federal republic of nigeria - adamawa state government
-
Upload
khangminh22 -
Category
Documents
-
view
3 -
download
0
Transcript of federal republic of nigeria - adamawa state government
FEDERAL REPUBLIC OF NIGERIA
ADAMAWA STATE GOVERNMENT RURAL ACCESS & MOBILITY PROJECT (RAMP II)
DETAILED ENGINEERING, SAFEGUARDS STUDIES AND PREPARATION OF BIDDING DOCUMENTS
FOR PRIORITIZED ROADS IN ADAMAWA STATE (RAMP II)
PREPARED BY
YAROSON PARTNERSHIP LIMITED, NIGERIA
CLIENT
National Coordinator
Federal Project Management Unit
Rural Access & Mobility Project (RAMP)
Federal Ministry of Agriculture & Rural
Development
NAIC House, Plot 590, Zone AO
Along Airport Road, Central Area
Abuja - Nigeria.
JUNE, 2012
CONSULTANTS YAROSON PARTNERSHIP LIMITED
Halford Pavey House
IB Aliyu Turaki Road,
P. O. Box 843, Kaduna, Nigeria.
Email: [email protected]
AND Plot 576 Mobolaji Crescent
Gudu - Abuja, Nigeria.
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
i
TABLE OF CONTENTS
Content Page
Table of contents
List of Tables
List of Figures and Plates
List of Appendices
List of Acronyms
i
iv
v
vi
vi
Executive Summary vii
1.0 PROJECT BACKGROUND AND DESCRIPTION
1.1 Introduction
1.2 Project Background
1.3 Project objective
1.4 Existing Condition of the Roads
1.5 The Scope of Work (ToR)
1.6 The Study Approach and Methodology
1.7 Interactive Discussions and Consultations
1
1
1
1
1
4
4
9
2.0 POLICY, LEGAL ADMINSTRATIVE & INSTITUTIONAL FRAMEWORK
2.1 Introduction
2.2 Relevant Regulatory Instruments
2.2.1 World Bank Operational Policies
2.2.2 Federal Government of Nigeria (FGN) Acts
2.3 Safeguard Policies that Apply to the RAMPII Adamawa Project
12
12
12
12
13
14
3.0 DESCRIPTION OF PROJECT
3.1 Project activities
3.1.1 Project Design
3.1.2 Design Criteria and Standards
3.1.3 Geometric Design Standards
3.1.4 Pavement Structure
3.1.5 Culvert Types
3.1.6 Construction Materials
3.2 Safeguard Sustainability Issues
15
16
16
17
17
17
17
17
19
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
ii
Content Page
4.0 BASELINE CONDITIONS
4.1 Physical Conditions
4.2 Biodiversity
4.2.1 Species Diversities
4.3 Settlement pattern
4.4 Population and Demographic characteristics
4.5 Ethnic Composition
4.6 Soil Types
4.7 Air Quality
4.8 Noise Pollution
21
21
21
21
21
21
22
23
26
26
5.0 SUMMARY OF POTENTIAL IMPACTS
5.1 Impact Identification and Analyses
5.2 Nature of impacts
5.3 Analyses of project alternatives
27
27
27
34
6.0 ENVIRONMENTAL/SOCIO-ECONOMIC IMPACTS MITIGATION
MEASURES
6.1 Summary of Negative Impacts and Mitigation Measures by Activity
6.2 Integrating Impact Mitigation into Bidding and Contract Document
6.2.1 General Clauses
36
36
37
38
7.0 ENVIRONMENTAL AND SOCIO-ECONOMIC MANAGEMENT
FRAMEWORK
7.1 Introduction
7.2 Key Stakeholders
7.3 Key Actions and Responsibilities
7.4 Monitoring
7.4.1 Environmental and Socio-Economic Compliance Monitoring
7.5 Waste /Environmental Management
7.6 Measures for Strengthing Institutional and Organisational Capacity
7.7 Capacity of CBOs and local institutions
7.8 Perception of the proposed road project
42
42
42
42
42
42
46
54
55
8.0 SUMMARY AND CONCLUSION
8.1 Summary
8.2 Conclusion
56
57
58
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
iii
LIST OF TABLES
Content Page
Table1.1 Summary of Roads Selected for Upgrading in Adamawa State,
RAMP 2
Table 1.2
Table 2.1
Consultations at Various Critical Communities along the Road
Routes.
Triggered safeguard policies
9
14
Table 3.1 Summary of the Road Project Activities 15
Table 3.2 Road Construction Materials and their Sources 18
Table 3.3 Sustainability of Roads 20
Table 4.1 Census Population Figures for Adamawa State RAPM Communities
(2006) 23
Table 4.2 Soil Fertility Tests Results from Project Area 24
Table 4.3 Summary of Baseline Environmental Conditions for Adamawa State 25
Table 5.1 Summary of potential negative impacts and mitigations 28
Table 5.2 Site - specific negative environmental impacts with mitigation 29
Table 5.3 Site - specific negative socio-economic impacts with mitigation 30
Table 5.4 (a)
Table 5.4 (b)
Table 5.4 (c)
Table 5.4 (d)
Some Regulatory Standards for Air Quality
Guidelines Governing Exposures to Noise
Water Quality Standards (National Waters)
Noise Levels Construction Equipment are likely to Generate during
Construction
32
33
Table 6.1
Table 6.2
Potential Negative Impacts of the RAMPII Adamawa Project and
Mitigations
Summary of Mitigation Implementation by Road Cluster
36
39
Table 7.1 Responsibilities of Key Stakeholders 43
Table 7.2 Project Monitoring Indicators 47
Table 7.3 Environmental/ Socioeconomic Management Plan (ESMP),
Mitigation Measures with Responsibilities and Cost 49
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
iv
LIST OF FIGURES AND PLATES
Content Page
Fig. 2.1 Adamawa State Showing the 21 LGAs 3
Plate 1 Exsisting road ravaged by erosion in Zah area, Michika LGA 2
Plate 2 Consultations with community women (Kebali) 8
Plate 3 Consultations with community members (Kebali) 8
Plate 4 Consultations with community women (Yanga) 8
Plate 5 Consultations with community members (Yanga) 8
Plate 5 PAP at Dubwangun along the road 10
Plate 6 Cross section of Consultees at Dubwangun 10
Plate 7 Consulation at the chief’s palaces at Bille 10
Plate 8 Consultation at village square in Bille 10
Plate 9 Proposed new alignment at Kodomun 10
Plate 10 Cross-Section of consultees at kodomun (Chief in the background) 10
Plate 11 Some chiefs at palace in Borrong during consultation 11
Plate 12 Consultees outside the palace at Borrong 11
Plate 13 Road route terminating at palace in Borrong.(proposed by the chiefs) 11
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
v
LIST OF APPENDICES
Content
Appendix 1: Photographs of Adamawa RAMP Roads Conditions
Appendix 2: List of Economic and Medicinal Plant in Project Areas
Appendix 3: List of Community Members Consulted Along the Roads
Appendix 4: List of Women Groups Consulted in the Communities
Appendix 5: Minutes of Meetings for the Discussion of ARAP in project area
LIST OF ACRONYMS
Content
EIA- Environmental Impact Assessment
PPP- Public- Private-Partnership
EMP- Environmental Monitoring Plan
ES- Environmental Setting
LFN- Law of the Federal Republic of Nigeria
FGN- Federal Government of Nigeria
FMWHUD- Federal Ministry of Works, Housing and Urban development
FEPA- Federal Environmental Protection Agency
SEPA- State Environmental Protection Authority
UNCED- United Nations Conference on Environmental Developments
WSSD- Water Supply and Sanitation Development
MDG- Millennium Development Goals
HIV- Human Immuno-deficiency Virus
AIDS- Acquired Immuno- Deficiency Syndrome
LGA- Local Government Area
LGC- Local Government Council
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
i
EXECUTIVE SUMMARY
INTRODUCTION
The World Bank requires that an Environmental and Social Impact Assessment (ESIA) be
carried out on projects proposed for Bank financing. The exercise ensures that projects are
both socially and environmentally feasible and sustainable. The ESIA enables sound decision
making.
This executive summary presents the key findings of the assessment together with the
recommended actions.
Section One describes the background of the project paying particular attention to the road
conditions, locations and lengths
In section two, the Policy, Legal, Administrative and Institutional Framework of the World
Bank and the Federal Republic of Nigeria for development projectsare reviewed; while
section three is a summary of project description together with the design concept and
envisaged project activities.
Section four describes the baseline conditions of the entire project area detailing both
environmental and scio-economic conditions.
In section five, a summary of the project potential impacts are listed together with a
discussion of project alternatives. Environmental and Socio-economic mitigation measures
are in section six and section seven contains the environmental and socio-economic
monitoring framework (ESMF).
A. Environmental Issues
1. Positive Environmental Impacts
a) Improvement in Visual Impact of the Road: The road improvement would bring
about an increase in passing and stopping sight distance. There would be an
overall improvement in the visual quality and aesthetics of the roads. This impact
would have local appeal, long term in duration is irreversible in nature and would
be spread across the entire project area.
b) Aquatic Ecosystem Modification: The construction of the roads would increase
sediment loads and transportation into streams and rivers. Also, the volumes of
surface run off from the roads would increase. These two factors would together
lead to aggradations of the rivers/streams and cause increased flooding during
the rainy season. Wider flood plains would be created and would signal the
beginning of fresh areas of vegetative succession and new habitats. An
improvement in the riparian ecosystem may occur. This impact would be felt at
project locations like Labondo-Borrong road which lies roughly along the flood
plains of the Benue river; Jambutu-Bogare and Gyawama –Lamurde roads.
c) Ground Water Recharge: Increased flood plains acreage from flooding, would
lead to improved groundwater recharge potentials of the area. This impact would
be felt in low lying areas, along Gwakrah-Borrong road.
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
ii
d) Reduction in Solid wastes along the Roads: Many of the roads pass through built
up and habited areas. There are many squatter traders along such places. As a
result, the road/route is littered with wastes. Many of the built-up areas would be
by passed during construction. Therefore, the roads would not be subjected to
litter left behind by the traders especially at Bomari, Goron, Borrong, Bille,
Kodomun and Pudde.
2. Negative Environmental Impacts
a) Obstruction of Migration and Grazing Routes: The roads cut across some routes
used by migrating and grazing animals;and would constitute a barrier to
migrating and grazing animals. Migrating animals in search of watering and
breeding grounds and sanctuaries would be handicapped. Biodiversity loss could
be caused. Cattle cross the roads frequently in parts of Gerei, Demsa, Numan and
Lamrude LGAs.
Mitigation: Transhumance and migratory routes crossing the roads should be
protected by providing crossings with adequately secured entrances and exits.
Tunnels and culverts could be created for use by wildlife, especially close to forest
reserves.
b) Increased Air Pollution: During the construction stage, air pollution will be due
mainly to dust particles. During the operational phase, the increase in vehicular
traffic on the roads would result in increased emissions of carbon monoxide,
hydrocarbon particulates, dust, lead and some carbon dioxide into the
atmosphere. Air pollution will be high especially during the dry season. Despite
the likelihood of atmospheric dispersion reducing the impact of the air pollutants,
the pollutants would build up to significant levels. All the roads would experience
this impact.
Heat fluxes
Also, vehicular traffic along the roads is expected to result in increased heat
fluxes which could affect the transpiration of plants in the narrow strip bordering
the roads. Therefore there may be poor performance of crops in adjacent farms.
No significant macro-climate modification is expected on the short run.
Mitigation: planting and maintaining a hedge of forest trees at intervals along the
edge of the road will assist in the sequestration of carbon dioxide and in noise
attenuation. Watering the road surface regularly during the construction and
operation phases would help control dust particularly in the dry season.
c) Noise Pollution: During the construction stage, movement of heavy plants and
machineries would generate more than average amounts of noise to the workers
and the environment. During the operational phase, high vehicular traffic would
contribute significantly to noise levels. The escalated noise levels could scare
away wild life like birds etc apart from the effects on humans.
Mitigation: The workers should be supplied with and made to use protective
gadgets like masks, ear plugs and muffs. It may also be necessary to insulate some
of the machines and equipment so that they do not produce higher than normal
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
iii
levels of noise, Screening with a reasonable width of hedge row of plants or
suitable economic trees and animal friendly shrubs along both sides of the roads
will assist in attenuating the noise.
d) Erosion: The construction of a road increases the run-off and hence reduces
infiltration of rain water into the ground. Given the often torrential nature of rains
in the region, soils are very easily eroded especially at the slopes.
Mitigation: Avoid creating or leaving steep slopes on the sides of the road and
where the road has to pass at the base of broken hills. Plant grass and a screen of
trees which will aid infiltration of rain water and delay the delivery of storm water
into drainage channels. This will significantly dissipate the erosive energy of the
runoffs.
e) Ecosystem Disruption: During the construction of the access and feeder roads,
some sensitive ecological areas (protected forested areas, forest reserves and
areas of marginal stability especially along slopes) could be traversed. This would
lead to a disruption of the eco-system resulting in environmental degradation and
possibly biodiversity loss.
Mitigation
During the construction phase of the project ensure that only methods that would
involve the cutting of a minimum number of trees and other vegetation are used.
Also, remedial action to forestall erosion should be put in place.
B. Socio-Economic Impacts
1. Positive Impacts
a. Easier Movement of Goods and Services: The improved access would not only
make for the easy movement of people within the area and beyond but also
adequately and efficiently enable the distribution of factors of production
including manpower. This positive impact of regional spread is long term in
nature but is reversible, if there is no sustainability factor built in.
b. Reduction in Cost of Operation and Maintenance of Vehicles: Improved road
surfacing and prompt repairs of failures on the road will significantly reduce the
wear and tear of vehicles. Similarly, the reduction in the average travel time will
result in reduced cost of operating vehicles. This is a significant beneficial impact
of local importance that is long term but reversible in nature.
c. Employment Generation: During the construction phase of the project a large
numbers of unskilled and a smaller but significant number of skilled labour would
be required. New jobs would be created both for skilled and unskilled workers
during the construction phase. This is a long term positive impact that is localized
at first but which will later turn regional in coverage. This impact is reversible in
nature and is expected to bring about significant benefits to the employees and
shareholders of companies engaged in the construction work.
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
iv
d. Contribution to Agriculture: The road would facilitate the movement of
agricultural produce to markets. Farmer would be encouraged to increase their
productivity
e. Gender Empowerment through Provision of Access: Construction of the road will
further improve access to factors of production and market facilities. The case in
point here is the access to markets for the female gender group to enable them sell
their wares (fruits and vegetables), to sustain and empower them. It is possible
for the government to assist these women by training them in fruit and vegetable
processing skills so that they can diversify their businesses. With soft loans the
women could crate viable small and medium scale enterprises and participate in
training that could enhance their productivity.
2. Adverse Socio-Economic Impacts of the Proposed Road Renovation Project General
a) Displacement of people: The roads’ right of way is encroached upon in some
locations. Although there are no resettlements or relocation of persons. As a
result some livelihoods would be affected.(e.g hawkers and other livelihoods
encroaching on the road) particularly at Goron, Bille, Kodomun and Pudde.
- Mitigation: Where commercial activities are responsible for encroachment on
the roads, lay bys of adequate sizes should be created at such locations. (e.g
Borrong, Goron etc). Also consider changing the road alignment.
3. Other Socio-Economic Impacts
a. Accidents: Pedestrians, cyclists and other road users are vulnerable to accidents.
During the operational phase, accidents could become common because of fast
moving vehicles and if the roads are encroached upon by squatter traders
Mitigation: Road markings and signs should be provided to warn of danger
requiring a reduction in speed. The, education of road users to appreciate road
markings and signs is usually also helpful in preventing accidents. The
Community members should be enlightenend about the dangers of encroaching on
the roads. Install speed checks in inhabited areas. Ensure fuctional clinics and
health centres are built. Sensitize drivers about road safety measures/signs
b. Security Risk: Improved mobility will enable persons of dubious character ease of
mobility from far and near. Thus, the security risk in the area traversed by the
road will increase. This is a local adverse impact of short duration that is
reversible in nature.
Mitigation: Provide surveillance by members of the communities to complement
the efforts of State and Local Government Area security personnel. Establish
police posts.
c. Spread of Diseases: Improved access will result in increased interactions among
people. These interactions are avenues for the transmission of diseases especially
sexually transmitted diseases. Other diseases which may not be indigenous to the
region may be introduced and transmitted in this manner. This impact is local in
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
v
coverage but could be regional as the diseases spread. They are reversible in
nature.
Mitigation: Public enlightenment about the various ways of contracting and
preventing diseases (HIV/AIDS) will go a long way to help in the fight against
the spread of diseases. Establishment of adequately manned and equipped
hospitals will provide the much needed medical attention to victims of such
diseases. The health centres will also assist in the treatment of accident victims
along the road route.
Table of Activity: Potentials Impacts of Rural Roads Construction in Adamawa State
Project phase Proposed activities Potential Impacts
Mobilization
Identification and demarcation of
Right of Way (RoW), workers,
campsite, burrow pits areas, quarry
sites, access roads, stone crushing
areas and materials storage yards.
Site clearing within the RoW, workers
campsite, burrow pits, quarry sites
and access roads.
Opening of burrow pits, quarry sites
and access roads.
Transportation of equipment (bull
dozers, caterpillars, heavy duty
vehicles, stone crushers, etc), and
construction materials (e.g. stone
aggregates, sand, cement, gravel, etc)
to the site
Removal of vegetation cover, loss of
biodiversity through ecological
disruption, erosion, water pollution,
air pollution, noise pollution.
Increased incidence of respiratory
disorders, loss of fertile top soils.
Employment.
Noise pollution, Air pollution,
disruption of movement of local
community
Employment opportunities
Construction Earth movements, excavations and
stockpiling of excavated materials.
Road cutting, filling-in, and surfacing.
Operation of burrow pits, quarry sites
and cement batch plant.
Stockpiling of construction materials
such as sand, stone aggregates,
cement, etc.
Installation of culverts and bridge
structures
Creation of roadside drains and storm
water drainages and access roads.
Transportation of construction
materials such as sand, cement, stone
aggregate and soils.
Noise pollution, Air pollution,
visibility loss, loss of top soil and
vegetation, tree felling and climate
concerns, loss of endangered
species, biodiversity loss, changes
visual quality, water quality
deterioration, altered river flows,
diversion of traffic. Accidents,
Obstruction of migratory and
grazing animals, erosion,
employment potential
Demobilization
Demolition of workers and
Contractor’s camp site
Closure and restoration of burrow
pits and quarry sites
Noise/Air pollution, Accidents,
Regained fertility, Restored visual
quality, Reclaim land for other
development, land use restored.
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
vi
Rehabilitation / restoration of access
roads.
Closure and restoration of materials
storage yards and stone crusher sites.
Dismantling / demolition of cement
and stone crushers.
Operational
Completion of project, leading to all
associated positive benefits of
increased access.
Improved access, faster movement
of goods and services, cultural and
social linkage with neighbours,
Regional integration and harmony,
increased accident rates, population
increase, incidents of some diseases
(STDs), increased noise levels,
increase air pollution (earth roads)
alteration of stream/river
hydraulics, water pollution from
runoffs
Some capacity building needs were identified for redress so as to strengthen the rather weak
capacity of the rural people and insitutions as detailed below.
Capacity Building (Training) Budget
S/N S/N Capacity
Needs Participant Subject
Resource
Persons
Cost per
Participant
($)
Duration
1. Dry season
farming.
Farmers
Near
waterways
Irrigated
Agriculture
Extension worker
from ministry of
Agriculture,
Upper Benue
RBDA
1,000.00
incuding
transport
accommodati
on and
honorarium
for resource
person
1 week
2. Farming System Other
Farmers
Intercropping/
mixed
cultivation
Extension worker
from ministry of
Agriculture,
Upper Benue
RBDA
1,000.00
Ditto
1 week
3. Skills
Acquisition
(a)
Women as
well as some
young men
Dressmaking
Hairdressing
National
Directorate of
Employment,
NGO/CBOs
24,000.00
6 months
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
vii
S/N S/N Capacity
Needs Participant Subject
Resource
Persons
Cost per
Participant
($)
Duration
(b) Youths Road
maintenance
State/LGA
Department of
works,
contractors
4,000.00 4 weeks
(c) Community
members
(youths)
Environmental
Sanitation
Practices
State/LGA
Ministry of
Health/Environm
ent
Consultant
1,000.00 1 week
4. Training
a.
Community
members,
contractors
staff etc.
Malaria/HIV-
AIDS
Awareness
campaigns
Consultant
Ministry of
Health
1,500.00 for
each
Campaign
4,500.00 for
three.
Two or
Thrice
during
project
constructi
on phase
(Day)
b.
c.
LGA Staff
SPIU Staff
Training in
RAMP
Operation and
managment
FPMU
Consultants
Needs
Assessment
first
1 week
d. LG Council
Staff
SPIU Staff
Institutional
Strentheing
Consultant
FPMU
Needs
Assessment
first
Progressi
ve
5. Construction
and maintenace
of equipment.
LG Council
Staff
SPIU Staff
Road
Maintennance
equipment
training/aquist
ion
Manufacturers
Representative
Needs
Assessment
first
2 weeks
for
training
6. Honorarium, Transport, Accommodation, Feeding for 20 resource
person
20,000.00
Total per participant $55,500.00
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
viii
Budget Summary (13 Roads)
S/N Budget Item Cost ($)(Estimated)
1. Compensation
a. Trees
b. Lands
c. Fencing
31,500.00
9,000.00
8,700.00
2. Capacity Building
a. Training
b. Institutional Strengthening
35,000.00/yr
Needs to be assessed
3. ESMP 448,631.25
Total 532,831.25
*This budget excludes the cost of institutional strengthening.
Public consultations:
Public conslutations were held (during the field visits), at Dubwangun, Bille, Kodomun and
Borrong where road re-alignment is being proposed. The summaries are presented in the
table below.
Consultations were held at many other locations regarding livelihoods, community socio-
economic lives and the perception of the people about the project.
Generally the idea of the roads projects was well received and the community members
everywhere visited were very enthusiastic and anxious to have the project commence.
Sumarry of Consultations at Locations with Challenges
Location Attendance(NO)
Concerns Expressed by Stakeholders Remark
Male Female
Dubwangun
Lamurde
LGA
32 7 Would compensation be paid for any
property removed?
Would it be paid before construction work
starts?
What will happen to the water pipe in the
ground along the road?
Yes
Before
It will be relocated
Bille
Lamurde
LGA
59 52 Issue of conpensation for economic trees
along the new road alignment
Would contractor employ local people?
Why is the bank not refurbishing the road
from Mararaba to Bille instead of Bille to
Mayo Belwa
Will be paid
As much as
possible
That is already
been repaired
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
ix
Kodomun
Demsa LGA
16 15 Will contractor employ local People
What type of road is to be constructed?
How are community members going to
feed the contractors workforce?
Yes
Earth road
Prepare the food
for workers to
purchase
Borrong
Gerei LGA
40 6 When will work commence? Will it be this
year?
How would the marshy portion of the road
constructed?
Some people have stockpiles of
construction materials. Will the
contractor patronise us?
The chifewould prefer the road terminate
at the palace, deviating from proposed
alignment.
Definitely not
during the rainy
season
There would be
culverts
If the materials
meet the required
standards
There are some
challenges along
that route.
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
1
1.0 PROJECT BACKGROUND AND DESCRIPTION
1.1 Introduction
The Federal Ministry of Agriculture and Rural Development, has received credit
from the World Bank (WB), and the French Development Agency, to support and
finance its policy on Rural Access and Mobility Projects (RAMP). The RAMP is
aimed at improving and enhancing accessibility and mobility in rural areas
towards effective regional integration and poverty alleviation. Adamawa State is
one of the states of the federation designated to benefit from RAMP projects.
1.2 Project Location
Adamawa State was created in 1991 out of the former Gongola State. The state is
located between latitude 70 28 and 10
0 15 and longitude 11
0 30 and 13
0 45, and
occupies about 36,917 square kilometres. It is bordered by Borno to the northwest,
Gombe to the west and Taraba to the southwest. Its eastern border also forms the
Nigerian eastern border with Cameroon. The capital Yola is both the seat of
administration and the traditional council.
1.3 Project objective
The objective of RAMP II is to improve the transportation system in rural areas.
The long-term objective is to improve the welfare and economy of the local
people in the project area and contribute to poverty alleviation. The capacity of
relevant government agencies to manage rural transport infrastructure would be
enhanced. About 201.4 km of rural roads are to be rehabilitated.
1.4 Existing Condition of the Roads
Nearly all the selected roads have less than 6 m pavement width and are without
shoulders or drainages. The surfaces are rough throughout, with either boulder
outcrops or sandy surfaces. On level lands, the roads have been deeply incised,
due to sheet wash; while on gently sloping terrain, they are straddled by rills and
gullies. (plate 1). Traffic on the roads varies considerably, from very low to low,
in most cases.
A few of the roads have old and deeply weathered or eroded box culverts. A
number of such culverts have indeed become obstacles on the roads themselves.
The 201.4 km of roads identified for rehabilitation are detailed in Table 1.1 and
presented in fig 1.1.
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
2
Plate 1: Exsisting road ravaged by erosion in Zah area, Michika LGA
Table1.1: Summary of Roads Selected for Upgrading in Adamawa State, RAMP
Road segment name Road length
(Km) LGA
Relative position in
Adamawa
Jambutu - Ngolomba - Bagare 7.5 Yola North Central
Njoboli - Njoboliyo - Rugange 9.3 Yola South Central
Kwanawaya - Namtari 4.1 Yola North Central
Labondo - Gwakrah - Koh - Goron - Borrong 35.5 Gerei Central
Kaya - Kuda - Bitiku - Yingu 17.5 Madagali Northern
Shuwa - Pallam 8.5 Madagali Northern
Midlo - Muduvu - Yibango - Masawa - Kambano -
Madagali 15 Madagali Northern
Bazza - Betso - Mangoro - Kalikasa - Zah 24.4 Michika Northern
Main Road - Koe - Koppa 7.8 Madagali Northern
New Demsa - Old Demsa - Kadomun - Kwaine 26.8 Demsa Southern
Kpasham - Kebali - Yanga 15 Numan/Demsa Southern
Bille - Gumari - W/Hamawa - W/Bobbo -
Gadamayo - Belwa 15.5 Lamurde Southern
Gyawana - Hadiyo - Lamurde 13 Lamurde Southern
TOTAL 201.4
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
3
Fig. 1.1 Adamawa State Showing the 21 LGAs
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
4
1.5 The Scope of Work (ToR)
The scope of this ESIA study is specifically based on the ToR provided by the
client. The ToR requires the standard preparation of an ESIA for the road project,
and entails the following;
Consultation with relevant Government agencies and affected local
community members.
The establishment of an environmental and social baseline information for the
project area and description of the proposed road works.
The assessment and quantification of the potential environmental and socio-
economic impacts resulting from the road development, especially within the
zone of influence of the project.
The development of Environmental and Social Management Plan (ESMP)
detailing actions and responsibilities for impacts mitigation and monitoring.
Prepare environmental monitoring plan to reflect the management measures in
the EMP; specifying indicators to be observed or measured, frequency of
observations, and identity of monitors.
1.6 The Study Approach and Methodology
The approach methodology employed in this study comprised reconnaissance
survey, desktop review and detail field work.
i. Reconnaissance survey and consultation with relevant stakeholders
There were preliminary trips to the project area for consultation with relevant
stakeholders of the project, including SPIU, Director of State Ministry of
Rural Development, some local communities of project area, and relevant
institutions in project Local Government Area. It also included a drive through
all roads to be upgraded. Representatives of both the project committee (state
official) and the host communities provided the much needed guided tour at
this phase.
The objectives of the preliminary consultation with the relevant stakeholders
and survey of all proposed road projects are to:
a) determine the nature of the assignment;
b) secure and analyze available baseline information on the environment of
the study area, including available topographical maps, air photographs
and satellite imagery;
c) promote understanding of the intended project activities and to identify
and mobilize potential actors and partners in the process.
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
5
The consultation and reconnaissance survey was undertaken between 19 –26th
of February 2012.
ii. Screening Process in the Environmental and Social Impact Assessment of
the 201.4 km Rural Feeder Roads Improvement in RAMP - II project in
Adamawa State.
A preliminary reconnaissance visit to the roads chosen for improvement under
RAMP II was undertaken in the last week of February 2012. This Initial
Environmental Evaluation (IEE) of the project is as required by the EIA Act
(1992). A preliminary determination of the expected impacts of the project on
the environment was carried out. Also, this visit enabled the collection of
information about the relevant stakeholders, the sources and distribution of the
construction materials, available local skills, and community perception of the
project.
Though rural roads do not fall within the mandatory list of projects requiring
EIA under the EIA Act of 1992, the terrain traversed by most of the roads is
mainly the flood plains of the River Benue and other major drainage rivers of
the state, which are sensitive ecological zones that are transit regions between
permanent wetlands (with high biodiversity) and terrestrial ecosystems. The
areas to be served by the project are agriculturally active with production of
arable crops like maize, rice, beans, guinea corn and vegetables. There are
some small holder irrigation schemes providing dry season farming. Animal
husbandry is common, among the Bachamas and Fulanis alike. There are
many tribes, which have diverse cultural and religious characteristics.
Women engage in early marriages and education does not usually exceed the
secondary school level.
In view of these initial findings which were considered to be likely to produce
significant impacts, it was considered necessary for a detailed Environmental
and Social Impact Assessment to be undertaken, categorizing the project as a
category A project.
iii. Scoping Process in the Environmental and Social Impact Assessment of the
201.4 km Rural Feeder Roads Improvement under the RAMP –II project in
Adamawa State.
Scoping was undertaken under the requirement of the Nigerian EIA Act
(1992) and the World Bank Operational Policy (OP 4.01) 2007. The scope of
the improvement of the rural roads calls for a comprehensive environmental
assessment which considers both likely physical, biological, aquatic, terrestrial
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
6
and the socio- economic impacts on the environment and beneficiaries. This
would enable only important issues to be considered highlighted and
identified, so as to ensure that time and coverage of the ESIA are properly
deployed.
Some of the scoping had been carried out by the proponent of the project in
the broad context of the classification; and the criteria used for selection of
roads. A review meeting held in the second week of March, 2012 at the
FPMU. The review highlighted parts of the terms of reference including the
issue of Gender Relations in the communities served by the roads. It was
agreed that the lengths of the roads should correspond with the initial
submission of the State Governor. Where the road route crosses
developments, it was also resolved that RAP/ARAP should apply and where
displacements arise, compensation was to be proposed for involuntary
resettlement. Thus the screening carried out in the project aided in the scoping
which covered these vital areas.
The environmental/social impact assessment is to highlight the burden borne
by women in the rural communities where the roads traverse. The
communities are to have all year round motorable roads that will grant them
access to markets, health centres, farms and food processing centres among
others. Family harvest can be sold at higher prices instead of the present
practice of hurried sale after harvest at lower market prices. Higher
income/revenue would accrue to the people and there would be improved
access to credit facilities. This would stimulate improved standards of living
and family harmony.
This and other aspects were adequately covered in the Environmental/Social
Impact Assessment. It was only in about five instances (at Dubwangun, Bille,
Borrong, Kodomun and Midlo) that the roads’ corridor traverse built up areas
or markets. Adequate compensation has been proposed as appropriate; and an
ARAP has been prepared as required.
iv. Desk review
The desk review involved preparation of environmental impact identification
checklists, acquisition and review of engineer’s reports and drawings,
background project documents, reports maps, plans and other relevant
documents. The information from previous documents would help to
supplement primary data obtained from the fieldwork.
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
7
v. Detailed field work
The survey was executed by means of a 4WD Vehicle and on foot whenever
necessary. The survey incorporated both visual and empirical field
assessment/measurement of environmental baseline conditions along the road
corridor. The consultants also interviewed the local people encountered along
the route and in the settlements nearby, using an Environmental Impact
Identification (EII) Checklist. Such interviews helped to confirm the local
place names and to establish the presence or not of any important features of
ecological, biological, physical, social, economic, cultural, historic and / or
archaeological significance. The survey also obtained photographs for
illustration, whenever necessary. Issues that were not resolved, and which
were listed and prioritized in the reconnaissance phase, were further
deliberated on during this phase. The names of the people consulted and some
issues raised during the survey are shown in APPENDIX 3.
For purposes of the baseline assessment and impact identification during the
field survey, the route corridors were into two:
a. The direct impact zone - Comprising 50m to the left and right hand side of
the existing road. The assumption was that the Contractor’s activities,
including stockpiling of soils, temporary storage of construction materials,
and movement of equipment and/or machinery, and possible contractor’s
campsite would not exceed this distance.
b. The zone of influence - This includes the wider geographical areas along
the route alignment. The zone of influence was taken as an arbitrary area
roughly 2 km on either side of the route alignment.
vi. Identification, assessment and analysis of Impacts
Impacts were assessed and analysed using a rapid assessment approach, which
was informed by using an Impact Identification checklist. The generic criteria
and systematic approach used to identify, describe and assess impacts include the
following:
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
8
Magnitude of impact (high, medium, low)
Direction of impact (positive, negative, no change)
Duration (months, years, decade, permanent)
Scope (local, regional)
Intensity (nil, low, medium, high)
Probability (improbable, probable, highly probable, definite)
Significance (not significant, significant, Impact not immediately known)
1.7 Interactive Discussions and Consultations
During the detailed field visits, consultants held consultations with community
members along each road not only to intimate them of the project but also to find
out their feelings and disposition to the project.
Along each road, consultations were also held with women groups about their
socio-economic lives and their empowerment requirements. (e.g. at Bazza-
Kalikassa road, Gyawanna - Lamurde) see plate 2-14)
Plate 2: Consultations with community members (Kebali Numa) Plate 3: Consultations with community members (Kebali Numa)
Plate 4: Consultations with community members Plate 5: Consultations with community members (Yanga)
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
9
Table 1.2 shows some of the concerns expressed by some consultees at some of the
communities.
Table 1.2: Consultations at Various Critical Communities along the Road Routes
Location Attendance(NO)
Concerns Expressed by Stakeholders Remark
Male Female
Dubwangun
Lamurde
LGA
32 7 Would compensation be paid for any
property removed?
Would it be paid before construction work
starts?
What will happen to the water pipe in the
ground along the road?
Yes
Before
It will be relocated
Bille
Lamurde
LGA
59 52 Issue of compensation for economic trees
along the new road alignment
Would contractor employ local people?
Why is the bank not refurbishing the road
from Mararaba to Bille instead of Bille to
Mayo Belwa
Will be paid
As much as
possible
That is already
been repaired
Kodomun
Demsa LGA
16 15 Will contractor employ local People
What type of road is to be constructed?
How are community members going to feed
the contractors workforce?
Yes
Earth road
Prepare the food
for workers to
purchase
Borrong
Gerei LGA
40 6 When will work commence? Will it be this
year?
How would the marshy portion of the road
constructed?
Some people have stockpiles of construction
materials. Will the contractor patronise us?
The chife would prefer the road terminate at
the palace, deviating from proposed
alignment.
Definitely not
during the rainy
season
There would be
culverts
If the materials
meet the required
standards
There are some
challenges along
that route.
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
10
Plate 6: PAP at Dubwangun along the road Plate 7: Cross section of Consultees at Dubwangun
Plate 8: Consulation at the chief’s palaces at Bille Plate 9: Consultation at village square in Bille
Plate 10: Proposed new alignment at Kodomun Plate 11: Cross-Section of consultees at Kodomun
(Chief in the background)
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
11
Plate 12: Some chiefs at palace in Borrong during consultation Plate 13: Consultees outside the palace at Borrong.
Plate 14: Road route terminating at palace in Borrong.(proposed by the chiefs)
A multi-disciplinary team of scientists and environmental professionals was involved in the
study (Appendix 4). An interactive approach among the team members and other project
professionals was adopted with team meeting to discuss the progress of investigations and
analyses and to facilitate integration of data. The team utilized the Charette-style approach to
data gathering, analysis, and presentation in which team members conducted the field survey
together, to determine the critical elements for analysis. The ESIA study was carried out
between March 8 and 14 2012.
This document is structured as follows:
Chapter One: Project Background and Description
Chapter Two: Policy, Legal, Administrative and Institutional Framework
Chapter Three: Description of Project
Chapter Four: Description of Baseline Conditions
Chapter Five: Summary of Potential Impacts
Chapter Six: Environmental / Socio-economic Impacts Mitigation Measures
Chapter Seven: Environmental and Socio-economic Management Plan
Chapter Eight: Summary and Conclusion
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
12
2.0 POLICY, LEGAL ADMINSTRATIVE AND INSTITUTIONAL FRAMEWORK
2.1 Introduction
The existing policies, land laws and regulations regarding development projects
with potential impacts on the environment in Nigeria are consistent with the
World Bank Operational Guidelines in which the environment is considered to be
a pertinent issue. The Nigerian Development vision, for example, recognizes and
stresses the need for striking a balance between development pursuits, cultural
considerations and basic needs on one hand and the preservation of the natural
environment for the current and future generations on the other hand. The
National Policy on Environment is an important national document that
summarizes the country’s position on environmental issues, and is relevant for the
road sector. The power to regulate all environmental issues in Nigeria is vested in
the Federal Ministry of Environment and its agencies which, before now, was the
Federal Environmental Protection Agency (FEPA) established by Act 88 of 1988.
Some policies, legal and institutional framework that are relevant to the project
implementation are reviewed below.
2.2 Relevant Regulatory Instruments
Some relevant instruments for environmental regulation and protection in Nigeria
include:
World Bank Policies and Guidelines
Current Federal, state and Local Government Acts, rules, regulations and
standards of the Country
International treaties and agreements especially those that have been
domesticated.
2.2.2 World Bank Operational Policies
The Bank’s environmental and social guidelines are geared mainly to
ensuring sustainable poverty reduction. The policies have (as their main
objective) the prevention and mitigation of undue hardships to persons and
their environments as a result of development projects. Hence OP 4.01
relates specifically to the requirement to prepare an Environmental
Assessment for development projects including roads. Operational Policy
OP4.12 deals with involuntary resettlement. Others guidelines for other
specific projects include:
OP4.04 for the Conservation of Natural Habitats
OP4.09 for Pest Management
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
13
OP4.11 for Safeguarding Cultural Property
OP4.36 for Forestry Protection
OP4.37 for the Safety of Dams
2.2.2 Federal Government of Nigeria (FGN) Acts
Federal Environmental Protection Agency (FEPA) Act- Cap - Retained
as Cap F10 LFN 2004
This Act was enacted to give functions and powers to FEPA for the
effective implementation of its functions, which is basically the
protection and development of the environment, biodiversity
conservation and sustainable development of Nigeria natural resources.
Environmental Impact Assessment Act - (No.86 of 1990) Retained as
Cap E12 LFN 2004
This Act was enacted to set out the general principles, procedures and
methods to enable the prior consideration of environmental impacts of
certain public or private projects. The law aims at promoting the
implementation of appropriate policy in all Federal lands; States and
Local Government Areas.
Harmful Waste (Special Criminal Provision, etc) Act - (No 42 of 1988)
Retained as Cap H1 LFN 2004
This law was enacted to prohibit the carrying, depositing and dumping
of harmful waste on any land, territorial waters and other related
matters.
Endangered Species (Control of International Trade and Traffic) Act -
Retained as Cap E9 LFN 2004
Enacted to provide for the conservation and management of Nigeria’s
wild life and the protection of her endangered species.
Water Resources Act - Retained as Cap W2 LFN 2004
The Act was enacted to promote the optimum planning, development
and use of the Nigeria’s Water Resources and other matters connected
therewith.
National Environmental Standards and Regulations Enforcement
Agency Act
The Act establishes the Enforcement Agency for the effective
enforcement of Standards, Regulations and all National and
International Agreements, Treaties, Conventions and Protocols on
environment to which Nigeria is a signatory.
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
14
National Policy on Environment and National Agenda 21
This statement of environmental policy establishes priorities and gives
expression to national goals and aspirations. It provides a statutory
foundation for which decision-makers may refer to for guidance in
making decisions in respect of sustainable development, whenever
environmental values are in conflict with other values or whenever
transboundary issues are involved.
2.2.3 Environmental laws of Adamawa State
States in Nigeria have set up their individual Ministries of Environment
and Environmental Protection Authorities (SEPA). They regulate protect
and manage the environment using Acts, edicts and laws as enforcement
tools. The functions of the SEPA include the following:
Enforcement of all legislations, policies etc
Co-ordination and supervision of Environmental Assessment reports
Regulation of development impacts issues on the ecosystem
Supervision of the preservation, conservation, and restoration activities
of biodiversity
Co-ordination of the protection of Air, Water, land, forest and Wildlife
resources
Co-ordination and supervision of Pollution Control, and State
Environmental health
In carrying out these functions, SEPA is expected to collaborate with other
agencies like FMENV, WB, AFDB, FMOH, UNDP, UNICEF etc.
2.3 Safeguard Policies that Apply to the RAMPII Adamawa Project
The following World Bank safeguard policies are relevant to this project and help
to manage the concerns in the project. Adequate consultations are indicated.
Table 2.1: Triggered safeguard policies
Policy Yes No Useful for the reason that Activity for Redress
Environmental and
socio-economic
Impact
Assessment(OP4.12)
Yes
The road construction would result in
some site specific negative impacts
like noise and air pollution due to
dust, erosion, health concerns, safety
issues etc.
These concerns have
been adequately
addressed in the
ESMF provided in
section seven.
Involuntary
Resettlement
(OP4.12) No
Road re-alignment has been proposed
at four locations (Dubwangun, Bille,
Kodomun and Borrong). Some trees
would have to be felled and at
Consultations have
been held. No re-
settlement of persons
is necessary but
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
15
Dubwangun, the fence of a
compound is affected and a portion
of the compound would be acquired
to achieve the desired road width.
compensation
commensurate with
property values
would be paid.
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
16
3.0 DESCRIPTION OF PROJECT
3.1 Project activities
The proposed road project involves the upgrading of 13 stretches of feeder roads
within eight LGAs in the state. In all, the roads total some 201.4km. All are
existing roads and follow existing tracks for the greater parts of their lengths,
except where some minor realignment would be necessary. The specific roadway
segments and their administrative locations are shown in Table 1.1
The roadways will be built to a standard feeder road cross-section 6-meter
formation width, supported with longitudinal drainage structures where required.
The exact design of the roadway cross-section will depend on conditions at any
given location.
As the pavement of all the roads alone is expected to be 6m wide, the widening of
the present width of most of the road and therefore, road route clearance will be
the primary activity during the construction phase. In most areas, this would
involve de-vegetation, layout of the roads and pavement construction and erection.
A summary of the project activities is presented in Table 3.1.
Table 3.1: Summary of the Road Project Activities
Project phase Proposed activities
Mobilization
Identification and demarcation of Right of Way (RoW), workers,
campsite, burrow pits areas, quarry sites, access roads, stone
crushing areas and materials storage yards.
Site clearing within the RoW, workers campsite, burrow pits,
quarry sites and access roads.
Opening of burrow pits, quarry sites and access roads.
Transportation of equipment (bull dozers, caterpillars, heavy duty
vehicles, stone crushers, etc), and construction materials (e.g. stone
aggregates, sand, cement, gravel, etc) to the site
Construction Earth movements, excavations and stockpiling of excavated
materials.
Road cutting, filling-in, and surfacing.
Operation of burrow pits, quarry sites and cement batch plant.
Stockpiling of construction materials such as sand, stone
aggregates, cement, etc.
Installation of culverts and bridge structures
Creation of roadside drains and storm water drainages and access
roads.
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
17
Transportation of construction materials such as sand, cement,
stone aggregate and soils.
Demobilization
Demolition of workers and Contractor’s camp site
Closure and restoration of burrow pits and quarry sites
Rehabilitation / restoration of access roads.
Closure and restoration of materials storage yards and stone
crusher sites.
Dismantling / demolition of cement and stone crushers.
Operational
Completion of project, leading to all associated positive benefits of
increased access.
3.1.1 Project Design
3.1.2 Design Criteria and Standards
The overall objective of selecting design criteria and standards is to allow
for the movement of the greatest number of vehicles possible at the highest
speed possible within the laws and with maximum comfort and safety.
The criteria and standards envisaged in this design are suitable and
commensurate with major controls to allow for future improvements with
minimum investment loss. The standards enumerated are constant with the
anticipated traffic volume, composition of traffic, design speed and access
control.
3.1.3 Geometric Design Standards
Design Speed min - 50Km/hr.
Optimum - 70Km/hr.
Traffic level - 50 ADT
Minimum Radius (Horizontal) min - 86 m
Opti - 203m
Carriageway Width - 6.0m (Each made up of 2-single lane
of 3.0m width)
Shoulder width - 1.0m (on each side of the road)
Carriageway Crossfall - 4.00%
Shoulder Crossfall - 5.00%
Maximum Degree of Curvature - 5 degrees
Maximum Super elevation - 8%
Coefficient of Side Friction - 0.12
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
18
Stopping Sight Distance - 65m (Minimum)
- 105m (Optimum)
Passing Sight Distance - 345m (Minimum)
- 485 (Optimum)
Maximum Gradient - 4.00%
Minimum Gradient - 0.50% (Desirable)
- 0.35% (Minimum)
Minimum K - Value for crest - 50m
Minimum K - Value for sag - 35m
Minimum Length of Vertical curve - 150m
V-Shape Earth Drainage - 0.5m x 0.5m on either side
Rectangular shaped - 225mm sandcrete block drain (0.5m
x 0.5m)
3.1.4 Pavement Structure
Base Course - 150mm Laterite (Min. CBR = 80%)
Sub base - 150mm Laterite (Min. CBR = 30%)
(Pavement designs will be carried out to determine the thickness of the
pavement materials to be used for the Proposed Carriageway).
3.1.5 Culvert Types
Box culvert 1 x 1m, 1.5 x 1.5m, 2.0 x 2.0m, 2.5 x 2.5m etc. pipe culverts,
drains, sizes 900mm, 1200mm, 1500mm,
3.1.6 Construction Materials
The details of the quantities / amount of materials required for the road
construction can be found in the Tender Documents. Table 3.2 summaries
the materials required for the road project and their sources.
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
19
Table 3.2: Road Construction Materials and their Sources
Materials Sources Remark
Gravel and fill materials - pits.
From burrows
All fill materials will be
transported by trucks to
the designated fill areas.
Burrow pits will be
identified based on
proximity to project,
material type required,
type of approval from
authorities.
Crushed aggregates and surface
dressing chips:
Stones chipping and
boulders will be obtained
from closest site.
These will be transported
by trucks to the
designated needed areas.
However, this material
may not be required
Sharp sand:
River channel in the
vicinity
It is anticipated fine
materials from crushed
stones (stone dust) could
be used.
Construction Water: The water for construction
will be obtained from
existing nearby seasonal
rivers and streams, during
rainy season. However,
during dry seasons, it may
be necessary to drill
boreholes.
Construction Equipment
Bulldozer 250 - 350 HP
Front End Loader 2.0 - 3.0 m³
Motor Grader 140 - 185 HP
Excavator 1.0 - 1.5 m³
Grid Roller (Sheep foot roller) 10 -
13.5 tonnes
Vibratory Roller (static and
It is expected contractor
would prepare all
equipment required for the
project.
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
20
Materials Sources Remark
dynamic) 120 kN/m with @ 25 Hz
Steel Wheel Roller 8 - 10 tonnes
Tandem Roller 10 - 12 tonnes
Pneumatic Roller 10 - 16 tonnes
Water Bowser 12,000 - 14,000
litres
Tipper Trucks 10 - 15 m³
Self-propelled Chip Spreader 3 - 6
tonnes
Concrete Mixer 0.5 - 0.75 m³
Concrete Truck Mixer 6 m³
Diesel Generators 15-20 kVA
Air compressor and Wagon drill 5
000 l/min
All essential supporting units, such
as welding machines, water pumps,
mobile workshop, tyre repair shops,
Supervision vehicles, Service
trucks, Low bed trailer units, etc.
3.2 Safeguard Sustainability Issues
In order that the road is sustainably used, some measures are here recommended
for implementation during construction. The verges of the road should be planted
with grass to help check erosion from that source.
Suitable trees and/ or shrubs should be planted perhaps 2-3 meters away from the
roads carriageway to help check erosion, noise attenuation during the operational
phase. The trees would enhance carbon sequestration help check air pollution and
serve as an effective wind breaker reducing wind erosion.
It is expected that the contractors would employ some local labour for the
construction of the roads. During that period, sensitization and mobilisation of the
local youth should be carried out about ownership and the responsibility of
operating and maintaining the roads after construction.
The water sources in many of the communities (wells and boreholes with hand
pumps), are located close to the roads. Wastewater from the water points is
allowed to flow without proper channelling. When the roads are constructed,
deliberate attempts should be made to channel the wastewaters away from the
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
21
roads into properly constructed soakaways or into household gardens where
vegetables can be grown.
Table 3.3: Sustainability of Roads
S/N Activity Extent Cost $
1. Grass planting on verge of
roads
Wherever there is erosion potential(up to a
total of 200km)
312,500.00
2. Tree planting Where road passes through communities
(40% of total road length) 3m apart (i.e.,
between trees)
106,250.00
3. Dust Control During construction and dry seasons of
maintenance phase
100,000.00
4. Provision of soakaway pits to
channel wastewater away from
roads
At locations where wells and handpump
boreholes are located close to the roads
(20-30 locations)
2,000.00
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
22
4.0 BASELINE CONDITIONS
A. Environmental Conditions
4.1 Physical Conditions
Adamawa State has typical Savanna features. To the north it is typically Sudan
while the southern parts experience northern Guinea Savanna. The baseline
environmental and socio-economic conditions of the state are summarized in table
4.3.
4.2 Biodiversity
4.2.1 Species Diversities
The northern part of Adamawa State has the sub-sudan vegetation type
marked by short grasses interspersed with short trees, while in the southern
part, the northern Guinea savannah vegetation exists. The identification of
the flora was carried out physically on sites while fauna/fishery inventories
were accomplished by additional complimentary interviews of the local
inhabitants for those fauna and fish species known to be available but
immediately out of sight during the survey.
4.2.1.1 Flora:
The floral species in the two ecological zones differ primarily only in
terms of density and height.
Appendix 2 shows the results of the inventory of the floral species along
the respective road routes
4.2.1.2 Fauna
The wildlife species of the rout corridors were equally numerous. They
include:
Mammals: Monkeys, Wildcats, Hare, Antelopes, Pig, Buffalos,
Hippopotamus
Birds: Doves, Cattle egret, Hawks, Bush fowls, Guinea fowls
Rodents: Grass-cutters, Rats, Giant rats, Squirrels
Reptiles: Crocodile, Snakes (of several varieties), Cobra, Vipers
Fish: tilapia, catfish
Local inhabitants acknowledged that there are several more species, which
in recent times have virtually become extinct or rare, due to hunting and
perhaps habitat loss. Such species include hyena and lion.
4.3 Settlement Pattern
The settlement patterns along the road corridors are largely nucleated, showing a
strangely ribbon appearance along the road alignments, possibly for easy access to
road transportation. In some cases the road alignment is encroached upon by
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
23
structures like buildings, perimeter fences, trees, etc (see Table 3.1). Several small
pastoral Fulani or semi-settled Fulani camps have also sprung up on the routes.
Typical settlements are composed of concentrated clusters of residential dwellings
with the remaining areas being either farms or long-standing fallows. Information
obtained shows that there is a steady emigration from villages to rapidly growing
trading centers of the LGA and State capital. The pull factor of these two areas is
probably employment opportunities (mainly in the informal sector) associated
with urbanization.
4.4 Population and Demographic characteristics
By the 2006 Census the eight LGAs of Adamawa State where the RAMP is being
implemented have populations shown in table 3.2. The table show that Yola north
has the highest population of 199,674 while Lamurde has the least with 111,254.
The difference in the population in males and females is small with the males
generally being more in numbers. However, in Lamurde, Demsa, and Madagali
LGAs, the female populations are marginally higher.
4.5 Ethnic Composition
The state has a diverse ethnic composition (almost 60). The ethnic groups of the
route corridors vary considerably. Among them are Mbula-Bwazza, Marghi,
Longuda, Kpasham, Ga'anda, Fulfulde, Fali, Gudu, Dadiya, Dera, Bile, Bali,
Lamang, Kamwe, Mangi, Higgi, Bwaiye, Chambe, Mbaula, Kiba, and Fulani,who
live in segmented large and small communities, speaking languages based on their
ethnic group. Although the various ethnic groups have their distinct languages and
dialects, Hausa and Fulfulde are widely spoken. While most communities are
mixed with respect to religion, the Christians predominate in most of them.
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
24
Table 4.1: Census Population Figures for Adamawa State RAMP II Communities
(2006).
S/No LGA Males Females Total
1. Gerei 66,906 62949 129855
2. Demsa 89,511 88,896 178,407
3. Numan 47,512 44,037 91,594
4. Lamurde 56,495 54,759 111,254
5. Yola South 99,814 96,383 196,197
6. Yola North 108,379 91,295 199,674
7. Madagali 67,134 68,008 135,142
8. Michika 155,238 75,036 230,274
4.6 Soil Types
Soil samples were taken from the roads to determine their nutrient levels. Result
(Table 4.2) shows, generally, that all the farms on all the roads are low in
phosphorus (P). However, Jambutu - Bogare Rd, Kpashem - Yanga Rd, Kaya-
Yinagu-S/Gari Rd and Midlo - Madagali Rd have high levels of organic matter,
while the rest have low to medium levels of organic matter. Their textural class is
shown on the table.
On the varying percentages of clay, silt and sand, reconditioning or amendment of
the soil is generally advised. These measures include planting of tress and cover
crops; and incorporation of farm residues into the soil.
All the roads have high Nitrogen (N). This could be attributed to the farming
system and management being practiced.
Soil samples from all the routes have moderate - low Potassium (K). Burning of
farm wastes in the farm should be encouraged to boost their potassium content.
Better crop performance could be achieved if a combination of organic residues
and fertilizers is incorporated into the soil. Organic matter management is
important for the sustainable fertility and productivity of the soils. Table 4.2
shows results of soil fertility tests conducted on samples collected from along the
various roads.
While table 4.3 is a summary of the general baseline conditions of the area.
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
25
Table 4.2: Soil Fertility Tests Results from Project Area
SITE/ROUTE Rout PH
H2O
N
%
P
ppm
K
% meq
Org.C
%
CLAY
%
SILT
%
SAND
% Textural class
Kwana waya - Namtari - Mange
Road
1
5.8 0.67 6.13 0.45 0.251 10 12 78 Sandy loam
Jambutu - Ngolomba Bogare Road 2 6.4 0.74 6.13 0.27 1.073 44 24 32 Clay
Njoboli- Rugange Road 3 6.3 0.70 7.88 0.25 0.771 26 34 40 Loam
Labondo - Borrong Road 4 5.6 0.60 7.00 1.18 0.335 12 10 78 Sandy loam
Gyawana - Larmude Road 5 7.4 0.77 6.13 0.24 0.788 42 30 28 Clay
Kpasham - Yanga Road 6 6.5 0.74 7.00 0.23 1.307 20 30 50 Loam
Bazza - Kasudi - Zah Road 7 6.0 0.88 7.88 0.34 0.838 8 24 68 Sandy loam
Kaya - Yinagu - S/Gari Road 8 6.2 0.74 6.13 0.23 1.458 30 44 26 Clay loam
Midlo - Madagali Road 9 6.1 .85 9.63 0.20 1.039 14 40 46 Loam
Laterite - - - - - 0.067 26 24 50 Sandy clay loam
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
26
Table 4.3: Summary of Baseline Environmental Conditions for Adamawa State
S/N Parameter Baseline conditions
1. Location 9o20’N;12
o30’E
2. Capital Yola
3. No of LGAs 21
4. Geo-political Zone North-Eastern
5. Boundaries Borno to the North-west, Gombe to the west, Taraba to the
South west, National Border with Cameroon to the east.
6. Land mass 36,917km2
7. Soil type Lateritic with areas of black cotton soil
8. Average Temperature Between 11oC and 33
oC between the seasons
9. Mean rainfall Rainfall is seasonal and precipitation varies from year to year.
Two distinct seasons- Rainy and Dry seasons. Rainy season
usually from April or June to October while dry season is
usually from November to March. State average rainfall is
between 759mm-1,1051mm North to South of the State.
10. Geology/Terrain Picturesque mountains an hills to the east where the Mandara
and Adamawa formations are to be found. The terrain is
mainly undulating with vast flood plains of big rivers like the
Benue, Gongola, yadsarem etc.
11. Vegetation The sub-Sudan type is predominant in the northern parts while
the northern Guinea savannah is found in the southern parts of
the state. The vegetation in the southern part is punctuated
with teak, tall grasses and trees.
12. Main Languages Hausa and Fufulde
13. Main Tribes Hausa, Fulani and Bachama
14. Population 2006 3,178,950: 1,607,270 males and 1,571,680 females
15. Population Density 68 persons per km2
16. Per capita income $1,417
17. GDP 4.6
18. Main Occupation Farming
19. Economy Farming
20. Settlement pattern Sparse with large masses of land dedicated to cattle rearing
21. Cultural Heritage Koma hills, Mandara Mountains, Lamurde Hot water springs,
a UNESCO, world Heritage Site, three sister rocks, Kiri dam,
Moddibo Adama tomb.
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
27
4.7 Air Quality
The country side type of air quality prevails in the road corridors. The quality is
generally good with no specific sources of gaseous or particulate emissions. In the
dry reason when the north-eastern harmattan winds are prevalent, some fine dust
particles could cause air pollution. The air quality would also be affected
negatively during construction and haulage activities, when dust would be raised.
4.8 Noise Pollution
The noise levels along the roads corridors are low because of the rural nature of
the roads alignments. The background noise limits of 55dBA between 0600 and
2200 hours set by the Ministry of Environment is not exceeded anywhere in the
project roads except at market places, on market days.
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
28
5.0 SUMMARY OF POTENTIAL IMPACTS
5.1 Impact Identification and Analyses
The methodology used for identifying the likely impacts of the Rural Feeder
Roads improvement Under RAMP in Adamawa State on the environment was the
Ad Hoc methodology, which is primarily an integrated multidisciplinary
approach, using the modified Leopold Matrix by Clarke et al (1976). The impact
significance and magnitude were quantitatively assessed, where possible, using
appropriate indicators and models. In instances where detailed background
information were not measurable; the expertise of the various consultants were
employed to determine the likely impacts of the project on the environment.
5.2 Nature of Impacts
This section assesses the nature of the impacts the upgrading of the roads is likely
to have on the local environment through which the roads traverse. Some of the
potential positive impacts of the project are listed below. The section also presents
the negative impacts by activity (Table 5.1). Table 5.2 is a summary of site-
specific negative environmental impacts, while Table 5.3 summarises the negative
socio-economic impacts, both with mitigation measures. The regulatory standards
for air pollution, noise exposure and water quality are in tables 5.4 (a-c), while
table 5.4 d is a summary of noise levels likely to emanate from road construction
equipment (muffled and unmuffled)
A. Potential Environmental Impacts
1) Positive Environmental Impacts
Improvement in the Visual Impact of the Road
Modification of the aquatic ecosystem: During the road construction
stage between Gwakrah and Borrong, for example, the various activities
will cause increased sediment loads in the streams and rivers crossed by
the roads. This could lead to the aggradations of the river channel and
cause an increase in the sedimentation of materials in the rivers especially
during the rainy season; creating wider flood plains thereby starting fresh
grounds for vegetative succession and the improvement of the riparian
ecosystem. This is an initial locally beneficial impact which would
gradually become regional, long term in nature but reversible.
Removal of wastes from the road
B Potential Positive Socio-Economic Impacts
Improved Access:
Savings in Travel time
Easier Movement of Goods and Services
Reduction in Cost of Operation and Maintenance of Vehicles
Employment Generation
Contribution to Agriculture
Women Empowerment through Provision of Access
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
29
Table 5.1: Summary of Potential Negative Impacts
Activity Negative impacts
Site Clearing Destruction of terrestrial ecosystem (felling trees and wild life
displacement)
Exposure of soil could start soil erosion/
Likely siltation of natural water bodies.
Use of Heavy
Construction
Equipment
Erosion could start because of tracks of equipment on road
surface and river banks.
Oil spills could pollute surface and ground water.
Excavation, Cutting
and Filling
Slope instability
Development of erosion or gullies, siltation
Exposure of people to slopes and falls
Blockage of waterway altering hydrology and degrading water
quality
Drainage
Construction
Cause erosion
Affect water quality and river hydrology
Traffic Hazards Increase vehicular speed could lead to increased incidence of
accidents
Road Works Risk of injury from machinery
Poorly operated burrow pits may lead to falls or even
drowning
Traffic Interruption Poorly planned detours may result in accidents
Involuntary
Resettlement
Demolition of houses
Loss of agricultural land
Loss of forestry lands and reserves
Excavation, Cutting May reveal archaeological or other valuable cultural resources
which could be damaged by construction equipment
Public Occupational
Health and Safety
Concerns
Road workers from elsewhere can spread communicable
diseases e.g STDs.
Injury at worksites
Exposure to noise and emissions
Accidents due to poor site management
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
30
Table 5.2: SITE - SPECIFIC NEGATIVE ENVIRONMENTAL IMPACTS WITH MITIGATION
S/N Negative Impacts Mitigation Location
1. Increase Air pollution during construction
(dust) and operational phase (dust during
the dry season and vehicular emissions)
Plant carefully selected resistant trees and hedges along the
roads especially within the villages. The plants would
sequester carbon dioxide and attenuate noise.
Water the roads regularly during construction phase and in
dry season
Provide mask for workers’ used
This is relevant in all
locations
2. Noise pollution from construction
equipment and operational phase, due to
vehicular movement
Provide workers with protective gadgets (ear plugs, mask)
Regular maintenance of construction equipment in
accordance with handbook and manufacturers regulations
to the satisfaction of consultant.
Device mufflers for machines
Workers should not be exposed to noise for more than 8
hours a day
Relevant in all locations
3. Erosion Avoid creating or leaving steep slopes on sides of roads
and where roads pass the base of broken hills
Plant grass and trees in valuable areas
Storm water out fall should be far into the receiving stream
Burrow pits should be properly worked
Excavation spoils should be properly disposed to avoid
beginning erosion
Jambutu-Bogare Road
Njiboli-Njiboliyo-Rugange
Labondo-Gwakrah-Borrong
road
Bazza-Kalikana road
4. Surface water quality impairment Reduce disturbance of top soil and vegetation cover during
site preparation
Construct drainage out fall adequately
Divert river channel when constructing culvert
At locations with culverts.
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
31
A. TABLE 5.3: SITE –SPECIFIC NEGATIVE SOCIO-ECONOMIC IMPACTS WITH MITIGATION
S/N Negative Impacts Mitigation Location
1. 1) Displacement of persons (squatter traders)
2) Destruction of compound fence to create
way for road. Some trees be felled
Provide temporary trading areas for traders during
road construction. Change road alignment away
from built-up areas.
Pay compensation for trees and fence; and for 60m2
of land
Bomari, Bille, Kodomum,
Borrong
Dubwangun
2. Security Risk due to influx of undesirable
elements into communities
Establish day and night surveillance by members of
the communities (youths)
Establish more police posts
Relevant in all locations
3. Spread of communicable diseases due to
increased interaction between local population
and visitors, transit persons, workers etc.
Mount public enlightenment campaigns on
causation and prevention of diseases including
HIV/AIDS and Malaria or other diseases.
Relevant in all locations
4. a) Accidents due to operation of construction
equipment
b) Accidents due to increased vehicular traffic
Ensure re-training of operating staff of machinery
Carry out regular safety drills
Regular maintenance of vehicles
Regular road safety drills for both community
members and drivers.
Install proper road safety signs
Install speed checks especially in the villages.
Relevant in all locations
5. Obstruction of migrating wild-life and grazing Identify the routes and provide protected crossings Gwakrah, Koh, Goron
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
32
cattle with clearly identified entrances and exits.
6. During road operation and maintenance;
- Clearing of drainages could lead to erosion
and sediment transport.
Drainage clearance to be carried out with care not
to scrape the drains while removing accumulated
silt and other solid waste.
Everywhere there are
drainage structures
especially along
settlements.
- Clearing vegetation on road shoulders could
cause loss of construction materials on road
verges and start failure of carriageway
Vegetation control must not involve scrapping with
bulldozers or graders but should be carried out
manually with machetes
Along all the roads with
grassed shoulders.
Replacement of road cover (laterite or gravel)
could result in dust; and noise from compaction
equipment.
This activity would most likely take place in the dry
season. So, the road surface should be sprinkled
with water regularly to reduce dust, compaction
equipment should be adequately maintained
(muffled), to reduced noise. Compaction should
only be done during the day in order not to disrupt
peoples sleep at night. Camp clinic should be
stocked with drugs and remedies for respiratory
tract infections. Workers to put on protective
gadgets- mask and ear plugs.
Along the road routes
especially in settlement
areas.
Dust control through watering the carriageway
could lead to materials losses and could start
erosion.
Effort should be made not to over wet the roads
such that small puddles or rivulets are created. If
possible, an alternative dust control means can be
employed.
Along the road routes
especially adjacent to
settlements.
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
33
Table 5.4 (a): Some Regulatory Standards for Air Quality
Table 5.4(b): Guidelines Governing Exposures to Noise
S/No Pollutant Time Average Limits
1. Particulates (Dust) Average of Daily
Values
One-hourly Value
250mg/m3
600mg/ m3(Not to be
exceeded more than
once a year)
2. Sulphur Oxides (SOx) Daily Average of
hourly values
Hourly average
0.01ppm (26mg/ m3)
0.1ppm(260mg/ m3)
3. Nitrogen Oxides (NOx) Daily Average of
hourly values
0.04ppm-0.06ppm
(75mg/ m3-113mg/
m3)
4. Hydrocarbon particulates Daily Average of 3-
hourly values
8 hourly average
10ppm (11.4mg/m3)
20ppm(22.8mg/m3)
S/No Daily Exposure
(Hr)
Permissible Exposure
Limit (dBA) Remarks
1. 8 90 Exposure to impulsive or impact noise
should not exceed 140dBA peak sound
pressure level.
2. 6 92
3. 4 95
4. 3 97
5. 2 100
6. 1.5 102
7. 1 105
8. 0.5 110
9. 0.25 or less 115
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
34
Table 5.4 (c): Water Quality Standards (National Waters)
Parameters Allowable Limits
BOD 5mg/L (10mg/L Max)
DO 5mg/L (2mg/L Mim)
Fluoride 1ppm
pH 6.8- 7.2
Colour 30NTU
Turbidity 20mg/L
Oil and Grease 0 mg/L
Lead < 0.1 mg/L
TDS 3000 ppm
NO3 1 ppm
SO4 1000 ppm
Fe 0.5 ppm
Mn 0.2 ppm
HCO3-
500 ppm
Cl- 1000 ppm
Table 5.4(d): Noise Levels Construction Equipment are likely to Generate during
Construction
Equipment Type Noise levels at 15m (dBA)
Without Muffling With Mufflers
Earth moving
Front loaders
Backhoes
Bulldozers
Tractors
Scrapers
Graders
Trucks
Pavers
79
85
80
80
88
85
91
89
75
75
75
75
80
75
75
80
Materials Handling
Concrete Mixers
Concrete Pumps
Cranco
85
82
83
75
75
75
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
35
Stationery
Pumps
Generators
Compressors
76
78
81
75
75
75
Impact
Pile Drivers
Jack Hammers
Pneumatic tools
101
88
86
95
75
80
Others
Saws
Vibrators
Asphalt Concrete Batch Plants
78
76
81
75
75
-
Source: USEPA (2001) Asphalt Drum Mixers Inc. (ADM) 1998
5.3 Analyses of Project Alternatives
Alternatives to these Rural Earth Road project include the following:
a. Construction of fully paved asphalt roads
b. Use of Rail transport
c. Do nothing (Zero option)
Alternative (a) Build Fully-Paved Asphaltic Roads
The construction of fully paved roads across the selected terrain would have been
a worthwhile venture in view of the importance of good road networks to the
agriculturally active communities. In view of the terrain being mostly lowland
areas adjoining major rivers, (Flood Plains), the cost of a project of such
dimension would be very high. The amount would hardly construct an
appreciable proportion of the roads of such importance. Hence the desired
objective would hardly be realized.
Also, the communities are expected to be involved in road maintenance and so, a
fully paved asphalt road network would require more sophisticated technology
that is far out of reach of the rural people. Therefore, a more stabilized earth road
would be appropriate as a community project that the community can use and
maintain.
Option (b)”: The Zero Option
The zero option implies that no action is taken to repair or strengthen the road
pavement; leaving the road as it currently is, with all its defects and inadequacies.
The road would therefore:
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
36
- Progressively deteriorate with time in terms of its pavement quality.
- The geometry, vertical and horizontal alignments of the road which are now
even sub-standard for the class of road, would not be improved despite of the
increased vehicular and other traffic in the stretch of road.
- The capacity of the road Section to handle increased traffic load would not only
remain inadequate but actually drop drastically.
- Road conflicts (accident) rate would rise progressively and could become
excessive. Road safety would be jeopardized.
- Development opportunities and benefits as detected elsewhere in this report
would be lost. The regional integration and trans-border socio-economic
activities may progress but only at a slow pace. The movement of goods and
services would gradually (at first) their rapidly (later), grind to a halt.
- Travel time would increase travel comfort would be sacrificed as would safety.
When compared with the alternatives, it is obvious that the road improvement project
has by far overwhelming advantages over the two alternatives discussed above.
Therefore, the lateritic roads project is the preferred development option based on the
analyses. The identified negative impacts have been presented together with
suggested mitigations. If these actions are taken together with the monitoring plan,
the road strengthening project would result in the achievement of the desired
objectives for embarking on the project.
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
37
6.0 ENVIRONMENTAL / SOCIO-ECONOMIC IMPACTS MITIGATION
MEASURES
6.1 Summary of Negative Impacts and Mitigation Measures by Activity
The following mitigation measures are intended for integration into the design
and procurement documents. The potential negative impacts of the RAMPII
Adamawa project requiring mitigation are shown in table 6.1
Table 6.1: Potential Negative Impacts of the RAMPII Adamawa Project and Mitigations
Activity Negative impact Mitigations
Site Clearing Destruction of terrestrial
ecosystem (felling trees and wild
life displacement)
Exposure of soil could start soil
erosion/
Likely siltation of natural water
bodies.
Transplant endangered species. Plant
grass and trees to replace felled trees.
Minimize destruction to ecosystem
Plant grass and trees. Install erosion
control devices
Provide silt traps
Use of
Heavy
Construction
Equipment
Erosion could start because of
tracks of equipment on road
surface and river banks.
Oil spills could pollute surface and
ground water.
Compact soil especially on road
shoulders and verges
Provide sumps to collect spill liquids.
Immediately remove spill materials
from road surface
Excavation,
Cutting and
Filling
Slope instability
Development of erosion or gullies,
siltation
Exposure of people to slopes and
falls
Blockage of waterway altering
hydrology and degrading water
quality
Compact slopes and plant grass
Provide silt traps
Provide adequate warning signs.
Provide alternative routes
Remove (promptly) any material
deposited on or near waterways.
Provide silt traps
Drainage
Construction
Cause erosion
Affect water quality and river
hydrology
Plant grass and trees
Provide proper drainage, silt traps
Traffic
Hazards
Increase vehicular speed could
lead to increased incidence of
accidents
Provide speed checks
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
38
Activity Negative impact Mitigations
Road Works Risk of injury from machinery
Poorly operated burrow pits may
lead to falls or even drowning
Give adequate training to Plant
Operators. Provide safety gear.
Restore spent burrow pits promptly
Traffic
Interruption
Poorly planned detours may result
in accidents
Provide adequate road warning signs.
Provide properly made detours and
restore road promptly
Involuntary
Resettlement
Demolition of houses
Loss of agricultural land
Loss of forestry lands and reserves
Carryout RAP or ARAP and pay
adequate compensation prior to
commencement of the project.
Excavation,
Cutting
May reveal archaeological or
other valuable cultural resources
which could be damaged by
construction equipment
Carry out due consultations and RAP
or ARAP. Restore all affected Cultural
and Archaeological resources
Public
Occupational
Health and
Safety
Concerns
Road workers from elsewhere can
spread communicable diseases e.g
STDs.
Injury at worksites
Exposure to noise and emissions
Accidents due to poor site
management
Mount health awareness campaigns
Provide First-Aid facilities, ambulance
and clinic. Provide safety gadgets
Employ safety /environmental officer
for proper site management.
In addition table 6.2 shows the site-specific potential negative impacts with
mitigation and estimated costs of the measures prescribed.
6.2 Integrating Impact Mitigation into Bidding and Contract Document
In order to effectively manage the identified potential negative impacts, the best
approach is to incorporate clauses in the contract and bidding documents. The
rigorous enforcement of these clauses would ensure the effective mitigation of the
potential negative impacts. The clauses are categorized into “General, Environmental
and Socio-economic clauses and clearly define the contractor’s responsibilities. Only
the general clauses are presented below but the environmental and socio-economic
clauses are in Appendix 6.
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
39
6.2.1 General Clauses
Clause 1: Contractor shall familiarize himself with all National and local laws
and edicts relevant to his activities during the construction phase.
Clause 2: Throughout the implementation phase of the project, the contractor
shall ensure the protection of the environment at all times, to avoid any damage or
create any nuisance to property (public and private) and to persons as a result of
pollution, noise or other causes arising from or as a consequence of his operations
or activities.
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
40
Table 6.2: Summary of Mitigation Implementation by Road Cluster
Road cluster Nature of Impact Mitigation Action Cost ($) Responsibility
A. Northern
1. 1. Kaya-kuda-yinagu
Slope instability, spoil disposal,
dust and noise, health concerns,
road safety concerns
Compact slopes and plant grass, identify
appropriate spoil disposal sites, plant trees along
road. Use speed checks especially in communities,
establish local community policing, mount health
campaigns, wet road periodically
Include
in BEME
Contractor
2. Shuwa-Pallam Ditto Ditto Ditto Ditto
3. Midlo-Mudwu-Madagali Ditto.
Plus water management
Ditto. Provide appropriate water discharge
facilities at stream crossing.
Ditto Contractor and
Consultant
4. Bazza-Kalikasa Ditto
Erosion
Ditto Ditto Ditto
5. Main road-Koe-Koppa Ditto Ditto Ditto Ditto
B. Central
1. Jambutu-Bogare
Slope instability, flooding at
Ngolomba all through to
behind FGGC. Spoil disposal,
dust and noise, health and
safety issues
Ditto
Provide appropriate drainage design
Ditto Implementation
document
2.Njoboli-Njoboliyo-
Rugange
Slope instability, spoil disposal,
burrow pits, dust and noise,
health and safety concerns.
Erosion
Plant grass, identify spoil disposal sites, restore
spent burrow pits, wet road periodically, establish
community policing, mount health campaigns.
Ditto Contractor
SPIU
Consultants
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
41
Road cluster Nature of Impact Mitigation Action Cost ($) Responsibility
5 Kwana waya-Manga Ditto Ditto Ditto Ditto
6 Labondo-Gwakrah-Koh
Goron-Borrong
Slope instability, obstruction of
cattle routes, flooding
especially at Koh and
Gwakrah, dust and noise,
erosion, health and safety
concerns, road is encroached at
Goron and Borrong
Compact slope, plant grass and trees, provide
water, drainage structures, especially at Koh,
Goron and Gwakrah, establish community police
and mount health campaigns. Realign road from
built up areas.
Include
in BEME
Contractor
Consultant
SPIU
C. Southern
1. New Demsa-Old Demsa-
Kodomun-Kwaine
Slope instability, spoil disposal,
land use, dust and noise, water
management, health and safety
concerns, road encroached,
squatter traders along existing
road.
Compact slopes and plant grass and trees, wet road
periodically, provide proper drainage system, re-
align road away from built-up area from CH 11+
450 to CH 13+150 to avoid graveyard, pay
compensation for about 20 juvenile Dum palms
Include
in BEME
Contractor
Consultant
SPIU
2. Kpasham-Kebali-Yanga Slope stability, dust and noise;
spoil disposal, health and safety
issues.
Compact slopes, plant grass and trees, identify
proper spoil disposal sites, establish community
police, mount health campaigns.
Ditto Ditto
3. Bille –Gumari-M-Belwa Slope instability, dust and
noise, erosion, spoil disposal,
road is encroached, burrow
pits.
Compact slopes, plant grass and trees, identify
spoil disposal sites, restore burrow pits, wet road
periodically, provide appropriate drainage. Re-
align road and pay compensation for about 20
trees.
Ditto Ditto
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
42
Road cluster Nature of Impact Mitigation Action Cost ($) Responsibility
4. Gyawana-Dubwangun-
Hadiyo-Lamurde
Slope instability, water
management, dust and noise,
road is encroached at
Dubwangun, some trees to be
felled and some land acquired,
water pipeline near road
pavement, health and safety
issues.
Stabilize road, plant trees, provide proper
drainage, wet road periodically, and pay
compensation for 36 trees and 60m2 of lands.
Assist household with new fence. Community
police and health campaigns
Ditto Contractor
Consultant
SPIU
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
43
7.0 ENVIRONMENTAL AND SOCIO-ECONOMIC MANAGEMENT PLAN
7.1 Introduction
This environmental and socio-economic management plan would act as an
abridged operational manual for the project with respect to environmental and
socio-economic issues during implementation and operation. In practical terms, it
details how the mitigation measures proposed should be carried out; and the
responsibilities and frequencies of the actions.
7.2 Key Stakeholders
The key stakeholders in the environmental and socio-economic management plan
are: The Federal Ministry of Agriculture (FPMU), the Federal Ministry of
Environment (FMEnv.), Adamawa State Government (SPIU). The design
engineers (YPL), Contractors, Local Government Area Councils and the
beneficiary communities. A summary of the roles of the key stakeholders is
presented in table 7.1.
7.3 Actions and Responsibilities
A number of possible negative impacts were identified during the ESIA.
Mitigation measures to minimize or eliminate the impacts have been proposed
with details of the actions, responsibilities and estimated costs. The
responsibilities of the key stakeholders are in table 7.1. Table 7.2 contains the
monitoring indicators and table 7.3 a summary of the environmental and socio-
economic management plan (ESMP).
7.4 Monitoring
7.4.1 Environmental and Socio-Economic Compliance Monitoring
The implementation of the various measures for the mitigation of the potential
negative impacts of the roads requires the input of a well-funded
environmental monitoring programme. The scheme would aim at the
collection of information or data that would enable the assessment of the status
of the concerned environmental/socio-economic parameter, and to take prompt
action, if need be, towards forestalling the occurrence, or to reduce to the
barest minimum, its negative impact or regularity. Monitoring also enables a
co-ordinated scheduling of activities between all project stakeholders. Table
7.2 lists some of the important monitoring indicators while table 7.3 deals with
the details of the parameters to be monitored.
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
44
Table 7.1: Responsibilities of Key Stakeholders
SN Stakeholder Responsibilities Project Phase
1. FGN Overall control and policy formulation for project
funding guarantees
Receive and consider regular project progress
and project performance report.
Project
Preparation
Project execution
2. FMEnV Issue the necessary environmental permits,
provide monitoring framework, enforce
regulations
Preparation
Execution
Demobilization
3. FPMU Co-ordinate all RAMP II projects, engage project
consultants, monitor project execution, co-
ordinate maintenance activities
Preparation
Execution
Demobilization
4. SPIU Identify roads, co-ordinate resettlement
activities/compensations. Co-ordinate local level
road maintenance
Preparation
Execution
Demobilization
5. Consultant
(Design
Engineers)
a. Design for erosion control, water management and
other negative impacts.
Project Design
b. Incorporate suitable clauses committing contractor to
execute his task with due diligence applying
environment friendly methods. The document should
include necessary monitoring and enforcement clauses
consistent with best practices.
Preparation of
Contract
Document
Phase
c. Supervise contractors performance and ensure that
regulations and instructions are enforced with respect
to socio-economic and environmental provision in the
contract document
d. Liaise with local health, traffic and educational
authorities to plan agreed awareness campaign
Implementation
Phase
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
45
SN Stakeholder Responsibilities Project Phase
6. Contractor a. Ensure that all management staff including foremen,
safety officer and site managers are conversant with
environmental and socio-cultural issues of the
RAMPII
b. Make sure that all staff above are informed about and
fully understand environment-friendly construction
methods relating to environmental sustainability
c. Establish, operate and maintain construction
Mobilisation
Phase
Camps and rehabilitate campsite after project
d. Prepare and submit burrow pit management plans for
approval by relevant authorities and consultant in good
time before exploitation commences.
e. Prepare, establish and submit to consultant, waste
management plan for all categories of wastes
f. Acquaint himself with all the relevant environmental
legislation and regulations in Nigeria and Adamawa
State.
g. Ensure that all socio-economic and environmental
requirements of the project are satisfied.
h. Utilize only environment friendly methods and
equipment in the project
i. Take responsibility for the occupational health and
safety of all persons at the worksites at all times.
j. Inform consultant of any negative (unforeseen)
impacts arising from the project.
k. Provide safety around and through all work sites for
all kinds of traffic. For this purpose, provide
acceptable Traffic management Plan (TMP) to the
consultant
l. Provide and implement erosion prevention measures
e.g. grass and tree planting in exposed areas.
m. Provide appropriate storage for fuels, oils and
lubricants and wastes to prevent both water and land
pollution
n. Provide potable water to any community whose water
Project
Execution
Phase
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
46
SN Stakeholder Responsibilities Project Phase
source is made unwholesome by project activities till
water quality is restored.
o. Ensure that no unmarked tree is felled or else face
fines to be deducted from next payment due. Felled
trees remain the property of the FGN.
p. Manage all wastes from all construction activities in a
manner consistent with best practices.
q. Eliminate all breeding sites of disease vectors arising
from project activities.
r. Ensure that all project areas are properly cleaned and
restored.
Demobilisation
7. World
Bank and
FDA
Quality control of project
Fund mobilization efficiency and effectiveness
Ensure timely execution of project
Throughout the
project
8. NGOs’
CBOs’
Work with community members throughout the
project.
Drive community policing
Be involved in the maintenance activities,
participate in Health awareness campaigns
Throughout the
project
9. Community
Members
a. Express any concerns about the project both in the
preliminary design and at any other phase of the
project including those not originally envisaged.
b. Be prepared to participate fully in road maintainace
activities.
c. Be prepared to participate in community policing.
d. Be prepared to participate in road construction work.
e. Be prepared to participate in health awareness
campaigns.
Throughout
Project Phase
7.5 Waste /Environmental Management
The contractor should employ an Environmental/Safety Officer for the project, to
be responsible for all safety and waste management issues, including fire risk.
Wastes are expected to be generated during project execution in the form of
spillages emissions from plant operation and excavations, bush clearing etc,
during site development for establishing camp sites. Also, wastes (both liquid and
solid), would be generated at the camps- in the form of wastewater and garbage.
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
47
The wastes should be categorized into: gaseous, liquid and Solid Wastes.
Gaseous emissions include sulphur, nitrogen and carbon oxides from burning
fossil fuels. The quantities of these gases are not expected to be significant.
Liquid wastes – spilled fuels, lubricants and wastewater. The oily wastes (Diesel
oil, gasoline and engine oil) are to be confined to the fuel depot. Spillages should
be washed into a concrete sump from where they can be collected and taken for
proper disposal (Refinery). Domestic wastewaters should be channelled into
soakaways and septic tanks at the yards (camp sites).
The solid wastes should be segregated into garbage, plastic, paper, metallic wastes
etc.
- The garbage should be composted (i.e. buried)
- The plastics e.g. bottles and bags, could be re-used for storage thereby
minimizing the waste. Those that cannot be re-used should be collected and
stored in tied bags to be sent for recycling in plastic factories.
- Metallic wastes should be collected and stored for recycling (sold to
scavengers)
The client should have a social monitoring plan (SMP). The company does not
need to have a separate unit for SMP but officers should work in collaboration
with the client.
A monitoring plan should be produced by the contractor and his company
should be ready to comply with the directives. Table 7.2 shows the monitoring
indicators of the project
Health Care facilities
A few health care facilities (clinics, maternities) exist in some of the road
corridors e.g., Bazza to Kalikasa road. The effectiveness of the health care
facilities can be monitored by evaluating the
- The number of patients (cases) attended to on a periodic e.g quarterly
basis; particularly road accident victims.
- The disease pattern over the entire area over time (say quarterly)
- Successful birth rate figures over time (say quarterly)
- Maternal mortality rate over time in the area (also quarterly)
- Child mortality rate over time (quarterly) in the area
- Disease surveillance in the area (if any)
- The level of sanitation, health and hygiene practices in the area
- Successes of immunization programmes
- The efficiency of ambulatory services between the PHCs and the General
Hospital
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
48
These indices are to be computed for the road corridor and compared with
those before the rehabilitation, to indicate if the road rehabilitation has
impacted in any way on the health life of the communities.
The responsibility for monitoring is vested in the contractor who should
produce his scheduling plan to the consultant.
Table 7.2: Project Monitoring Indicators
S/No Item Monitoring
frequency
Method of
Sampling Monitoring indicators
1. Improved access Quarterly Grab Traffic count
2. Crime Rate Monthly,
Quarterly
and Yearly
Records of all
reported crimes kept
Numbers of different crimes
reported.
3. Accidents Once a
month
Grab 24 hour sample
and collate
Numbers of accidents
reported as number of
fatalities, injuries,
hospitalized
4. Road Sign
Awareness
Quarterly Analysis of accident
records and driver
assessment
Number of accidents due to
road sign violations
5. Health Care
facilities
Quarterly Analyses of Health
records
Number of patients treated at
clinics, live birth rate figures
of maternal mortality rates
child mortality rates. Success
rates of immunization,
number of ambulance
services carried out.
7. Soil quality
Near Solid waste
Dumps in camp site
Intervals at road
axis
Ecological
Preservation in
burrow pit areas
During Dry
and rainy
season
ditto
Grab/Visual
observation
Visual
Soil moisture, salinity, So4,
NO3 PO4, hydrocarbons and
photographs
Photographs
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
49
S/No Item Monitoring
frequency
Method of
Sampling Monitoring indicators
8. Air Quality
Ambient air quality
within operations
area (asphalt plant,
quarry sites etc)
around the
construction
equipment and
diesel generating
set locations
Once a
month
Grab (24Hrs hourly)
sample
SOx, NOx, CO,CO2 NHx
Particulates
9. Noise level
Plant boundaries
(asphalt plant,
quarry sites etc)
Around
Construction
equipment and
diesel generating
sets
Once a
month
Grab (24Hrs hourly)
samples
Noise levels (dBA)
10. Water Quality
Testing
Once a
month
Grab sample for PO4
,SO4, NO3, oil and
Grease
Compare with water quality
standards.
11. Disposal areas
(waste dump and
oil sumps)
Once a
month
Visual observation
Grab Samples
Photographs and
Video
Hydrocarbon, Oil and grease
photographs and video
recordings
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
50
Table 7.3: Environmental/ Socioeconomic Management Plan (ESMP), Mitigation Measures with Responsibilities and Cost
S/N Project Impact Source of Impact Mitigation Measures
Mitigation compliance
index
(frequency)
Approximate
Mitigation
cost/year (N)
Responsibility
A
Ecology
Loss of Habitat
and Biodiversity
Airborne and
Noise Pollution
Soil erosion and
change in
drainage patterns
Sand mining
Transportation
Site Preparation,
removal of trees and
shrubs
Increased traffic from
heavy equipment.
Removal of vegetation
cover and deposition
on drainage channels
Working of burrow
pits
Increased water
depth, could affect
channel characteristics
Spillage at fuel
Transplant endangered species.
Plant 4 new tress for everyone
felled
- Sprinkle water over scraped
road surface. Maintain
equipment, plant trees/shrubs
Provide Personal protective
equipment for the workforce.
(ear muffs nose masks, gloves,
helmets, boots, etc.)
Clear natural drainage and create
new ones to ensure free flow of
runoff.
Restore burrow pits by replacing
top soil
Monitor sand source
Provide lined sumps to collect
All endangered species
are transplanted and/or
rehabilitated. New trees
planted(Bi-monthly)
- Reduction in dust and
noise levels
- protective equipment are
seen to be used
(Always)
Free flow of water in
drains.(Weekly)
Original land forms
restored (Afterwards)
Measure depth of water at
sand source.
(Twice a year)
80,000.00
300,000.00
23,400,000.00
(i.e for 13 roads)
@ 1,800,000.00
(per road)
1,000.00
200,000.00
Contractor.
Contractor,
communities,
SPIU, LGAs
Department of
works, RAMP,
Consultant
RAMP, SPIU,
Contrac0tor,
Consultant,
SEPA.
RAMP, SPIU,
Consultant,
SEPA.
Contractor
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
51
S/N Project Impact Source of Impact Mitigation Measures
Mitigation compliance
index
(frequency)
Approximate
Mitigation
cost/year (N)
Responsibility
and storage of
construction
materials
Disposal of
construction
Debris
Soil and water
pollution due to
Solid waste and
liquid waste
generated
Effect of concrete
curing water on
the environment
dumps, improper
storage of chemicals
and explosives
Removal of road
surfacing and culverts
Wastes generated
from restaurant, clinic
and living quarters
Construction of
prefabricated concrete
structures
waste fuel lubricants and
solvents for easy removal for
final disposal- Ensure proper
storage of solvents and
explosives with appropriate
warning signs
Reuse debris as base material for
new roads or for filling potholes
Segregate wastes at the point of
generation. Provide septic tank
and soak away for liquid waste.
Compost organic waste.
Recycles and reuse others where
possible.
Check soil Quality
Ensure proper channelling into
drainage pits
Regular evacuation of the
sumps.(Monthly)
Regular inspection of
explosive and chemical
stores. (Quarterly)
No construction debris left
unattended. (Always)
The environment is clean
and free from waste and
garbage.
(Daily)
Soil not contaminated
with oil and
grease.(Quarterly)
Water quality test results
comply with standards.
No accumulation of
curing water(Monthly)
120,000.00
BEME
100,000.00
200,000.00
500,000.00
Contractor
Contractor
Contractor
Contractor
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
52
Table 5.1: Cont’d.
S/N Project Impact Source of Impact Mitigation Measures Mitigation compliance index
Approximate
Mitigation Cost
(Contractor)
N
Responsibility
B Socio-economic
impacts
Land use
Employment and
income
Transportation
Social stratification
due to improved
income.
Reduction in farming
activities due to
unskilled labour
mobility
Difficulties in going
to work
Monetized housing policy
for both senior and junior
staff.
- Provide appropriate
transport for movement
of work force to and
from work locations
- Management staff are
housed in Camps
- Housing allowance is paid
to each class of workers.
(During execution)
- Senior and Junior staff are
employed.
- Unskilled labour is
engaged from the
community. (During
execution)
- Adequate transportation is
provided
(During execution)
25,000,000.00
For
construction,
furnishing and
maintaining at
least 5 (No)
houses
BEME
BEME
BEME
Contractor,
Contractor
Contractor
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
53
S/N Project Impact Source of Impact Mitigation Measures Mitigation compliance index
Approximate
Mitigation Cost
(Contractor)
N
Responsibility
Community
development
- Population
dynamics
- Public health
- Increase in vices
Employ local labour
Provide amenities
Equip Site clinic with
drugs and a site nurse
Provide police posts
Organize surveillance
- Most Communities along
the road axis are provided
with amenities (electricity,
boreholes etc).
- Health is taken care of by
a staff Nurse already
employed. (During
execution)
BEME
BEME
Contractor
C Construction
Hazards
Hold - ups
Accidents
Prefabricated
concrete structures
- Diversions
- Slippery surfaces
- Heavy construction
equipment on roads
- Provide adequate warning
signs (Bend, Slow Down,
Men at Work, Diversion,
Heavy Equipment
Crossing, etc)
Adequate warning signs have
been deployed including
human traffic control in day
time periods (As required)
Part of Contract
Sum
Contractor
D Restoration of
Burrow pits
Source of construction
materials
Should be filled back
with removed top soil and
construction wastes
Burrow pits are restored.
(soon after work)
Part of Contract
Sum
Contractor
E Solid waste
management (local
population to be
educated and
encouraged)
- Debris from
construction
activities
- Sorting of solid
waste
- Debris should be used for
construction of houses
- Components such as
bottles, metals and,
plastics can be resold
Environment is free of solid
waste (daily)
1,500,000.00 for
design, building
and operation of
composting
plant.
Contractor
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
54
S/N Project Impact Source of Impact Mitigation Measures Mitigation compliance index
Approximate
Mitigation Cost
(Contractor)
N
Responsibility
- Garbage from
restaurants and
living quarters
- Composted waste can be
used as manure as well as
generate gas for domestic
use
F Health Challenges - Increased STDs
- Unwanted
pregnancies
- Provide health awareness
campaigns
- Distribute condoms
HIV and malaria awareness
campaign put in place
Keep records of condom
distribution. (At least 3 times
per cluster, i.e 9 campaignes)
9,000,000.00 for
campaign of 3
clusters (i.e.
1,000,000.00 per
campaign)
Contractor, SPIU,
Consultant.
G Fire Safety and
Emergency
Management
- Mal-functioning of
electrical equipment
- Conduct fire and
emergency training and
drills
- Install fire fighting
equipment
Fire and emergency training
and drills conducted
Fire fighting equipment
installed. Health and Safety
Records (At least 5 times a
year)
2,500,000.00
(i.e. 500,000.00
per training for
honorarium,
transport,
accommodation
of resource per
son and
refreshment at
training
Contractor
Grand Summary in Naira 62,901,000.00
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
55
7.6 Measures for Strengthing Institutional and Organisational Capacity
Capacity Building
There are many capacity gaps in the project area both in terms of farming and
other livelihoods; training needs, institutional strengthening and
facilities/infrastructural development. A summary of the capacity needs are in
table 7.4
Table 7.4: Capacity Building (Training) Needs
S/N S/N Capacity
Needs Participant Subject
Resource
Persons
Cost per
Participant
($)
Duration
1. Dry season
farming
Farmers
Near
waterways
Irrigated
Agriculture
Extension
worker from
ministry of
Agriculture,
Upper Benue
RBDA
1,000.00
including
transport
accommodatio
n and
honorarium
for resource
person
1 week
2. Farming
System
Other
Farmers
Intercropping/
mixed
cultivation
Extension
worker from
ministry of
Agriculture,
Upper Benue
RBDA
1,000.00
Ditto
1 week
3. Skills
Acquisition
(a)
Women as
well as some
young men
Dressmaking
Hairdressing
National
Directorate of
Employment,
NGO/CBOs
24,000.00
6 months
(b) Youths Road
maintenance
State/LGA
Department of
works,
contractors
4,000.00 4 weeks
(c ) Community
members
(youths)
Environmental
Sanitation
Practices
State/LGA
Ministry of
Health/Environ
ment
Consultant
1,000.00 1 week
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
56
S/N S/N Capacity
Needs Participant Subject
Resource
Persons
Cost per
Participant
($)
Duration
4. Training
a
Community
members,
contractors
staff etc.
Malaria/HIV-
AIDS
Awareness
campaigns
Consultant
Ministry of
Health
1,500.00 for
each
Campaign
4,500.00 for
three.
Two or
Thrice
during
project
construction
phase (Day)
b.
c.
LGA Staff
SPIU Staff
Training in
RAMP
Operation and
management
FPMU
Consultants
Needs
Assessment
first
1 week
d. LG Council
Staff
SPIU Staff
Institutional
Strengthening
Consultant
FPMU
Needs
Assessment
first
Progressive
5. Construction
and
maintenance
of equipment.
LG Council
Staff
SPIU Staff
Road
Maintenance
equipment
training/acqui
sition
Manufacturer’s
Representative
Needs
Assessment
first
2 weeks for
training
6. Honorarium, Transport, Accommodation, Feeding for 20
resource person
20,000.00
Total per participant $55,500.00
7.7 Capacity of CBOs and local institutions
In nearly all the communities along all route corridors, there are varieties of
CBOs. These associations are mostly on gender- and agro - lines, and border on
improved livelihood of members and general community development. In nearly
all communities, however, such associations are generally very weak. The
officials of most of the associations lacked the minimum skills and capacities to
reach out to other relevant organizations and government institutions at state and
national levels. On the other hand, the capacity of government sponsored local
institutions in few of the communities is also very weak. The Local Government
Council, which is the nearest government to the community, lacks the adequate
capacity in terms of manpower and financial resources to perform the roles
expected of it (i.e. improvement of the socio-economic life of members of the
community). It is also evident that the Local Government Council expends most
of its resources on urban and semi-urban areas within its jurisdiction. This leaves
out rural communities in the present study area at a disadvantage. The
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
57
community/social development units in the Local Government Councils need
upgrading.
7.8 Perception of the proposed road project
Overall, the awareness and reception of the proposed road is excellent in the
respective communities. All the residents of the communities visited expressed
joy at the proposed project. Their expectation is that it will promote development
in the region by way of job creation, infrastructural development, in particular,
housing, healthcare, better schools, portable water and electricity supply, and most
probably promote tourism. From the consultations held with the community
members along the roads, the following are the appreciations noted by the
stakeholders.
Increased road strength and capacity
All year access would be provided
Improved drainage and reduced flooding
Reduction cost of transportation
Increased travel comfort
Reduced vehicle operating cost and travel time
Attraction of investment and businesses
Increased revenue of local people from businesses
Increased employment during construction and road maintenance phases
Enhance regional integration and harmony
Improved living standards
Nevertheless, the stakeholders expressed some concerns regarding the following
issues:
Timelines and adequacy of their compensation packages where applicable
Increased atmospheric dust and noise during construction
Provision of adequate road signs and other architecture to reduce
pedestrian- vehicular conflicts
Pedestrian safety in the settlement areas along roads corridor
Pedestrian and travellers safety with respect to vehicular speed
Proper location and rehabilitation of burrow pits and quarries
Public awareness and education about the project especially the road
maintenance activities.
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
58
8.0 SUMMARY AND CONCLUSION
8.1 Summary
After the Environmental and Socio-Economic Impact Assessment exercise for
Adamawa State RAMP II Project, the key issues identified are summarized as
follows;
In the recent past (10 years) a good number of changes have taken place in the
country to strengthens the National policy and the legislative framework for
managing the country’s’ resources as defined in the National Policy on
Environment (Agenda 21) of 1999. Considerable progress has been made in
establishing the policy and legal framework for environmental concerns, but the
institutional capacities of the enforcing agencies are still being developed
(NESREA). The overall responsibility for implementing the various
environmental legislations is vested in the Federal and States Ministries of
Environment through their different agencies.
Some key pieces of legislation to facilitate environmental management in Nigeria
are; the Environmental Impact Assessment ACT (2004); Harmful Waste (special
criminal provision etc) ACT (2004); Water Resources ACT (2004) and the
National Environmental Standards and Regulations Enforcement Agency
(NESREA) ACT 2010, to mention a few.
During the ESIA field survey, it became obvious that the internal capacity for the
environmental and social management of the road sector needs to be strengthened.
The consultants and contractors and other sector players need to acquire self-
regulatory roles regarding environmental impact management.
When the list of roads was given, no road map was supplied. Some names of the
villages along the routes were wrongly spelt and distances were inaccurate in
some cases.
There is really no major significant negative impact anticipated to be associated
with the project as the predicted potential negative impacts are predominantly
direct and short term. If the mitigation measures proposed are implemented, such
impacts would be greatly minimized or even eliminated.
Some factors interact to give rise to environmental impacts on road projects. For
instance, erosion on roads arises from the interaction between design,
construction, surrounding land use and soil type. As such the definition of
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
59
quantifiable evaluation criteria to enable the assessment of impact trends is
difficult. Therefore, one usually resorts to taking a qualitative approach derived
from information about the area and references of other activities.
The nature of the RAMP II project in Adamawa State is such that virtually all the
construction work would be on the existing roads alignment and so, would avoid
or considerably reduce the intensity of the adverse impacts, usually experienced in
new roads construction. Good management, good engineering design and good
construction and supervision would ensure the effective mitigation of the impacts.
There would be no direct impacts on sensitive environments like habitats,
sanctuaries, cultural heritage or archaeological finds as a result of this project.
One family at Dubwangun would be affected through the acquisition of about
60m2 of their land and the removal of a fence of trees surrounding their
compound. This is to allow for a widening of the road adjacent to the compound.
This family will suffer only a very marginal discomfort and an ARAP has been
prepared for it.
One important problem militating against effective environmental management of
road projects is the general lack of awareness of field engineers, contractors and
many stakeholders, about environmental issues and concerns. It is very unlikely
that any real support to address this can be provided in the short term.
As much as possible, the World Bank requirements stipulating the involvement of
the beneficiaries in project cycles have been highlighted as a strong tool for
environmental management and sustainability of the project.
8.2 Conclusion
This ESIA report has considered the environmental and socio-economic
implications of executing the RAMP II project in Adamawa State, in consonance
with the ToR.
There is generally a heightened awareness among members of the public who
show concern and expect high quality services. Therefore, it is important that
efforts are made to address the relevant environmental and social issues identified.
With respect to RAMP II in Adamawa State, the contractor and the supervising
institutions must show a high level of commitment to the effective implementation
of the mitigation measures. Invariably, a systematic programme of capacity
building for manpower development is essential.
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
60
After examining all the components of the RAMP in Adamawa State, it may be
concluded that the project is feasible and viable. Compared with the alternatives
which analyses have been documented in Chapter 4, the rural road project is
capable of boosting agricultural productivity, improved livelihoods, economic
empowerment, socio-cultural harmony and integration in the project areas.
However, the realization of these noble objectives is firmly rooted in the political
will, commitment and determination of all stakeholders to vigorously implement
all the safeguards and mitigations recommended to address the negative
environmental and socio-economic impacts identified. The ESMP prescribed has
adequately specified the tasks and responsibilities of the various stakeholders
whose compliance would greatly enhance the sustainability of the project.
Disclosures:
The ESIA ARAP and ESMP documents would be disclosed by the FPMU who
would make copies available to all their State Project Implementation Units, their
websites, and to PAPs. Copies would also be sent to the State and Federal
Ministries of Environment for public display on their notice board; and to the 8
Local Government Area councils where the project is domiciled. Efforts would
also be made to display the documents at strategic public places in the project area
for the benefit of stakeholders. When the FPMU has done this, the World Bank,
the French Development Agency would then disclose them electronically in their
websites.
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
61
REFERENCES
Abbreviated Resettlement Action Plan. Kenya Highways; National Authority Kenya.
Bijaya Raj Paudyal et al (2002): My field to Rural Community Environmental
Awareness. BMX - V Consultants.
Biodiversity in Development: Road infrastructure and Biodiversity, brief 8
http://europa.eu.int/comm/development/sectir/environment.
Boating E., Ewusi K, Kanbur R. and Mc kay A. (1992): Poverty Profile for Ghana,
1987, 1988.Journal of African Economies 1 (1) s 26-58, March.
Branch, K., D.A. Hooper, J. Thompson, and J. Creighton, 1984. Guide to Social
Assessment: a Framework for Assessing Social Change, Westview Press Boulder.
Burge, R.J. P. 1995, A Community guide to Social Impact Assessment. University of
Illinois: Urbana.
Burdge, R.J.P. Fricke, K. Finsterbusch, W.R. Freudenberg, R. Gramling, A. Holden, L.
Byron, H (undated).Biodiversity issues in the road environmental impact assessments:
Guidance and case studies. Environmental policy and management group, TH Huxley
School of environment, Earth sciences and Engineering, Imperial College, London,
U.K.
Canter L.W (1977): Environmental Impact Assessment. McGraw Hill Book
Company, New York.
Case Design (2003): Highway Design Notes 1-4. Publications of the Transport
Research Laboratory, TRL, Old Wokingham Road Berkshire, U. K. RG45 6AU.
Canter, L.W. 1985, Socio-Economic Factors Used Environmental Impact Studies, In
Canter L.W. Impact of Growth: a Guide of social-Economic Impact Assessment and
Planning, Pp. 328-394, Lewis Publishers: Chelsea, MI.
Carley, M.J. and Busteilo, E.S (1984) Social Impact Assessment and Monitoring: A
guide to the literature.Boulder: Westview Press.
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
62
Chadwick, A. 1995.Social-Economic Impacts 2: Social Impacts.In Morris, P. and R.
Therivel, Methods of Environmental Impact Assessment, pp 29-49. University of
British Columbia Press: Vancouver.
Chenoweth, R. 1999. Integrating Information Technologies for Citizen-based Land
use Decision-Making. College of agricultural and Life Sciences, University of
Wisconsin.
Christensen, K. social Impacts of Land Development: an Initial Approach for
Estimating Impacts on Neighborboard Usages and Perceptions.The Urban Institute:
Washing ton D.C.
Clarke, B. D. Chapman, K. Bisset, R. and Withern, P. (1976): Assessment of major
Industrial Application.A Manual.Research Report 13.Department of the Environment,
London, UK.
Environmental Protection Agency, Office of Wasterwater Management and Region
V. 1990, Urban Runoff Management Information/Education Products. OWEC (EN-
366) Washington, D.C.
FEPA (1992) Environmental Impact Assessment – Sectoral Guidelines:- Agricultural
and Rural Development. Publ. by Federal Environmental Protection Agency, Nigeria
Pp. 28-48.
Finsterbusch, K. (1985) State of the Art in Social Impact Assessment. Environment
and Behaviour 17, 192-221
Freudenberg, W.R. 1986. Social Impact Assessment.Annual Review of Sociology.
12:451 - 78 Gontier, M., Balfors, B. and Mortberg, U. (undated). Biodiversity in
environmental assessments current practice and tools for prediction.Environmental
Management and Assessment Group, Department of Land and Water and
Resources.Engineering, Royal Institute of Technology SE-100 44 Stockholm, Sweden
[email protected]/ [email protected]/[email protected].
Handbook for Preparing a Resettlement Action Plan: Environment and Social
Development Department, International Finance Corporation(IFC)
Hustedde, R.J., R. Shaffer, G. Plover. 1983. Community Economic Analysis: a how-
to Manual, North Central Regional Center for Rural Development, Ames, Iowa.
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
63
International Association for impact assessment (IAIA) http/www.iaia.org.
International Association for Impact Assessment (1994) Guidelines and Principles for
Social Impact Assessment 12 (2)
International Committee on Guidelines and Principles for Social Impact Assessment
(1994) Guidelines and Principles for Social Impact Assessment US Department of
Commerce; National Oceanic and Atmosphere Administration; National Marine
Fisheries Service
Ita, E.O. (1994). Aquatic Plant and Westland wildlife Resources of Nigeria.CIFA
occasional paper no 21, FAO, Rome 52pp.
Liewellyn, J.S. Petterson, J. Thompson, and G. Williams, 1995.Guidelines and
Principles of Social Impact Assessment.Environmental Impact Assessment
Review.15-11-43, Elsevier Science, Inc. New York.
Ohm, B.W. 1999. Guide to Community Planning in Wisconsin.Department of Urban
and Regional Planning, University of Wisconsin-Madison.
Resettlement Action Plan for Amugulang-Ebudouge ClassIII Porthighway. Inner
Monogolia Autonomous Region Communications Department 2004.
Resettlement Policy Framework (RPF) for RAMPII in Adamawa, Enugu, Niger and
Osun States: Federal project Management Unit(FPMU), Federal Ministry of
Agriculture and Rural Development Abuja.
RSPB, WWF, English Nature and the wildlife Trust (2000). Biodiversity and
Environmental impactassessment: A New Approach. RSPB,
Sandy.http/www.rspb.org.uk.
Ryan B.J. Braatz and A. Brault. 1998. Retail Mix in Wisconsin’s Small Downtowns:
An analysis of Cities and Villages with Populations of 2,500-15,000. Center for
community economic Development, University of Winsconsin-Extention.
Trusty, W. 1999, Land Use Planning, Design Review: Essential Components for
Maintaining Countryside Character. Prepared for the Planning Committee and Town
Board of Lyons, Walworth County.January 6, Urban Land Institute, Development
Impact Assessment. Chapter 6, Social Impact Analysis.
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
64
Wood, C. M. and Lee N. (1984): Methods of EIA in Project Appraisals
Department of Town and Country Planning, University of Manchester, Manchester,
England
World Business Council for Sustainable Development (2005) Environmental and
Social Impact Assessment (ESIA) Guidelines.
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
APPENDICES
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
APPENDIX ‘I’
Site Photographs of Adamawa RAMP II Road Conditions
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
Fig. 1: Exsisting road ravaged by erosion2: Erosion ravaged
landscape, Zah area, Michika LGA
Fig. 2: Highly dissected terrain at foot hill of the Eastern
Piedmont mountain ranges, Zar area Michika LGA
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
Fig. 3: Upland hill ranges of the Eastern Piedmont Mountain at the
background, Zah area Michika LGA
Fig. 4: Outliers of mesas and buttes Zah area Michika LGA
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
Fig. 5: Typical scenery over the Benue River trough showing gullying, in Kebali, Demsa LGA
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
Fig. 6: Children scooping out water from river bed in the dry season
Fig. 7: Federal rural water supply Project in Njoboliyo, Yola South LGA
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
Fig. 8: Water vendor at suburb location, Kwanawaya, Yola South LGA
Fig. 9: Terrace cropping, at Zah area in Michika LGA
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
Fig. 10: Terrace cropping, in Zah area Michika LGA
Fig. 11: Uncultivated alluvial soils –Mbemun (Larmude LGA)
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
Fig. 12: Typical park land vegetation close to settlement
Fig. 13: Compound vegetation, Bitiku, Madagali LGA
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
Fig. 14: Scrub land
Fig. 15: Dum pam forest at Kodomun, Demsa LGA
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
Fig. 16: Riparian forest- Kebali, Numan LGA
Fig. 17: Fuelwood merchant heading to town- picture taken at Goron
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
Fig. 18: Savanna sugar company plantation at Mbemun, Lamude LGA
Fig. 19: Irrigation cropping along floodplain over highland area sefa, Michika LGA
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
Fig. 20: Quarying for brick block moulding, Lawe, Demsa LGA
Fig. 21a: Typical scenery during the soccio -economic survey of
communities along the road corridors -Kebali Numan.
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
21b .
21c .
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
Fig. 21d: Yanga, Demsa LGA
Fig. 21e: Yanga, Demsa LGA
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
Fig. 21f: Partial encroachment spot on the road at Dubwangun, Larmude LGA
Fig. 21g:: Segement of encroachment at Kodomun, Demsa LGA
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
Fig. 22a: Typical village compound on the Benue flood plains, Kebali, Numan LGA
Fig. 22b: Typical compound over the foothill, Sefa area Michika LGA
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
Fig. 22c: Typical compound over the foothill, Zah area Michika LGA
Fig. 23a: Typical market under tree at village square, Goron, Gerei LGA
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
Fig. 23b: Market at village square
Fig. 24a: Village mechanic at Njoboliyo
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
Fig. 24b: Village kiosks
Fig. 24c: Tailoring services under NDE programme, Sefa, Michika LGA
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
APPENDIX ‘II’
List of Economic and Medicin al Plant in the Project Areas
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
LIST OF PLANT ALONG KWANAN WAYA-NAMTARI ROAD (YOLA SOUTH L.G.A)
S/N BOTANICAL NAME FAMILY COMMON NAME HAUSA NAME ETHNO-BOTANY
1. Azadirachta Indica Meliaceae Neem Dogon yaro Insecticide
2. Tamarindus indica Leguminosae:C Tamarind Tsamiya Laxative
3. Hyphaene thebiaca Palmae Dum palm Goriba Leaves (Jaundice)
4. Annogeissus leiocarpus Combretaccea African Birch Marke LVS (cough)
5. Guiera senegalensis Combretaceae Senegals guiera Sabara Anti diarrhoeal
6. Borassus aethiopum Palmae Fan palm Giginya Root (sore Throat)
7. Combretum molle Combretaceae Combretum Gogen damo Bark (injuries)
8. Daniellia oliverii Leguminosae:C Balsam tree Kadaura Bark (Menstrual disorder)
9. Adansonia digitata Bombacaceae Baobab Kuka LVS (Asthma)
10. Khaya senegalensis Meliaceae Mahogany Madaci Bark (malaria Fever)
11. Acacia polyacantha Leguminosae:M Flat spine gum Arabic Kumbar shaho Root (snake bite)
12. Teminallia avvicennoide Combretaceae Terminacia Baushe Anti bacterial
13. Wissadula amplisima Malvaceae Wissa leave
14. Dichrostachys cinerea Leguminosae:M Double flower
Marabou thorn Dundu Root (diuretic)
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
15. Waltheria indica Sterculiaceae Indian waltheria Hankufa Adrenalin sufressor
16. Lannea acida Anacardiaceae Lannea plum Faru Venereal diseases
17. Adansonia digitata Bombacaceae Baobab Kuka Lvs. (Asthma)
18. Phoenix dactylifera Palmae Dabino Lvs. (Mat weaving)
19. Musa sapientum Musaceae Banana Ayaba
20. Eucalyptus citriodora Myrtaceae Eucalyptus
Lemon scented gum Turare Bronchitis
21. Entada Africana Leguminosae:M African entada Tawasja Root (syphilis)
22. Dichrostachys cinerea Leguminosae:M Double flower Dundu Dieuretic, Measles
23. Ziziphus mucrunata Rhamnaceae Jujube Magaryar kuka Gonococcal Infection
24. Feretia apodanthera Rubiaceae Lallen jiba Syphilis and Gonorhea (root)
25. Saba florida Sapotaceae Ciwo Root (analgesic)
26. Eragorastis ligulata Poaceae Wiry love grass Komayya Love remote
27. Leptadenia hastata Asclepiadaceae Ya diya Condiments
28. Ficus platyphylla Moraceae Flake rubber tree Gamji Stem (convulsion)
29. Detarium microcarpum Leguminosae:M Tallow tree Taura Root (diarrhea)
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
LIST OF PLANTS ALONG JIMETA BYE-PASS - JAMBUTU- BOGGARE ROAD (YOLA NORTH L.G.A)
S/N BOTANICAL NAME FAMILY COMMON
NAME HAUSA NAME NOTE ETHNO-BOTANY
1. Ficus polita Moraceae Shiny leaved
fig Durumi Shade
2. Mangifera indica Anacardiaceae Mango Magoro Fuel wood, shade
3. Polyalthia longifolia Annonaceae Masquerade Machikule Wind breaker
4. Tamarindus indica Leguminosae: C Tamarind Tsamiya Source of vitamin c
5. Urelytrum gigenteum Poaceae Giant
urelytrum Jema Preservation of water
6. Acacia senegalensis Leguminosae:M Fodder tree Kumba shaho Medicinal
7. Cissus quadrangularis Vitaceae 4angled steam Daddori
8. Boscia senegalensis Capparidaceae Anza Root (sexual impotence)
9. Moringa oleifera Moringaceae Horse raddish Zogale Hypertension
10. Phoenix dactylifera Palmae Phoenix Dabino Mat making
11. Newbouldia laevis Bignoniaceae Tree of life Aduruku Breast cancer (Lvs.)
12. Achyranthes aspera Amaranthaceae Prickly chaff
flower
Kaimin
kadangare Aid walking in children
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
LIST OF PLANTS ALONG MILDO - KAMBURO - MADAGALI ROAD (MADAGALI L.G.A)
S/N BOTANICAL NAME FAMILY COMMON NAME HAUSA NAME ETHNO-BOTANY
1. Parkinsonia aculeata Leguminosae:C Jerusalem thorn Aljannatu Seeds (tuberculosis)
2. Acacia nilotica Leguminosae:M Fodder tree Gawo Tannin
3. Hypaene thebiaca Palmae Dum palm Goriba Dizziness (fruit)
4. Mangifera indica Anacardiaceae Mango Mangoro Stem (piles)
5. Balanites aegyptiaca Balanitaceae Desert date Aduwa Piles
6. Sclerocarya birrea Anacardiaceae Plum Danya Bark (anti venom)
7. Ipomoea fistulosa Convolvulaceae Carnea weed - Keep off snakes
8. Combretum racemosum Combretaceae Red flowered combretum Bauli Apiculture
9. Adansonia digitata Bombacaceae Baobab Kuka Lvs (Asthma)
10. Azadirachta indica Meliaceae Neem Darbejiya Insecticide
11. Ficus ingens Moraceae Fig tree Kawuri Piles
12. Jatropha curcas Euphorbiaceae Purgin nut Bini da zugu Insecticide (seeds)
13. Tamarindus indica Leguminosae:C Tamarind Tsamiya Laxative
14. Ficus platyphylla Moraceae Fig tree Gamji Piles
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
15. Vitex doniana Ebenaceae Balack plum Dinya Diarrhoea
16. Acacia polyacantha Leguminosae:M Thorny fodder Dakwara Root( Snake bite)
17. Sclerocarya birrea Anacardiaceae plum Danya Astringent
18. Commiphora kerstingii Burseraceae African myrrh Arrow poison
19. Eucalyptus citriodora Myrtaceae Lemon scented gum Turare Bronchodilator
20. Parkia biglobosa Leguminosae: M Locust bean Dorawa Stem (piles)
21. Annogeissus leiocarpus Combretaceae African birch Marke Cough
22. Lannea acida Anacardiaceae Plum Faru Fruit (Scurvy)
23. Butyrospermum
paradoxum Sapotaceae Shear butter Kadanya Bush lamp oil
24. Ricinus communis Euphorbiaceae Castor oil Zurman Oil
25. Sterculia setigera Sterculiaceae Karaya gum Kukuki Bark (vomiting)
26. Terminalia macroptera Combretaceae Canni Baushe Lvs (Gastritis)
27. Newbouldia laevis Bignoniaceae Fertility tree Aduruku
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
LIST OF PLANTS ALONG SHUWA - PALLAM ROAD (MADAGALI L.G.A)
S/N BOTANICAL NAME FAMILY COMMON NAME HAUSA NAME ETHNO-BOTANY
1. Ficus polita Moraceae Shiny leaved fig. Durumi Shade
2. Mangifera indica Anacardiaceae Mango Magoro Fuel wood, shade
3. Polyalthia longifolia Annonaceae Masquerade Machikule Wind braker
4. Tamarindus indica Leguminosae: C Tamarind Tsamiya Source of vitamin C
5. Urelytrum giganteum Poaceae Giant urelytrum Jema Preservation of water
6. Acacia senegalensis Leguminosae: M Fodder tree Kumba shaho Sore throat
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
LIST OF PLANTS ALONG KOE TO KOPPA ROAD (MADAGALI L.GA)
S/N BOTANICAL NAME FAMILY COMMON NAME HAUSA NAME ETHNO-BOTANY
1. Cissus quadrangularis Vitaceae 4 angled stem Daddori
2. Boscia senegalensis Capparidaceae Anza Sexual impotence
3. Moringa oleifera Moringaceae Horse raddish Zogale Diabetes
4. Phoenix dactylifera Arecaceae Phoenix Dabino Craft (Lvs)
5. Newbouldia laevis Bignoniaceae Fertility tree Aduruku Lvs (Breast cancer)
6. Achyranthes aspera Amaranthaceae Kaimin kadangare Aid walking
7. Balanites aegyptiaca Balanitaceae Desert date Aduwa Piles (fruit)
8. Ziziphus mucrunata Rhamnaceae Jujube Magaryar kura Bark (Urethritis)
9. Butyrospermum
paradoxum Sapotaceae Shear butter Kadanya Bush Lamp Oil
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
LIST OF PLANTS ALONG KAYA-SABON GARI ROAD (MADAGALI LGA).
S/N BOTANICAL NAME FAMILY COMMON NAME HAUSA NAME ETHNO-BOTANY
1. Vitellaria paradoxum Sapotceae Shear butter Kadanya Oil bush lamp
2. Danielia oliverii Fabaceae:C Balsam tree Maje Tooth ache
3. Piliostigma thonningii Fabaceae:C Camels foot Kalgo Snake bite
4. Parinari macrophylla Chrysoba lanaceae Ginger bread plum Rura Seed (antihelminthic)
5. Citrus sinensis Rutaceae Sweet orange Lemu Cough
6. Elaise geneensis Arecaceae Palm oil Kwakwan manja Root (syphilis)
7. Lannea acida Anacardiaceae Bunch plum Faru Fruit (rickets)
8. Strychnos spinosus Loganiaceae Monkey ball tree Kokiya Panacea
9. Pterocarpus
erinacceaus Fabaceae: P Senegal rose wood tree Madobiya (leave Ashes) mental illness
10. Musa sapientum Musaceae Banana Ayaba Fever
11. Ficus thonningii Fabaceae: C Camels foot Kalgo Snake bite
12. Annogeisus leiocarpus Combretaceae African birch Marke Cough
13. Anacardium occidentale Anacardiaceae Cashew Yazawa Fungicides
14. Calotropis procera Ascleipiadaceae Sodom apple tamfafiya Lvs (piles)
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
LIST OF PLANTS NJOBOLI - RUGANGE ROAD (YOLA SOUTH L.G.A.)
S/N BOTANICAL NAME FAMILY COMMON NAME HAUSA NAME ETHNO-BOTANY
1. Cordia Africana Boraginaceae Sebesten plum Alilliba Lvs (leprosy)
2. Leptadenia hastata Ascleipiadaceae Crown sthrub Yadiya
3. Acacia albida Leguminosae:M Apple ring Gawo Root (pneumonia)
4. Euphorbia deightonii Cactaceae Cactus Kerana Fencing
5. Ficus sycomorus Moraceae Fig tree Baure Bark (purgative)
6. Ficus platyphylla Moraceae Fig tree Gamji
7. Prosopis Africana Leguminosae:M Iron wood Kirya Root (Lvs. Fatique)
8. Ficus ingens Moraceae Fig tree Kawuri Root (Neurlgia)
9. Spondias cytherea Anacardiaceae Plum Maleruwa Resinos gum
10. Pandiaka heudollottii Amaranthaceae Sessile weed Witch craft
11. Agave sisalana Agavaceae Sisal hemp Zabuwa Blood tonic
12. Cassia sinqueana Leguminosae:C Yellow flowered senna Runhu Leaves (post-natal care)
13. Indigofera arrecta Leguminosae:P Indigo weed Baba Dye source
14. Mimosa pigra Leguminosae:M Sensitive plant Gumbi Root ashes (T.B)
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
15. Coldenia procumbens Boraginaceae
16. Cardiospermum
halicavum Sapindaceae Frogs bladder Hantar kwado
17. Ficus iteophylla Moraceae
18. Sclerocarya birrea Anacardiaceae Nunu danya Bark (Anti venom)
19. Piliostigma thonningii Leguminosae:C Camel’s foot Kalgo Snake bite
20. Carrisa edulis Apocynaceae Natal plum Cizaki
21. Mangifera indica Anacardiaceae Mango Mangoro (Stem) Piles
22. Psidium guaja Myrtaceae Guava Gwaiba Lvs (Anti diarrhoea)
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
LIST OF PLANTS ALONG LABONDO TO BORRONG ROAD (GEREI LGA)
S/N BOTANICAL NAME FAMILY COMMON
NAME HAUSA NAME NOTE ETHNO-BOTANY
1. Adasonia digitata Bambacaceae Baobab Kuka Asthma
2. Hypheaene thebiaca Palmae Dum palm Goriba Fruit (dizziness)
3. Spondias mombin Anacardiaceae Hog Plum Tsadar masar Bark (Emetic)
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
LIST OF PLANTS IN MICHIKA L.G.A
BAZZA TO KALIKASA
S/N BOTANICAL NAME FAMILY COMMON NAME HAUSA NAME ETHNO-BOTANY
1. Khaya senegalensis Meliaceae Mahogany Madaci Stem (Nausea)
2. Azadirachta indica Meliaceae Neem Darbejiya Lvs (Insecticide)
3. Ficus thonningii Moraceae Fig tree Chediya Root (Tetanus)
4. Ziziphus abbysinica Rhamnaceae Jujuba catch thorn Magaryar kura Root (Analgesic)
5. Acacia polyacantha Leguminosae: M Fodder tree Kumbar shaho Gastro Intestinal Disorder
6. Euphorbia camerunica Cactaceae Cactus Tunya Latex (Purgative)
7. Jatropha carcass Euphorbiaceae Purgin nut Bini da zugu Ringworm
8. Balanites aegyptiaca Baianitaceae Desert date Aduwa Desert date
9. Tamanndus indica Leguminosae: C Tamarind Tsamiya Laxative
10. Acacia nilotica Leguminosae: M Black tamarind Bagaruwa Tannin
11. Ipomoea fistulosa Convolvulaceae Carnea weed - Send away snakes off
12. Euphorbia deightonii Euphorbiaceae Cactus Tunya Latex (High blood pressure)
13. Parinari cutatellifolia Chrysobacanaceae Bread plum Rura Root (Rhinitis)
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
LIST OF PLANTS IN BUPPA VILLAGE
S/N BOTANICAL NAME FAMILY COMMON NAME HAUSA NAME ETHNO-BOTANY
1. Acacia senegalensis Leguminosae: M Gum Arabic Kumba shaho Sore throat (Bark)
2. Borrassus aethiopum Palmae Fan palm Giginya Root (Sore throat)
3. Mangifera indica Anacardiaceae Mango Mangwaro Piles
4. Manihot utilissima Euphoribiaceae Cassava Rogo Hernia (Lvs)
5. Ficus ingens Moraceae Fig Kawuri Piles
6. Borassus aethiopum Palmae Fan palm Giginya Root (Sore throat)
7. Parkia biglobosa Leguminosae: M Locust bean Dorawa Root (Pneumonia)
8. Ipomoea fistilosa Convolvulaceae Carnea’s weed - Send away snakes off
9. Calotropis procera Ascleipiadaceae Sodom apple Tumfafiya Root (Purgative)
10. Hollarhena floribunda Apocynaceae False rubber tree Bakin mayu Root (Gonorrhoea)
11. Isoberlinia doka Leguminosae: C Doka Doka Economic Wood
12. Acacia siebenana Leguminosae: M White thorn Farar kaya Root (Anaemia)
13. Cassia singueana Leguminosae: C Yellow senna Runhu Post natal care
14. Adansonia digitata Bombacaceae Baobab Kuka Lvs (Asthma)
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
LIST OF PLANTS ALONG KARAZZAH TO ZAH ROAD
S/N BOTANICAL NAME FAMILY COMMON NAME HAUSA NAME ETHNO-BOTANY
1. Combretum racemosum Comretaceae red flowered combretum Baushe -
2. Euphorbia camerunica Cactaceae Cactus Tunya Latex (Purgative)
3. Opuntia-ficus-carica Cactaceae Cactus Tunya
4. Euphoribia deightonii Euphoribiaceae Cactus Tunya Latex (High blood pressure)
5. Burkea Africana Fabaceae: C Makarho Back (Gonorrhoea)
6. Antidesma venosum Euphorbiaceae Bark cloth Stem (Itching)
7. Cassia sieberiana Fabaceae: C Drumstick Marga Root (expel tapeworm)
8. Afzelia Africana Fabaceae: C African oak Kawo Antidote to poison
9. Uvaria chamae Annonaceae Finger root Lukuki Rheumatic colds (root)
10. Erythrophleum
suaveolens Fabaceae: C Odeal tree Sanberu Cardiotonic
11. Bombax costatum Bombacaceae Red silk cotton Gurjiya Bark (ease childbirth)
12. Fagara xanthozyloides Rutaceae Candle stick Fasakwari Root (sickle cell)
13. Baphia nitida Fabaceae: P Cam wood Majigi Anti-Microbial
14. Tamarindus indica Fabaceae: C Tamarind Tsamiya Laxative
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
15. Punica granatum Punicaceae Pomegranate Ruman Fruit (scurvy)
16. Psidium guajava Myrtaceae Guava Gwaiba Anti diarhoea (Lvs)
17. Ceiba pentandra Bombacaceae Silk cotton Rimi Soft wood
18. Stereospermum
kunthianum Bignoniaceae Kunths stercos Jiri Root (Dieuretic)
19. Rouvolfia caffra Apocynaceae Swizzle stick Wada
20. Adamsonia digitata Bombacaceae Baobab Kuka Lvs (Asthma)
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
LIST OF PLANT IN NUMAN L.G.A.
LIST OF PLANTS ALONG KPASHAM-YANGA ROAD
S/N BOTANICAL NAME FAMILY COMMON NAME HAUSA NAME ETHNO-BOTANY
1. Parkinsonia aculeate Leguminosae:M Jerusalem thorn Aljanatu Lvs (Dieuretic)
2. Ziziphus mucrunata Rhamnaceae Jujube Magaryar kura Root (gonococcal Infection)
3. Azadirachta indica Meliaceae Neem tree Dogon yaro Lvs (Insecticide)
4. Carica papaya Caricaceae Paw paw Gwanda Yellow fever (Lvs)
5. Blighia sapida Sapindaceae Akee Gwanja kusa Bark (stimulant)
6. Entada africana Fabaceae: M Tawatsa Bark (ricket) antiseptic
7. Khaya senegalensis Meliaceae Mahogany Madaci Stem (Nausea)
8. Prosopis africana Fabaceae: M Axle wood Kirya
9. Detarium microcarpum Fabaceae: C Taura
10. Detarium Senegalese Fabaceae: M Tallow tree Taura Bark (Pneumonia)
11. Afromosia laxiflora Fabaceae: C Satin Wood Makarho (Bites, Dog, Snake)
12. Gmelina arborea Verbenaceae Gmelina Dinyar bature Insecticide (seeds)
13. Terminalia
avecenneides Combretaceae Baushe Root (Leprosy)
14. Combretum sericeum combretaceae African group Taro
15. Gliricidia sepium Fabaceae:P Chocholate tree Lus (RAT Poison)
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
S/N BOTANICAL NAME FAMILY COMMON NAME HAUSA NAME ETHNO-BOTANY
16. Annona senegalensis Annonaceae Custard apple Gwandar daji Fruit (expel Worms)
17. Terminalia mollis Combretaceae Baushe Anti Microbal
18. Vitex doniana Verbenaceae Black plum Dinya Fruit (Anti Diarrhoea)
19. Bauhinia rufescens Fabaceae: C Camel’s foot Jirga Bark (Hepatitis)
20. Tamarindus indica Leguminosae: C Tamarind Tsamiya Laxative
21. Hyphaene thebiaca Palmae Dum palm Goriba Craft, Mat
22. Annogeissus leiocarpus Combretacea African birch Marke Stem (Cough)
23. Guiera senegalensis Combretacea Senegals guiera Sabara Anti Diarrhoea
24. Borassus aethiopum Palmae Fan palm Giginya Lvs. (Mat)
25. Combretum molle Combretacea Combretum Gogen damo Root (Convulsion)
26. Daniellia oliverii Leguminosae: C Balsam tree Kadaura Tooth Ache
27. Khaya senegalensis Meliaceae Mahogany Madaci Stem (Stomach Ache)
28. Acacia polyacantha Leguminosae: M Flat Thorn Acacia Kumbar Shaho Root (Snake Bite)
29. Terminalia
avviecennoide Combretaceae Terminacia Baushe Root (Leprosy)
30. Wissadula amplisima Malvaceae Wissa leave
31. Dichrostachys cinerea Leguminosae:M Marabou Thorn Dundu Root (Anti Venom)
32. Waltheria indica Sterculiaceae Indian waltheria Hankufa Tyroxine Suppressor
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
S/N BOTANICAL NAME FAMILY COMMON NAME HAUSA NAME ETHNO-BOTANY
33. Ipomoea fistulusa Convolvulaceae Carnea’s weed - Keep snake off
34. Lannea acida Anacardiaceae Lannea plum Faru
35. Adamsonia digitata Bombacaceae Baobab Kuka Lvs (Asthma)
36. Phoenix dactylifera Palmae Date palm Dabino Lvs (Mat)
37. Musa sapientum Musaceae Banana Ayaba Yellow Fever
38. Eucalyptus citriodora Myrtaceae Eucalyptus Turare Bronchitis
39. Entada Africana Leguminosae:M African entada Tawatsa Root (Rickets)
40. Dichrostachys cinerea Leguminosae:M Marabou Thorn Dundu Root (Anti Venom)
41. Ziziphus mucrunata Rhamnaceae Jujuba Magaryar kura Root (Dieuretic)
42. Feretia apodanthera Rubiaceae Lallen jiba Root (Syphilis &
Gonorrhoea)
43. Saba florida Sapotaceae Ciwo Root (Jaundice)
44. Eragorastis ligulata Poaceae Wiry love grass Komayya Love remote
45. Leptadenia hastata Asclepiadaceae Ya diya Lvs. (Vermifuge)
46. Ficus platyphylla Moraceae Broad leaved fig Gamji Root (Female Sterility)
47. Detarium microcarpum Leguminosae:C Tallow tree Taura Bark (Pneumonia)
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
LIST OF PLANT IN LAMURDE L.G.A.
LIST OF PLANTS ALONG BILLE TO MAYO-BELWA ROAD
S/N BOTANICAL NAME FAMILY COMMON NAME HAUSA NAME ETHNO-BOTANY
1. Wissadula amplisima Malvaceae Wissa leave
2. Dichrostachys cinerea Leguminosae:M Double flower Dundu Root (Anti Venom)
3. Waltheria indica Sterculiaceae Indian waltheria Hankufa Tyroxine Suppressor
4. Lannea acida Anacardiaceae Lannea plum Faru Root (Veneral Disease
5. Adamsonia digitata Bombacaceae Baobab Kuka Lvs. (Asthma)
6. Phoenix dactylifera Palmae Date Palm Dabino Lvs (Mat)
7. Musa sapientum Musaceae Banana Ayaba Yellow fever
8. Eucalyptus citriodora Myrtaceae Eucalyptus Turare Bronchitis
9. Entada Africana Leguminosae: M African entada Tawatsa Root (Rickets)
10. Dichrostachys cinerea Leguminosae: M Double flower Dundu Root (Anti Venom)
11. Ziziphus mucrunata Rhamnaceae Jujube Magaryar kura Root (Dieuretic)
12. Feretia apodanthera Rubiaceae - Lallen jiba Root (Syphilis & Gonorrhoea
13. Mitragyna Innermis Rubiaceae False Abura Giyayya Wick-low
14. Ficus thonningii Moraceae Fig tree Chediya Root (Jaundice)
15. Azadirachta indica Meliaceae Neem Darbejiya Lvs. (Insecticide)
16. Khaya senegalensis Meliaceae Mahogany Madaci Stem (Stomach Ache)
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
S/N BOTANICAL NAME FAMILY COMMON NAME HAUSA NAME ETHNO-BOTANY
17. Ziziphus abbysinica Rhamnaceae Jujuba Magaryar kura Root (Dieuretic)
18. Jatropha curcas Euphorbiaceae Purging nut Bini da zugu Seeds Birth Control
19. Euphorbia camerunica Cactaceae Cactus Tunya
20. Acacia polyacantha Leguminosae: M Fodder tree Kumbar shaho Root (Snake Bite)
21. Ipomoea fistulosa Convolvulaceae Carnea weed - Send Away Snake off
22. Tamanndus indica Leguminosae: C Tamarind Tsamiya Fruit (Laxative)
23. Acacia nilotica Leguminosae: M Black tamarind Bagaruwa
24. Balanites aegyptiaca Bacanitaceae Desert date Aduwa Piles
25. Acacia Senegalensis Leguminosae: M Senegals acacia Kumba shaho Root (Snake Bite)
26. Manihot utilissima Euphoribiaceae Cassava Rogo Lvs. (Hernea)
27. Mangifera indica Anacardiaceae Mango Mangwaro Piles
28. Borrassus aethiopum Palmae Fan palm Giginya Skin Disease
29. Ficus ingens Moraceae Fig Kawuri Bark (Tonic)
30. Parkia biglobosa Leguminosae: M Locust bean Dorawa Bark (Piles)
31. Borassus aethiopum Palmae Fan palm Giginya Lvs. (Craft)
32. Calotropis procera Ascleipiadaceae Sodom apple Tumfafiya Lvs. (Heammorhoides)
33. Acacia siebenana Leguminosae: M Fodder Farar kaya Bark (Vermifuge)
34. Isoberlinia doka Leguminosae: C Doka Doka Economic Wood
35. Hollarhena floribunda Apocynaceae Bunch of flower Bakin mayu Root (High Blood Pressure)
36. Cassia singueana Leguminosae: C Yellow senna Runhu Post natal Care
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
LIST OF PLANTS IN NEW DEMSA - PUDDE (DEMSA L.G.A)
S/N BOTANICAL NAME FAMILY COMMON NAME HAUSA NAME ETHNO-BOTANY
1. Acacia Senegal Leguminosae: M Senegals acacia Kumba shaho Root (Snake Bite)
2. Manihot utilissima Euphorbiaceae Cassava Rogo Lvs. (Hernia)
3. Mangifera indica Anacardiaceae Mango Mangwaro Stem (Piles)
4. Borrassus aethiopum Palmae Fan palm Giginya Lvs. (Mat)
5. Parkia biglobosa Leguminosae: M Locust bean Dorawa Lvs. (Hemorrhages)
6. Borassus aethiopum Palmae Fan palm Giginya Lvs. (Mat)
7. Ficus ingens Moraceae Fig Kawuri Bark (Tonic)
8. Hollarhena floribunda Apocynaceae False Rubber Bakin mayu Root (High Blood Pressure)
9. Calotropis procera Ascleipiadaceae Sodom apple Tumfafiya Lvs (Piles)
10. Ipomoea fistulosa Convolvulaceae Carnea’s weed - Send Away Snakes off
11. Isoberlinia doka Leguminosae: C Doka Doka Economic Wood
12. Adansonia digitata Bombacaceae Baobab Kuka Lvs. (Asthma)
13. Cassia singueana Leguminosae: C Yellow senna Runhu Post Natal Care
14. Acacia siebenana Leguminosae: M White Thorn Farar kaya Root (Snake Bite)
15. Ziziphus spina-christi Rhamnaceae Jujuba Magaryar kura Root (Dieuretic)
16. Cadaba farinosa Caparidaceae - Anza Root (food Poisoning)
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
APPENDIX ‘III’
List of Community Members Consulted along the Roads
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
1. KPASHAM - KEBALI - YANGA
9/3/2012
Lady Seraya Linus
Patricia Abraham
Tejia Linus
Ruth Daniel
Paulina Ndiddah
Rahman Ndidda
Wurizammah Ndidda
Zebulom Linus
Felix Jerome
Ndagi Jonathan
Felicia Aassa
Linus Zaro
Danjos
Lackson Istakids
Maigia Istakids
John Wakili
Pius Japhet
Innocent Eremiaya
Samiruna B. Kalu
Lewis J. Kalu
Akanyato Hauka
Humwupwa Haruna
Reuben Jonathan
Umashi Yohanna
James Audu
Dishon Edison
Gamaliel Marcus
Elewese Zakusa
Roger Moses
Maigari Bello
Musa Ibrahim
Pango Shedi
Edison Bakarorra
Abel Janko
Haruna Marcus
Babao Sericus
Marcles Jinde
Ibrahim Buba
Samuel Jokthan
Sanamo Niyanso
Gideon Jerrison
Goje Yang
Emmanuel Nwemi
Mathias Nzegilanwe
Thioshi Aliu
Raji Marcus
Leje Haruna
Shedrach Philip
Davis Marcus
Thombolowa Marcus
Kpeshi Paulvis
Shalom Anthony
Eremedi Nehemiah
Eremia Nehemiah
Mr. Gillah
Chabwanin Boy
Kingsley Rude
2. NewDemsa- Pudde 10/3/2012
Supplementary List to the Gender List
Mall. Buba Isah and his household
comprising of:
Mrs Ladi Buba Isa - wife
Mrs Hassana Buba Isa - wife
Mrs Ladi Buba Isa – wife
Mrs Blessing Amos – Chancellor’s
wife
Adamu Kodomum,
Dwalana Aliu
Somaila Donald
Rabiu Mohammad
Osoun Seaman
Losun Lefiya
Chabwanimim Boy Gillah.
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
Obadiah
John Wakili
Gipson Tawunan
Granso Babaka Maliki
Samaila Donath
3. Njiboli -Rugange 11/3/2012
Henry Samare - Carpenter
Wyeliff Basil - Carpenter
Enoch Zaria - Farmer
Musa Hamman - Civil Servant
Istiphanus Titus
Wakawa Pulsung
4. Labando - Borrong
Mohammed lawal
Suleiman Musa
Ahmadu Ahmadu
Abdulhamid Musa
Dauda Alhamdu
Shaibu Auchan
Goma Dabir
Bulus Dauda
Adamu Amedu
Gregory Eli,
Istifanus Titus,
Abdullahi Wakawa,
Shaibu Anchau,
Garuba Bawa,
Bagobiri Useni,
Freelan Christopher,
Elison Belmon,
Simon Missan
4 Mildo - Madagali 12/3/2012
Ardo - Baba Village Head
Rabe Ahmed Jumba
Hussaini Usman
Alhaji Abubakar Burda
Kawo Hamman
Aminu Farouk
Shehu Umar Adamu
Ayuba Yusuf
Bello Dalhatu
Buba Bappa
Salihu Abubakar
Saddam A. Buba
Ado A. Bappa
Ibrahim Jallo
Ibrahim A. Baba
Yonana Bunga
Anasi Buba
Yohanna Buba
Malwi Abdu
Danhajja Dalhatu
Hammadu Buba
Bitrus Queiza
Yerima Sidi
Isah A. Baba
Paul Yohanna (Teacher)
Pastor Peter Bakare
Pius Japhet
Simon B. Zagiyo
Esther Joseph
Ezekiel Dickson
Kamburu Madagali
Paul Yohannah
5 Kaya- Sabon Gari
Luka Mbaryam
Wazani D. Burbur
Isyaku Wafudu
Ilya Uluba
Jesibu Jida
Danladi Umar - Mason
Livinus Luka
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
Danjuma Margimari
Ijan Gari Apagu
Zakariya Ijabada
Usman Wazani
Bitrus Wifu
Jida Inginda
Wifu Simda
Sylvester Daniel
Catherine Thomas
Fidelis Manga
Yohana Mathias
Mal. Musa Pallam
Audi Ali
Lawan Bello.
Garba Bawa Bagobiri
6 Shuwa - Pallam
Philip Dugun Pallam – Teacher, video
camera man and Gen set/motorcycle
mechanic
Shagari LawalHealthAttendant
Solomon Isah C/Servant
Ishaya Apaju Farmer
Emmanuel Koji Applicant - Cert
in Public Admin
Anthony Ularamu applicant -SSCE
Simon Bzagiyu
Mrs. Anna Mallam
Ijumptil Luke
Esther Joseph.
Jaro Linus
Latia Danjos
John Wakili
7 Main Road - Koe - Koppa
Michael Tizhe
Marcus Cyprian - Business man
Joel Zra
Marcus Zra
Bitrus Emmanuel - Mason
Usman Baba
Abel Tizhe
Lazarus Sini - Carpenter
Andrew Boye - Blacksmith
Umaru Musa
Emmanuel Moses
Kojigili Zra
Tari Kwada
Cyprian D. Zirha - Teacher
Augustine Tailor - Butcher
Ibrahim Tar
Mrs. Martina Stephen
Mrs. Martina Steven (Nurse)
8 Bazza - Zah
Thomas Z Bashari
Daniel Tizhe
Philemon Mathias
Daniel V. Koji
Ironias Sebastine
Eugene Mathias
Thomas Tizhe
Lihama Linus
Anthony Yegwa
Noel Peter
Peter Tighu
Jacob Augustine
Wilfred Julius
Dahiru Ibrahim
Isiah Tizhe
Dauda Tumba
Bulama Lawrence Tumba - Village
Head
Solomon N Audu
Julius Tumba
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
Marcus Paul
Babangida John
Iko Yonana
Isa Tumba Karasude
Adqmu Garba
Danaladi jida
Ibrahim Zira
Yakubu Neyi
Tije Zira
danGaruba Goje
Yakubu Zira
Roseline Sunday
Juami Jospeh
Ishaya Sani
Tumba Bazza
Mbrisa Bitrus
Martin smion
Mal. Waga
Isaiah Semi
Isah Hubaiji
Dauda Wagalda
Tauba Tanza
9 Gyawana-Lamurde
Dommic Stephen
Samson Cleophas
Justin Manador
Mrs. Ladi Hadry
Cornelius Deckland
Granson Bakare
Victor Japhet
Jackson Matthew
Ambrose We
Kingsley Steven
11 Jambutu - Boggare
Maina Abdu
Sileiman Nasiru
Nama Maina
Umaru Gasawu
Gadawayo Huleri
Bashriu Ma
Alh. Suleiman Usman
Ruth Matthew
Mal. Mohd. Chibada
Hamza Adamu
12 Kwana waya-Namtari
Mrs Martina Jemmy
Suleiman Usman
Emma Aliyu
Isah Umar
Maina Abdu
Mohammed Kamilu
13 Bille-Mayo Belwa
Gibson Tawunan
Ibrahim Tari
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
APPENDIX ‘IV’
List of Women Groups Consulted in the Communities
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
1. Kpasham - Kebali.
Lady Saraya Linus
Patricia Abraham
Tejiya Linus
Ruth Daniel
Pauline Aassa
2. Kabeli-Lawe
Janet Paul
Hamediya Yusufu
Mary Jonathan
Christiana Gayus
Rhoda Aba
Rosetina Anthony
Laraba Anthony
Yosi Peter
Naomi Haneil
3. Lawe-yanga
Catherine Kemuel
Mary Gamaliel
Mighty Gilbert
Ladi Ericson
Ramatu Macless
Paulina Rueben
Pwalyenti Haruna
Agoso Tufe
Nelis Sidney
Tina Pwali
Helmina Bildad
Pwakulti Sidney
Doris Ericson
Pawanadi Jerison
Limna Alexander
Sabteka Timothy
Glary Jacob
Damaris Davison
Mercy Yohannah
Doris Clement
Wenti Dogara
Clara Gidieon
Rejoice P. Ericson
Forget Obadiah
Marbel Linton
Ley Azie
Faith Reuben
4. Dabah (Mayobelwa)
Esther Kilyobas
Cilyatu Wilson
Keturah Elam
Victoria Wilson
Cecilia Kalyabas
Rifikatu Alkali
5. Dubange Fade
Zirige
Hon. Agnes Daniel
Jeal Kefas
Wunba
Rejoice Ezra
Ladi Buba Isa
Hassana Isa
Ladi Isa
Blessing Amos
6. Nyibango
Hafsat Usman
Salamatu Kawo
Laraba Garga
Fadimatui Usman
Amina Adadu
Kuvum Yiguda
Ruth John
Esther Dalhatu
7. Bitiku
Aishatu Bulus
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
Cecilia Ijigil
Maru Dali
Juliana Musa
Rebecca Bullus
Naomi Gambo
Mangayo Mallam
Dressa Dali
Vitoria wazani
Ijafida Bulus
8. Pallam
Juliana Anthony
Esther Isa
Deborah Warda
Lucy Anthony
Laraba Sini
Jummai Sani
Stella Sunday
Musa Vandu
Rejoice Kwalha Anthony
9. Wruganyandi
Martina Stephen
Christiana Peter
Mary Joseph
Rose Steven
Rose Colomber
Lucy Christopher
Augustina Stephen
Maria Siprel
Susana Markus
Rebecca Andrew
Lucy Stephen
Lydia Peter
Paulina Augustine
Joesephen Aden
Elina Terry
10. Whobazhi
Umurat Umaru
Esther Geofery
Monica Mathias
Eunice Mathias
Saraya Daniel
Maimuna Sambo
Maria Clement
Esther Oliver
Mary Sylvester
11. Mampe
Hajiya Salome
Naomi Enoch
Ruth Peter
Monica Andarawus
Esther Bitrus
Cecilia Amos
Martha Markus
Hauwa Sunday
Saratu Sunday
12. Karausude (Zar)
Saratu Inuwa
Saratu Isa
Jummai Zira
Ladi Idi
Saratu James
Hannatu Inuwa
Naomi Ezra
Ladi John
Rebecca Bitrus
Saraya Danfulani
Hauwa Peter
Hauwa Ayuba
Saraya Inwa
Hajaratu Musa
Rebecca Amos
Lydia Joseph
Phoebe Zira
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
APPENDIX ‘V’
Munites of Meetings for the Discussion of Arap in Project Area
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
a) COMMUNITY MEETING HELD WITH PEOPLE OF DUBWANGUN ON 2ND
APRIL 2012
Agenda
1. Opening Prayer
2. Introduction
3. Chairman’s Opening Remarks
4. General Discussions
5. Any Other Business
The meeting started at about 10.30am with an opening prayer by Mr. Elisha Abba
Introduction
Professor Charles Okuofu an environmental Engineer from Yaroson Partnership Limited
the Chairman of the meeting introduced himself. All other members present at the
meeting introduced themselves.
The chairman started his opening speech by introducing RAMP II project of Adamawa
State Government through World Bank assisstant. The chairman stressed the following
points:
- The road to be constructed will be laterite with good ring pipe and box - culverts as,
well as bridges as the case may require
- That the aim of the meeting is to have an open discussion and interaction with
members of the community to establish the ownership of houses, farmlands as well
as economic trees to be affected by the road alignment; and also to hear the owners’
views.
The chairman further stated that the road would belong to them (community) and not the
government. The road will be delivered to the community by government for the
community to maintain.
General Discussion/Any Other Business
Responses from the community members:
- Michael Trune: “I am happy when I receive strangers like these” He cited the
example of the ADSUBEB project executed by Adamawa state government in their
community saying in the course of the project. He therefore called on his people
(villagers) to come together and support whatever the government is bringing to
them. The chairman made it known very clearly that it is not the intention to render
anybody homeless or even to relocate people unnecessarily. However, should there
be need to acquire anybody’s land, adequate compensation would be made.
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
- Samuel Shaba: Asked about the chainage markings on the wall of his house.
Response: Those markings on the houses and trees are to guide the surveyors and
contractors.
- Agnes Daniel: Asked about the compensation as to whether it is after or before the
construction, but it was made clear to her that a comprehensive compensation will be
made before construction if the need arises.
- Barnabas: Made it known to the consultant that there is an existing water pipe (3 -
4m deep) along the alignment from Chainage 2 + 000 to 2 +725 which the consultant
noted.
- Sylvanus Raun: Advised the youth to co-operate with the contractors during the
construction period so that all would benefit from the project.
The chairman requested Mr. Jimmy Joel (Brother to the PAP), to comment. He
responded that since the project is for the benefit of the community, he had no objection
particularly as compensation would be paid for whatever is affected.
In his closing remarks, the chairman thanked all the community members that attended
the meeting.
The meeting ended at about 11.45am with a closing prayer by Mrs. Doris Felix.
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
b) COMMUNITY MEETING HELD AT BILE ON 2nd
APRIL 2012
AGENDA
1. Opening prayer
2. Introduction
3. Chairman’s opening remarks
4. General discussions
5. Any Other Business
Before the meeting with the community, consultants held discussions with the village
Head of Bille: Chief Pius (Maigari Bille), at his residence. The Chief was told about the
need to change the road alignment and he was shown the proposed (new) route. He
confirmed the earlier thinking that the land belongs partly to Government and the
community. No objection was expressed about routing the road through that land except
that if any economic tree is cut, adequate compensation should be paid. Consultants
took the chief through the proposed route for clarity.
The meeting with the community members started about 3.00pm with an opening prayer
by Miss Memhgayans Michael.
The chairman started by telling the community the importance of the road to be
constructed. The road after construction will be handed to the community for proper
maintenance. The road will be lateritic and it is expected that the youth would be
involved in its maintenance. The chairman further stated that, after the road
construction, it is expected to open up the community and the rate of insecurity could be
increased, necessitating a need for a vigilante group. The rate of communicable diseases
could also increase to a higher level, and so the need for awareness creation. He charged
women to come out of their shells as there is no job that is strictly for men but that all
jobs are for both men and women.
The chairman ended by asking the following questions:
1. Do you want the road?
2. Are you ready to maintain the road?
Responses from the Community:
Samuel Elkanah: Asked of compensation of economic trees and farmland.
Response: Compensation would be paid as appropriate
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
Sylveaster Dada: Advised and suggested that during the construction the contractor
should engage local workers from the community.
Justine A. Dadawa: (1) Why should World Bank start their work from Bille to Tunga
and not from Maraba to Bille village?
Response: That was the decision of the State Government. We do not know.
Elkanah Malavi: Doesn’t the community have the right to choose.
Response: This is an issue we cannot comment on.
Haki Kadidi: We prefer the World Bank to handle the road from Mararaba Bille to Bille
town.
Response: It is a bit too late for that. As you can see, work has started on the section
Mararaba - Bille
The meeting ended with closing prayer at about 3.35pm by Ibrahim Dali.
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
c) VISIT TO KODOMUN DEMSA L.G.A ON 3RD
APRIL 2012
At Kodomun, we were directed to meet the village head of Kodomun in the person of
Theophilus H. Manadi. The village head advised that we should meet the paramount
ruler of Demsa first.
The consultants together with village head and his deputy paid a courtesy call on the
paramount ruller of Demsa, at New Demsa.
At the palace of the paramount ruler, the consultants (Yaroson Partnership) explained
the reason for the visitation. The paramount ruler of Demsa HRH ALHAMDU G.
TENEKE (Haman Batta Demsa) welcomed us to the palace and asked the consultants to
go ahead with their mission promising to give necessary support in the course of the
project. He asked the consultants to take account of any economic trees for necessary
compensation. After the courtesy call at Demsa, consultants came back to Kodomun
and drove along the proposed by-pass with the village head and his deputy (Galadima,
Pius Tagbona).
The village head of Kodomun observed that the new route did not affect people’s
farmland and that the land belongs to the community. Only a few economic trees would
need to be compensated. After the tour through the proposed by-pass, we all moved to
the village square and had a meeting with the villagers.
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
MEETING AT KODOMUN VILLAGE ON 3RD
APRIL 2012
AGENDA
1. Opening prayer
2. Introduction
3. Chairman’s opening remarks
4. General discussions/Any Other Business
5. Closing Remarks by the Chairman
The meeting started at about 12.28pm with an opening prayer by Mr. Dominic Zethan.
INTRODUCTION
The chairman and the other consultant introduced themselves and requested the
community members to do the same. The chairman started the meeting by telling the
people the importance of the road project to the community. The government according
to him will hand over the project to the community after execution for proper
maintenance. He stressed that the road is for the community to use throughout the year
without any problem. Farmers and businessmen will move easily and the rate of traffic
flow will increase. Also he said the rate of insecurity could increase. So there may be a
need for a vigilante group to be formed by the youths.
The chairman further created awareness of the possibility of diseases after the road
construction.
GENERAL DISCUSSION/A.O.B
Reactions from the community members:
Johana Lawi: Will the contractor that is going to handle the road project employ local
people?
Response: The contractor will be urged to do that.
Mrs. Ronika Lawi: Which type of road will be constructed for us?
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
Response: The road will be constructed to base course level with good lateritic finish.
Goth Jimoye (Mrs): How are we going to provide the workers of the project with food?
Response: “You are to prepare and sell the food to them”.
The chairman said that the community should interact and co-operate with the contractor
handling the project when the time comes so that all can benefit.
In his closing remarks, the chairman told the community that if they want the road they
should be prepared to own and be ready to maintenance it.
The meeting ended at about 1.10pm with a closing prayer by Mrs. Ronika Lawi.
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
d) MEETING AT THE PALACE OF HRH DR. JORAM J. FWA (OON) MURUM
MBULA) BORRONG WITH THE COUNCIL OF CHIEFS ON 4TH
APRIL 2012
His Royal Highness was away at Yola but had directed that the meeting be held. The
consultants introduced themselves to the council of Chiefs and told them the object of
their visit to Borrong. They went ahead to describe the new road route being proposed
and sought to know from the council, if there is anybody that the new road alignment
would touch or disturb their houses or farmlands.
The chairman told the council that the road to be built is for the community use therefore
after the construction the road will be handed to the community for proper maintenance.
After this interaction with the traditional council of chiefs, we all drove along the
proposed detour. The chiefs affirmed that the new alignment does not affect any
property or farmland and consented to the detour. However, they presented a request
from the paramount ruler to the effect that he (HRH) would prefer the road to terminate
at his palace, along a route commencing at the ECWA church and passing through a
built up area to terminate at the Police Station next to the palace. However, when the
consultants drove along the route, the following observations were made:
- There are some houses whose perimeter block-wall fences would be affected
- There is a stream with a channel width of about 10 - 15m and about 3m depth which
would require at least box culverts, along this route.
- The length of road here is 0.6km
- From the ECWA church to the end of the road (as proposed) is also about 0.6km but
without obstacles.
- There are 6 economic trees that would be affected.
When these facts were presented to the chiefs, they all assured us that there would be
no problem.
After meeting with the chiefs, consultants had a brief meeting with some community
members. The consultants asked the council if there is anybody affected by the
proposed road alignment. Such persons should speak up and be documented. There was
nobody so affected. In response to the chairman’s address, the council representative
welcomed the consultants and stated their readiness to cooperate in the execution of the
project.
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
MEETING WITH THE COMMUNITY MEMBERS
AGENDA
1. Opening prayer
2. Introduction
3. Chairman’s opening remark
4. General Discussion/Any Other Business
The meeting started at about 11.45am with an opening prayer by Jonah John. The
chairman started by introducing himself after which the rest of the community did the
same.
After the introductions, the consultant (Professor Okuofu) who acted as the chairman,
briefed the community members about the road, stressing the need for all (especially the
women), to get involved in the project and participate fully during construction. He
informed them that the road is meant to improve their living conditions and enhance
their farming and businesses. Therefore, there is need for them to assume ownership of
the road. He stressed the need for the community to take over the road maintenance
after it would have been built. The chairman also intimated the community about other
fallouts like possible increases in accidents, crimes and diseases which they would have
to contend with. Therefore, apart from road maintenance, the youth would have to try to
also arrange for adequate complementary security in collaboration with the police.
GENERAL DISCUSSION/A.O.B
Reaction from the Community members:
1. Panason Murna: is it only from Labondo to Borrong that the project would
cover? Response: Yes though there are other roads.
2. Edwin Edward: Will the construction be started this year or next year?
Response: Probably later this year.
3. Kany Teman: How will you take care of the marshy area along the alignment?
Response: There will be culverts
4. Samson Mango: Which contractor will handle the job?
Response: We do not know yet.
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
5. Patrick James: We have materials available for road constructions please,
contractors should patronize us.
Response: We’ll try to remember and inform him.
The closing prayer was said by Sarkin Hausa Alh. Bapatel
At the end of the meeting consultants left for Yola to meet with HRH Dr. Joran J. Fwa
the Murumbula of Borrong as he had requested.
At the meeting, the paramount ruler gave us a slightly different request from what his
chiefs had given earlier. His request specifically is that rather than terminate the road
opposite Late Major Fwa’s residence, it should be extended to the culvert near the
market. He would however also be pleased if the road his chiefs showed us could be
repaired. The consultants noted these and promised to convey the message to the
appropriate quarters.
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
APPENDIX ‘VI’
Cluses to be included in Bidding and Contract Document
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
Environmental Clauses
Waste Disposal
The roads project would necessarily generate different forms of solid wastes which would
require proper handling to avoid environmental degredation on or off site. The following
clauses are proposed.
Clause 1: At all times, the contractor shall maintain all sites in a clean, tidy, condition.
Appropirate and adequate facilities for storing wastes, to avoid wastes be provided.
Clause 2: The safe transportation and disposal of all wastes generated as a result of his
operations and activities shall be the responsibility of the contractor. Such transportation
and disposal shall be done such that no environmental pollution occurs; or any hazard to
man and animals caused. If the contractor involves a third party (sub-contractor) in this,
the contractor shall remain responsible until he demonstrates that the transportation and
disposal of the wastes have not given rise to pollution or created or potentially created
health hazards.
Clause 3: the contractor shall be responsible for providing adequate sanitary facilities for
his workforce and sub-contractors. The contractor shall not allow the discharge of any
untreated sanitary waste to any water source (surface or groundwater).
The contractor shall provide a detailed sanitary proposal to the FPMU/Consultant for
approval, ensuring that the proposed facilities shall not pollute water resources.
Water Resources
There is a likelihood of accidental sipllages occurring due to leakages of fuel, oil or some
other harzadous materials. Specific control measures are necessary to minimize this
possibility of polluting water resources. The following therefore need inclusion.
Clause 4: All reasonable measures shall be taken by the contractor, to prevent spillages
and leakages at all sites likely to cause water pollution. The measures shall include (but
not limited to) the provision of bunds around fuel and oil storage facilities, grease traps in
drainage channels associated with vehicle and plant washing and fuelling areas. The
contractor shall submit to the consultant, prior to locating such facilities, details of his
pollution prevention measures, for approval.
Replanting of Trees
The replacement of trees felled to provide space for the roads is an important mitigation
measure and would be controlled by the following clause.
Clause 5: The contractor shall exercise caution during site clearing, to reduce to a
minimum, the number of trees felled. For every tree felled, 4 new ones of appropriate
species shall be planted by the contractor.
Restoration of Burrow Pits
After extracting road construction materials, it is important to restore burrow pits to
mitigate the associated hazards. Therefore the following clause shall apply.
Yaroson Partnership Ltd.
Rural Access and Mobility Project/Federal Project Management Unit (RAMP-FPMU) Detailed Engineering, Safeguards Studies and Preparation of Bidding Documents for Prioritized Roads in Adamawa State (RAMP II) Enviromental and Social Impact Assessment Report
Clause 6: The contractor shall ensure that any gravel or other burrow pits working areas
etc, are regraded and covered with topsoil or a suitable product to ensure their natural
regeneration, to the satisfaction of the consultant.
Clause 7: Contractor shall arrange to store any top-soil suitable for later use. The topsoil
removal shall be in horizon with each horizon stored separately in piles for later reuse.
Each pile shall be grassed over or covered to the satisfaction of the consultant.
Materials Transport
The transportation of materials (sand stones) to site may not cause problems en-route.
Nonetheless, the following clause is recommended.
Clause 8: The contractor shall make sure that his vehicles do not cause any safety hazard,
noise, dust or nuisance to local inhabitants.
Noise and Air Pollution
Noise and air pollution could be problematic to people living near the roads corridor and
could be controlld thus:
Clause 9: All vehicles and plant operated by the contractor or his sub-contractor shall, at
all times, be maintained in accordance with the original manufacturers’ specifications and
service manuals with particular reference to noise and hydrocarbon particulate emissions.
The consultant shall exercise the right to cause the contractor to replace or rectify, within
days, any vehicle or plant which, in his opinion, is emitting excessive smoke or noise.
Socio-Economic Clauses
Traffic Management, Health and Safety During Constuction
Often, during road projects, temporary diversions are made for which all reinstatement is
required. In such cases, alternative pedestrian routes are required. Also, the road project
would attract the influx of workers who may not reside locally; and could import some
health disorders. Some clauses are recommended to control these situations.
Clause 10: The contractor shall provide, erect and maintain on the site and at such
locations on the approaches, traffic signs and control signals necessary for the direction
and control of traffic. The signs shall be reflectorized or properly illuminated at night as
approved by the consultant. They shall be kept clean and legible at all times. The
contractor shall reposition, remove or cover the signs as required during the different
work stages.
Clause 11: The contractor shall be responsible for taking reasonable precautions to keep
the roads clear of any spillage of materials from his operation, to the satisfaction of the
consultant; and shall clear any spillage without delay.
Clause 12: The contractor shall construct, maintain, remove and re-instate temporary
diversions to the satisfaction of the consultant.
Clause 13: The contractor shall organize periodic health awareness campaigns
(especially HIV/AIDS and Malaria), for the workforce and members of the communities
along the road routes.
Clause 14: The contractor shall spray the road with water during construction to
minimize dust production.