FOTO RENCANA KEGIATAN MTsN 27 KEMBANGAN KERAMIK EXISTING
-
Upload
independent -
Category
Documents
-
view
0 -
download
0
Transcript of FOTO RENCANA KEGIATAN MTsN 27 KEMBANGAN KERAMIK EXISTING
KEGIATAN : WAJIB BELAJAR PENDIDIKAN DASAR SEMBILAN TAHUNPEKERJAAN : REHAB GEDUNGLOKASI : MTsN 27 JOGLO, JAKARTA BARATTAHUN ANGGARAN : ABPN‐P T.A 2011
NO JUMLAH HARGA (Rp)I PEKERJAAN PERSIAPAN 1,955,200.00 II PEKERJAAN ARSITEKTUR
1. PEKERJAAN BONGKARAN 1,440,000.00 2. PEKERJAAN KERAMIK 24,912,000.00 3. PEKERJAAN PENGECATAN (FINISHING) 34,398,090.00
JUMLAH 62,705,290.00 PPn 10 % 6,270,529.00
TOTAL 68,975,819.00 DIBULATKAN 68,975,000.00
TERBILANG :Enam Puluh Delapan Juta Sembilan Ratus Tujuh Puluh Lima Ribu Rupiah
Direktur
REKAPITULASI
URAIAN PEKERJAAN
Jakarta, September 2011PT. Bahana Nusantara
Ir. Tjutju Rasmadi Dj.
KEGIATAN : WAJIB BELAJAR PENDIDIKAN DASAR SEMBILAN TAHUNPEKERJAAN REHAB GEDUNG
DAFTAR KUANTITAS DAN HARGA
PEKERJAAN : REHAB GEDUNGLOKASI : MTsN 27 JOGLO, JAKARTA BARATTAHUN ANGGARAN : ABPN‐P T.A 2011
NO VOLUME SATUAN HARGA
SATUAN (Rp)JUMLAH HARGA
(Rp)I PEKERJAAN PERSIAPAN
1. Papan Nama Proyek 1.00 bh 325,200.00 325,200.00 2 Photo Proyek 3 Phase Color 1 00 set 290 000 00 290 000 00
URAIAN PEKERJAAN
2. Photo Proyek 3 Phase Color 1.00 set 290,000.00 290,000.00 3. Air Kerja 1.00 ls 590,000.00 590,000.00 4. Pembersihan Lokasi dan Mobilisasi 1.00 ls 750,000.00 750,000.00
Jumlah 1,955,200.00 II PEKERJAAN ARSITEKTUR
1. PEKERJAAN BONGKARAN‐ Pek Bongkar Lantai keramik 288.00 m2 5,000.00 1,440,000.00
2. PEKERJAAN KERAMIK2. PEKERJAAN KERAMIK‐ Lantai Keramik Setara Mulia 288.00 m2 86,500.00 24,912,000.00
3. PEKERJAAN PENGECATAN (FINISHING)‐ Pek Cat Kusen pintu dan Jendela 180.60 m2 40,900.00 7,386,540.00 ‐ Pek Cat Kaca Jendela 26.00 m2 40,900.00 1,063,400.00 ‐ Pek Cat Daun Pintu 31.50 m2 40,900.00 1,288,350.00
‐ Pek Cat Dinding Dalam 375.75 m2 30,400.00 11,422,800.00 g , , ,‐ Pek Cat Plafond 434.00 m2 30,500.00 13,237,000.00
Jumlah 60,750,090.00 JUMLAH 62,705,290.00 PPn 10 % 6,270,529.00 TOTAL 68,975,819.00 DIBULATKAN 68,975,000.00
NO. URAIAN KOEF. SAT. HARGA SAT. JUMLAHPEKERJAAN PERSIAPAN1 m2 ‐ Pembersihan LokasiPekerja 0.0500 hr 45,000.00 2,250.00 Mandor 0.0100 hr 58,500.00 585.00
Jumlah 2,835.00 Dibulatkan 2,800.00
1 m1 ‐ Pengukuran & pemasangan bouwplankKayu Kaso terentang 5/7‐400 cm 0.0040 m3 1,800,000.00 7,200.00 Kayu Papan terentang 2/20‐ 400 cm 0.0060 m3 1,440,000.00 8,640.00 Paku segala ukuran 0.0200 kg 16,000.00 320.00 Pekerja 0.0500 hr 45,000.00 2,250.00 Tukang Kayu 0.0500 hr 49,500.00 2,475.00 Mandor 0.0050 hr 58,500.00 292.50
Jumlah 21,177.50 Dibulatkan 21,100.00
1 m1 ‐ Pagar Pengaman ProyekPasir Beton 0.0012 m3 153,000.00 183.60 Batu kali 0.0048 m3 180,000.00 864.00 Semen PC ( 50 kg ) 0.0170 zak 54,000.00 918.00 Kaso Meranti Jambi Basah uk. 5 x 10 x 400 cm 0.0360 m3 3,060,000.00 110,160.00 Seng Gelombang BJLS 28 (80x180) cm 1.4300 lbr 60,000.00 85,800.00 Paku Kayu Segala uk. 0.0200 kg 16,000.00 320.00 Pekerja 0.3000 hr 45,000.00 13,500.00 Tukang Batu 0.3750 hr 49,500.00 18,562.50 Tukang Kayu 0.1500 hr 49,500.00 7,425.00 Mandor 0.0150 hr 58,500.00 877.50
Jumlah 238,610.60 Dibulatkan 238,600.00
1 m1 ‐ Pagar BRC tinggi 90 cmBRC t = 0.9 m Ø 6 0.4340 lbr 195,000.00 84,630.00 Pekerja 0.0420 hr 45,000.00 1,890.00 Tukang Kayu 0.0420 hr 49,500.00 2,079.00 Kepala Tukang Kayu 0.0040 hr 54,000.00 216.00 Mandor 0.0020 hr 58,500.00 117.00
Jumlah 88,932.00 Dibulatkan 88,900.00
1 bh ‐ Papan nama proyekMultipleks 120 x 240, 9 mm 0.5000 lbr 140,000.00 70,000.00 Cat kayu/besi 1.1000 kg 56,000.00 61,600.00 Kaso kayu meranti 0.0280 m3 3,060,000.00 85,680.00 Penulisan 1.0000 ls 49,500.00 49,500.00 Ongkos pasang 1.0000 ls 58,500.00 58,500.00
Jumlah 325,280.00 Dibulatkan 325,200.00
1 m2 ‐ Direksikeet (lantai plesteran)Pasir pasang 0.2500 m3 162,000.00 40,500.00 Pasir beton 0.0517 m3 153,000.00 7,910.10 Batu bata merah 25.0000 bh 600.00 15,000.00 Semen PC 50 kg 0.2500 zak 54,000.00 13,500.00 Kayu kaso meranti 0.0300 m3 3,060,000.00 91,800.00 Triplek 122 x 244 x 4 mm 1.0000 lbr 64,000.00 64,000.00 Engsel pintu uk 3 " 0.1667 bh 21,000.00 3,500.70 Asbes semen gelombang 250x92 x 0. 5 cm 0.5000 lbr 52,000.00 26,000.00 Kaca polos 5 mm 0.2917 m2 76,000.00 22,169.20 Rangka teralis nako 0.2917 bh 120,000.00 35,004.00 Paku segala ukuran ( rata‐rata) 0.5000 kg 16,000.00 8,000.00 Kunci gembok kecil 0.0833 bh 54,000.00 4,498.20 Pekerja 0.4000 hr 45,000.00 18,000.00 Tukang batu 0.0834 hr 49,500.00 4,128.30 Tukang kayu 0.3340 hr 49,500.00 16,533.00 Mandor 0.0200 hr 58,500.00 1,170.00
Jumlah 371,713.50 Dibulatkan 371,700.00
PEKERJAAN TANAH1 m3 ‐ Perataan TanahPekerja 0.0400 hr 45,000.00 1,800.00 Mandor 0.0040 hr 58,500.00 234.00 Alat bantu 0.6000 set 1,000.00 600.00
Jumlah 2,634.00 Dibulatkan 2,600.00
1 m3 ‐ Galian Tanah Biasa Kedalaman 1 mPekerja 0.7500 hr 45,000.00 33,750.00 Mandor 0.0250 hr 58,500.00 1,462.50 Alat bantu 0.6000 set 1,000.00 600.00
ANALISA TEKNISHARGA SATUAN PEKERJAAN
Jumlah 35,812.50 Dibulatkan 35,800.00
1 m3 ‐ Galian Tanah Biasa Kedalaman 1 m ‐ 2 mPekerja 0.9000 hr 45,000.00 40,500.00 Mandor 0.0325 hr 58,500.00 1,901.25 Alat bantu 0.6000 set 1,000.00 600.00
Jumlah 43,001.25 Dibulatkan 43,000.00
1 m3 ‐ Galian Tanah Biasa Kedalaman 2 m ‐ 3 mPekerja 0.9350 hr 45,000.00 42,075.00 Mandor 0.0730 hr 58,500.00 4,270.50 Alat bantu 0.6000 set 1,000.00 600.00
Jumlah 46,945.50 Dibulatkan 46,900.00
1 m3 ‐ Galian Tanah Biasa Kedalaman 3 m ‐ 4 mPekerja 0.9400 hr 45,000.00 42,300.00 Mandor 0.0940 hr 58,500.00 5,499.00 Alat bantu 0.6000 set 1,000.00 600.00
Jumlah 48,399.00 Dibulatkan 48,300.00
1 m3 ‐ Galian Tanah Biasa Kedalaman 1‐ 5 m dengan alat berat.Pekerja 0.2000 hr 45,000.00 9,000.00 Mandor 0.0020 hr 58,500.00 117.00 Excavator kap. 80 ‐ 120 HP 0.1000 jam 340,000.00 34,000.00 Alat bantu 0.3000 set 1,000.00 300.00
Jumlah 43,417.00 Dibulatkan 43,400.00
1 m3 ‐ Galian Tanah KerasPekerja 0.9650 hr 45,000.00 43,425.00 Mandor 0.0350 hr 58,500.00 2,047.50 Alat bantu 0.6000 set 1,000.00 600.00
Jumlah 46,072.50 Dibulatkan 46,000.00
1 m3 ‐ Galian Tanah BerbatuPekerja 1.9600 hr 45,000.00 88,200.00 Mandor 0.0323 hr 58,500.00 1,889.55 Alat bantu 0.6000 set 1,000.00 600.00
Jumlah 90,689.55 Dibulatkan 90,600.00
1 m3 ‐ Galian Tanah LumpurPekerja 0.9750 hr 45,000.00 43,875.00 Mandor 0.0325 hr 58,500.00 1,901.25 Alat bantu 0.6000 set 1,000.00 600.00
Jumlah 46,376.25 Dibulatkan 46,300.00
1 m3 ‐ Galian Tanah Sumuran Kedalaman Max. 10 mPekerja 1.2000 hr 45,000.00 54,000.00 Mandor 0.0500 hr 58,500.00 2,925.00 Alat bantu 0.6000 set 1,000.00 600.00
Jumlah 57,525.00 Dibulatkan 57,500.00
1 m3 ‐ Angkutan Galian Jarak Max. 30 MPekerja 0.2480 hr 45,000.00 11,160.00 Mandor 0.0080 hr 58,500.00 468.00 Alat bantu 0.6000 set 1,000.00 600.00
Jumlah 12,228.00 Dibulatkan 12,200.00
1 m3 ‐ Urugan Kembali Galian TanahPekerja 0.3000 hr 45,000.00 13,500.00 Mandor 0.0100 hr 58,500.00 585.00 Alat bantu 0.6000 set 1,000.00 600.00
Jumlah 14,685.00 Dibulatkan 14,600.00
1 m3 ‐ Urugan Tanah bahan dari luar dipadatkan dg stamper tiap 20 cm (tanah biasa)Tanah Urug 1.2000 m3 35,000.00 42,000.00 Pekerja 0.1240 hr 45,000.00 5,580.00 Mandor 0.0040 hr 58,500.00 234.00 Stamper, 5 HP, Kap. 0.17 ton 0.9000 jam 80,000.00 72,000.00 Alat bantu 0.3000 set 1,000.00 300.00
Jumlah 120,114.00 Dibulatkan 120,100.00
1 m3 ‐ Urugan Tanah bahan dari luar pakai alat besar ( tiap 20 cm ) tanah biasaTanah Urug 1.2000 m3 35,000.00 42,000.00 Pekerja 0.1500 hr 45,000.00 6,750.00 Mandor 0.0050 hr 58,500.00 292.50 Buldozer kap. 100 ‐ 150 HP 0.1500 jam 360,000.00 54,000.00 Alat bantu 0.3000 set 1,000.00 300.00
Jumlah 103,342.50 Dibulatkan 103,300.00
1 m3 ‐ Urugan Tanah bahan dari luar pakai alat besar ( tiap 20 cm ) tanah berbatuTanah Urug 1.2000 m3 35,000.00 42,000.00 Pekerja 0.1240 hr 45,000.00 5,580.00 Mandor 0.0040 hr 58,500.00 234.00 Buldozer kap. 100 ‐ 150 HP 0.1000 jam 360,000.00 36,000.00 Alat bantu 0.3000 set 1,000.00 300.00
Jumlah 84,114.00 Dibulatkan 84,100.00
1 m3 ‐ Urugan pasir bawah lantai & pondasiPasir Urug 1.2000 m3 135,000.00 162,000.00 Pekerja 0.3000 hr 45,000.00 13,500.00 Mandor 0.0100 hr 58,500.00 585.00 Alat bantu 0.6000 set 1,000.00 600.00
Jumlah 176,685.00 Dibulatkan 176,600.00
1 m3 ‐ Urugan SirtuSirtu 1.2000 m3 144,000.00 172,800.00 Pekerja 0.5000 hr 45,000.00 22,500.00 Mandor 0.0200 hr 58,500.00 1,170.00 Alat bantu 0.6000 set 1,000.00 600.00
Jumlah 197,070.00 Dibulatkan 197,000.00
1 m3 ‐ Pemadatan Tanah ( tiap 20 cm ) dengan stamperPekerja 0.3000 hr 45,000.00 13,500.00 Mandor 0.0050 hr 58,500.00 292.50 Stamper 0.9000 jam 80,000.00 72,000.00 Alat bantu 0.6000 set 1,000.00 600.00
Jumlah 86,392.50 Dibulatkan 86,300.00
1 m3 ‐ Galian Tanah bore pile dengan mesin borPekerja 0.4000 hr 45,000.00 18,000.00 Mandor 0.0400 hr 58,500.00 2,340.00 Mesin bor 3.0000 jam 80,000.00 240,000.00 Alat bantu 0.6000 set 1,000.00 600.00
Jumlah 260,940.00 Dibulatkan 260,900.00
PEKERJAAN PONDASI1 m3 ‐ Lantai kerja, mutu fc = 7.4 MPa (K.100)Pasir beton 0.6200 m3 153,000.00 94,860.00 Split pecah mesin 2/3 0.7400 m3 190,000.00 140,600.00 Semen PC ( 50 kg ) 4.9400 zak 54,000.00 266,760.00 Pekerja 1.6500 hr 45,000.00 74,250.00 Tukang batu 0.2500 hr 49,500.00 12,375.00 Kepala Tukang 0.0250 hr 54,000.00 1,350.00 Mandor 0.0800 hr 58,500.00 4,680.00 Sewa molen 0.4000 jam 60,000.00 24,000.00
Jumlah 618,875.00 Dibulatkan 618,800.00
1 m3 ‐ Pas.Pondasi batu kali 1 : 2Pasir Pasang 0.4300 m3 162,000.00 69,660.00 Batu Kali 1.2000 m3 180,000.00 216,000.00 Semen PC ( 50 kg ) 5.2000 zak 54,000.00 280,800.00 Pekerja 1.6500 hr 45,000.00 74,250.00 Tukang Batu 0.5775 hr 49,500.00 28,586.25 Mandor 0.0495 hr 58,500.00 2,895.75 Alat Bantu 2.0000 set 1,000.00 2,000.00
Jumlah 674,192.00 Dibulatkan 674,100.00
1 m3 ‐ Pas.Pondasi batu kali 1 : 3Pasir Pasang 0.4560 m3 162,000.00 73,872.00 Batu Kali 1.2000 m3 180,000.00 216,000.00 Semen PC ( 50 kg ) 4.0000 zak 54,000.00 216,000.00 Pekerja 1.6500 hr 45,000.00 74,250.00 Tukang Batu 0.5775 hr 49,500.00 28,586.25 Mandor 0.0495 hr 58,500.00 2,895.75 Alat Bantu 2.0000 set 1,000.00 2,000.00
Jumlah 613,604.00 Dibulatkan 613,600.00
1 m3 ‐ Pas.Pondasi batu kali 1 : 4Pasir Pasang 0.3910 m3 162,000.00 63,342.00 Batu Kali 1.2000 m3 180,000.00 216,000.00 Semen PC ( 50 kg ) 3.5280 zak 54,000.00 190,512.00 Pekerja 1.6500 hr 45,000.00 74,250.00 Tukang Batu 0.8000 hr 49,500.00 39,600.00 Mandor 0.2000 hr 58,500.00 11,700.00 Alat Bantu 2.0000 set 1,000.00 2,000.00
Jumlah 597,404.00 Dibulatkan 597,400.00
1 m3 ‐ Pas.Pondasi batu kali 1 : 5
Pasir Pasang 0.5600 m3 162,000.00 90,720.00 Batu Kali 1.2000 m3 180,000.00 216,000.00 Semen PC ( 50 kg ) 2.8640 zak 54,000.00 154,656.00 Pekerja 1.6500 hr 45,000.00 74,250.00 Tukang Batu 0.5775 hr 49,500.00 28,586.25 Mandor 0.0495 hr 58,500.00 2,895.75 Alat Bantu 2.0000 set 1,000.00 2,000.00
Jumlah 569,108.00 Dibulatkan 569,100.00
1 m3 ‐ Pas.Batu kosongBatu Kali 1.2000 m3 180,000.00 216,000.00 Pekerja 1.1240 hr 45,000.00 50,580.00 Mandor 0.0560 hr 58,500.00 3,276.00 Alat Bantu 2.0000 set 1,000.00 2,000.00
Jumlah 271,856.00 Dibulatkan 271,800.00
1 m2 ‐ Pas. Cerucuk Bambu sedalam 3 m jarak tiap 50 cmBambu dia 8‐10 x 350‐400 cm 4.0000 btg 23,500.00 94,000.00 Pekerja 0.7500 hr 45,000.00 33,750.00 Tukang Kayu 0.2625 hr 49,500.00 12,993.75 Mandor 0.0505 hr 58,500.00 2,954.25 Alat Bantu 2.1000 set 1,000.00 2,100.00
Jumlah 145,798.00 Dibulatkan 145,700.00
PEKERJAAN BETON1 m3 ‐ Cor beton K.125 ( manual )Pasir beton 0.5070 m3 153,000.00 77,571.00 Split pecah mesin 2/3 0.7160 m3 190,000.00 136,040.00 Semen PC ( 50 kg ) 5.0000 zak 54,000.00 270,000.00 Pekerja 1.8000 hr 45,000.00 81,000.00 Tukang batu 0.4750 hr 49,500.00 23,512.50 Mandor 0.2858 hr 58,500.00 16,719.30 Alat bantu 2.5000 set 1,000.00 2,500.00
Jumlah 607,342.80 Dibulatkan 607,300.00
1 m3 ‐ Cor beton K.175 ( manual )Pasir beton 0.5070 m3 153,000.00 77,571.00 Split pecah mesin 2/3 0.7160 m3 190,000.00 136,040.00 Semen PC ( 50 kg ) 9.0000 zak 54,000.00 486,000.00 Pekerja 1.8000 hr 45,000.00 81,000.00 Tukang batu 0.4858 hr 49,500.00 24,047.10 Mandor 0.2608 hr 58,500.00 15,256.80 Alat bantu 2.5000 set 1,000.00 2,500.00
Jumlah 822,414.90 Dibulatkan 822,400.00
1 m3 ‐ Cor beton K.225 ( manual )Pasir beton 0.5070 m3 153,000.00 77,571.00 Split pecah mesin 2/3 0.7160 m3 190,000.00 136,040.00 Semen PC ( 50 kg ) 11.0000 zak 54,000.00 594,000.00 Pekerja 1.8000 hr 45,000.00 81,000.00 Tukang batu 0.2608 hr 49,500.00 12,909.60 Mandor 0.5858 hr 58,500.00 34,269.30 Alat bantu 2.5000 set 1,000.00 2,500.00
Jumlah 938,289.90 Dibulatkan 938,200.00
1 m3 ‐ Cor beton K.250 ( manual )Pasir beton 0.4000 m3 153,000.00 61,200.00 Split pecah mesin 2/3 0.7400 m3 190,000.00 140,600.00 Semen PC ( 50 kg ) 11.8000 zak 54,000.00 637,200.00 Pekerja 1.8000 hr 45,000.00 81,000.00 Tukang batu 0.2620 hr 49,500.00 12,969.00 Mandor 0.6270 hr 58,500.00 36,679.50 Alat bantu 2.5000 set 1,000.00 2,500.00
Jumlah 972,148.50 Dibulatkan 972,100.00
1 m3 ‐ Cor beton K.125 dengan readymixBeton readymix K.125 1.0000 m3 580,000.00 580,000.00 Pekerja 0.5508 hr 45,000.00 24,786.00 Tukang batu 0.1377 hr 49,500.00 6,816.15 Mandor 0.0688 hr 58,500.00 4,024.80 Concrete vibrator 0.4819 jam 60,000.00 28,914.00 Alat bantu 2.5000 set 1,000.00 2,500.00
Jumlah 647,040.95 Dibulatkan 647,000.00
1 m3 ‐ Cor beton K.225 dengan readymixBeton readymix K.225 1.0000 m3 650,000.00 650,000.00 Pekerja 0.6885 hr 45,000.00 30,982.50 Tukang batu 0.1377 hr 49,500.00 6,816.15 Mandor 0.0688 hr 58,500.00 4,024.80
Concrete vibrator 0.4819 jam 60,000.00 28,914.00 Alat bantu 2.5000 set 1,000.00 2,500.00
Jumlah 723,237.45 Dibulatkan 723,200.00
1 m3 ‐ Cor beton K.250 dengan readymixBeton readymix K.250 1.0000 m3 705,000.00 705,000.00 Pekerja 0.6885 hr 45,000.00 30,982.50 Tukang batu 0.1377 hr 49,500.00 6,816.15 Mandor 0.0688 hr 58,500.00 4,024.80 Concrete vibrator 0.4819 jam 60,000.00 28,914.00 Alat bantu 2.5000 set 1,000.00 2,500.00
Jumlah 778,237.45 Dibulatkan 778,200.00
1 m3 ‐ Cor beton K.300 dengan readymixBeton readymix K.300 1.0000 m3 755,000.00 755,000.00 Pekerja 0.6885 hr 45,000.00 30,982.50 Tukang batu 0.1377 hr 49,500.00 6,816.15 Mandor 0.0688 hr 58,500.00 4,024.80 Concrete vibrator 0.4819 jam 60,000.00 28,914.00 Alat bantu 2.5000 set 1,000.00 2,500.00
Jumlah 828,237.45 Dibulatkan 828,200.00
1 m3 ‐ Cor beton K.350 dengan readymixBeton readymix K.350 1.0000 m3 825,000.00 825,000.00 Pekerja 0.6885 hr 45,000.00 30,982.50 Tukang batu 0.1377 hr 49,500.00 6,816.15 Mandor 0.0688 hr 58,500.00 4,024.80 Concrete vibrator 0.4819 jam 60,000.00 28,914.00 Alat bantu 2.5000 set 1,000.00 2,500.00
Jumlah 898,237.45 Dibulatkan 898,200.00
1 m3 ‐ Cor beton K.400 dengan readymixBeton readymix K.400 1.0000 m3 895,000.00 895,000.00 Pekerja 0.6885 hr 45,000.00 30,982.50 Tukang batu 0.1377 hr 49,500.00 6,816.15 Mandor 0.0688 hr 58,500.00 4,024.80 Concrete vibrator 0.4819 jam 60,000.00 28,914.00 Alat bantu 2.5000 set 1,000.00 2,500.00
Jumlah 968,237.45 Dibulatkan 968,200.00
1 kg ‐ Pembesian ( besi polos )Kawat beton 0.0200 kg 13,000.00 260.00 Besi beton polos 1.1000 kg 8,000.00 8,800.00 Pekerja 0.0150 hr 45,000.00 675.00 Tukang besi 0.0050 hr 49,500.00 247.50 Mandor 0.0050 hr 58,500.00 292.50 Alat bantu 2.5000 set 1,000.00 2,500.00
Jumlah 12,775.00 Dibulatkan 12,700.00
1 kg ‐ Pembesian ( besi ulir )Kawat beton 0.0200 kg 13,000.00 260.00 Besi beton ulir 1.1000 kg 9,000.00 9,900.00 Pekerja 0.0150 hr 45,000.00 675.00 Tukang besi 0.0050 hr 49,500.00 247.50 Mandor 0.0050 hr 58,500.00 292.50 Alat bantu 2.5000 set 1,000.00 2,500.00
Jumlah 13,875.00 Dibulatkan 13,800.00
1 m2 ‐ Bekisting dengan papan + bongkaran dan penyiramanKayu Papan terentang 2/20‐400 cm 0.0240 m3 1,440,000.00 34,560.00 Kayu Kaso terentang 5/7‐400 cm 0.0280 m3 1,800,000.00 50,400.00 Paku 0.2500 kg 16,000.00 4,000.00 Pekerja 0.1650 hr 45,000.00 7,425.00 Tukang kayu 0.3940 hr 49,500.00 19,503.00 Mandor 0.0270 hr 58,500.00 1,579.50 Alat bantu 2.5000 set 1,000.00 2,500.00
Jumlah 119,967.50 Dibulatkan 119,900.00
1 m2 ‐ Bekisting dengan triplex 9 mm + bongkaran dan penyiramanKayu Kaso terentang 5/7‐400 cm 0.0280 m3 1,800,000.00 50,400.00 Triplex 9 mm 0.3500 lbr 140,000.00 49,000.00 Paku 0.2500 kg 16,000.00 4,000.00 Pekerja 0.1650 bh 45,000.00 7,425.00 Tukang kayu 0.3940 hr 49,500.00 19,503.00 Mandor 0.0270 hr 58,500.00 1,579.50 Alat bantu 2.5000 set 1,000.00 2,500.00
Jumlah 134,407.50 Dibulatkan 134,400.00
1 m3 ‐ Bekisting kolom beton struktur
Kayu Kaso terentang 5/7‐400 cm 0.2520 m3 1,800,000.00 453,600.00 Triplex 9 mm 3.1500 lbr 140,000.00 441,000.00 Paku 2.2500 kg 16,000.00 36,000.00 Pekerja 1.4850 bh 45,000.00 66,825.00 Tukang kayu 3.5440 hr 49,500.00 175,428.00 Mandor 0.2430 hr 58,500.00 14,215.50 Alat bantu 2.5000 set 1,000.00 2,500.00
Jumlah 1,189,568.50 Dibulatkan 1,189,500.00
1 m3 ‐ Bekisting balok beton strukturKayu Kaso terentang 5/7‐400 cm 0.1870 m3 1,800,000.00 336,600.00 Triplex 9 mm 2.3500 lbr 140,000.00 329,000.00 Paku 1.6680 kg 16,000.00 26,688.00 Pekerja 1.1010 bh 45,000.00 49,545.00 Tukang kayu 2.6260 hr 49,500.00 129,987.00 Mandor 0.1800 hr 58,500.00 10,530.00 Alat bantu 2.5000 set 1,000.00 2,500.00
Jumlah 884,850.00 Dibulatkan 884,800.00
1 m3 ‐ Bekisting lantai betonKayu Kaso terentang 5/7‐400 cm 0.2320 m3 1,800,000.00 417,600.00 Triplex 9 mm 2.9050 lbr 140,000.00 406,700.00 Paku 2.0750 kg 16,000.00 33,200.00 Pekerja 1.3700 bh 45,000.00 61,650.00 Tukang kayu 3.2685 hr 49,500.00 161,790.75 Mandor 0.2245 hr 58,500.00 13,133.25 Alat bantu 2.5000 set 1,000.00 2,500.00
Jumlah 1,096,574.00 Dibulatkan 1,096,500.00
1 m2 ‐ Perancah kayu / stoot werk ‐ tinggi s/d 2 mKayu Kaso terentang 5/7‐400 cm 0.0608 m3 1,800,000.00 109,440.00 Paku 0.3000 kg 16,000.00 4,800.00 Pekerja 0.6000 hr 45,000.00 27,000.00 Tukang kayu 0.4200 hr 49,500.00 20,790.00 Mandor 0.0300 hr 58,500.00 1,755.00 Alat bantu 2.5000 set 1,000.00 2,500.00
Jumlah 166,285.00 Dibulatkan 166,200.00
1 m2 ‐ Perancah kayu / stoot werk ‐ tinggi s/d 3 mKayu Kaso terentang 5/7‐400 cm 0.0851 m3 1,800,000.00 153,180.00 Paku 0.4200 kg 16,000.00 6,720.00 Pekerja 0.8400 hr 45,000.00 37,800.00 Tukang kayu 0.5880 hr 49,500.00 29,106.00 Mandor 0.0420 hr 58,500.00 2,457.00 Alat bantu 3.5000 set 1,000.00 3,500.00
Jumlah 232,763.00 Dibulatkan 232,700.00
1 m2 ‐ Perancah kayu / stoot werk ‐ tinggi s/d 4 mKayu Kaso terentang 5/7‐400 cm 0.1094 m3 1,800,000.00 196,920.00 Paku 0.5400 kg 16,000.00 8,640.00 Pekerja 1.0800 hr 45,000.00 48,600.00 Tukang kayu 0.7560 hr 49,500.00 37,422.00 Mandor 0.0540 hr 58,500.00 3,159.00 Alat bantu 4.5000 set 1,000.00 4,500.00
Jumlah 299,241.00 Dibulatkan 299,200.00
1 m2 ‐ Perancah kayu / stoot werk ‐ tinggi s/d 5 mKayu Kaso terentang 5/7‐400 cm 0.1398 m3 1,800,000.00 251,640.00 Paku 0.6900 kg 16,000.00 11,040.00 Pekerja 1.3800 hr 45,000.00 62,100.00 Tukang kayu 0.9660 hr 49,500.00 47,817.00 Mandor 0.6900 hr 58,500.00 40,365.00 Alat bantu 5.7500 set 1,000.00 5,750.00
Jumlah 418,712.00 Dibulatkan 418,700.00
1 m3 ‐ Balok beton praktis K.175Adukan beton K.175 ( konvensional ) 1.0000 m3 822,400.00 822,400.00 Pembesian besi polos 120.0000 kg 12,700.00 1,524,000.00 Bekisting dengan papan 5.0000 m2 119,900.00 599,500.00 Alat bantu 4.2000 set 1,000.00 4,200.00
Jumlah 2,950,100.00 Dibulatkan 2,950,100.00
1 m3 ‐ Kolom beton praktis K.175Adukan beton K.175 ( konvensional ) 1.0000 m3 822,400.00 822,400.00 Pembesian besi polos 150.0000 kg 12,700.00 1,905,000.00 Bekisting dengan papan 5.0000 m2 119,900.00 599,500.00 Alat bantu 4.2000 set 1,000.00 4,200.00
Jumlah 3,331,100.00 Dibulatkan 3,331,100.00
1 m3 ‐ Pondasi beton setapak K.225Adukan beton K.225 ( konvensional ) 1.0000 m3 938,200.00 938,200.00 Pembesian besi polos 106.0000 kg 12,700.00 1,346,200.00 Bekisting triplek 9 mm 2.6670 m2 134,400.00 358,444.80
Jumlah 2,642,844.80 Dibulatkan 2,642,800.00
1 m3 ‐ Pondasi beton setapak K.225Adukan beton K.225 ( konvensional ) 1.0000 m3 938,200.00 938,200.00 Pembesian besi polos 132.0000 kg 12,700.00 1,676,400.00 Bekisting triplek 9 mm 2.6670 m2 134,400.00 358,444.80
Jumlah 2,973,044.80 Dibulatkan 2,973,000.00
1 m3 ‐ Sloof beton 15x20 K.225 Brsi 169 kg/m3 (bekisting 2x pakai)Adukan beton K.175 ( site mix ) 1.0000 m3 822,400.00 822,400.00 Pembesian besi polos 169.0000 kg 12,700.00 2,146,300.00 Bekisting balok struktur 0.6667 m3 884,800.00 589,869.62
Jumlah 3,558,569.62 Dibulatkan 3,558,500.00
1 m3 ‐ Sloof beton 20/35 K‐225 Adukan beton K‐225 (Konvensional) 1.0000 m3 938,200.00 938,200.00 Pembesian besi polos 165.0000 kg 12,700.00 2,095,500.00 Bekisting balok struktur 1.0000 m3 884,800.00 884,800.00
Jumlah 3,918,500.00 Dibulatkan 3,918,500.00
1 m3 ‐ Sloof beton 15/30 K‐225 (SL2)Adukan beton K‐225 (Konvensional) 1.0000 m3 12,969.00 12,969.00 Pembesian besi polos 204.0000 kg 12,700.00 2,590,800.00 Bekisting balok struktur 1.0000 m3 884,800.00 884,800.00
Jumlah 3,488,569.00 Dibulatkan 3,488,500.00
1 m3 ‐ Sloof beton 20/35 K‐225 (SL‐1)Adukan beton K‐225 (Konvensional) 1.0000 m3 938,200.00 938,200.00 Pembesian besi polos 165.0000 kg 12,700.00 2,095,500.00 Bekisting balok struktur 1.0000 m3 884,800.00 884,800.00
Jumlah 3,918,500.00 Dibulatkan 3,918,500.00
1 m3 ‐ Kolom beton 30/35 K‐225Adukan beton K‐225 (ready‐mixl) 1.0000 m3 723,200.00 723,200.00 Pembesian 237.0000 kg 12,700.00 3,009,900.00 Bekisting Kolom 1.0000 m3 1,189,568.50 1,189,568.50
Jumlah 4,922,668.50 Dibulatkan 4,922,600.00
1 m3 ‐ Kolom beton 30/30 K‐225 ( K1 )Adukan beton K‐225 (ready‐mixl) 1.0000 m3 723,200.00 723,200.00 Pembesian 189.3333 kg 12,700.00 2,404,532.91 Bekisting Kolom 1.0000 m3 1,189,568.50 1,189,568.50
Jumlah 4,317,301.41 Dibulatkan 4,317,300.00
1 m3 ‐ Kolom beton 25/25 K.225 ( K2)Adukan beton K.225 ( ready ‐ mix ) 1.0000 m3 723,200.00 723,200.00 Pembesian besi polos 297.0000 kg 12,700.00 3,771,900.00 Bekisting kolom 1.0000 m3 1,189,568.50 1,189,568.50
Jumlah 5,684,668.50 Dibulatkan 5,684,600.00
1 m3 ‐ Balok beton 25x65 K.225 Adukan beton K.225 ( ready ‐ mix ) 1.0000 m3 723,200.00 723,200.00 Pembesian besi ulir 150.0000 kg 13,800.00 2,070,000.00 Perancah kayu / stoot werk ‐ tinggi s / d 4 m 2.0000 m2 299,200.00 598,400.00 Bekisting balok 1.0000 m3 884,800.00 884,800.00
Jumlah 4,276,400.00 Dibulatkan 4,276,400.00
1 m3 ‐ Balok beton 25/60 K.225 Adukan beton K.225 ( ready ‐ mix ) 1.0000 m3 723,200.00 723,200.00 Pembesian besi polos 150.0000 kg 12,700.00 1,905,000.00 Perancah kayu / stoot werk ‐ tinggi s / d 4 m 1.6675 m2 299,200.00 498,916.00 Bekisting balok 1.0000 m3 884,800.00 884,800.00
Jumlah 4,011,916.00 Dibulatkan 4,011,900.00
1 m3 ‐ Balok beton 25/35 K.225Adukan beton K.225 ( ready ‐ mix ) 1.0000 m3 723,200.00 723,200.00 Pembesian besi polos 152.0000 kg 12,700.00 1,930,400.00 Perancah kayu / stoot werk ‐ tinggi s / d 4 m 1.6675 m2 299,200.00 498,916.00 Bekisting balok 1.0000 m3 884,800.00 884,800.00
Jumlah 4,037,316.00 Dibulatkan 4,037,300.00
1 m3 ‐ Balok beton 20/45 K.225 (B4)Adukan beton K.225 ( ready ‐ mix ) 1.0000 m3 723,200.00 723,200.00 Pembesian besi polos 170.0000 kg 12,700.00 2,159,000.00 Perancah kayu / stoot werk ‐ tinggi s / d 4 m 1.6675 m2 299,200.00 498,916.00
Bekisting balok 1.0000 m3 884,800.00 884,800.00 Jumlah 4,265,916.00
Dibulatkan 4,265,900.00 1 m3 ‐ Balok beton 15/25 K.225 Adukan beton K.225 ( ready ‐ mix ) 1.0000 m3 723,200.00 723,200.00 Pembesian besiulir 150.0000 kg 13,800.00 2,070,000.00 Perancah kayu / stoot werk ‐ tinggi s / d 4 m 4.0000 m2 299,200.00 1,196,800.00 Bekisting balok 1.0000 m3 884,800.00 884,800.00
Jumlah 4,874,800.00 Dibulatkan 4,874,800.00
1 m3 ‐ Balok beton 12/60 K.225 Adukan beton K.225 ( ready ‐ mix ) 1.0000 m3 723,200.00 723,200.00 Pembesian besiulir 120.0000 kg 13,800.00 1,656,000.00 Perancah kayu / stoot werk ‐ tinggi s / d 4 m 1.6665 m2 299,200.00 498,616.80 Bekisting balok 1.0000 m3 884,800.00 884,800.00
Jumlah 3,762,616.80 Dibulatkan 3,762,600.00
1 m3 ‐ Trap anak tangga dari beton K‐225 Adukan beton K.225 ( ready ‐ mix ) 1.0000 m3 723,200.00 723,200.00 Pembesian besi polos 114.0000 kg 12,700.00 1,447,800.00 Bekisting balok 1.0000 m3 884,800.00 884,800.00
Jumlah 3,055,800.00 Dibulatkan 3,055,800.00
1 m3 ‐ Ring Balok beton 20/40 K.225 Adukan beton K.225 ( ready ‐ mix ) 1.0000 m3 723,200.00 723,200.00 Pembesian besi polos 154.0000 kg 12,700.00 1,955,800.00 Perancah kayu / stoot werk ‐ tinggi s / d 4 m 2.5000 m2 299,200.00 748,000.00 Bekisting balok 1.0000 m3 884,800.00 884,800.00
Jumlah 4,311,800.00 Dibulatkan 4,311,800.00
1 m3 ‐ Ring Balok beton 20/35 K.225 (RB1)Adukan beton K.225 ( ready ‐ mix ) 1.0000 m3 723,200.00 723,200.00 Pembesian besi ulir 167.0000 kg 13,800.00 2,304,600.00 Perancah kayu / stoot werk ‐ tinggi s / d 4 m 3.3300 m2 299,200.00 996,336.00 Bekisting balok 1.0000 m3 884,800.00 884,800.00
Jumlah 4,908,936.00 Dibulatkan 4,908,900.00
1 m3 ‐ Ring Balok beton 20/25 K.225 (RB2)Adukan beton K.225 ( ready ‐ mix ) 1.0000 m3 723,200.00 723,200.00 Pembesian besi ulir 161.0000 kg 13,800.00 2,221,800.00 Perancah kayu / stoot werk ‐ tinggi s / d 4 m 1.6675 m2 299,200.00 498,916.00 Bekisting balok 1.0000 m3 884,800.00 884,800.00
Jumlah 4,328,716.00 Dibulatkan 4,328,700.00
1 m3 ‐ Ring Balok beton 20/25 K.225 (RB3)Adukan beton K.225 ( ready ‐ mix ) 1.0000 m3 723,200.00 723,200.00 Pembesian besi ulir 133.0000 kg 13,800.00 1,835,400.00 Perancah kayu / stoot werk ‐ tinggi s / d 4 m 1.6675 m2 299,200.00 498,916.00 Bekisting balok 1.0000 m3 884,800.00 884,800.00
Jumlah 3,942,316.00 Dibulatkan 3,942,300.00
1 m3 ‐ Balok beton 15/20 K.225 (RB4)Adukan beton K.225 ( ready ‐ mix ) 1.0000 m3 723,200.00 723,200.00 Pembesian besi polos 186.0000 kg 12,700.00 2,362,200.00 Perancah kayu / stoot werk ‐ tinggi s / d 4 m 1.6675 m2 299,200.00 498,916.00 Bekisting balok 1.0000 m3 884,800.00 884,800.00
Jumlah 4,469,116.00 Dibulatkan 4,469,100.00
1 m3 ‐ Plat lantai & tangga beton K.250Adukan beton K.225 ( ready ‐ mix ) 1.0000 m3 723,200.00 723,200.00 Pembesian besi polos 175.0000 kg 12,700.00 2,222,500.00 Perancah kayu / stoot werk ‐ tinggi s / d 4 m 6.2475 m2 299,200.00 1,869,252.00 Bekisting plat lantai 1.0000 m3 1,096,500.00 1,096,500.00
Jumlah 5,911,452.00 Dibulatkan 5,911,400.00
1 m3 ‐ Plat lantai K.225Adukan beton K.225 ( ready ‐ mix ) 1.0000 m3 723,200.00 723,200.00 Pembesian besi polos 114.0000 kg 12,700.00 1,447,800.00 Perancah kayu / stoot werk ‐ tinggi s / d 4 m 6.2475 m2 299,200.00 1,869,252.00 Bekisting plat lantai 1.0000 m3 1,096,500.00 1,096,500.00
Jumlah 5,136,752.00 Dibulatkan 5,136,700.00
1 m3 ‐ Ring Balok beton 13/20 K.175 (site mix) Adukan beton K.225 ( ready ‐ mix ) 1.0000 m3 723,200.00 723,200.00 Pembesian besi polos 170.0000 kg 12,700.00 2,159,000.00
Perancah kayu / stoot werk ‐ tinggi s / d 4 m 3.3300 m2 299,200.00 996,336.00 Bekisting balok 1.0000 m3 884,800.00 884,800.00
Jumlah 4,763,336.00 Dibulatkan 4,763,300.00
1 m3 ‐ Ring Balok beton 15/30 K.225Adukan beton K.225 ( ready ‐ mix ) 1.0000 m3 723,200.00 723,200.00 Pembesian 204.0000 kg 12,700.00 2,590,800.00 Perancah kayu / stoot werk ‐ tinggi s / d 4 m 3.0000 m2 299,200.00 897,600.00 Bekisting balok 1.0000 m3 884,800.00 884,800.00
Jumlah 5,096,400.00 Dibulatkan 5,096,400.00
1 m3 ‐ Pondasi Tangga beton uk. 60x150 cm K. 225 Besi 150 kg/m3 ( bekisting 2x pakai )Adukan beton K.225 ( ready ‐ mix ) 1.0000 m3 723,200.00 723,200.00 Pembesian 150.0000 kg 12,700.00 1,905,000.00 Bekisting triplek 9 mm 4.0000 m2 134,400.00 537,600.00
Jumlah 3,165,800.00 Dibulatkan 3,165,800.00
1 m3 ‐ Plat Lantai beton T = 10 cm K. 225Adukan beton K‐225 (ready‐mixl) 1.0000 m3 723,200.00 723,200.00 polosUlir 68.0000 kg 12,700.00 863,600.00 Bekisting triplek 9 mm + bongkaran dan penyiram 2.1192 m2 134,407.50 284,836.37
Jumlah 1,871,636.37 Dibulatkan 1,871,600.00
1 m2 ‐ Topian beton t = 10 cm ‐ K. 225 Adukan beton K‐225 (ready‐mixl) 1.0000 m3 723,200.00 723,200.00 polosUlir 75.0000 kg 12,700.00 952,500.00 Bekisting triplek 9 mm + bongkaran dan penyiram 2.1192 m2 134,407.50 284,836.37
Jumlah 1,960,536.37 Dibulatkan 1,960,500.00
1 m2 ‐ Plat beton wiremesh K. 225 t=10 cmAdukan beton K‐225 (ready‐mixl) 0.1000 m3 723,200.00 72,320.00 Wiremesh uk. 5.4 x 2.1 m 0.0882 kg 12,700.00 1,120.14 Bekisting triplek 9 mm + bongkaran dan penyiram 2.2000 m2 134,407.50 295,696.50
Jumlah 369,136.64 Dibulatkan 369,100.00
1 m3 ‐ Plat lantai & tangga t=12 cm K 225 Besi 114 kg/m3Adukan beton K‐225 (ready‐mixl) 1.0000 m3 723,200.00 723,200.00 Pembesian besi polos 114.0000 kg 12,700.00 1,447,800.00 Bekisting triplek 9 mm + bongkaran dan penyiram 6.2475 m2 134,407.50 839,710.86
Jumlah 3,010,710.86 Dibulatkan 3,010,700.00
1 m2 ‐ Plat beton wiremesh K. 225 t=12 cmAdukan beton K‐225 (ready‐mixl) 1.0000 m3 723,200.00 723,200.00 Pembesian besi wiremash M‐8 0.7349 lbr 89,000.00 65,406.10 Perancah kayu / stoot werk ‐ tinggi s / d 4 m 6.2475 m2 299,200.00 1,869,252.00 Bekisting plat lantai 1.0000 m3 1,096,500.00 1,096,500.00
Jumlah 3,754,358.10 Dibulatkan 3,754,300.00
PEKERJAAN DINDING1 m2 ‐ Pas.Batu bata, t = 1 / 2 bata ad. 1 : 2Pasir pasang 0.0380 m3 162,000.00 6,156.00 Bata merah 75.0000 bh 600.00 45,000.00 Semen PC ( 50 kg ) 0.4700 zak 54,000.00 25,380.00 Pekerja 0.3600 hr 45,000.00 16,200.00 Tukang batu 0.1875 hr 54,000.00 10,125.00 Mandor 0.0155 hr 58,500.00 906.75 Alat bantu 4.0000 set 1,000.00 4,000.00
Jumlah 107,767.75 Dibulatkan 107,700.00
1 m2 ‐ Pas.Batu bata, t = 1 / 2 bata ad. 1 : 3Pasir pasang 0.0430 m3 162,000.00 6,966.00 Bata merah 75.0000 bh 600.00 45,000.00 Semen PC ( 50 kg ) 0.3600 zak 54,000.00 19,440.00 Pekerja 0.3600 hr 45,000.00 16,200.00 Tukang batu 0.1875 hr 49,500.00 9,281.25 Mandor 0.0155 hr 58,500.00 906.75 Alat bantu 4.0000 set 1,000.00 4,000.00
Jumlah 101,794.00 Dibulatkan 101,700.00
1 m2 ‐ Pas.Batu bata, t = 1 / 2 bata ad. 1 : 4Pasir pasang 0.0460 m3 162,000.00 7,452.00 Bata merah 75.0000 bh 600.00 45,000.00 Semen PC ( 50 kg ) 0.2900 zak 54,000.00 15,660.00 Pekerja 0.3600 hr 45,000.00 16,200.00 Tukang batu 0.1875 hr 49,500.00 9,281.25 Mandor 0.0155 hr 58,500.00 906.75 Alat bantu 4.0000 set 1,000.00 4,000.00
Jumlah 98,500.00 Dibulatkan 98,500.00
1 m2 ‐ Pas.Batu bata, t = 1 / 2 bata ad. 1 : 5Pasir pasang 0.0480 m3 162,000.00 7,776.00 Bata merah 75.0000 bh 600.00 45,000.00 Semen PC ( 50 kg ) 0.2400 zak 54,000.00 12,960.00 Pekerja 0.3600 hr 45,000.00 16,200.00 Tukang batu 0.1875 hr 49,500.00 9,281.25 Mandor 0.0155 hr 58,500.00 906.75 Alat bantu 4.0000 set 1,000.00 4,000.00
Jumlah 96,124.00 Dibulatkan 96,100.00
1 m2 ‐ Pas.batako beton ad. 1:2Pasir Pasang 0.0130 m3 162,000.00 2,106.00 Batako beton 20/40 13.0000 bh 1,200.00 15,600.00 Semen PC ( 50 kg ) 0.1570 zak 54,000.00 8,478.00 Pekerja 0.2900 hr 45,000.00 13,050.00 Tukang batu 0.1500 hr 49,500.00 7,425.00 Mandor 0.0300 hr 58,500.00 1,755.00 Alat bantu 2.0000 set 1,000.00 2,000.00
Jumlah 50,414.00 Dibulatkan 50,400.00
1 m2 ‐ Pas.batako beton ad. 1:3Pasir Pasang 0.0140 m3 162,000.00 2,268.00 Batako beton 20/40 13.0000 bh 1,200.00 15,600.00 Semen PC ( 50 kg ) 0.1000 zak 54,000.00 5,400.00 Pekerja 0.2900 hr 45,000.00 13,050.00 Tukang batu 0.1500 hr 49,500.00 7,425.00 Mandor 0.0300 hr 58,500.00 1,755.00 Alat bantu 2.0000 set 1,000.00 2,000.00
Jumlah 47,498.00 Dibulatkan 47,400.00
1 m2 ‐ Pas.batako beton ad. 1:4Pasir Pasang 0.0150 m3 162,000.00 2,430.00 Batako beton 20/40 13.0000 bh 1,200.00 15,600.00 Semen PC ( 50 kg ) 0.1000 zak 54,000.00 5,400.00 Pekerja 0.2900 hr 45,000.00 13,050.00 Tukang batu 0.1500 hr 49,500.00 7,425.00 Mandor 0.0300 hr 58,500.00 1,755.00 Alat bantu 2.0000 set 1,000.00 2,000.00
Jumlah 47,660.00 Dibulatkan 47,600.00
1 m2 ‐ Pas.batako beton ad. 1:5Pasir Pasang 0.0160 m3 162,000.00 2,592.00 Batako beton 20/40 13.0000 bh 1,200.00 15,600.00 Semen PC ( 50 kg ) 0.0800 zak 54,000.00 4,320.00 Pekerja 0.2900 hr 45,000.00 13,050.00 Tukang batu 0.1500 hr 49,500.00 7,425.00 Mandor 0.0300 hr 58,500.00 1,755.00 Alat bantu 2.0000 set 1,000.00 2,000.00
Jumlah 46,742.00 Dibulatkan 46,700.00
1 m2 ‐ Plesteran & acian tebal 1,5 cm ad. 1 : 2Pasir pasang 0.0180 m3 162,000.00 2,916.00 Semen PC ( 50 kg ) 0.2130 zak 54,000.00 11,502.00 Pekerja 0.3000 hr 45,000.00 13,500.00 Tukang batu 0.1575 hr 49,500.00 7,796.25 Mandor 0.0115 hr 58,500.00 672.75 Alat bantu 2.0000 set 1,000.00 2,000.00
Jumlah 38,387.00 Dibulatkan 38,300.00
1 m2 ‐ Plesteran & acian tebal 1,5 cm ad. 1 : 3Pasir pasang 0.0210 m3 162,000.00 3,402.00 Semen PC ( 50 kg ) 0.1920 zak 54,000.00 10,368.00 Pekerja 0.3000 hr 45,000.00 13,500.00 Tukang batu 0.1575 hr 49,500.00 7,796.25 Mandor 0.0115 hr 58,500.00 672.75 Alat bantu 2.0000 set 1,000.00 2,000.00
Jumlah 37,739.00 Dibulatkan 37,700.00
1 m2 ‐ Plesteran & acian tebal 1,5 cm ad. 1 : 4Pasir pasang 0.0230 m3 162,000.00 3,726.00 Semen PC ( 50 kg ) 0.1570 zak 54,000.00 8,478.00 Pekerja 0.3000 hr 45,000.00 13,500.00 Tukang batu 0.1575 hr 49,500.00 7,796.25 Mandor 0.0115 hr 58,500.00 672.75 Alat bantu 2.0000 set 1,000.00 2,000.00
Jumlah 36,173.00 Dibulatkan 36,100.00
1 m2 ‐ Plesteran & acian tebal 1,5 cm ad. 1 : 5Pasir pasang 0.0240 m3 162,000.00 3,888.00
Semen PC ( 50 kg ) 0.1240 zak 54,000.00 6,696.00 Pekerja 0.3000 hr 45,000.00 13,500.00 Tukang batu 0.1575 hr 49,500.00 7,796.25 Mandor 0.0115 hr 58,500.00 672.75 Alat bantu 2.0000 set 1,000.00 2,000.00
Jumlah 34,553.00 Dibulatkan 34,500.00
1 m2 ‐ Pek.AcianSemen PC ( 50 kg ) 0.0800 zak 54,000.00 4,320.00 Pekerja 0.1430 hr 45,000.00 6,435.00 Tukang batu 0.1123 hr 49,500.00 5,558.85 Mandor 0.0063 hr 58,500.00 368.55 Alat bantu 2.0000 set 1,000.00 2,000.00
Jumlah 18,682.40 Dibulatkan 18,600.00
1 m2 ‐ Pasang Dinding Rooster / Terawang, Natural, uk. 12x11x24 cm, Ad. 1Pc : 4PsRooster 36.0000 bh 20,000.00 720,000.00 Pasir pasang 0.0350 m3 162,000.00 5,670.00 Semen PC ( 50 kg ) 0.2560 zak 54,000.00 13,824.00 Pekerja 0.3000 hr 45,000.00 13,500.00 Tukang Batu 0.1000 hr 49,500.00 4,950.00 Kepala Tukang Batu 0.0100 hr 54,000.00 540.00 Mandor 0.0150 hr 58,500.00 877.50
Jumlah 759,361.50 Dibulatkan 759,300.00
1 m2 ‐ Pas. Dinding glass block uk. 20x20x10 cm , ad. 1 PC : 4 psrGlass Block 20 x 20 (Kedawung) 25.0000 bh 46,000.00 1,150,000.00 Pasir pasang 0.0350 m3 162,000.00 5,670.00 Semen PC ( 50 kg ) 0.2560 zak 54,000.00 13,824.00 Pekerja 0.3000 hr 45,000.00 13,500.00 Tukang Batu 0.1000 hr 49,500.00 4,950.00 Kepala Tukang Batu 0.0100 hr 54,000.00 540.00 Mandor 0.0150 hr 58,500.00 877.50
Jumlah 1,189,361.50 Dibulatkan 1,189,300.00
1 m2 ‐ Pas. Dinding Batu Palimanan Kuning 20x20 cm Texture KasarBatu Tempel Palimanan 1.0500 m2 195,000.00 204,750.00 Pasir pasang 0.0350 m3 162,000.00 5,670.00 Semen PC ( 50 kg ) 0.3250 zak 54,000.00 17,550.00 Pekerja 0.2350 hr 45,000.00 10,575.00 Tukang Batu 0.6200 hr 49,500.00 30,690.00 Kepala Tukang Batu 0.0350 hr 54,000.00 1,890.00 Mandor 0.0300 hr 58,500.00 1,755.00
Jumlah 272,880.00 Dibulatkan 272,800.00
1 m2 ‐ Pas. Bata Ringan (Silicon) beton ad. 1 : 5Pasir pasang 0.0150 m3 162,000.00 2,430.00 Bata Hebel / Celcon uk. 60 x 20 x 10 cm 8.7500 bh 6,500.00 56,875.00 Semen PC ( 50 kg ) 0.1000 zak 54,000.00 5,400.00 Pekerja 0.2000 hr 45,000.00 9,000.00 Tukang batu 0.1000 hr 49,500.00 4,950.00 Mandor 0.0300 hr 58,500.00 1,755.00 Alat bantu 1.0000 set 1,000.00 1,000.00
Jumlah 81,410.00 Dibulatkan 81,400.00
PEKERJAAN ATAP1 m3 ‐ Kuda‐kuda kayu kamper kruingKayu balok kamper kruing 1.1000 m3 3,780,000.00 4,158,000.00 Paku 8‐12 3.0000 kg 16,000.00 48,000.00 Besi pengikat kuda ‐ kuda 15.0000 kg 16,500.00 247,500.00 Pekerja 5.0000 hr 45,000.00 225,000.00 Tukang kayu 15.7500 hr 49,500.00 779,625.00 Mandor 1.0000 hr 58,500.00 58,500.00
Jumlah 5,516,625.00 Dibulatkan 5,516,600.00
1 m3 ‐ Kuda‐kuda kayu kamper banjarKayu balok kamper banjar 1.1000 m3 3,780,000.00 4,158,000.00 Paku 8‐12 3.0000 kg 16,000.00 48,000.00 Besi pengikat kuda ‐ kuda 15.0000 kg 16,500.00 247,500.00 Pekerja 5.0000 hr 45,000.00 225,000.00 Tukang kayu 15.7500 hr 49,500.00 779,625.00 Mandor 1.0000 hr 58,500.00 58,500.00
Jumlah 5,516,625.00 Dibulatkan 5,516,600.00
1 m3 ‐ Kuda‐kuda kayu kamper merantiKayu balok kampermeranti 1.1000 m3 2,880,000.00 3,168,000.00 Paku 8‐12 3.0000 kg 16,000.00 48,000.00 Besi pengikat kuda ‐ kuda 15.0000 kg 16,500.00 247,500.00 Pekerja 5.0000 hr 45,000.00 225,000.00
Tukang kayu 15.7500 hr 49,500.00 779,625.00 Mandor 1.0000 hr 58,500.00 58,500.00
Jumlah 4,526,625.00 Dibulatkan 4,526,600.00
1 m3 ‐ Rangka atap (kaso 5/7 dan reng 3/4 kayu merantiKayu meranti 0.0180 m3 3,060,000.00 55,080.00 Paku 8‐12 0.1500 kg 16,000.00 2,400.00 Pekerja 0.1000 hr 45,000.00 4,500.00 Tukang kayu 0.1000 hr 49,500.00 4,950.00 Mandor 0.0150 hr 58,500.00 877.50
Jumlah 67,807.50 Dibulatkan 67,800.00
1 m' ‐ Pas. listplank 3 / 30 + 3 / 15 kayu kamper banjarPapan kay kamper banjar 0.0150 m3 4,200,000.00 63,000.00 Paku 8 ‐ 12 0.8000 kg 16,000.00 12,800.00 Pekerja 0.2800 hr 45,000.00 12,600.00 Tukang kayu 0.5600 hr 49,500.00 27,720.00 Mandor 0.0720 hr 58,500.00 4,212.00
Jumlah 120,332.00 Dibulatkan 120,300.00
1 m' ‐ Pas. listplank 3 / 30 kayu kamper banjarPapan kay kamper banjar 0.0100 m3 3,420,000.00 34,200.00 Paku 8 ‐ 12 0.0500 kg 16,000.00 800.00 Pekerja 0.1430 hr 45,000.00 6,435.00 Tukang kayu 0.2850 hr 49,500.00 14,107.50 Mandor 0.0360 hr 58,500.00 2,106.00
Jumlah 57,648.50 Dibulatkan 57,600.00
1 m2 ‐ Atap genteng morando glasurGenteng morando glasur 18.0000 bh 3,000.00 54,000.00 Pekerja 0.1500 hr 45,000.00 6,750.00 Kepala Tukang Kayu 0.0790 hr 49,500.00 3,910.50 Mandor 0.0120 hr 58,500.00 702.00
Jumlah 65,362.50 Dibulatkan 65,300.00
1 m1 ‐ Karpusan genteng morando glasurPasir Pasang 0.0320 m3 162,000.00 5,184.00 Semen PC 50 kg 0.2200 zak 54,000.00 11,880.00 Genteng nok morando glasur 3.5000 bh 6,000.00 21,000.00 Pekerja 0.3000 hr 45,000.00 13,500.00 Kepala Tukang Kayu 0.1575 hr 49,500.00 7,796.25 Mandor 0.0225 hr 58,500.00 1,316.25
Jumlah 60,676.50 Dibulatkan 60,600.00
1 m2 ‐ Atap genteng beton polosGenteng beton polos 18.0000 bh 2,200.00 39,600.00 Pekerja 0.1500 hr 45,000.00 6,750.00 Kepala Tukang Kayu 0.0790 hr 49,500.00 3,910.50 Mandor 0.0120 hr 58,500.00 702.00
Jumlah 50,962.50 Dibulatkan 50,900.00
1 m1 ‐ Karpusan genteng genteng betonPasir Pasang 0.0320 m3 162,000.00 5,184.00 Semen PC 50 kg 0.2200 zak 54,000.00 11,880.00 Genteng bumbungan/nok 3.5000 bh 4,800.00 16,800.00 Pekerja 0.3000 hr 45,000.00 13,500.00 Kepala Tukang Kayu 0.1575 hr 49,500.00 7,796.25 Mandor 0.0225 hr 58,500.00 1,316.25
Jumlah 56,476.50 Dibulatkan 56,400.00
1 m2 ‐ Pasang atap asbes gelombang 5 mmAsbes Gelombang 5 mm (180x108) cm 0.9000 lbr 52,000.00 46,800.00 Paku asbes/kg 0.1200 kg 16,000.00 1,920.00 Pekerja 0.1400 hr 45,000.00 6,300.00 Tukang kayu 0.0750 hr 49,500.00 3,712.50 Kepala Tukang Kayu 0.0080 hr 49,500.00 396.00 Mandor 0.0080 hr 58,500.00 468.00
Jumlah 59,596.50 Dibulatkan 59,500.00
1 m2 ‐ Pasang bumbungan/nok atel 1.05 mAsbes nok stel 2.1000 lbr 32,500.00 68,250.00 Paku kayu segala ukuran 0.1200 kg 16,000.00 1,920.00 Pekerja 0.0840 hr 45,000.00 3,780.00 Tukang kayu 0.1250 hr 49,500.00 6,187.50 Kepala Tukang Kayu 0.0130 hr 49,500.00 643.50 Mandor 0.0040 hr 58,500.00 234.00
Jumlah 81,015.00 Dibulatkan 81,000.00
1 kg ‐ Konstruksi baja H ‐ beam / WF ( termasuk plat simpul,las & zinkchromate )
Zinkcchromate 0.0400 m2Besi WF ex. DN SII 1.0500 kgPekerja 0.0600 hrTukang besi 0.0045 hrMandor 0.0025 hrErection 1.0000 hr
JumlahDibulatkan
1 kg ‐ Konstruksi besi siku ( termasuk plat simpul,las & zinkchromate )Zinkcchromate 0.0400 m2Besi siku ex. DN SII 1.0500 kgPekerja 0.0600 hrTukang besi 0.0045 hrMandor 0.0025 hrErection 1.0000 hr
JumlahDibulatkan
1 kg ‐ Konstruksi gording besi ( termasuk plat simpul,las & zinkchromate )Zinkcchromate 0.0400 m2Gording besi 1.0200 kgPekerja 0.0600 hrTukang besi 0.0045 hrMandor 0.0025 hrErection 1.0000 hr
JumlahDibulatkan
1 m2 ‐ Alumunium foilGenteng metal 1.0500 m2 85,000.00 89,250.00 Pekerja 0.0330 hr 45,000.00 1,485.00 Tukang kayu 0.0330 hr 49,500.00 1,633.50 Mandor 0.0050 hr 58,500.00 292.50
Jumlah 92,661.00 Dibulatkan 92,600.00
1 m1 ‐ Talang datar / jurai seng tebal 0.3 mmPapan kayu meranti 2 / 30 0.0096 m3 3,600,000.00 34,560.00 Plat seng lebar 90 cm, tebal 0.30 mm 0.5000 m1 26,000.00 13,000.00 Paku 0.0150 kg 16,000.00 240.00 Pekerja 0.0500 hr 45,000.00 2,250.00 Tukang kayu 0.1200 hr 49,500.00 5,940.00 Mandor 0.0120 hr 58,500.00 702.00
Jumlah 56,692.00 Dibulatkan 56,600.00
1 m' ‐ Pas. Kembali listplank 3 / 30 + 3 / 15 kayu kamper banjarPaku 8 ‐ 12 0.4000 kg 16,000.00 6,400.00 Pekerja 0.0840 hr 45,000.00 3,780.00 Tukang kayu 0.2800 hr 49,500.00 13,860.00 Mandor 0.0360 hr 58,500.00 2,106.00
Jumlah 26,146.00 Dibulatkan 26,100.00
1 m2 ‐ Atap genteng metal roofGenteng metal 1.0000 lbr 85,000.00 85,000.00 Paku 0.1200 kg 16,000.00 1,920.00 Pekerja 0.1400 hr 45,000.00 6,300.00 Tukang 0.1000 hr 49,500.00 4,950.00 Kepala Tukang Kayu 0.0080 hr 54,000.00 432.00 Mandor 0.0080 hr 58,500.00 468.00
Jumlah 99,070.00 Dibulatkan 99,000.00
1 m2 ‐ Atap genteng metalGenteng metal 1.0000 m2 85,000.00 85,000.00 Paku 0.1200 kg 16,000.00 1,920.00 Pekerja 0.1500 hr 45,000.00 6,750.00 Tukang 0.0790 hr 49,500.00 3,910.50 Mandor 0.0120 hr 58,500.00 702.00
Jumlah 98,282.50 Dibulatkan 98,200.00
1 m' ‐ Pasang Nok Atap Metal roofNok Atap Metal Roof type stone 1.1000 m1 32,500.00 35,750.00 Paku asbes/kg 0.1200 kg 16,000.00 1,920.00 Pekerja 0.1400 hr 45,000.00 6,300.00 Tukang kayu 0.1000 hr 49,500.00 4,950.00 Kepala Tukang Kayu 0.0080 hr 54,000.00 432.00 Mandor 0.0080 hr 58,500.00 468.00
Jumlah 49,820.00 Dibulatkan 49,800.00
1 m' ‐ Pasang Lisplank GRC tebal 12 mm Profil susun lebar 30 cmGRC uk. 30 x 240 tebal = 12 mm 1.0000 m1 24,583.33 24,583.33 GRC uk. 15 x 240 tebal = 12 mm 1.0000 m1 20,416.67 20,416.67 Paku asbes / kg 0.1200 kg 16,000.00 1,920.00
Pekerja 0.2800 hr 45,000.00 12,600.00 Tukang Kayu 0.5600 hr 49,500.00 27,720.00 Mandor 0.0720 hr 58,500.00 4,212.00
Jumlah 91,452.00 Dibulatkan 91,400.00
1 m' ‐ Pasang Lisplank GRC tebal 12 mm + rangka kayu merantiKayu meranti 0.0024 m3 3,060,000.00 7,344.00 GRC 12 mm 0.2500 lbr 24,583.33 6,145.83 Paku 0.0525 kg 16,000.00 840.00 Pekerja 0.0660 hr 45,000.00 2,970.00 Tukang Kayu 0.1050 hr 49,500.00 5,197.50 Mandor 0.0138 hr 58,500.00 807.30 Alat Bantu 1.0000 set 1,000.00 1,000.00
Jumlah 24,304.63 Dibulatkan 24,300.00
1 bh ‐ Plat Kopel U plat baja t = 5 mm ( termasuk plat simpul,las & zinkchromate )Zinkcchromate 0.1105 m2Plat baja t = 5 mm 4.4891 kgMur baut dia 16 HTB 2.0000 bhPekerja 0.2400 hrTukang besi 0.0180 hrMandor 0.0100 hrErection 1.0000 bh
JumlahDibulatkan
PEKERJAAN KAYU1 m3 ‐ Kusen kayu kamper samarindaKayu balok kamper samarinda 1.1000 m3 4,000,000.00 4,400,000.00 Paku 3.0000 kg 16,000.00 48,000.00 Angkur 10.5600 kg 8,000.00 84,480.00 Pekerja 7.2000 hr 45,000.00 324,000.00 Tukang kayu 25.2000 hr 49,500.00 1,247,400.00 Mandor 1.5600 hr 58,500.00 91,260.00
Jumlah 6,195,140.00 Dibulatkan 6,195,100.00
1 m3 ‐ Kusen kayu kamper banjarKayu balok kamper banjar 1.1000 m3 3,780,000.00 4,158,000.00 Paku 3.0000 kg 16,000.00 48,000.00 Angkur 10.5600 kg 8,000.00 84,480.00 Pekerja 7.2000 hr 45,000.00 324,000.00 Tukang kayu 25.2000 hr 49,500.00 1,247,400.00 Mandor 1.5600 hr 58,500.00 91,260.00
Jumlah 5,953,140.00 Dibulatkan 5,953,100.00
1 m3 ‐ Kusen kayu kamper kruingKayu balok kamper kruing 1.1000 m3 3,420,000.00 3,762,000.00 Paku 3.0000 kg 16,000.00 48,000.00 Angkur 10.5600 kg 8,000.00 84,480.00 Pekerja 7.2000 hr 45,000.00 324,000.00 Tukang kayu 25.2000 hr 49,500.00 1,247,400.00 Mandor 1.5600 hr 58,500.00 91,260.00
Jumlah 5,557,140.00 Dibulatkan 5,557,100.00
1 m3 ‐ Kusen kayu merantiKayu balok meranti 1.1000 m3 2,880,000.00 3,168,000.00 Paku 3.0000 kg 16,000.00 48,000.00 Angkur 10.5600 kg 8,000.00 84,480.00 Pekerja 7.2000 hr 45,000.00 324,000.00 Tukang kayu 25.2000 hr 49,500.00 1,247,400.00 Mandor 1.5600 hr 58,500.00 91,260.00
Jumlah 4,963,140.00 Dibulatkan 4,963,100.00
1 m2 ‐ Daun pintu double teakwoodRangka papan kamper banjar 0.0400 m3 3,420,000.00 136,800.00 Teakwood 4 mm ukuran pintu 1.0000 lbr 65,000.00 65,000.00 Lem putih 0.3000 kg 40,000.00 12,000.00 Paku triplek 0.0300 kg 16,000.00 480.00 Pekerja 0.4800 hr 45,000.00 21,600.00 Tukang kayu 1.6000 hr 49,500.00 79,200.00 Mandor 0.1840 hr 58,500.00 10,764.00
Jumlah 325,844.00 Dibulatkan 325,800.00
1 m2 ‐ Daun pintu double triplekRangka papan kamper banjar 0.0400 m3 3,420,000.00 136,800.00 Triplek 4 mm ukuran pintu 1.0000 lbr 65,000.00 65,000.00 Lem putih 0.3000 kg 40,000.00 12,000.00 Paku triplek 0.0300 kg 16,000.00 480.00 Pekerja 0.4800 hr 45,000.00 21,600.00 Tukang kayu 1.6000 hr 49,500.00 79,200.00
Mandor 0.1840 hr 58,500.00 10,764.00 Jumlah 325,844.00
Dibulatkan 325,800.00 1 m2 ‐ DDaun pintu double teakwood lapis formika ( untuk KM/WC )Rangka papan kamper banjar 0.0400 m3 3,420,000.00 136,800.00 Teakwood 4 mm ukuran pintu 1.0000 lbr 65,000.00 65,000.00 Formika 0.5000 lbr 220,000.00 110,000.00 Lem putih 0.8000 kg 40,000.00 32,000.00 Paku triplek 0.0300 kg 16,000.00 480.00 Pekerja 0.4800 hr 45,000.00 21,600.00 Tukang kayu 1.6000 hr 49,500.00 79,200.00 Mandor 0.1840 hr 58,500.00 10,764.00
Jumlah 455,844.00 Dibulatkan 455,800.00
1 m2 ‐ Daun pintu kaca�polosRangka papan kamper banjar 0.0300 m3 3,420,000.00 102,600.00 Lem putih 0.4000 kg 40,000.00 16,000.00 Paku 0.0300 kg 16,000.00 480.00 Kaca polos 5 mm 0.9000 m2 76,000.00 68,400.00 Pekerja 0.8000 hr 45,000.00 36,000.00 Tukang kayu 2.0000 hr 49,500.00 99,000.00 Mandor 0.2400 hr 58,500.00 14,040.00
Jumlah 336,520.00 Dibulatkan 336,500.00
1 m2 ‐ Daun pintu raybenRangka papan kamper banjar 0.0300 m3 3,420,000.00 102,600.00 Lem putih 0.4000 kg 40,000.00 16,000.00 Paku 0.0300 kg 16,000.00 480.00 Kaca rayben 5 mm 0.9000 m2 90,000.00 81,000.00 Pekerja 0.8000 hr 45,000.00 36,000.00 Tukang kayu 2.0000 hr 49,500.00 99,000.00 Mandor 0.2400 hr 58,500.00 14,040.00
Jumlah 349,120.00 Dibulatkan 349,100.00
1 m2 ‐ Daun pintu esRangka papan kamper banjar 0.0300 m3 3,420,000.00 102,600.00 Lem putih 0.4000 kg 40,000.00 16,000.00 Paku 0.0300 kg 16,000.00 480.00 Kaca es 5 mm 0.9000 m2 180,000.00 162,000.00 Pekerja 0.8000 hr 45,000.00 36,000.00 Tukang kayu 2.0000 hr 49,500.00 99,000.00 Mandor 0.2400 hr 58,500.00 14,040.00
Jumlah 430,120.00 Dibulatkan 430,100.00
1 m2 ‐ Daun pintu panel kayu samarindaRangka papan kamper samarinda 0.0440 m3 4,200,000.00 184,800.00 Lem putih 0.4000 kg 40,000.00 16,000.00 Pekerja 1.2150 hr 45,000.00 54,675.00 Tukang kayu 2.4300 hr 49,500.00 120,285.00 Mandor 0.2590 hr 58,500.00 15,151.50
Jumlah 390,911.50 Dibulatkan 390,900.00
1 m2 ‐ Daun pintu panel kayu banjarRangka papan kamper banjar 0.0440 m3 3,420,000.00 150,480.00 Lem putih 0.4000 kg 40,000.00 16,000.00 Pekerja 1.2150 hr 45,000.00 54,675.00 Tukang kayu 2.4300 hr 49,500.00 120,285.00 Mandor 0.2590 hr 58,500.00 15,151.50
Jumlah 356,591.50 Dibulatkan 356,500.00
1 m2 ‐ Daun pintu panel kayu merantiRangka papan kamper meranti 0.0440 m3 3,600,000.00 158,400.00 Lem putih 0.4000 kg 40,000.00 16,000.00 Pekerja 1.2150 hr 45,000.00 54,675.00 Tukang kayu 2.4300 hr 49,500.00 120,285.00 Mandor 0.2590 hr 58,500.00 15,151.50
Jumlah 364,511.50 Dibulatkan 364,500.00
1 m2 ‐ Daun pintu / jendela krepyak ( jalusi ) kamper samarindaRangka papan kamper samarinda 0.0420 m3 4,200,000.00 176,400.00 Lem putih 0.2000 kg 40,000.00 8,000.00 Pekerja 1.0000 hr 45,000.00 45,000.00 Tukang kayu 3.0000 hr 49,500.00 148,500.00 Mandor 0.3500 hr 58,500.00 20,475.00
Jumlah 398,375.00 Dibulatkan 398,300.00
1 m2 ‐ Daun pintu / jendela krepyak ( jalusi ) kamper banjarRangka papan kamper banjar 0.0420 m3 3,420,000.00 143,640.00 Lem putih 0.2000 kg 40,000.00 8,000.00
Pekerja 1.0000 hr 45,000.00 45,000.00 Tukang kayu 3.0000 hr 49,500.00 148,500.00 Mandor 0.3500 hr 58,500.00 20,475.00
Jumlah 365,615.00 Dibulatkan 365,600.00
1 m2 ‐ Daun jendela/Boven light kamper samarindaRangka papan kamper samarinda 0.0160 m3 4,200,000.00 67,200.00 Kaca Polos 5 mm 0.8525 m2 76,000.00 64,790.00 Lem putih 1.0000 kg 40,000.00 40,000.00 Pekerja 0.2500 hr 45,000.00 11,250.00 Tukang kayu 0.7500 hr 49,500.00 37,125.00 Mandor 0.1500 hr 58,500.00 8,775.00
Jumlah 229,140.00 Dibulatkan 229,100.00
1 unit ‐ Jalusi (SDN Wil. Tengah)Rangka kusen aluminium 3.7000 m1 110,000.00 407,000.00 Jalusi Hollow 4x4 6.0000 m1 18,500.00 111,000.00 Pekerja 0.3810 hr 45,000.00 17,145.00 Tukang Kayu 0.3420 hr 49,500.00 16,929.00 Mandor 0.0240 hr 58,500.00 1,404.00
Jumlah 553,478.00 Dibulatkan 553,400.00
1 bh ‐ Kusen Jendela Alumunium (J1 SMPN 22)Kusen Alumunium warna ukuran 4" x 1 3/4" 9.6000 m1 110,000.00 1,056,000.00 Frame daun Jendela Alumunium 8.7400 m1 96,000.00 839,040.00 Kaca Polos 5 mm 1.8390 m2 76,000.00 139,764.00 Sealent 1.7307 tube 30,000.00 51,921.00 Karet List 11.5000 m1 5,000.00 57,500.00 Pekrja 0.2028 hr 45,000.00 9,126.00 Tukang 0.7453 hr 49,500.00 36,892.35 Mandor 0.0426 hr 58,500.00 2,492.10
Jumlah 2,192,735.45 Dibulatkan 2,192,700.00
1 bh ‐ Kusen Bouvenligh Alumunium (BV1 SMPN 22)Kusen Alumunium warna ukuran 4" x 1 3/4" 3.0000 m1 110,000.00 330,000.00 Kaca Polos 5 mm 0.4050 m2 76,000.00 30,780.00 Sealent ( 300 ml ) 1.1538 tube 30,000.00 34,614.00 Karet List 6.0000 m1 5,000.00 30,000.00 Pekerja 0.1593 hr 45,000.00 7,168.50 Tukang kayu 0.2928 hr 49,500.00 14,493.60 Mandor 0.0168 hr 58,500.00 982.80
Jumlah 448,038.90 Dibulatkan 448,000.00
1 bh ‐ Kusen Jendela Alumunium (J2 SMPN 22)Kusen Alumunium warna ukuran 4" x 1 3/4" 5.7400 m1 110,000.00 631,400.00 Frame daun Jendela Alumunium 5.9200 m1 96,000.00 568,320.00 Kaca Polos 5 mm 1.0902 m2 76,000.00 82,855.20 Sealent 0.9650 tube 30,000.00 28,950.00 Karet List 9.6000 m1 5,000.00 48,000.00 Pekrja 0.1304 hr 45,000.00 5,868.00 Tukang 0.4791 hr 49,500.00 23,715.45 Mandor 0.0274 hr 58,500.00 1,602.90
Jumlah 1,390,711.55 Dibulatkan 1,390,700.00
1 bh ‐ Kusen Bouvenligh Alumunium (BV1 SMAN 4)Kusen Alumunium warna ukuran 4" x 1 3/4" 4.8000 m1 110,000.00 528,000.00 Kaca Polos 5 mm 0.4800 m2 76,000.00 36,480.00 Sealent ( 300 ml ) 2.0000 tube 30,000.00 60,000.00 Karet List 11.6000 m1 5,000.00 58,000.00 Pekerja 0.1593 hr 45,000.00 7,168.50 Tukang kayu 0.5856 hr 49,500.00 28,987.20 Mandor 0.0335 hr 58,500.00 1,959.75
Jumlah 720,595.45 Dibulatkan 720,500.00
1 bh ‐ Kusen Bouvenligh Alumunium (BV SMAN 4)Kusen Alumunium warna ukuran 4" x 1 3/4" 2.4000 m1 110,000.00 264,000.00 Kaca Polos 5 mm 0.2400 m2 76,000.00 18,240.00 Sealent ( 300 ml ) 1.0000 tube 30,000.00 30,000.00 Karet List 9.6000 m1 5,000.00 48,000.00 Pekerja 0.1304 hr 45,000.00 5,868.00 Tukang kayu 0.4791 hr 49,500.00 23,715.45 Mandor 0.0274 hr 58,500.00 1,602.90
Jumlah 391,426.35 Dibulatkan 391,400.00
1 bh ‐ Kusen Jendela Alumunium (J2 SMPN 4)Kusen Alumunium warna ukuran 4" x 1 3/4" 9.0000 m1 110,000.00 990,000.00 Frame daun Jendela Alumunium 11.2000 m1 96,000.00 1,075,200.00 Kaca Polos 5 mm 1.6900 m2 76,000.00 128,440.00 Sealent 1.7307 tube 30,000.00 51,921.00
Karet List 10.0000 m1 5,000.00 50,000.00 Pekrja 0.2028 hr 45,000.00 9,126.00 Tukang 0.7453 hr 49,500.00 36,892.35 Mandor 0.0426 hr 58,500.00 2,492.10
Jumlah 2,344,071.45 Dibulatkan 2,344,000.00
1 bh ‐ Kusen Jendela Alumunium (J3 SMPN 4)Kusen Alumunium warna ukuran 4" x 1 3/4" 5.0000 m1 110,000.00 550,000.00 Kaca Polos 5 mm 0.8550 m2 76,000.00 64,980.00 Sealent 1.0000 tube 30,000.00 30,000.00 Karet List 5.0000 m1 5,000.00 25,000.00 Pekrja 0.2850 hr 45,000.00 12,825.00 Tukang 0.3960 hr 49,500.00 19,602.00 Mandor 0.0726 hr 58,500.00 4,247.10
Jumlah 706,654.10 Dibulatkan 706,600.00
1 bh ‐ Kusen Jendela Alumunium (J4 SMPN 4)Kusen Alumunium warna ukuran 4" x 1 3/4" 5.4000 m1 110,000.00 594,000.00 Frame daun Jendela Alumunium 5.4000 m1 96,000.00 518,400.00 Kaca Polos 5 mm 0.8750 m2 76,000.00 66,500.00 Sealent 1.0000 tube 30,000.00 30,000.00 Karet List 5.0000 m1 5,000.00 25,000.00 Pekrja 0.2850 hr 45,000.00 12,825.00 Tukang 0.3960 hr 49,500.00 19,602.00 Mandor 0.0726 hr 58,500.00 4,247.10
Jumlah 1,270,574.10 Dibulatkan 1,270,500.00
1 bh ‐ Kusen Jendela Alumunium (J5 SMPN 4)Kusen Alumunium warna ukuran 4" x 1 3/4" 4.7000 m1 110,000.00 517,000.00 Kaca Polos 5 mm 0.4750 m2 76,000.00 36,100.00 Sealent 1.0000 tube 30,000.00 30,000.00 Karet List 4.0000 m1 5,000.00 20,000.00 Pekrja 0.2850 hr 45,000.00 12,825.00 Tukang 0.3960 hr 49,500.00 19,602.00 Mandor 0.0726 hr 58,500.00 4,247.10
Jumlah 639,774.10 Dibulatkan 639,700.00
1 bh ‐ Kusen Jendela Alumunium (J6 SMPN 4)Kusen Alumunium warna ukuran 4" x 1 3/4" 4.7000 m1 110,000.00 517,000.00 Kaca Polos 5 mm 0.3625 m2 76,000.00 27,550.00 Sealent 1.0000 tube 30,000.00 30,000.00 Karet List 4.0000 m1 5,000.00 20,000.00 Pekrja 0.2520 hr 45,000.00 11,340.00 Tukang 0.1950 hr 49,500.00 9,652.50 Mandor 0.0726 hr 58,500.00 4,247.10
Jumlah 619,789.60 Dibulatkan 619,700.00
1 bh ‐ Kusen Jendela Alumunium (J7 SMPN 4)Kusen Alumunium warna ukuran 4" x 1 3/4" 6.2000 m1 110,000.00 682,000.00 Frame daun Jendela Alumunium 3.0000 m1 96,000.00 288,000.00 Kaca Polos 5 mm 0.5600 m2 76,000.00 42,560.00 Sealent 1.0000 tube 30,000.00 30,000.00 Karet List 5.0000 m1 5,000.00 25,000.00 Pekrja 0.1028 hr 45,000.00 4,626.00 Tukang 0.2650 hr 49,500.00 13,117.50 Mandor 0.0426 hr 58,500.00 2,492.10
Jumlah 1,087,795.60 Dibulatkan 1,087,700.00
1 bh ‐ Kusen Jendela Alumunium (J1 SMPN 4)Kusen Alumunium warna ukuran 4" x 1 3/4" 18.0000 m1 110,000.00 1,980,000.00 Frame daun Jendela Alumunium 10.4000 m1 96,000.00 998,400.00 Kaca Polos 5 mm 2.2700 m2 76,000.00 172,520.00 Sealent 1.7307 tube 30,000.00 51,921.00 Karet List 13.5000 m1 5,000.00 67,500.00 Pekrja 0.2028 hr 45,000.00 9,126.00 Tukang 0.7453 hr 49,500.00 36,892.35 Mandor 0.0426 hr 58,500.00 2,492.10
Jumlah 3,318,851.45 Dibulatkan 3,318,800.00
unit ‐ Kusen Jendela (J1)Kusen Alumunium warna ukuran 4" x 1 3/4" 4.0000 m1 110,000.00 440,000.00 Bingkai jendela alumunium 4.0000 m1 96,000.00 384,000.00 Kaca Polos 5 mm 0.6500 m2 76,000.00 49,400.00 Engsel jendela casemen 16" 1.0000 set 38,000.00 38,000.00 Karet List 4.0000 m1 5,000.00 20,000.00 Fisher 4.0000 bh 1,800.00 7,200.00 Ram buncis 1.0000 bh 85,000.00 85,000.00 Upah potong kaca 0.6500 m2 12,375.00 8,043.75 Upah pasang dan Aksesories 1.0000 unit 70,200.00 70,200.00
Jumlah 1,101,843.75 Dibulatkan 1,101,800.00
unit ‐ Kusen Jendela (J2)Kusen Alumunium warna ukuran 4" x 1 3/4" 13.0000 m1 110,000.00 1,430,000.00 Pas. Kaca reflektif t = 8 mm 3.6000 m2 290,000.00 1,044,000.00 Fisher 12.0000 bh 1,800.00 21,600.00 upah potong kaca 3.6000 m2 12,375.00 44,550.00 Upah pasang dan Aksesories 1.0000 unit 70,200.00 70,200.00
Jumlah 2,610,350.00 Dibulatkan 2,610,300.00
unit ‐ Kusen Jendela (J5)Kusen Alumunium warna ukuran 4" x 1 3/4" 5.4000 m1 110,000.00 594,000.00 Pas. Kaca reflektif t = 6 mm 0.9800 m2 236,000.00 231,280.00 Fisher 6.0000 bh 1,800.00 10,800.00 upah potong kaca 0.9800 m2 12,375.00 12,127.50 Upah pasang dan Aksesories 1.0000 unit 70,200.00 70,200.00
Jumlah 918,407.50 Dibulatkan 918,400.00
unit ‐ Kusen Jendela (J6/6a)Kusen Alumunium warna ukuran 4" x 1 3/4" 9.1000 m1 110,000.00 1,001,000.00 Pas. Kaca reflektif t = 8 mm 2.8800 m2 290,000.00 835,200.00 Fisher 10.0000 bh 1,800.00 18,000.00 upah potong kaca 2.2500 m2 12,375.00 27,843.75 Upah pasang dan Aksesories 1.0000 unit 70,200.00 70,200.00
Jumlah 1,952,243.75 Dibulatkan 1,952,200.00
unit ‐ Kusen Jendela (J3)Pas. Kaca reflektif t = 6 mm 0.3500 m1 236,000.00 82,600.00 Pasangan U alumunium 3.3600 m2 58,000.00 194,880.00 upah potong kaca 0.3500 bh 12,375.00 4,331.25 Upah pasang dan Aksesories 1.0000 unit 70,200.00 70,200.00
Jumlah 352,011.25 Dibulatkan 352,000.00
unit ‐ Kusen Jendela (J4)Kusen Alumunium warna ukuran 4" x 1 3/4" 2.2000 m1 110,000.00 242,000.00 Kaca Es 5 mm 0.3000 m2 180,000.00 54,000.00 upah potong kaca 0.3000 m1 12,375.00 3,712.50 Upah pasang dan Aksesories 1.0000 unit 70,200.00 70,200.00
Jumlah 369,912.50 Dibulatkan 369,900.00
unit ‐ Kusen Jendela (J4a)Kusen Alumunium warna ukuran 4" x 1 3/4" 2.2000 m1 110,000.00 242,000.00 Kaca Es 5 mm 0.2600 m2 180,000.00 46,800.00 upah potong kaca 0.2600 m1 12,375.00 3,217.50 Upah pasang dan Aksesories 1.0000 unit 70,200.00 70,200.00
Jumlah 362,217.50 Dibulatkan 362,200.00
1 UNIT PKPintu Kaca+kaca Frameless Tempered 12mm 8.3000 m2 1,680,000.00 13,944,000.00 Floor Hings, Ex. Dexon 2.0000 set 936,000.00 1,872,000.00 Pasang Fitch Fitting Komplit 1.0000 set 495,000.00 495,000.00 Handle Stainless 2.0000 psg 445,000.00 890,000.00 Upah kerja + pasang 1.0000 unit 250,000.00 250,000.00
Jumlah 17,451,000.00 Dibulatkan 17,451,000.00
1 UNIT P1Kusen kayu kamper samarinda 0.0440 m3 6,195,100.00 272,584.40 Daun pintu panel kayu samarinda 1.7100 m2 390,900.00 668,439.00 Pas. Double Multipleks 6 mm + Teakwood 0.2000 m2 325,800.00 65,160.00 Pasang Engsel pintu nilon 4" 3.0000 bh 25,000.00 75,000.00 Pasang kunci standar 1.0000 psg 190,000.00 190,000.00 Handle Stailess Steel (Decksen) 2.0000 bh 445,000.00 890,000.00 Kaca Es 5mm 0.1700 m2 180,000.00 30,600.00
Jumlah 2,191,783.40 Dibulatkan 2,191,700.00
1 UNIT P2Kusen kayu kamper samarinda 0.0400 m3 6,195,100.00 247,804.00 Daun pintu panel kayu samarinda 1.5000 m2 390,900.00 586,350.00 Pas. Double Multipleks 6 mm + Teakwood 0.2000 m2 325,800.00 65,160.00 Pasang Engsel pintu nilon 4" 3.0000 bh 25,000.00 75,000.00 Pasang kunci standar 1.0000 bh 190,000.00 190,000.00 Handle Stailess Steel (Decksen) 2.0000 bh 445,000.00 890,000.00 Kaca Es 5mm 0.1700 m2 180,000.00 30,600.00
Jumlah 2,084,914.00 Dibulatkan 2,084,900.00
1 UNIT P6Kusen kayu kamper samarinda 0.1000 m3 6,195,100.00 619,510.00 Daun pintu panel kayu samarinda 1.7100 m2 390,900.00 668,439.00 Pas. Double Multipleks 6 mm + Teakwood 0.7500 m2 325,800.00 244,350.00
Pasang Engsel pintu nilon 4" 3.0000 bh 25,000.00 75,000.00 Pasang kunci standar 1.0000 bh 190,000.00 190,000.00 Handle Stailess Steel (Decksen) 2.0000 bh 445,000.00 890,000.00 Kaca Es 5mm 1.6500 m2 180,000.00 297,000.00
Jumlah 2,984,299.00 Dibulatkan 2,984,200.00
1 UNIT P3Kusen kayu kamper samarinda 0.0300 m3 6,195,100.00 185,853.00 Daun pintu panel kayu samarinda 1.3000 m2 390,900.00 508,170.00 Pasang Engsel pintu nilon 4" 3.0000 bh 25,000.00 75,000.00 Pasang kunci standar 1.0000 bh 190,000.00 190,000.00 Handle Stailess Steel (Decksen) 2.0000 bh 445,000.00 890,000.00 Kaca Es 5mm 0.1200 m2 180,000.00 21,600.00
Jumlah 1,870,623.00 Dibulatkan 1,870,600.00
1 UNIT P4Pintu PVC 1.0000 bh 750,000.00 750,000.00 Upah pasang 1.5100 m2 70,200.00 106,002.00
Jumlah 856,002.00 Dibulatkan 856,000.00
PEKERJAAN PARTISI1 M2 Rangka partisi besi hollow, modul 60X60 CMHollow 40X40X0,7 mm 1.1000 btg 74,000.00 81,400.00 Paku Riffet 6.0000 bj 600.00 3,600.00 Tukang 0.2260 org/hr 49,500.00 11,187.00 Pekerja 0.2160 org/hr 45,000.00 9,720.00 Mandor 0.0250 org/hr 58,500.00 1,462.50
Jumlah 107,369.50 Dibulatkan 107,300.00
1 M2 Partisi gypsumboard 9 MMGypsumboard 9 mm 0.4320 lbr 70,000.00 30,240.00 Drywall Screw 0.0400 dos 65,000.00 2,600.00 Cornice Adhesive 0.0340 zak 65,000.00 2,210.00 Catton Tape 0.0520 roll 6,500.00 338.00 Tukang 0.1220 org/hr 49,500.00 6,039.00 Pekerja 0.1080 org/hr 45,000.00 4,860.00 Mandor 0.0250 org/hr 58,500.00 1,462.50
Jumlah 47,749.50 Dibulatkan 47,700.00
Mengerjakan dinding partisi type ‐ PR1Rangka hollow 4/4 4.5625 m2 74,000.00 337,625.00 Gypsumboard 9 mm 9.1250 m2 70,000.00 638,750.00 Papan kayu 3X10 cm 3.2000 m1 14,000.00 44,800.00 List profil kayu 2X4 cm 6.4000 m1 9,000.00 57,600.00 Plint kayu 1,5/10 12.8000 m1 12,000.00 153,600.00 Paku 0.2000 kg 16,000.00 3,200.00
Jumlah 1,235,575.00 Dibulatkan 1,235,500.00
Mengerjakan dinding partisi type ‐ PR2Rangka hollow 4/4 4.1250 m2 74,000.00 305,250.00 Gypsumboard 9 mm 8.2500 m2 70,000.00 577,500.00 Papan kayu 3X10 cm 3.2000 m1 14,000.00 44,800.00 List profil kayu 2X4 cm 6.4000 m1 9,000.00 57,600.00 Plint kayu 1,5/10 12.8000 m1 12,000.00 153,600.00 Paku 0.2000 kg 16,000.00 3,200.00
Jumlah 1,141,950.00 Dibulatkan 1,141,900.00
Mengerjakan dinding partisi type ‐ PR3Rangka hollow 4/4 2.1875 m2 74,000.00 161,875.00 Gypsumboard 9 mm 4.3750 m2 70,000.00 306,250.00 Papan kayu 3X10 cm 1.4800 m1 14,000.00 20,720.00 List profil kayu 2X4 cm 2.9600 m1 9,000.00 26,640.00 Plint kayu 1,5/10 5.9200 m1 12,000.00 71,040.00 Paku 0.1000 kg 16,000.00 1,600.00
Jumlah 588,125.00 Dibulatkan 588,100.00
Mengerjakan dinding partisi type ‐ PR4Rangka hollow 4/4 3.2750 m2 74,000.00 242,350.00 Gypsumboard 9 mm 6.5500 m2 70,000.00 458,500.00 Papan kayu 3X10 cm 2.3300 m1 14,000.00 32,620.00 List profil kayu 2X4 cm 4.6600 m1 9,000.00 41,940.00 Plint kayu 1,5/10 9.3200 m1 12,000.00 111,840.00 Paku 0.1500 kg 16,000.00 2,400.00
Jumlah 889,650.00 Dibulatkan 889,600.00
PEKERJAAN LANTAI1 m2 ‐ Rabat beton 7 cm + plester dan acianPasir pasang 0.0030 m3 162,000.00 486.00 Pasir beton 0.0330 m3 153,000.00 5,049.00
Kerikil / split 0.0650 m3 190,000.00 12,350.00 Semen PC ( 50 kg ) 0.2760 zak 54,000.00 14,904.00 Pekerja 0.1150 hr 45,000.00 5,175.00 Tukang batu 0.0120 hr 49,500.00 594.00 Mandor 0.0060 hr 58,500.00 351.00
Jumlah 38,909.00 Dibulatkan 38,900.00
1 m2 ‐ Lantai keramik 20 x 20 ad.1 : 3Pasir pasang 0.0300 m3 162,000.00 4,860.00 Semen PC ( 50 kg ) 0.0337 zak 54,000.00 1,819.80 Semen warna ( cor nat ) 0.0125 kg 10,000.00 125.00 Keramik 20 x 20 standar 1.0500 m2 36,000.00 37,800.00 Pekerja 0.2816 hr 45,000.00 12,672.00 ukang batu 0.1320 hr 49,500.00 6,534.00 Mandor 0.0203 hr 58,500.00 1,187.55 Alat bantu 0.6000 set 1,000.00 600.00
Jumlah 65,598.35 Dibulatkan 65,500.00
1 m2 ‐ Lantai keramik 30 x 30 ad.1 : 3Pasir pasang 0.0300 m3 162,000.00 4,860.00 Semen PC ( 50 kg ) 0.0337 zak 54,000.00 1,819.80 Semen warna ( cor nat ) 0.0125 kg 10,000.00 125.00 Keramik 30 x 30 standar 1.0500 m2 56,000.00 58,800.00 Pekerja 0.2816 hr 45,000.00 12,672.00 Tukang batu 0.1320 hr 49,500.00 6,534.00 Mandor 0.0203 hr 58,500.00 1,187.55 Alat bantu 0.6000 set 1,000.00 600.00
Jumlah 86,598.35 Dibulatkan 86,500.00
1 m2 ‐ Lantai keramik 40 x 40 ad.1 : 3Pasir pasang 0.0300 m3 162,000.00 4,860.00 Semen PC ( 50 kg ) 0.0337 zak 54,000.00 1,819.80 Semen warna ( cor nat ) 0.0125 kg 10,000.00 125.00 Keramik standar 40 x 40 1.0500 m2 54,000.00 56,700.00 Pekerja 0.2816 hr 45,000.00 12,672.00 Tukang batu 0.1320 hr 49,500.00 6,534.00 Mandor 0.0203 hr 58,500.00 1,187.55 Alat bantu 0.6000 set 1,000.00 600.00
Jumlah 84,498.35 Dibulatkan 84,400.00
1 m2 ‐ Keramik dinding 20 x 20Pasir pasang 0.0380 m3 162,000.00 6,156.00 Semen PC ( 50 kg ) 0.0340 zak 54,000.00 1,836.00 Semen warna ( cor nat ) 0.0125 kg 10,000.00 125.00 Keramik standar 20 x 20 1.0500 m2 36,000.00 37,800.00 Pekerja 0.2620 hr 45,000.00 11,790.00 Tukang batu 0.2760 hr 49,500.00 13,662.00 Mandor 0.0263 hr 58,500.00 1,538.55 Alat bantu 0.6000 set 1,000.00 600.00
Jumlah 73,507.55 Dibulatkan 73,500.00
1 m2 ‐ Keramik dinding 20 x 25Pasir pasang 0.0380 m3 162,000.00 6,156.00 Semen PC ( 50 kg ) 0.0340 zak 54,000.00 1,836.00 Semen warna ( cor nat ) 0.0125 kg 10,000.00 125.00 Keramik standar 20 x 25 1.0500 m2 38,000.00 39,900.00 Pekerja 0.2620 hr 45,000.00 11,790.00 Tukang batu 0.2760 hr 49,500.00 13,662.00 Mandor 0.0263 hr 58,500.00 1,538.55 Alat bantu 0.6000 set 1,000.00 600.00
Jumlah 75,607.55 Dibulatkan 75,600.00
1 m1 ‐ Plint keramik standarPasir pasang 0.0030 m3 162,000.00 486.00 Semen PC ( 50 kg ) 0.0353 zak 54,000.00 1,906.20 Plint Keramik standar 0.1100 bh 2,500.00 275.00 Semen warna ( cor nat ) 0.0500 kg 10,000.00 500.00 Pekerja 0.4000 hr 45,000.00 18,000.00 Tukang batu 0.1300 hr 49,500.00 6,435.00 Mandor 0.0260 hr 58,500.00 1,521.00 Alat bantu 0.6000 set 1,000.00 600.00
Jumlah 29,723.20 Dibulatkan 29,700.00
1 m1 ‐ Plint kayu standarRangka papan kamper banjar 0.0016 m3 3,420,000.00 5,472.00 Paku segala ukuran 0.1000 kg 16,000.00 1,600.00 Pekerja 0.4000 hr 45,000.00 18,000.00 Tukang batu 0.1300 hr 49,500.00 6,435.00 Mandor 0.0260 hr 58,500.00 1,521.00
Alat bantu 0.6000 set 1,000.00 600.00 Jumlah 33,628.00
Dibulatkan 33,600.00 1 m1 ‐ Plint keramik 10x20 dinding Kamar mandiPasir pasang 0.0030 m3 162,000.00 486.00 Semen PC ( 50 kg ) 0.0353 zak 54,000.00 1,906.20 Plint keramik standar 5.0000 m1 2,500.00 12,500.00 Semen warna ( cor nat ) 0.0500 kg 10,000.00 500.00 Pekerja 0.4000 hr 45,000.00 18,000.00 Tukang batu 0.0130 hr 49,500.00 643.50 Mandor 0.0026 hr 58,500.00 152.10 Alat bantu 0.0600 set 1,000.00 60.00
Jumlah 34,247.80 Dibulatkan 34,200.00
1 m1 ‐ Border 7x20 / Plint keramik dinding Kamar mandiPasir pasang 0.0030 m3 162,000.00 486.00 Semen PC ( 50 kg ) 0.0353 zak 54,000.00 1,906.20 Border Keramik Dinding 7/20 1.0000 m1 2,500.00 2,500.00 Semen warna ( cor nat ) 0.0500 kg 10,000.00 500.00 Pekerja 0.4000 hr 45,000.00 18,000.00 Tukang batu 0.0130 hr 49,500.00 643.50 Mandor 0.0026 hr 58,500.00 152.10 Alat bantu 0.0600 set 1,000.00 60.00
Jumlah 24,247.80 Dibulatkan 24,200.00
1 m2 ‐ Lantai keramik 30 x 30 KW 1 DN warna/ anti slip ad.1 : 3Pasir pasang 0.0300 m3 162,000.00 4,860.00 Semen PC ( 50 kg ) 0.0337 zak 54,000.00 1,819.80 Semen warna ( cor nat ) 0.0125 kg 10,000.00 125.00 Keramik 30 x 30 standar 1.0500 m2 56,000.00 58,800.00 Pekerja 0.2816 hr 45,000.00 12,672.00 Tukang batu 0.1320 hr 49,500.00 6,534.00 Mandor 0.0203 hr 58,500.00 1,187.55 Alat bantu 0.6000 set 1,000.00 600.00
Jumlah 86,598.35 Dibulatkan 86,500.00
1 m' ‐ Step Noising KeramikPasir pasang 0.0030 m3 162,000.00 486.00 Semen PC ( 50 kg ) 0.0353 zak 54,000.00 1,906.20 Step Noising Keramik 3.3000 m1 6,000.00 19,800.00 Semen warna ( cor nat ) 0.0500 kg 10,000.00 500.00 Pekerja 0.0400 hr 45,000.00 1,800.00 Tukang batu 0.0130 hr 49,500.00 643.50 Mandor 0.0026 hr 58,500.00 152.10 Alat bantu 0.0600 set 1,000.00 60.00
Jumlah 25,347.80 Dibulatkan 25,300.00
PEKERJAAN PLAFOND1 m2 ‐ Rangka plafond gird 50 x 100 cm ( kayu meranti )Kayu meranti 0.0080 m3 3,060,000.00 24,480.00 Paku 0.1400 kg 16,000.00 2,240.00 Pekerja 0.1700 hr 45,000.00 7,650.00 Tukang kayu 0.2800 hr 49,500.00 13,860.00 Mandor 0.0370 hr 58,500.00 2,164.50 Alat bantu 0.6000 set 1,000.00 600.00
Jumlah 50,994.50 Dibulatkan 50,900.00
1 m2 ‐ Rangka plafond gird 60 x 60 cm ( Rangka Hollow )Hollow 20X40X0,7 mm 0.4500 btg 35,000.00 15,750.00 Hollow 40X40X0,7 mm 0.2250 btg 22,500.00 5,062.50 Wall Angle 0.2400 btg 26,000.00 6,240.00 Suspention Road 4 mm 0.9750 unit 15,000.00 14,625.00 Paku Riffet 0.0180 dos 75,000.00 1,350.00 Gypsumboard 9 mm 0.4320 lbr 70,000.00 30,240.00 Drywall Screw 0.0400 dos 65,000.00 2,600.00 Cornice Adhesive 0.0340 zak 65,000.00 2,210.00 Catton Tape 0.0520 roll 6,500.00 338.00 Tukang 0.3980 hr 49,500.00 19,701.00 Pekerja 0.3740 hr 45,000.00 16,830.00 Mandor 0.0700 hr 58,500.00 4,095.00
Jumlah 119,041.50 Dibulatkan 119,000.00
1 m2 ‐ Plafond asbes 5 mm + rangka kayu merantiKayu meranti 0.0080 m3 3,060,000.00 24,480.00 Plat asbes semen 100 x 100 cm, t = 5 mm 1.0250 lbr 23,500.00 24,087.50 Paku 0.1750 kg 16,000.00 2,800.00 Pekerja 0.2200 hr 45,000.00 9,900.00 Tukang kayu 0.3500 hr 49,500.00 17,325.00 Mandor 0.0460 hr 58,500.00 2,691.00
Alat bantu 1.0000 set 1,000.00 1,000.00 Jumlah 82,283.50
Dibulatkan 82,200.00 1 m2 ‐ Plafond gysum 9 mm + rangka kayu merantiKayu meranti 0.0080 m3 3,060,000.00 24,480.00 Gypsum 9 mm 0.5800 lbr 70,000.00 40,600.00 Paku 0.1750 kg 16,000.00 2,800.00 Pekerja 0.2200 hr 45,000.00 9,900.00 Tukang kayu 0.3500 hr 49,500.00 17,325.00 Mandor 0.0460 hr 58,500.00 2,691.00 Alat bantu 1.0000 set 1,000.00 1,000.00
Jumlah 98,796.00 Dibulatkan 98,700.00
1 m2 ‐ Plafond triplek 4 mm + rangka kayu merantiKayu meranti 0.0080 m3 3,060,000.00 24,480.00 Triplek 4 mm 0.3750 lbr 64,000.00 24,000.00 Paku 0.1750 kg 16,000.00 2,800.00 Pekerja 0.2200 hr 45,000.00 9,900.00 Tukang kayu 0.3500 hr 49,500.00 17,325.00 Mandor 0.0460 hr 58,500.00 2,691.00 Alat bantu 1.0000 set 1,000.00 1,000.00
Jumlah 82,196.00 Dibulatkan 82,100.00
1 m2 ‐ Plafond asbes 5 mm + rangka kayu merantiKayu meranti 0.0080 m3 3,060,000.00 24,480.00 Asbes 5 mm 0.3750 lbr 64,000.00 24,000.00 Paku 0.1750 kg 16,000.00 2,800.00 Pekerja 0.2200 hr 45,000.00 9,900.00 Tukang kayu 0.3500 hr 49,500.00 17,325.00 Mandor 0.0460 hr 58,500.00 2,691.00 Alat bantu 1.0000 set 1,000.00 1,000.00
Jumlah 82,196.00 Dibulatkan 82,100.00
1 m2 ‐ Plafond Gyptile 9 mm + rangka metal furing ( Main Tee/Cross Tee )Rangka Metal Main Tee/Cross Tee 2.0833 btg 24,500.00 51,040.85 Gypsum Tile 9 mm 1.3889 lbr 70,000.00 97,223.00 Clip metal 4.0000 bh 1,500.00 6,000.00 Paku Tembak 0.1750 kg 25,000.00 4,375.00 Tukang kayu 0.3500 hr 49,500.00 17,325.00 Mandor 0.0460 hr 58,500.00 2,691.00 Alat bantu 1.0000 set 1,000.00 1,000.00
Jumlah 179,654.85 Dibulatkan 179,600.00
1 m2 ‐ Plafond GRC t=5 mm + rangka besi hollowBesi Hollow 4x4 0.9375 btg 35,000.00 32,812.50 GRC Board t = 5 mm 0.3472 lbr 50,000.00 17,360.00 Paku 0.1750 kg 16,000.00 2,800.00 Pekerja 0.2200 hr 45,000.00 9,900.00 Tukang kayu 0.3500 hr 49,500.00 17,325.00 Mandor 0.0460 hr 58,500.00 2,691.00 Alat bantu 1.0000 set 1,000.00 1,000.00
Jumlah 83,888.50 Dibulatkan 83,800.00
1 m1 ‐ List Plafond Kayu Kamper Samarinda 5 cmList Profil Kamper 5 cm 1.1000 m1 9,000.00 9,900.00 Paku 0.0100 kg 16,000.00 160.00 Pekerja 0.0500 hr 45,000.00 2,250.00 Tukang kayu 0.0500 hr 49,500.00 2,475.00 Kepala Tukang Kayu 0.0050 hr 49,500.00 247.50 Mandor 0.0030 hr 58,500.00 175.50
Jumlah 15,208.00 Dibulatkan 15,200.00
1 m2 ‐ Plafond GRC + rangka kayu merantiKayu meranti 0.0080 m3 3,060,000.00 24,480.00 GRC Board 4 mm 0.5800 lbr 50,000.00 29,000.00 Paku 0.1750 kg 16,000.00 2,800.00 Pekerja 0.2200 hr 45,000.00 9,900.00 Tukang kayu 0.3500 hr 49,500.00 17,325.00 Mandor 0.0460 hr 58,500.00 2,691.00 Alat bantu 1.0000 set 1,000.00 1,000.00
Jumlah 87,196.00 Dibulatkan 87,100.00
PEKERJAAN CAT1 m2 ‐ Cat dinding dalam ( ICI )Cat setara ICI ‐ interior 0.2800 kg 35,000.00 9,800.00 Roll cat + bak 0.0100 bh 25,000.00 250.00 Plamur / dempul tembok 0.1600 kg 20,000.00 3,200.00 Ampelas 0.5000 lbr 4,000.00 2,000.00 Tukang cat 0.2950 hr 49,500.00 14,602.50
Mandor 0.0250 hr 58,500.00 1,462.50 Jumlah 31,315.00
Dibulatkan 31,300.00 1 m2 ‐ Cat dinding dalam ( Jotun )Cat setara jotun 0.2800 kg 35,000.00 9,800.00 Roll cat + bak 0.0100 bh 25,000.00 250.00 Plamur / dempul tembok 0.1600 kg 20,000.00 3,200.00 Ampelas 0.5000 lbr 4,000.00 2,000.00 Tukang cat 0.2950 hr 49,500.00 14,602.50 Mandor 0.0250 hr 58,500.00 1,462.50
Jumlah 31,315.00 Dibulatkan 31,300.00
1 m2 ‐ Cat dinding luar dengan ( ICI Weathershield )Cat setara ICI Weathershield ) 0.2800 kg 38,000.00 10,640.00 Roll cat + bak 0.0100 bh 25,000.00 250.00 Plamur / dempul tembok 0.1600 kg 20,000.00 3,200.00 Ampelas 0.5000 lbr 4,000.00 2,000.00 Tukang cat 0.2950 hr 49,500.00 14,602.50 Mandor 0.0250 hr 58,500.00 1,462.50
Jumlah 32,155.00 Dibulatkan 32,100.00
1 m2 ‐ Cat dinding luar denganVinilexCat setaraVinilex 0.2800 kg 32,000.00 8,960.00 Roll cat + bak 0.0100 bh 25,000.00 250.00 Plamur / dempul tembok 0.1600 kg 20,000.00 3,200.00 Ampelas 0.5000 lbr 4,000.00 2,000.00 Tukang cat 0.2950 hr 49,500.00 14,602.50 Mandor 0.0250 hr 58,500.00 1,462.50
Jumlah 30,475.00 Dibulatkan 30,400.00
1 m2 ‐ Cat dinding luar denganMetrolithCat setara Metrolith 0.2800 kg 34,000.00 9,520.00 Roll cat + bak 0.0100 bh 25,000.00 250.00 Plamur / dempul tembok 0.1600 kg 20,000.00 3,200.00 Ampelas 0.5000 lbr 4,000.00 2,000.00 Tukang cat 0.2950 hr 49,500.00 14,602.50 Mandor 0.0250 hr 58,500.00 1,462.50
Jumlah 31,035.00 Dibulatkan 31,000.00
1 m2 ‐ Cat plafond setara ICICat setara ICI 0.3000 kg 35,000.00 10,500.00 Roll cat + bak 0.0500 bh 25,000.00 1,250.00 Plamur / dempul tembok 0.0450 kg 20,000.00 900.00 Ampelas 0.2000 lbr 4,000.00 800.00 Tukang cat 0.3150 hr 49,500.00 15,592.50 Mandor 0.0250 hr 58,500.00 1,462.50
Jumlah 30,505.00 Dibulatkan 30,500.00
1 m2 ‐ Cat plafond setara JotunCat setara Jotun 0.3000 kg 35,000.00 10,500.00 Roll cat + bak 0.0500 bh 25,000.00 1,250.00 Plamur / dempul tembok 0.0450 kg 20,000.00 900.00 Ampelas 0.2000 lbr 4,000.00 800.00 Tukang cat 0.3150 hr 49,500.00 15,592.50 Mandor 0.0250 hr 58,500.00 1,462.50
Jumlah 30,505.00 Dibulatkan 30,500.00
1 m2 ‐ Cat besi memakai kuasCat besi / kayu setara F ‐ Talit 0.2000 kg 56,000.00 11,200.00 Kuas 3" 0.0500 bh 15,000.00 750.00 Minyak cat / thiner 0.1500 lt 15,000.00 2,250.00 Meni besi 0.1675 kg 35,000.00 5,862.50 Ampelas 0.4000 lbr 4,500.00 1,800.00 Tukang cat 0.3150 hr 49,500.00 15,592.50 Mandor 0.0250 hr 58,500.00 1,462.50
Jumlah 38,917.50 Dibulatkan 38,900.00
1 m2 ‐ Cat kayu memakai kuasCat besi / kayu setara F ‐ Talit 0.2000 kg 56,000.00 11,200.00 Kuas 3" 0.0500 bh 15,000.00 750.00 Plamir kayu 0.0630 kg 36,000.00 2,268.00 Meni kayu 0.1670 kg 35,000.00 5,845.00 Ampelas 0.4000 lbr 4,000.00 1,600.00 Minyak cat / thiner 0.1500 lt 15,000.00 2,250.00 Tukang cat 0.3150 hr 49,500.00 15,592.50 Mandor 0.0250 hr 58,500.00 1,462.50
Jumlah 40,968.00 Dibulatkan 40,900.00
1 m2 ‐ Cat plafond setara Vinilex
Cat setara Vinilex 0.3000 kg 32,000.00 9,600.00 Roll cat + bak 0.0500 bh 25,000.00 1,250.00 Plamur / dempul tembok 0.0450 kg 20,000.00 900.00 Ampelas 0.2000 lbr 4,000.00 800.00 Tukang cat 0.3150 hr 49,500.00 15,592.50 Mandor 0.0250 hr 58,500.00 1,462.50
Jumlah 29,605.00 Dibulatkan 29,600.00
1 m2 ‐ Pekerjaan MelamicMelamik 0.6000 kg 40,000.00 24,000.00 Alat bantu 1.0000 ls 2,500.00 2,500.00 Plamur kayu 0.0630 kg 36,000.00 2,268.00 Meni Kayu 0.1670 kg 35,000.00 5,845.00 Ampelas 0.4000 lbr 4,000.00 1,600.00 Minyak Cat / thiner 0.1500 lt 15,000.00 2,250.00 Tukang cat 0.5000 hr 49,500.00 24,750.00 Mandor 0.0250 hr 58,500.00 1,462.50
Jumlah 64,675.50 Dibulatkan 64,600.00
1 m2 ‐ Water proofing ex emultion�MortarWaterproofing ex emultion mortar 2.0000 kg 8,250.00 16,500.00 Pekerja 0.1000 hr 45,000.00 4,500.00 Tukang cat 0.1000 hr 49,500.00 4,950.00 Mandor 0.0100 hr 58,500.00 585.00
Jumlah 26,535.00 Dibulatkan 26,500.00
1 m2 ‐ Water proofing memakai kuasWater proofing 0.5000 kg 25,000.00 12,500.00 Kuas 3" 0.0500 bh 15,000.00 750.00 Ampelas 0.4000 lbr 4,000.00 1,600.00 Tukang cat 0.3150 hr 49,500.00 15,592.50 Mandor 0.0250 hr 58,500.00 1,462.50
Jumlah 31,905.00 Dibulatkan 31,900.00
PEKERJAAN SANITER1 unit ‐ Closet jongkok standarPasir pasang 0.1500 m3 162,000.00 24,300.00 Semen PC ( 50 kg ) 0.1000 zak 54,000.00 5,400.00 Closet jongkok standar 1.0000 bh 320,000.00 320,000.00 Pekerja 0.3000 hr 45,000.00 13,500.00 Tukang batu 0.2500 hr 49,500.00 12,375.00 Mandor 0.1800 hr 58,500.00 10,530.00
Jumlah 386,105.00 Dibulatkan 386,100.00
1 unit ‐ Closet DudukPasir pasang 0.1500 m3 162,000.00 24,300.00 Semen PC ( 50 kg ) 0.1000 zak 54,000.00 5,400.00 ClosetDuduk 1.0000 bh 2,500,000.00 2,500,000.00 Pekerja 0.3000 hr 45,000.00 13,500.00 Tukang batu 0.2500 hr 1,000.00 250.00 Mandor 0.1800 hr 58,500.00 10,530.00
Jumlah 2,553,980.00 Dibulatkan 2,553,900.00
1 bh ‐ Bak air fiber glass kap. 200 ltrPasir pasang 0.1500 m3 162,000.00 24,300.00 Semen PC ( 50 kg ) 0.1000 kg 54,000.00 5,400.00 Tangki air kapasitas 1 m3 1.0000 bh 800,000.00 800,000.00 Pekerja 0.1000 hr 45,000.00 4,500.00 Tukang batu 0.2500 hr 1,000.00 250.00 Mandor 0.0250 hr 58,500.00 1,462.50
Jumlah 835,912.50 Dibulatkan 835,900.00
1 bh ‐ Floor drainFloor drain kuningan 1.0000 bh 125,000.00 125,000.00 Pekerja 0.0100 hr 45,000.00 450.00 Tukang batu 0.1000 hr 49,500.00 4,950.00 Mandor 0.0050 hr 58,500.00 292.50
Jumlah 130,692.50 Dibulatkan 130,600.00
1 buah ‐ Kran air 1/2"Kran air 1/2 ex lokal 1.0000 bh 85,000.00 85,000.00 Seal tape 0.0250 roll 6,000.00 150.00 Lem pipa PVC 0.1250 tube 18,000.00 2,250.00 Pekerja 0.0100 hr 45,000.00 450.00 Tukang batu 0.1000 hr 49,500.00 4,950.00 Mandor 0.0050 hr 58,500.00 292.50
Jumlah 93,092.50 Dibulatkan 93,000.00
1 unit ‐ Pompa air jet pump + Instalasi dan pengeboran
Pompa air jet pump 1.0000 bh 4,500,000.00 4,500,000.00 Pipa PVC 1 " 40.0000 m1 9,000.00 360,000.00 Pipa PVC 4 " 16.0000 m1 28,000.00 448,000.00 Bocht LL‐D 1" (lokal) 6.0000 bh 6,000.00 36,000.00 Water moer 2.0000 bh 8,000.00 16,000.00 Ongkos pengeboran 1.0000 ls 1,200,000.00 1,200,000.00
Jumlah 6,560,000.00 Dibulatkan 6,560,000.00
1 unit ‐ Water tower rangka besi sikuKonstruksi besi siku 175.0000 kg 16,500.00 2,887,500.00 Pondasi beton tapak K. 175 0.7665 m3 2,642,800.00 2,025,706.20 Pekerja 2.5000 hr 45,000.00 112,500.00 Tukang besi 3.0000 hr 49,500.00 148,500.00 Tukang batu 3.0000 hr 49,500.00 148,500.00 Mandor 0.3000 hr 58,500.00 17,550.00
Jumlah 5,340,256.20 Dibulatkan 5,340,200.00
1 buah ‐ Tangki air kapasitas 1 m3Tangki air kapasitas 1 m3 1.0000 bh 800,000.00 800,000.00 Pekerja 0.1000 hr 45,000.00 4,500.00 Tukang batu 0.2500 hr 49,500.00 12,375.00 Mandor 0.0250 hr 58,500.00 1,462.50
Jumlah 818,337.50 Dibulatkan 818,300.00
1 unit ‐ Sumur ResapanPas batu bata, t = 1/2 bata ad 1 : 2 4.0000 m2 107,700.00 430,800.00 Pasir urug unt rembesan 0.3000 m3 135,000.00 40,500.00 Batu Kali 1.0000 m3 180,000.00 180,000.00 Koral beton unt. rembesan 0.1500 m3 190,000.00 28,500.00 Plesteran dan acian trasraam ad. 1 : 3 4.0000 m2 38,300.00 153,200.00 Plat beton penutup t = 12 cm (beton site mix K. 175) 0.2028 m3 #REF! #REF!Besi beton polos 14.2200 kg 8,000.00 113,760.00 Pipa PVC 1 " 0.5000 m1 9,000.00 4,500.00 Pipa porous 4 " 1.0000 m1 28,000.00 28,000.00 Ijuk 15.0000 ikat 30,000.00 450,000.00 Pekerja 1.2500 hr 45,000.00 56,250.00 Tukang batu 1.5000 hr 49,500.00 74,250.00 Mandor 0.0500 hr 58,500.00 2,925.00
Jumlah #REF!Dibulatkan #REF!
1 unit ‐ Septictank & Rembesan + InstalasiPas batu bata, t = 1/2 bata ad 1 : 2 12.5000 m2 107,700.00 1,346,250.00 Pasir urug unt rembesan 0.3000 m3 135,000.00 40,500.00 Koral beton unt. rembesan 1.5080 m3 190,000.00 286,520.00 Plesteran dan acian trasraam ad. 1 : 3 11.3400 m2 38,300.00 434,322.00 Plat beton penutup t = 12 cm (beton site mix K. 175) 0.3600 m3 #REF! #REF!Besi beton polos 47.4000 kg 8,000.00 379,200.00 Pipa PVC 1 " 0.5000 m1 9,000.00 4,500.00 Pipa porous 4 " 3.0000 m1 30,000.00 90,000.00 Ijuk 30.0000 ikat 30,000.00 900,000.00 Pekerja 2.5000 hr 45,000.00 112,500.00 Tukang batu 3.0000 hr 49,500.00 148,500.00 Mandor 0.0500 hr 58,500.00 2,925.00
Jumlah #REF!Dibulatkan #REF!
1m' ‐ Instalasi air bersih, dari water tower ke ‐ kran airPipa PVC 3/4" 1.2000 m1 6,000.00 7,200.00 Knee PVC 0.2000 bh 1,500.00 300.00 Lem Pipa PVC 0.2500 tube 18,000.00 4,500.00 Pekerja 0.0500 hr 45,000.00 2,250.00 Tukang Pipa / Plumbing 0.3000 hr 49,500.00 14,850.00 Mandor 0.0300 hr 58,500.00 1,755.00
Jumlah 30,855.00 Dibulatkan 30,800.00
1m' ‐ Instalasi air kotor, dari closet & Floor Drain ke SeptictankPipa PVC 4" 1.2000 m1 28,000.00 33,600.00 Knee PVC 0.2000 bh 6,500.00 1,300.00 Lem Pipa PVC 0.2500 tube 18,000.00 4,500.00 Pekerja 0.0500 hr 45,000.00 2,250.00 Tukang Pipa / Plumbing 0.3000 hr 49,500.00 14,850.00 Mandor 0.0300 hr 58,500.00 1,755.00
Jumlah 58,255.00 Dibulatkan 58,200.00
PEKERJAAN ASESORIS1 bh ‐ Pasang Engsel pintu nilon 4"Engsel nilon 4" 1.0000 bh 25,000.00 25,000.00 Pekerja 0.0150 hr 45,000.00 675.00
Tukang kayu 0.1500 hr 49,500.00 7,425.00 Mandor 0.0075 hr 58,500.00 438.75
Jumlah 33,538.75 Dibulatkan 33,500.00
1 bh ‐ Pasang Engsel jendelaEngsel nilon 3" 1.0000 bh 21,000.00 21,000.00 Pekerja 0.0100 hr 45,000.00 450.00 Tukang kayu 0.1000 hr 49,500.00 4,950.00 Mandor 0.0050 hr 58,500.00 292.50
Jumlah 26,692.50 Dibulatkan 26,600.00
1 bh ‐ Pasang hak anginHak angin 1.0000 bh 20,000.00 20,000.00 Pekerja 0.0100 hr 45,000.00 450.00 Tukang kayu 0.1000 hr 49,500.00 4,950.00 Mandor 0.0050 hr 58,500.00 292.50
Jumlah 25,692.50 Dibulatkan 25,600.00
1 bh ‐ Pasang slot jendelaSlot jendela 1.0000 bh 7,500.00 7,500.00 Pekerja 0.0100 hr 45,000.00 450.00 Tukang kayu 0.1000 hr 49,500.00 4,950.00 Mandor 0.0050 hr 58,500.00 292.50
Jumlah 13,192.50 Dibulatkan 13,100.00
1 bh ‐ Pasang slot / grendel pintuSlot pintu 1.0000 bh 25,000.00 25,000.00 Pekerja 0.0100 hr 45,000.00 450.00 Tukang kayu 0.1000 hr 49,500.00 4,950.00 Mandor 0.0050 hr 58,500.00 292.50
Jumlah 30,692.50 Dibulatkan 30,600.00
1 bh ‐ Pasang kunci double slaag (SOLID)Kunci double slaag (SOLID) 1.0000 bh 190,000.00 190,000.00 Pekerja 0.0500 hr 45,000.00 2,250.00 Tukang kayu 0.2500 hr 49,500.00 12,375.00 Mandor 0.0100 hr 58,500.00 585.00
Jumlah 205,210.00 Dibulatkan 205,200.00
1 m' ‐ Hand Ralling TanggaPipa Galv Medium dia 2 inch 1.0500 m1 34,000.00 35,700.00 Cat besi 0.1570 m2 56,000.00 8,792.00 Dynabolt 1.0000 bh 19,000.00 19,000.00 Pekerja 0.1775 hr 45,000.00 7,987.50 Tukang 0.2218 hr 49,500.00 10,979.10 Mandor 0.0226 hr 58,500.00 1,322.10 Alat bantu 1.0000 set 1,000.00 1,000.00
Jumlah 84,780.70 Dibulatkan 84,700.00
1 m' ‐ Pas.Reilling tangga Steinless�steelPipa steinlees dia. 1¼" 3.0000 m1 120,000.00 360,000.00 Pipa steinless steel dia.1" 1.0000 m1 98,000.00 98,000.00 Pipa steinless steel dia.¾" 2.0000 m1 45,000.00 90,000.00 Pekerja 0.2200 hr 45,000.00 9,900.00 Tukang 0.3500 hr 49,500.00 17,325.00 Mandor 0.0460 hr 58,500.00 2,691.00
Jumlah 577,916.00 Dibulatkan 577,900.00
1 m' ‐ Hand Ralling Tangga kayuKayu kamper Samarinda dia 50 mm 1.0500 m1 120,000.00 126,000.00 Cat kayu 0.1570 m2 56,000.00 8,792.00 Dynabolt 1.0000 bh 19,000.00 19,000.00 Pekerja 0.1775 hr 45,000.00 7,987.50 Tukang 0.2218 hr 49,500.00 10,979.10 Mandor 0.0226 hr 58,500.00 1,322.10 Alat bantu 1.0000 set 1,000.00 1,000.00
Jumlah 175,080.70 Dibulatkan 175,000.00
PEKERJAAN SARANA LUAR1 m' ‐ Saluran buis beton 1/2 dia. 30 cmBuis beton 1/2 dia. 30 cm 1.0250 m1 30,000.00 30,750.00 Pasir urug 0.1200 m3 135,000.00 16,200.00 Pasir pasang 0.0540 m3 162,000.00 8,748.00 Semen PC ( 50 kg ) 0.0270 zak 54,000.00 1,458.00 Pekerja 0.0750 hr 45,000.00 3,375.00 Tukang batu 0.0500 hr 49,500.00 2,475.00 Mandor 0.0125 hr 58,500.00 731.25
Jumlah 63,737.25 Dibulatkan 63,700.00
1 m2 ‐ Paving block t = 6 cmPaving block t = 6 cm K.250 1.0250 m2 75,000.00 76,875.00 Pasir beton 0.0250 m3 162,000.00 4,050.00 Pekerja 0.1500 hr 45,000.00 6,750.00 Tukang batu 0.0500 hr 49,500.00 2,475.00 Mandor 0.0030 hr 58,500.00 175.50
Jumlah 90,325.50 Dibulatkan 90,300.00
1 m2 ‐ Paving block t = 8 cmPaving block t = 8 cm K.250 1.0250 m2 80,000.00 82,000.00 Pasir beton 0.0250 m3 162,000.00 4,050.00 Pekerja 0.1500 hr 45,000.00 6,750.00 Tukang batu 0.0500 hr 49,500.00 2,475.00 Mandor 0.0030 hr 58,500.00 175.50
Jumlah 95,450.50 Dibulatkan 95,400.00
1 m2 ‐ Grass block uk. 20.40.6 cmGrass block 6.2500 bh 46,000.00 287,500.00 Pasir beton 0.0250 m3 162,000.00 4,050.00 Pekerja 0.1500 hr 45,000.00 6,750.00 Tukang batu 0.0500 hr 49,500.00 2,475.00 Mandor 0.0030 hr 58,500.00 175.50
Jumlah 300,950.50 Dibulatkan 300,900.00
1 m' ‐ Kanstin abu ‐ abu 10.20.40 ‐ K.175Kanstin abu ‐ abu 10.20.40 ‐ K.175 1.0000 m2 35,000.00 35,000.00 Adukan 0.0100 m3 450,000.00 4,500.00 Pekerja 0.0500 hr 45,000.00 2,250.00 Tukang batu 0.0175 hr 49,500.00 866.25 Mandor 0.0088 hr 58,500.00 511.88
Jumlah 43,128.13 Dibulatkan 43,100.00
1 m' ‐ Pagar beton precat t = 2.00 mGalian tanah pondasi 0.1200 m3 35,800.00 4,296.00 Pasir beton 0.0150 m3 162,000.00 2,430.00 Batu pecah 3/4 0.0290 m3 190,000.00 5,510.00 Semen 0.2250 zak 54,000.00 12,150.00 Tinggi pagar 5 panel/ 2 m, panjang kolom 3 m, mutu beton K225 1.0000 m 403,750.00 403,750.00 Pekerja 0.6000 hr 45,000.00 27,000.00 Tukang batu 0.3500 hr 49,500.00 17,325.00 Mandor 0.0350 hr 58,500.00 2,047.50
Jumlah 474,508.50 Dibulatkan 474,500.00
1 m' ‐ Pagar beton precat t = 2.40 mGalian tanah pondasi 0.1200 m3 35,800.00 4,296.00 Pasir beton 0.0150 m3 162,000.00 2,430.00 Batu pecah 3/4 0.0290 m3 190,000.00 5,510.00 Semen 0.2250 zak 54,000.00 12,150.00 Tinggi pagar 6 panel/ 2.4 m, pjang kolom 3.5 m, mutu beton K225 1.0000 m 403,750.00 403,750.00 Pekerja 0.6000 hr 45,000.00 27,000.00 Tukang batu 0.3500 hr 49,500.00 17,325.00 Mandor 0.0350 hr 58,500.00 2,047.50
Jumlah 474,508.50 Dibulatkan 474,500.00
1 m' ‐ Pas.Pagar Tralis�BesiGalian tanah pondasi 0.1000 m3 35,800.00 3,580.00 Urugan Tanah Kembali 0.0250 m3 14,600.00 365.00 Pas. Batu Kali 1 : 5 0.1875 m3 569,100.00 106,706.25 Sloof beton 15/20 K.175 0.0300 m3 3,558,500.00 106,755.00 Kolom beton 25/25 K.225 0.0354 m3 #REF! #REF!Kepala pagar dengan beton K.225 0.0167 m3 723,200.00 12,077.44 Pas.Batu bata 1 : 5 0.5000 m2 96,100.00 48,050.00 Plester + Acian 0.1520 m2 34,500.00 5,244.00 Pas. Batu Tempel 1.0000 m2 195,000.00 195,000.00 Pengecetan Kolom 1.5200 m2 32,100.00 48,792.00 Besi Beton Polos dia..16 9.8000 kg 8,000.00 78,400.00 Besi Beton Polos dia..10 2.2200 kg 8,000.00 17,760.00 Besi siku L.40.40.4 4.8333 kg 16,500.00 79,749.45 Tombak Beton 7.0000 bh 25,000.00 175,000.00 Pengelasan & Pengecetan 1.0000 ls 650,000.00 650,000.00 Ongkos pasang Pagar Besi 1.0000 ls 750,000.00 750,000.00
Jumlah #REF!Dibulatkan #REF!
1 m' ‐ Pas. Pintu Pagar Tralis�BesiBesi Beton Polos dia..16 18.0000 kg 8,000.00 144,000.00 Besi Beton Polos dia..10 4.9950 kg 8,000.00 39,960.00 Besi Galvanis dia. 2" 4.5000 m1 75,000.00 337,500.00
Tombak Beton 54.0000 bh 25,000.00 1,350,000.00 Pengelasan & Pengecetan 1.0000 ls 650,000.00 650,000.00 Roda Pagar 0.7500 bh 250,000.00 187,500.00 Kunci Pagar 0.2500 bh 150,000.00 37,500.00 Rel Besi 1.3000 kg 8,000.00 10,400.00 Ongkos pasang Pagar Besi 1.0000 lz 750,000.00 750,000.00
Jumlah 3,506,860.00 Dibulatkan 3,506,800.00
1 m2 ‐ Partisi double gysum 9 mm + rangka kayu meranti + List kayu papan diprofil + finish catKayu meranti 0.0210 m3 3,060,000.00 64,260.00 Gypsum 9 mm 0.7656 lbr 70,000.00 53,592.00 Paku 0.3500 kg 16,000.00 5,600.00 List papan diprofil 1.6x 9 cm(atas partisi 3muka bw 3.5714 m1 75,000.00 267,855.00 Cat dinding partisi (cat tembok) 2.0000 m2 31,300.00 62,600.00 Cat kayu 0.3571 m2 40,900.00 14,605.39 Pekerja 0.2200 hr 45,000.00 9,900.00 Tukang kayu 0.3500 hr 49,500.00 17,325.00 Mandor 0.0460 hr 58,500.00 2,691.00 Alat bantu 1.0000 hr 1,000.00 1,000.00
Jumlah 499,428.39 Dibulatkan 499,400.00
1 m' ‐ Pas.Pagar Besi�Hollow�BesiGalian tanah pondasi 0.1000 m3Urugan Tanah Kembali 0.0250 m3Pas. Batu Kali 1 : 5 0.1875 m3Sloof beton 15/20 K.175 0.0300 m3Kolom beton 25/25 K.225 0.0354 m3Kepala pagar dengan beton K.225 0.0167 m3Pas.Batu bata 1 : 5 0.5000 m2Plester + Acian 1.5200 m2Pas. Batu Tempel 1.0000 m2Pengecetan Kolom 1.5200 m2Besi Hollow (6 x 6) cm t = 2 mm 23.2000 kgBesi Hollow (4 x 4) cm t = 2 mm 9.0000 kgBesi Hollow (3 x 3) cm t = 2 mm 12.5800 kgPengelasan & Pengecetan 1.0000 lsOngkos pasang Pagar Besi 1.0000 ls
JumlahDibulatkan
1 m' ‐ Pas. Pintu Pagar Besi Hollow�BesiBesi Hollow (6 x 6) cm t = 2 mm 33.8333 kgBesi Hollow (4 x 4) cm t = 2 mm 14.0000 kgBesi Hollow (3 x 3) cm t = 2 mm 17.9667 kgPengelasan & Pengecetan 1.0000 lsRoda Pagar 1.0000 bhKunci Pagar 0.2500 bhRel Besi 1.3000 kgOngkos pasang Pagar Besi 1.0000 lz
JumlahDibulatkan
PEKERJAAN MEKANIKAL ELEKTRIKAL1 Titik ‐ Instalasi Lampu (kabel NYM 3x2,5 mm)Kabel NYM 3x2.5 mm 5.0000 m 35,000.00 175,000.00 Klem kabel 1.0000 dos 20,000.00 20,000.00 Pipa PVC AW 1/2" 2.0000 m 7,000.00 14,000.00 Pembantu Instalator 0.3715 hr 45,000.00 16,717.50 Instalator 0.1050 hr 54,000.00 5,670.00 Mandor 0.0050 hr 58,500.00 292.50
Jumlah 231,680.00 Dibulatkan 231,600.00
1 Titik ‐ Instalasi Saklar/Stop Kontak (kabel NYM 3x2,5 mm)Kabel NYM 3x2.5 mm 5.0000 m 35,000.00 175,000.00 Klem kabel 1.0000 dos 20,000.00 20,000.00 Pipa PVC AW 1/2" 2.0000 m 7,000.00 14,000.00 Pembantu Instalator 0.3715 hr 45,000.00 16,717.50 Instalator 0.1050 hr 54,000.00 5,670.00 Mandor 0.0050 hr 58,500.00 292.50
Jumlah 231,680.00 Dibulatkan 231,600.00
1 Bh ‐ Pasang Saklar TunggalSaklar tunggal 1.0000 bh 20,000.00 20,000.00 Pembantu Instalator 0.2500 hr 45,000.00 11,250.00 Instalator 0.1500 hr 54,000.00 8,100.00 Mandor 0.0050 hr 58,500.00 292.50
Jumlah 39,642.50 Dibulatkan 39,600.00
1 Bh ‐ Pasang Saklar GandaSaklar ganda 1.0000 bh 24,000.00 24,000.00 Pembantu Instalator 0.2500 hr 45,000.00 11,250.00
Instalator 0.1500 hr 54,000.00 8,100.00 Mandor 0.0050 hr 58,500.00 292.50
Jumlah 43,642.50 Dibulatkan 43,600.00
1 Bh ‐ Pasang Stop Kontak ACStop Kontak AC 1.0000 bh 22,000.00 22,000.00 Pembantu Instalator 0.2500 hr 45,000.00 11,250.00 Instalator 0.1500 hr 54,000.00 8,100.00 Mandor 0.0050 hr 58,500.00 292.50
Jumlah 41,642.50 Dibulatkan 41,600.00
1 Bh ‐ Box Sekring 2 MCB 10 AmpereBox MCB 1.0000 bh 150,000.00 150,000.00 Kabel NMY 3x2,5 mm 5.0000 m1 35,000.00 175,000.00 MCB 10 Ampere 2.0000 bh 35,000.00 70,000.00 Tukang listrik 0.1045 hr 45,000.00 4,702.50 Mandor 0.0050 hr 58,500.00 292.50 Alat bantu 0.3000 set 600.00 180.00
Jumlah 400,175.00 Dibulatkan 400,100.00
1 titik ‐ Lampu TL 2 x 18 watt setara philips (inbouw) termasuk bahan komplitLampu TL 2 x 18 watt, armatur, komplit philips 1.0000 bh 346,000.00 346,000.00 Pembantu instalator 0.3132 hr 45,000.00 14,094.00 Instalator 0.1045 hr 54,000.00 5,643.00 Mandor 0.0050 hr 58,500.00 292.50 Alat bantu 0.3000 set 600.00 180.00
Jumlah 366,209.50 Dibulatkan 366,200.00
1 titik ‐ Lampu SL 18 watt setara philips (inbouw) termasuk bahan komplitLampu SL 18 watt, armatur, komplit philips 1.0000 bh 42,000.00 42,000.00 Fitting keramik 1.0000 bh 15,000.00 15,000.00 Pekerja 0.3132 hr 45,000.00 14,094.00 Tukang listrik 0.1045 hr 49,500.00 5,172.75 Mandor 0.0050 hr 58,500.00 292.50 Alat bantu 0.3000 set 600.00 180.00
Jumlah 76,739.25 Dibulatkan 76,700.00
1 Bh ‐ Pasang Stop KontakStop Kontak 1.0000 bh 22,000.00 22,000.00 Pembantu Instalator 0.2500 hr 45,000.00 11,250.00 Instalator 0.1500 hr 54,000.00 8,100.00 Mandor 0.0050 hr 58,500.00 292.50
Jumlah 41,642.50 Dibulatkan 41,600.00
PEKERJAAN BONGKARAN1 m3 ‐ Bongkar struktur bangunan (manual)Pekerja 2.3520 hr 45,000.00 105,840.00 Mandor 0.0388 hr 58,500.00 2,269.80
Jumlah 108,109.80 Dibulatkan 108,100.00
1 m3 ‐ Bongkar struktur Bangunan ( dengan alat berat )Pekerja 2.3520 hr 45,000.00 105,840.00 Mandor 0.0388 hr 58,500.00 2,269.80 Kompresor kap.400 ‐ 6500 ltr/menit 0.1000 jam 260,000.00 26,000.00 Jack Hammer 0.1000 set 80,000.00 8,000.00
Jumlah 142,109.80 Dibulatkan 142,100.00
1 m2 ‐ Bongkar dinding bata merahPekerja 0.1000 hr 45,000.00 4,500.00 Mandor 0.0250 hr 58,500.00 1,462.50
Jumlah 5,962.50 Dibulatkan 5,900.00
1 m2 ‐ Bongkar lantai�keramikPekerja 0.0800 hr 45,000.00 3,600.00 Mandor 0.0250 hr 58,500.00 1,462.50
Jumlah 5,062.50 Dibulatkan 5,000.00
1 m2 ‐ Bongkar GentengPekerja 0.0400 hr 45,000.00 1,800.00 Mandor 0.0100 hr 58,500.00 585.00 Alat bantu 1.0000 set 1,000.00 1,000.00
Jumlah 3,385.00 Dibulatkan 3,300.00
1 m2 ‐ Bongkar rangka atapPekerja 0.2000 hr 45,000.00 9,000.00 Tukang kayu 0.0550 hr 49,500.00 2,722.50 Mandor 0.0102 hr 58,500.00 596.70 Alat bantu 1.0000 set 1,000.00 1,000.00
Jumlah 13,319.20 Dibulatkan 13,300.00
1 m2 ‐ Bongkar plafondPekerja 0.1250 hr 45,000.00 5,625.00 Mandor 0.0500 hr 58,500.00 2,925.00 Alat bantu 1.0000 set 1,000.00 1,000.00
Jumlah 9,550.00 Dibulatkan 9,500.00
1 m2 ‐ Pekerjaan kupasan dindingPekerja 0.0500 hr 45,000.00 2,250.00 Mandor 0.0250 hr 58,500.00 1,462.50 Alat bantu 1.0000 set 1,000.00 1,000.00
Jumlah 4,712.50 Dibulatkan 4,700.00
1 m2 ‐ Pekerjaan dinding bataPekerja 0.3300 hr 45,000.00 14,850.00 Mandor 0.0330 hr 58,500.00 1,930.50 Alat bantu 2.0000 set 1,000.00 2,000.00
Jumlah 18,780.50 Dibulatkan 18,700.00
1 m2 ‐ Bongkar pintu besiPekerja 0.3300 hr 45,000.00 14,850.00 Mandor 0.0330 hr 58,500.00 1,930.50 Alat bantu 2.0000 set 1,000.00 2,000.00
Jumlah 18,780.50 Dibulatkan 18,700.00
1 m1 ‐ Bongkaran karpusan genteng morando�glasuurPekerja 0.0500 hr 45,000.00 2,250.00 Mandor 0.0225 hr 58,500.00 1,316.25 Alat bantu 1.0000 set 1,000.00 1,000.00
Jumlah 4,566.25 Dibulatkan 4,500.00
1 m1 ‐ Bongkaran listplank 3 / 30 + 3 / 15 kayu kamper banjar�glasuurPekerja 0.0840 hr 45,000.00 3,780.00 Mandor 0.1680 hr 58,500.00 9,828.00 Alat bantu 0.0216 set 1,000.00 21.60
Jumlah 13,629.60 Dibulatkan 13,600.00
1 kg ‐ Bongkar konstruksi gording besi�glasuurPekerja 0.0600 hr 45,000.00 2,700.00 Tukang besi 0.0045 hr 49,500.00 222.75 Mandor 0.0025 hr 58,500.00 146.25 Erection 1.0000 kg 4,500.00 4,500.00
Jumlah 7,569.00 Dibulatkan 7,500.00
NO NAMA BAHAN/MATERIAL HARGA SATUAN SATUAN
1 2 3 4I PASIR DAN BATU
Abu batu/screening 5 mm 185,000.00 m3Batu Pallmanan uk. 10X20 cm 195,000.00 m2Batu Belah Pondasi 180,000.00 m3Batu Pecah/Split ukr. 1‐2 cm 200,000.00 m3Batu pecah/Split ukr. 2‐3 cm 190,000.00 m3Batu Pecah/Split ukr. 3 ‐ 4 cm 190,000.00 m3Macadam/Steel Slag ukr. 5 ‐ 7 cm 190,000.00 m3Batu Tempel Hitam 650,000.00 m3Koral Beton 162,000.00 m3Pasir Beton 153,000.00 m3Pasir pasang 162,000.00 m3Pasir urug darat 135,000.00 m3Sirtu 144,000.00 m3Tanah Merah 35,000.00 m3
II PAVING BLOCKKastin Abu‐abu ukr. 10.20.40 K 250 35,000.00 m1Kastin Abu‐abu ukr. 10.20.40 K 300 39,000.00 mlPaving Block K 250 Tebal 6 Abu‐abu 75,000.00 m2Paving Block K 250 Tebal 8 Abu‐abu 80,000.00 m2Paving Block K 350 Tebal 6 Abu‐abu 86,000.00 m2Paving Block K 350 Tebal 8 Abu‐abu 94,000.00 m2Pagat panel beton 403,750.00 m2
III SEMEN DAN KAPURBata merah 600.00 bhBataco (bhn Semen + Pasir + Abu Batu) 1,200.00 bhBatako Putih / Hebel 6,500.00 bhRooster Beton 20 x 20 x 7 cm 20,000.00 bhGlass block 46,000.00 bhSemen Cibinong (Holcim) 40 kg 48,000.00 zakSemen Tiga Roda 50 kg 54,000.00 zakSemen Putih Tiga Roda 40 kg 80,000.00 zakSemen Warna 10,000.00 kgCornese 65,000.00 zak
IV KAYUKaso kayu Meranti Jambi/Palembang ‐ 400 cm 3,060,000.00 m3Kayu Kaso terentang 5/7‐400 cm 1,800,000.00 m3Balok Kayu Kamper Kruing/ Medan / Banjar ‐ 400 cm 3,780,000.00 m3Balok Kayu Meranti Jambi/palembang ‐ 400 cm 2,880,000.00 m3Papan Kayu Kamper Kruing/ Medan/Banjar (oven) ‐ 400 cm 3,420,000.00 m3Papan Kayu Kamper Singkil (oven) ‐ 400 cm 3,240,000.00 m3Papan Kayu Meranti (oven) ‐ 400 cm 3,600,000.00 m3Papan Kayu Terentang ‐ 400 cm 1,440,000.00 m3Papan kayu 3X10 cm 16,000.00 m'Dolken Ø 5 ‐ 7 cm ukr. 300 ‐ 400 cm 36,000.00 btgDolken Ø 8 ‐ 10 cm ukr. 350 ‐ 400 cm 43,000.00 btgList Gypsum 7 cm 12,000.00 m1List Gypsum 10 cm 15,000.00 m1List profil kamper 5 Cm 9,000.00 m1List Profil Kamper 2 cm 6,000.00 m1Plint kayu 1,5/10 12,000.00 m1Catur kayu kamper 54,000.00 bhHand Railling 162,000.00 m1Balok Kayu Kamper Samarinda Oven : 6x15x400 cm 4,000,000.00 m3Papan Kayu Kamper Samarinda Oven : 3x30x400 cm 4,200,000.00 m3Daun Pintu Kayu Kamper Samarinda (Bukan Oven) 600,000.00 unitDaun Pintu Kayu Kamper Samarinda Kualitas Export (Oven) 800,000.00 unitBahan plafond hardplex 5 mm 120x240 84,000.00 lbrBahan plafond asbes semen 5 mm 20,000.00 lbrBlock teak 122 x 244 tebal 18 mm 1 muka 200,000.00 lbrFormika ukr. 122 x 244 x 3 mm 220,000.00 lbrGRC Board 6 mm 50,000.00 lbrGypsum 9 mm 120 x 240 ex. DN 70,000.00 lbrCornice Adhesive 160,000.00 zakCotton tape 8,000.00 rollKusen dan Daun Pintu PVC ukuran standar 750,000.00 unitMelamin 122 x 244 x 3 mm 95,000.00 lbr
HARGA SATUAN DASARBAHAN / MATERIAL DAN UPAH KERJA
Multiplek ukr. 122 x 244 x 9 mm 140,000.00 lbrMultiplek ukr. 122 x 244 x 12 mm 180,000.00 lbrMultiplek ukr. 122 x 244 x 15 mm 200,000.00 lbrMultiplek ukr. 122 x 244 x 18 mm 245,000.00 lbrTeak Wood ukr. 90 x 210 x 3 mm 60,000.00 lbrTeak Wood ukr. 122 x 244 x 3 mm 74,000.00 lbrTeakwood ukr. 90 x 210 x 4 mm 65,000.00 lbrTeakwood ukr. 122 x 244 x 4 mm 82,000.00 lbrTriplek ukr. 122 x 244 x 3 mm 52,000.00 lbrTriplek ukr. 122 x 244 x 4 mm 64,000.00 lbrTriplek ukr. 122 x 244 x 6 mm 78,000.00 lbrBambu cerucuk 23,500.00 btgDraywall Sdrew 65,000.00 dosCatton 6,500.00 roll
V READYMIX m3Readymix beton K‐125 tanpa pompa 580,000.00 m3Readymix beton K‐175 tanpa pompa 615,000.00 m3Readymix beton K‐225 tanpa pompa 650,000.00 m3Readymix beton K‐250 tanpa pompa 705,000.00 m3Readymix beton K‐300 tanpa pompa 755,000.00 m3Readymix beton K‐350 tanpa pompa 825,000.00 m3Readymix beton K‐400 tanpa pompa 895,000.00 m3
VI BETONBuis BetonBuis Beton Ukuran .Ø 20 cm tanpa tulangan panjang 1,00 m Lokal 40,000.00 m1Buis Beton Ukuran .Ø 30 cm tanpa tulangan panjang 1,00 m lokal 52,000.00 m1Buis Beton Ukuran .Ø 40 cm tanpa tulangan panjang 1,00 m Lokal 68,000.00 m1Buis Beton Ukuran .Ø 50 cm tanpa tulangan panjang 1,00 m Lokal 112,000.00 m1Buis Beton Ukuran .Ø 60 cm tanpa tulangan panjang 1,00 m K 400 134,000.00 m1Buis Beton Ukuran .Ø 60 cm tanpa tulangan panjang 1,00 m Lokal 120,000.00 m1Buis Beton Ukuran .Ø 80 cm tanpa tulangan panjang 1,00 m K 400 206,000.00 m1Buis Beton Ukuran .Ø 80 cm tanpa tulangan panjang 1,00 m Lokal 180,000.00 m1Buis Beton Ukuran .Ø 100 cm tanpa tulangan panjang 1,00 m K 400 242,000.00 m1Buis Beton Ukuran .Ø 100 cm tanpa tulangan panjang 1,00 m Lokal 230,000.00 m1Buis Beton Ukuran .1/2 Ø 100 cm tanpa tulangan panjang 1,00 m lokal 246,000.00 btgBuis Beton Ukuran .1/2 Ø 80 cm tanpa tulangan panjang 1,00 m lokal 146,000.00 btgBuis Beton Ukuran .1/2 Ø 20 cm tanpa tulangan panjang 1,00 m lokal 24,000.00 btgBuis Beton Ukuran .1/2 Ø 30 cm tanpa tulangan panjang 1,00 m lokal 30,000.00 btgBuis Beton Ukuran .1/2 Ø 40 cm tanpa tulangan panjang 1,00 m lokal 48,000.00 btgBuis Beton Ukuran .1/2 Ø 50 cm tanpa tulangan panjang 1,00 m lokal 86,000.00 btgBuis Beton Ukuran .1/2 Ø 60 cm tanpa tulangan panjang 1,00 m lokal 120,000.00 btg
VII C A T lbrAmplas Kayu 4,000.00 lbrAmpelas Besi 4,500.00 kgBahan pelitur Kripik ( sirlak india) 30,000.00 kgCat besi setara F Talit 56,000.00 kgCat Besi setara Glotek 40,000.00 kgCat besi setara seiv 45,000.00 kgCat tembok setara Jotun Interior 35,000.00 kgCat tembok setara Jotun Exterior 45,000.00 kgCat tembok Dulux/ICI interior 35,000.00 kgCat tembok Dulux/ICI exterior 38,000.00 kgCat tembok setara Vinilex 32,000.00 kgCat tembok setara Metrolith 34,000.00 kgCat dasar setara Dulux/ICI 30,000.00 kgDempul halus/Infra 52,000.00 kgDempul plitur 50,000.00 kgIjuk 30,000.00 ikatKwas 3" 15,000.00 bhMelamik 40,000.00 kgMeni Besi setara Nippon 35,000.00 kgMeni Kayu setara Nippon 35,000.00 kgMinyak Cat/Tinner 15,000.00 ltrOker 18,000.00 kgPelamir Tembok 15,000.00 kgPelitur 55,000.00 kgPelumas 12,000.00 ltrPlamur Tembok setara Matek/Metrolite 20,000.00 kgPlamur Kayu/Dempul Kayu 36,000.00 kgResidu 15,000.00 kgRool cat tembok 25,000.00 bhSapu Lidi 15,000.00 ikatSoda Api 10,000.00 kgSpirtus 7,500.00 ltrThiner A 15,000.00 ltr
Thiner B 17,500.00 ltrVernis Bee Brand 66 (kayu/besi) 60,000.00 ltr
VIII LANTAIUbin Keramik Ukr. 10x20 Standar KW 2 26,000.00 m2Ubin Keramik Ukr. 10x20 Standar KW 1 30,000.00 m2Border Keramik Dinding 7/20 30,000.00 m1Ubin Keramik Ukr. 20x20 Standar KW 2 32,000.00 m2Ubin Keramik Ukr. 20x20 Standar KW 1 36,000.00 m2Ubin Keramik Ukr. 20x25 Standar KW1 38,000.00 m2Ubin Keramik Ukr. 20x25 Standar KW2 32,000.00 m2Ubin Keramik Ukr. 30x30 Standar KW 2 30,000.00 m2Ubin Keramik Ukr. 30x30 Standar KW 1 56,000.00 m2Ubin Keramik Ukr. 40x40 Standar KW 2 45,000.00 m2Ubin Keramik Ukr. 40x40 Standar KW 1 54,000.00 m2Ubin Keramik 10x20 dan 20x20 KW1 DN Standar 38,000.00 m2Ubin Keramik 10 x 25 Standar KW 2 32,000.00 m2Ubin Keramik 20 x 25 Standar KW 1 38,000.00 m2Ubin Keramik 30x30 KW1 DN warna/corak/anti slip 42,000.00 m2Step noising Keramik 10 x 30 6,000.00 bhPlint Keramik 2,500.00 bh
IX ALAT PENGUNCIEngsel Pintu Nilon ukuran 3" 21,000.00 psEngsel Pintu Nilon ukuran 4" 25,000.00 psEngsel Piano (RRC) 28,000.00 psEngsel Stainless Stell setara YANK 3" 58,000.00 psEngsel Stainless Stell setara YANK 4" 74,000.00 psEngsel Stainless stell setara Dekon/Poloma uk. 3" 68,000.00 psEngsel Stainless stell setara Dekon/Poloma uk. 4" 115,000.00 psEngsel Jendela Casemen 3 " 26,000.00 setEngsel Jendela Casemen 4" 38,000.00 setKunci Double Slaag setara Solid 190,000.00 bhGembok 60mm merk AXEL 54,000.00 bhGrendel Ukuran 4" setara Solid 18,000.00 bhGrendel Ukuran 6" setara Solid 24,000.00 bhGrendel Ukuran 4" setara Dekon 46,000.00 bhGrendel Ukuran 6" setara Dekon 58,000.00 bhSlot Jendela 7,500.00 bhSlot Pintu 25,000.00 bhHak Angin 20,000.00 setFloor Hings, Ex. Dexon 936,000.00 setFitch Fitting Komplit, Ex. Dexon 495,000.00 setHandle Stainless 445,000.00 psg
X SANITASI AIRBak mandi Alco Piber uk. 65x65 cm 300,000.00 bhCloset Duduk CW 660 J/ SW 660 J Rough ‐ in : 230 m 2,500,000.00 bhColset Jongkok Merk Toto Tipe Standar 320,000.00 bhFloor Drain Kuningan 125,000.00 bhKran Air TOTO 1/2" 85,000.00 bhSealtape 6,000.00 bhLem Pipa PVC 18,000.00 tubeLem Putih (Fox) 40,000.00 KgPompa Jet Pump 4,500,000.00 UnitPipa PVC 1/2" 4,000.00 m1Pipa PVC 3/4" 6,000.00 m1Pipa PVC 1" 9,000.00 m1Pipa PVC 2" 14,000.00 m1Pipa PVC 4" 28,000.00 m1Bocht LL‐D 1" 6,000.00 bhWater Moer 8,000.00 bhKnee PVC 3/4" 1,500.00 bhKnee PVC 1/2" 15,000.00 bhKnee PVC 4" 6,500.00 bh
XI A T A PRangka atap baja ringan 195,000.00 m2Atap genteng metal Type Stone tebal: 0,35 mm 85,000.00 m2Atap zincalume + glosswall lengkap 65,000.00 m2Bubungan genteng metal 32,500.00 m1Alumunium Foil 1 muka, medium weight (HF 404) 16,000.00 m2Glasswool 28,000.00 m2Bubungan genteng beton 4,800.00 bhBubungan Genteng ex. Jatiwangi 3,600.00 bhBubungan Genteng Kanmuri 5,200.00 bhBubungan Genteng Kodok Plentong Natural 4,500.00 bhBubungan Genteng Marundo 5,600.00 bh
Bubungan Genteng Marundo Glasur 6,000.00 bhBubungan Genteng Glasur Pelita 5,800.00 bhFiber / Asbes semen gelombang 150x105x0,4 cm 48,000.00 lbrFiber / Asbes semen gelombang 240x105x0,4 cm 62,000.00 lbrFiber / Asbes semen gelombang 270x105x0,4 cm 74,000.00 lbrFiber / Asbes semen gelombang 300x105x0,4 cm 86,000.00 lbrFiber / Asbes semen gelombang 180x108x0,5 cm 52,000.00 lbrFiber / Asbes semen gelombang 250x92x0,5 cm 64,000.00 lbrFiber / Asbes semen gelombang 210x108x0,5 cm 56,000.00 lbrFiber / Asbes semen gelombang 240x108x0,5 cm 64,000.00 lbrFiber / Asbes semen gelombang 270x108x0,5 cm 76,000.00 lbrFiber / Asbes semen gelombang 300x108x0,5 cm 86,000.00 lbrZinc Alume (tambah rangka) 228,000.00 m2Zinc Alume (Bahan) Gelombang Kecil 140,000.00 m2Zinc Alume (Bahan) Gelombang Besar 165,000.00 m2Genteng Beton Polos 2,200.00 bhGenteng beton warna 2,400.00 bhGenteng Glasur setara Pelita 6,400.00 bhGenteng Kanmuri Espanila Natural 3,000.00 bhGenteng Kodok, Plentong Natural 1,800.00 bhGenteng Morando 2,600.00 bhGenteng Morando Glasur 3,000.00 bhGenteng List plang Marundo Glasur setara Pelita 3,000.00 bhGenteng plentong ex. Jatiwangi 2,600.00 bhKusen Alumunium Natural Ukuran 3" x 1 1/2" 86,000.00 m1Kusen Alumunium Natural Ukuran 4" x 1 3/4" 98,000.00 m1Kusen Alumunium Warna Ukuran 4" x 1 3/4" 110,000.00 m1Jalusi Alumunium Warna 98,000.00 m1Frame daun Jendela Alumunium 96,000.00 m1Nok stil rata 92 cm 84,000.00 lbrNok stil rata 105 cm 116,000.00 lbrNok stil rata 108 cm 134,000.00 lbrPintu P.V.C. ex. Moradon Typ 105 E Polos lengkap kunci + Engsel 423,000.00 bhPintu P.V.C. ex. Moradon Typ 104 D Polos lengkap kunci + Engsel 415,000.00 bhPintu PVC Standard 360,000.00 bhPintu Baja Standar Lengkap Engsel + Cat Dasar 860,000.00 bhPlat Asbes 100 x 100 tebal 5 mm 19,000.00 lbPlat Asbes 100 x 100 tebal 6 mm 23,000.00 lbPlat Fiber Semen Harflek 100x100 cm tbl. 5 mm 26,000.00 lbPlat seng tebal 0,020 cm lebar 0,90 21,000.00 m1Plat seng tebal 0,030 cm lebar 0,90 26,000.00 m1Sealent 30,000.00 tubeKaret List 5,000.00 m1Seng gelombang 180 x 90 x 0,20 60,000.00 lbrGRC Lispang 30 x 240 x 0.12 cm 59,000.00 btgGRC Lispang 15 x 240 x 0.12 cm 49,000.00 btg
XII BAJA TULANGAN / PROFILBesi beton polos 8,000.00 kgBesi beton ulir 9,000.00 kgBaja IWF ex.DN SII 16,000.00 kgBaja Canal C 16,500.00 kgBesi Siku/Profil 3 x 3 x 30 mm ( 6 m) 16,500.00 kgBesi Hollow 2 x 4 cm 46,000.00 batangBesi Hollow 4 x 4 cm 54,000.00 batangBesi Hollow 4 x 4 cm x 1,8 mm 74,000.00 batangBesi Hollow 4 x 2 cm x 1,8 mm 70,000.00 batangBesi Plat Strip 2 x 30 mm, (6 m) 16,500.00 kgBesi Plat Strip 3 x 30 mm, (6 m) 16,500.00 kgDyna Bold 19,000.00 bhWall angle 26,000.00 batangSuspention Rod 4 mm 15,000.00 UnitTangki Air 1 m3 800,000.00 BhPipa steinlees dia. 1¼" 120,000.00 m1Pipa steinless steel dia.1" 98,000.00 m1Pipa steinless steel dia.¾" 45,000.00 m1
XIII KAWATKawat beton 13,000.00 kgKawat las harmonika 36,000.00 mKawat las listrik 40,000.00 kgPaku segala ukuran (rata‐rata) 16,000.00 kgPaku fisher 1,800.00 bhPaku Rifet 600.00 bhDrywall screw 34,000.00 dosWiremesh DM 8,dia.8x8,spasi 150x150mm,uk.5,4x2,1 m 89,000.00 lbrPipa Galv Medium dia 2 inch p. 6 m 34,000.00 mPagar BRC t = 0.9 m Ø 6 195,000.00 m1
XIV KACAKaca bening 2 mm 52,000.00 m2Kaca bening 3 mm 65,000.00 m2Kaca bening 5 mm 76,000.00 m2Kaca bening 8 mm 95,000.00 m2Kaca bening 10 mm 115,000.00 m2Kaca Es 3 mm 156,000.00 m2Kaca Es 5 mm 180,000.00 m2Kaca Rayben 5 mm 90,000.00 m2Kaca Rayben 8 mm 120,000.00 m2Kaca Rayben 10 mm 158,000.00 m2Kaca Rayben 12 mm 205,000.00 m2Pintu Kaca+kaca Frameless Tempered 12mm 1,680,000.00 m2Kaca Reflectif 6mm 236,000.00 m2Kaca Reflectif 8mm 290,000.00 m2
XV LISTRIKKabel NYM 3x2.5 mm 35,000.00 mKlem kabel 20,000.00 dosPipa AW 1/2" 7,000.00 mSaklar tunggal 20,000.00 bhSaklar double 24,000.00 bhStop Kontak 22,000.00 bhLampu TL 2 x 18 watt, armatur, komplit philips 346,000.00 bhLampu SL 18 watt, komplit philips 42,000.00 bhFitting Keramik 15,000.00 bh
XV SEWA ALATBuldozer 100 ‐ 150 HP 360,000.00 JamCompressor 4000‐6500 liter/menit 260,000.00 JamConcrete Vibrator 60,000.00 JamExcavator 80 ‐ 120 HP 340,000.00 JamGenerator Set 125 KVA 250,000.00 JamJack Hammer 80,000.00 JamStamper 80,000.00 JamMolen 60,000.00 Jam
XVI UPAHPekerja / knek 45,000.00 hariTukang gali 45,000.00 hariTukang Batu 49,500.00 hariTukang Kayu 49,500.00 hariTukang Besi 49,500.00 hariTukang Cat 49,500.00 hariTukang Listrik 54,000.00 hariKepala Tukang Batu 54,000.00 hariKepala Tukang Kayu 54,000.00 hariKepala Tukang Besi 54,000.00 hariKepala Tukang Cat 54,000.00 hariPembantu Instalator 45,000.00 hariInstalator 54,000.00 hariMandor / pengawas 58,500.00 hari
JADWAL PELAKSANAAN PEKERJAAN
PROYEK : REHAB GEDUNGLOKASI : MTsN 27 JOGLO, JAKARTA BARATTAHUN ANGGARAN : ABPN‐P T.A 2011
BULANNO BOBOT
1 2 3 4
I PEKERJAAN PERSIAPAN1. Papan Nama Proyek 0.519 0.519 100%
BULAN%
URAIAN PEKERJAAN MINGGU
2. Photo Proyek 3 Phase Color 0.462 0.231 0.231 3. Air Kerja 0.941 0.235 0.235 0.235 0.235 4. Pembersihan Lokasi dan Mobilisasi 1.196 0.598 0.598 50%
II PEKERJAAN ARSITEKTUR1. PEKERJAAN BONGKARAN 2.296 1.148 1.148 2. PEKERJAAN KERAMIK 39.729 13.243 13.243 13.243 3. PEKERJAAN PENGECATAN (FINISHING) 54.857 18.286 18.286 18.286
Jumlah Bobot (%) 100.00 Kemajuan Pekerjaan (%) 1.583 32.912 32.912 32.593Komulatif Kemajuan Pekerjaan (%) 1.583 34.495 67.407 100.000