 32’ 10.92” N, 72° 55’ 11.65” E. Capacity expansion at Sanegaon will be achieved by all year round operations as mother vessels will discharge at Korlai Jetty, by using bigger size barges of 4500 DWT and by dredging of channel from Korlai to Sanegaon to 3.1 m CD. 

The capacity of existing facility at Sanegaon is largely limited due to Handling of Coal at the anchorage is unreliable as is non‐operational for about 4 months during southwest monsoon, Depth (draught) available in the River is tide assisted and capacity of the Barges are largely limited and restricted by the Bridge spans (Salav Bridge), it has to cross for transiting to IWT. Improvement of capacity and construction of new jetty will Ensure round the year operation by shifting anchorage operations inside the creek also Undertake dredging wherever required to  improve  available  draught  in  the  river  and  rationalize  barge  dimensions  to  increase capacity. 

IEIL has entrusted the works for the planning, engineering design, project management and commissioning for the proposed project to C‐Borne Services (CBS). Terracon Ecotech Pvt. Ltd., a NABET accredited environmental consultant has been appointed by CBS for providing the services to obtain Environment & CRZ clearance for the proposed project. 

The proposed project attracts Environment clearance under Sector 33 and falls in category A as  per  EIA  Notification  2006  and  its  subsequent  amendments  as  project  attracts  general condition.  

EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy International Ltd. 

 

TEPL/ENV/CBS/2021‐05  III  

Further it also attracts CRZ Clearance under CRZ notification 2011. The proposed deep water jetty facility project falls under CRZ IVB, II and IB according to the CRZ map, whereas, capacity expansion of existing inland water jetty facility at Sanegaon falls under CRZ III and CRZ I (ii). The  CRZ  map  (HTL/LTL  Demarcation)  for  this  project  is  prepared  by  National  Centre  for Sustainable Costal Management (NCSCM) Chennai. 

Public  Consultation  was  carried  out  at  two  different  locations  for  Korlai  and  Sanegaon projects.   First public hearing for Korlai Project was held at mount Carmel High School, on 19.11.2016, Second hearing was held for Sanegaon Project on 21.11.2016 near project site respectively and public MoM of same is published by MPCB (Raigad II SRO).  

As per EIA Notification 2006 and its amendments, ToR application were submitted to MoEFCC for grant of ToR on 10th November 2015 and further presentation was held in EAC meeting on 21st and 22nd December 2015, TOR was  issued on 28th January, 2016 vide  letter no. F. No.10‐34/2015‐IA.III and extended by one year in 2019. 

PROJECT DESCRIPTION 

The proposed project involves development of the jetty about 525 m x 46 m with one 8 m x 8 m mooring dolphin on the east side. The project will  involve dredging a 14.5 km channel requiring 11 million cum of dredging for a depth of 11.0 m CD  in Phase I.  In second phase channel length would increase to 17.5 km and would require 23 million cum (i.e. 12 million cum additional) of dredging for a channel depth of 14.6 m CD. In the final phase the channel length would  increase to 21.5 km and would require 35.5 million cum (i.e. additional 12.5 million cum) dredging for a channel depth of 19.0 m CD and Dredging of 0.99 Mm3 in the inner channel from Korlai to Sanegaon for a depth of 3.1 m CD.  The salient features of proposed facility are as following: 

a) The Jetty will be provided with mobile harbour cranes in the first phase and with fixed ship unloaders in the final phase. 

b) The equipment will discharge  in  to hoppers and  through covered  conveyors  to  the covered stock yard. 

c) Dust suppression mechanisms would be in place. d) Palletized cargo and containers would be handled using mobile harbour cranes and 

taken to the yard by tractor‐trailers. e) The cargo receipt and dispatch would be fully mechanized. f) The barge loading system would be installed for emission free loading. 

 Dredging work 

A 17.5 km channel consisting of 23 million cum of dredging for Panamax Vessels and about 35.5 million cum for Cape Vessels would be required in the ultimate stage. Initial channel will be narrow and  limited to 160 m width with a draft of 11 m and  involve 11 million cum of 

EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy International Ltd. 

 

TEPL/ENV/CBS/2021‐05  IV  

dredging, which will be subsequently dredged to have navigable depth of around 14.6 m and further increased to 19.0 m in the final phase. The dredging spoils of the inner harbour would be used for reclamation of back up area.  

Raw material 

The raw materials used for the construction of wharf will including cement, aggregates, rock, sand, steel, etc. Soil, sand, gravel, stone aggregates will be procured from nearby  licensed sources; whereas,  Cement  and  steel will  be  procured  from  reputed manufacturers  as  per availability. Transportation of the raw material will be by road & Sea. 

Manpower  

Local labours will be hired during construction phase and operation phase. Total manpower requirement for construction phase will be 850 and operation phase will be 350. 

Water requirement 

The total water requirement, the per capita consumption for the in port consumption is taken as 90 liters per day. The occupancy is taken as 350 in the port. Total consumption will be 31, 500  liters  per  day.  The  water  requirement  shall  be  sourced  from  MIDC  or  irrigation department. 

Power requirement 

It  is proposed that the incoming HT supply  is taken from the nearest substation at voltage level of 33 KV. Single transformer of capacity of 33 KV/ 11 KV, 12 MVA oil filled out door type shall be installed. A 33 KV switch yard is to be set up near to the Port area from where three or four 11 KV feeders are taken to feed the port equipment. 33 KV and 1l KV control rooms are required near the yard. 11 KV supply will feed Transformers for Dry Bulk Terminal (Iron Ore), Dry Bulk Terminal (Coal) and common utility. Each Transformer size could be selected based on the individual total connected load. 

Waste management 

During construction phase sewage will be generated from workers camp which will be treated in  STP.  Total  sewage  generation  during  operation  phase  will  be  28.3  m3/day.  Sewage Treatment Plant of capacity 30 m3/day will be provided to treat the sewage. Treated sewage will be used for gardening, dust suppression and the sludge will be used as manure. In any case  there will  be no disposal  of  treated  sewage  in marine water. Water mixed with  coal particles during sprinkling will be collected through channel along the storage into a clarifier system wherein water and coal dust will be separated 

The debris generated due to dredging will be majorly used for reclamation of backup area of the port and the balance  is to be disposed in deep sea at designated area. The other solid waste will be segregated. Recyclable waste will be disposed of through approved vendors and remaining waste will be disposed off though approved facility. 

EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy International Ltd. 

 

TEPL/ENV/CBS/2021‐05  V  

Project implementation period and cost 

The project implementation schedule will be of 30 months. The total cost of the project is INR 2000 Crores. For Phase I – INR 1160.83 Cr, For Phase II‐ INR 408.70 Cr, For Phase III‐ INR 430.70 Cr. 

DESCRIPTION OF ENVIRONMENT 

Baseline environmental study was carried out in post‐monsoon in October 2015 to February 2016 for Soil quality, Ambient air quality, Water quality, Terrestrial ecology, Marine ecology, Noise level monitoring and Socio‐economic studies in an area of 10 km radius from proposed project site.  

Monitoring surveys of the study area (project area) has been carried out in one season i.e. October 2015 to February 2016. In addition separate studies for the bed material and marine ecology were carried out between March 2016 and May 15th 2016.  The Ambient Air quality monitoring was carried out by the MoEF and CC approved lab Enviro care Pvt. Ltd. Whereas water and soil sampling and analysis were carried out by NABL approved Ana laboratories. 

Land Environment 

Soil 

The soil samples collected from four locations shows pH in slight to moderate alkaline range. The soil texture was found to be loamy due to which it shows low moisture content. Moderate levels of EC indicate no effect of salinity in soil. Absence of heavy metals shows that there is no pollution due  to domestic or  industrial waste. Organic matter  in  range of 1.77  to 2.86 showed good quality of soil. Soil sample of project site showed natural levels other micro and macronutrients. 

Marine Water 

The pH of marine water samples at all the four locations sampled was found to be moderately alkaline. Electrical conductivity and Salinity are present at optimum levels of sea water. Micro & macro nutrients are present at natural levels. Also presence of COD, BOD, heavy metals and Oil  &  Grease  indicates  commercial  or  domestic  pollution  in  the  sampled  areas.  Overall qualitative analysis of marine water indicated presence of source of pollution which may be due to anthropogenic activities, industrial waste, and domestic waste and boat movements. 

Marine Ecology 

The concentration and the numerical abundance of the phytoplankton indicate the fertility of a  region.  The Asterionella  Formosa, Navicula, Coscinodiscus and Streptotheca  species was little  dominant  which  was  recorded  in  all  stations,  no  rare  or  endangered  group  of phytoplankton were found in the area. The concentration and the numerical abundance of the  zooplankton  indicate  the  high  productive  water  body.  Luciferid  shrimps  (larvae  and adults) had  the highest  contribution  in  abundance,  in  the  coastal  and oceanic  region.  The 

EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy International Ltd. 

 

TEPL/ENV/CBS/2021‐05  VI  

sample analysis results reveal high benthic productivity in the study area. Brachyuran, Nereis and Oyster were dominant. 

Terrestrial Ecology 

Fauna 

In the core, total 21 species of faunal species were encountered based on random survey. The avian  group  was  the  most  diverse  followed  by  insects.  Common  sandpiper  (Actitish hypoleucos) and Indian pond heron (Ardeola grayii) are the most common bird species in the core. The butterfly‐Small Salmon Arab (Colotis amata) is the most dominating insect species in core. 

Flora 

During the study, random sampling along with systematic sampling using nested quadrates was undertaken in the core and buffer. Based on the data collected by these techniques an overall species list was generated. In all, 164 species were encountered during this rapid single season study. These 164 species belonged to 58 families.  The species observed can be further categorized into following habits: 

Habit  Number of species 

Tree  66Herb  49 Climber  28 Shrub  19Epiphyte  2 

 

Ambient Air Quality 

Ambient Air Quality Monitoring was carried out for 8 locations as per NAAQM specifications of CPCB for the parameters PM10, PM2.5, SO2, NOx and samples were collected on 24 hours basis for all parameters and one hour sampling for CO as per standard method. Additionally O3, NH3, C6H6, BaP, Pb, As and Ni were analyzed. Frequency of sampling was twice a week during study period. 

During the study period in the entire study area the maximum value of PM2.5 was observed at Mandala i.e. 18.59 μg/m3 and the lowest was observed at project site i.e 14.60 μg/m3. PM 10 was maximum at Mandala and minimum at project site the values are 51.20 μg/m3 42.78 μg/m3 respectively.  The  minimum  SOx  concentration  value  of  6.88  μg/m3  was  observed  at  project  site  and maximum concentration of 7.98 μg/m3 was observed at Salav. Maximum concentration of NOx was observed at Mandala  i.e. 16.94 μg/m3 and minimum concentration of NOx was observed at Project site i.e. 13.48 μg/m3. The other parameters recorded includes Ammonia, Ozone, Nickel CO, Lead(Pb), Arsenic (As), Benzene, Benzo(a) pyrene were found to be within permissible limits. 

EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy International Ltd. 

 

TEPL/ENV/CBS/2021‐05  VII  

Ambient Noise Quality 

The monitoring of ambient noise was conducted to assess the background noise levels at eight (08) nos. Noise monitoring was carried out for 8 location within 10 km radius of project site. All the readings are within CPCB norms. 

Socio‐Economic Profile  

The proposed project  is expected to have positive  impact on socio‐economic status of the region. Priority for employment will be given to the local people, depending on their skills. Project will as contribute in strengthening the nation’s defence mechanism. 

ANTICIPATED IMPACTS AND MITIGATION MEASURES 

Construction Phase 

Area  Impact  Mitigation Measure 

Land/soil Environment 

Disposal  of  solid  waste  from labour  camps  and  construction activities  may  lead  to  soil contamination, thereby disturbing soil micro‐flora.  Disposal  of  dredged  material on  the  land  area  may  lead  to  soil degradation.  Storage  of  raw  material  on land may lead to accidental spillage of oil or run‐off due to rain water. 

Color  coded  containers will be  provided  for  solid  waste collection.  Also,  toilets  will  be provided to avoid open defecation. The  re‐usable  construction solid waste shall be reused for land filling and reclaiming activities, rest shall be disposed off as per existing local norms.   The  dredged  material generated  shall  be  reused  for reclamation  and  remaining  waste will be disposed off  in deep sea at designated site. 

Marine environment 

The  capital  dredged  and  the disposal  site  of  dredged  material temporary  biological  impacts depending on the prevailing flora and fauna at the sites, areas involved and dredging duration.  Water  turbidity  and  aqueous discharges  (oily  wastes,  sanitary wastes) from the dredgers, barges and workboats involved in the activity may 

Dredging will be confined to only those areas earmarked for the purpose to limit the impact and the dredged sediment will be carefully disposed  at  pre‐decided  sites  at shore  terminal  area  or  used  in construction  During construction period, suitable  barrier  will  be  used  to protect the adjoining water bodies 

EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy International Ltd. 

 

TEPL/ENV/CBS/2021‐05  VIII  

Area  Impact  Mitigation Measure 

affect  photosynthetic  activity  which restrict to plankton food production   Macrobentos at the footprints of  new  construction  will  be  lost permanently.  Water  runoff  from construction  activity  may  affect intertidal habitat.   Due  to  construction  activity mangrove habitat may little disturb in vicinity of the project site. 

from the falling earth materials and dust raised to avoid sedimentation.  Fresh  surface  area  of  the newly  constructed  underwater structures  would  provide  new habitats for selected benthic fauna to  colonize  and  grow.  However macrobenthos  will  be  periodically studied to enable taking corrective measures, if warranted  Contractor should take care to  stop  run‐off  water  enter  in intertidal area.  Mangrove  management plan has been sketched out for the conservation  of  mangroves  in  the marine ecosystem at or in vicinity of the project site. 

Terrestrial ecology 

The project  area does not  fall under any of the reserved forest area. There  are  no  endangered  species  of flora  and  fauna  within  the  project area,  neither  any  endemic  flora  nor fauna  species  are  found  in  the adjoining area. Wild life activity is also absent in the area. 

During  construction  all  the care  will  be  taken  to  preserve existing flora and fauna   The  loss  of  these  will  be compensated as per  the standards norms and practice. 

Air  Dust  will  be  generated  from loading  un‐loading  of  raw‐materials, dredging,  reclamation  and  other construction activities can degrade air quality.  Emissions  from  the construction  equipment  used  for activities  like  reclamation,  boring, pilling and dredging may contribute to deterioration of air quality.   DG  sets  will  be  operated  in case of  any power  failure which may contribute to emissions 

Adopt  dust  settlement mechanisms  by  way  of  a  water sprinkler  system  while  conducting construction activities.   Wind sheltering with help of barriers shall be installed during the stock  piling  activity.  The  raw‐material  storage  shall  be temporarily  covered  as  far  as possible  with  adequate  covering material such as plastic, tarps etc. 

EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy International Ltd. 

 

TEPL/ENV/CBS/2021‐05  IX  

Area  Impact  Mitigation Measure 

Dust masks will be provided to  workers  toll  minimize  their exposure to dust.   It  will  be  ensured  that loading,  transfer,  and  discharge  of construction  materials  take  place with a minimum height of fall, and shielded  against  wind.  Dust suppression  spray  unit  will  be deployed where necessary.  Vehicles  having Government license and certificate for  transportation  of  construction will be commissioned.  The  DG  sets  should  be provided  with  adequate  stack height  for  the  proper  dispersal  of the pollutants. 

Noise  Construction  activities  will have  major  impact  on  noise environment.    The  major  sources  of  noise pollution  during  construction  phase would  be  operation  of  equipment engaged  in  various  construction activities.  •  Noise  would  be generated  during  transportation, loading  and  unloading  of  raw materials, dredging process, use of DG sets. 

• All  construction  equipment  shall be  fitted  with  exhaust  silencer. Damaged  silencer  to  be  promptly replaced and equipment should be maintained  properly  by  the contractor. •  It will  be  ensured  specified noise emission standards are met. •  DG  sets  will  be  used  with acoustic enclosure. •  •  Aspects  of  the  land reclamation  construction  that generate  excessive  noise,  such  as pile  driving,  will  be  undertaken during  daylight  hours  where possible •  Protect  the  amenity  of surrounding  area  by  ensuring  that noise  levels  meet  the  statutory requirements  and  acceptable standards. 

Socio‐Economics  Positive  impacts  in  terms  of direct  employment  generation  as 

Inconvenience  caused  to people  during  construction  phase 

EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy International Ltd. 

 

TEPL/ENV/CBS/2021‐05  X  

Area  Impact  Mitigation Measure 

construction  of  the  proposed  project will  need  skilled  and  semi‐skilled labours.  There  can  be  inconvenience caused  to  the  people  during construction  period  in  terms  of  high noise levels, traffic, etc.  

will be kept at a minimal level. Use of  silencer  in  noise  producing equipment’s  and  proper maintenance of vehicles should be done wherever possible.    Safe  navigation  routes should  be  created  for  civilians  to minimize the inconvenience caused to them during construction.  

Operation Phase 

Area  Impact  Mitigation Measures 

Soil  Oily  wastes  and  dredged material removed during maintenance dredging may lead to contamination of land environment.  Solid  waste  generated  may contaminate the area and lead to foul smell if not maintained well. 

Oily wastes and dredged material  removed  during maintenance  dredging  may lead  to  contamination  of  land environment.  Solid  waste  generated may contaminate the area and lead  to  foul  smell  if  not maintained well. 

Marine environment 

The waste water generated due to sprinkling of water on coal stack may lead to water contamination.   The  sewage  generated  from ships if not managed properly may lead to nuisance to local people and loss of aesthetic  value  of  the  area.  Further aqueous discharges from vessels such as  dumping  of  ship  waste  (sullage/ sewage), oil contaminated bilge water, holding  cleaning  and  tank  cleaning residues (slop), and spillages upon re‐fueling and lubricating oil changes and disposal  of  solid  wastes  may 

The  waste  water generated  due  to  sprinkling  of water  on  coal  stack  shall  be collected  and  treated  in clarifier; the treated water shall be  reused  for  sprinkling purposed while the dust will be sent to coal stack.  The  sewage  will  be treated  in  the  Sewage treatment plant and the treated water  shall  be  utilized  in landscaping  and  dust suppression,  whereas  the sludge shall be used as manure. 

EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy International Ltd. 

 

TEPL/ENV/CBS/2021‐05  XI  

Area  Impact  Mitigation Measures 

contaminate quality of  sea water and sediment too.  Loading  and  unloading activities  may  lead  to  accidental spillage of material.   Storm  water  drainage  system may lead to increase in  levels of oil & grease due to spillage or leakage.   Water  used  for  hydraulic testing may mix with any of the water body.

The  sewage  from  the ships will also be treated within the  ships  and  hence  there will be no  risk of  contamination of surface  or  groundwater  as  a result  of  the  effluent  or waste discharge  from the ships when within the port area.  Ships will not be allowed to  release  any oily  bilge waste or  ballast  water  in  the  sea within  port  limits  and  hence wastes from the ships will also not  affect  any  surface  or groundwater  according  to  the International  Convention  for the  Prevention  of  Pollution from  Ships,  1973,  as  modified by  the  protocol  of  1978 (MARPOL, 73/78),  Aqueous  discharges from  vessels  and  disposal  of solid wastes will be regulated to minimize  impact  on  marine water and sediment quantity.  Due  care  will  be  taken such  that  no  water  pollution/ contamination  occurs  during loading  and  unloading activities.   The  runoff  from  the slipway,  berths,  etc  will  be collected  and  treated  into  the effluent treatment plant.   Proper  storm  water drainage system with adequate oil  &  grease  traps  shall  be incorporated  in  order  to 

EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy International Ltd. 

 

TEPL/ENV/CBS/2021‐05  XII  

Area  Impact  Mitigation Measures 

remove  any  spillage/  leakage/ runoff of oil and other wastes in sea water.  Water  used  for hydraulic  testing  will  not  be allowed to mix with any of the water body and will be disposed off through drainage system of local authority.

Terrestrial Ecology 

There  will  be  no  significant impact  of  the  project  on  flora  and fauna and other vegetation due to any of  the  pollution  parameters  during operational  phase  of  the  project.  No significant  impact  is envisaged on  the local  terrestrial  flora  fauna during the operational phase of the project. Since there are no reserved forests or forest area in the project area, there will not be any violation of flora and fauna.  Negligible  Impact  on  marine flora  fauna  is  envisaged  due  to navigation of ships,  loading unloading of  cargos,  run‐off  water  from  the refueling  stations  etc.  Green  belt development  will  help  in  attenuating any  pollution  caused  during  the operation of the proposed facility. 

Proper  care will  be  taken to maintain eco‐balance.  

Air Environment 

Air  quality  may  impact  while loading, unloading and  transportation of coal.  The major  activities  envisaged in  the  proposed  project  is  fugitive emissions  from the cargo  loading and unloading  activities,  DG  sets, navigational equipment/ machinery. 

Water spray or sprinkler system will be provided at the barge unloader, coal stacks and truck loading station.  Regular  monitoring  of air quality as mentioned in EMP will  enable  to  keep  the  air 

EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy International Ltd. 

 

TEPL/ENV/CBS/2021‐05  XIII  

Area  Impact  Mitigation Measures 

Over‐fueling or careless fuelling practices may also  lead to  impacts on air quality of the project site area.  

quality  below  permissible standards  The  exhaust  emissions from  ships/vessels  shall  be controlled on the ship  itself by providing  long  stacks  with  air emission control option such as sea‐water  scrubbing  and  fuel substitution.  D.G Set will be used only in  case  of  emergency  with proper enclosures.  Control  and  check  will be  kept  on  careless  fuelling  of the  ships  if  any  and  excessive trafficking  of  the  ships  at  one place.  Approach  roads  will  be covered with green belt on both the sides to avoid any air quality problems  to  the  nearby residents. Road  Furniture  / Signboards will be put along the approach  roads  and  at  project building  requesting  motorists to avoid idling or/and stoppage of  the  vehicles  at  non‐designated places

Noise Environment 

During  the  operation  phase, noise  will  be  generated  due  to  the operation  of  the  generators,  pumps, engines of boats and ships, cranes for handling vessel and shipment.   DG  set  installed  for  power backup may  also  result  in  increase of noise levels of the area when used.

All  vehicles  used  for operation  shall  be  properly maintained  by  doing  properly lubrication  and  servicing  to keep  noise/vibration  within permissible limits.   Silent  DG  sets  will  be used  during  operation  with proper enclosures.  

ENVIRONMENTAL MONITORING PROGRAM   

EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy International Ltd. 

 

TEPL/ENV/CBS/2021‐05  XIV  

Monitoring of different components of the environment including air, soil and water as well as flora and fauna wherever necessary, as detailed in the EIA Report will be conducted during the construction as well as the operational phases of the project to evaluate the performance of the  EMP.  The  monitoring  plan  specifies  the  parameters  to  be  monitored,  location  of  the monitoring sites, frequency and duration of monitoring, applicable standards and institutional responsibilities for implementation.  

ADDITIONAL STUDIES 

Risk assessment study was carried out to identify negative impacts of proposed project and the associated risks and hazards  involved during the construction and operational phases of the project.  

A disaster management plan was prepared for the occurrences of cyclone, oil spills and other such emergencies. Roles and responsibilities have been clearly defined and details have been outlined in the EIA report.  

PROJECT BENEFITS  

The proposed project will  increase  the EXIM  trade and  creating  employment opportunity, supply chain management, facilities for  industries  in the Maharashtra. The development  is envisaged  to  play  a  significant  role  in  strengthening  connectivity  along  the  Maharashtra coastline.  

Substantial positive impact on socio‐economic profile of Revdanda, in Particular, and Raigad, in general, both in terms of overall employment and skill development of local workforce.  

Enhancement in economy of Maharashtra. The economic growth will have positive impact; it will also help in increase in living standards of the local residents. Direct as well as indirect employment potential is envisaged.  

Probable augmentation in infrastructure resources such as transport, Communication, health facilities & other basic facilities. 

Additionally,  the  proposed  project  will  provide  direct  and  indirect  employment  to skilled/unskilled  and  semiskilled  labourers  to  about  1200  people.  Directly  boost  defence infrastructure which will indirectly provide social benefits during national emergency too. 

ENVIORNMENTAL MANAGEMENT PLAN 

Management  of  environment  during  construction  and  operation  phase  would  include monitoring  of  implementation  of  mitigation  measures  suggested  for  protection  of surrounding  environment  from  adverse  impacts  of  construction  and  operation  phase activities. 

Proper work practice by skilled workforce, use of silt curtains and water sprinkling should be ensured by project proponent or site in charge in construction phase.  

EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy International Ltd. 

 

TEPL/ENV/CBS/2021‐05  XV  

Appropriate measures should be taken to reduce noise levels to the possible extent. Training should  be  given  to  all  the  workers  for  the  proper  handling  of  equipment’s  with  Personal Protective Equipment (PPE). 

The cost estimates for implementing EMP shall be INR 1.5 Crores. The cost includes solid waste management, installation of sanitary facilities, STP, ETP, noise meters green belt development etc. The cost required for implementation of Environmental Monitoring Programme for marine ecology and ambient air quality during construction phase is INR 35 lacs. 

The  cost  required  for  implementation  of  Environmental Monitoring  Programme  for marine water quality, ambient air quality monitoring and effluent management from coal stack yard during operation phase is INR 75 lacs per annum. 

The cost estimates for implementing EMP during construction phase will be Rs. 21.10 lakhs and Rs. 10.00 lakhs during operation phase. 

As  a  responsible  corporate,  M/s  Indo‐Energy  International  Limited  would  integrate  its environment, HR and ethical business policies with appropriate community engagement and gender  equity.  The  major  social  sectors  IEIL  would  emphasize  for  the  local  community developments are Education, Water Sanitation, Health, Livelihood and Empowerment, Sports, Environment, and Infrastructure Development. The total budgetary cost towards the CSR plan to be implanted is INR 40 Cr. 

SUMMARY AND CONCLUSION 

From the Environmental Impact Assessment study, it can be concluded that this project under consideration will not have any significant negative impacts. All possible environment aspects have been adequately assessed and necessary  control measures have been  formulated  to meet the statutory requirements. Thus implementing this project will have positive impacts. 

 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  1  

 

Table of Contents 

1.  Introduction ........................................................................................................................................ 11 

1.1.  Preamble ..................................................................................................................................... 11 

1.2.  General Information on Port and Harbour ................................................................................. 11 

1.3.  Environment Clearance Process ................................................................................................. 11 

1.3.1.  Classification of proposed project as per EIA Notification, 2006 ........................................ 14 

1.4.  CRZ Clearance Process ................................................................................................................ 14 

1.5.  Classification of the project as per CRZ notification 2011 .......................................................... 16 

1.6.  Terms Of Reference (TOR) .......................................................................................................... 19 

1.7.  Validity of EC and CRZ clearance ................................................................................................. 24 

1.8.  Post Environmental Clearance Monitoring ................................................................................. 25 

1.9.  Applicable Legal and Policy Framework ...................................................................................... 25 

1.10.  Generic Structure of the document ........................................................................................ 28 

1.11.  Introduction of Project Proponent ......................................................................................... 29 

1.12.  Brief Description of the Project .............................................................................................. 30 

1.13.  Need of the project ................................................................................................................. 32 

1.14.  Regulatory Compliance ........................................................................................................... 32 

1.15.  Environmental Sensitivity ....................................................................................................... 32 

2.  Project Description.............................................................................................................................. 37 

2.1.  General ........................................................................................................................................ 37 

2.2.  Description of Project Site .......................................................................................................... 37 

2.2.1.  Existing Infrastructure ......................................................................................................... 38 

2.3.  Project Details of Proposed Jetty ................................................................................................ 39 

2.3.1.  Salient features of proposed port configuration ................................................................ 40 

2.4.  Project Details of Sanegaon Facility ............................................................................................ 43 

2.4.1.  Existing Facility .................................................................................................................... 43 

2.4.2.  Need of Expansion at Sanegaon Facility ............................................................................. 43 

2.4.3.  Improvements proposed for Augmenting Capacity ............................................................ 43 

2.5.  Present Opration ......................................................................................................................... 46 

2.6.  Traffic Study & Demand Assessment .......................................................................................... 46 

2.6.1.  Methodology ....................................................................................................................... 46 

2.6.2.  Forecast Model ................................................................................................................... 46 

2.6.3.  Total Traffic for the port ..................................................................................................... 47 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  2  

2.7.  Engineering surveys and investigations ...................................................................................... 48 

2.7.1.  Objective of Work ............................................................................................................... 48 

2.7.2.  Laboratory testing ............................................................................................................... 48 

2.7.3.  Soil Condition ...................................................................................................................... 48 

2.7.4.  Foundation Recommendation ............................................................................................ 49 

2.7.5.  Dredgeability ....................................................................................................................... 49 

2.8.  Development plans for proposed jetty ....................................................................................... 49 

2.8.1.  Demarcation of Port Basin .................................................................................................. 49 

2.9.  Navigation Channel ..................................................................................................................... 49 

2.9.1.  Alignment ............................................................................................................................ 50 

2.9.2.  Navigational Requirements ................................................................................................. 51 

2.9.3.  Model Bathymetry .............................................................................................................. 51 

2.9.4.  Hydrodynamic Model .......................................................................................................... 52 

2.9.5.  Turning Circle in the basin................................................................................................... 53 

2.9.6.  Berths .................................................................................................................................. 54 

2.9.7.  Berth Requirements ............................................................................................................ 54 

2.9.8.  Width of the Berth .............................................................................................................. 55 

2.10.  On shore layout & requirements ............................................................................................ 60 

2.10.1.  Utilization of land reclaimed for the Project.................................................................... 60 

2.10.2.  Storage Area. ................................................................................................................... 61 

2.10.3.  Operation area at the Berth ............................................................................................ 61 

2.10.4.  Ship Unloading ................................................................................................................ 62 

2.10.5.  Proposed System ............................................................................................................. 62 

2.10.6.  Edible Oil ......................................................................................................................... 64 

2.10.7.  Proposed System (Edible Oil) .......................................................................................... 68 

2.10.8.  Bauxite ............................................................................................................................ 68 

2.10.9.  Reclaiming and Ship loading ........................................................................................... 68 

2.10.10.  System Description .......................................................................................................... 69 

2.10.11.  Reclaiming and Ship loading ............................................................................................ 69 

2.11.  Stacking area Computation ..................................................................................................... 69 

2.12.  Dredging .................................................................................................................................. 70 

2.12.1.  Quantity of dredging ....................................................................................................... 70 

2.12.2.  Dredged Volume ............................................................................................................. 70 

2.12.3.  Dispersion of Dredged material ...................................................................................... 72 

2.12.4.  Reclamation .................................................................................................................... 73 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  3  

2.13.  Road And Rail Connectivity ..................................................................................................... 74 

2.13.1.  Road ................................................................................................................................ 74 

2.13.2.  Rail ................................................................................................................................... 75 

2.14.  Natural resources .................................................................................................................... 75 

2.14.1.  Water requirement ......................................................................................................... 75 

2.14.2.  Power requirement ......................................................................................................... 76 

2.14.3.  Wastewater Generation and Management .................................................................... 76 

2.14.4.  Solid Waste Generation and Management ..................................................................... 76 

2.15.  Manpower requirement ......................................................................................................... 77 

2.16.  Project implementation schedule ........................................................................................... 77 

3.  Description of environment ................................................................................................................ 79 

3.1.  General ........................................................................................................................................ 79 

3.2.  Study Area ................................................................................................................................... 79 

3.3.  Topographic Survey .................................................................................................................... 80 

3.4.  Geology ....................................................................................................................................... 81 

3.4.1.  Drainage Pattern ................................................................................................................. 81 

3.5.  Physiography ............................................................................................................................... 82 

3.6.  Land Use ...................................................................................................................................... 84 

3.7.  Shore line .................................................................................................................................... 86 

3.8.  Seismicty ..................................................................................................................................... 87 

3.9.  Cyclone zone ............................................................................................................................... 88 

3.10.  Water Environment ................................................................................................................ 89 

3.11.  Biological Environment ........................................................................................................... 91 

3.11.1.  Marine Ecology................................................................................................................ 91 

3.11.2.  Terrestrial Ecology .......................................................................................................... 96 

3.11.3.  Material and methods ..................................................................................................... 96 

3.11.4.  Sampling Stations ............................................................................................................ 98 

3.12.  Air Environment .................................................................................................................... 107 

3.12.1.  Meteorological Data ..................................................................................................... 107 

3.12.2.  Secondary ...................................................................................................................... 107 

3.13.  Air Quality ............................................................................................................................. 126 

3.14.  Noise Quality ......................................................................................................................... 139 

3.15.  Socio‐Economic Environment ............................................................................................... 141 

4.  Anticipated environmental impact and mitigation measures .......................................................... 147 

4.1.  Environmental Impact Assessment Definitions (EIA) ................................................................ 147 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  4  

4.2.  Purpose of Environment Impact Assessment ........................................................................... 147 

4.3.  Potential Environment Impacts of the Project ......................................................................... 148 

4.4.  Environment impact assessment and mitigation measures ..................................................... 148 

4.4.1.  Introduction ...................................................................................................................... 148 

4.5.  Significant Environmental Impacts and Mitigative Measures .................................................. 148 

4.5.2.  Important attributes during construction phase .............................................................. 150 

4.6.  Impacts during construction phase ........................................................................................... 151 

4.6.1.  Air quality .......................................................................................................................... 151 

4.6.2.  Noise quality ..................................................................................................................... 152 

4.6.3.  Water quality .................................................................................................................... 153 

4.6.4.  Land environment ............................................................................................................. 155 

4.6.5.  Topography soil and geology ............................................................................................ 156 

4.6.6.  Reserved forest and fauna ................................................................................................ 156 

4.6.7.  Land use ............................................................................................................................ 156 

4.6.8.  Impacts on utility services and community severance ..................................................... 157 

4.6.9.  Marine Environment ......................................................................................................... 157 

4.6.10.  Impacts during operation phase ................................................................................... 158 

4.6.11.  Air quality ...................................................................................................................... 158 

4.6.12.  Noise quality ................................................................................................................. 159 

4.6.13.  Water quality ................................................................................................................ 160 

4.6.14.  Land Environment ......................................................................................................... 161 

4.6.15.  Ecological resources and flora and fauna ..................................................................... 161 

4.6.16.  Land use ........................................................................................................................ 162 

4.6.17.  Oil spills: ........................................................................................................................ 163 

4.6.18.  Mangrove: ..................................................................................................................... 163 

4.6.19.  Dredging and dredged material management activities: ............................................. 164 

4.6.20.  IMPACTS ON QUALITY OF LIFE ...................................................................................... 164 

4.6.21.  Construction Phase ....................................................................................................... 165 

4.6.22.  Operation Phase ............................................................................................................ 168 

4.6.23.  Evaluation of impacts .................................................................................................... 171 

4.6.24.  Evaluation of impacts .................................................................................................... 171 

5.  Alternative Analysis........................................................................................................................... 174 

6.  Environmental Monitoring programme ............................................................................................ 178 

6.1.  The Need ................................................................................................................................... 178 

6.2.  Monitoring Plan ........................................................................................................................ 179 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  5  

6.2.1.  Monitoring during Construction Phase ............................................................................. 179 

6.2.2.  Monitoring during the Operational Phase ........................................................................ 179 

6.3.  Reporting ................................................................................................................................... 179 

6.3.1.  Compliance Reports .......................................................................................................... 179 

7.  Additional Studies ............................................................................................................................. 184 

7.1.  Environmental risk .................................................................................................................... 184 

7.1.1.  Risk identification and quantification ............................................................................... 184 

7.1.2.  Risk mitigation ................................................................................................................... 184 

7.1.3.  Concept of risk assessment ............................................................................................... 185 

7.1.4.  Leaks and spillages ............................................................................................................ 185 

7.1.5.  Risk analysis study ............................................................................................................. 187 

7.2.  Onsite emergency plan ............................................................................................................. 188 

7.2.1.  Life saving appliances and arrangements ......................................................................... 189 

7.2.2.  Occupational health and safety ........................................................................................ 189 

7.3.  Disaster management plan (dmp) ............................................................................................ 191 

7.3.1.  Disaster management plan objective ............................................................................... 191 

7.3.2.  Emergency plan for berths and vessel terminal ............................................................... 192 

7.3.3.  Rough weather .................................................................................................................. 192 

7.3.4.  First aid & fire fighting services ......................................................................................... 192 

7.3.5.  Identification of major hazards ......................................................................................... 192 

7.4.  Emergency response measures for natural hazards ................................................................. 193 

7.4.1.  Response in case of earthquake ....................................................................................... 193 

7.4.2.  Response in case of Fire .................................................................................................... 194 

7.4.3.  Response in case of Tsunamis/Storm Surges .................................................................... 195 

7.5.  Identification and assessment of hazards ................................................................................. 196 

8.  Project benefits ................................................................................................................................. 199 

8.1.  Economic Benefits ..................................................................................................................... 199 

8.2.  Socio‐economical benefits ........................................................................................................ 199 

8.3.  Aesthetics and landscape .......................................................................................................... 199 

8.4.  Corporate environmental responsibility ................................................................................... 199 

9.  Environmental Management Plan .................................................................................................... 204 

9.1.  General ...................................................................................................................................... 204 

9.2.  Objectives of Environment Management ................................................................................. 204 

9.3.  Identification of implementing authority ................................................................................. 205 

9.4.  EMP for Construction and Operation Phase ............................................................................. 205 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  6  

9.4.1.  Construction Phase ........................................................................................................... 205 

9.4.2.  Operation Phase ................................................................................................................ 208 

9.5.  Details of management plans ................................................................................................... 211 

9.5.1.  Water Management .......................................................................................................... 211 

9.5.2.  Control of Water Pollution from Marine Transportation ................................................. 211 

9.5.3.  Solid and Hazardous Waste Management Plan ................................................................ 212 

9.5.4.  Other waste ....................................................................................................................... 213 

9.5.5.  Energy conservation .......................................................................................................... 214 

9.5.6.  Plantation, Landscaping and Ecological Management ..................................................... 215 

9.6.  Environment Management Cost ............................................................................................... 216 

9.6.1.  Environmental training ..................................................................................................... 217 

10.  Summary & Conclusion ................................................................................................................ 219 

10.1.  Summary ............................................................................................................................... 219 

10.2.  Conclusion ............................................................................................................................. 222 

11.  Disclosure of Consultants............................................................................................................. 224 

11.1.  About Consultant .................................................................................................................. 224 

11.2.  Accreditation of Organisation ............................................................................................... 224 

11.3.  Services ................................................................................................................................. 224 

 

ListofFigures

Figure 1.1 Project layout for proposed deep water jetty superimposed on CRZ map ............................... 17 

Figure 1.2 Project layout superimposed on CRZ map for Capacity expansion of Sanegaon facility ........... 18 

Figure 1.3 Project location map .................................................................................................................. 31 

Figure 1.4 Environment sensitivity map ..................................................................................................... 35 

Figure 2.1 Korlai Deepwater Jetty off the mouth of the Kundalika River ................................................... 37 

Figure 2.2 Existing JSW Revdanda port facility ........................................................................................... 38 

Figure 2.3 Existing Sanegaon Facility .......................................................................................................... 39 

Figure 2.4 Middle Spans of Bridge on Kundalika River ............................................................................... 39 

Figure 2.5 Concept plan for development of jetty on Kundalika River ....................................................... 40 

Figure 2.6Layou of proposed jetty .............................................................................................................. 42 

Figure 2.7 Existing Sanegaon facility ........................................................................................................... 43 

Figure 2.8Layout for Sanegaon facility ........................................................................................................ 45 

Figure 2.9 Location of present unloading facility at Sanegaon on the West Coast of    India .................... 46 

Figure 2.10Methodology adopted for the traffic study and demand ......................................................... 46 

Figure 2.11 Total Traffic for the Proposed Facility at Revdanda ................................................................. 47 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  7  

Figure 2.12 Location of the port basin ........................................................................................................ 49 

Figure 2.13 Navigation channel plan – Navigation chart #2026 (Extract) .................................................. 51 

Figure 2.14 Bathymetry of the Kundalika River and Arabian Sea for computation .................................... 52 

Figure 2.15 Flow concentration/or stagnation ........................................................................................... 53 

Figure 2.16 Bathymetry of the Kundalika River and Arabian Sea for computation (Close up) .................. 53 

Figure 2.17 Cross section of Approach trestle ............................................................................................ 55 

Figure 2.18 Section of the Berth facility ...................................................................................................... 56 

Figure 2.19Flow diagram for coal handling ................................................................................................ 60 

Figure 2.20 Section of the Final Phase Stock yard for coal ......................................................................... 61 

Figure 2.21 Operation at the berth ............................................................................................................. 62 

Figure 2.22 Storage Shed for fertilizers ...................................................................................................... 63 

Figure 2.23 Truck and Rake loading shed for fertilizers .............................................................................. 64 

Figure 2.24 Unloading of ship by flexible hose ........................................................................................... 65 

Figure 2.25 Unloading of ship by unloading arms ...................................................................................... 65 

Figure 2.26 The P&I diagram for the Liquid cargo handling ....................................................................... 66 

Figure 2.27 Truck/Wagon Loading System for POL/OIL .............................................................................. 67 

Figure 2.28 Loading arrangements at the Bauxite Yard ............................................................................. 68 

Figure 2.29 Inner and Outer Navigational Channel used for computation of quantities ........................... 71 

Figure 2.30 Computation of Dredged Volume ............................................................................................ 71 

Figure 2.31 Dumping location of dredged materials .................................................................................. 72 

Figure 2.32 Model simulated deposition depth after dumping ................................................................. 73 

Figure 2.33 Layout of the Berth along with the approaches and mooring dolphin ................................... 74 

Figure 3.1 Topography map ........................................................................................................................ 80 

Figure 3.2: Drainage map of Raigad ............................................................................................................ 82 

Figure 3.3 Physiography map of Raigad district .......................................................................................... 83 

Figure 3.4 Land use map of proposed project site ..................................................................................... 85 

Figure 3.5 Physical setting of the Shorelines & creek area fo Korli deep water jetty ................................. 86 

Figure 3.6 Map showing seismic zones of India .......................................................................................... 87 

Figure 3.7 : Wind and Cyclone Zones in IndiaSediment Quality ................................................................. 88 

Figure 3.8 Water Sampling .......................................................................................................................... 91 

Figure 3.9 Sampling locations for flora & fauna ......................................................................................... 99 

Figure 3.10 Marine sampling locationsFlora ............................................................................................. 100 

Figure 3.11wind rose ................................................................................................................................ 108 

Figure 3.12 Data collection stations.......................................................................................................... 125 

Figure 3.13 Measured Current Strength and Direction at Location C1 .................................................... 125 

Figure 3.14 Measured Current Strength and Direction at Location C2 .................................................... 126 

Figure 3.15 Graph of Ambient Air Quality Analysis for PM10 .................................................................... 136 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  8  

Figure 3.16Graph of Ambient Air Quality Analysis for PM2.5 .................................................................... 136 

Figure 3.17Graph of Ambient Air Quality Analysis for SO2 ....................................................................... 137 

Figure 3.18Graph of Ambient Air Quality Analysis for NO2 ...................................................................... 137 

Figure 3.19Graph of Ambient Air Quality Analysis for NH3 ...................................................................... 138 

Figure 3.20Graph of Ambient Air Quality Analysis for CO ........................................................................ 138 

Figure 3.21Graph of Ambient Air Quality Analysis for Ozone .................................................................. 139 

Figure 5.1 Possible locations of the port .................................................................................................. 174 

   

List of Tables 

Table 1.1 Standard ToR ............................................................................................................................... 19 

Table 1.2  Additional ToR ............................................................................................................................ 23 

Table 1.3 Applicable legal and policy framework ....................................................................................... 25 

Table 1.4: Environment sensitivity of the project sites .............................................................................. 32 

Table 2.1: Salient features of proposed jetty facility .................................................................................. 40 

Table 2.2 Existing and Projected Traffic at the Sanegaon Barge facility ..................................................... 44 

Table 2.3 Design vessels for the Proposed Jetty/Port ................................................................................ 50 

Table 2.4 Berth Requirements in Phase –I .................................................................................................. 57 

Table 2.5 Berth Requirements in Phase – II ................................................................................................ 57 

Table 2.6 Berth Requirements in Phase – III ............................................................................................... 58 

Table 2.7 Occupancy of the ship unloader fertilizer handling for .............................................................. 62 

Table 2.8 Storage area requirements for various phases ........................................................................... 69 

Table 2.9Designed Ship Vessel Size ............................................................................................................ 70 

Table 2.10 Designed depths in the Navigation channel for a vessel draft of 14.3 m ................................. 70 

Table 3.1 Environmental Monitoring Stations ............................................................................................ 80 

Table 3.2 Damage capacity of cyclone ........................................................................................................ 88 

Table 3.3 Phytoplankton Species observed ................................................................................................ 92 

Table 3.4: Observed Zooplankton Species with Diversity Index ................................................................. 94 

Table 3.5: Observed Macro Benthic Fauna ................................................................................................. 95 

Table 3.6 Habitat summary of the EB sampling points ............................................................................... 98 

Table 3.7 Wind data .................................................................................................................................. 108 

Table 3.8 Ambient Air Quality Monitoring Standards (CPCB) ................................................................... 127 

Table 3.9 Techniques for Measurement of Pollutants ............................................................................. 127 

Table 3.10 Ambient Air Monitoring Report .............................................................................................. 129 

Table 3.11 Ambient Air Quality Recorded at eight locations .................................................................... 135 

Table 3.12 Ambient Noise Levels .............................................................................................................. 140 

Table 3.13: Basic features of Maharashtra ............................................................................................... 141 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  9  

Table 3.14: Maharashtra Population (SC and ST) ..................................................................................... 142 

Table 3.15: Maharashtra Literacy Level .................................................................................................... 142 

Table 3.16: Maharashtra Worker Population ........................................................................................... 142 

Table 3.17: Basic features of Raigad district ............................................................................................. 143 

Table 3.18: Raigad District Population (SC and ST) ................................................................................... 143 

Table 3.19: Raigad District Literacy Level ................................................................................................. 144 

Table 3.20: Raigad District Worker Population ......................................................................................... 144 

Table 4.1Environmental Impacts and Mitigation Measures ..................................................................... 165 

Table 4.2Environmental Impacts and Mitigation Measures ..................................................................... 168 

Table 4.3 List of possible environment impacts due to proposed project ............................................... 172 

Table 5.1 Multi‐criteria analysis of the three port locations .................................................................... 175 

Table 6.1 Environmental Monitoring Plan during project construction phase and operation phase ...... 180 

Table 7.1 Information to be Maintained of Emergency Response Agencies. ........................................... 190 

Table 7.2 Summary of the Disasters Preparedness Plans ......................................................................... 196 

Table 9.1: Environment Management Plan for Construction Phase ........................................................ 206 

Table 9.2: EMP for Operation Phase ......................................................................................................... 209 

Table 9.3 Budgetary rovision for EMP during Construction Phase ........................................................... 216 

Table 9.4 Budgetary Provision for EMP during Operation Phase ............................................................. 216 

 

List of Annexures 

Annexure 1: Awarded ToR Annexure 2: Ship tranquillity study Annexure 3:  Appendix for Terrestrial Ecology Annexure 4: Compliance for 49th EAC meeting    

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  10  

Chapter1Introduction

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  11  

1. INTRODUCTION 

1.1. PREAMBLE 

An Environmental Impact Assessment (EIA) is an assessment of the impacts ‐ adverse or beneficial ‐ that a proposed project may have on the environment, together consisting of the natural, social and economic aspects.  Its purpose  is  to  identify,  examine,  assess and evaluate  the  likely  and probable impacts of a proposed project on the environment and thereby, to design action plans to minimize adverse impacts on the environment.  

The  Ministry  of  Environment,  Forest  &  Climate  Change,  Government  of  India,  New  Delhi (MoEFCC), through its EIA Notification number SO1533 (E) issued on 14th September 2006 and its subsequent amendments, under the Environment Protection Act, 1986. The EIA notification 2006 categorizes various projects and subscribes different processes for Environment Clearance.  

EC  procedure  outlined  in  the  EIA  Notification  reduces  conflicts  by  promoting  community participation, public  information and  transparent decisions as well as helps  in developing  the base for environmentally sound project. 

1.2. GENERAL INFORMATION ON PORT AND HARBOUR 

Ports and harbours serve an essential medium of maritime trade in India. Country’s 95% trade by volume and 70% by value occurs through maritime transport. Enhancement of standard of living calls for continual growth in the economy and commensurate development of all the associated sectors  of  the  country  as  a  whole.  The  intensification  of  maritime  traffic  needs  sustainable management of ports to reduce harmful consequences on local population and environment as well as economy of the country. 

Port activities can cause deterioration of air and marine ecology in the surrounding areas due to multifarious  activities.  Hence,  for  the  determination  of  levels  of  pollution,  identification  of pollution sources, control and disposal of waste from various point and non‐point sources and for prediction of pollution levels for future, regular monitoring and assessment are required for ports.  

In order to assess the likely impacts arising during construction and operation of port, harbour or other  facilities  using  inshore  and  foreshore  zones,  EIA  study  is  undertaken,  followed  by preparation of a detailed Environment Management Plan (EMP) to ensure effectiveness of the impact mitigation strategies implemented. 

1.3. ENVIRONMENT CLEARANCE PROCESS 

The  Ministry  of  Environment,  Forest  &  Climate  Change,  Government  of  India,  New  Delhi (MoEFCC), through its EIA Notification number SO1533 (E) issued on 14th September 2006 and its subsequent  amendments,  under  the  Environment  Protection  Act,  1986,  classified  the  Ports, harbors, break waters and dredging projects into two Categories. The project handling ≥ 5 MTPA (Million Tons Per Annum) of cargo falls under Category A and the project handling <5 MTPA of cargo  and  ≥10,000  TPA  of  fish  handling  capacity  falls  under  Category  B.  Category  A  projects (including new, expansion and modernization of existing projects) require Prior EC from MoEFCC 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  12  

while  Category  B  projects  are  to  be  considered  by  the  State  Level  Environmental  Impact Assessment Authority (SEIAA), constituted by MoEFCC. If in case the “General Condition” given in the EIA Notification are applicable to any Category B project, it is be treated as a Category A and  will  be  appraised  by  EAC.  Given  below  are  the  General  Conditions  specified  to  in  the Notification: 

New EIA notification 2020 is published but still is in draft stage. It can be applicable to the project if it is finalized and relished by MoEFCC in span of acquiring EC for this project   If located in whole or in part within 5 km from the boundary of: (I) Protected areas notified under the Wildlife (Protection) Act, 1972;  (II) Critically polluted areas as identified by the CPCB from time to time; (III) Eco‐sensitive areas as notified under section 3 of the Environment (Protection) Act, 1986  (IV) Inter‐state boundaries and international boundaries 

Application for Prior Environmental Clearance (EC)   

An EIA project  is  initiated by the project proponent submitting a ToR application for an EC to either the MoEFCC or the SEAC as the case may be. The application is made in the Form 1 format provided in the EIA Notification. Form 1 covers basic information about the project. As a part of Form 1 the project proponent has to propose a set of Terms of Reference (ToR) for the EIA studies that  it  would  undertake  for  the  project  and  a  copy  of  the  pre‐feasibility  project  report.  The process of EC can begin only after the approval of ToR from MoEFCC or SEAC. Stages in the EC Process for New Projects 

The EC process for new projects comprises of a maximum of four stages, all of which may not apply to particular cases as set forth below in this Notification. These four stages in sequential order are: ‐ •  Stage (1) Screening (Only for Category ‘B’ projects and activities) •  Stage (2) Scoping •  Stage (3) Public Consultation •  Stage (4) Appraisal Stage (1) ‐ Screening 

In case of Category ‘B’ projects or activities, this stage involves the scrutiny of the Form 1 by the concerned  SEAC  for  determining  whether  or  not  the  project  or  activity  requires  further environmental studies for preparation of an EIA report for its appraisal prior to the grant of the EC depending upon the nature and location specificity of the project. The projects requiring an EIA is termed Category ‘B1’ and remaining projects as Category ‘B2’ which do not require an EIA. For categorization of projects into B1 or B2 the MOEFCC issues appropriate guidelines from time to time. 

 Stage (2) ‐ Scoping  

 “Scoping” refers to the process by which the EAC in the case of Category ‘A’ projects or activities, and SEAC in the case of Category ‘B1’ projects or activities, including applications for expansion and/or  modernization,  determine  detailed  and  comprehensive  ToR  addressing  all  relevant 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  13  

environmental concerns for the preparation of EIA Report in respect of the project or activity for which prior environmental clearance is sought.  

Stage (3): Public Consultation 

“Public Consultation” refers to the process by which the concerns of local affected persons and others  who  have  plausible  stake  in  the  environmental  impacts  of  the  project  or  activity  are ascertained with a view to taking into account all the material concerns in the project or activity design  as  appropriate. All  Category  ‘A’  and Category B1 projects  or  activities  are  required  to undertake Public Consultation, in accordance with the procedure described in Appendix IV of the Notification, except the following: 

a. Modernization of irrigation projects. b. All Category ‘B2’ projects and activities. c. All  projects  or  activities  concerning  national  defense  and  security  or  involving  other 

strategic considerations as determined by the Central Government. The Public Hearing ordinarily has two components comprising of: 

(a) A Public Hearing at the project site or in its close proximity – district‐wise to be carried out in the manner prescribed in Appendix IV for ascertaining concerns of the project affected persons; 

(b) Obtain  responses  in writing  from other concerned persons having a plausible stake  in  the environmental aspects of the project or activity and attempting to satisfy them through facts if some of the concerns are unfounded or due to incorrect assessment of the consequences. 

The public hearing at, or in close proximity to, the site(s) in all cases is to be conducted by the State Pollution Control Board (SPCB) or the Union territory Pollution Control Committee (UTPCC) concerned  in  the  specified manner  and  forward  the  proceedings  to  the  regulatory  authority concerned within 45 (forty‐five) days of a request to the effect from the applicant. 

 Stage (4): Appraisal 

Appraisal means the detailed scrutiny by the EAC or SEAC of the application and other documents like  Detailed  Project  Report  (DPR),  the  Final  EIA  and  EMP  Report,  outcome  of  the  Public Consultations including Public Hearing proceedings, submitted by the applicant to the regulatory authority concerned for grant of environmental clearance. On conclusion of this proceeding, the EAC  or  SEAC  concerned  makes  categorical  recommendations  to  the  regulatory  authority concerned  either  for  grant  of  EC  on  stipulated  terms  and  conditions,  or  rejection  of  the application for EC, together with reasons for the same.  

Grant or Rejection of EC 

The  regulatory  authority  considers  the  recommendations  of  the  EAC or  SEAC  concerned  and convey its decision to the applicant within 45 days of the receipt of the recommendations of the EAC or the SEAC concerned or in other words within 105 days of the receipt of the Final EIA, and 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  14  

where  EIA  is  not  required,  within  105  days  of  the  receipt  of  the  complete  application  with requisite documents, except as indicated otherwise in the Notification. 

1.3.1. CLASSIFICATION OF PROPOSED PROJECT AS PER EIA NOTIFICATION, 2006 

The proposed project “Development of deep water jetty facility on Kundalika river, village‐Korlai, Ditrict‐Raigad,  Maharashtra  &  capacity  expansion  of  existing  inland  water  jetty  facility,  on Kundalika rivers village‐Sanegaon, Ditrict‐Raigad, Maharashtra” falls under Category A as per EIA Notification 2006 and its subsequent amendments as proposed project involves development of the Jetty about 525 m long with one 8 m x 8 m mooring dolphin on the east side. The project will involve dredging a 14.5 km channel requiring 11 million cum of dredging for a depth of 11.0 m CD in Phase I. In second phase channel length would increase to 17.5 km and would require 23 million cum (i.e. 12 million cum additional) of dredging for a channel depth of 14.6 m CD. In the final phase the channel length would increase to 21.5 km and would require 35.5 million cum (i.e. additional 12.5 million cum) dredging for a channel depth of 19.0 m CD and Dredging of 0.99 Mm3 in the inner channel from Korlai to Sanegaon for a depth of 3.1 m CD. 

Public Consultation was carried out at two different locations for Korlai and Sanegaon projects.  First public hearing  for Korlai  Project was held at Mount Carmel High School, on 19.11.2016, Second hearing was held for Sanegaon Project on 21.11.2016 near project site respectively and public MoM of same is published by MPCB (Raigad II SRO).. 

1.4. CRZ CLEARANCE PROCESS 

MoEFCC had declared coastal stretches as Coastal Regulation Zone and imposed restrictions on industries, operations and processes in the CRZ through a Notification in 2019 and outlined the procedure for obtaining the CRZ clearance for the developmental activities in the CRZ.  

However, as per the letter no. F.No.19‐36/2017‐IA.III dated 26.02.2019 by MoEFCC, clarification on implementation of project falling in CRZ area in Maharashtra has been given which directs  to state that “Until the CZMPs of Maharashtra prepared under provision of CRZ notification 2011 are  updated/revised  under  provision  of  CRZ  notification  2019  issued  vide  GSR  37(E),dated 18.01.2019 the provision of CRZ notification 2011 shall continue to be followed for appraisal and CRZ clearance of projects in CRZ area and provision of new notification shall not apply”.  

Hence, as per the Coastal Regulation Zone Notification 2011 and its amendments thereafter; for regulating development activities along the coast open to the sea, the coastal stretches within 500 m of High Tide Line (HTL) on the landward side are classified into four categories, namely: CRZ (I), (II), (III) and (IV).  

1. CRZ‐I: (A): The areas that are ecologically sensitive and the geomorphological features which play a role in the maintaining the integrity of the coast,‐ (i) mangroves; (ii) coral reefs; (iii) sand beaches and sand dunes; (iv) mudflats; (v) protected areas under the Wild Life (Protection) Act, 1972 (53 of 1972), the Forest (Conservation) Act, 1980 (69 of 1980) or Environment (Protection) Act,  1986  (29  of  1986);  (vi)  salt marshes;  (vii)  turtle  nesting  grounds;  (viii)  horse  shoe  crabs 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  15  

habitats; (ix) sea grass beds; (x) sea weed beds; (xi) nesting grounds of birds; (xii) fishing villages and areas of traditional rights. 

(B) ‐ The area between Low Tide Line and High Tide Line. 

2. CRZ‐II ‐ The areas that have been developed up to or close to the shoreline. 

3. CRZ‐III  ‐ Areas that are relatively undisturbed and those do not belong to either CRZ‐I or  II which include coastal zone in the rural areas (developed and undeveloped) and also areas within municipal limits or in other legally designated urban areas, which are not substantially built up. 

4. CRZ‐IV: CRZ IV shall constitute the water area and is further classified as follows: 

(A) The water area from the Low Tide Line to twelve nautical miles on the seaward side; and  

(B) The water area of the tidal influenced water body from the mouth of the water body at the sea up to the influence of tide which is measured as five parts per thousand during the driest season of the year. 

If an organization wishes to obtain CRZ clearance for the development/construction activity, it will be first required to prepare an EIA report for the project. An important step for preparing EIA for CRZ clearance is to classify the site to appropriate CRZ category. This is to be done by the help of CRZ mapping of the area through an agency authorized by the MOEFCC. CRZ map which is to be in 1:4000 scale normally shows the area of 7 km radius from the proposed project site. Various technical aspects like HTL, LTL, eco sensitive areas etc. are to be shown on the map along with the superimposition of the proposed project. The MOEFCC has authorized 8 agencies across India to undertake the CRZ mapping.  

Authorized agencies by MoEFCC for carrying out CRZ mapping are: 

Space Application Centre–Ahmadabad  Centre for Remote Sensing–CESS, Thiruvananthapuram  Institute for Remote Sensing–Anna University–Chennai  Institute for wetland Management and ecological designs–Kolkata  National Hydrographic Office–Dehradun  National Institute of Oceanography–Goa  National Institute of Ocean Technology– Chennai   National Centre for Sustainable Coastal Management (NCSCM).  

Every coastal  state  in  India has a Coastal Zone Management Authority  (CZMA) which has  the mandate to accord CRZ clearance / recommendation to the proposed development activity. The documents and reports that need to be submitted for consideration of the CRZ clearance are given below:   

Project  summary  details  which  includes  relevant  information  about  the  project  in  a summarized form 

EIA Report 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  16  

Disaster Management Report, Risk Assessment Report and Management Plan   CRZ map indicating HTL and LTL demarcated by an authorized agency (1:4000 scale)  Project layout superimposed on the CRZ map  No  Objection  Certificate  from  the  concerned  State  Pollution  Control  Board  or  Union 

territory Pollution Control Committee  for  the projects  involving discharge of effluents, solid wastes, sewage etc. 

The concerned CZMA examines the above documents in accordance with the approved EMP and CRZ Notification and calls for a meeting within 60 days from the receipt of above documents. If the Committee finds the proposed project appropriate for clearance their recommendation  is forward to MoEFCC or SEIAA where final clearance is granted to the project. 

1.5. CLASSIFICATION OF THE PROJECT AS PER CRZ NOTIFICATION 2011 

The proposed deep water jetty facility project fall under CRZ IVB, II and IB according to the CRZ map. The CRZ map  (HTL/LTL Demarcation)  for  this project  is prepared by National Centre  for Sustainable Costal Management (NCSCM) Chennai. Capacity expansion of existing inland water jetty facility at Sanegaon falls under CRZ III, CRZ I. Project layout superimposed on approved CRZ map for proposed deep water jetty given in Figure 1.1. and for Capacity expansion for Sanegaon facility is given in  

Figure 1.2.

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy International Ltd. 

TEPL/ENV/CBS/2021‐05  17  

 

Figure 1.1 Project layout for proposed deep water jetty superimposed on CRZ map 

 

   

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy International Ltd. 

TEPL/ENV/CBS/2021‐05  18  

 

Figure 1.2 Project layout superimposed on CRZ map for Capacity expansion of Sanegaon facility

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  19  

1.6. TERMS OF REFERENCE (TOR) 

As per EIA Notification 2006 and its amendments, ToR application (Form‐I, Prefeasibility Report and proposed ToR) were submitted to MoEFCC for grant of ToR on 10th of November 2015. The ToR presentation was conducted during meeting held on 21st and 22nd December 2015 TOR was issued on 28th January, 2016 vide letter no. F. No.10‐34/2015‐IA.III (Annexure 1).  On the basis of  recommendations  of  the Committee, Ministry  of  Environment,  Forest  and  climate Change hereby accord approval to the project for award of TOR with following stipulations as listed in Table 1.1 and Table 1.2  

Table 1.1 Standard ToR 

S. No.  Standard ToR  Compliance 

Reason  for  selecting  the  site  with  details  of alternative  sites  examined/rejected/selected  on merit with comparative statement and reason/basis for  selection.  The  examination  should  justify  site suitability  in  terms  of  environmental  angles, resources  sustainability  associated  with  selected site  as  compared  to  rejected  sites.  The  analysis should  include  parameters  considered  along  with weightage criteria for short listing selected site. 

Details of Alternatives are given in Chapter 5 

Details of  the  land use break‐up  for  the proposed project. Details of the land use around 10 km radius of  the  project  site.  Examine  and  submit  details  of land use around the 10 km radius of the project site and map of the project area and 10 km area from boundary  of  the  proposed/existing  project  area, delineation project area notified under the wildlife (protection)  Act  1972/critically  polluted  area  as identified by CPCB from time to time/ notified eco‐ sensitivity  area/interstate  boundaries  and international boundaries. Analysis should be made based on  latest satellite  imagery  for  land use with raw images. 

Land use map is presented inChapter 3 and the details of Study Area of 10 km radius around the project site are given in Chapter 3 Section 3.5

Submit  the  present  land  use  and  permission required  for  any  conversion  such  as  forest, agriculture,  etc.  land  acquisition  status, rehabilitation of communities / villages and present status of such activities. 

Present  land  use  is  included in  Chapter  3  section  3.6. Conversion  of  forest  land  is not involved. 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  20  

S. No.  Standard ToR  Compliance 

Examine and submit the water bodies including the seasonal  ones within  the  corridor  of  impact  along with  their  status,  volumetric  capacity,  and  quality likely impacts on them due to the project.  

Water  bodies  in  the  study area  are  mentioned  in Chapter 3 section 3.10. The impacts on water bodies due proposed project and its mitigation  measures  are given in Chapters 4. 

5 Submit  a  copy  of  the  contour  plan  with  slope, drainage pattern of the site and surrounding area. 

Contour  plan  and  drainage pattern is given in Chapter 3 section 3.3.1 

6 Submit  the details of  terrain,  level with  respect  to  MSL, filling required, source of filling materials and transportation details etc. 

Details  are  provided  in chapter 2 section 2.12.4 

Examine  road/rail  connectivity  to  the  project  site and impact on the existing traffic network due to the proposed  project/activities.  A  detailed  traffic  and transportation  study  should  be  made  for  existing and projected passenger and cargo traffic. 

Information  on  road/rail connectivity  and  impact  on the  existing  traffic  network due  to  the proposed project including  transportation study  are  discussed  in Chapter 2 section.2.13 

8 Submit  details  regarding  R&R  involved  in  the project. 

R & R issues are not involved in the proposed project. 

Submit  a  copy  of  layout  superimposed  on  the HTL/LTL map demarcated by an authorized agency on 1:4000 scale along with the recommendation of the SCZMA. 

CRZ  map  with  the  project layout  superimposed  on  the drawing  prepared  by (NCSCM)  is  reproduced  in Chapter 1 section 1.4.1. 

10 Submit the status of shore line change at the project site. 

Studies on shore line change are  including  in  Chapter  3 section.3.7 

11 Details  of  the  layout  plan  including  details  of channel,  breakwaters,  dredging,  disposal  and reclamation. 

Layout  plan  and  details  of navigation  channel  are discussed  in  Chapter  2 section. 2.3.2,2.4.2 and 2.9 

12 

Details of handling of each cargo, storage, transport along  with  spillage  control,  dust  prevention measures. In case of coal, mineral cargo, details of storage  and  closed  conveyance,  dust  suppression and prevention filters. 

Details are given in Chapter 2 section and Chapter 9 section 9.5. 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  21  

S. No.  Standard ToR  Compliance 

13 

Submit  the  details  of  fishing  activity  and  likely impacts  on  the  fishing  activity  due  to  the project. Specific study on effects of construction activity and pile driving on marine life. 

Details provided in chapter 4 section 4.4.3.6 and  

14  Details of oil spill contingency plan 

Significant  oil  spills  are  not expected.  Facilities  to combat  oil  spills  are discussed  in  Chapter  4 section  4.4.4.2.  Also  oil  spill modelling  report  is  attached as point iv of EAC compliance

15  Details of bathymetry study.  Details provided in chapter 2 section 2.9.3 

16  Details of ship tranquility study.  Study is covered in Annexure 2 

17 Examine  the details  of water  requirement,  impact on  competitive  user,  treatment  details,  use  of treated waste water. Prepare a water balance chart.

Water  requirement, wastewater  treatment,  use of  treated  waste  water  etc. are  given  in  Chapter  2 section. 2.14.1 and 2.14.3 

18 Details  of  rainwater  harvesting  and  utilization  of rain water. 

Rain water  harvesting  is  not proposed  as  the  ground water  level  is  high  being along the bank of the river.  

19 Examine details of solid waste generation treatment and its disposal. 

Solid  waste  generation, storage  and  its  disposal  are addressed Chapter  2  section 2.14.4 

20 Details of desalination plant and the study for outfall and intake. 

Desalination  plant  is  not envisaged. 

21 Examine baseline environmental quality along with projected  incremental  load  due  to  the  proposed project/activities  

Baseline  environmental quality  and  probable incremental  load  due  to  the proposed project are given in Chapters 3 and 4.  

22 The  air  quality  monitoring  should  be  carried  out according  to  the  notification  issued  on  16th November 2009. 

Air  quality  monitoring  was done as specified and results are  included  in  Chapter  3 section 3.12. 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  22  

S. No.  Standard ToR  Compliance 

23 

Examine separately the details for construction and operation  phase  both  for  environmental management  plan  and  environmental  monitoring plan with cost and parameters. 

Environment  management Plan  and  Environment Monitoring  Plan  for construction  and  operation phases  are  addressed  in Chapter  6  and  10 respectively. 

24 

Submit details of a comprehensive risk assessment and disaster management plan including emergency evacuation  during  evacuation  during  natural  and man ‐ made disasters 

Comprehensive  risk assessment  and  disaster management plan is given in chapter 7 of EIA report 

25 

Submit details of the trees to be cut including their species and weather it also involves any protected or endangered  species. Measures  taken  to  reduce the  number  of  trees  to  be  removed  should  be explained  in  detail.  Submit  the  details  of compensatory  plantation.  Explore  the  possibilities of relocating the existing trees. 

Tree cutting is not envisaged for the proposed project. 

26 

Examine  the  details  of  afforestation  measures indicating land and financial outlay. Landscape plan, green belts  and open  spaces may be described. A thick  green belt  should be planned all  around  the nearest settlement to mitigate noise and vibrations. The identification of species/ plants should be made on the basis of botanical studies. 

Plantation,  landscaping  and ecological  management  are addressed  in  Chapters  9 section 9.5.5 

27 

The  public  hearing  should  be  conducted  for  the project  in  accordance  with  provisions  of Environment Impact Assessment Notification, 2006 and  the  issues  raised  by  the  public  should  be addressed in the Environmental Management Plan. The Public Hearing should be conducted based on the ToR letter issued by the Ministry and not on the basis  of  Minutes  of  the  meeting  available  on  the website. 

Public  Consultation  was carried  out  at  two  different locations  for  Korlai  and Sanegaon projects.  01. Public  hearing  for  Korlai 

Project  was  held  at Mount  Carmel  High School, on 19.11.2016.  

02. Public  hearing  was  held for  Sanegaon  Project  on 21.11.2016  near  project site  respectively  and public  MoM  of  same  is 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  23  

S. No.  Standard ToR  Compliance 

published  by  MPCB (Raigad II SRO). 

28 

A detailed draft EIA/EMP report should be prepared in  accordance  with  the  above  additional  ToR  and should be submitted to the ministry in accordance with the notification. 

The final EIA report including EMP  will  be  submitted  to EAC. 

29 Details of  litigation pending against the project  ,  if any, with direction/order passed by any court of law against the project should be given 

There is no litigation pending against the project. 

30 The cost of  the project (Capital Cost and recurring cost)  as  well  as  the  cost  towards  the implementation of EMP should be clearly spelt out. 

Details included in Chapter 9 section 9.6. 

31 

Any further clarifications on carrying out the above studies  including  anticipated  impacts  due  to  the project and mitigative measures, project proponent can  refer  to  the model  ToR  available  on Ministry website  "http://moef.nic.in/manual/Port  and harbour". 

This suggestion is noted. 

Table 1.2  Additional ToR 

S. No.  Standard ToR  Compliance 

1  Importance and benefits of the project.  Details provided in chapter 8  

A  separate  chapter  on  status  of  compliance  of Environmental  Conditions  granted  by state/Centre to be provided. As per circular dated 30” May. 2012 issued by MoEF. a certified report by  Regional  Office.  MoEF&CC  on  status  of compliance  of  conditions  on  existing  unit  to  be provided in EIA‐EMP report 

Not Applicable  

3 Copy  of  consent  to  establish  and  consent  to operate for the existing facilities.  In Process 

4 Submit  a  copy  of  layout  superimposed  on  the HTULTL map demarcated by an authorized agency on 1 4000 scale. 

CRZ  map  with  the  project layout  superimposed  on  the drawing prepared by  (NCSCM) is  reproduced  in  Chapter  1 section 1.4.1. 

5 Various  Ports  facilities  with  capacities  for  the existing as well as proposed project. 

Details mentioned in Chapter 1 section  1.5 

6 List  of  cargo  to  be  handled  along with mode  of transportation. 

Details mentioned in Chapter 2 section 2.2.1 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  24  

S. No.  Standard ToR  Compliance 

7  Layout plan of existing Port and Proposed Port.  Details mentioned in Chapter 2 section 2.11 

8 Details  of  air  pollution  control  measures  to  be taken as well as cost to be incurred 

Impacts  and  mitigation measures  for  controlling  air quality  are  addressed  in Chapter 4 section 1.4.4 and the implementation cost of EMP is included  in  Chapter  9  section 9.6. 

9 Total  water  consumption  and  its  source. Wastewater management plan. 

Total  water  consumption  and its sources are given in Chapter 2  section. Water management plan  is  given  in  chapter  9 section 9.5.1 

10  Details of Environmental Monitoring Plan. Details  for  Environmental Monitoring  Plan  are  given  in Chapter 6. 

11 Disaster  Management  Plan  for  the  above terminal. 

Incorporated  in  Chapter Chapter 7 section 7.3 

12  Layout plan of existing and proposed Greenbelt. 

25% of toal area for green belt and roads in Proposed jetty and 10%  area  for  green  belt  in Sanegaon facility. 

13  Status of court case pending against the project.  There  is  no  litigation  pending against the project. 

14  Recommendation of the SCZMA. 

Recommendation  received from  MCZMA  in  MoM  dated 09.01.2018  and  24.05.2019 which are attached herewith as point  number  ii  of  49th  EAC compliance 

15 A  tabular  chart  with  index  for  point  wise compliance of above TORs. 

Incorporated  in  Chapter  1 section 1.5 

16 

Public hearing to be conducted and issues raised and commitments made by the project proponent on  the  same  should  be  included  in  EIA/EMP Report in the form of tabular chart with financial budget  for  complying  with  the  commitments made. 

Incorporated  in  Chapter1  Section 1.6 

1.7. VALIDITY OF EC AND CRZ CLEARANCE 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  25  

The environmental clearance granted for ports and harbour sector is valid for a period of seven years as per amendment in EIA notification 2006 notified via a Notification, S.O. 1411(E) dated 29 April, 2015. 

As per the CRZ Notification 2011 and its subsequent amendment, the clearance accorded to the projects under the notifications shall be valid for the period of seven years from the date of issue of the clearance for commencement of construction. 

1.8. POST ENVIRONMENTAL CLEARANCE MONITORING 

As per CRZ and EIA Notifications it is mandatory to submit the half‐yearly compliance reports of the conditions in the EC on 1st June and 1st December of each calendar year to the concerned regulatory authority. All such reports are public documents. The latest such compliance report is to be displayed on the website of the concerned regulatory authority. 

1.9. APPLICABLE LEGAL AND POLICY FRAMEWORK 

Applicable legal policy and framework is given in Table 1.3  

Table 1.3 Applicable legal and policy framework 

Sr. No.  Components  Regulatory Bodies Notifications/Rules  /  Acts 

etc. as applicable 

1.   Environment Ministry  of Environment Forest and climate change 

Environment  Protection Act 1986 

2.   Environment Clearance Ministry  of Environment Forest and climate change 

EIA Notification 2006 

3.  Coastal Regulatory zone clearance 

Ministry  of Environment Forest and climate change 

CRZ Notification 2011 

4.  Solid  Waste management 

‐ Solid  waste  management rules, 2016 

5.   E‐Waste management  ‐ E‐ waste management rule, 2016 

6.  Plastic  waste management 

‐  Plastic waste management 

Air quality monitoring and preservation 

7.  

Dust  Mitigation Measures  for Construction  and Demolition  Activities for  projects  requiring Environmental Clearance 

‐ Notification  GSR  94(E) dated  25.01.2018  of MoEFCC  

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  26  

8.  

Diesel  power generating  sets proposed  as  source  of backup  power  should be of enclosed type and conform 

‐ Environment  protection Act, 1986 

9.  

All demolition and construction waste shall be managed as per  the provisions 

‐ Construction  and demolition  waste  rule 2016. 

Water quality monitoring and preservation 

10.  Ground water  recharge /Ground  water dewatering 

‐  CGWB norms 

11.  

Sludge  from  the  onsite sewage  treatment, including  septic  tanks, shall be collected, conveyed and disposed 

‐ 

Ministry  of  Urban Development,  Central Public  Health  and Environmental  Engineering Organization  (CPHEEO) Manual  on  Sewerage  and Sewage  Treatment Systems, 2013. 

12.  

The  quantity  of  fresh water  usage,  water recycling and rainwater harvesting shall be measured and recorded to  monitor  the  water balance as projected by the project Proponent.  The  record shall  be  submitted  (Six monthly compliance) 

to  Regional  Officer  of the Ministry 

According  to  CPCB guideline 

Noise monitoring and prevention 13.   Ambient Noise  ‐   

14.  Noise monitoring (Six  monthly compliance) 

 Regional Officer of  the Ministry 

Noise  Pollution  (Control and Regulation) Rules, 2000

  Waste Management     

15.  A  certificate  handling municipal  solid  wastes, indicating the 

competent  authority handling municipal solid wastes 

 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  27  

existing  civic  capacities of  handling  and  their adequacy  to  cater  to the M.S.W. generated From  project  shall  be obtained. 

16.   Non‐biodegradable waste 

Authorized vender  0.3kg/person/day 

17.   Hazardous waste  ‐ 

Hazardous  Wastes (Management,  Handling and  Tran’s  boundary Movement) Rules, 2008. 

18.   Use  of  fly  ash  and  pre mixed concrete mixture

‐ 

Fly  Ash  Notification  of September,  1999  and amended  as  on  27th August,  2003  and  25 January, 2016. 

19.  Waste  from construction  and demolition activity 

‐ Construction  and Demolition  Waste  Rules 2016 

Transport 

20.   Mobility plan Ministry  of  Urban Development 

MoUD  best  practices guidelines (URDPFI) 

21.   Vehicles Hired 

State  urban development department  and P.W.D/component authority  for  road augmentation  

pollution  check  certificate and  should  conform  to applicable  air  and  noise emission standards 

22.  Traffic  management and  Traffic decongestion plan 

State  urban development department  and P.W.D/component authority  for  road augmentation 

 

Human and Health issue 

23.  Corporate Environmental Responsibility 

‐ Ministry's  OM  vide  F.No. 22‐65/2017‐IA.III dated 1st May 2018 

24.  Company  should  have well  laid  down environmental  policy 

‐ The  copy  of  the  board resolution  in  this  regard shall  be  submitted  to  the 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  28  

and standard operation procedure  and  must report  in  case  of  and violation/deviation 

MoEFCC  as  a  part  of  six‐monthly report 

25.  

Action  plan  for implementing EMP and environmental conditions  along  with responsibility matrix 

‐ 

Year  wise  progress  of implementation  of  action plan  shall  be  reported  to the  Ministry/Regional Office  along  with  the  Six‐Monthly  Compliance Report 

Miscellaneous 

26.   Submission of Copies of EC  

Head of local bodies Panchayat Municipal Bodies Relevant  government officials 

 

27.   Upload  status  of compliance 

‐ On  website  and  in  6 monthly compliance report 

28.  environmental statement  for  each financial year in Form‐V 

State  Pollution  Control Board 

Environment  (Protection) Rules, 1986 

29.   Any appeal against EC  National Green TribunalNational  Green  Tribunal Act, 2010. 

30.   Disaster Management     44 DM_act2005 

31.  

Ancient  Monuments and  Archaeological  site & Remains Act  

Act  to  provide conservation of cultural and  historical  remains found in India. 

Ancient  Monuments  and Archaeological  site  & Remains Act, 1958 

1.10. GENERIC STRUCTURE OF THE DOCUMENT 

The following chapters have been included in this EIA report, which is in line with the Generic Structure of Environmental Impact Assessment and as per the EIA Notification 2006: 

1. Introduction 

This chapter contains the scope of the study, purpose of the report, identification of project proponent and details of the environmental and CRZ clearance processes.  

2. Project description 

This chapter covers the description of the project, such as the type of project, need for the project, project location, project layout, and the project implementation schedule, estimated cost of development etc. 

3. Description of the Environment 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  29  

This chapter contains the comprehensive data on the existing and additional data collected on the baseline environmental data in the study area as well as in the surrounding area that is likely to be affected by the proposed activity. 

4. Anticipated Environmental Impacts & Mitigation Measures 

This chapter covers the anticipated impact on the environment and mitigation measures. It consists of the details of the impact on the baseline parameters, both during the construction and operational phases and the mitigation measures to be implemented by the proponent. 

5. Analysis of Alternatives (Technology & Site) 

This chapter covers the details of various alternatives both in respect of location of site and technologies to be deployed, in case the initial scoping exercise considers such a need. 

6. Environmental Monitoring Program 

This chapter covers the planned Environmental Monitoring Program. It includes the technical aspects of monitoring the effectiveness of mitigation measures.  

7. Additional Studies 

This chapter covers the details of the additional studies, if any, required in addition to those specified in the standard TOR. 

8. Project Benefits 

This chapter covers the benefits accruing to the locality, neighborhood, region and nation as a  whole.  It  should  bring  out  details  of  benefits  by  way  of  improvements  in  the  physical infrastructure, social infrastructure, employment potential and other tangible benefits. 

9. Environmental Management Plan (EMP) 

This chapter comprehensively presents the Environmental Management Plan (EMP), which includes the administrative and technical setup, summary matrix of EMP, the cost involved to implement the EMP, both during the construction and operational phases. 

10. Summary & Conclusion 

This chapter makes the summary of the full EIA report condensed to ten A‐4 size pages at the maximum. It provides the overall justification for implementation of the project and should explain how the adverse effects are proposed to be mitigated. 

11. Disclosure of Consultants engaged This  chapter  includes  the  names  of  the  consultants  engaged with  their  brief  resume  and nature of consultancy rendered. 

1.11. INTRODUCTION OF PROJECT PROPONENT 

Indo Energy International Limited (IEIL) is a company in the sector of Infrastructure Development and Power. Set up in 1999, it is promoted by Esquire Shipping Pvt. Ltd. To cargo by sea, train or road, and also clearance, cargo handling, warehousing and distribution. Some of the services are chartering  and  brokerage,  ship  agency  management,  shipping  consulting  and  multi  modal transport. 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  30  

IEIL started out by servicing the needs of the power sector by building a jetty and barge unloading points. The company specializes in the fields of – Handling of import/export bulk cargo like Steam Coal, Iron Ore, Bauxite, Lime Stone, Sulphur; International trading; Multi modal transport; Port infrastructure development; Marine surveys and consulting. In 2009 the company also built a fair weather multi‐  purpose  terminal,  notified  under  the  Indian  Customs  Act  1962,  to  handle  all import/export and coastal cargos at the rate of 12000‐ 20000 MT/day. 

IEIL has an operational multipurpose jetty at Sanegaon since 2009. The jetty has been approved by Customs, through their notification dated 2 Feb 2010, for unloading of imported goods namely Iron,  Iron  ore  pellets,  Iron  ore  concentrate,  Coal,  Dolomite/Limestone,  Petroleum Gas,  Steel melting scrap, HDI chips/fines, Pulp, Magnesite, Sulphur. The jetty has also been approved by customs for loading of export goods namely Sponge Iron, rejects of Iron Ore chips and Bauxite. IEIL has 6000 m2 of notified unloading/loading area (200 m x 30 m) at Sanegaon and has a custom bonded area of around 40,000 m 

1.12. BRIEF DESCRIPTION OF THE PROJECT 

The IEIL proposes to develop Deep Water Jetty facility on Kundalika River, village Korlai, district Raigad, Maharashtra and capacity expansion at existing Inland Water Jetty Facility, on Kundalika River at village Sanegaon, district Raigad, Maharashtra. The proposed port will be developed in 3 phases,  at  Korlai  Phase  I‐9.25  MMT,  Phase  II‐16.75  MMT,  Phase  III‐23.50.  Geographical coordinates of project is  180 32’ 10.92” N, 720 55’ 11.65” E 

IEIL  is  presently  engaged  in  transportation  and  trading  of  Coal  using  lighterage  facility  at Sanegaon, located on the Right Bank of the Kundalika River, about 50 km south of Mumbai by sea and about 130 km by road. IEIL intends to expand the facility to include the coal required for the proposed power plant planned to be located close to the riverine facility at Sanegaon. The existing  Jetty  is about 21 km upstream (refer Figure 1.1 below) on the right bank of  the river Kundalika and is about 200 m long with a backup area of about 5 hectare for storage, handling and dispatch of material. The clear span between the intermediate bridge piers is 36 m. project location map is given in Figure 1.3. 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy International Ltd. 

TEPL/ENV/CBS/2021‐05  31  

 

 Figure 1.3 Project location map

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  32  

1.13. NEED OF THE PROJECT 

The  capacity  of  existing  facility  at  Sanegaon  is  largely  limited  due  to Handling  of  Coal  at  the anchorage  is unreliable as  is non‐operational for about 4 months during southwest monsoon, Depth (draught) available in the River is tide assisted and capacity of the Barges are largely limited and  restricted  by  the  Bridge  spans  (Salav  Bridge),  it  has  to  cross  for  transiting  to IWT.Improvement of capacity and construction of new jetty will Ensure round the year operation by shifting anchorage operations inside the creek also Undertake dredging wherever required to improve available draught in the river and rationalize barge dimensions to increase capacity. 

1.14. REGULATORY COMPLIANCE 

Environmental impact assessment notification, 2006 and amendments  Coastal Regulation Zone Notification, 2011 and subsequent amendments  Coastal Regulation Zone Notification, 2019  Technical Guidance Manual for Ports and harbours, Feb 2015 by ASCI  CRZ prepared as per CRZ notification 2011.  Documents received from C‐Born Services   Preliminary project report   Detailed Project Report  

1.15. ENVIRONMENTAL SENSITIVITY  

The  environment  setting  for  the  proposed  project  is  as  shown  in  given  in  Table  1.4.  and environmental sensitivity map will be given in .Figure 1.4 

Table 1.4: Environment sensitivity of the project sites 

Sr. 

No. Areas  Yes/No

Name/Identity  (within  15  km.) 

Proposed  project  location 

boundary 

Areas  protected  under  international conventions,  national  or  local legislation  for  their  ecological, landscape,  cultural  or  other  related value 

Yes 

Phansad wild life Sanctuary is ~ 14.7 km away from Proposed Korlai Jetty and ~ 14.43 km away from existing Sanegaon facility. 

Areas which are important or sensitive for  ecological  reasons  ‐  Wetlands, watercourses  or  other  water  bodies, coastal  zone,  biospheres,  mountains, forests 

Yes Proposed Korlai Jetty project  lies in CRZ  IVB,  II  and  IB.and  Sanegaon facility lies in III.  

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  33  

Sr. 

No. Areas  Yes/No

Name/Identity  (within  15  km.) 

Proposed  project  location 

boundary 

Areas used by protected,  important or sensitive  species  of  flora  or  fauna  for breeding,  nesting,  foraging,  resting, over wintering, migration 

No  Not Applicable 

4  Inland, coastal, marine or underground waters 

Yes The proposed project will be in the Arabian sea  

5  State, National boundaries  No  Not applicable 

6 Routes  or  facilities  used  by  the  public for access to recreation or other tourist, pilgrim areas 

No  Not applicable 

7  Defense installations  No  Not applicable  

8  Densely populated or built‐up area  Yes  Korlai village ~ 1km away 

9 Areas occupied by sensitive man‐made land uses  (hospitals,  schools, places of worship, community facilities) 

Yes 

Korlai Church ~ 1.1km . from Korlai jetty 

There  are  several  schools and  health  centers  within 15 km of both project site 

10 

Areas  containing  important,  high quality  or  scarce  resources  (ground water  resources,  surface  resources, forestry, agriculture, fisheries, tourism, minerals) 

Yes 

Revdanda  fort  ~1.26  km  from proposed  Korlai Jetty and 14.04 km from sanegaon fort. 

Korlai fort ~. 1.2 km from proposed Korlai jetty. 

Korlai light house ~1.4 km 

11 

Areas already subjected to pollution or environmental  damage.  (those  where existing  legal  environmental  standards are exceeded) 

No  Not applicable 

12 

Areas  susceptible  to  natural  hazard which  could  cause  the  project  to present  environmental  problems (earthquakes,  subsidence,  landslides, 

No 

The project area is classified in Zone IV  as  per  NDMA,  Earthquake vulnerability map, having moderate seismic intensity to earthquake. 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  34  

Sr. 

No. Areas  Yes/No

Name/Identity  (within  15  km.) 

Proposed  project  location 

boundary 

erosion, flooding or extreme or adverse climatic conditions) 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy International Ltd. 

TEPL/ENV/CBS/2021‐05  35  

 

Figure 1.4 Environment sensitivity map

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  36 

Chapter2Project

Discription

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  37  

2. PROJECT DESCRIPTION 

2.1. GENERAL  

The  Indo  Energy  International  Limited  (IEIL)  proposed  development  of  Deep Water  Jetty Facility on Kundalika River, village Korlai, district Raigad, Maharashtra and capacity expansion at  existing  Inland  Water  Jetty  Facility,  on  Kundalika  River  at  village  Sanegaon,  district Raigad,Maharashtra.. The facility would be equipped with a 160/180/225 m wide dredged approachchannel, 500/550 m diameter turning circle, port basin of adequate depth and a 525 m berth with a mooring dolphin to the East. There will be total 4 numbers of berths for cargo transfer and one additional berth for mooring of the port crafts. 

In  addition,  the  existing  Sanegaon  facility  would  be  augmented  by  upgrading  of equipment,mechanization  of  storage  and  stacking,  loading,  unloading  arrangements,  for handling barges upto 4500 MT. Accordingly, the existing channel would have to be deepened (dredged) for handling these higher draught vessels.  The proposed port will be developed in 3  phases,  at  Korlai,  Phase  I‐9.25  MMT,  Phase  II‐  16.75  MMT,  Phase  III‐23.50  MMT,  at Sanegaon 5‐6 MMT (included in above projections).  

2.2. DESCRIPTION OF PROJECT SITE 

The proposed project site  is on Kundalika River, village Korlai, district Raigad, Maharashtra Revdanda Port lies in the estuary of Kundalika River The estuary entrance is protected by a peninsula on west side of entrance on which the Korlai Fort is situated. The Korlai Headland provides the necessary protection from southwesterly waves; however the Kundalika estuary remains  disturbed  due  to  the  westerly  waves..  The  proposed  facility  located  between geographical co‐ordinates of latitude 18° 32' 9.66"N, longitude 72° 54' 54.88"E and latitude 18° 32' 11.82"N, longitude 72° 55' 11.71"E, on the left bank of the Kundalika River, North East of ‘Rat Island’ 

 

Figure 2.1 Korlai Deepwater Jetty off the mouth of the Kundalika River 

Two major  ports  along  the West  coast  namely  JNPT  and Mumbai  Port  both Major  Ports arelocated about 52 and 48 km north respectively. In the South about 32 km away a Private port  islocated at Dighi  in  the Rajpuri creek.The only other deep‐water Port  in  the state of 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  38  

Maharashtra  is  located  about  145  km  south  at  Jaigarh,  In  Ratnagiri  District;  capable  of handling up to Cape Size vessels (180,000 DWT). 

2.2.1. EXISTING INFRASTRUCTURE  

Revdanda Port lies in the estuary of Kundalika River. The estuary entrance is protected by a peninsula on west side of entrance on which Korlai fort is situated. Though there is protection from south westerly waves, the westerly waves enter the Kundalika estuary entrance. The prevailing depth in berthing basin at port facility is 5 to 6 m from chart datum.  

IEIL operations are mostly concentrated in the Sanegaon area. The Sanegaon facility consists of a 200 m  long concrete  Jetty attached  to a 5 hectare storage area.   The barges operate between the anchorage and the existing barge handling facility at Sanegaon. Google image of facilities given in   

In view of the limited depth and presence of a sand bar at confluence of Kundalika River with ocean the port is used as lighterage port located at Sanegaon. Coal is transshipped in the self‐ propelled ISV barges of capacity 2500 ‐ 2800 DWT from mother vessel at anchorage. A 100 m wide, 7 nautical miles long entrance channel leads from anchorage point to JSW jetty for safe navigation of barges. At the confluence of Kundalika River with ocean a shallow sandbar has been formed, depth over sandbar is only 0.5 to 1.5 m and channel is maintained by regular dredging. Google image of facilities given in Figure 1.2 

A bridge exists on Kundalika River about 400 m east of existing JSW jetty. The bridge has nine (9) spans and the middle span has air drought of 9.6 m at highest high tide of +4.60 m. The clear horizontal span at soffit of beam is 38 m. Middle spans of Bridge on Kundalika River are shown in Figure 2.4. 

 

Figure 2.2 Existing JSW Revdanda port facility 

 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  39  

 

Figure 2.3 Existing Sanegaon Facility 

 

 

Figure 2.4 Middle Spans of Bridge on Kundalika River 

2.3. PROJECT DETAILS OF PROPOSED JETTY 

The proposed project is a conventional marine project requiring new jetty of 525 m length, with one mooring dolphin 25 m from the jetty on the eastern side of the berth. The location and alignment of the berth to be decided through model studies & reclamation of about 50 ha  for  foreshore  facilities  at  village  Korlai,  district  Raigad,  Maharashtra.  The  capacity expansion at Sanegaon  (lnland water  facility) will be by upgrading  the equipments and by operating  throughout  the year deploying  improved  types of barges of 4500 DWT size and dredging the inner channel for the same. The waterfront has a depth between 3 and 5 m and shallow region (‘0’ m contour) near the bank line. Hydrographic chart 2026 indicates that the 5 m contour is at about 2.5 km and 10 m contour at 5.0 km from the shore line. There is a channel for the existing lighterage operation. Hence the approach channel as required in the 

Existing Sanegaon Facility 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  40  

various phases shall be dredged. There will be 4 berths in all for cargo handling and one berth for mooring of Port Crafts.In addition to the approach channel, there will be a 500 m diameter turning circle and deeper port basin for allowing mother vessels of various sizes, starting from Handymax to Cape size, at all stages of the tide. There will be a barge loading berth on the side of the reclamation for meeting the requirements of the Sanegaon facility and others. 

2.3.1. SALIENT FEATURES OF PROPOSED PORT CONFIGURATION 

The Jetty is aligned to the predominant tidal current. The size of the berth 525 m x 46 m +2 approaches to the stack area. One 8 m x 8 m mooring dolphin on the eastern side of the jetty 125 acre (50 ha) reclaimed area for stacking and cargo handling will be provided. The port will be designed to handle Panamax sized vessels in the first phase and Cape size carriers in the final  phase.  No  breakwater  protection  is  required,  as  the  Korlai  head  land  provides  the required tranquility. 

 

Figure 2.5 Concept plan for development of jetty on Kundalika River 

A 17.5 km channel consisting of 23 million cum of dredging for Panamax Vessels and about 34 million cum for Cape Vessels would be required in the ultimate stage. Initial channel will be narrow and  limited to 160 m width with a draft of 11 m and  involve 11 million cum of dredging, which will be subsequently dredged to have navigable depth of around 15.60 m and further increased to 19.8 m in the final phase. The dredging spoils of the inner harbour would be used for reclamation of back up area. 

Table 2.1: Salient features of proposed jetty facility 

Type of Jetty  Open  coast,  Naturally  protected,  all  weather,  deep  draft  jetty  (no breakwaters)  

Existing features   Deep  embayment  with  shallow  area  near  shore,  for  creating reclaimed land, no trees, no mudflat, no mangroves, no creeklets 

Breakwater  No Breakwater  

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  41  

Berths and Mooring Structures  

One continuous berth of 525 m length with one mooring dolphins on the  East  side  of  the  berth  for  handling  bulk  cargo,  general  cargo, container, palletized, unitized and liquid cargo.  

Basin  Dredged uniform depth of (‐) 11 m initially, 15.6 m in the second and 19.8 m in the final phase. All depths are with respect to CD 

Channel  160/180/200 m wide, (‐) 11 m deep initially and thereafter 14.6 m deep, 17.5 km long  

Dredging   11 million cum for handymax vessels, 23 million cum for panamax vessels and 34 million cum for cape vessels About 1.5 million cum for inner channel from Korlai to Sanegaon for 4500 DWT barges 

Land/  Reclaimed Land 

Reclaimed  land  of  125  acres  (50  Ha),  to  accommodate  bulk  cargo stockyard, hard stands, silos, covered transit sheds, container stack yard , ICD,  railway yard etc. 

Navigation Aids   Channel markers with solar lanterns.  Flotilla   Tugs with firefighting capability, pilot launch, utility crafts.  Linkage   Last mile rail connectivity of ~ 40 km from Roha BG trunk line. 

Road Linkage   From Salav to Roha  Port Amenities   

Marine terminal, fire fighting arrangement, STPs, workshop, canteen, administrative offices, offices of stewards/CF agents, security, ICD & CFS.  

The Jetty will be provided with mobile harbour cranes in the first phase and with fixed ship unloaders in the final phase.  

The Equipments will discharge in to hoppers and through covered conveyors to the covered stockyard. 

Palletised cargo and containers would be handled using mobile harbour cranes and taken to the yard by tractor‐trailers. 

The cargo receipt and dispatch would be fully mechanised.  The barge loading system would be installed for emission free loading.   

Layout of proposed jetty is given in Figure 2.6

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy International Ltd. 

TEPL/ENV/CBS/2021‐05  42  

 

Figure 2.6Layou of proposed jetty

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  43  

2.4. PROJECT DETAILS OF SANEGAON FACILITY 

2.4.1. EXISTING FACILITY 

Indo  Energy  International  Limited  ha  existing  facility  for  coal  handling  at  Sanegaon  which  is operational  science  2009.  The Multipurpose  terminal  has  a  capacity  of  handling,  storing  and dispatching of about 1.0 million tonnes of Bulk cargo annually. The Terminal also has an open storage  space  of  60000  square  meters  away  from  population  centres  for  limiting  the environmental pollution due to fugitive emissions. Water sprinklers and other dust suppression system  are  located  strategically  for  pollution  prevention.  This  terminal  is  very  conveniently located at a distance of about 100 KM from New Bombay, about 10 km from the Roha railway Siding and about 12 KM from the nearest National Highway. The Multipurpose terminal has all the  advantages  to  make  it  highly  viable  location  for  the  various  Industries  located  in  the immediate as well as the entire State of Maharashtra & Karnataka to move their raw materials and thus reducing their production costs and provide cheaper products to the end user. Existing facility consist of jetty and coal storage and handling yard about 21 km upstream from proposed Korlai  facility.  The  Inland  Waterway  course  is  served  by  barges  of  2500  DWT  (draft  ‐2.5  m CD).Google image of existing facility is shown in  

 

Figure 2.7 Existing Sanegaon facility 

2.4.2. NEED OF EXPANSION AT SANEGAON FACILITY 

Handling of Coal at the anchorage is unreliable as is non‐operational for about 4 months during southwest monsoon. 

Depth (draught) available in the River is tide assisted. 

2.4.3. IMPROVEMENTS PROPOSED FOR AUGMENTING CAPACITY 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  44  

Intervention would involve streamlining the existing operation using the existing resources and adding only minimal equipment and facilities as stated below: also layout of Sanegaon facility is given in Figure 2.8 

Handling wharf: 200 m  The handling equipment will be replaced with new similar kind machines – Sennebogen 

Material  handler or similar type  The stack yards will be streamlined, only 3 stacks with a capacity of 240,000 MT will be 

used   Stacker cum Reclaimer in phases shall be deployed for supplying to the truck loader or to 

the power plant.  Dredging of channel from Korlai to Sanegaon to 3.1 m CD.   Use of  4500 DWT barges  All year round operations as mother vessels will discharge at Korlai Jetty. 

Table 2.2 Existing and Projected Traffic at the Sanegaon Barge facility 

Sr.No  Cargo  Handled  Handled  Handled  Expected  Projected 2012‐2013 Tonne 

2013‐2014 Tonne

2014‐2015 Tonne 

2015‐2016 Tonne 

2016‐2017 Tonne 

1  Coal  740542  522881  800000  1500000  1500000 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy International Ltd. 

TEPL/ENV/CBS/2021‐05  45 

 

Figure 2.8Layout for Sanegaon facility

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  46  

2.5. PRESENT OPRATION 

IEIL is presently engaged in transportation and trading of coal using lighterage facility at Sanegaon, located on the right bank of the Kundalika River, about 50 km south of Mumbai by sea and about 130 km by road as shown in .Figure 2.9

 

Figure 2.9 Location of present unloading facility at Sanegaon on the West Coast of    India 

2.6. TRAFFIC STUDY & DEMAND ASSESSMENT 

2.6.1. METHODOLOGY 

The  methodology  adopted  for  the  traffic  study  and  demand  assessment  is  presented  in the  Figure 2.10 below and all the steps carried out are explained below. 

 

Figure 2.10Methodology adopted for the traffic study and demand 

2.6.2. FORECAST MODEL 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  47  

Current port traffic in India and Maharashtra  The  statistics  of  the  traffic  handled  at  the  Indian  Major  and  Minor  Ports  from 1996‐97 to the present were obtained.  

Forecast of future port traffic  First, a series of macroeconomic  figures  that  reflect  the  economic  and  social growth  of  the  country  (Gross  Domestic  Product  GDP,  Population,  and  Per Capita Income –PCI) were analyzed over the period 1996‐97 to present. The growth estimates of these parameters until 2040‐41 was also obtained. Secondly, an analysis of the relation between these macroeconomic variables and the port  traffic  from 1996‐97  to  the present was  carried out, obtaining well  correlated  linear regressions. Finally, using the linear regressions line and the macroeconomic variables projection estimates for the next 30 years, the port traffic projection until 2040 was estimated.   

This study was performed both  for  India and Maharashtra State. The traffic projection based in correlation with PCI for Karnataka State means there will be cumulative annual traffic growth of 7.78 %.  

Selection of the type of cargo to be moved through Korlai Port.   Current total traffic of the cargo.   For these cargos the current total traffic were obtained.   Future total traffic of the cargo.  

The  future  projection  of  the  iron  ore  requirements,  coal  import  and  steel  production  were         obtained from various information sources. The projected port traffic forecast also was obtained in  addition  the  miscellaneous  cargoes  such  as  Fertilizer,  Edible  oil  and  such  other  cargoes requiring distribution in the hinterland. 

2.6.3. TOTAL TRAFFIC FOR THE PORT 

The location advantage offered by the port could act as a viable alternative for various existing as well as upcoming industries.   

Direct berthing of mother vessels would bring down the logistics cost and would imbibe more efficiency by doing away from the anchorage handling in the region including the Mumbai Port. 

Inland water connectivity to the port and the handling facility upstream provides greater penetration to the hinterland. 

Readymade rail connectivity provides connectivity unparalleled in the region. Hence with the requisite efficiency the following total traffic for the facility could be realistically predicted. 

Figure 2.11 Total Traffic for the Proposed Facility at Revdanda 

Traffic  Year 5 Year 10 Year 15 Year 25  Export/Import

Coal  5.00  10.00 12.00 12.00 Import IBRM  1.0  2.0  2.5  3.0  Import Lime Stone/Dolomite   0.5  1.0 1.5 1.5 Import Iron and Steel  0.5  1.0  1.5  2.5  Export Bauxite  0.25  05  0.5  0.5  Import 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  48  

Cement   0.5  0.5 0.5 1.0 Import Fertilizer   0.5  0.50  1.0  1.0  Import/Export Containers   0.5  0.5  0.5  1.0  Import/Export Liquid  Cargos  (Edible Oil)  

0.25  0.5  0.5  1.0  Import/Export 

Molasses   0.25  0.25 0.25 0.5 Export Transshipment Cargo  2.0  3.0  5.0  5.0  Transshipment Total   9.25  16.75  20.75  23.5   

 

2.7. ENGINEERING SURVEYS AND INVESTIGATIONS 

The field investigation forms an important component of the port development process. It must be recognized that the quality of output is proportionate to the quality of input and as such more the availability of quality data more accurate would be the results. In the proposed proposal, the measure cost component is expected from dredging and the berth construction. Hence  it was considered necessary to carry out additional boreholes.  

2.7.1. OBJECTIVE OF WORK 

The field investigation forms an important component of the port development process. It must be recognized that the quality of output is proportionate to the quality of input and as such more the availability of quality data more accurate would be the results. In the proposed proposal, the measure cost component is expected from dredging and the berth construction. Hence  it was considered necessary to carry out additional boreholes. 

2.7.2. LABORATORY TESTING 

Selected soil samples, collected during boring/drilling of boreholes were subjected to laboratory tests to determine the index and engineering characteristics as specified. The classification, index property, NMC, specific gravity, density, and chemical tests were carried out on the soil samples. 

Following tests were performed 

1.  Particle size distribution. 

2.  Sedimentation/ Hydrometer analysis. 

3.  Alterberg limits. 

4.  Particle density/ Specific gravity. 

2.7.3. SOIL CONDITION 

Sub‐Seabed Condition: The subsea conditions at  the proposed  locations of  the various structures are investigated.  

Navigation  Channel:  The  area  for  the  proposed Navigation  Channel  is  investigated  by drilling  Seven  (7)  boreholes  MBH‐53  to  MBH‐59.  The  Sub  Surface  stratigraphy  is graphically depicted in Plate 3 thru Section A‐A.  

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  49  

Jetty:  Bore whole  no. MBH‐60  was  located  near  the  proposed  jetty.  The  sub  surface comprises top layer of Medium dense SAND up to ‐14.40 m CD. The SPT (“N”) value varies from 11 to 22. This is followed by a 1.0 m thick layer of soft to firm CLAY, underlain by Residual Soil (Grade VI) followed by bedrock that is basalt. 

2.7.4. FOUNDATION RECOMMENDATION 

The subsea study indicates that, the sub soil mainly comprises of medium dense underlain by soft to  firm  clay.  As  the  sandy  soils  encountered  are  of Medium Dense  consistency  they will  not provide enough end bearing capacity to the piles required for the load coming from the heavy superstructure. Similarly, the Soft to Stiff clay layers encountered are not of enough thickness to provide the required skin resistance. The piles are to be terminated in rock at the level found at the particular location. The Piles installed will be end‐bearing piles socketed into rock. 

2.7.5. DREDGEABILITY 

Dredgeability is defined as the ease with which the material can be dredge. The channel locations are investigated by drilling MBH‐53 thru MBH‐59. The subsurface stratigraphy as revealed from the soil investigations indicates soft material up to ‐14.70 m CD in the channel, dredgeable by suction dredgers. However, with little deftness, the Channel could be suitably aligned to be ready for Panamax vessels 

2.8. DEVELOPMENT PLANS FOR PROPOSED JETTY 

2.8.1. DEMARCATION OF PORT BASIN 

According to the available  land  for  the onshore development,  the port basin  is  located at the widest part of the river, i.e. at the river mouth.  The approach channel, the turning area, the port basin etc. would be created at this location, for the largest possible ship. 

 

Figure 2.12 Location of the port basin 

2.9. NAVIGATION CHANNEL 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  50  

The  capital  objective  of  navigation  channel  is  to  define  the  geometric  characteristics  of  the approach      waterway      for      the      new      port      (dimensions      and      alignment)      and      the navigational requirements. 

Table 2.3 Design vessels for the Proposed Jetty/Port 

Type  DWT  LOA  B  D 

Bulk Carriers  105,000  270.0 m  43.5 m  14.0 m 

Multipurpose  Carriers  80,000 240.0 m 36.5 m  14.0 m

Crude Oil Tankers  85,000  260.0 m  40.0 m  14.0 m 

Liquid Gas Carriers  60,000  265.0 m  42.2 m  13.5 m 

Container ships  80,000 290.0 m 42.5 m  14.0 m

Ro‐Ro vessels  50,000  287.0 m  32.2 m  12.4 m 

General cargo vessels  40,000 209.0 m 30.0 m  12.5 m

Car carriers  30,000  193.0 m  32.2 m  11.7 m 

Ferries  25,000 197.0 m 30.6 m  7.1 m 

Passenger cruise ships  80,000 (GT)  272.0 m  35.0 m  8.0 m 

Maximum sizes  105,000  290.0 m  43.5 m  14.0 m 

 

The highlighted ships (bulk carriers and container ships) represent the greatest ships dimensions and hence could be considered as the design dimensions for the port components. It must also be recognized; that though the traffic studies indicate that this  facility  is  for  predominantly handling  of  coal,  provision  for  container  handling may not be completely out of place, since, high  value  CR  coils  and  value  added  steel products are general ly   taken  in containers  for export.    Hence  it  was  considered  prudent  to  plan  for  the  turning  and  accommodation  of container vessel as well, which could be implemented with very little incremental cost. When defining the navigation channel, the beam of the vessel can be considered as the limiting factor. Therefore we can affirm that the bulk carriers are the most difficult ship for navigation at this port. 

2.9.1. ALIGNMENT 

The alignment of the navigation channel, especially at open sea areas, is mainly considered by the meteorological  conditions  that  can  affect  the maneuverability  conditions  of  the  vessels sailing  through  the  channel.  The   principal   meteorological   agents   that   affect   the   ships  maneuverability  are  (from most  important  to  least  important)  the  wind,  the  currents  and  the  waves.    It  is  not  always  easy  to  fully  avoid  these  agents,  which  when  acting  on  the  ship transversally,  increases  the  effect  over  the  maneuverability  of  vessels.  The  effect considerably increases when angles between the ship’s axis and the agent –wind, current or wave, is over 45 º.  

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  51  

The main  currents  at  the  area  are  produced by  the  river  discharge,  the  tides  and the  long shore  movements.  The  discharges  from  the  river  are  approximately  NNW,  and  that  is conditioned mainly by the geometry of the river mouth.   

Obviously it is not possible to obtain an alignment such that all the wind directions attack the vessels longitudinally (i.e. with an angle less than 45º), but the transversal wind directions can be reduced.  

Considering  all  the  factors  mentioned  above  the  alignment  of  the  outer  channel  has been planned along 070˚ ‐ 250˚. The navigation channel is shown on navigation chart 2026 in Figure 2.13 

 

Figure 2.13 Navigation channel plan – Navigation chart #2026 (Extract) 

2.9.2. NAVIGATIONAL REQUIREMENTS 

In this facility floating lateral markers (buoys) are proposed to be used to signal its navigation channel, with a longitudinal distance between markers of 2,000 meters. These  buoys  can  be staggered  on  either  side  of  the  channel,  which  will  reduce  the number of buoys. 

2.9.3.  MODEL BATHYMETRY 

The overall shape of Kundalika River is funnel shaped with general depths varying between 2 m and 4 m (B.C.D). The sites of the jetty structure are proposed in Kundalika River and are on the left  (south) bank near village Salav on  the west coast of  India. Bathymetry at  the project  site between Arabian Sea and Kundalika River indicates that the depths are shallow. For the study under considerations following bathymetry charts were used: 

1. Navigation chart no. 2026 for depths – 19m contour to ‐4 m contour 

2. Hydrographic survey charts of MMB in 2005 extending deep in to the river up to the HTL. 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  52  

 

Figure 2.14 Bathymetry of the Kundalika River and Arabian Sea for computation 

2.9.4. HYDRODYNAMIC MODEL 

The  study was carried out  in  a  zonal model,  so  that  local hydrodynamics  could be accurately simulated and computed bereft of any boundary effects. The initial simulation was carried out for the existing condition and the model would be calibrated utilizing the site collected data. The calibrated model then would be used for simulating the effects after the developments proposed. 

The overall shape of Kundalika River is funnel shaped with general depths varying between 2 m and 4 m (B.C.D). The sites of the jetty structure are proposed in Kundalika River and are on the left  (south) bank near village Korlai on the west coast of  India. Bathymetry at the project site between Arabian Sea and Kundalika River indicates that the depths are shallow. For the study under considerations following data charts were used to create the MIKE 21 Bathymetry shown in.Figure  2.15  and  Figure  2.16  Project  was  crafted  on  the  bases  of  results  of  hydrodynamic modelling such as there would be no flow concentration/or stagnation, morphology of the region would not change and would not lead to sedimentation or erosion. 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  53  

 

Figure 2.15 Flow concentration/or stagnation 

 

 

Figure 2.16 Bathymetry of the Kundalika River and Arabian Sea for computation (Close up) 

2.9.5. TURNING CIRCLE IN THE BASIN 

In the case of the proposed Port the Turning Circle would be located upstream in the North West direction, behind the Korlai Headland. It has been endevoured to reduce the capital as well as the maintenance dredging of the Turning Circle area. Further, the location is selected so as to have  zero hard material  dredging  atleast  in  the  first  phase. Never  the  less  the  turning  circle dimensiosn  will  be  optimum  considering  transquil  environment  it  is  proposed  be  located. Therefore, the assistance of tugs has been considered and a diameter of 2 times the length of 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  54  

the  largest  ship has been applied.  The design vessel  for  the port  as per Technical  Feasibility Report  (TFR)  is 290 m  long. Thus, a  turning circle with a diameter of 500 m  (1.7 L) has been considered based on the PINAC recommendations. The  turning  circles  will  be  dredged  to  ‐16  m  CD,  which  is similar to the depths provided in the inner channel. 

2.9.6. BERTHS 

Taking  into  account  the  results  of  the  traffic  study  performed,  berth  alignment  has been established. Berths are aligned to the predominant directions of tidal current for a length of 525 m, which is 115o to the true North.  There will be a mooring dolphin on the eastern side of Jetty, so  that  two  Panamax  vessels  could  be  accommodated with  deft  and  one  Panamax  and  one Handymax with ease. 

2.9.7. BERTH REQUIREMENTS  

The computations for ship calls, berth days, and berth requirements are given in Table 2.4, Table 2.5 and Table 2.62.11 below  for  Phase  I  (5  Years),  Phase  II  (10  Years)  and  Phase  III  (30  Years) scenario. 

Port projects have a long gestation period as the cargo build up is gradual and time consuming. Hence determining the design vessel for a new port would be dynamic and would depend on the market forces. In the initial years of the development, the port would be using vessels of lower capacity which would gradually increase to the envisaged sizes of Panamx Vessels and beyond.   However, for the computations of Table 2.4 valid for the first phase operations, 105,000 DWT vessel is considered as the design vessel. However, due to the mix in the population of the ship visiting the port, a lower average parcel size of 80000 is considered.  

Till the end of year 10, i.e. the end of Phase – II, the same vessel size is considered. However, in the later stages the vessel size would increase to 180,000 DWT based on demand.  

Similarly, the equipment build up at the berth as well as the stack yard would be gradual and based on the need and efficiency desired. Based on the above principle,  the operation would commence with 2 MHCs at the berth, which would be gradually built up to gantry unloaders in phase II. Similarly upgradation of the stack yard equipment would be planned in phases.  

In Phase  II  the vessel size  is kept similar while the Jetty  is now equipped with higher capacity Gantry Cranes. 2 no. berths would be sufficient for the projected 17 MTPA cargo. In Phase III, Cape size vessels with average size of 180,000 DWT would be expected to handle the bulk cargo. The corresponding size of the Lime Stone and Bauxite vessels also has been increased. However, for this case two berths may not be sufficient since the general cargo handling takes up more time and keeps the berth more occupied, due to two main reasons‐ 

1. Lower parcel size and 2. Lower handling rate 

It must also be recognized that the additional hours indicated in the table will comprise of the following:

1. Berthing time      : 2 Hours 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  55  

2. Berth readiness for Handling  : 1 hours 3. Un‐berthing time      : 2 Hours 

2.9.8. WIDTH OF THE BERTH 

The width of  the berth  is  calculated  two ways, besides  the  functional  requirements. The  first being the width necessitated by accommodation of a riveted slope under the berth and second the crane rails for special purpose cargos. In the first type berths are generally shore connected wharfs and have contiguous  land area behind the berth.  In  this case the berth would have to accommodate a sloping apron below the deck, so that the earth retained remains stable. In the second  type,  the  unloader’s  requirement  dictates  the  width.  For  example,  for  efficient functioning of  the container unloading  crane,  the  standard  crane  rails on  the  Jetty  are about 30.48 m apart.  This would make  the width of  the berth about  50 m  considering  the  forward distance and the areas for keeping the hatch covers. In the present case, since the cargo would be mostly Bulk cargoes, the Crane rails shall be about 22 m apart. Considering the distance of 3.5 m between the forward crane and the Jetty front line, and a transport lane of 8 m, the total width = 22+3.5+8 = 33.5. Considering the distance between the center of the back row pile and the edge of the jetty as 2 m, total width = 35.5 say 36 m. Cross section of Approach trestle is given in Figure 2.6 and Section of the Berth facility Figure 2.7. 

 

Figure 2.17 Cross section of Approach trestle 

 

 

 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  56  

 

Figure 2.18 Section of the Berth facility 

 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy International Ltd. 

TEPL/ENV/CBS/2021‐05  57 

Table 2.4 Berth Requirements in Phase –I 

Cargo  Traffic  Avg. 

Parcel 

Size 

Ship 

Calls 

Avg. 

Handling 

Rates 

Handling

Rates  at

70 % 

efficiency 

Ship Time at Berth Working 

Hours  / 

Day 

Berth

Days 

per  S

hip

Required

Berth 

Time 

Berth Available

Berth 

Time 

Berth

Occupancy 

No. Of

Berths 

Service Additional Total

Phase ‐I   Tons  Tons  No.  TPHs Hrs Hrs Hrs Hrs  Days Days No. Days No. No.Coal  3000000  80000  37.5  2000 1400 57 5 62.0 24  1.4 97.1 1 330 0.7 0.42

Iron Ore  1000000  80000  12.5  3000 2100 38.1 5 43.1 24  1.27 22.4 1 330 0.7 0.10

Lime Stone 

500000  45000  11.1  2000 1400 32.1 5 37.1 24  1.55 17.2 1 330 0.7 0.07

Bauxite  500000  45000  11.1  2000 1400 32.1 5 37.1 24  1.55 17.2 1 330 0.7 0.07

Fertilizer  1000000  45000  22.2  1200 840 53.6 5 58.6 24  2.44 54.2 1 330 0.7 0.23

Iron  S crap 

250000  30000  8.3  800 560 53.6 5 58.6 24  2.44 20.3 1 330 0.7 0.09

HBI Chips 

250000  30000  8.3  800 560 53.6 5 58.6 24  2.44 20.3 1 330 0.7 0.09

Iron  &  S teel 

  500000  25000  20.0  800 560 44.6 5 49.6 24  2.07 41.4 1 330 0.7 0.18

Other  500000  30000  16.7  800 560 53.6 5 58.6 24  2.4 40.7 1 330 0.7 0.18

Total  750000

  147.8  418 463   330.9 1.43

Table 2.5 Berth Requirements in Phase – II  

Traffic  Avg. 

Parcel Size 

Ship 

Calls Avg. 

Handling 

Rates 

Handling

Rates  at

70 % efficiency

Ship Time at Berth Working 

Hours/Day Berth

Days 

per  S 

hip

Required

Berth 

Time 

Berth Available

Berth 

Time 

Berth

Occupancy No of Berths 

Services Additional  Total

Phase‐II  Tons  Tons  No.  TPHs Hrs Hrs Hrs Hrs  Days Days No. Days No. No.

Coal  9000000  80000  112.5  4000 2800 29.0 5 34.0 24 1.40 157.4 1 330 0.7 0.68

Iron Ore  2000000  80000  25.0  5000 3500 22.9 5 27.9 24 1.16 29.0 1 330 0.7 0.13

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy International Ltd. 

TEPL/ENV/CBS/2021‐05  58 

Lime Stone 

1000000  45000  22.2  4000 2800 16.1 5 21.1 24 0.88 19.5 1 330 0.7 0.08

Bauxite  1000000  45000  22.2  4000 2800 16.1 5 21.1 24 0.88 19.5 1 330 0.7 0.08

Fertilizer  1000000  45000  22.2  1200 840 53.6 5 58.6 24 2.44 54.2 1 330 0.7 0.23

Iron S crap 500000  30000  16.7  1200 840 35.7 5 40.7 24 1.70 28.3 1 330 0.7 0.12

HBI Chips  500000  30000  16.7  1200 840 35.7 5 40.7 24 1.70 28.3 1 330 0.7 0.12

Iron &S teel 

1000000  25000  40.0  1200 840 29.8 5 34.8 24 1.45 57.9 1 330 0.7 0.25

Other  1000000  30000  33.3  1200 840 35.7 5 40.7 24 1.70 56.5 1 330 0.7 0.24

Total  17000000  310.8  274 319 450.7 1.95

Table 2.6 Berth Requirements in Phase – III 

Cargo  Traffic Avg. Parcel Size 

Ship Calls 

Avg. Handling Rates 

Avg. Handling Rates  at70% efficiency 

Ship Time at BerthWorking Hours  / Day 

Berth Days per Ship 

Required Berth Time

Berth Available Berth Time 

Berth Occupancy 

No. Of Berths Service  Additional  Total 

Phase‐III  Tons  Tons  No.  TPHs  Hrs  Hrs  Hrs  Hrs  Days  Days  No.  Days  No  No. 

Coal   11000000  1800000  6.7  4000  2800  643  5  648  24  27.0  165.0  1  330  0.7  0.71 

Iron Ore   2000000  1800000  1.1  5000  3500  514.3  5  519.3  24  21.64  24.0  1  330  0.7  0.10 

Lime Stone  2000000  100000  20.0  4000  2800  35.7  5  40.7  24  1.70  33.9  1  330  0.7  0.15 

Bauxite   2000000  100000  20.0  4000  2800  35.7  5  40.7  24  1.70  33.9  1  330  0.7  0.15 

Fertilizer   2000000  80000  25.0  1200  840  95.2  5  100.2  24  4.18  104.4  1  330  0.7  0.45 

Iron Scrap  500000  50000  10.0  1200  840  59.5  5  64.5  24  2.69  26.9  1  330  0.7  0.12 

HBI Chips  500000  50000  10.0  1200  840  59.5  5  64.5  24  2.69  26.9  1  330  0.7  0.12 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy International Ltd. 

TEPL/ENV/CBS/2021‐05  59 

Iron &Steel  1000000  50000  20.0  1200  840  59.5  5  64.5  24  2.69  53.8  1  330  0.7  0.23 

Other   1000000  50000  20.0  1200  840  59.5  5  64.5  27  2.70  53.8  1  330  0.7  0.23 

Total  22000000  132.2  1562  1607  522.6  2.26 

 

 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  60 

Orientation 

The orientation of the berth inside an estuary with tidal currents driving the flow hydrodynamics, the  orientation  of  the  berth  alignments  are  in  general  guided  by  the  flow  vectors.  Since  the predominant current direction is 115o ‐ 295o,   the  Jetty  shall  be  aligned  to  the  same  as shown in Figure 2.5.  

2.10. ON SHORE LAYOUT & REQUIREMENTS 

2.10.1. UTILIZATION OF LAND RECLAIMED FOR THE PROJECT 

According  to  the  results  of  the  traffic  study,  for  the  design  of  the  port  of  onshore  layout two types of terminals have been considered:   

Dry Bulk Terminal: For  the design of  this  terminal, both coal  import and export has  been taken into account with independent handling of operations for both. Thus two circuits have been defined: one for export and other for coal import.  

Multipurpose Terminal: The steel products export circuit has been considered. The northern area is defined for possible future extension.  

 

 

Figure 2.19Flow diagram for coal handling 

 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  61 

2.10.2. STORAGE AREA. 

The  maximum  area  required  for  the  coal  stacking  would  be  10  ha  at  the  last  phase  of development.  

 

Figure 2.20 Section of the Final Phase Stock yard for coal   

2.10.3. OPERATION AREA AT THE BERTH 

The  berth  operation  area  would  have  the  facility  to  receive  as  well  as  load  the barges/ships  as  the  case  may  be.  All the conveyor belts will have a capacity of 5000 tonnes/h in stacking mode and 3000 tonnes/h in the reclaiming mode. Average  unloading  capacity  of  the  unloaders  is 2500  tonnes/h  and  average throughput of each ship/barge loader must be at least 1,500 tph. Two  ship  loaders  at  each  berth  position  with  adequate  capacity  have  been chosen instead of only one higher capacity ship loader because:   

i) In   case   of   maintenance   or   breakdown   of   one   ship   loader   the operation  at the  berth  position  can  continue  (although with  lower throughput)  

ii) The width of this operation area is 46 m. Two bulk carriers can be unloaded with coal simultaneously, whenever the berth no 2 is not occupied by the coal loading operation.  

 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  62 

   

Figure 2.21 Operation at the berth 

2.10.4. SHIP UNLOADING 

Since the Berth No.1 will be fully occupied with handling of coal, Berth no 2 will have to be made equipped for the other cargo handling including fertilizers.  A ship unloader‐cum‐loader will be an ideal option rather than having two separate machines i.e.  ship unloader  (for  import)  and ship  loader    (for  export).  The  ship  unloader  capacity  is  proposed  as  2000  TPH  (rated) standardizing with the existing unloader capacity with a view to provide flexibility and spare time availability for handling other cargo at this berth. The occupancy of ship unloader for fertilizers is analysed below in Table 2.7  

Table 2.7 Occupancy of the ship unloader fertilizer handling for 

Throughput  1.5 MTPA Ship Size (Avg.)  50,000DWT Unloader Capacity (Rated)  2000 TPH Unloading Efficiency  55% Berth     time     required     for     handling     the throughput  ~45 days in a year 

 

2.10.5. PROPOSED SYSTEM 

One combined ship unloader‐cum‐loader having an unloading capacity (rated) of 2000 TPH will be installed on Berth no 2 along with a new conveyor stream (parallel to the existing stream). The new receiving conveyors up to and within the storage will be rated for 2000 TPH having belt width as 1400 mm. The storage conveyor will be elevated and provided with an overhead tripper to facilitate stacking in storage shed of the fertilizers received from the berth (ref. Figure 2.22).  

 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  63 

 

Figure 2.22 Storage Shed for fertilizers 

The  storage  will  be  in  a  covered  shed  having  a  capacity  of  about  100,000  T.  The  reclaimed  conveyor  in  the  shed  will  be  rated  at  about  625  TPH  and  will be equipped with four fixed hoppers provided with 175 TPH vibrating feeders. Payloaders  (3  cu. m. bucket  capacity) will  be used  for  loading  the  fertilizers from  the  storage  shed  into  the  hoppers.  Conveyor  streams, from storage  shed to wagon (bag) loading will be common for handling lime stone, bauxite and fertilizers for reasons explained earlier. Since the materials are not compatible, cleaning system will  be  provided  at  the  transfer  points  to  clean  the  belt.  The  cleaning  system would mostly comprise of a washing system and a drying system. For example, when fertilizer is handled after the coal in the same conveying system, the belt needs to be washed with water. After washing the belt must be dried up using compressed air. However, many times washing is not required when  coal  is handled after  fertilizer,  unless  the coal  is used  in  a blast  furnace. Hoods will  be provided on the belt conveyors while their supporting gallery will be open type.  Bagging station will comprise of a continuous elevated hopper having  six  outlets,  each  equipped  with  two bagging  and  stitching  machines, thus  having  12  Nos.  bagging  machines  in  the  initial  stage, which subsequently could be duplicated in case the need arises.  

Material received from the storage will be discharged into the elevated hoppers via a shuttle conveyor Bagging Station, which is planned adjoining and in the middle of the wagon loading platform about 720 m long x 15 m wide x 1.1 m high.  Bags from the bagging stations will be brought to the platform by the bag conveyors with mobile discharge chute to facilitate discharge bags onto the platform. Bags are planned to be loaded manually into the wagons.  

 

 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  64 

 

Figure 2.23 Truck and Rake loading shed for fertilizers 

2.10.6. EDIBLE OIL 

Unloading and Storage 

Edible Oil will arrive in tankers and is proposed to be handled at the common Berth 2. Generally the tanker vessels are equipped with their own pumps to discharge  the  load  and  are  so  rated  to  complete  the  unloading  operations within  18  hours  having  working  pressure  ranging  from  8  to  10  kg/sq.cm., which  can  pump  the  liquid  at  the  required rate  to  the  storage tank  located about 2‐2.5 km away from the berth and about 18 m high. With the unloading rate of about 600 TPH, the tanker with 10,000 T parcel size will have a turn‐ around time of about 24 hours. Thus the edible oil import will occupy the berth for 20 days in a year.   

The storage preferably is located in an area such that the edible oil unloaded from the tanker can directly  be  pumped  into  the  storage  tank  using  ship’s pumps and also near the dispatch area as far as possible. However, due to elevation difference between the berth and the dispatch area (where railway tracks will be located), it will be necessary to provide a boosting station on the receiving line considering that storage tank farm is located near the wagon loading station (edible  oil).  Tank  farm  planned  near  the  dispatch  area  (located  in  the  area  having  higher elevation)  will  provide  better  control  over  the  wagon/truck  loading  operations.  Storage comprising  of  3  x  10,000  T  tank  is proposed.   

Unloading from ship is planned by use of flexible hoses (connection between ship’s manifold and the pipeline on the berth), (ref. Figure 2.24) as compared to conventional mobile unloading arm (ref. Figure 2.25) mainly due  to economic consideration. P&I Diagram is shown in Figure 2.26. 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  65 

 

Figure 2.24 Unloading of ship by flexible hose 

 

Figure 2.25 Unloading of ship by unloading arms 

 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy International Ltd. 

TEPL/ENV/CBS/2021‐05  66 

 

Figure 2.26 The P&I diagram for the Liquid cargo handling 

 

 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy International Ltd. 

TEPL/ENV/CBS/2021‐05  67 

 

 

Figure 2.27 Truck/Wagon Loading System for POL/OIL 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  68 

2.10.7. PROPOSED SYSTEM (EDIBLE OIL) 

As  explained  above,  it  is  proposed  to  use  flexible  hose  for  unloading  the  liquid from the ship by operating the ship’s pumps at 600 TPH. The receiving pipeline, 300 mm diameter, from berth to storage will be supported from the conveyor gallery (fertilizer/coal) as far as possible. Since the ship’s pumps are expected to be inadequate to pump the liquid into storage tanks located in  the  area  having  elevation  about  30 m more  above  the  berth  elevation,  it  is  proposed  to provide the  receiving  pipeline  (300  mm  dia)  with  a  booster  pump  to  do  the  needful. Tank farm will comprise 3 tanks of 10,000 T capacity having 25 m dia and 15 m high.  

2.10.8. BAUXITE 

Throughput = 0.5 to 1 MTPA (Export); receipt in Trucks.  Since  the  cargo  arrival  is  by  trucks,  the  unloading  station  shall  ideally  be located as close to the stockyard area as far as possible to reduce the transportation  distance  between  the  two  areas,  i.e.  unloading  station  and  the stockyard.   The  material   will   be  stacked   in   an   open  stockyard  having   capacity   of   about 67,000  tonnes. Stockyard is planned North East  of berth with a view to minimise the conveying distance between the stockyard and the berth.  

2.10.9. RECLAIMING AND SHIP LOADING 

Berth 2 will remain occupied for Import Cargo (Fertilizers, Edible Oil) for a duration  of  60  (45 + 15)  days  with  155  days  as  spare  time  available, considering 65% berth occupancy, for handling other cargo like the one under consideration,  i.e.  Bauxite.  With  ship  loading  rate  of 2000  TPH  and  system efficiency as 65% (on conservative side), a ship of 50,000 DWT could be loaded in about 39 hours. Analysis of data appearing in the Drewry reveal reporting of only  14  fixtures  of  Bauxite  during  Jan  to  Nov  2009  with  ship  loading  rate  of 24,000  Tonnes  per  day  for  ships  ranging  from  50,000  to  60,000  DWT.  With 1500  TPH,  ship  loading  rate  considered  in   the   facility,   average   loading   rate   of 24,000 – 25,000 Tonnes per day  is achievable. With quantum of import and export cargo proposed to be handled at berth 2, total berth utilization time will thus be about 120 days per annum,  i.e. 60 days  for bauxite and 60  for other cargo.   

 

Figure 2.28 Loading arrangements at the Bauxite Yard 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  69 

2.10.10. SYSTEM DESCRIPTION 

Belt conveyors (same as the one used for the Bauxite) from the berth transport the cargo to the stockyard and the same will be stacked via an overhead tripper provided with shuttle conveyor. The discharge  from  the  shuttle  conveyor will  be through a telescopic chute to reduce the dust emission.   Dumpers  with  about  15  T  payloads  will  be  loaded  in  loading  hoppers  provided with vibrating feeders each rated at 125 TPH. With two hoppers, two dumpers can be unloaded simultaneously.   Throughput = 0.75 MTPA (Export) to 1.5 MTPA; receipt  in Trailers and rakes.   Since the cargo arrival  is by trailers and rakes, the unloading station shall  ideally be located as close to the stockyard area as far as possible to reduce the transportation distance between the two areas i.e. unloading station and the stockyard.  

2.10.11. RECLAIMING AND SHIP LOADING 

Berth 2  is proposed to be used for handling of this cargo. The average parcel  load of the ship is about 50,000 T. Hence there will be about 30 ship calls a year. The loading shall be carried out through MHCs, with an average handling rate of 1400 T at 70% efficiency. 

Hence the loading time would be around 44 hours, which is about 2.2 days per shipload. Hence the berth would be occupied for 66 days. However, by using two MHCs would reduce the berth occupancy to 33 days. Hence the total number of utilisation of the berth no. 2 is for 181 + 33 = 214 days with 20 days spare with berth occupancy of 70%, which is allowed for 2 berths.  

2.11. STACKING AREA COMPUTATION 

The area required for coal stacking is about 10 ha. The total storage required for all the cargos and the associated facilities as in the Feasibility document is given in the Table below.  

Table 2.8 Storage area requirements for various phases 

Sr.No Particulars First Phase Ultimate Phase

3.75* 3.75* 2 Dry Bulk Stackyard Area

Coal Stackyard 7 10 IRMB Stackyard  0.75 1.5 Limestone Stackyard 0.7 1.2 Bauxoite Stackyard  0.5 0.5

3 Container Stackyard area  1.5 2.5 4 General Cargo  (Cement + Fertilizer + General Bulk, 

etc.)  1.4 5.0

5 Liquid Bulk Cargo 0 2 6 Iron and Steel products  0.5 1.0 7 Wagon Loading and Engine Escape Line facilities  00 10.0 8 Others 

Conveyor Corridor  0.5 1.0 Pipelines  0 1.0

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  70 

Truck terminal  0.5 2 Sewage Treatment Plant  0.5 1 Common User Facility  0 2 Misc. Port related facilities 0 2

Total  15.4 43.2 Greenbelt and others (Roads) @ 25% of total  19.0 54.0**In the above table the computations have considered the following;  

1. Specific gravity of Iron Ore : 2.5 tonnes/m3  2. Specific gravity of Lime Stone  : 1.0 tonnes/m3  3. Specific gravity of Bauxite    : 1.2 tonnes/m3  4. The angle of repose of Iron  : 40O 5. The angle of repose of other cargo  : 30O  Since  the  first  phase  dredging would  generate  huge  quantities  of  good  quality materials  it  is better  to  reclaim  the  entire  50  ha  =  125  acres  of  land  in  the  first  phase  itself,  so  that  the consolidation over the years will make the required ground improved for construction. 

2.12. DREDGING 

2.12.1. QUANTITY OF DREDGING 

Dredged Depth 

The design ship has the following size;   

Table 2.9Designed Ship Vessel Size 

Ship  DWT  L B D Design  Ship  105,000  290.0 m 43.5 m 14.0 m 

Hence  with  the  under‐keel  clearance  the  depth  in  the  channel  at  various  sections would be as follows: (PIANC recommendation based on the environmental parameters) 

Table 2.10 Designed depths in the Navigation channel for a vessel draft of 14.3 m 

  INNER CHANNEL OUTER CHANNEL KEEL CLEARANCE DEPTH KEEL CLEARANCE  DEPTH

SUMMARY  14%  2.0 m 16.0 m 27% 3.8 m  17.8 m

2.12.2. DREDGED VOLUME 

Computation of  the dredging  volumes  is based on  the Chart no. 1204/2010 and Navigational Chart no. 2026/211. The channel has been divided in two smaller stretches and average depth along the stretch is considered. This computation is approximate and detailed computation could be carried out at the DPR stage when the actual depths for the outer channel are surveyed and accurate depths at closer intervals are available.  

Based on the available information on the subsoil (boreholes data), it could be safely assumed that the initial design depths could be achieved only by dredging soft material. However, detailed 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  71 

examination of the Geo‐technical data along with the Geophysical imprints reveals that, there is a possibility of occurrence of rock at the entrance of the creek, just past the existing sand bar. Therefore, 0.2 million cum of hand rock dredging is considered in the current calculations. This is however, subjected to verification at the DPR stage, when more detailed geo‐technical surveys would be carried out. It must be recognised that in order to allow navigation of Cape Size vessels these rock dredging quantities may further increase. This is a subject matter of verification at the DPR stage.  

 

Figure 2.29 Inner and Outer Navigational Channel used for computation of quantities 

Figure 2.30 Computation of Dredged Volume 

Sl. No  Length in mWidth in m DesignedDredged 

depth in m

Existing 

Depth in m

Depth to

be 

dredged in

Volume1

(central)  in

m3 

Volume  2

(slope) in m3 Total 

Volume  in

m3 

Part A – Approach Channel for the Direct Berthing Jetty at Korlai

A1  700  180  14.6 4.5 10.1 1272600 357035  1629635A2  750  180  14.6 3.5 11.1 1498500 462037.5  1960537.5A3  600  180  14.6 6.0 8.60 928800 221880  1150680A4  800  180  14.6 3.5 11.1 1598400 492840  2091240A5  350  180  14.6 2.0 12.6 793800 277830  1071630A6  500  180  14.6 3.5 11.1 999000 308025  1307025A7  800  180  14.6 4.4 10.2 1468800 416160  1884960A8  450  180  14.6 5.5 9.10 737100 186322.5  923422.5A9  12550  180  14.6 10.25 4.35 9626650 1187387  10814037(Weathered) Rock Dredging    200,000

Total A  17500  ‐‐  ‐‐ ‐‐ ‐‐ 19123650 3909517  23033167

Part B – Inner Channel for the Sanegaon Facility

B1  20540  80  3.1 2.2 0.9 1478488 295776  1508064

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  72 

Grand 

Total  

      20602138 3939093  24541231

In the first phase however, a lesser depth for handling handy max vessel may be evaluated, for the sake of making the port viable. However, keeping pace with the traffic the dredged depth would  be  increased  for  the  Cape  handling which would  be  in  the  tune  of  34.0 million  cubic meters. 

2.12.3. DISPERSION OF DREDGED MATERIAL 

Identification of the dumping site in the offshore area was carried out so that after dumping the resulting  concentration  in  the  identified  location  is  within  permissible  limits.  The  already calibrated hydrodynamic model was coupled with a dispersion module to give the likely spread (dispersion) of the dumped material. Dumping location of dredged materials is given in Figure 2.31 

DHI selected the modelled dumping grounds based on information and earlier studies provided by  the  client.  Two  locations  18°31'41"N,  72°41'32"E  for  the  northern  dumping  site  and 18°28'21"N, 72°42'53"E for the southern dumping site are selected which are approx. 24 km from the shore.  

 

Figure 2.31 Dumping location of dredged materials 

The  dispersion  of  dredge  spoil  around  the  disposal  area  was  simulated  for  the  Northeast monsoon period from 26.10.2016 to 26.11.2016. The spread of the disposed sediment on the sea floor after the one month of sediment disposal for the Northern location is shown in Figure 2.32.  

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  73 

 

Figure 2.32 Model simulated deposition depth after dumping 

The dispersion studies carried out at the proposed north and south dumping locations indicated that  irrespective  of  the  phase  of  the  tide,  dumped  material  does  not  enter  the  proposed extension of the outer channel. Also, material could be dumped inside the periphery of about 1.5 km radius from the suggested location. About 20 Million cum of the dredged material resulting from  the  capital  dredging  is  assumed  to  be  disposed  of  suitably  at  these  two  locations.  For maintenance dredging, these dumping locations could also be utilised for disposing of dredged material during the maintenance of the channel, if the properties of the dumped material do not significantly changed from the material considered in the study. The model also indicated that the average depth of deposition after dumping is about 0.30 m. 

2.12.4. RECLAMATION 

From the examination of the boreholes it was ascertained that there is good quality sand on the top 7 m of the seabed. This could be used for reclaiming the land between the high‐water line and the 0 m contour. This area would be utilized for material handling and storage. 

The reclamation would be carried out between retaining embankments. The dredged material could be directly pumped in to the enclosed area through rain or by pumping through floating pipelines. 

The tentative area for the reclamation and the berth is shown in Figure 2.2. The berth close up showing the details of the berth area and the dolphin and approaches is shown in figure 2.23 below. 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  74 

The area to be reclaimed is about 50 hectares.  

The top level of the recalamation can be calculated as follows; 

Highest Astronomical Tide    : 4.6 m  

Storm Surge        : 0.30 

Local wind generated wave    : 0.40 (inner creek) 

Assuming 1.0 m air gap, 1.2 m thick deck structure the deck level is 7.5 m with respect to CD. 

There will be one dolphin on the eastern side of the berth at a distance of 25 m from the end of the berth 525 m x 46 m size. The area of reclamation confined between the shoreline and the ‘0’ m contour, has two approaches to the berth of 12‐16 m wide. The barge loading berth is located along the northern face of the reclamation. Figure 2.33 for details. 

 

 

Figure 2.33 Layout of the Berth along with the approaches and mooring dolphin 

2.13. ROAD AND RAIL CONNECTIVITY   

2.13.1. ROAD 

A four‐lane road would be planned from the existing approach to connect the port. There will be outer peripheral road around the storage yard. This would act as the main road.  

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  75 

There  will  be  internal  roads,  which  would  be  connecting  the  peripheral  road  based  on requirement and alignment of the starage areas.  

In the final phase there would be four lane road connecting the port to Roha shall be establisehed for better communication. 

2.13.2. RAIL   

The nearest railhead is near Roha, which is located around 40 kms away on the Kokan railways network  

2.14. NATURAL RESOURCES 

2.14.1. WATER REQUIREMENT 

2.14.1.1. Domestic requirement  

Water requirement for meeting domestic water requirement in construction phase will be 38.25 KLD and in operation phase will be 35.5 KLD. 

The per capita consumption for the in port consumption is taken as 90 liters per day.residential accommodation would be permitted inside the CRZ area. The occupancy is taken as 350 in the port.  Total  consumption will  be  35,500  liters  per  day.  A  reservoir  of  capacity  1  lakh  liters  is proposed at location of highest contour. The water would be received from the MIDC supplies.  All the utility buildings shall be provided with individual Overhead Tanks in order to achieve water supply  system.  The  pump  room  will  be  under  the  Overhead  tank  connected  with  a  water treatment plant (WTP) if required. Otherwise, the raw water will be directly fed to the OHT.  The Pumps are so selected to fill the tank once in a day. Two numbers (one as standby) 25 HP water supply  pump  with  suitable  pump  panel  is  proposed.  Pipelines  are  spread  over  the  area underground/ in built‐up trench and provided with outlet points wherever necessary. 

Water requirment for Jetty Activities 

Sr.No  Activities  Phase I  Final Phase 

  Potable water Demand (Other than Port Building)  17  17   Potable water Demand (Port Users & Operation 

Buildings) 18  18 

  Fire Demand in Buildings  30  30   Water Demand for washing and servicing  15  15   Total  water  demand  for  Coal  Stackyard  Dust 

Suppression System for 2 days 200  500 

  Total  water  demand  for  IBRM  Stackyard  Dust Suppression System for 2 days 

100 250 

  Fire Fighting Demand in Stackyard area  100  1080   Total (in cum/day)  480  1080 Total (in MLD)  0.48  1.08  

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  76 

2.14.2. POWER REQUIREMENT 

Electrical  system  design  should  from  an  integral  part  of  the  project.  Selection  of  equipment distribution pattern, cable route, and earthing arrangement, location of switches boards, captive power  requirement etc.,  shall  be  considered  for preparing  schemes. Obtain  a  general  layout, mark it with major loads at various locations was the method used to determine the appropriate total load in KW/KVA.  

It is proposed that the incoming HT supply is taken from the nearest substation at voltage level of 33 KV. Single transformer of capacity of 33 KV/ 11 KV, 12 MVA oil filled out door type shall be installed. Detailed working of the power requirements are given in the TFR document. A 33 KV switch yard is to be set up near to the Port area from where three or four 11 KV feeders are taken to feed the Port equipment.  

33 KV and 11 KV control rooms are   required near the Yard. 11 KV supply will feed Transformers for Dry Bulk Terminal (Iron Ore), Dry Bulk Terminal (coal) and common utility. Each Transformer size could be selected based on the individual total connected load.   

Outdoor transformers are preferable where space is not a constraint and in the case of those for which the main switch board can be away from the transformer. But in large industries, larger transformers are invariable which will be indoor type since it requires bus trunking at the LT side and main switchboard should be near the trunking.  

For  outdoor  transformers,  11KV  supply  is  drawn  to  the  consumers  premise through OH lines and received at a separate DP structure for mounting it. There will be another DP structure for the consumer for fixing the AB switch and fuses. Substation for Iron ore and Coal is considered separately in different locations.   

2.14.3. WASTEWATER GENERATION AND MANAGEMENT 

During construction phase sewage will be generated from workers camp which will be treated in STP. Total sewage generation during operation phase will be 28.3 m3/day. Sewage Treatment Plant of capacity 30 m3/day will be provided to treat the sewage. 

The   sewage   network   includes   HDPE   pipelines,   Manholes,   Gully   chambers, Inspection chambers, Oil and soap removal chambers. Most of the work involves civil  construction  activity  with  construction  of  the  flow  path  of  sewage  to  the Sewage  Treatment  Plant.  The sewage network is connected to the Sewage Treatment Plant at the final phase of flow from a far point of origin. A network of such lines equipped with appropriate manholes will be led to the mouth of the STP. The treated water will be used for irrigation or dust suppression. Sludge generated will be used as manure. 

2.14.4. SOLID WASTE GENERATION AND MANAGEMENT 

Construction waste will be disposed suitably as per Maharashtra Pollution Control Board (MPCB) guidelines through contractors. In operation phase Solid waste generated is proposed to be sent to authorized and organized solid waste management units. Estimated Amount of solid waste to be generated in construction phase will be 340 Kg/day and in operation phase will be 140 Kg/day. 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  77 

2.15. MANPOWER REQUIREMENT  

Man power requirement in construction phase is 850 and of operation phase is 350. 

2.16. PROJECT IMPLEMENTATION SCHEDULE  

The project implementation schedule for construction of proposed wharf will be of 30 months 

   

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  78 

CHAPTER03BASELINE

ENVIRONMENTALSTATUS

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  79 

3. DESCRIPTION OF ENVIRONMENT 

3.1. GENERAL 

Baseline  data  is  a  preliminary  step  in  the  EIA  process  collected  within  10  km  radius  of  the proposed project sites  for environmental components. Baseline data  is collected to serve two purposes in the EIA study, first it helps to understand the current conditions of the area, and how the project needs to be implemented considering these conditions and second, it helps to assess and predict the possible environmental changes that could occur, once the project is proceeding. 

Baseline data is the data collected for various factors of the project study. This includes:  Physical‐  the  area,  the  soil  properties,  the  geological  characteristics,  the  topography, 

watershed properties, etc.  Chemical‐ water, air, noise and soil pollution levels, etc.  Biological‐ the biodiversity of the area, types of flora and fauna, species richness, species 

distribution,  types  of  ecosystems,  presence  or  absence  of  endangered  species  and/or sensitive ecosystems etc. 

Socioeconomic‐  demography,  social  structure,  economic  conditions,  developmental capabilities, displacement of locals, etc. 

Cultural‐ location and state of archaeological and/or religious sites. 

The levels of the various environmental parameters which could be affected significantly due to the project activities are measured.  

For  the  proposed  project  baseline  data  was  collected  and  monitored  for  one  season  (Pre‐monsoon) Secondary data was collected from various Government organizations, news articles and research papers. 

M/s Ana Laboratories was  involved  in  for environmental baseline studies for components  like ambient air, soil, water, noise marine water & sediment, marine biology. 

Monitoring  surveys  of  the  study  area  (project  area)  has  been  carried  out  in  one  season  i.e. October 2015 to February 2016.  In addition separate studies for the bed material and marine ecology were carried out between March 2016 and May 15th 2016.   

3.2. STUDY AREA 

The environmental baseline data was collected in the pre‐monsoon and post‐monsoon season for an area of 10 km radius from proposed project site. The secondary data for the Raigad region was collected from various secondary sources such as published reports, online literature review, NDMA, CGWB report, etc. 

The entire project  area  is  divided  in  to  various  environmental  segments  in order  to  establish baseline environmental study. The various 8 locations selected on the merits of environmental settings are indicated in Table 3.1 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  80 

Table 3.1 Environmental Monitoring Stations 

3.3. TOPOGRAPHIC SURVEY 

Topographic maps are detailed, accurate graphic representations of features that appear on the Earth's  surface.  The  features  include  roads,  buildings,  urban  development,  railways,  airports, names  of  places  and  geographic  features,  administrative  boundaries,  state  and  international borders, reserves, hydrography, relief and vegetation the project area. These were later verified by using SOI topo sheet. The proposed project study area (10 km) falls in Topo sheet no. E43G13 on scale of 1:50000. The topo sheet is given in 

 

Figure 3.1 Topography map 

SR. NO.  STUDY LOCATION 

01  Project Site02  Bagmala03  Walke04  Mandala05  Vave 06  Talekhar 07  Salav 08  Korlai 

Proposed 

Jetty 

Existing Facility 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  81 

3.4. GEOLOGY 

Geologically, the Konkan lowlands are a platform of marine denudation raised to form a narrow plain. The geology of the entire district consists of dark coloured volcanic lava flows and laterites which date back to the Mesozoic Era. These are spread out in the form of horizontal sheets or beds and have innumerable spurs, hills, ridges, peaks and plateau, the lava are termed as plateau basalts. Since these basaltic lava flows cover an extensive region in the Deccan and frequently present step like appearance to the hills and ridges, they are commonly known as “Deccan trap”. 

The rocks either by exploration into massive spheroid boulders, which are usually seen on hill slopes and foot hills. The Deccan traps generally lack minerals of economic importance but being hard,  dense  and  durable,  are most  suitable  as  building materials.  There  are  two well‐known groups of springs in the district, namely the Unhere and Sav springs. These are known to possess medicinal value in curing skin diseases and rheumatic complains. Nodular Kankar, a concretionary lime carbonate, is usually found sporadically on soils and alluvium covering the Deccan trap in the district. The sea shells found along the coast at places are used for the manufacturing lime; salt is produced by direct evaporation of sea water near Uran, Sheva, Karanja, Pen and Panvel town. The region  is made up of Basalt and Laterite and both are used as a building material. Bauxite is available in Murud and Shrivardhan tehsils. At few places, especially in Varanda Ghats area zeolites are reported. 

3.4.1. DRAINAGE PATTERN 

The  district  is  drained  by  short  westwards  flowing  parallel  streams,  which  originate  in  the Sahyadri  hills  in  the  east  and  flow  into  the  Arabian  Sea.  These  streams  are  swift  and  erode material  and  deposit  on  the  shoreline.  Besides  the  general  parallel  pattern  of  the  rivers,  the tributary pattern tends, at places, to be rectangular suggesting the adaptation of stream to the local rock structure. In the north‐west the Panvel creek collects water from a radial pattern of short stream of which the Kalundri River is a major stream but others are very short and seasonal. The Patalganga, Bhogawati and Amba rivers drain mainly Khalapur, Sudhagad and Pen tehsils into the Dharamtar creek. The Patalganga River receives the tail water of the Khopoli Hydel Power Station. The Kundlika or Roha River drains a narrow central belt into the Chaul creek. The Mandad river drainage basin is like an amphitheater closing round the wide estuary at the mouth of Janjira fort. The southern part of the district is drained by the well‐developed system of the Savitri. The main tributaries of the Savitri are the Ghod, the Gandhari, the Kal, the Nageshri rivers. The map of drainage pattern is given in Figure 3.2. 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  82 

 

Figure 3.2: Drainage map of Raigad 

3.5. PHYSIOGRAPHY  

Raigad district forms a part of Maharashtra littoral, the micro level divisions of coastal plain. It is slightly elongated in the north ‐ south direction. Raigad has a long indented coastline. The length of the coastline is about 240 km, with a number of creeks and inlets, suggesting submergence confirmed  by  the  submerged  khair  forest  in  Thane  creek  and Mumbai  harbour.  Though  the districts  form  an  important  part  of  the  traditional  “Konkan  Plain‟,  ruggedness  and  uneven topography are its governing physical features. The Sahyadri (Western Ghats) in the east send several transverse numbers of subsidiary hills westwards denying the plains of a uniform level and continuous character. On the basis of variation in  local relief, the district can be classified into six groups’ i.e. 

i. Sahyadri Hills  ii. Konkan Forested Hills  iii. Sudhagad Plateau iv. Ulhas Basin  v. Kal‐ Savitri Valley  vi. Raigad Coast 

The physiography map for Raigad is given in Figure 3.3 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  83 

 

Figure 3.3 Physiography map of Raigad district 

The district has three physiographic divisions i.e. (i) Coastal zone in west covers about 20% of the district (ii) Central zone covers about 1/3rd of the district, consisting of fertile land in low lying area (iii) Hilly zone in the eastern part highly uneven in altitude and covered with forest. This hill range is characterized by ruggedness and uneven topography, with crest line of peaks and saddles forming the eastern horizon. Ulhas, Panvel and Patalganga are the three main rivers in northern 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  84 

part. Kundalika River is the main river in central part whereas in the southern part Savitri River is the main river. 

The soils in the district are formed from the Deccan Trap which is predominating rock formation with small out crops of Laterite at a few places in the Poladpur taluka and Matheran hill. The soils are  grouped  as  Forest,  Varkas,  Rice,  Khar  or  Saline,  Coastal  Alluvium  and  Laterite  as  per  the location and topographical situation. 

3.6. LAND USE 

Primary Data  

In  the present  study,  both  digital  image  processing  and  using  visual  interpretation  technique were used to generate an output of Land use / Land cover map of study area on 1: 50,000 scale.  

Methodology: The methodology used for the study consists of the following components:  

(i) Base Map Preparation  

The  base  map  was  prepared  using  the  Survey  of  India  reference  map  on  1:50,000  scale. Interpreted thematic details were transferred on the base map. Besides, other supporting data like project reports and statistical data published by various Government departments have also been used.  

(ii) Ground Truth Data Collection  

Ground data on geo‐environmental components of the study area were collected for verification of information about the different features on the study areas. During the ground truth, detailed information on agricultural practices, wastelands, mining, industrial area etc. was collected along with other land features.  

(iii) Interpretation of Remote Sensing Data  

A  hybrid  technique  has  been  used  i.e.  visual  interpretation  and  digital  processing  for identification of different  land use /land cover classes based on  the  image characteristics  like tone,  size,  shape, pattern,  texture,  location and association etc. An  image  interpretation keys were developed based on  such  image  characteristics, which enable  interpretation of  satellite images  for  land use/land cover  features.  Further,  the  land use/land cover and other baseline layers were put in a GIS database for integration, analysis, statistics generation and final out in the form of land use the land cover map.  

Land use pattern was determined for 7km radius of project site. It was observed that as proposed area  surrounding  the  project  consist  mostly  of  Agricultural  land,  Thorn  scrub  and  Moist Deciduous forest with spars settlement and mangrove. Land use of the proposed site on scale 1:50000 is given in Figure 3.4. 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  85 

 

Figure 3.4 Land use map of proposed project site   

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  86 

3.7. SHORE LINE  

The coastal stretch in the vicinity of the Revadanda/Salav/Korlai is covered by Naval Hydrographic chart nos. 2026. It can be seen from this chart that the coastline is pierced by the Kundalika River, which divides the shore line in to two distinct segments. While the southern shoreline is mostly North‐South direction,  the Northern shoreline makes an angle of 3400  ‐ 3500 N. The estuary entrance is protected by a peninsula on the west of entrance known as Korlai Headland, providing the necessary protection from the south‐westerly waves. 

The shoreline near the entrance is generally rocky and fronts an elevated plateau. The slopes of the shoreline are steep and almost vertical on the southern part of the estuary. The shoreline of the bay  is generally  in the east‐west direction and  is  fringed with  laterite rocky outcrops. The Southern shoreline carries the Korlai Fort and small hamlet of fishermen community. To the north of the entrance the shoreline is flatter and fronts a white and wide beach. The foreshore of this area is in general flat and more populated than the southern part of the shoreline. The shoreline is mildly sloping along the coastline. The near shore area behind the development zone is shallow and located in a slight embayment, creating conducive zone for reclamation for the port back up without affecting the creek morphology adversely. Physical setting of the Shorelines & creek area is given in Figure 3.5 

 

Figure 3.5 Physical setting of the Shorelines & creek area fo Korli deep water jetty 

The existing facility at Sanegaon on the Right bank of the Kundalika River is shown on the Satellite imagery obtained from the Google satellite archives. The depth of water upstream of the facility is about 2 to 3 m along the deepest channel. The downstream area is deeper than the upstream, because of the channelization and meandering respectively. The upstream of the existing facility, the river meanders due to the tidal effect and stagnating flows especially in the non‐monsoon conditions.  The  channelization  happens  right  at  the  facility.  Due  to  the  flow  channelization, depths in the river below this point are slightly better varying between 2.5 to 3.5 m with respect to the Chart Datum. 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  87 

3.8. SEISMICTY 

The  project  area  is  classified  in  Zone  IV  as  per  NDMA,  Earthquake  vulnerability map,  having moderate seismic  intensity to earthquake. All the construction of the proposed project would adhere to the norms for this seismic zone and seismic zone is as given in Figure 3.6 

Figure 3.6 Map showing seismic zones of India   

Project Location

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  88 

3.9. CYCLONE ZONE 

In general, the west coast of India is less prone to cyclonic storms compared to the east coast. It is observed from the tracks of the cyclones in the Arabian Sea from 1877 to 1992 that only 10 storms endangering the Mumbai coast have occurred in the above said period i.e. at a frequency of once in 12 years. The Proposed site falls under Tropical cyclone which further is characterized under category 02 “Moderate Damage Risk Zone”. The damage capacity of cyclone  is given  in Figure 3.7 and Table 3.2. 

Table 3.2 Damage capacity of cyclone 

Cyclone Category Wind Speed in Km/h Damage Capacity 01 120‐150 Minimal02 150‐180 Moderate03 180‐210 Extensive04 210‐250 Extreme05 250 and above Catastrophic

 

Figure 3.7 : Wind and Cyclone Zones in IndiaSediment Quality 

Project Location 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  89 

Secondary Data 

Deccan Trap basal of upper Cretaceous to lower Eocene is the major rock formation and intruded by a number of dykes. Soil sediments found in most part of the river is found to be sandy clay. The river does not show braiding which is popularly attributed to heavy sediment load in a river having a wide and shallow cross section. The river does not have a steep gradient which may cause increase in velocity and turbulence. The slopes of this river  indicate that  it does not fall under rapid zone. It is also observed that there is negligible migration of the settlement of soil in the river. 

The  river  shows  salinity  variation  at  high  tide  as well  as  at  low  tide.  The  sedimentology  and vegetation cover of island groups nearby are influenced by these salinity changes at high tide and low tide  in  the river. Rate of sedimentation  is highly dependent on the amount of suspended sediment matter. The rate is found to be highest in between 12 to 15 km from the mouth of the river.  {Source:  Detailed  project  report:  Revadanda  creek/Kundalika  river  (client:IWAI) http://iwai.nic.in/sites/default/files/6770816065NW‐85%20Final%20DPR_Revdanda.pdf  and  A geo‐environmental  study  of  creek  and  river  islands  in  Kundalika  between  Kopri  and  Bahe  in Raigad district of Maharashtra http://hdl.handle.net/10603/2499} 

Primary Data 

The sediment sampling stations were decided on the basis of site specific information such as source  of  pollution  along  the  sampling  site,  existing  ecology  etc.  Sediment  samples  were collected at 16 locations. 

Methodology for Sample Collection, Preservation and Analysis 

All samples were collected within the survey area using a suitable grab sampler and sub‐sampled in plastic zip lock bags. The samples were transported to the laboratory and analyzed for selected physical and chemical parameters using standard methods. 

Interpretation 

Presence of heavy metals and oil & grease could be as a result of  the operation of boats and vessels where oil leakage or grease mixing/solid waste in water can be a source of contamination. Also, higher levels of iron & chromium may be due to industrial & domestic activity and other existing structures. 

3.10. WATER ENVIRONMENT 

Water environment includes two environmental settings, i.e. ground and surface. Baseline data with regard to these two environmental settings was generated. The results were compared to CPCB’s  stipulated  criteria  for  raw water usages, use based classification of  surface water  and water quality standards for coastal waters. 

Secondary data 

Kundalika is a non‐perennial river having a length of approximately 35.5 km. The river flows from hilly areas near Roha city and merges in the creek at Salav. MIDC has established an industrial estate at Dhatav, on the bank of this river. It is a prime source of water for the industrial estate, 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  90 

for nearby villages and for Roha city. Saline water zone starts from the downstream of MIDC to Salav. 

Kundalika  River  falls  under  priority  class  II  which means  it  falls  in  a  relatively more  polluted category. One of main reasons for the pollution of this river is due to the discharge of domestic wastes from villages/towns along the bank of the river. Major villages/towns along the bank of river are Roha, Astami, Bhira and Kolad. The wastes are direct discharged into the river without any treatment and have become a regular and substantial source of pollution of the sweet water zone of the river. A report of MPCB in 2019 shows that the total discharge of sewage in Roha city was 2.8 MLD. There are no STPs  in that area to treat the sewage. BOD and COD of a drain at Ashtami  Bridge,  Roha  was  found  to  be  105.0  mg/l  and  228  mg/l  indicating  high  amount  of pollution. MPCB under the project National Water Monitoring Programme (NWMP) monitors the quality of Kundalika River. From this data it was observed that most of the locations were not complying to the bathing standards.  

Other important reason for pollution in the river is that there are a number of industries present near  the  river which use water  from  that  river. MIDC Roha has 41 units  out of which 35  are effluent generating units. For these industries there is a common effluent treatment plant (CETP) of Roha Industrial Association (ROHA) having a capacity of22.5 MLD. After treatment, the effluent is  disposed  in  the  creek  14.7  km  away  from  CETP.  From  these  industries,  there  is  no  direct discharge of effluents into the Kundalika river. It was observed that the CETP had an efficiency of 75%,  was  not  able  to  attain  the  discharge  limit  of  100mg/l  and  250 mg/l  for  BOD  and  COD respectively.    (Source:  Detailed  project  report:  Revadanda  creek/Kundalika  river  (client:IWAI) http://iwai.nic.in/sites/default/files/6770816065NW‐85%20Final%20DPR_Revdanda.pdf Report on  Action  plan  for  clean‐up  of  pollution  stretch  of  Kundalika  river https://www.mpcb.gov.in/sites/default/files/river‐polluted/action‐plan priority/priority_I_KUNDALIKA_28052019.pdf). 

Primary data 

To  assess  the  quality  of  water  representative  samples  were  collected  from  sixteen  different sampling stations within the survey area. 

Methodology for Sample Collection, Preservation and Analysis 

The representative water samples were collected at 16 locations within the impact zone to evolve a general background of the project sites in 2 liter pre‐cleaned bottles. Appropriate preservatives according  to  the  CPCB  (Guidelines  for  Water  Quality  Management,  2008)  were  added  and samples were stored in ice‐box at temperature of 4°C in dark & brought to the laboratory with utmost care. Highly unstable parameters like pH, temperature, turbidity were measured on site and dissolved oxygen  (DO) of  the  samples was  fixed  immediately.    Photographs of  the water sampling are as shown in Figure 3.8. 

Standard analytical methods were adopted for the analysis of physio‐chemical, microbiological and heavy metal analysis. Analysis was carried out within the stipulated time period.  

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  91 

 

Figure 3.8 Water Sampling 

Interpretation:   

The  pH  of water  samples  at  all  the  locations was  found  to  be moderately  alkaline.  Electrical conductivity and Salinity are present at optimum levels of sea water. Micro & macro nutrients are present at natural levels. Also presence of COD, BOD, heavy metals and Oil & Grease indicates commercial or domestic pollution in the sampled areas. Overall on basis of secondary data and qualitative analysis of the water, it can be concluded that the presence of source of pollution may be due to anthropogenic activities, industrial waste, domestic waste and boat movements. 

3.11. BIOLOGICAL ENVIRONMENT 

3.11.1. MARINE ECOLOGY 

In view of the need for conservation of environmental quality and biodiversity, study of biological environment  is  one  of  the most  important  components  for  ecological  assessment.  Ecological system shows inter relationship between biotic and abiotic components including dependence, competition and mutualism. Biotic component comprises of both plant and animal communities, which  interact  not only within and between  them but  also with  the  abiotic  components  viz., physical and chemical components of the environment. Generally biological communities are the indicators  of  climatic  conditions,  dependent  on  environmental  condition  and  resource  of  its distribution and survival. It may change if there is alteration in the environmental variables like temperature, humidity, rainfall, soil characteristics, topography etc., which are responsible for maintaining  the  homeostasis  of  the  environment.  The  species  of  flora  and  fauna  in  the environment  are  organized  into  natural  communities  with  mutual  dependencies  and  show various responses and sensitivities to anthropogenic influences. The changes in biotic community are studied in the pattern of distribution, abundance and diversity. 

3.11.1.1. Phytoplankton 

Plankton  is  an  important  component  of  an  aquatic  ecosystem, which  responds  to  ecosystem alterations rather rapidly. It is due to the fact that planktonic organisms, which react to different 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  92 

types of water pollution, play a key role in turnover of organic matter and energy through the ecosystem. This reaction is very rapid because of relatively short lifetime and high reproduction rates of these organisms. Since the phytoplankton plays a key role of primary producer in aquatic environment,  it  is  the  first  component  in  the  trophic  tier  to  be  affected  by  pollution. Phytoplankton  can  grow  rapidly  and  form  massive  blooms  that  can  be  regulated  by environmental factors such as nutrients, availability of light and biotic interaction with grazers. Phytoplankton is generally microscopic and passive drifters with the currents.  

Methodology for Sample Collection, Preservation and Analysis of Phytoplankton 

Phytoplankton  was  enumerated  from  unfiltered  water  samples.  Plastic  bucket  was  used  for collection of water samples. Phytoplankton samples were collected from  different locations in 250 ml plastic bottles. After collection samples was preserved with Lugol’s solution and brought to the laboratory with utmost care. To prevent outside contamination, the bottle were closed properly. Phytoplankton samples were allowed to settle; 1 ml of aliquot of sample was taken for quantitative  population  analysis  and  Bio‐diversity  indices.  Organisms  were  counted  under microscope using standard identification key.  

 

Result 

Phytoplankton counts recorded at different sampling stations are presented in Table 3.3.   

Table 3.3 Phytoplankton Species observed 

Sr. No. Species observed in core area Species observed in buffer area 1. Asterionella sp.  Asterionella sp. 2. Thalassiothrix sp  Thalassiothrix sp 3. Streptotheca sp  Streptotheca sp 4. Navicula sp  Navicula sp 5. Coscinodiscuss sp  Coscinodiscuss sp 6. Skeletonema sp  Skeletonema sp 7. Thalassiosira sp  Thalassiosira sp 8. cyclotella sp  cyclotella sp 9. Odontella sp  Odontella sp 10. Rhizosolenia sp  Rhizosolenia sp11. Leptocylindrus sp  Leptocylindrus sp 12. -  Guinardia sp13. -  Ditylum sp14. -  Dictyocha sp 15. -  Melosira sp16. -  Triceratium sp 17. -  Asteromphalus sp 18. -  Pleurosigma sp 19. -  Gyrosigma sp 20. -  Trichodesmium sp 21. -  Thalassionem sp 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  93 

Sr. No. Species observed in core area Species observed in buffer area 22. -  Nitzschia sp 23. -  Grammatophora sp 24. -  Chaetoceros sp 25. -  Ceratium furca 26. -  Ceratium tripos 27. - Pyrophacus sp 28. -  Phaeodactylum sp 29. -  Climacodium sp 30. -  Planktoneilla sp 31. -  Peridinium sp32. -  Surirella sp33. -  Dytilum sp34. -  Clostidium sp35. -  Actinoptychus sp 

 

Interpretation 

The concentration and the numerical abundance of the phytoplankton indicate the fertility of a region. Samples were collected in core area (project site) and buffer area (offshore area) however the  highest  diversity  index was  observed  in  buffer  area.  The  Asterionella  Formosa,  Navicula, Coscinodiscus and Streptotheca species was little dominant which was recorded in all stations. Asterionella formosa is one of the most common planktonic diatoms which is found in eutrophic water  however  its  density  has  been  interpreted  as  a  response  to  atmospheric  nutrient enrichment (Saros et al. 2005, Saros et al. 2010). Coscinodiscus and Streptotheca  is very common plankton its widespread showed very high cell density in warm water, it presence is an indication of organic pollution (Naik et al., 2009; Sahu et al., 2012).This results show that study area water body received high organic load and rich in nitrogen concentration because high concentration of Navicula diatom is indicate high loads of nutrients which will be increased productivity in algae, resulting in blooms that can cause low dissolved oxygen and fish kills. However there is no rare or endangered group of phytoplankton were found in the area. 

3.11.1.2. Zooplankton 

Zooplankton  is  a  very  important  group  in  the  aquatic  ecosystem  and  acts  as  the  primary consumer.  The  zooplankton  serves  as  the  natural  food  source  for  many  aquatic  organisms, including fishes. Creek water zooplankton show considerable variety comprising of members of almost  every  group  from  protozoa  to  chordate.  Depending  on  seasons  and  environmental conditions,  the  plankton  community  shows  pronounced  variation  in  its  character  and composition. 

Methodology for Sample Collection, Preservation and Analysis of Zooplankton 

Desired  volumes  of  the  waters  were  filtered  through  plankton  net  (300  μm  mesh  size) Zooplankton samples were collected from   different  locations  in 250 ml plastic bottles.   After 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  94 

collection  samples  was  preserved  with  5%  buffered  formalin  solution  and  brought  to  the laboratory with  utmost  care.  Samples were  allowed  to  settle;  1 mL  of  sample was  taken  for quantitative analysis of density, bio‐diversity indices and total bio‐mass. Different zooplankton taxa were sorted, identified and enumerated under stereoscopic microscope. Organisms were counted under microscope using standard identification key.  

Result 

Zooplankton groups were observed and their Shannon‐Wiever index is given in the Table 3.4 

 Table 3.4: Observed Zooplankton Species with Diversity Index 

Sr. No. Species observed in core area Species observed in buffer area 1. Gastropod larva  Copepoda

2. Bivalve larva  Amphipoda

3. Copepoda  Polychaeta larvae 

4. Fish larvae  Decapoda larvae 

5. Amphipoda  Chaetognatha 

6. Polychaeta larvae  Gastropod larva 

7. Decapoda larvae  Fish larvae

8. Chaetognatha  Foraminifera

9. Lucifers  Nauplius larva 

10. Foraminifera  Cladocera

11. ‐  Hydromedusa 

12. ‐  Medusa

13. ‐  Lammalibranch 

14. ‐  Cephalopoda larvae 

15. ‐  Salpidae

16. ‐  Heteropoda

17. ‐  Invertebrate larva 

18. ‐  brachiopooda larva 

19. ‐  Ctenophora

20. ‐  Isopoda

Interpretation 

The concentration and the numerical abundance of the zooplankton indicate the high productive water body. Samples were collected in core area (project site) and buffer area (offshore area) however the highest diversity index was observed in buffer area. The Copepoda, Amphipods and Lucifer larva species was little dominant which was recorded in all stations.  Copepods are a group of small crustaceans found in nearly every freshwater and saltwater habitat. Some species are planktonic, and some are benthic. Pollution affects its molecular biology i.e.  Swimming behavior, reproduction etc. Copepod constitutes one of the major zooplankton community and serves as food for several fishes and play major role in the fisheries. luciferid shrimps (larvae and adults) 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  95 

had the highest contribution in abundance, in the coastal and oceanic region. Low salinity coastal waters are preferred for the reproduction of many of these organisms (Borradaile, 1915) (Harper, 1968;Lee  et  al.,  1992;Teodoro  et  al.,  2012),  Amphipods  are  considered  a  sensitive  group  to pollution, Sewage pollution produced a decrease in the abundance and richness of amphipods whereas some of the species appeared to be more tolerant to the sewage input. Study area high Amphipods concentration indicates pollution level of water.  

3.11.1.3. Benthos 

The organisms which inhabit the bottom of aquatic body are called benthos. Many of them are sessile while; some creep over or burrow in mud. The quality and quantity of animals found at the bottom is not only related  to  the nature of  substrata but also  to depth,  the kind and the quality of aquatic plants present  in such environment and food availability. Their number and distribution also depend upon physico‐chemical properties of water, community structure and other factors. 

Methodology for Sample Collection, Preservation and Analysis of Benthos 

Sediment  samples  were  collected  from  locations  by  using  van  veen  grab  quadrant  sampler. Benthic organisms was separated out using 500 micron mesh sieve and preserved in rose Bengal and  5%  formalin  solution  Samples were  sorted‐out  separately  and macro  benthic  specimens were  identified  to  the  lowest  possible  level  under  a  stereoscopic  microscope.  All  identified specimens were  referred by quantitative analysis of density, bio‐diversity  indices &  total bio‐mass. After analysis sample was preserved in 10% formalin and density was expressed in no/m2.  

Results  

Macro benthic fauna were observed is given in the Table 3.5. 

Table 3.5: Observed Macro Benthic Fauna  

Sr. No. Species observed in core area Species observed in buffer area 1. Brachyuran sp  Anomura

2. Nereis sp  Capitellidae sp 

3. Syllis sp  Caprella sp

4. Notomastus sp  Cardita sp

5. Gafrarium  Cumacea

6. Oysrer spat  Cyathura

7. Planaxis sp  Donax sp

8. Caprella sp  Gafrarium

9. Corophium sp  Hydrozoa

10. Hydrozoa  Katelysia

11. Anomura  Marginella sp 

12. Megalona sp  Megalona sp

13. Donax sp  Murucidea sp 

14. Charybdis sp  Nassaria sp

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  96 

Sr. No. Species observed in core area Species observed in buffer area 15. Grapus sp 1  Nereis sp

16. Grapus sp 2  Oligochaeta

17. Ocypode  Olivia sp

18. Uca sp.  Oysrer spat

19. Diogenes sp  Paphia sp

20. ‐  Planaxis sp

Interpretation 

A benthic survey was conducted to provide baseline macro benthic status in the study area so samples were collected in core area (project site) and buffer area (offshore area). The sample analysis results reveal high benthic productivity in the study area. Considering core and buffer area  Brachyuran, Nereis  and Oyster was  little  dominant.  Brachyuran  crabs  are  highly  diverse organisms. To check the effectiveness of the pollutants do affect different levels of ecosystem and the effect can be traced using Brachyuran crab as a bio indicator species. Nereis (polychaete) is found in shallow and brackish waters. Its high density found in sewage deposition of particulate organic matter and nutrient enrichment area. Nereis serves as a good bio‐monitor of pollution in different sewage sites. Nereis greater dependence on deposit feeding, rather than filter feeding typical in clean sites. Oysters act a filtering out chemical and pollutants and leaving behind clean water. So high density of Neris and Oyster indicate the study site is quite polluted 

3.11.2. TERRESTRIAL ECOLOGY 

The present document is a flora, fauna and associated ecology status assessment report for the new and  the expansion project being proposed by  the  IEIL  through  their consultants C‐Borne services, Mumbai. The project location is at Sanegaon on Kundalika River near Korlai, Raigad in the state of Maharashtra. 

 

In‐order to review the present status of natural ecology and biodiversity elements in the ‐core area  and  surrounding  region  i.e.  buffer  area.  The  objectives  of  this  study was  to  provide  an assessment of present status of flora, fauna and ecological habitat  in the site, comment upon ecological richness, assess the occurrence of ecologically important or rare variety of floral and faunal species, evaluate possible direct or indirect impact of the project on ecology ‐ biodiversity and suggest mitigation measures accordingly. 

3.11.3. MATERIAL AND METHODS 

Desk Study 

The purpose of the desk study was to identify habitats and species of conservation value that may not have been present or apparent during the survey visit (e.g. season specific plants). The desk study was also helpful in understanding the historical biodiversity and ecological status of the site related to ecology and biodiversity of the region or of other related areas encompassing 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  97 

the  proposed  site.  Literature  survey  was  also  undertaken  by  collecting  and  stating  research papers and reports specific to the region. 

Habitat Survey 

To collect data on  flora  (Herbs, Shrubs and Trees) and  fauna  (Birds,  Insects, Spiders, Reptiles, Mammals)  various  strategies  were  practiced.  These  strategies  differed  as  per  the  habit  and habitat of concerned group of species. 

Flora 

The  structure  and  composition  of  vegetation  cover  was  studied  by  using  Phytosociological  methods. Analysis and estimation of diversity, density, dominance and  frequency of different members of plant populations encountered were made. Observations were made in the forest area as well as in non‐forest areas by laying plots and adopting quadrate method. The quadrate method included laying down square sample plots or units for quantitative analysis of vegetation. The sample plot method given by Clements (1898); Philips (1959); Muller and Ellenberg (1974) and Rau and Wooten (1988) EIA Hand Book (ch.7, pp.44) was followed. The Quadrate sizes of 1 m x 1m, 5m x 5m and 10m x 10m were taken for herbs, shrub and trees respectively. 

Co‐existence  and  competition  both  are  affected  directly  by  the  number  of  individuals  in  the community. Therefore,  it  is essential to know the quantitative structure of the community. To characterize  the  community  as  whole,  certain  derived  parameters  are  used  i.e.  Density, Frequency,  Abundance,  and  Importance  Value  Index  (IVI).  Diversity  Index  (Simpson  (D),  and Shannon (H) was used to understanding the biodiversity significance of habitats in the study area and study areas as whole. 

To  summarize,  the  following  parameters  were  used  during  the  Floristic  diversity  and Phytosociological assessment: 

1. Density, Frequency, Dominance, Abundance 2. Importance Value Index (IVI) (by following Cottam and Curtis,1956) 3. Simpsons Index (D) 4. Shannon index (W) 

Fauna and Avifauna 

The assessment of wild fauna was based on random search‐research survey. For animals, other than  directly  sighted,  secondary  evidences  were  recorded  through  calls,  dung  boles,  scats, spoors, rub signs, signs of debarking, drag mark etc. For birds, actual counts at each sampling site were made, by walking through a chosen one‐kilometer stretch of the site and the number of birds were directly counted and listed. A species list was prepared along with taxonomic position of each species. 

Technology used 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  98 

GPS device along with mapping software of Trimble make was used to take GPS positioning of sampling location and important species. ArcGIS was used as platform to create GIS based maps if needed. 

 

 

Trimble to map locations 

3.11.4. SAMPLING STATIONS 

To  collect  data  of  the  overall  landscape,  multiple  sampling  locations  at  village  level  were undertaken. Nested quadrates were used to collect diversity information about flora and fauna. Phytosociological  study  was  undertaken  to  assess  the  quantitative  parameters  of  flora.  4 quadrates per location (8 buffer locations + 1 core). In total 36 sampling quadrates were used to study  9  sample  locations  in  core  and  buffer.  Habitat  summary  of  each  sampling  location  is attached in Table 3.6. 

 Table 3.6 Habitat summary of the EB sampling points 

Sr. 

No. 

Sampling 

location 

Distance 

radius 

Habitat  Notes 

1  Core site  0.5 km 

Very sparse  and stunted Mangrove 

Very sparse and stunted mangrove patches dominated  by  Avicennia  species, Cultivation of vegetables e.g. brinjal done in the  nearby  areas.  The  proposed development in sea about 500 m from the existing stunted mangroves 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  99 

2   Korlai fort 

 2 

Plantations  on mountain surrounded  by coastal ecosystem 

Tourist  spot  with  high  human  activity, monoculture  of  Acacia  aurculiformis‐the Australian acacia 

3  Korlai Forest 

Low  human  impact,  potential  for  highbiodiversity 

4  Revdanda jetty 

Mangrove Mangrove patches dominated by Avicennia species, presence of migratory birds 

5  Barashiv     5 

Dense forest Selective logging6  Mahalunge 

Forest Some  forest  patches  converted  to plantations of mango, cashew & jackfruit 

7  Amali Dense forest 

Selective logging 

8  Revdanda Beach 

 Beach  (Coastal System) 

Tourist spot which has high human activity, monoculture  of  plant  species  like casuarinas,  coconut  &  areca  nut  in  the surrounding areas 

9  Agrav jetty Mangrove 

Mangrove species dominated by Avicennia species, presence of migratory birds 

 

 

 

 

 

 

 

Figure 3.9 Sampling locations for flora & fauna 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  100 

 

 

Figure 3.10 Marine sampling locationsFlora   

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  101 

3.11.4.1. Floral  

Study was undertaken to document diversity of herb, shrub, climber and tree species existing in the  areas  falling  within  the  core  site  and  Buffer  region.  Background  information  on  floristic diversity from literature survey was used to create a detailed account of  local vegetation that might occur at the study site. 

Sampling  was  done  following  the  quadrat  method.  Quadrats  were  laid  randomly  at  various locations within the Core and Buffer region of the project. Random survey was also undertaken to create a detailed inventory of species. Plants were photographed and specimens that could not  be  identified  on  field were  photographed  for  off‐field  analysis.  Based  on  the  direct  field observation and strategic selection of sampling locations primary data was collected to represent the status of flora prevalent in the core site and the buffer region of the project 

Observations 

Habitats within 2 km radius from core comprise of sea, river, forest patches, agricultural patches, plantations  &  mangrove  dominated  areas.    Plantation  of  coconut,  areca  nut,  mango  etc.  is prominent towards Revdanda. Korlai has a mix of agriculture, forest & plantation. In many parts of the area, the forest is converted into plantations. Indirect evidences of foxes as well as Indian peafowl  were  found  in  forest  and  mangrove  patches  within  2  km  range.  South  east  region comprises  of  moist  deciduous  forest  with  some  area  comprising  scrub  land  &  agriculture including human habitation 

Habitats  in  5  km  radius  from  core  comprises  of  sea,  river,  forest,  agriculture,  plantation  & mangrove ecosystem. Plantation of coconut, areca nut, mango etc. is prominent towards North. Southern part has a mix of agriculture, forest & plantation. 

Mangrove ecosystem dominates all along the Kundalika River which serve as nesting & feeding ground for various migratory birds which include birds like black headed ibis, gulls, terns etc. In many parts, the forest is converted into a plantation. South section has biodiversity important areas  as  the  Phansad wildlife  Sanctuary  is  very  close  to  it.  However,  the  port  area  both  the bankline and the water area to be used for reclaimation is devoid of any mangroves. 

Species richness 

Species richness indicates the total number of species present in a given area or a category. The total species richness is often used as an indicator of biodiversity value.  The species richness in the core site was measured by calculating the total number of species encountered during the study phase. We followed two methods of estimating species richness – (i) by pooling species from all observations, random and quadrate and (ii) species from vegetation quadrates. 

Total 18 species were encountered during the study phase in and around (2 km) the core. The biodiversity of the area around the core site is dominated by endogenic trees followed by herbs and  shrubs.  The  18  species  encountered  in  the  core  can  be  categorized  into  following  habit combinations.  The immediate work site is away from the mangrove population and no mangrove would be affected by the project. 

The checklist of species observed in the core is attached in Appendix 2.1a of Annexure 3 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  102 

Phytosociological study 

Phytosociological  study  is  used  to  quantify  species  composition,  relative  abundance  and importance of species in the given area. We undertook phytosociological study by using quadrate sampling technique. Following are the observations of phytosociological assessment in core. 

To understand which species dominates the plant community documented in the core, a relative abundance of each species was calculated. The relative abundance  is abundance measured in relation to other co‐occurring species. On the basis of the relative abundance value it was found that  the  overall  plant  community  was  very  uneven  i.e.  dominated  by  just  few  species.  The evenness of the community can be further evaluated by measuring biodiversity index. 

The vegetation diversity around the core, about 300 m away, is dominated by three species of  Avicennia marina (50%), Avicennia officianlis (20%) and Sonneretia alba (17.5%).Mangroves are considered key habitats of coastal ecosystem and are ecologically critical as breeding and feeding zones of various  fishes and bird species. However,  the proposed area  is devoid of mangroves except for sparse and stunted patches. The list of species in core along with relative abundance, dominance and importance value index is attached in Appendix 2.1b of Annexure 3. 

Flora in the Buffer range 

The  region  covering  the  buffer  range  belong  to  the  Mangrove  dominated  ecosystem.    The dominant  vegetation  in  the  forests  in  the Buffer  region can be broadly  categorized as mix of southern tropical mix deciduous forests and tropical forest.   In the Buffer range, the vegetation diversity  can be divided  into mostly  urban,  agricultural  and  forest  based.  Common  cultivable plants such as Banyan, Pipal, Coconut and Peltaforum can be observed in areas within city. In the forested landscapes the floristic diversity is composed of Pongamia pinnata (Karanj), Terminalia 

belerica  (Behada),  Garuga    pinnata    (Kakad),    Lannea    coromandalica    (Shemat),   Wrightia  

tinctoria  (Kuda),  Lagerstromia  indica (Tamhan), Morina tinctoria (Baratondi), Butea monospera, 

Erythrina  indica  (Pangara)and  related species. To understand more objectively  the vegetation diversity prevalent  in the buffer, a random qualitative sampling was done to generate species richness value.  Further a quantitative assessment was done using quadrates. The list of species in buffer along with relative abundance, dominance and importance value index is attached in Appendix 2.2b of Annexure 3 

Qualitative study 

During the study, random sampling along with systematic sampling using nested quadrates was undertaken in the core and buffer. Based on the data collected by these techniques an overall species list was generated. In all, 164 species were encountered during this rapid single season study.  These  164  species  belonged  to  58  families.    The  species  observed  can  be  further categorized into following habits: 

Habit  Number of species 

Tree  66 Herb  49 Climber  28 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  103 

Shrub  19 Epiphyte  2 Quantitative study 

To understand  the community  structure, phytosociological analysis was undertaken based on vegetation sampling using quadrates. The species observed in the buffer had higher beta diversity (number of unique species) compared to the core sites. Also the species observed in the overall buffer  are  representative  of  the mosaic  of  landcovers  such  as mangrove,  deciduous  forests, agricultural systems, etc. prevalent in the buffer. 

Species  richness  is  the most  basic  form  of  biodiversity measurement. We measured  species richness from plots which also gave us opportunity to evaluate species accumulation curve and bootstrap  the  plot  based  richness measures  to  account  for  sampling  bias  and  provide  better comparison. 

Based on the species richness, the buffer area as expected has more species than the areas within 2 km radius and core. The 5km radius can also be considered as buffer area. Areas in buffer have higher species richness than the core. 

On the basis of relative abundance and importance value index, the mangroves and mangrove associates dominate in the buffer followed by other more deciduous forest specific species such as Zizyphus, Wrightia and Tectona.  Also including many invasive exotic species such as Lantana and Alternenthera. 

Domesticated plants during the survey 

List of plant species associated with plantations, avenues and agricultural landscapes (Domestic plants) were made.  In total 30 species of plants were observed to be very commonly used as domesticated  species  in  the  nearby  locations  of  the  project  site  and  the  buffer  region. Considerable numbers of these species are exotic species. Native species must be promoted to enhance the native ecology. 

Agriculture and Horticulture plant species 

Some common plants planted in orchards and plantations by locals are: 

Sr. no.  Fruiting plants  Major Field crops Vegetables 1.  Mango  Red gram Tomato 2.  Citrus  Sorghum Brinjal 3.  Tamarind  Chickpea Onion 4.  Banana  Sunflower Green chilly 5.  Guava Bajra Beetle vine 6.  Custard apple  Groundnut Turmeric 7.  Bael  Soya bean 

 

Ecologically important species 

Plant species form the basis of ecological interaction in nature. In the web of life, the diversity, density and abundance of plants species are decisive factors.  More  the  native  plant  species  

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  104 

better  is  the  association  with  faunal  diversity. Documenting local species that are ecologically important may be helpful in restoration and greenbelt development planning.   With the help of actual  field  observations  and  literature  review,  a  list  of  plant  species  that  are  ecologically significant  was  prepared.  These  plant  species  are  considered  ecologically  important  as  they attract and support faunal diversity. These plants can be helpful in restoration of natural ecology if planted  in strategic composition. List of ecologically  important plants  found  in  the region  is attached in the Appendix 2.2d of Annexure 3 

Protected species in the region 

The project area and the buffer fall into the tropical moist mixed deciduous forest and estuarine ecosystem.  The  floristic  composition  in  the  less  disturbed  forest  patches  are  represented  by Terminalia  arjuna,  Butea  monosperma,  several  species  of  Ficus  genera,  Cassia  fistula  and Zizyphus oenoplia. 

Other than the common species that represent the general structure of the forest, there can be species that are rare, endangered, and vulnerable or near threatened. These species often have very niche temporal and spatial distribution and may not be encountered during a short term survey. However, a list of Rare, Endangered, Vulnerable or Near Threatened species (RET) was extracted on the basis of  literature  review, by analysis of  the species distribution and also by examining the possibility of being found in the buffer habitat region.  

 

None of the RET listted were actually observed during the study in the buffer region of the project 

Conclusion 

Total number of plant species observed in the core site  :  18  Total number of species observed in the buffer region  : 164  Number of quadrates used in studying buffer region  : 36  Number of locations studied in Buffer      : 9 

3.11.4.2. Fauna 

To study faunal diversity and richness in the area, random sightings were preferred and various methods of observation were practiced. For reptiles, stone lifting was done; rock crevices and wall space of structures in the site were checked. Amphibians were searched near the stagnant water  pools  and  small  streams.  Insects  were  observed  on  underside  of  leaves,  nests,  rock crevices, bushes and other places. Birds were studied by point sampling method and mammal diversity  assessment  was  based  on  indirect  evidences  and  random  interviews  with  the  local human community.   Quantitative analysis was done for mammals and aves. While for reptiles, insects and spiders, species richness was evaluated by qualitative sampling. 

In the core, total 21 species of faunal species were encountered based on random survey. The avian group was the most diverse followed by insects. 

Mammal diversity 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  105 

On the basis of some direct sightings and many indirect evidences such as scats and tracks, the core site seems to offer nesting and foraging sites for small mammals such as Indian palm squirrel and some domesticated animals. Mammal where not found during our quadrate survey. 

Also, no indication of any big wild mammals, or mammals of protected status was observed in core area. It is possible that core and areas around the core may be used by small mammals such as Mongoose, shrews, rats etc. but of poor or no protection / conservation value. 

Avian diversity 

In areas falling within the core site and adjoining areas, we observed total 11 species through random qualitative sampling and by quadrates. 

Using relative abundance we also plotted an abundance rank plot (fig 19) which highlights that common sandpiper (Actitish hypoleucos) and  Indian pond heron (Ardeola grayii) are the most common bird species in the core. The bird diversity in core is characteristic of coastal ecosystem. List of birds is provided in the bird diversity in core is characteristic of coastal ecosystem. List of birds is provided in Appendix 3.1b of Annexure 3 

Insect diversity 

Butterflies, Damselflies, Dragonflies  and Grasshopper groups were used as  indicator of  insect diversity in the core. During the  study  only  6  species  of  insects  were  found  by  quadrate  sampling.  Based on the quantitative assessment relative abundance of species was calculated. The butterfly‐Small Salmon Arab (Colotis amata) is the most dominating insect species in core. List of insects can be found in Appendix 3.1b of Annexure 3 

Faunal diversity in buffer 

During our buffer sampling, we encountered total 127 species. Like in core, the avian group was the most diverse followed by insects. 

Mammals in Buffer 

The mammals in buffer were investigated based on qualitative random sampling and quantitative quadrate sampling by evidence survey to generate a mammal species richness value for buffer. In total 6 species of mammals were documented. Of these 6 species, 2 are of least concerned group  as  per  IUCN  but  in  Schedule  II  of  Wildlife  protection  1972.  Mammal  list  in  buffer  is presented in Appendix 3.2b of Annexure 3 

Family  Common 

name 

Scientific name Abundance IUCN 

Status 

Schedule 

WPA 1972 

Cercopithecidae  Langur  Semnopithecus spp

4 Least concerned 

II 

Sciuridae  Grey mongoose 

Herpestes edwardsii 

3 Least concerned 

II 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  106 

 

Aves in Buffer 

On the basis of quantitative sampling by point count method, 70 species of birds were found. Out of these bird species 2 species, Indian Peafowl and Osprey  was found to be in Schedule‐I as per Indian wildlife protection act 1972 (WPA 1972) . The Indian spotted eagle is vulnerable as per IUCN. 

In  the  buffer  species  such  as  Red‐whiskered  bulbul  (Pycnonotus  jocosus),  Green  bee‐eater (Merops  orientalis),  Little  egret  (Egretta  garzetta),  Blyth's  reed  warbler  (Acrocephalus dumetorum), Purple‐rumped sunbird (Leptocoma zeylonica) are the top 5 most common species. Insects in Buffer 

We observed in total 33 species of insects by quadrate sampling. These 33 species in quadrates belonged  to  10  insect  groups  ‐  Butterflies,  Grasshoppers,  Dragonflies,  Bugs,  Beetles, Wasps, Damselflies, Flies, Mantids and. Of these groups, butterflies were the most diverse. 

Other faunal diversity in core and buffer 

Reptile  and  Amphibian  Diversity:    During  survey  the,  1  species  of  reptile  and  1  species  of amphibians were found in areas close to the project site. On expanding, the survey to nearby ranges in the Buffer region, 3 species of reptiles and 1 species of amphibians were encountered. 

Spider  diversity:  Spiders  are  functionally  important  features  in  any  ecosystem.  They  play  a unique role of controlling pests or specifically population of insects in an ecosystem.  The species observed in the site area were common species and are associated with urban environments. However,  in  the  forest  and  areas  with  thick  vegetation,  more  forest  representative individuals/species were observed. The  list of  insect species  in buffer along with their relative abundances can be found in Appendix 3.2b Of Annexure 3 

 

Conclusion 

Core: 

Number of Mammal species observed in the core site: 1  Number of Bird species observed in the core site: 11  Number of Insect species observed core site: 06  Number of reptile and amphibian species observed in the core site: 2  Mammal species in core:  Indian palm squirrel 

Buffer: 

Number of mammal species in buffer: 6  Number of Bird species observed in Buffer: 70  Number of Insect species observed in Buffer: 33 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  107 

Number of Reptile and amphibian observed in Buffer: 3  Protected species: 

Birds: 

Scientific name  Common name Family IUCN status  Schedule

WPA 1972 

Pandion haliaetus  Osprey  Pandionidae  Least concern  I Pavo cristatus  Indian peafowl  Phasianidae  Least concern  I Clanga hastata  Indian spotted eagle  Accipitridae  vulnerable  ‐ 

 

Mammals: 

Family  Common 

name 

Scientific name Abundance IUCN 

status 

Schedule

1972WPA 

Cercopithecidae  Langur  Semnopithecus spp 

4 Least concerned 

II 

Sciuridae  Grey mongoose 

Herpestes  dwardsii 

3 Least concerned 

‐ 

3.12. AIR ENVIRONMENT 

3.12.1. METEOROLOGICAL DATA 

The  study  of  meteorological  conditions  of  a  particular  region  is  of  utmost  importance  to understand  the  variations  in  the  ambient  air  quality  status  in  that  region.  The  prevailing meteorology at project site plays a crucial role  in transport and dispersion of air pollutants. A Meteorology station for collection of meteorological data was installed at the project site during baseline monitoring period. 

3.12.2. SECONDARY 

Secondary data was collected for wind direction and wind speed for a year and wind rose of the same derived for better understanding of climatic condition of the project site. Wind data is given in Table 3.7 and wind rose is given in Figure 3.11. 

 

 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  108 

Table 3.7 Wind data 

 

 

Figure 3.11wind rose 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  109 

3.12.2.1. Temperature 

The characteristic feature of the climate is in occurrence of extreme temperature conditions. The mean daily maximum & minimum temperature is recorded in the month of May & January, which is about 32.1ºC & 17.6ºC respectively. 

3.12.2.2. Wind 

The mean monthly wind velocity is highest during the month of December with a wind speed of 01‐19 km/hr occurring for 29 days & is lowest during the month of July with a wind speed of 1‐19 km/hr occurring for 12 days. The mean wind speed prevailing in the area is 4 km/hr.  

3.12.2.3. Humidity & Vapour pressure 

Relative humidity varies  from month  to month, being maximum during  the month of  July  i.e. during monsoon & minimum during the month of January. The average humidity is 78.91%. The average vapour pressure is 26.09 hPa with maximum vapour pressure in the month of June of about 33 hPa & minimum of 16.7 hPa in the month of January. 

3.12.2.4. Rainfall 

The project site receives greater part of annual rainfall from South West monsoon between June to September accounting for nearly 85% of annual rainfall & the remaining 15% of the rainfall is recorded during the rest of the year. The average yearly rainfall in the study area is about 2177 mm. usually maximum average monthly rainfall of 741.8 mm occurs in July. January & February are generally the driest month of the year. There is practically no rainfall from December to April. 

Year  Month  Day  Hour W.S. (m/sec) 

W.D. (Deg) 

TMP (°C) 

HMD (%) 

2016  1  14  11 1.6 249 25.6  45.02016  1  14  12 1.1 266 27.1  42.32016  1  14  13 1.0 342 27.6  41.82016  1  14  14  0.7  256  27.7  40.7 2016  1  14  15 0.5 333 25.6  48.72016  1  14  16  1.5  273  23.6  55.6 2016  1  14  17 1.3 128 23.4  59.32016  1  14  18  1.6  264  22.4  65.1 2016  1  14  19  1.5  271  21.6  69.9 2016  1  14  20  1.1  337  20.3  78.3 2016  1  14  21  0.8  309  18.8  79.9 2016  1  14  22  0.2  175  18.3  81.0 2016  1  14  23  0.4  199  18.5  84.2 2016  1  15  0  0.1  342  17.6  83.5 2016  1  15  1  0.0  189  17.2  85.0 2016  1  15  2  0.2  338  17.3  84.5 2016  1  15  3 0.2 100 17.6  83.52016  1  15  4 0.1 104 18.2  76.32016  1  15  5 0.8 240 19.6  74.82016  1  15  6 0.0 228 19.5  73.3

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  110 

2016  1  15  7 0.7 240 21.2  70.72016  1  15  8 1.2 182 21.5  62.52016  1  15  9 1.6 49 23.6  53.42016  1  15  10 0.4 261 24.2  55.42016  1  15  11 0.0 122 25.4  45.22016  1  15  12 1.5 272 26.2  38.62016  1  15  13 1.5 269 27.0  39.12016  1  15  14  1.6  307  27.9  39.1 2016  1  15  15  1.4  270  25.5  45.7 2016  1  15  16  0.7  326  23.6  51.3 2016  1  15  17  1.2  277  23.2  54.9 2016  1  15  18  2.2  75  22.0  63.1 2016  1  15  19  4.9  340  21.8  66.1 2016  1  15  20  1.4  97  19.8  73.8 2016  1  15  21  1.1  320  19.4  74.8 2016  1  15  22  0.3  175  19.0  77.3 2016  1  15  23 0.4 312 17.9  82.92016  1  16  0 0.0 220 17.1  81.42016  1  16  1 2.8 158 17.1  81.42016  1  16  2 0.2 336 17.6  80.42016  1  16  3 0.3 332 17.9  77.82016  1  16  4 0.3 357 18.9  76.22016  1  16  5 0.0 273 19.4  74.72016  1  16  6  1.6  356  19.5  70.0 2016  1  16  7  1.5  332  20.9  63.2 2016  1  16  8  1.2  246  21.6  57.0 2016  1  16  9  0.0  350  23.8  49.2 2016  1  16  10  1.6  274  24.0  47.6 2016  1  16  11  0.8  277  25.5  39.3 2016  1  16  12  2.2  45  27.2  38.8 2016  1  16  13  0.9  349  27.7  34.6 2016  1  16  14  4.9  331  27.7  34.6 2016  1  16  15  0.3  19  25.7  39.8 2016  1  16  16 0.4 227 24.0  46.62016  1  16  17 1.6 38 23.1  52.82016  1  16  18 1.6 320 21.4  62.22016  1  16  19  0.4  180  21.7  64.3 2016  1  16  20 0.6 37 19.6  68.42016  1  16  21 0.0 69 18.7  72.12016  1  16  22  0.0  239  18.4  73.1 2016  1  16  23  0.0  212  17.8  76.8 2016  1  17  0  0.4  314  16.7  84.0 2016  1  17  1  5.9  314  16.1  82.1 2016  1  17  2  3.3  324  16.3  83.4 2016  1  17  3  0.4  285  16.9  76.9 2016  1  17  4  0.1  59  17.6  75.6 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  111 

2016  1  17  5 0.2 36 19.3  72.32016  1  17  6 2.2 358 19.1  71.02016  1  17  7 0.5 295 20.4  64.52016  1  17  8 3.6 44 22.1  56.12016  1  17  9 0.0 221 23.3  42.42016  1  17  10 1.3 47 24.6  43.72016  1  17  11 0.7 87 26.4  34.02016  1  17  12  0.0  325  27.4  25.5 2016  1  17  13  4.0  35  28.6  22.3 2016  1  17  14  0.2  209  28.6  20.3 2016  1  17  15  2.8  96  26.0  34.0 2016  1  17  16  1.4  295  24.2  41.8 2016  1  17  17  1.4  319  23.7  41.8 2016  1  17  18  1.3  321  21.2  56.1 2016  1  17  19  1.8  138  21.7  57.4 2016  1  17  20  0.8  324  19.3  65.8 2016  1  17  21 0.0 60 18.9  69.12016  1  17  22 0.3 144 18.3  71.02016  1  17  23 0.8 326 16.8  74.92016  1  18  0 1.7 157 16.5  87.12016  1  18  1 0.1 165 16.4  90.02016  1  18  2 0.2 98 16.1  87.12016  1  18  3 0.1 172 17.0  83.52016  1  18  4  1.6  317  18.6  80.6 2016  1  18  5  1.4  290  18.6  79.4 2016  1  18  6  1.8  59  19.3  76.4 2016  1  18  7  1.0  348  20.8  70.5 2016  1  18  8  1.0  277  21.3  61.1 2016  1  18  9  2.7  249  24.5  53.4 2016  1  18  10  5.5  315  24.5  49.9 2016  1  18  11  1.3  260  25.8  45.2 2016  1  18  12  1.0  160  27.1  38.1 2016  1  18  13  0.3  190  27.8  35.1 2016  1  18  14 1.2 330 29.0  31.62016  1  18  15 5.4 4 25.9  44.02016  1  18  16 1.1 342 23.9  51.72016  1  18  17  1.1  244  23.7  55.8 2016  1  18  18 2.5 35 22.5  63.52016  1  18  19 0.2 159 21.2  66.42016  1  18  20  4.1  2  19.6  77.6 2016  1  18  21  0.7  262  18.9  76.4 2016  1  18  22  0.2  288  18.6  83.5 2016  1  18  23  0.5  328  17.7  84.7 2016  1  19  0  1.1  316  15.5  77.0 2016  1  19  1  1.3  290  15.0  78.3 2016  1  19  2  0.4  267  15.1  78.3 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  112 

2016  1  19  3 0.3 216 16.8  75.72016  1  19  4 0.4 353 16.6  70.42016  1  19  5 0.4 268 17.9  65.12016  1  19  6 0.9 332 18.3  63.82016  1  19  7 1.1 41 19.0  55.92016  1  19  8 1.0 98 20.2  47.32016  1  19  9 0.6 263 23.5  36.12016  1  19  10  1.0  43  23.5  37.4 2016  1  19  11  1.5  288  24.8  26.9 2016  1  19  12  0.9  333  26.3  23.6 2016  1  19  13  5.6  1  26.7  19.6 2016  1  19  14  0.1  349  27.4  13.0 2016  1  19  15  1.3  329  24.9  25.5 2016  1  19  16  1.5  40  23.3  34.1 2016  1  19  17  2.0  349  23.3  42.0 2016  1  19  18  1.2  42  21.1  51.3 2016  1  19  19 1.4 264 20.7  52.62016  1  19  20 0.3 357 18.4  61.22016  1  19  21 1.3 323 17.0  63.22016  1  19  22 0.3 15 16.6  71.72016  1  19  23 0.0 191 15.8  71.12016  1  20  0 1.1 307 12.5  60.42016  1  20  1 3.3 308 12.2  60.42016  1  20  2  0.1  153  12.7  60.9 2016  1  20  3  2.0  323  12.9  53.9 2016  1  20  4  0.1  301  14.5  53.9 2016  1  20  5  1.1  92  14.9  51.2 2016  1  20  6  1.5  326  16.3  47.4 2016  1  20  7  0.8  84  19.9  43.1 2016  1  20  8  0.5  305  20.5  35.5 2016  1  20  9  1.5  262  21.9  28.0 2016  1  20  10  1.3  309  23.3  26.9 2016  1  20  11  2.5  320  26.0  16.6 2016  1  20  12 2.2 348 27.5  11.22016  1  20  13 0.0 140 28.2  9.62016  1  20  14 0.6 340 29.3  11.22016  1  20  15  0.8  254  25.7  17.7 2016  1  20  16 1.5 331 24.4  24.22016  1  20  17 0.8 321 22.1  27.42016  1  20  18  0.9  307  19.9  36.6 2016  1  20  19  1.5  4  19.4  42.6 2016  1  20  20  1.3  352  15.8  48.0 2016  1  20  21  3.2  244  14.9  48.5 2016  1  20  22  6.1  84  14.5  52.8 2016  1  20  23  0.2  263  14.0  58.2 2016  1  21  0  0.1  107  15.5  66.9 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  113 

2016  1  21  1 0.4 327 15.2  66.42016  1  21  2 5.1 278 15.5  65.82016  1  21  3 0.4 1 16.4  64.22016  1  21  4 2.1 159 18.2  57.62016  1  21  5 0.0 201 17.7  55.42016  1  21  6 1.2 266 19.5  53.72016  1  21  7 1.3 325 21.9  43.82016  1  21  8  0.7  320  21.7  42.2 2016  1  21  9  1.1  254  24.3  37.2 2016  1  21  10  0.1  55  25.6  30.1 2016  1  21  11  1.4  131  28.0  21.8 2016  1  21  12  0.2  301  28.3  20.7 2016  1  21  13  1.3  345  30.5  18.5 2016  1  21  14  1.2  315  30.8  13.0 2016  1  21  15  4.6  130  28.1  26.8 2016  1  21  16  0.7  2  24.9  32.8 2016  1  21  17 0.1 290 24.8  32.32016  1  21  18 1.0 314 21.6  44.42016  1  21  19 1.6 314 21.7  48.22016  1  21  20 1.2 329 19.8  51.52016  1  21  21 1.6 263 18.0  58.72016  1  21  22 10.3 279 17.4  59.82016  1  21  23 0.4 63 16.8  64.72016  1  22  0  1.1  320  17.6  42.0 2016  1  22  1  6.3  312  17.5  42.0 2016  1  22  2  2.9  271  17.2  41.4 2016  1  22  3  0.0  21  18.8  38.3 2016  1  22  4  0.3  202  20.0  38.0 2016  1  22  5  6.3  279  19.6  36.4 2016  1  22  6  0.8  342  21.1  34.6 2016  1  22  7  1.6  45  22.1  29.0 2016  1  22  8  0.8  272  23.0  28.1 2016  1  22  9  0.0  170  26.6  24.3 2016  1  22  10 1.2 159 26.5  22.22016  1  22  11 0.8 241 29.0  18.12016  1  22  12 1.5 345 29.3  17.22016  1  22  13  4.8  9  31.3  14.1 2016  1  22  14 0.9 347 32.0  11.92016  1  22  15 1.5 43 28.9  18.82016  1  22  16  1.5  184  26.2  21.9 2016  1  22  17  1.5  337  25.4  22.5 2016  1  22  18  1.1  57  24.5  28.1 2016  1  22  19  0.7  35  23.2  28.4 2016  1  22  20  2.3  343  21.2  35.5 2016  1  22  21  1.3  331  19.9  37.4 2016  1  22  22  0.4  219  19.1  37.7 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  114 

2016  1  22  23 0.4 358 19.3  39.82016  1  23  0 0.2 32 16.4  56.12016  1  23  1 0.8 282 16.0  56.62016  1  23  2 0.3 5 16.4  55.72016  1  23  3 0.4 240 17.3  50.32016  1  23  4 0.2 230 19.1  49.42016  1  23  5 0.2 295 19.4  46.22016  1  23  6  5.1  276  20.5  45.8 2016  1  23  7  0.0  356  21.8  38.1 2016  1  23  8  0.0  247  24.6  37.7 2016  1  23  9  0.7  75  27.5  27.8 2016  1  23  10  4.9  306  28.6  27.8 2016  1  23  11  1.0  350  30.2  21.9 2016  1  23  12  0.3  178  31.7  16.1 2016  1  23  13  1.4  52  33.1  15.2 2016  1  23  14  1.1  354  32.4  13.8 2016  1  23  15 5.5 331 30.6  21.02016  1  23  16 1.6 64 27.2  26.42016  1  23  17 0.9 327 26.6  30.02016  1  23  18 1.4 317 24.1  34.52016  1  23  19 1.4 36 24.1  41.32016  1  23  20 1.2 261 19.6  45.32016  1  23  21 1.3 262 19.1  46.72016  1  23  22  0.2  4  19.2  51.2 2016  1  23  23  0.3  96  17.6  53.9 2016  1  24  0  1.4  89  16.2  66.5 2016  1  24  1  1.8  322  16.3  66.5 2016  1  24  2  0.1  128  16.7  65.0 2016  1  24  3  1.3  268  18.4  59.9 2016  1  24  4  0.3  321  18.6  57.8 2016  1  24  5  1.1  270  19.6  54.8 2016  1  24  6  0.6  305  19.4  56.3 2016  1  24  7  1.1  61  21.1  44.1 2016  1  24  8 0.7 357 24.2  44.62016  1  24  9 1.3 348 26.0  37.42016  1  24  10 1.6 62 27.7  34.42016  1  24  11  1.2  289  29.3  28.8 2016  1  24  12 1.4 328 31.8  20.62016  1  24  13 0.7 256 32.7  17.02016  1  24  14  0.3  268  32.7  17.0 2016  1  24  15  0.8  318  29.3  27.7 2016  1  24  16  0.8  342  27.4  31.8 2016  1  24  17  0.9  88  25.4  34.9 2016  1  24  18  1.3  252  23.7  45.6 2016  1  24  19  0.7  359  23.7  48.1 2016  1  24  20  1.3  334  19.9  53.2 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  115 

2016  1  24  21 1.1 344 18.6  58.32016  1  24  22 1.3 316 18.4  60.92016  1  24  23 1.7 324 17.4  63.42016  1  25  0 0.0 124 15.5  75.02016  1  25  1 0.1 219 15.3  75.02016  1  25  2 1.2 268 15.3  72.62016  1  25  3 5.2 96 17.4  70.92016  1  25  4  1.2  308  18.1  66.2 2016  1  25  5  0.8  317  18.2  62.6 2016  1  25  6  3.0  306  19.1  60.3 2016  1  25  7  0.9  323  21.8  54.4 2016  1  25  8  0.6  308  23.3  50.8 2016  1  25  9  3.2  352  24.9  38.4 2016  1  25  10  3.9  270  26.9  37.2 2016  1  25  11  0.1  213  29.5  30.2 2016  1  25  12  1.1  305  31.2  23.7 2016  1  25  13 0.2 9 30.8  21.92016  1  25  14 2.8 329 30.5  16.02016  1  25  15 1.6 3 29.5  25.42016  1  25  16 3.7 57 26.7  37.22016  1  25  17 0.8 137 25.9  38.42016  1  25  18 0.9 289 22.8  47.92016  1  25  19 1.6 321 22.5  49.02016  1  25  20  0.8  322  19.9  58.5 2016  1  25  21  4.6  139  18.9  62.6 2016  1  25  22  0.2  6  17.2  66.7 2016  1  25  23  0.4  63  17.0  70.9 2016  1  26  0  5.1  153  13.2  71.7 2016  1  26  1  2.1  298  13.0  73.4 2016  1  26  2  0.3  186  13.3  71.7 2016  1  26  3  0.6  344  14.6  69.9 2016  1  26  4  0.3  344  15.4  67.6 2016  1  26  5  0.7  142  15.7  64.7 2016  1  26  6 0.6 329 17.6  61.22016  1  26  7 1.1 330 19.6  56.02016  1  26  8 3.0 336 19.7  46.72016  1  26  9  0.1  132  22.8  39.2 2016  1  26  10 0.7 75 23.4  37.52016  1  26  11 1.1 3 25.8  28.22016  1  26  12  0.6  69  26.8  27.6 2016  1  26  13  4.0  243  27.6  18.9 2016  1  26  14  4.7  333  28.8  21.2 2016  1  26  15  1.5  247  25.0  27.0 2016  1  26  16  0.9  279  23.9  35.1 2016  1  26  17  1.2  326  22.8  40.9 2016  1  26  18  6.2  9  20.2  50.8 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  116 

2016  1  26  19 0.9 304 19.7  49.62016  1  26  20 0.6 317 16.7  60.12016  1  26  21 3.0 72 15.7  65.32016  1  26  22 6.7 315 14.8  65.32016  1  26  23 2.9 263 13.8  65.32016  1  27  0 1.0 275 16.5  88.02016  1  27  1 0.2 189 16.1  88.02016  1  27  2  1.0  328  16.1  87.5 2016  1  27  3  3.9  315  16.7  82.2 2016  1  27  4  0.7  257  17.3  78.5 2016  1  27  5  0.1  351  18.9  74.8 2016  1  27  6  0.3  263  19.4  76.3 2016  1  27  7  1.6  271  20.6  66.8 2016  1  27  8  1.6  281  21.8  62.6 2016  1  27  9  1.3  345  23.4  53.6 2016  1  27  10  5.5  54  23.8  51.4 2016  1  27  11 0.3 206 26.0  44.02016  1  27  12 0.7 303 26.2  45.12016  1  27  13 1.2 269 28.0  35.02016  1  27  14 1.4 41 26.8  37.72016  1  27  15 0.6 10 25.4  44.52016  1  27  16 1.5 295 23.4  54.62016  1  27  17 0.7 41 23.8  55.12016  1  27  18  1.2  262  21.6  66.8 2016  1  27  19  0.3  4  21.2  67.3 2016  1  27  20  0.0  87  18.6  77.4 2016  1  27  21  0.1  253  18.2  76.3 2016  1  27  22  0.3  251  18.4  78.5 2016  1  27  23  0.4  334  17.6  85.4 2016  1  28  0  1.3  339  14.7  83.5 2016  1  28  1  1.4  325  14.4  85.4 2016  1  28  2  0.2  352  14.7  84.1 2016  1  28  3  1.5  253  15.4  79.8 2016  1  28  4 6.8 305 16.9  77.92016  1  28  5 0.2 177 17.4  73.02016  1  28  6 0.9 268 19.2  70.52016  1  28  7  0.7  38  21.9  63.7 2016  1  28  8 0.8 256 22.8  59.32016  1  28  9 3.4 327 24.6  47.62016  1  28  10  1.6  325  26.2  43.8 2016  1  28  11  0.8  37  27.9  33.3 2016  1  28  12  1.0  96  30.2  33.9 2016  1  28  13  1.1  252  31.5  27.7 2016  1  28  14  0.6  357  31.1  30.2 2016  1  28  15  0.4  185  28.9  34.5 2016  1  28  16  0.0  301  26.2  45.7 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  117 

2016  1  28  17 1.2 142 24.1  46.32016  1  28  18 0.9 10 22.6  57.52016  1  28  19 1.4 334 21.4  59.32016  1  28  20 1.3 55 19.2  68.02016  1  28  21 0.4 61 17.1  70.52016  1  28  22 6.7 56 17.1  79.22016  1  28  23 0.0 199 15.4  82.92016  1  29  0  0.8  312  17.0  88.1 2016  1  29  1  2.7  325  17.5  88.1 2016  1  29  2  0.2  219  17.2  88.7 2016  1  29  3  0.3  280  18.6  85.5 2016  1  29  4  1.5  331  19.4  79.6 2016  1  29  5  0.2  245  20.0  76.4 2016  1  29  6  0.2  144  21.5  71.8 2016  1  29  7  0.7  335  22.3  66.6 2016  1  29  8  0.3  226  24.4  64.0 2016  1  29  9 1.3 271 26.4  49.72016  1  29  10 0.7 335 27.9  50.42016  1  29  11 1.2 335 30.4  36.12016  1  29  12 1.5 317 31.2  35.42016  1  29  13 2.9 283 31.9  28.92016  1  29  14 1.1 306 32.8  29.62016  1  29  15 1.3 331 29.5  36.72016  1  29  16  0.3  204  28.2  45.8 2016  1  29  17  0.8  330  26.4  50.4 2016  1  29  18  0.2  264  24.7  64.0 2016  1  29  19  4.0  317  24.0  61.4 2016  1  29  20  1.3  286  21.2  73.8 2016  1  29  21  1.4  318  19.9  73.8 2016  1  29  22  0.7  128  19.6  80.3 2016  1  29  23  0.0  73  18.1  80.3 2016  1  30  0  1.8  336  18.7  77.6 2016  1  30  1  2.1  308  18.4  76.7 2016  1  30  2 0.0 308 18.3  77.62016  1  30  3 1.1 307 20.0  72.82016  1  30  4 0.2 323 19.7  72.82016  1  30  5  0.4  22  21.1  70.7 2016  1  30  6 0.4 49 20.8  65.12016  1  30  7 0.9 317 24.2  63.02016  1  30  8  1.1  309  25.0  56.5 2016  1  30  9  4.7  296  25.7  54.4 2016  1  30  10  1.4  89  27.5  47.9 2016  1  30  11  0.0  82  29.2  42.3 2016  1  30  12  1.6  100  31.3  37.2 2016  1  30  13  1.1  332  30.7  36.7 2016  1  30  14  0.6  330  31.7  35.9 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  118 

2016  1  30  15 0.8 249 29.6  45.82016  1  30  16 2.8 254 27.0  49.62016  1  30  17 1.6 75 26.0  53.52016  1  30  18 1.1 130 25.0  59.52016  1  30  19 1.1 315 23.0  59.12016  1  30  20 1.1 69 21.5  69.42016  1  30  21 2.8 52 20.4  69.02016  1  30  22  0.8  99  19.8  73.3 2016  1  30  23  4.5  38  19.8  73.3 2016  1  31  0  0.4  14  18.1  84.3 2016  1  31  1  0.4  152  18.3  86.5 2016  1  31  2  0.3  94  18.4  85.9 2016  1  31  3  0.0  109  19.5  83.2 2016  1  31  4  1.3  306  20.4  76.6 2016  1  31  5  0.6  313  21.5  76.6 2016  1  31  6  0.9  238  22.2  73.3 2016  1  31  7 2.7 92 23.0  66.72016  1  31  8 1.5 287 25.0  62.32016  1  31  9 0.8 276 25.8  52.42016  1  31  10 1.5 45 26.7  53.52016  1  31  11 0.7 86 28.5  43.62016  1  31  12 0.8 345 29.2  37.52016  1  31  13 1.6 275 31.3  34.22016  1  31  14  0.2  43  30.9  35.9 2016  1  31  15  1.3  79  28.6  44.7 2016  1  31  16  0.8  324  27.1  53.5 2016  1  31  17  0.2  292  26.3  55.7 2016  1  31  18  0.1  58  23.9  63.9 2016  1  31  19  1.1  332  23.6  67.8 2016  1  31  20  1.4  348  22.2  76.0 2016  1  31  21  1.4  71  21.4  76.0 2016  1  31  22  0.0  71  20.4  76.0 2016  1  31  23  0.0  21  20.1  81.5 2016  2  1  0 0.1 43 18.6  84.32016  2  1  1 1.2 308 18.0  85.92016  2  1  2 0.4 53 18.3  86.52016  2  1  3  0.0  283  19.7  82.6 2016  2  1  4 0.4 348 20.5  76.62016  2  1  5 0.8 315 20.7  76.62016  2  1  6  0.3  70  21.4  70.5 2016  2  1  7  1.3  334  22.5  70.5 2016  2  1  8  0.0  249  24.9  63.9 2016  2  1  9  1.6  355  25.7  52.4 2016  2  1  10  0.1  110  27.1  54.0 2016  2  1  11  1.0  340  29.9  43.6 2016  2  1  12  1.1  288  30.6  39.7 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  119 

2016  2  1  13 5.5 131 30.9  37.52016  2  1  14 0.9 320 30.7  33.72016  2  1  15 1.2 323 28.6  45.82016  2  1  16 1.0 342 26.7  49.62016  2  1  17 1.5 79 26.8  54.62016  2  1  18 2.1 77 24.2  62.32016  2  1  19 2.6 330 23.9  66.12016  2  1  20  0.3  245  20.9  73.3 2016  2  1  21  1.4  315  21.2  73.3 2016  2  1  22  1.4  101  19.7  79.3 2016  2  1  23  0.1  358  19.3  81.0 2016  2  2  0  0.0  172  17.3  74.0 2016  2  2  1  0.4  62  17.3  75.0 2016  2  2  2  0.4  109  17.6  73.5 2016  2  2  3  0.9  3  18.4  71.0 2016  2  2  4  2.1  306  20.2  66.5 2016  2  2  5 0.0 71 20.7  68.52016  2  2  6 1.3 75 21.2  61.02016  2  2  7 4.0 341 23.7  60.02016  2  2  8 0.6 323 24.8  51.52016  2  2  9 0.3 356 26.8  46.52016  2  2  10 0.7 40 26.6  42.02016  2  2  11 3.3 275 30.6  35.52016  2  2  12  1.0  241  31.2  36.0 2016  2  2  13  4.8  334  32.5  28.0 2016  2  2  14  0.6  240  31.9  28.5 2016  2  2  15  1.6  340  30.0  38.5 2016  2  2  16  0.8  315  27.9  45.5 2016  2  2  17  0.7  309  27.4  45.0 2016  2  2  18  1.6  355  23.9  53.5 2016  2  2  19  4.4  351  23.9  58.0 2016  2  2  20  1.2  87  21.2  62.0 2016  2  2  21  0.8  340  20.2  65.0 2016  2  2  22 1.4 321 20.0  66.52016  2  2  23 2.0 243 17.8  69.52016  2  3  0 1.9 282 15.2  82.42016  2  3  1  0.9  331  15.0  81.8 2016  2  3  2 6.7 317 15.5  81.12016  2  3  3 2.0 291 17.0  76.22016  2  3  4  0.9  305  17.9  76.8 2016  2  3  5  5.9  256  17.6  71.2 2016  2  3  6  0.3  256  18.4  68.1 2016  2  3  7  1.3  312  21.6  57.6 2016  2  3  8  0.4  161  22.1  53.2 2016  2  3  9  1.3  278  24.7  48.9 2016  2  3  10  1.0  347  26.4  39.6 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  120 

2016  2  3  11 1.1 336 28.3  34.62016  2  3  12 1.4 42 30.6  33.42016  2  3  13 0.9 342 30.5  27.22016  2  3  14 3.9 336 31.2  25.32016  2  3  15 0.8 83 28.3  30.92016  2  3  16 1.3 22 26.6  45.82016  2  3  17 0.8 268 26.1  42.72016  2  3  18  5.3  322  22.8  53.2 2016  2  3  19  1.3  71  22.0  56.3 2016  2  3  20  0.4  340  18.9  70.0 2016  2  3  21  0.9  303  17.7  73.7 2016  2  3  22  0.2  34  18.1  72.5 2016  2  3  23  0.2  319  15.9  74.9 2016  2  4  0  2.1  339  14.3  81.4 2016  2  4  1  0.6  316  14.2  80.2 2016  2  4  2  0.2  252  14.5  81.4 2016  2  4  3 4.3 260 15.4  74.92016  2  4  4 4.8 316 16.4  73.22016  2  4  5 0.2 78 17.8  67.82016  2  4  6 1.3 346 18.8  64.32016  2  4  7 1.3 319 20.1  56.02016  2  4  8 0.5 310 22.0  54.32016  2  4  9 1.5 73 23.9  44.82016  2  4  10  0.9  348  24.4  43.1 2016  2  4  11  0.1  170  27.0  33.0 2016  2  4  12  0.2  45  29.2  27.7 2016  2  4  13  1.4  37  28.7  27.1 2016  2  4  14  1.6  260  28.4  28.3 2016  2  4  15  0.9  287  27.1  37.2 2016  2  4  16  0.9  342  24.4  45.4 2016  2  4  17  0.0  172  23.4  46.6 2016  2  4  18  0.9  351  22.0  56.0 2016  2  4  19  3.3  341  19.8  59.0 2016  2  4  20 7.4 314 17.5  66.72016  2  4  21 1.9 74 16.9  73.22016  2  4  22 0.0 147 15.8  74.92016  2  4  23  1.5  133  14.8  79.1 2016  2  5  0 0.0 357 16.4  88.72016  2  5  1 2.6 307 16.4  89.32016  2  5  2  0.0  310  16.5  89.3 2016  2  5  3  3.5  266  17.4  84.6 2016  2  5  4  0.1  300  18.6  80.6 2016  2  5  5  2.0  338  18.1  75.3 2016  2  5  6  4.8  294  19.9  72.6 2016  2  5  7  1.4  310  21.5  69.2 2016  2  5  8  0.3  26  22.1  59.9 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  121 

2016  2  5  9 0.9 271 24.3  52.52016  2  5  10 4.1 95 25.0  44.42016  2  5  11 3.9 49 26.5  37.12016  2  5  12 5.2 53 26.4  33.12016  2  5  13 3.7 312 27.8  23.72016  2  5  14 1.2 313 28.6  26.42016  2  5  15 5.5 48 26.5  35.72016  2  5  16  3.2  273  24.8  47.1 2016  2  5  17  1.3  23  24.5  48.5 2016  2  5  18  0.7  253  21.2  56.5 2016  2  5  19  0.1  251  21.5  61.9 2016  2  5  20  2.5  307  19.3  75.9 2016  2  5  21  0.8  41  18.7  73.3 2016  2  5  22  8.5  261  18.0  78.6 2016  2  5  23  2.1  306  16.9  81.3 2016  2  6  0  1.4  315  17.6  88.1 2016  2  6  1 1.4 270 17.1  88.72016  2  6  2 1.7 293 17.6  88.72016  2  6  3 0.3 337 18.3  85.02016  2  6  4 0.0 47 18.2  80.62016  2  6  5 4.8 95 18.8  74.92016  2  6  6 2.4 260 19.5  74.92016  2  6  7 0.1 45 21.1  61.72016  2  6  8  1.6  347  22.0  59.8 2016  2  6  9  1.4  5  24.2  52.2 2016  2  6  10  3.4  267  23.8  47.2 2016  2  6  11  0.4  202  25.3  42.8 2016  2  6  12  0.9  272  27.2  32.0 2016  2  6  13  3.8  336  27.7  27.0 2016  2  6  14  0.1  158  27.5  27.0 2016  2  6  15  1.1  321  26.1  39.0 2016  2  6  16  0.5  61  24.6  47.8 2016  2  6  17  2.0  46  24.0  50.3 2016  2  6  18 1.3 253 21.4  62.32016  2  6  19 0.6 281 20.9  64.22016  2  6  20 1.5 279 20.1  72.42016  2  6  21  1.5  336  19.2  80.6 2016  2  6  22 0.4 215 18.8  83.12016  2  6  23 2.0 270 17.9  83.12016  2  7  0  0.8  319  17.0  88.9 2016  2  7  1  0.1  293  17.3  88.4 2016  2  7  2  0.3  171  17.4  88.4 2016  2  7  3  0.1  78  18.1  84.5 2016  2  7  4  0.5  246  18.1  83.4 2016  2  7  5  0.6  326  19.4  78.5 2016  2  7  6  1.3  294  19.3  74.1 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  122 

2016  2  7  7 5.5 330 21.1  66.92016  2  7  8 3.6 307 21.4  67.52016  2  7  9 0.6 305 23.2  58.12016  2  7  10 3.2 341 24.2  52.12016  2  7  11 1.3 271 26.4  44.92016  2  7  12 4.8 267 25.8  45.52016  2  7  13 0.3 217 27.9  40.52016  2  7  14  1.1  342  27.3  37.2 2016  2  7  15  1.1  35  25.9  43.3 2016  2  7  16  2.8  51  24.6  54.8 2016  2  7  17  1.5  330  23.7  59.2 2016  2  7  18  2.3  275  22.2  65.3 2016  2  7  19  1.4  132  21.1  70.8 2016  2  7  20  1.2  316  19.9  74.1 2016  2  7  21  1.4  257  19.8  81.2 2016  2  7  22  2.2  91  18.2  82.3 2016  2  7  23 1.8 314 18.2  87.32016  2  8  0 0.1 6 14.0  82.02016  2  8  1 0.0 54 14.5  81.62016  2  8  2 1.1 100 14.5  82.02016  2  8  3 1.1 261 15.9  78.22016  2  8  4 5.7 317 15.8  78.22016  2  8  5 0.0 276 17.4  75.32016  2  8  6  4.9  47  18.6  71.0 2016  2  8  7  1.1  320  19.6  63.8 2016  2  8  8  0.8  55  21.7  62.8 2016  2  8  9  1.0  99  24.4  54.2 2016  2  8  10  1.0  49  24.4  50.4 2016  2  8  11  0.6  76  26.8  46.0 2016  2  8  12  0.8  322  27.8  42.2 2016  2  8  13  0.0  47  28.4  36.4 2016  2  8  14  0.7  336  29.4  37.9 2016  2  8  15  1.6  335  26.8  44.6 2016  2  8  16 1.5 320 24.1  54.22016  2  8  17 0.2 181 24.4  55.22016  2  8  18 0.2 126 21.5  61.42016  2  8  19  4.0  336  21.2  63.3 2016  2  8  20 2.1 143 18.0  70.52016  2  8  21 0.7 321 16.4  73.42016  2  8  22  0.2  270  15.8  73.4 2016  2  8  23  0.2  99  14.8  80.1 2016  2  9  0  1.0  130  17.3  87.3 2016  2  9  1  0.3  6  17.1  88.4 2016  2  9  2  0.7  252  17.7  86.8 2016  2  9  3  0.4  321  19.0  81.7 2016  2  9  4  0.0  6  19.1  78.9 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  123 

2016  2  9  5 0.4 327 20.1  75.62016  2  9  6 0.6 46 20.3  76.72016  2  9  7 1.6 244 21.7  66.62016  2  9  8 1.2 348 22.6  64.42016  2  9  9 0.7 67 25.5  56.52016  2  9  10 1.2 332 25.5  53.22016  2  9  11 0.2 23 28.1  45.32016  2  9  12  0.4  273  28.6  35.8 2016  2  9  13  0.4  219  29.6  34.1 2016  2  9  14  0.8  240  29.6  34.1 2016  2  9  15  0.6  63  27.4  44.8 2016  2  9  16  0.7  353  25.6  52.6 2016  2  9  17  0.6  80  24.4  52.6 2016  2  9  18  1.6  2  22.2  62.7 2016  2  9  19  0.4  311  22.7  68.3 2016  2  9  20  0.2  259  20.6  76.1 2016  2  9  21 1.4 313 19.5  77.22016  2  9  22 6.5 315 19.0  81.72016  2  9  23 0.4 331 19.0  80.62016  2  10  0 2.0 125 19.6  87.42016  2  10  1 1.8 89 19.3  88.02016  2  10  2 3.0 309 19.6  89.32016  2  10  3 0.4 285 20.3  86.02016  2  10  4  0.3  313  21.0  82.1 2016  2  10  5  1.5  309  21.2  76.1 2016  2  10  6  1.3  294  21.5  74.2 2016  2  10  7  0.6  1  23.1  62.9 2016  2  10  8  0.2  192  23.6  62.9 2016  2  10  9  4.3  51  25.6  47.1 2016  2  10  10  4.9  157  26.5  46.4 2016  2  10  11  3.5  326  27.8  35.2 2016  2  10  12  1.4  263  28.0  35.2 2016  2  10  13  1.4  7  29.6  25.3 2016  2  10  14 1.3 78 29.7  28.02016  2  10  15 1.3 56 28.1  34.62016  2  10  16 1.4 329 26.4  50.42016  2  10  17  5.5  308  25.7  51.7 2016  2  10  18 0.6 85 24.5  61.62016  2  10  19 1.2 77 23.2  66.22016  2  10  20  5.5  77  21.4  70.9 2016  2  10  21  1.2  257  21.5  79.4 2016  2  10  22  1.6  335  20.3  78.8 2016  2  10  23  0.2  309  20.4  86.7 2016  2  11  0  1.4  306  19.1  82.0 2016  2  11  1  2.2  280  19.1  82.3 2016  2  11  2  0.2  138  19.2  82.3 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  124 

2016  2  11  3 0.4 209 19.9  81.32016  2  11  4 0.8 256 20.4  76.42016  2  11  5 0.2 279 20.4  76.02016  2  11  6 0.6 341 21.2  74.3Interpretation: Meteorological parameters such as wind, temperature and humidity was carried out in the month of January and February 2016. Maximum wind speed for months of January and February is about 10.3 m/s, Temperature is mostly humid with maximum humidity is 90 % and minimum humidity being 9.6%.Highest temperature for these months is 33.1 (°C) while lowest is 12.2 (°C). 

3.12.2.5. Tides 

The tidal variations in Mumbai waters are mainly semi‐diurnal but with an appreciable diurnal element which produces unequal tides on most days and causes wide variations in extreme levels such that the lowest HW is actually lower than the highest LW. Generally in the narrow estuarine areas, spatial variation of tide is likely to be prominent and the area like Kundalika River is not an exception and there is significant variation in high water levels as one moves upstream compared to open area water levels. This results increased tidal current upstream of river. The excursion length ranges almost 25 km during flood conditions. The tidal data for tidal cycle of 15 days was collected  at  existing  jetty  location  (Latitude  18˚  32’16.17  N  and  Longitude  72˚  55’  29.73  E) situated near the mouth of Kundalika River. The data was collected. at a sampling interval of 15 mins. The lowest tidal level is 0.23 m CD and highest level is 3.9 m. The maximum tidal range is 3.5 m, and minimum tidal range is 1.9 m. All levels are with respect to chart datum. 

3.12.2.6. Currents 

The measurement of current data at C1 (latitude 18º 32’ 26” N & longitude 72” 54’ 46” E) & C2 (latitude 18” 32’ 30” N & longitude 72” 57’ 30” E) carried out. The observations were carried out at surface, mid depth and 1m above seabed level. These data were collected simultaneously at 15 minutes  interval  for  which  the  tidal  data  was  also  collected.    The  typical  plot  of  current strength and direction at C1 and C2  locations are shown in Figure 3.2 and 3.3. The data at C2 indicates that strength of current at mid depth is as high as 1.60 m/s. It also indicates that during the flood the predominant direction varies between 115° and 125°, while during ebb flow the direction is steady and is at 295° with respect to north. The current strength measured at 1 m depth  below the surface indicates that maximum strength.  

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  125 

Figure 3.12 Data collection stations

Figure 3.13 Measured Current Strength and Direction at Location C1

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  126 

Figure 3.14 Measured Current Strength and Direction at Location C2

3.12.2.7. Waves 

Mathematical Model Studies carried out at CWPRS, Pune.   It  indicates  that  the  average  wave period varies between 5 sec & 9 sec. The wave height during non‐monsoon period varies from 3 m to 4.5 m while during monsoon it varies between 4.5 m & 7.5 m, depending on the direction of waves. Due to presence of Korlai headland at the mouth of the Kundalika River at the south bank & sand bar at the entrance in the eastern side extending up to the northern side of Salav Bridge, there is an attenuation of wave heights reaching the bay. 

From the above it is clear that for any structure designed inside the creek waves coming from above N, NNW, NWN, WNW & W are important. Proposed jetty is sheltered from ocean waves & will be subject only to tidal currents & occasional swells. 

3.13. AIR QUALITY 

Air quality monitoring was carried out at eight (8) locations along the proposed project area in one season. The baseline Ambient Air Quality data of the region has also been obtained. 

a) Selection of Monitoring Stations 

The monitoring stations were selected considering the spatial relationship of various  land use along the project road & wind direction  in accordance with BIS guidelines [IS: 5182 (part‐14)‐1985].    This  project  neither  in  construction  phase  nor  in  operational  phase will  have  any  far reaching effect on environmental settings in 5‐10 km radius area. Although surveys have been carried out up to 10 km emphasis is up to 2 km radius from the project area. 

b) Monitoring Methodology 

Monitoring of ambient air quality was carried out as per CPCB guidelines. The NOx concentration was analyzed as per modified West & Geake method & SO2 concentration analyzed as per Jacob 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  127 

& Hochheise. Ambient Air Quality Standards stipulated by CPCB are presented in Table 3.8.The ambient air monitoring has been carried out at all the six segments mentioned.  

Table 3.8 Ambient Air Quality Monitoring Standards (CPCB)

Pollutant  Time Weighted

Average 

Concentration in Ambient Air 

Industrial, 

Residential,  Rural 

and other areas 

Ecologically Sensitive 

areas  notified  by 

Central Government 

Sulphur  Dioxide  (SO2) (g/m3) 

Annual Average* 24 hours** 

50 80 

20 80 

Oxides  of  Nitrogen (NOx) (g/m3) 

Annual Average* 24 hours** 

40 80 

30 80 

Particulate  Matter (PM10) (g/m3) 

Annual Average* 24 hours** 

60 100 

60 100 

Particulate  matter (PM2.5) (g/m3) 

Annual Average* 24 hours** 

40 60 

40 60 

Carbon  Monoxide (CO) (mg/m3) 

8 hours**1 hour 

0204 

02 04 

Table 3.9 Techniques for Measurement of Pollutants

Sr.  

No. Pollutant  Code Of Practice 

Methods  Of 

Measurement 

Minimum 

Detectable Limit 

1 Sulphur  Dioxide (SO2)  

IS‐5182  (Part‐II):2001 RA 2012 

Improved  West  and Geake 

6.5 µg/m3 

2 Nitrogen  Dioxide (NO2)  

IS‐5182  (Part‐VI): 2006 RA 2012 

Modified  Jacob  & Hochheiser  (Na‐Arsenite) 

4.0 µg/m3 

3 Particulate  Matter (size  less  than  10 µm) or PM10  

IS‐5182 (PART‐23):2006  & CPCB Guidelines 

Gravimetric 

10 µg/m3 

4 Particulate  Matter (size  less  than  2.5 µm) or PM2.5 

5 µg/m3 

5  Ozone (O3)  IS‐5182  (Part‐IX):1974  &  CPCB Guidelines 

Spectrophotometric  Method 

1 µg/m3 

6 Carbon  Monoxide (CO)  

IS:  5182  (Part‐X)  & CPCB Guidelines 

Non  Dispersive  Infra Red  (NDIR) spectroscopy 

0.1 mg/m3 

7  Ammonia (NH3)  APHA,  (Method‐401) & CPCB Guidelines 

Indophenol  blue method 

6 µg/m3 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  128 

8  Benzene (C6H6)  IS‐5182  (Part‐XI):2006  &  CPCB Guidelines 

Gas Chromatography  1.0 µg/m3 

9 Benzo  (a)  Pyrene (BaP)  –  particulate phase only,  

IS‐5182  (Part‐XII):2004  &  CPCB Guidelines 

Solvent  extraction followed  by  HPLC analysis 

0.5 ng/m3 

10  Lead (Pb)   USEPA/625/R‐96/0109/IO‐3.1&  3.2 & CPCB Guidelines 

AAS method 0.1 µg/m3 

11  Arsenic (As)   1 ng/m3 12   Nickel (Ni)   1 ng/m3 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy International Ltd. 

TEPL/ENV/CBS/2021‐05  129  

Table 3.10 Ambient Air Monitoring Report

Location (01) : Project Site  Date  of Monitoring 

 WEEK 

 PM10 

 PM2.5 

 SO2 

 NOX 

 Pb 

 NH3 

 C6H6 

O3  As  Ni  B‐(a)‐P 

CO 0600 ‐ 1400 

1400 ‐ 2200 

2200 ‐ 0600 

0600 ‐ 1400 

1400 ‐ 2200 

2200 ‐ 0600

µg/m3  ng/m3  mg/m3 14/1/2016  I  41.8  14.5  6.8  13.4  <0.1  8.6  <1.0  6.2  5.6  6.3  <1.0  <1.0  <0.5  0.41  0.82  0.60 19/1/2016  45.6  15.7  7.1  14.0  <0.1  9.7  <1.0  5.7  4.9  6.6  <1.0  <1.0  <0.5  0.84  0.70  0.57 21/1/2016  II  43.3  15.1  7.3 14.3 <0.1 9.2 <1.0 5.4 4.3  6.8 <1.0 <1.0 <0.5 0.65 0.78 0.8127/1/2016  42.7  14.6  6.6  13.0  <0.1  10.7  <1.0  4.8  3.2  7.7  <1.0  <1.0  <0.5  0.81  0.42  0.47 29/1/2016  III  44.9  15.5  7.0  13.7  <0.1  10.2  <1.0  5.2  7.4  4.1  <1.0  <1.0  <0.5  0.80  0.45  0.46 02/02/2016  42.0  14.2  6.8  13.2  <0.1  9.9  <1.0  7.3  6.2  4.5  <1.0  <1.0  <0.5  0.58  0.83  0.57 04/02/2016  IV  40.6  13.4  6.5 12.7 <0.1 8.8 <1.0 4.2 5.0  4.0 <1.0 <1.0 <0.5 0.70 0.57 0.6809/02/2016  41.3  13.8  6.9  13.5  <0.1  9.7  <1.0  3.6  7.5  5.3  <1.0  <1.0  <0.5  0.48  0.72  0.38 CPCB Limits  100  60  80  80  1  400  5    100    6  20  1    2   Minimum  40.6  13.4  6.5  12.7  <0.1  8.6  <1.0  3.2  <1.0  <1.0  <0.5  0.38 Maximum  45.6  15.7  7.3 14.3 <0.1 10.7 <1.0 7.7 <1.0 <1.0 <0.5 0.84Average  42.78  14.60  6.88  13.48 –  9.60  –  5.49  –  –  –  0.63 

Location (02) : Bagmala  Date  of Monitoring 

 WEEK 

 PM10 

 PM2.5 

 SO2 

 NOX 

 Pb 

 NH3 

 C6H6

O3  As  Ni  B‐(a)‐P 

CO 0600 ‐ 1400 

1400 ‐ 2200 

2200 ‐ 0600 

0600 ‐ 1400 

1400 ‐ 2200 

2200 ‐ 0600

µg/m3  ng/m3  mg/m3 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy International Ltd. 

TEPL/ENV/CBS/2021‐05  130  

14/1/2016  I  45.8  15.7  7.8 15.5 <0.1 9.1 <1.0 5.4 4.3  6.4 <1.0 <1.0 <0.5 0.92 0.59 0.9219/1/2016  48.2  16.6  7.3 14.3 <0.1 9.7 <1.0 5.1 4.7  3.8 <1.0 <1.0 <0.5 0.86 0.84 0.9021/1/2016  II  51.3  17.8  8.1  16.1  <0.1  10.4  <1.0  6.9  4.0  6.2  <1.0  <1.0  <0.5  0.72  0.96  0.56 27/1/2016  46.1  15.5  8.4  16.7  <0.1  10.8  <1.0  4.6  4.4  5.7  <1.0  <1.0  <0.5  0.40  0.49  0.80 29/1/2016  III  43.7  15.8  8.7  17.2  <0.1  9.9  <1.0  4.2  5.1  6.8  <1.0  <1.0  <0.5  0.61  0.92  0.76 02/02/2016  52.6  17.2  7.4 14.5 <0.1 9.5 <1.0 5.7 6.3  4.6 <1.0 <1.0 <0.5 0.91 0.82 0.8704/02/2016  IV  50.1  17.2  7.9  15.6  <0.1  8.6  <1.0  5.4  4.1  6.7  <1.0  <1.0  <0.5  0.58  0.81  0.63 09/02/2016  47.3  16.3  9.2  17.5  <0.1  9.4  <1.0  7.2  7.6  5.1  <1.0  <1.0  <0.5  0.87  0.61  0.54 CPCB Limits  100  60  80  80  1  400  5    100    6  20  1    2   Minimum  43.7  15.5  7.3 14.3 <0.1 8.6 <1.0 3.8 <1.0 <1.0 <0.5 0.40Maximum  52.6  17.8  9.2  17.5  <0.1  10.8  <1.0  7.6  <1.0  <1.0  <0.5  0.96 Average  48.14  16.51  8.10  15.93 –  9.68  –  5.43  –  –  –  0.75 Location (03) : Walke   Date  of Monitoring 

 WEEK 

 PM10 

 PM2.5  SO2  NOX  Pb  NH3  C6H6

O3 As Ni B‐(a)‐P 

CO0600 ‐ 1400 

1400 ‐ 2200 

2200 ‐ 0600 

0600 ‐ 1400 

1400 ‐ 2200 

2200 ‐ 0600

µg/m3  ng/m3  mg/m3 14/1/2016  I  47.6  17.7  7.5  14.7  <0.1  8.9  <1.0  6.9  7.8  7.1  <1.0  <1.0  <0.5  0.70  0.42  0.69 19/1/2016  52.4  19.2  8.1  16.1  <0.1  9.5  <1.0  5.7  4.6  7.9  <1.0  <1.0  <0.5  0.75  0.69  0.48 21/1/2016  II  46.8  17.5  8.4  16.5  <0.1  10.4  <1.0  4.0  5.3  5.8  <1.0  <1.0  <0.5  0.65  0.78  0.54 27/1/2016  51.0  19.1  7.8  15.3  <0.1  9.8  1.14  6.2  3.5  7.4  <1.0  <1.0  <0.5  0.85  0.46  0.82 29/1/2016  III  53.0  18.5  8.2  16.2  <0.1  10.2  <1.0  5.8  4.1  6.2  <1.0  <1.0  <0.5  0.82  0.79  0.53 02/02/2016  49.3  18.3  8.6  17.0  <0.1  9.9  <1.0  7.1  5.2  6.0  <1.0  <1.0  <0.5  0.60  0.43  0.77 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy International Ltd. 

TEPL/ENV/CBS/2021‐05  131  

04/02/2016  IV  48.0  17.5  7.2 14.5 <0.1 10.8 1.06 7.2 4.0  6.1 <1.0 <1.0 <0.5 0.41 0.87 0.8009/02/2016  50.8  18.2  8.2  16.2  <0.1  10.3  <1.0  6.8  5.8  7.1  <1.0  <1.0  <0.5  0.55  0.83  0.62 CPCB Limits  100  60  80  80  1  400  5    100    6  20  1    2   Minimum  46.8  17.5  7.2  14.5  <0.1  8.9  1.06  3.5  <1.0  <1.0  <0.5  0.41 Maximum  53.0  19.2  8.6 17.0 <0.1 10.8 1.14 7.9 <1.0 <1.0 <0.5 0.87Average  49.86  18.25  8.00  15.81 –  9.98  1.10  5.98  –  –  –  0.66 Location (04) : Mandala 

 Date  of Monitoring 

 WEEK 

 PM10 

 PM2.5 

 SO2 

 NOX 

 Pb 

 NH3 

 C6H6

O3  As  Ni  B‐(a)‐P 

CO 0600 ‐ 1400 

1400 ‐ 2200 

2200 ‐ 0600 

0600 ‐ 1400 

1400 ‐ 2200 

2200 ‐ 0600

µg/m3  ng/m3  mg/m3 15/1/2016  I  48.0  17.7  7.6 15.1 <0.1 9.4 <1.0 6.7 7.0  4.8 <1.0 <1.0 <0.5 0.43 0.56 0.4618/1/2016  50.6  18.2  8.9  17.5  <0.1  9.9  <1.0  5.1  7.3  5.7  <1.0  <1.0  <0.5  0.40  0.72  0.55 22/1/2016  II  51.3  18.6  8.5 16.7 <0.1 10.3 <1.0 4.9 5.5  3.2 <1.0 <1.0 <0.5 0.43 0.46 0.6325/1/2016  52.4  19.1  8.1  15.5  <0.1  10.6  <1.0  4.8  5.9  3.7  <1.0  <1.0  <0.5  0.97  0.69  0.41 30/1/2016  III  49.3  17.8  9.5  18.9  <0.1  9.2  <1.0  7.6  7.0  5.5  <1.0  <1.0  <0.5  0.56  0.94  0.41 01/02/2016  54.1  19.5  9.2  18.1  <0.1  8.5  1.03  4.7  5.1  6.0  <1.0  <1.0  <0.5  1.01  0.42  0.62 05/02/2016  IV  51.7  18.8  8.4 16.5 <0.1 9.6 <1.0 6.2 4.5  5.8 <1.0 <1.0 <0.5 0.66 0.86 0.5208/02/2016  52.2  19.0  8.7  17.2  <0.1  9.1  <1.0  5.3  4.2  7.7  <1.0  <1.0  <0.5  0.84  0.87  0.53 CPCB Limits  100  60  80  80  1  400  5    100    6  20  1    2   Minimum  48.0  17.7  7.6  15.1  <0.1  8.5  1.03  3.2  <1.0  <1.0  <0.5  0.40 Maximum  54.1  19.5  9.5 18.9 <0.1 10.6 1.03 7.7 <1.0 <1.0 <0.5 1.01Average  51.20  18.59  8.61  16.94 –  9.58  1.03  5.59  –  –  –  0.62 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy International Ltd. 

TEPL/ENV/CBS/2021‐05  132  

Location (05) : Vave 

 Date  of Monitoring 

 WEEK 

 PM10 

 PM2.5 

 SO2 

 NOX 

 Pb 

 NH3 

 C6H6

O3  As  Ni  B‐(a)‐P 

CO 0600 ‐ 1400

1400 ‐ 2200 

2200 ‐ 0600 

0600 ‐ 1400 

1400 ‐ 2200 

2200 ‐ 0600

µg/m3  ng/m3  mg/m3 15/1/2016  I  48.9  17.8  7.9  15.6  <0.1  9.5  <1.0  4.3  5.6  6.2  <1.0  <1.0  <0.5  0.66  0.87  0.83 18/1/2016  52.4  19.2  8.4 16.4 <0.1 10.7 <1.0 5.0 7.2  5.9 <1.0 <1.0 <0.5 0.87 0.77 0.9022/1/2016  II  45.6  16.6  9.5  18.7  <0.1  9.8  <1.0  7.0  4.1  5.2  <1.0  <1.0  <0.5  0.96  0.55  0.98 25/1/2016  50.7  18.4  7.4  14.3  <0.1  10.0  <1.0  7.4  5.5  6.1  <1.0  <1.0  <0.5  0.92  0.70  0.56 30/1/2016  III  51.5  18.6  9.2  18.1  <0.1  10.4  <1.0  5.5  4.6  3.5  <1.0  <1.0  <0.5  0.75  0.58  0.70 01/02/2016  48.6  17.7  8.4 16.5 <0.1 9.7 <1.0 5.0 6.2  6.4 <1.0 <1.0 <0.5 0.46 0.73 0.4605/02/2016  IV  50.4  18.2  9.8  19.3  <0.1  10.2  <1.0  6.6  3.1  7.4  <1.0  <1.0  <0.5  0.78  0.50  0.93 08/02/2016  51.7  18.7  7.6  15.1  <0.1  9.9  <1.0  3.9  7.5  7.1  <1.0  <1.0  <0.5  0.98  0.89  0.77 CPCB Limits  100  60  80  80  1  400  5    100    6  20  1    2   Minimum  45.6  16.6  7.4 14.3 <0.1 9.5 <1.0 3.1 <1.0 <1.0 <0.5 0.46Maximum  52.4  19.2  9.8  19.3  <0.1  10.7  <1.0  7.5  <1.0  <1.0  <0.5  0.98 Average  49.98  18.15  8.53  16.75 –  10.03 –  5.68  –  –  –  0.75 Location (06) : Talekhar 

 Date  of Monitoring 

 WEEK 

 PM10 

 PM2.5 

 SO2 

 NOX 

 Pb 

 NH3 

 C6H6

O3  As  Ni  B‐(a)‐P 

CO 0600 ‐ 1400

1400 ‐ 2200 

2200 ‐ 0600

0600 ‐ 1400

1400 ‐ 2200

2200 ‐ 0600

µg/m3  ng/m3  mg/m3 15/1/2016  I  46.7  17.1  7.5 14.6 <0.1 9.8 <1.0 7.7 6.8  4.6 <1.0 <1.0 <0.5 1.02 0.99 1.03

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy International Ltd. 

TEPL/ENV/CBS/2021‐05  133  

18/1/2016  50.2  18.4  8.3 16.3 <0.1 10.8 <1.0 6.0 6.5  7.3 <1.0 <1.0 <0.5 0.75 0.91 0.8622/1/2016  II  48.3  17.6  8.7  17.1  <0.1  9.2  1.04  4.9  4.3  6.5  <1.0  <1.0  <0.5  0.93  0.56  0.57 25/1/2016  52.1  19.1  7.9  15.4  <0.1  8.7  <1.0  4.6  6.1  6.3  <1.0  <1.0  <0.5  0.56  0.59  0.71 30/1/2016  III  50.6  18.2  8.3  16.3  <0.1  9.6  <1.0  7.7  3.6  4.0  <1.0  <1.0  <0.5  0.96  0.77  0.59 01/02/2016  49.2  17.6  8.9 17.5 <0.1 10.5 <1.0 5.5 7.0  6.8 <1.0 <1.0 <0.5 0.52 0.76 0.5405/02/2016  IV  47.3  17.0  9.2  18.1  <0.1  9.7  1.11  6.3  7.3  3.6  <1.0  <1.0  <0.5  0.97  0.47  0.53 08/02/2016  51.1  18.4  8.0  15.8  <0.1  9.4  <1.0  7.8  5.7  4.3  <1.0  <1.0  <0.5  0.78  0.68  0.44 CPCB Limits  100  60  80  80  1  400  5    100    6  20  1    2   Minimum  46.7  17.0  7.5 14.6 <0.1 8.7 1.04 3.6 <1.0 <1.0 <0.5 0.44Maximum  52.1  19.1  9.2  18.1  <0.1  10.8  1.11  7.8  <1.0  <1.0  <0.5  1.03 Average  49.44  17.93  8.35  16.39 –  9.71  1.08  5.88  –  –  –  0.73 Location (07) : Salav 

  Date  of Monitoring   

  WEEK   

  PM10 

  PM2.5 

  SO2 

  NOX 

  Pb 

  NH3 

  C6H6

O3  As  Ni  B‐(a)‐P 

CO 0600 ‐ 1400 

1400 ‐ 2200 

2200 ‐ 0600 

0600 ‐ 1400 

1400 ‐ 2200 

2200 ‐ 0600 

µg/m3  ng/m3 mg/m314/1/2016  I  46.1  15.2  7.5  15  <0.1  9  <1.0  5.4  4.3  6.4  <1.0  <1.0  <0.5  0.92  0.59  0.92 19/1/2016  47.2  16.9  7  14.7  <0.1  9.2  <1.0  5.1  4.7  3.8  <1.0  <1.0  <0.5  0.86  0.84  0.9 21/1/2016  II  50.9  16.8  8.3 16.7 <0.1 10.1 <1.0 6.9 4  6.2 <1.0 <1.0 <0.5 0.72 0.96 0.5627/1/2016  45.8  15.1  8.4  16.3  <0.1  10.5  <1.0  4.6  4.4  5.7  <1.0  <1.0  <0.5  0.4  0.49  0.8 29/1/2016  III  42.8  15.7  8.8 17.1 <0.1 9.6 <1.0 4.2 5.1  6.8 <1.0 <1.0 <0.5 0.61 0.92 0.762/2/2016  51.6  17.3  7.2 15 <0.1 9.2 <1.0 5.7 6.3  4.6 <1.0 <1.0 <0.5 0.91 0.82 0.874/2/2016  IV  49.7  16.9  7.5 15.1 <0.1 8.8 <1.0 5.4 4.1  6.7 <1.0 <1.0 <0.5 0.58 0.81 0.639/2/2016  46.8  16.4  9.1 17 <0.1 9.1 <1.0 7.2 7.6  5.1 <1.0 <1.0 <0.5 0.87 0.61 0.54CPCB Limits  100  60  80 80 1 400 5 100 6 20 1 2

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy International Ltd. 

TEPL/ENV/CBS/2021‐05  134  

Minimum  42.8  15.1  7 14.7 <0.1 8.8 <1.0 3.8 <1.0 <1.0 <0.5 0.4Maximum  51.6  17.3  9.1 17.1 <0.1 10.8 <1.0 7.6 <1.0 <1.0 <0.5 0.96Average  47.61  16.29  7.98  15.86 –  9.44  –  5.43  –  –  –  0.75 Location (08) : Korlai  

            O3 As Ni B‐(a)‐P 

CODate  of Monitoring 

WEEK  PM10  PM2.5  SO2  NOX  Pb  NH3  C6H6 0600 ‐ 1400

1400 ‐ 2200 

2200 ‐ 0600

0600 ‐ 1400

1400 ‐ 2200

2200 ‐ 0600

      µg/m3  ng/m3  mg/m3 14/1/2016  I  45.5  15  7.7  15.7  <0.1  9.8  <1.0  5.1  4.5  6.6  <1.0  <1.0  <0.5  0.95  0.55  0.89 19/1/2016  48.1  16.2  7.2  14.2  <0.1  9.1  <1.0  5.3  5.1  3.5  <1.0  <1.0  <0.5  0.78  0.82  0.91 21/1/2016  II  51.2  16  8  16.3  <0.1  10.3  <1.0  6.5  4.3  6.7  <1.0  <1.0  <0.5  0.69  0.94  0.6 27/1/2016  46  15.2  8.1  16.6  <0.1  10.1  <1.0  4.1  4.2  5.2  <1.0  <1.0  <0.5  0.45  0.51  0.78 29/1/2016  III  41.2  15.1  8.5  17.5  <0.1  9.5  <1.0  4.4  5.7  6.6  <1.0  <1.0  <0.5  0.63  0.89  0.72 2/2/2016  50.9  17.8  7  15.2  <0.1  9.1  <1.0  5  6.2  4.1  <1.0  <1.0  <0.5  0.9  0.79  0.85 4/2/2016  IV  48.7  15.5  7.7  15.7  <0.1  8.7  <1.0  5.2  4.3  6.8  <1.0  <1.0  <0.5  0.6  0.8  0.62 9/2/2016  47  16.3  9.3  17.1  <0.1  9.3  <1.0  7  7.1  5.3  <1.0  <1.0  <0.5  0.82  0.65  0.51 CPCB Limits  100  60  80 80 1 400 5 100    6 20 1 2Minimum  41.2  15  7 14.2 <0.1 8.7 <1.0 3.5 <1.0 <1.0 <0.5 0.45Maximum  51.2  17.8  9.3 17.5 <0.1 10.8 <1.0 7.1 <1.0 <1.0 <0.5 0.95Average  47.3  15.89  7.9 16.0 – 9.49 – 5.37 – – – 0.74BDL: Below Detection Level (All Parameter Units Are µg/M3) Standard from ‘The Air (Prevention and Control of Pollution) Act, 19 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  135 

Table 3.11 Ambient Air Quality Recorded at eight locations 

Sr. No. 

Parameter 

Units 

Locations  Permissible limitsProje

ct site 

Bagmala 

Walke 

Mandala 

Vave 

Talekhar 

Salav 

Korlai 

1  PM2.5  µg/m3 

14.60 

16.51  18.25 

18.59  18.15 

17.93  16.29 

15.89 

60.0 

2  PM10  µg/m3 

42.78 

48.14  49.86 

51.20  49.98 

49.44  47.61 

47.3  100.0 

3  SO2  µg/m3 

6.88  8.10  8.00  8.61  8.53 8.35  7.98  7.9  80.0 

4  NOX  µg/m3 

13.48 

15.93  15.81 

16.94  16.75 

16.39  15.86 

16.0  80.0 

5  Pb  µg/m3 

<0.1  <0.1  <0.1  <0.1  <0.1 <0.1  <0.1  <0.1  1.0 

6  NH3  µg/m3 

9.60  9.68  9.98  9.58  10.03 

9.71  9.44  9.49  400.0 

7  C6H6  µg/m3 

<1.0  <1.0  1.10  1.03  <0.1 1.08  <0.1  <0.1  5.0 

8  O3  µg/m3 

5.49  5.43  5.98  5.59  5.68 5.88  5.43  5.37  100.0 

9  As  µg/m3 

<1.0  <1.0  <0.1  <0.1  <0.1 <0.1  <0.1  <0.1  6.0 

10  Ni  µg/m3 

<1.0  <1.0  <0.1  <0.1  <0.1 <0.1  <0.1  <0.1  20.0 

11  B‐(a)‐P  µg/m3 

<0.5  <0.5  <0.5  <0.5  <0.5 <0.5  <0.5  <0.5  1.0 

12  CO  µg/m3 

0.63  0.75  0.66  0.62  0.75 0.73  0.75  0.74  2.0 

The Ambient Air quality monitoring was carried out at eight locations including project site within the project area within 10 Km radius. The results of ambient air quality are presented in Table 3.10 and Table 3.11.   

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  136 

 

Figure 3.15 Graph of Ambient Air Quality Analysis for PM10 

 

Figure 3.16Graph of Ambient Air Quality Analysis for PM2.5   

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  137 

 

Figure 3.17Graph of Ambient Air Quality Analysis for SO2 

 

Figure 3.18Graph of Ambient Air Quality Analysis for NO2   

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  138 

 

Figure 3.19Graph of Ambient Air Quality Analysis for NH3 

 

Figure 3.20Graph of Ambient Air Quality Analysis for CO   

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  139 

 

Figure 3.21Graph of Ambient Air Quality Analysis for Ozone 

Interpretation 

During  the  study  period  in  the  entire  study  area  the  maximum  value  of  PM2.5  was observed at Mandala  i.e. 18.59 μg/m3 and  the  lowest was observed at project  site  i.e 14.60 μg/m3. PM 10 was maximum at Mandala and minimum at project site the values are 51.20 μg/m3 42.78 μg/m3 respectively.  

The minimum SOx concentration value of 6.88 μg/m3 was observed at project site and maximum concentration of 7.98 μg/m3 was observed at Salav. 

Maximum concentration of NOx was observed at Mandala i.e. 16.94 μg/m3 and minimum concentration of NOx was observed at Project site i.e. 13.48 μg/m3. 

The other parameters recorded  includes Ammonia, Ozone, Nikel CO, Lead(Pb), Arsenic (As), Benzene, Benzo(a) pyrene were found to be within permissible limits. 

3.14. NOISE QUALITY 

The following sources were used as secondary data: 

•  Literature Review  

•  CPCB guidelines 

•  Previous reports 

Primary Data 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  140 

A preliminary reconnaissance survey has been undertaken to identify different noise generating sources based on the activities in the study area. To establish the ambient noise in the study area, monitoring of ambient noise level was carried out at three locations for each scheme in the study area. 

Methodology of Ambient Noise Monitoring 

Noise  levels  were  monitored  as  per  the  CPCB  2015  guidelines  for  the  study  period.  Noise measurements for 24‐hour period were made a 8 locations near project site.. Noise levels were measured using Noise Meter PCE‐322A meter manufactured by PCE Instruments..  

Area  Category of Area  Permissible Limit 

Leq Day time  Leq Night time 

A  Industrial Area  75  70 B  Commercial Area  65  55 C  Residential Area  55  45 D  Silence Zone  50  40 

Note - 1 Day time is reckoned in between 6.a m and 10 p.m. Note - 2 Nighttime is reckoned in between 10 p.m. and 6 p.m.

Table 3.12 Ambient Noise Levels

Location  Project site 

Bagmala 

Walke  Mandala 

Vave  Talekhar  Salav  Korlai 

DATE  19/1/16 

21/1/16  27/1/16 

18/1/16  22/1/16 29/1/16  28/1/16 

20/1/16 

Hourly L e

06:00  40.8  44.4  40.5  44.0  41.2  41.8  40.7  40.5 07:00  44.4  48.6  47.8  47.5  46.4  46.9  45.3  45.7 08:00  44.0  50.0  47.9  52.1  45.1  48.0  46  47.3 09:00  43.6  53.7  50.1  46.0  48.7  48.4  48  47.6 10:00  43.5  50.8  48.3  49.2  53.1  51.0  54.1  51.3 11:00  48.8  50.4  53.1  52.5  50.7  52.1  51.3  52.2 12:00  44.8  50.3  54.2  50.8  50.1  52.8  51.2  52.1 13:00  46.3  49.3  52.8  50.9  51.4  55.1  50.5  55.7 14:00  51.6  48.1  50.6  48.0  53.9  48.9  55  47.9 15:00  45.2  50.4  50.0  48.3  55.5  50.7  55.1  50.1 16:00  44.4  52.8  48.7  47.7  50.4  46.7  49.9  46.4 17:00  42.2  51.9  44.8  49.5  51.8  51.1  50.7  51.3 18:00  44.8  49.4  48.8  48.2  51.7  48.6  52.5  48.1 19:00  44.4  53.2  45.8  53.8  49.3  50.0  49.1  49.7 20:00  43.7  52.1  44.5  49.1  45.3  46.4  45.1  46.2 21:00  43.8  46.2  44.5  47.6  47.7  44.9  46.3  44.1 22:00  39.6  43.4  41.2  42.4  42.6  40.5  41.5  40.3 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  141 

23:00  39.7  43.4  42.1  41.5  40.3  40.6  40.2  40.1 00:00  39.0  42.8  40.2  40.2  40.5  40.3  40.7  40.4 01:00  38.6  40.6  39.2  39.6  39.6  39.4  38.7  38.7 02:00  38.7  41.4  39.7  39.9  39.9  39.9  40.1  40.1 03:00  40.5  39.3  40.3  40.3  39.4  40.2  38.8  41 04:00  39.8  40.5  39.6  40.3  40.7  39.6  40.2  38.5 05:00  40.7  42.3  41.2  42.0  41.5  40.8  41.8  41.2 

Leq Day  45.6  50.7  49.6  49.8  50.8  50.0  51.3  50.4 Leq Night  39.6  41.9  40.5  40.9  40.7  40.2  38.7  37.7 LDN  47.4  51.1  49.9  50.2  50.8  50.1  50.9  50.2 

Interpretation The projects site  is  located  in the west coast of Arabian Sea. The ambient noise monitoring  is carried out at nearby surrounding to establish the baseline conditions in the area for comparison with future levels during construction phase.  

The monitoring  of  ambient  noise was  conducted  to  assess  the  background  noise  levels  at  8 locations. Noise  levels during day  time  (Lday)  ranges  from 45.6  to 51.3 dB  (A) and night  time (Lnight) ranges from 37.7 to 41.9 dB (A).it was observed that maximum day time knowledge is found in Salav and for night time is found in Project site All the readings are within CPCB norms.  

3.15. SOCIO‐ECONOMIC ENVIRONMENT 

3.15.1.1. Maharashtra State 

The  published  information  included  the  websites  of  the  Government  of  India  and  the Government of Maharashtra and the Census of India data 2011, which was utilized to enlist the socio‐economic profile of the project area. As seen in Table 3.13, Maharashtra is the third largest state in India with an area of 3,07,713 sq. km. and a population of 11.2 crore.  It  is one of the wealthiest and most developed states in the country, which constitutes approximately 5.8 crore of male  and 5.4  crore of  female population.  The density of  the  state overall  is  365/km2.  The literacy rate is of the state is 82.34 percent. The sex ratio is 929 females per 1000 males. 

Table 3.13: Basic features of Maharashtra 

Sr. No.  Particulars  Details 

1  Geographical location Geographical  Coordinates  of Maharashtra are 19.7515° N, 75.7139° E

2  Area  3,07,713 Sq. km. 3  Population  11,23,74,333 4  Population (Male)  5,82,43,056 5  Population (Female)  5,41.31,277 6  Population density  365 per Sq. km. 7  Sex ratio  929 females per 1000 males 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  142 

8  Literacy rate  82.34  percent 9  Decadal Growth  percentage  15.99  percent 

Source: Census 2011 

As seen in Table 3.14, 20 percent of the total population of Maharashtra consists of SC and ST.  The state consists of 1.3 crore population of scheduled caste of which 67 lakh are males and 65 lakh are females. The state also has 1.05 crore of scheduled tribes of which 53 lakh are males and 51 lakh are females.  

Table 3.14: Maharashtra Population (SC and ST) 

Caste  Total  Male  Female 

SC  1,32,75,898  67,67,759  65,08,139 ST  1,05,10,213  53,15,025  51,95,188 

Source: Census 2011 

As  seen  in  Table  3.15, Maharashtra  has  a  good  literacy  overall, with  a  literate  population  of 8,15,54,290 out of 11.2 crore individuals that is 82.34 percent of literacy rate overall. 4.5 crore out of 5.8 crore males are  literate.  Literacy  rate  is good among males  i.e. 88.38 percent. The literacy  rate  among  females  is  relatively  low,  with  25  percent  of  female  population  being illiterate. Only 3.6 crore out of 5.4 crore females are literate.  

Table 3.15: Maharashtra Literacy Level 

Parameter  Male  Female 

Literacy  4,52,57,584  3,62,96,706 

Percentage  88.38  75.87 Source: Census 2011 

Table 3.16 shows the work population of Maharashtra. Around 4,94,27,878 people are working as per census of 2011. Out of which 3.2 crore are males and 1.6 crore are females which is 32 percent of the worker population. This shows that females are not very keen to work which also coincides with low literacy rate in females. 

Table 3.16: Maharashtra Worker Population 

Parameter  Male  Female 

Workers (Main and Marginal)  3,26,16,875  1,68,11,003 

Percentage  56  31.06 Source: Census 2011 

3.15.1.2. Raigad District 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  143 

According to Census 2011 Raigad had a population of 26.3 lakhs of which males were 13.4 lakh and remaining 12.8 lakh were females, spread over urban & rural section. Total area of the Raigad district is 7,152 square kilometre. Total No. of households are around 6.1 lakh. 

Average literacy rate of Raigad was 73.64% in 2011; on comparing gender wise, male and female literacy were 54.62% and 45.37% of  total  literate  respectively. Total  literate  in Raigad District were 19.3 lakh of which male and female were 10.5 lakh and 8.8 lakh respectively. Sex ratio is 959 females per 1000 males. 

Table 3.17: Basic features of Raigad district  

Sr. No.  Particulars  Details 

1  Geographical location Geographical  Coordinates  Raigad: 18.5158° N, 73.1822° E 

2  Area  7,152 Sq. Km 

3 Population  26,34,200 Population (Male)  13,44,345 Population (Female)  12,89,855 

4  Population density  ~ 368 per square km 5  Sex Ratio  959 females per 1000 males 6  Literacy rate  73.64 % 7  Decadal Growth  percentage  (+) 19.31 

Source: Census 2011 

Table 3.18 shows  the population of SC and ST  in Raigad district. Raigad district has a  total of 1,34,952 people belonging  to  scheduled  caste out of which 67,980 are males and 66,972 are females. They constitute 5.12 percent of the total Raigad district population. Raigad district also has a total of 3,05,125 people belonging to scheduled tribe (ST) out of which 1,51,468 are females and the rest 1,53,657 are males. They constitute 11.58 percent of the total population of Raigad district. 

Table 3.18: Raigad District Population (SC and ST) 

Caste  Total  Male  Female 

SC  1,34,952  67,980  66,972 ST  3,05,125  1,53,657  1,51,468 

Source: Census 2011 

Table  3.19  shows  the  literacy  rate  of  Raigad district  population.  Raigad district  has  a  total  of 19,39,994  literate  people which  is  73.64  percent  of  the  total  population.  The  literacy  among males  is 10.59  lakh which are 78.82 percent of the total male population. The  literacy among female population is 8.80 lakh which are of 68.24 percent of total female population.   

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  144 

Table 3.19: Raigad District Literacy Level 

Particulars  Male  Female 

Literacy  10,59,692  8,80,302  Percentage  78.82  68.24 

Source: Census 2011 

Table 3.20 shows the working population of Raigad district. The total population of Raigad district consist of 10,72,969 workers. 7.53 lakh males are workers which constitute 70.25 percent of the total workers population. Number of female workers is 3.19 lakh females are working which are 29.74 of the total workers population. 

Table 3.20: Raigad District Worker Population 

Particulars  Male  Female 

Workers (Main and Marginal)  7,53,843  3,19,126 

 Percentage  70.25  29.74 Source: Census 2011 

The other parameters recorded  includes Ammonia, Ozone, Nikel CO, Lead(Pb), Arsenic (As), Benzene, Benzo(a) pyrene were found to be within permissible limits. 

– Socioeconomic status of nearby villages 

Name of village/ town 

class  No of houses 

Population 

Children(0‐6)  

SC  ST  Literacy 

Illiterate 

Total work 

Working Population 

Non‐working Population 

Kude  Total  81  293  24  4  0  192  101  159  157  134 Male   0  142  11  3  0  106  36  82  81  60 Female 

0  151  13  1  0  86  65  77  76  74 

sanegaon 

Total  153  655  55  172  72  511  144  405  397  250 Male   0  337  26  96  35  292  45  212  210  125 Female 

0  318  29  76  37  219  99  193  187  125 

Ashtami 

Total  26  146  21  0  27  105  41  56  48  90 Male   0  82  8  0  16  68  14  49  43  33 Female 

0  64  13  0  17  37  27  7  5  57 

Shenvai 

Total  268  1134  92  34  168  825  282  646  484  488 Male   0  582  46  12  82  470  112  378  301  204 Female 

0  552  46  22  86  382  170  268  183  284 

Bhilji  Total  135  592  60  0  0  447  145  370  264  222 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  145 

Male   0  286  31  0  0  238  48  186  130  100 Female 

0  306  29  0  0  209  97  184  134  122 

Bhise  Total  181  815  73  5  0  643  172  409  359  406 Male   0  424  39  3  0  363  61  270  258  154 Female 

0  391  34  2  0  280  111  139  101  252 

Yesade 

Total  39  153  7  0  0  125  28  90  75  63 Male   0  68  3  0  0  60  8  47  41  21 Female 

0  85  4  0  0  65  20  43  34  42 

Roha  Total  34267 

146261 

15670  6351 

21652 

104186 

42075 

64614 

50839  81647 

Male   0  75048  8101  3134 

10889 

58202 

16846 

43456 

36090  31592 

Female 

0  71213  7569  3217 

0763 

45984 

25729 

21158 

14749  50055 

Medhe 

Total  326  93  93  30  30  1025  271  835  302  461 Male   0  41  41  12  25  549  90  446  253  193 Female 

0  52  52  18  15  476  181  389  49  268 

Chanere 

Total  241  945  107  73  29  729  246  327  263  618 Male   0  4884  62  34  13  390  94  253  210  231 Female 

0  461  45  39  16  339  122  74  53  387 

Socioeconomic data for the villages has been collected from the Census of India, 2011.   Korlai, Salav, Borlai and Cheher are the larger villages among the 12 villages within 5 km 

of the site.   The villages are characterized by very high literacy rate even for female population.   Significant proportion of the population of village Borli are Schedule Tribes. Small village 

of Kolamandale is primarily a tribal village.   The  villages  enjoy  good  level  of  development  and  standard  of  living.  All  villages  have 

electrification, access to clean drinking water and village roads.   Primary medical facilities are available at Salav and Revdanda 

   

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  146 

 

 

 

CHAPTER4ANTICIPATED

ENVIRONMENTALIMPACTS

&MITIGATIONMEASURE

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  147 

4. ANTICIPATED  ENVIRONMENTAL  IMPACT  AND  MITIGATION 

MEASURES 

4.1.  ENVIRONMENTAL IMPACT ASSESSMENT DEFINITIONS (EIA)  

A  process  or  set  of  activities  designed  to  contribute  pertinent  environmental  information  to project or programme decision‐making. It is a process, which attempts to identify, predict and assess  the  likely  consequences  of  proposed  development  activities.  EIA  is  a  planning  aid concerned with  identifying,  predicting  and  assessing  impacts  arising  from proposed  activities such as policies, programs, plans and development projects which may affect the environment. EIA is a basic tool for the sound assessment of development proposals to determine the potential environmental, social and health effects of a proposed development.  

Environment  Impact Assessment  is becoming more and more common. Based on the “Law of Environment Protection” in India, environmental impact of every planned engineering project, including regulation works for navigation channels, should be carried. The local environmental protection  bureau,  where  the  project  is  located,  will  examine  the  potential  impact  on environment. The project will be approved, only when its environment impacts are acceptable. A thorough environmental impact assessment must incorporate an assessment of the economic impact of a project,  the physical and chemical condition of  the area,  the  flora and  fauna and human reflections. 

4.2. PURPOSE OF ENVIRONMENT IMPACT ASSESSMENT 

The projects, like any others, have impacts in the environment at a smaller degree. The magnitude of the impacts, of course, depends on the scale of the works. For this reason one should also realize that the extent of the investigation is not always the same. The points to be considered for EIA are given below. One should assess for every project, in the feasibility study, the scope and the size of EIA. 

A complete Environment Impact Assessment study should describe the following items.  A description of the “as is” situation before the project starts in the area influenced by 

the project.  A  description  of  the  proposed  project  and  its  influence  on  the  environment  after 

completion.  A description of the works and actions to be carried out to implement the project.  A description of the probable impact of all works and action described relating to‐ 

The biological equilibrium, including; 

The regional ecosystem  The fluvial ecosystem and   The human ecosystem 

 The non‐biological equilibrium, including 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  148 

Water quality  Air quality  Socio‐economic factors  Landscape  Land use  Noise  Employment   Infrastructure   Recreational activities and   The possible beneficial environmental effects of the project.  The possible adverse environment effects of the project  An evaluation of  the effects of  various execution methods during  the  implementation 

period of the project  An evaluation of the effects during the period the project is commissioned  An evaluation of the effects of demolishing a structure during the period of construction  An evaluation of the irreversibility of impacts  The range of primary, secondary and tertiary impacts (direct or indirect) of the project  A proposal for remedial actions to reduce the impacts of the project 

4.3. POTENTIAL ENVIRONMENT IMPACTS OF THE PROJECT 

The  first  step of  an environmental  impact  assessment  is  to  identify  the potential  effects of  a project on environment. In this section, attempts will be made on outlining possible effects of the project on environment, together with mitigation measures. 

4.4. ENVIRONMENT IMPACT ASSESSMENT AND MITIGATION MEASURES 

4.4.1. INTRODUCTION 

This chapter deals with the assessment of project impacts on environment. Mitigative measures are suggested to minimize the  likely negative  impacts. An environmental management plan  is also  suggested  along with  an  estimate  of  environmental  costs  as  an  input  for  evaluation  the economic feasibility of the project. 

The  project will  have  impacts  of  varying magnitude  on  different  environmental  components. These impacts could be categorized as‐ 

Primary impacts, i.e. impacts which occur as a direct result of the project activities  Secondary and tertiary impacts, i.e. impacts that occur as a result of primary impacts. 

Impacts  could  occur  during  the  construction  phase  as  well  as  during  the  operational  phase. Impacts during these phases are discussed separately in this chapter. 

4.5. SIGNIFICANT ENVIRONMENTAL IMPACTS AND MITIGATIVE MEASURES 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  149 

In view of the above study, we will sub divide the key environmental factors into 3 groups:‐ 

In respect of existing status  In respect of construction phase and  In respect of operation phase  

The  type  and magnitude  of  the  impacts  is  entirely  site  specific.  In  order  to  logically  analyze situation  on  a  probable  scale,  following  standards  have  been  devised  for  the  project  under consideration to quantify the impact: 

     0    =     No Impact     ‐ 1   =     Negligible    ‐ 2   =     Mild    ‐ 3   =     Moderate    ‐ 4   =     Significant    ‐ 5   =     Severe Utility of the above noted qualitative scale is that it can be used as a method to approximately indicate varying order of caution while dealing with different stretches of the project.(referTable 4.3) 

Each of the negative impacts on the environment requires consideration of mitigative measures. Some  of  these  measures  require  judicious  application  of  road  engineering  design  and construction methodology while others require special techniques. An attempt has been made to indicate the required mitigative measures for each type of identified negative impact. 

4.5.1.1. Impacts from the project Location 

Potential Impact due to Port Location 

Port  projects  may  also  involve  changes  in  land  terrain  like  reclamation  of  areas  for creation  of  huge  extant  of  port  infrastructure  like  operational  areas,  storages,  roads, railway lines etc. 

Coastline changes like erosion or accretion may be expected due to the establishment of ports. 

Transportation of huge quantities of  construction material  for  the berths, operational, administrative and welfare buildings, land filling/development, formation of storage and stacking yards etc., 

During  operations  phase  of  the  port  may  result  in  excessive  use  of  existing  public infrastructure like roads, railways and in‐land waterways etc., resulting in congestion and early ageing etc.  

Public utilities such as water supply, drainage, electrical power etc. may also get undue demand. 

Mitigation measures 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  150 

Careful site selection and port design should be carried out, focusing on the possibility of limiting the extent of land area requirement. 

Coast line changes like erosion or accretion due to interference to littoral process, likely to  have  serious  consequences  are  to  be  assessed  by  proper  techniques  sometimes involving mathematical/physical model studies to ascertain remedial measures such as shore protection works, sand by passing etc. 

Rainwater harvesting systems shall be provided.   Drainages,  roads  and  rail  connectivity  should  suitably  designed  and  implemented  to 

overcome affects of changes in land terrain.   Existing network of road and rail  infrastructure will be improved by suitable expansion 

including development of bye passes as part of project  to avoid congestion of existing road rail net works and resulting inconvenience to the public.  

Utilities  like  water  supply,  surface  drainage  including  storm  water,  sewage treatment/disposal, waste management/disposal,  and  electrical  power  supply  shall  be augmented or developed as the case may be part of the port project. 

 

4.5.2. IMPORTANT ATTRIBUTES DURING CONSTRUCTION PHASE 

The major activities during the construction phase of the project will be:  Transportation of pre cast material and solid wastes.  Construction and dredging activities for the proposed project.  Reclamation activities for the proposed multipurpose jetty.  Construction of berthing facility, ship parking facility.  Ship lifts stations development.  Storage of materials and equipments.  Construction of support infrastructure such as offices, toilets, etc.  Construction of internal roads, and other infrastructure.  Operational construction equipment.  Runoff from construction debris and sanitary wastes (Construction workers camp).  Disposal of liquid and solid wastes generated during construction. 

Impacts  of  these  activities  on  various  components  of  the  environment  are  discussed  in  the following subsections. It must be noted that most of the impacts during the construction phase will be temporary, and will not be  felt at  the end of  the construction phase. However proper mitigative measures are provided for the minimization of the impacts caused by these activities which we shall see further in detail. 

4.5.2.1. POSITIVE IMPACTS 

Some of the potential positive impacts expected from the project are:  Significant improvement in coastal trade along with the development of nearby ports. 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  151 

Development of ancillary facilities along with the ship/ barge resting facilities.  Opportunities for locals for better employment.  No additional burden on existing water and power supply.  Commercial development of the locality  Proper care monitoring of environmental parameters.  Increase in aesthetic value due to project after completion  

4.5.2.2. ADVERSE IMPACTS 

Assessment has been made of the adverse  impacts due to the project. These could be during construction and / or operation stages of the project. The details of the measures to be adopted including mitigative measures have been mentioned in this chapter. 

4.6. IMPACTS DURING CONSTRUCTION PHASE 

4.6.1. AIR QUALITY 

The proposed project involves the construction of jetty followed by reclamation, dredging, use of  DG  sets  and  various  construction  equipment  which  leads  to  dust  emissions  and  gaseous emissions. The reclamation and dredging activity will have impact on air quality due to running of cranes, dredgers etc. and DG sets. 

Major emissions would be limited to the wind‐blown dust due to the movement of vehicles and construction equipment as well from exhaust from vehicles, machinery, DG set and ships. Hence, the potential impact on air environment during the construction phase would be marginal. 

Impacts 

Loading  un‐loading  of  raw‐materials,  dredging,  reclamation  and  other  construction activities shall impact the air environment. However this will be a temporary and short duration,  reversible  impact.  Moreover  proper  mitigative  measures  shall  be  followed during the construction phase. 

Dust will be generated from construction activities and the airborne cement particles can degrade air quality. 

Emissions from the construction equipment used for activities like reclamation, boring, pilling and dredging may contribute to deterioration of air quality.  

DG sets will be operated in case of any power failure which may contribute to emissions. Emission of gases from equipment deployed during construction. 

Impact also includes accidental leakage of emissions, exposures, fumes, odors, hazardous airborne emissions and water front industries.  

Mitigation measures  

The  project  proponent  shall  adopt  dust  settlement  mechanisms  by  way  of  a  water sprinkler system while conducting construction activities. 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  152 

The project proponent shall take ample measures to ensure that all vehicles (construction machineries, ships, boats, trucks etc.) involved in the construction of the proposed project are regularly serviced and maintained  in order to minimize the generation of dust and other pollutants. 

Restriction of vehicle movements and vehicle speeds to reduce dust emissions.  General housekeeping practices and regular maintenance of equipment and machinery 

will be done.  Effective system of dust control shall be installed during handling and storage of coal.  No construction material except piles and other support structures will be permitted into 

waterway during construction phase.  Wind sheltering with help of barriers shall be installed during the stock piling activity. The 

raw‐material  storage  shall  be  temporarily  covered  as  far  as  possible  with  adequate covering material such as plastic, tarps etc.  

Green  belt  will  be  developed  hence  vegetation  cover  will  act  as  a  barrier  for  any penetration of air quality and odor in the nearby area also  institutional arrangements will be    proposed  with  other  agencies  for  effective  implementation  of  environmental measures, applicable environmental standards and compliance. 

This vegetation cover will act as a barrier for any penetration of air quality and odor in the nearby area. 

Approach roads will be covered with green belt on both the sides to avoid any air quality problems to the nearby residents. 

Signboards will be put along the approach roads and at project Site requesting motorists to avoid idling or/and stoppage of the vehicles at non‐designated places. 

4.6.2. NOISE QUALITY 

Construction activities may create a problem of noise and vibration generated by construction equipment, truck traffic, work vessels and other similar sources. The principle source of noise along the project area is expected from vehicles. Since there is smooth movement without any obstruction and proper dispersion, there will not be any increase in the noise levels. However, noise levels on the existing roads are expected to be reduced considerably. 

Impacts 

Construction activities will have major impact on noise environment.    The major sources of noise pollution during construction phase would be operation of 

equipment engaged in various construction activities.  The expected noise sources during construction phase are listed in table below 

 Noise Source during Construction Phase 

Activities  Equipment 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  153 

Dredging  Construction  crane,  haul  truck,  excavator,  dozer and  dredger.  oard  engines,  propellers  and thrusters 

Reclamation  piling  for  the  berth  and  from  construction equipment including trucks and dozers 

Foundation  Excavator, Concrete Mixer, Roller / Compactor etc.Others  Horn / Siren, DG Sets, Compressor Motors, Pumps

 

Dredging process consists of a number of noise emitting activities which were grouped under  sediment  excavation,  sediment  transport  and  placement  of  sediment  (dredged materials) for back filling. 

Noise would be generated during transportation, loading and unloading of raw materials, use of DG sets. 

Mitigation measures  

All construction equipment shall be fitted with exhaust silencer. Damaged silencer to be promptly replaced by the contractor. 

Ready mix concrete will be used for any concrete work so that batching plant etc. will not be  installed  at  site.  This  will  totally  reduce  noise  generation  from  this  important construction machinery. 

Proper maintenance of equipment shall be undertaken with the provision of enclosures and intake silencers. 

DG sets, if used, shall adhere to the noise and air emission standards of MoEF & CC.  Construction  works  will  be  undertaken  in  the  agreed  working  hours.  Construction 

activities involving generation of high noise shall be avoided between 10 pm and 6 am in the residential and sensitive areas. 

Personal protective equipments will be given to the workers working in the areas of high noise generation.  

Continuous  Noise  monitoring  will  be  carried  out  during  operational  phase  to  collect comparative data. 

Transmission of noise and vibration are limited by the distance from their sources. Noise could  be  considerably  reduced  by  adoption  of  low  noise  equipment  or  installation  of sound insulation fences. Green belt shall also attenuate the noise levels. 

For the pilling activity hydraulic or manual pilling equipment will be put to use. 

4.6.3. WATER QUALITY 

The project site is located at latitude 18° 32' 9.66” N and longitude 72° 54' 54.88” E & latitude 18° 32' 11.82” N and longitude 72° 55' 11.71” E  on the left bank of the Kundalika River.  

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  154 

Revdanda  port  lies  in  the  estuary  of  Kundalika  River.  The  estuary  entrance  is  protected  by  a peninsula on west side of entrance on which the Korlai Fort is situated. 

A water storage system to meet the demands of the proposed facilities can be created with a connection from the main supply line of MIDC & other irrigation department. This in‐turn can be distributed to other parts of the site and its associated facilities. 

Anticipated Impacts 

Sea water quality will be affected during the dredging and piling activities which will lead to increase in turbidity and disturbance of water column 

Site  specific  pollution  of  sea  water  due  to  seepage  of  oil/grease  from  construction equipment due to leakage or accidental spillage is envisaged. 

Heavy metal pollution due to entry of various metal pieces emanating from equipment/ chemical etc. during construction phase. 

Construction activities may disturb the navigation of other ships in the proposed project area. 

Mixing of storm water may increase levels of oil and grease in the sea water   Run‐off  of  sewage  water  generated  due  to  labour  camp  or  water  used  for  hydraulic 

testing may mix with sea water and further contaminate the same. Mitigation measures  

Dredging  will  be  undertaken  in  a  manner  that  uses  the  best  practicable  available technology to minimize impacts on the site or adjacent area. The dredged material will be  pumped  up  carefully  such  that  less  dispersion  of  sediment  occurs.  The  dredged material will be reused for reclamation as much feasible and the rest of it will be disposed off in deep sea. 

During construction period, suitable barrier will be used to protect the adjoining water bodies from the falling earth materials and dust raised to avoid sedimentation.  

Removal of contaminated sediments, capping, as well as periodical beach nourishment could be effective measures against adverse effects on water quality. 

All diesel and motor oil stored on the site will be stored in bounded area away from the shore. Signs will be posted indicating the storage of these substances. Also, intercepting drains  around  the  site  of  construction  and  designated  places  for  the machines where refuelling and change of lubricants shall be carried out.  

To avoid pollution due to heavy metals it is proposed to use pre‐cast material wherever possible  so  as  to  avoid  any  mixing  of  run‐off  water  with  storm  water  drain  during construction. 

Navigational aids such as channel beacons, buoys will be provided during construction phase for other proper movement of other ships. 

Adequate storm water drainage will be provided all along the project area. Oil Traps will be  installed  in  the  storm water  drainage  in  order  to  remove  any  oil &  grease matter 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  155 

caused due to run‐off. The surface run off shall be made to pass through oil and grease cum sedimentation chamber. 

Installations of lavatory for construction workers at a minimum distance of 200 m from water bodies and provision for composting the domestic refuse will be done. Also, sewage generated from labour camp will be conventionally treated in Sewage Treatment Plant and therefore avoid mixing with surrounding environment. 

Use of environmental friendly degreasers and detergents will be promoted.  Water used for hydraulic testing will not be allowed to mix with any of the water body 

and will be disposed off through drainage system of local authority. No impacts on ground water quality and its availability are anticipated as a result of the proposed actions at the sites. 

4.6.4. LAND ENVIRONMENT 

The  solid wastes will  be  generated  in  the  form  of  dredged material  during  construction  and dredging  activities.  There  will  be  certain  impacts  on  land  environment  due  to  the  proposed developmental  activity.  During  construction  phase  slight  impact  on  the  land  environment  is envisaged because of constructional activity and dredge material disposal management. Baseline sediment analysis  for  the project has been  incorporated  in  chapter 3, which shows adequate amounts of nutrients  in  the sediment quality. Greenbelt development within and around  the project site will help in improving the ecology and aesthetic value of the area. The planted trees will  absorb  specific  air  pollutants,  reduce  noise  pollution,  control  soil  temperature,  help  for holding moisture in soil, attract more birds and will help in maintaining the overall environmental quality.   

Anticipated Impacts 

Disposal of  solid waste  from  labour camps and construction activities may  lead  to soil contamination, thereby disturbing soil micro‐flora. 

Disposal of dredged material on the land area may lead to soil degradation.  Storage of raw material on land may lead to accidental spillage of oil or run‐off due to rain 

water. Mitigation measures 

Proper  solid waste  disposal management will  be  done  during  the  construction  phase. Color  coded containers will be provided  for  solid waste  collection. Also,  toilets will be provided to avoid open defecation. 

All the construction waste debris will be collected and segregated at site before disposal. The  re‐usable  construction  solid  waste  shall  be  reused  for  land  filling  and  reclaiming activities, rest shall be disposed off as per existing local norms.  

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  156 

The dredged material generated during maintenance dredging will mainly consist of soft silty clay which shall be reused for reclamation and remaining waste will be disposed off in deep sea at designated site. 

Oil  and  fuel will  be  stored  in  separate  bunkers.  Proper maintenance  of  the  construction  and dredging equipment will be done to avoid spillage or leakage of oil or other greasy material on the land environment.  

4.6.5. TOPOGRAPHY SOIL AND GEOLOGY  

Project is located in Korlai & Sanegaon village, Tehsil Murud & Roha, Dist. Raigad, on the left bank of Kundalika River. The existing land under consideration falls in CRZ area. Good drainage facilities are available in the form of Sewage Treatment Plant. The dredged material generated dredging will mainly be reused for reclamation and remaining waste will be disposed off in deep sea. 

Mitigation Measures  

Green belt of proper size and shape will be developed to increase the aesthetic value of the project. 

The dredged material shall be either re‐used during land reclamation or disposed off in deep sea in the identified location. 

Reclamation  bunds  shall  be  constructed.  Approach  bund  and  temporary  road  will  be constructed for reclamation purpose. 

Adequate ground treatment is proposed after reclaimed land.  The  construction  and  building materials  will  be  taken  only  from  selected/  approved/ 

licensed borrow area to avoid any adverse effect in the area.  Cutting material will be utilized for earthwork filling requirement. 

Design of all structures will take the area’s seismic characteristics into account. 

4.6.6. RESERVED FOREST AND FAUNA  

The project area does not fall under any of the reserved forest area. There are no endangered species of flora and fauna within the project area, neither any endemic flora nor fauna species are found in the adjoining area. Wild life activity is also absent in the area. 

Mitigation Measures 

During construction all the care will be taken to preserve existing flora and fauna   The loss of these will be compensated as per the standards norms and practice. 

4.6.7. LAND USE 

The  project  area  on  the  landside  consists  of  main  &  arterials  roads  including  commercial establishments. No agricultural or forestland is involved. The existing approach arterial roads will 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  157 

not be altered during pre and post development. Stone rubble, aggregate etc. is to be procured from existing authorized quarries.  

Mitigation Measures 

Development of any land will be in accordance with the government regulations.   Care will  be  taken  to  ensure  that  the  construction worker’s  camp doesn’t  disturb  the 

surrounding land use pattern.   The care will be taken to avoid cutting of any vegetation and if any portion is cut for any 

purpose it will be restored and replanted according to the standards norms.  Proper navigational  channels will be provided during construction phase and dredging 

activity.  Reclamation  bunds  shall  be  constructed.  Approach  bund  and  temporary  road  will  be 

constructed for reclamation purpose.  Adequate ground treatment is proposed after reclaimed land.     

4.6.8. IMPACTS ON UTILITY SERVICES AND COMMUNITY SEVERANCE  

Utility lines like electric poles, telephone poles, transformers high and low tension electric lines and telephone lines which may be affected by project, if any, will be identified with respect to their  locations  in the project area. Community severance and sensitive receptors  like religious places community  centers  schools,  inhabitant centers and cattle  crossing  location etc. will be taken in to consideration during construction phase. 

4.6.9. MARINE ENVIRONMENT 

The  marine  environment  and  biodiversity  includes  the  fishes,  benthic  flora‐fauna  and  other marine organisms which may be affected by the proposed project activity. Since the proposed project comes in the inter tidal region of the Revdanda creek 

Anticipated Impact: 

The  capital  dredged  and  the  disposal  site  of  dredged  material  temporary  biological impacts  depending  on  the  prevailing  flora  and  fauna  at  the  sites,  areas  involved  and dredging duration 

Water turbidity and aqueous discharges (oily wastes, sanitary wastes) from the dredgers, barges and workboats  involved in the activity may affect photosynthetic activity which restrict to plankton food production  

Macrobentos at the footprints of new construction will be lost permanently. Water runoff from construction activity may affect intertidal habitat.  

Due to construction activity mangrove habitat may little disturb in vicinity of the project site. 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  158 

 Mitigation Measures: 

Dredging will  be  confined  to  only  those  areas  earmarked  for  the purpose  to  limit  the impact and the dredged sediment will be carefully disposed at pre‐decided sites at shore terminal area or used in construction 

During construction period, suitable barrier will be used to protect the adjoining water bodies from the falling earth materials and dust raised to avoid sedimentation.  

Fresh surface area of the newly constructed underwater structures would provide new habitats for selected benthic fauna to colonize and grow. However macrobenthos will be periodically studied to enable taking corrective measures, if warranted 

Contractor should take care to stop run‐off water enter in intertidal area.  Mangrove management plan has been sketched out for the conservation of mangroves 

in the marine ecosystem at or in vicinity of the project site. 

4.6.10. IMPACTS DURING OPERATION PHASE 

4.6.10.1. Positive impacts of the proposed project 

Any developmental project related to infrastructure and community development would have its own impacts on various parameters. These impacts, besides moderate on environment during construction phase, may also have sustainable positive  impacts. The said project certainly has certain positive impacts on socio‐economy as well as environmental factors. The social impact will  include  additional  employment  and  commercialization  of  the  area.  The  project  will  also enhance aesthetic look of the area.  

4.6.11. AIR QUALITY 

The proposed not involve any major impact on air quality of the area; however various activities related to proposed facility may cause negligible impact on air quality of the area. Ambient air quality at all the sites was monitored for baseline conditions. The proposed project operations such as loading, unloading of ships, ship fuelling activities and ancillary activities shall generate dust emissions and VOC’s. Particulate emissions will be generated from loading and unloading operations. Moving of vehicles shall also emit small amount of vehicular pollution. 

Anticipated Impacts 

Air quality may impact while loading, unloading and transportation of coal.  The major activities envisaged in the proposed project is fugitive emissions from the cargo 

loading and unloading activities.  Emissions from DG sets, navigational equipment/machinery.  During  operation  phase  over‐fueling  or  careless  fuelling  practices  may  also  lead  to 

impacts on air quality of the project site area.  

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  159 

Mitigation measures  

Effective system of dust control shall be installed during handling and storage of coal.  Water spray or sprinkler system will be provided at the barge unloader, coal stacks and 

truck loading station.  Regular monitoring of air quality as mentioned in EMP will enable to keep the air quality 

below permissible standards  The  exhaust  emissions  from  ships/vessels  shall  be  controlled  on  the  ship  itself  by 

providing long stacks with air emission control option such as sea‐water scrubbing and fuel substitution. 

Day to day management and maintenance of the facility and the ancillary structures.  D.G Set will be used only in case of emergency with proper enclosures in order to reduce 

the impact of air emissions.  Control  and  check  will  be  kept  on  careless  fuelling  of  the  ships  if  any  and  excessive 

trafficking of the ships at one place.  This vegetation cover will also act as a barrier for any penetration of air quality and odour 

in the nearby area.  Approach roads will be covered with green belt on both the sides to avoid any air quality 

problems to the nearby residents.  Road Furniture / Signboards will be put along the approach roads and at project building 

requesting motorists to avoid idling or/and stoppage of the vehicles at non‐designated places. 

4.6.12. NOISE QUALITY   

Major  noise  generating  sources  are  loading  and unloading of  cargo,  equipment  handling  and vehicular movement.  

Mitigation measures  

Noise barriers in terms of vegetation cover wherever required will be used for attenuation of noise. 

Signboards  will  be  put  along  the  approach  roads  and  at  terminal  building  requesting motorists to avoid unusual use of horns and also for avoiding idling noise.  

Major Noise generating equipment will be designed such that the cumulative noise at a distance  of  1 m  remains  80  dB(A),  by  giving  proper  acoustic  enclosures  to  such  noise generating equipment’s and machinery.  

The occupational noise exposures to the workers in the form of 8 hourly time weighted average will be maintained within the prescribed OSHA standard limits. 

Workers exposed  to excessive noise will be given appropriate PPE  including ear plugs, muffs. 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  160 

Continuous  noise  monitoring  will  be  carried  out  during  operational  phase  to  collect comparative data. 

Proper maintenance of the equipment’s in terms of noise generation will carried out.  

4.6.13. WATER QUALITY 

The proposed project activities such as ship washing and surface run‐off during operation phase shall impact on the water quality of the area. The effluent ship parking facility and sewage water from the onsite support facilities shall impact on the water quality of the area. Proper mitigative measures are proposed for the treatment and disposal of waste water generated from the ship multipurpose terminal and berthing facility.  

Anticipated impacts 

The waste water generated due to sprinkling of water on coal stack may lead to water contamination.  

The sewage generated from ships if not managed properly may lead to nuisance to local people and loss of aesthetic value of the area. Further aqueous discharges from vessels such as dumping of ship waste (sullage/ sewage), oil contaminated bilge water, holding cleaning and tank cleaning residues (slop), and spillages upon re‐fueling and lubricating oil  changes  and  disposal  of  solid  wastes  may  contaminate  quality  of  sea  water  and sediment too. 

Loading and unloading activities may lead to accidental spillage of material.   Storm water drainage system may lead to increase in levels of oil & grease due to spillage 

or leakage.   Water used for hydraulic testing may mix with any of the water body. 

Mitigation measures 

The waste water generated due to sprinkling of water on coal stack shall be collected and treated in clarifier; the treated water shall be reused for sprinkling purposed while the dust will be sent to coal stack. 

The sewage will be treated in the Sewage treatment plant and the treated water shall be utilized in landscaping and dust suppression, whereas the sludge shall be used as manure.  

The sewage from the ships will also be treated within the ships and hence there will be no risk of contamination of surface or groundwater as a result of the effluent or waste discharge from the ships when within the port area. 

Ships will not be allowed to release any oily bilge waste or ballast water in the sea within port  limits  and  hence  wastes  from  the  ships  will  also  not  affect  any  surface  or groundwater according to the International Convention for the Prevention of Pollution from Ships, 1973, as modified by the protocol of 1978 (MARPOL, 73/78), 

Aqueous  discharges  from  vessels  and  disposal  of  solid  wastes  will  be  regulated  to minimize impact on marine water and sediment quantity. 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  161 

Due care will be taken such that no water pollution/ contamination occurs during loading and unloading activities.  

The runoff from the slipway, berths, etc will be collected and treated  into the effluent treatment plant.  

Proper  storm  water  drainage  system  with  adequate  oil  &  grease  traps  shall  be incorporated in order to remove any spillage/ leakage/ runoff of oil and other wastes in sea water. 

Water used for hydraulic testing will not be allowed to mix with any of the water body and will be disposed off through drainage system of local authority. 

Alternatives for reducing waste include oil/water separation and waste oil reclamation will also be considered 

4.6.14. LAND ENVIRONMENT 

Since the proposed project deals with ship loading, unloading and berthing facility there will not be any major hazardous waste generation on site. The solid waste generated on the facility will be collected, segregated. Recycle bale waste will such as paper, glass metal etc. will be sold to authorise vendor and remaining waste will be disposed off to the local municipal authority. Major issues like oil spillage and refuelling will be handled carefully and proper solid/hazardous waste management will be implemented. 

Anticipated Impacts 

Oily wastes and dredged material  removed during maintenance dredging may  lead  to contamination of land environment. 

Solid waste generated may contaminate the area and lead to foul smell if not maintained well. 

Mitigation measures 

Dredged material removed during maintenance dredging will be disposed off in deep sea at designated area. 

Solid waste will  be  segregated  into  recyclable,  degradable  and  non‐degradable  at  site itself. The recyclable waste will be either reused or given to authorize end‐users, whereas remaining solid waste shall be handled to local municipal authority. 

4.6.15. ECOLOGICAL RESOURCES AND FLORA AND FAUNA    

There will be no significant impact of the project on flora and fauna and other vegetation due to any of the pollution parameters during operational phase of the project. No significant impact is envisaged on the local terrestrial flora fauna during the operational phase of the project. Since there are no reserved forests or forest area in the project area, there will not be any violation of flora and fauna. 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  162 

Negligible Impact on marine flora fauna is envisaged due to navigation of ships, loading unloading of cargos, run‐off water from the refueling stations etc. However, proper mitigative measures will be taken to minimize the impacts due to the operation of the proposed project. Green belt development will help in attenuating any pollution caused during the operation of the proposed facility. 

Mitigation measures 

Criss‐cross drainage system installed with oil & grease traps, channelized into main storm water drainage will be incorporated in so as to ensure all the run‐off water is treated and channelized into storm water drainage leaving no run‐off water going directly into sea. 

The waste water generated due to sprinkling of water on coal stack shall be collected and treated in clarifier; the treated water shall be reused for sprinkling purposed while the dust will be resend to coal stack. 

The route of navigation of ships will be designed such that the fishery in the nearby area will not be affected. 

The navigational  route will  be designed keeping  in mind  the mangrove patches  in  the farther end of the creek such that the water currents towards the mangroves will be least affected.  

The sewage from the ships will also be treated within the ships and hence there will be no risk of contamination of surface or groundwater as a result of the effluent or waste discharge from the ships when within the port area. 

Ships will not be allowed to release any oily bilge waste or ballast water in the sea within port  limits  and  hence  wastes  from  the  ships  will  also  not  affect  any  surface  or groundwater. 

Aqueous discharges  from vessels such as dumping of ship waste  (sullage/ sewage), Oil contaminated bilge water, holding cleaning and tank cleaning residues(slop), and spillages upon re‐fueling and lubricating oil changes and disposal of solid wastes will be regulated to minimize impact on marine water and sediment quantity. 

4.6.16. LAND USE 

The  land  use  pattern,  which  will  undergo  slight  changes,  will  not  be  further  altered  during operational phase. The land use covered under green belt will be maintained during operational phase. The commercial  activities may  increase on  the  land ward  side with proper  layout and permission from local authorities. The aesthetic  look of the said  land use will be enhanced by green belt & other signage with proper architectural plans. 

Mitigation measures  

A green strip of local trees on both sides of the road will be planted on the approach roads   Tree loss due to access roads, if any, will be mitigated by tree planting programs at the 

ratio of 1:2, i.e. two tree plantations for one tree cutting. 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  163 

4.6.17. OIL SPILLS:  

Oil spills are an unlikely phenomenon in this harbour. In the unlikely event of leakage of fuel from the ships, this may cause damage aquatic biology and near‐by mangrove communities by coating roots,  limiting  the  transport of oxygen  to  the underground  roots. However, proper mitigative measures will be in place to avoid any such oil spillage. Oil spill Contingency Plan has also been sketched out in order to reduce the impact of oil spillage. 

Mitigation measures: 

The used oils and lubricants will be collected in drums from the equipment such as diesel engines; compressors etc. and either re‐used or will be sent to MPCB authorized recyclers. 

The ship terminal will have a wastewater treatment plant with oil and grease trap wherein all the waste water will be channelized.  

Oil traps will be installed in the storm water drainage in order to remove any oil & grease matter caused due to run‐off. The surface run off shall be made to pass through oil and grease cum sedimentation chamber. 

Intercepting  drains  around  the  site  of  construction  and  designated  places  for  the machines where refueling and change of lubricants shall be carried out.  

4.6.18. MANGROVE:  

The proposed developmental activity may impact the mangrove community downstream of the project site. There are no mangroves in the area under reclamation; hence no direct destruction of mangroves is envisaged due to the development.  

Direct  loss  of mangroves  is  associated with  the  damage  or  removal  of mangrove  due  to  the proposed project. Since the proposed project layout for port facilities is located on a reclaimed area connected to shore damage is minimized. There shall be no direct loss of mangroves since the proposed project area is beyond the mangrove patch. 

Mitigation Measures: 

No direct loss of Mangroves is envisaged, however proper care shall be taken in case of any loss.   

Optimum layout at the entrance to the creek is envisaged by proper assessment of all the alternatives such that, minimal disturbance shall be caused to the tidal currents towards the creek.  

Mangrove  mapping  shall  be  done  before  carrying  out  the  construction  activity  as  a measure to preserve the mangrove community. 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  164 

In case of any direct loss caused to the mangroves, if any, the same shall be replanted in the nearby area by beach nourishment and safe transportation of the affected mangrove species. 

4.6.19. DREDGING AND DREDGED MATERIAL MANAGEMENT ACTIVITIES: 

During  operation  phase  there  is  no  major  effect  seen  on  water  body  and  aquatic  biology (plankton, benthos, fish and nearby mangrove habitat) 

Mitigation Measures 

Environmental  friendly  dredging  techniques  which  are  designed  to  dredge  with  a minimum of turbidity such as Environmental disc‐cutter “Vetch” can be used. Here the cutter is provided with a closed, adjustable visor system. Turbidity‐free dredging of high‐density  mixture  concentrations  is  achieved  with  the  aid  of  a  process  control  system through which the position of the visor and the suction flow can be regulated. .  

The maintenance dredged material will be pumped up carefully such that less dispersion of soil occurs. The dredged material will be reused for reclamation as much feasible and the rest of it will be disposed in deep sea at designated location.  

4.6.20. IMPACTS ON QUALITY OF LIFE  

Socio‐Economic Condition  

The  socio‐economic  scenario  in  the  region will  certainly  change with  positive  impact  on  the  existing regional socio‐economic pattern. There will be change in employment pattern with local residents will be given preference for jobs opportunities and/or self‐employment. The economic growth will have positive impact;  it will  also  help  in  increase  in  living  standards  of  the  local  residents.  Due  to  enhancement  in infrastructure  facilities and utilities  in  living condition will  also  improve.  It will have positive effect on industrial sector in the area.  

Accident hazards and safety  

During operational phase accidents / hazards will be greatly minimized and ensure further safety of the local people. In addition, by adopting mitigation measures will ensure an efficient traffic system with high standards of safety. Onsite and Offsite Emergency Preparedness Plan as well as Disaster Management Plan have been sketched out and shall be implemented. The Risk analysis for the proposed project is also carried out.  

Aesthetics and landscape  

The landscaping and tree plantation with regular monitoring will greatly enhance aesthetic beauty. The proposed ship terminal along with its ancillary structures will add to the existing aesthetic beauty of the area. A detailed Green Belt Plan will be encouraged during operational phase.

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy International Ltd. 

TEPL/ENV/CBS/2021‐05  165 

4.6.21. CONSTRUCTION PHASE 

Table 4.1Environmental Impacts and Mitigation Measures 

Sr. No. 

Environmental Parameters 

Impact Attributes  Degree of Impacts 

Mitigation Measures  Implementing Organization 

1  Physiography  Disturbance  in  relief feature  

Mild  Will be achieved by systematic planning and designing of the project activities. 

Promoter, Client, etc. 

2  Land resources   Change in land‐use  Mild  Will be achieved by systematic planning and implementation. 

Promoter, Client, etc. 

3  Human resources   No adverse impact  Negligible  Will    be  achieved  by  systematic  planning and resources. 

Promoter, Client, etc. 

4  Ecological resources – Flora & Fauna  

No  impact anticipated  to threatened  or endangered  plant species.   Negligible  impact on marine  species which  will  be mitigated. 

Negligible  Cutting of larger girth size trees are avoided by suitably adjusting the road alignment, if required. Plantation of trees (at 1:2 ratio) will be done with the indigenous plant species.  Mangroves species if present on site will not be destroyed, in case of removal if any, will be  compensated  by  restoration  of mangrove  species  to  a  nearby  area  with help of various technologies. Greenbelt  shall  be  developed  around  the site. 

Promoter,  Forestry Dept.  involving  NGOs and local people. 

5  Environmental aesthetics values  

Removal  of  trees  & mangroves  if  any shall  have  impacts on  landscape  & aesthetic  values  of the area 

Moderate Loss of vegetation will be kept minimum as far as possible during site clearance. In case of any loss the same will be compensated by rehabilitation  and  restoration  of  the mangrove species that shall be affected. 

Promoter  through prospective contractor    

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy International Ltd. 

TEPL/ENV/CBS/2021‐05  166 

Sr. No. 

Environmental Parameters 

Impact Attributes  Degree of Impacts 

Mitigation Measures  Implementing Organization 

6  Utility  & infrastructural facilities  

Removal  of  utility line  like  electrical poles,  telephone poles,  transformer, HT & LT lines, if any 

Moderate Shifting and elevation of utility lines will be done  in  consultation  with  concerned Government Organizations. 

Promoter, telecommunication dept.  &  line  dept.  of GoM. 

7  Sub‐surface hydrology 

No  wells  and  hand pumps are existing in project area 

Negligible  Whenever possible, care is taken to avoid its relocation  by  judicious  engineering  road design.  Temporary alternative water sources will be provided in case drinking water means are affected. 

Promoter  through prospective contractor 

8  Religious places                 ‐‐‐‐‐  ‐‐‐‐                              ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐                  ‐‐‐‐‐‐‐ 

9  Geology  Not much affected   Negligible  Systematic  planning  and  implementation during  the  construction  and  dredging. Reclamation  will  be  done  with  systemic planning  and  least  disturbance  to  the natural geology. 

Promoter  through prospective contractor 

10  Surface of water   Contamination  from solid  wastes  and sewage  generated due  to  construction labour camp  Surface  runoff  from the  ship  terminal and parking facility. 

Mild  Installations  of  lavatory  for  construction workers  at  a minimum  distance  of  200 m from  water  bodies  and  provision  for composting the domestic refuse.  

Promoter  through prospective contractor 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy International Ltd. 

TEPL/ENV/CBS/2021‐05  167 

Sr. No. 

Environmental Parameters 

Impact Attributes  Degree of Impacts 

Mitigation Measures  Implementing Organization 

11  Air quality  Short‐term deterioration  of  air quality  due  to generation  of fugitive dust.  Dredging  activities and  other construction activities  leading  to fugitive emission. 

Moderate Trucks  carrying  soil,  sand,  stone,  will  be covered to avoid spilling.  Fugitive  dust  sources will  be  sprayed with water to suppress dust. Emissions from vehicles & machinery will be checked regularly & maintained properly to confirm  to  National  and  State  Emission Standards  Barriers  during  construction activities such as dredging will be installed.  

Promoter  through Prospective Contractor (PC) 

12  Noise level  Increased  noise levels due to project activities 

Mild  All  the equipments will be duly  lubricated, maintained  in  good  working  condition  to minimize noise levels. Stationary construction equipments will be placed  as  far  as  possible  from  dense habitation. Green belt barrier. Provision of protection devices  (ear plugs) to be provided to the workers operating in the  vicinity  of  high  noise  generating machineries. 

Promoter  through Prospective  Contractor (PC) 

13  Ecological resources – Flora & Fauna 

No  endangered species found  

Negligible  Proper care will be taken to maintain eco‐balance.  

Promoter  through Prospective Contractor (PC) 

14  Land use  Land acquisition is as per  the  government regulation  and policy.  Mild  impacts on  local  land  use may be visualized  

Mild  Proper  management  planning  will  be achieved.  

Promoter  through Prospective Contractor (PC) 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy International Ltd. 

TEPL/ENV/CBS/2021‐05  168 

Sr. No. 

Environmental Parameters 

Impact Attributes  Degree of Impacts 

Mitigation Measures  Implementing Organization 

15  Construction workers camp 

Impacts  on community health 

Mild  Supply  of  safe  drinking  water  to  the construction camp. Provision  of  adequate  drainage  system  to avoid undesirable water  logging.  Provision of hygienic facilities to construction workers camp is made. A  system  of  regular  disposal  of  domestic waste & sewage.  

Promoter  through prospective  contractor (PC)    

16  Accident  hazards and safety  

Short  term  impacts from road accidents. Impacts  from accidents  during handling  and  use  of Construction machinery. 

Mild  Proper  traffic  diversion  and  management during  construction.  Construction  Safety measures will be employed. Proper  warning  signs  will  be  used  at construction site.  

Promoter  through prospective  contractor (PC) 

4.6.22. OPERATION PHASE 

Table 4.2Environmental Impacts and Mitigation Measures 

Sr. 

No. 

Project Related Issues  Actions to be Taken   Responsible Organisation 

1  Prevention  of  Road  side Squatters  or  indirect  Urban Sprawls 

Involve  land  use  planning  agencies  like  the  Revenue Department at all levels during operation stage. 

Plan and control development activity.  Removal, cleaning of squatter and temporary hutments 

of construction workers once construction activities has been completed. 

P  &  C  in  consultation with  the  Municipal corporation. 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy International Ltd. 

TEPL/ENV/CBS/2021‐05  169 

Sr. 

No. 

Project Related Issues  Actions to be Taken   Responsible Organisation 

2  Road  Safety  and  Traffic Management 

Adequate  number  of  proper  &  legible  signs  will  be installed along the road. 

Prepare  and  administer  a monitoring  system  on  road/ accidents. 

P & C in consultation with Public Works Department and State Traffic Police. 

3  Air Quality  Monitor periodically ambient air quality at selected sites. Confinement and absorption of the pollutants at source 

by creating vegetation along the length.  Enforcing different control measures to check pollution 

(e.g. catalytic converters, unleaded petrol, proper serving etc.)  

P & C in consultation with MPCB 

4  Noise level  Monitor  periodically  ambient  noise  level  at  selected sites. 

Minimization  of  use  of  horns  near  sensitive  locations/ silence  zones  with  the  help  of  sign  boards  at  proper places. 

Provide noise barriers with roadside plantation. 

P  &  C  in  consultation with MPCB 

5  Water Quality  Monitor  periodically  water  quality  for  establishing  the change  of  water  quality,  if  any,  and  assessing  its potentiality of surviving aquatic flora and fauna and for irrigation use. 

P & C and MPCB  

6  Soil Characteristics   Periodic monitoring of  soil quality at  specified distance for assessing contamination by vehicular emissions. 

Checking the overflow of spillage from the carriageway by promoting growth of vegetation cover along the road shoulders and preventing overflow to green belt. 

P  &  C  in  consultation with  Public  Works Department (PWD). 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy International Ltd. 

TEPL/ENV/CBS/2021‐05  170 

Sr. 

No. 

Project Related Issues  Actions to be Taken   Responsible Organisation 

7  Maintenance of Avenue trees  Plantation  will  be  undertaken  by  the  concession company  on  an  aggressive  note  along  the  whole stretches on the both sides of the road. 

Restoration of Mangroves if any will be done adequately with proper technology. 

P & C in consultation with authorities  and  State forest Department 

8  Human Health and Safety  Vulnerable stretches, which are prone to accidents, will be identified. 

Adopt Safety measures and other control measure during Operation of the facility.  Installing proper road signs, marking along the whole 

stretch of the tolled highway in the form of cautioning, informatory and mandatory signs of gantry mounted overhead sizes. 

Installing  fire  safety  measures,  electrical  safety measures, Personal protective Equipments and other work‐safety measures.  

Incorporation  of  On‐site  Emergency  Preparedness, Off‐site Emergency Plan, Disaster Management Plan 

P & C in consultation with MPCB. State Public Health Works Department (PWD)

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  171 

4.6.23. Evaluation of impacts 

The Environment impact of the project has been discussed in this chapter and the potential of the impact is mainly under the construction and operational phase. The type and magnitude of the impact is entirely site specific.  

4.6.23.1. Impacts from Project Location 

Project  location plays an  important role  in prevention of adverse  impacts and to minimize the mitigative measures. These measures can be classified as follows: ‐ 

Through Engineering Design  Through project Scheduling  Through Tree Planting   Through Rehabilitation & Resettlement Planning or through property constructed and maintained 

labour camps.  Through post construction by providing facilities other Government, Departments and agencies 

to watch, monitor, enforce environment standards.  

All this is presented in individuals tables 

4.6.24. Evaluation of impacts 

Evaluation of impacts has been done for following issues namely:   Environmental Impact due to project location  Environmental Impact from construction camps  Environmental Impact from road construction phase  Environmental Impact from Operation phase.

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  172 

Table 4.3 List of possible environment impacts due to proposed project 

Sr. No.  Attributes  Proposed 

Development 

Impact Marks 

Mitigative measures 

1  Project Location  2  Change in land use pattern 2  Soil Slippage  1  Proper  soil  engineering  and  foundation 

designs and structural protection 3  Rock Quarrying  1  Material will be obtained  from authorized 

agencies 4  Air quality  2  Provision  of  adequate  monitoring  during 

operational  phase,  no  changes  in  this  line during  construction  period  due  to  proper mitigative measures. 

5  Water Quality  2  Sewage Treatment Plant (STP) and Effluent treatment  plant  (ETP)  during  operational phase. 

6  Noise Quality  

2  Proper  noise  control  management  plan during  construction  period,  noise  barriers in terms of thick vegetation proposed. 

7  Land use  2  The land use pattern shall change after the proposed project. 

8  Reduction  in  built habitation of structures 

1  Not Applicable 

9  Displacement  of population  

0  No encroachments or settlements. 

10  Heritage / Archaeology  0  No such structures within the project area. 11  Socio ‐ economy  1  Better  employment  opportunities, 

improved  economic  status,  increase  in commercial and business opportunity. 

12  Loss  of    Environmental Aesthetics 

1  Proposed project will cause changes in the existing  Land  use  of  the  site,  however, enhancement  in  the  environmental settings envisaged. 

Note: The total negative impact is only 14 where severe most could have been 5 x 12 = 60. So negative impact is 23% to positive impact is 77%.As the total positive impact of the project is 77, therefore, it can be concluded that this is an environment friendly project.   

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  173 

Chapter5Alternative

Analysis

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  174 

5. ALTERNATIVE ANALYSIS The proposed project is to develop Deep Water Jetty facility on Kundalika River, village Korlai, district Raigad, Maharashtra and capacity expansion at existing  Inland Water Jetty Facility, on Kundalika River at village Sanegaon, district Raigad, Maharashtra.  

This study of preliminary nature was carried out for selection of the project site of proposed deep water  jetty. The preliminary study of alternatives was carried out, considering both  inner and outer locations on Kundalika River and  three locations on the same shore where selected. All of the 3 locations where selected in such a way that river and tidal flow was not affected. The three locations were drawn within same onshore area, so that all of them had the same capacity and they were comparable. The road accesses also all the location where also considered. All the site alternative are represented in Figure 5.1 

 

Figure 5.1 Possible locations of the port 

A multi‐criteria analysis of the three  locations  is presented in Table 5.1. The figures between brackets   [   ]   represent   the  evaluation  of  each   location   for  each  aspect according to the following criteria:   

3 = positive    2 = medium    1 = negative  

 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  175 

 

Table 5.1 Multi‐criteria analysis of the three port locations 

Criteria  Location 1  Location 2  Location 3 Technical aspects 

Score  Technical aspects 

Score  Technical aspects 

Score 

Need  of breakwater 

Yes   [1]  Yes [1]  No   [3] 

Need  of dredging 

High     [2]  Low/Medium [3]  Medium   [1] 

Road connection 

Easy and cheap  (short)  

[2]  Difficult (dueto  the topography    &  habitation)  

[1]  Easy  and inexpensive (Very short) 

[3] 

Railway connection 

Longer  Route through habitation            (Long)   

[1]  Very difficultand  expensive (due  to  the topography   

[1]  Easy  but expensive  (long)  

[2] 

Possibility of extension 

Easy      and  cheap  

[3]  Difficult     and  expensive   

[1]  Limited   [2] 

Criteria  Environmental aspects 

Score  Environmental aspects 

Score  Environmental aspects 

Score 

Impact  on beaches  

Disappearance of  600    m beach  

[1]  Disappearance of      400    m beaches  

[1]  No effect   [1] 

Impact  on estuary dynamics 

Minimum   [3]  Minimum [3]  Impact        due  to    dredging  

[1] 

Impact  on flora  and fauna 

Higher   [1]  Medium [2]  Lower   [3] 

Social Impact 

Higher   [1]  Closer to FortKorlai  

[1]  Least      Impact            as    on  reclaimed land  

[3] 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  176 

Final 

assessment [15]  [13]  [19] 

From the Table 5.1,  it was clear that the location no. 3 which is located inside the Revadanda creek is the  most  suited  for  the  port,  with  minimum  impact  on  the  immediate  environs  and therefore ideal for port development.   

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  177 

Chapter6:EnvironmentalMonitoringProgramme

 

 

 

 

 

 

 

 

 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  178 

6. ENVIRONMENTAL MONITORING PROGRAMME 

6.1. THE NEED 

An Environmental Monitoring Plan provides  a delivery mechanism  to address  the  adverse environmental  impacts  of  a  project  during  its  execution,  to  enhance  project  benefits  and finally to introduce standards of good practice to be adopted. With the knowledge of baseline conditions,  the  monitoring  program  serves  as  an  indicator  for  any  deterioration  in environmental  conditions  due  to  operation  of  the  project,  to  enable  taking  up  suitable mitigation steps in time to safeguard the environment. Monitoring is as important as control of pollution since the efficiency of control measures can be determined by monitoring.  

Thus the Environmental Monitoring Plan subsequent to the project implementation indicates or  otherwise  if  the  project  activities  are  being  undertaken  keeping  with  good  industry practices.  Evidently,  the  post‐project  monitoring  provides  necessary  feedback  about  the actual  environmental  impacts  of  the  project  activities  and  reveals  whether  the implementation  of  the  EMP  effectively  support  the  suggested mitigation measures.  Thus, periodic  monitoring  of  designated  environment‐related  parameters  is  vital  to  assess  the status of environment during the operational phase of any project.  

Monitoring of different components of the environment including air, soil and water as well as flora and fauna wherever applicable is mandatory to meet regulatory permit requirements and  to  assess  the  performance  of  EMP  implementation.  The  project  proponent  needs  to report every six months on the progress of implementation of the conditions of the clearance. Expert team from the designated Regional Office may also visit the project site to ascertain the implementation of the conditions of clearance and also the EMP. Further, the SPCBs make it mandatory for the project proponent to meet the conditions of the clearance in addition to several other  stipulations made while granting  the Consent  to Operate without which  the proposed transport facility cannot be commenced. 

Objectives of Environmental Monitoring Plan  To  define  the  responsibilities  of  the  project  proponents,  contractors  and 

environmental monitoring personnel and provide means of effective communication of environmental issues among them. 

To delineate monitoring mechanism and identify monitoring parameters.  To assess  validity of  environment‐related predictions  and evaluations made during 

planning stage.  To pinpoint deviations if any from the predicted impacts on the environment.  To review the EMP and implement actions to remedy the situation, if required.   To  verify  evaluations  made  during  risk  and  impact  assessments  and  measure 

operational and efficiency of mitigation measures.   To assess compliance with statutory and corporate requirements.   To provide the basis for environmental audit.  

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  179 

6.2. MONITORING PLAN  

The  project  proponent  will  have  a  comprehensive  approach  towards  the  construction activities at site and the ensuing operations. Environment, Health and Safety (EHS) principles will be built into the design stages, which are followed when contracts are drafted for project management,  operations  and  maintenance.  While  different  agencies  may  be  involved  in executing  and  operating  different  aspects  of  the  project,  the  developer  has  overall responsibility for the execution of the Monitoring Plan. 

With reference to these, proponent will confirm that the contractor(s) during the construction and operation phases undertake(s) the implementation and adherence to plan that addresses impacts and mitigation measures. Adequate budgetary provisions will be made for fulfilling developer's obligations arising from the implementation of measures towards the betterment of environment. 

Correct  methodology  for  collection  of  samples  and  their  analyses  using  appropriate  and approved methods  is  imperative  for dependable output of monitoring. To ascertain  this  it must be ensured that sampling and analysis proposed in the monitoring plan are carried out by a NABL and MoEFCC accredited laboratory under the supervision of the project proponent. 

6.2.1. MONITORING DURING CONSTRUCTION PHASE 

From  a monitoring  perspective,  the  important  environmental  components  are water,  air, noise,  soil,  sediment,  flora,  fauna,  and  occupational  health.  The  sampling  and  analysis proposed  in  the  monitoring  plan  will  be  carried  out  by  the  proponent  directly  or  by  a contracted  qualified  agency.  Summary  of  Environmental  Monitoring  Programme  during construction phase is given in Table 6.1. 

6.2.2. MONITORING DURING THE OPERATIONAL PHASE 

The project proponent is responsible for monitoring environmental components during the operational phase even when activities are out‐sourced to third parties. The proponent will develop a separate Operational Environment Monitoring Plan for specific project sites such as indoor monitoring at vulnerable areas in the terminal, jetty etc. Summary of Environmental Monitoring Programme during the operational phase is given in.Table 6.1.  

The  implementation  of  the  Environment Monitoring  Plan will  be  the  responsibility  of  the Environment  Management  Cell  within  the  project  framework  which  will  generated monitoring reports, findings and conclusions on a regular basis.  

6.3. REPORTING 

6.3.1. COMPLIANCE REPORTS 

As  a  part  of  environmental  monitoring  program,  following  compliance  reports  shall  be submitted to MPCB and Regional Office of MOEFCC. 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  180 

Half yearly compliance reports in respect of the conditions stipulated in the terms and conditions of the clearance.  

Environmental statement to MPCB, every year.  Format for maintaining records of hazardous waste in Form 3 as per Hazardous Waste 

(Management, Handling and Transboundary movement) Rules, 2016.   Format  for maintaining  notification  of major  accident  in  Schedule  6  as  per MISHC 

rules, 1989 (as amended). 

Table 6.1 Environmental Monitoring Plan during project construction phase and operation phase 

Sr. no 

Aspects Parameters  to  be monitored 

Location Frequency of monitoring 

Methodology

1  Ambient  Air Quality 

PM10,  PM2.5,  S02,  NOx, CO,  

Minimum  3 locations should  be monitored near  project site 

Monitoring every  six months  (as per  CPCB guidelines) 

NAAQS, 2009. 24 hour reading  as per standards for  (PM10, PM2.5,  SO2, NO2)  &1 hours  for  CO & 8 hours for HC 

2 Ambient Noise Quality 

Noise  intensity  in  dB(A) Day  &  Night,  Leq,  Lmin, Lmax, L10, L90, L50 

Minimum  3 locations within  500  m representing different receptors 

Monitoring every  six months  (as per  CPCB guidelines)  

24  hour reading as per standards. 

3 Ground Water Quality 

pH,  salinity,  total dissolved  solids,  BOD, Coliform count, electrical conductivity, Chlorides & COD 

3‐4  locations in  and around the site 

Monitoring every  six months  (as per  CPCB guidelines) 

Two  litres  of samples  from each  source, locations  are chosen  based on  availability of  ground water  body within  study area. 

4 Surface Water Quality 

Colour,  Temperature, Turbidity,  Electrical Conductivity,  Total dissolved  solids,  Total suspended  solids  pH, 

3‐4  locations in  and around the site 

Monitoring every  six months  (as per  CPCB guidelines) 

Two  litres  of samples  from each  source. Sampling locations  are 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  181 

salinity, Dissolve Oxygen, Alkalinity as CaCO3, BOD, COD,  Nitrate,  Sulphates, Phosphate  as  PO4, Calcium  Heavy  Metals (Arsenic,  Zinc,  Cadmium, and  Lead),  Chlorides, Boron,  Iron,  Fluorides, Copper  and  Chromium, Total Coliform count 

chosen  based on  presence of  surface water  bodies in  the  study area. 

5 Marine Water quality 

Physio‐chemical: Temperature, Transparency,  EC, turbidity,  TDS,  Alkalinity, Salinity,  TSS,  pH,  DO, COD,  Sulphates, Ammonia,  total Nitrogen Chlorides,  BOD, Phosphates,  Sodium, Potassium,  Silicates, Hydrocarbon,  Nitrates, Nitrites,  Oil  &Grease, Heavy metals (Pb, Hg, As, Zn, Cr, Cd, Cu, Fe). 

3‐4  locations in  and around the site 

Monitoring every  six months  (as per  CPCB guidelines) 

Two  litres  of samples  from each station. 

Locations  are planned depending  on current pattern  and intensity  of impact  of construction activity. Biological  parameters: 

Phytoplankton  (No.  of species and their density) ,  Zooplankton  (No.  of species and their density)

6 Marine Sediment Quality 

Physio‐chemical parameters  :  Size  and Texture , colour, pH, oil & grease,  nitrogen, phosphorus,  sulphide, heavy  metals  (Arsenic, Iron,  Lead,  Zinc,  Cobalt, Copper,  Cadmium, Nickel,  Silver),  organic nitrogen 

At  3‐4 locations 

Monitoring every  six months  (as per  CPCB guidelines) 

1 Grab sample from  each station. Locations  are planned depending  on current pattern  and intensity  of impact  of construction activity. 

Biological  parameters: Benthos  (Macro‐benthos) 

7  Soil Quality 

Soil texture, pH, Electrical Conductivity,  Salinity, Sodium,  Nitrates, Phosphates,  Organic content, potassium 

At  2  locations (project site & transportation route) 

Once  in  a season monitoring except  for monsoon (once  a year) 

1kg  sample at every station 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  182 

8  Ecology  Survey of flora & fauna  At site 

Monitoring every  six months  (as per  CPCB guidelines) 

‐ 

9  Greenbelt Development 

Rate  of  Survival  and Growth  Of  Various Species 

At site  Once  per month  ‐ 

   

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  183 

  

 CHAPTER 07 

ADDITIONAL  STUDIES

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  184 

7. ADDITIONAL STUDIES 

This  chapter broadly deals with Risk Assessment  study Disaster Management of Proposed project of “proposed jetty at Korlai River and expansion of existing jetty at Sonegaon by Indo Energy International Ltd”. Risk assessment, disaster management plan and natural resource conservation plan are also included in this chapter.  

7.1. ENVIRONMENTAL RISK  

Environmental risks are inherent in the construction and operation of ports and terminals. Because of where they are located, special consideration needs to be given to the potential harm that could be caused by significant pollution of coastal or estuarine environs as a result of their construction or operation.   Strict environmental legislation in many countries has resulted in defined requirements for port and terminal operators to assess the potential for environmental impacts, and to manage their business activities accordingly. Heightened public awareness of environmental  issues has also led to the enhanced potential for third‐party claims for pollution and environmental damage.  Environmental risks can arise at all stages of the port and terminal life cycle:  Construction – Dredging, removal, and disposal of contaminated material, transportation 

and storage of significant overburden.   Operation  –  Pollution  and  environmental  damage  caused  by  contaminants  released 

during the handling, movement, and storage of products and goods, and associated health and safety risks.  

Closure and restoration – Extensive ground works mean that risks include the treatment and disposal of  contaminated  sediments. While many environmental  risks are generic, others are specific to the particular facility.   

The significance of  site‐specific  risks will depend on  the environmental  characteristics and sensitivity of the surrounding area, often categorized in terms of the surrounding land and coastal habitats. 

7.1.1. RISK IDENTIFICATION AND QUANTIFICATION  

Detailed analysis by risk type: –   Market (e.g. commodity risk, interest rates, foreign exchange).   Operational (construction risk, completion of milestones & start‐ups)   Human capital (health, welfare, and pensions)   Demand forecasting  

7.1.2.  RISK MITIGATION  

1. Operational and construction safety management system, Evacuation & Fire fighting, First aid training, Training, including portfolio insurance procurement.  

2. Development of Skill Human capital against natural & man made threats.  

3. Minimizing Environmental risk.  

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  185 

4. Weather risk.  

7.1.3. CONCEPT OF RISK ASSESSMENT 

The concept of risk assessment and its engineering application has been well acclaimed since more than a decade. A variety of major accidents have focused attention on the dangers of risk exposure for human health and environment. Risk analysis provides numerical measures of the risk that a particular facility posses to the public. It begins with identification of potential risk involving events and determination of the impact of  each event.  The  consequences of  each event  are  than  calculated  for numerous combinations of weather conditions and wind directions these consequence predictions are combined to provide numerical measure soft the risk for the entire facility. Risk for a particular facility is based on the following variables:  Multiple accident outcomes   Population disturbance  Site‐specific meteorological data  “Risk analysis is a tool which helps to translate hindsight (accidents) into foresight (planning), showing ways and means (improved engineering, procedure and supervision) to prevent the calculated accident from happening.  Visualize failure scenarios for the structures, handling equipment and estimate distances safe from damage. 

7.1.4. LEAKS AND SPILLAGES 

It will be of prime  importance  to protect  the marine and  terrestrial ecosystem during  the operations of  crafts. The various possibilities of  leakages and spillages of  the  fuel  includes following probabilities  1) Spillages of fuel during re‐fueling  2) Leakages of fuel during navigation  3) Leakages of fuel from storage tanks 4) Leakage or spillage during ship washing process 

7.1.4.1. Spillages of Fuel during Re‐ Fueling  

The crafts will require fueling its operation depending upon its trips two end fro. There will be a possibility of spillage of fuel during re‐fueling process. This may lead to disturbance in the shore ecosystem in a temporary manner. The spillage portion will be although small one, it may affect the natural marine life to save extent. To avoid such accidental spillage, following measures shall be adopted   

Proper routine checks shall be performed on the pipeline used for re‐fueling, various pumps, motor valves etc.  

Safety  audit  shall  be  performed  yearly  to  account  for  the  performance  of  the  re‐ fueling system. 

Chemical foam system shall be kept accessible to spray on the spillage.   Oil‐water separator shall be installed. 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  186 

Area of spillage will be contented using HDP or PE pipes.  Oil Spill Contingency Plan will be followed.  

In case of such a spillage oil‐water separator shall be immensely used to recover the oil spread on  the  surface  of  seawater.  In  case,  of  major  spillage,  containment  technique  shall  be employed immediately and oil shall be recovered without further spreading it on the sandy shore. Therefore, the major methods to be adopted for the oil spill closed to the shore shall be;  i)   Containment technique  ii)   Scavenging  iii)   Mechanical removal  iv)   Dispersion technique  v)   Use of absorbing material  Incase  Oil  spill  accident,  the  below  given  mitigative  measures  shall  be  taken  in  order  to preserve the mangroves from damage due to oil spill:  Booming and skimming of oil on the water surface in mangrove creeks  Pumping of bulk oil from the sediment surface, depressions and channels  Water flushing of free oil from sediment surface and mangroves into areas where it may 

be collected  Use of absorbent materials, with subsequent collection and disposal.  

7.1.4.2. Leakages of Fuel during Navigation  

There is a possibility of fuel being leaked from engine room because of various reasons. It may even happen during a collision and fuel/oil may spread on larger area in the sea. To prevent such  accidental  leakages,  proper mechanical maintenance  shall  be  carried  out  during  the routine surveys as mentioned above.  In case of  such an event  the craft  shall be very well equipped with recovery system. These leakages can lead to water pollution leading to damage to mangroves, fishes, spawning problems, distraction of marine eco‐culture, odor problem, and effect on marine bio‐diversity.  Various mitigation measures will be enforced depending upon type of oil, quantity of spread, distance from the shore, etc. such as: i. Burning of the oil  ii. Scheming the surface with a suction device iii. Absorbent technique  iv. Gelling method  v. SilIking method vi. Emulsification / dispersion 

7.1.4.3. Leakages of fuel from storage tanks   

There will be possibility of minor/major leak from the storage tank. It may be due to faulty materials of construction,  faulty erection, etc. Periodical checks shall be carried out of the tanks to find minor leakages, which may not be detected, in the routine course. Proper care 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  187 

should be taken to avoid the leakage of such materials into the sea. In case of such events following emergency measures shall be taken:  i. The marine terminal building shall be well equipped with oil containment facilities. ii. There shall be a small drainage system near the fuel storage tanks, which can carry the 

leaked oil to the oil‐water separator. The storage area is channelized with storm water drainage  with  inbuilt  oil  &  grease  traps  at  various  locations  which  shall  separate  oil discharges from the run‐off water. 

iii. Absorbent and dispersion techniques made available near the fuel storage tanks. iv. Intercepting  drains  will  be  provided  around  the  site  of  construction  and  designated 

places for the machines where refueling and change of lubricants shall be carried out, in order trap any oil & grease discharge from the same. 

v. The used oils and lubricants will be collected in drums from the equipment such as Diesel engines,  compressors etc and will be send  to  the  firm which  is MPCB authorized and registered with MPCB, for recycling. 

vi. These gases would be stored in enclosed tanks (Bullets) and would be routed through secured  pipelines  to  consumers  such  as  Automatic  Panel  Welding  Machine,  KOIKE machines etc the regular checks of gas cylinders and gas systems is carried out to prevent any gas leakages. 

vii. Proper channeling from all over the seaward side of the project side will be done such as to avoid any such spillage/ leakage to enter the sea‐water. 

7.1.4.4. Leakage or spillage during ship washing process 

Since the proposed terminal shall provide the berthing and parking facility of ships. There will be as such no major impact of oil spillage on the environment. However, there is a possibility of  spillage during  the  ship washing process  from  the  ship parking  facility.  These Spills  can further  contaminate  the  land as well  as water,  if  it  is  not properly  channelized. However, proper mitigative measures are taken in order to avoid any such spillage/ leakage during the workshop processes.   i. The  intercepting  drains  passing  from  the  area  are  installed with  oil  &  grease  trap  to 

entrap the oil spills, the remaining water will then be sent to sedimentation tank where it will be further treated for oil spills and pollutants. The treated water will be reused within the plant. 

ii. Awareness  amongst  the  workers  regarding  safe  handling  techniques  and  safety measures will be made through various workshops and seminars. 

iii. In case of any accidental spill, all processes will be brought to halt. 

7.1.5. RISK ANALYSIS STUDY 

Identification of potential physical hazards which could trigger loss causing events such as fire and explosion, leakage of flammable materials etc. from the proposed facility. 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  188 

Identifying the Maximum Credible Loss Scenarios (MCLS) for the vulnerable areas in the storage  areas  in  the  facility  for  assessing  the magnitude and  severity of  the  impact of various failure scenarios in terms of damage to property and injury to personnel.  

Recommendations  for  risk  reduction  shall  be  made  on  the  basis  of  the  above  for minimizing, if not eliminating various hazards and providing information on improvement of safety systems, where necessary.  

The major risk is envisaged from the storage yards, fueling of cargos. The leakage in piping, pumps and electrical fault can lead to hazardous event.  

A complete Risk Assessment will be done and the mitigative measures as well as safety measures will be proposed for the same. 

7.2. ONSITE EMERGENCY PLAN 

Assessing the adequacy of available resources to take care of emergencies as identified in the risk analysis study. Providing recommendations on the infrastructure, communication system and other facilities such as first aid, security, fire fighting etc. in view of effective handling of the emergencies identified. Specifying the roles and relationship amongst personnel from the facility  and  outside  agencies  for  effective  handling  of  the  emergencies.  Identification  of assembly  points  and  escapes  routes  for  evacuation.  Preparation  of  an  Onsite  Emergency Response Plan Document is envisaged. The stages of On‐site Emergency Plan include: 1. Outline Emergency Response Team. 

Designated person in charge.  Key responsibility of each individual.  Telephone numbers for key people. 

2. Risk Evaluation on preliminary hazards 

Type, Quantity and Storage method of Hazardous materials used at site along with MSDS. 

Location  of  possible Hazards  (Process,  Storage‐yard,  Transfer,  Piping,  etc.)\Type  of Accidents. 

Special handling requirements, fire fighting procedures as per MSDS.  Safety measures to be taken and installed if any. 

3.  Details regarding   Location of Key‐personals.  Emergency Control room, if provided.  Emergency Telephone numbers.  First‐aid Kit and Fire Extinguisher locations.  Warning alarm, safety and security.  Precautions during design and Engineering.  Continuous surveillance.  Details of Hospital and Fire‐brigade facility.  Procedures for notifying family members of injured employees.  Procedure for reporting emergencies. 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  189 

4. Awareness amongst workers for 

Knowledge of chemicals used (property, toxicity, handling methods, etc)  Use of fire‐fighting equipment and first‐aid.  Mock‐drill for Hazards and Disasters.  Use of personal protective equipment.  Procedure for reporting emergency.  Knowledge of alarm systems.  Manuals for each Operating system. 

5. Control Plans 

Emergency Control plans.  Safe time to resume work after an emergency.  Control measures for any spillage, leakage, explosion, etc. 

7.2.1. LIFE SAVING APPLIANCES AND ARRANGEMENTS  

It is one of the important aspects towards the mitigative measures to be adopted on the craft. It  is also recommended to have safety appliances and arrangements even at ship terminal facility,  in  case  of  emergency  for  the  craft  during  its  navigation.  Various  life  saving arrangements/appliances shall be made available for such eventualities. The major issues to be tackled for the life saving or rescue operations will be during any eventualities arising out of  collision  or  submergence  of  the  craft.  In  case  of  such  eventualities  various  life  saving appliances such as embarkation ladder, float free launching pads, spaces for laundry emersion suit inflammable appliances shall be made available on the craft. In addition to this life saving appliances an effective ladder communication system shall be made available on the crafts.  In the event of noting such as event at the marine terminal control room to allowing life 

saving appliances kept ready.  Rescue boat, which is design to rescue person in distress and to marshal survival craft.   Retrieval rescue team for the safe recovery of the survivors and evacuation.   Retro reflective material for detection of damaged craft in poor tight conditions   Embarkation ladder to permit safe access at the survival craft.   Live  saving appliances  such as  thermal, protective aid emersion  suit  radio  life  saving 

appliances radiotelegraph installations in lifeboats shall be made available.   Life  buoys  compiling  with  the  requirement  and  regulation  shall  be  kept  ready  and 

accessible during emergency life jackets etc shall be accessible  Trained personnel with experience of rescue operation shall be provided on board on 

rescue boat.   In  case  of  addition  to  the  rescue boat  craft with  all  novel  life  saving  appliances  it  is 

recommended that to take help of Coast Guards and also naval helicopters to search the exact site of accident.  

7.2.2. OCCUPATIONAL HEALTH AND SAFETY 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  190 

Specific occupational health and safety issues relevant to proposed project primarily include the following:    Physical hazards   Chemical hazards  Confined Spaces    Exposure to Organic Inorganic Dust  Exposure to Noise 

The main sources of physical hazards at ports are associated with cargo handling and use of associated machinery and vehicles. However this shall be taken care of by applying all  the terminal related norms and standards. The workers and vehicles passageway shall be kept separate. Avoiding entry of workers as far as possible in the area of ship loading and unloading activity and areas where grab is operational. The  chemical  hazards  are  related  to  inhalation  of  fumes  during  fueling  refueling  or  other emissions from the cargo. This can be eliminated by providing adequate personal protective Equipments to the workers working in such areas of exposure. The workers working in Confined spaces shall follow the General EHS Guidelines for working in confined spaces. They will also be provided with relevant personal protective equipment. Noise pollution can cause due to one of the various activities at the terminal or parking facility. However, proper mitigative measures are out‐lined for control of noise at the Facility. Onsite medical facility will be provided in case of any hazard or casualty during the operational phase. Fire safety measures shall be incorporated and implemented. Periodic health check‐up of all the workers shall be carried out. 

Table 7.1 Information to be Maintained of Emergency Response Agencies. 

No.  Personnel  Contact number 

1  Collector  +91‐2141‐222001, 02141‐222118

2  Ambulance suppliers  +91  2141  224515,  +91  2141 220225 

3  Police station  02141 222100, +912141240033 

4  Maharashtra  State  Electrical  Distribution Company Limited (MSEDCL)  1800‐1023435, 1800‐2333435 

5  Station help‐line number  086526 13697 6  State Transport Manager  02194 242447 7  Superintendent of Police  9870562001 8  Municipal Corporation  02141‐222015 9  Fire brigade near to jetty location  +91 02194163600 10  Earth moving machinery near jetty location  020 2428 1504 

11  Medical shops near 10 km area  +91  9420392691,  +91 9271777178 

12  Tahsildar  02145‐222142 13  Private transporters  +91 9226382172 

14  Maritime SAR (Search and Rescue operation) Emergency services to Indian coast guards  1554 

 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  191 

7.3. DISASTER MANAGEMENT PLAN (DMP) 

Disaster Management  implies  continuous  and  integrated  process  of  planning,  organizing, coordinating and  implementing measures  for natural and manmade events. Also, disaster. management is a set of actions and processes designed to lessen disastrous effects before, during and after a disaster. 

7.3.1. DISASTER MANAGEMENT PLAN OBJECTIVE 

To localize the emergency   To minimize the consequences  To ensure that the following concepts are considered, namely rescue, first aid, evacuation, 

rehabilitation, spreading the information  To identify type of major disasters which may occur   To minimize the effect of accidents  Elimination  of  hazard  will  require  equipment  like  fire  fighting  equipments,  water  sprays, emergency shutoff valves and purposeful construction. Minimizing the effect will be prompt action  by  operating  and  emergency  staff,  rescue,  first  aid,  evacuation,  rehabilitation  and giving information promptly to people living / working nearby. b)  Types of Possible Emergencies:  

Fire on berth / approach trestle / storage / buildings  Spillage while bunkering by vessel   Spillage due to collision in channel  Natural calamities like cyclone / rough weather / earthquake/ Tsunami  War situation/ Air strike.   

c)  Functions of Disaster Management 

Controlling spread of accidental effects with minimum damage  to men, material, machine and structures.   To inform relevant agencies and request for help.  To rescue victims and provide succor.   To protect other and safely evacuate.   To inform nearby inhabitations.   To identify the affected persons and inform their relatives.   To provide authentic information to news media and other.   To  preserve  relevant  records  and  equipment  needed  as  evidence  in  any  subsequent 

inquiry.  To rehabilitate the affected areas and alot specific assignment to available manpower. d) Classification of Accident 

Level I  : Operator Level Level II  : Local / Community Level Level III  : Regional level Level IV   : International level 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  192 

e) Critical Targets  

Disaster Management Plan is prepared after identifying the objects likely to be affected in the event  of  emergency.  The  target  of  fire  includes  personnel  if  emergency  occurs  at  service platform during discharging of vessel and tank farm on shore.  f) Control Room (CR) 

A control room will be established at a location away from likely spots of accidents and shall be easily accessible. Better location will be near the room from where all unloading operation are conducted and controlled.  

7.3.2. EMERGENCY PLAN FOR BERTHS AND VESSEL TERMINAL   

This plan will be drawn up in consultation with authority, fire brigade, coast guard and police etc. The plan will include:   Specific initial action to be taken by those at the location of emergency (to notify time, 

position source and cause of spill) to control room and Coast guard.  Immediate action to combat Oil –pollution.  Evaluations of situation by on scene controller regarding threat posed by spill and identify 

threatened resources.  Details of Communication system available siren code.  An inventory including location details of emergency equipment.  Sound alarm‐terminal fire fighting staff to fight fire.  Mobilize fire‐fighting equipment.  Electric power to switch off ‐ emergency lighting to switch on.  The ships calling at termianal will be advised of the terminal's emergency plan particularly   

the alarm signals and procedures to summon assistance in the event of an emergency, on board.  

7.3.3. ROUGH WEATHER  

The rough weather operations will be controlled in three stages   Green Status ‐ the operations of loading / unloading will be carried out as planned.  Yellow status ‐ This is an alert stage indicating possibility of rough weather, still operations 

can be continued with all emergency precautions.   Red  Status  ‐  Emergency  situation  or  rough  weather;  operation  will  be  suspended  ‐ 

Activities controlled by In charge of emergency operations. The vessel / tanker is to be unearthed to safe anchorage or will be advised to proceed to sea.  

7.3.4. FIRST AID & FIRE FIGHTING SERVICES 

The proposed project will have full‐fledged medical facilities as well as fire fighting facilities available in the area.  

7.3.5. IDENTIFICATION OF MAJOR HAZARDS 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  193 

The hazards occurring at Proposed Project can be broadly classified as natural and man‐made hazards. Some of the hazards existing at site are as follows:  Earthquakes  Fire  Tsunamis      

Earth Quake 

An earthquake is a sudden, rapid shaking of the Earth caused by the breaking and shifting of rock  beneath  the  Earth's  surface.  This  shaking  can  cause  buildings,  dams  and  bridges  to collapse;  disrupt  gas,  electric,  and  phone  service;  and  sometimes  trigger  landslides,  flash floods  and  fires;  all  these  are  possible  scenarios  at  Proposed  Project.  Buildings  with foundations resting on unstable soil and slopes are most at risk. The greatest danger for people in an earthquake exists directly outside buildings, at exits, and alongside exterior walls. Ground movement during an earthquake is seldom the direct cause of  death  or  injury. Most  earthquake‐related  casualties  result  from  collapsing walls,  flying glass, and falling objects.  

 

Fire 

Fire  is  the most  probable  emergency  scenario  at  proposed  project.  Fire  can  be  caused  in buildings  and  installations  as  electrical  fire,  chemical  fire  (leakage  of  LPG),  Fuel  fire  (HSD storage tanks) or fire in buildings. To handle this scenario an onsite emergency plan has been developed by the security team and is currently operational.  

Tsunamis 

Tsunamis are generated by large and rapid displacements of water, mainly from sudden and large scale changes in the configuration of the sea floor associated with fault displacement or gigantic underwater landslides, which could be mainly due to earthquakes. Earthquakes generate tsunamis by vertical movement of the sea floor as in normal faulting or thrust faulting. If the sea floor movement is horizontal, tsunamis are not generated as in strike slip earthquake. Sometimes they are triggered by marine landslides into or under the water surface,  also  generated  by  volcanic  activity  and  meteorite  impacts,  but  such  events  are extremely  rare.  Tsunami  hazard  along  a  coastline  is  therefore  a  combination  of  all  the potential sources of tsunamis that lie in the neighboring sea or ocean. Tsunami waves travel at a speed of approximately 700 km/ hr  in 4000 m of water.  In 10 m of water the velocity drops to about 36 km/hr. 

7.4. EMERGENCY RESPONSE MEASURES FOR NATURAL HAZARDS  

Natural  Hazards  cannot  be  prevented.  However  with  mitigation  measures  the effects/damages could be reduced.  

7.4.1. RESPONSE IN CASE OF EARTHQUAKE 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  194 

Response procedures for worker  1. If indoors: 

Take cover under a piece of heavy furniture or against an inside wall and hold on. 2. If indoors: 

Stop the process and move away from machinery, equipment, etc.  Avoid moving around until the shaking stops. 

3. If outdoors:  Move into the open, away from process area, office building and utility wires.  Gather  at  the  Evacuation  point  mentioned  during  the  safety  drill  and  await 

instructions. 4. If in a moving vehicle: 

Stop quickly and stay in the vehicle.  Once the shaking has stopped, proceed with caution.  

5. After be prepared for aftershocks.  Although smaller than the main shock, aftershocks cause additional damage and may 

bring  weakened  structures  down.  Aftershocks  can  occur  in  the  first  hours,  days, weeks, or even months after the quake. 

6. Help injured or trapped co‐workers.  Give first aid where appropriate. Do not move seriously injured persons unless they 

are in immediate danger of further injury. Call for help. Use Emergency numbers.  Stay out of damaged buildings, machinery, equipments.  Get your entire process area checked with Safety officers    Use the telephone only for emergency calls. 

Emergency Response Procedure 

1. Initiate the Quick Response Team and First aid team for earthquake response 2. Give a long siren for earthquake warning 3. Inform the necessary authorities for aid 4. Ensure no personnel or residents are stuck beneath any debris 5. Ensure that all residents and personnel standing outside near the buildings are taken 

to open areas. 6. Close the entry gate to restrict any incoming traffic 7. Inform Electrical department to shut off the utilities. 8. Ensure that the first aid ambulance and fire tender vehicles are mobilized 9. Ensure that emergency telephone number is only used for this purpose 10. Check the utilities and storage tanks for any damage. 11. Inform structural engineers to check for any damage to the Dam structure  

7.4.2. RESPONSE IN CASE OF FIRE 

On sighting a fire the first person should immediately inform the control room.  If the fire is small engage in extinguishing the fire using the nearest fire extinguisher or 

retrieve the property that may be damaged. 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  195 

Guide staff to the emergency assembly point.  The  control  room will  immediately  inform  the  first  aid  centre  and  the  quick  response 

team, which has trained fire‐fighting personnel. Mobilize the fire tender.  The Quick Response team will immediately move to the point of fire and take all necessary 

steps to stop the fire. If the fire is not controllable and spreads to the other    area then immediately  inform the security post who would  in  turn  inform the district authorities and call for external help. 

First  aid  team will  provide  immediate  relief  to  the  injured  personnel  at  the  scene  of   incidence. The patients would then be evacuated on priority to the dispensary or hospital based on their condition.  

 Instructions for an Individual in case of fire 

Get out of buildings as quickly and as safely as possible. If outdoors stop all processes and inform the control room using emergency alarm system and Emergency numbers. 

Use the stairs to escape. When evacuating, stay low to the ground. Evacuate and assemble at the assembly point decided previously. 

If possible, cover mouth with a cloth to avoid inhaling smoke and gases.  Close doors in each room after escaping to delay the spread of the fire.  If in a room with a closed door.  If smoke is pouring in around the bottom of the door or it feels hot, keep the door closed.  Open a window to escape or for fresh air while awaiting rescue.  If there is no smoke at the bottom or top and the door is not hot, then open the door 

slowly.  If there is too much smoke or fire in the hall, slam the door shut.  Call the security from the nearest phone   Inform security gate if there are any persons trapped in the house or injured.  Stay out of damaged buildings.  Check that all wiring and utilities are safe. 

 

7.4.3. RESPONSE IN CASE OF TSUNAMIS/STORM SURGES 

a) Structural measures: 

1. Construction of cyclone shelters 2. Plantation of mangroves and coastal forests along the coast line acting as Bioshields 3. Development of a network of local knowledge centers (rural/urban) along the coast lines 

to provide necessary training and emergency communication during crisis time 4. Construction of location specific sea walls and coral reefs in consultation with experts 5. Development of well designed break waters along the coast to provide necessary cushion 

against cyclone and tsunami hazards 6. Development of tsunami detection, forecasting and warning dissemination centres 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  196 

7. Development  of  a  “Bio‐Shield”  ‐  a  narrow  strip  of  land  along  coastline.  Permanent structures, if any in this zone with strict implementation of suggested norms. Bio‐Shield can be developed as coastal zone disaster management sanctuary, which must have thick plantation and public spaces for public awareness, dissemination and demonstration. 

8. Increasing the river dike height, increasing the height of the coast by filling up of coastal sand of the same place. 

9. Identification of vulnerable structures and appropriate  retrofitting  for  tsunami/cyclone resistance of all such buildings as well as appropriate planning, designing, construction of new facilities like  Critical infrastructures e.g. power stations, warehouses, oil and other storage tanks etc. 

located along the coastline.  All other infrastructure facilities located in the coastal areas.  Public buildings and private houses.  All marine structures.  Construction and maintenance of national and state highways and other coastal roads. 

 b) Non‐Structural Measures 

1. Coastal regulations Zone Act – Strict implementation.  2. Aggressive capacity building requirements for the local people and the administration 

for facing the disasters in wake of tsunami and cyclone, ‘based on cutting edge level’ 3. Developing tools and techniques for risk transfer in highly vulnerable areas 4. Conserving  and  developing  Natural  Bioshields  (Mangroves)  and  shelterbelt 

plantations (Casuarina) 5. Maintaining natural sand dunes.  6. Maintaining and promoting beach development. 7. Having diverse livelihood options. 8. Launching  a  series  of  public  awareness  campaign  throughout  the  coastal  area  by 

various means. 9. Training of local administration in forecasting warning dissemination and evacuation 

techniques 10. Awareness generation and training among the fishermen, coast guards, officials from 

fisheries department and port authorities and local district officials etc., in connection with evacuation and post tsunami storm surge management activities. Regular drills should be conducted to test the efficacy of the DM plans. 

7.5. IDENTIFICATION AND ASSESSMENT OF HAZARDS 

Storms,  Floods  and  fires  are  potential  disasters  for  such  Projects.  Their  likelihood  of occurrence and the resulting risk of damage should be incorporated into the design analysis of each project facility. 

Table 7.2 Summary of the Disasters Preparedness Plans 

DISASTER  DESCRIPTION  RESPONSE PLAN  STAGES 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  197 

Hurricanes and storms 

Depending  on  the  magnitude  storms can  damage  the  infrastructure  of  the project area to varying extent, thereby affecting its operation 

Hurricane Preparedness Plan Secure insurance coverage. 

Alert,  Response Recovery 

Earthquake  The  proposed  site  is  not  in  an earthquake  prone  area.  Thus  less chances of earthquake are envisaged. 

Building  and  construction shall  adhere  to  the earthquake efficiency norms. 

Planning, Response, Damage Assessment and Recovery. 

Fire   Fire  outbreaks  also  vary  in  size  and location and cause irreparable damage to the infrastructure. 

Fire  Prevention  and Preparedness Plan Install  fire  fighting equipments  Electrical  work  will  be  done by certified electrician. Provide  proper  Insurance coverage. 

Response, Planning  Fire Drills,  Damage Assessment. 

Oil  Spills  and leaks 

Oil  or  fuel  spill  due  to  accidents  or leakages pose a serious  impact  to the sensitive environment. 

Spill Contingency Plan All petroleum products stored in bunded areas. 

Report  and Response, Recovery 

Climate change 

This natural occurring phenomena can pose a risk to the project if not adapted in time. 

Contingency Plan Alert, Response

Medical   Medical emergencies can occur at any moment and therefore requires a quick and  coordinated  effort  to  respond  to the need. 

Medical Emergency Plan  First aid equipment and staff trained in CPR. 

Response, Recovery 

 

   

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  198 

Chapter8ProjectBenefit

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  199 

8. PROJECT BENEFITS  

8.1. ECONOMIC BENEFITS  

The EXIM trade due to this facility will increase and creating employment opportunity, supply chain management, facilities for industries in the Maharashtra. 

The development is envisaged to play a significant role in strengthening connectivity along the Maharashtra coastline.  

Enhancement  in economy of Maharashtra. The economic growth will have positive impact; it will also help in increase in living standards of the local residents. 

Substantial positive impact on socio‐economic profile of Revdanda, in Particular, and Raigad, in general, both in terms of overall employment and skill development of local workforce.  

Direct as well as indirect employment potential is envisaged.   Probable augmentation in infrastructure resources such as transport, Communication, 

health facilities & other basic facilities.  

8.2. SOCIO‐ECONOMICAL BENEFITS  

The socio‐economic scenario in the region will certainly change with positive impact on the existing regional socio‐economic pattern.  

There  will  be  change  in  employment  pattern  with  local  residents  will  be  given preference for jobs opportunities and/or self‐employment.  

Due to enhancement in infrastructure facilities and utilities in living condition will also improve.  

8.3. AESTHETICS AND LANDSCAPE  

It  is  proposed  to develop  greenbelt  around  the plant, which will  go  a  long way  to achieve environmental protection as well as aesthetics of the area.  

A  vegetative  cover  at  both  ends  of  the  project  and  also  along  internal  roads  will certainly reduce the air pollution.  

This vegetation cover will also act as a barrier for any penetration of air quality and odor in the nearby area.  

Approach  roads will be covered with green belt on both  the sides  to avoid any air quality problems to the nearby residents.  

8.4. CORPORATE ENVIRONMENTAL RESPONSIBILITY 

Plan  for  Corporate  Environment  Responsibility  (CER)  as  specified  under  Ministry’s  Office Memorandum issued vide letter F. No. 22‐65/2017‐IA.III dated 01.05.2018. 

With reference to the above OM following are the concerns raised during the public consultation and thereof the commitments made by the project proponent to address the same:

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  200 

SR. NO 

ISSUES RAISED WITH RESPECT TO ENVIRONMENT

COMMITMENT BY IEIL 

A. Korlai fort: With reference to MoM of public hearing held on 19th November 2016 

1.

Suffering of  local people due  to  coal dust nuisance. This may also affect the adjacent eco‐friendly  village  Chaul,  which  is  at  a distance of 400 mtrs. 

Use  of  slit  curtains  will  be  done  to minimize the coal dust emission. Also water spray or sprinkler system will be provided at  the barge unloader,  coal stacks and truck loading station. 

2.

Coal  and  other  mineral  material  will  be handled  in  the  project,  contamination  of sea water with  liquid material may occur, due to this many fishes may die.

Use  of  slit  curtains  will  be  done  to minimize  the  coal  dust emission.  For development of fisheries Rs. 6 crores are allotted under ESR activity. 

3.

Reserved  forest  Phansad  is  near  to  the proposed project site. Due to the project, activities  such  as  fishing,  ecology  of  the area and the reserved forest will be ruined.

Phansad wild  life  Sanctuary  is  ~  14.7 km  away  from  proposed  Korlai  Jetty and  ~  14.43  km  away  from  existing Sanegaon  facility,  hence  no  adverse impact is envisaged. 

4. Possibilities  of  noise  pollution  during handling of cargo. 

Use  of  noise  barrier  equipment  and roadside  plantation  may  aid  in reducing noise pollution 

5. Coconut and Arecanut cultivation may get burnt.   

6. Health and  livelihood of people will  be  in danger due to environmental pollution 

Proper  mitigation  measures  and implementation plan addressed in EIA report and  same will  be practiced  to avoid pollution. 

7. No  proper  facilities  available  for  material storage and transportation. This will affect the environment of the area

Raw  material  storage  facility  is earmarked and the location for same is shown in Chapter 2 of EIA report 

8.

In the report it is mentioned that there are neither mangroves nor mud at project site. Whereas mangroves and mud are present in the project site. 

The  proposed  area  is  devoid  of mangroves  except  for  sparse  and stunted patches. Site photographs are shown  in  EIA  report  chapter  3  Also, port area both the bank  line and the water area to be used for reclamation is devoid of any mangroves 

9. In the project it in mentioned that there is no creek. Creek exists in the project site. 

The  river  has  tidal  influence  water creek is certain part of river stretch,  as project  covers  large  stretch  of  the river common word river is utilized. 

10

Brinjals and vegetables cultivated by  local Christian  families  are  very  popular  in  the area.  The  project will  destroy  agricultural businesses in that area. 

Care will be taken that project will not hamper local community 

11There will be violation of Article 48, 51 of the constitution of  India due  to proposed project. 

No  violation  of  article  48  (organize agriculture and animal husbandry on modern  and  scientific  lines)  and  51 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  201 

SR. NO 

ISSUES RAISED WITH RESPECT TO ENVIRONMENT

COMMITMENT BY IEIL 

(international  peace  and  security) envisaged  

12Various species of birds and animals will be affected due to dust emissions done by the proposed project 

Proper mitigation measures proposed to combat dust emissions in the area due to proposed project. 

13 Kundalika river water pollution due to dust emission from the proposed project. 

Silt  curtains  to  be  used  to  minimize pollution of Kundalika river. 

14. B.  Sanegaon  Village:  With  reference  to  MoM  of  public  hearing  held  on  21st November 2016 

15 Nuisance problems due to dust emission is being  faced  by  the  local  people.  Coal powder is being deposited on surrounding trees. 

Use  of  slit  curtains  will  be  done  to minimize the coal dust emission. Also water spray or sprinkler system will be provided at  the barge unloader,  coal stacks and truck loading station. 

16 There will  be water  shortage,  agricultural and farming activities will be affected due to increase in river depth. 

In  construction  phase  water  will  be sourced  from  eater  tankers  and  in operation  phase  water  would  be received from the MIDC supplies.

17 Proposed  project  will  affect  the surrounding villages and mangroves due to excavation of mud from river. 

Care will be taken that mangroves are not affected. 

18 Kundalika  river  water  contamination  due to water sprinkled on coal. Fishes may die due to this. 

The effluent from coal stack yard will be collected  in clarifier wherein clear water  will  be  reused  for  sprinkling purposed  and  dust  particles  will  be resend  in  coal  stack  yard.  Further, water mixed with coal particles during sprinkling  will  be  collected  through channel  along  the  storage  into  a clarifier  system  wherein  water  and coal dust will be separated. Also, for development of fisheries Rs. 75  Lakhs  are  allotted  under  ESR activity.

19 Erosion  can  take place due  to  increase  in channel depth. 

Shoreline will  be  assessed  by  proper techniques  sometimes  involving mathematical/physical model  studies to  ascertain  remedial measures  such as  shore  protection  works,  sand  by passing etc. 

20 Coal transporting vehicles are overloaded, they  are  not  covered  in  tarpaulin  sheet. This is causing dust emission. 

Proper  precautionary  measures  will be adopted to minimize dust emission in  the  area  due  to  the  proposed project such as use of tarpaulin, water 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  202 

SR. NO 

ISSUES RAISED WITH RESPECT TO ENVIRONMENT

COMMITMENT BY IEIL 

sprinklers  and  maintained  speed limits. 

21 It  is wrongly mentioned that there are no wild  life.  Surrounding  area  of  700  to  800 acres  will  be  affected  due  to  increasing navigation channel depth. 

Care  will  be  taken  that  surrounded wild life will  are not affected. 

Additional as a responsible corporate, M/s Indo-Energy International Limited would integrate its environment, HR and ethical business policies with appropriate community engagement and gender equity. The major social sectors IEIL would emphasize for the local community developments are Education, Water Sanitation, Health, Livelihood and Empowerment, Sports, Environment, and Infrastructure Development. The total budgetary cost towards the CSR plan to be implanted is INR 40 Cr.

 

   

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  203 

Chapter9EnvironmentalManagement

Plan   

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  204 

9. ENVIRONMENTAL MANAGEMENT PLAN 

9.1. GENERAL 

An  Environmental Management  Plan  (EMP)  consists  of  a  set  of  mitigation measures  and compensatory.  These  measures  are  to  be  taken  during  the  construction  and  operational phase of the project to eliminate adverse environmental impacts, to offset them or to reduce them  to  acceptable  levels.  The  environmental  management  must  be  integrated  into  the process of project planning so that ecological balance of the area is maintained and adverse effects are minimized. EMP should be viewed as a commitment on the part of the proponent to minimize environmental impacts. 

Environmental Management Plan gives the tools to assess and manage environmental issues during every phase of project or operations. The outcome minimizes the risk of costly & time consuming environmental issues, while maximizing productivity and performance. It provides a  framework  through  which  environmental  priorities,  responsibilities  and  risks  are systematically managed. 

In many instances, it has been found that successful implementation of EMP has resulted in reduction  in project  costs  in  the  long  run. This  is because  the EMP contains proposals  for optimum usage of available resources plans to address minor faults at the initial stage.  

As mentioned in Chapter 1 & 2, proposed project is to develop Deep Water Jetty facility on Kundalika River, village Korlai and capacity expansion at existing Inland Water Jetty Facility, on Kundalika River at village Sanegaon, district Raigad, Maharashtra, hence, it is essential to ensure the quality of existing environment and maintenance of same. The proposed project should  incorporate environmental and technical alternatives at the  initial stages of project development.  

9.2. OBJECTIVES OF ENVIRONMENT MANAGEMENT 

The main aim of the EMP is to ensure that the various adverse impacts are mitigated and the positive impacts are enhanced which can be established as follows: 

To enhance the environmental and infrastructure  benefits of a proposal  To avoid, minimize or remediate the adverse impacts;  To ensure that the residual adverse impacts are kept within acceptable levels.  To maintain ecological  integrity and establish necessary action for unforeseen 

impact occur The EMP is proactive  in nature and should be upgraded if new facilities or modification of existing facilities, with environmental concerns, come up. 

EMP included four major elements: 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy 

International Ltd. 

TEPL/ENV/CBS/2021‐05  205 

Commitment  and  Policy:  The  project  will  strive  to  provide  and  implement  the Environmental Management Plan that incorporates all issues related to air, land and water. 

Planning: This  includes identification of environmental  impacts,  legal requirements, and  setting  environmental  objectives.  The  various  potential  impacts  are  discussed under chapter 5 

Implementation:  This  comprises  of  resources  available  to  the  developers, accountability  of  contractors,  training  of  operational  staff  associated  with environmental control facilities and documentation of measures to be taken. 

Measurement  and  evaluation:  This  includes  monitoring,  corrective  actions,  and record keeping. 

9.3. IDENTIFICATION OF IMPLEMENTING AUTHORITY 

The  responsibility  for  the  implementation  of  the  EMP  will  be  with  the  Promoter  and Contractor (P & C). An environmental management cell (EMC) will be established by the P & C for implementing the mitigative measures. To mobilize the appropriate expertise to design diverse type of mitigation measures. The P & C need to be collaborating with order institutions in the public and private sector viz. State Forest Department, State Public Health Engineering Department, State Traffic Department, and State Police Department etc. The EMC will ensure timely implementation of various mitigative measures at different stages of the project i.e. during construction and operation stage and the completion of the project within scheduled time frame.   

In  addition,  an  Environmental  Officer  will  be  appointed  by  project  authorities  for management of the project with the objective of reviewing and assessing the progress made by the concession company in implementing the suggested mitigative measures. 

9.4. EMP FOR CONSTRUCTION AND OPERATION PHASE 

This  section of  the  report  identifies  standard methods  and practices  as part  of mitigation measures with respect to environmental, social and health impacts identified generically and specifically for the proposed construction and operation of the project in chapter 5. For each aspect,  the  environmental  management  plan  is  prepared  to minimize  the  impact  on  the surrounding environment during the construction and operation phase. 

9.4.1. CONSTRUCTION PHASE 

Environmental impact from proposed development is likely to occur during the construction stage.  Following Table 9.1 outlines Environment Management Aspects and measure  to be monitored along with necessary action plan and its frequency during construction phase. 

 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy International Ltd. 

TEPL/ENV/CBS/2021‐05  206  

Table 9.1: Environment Management Plan for Construction Phase 

Sr. No. Environment Management Aspects 

Measures  to  be Monitored 

Action Plan Frequency (as per action plan)

Resources Required  Responsibility 

1. Air quality PM10 & PM2.5 in Airfor  monitoring  dust emission 

1. Vehicles  carrying construction material and storage  area  to  be covered by traps. 

2. Regular  Water  sprinkling on roads 

3. Maintenance  and servicing  of  construction machinery  / transportation vehicle. 

Regularly  during construction period 

1. Covered storage area 2. Water sprinklers 3. Maintenance  and 

servicing    and  keeping valid  certificates  and records 

Promoter  and Contractor  

2. Noise level   Monitoring  of  noise level 

1. Construction  activities strictly  prohibiting between 10 pm and 6 pm near habitation 

2. Provision  of  Personal protective  equipment  to workers  being  exposed high noise levels 

3. Vegetative  and  solid barrier  along  inhabitant centre  and  sensitive receptor. 

4. DG  set  with  acoustic enclosure  

Regularly  during construction period 

1. Vegetation  cover surrounding  the construction area  

2. PPE to workers 3. Acoustic enclosure 

Promoter  and Contractor 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy International Ltd. 

TEPL/ENV/CBS/2021‐05  207  

Sr. No. Environment Management Aspects 

Measures  to  be Monitored 

Action Plan Frequency (as per action plan)

Resources Required  Responsibility 

3. Water quality  Quality  of  marine water and sediment

1. Training to all workers on best  practices  to  avoid spilling of raw materials & avoid  run‐off  from site  to be enforced. 

2. Storm  water  during monsoon  to  be  properly channeled  

3. Stored raw materials to be covered properly to avoid run‐off 

4. Monitoring  and  guidance to workforce 

Monthly  during construction stage

1. Training to workforce2. Silt  curtain/suitable 

barriers   3. Regular  checking  and 

maintenance  of construction  machinery to  be  done  to  avoid spillage  of  oil  and hazardous substance. 

4. Cleaning of channels for discharge storm water. 

5. Scheduling  of ship/vessel trips 

Promoter  and Contractor 

4. Soil Quality   Physiochemical parameter  

1. Storage of raw material in  covered  designated areas  to  avoid  soil contamination. 

2. Solid  waste  generated will  be  segregated accordingly and handed over  to  the  respective authority  for  final disposal 

3. Provision of toilets

Regularly  during construction period 

1. Covered storage area.2. Color coded containers 

will  be  provided  for solid waste collection. 

3. Regular  maintenance of toilets 

Promoter  and Contractor 

5. Marine ecology  Mangrove enumeration 

1. Mangrove management plan  for  the conservation  

Regularly  during construction period 

1. Following  the  sketched plan  Promoter  and 

Contractor 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy International Ltd. 

TEPL/ENV/CBS/2021‐05  208  

Sr. No. Environment Management Aspects 

Measures  to  be Monitored 

Action Plan Frequency (as per action plan)

Resources Required  Responsibility 

6. Occupational  Health and Safety 

1. Training  to workforce 

2. Usage of PPE by workforce 

1. Training to all workers on health  and  safety  best practices 

2. Provision  of  PPE  to workforce 

Regularly  during construction stage

Training  and  PPE  to  the workforce 

Promoter  and Contractor 

7. Dredging management 

Dredging  material disposal 

Dredging material to be use for backfilling and  disposal to selected site   

As  per  required quantity 

Licensed  carriers  to transport and    disposal  at designated site  

Promoter  and Contractor  

8. Spillage management 

Spillage  of  oil  from heavy vessels Oil contingency plan  Regularly  during 

construction  Equipment and Personnel  Promoter  and Contractor 

9. Traffic management Record maintenance  of vehicle and ships 

Traffic management plan  Regularly  during construction stage

Skilled Workforce  and  data 

management 

Promoter  and Contractor  

 

9.4.2. OPERATION PHASE 

An Environment Management Plan for the operation phase of proposed project is given below in Table 9.2 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy International Ltd. 

TEPL/ENV/CBS/2021‐05  209  

Table 9.2: EMP for Operation Phase 

Sr. No. Environment Management Aspects 

Measures  to  be Monitored 

Action Plan  Frequency Resources Required 

Responsibility 

1.  Air  monitoring  for PM10 and PM2.5 (dust emission) 

Air quality 

1. Vegetation cover 2. Enforcing  different 

control  measures  to check pollution  Regularly  (as 

required) 

Periodic maintenance  of vegetation cover. 

Promoter  and Contractor  in consultation with MPCB 

2.  Road Safety and Traffic Management  Traffic management 

1. Adequate  number  of proper  &  legible  signs will  be  installed  along the road. 

2. Prepare  and  administer a monitoring system on road/ accidents. 

Regularly  (as required)  Skilled workforce 

Promoter  and Contractor  in consultation with  Public Works Department  and State  Traffic Police 

3.  Marine environment 

Water  &  sediment physio‐chemical parameter  (as  per CPCB norms) 

1. Regulation of ship waste2. Provision of storm water 

drainage system 3. Follow MARPOL norms  

Regularly (as required)  

1. Proper  record maintenance of waste regulation. 

2. Maintenance of drainage system. 

Promoter through prospective contractor 

 EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy International Ltd. 

TEPL/ENV/CBS/2021‐05  210  

Sr. No. Environment Management Aspects 

Measures  to  be Monitored 

Action Plan  Frequency Resources Required 

Responsibility 

4  Solid and liquid waste  Waste management 

1.  Strict  following  of  solid waste  &  liquid  waste management at site 2. Follow MARPOL norms 

Regularly  (as required) 

Dustbins,  waste collector  

Promoter through prospective contractor 

Occupational  Health and Safety  health  of  worker  and 

accidents at site Provision  of  PPE/PPA  to workforce  Regularly 

Personal  protective equipment’s(PPE)/ Personal  protective apparel(PPA)  and training 

Promoter through prospective contractor 

EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy International Ltd.  

  

TEPL/ENV/CBS/2021‐05  211 

9.5. DETAILS OF MANAGEMENT PLANS  

9.5.1. WATER MANAGEMENT 

The water constitutes one of the major component and its consumption and generation of waste accounts  for  the major environmental  factor.  The water management  includes  source of  raw water, storage and treatment of raw water and its consumption in various uses. Generation of used  /  waste  water,  its  treatment  and  disposal,  recycling/  reused  possibilities.  It  is  a  prime concern  and  duty  of  the  project  proponent  to  initiate  and  implement  a  proper  water management plan during construction and operational phases. A water storage system to meet the demands of the proposed facilities can be created with a connection from the main supply line of MIDC / MJP. During construction phase most of the water will be required for the various construction activities,  hydraulic  tests etc.  and also  for  labour  camp.  The water  consumption during the operational phase will be consumed for domestic purposes.  

During operation phase, sewage generated will be treated in sewage treatment plant and treated wastewater  will  be  reused  in  gardening  and  for  dust  suppression.  The  sludge  from  sewage treatment will be used as manure. The effluent from coal stack yard will be collected in clarifier wherein clear water will be reused for sprinkling purposed and dust particles will be resend in coal stack yard. A drainage system will be provided with buried perforated drain lines connected to open concrete trenches. 

9.5.2. CONTROL OF WATER POLLUTION FROM MARINE TRANSPORTATION 

The International Convention for the Prevention of Pollution from Ships, 1973, as modified by the protocol of 1978 (MARPOL, 73/78), has issued guidelines for prevention of Marine Pollution. Some of  the guidelines applicable for  the proposed project are  listed as below and should be strictly adhered to for prevention of marine pollution. 

Ships are prohibited to discharge oil or oily water such as oily bilge water containing more than 15 ppm of oil within 19 km (12 miles) of land 

Sewage generated at the ship should not be disposed off into the sea, unless it is treated or it is disposed off at a certain distance from land  

No ballast water containing harmful aquatic organisms or pathogens may be discharged from a vessel into waters. 

All vessels must be operated in compliance with the requirements specified in that marine pollution prevention Convention.  

A person wishing to discharge a pollutant or harmful substance for the purpose associated with responding to a specific pollution incident shall apply in writing to the Director for a Discharge Permit and shall provide the required information 

EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy International Ltd.  

  

TEPL/ENV/CBS/2021‐05  212 

All  vessels  will  comply  with  all  of  the  design  and  pollution  prevention  equipment provisions specified in that Convention. 

Garbage produced on ship must be kept on board and discharged either ashore or into the sea under certain conditions, such as distance from the land; discharge of all plastics is prohibited. 

 Water Conservation Management Plan 

It  will  be  the  prime  duty  and  concern  of  the  promoters  to  scientifically  planned  water conservation and its management. Water conservation plans consists of recycling of wastewater, enforcing alternative sources of water and reduction or minimization of water consumed. 

Water consumption minimization 

This can be achieved by using various water saving appliances and water management measures in a planned way. The water management measures message will be spread to all users by way of  signage  and  awareness  posters  at  the  proper  locations.  Specific  measures  that  will  be implemented include the following: 

Reduce toilet cistern volume in single flush models  Promote awareness on water conservation and reducing water wastage.  Drip irrigation system shall be used for  lawns and other green area. Drip  irrigation can 

save between 15‐40% of the water use, compared with other watering techniques.  Use of low‐ volume, low‐ angle sprinklers for lawn areas.  Select controllers with adjustable watering schedules and moisture sensors to account for 

seasonal variations, and calibrate them during commissioning. 

9.5.3. SOLID AND HAZARDOUS WASTE MANAGEMENT PLAN 

The project development will be carried out in phases. The port will generate floating population, thus the quantity of waste generated will vary. However, on an average waste generation will be constant, and a broad outline on reducing the effect of solid waste on the environment is given below. 

During construction phase, the project site will generate large amount of waste. The solid wastes will be generated in the form of dredged material during construction and dredging activities. Wastes from construction activity includes, construction debris and other waste. The following section  discusses  management  of  each  type  of  waste.  Being  predominantly  inert  in  nature construction  and  demolition  waste  does  not  cause  chemical  or  biological  pollution.  Hence, maximum effort should be done to reuse the waste. 

EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy International Ltd.  

  

TEPL/ENV/CBS/2021‐05  213 

The dredged material generated during maintenance dredging will mainly consist of soft silty clay which shall be reused for reclamation and remaining waste will be disposed off in deep sea. 

Saleable items such as metal scrap should be kept separately and cleared off as soon as possible. 

Large unusable material should be sent for land filling in designated areas of Municipal Corporation. 

Recycled  aggregate  will  be  used  for  filter  application,  and  as  a  sub‐base  for  road construction. Mixed debris with high gypsum, plaster shall not be used as fill, as they are highly susceptible to contamination, and will be given to recyclers. 

Bricks  and  rubbles  can  be  used  as  fill material  at  project  site  or  sold  to  vendors  and builders. 

During construction also this management practice would be implemented. Non‐reusable waste will be disposed of at approved dumping ground and landfills. 

In  the  operation  phase  only  organic  and  in  organic  waste  will  be  generated  from  proposed Project. Apart from organic waste or food scrap there will be paper and plastics in considerable amount.   

MoEFCC  formulate  the  draft  Municipal  Solid  Waste  (Management  and  Handling)  Rules  in September 1999 and subsequently notified the MSW rules in September 2000. The management of MSW is covered under the schedule II of the Rules and provides directions for segregation, collection, storage, transportation, processing and disposal of waste.  

9.5.4.  OTHER WASTE 

Construction sites are sources of some toxic substances, such as paints, solvents, adhesives and sealants. Empty containers of these substances shall be returned back to the manufactures or dealers as the case may be.  

Some management practices to be developed are:  

Paint brushes and equipment  for water and oil based paints shall be cleaned within a contained  area  and  shall  not  be  allowed  to  contaminate  site  soils,  watercourses,  or drainage systems. 

Provide adequate hazardous waste storage facilities and taking away by the supplier any balance material after use. 

Clearly label all hazardous waste containers with the waste being stored and the date of generation. 

Educate employees and sub‐contractors on hazardous waste storage. 

EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy International Ltd.  

  

TEPL/ENV/CBS/2021‐05  214 

Instruct employees and sub‐contractors in identification of hazardous and solid waste 

9.5.4.1. Public Awareness 

Public awareness will be there on waste segregation and disposal rules. The residents, workers and staff periodic awareness talks will be given waste management. Signboards and information boards will be put up in required area in English and local language (Marathi). 

9.5.4.2. Waste Segregation 

The debris generated due to dredging will be majorly used for reclamation of backup area of the port and the balance  is  to be disposed  in deep sea. The other solid waste will be segregated. Recyclable waste will  be disposed of  through approved  vendors  and  remaining waste will  be disposed off though approved facility.  

9.5.4.3. Waste treatment and disposal 

During construction phase sewage will be generated from workers camp which will be treated in STP. Total sewage generation during operation phase will be 28.3 m3/day. Sewage Treatment Plant of capacity 30 m3/day will be provided to treat the sewage. Treated sewage will be used for gardening, dust suppression and the sludge will be used as manure.  In any case there will be no disposal of treated sewage in marine water.  Water mixed with coal particles during sprinkling will be collected through channel along the storage into a clarifier system wherein water and coal dust will be separated. Clear  

9.5.5. ENERGY CONSERVATION 

Energy conservation measures are often the easiest, quickest and cheapest way to reduce costs and be environmentally pro–active. Energy conservation program will be implemented through measures taken both on energy demand and supply. 

 

 

Supply  Energy Conservation

Demand 

Utilize energy –efficient diesel generators 

Exploring  the  possibilities  of introducing renewable energy  

Reduce Consumption  Use energy efficient appliances  Create Guest Awareness  Segregation  of  Areas  for  light 

points 

EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy International Ltd.  

  

TEPL/ENV/CBS/2021‐05  215  

Figure 8.1: Energy Conservation Model 

Energy conservation will be one of the focuses during the complex planning and operation stages. The conservation efforts would consist of the following: 

Architectural design 

Maximize the use of natural lighting through design Energy Saving Practices 

Purchase of energy efficient appliances  Constant monitoring of energy consumption and defining targets for energy conservation  Adjusting the settings and illumination levels to ensure minimum energy used for desired 

comfort levels.  Use of compact fluorescent lamps and low voltage lighting  Sunscreen films on windows to reduce heating inside the building 

Behavioral Change on Consumption 

Promoting awareness on energy conservation among the employees and staff.  Training staff on methods of energy conservation and to vigilant to such opportunities. 

9.5.6. PLANTATION, LANDSCAPING AND ECOLOGICAL MANAGEMENT 

During the construction phase, following precautions should be followed: 

Restriction of construction activities to defined project areas, which are ecologically less sensitive. 

Restriction on location of labour camps and offices for project staff near the project area to avoid human induced secondary additional impacts on the flora and fauna species. 

Cutting, uprooting, coppicing of trees or small trees present in and around the project site for cooking, burning or heating purposes by  the  labors will be prohibited and suitable alternatives for this purpose will be found. 

After  completion  of  major  construction  work,  the  green  belt  will  be  developed  with recommended plant species, as there will be no or less disturbance in these areas.  

Cutting, uprooting of existing plants in the periphery will be prohibited and other plants in the site will be minimized. 

After completion of soil work, temporary vegetation preferably grasses to be planted to minimize soil erosion. 

EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy International Ltd.  

  

TEPL/ENV/CBS/2021‐05  216  

During, operation phase, enhancement of the current ecology at the site will be done through the following measures: 

Plantation and Landscaping  Green belt development 

In  green  belt  development,  a  suitable  plantation  matrix  will  be  adopted  for  the  green  belt development. It will also include earth filling and providing manure, which may be required for the proper nutritional balance and nourishment of the sapling.  

9.6. ENVIRONMENT MANAGEMENT COST 

An effective Environmental Management Plan (EMP) is proposed for the construction phase and operational  phase of  the project  to  conserve  the environment  at  site.  .  The  total  cost of  the  project is INR  2000 Crores. For Phase I – INR 1160.83 Cr, For Phase II‐ INR 408.70 Cr, For Phase III‐ INR 430.70 Cr. The cost estimates for implementing EMP during construction phase shall be Rs. 21.10 lakh and for operation phase shall be 10.00 lakh. The details of EMP are as under Table 9.3 and Table 9.4 

Table 9.3 Budgetary rovision for EMP during Construction Phase 

SN  Parameter  Total Cost Rs. (in lakhs) 

1  Pollution Control Measures   Water sprinklers for dust control  02.00   Acoustic enclosures  01.20   Solid Waste Management   00.40   For marine‐ silt curtain  07:50 2.  Environmental Monitoring (As per CPCB norms)  03.00 3  Occupational Health & Safety Measures   Personal Protective Equipment  01.00   Health Check Up   01.50   Fire Management  01.50   EHS Training Programs  03.00 Total cost  21.10 

Table 9.4 Budgetary Provision for EMP during Operation Phase 

SN  Parameter  Total Cost Rs. (in lakhs)/year 

1.   Environmental Monitoring (As per CPCB norms)  03:00 2.   Solid  & Liquid Waste Management  01:00 3.   EHS Training Programs & Health Check Up  05:00 4.   Miscellaneous  01:00 

EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy International Ltd.  

  

TEPL/ENV/CBS/2021‐05  217  

SN  Parameter  Total Cost Rs. (in lakhs)/year 

Total Cost  10.00 

The  Environmental  Management  Plan  should  be  effectively  implemented  so  that  maximum benefit could be achieved 

9.6.1. ENVIRONMENTAL TRAINING 

The Environment Management Cell (EMC), in addition to implementing and monitoring different environmental  attributes,  will  also  be  actively  involved  in  imparting  training  and  raising environmental  awareness  of  Construction  Engineers/  Contractors  and  other  staff  members/ workers so as to enable them take the environmental aspects into consideration as and when required. In the long run, the EMC can impart additional and specialized training in environmental management of the road and building construction system. 

   

EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy International Ltd.  

  

TEPL/ENV/CBS/2021‐05  218  

Chapter10Summary&Conclusion

EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy International Ltd.  

  

TEPL/ENV/CBS/2021‐05  219  

10. SUMMARY & CONCLUSION 

10.1. SUMMARY 

The IEIL proposes to develop Deep Water Jetty facility on Kundalika River, village Korlai, district Raigad, Maharashtra and capacity expansion at existing Inland Water Jetty Facility, on Kundalika River at village Sanegaon, district Raigad, Maharashtra. The proposed port will be developed in 3 phases, at Korlai Phase I‐9.25 MMT, Phase II‐16.75 MMT, Phase III‐23.50. Geographical coordinates of project is 18°32’ 10.92” N, 72°55’ 11.65” E. Capacity expansion at Sanegaon will be achieved by all year round operations as mother vessels will discharge at Korlai Jetty, by using bigger size barges of 4500 DWT and by dredging of channel from Korlai to Sanegaon to 3.1 m CD. 

IEIL is presently engaged in transportation and trading of Coal using lighterage facility at Sanegaon, located on the Right Bank of the Kundalika River, about 50 km south of Mumbai by sea and about 130 km by road. IEIL intends to expand the facility to include the coal required for the proposed power plant planned to be located close to the riverine facility at Sanegaon. The existing Jetty is about 21 km upstream on the right bank of the river Kundalika and is about 200 m long with a backup area of about 5 hectare for storage, handling and dispatch of material. The clear span between the intermediate bridge piers is 36 m in the road bridge across the Kundalika River at Revdanda. 

The proposed project attracts Environment clearance under Sector 33 and falls in category A as per EIA Notification 2006 and its subsequent amendments as project attracts general condition.  

Further it also attracts CRZ Clearance under CRZ notification 2011. The proposed deep water jetty facility project falls under CRZ IVB, II and IB according to the CRZ map, whereas, capacity expansion of existing inland water jetty facility at Sanegaon falls under CRZ III, CRZ I. The CRZ map (HTL/LTL Demarcation) for this project is prepared by National Centre for Sustainable Costal Management (NCSCM) Chennai. 

Public Consultation was  carried out at  two different  locations  for Korlai  and  Sanegaon projects.    First public hearing for Korlai Project was held at Mount Carmel High School, on 19.11.2016, Second hearing was held for Sanegaon Project on 21.11.2016  near project site respectively and public MoM of same is published by MPCB (Raigad II SRO). 

As per EIA Notification 2006 and its amendments, ToR application were submitted to MoEFCC for grant of  ToR  on  10th  November  2015  and  further  presentation was  held  in  EAC meeting  on  21st    and  22nd December 2015, TOR was issued on 28th January, 2016 vide letter no. F. No.10‐34/2015‐IA.III and extended by one year in 2019. 

The proposed project involves development of the jetty about 525 m long with one 8 m x 8 m mooring dolphin on the east side. The project will involve dredging a 14.5 km channel requiring 11 million cum of dredging for a depth of 11.0 m CD in Phase I. In second phase channel length would increase to 17.5 km and would require 23 million cum (i.e. 12 million cum additional) of dredging for a channel depth of 14.6 m CD. In the final phase the channel length would increase to 21.5 km and would require 35.5 million cum 

EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy International Ltd.  

  

TEPL/ENV/CBS/2021‐05  220  

(i.e. additional 12.5 million cum) dredging for a channel depth of 19.0 m CD and Dredging of 0.99 Mm3 in the inner channel from Korlai to Sanegaon for a depth of 3.1 m CD. 

The salient features of proposed facility are as following: 

a. The  Jetty  will  be  provided with mobile  harbour  cranes  in  the  first  phase  and with  fixed  ship unloaders in the final phase. 

b. The equipment will discharge in to hoppers and through covered conveyors to the covered stock yard. 

c. Dust suppression mechanisms would be in place. d. Palletized cargo and containers would be handled using mobile harbour cranes and taken to the 

yard by tractor‐trailers. e. The cargo receipt and dispatch would be fully mechanized. f. The barge loading system would be installed for emission free loading. 

Local labours will be hired during construction phase and operation phase. Total manpower requirement for construction phase will be about  850 and operation phase will be 350 no.  

The total water requirement, the per capita consumption for the in port consumption is taken as 90 liters per day. The occupancy is taken as 350 in the port. Total consumption will be 31, 500 liters per day. The water requirement shall be sourced from MIDC or irrigation department.  

During construction phase sewage will be generated from workers camp which will be treated  in STP. Total sewage generation during operation phase will be 28.3 m3/day. Sewage Treatment Plant of capacity 30  m3/day  will  be  provided  to  treat  the  sewage.  Treated  sewage  will  be  used  for  gardening,  dust suppression and the sludge will be used as manure. In any case there will be no disposal of treated sewage in marine water. Water mixed with coal particles during sprinkling will be collected through channel along the storage into a clarifier system wherein water and coal dust will be separated. 

For power requirement, it is proposed that the incoming HT supply is taken from the nearest substation at voltage level of 33 KV. Single transformer of capacity of 33 KV/ 11 KV, 12 MVA oil filled out door type shall be installed. A 33 KV switch yard is to be set up near to the Port area from where three or four 11 KV feeders are taken to feed the port equipment. 33 KV and 1l KV control rooms are required near the yard. 11  KV  supply  will  feed  Transformers  for  Dry  Bulk  Terminal  (Iron  Ore),  Dry  Bulk  Terminal  (Coal)  and common utility. Each Transformer size could be selected based on the individual total connected load. 

The debris generated due to dredging will be majorly used for reclamation of backup area of the port and the balance is to be disposed in deep sea at designated area. The other solid waste will be segregated. Recyclable waste will be disposed of through approved vendors and remaining waste will be disposed off though approved facility.  

The project  implementation schedule will be of 30 months. The total cost of  the   project  is  INR   2000 Crores. For Phase I – INR 1160.83 Cr, For Phase II‐ INR 408.70 Cr, For Phase III‐ INR 430.70 Cr.   

EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy International Ltd.  

  

TEPL/ENV/CBS/2021‐05  221  

Primary and secondary data were used to assess the environmental impacts of the proposed project. The environmental impacts were anticipated in a comprehensive manner. 

The baseline data was studied  for understanding  the existing environmental  setting of  the study area (within 10 km radius of the proposed project site).  

Monitoring (sample collection and analysis) by NABL approved lab was done in pre‐monsoon and post‐monsoon season; the following environmental components were studied: 

Land   Soil environment   Water environment  Marine environment  Biological environment  Air environment  Noise     Socio‐economic status 

Baseline data analysis showed most of the parameters of the environmental components to be within the prescribed limits.  

The  anticipated  impacts  on  the  environmental,  social  and  health  components  associated  with  the proposed  project were  identified  and mitigation measures  are  proposed  for  the  same. Marine water quality and biology is likely to be impacted during construction phase. 

As part of mitigation measures with respect to environmental, social and health impacts identified for the proposed  project,  the  environmental  management  plan  is  prepared  to  minimize  the  impact  of atmospheric emissions, spillage, solid wastes & noise generation on the surrounding environment during the construction and operation phase.  

The  cost  estimates  for  implementing  EMP  shall  be  INR  1.5  Crores.  The  cost  includes  solid  waste management, installation of sanitary facilities, STP, ETP, noise meters green belt development etc. The cost  required  for  implementation  of  Environmental  Monitoring  Programme  for  marine  ecology  and ambient air quality during construction phase is INR 35 lacs. 

The cost required for implementation of Environmental Monitoring Programme for marine water quality, ambient air quality monitoring and effluent management from coal stack yard during operation phase is INR 75 lacs per annum. 

The cost estimates for implementing EMP during construction phase will be Rs. 21.10 lakhs and Rs. 10.00 lakhs during operation phase. 

As a responsible corporate, M/s Indo‐Energy International Limited would integrate its environment, HR and ethical business policies with appropriate community engagement and gender equity. The major  social  sectors  IEIL would  emphasize  for  the  local  community  developments  are  Education, 

EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy International Ltd.  

  

TEPL/ENV/CBS/2021‐05  222  

Water  Sanitation,  Health,  Livelihood  and  Empowerment,  Sports,  Environment,  and  Infrastructure Development. The total budgetary cost towards the CSR plan to be implanted is INR  40 Cr. 

Additionally, the proposed project will provide direct and indirect employment to skilled/unskilled and semiskilled  labourers  to  about  1200  pople.  Directly  boost  defence  infrastructure which will  indirectly provide social benefits during national emergency too. 

10.2. CONCLUSION  

From  the  Environmental  Impact  Assessment  study,  it  can  be  concluded  that  this  project  under consideration will not have any significant negative impacts. All possible environment aspects have been adequately  assessed  and  necessary  control  measures  have  been  formulated  to  meet  the  statutory requirements. Thus implementing this project will have positive impacts.   

EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy International Ltd.  

  

TEPL/ENV/CBS/2021‐05  223  

Chapter11DISCLOSURE

OFCONSULTANTS

EIA for proposed jetty at Korlai River and expansion of existing jetty at Sanegaon by Indo Energy International Ltd.  

  

TEPL/ENV/CBS/2021‐05  224  

11. DISCLOSURE OF CONSULTANTS 

11.1. ABOUT CONSULTANT 

M/s. Terracon Ecotech Pvt. Ltd. (TEPL) has created a visible difference in the domain of ecology, biodiversity,  environment  and  sustainability  since  its  formation  in  2008.  Having  worked  and completed more than 80 projects with 40+ clients spread over 12 states of India has resulted in country wide  exposure  and  experience.  An  experienced  team  of  experts  (both  in‐house  and empaneled)  that  intersect  science/research,  business  and  advocacy  provides  much  needed balance  to  understand  and  create  client  specific  solutions  in  the  areas  of  environment, sustainability and natural resource management.  

TEPL  is  a  BIS  quality  approved  certified  (ISO  9001:2008)  firm  which  favors  the  sustainable management of natural resources as well as the protection of the environment. In its recognition of humanity as a participant in ecosystems, the movement is centered on ecology, health and human  rights.  Conservation  of  environment  simply  implies  the  sustainable  use  as  well  as management of natural resources which include wildlife, water, air, and earth deposits. 

11.2.   ACCREDITATION OF ORGANISATION 

TEPL mission is to serve government and industries with its technical and business knowledge in delivering sustainable solutions that ensure growth in their economic, social and natural capital. 

M/s. Terracon Ecotech Pvt. Ltd.  (TEPL) 202, Kingston Tejpal  road, Vile Parle  (East), Mumbai  is accredited under QCI‐NABET Accreditation Scheme for EIA Consultant Organization (Version 3). Certificate No. NABET/EIA/1619/RA 0029, Issue date: 14th Feb 2017, Category ‘A’. 

  Organization’s  aim  to be  India’s  leading ecological  solutions & natural  resource management strategic consultancy firm. Its strengths include its technical knowledge and capabilities in the domain  of  ecology,  botany,  agriculture  and  environmental  science,  as  well  as  its  deep understanding of today’s sustainability issues and ability to design forward‐thinking sustainability strategies. 

11.3. SERVICES 

TEPL services and offerings i.e Urban Ecology, Biodiversity Conservation, Marine Ecology, Natural Resource Management,  Ecological  Restoration,  Energy Management,  Sustainability & Climate Change, Renewable Energy, Carbon Advisory & Environmental Finance Services are suitable for Central  Government,  State  Governments,  Local  Governments,  Zilla  Parishads,  Municipal Corporations, as well as Panchayats, Non – Government Organizations, Industrial projects.   

 

 

 

 

 

 

 

Annexure 1 

Awarded ToR 

Scanned by CamScanner

Scanned by CamScanner

Scanned by CamScanner

Scanned by CamScanner

 

 

 

 

 

 

Annexure 2   

Ship tranquillity study   

Mathematical Model Studies for the Development of the Direct Berthing Deepwater Jetty inside the Revadanda Creek and the Inland Water Facility at Sanegaon, Raigarh, Maharashtra

Mathematical Modelling

Final Report

June 2016

This report has been prepared under the DHI Business Management System certified by BVC to comply with ISO 9001 (Quality Management), ISO 14001 (Environmental

Management), OHSAS 18001 (Health and Safety Management)

Approved by Dr. Flemming Jakobsen Managing Director

DHI (India) Water & Environment Pvt Ltd•NSIC Bhawan, IIIrd Floor, NSIC-STP Complex•Okhla Industrial Estate•IN-11 00 20New Delhi• India

Telephone: +91 11 4703 4500 • Telefax: +91 11 4703 4501 • • www.dhigroup.com

Mathematical Model Studies for the Development of the Direct Berthing Deepwater Jetty inside the Revadanda Creek and the Inland Water Facility at Sanegaon, Raigarh, Maharashtra

Mathematical Modelling

Final Report

June 2016

Prepared for Indo Energy International Ltd.

and their consultants C-Borne Services Represented by Capt. R.K. Karnal (IEIL)

Report authors Dr. Ruchi Kalra, Dr. Susant K Misra, Mr. V. Jinesh Kumar, Mr Arjun S

Quality assurance Dr. Flemming Jakobsen, Managing Director

Project number 63801014

Approval date 15th June 2016

Revision A

Classification Confidential

© DHI. All rights reserved. No parts of this document may be reproduced, transmitted or otherwise disseminated in any form or by any means outside the recipient’s organisation without the prior written permission of DHI.

i

CONTENTS

1 Introduction ............................................................................................. 1 1.1 DHI Project ............................................................................................................... 1 1.2 Background .............................................................................................................. 1 1.3 Scope of Work ......................................................................................................... 2 1.3.1 Secondary data collection and review ..................................................................... 2 1.3.2 Numerical modelling ................................................................................................ 3 1.4 Outline of the report ................................................................................................. 3

2 Site Conditions ........................................................................................ 4 2.1 General .................................................................................................................... 4 2.2 Shoreline Environment ............................................................................................. 5 2.3 Tides ........................................................................................................................ 7 2.4 Wind ......................................................................................................................... 8 2.5 Wave Climate - Offshore conditions ........................................................................ 8 2.6 Storms/Cyclones ...................................................................................................... 8

3 Analysis of Secondary Data ................................................................. 10 3.1 Data provided by the client .................................................................................... 10 3.2 Secondary Wind and Wave Data procured by DHI ............................................... 11 3.2.1 Wind Data Analysis ................................................................................................ 11 3.2.2 Offshore Wave Data Analysis ................................................................................ 24

4 Numerical Modelling Studies ................................................................ 48 4.1 Hydrodynamic Modelling ........................................................................................ 48 4.1.1 Bathymetry ............................................................................................................. 48 4.1.2 Boundary Conditions .............................................................................................. 56 4.1.3 Bed Resistance ...................................................................................................... 56 4.1.4 Production Period .................................................................................................. 56 4.1.5 Model Calibration and Validation ........................................................................... 56 4.1.6 Model Results ........................................................................................................ 59 4.2 Spectral Wave Modelling ....................................................................................... 76 4.2.1 Bathymetry ............................................................................................................. 76 4.2.2 Boundary Conditions .............................................................................................. 79 4.2.3 Wind Forcing .......................................................................................................... 81 4.2.4 Spectral Wave Model Calibration and Validation................................................... 81 4.2.5 Wave Model Results for proposed facility .............................................................. 85 4.3 Wave tranquillity at the proposed facility ............................................................... 90 4.4 Downtime Study ..................................................................................................... 90 4.5 Cyclone Modelling .................................................................................................. 90 4.5.1 Tropical Cyclone Tracks ........................................................................................ 90 4.6 Sediment Transport modelling ............................................................................... 95 4.7 Shoreline changes ................................................................................................. 98 4.8 Dredge Disposal modelling .................................................................................... 99

5 Conclusion ........................................................................................... 101

ii

LIST OF FIGURES Figure 1.1 Location of present unloading facility at Sanegaon on the West Coast of India ..... 1 Figure 2.1 Location of Proposed facility off the mouth of Kundalika River ............................... 4 Figure 2.2 Existing JSW Revdanda port facility at Maharashtra coast ..................................... 5 Figure 2.3 Local Bathymetry off Revdanda ............................................................................... 6 Figure 2.4 Local Bathymetry showing very near to the study area ........................................... 6 Figure 2.5 Local Bathymetry showing very near to the prosed facility and existing JSW jetty. 7 Figure 2.6 Tracks of the cyclones passed through the study area during 1915 to 2014 .......... 8 Figure 3.1 Location of the different data bases ....................................................................... 10 Figure 3.2 Extraction Location of UKMO data ........................................................................ 11 Figure 3.3 Rose (speed and direction) of wind data for 1 January 2006 to 31 December

2015 ....................................................................................................................... 12 Figure 3.4 Scatter Plot of wind data for 1 January 2006 to 31 December 2015 ..................... 12 Figure 3.5 Annual wind roses wind data from 1 January 2006 to 31 December 2015

(Direction coming from) .......................................................................................... 13 Figure 3.6 Monthly Rose (January- August) of wind data from 2006 - 2015 (Direction coming

from) ....................................................................................................................... 14 Figure 3.7 Monthly Rose (November - December) of wind data from 2006 – 2015 (Direction

coming from) .......................................................................................................... 15 Figure 3.8 Percentage of exceedance probability of wind speed based on UKMO (2006 -

2015) ...................................................................................................................... 23 Figure 3.9 Rose plot (Significant wave height and direction) for the period 1 January 2006 to

31 December 2015 ................................................................................................ 25 Figure 3.10 Scatter Plot (Significant wave height and direction) for the period 1 January 2006

to 31 December 2015 ............................................................................................ 25 Figure 3.11 Rose plot (Peak wave period and direction) for the period 1 January 2006 to 31

December 2015 ..................................................................................................... 26 Figure 3.12 Scatter Plot (peak wave period and direction) for the period 1 January 2006 to 31

December 2015 ..................................................................................................... 26 Figure 3.13 Rose plot (Zero crossing wave period and wave direction) for the period 1 January

2006 to 31 December 2015 ................................................................................... 27 Figure 3.14 Scatter Plot (Zero crossing wave period and direction) for the period 1 January

2006 to 31 December 2015 ................................................................................... 27 Figure 3.15 Annual Wave Roses of significant wave height (m) from 1 January 2006 to 31

December 2015 ..................................................................................................... 28 Figure 3.16 Monthly Rose (January- October) of significant wave height from 2006 to 2015 .. 29 Figure 3.17 Monthly Rose (November - December) of significant wave height from 2006 to

2015 ....................................................................................................................... 30 Figure 3.18 Monthly Rose (January-October) of peak wave period from 2006 to 2015 ........... 30 Figure 3.19 Monthly Rose (November-December) of peak wave period from 2006 to 2015 ... 31 Figure 3.20 Percentage of exceedance probability for significant wave height for the period of

1 January 2006 to 31 December 2015 .................................................................. 47 Figure 3.21 Percentage of exceedance probability for peak wave period for the period of 1

January 2006 to 31 December 2015 ..................................................................... 47 Figure 4.1 Water depth points with tidal stations (source: C-map) ......................................... 49 Figure 4.2 Snapshot of water elevation at Arnalapada, Vasai, Bandra & Apollo Bandra

(source: C-map) ..................................................................................................... 50 Figure 4.3 Snapshot of water elevation at Trombay, Mora Bandar, Revas Bandar &

Revadanda (source: C-map) .................................................................................. 51 Figure 4.4 Snapshot of water elevation at Murud-janjira harbour, Bankot, Port Dabhol &

Jaigarh (source: C-map) ........................................................................................ 52 Figure 4.5 Snapshot of water elevation at Ratnagiri (source: C-map) .................................... 53 Figure 4.6 Bathymetry of a full model domain (HD Model). .................................................... 53 Figure 4.7 Zoom in figure of bathymetry snapshot including mesh ........................................ 54 Figure 4.8 Zoom in figure of bathymetry snapshot including mesh very near to approach

channel ................................................................................................................... 54

iii

Figure 4.9 Zoom in figure of bathymetry snapshot showing the location of the proposed facility ..................................................................................................................... 54

Figure 4.10 Bathymetry snapshot including the proposed facility ............................................. 55 Figure 4.11 Zoom in figure of bathymetry snapshot including proposed facility ....................... 55 Figure 4.12 Comparison of measured and simulated water level at the third pillar of the

Revdanda Bridge ................................................................................................... 57 Figure 4.13 Comparison of measured and simulated current speed at location CM1 .............. 57 Figure 4.14 Comparison of measured and simulated current direction at location CM1 .......... 58 Figure 4.15 Comparison of measured and simulated current speed at location CM2 .............. 58 Figure 4.16 Comparison of measured and simulated current direction at location CM2 .......... 58 Figure 4.17 Comparison of measured and simulated current speed at location CM3 .............. 59 Figure 4.18 Comparison of measured and simulated current direction at location CM3 .......... 59 Figure 4.19 Maximum current speed during NE monsoon with existing condition ................... 60 Figure 4.20 Zoom figure in Maximum current speed during NE monsoon with existing

condition ................................................................................................................. 60 Figure 4.21 Mean current speed during NE monsoon with existing condition .......................... 61 Figure 4.22 Zoom figure in mean current speed during NE monsoon with existing condition .. 61 Figure 4.23 Snapshot of current pattern during peak flood tide and NE monsoon with existing

condition ................................................................................................................. 61 Figure 4.24 Very close snapshot of current pattern during peak flood tide and NE monsoon

with existing condition ............................................................................................ 62 Figure 4.25 Snapshot of current pattern during the ebb flood tide and NE monsoon with

existing condition ................................................................................................... 62 Figure 4.26 Very close snapshot of current pattern during the ebb flood tide and NE monsoon

with existing condition ............................................................................................ 62 Figure 4.27 Location of extraction Points t1, t2, t3, t4 at existing condition .............................. 63 Figure 4.28 Time series corresponding to surface elevation at extraction locations for existing

conditions ............................................................................................................... 63 Figure 4.29 Time series corresponding to current speed at extraction locations for existing

conditions at t1. ...................................................................................................... 63 Figure 4.30 Time series corresponding to current speed at extraction locations for existing

conditions at t2. ...................................................................................................... 64 Figure 4.31 Time series corresponding to current speed at extraction locations for existing

conditions at t3. ...................................................................................................... 64 Figure 4.32 Time series corresponding to current speed at extraction locations for existing

conditions at t4. ...................................................................................................... 64 Figure 4.33 Time series corresponding to current direction at extraction locations for existing

conditions ............................................................................................................... 65 Figure 4.34 Rose corresponding to current speed at extraction locations for existing

condition ................................................................................................................. 65 Figure 4.35 Maximum current speed during NE monsoon with proposed facility ..................... 66 Figure 4.36 Zoom figure in Maximum current speed during NE monsoon with proposed

facility ..................................................................................................................... 66 Figure 4.37 Mean current speed during NE monsoon with proposed facility ........................... 67 Figure 4.38 Zoom figure in mean current speed during NE monsoon with proposed facility ... 67 Figure 4.39 Snapshot of current pattern during peak flood tide and NE monsoon with proposed

facility ..................................................................................................................... 68 Figure 4.40 Very close snapshot of current pattern during peak flood tide and NE monsoon

with proposed facility .............................................................................................. 68 Figure 4.41 Snapshot of current pattern during ebb tide and NE monsoon with proposed

facility ..................................................................................................................... 69 Figure 4.42 Very close snapshot of current pattern during ebb tide and NE monsoon with

proposed facility ..................................................................................................... 69 Figure 4.43 Location of extraction points t1, t2, t3, t4 ............................................................... 70 Figure 4.44 Rose corresponding to current speed at extraction locations with proposed facility

condition ................................................................................................................. 70 Figure 4.45 Extraction points for existing and proposed facility conditions .............................. 72 Figure 4.46 Extent of regional model domain ........................................................................... 77

iv

Figure 4.47 Extent of regional model domain with local boundary point .................................. 78 Figure 4.48 Extent of local model domain with existing condition ............................................ 78 Figure 4.49 Time series plots of Hs, Hmax, Tz and MWD at entrance of the approach

channel ................................................................................................................... 80 Figure 4.50 Time series comparison between measured and model simulated significant wave

height Hs [m] for locations CM2 ............................................................................. 81 Figure 4.51 Time series comparison between measured and model simulated significant wave

height Hs [m] for locations CM 3 ............................................................................ 82 Figure 4.52 Snapshot for nearshore wave transformation result (Maximum wave height) during

June 2015 (Existing Condition). ............................................................................. 83 Figure 4.53 Snapshot for nearshore wave transformation result (Significant wave height)

during June 2015 (Existing Condition). .................................................................. 83 Figure 4.54 Snapshot for nearshore wave transformation result (Zero crossing wave period)

during June 2015 (Existing Condition). .................................................................. 84 Figure 4.55 Snapshot for nearshore wave transformation result (mean wave direction) during

June 2015 (Existing Condition). ............................................................................. 84 Figure 4.56 Extent of regional model domain with proposed facility with mesh ....................... 85 Figure 4.57 Extent of local model domain with proposed facility without mesh ........................ 85 Figure 4.58 Snapshot for nearshore wave transformation result (Significant wave height)

during June 2007 (Proposed Condition). ............................................................... 86 Figure 4.59 Snapshot for nearshore wave transformation result (Significant wave height)

during June 2007 including extraction locations .................................................... 86 Figure 4.60 Snapshot for nearshore wave transformation result (maximum wave height) during

June 2007 for proposed condition ......................................................................... 87 Figure 4.61 Snapshot for nearshore wave transformation result (Zero crossing wave period)

during June 2007 for proposed condition .............................................................. 87 Figure 4.62 Snapshot for nearshore wave transformation result (mean wave direction) during

June 2007 for proposed condition ......................................................................... 87 Figure 4.63 The time series plot of significant wave height (Hs), Maximum wave height

(Hmax), Zero crossing wave Period (Tz), and mean wave direction (MWD) during 2006 at the four extraction locations. ..................................................................... 88

Figure 4.64 Synthetic cyclone track with satellite imagery ........................................................ 92 Figure 4.65 Model domain for Cyclonic condition with synthetic cyclone track ........................ 93 Figure 4.66 Snap short of storm surge near the proposed facility with extraction points ......... 94 Figure 4.67 Time series plot of storm surge near the proposed facility .................................... 94 Figure 4.68 Snap short of cyclonic waves near the proposed facility with extraction points .... 94 Figure 4.69 Time series plot of cyclonic wave heights near the proposed facility .................... 95 Figure 4.70 snapshot of bed level change for the existing condition ........................................ 96 Figure 4.71 Very close snapshot of bed level change for the existing condition ...................... 96 Figure 4.72 snapshot of bed level change for the proposed marine facility.............................. 97 Figure 4.73 Very close snapshot of bed level change for the proposed marine facility ............ 97 Figure 4.74 Bed level changes and sedimentation quantity for different section at proposed

marine facility ......................................................................................................... 98 Figure 4.77 Satellite imagery of the shoreline .......................................................................... 99 Figure 4.75 Dumping location of dredged materials ............................................................... 100 Figure 4.76 TO be updated after the model simulation is completed ..................................... 100

LIST OF TABLES Table 2.1 Tidal Levels at Revdanda ........................................................................................ 7 Table 2.2 Month wise distribution of storms that crossed within 150 km radius from the

proposed site during the period (1915–2014) .......................................................... 9 Table 3.1 UKMO wind statistics for the period of 1 January 2006 to 31 December 2015

(Direction coming from) .......................................................................................... 16 Table 3.2 UKMO wind statistics for the month of January 2006 to 2015 (Direction coming

from) ....................................................................................................................... 16

v

Table 3.3 UKMO wind statistics for the month of February 2006 to 2015 (Direction coming from) ....................................................................................................................... 17

Table 3.4 UKMO wind statistics for the month of March 2006 to 2015 (Direction coming from) ....................................................................................................................... 17

Table 3.5 UKMO wind statistics for the month of April 2006 to 2015 (Direction coming from) ....................................................................................................................... 18

Table 3.6 UKMO wind statistics for the month of May 2006 to 2015 (Direction coming from) ....................................................................................................................... 18

Table 3.7 UKMO wind statistics for the month of Jun 2006 to 2015 (Direction coming from) ....................................................................................................................... 19

Table 3.8 UKMO wind statistics for the month of July 2006 to 2015 (Direction coming from) ....................................................................................................................... 19

Table 3.9 UKMO wind statistics for the month of August 2006 to 2015 (Direction coming from) ....................................................................................................................... 20

Table 3.10 UKMO wind statistics for the month of September 2006 to 2015 (Direction coming from) ....................................................................................................................... 20

Table 3.11 UKMO wind statistics for the month of October 2006 to 2015 (Direction coming from) ....................................................................................................................... 21

Table 3.12 UKMO wind statistics for the month of November 2006 to 2015 (Direction coming from) ....................................................................................................................... 21

Table 3.13 UKMO wind statistics for the month of December 2006 to 2015 (Direction coming from) ....................................................................................................................... 22

Table 3.14 UKMO wave statistics (Significant wave height Vs Wave Direction) for the period of 1 January 2006 to 31 December 2015 .............................................................. 32

Table 3.15 UKMO wave statistics (Peak wave period; tp Vs significant wave height; Hs) for the period of 1 January 2006 to 31 December 2015 ............................................. 33

Table 3.16 UKMO wave statistics (Zero crossing wave period; tz Vs significant wave height; Hs) for the period of 1 January 2006 to 31 December 2015 ................................. 34

Table 3.17 Monthly UKMO wave statistics (Significant wave height Vs Wave Direction) for the month of January 2006 to 2015 ............................................................................. 35

Table 3.18 Monthly UKMO wave statistics (Significant wave height Vs Wave Direction) for the month of February 2006 to 2015............................................................................ 36

Table 3.19 Monthly UKMO wave statistics (Significant wave height Vs Wave Direction) for the month of March 2006 to 2015 ................................................................................ 37

Table 3.20 Monthly UKMO wave statistics (Significant wave height Vs Wave Direction) for the month of April 2006 to 2015 ................................................................................... 38

Table 3.21 Monthly UKMO wave statistics (Significant wave height Vs Wave Direction) for the month of May 2006 to 2015 ................................................................................... 39

Table 3.22 Monthly UKMO wave statistics (Significant wave height Vs Wave Direction) for the month of June 2006 to 2015 .................................................................................. 40

Table 3.23 Monthly UKMO wave statistics (Significant wave height Vs Wave Direction) for the month of July 2006 to 2015 .................................................................................... 41

Table 3.24 Monthly UKMO wave statistics (Significant wave height Vs Wave Direction) for the month of August 2006 to 2015 ............................................................................... 42

Table 3.25 Monthly UKMO wave statistics (Significant wave height Vs Wave Direction) for the month of September 2006 to 2015 ........................................................................ 43

Table 3.26 Monthly UKMO wave statistics (Significant wave height Vs Wave Direction) for the month of October 2006 to 2015 ............................................................................. 44

Table 3.27 Monthly UKMO wave statistics (Significant wave height Vs Wave Direction) for the month of November 2006 to 2015 ......................................................................... 45

Table 3.28 Monthly UKMO wave statistics (Significant wave height Vs Wave Direction) for the month of December 2006 to 2015 ......................................................................... 46

Table 4.1 Simulated water level and current pattern at different locations for existing conditions ............................................................................................................... 73

Table 4.2 Simulated water level and current pattern at different locations with proposed facility ..................................................................................................................... 74

Table 4.3 Standard deviation between existing and proposed facility ................................... 75

vi

Table 4.4 Comparison of wave characteristics at a deep water location with simulated & NIOT wave Atlas .................................................................................................... 82

Table 4.5 Percentage of occurrence for significant wave height Vs zero crossing wave period ..................................................................................................................... 89

Table 4.6 Percentage of occurrence for maximum wave height Vs zero crossing wave period ..................................................................................................................... 89

Table 4.7 Synthetic cyclones considered............................................................................... 91

1

1 Introduction

1.1 DHI Project

M/s C-Borne Services, Navi Mumbai has engaged DHI (India) Water and Environment Pvt Ltd. to carry out the mathematical modelling for development of the direct berthing deep-water Jetty inside Revadanda Creek at the confluence of the Kundalika River with sea and the Sanegaon facility. DHI (India) is submitting this final report according to the Scope of Work given below.

1.2 Background

C-Borne Services was appointed by Indo Energy International Ltd. (IEIL) as a consulting firm to conduct various studies for development of the direct berthing deep-water Jetty inside Revadanda Creek at the confluence of the Kundalika River with sea and the Sanegaon facility.

Indo-Energy Limited (IEIL), is presently engaged in transportation and trading of Coal using lighterage facility at Sanegaon, located on the Right Bank of the Kundalika River, about 50 km south of Mumbai as shown in Figure 1.1 below.

Figure 1.1 Location of present unloading facility at Sanegaon on the West Coast of India

IEIL intends to expand the facility to include the Coal required for the proposed Power Plant planned to be located close to the riverine facility at Sanegaon. The existing Jetty is about 21 km upstream on the right bank of the river Kundalika and is about 200 m long with a backup area of about 5 hectare for storage, handling and despatch of material.

The sizes of the barges moving in the River are largely controlled by the depth in the river and the navigation width offered by the bridge piers downstream of the River.

The clear span between the intermediate bridge piers is 36 m. In order to ensure safe navigation, the beam of the barges would have to be limited to about 15 to 16 m, especially

2

in the monsoon, when the higher current could affect the stability and navigational control of such vessels. The dimensions of the present day barges used by IEIL generally agree with the above assertion and are as follows:

1. Length over all (LoA): 60 m

2. Beam: 14 m

3. Loaded Draught: 3.8 m

4. Capacity: About 2500 DWT

The capacity of the present day operations is largely limited by the following three factors and has limited capacity of about 1 million tons of coal per year.

1. Handling of the coal at the anchorage which is non-operational for about 4 months during south west monsoon

2. Depth (Draught available in the river)

3. Capacity of the Barges

In order to improve the capacity of this transportation chain, following recommendations are proposed:

1. Ensure all year by shifting mother ship operations inside the creek

2. Undertake dredging wherever required to improve the available draught in the river

3. Modernise/ Mechanise handling system at the jetty

4. Rationalise dimensions of the barges to increase carrying capacity of the barges

1.3 Scope of Work

This main objective of this study is to conduct mathematical modelling study on waves, hydraulics and sediment transport, required to support a development expansion of the existing as well as the new facility inside the creek. Based on the objective following scope of work was defined for the present study. The scope of the study is as follows:

1.3.1 Secondary data collection and review 1. Collection and review of existing data delivered by the client , the head supplier or

the client and other relevant sources, preparation of data as input data for the numerical study and assessment of data quality for all modelling relevant input data.

2. Wind data: Secondary data of wind condition will be procured from UKMO or GROW (whichever is available) for a period minimum of 10 years.

3. Wave data: Secondary data for wave condition will be procured from UKMO or GROW (whichever is available) for a period minimum of 10 years.

3

1.3.2 Numerical modelling

1. Hydrodynamic model: Set-up of a 2-dimensional numerical hydrodynamic model and simulation of water levels and currents during one typical season conditions will be selected for the baseline conditions. The calibration will be based on existing site measurements of hydrodynamic processes. The HD-model will be the basis for all following models and simulations.

2. Cyclonic storm surge model: Setup and estimation of storm surge induced water levels and currents for near the proposed location.

3. Spectral wave model: Set-up of a 2-dimensional numerical spectral wave model and simulation of wave height, wave directions and periods for the baseline conditions. The calibration will be based on existing site measurements on waves.

4. Hydrodynamic and wave pre-study (For Phase 1): Pre-study of the hydrodynamics (HD) and waves (SW) including one concept plan for the development of jetty on an analysis for water levels, currents. The impacts of reclamation and dredging in the hydrodynamics will be examined

5. Sedimentation model: Based on the Set-up of the HD and the SW-Model from Point 3 and 4 a sedimentation model will be build-up. And the annual siltation in the deep channel and river channel will be simulated.

6. Dredge Disposal Study: The suitable dumping location for the dredge spoil will be identified.

7. Downtime study: The wave penetration inside the creek and the down time at the berth and the wave heights at the berth around the year will be determined.

8. Assessment of Shoreline Changes: Coastal Impact Assessment studies due to development of the facility will be done.

1.4 Outline of the report

The kick off meeting for the present project was held on the 17th March 2016. During the meeting the methodology and schedule for the execution of the project was presented.

The model relevant data was provided by the client through e-mail and the same was reviewed and prepared for numerical study.

Subsequent to the kick-off meeting, a review meeting was held on 6th May 2016. In the meeting preliminary Hydrodynamics and Wave results for baseline conditions were presented and phase wise layout development was discussed.

The present report on the study is divided in to the following sections;

Section – 2 : Site Conditions Section – 3 : Secondary Data Analysis and Reviews Section – 4 : Numerical Modelling Section – 5 : Conclusions

4

2 Site Conditions

2.1 General

The proposed Revdanda facility is located between geographical co‐ordinates of latitude 18° 32' 9.66"N, longitude 72°54' 54.88"E and latitude 18° 32' 11.82"N, longitude 72° 55' 11.71"E, on the left bank of the Kundalika River, North East of Rat Island (Figure 2.1).

The Revadanda creek formed by the confluence of the Kundalika River and the Arabian Sea is protected naturally from the predominant SW waves by the Korlai headland.

East of the proposed facility there is an existing JSW jetty which is a 235 m concrete block gravity wall Jetty with end radius at both ends of 7.5 m. JSW jetty has mooring dolphins which lie 21 m to the east, thereby increasing the total length of the jetty to 256 m. This Jetty is L shaped and both the faces of jetty are used for berthing of vessels. The north face accommodates two (2) unloading berths and one (1) loading berth. The Southern face of jetty is used for mooring of barges awaiting discharge, barges undergoing repairs and idle barges. The south face provides two berths. Existing JSW Revdanda Port facility is shown in Figure 2.2.

At the confluence of Kundalika River with sea, a shallow sandbar has been formed and depth over sandbar is only 0.5 to 1.5 m. In view of the limited depth, the port is used as lighterage port. Coal is transshipped in the selfpropelled RSV II/IV barges of capacity 2500 ‐ 2800 DWT from mother vessel at anchorage. A 100 m wide, 7 nautical miles long entrance channel leads from anchorage point to JSW jetty for safe navigation of barges.

A bridge exists on Kundalika River about 400 m east of existing JSW jetty.

Figure 2.1 Location of Proposed facility off the mouth of Kundalika River

5

Figure 2.2 Existing JSW Revdanda port facility at Maharashtra coast

2.2 Shoreline Environment

The bathymetry map extracted from DHI’s in-house tool C-map for Site location is shown in Figures 2.3 to 2.5. The bathymetry map indicates 10 m contour reaching within approx. 20 km from the mouth of the creek and shows offshore currents having a magnitude of approx. 0.5 knots.

It can be seen that the depths in the creek near the proposed port facility along the navigation channel vary from ‐3 m CD to ‐5 m CD.

The water depth in and around the existing JSW Revdanda jetty are of the order of ‐5 m CD. However, in the fairway the depths range from – 3 m CD to ‐5 m CD.

There are sandy shoals and pockets of shallower depths at the creek entrance and the depths reduce to about ‐0.5 m CD to ‐1 m CD.

6

Figure 2.3 Local Bathymetry off Revdanda

Figure 2.4 Local Bathymetry showing very near to the study area

7

Figure 2.5 Local Bathymetry showing very near to the prosed facility and existing JSW jetty.

2.3 Tides

The Naval Hydrographical Chart No 211 gives information on the tide and tidal levels and is reproduced in Table 2.1. The spring and neap tidal ranges are 2.6m and 1.6 m respectively.

Table 2.1 Tidal Levels at Revdanda

MHWS 3.6

MHWN 3.3

MSL 2.4

MLWN 1.7

MLWS 1.0

Generally in the narrow estuarine areas, spatial variation of tide is likely to be prominent and the area like Kundalika River is not an exception and there is significant variation in high water levels as one moves upstream compared to open area water levels. This results in increased tidal current upstream of river.

8

2.4 Wind

During the months of June, July and August, the wind direction is SW-WSW. For rest of the months, predominant wind direction is NNE-N-NNW in the area. The wind speed is less than 10 m/s for 95% of the time (Table 3.1). The wind roses and statistical analysis are given in Section 3.

2.5 Wave Climate - Offshore conditions

It may be seen that the predominant directions of waves in the deep sea are from SW. It can also be seen that waves are less than 2 m, 4 m, and 5 m in height for 76%, 97.0% and 99.8% of the time respectively. The wave roses and statistical analysis are given in Section 3.

2.6 Storms/Cyclones

The north Indian Ocean accounts for 7% of global tropical cyclones (ref /1/, Gray, W. M. 1968). More cyclones occur in the Bay of Bengal than in the Arabian Sea; the ratio of their respective frequencies is about 4:1 (ref /2/, Dube S.K. 1997).

The storm tracks and atmospheric conditions during storms are available with the India Meteorological Department. The best tracks recorded for the period 1916 to 2015 from (websites) India Meteorological Department (IMD, India) are given in Figure 2.6.

Figure 2.6 Tracks of the cyclones passed through the study area during 1915 to 2014

The number of cyclones that has occurred within the vicinity of 150 km to the proposed project locations between the years 1916 and 2015 are 6 and their month wise distribution is given in Table 2.2. The frequency of storms that crossed the proposed project region during the month of October and November is the highest (02) and the frequency during the months of May and June are significantly less (01 each), while no cyclone has crossed the coast in January to April, July to September and December.

9

Table 2.2 Month wise distribution of storms that crossed within 150 km radius from the proposed site during the period (1915–2014)

Months Cyclone crossed

January -

February -

March -

April -

May 01

June 01

July -

August -

September -

October 02

November 02

December -

Total 06

10

3 Analysis of Secondary Data

3.1 Data provided by the client

The following data relevant for the model calibration and validation has been provided by the Client and reviewed by DHI:

Tide data from 26 October 2015 to 16 November 2015.

Location of station: Revdanda Bridge-3rd Pillar

• Latitude: 18°32'19.48"N

• Longitude: 72°55'51.40"E Refer to Figure 3.1 for station location.

Currents data (Acoustic Doppler Current Profiler) from 26 October 2015 to 16 November 2015 Location of station: CM 1

• Latitude: 18°32'12.47"N

• Longitude: 72°54'52.62"E Location of station CM 2

• Latitude: 18°32'59.12"N

• Longitude: 72°53'55.88"E Location of station CM 3

• Latitude: 18°31'27.00"N

• Longitude: 72°48'32.00"E Refer to Figure 3.1 for all the three station locations.

Waves data at the same locations and for the same period where the currents data were

measured (see above current data details)

Figure 3.1 Location of the different data bases

11

3.2 Secondary Wind and Wave Data procured by DHI

DHI has procured offshore 3-hourly wind and wave data from the United Kingdom Meteorological Office (UKMO) which covers the period of 10 years from 1 January 2006 to 31 December 2015. UKMO data has been derived on the basis of a well-recognized regional wave hind cast model.

The UKMO data obtained for the extraction point 18°30'58"N and 72° 4'12.00"E (Figure 3.2) forms a very useful data set, particularly for transforming from deep water to shallow water location.

Figure 3.2 Extraction Location of UKMO data

3.2.1 Wind Data Analysis Offshore 3-hourly marine wind data from the UK Meteorological Office (UKMO) from January 2006 to June 2015 is procured.

It should be noted that since the UKMO data are offshore wind data, land and sea breeze effects are not represented in the data. Furthermore, due to the limited spatial and time resolution of the UKMO wave hind cast model, cyclones cannot be expected to be fully resolved in the data.

The UKMO wind rose and scatter plot generated from the UKMO wind fields for 1 January 2006 to 31 December 2015 is presented in Figures 3.3 and 3.4 respectively. The annual wind roses form January 2006 to 31 December 2015 is shown in Figure 3.5. Similarly, the monthly wind roses are shown in Figures 3.6-3.7 (for the data set of 1 January 2006 to 31 December 2015).

The corresponding statistical analysis of wind fields for 1 January 2006 to 31 December 2015 is presented in Table 3.1 and the monthly statistical analysis of wind fields for 1 January 2006 to 31 December 2015 are presented in Table 3.2 to 3.13. From the table it

12

is found that wind speeds are below 10 m/s for approx. 95% of the time. The corresponding percentage of exceedance probability of wind speed is given in Figure 3.8.

Figure 3.3 Rose (speed and direction) of wind data for 1 January 2006 to 31 December 2015

Figure 3.4 Scatter Plot of wind data for 1 January 2006 to 31 December 2015

13

Figure 3.5 Annual wind roses wind data from 1 January 2006 to 31 December 2015 (Direction coming from)

14

Figure 3.6 Monthly Rose (January- August) of wind data from 2006 - 2015 (Direction coming from)

15

Figure 3.7 Monthly Rose (November - December) of wind data from 2006 – 2015 (Direction coming from)

16

Table 3.1 UKMO wind statistics for the period of 1 January 2006 to 31 December 2015 (Direction coming from)

Wind Speed (m/s)

Percentage of Occurrence for Wind Direction (deg) %

From To 0 -22.5

22.5- 45

45-67.5

67.5-

90

90-

112.5

112.5-

135

135-

157.5

157.5-

180

180-

202.5

202.5-

225

225-

247.5

247.5-

270

270-

292.5

292.5-

315

315-

337.5

337.5-360.0

0 < 2 0.39 0.30 0.28 0.18 0.14 0.08 0.10 0.13 0.14 0.11 0.19 0.21 0.36 0.40 0.51 0.35 3.87

2 <4 3.05 1.90 0.99 0.36 0.25 0.16 0.11 0.14 0.16 0.31 0.86 1.61 2.61 2.61 2.70 2.82 20.64

4 <6 6.48 3.45 1.30 0.41 0.13 0.04 0.04 0.07 0.18 0.52 1.61 3.07 3.72 4.38 5.22 5.62 36.27

6 <8 4.48 2.17 0.60 0.26 0.05 0.06 0.09 0.06 0.13 0.43 2.19 4.16 1.81 1.51 2.61 2.94 23.54

8 <10 0.96 0.57 0.11 0.04 0.02 0.01 0.05 0.08 0.06 0.18 2.34 4.38 0.71 0.22 0.34 0.18 10.24

≥10 0.09 0.07 0.02 0.00 0.01 0.01 0.04 0.03 0.01 0.08 1.43 3.41 0.20 0.02 0.01 0.01 5.44

Total (%) 15.45 8.45 3.30 1.26 0.60 0.36 0.42 0.51 0.67 1.63 8.63 16.83 9.42 9.14 11.39 11.92 100.00

Table 3.2 UKMO wind statistics for the month of January 2006 to 2015 (Direction coming from)

Wind Speed (m/s)

Percentage of Occurrence for Wind Direction (deg) %

From To 0 -22.5

22.5- 45

45-67.5

67.5-

90

90-

112.5

112.5-

135

135-

157.5

157.5-

180

180-

202.5

202.5-

225

225-

247.5

247.5-

270

270-

292.5

292.5-

315

315-

337.5

337.5-360.0

0 < 2 0.48 0.40 0.28 0.24 0.16 0.00 0.08 0.04 0.04 0.00 0.12 0.04 0.20 0.16 0.44 0.40 3.10

2 <4 4.68 2.86 0.81 0.36 0.08 0.04 0.00 0.00 0.00 0.00 0.00 0.04 0.56 0.93 1.49 3.99 15.85

4 <6 16.73 7.66 2.10 0.48 0.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.08 0.97 2.54 8.43 39.07

6 <8 19.44 5.81 0.77 0.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.08 0.97 6.65 33.79

8 <10 4.84 1.94 0.20 0.04 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.16 0.32 7.50

≥10 0.24 0.36 0.04 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.04 0.69

Total (%) 46.41 19.03 4.19 1.21 0.32 0.04 0.08 0.04 0.04 0.00 0.12 0.08 0.85 2.14 5.60 19.84 100.00

17

Table 3.3 UKMO wind statistics for the month of February 2006 to 2015 (Direction coming from)

Wind Speed (m/s)

Percentage of Occurrence for Wind Direction (deg) %

From To 0 -22.5

22.5- 45

45-67.5

67.5-

90

90-

112.5

112.5-

135

135-

157.5

157.5-

180

180-

202.5

202.5-

225

225-

247.5

247.5-

270

270-

292.5

292.5-

315

315-

337.5

337.5-360.0

0 < 2 0.44 0.40 0.13 0.13 0.04 0.04 0.00 0.09 0.13 0.04 0.27 0.22 0.35 0.62 0.40 0.53 3.86

2 <4 3.10 1.60 0.89 0.13 0.18 0.04 0.00 0.04 0.00 0.13 0.04 0.49 1.29 2.48 6.03 5.32 21.76

4 <6 10.33 2.48 0.62 0.04 0.09 0.00 0.00 0.00 0.00 0.00 0.18 0.84 0.71 2.08 9.04 17.77 44.19

6 <8 7.89 1.68 0.22 0.04 0.00 0.00 0.00 0.09 0.00 0.00 0.00 0.22 0.04 0.35 2.79 10.33 23.67

8 <10 3.32 1.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.09 0.53 0.80 5.94

≥10 0.44 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.13 0.58

Total (%) 25.53 7.36 1.86 0.35 0.31 0.09 0.00 0.22 0.13 0.18 0.49 1.77 2.39 5.63 18.79 34.88 100.00

Table 3.4 UKMO wind statistics for the month of March 2006 to 2015 (Direction coming from) Wind Speed (m/s)

Percentage of Occurrence for Wind Direction (deg) %

From To 0 -22.5

22.5- 45

45-67.5

67.5-

90

90-

112.5

112.5-

135

135-

157.5

157.5-

180

180-

202.5

202.5-

225

225-

247.5

247.5-

270

270-

292.5

292.5-

315

315-

337.5

337.5-360.0

0 < 2 0.40 0.24 0.32 0.20 0.16 0.12 0.12 0.12 0.24 0.00 0.36 0.16 0.60 0.60 0.73 0.20 4.60

2 <4 2.38 0.85 0.16 0.00 0.04 0.16 0.12 0.08 0.20 0.12 0.40 0.97 1.85 3.10 5.16 5.00 20.60

4 <6 5.24 1.01 0.12 0.04 0.00 0.00 0.00 0.00 0.00 0.00 0.04 0.24 1.73 6.45 16.81 13.55 45.24

6 <8 3.71 0.65 0.08 0.00 0.00 0.00 0.00 0.00 0.00 0.04 0.08 0.00 0.12 1.90 10.16 9.15 25.89

8 <10 0.93 0.16 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.04 0.20 0.00 0.00 1.13 1.05 3.51

≥10 0.04 0.04 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.08 0.00 0.16

Total (%) 12.70 2.94 0.69 0.24 0.20 0.28 0.24 0.20 0.44 0.16 0.93 1.57 4.31 12.06 34.07 28.95 100.00

18

Table 3.5 UKMO wind statistics for the month of April 2006 to 2015 (Direction coming from)

Wind Speed (m/s)

Percentage of Occurrence for Wind Direction (deg) %

From To 0 -22.5

22.5- 45

45-67.5

67.5-

90

90-

112.5

112.5-

135

135-

157.5

157.5-

180

180-

202.5

202.5-

225

225-

247.5

247.5-

270

270-

292.5

292.5-

315

315-

337.5

337.5-360.0

0 < 2 0.71 0.13 0.04 0.04 0.08 0.00 0.04 0.04 0.08 0.17 0.25 0.58 1.08 1.00 1.08 0.38 5.71

2 <4 0.67 0.08 0.04 0.00 0.00 0.04 0.00 0.04 0.08 0.33 1.17 3.46 6.17 6.92 5.08 3.04 27.13

4 <6 1.46 0.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.04 0.54 1.67 5.79 13.17 14.46 7.33 44.54

6 <8 0.25 0.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.13 0.46 6.04 9.83 3.25 20.04

8 <10 0.04 0.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.63 1.79 0.00 2.54

≥10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.04 0.00 0.00 0.04

Total (%) 3.13 0.46 0.08 0.04 0.08 0.04 0.04 0.08 0.17 0.54 1.96 5.83 13.50 27.79 32.25 14.00 100.00

Table 3.6 UKMO wind statistics for the month of May 2006 to 2015 (Direction coming from)

Wind Speed (m/s)

Percentage of Occurrence for Wind Direction (deg) %

From To 0 -22.5

22.5- 45

45-67.5

67.5-

90

90-

112.5

112.5-

135

135-

157.5

157.5-

180

180-

202.5

202.5-

225

225-

247.5

247.5-

270

270-

292.5

292.5-

315

315-

337.5

337.5-360.0

0 < 2 0.16 0.12 0.04 0.04 0.00 0.00 0.12 0.04 0.08 0.08 0.08 0.24 0.52 0.24 0.36 0.12 2.26

2 <4 0.12 0.04 0.00 0.00 0.00 0.00 0.00 0.00 0.16 0.60 2.38 4.35 8.23 5.60 2.10 0.85 24.44

4 <6 0.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.20 0.69 5.36 10.89 16.77 15.00 5.32 0.97 55.28

6 <8 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.12 0.36 0.77 2.46 3.83 5.12 3.63 0.32 16.61

8 <10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.04 0.12 0.12 0.52 0.52 0.08 0.00 1.41

≥10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total (%) 0.36 0.16 0.04 0.04 0.00 0.00 0.12 0.04 0.56 1.77 8.71 18.06 29.88 26.49 11.49 2.26 100.00

19

Table 3.7 UKMO wind statistics for the month of Jun 2006 to 2015 (Direction coming from)

Wind Speed (m/s)

Percentage of Occurrence for Wind Direction (deg) %

From To 0 -22.5

22.5- 45

45-67.5

67.5-

90

90-

112.5

112.5-

135

135-

157.5

157.5-

180

180-

202.5

202.5-

225

225-

247.5

247.5-

270

270-

292.5

292.5-

315

315-

337.5

337.5-360.0

0 < 2 0.04 0.08 0.21 0.00 0.08 0.17 0.08 0.13 0.21 0.13 0.33 0.13 0.08 0.17 0.25 0.17 2.25

2 <4 0.21 0.17 0.13 0.00 0.21 0.17 0.21 0.63 0.88 1.33 2.75 3.38 2.42 1.25 0.58 0.38 14.67

4 <6 0.00 0.21 0.13 0.04 0.00 0.13 0.17 0.67 1.38 2.25 4.83 8.29 4.00 2.00 0.75 0.00 24.83

6 <8 0.04 0.04 0.04 0.00 0.08 0.25 0.50 0.38 0.88 2.29 7.83 9.08 2.17 0.04 0.00 0.04 23.67

8 <10 0.00 0.00 0.00 0.00 0.00 0.00 0.42 0.92 0.67 1.67 9.96 8.50 0.38 0.29 0.00 0.00 22.79

≥10 0.00 0.00 0.00 0.00 0.00 0.04 0.42 0.42 0.08 0.92 6.21 3.42 0.17 0.13 0.00 0.00 11.79

Total (%) 0.29 0.50 0.50 0.04 0.38 0.75 1.79 3.13 4.08 8.58 31.92 32.79 9.21 3.88 1.58 0.58 100.00

Table 3.8 UKMO wind statistics for the month of July 2006 to 2015 (Direction coming from)

Wind Speed (m/s)

Percentage of Occurrence for Wind Direction (deg) %

From To 0 -22.5

22.5- 45

45-67.5

67.5-

90

90-

112.5

112.5-

135

135-

157.5

157.5-

180

180-

202.5

202.5-

225

225-

247.5

247.5-

270

270-

292.5

292.5-

315

315-

337.5

337.5-360.0

0 < 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

2 <4 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.08 0.24 0.48 0.60 0.52 0.08 0.00 0.00 2.02

4 <6 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.73 2.62 3.51 1.25 0.36 0.08 0.00 8.55

6 <8 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.36 7.50 12.30 2.18 0.08 0.00 0.00 22.42

8 <10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.04 9.68 22.34 2.06 0.00 0.00 0.00 34.11

≥10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7.18 24.84 0.89 0.00 0.00 0.00 32.90

Total (%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.08 1.37 27.46 63.59 6.90 0.52 0.08 0.00 100.00

20

Table 3.9 UKMO wind statistics for the month of August 2006 to 2015 (Direction coming from)

Wind Speed (m/s)

Percentage of Occurrence for Wind Direction (deg) %

From To 0 -22.5

22.5- 45

45-67.5

67.5-

90

90-

112.5

112.5-

135

135-

157.5

157.5-

180

180-

202.5

202.5-

225

225-

247.5

247.5-

270

270-

292.5

292.5-

315

315-

337.5

337.5-360.0

0 < 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.04 0.08 0.08 0.04 0.00 0.24

2 <4 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.04 0.08 0.52 1.29 2.26 1.05 0.40 0.32 5.97

4 <6 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.08 0.69 2.42 5.93 7.26 2.74 0.97 0.16 20.24

6 <8 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.08 0.28 5.36 17.94 8.39 1.17 0.12 0.00 33.35

8 <10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5.93 16.45 2.90 0.04 0.00 0.00 25.32

≥10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.50 11.09 1.25 0.04 0.00 0.00 14.88

Total (%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.20 1.05 16.73 52.74 22.14 5.12 1.53 0.48 100.00

Table 3.10 UKMO wind statistics for the month of September 2006 to 2015 (Direction coming from)

Wind Speed (m/s)

Percentage of Occurrence for Wind Direction (deg) %

From To 0 -22.5

22.5- 45

45-67.5

67.5-

90

90-

112.5

112.5-

135

135-

157.5

157.5-

180

180-

202.5

202.5-

225

225-

247.5

247.5-

270

270-

292.5

292.5-

315

315-

337.5

337.5-360.0

0 < 2 0.04 0.21 0.08 0.04 0.29 0.17 0.21 0.42 0.42 0.46 0.50 0.58 0.75 0.67 0.67 0.25 5.75

2 <4 0.92 0.58 0.25 0.04 0.08 0.21 0.13 0.25 0.21 0.54 2.04 3.96 6.04 6.17 4.92 1.83 28.17

4 <6 1.25 0.17 0.04 0.04 0.00 0.00 0.00 0.00 0.33 1.79 3.21 4.17 5.42 6.25 5.79 1.75 30.21

6 <8 0.08 0.29 0.00 0.00 0.00 0.00 0.00 0.00 0.29 1.83 4.71 7.33 3.63 2.54 2.50 0.92 24.13

8 <10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.04 0.46 2.25 4.38 1.67 0.54 0.13 0.00 9.46

≥10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.04 0.08 1.17 0.92 0.08 0.00 0.00 0.00 2.29

Total (%) 2.29 1.25 0.38 0.13 0.38 0.38 0.33 0.67 1.33 5.17 13.88 21.33 17.58 16.17 14.00 4.75 100.00

21

Table 3.11 UKMO wind statistics for the month of October 2006 to 2015 (Direction coming from)

Wind Speed (m/s)

Percentage of Occurrence for Wind Direction (deg) %

From To 0 -22.5

22.5- 45

45-67.5

67.5-

90

90-

112.5

112.5-

135

135-

157.5

157.5-

180

180-

202.5

202.5-

225

225-

247.5

247.5-

270

270-

292.5

292.5-

315

315-

337.5

337.5-360.0

0 < 2 1.09 0.81 0.89 0.65 0.56 0.24 0.40 0.40 0.32 0.16 0.24 0.36 0.56 0.81 1.29 0.93 9.72

2 <4 9.03 5.32 2.86 1.01 0.93 0.69 0.36 0.36 0.12 0.24 0.32 0.73 1.90 3.15 3.71 5.28 36.01

4 <6 10.20 6.94 2.78 1.29 0.60 0.16 0.12 0.08 0.00 0.08 0.08 1.09 1.41 3.27 5.24 6.17 39.52

6 <8 2.50 2.98 1.53 0.52 0.24 0.24 0.36 0.00 0.00 0.00 0.00 0.12 0.73 0.73 1.21 1.01 12.18

8 <10 0.00 0.16 0.16 0.04 0.08 0.16 0.08 0.00 0.00 0.00 0.00 0.00 0.89 0.56 0.28 0.00 2.42

≥10 0.00 0.04 0.00 0.00 0.08 0.04 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.16

Total (%) 22.82 16.25 8.23 3.51 2.50 1.53 1.33 0.85 0.44 0.48 0.65 2.30 5.48 8.51 11.73 13.39 100.00

Table 3.12 UKMO wind statistics for the month of November 2006 to 2015 (Direction coming from) Wind Speed (m/s)

Percentage of Occurrence for Wind Direction (deg) %

From To 0 -22.5

22.5- 45

45-67.5

67.5-

90

90-

112.5

112.5-

135

135-

157.5

157.5-

180

180-

202.5

202.5-

225

225-

247.5

247.5-

270

270-

292.5

292.5-

315

315-

337.5

337.5-360.0

0 < 2 0.50 0.67 0.96 0.50 0.17 0.13 0.13 0.17 0.17 0.21 0.13 0.17 0.08 0.33 0.29 0.75 5.33

2 <4 8.58 6.29 4.63 1.79 0.92 0.33 0.42 0.21 0.17 0.13 0.25 0.08 0.08 0.42 1.38 2.96 28.63

4 <6 15.75 11.75 6.50 1.96 0.42 0.21 0.25 0.08 0.17 0.04 0.00 0.04 0.00 0.04 0.33 4.67 42.21

6 <8 7.38 7.29 2.33 1.63 0.21 0.21 0.17 0.25 0.17 0.00 0.00 0.00 0.00 0.00 0.08 1.38 21.08

8 <10 0.25 1.04 0.50 0.42 0.08 0.00 0.08 0.04 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.42

≥10 0.00 0.00 0.21 0.04 0.00 0.00 0.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.33

Total (%) 32.46 27.04 15.13 6.33 1.79 0.88 1.13 0.75 0.67 0.38 0.38 0.29 0.17 0.79 2.08 9.75 100.00

22

Table 3.13 UKMO wind statistics for the month of December 2006 to 2015 (Direction coming from)

Wind Speed (m/s)

Percentage of Occurrence for Wind Direction (deg) %

From To 0 -22.5

22.5- 45

45-67.5

67.5-

90

90-

112.5

112.5-

135

135-

157.5

157.5-

180

180-

202.5

202.5-

225

225-

247.5

247.5-

270

270-

292.5

292.5-

315

315-

337.5

337.5-360.0

0 < 2 0.85 0.52 0.40 0.28 0.12 0.12 0.00 0.12 0.00 0.04 0.04 0.04 0.04 0.12 0.60 0.48 3.79

2 <4 6.90 4.96 2.18 1.01 0.56 0.20 0.04 0.04 0.00 0.00 0.00 0.00 0.00 0.32 1.94 4.96 23.10

4 <6 16.77 10.97 3.35 1.05 0.40 0.04 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.20 1.69 7.46 41.94

6 <8 12.50 7.10 2.14 0.81 0.12 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.08 2.70 25.44

8 <10 2.22 2.26 0.40 0.04 0.04 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.04 5.00

≥10 0.36 0.32 0.04 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.73

Total (%) 39.60 26.13 8.51 3.19 1.25 0.36 0.04 0.16 0.00 0.04 0.04 0.04 0.04 0.65 4.31 15.65 100.00

23

Figure 3.8 Percentage of exceedance probability of wind speed based on UKMO (2006 -2015)

24

3.2.2 Offshore Wave Data Analysis Offshore 3-hourly United Kingdom Meteorological Office (UKMO) wave data was procured from 1 January 2006 to 31 December 2015 at the following location: Latitude: 18°30'58"N Longitude: 72° 4'12.00"E Refer to Figure 1.1 for station location. The wave rose and scatter plot (significant wave height vs wave direction) corresponding to 10 years period from 1 January 2006 to 31 December 2015 is given in Figures 3.9 and 3.10 respectively.

The rose plot and scatter plot corresponding to peak wave period vs wave direction from 1 January 2006 to 31 December 2015 is given in Figure 3.11 and Figure 3.12 respectively.

The rose plot and scatter plot corresponding to Zero crossing wave period vs wave direction from 1 January 2006 to 31 December 2015 is given in Figure 3.13 and Figure 3.14 respectively.

The corresponding annual and monthly wave roses (significant wave height vs wave direction) are given in Figure 3.15 - Figure 3.17 respectively.

The monthly roses corresponding to peak wave period is given in Figures 3.18 and 3.19 respectively.

The statistical analysis corresponding to significant wave height vs wave direction and significant wave height vs peak wave period from 1 January 2006 to 31 December 2015 is given in Table 3.14 to 3.16 respectively.

The corresponding monthly statistical wave analysis is given in Tables 3.17- 3.28.

The corresponding Exceedance probability plot for significant wave height and peak wave period is given in Figures 3.20 and 3.21 respectively.

25

Figure 3.9 Rose plot (Significant wave height and direction) for the period 1 January 2006 to 31 December 2015

Figure 3.10 Scatter Plot (Significant wave height and direction) for the period 1 January 2006 to 31 December 2015

26

Figure 3.11 Rose plot (Peak wave period and direction) for the period 1 January 2006 to 31 December 2015

Figure 3.12 Scatter Plot (peak wave period and direction) for the period 1 January 2006 to 31 December 2015

27

Figure 3.13 Rose plot (Zero crossing wave period and wave direction) for the period 1 January 2006 to 31 December 2015

Figure 3.14 Scatter Plot (Zero crossing wave period and direction) for the period 1 January 2006 to 31 December 2015

28

Figure 3.15 Annual Wave Roses of significant wave height (m) from 1 January 2006 to 31 December 2015

29

Figure 3.16 Monthly Rose (January- October) of significant wave height from 2006 to 2015

30

Figure 3.17 Monthly Rose (November - December) of significant wave height from 2006 to 2015

Figure 3.18 Monthly Rose (January-October) of peak wave period from 2006 to 2015

31

Figure 3.19 Monthly Rose (November-December) of peak wave period from 2006 to 2015

32

Table 3.14 UKMO wave statistics (Significant wave height Vs Wave Direction) for the period of 1 January 2006 to 31 December 2015

Significant wave

height (m/s)

Percentage of Occurrence for Wave Direction (deg) %

From To 0 -22.5

22.5- 45

45-67.5

67.5-90

90-112.5

112.5-135

135-157.5

157.5-180

180-202.5

202.5-225

225-247.5

247.5-270

270-292.5

292.5- 315

315-337.5

337.5-360.0

0 <0.5 0.14 0.12 0.10 0.06 0.04 0.06 0.09 0.12 0.85 1.68 0.91 0.89 0.70 0.39 0.26 0.35 6.76

0.5 <1.0 1.66 0.54 0.39 0.18 0.17 0.12 0.14 0.23 1.27 6.29 6.70 6.82 6.12 4.86 3.86 4.33 43.68

1.0 <1.5 0.97 0.05 0.01 0.01 0.01 0.01 0.02 0.04 0.16 1.93 6.52 3.97 1.92 1.50 0.92 1.62 19.67

1.5 <2.0 0.28 0.00 0.00 0.01 0.00 0.00 0.01 0.07 0.08 0.24 3.25 1.47 0.12 0.07 0.03 0.23 5.85

2.0 <2.5 0.01 0.00 0.00 0.00 0.00 0.01 0.00 0.00 0.04 0.06 3.43 2.20 0.00 0.00 0.00 0.00 5.77

2.5 <3.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.01 0.03 0.05 4.01 2.02 0.00 0.00 0.00 0.00 6.12

3.0 <3.5 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.02 0.01 2.30 2.27 0.00 0.00 0.00 0.00 4.60

3.5 <4.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.02 0.02 2.24 1.70 0.00 0.00 0.00 0.00 3.97

4.0 <4.5 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.02 1.16 1.31 0.00 0.00 0.00 0.00 2.49

4.5 <5.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.47 0.30 0.00 0.00 0.00 0.00 0.77

≥5.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.28 0.04 0.00 0.00 0.00 0.00 0.32

Total (%) 3.07 0.72 0.50 0.26 0.23 0.20 0.26 0.47 2.47 10.31 31.28 22.99 8.86 6.82 5.07 6.52 100.00

33

Table 3.15 UKMO wave statistics (Peak wave period; tp Vs significant wave height; Hs) for the period of 1 January 2006 to 31 December 2015

Significant wave

height (m/s)

Percentage of Occurrence for Peak wave period (sec) %

From To 0-2 2-4 4-6 6-8 8-10 10-12 12-14 14-16 16-18 18-20 ≥ 20

0 <0.5 0.00 0.05 0.02 0.02 0.11 1.80 3.44 1.01 0.27 0.03 0.01 6.76

0.5 <1.0 0.00 1.34 2.80 0.71 0.43 6.47 20.01 8.45 2.85 0.53 0.11 43.68

1.0 <1.5 0.00 0.02 3.21 1.62 1.58 1.02 5.96 4.15 1.73 0.35 0.02 19.67

1.5 <2.0 0.00 0.00 0.60 0.72 2.61 0.26 0.59 0.60 0.36 0.10 0.01 5.85

2.0 <2.5 0.00 0.00 0.02 0.43 3.91 1.06 0.09 0.12 0.12 0.02 0.00 5.77

2.5 <3.0 0.00 0.00 0.00 0.10 3.49 2.30 0.02 0.13 0.08 0.01 0.00 6.12

3.0 <3.5 0.00 0.00 0.00 0.01 2.01 2.54 0.04 0.00 0.00 0.00 0.00 4.60

3.5 <4.0 0.00 0.00 0.00 0.00 0.82 3.05 0.07 0.00 0.03 0.00 0.00 3.97

4.0 <4.5 0.00 0.00 0.00 0.00 0.12 2.29 0.09 0.00 0.00 0.00 0.00 2.49

4.5 <5.0 0.00 0.00 0.00 0.00 0.01 0.72 0.04 0.00 0.00 0.00 0.00 0.77

≥5.0 0.00 0.00 0.00 0.00 0.00 0.22 0.10 0.00 0.00 0.00 0.00 0.32

Total (%) 0.00 1.41 6.65 3.60 15.08 21.74 30.45 14.46 5.43 1.04 0.15 100.00

34

Table 3.16 UKMO wave statistics (Zero crossing wave period; tz Vs significant wave height; Hs) for the period of 1 January 2006 to 31 December

2015

Significant wave

height (m/s)

Percentage of Occurrence for Zero crossing wave period (sec) %

From To 0-2 2-4 4-6 6-8 8-10 10-12 12-14 14-16 16-18 18-20 ≥ 20

0 <0.5 0.00 3.15 2.35 0.75 0.40 0.09 0.02 0.00 0.00 0.00 0.00 6.76

0.5 <1.0 0.00 19.71 19.80 3.08 0.85 0.18 0.05 0.02 0.00 0.00 0.00 43.68

1.0 <1.5 0.00 2.08 13.05 3.85 0.48 0.11 0.10 0.00 0.00 0.00 0.00 19.67

1.5 <2.0 0.00 0.00 3.06 2.63 0.17 0.00 0.00 0.00 0.00 0.00 0.00 5.85

2.0 <2.5 0.00 0.00 2.05 3.58 0.14 0.00 0.00 0.00 0.00 0.00 0.00 5.77

2.5 <3.0 0.00 0.00 0.47 5.54 0.11 0.00 0.00 0.00 0.00 0.00 0.00 6.12

3.0 <3.5 0.00 0.00 0.00 4.55 0.05 0.00 0.00 0.00 0.00 0.00 0.00 4.60

3.5 <4.0 0.00 0.00 0.00 3.95 0.02 0.00 0.00 0.00 0.00 0.00 0.00 3.97

4.0 <4.5 0.00 0.00 0.00 2.43 0.06 0.00 0.00 0.00 0.00 0.00 0.00 2.49

4.5 <5.0 0.00 0.00 0.00 0.75 0.02 0.00 0.00 0.00 0.00 0.00 0.00 0.77

≥5.0 0.00 0.00 0.00 0.12 0.20 0.00 0.00 0.00 0.00 0.00 0.00 0.32

Total (%) 0.00 24.93 40.77 31.23 2.50 0.38 0.17 0.02 0.00 0.00 0.00 100.00

35

Table 3.17 Monthly UKMO wave statistics (Significant wave height Vs Wave Direction) for the month of January 2006 to 2015

Significant wave

height (m/s)

Percentage of Occurrence for Wave Direction (deg) %

From To 0 -22.5

22.5- 45

45-67.5

67.5-90

90-112.5

112.5-135

135-157.5

157.5-180

180-202.5

202.5-225

225-247.5

247.5-270

270-292.5

292.5- 315

315-337.5

337.5-360.0

0 <0.5 0.44 0.40 0.32 0.04 0.08 0.08 0.04 0.12 1.17 2.94 3.51 2.22 1.41 1.17 1.17 1.85 16.98

0.5 <1.0 4.64 0.77 0.28 0.00 0.00 0.00 0.00 0.00 0.04 0.97 2.58 4.03 5.12 7.86 15.24 21.77 63.31

1.0 <1.5 4.68 0.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.04 0.40 0.08 1.09 2.74 7.50 16.81

1.5 <2.0 1.61 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.17 2.78

2.0 <2.5 0.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.04 0.12

2.5 <3.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

3.0 <3.5 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

3.5 <4.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

4.0 <4.5 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

4.5 <5.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

≥5.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total (%) 11.45 1.45 0.60 0.04 0.08 0.08 0.04 0.12 1.21 3.91 6.13 6.65 6.61 10.12 19.15 32.34 100.00

36

Table 3.18 Monthly UKMO wave statistics (Significant wave height Vs Wave Direction) for the month of February 2006 to 2015

Significant wave

height (m/s)

Percentage of Occurrence for Wave Direction (deg) %

From To 0 -22.5

22.5- 45

45-67.5

67.5-90

90-112.5

112.5-135

135-157.5

157.5-180

180-202.5

202.5-225

225-247.5

247.5-270

270-292.5

292.5- 315

315-337.5

337.5-360.0

0 <0.5 0.27 0.13 0.00 0.04 0.00 0.00 0.22 0.18 0.49 2.70 3.59 4.74 4.48 1.55 0.53 0.40 19.33

0.5 <1.0 1.42 0.09 0.00 0.00 0.00 0.00 0.04 0.04 0.00 2.08 4.12 7.62 12.46 19.50 12.72 5.76 65.87

1.0 <1.5 0.89 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.09 0.22 3.01 3.46 5.45 13.12

1.5 <2.0 0.18 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.18 0.31 1.02 1.68

2.0 <2.5 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

2.5 <3.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

3.0 <3.5 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

3.5 <4.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

4.0 <4.5 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

4.5 <5.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

≥5.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total (%) 2.75 0.22 0.00 0.04 0.00 0.00 0.27 0.22 0.49 4.79 7.71 12.46 17.15 24.25 17.02 12.63 100.00

37

Table 3.19 Monthly UKMO wave statistics (Significant wave height Vs Wave Direction) for the month of March 2006 to 2015

Significant wave

height (m/s)

Percentage of Occurrence for Wave Direction (deg) %

From To 0 -22.5

22.5- 45

45-67.5

67.5-90

90-112.5

112.5-135

135-157.5

157.5-180

180-202.5

202.5-225

225-247.5

247.5-270

270-292.5

292.5- 315

315-337.5

337.5-360.0

0 <0.5 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.73 0.93 1.45 0.89 0.24 0.00 0.00 5.24

0.5 <1.0 0.24 0.00 0.00 0.00 0.00 0.00 0.00 0.04 0.12 8.43 11.33 15.44 21.61 16.37 3.95 1.29 78.83

1.0 <1.5 0.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.16 0.52 0.44 3.19 6.65 2.62 1.65 15.52

1.5 <2.0 0.04 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.12 0.12 0.00 0.00 0.12 0.40

2.0 <2.5 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

2.5 <3.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

3.0 <3.5 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

3.5 <4.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

4.0 <4.5 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

4.5 <5.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

≥5.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total (%) 0.56 0.00 0.00 0.00 0.00 0.00 0.00 0.04 0.12 10.32 12.78 17.46 25.81 23.27 6.57 3.06 100.00

38

Table 3.20 Monthly UKMO wave statistics (Significant wave height Vs Wave Direction) for the month of April 2006 to 2015

Significant wave

height (m/s)

Percentage of Occurrence for Wave Direction (deg) %

From To 0 -22.5

22.5- 45

45-67.5

67.5-90

90-112.5

112.5-135

135-157.5

157.5-180

180-202.5

202.5-225

225-247.5

247.5-270

270-292.5

292.5- 315

315-337.5

337.5-360.0

0 <0.5 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.04 0.13 0.17 0.00 0.00 0.00 0.00 0.33

0.5 <1.0 0.04 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3.42 18.17 22.83 21.50 5.00 0.21 0.29 71.46

1.0 <1.5 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.04 6.17 5.71 7.67 5.08 0.42 0.17 27.25

1.5 <2.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.33 0.00 0.63 0.00 0.00 0.96

2.0 <2.5 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

2.5 <3.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

3.0 <3.5 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

3.5 <4.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

4.0 <4.5 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

4.5 <5.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

≥5.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total (%) 0.04 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5.50 24.46 29.04 29.17 10.71 0.63 0.46 100.00

39

Table 3.21 Monthly UKMO wave statistics (Significant wave height Vs Wave Direction) for the month of May 2006 to 2015

Significant wave

height (m/s)

Percentage of Occurrence for Wave Direction (deg) %

From To 0 -22.5

22.5- 45

45-67.5

67.5-90

90-112.5

112.5-135

135-157.5

157.5-180

180-202.5

202.5-225

225-247.5

247.5-270

270-292.5

292.5- 315

315-337.5

337.5-360.0

0 <0.5 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.5 <1.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.44 9.68 13.91 1.85 0.00 0.00 0.00 25.89

1.0 <1.5 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.98 25.56 26.53 8.95 0.48 0.00 0.00 64.52

1.5 <2.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.08 4.80 2.82 0.36 0.00 0.00 0.00 8.06

2.0 <2.5 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.93 0.00 0.00 0.00 0.00 0.93

2.5 <3.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.16 0.00 0.00 0.00 0.00 0.16

3.0 <3.5 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.36 0.08 0.00 0.00 0.00 0.00 0.44

3.5 <4.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

4.0 <4.5 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

4.5 <5.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

≥5.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total (%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3.51 40.40 44.44 11.17 0.48 0.00 0.00 100.00

40

Table 3.22 Monthly UKMO wave statistics (Significant wave height Vs Wave Direction) for the month of June 2006 to 2015

Significant wave

height (m/s)

Percentage of Occurrence for Wave Direction (deg) %

From To 0 -22.5

22.5- 45

45-67.5

67.5-90

90-112.5

112.5-135

135-157.5

157.5-180

180-202.5

202.5-225

225-247.5

247.5-270

270-292.5

292.5- 315

315-337.5

337.5-360.0

0 <0.5 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.5 <1.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.13 0.13 0.04 0.08 0.00 0.00 0.00 0.00 0.38

1.0 <1.5 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.25 1.67 7.38 4.46 0.00 0.00 0.00 0.00 13.75

1.5 <2.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.42 0.75 7.96 2.21 0.00 0.00 0.00 0.00 11.33

2.0 <2.5 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.04 0.54 0.63 12.08 1.83 0.00 0.00 0.00 0.00 15.13

2.5 <3.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.08 0.38 0.63 15.54 4.04 0.00 0.00 0.00 0.00 20.67

3.0 <3.5 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.21 0.13 8.25 4.29 0.00 0.00 0.00 0.00 12.88

3.5 <4.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.21 0.21 11.08 3.42 0.00 0.00 0.00 0.00 14.92

4.0 <4.5 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.21 5.54 1.54 0.00 0.00 0.00 0.00 7.29

4.5 <5.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.04 1.13 0.17 0.00 0.00 0.00 0.00 1.33

≥5.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.33 0.00 0.00 0.00 0.00 0.00 2.33

Total (%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.13 2.13 4.38 71.33 22.04 0.00 0.00 0.00 0.00 100.00

41

Table 3.23 Monthly UKMO wave statistics (Significant wave height Vs Wave Direction) for the month of July 2006 to 2015

Significant wave

height (m/s)

Percentage of Occurrence for Wave Direction (deg) %

From To 0 -22.5

22.5- 45

45-67.5

67.5-90

90-112.5

112.5-135

135-157.5

157.5-180

180-202.5

202.5-225

225-247.5

247.5-270

270-292.5

292.5- 315

315-337.5

337.5-360.0

0 <0.5 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.5 <1.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

1.0 <1.5 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

1.5 <2.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.89 0.12 0.00 0.00 0.00 0.00 1.01

2.0 <2.5 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3.02 3.02 0.00 0.00 0.00 0.00 6.05

2.5 <3.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 13.02 6.73 0.00 0.00 0.00 0.00 19.76

3.0 <3.5 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 12.78 12.98 0.00 0.00 0.00 0.00 25.77

3.5 <4.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 11.98 10.04 0.00 0.00 0.00 0.00 22.02

4.0 <4.5 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6.33 10.77 0.00 0.00 0.00 0.00 17.10

4.5 <5.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4.27 2.58 0.00 0.00 0.00 0.00 6.85

≥5.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.05 0.40 0.00 0.00 0.00 0.00 1.45

Total (%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 53.35 46.65 0.00 0.00 0.00 0.00 100.00

42

Table 3.24 Monthly UKMO wave statistics (Significant wave height Vs Wave Direction) for the month of August 2006 to 2015

Significant wave

height (m/s)

Percentage of Occurrence for Wave Direction (deg) %

From To 0 -22.5

22.5- 45

45-67.5

67.5-90

90-112.5

112.5-135

135-157.5

157.5-180

180-202.5

202.5-225

225-247.5

247.5-270

270-292.5

292.5- 315

315-337.5

337.5-360.0

0 <0.5 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.5 <1.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

1.0 <1.5 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.98 1.01 0.00 0.00 0.00 0.00 3.99

1.5 <2.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.04 8.47 6.90 0.00 0.00 0.00 0.00 15.40

2.0 <2.5 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 15.77 14.56 0.00 0.00 0.00 0.00 30.32

2.5 <3.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 12.26 9.76 0.00 0.00 0.00 0.00 22.02

3.0 <3.5 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4.96 8.51 0.00 0.00 0.00 0.00 13.47

3.5 <4.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.66 6.41 0.00 0.00 0.00 0.00 9.07

4.0 <4.5 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.69 3.19 0.00 0.00 0.00 0.00 4.88

4.5 <5.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.77 0.00 0.00 0.00 0.00 0.77

≥5.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.08 0.00 0.00 0.00 0.00 0.08

Total (%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.04 48.79 51.17 0.00 0.00 0.00 0.00 100.00

43

Table 3.25 Monthly UKMO wave statistics (Significant wave height Vs Wave Direction) for the month of September 2006 to 2015

Significant wave

height (m/s)

Percentage of Occurrence for Wave Direction (deg) %

From To 0 -22.5

22.5- 45

45-67.5

67.5-90

90-112.5

112.5-135

135-157.5

157.5-180

180-202.5

202.5-225

225-247.5

247.5-270

270-292.5

292.5- 315

315-337.5

337.5-360.0

0 <0.5 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.5 <1.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3.42 5.50 3.58 0.75 0.50 0.08 0.00 13.83

1.0 <1.5 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3.00 24.96 5.50 1.29 0.46 0.04 0.00 35.25

1.5 <2.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.46 16.92 3.33 0.38 0.00 0.00 0.00 21.08

2.0 <2.5 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10.29 5.17 0.00 0.00 0.00 0.00 15.46

2.5 <3.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7.13 3.33 0.00 0.00 0.00 0.00 10.46

3.0 <3.5 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.08 1.08 0.00 0.00 0.00 0.00 2.17

3.5 <4.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 0.25 0.00 0.00 0.00 0.00 1.25

4.0 <4.5 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.33 0.00 0.00 0.00 0.00 0.00 0.33

4.5 <5.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.17 0.00 0.00 0.00 0.00 0.00 0.17

≥5.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total (%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6.88 67.38 22.25 2.42 0.96 0.13 0.00 100.00

44

Table 3.26 Monthly UKMO wave statistics (Significant wave height Vs Wave Direction) for the month of October 2006 to 2015

Significant wave

height (m/s)

Percentage of Occurrence for Wave Direction (deg) %

From To 0 -22.5

22.5- 45

45-67.5

67.5-90

90-112.5

112.5-135

135-157.5

157.5-180

180-202.5

202.5-225

225-247.5

247.5-270

270-292.5

292.5- 315

315-337.5

337.5-360.0

0 <0.5 0.04 0.00 0.00 0.00 0.00 0.08 0.40 0.52 2.50 2.98 0.65 0.52 0.12 0.00 0.00 0.00 7.82

0.5 <1.0 1.05 0.44 0.73 0.24 0.36 0.36 0.44 0.56 5.81 27.78 12.70 6.13 2.02 1.77 1.21 0.97 62.58

1.0 <1.5 0.12 0.00 0.00 0.00 0.04 0.08 0.16 0.04 0.97 10.24 9.48 2.26 0.52 0.40 0.16 0.08 24.56

1.5 <2.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.56 0.32 0.93 0.04 1.69 0.60 0.00 0.04 0.08 4.27

2.0 <2.5 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.12 0.00 0.65 0.00 0.00 0.00 0.00 0.77

2.5 <3.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

3.0 <3.5 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

3.5 <4.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

4.0 <4.5 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

4.5 <5.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

≥5.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total (%) 1.21 0.44 0.73 0.24 0.40 0.52 1.01 1.69 9.60 42.06 22.86 11.25 3.27 2.18 1.41 1.13 100.00

45

Table 3.27 Monthly UKMO wave statistics (Significant wave height Vs Wave Direction) for the month of November 2006 to 2015

Significant wave

height (m/s)

Percentage of Occurrence for Wave Direction (deg) %

From To 0 -22.5

22.5- 45

45-67.5

67.5-90

90-112.5

112.5-135

135-157.5

157.5-180

180-202.5

202.5-225

225-247.5

247.5-270

270-292.5

292.5- 315

315-337.5

337.5-360.0

0 <0.5 0.17 0.25 0.46 0.46 0.33 0.29 0.17 0.29 4.33 4.79 0.92 0.54 0.58 0.79 0.38 0.50 15.25

0.5 <1.0 5.04 2.71 2.08 0.88 1.25 0.67 0.88 1.67 7.83 21.17 7.75 4.17 3.83 2.50 5.25 6.21 73.88

1.0 <1.5 0.96 0.08 0.08 0.08 0.04 0.04 0.08 0.50 0.71 3.00 0.75 0.75 0.63 0.25 0.29 1.17 9.42

1.5 <2.0 0.00 0.00 0.00 0.08 0.00 0.00 0.08 0.25 0.25 0.63 0.00 0.00 0.00 0.00 0.00 0.00 1.29

2.0 <2.5 0.00 0.00 0.00 0.00 0.04 0.08 0.04 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.17

2.5 <3.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

3.0 <3.5 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

3.5 <4.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

4.0 <4.5 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

4.5 <5.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

≥5.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total (%) 6.17 3.04 2.63 1.50 1.67 1.08 1.25 2.71 13.13 29.58 9.42 5.46 5.04 3.54 5.92 7.88 100.00

46

Table 3.28 Monthly UKMO wave statistics (Significant wave height Vs Wave Direction) for the month of December 2006 to 2015

Significant wave

height (m/s)

Percentage of Occurrence for Wave Direction (deg) %

From To 0 -22.5

22.5- 45

45-67.5

67.5-90

90-112.5

112.5-135

135-157.5

157.5-180

180-202.5

202.5-225

225-247.5

247.5-270

270-292.5

292.5- 315

315-337.5

337.5-360.0

0 <0.5 0.81 0.65 0.44 0.20 0.12 0.24 0.20 0.28 1.69 5.00 1.41 1.29 1.17 1.01 1.01 1.41 16.94

0.5 <1.0 7.46 2.50 1.53 1.05 0.44 0.44 0.32 0.40 1.25 7.38 8.47 4.19 4.92 5.77 8.10 15.44 69.68

1.0 <1.5 4.56 0.28 0.08 0.00 0.00 0.00 0.00 0.00 0.04 0.00 0.24 0.12 0.36 0.73 1.49 3.55 11.45

1.5 <2.0 1.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.36 1.90

2.0 <2.5 0.04 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.04

2.5 <3.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

3.0 <3.5 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

3.5 <4.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

4.0 <4.5 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

4.5 <5.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

≥5.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total (%) 14.40 3.43 2.06 1.25 0.56 0.69 0.52 0.69 2.98 12.38 10.12 5.60 6.45 7.50 10.60 20.77 100.00

47

Figure 3.20 Percentage of exceedance probability for significant wave height for the

period of 1 January 2006 to 31 December 2015

Figure 3.21 Percentage of exceedance probability for peak wave period for the period of 1 January 2006 to 31 December 2015

48

4 Numerical Modelling Studies

Numerical simulations were carried out for determining the flow dynamics and the near shore waves. The discussion below gives a brief description of the modelling tools, the procedure adopted and the results of the simulations.

4.1 Hydrodynamic Modelling

Hydrodynamic modelling is carried out using DHI’s MIKE21 FM (Flexible Mesh) HD model. The model simulates 2D free-surface flows, solving the depth averaged Navier-Stokes equations and is applicable to the simulation of hydrodynamic processes in lakes, estuaries, bays, coastal areas and seas. The FM module of MIKE 21 is based on Flexible Mesh approach using triangular and quadrangular elements for addressing geometrical flexibility to complex coastlines, like archipelago, lagoons, estuaries etc.

The hydrodynamic model simulates water level variations and flows in response to a variety of forcing functions. The effects and facilities in the HD includes:

Bottom shear stress Wind shear stress Barometric pressure gradients Coriolis force Momentum dispersion Sources and Sinks Evaporation Flooding and Drying Wave radiation stress

MIKE 21 FM can be applied to a wide range of hydraulic and related phenomena including modelling of tidal hydraulics, wind and wave generated currents, storm surges. The main governing conditions which affect the performance of the hydrodynamic model are:

Bathymetry Boundary conditions (wind and water level on open boundaries) Bottom resistance Eddy viscosity

4.1.1 Bathymetry Existing bathymetry of the region is prepared on the basis of MIKE – CMAP supplemented with at site-specific data provided by the client near the proposed study area. C-Map is a global digitised chart, which includes the water depth contours and water surface elevation data (tidal stations) for the entire globe. The C-Map depth points can be seen in Figure 4.1, which were imported on to the MIKE 21 suite, for setting up the bathymetry. The water elevation from C-map data base at different locations given in Figure 4.1 are shown in Figures 4.2 to 4.5 respectively.

The bathymetry of the baseline (Existing) conditions used for the hydrodynamic simulations is given in Figure 4.6 and the corresponding fine resolution in the port area is given Figures 4.7 to 4.9.

49

The mesh ranges from fine resolution near-shore of 50m to 2,700m offshore and a very fine resolution (10 m) inside the creek. , along the channel, entrance of the creek and proposed facility.

Later, proposed facility layouts are introduced in the existing bathymetry, where navigational channel (180 m width) is considered to be deepened to -14.5 m and the turning circle of diameter 500 m to -15.5 m depth. The berth pocket in front of the jetty is maintained at the same depth of -15.5 m. The depths behind the main berth and at the barge berth were maintained at -12 m and -6 m respectively. The depth on the eastern part of the jetty for the Port crafts are in the range of (-3) to (-5) m. Model Bathymetry of the domain after including the proposed facility layout is given in Figure 4.10 and the corresponding zoon-in figure showing fine resolution near the port area is shown in Figure 4.11.

Figure 4.1 Water depth points with tidal stations (source: C-map)

50

Figure 4.2 Snapshot of water elevation at Arnalapada, Vasai, Bandra & Apollo Bandra (source: C-map)

51

Figure 4.3 Snapshot of water elevation at Trombay, Mora Bandar, Revas Bandar & Revadanda (source: C-map)

52

Figure 4.4 Snapshot of water elevation at Murud-janjira harbour, Bankot, Port Dabhol & Jaigarh (source: C-map)

53

Figure 4.5 Snapshot of water elevation at Ratnagiri (source: C-map)

Figure 4.6 Bathymetry of a full model domain (HD Model).

54

Figure 4.7 Zoom in figure of bathymetry snapshot including mesh

Figure 4.8 Zoom in figure of bathymetry snapshot including mesh very near to approach

channel

Figure 4.9 Zoom in figure of bathymetry snapshot showing the location of the proposed facility

55

Figure 4.10 Bathymetry snapshot including the proposed facility

Figure 4.11 Zoom in figure of bathymetry snapshot including proposed facility

56

4.1.2 Boundary Conditions The boundary conditions for the HD model were extracted from DHI’s Global tide prediction model. This model is a Global tide prediction model assimilated with 20 years of SSH from TOPEX/POSEIDON altimetry data. It represents the major diurnal (K1, O1, P1 and Q1) and semidiurnal tidal constituents (M2, S2, N2 and K2) with a spatial resolution of 0.25 × 0.25 degrees. For the present study, Model was trained providing three open sea boundaries which were extracted from this Tide model. However, the boundary condition of upstream discharge for Kundalika River is approximately 40 m3/s.

Wind is introduced over model as the atmospheric boundary condition through a speed dependent wind friction coefficient. The source of winds are derived from the UKMO dataset.

4.1.3 Bed Resistance The MIKE21 hydrodynamic model is governed by the Reynolds-Averaged Navier-Stokes (RANS) equations, which are depth-integrated over the water column to finally yield the St. Venant equations. In the governing equations, the friction parameter is expressed as:

3/12hMgk

Where M (m1/3/s) is the Manning Number (the Manning Number is also seen in the literature as n=1/M). The importance of Manning Number is well known in both traditional as well as numerical hydraulics.

A varying manning number is applied throughout the model domain to get a reasonable calibration to the tidal water level, both amplitude and phase.

4.1.4 Production Period The hydrodynamic modelling is carried out for a periods of 22 days period to cover the full spring and neap phase of tidal cycle for validating the model. The production period of the hydrodynamic model is given below.

Tide with North east monsoon winds: 26 October 2015 to 16 November 2015.

4.1.5 Model Calibration and Validation The results of calibration are provided in this section. This calibration is based on the field collected data provided by the client.

The current data (magnitude and direction) was available at three locations namely CM1, CM2 and CM3 (Figure 3.1). The location of tide measurements at third pillar of Revadanda Bridge is also shown in Figure 3.1.

Figure 4.12 gives the calibration plot with respect to water surface elevation. The simulated tidal levels are having a good agreement with the measured data. The comparison of the

57

simulated and measured water level is in the acceptable range with RMS deviation of 0.17, which accounts about 2% of the tidal range.

Calibration and validation with respect to current speed and direction has been carried out at three locations CM1, CM2 and CM3.

The predicted and measured current speed and direction at locations CM1, CM2 and CM3 has been represented in Figure 4.13 -14, Figures 4.15-16 and Figure 4.17-18 respectively. From the figure it could be seen that the results are in agreement with the field measured data with the error of around 10-15% which can be attributed to the changes in the bathymetry.

HD model gives depth averaged current. The surface and bottom currents may have minor variation. Hence it is suggested to use following simplified formulation for estimating current at desired layers,

Current at a Layer = 1.142 X Depth Averaged Current x ( Layer Depth

Total Water Depth)

0.142

NB: Layer depth is numbered inversely like at 15m water depth, the surface layer is 15 and bottom layer is 1.

Figure 4.12 Comparison of measured and simulated water level at the third pillar of the Revdanda Bridge

Figure 4.13 Comparison of measured and simulated current speed at location CM1

58

Figure 4.14 Comparison of measured and simulated current direction at location CM1

Figure 4.15 Comparison of measured and simulated current speed at location CM2

Figure 4.16 Comparison of measured and simulated current direction at location CM2

59

Figure 4.17 Comparison of measured and simulated current speed at location CM3

Figure 4.18 Comparison of measured and simulated current direction at location CM3

4.1.6 Model Results

4.1.6.1 Existing conditions On calibrating and validating the model satisfactorily, the results were analysed in the region with particular focus on the proposed facility.

The simulated depth averaged currents are analysed statistically to give mean currents speed and maximum current speeds as shown in Figures 4.19 to 4.22.

Figure 4.23, gives the snapshot of the flow vectors for flood conditions and the closer view is shown in figure 4.24. The snapshot of flow vectors during ebb and its closer view is shown in Figures 4.25 and 4.26.

Model simulated surface elevation and current speed and current direction were extracted at four locations as given in Figure 4.27.

60

The time series at the extraction locations for surface elevation, current speed and current direction are given in Figure 4.28, 4.29-4.32, 4.33 respectively. Figure 4.34 gives the rose plots corresponding to current speed and current direction at the extraction locations.

Figure 4.19 Maximum current speed during NE monsoon with existing condition

Figure 4.20 Zoom figure in Maximum current speed during NE monsoon with existing condition

61

Figure 4.21 Mean current speed during NE monsoon with existing condition

Figure 4.22 Zoom figure in mean current speed during NE monsoon with existing condition

Figure 4.23 Snapshot of current pattern during peak flood tide and NE monsoon with existing condition

62

Figure 4.24 Very close snapshot of current pattern during peak flood tide and NE monsoon with existing condition

Figure 4.25 Snapshot of current pattern during the ebb flood tide and NE monsoon with existing condition

Figure 4.26 Very close snapshot of current pattern during the ebb flood tide and NE monsoon with existing condition

63

Figure 4.27 Location of extraction Points t1, t2, t3, t4 at existing condition

Figure 4.28 Time series corresponding to surface elevation at extraction locations for existing conditions

Figure 4.29 Time series corresponding to current speed at extraction locations for existing conditions at t1.

64

Figure 4.30 Time series corresponding to current speed at extraction locations for existing conditions at t2.

Figure 4.31 Time series corresponding to current speed at extraction locations for existing conditions at t3.

Figure 4.32 Time series corresponding to current speed at extraction locations for existing conditions at t4.

65

Figure 4.33 Time series corresponding to current direction at extraction locations for existing conditions

Figure 4.34 Rose corresponding to current speed at extraction locations for existing condition

4.1.6.2 Proposed Facility Condition The hydrodynamic model was then simulated for the proposed marine facility and the simulated depth averaged currents were analysed to give instantaneous maximum currents speed and mean current speeds and directions as shown in Figures 4.35 to 4.39 respectively.

66

The snapshot of current pattern during peak flood tide is shown in Figures 4.39 and its zoom-in figure in 4.40. Similarly, the snapshot of current pattern during the ebb tide is shown in Figures 4.41 and its zoom-in figure in 4.42.

Figure 4.44 gives the rose plots corresponding to current speed and current direction at the extraction locations marked in Figure 4.43.

Figure 4.35 Maximum current speed during NE monsoon with proposed facility

Figure 4.36 Zoom figure in Maximum current speed during NE monsoon with proposed facility

67

Figure 4.37 Mean current speed during NE monsoon with proposed facility

Figure 4.38 Zoom figure in mean current speed during NE monsoon with proposed facility

68

Figure 4.39 Snapshot of current pattern during peak flood tide and NE monsoon with proposed facility

Figure 4.40 Very close snapshot of current pattern during peak flood tide and NE monsoon with proposed facility

69

Figure 4.41 Snapshot of current pattern during ebb tide and NE monsoon with proposed facility

Figure 4.42 Very close snapshot of current pattern during ebb tide and NE monsoon with proposed facility

70

Figure 4.43 Location of extraction points t1, t2, t3, t4

Figure 4.44 Rose corresponding to current speed at extraction locations with proposed facility condition

71

4.1.6.3 Comparison between existing and proposed facility conditions

The statistical maximum and mean corresponding to model simulated water level and currents were compared for the existing and proposed facility conditions for the location as given in Figure 4.45.

Table 4.1 and Table 4.2 corresponds to the existing conditions and proposed facility conditions respectively. The standard deviation between the two conditions are given in Table 4.3.

It can be seen that the maximum current speed is decreased for the proposed facility conditions at the locations where the channel is dredged.

72

Figure 4.45 Extraction points for existing and proposed facility conditions

73

Table 4.1 Simulated water level and current pattern at different locations for existing conditions

Sl. No.

Geographical Coordinates (WGS 84) , UTM-43 Water level (m) Current speed (m/s) Latitude, N Longitude, E Easting (m) Northing (m) Maximum Average Maximum Average

1 18.50859 72.76418 263950 2047918 4.264 2.288 0.48 0.18 2 18.52255 72.80484 268263 2049411 4.288 2.286 0.49 0.19 3 18.54460 72.88702 276971 2051748 4.345 2.282 0.53 0.18 4 18.54809 72.90083 278433 2052117 4.359 2.281 0.90 0.21 5 18.53959 72.91343 279753 2051161 4.365 2.276 1.20 0.27 6 18.53763 72.91674 280100 2050940 4.373 2.278 1.30 0.26 7 18.53713 72.91914 280353 2050882 4.380 2.278 1.35 0.27 8 18.53704 72.91655 280079 2050875 4.373 2.278 1.38 0.28 9 18.53596 72.91634 280055 2050755 4.376 2.280 0.92 0.23

10 18.53578 72.91739 280166 2050734 4.377 2.279 1.05 0.26 11 18.53614 72.92039 280483 2050771 4.384 2.280 1.32 0.27 12 18.53551 72.92046 280490 2050701 4.385 2.281 0.94 0.24 13 18.53861 72.92564 281041 2051038 4.397 2.278 1.08 0.27 14 18.54003 72.92909 281407 2051190 4.405 2.271 1.37 0.37 15 18.54458 72.94656 283257 2051673 4.457 2.272 1.32 0.36 16 18.54217 72.95862 284528 2051392 4.484 2.272 1.51 0.36 17 18.53349 72.97091 285814 2050416 4.505 2.275 1.17 0.29 18 18.52019 72.97289 286007 2048942 4.516 2.279 0.87 0.19 19 18.45593 73.01109 289963 2041784 4.571 2.288 0.40 0.09 20 18.46228 73.02392 291326 2042471 4.605 2.288 0.33 0.08 21 18.47497 73.02719 291686 2043873 4.644 2.288 0.15 0.04 22 18.47842 73.03718 292746 2044243 4.657 2.288 0.14 0.04 23 18.48450 73.04277 293343 2044910 4.666 2.287 0.10 0.05 24 18.48449 73.04655 293743 2044904 4.667 2.287 0.12 0.03

74

Table 4.2 Simulated water level and current pattern at different locations with proposed facility

Sl. No.

Geographical Coordinates (WGS 84) , UTM-43 Water level (m) Current speed (m/s) Latitude, N Longitude, E Easting (m) Northing (m) Maximum Average Maximum Average

1 18.50859 72.76418 263950 2047918 4.265 2.288 0.48 0.19 2 18.52255 72.80484 268263 2049411 4.291 2.286 0.42 0.16 3 18.54460 72.88702 276971 2051748 4.349 2.283 0.36 0.11 4 18.54809 72.90083 278433 2052117 4.362 2.282 0.50 0.13 5 18.53959 72.91343 279753 2051161 4.375 2.281 0.49 0.13 6 18.53763 72.91674 280100 2050940 4.380 2.282 0.40 0.12 7 18.53713 72.91914 280353 2050882 4.382 2.282 0.42 0.12 8 18.53704 72.91655 280079 2050875 4.380 2.282 0.38 0.12 9 18.53596 72.91634 280055 2050755 4.380 2.282 0.43 0.12

10 18.53578 72.91739 280166 2050734 4.381 2.282 0.43 0.12 11 18.53614 72.92039 280483 2050771 4.385 2.283 0.50 0.15 12 18.53551 72.92046 280490 2050701 4.386 2.283 0.39 0.11 13 18.53861 72.92564 281041 2051038 4.393 2.280 0.66 0.19 14 18.54003 72.92909 281407 2051190 4.398 2.271 1.34 0.37 15 18.54458 72.94656 283257 2051673 4.434 2.275 1.11 0.30 16 18.54217 72.95862 284528 2051392 4.450 2.274 1.23 0.31 17 18.53349 72.97091 285814 2050416 4.468 2.276 1.14 0.29 18 18.52019 72.97289 286007 2048942 4.478 2.280 0.90 0.20 19 18.45593 73.01109 289963 2041784 4.497 2.288 0.36 0.10 20 18.46228 73.02392 291326 2042471 4.540 2.289 0.30 0.08 21 18.47497 73.02719 291686 2043873 4.569 2.289 0.15 0.04 22 18.47842 73.03718 292746 2044243 4.579 2.288 0.14 0.04 23 18.48450 73.04277 293343 2044910 4.585 2.288 0.10 0.04 24 18.48449 73.04655 293743 2044904 4.585 2.287 0.13 0.04

75

Table 4.3 Standard deviation between existing and proposed facility

Sl. No.

Geographical Coordinates (WGS 84) , UTM-43 Water level (m) Current speed (m/s) Latitude, N Longitude, E Easting (m) Northing (m) Maximum Average Maximum Average

1 18.50859 72.76418 263950 2047918 0.0007 0.0000 0.0000 0.0071 2 18.52255 72.80484 268263 2049411 0.0021 0.0000 0.0495 0.0212 3 18.54460 72.88702 276971 2051748 0.0028 0.0007 0.1202 0.0495 4 18.54809 72.90083 278433 2052117 0.0021 0.0007 0.2828 0.0566 5 18.53959 72.91343 279753 2051161 0.0071 0.0035 0.5020 0.0990 6 18.53763 72.91674 280100 2050940 0.0049 0.0028 0.6364 0.0990 7 18.53713 72.91914 280353 2050882 0.0014 0.0028 0.6576 0.1061 8 18.53704 72.91655 280079 2050875 0.0049 0.0028 0.7071 0.1131 9 18.53596 72.91634 280055 2050755 0.0028 0.0014 0.3465 0.0778

10 18.53578 72.91739 280166 2050734 0.0028 0.0021 0.4384 0.0990 11 18.53614 72.92039 280483 2050771 0.0007 0.0021 0.5798 0.0849 12 18.53551 72.92046 280490 2050701 0.0007 0.0014 0.3889 0.0919 13 18.53861 72.92564 281041 2051038 0.0028 0.0014 0.2970 0.0566 14 18.54003 72.92909 281407 2051190 0.0049 0.0000 0.0212 0.0000 15 18.54458 72.94656 283257 2051673 0.0163 0.0021 0.1485 0.0424 16 18.54217 72.95862 284528 2051392 0.0240 0.0014 0.1980 0.0354 17 18.53349 72.97091 285814 2050416 0.0262 0.0007 0.0212 0.0000 18 18.52019 72.97289 286007 2048942 0.0269 0.0007 0.0212 0.0071 19 18.45593 73.01109 289963 2041784 0.0523 0.0000 0.0283 0.0071 20 18.46228 73.02392 291326 2042471 0.0460 0.0007 0.0212 0.0000 21 18.47497 73.02719 291686 2043873 0.0530 0.0007 0.0000 0.0000 22 18.47842 73.03718 292746 2044243 0.0552 0.0000 0.0000 0.0000 23 18.48450 73.04277 293343 2044910 0.0573 0.0007 0.0000 0.0071 24 18.48449 73.04655 293743 2044904 0.0580 0.0000 0.0071 0.0071

76

4.2 Spectral Wave Modelling

2D wind-wave hindcast modelling has been carried out to transform the offshore wave field (UKMO data) to the proposed facility location.

The wave climate is mainly dominated by a combination of locally-generated wind waves and incoming swell waves from offshore. The modelling has been carried out using DHI’s MIKE 21 Spectral Wave (SW) model. It is a 3rd generation spectral wind-wave model based on the finite volume method on unstructured meshes and enables full time domain simulations, which prove to be important for the present development site. The model simulates the growth, decay and transformation of wind-generated waves and swells in offshore and coastal area. For more details on the model, refer to Sørensen (2004).

DHI’s MIKE 21 SW is well-established modelling system that has been used in numerous met-ocean studies worldwide. MIKE 21 SW includes the following physical phenomena:

Wave growth by action of wind

Non-linear wave-wave interaction

Dissipation due to white-capping

Dissipation due to bottom friction

Dissipation due to depth-induced wave breaking

Refraction and shoaling due to depth variations

Wave-current interaction

Effect of time-varying water depth

Diffraction (Holthuijsen’s parameterised spectral diffraction).

The discretisation of the governing equations in geographical and spectral space is performed using cell-centred finite volume method. In the geographical domain, an unstructured mesh technique is used. The time integration is performed using fractional step approach where a multi-sequence explicit method is applied for the propagation of wave action.

4.2.1 Bathymetry The model domain for wave model is chosen according to the position of UKMO locations (Given in Figure 3.7) over the area, so that it will be easier to apply the boundary conditions.

Since the spatial extent is quite large, so it is computationally impractical to use fine resolution model for the entire area. So, two models were used to resolve the physical processes at the project site, i.e., Regional model and local model.

Regional model with resolution varying from 5 km to1 km is shown in figures 4.46 & 4.47 respectively .The local model resolution varies from 1km to 20 m at the existing facility (Figure 4.48).

77

The water depths were extracted from digitised bathymetry chart, i.e. MIKE C-MAP data base updated with the more detailed local bathymetry provided by the client.

This bathymetry was used as the model domain in order to simulate the wave conditions, and evaluating effects near-shore.

Figure 4.46 Extent of regional model domain

78

Figure 4.47 Extent of regional model domain with local boundary point

Figure 4.48 Extent of local model domain with existing condition

79

4.2.2 Boundary Conditions At the open boundaries of the model domain the energy spectrum is determined as the superposition of the energy spectra determined from wave parameters for wind-sea and the wave parameters for swell. The following wave parameters have to be specified:

Significant wave height, wind-sea Peak wave period, wind-sea Mean wave direction, wind-sea Directional spreading index, wind-sea Significant wave height, swell Peak wave period, swell Mean wave direction, swell Directional spreading index, swell

The input wave parameters are obtained from the UKMO data for the regional model. The wave parameters were extracted from the model simulations of regional model at the model boundary of local model to derive at its boundary conditions. The time series plot of significant wave height (Hs), Maximum wave height (Hmax), Zero crossing wave Period (Tz), and mean wave direction (MWD) during 2006-2015 is given in Figure 4.49.

80

Figure 4.49 Time series plots of Hs, Hmax, Tz and MWD at entrance of the approach channel

81

4.2.3 Wind Forcing For the SW model, a wind field is applied as wind forcing. The wind field is generated using the offshore UKMO wind data.

4.2.4 Spectral Wave Model Calibration and Validation The model results have to be validated with the observational data for their reliability. On this aspect, field observation buoy data provided by the client was used.

Figures 4.50 to 4.51 show comparison between observed and model simulated resultant parameters and the result shows a good correlation between observed and model simulation.

The near shore wave data provided by the client covers a limited period of approx. one non monsoon month. The site specific wave data does not include the monsoon months and the period covered is insufficient for validation.

Hence for further validation purpose, the site specific wave data from NIOT wave atlas was used. The comparison between model simulated waves and NIOT wave Atlas at a deep water location is given in Table 4.4.

Figures 4.52 to 4.55 shows the snapshot for nearshore wave transformation result for existing conditions for the month of June, 2015.

Figure 4.50 Time series comparison between measured and model simulated significant wave height Hs [m] for locations CM2

82

Figure 4.51 Time series comparison between measured and model simulated significant wave height Hs [m] for locations CM 3

Table 4.4 Comparison of wave characteristics at a deep water location with simulated & NIOT wave Atlas

Months Simulated data NIOT Wave Atlas

Hs in metre

Tm in second

WӨ in degree

Hs in metre

Tm in second

WӨ in degree

January 0.5-1.0 3-5 290-360 0.5-1.0 3-5 270-315 February 0.5-1.0 3-5 270-360 0.5-1.0 3-5 270-315 March 0.5-1.0 3-5 225-315 0.5-1.0 3-5 255-315 April 0.5-1.0 3-5 225-300 0.5-1.0 3-5 240-300 May 0.5-1.5 3-6 225-280 0.5-1.5 3-6 225-285 June 1.0-2.5 5-8 225-260 1.0-2.5 5-8 240-270 July 1.5-3.0 5-8 225-260 1.5-3.0 5-8 255-270 August 1.0-2.5 4-7 225-270 1.0-2.5 4-7 255-270 September 0.5-2.0 4-7 225-270 0.5-2.0 4-7 240-270 October 0.5-1.0 4-6 200-270 0.5-1.0 4-6 210-270 November 0.5-1.0 3-6 205-290 0.5-1.0 3-6 295-285 December 0.5-1.0 3-5 210-360 0.5-1.0 3-5 255-315

83

Figure 4.52 Snapshot for nearshore wave transformation result (Maximum wave height) during June 2015 (Existing Condition).

Figure 4.53 Snapshot for nearshore wave transformation result (Significant wave height) during June 2015 (Existing Condition).

84

Figure 4.54 Snapshot for nearshore wave transformation result (Zero crossing wave period) during June 2015 (Existing Condition).

Figure 4.55 Snapshot for nearshore wave transformation result (mean wave direction) during June 2015 (Existing Condition).

85

4.2.5 Wave Model Results for proposed facility Based on the calibrated wave model described in the previous section, wave field was simulated with UKMO data base for the model domain including the proposed facility. The bathymetry is shown in Figures 4.56 and 4.57 respectively.

Figure 4.56 Extent of regional model domain with proposed facility with mesh

Figure 4.57 Extent of local model domain with proposed facility without mesh

86

Figures 4.58 and 4.59 shows the snapshot for nearshore wave transformation result (Significant wave height, Hs) near to the proposed facility for the month of June, 2007. The corresponding snapshot for maximum wave height, zero crossing wave period and mean wave direction are given in Figures 4.60, 4.61 and 4.62 respectively.

The time series plot of significant wave height (Hs), Maximum wave height (Hmax), Zero crossing wave Period (Tz), and mean wave direction (MWD) during 2006 at the four extraction locations are given in Figure 4.63.

The percentage occurrence of significant wave height vs Zero crossing wave period and maximum wave height vs Zero crossing wave period at the proposed facility location (t3) is given in Tables 4.5 and 4.6 respectively.

Figure 4.58 Snapshot for nearshore wave transformation result (Significant wave height) during June 2007 (Proposed Condition).

Figure 4.59 Snapshot for nearshore wave transformation result (Significant wave height) during June 2007 including extraction locations

87

Figure 4.60 Snapshot for nearshore wave transformation result (maximum wave height) during June 2007 for proposed condition

Figure 4.61 Snapshot for nearshore wave transformation result (Zero crossing wave period) during June 2007 for proposed condition

Figure 4.62 Snapshot for nearshore wave transformation result (mean wave direction) during June 2007 for proposed condition

88

Figure 4.63 The time series plot of significant wave height (Hs), Maximum wave height (Hmax), Zero crossing wave Period (Tz), and mean wave direction (MWD) during 2006 at the four extraction locations.

89

Table 4.5 Percentage of occurrence for significant wave height Vs zero crossing wave period

Peak wave period (s)

Percentage of Occurrence for significant wave height Vs Zero crossing wave period (%) during 2006 at t3 location

%

From To <0.05 0.05-0.10 0.10-0.15 0.15-0.20 0.20-0.25 0.25-0.30 0.30-0.35 0.35-0.40 0.40-0.45 0.45-0.50 ≥0.5

0 <0.8 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.8 <1.6 9.55 33.89 3.85 0.06 0.00 0.00 0.00 0.00 0.00 0.00 0.00 47.35

1.6 <2.4 38.16 13.66 0.02 0.00 0.00 0.00 0.00 0.00 0.01 0.00 0.00 51.86

2.4 <3.2 0.49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.49

3.2 <4.0 0.27 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.27 ≥4.0 0.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.02 Total (%) 48.50 47.56 3.87 0.06 0.00 0.00 0.00 0.00 0.01 0.00 0.00 100.0

Table 4.6 Percentage of occurrence for maximum wave height Vs zero crossing wave period

Peak wave period (s)

Percentage of Occurrence for maximum wave height Vs Zero crossing wave period (%) during 2006 at t3 location

%

From To <0.05 0.05-0.10 0.10-0.15 0.15-0.20 0.20-0.25 0.25-0.30 0.30-0.35 0.35-0.40 0.40-0.45 0.45-0.50 ≥0.5

0 <0.8 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.8 <1.6 1.03 7.37 14.92 17.84 5.65 0.43 0.10 0.00 0.00 0.00 0.00 47.35

1.6 <2.4 19.81 17.76 10.26 3.89 0.13 0.00 0.00 0.00 0.00 0.00 0.01 51.86

2.4 <3.2 0.00 0.49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.49

3.2 <4.0 0.00 0.27 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.27 ≥4.0 0.00 0.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.02 Total (%) 20.83 25.92 25.18 21.74 5.78 0.43 0.10 0.00 0.00 0.00 0.01 100.0

90

4.3 Wave tranquillity at the proposed facility

The wave transformation (Section 4.2) from the open ocean into the river in the presence of proposed marine facility with existing JSW jetty was simulated using MIKE 21 SW (Spectral Wave) module. The results reveal that the deep water wave heights attenuate to very less energy by the time they reach the prosed marine facility (location t3) indicating tranquil wave conditions during the monsoon and non-monsoon periods. Further, the waves get totally attenuated inside the Kundalika River towards the upstream. The proposed marine facility would form a good protected harbour area.

4.4 Downtime Study

The downtime of the operations at the proposed facility depends on the probability of exceedance of met-ocean conditions above the thresholds required for safe operations of vessels.

Considering the threshold values (Hs>0.5m, current speed > 1 m/s, wind > 20 knots) at the proposed facility (extraction location t3), the exceedance percentage is approx. zero.

However, long-term observations in proximity to the proposed facility is required for obtaining downtime with a higher level of confidence, especially concerning seasonal/monthly variations.

The present analysis pertains to normal operating conditions; it does not include extreme events like the possible land fall of cyclones. Considering the frequency of cyclonic storms crossing the coast during 1915-2015 (Section 2.6), there is an average of only 1 cyclone per 15 year. Hence, a downtime of approx. 0.5-day/year (one week per cyclone) is envisaged for extreme events. This sort of downtime should be predicted based on met-ocean forecast for the area, once the facility is in operation.

4.5 Cyclone Modelling

4.5.1 Tropical Cyclone Tracks As a tropical cyclone passes over sea surface, it simultaneously generates storm surge and cyclonic waves associated with low pressure and turning wind. Extreme waves and surges are generated by cyclonic turning wind fields as they propagate to the coast. The associated wave heights and water levels are exceptionally high and the characteristics change from storm to storm. These parameters are important to a large extent for planning and safe design of coastal structures. The information on the frequency and intensity of the storms passing over the study area is illustrated by the recorded best tracks obtained from (websites of) India Meteorological Department (IMD, India) and weather Unisys.

From these storm track data, cyclonic stages, maximum wind speed of the system, pressure drop, radius to maximum wind are retrieved and estimated.

The processes of selecting design water level and waves are site specific. Long-term measurements of water levels and waves are seldom available in Indian Coast. Hence storm surge and cyclonic waves are hindcasted from cyclonic track records for arriving at extreme conditions at the proposed facility location. The methodology adopted for

91

hindcasting surge levels and storm waves, and transformation to proposed site are presented in the following sections.

The key elements of the methodology are:

Cyclonic wind field generation for historical cyclones using DHI’s MIKE 21 Cyclone generation toolbox.

Setup DHI’s MIKE 21 HD model to estimate the storm surge in all the scenarios.

Based on the surge model output a statistical analysis is performed for historic cyclones irrespective of the actual track. From this analysis, estimated return periods are assigned to the most severe events.

The next step is to use the cyclone events in a numerical hindcast SW model to assess the storm waves associated with them.

It is emphasized that the methodology applied will produce indicative values of cyclone events at the site. We only know what has occurred in the past and try to predict what can happen in the future, and we are dealing with a highly random and unpredictable process. A full-blown rigorous approach involves much more complex modeling and analysis beyond the scope and time frame of the present project.

It was noted that the historical cyclones passing near the site (Figure 2.6) are either very weak or their path is far from the location. It is therefore, decided to modify the cyclonic track of very severe cyclonic event (irrespective of the actual track) to the proposed location to simulate their effect.

The details of the synthetic cyclonic event considered within the vicinity of the study area are given in Table 4.7. The corresponding tracks is given in Figure 4.64.

Table 4.7 Synthetic cyclones considered

Latitude Longitude Nature of the cyclone R-max (Km) V (m/s) Cp (hpa) Np (hpa)

16.49957 61.08170

VSCS

30 15 1005 1013

16.59197 61.55043 30 15 1005 1013

16.69341 62.06473 30 15 1005 1013

16.78006 62.48444 30 15 1005 1013

16.89107 63.04619 30 18 1003 1013

16.96845 63.46787 30 21 1001 1013

17.09923 64.16616 30 23 999 1013

17.21737 64.81389 30 26 997 1013

17.39116 65.76623 30 28 994 1013

17.58993 66.88064 30 31 992 1013

17.83633 68.15357 30 33 990 1013

18.05039 69.42627 30 36 987 1013

18.25641 70.70901 30 41 982 1013

92

Figure 4.64 Synthetic cyclone track with satellite imagery

Storm surge is atmospherically forced oscillations of the sea water level due to the presence of a storm. As a storm approaches the coastline, it acts like a sequence of events. In a storm surge, the three important phenomena are:

Forerunners Surge elevation Resurgence

Forerunner is the gradual rise in sea level that precedes the arrival of the cyclone, which may occur while the storm centre is at great distance from the point of observation. The surge elevation is the substantial rise in water level that accompanies violent winds of the storm and resurgence occur after the passage of a cyclone. Cyclone induced storm surge may contribute significantly to the design water level for coastal infrastructure.

For this present study the storm tracks and atmospheric conditions during historic storms in Arabian Sea were collected for past 100 years. In the past century, only six cyclone crossed in 150 Km radius. So it is clearly indicated that the study area was non cyclogenesis. But the worst scenario, synthetic cyclone is considered in the present simulation. The present simulation gives a detailed and critical picture of the surge level for the proposed study area. This attempt may be helpful for future analysis.

18.46713 72.06183 30 44 979 1013

18.65520 73.53481 30 41 982 1013

18.80991 74.87932 30 36 987 1013

18.93086 76.15037 30 26 997 1013

93

The model domain and snapshot of results obtained from MIKE 21 HD storm surge simulations of synthetic cyclone is presented in Figures 4.65, 4.66 & 4.67 respectively. The snapshot of results obtained from SW simulated wave heights for synthetic cyclone is presented in Figures, 4.68 & 4.69 respectively

Figure 4.65 Model domain for Cyclonic condition with synthetic cyclone track

94

Figure 4.66 Snap short of storm surge near the proposed facility with extraction points

Figure 4.67 Time series plot of storm surge near the proposed facility

Figure 4.68 Snap short of cyclonic waves near the proposed facility with extraction points

95

Figure 4.69 Time series plot of cyclonic wave heights near the proposed facility

Based on the simulation results, storm surge level (Figure 4.67) and extreme wave parameters (Figure 4.69) are obtained at proposed facility. It shall be noticed that the study approach produces estimates for a synthetic extreme event.

4.6 Sediment Transport modelling A preliminary model using MIKE 21FM ST was set up to simulate the sedimentation in the proposed area. The model domain was kept same as used in HD Modelling (Section 4.2).

Sediment characteristic is very important in determining the total sediment transport load. The geometrical characteristics of the bed material are represented through the median grain size (d50) when numerically calculating the concentration of suspended sediment and the sediment transport.

The sediment distribution is internally described in the MIKE21 ST module by a log-normal grain curve which is calculated on the basis of the median grain size d50. The sediment characteristic in the whole domain is chosen to be fine sand with d50 of 0.17mm. This assumption is based on the data provided by the client.

The sediment transport modelling was carried out for the same period of from 26th October 2015 to 16th November 2015 as HD model.

The calculation of the bed level change assumes the bulk density of pure quartz sand of 2,650 kg/m3. The numbers in terms of bed level change will vary by considering different bulk densities.

The bed level change at the entrance and in the channel can be observed in Figure 4.70 and 4.71 for existing conditions and Figure 4.72 and 4.73 for proposed facility condition.

The statistical results of the 22 days simulation for the proposed facility are presented in terms of incremental annual mean bed level change which is given by scaling of bed level changes observed during simulation periods (Figure 4.74).

96

Figure 4.70 snapshot of bed level change for the existing condition

Figure 4.71 Very close snapshot of bed level change for the existing condition

97

Figure 4.72 snapshot of bed level change for the proposed marine facility

Figure 4.73 Very close snapshot of bed level change for the proposed marine facility

98

Figure 4.74 Bed level changes and sedimentation quantity for different section at proposed marine facility

The average rate of siltation per annum along the various reaches of channel approaching the proposed facility is given above.

The average rate of siltation in the area proposed to be dredged corresponds to quantum of siltation of approx. 1.5 million Cum.

The siltation rates are not uniform over the area under consideration and vary based on the prevailing hydrodynamic conditions.

The rates of siltation estimated from model are based on the fact that the entire dredged area is maintained to the required depths and deposition is due to settlement of suspended sediment material.

It is also important to mention that since the entire area which will be dredged is a virgin land, it is likely that there is possibility of increase in siltation than estimates by model studies during initial few years till the side slopes of dredged/nearby area gets stabilized.

4.7 Shoreline changes The objective of the present assessment is to analyse the effect of the proposed development on the sedimentation regime within the port area, and determine coastal impacts, if any.

The longshore transport is governing the availability of sediments and thus the sedimentation in the access channel. Therefore, as long as there are no significant changes in the longshore transport due to external factors, no major changes in sedimentation in the area are expected.

The satellite imageries were analysed to ascertain the shoreline evolution for past 11 years. Three satellite imageries (Figure 4.75) corresponding to the spring tide period (2005, 2013

99

and 2015) are given below. An examination of the high water line for the past 11 years indicates that the shoreline is quite stable.

The Maharashtra coast experiences low annual net transport. The coast of Maharashtra is very stable and it does not have a problem of annual net erosion or excess deposition as reported in Chandramohan et. al. 1992 (ref/3/).

Hence it is concluded that there will be no significant shoreline impact with the proposed development.

Figure 4.75 Satellite imagery of the shoreline

4.8 Dredge Disposal modelling Identification of the dumping site in the offshore area was carried out so that after dumping the resulting concentration in the identified location is within permissible limits. The already calibrated hydrodynamic model was coupled with a dispersion module to give the likely spread (dispersion) of the dumped material.

DHI selected the modelled dumping grounds based on information and earlier studies provided by the client. Two locations 18°31'41"N, 72°41'32"E for the northern dumping site and 18°28'21"N, 72°42'53"E for the southern dumping site are selected which are approx. 24 km from the shore (Figure 4.76).

100

Figure 4.76 Dumping location of dredged materials

The dispersion of dredge spoil around the disposal area was simulated for the Northeast monsoon period from 26.10.206 to 26.11.2016. The spread of the disposed sediment on the sea floor after the one month of sediment disposal for the Northern location is shown in Fig. 4.77.

Figure 4.77 Model simulated deposition depth after dumping

The dispersion studies carried out at the proposed north and south dumping locations indicated that irrespective of the phase of the tide, dumped material does not enter the proposed extension of the outer channel. Also, material could be dumped inside the periphery of about 1.5 km radius from the suggested location. About 20 Million cum of the dredged material resulting from the capital dredging is assumed to be disposed off suitably at these two locations. For maintenance dredging, these dumping locations could also be utilised for disposing of dredged material during the maintenance of the channel, if the properties of the dumped material do not significantly changed from the material considered in the study.

101

5 Conclusion

The proposed Revdanda facility is located on the left bank of the Kundalika River.

The Revadanda creek formed by the confluence of the Kundalika River and the Arabian Sea is protected naturally from the predominant SW waves by the Korlai headland.

East of the proposed facility there is an existing JSW jetty and a bridge exists on Kundalika River about 400 m east of existing JSW jetty.

The hydrodynamic conditions were simulated using MIKE 21 HD FM model and the proposed facility is found to be well aligned with respect to the flow conditions with current speed of less than 0.5 m/s near the proposed facility. The maximum spring tidal range at the proposed facility is observed to be approx. 4.0 m.

Offshore wind and wave data was acquired from the United Kingdom Meteorological Office (UKMO) between 2006 and 2015 at a location 18°30'58"N and 72° 4'12.00"E, which is approximately 90 km off the coast.

MIKE 21 SW model was applied to transform the offshore wave climate to the nearshore conditions in the vicinity of the proposed facility. Results were presented as maps showing the spatial variation of the wave climate as well as wave roses and probability exceedance tables. The conclusion from the one year simulation is that the proposed facility is well protected with low wave disturbance indicating tranquil conditions.

To study the extreme weather conditions, hind casting was carried out for a synthetic cyclonic event considered within the vicinity of the study area. A storm surge of approx. 0.9 m and significant wave of 0.45 m was simulated at the proposed marine facility.

The results of the hydrodynamic simulations have been applied to simulate the sediment transport in order to estimate the sedimentation and bed level change for the proposed marine facility and presented in terms of incremental annual mean bed level change which is given by scaling of bed level changes observed during simulation periods. The quantity of siltation is simulated to be of the order of 1.5 million cu. m for the navigational channel.

No significant shoreline impact with the proposed development is envisaged.

The material obtained from dredging of the channel and the port area is to be dumped at a disposal ground located about 24 km from the shore line at 18°31'41"N, 72°41'32"E for the northern dumping site and 18°28'21"N, 72°42'53"E for the southern dumping site

102

References

/1/ Gray, W.M. (1968) Global view of the origin of tropical disturbances and storms. Mon. Wea. Rev., 96, 669-700

/2/ Dube, S.K., Rao, A.D., Sinha, P.C., Murty, T.S. and Bahulayan, N. (1997) Storm surge in the Bay of Bengal and Arabian Sea: The problem and its prediction. Mausam, Vol.48; 283-304p.

/3/ Chandramohan, P. and Nayak, B. U. (1992) Longshore Sediment Transport Model for the Indian West Coast, Journal of Coastal Research, Vol. 8; 775-787p

 

 

 

 

 

Annexure 3 

Appendix for Terrestrial Ecology

Annexure 3 :Appendix for Terrestrial Ecology Appendix 1: Sampling location

Sr. No.

Sampling locations

Quadrate number

Quadrate code

Distance radius

Habitat Impact notes

1

Core site q1 s1q1 0.5 km Very sparse and stunted Mangrove away from the site

moderate Sparse mangrove patches dominated by Avicennia species, away from the proposed development.

Cultivation of vegetatbles-e.g. brinjal done in the nearby areas.

2

Core site q2 s1q2 0.5 km Mangrove moderate Sparse mangrove patches dominated by Avicennia species, away from the proposed

development. 3 Core site q3 s1q3 0.5 km Mangrove moderate Sparse mangrove patches dominated by

Avicennia species, away from the proposed development.

4 Core site q4 s1q4 0.5 km Mangrove moderate Sparse mangrove patches dominated by Avicennia species, away from the proposed

development. 5 Barashiv

q1 s2q1 5 km Dense forest low Selective logging

6 Barashiv

q2 s2q2 5 km Dense forest low Selective logging

7 Barashiv

q3 s2q3 5 km Dense forest low Selective logging

8 Barashiv

q4 s2q4 5 km Dense forest low Selective logging

9 Mahalunge q1 s3q1 5 km Forest moderate Some forest patches converted to plantations of mango, cashew & jackfruit

Sr. No.

Sampling locations

Quadrate number

Quadrate code

Distance radius

Habitat Impact notes

10 Mahalunge q2 s3q2 5 km Forest moderate Some forest patches converted to plantations of mango, cashew & jackfruit

11 Mahalunge q3 s3q3 5 km Forest moderate Some forest patches converted to plantations of mango, cashew & jackfruit

12 Mahalunge q4 s3q4 5 km Forest moderate Some forest patches converted to plantations of mango, cashew & jackfruit

13 Amali

q1 s4q1 5 km Dense forest moderate Selective logging

14 Amali

q2 s4q2 5 km Dense forest moderate Selective logging

15 Amali

q3 s4q3 5 km Dense forest moderate Selective logging

16 Amali

q4 s4q4 5 km Dense forest moderate Selective logging

17 Revdanda beach

q1 s5q1 5 km Beach (coastal ecosystem)

high Tourist spot which has high human activity, monoculture of plant species like casuarinas, coconut & areca nut in the surrounding areas

18

Revdanda beach

q2 s5q2 5 km Beach (coastal ecosystem)

high Tourist spot with high human activity, monoculture of plant species like casuarinas, coconut & areca nut in the surrounding areas

19 Revdanda beach

q3 s5q3 5 km Beach (coastal ecosystem)

high Tourist spot with high human activity, monoculture of plant species like casuarinas, coconut & areca nut in the surrounding areas

20 Revdanda beach

q4 s5q4 5 km Beach (coastal ecosystem)

high Tourist spot with high human activity, monoculture of plant species like casuarinas, coconut & areca nut in the surrounding areas

Sr. No.

Sampling locations

Quadrate number

Quadrate code

Distance radius

Habitat Impact notes

21 Korlai fort q1 s6q1 2 km Plantations on mountain

surrounded by coastal ecosystem

high Tourist spot with high human activity

22 Korlai fort q2 s6q2 2 km Plantations on mountain

surrounded by coastal ecosystem

high Tourist spot with high human activity, monoculture of Acacia aurculiformi-the Australian

acacia

23 Korlai fort q3 s6q3 2 km Plantations on mountain

surrounded by coastal ecosystem

high Tourist spot with high human activity, monoculture of Acacia aurculiformi-the

Australian acacia

24 Korlai fort q4 s6q4 2 km Plantations on mountain

surrounded by coastal ecosystem

high Tourist spot with high human activity, monoculture of Acacia aurculiformi-the

Australian acacia

25 Korlai

q1 s7q1 2 km Agriculture moderate Agricultural landuse

26 Korlai

q2 s7q2 2 km Forest Low Low human impact, potential for high biodiversity

27 Korlai

q3 s7q3 2 km Forest Low Low human impact, potential for high biodiversity

28 Korlai

q4 s7q4 2 km Forest Low Low human impact, potential for high biodiversity

29 Revdanda jetty

q1 s8q1 2 km Mangrove moderate Mangrove species dominated by Avicennia species, presence of migratory birds

Sr. No.

Sampling locations

Quadrate number

Quadrate code

Distance radius

Habitat Impact notes

30 Revdanda jetty

q2 s8q2 2 km Mangrove moderate Mangrove species dominated by Avicennia species, presence of migratory birds

31 Revdanda jetty

q3 s8q3 2 km Mangrove moderate Mangrove species dominated by Avicennia species, presence of migratory birds

32 Revdanda jetty

q4 s8q4 2 km Mangrove moderate Mangrove species dominated by Avicennia species, presence of migratory birds

33 Agrav jetty q1 s9q1 5 km Mangrove moderate Mangrove species dominated by Avicennia species, presence of migratory birds

34 Agrav jetty q2 s9q2 5 km Mangrove moderate Mangrove species dominated by Avicennia species, presence of migratory birds

35 Agrav jetty q3 s9q3 5 km Mangrove moderate Mangrove species dominated by Avicennia species, presence of migratory birds

36 Agrav jetty q4 s9q4 5 km Mangrove moderate Mangrove species dominated by Avicennia species, presence of migratory birds

Appendix 2: Flora Appendix 2.1 Flora in Core Appendix 2.1 a Checklist of flora in core

Sr. No. Scientific name Common name Family Habit

1 Avicennia marina (Forssk.)Vierh Mauritian grass Avicenniaceae Tree 2 Avicennia officinalis L. Tivar Avicenniaceae Tree 3 Pongamia pinnata (L.) Pierre Karanj Fabbaceae Tree 4 Sonneratia alba Sm. Karpu Acanthaceae Tree 5 Zizyphus mauritiana Lamk. Ber Rhamnaceae Tree 6 Erythrina stricta Roxb. Phangara Fabbaceae Tree 7 Kirganelia reticulata (Poir) Baill. Pitouri Euphorbiaceae Shrub 8 Ricinus communis Linn. Castor Euphorbiaceae Shrub 9 Achyranthes aspera L. Tivar Amaranthaceae Herb

10 Ageratum conyzoides L. Aghada Asteraceae Herb 11 Alternanthera paronychioides St. -Hill. Osadi Amaranthaceae Herb 12 Apluda mutica L. Smooth chaff Flower Poaceae Herb 13 Celosia argentea L. Kurdu Amaranthaceae Herb 14 Crotalaria juncea L. Sun hemp Fabaceae Herb 15 Mimosa pudica L. Lajalu Mimosaceae Herb 16 Scoparia dulcis L. Sweet Broom Weed Scrophulariaceae Herb 17 Sida cordata (Burm.f.) Borssum Bhui-chikna Malvaceae Herb 18 Cocculus hirsutus (L.) Diels Vasan vel Menispermaceae Climber

Appendix 2.1 b Phytosociological study in core I: Individuals- Number of individuals encountered-abundance, O: Occurrence -Number of quadrate a species has occurred in, RDo: Relative Dominance, RF: Relative Frequency, IVI: Importance Value Index

Sr. No. Scientific.name Habit Family Common name I O Rdo RF IVI 1 Avicennia marina (Forssk.) Vierh. Tree Avicenniaceae Tivar 32 4 50.79365 30.76923 81.56288 2 Avicennia officinalis L. Tree Avicenniaceae Tivar 13 3 20.63492 23.07692 43.71184 3 Sonneratia alba Sm. Tree Acanthaceae Karpu 11 3 17.46032 23.07692 40.53724 4 Pongamia pinnata (L.) Pierre Tree Fabbaceae Karanj 5 2 7.936508 15.38462 23.32112 5 Erythrina stricta Roxb. Tree Fabbaceae Phangara 2 1 3.174603 7.692308 10.86691

Appendix 2.2 Flora in Buffer Appendix 2.2 a Checklist of flora in buffer Sr. No. Scientific name Common name Family Habit

1 Acacia auriculiformis A.Cunn.exBenth. Australian babhul Mimosaceae Tree 2 Acacia catechuoides (Roxb.)Benth. Khair Mimosaceae Tree

3 Albizia odoratissima (L.f.) Benth. Chinchwa Mimosaceae Tree 4 Alstonia scholaris (L.) R.Br. Saptaparni Apocynaceae Tree 5 Anacardium occidentale L. Kaju Anacardiaceae Tree

6 Annona reticulata Linn. Ramphal Annonaceae Tree 7 Artocarpus heterophyllus Lamk. Phanas Moraceae Tree 8 Artocarpus incisus (Thunb.) L.f. Nirphanas Moraceae Tree

9 Avicennia officinalis L. Tivar Avicenniaceae Tree 10 Avicennia marina (Forssk.) Vierh. Tivar Avicenniaceae Tree

11 Bridelia spinosa Willd. Asana Euphorbiaceae Tree 12 Careya arborea Roxb. Kumbh Lecythidaceae Tree 13 Carica papaya L. Pappayi Caricaceae Tree

Sr. No. Scientific name Common name Family Habit

14 Caryota urens L. Bherli Mad Arecaceae Tree 15 Casuarina equisetifolia J. R. & G. Forst Suru Casuarinaceae Tree 16 Ceiba pentandra (L.) Gaertn. Kapok Malvaceae Tree

17 Cocos nucifera L. Naral Arecaceae Tree 18 Cordia dichotoma Forst.f. Bhokar Boraginaceae Tree 19 Delonix regia (Hook.) Rafin. Gulmohar Caesalpiniaceae Tree

20 Erythrina variegata L. Pangro Fabaceae Tree

21 Eucalyptus globulus Labil. Nilgiri Myrtaceae Tree

22 Ficus benghalensis L. Vad Moraceae Tree

23 Ficus hispida L.f. Kala Umber Moraceae Tree 24 Ficus racemosa L. Umber Moraceae Tree

25 Ficus religiosa L. Pimpal Moraceae Tree 26 Ficus callosa Willd. Calloused fig Moraceae Tree 27 Firmiana colorata (Roxb.) Br. Kavas Sterculiaceae Tree

28 Flacourtia indica (Burm.f.) Merr. Athruna Flacourtiaeae Tree

29 Gliricidia sepium (Jacq.) Walp. Giripushpa Fabaceae Tree

30 Grewia tiliaefolia Vahl Dhaman Tiliaceae Tree 31 Jatropha curcas Linn. Mogali erand Euphorbiaceae Tree 32 Lagerstroemia parviflora Roxb. Nana Lythraceae Tree 33 Lannea coromandelica (Houtt.) Merrill Shemat Anacardiaceae Tree 34 Leucaena leucocephala (Lamk.) De Wit. Subabhul Mimosaceae Tree 35 Macaranga peltata (Roxb.) Muell-Arg. Chanda Euphorbiaceae Tree

Sr. No. Scientific name Common name Family Habit

36 Mallotus philipinensis (Lamk.) Muell.-Arg. Shendri Euphorbiaceae Tree 37 Mangifera indica L. Amba Anacardiaceae Tree 38 Manilkara hexandra (Roxb.) Dubard Ceylon iron wood, Khirni Sapotaceae Tree 39 Memecylon umbellatum Burm. f. Anjan Melastomataceae Tree 40 Morinda pubesence Sm. Bartondi (Mp) Rubiaceae Tree 41 Oroxylum indicum (L.) Vent. Tetu Bignoniaceae Tree 42 Peltophorum pterocarpum (DC.) Bk.exHyn Sonmohar Caesalpiniaceae Tree 43 Plumeria alba L. Champa Apocynaceae Tree 44 Polyalthia longifolia (Sonn.) Thw. Asupalav (Pasarat) Annonaceae Tree 45 Pongamia pinnata (L.) Pierre Karanj Fabaceae Tree 46 Pterocarpus marsupium Roxb. `Bibla Fabaceae Tree 47 Rhizophora mucronata Lam. Asiatic Mangroove Rhizophoraceae Tree 48 Salmalia rubra (Buch.-Ham.) S. Dutta & P. Harvey Kate savar Bombacaceae Tree 49 Salvadora persica Linn. Pilu, Pilva Salvadoraceae Tree 50 Samania saman (Jacq.) Merrill Raintree Mimosaceae Tree 51 Sonneratia alba Sm. Karpu Acanthaceae Tree 52 Sterculia urens Roxb. Kahandol Sterculiaceae Tree 53 Streblus asper Lour. Kharoti Moraceae Tree 54 Syzygium cuminii (L.) Skeels Jamun Myrtaceae Tree 55 Tamarindus indica L. Chinch Caesalpiniaceae Tree 56 Tectona grandis L.f. Sag Verbenaceae Tree 57 Terminalia bellirica (Gaertn.) Roxb. Beheda Combretaceae Tree 58 Terminalia catappa L. Deshi badam Combretaceae Tree 59 Terminalia crenulata (Heyne) Roth Ain Combretaceae Tree

Sr. No. Scientific name Common name Family Habit

60 Terminalia paniculata Roth Kindal Combretaceae Tree 61 Thespesia populnea (L.) Sol.exCor. Bhend Malvaceae Tree 62 Vitex negundo L. Nirgudi Verbenaceae Tree 63 Zanthoxylum rhetsa DC Tirphal Rutaceae Tree 64 Zizyphus mauritiana Lamk. Ber Rhamnaceae Tree 65 Bombax ceiba L. Kate savar Bombacaceae Tree 66 Azadirachta indica (L.) Juss. Kadu Neem Meliaceae Tree 67 Abelmoschus manihot (Linn.) Medicus Raan Bhendi Malvaceae Shrub 68 Acanthus ilicifolius L. Marangi Acanthaceae Shrub 69 Calotropis gigantea (L.) R.Br. Akra,Ruie Asclepiadaceae Shrub 70 Calotropis procera (Ait.) R.Br. Akra,Ruie Asclepiadaceae Shrub 71 Catunaregam spinosa (Thunb.) Tiruveng. Gela Rubiaceae Shrub 72 Citrus limon (L.) Osbeck Nimbu Rutaceae Shrub 73 Crotalaria verrucosa L. Blue rattlepod, Sagartag Fabaceae Shrub 74 Ervatamia alternifolia (L.) S.M.Almeida Naag-kuda Apocynaceae Shrub 75 Eupatorium repandum Willd. Ranmodi Asteraceae Shrub 76 Hamelia patens Jacq. Firebush Rubiaceae Shrub 77 Helicteris isora L. Murad-sheng Sterculiaceae Shrub 78 Ixora parviflora Lamk. Lokhandi Rubiaceae Shrub 79 Kirganelia reticulata (Poir) Baill. Pitouri Euphorbiaceae Shrub 80 Lantana camara L. Ghaneri Verbenaceae Shrub 81 Leea macrophylla Roxb Gajkarni Leeaceae Shrub 82 Leea indica (Burm. f.) Merr. Karkani Leeaceae Shrub 83 Psidium guajava Linn. Peru Myrtaceae Shrub

Sr. No. Scientific name Common name Family Habit

84 Woodfordia fruticosa (L.) Kurz. Dhaiti Lythraceae Shrub 85 Carissa carandas L. Karvanda Apocynaceae Shrub 86 Abutilon indicum (L.) Sweet Mudra Malvaceae Herb 87 Acalypha indica Linn. Kupi Euphorbiaceae Herb 88 Achyranthes aspera L. Aghada Amaranthaceae Herb 89 Aerva lanta (Linn.) Juss. Kapuri-Madhuri Amaranthaceae Herb 90 Ageratum conyzoides L. Osadi Asteraceae Herb 91 Alternanthera paronychioides St. -Hill. Smooth chaff Flower Amaranthaceae Herb 92 Alysicarpus vaginalis (L.) DC., Chipta Fabaceae Herb 93 Andrographis paniculata (Burm.f.) Wall.ex Nees Kariyat Acanthaceae Herb 94 Anisomeles heyneana Benth. Chandar , Gopali Lamiaceae Herb 95 Apluda mutica L. Mauritian grass Poaceae Herb 96 Barleria pretoriensis C.B.Clarke Vajradanti Acanthaceae Herb 97 Blepharis maderaspatensis (L.) Roth, Creeping Blepharis Acanthaceae Herb 98 Blumea sp. Asteraceae Herb 99 Canscora diffusa (Vahl) R.Br. Kilwar Gentianaceae Herb

100 Cassia tora L. Takla Caesalpiniaceae Herb 101 Celosia argentea L. Kurdu Amaranthaceae Herb 102 Colocasia esculenta (L.) Schott Aaloo Araceae Herb 103 Crotalaria juncea L. Sun hemp Fabaceae Herb 104 Crotalaria pallida Aiton Sun hemp Fabaceae Herb 105 Cyathocline purpurea Gangotra Asteraceae Herb 106 Cyperus difformis L. Variable flatedge Cyperaceae Herb 107 Cyperus irea L. Kangaroo grass Cyperaceae Herb

Sr. No. Scientific name Common name Family Habit

108 Desmodium triflorum (L.) DC Ranmethi Fabaceae Herb 109 Eranthemum roseum (Vahl) R.Br. Dasmuli Acanthaceae Herb 110 Gomphrena celosioides Mart. Prostrate gomphrena Amaranthaceae Herb 111 Hemegraphis latebrosa (Roth) Nees Shade loving Acanthaceae Herb 112 Hygrophila ringens (L.) R. Br. ex Spreng. Erect hygrophilla Acanthaceae Herb 113 Hyptis suaveolens (Linn.) Poir Bhustrena Lamiaceae Herb 114 Ixora coccinea L. Patkalin Rubiaceae Shrub 115 Leucas aspera (Willd.) Link. Tumba Lamiaceae Herb 116 Ludwigia perensis Linn. Paddy clove Onagraceae Herb 117 Malachra capitata L. Ranbhendi Malvaceae Herb 118 Ocimum tenuiflorum L. Tulsi Lamiaceae Herb 119 Oldenlandia herbacea (L.) Roxb. Slender oldenlandia Rubiaceae Herb 120 Oplismenus compositus Beauv. Running mountaingrass Poaceae Herb 121 Pedilanthus tithymaloides (L.) Poit. Devil'sBackbone Euphorbiaceae Herb 122 Plumbago zyelanica L. Chitrak Plumbaginaceae Herb 123 Portulaca oleracea Linn. Ghol Portulacaceae Herb 124 Scoparia dulcis L. Sweet Broom Weed Scrophulariaceae Herb 125 Sida cordata (Burm.f.) Borssum Bhui-chikna Malvaceae Herb 126 Sida rhombifolia L. Chikna Malvaceae Herb 127 Sphaeranthus indicus L. Gorakhmundi Asteraceae Herb 128 Synedrella nodiflora (L.) Gartn. Pig Grass Asteraceae Herb 129 Tephrosia purpurea (L.) Pers. Unchali Fabaceae Herb 130 Themeda quadrivalvis (Linn.) O. Kuntze Kangaroo Grass Poaceae Herb 131 Tridax procumbens L. Dagdipala,Ekdandi Asteraceae Herb

Sr. No. Scientific name Common name Family Habit

132 Triumfetta rhomboidea Jaquin Ottu Pullu Tiliaceae Herb 133 Urena lobata L. Van-bhendi Malvaceae Herb 134 Vernonia cinerea (L.) Less. Sahadevi Asteraceae Herb 135 Dendrophthoe falcata (L.f.) Ettingsh. Vanda Loranthaceae Epiphyte 136 Vanda sp. Orchidaceae Epiphyte 137 Abrus precatorius L. Gunj Fabaceae Climber 138 Argyreia nervosa (Burm. f.) Bojer Elephant Creeper Convolvulaceae Climber 139 Bridelia stipularis (L.) Blume Patharphodi Euphorbiaceae Climber 140 Cajanus scarabaeoides (L.) Thouars Ghoshyachi vel Fabaceae Climber 141 Calycopteris floribunda Lamk. Ukshi Combretaceae Climber 142 Canavalia gladiata (Jacq.) DC. Abhai Fabaceae Climber 143 Capparis zeylanica L. Tarati Capparaceae Climber 144 Celastrus paniculatus Kanguni, Black oil plant Celastraceae Climber 145 Coccinea grandis (L.) Voight Tondli Cucurbitaceae Climber 146 Cocculus hirsutus (L.) Diels Vasan vel Menispermaceae Climber 147 Cucumis melo L. Wild Melon Cucurbitaceae Climber 148 Cucumis sativus L. Cucumber Cucurbitaceae Climber 149 Cyclea peltata (Lamk.) Hook.f. & Thoms. Pakar Menispermaceae Climber 150 Dalbergia volabilis Roxb. Alai Fabaceae Climber 151 Dregea volubilis (L.f.) Benth. Ex Hoo.f. Hiran Dodi Asclepiadaceae Climber 152 Evolvulus nummularifolia L. Nimulvel Convolvulaceae Climber 153 Ficus repens Roxb. ex Sm. Black ficus Moraceae Climber 154 Hemidesmus indicus (Linn.) Schult. Anantmul Periplocaceae Climber 155 Ipomoea biloba Forssk. Morning glory Convolvulaceae Climber

Sr. No. Scientific name Common name Family Habit

156 Jasminum malabaricum Wight Malabar Jasmine, Kusar Oleaceae Climber 157 Momordica charantia Linn. Karela Cucurbitaceae Climber 158 Mucuna pruriens (L.) DC. Prodr. Khaj-kuili Fabaceae Climber 159 Paracalyx scariosus (Roxb.)Ali Ran ghevda Fabaceae Climber 160 Passiflora foetida Linn. Veli-ghani Passifloraceae Climber 161 Quisqualis indica Linn. Madhumalti Combretaceae Climber 162 Smilax zeylanica L. Ghotvel Smilacaceae Climber 163 Zizyphus oenoplia (L.) Mill. Burgi Rhamnaceae Climber 164 Zizyphus xylopyra (Retz.) Willd. Giti Rhamnaceae Climber

Appendix 2.2 b Phytosociological study in buffer I: Individuals- Number of individuals encountered-abundance, O: Occurrence -Number of quadrate a species has occurred in, RDo: Relative Dominance, RF: Relative Frequency, IVI: Importance Value Index

Sr. No.

Scientific name Habit Common name

I O Rdo RF IVI

1 Carissa carandas L. Karvanda Shrub 48 13 4.98 4.02 9.0092 2 Avicennia marina (Forssk.) Vierh. Tivar Tree 43 8 4.47 2.48 6.942 3 Hemigraphis latebrosa (Heyne ex Roth) Nees in DC Shade loving hemigraphis Herb 33 10 3.43 3.1 6.5228 4 Eupatorium odorata Ranmodi Shrub 33 7 3.43 2.17 5.594 5 Lantana camara L. Ghaneri Shrub 33 7 3.43 2.17 5.594 6 Zizyphus mauritiana Lamk. Ber Tree 32 9 3.32 2.79 6.1093 7 Themeda quadrivalvis (Linn.) O. Kuntze Kangaroo grass Herb 32 7 3.32 2.17 5.4901 8 Wrightia tinctoria (Roxb.) R.Br Kuda Tree 26 8 2.7 2.48 5.1767 9 Avicennia officinalis L. Tivar Tree 26 7 2.7 2.17 4.8671 10 Alternanthera paronychioides St. -Hill. Smooth chaff flower Herb 25 6 2.6 1.86 4.4536 11 Tectona grandis L.f. Sag Tree 24 6 2.49 1.86 4.3498

Sr. No.

Scientific name Habit Common name

I O Rdo RF IVI

12 Acacia catechuoides (Roxb.)Benth. Khair Herb 23 6 2.39 1.86 4.246 13 Calycopteris floribunda Lamk. Ukshi Climber 22 9 2.28 2.79 5.0709 14 Acacia auriculiformis A.Cunh Australian bahul Tree 20 6 2.08 1.86 3.9344 15 Calotropis gigantea (L.) R.Br. Akra,Ruie Shrub 19 6 1.97 1.86 3.8306 16 Grewia asiatica L. Phalsa Tree 18 7 1.87 2.17 4.0363 17 Acanthus ilicifolius L. Marangi Shrub 18 5 1.87 1.55 3.4171 18 Ficus hispida L. Kala umber Tree 18 5 1.87 1.55 3.4171 19 Sonneratia alba Sm. Karpa Tree 18 5 1.87 1.55 3.4171 20 Tridax procumbens L. Dagdipala,Ekdandi Herb 17 4 1.77 1.24 3.0037 21 Casuarina equisetifolia J. R. & G. Forst Suru Tree 17 3 1.77 0.93 2.6941 22 Eranthemum roseum (Vahl) R.Br. Dasmuli Herb 15 5 1.56 1.55 3.1056 23 Gliricidia sepium (Jacq.) Walp. Giripushpa Tree 15 4 1.56 1.24 2.796 24 Apluda mutica L. Chandar , Gopali Herb 14 6 1.45 1.86 3.3114 25 Salmalia rubra (Buch.Ham.) S. Dutta & P. Harvey Kate savar Tree 14 6 1.45 1.86 3.3114 26 Ipomoea biloba Forssk Morning glory Climber 14 3 1.45 0.93 2.3826 27 Desmodium triflorum (L.) DC Ranmethi Herb 13 7 1.35 2.17 3.5171 28 Lannea coromandelica (Houtt.) Merrill Shemat Tree 13 7 1.35 2.17 3.5171 29 Mangifera idica Linn. Amba Tree 13 5 1.35 1.55 2.8979 30 Ixora brachiata Roxb Lokhandi Tree 13 4 1.35 1.24 2.5883 31 Ageratum conyzoides L. Osadi Herb 12 6 1.25 1.86 3.1037 32 Celosia argentea L. Kurdu Herb 12 4 1.25 1.24 2.4845 33 Portulaca oleracea Linn. Ghol Herb 12 3 1.25 0.93 2.1749 34 Smilax zeylanica L Ghotvel Climber 11 4 1.14 1.24 2.3807 35 Terminalia crenulata Roth. Ain Tree 10 4 1.04 1.24 2.2768 36 Cyathocline purpurea (Buch.-Ham. ex D.Don) Kuntze Gangotra Herb 10 3 1.04 0.93 1.9672 37 Crotalaria verrucosa L. Blue rattlepos,Sagartag Shrub 9 3 0.93 0.93 1.8634

Sr. No.

Scientific name Habit Common name

I O Rdo RF IVI

38 Helicteres isora L. Murud sheng Shrub 9 3 0.93 0.93 1.8634 39 Hemidesmus indicus (Linn.) Schult. Anantmul Climber 9 3 0.93 0.93 1.8634 40 Blepharis maderaspatensis (L.) Roth. Creeping blepharis Herb 8 4 0.83 1.24 2.0691 41 Macaranga peltata (Roxb.) Muell-Arg. Chanda Tree 8 4 0.83 1.24 2.0691 42 Lanatana camara Ghaneri Shrub 8 2 0.83 0.62 1.4499 43 Flacourtia montana Graham. Athruna Tree 7 3 0.73 0.93 1.6557 44 Cyclea peltata (Lamk.) Hk.f. Pakar Climber 7 2 0.73 0.62 1.3461 45 Dalbergia volubilis Roxb Alai Climber 7 2 0.73 0.62 1.3461 46 Tephrosia purpurea (L.) Pers. Unchali Herb 7 2 0.73 0.62 1.3461 47 Cocculus hirsutus (L.) Diels. Vasan vel Climber 6 3 0.62 0.93 1.5518 48 Pongamia pinnata (L.) Pierre Karanj Tree 6 3 0.62 0.93 1.5518 49 Salvadora persica Linn. Pilu ,Pilva Tree 6 3 0.62 0.93 1.5518 50 Kirganelia reticulata (Poir) Baill. Pitouri Shrub 6 2 0.62 0.62 1.2422 51 Mucuna pruriens (L.) DC. Prodr. Khaj-Kuili Climber 6 2 0.62 0.62 1.2422 52 Urena lobata L. Van-Bhendi Herb 6 2 0.62 0.62 1.2422 53 Careya arborea Roxb Kumbha Tree 5 5 0.52 1.55 2.0672 54 Canavalia gladiata (Jacq.) DC. Abhai Climber 5 3 0.52 0.93 1.448 55 Thespesia populnea (L.) Sol.exCor. Bhend Tree 5 3 0.52 0.93 1.448 56 Andrographis paniculata (Burm.f.) Wall.ex Nees Kariyat Herb 5 2 0.52 0.62 1.1384 57 Anogeisus latifolia (Roxb.ex DC.) Guillemin. & Perottet. Dhavda Tree 5 2 0.52 0.62 1.1384 58 Barleria pretoriensis C.B.Clarke Vajradanti Herb 5 2 0.52 0.62 1.1384 59 Sida rhombifolia L. Chikna Herb 5 2 0.52 0.62 1.1384 60 Vitex negundo L. Nirgudi Tree 5 2 0.52 0.62 1.1384 61 Hyptis suaveolens (Linn.) Poir Bhustrena Herb 5 1 0.52 0.31 0.8288 62 Anisomeles heyneana Benth Chandar Gopali Herb 4 3 0.42 0.93 1.3442 63 Triumfetta rhomboidea Jaquin Ottu Pullu Herb 4 1 0.42 0.31 0.725

Sr. No.

Scientific name Habit Common name

I O Rdo RF IVI

64 Bridelia spinosa Willd. Asana Tree 3 3 0.31 0.93 1.2403 65 Ficus racemosa L. Umber Tree 3 3 0.31 0.93 1.2403 66 Ixora coccinea L. Patkalin Shrub 3 2 0.31 0.62 0.9307 67 Streblus asper Lour. Kharoti Tree 3 2 0.31 0.62 0.9307 68 Woodfordia subfruticosa (L.) Kurz Dhaiti Shrub 3 2 0.31 0.62 0.9307 69 Blumea oxyodonta DC. Spiny leaved blumea Herb 3 1 0.31 0.31 0.6211 70 Cordia dichotoma Forst.f. Bhokar Tree 3 1 0.31 0.31 0.6211 71 Eclipta prostrata (L.) L. Bhringraj Herb 3 1 0.31 0.31 0.6211 72 Leucaena leucocephala (Lamk.) De Wit. Subabhul Tree 3 1 0.31 0.31 0.6211 73 Microcos paniculata L. Hansoli,Shiral Tree 3 1 0.31 0.31 0.6211 74 Triumfetta rhomboidea Jacq Ottu pullu Herb 3 1 0.31 0.31 0.6211 75 Azadirachta indica (L.) Juss. Kadu neem Tree 2 2 0.21 0.62 0.8269 76 Abrus precatorius L. Gunj Climber 2 1 0.21 0.31 0.5173 77 Dregea volubilis (L.f.) Benth. ex Hoo.f. Hiran dodi Climber 2 1 0.21 0.31 0.5173 78 Ficus benghalensis L. Vad Tree 2 1 0.21 0.31 0.5173 79 Grewia tiliaefolia Vahl Dhaman Tree 2 1 0.21 0.31 0.5173 80 Smilex indica Ghotvel Climber 2 1 0.21 0.31 0.5173 81 Abelmoschus manihot (L.) Medic Raan Bhendi Shrub 1 1 0.1 0.31 0.4134 82 Bauhinia racemosa Lamk. Apta Tree 1 1 0.1 0.31 0.4134 83 Borasus flabelliformis L. Tad Tree 1 1 0.1 0.31 0.4134 84 Bridelia stipularis (L.) Blume Patharphodi Tree 1 1 0.1 0.31 0.4134 85 Catunaregam spinsa (Thunb.) Triveng. Gela Tree 1 1 0.1 0.31 0.4134 86 Coccinea grandis (L.) Voight. Tondli Climber 1 1 0.1 0.31 0.4134 87 Diploclisia glaucescens (Bl.) Diels. Ramrakh Climber 1 1 0.1 0.31 0.4134 88 Flacourtia indica Athrun Tree 1 1 0.1 0.31 0.4134 89 Leea macrophylla Roxb Gajkarni Shrub 1 1 0.1 0.31 0.4134

Sr. No.

Scientific name Habit Common name

I O Rdo RF IVI

90 Passiflora foetida Linn. Vel-ghani Climber 1 1 0.1 0.31 0.4134 91 Sterculia urens Roxb. Kahandol Tree 1 1 0.1 0.31 0.4134 92 Syzygium cuminii (L.) Skeels Jambhul Tree 1 1 0.1 0.31 0.4134 93 Vernonia acuminatum (D.Don) Almeida Shadevi Herb 1 1 0.1 0.31 0.4134 94 Zizyphus xylopyra (Retz.) Willd. Giti Climber 1 1 0.1 0.31 0.4134

Appendix 2.2 c Common plants in Buffer

Sr. No. Scientific Name Habit Common name Abundance 1 Carissa carandas L. Karvand Shrub 48 2 Avicennia marina (Forssk.) Vierh. Tivar Tree 43 3 Hemigraphis latebrosa (Heyne ex Roth) Nees in DC Shade loving hemigraphis Herb 33 4 Eupatorium odorata Ranmodi Shrub 33 5 Lantana camara L. Ghaneri Shrub 33 6 Zizyphus mauritiana Lamk. Ber Tree 32 7 Themeda quadrivalvis (Linn.) O. Kuntze Kangaroo grass Herb 32 8 Wrightia tinctoria (Roxb.) R.Br Kuda Tree 26 9 Avicennia officinalis L. Tivar Tree 26

10 Alternanthera paronychioides St. -Hill. Smooth chaff flower Herb 25 11 Tectona grandis L.f. Sag Tree 24 12 Acacia catechuoides (Roxb.)Benth. Khair Tree 23 13 Calycopteris floribunda Lamk. Ukshi Climber 22 14 Acacia auriculiformis A.Cunh Australian babhul Tree 20 15 Calotropis gigantea (L.) R.Br. Akra, Ruie Shrub 19 16 Grewia asiatica L. Phalsa Tree 18 17 Acanthus ilicifolius L. Marangi Shrub 18 18 Ficus hispida L. Kala umber Tree 18

Sr. No. Scientific Name Habit Common name Abundance 19 Sonneratia alba Sm. Karpu Tree 18 20 Tridax procumbens L. Dagdipala, Ekdandi Herb 17 21 Casuarina equisetifolia J. R. & G. Forst Suru Tree 17 22 Eranthemum roseum (Vahl) R.Br. Dasmuli Herb 15 23 Gliricidia sepium (Jacq.) Walp. Giripushpa Tree 15 24 Apluda mutica L. Mauritian grass Herb 14 25 Salmalia rubra (Buch.?Ham.) S. Dutta & P. Harvey Kate savar Tree 14 26 Ipomoea biloba Forssk Morning glory Climber 14 27 Desmodium triflorum (L.) DC Ranmethi Herb 13 28 Lannea coromandelica (Houtt.) Merrill Shemat Tree 13 29 Mangifera idica Linn. Amba Tree 13 30 Ixora brachiata Roxb Lokhandi Shrub 13

Appendix 2.2 d ecologically important species Note: These are non-mangrove species. These represent ecologically important species in and around the degraded forest patches.

Sr. No. Plant species Common Name

Family Habit Status Main Attractant for animals

1. Acacia catechu Khair Leguminosae Tree Native Flowers 2. Aegele marmelos Bel Rutaceae Tree Native Flowers and fruits 3. Albizia lebbeck Kala-siris Leguminosae Tree Native Flower and Fruits 4. Anogeissus latifolia Dhaora Sappotaceae Tree Native Fruits 5. Bauhinia purpurea Keolar Leguminosae Tree Native Flowers 6. Bauhinia racemosa Asta Leguminosae Tree Native Flowers 7. Bombax ceiba Semal Malvaceae Tree Native Flowers 8. Bridelia retusa Kasai Euphorbiaceae Tree Native Fruits 9. Buchanania latifolia Achar Anacardiaceae Tree Native Fruits

10. Butea monosperma Palas Leguminosae Tree Native Flowers

Sr. No. Plant species Common Name

Family Habit Status Main Attractant for animals

11. Carreya arborea Kumbhi Lecythedaceae Tree Native Flowers 12. Casaeria graveolens Gilchi Samydaceae Tree Native 13. Cassia fistula Amaltas Leguminosae Tree Native Fruits 14. Dalbergia latifolia Shisham Leguminosae Tree Native 15. Dalbergia sisoo Sisoo Leguminosae Tree Native Fruits 16. Diospyros melanoxylon Tendu Ebenaceae Tree Native Fruits 17. Diospyros montana Bistendu Ebenaceae Tree Native Fruits 18. Ficus benghalensis Bar Moraceae Tree Native Fruits 19. Ficus glomerata Gular Moraceae Tree Native Fruits 20. Ficus infectoria Pakar Moraceae Tree Native Fruits 21. Ficus religiosa Pipal Moraceae Tree Native Fruits 22. Flacourtia indica Native Fruits 23. Garuga pinnata Kekad Burseraceae Tree Native Flowers and fruits 24. Gmelina arborea Gamari Verbenaceae Tree Native Flower 25. Grewia tilifolia Dhaman Tiliaceae Tree Native Flower 26. Holoptelia integrifolia Chirol Ulmaceae Tree Native Fruit 27. Lagerstroemia parviflora Seja Lythraceae Tree Native Flower 28. Lannea coromondalica Jhingan Anacardiaceae Tree Native Fruits 29. Madhuca longifolia Mahua Euphorbiaceae Tree Native Flowers 30. Mangifera indica Amba Anacardiaceae Tree Native Flower and Fruits 31. Pongamia pinnata Karanj Leguminosae Tree Native Flowers 32. Pterocarpus marsupium Bijasal Leguminosae Tree Native Fruits 33. Schleichera oleosa Kusum Sapindaceae Tree Native Fruits 34. Sterculia urens Kulu Sterculiaceae Tree Native Fruits 35. Tamarindus indica Imli Leguminosae Tree Introduced Fruits 36. Tectona grandis Sagon Verbenaceae Tree Native Flowers

Sr. No. Plant species Common Name

Family Habit Status Main Attractant for animals

37. Terminalia arjuna Arjun Combretaceae Tree Native Fruits and flowers 38. Terminalia belerica Bahera Combretaceae Tree Native Flowers 39. Terminalia chebula Harra Combretaceae Tree Native Flowers 40. Terminalia tomentosa Tondri Combretaceae Tree Native Flowers

Appendix 3: Fauna Appendix 3.1 Fauna in Core Appendix 3.1 a Checklist of faunal species in core

Sr. No.

Scientific name Common name Family Faunal group

IUCN status Schedule

(WPA 1972)

1 Plexippus paykulli jumping spider Salticidae Arachnida - - 2 Cyrtophora bidenta tent spider Araneidae Arachnida - - 3 Egretta garzetta Little Egret Ardeidae Avian Least Concern IV 4 Acrocephalus dumetorum Blyth's Reed Warbler Acrocephalidae Avian Least Concern - 5 Actitis hypoleucos Common Sandpiper Scolopacidae Avian Least Concern IV 6 Alcedo atthis Common Kingfisher Alcedinidae Avian Least Concern IV 7 Ardeola grayii Indian Pond Heron Ardeidae Avian Least Concern IV 8 gelochelidon nilotica Common Gull-billed Tern Laridae Avian Least Concern - 9 Halcyon smyrnensis White-breasted Kingfisher Alcedinidae Avian Least Concern IV

10 Pluvialis squatarola Grey Plover Charadriidae Avian Least Concern IV 11 Tringa stagnatilis Marsh Sandpiper Scolopacidae Avian Least Concern IV 12 Tringa totanus Common Redshank Scolopacidae Avian Least Concern IV 13 Ariadne merione Common Castor Nymphalidae Insecta - - 14 Catopsilia pomona Lemon Emigrant Pieridae Insecta - - 15 Colotis amata Small Salmon Arab Pieridae Insecta - - 16 Danaus genutia Striped Tiger Nymphalidae Insecta - -

Sr. No.

Scientific name Common name Family Faunal group

IUCN status Schedule

(WPA 1972)

17 Euploea core Common Crow Nymphalidae Insecta Least Concern - 18 Papilio polytes Common Mormon Papilionidae Insecta - - 19 Ocypodinae sp. Ghost Crab Ocypodidae Malacostraca - - 20 Uca sp. Feedler Crab Ocypodidae Malacostraca - -

Appendix 3.1 b Fauna diversity by quadrate sampling in core

Sr. No. Scientific name Common name Faunal group Abundance Occurrence 1 Halcyon smyrnensis White-breasted Kingfisher Avian 1 1 2 Pluvialis squatarola Grey Plover Avian 1 1 3 Acrocephalus dumetorum Blyth’s Reed Warbler Avian 2 1 4 Egretta garzetta Little Egret Avian 2 2 5 Tringa stagnatilis Marsh Sandpiper Avian 2 1 6 Alcedo atthis Common Kingfisher Avian 4 2 7 gelochelidon nilotica Gull-billed Tern Avian 7 1 8 Tringa totanus Common Redshank Avian 9 2 9 Ardeola grayii Indian Pond Heron Avian 10 3

10 Actitis hypoleucos Common Sandpiper Avian 58 3 11 Ariadne merione Common Castor Insecta 1 1 12 Danaus genutia Striped Tiger Insecta 1 1 13 Papilio polytes Common Mormon Insecta 1 1 14 Euploea core Common Crow Insecta 2 2 15 Catopsilia pomona Common Emigrant Insecta 3 2 16 Colotis amata Salmon Arab Insecta 50 1 17 Uca Fiddler Crab Malacostraca 20 1

Sr. No. Scientific name Common name Faunal group Abundance Occurrence 18 Ocypodinae Ghost Crab Malacostraca 25 1

Appendix 3.2 Fauna in Buffer Appendix 3.2 a Checklist of faunal species in Buffer

Sr. No.

Scientific name Common name Family Faunal groupIUCN Status

Schedule (WPA 1972)

1 Oxudercinae sp. Mudskipper Gobiidae Actinopterygii - -

2 Argiope anasuja Signature Spider Araneidae Arachnida - -

3 Castianeira longipalpa Long-palped Ant-mimicking Sac Spider

Corinnidae Arachnida - -

4 Chilobrachys fimbriatus Indian Violet Tarantula Theraphosidae Arachnida Least Concern - 5 Cyrtophora sp. Tent spider Araneidae Arachnida - - 6 Heterometrus longimanus Asian Forest Scorpion Scorpionidae Arachnida - - 7 Hippasa partita Funnel web spider Agelenidae Arachnida - - 8 Lycosidae sp. Wolf spider Lycosidae Arachnida - - 9 Salticidae jumping spider Salticidae Arachnida - -

10 Hottentotta sp. Hottentotta Buthidae Arachnida - - 11 Pandion haliaetus osprey Pandionidae Avian Least Concern I 12 Pavo cristatus Indian Peafowl Phasianidae Avian Least Concern I 13 Accipiter badius Shikra Accipitridae Avian Least Concern - 14 Clanga hastata Indian Spotted Eagle Accipitridae Avian Vulnerable -

15 Acridotheres tristis Common Myna Sturnidae Avian Least Concern IV

16 Actitis hypoleucos Common Sandpiper Scolopacidae Avian Least Concern IV

17 Alcedo atthis Common Kingfisher Alcedinidae Avian Least Concern IV

18 Ardea intermedia Intermediate Egret Ardeidae Avian Least Concern IV

Sr. No.

Scientific name Common name Family Faunal groupIUCN Status

Schedule (WPA 1972)

19 Bubulcus ibis Cattle Egret Ardeidae Avian Least Concern IV

20 Caprimulgus atripennis Jerdon's Nightjar Caprimulgidae Avian Least Concern IV

21 Charadrius alexandrinus Kentish Plover Charadriidae Avian Least Concern IV

22 Chroicocephalus brunnicephalus

Brown-headed Gull Laridae Avian Least Concern IV

23 Cinnyris asiaticus Purple Sunbird Nectariniidae Avian Least Concern IV

24 Cinnyris lotenius Loten's Sunbird Nectariniidae Avian Least Concern IV

25 Corvus macrorhynchos Large-billed Crow Corvidae Avian Least Concern -

26 Dendrocitta vagabunda Rufous Treepie Corvidae Avian Least Concern IV

27 Dicaeum agile Thick-billed Flowerpecker Dicaeidae Avian Least Concern IV 28 Dicrurus macrocercus Black Drongo Dicruridae Avian Least Concern IV 29 Dinopium benghalense Black-rumped Flameback Picidae Avian Least Concern IV 30 Egretta garzetta Little Egret Ardeidae Avian Least Concern IV 31 Halcyon smyrnensis White-throated Kingfisher Alcedinidae Avian Least Concern IV 32 Hypothymis azurea Black-naped Monarch Muscicapidae Avian Least Concern IV 33 Leptocoma zeylonica Purple-rumped Sunbird Nectariniidae Avian Least Concern IV 34 Psilopogon viridis White-cheeked Barbet Megalaimidae Avian Least Concern IV 35 Psilopogon zeylanicus Brown-headed Barbet Megalaimidae Avian Least Concern IV 36 Microcarbo niger Little Cormorant Phalacrocoracidae Avian Least Concern IV 37 Oriolus kundoo Indian Golden Oriole Oriolidae Avian Least Concern IV 38 Passer domesticus House Sparrow Passeridae Avian Least Concern - 39 Pericrocotus cinnamomeus Small Minivet Campephagidae Avian Least Concern IV

40 Pluvialis squatarola Grey Plover Charadriidae Avian Least Concern IV

41 Psittacula krameri Rose-ringed Parakeet Psittaculidae Avian Least Concern IV

42 Pycnonotus cafer Red-vented Bulbul Pycnonotidae Avian Least Concern IV

43 Pycnonotus jocosus Red-whiskered Bulbul Pycnonotidae Avian Least Concern IV

Sr. No.

Scientific name Common name Family Faunal groupIUCN Status

Schedule (WPA 1972)

44 Pycnonotus luteolus White-browed Bulbul Pycnonotidae Avian Least Concern IV

45 Rhipidura albicollis White-throated Fantail Rhipiduridae Avian Least Concern -

46 Spilopelia senegalensis Laughing Dove Columbidae Avian Least Concern IV

47 Spilopelia suratensis Western Spotted Dove Columbidae Avian Least Concern IV

48 Threskiornis melanocephalus Black-headed Ibis Threskiornithidae Avian Near Threatened

IV

49 Treron phoenicopterus Yellow-footed Green-pigeon Columbidae Avian Least Concern IV

50 Tringa stagnatilis Marsh Sandpiper Scolopacidae Avian Least Concern IV

51 Larus ichthyaetus Pallas's Gull Laridae Avian Least Concern -

52 Pernis ptilorhynchus Oriental Honey-buzzard Accipitridae Avian Least Concern - 53 Acrocephalus dumetorum Blyth's Reed-warbler Acrocephalidae Avian Least Concern - 54 Aquila rapax Tawny Eagle Accipitridae Avian Vulnerable - 55 Ardeola grayii Indian Pond-heron Ardeidae Avian Least Concern IV 56 Cecropis daurica Red-rumped Swallow Hirundinidae Avian Least Concern - 57 Centropus sinensis Greater Coucal Cuculidae Avian Least Concern - 58 Circus aeruginosus Western Marsh-harrier Acipitridae Avian Least Concern - 59 Cisticola juncidis Zitting Cisticola Cisticolidae Avian Least Concern - 60 Columba livia Rock Dove Columbidae Avian Least Concern - 61 Cypsiurus balasiensis Asian Palm-swift Apodidae Avian Least Concern - 62 Egretta gularis Western Reef-egret Ardeidae Avian Least Concern IV 63 Eudynamys scolopaceus Western Koel Cuculidae Avian Least Concern - 64 Gelochelidon nilotica Common Gull-billed Tern Laridae Avian Least Concern -

65 Gymnoris xanthocollis Chestnut-shouldered Bush-sparrow Passeridae Avian Least Concern -

66 Haliastur indus Brahminy Kite Accipitridae Avian Least Concern -

67 Hieraaetus pennatus Booted Eagle Accipitridae Avian Least Concern -

68 Lanius schach Long-tailed Shrike Laniidae Avian Least Concern -

Sr. No.

Scientific name Common name Family Faunal groupIUCN Status

Schedule (WPA 1972)

69 Larus canus Mew Gull / Common Gull Laridae Avian Least Concern -

70 Merops orientalis Green Bee-eater Meropidae Avian Least Concern -

71 Monticola solitarius Blue Rock-thrush Muscicapidae Avian Least Concern IV

72 Orthotomus sutorius Common Tailorbird Cisticolidae Avian Least Concern -

73 Phylloscopus trochiloides Greenish Warbler Phylloscopidae Avian Least Concern -

74 Prinia hodgsonii Grey-breasted Prinia Cisticolidae Avian Least Concern -

75 Copsychus fulicatus Indian Robin Muscicapidae Avian Least Concern IV

76 Ariadne merione Common Castor Nymphalidae Insecta - -

77 Blaberus giganteus forest cockroach Blaberidae Insecta - -

78 Caelifera Grasshopper -- Insecta - - 79 Castalius rosimon Common Pierrot Lycaenidae Insecta - - 80 Catochrysops strabo Forget-Me-Not Lycaenidae Insecta - - 81 Catopsilia pomona Lemon Emigrant Pieridae Insecta - - 82 Colotis amata Small Salmon Arab Pieridae Insecta - - 83 Crematogaster sp. Crematogaster ant Formicidae Insecta - - 84 Danaus genutia Striped Tiger Nymphalidae Insecta - - 85 Euchrysops cnejus Gram Blue Lycaenidae Insecta - II 86 Eurema hecabe Common Grass Yellow Pieridae Insecta - - 87 Symphaedra nais Baronet Nymphalidae Insecta - - 88 Parantica aglea Glassy Tiger Nymphalidae Insecta - - 89 Ischnura sp. Ischnura sp. damselfly Coenagrionidae Insecta - - 90 Jamides celeno Common Cerulean Lycaenidae Insecta - -

91 Junonia lemonias Lemon Pansy Nymphalidae Insecta - -

92 Junonia orithya Blue Pansy Nymphalidae Insecta - -

93 Lepisma saccharina Silverfish Lepismatidae Insecta - -

94 Leptosia nina Psyche Pieridae Insecta - -

Sr. No.

Scientific name Common name Family Faunal groupIUCN Status

Schedule (WPA 1972)

95 Oecophylla sp. Weaver ant Formicidae Insecta - -

96 Oniscidea sp. woodlouse Malacostraca Insecta - -

97 Orthetrum sabina Slender Skimmer / Green Marsh Hawk

Libellulidae Insecta Least Concern -

98 Papilio polytes Common Mormon Papilionidae Insecta - -

99 Pareronia valeria common wanderer Pieridae Insecta - -

100 Phalanta phalantha Common Leopard Nymphalidae Insecta - -

101 Xylocopa carpenter bee Apidae Insecta - -

102 spp2 Tree hopper Membracidae Insecta - -

103 Paguroidea sp. Hermit Crab species Coenobitidae Malacostraca - - 104 Ocypodinae sp. Ghost Crab Ocypodidae Malacostraca - - 105 Uca sp/ Feedler Crab Ocypodidae Malacostraca - - 106 Urva edwardsii Indian Gray Mongoose Herpestidae Mammalia Least Concern II 107 Semnopithecus hypoleucos Black-footed Gray Langur cercopithecidae Mammalia Least Concern II 108 Funambulus palmarum Three-striped Palm Squirrel Sciuridae Mammalia Least Concern - 109 Sus scrofa wild boar Suidae Mammalia Least Concern III 110 Vulpes bengalensis Indian Fox Canidae Mammalia Least Concern II 111 Lepus nigricollis Black-naped Hare Leporidae Mammalia Least Concern IV 112 Monilesaurus rouxii Forest Blood Sucker Agamidae Reptilia Least Concern - 113 Hemidactylus brookii Brook's Gecko Gekkonidae Reptilia Least Concern - 114 Eutropis carinata Keeled Indian Mabuya Scincidae Reptilia Least Concern -

Appendix 3.2 b Fauna diversity by quadrate sampling in buffer Sr. No.

Scientific name Faunal group Abundance Occurrence

1 Argiope anasuja Arachnida 1 1 2 Chilobrachys fimbriatus Arachnida 1 1 3 Cyrtophora Arachnida 1 1 4 Heterometrus longimanus Arachnida 1 1 5 Salticidae Arachnida 1 1 6 Scorpio hottentotta Arachnida 1 1 7 sp3 Arachnida 1 1 8 Castianeira longipalpa Arachnida 2 2 9 Hippasa partita Arachnida 15 6

10 Acridotheres tristis Avian 1 1 11 Aquila rapax Avian 1 1 12 Ardea alba Avian 1 1 13 Chroicocephalus brunnicephalus Avian 1 1 14 Cinnyris lotenius Avian 1 1 15 Circus aeruginosus Avian 1 1 16 Clanga hastata Avian 1 1 17 Dinopium benghalense Avian 1 1 18 Monticola solitarius Avian 1 1 19 Oriolus kundoo Avian 1 1 20 Pandion haliaetus Avian 1 1 21 Pernis ptilorhynchus Avian 1 1 22 Rhipidura albicollis Avian 1 1 23 Sialia sialis Avian 1 1 24 sp5 Avian 1 1 25 sp6 Avian 1 1 26 Actitis hypoleucos Avian 2 2 27 Centropus sinensis Avian 2 2 28 Cisticola juncidis Avian 2 1 29 Corvus splendens Avian 2 2 30 Cypsiurus balasiensis Avian 2 1 31 Dendrocitta vagabunda Avian 2 1 32 Eudynamys scolopaceus Avian 2 1 33 Ichthyaetus ichthyaetus Avian 2 1 34 Megalaima viridis Avian 2 1 35 Megalaima zeylanica Avian 2 2 36 Microcarbo niger Avian 2 2 37 Spilopelia senegalensis Avian 2 1 38 Accipiter badius Avian 3 3 39 Alcedo atthis Avian 3 3 40 Ardea intermedia Avian 3 1

Sr. No.

Scientific name Faunal group Abundance Occurrence

41 Caprimulgus atripennis Avian 3 1 42 Halcyon smyrnensis Avian 3 3 43 Lanius schach Avian 3 3 44 Orthotomus sutorius Avian 3 1 45 Psittacula krameri Avian 3 1 46 Tringa stagnatilis Avian 3 1 47 Corvus culminatus Avian 4 2 48 Corvus macrorhynchos Avian 4 4 49 Hypothymis azurea Avian 4 1 50 Pavo cristatus Avian 4 1 51 Petronia xanthocollis Avian 4 1 52 Threskiornis melanocephalus Avian 4 2 53 Bubulcus ibis Avian 5 3 54 Charadrius alexandrinus Avian 5 2 55 Cinnyris asiaticus Avian 5 3 56 Egretta gularis Avian 5 2 57 Hieraaetus pennatus Avian 5 3 58 Phylloscopus trochiloides Avian 5 3 59 Spilopelia chinensis Avian 5 5 60 Turdoides striata Avian 6 2 61 Columba livia Avian 7 2 62 Tringa totanus Avian 7 1 63 Larus canus Avian 8 4 64 Saxicoloides fulicatus Avian 8 4 65 Pericrocotus cinnamomeus Avian 9 2 66 Cecropis daurica Avian 10 2 67 Prinia hodgsonii Avian 10 4 68 Pycnonotus cafer Avian 10 3 69 Passer domesticus Avian 11 1 70 Dicrurus macrocercus Avian 14 7 71 Haliastur Indus Avian 14 5 72 gelochelidon nilotica Avian 15 3 73 Ardeola Avian 17 5 74 Treron phoenicoptera Avian 21 2 75 Leptocoma zeylonica Avian 25 5 76 Acrocephalus dumetorum Avian 28 11 77 Egretta garzetta Avian 39 4 78 Merops orientalis Avian 39 7 79 Pycnonotus jocosus Avian 47 6 80 Scolopendra polymorpha Chilopoda 1 1 81 Scutigera coleoptrata Chilopoda 1 1

Sr. No.

Scientific name Faunal group Abundance Occurrence

82 Abisara echerius Insecta 1 1 83 Blaberus giganteus Insecta 1 1 84 C. corticicola Insecta 1 1 85 Caelifera Insecta 1 1 86 Catochrysops strabo Insecta 1 1 87 Crematogaster corticicola Insecta 1 1 88 Euthalia nais Insecta 1 1 89 Ideopsis similis Insecta 1 1 90 Ischnura sp. Insecta 1 1 91 Junonia orithyaq Insecta 1 1 92 Neptis hylas Insecta 1 1 93 Orthetrum sabina Insecta 1 1 94 Pareronia valeria Insecta 1 1 95 Phalanta phalantha Insecta 1 1 96 sp4 Insecta 1 1 97 Xylocopa Insecta 1 1 98 Ariadne merione Insecta 2 1 99 Atrophaneura hector Insecta 2 2

100 Danaus genutia Insecta 2 2 101 Euchrysops cnejus Insecta 2 2 102 Junonia lemonias Insecta 2 2 103 Oecophylla Insecta 2 2 104 sp1 Insecta 2 2 105 Jamides celeno Insecta 4 3 106 Spindasis vulcanus Insecta 4 3 107 Castalius rosimon Insecta 5 4 108 Catopsilia pomona Insecta 5 5 109 Delias eucharis Insecta 5 4 110 Oniscidea Insecta 6 1 111 Papilio polytes Insecta 6 4 112 Eurema hecabe Insecta 9 3 113 Leptosia nina Insecta 10 4 114 Lepisma saccharina Insecta 12 5 115 Colotis amata Insecta 15 3 116 Euploea core Insecta 19 4 117 Paguroidea Malacostraca 1 1 118 Ocypodinae Malacostraca 2 2 119 Funambulus palmarum Mammalia 1 1 120 Sus scrofa Mammalia 1 1 121 Vulpes bengalensis Mammalia 1 1 122 sp2 (Hare) Mammalia 2 2

Sr. No.

Scientific name Faunal group Abundance Occurrence

123 Urva edwardsii Mammalia 3 2 124 Semnopithecus hypoleucos Mammalia 4 2 125 Hemidactylus brookii Reptilia 2 2 126 Calotes Reptilia 4 4 127 Mabuya carinata Reptilia 14 5

Appendix 4.a Marine diversity in Core

Sr. No. Marine faunal group Species group 1 Zooplankton Gastropod larva 2 Zooplankton Bivalve larva 3 Zooplankton Copepoda 4 Zooplankton Fish larvae 5 Zooplankton Amphipoda 6 Zooplankton Polychaeta larvae 7 Zooplankton Decapoda larvae 8 Zooplankton Chaetognatha 9 Zooplankton Lucifers

10 Zooplankton Foraminifera 11 Phytoplankton Asterionella sp. 12 Phytoplankton Thalassiothrix sp 13 Phytoplankton Streptotheca sp 14 Phytoplankton Navicula sp 15 Phytoplankton Coscinodiscuss sp 16 Phytoplankton Skeletonema sp 17 Phytoplankton Thalassiosira sp 18 Phytoplankton cyclotella sp 19 Phytoplankton Odontella sp 20 Phytoplankton Rhizosolenia sp 21 Phytoplankton Leptocylindrus sp 22 Benthos Brachyuran sp 23 Benthos Nereis sp 24 Benthos Syllis sp 25 Benthos Notomastus sp 26 Benthos Gafrarium 27 Benthos Oysrer spat 28 Benthos Planaxis sp 29 Benthos Caprella sp 30 Benthos Corophium sp 31 Benthos Hydrozoa 32 Benthos Anomura 33 Benthos Megalona sp

Sr. No. Marine faunal group Species group 34 Benthos Donax sp 35 Brachymura Charybdis sp 36 Brachymura Grapus sp 1 37 Brachymura Grapus sp 2 38 Brachymura Ocypode 39 Anomura Uca sp. 40 Anomura Diogenes sp

Appendix 4.b Marine diversity in buffer

Sr. No. Marine faunal group Species group 1 Zooplankton Copepoda 2 Zooplankton Amphipoda 3 Zooplankton Polychaeta larvae 4 Zooplankton Decapoda larvae

5 Zooplankton Chaetognatha 6 Zooplankton Gastropod larva 7 Zooplankton Fish larvae 8 Zooplankton Foraminifera 9 Zooplankton Nauplius larva

10 Zooplankton Cladocera 11 Zooplankton Hydromedusa 12 Zooplankton Medusa 13 Zooplankton Lammalibranch 14 Zooplankton Cephalopoda larvae 15 Zooplankton Salpidae 16 Zooplankton heteropoda 17 Zooplankton Invertebrate larva 18 Zooplankton brachiopooda larva 19 Zooplankton Ctenophora 20 Zooplankton isopoda 21 Phytoplankton Asterionella sp. 22 Phytoplankton Thalassiothrix sp 23 Phytoplankton Streptotheca sp 24 Phytoplankton Navicula sp 25 Phytoplankton Coscinodiscuss sp 26 Phytoplankton Skeletonema sp 27 Phytoplankton Thalassiosira sp 28 Phytoplankton cyclotella sp 29 Phytoplankton Odontella sp 30 Phytoplankton Rhizosolenia sp 31 Phytoplankton Leptocylindrus sp 32 Phytoplankton Guinardia sp

Sr. No. Marine faunal group Species group 33 Phytoplankton Ditylum sp 34 Phytoplankton Dictyocha sp 35 Phytoplankton Melosira sp 36 Phytoplankton Triceratium sp 37 Phytoplankton Asteromphalus sp 38 Phytoplankton Pleurosigma sp 39 Phytoplankton Gyrosigma sp 40 Phytoplankton Trichodesmium sp 41 Phytoplankton Thalassionem sp 42 Phytoplankton Nitzschia sp 43 Phytoplankton Grammatophora sp 44 Phytoplankton Chaetoceros sp 45 Phytoplankton Ceratium furca 46 Phytoplankton Ceratium tripos 47 Phytoplankton Pyrophacus sp 48 Phytoplankton Phaeodactylum sp 49 Phytoplankton Climacodium sp 50 Phytoplankton Planktoneilla sp 51 Phytoplankton Peridinium sp 52 Phytoplankton Surirella sp 53 Phytoplankton Dytilum sp 54 Phytoplankton Clostidium sp 55 Phytoplankton Actinoptychus sp 56 Benthos Anomura 57 Benthos Capitellidae sp 58 Benthos Caprella sp 59 Benthos Cardita sp 60 Benthos Cumacea 61 Benthos Cyathura 62 Benthos Donax sp 63 Benthos Gafrarium 64 Benthos Hydrozoa 65 Benthos Katelysia 66 Benthos Marginella sp 67 Benthos Megalona sp 68 Benthos Murucidea sp 69 Benthos Nassaria sp 70 Benthos Nereis sp 71 Benthos Oligochaeta 72 Benthos Olivia sp 73 Benthos Oysrer spat 74 Benthos Paphia sp

Sr. No. Marine faunal group Species group 75 Benthos Planaxis sp 76 Brachymura Scylla serrata 77 Brachymura Charybdis sp 78 Brachymura Grapus sp 1 79 Brachymura Grapus sp 2 80 Brachymura Ocypode 81 Anomura Uca sp. 82 Anomura Diogenes sp

Appendix 4.c Marine diversity based on market and random survey Sr. No Family Scientific Name Common Name Type

1 Clupidae Sardinella longiceps Indian oil sardine Fish 2 Engraulidae Coilia dussumieri Golden ancovy Fish 3 Stromateidae Parastromateus niger Black pomfret Fish 4 Scombridae scomberomorus guttatus Surmai Fish 5 Scombridae scomberomorus commerson surmai Fish 6 Nemipteridae Arius dussumeri cat fish Fish 7 Synodontidae harpadon nehereus Bombay duck Fish 8 Cynoglossidae Cynoglossus arel Ghost crab Fish 9 Sciaenidae johnius dussumieri Dhoma Fish

10 Scatophagidae Scatophagus argus Spotted scat Fish 11 Carcharhinidae Scoliodon sp Dog fish Fish 12 Teripontidae terapon theraps perch Fish 13 Penaeidae Penaeus monodon - Prawn 14 Penaeidae Penaeus indicus - Prawn 15 Penaeidae Penaeus japonicus - Prawn 16 Penaeidae Metapenaeus monoceros - Prawn 17 Palinuridae Panulirus sp - Prawn 18 Portunidae Scylla serrata - Crab 19 Portunidae Portunus sanguinolentus - Crab 20 Brachyura Charybdis sp - Crab 21 Brachyura Grapus sp 1 - Crab 22 Brachyura Grapus sp 2 - Crab 23 Brachyura Ocypode Ghost crab Crab 24 Anomura Uca sp. Fiddler crab Crab 25 Anomura Diogenes sp Hermit crab Crab

Sr. No Family Scientific Name Common Name Type 26 Anomura Calcinus sp Hermit crab Crab 27 Trochidae Trochus chloromphalus A.Adams, 1853 - Gastropod 28 Trochidae Trochus radiatus Gmelin, 1791 - Gastropod 29 Trochidae Umbonium vestiarium Linnaeus, 1758 - Gastropod 30 Neritidae Nerita oryzarum Recluz, 1841 - Gastropod 31 Neritidae Nerita violacea Gmelin,1791 - Gastropod 32 Neritidae Nerita litterata Gmelin, 1791 - Gastropod 33 Littorinidae Littoraria intermediate Philippi, 1846 - Gastropod 34 Littorinidae Littoraria undulata Gray, 1839 - Gastropod 35 Potamididae Cerithidropsilla cingulata Gmelin,1791 - Gastropod 36 Naticidae Natica maculosa Lamarck, 1822 - Gastropod 37 Turridae Paradrillia patruelis E.A.Smith, 1875 - Gastropod 38 Buccinidae Pollia rubiginosa Reeve, 1846 - Gastropod 39 Babylonidae Babylonia spirata Linnaeus, 1758 - Gastropod 40 pyrinidae Euplica scripta Lamarck, 1822 - Gastropod 41 Scaphandridae Eocylichna protracta A.A.Gould ,1859 - Gastropod 42 olividae Oliva oliva Linnaeus, 1758 - Gastropod 43 Terebridridae Granuliterebra bathyrhaphe - Gastropod

11.0 Photo Feature

Figure 27 : Core Site (Stunted mangroves 300 – 500 m from proposed development)

Figure 28 : Team working in field

Figure 29: Ixora coccinea

Figure 30 : Eranthemum roseum (Vahl) R.Br.

Figure 31: Abrus precatorius L.

Figure 32: Plumbago Zyelanica L.

Figure 33: Convolus Sps.

Figure 34: Barleria Pretoriensis C.B. Clark

Figure 35: Brahminy Kite

Figure 36: Black-footed Gray Langur

Figure 37: House Centipede

Figure 38: Common Kingfisher

Figure 39: Osprey

Figure 40: Garden Lizard

Figure 41: Ghost Crab

Figure 42: Small Salmon A

 

 

 

 

 

Annexure 4 

Compliance for 49th EAC Meeting

 

 

 

 

 

 

i. Upload  copy  of  updated  EIA/EMP 

Report  along  with  point‐wise  ToR 

Compliance and Annexures. 

EIA/EMP  is  updated  as  per  standard ToR  and  Awarded  ToR.  Point  wise compliance  of  standard  ToR  and Awarded  is given  in Chapter 1 of EIA report.

      

ii. Upload  copy  of  CZMA 

recommendations  given  by 

Maharashtra CZMA 

I~

3. ·1 he proposal was deliberated in l l 6111 meeting of the MCLMA wherein 22"J March, 2017 wherein the Authority decided to, isit the site. Accordingly. site visit "as conducted on

a) The proposal is for 1) direct berthing deep water jetty facility on Kundalika River. village Korlai and 2) capacity enhancement at existing Inland Water Jett) Facility on Kundalika River at Village anegaon. 1 al. i\turud, Dist. Raigad.

b) The jell) facility is proposed on the Jell bank of the Kundalika River. in the Lee of the Korlai head. which will provide the necessary tranquil condition for the jetty operations.

c) I he Jett} is about 525 m long with one 8m x 8 m mooring dolphin on the East. d) The project will involve dredging up to a 14.5 km ling channel requiring I I million

cum of dredging for a depth of 11.0 m CD in phase I for l land) max vessels. Tn second phase channel length would increase to I 7.5km involving 23millon cum of dredging for a channel depth of 14.6m CD for Panamax vessels. In the final phase the channel length would increase to 2 I .5km and would require 35.2 million cum dredging for a channel depth of 19.0m CD for capsized , cssels. The dredging of the inner channel in the river for facilitating movement of 4500 D\\ T barges would involve 0.99 Mm3 for a depth of 3.1 m to CD.

c) As per the CRZ map prepared by NCSCM in I: 4000 scales. the project is proposed in CRZ I (8). CRZ Ill. CRL IV area.

I) I he PP has submitted the Rapid £:.IA/EMP for the project.

" Ihc Authority noted the detail as follows:

The proposal regarding proposed direct berthing deep , .. ater jetty facility on Kundalika River. village Korlai and capacity enhancement at existing Inland Water Jetty Facility on Kundalika River at Village anegaon. I al. Murud. Dist. Raigad b) Mis lndo Energy International Limited was considered in I l61h & 121'' meeting of Maharashtra Coastal Zone Management Authority (MC7.MA) held on 22"d to 23rd March.2017 and I 51h to I 61h September 2017 respectively.

Proposed direct berthing deep water jetty facility on Kundalika River. , illage Korlai and capacity enhancement at existing Inland Water Jett) lacility on Kundalika River at Village Sanegaon, Tal. Murud. Dist Raigad b) ~1 s lndo Inergy International Limited.

ubject:

To. Director (IA-Ill). Coastal Zone Regulation. Government of India. Ministry of Lnv ironmcnt. l-oresrs & Climate Change. lndira Paryavaran Bhavan. Jor Bagh Road. New Delhi - 1 IO 003

'-lo. CRl- 2011/ CR-4 TC 4 Office of the - vtaharashtra Coastal Lone Management Authority, Lnv ironment Department, I S'h floor, l\c,, Administrative Building, Mantralaya. Mumbai- 400 032. Date: 09'11 January, 2018

Tel 1'.Jo .. 22873844 E-mail : dirl.1neHnh<a'nic in \\ ebsite· https: mczma.mahar3!>htra.go\ .in/

\IAHARA~llTRA COASTAL ZO 'E MANAGEME T Al'THORITY

2

General Conditions: 1. The MCZMA reserves the right to revoke this recommendation. if the conditions

stipulated are not complied with to the satisfaction of the MCZMA or Environment Department.

11. The MCZMA or any other competent authority may stipulate any additional conditions subsequently. if deemed necessary. for environmental protection. which shall be complied with.

Specific conditions: 1. Proposed project should be as per the provisions of CRZ Notification.2011 (amended

from time to time) 11. All other required permission from different statutory authorities should be obtained.

5. After deliberation. the Authority decided lo recommend the proposal of direct berthing deep water jetty facility to MoEF. New Delhi subject to observations as stated above. I Iowever. the proposal for Expansion of the Sancgoan jetty at village Sanegoan is not recommended at present for the observations and compliance as staled above.

4. During the meeting, the Authority observed the followings: a) There will be change in hydrodynamic of the flow of the Revdanda creek due lo the

proposed construction of port and reclamation of 50 Ha area for stoppage of goods. b) PP needs to make a detailed plan for traffic management for carry ing cargoes.

considering the availability of narrow road adjacent to proposed port. The PP to develop detail traffic now management plan.

c) PP to redesign and construct. develop and monitor the existing roads proposed to be utilised for heavy cargo movement. considering its frequency.

d) PP lo ensure livelihood of local fisherman is not impacted due to proposed port and also develop alternate livelihood means under the project.

c) PP to submit the compliance of the Environment Clearance granted to Sanegoan jetty. Expansion of the Sancgoan jetty ma) not be permissible at present without compliance of the issues raised by committee of the Maharashtra Legislative Assembly in July. 2017.

a) The proponents should explore and submit the alternative plans/proposal for the proposed jetty facility those have minimal reclamation and alteration of local geomorphology.

b) There is involvement of a significant alteration of local geomorphology. reclamation of over 50 ha area. drastic change in the tidal water inflow and its distribution at the river mouth, extension of project actix ity right in the water channel.

c) The proponents have explained the need of having merry go round model of a railway line for convenient operation which was not mentioned in the EIA report the CRL map submitted and even the presentation made by the agency during 1 I 61h meeting of MCZMA.

d) Anticipating the scale of this proposal and its impact on the local inhabitants and resources, their perceptions about this development and its impact on to their livelihood has to be respected and counted in the studies.

I 6th July. 2017 by the Dr. Mahesh Sindikar. Expert Member. MCZMA with other officials. Mr. Pinto, VC from Mis Jndo Energy International Ltd and consultants for the project Captain Rohila. and Mr. Ajinkya were present for the site visit. The Authority look on record the site visit report of the expert member of the MCZMA.

3

Copy for information to: 1. Additional Chief Secretary, Environment & Chairman. MCZMA. Environment

Dept. Room No. 217, Annexe Building. Mantralaya. Mumbai. 2. Member ecretary, Maharashtra Pollution Control Board. KaJpataru Point. 3rd and

4th floor. Opp. CincMax Theatre. Sion (E). Mumbai-400 022 ~-~istrict Collector, Raigad

/- ~s. India Energy International Ltd, 609-610, Vindhya Commercial Complex. Sector-I 1. CBD Belapur. Navi Mumbai

5. Select File- TC 4

Dire . Em ironment & Member Secretary, MCZMA

6. The agenda item. minutes and the copy of this recommendation on the website of MCZMA i.e. http://mczma.maharashtra.gov.in.

111. A copy of the recommendation letter shall be marked to the concerned local body/ local NGO, if any. from whom any suggestion/ representation has been received while processing the proposal.

rv, The environmental safeguard measures should be implemented in letter and spirit. v. This recommendation will be valid for 5 years from the date of issue of

recommendation for commencement of construction & operation. No construction should be initiated till final permission from MoEF is obtained to the project.

vi. The recommendation from CRZ point of view is being issued without prejudice to the action initiated under EP Act or any court case pending in the court of law and it does not mean that project proponent has not violated an) environmental laws in the past and whatever decision under EP Act or of the Hon'blc court will be binding on the project proponent. I lence this recommendation does not give immunity to the project proponent in the case filed against him. if an) or action initiated under EP Act.

 

 

 

 

 

 

iii. Certificate  from  Chief  Wild  Life 

Warden regarding permissibility and 

distance of the project from Phansad 

Wildlife Sanctuary. 

 

 

 

 

 

 

iv. Certificate  from  Archaeological 

Survey  of  India  regarding 

permissibility  and  distance  of  the 

project from Korlai Fort. 

 

 

 

 

 

 

v. Impacts  of  the  proposed  project  on 

crocodiles  present  in  the  upstream 

of the Kundalika estuary. 

Impact Mitigation plan for Crocodiles in the Project area

Mugger Crocodile also known as the Mugger or Marsh Crocodile (Crocodylus palustris) is a medium-sized crocodile having broadest snout among the living members of the genus Crocodylus. It is a species restricted to Indian sub-continent, and habits river, lakes and marshes. Adaptation of this species to big reservoirs, irrigation canals, and man-made ponds have been recorded in India, Pakistan, Sri Lanka and Iran. In few cases, its also have been found inhabiting coastal saltwater lagoons and estuaries. Crocodiles being reptiles having no homeostasis, are known to bask in the heat of the sunlight (Da Silva, 2010).

This species is protected under schedule I of the Wildlife (Protection) Act, 1972 of India. In terms of International conservation status, it is also categorized as “Vulnerable” species by International Union for The Conservation of Nature and Natural Resources (IUCN). These factors make it crucial for understanding the presence of the animal in the project area.

Mugger is a hole nesting species, with egg-laying taking place during the annual dry season. After attaining maturity, female lays eggs from 25-30 in number. Incubation period for these

eggs on an average is about couple of months (Da Silva, 2010).

Muggers are known to dig burrows, which provides protection to them and their eggs as well. Muggers take refuge in these burrows during hot day time as well. And critical role is played by such burrows in survival of crocodiles as burrows allow crocodiles to avoid exposure to excessively low or high temperatures (Da Silva, 2010).

Figure 1: Representative image of a crocodile from Kokan region

Principal threats to mugger identified were habitat destruction and fragmentation, drowning in fishing nets, egg predation by humans, etc. (Da Silva, 2010)

Understanding the presence of an animal

1. In order to learn about current status of the mugger population, a detailed species-specific survey shall be carried out.

2. As a part of the assessment, nesting sites and regularly used basking sites should be identified, monitored and mapped.

3. Survey should be conducted in the entire river stretch of the project area and also presence of the animal should be checked couple of kilometres outside the study area to estimate probability of the animal coming in the project area.

4. Socio-ecological surveys involving interviews with locals should be conducted for estimating current and past sightings of the animals.

Assuming the presence of Mugger in the project area, following impacts and mitigations have been drafted

Impacts during construction phase:

1. Dumping of construction material can disturb the animal or its nesting habitat or both

2. Noise and vibration can startle the animal and can make it leave the area / habitat.

3. Increased turbidity might make animal to leave the area

4. Construction workers knowingly or unknowingly creating man-animal conflict situations.

5. Waste released by construction worker can damage the habitat of not just crocodile but also of other animals and plants.

Impact during operational phase:

1. Accidents with vessels can result in injuries or fatalities to the animal

2. Vessel operation if not maintained properly are prone to oil and fuel spillage. Such accidents can damage animal life.

3. Vessel operation might damage / disturb the nesting habitats of the animal.

4. Wastage released from vessel and operational activities can damage the wildlife significantly.

Mitigation plan during construction phase:

5. Covering of construction material during transport and storage in order to avoid spillage of the material and prevent disturbance to the animal and nesting site of the animal.

6. Animal movement due to noise and vibration can be temporary and this impact is reversible type as animal can return to the nesting site once the disturbance stops.

7. Noise barriers and efficient construction equipment shall be used to in order to reduce the impact from noise and vibration.

8. Increased turbidity does disturb the animal, but muggers have been known to inhabit such turbid waters. Also, one the disturbance causing turbidity stops, animal can return to its habitat.

9. In order to learn about current status of the mugger population, a detailed species-specific survey shall be carried out. To reduce man-animal conflict such surveys can help manage safe operating protocols or guidelines around the area of operation and construction.

10. Locals should be made aware about the animal in case its presence is detected from the survey.

11. Regular monitoring for animal activity is advised to understand its movement in the project area clearly.

12. Proper waste management plan shall be prepared and shall be monitored for implementation. Regular assessments of its implementation shall be done.

Mitigation during operational phase

13. Vessel operators shall be sensitized towards safety of such faunal elements while operating their vessels in the water.

14. During operation care should be taken that no amount of oil or any fuel or chemical spillage shall occur at site of operation.

15. In case of sightings of animal, vessel operator or team shall be to document it regularly and keep a database on the same.

16. Corrective measures for operation of the vessels shall be taken with the help of data collected regularly.

17. Identified mugger burrows should be prevented from grazers to prevent mugger as well as to prevent man-animal conflict in the area.

18. Proper waste management plan shall be prepared and shall be monitored for implementation. Regular assessments of its implementation shall be done.

19. Capacity building and awareness generation shall be done for local communities with respect to the presence of mugger, and dos and don’ts.

References

Da Silva, A. a. (2010). Mugger Crocodile Crocodylus palustris. Crocodiles. Status Survey and

Conservation Action .

 

 

 

 

 

 

vi. A  study  on  impacts  of  accidental 

spillage  due  to  ship  grounding  or 

collision  through  model  and  its 

mitigation. 

Spill Modelling for the Development of the Direct Berthing Deepwater Jetty inside the Revadanda Creek and Inland Water Facility at Sanegaon, Raigarh, Maharashtra

Final Report

July 2020

This report has been prepared under the DHI Business Management System certified by BVC to comply with ISO 9001 (Quality Management), ISO 14001 (Environmental

Management), OHSAS 18001 (Health and Safety Management)

Approved by Dr. Tirumaleswara Reddy Technical Director

DHI (India) Water & Environment Pvt Ltd•Unit No. 612, Sixth Floor, DLF Prime Tower• Plot No. F-79-80 Okhla Phase-1• IN-11 00 20 New Delhi• India Telephone: +91 11 4704 6256 • www.dhigroup.com

Spill Modelling for the Development of the Direct Berthing Deepwater Jetty inside the Revadanda Creek and Inland Water Facility at Sanegaon, Raigarh, Maharashtra

Final Report

July 2020

Prepared for Indo Energy International Ltd.

and their consultants C-Borne Services LLP Represented by Capt. R.K. Karnal (IEIL)

Report authors Mr. Jinesh Kumar

Quality assurance Dr. N T Reddy

Project number 63801014

Approval date 18th July 2020

Revision B

Classification Confidential © DHI. All rights reserved. No parts of this document may be reproduced, transmitted or otherwise disseminated in any form or by any means outside the recipient’s organisation without the prior written permission of DHI.

i

CONTENTS

1 Introduction ............................................................................................. 1 1.1 DHI Project ............................................................................................................... 1 1.2 Background .............................................................................................................. 1 1.3 Scope of Work ......................................................................................................... 1

2 Site Conditions ........................................................................................ 2 2.1 General .................................................................................................................... 2 2.2 Shoreline Environment ............................................................................................. 2 2.3 Tides ........................................................................................................................ 4 2.4 Wind ......................................................................................................................... 4 2.5 Wave Climate - Offshore .......................................................................................... 4

3 Hydrodynamic Modelling ........................................................................ 5 3.1 Bathymetry ............................................................................................................... 5 3.2 Boundary Conditions ................................................................................................ 6 3.3 Bed Resistance ........................................................................................................ 7 3.4 Production Period .................................................................................................... 7 3.5 Model Calibration and Validation ............................................................................. 7 3.6 Model Results .......................................................................................................... 9

4 Oil Spill Modelling ................................................................................. 10 4.1 Overview ................................................................................................................ 10 4.2 Oil Spill Processes ................................................................................................. 10 4.3 Oil spill Process and Properties ............................................................................. 11 4.4 Oil Properties ......................................................................................................... 12 4.5 Environmental Data ............................................................................................... 12 4.5.1 Currents ................................................................................................................. 12 4.5.2 Wind Data .............................................................................................................. 13 4.5.3 Oceanographic Data .............................................................................................. 13 4.6 Spill Scenarios ....................................................................................................... 13 4.7 Oil Spill Modelling Results ..................................................................................... 14 4.7.1 Scenario-1 (Berthing Area Spill) ............................................................................ 14 4.7.2 Scenario-2 (Turning Circle) .................................................................................... 16 4.7.3 Scenario-3 (Anchorage Area Spill) ........................................................................ 18 4.8 Oil Spill Management Strategy .............................................................................. 20

5 Bulk Solid Cargo Spillage ..................................................................... 20

6 Conclusions ........................................................................................... 21

ii

LIST OF FIGURES Figure 1-1 Location of present unloading facility at Sanegaon on the West Coast of India ..... 1 Figure 2-1 Location of Proposed facility off the mouth of Kundalika River ............................... 2 Figure 2-2 Local Bathymetry showing very near to the study area ........................................... 3 Figure 2-3 Local Bathymetry showing very near to the prosed facility and existing JSW jetty. 3 Figure 3-1 Water depth points with tidal stations (source: C-map) ........................................... 6 Figure 3-2 Zoom in figure of bathymetry snapshot showing the location of the proposed

facility ....................................................................................................................... 6 Figure 3-3 Comparison of measured and simulated water level at third pillar of Revdanda

Bridge ....................................................................................................................... 8 Figure 3-4 Comparison of measured and simulated current speed at location CM1 ................ 8 Figure 3-5 Comparison of measured and simulated current speed at location CM2 ................ 8 Figure 3-6 Comparison of measured and simulated current speed at location CM3 ................ 8 Figure 3-7 Very close snapshot of current pattern during peak flood tide and NE monsoon

with existing condition .............................................................................................. 9 Figure 3-8 Very close snapshot of current pattern during the ebb tide and NE monsoon with

existing condition ..................................................................................................... 9 Figure 4-1 Processes acting on spilled oil .................................................................................. 10 Figure 4-2 A schematic representation of the fate of a crude oil showing changes in the relative

importance of weathering processes with time ...................................................... 11 Figure 4-3 Spill locations ............................................................................................................ 14 Figure 4-4 Maximum thickness during SW monsoon for simulation between 04 July 2015 to 19

July 2015 ................................................................................................................ 15 Figure 4-5 Maximum thickness during NE monsoon for simulation between 26 October 2015 to

11 November 2015. ............................................................................................... 15 Figure 4-6 Maximum thickness during SW monsoon for simulation between 04 July 2015 to 19

July 2015 ................................................................................................................ 17 Figure 4-7 Maximum thickness during NE monsoon for simulation between 26 October 2015 to

11 November 2015. ............................................................................................... 17 Figure 4-8 Maximum thickness during SW monsoon for simulation between 04 July 2015 to 19

July 2015 ................................................................................................................ 19 Figure 4-9 Maximum thickness during NE monsoon for simulation between 26 October 2015 to

11 November 2015 ................................................................................................ 19

LIST OF TABLES Table 2-1 Tidal Levels in m at Revdanda................................................................................. 4 Table 4-1 Oil fractions ............................................................................................................ 12 Table 4-2 Spill parameter for scenarios 1-3 ........................................................................... 13

1

1 Introduction

1.1 DHI Project

M/s C-Borne Services LLP, Navi Mumbai has engaged DHI (India) Water & Environment Pvt Ltd. to carry out the oil spill and bulk solid cargo spill modelling for development of the direct berthing deep-water Jetty inside Revadanda Creek at the confluence of the Kundalika River with sea and the Sanegaon facility. DHI (India) is submitting this modelling report according to the Scope of Work given below.

1.2 Background

C-Borne Services LLP was appointed by Indo Energy International Ltd. (IEIL) as a consulting firm to conduct various studies for development of the direct berthing deep-water Jetty inside Revadanda Creek at the confluence of the Kundalika River with sea and the Sanegaon facility.

Indo-Energy Limited (IEIL), is presently engaged in transportation and trading of Coal using lighterage facility at Sanegaon, located on the Right Bank of the Kundalika River, about 50 km south of Mumbai as shown in Figure 1-1 below.

Figure 1-1 Location of present unloading facility at Sanegaon on the West Coast of India

1.3 Scope of Work

The scope of the work is to conduct oil spill modelling and bulk solid cargo spill assessment required to support the proposed expansion of the existing as well as the new facility inside the creek.

2

2 Site Conditions

2.1 General

The proposed Revdanda facility is located between geographical co‐ordinates of latitude 18° 32' 9.66"N, longitude 72°54' 54.88"E and latitude 18° 32' 11.82"N, longitude 72° 55' 11.71"E, on the left bank of the Kundalika River, North East of Rat Island (Figure 2-1).

The Revadanda creek formed by the confluence of the Kundalika River and the Arabian Sea is protected naturally from the predominant SW waves by the Korlai headland.

East of the proposed facility there is an existing JSW jetty which is a 235 m concrete block gravity wall Jetty with end radius at both ends of 7.5 m. JSW jetty has mooring dolphins which lie 21 m to the east, thereby increasing the total length of the jetty to 256 m. This Jetty is L shaped and both the faces of jetty are used for berthing of vessels. The north face accommodates two (2) unloading berths and one (1) loading berth. The Southern face of jetty is used for mooring of barges awaiting discharge, barges undergoing repairs and idle barges.

At the confluence of Kundalika River with sea, a shallow sandbar has been formed and depth over sandbar is only 0.5 to 1.5 m. In view of the limited depth, the port is used as lighterage port. Coal is transhipped in the self-propelled RSV II/IV barges of capacity 2500 ‐ 2800 DWT from mother vessel at anchorage. A 100 m wide, 7 nautical miles long entrance channel leads from anchorage point to JSW jetty for safe navigation of barges.

A bridge exists on Kundalika River about 400 m east of existing JSW jetty.

Figure 2-1 Location of Proposed facility off the mouth of Kundalika River

2.2 Shoreline Environment

The bathymetry map extracted from DHI’s in-house tool C-map for Site location is shown in Figure 2-2 and Figure 2-3. The bathymetry map indicates 10 m contour reaching within approx. 20 km from the mouth of the creek and shows offshore currents having a magnitude of approx. 0.5 knots.

The depths in the creek near the proposed port facility along the navigation channel vary from ‐3 m CD to ‐5 m CD.

3

The water depth in and around the existing JSW Revdanda jetty are of the order of ‐5 m CD. However, in the fairway the depths range from -3 m CD to ‐5 m CD.

There are sandy shoals and pockets of shallower depths at the creek entrance and the depths reduce to about ‐0.5 m CD to ‐1 m CD.

Figure 2-2 Local Bathymetry showing very near to the study area

Figure 2-3 Local Bathymetry showing very near to the prosed facility and existing JSW jetty.

4

2.3 Tides

The Naval Hydrographical Chart No 211 gives information on the tide and tidal levels and is reproduced in Table 2-1. The spring and neap tidal ranges are 2.6 m and 1.6 m respectively.

Table 2-1 Tidal Levels in m at Revdanda

MHWS 3.6

MHWN 3.3

MSL 2.4

MLWN 1.7

MLWS 1.0

Generally in the narrow estuarine areas, spatial variation of tide is likely to be prominent and the area like Kundalika River is not an exception and there is significant variation in high water levels as one moves upstream compared to open area water levels. This results in increased tidal current upstream of river.

2.4 Wind

During the months of June, July and August, the wind direction is SW-WSW. For rest of the months, predominant wind direction is NNE-N-NNW in the area. The wind speed is less than 10 m/s for 95% of the time.

2.5 Wave Climate - Offshore

It may be seen that the predominant directions of waves in the deep sea are from SW. It can also be seen that waves are less than 2 m, 4 m, and 5 m in height for 76%, 97.0% and 99.8% of the time respectively.

5

3 Hydrodynamic Modelling

Hydrodynamic modelling is carried out using DHI’s MIKE21 FM (Flexible Mesh) HD model. The model simulates 2D free-surface flows, solving the depth averaged Navier-Stokes equations and is applicable to the simulation of hydrodynamic processes in lakes, estuaries, bays, coastal areas and seas. The FM module of MIKE 21 is based on Flexible Mesh approach using triangular and quadrangular elements for addressing geometrical flexibility to complex coastlines, like archipelago, lagoons, estuaries etc.

The hydrodynamic model simulates water level variations and flows in response to a variety of forcing functions. The effects and facilities in the HD include:

• Bottom shear stress • Wind shear stress • Barometric pressure gradients • Coriolis force • Momentum dispersion • Sources and Sinks • Evaporation • Flooding and Drying • Wave radiation stress

MIKE 21 FM can be applied to a wide range of hydraulic and related phenomena including modelling of tidal hydraulics, wind and wave generated currents, storm surges. The main governing conditions which affect the performance of the hydrodynamic model are:

• Bathymetry • Boundary conditions (wind and water level on open boundaries) • Bottom resistance • Eddy viscosity

3.1 Bathymetry

Existing bathymetry of the region is prepared based on MIKE – CMAP supplemented with at site-specific data provided by the client near the proposed study area. C-Map is a global digitised chart, which includes the water depth contours and water surface elevation data (tidal stations) for the entire globe. The C-Map depth points can be seen in Figure 3-1, which were imported on to the MIKE 21 suite, for setting up the bathymetry.

The mesh ranges from fine resolution near-shore of 50m to 2,700m offshore and a very fine resolution (10 m) inside the creek, along the channel, entrance of the creek and proposed facility.

The proposed facility layouts are introduced in the existing bathymetry, where navigational channel (180 m width) is deepened to -14.5 m and the turning circle of diameter 500 m to -15.5 m depth. The berth pocket in front of the jetty is maintained at the same depth of -5.5m. The depths behind the main berth and at the barge berth were maintained at -12 m and -6 m respectively. The depth on the eastern part of the jetty for the Port crafts are in the range of (-3) to (-5) m. Model Bathymetry of the domain after including the proposed facility layout is given in Figure 3-2.

6

Figure 3-1 Water depth points with tidal stations (source: C-map)

Figure 3-2 Zoom in figure of bathymetry snapshot showing the location of the proposed facility

3.2 Boundary Conditions

The boundary conditions for the HD model were extracted from DHI’s Global tide prediction model. This model is a Global tide prediction model assimilated with 20 years of SSH from TOPEX/POSEIDON altimetry data. It represents the major diurnal (K1, O1, P1 and Q1) and semidiurnal tidal constituents (M2, S2, N2 and K2) with a spatial resolution of 0.25 × 0.25 degrees. For the present study, Model was trained providing three open sea boundaries which were extracted from this Tide model. However, the boundary condition of upstream discharge for Kundalika River is approximately 40 m3/s.

7

Wind is introduced over model as the atmospheric boundary condition through a speed dependent wind friction coefficient. The source of winds is derived from the UKMO dataset.

3.3 Bed Resistance

The MIKE21 hydrodynamic model is governed by the Reynolds-Averaged Navier-Stokes (RANS) equations, which are depth-integrated over the water column to finally yield the St. Venant equations. In the governing equations, the friction parameter is expressed as:

3/12hMgk =

Where M (m1/3/s) is the Manning Number (the Manning Number is also seen in the literature as n=1/M). The importance of Manning Number is well known in both traditional as well as numerical hydraulics. A varying Manning number is applied throughout the model domain to get a reasonable calibration to the tidal water level, both amplitude and phase.

3.4 Production Period

The hydrodynamic modelling is carried out for a periods of 22 days period to cover the full spring and neap phase of tidal cycle for validating the model. The production period of the hydrodynamic model is given below. Tide with northeast monsoon winds: 26 October to 16 November 2015.

3.5 Model Calibration and Validation

The results of calibration are provided in this section. This calibration is based on the field collected data provided by the client. Figure 3-3 gives the calibration plot with respect to water surface elevation. The simulated tidal levels are having a good agreement with the measured data. The comparison of the simulated and measured water level is in the acceptable range with RMS deviation of 0.17, which accounts about 2% of the tidal range.

Calibration and validation with respect to current speed and direction has been carried out at three locations CM1, CM2 and CM3. The predicted and measured current speed and direction at locations CM1, CM2 and CM3 has been represented in Figure 3-4 to Figure 3-6 respectively. From the figure it could be seen that the results are in agreement with the field measured data with the error of around 10-15% which can be attributed to the changes in the bathymetry.

HD model gives depth averaged current. The surface and bottom currents may have minor variation. Hence it is suggested to use following simplified formulation for estimating current at desired layers,

Current at a Layer = 1.142 X Depth Averaged Current x ( Layer Depth

Total Water Depth)

0.142

NB: Layer depth is numbered inversely like at 15m water depth, the surface layer is 15 and bottom layer is 1.

8

Figure 3-3 Comparison of measured and simulated water level at third pillar of Revdanda Bridge

Figure 3-4 Comparison of measured and simulated current speed at location CM1

Figure 3-5 Comparison of measured and simulated current speed at location CM2

Figure 3-6 Comparison of measured and simulated current speed at location CM3

9

3.6 Model Results

On calibrating and validating the model satisfactorily, the results were analysed in the region with particular focus on the proposed facility.

Figure 3-7 and Figure 3-8, gives the snapshot of the flow vectors during flood and ebb conditions.

Figure 3-7 Very close snapshot of current pattern during peak flood tide and NE monsoon with existing condition

Figure 3-8 Very close snapshot of current pattern during the ebb tide and NE monsoon with existing condition

10

4 Oil Spill Modelling

4.1 Overview

An oil slick on the surface will be subject to transport by predominant currents and winds. A good hydrodynamic model and good information on local winds at the spill site are therefore critical for predicting the movements of the oil. The HD modelling has been carried out using DHI MIKE21 modelling suite. The simulation of the hydrocarbon spills has been carried out using DHI’s Oil Spill model MIKE 21 OS. In this model the oil is represented as (Lagrangian) particles being advected with the surrounding water body and exposed to weathering processes. The advection (drift) of the individual particles is determined by the combined effects of current, wind and bed drag. The model provides information on oil slick locations, the amount of oil left on the sea surface, the slick mobility and the evolution of the physiochemical properties of the oil. The weathering processes included in the model are described below.

4.2 Oil Spill Processes

MIKE 21 OS model describes the spreading and weathering of oil spills in an aquatic environment under the influence of water movements and the associated dispersion processes (Figure 4-1). The oil itself is defined according to its distillation properties and chemical structure.

Figure 4-1 Processes acting on spilled oil

The following processes are considered in the models (Figure 4.1)

• Spreading (through advection by currents and dispersion)

11

• Evaporation

• Emulsification

• Vertical dispersion

• Dissolution

The physical and chemical changes that spilled oil undergoes are collectively known as weathering. Although the individual processes causing these changes may act simultaneously, their relative importance vary with time. Together they affect the behaviour of the oil and determine the fate. These processes are illustrated in Figure 4-2 for a spill of a typical medium crude oil under moderate sea conditions. Sedimentation only occurs for very heavy oils in connection with mineral particles (sand/clay). Biodegradation and photo-oxidation only affect oil spills in the longer term (i.e. weeks to months or years).

Figure 4-2 A schematic representation of the fate of a crude oil showing changes in the relative importance of weathering processes with time

4.3 Oil spill Process and Properties

The different parameters applied for the oil spill processes are listed below.

• Spreading: The currents define the water movement (advection) while the dispersion in the OS module is described using three dispersion coefficients that are proportional to the current in the longitudinal, transverse and vertical directions. Proportionality constants of 1.0 [m], 0.1 [m] and 0.01 [m] respectively were applied.

• Evaporation: Evaporation is given as a constant that is proportional to the amount of the evaporated oil. A default value of 0.0292 (dimensionless) has been applied.

• Emulsification: The emulsification process (water uptake) leads to a reduction in concentration, but also diminishes the evaporation of components from an emulsion. For the present study the emulsification is not included.

• Dispersion (called entrainment in MIKE 21 OS): The entrainment of oil (or vertical dispersion) into the water column is simulated using an interfacial tension parameter with a value of 20 dyne/cm (default value) valid for nonbreaking waves.

12

• Dissolution: The volume of oil leaving the slick due to dissolution is calculated via a mass transfer coefficient set to a default value of 2.36·10-6 (dimensionless).

Additionally, the heat transport is considered in MIKE 21 OS with the following parameters used in the balance calculation:

• Albedo value: 0.14

• Emissivity of oil: 0.8

• Emissivity of water: 0.95

• Emissivity of air: 0.82

4.4 Oil Properties

Oil properties are described in MIKE 21 OS through the percentage of each eight oil fractions given in Table 4-1.

Table 4-1 Oil fractions

Fraction Description Boiling range Values (%)

1 C6 – C12 (Paraffin) 69 – 2300 C 6.3

2 C13 – C25 (Paraffin) 230 – 4050 C 29.3

3 C6 – C12 (Cycloparaffin) 70 – 2300 C 15.3

4 C13 – C23 (Cycloparaffin) 230 – 4050 C 5.2

5 C6 – C11 (Aromatic) 80 – 2400 C 3.9

6 C12 – C18 (Aromatic) 240 – 4000 C 10

7 C9 – C25 (Napthteno-aromatic) 180 – 4000 C 10

8 Residual (incl. heterocycles) >4000 C 20

Additionally, a viscosity of 3.24 and reference temperature of 200 C are included in the spill modelling setup.

4.5 Environmental Data

As outline previously in the report, the hydrodynamic and wind conditions are key to driving the oil spill model.

4.5.1 Currents The drift applied in the oil spill simulations is a combination of a traditional bed shear profile (logarithmic from the hydrodynamic model simulation and wind acceleration of particles

13

directly exposed to the wind). The drift profile applied in the model is the sum of these two profiles.

4.5.2 Wind Data Wind data obtained from the DHI secondary data sources is applied in the oil spill model to describe the surface drift.

4.5.3 Oceanographic Data A constant salinity of 33 psu and a constant sea water temperature of 27 degree C have been applied.

4.6 Spill Scenarios

Three spill scenarios have been modelled:

Scenario 1- Leakages during loading and unloading processes at berth area

Scenario 2- Collision at the turning circle

Scenario 3- Collison at waiting/anchorage area with possible rupture of hale and grounding

Details of the individual oil spill scenarios are given in Table 4-2. Each spill simulates fuel oil as a conservative approach.

Table 4-2 Spill parameter for scenarios 1-3

Scenario Number 1 2 3

Location Near Berth At Turning Circle At Anchorage

Area

Type of oil Fuel oil Fuel oil Fuel oil

Total Spill 1000 Tonnes 10000 Tonnes 10000 Tonnes

Spill duration 2 hr 6 hrs 6 hrs

Simulation duration 15 days 15 days 15 days

Temperature 26 26 26

Water depth 14.5m 15.5m 15.5m

The locations of the spill are shown in Figure 4-3

14

Figure 4-3 Spill locations

4.7 Oil Spill Modelling Results

The results from the combination of 3 spill scenarios and 6 individual start times within the two monsoon seasons are presented by plots of arrival times and oil thickness.

4.7.1 Scenario-1 (Berthing Area Spill) Figure 4-5 and Figure 4-4 show the maximum oil thickness at the end of 15 day simulation occurring during Sw and NE monsoon.

Some key observations include:

• During SW monsoon, the oil slick can travel beyond the berthing area and enter inside the Revdanda river within the simulated two-week period, carried by the monsoon generated net currents.

• During NE monsoon, the oil slick is concentrated within the berth area and does not travel far away towards the Revdanda river

• The oil spill coverage is less during NE monsoon as it has higher probability to contained by west of the proposed development as shown in Figure 4-5.

• The oil slick travels towards coastline during NE monsoon while having a higher probability of being pushed more towards river during the SW monsoon.

• For some combination of tide and wind conditions, the oil slick tends to get trapped within the port premises in the model.

15

Figure 4-4 Maximum thickness during SW monsoon for simulation between 04 July 2015 to 19 July 2015

Figure 4-5 Maximum thickness during NE monsoon for simulation between 26 October 2015 to 11 November 2015.

16

4.7.2 Scenario-2 (Turning Circle) Figure 4-6 and Figure 4-7 show the maximum oil slick thickness at the end of 15 days simulation occurring during SW and NE monsoon for Scenario 2.

• The pattern for the spill in the turning circle is similar to the berthing area spill with the following main differences:

• The spill area is more exposed to the current flowing by the harbour and the slick therefore leaves the turning circle faster and spreads towards offshore during NE monsoon.

• The slick travels significantly further towards offshore during NE monsoon due to the more exposed spill location

• The oil slick travels towards coastline during SW monsoon due to the monsoon wind direction occurrence

• The probability of slick being contained within the harbour area is also much smaller than compared to the spill at the berthing area.

• The same precautions in the result interpretation apply as for spill Scenario 1 during SW monsoon, i.e it would be expected that the sea breeze effects and waves would lead to impacts along the coastline and rivermouth.

17

Figure 4-6 Maximum thickness during SW monsoon for simulation between 04 July 2015 to 19 July 2015

Figure 4-7 Maximum thickness during NE monsoon for simulation between 26 October 2015 to 11 November 2015.

18

4.7.3 Scenario-3 (Anchorage Area Spill) Spill Scenario 3 is at the Anchorage area well seaward of the proposed development. Figure 4-8 and Figure 4-9 show maximum oil thickness at the end of 15days simulation occurring during NE and SW monsoon respectively.

• With the same climatic scenarios, the slick behaviour with seasons is similar for spill Scenario 1 and 2. Notable differences for Spill Scenario 3 include:

• The spill occurs further off-shore, and the slick therefore travels offshore during NE monsoon.

• During SW monsoon conditions, the slick may reach coastline and it is possible that sea breeze effects would further increase risk that the slick is drawn along the coastline

19

Figure 4-8 Maximum thickness during SW monsoon for simulation between 04 July 2015 to 19 July 2015

Figure 4-9 Maximum thickness during NE monsoon for simulation between 26 October 2015 to 11 November 2015

20

4.8 Oil Spill Management Strategy

The oil spill modelling study indicates that, the fuel oil spill of 15000T will spread over a width of 2000m and will reach the mouth of the Revdanda river. Accordingly, the resource requirement based on the existing sea conditions and other environmental factors, should be kept in readiness in the study area. Resources such as booms, skimmers, dispersants and other necessary equipment should be placed in the Port for quick oil spill combat operations.

Priority should be given to contain the oil spill by physical means such as booms and skimmers. Dispersants (chemicals) should be used only if necessary, depending on the clean-up situation and damage that is likely to occur to the environment.

An Oil Spill Contingency Plan is an important working document that identifies the oil spill risks, the appropriate response strategies, the resources required to submit a response and the training and exercise necessary to ensure practicality and effectiveness of the plan. The purpose of this document is to provide guidance for the Disaster Management groups of the port. The main objective of the Contingency Plan is to prepare a Pollution control team to respond to the situation within maximum 30 minutes and also to ensure efficient communication processes as the communication plays an important role in the efficient management of an oil spill response.

5 Bulk Solid Cargo Spillage

Bulk solid cargo, consists of a combination of particles, granules, or any larger pieces of material, generally uniform in composition, and loaded directly into the cargo spaces without any intermediate form of containment. Most dry bulk cargo is prone to spillage, and if allowed to happen can pose environmental problems even for ports which handle comparatively low tonnages.

With advances in technologies, the equipment’ is provided with state-of-the-art pollution control measures such as, water fog system at the cargo hoppers and transfer point to arrest any unlikely dust emission. The cargo unloading grabs are also specially made spillage proof.

However, in the unlikely event of cargo spillage, due to heaviness of the material it is likely to sink to the sea bottom. These cargos are in general are not toxic and therefore would not cause appreciable water contamination. The spilled material in water however small quantities, would be cleaned from time to time and are not likely to cause any water pollution. The specific gravity of the material would not allow movement of these material under the combined action of the current and waves in the protected harbour environment. Accordingly, there would not be any appreciable effect on the immediate environs.

Since, the fines are very less, particle tracking model would not yield any significant result. It is therefore, a necessary requirement to design the equipment which are largely spillage proof and accidental spillage, if any would be on rarest of rare occasions. In case of such occurrences, immediate cleaning of the seabed in a radius of about 500-1000 meters would be carried out using appropriate equipment.

21

6 Conclusions

Monsoon wind driven currents tend to dominate over tidally driven currents at the proposed site, this leads to:

• Predominantly onshore transport of the oil slick during SW monsoon conditions

• Predominantly offshore transport of the oil slick during NE monsoon conditions

• The net currents driven the monsoon winds can transport the oil slick fairly long distances within the relatively short periods of time.

• Although the dominant monsoon winds are largely predominant, it should be noted that local wind effects are not resolved in the winds available, and it is considered likely that sea breeze effects combined with waves will tend to push the oil slick towards the coastline.

• The proposed development area is at risk for nearshore oil spills during the SW monsoon period. Oil spills further offshore such as at the anchorage area may travel further offshore during NE monsoon, but may also impact the coastline during SW monsoon.

• Spilled bulk solid cargo due to accident will mostly spread around the site, say in a radius of about 500-1000 metres and shall be cleared by using appropriate equipment.

 

 

 

 

 

 

vii. Point‐wise  details  of  each  of  the 

issues  raised  during  public  hearing 

and  commitments  made  by  the 

project  proponent  with  EMP.

Indo Energy International Ltd.

Point-wise details of each of the issues raised during public hearing and commitments made

by the project proponent with EMP.

19th November, 2016, at Mr. Carmel School, Korlai, Ta. Murud, Dist. Raigad

Sh. Kiran Panbude, Additional District Magistrate, Raigad

Dr. AN Harshwardhan, RO, MPCB, Raigad

Sr. No.

Concerns raised

Our Response

1 The contents of the presentation are not correct. Local people are suffering due to nuisance of coal dust. As mentioned in the presentation, if 200 trucks are required for material transportation; the connecting roads are inadequate. The adjacent eco-friendly VIllage Chaul, is at a distance of 400 mtrs. Government has planned to develop Allbag and Murud as "Tourist Spots." In the project, coal and other mineral material will be handled. Due to contamination of sea water with liquid material of project, the fishes may die. The livelihood of local families is solely dependent on fishing. The project proponent has not implemented any scheme under CSR activities at Sanegaon. The project proponent was not willing to provide financial assistance to the family of deceased employee. The Reserved Forest Phanasad is near to the proposed project site. Due to the project, fishing activities, ecology of the area and Reserved Forest will be ruined. Korlai Fort of Archaeological Department and Phansad Reserved Forest having area of 6979 hector are nearby the project site. There Is one Light House near the proposed project. All these wlll be affected due to the proposed project. About sixteen types of minerals will be handled In the project. People may suffer from Cancer, Skin diseases and various other diseases due to handling of coal. There are possibilities of noise pollution during cargo handling. The ill-effects of pollution are observed in the vicinity of Sanegaon project. The proposed project may degrade surrounding environment, the eco-friendly Chaul village will also be affected. Coconut and Arecanut cultivation will be burnt. The health and livelihood of people will be in danger. Facilities for material storage and transportation are not available In the project. As the project will affect environment, we are opposing lt.

Project representative explained about the project and various mitigation measures in place to regulate traffic congestion on the present roads. The two lane Korlai-Roha road have been four-laned and carrying capacity of the roads have increased to take load of cargo evacuation by road. The project side is outside of the ecosensitive zone of the Phansad WS. Care will be taken that fishing carried out in the river is not hampered due to proposed project. Cautious care will be taken in controlling air pollution from the project. Proposal was submitted to Archaeological Survey of India but it was stated that Proposed project is outside Notified Zone of Korlai Fort hence NOC is not required

Indo Energy International Ltd.

2 The project will be established on 125 acres of land, it is mentioned in the report that there are neither mangroves nor mud at project site. We are here from the generations together, there are mangroves and mud; fishing of prawns and crabs is done by our fishing community. The bread and butter of the fishing community will be spoiled by the project. The project proponent has misled the Government and local people by providing wrong information. There are mangroves and mud at project site. It is mentioned In the project that there is no creek, however the creek is in existence. Fishing is carried in River Kundalika during monsoon. There are nearly 120 fishing boats owned by Korlai fishermen. Due to proposed project, Allbag and Murud talukas will be destroyed. Brinjals and vegetables cultivated by local Christian families are very popular in this area. The project will destroy agriculture business In this area. Therefore, we are opposing the project.

Project representative explained that project will be established without disturbing the mangroves, project will not be established at fishermen's fishing area.

3 Presentation given by project proponent is misleading. If the local people will be affected due to the project, we do not want the project

All care has been taken to communicate the summary impacts and mitigations plan of the project.

4 There will be violation of Article 48, 51 of the Constitution of India due to proposed project. We do not want the project. There are mangroves at project site. Dust emissions from project will affect the Phansad Reserved Forest and Korlai Fort. Various species of birds and wild animals will be affected, hence we are opposing the project.

The project side is outside of the ecosensitive zone of the Phansad WS. Care will be taken that fishing carried out in the river is not hampered due to proposed project. Cautious care will be taken in controlling air pollution from the project.

5 Applications were submitted to various government offices under the RTI Act, 2005. It is suspected that Sanegaon jetty may be illegal. There are possibilities of Kundalika river water pollution due to dust emissions from the proposed project. Project proposal seems to be illegal and we are opposing the project.

All existing facilities are operating under valid permissions of statutory authorities.

6 During various meetings, the villagers informed that they have no objection for the proposed jetty project. In the last meeting, it was decided that if the village problems will be attended, then project should be allowed. If all are opposing, then I am with the local people.

Welcome.

7 While inspection by me, member of our society, deputy Sarpanch of our village & two representatives of company we asked about project. Company representative informed that

Comments is not related to the project.

Indo Energy International Ltd.

project will be developed leaving area of 500 meters near to Kasha. Afterwards area of Birla company will be left. If area of 500 meters will be leaved it Is not related with our creek. Sufficient space is not available for handling of 2,000 Ton material and cargoes.

8 Proper information in respect of job opportunities in the project should be given. It is informed' during presentation that there will be job opportunities for 120 personnel. The proposed project will affect environment, we are opposing the project.

Job opportunities will be given to locals on a priority basis subject to skill availability.

9 Information given in the presentation is inadequate. Details of land admeasuring 120 acres is not explained.

All care has been taken to communicate the summary impacts and mitigations plan of the project.

10 Safety measures will not be implemented and local people will suffer due to project.

All care has been taken to communicate the summary impacts and mitigations plan of the project.

11 Our Korlai village is gifted with greenery and natural beauty. We are opposing the project.

Proposed project will not hamper the surrounding region.

21th November, 2016, at near Sanegaon Jetty site Ta. Roha, Dist. Raigad

Sh. Kiran Panbude, Additional District Magistrate, Raigad

Dr. AN Harshwardhan, RO, MPCB, Raigad

Sr. No.

Concerns raised

Our Response

1. Local residents are facing nuisance problems due to dust emissions from existing project. Due to this, local students are taking admission in Roha School which is at far distance than local school. Coal powder emissions are deposited on surrounding trees.

A comprehensive dust control system will be implemented to ensure no dust nuisance occurs outside the Sanegaon facility boundary.

2. It is necessary to verify distance of project from environmental sensitive zone and forest areas. Due to increasing river depth, agricultural and farming activities will be affected, there will shortage of drinking water.

All care has been taken to communicate the summary impacts and mitigations plan of the project.

3. Who is responsible for conducting the public hearing, which Government Officials are conducting the hearing?

The hearing was being conducted as per MoEF & CC, GoI notification. Chairman of the Public Hearing Committee is attending the hearing as representative of District Magistrate, Raigad. Convenor of the public hearing introduced the Government Officials on the dias to the public.

4. Whether public hearing was conducted for establishment of existing project jetty in 2009?

Environmental clearance to the project was accorded in the year

Indo Energy International Ltd.

He has submitted RTI application to various government offices, in response MPCB has communicated that public hearing not required for the project. Surrounding villages and mangroves will be affected due to excavation of mud from river. Kundalika river water will be contaminated due to run off water sprinkled on coal, due to this fish kill may happen, affecting the livelihood of fishermen.

2005 far before MoEF&CC, GoI notification dated 14th September, 2006. Public hearing was not required at that time. No mangrove or fishing activity will be effected due to the proposed modernization.

5. Thousands of acres of agricultural land became non-productive due to discharging of polluted water by the industry located at MIDC Dhatav. By discussing issues of dust and smell nuisance, people should take commitment from the industry. For compensation, people should discuss with the company. We can solve the problem by mutual understanding and discussions.

A comprehensive dust control system will be implemented to ensure no dust nuisance occurs outside the Sanegaon facility boundary.

6. There was erosion on the river bank of length about 1.5 to 2.0 k.m. in the year 2009 for the water transportation. Due to increasing channel depth, further erosion will take place, we are opposing the project.

No erosion has been observed in the river; the same is due to low flow in the river and very weak tidal incursion.

7. Shri Shantaram Ganu Shelke asked for name and address of project occupier. Surrounding villagers and students of Asharam School are suffering due to the project. He asked information about local and other State I outside Region company employees. The condition of Sanegaon-Nidi Road Is worst and repairing of the same is essential.

Earlier depth of navigation channel was 3.0 meters and it will be increased up to 3.1 meters. Effluent Treatment Plant is installed in the existing project and it will be upgraded during expansion. Regular health check-up of school students is carried by the company, the employees are insured by company. Captain Karnal is Occupier of company who is residing at Vashi, Navi Mumbai.

8. The insurance compensation is yet not received by the family of deceased employee, Shri Santosh Thakur.

The company has deposited the requisite insurance amount in the office of commissioner of Labour, the compensation will be disbursed from commissioner of Labour office. Company has made all expenses during the medical treatment of deceased Shri Santosh Thakur.

9. Company has destroyed mangroves at Gut no.12 to 66, Village Sanegaon. The coal transporting dredgers have damaged the fishing nets of fishermen. Water and air pollution Is being created by the company.

No mangrove or fishing activity will be effected due to the proposed modernization.

Indo Energy International Ltd.

Road condition IS affected due to material transportation. Company should be closed down.

10. There is a development in this area due to the company. Instead of arguments, villagers should discuss with company for their problems.

Company agrees for further discussion

11. C Dust is emission in his agricultural land which is adjacent to company; however, company is not considering his problems. For control of dust emissions, water sprinkling should be done on the road between Sanegaon to Nidi. Coal should be covered by tarpaulin sheet during transportation.

Agreed

12. Company's coal transporting vehicles are over-loaded and dust is emitted during transportation as coal is not covered by tarpaulin sheet. Water sprinkling is done upto Shenvai village by the company and the same should be sprinkled upto Nidi village. The arrogant drivers drive vehicles in dangerous speed.

Agreed

13. Pollution control measures should be strictly Implemented. Polluted water should not be disposed Into creek. Proper care should be taken for protection of fishermen's business. Care should also be taken to avoid dust deposition on surrounding trees. It should be noted that the local people are mostly doing fishing business.

Agreed

14. Locals are doing fishing and sand dredging business. Dhatav MIDC is located at a distance of 21 Kms. Company has donated school bus and now should provide ambulance for the villagers. Company should take Into confidence the local people to solve their problem and provide them employment opportunities. We are supporting the project.

Care will be taken that fishing activity is not affected by Sanegaon facility. Local will be prioritized for new employment opportunity in facility. Village development will be taken up as per CSR and CER guidelines.----

15. Company should control their pollution and provide good road for the students of Ashram Shaia. The Development Fund should be utilized for constructing roads, providing drinking water facilities, expenses of water bills under CSR activities. We are not against the project.

Village development will be taken up as per CSR and CER guidelines.agree

16. Company should control their air pollution problems and avoid coal dust emission.

Point noted

17. The coastal area and agriculture is affected, also there are water scarcity problems.

Village development will be taken up as per CSR and CER guidelines.

18. In the report, it is wrongly mentioned that there are is no wild life. In the report, JNPT location is

Aerial distance is considered hence 45km.

Indo Energy International Ltd.

shown at a distance of 45 Kms from the project, however, actually it is about 70 to 80 Kms from the project. Surrounding area of 700 to 800 acres will be affected due to increasing navigation channel depth. Fishermen and villagers will be affected, we are opposing the project.

19. Fishing nets of fishermen are damaged due to company operations, but compensation is not given to them by Company. There are mangroves in the surrounding area. Company Is violating various Government Enactments and various Articles of Indian Constitution.

Project representative Shri Mahadik informed that fishermen should inform the company about damage of their fishing nets. As per demand of people, water sprinkling will be done on road between Sanegaon to Nidi.

Detailed Environmental Management plan is given in Chapter 9 and Environmental Corporate

responsibility (CER) is given in 8.4 of the EIA report

 

 

 

 

 

 

 

viii. Details of EIA Consultant along with 

Accreditation Certificate. 

Details  of  EIA  consultant  is  provided in chapter 11 of EIA  report and valid Accreditation  Certificate  is  attached in EIA report 

 

 

 

 

 

ix. Plan  for  Corporate  Environment 

Responsibility  (CER)  as  specified 

under  Ministry’s  Office 

Memorandum  issued  vide  letter 

F.No.  22‐65/2017‐IA.III  dated 

01.05.2018.  

  

 

 

 

 

 

 

CORPORATE ENVIRONMENTAL RESPONSIBILITY

Plan for Corporate Environment Responsibility (CER) as specified under Ministry’s Office

Memorandum issued vide letter F. No. 22-65/2017-IA.III dated 01.05.2018.

With reference to the above OM following are the concerns raised during the public consultation and thereof the commitments made by the project proponent to address the same:

SR. NO

ISSUES RAISED WITH RESPECT TO ENVIRONMENT

COMMITMENT BY IEIL

A. Korlai fort: With reference to MoM of public hearing held on 19th November 2016

Suffering of local people due to coal dust nuisance. This may also affect the adjacent eco-friendly village Chaul, which is at a distance of 400 mtrs.

Use of slit curtains will be done to minimize the coal dust emission. Also water spray or sprinkler system will be provided at the barge unloader, coal stacks and truck loading station.

Coal and other mineral material will be handled in the project, contamination of sea water with liquid material may occur, due to this many fishes may die.

Use of slit curtains will be done to minimize the coal dust emission. For development of fisheries Rs. 6 crores are allotted under ESR activity.

Reserved forest Phansad is near to the proposed project site. Due to the project, activities such as fishing, ecology of the area and the reserved forest will be ruined.

Phansad wild life Sanctuary is ~ 14.7 km away from proposed Korlai Jetty and ~ 14.43 km away from existing Sanegaon facility, hence no adverse impact is envisaged.

Possibilities of noise pollution during handling of cargo.

Use of noise barrier equipment and roadside plantation may aid in reducing noise pollution

Coconut and Arecanut cultivation may get burnt.

Health and livelihood of people will be in danger due to environmental pollution

Proper mitigation measures and implementation plan addressed in EIA report and same will be practiced to avoid pollution.

No proper facilities available for material storage and transportation. This will affect the environment of the area

Raw material storage facility is earmarked and the location for same is shown in Chapter 2 of EIA report

In the report it is mentioned that there are neither mangroves nor mud at project site. Whereas mangroves and mud are present in the project site.

The proposed area is devoid of mangroves except for sparse and stunted patches. Site photographs are shown in EIA report chapter 3 Also, port area both the bank line and the water area to be used for reclamation is devoid of any mangroves

SR. NO

ISSUES RAISED WITH RESPECT TO ENVIRONMENT

COMMITMENT BY IEIL

In the project it in mentioned that there is no creek. Creek exists in the project site.

The river has tidal influence water creek is certain part of river stretch, as project covers large stretch of the river common word river is utilized.

Brinjals and vegetables cultivated by local Christian families are very popular in the area. The project will destroy agricultural businesses in that area.

Care will be taken that project will not hamper local community

There will be violation of Article 48, 51 of the constitution of India due to proposed project.

No violation of article 48 (organize agriculture and animal husbandry on modern and scientific lines) and 51 (international peace and security) envisaged

Various species of birds and animals will be affected due to dust emissions done by the proposed project

Proper mitigation measures proposed to combat dust emissions in the area due to proposed project.

Kundalika river water pollution due to dust emission from the proposed project.

Silt curtains to be used to minimize pollution of Kundalika river.

B. Sanegaon Village: With reference to MoM of public hearing held on 21st November 2016

Nuisance problems due to dust emission is being faced by the local people. Coal powder is being deposited on surrounding trees.

Use of slit curtains will be done to minimize the coal dust emission. Also water spray or sprinkler system will be provided at the barge unloader, coal stacks and truck loading station.

There will be water shortage, agricultural and farming activities will be affected due to increase in river depth.

In construction phase water will be sourced from eater tankers and in operation phase water would be received from the MIDC supplies.

Proposed project will affect the surrounding villages and mangroves due to excavation of mud from river.

Kundalika river water contamination due to water sprinkled on coal. Fishes may die due to this.

The effluent from coal stack yard will be collected in clarifier wherein clear water will be reused for sprinkling purposed and dust particles will be resend in coal stack yard. Further, water mixed with coal particles during sprinkling will be collected through channel along the storage into a clarifier system wherein water and coal dust will be separated.

SR. NO

ISSUES RAISED WITH RESPECT TO ENVIRONMENT

COMMITMENT BY IEIL

Also, for development of fisheries Rs. 75 Lakhs are allotted under ESR activity.

Erosion can take place due to increase in channel depth.

Shoreline will be assessed by proper techniques sometimes involving mathematical/physical model studies to ascertain remedial measures such as shore protection works, sand by passing etc.

The company has destroyed mangroves at Gut No. 12 to 66 in Sanegaon village. It also generates a lot of water and air pollution.

Coal transporting vehicles are overloaded, they are not covered in tarpaulin sheet. This is causing dust emission.

Proper precautionary measures will be adopted to minimize dust emission in the area due to the proposed project such as use of tarpaulin, water sprinklers and maintained speed limits.

It is wrongly mentioned that there are no wild life. Surrounding area of 700 to 800 acres will be affected due to increasing navigation channel depth.

Additional as a responsible corporate, M/s Indo-Energy International Limited would integrate its environment, HR and ethical business policies with appropriate community engagement and gender equity. The major social sectors IEIL would emphasize for the local community developments are Education, Water Sanitation, Health, Livelihood and Empowerment, Sports, Environment, and Infrastructure Development. The total budgetary cost towards the CSR plan to be implanted is INR 40 Cr.