Development of Nuclear Safety Technology - OSTI.GOV
-
Upload
khangminh22 -
Category
Documents
-
view
2 -
download
0
Transcript of Development of Nuclear Safety Technology - OSTI.GOV
KINS/RR-304
emg yg flXfl71# 7H^
Development of Nuclear Safety Technology
sstiHi flxipie nmDevelopment of Regulatory Techniques for Operational
Performance Evaluation of Nuclear Power Plants
yy ann ss «hs %
as m*\
2005. 3
*11
^ SJIAiS ^Aj|7|# 7H^” jZ^I # Al|“H^i|o|
-y^ S7|- i?Al|7|# 7H W S| Ai|ti o|g AIZ|c ^7i|x|
§ @A| S-Ajoll ^*113 SJIAiS Ai|#fl-u|cL
'ss yu| gg
yy tiHS si 3
2005ti 3 3
: yAj-aoi-yyzji^
: 3 s y
^£^3*1- : y 711 #
y 0^ y ^ §j : 0| y ^
i
O ot
I. 41 4
44 44E 444 ## 44 # ## ^4 £-#
II. 7H#S| * 1°^
44 44E #444 (SDP)-B- 44 NRC7> 4Af^c^i 444#4 4#4444 44e (#^_4 4E)# 44# 44-4-b 4444E 44#44 2.E/7}e 4# 4# #4 444 4#e 4E4 441 444 444E#- #4# #7l 4% 44e5zl444-- SDP 4^# 44l7>44 E#- #4 Ef#4 441 44 44-4-4 441 4444 #444 4 5141 4441, 4444 44 NRC 44 4 E4 441444141 4#e 4E# #44 441 44444 441 # 4 441 44 4 #44- SDP# 47>4 44 444 444 44 4444-
o NRC 44^.4444 (ROP) 43144 SDP# 44 #4444 44 444 #P_ E# 47>44 4# 4 El- 4444-
o SDP4 44 #4444 444 4447} 4 #4444 44 4## 4#44- o SDP4 4A} #^-<44^ eliaf #-§-# 4 4E# #4E E-f} #eh JI# (risk
insight) #E# 4A}# oil Tfl 4444-o SDP4 44 #4444 E#4-4 44a}# a}#a} 444 4## 444 4#
44(4#)# #14# 4 44-
444 SDP# 44 tifl# 4 44# ea}43l n 44 44# 44# #4 #444 4# 44 a}## Jl### 44 4^^ 444^4 #4 4^?}2.E #E# 444-31# 444-
III. 4 #4114 MIS ^ 44
44 NRC4a) a}#-#37 #-4 44E ## 444 #Ea#E# 4# #444-4 #4 444 #444 444 s#44 s#4# 4^4# ## ### 444444-
444 2 SDP 444 4-8-4# 4# 4444 44 4#4 ## 44# 42a 424 4% #414# sdp 44 4*34 yy y#yy ^^7} 44. s. y^yA^y y# nrc 4 °4J #^# 243. 44 sdp #44 y# nW4 #4* 4442 44 4###42424- 4^4- 4)4422# 444 44 44# 4442 ### 4444 #2 a.444## 4442^ 47>4#4 &# o] #444 2# #4 44 #41444 44 4 2# #22 44 244 4444# 4^4^24 44 (#4 44) 44 #4 2 4#4^ 4.
IV. 44711444 m *#ol| me S4
444 sdp 4l27> 24# 7}44 44# 444, sdp 4 444 #44 #41# 4# 4444 24444 442 4444- 4 244-44# 4444 44 7ie# 4442 444 ## 44# 4#4 44 4(threshold)# 444# 44 #444- sdp 4 #44 44 444 4444# #4 44-4 sdp 44#4 4444# 44 #4444 42/ 4424 22114 7B44 7j#4 2#* # 444-
iv
SUMMARYI . Project Title
Background and procedure analysis for threshold of safety significance determination
II. Objective and Importance of the Project
The safety significance determination process (SDP) is a regulatory program
which gives an emphasis to the real insights gained from risk information rather than
to the assurance of as-stated deterministic codes and standards; it has been used in
the NEC's inspection for the purpose of determining the risk significance against
potential findings. The implementation of SDP can help us to improve the regulatory
effectiveness when it is intensively used in the high resource-demanding affairs, for
which may be able easily to make a risk-informed decision to an inspector or a
regulatory staff. The further consequences of SDP are outlined as follows:
o In the implementation of well-known new regulatory system, i.e. Reactor
Oversight Process, it provides us with a measure of evaluation regarding the
safety significance.
o It provides a rationale for a regulator whose actions and in-time evaluations are
required in association with inspector's findings,
o It gives the inspector some information gained from risk insights so as to utilize
during the inspection.
o It can make an open-room for negotiation and a common language used by both
the regulator and the licensee, including the stakeholders.
Therefore, it would be urgent and necessary for establishing our own effective
regulatory system that the survey and the research for the background of threshold of
SDP, including the procedure for its determination, should be done by us.
v
III. Scope and Contents of the Project
The SDP, being applied by USNRC, is one of regulatory approaches which can
improve the regulatory effectiveness and efficiency by utilizing the risk information to
any regulatory inspections and issue resolution. The decision-making criteria and some
risk thresholds for the determination of significance can be, therefore, essential
elements in actual SDP implementation. Based on USNRC's experiences, this study has
the purpose to identify the rationale and background for the determination of
significance and to check the feasibility of the implementation to Korean nuclear
power plants. Our attentions have been basically concentrated on establishing its
step-by-step processes, identifying the current issues, and assessing major issues for
the application to domestic plants. Practically, two examples have been analyzed after
consulting the database on our actual regulatory inspections and incidents.
IV. Results and Recommendations for Application
Regardless of our current non-preparation of SDP, we are sure that the
regulatory matters relevant to the SDP be seriously considered at present, which
includes major two tasks both for preparing a decision-making criteria and for
establishing some risk thresholds for the determination of significance. Some resolution
for issues, identified through establishing process of each phase of SDP, would give a
technical support to enhance the domestic regulatory inspections and/or formal
incident/accident survey program.
VI
x}
..................................................................................... :............... iA}................................................................................................................................................. vii
1. >| ^.................................................................................................. 12. till ^ .............................................................................................................................................. 2
3. tfl# ^ ti-O): ........................................................................................................... 4
4 ol^S^x}..................................................................................................... 10
5. tiR NRC^l SDP ^ ..........................................17
6. ^-g- ^3) 7flo>..........................................................................................................................20
7. ^.Sl . 22
8. ^ A}^ 27
9- a>^1.....................................................................................................30
10. ##....................................................................................................................... 31
#31^%.................................................................................................... .................. 31
1. S7lA}^^ 7)1^ Sjl .........................................................37
2. h|5^ Farley SDP Worksheet...........................................................51
#-# #4^ 4#i4 #4 44 ^ #4 #4
1. 4#
#4 ### 441-2.## #4# 425- #23 Wi#-# #7144 #4471
4 4 #4 ## # #2 44 44 (significance determination process: SDP)# ^25.
2000# 4 #4 4# NRC# 44 #24#4. SDP# iMl 7144 ^A}x}ofl #4 ##4 7jA> (inspection finding - 5# 444 A)# 25 4 A} 4 4 A} 4 4-2
424#o]l 444# ##4# ## 447} 4# cfSES 4# 2143 24#)# Z7M ## 4244, 4 44 #4444 2#4# 44 4 444 44(performance deficiency) 4 44 ##4 4 #44-23 44 444 4—3 #7}#244##4 44# 444# 4444. 4, sdp# 44 #4444 #444 444 (##4 #2)5 #44# #444 7|#4 #44 4# ## 444 444 24# ## 444 4#2 4#4 44 44# st4ft #4 7^4 #44# #4 444# nrc 444 ## 44-2-44 44 44#4# #4 44 711 #4 44 #7>4#o]4- # # #4. sdp4 #4# 4#4 #4 #4# 4 44.
• nrc 443.444# (ROP) 4 3H4 44 #4444 4# 444 #225 #7>47l 4# 43# 4 #44.
• 444# 244 44 444##4] 4-7H4# 4# ##24 44 444, ### #4444 7]e# 4444.
• #7} #4444 444 44# 7} # #4544 44 44# 4# #4.• 44 ##44 #23# ### 4 #2# ##2 2# #23 2# (risk
insight) #2# 44-44 4 4444-
44 NRC4 ROP iSEli 444# 2# #4 442>1 4# 442 #444# # 2tfl3 4234 444# 441423 4#42 47>44. ##
#4423 ROP 23244 22 # 44# 7]4 #71144 (baseline inspection)0!!4### 4#, 4 #43 #44 44# (2# 7)42 444)# 4444# 4##
1
SDP5 4 A}Sl^lsM #7} # 443## *#* #*44 [1]. 4,
#4444 #45# ### *443 #aa #4 4444 #4# 4#4# e)aa 43 ## 45#4# 7] 445 711^014.
#43 5]i3 #7}# 4## 7}^4o] #43 4444 44 44441:4 44 W44# #444. # 44 47}44# 35 #aa*4 ##7}# 444444 4444 447} 3### 44 *7}4# ##|a4## 44444
444 44 44# 4 44 44.
43a 443 44W4444# 4445 A}a*4# 444 4444
A}a*4# 4-8-44, 444 44 #4444 444# 444# #443444# 454 #44 (operability) 4 #7} 444 7] #4 4 4( functionalcapability)°1 44. SDP5 43a 437} 4|#|4#3, 44444 4444 4433 4## * 4## 34#4. 34 4# 44414171) 444711 44 #444# 444435 4# 444 *#144# 4444. 4433# A]|a# 444 44 44## #444443 47} 4444# #4 444 7)4# 4444.
2. 44
NRC4 199044) #7H 4# 44 #44 3# #47} 4#A}ofl ##) A]] a# #3a43 ## #4 #544 (ROP)# 4#4#4. 34 4# 47}* 4# 444 444 4# rop# 37] 4# a## 4#4#4. rop 4 44444 sdp# #4* a# 2-14M a### 4444# 414433# # * #4. a# 2-144 35# rop 33asdp4 pi (4 #43)4 #4 5# *433#*S44, 35 44 33a4## 4##a #* 7]#33 4# 3#4# # 44443# 5# #44# # * #4.
NRC5 ROP A]tis|7} 44# 54433 47}, 3#4a ### 44# 444#447) 44# 4# 33a®§ 4 7}4 44 (PPEP: Pilot Program Evaluation Panel)#
2
3-2. ^7lA>5, ^ tio^ cornerstone4# lM SDP (1/3)
LER tiS ( gxfSJlA) tiS ( )
(1) 52 7H2. (tiS):
1-1 ufoi-Ej ^yoi| o|S|j x-jgg AIM
1-2 g-g-g ^goii g# xigg 2!ti
1-3 2IS EE-^ 21 tig 7|M 7|^
1-4 2I5 Etg 2iti-l ct-g tiS7H
1-5 Stilus W:
1-6 ggg 525| *ig 7|g ( )W ( ) A|y
(2) x)#g 7|-^ ti Cornerstone §3:
2-1 i7|A^go gSARI (gx(SEBj #)
o LOCA ti 24# qiStiHgs|.g
2-2
O ^71 5z-fej g-tiAl|7H7M O #7| gtiA1|7l7M
O y§£A||CH 7M o $W/g^/x|g/y#
2-3 ptg bw
o 1X|- 2I#
o gM*H gg
o titi □(3) 71E) til) 7fe 71-5- §g:
3-1 #AHti&7M |
3-2 S2f ti@7M |
O 27H O|xro| Check Point Si§ [ j ---------> 2ti2l SDP
o VHti Check Point tiS | | H► cm EMryiy (2^)
o Check Point ti S [ | —► 1 ti-21 SDP #S.
7
#44^4. ppep4 A]ti 4-§-0^4 ^7] 4^-44# 4# 4 ^4-.• 44^ #-=■ o]S)fii 4-# 4-#4 4# 44 7fl4
• 344 SDP4414 pra #-0-4 444 nrc4 444 44 4444#444 44
• 44 4# sdp4 44 4444 44 444 4444 444 44# 44441 44444 44.
#4 PPEP7} 44 4# 44-4 4# ^4 ^jla}^-^^ 4&44 4 sdp
444 471)4 Ji-B- 444-44 444# 4^a 444 44444 444# #4 4 #451# J34F-# 444.
REACTOR OVERSIGHT PROCESSCommiaiicatfotis
Agmry ilesimise-
A^mnirnl PfOff^ill r L it ce. cc \t i(Action MWl*}I >t •» » i i
( llfal I’rjtkrlkt
Cy iMy^kyitsi *»f S^TriyJtlr.' I Ii|fwjfj>ij|i SVfiii/iraur* F~*,uftttJJioni
i iih< Imliw ifi»r tl-ir^-h t<lx
'‘-ill pi ki f i*L «' -n* i*
Performance Indicators
IVif formance Resttlfs in all T Corim$(<mt-s of SafcH>
zz-4 2-i. 444 4^a4M. #4- 44 4444 (RQP) ##£.
3
3. 44 ^ y-o>
44 44 44AS ^ r)-g-3i) 4^ 97i 44?) 4444 44[2],
- #4#4# 44-s 44 44
- MtiJ-jir 4444
- 444 44
- 444# 444- 44 4-§-
- 44?) 4# 444 44
- 44 4# 444 44
, - #44 4&
- 444 ^144, 44 4#
4 f°Hl 441 sdp# 4--B-4 44 344 44#^ #444.• 144 (Phase 1): 44 44444 444 green 4444 444
4444. 444 green 444 5. 3-144 4444 44 44 ^4# i^4444# (ccdp) i£4 acdf7> 1.0E-6 444 4^a ##4
4444.
• 244 (Phase 2): 44 44444 green 44 444 4 4444 44 44 43=: 4S 444 44444 47>44. 44 44^&4 i 3- H14 4444 44 44 white (ACDP l.OE-5 44), yellow (ACDP l.OE^t 44), red (ACDP i.OE-4 44) 7> 44. 4 4444^ 44 444 4 4 4 4444 44 #444. 44 44 444 4 44^4 4444 44.
• 344 (Phase 3): 44 44444 green M 44^-5. 444 4444-f-, 44 4^a 444 4#7)4 44 #^44. serp(Sdp &Enforcement Review Panel)?) 4 hi 4 4444-
4
#4444 4# a}#£ 433 si£014. 3# 4#oj 444 7#) £4 44 nfl^-oii oj^-ti-^-y- 7l7li-oi 444 #43 44 444 4 #3# 344#
4 44 acdf 4 ccdp 444 £4 444 4 44. 444 44 433 4£&4 ccdp7> 444 4444 44 #44 44# 444 444£3 acdf 34 4 ## 44£ 44# 444 4 44. £4 nrc# 444 4# 4 #3 sdp 444 444 ccdp 344 acdf# 4#4£# 4344.
• 44- #4444 44£# #444# sdp4 44 44# £44343(NRC action matrix) 444 44433 4444 44434 4#4344 44 444. 44344. cornerstone4 4443 4444 44 CDF #71-44 5-7144 7H#4^3£3 444 #444 sdp44£
4# 444# 44 #4.• 44 444 .444 #4# 4444 44 ccdp7> 4444# 4#
444 44 4 44 44 444 44# 44 433 4444 #44. £4 °i# 10 CFR 50.65 (4434). 34# 4#4# 4#4 4#44 4^ #444 # 41 444# #44 #44 #4 44.
• 4#44# 44# il 4 £# 4 4 #444 4#4# 4£# 433 CCDP7} A>-g-#4# A><y7> 4# #Aj# 4a>44 4414# 4# 444
444 #44 M4# 443 44 444 44 #44 %#44 44.
144 (Phase I) SDP 44# 43#33 #44 4444 #4(decision logic)# 4# 4 4 4 4 44- 3 3-2# £7l A}#, 44 41# 4 44 comers tone 4 44 1441 SDP 44 44# 4 4H 4443 3444. s. 3-244 3# 44 #4 1441 SDP 4444# Green #433 ##44 ##4714 244 SDP 44#4^444 34£ o>4y 344 sdp 44 ### 44 44# 4#4# 37>4 4#3 4444. 3 3-24 71)44444 44 #4a>#oi 4711434 44444 ^43 44, #aih#, 3£4#, £# a>#4 q43 44-34 44 4#4
44# 444#4 444 444 4# 44 433 444# 44# 4 4# ##7> 4 #s>£3 o]oi] 4-4- sdp #44 ## #7}433 7M44°} 4 433
44-44
5
sdp 4444 44 44444 453 4444 44, 44# 4 4444 444 44 #4 3444 444 44-5 444 44 444 4453 4444 244 444 444. 4 444 44 444 44 44 4444 44.
(1) 44 5:44-4 44(2) 44 #4444 4 2:444# 444 44(3) 447144 44 4444 44(4) 44 #4444 4# 4444 45. s4(5) 444 442:4 7}^4 #7}(6) 43i44# 444 45 44(7) ##4 45a. 443 44
±t 3-1. Risk Significance Based on Risk Measures
Frequency Range
(/ry)SDP based on ACDF SDP based on ALERF
> 1E-4 Red Red
< 1E-4 - 1 E-5 Yellow Red
< 1E-5 - 1E-6 White Yellow
< 1E-6 - 1 E-7 Green White
< 1 E-7 Green Green
6
00
-lx H 40 r24J2 °tryo|n o.| ± °£ H" U : s o >.iM -Li r* Id nhJioffl |
r|r V o°? 0£ > 0$02 ol M
o& K) oi i
H Jo i° Id rido|r iu c a >l
Hi mini -P- i
r2 S-
m. JS oy l-X o|r ni£r|r o|r a
"m m2 4o
Ho J2 —
3-2. 2
:7lA>y,
^
cornerstone^] 4# l^^l SD
P ## %?} (2/3)
cornerstone'll 4^" SDP tirEi yd7'} (3/3)it 3-2. 3:7lA>5, ##7## ^
xia, SM, S^, y# #011 cHtt S«7|e
1. %tg, a* (-y^y ^4) #oii ohu|5h #^#i ###aeSTIIS 7|7| EE# 7|#s| X|S)S i®5p;l?
- 7|#°| Otis x|y ^Liut, g^y-sxii #0| Sic).- y sphss-e ft# ?pi ee# 7i#°i x-h# ms sdp a^s @7)@c).
□ 2iHa, c)# 2y S# xti^
Q o)u|gt Green #3 2#
2. E.H 7171 EE# °>g7|#0| 2tgs| sgpTic) 0|###e)c)J% 7)9# S#,P# a## 0)2 gu)B)E 6HBH#H Sj-oigc).
- 2|Y-A)g ##A| 2)&)#ag ^ 7f71 EE# 7|#°| X)A|| §X|U)7|E) &7|A)g# ^ystc).
- a[YA)g y#A| g)m)#ag 7171 EE# 7|#°| xp-ti A^o c)# 7i!« o>S7t|*o| 27H 0|g°| Til'S #S# #^gc).
- 2|#Api S#A| g)A)#aa 7171 EE# 7|#S| X)*t| ### £>S7|##Aism# #2H|#°| 3#) O|yo| 7||g ^9# #S-gc).
□ rung, s3A)#e gxng°s Bi^a sasoi sic). 2# ## tsi#
□ o)u|a, Green #S a#
3. ##x)%i-o| psa EE# #x) “-xioii ggii a| “AHoi| °|a tg#g AHa^ahb|oo)| 7|o4gcH #°)@ o)g °i-g7|#°| g## 2@##7)?
□ EiiHS, aaAifs SAHS °s E|#a sa#o| sic). 2# §-# t)H
□ o)u|S, Green #S aS
1 EJ-7}| SDP##az( □ Green
^2. 7)9 A)# (S2A| 7|X||)
□ 2E)7{| SDP #§! □ SEPil SDP EH xi|g
9
4. #3# 44 44
(1) 34 44 #4:
Phase 1 Worksheet 4# #444 34 443 43 #444-° 4
4447} a### 34 44# 44 Hcensee4 44# 4# #44 34
44,° s. ###4. 34 #4444 34 43 #4 ##3#a licensee
353-4- 4444, 344444 34-°^ 4444. 4 34 #3444
4434 iL4 444 44 434 4 344 3344.
(2) 4444 44 #3:
iL4 Phase 1 Worksheet 3 3444 #4 4433 44# 4444 ##4
4 444 44 44 §14# green #4°.# #3# 4 #43 #344 (5
3-2 ##). 3444 4# Phase 1 4334 green #4°-# #3444#
Phase 2 Worksheet# 4444 34 ##44# #7}4_E# ##43. ##.
4441 #°-#4 #44 a#4 H|i3. #### ## # #4.
(3) #44 J7#4 44a 3# ## 34334 3# (Phase 2 #4)
<D 4# #3A>4 44-: 34 ##443 ### 41# # 3 3# 444a “334- 3:34444 44443# 443”# 444# #5[##4 7# ##]# 4444 44 #71434 4#4#3 4444. 3 #4 #3 #37] ##3 3 3 # H-(msiv>4 4#4 34 ##44# #3 “##3*113: 4#44” #7#}34# ##44, 7]3344 (ccw) ##4- ### 34 ##44# a# &343oil ### 344. 444# 33 3443#4 ## 34## 3444 #33##4
434# 4a#4 7)## 3 #4# 7l## #7) 3#44. 4
#5# 343343 34444 44.© 34 ##444 4 #343# #4 334 #3: 4 #343 #4
## 4t## #-## #3434 #4 334 3# (event likelihood
measure)# “34 #4# ### 4434 #34 343 3”4 #7)3
10
44 37>4 #4ss 4lzH4 #44 £11 4444 4444. #
44444 34 4 3044 4esa. 37>4 #4ss #44s 44
4444°1 4 4 4—4 #44 44444 63(coioum)4 44 4-2- £t 4 4 s344 4 4444 #(row)4 41444 4414 4 s#44441 44. (47114 4s4 44 5-44 7444 4444.) 5 4- H4# # 8 7>4 (0-7)4 4S7> S4A>y4 44 4"44#
4#ss 47144 44. 44 44 4414 £11 414 #4#4 47}4444 44444 44. 44 4A> 447>44 s4A}y4 MSlsi- #7}4444 S4a>^ 4-44 44 S4444
44. 4444 44 s4#4# ## 4444.© 4.3 4 44 4444 44: 47}4444 4 #4743 44-^
44S (worksheet) [44# 71# >W|4 44 #A> ##AH> o;^ 44#441 4# 44444 #41444 #444. 4 4454 4444444 s#4# 44slS(7}7i44)# 4444 5444.
© 47} 447}4oi] 4= 4#44 45 s4: 4A> 447^ss 4##
441 45 4 444#4 441 44 4 44 44# 47144-.444 #4 4441 44-7] 44-4^^ #44# 44## 44 ####(Remaining Matigation Capability) a] j£ 44# 714 4-1 44 71# 4-4# 5 4-24 444 #4# #ss 44 44 44# 4##471-44444 444 4|7l#4. 4714 #4 ti# 4-1 4a) h# 4-4#
#444 4#4 #4 4# #44 4# 44#4# 5 4-24 4444 (column)# S #4471 ##. #44SS #44#, 71^ 4-1# 5 4- 24 3#4, 71^ 4-2# 5 4-24 4#4, 71^ 4-3# 5 4-24 5#4 44 4444. 7i^ 4-4# 44 #44 5: 4-24 4s 44s4444 a>4# s. 4-24 444- 544 #44 444-s # # 44-. 444- 4A} ##a>4-si 44-s 4 451 S444-. ss^-#4## 4 s a) ##44-. 4s 44S4 ss##4#4 4444 4- 100%
#44 ######(MDP)# S4# 27114 44# 4#s #444
11
%144 4 £5 4-24 444 “3”4 44 44#4£ 5-4 44. 444 44= o] £ fj- Tflti o| MDP 71^4 44# 44£ 4# #44
4445344 4a 44 4^4o] 44-5)3 4^4aa# 44 444 444444 a£4£ 44aa 44 44444 5 4-24 44 “2”a
£44 444.
© £44 4£a4 44444: 44 4444, 4£#£4 #4#
4444 £444 44 £7)4:3 4444 4# 5£ 444)4 4444 £ 5344 3J444. 444££ 4aa 4444.
© 43444 44445. 44: 244444 54 444 44# #aa
44 444444 4 44 &?144 4^4444 45a. 444
45# 4444. 4 43.444 43a 444 454 £444 #4
7}£4 45, 44 4444 454 4£a4 45# a# 444
444.
(4) #44 4aa 44-a £4 (Phase 2 £4)
(3)4 4444 444 s)aa 44445 4444# £3 ##£4444
44 4££ 4£44 4£4aa 4aa 44a# £444. worksheetaa
444 £ 4# ##£4 44£ 444 44444 4£ 4a 444
457} 371)7} 44 4# 4 44 4-44 45a 4-4=44£ 4# 4444.
£, 371) 4a4 44 45# 4# s)aa 444£ 4 44 #444 (one
order risk increase) #3 a# 444- 45.4 444 457} 4 44 RED,
45 5 44 YELLOW, 45 6 44 WHITE, 3 4444 GREEN a a
4444.
4, 45 7 444 4£4a 4-7)1, 4£, ££, 44 #4 4£444 44
4aa 44# 34471 444 344 (Phase 3) 4 7}4-4# £^44.
4444 4£444 44 i£ 444 4aa #7}* 7}4# £ 44
4 £4 4.
12
it 4-1. 44 7T-y-^^5.^ SDPPhase 2 W* 7)4 44
4 2:7] A>5 2:7]a>5 ^ (PWR) S7lA>5 44AjX = -logic (IE probability)
I > 1 per 1-10 yr* Reactor Trip
(General Transient)*
0 1 2
11 1 per 10 -102 yr
** 4 7)4 4444* 4471 4444* cflS °1a># 44
1 2 3
III 1 per 102 -103 yr
* 47l 44 7] Vt-y:* RCP 44 44a)144
A>J1* Safety/Relief Valve
stuck open* 4.16 kV tatt-M 44* 125V 44S4 44* 44# 44* Til #4 #7l 44
2 3 4
IV 1 per 103 -104 yr * 44 44444 4v 3 4 5
V 1 per 104 -105 yr * #4 44^)144 42* 4444 4:e44 4 5 6
VI < 1 per 105 yr
* 414 44aH44 42.* 44 444
414444 42* 44-3.47) 44
5 6 7
> 30 4 30-3 4 <34
4444 M4 4444
13
5. 4-2. gg 44##
gy yggyg gE|| gy sg gyx = -logi o (mg##)
y 7i|S4 #7If# yy#y (1 ASD Train)-100% ### gg sss Ely f# 7|7|# itti nm- 0| 7flS# 2!*^ gx|. §1 gu| #o^ ojy # mg##e °f0.1 5. 7)#
1
# 7|-x|°| cj-yy 7{|S (2 Diverse Trains)-2tH°| yyg gy 7j|S^ fg- yaw g#gymg y-g-- o| Tjjyg mg, sj §ti| #o^ ojy # JZg-Sfg# yTIIS^I yy#ao| ti||7) £|H5. °f 0.0001 5. 7IS
4(2 + 2)
yu|-o| yg 7j|S ys|-#s| (1 Multi-Train)-2 7U oigg ci-# gs yg7|#- ysggmg- TiEi; ggxi % n Tiisoi yyy go}SIS*! HE}#x| ys.- o| Ttisg mg-, gx|. y yn| #o^ yy # Tig#me y 0.001 s. 7^g
3
y 7j|S# 9S|## (1 Train)- 100% §§§ 7|gl 0}E-| 7|7|# si® 7}|S- oi tiis —i Tig, sa|. s gui °jy § mg##e yo.oi s. 7ig
2
Tigy TIIS# ## 4# (Recovery of Failed Train)- ^7|x|.g s-g o|* mgy 7p|g #gy s|g-m*| m#- zA|# #AticHgom ygoiig sgew, zx| 7(#go| @7(go}o|: y- zA| gnn#se s o.i ^ 7fg
1
ggy^A| sg (Operator Action Credit)- y a|-tia|i_p|2.oj|a-} f gg# #a eggmg*
yg- ZA|o###0}| a(B|- 3 7p|^ e#- mgm###o| o.5 oil a) o.05 a|-o|oi g°; yg#g = 1- ZA|o##*0| 0.05 oil A.-} 0.005 A|0|y , SSfey =2- mA|m###o| 0.005 011 A-} 0.0005 A)o|S #£]■## =3
1,2, Er3
14
Table 2 Column 3
2 Trains Remaining(Both Remaining Trains are Diverse - Not Subject to CCF)
TRAIN - Remaining
TRAIN - Remaining
TRAIN - Remaining
TRAIN - Remaining
4-1. ^4-22} ^3^4 2)]# tiJl'I
Table 2 Column 4
1 Redundant (Multi-Train) System Remaining (Remaining Trains Subject to CCF)
TRAIN - Remaining
TRAIN - Remaining
OR
TRAIN - Remaining
TRAIN- Failed
TRAIN - Remaining
4-2. &4-24 ^4^4 2)]# till* 1! ^4)
15
Table 2 Column 5
1 Train Remaining(Remaining Train Not Affected by CCF)
TRAIN - Failed
TRAIN - Remaining
4-3. IL4-2-2] ^5^4 M
Table 2 Column 2
1 Redundant (Multi-Train) System + 1 Train Remaining
TRAIN - Failed - ----------
TRAIN - Remaining
TRAIN - Remaining
TRAIN - Remaining
4-4. 7] Bj- 7}^#
16
(5) LERF 4 ## 4 iE 714# 4# (Phase 2 #4)
47}a. 444 #4 244 sdp #44# 45. i 444 #53 445.1- 4445 41- 7>44 444 4-5441- l##5 444 lerp 4 44 453. 7(44 4444& 14##. lerf 4 44 453 7]44 44444 #5S 4444. [44 44]
• Interfacing System LOCA
• Transient (445 44 4344 5#)
• Small LOCA
• SGTR
(6) 344 47>44 (Phase 3 44)
444 4444 4447] 444 454, 144 4 2 444444 444
54 44#! 34444 447}# 4 44. ##5S1 2 44445s
47>4 4 ### 44 447>41 47}#4s 44. 344 sdp 47>444 54 4445 444 4441 44 #44 a-551 34 (41: spar)4 psa 7141 #144 1444 453 1444 4144 4143s 444
47}444- 444 14444 #4.
5. 44 nrc4 sdp 71] #4-4 414 #44 13 #4
7>. 44 i: 44H4 tfltb 14444 44
i) sdp7} 44 #4^1-41 14414 44 44^1-4 44 415 #471-44 #4 44 44441 41# 1 414 ##44. 44 4#4 4 41# #4.- phase 1 47} 304 444 phase 2 #7f7f #3-# 1 414,
- phase 3 #7>4 90%7} phase 1 #7} 904 444 #3# 1 414,- phase 3 #7f# 100%7} phase 1 #7> 120# 444 #3# 1 #14 #4
17
2) *4 S:7H1 4*5 44444 Bj-y- #45 5* sdp *#4 57}
**4* 44 *4 *## 4*4* *4* *55 444*. 444#* *55 #44^* *4*44 44. 444 4441 444 4^ 444
445 5* a>ji*4 ** sdp 1l^i7} 7B4*44 4*5 #5*44-
3) 444 4^-4 4*55 4# 44s. 44^ #4 sdp 47}4 *71*44#
47>44 4^44.
4) phase 3 47H44 psa #** #444 447} 44A}4 NRC4 45:4*
444 54 4 44444 445 45444.
4- 44 2: 4## 444 444 47}
1) 444 4A}4% 711444. 4a} 4'4a}4°1 4 44 4 444 44 44
445 *** 444 444 4 444 4444.
2) Phase 2 worksheet7> 4 4 4 445 4444 4 554 7}4 714 444 444444 4 $44 444 ui^**# 444 5 44. #4 *4A}##*
455 44A}7} 54 444 44 (non-Green issue)#* 4455 H #544 45# 4444 44A) 4544 Phases #4* 4W4 *4 4544.
3) SDP *4444* 4445 44 4# 4 *a> 44A}4* 95% 44*44*1 4#4 4*, 454 95%4 4a} #4A}44 sdp* 44 444 4*4 * *** 54# * *4. 44 *5**4 54 4554 44* 4a}
*4a}4#4 44**** 4** *444.
4) 44 4 * (human performance)* 4* ## 4*44 (cross-cutting issues)*
4*44 *4* 7>4a>44 444* *4-455 #44 * 4*4*5571^01 o}?$ 571 * *5**5 *5*4*.
18
5) A>y tjj* * ^ * £ *(enforcement)^ *444 CDF 4# CDP* #*44,
44£ SDP 4 44 *4# CDP *34 CDF* ##44 *734
*-#*1 tfl«H *4* 4*4* * 4 *£4431
6) 4**1 4# 4 4 4134* *4 4 71 o]^o]]£ #a}47} *4 4 SDP 4**1
*444 £44# *44# 4#4 *£* *### sdp 44 *£44
#4444 44-31 4*4-.
4-- 44 3: PSA #4 4 ?M4 #4
1) 44 nrc4 #*-£ #44-** 4^=a. #*#4 #** 4#|a3 4*a *44
4 #444 4# 4M4 4**# **(tooi)4 #44 #444 4*44. 44 nrc* 4*£ *J£ #44 #4 *4 7}# *44 ** 7fl*4 ;13#
*#£4 psa4 341 4*431 444 44* *#* 44444.
2) #44 Phase 2 worksheet* #444 *4* 44 441 &4* *##£51
4 *4 #4. Phase 3 *4* 414 4* 4 7>4 ##A}4#4| 4#
*4 7}# *4* nrc7> ul 444 #4# 4*4 44 * 4*1# (44*7}
#444) 44* #*# ** 4447} *44 *££ 4*44. * 4*1 #
tool# a}#** #7}# ## *££ #4£* 44444 7}*#4 *£££
4* #44 44#(predictability)# *#5L 4*44.
3) 44# 4 £##Ai s** *444 *4 *#* £# #a} ##a}4* #7}4
4 44*437 *44 44# ## 4 #* 4*1 £44 44# 44444.
444 #7}s. *-##44 4# 7fl443L £#44 *££ *#734*
4*4* £44 *£44.
19
6. % 44 44
4 444* *444541 4^h. ^5# 4*44 44 *4444 44445 *444* 54*7) 44 107H 7l^-3lo] 4*44* 4*4 #4
4* 4*4 4* 414 4^*5 #55 4: 444. [3]
(1) 444 4^4^ 44
SDP# ^a>x>7> A>-g-§>^^] 44 #^4 -447} ^}* 44# 4 ^4 #4 44444 44. 4# 441 4*3 *44^ 444 4** 44444 444 A}4-1-4 5 54:2 7l]44 4 444- 3|7}4 (SDPPanei)4 44444 4-4.
(2) 444 45 4 4A1# 44
444 47} 444 #5§}7l 444 5.4 7}*4-5 444 45.44 444
*Ais}(documentation)4 444 4-g-s]4 4 44- 4 45.44 4444 4441: iff 4 44 AM}#4 e#5 £444.
(3) 3:44 4 44 4*
444 ^r.2.4 444 44 4 #*#5 3:445.5. 44* 444 4 44444- 4* 44) 45*4 4(over-conservative) SDP 44444 45*4 4(non
conservative) SDP 44444 *# 4*# 4444. 4 44*4 *44**
4444 444 454* 44* 54* 44 44444.
(4) *A} 4* 7]# 44
54 4*44 4 *4*41 4*4 **4 4*55 #47)e* #4444
44. 4* # 4 4444 44) sdp 44444 4444 4 A1 4^-ofl 4 s. 44*44* 4*7} 44.
(5) a}-§- 444 5*/44 4*
4a}54*4 4 4# *444 4* 4 *4 4* #444 **441 A}_&^
20
# 4# is.a. 444 SDP 7M4 All#444 fl-rq-.
(6) i-EH 44
44# 44 4 4W4 44# 4## 4444 4i4i4 4 4#### i-i#-# 4 #4 4-4-. 4##4 5 ##4A<H 4i4 4### tl 44# 4-44-s 4*d ### #-44- i5744 iiii 4^444 #4.
(?) #4 #444 #4#44 4444 4A} y>#A}#i ^01 44431 #4 ###4 444
44444 44. 4# 44 471 4 4 # a] 3b 4 a] a] 45. (timeliness goal)?}
44444 44.
(8) #4 444 7}##°144-a>a>i-oi sdp 44# 4^4 44 #44 is# 7>4ji 7D### 4
4# 7l#4 444 #4444 44.
(9) #4 #4444 44a>44 ##4 44 4444 4#444 44444 44. 4
4444# 444 4444 #4 4#s s#44. s# 447} 44a}7} sdp 44# 44444 44, 44(appeal) A}^# 44431 44440} 44,
(10) Ai) 4 4s/#i44 til#4 44 44 ##4 s# 44 #4 tii^-^444 ^4^- 31444
4#444 44. 4# 44 444#4 #444, 44 444 444i-(non-green finding)4 44 Si444 ## Afli#4 444-4--
21
7. t* *#44
7.1. 44#4*## 444 sdp* *4 *4 #4, *5* 44*#*, #*## *
4*a}* 4*4* #44 #444## W#*# *44* #*# *#4* 4M4. M**4 *4 4# 44444 44 *4A}4#, *5* 4 ##4* 4444 444 44 44* 44 #44 442} #47}*# 444 #4* 44
47}* * *4.
5. 7-1-8: #4 nrc4 sdp #4 44444 kins44 4*84# 4^ 4444* #h* 444. 44 #4444 44 sdp 4445* rop 44 4445. 4S.4 4444 licensee 44# 4 7}#-*# #*44- SDP 44444 44 44# .4*#22 4444s.* *4*4 44A>44 4# NRC 44 4 4*4(enforcement
actions)# *444. 44 *444# sdp #4*5 4444# 444*4 #4* 444* 4# #4 * 7ie* 444*4 4* 4*5 44*4.
** 4a> ji*A}#i- #5* 45* 4*4 #4*5 a>##^ 4* **#
##* *4# #4**4 *** #4 ***4. *aH4 #4*4 4 #4* #44 ### #44 *44 4** *44 *4* 44 4*4* 44 **4 44* 4* 44# 4# *4* 45 ###A}5 *47} #*| 44.
sdp 44# #Afl# *44* *4* 4# 4**4 4*2 *4a}# *a>*7>**7> *4 7} 4 7l#**4 7]#4 45 4 #4 7>4a>#^oii #5ii *4*4# 4*4. ## *-4*-##* nrc 4*244# ##4*5 ##4# 47]* #** 44 #*a>#o] ## #4* #44 45*4* *4# # 4 *4. 4* nrc #*2*4474444 **7> *44 a>o]# *#oi 55 #4* ,*4* *#**# 4 *4. 4# *4 #a>7>^* **7> *4-7}# psa #5* 5*4# sdp# a}#-# 54 45#* #4 4##4 *4* ^444.
22
3. 7-i.nrcsdp ^a}«4 h
#4 gA^A, ROP (Inspection) °ll a)s|SDR 3@33
4-MlSDP3ss ?ie3SA)#
gA) Z3I§7|SA\U} gj Sig-^xm-w X| 2
33 4413 44, S2A|337) x|3
2 A) 0|#333# 3 3A)y ys 34 (2X)S13)
77H safety cornerstone (S7| A)3, 3S)7||#, b|#E:M #) #o) #0) 23 |2
2 A) ## 7|#XI23 SSfH77H safety cornerstone 4XI 33# ?!3 397H baseline 2x)ifs.
40)22 |2
2 a) 33 22227| #^5)2
SAWnj-^oll $|-°
(433, 223)
3 X)A) (0609.02)011 [[)# 3 2)2) &7| #223 Z!|#3 A|Aj 5)
3x) SK S2
2a) 2°) X-IEiy- 3
Mj¥ x(e.|2x)oi| 37) 3 2t|| (3 phases) Af|# x) B| 3 x) 2x) ya| a<2_
gS-y §7W a AW §i @7)335| SERF (SDR and Enforcement Review Panel)
S3 §22 @7) 7|§
22^3 7|g (Code & Standard,T/S Si HaW #2 #)
A|| 7)X| S#e| 2@/A)3 X|#A] 30|| CC)E) X)# 7|# $4#S)0i 7)3 233 2xi##a|l.)b|2# 3^5)3 ?lt)4 33 (risk level)33
7|# *il3 mo
S3 §22 @7|- 32 Si X|xjo| 2 3-711 437|| color (graded approach) 7|# A||§ m°
33 aID/Sx)SJ3 2a)x|*]a) + e:H2 gf-y^“ot« gA[gg =
RIBI/SDP 2 a)x|xia) + ?|Sj27| 3 3322# 2A)325(RI inspection notebook)
x|5) 7H1 |2
§2 7|y ss. T/S, FSAR Si 7(Bj- 3# 7|#7| 34 #4 + PSA 35) Si 33237)21 (SPAR)
21 7H# 12
a|23Ex| @23371231 a|22x| 23 (x|5j A)#3B|gx)) + T/S ?! tLWS-21 33 #W2E%|
Action MatrixO|| rr)H 2x|Hj# x) # + Licensee Appeal 32 2# 3 Assessment & Enforcement Process
Sx) SU mo
23
7.2. ^7]A>g
#5 44 NRC5 4 #4 994a] r]-994l 999 4"45 19874451995444 444 22A]^ NUREG/CR-5750[4]# 44494- 4 7] A] NRC5 49
44^114442-4 5°1 44 5 4 °l 44 a}ji^- throughwall crack 444
4^445.44 444 correlation^#9# 44494- 4 22AiS}- ir4
5,6571 PSA iLJ7.Ai[5]i- 9-52 44 44 7}99529 444 44 7}#9 sdp
Phase 2 47}# 44 44 244 27]A}£ 444 worksheet# 44494- 44
445 5. 4-H 4444 924, nureg/cr-575(M14 45, 454 94
4444442, 44 44444, 444 4444, 44444444 44
9544- nureg/cr-5750 53.AMI 444944 955 2# #44 94
7}9#5 #4 5,654 PSA 52Ai# 95994. 49 5,657] PSA 52A] °\)
9447] 95 RCP 99 LOCA, Safety/Relief Valve Stuck Open, 449 94 44444 455 nureg/cr-57504 945 49 49494.
7.3. 54A>y^ iM3 99495 94 9-9a>49 54A}4^ 49 444 495 44 4 #4 9 4
54494. 99925 99 44 54 49# 4 95 54a>4s] 444 245 ###22# s] 494 40] 944 9 94. 44A] ±45 45525 45 94
54.
g~a Ctxp(x',a) =-----— x = 0,l,2,... (1)
x!
4 245 525 #94 94 2# Ml 444 #9-445 %4 49 9495 (probability mass function)# 4444- 4 #2# 99 At a]^> 94 99#5 A>4(event)4 4444 94 499 99 4445 45# x 2 5# 91,
e~^’(AA tYp(x;AAt) =------ a = 0,1,2,... (2)
x!
24
444 2-5 (parameter) 2 5 54 7}^, 444 JE# a 5 5444 54444 44 55^ 4#44&# <*£ 4 #4- ## 54 At 4# ^o> 544
#54 4445 4#5 ##4 54.
P(2f >1) = 1-P(2f = 0) = 1------^^- = 1- 5^0!
(3)
At (3)4 54 55 44 (infinite series expansion)#4 544 54 44,
P(X > 1) = 1 - (1 - 2At + (2At)2 / 2! + -....) « 2At (4)
454 4(4)5 44 At 44 544 a 5455 7}4jz 44 444 444 4#5 5445 44 44. 4# 54444 4444 44, 44 t,4 t2 444 4445 i,E # 7>4 444 5444 44 4#4 454 44 444 5 54.
Pr(/P between /, and t2) « 2jE(t, - z\2) (5)
5 4-14 445 “54 545 445 4545 2:54 4444”5 44 305 44, 3044 35 44, 35 444 344^ 454454 4# #544 4444454 4 44444 4445 4444 444 454 45 4534444.
• 2:71 44444 44 it (upperrange)# 4544-• 45444 305 444 55 14P-5. 7}444.
• 44444 3054 35 444 55 o.i4P.s 7} 444.• 44444 35 445 55 0.014P.S 7>444.
44 45 7}5# 4-8-44 454P-& 4 iM### 4784 55 4^4 44444.
25
4-5-4 14 44 415 44 44. 5. 4-i-ir 51 125V 445-4 444
ml4 4444 4£7} io2 444 103 4 444 4 4 44, 4 44 l0~2/yrl
44 15# 44 45.5. 4444. 44 4 444 4444 444 44 444
44 5# 44444 4 "s 44 444 4 2514 44414s. 4441
A444 444 4^ 44 444 14 34 44.
vV = - log10 (Pr(IE’ during condition period)) = - log10 (1 O'2 x 10”1) = 3
44 44 44 445. 144 4444 544 44444 44 44444
NRC4 37>4 44454 44444 14 414 5444 1444 444
scfls. #5414. 54 4414 455 5. 4-M4 5.5 44 14 o44 744
nrc4 447>45. 87>4s. 554144 44 nrc 455 144 844 4444
14 4 54 45 54455 44414.
7.4. 7] 4 44
4# 544 44545 45 55 445 44444 1444.
(1) #54 54 414 14.
(2) 454 4545 #4514 14.
(3) 4## 14 54# 4## 4447} 14.
(4) 44# 5144 11 4445 51# 444 14.
(5) 54# 54454 #5# 7147} 4444 45 44444 14.
#14 45/444 1# 5441 444 1145 4445 554 545
#15 54 #44 4544 4555. 54 444s 1141 445 44444
#4. 4 554 5#444 45 455 45 #15 s# 544 4514. 5
15# 54 7il#l 571414 451 544 1445 (DIM: dependency linking
matrix)5 55 l4 4444 154, 45 515,657] PSA# %4s. 5 57]4
5441 55 455 44-55 14# 144. 5544 55 44 14 444
26
3]#4 4# ZL #_& 44# 4#7fl# ### A
7H#/7]7]4 444# 34 a}# 4 #4# 41454. #34 4 a]# 4 4#4
34a}#4 444 ##44 4 #4 4# 4# 444 44# 44 444 44# 5344-.
8- 44 AM 4###
44#4 sdp 4414 4M4-7} #43 444 #634 =4 5#4 4444
444 #41 a>41 #4# #W£#. A}413# 7}## 44 444444 4 4,
7}^f 1M# AM414 4 4# 44- 444S4. 444 4 44 4)334#^
3 Loop 900MWe 7}<44#3^M JL# 3,43:71 # 44 1,231714- 4444, 4All
SDP worksheet7> 4444 44 &333 #A} 444 44 2:41= 444 (Joseph
M. Farley) #444 200144 4444 7)144 4^3 43 4a}443[6]4
worksheet# #&444. ¥ 4 £t 4 a} #4A}4o]4 7>4S}J1 44#
#634434, #44 44# 44-4 34=44 7}4 4 7}#4 4# 34#
43444.
7}. A}4 1: 314 434 7l7l444=(CCW) 43 71### 4AH4
4 AM<41 A) 44# 4a} ##A}## 4## 44-.
“20004 34 437] 12# 47]4A}6)]4 CCW 43## AH## 4A]#3
3#4 4«fl 1ST 344 44 #4444 43 4444^14 #*344 #3
37fl# #7]3 ##634##4-0] #@34ji 4# A}## #4444. (44 a}#
4443 00-3-018)” [7]
4 4 a} iMa}#-# 44- ##] #434 A}# o}# 44# a] 4## 4#A}#ofl #4444 4 #444# 3##33 #7]#4 3# ccw
434 Afl##4 #### #44A] 7)44 4#44* ###3 ##433
27
4#### 444# #7}} 4# ## 7}4#4. 44 44 SDP
14 #7}# 4444.
(1) m^il SDP: #4 5. 3-2(l/3)°ll 445 4144# 4544. 444 5#4
4444# l### #4- 444 4# 5 Cornerstone4 4444 -£#
554 Check Point?} 444a4 444 4 444 144 SDP
4444 SI4 45- 244 SDP 4445# 44444 44 45.5.
4444. (5 8-i %>5)
(2) 44 5454 4-4: ccw 44# a# 44 545 ^44##45 5
445.5444# 444 544-44 4454.
(3) 4 54544 444 54: 5 4-14 305 444 4#44 54
45444 44 -£# l(row)4 444 454 4444.
(4) 44 44#4 54 4 45#4 45 54= 5 4-2# 4544 ccw
41 #4 44 45#4# "44444 554 ?}4# 44 44#4# 25
44. 444 CCW 4144 445. 521454 5#4# 444l#(frontline
system)4 44 ?) 4I#4 54 44#4 54# 4 4# 4 414
4#454 44 4# 44 4#4 44#4 44-7} 44 4 44. 4
44# 4 5?}# 5 4-2# #554 5444.
(5) 5^444 44-545 44: 4# 545 444 444 4## 45
44445 157}) worksheet# 4#54 244 sdp 44 44# 5W4.
444 ccw 41## cvcs/hpsi, rhr/lpsi 5 rcp# 445# 4444.
454 44 41 #4 4 4115 4###445 54455 7}4#4.
444 5 8-24 4 5.7155 SDP Worksheet^)# H?)## 44#44
4444 Si# 4W44 4444# 4#45 44#4 45 144
4# 4444.
(6) 4 7}14, 4# 57154 4#4444 #4555 4 ## 27}), 5## 57i), 6
## 47H 4#4 5544 444457} 45455a. red# 44444.
(5 8-2 45) #4 47114## a#4# 4445 4#4S1# #4# 44
#44# 47}_s_## ### 3441 sdp #44 ##544.
28
4- 431 2: 4# 13171 44444(MFIV) 31#
4 4314 7]7} 31445. 47>5.7> 444 44444 4444 44 3144444 4444^ 444 4^-^ 4444 4444.
“20024 64 194 44 1^7] #444# #44 44#4 3i##5.#7] 4-737HI ##7> #4431 #714-737] 4-4 433] 431 #7>5. 4 44-
4447> 444. 31444# #4# 44## 4## #44144 #4 #4## 4##7> ##4 44 7144. (ler #31 43. 2002-06#[020619Y1])” [8]
44 4# sdp 44 44# 4444.
(1) 1431 SDP: #4 & 3-2(1/3)31 444 4444# 7]#44. 444 #444#444 44 o/h (20024 2#)3] 44444 #334 4# 4444 444 444 444 44 27I# 4## 44. 44-4 4# 4Cornerstone4 4444 2-1 #7] 4-4 4 4-SA]-g4 4# 144 Check Point7> 44434 4-4-4 4# 1431 sdp 4444 #5- 4 4 #4. (& 8- 3 ##)
(2) 5 3-2(2/3)31 444 4444# 4444. #7]Al-4 comerstone3l 44 24 ##314 447144 4###3]# 44# #43i 4444 244 sdp 4444## 4#44 44.
(3) 44 #444 44: mfiv# 4#44 44# #7]A}43]4 4444.
(4) 4 #444# 4AH4 #4: s 4-i# 30# 0)44 4444 34
444431 44 444 434 4444. 444 34 a} 4 4-44 4##
o# 44.
(5) 44 4##4 #4 4 4##4 44 #4: ### 31## #4433
A}3.4#3] A}#5]4 ^OnS o] y-Til# #A)44.
29
(6) 4:2#41 Ajzl-Ajxls: 4^: 4# ^Bjol 444 Si^a 4M.
4444S# 4S/)-44 5)14# 27)1 worksheet# 4##4 2#4 SDP14 #4# #444.
(7) 3|7>#4, 6 ## 37]), 8 ## 37M A>J1^^| ^4^x157} ijEl^^ES
## S414# 44 4#4SS 5##4 4 $#4 4-4-4 YELLOWS
45444. (5 8-4 #S) 4#4ss #4 4- -2-4-45# 4a54
7)44 (accident sequence precursor: ASP) #4# #4) 4 L3 444#
#4444 1 4SS 4-454-.
9. W <9# 44
4## 471 #44444 4-4-4 4# #4 1SA}4#^- 444 444-.
(1) 444444 4 #7)44 #4S 44# (worksheet)# 44# -H#444 44444 444 44# #4444 44. 44 #444# 44#s 44 #7#}4 44# 44## 4444.
(2) 44 4444 444 44 44 #4444 #741-44 #47}#4#
#7>4444 # #47}#4# 44 #4444 44. #444 44 #444# 4 #4 <9 #4# 4S44 *11444.
(3) lerf 4 44 4^a 7H^ 4444# l#s #444.
(4) 444#4 44444 44s 44, #444, s#4#, #4 4## 44s 44#4 44 4#4 444 44 4#4 454 444# 54 44454 4^a 444# 441- # 5# 14# 7j)H4.
(5) 44 71)14 s4444 4#4 #44 s# (5# 1 4#)4 4444 444# (v&v)# #W4.
30
10. 9# 4 a#
4# NRC# A) 7ij# A}-g-S}31 ## 99 993 #Aj (SDP) 99# 5)33-93#
99 #44 #-§-#4 3#94 349# 4U#71 #9 4#4 444494. n
sdp 944 #-§-4# 4# 44#4 99 4## ## #9# 5)33 #3# 49
444(threshold)# ##4 "a4 4—3 43# #4 #-§-##4 #4 ##4#
Ri7} #4. 94 ##44# 44 nrc4 ## A}## ei|s. zl 444 44
444- #4 #4# 3A> #4 ##4-. #4# #3 67}%) 49# 44 #4#
4 44-31 ##4- 93 34A}## 9994 44 43# #443# 94444 #
44## 3#4#4 344 9444. 44 44 9 a} 9 399-91- #-## #
244 A>3n#Aio] #^494. 3# ## 44 44944 sdp 4# #9# 94
7)44 9 4994# 49494.
n. #3 #4
[1] 6th Technical Meeting Minute of Risk-based Precursor Analysis, Association Vincotte Nuclear, November 6-7, 2003.
[2] NRC Inspection Manual, Chapter 0609, March 21, 2003.[3] ROP Performance Metrics, October 12, 2000.
[4] J. P. Poloski, et al., Rates of Initiating Events at U. S. Nuclear Power Plants: 1987-1995, NUREG/CR-5750, US NRC, February 1999.
[5] #9 5,637) PSA 331 A), #499#%M9), 2002. 6.
[6] M. A. Azam, et ah, Risk-informed Inspection Notebook for Joseph M. Farley Nuclear Plant Units 1 and 2, BNL/NRC, Rev.0, September 7, 2001.
[7] KINS/AR-I09, 315) #a}9 437) ^A}#J7A), 412# 9 7) 9 A},
94949 997)^9,2000.10.
[8] KINS/AR-813, 2002#3 #9 A)-3-3# #A}#j7A), 94#A}#9971##, 2003.
5.
31
it 8-1. JLEJ 43:7] x>3i]o]] tfltlr l^l SDP 44 44
LER tiS ( ) gx^32AH H}S (KINS/AR- 109 )
(1) ig 7HS (-MS):CCW Tge# 2,#0)1
4)6)1 583gAiy °1 4=^5)7) ##
1-1 zlSE! sgo)| °]SH xisi-g 7f|# xp|yg^7||5
1-2 sgoH 2|§H xj#g 7)|g
1-3 4I# 5E# 2IISS] 7|M 7|^•n-y 51i^s (gxiazr) §j gyy#
I2||7i
1-4 ?ii'e c)s
1-5 N/A
1-6 #sr@ sgo| 7|^ 7|t> ( 365 ) 1 ( ) a|t>
(2) xlsl-sj 7|#r g! Cornerstone 99:
2-1 S7|A|-S
O 2f£Af>! (gx^EEj [2]
o LOCA S! 2## c|jStiHg-n)cr [22]
2-2 glsMi#
O 5L?| Sl# Xl«X-j|7)7|^ [ y\ O 5PI £M*l|7p|^ IJ7
o S#^g|o) 7)^ | | O SM/S^/X|ZI/S# 1
2-3 orgurw
o 17) 2#e ss [2
o ttj<ys ds |
o gyys ss |/|
(3) 7|Ef Si 7)# 7|# gg:
3-1sl2HS&7|# | tf
3-2@x|# °)#7|(=- | j/f
SB
o 2?H o|-y°) Check Point Si# | V\ ------------—► 2E14I SDP
o VH°| Check Point Si# [2] ------------*" "=!# E121I (2#)
o Check Point Si# | j ---------------- ► 1 &J\\ SDP #S
32
Table 8-2(2) SDP Worksheet for Farley Nuclear Plant Transients with Loss of PCS (TPCS)
Estimated Frequency (Table 1 Row) / *7Exposure Time / Table 1 Result (circle):ABCDEFGH
Safetv Functions Needed:Secondary Heat Removal (AFW)
Early Inventory, High Pressure Injection (EIHP) Primary Heat Removal, Feed/Bleed (FB)High Pressure Recirculation (HPR)
Full Creditable Mitigation Capability for Each Safety Function:1/2 MDAFW trams (1 multi-train system) or 1/1 TDAFW tram (1 ASD train) to 2/3 SGs xvith 1/5 SG safety valves cm each SG fed by AFW(l>1/2 charging pumps or use of spare charging pump (I multi-tram system)691/2 PORVs open for Feed/Bleed (operator action = 2)1/2 charging pumps with 1/2 RHR pumps and with operator action for switchover (operator action =3)
Circle Affected Functions Recovery of Remaining Mitigation Capability Ratio? for Each Affected SequenceFailed Train Sequence Color
I TPCS-AFW-HPR (3) o ■/ 3 -f-
2 TPCS - AFW - FB (4) f 3 -/ 3 i
3 TPCS - AFW - E1HP (5)o -i ■> / 5-
Identify any operator recovery actions that are credited to directly restore the degraded equipment or initiating event:
if operator actions are required to credit placing mitigation equipment in service or for recover)' actions, such credit should be given only if the Followcig criteria are met: ?) sufficient time is available to implement these actions, 2) environmental conditions allow access where needed, 3) procefcires exist. 4) training is conducted on the existing procedures under conditions similar to the scenario assumed, and 5) any equipment needed to complete these actions is available and ready for use.
Table 8-2(3) SDP Worksheet for Farley Nuclear Plant — Small LOCA (SLOCA)
Estimated Frequency (Table 1 Row) Exposure Time f 7 ^ Table 1 Result (circle):
ABCDEFGH
Safety Functions Needed: Full Creditable Mitigation Capability for Each Safety Function:
Early Inventory, HP Injection (EIHP)Secondary' Heat Removal (AFW)RCS Cooldown / Depressurization (DEP1)RCS Cooldown / Depressurization (DEP2)Primary Heat Removal, Feed/Bleed (FB)Low Pressure Injection (LPI)High Pressure Recirculation (HPR)Low Pressure Recirculation (LPR)
1/2 charging trains or use of spare charging pump (I multi-train system)<l>1/2 MDAFW trains (l multi-train system) or 1/1 TDAFW train (1 ASD train)Operator depressurizes RCS using 1/2 PORVs (operator action = 2)Operator depressurizes RCS by using 1/2 PORVs and by opening 2 Z3 AKVs (operator action™ 2)1/2 PORVs open for Feed/Bleed (operator action = 2)1/2 RHR trains (1 multi-train system)1/2 charging trains with 1/2 RHR trains and with operator action for switchover (operator action = 3) 1/2 RHR trains with operator action for switchover (operator action = 3)
Circle Affected Functions Recovery of Remaining Mitigation Capability Rating for Each Affected SequenceFailed Train Sequence Color
1 SLOCA - LPR (2, 9) 3 f
2 SLOCA - DEPI - HPR (4)~b -7" 3- -f 2- 7
3 SLOCA - AFW - HPR (6) 3 -f -h 2- • 74 SLOCA-AFW-FB (7) t / > -/- 3 9
5 SLOCA-EIHP-LPI (10) v f 2- ~f 2- 7
6 SLOCA-EIHP-DEP2 (11)9 -t ■*- -f 3- 7
7 SLOCA-EIHP-AFW (12) *
33
Table 8-2(7) SDP Worksheet for Farley Nuclear Plant — Loss of Offsite Power (LOOP)
Exposure Time ^ Table 1 Result (circle):
ABCDEFGH
Full Creditable Mitigation Caoabilitv for Each Safety Function:
Emergency AC Power (EAC)Turbine-driven AFW Pump (TDAFVV)Secondary Heat Removal (AFW)Recovery of AC Power in < 1 hr (REC1)Recovery of AC Power in <5 hrs (REC5)Early Inventory, HP Injection (EIHP)Primary Heat Removal (FB)High Pressure Recirculation (HPR)
1/1 dedicatedEDG(Itiain)or 1/1 swing EDG (operator action =l)w1/1 TDP trains of AFW with 2/3 ARVs (1 ASD bain)1/2 MDAFW trains (I multi-train system) or 1/1 TDAFW train (1 ASD train)Recovery of AC power within I hour (operator action = 1}<2*Recovery of AC power within 5 horns (operator action = I)1/2 charging pumps or use of spare charging pump (1 multi-tram system)*5*Operator uses 1/2 piessurizer PORVs (operator action * 2)1/2 charging pumps with 1/2 RHR pumps and with operator action for switchover (operator action = 3)
Recovery of Remaining Mitigation Caoabilitv Ratine for Each Affected SeauenceFailed Train Sequence
1 LOOP- AFW -HPR (3) // ?-y-5- i
2 LOOP-AFW-FB (4) /-f 3 + 3 7
3 LOOP - AFW - EIHP (5) / -f 3 ■+ 3-
4 LOOP - EAC - HPR (7,11) (AC recovered) / -+ 3- -+ 3- ir
5 LOOP - EAC - EIHP (8, 13) (AC recovered) ( -f -7- -f 2-
6 LOOP - EAC - REC5 (9) / -h 3- -y- /
7 LOOP - EAC - TDAFW - FB (12) !-f- t
8 LOOP - EAC - TDAFW - REC1 (14)/ •/- 2- -f i V- i 7
Table 8-2(12) SDP Worksheet for Farley Nuclear Plant — Loss of Instrument Air (LIA)(1)
Estimated Frequency (Table 1 Row) Exposure Time / J ^ Table I Result (circle):
ABCDEFGH
Safety Functions Needed: Full Creditable Motivation Canabilltv for Each Safety Function:
RCP Seal Injection and HP Injection (EIHP)
Secondary Heat Removal (AFW)
1/2 charging trains or use of spare charging pump provide RCP seal injection and high-pressure injection (1 multi-train system)(2>1/2 MDAFW trains (operator action = 2)®
Circle Affected Functions Recovery of Remaining Mitigation Capability Rating for Each Affected SeauenceFailed Train Seauence Color
ILIA-AFW (2)
2 LIA-EIHP (3)3- -j >- ¥■
Identify any operator recovery actions that are credited to directly restore the degraded equipment or initiating event
If operator actions are required to credit placing mitigation equipment in service or for recovery actions, such credit should be given only if the following criteria are mer. 1} sufficient time is available to implement these actions, 2) environmental conditions allow access where needed. 3) procedures exist, 4) training is conducted on the existing procedures under conditions similar to the scenario assumed, and 5) any equipment needed to complete these actions is available and ready for use.
34
5. 8-3. <8^ 1^7) a>bH 41# 1#4) SDP ## 4^
#519#: LER BI ( 2002-0651 ) 33S5IA) 921 ( )
(1) 493 2L3 7Ka(^@): 454= 39# “ 9## 55ns9=|2-H #9°s. 9## V#
1-1 393 ^gloll °ISfi 3# 454=3#
1-2 393 ^ycH| °|si| 343 39
1-3 Til# EE# 7l|g°| 7|S. 71# 233# 9374
1-4 Til# 55# Ti|9=| c|# =137|#
1-5 9359 9^ N/A
1-6 393 3sy o| X|# 7|9 ( 60 ) 9 ( ) 93
(2) 343 71-5- 9 Cornerstone @9:
2-1 S7|A^>| xO 3933 (99SH9 #) [_KJ
o LOCA 9 234 CHSBH94-9 [ |
2-2 333#o S7| ## 39Til737|# j | o 371 39A||73T|#
o 9#£34 7|# | | o sM/#^/x|3/3#□□
2-3 9399o 13 T||* yw □ o 333# 33 Q
o 39# 333 99 | |
(3) 7|E|. <ggt 7f# 7|* gg:
3-1 33 927]# | |
3-2 @3# 937|# | |
35
o 23 o|3°| Check Point 9# j^j ---------- ► 293 SDP#3
o 13=| Check Point 9# | l/\ --------K 9* 93 33 (2#)
o Check Point 9# | | -----------► 1 93 SDP #S
35
Table 8-4(1) SDP Worksheet for Farley Nuclear Plant — Transients with PCS Available (Reactor Trip) (TRANS)
Estimated Frequency (Table 1 Row)Exposure Time , ^ Table 1 Result (circle):
ABCDEFGH
Safety Functions Needed:
Power Conversion System (PCS)Secondary Heat Removal (AFW)
Early Inventory, High Pressure Injection (EIHP) Primary Heal Removal, Feed/Bleed (FB)High Pressure Recirculation (HPR)
Full Creditable Mitigation Capability for Each Safety Function:
1/2 Main Feedwater trams with 1/3 condensate trains (operator action = 2)1/2 MDAFW trains (1 mute-train system) or 1/1 TDAFW train (I ASD train) to 2/3 SGs with 1/5 SG safety valves on each SG fed by AFW11*1/2 charging trains or use of spare charging pump (1 multi-train system)121 i/2 PORVs open for Feed/Bleed (operator action = 2)1/2 charging trains with 1/2 RHR trains and with operator action for switchover (operator action = 3)
Circle Affected Functions Recovery of Remaining Mitigation Capability Rating for Each Affected SequenceFailed Train Sequence Color
1 TRANS-PCS-AFW-HPR (4)0-f T'-f 3 Sr
2 TRANS-PCS-AFW-FB (5)a -/ 2- -f 3
3 TRANS-PCS-AFW-EIHP (6)o V a- -f- 3 -T 3 B
Identify any operator recovery actions that are credited to directly restore the degraded equipment or initiating event.
If operator actions are required to credit placing mitigation equipment m service or for recovery actions, such credit should be given only if the following criteria are met: 1) sufficient lime is available to implement these actions, 2) environmental conditions allow access where needed, 3) procedures exist, 4) training is conducted on the existing procedures under conditions similar to the scenario assumed, and 5) any equipment needed to complete these actions is available and ready for use.
Table 8-4(2) SDP Worksheet for Farley Nuclear Plant — Transients with Loss of PCS (TPCS)
Estimated Frequency (Table 1 Row)Exposure Time ^ ° ^ Table 1 Result (circle):
ABCDEFGH
Safety Functions Needed:Secondary Heal Removal (AFW)
Early Inventory, High Pressure Injection (EIHP) Primary Heat Removal, Feed/Bleed (FB)High Pressure Recirculation (HPR)
Full Creditable Mitigation Canabititv for Each Safetv Function:1/2 MDAFW trains (I multi-train system) or 1/1 TDAFW train {1 ASD train) to 2/3 SGs with 1/5 SG safety valves on each SG fed by AFW(I}1/2 charging pumps or use of spare charging pump (1 multi-train system)1211/2 PORVs open for Feed/Bleed (operator action = 2)1/2 charging pumps with 1/2 RHR pumps and with operator action for switchover (operator action =3)
Circk: Affected Functions Recovery of Remaining Mitigation Capability Rating for Each Affected SequenceFailed Train Sequence Color
1 TPCS - AFW - HPR (3)i
2 TPCS-AFW-FB (4)» -/ ? -f- 3
3 TPCS-AFW-EIHP (5)£> f 3 B 3 t?
Identify any operator recovery actions that are credited to directly restore the degraded equipment or initiating event:
If operator actions are required to credit placing mitigation equipment m service or for recovery actions, such credit should be given only if the following criteria are met: 1) sufficient time is available to implement these actions, 2) environmental conditions allow access where needed, 3) procedures exist, 4) training is conducted on the existing procedures under conditions similar to the scenario assumed and 5) any equipment needed to complete these actions is available and ready for use.
36
Initiators and System Dependency in UCN 5&6
Sys CompCode Code
1-.
Affected Systems :0:2:;2:;: Saasgfasi1 4.16kv SW01A, 125V DC DC01A, #7|
SI p 2ofof2^oig2 5SfTlST||™ a, yS2@i8#8s-Aag}yg?gj«H 2 4.16kv SW01B, 125V DC DC01B, S?lza}T{#4@ b, yg28868£-BSI 617, 627, 637, 480V MCC MC 08A, yg2y8S8£
SI 2gm£!2g|4ft v_ 3ojof2?o)25f^a| 647 -ASI 616, 626, 636, 4BOV MCC MC 08B,646 -B
SI-603 480V MCC MC05ASI-604 4BOV MCC MC05B
mt§m 2€3 2jB|W»SI-321 125V DC DC01CSI-331 125V DC DC01D SLOCA, LOFW, SGTR, ATWS(CSGTR), LSSB, LOCV, LOOP, LOCCW, LOKV, LODC, SBC, GTRN, ATWS, LLOCA,III! 2 Of 012 ^oj Til s. III ayyg^gjgH, 2 B|5|^^s|geSI—699 480V MCC MC05ASI-698 480V MCC MC05B MLOCA, ATWStPSVstuck open)SI-667 480V MCC MC05A, 42% 858S.-A
0i# 2yyg2S4s Eitii *|5 ^s| ^5 4a| 1 SI-666 4B0V MCC MC05B, 42% Sf€8s-BSI-659 125V DC DC01A, 42% 8S8S.-ASI-660 125V DC DC01B, 42%
Si jiofofg^ojTjs. V_ 4'82# 825 3E| SI-675 480V MCC MC01A, 42% ^tSil2-ASI-676 480V MCC MC01 B, 42% i|§i!2-BCH-531 4BOV MCC MC01ASi 30f0f2^0l7)g V_ 489233 4all5CH-530 480V MCC MC01B
2005-05-08 39
2.
:'Aifect6^Sy^t:e%S;;y ivVSStipftdtti^ initiating Event.
4,16kv SW01A, 125V DC DC01A, 33asaaf3@a1 ?y 3532 43 a , 4 ?a 363
3333?945 ■>. ag}33?aaHayaa^san2
2. 49 A, 57|Z£|45 49 A
4.16kv SW01B, 125V DC DC01B, 33?a 3532 49 b, 4 eaa^ds
49 B, S7|Z£|7|# 49 B
SI 615480V MCC-MC08B, 33? 9 5,'§i!S
49 B
SI 625
SI 635
480V MCC-MC08B, 33? 3 3532
1)11 aya3?945 v_ 3a33?SHaaB| Tim B480V MCC-MC08A, 33?3 3532
49 A
SI 645480V MCC-MC08A, 33? 3 3532
49 A
SI-668480V MCC-MC05B, 4S@ 3532
49 B
3y3t3?34* 111! ay9S?33:£°4iavails
SI-669
SI-659
480V MCC-MC05A, 4r@ 3532 49 A
125V DC-DC01 A, 4t9 3532 4 9 A
SLOCA, SGTR, LLOCA
SI-660125V DC-DC01B, 4?3 3532 4
9 B
WM a993?34s i>ill- ayy# 3?2 aa SI-675
SI-676
480V MCC-MC01A, 4S3 3532 49 A
480V MCC-MC01B, 4r3 3532 49 B
§il 3933?94s iSII; 3333?3a263a asi^s
SI-691
SI-692
480V MCC-MC01A
480V MCC-MC01B
uiM ayaa?g4# v_4yaa?3aH «@ ?, 33^34* 9JZ ¥!7| 3?? Hx(3 4
B|502
SI-693
SI-694
480V MCC-MC05A
480V MCC-MC05B
433?aa2?E| 5 CH-530 480V MCC-MC01BSixx; ag}33?34s V 33333365521
ci53 3392 CH-531 480V MCC-MC01A
2005-05-08 40
3
Support Systems
4.16kV SW01A, 125V DC DC01A, 39XISM^SSH 1 ?3 $t69£ MS1|°! A, 9ie#969
£ 593 A, 57|S$|7||E — *-fi 3 ASI @9yzi7«# Siffig 9 3334^® 2
93394;3@h 24.16kV SW01B, 125V DC DC01B, 39 4=3 9B9£ sen3 B. 7H£i* 969£ S3|3 B, 37|Z#7#* £S13 B
SI-615, 625 480V MCC-MC08B, 39f 3 469 £SI v_ 933a 4s 39 ^ais B9I3 B
SI-635, 645 480V MCC-MC08A, 334=3 469 £ Eejol A
9 339 4s 3 @= s 3S 9a|Ms
SI-691 480V MCC-MC01Afe sgyzMis v_
SI-692 480V MCC-MC01 B
ga^g^gJSHBHT SI-693 480V MCC-MC05AWM :. s, 99 yziTis #3
isf3 zjaiSSs SI-694 480V MCC-MC05B
SI-695 480V MCC-MC05A
s^mzf^e ms S9S47II5 uHtS 9aiWH
S1-69 6 480V MCC-MC05B
SI-657 480V MCC-MC05A
SI-658 480V MCC-MC05B SLOCA, SGTR; LOOP,SBC, ATWS, LSSB,
9339t3@hg^aigs
SI-307 480V MCC-MC05A LOCV, LOFW, GTRN,§^iyz}7is V
SI-306 480V MCC-MC05BLOCCW, LODC, LOKV
HX 1 7|7|yz|4: 7j« A@9^44# HX_ 9999716 WH#7|
HX 2 7|7|yz{4: 7fl« B
SI-655 480V MCC-MC01A
SI-656 480V MCC-MC01B
Ill g^iyzjTis V.3913971# *14=32;
91 =
SI-653 125V DC DC01A
SI-654 125V DC DC01B
SI-651 480V MCC-MC03A
SI-652 480V MCC-MC03B
SI-689 480V MCC-MC08As^iyziTis i®l; 0133 4412
SI-690 480V MCC-MC08B
gift ;ll||#4=
325^E} §7|UjZ|7j% 63S259 2}a|
V-0033 480V MCC-MC01A
V—0034 480V MCC-MC01B
2005-05-09 41
4. ziWasaK8**
: i MeetbilSysfefb 6 l :;;'-.;i; ;^|b;r: SoMp'OiRentS;^;:;: ;•:.; i':.‘.;i:i:;':;;i: Support Systems
4.16kV SW01, 125V DC DC01A, 2W4yy#^4Hz1 2# 4*4=*iS4l4 A, 57|3E$17||
#0 3fet2e-kiT?iis :s#lll ay*2S 4*4=tiH * saia a
4.16kV SW01B, 125V DC DC01B, AH4yy##4=az 2 2# 44= 4*52$ 7*@ B, 07|2S^
e MZ1|°I B
Hi ati2S4*4=7is HI! 2!yss#T sas ^aias
V—0035
V—0036
480V MCC-MC08A, 4y2# 4*4= $t S23:7ig A
480V MCC-MC08B, ab*2S 4*4= $i #2z7#a B
Hi 4H2##4=M* :IHI1 4y*2# 4*4=1!H Sf V-0025
V-0026
480V MCC-MC05A, 7452$7|@ A
480V MCC-MC05B,7|1 B
Alt except for ISLOCA and RVR
gsisj ohQMH| @ =4a|g2
SI-659125V DC-DC01 A, H
s ACR : 4y2s#4=7{* V.SI-660
125V DC-DC018. *169 21523. 7| a B
W^> 4y2#44=7|# lilt 4yy#a4=z ^si SI-675480V MCC-MC01A, 4149 45 4 3
7| s A
' SI-676480V MCC-MC01B, JfSdS
7#@ B
ills 4W2##^4# HX_ qyys#^a is71
HE01A 7171^24= 7|« A
HE01B 7|7|yz> 4=781 B
5.
Affected, System s 1:1:; ? > i 1: 1:: P ^ e . Support Systems
254*a7i|s mi ygyyTjg g*#^si RC101
RC102
125V DC - DC01C
125V DC - DC01D All except for LLOCA, MLOCA, ISLOCA and
liii ygygMs atisRC103 480V MCC - MC03A
RVR + Consequential SGTR in ATWS
RC104 480V MCC - MC03B
2005-05-08 42
6. sMgxmqoM
11 : C:Offi-pdfi : |i::?s^p^j£;Sysf4iS:S|i: |l|::ll;ll 1: IH
@5 1 4.16W SW01A, 57|2S[7|S Til AC.Vx-:; 3! i|^*#0)7|S fills #s@“
85 2 4.16kV SW01B, 125V DC DC01B, g7|
Hill S(Sf y *M4|oj7||e lllll 632 4#g} *flo)»S CH-239 H| IBS 125V DC01M,
CH-240 H| 1E5 125V DC01N, BS57|7||#
llll iF*f y lililM33|o|ga 40 3
yyss CH-501 480V MCC MC05A
CH-504 480V MCC MC05B
S(6f y 442|0M# v_qye§ CH-514 H| 1E5 MCC MC30N ATWS, SGTR
lllll SfSf y 4^410)7#* RWT S44B2 4B| CH-534 480V MCC MC01B
CH-536 480V MCC MC01A
cv am y :||1|1 #24£» B2B2 1 n| 1E3 MCC MC28N
BE 2 «l 1EB MCC MC28N
cv ifSf y *aw7|0)7ts Hill 25443 #ziao|s CH-203 125V DC DC01B
CH-205 125V DC DC01A
nSr
Systemisi: Major Components
RG-103 Class 1 Eg 125V 2-7?-S3 DC4-01A
RG-104 Class 1 Eg 125V DC4-01B
u«7|7|#
lllill 6Ef5iO|B 46 BalRG-105 Class 1 Eg 125V 3452 DC4-01C SGTR
RG-107 Class 1 Eg 125V B#40 DC4-01C
RG-108 Class 1 Eg 125V DC4-01D
2005-05-08 43
:y- G>;m:p<>06rits;*:: [.: :%'y: :<:) Vei^tyi ^x-:
01A 4.16kV SW01A, 125V DC 01A, g7|2n°A A,;i|i; 2E1f#2234=@S
02B 4.16kV SW01B. 125V DC 01B, 57|2 SITUS 783 B, 2234= *[#7)2-2
01B 125V DC01B, 253t *t#tiz-12234=78# PT_ E)gt?s si^tg:
02A 125V DC 01 A, 2234=^t^d2-2
V0044 125V DC 01C, 2334=*t#dz- 1 (cycling) SLOCA, LOFW, LOCV,
V0043 480V MCC 8-MC08A, 2234= *t#ti GTRN, LOOP, LSSB,2234=78# V ^-1 (cycling) SGTR, SBO, LOCCW,
V0045 480V MCC 8-MC08B. 2234= *[##1 LOKV, LODC,2-2(cycling)
VO 04 5 125V DC 01D, 2234=^(#d^- 2(cycling)
VO 03 5 125V DC 01A, 2234= *l#d2-1
V0036 125V DC 01B, 2234= *I#t|S-1#:;;g S!23=r^lS 2234= @3#2
V037 125V DC 01A, 2234= *t#£!:2-2
V038 125V DC 01B, 2234= *t#ti2-2
9.^34= J##
Affected- Systems Major Components Support Systems
FAT ?34=7|* fill 7|S34=BH 07 P ti| 1E3 13.8kV SW02N, «| 1E3 125V DC01N
111: 4^4=78# lllil;: ^34=^RISH131,133 125V DC01B, 3S57|78S
132, 134 - 125V DC01A, 3Rg7|78S SGTR, LOCV, GTRN,
F* ?^4=78# y_093 u| 1E3 480V MCC MC05N
LOCCW, LOKV
058 »l 1E3 480V MCC MC06N
1m ?34=7|@ #7|7|78Sga(DST) W47| u| 1E^ 13.8kV SW02M, »l 1E^ 13.8 kV SW02N
2005-05-08 44
10. y\n%
/ll.rlrllSUppPft^Sy Sfejti
171 480V MCC MC04A, 125V DC 01 A, 125V DC 01C
^#7|79S llfil; q]7|gnw2172
173
480V MCC MC04B, 125V DC 01B,125V DC 01 D
480V MCC MC04A, 125V DC 01A, 125V DC 01C
174 480V MCC MC04B, 125V DC 01B, 125V DC 01D
ill V.. E)aJ^Sj«H V1001-1008 H| 1ES 125V DC MC01M, 8#g7|7{ *SGTR, Consequential
SGTR, SLOCA
V105 480V MCC MC04A
v„. qpig^xtygeV106 480V MCC MC04B
V107 480V MCC MC04A
V108 480V MCC MC04B
11.S7|WS7i4le7t#
SD S7iws7|$ie7«s ^ya#4BlSH AV-005
MV-007
125VDC01A, °j^57|7lS
125V DC01A, 480V AC MCC MC04A
SD S7|u^7|*|#7(e ill HCBD AV-017 «1 1ES 125VDC01M, 54@7|2|# SGTR
SD S7|tijS7|$|#7lS ill hcbd goi^ysggAV-023 HI 1 Eh 125VDC01M. y^37|7is
SD S7|Wj97|-He7*S 1111:11 HCBD go| g5 P-022 h| 1 Eh 480V MCC MC02M
2005-05-08 45
la.g^Tis
StimpMerii'S [S tti: :S y St S ^ > I:!;: : I:::!
MP,APDC
1E3 4.1 6kV S34.16kV SW01A
4.16kV SW01B
DG 01 A, Unit Aux. XFMR TR01M, Standby Aux. XFMR TR02M
UU U1t5, AAU Uti Ulfc, unit AUX.
XFMR TR01 Nr Standby Aux. XFMR
f’fAPDC..;
6D_ 44HW3S c|l!S}3 7|
4.16kV SW01E
AAC DQ
AAC DQ 01E
125V DC, 07I2SWI*
MFAP,DC
344# •ill 434#St37|DG 01A
DG01B
125V DC, 7|7|yzt4=7lS, 571z$|t| S
125V DC, 7|7|yz{4=7ls, 57!2ES|7S#
480V AC LC LC01A 4.16kV SW01A
M-’AP,DC
344# 1EB 480V 3H34
480V AC LC LC01B
480V AC LC LC02A
4.16kV SW01B
4.16kV SW01A
480V AC LC LC02B 4.16kV SW01B
AAC 480V AC LC01E AAC AC LC 9-LC01A
480V AC MCC01A 480V AC LC 9-LC01A
480V AC MCC01B 480V AC LC 9-LC01B
AAC 480V MCC01E 4.16kV BUS SW01E
480V AC MCC02A 480V AC LC LC01A
480V AC MCC02B 480V AC LC LC01 B
AAC 480V MCC02E 4.16kV BUS SW02E
480V AC MCC03A 480V AC LC 9-LC01A
480V AC MCC03B 480V AC LC 9-LC01B
MP,mm
DC344* 1E3 480V SEJ443
4
480V AC MCC04A
480V AC MCC04B
480V AC LC 9-LC02A
480V AC LC 9-LC02B
480V AC MCC05A 480V AC LC 9-LC02A
480V AC MCC05B 480V AC LC 9-LC02B
480V AC MCC06A 480V AC LC 9-LC02A
480V AC MCC06B 480V AC LC 9-LC02B
480V AC MCC07A 480V AC LC 9-LC01A
480V AC MCC07B 480V AC LC 9-LC01B
480V AC MCC08A 480V AC LC 9-LC02A
480V AC MCC08B 480V AC LC 9-LC02B Subtree of HPSI, LPSI,eves, css, ccws,
ECWS, ESWS, AFWS, SCS, EPS, HVAC,
SDS, MSS, SGBDS, MEWS, RCGVS, SWS,
MP,AP fla?fim- 1P^ 1W t?Ai
125V DC 13-DC01A
125V DC 13-DC01B
AM 13-BT01A, AM 13-BC01A
AM 13-BT01B, AM #M 13- BC01B
2005-05-08 46
HP,:
ap,lie
MrDC
HI#0:DC
MP,AP,DC
Ml
AP,.DC
MP,APDO,
' '
DC
954 TUB
9^4 7||S
954 T«S
95473#
95473 =
9B471S
9a?73S
BC_
1 1— [=1 ItJV —1 TT
125V DC 13-DC01C ^9^i.13-BT0lC, #g7| 13-BC01C
RCGVSF, IAS (Hl2)
125V DC 13-DC01D 13-BT01D, 13-BC01D
Battery Charger BC01A 480V AC LC01A
Battery Charger BC01B
Battery. Charger BC01C
480V AC LC01BlEg 499 597|
480V AC LC02A
Battery Charger BC01D 480V AC LC02B
H|.1Eg 13.8kV 3- Unit Aux.. XFMR TR01M, Standby. Aux.
H| 1Eg 13.8kVSW02M
u| 1Eg 13.8W 3- SW02N
XFMRTR02M
Unit Aux. XFMR TR01 N„ Standby. Aux. XFMR TR02N
B| 1Eg 4.16kV 4- Unit Aux.. XFMR TR01M,. Standby Aux.
ti| 1Eg 4.16W SW02MB| 1 Eg. 4.16kV 4-
XFMR TR02MUnit Aux.. XFMR TR01N, Standby Aux.
SW02N XFMR TR02Nul.1E5.480V.AC 7-
LC11M H|.1Eg.4.16kV 4-SW02M
H| 1 Eg 480V AC 7- LC09N h|. 1 Eu. 4.16kV 4-SW02N
n| 1Eg 480V AC 7- LC1 ON 1Eg 4.16kV 4-SW02N
u| 1 Eh 480VE4
u| 1ES. 480V AC. 7- LC11N H| lEg 4.16kV 4-SW02N
H|.1Eg 480V AC 7- LC11M b[ 1Eg 13.8kV 3-SW02M
ul 1Eg 480V AC. 7- LC03N u| 1 Eg 13.8W 3-SW02N
u| 1 Eg 480V AC 7- LC05M h| 1 Eg. 13.8kV 3-SW02M
B| 1Eg 480V AC. 7- MC05N H| 1 Eg 480V LC7-LC11N
uf.1E5 480V AC 7- MC06N B| 1Eg 480V LC 7-LC11N
H| 1ES 480V. AC. 7- MC28N
h| 1 Eg 480V LC 7-LC10N
B|1Eg 480V HE4*30| -9IE4
u| 1Eg 480V AC. 7- MC30N
H| 1 Eg 480V LC 7-LC10N
u| 1 Eu 480V AC 7- MC06M 9.1 Eg 480V LC 7-LC03M
h| 1Eg 480V AC. 7- MC07N
u| 1Eg 480V LC 7-LC03N
u| 1 Eg 480V AC 7- LC10M u| 1Eg.13.8kV 3-SW02M
u| 1 Eg 125V DC #99 59?| 13-BC01M, *99 59u| 1Eg 125V 13-DC01M 7l 13-BC03M, #99 13-BT01M
H| 1Eg 125V DC 499 S97| 13-BC01N, #99 5913-DC01N 7| 13-BC03N, #99 13-BT01N
.13-BC01M
Agx| 6£7| 13-' BC03N
H| 1 Eg 480V LC 7-LC11MuhEg 499 597|
b| 1 Eg 480V LC 7-LC07N
2005-05-08 47
13.7}7|^44=711
Affected Systems Initiating Event
01 PA 4.16kV AC - SW01A, 125V DC-DC01A, S7|5$f7l|# 7j|^ A
01B 4.16kV AC - SW01B, 125V DC -7|7!y44=7j# P_ 7|7)yZ|f @5 DC01B, S7|5i}7«# 7|fl B
02PA 4.16kV AC - SW01A, 125V DC -DC01A, 57|5$l7«S 7#@ A
02PB 4.16kV AC - SW01B, 125V DC-DC01B, 57|5$t7«# 7*@ B
HX01A 7|7|yzf=l|f7l# 7|@ A
HX01B 7|7|yqsflf7|s 7|@ B
HX02A 7|7|yzf=i|4=7$# A7|7|U<44=71|# H' 7|7|yz{4= wm#7[
HX02B 7|7|yZMf7|# 7|^ BSubtree of 4 w4##
HX03A 717|yztei|4-75# 711 A 4=7i#, g^Ti#, if y^TlS, STiiyzfTl
HX03B 7|7|y4Sfl4=7)#71" B# (0|72)
SXISZJSHSPI f °J MOV 073 480V AC - MC01A7|7|y44=7ts S^12H
MOV 074 480V AC - MC01B
MOV 141
MOV 142
480V AC - MC01A, 3®}4^a#H|7|
7|7|y44=7fS V_fa
zjaiW=,*
480V AC - MC01B, 3*f4 2hg^u|7fl *
7|7|yzf4=7«5 V_S4=y47| Mf7| y
«Z|2|WS
MOV 095 480V AC - MC05A
MOV 096 480V AC - MC05B
7171^4 4=711# v_ r.m^g7| ^m#7[ MOV 105 480V AC - MC02A
MOV 106 480V AC - MC02B
14.717|yz|5l|T7|S
.: A ffected System s: Major Components Support Systems
01 PA 4.16kV AC - SW01A, 125V DC - DC01A, 37|S$17|# 7*« A
4.16kV AC - SW01A, 125V DC -02PA7l7|uzt5g^7||# p 7|7|yztii|4=®5 DC01A, 37|Z#7## 7|« A
4.16kV AC - SW01B, 125V DC - DC01B, g7|2#7{# 7#™ B
4.16kV AC - SW01B, 125V DC -
Subtree of 7|7|y4f711* (u|2) '
01PB
02PB DC01B, 37|ZSM* 7«S B
2005-05-06 48
:: iA:ffe'di;£&:SVst>to-S::> ::y: •:: .'i:;:S'UPP'Oft:>Sy-S-teili iv;: lAitiAWn#. :EVe%i>:
PP01A 480V AC MC05A
B4y44S ### a4y4@EPP02A 480V AC MC05A
PP01B 480V AC MC05B
PP02B 480V AC MC05B Subtree of 3^1?
CH01A 4.16kV AC SW01A, 480V AC MV05A, 125V DC DC01A, CCWS
# M2)
B4-y44* B4=y4=yz{7iCH02A
CH01B
4.16W AC SW01A, 480V AC MV05A, 125V DC DC01A, CCWS
4.16kV AC SW01 B, 480V AC MV05B, 125V DC DC01B, CCWS
CH02B 4.16kV AC SW01B, 480V AC MV05B, 125V DC DC01B, CCWS
16.57|3ESW*
:;!% \StipP bftySysterh iS;:;!:!:: . Initiating Event
VY{?)Hi-yic^az)7j|« 7|71B .'37|5EJtt4S 959945929
be a ayzj7i y
be b gyB7i y
480V AC MC05A, #4yi4SlS SIW A
480V AC MC05B, H4I34SIS Slg B
ti|9ic9y44S 7| mm 459@#44*9E BE A 4'y47| y 480V AC MC05A, 814)34SIS Slg Avi\a 7|# g7|Z#4* . a
BE B 4'9B7| y 480V AC MC058, 814)34= SIS Slg 8
VY{?> ui-yic-yy^Tis 7| 7IB g7|si)4S
ifiiii 299945929Be A 4'y47| y
BE b ay47i y
480V MCC MC05A, #4)34= SIS Sl“ A
480V MCC MC05B, B4S34SIS SIS 8
7| 1111 E2gt SN7# a be ia ay 47i y 480V MCC MC01A, B4S34SIS SI5 A
7|B 37|3L£(4B Itl
IU>
be 2b ayzM y 480V MCC MC01B, #4S34SIS Sg B
VY<7) H|9E9y44* 7|7IB 37i5E£|4S @9929
BE ia 9y 47| y 480 V MCC MC05A, M4S4SIS SIS A
be ib 4!y^7i y 480 V MCC MC05B, #4y4SIS SIS 8
ui-y^ByztTi# 7j 7|B 37l2£)4S
be a ayB7i y
BE b tiy47i y
480 V MCC MC06A, #4)34318 SI s A
480 V MCC MC068, #4!343IS Sl“ 8VY{?) 1111 7|7|yz
Subtree ofS, 7|7|UjZ*44#, £|#5 ^19444*. 4 52eiK"4S, @%iy 94*. 352*9454 B, 9559454S,
VY{?) C|^@t97|# 57|3 S)4B
1111 q^s97ia a57|s $)4S
03A,05A
2## oH7|5fl 04A, 06A
480V MCC MC02A
480V MCC MC02A
qsws7ia 57i$ lilii 4#g,*97|9 B57|S03B,
05B 480V MCC MC02B94354*. 7|7|yz*
S#4* £)4S 2Sg “H7|y 04B,
06B
2ig B7[y
480V MCC MC02B(H|2)
15CE
17CE
480V MCC MC02E
480V MCC MC01E
2005-05-08 49
VY(?) qg^xpi*! =7|s 19CE 480V MCC MC02ESMIS 7|^ g7|Z#7|e
2§ o “»7|at
1 6CE 480V MCC MC02E
18CE 480V MCC MC01E
20CE 480V MCC MC02E
7|7|yzj4=6#-M5 57|$# g yy«7||
sAC_ 7|7iyz}4= i(^52
# 3713# Tflg.
7|7|gzii#=?=flH A a# 37|3#7S*.S
7| at7|7|y#5i|4=@” ba# g7|3#7ie g
7\M
480V. AC MC07A
480V AC. MC07B
17.1 7M#
Affected Systems •:• Initiating:Event".. .•
CM 01
CM02
u| 1 Eg 4.16kV SW02M, «l 1 Eg 480V
2f#37|7|* MC_ 37|gfS?7|AC MC06M, TBCCW
u| 1 Eg 4.16kV SW02N, "I 1Eg AC MC07N. TBCCW
480V Subtree of ## % ^0j7|S,
A DP-01 S u| 1 Eg 480V AC MC06M4#7|7|#. =7|ttta7| ?IS7j* (H|T2)
y^57|7!IS MD_ #7|aZ7|
ADP-02S o] Class 1 Eg 480V AC MC23N
i8.°ig^g!ga
. Affected .Systems:. :-:Si^pb!A:::S^sientSy ijili ;i: V-
efg^gjga HHe1E g @7| BUS Tie- 480V HE4 *»(X y. i|t§7jffi. srtgg
7|*LLOCA, SLOCA, SQTR
2005-05-08 50
Transients with PCS Available (ReactorTable 2(1) SDP Worksheet for Farley Nuclear Plant — Trip) (TRANS)
Estimated Frequency (Table 1 Row) Exnosure Time Table 1 Result (circle):ABCDEFGH
Safety Functions Needed: Full Creditable Mitigation Canabilitv for Each Safety Function:
SGs with 1/5
or action = 3)
Power Conversion System (PCS) 1/2 Main Feedwater trains with 1/3 condensate trains (operator action = 2)Secondary Heat Removal (AFW) 1/2 MDAFW trains (1 multi-train system) or 1/1 TDAFW train (1 ASD train) to 2/3
SG safety valves on each SG fed by AFW(I)
Early Inventory, High Pressure Injection (EIHP) 1/2 charging trains or use of spare charging pump (1 multi-train system)(2)Primary Heat Removal, Feed/Bleed (FB) 1/2 PORVs open for Feed/Bleed (operator action = 2)High Pressure Recirculation (HPR) 1/2 charging trains with 1/2 RHR trains and with operator action for switchover (opera
Circle Affected Functions Recovery of Remaining Mitigation Canabilitv Rating for Each Affected Sequence
1 TRANS - PCS - AFW - HPR (4)
Failed Train Sequence Color
2 TRANS-PCS-AFW-FB (5)
3 TRANS - PCS - AFW - EIHP (6)
Identify any operator recovery actions that are credited to directly restore the degraded equipment or initiating event:
If operator actions are required to credit placing mitigation equipment in service or for recovery actions, such credit should be given only if the following criteria are met: 1) sufficient time is available to implement these actions, 2) environmental conditions allow access where needed, 3) procedures exist, 4) training is conducted on the existing procedures under conditions similar to
the scenario assumed, and 5) any equipment needed to complete these actions is available and ready for use.
53
Table 2(2) SDP Worksheet for Farley Nuclear Plant Transients with Loss of PCS (TPCS)
Estimated Frequency (Table 1 Row) Exuosure Time Table 1 Result (circle):
ABCDEFGH
Safety Functions Needed:
Secondary Heat Removal (AFW)
Early Inventory, High Pressure Injection (EIHP) Primary Heat Removal, Feed/Bleed (FB)High Pressure Recirculation (HPR)
Full Creditable Mitigation Canabilitv for Each Safety Function:
1/2 MDAFW trains (1 multi-train system) or 1/1 TDAFW train (1 ASD train) to 2/3 SGs with 1/5 SG safety valves on each SG fed by AFW(I)1/2 charging pumps or use of spare charging pump (1 multi-train system)(2)
1/2 PORVs open for Feed/Bleed (operator action = 2)1/2 charging pumps with 1/2 RHR pumps and with operator action for switchover (operator action = 3)
Circle Affected Functions Recovery of Remaining Mitigation Canabilitv Rating for Each Affected SequenceFailed Train Sequence Color
1 TPCS-AFW-HPR (3)
2 TPCS - AFW - FB (4)
3 TPCS - AFW - EIHP (5)
Identify any operator recovery actions that are credited to directly restore the degraded equipment or initiating event:
If operator actions are required to credit placing mitigation equipment in service or for recovery actions, such credit should be given only if the following criteria are met: 1) sufficient time is
available to implement these actions, 2) environmental conditions allow access where needed, 3) procedures exist, 4) training is conducted on the existing procedures under conditions similar to the scenario assumed, and 5) any equipment needed to complete these actions is available and ready for use.
54
Table 2(3) SDP Worksheet for Farley Nuclear Plant — Small LOCA (SLOCA)
Estimated Frequency (Table 1 Row) Exposure Time Table 1 Result (circle):ABCDEFGH
Safety Functions Needed: Full Creditable Mitigation Capability for Each Safety Function:Early Inventory, HP Injection (EIHP) 1/2 charging trains or use of spare charging pump (1 multi-train system)(l)
Secondary Heat Removal (AFW) 1/2 MDAFW trains (1 multi-train system) or 1/1 TDAFW train (1 ASD train)RCS Cooldown / Depressurization (DEP1) Operator depressurizes RCS using 1/2 PORVs (operator action = 2)
RCS Cooldown / Depressurization (DEP2) Operator depressurizes RCS by using 1/2 PORVs and by opening 2 /3 ARVs (operator action = 2)
Primary Heat Removal, Feed/Bleed (FB) 1/2 PORVs open for Feed/Bleed (operator action = 2)
Low Pressure Injection (LPI) 1/2 RHR trains (1 multi-train system)
High Pressure Recirculation (HPR) 1/2 charging trains with 1/2 RHR trains and with operator action for switchover (operator action = 3)
Low Pressure Recirculation (LPR) 1/2 RHR trains with operator action for switchover (operator action = 3)
Circle Affected Functions Recovery of Remaining Mitigation Canabilitv Rating for Each Affected Sequence
1 SLOCA-LPR (2,9)
Failed Train Sequence Color
2 SLOCA-DEP1 - HPR (4)
3 SLOCA-AFW-HPR (6)
4 SLOCA-AFW-FB (7)
5 SLOCA-EIHP-LPI (10)
6 SLOCA-EIHP-DEP2 (11)
7 SLOCA-EIHP-AFW (12)
55
Table 2(4) SDP Worksheet for Farley Nuclear Plant — Stuck Open PORV (SORV)(l)
Estimated Frequency (Table 1 Row) Exposure Time Table 1 Result (circle):ABCDEFGH
Safety Functions Needed: Full Creditable Mitigation Canabilitv for Each Safety Function:
)r action = 3)
Isolation of Small LOCA (BLK) The closure of the block valve associated with stuck open PORV (1 train)(2)Early Inventory, HP Injection (EIHP) 1/2 charging trains or use of spare charging pump (1 multi-train system)(3)Secondary Heat Removal (AFW) 1/2 MDAFW trains (1 multi-train system) or 1/1 TDAFW train (1 ASD train)
RCS Cooldown / Depressurization (DEP1) Operator depressurizes RCS(4) (operator action = 2)
RCS Cooldown / Depressurization (DEP2) Operator depressurizes RCS by opening 2/3 ARVs (4) (operator action = 2)
Primary Heat Removal, Feed/Bleed (FB) Operator carries out Feed/Bleed ^ (operator action = 2)
Low Pressure Injection (LPI) 1/2 RHR trains (1 multi-train system)
High Pressure Recirculation (HPR) 1/2 charging trains with 1/2 RHR trains and with operator action for switchover (operate
Low Pressure Recirculation (LPR) 1/2 RHR trains with operator action for switchover (operator action = 3)
Circle Affected Functions Recovery of Remaining Mitigation Canabilitv Rating for Each Affected Sequence
1 SORV - BLK - LPR (2, 9)
Failed Train Sequence Color
2 SORV - BLK - DEP1 - HPR (4)
3 SORV-BLK-AFW-HPR (6)
4 SORV-BLK-AFW-FB (7)
5 SORV - BLK - EIHP - LPI (10)
6 SORV - BLK - EIHP - DEP2 (11)
7 SORV - BLK - EIHP - AFW (12)
56
Table 2(5) SDP Worksheet for Farley Nuclear Plant Medium LOCA (MLOCA)
Estimated Frequency (Table 1 Row) Exposure Time Table 1 Result (circle):ABCD EFGH
Safety Functions Needed:Early inventory, HP Injection (EIHP)Secondary Heat Removal (AFW)RCS Depressurization (DEP1)RCS Depressurization (DEP2)Accumulators (ACCU)Low Head Injection (LHI)High Pressure Recirculation (HPR)Low Pressure Recirculation (LPR)
Full Creditable Mitigation Capability for Each Safety Function:1/2 charging trains or use of spare charging pump (1 multi-train system) ^
1/2 MDAFW trains (1 multi-train system) or 1/1 TDAFW train (1 ASD train)2/3 ARVs (operator action = 1)(2)2/3 ARVs (operator action = 3)(3)2/2 remaining accumulators ^ (1 train)
1/2 RHR trains (1 multi-train system)1/2 charging trains with 1/2 RHR trains and with operator action for switchover (operator action = 3) 1/2 RHR trains with operator switchover from injection to recirculation (operator action = 3)
Circle Affected Functions Recovery of Remaining Mitigation Capability Rating for Each Affected SequenceFailed Train Sequence Color
1 MLOCA - LPR (2, 8)
2 MLOCA - DEP2 - HPR (4)
3 MLOCA - AFW - HPR (6)
4 MLOCA - EIHP - LHI (9)
5 MLOCA - EIHP - ACCU (10)
6 MLOCA - EIHP - DEP1 (11)
7 MLOCA-EIHP-AFW (12)
57
Table 2(6) SDP Worksheet for Farley Nuclear Plant Large LOCA (LLOCA)
Estimated Frequency (Table 1 Row) Exuosure Time Table 1 Result (circle):ABCDEFGH
Safety Functions Needed:Accumulators (ACCU)Early Inventory, LP Injection (EILP)Low Pressure Recirculation (LPR)
Full Creditable Mitigation Capability for Each Safetv Function:2/2 remaining accumulators(l) (1 train)
1/2 RHR trains (1 multi-train system)
1/2 RHR trains with operator switchover from injection to recirculation (operator action = 3)
Circle Affected Functions Recovery of Remaining Mitigation Capability Rating for Each Affected SequenceFailed Train Sequence Color
1 LLOCA-LPR (2)
2 LLOCA-EILP (3)
3 LLOCA-ACCU (4)
Identify any operator recovery actions that are credited to directly restore the degraded equipment or initiating event:
If operator actions are required to credit placing mitigation equipment in service or for recovery actions, such credit should be given only if the following criteria are met: 1) sufficient time is
available to implement these actions, 2) environmental conditions allow access where needed, 3) procedures exist, 4) training is conducted on the existing procedures under conditions similar to
the scenario assumed, and 5) any equipment needed to complete these actions is available and ready for use.
58
Table 2(7) SDP Worksheet for Farley Nuclear Plant Loss of Offsite Power (LOOP)
Estimated Frequency (Table 1 Row) Exposure Time Table 1 Result (circle):ABCDEFGH
Safety Functions Needed: Full Creditable Mitigation Canabilitv for Each Safety Function:Emergency AC Power (FAC) 1/1 dedicated EDG (1 train) or 1/1 swing EDG (operator action =1)(1)
Turbine-driven AFW Pump (TDAFW) 1/1 TDP trains of AFW with 2/3 ARVs (1 ASD train)
Secondary Heat Removal (AFW) 1/2 MDAFW trains (1 multi-train system) or 1/1 TDAFW train (1 ASD train)
Recovery of AC Power in < 1 hr (REC1) Recovery of AC power within 1 hour (operator action = 1)(2)
Recovery of AC Power in < 5 hrs (REC5) Recovery of AC power within 5 hours (operator action = 1)(3,4)
Early Inventory, HP Injection (EIHP) 1/2 charging pumps or use of spare charging pump (1 multi-train system)(5)
Primary Heat Removal (FB) Operator uses 1/2 pressurizer PORVs (operator action = 2)
High Pressure Recirculation (HPR) 1/2 charging pumps with 1/2 RHR pumps and with operator action for switchover (operatoraction = 3)
Circle Affected Functions Recovery of Remaining Mitigation Canabilitv Rating for Each Affected Sequence
1 LOOP - AFW - HPR (3)
Failed Train Sequence Color
2 LOOP-AFW-FB (4)
3 LOOP-AFW-EIHP (5)
4 LOOP - EAC - HPR (7, 11) (AC recovered)
5 LOOP - EAC - EIHP (8,13) (AC recovered)
6 LOOP - EAC - REC5 (9)
7 LOOP - EAC - TDAFW - FB (12)(AC recovered)
8 LOOP - EAC - TDAFW - REC1 (14)
59
Table 2(8) SDP Worksheet for Farley Nuclear Plant Steam Generator Tube Rupture (SGTR)(I)
Estimated Frequency (Table 1 Row) Exposure Time Table 1 Result (circle):ABCDEFGH
Safety Functions Needed: Full Creditable Mitigation Capability for Each Safety Function:Secondary Heat Removal (AFW)Early Inventory, HP Injection (EIHP)Pressure Equalization (EQ)
Feed-and-Bleed (FB)High Pressure Recirculation (HPR)
(1/2 MDPs of AFW or 1/1 TDP of AFW) with 2/3 ARVs (operator action = 3)1/2 charging pumps or use of spare charging pump (1 multi-train system)(2)
Operator isolates the ruptured SG and depressurizes RCS using 1/1 SG ARV (on each SG fed by AFW) to less than setpoint of relief valves of SG (1 train)(3)
Operator uses 1/2 pressurizer PORVs (operator action = 1)(4)
1/2 RHR trains with 1/2 charging pumps and with switchover to recirculation (operator action = 3)
Circle Affected Functions Recovery of Remaining Mitigation Capability Rating for Each Affected Sequence
1 SGTR - EIHP - EQ (3)
Failed Train Sequence Color
2 SGTR - AFW - HPR (5)
3 SGTR-AFW-FB (6)
4 SGTR-AFW-EIHP (7)
60
Table 2(9) SDP Worksheet for Farley Nuclear Plant Anticipated Transients without Scram (ATWS)
Estimated Frequency (Table 1 Row) Exposure Time Table 1 Result (circle):ABCDEFGH
Safety Functions Needed: Full Creditable Mitigation Capability for Each Safety Function:Turbine trip (TTP)Secondary Heat Removal (AFW)
Primary Relief (SRV)Emergency Boration (EMBO)
AMS AC system trips the turbine and starts AFW pumps (1 train)2/2 MDPs of AFW with 1/1 TDP of AFW (1 ASD train) to 3 SGs with 4/5 SG safety valves open on each SG3/3 SRVs with 2/2 PORVs open (1 train)Operator conducts emergency boration using 1/2 charging pumps with 1/2 boric acid transfer pumps (operator action = 2)
Circle Affected Functions Recovery of Remaining Mitigation Capability Rating for Each Affected SequenceFailed Train Sequence Color
1 ATWS-EMBO (2)
2 ATWS-SRV (3)
3 ATWS-AFW (4)
4 ATWS - TTP (5)
61
Table 2(10) SDP Worksheet for Farley Nuclear Plant — Main Steam Line Break Outside Containment (MSLB)
Estimated Frequency (Table 1 Row) Exposure Time Table 1 Result (circle):ABCDEFGH
Safety Functions Needed: Full Creditable Mitigation Capability for Each Safety Function:MSLB Isolated (MSIV)(1) 2/3 steam paths close(2) (1 multi-train system)Early Inventory, HP Injection (EIHP) 1/2 charging trains or use of spare charging pump (1 multi-train system)(3)Secondary Heat Removal (AFW) 1/2 MDAFW trains (1 multi-train system) or 1/1 TDAFW train (1 ASD train)Feedwater valves close (FWVC) Operators close the valves feeding the SG whose MSIV did not close (1 train)(4)Stop Injection (STIN) Operators stop high pressure injection (operator action = 2)(5)Primary Heat Removal, Feed/Bleed (FB) 1/2 PORVs open for Feed/Bleed (operator action = 2)High Pressure Recirculation (HPR) 1/2 charging trains with 1/2 RHR trains and with operator action for switchover (operator action = 3)
Circle Affected Functions Recovery of Remaining Mitigation Canabilitv Rating for Each Affected Sequence
1 MSLB - FWVC - STIN (3)
Failed Train Sequence Color
2 MSLB-AFW-HPR (5)
3 MSLB - AFW - FB (6)
4 MSLB - EIHP - FWVC (8)
5 MSLB-EIHP-AFW (9)
6 MSLB - MSIV (10)
62
Table 2(11) SDP Worksheet for Farley Nuclear Plant — Loss of On-Service Train of Cooling (LOTC)(1)
Estimated Frequency (Table 1 Row) Exposure Time Table 1 Result (circle):ABCDEFGH
Safety Functions Needed: Full Creditable Mitigation Capability for Each Safety Function:RCP Trip (RCPT) Operator trips RCPs in less than 3 minutes after loss of cooling (operator action - 2)Off-service Train (OFST) Operator aligns mitigating equipment to the off-service train and provides RCP seal cooling (operator
action = 1)®
Secondary Heat Removal (AFW) 1/2 MDAFW trains (1 multi-train system) or 1/1 TDAFW train (1 ASD train)Early Inventory, HP Injection (EIHP) 1/1 charging pump or use of spare charging pump (1 train)(3)RCS Cooldown / Depressurization (DEP1) Operator depressurizes RCS using 1/2 PORVs (operator action = 2)
RCS Cooldown / Depressurization (DEP2) Operator depressurizes RCS by using 1/2 PORVs and by opening 2/3 ARVs (operator action = 2)
Primary Heat Removal, Feed/Bleed (FB) 1/2 PORVs open for Feed/Bleed (operator action = 2)
Low Pressure Injection (LPI) 1/1 RHR train (1 train) .
High Pressure Recirculation (HPR) (1/1 charging train or use of spare charging pump) ® with 1/1 RHR train and with operator action forswitchover (1 train)(4)
Low Pressure Recirculation (LPR) 1/1 RHR train with operator action for switchover (1 train)(4)
Circle Affected Functions Recovery of Remaining Mitigation Canabilitv Rating for Each Affected Sequence
1 LOTC - AFW - HPR (3,16)
Failed Train Sequence Color
2 LOTC-AFW-FB (4,17)
3 LOTC-AFW-EIHP (5,18)
4 LOTC-OFST (6,19)
5 LOTC - RCPT - LPR (8,12)
6 LOTC - RCPT - DEP1 - HPR (10)
7 LOTC - RCPT - EIHP - LPI (13)
8 LOTC - RCPT - EIHP - DEP2 (14)
63
Table 2(12) SDP Worksheet for Farley Nuclear Plant — Loss of Instrument Air (LIA)(1)
Estimated Frequency (Table 1 Row) Exposure Time Table 1 Result (circle):ABCDEFGH
Safety Functions Needed:RCP Seal Injection and HP Injection (EIHP)
Secondary Heat Removal (AFW)
Full Creditable Mitigation Capability for Each Safety Function:1/2 charging trains or use of spare charging pump provide RCP seal injection and high-pressure injection (1 multi-train system)®
1/2 MDAFW trains (operator action = 2)(3)
Circle Affected Functions Recovery of Remaining Mitigation Capability Rating for Each Affected SequenceFailed Train Sequence Color
1 LIA - AFW (2)
2 LIA - EIHP (3)
Identify any operator recovery actions that are credited to directly restore the degraded equipment or initiating event:
If operator actions are required to credit placing mitigation equipment in service or for recovery actions, such credit should be given only if the following criteria are met: 1) sufficient time is available to implement these actions, 2) environmental conditions allow access where needed, 3) procedures exist, 4) training is conducted on the existing procedures under conditions similar to
the scenario assumed, and 5) any equipment needed to complete these actions is available and ready for use.
64
Table 2(13) SDP Worksheet for Farley Nuclear Plant — Loss of a DC Bus (LBDC)(,)
Estimated Frequency (Table 1 Row) Exposure Time Table 1 Result (circle):ABCDEFGH
Safety Functions Needed: Full Creditable Mitigation Canabilitv for Each Safety Function:Early Inventory, HP Injection (EIHP) 1/1 charging train or use of spare charging pump (1 train)®
Secondary Heat Removal (AFW) 1/1 MDAFW train (1 train) or 1/1 TDAFW train (1 ASD train)
RCS Cooldown / Depressurization (DEP) Operator depressurizes RCS by using 1/1 remaining PORV and by opening 2/3 ARVs (operator action= 1)(3)
Primary Heat Removal, Feed/Bleed (FB) 1/1 remaining PORV open for Feed/Bleed (operator action = 2)
Low Pressure Injection (LPI) 1/1 RHR train (1 train)
High Pressure Recirculation (HPR) (1/1 charging train or use of spare charging pump) ^ with 1/1 RHR train and with operator action forswitchover (1 train)(4)
Low Pressure Recirculation (LPR) 1 /1 RHR train with operator action for switchover (1 train)(4)
Circle Affected Functions Recovery of Remaining Mitigation Canabilitv Rating for Each Affected Sequence
1 LBDC - AFW - HPR (3)
Failed Train Sequence Color
2 LBDC-AFW-FB (4)
3 LBDC - EIHP - LPR (6)
4 LBDC - EIHP - LPI (7)
5 LBDC - EIHP - DEP (8)
6 LBDC - EIHP - AFW (9)
65
Table 2(14) SDP Worksheet for Farley Nuclear Plant Loss of 4160 V Bus F or G (LBAC) (i)
Estimated Frequency (Table 1 Row) Exnosure Time Table 1 Result (circle):ABCDEFGH
Safety Functions Needed: Full Creditable Mitigation Capability for Each Safety Function:RCP Trip (RCPT) Operator trips RCPs in less than 3 minutes after loss of cooling (operator action = 2)Off-service Train (OFST) Operator aliens mitigating equipment to the off-service train and provides RCP seal cooling (operator
action = 1)®
Secondary Heat Removal (AFW) 1/1 MDAFW train (1 train)Early Inventory, HP Injection (EIHP) 1/1 charging pump or use of spare charging pump (1 train)(3)RCS Cooldown / Depressurization (DEP1) Operator depressurizes RCS using 1/1 remaining PORV (1 train)(4)
RCS Cooldown / Depressurization (DEP2) Operator depressurizes RCS by using 1/1 remaining PORV and by opening 2/3 ARVs (1 train)(4)
Primary Heat Removal, Feed/Bleed (FB) 1/1 remaining PORV open for Feed/Bleed (1 train)(4)
Low Pressure Injection (LPI) 1/1 RHR train (1 train)
High Pressure Recirculation (HPR) (1/1 charging train or use of spare charging pump)(3) with 1/1 RHR train and with operator action forswitchover (1 train)(5)
Low Pressure Recirculation (LPR) 1/1 RHR train with operator action for switchover (1 train)(5)
Circle Affected Functions Recovery of Remaining Mitigation Cauabilitv Rating for Each Affected Sequence
1 LBAC-AFW-HPR (3, 16)
Failed Train Sequence Color
2 LBAC - AFW - FB (4,17)
3 LBAC - AFW - EIHP (5,18)
4 LBAC - OFST (6,19)
5 LBAC - RCPT - LPR (8,12)
6 LBAC - RCPT - DEP1 - HPR (10)
7 LBAC - RCPT - EIHP - LPI (13)
8 LBAC - RCPT - EIHP - DEP2 (14)
66
Table 2(15) SDP Worksheet for Farley Nuclear Plant — LOOP with Loss of 4160 V Bus F or G (LEAC)(I)
Estimated Frequency (Table 1 Row) Exposure Time Table 1 Result (circle):ABCDEFGH
Safety Functions Needed: Full Creditable Mitigation Capability for Each Safety Function:PORV Recloses (PORV) 2/2 Pressurizer PORVs reclose after opening during transient (1 train)Secondary Heat Removal (AFW) 1/1 MDAFW train (1 train)Early Inventory, HP Injection (EIHP) 1/1 charging train or use of spare charging pump (1 train)(2)RCS Cooldown / Depressurization (DEP) Operator depressurizes RCS by opening 2/3 ARVs (operator action = 2)
Primary Heat Removal, Feed/Bleed (FBI) 1/1 remaining PORV open for Feed/Bleed (1 train)(3)Primary Heat Removal, Feed/Bleed (FB2) Operator carries out Feed/Bleed(4) (operator action = 2)
Low Pressure Injection (LPI) 1/1 RHR train (1 train)High Pressure Recirculation (HPR) (1/1 charging train or use of spare charging pump)(2) with 1/1 RHR train and with operator action for
switchover (1 train)(5)
Low Pressure Recirculation (LPR) 1/1 RHR train with operator action for switchover (1 train)(5)
Circle Affected Functions Recovery of Remaining Mitigation Cauabilitv Rating for Each Affected Sequence
1 LEAC - AFW - HPR (3, 13)
Failed Train Sequence Color
2 LEAC - AFW - FBI (4)
3 LEAC-AFW-EIHP (5, 15)
4 LEAC - PORV - LPR (7, 9)
5 LEAC - PORV - EIHP - LPI (10)
6 LEAC - PORV - EIHP - DEP (11)
7 LEAC - PORV - AFW - FB2 (14)
67
Interfacing SystemsTable 2(16) SDP Worksheet for Farley Nuclear Plant — LOCA (ISLOCA)(1)
Estimated Frequency (Table 1 Row) _________________ Exposure Time _________________ Table 1 Result (circle):ABCDE FGH
Safety Functions Needed: Full Creditable Mitigation Capability for Each Safety Function:RHR Hot Leg Suction Line Isolation Valves2 Low Pressure Injection System3 Residual Heat Removal System3 High Pressure Injection System (suction)3 Chemical and Volume Control System (suction)3Component Cooling Water System (thermal barrier heat exchanger)3
Circle Affected Functions Recovery of Remaining Mitigation Capability Rating for Each Affected SequenceFailed Train Sequence Color
Identify any operator recovery actions that are credited to directly restore the degraded equipment or initiating event:
If operator actions are required to credit placing mitigation equipment in service or for recovery actions, such credit should be given only if the following criteria are met: 1) sufficient time is
available to implement these actions, 2) environmental conditions allow access where needed, 3) procedures exist, 4) training is conducted on the existing procedures under conditions similar to
the scenario assumed, and 5) any equipment needed to complete these actions is available and ready for use.
68
^ *1 ^ s. <£ >4**7l4££44£ 4 44 4*37-1 * 5
KINS/RR-304
45/441
** 44£
****-714 441* 4 441**7}
4*7} 4 ***
* * 4 4*
41 °1 7-1 80 p.
*414 4* 4* 4 #* *4 *4
4441*: *4*4* 54l7l*7l|4 PJI^)41*441*: -@* 44 **** *7} 441*# 7H# (*415)
°l*-5
4*714 44*44 4*71** 4** 2005* 14
£ 5 * (0), * ( ) 3 7l 210mmx297mm
*37}*
ti]^4 «- *4 (O), til^7l) ( )
*4*4*4
*3# #5 y^S-JlA-l
41 4 * 435 (2004* 414)
*4 NRC4I4 4-§-4ji 534 <** Aizi-5. 44 4* (SDP)5 *£3*£# 4
4 441*7} * *4 41441 *-§-#4 if414 M^4 £4-4* 413** 4* 4
5-4 5-41*4:44-. 444 3 SDP *7}* 45*4 4# 44*4 #4 4#4 5
5 *4* *£3 4£41 4# *414* SDP *41 4*41 44 **44 ££7} 4
4- * 4*414* 44 NRC4 4* *4* £4£ 44 SDP *414 4* 4*4
4*# 4-443 *4 *5*5 *£4-3.4- 444- 7)144££45 4414 4* 44
# *1143 445 4444 *3 3444## 441 *3£ *7}4*4 3*4 *
4*4- £4 441 44 541*44 5* 53# *££ 44 2*4 441*4# **
444-
*41* 4*3 (1044 44)
4* **£ #*, 4##* 4*4*7}, **£*£ #5 541, 4*3 *£, 5*1*5
BIBLIOGRAPHIC INFORMATION SHEET
Performing Org. Report No.
Sponsoring Org. Report No.
KINS/RR-304
Title/Subtitle
Background and procedure analysis for threshold of safety significance determination
Sponsoring Org. Project and
Project Manager
Development of risk-informed regulation technology (K. Y. Sung)
Researcher and Dep't. C. }. Lee (Nuclear Safety Research Department)
Pub.Place
Daejon Pub. Org. KINS Pub. Date 2005. 1.
Page 80 p. 11. and Tab. Yes (O), No ( ) Size 210mm x297mm
Note
Classified Unclassified(O), Classified( ) Report Type Research Report
Sponsoring Org. Contract No.Abstract (About 200 Words)
The safety significance determination process (SDP), being applied by USNRC, is one of regulatory approaches which can improve the regulatory effectiveness and efficiency by utilizing the risk information to any regulatory inspections and issue resolution. The decision-making criteria and some risk thresholds for the determination of significance can be, therefore, essential elements in actual SDP implementation. Based on USNRCs experiences, this study has the purpose to identify the rationale and background for the determination of significance and to check the feasibility of the implementation to Korean nuclear power plants. Our attentions have been basically concentrated on establishing its step-by-step processes, identifying the current issues, and assessing major issues for the application to domestic plants. Practically, two examples have been analyzed after consulting the database on our actual regulatory inspections and incidents.
Subject Keywords (About 10 Words)
safety significance determination, probabilistic safety assessment, risk-informed regulation, risk measure, regulatory inspection