Future buildings…..3 Bed Semi detached case study - Passive ...
-
Upload
khangminh22 -
Category
Documents
-
view
0 -
download
0
Transcript of Future buildings…..3 Bed Semi detached case study - Passive ...
ulster.ac.uk
Future buildings…..3 Bed Semi detached case studyNearly Zero Energy Building(NZEB), and the CostsDr. Shane Colclough
Dip EE, BSc, MIE, MBA, PhD, MIEI, CEng, EurIng
Ulster University
ulster.ac.uk
The Passive House….., the Nearly Zero Energy Building(NZEB), and the Costs
Dr. Shane Colclough
Dip EE, BSc, MIE, MBA, PhD, MIEI, CEng, EurIng
Ulster University
ulster.ac.uk
The Passive House, the Nearly Zero Energy Building (NZEB)……..
Dr. Shane Colclough
Dip EE, BSc, MIE, MBA, PhD, MIEI, CEng, EurIng
Ulster University
ulster.ac.uk
The Passive House, the Nearly Zero Energy Building (NZEB), and the Costs
Dr. Shane Colclough
Dip EE, BSc, MIE, MBA, PhD, MIEI, CEng, EurIng
Ulster University
Architects: Bott, Ridder, WestermayerPrivately financed project,
Additional costs subsidized by the State of Hesse
Dr. Wolfgang Feist
1996Passive House Institute
Today50,000+ Worldwide
19911st Passive House built
What is a Passive House: Genesis
Sustainability
Costeffectiveness
Comfort
PassiveHouse
Standard
Buildingsbuilt
better
Flexible, straightforward and open to all
What is a Passive House: Objective
A Passive House is a building in which thermal comfort [ISO 7730] can be guaranteed by post-heating or post-cooling the fresh-air flow required for a good indoor air quality without additional recirculation.
Climate independent Passive House definition
What is a Passive House: Definition
What is a Passive House: The Maths..(Where does the 10W/m2 come from?)
• Specific Heat Capacity of Air: 1.005kJ/Kg.K
• Density of Air: 1.205 kg/m3
• SHC per m3: 1.211 kJ/K
• For wall height of 2.5m & ach-1 of 0.5, 1.3m3 of air is exchanged each hour allowing 1.81 kJ/K of heat to be transported by air per m2 of floor area (0.42W/Km2).
• Assuming a lift of 25°C is possible (avoiding dust scorching), the max amount of heat transferable by air is 10W/m2.
*all based on treated floor area
**including (DHW, heating, cooling, auxiliary & household electricity)
Heating demand 15 KWh/(m²yr)
OR Heating load 10 W/m²
Cooling demand 15 KWh/(m²yr)
OR Cooling load 10 W/m²
Airtightness n50 0.6ac/h
Primary energy demand 120 KWh/(m²yr)**
Passive House criteria*
What is a Passive House: Criteria
11
1 Thermal
insulation:
U 0.15 W/(m²K)
Uw 0.8 W/(m²K)
33-pane glazing:
Ug 0.8 W/(m²K)
g-value 50 - 55%
4Airtight
envelope
n50 0.6 /h
5 Ventilation with heat
recovery 75%
outside air waste air
supply airexhaust air
2 Avoid thermal
bridge effectsa 0.01 W/(mK)
What is a Passive House: Typical Approach
Source: Department of Environment, Community and Local Government. ‘Towards Nearly Zero Energy Buildings in Ireland, Planning for 2020 and Beyond. November 2012
RoI National Targets for NZEB
• Passive House ‘appears’ to perform worse than NZEB
• Reality is different – PH is already NZEB
Advancement in Energy Efficiency in Republic of Ireland
Passive House max, including plug loads = 120 kWh/m2.year
Passive House max, excluding plug loads = ~ 60 kWh/m2.year
Primary Energy in kWh/m2.year
Passive House typical, excluding plug loads = ~ 40 kWh/m2.year
Source: Department of Environment, Community and Local Government. ‘Towards Nearly Zero Energy Buildings in Ireland, Planning for 2020 and Beyond. November 2012
• Passive Houses
• Prevailing Min Building
• Regulations
• nZEB Houses
Location of Case StudynZEBDwellings
Bennett Passive House DEAP Output
37.7
8.2
0.2420.250
DEAP
• Project Already Exceeds NZEB Requirements according to DEAP
Bennett Passive House Normal PHPP Output
37.7
8.2
0.2420.250
DEAP
112
29.2
N/RN/R
Normal PHPP
• ‘Passive House’ Appears to Fail NZEB Miserably???????
Basis of Calculations of Primary Energy Demand {kWh/M2a}
Passive House
• Net Floor Area (TFA)
• Prim energy conv factor of 2.6
• All consumed energy
nZEB (Republic of Ireland)
• Gross Floor area
• Prim energy conv factor of 2.1
• DHW & Space Heating, fixed lighting & ventilation (omits egcooking, washing & clothes drying, entertainment eqpt, home office)
10%
24%
50%
24.24
5.26
0.1590.165
DEAP
Bennett Passive House ‘DEAP’ PHPP Output
91.1
18.6
N/RN/R
Normal PHPP
• ‘DEAP’ PHPP adjusted to omit plug loads, include PV production and reduce Primary Energy factor for electricity from 2.6 to 2.19
42.4
5.8
N/RN/R
‘DEAP’ PHPP
• Bennett Passive House Already NZEB
Other Factors Not Considered
DEAP Model PHPP Model
Floor area calculation Gross Net (“Treated Floor Area”)(excludes internal walls and stairs)
Winter Interior Temperature
~ 18.5OCAverage based on typical Irish dwelling layouts for 8 hrs per day
20OC throughout
Summer Interior Temperature
Overheating not predicted
25OC Max for 10% of year
Radiant Temperature Asymmetry
Not considered Avoided
Unintended air infiltration
< 7 m3/m2/hr @ 50Pa < 0.6 ach-1 @ 50Pa
Ventilation rate To be specified 15m3 fresh air per person per hour
Basis for model Benchmark house Bespoke model for each design
Validation of performance
Unpublished Scientifically validated
Heating duration 8 hours per day 24 hours per day
ulster.ac.uk
Key Message: PHPP and RoINational Dwelling Energy Assessment Procedure are fundamentally different
ulster.ac.uk
Key Message: Initial indications:Dwelling is performing in line with PH and DEAP expectations
Building to the passive house
standard compared with the
prevailing building regulations
The historical cost differentials
2000 (single dwelling) €18,010
2010 (scheme) € 4,000
2020 (scheme) ?
Analysis Aim
Examine the construction cost of building a
BER A3 house (current Requirement) in
comparison to an nZEB (BER A1 house).
Analysis applies to a housing scheme of 12
houses, and not a single house project.
32
Parametric comparisonEnergy influencing elements
Item A3 A1
Thermal Envelope
{W/m2K} {W/m2K}
Insulation U Value Roof 0.16 0.07
Floor 0.21 0.08
Walls 0.21 0.17*
Windows & Doors 1.24 0.74
Ventillation system
Natural Ventilation Heat Recovery Ventilation
Heating System Main Oil Fired Central Htg
2 x 550W Electric rads
2 x 175W Towel rads
Backup & Multifuel Stove & air post heater
DHW
Immersion Heat Pump
Cost Comparison:2015 & nZEB (A1)Building Regulations
•Only building elements influenced by an energy aspect are examined.
•Company overheads or profit margins have not been included in the analysis.
•VAT has not been added on to the final figure.
•All costs figures quoted are at 1 Jan 2017.
•detailed base costs produced independently
of the developer
Basis of CalculationsA1 to A3
A1 house has been costed
What savings could be made by building to the A3
standard?
Analysis:
Quantity Surveyor from Building Firm
Quantity Surveyor from Waterford Institute of Technology
Researcher Ulster University
Overview: A1 to A3 Comparison
1. Preliminaries (Site Overheads)
2. Thermal Envelope-Substructure
3. Thermal Envelope-Superstructure
4. Windows and External Doors
5. Ventilation and Heating
38
€ 2,265.00
€ 715.00
€ 3,170.00
€ 900.00
€ 2,650.00
€ 130.00
Red = Additional CostBlack = Savings
Some conclusions: builders
perspective
Knowledge is essential.
Very few snags on completion.
Operator Manual is essential.
BER A1 House - Quicker turnaround
Highest standards are cost achievable.
ulster.ac.uk
Acknowledgements
Seamus Mullins, Michael Bennett Group, QS Michael Bennett, Michael Bennett GroupJohn Mernagh, Derrek Sinnott, WIT, QSProf Philip Griffiths, Prof NJ Hewitt
ulster.ac.uk
The Passive House, the
Nearly Zero Energy Building
(NZEB), and the Costs
Dr. Shane Colclough
Dip EE, BSc, MIE, MBA, PhD, MIEI, CEng, EurIng
Ulster University
ulster.ac.uk
Future buildings…..3 Bed Semi
detached case study
Nearly Zero Energy Building
(NZEB), and the CostsDr. Shane Colclough
Dip EE, BSc, MIE, MBA, PhD, MIEI, CEng, EurIng
Ulster University
A1 to A3 Comparison
1. Preliminaries (Site Overheads)
Additional Costs for A3
Increase in length of programme bar chart €2,750.00
Planning Contributions discount € 225.00
€2,975.00
Cost Reductions for A3
PHPP Fee (Passive House) € 540.00
Door Blower Test € 170.00
€ 710.00
Net Additional Cost to A3 €2,265.00
A1 to A3 Comparison
2. Thermal Envelope- Substructure
Additional Costs for A3
Provide chimney stack base
Reduced cold bridging detailing € 10.00
Cost Reductions for A3
Reduction in insulation (230mm-80mm) € 725.00
Net Cost Reduction to A3 € 715.00
A1 to A3 Comparison
3. Thermal Envelope- Superstructure
Additional Costs for A3 Nil
Cost Reductions for A3
Reduced cold bridging detailing €1,384.00
Reduced structure and insulation €1,786.00
Net Cost Reduction to A3 €3,170.00
A1 to A3 Comparison4. Windows and External Doors
Additional Costs for A3
Double Glazed windows and doors
(U Value 1.20W/m2K) €3,300.00
Cost Reductions for A3
Triple Glazed windows and doors
(U Value 0.80W/m2K) €4,200.00
Net Cost Reduction to A3 € 900.00