Documents Attached - Environmental Clearance

330
Documents Attached 1. EDS reply 2. Checklist 3. Toposheet 4. EMP 5. Risk Assessment 6. Form-I 7. Annexures 8. Drawings

Transcript of Documents Attached - Environmental Clearance

Documents Attached

1. EDS reply

2. Checklist

3. Toposheet

4. EMP

5. Risk Assessment

6. Form-I

7. Annexures

8. Drawings

Warehouse Project

Plot Nos. B-3 to B-8 and A-4, Focal Point, Ludhiana, Punjab

M/s Nahar Industrial Enterprises Ltd. EDS Reply

Eco Laboratories & Consultants Pvt. Ltd.

(QCI-NABET Approved EIA Consultant)

EDS Reply for Proposal No. SIA/PB/MIS/108792/2019 dated 9/10/2019

S.No. Observations EDS Reply

1. In Form 1 and Drawing 4, the built up area is

62,684.07 sq.m. But in Form 1A the same is

mentioned as 66,284.07 sq.m. Please clarify.

Built-up area for the proposed project is 62,684.07 sq.m. However,

due to typographical error wrong built-up area was inadvertently

mentioned in Form IA. The same has been corrected now.

2. Existing built-up area is not submitted. As such there is no existing building at the site. However, there are

some existing structures of Punjab Concast Steels Ltd. that needs to

be demolished and the same is reflected in contour plan.

3. As per letter dated 15.10.2012 at annexure 1(b), new

lease deed has been made after 30.09.2019, but the

same has not been attached.

As per letter dated 15.10.2012 at Annexure 1(b), reference of letter

dated 30.09.2012 is there in place of letter dated 30.09.2019.

Further, letter dated 30.09.2012 is enclosed as Annexure-14.

4. As per photographs submitted by the project

proponent in Annexure-12, it has been observed that a

significant level of construction is going on.

As mentioned in point no. 2; there are some existing structures of

Punjab Concast Steels Ltd. which needs to be demolished and the

same is reflected in contour plan in an area of 25.57 acres of

project. Copy of contour plan is enclosed as Drawing 9.

5. After pursuing the application submitted by the project

proponent, it is observed that the total land area with

NIEL is 44.10 acres. Out of this, land of 10.04 acres

has been leased to M/s Cotton County Retail Limited

which is already existing project. You are also

constructing a warehouse in a land of 8.49 acres for

M/s Instakart Services Pvt. Ltd. Since, the land is

owned by the same promoter company i.e. M/s NIEL

and the construction activity is going on at the site for

warehousing project by the same project proponent

and the promoter company is also applying for

obtaining Environmental Clearance for the same

Total land area of 44.10 acres is divided into:

a) 10.04 acres has been leased to M/s Cotton County Retail

Limited which is already an existing project for which

Consent to Operate (Air & Water) has been granted by

PPCB. Copy of CTO is already enclosed as Annexure 1(b).

Copy of approved drawing is enclosed as Drawing 11.

b) 8.49 acres of land for which Consent to Establish has

already been obtained from PPCB for garments industry by

NEIL; copy of CTE dated 24.04.2019 is already enclosed as

Annexure 1(d). Later on, same was leased to M/s Instakart

Services Pvt. Ltd. vide dated 23.05.2019; copy of lease deed

is already enclosed as Annexure 1(d). Copy of approved

drawing is enclosed as Drawing 12.

Warehouse Project

Plot Nos. B-3 to B-8 and A-4, Focal Point, Ludhiana, Punjab

M/s Nahar Industrial Enterprises Ltd. EDS Reply

Eco Laboratories & Consultants Pvt. Ltd.

(QCI-NABET Approved EIA Consultant)

component i.e. warehouse project for 25.57 acres only,

separately, not as a consolidated project of land area

of 34.85 acres, it seems to be a violation of

Environmental Clearance project. Whether any

building plan has been got approved for construction

activity which is going on at the site before carrying

out construction activity. Please submit approved

building plan of the area for which construction

activity is going on, which should be approved from

the competent authority before the date of application

of Environmental Clearance for the project of 25.57

acres.

c) Later on, planning was made for 25.57 acres for which application has been submitted for Environmental clearance.

Thus, both (b) & (c) are separate projects and owned by different

developers i.e. M/s Instakart Services Pvt. Ltd. and M/s Nahar

Industrial Enterprises Ltd. Thus, proposed warehouse project in an

area of 25.57 acres of land should not be considered under violation

case. Further, layout has not been approved by competent authority.

S.No. Documents required for obtaining

environmental clearance for commercial

project

Observations EDS Reply

1. EC processing fee (DD No. & date)

For B1 projects :

At the time of TOR 25% and at the time of

EC 75%

For B2 project

At the time of time of EC 100%

Fee is required to be paid @ Rs. 2/ sq.m

of the built up area.

Processing fees for

Environmental Clearance

application @ Rs. 2 / sq.m i.e.

Total built up area x Rs. 2 sq.m =

Rs. 1,24,568.14 i.e. approx. Rs.

1,24,570/- has been submitted

through RTGS vide UTR No.

SBIN41926655995 dated

23.09.2019.

Warehouse Project

Plot Nos. B-3 to B-8 and A-4, Focal Point, Ludhiana, Punjab

M/s Nahar Industrial Enterprises Ltd. EDS Reply

Eco Laboratories & Consultants Pvt. Ltd.

(QCI-NABET Approved EIA Consultant)

2. Whether the project falls in the critical

polluted area notified by MoEF&CC

Not Submitted. The project falls in Ludhiana

which has been notified as

critically polluted by MOEF&CC.

But, the moratorium has been

uplifted vide F.No. J-11013-

5/2010-IA.II(I) dated 15.02.2011.

Copy of office memorandum is

enclosed as Annexure-13(a).

Further as per Office

Memorandum F.No. J-11013-

5/2010-IA.II(I) dated 24.05.2011;

General conditions are not

applicable on Construction

projects. Copy of OM is enclosed

as Annexure 13(b).

3. Various documents to be submitted along

with the EC are listed as under:

1. Is the project involves diversion of

forest land. If yes,

a) Extent of the forest land.

b) Status of the forest clearance.

c) In case, project involves diversion of

forest land then the project proponent will

file an application before the concerned

DFO obtaining forest clearance under

Forest (Conservation) Act, 1980 and

submit acknowledgement

along-with copy of application submitted

Not Submitted. 1. No. There is no diversion of

forest land for the proposed

project. Undertaking regarding

the same is attached along as

Annexure-4.

Warehouse Project

Plot Nos. B-3 to B-8 and A-4, Focal Point, Ludhiana, Punjab

M/s Nahar Industrial Enterprises Ltd. EDS Reply

Eco Laboratories & Consultants Pvt. Ltd.

(QCI-NABET Approved EIA Consultant)

to concerned DFO

2. a) Is the project covered under

PLPA,1900, if No but located near to

PLPA area then the project proponent is

required to submit NOC from the

concerned DFO to the effect that project

area does not fall under the provision of

PLPA Act, 1900.

b) Is the project covered under PLPA,

1900, if yes then Status of the NOC w.r.t

PLPA, 1900.

3. If the project falls within 10 km of eco-

sensitive area. If yes,

a. Name of eco-sensitive area and distance

from the project site.

b. Status of clearance from National Board

for Wild Life (NBWL).

c. The project proponent is required to

submit either documentary proof to the

effect that Wildlife Sanctuary is more than

10 kms from the project site or in case, the

same is within 10 kms radius then, the

project proponent will file an application

before the concerned DFO, Wildlife for

obtaining NBWL permission and submit

acknowledgement along-with copy of

application submitted to concerned DFO

Wildlife for obtaining permission from

2. The project is not covered

under provisions of PLPA

Act, 1900. Undertaking

regarding the same is attached

along as Annexure-4.

3. No wildlife or bird sanctuary

falls within 10 km of project

site, thus, there is no

requirement of NBWL

clearance.

Warehouse Project

Plot Nos. B-3 to B-8 and A-4, Focal Point, Ludhiana, Punjab

M/s Nahar Industrial Enterprises Ltd. EDS Reply

Eco Laboratories & Consultants Pvt. Ltd.

(QCI-NABET Approved EIA Consultant)

NBWL.

4. (a) Undertaking regarding conforming of

site to the siting guidelines framed by

PPCB

Not Submitted As our project falls in the

designated Industrial zone as per

the Master plan of Ludhiana

(Copy of Master Plan showing the

location of project is enclosed as

Drawing-2(b)) therefore, our

project meet the general siting

guidelines framed by PPCB.

5. Construction Phase

i) Max. Water Requirement (KLD),

Source of the Water and treatment facility.

Not Submitted Max. water demand during

construction phase will be 20

KLD which will be provided by

treated water from STP already

installed in Instakart Services Pvt.

Ltd. Wastewater generated will be

treated in septic tank.

6. The project proponent is required to

submit the following information on the

email [email protected]:-

i) Synopsis of the project (Annexure-A)

in pdf file and MS word format

ii) A copy of presentation in PPT format.

Not Submitted

(i) Synopsis of the project in

both formats is being mailed

to the mentioned E-mail ID.

(ii) Copy of presentation will be

submitted separately.

Warehouse Project

Plot Nos. B-3 to B-8 and A-4, Focal Point, Ludhiana, Punjab

M/s Nahar Industrial Enterprises Ltd. EDS Reply

Eco Laboratories & Consultants Pvt. Ltd.

(QCI-NABET Approved EIA Consultant)

EDS Reply for the Proposal No. SIA/PB/MIS/108792/2019 dated 18/09/19

S.No. Documents required for obtaining

environmental clearance for commercial

project

Observations EDS Reply

1. EC processing fee (DD No. & date)

For B1 projects :

At the time of TOR 25% and at the time of

EC 75%

For B2 project

At the time of time of EC 100%

Fee is required to be paid @ Rs. 2/ sq.m

of the built up area.

Processing fees for

Environmental Clearance

application @ Rs. 2 / sq.m i.e.

Total built up area x Rs. 2 sq.m =

Rs. 1,24,568.14 i.e. approx. Rs.

1,24,570/- has been submitted

through RTGS vide UTR No.

SBIN41926655995 dated

23.09.2019.

2. Whether the project falls in the critical

polluted area notified by MoEF&CC

Not Submitted. The project falls in Ludhiana

which has been notified as

critically polluted by MOEF&CC.

But, the moratorium has been

uplifted vide F.No. J-11013-

5/2010-IA.II(I) dated 15.02.2011.

Copy of office memorandum is

enclosed as Annexure-13(a).

Further as per Office

Memorandum F.No. J-11013-

5/2010-IA.II(I) dated 24.05.2011;

General conditions are not

applicable on Construction

projects. Copy of OM is enclosed

Warehouse Project

Plot Nos. B-3 to B-8 and A-4, Focal Point, Ludhiana, Punjab

M/s Nahar Industrial Enterprises Ltd. EDS Reply

Eco Laboratories & Consultants Pvt. Ltd.

(QCI-NABET Approved EIA Consultant)

as Annexure 13(b).

3. Various documents to be submitted along

with the EC are listed as under:

1. Is the project involves diversion of

forest land. If yes,

a) Extent of the forest land.

b) Status of the forest clearance.

c) In case, project involves diversion of

forest land then the project proponent will

file an application before the concerned

DFO obtaining forest clearance under

Forest (Conservation) Act, 1980 and

submit acknowledgement

along-with copy of application submitted

to concerned DFO

2. a) Is the project covered under

PLPA,1900, if No but located near to

PLPA area then the project proponent is

required to submit NOC from the

concerned DFO to the effect that project

area does not fall under the provision of

PLPA Act, 1900.

b) Is the project covered under PLPA,

1900, if yes then Status of the NOC w.r.t

PLPA, 1900.

3. If the project falls within 10 km of eco-

sensitive area. If yes,

a. Name of eco-sensitive area and distance

Not Submitted. 1. No. There is no diversion of

forest land for the proposed

project. Undertaking regarding

the same is attached along as

Annexure-4.

2. The project is not covered

under provisions of PLPA

Act, 1900. Undertaking

regarding the same is attached

along as Annexure-4.

3. No wildlife or bird sanctuary

falls within 10 km of project

site, thus, there is no

Warehouse Project

Plot Nos. B-3 to B-8 and A-4, Focal Point, Ludhiana, Punjab

M/s Nahar Industrial Enterprises Ltd. EDS Reply

Eco Laboratories & Consultants Pvt. Ltd.

(QCI-NABET Approved EIA Consultant)

from the project site.

b. Status of clearance from National Board

for Wild Life (NBWL).

c. The project proponent is required to

submit either documentary proof to the

effect that Wildlife Sanctuary is more than

10 kms from the project site or in case, the

same is within 10 kms radius then, the

project proponent will file an application

before the concerned DFO, Wildlife for

obtaining NBWL permission and submit

acknowledgement along-with copy of

application submitted to concerned DFO

Wildlife for obtaining permission from

NBWL.

requirement of NBWL

clearance.

4. (a) Undertaking regarding conforming of

site to the siting guidelines framed by

PPCB

Not Submitted As our project falls in the

designated Industrial zone as per

the Master plan of Ludhiana

(Copy of Master Plan showing the

location of project is enclosed as

Drawing-2(b)) therefore, our

project meet the general siting

guidelines framed by PPCB.

5. Construction Phase

i) Max. Water Requirement (KLD),

Source of the Water and treatment facility.

Not Submitted Max. water demand during

construction phase will be 20

KLD which will be provided by

treated water from STP already

installed in Instakart Services Pvt.

Warehouse Project

Plot Nos. B-3 to B-8 and A-4, Focal Point, Ludhiana, Punjab

M/s Nahar Industrial Enterprises Ltd. EDS Reply

Eco Laboratories & Consultants Pvt. Ltd.

(QCI-NABET Approved EIA Consultant)

Ltd. Wastewater generated will be

treated in septic tank.

6. The project proponent is required to

submit the following information on the

email [email protected]:-

i) Synopsis of the project (Annexure-A)

in pdf file and MS word format

ii) A copy of presentation in PPT format.

Not Submitted

(i) Synopsis of the project in

both formats is being mailed

to the mentioned E-mail ID.

(ii) Copy of presentation will be

submitted separately.

Warehouse Project

Plot No B-3 to B-8 and A-4, Focal Point, Ludhiana, Punjab

M/s Nahar Industrial Enterprises Ltd. Checklist

Consultant: Eco Laboratories & Consultants Pvt. Ltd. Format No. EL\EIA\F-5.3\9 Date 15.01.2019

QCI-NABET Approved EIA Consultant

AS PER CHECK LIST SEIAA, PUNJAB FOR BUILDING, CONSTRUCTION, TOWNSHIP AND AREA DEVELOPMENT PROJECTS

Sr.

No.

Description Reply

1. Properly filled Form 1 & 1A Form I & IA are enclosed with the application.

2. (a) In case(s) where land has already been

purchased/acquired:

Proof of ownership of land

(b) In case where land is yet to be

purchased/acquired:

Proof of ownership of land (existing owner)

such as copy of latest Jamabandi (not more

than one month old) and credible document

showing status of land acquisition w.r.t.

project site as prescribed in OM dated

07.10.2014 issued by MoEF)

M/s Nahar Industrial Enterprises Ltd. has

been alloted Industrial plots i.e. Plot Nos. B-3

to B-8 and A-4 at Focal Point, Ludhiana,

Punjab measuring 44.10 acres by Greater

Ludhiana Area Development Authority

(GLADA) vide Letter No.

A/Glada/Ludhiana/2015/2056 dated

29.04.2015. Originally ths land was owned

by Punjab Con-cast Steels Limited (PCSL)

which was incorporated on 27th June, 1970.

The name of the company was changed from

Punjab Con-cast Steels Ltd. to Nahar

International Ltd. (NINL) and a Fresh

Certificate of Incorporation consequent on

change of name of Company was issued by

the Registrar of Companies, Punjab , H.P.

and Chandigarh on 6th October, 1994. Later,

Nahar International Ltd. (NINL) was

amalgamated with Nahar Industrial

Enterprises Ltd. (NIEL) vide Order dated

4.3.2005 passed by the Hon’ble Punjab &

Haryana High Court at Chandigarh. Copy of

documents are enclosed as Annexure-1(a).

Copy of MoA comprising of the copy of

court order along with list of directors are

enclosed as Annexure-2(a) & 2(b)

1

Warehouse Project

Plot No B-3 to B-8 and A-4, Focal Point, Ludhiana, Punjab

M/s Nahar Industrial Enterprises Ltd. Checklist

Consultant: Eco Laboratories & Consultants Pvt. Ltd. Format No. EL\EIA\F-5.3\9 Date 15.01.2019

QCI-NABET Approved EIA Consultant

respectively.

3. Copy of Master Plan of the area showing land

use pattern of the proposed site/certificate

from Competent Authority intimating land use

pattern of the project site as per proposals of

Master Plan of the area.

Master plan of Ludhiana showing project

location is enclosed as Drawing 2(b).

4. Layout plan duly approved by the Competent

Authority / Conceptual plan of the project.

Copy of Conceptual layout plan is attached as

Drawing 4.

5. Topographical map of the area showing

Contour Plan. In case of Area Development

Projects, the Contour Plan should reflect the

true existing physical features of the site and

may be prepared by the project proponent

w.r.t. some permanent reference marks.

Contour plan is enclosed as Drawing 9.

6. Status of construction, if any, along with

photographs from all the four sides.

The construction has not yet started. Site

photographs are enclosed as Annexure 12.

7. 500 meter radius map of the area from

periphery of project site clearly indicating the

various industries (specifically red category

industries) and structures lying in the area.

Google Earth Image showing project site &

surroundings within 500 m is enclosed as

Drawing 1.

8. Location plan showing the exact location of

the project site w.r.t. some permanent /

important features of the area and site plan of

the project showing the following:

i) Location of STP

ii) Solid waste storage area

iii) Green belt

iv) Parking space

v) RWH and water recharge pits

vi) Fire fighting equipment layout

vii) First aid room

Services plan showing the location of STP,

location of borewell, Solid Waste segregation

area, First Aid room, RWH pits ( 14 No.), DG

set and Transformers is enclosed as Drawing

5.

Green belt is shown in layout plan enclosed as

Drawing 4.

Also, Fire Fighting plan is enclosed as

Drawing 7.

2

Warehouse Project

Plot No B-3 to B-8 and A-4, Focal Point, Ludhiana, Punjab

M/s Nahar Industrial Enterprises Ltd. Checklist

Consultant: Eco Laboratories & Consultants Pvt. Ltd. Format No. EL\EIA\F-5.3\9 Date 15.01.2019

QCI-NABET Approved EIA Consultant

viii) Location of Tubewells

ix) DG Sets and Transformers

x) Any other utilities

9. Permission of Competent Authority for;

a) Water and Sewerage connection

A letter from concerned Local Body /

Authority giving details about existing status

of sewer connectivity and availability of

water supply in the area and acceptance of

Local Body for taking the quantity of sewage

to be generated by the proposed project and

providing the water supply. Existing position

of public sewer and water supply line duly

marked on the layout map / plan.

b) Collection of Solid waste

Project falls within the MC limits of

Ludhiana, Thus solid waste disposal and

sewerage connections will be provided by

MC, Ludhiana. NOC regarding solid waste

will be obtained from MC Ludhiana.

Water demand will be met through borewell.

CGWA application has been field; Copy is

enclosed as Annexure 10.

10. Water balance chart for summer, rainy and

winter seasons indicating critical requirements

Water Balance Diagrams for different seasons

i.e. Summer, Winter & Monsoon season are

shown in Conceptual Plan as Figure No.

1(a), 1(b) & 1(c) respectively.

11. Availability of adequate land for use of

treated sewage and plantation.

NA

12. Analysis reports of ambient air, ground water

and noise levels from NABL / MoEF

Accredited laboratories as per detail below:

(i) The field data sheets as prescribed by

SEIAA, Punjab which are available on the

official website of SEIAA, Punjab along with

exact location of sampling / monitoring point

marked on the layout map should be filled at

the time of sample collection/monitoring by

the Lab and should be attached with the water,

Lab reports along with Field data sheets are

enclosed as Annexure 7 (b) & Annexure 7

(c) respectively.

Intimation Mail copy depicting the intimation

to PPCB & SEIAA for baseline monitoring is

enclosed as Annexure(a).

3

Warehouse Project

Plot No B-3 to B-8 and A-4, Focal Point, Ludhiana, Punjab

M/s Nahar Industrial Enterprises Ltd. Checklist

Consultant: Eco Laboratories & Consultants Pvt. Ltd. Format No. EL\EIA\F-5.3\9 Date 15.01.2019

QCI-NABET Approved EIA Consultant

air, noise & soil monitoring reports.

(ii) Water, air, noise & soil monitoring reports

more than 6 months old or prior to date of

signing of consent letters/agreement with the

land owner shall not be accepted w.e.f. June,

1st 2015 onwards.

(iii) Atleast one groundwater sample from

the shallow / first aquifer and in case

groundwater is to be abstracted for drinking

purposes then atleast one groundwater sample

from the said aquifer should be monitored and

reports be attached accordingly.

13. Quantification of energy saved and renewable

energy devices used.

Details on Quantification of energy saved are

enclosed as Annexure-9.

Roof Plan showing area reserved for Solar

Panels is enclosed as Drawing 8.

14. Drawing showing plumbing systems for use

of fresh, treated and hot water

Services plan showing dual plumbing systems

for use of fresh, waste water and treated water

line is enclosed as Drawing 5.

15. Construction schedule (PERT/CPM Chart) PERT Chart is enclosed as Annexure 5.

16. Undertaking(s) for;

a) Constitution of Environment Monitoring

Cell.

b) Use of ready mix concrete or use of fly ash

during construction.

c) To provide Fire Fighting System.

d) To provide wind breaking curtains and

water sprinkling system to minimize dust

emissions during construction phase.

e) To provide adequate safety measures for

Affidavit for the same is enclosed as

Annexure 8.

4

Warehouse Project

Plot No B-3 to B-8 and A-4, Focal Point, Ludhiana, Punjab

M/s Nahar Industrial Enterprises Ltd. Checklist

Consultant: Eco Laboratories & Consultants Pvt. Ltd. Format No. EL\EIA\F-5.3\9 Date 15.01.2019

QCI-NABET Approved EIA Consultant

the construction workers during the

construction phase.

17. Environmental Management Plan

indicating the following:

a) All mitigation measures for each item-

wise activity to be undertaken during the

construction, operation and the entire life

cycle to minimize adverse environmental

impacts as a result of the activities of the

project.

b) Compliance of various environmental

regulations.

c) Steps to be taken in case of emergency

such as accidents at the site including fire.

d) For how long period the project proponent

will be responsible for implementation of

EMP and the name of the person(s)

responsible for implementation of EMP.

e) Capital & recurring cost for the EMP per

year and the details of funds for the same.

f) Name of the individual persons /

organization, who will be responsible for

implementation of EMP after the lapse of the

period for which the project proponent is

responsible.

EMP is enclosed along with the application.

The Project proponent will be responsible for

implementation of EMP till the project is

handed over to RWA.

Capital cost of Rs 50 lakhs has been reserved

for EMP during Construction phase of

project. While Rs 3.35 lakhs & Rs 8.6 lakhs

has been reserved as recurring cost per annum

during construction & operation phase

receptively.

Mr. Suman Kumar Thakur of M/s Nahar

Industrial Enterprises Ltd. will be responsible

for implementation Environment

Management Plan

18. Corporate Social Responsibility indicating

various activities to be undertaken,

provisions of funds for the same, the period

for which the same is to be implemented and

Mr. Suman Kumar Thakur of M/s Nahar

Industrial Enterprises Ltd. will be responsible

for implementation of CER (Corporate

Environment Responsibility). The cost of

5

Warehouse Project

Plot No B-3 to B-8 and A-4, Focal Point, Ludhiana, Punjab

M/s Nahar Industrial Enterprises Ltd. Checklist

Consultant: Eco Laboratories & Consultants Pvt. Ltd. Format No. EL\EIA\F-5.3\9 Date 15.01.2019

QCI-NABET Approved EIA Consultant

the person(s) responsible for the

implementation of the same.

proposed expansion is Rs. 73.41 Crores.

Thus, Rs. 73.41 lakhs (@ 1% of expansion

cost) is required for C.E.R activities as per

Office Memorandum vide F. No. 22-65/

2017-IA.III dated 01.05.2018. However, Rs

73.5 lakhs has been proposed to be spent

under CER activities as mentioned in Table 2

of EMP.

19. Traffic Circulation System and connectivity

with a view to ensure adequate parking,

conflict free movements, Energy efficient

Public Transport.

Parking plan showing traffic circulation is

enclosed as Drawing 6.

20. Disaster/Risk Assessment and Management

Plan.

Risk Assessment is enclosed with the

application.

21. Copy of Memorandum of Article &

Association / partnership deed / undertaking

of sole proprietorship / list of Directors and

names of other persons responsible for

managing the day-to-day affairs of the

project.

Copy of MOA & AOA of M/s Nahar

Industrial Enterprises Ltd. along with list of

directors are enclosed as Annexure 2(a) &

Annexure 2(b) respectively.

22. In case of expansion projects, compliance

report of earlier granted environmental

clearance conditions verified by Northern

Regional Office of Ministry of Environment,

Forests & Climate Change, Chandigarh.

This point is not applicable as this is the fresh

application for the Environmental Clearance of

Warehouse project.

23. Copy of presentation to be made before the

SEAC at the time of appraisal in PDF format

having size less than 25 MB.

Agreed

6

Warehouse Project

Plot No B-3 to B-8 and A-4, Focal Point, Ludhiana, Punjab

M/s Nahar Industrial Enterprises Ltd. Checklist

Consultant: Eco Laboratories & Consultants Pvt. Ltd. Format No. EL\EIA\F-5.3\9 Date 15.01.2019

QCI-NABET Approved EIA Consultant

24. Soft copy of all documents in compliance to

Ministry of Environment & Forests, New

Delhi Office Memorandum No. J-11-

013/19/2012-IA-II(I) dated 31st May, 2012

having size less than 25 MB.

Agreed.

25 For expansion projects:

i. All the columns in the application form

may be got filled in three parallel columns

i.e. Existing, Proposed and Total.

ii. In case of increase in no. of story's,

Structural Safety/ Stability Certificate may be

required from the Approved Engineer.

iii. The existing building plan may be got

super imposed with the proposed building

plan and be marked in different colors.

iv. Specify the adequacy of internal water

supply system, sewer line and STP for the

proposed expansion/revision.

This point is not applicable as this is the fresh

application for the Environmental Clearance.

7

76°0'0"E

76°0'0"E

75°55'0"E

75°55'0"E

75°50'0"E

75°50'0"E31

°0'0"

N

31°0

'0"N

30°5

5'0"N

30°5

5'0"N

30°5

0'0"N

30°5

0'0"N

30°4

5'0"N

30°4

5'0"N

Toposheet Map of Warehouse Project Plot No.B-3 to B-8 and A-4, Focal Point, Ludhiana-141010, Punjab

±

Project Site

LEGEND10 Km Buffer From Site

Toposheet No H43K1Toposheet No H43J13 0 1 2 3 40.5

Kilometers

1 cm = 1 km

Northern Railway Main Track

Ludhiana

Sidhwan Branch (Sirhind Canal)

Project Site NH 95

abc
Textbox
8

Warehouse Project Plot Nos. B-3 to B-8 and A-4, Focal Point, Ludhiana, Punjab M/s Nahar Industrial Enterprises Ltd. EMP

Consultant: Eco Laboratories & Consultants Pvt. Ltd. Format No. EL\EIA\F-5.3\9 Date 15.01.2019 QCI-NABET Approved EIA Consultant

ENVIRONMENTAL MANAGEMENT PLAN DURING CONSTRUCTION AND

OPERATION PHASE

Environment Management Plan (EMP) is prepared for the better formulation, proper implementation,

monitoring of mitigation measures adopted to mitigate the possible adverse impacts of a project. EMP

thus ensures that probable environmental impacts are foreseen and taken into consideration before,

during and after the completion of the project. The main objective of the EMP is to identify project

specific activities that are to be considered for investigation of the significant adverse impacts and the

mitigation measures required.

Mitigation Measures for Air Environment during Construction and Operation Phase

The construction shall be completed as per PERT/CPM which is enclosed as Annexure 5.

Tarpaulin sheets will be provided around the area of construction and the building

Construction material of any kind at the site will be fully covered in all respects so that it does

not disperse in the air in any form.

All construction material and debris shall be carried in trucks or other vehicles which are fully

covered and protected to ensure that the construction debris or material does not get dispersed

in the air or atmosphere, in any form whatsoever.

All workers at the construction site and involved in loading, unloading and carriage of

construction material and construction debris shall be provided with masks to prevent

inhalation of dust particles.

Medical help, investigation and treatment will be provided to the workers involved in the

construction of building and carrying construction material and debris relatable to dust

emission.

All excavation work shall be done mechanically in minimum time to reduce dust generation.

There shall be provision of sprinklers so as to suppress the fugitive emission of dust. Also the

nuisance dust generated due to wind at construction site will be taken care of by immediate

removal and recycling of the debris and unutilized construction material and earth.

11

Warehouse Project Plot Nos. B-3 to B-8 and A-4, Focal Point, Ludhiana, Punjab M/s Nahar Industrial Enterprises Ltd. EMP

Consultant: Eco Laboratories & Consultants Pvt. Ltd. Format No. EL\EIA\F-5.3\9 Date 15.01.2019 QCI-NABET Approved EIA Consultant

The vehicles employed will be checked for vehicular emissions and PUC certificates. The

developers shall also impress upon the service agencies to get vehicles regularly checked for

vehicular emission.

The mitigation measures shall include regular maintenance of machinery and provision of

personnel protective equipments to workers where needed.

The steps shall be taken to reduce the impact of noise by plantations from the very beginning.

Construction Activities shall not be carried out at night.

The work shall be undertaken in phases over specific areas so that effective material

management is possible.

The standby generator will be installed with enclosure as per guidelines of Central pollution Control

Board and after taking consent from State Pollution Control Board under Air (Prevention and Control

of Pollution) Act, 1981. The generator installed shall comply with emission limits as given in G.S.R.

520 (E), Environment (Protection) Amendment Rules, 2003 at the manufacturing stage itself. The DG

set shall further be procured from agencies complying the noise emission standards at the

manufacturing stage itself as per G.S.R. 371(E), the Environment (Protection) Second Amendment

Rules, 2002. These Rules say that the maximum permissible sound pressure level for new diesel

generator (DG) set with rated capacity up to 1000 KVA, manufactured on or after the 1st January, 2005

shall be 75 dB(A) at 1 meter from the enclosure surface. The diesel generator set should be provided

with integral acoustic enclosure at the manufacturing stage itself. Installation of a DG set shall be

strictly in compliance with the recommendations of the DG set manufacturer. A proper routine and

preventive maintenance procedure for the DG set should be set and followed in consultation with the

DG set manufacturer which would help prevent noise levels of the DG set from deteriorating with use.

The DG Set area shall also be attenuated using green belt.

Once project is occupied it is also expected to bring vehicular traffic. Due consideration has been

given to traffic management. The layout of the project is so done that traffic congestion is not there.

12

Warehouse Project Plot Nos. B-3 to B-8 and A-4, Focal Point, Ludhiana, Punjab M/s Nahar Industrial Enterprises Ltd. EMP

Consultant: Eco Laboratories & Consultants Pvt. Ltd. Format No. EL\EIA\F-5.3\9 Date 15.01.2019 QCI-NABET Approved EIA Consultant

Mitigation Measures for Water Environment during Construction and Operation Phase

Construction Phase

As mentioned above, the construction related solid waste as malba, loose soil etc. will be

removed immediately, thus, controlling run-off during development/construction phase.

The land clearing activity shall be kept to the absolute minimum by working at the specific

sites one by one where construction is to take place.

Water required during the construction period will be supplied through private water tanker.

There shall be no discharge as such from the water used for construction, as it will be

consumed in the process. There shall thus be no impact on ground or surface water resources.

The flow from the site during monsoons does not directly enter any surface water body.

The surface water environment can be slightly affected if run-off over excavated material or

construction material dumps during monsoons carries the materials along with. The excavation

and other construction debris as construction material shall be kept in identified areas and used

within the project so that it is not carried along with run-off. The site further does not interfere /

obstructs any natural drain.

A toilet facility for workers shall be provided at site and the same shall be connected to Septic

Tank. Workers shall be discouraged from open defecation.

Operation Phase

5.2 KLD of sewage will be generated from the project which will be treated in STP of 10 KLD

capacity based on MBBR Technology (skid mounted). Treated wastewater from STP shall be recycled

for landscaping within the project and flushing. Water balance diagram for different seasons are shown

in the Conceptual Plan.

13

Warehouse Project Plot Nos. B-3 to B-8 and A-4, Focal Point, Ludhiana, Punjab M/s Nahar Industrial Enterprises Ltd. EMP

Consultant: Eco Laboratories & Consultants Pvt. Ltd. Format No. EL\EIA\F-5.3\9 Date 15.01.2019 QCI-NABET Approved EIA Consultant

Mitigation Measures for Land Environment during Construction and Operation Phase

To avoid erosion of the top soil, the development is planned in the shortest possible time and

land-clearing activity shall be kept to the absolute minimum by working at the specific sites

one by one where construction is to take place so as to increase detention and infiltration.

These conditions shall be made a part of contract agreement.

The activities that result in soil being laid bare shall be scheduled in such a way that some type

of vegetative cover appropriate to the site shall be established prior to onset of monsoons.

The requirements of sand and aggregates for the construction work are met from authorized

sources. The fly ash based cement shall be used for the purpose.

For the construction works, the use of wood shall not be allowed (Timber Free Construction)

and all shuttering shall be of mild steel. The use of MDB, Mild Steel, Aluminium, Glass and

Plastic shall be undertaken to the extent possible to reduce the use of wood. The land use as

proposed shall not be altered.

Environment Monitoring Programme

Mr. Suman Kumar Thakur of M/s Nahar Industrial Enterprises Ltd. will be responsible for

implementation Environment Management Plan. Rs. 50 Lakhs has been planned to be reserved for

EMP during construction phase. While, Rs 3.35 lakhs & Rs. 8.6 lakhs has been planned to be reserved

for EMP during recurring cost during construction & operation phase.

The details of the expenditure on environmental measures during construction & Operation Phase are

given in Table 1(a) & 1(b) respectively:

14

Warehouse Project Plot Nos. B-3 to B-8 and A-4, Focal Point, Ludhiana, Punjab M/s Nahar Industrial Enterprises Ltd. EMP

Consultant: Eco Laboratories & Consultants Pvt. Ltd. Format No. EL\EIA\F-5.3\9 Date 15.01.2019 QCI-NABET Approved EIA Consultant

Table 1(a): Expenditure on typical Environmental Measures during Construction Phase

Description Capital

Rs. Lakhs

Recurring

Cost/Annum

Rs. Lakhs

Waste water Management: Dual plumbing

system, Sewage Treatment Plant 20 -

Air & Noise Pollution Management (Acoustics

enclosures for DG set) 2 0.1

Landscaping 5 1.5

Rainwater Recharging 20 0.25

Environmental Monitoring: (Water sprinkling

for dust control, Monitoring of DG set as per

PPCB Guidelines)

1 1

Waste Management: (Collection of Solid Waste

and disposal) 2 0.5

TOTAL Rs. 50 Lakhs Rs. 3.35 Lakhs

Table 1(b): Expenditure on typical Environmental Measures during Operation Phase

Description Recurring Cost/Annum

Rs. Lakhs

Waste water Management:- Dual plumbing system, Sewage

Treatment Plant 2

Air & Noise Pollution Management: (Acoustics enclosures for DG

set) 0.1

Landscaping 1.5

Rainwater Recharging 2

Environmental Monitoring: (Water sprinkling for dust control,

Monitoring of DG set as per PPCB Guidelines) 1

Waste Management (Collection of Solid Waste and disposal) 2

TOTAL Rs. 8.6 Lakhs

15

Warehouse Project Plot Nos. B-3 to B-8 and A-4, Focal Point, Ludhiana, Punjab M/s Nahar Industrial Enterprises Ltd. EMP

Consultant: Eco Laboratories & Consultants Pvt. Ltd. Format No. EL\EIA\F-5.3\9 Date 15.01.2019 QCI-NABET Approved EIA Consultant

CORPORATE ENVIRONMENTAL RESPONSIBILITY

Mr. Suman Kumar Thakur of M/s Nahar Industrial Enterprises Ltd. will be responsible for

implementation of CER (Corporate Environment Responsibility). The estimated cost of the project is

Rs. 73.41 Crores. Thus, Rs. 73.41 lakhs (@ 1% of project cost) is required for C.E.R activities as per

Office Memorandum vide F. No. 22-65/ 2017-IA.III dated 01.05.2018. However, Rs. 73.5 Lakhs has

been proposed under following CER activities as mentioned in Table 2.

Table 2: Activities proposed under CER

S.No. Activities Annual

Expenditure

(in Lakhs)

Timeline Total Expenditure

in 5 Years

(in Lakhs)

1. Health

Health care facilities to Polio

persons through Bharat Vikas

Parishad, Punjab.

2

1 year

2

2. Education

Construction and

maintenance of toilets of

Government Primary

School, Giaspura.

Scholarship to needy

students of Government

High School, Jamalpur,

Ludhiana.

Renovation work in Govt.

Blind School & Govt.

Primary School, College

Road, Ludhiana.

Construction work in

12

2.5

3

3

1 year

12

2.5

3

3

16

Warehouse Project Plot Nos. B-3 to B-8 and A-4, Focal Point, Ludhiana, Punjab M/s Nahar Industrial Enterprises Ltd. EMP

Consultant: Eco Laboratories & Consultants Pvt. Ltd. Format No. EL\EIA\F-5.3\9 Date 15.01.2019 QCI-NABET Approved EIA Consultant

Govt. Primary School,

Churpur.

White wash in VRTC

School, Ludhiana

0.5

0.5

3. Roads

To maintain Fountain chowk

and Public park on National

Highway, GT Road, Ludhiana.

47

1 year

47

4. Financial aid to sports

persons

1 1 year 1

5. Sanitation

To protect canal at Verka Milk

Plant, Ferozepur Road,

Ludhiana to control water

pollution and public welfare of

society under Swachh Bharat

Abhiyan.

2.5

1 year

2.5

Total

Rs. 73.5

lakhs Rs. 73.5 lakhs

Compliance to Environmental Legislations

All applicable environmental laws/legislation will be complied with including:

1. Compliance of conditions stipulated in NOC granted by PPCB under Water and Air Act.

2. Compliance of Environmental Clearance as granted by SEIAA, Punjab.

3. Compliance of conditions imposed in Consent to Operate under Water & Air act.

4. The project proponent will abide by all other applicable rules/regulations as and when amended

from time to time.

17

Warehouse Project Plot Nos. B-3 to B-8 and A-4, Focal Point, Ludhiana, Punjab M/s Nahar Industrial Enterprises Ltd. RISK ASSESMENT

Consultant: Eco Laboratories & Consultants Pvt. Ltd. Format No. EL\EIA\F-5.3\9 Date 15.01.2019 QCI-NABET Approved EIA Consultant

RISK ASSESSMENT PLAN

M/s Nahar Industrial Enterprises Ltd. has plan to construct Warehouse Project at plot Nos. lot Nos.

B-3 to B-8and A-4 at Focal Point, Ludhiana, Punjab. The total plot area of the project is 25.57 acres

of land. The project mainly comprises of 4 blocks for the storage of Non-Agro Products.

Emergency Plan

Since the project may face fire hazards or other emergency situations; an emergency plan is provided

to caution the staff during any accidents. The fundamental approach, governing fire safety attempts

to ensure that fires do not at all start in the first place and if they occur, to restrain their spread by

quick detection and extinguishments.

Fire detection

Despite many precautions taken, fires may breakout. Hence the industry will establish measures to

detect a fire and to extinguish it. Automatic fire detection has many advantages such as speed and

reliability and is recommended.

Depending on the nature of the occupancy and the hazard, a variety of detection systems are

available. They are activated by one of the effects of fire such as temperature rise, smoke, flame or

heat and can be coupled to an alarm system which would provide visual/ audible alarms at designed

manned locations. They can also be designed to automatically actuate fire-extinguishing systems.

The selection / installation of the detection system should confirm to the applicable national

standards.

Extinguishing system

Equipment for the fighting should be chosen with care and suited to the task. Fires are classified

depending on the materials involved and appropriate extinguishing agents are also recommended.

Table-I gives the classification/ recommendation as per Indian Standard IS-15683. The

extinguishing agents mentioned are applied to the fire using portable or fixed appliances. To fight

abc
Textbox
18

Warehouse Project Plot Nos. B-3 to B-8 and A-4, Focal Point, Ludhiana, Punjab M/s Nahar Industrial Enterprises Ltd. RISK ASSESMENT

Consultant: Eco Laboratories & Consultants Pvt. Ltd. Format No. EL\EIA\F-5.3\9 Date 15.01.2019 QCI-NABET Approved EIA Consultant

fires at their incipient stage, portable extinguishers prove very useful. These must be provided in

adequate numbers at appropriate locations and staff should be thoroughly trained in their use.

Management Plan

Since the project may face fire hazards or other emergency situations; an emergency plan is provided

to caution the staff during any accidents. The fundamental approach, governing fire safety attempts

to ensure that fires do not at all start in the first place and should they occur, to restrain their spread

by quick detection and extinguishments.

Table-1: Fires - Classification & Extinguishing Media

Class of fire Description Extinguishing

medium

Indian

Standard

A Fires involving ordinary combustible

materials, like woods, paper textiles,

etc. where the cooling effect of water is

essential for the extinction of fire.

Water 934

940

6234

B Fire in flammable liquids like oils,

solvents, petroleum products,

varnishes, pains etc. where a blanketing

effects is essential

Foam

Carbon dioxide

Dry chemical

933

2878

2171

4308

C Fires involving gaseous substances

under pressure where it is necessary to

dilute the burning gas at a very fast rate

with an inert gas or powder.

Carbon dioxide Dry

Chemical powder

The best way to

extinguish such fires

is by stopping the

2878

2171, 4308

abc
Textbox
19

Warehouse Project Plot Nos. B-3 to B-8 and A-4, Focal Point, Ludhiana, Punjab M/s Nahar Industrial Enterprises Ltd. RISK ASSESMENT

Consultant: Eco Laboratories & Consultants Pvt. Ltd. Format No. EL\EIA\F-5.3\9 Date 15.01.2019 QCI-NABET Approved EIA Consultant

Class of fire Description Extinguishing

medium

Indian

Standard

flow of fuel gas to the

fire. Container is kept

cool with water spray

D Fires involving metals like magnesium,

aluminium, zinc, potassium, etc. where

the burning metal is reactive to water

and which requires special

extinguishing media or technique.

Special dry powders 2171

4861

The task of accident and emergency control can be simplified and made effective if pre-planned

systems and procedures are available. Without these, important matters may be overlooked at the

time of an emergency.

Every management must survey the total operation to identify potential for fire losses and develop

an action plan to put the business back to normal with minimum loss of time. A fire protection

Manual should be prepared, preferably in 3-parts. The first part should outline the fire risks in

terms of plant locations, equipment and facilities and indicate the ways in which risks have been

minimized. The second part would set out operating procedures, standards of fire protection

established, and maintenances of these standards action to be taken in the event of fire by every level

of management responsibility for inspection and repair. It should also include instructions for staff

responsible for building services. The third part should outline the training required for existing and

new staff, the inspection schedules and check lists, sources of additional information and help.

The Management Cell of the project shall keep ready a plan to alert and take care of staff in case

there is any fire. There shall be designated an Emergency Team that shall consist of staff of

maintenance department, security supervisor representative of staff from campus.

abc
Textbox
20

Warehouse Project Plot Nos. B-3 to B-8 and A-4, Focal Point, Ludhiana, Punjab M/s Nahar Industrial Enterprises Ltd. RISK ASSESMENT

Consultant: Eco Laboratories & Consultants Pvt. Ltd. Format No. EL\EIA\F-5.3\9 Date 15.01.2019 QCI-NABET Approved EIA Consultant

During non-emergencies, this team shall engage in activities as (1) Earmarking Area for Assembling

during Emergencies (2) Awareness Programme for the on fire, first aid and evacuation (3)

Identification of Hospitals (4) Identification and Displaying Emergency Numbers and Contacts (5)

Displaying Emergency Symbols (6) Updating First Aid Emergency Kit (7) Updating Fire Control

Systems (8) Preparation and Updating of Standard Operating procedures (SOP).

In case member on duty spots the emergency like comes to know about any fire, he will also try his

best to find out about the exact location and nature of emergency. In accordance with the SOP, the

following activities will immediately begin (1) Staff will be informed, necessary Alarms shall be

activated to direct the staff to the emergency assembly area if needed (2) The external network of

District Fire Station, Police and Hospital shall be intimated. Once the emergency situation is under

control, the team will initiate step-by-step restoration of normal operation.

abc
Textbox
21

Warehouse Project Plot Nos. B-3 to B-8 and A-4, Focal Point, Ludhiana, Punjab M/s Nahar Industrial Enterprises Ltd. FORM-I

Eco Laboratories & Consultants Pvt. Ltd. Format No. EL\EIA\F-5.3\9 Date 15.01.2019 (QCI-NABET Approved EIA Consultant)

Application for Environmental Clearance Form – I

(I) Basic Information: S.

No.

Item No. Details

1 Name of the Project/s Warehouse Project at Plot Nos. B-3 to B-8 and A-4, Focal

Point, Ludhiana, Punjab by M/s Nahar Industrial Enterprises

Ltd.

2 S. No. in the schedule The project falls under S.No. 8(a) ‘Building & Construction

Project’ as the built-up area of the project is 62,284.07 m2

3 Proposed capacity / area / length/

tonnage to be handled / command area

/ lease area / number of wells to drilled

M/s Nahar Industrial Enterprises Ltd. has plan to construct

Warehouse Project at Plot Nos. B-3 to B-8 and A-4, Focal

Point, Ludhiana, Punjab.

Total plot area of warehouse project site is 1,03,477 (25.57

acres). The project comprises of 4 blocks for storage of Non-

Agro Products.

Proposed Builtup area: 62,284.07 m2

List of Annxures enclosed:

Annexure 1(a): Land Allotment documents

Annexure 1(b): Cotton County Lease deem and CTO’s

Annexure 1(c) : CLU from General Manger,Distrct

Industries Center Ludhiana

Annexure 1(d): Instakart Services lease deed & CTE

Annexure 2: Memorandum and Articles of Association of

Nahar Inustrial Enterprises Limited

Annexure 3: Board of Resolution

Annexure 4: Undertaking regarding No litigation against

Forest, Wildlife & CRZ

Annexure 5: PERT Chart

Annexure 6: Soil Investigation report

Annexure 7(a): Intimation mail to PPCB

Annexre 7(b): Test report

39

Warehouse Project Plot Nos. B-3 to B-8 and A-4, Focal Point, Ludhiana, Punjab M/s Nahar Industrial Enterprises Ltd. FORM-I

Eco Laboratories & Consultants Pvt. Ltd. Format No. EL\EIA\F-5.3\9 Date 15.01.2019 (QCI-NABET Approved EIA Consultant)

Annexure 7(c): Field data sheets

Annexure 8: Affidavit Regarding EMC

Annexure 9: CA Certificate

Anneuxre 10: CGWA application

Annexure 11: Qunatification of Energy

Annexure 12: Site Photographs

Annexure 13(a): Office Memorandum regarding lifting of

Moratorium of Ludhiana

Annexure 13(b): Consideration of Projects in respect of Critically Polluted areas applicability of General Conditions to Construction Projects List of Drawings enclosed:

Drawing 1: Google Earth image showing 500m surroundngs

Drawing 2(a): Location plan

Drawing 2(b): Master plan pf Ludhiana

Drawing 3: Area Distribution Map

Drawing 4: Layout plan

Drawing 5: Services plan

Drawing 6: Parking plan

Drawing 7: Fire-fighting plan

Drawing 8: Roof plan

Drawing 9: Contour plan

Drawing 10: STP Schemtaic plan

4 New / Expansion / Modernization New

5 Existing capacity / Area etc N.A

6 Category of the project ‘ A’ or ‘B’ Category ‘B’(B-2)

7 Does it attract the general conditions?

If Yes, Please Specify.

No

8 Does it attract the specific conditions?

If Yes, Please Specify

No

9 Location Proposed project is located at Plot Nos. B-3 to B-8 and A-4,

Focal Point, Ludhiana, Punjab

40

Warehouse Project Plot Nos. B-3 to B-8 and A-4, Focal Point, Ludhiana, Punjab M/s Nahar Industrial Enterprises Ltd. FORM-I

Eco Laboratories & Consultants Pvt. Ltd. Format No. EL\EIA\F-5.3\9 Date 15.01.2019 (QCI-NABET Approved EIA Consultant)

Center coordinates of project loaction are 30053’00.00” N &

75054’20.96”.

Location plan showing the project location is enclosed as

Drawing 2(a)

Plot/ Survey/Khasra No. Plot Nos. B-3 to B-8 and A-4

Village Focal Point

Tehsil Ludhiana East

District Ludhiana

State Punjab

10. Nearest railway station / Airport along

with distance in kilometers.

Nearest railway station :

Dhandari Kalan Railway Station : 1.0 km (SE)

Ludhiana Railway Station : 6.50 km (NW)

Nearest Airport:

Ludhiana Airport, Sahnewal : 5.0 km; SE

11 Nearest town/District headquarters

along with distance in kilometers

The project lies within Ludhiana city .

District Headquaters: Ludhiana

12 Village Panchayat, Zilla Parishads,

Municipal corporation, local Bodies

(Complete Postal address with

telephone No. to be given)

Municipal Corporation Ludhiana,

Zone-B

Back side Shingar Cinema, Ludhiana

0161-2224308

13 Name of the applicant Mr. Suman Kumar Thakur

(Authorized Signatory)

Board of resolution for authorization is enclosed as

Annexure 3.

14 Registered address

M/s Nahar Industrial Enterprises Ltd.

Focal Point, Ludhiana

15 Address for correspondence : M/s Nahar Industrial Enterprises Ltd.

Focal Point, Ludhiana

Name : Mr. Suman Kumar Thakur

Designation (owner / Partner / CEO) Authorized Signatory

Address M/s Nahar Industrial Enterprises Ltd.

Focal Point, Ludhiana

41

Warehouse Project Plot Nos. B-3 to B-8 and A-4, Focal Point, Ludhiana, Punjab M/s Nahar Industrial Enterprises Ltd. FORM-I

Eco Laboratories & Consultants Pvt. Ltd. Format No. EL\EIA\F-5.3\9 Date 15.01.2019 (QCI-NABET Approved EIA Consultant)

Pin Code 141010

E- Mail [email protected]

Telephone No. 0091-161-2672590

Fax No. 0091-161-2674072

16 Details of alternative Sites examined,

if any. Location of these sites should

be shown on the topo Sheets.

No

17 Interlinked Projects No

18 Whether separate application of

interlinked project has been

submitted?

Not Applicable

19 If Yes, date of submission. Not Applicable

20 If No, reason Not Applicable

21 Whether the Proposal involves

approval / Clearance under : If Yes,

details of the same and their to be

given .

(a) The Forest Conservation, Act,1980

(b) The wild life Protection Act, 1972

(c) The C.R.Z Notification, 1991.

No. The project does not involve approval under Forest,

Wildlife & CRZ Clearance.Undertaking regarding the same

is enclosed as Annexure 4.

22 Either their is any government Order /

policy relevant / relating to the site?

No.

23. Forest land Involved (hectare) No

24. Whether there is any litigation

pending against the project and /or

land in which the Projects is proposed

to be set up?

(a) Name of the court

(b) Case no.

(c) Orders / Directions of the Courts ,

if any and its relevance with the

Project.

No. There is no litigation pending against the project.

Undertaking regarding the same is enclosed as Annexure 4.

42

Warehouse Project Plot Nos. B-3 to B-8 and A-4, Focal Point, Ludhiana, Punjab M/s Nahar Industrial Enterprises Ltd. FORM-I

Eco Laboratories & Consultants Pvt. Ltd. Format No. EL\EIA\F-5.3\9 Date 15.01.2019 (QCI-NABET Approved EIA Consultant)

(II) Activity

1. Construction, Operation or Decommissioning of the Project involving actions, which will

cause physical changes in the locality (topography, land use, changes in water bodies, etc.)

S.No. Information/Checklist confirmation Yes/No Details thereof (with approximate

quantities /rates, wherever possible) with

source of information data

1.1 Permanent or temporary change in land

use, land cover or topography including

increase in intensity of land use (with

respect to local land use plan)

Yes Change in land use has been issued from

General Industries, District Industries

Centre, Ludhiana vide Letter No.

DIC/LDH/595. Further, Project falls in

Industrial zone as per Master plan of

Ludhiana. Copy of the CLU as well as

Master plan of ludhiana is enclosed as

Annuxure 1(c) and Drawing 2(b)

respectively.

1.2 Clearance of existing land, vegetation and

buildings?

Yes The development of project requires

clearance of existing buildings as well as

vegetation.

1.3 Creation of new land uses? No The proposed construction will conform to

approved land use.

1.4 Pre-construction investigations e.g. bore

houses, soil testing?

Yes Soil investigation has been carried out at

the project location. Copy of the same is

enclosed Annexure 6.

1.5 Construction works?

Yes The construction of the project shall be as

per Layout plan and details of the same are

mentioned in Conceptual Plan.

Copy of layout plan is enclosed as

Drawing 3 and PERT/CPM is enclosed as

Annexure 5.

43

Warehouse Project Plot Nos. B-3 to B-8 and A-4, Focal Point, Ludhiana, Punjab M/s Nahar Industrial Enterprises Ltd. FORM-I

Eco Laboratories & Consultants Pvt. Ltd. Format No. EL\EIA\F-5.3\9 Date 15.01.2019 (QCI-NABET Approved EIA Consultant)

1.6 Demolition works? Yes Demolition work will be done for existing

buildings.

1.7 Temporary sites used for construction

works or housing of construction

workers?

Yes All the construction activity including

stocking of raw materials will be confined

within the project site only. Temporary

shelters for labor have been proposed.

Local labors from nearby area will be hired.

Sanitation facilities will be developed at

site.

1.8 Above ground buildings, structures or

earthworks including linear structures, cut

and fill or excavations

Yes Excavation will be carried out for the

foundation of proposed warehouse

buildings. Soil excavated will be stored

within the project & will be used for

landscaping within the project only

1.9 Underground works including mining or

tunneling?

No No underground works including mining or

tunneling is required except excavation of

earth.

1.10 Reclamation works? No No reclamation work is required.

1.11 Dredging? No No dredging is required.

1.12 Offshore structures? No No offshore structure is required.

1.13 Production and manufacturing processes? No No production and manufacturing process

is involved as the warehouse project is used

for storage of non-agro products.

1.14 Facilities for storage of goods or

materials?

Yes Raw materials will be stored at site in a

covered area. Cement will be separately

stored under cover in bales. Sand will be

stacked neatly under tarpaulin cover. Bricks

and steel will be laid in open.

1.15 Facilities for treatment or disposal of solid

waste or liquid effluents?

Yes Solid waste

Construction phase

Construction activities will cause

generation of debris, brick bats, plaster

44

Warehouse Project Plot Nos. B-3 to B-8 and A-4, Focal Point, Ludhiana, Punjab M/s Nahar Industrial Enterprises Ltd. FORM-I

Eco Laboratories & Consultants Pvt. Ltd. Format No. EL\EIA\F-5.3\9 Date 15.01.2019 (QCI-NABET Approved EIA Consultant)

falls, battered stone mixture, aggregate

leftovers, sand leftovers, empty cement

bags, cartons, etc. Most of the construction

waste generated will be reused in road

construction and filling.

Operation phase

Solid waste of about 29 kg/day (@ 0.20

kg/capita/day for staff and @ 0.15

kg/capita/day for floating) will be

generated from project. A separate area will

be earmarked for segregation of solid

waste. Biodegradable waste will be

composted by use of compost pit. Inert

waste will be dumped to authorized

dumping site.

All the solid waste generated during

construction and operational phase will be

treated and disposed off as per MSW

(Management & Handling) Rules, 2000 and

its amendments

Liquid effluent:

Construction phase

Sewage generation during construction

phase will be treated and disposed

Operational phase

5.2 KLD of sewage will be generated from

the project which will be treated in STP of

10 KLD capacity based on MBBR

Technology (skid mounted). The water

balance diagrams for 3 different seasons i.e.

Summer, Winter & Monsoon season is

shown in Figure 1(a), 1(b) & 1(c)

45

Warehouse Project Plot Nos. B-3 to B-8 and A-4, Focal Point, Ludhiana, Punjab M/s Nahar Industrial Enterprises Ltd. FORM-I

Eco Laboratories & Consultants Pvt. Ltd. Format No. EL\EIA\F-5.3\9 Date 15.01.2019 (QCI-NABET Approved EIA Consultant)

respectively in conceptual plan.

1.16 Facilities for long term housing of

operational workers?

No Local labourers will be hired from nearby

areas during construction phase of the

project. Temporary hutments will be

provided for few workers during

construction phase.

1.17 New road, rail or sea traffic during

construction or operation?

Yes The site is at a distance of approx. 0.8 km

(S) from National Highway NH-1. Internal

roads, paths will be developed for vehicular

movements for transportation of

construction material during construction

phase whereas internal tracks and paths will

be developed for traffic circulation during

operational phase.

1.18 New road, rail, air waterborne or other

transport infrastructure including new or

altered routes and stations, ports, airports

etc

No The site is well connected to road network.

The nearest highway is NH-1 which is at a

distance of 0.8 km from the project. Thus,

no new road, rail, air waterborne or other

transport infrastructure is required.

1.19 Closure or diversion of existing transport

routes or infrastructure leading to changes

in traffic movements?

No There is no need of diversion of existing

transport routes.

1.20 New or diverted transmission lines or

pipelines?

No There are no new or diverted transmission

lines.

1.21 Impoundment, damming, culverting,

realignment or other changes to the

hydrology of watercourses or aquifers?

No

No Impoundment, damming, culverting,

realignment or other changes to the

hydrology of watercourses or aquifers is

proposed.

1.22 Stream crossings? No There is no stream running across the site.

1.23 Abstraction or transfers of water form

ground or surface waters?

Yes Construction phase

Water required during the construction

period, will be supplied through private

46

Sachin ems
Textbox
STP

Warehouse Project Plot Nos. B-3 to B-8 and A-4, Focal Point, Ludhiana, Punjab M/s Nahar Industrial Enterprises Ltd. FORM-I

Eco Laboratories & Consultants Pvt. Ltd. Format No. EL\EIA\F-5.3\9 Date 15.01.2019 (QCI-NABET Approved EIA Consultant)

water tanker.

Operation phase

During operation phase, total groundwater

requirement for the project will be 64.5

KLD. 4 KLD is fresh water requirement

and 2.5 KLD is flushing water requirement.

During operational phase, water will be

abstracted through borewell.

1.24 Changes in water bodies or the land

surface affecting drainage or run-off?

No Run off will increase due to increased

paved surface. However, increased run off

will be managed by well-designed rain

water recharging system and storm water

management plan. Layout plan showing 14

Rain water harvesting pits is enclosed as

Drawing 5.

1.25 Transport of personnel or materials for

construction, operation or

decommissioning?

Yes During construction phase, movement of

10-12 vehicles shall be there.

Adequate parking space within the project

site for loading and unloading of materials

will be provided. Adequate parking space

of 15,591m2 will be provided for

operational phase within the project

premises.

1.26 Long-term dismantling or

decommissioning or restoration works?

No No long-term dismantling or

decommissioning or restoration work is

involved.

1.27 Ongoing activity during decommissioning

which could have an impact on the

environment?

No No decommissioning activity is involved,

Hence, No impact on the environment by

the proposed project is supposed.

1.28 Influx of people to an area in either

temporarily or permanently?

No Local laborers from nearby area will be

employed during the construction phase.

47

Sachin ems
Textbox
Sachin ems
Textbox
of Instakart Services Pvt. Ltd.

Warehouse Project Plot Nos. B-3 to B-8 and A-4, Focal Point, Ludhiana, Punjab M/s Nahar Industrial Enterprises Ltd. FORM-I

Eco Laboratories & Consultants Pvt. Ltd. Format No. EL\EIA\F-5.3\9 Date 15.01.2019 (QCI-NABET Approved EIA Consultant)

In the operation phase, most of the

expected staff members and visitors will be

from the surrounding areas. Hence, the

project will lead to a redistribution of

occupants within the city. Thus, no

significant influx of people is envisaged.

1.29 Introduction of alien species? No The landscaping is being carried out with

mainly local species with a few ornamental

varieties of flora that are well suited to the

local conditions.

1.30 Loss of native species or genetic

diversity?

No There will be no significant impact on the

loss of native species or genetic diversity.

1.31 Any other actions? No Not Applicable

2. Use of Natural resources for construction or operation of the Project (such as land, water,

materials or energy, especially any resources which are non-renewable or in short supply):

S.No

. Information/Checklist confirmation

Yes/

No

Details thereof (with approximate

quantities /rates, wherever possible) with

source of information data

2.1 Land especially undeveloped or

agricultural land (ha)

No Project falls in Industrial zone as per Master

plan of ludhiana. Copy of the Master plan

showing project location is enclosed as

Drawing 2(b).

2.2 Water (expected source & competing

users) unit: KLD

Yes During operation phase, water supply will

be provided from existing bore well. Total

groundwater requirement for the project

will be 64.5 KLD. 4 KLD is fresh water

requirement and 2.5 KLD is flushing water

requirement.

2.3 Minerals (MT) Yes Minerals such as sand and aggregates will

be required during the construction phase

48

Warehouse Project Plot Nos. B-3 to B-8 and A-4, Focal Point, Ludhiana, Punjab M/s Nahar Industrial Enterprises Ltd. FORM-I

Eco Laboratories & Consultants Pvt. Ltd. Format No. EL\EIA\F-5.3\9 Date 15.01.2019 (QCI-NABET Approved EIA Consultant)

3. Use, storage, transport, handling or production of substances or materials, which could be

harmful to human health or the environment or raise concerns about actual or perceived

risks to human health.

S.

No.

Information/Checklist confirmation Yes/

No

Details thereof (with approximate

quantities /rates, wherever possible) with

source of information data

3.1 Use of substances or materials, which are

hazardous (as per MSIHC rules) to human

health or the environment (flora, fauna,

and water supplies)

No The project will not use any hazardous

substances/ chemicals except for the used

Oil generated from DG set (Hazardous

Waste category 5.1). The same shall be

stored in HDPE tanks and will be sold to the

authorized recyclers in the region. It shall be

handled as per The Manufacture, Storage

and Import of Hazardous Chemical Rules,

2.4 Construction material – stone, aggregates,

sand/s oil (expected source – MT)

Yes All materials for construction will be

arranged through locally selected suppliers.

2.5 Forests and timber (source – MT) Yes The Project involves minimum use of

timber during construction purpose. All

material required for shuttering purpose

shall be that of mild steel.

2.6 Energy including electricity and fuels

(source, competing users) Unit: fuel (MT),

energy (MW)

Yes Total Power requirement for warehouse

project is estimated to be 165 KW which

will be provided by Punjab State Power

Corporation Limited.

Total 1 DG set of 250 KVA capacity

equipped with acoustic enclosure to

minimize noise generation and adequate

stack height for proper dispersion.

2.7 Any other natural resources (use

appropriate standard units)

No Not Applicable

49

Warehouse Project Plot Nos. B-3 to B-8 and A-4, Focal Point, Ludhiana, Punjab M/s Nahar Industrial Enterprises Ltd. FORM-I

Eco Laboratories & Consultants Pvt. Ltd. Format No. EL\EIA\F-5.3\9 Date 15.01.2019 (QCI-NABET Approved EIA Consultant)

1989 and Material Safety Data Sheet.

3.2 Changes in occurrence of disease or affect

disease vectors (e.g. insect or water borne

diseases)

No Suitable drainage and waste management

measures will be adopted in the construction

phase such that there is no stagnation of

water or accumulation of waste. This

effectively restricts the reproduction and

growth of disease vectors.

3.3 Affect the welfare of people e.g. by

changing living conditions?

Yes Socio-economic standard of people will

improve due to increased employment

opportunities provided by this project. This

will lead to better quality of life and will

also set a standard for future developments

in the area.

3.4 Vulnerable groups of people who could be

affected by the project e.g. hospital

patients, children, the elderly etc.

No Impacts of this type are not expected.

3.5 Any other cause No Not Applicable

4. Production of Solid Wastes during construction or operation or decommissioning (MT/month)

S.No.

Information/Checklist confirmation Yes/ No

Details thereof (with approximate quantities /rates, wherever possible) with source of information data

4.1 Spoil, overburden or mine wastes No Not much spoil, overburden or mine wastes will be generated.

4.2 Municipal waste (domestic and or commercial wastes)

Yes Construction phase

Construction activities will cause generation

of debris, brick bats, plaster falls, battered

stone mixture, aggregate leftovers, sand

leftovers, empty cement bags, cartons, etc.

Most of the construction waste generated

will be reused in road construction and

filling.

Operation phase

50

Warehouse Project Plot Nos. B-3 to B-8 and A-4, Focal Point, Ludhiana, Punjab M/s Nahar Industrial Enterprises Ltd. FORM-I

Eco Laboratories & Consultants Pvt. Ltd. Format No. EL\EIA\F-5.3\9 Date 15.01.2019 (QCI-NABET Approved EIA Consultant)

Solid waste of about 29 kg/day (@ 0.20

kg/capita/day for staff and @ 0.15

kg/capita/day for floating) will be generated

from project. A separate area will be

earmarked for segregation of solid waste.

Biodegradable waste will be composted by

use of compost pit. Inert waste will be

dumped to authorized dumping site.

All the solid waste generated during

construction and operational phase will be

treated and disposed off as per MSW

(Management & Handling) Rules, 2000 and

its amendments.

4.3 Hazardous wastes (as per Hazardous Waste Management Rules)

Yes The only hazardous waste generated from

the project will be used/spent oil from

standby DG set, which is classified as

Hazardous waste Category 5.1 as per

Hazardous and Other Wastes (Management

and Transboundary Movement) Rules,

2016. The spent oil will be carefully stored

in HDPE drums under isolated storages and

will be sold to authorized vendors.

4.4 Other industrial process wastes No Not Applicable

4.5 Surplus product No Not Applicable

4.6 Sewage sludge or other sludge from effluent treatment

Yes STP sludge will be generated from proposed

STP to be installed within the project

premises. It will be dried and later will be

used as manure for landscaping.

4.7 Construction or demolition wastes Yes The construction waste consists of excess

earth & construction debris along with

cement bags, steel in bits & pieces,

including insulating & packaging materials,

51

Warehouse Project Plot Nos. B-3 to B-8 and A-4, Focal Point, Ludhiana, Punjab M/s Nahar Industrial Enterprises Ltd. FORM-I

Eco Laboratories & Consultants Pvt. Ltd. Format No. EL\EIA\F-5.3\9 Date 15.01.2019 (QCI-NABET Approved EIA Consultant)

etc. Recyclable waste construction materials

will be sold to recyclers. Unusable and

excess construction debris will be disposed

at designated places in tune with the local

norms.

4.8 Redundant machinery or equipment No Redundant machinery will not be generated.

4.9 Contaminated soils or other materials No Contaminated soils or other materials will not be generated.

4.10 Agricultural wastes No Not Applicable

4.11 Other solid wastes No Not Applicable

5. Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr)

S.

No.

Information/Checklist confirmation Yes/

No

Details thereof (with approximate

quantities /rates, wherever possible) with

source of information data

5.1 Emissions from combustion of fossil fuels

from stationary or mobile sources

Yes The project does not envisage any major air

pollution sources except operation of 1 DG

set of 250 KVA capacity during power

failure and vehicular traffic.

5.2 Emissions from production processes No No production processes involved. Hence,

there will be no such emissions.

5.3 Emissions from materials handling

including storage or transport

No Not Applicable

5.4 Emissions from construction activities

including plant and equipment

Yes This will be restricted to the construction

phase and the construction site only. PERT/

CPM chart is attached as Annexure 5.

5.5 Dust or odours from handling of materials

including construction materials, sewage

and waste

Yes The construction material involved shall not

provide any odour. A green belt is further

proposed along the boundary with internal

parks and lawns and solid waste

segregation area to mitigate crossover of

52

Warehouse Project Plot Nos. B-3 to B-8 and A-4, Focal Point, Ludhiana, Punjab M/s Nahar Industrial Enterprises Ltd. FORM-I

Eco Laboratories & Consultants Pvt. Ltd. Format No. EL\EIA\F-5.3\9 Date 15.01.2019 (QCI-NABET Approved EIA Consultant)

odours, if any. Tarpaulin cover will be

provided on stored loose materials to

reduce the dust emission.

5.6 Emissions from incineration of waste No No incineration of waste is proposed.

5.7 Emissions from burning of waste in open

air (e.g. slash materials, construction

debris)

No Not Applicable

5.8 Emissions from any other sources No Not Applicable

6. Generation of Noise and Vibration, and Emissions of Light and Heat:

S.

No.

Information/Checklist confirmation Yes /

No

Details thereof (with approximate

quantities /rates, wherever possible) with

source of information data

6.1 From operation of equipment e.g. engines,

ventilation plant, crushers

Yes The unit shall install 1 DG set of capacity

250 KVA for standby use during

operational phase. The DG set shall be with

in-built acoustic enclosure as approved by

CPCB and conforming to MoEF

Notification, GSR 371 (E).

6.2 From industrial or similar processes No Not Applicable.

6.3 From construction or demolition No Normal construction will be there without

using any heavy machinery. No

construction at night shall be there.

6.4 From blasting or piling No Not Applicable.

6.5 From construction or operational traffic Yes Some noise will be generated from

vehicular movement in the construction and

operational phase but that will be mitigated

with green belt and PUC vehicle will be

only operated. Layout plan showing the

green area is shown in layout plan which is

enclosed as Drawing 4.

53

Warehouse Project Plot Nos. B-3 to B-8 and A-4, Focal Point, Ludhiana, Punjab M/s Nahar Industrial Enterprises Ltd. FORM-I

Eco Laboratories & Consultants Pvt. Ltd. Format No. EL\EIA\F-5.3\9 Date 15.01.2019 (QCI-NABET Approved EIA Consultant)

6.6 From lighting or cooling systems No No significant noise impact will result from

lighting or cooling systems.

6.7 From any other sources No Not Applicable.

7. Risks of contamination of land or water from releases of pollutants into the ground or into

sewers, surface waters, groundwater, coastal waters or the sea:

S.

No.

Information/Checklist confirmation Yes /

No

Details thereof (with approximate

quantities /rates, wherever possible) with

source of information data

7.1 From handling, storage, use or spillage

of hazardous materials

No The used oil from DG set will be carefully

stored in HDPE drums at isolated storage

and periodically sold to authorized

recyclers. All precautions will be taken to

avoid spillage from storage as per

Hazardous and Other Wastes (Management

and Transboundary Movement) Rules,

2016.

7.2 From discharge of sewage or other

effluents to water or the land (expected

mode and place of discharge)

Yes 5.2 KLD of sewage will be generated from

the project which will be treated in STP of

10 KLD capacity based on MBBR

Technology (skid mounted). There will be

no discharge of untreated sewage on land

or into water bodies. Recycled water will

be re-used for flushing and landscaping.

The water balance diagrams for 3 different

seasons i.e. Summer, Winter & Monsoon

season is shown in Figure 1(a), 1(b) &

1(c) respectively in conceptual plan.

7.3 By deposition of pollutants emitted to air

into the land or into water

No The DG set will be provided with stack of

adequate height. Hence, dispersion will be

achieved and avoid deposition of pollutants

54

Warehouse Project Plot Nos. B-3 to B-8 and A-4, Focal Point, Ludhiana, Punjab M/s Nahar Industrial Enterprises Ltd. FORM-I

Eco Laboratories & Consultants Pvt. Ltd. Format No. EL\EIA\F-5.3\9 Date 15.01.2019 (QCI-NABET Approved EIA Consultant)

in significant concentrations at any single

location.

7.4 From any other sources No Not Applicable

7.5 Is there a risk of long term build up of

pollutants in the environment from these

sources?

No Not Applicable

8. Risk of accidents during construction or operation of the Project, which could affect

human health or the environment

S.

No.

Information/Checklist confirmation Yes /

No

Details thereof (with approximate

quantities /rates, wherever possible) with

source of information data

8.1 From explosions, spillages, fires etc

from storage, handling, use or

production of hazardous substances

Yes This is a Warehouse project and does not

involve major hazardous construction

activity. Hence, chances of explosions,

spillages, fires etc. are minimal.

During construction, suitable personal

protective equipment will be provided to all

construction workers as required under the

health & safety norms. Awareness &

Training about safety norms will be

provided to all the supervisor and

construction workers involved in

construction activities

To deal with any fire related accident, fire

fighting facility will be provided within the

project. Firefighting layout plan is enclosed

as Drawing 7.

8.2 From any other causes

No No other causes are involved except the

mentioned above.

55

Warehouse Project Plot Nos. B-3 to B-8 and A-4, Focal Point, Ludhiana, Punjab M/s Nahar Industrial Enterprises Ltd. FORM-I

Eco Laboratories & Consultants Pvt. Ltd. Format No. EL\EIA\F-5.3\9 Date 15.01.2019 (QCI-NABET Approved EIA Consultant)

8.3 Could the project be affected by natural

disasters causing environmental damage

(e.g. floods, earthquakes, landslides,

cloudburst etc)?

No The project falls under seismic active Zone

IV according to the Indian Standard Seismic

Zoning Map.

Suitable seismic coefficient will be adopted

in horizontal and vertical direction

respectively, while designing the structure.

There is no possibility of flood as per

records available near the proposed project

site.

9. Factors which should be considered (such as consequential development) which could lead

to environmental effects or the potential for cumulative impacts with other existing or

planned activities in the locality

S.No. Information/Checklist confirmation Yes /

No

Details thereof (with approximate

quantities /rates, wherever possible) with

source of information data

9.1 Lead to development of supporting.

utilities, ancillary development or

development stimulated by the project

which could have impact on the

environment e.g.:

•Supporting infrastructure (roads,

power supply, waste or waste water

treatment, etc.)

• housing development

• extractive industries

• supply industries

• other

Yes Appropriate infrastructure like roads, power

supply, waste management and waste water

treatment will be developed within the

project site.

The project will have positive impact on the

ancillary infrastructure like road, markets,

public health, amenities, conveyance

facilities etc.

No housing development

No Extractive industries

No Supply industries

NA

9.2 Lead to after-use of the site, which

could have an impact on the

environment

No Not Anticipated.

56

Warehouse Project Plot Nos. B-3 to B-8 and A-4, Focal Point, Ludhiana, Punjab M/s Nahar Industrial Enterprises Ltd. FORM-I

Eco Laboratories & Consultants Pvt. Ltd. Format No. EL\EIA\F-5.3\9 Date 15.01.2019 (QCI-NABET Approved EIA Consultant)

9.3 Set a precedent for later developments No Not Applicable

9.4 Have cumulative effects due to

proximity to other existing or planned

projects with similar effects

No Not Applicable

(III) Environmental Sensitivity

S.No. Areas Name/

Identity

Aerial distance (within

15 km) Proposed project

location boundary

1 Areas protected under international

conventions, national or local legislation for

their ecological, landscape, cultural or other

related value

No None

2 Areas which are important or sensitive for

ecological reasons - Wetlands, watercourses or

other water bodies, coastal zone, biospheres,

mountains, forests

Yes Sutlej River : 13.0 km;

SW

3 Areas used by protected, important or sensitive

species of flora or fauna for breeding, nesting,

foraging, resting, over wintering, migration

No None

4 Inland, coastal, marine or underground waters Yes Underground water exists

5 State, National boundaries No None

6 Routes or facilities used by the public for

access to recreation or other tourist, pilgrim

areas

NH-1 Approx. 0.8 km (S)

7 Defense installations No None

8 Densely populated or built-up area Shimlapuri

Mundian

Approx. 3.3 km (SW)

Approx. 3.2 km (NE)

57

Warehouse Project Plot Nos. B-3 to B-8 and A-4, Focal Point, Ludhiana, Punjab M/s Nahar Industrial Enterprises Ltd. FORM-I

Eco Laboratories & Consultants Pvt. Ltd. Format No. EL\EIA\F-5.3\9 Date 15.01.2019 (QCI-NABET Approved EIA Consultant)

9 Areas occupied by sensitive man-made land

uses (hospitals, schools, places of worship,

community facilities)

BCM College of

Education

Guru Nanak Dev

Polytechnic

College

Guru Nanak

Girls College

SPS Hospital

Fortis Hospital

Krishna Temple

Gurudwara Nanaska

2.5 km; NW

5.0 km; SW

6.0 km; W

1.7 km; W

3.0 km; NE

2.0 km; NW

4.0 km; NW

10 Areas containing important, high quality or

scarce resources (ground water resources,

surface resources, forestry, agriculture,

fisheries, tourism, minerals)

No None

11 Areas already subjected to pollution or

environmental damage. (those where existing

legal environmental standards are exceeded)

None The area is not subjected

to any environmental

damage.

12 Areas susceptible to natural hazard which could

cause the project to present environmental

problems (earthquakes, subsidence, landslides,

erosion, flooding or extreme or adverse

climatic conditions)

Earthquakes The site falls under the

zone IV as per the

Seismic Zone Map of

India and is thus prone to

high damage risk zone.

Adequate measures will

be taken during the

construction of the

project.

58

Warehouse Project Plot Nos. B-3 to B-8 and A-4, Focal Point, Ludhiana, Punjab M/s Nahar Industrial Enterprises Ltd. FORM-I

Eco Laboratories & Consultants Pvt. Ltd. Format No. EL\EIA\F-5.3\9 Date 15.01.2019 (QCI-NABET Approved EIA Consultant)

(IV) Terms of Reference:

Not Applicable as project comes under category 8(a).

I hereby give the Undertaking that the data and information given in the application and enclosure are true to the best of my knowledge and belief, I am aware that if any part of the data and information submitted is found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. Date: 22.06.2019

Place: Ludhiana

Signature of the applicant Mr. Suman Kumar Thakur

Plot Nos. B-3 to B-8 and A-4, Focal Point, Ludhiana, Punjab NOTE:

1. The project involving clearance under Coastal Regulation zone Notification, 1991 shall

submit with the application a C.R.Z map duly demarcated by one of the authorized agencies,

showing the project activities, w.r.t. C.R.Z (at the stage of TOR) and the recommendation of

the state coastal zone Management Authority (at the stage of EC). Simultaneous action shall

also be taken to obtain the requisite clearance under the provisions of the C.R.Z Notification,

1991 for the activities to be located in the CRZ.

2. The project to be located within 10 km of the National parks, Sanctuaries, Biophere

Reserves, Migratory Corridors of wild Animals, the project proponent shall submit the map

duly authenticated by chief wildlife warden showing these features vis-à-vis the project

location and the recommendation or comments of the Chief wildlife warden thereon (at the

stage of EC).

3. All correspondence with the Ministry of Environment & Forests including submission

of application for TOR/Environmental Clearance, subsequent clarification, as may be required

from time to time, participation in the authorized signatory only. The authorized signatory

59

Warehouse Project Plot Nos. B-3 to B-8 and A-4, Focal Point, Ludhiana, Punjab M/s Nahar Industrial Enterprises Ltd. FORM-I

Eco Laboratories & Consultants Pvt. Ltd. Format No. EL\EIA\F-5.3\9 Date 15.01.2019 (QCI-NABET Approved EIA Consultant)

should also submit a document in support of his claim of being an authorized signatory for the

specific project.

60

75

abc
Textbox
Annexure1(a)

Scanned by CamScanner76

77

78

79

80

81

82

83

84

85

86

87

88

89

90

91

92

93

Scanned by CamScanner94

abc
Textbox
Annexure 1(b)

Scanned by CamScanner95

Scanned by CamScanner96

Scanned by CamScanner97

Scanned by CamScanner98

“This is computer generated document from OCMMS by PPCB”

Nahar industrial enterprises ltd. (garment unit), leased to cotton county retail ltd. ,Focal point, phase iv, ludhiana-i,Jagroan,Ludhiana i,141010

Page1

1. Particulars of Consent to Operate under Air Act, 1981 granted to the industry

2. Particulars of the Industry

PUNJAB POLLUTION CONTROL BOARDZonal Office-I, Ludhiana

Website:- www.ppcb.gov.in

Office Dispatch No : Registered/Speed Post Date:

Industry Registration ID: G13LDH1397066 Application No : 7137677

To,H N SINGHALNAHAR INDUSTRIAL ENTERPRISES LTD.LUDHIANA,LUDHIANA-141010

Subject: Renewal of 'Consent to Operate' u/s 21 of Air (Prevention & Control of Pollution) Act, 1981 for discharge ofemissions arising out of premises.

With reference to your application for obtaining Renewal of 'Consent to Operate' u/s 21 of Air (Prevention &Control of Pollution) Act, 1981, you are hereby, authorized to operate an industrial unit for discharge of theemission(s) arising out of your premises subject to the Terms and Conditions as mentioned in this Certificate.

Consent to Operate Certificate No. CTOA/Renewal/LDH1/2018/7137677

Date of issue : 23/04/2018

Date of expiry : 30/09/2022

Certificate Type : Renewal

Previous CTO No. & Validity : R14LDH1CTOA621177From:01/01/2014 To:31/03/2018

Name & Designation of the Applicant H N SINGHAL, (PRESIDENT)

Address of Industrial premises Nahar industrial enterprises ltd. (garment unit), leased tocotton county retail ltd. ,Focal point, phase iv, ludhiana-i,Jagroan,Ludhiana i-141010

Capital Investment of the Industry 1364.33 lakhs

Category of Industry Orange

Type of Industry Other

Scale of the Industry Large

Office District Ludhiana i

99

“This is computer generated document from OCMMS by PPCB”

Nahar industrial enterprises ltd. (garment unit), leased to cotton county retail ltd. ,Focal point, phase iv, ludhiana-i,Jagroan,Ludhiana i,141010

Page2

Endst. No.: Dated:

A copy of the above is forwarded to the following for information and necessary action please:

The Environmental Engineer, Regional Office-1, Punjab Pollution Control Board, Ludhiana for information & necessary action.

Consent Fee Details Rs. 2400/- vide UTRL no.SBIN918023840308 dated 23.01.2018 asNOC regularization feeRs. 90,000/- vide UTR no.SBIN918022139362 dated 22.01.2018under Water Act, 1974.Rs. 90,000 vide UTR no.SBIN818020377912 dated 20.01.2018under Air Act, 1981.Adequate up to 31.03.2023

Raw Materials (Name with Quantity per day) Fusing @ 150000 MT/Year, Fabric @ 2218800 MT/Year,Pocketing @ 150000MT/Year, Zipper @ 720000 No./Year, Button @ 4500000No./Year, Labels @2650000 @ No./Year, Tags @ 465000 No./Year, Polybag @750000 No./year,Thread @ 340000 No./Year, Corrugated Boxes @ 80000No./Year

Products (Name with Quantity per day) Garments Production & Washing @ 10,000 Nos./day

By-products, if any, (Name with Quantity per day) Nil

Details of the machinery and process Fabric Receiving & Checking-> Cutting & Stickering ->Stitching & 1st Cheking -> Kaj & Buttoning -> ThreadCutting -> Washing Process-> Pressing & Final Checking -> Tagging & Packing -> Ready to Dispatch.

Quantity of fuel required (in TPD) and capacity ofboilers/ Furnace/Thermo heater etc.

Wood & Briquettes @ 3 MT/day

Type of Air Pollution Control Devices to be installed Cyclone Separator as APCDD.G. Sets placed in a room provided with acousticenclosure

Stack height provided with each boiler/thermoheater/Furnace etc.

Stack height of Boiler @ 33 M (Above Ground Level)/20 M(Above Roof Level)Stack height of D.G. Sets @ 12 M ( Above Ground Level)/4M (Above Roof Level)

Sources of emissions and type of pollutants One Boiler (Thermax) @ 1.0 TPHThree D.G. Sets @ 320 KVA, 200 KVA & 625 KVA

Standards to be acheived under Air(Prevention &Control of Pollution) Act, 1981

As Prescribed by the Board.

Environmental EngineerFor & on behalf

of

(Punjab Pollution Control Board)

Environmental EngineerFor & on behalf

of

100

“This is computer generated document from OCMMS by PPCB”

Nahar industrial enterprises ltd. (garment unit), leased to cotton county retail ltd. ,Focal point, phase iv, ludhiana-i,Jagroan,Ludhiana i,141010

Page3

(Punjab Pollution Control Board)

101

“This is computer generated document from OCMMS by PPCB”

Nahar industrial enterprises ltd. (garment unit), leased to cotton county retail ltd. ,Focal point, phase iv, ludhiana-i,Jagroan,Ludhiana i,141010

Page4

TERMS AND CONDITIONS

A. GENERAL CONDITIONS

1. This consent is not valid for getting power load from the Punjab State Power Corporation Ltd. or for gettingloan from the financial institutions.

2. The industry shall apply for renewal /extension of consent at least two months before expiry of the consent.

3. The industry shall not violate any of the norms prescribed under the Air (Prevention & Control of Pollution)Act, 1981, failing which, the consent shall be cancelled / revoked.

4. The achievement of adequacy and efficiency of the air pollution control devices installed shall be the entireresponsibility of the industry

5. The authorized fuel being used shall not be changed without the prior written permission of the Board.

6. The industry shall not discharge any fugitive emissions. All gases shall be emitted through a stack ofsuitable height, as per the norms fixed by the Board from time to time.

7. The industry shall provide port-holes, platforms and/or other necessary facilities as may be required forcollecting samples of emissions from any chimney, flue or duct or any other outlets.

Specifications of the port-holes shall be as under:-

i) The sampling ports shall be provided atleast 8 times chimney diameter downstream and 2 timesupstream from the flow disturbance. For a rectangular cross section the equivalent diameter (De)shall be calculated from the following equation to determine upstream, downstream distance:-

De = 2 LW / (L+W)

Where L= length in mts. W= Width in mts.

ii) The sampling port shall be 7 to 10 cm in diameter

8. The industry shall put display Board indicating environmental data in the prescribed format at the mainentrance gate.

9. The industry shall discharge all gases through a stack of minimum height as specified in the followingstandards laid down by the Board.

(i) Stack height for boiler plants

S.NO. Boiler with Steam GeneratingCapacity

Stack heights

1. Less than 2 ton/hr. 9 meters or 2.5 times the height of neighboring buildingwhich ever is more

2. More than 2 ton/hr. to 5 ton/hr. 12 meters

3. More than 5 ton/hr. to 10 ton/hr 15 meters

4. More than 10 ton/hr. to 15 ton/hr 18 meters

5. More than 15 ton/hr. to 20 ton/hr 21 meters

6. More than 20 ton/hr. to 25 ton/hr. 24 meters

7. More than 25 ton/hr. to 30 ton/hr. 27 meters

8. More than 30 ton/hr. 30 meters or using the formulaH = 14 Qg0.3orH = 74 (Qp)0.24Where Qg = Quantity of SO2 in Kg/hr.Qp = Quantity of particulate matter in Ton/day.

Note : Minimum Stack height in all cases shall be 9.0 mtr. or as calculated from relevant formulawhichever is more.

(ii) For industrial furnaces and kilns, the criteria for selection of stack height would be based on fuelused for the corresponding steam generation.

(iii) Stack height for diesel generating sets:

102

“This is computer generated document from OCMMS by PPCB”

Nahar industrial enterprises ltd. (garment unit), leased to cotton county retail ltd. ,Focal point, phase iv, ludhiana-i,Jagroan,Ludhiana i,141010

Page5

Capacity of diesel generating set Height of the Stack

0-50 KVA Height of the building + 1.5 mt

50-100 KVA -do- + 2.0 mt.

100-150 KVA -do- + 2.5 mt.

150-200 KVA -do- + 3.0 mt.

200-250 KVA -do- + 3.5 mt.

250-300 KVA -do- + 3.5 mt.

For higher KVA rating stack height H (in meter) shall be worked out according to the formula:

H = h+0.2 (KVA)0.5

where h = height of the building in meters where the generator set is installed.

10. The pollution control devices shall be interlocked with the manufacturing process of the industry to ensureits regular operation.

11. The existing pollution control equipment shall be altered or replaced in accordance with the directions of theBoard, and no pollution control equipment or chimney shall be altered or as the case may be erected or re-erected except with the prior approval of the Board.

12. The industry will provide canopy and adequate stack with the D.G sets so as to comply with the provision ofnotification No GSR-371 E dated 17-5-2002(amended from time to time) issued by MOEF underEnvironment (Protection) Act, 1986.

13. The Govt. of Punjab, Department of Science, Technology & Environment vide its notification no.4/46/92-3ST/2839 dt. 29/12/1993 has put prohibition on the use of rice husk as fuel after 1.4.1995 except thefollowing:-

“In the form of briquettes and use of rice husk in fluidized bed combustion.So the industry shall makethe necessary arrangement to comply with the above notification.”

14. The industry shall submit balance sheet of every financial year to the concerned Regional Office by 30thJune of every year

15. That the industry shall submit a yearly certificate to the effect that no addition / up-gradation/ modification/modernization has been carried out during the previous year otherwise the industry shall apply for the variedconsent.

16. a) The industry shall ensure that at any time the emission do not exceed the prescribed emissionsstandards laid down by the Board from time to time for such type of industry /emissions.

b) The industry shall ensure that the emissions from each stack shall conform to the followingemission standards laid down by the Board in respect of the Industrial Boilers.

Steam Generatingcapacity A.

Required particulate matter B.

Area upto 5 Km fromOther than the peripheryof I and Class-II town

Other than 'A' class

Less than 2 ton/hr. 800 mg/NM3 1200 mg/NM3

2 ton to 10 ton/hr. 500 mg/NM3 1000 mg/NM3

Above 10 ton to 15 ton/hr 350 mg/NM3 500 mg/NM3

Above 15 ton/hr 150 mg/NM3 150 mg/NM3

All emissions normalized to 12% carbon dioxide.

17. The industry shall ensure that the Hazardous Wastes generated from the premises are handled as per theprovisions of theHazardous Waste (Management, Handling and Transboundary Movement) Rules, 2008,without any adverse effect on the environment, in any manner.

18. The air pollution control equipments shall be kept at all time in good running condition and;

103

“This is computer generated document from OCMMS by PPCB”

Nahar industrial enterprises ltd. (garment unit), leased to cotton county retail ltd. ,Focal point, phase iv, ludhiana-i,Jagroan,Ludhiana i,141010

Page6

(i) All failures of control equipments.

(ii) The emissions of any air pollutant into the atmosphere in excess of the standards lay down by theBoard occurring or being apprehended to occur due to accident or other unforeseen act or event.'Shall be intimated through fax to the concerned Regional Office as well as to the Director ofFactories, Punjab, Chandigarh as required under rule 10 of the Punjab State Board for thePrevention and Control of Air Pollution Rules, 1983'.

19. The industry shall plant minimum of three suitable varieties of trees at the density of not less than 1000 treesper hectare all along the boundary of the industrial premises.

20. The industry shall submit a site emergency plan approved by the Chief Inspector of Factories, Punjab asapplicable.

21. The industry shall comply with the conditions imposed by the SEIAA/MOEF in the EnvironmentalClearance granted to it as required under EIA notification dated 14/9/06, if applicable.

22. The industry shall make necessary arrangements for the monitoring of stack emissions and shall get itsemissions analyzed from lab approved / authorized by the Board:-

(i) Once in Year for Small Scale Industries.

(ii) Twice/thrice/four time in a Year for Large/Medium Scale Industries.

23. The industry shall maintain the following record to the satisfaction of the Board :-

(i) Log books for running of air pollution control devices or pumps/motors used for it.

(ii) Register showing the result of various tests conducted by the industry for monitoring of stackemissions and ambient air.

(iii) Register showing the stock of absorbents and other chemicals to be used for scrubbers.

24. The industry will install the separate energy meter for running pollution control devices and shall maintainrecord with respect to operation of air pollution control device so as to the satisfy the Board regarding theregular operation of air pollution control device and monthly reading / record may be sent to the Board bythe fifth of the following month.

25. The industry shall provide online monitoring system as applicable, for in stack emission and shall maintainthe record of the same for inspection of the Board Officers.

26. The Board reserves the right to revoke the consent granted to the industry at any time, in case the industry isfound violating the provisions of Air (Prevention & Control of Pollution) Act, 1981 as amended from timeto time.

27. The industry shall comply with any other conditions laid down or directions issued in due course by theBoard under the provisions of the Air (Prevention & Control of Pollution) Act, 1981.

28. Nothing in this consent shall be deemed to neither preclude the institution of any legal action nor relieve theapplicant from any responsibilities, liabilities or penalties to which the applicant is or may be subjected tounder this or any other Act.

29. Any amendments/revisions made by the Board/CPCB/MOEF in the emission/stack height standards shall beapplicable to the industry from the date of such amendments/revisions.

30. The industry shall dispose off its solid waste generated by the burning of fuel in an Environmentally SoundManner within the premises/outside as approved by the Board, to avoid public nuisance and air pollutionproblem in the area.

31. The industry shall ensure that no air pollution problem or public nuisance is created in the area due to thedischarge of emissions from the industry.

32. The industry shall provide adequate arrangement for fighting the accidental leakage/discharge of any airpollutant/gas/ liquids from the vessels, mechanical equipment's etc, which are likely to cause environmentalpollution.

33. The industry shall not change or alter the manufacturing process(es) and fuel so as to change thequality/quantity of emissions generated without the prior permission of the Board.

34. The industry shall earmark a land within their premises for disposal of boiler ash in an environmentallysound manner, and / or the industry shall make necessary arrangements for proper disposal of fuel ash in ascientific manner and shall maintain proper record for the same, if applicable.

35. The industry shall obtain and submit Insurance cover under the Public Liability Insurance Act, 1991.

36. The industry shall provide proper and adequate air pollution control arrangements for control emission fromits fuel handling area, if applicable.

104

“This is computer generated document from OCMMS by PPCB”

Nahar industrial enterprises ltd. (garment unit), leased to cotton county retail ltd. ,Focal point, phase iv, ludhiana-i,Jagroan,Ludhiana i,141010

Page7

37. The industry shall comply with the code of practice as notified by the Government/Board for the type ofindustries where the siting guidelines / Code of Practice have been notified.

38. The industry shall not cause any nuisance/traffic hazard in vicinity of the area

39. The industry shall ensure that the noise & air emission from D.G. sets do not exceed the standardsprescribed for D.G. sets by the Ministry of Environment & Forests, New Delhi.

40. The industry shall ensure that there will not be significant visible dust emissions beyond the property line

41. The industry shall provide adequate and appropriate air pollution control devices to contain emissions fromhandling, transportation and processing of raw material & product of the industry.

42. The Industry shall ensure that its production capacity does not exceed the capacity mentioned in the consentand shall not carry out any expansion without the prior permission / NOC of the Board.

Environmental EngineerFor & on behalf

of

(Punjab Pollution Control Board)

105

“This is computer generated document from OCMMS by PPCB”

Nahar industrial enterprises ltd. (garment unit), leased to cotton county retail ltd. ,Focal point, phase iv, ludhiana-i,Jagroan,Ludhiana i,141010

Page1

1. Particulars of Consent to Operate under Water Act, 1974 granted to the industry

2. Particulars of the Industry

PUNJAB POLLUTION CONTROL BOARDZonal Office-I, Ludhiana

Website:- www.ppcb.gov.in

Office Dispatch No : Registered/Speed Post Date:

Industry Registration ID: G13LDH1397066 Application No : 7138197

To,H N SINGHALNAHAR INDUSTRIAL ENTERPRISES LTD.LUDHIANA,LUDHIANA-141010

Subject: Renewal of 'Consent to Operate'an outlet u/s 25/26 of Water (Prevention & Control of Pollution) Act, 1974 fordischarge of effluent.

With reference to your application for obtaining Renewal of ‘Consent to Operate’an outlet for discharge of theeffluent u/s 25/26 of Water (Prevention & Control of Pollution) Act, 1974, you are, hereby, authorized to operate anindustrial unit fordischarge of the effluent(s) arising out of your premises subject to the Terms and Conditions asmentioned in this Certificate.

Consent to Operate Certificate No. CTOW/Renewal/LDH1/2018/7138197

Date of issue : 23/04/2018

Date of expiry : 30/09/2022

Certificate Type : Renewal

Previous CTO No. & Validity : R14LDH1CTOW621259From:27/01/2014 To:31/03/2018

Name & Designation of the Applicant H N SINGHAL, (PRESIDENT)

Address of Industrial premises Nahar industrial enterprises ltd. (garment unit), leased tocotton county retail ltd. ,Focal point, phase iv, ludhiana-i,Jagroan,Ludhiana i-141010

Capital Investment of the Industry 1364.33 lakhs

Category of Industry Orange

Type of Industry Other

Scale of the Industry Large

Office District Ludhiana i

106

“This is computer generated document from OCMMS by PPCB”

Nahar industrial enterprises ltd. (garment unit), leased to cotton county retail ltd. ,Focal point, phase iv, ludhiana-i,Jagroan,Ludhiana i,141010

Page2

Endst. No.: Dated:

A copy of the above is forwarded to the following for information and necessary action please:

The Environmental Engineer, Regional Office-1, Punjab Pollution Control Board, Ludhiana for information & necessary action.

Consent Fee Details Rs. 2400/- vide UTRL no.SBIN918023840308 dated 23.01.2018 asNOC regularization feeRs. 90,000/- vide UTR no.SBIN918022139362 dated 22.01.2018under Water Act, 1974.Rs. 90,000 vide UTR no.SBIN818020377912 dated 20.01.2018under Air Act, 1981.Adequate up to 31.03.2023

Raw Materials(Name with quantity per day) Fusing @ 150000 MT/Year, Fabric @ 2218800 MT/Year,Pocketing @ 150000MT/Year, Zipper @ 720000 No./Year, Button @ 4500000No./Year, Labels @2650000 @ No./Year, Tags @ 465000 No./Year, Polybag @750000 No./year,Thread @ 340000 No./Year, Corrugated Boxes @ 80000No./Year

Products (Name with quantity per day) Garments Production & Washing @ 10,000 Nos./day

By-Products, if any,(Name with quantity per day) Nil

Details of the machinary and processes Fabric Receiving & Checking-> Cutting & Stickering ->Stitching & 1st Cheking -> Kaj & Buttoning -> ThreadCutting -> Washing Process-> Pressing & Final Checking -> Tagging & Packing -> Ready to Dispatch.

Details of the Effluent Treatment Plant Trade Effluent @ 140 KLDDomestic Effluent @ 25.0 KLD

Mode of Disposal Trade Effluent into Sewer after ETPDomestic Effluent into sewer

Standards to be achieved under Water(Prevention &Control of Pollution) Act, 1974

As Prescribed by the Board.

Environmental EngineerFor & on behalf

of

(Punjab Pollution Control Board)

Environmental EngineerFor & on behalf

of

(Punjab Pollution Control Board)

107

“This is computer generated document from OCMMS by PPCB”

Nahar industrial enterprises ltd. (garment unit), leased to cotton county retail ltd. ,Focal point, phase iv, ludhiana-i,Jagroan,Ludhiana i,141010

Page3

TERMS AND CONDITIONS

A. GENERAL CONDITIONS

1. This consent is not valid for getting power load from the Punjab State Power Corporation Limited or forgetting loan from the financial institutions.

2. The industry shall apply for renewal/further extension in validity of consent atleast two months beforeexpiry of the consent.

3. The industry shall ensure that the effluent discharging through the authorized outlet shall confirm to theprescribed standards as applicable from time to time.

4. The industry shall plant minimum of three suitable varieties of trees at the density of not less than 1000 treesper hectare all along the boundary of the industrial premises.

5. The achievement of the adequacy and efficiency of the effluent treatment plant/pollution control devices/re-circulation system installed shall be the entire responsibility of the industry.

6. The industry shall ensure that the Hazardous Wastes generated from the premises are handled as per theprovisions of the Hazardous Wastes(Management, Handling and Trans boundary Movement) Rules, 2008 asamended time to time , without any adverse effect on the environment, in any manner

7. The responsibility to monitor the effluent discharged from the authorized outlet and to maintain a record ofthe same rests with the industry. The Board shall only test check the accuracy of these reports for which theindustry shall deposit the samples collection and testing fee with the Board as and when required.

8. The industry shall submit balance sheet of every financial year to the concerned Regional Office by 30thJune of every year.

9. The industry shall submit a yearly certificate to the effect that no addition/up-gradation/ modification/modernization has been carried out during the previous year otherwise the industry shall apply for the variedconsent.

10. During the period beginning from the date of issuance and the date of expiration of this consent, theapplicant shall not discharge floating solids or visible foam.

11. Any amendments/revisions made by the Board in the tolerance limits for discharges shall be applicable tothe industry from the date of such amendments/revisions.

12. The industry shall not change or alter the manufacturing process(es) so as to change the quality and/orquantity of the effluents generated without the written permission of the Board.

13. Any upset conditions in the plant/plants of the factory, which is likely to result in increased effluent and/orresult in violation of the standards lay down by the Board shall be reported to the Environmental Engineer,Punjab Pollution Control Board of concerned Regional Office immediately failing which any stoppage andupset conditions that come to the notice of the Board/its officers, will be deemed to be intentional violationof the conditions of consent.

14. The industry shall provide terminal manhole(s) at the end of each collection system and a manhole upstreamof final outlet (s) out of the premises of the industry for measurement of flow and for taking samples.

15. The industry shall for the purpose of measuring and recording the quantity of water consumed and effluentdischarged, affix meters of such standards and at such places as approved by the Environmental Engineer,Punjab Pollution Control Board of the concerned Regional Office.

16. The industry shall maintain record regarding the operation of effluent treatment plant i.e. record of quantityof chemicals and energy utilized for treatment and sludge generated from treatment so as to satisfy theBoard regarding regular and proper operation of pollution control equipment.

17. The industry shall provide online monitoring equipment’s for the parameters as decided by concernedRegional Office with the effluent treatment plant/air pollution control devices installed, if applicable.

18. The pollution control devices shall be interlocked with the manufacturing process of the industry.

19. The authorized outlet and mode of disposal shall not be changed without the prior written permission of theBoard.

20. The industry shall comply with the conditions imposed by the SEIAA / MOEF in the environmentalclearance granted to it as required under EIA notification dated14/9/06, if applicable.

21. The industry shall obtain and submit Insurance cover as required under the Public Liability Insurance Act,1991.

22. The industry shall not use any unauthorized out-let(s) for discharging effluents from its premises. Allunauthorized outlets, if any, shall be connected to the authorized outlet within one month from the date ofissue of this consent.

108

“This is computer generated document from OCMMS by PPCB”

Nahar industrial enterprises ltd. (garment unit), leased to cotton county retail ltd. ,Focal point, phase iv, ludhiana-i,Jagroan,Ludhiana i,141010

Page4

23. The industry shall make necessary arrangements for the monitoring of effluent being discharged by theindustry and shall monitor its effluents:-

(i) Once in Year for Small Scale Industries.

(ii) Four in a Year for Large/Medium Scale Industries.

(iii) The industry will submit monthly reading/ data of the separate energy meter installed for runningof effluent treatment plant/re-circulation system to the concerned Regional Office of the Boardby the 5th of the following month.

24. The industry shall provide electromagnetic flow meters at the source of water supply, at inlet/outlet ofeffluent treatment plant within one month and shall maintain the record of the daily reading and submit thesame to the concerned Regional Office by the 5th of the following month.

25. The Board reserves the right to revoke this consent at any time in case the industry is found violating any ofthe conditions of this consent and/or the provisions of Water (Prevention & Control of Pollution) Act, 1974as amended from time to time.

26. The issuance of this consent does not convey any property right in either real or personal property, or anyexclusive privileges, nor does it authorize any injury to private property or any invasion of personal rights,nor any infringement of Central, State or Local Laws or Regulations.

27. The consent does not authorize or approve the construction of any physical structures or facilities forundertaking of any work in any natural watercourse.

28. Nothing in this consent shall be deemed to neither preclude the institution of any legal action nor relieve theapplicant from any responsibilities, liabilities or penalties to which the applicant is or may be subjectedunder this or any other Act.

29. The industry shall make necessary and adequate arrangements to hold back the effluent in case of failure ofseptic tank.

30. The diversion or bye pass of any discharge from facilities utilized by the applicant to maintain compliancewith the terms and conditions of this consent is prohibited except.

(i) Where unavoidable to prevent loss of life or some property damage or

(ii) Where excessive storm drainage or run off would damage facilities necessary for compliancewith terms and conditions of this consent. The applicant shall immediately notify the consentissuing authority in writing of each such diversion or bye-pass.

31. The industry shall ensure that no water pollution problem is created in the area due to discharge of effluentsfrom its industrial premises.

32. The industry shall comply with the code of practice as notified by the Government/ Board for the type ofindustries where the siting guidelines/ code of practice have been notified.

33. Solids, sludge, filter backwash or other pollutant removed from or resulting from treatment or control ofwaste waters shall be disposed off in such a manner to prevent any pollutants from such materials fromentering into natural water.

34. The industry shall re-circulate the entire cooling water and shall also re-circulate/reuse to the maximumextent the treated effluent in processes

35. The industry shall make necessary and adequate arrangements to hold back the effluent in case of failure ofre-circulation system/ effluent treatment plant.

36. The industry shall make proper disposal of the effluent so as to ensure that no stagnation occurs inside andoutside the industrial premises during rainy season and no demand period.

37. Where excessive storm water drainage or run off, would damage facilities necessary for compliance withterms and conditions of this consent, the applicant shall immediately notify the consent issuing authority inwriting of each such diversion or bye-pass.

38. The industry shall submit a detailed plan showing therein the distribution system for conveying waste-waterfor application on land for irrigation along with the crop pattern for the year.

39. The industry shall ensure that the effluent discharged by it is toxicity free.

40. The industry shall not irrigate the vegetable crops with the treated effluents which are used/ consumed asraw.

41. Drains causing oil & grease contamination shall will be segregated. Oil & grease trap shall be provided torecover oil & grease from the effluent.

109

“This is computer generated document from OCMMS by PPCB”

Nahar industrial enterprises ltd. (garment unit), leased to cotton county retail ltd. ,Focal point, phase iv, ludhiana-i,Jagroan,Ludhiana i,141010

Page5

42. The industry shall establish sufficient number of piezometer wells in consultation with the concernedRegional Office, of the Board to monitor the impact on the Ground Water Quantity due to the industrialoperations, and the monitoring shall be submitted to the Environmental Engineer of the concerned RegionalOffice by the 5th of every month.

43. The industry shall ensure that its production capacity & quantity of trade effluent do not exceed the quantitymentioned in the consent and shall not carry out any expansion without the prior permission/NOC of theBoard.

Environmental EngineerFor & on behalf

of

(Punjab Pollution Control Board)

110

111

abc
Textbox
Annexure1(c)

112

abc
Textbox
Annexure 1(d)
abc
Textbox

113

114

115

116

117

118

119

120

121

122

123

124

125

126

127

128

129

130

131

132

133

134

135

136

137

138

139

140

141

142

143

144

145

146

147

148

149

150

151

152

153

154

155

156

157

158

159

160

161

“This is computer generated document from OCMMS by PPCB”

Nahar industrial enterprises ltd.(garment & regd. office) warehouse-1 ,Focal point, phase iv (i & ii), ludhiana,Ludhiana east,Ludhiana i,141010

Page1

1.Particulars of Consent to Establish (NOC) granted to the Industry

2. Particulars of the Industry

PUNJAB POLLUTION CONTROL BOARDZonal Office-1, Ludhiana

Website:- www.ppcb.gov.in

Office Dispatch No : Registered/Speed Post Date:

Industry Registration ID: O19LDH150190 Application No : 9669707

To,NAVDEEP SHARMA200-E, KITCHLU NAGARLUDHIANA,LUDHIANA-141001

Subject: Grant of ‘Consent to Establish’(NOC) for an industrial unit u/s 25 of Water (Prevention & Control ofPollution) Act, 1974 and u/s 21 of Air (Prevention & Control of Pollution) Act, 1981.

With reference to your application for obtaining fresh 'Consent to Establish'(NOC) an industrial plant u/s 25 ofWater (Prevention & Control of Pollution) Act, 1974 and u/s 21 of Air (Prevention & Control of Pollution) Act,1981, you are, hereby, permitted to establish the industrial unit to discharge the effluent(s) & emission(s) arising outof your premises subject to the Terms and Conditions as specified in this Certificate.

Certificate No. CTE/Fresh/LDH1/2019/9669707

Date of issue : 24/04/2019

Date of expiry : 23/04/2020

Certificate Type : Fresh

Name & Designation of the Applicant H.N.SINGHAL, (PRESIDENT (CORP. HR& ADMN.))

Address of Industrial premises Nahar industrial enterprises ltd.(garment &regd. office) warehouse-1 ,Focal point, phase iv (i & ii), ludhiana,Ludhiana east,Ludhiana i-141010

Capital Investment of the Industry 1401.1 lakhs

Category of Industry Orange

Type of Industry 2099-Building and construction project 20,000 sq. m built up area

Scale of the Industry Large

Office District Ludhiana i

Consent Fee Details Rs. 21600/- vide UTR NO.SBIN319081442411

Raw Materials (Name with quantity per day) Storage of goods only

Products (Name with quantity per day) Storage of goods only

By-Products, if any,(Name with quantity per day) Nil

162

“This is computer generated document from OCMMS by PPCB”

Nahar industrial enterprises ltd.(garment & regd. office) warehouse-1 ,Focal point, phase iv (i & ii), ludhiana,Ludhiana east,Ludhiana i,141010

Page2

Endst. No.: Dated:

A copy of the above is forwarded to the following for information and necessary action please:

The Environmental Engineer, Pb. Pollution Control Board, Regional Office-1, Ludhiana

Details of the machinery and processes As per application form

Details of the Effluent Treatment Plant Not required

Mode of Disposal of Effluent Only domestic effluent @ 40 KLD into sewer

Standards to be achieved under Water (Prevention & Control ofPollution) Act, 1974

As prescribed by the Board

Sources of emissions and type of pollutants 2 No. D.G. sets of capacity 250 KVA each

Mode of disposal of emissions with stack height Adequate stack height

Quantity of fuel required in TPD Diesel @ 50 ltrs/day each

Type of Air Pollution Control Devices to be installed Not Required

Standars to be achieved under Air (Prevention & Control of Pollution)Act, 1981

As prescribed by the Board

24/04/2019

( Ravinder Bhatti )Environmental Engineer

For & on behalf

of

(Punjab Pollution Control Board)

24/04/2019

( Ravinder Bhatti )Environmental Engineer

For & on behalf

of

(Punjab Pollution Control Board)

163

“This is computer generated document from OCMMS by PPCB”

Nahar industrial enterprises ltd.(garment & regd. office) warehouse-1 ,Focal point, phase iv (i & ii), ludhiana,Ludhiana east,Ludhiana i,141010

Page3

A. GENERAL CONDITIONS

1. The industry shall apply for consent of the Board as required under the provision of Water (Prevention &Control of Pollution) Act, 1974, Air (Prevention & Control of Pollution) Act, 1981 & Authorization underHazardous and other Wastes (Management and Transboundary Movement) Rules, 2016, two months beforethe commissioning of the industry.

2. The industry shall provide adequate arrangements for fighting the accidental leakages/ discharge of any airpollutant/gas/liquids from the vessels, mechanical equipments etc. which are likely to cause environmentalpollution.

3. The Industry shall apply for further extension in the validity of the CTE atleast two months before theexpiry of this CTE, if applicable.

4. The industry shall comply with any other conditions laid down or directions issued by the Board under theprovisions of the Water (Prevention & Control of Pollution) Act, 1974 and the Air (Prevention & Control ofPollution) Act,1981 from time to time.

5. The project has been approved by the Board from pollution angle and the industry shall obtain the approvalof site from other concerned departments, if need be.

6. The industry shall get its building plans approved under the provisions of section 3-A of Punjab FactoryRules, 1952.

7. The industry shall put up display board indicating the Environment data in the prescribed format at the mainentrance gate.

8. The industry shall provide port-holes, platforms and/or other necessary facilities as may be required forcollecting samples of emissions from any chimney, flue or duct or any other outlets.

Specifications of the port-holes shall be as under:-

i) The sampling ports shall be provided atleast 8 times chimney diameter downstream and 2 timesupstream from the flow disturbance. For a rectangular cross section the equivalent diameter (De)shall be calculated from the following equation to determine upstream, downstream distance:-

De = 2 LW / (L+W)

Where L= length in mts. W= Width in mts.

ii) The sampling port shall be 7 to 10 cm in diameter

9. The industry shall discharge all gases through a stack of minimum height as specified in the followingstandards laid down by the Board.

(i) Stack height for boiler plants

S.NO. Boiler with Steam GeneratingCapacity

Stack heights

1. Less than 2 ton/hr. 9 meters or 2.5 times the height of neighboring buildingwhich ever is more

2. More than 2 ton/hr. to 5 ton/hr. 12 meters

3. More than 5 ton/hr. to 10 ton/hr 15 meters

4. More than 10 ton/hr. to 15 ton/hr 18 meters

5. More than 15 ton/hr. to 20 ton/hr 21 meters

6. More than 20 ton/hr. to 25 ton/hr. 24 meters

7. More than 25 ton/hr. to 30 ton/hr. 27 meters

8. More than 30 ton/hr. 30 meters or using the formulaH = 14 Qg0.3orH = 74 (Qp)0.24Where Qg = Quantity of SO2 in Kg/hr.Qp = Quantity of particulate matter in Ton/day.

Note : Minimum Stack height in all cases shall be 9.0 mtr. or as calculated from relevant formulawhichever is more.

(ii) For industrial furnaces and kilns, the criteria for selection of stack height would be based on fuelused for the corresponding steam generation.

(iii) Stack height for diesel generating sets:

164

“This is computer generated document from OCMMS by PPCB”

Nahar industrial enterprises ltd.(garment & regd. office) warehouse-1 ,Focal point, phase iv (i & ii), ludhiana,Ludhiana east,Ludhiana i,141010

Page4

Capacity of diesel generating set Height of the Stack

0-50 KVA Height of the building + 1.5 mt

50-100 KVA -do- + 2.0 mt.

100-150 KVA -do- + 2.5 mt.

150-200 KVA -do- + 3.0 mt.

200-250 KVA -do- + 3.5 mt.

250-300 KVA -do- + 3.5 mt.

For higher KVA rating stack height H (in meter) shall be worked out according to the formula:

H = h+0.2 (KVA)0.5

where h = height of the building in meters where the generator set is installed.

10. The industry shall put up canopy on its DG sets and also provide stack of adequate height as per normsprescribed by the Board and shall ensure the compliance of instructions issued by the Board vide officeorder no. Admin./SA-2/F.No.783/2011/448 dated 8/6/2010.

11. The industry shall put up canopy on its DG sets and also provide stack of adequate height as per normsprescribed by the Board and shall ensure the compliance of instructions issued by the Board vide officeorder no. Admin./SA-2/F.No.783/2011/448 dated 8/6/2010.

(i) Once in Year for Small Scale Industries.

(ii) Four in a Year for Large/Medium Scale Industries.

(iii) The industry will submit monthly reading/ data of the separate energy meter installed for runningof effluent treatment plant/re-circulation system to the concerned Regional Office of the Boardby the 5th of the following month.

12. The industry shall provide flow meters at the source of water supply, at the outlet of effluent treatment plantand shall maintain the record of the daily reading and submit the same to the concerned Regional Office bythe 5th day of the following month.

13. The industry shall make necessary arrangements for the monitoring of stack emissions and shall get itsemissions analyzed from lab approved / authorized by the Board:-

(i) Once in Year for Small Scale Industries.

(ii) Twice/thrice/four time in a Year for Large/Medium Scale Industries.

14. The pollution control devices shall be interlocked with the manufacturing process of the industry.

15. The Board reserves the right to revoke this “consent to establish” (NOC) at any time, in case the industry isfound violating any of the conditions of this “consent to establish” and/or the provisions of Water(Prevention & Control of Pollution) Act, 1974 and Air (Prevention & Control of Pollution) Act, 1981 asamended from time to time.

16. The industry shall plant minimum of three suitable varieties of trees at the density of not less than 1000 treesper acre along the boundary of the industrial premises.

17. The issuance of this consent does not convey any property right in either real or personal property, or anyexclusive privileges, nor does it authorize any injury to private property or any invasion of personal rights,nor any infringement of Central, State or Local Laws or Regulations.

18. The consent does not authorize or approve the construction of any physical structures or facilities forundertaking of any work in any natural watercourse.

19. Nothing in this NOC shall be deemed to neither preclude the institution of any legal action nor relieve theapplicant from any responsibilities, liabilities or penalties to which the applicant is or may be subjectedunder this or any other Act.

20. The diversion or bye pass of any discharge from facilities utilized by the applicant to maintain compliancewith the terms and conditions of this consent is prohibited except.

(i) Where unavoidable to prevent loss of life or some property damage or

(ii) Where excessive storm drainage or run off would damage facilities necessary for compliancewith terms and conditions of this consent. The applicant shall immediately notify the consentissuing authority in writing of each such diversion or bye-pass.

21. The industry shall ensure that no water pollution problem is created in the area due to discharge of effluentsfrom its industrial premises.

165

“This is computer generated document from OCMMS by PPCB”

Nahar industrial enterprises ltd.(garment & regd. office) warehouse-1 ,Focal point, phase iv (i & ii), ludhiana,Ludhiana east,Ludhiana i,141010

Page5

22. The industry shall comply with the conditions imposed if any by the SEIAA/MOEF in the EnvironmentalClearance granted to it as required under EIA notification dated 14/9/06, if applicable.

23. The industry shall earmark a land within their premises for disposal of boiler ash in an environmentallysound manner, and / or the industry shall make necessary arrangements for proper disposal of fuel ash in ascientific manner and shall maintain proper record for the same, if applicable.

24. The industry shall obtain and submit Insurance cover as required under the Public Liability Insurance Act,1991.

25. The industry shall submit a site emergency plan approved by the Chief Inspector of Factories, Punjab asapplicable.

26. The industry shall provide proper and adequate air pollution control arrangements for control emission fromits coal/fuel handling area, if applicable.

27. The Industry shall comply with the code of practice as notified by the Government / Board for the type ofIndustries where the siting guidelines / code of practice have been notified

28. Solids, sludge, filter backwash or other pollutant removed from or resulting from treatment or control ofwaste waters shall be disposed off in such a manner so as to prevent any pollutants from such materials fromentering into natural water.

29. The industry shall submit a detailed plan showing therein, the distribution system for conveying waste-waters for application on land for irrigation along with the crop pattern to be adopted throughout the year.

30. The industry shall not irrigate the vegetable crops with the treated effluents which are used/ consumed asraw.

31. The industry shall ensure that its production capacity & quantity of trade effluent do not exceed the quantitymentioned in the NOC and shall not carry out any expansion without the prior permission/NOC of theBoard.

32. All amendments/revisions made by the Board in the emission/stack height standards shall be applicable tothe industry from the date of such amendments/revisions.

33. The industry shall not cause any nuisance/traffic hazard in vicinity of the area.

34. The industry shall maintain the following record to the satisfaction of the Board :-

(i) Log books for running of air pollution control devices or pumps/motors used for it.

(ii) Register showing the result of various tests conducted by the industry for monitoring of stackemissions and ambient air.

(iii) Register showing the stock of absorbents and other chemicals to be used for scrubbers.

35. The industry shall ensure that there will not be significant visible dust emissions beyond the property line.

36. The industry shall establish sufficient number of piezometer wells in consultation with the concernedRegional Office, of the Board to monitor the impact on the Ground Water Quantity due to the industrialoperations, if applicable.

37. The industry shall provide adequate and appropriate air pollution control devices to contain emissions fromhandling, transportation and processing of raw material & product of the industry

24/04/2019

( Ravinder Bhatti )Environmental Engineer

For & on behalf

of

(Punjab Pollution Control Board)

166

“This is computer generated document from OCMMS by PPCB”

Nahar industrial enterprises ltd.(garment & regd. office) warehouse-1 ,Focal point, phase iv (i & ii), ludhiana,Ludhiana east,Ludhiana i,141010

Page6

167

“This is computer generated document from OCMMS by PPCB”

Nahar industrial enterprises ltd.(garment & regd. office) warehouse-1 ,Focal point, phase iv (i & ii), ludhiana,Ludhiana east,Ludhiana i,141010

Page7

B. SPECIAL CONDITIONS

1. The industry will obtain permission from CGWA for extraction of ground water.

24/04/2019

( Ravinder Bhatti )Environmental Engineer

For & on behalf

of

(Punjab Pollution Control Board)

168

169

abc
Textbox
Annexure 2(a)

170

171

172

173

174

175

176

177

178

179

180

181

182

183

184

185

186

187

188

189

190

191

192

193

194

195

196

197

198

199

200

201

202

203

204

205

206

207

208

209

210

211

212

213

214

215

216

217

218

219

220

221

222

223

224

225

226

227

228

229

230

231

232

233

234

235

236

237

238

239

240

241

242

243

244

245

246

247

248

249

250

251

252

253

254

255

256

257

258

259

260

261

262

263

264

265

266

267

268

269

270

271

272

273

274

275

276

277

278

abc
Textbox
Annexure 2(b)

279

Scanned by CamScanner280

abc
Textbox
Annexure 3
Sachin ems
Typewritten text
Annexure 4
Sachin ems
Typewritten text
281

Start Date End Date01/10/2019 29/03/2020

0

WBS Tasks

Requ

ired

Days Start Date End

Dura

tion

(Day

s)

%

Com

plet

e

Wor

king

Da

ysDa

ys

Com

plet

eDa

ys

Rem

aini

ng

27/0

9/20

1928

/09/

2019

29/0

9/20

1930

/09/

2019

01/1

0/20

1902

/10/

2019

03/1

0/20

1904

/10/

2019

05/1

0/20

1906

/10/

2019

07/1

0/20

1908

/10/

2019

09/1

0/20

1910

/10/

2019

11/1

0/20

1912

/10/

2019

13/1

0/20

1914

/10/

2019

15/1

0/20

1916

/10/

2019

17/1

0/20

1918

/10/

2019

19/1

0/20

1920

/10/

2019

21/1

0/20

1922

/10/

2019

23/1

0/20

1924

/10/

2019

25/1

0/20

1926

/10/

2019

27/1

0/20

1928

/10/

2019

29/1

0/20

1930

/10/

2019

31/1

0/20

1901

/11/

2019

02/1

1/20

1903

/11/

2019

04/1

1/20

1905

/11/

2019

06/1

1/20

1907

/11/

2019

08/1

1/20

1909

/11/

2019

10/1

1/20

1911

/11/

2019

12/1

1/20

1913

/11/

2019

14/1

1/20

19

15/1

1/20

19

16/1

1/20

19

17/1

1/20

19

18/1

1/20

19

19/1

1/20

19

20/1

1/20

19

21/1

1/20

19

22/1

1/20

19

23/1

1/20

19

24/1

1/20

19

25/1

1/20

19

26/1

1/20

19

27/1

1/20

19

28/1

1/20

19

29/1

1/20

19

30/1

1/20

19

01/1

2/20

19

02/1

2/20

19

03/1

2/20

19

04/1

2/20

19

05/1

2/20

19

06/1

2/20

19

07/1

2/20

19

08/1

2/20

19

09/1

2/20

19

10/1

2/20

19

11/1

2/20

19

12/1

2/20

19

13/1

2/20

19

14/1

2/20

19

15/1

2/20

19

16/1

2/20

19

17/1

2/20

19

18/1

2/20

19

19/1

2/20

19

20/1

2/20

19

21/1

2/20

19

22/1

2/20

19

23/1

2/20

19

24/1

2/20

19

25/1

2/20

19

26/1

2/20

19

27/1

2/20

19

28/1

2/20

19

29/1

2/20

19

30/1

2/20

19

31/1

2/20

19

01/0

1/20

20

02/0

1/20

20

03/0

1/20

20

04/0

1/20

20

05/0

1/20

20

06/0

1/20

20

07/0

1/20

20

08/0

1/20

20

09/0

1/20

20

10/0

1/20

20

11/0

1/20

20

12/0

1/20

20

13/0

1/20

20

14/0

1/20

20

15/0

1/20

20

16/0

1/20

20

17/0

1/20

20

18/0

1/20

20

19/0

1/20

20

20/0

1/20

20

21/0

1/20

20

22/0

1/20

20

23/0

1/20

20

24/0

1/20

20

25/0

1/20

20

26/0

1/20

20

27/0

1/20

20

28/0

1/20

20

29/0

1/20

20

30/0

1/20

20

31/0

1/20

20

01/0

2/20

20

02/0

2/20

20

03/0

2/20

20

04/0

2/20

20

05/0

2/20

20

06/0

2/20

20

07/0

2/20

20

08/0

2/20

20

09/0

2/20

20

10/0

2/20

20

11/0

2/20

20

12/0

2/20

20

13/0

2/20

20

14/0

2/20

20

15/0

2/20

20

16/0

2/20

20

17/0

2/20

20

18/0

2/20

20

19/0

2/20

20

20/0

2/20

20

21/0

2/20

20

22/0

2/20

20

23/0

2/20

20

24/0

2/20

20

25/0

2/20

20

26/0

2/20

20

27/0

2/20

20

28/0

2/20

20

29/0

2/20

20

01/0

3/20

20

02/0

3/20

20

03/0

3/20

20

04/0

3/20

20

05/0

3/20

20

06/0

3/20

20

07/0

3/20

20

08/0

3/20

20

09/0

3/20

20

10/0

3/20

20

11/0

3/20

20

12/0

3/20

20

13/0

3/20

20

14/0

3/20

20

15/0

3/20

20

16/0

3/20

20

17/0

3/20

20

18/0

3/20

20

19/0

3/20

20

20/0

3/20

20

21/0

3/20

20

22/0

3/20

20

23/0

3/20

20

24/0

3/20

20

25/0

3/20

20

26/0

3/20

20

27/0

3/20

20

28/0

3/20

20

29/0

3/20

20

1 Activity 180 0% 0 0 1801.01 4 01/10/2019 05/10/2019 4 0% 4 0 41.02 4 05/10/2019 09/10/2019 4 0% 3 0 41.03 7 09/10/2019 16/10/2019 7 0% 6 0 71.04 20 16/10/2019 05/11/2019 20 0% 15 0 201.05 20 20/10/2019 09/11/2019 20 0% 15 0 201.06 90 09/10/2019 07/01/2020 90 0% 65 0 901.07 110 23/10/2019 10/02/2020 110 0% 79 0 1101.08 45 24/10/2019 08/12/2019 45 0% 32 0 451.09 25 27/10/2019 21/11/2019 25 0% 19 0 251.10 40 29/10/2019 08/12/2019 40 0% 29 0 401.11 40 02/11/2019 12/12/2019 40 0% 29 0 401.12 18 25/10/2019 12/11/2019 18 0% 13 0 181.13 60 25/10/2019 24/12/2019 60 0% 43 0 60

1.14 30 30/10/2019 29/11/2019 30 0% 23 0 30

1.15 40 04/11/2019 14/12/2019 40 0% 30 0 40

1.16 50 10/11/2019 30/12/2019 50 0% 36 0 50

1.17 35 14/11/2019 19/12/2019 35 0% 26 0 351.18 40 19/12/2019 28/01/2020 40 0% 29 0 401.19 30 13/01/2020 12/02/2020 30 0% 23 0 301.20 30 28/01/2020 27/02/2020 30 0% 23 0 301.21 60 20/11/2019 19/01/2020 60 0% 43 0 601.22 7 28/01/2020 04/02/2020 7 0% 6 0 71.23 20 28/01/2020 17/02/2020 20 0% 15 0 20

2.01 7 10/10/2019 17/10/2019 7 0% 6 0 7

2.02 20 15/10/2019 04/11/2019 20 0% 15 0 20

2.03 20 25/10/2019 14/11/2019 20 0% 15 0 202.04 22 10/11/2019 02/12/2019 22 0% 16 0 222.05 30 04/12/2019 03/01/2020 30 0% 23 0 302.06 7 12/12/2019 19/12/2019 7 0% 6 0 7

3.01 3 06/02/2019 09/02/2019 3 0% 3 0 33.02 2 09/02/2019 11/02/2019 2 0% 1 0 23.03 4 23/10/2019 27/10/2019 4 0% 3 0 43.04 4 26/10/2019 30/10/2019 4 0% 3 0 43.05 37 09/10/2019 15/11/2019 37 0% 28 0 373.06 40 26/10/2019 05/12/2019 40 0% 29 0 403.07 7 28/10/2019 04/11/2019 7 0% 6 0 73.08 4 01/11/2019 05/11/2019 4 0% 3 0 43.09 24 06/11/2019 24/11/2019 18 0% 13 0 183.10 24 06/11/2019 30/11/2019 24 0% 18 0 243.11 4 01/12/2019 05/12/2019 4 0% 4 0 43.12 1 05/12/2019 06/12/2019 1 0% 2 0 13.13 1 06/12/2019 06/12/2019 0 0% 1 0 03.14 3 11/12/2019 14/12/2019 3 0% 3 0 33.15 7 13/12/2019 20/12/2019 7 0% 6 0 73.16 14 13/12/2019 27/12/2019 14 0% 11 0 143.17 14 20/12/2019 03/01/2020 14 0% 11 0 143.18 20 29/12/2019 18/01/2020 20 0% 15 0 20

3.19 7 08/01/2020 15/01/2020 7 0% 6 0 7

3.20 6 08/01/2020 14/01/2020 6 0% 5 0 63.21 7 12/01/2020 19/01/2020 7 0% 5 0 7

4.01 10 05/11/2019 15/11/2019 10 0% 9 0 104.02 3 17/11/2019 20/11/2019 3 0% 3 0 34.03 30 21/11/2019 21/12/2019 30 0% 22 0 304.04 31 23/11/2019 24/12/2019 31 0% 22 0 314.05 32 25/11/2019 27/12/2019 32 0% 25 0 324.06 10 03/01/2020 13/01/2020 10 0% 7 0 10

4.07 7 01/10/2019 08/10/2019 7 0% 6 0 74.08 2 08/10/2019 10/10/2019 2 0% 3 0 24.09 7 10/10/2019 17/10/2019 7 0% 6 0 74.10 2 17/10/2019 19/10/2019 2 0% 2 0 24.11 2 25/02/2019 27/02/2019 2 0% 3 0 24.12 40 27/02/2019 08/04/2019 40 0% 29 0 404.13 60 08/04/2019 07/06/2019 60 0% 45 0 604.14 50 07/06/2019 27/07/2019 50 0% 36 0 504.15 60 27/07/2019 25/09/2019 60 0% 43 0 604.16 60 25/09/2019 24/11/2019 60 0% 43 0 60Final Handover

PEB PART

Anchor Bolt ApprovalGA Drawing SubmissionGA approvalAnchor Bolt DispatchBuilding DispatchErection of StructureRoof SheetingWall Cladding

Anchor Bolts Drawings, Reaction

Week-18

WBM from Flooring

Week-8 Week-9 Week-10 Week-13 Week-14 Week-15 Week-16 Week-17

Steel Binding

Site Cleaning Layout and Demarcation

Week-11 Week-12

Water Proofing

Excavation for FootingsPCC in Footings

CIVIL WORKS - TOILET AND OTHER AREAS

Casting of Plinth BeamBrick Work in Super StructureLifting of ColumnsShuttering for SlabSteel Binding for SlabCasting of SlabTile TerracePlumbing WorksElectrical WorksFixing of TilesPainting Works

Footing Casting

Layout and DemarcationMaking of Burji

Week-1 Week-2

Site Cleaning

Project Name:

CIVIL WORKS - INSIDE

Week-4 Week-5 Week-6 Week-7

Ltd. At Ludhiana

Project Time Line

Week-3

Construction of Warehouse for at Nahar Industrial Enterprises

Steel BindingShuttering for RCC Casting for RCC

Fixing of Anchor BoltsCasting of Tie Beam

Fixing of Dock BumpersElectrical Works Inside Warehouse

Back filling in Footing

Fire Fighting WorksPainting and Finishing

CIVIL WORKS - OUTSIDEExcavation for Storm Water and Sewer Lines

Brick Work from NGL to FFL

Block work from FFL to 4m height

Inside and Out Side Plaster

Casting Plinth Beam

Earth Filling and Compaction

UNDER GROUND WATER TANK

Layout, Demarcation and ExcavationPCC in Base

Laying of Sewer and Storm Water LinesMaking of Inspection PitsWBM for Outer Roads Concrete for Outer RoadBitumen for Outer Road

Trimix Flooring

Fixing of Electrical and Plumbing Fixtures

Densification for Flooring

Fixing of Doors and WindowsFinishing Works

Shuttering

Steel Binding

Excavation PCC in Footing

Shuttering for RCC worksFooting Casting

282

user
Typewriter
Annexure-5

283

abc
Textbox
Annexure 6

284

285

286

287

288

289

290

291

292

293

1

Priyanka madan

From: simran <[email protected]>Sent: Tuesday, June 11, 2019 2:35 PMTo: [email protected]; [email protected]: [email protected]: Regarding Intimation of Environmental Monitoring for Environmental Clearance

11.06.2019

To,

The Member Secretary,SEIAA/SEAC, Punjab, Directorate of Environment and Climate Change,C/o Punjab State Council for Science & Technology,MGSIPA Complex, Sector 26- Chandigarh-160019.E-mail: [email protected]; [email protected]

Subject :- Intimation of Environmental monitoring for Environmental Clearance

Sir,

As per proceedings of 6th combined meeting of SEIAA & SEAC held on 17.10.2014, it is to bring to yourkind notice that we will be undertaking sampling for Environmental Clearance on 15th June, 2019; Saturdayfor the Warehouse Project proposed at Plot No. B-3 to B-8 and A-4 at Focal Point, Ludhiana, Punjab byNahar Industrial Enterprises Ltd.

This is for your information please.

CC:Regional Office Ludhiana-2, Phase-V, Focal Point, Ludhiana, PunjabEmail: [email protected]

With Warm Regards

SIMRANJIT KAURM.Sc. | M.Phill. | Ph.D. Scholar (Solid Waste Management)Head/AGM – EMS & Biological [email protected] | +91-8872043178 | www.ecoparyavaran.org

Corporate & Head Office: ECO Bhawan, E-207, Industrial Area, Phase VIII-B, Sector-74, Mohali, Punjab-160071, Tel: 0172-4616225NCR Delhi Office: # Plot no 355, Sector 43, Near Golf Course Road , Gurgaon, Tel: 88720-43181Jammu Office: # 38, Sarwal Colony, Near Jammu Public Sr. Sec. School, Jammu- 180005, Tel: 87250-02813

294

com-ems
Typewriter
Annexure-7(a)

2

Disclaimer:This e-mail message (including any attachments) may contain confidential, legally privileged and proprietary information to Eco Group (Eco Paryavaran Engineers &Consultants Pvt. Ltd. & Eco Laboratories & Consultants Pvt. Ltd.) or any group companies of Eco Group and may also be protected by product immunity. If you have erroneouslyreceived this message, please notify the sender by return e-mail and delete this message from your system. Any unauthorized use or dissemination of this message in whole or part isstrictly prohibited. E-mail transmission cannot be guaranteed to be secure or free of errors, viruses, interceptions or interferences and Eco Group shall not be liable for any delay in itsreceipt or damage to your system or for any violation of intellectual property right of any person. Any views, opinions and other information in this message that do not relate to theofficial business of Eco Group or any of its group companies shall be understood as neither given nor endorsed by it.

295

296

com-ems
Typewriter
Annexure-7(b)

297

298

299

300

301

302

303

304

305

306

307

308

com-ems
Typewriter
Annexure-7(c)

309

310

311

312

313

314

315

316

317

318

319

320

321

322

323

Scanned by CamScanner324

abc
Textbox
Annexure 8

325

abc
Textbox
Annexure 9

6/22/2019 NOCAP-Infrastructure Application-New

cgwa-noc.gov.in/ExternalUser/InfrastructureNew/Submit.aspx 1/1

Location Details

Communication Address

Land Use Details

Water Requirement Details

De-Watering Existing

Structure

De-Watering Proposed

Structure

Breakup of Water Requirment

Water Supply Detail

Groundwater Abstraction

Structure-Existing

Groundwater Abstraction

Structure-Proposed

Other Details

Self Declaration

Attachment

Final Submit

Government of IndiaCentral Ground Water Authority (CGWA)

Ministry of Water Resources, River Development and Ganga Rejuvenation

Application for Issue of NOC to Abstract Ground Water (NOCAP)Welcome : nahar2019 Previous Login Date Time: 22/06/2019 15:12:23 PM , IP Address: 122.161.192.74 Logout

INFRASTRUCTURE USE : SUCCESSFUL SUBMISSION

Print Application

Your Application Submitted Successfully.Your Application Detail here :

Application Number : 21-4/5417/PB/INF/2019

Name of Infrastructure : WAREHOUSE PROJECT BY M/S

NAHAR INDUSTRIAL ENTERPRISES

LTD.

Submitted Date : 22/06/2019 16:52:25

Net Ground Water Requirement (m3/day): 64.50

Please note your application number for future reference.

This e-application will be Processed only After Receipt of Printed form Duly Signed by the

Applicant along with all Relevant Enclosures at the Regional Director within seven (7) days of

Uploading Completed Application Online. Please Send Your Applicaiton to Given Address

Below.

Regional Director<br />Central Ground Water Board North Western Region<br/>Bhujal

Bhawan<br/>Plot No. 3B, Sector 27-A<br/>CHANDIGARH<br/>CHANDIGARH<br/>PinCode :

160019<br/>

Note:-

a) The Processing Fee is Non-Refundable. Applicant should ensure "Check Eligibility" and

"Documents Required" before Submitting Application Online.

b) Applicant has to Submit Processing Fee of Rs 1000.00 /- (Rupees One Thousand Only) through

NON TAX RECEIPT PORTAL (https://bharatkosh.gov.in). A receipt will be generated. Please fill in the

Transaction Ref No. and Date from the receipt, in print out of application and attach receipt along with

hard copy of application.

c) Submitted Application will not be Processed till the Print Out of the Signed Complete Application is

Submitted to Regional Office.

Applicant Home Apply Feedback Change Password Profile

326

abc
Textbox
Annexure 10

1. General Information:

Water Quality: Fresh Water

Application Type Category/ Type of Application: Warehouse

(i) Name of Infrastructure: WAREHOUSE PROJECT BY M/S NAHAR INDUSTRIAL ENTERPRISES LTD.

(ii) Location Details of the Infrastructure Unit- (Attach Approved Site Plan with Location Map) ($)

Address Line 1 : PLOT NOS. B-3 TO B-8 AND A-4 AT FOCAL POINT

Address Line 2 : LUDHIANA, PUNJAB

Address Line 3 :

State: PUNJAB

District: LUDHIANA

Sub-District: Ludhiana (M Corp.) Area

Village/Town: Ludhiana (M Corp.)

Latitude: 30.530000

Longitude: 75.540000

Area Type : Notified

Area Type Category : Over Exploited

(iii) Communication Address

Address Line 1: WAREHOUSE PROJECT BY M/S NAHAR INDUSTRIAL ENTERPRISES LTD.

Address Line 2: PLOT NOS. B-3 TO B-8 AND A-4 AT FOCAL POINT

Address Line 3: LUDHIANA, PUNJAB

State: PUNJAB

District: LUDHIANA

Sub-District: Ludhiana (M Corp.) Area

Pincode: 141010

Phone Number with Area Code:

Mobile Number: 91 9888908258

Fax Number:

E-Mail: [email protected]

(iv) Type of Infrastructure : Warehouse

(v) Land Use Details of the Existing/Proposed

Land Use Details Existing (sq meter) Proposed (sq meter) Grand Total (sq meter)

Green Belt Area 0.00 11400.00 11400.00

Open Land 0.00 8938.00 8938.00

Road/ Paved Area 0.00 20854.93 20854.93

Page 1 of 622/06/2019 04:53 PM

Government of IndiaCentral Ground Water Authority (CGWA)

Ministry of Water Resources, River Development and Ganga RejuvenationApplications for Issue of NOC to Abstract Ground Water (NOCAP)

Application for Permission to Abstract Ground Water for Infrastructure Use(Application for New NOC)

Application Number : 21-4/5417/PB/INF/2019

327

Rooftop area of building/ sheds

62284.07 62284.07

Total 0.00 103477.00 103477.00

(vi) Source of Availability of Surface Water for Infrastructure Use (Submit Water Availability / Non Availability Certificate):($)

There is no rivulet exists around the industry.

(vii) Average Annual Rainfall in the Area (in mm): 680.00

(viii) Whether Ground Water Utilization for: Existing Industry

Date of Commencement Infrastructure: 16/11/1976

Date of Expansion :

2. Total Number and Type of :

a) Dwelling Units 0

b) Commercials Units 0

c) Industrial Units 0

d) Others Area = 25.57 acres

3. Details of Water Requirement (Fresh and Recycled Water Usage) (Please Enclose Water Flow Chart of Activities and Requirement of Water at each Stage)($)

(i) Total Water Requirement (a+b+c+d) (m3/day)

Existing Proposed Total

Water Requirement Details (Fresh Water) (m3/day)

(a) Ground Water Requirement (m3/day): 64.50 0.00 64.50

(b) Surface Water Available(Canal, River, Ponds etc.) (m3/day):

0.00 0.00 0.00

(c) Water Supply from Any Agency (m3/day): 0.00 0.00 0.00

Total Fresh Water Requirement (a+b+c)(m3/day):

64.50 0.00 64.50

(d) Recycled Water Usage (m3/day): 5.00 0.00 5.00

Total Water Requirement (a+b+c+d)(m3/Day):

69.50 0.00 69.50

3. (i-a) Dewatering Required, Whether the Groundwater Table will be Intersected No

(a) Depth (m bgl)

Minimum (m bgl)

Maximum (m bgl)

(b) Maximum Depth Proposed to Dewater (m bgl)

(c) Proposed Quantity of Ground Water to be Dewaterd: (m3/day)

(m3/year)

(d) Proposed Utilisation of Pumped Water($)

(e) Any Other Information

(f) Particulars (i-a) is yes (Fill details of Dewatering Existing Structures)

Number of Existing Structures 0

Page 2 of 622/06/2019 04:53 PM

Government of IndiaCentral Ground Water Authority (CGWA)

Ministry of Water Resources, River Development and Ganga RejuvenationApplications for Issue of NOC to Abstract Ground Water (NOCAP)

Application for Permission to Abstract Ground Water for Infrastructure Use(Application for New NOC)

Application Number : 21-4/5417/PB/INF/2019

328

(ii) Breakup of Water Requirement and Usage:

Activity Existing Requirement

(m3/day)

Proposed Requirement

(m3/day)

Total Requirement

(m3/day)

No. of Operational

Days in a Year

Annual Requirement

(m3/year)

Residential/Domestic 4.00 0.00 4.00 360 1440.00

Commercial Activity 0.00 0.00 0.00 360 0.00

Industrial Activity 0.00 0.00 0.00 360 0.00

Greenbelt Development /Environment Maintenance

63.00 0.00 63.00 360 22680.00

Other Use 2.50 0.00 2.50 360 900.00

Grand Total 69.50 0.00 69.50 25020.00

SNo. Type of Structure

Name / Year of

Construction

Depth(Meter)

/Diameter

(mm)

Depthto

WaterLevel

(Metersbelow

Ground Level)

Discharge (m3/Hour)

Operational Hours

(day) / days(year)

Mode of

Lift Name

Horse Power

of Pump

Whether fitted with

Water Meter

Whether Permission Registered

with CGWA / If so

Details Thereof

(g) Particulars (i-a) is yes (Fill details of Dewatering Proposed Structures)

Number of Proposed Structures 0

SNo. Type of Structure

Name / Year of

Construction

Depth(Meter)/

Diameter(mm)

Depthto

WaterLevel

(Metersbelow

Ground Level)

Discharge (m3/Hour)

Operational

Hours(day) / days(year)

Mode of

Lift Name

Horse Power

of Pump

Whether fitted with

Water Meter

Whether Permission Registered

with CGWA / If so

Details Thereof

(iii) Whether ETP/STP Proposed, if so furnish following details: Yes

Breakup of Recycled Water Usage (m3/day) (Days) (m3/year)

a) Total Waste Water Generated: 5.50 360 1980.00

b) Quantity of Treated Water Available : 5.00

(i) Reuse in Commercial Activity: 0.00 360 0.00

(ii) Reuse in Industrial Activity 0.00 360 0.00

(iii) Reuse in Greenbelt Development :

2.50 360 900.00

(iv) Other Uses 2.50 360 900.00

c) Total Treated Water Utilised: 5.00 1800.00

Net Ground Water Requirement : 64.50 (m3/day)

Page 3 of 622/06/2019 04:53 PM

Government of IndiaCentral Ground Water Authority (CGWA)

Ministry of Water Resources, River Development and Ganga RejuvenationApplications for Issue of NOC to Abstract Ground Water (NOCAP)

Application for Permission to Abstract Ground Water for Infrastructure Use(Application for New NOC)

Application Number : 21-4/5417/PB/INF/2019

329

6. (a) Groundwater Abstraction Structure- Existing

Number of Existing Structures: 1

SNo. Type of Structure

Name / Year of

Construction

Depth(Meter)

/Diameter

(mm)

Depthto

WaterLevel

(Metersbelow

Ground Level)

Discharge

(m3/Hour)

Operational Hours(Day) / Days(Year)

Mode of

Lift Name

Horse Power

of Pump

Whether fitted with

Water Meter

Whether Permission Registered

with CGWA / If so

Details Thereof

1 Borewell / 1976

85.00 / 203

37.00 30.00 6 / 360 Submersible Pump

20.00 Yes No / -

(b) Groundwater Abstraction Structure- Proposed

Number of Proposed Structures: 0

SNo. Type of StructureName / Year of

Construction

Depth (Meter)

/ Diameter

(mm)

Depthto

WaterLevel

(Metersbelow

Ground Level)

Discharge

(m3/Hour)

Operational

Hours(Day) /

Days(Year)

Mode of

Lift Name

Horse Power

of Pump

Whether fitted with

Water Meter

Whether PermissionRegistered

with CGWA / If

so Details Thereof

7. Groundwater Availability (Please Enclose a Comprehensive Report / Note on Groundwater Condition in and Around the Area) Applicable to Industries Consuming Greater Than 500 m3/day : ($)

Not applicable as the ground water withdrawal is less than 500 KLD.

8. Details of Rainwater Harvesting / Artificial Recharge Measures for Groundwater Recharge in the Area. If already Implemented, details may be Furnished. (Attach Report on Comprehensive & Feasible Rainwater Harvesting / Recharge Proposal).- ($)

Detailed rainwater recharging plan is attached with the application.

9. Approval Letter of State Goverment Agency Approving the Infrastructure Development

CLU has been obtained from Competent Authority.

10. Consent to Operate / Estibilish / Approval Letter from Statutory Bodies viz Ministry of Environment & Forests(MoEF) or State Pollution Control Board(SPCB) or State Level Expert Appraisal Committee(SEAC) or State Level Environment Impact Assessment Authority(SLEIAA):($)

Attached Consent/ Approval of Government Agency (Previous:Referral Letter)

Letter Number Application has been filled for Environment Clearance.

Sr.No.

Attached Referral Letter Attachment Name File Name

1 Other State Agency CLU from General manager Industries

CLU from General manager Industries.pdf

4. Whether Local Goverment Water Supply Network Exists in the Area, if yes, provide details.($)

No

5. (i) Water Supply Application Status Applied

(ii) Water Supply Agency Goverment

a) Whether Water Supply Committed No

b) Whether Water Supply Denied No

Page 4 of 622/06/2019 04:53 PM

Government of IndiaCentral Ground Water Authority (CGWA)

Ministry of Water Resources, River Development and Ganga RejuvenationApplications for Issue of NOC to Abstract Ground Water (NOCAP)

Application for Permission to Abstract Ground Water for Infrastructure Use(Application for New NOC)

Application Number : 21-4/5417/PB/INF/2019

330

11. Have you Applied Earlier for Groundwater Clearance Permission from CGWA / State Government Agency:

If Yes, so Details thereof with Status:

INFRASTRUCTURE USE- Self Declaration

It is to certify that no case related to ground water withdrawal/ contamination is pending against the industry/ project/ unit as on date. Any such case filed against the company/ project/ unit in respect of ground water withdrawal/ contamination during the pendency of this application shall be immediately brought to the notice of CGWA.It is to Certify that the Data and Information Furnished Above are True to the Best of My Knowledge and Belief and I am Aware that if any Part of the Data / Information Submitted is Found to be False or Misleading at any Stage the Application will be Rejected Out Rightly.

1. Application Proforma is Subject to Modification from Time to Time.

2. Application should be Submitted to Regional Office.

Regional Director,Central Ground Water Board North Western Region, Bhujal Bhawan, Plot No. 3B, Sector 27-A, CHANDIGARH, CHANDIGARH, 160019

3. Incomplete Application will be Summarily Rejected.

Submitted Application will not be Processed till the Print Out of the Signed Complete Application is Submitted to Regional Office.

4. Applicant has to Submit Processing Fee of Rs. 1000.00/- (Rupees One Thousand Only) through NON TAX RECEIPT PORTAL (https://bharatkosh.gov.in). A receipt will be generated. Please fill in the Transaction Ref No. and Date from the receipt, in print out of application and attach receipt along with hard copy of application.

Bharatkosh Details:-

Transaction Ref Number:-

Dated:-

Note:- The Processing Fee is Non-Refundable. Applicant should ensure and Check Eligibility of Submission of Application and Required Documents before Submitting Online Application.

S.No Attachment Name File Name

1 Layout plan Layout plan.pdf

2). Location Map : (Refer: 1 (ii))

Attached Files:

1). Site Plan with Location Map (Previous:Site Plan) : (Refer: 1 (ii))

3). Documents of Ownership / Lease : (Refer: 1 (v))

4). Source Water Availability/Non-availability Certificate(Previous:Source of Availability of Surface Water) : (Refer: 1 (vi))

5). Water Balance Flow Chart(Previous:Water Requirement - Flow Chart of Activity and Requirement) : (Refer: 3)

S.No Attachment Name File Name

1 Location plan Location plan.pdf

No Attachment Found!

S.No Attachment Name File Name

1 Undertaking Undertaking.pdf

Page 5 of 622/06/2019 04:53 PM

Government of IndiaCentral Ground Water Authority (CGWA)

Ministry of Water Resources, River Development and Ganga RejuvenationApplications for Issue of NOC to Abstract Ground Water (NOCAP)

Application for Permission to Abstract Ground Water for Infrastructure Use(Application for New NOC)

Application Number : 21-4/5417/PB/INF/2019

331

6). Hydrogeological Report (Previous:Groundwater Availability Report) : (Refer: 7)

7). Rain Water Harvesting/Artificial Recharge proposal (Previous:Rainwater Harvesting / Artificial Recharge Measures) : (Refer: 8)

8). Authorization Letter (Previous:Authorization) :

12). Extra Attachment :

S.No Attachment Name File Name

1 Water requirement Water requirement.pdf

2 Water flow chart Water flow chart.pdf

S.No Attachment Name File Name

1 Not applicable Not applicable.pdf

S.No Attachment Name File Name

1 Rain water recharging proposal Rain water recharging proposal.pdf

2 Services plan showing recharge pits D-5 Service Plan.pdf

S.No Attachment Name File Name

1 Resolution Resolution.pdf

S.No Attachment Name File Name

1 Land Allotment documents Land Allotment documents.pdf

9). Approval Letter of State Government Agency : (Refer 9)

No Attachment Found!

Date : Name & Signature of the applicant

Place : (With official seal)

Associated User : nahar2019

Submitted By User : nahar2019

Submission Date : 22/06/2019

* In case signed by any authorized signatory, the details of the signatory with the authorization shall be enclosed.

------------------------------------------------------------------------------------------------------------------------------------------

11). Scanned Infrastructure Application :

No Attachment Found!

10). Ground Water Quality :

S.No Attachment Name File Name

1 Test Reports Test Reports.pdf

Page 6 of 622/06/2019 04:53 PM

Government of IndiaCentral Ground Water Authority (CGWA)

Ministry of Water Resources, River Development and Ganga RejuvenationApplications for Issue of NOC to Abstract Ground Water (NOCAP)

Application for Permission to Abstract Ground Water for Infrastructure Use(Application for New NOC)

Application Number : 21-4/5417/PB/INF/2019

332

Quantification of Energy saved for Warehouse Project

By M/s Nahar Industrial Enterprises Ltd.

LEDs have been proposed to be used instead of CFLs. 13.6 KW of energy will be saved

by using LEDs.

Calculations are as follows:

In Warehouse Project, approx. 1700 bulbs will be used

CFL: 15 Watt * 1700 bulbs = 25,500 Watts

LED: 7 Watt * 1700 bulbs = 11,900 Watts

Energy consumption by using CFLs = 25.5 KW

Energy consumption by using LEDs = 11.9 KW

Net energy saved = 25.5-11.9= 13.6 KW

SOLAR PANEL INSTALLATION

Roof top area = 66,184.07 m2

Space available for solar panel = 33,092.035 m2

Area Req. per K.W = 12 m2

Solar Power Generated = 2,757 KW

Cost approx. Rs. 80,000 per KW

Total Cost approx. = Rs. 22.05 Crores

333

abc
Textbox
Annexure 11

Site Photographs

334

abc
Textbox
Annexure 12

335

336

Sachin ems
Typewritten text
Annexure 13(a)
Sachin ems
Typewritten text
337
Sachin ems
Typewritten text
338
Sachin ems
Typewritten text
339
Sachin ems
Typewritten text
Annexure 13(b)
Sachin ems
Typewritten text
340

Map of Warehouse Project Plot No.B-3 to B-8 and A-4, Focal Point, Ludhiana-141010, Punjab±

LEGEND500 Mtrs Buffer From SiteProject Site

0 180 360 54090Meters

1 centimeter = 86 meters

Upper India Steel Mfg. & Engg.Co Ltd. Focal Point,Phase IV Ludhiana

Vardhman Special Steel :-Focal Point, Phase V, Ludhiana

Main Focal Point Road

Jeevan

Naga

r Roa

d

337

abc
Textbox
Drawing 1
user
Typewriter
A
user
Typewriter
A:30°52'59.55"N, 75°54'09.72"E
user
Typewriter
B:30°52'53.74"N, 75°54'20.69"E
user
Typewriter
B
user
Typewriter
C
user
Typewriter
D
user
Typewriter
E
user
Typewriter
F
user
Typewriter
G
user
Typewriter
H
user
Typewriter
I
user
Typewriter
J
user
Typewriter
K
user
Typewriter
L
user
Typewriter
C:30°52'54.36"N, 75°54'21.39"E
user
Typewriter
D:30°52'53.24"N, 75°54'23.70"E
user
Typewriter
E:30°52'53.76"N, 75°54'24.01"E
user
Typewriter
F:30°52'53.48"N, 75°54'24.87"E
user
Typewriter
G:30°53'02.41"N, 75°54'27.79"E
user
Typewriter
H:30°53'07.09"N, 75°54'21.07"E
user
Typewriter
I:30°53'06.50"N, 75°54'20.34"E
user
Typewriter
J:30°53'06.84"N, 75°54'19.10"E
user
Typewriter
K:30°53'01.09"N, 75°54'15.05"E
user
Typewriter
L:30°53'03.02"N, 75°54'12.04"E
Sachin ems
Textbox
341

338

abc
Textbox
Drawing 2 (a)
Sachin ems
Textbox
342

339

Sachin ems
Textbox
343

340

abc
Textbox
Drawing 3
abc
Textbox
Sachin ems
Textbox
344

341

abc
Textbox
Drawing 4
abc
Rectangle
abc
Rectangle
abc
Rectangle
abc
Rectangle
abc
Textbox
Solid waste segregation area
abc
Textbox
abc
Textbox
First aid room
abc
Textbox
Sachin ems
Textbox
345

342

abc
Textbox
abc
Textbox
Drawing 5
abc
Oval
abc
Oval
abc
Oval
abc
Rectangle
abc
Rectangle
abc
Arrow
abc
Textbox
Transformer and DG
abc
Rectangle
abc
Rectangle
abc
Rectangle
abc
Rectangle
abc
Oval
abc
Textbox
Solid waste segregation area
abc
Textbox
First Aid room
abc
Textbox
Borewell
abc
Textbox
abc
Rectangle
abc
Textbox
STP
Sachin ems
Textbox
346

343

abc
Textbox
Drawing 6
Sachin ems
Textbox
347

344

abc
Textbox
Drawing 7
Sachin ems
Textbox
348

345

abc
Textbox
Drawing 8
Sachin ems
Textbox
349

346

abc
Textbox
Drawing 9
Sachin ems
Textbox
350

G.Lvl.

BACKWASH WATER TO

COLLECTION TANK

FILTRATE WATER TO COLLECTION TANK

AB

SEWAGE

INLET

SKID MOUNTED UNIT ON MBBR TECHNOLOGY

PSF ACF

P3

1 2

3

4 56

9

FBS

HD

S

SKID MOUNTED UNIT

TSMMBBM

AIR PURGING GRID

7 8

TO IRRIGATION

MBBM

4

P3P2

AB

AIR PURGING GRID

CD

FMAD

9 9

HDPE

347

abc
Textbox
Drawing 10
Sachin ems
Textbox
351

Scanned by CamScanner

Sachin ems
Typewritten text
Drawing 11
Sachin ems
Typewritten text
Drawing 12