D6.3: Final Project Report | 5GROWTH
-
Upload
khangminh22 -
Category
Documents
-
view
0 -
download
0
Transcript of D6.3: Final Project Report | 5GROWTH
H2020 5Growth Project
Grant No. 856709
D6.3: Final Project Report
Abstract
This report constitutes the nonfinancial part of the Final Report to be delivered two months
after the end of the period (M33).
D6.3: Final Project Report 2
H2020-856709
Document properties
Document number D6.3
Document title Final Project Report
Document responsible Carlos J. Bernardos (UC3M)
Document editor Carlos J. Bernardos (UC3M)
Editorial team Carlos J. Bernardos (UC3M), Jesús Alonso (INNOVALIA) Andrés
García-Saavedra (NEC), Manuel Lorenzo (ERC), Diego San Cristobal
(ERC), Diego López (TID), Josep Mangues-Bafalluy (CTTC), Paola
Iovanna (TEI), Jim Miller (IDCC)
Target dissemination level PU
Status of the document Final
Version 1.0
Delivery date 28th February, 2022
Actual delivery date 28th February, 2022
Production properties
Reviewers Claudio Cassetti (POLITO), Antonio de la Oliva (UC3M)
Disclaimer
This document has been produced in the context of the 5Growth Project. The research leading to
these results has received funding from the European Community's H2020 Programme under grant
agreement Nº H2020-856709.
All information in this document is provided “as is" and no guarantee or warranty is given that the
information is fit for any particular purpose. The user thereof uses the information at its sole risk and
liability.
For the avoidance of all doubts, the European Commission has no liability in respect of this document,
which is merely representing the authors’ view.
D6.3: Final Project Report 3
H2020-856709
Contents List of Figures ......................................................................................................................................................................... 5
List of Tables ........................................................................................................................................................................... 7
List of Acronyms ................................................................................................................................................................... 8
Executive Summary ............................................................................................................................................................ 11
1. Summary for publication ............................................................................................................................................ 12
1.1. Summary of the context and overall objectives of the project ............................................................ 12
1.1.1. Project context ................................................................................................................................................ 12
1.1.2. Project objectives ........................................................................................................................................... 12
1.2. Work performed from the beginning of the project to the end of the period covered by the
report and main results achieved so far ................................................................................................................ 13
1.3. Progress beyond the state of the art, expected results until the end of the project and
potential impacts (including the socio-economic impact and the wider societal implications of
the project so far) .......................................................................................................................................................... 15
2. Dissemination activities ............................................................................................................................................... 17
2.1. Publications and technical dissemination .................................................................................................... 18
2.2. Synergies with other projects ........................................................................................................................... 27
2.3. Event organization ................................................................................................................................................ 32
2.4. Exhibitions and Technology Demonstrations ............................................................................................. 34
2.5. Bachelor, Master, PhD Theses and Internships........................................................................................... 36
3. Explanation of the work carried out by beneficiaries and overview of the progress ........................... 38
3.1. Objectives ................................................................................................................................................................. 38
3.2. Explanation of the work carried per WP ....................................................................................................... 46
3.2.1. WP1 ......................................................................................................................................................................... 46
3.2.2. WP2 ......................................................................................................................................................................... 48
3.2.3. WP3 ......................................................................................................................................................................... 61
3.2.4. WP4 ......................................................................................................................................................................... 68
3.2.5. WP5 ......................................................................................................................................................................... 74
3.2.6. WP6 ......................................................................................................................................................................... 91
3.3. Deliverables .............................................................................................................................................................. 95
3.4. Milestones ................................................................................................................................................................ 96
3.5. Exploitable Results ................................................................................................................................................ 96
D6.3: Final Project Report 4
H2020-856709
3.5.1. Exploitation on commercial products and PoCs developed internally to the companies . 96
3.5.2. Exploitation on standards ........................................................................................................................ 100
3.5.3. Patents ............................................................................................................................................................ 112
3.6. Impact ..................................................................................................................................................................... 112
3.6.1. Progress towards the 5G-PPP Key Performance Indicators ............................................................ 115
4. Update of the plan for exploitation and dissemination of results ............................................................122
5. Follow-up of recommendations and comments from previous review ..................................................123
5.1. Additional recommendations ........................................................................................................................ 126
6. Deviations from Annex 1 and Annex 2 ................................................................................................................130
6.1. Tasks ........................................................................................................................................................................ 130
6.2. Use of resources .................................................................................................................................................. 130
7. References ......................................................................................................................................................................131
D6.3: Final Project Report 5
H2020-856709
List of Figures
Figure 1: Final Design of the 5Growth System architecture ............................................................................... 14
Figure 2. SLA's elicitation phases .................................................................................................................................. 48
Figure 3: 5Growth high-level architecture ................................................................................................................ 49
Figure 4: 5Gr-AIMLP Representation .......................................................................................................................... 52
Figure 5: Federation/Multi-domain Architecture ................................................................................................... 53
Figure 6: Integration of O-RAN into 5Growth architecture ................................................................................ 54
Figure 7: Vertical-oriented Monitoring System architecture ............................................................................. 57
Figure 8: Anomaly Detection Algorithmic Framework ......................................................................................... 59
Figure 9. 5GR-FFB high level software architecture ............................................................................................... 60
Figure 10: Antennas at INNOVALIA Factory ............................................................................................................. 63
Figure 11: Experimentation at INNOVALIA Premises ............................................................................................ 63
Figure 12: Sites in COMAU Pilot ................................................................................................................................... 64
Figure 13: Experimentation at COMAU Facilities .................................................................................................... 65
Figure 14: Antenna at Aveiro Harbor .......................................................................................................................... 66
Figure 15: Train Detector and Equipment ................................................................................................................. 66
Figure 16: 5G CPE and RU at Secondary Substation ............................................................................................. 67
Figure 17: Experimentation at Aveiro university ..................................................................................................... 67
Figure 18: Microservice-based architecture of the SDA ...................................................................................... 70
Figure 19: Global architecture for 5Growth log parser ........................................................................................ 71
Figure 20: 5Growth experiment descriptor information elements and models ......................................... 72
Figure 21: 5Growth Communication, Dissemination, and Exploitation Plan (CoDEP) .............................. 76
Figure 22: 5Growth Poster .............................................................................................................................................. 80
Figure 23: 5Growth Leaflet .............................................................................................................................................. 81
Figure 24: 5Growth website landing page ................................................................................................................ 82
Figure 25: Web page visit statistics (counted for the previous 365 days from the reported Month).83
Figure 26: 5Growth website most visited pages on feb. 23, 2022 for the latest 365 days ..................... 83
Figure 27: 5Growth linkedin page ................................................................................................................................ 84
Figure 28: 5Growth Twitter account ............................................................................................................................ 84
Figure 29: Linkedin profile views .................................................................................................................................. 85
D6.3: Final Project Report 6
H2020-856709
Figure 30: Linkedin connections ................................................................................................................................... 85
Figure 31: Twitter profile visits....................................................................................................................................... 86
Figure 32: 5Growth Instagram page ............................................................................................................................ 86
Figure 33: Instagram statistics ....................................................................................................................................... 87
Figure 34: YouTube channel ........................................................................................................................................... 87
Figure 35: YouTube Studio STatistics .......................................................................................................................... 88
Figure 36: GitHub including a reference to the EU H2020 program ............................................................ 128
Figure 36: Instagram and Twitter descriptions ..................................................................................................... 128
D6.3: Final Project Report 7
H2020-856709
List of Tables
Table 1: Targeted versus measured dissemination metrics during the lifetime of the project ............ 17
Table 2: Publications of scientific journals and conferences in y1 ................................................................... 18
Table 3: Publications in scientific journals and conferences in Y2 ................................................................... 19
Table 4: Publications in scientific journals and conferendes in Y3 .................................................................. 20
Table 5: 5growth talks in scientific conferences and technology forums in Y1 .......................................... 23
Table 6: 5Growth talks in scientific conferences and technology forums in Y2.......................................... 24
Table 7: 5Growth talks in scientific conferences and technology forums in Y3.......................................... 26
Table 8: Collaborative activities with EU and international research projects in Y1 .................................. 27
Table 9: Collaborative activities with EU and international research projects in Y2 .................................. 29
Table 10: Collaborative activities with EU and international research projects in Y3 ............................... 31
Table 11: 5Growth Organized Events .......................................................................................................................... 32
Table 12: Exhibitions and technology demonstrations in dissemination events in Y1 ............................ 34
Table 13: Exhibitions and technology demonstrations in dissemination events in Y2 ............................ 34
Table 14: Exhibitions and technology demonstrations in dissemination events in Y3 ............................ 35
Table 15: 5Growth-related Bachelor, Master and PhD Theses, and internships ......................................... 36
Table 16: WP2 innovations .............................................................................................................................................. 50
Table 17: Mapping between platform requirements (gaps) and selected innovations ........................... 51
Table 18: Network KPIs used as features for the training set ............................................................................ 59
Table 19: 5Growth & ICT-17 Platform Software Artifacts ................................................................................... 62
Table 20: Communication activities achievements and targets ........................................................................ 77
Table 21: Communication videos in Y1 ...................................................................................................................... 88
Table 22: Communication videos in Y2 ...................................................................................................................... 88
Table 23: Communication videos in Y3 ...................................................................................................................... 89
Table 24: Communication talks ..................................................................................................................................... 89
Table 25: Lectures and courses ..................................................................................................................................... 90
Table 26: Exploitation table ............................................................................................................................................ 97
Table 27: Summary of the standard contributions per SDO ........................................................................... 100
Table 28: Complete list of sdo activities and candidate contributions in 5growth project ................. 101
Table 29: List of patents filed ...................................................................................................................................... 112
D6.3: Final Project Report 8
H2020-856709
List of Acronyms
5G-NR – 5G New Radio
5Gr-RL – 5Growth Resource Layer
5Gr-SO – 5Growth Service Orchestrator
5Gr-VS – 5Growth Vertical Slicer
AGV – Automated Guided Vehicle
AI – Artificial Intelligence
AMI – Advanced Metering Infrastructure
API – Application Programming Interface
AR – Augmented Reality
BB – Baseband
CB – Context Blueprint
CMM – Coordinate-Measuring Machine
CP – Control Plane
CPE – Customer Premises Equipment
CSMF – Communication Service Management Function
CUPS – Control and User Plane Separation
DSS – Decision Support System
E2E – End-to-End
eCPRI – enhanced Common Public Radio Interface
eMBB – enhanced Mobile Broadband
ExpB – Experiment Blueprint
ExpD – Experiment Descriptor
EVIAB – External Vertical Industries Advisory Board
FG – Forwarding Graph
GPS – Global Positioning System
GUI – Graphical User Interface
HSS – Home Subscriber Server
I4.0 – Industry 4.0
IIoT – Industrial Internet of Things
D6.3: Final Project Report 9
H2020-856709
IRU – Indoor Radio Units
KPI – Key Performance Indicator
LTE – Long Term Evolution
LV – Low-Voltage
LVS3 – Low Voltage Sensor
LX – Level Crossing
MANO – Mobile Network Management and Orchestration
ML – Machine Learning
mMTC – massive Machine Type Communications
MTTR – Mean Time To Repair
NDI – Network Device Interface
NFVI – Network Functions Virtualization Infrastructure
NFVO – Network Functions Virtualization Orchestrator
NG-PON2 – Next-Generation Passive Optical Network 2
NPN – Non-Public Network
NS – Network Service
NSA – Non-standalone
NSD – Network Service Descriptor
NSMF – Network Service Management Function
NTP – Network Time Protocol
OMS – Outage Management System
OTT – Over-The-Top
OWD – One Way Delay
OSS/BSS – Operations Support System and Business Support System
PMT – Project Management Team
PTZ – Pain-Tilt-Zoom
RAN – Radio Access Network
SDI – Serial Digital Interface
SFC – Service Function Chaining
SLA – Service Level Agreement
D6.3: Final Project Report 10
H2020-856709
SO – Service Orchestrator
TCB – Test Case Blueprint
UE – User Equipment
UP – User Plane
URLLC – Ultra-Reliable Low Latency Communication
vEPC – virtual Evolved Packet Core
VIM – Virtualized Infrastructure Management
VM – Virtual Machine
VNF – Virtual Network Function
VPN – Virtual Private Network
VS – Vertical Service
VSB – Vertical Service Blueprint
VSD – Vertical Service Descriptor
WIM – WAN Infrastructure Manager
ZDM – Zero Defect Manufacturing
D6.3: Final Project Report 11
H2020-856709
Executive Summary
The present deliverable called D6.3 presents the Part B of the First Periodic Report that will be
delivered before the 28th of February 2021. It mainly includes the information of the scientific work
carried out between the 1st of December 2020 and the 28th of February 2022. It is important to
highlight that the deadline of D6.3 is the 28th of February 2022, the final data for use of resources is
still not available at the end of February 2022. The full financial information will be included in the
Second Periodic Report in April 2022.
This document includes the Publishable Summary, patents and dissemination activities that will be
completed in the Participant Portal too, a description of the technical work carried out by
beneficiaries, and an overview of the progress in the last 15 months of the project, including the
objectives, the work performed by work package, the deliverables and milestones, the impact and
finally the deviations of the project.
D6.3: Final Project Report 12
H2020-856709
1. Summary for publication
1.1. Summary of the context and overall objectives of the project
1.1.1. Project context
5Growth is a 33-month collaborative project. The main objectives of the project are technical and
business validation of 5G technologies through field-trials for vertical industries. Four vertical
pilots across Industry 4.0, Transportation, and Energy will be field-trialed on four vertical-owned
sites. To conduct the Trials that demonstrate the 5Growth specific vertical use cases, 5Growth makes
use of the End-to-End connectivity platforms from to ICT-17-2018 projects: 5G EVE and 5G-VINNI,
to perform end-to-end testing and validation of service KPIs and 5G capabilities. To interconnect
with both ICT platforms, different integration approaches are explored.
Besides validating the current 5G technologies, another major aim is to develop new technological
innovations to enhance the service provisioning and automation process for the verticals with
an AI-driven Automated and Sharable 5G End-to-End Solution that will allow these industries to
achieve simultaneously their respective key performance targets. Towards this aim, 5Growth is
developing a set of innovations by extending the 5G-TRANSFORMER platform, to further enhance
the vertical support through (i) enhanced E2E network slicing solutions which enables automated
deployment and operation of slices, including 3GPP-defined RAN slices, customized to support
individual specific service requirements of various vertical industries, (ii) closed-loop automation and
SLA control for vertical services lifecycle management, and (iii) AI-driven end-to-end network solutions
to jointly optimize RAN, Transport, Core and Cloud, Edge resources, across multiple technologies,
multi-vendors and multi administrative domains (federation).
1.1.2. Project objectives
• Technical and business validation of 5G technologies in the selected four vertical pilots,
following a field-trial-based approach on vertical sites (TRL 6-7).
• To develop AI-driven E2E service orchestration solutions to enable automated multi-level,
cross-domain, hierarchical service orchestration along with multi-domain management of
resources, enabling seamless integration with existing5G E2E platforms at vertical sites.
• To design and develop the 5Growth platform integrating designed innovations, and related
architecture components, interfaces and algorithms, to support verticals to provision 5G
connectivity and services directly at the verticals’ sites, manage resources E2E and service
lifecycles to ensure meeting services requirements.
• Tight integration with ICT-17 facilities for E2E testing and validating 5G capabilities.
• Vertical-oriented trial-based assessment of core (network) and service (application) KPIs,
aligned with 5G-PPP KPIs.
• Communication, dissemination, and exploitation (incl. standardization) of 5Growth results.
D6.3: Final Project Report 13
H2020-856709
1.2. Work performed from the beginning of the project to the end
of the period covered by the report and main results achieved so
far
The work in the project has been divided into four Technical Work Packages (WPs).
WP1 is devoted to techno-economic analysis and business model design and validation. In the first
period, WP1 delivered the analysis of business requirements, technical and functional requirements
for the four vertical industry pilots in D1.1 and provided definition of the different business models
as well as methodology for the validation of business benefits of 5G and 5Growth innovations for
the project vertical use cases and their overall impact on the various stakeholders, in particular the
verticals, network operators and telecommunications manufacturers, as reported in D1.2. During the
second period, WP1 further refined the designed business models and developed a Service Level
Agreements (SLA) model to complement the business analysis. This work is documented in D1.3. The
outcome of WP1 provides a solid foundation for a properly defined and validated 5G business layer
(OSS/BSS) model to be applied over future advanced network services for vertical industries
scenarios. On top of that, WP1 also identified additional benefits on improving the safety, e.g.,
reducing of accidents in Industry 4.0 or in the crossing levels, as well as the reducing of environmental
footprint thanks to new remote-control capabilities for industrial equipment.
WP2 is dedicated to developing the 5Growth Platform for resource management at the vertical sites.
It inherits the building blocks from 5G-TRANSFORMER, extended with new modules and innovations
to cope with the new requirements from the vertical pilot use cases, particularly to enhance service
automation with AI/ML, monitoring and interfacing with vertical customers. During the first period,
WP2 proposed an initial design of 5Growth Platform including 12 designed innovations reported in
D2.1. Among them, a set of identified innovations have been integrated into the 5Growth platform.
The first release of the software was published on GitHub and documented in D2.2. In the second
period, WP2 ensured the successful completion of the final release of the 5Growth platform software,
including final design of architecture components on vertical-oriented monitoring system, AI/ML
platform, and forecasting module, enhanced vertical support for service automation, security, next
generation RAN, multi-domain and federation. The final design of the 5Growth platform (see Figure
3) is described in D2.3, and its final software release is published on GitHub and documented in D2.4.
WP3 is the key technical WP in charge of deployment of vertical pilots at four vertical sites integrating
with the ICT-17 platforms, namely 5G-VINNI and 5G EVE. In the first period, WP3 has identified
missing functionality required to deploy the envisioned pilots in these platforms (D3.1), and specified
ICT-17 in-house deployment (D3.2) including development of vertical applications and necessary
extensions towards the integration and deployment of the pilot over the ICT-17 platforms (D3.3 and
D3.4). In the second period, WP3 completed the development for the integration of the 5Growth
platform with ICT-17 (5G-EVE and 5G-VINNI) platforms and published the final release of the
software on Github and delivered in D3.5. Finally, WP3 deployed the infrastructure onsite at the
vertical facilities and implemented all the components and selected innovations required for the trials
D6.3: Final Project Report 14
H2020-856709
at the vertical sites for the execution of use cases for each of the pilots within the project. The
outcome of this work is documented in D3.6.
WP4 focuses on the evaluation of core (network) and service (application) KPIs through the 5Growth
field trials via several validation campaigns, validating the applicability of 5G technologies and
5Growth architecture to the different use cases of the project pilots. In the first period, WP4 has
defined a set of Service KPIs and Core 5G KPIs based on existing 5G-PPP KPIs and has identified the
correlation of the core 5G KPIs with respect to technical service KPIs for each pilot use case according
to their desired SLAs (D4.1). Moreover, WP4 has specified in D4.2 the measurement and testing
methodologies to be applied in the campaigns, including a series of tools to enable the automation
of the verification procedures, processing of measurement data and reproducibility of verification
results. During the second period, two last validations campaigns were executed to validate the
planned experimental and measurement configurations. The first campaign, reported in D4.3, was
executed at the ICT-17 facilities in use by the project, allowing to refine the initially verified tools and
methodologies, and to exercise the relevant KPIs in a controlled experimental environment that
reflects final deployment. The second campaign, reported in D4.4, conducted experiment
deployments at the vertical sites and their integration with the ICT-17 facilities, providing this way
sound evidence of KPI fulfilment in close-to-real operational conditions. Besides this, an analysis of
the application of specific innovations was performed as well under these conditions.
The work in WP4 was aligned with WP2 and WP3 activities, addressing three innovate-deploy-
validate cycles during the project lifetime. WP4 applied the appropriate software releases produced
by WP3, incorporating specific platform and innovation modules developed in WP2, and selecting
the applicable experimental environment for the corresponding cycle. As one of the final outcome
of interworking among WP2, WP3 and WP4, the final software release of the 5Growth Platform,
integration with the ICT-17 platforms, and all the pilot deployments at the vertical sites including
experiment catalogue are public available on GitHub: https://github.com/5growth.
FIGURE 1: FINAL DESIGN OF THE 5GROWTH SYSTEM ARCHITECTURE
D6.3: Final Project Report 15
H2020-856709
1.3. Progress beyond the state of the art, expected results until the
end of the project and potential impacts (including the socio-
economic impact and the wider societal implications of the
project so far)
5Growth targets innovations around five main components, illustrated in Figure 1: (1) 5Growth
Vertical Slicer (5Gr-VS): offering a powerful, yet simple and flexible, portal to verticals; (2) 5Growth
Service Orchestrator (5Gr-SO): instantiating and orchestrating network services in a smart and
automated manner by applying AI techniques; (3) 5Growth Resource Layer (5Gr-RL): integrating
compute, storage and networking resources and providing resource isolation for different slices; (4)
5Growth Vertical-oriented Monitoring System (5Gr-VoMS): providing monitoring across a
heterogeneous set of services and technological domains; and (5) 5Growth AI/ML Platform (5Gr-
AIMLP): offering services to different 5Growth layers to run AI/ML algorithms. These innovations are
combined into the 5Growth platform interacting with 5G EVE and 5G-VINNI platforms, providing E2E
solutions across multiple facilities and sites for deploying vertical services for different vertical
industries, while taking into account both technical and techno-economic requirements from the
stakeholders of the value chain. In this way, 5Growth creates a direct socio-economic impact, through
lower cost and higher efficiency for the stakeholders, better service (quality and ubiquitous access)
to the end users, and lower bills. The overall society will benefit from 5Growth innovations through
easier entry for verticals, more flexibility and cost-efficiency, whilst supporting the services envisioned
in 5G and beyond.
The final 5Growth software platform was released as open source on https://github.com/5growth,
enabling its adoption in other European projects and providing contributions to the overall 5G R&D
community and multiple open-source projects (e.g., OSM, ONOS, OpenStack). Particularly relevant,
5Growth building blocks software has been widely adopted for the development of 5G orchestration
platforms in many other 5G-PPP and H2020 projects.
The developed novel vertical services and 5Growth innovations will give the industrial companies
(large, medium, small) in the consortium and the extended European 5G-PPP community a privileged
position and competitive advantage in the European and global markets. An exploitation plan has
been made to assess the possible impact on the products and services roadmaps of the verticals,
vendors and operators as well as SMEs in the consortium, beyond the project lifetime.
A remarkable achievement in terms of pilots is the selection of multiple 5Growth pilots to be included
in the top 10 list of the EC H2020 5G Infrastructure PPP - PPP T&Ps Brochures n°2 and n°3.
• COMAU Pilot (“5Growth - Industry 4.0: Low-latency on a shared Network”) selected among the
top ten of the 5GPPP Infrastructure T&Ps Brochure No. 2 in 2020.
• COMAU Pilot (“5Growth - E2E Transport-aware Orchestration”) selected among the top ten of
the 5GPPP Infrastructure T&Ps Brochure No. 3 in 2021.
• INOVALIA Pilot (“5Growth: Industry 4.0 Remote Operation of Metrology Machinery over 5G”)
selected among the top ten of the 5GPPP Infrastructure T&Ps Brochure No. 3 in 2021.
D6.3: Final Project Report 16
H2020-856709
Moreover, in order to ensure the impact of 5Growth, the consortium has been very active in
dissemination efforts. Specifically, 5Growth has delivered:
• 81 scientific publications (47 journals and 34 international conferences/workshops);
• 21 organized (or co-organized) events (e.g., workshops co-located with renowned events,
exploitation workshop);
• 27 demonstrations at flagship academic and industrial events;
• 85 contributions to various SDOs were submitted: 20 to IETF/IRTF, 38 to 3GPP, and 10 to ETSI,
16 to IEEE, and 1 to GSMA, out of which 43 were accepted/adopted.
D6.3: Final Project Report 17
H2020-856709
2. Dissemination activities
This section describes the dissemination activities carried out in 5Growth that are listed in Table 1
along with the target KPIs.
TABLE 1: TARGETED VERSUS MEASURED DISSEMINATION METRICS DURING THE LIFETIME OF THE
PROJECT
Activity Targeted Metric Achieved Metric
Publications and
technical
dissemination
At least 10 publications per year in
top-tier scientific journals and
conferences.
A total of 81 publications (34
conferences and 47 journals) + 1 book
chapter accepted.
Synergies with
other projects
• Num. of meetings attended (target:
at least two per year).
• Num. of joint documents
generated (target: at least two per
year).
• Attended at least 66 5G-PPP
meetings (including architecture, test
and measurement, pre-
standardization working groups).
• A total of 42 joint publication
(including paper, white paper,
presentations).
Events Organization
• Organization of one 30-people
workshop co-located with a major
conference (e.g., EUCNC, IEEE
WCNC, ICC, INFOCOM) with 70%
satisfaction in the workshop quality
poll for attendees.
• Participation in workshops: we
measure the number of events
(target: at least one per year).
• A total of 21 workshops/events
organized (including academic and
industrial workshops/events).
• 67%, 87% and 82% satisfaction (very
satisfied) achieved for three
workshops that had more than 30
attendees. With “somewhat satisfied”
answers, the satisfaction ratios are
99%, 100% and 96% for these
workshops.
• Participation to a total of 82 events
(including 5G-PPP technology board
workshop, academic and industrial
workshops/events).
Exhibitions and
Technology
Demonstrations
• Technology demonstration in at
least two events – one at Y1 and
one at Y2. Two demonstration
deliverables are planned during the
project. More demonstrations in
several events are targeted.
• Vertical demonstrations in at least
three events. Two demonstration
deliverables are planned during the
project, which will include vertical-
oriented demonstrations.
• A total of 27 technology
demonstrations/exhibitions
(including academic and ETSI ENI
PoC).
• 8 out of 27 technology
demonstrations are vertical-oriented
demonstrations/exhibitions.
Research/Technical
Skill Development
Addition of core skills for technology
development within the project into
academic curriculums, along with the
proposal of PhD and MSc theses on
A total of 27 theses for bachelor, MSc,
PhD and internship studies, where 10 of
these were completed during the project
lifetime.
D6.3: Final Project Report 18
H2020-856709
specific topics on 5Growth research
agenda.
Standardization
Dissemination
• Submission of at least 10
contributions to SDOs, such as
3GPP, IETF, ETSI, IEEE, ITU over the
lifetime of the project.
• Participation in at least one open-
source project.
• A total of 85 submissions to SDOs
where 43 out of 85 contributions are
accepted/adopted.
• A total of 10 relevant contributions
to 7 open-source projects.
2.1. Publications and technical dissemination
Table 2, Table 3 and Table 4 present all 5Growth peer-reviewed articles in scientific journals and
studies/demos/posters in scientific conferences in Y1, Y2 and Y3, respectively. During the lifetime of
the project, a total of 81 peer-reviewed article submissions that includes 34 conference and 47 journal
papers (most of them belonging to the first quartile in terms of impact factor) accepted for
publication. In addition to that, one book chapter proposal was accepted.
TABLE 2: PUBLICATIONS OF SCIENTIFIC JOURNALS AND CONFERENCES IN Y1
Type Title Publication/Conference
journal Beyond 5G Evolution (Guest editorship) MDPI Electronics
journal Service Shifting: A Paradigm for Service Resilience in 5G IEEE Communications
Magazine
journal Reducing Service Deployment Cost Through VNF
Sharing
IEEE/ACM Transactions
on Networking
journal DeepCog: Optimizing Resource Provisioning in Network
Slicing with AI-based Capacity Forecasting IEEE JSAC
journal Is OpenCL Driven Reconfigurable Hardware Suitable for
Virtualising 5G Infrastructure?
IEEE Transactions on
Network and Service
Management
journal An Edge-based Framework for Enhanced Road Safety of
Connected Cars IEEE Access
journal On the integration of NFV and MEC technologies:
architecture analysis and benefits for edge robotics
Elsevier Computer
Networks
journal Federation of 5G services using Distributed Ledger
Technologies
Wiley Internet
Technology Letters
conference vrAIn: A Deep Learning Approach Tailoring Computing
and Radio Resources in Virtualized RANs ACM Mobicom 2019
conference
SliMANO: An Expandable Framework for the
Management and Orchestration of End-to-end Network
Slices
IEEE CloudNet 2019
conference PI2forP4: An Active Queue Management Scheme for
Programmable Data Planes ACM Conext 2019
D6.3: Final Project Report 19
H2020-856709
TABLE 3: PUBLICATIONS IN SCIENTIFIC JOURNALS AND CONFERENCES IN Y2
Type Title Publication/Conference
journal TOTP Moving Target Defense for sensitive network
services
Elsevier Pervasive and
Mobile Computing
journal Optical transport for industry 4.0
OSA Journal of Optical
Communications and
Networking
journal RISMA: Reconfigurable Intelligent Surfaces Enabling
Beamforming for IoT Massive Access IEEE JSAC
journal
Overview of Architectural Alternatives for the Integration
of ETSI MEC Environments from Different Administrative
Domains
MDPI Electronics
journal LACO: A Latency-driven Network Slicing Orchestration in
Beyond-5G Networks
IEEE Transactions on
Wireless
Communications
journal Decomposing SLAs for Network Slicing IEEE Communications
Letters
journal Modeling MTC and HTC Radio Access in a Sliced 5G
Base Station
IEEE Transactions on
Network and Service
Management
journal
5Growth: An End-to-End Service Platform for Automated
Deployment and Management of Vertical Services over
5G Networks
IEEE Communications
Magazine
journal Optimal Deployment Framework for Multi-Cloud
Virtualized Radio Access Networks
IEEE Transactions on
Wireless
Communications
journal vrAIn: Deep Learning based Orchestration for
Computing and Radio Resources in vRANs
IEEE Transactions on
Mobile Computing
journal Delay and reliability-constrained VNF placement on
mobile and volatile 5G infrastructure
IEEE Transactions on
Mobile Computing
journal Monitoring in fog computing: state-of-the-art and
research challenges
Inderscience
International Journal of
Ad Hoc and Ubiquitous
Computing (IJAHUC)
journal
Architecture for integrating vertical customer
programmability control of network functions and
connectivity in a slice-as-a service schema
EURASIP Journal on
Wireless
Communications and
Networking Journal
journal Public and Non-Public Network Integration for 5Growth
Industry 4.0 Use Cases
IEEE Communications
Magazine
journal Support for Availability Attributes in Network Slices in
GANSO
Wiley Internet
Technology Letters
D6.3: Final Project Report 20
H2020-856709
journal Towards Intelligent Cyber-Physical Systems: Digital Twin
meets Artificial Intelligence
IEEE Communications
Magazine
journal
A Genetic Algorithm Approach for Service Function
Chain Placement in 5G and Beyond, Virtualized Edge
Networks
Elsevier Compute
Networks
conference A Q-learning strategy for federation of 5G services IEEE ICC 2020
conference OKpi: All-KPI Network Slicing Through Efficient Resource
Allocation INFOCOM 2020
conference Handover Prediction Integrated with Service Migration
in 5G Systems IEEE ICC 2020
conference Orchestrating Edge- and Cloud-based Predictive
Analytics Services EuCNC 2020
conference 5Growth: AI-driven 5G for Automation in Vertical
Industries EuCNC 2020
conference Information Exchange to Support Multi-Domain Slice
Service Provision for 5G/NFV IFIP Networking 2020
conference DLT federation for Edge robotics IEEE NFV-SDN 2020
conference An Intelligent Edge-based Digital Twin for Robotics IEEE GlobeCom 2020
conference GANSO: Automate Network Slicing at the Transport
Network Interconnecting the Edge IEEE NFV-SDN 2020
conference On the Integration of AI/ML-based scaling operations in
the 5Growth platform IEEE NFV-SDN 2020
conference
Experimental Validation of Compute and Network
Resource Abstraction and Allocation Mechanisms within
an NFV Infrastructure
IEEE IM 2021
conference Bayesian Online Learning for Energy-Aware Resource
Orchestration in vRANs IEEE INFOCOM 2021
conference An RL Approach to Radio Resource Management in
Heterogeneous Virtual RANs IEEE WONS 2021
TABLE 4: PUBLICATIONS IN SCIENTIFIC JOURNALS AND CONFERENDES IN Y3
Type Title Publication/Conference
journal Towards Node Liability in Federated Learning:
Computational Cost and Network Overhead
IEEE Communications
Magazine
journal
Dissecting the Impact of Information and
Communication Technologies on Digital Twins as a
Service
IEEE Access
journal Multi-Domain Solution for the Deployment of Private 5G
Networks IEEE Access
journal
Live Migration of Virtual Machine and Container based
Mobile Core Network Components: A Comprehensive
Study
IEEE Access
D6.3: Final Project Report 21
H2020-856709
journal Automated Service Provisioning and Hierarchical SLA
Management in 5G Systems
IEEE Transactions on
Network and Service
Management
journal Intelligent Service Orchestration in Edge Cloud
Networks IEEE Network Magazine
journal A 5G-based eHealth monitoring and emergency
response system: experience and lessons learned IEEE Access
journal A Context-aware Radio Resource Management in
Heterogeneous Virtual RANs
IEEE Transactions on
Cognitive
Communications and
Networking
journal DQN Dynamic Pricing and Revenue driven Service
Federation Strategy
IEEE Transactions on
Network and Service
Management
journal
Resource Orchestration Strategies With Retrials for
Latency-Sensitive Network Slicing Over Distributed Telco
Clouds
IEEE Access
journal KPI Guarantees in Network Slicing IEEE Transactions on
Networking
journal A Model-based Approach to Multi-domain Monitoring
Data Aggregation
Journal of ICT
Standardization
journal Federation in dynamic environments: Can Blockchain be
the solution?
IEEE Communications
Magazine
journal Orchestrating Energy-Efficient vRANs: Bayesian Learning
and Experimental Results
IEEE Transactions on
Mobile Computing
journal AI-driven, Context-Aware Profiling for 5G and Beyond
Networks
IEEE Transactions on
Network and Service
Management
journal Performance Isolation for Network Slices in Industry 4.0:
The 5Growth Approach IEEE Access
journal A Multi-Criteria Decision Making Approach for Scaling
and Placement of Virtual Network Functions
Springer Journal of
Network and Systems
Management
journal Dimensioning V2N Services in 5G Networks through
Forecast-based Scaling IEEE Access
journal Service Based Virtual RAN Architecture for Next
Generation Cellular Systems IEEE Access
journal FlexDRAN: Flexible Centralization in Disaggregated
Radio Access Networks IEEE Access
journal Monitoring Platform Evolution towards Serverless
Computing for 5G and Beyond Systems
IEEE Transactions on
Network and Service
Management
D6.3: Final Project Report 22
H2020-856709
journal Distributed Ledger Technologies For Network Slicing: A
Survey IEEE Access
journal ML-driven Provisioning and Management of Vertical
Services in Automated Cellular Networks
IEEE Transactions on
Network and Service
Management
conference Serving HTC and Critical MTC in a RAN Slice IEEE WOWMOM 2021
conference 5Growth Data-Driven AI-Based Scaling EuCNC 2021
conference 5Growth: Secure and Reliable Network Slicing for
Verticals EuCNC 2021
conference On Slice Isolation Options in the Transport Network and
Associated Feasibility Indicators IEEE NetSoft 2021
conference Efficiency Gains due to Network Function Sharing in
CDN-as-a-Service Slicing Scenarios IEEE NetSoft 2021
conference 5Growth: Hardening Interdomain Vertical Services with
Moving Target Defense (MTD) EUCNC'21
conference COTORRA: COntext-aware Testbed fOR Robotic
Applications ACM MobiSys 2021
conference Cloud Native Computing for Industry 4.0: Challenges
and Opportunities IEEE ETFA'21
conference R-Learning-Based Admission Control for Service
Federation in Multi-domain 5G Networks IEEE GlobeCom 2021
conference Efficient Restoration of Simultaneous Transport Services
within an NFV Infrastructure IEEE GlobeCom 2021
conference OpenFlowMon: A Fully Distributed Monitoring
Framework for Virtualized Environments IEEE NFV-SDN'21
conference Outlook for Operator Adoption of 5G Networks EUCNC'21
conference Realizing Zenoh with programmable dataplanes ACM/IEEE ANCS’21
conference Dynamic Interdomain Network Slicing for Verticals in the
5Growth Project IEEE NFV-SDN'21
conference VERA: Resource Orchestration for Virtualized Services at
the Edge IEEE ICC’22
conference
End-to-End Network Service Orchestration in
Heterogeneous Domains for Next-Generation Mobile
Networks
IEEE NOMS’22
conference Model-Based Reinforcement Learning Framework of
Online Network Resource Allocation IEEE ICC’22
conference Near Optimal VNF Placement in Edge-Enabled 6G
Networks IEEE ICIN’22
Table 5, Table 6 and Table 7 present 5Growth consortium talks at scientific conferences, seminars,
and forums, with the goal of raising awareness on the 5Growth project during Y1, Y2 and Y3,
respectively. During the project lifetime, 5Growth consortium participated to various events including
academic and vertical-oriented events and gave a total of 60 talks in those events.
D6.3: Final Project Report 23
H2020-856709
TABLE 5: 5GROWTH TALKS IN SCIENTIFIC CONFERENCES AND TECHNOLOGY FORUMS IN Y1
Date Venue Description
2019-05-22 IEEE ICC 2019
Panelist at IEEE ICC 2019 Workshop: 5G-Trials –
From 5G Experiments to Business Validation called
Challenges in 5G Trials
2019-05-27
Dagstuhl Seminar 19222
“Control of Networked
Cyber-Physical Systems”
Impulsive presentation of 5Growth (“5G Service
Automation”)
2019-06-20 EuCNC 2019 Presentation of 5Growth in ICT-19 Session at
EUCNC 2019
2019-07-23 EuCNC 2019 Presentation of 5Growth in EMPOWER-PAWR
workshop: EuCNC.
2019-07-03 FUSECO FORUM Presentation of 5Growth (results and WIP) at
FUSECO Forum1
2019-09-03 ICT-19 session by 5G-EVE 5G-EVE organized a session devoted to discussing
collaboration with ICT-19 projects (i.e., 5Growth)
2019-10-08 5G PPP TB Workshop 5G-enabled Growth in Vertical Industries
2019-11-27 2nd Visions for Future
Communications Summit
Slicing with non-public networks – another
orchestration challenge for the next decade.
2020-01-13 Nokia Bell Labs (Paris-Saclay,
France)
Reinforcement Learning for Slice Resource
Allocation
2020-01-13 NYU Tandon School of
Engineering
Reinforcement Learning for Slice Resource
Allocation
2020-01-16 5G PPP SN WG Presentation of the 5Growth project to 5GPPP SN
WG
2020-03-09
“Jornadas Electrotécnicas
2020” at Instituto Superior
de Engenharia do Porto
Presentation of 5Growth project under the Seminar
“Research for beyond the Early 5G Network – EU
and PT”
2020-04-14 NMRG virtual meeting Metadata-based Aggregation of Telemetry Flows
2020-05-12
First meeting of 5Growth
External Vertical Industries
Advisory Board (EVIAB).
Presentation of the 5Growth project. Available at:
https://youtu.be/7uC0SN0F79g
2020-05-19
“The role of computing in
the post 5G-era:
Architectures and enabling
technologies”, workshop,
co-located with ONDM'20
(WS)
Evolutionary trends in operators' networks for
beyond 5G
2020-05-19 5th IEEE International
Workshop on Orchestration
Towards a standardized transport slicing
architecture in operator networks
1 https://www.fokus.fraunhofer.de/ngni/events/fuseco_forum_2019
D6.3: Final Project Report 24
H2020-856709
for Software Defined
Infrastructures (O4SDI), co-
located with the 2020
IEEE/IFIP NOMS
2020-05-26
5G PPP TB eWorkshop
(Session on Collaboration
among infrastructure and
vertical validation trials
projects)
An exemplary view from an ICT-19 project: 5Growth
– Link with 5G-EVE and 5G VINNI
2020-05-26
5G PPP TB eWorkshop
(Session on Business Model
Validation)
5Growth business validation
2020-05-26 5G PPP TB eWorkshop (AIML
session)
A Deep Learning Approach for vRAN Resource
Orchestration
2020-05-26
5G PPP TB eWorkshop
(Session on Validation and
KPIs)
5G PPP TMV TF on vertical KPIs Industry 4.0
TABLE 6: 5GROWTH TALKS IN SCIENTIFIC CONFERENCES AND TECHNOLOGY FORUMS IN Y2
Date Venue Description
2020-06-09 5G End-to-end
Experimentation by Verticals
in EU projects workshop
Intervention at Introductory Panel called: “Key
challenges and requirements for 5G experiments
with verticals” and at Concluding Panel called: “End
to end 5G experimentation across multiple EU
projects”
2020-09-11 5G From Theory to Practice
(5GToP) Workshop, in
conjunction with IEEE 5G
World Forum
Presentation overviewing 5Growth project:
“Validating 5G in vertical industries: the 5Growth
project”
2020-10-14 5G Workshop on “5G
Experimentation Facilities
and Vertical Trials: Current
Status and Future
Perspectives” organized by
5GENESIS/NCSR
“DEMOKRITOS”
Presentation called “Validating 5G in vertical
industries: the 5Growth project”
2020-09-29 CTIF Global Capsule “23rd
Strategic Workshop”, theme
“Sustainable Green
Environments”
Presentation called “5G-enhanced verticals:
contributions of the 5Growth project into the
railways and energy sectors”
2020-09-23 Event organized (Panel) by
5G Solutions project in
collaboration with the IEEE
ComSoc EMEA region
Presentation called “The Operator Point of View on
Transport Network, Not just phone calls and
messages where new telecommunication
technologies (5G) are hiding?”
D6.3: Final Project Report 25
H2020-856709
2020-10-02 Talk organized by IEEE
ComSoc EMEA
Presentation called “Get Smart – The Challenges in
Data-Driven Network Management”
2020-11-11 Keynote at
IEEE NFV SDN 2020
Keynote called “Serious science and serious
engineering - The way of software-based network
experimentation”
2020-11-09 Keynote at MOBISLICE III
workshop co-located with
the IEEE NFV-SDN 2020
Keynote called “Network slicing in practice through
service federation”
2020-11-19 Talk at MDPI webinar called
“Beyond 5G Webinar”
Talk called “5Growth Network Architectures for 5G
and beyond”
2020-12-09 5G PPP TB eWorkshop
(industry 4.0 session)
5Growth - Industry 4.0 Low Latency services on a
shared Transport Network
2020-12-09 5G PPP TB eWorkshop
(Testing: Methodologies and
Setup session)
5G EVE & 5Growth: Dealing with App validation, in
practice
2020-12-09 5G PPP TB eWorkshop
(Integrating Public and
Private Networks session)
On the operation of Non-Public Networks – An
MNO’s perspective
2020-12-09 5G PPP TB eWorkshop
(Integrating Public and
Private Networks session)
5Growth - “Slice Capability Exposure as an Enabler
for NSaaS
2020-12-09 5G PPP TB eWorkshop
(Working on verticals
session)
5Growth - E2E Solutions for experimenting 5G
vertical services across multiple Platforms and Sites
2020-12-09 Keynote at SBRC 2020 Scaling and Sharing Network Slices in 5G Networks
and Beyond
2020-12-11 Talk at the 5G PPP
Architecture WG Meeting
5Growth Architecture Design & Innovations
2021-01-11 Presentation at the 5G-
VINNI ESB (External
Stakeholders Board)
Presentation of the objectives, status and future
plans concerning the 5Growth 5G infrastructure
and Transportation and Energy use cases.
2021-03-10 Keynote at R2T2: Robotics
Research for Tomorrow's
Technology 2021
Supporting Industry 4.0 in Next-generation
Cellular: The Digital Twin Use Case
2021-03-25 Presentation at the
Metromeet'21 conference:
“Intelligent Metrology for a
Sustainable And Efficient
Digital Factory”
5Growth: 5G Metrology for a 5G Industry
2021-03-04 Presentation at 1st SLICES
workshop: Next Generation
ICT Research Infrastructures
Twinning Networks: On the Use and Challenges of
Network Digital Twins
2021-04-08 2nd 5G EVE Learn and Drive Panelist in the slot on “A great chance for SMEs and
startups to boost 5G applications”
D6.3: Final Project Report 26
H2020-856709
2021-04-13 Presentation at Layer123
Europe 2021 Event
Data flow aggregation for smarter network security
2021-04-27 NGIoT Thematic workshop
series on IoT and Edge
Computing (Session: Part I
Industrial IoT and Edge
Node Use Cases)
Towards an Autonomous Zero-X manufacturing
4.0: Human-Centred Tactile Manufacturing
Intelligence (Talk in panel)
2021-05-12 Presentation in Universidad
de Murcia
Introduction to Network Function Virtualization:
concept and standardization
2021-05-25 5GPPP TB eWorkshop 5Growth Interaction with 5G Experimentation
Platforms
TABLE 7: 5GROWTH TALKS IN SCIENTIFIC CONFERENCES AND TECHNOLOGY FORUMS IN Y3
Date Venue Description
2021-06-03 BEREC Workshop on 5G Panelist in BEREC Workshop on 5G. More info in:
https://berec.europa.eu/eng/events/berec_events_
2021/282-berec-workshop-on-5g (no presentation
associated)
2021-06-08 EUCNC'21 Talk in WS6: 5G
Private Networks
5Growth NPN Deployment Solutions & Industry
4.0 Pilot Examples
2021-06-08 EUCNC'21 Talk in WS6: 5G
Private Networks
Outlook for operator adoption of 5G Private
Networks
2021-06-11 EUCNC'21 Panelist EUCNC'21: "Seeding the long-term vision
for Autonomous Network Management on the
road to 6G Projects"
2021-07-20 Talk at the IEEE 7th World
Forum on Internet of Things
on Artificial Intelligence and
Machine Learning (AI/ML)
(TOP1)
Application of AI/ML for Learning-based Scaling
for the Industry 4.0 Services
2021-07-27 Talk at the NMRG meeting
within IETF111
A Practical Application of Monitoring data and AI
for Network Management in an Industrial
Environment
2021-07-27 Talk at the NMRG meeting
within IETF111
Toward Building a Context-Aware Data
Aggregation Framework for Network Monitoring
2021-10-13 Talk at the architecture
white paper version 4.0
presentation workshop
Architecture white paper. Chapter on
Management and orchestration.
2021-10-15 IEEE 5G World forum Moving to a new Innovation ecosystem powered
by 5G and AI
2021-10-25 Panelist at NetPA workshop
(co-located with IEEE
CNSM'21)
Panelist at IEEE CNSM'21 NetPA workshop. Panel
name: “On the challenges of network
programmability and automation under resilience
and sustainability stakes”
D6.3: Final Project Report 27
H2020-856709
2021-11-25 Talk at the 3 Visions for
Future Communications
Summit
Closing the Closed Loops
2021-12-07 "Human-Centric and Tactile
IoT" workshop co-located
with IEEE GLOBECOM 2021
Industry 4.0, 5G and Digital Factories (Keynote
talk)
2021-12-09 Panelist at IP2 of IEEE
Globecom 2021
Panelist at IEEE Globecom IPA2: Europe’s industrial
and digital development. The commitment of the
European Digital Innovation Hubs
2021-12-15 Talk at IEEE Standards
Summit 2021 - Short
Technical Talks:
“Standardization Activities
by 5GPPP Research
Projects“
SDO impacts of 5Growth
2022-01-18 Talk at 5GPPP TB e-
Workshop (5G-I TB
workshop ICT-17 & ICT-19
session)
E2E Solutions for experimenting 5G Vertical
services across ICT-17 and ICT-19 platforms
2.2. Synergies with other projects
Table 8, Table 9 and Table 10 report collaborative activities with other EU and international research
projects (e.g., through 5G PPP working groups, or working groups of other platforms) towards a
coordinated action inside the 5G PPP.
In addition to that, the project partners have been regularly attending the meetings and participating
in the activities of the 5G PPP working groups, including the steering board and technical board, Pre-
Standardization, Vision and Societal Challenges, 5G Architecture, Trials, SME, Software Networks,
Security, and Test, Measurements and KPI Validation. During the project lifetime, 5Growth
consortium has attended (due to the re-occurring nature of the 5G PPP WG meetings) attending at
least 66 5G-PPP meetings (estimated) and generated a total of 42 joint publications (including papers
and white papers). Additionally, several demos have been carried out with other projects.
TABLE 8: COLLABORATIVE ACTIVITIES WITH EU AND INTERNATIONAL RESEARCH PROJECTS IN Y1
Item Explanation
Joint Paper with project 5G-
TRANSFORMER @ IEEE Communications
Magazine
Service Shifting: A Paradigm for Service Resilience
in 5G
Joint Paper with projects: 5G-
TRANSFORMER, 5G-MoNArch, 5G-TOURS
@ ACM Mobicom 2019
vrAIn: A Deep Learning Approach Tailoring
Computing and Radio Resources in Virtualized
RANs
Joint Demo with projects: 5G-
TRANSFORMER, 5G-MoNArch, 5G-TOURS
@ ACM Mobicom 2019
vrAIn Proof-of-Concept — A Deep Learning
Approach for Virtualized RAN Resource Control
D6.3: Final Project Report 28
H2020-856709
5G PPP Technology Board meeting Report 5Growth interaction with ICT-17 platforms
5G PPP Software Network WG virtual
meeting
Discussion about our future plan/actions of the WG
for 2019-2020
Joint Paper submitted with 5G-
TRANSFORMER project @ IEEE ICC 2020 A Q-learning strategy for federation of 5G services
First technology roadmap for advanced
wireless, EMPOWER Roadmap
Joint Paper with project 5G-
TRANSFORMER and 5G-Tours project @
IEEE JSAC SI (“Advances in Artificial
Intelligence and Machine Learning for
Networking”)
DeepCog: Optimizing Resource Provisioning in
Network Slicing with AI-based Capacity Forecasting
Joint Demo with project 5G MISE Trial in
Bari and Matera
Remote Control of a Robot Rover Combining 5G,
AI, and GPU Image Processing at the Edge
EuCNC 2020 white paper on verticals.
Joint white paper on verticals (5GT +
5Growth + other projects) to be
presented during EuCNC 2020.
Empowering Verticals industries through 5G
Networks – Current Status and Future Trends
Presentation of the 5Growth project to 5G
PPP SN WG
Interaction with other projects of the H2020 5G
Infrastructure PPP, 5G PPP SNWG meeting
Brochure for MWC 2020 from 5G PPP
Software Network Working Group
Participation of 5Growth project in the MWC’20
brochure of SN WG called: Cloud Native and 5G
Verticals’ services
Joint demo: 5Growth (ICT-19 project), 5G-
CLARITY (ICT-20 project), and 5G-DIVE
(EU-Taiwan ICT-23 project) at EuCNC
2020 Booth
“Hybrid eMBB-URLLC network slicing for I4.0”
Joint demo with project 5G-
TRANSFORMER at INFOCOM 2020
NFV Service Federation: enabling Multi-Provider
eHealth Emergency Services
Joint demo with project 5G-
TRANSFORMER at INFOCOM 2020
Arbitrating Network Services in 5GNetworks for
Automotive Vertical Industry
5G PPP White paper on edge computing Contribution on Edge Computing in 5Growth
5G PPP White paper on 5G architecture
(consolidated version)
Capturing novel trends and key technological
enablers for the realization of the 5G architecture
Joint paper with 5G-TRANSFORMER and
5G-CORAL projects at Elsevier Computer
Networks
On the integration of NFV and MEC technologies:
architecture analysis and benefits for edge robotics
Joint workshop with 5G-DIVE, co-located
with Globecom 2020
Intelligent Fog and Edge Infrastructures for Future
Wireless Systems
5G PPP TB eWorkshop (Business model
validation session)
Participation in the discussion on business
validation with the 5Growth business validation
D6.3: Final Project Report 29
H2020-856709
TABLE 9: COLLABORATIVE ACTIVITIES WITH EU AND INTERNATIONAL RESEARCH PROJECTS IN Y2
Item Explanation
Joint Demo with project 5G-TOURS @ 5G
End-to-end experimentation by verticals
in EU projects Workshop
Demo called: “vrAIn: AI-driven orchestation of
vRAN resources”
Contribution to 5G IA white paper called
“Business Validation in 5G PPP vertical use
cases”, from “Vision and Societal
Challenges Working Group / Business
Validation, Models, and Ecosystems Sub-
Group”
White paper
Publication of white paper: Empowering
Verticals industries through 5G Networks
- Current Status and Future Trends, from
5GPPPTechnology Board&5G IA Verticals
Task Force
White paper
Joint paper with 5G-DIVE project at MDPI
Electronics journal
Paper called: Overview of Architectural Alternatives
for the Integration of ETSI MEC Environments from
Different Administrative Domains
Participation in the report of 5G PPP Pre-
Standardisation Work Group
Report called: “5G PPP Projects Impact on SDO
Technical Report”
Participation in the 5GPP TMV working
group White Paper on ICT-19
Performance KPIs
White paper name: “Service performance
measurement methods over 5G experimental
networks”
Joint paper with 5G-DIVE project at IEEE
NFV-SDN'20 Paper called: DLT federation for Edge robotics
Joint paper with 5G-DIVE at IEEE
Globecom 2020 WS AT5G+
Paper called: An Intelligent Edge-based Digital
Twin for Robotics
Joint paper with 5G-DIVE at IEEE NFV-
SDN 2020 WS MOBISLICE III
Paper called: “GANSO: Automate Network Slicing
at the Transport Network Interconnecting the Edge
Joint paper with MonB5G Project at
Transaction on Wireless Communications
Paper called: LACO: A Latency-driven Network
Slicing Orchestration in Beyond-5G Networks
EC H2020 5G Infrastructure PPP - PPP
T&Ps Summary Table - PPP T&Ps
Brochure n°2 - PPP Verticals Cartography
Participation with the pilot called: “5Growth:
Industry 4.0 Low Latency use cases on shared
Network”
5G PPP projects' brochure to be released
early next year. Phase 3 projects brochure
Joint workshop with 5G-DIVE and
Empower Beyond 5G Evolution
5G PPP White paper “Delivery to 5G Services to Indoors”
5G PPP White paper “AI/ML for future networks”
5G PPP TB eWorkshop (Industry 4.0
session)
5Growth - Industry 4.0 Low Latency services on a
shared Transport Network
5G PPP TB eWorkshop (Testing:
Methodologies and Setup session)
5G EVE & 5Growth - “Dealing with App validation,
in practice”
D6.3: Final Project Report 30
H2020-856709
5G PPP TB eWorkshop (Integrating Public
and Private Networks session)
5Growth - “Slice Capability Exposure as an Enabler
for NSaaS”
5G PPP TB eWorkshop (Working on
verticals session)
5Growth - "E2E Solutions for experimenting 5G
vertical services across multiple Platforms and
Sites”
5G PPP TB eWorkshop (Integrating Public
and Private Networks Session)
5Growth – “On the operation of Non-Public
Networks – An MNO’s perspective”
ETSI ENI PoC #9 ETSI ENI PoC #9: Autonomous Network Slice
Management for 5G Vertical Services
Joint webinar with 5G-DIVE 5Growth and 5G-DIVE Research Projects: diferentes
acercamientos para el Edge (in Spanish)
Joint webinar with 5G-DIVE Projetos de pesquisas 5Growth e 5G-DIVE:
diferentes abordagens para Edge (in Portuguese)
Joint journal paper with 5G-DIVE at IEEE
Transactions on Mobile Computing
Journal paper co-authored by 5Growth and 5G-
DIVE: “Delay and reliability-constrained VNF
placement on mobile and volatile 5G
infrastructure”
Participation in the 5G-VINNI ESB (Extern
Stakeholders Board) meeting
The objective, status and future plans concerning
the 5Growth 5G infrastructure and Transportation
and Energy use cases.
Joint Demo paper with 5G-DIVE at IEEE
INFOCOM'21
Demo paper called: “Demo: AIML-as-a-Service for
SLA management of a Digital Twin Virtual Network
Service”
Joint Demo paper with DAEMON at IEEE
INFOCOM'21
Demo paper called: “Demonstrating a Bayesian
Online Learning for Energy-Aware Resource
Orchestration in vRANs”
Joint journal article with 5G-DIVE at
Inderscience
Journal paper called: “Monitoring in fog
computing: state-of-the-art and research
challenges”
Joint journal article with 5G-DIVE at
Eurasip JWCN
Journal paper called: “Architecture for integrating
vertical customer programmability control of
network functions and connectivity in a slice-as-a
service schema”
Joint conference paper with 5G-DIVE and
5G-VINNI projects
Conference paper called: “On Slice Isolation
Options in the Transport Network and Associated
Feasibility Indicators”
Joint journal article with 5G-EVE project at
IEEE Communications Magazine
Journal paper called: “Public and Non-Public
Network Integration for 5Growth Industry 4.0 Use
Cases”
Joint journal article with 5G-DIVE at Wiley
Internet Technology Letters (Special Issue:
Mobility support in Slice-Based Network
Control for Heterogeneous Environment)
Journal paper called: “Support for Availability
Attributes in Network Slices in GANSO”
5G PPP White Paper “Service performance measurement methods over
5G experimental networks”
D6.3: Final Project Report 31
H2020-856709
5G PPP White Paper “Understanding the Numbers Contextualization
and Impact Factors of 5G Performance Results”
Joint journal article with 5G-DIVE at IEEE
Communications Magazine (Special Issue:
Networks for Cyber-Physical Systems and
Industry 4.0)
Journal paper called: “Towards Intelligent Cyber-
Physical Systems: Digital Twin meets Artificial
Intelligence”
TABLE 10: COLLABORATIVE ACTIVITIES WITH EU AND INTERNATIONAL RESEARCH PROJECTS IN Y3
Item Explanation
5GPPP Trials and Pilots Brochure No3 Participation in the [5G-TB] Trials and Pilots
Brochure No3: Results – COMAU Pilot
5GPPP Trials and Pilots Brochure No3 Participation in the [5G-TB] Trials and Pilots
Brochure No3: Results – INNOVALIA Pilot
5G IA White Paper “European Vision for the 6G Network Ecosystem”
Joint workshop organization in EUCNC'21
with INSPIRE-5Gplus, 5GASP, 5GZORRO,
5Growth, 5GENESIS, 5GMobix, 5G-
INDUCE, SPIDER, Hexa-X, Teraflow,
PALANTIR and PUZZLE
WS8: From 5G to 6G Automated and Intelligent
SecuriTy: FAST
Joint workshop organization in EUCNC'21
with FUDGE-5G, 5G-VINNI, 5G-RECORDS,
AFFORDABLE-5G, 5Growth, 5G-CLARITY,
5G-SMART, 5G-TOURS,
5G-INDUCE, 5G-Solutions, 5G- VICTORI,
PriMO-5G
WS6: 5G Private Networks
Joint workshop paper with 5G-DIVE at
"MobileServerless ‘21", co-located with
ACM MobiSys 2021
Workshop paper called: “COTORRA: COntext-aware
Testbed fOR Robotic Applications”
ECSEL/KDT and LIASE White Paper “Lighthouse Industry 4.0”
Moderator of 5GPPP TMV WG webinar
Webinar called: “Practical insights from 5G Test,
Measurement and KPI Validation with vertical
applications”
Joint workshop organization in CNSM'21
with Hexa-X, MON-B5G, 5G-DIVE
Zero-Touch Network and Service Management
(ZNSM) workshop, co-located with CNSM'21
Joint journal paper with 5G-DIVE at IEEE
Access
Journal called: "Dissecting the Impact of
Information and Communication Technologies on
Digital Twins as a Service"
Joint journal paper with 5G-EVE at IEEE
Access
Journal paper called: "Multi-Domain Solution for
the Deployment of Private 5G Networks"
5G PPP White Paper "View on 5G Architecture"
Joint journal article with 5G-
TRANSFORMER project at IEEE TNSM
Journal paper called: “Automated Service
Provisioning and Hierarchical SLA Management in
5G Systems”
Joint Exploitation Workshop organization
with 5G-DIVE "Experiences from field trial about vertical industry"
D6.3: Final Project Report 32
H2020-856709
Talk at IEEE 5G World forum “Moving to a new Innovation ecosystem powered
by 5G and AI (5G-EVE & 5Growth)”
Joint workshop paper with 5G-DIVE at
"MOBISLICE'21", co-located with IEEE
NFV-SDN 2021
Workshop paper called: “OpenFlowMon: A Fully
Distributed Monitoring Framework for Virtualized
Environments”
Joint journal article with INSPIRE-5Gplus
at Journal of ICT Standardization
Journal paper called: “A Model-based Approach to
Multi-domain Monitoring Data Aggregation”
Co-editor of 5GPPP White Paper "NPNs - State of the art and way forward"
Joint journal article with DAEMON project
at IEEE TMC
Journal paper called: “Orchestrating Energy-
Efficient vRANs: Bayesian Learning and
Experimental Results”
5G PPP Architecture WP Vice-chair
election
5Growth TM elected as Vice-chair of the 5GPPP
Architecture WG
Joint journal paper with 5G-DIVE at IEEE
Access
Journal paper called: “Dimensioning V2N Services
in 5G Networks through Forecast-based Scaling”
Joint demo paper with DAEMON at ACM
MobiHoc 21
Demo called: “Demo: Nuberu — A Reliable DU
Design Suitable for Virtualization Platforms”
Joint journal paper with Affordable5G,
DAEMON and 6GBrain
FlexDRAN: Flexible Centralization in Disaggregated
Radio Access Networks
Joint journal paper with 5G-EVE at IEEE
TNSM
Monitoring Platform Evolution towards Serverless
Computing for 5G and Beyond Systems
2.3. Event organization
Table 11 reports on the participation of the 5Growth consortium in the organization of dissemination
events during the project lifetime, which realization already happened during the Y2 and Y3 of the
project. Many of these events were co-located with renowned conferences (e.g., EUCNC’21).
Furthermore, satisfaction ratio for those events in which polls could be gathered was above 70%.
More specifically, the project organized three events of more than 30 attendees for which it could
gather polls with satisfaction rates of 99%, 100%, and 96%.
TABLE 11: 5GROWTH ORGANIZED EVENTS
Date Item Explanation
2020-06-09
Joint half-day online workshop with
5Growth, 5G-DIVE, 5G-EVE, 5G-VINNI,
and 5G-TOURS
Open virtual workshop in which 5G
projects will present their latest
results, including demonstrations.
2020-07-09 Powering 5G in industry Periodical webinar with Layer123
2020-09-10 5G from Theory to Practice (5GToP)
Workshop
Co-located with IEEE 5G World Forum
2020, Bangalore, India2
2020-11-10 IEEE NFV-SDN 2020 November 10-12, 2020
2 https://ieee-wf-5g.org/5g-from-theory-to-practice-5gtop-workshop/
D6.3: Final Project Report 33
H2020-856709
2020-11-10 Mobislice 2020 Co-located with IEEE NFVSDN 2020
2020-11-19 Beyond 5G Evolution MDPI Webinar 20203
2021-01-12
Webinar called “5Growth and 5G-DIVE
Research Projects: diferentes
acercamientos para el Edge”
Telesemana Webinar4
2021-01-14
Webinar called “Projetos de pesquisas
5Growth e 5G-DIVE: diferentes
abordagens para Edge”
Telecom Webinar5
2021-03-05 Ericsson internal event Outside-insight program: Factories of
the Future
2021-06-08
WS8: From 5G to 6G Automated and
Intelligent SecuriTy: FAST (co-located with
EUCNC21)
EUCNC’21
2021-06-08 WS6: 5G Private Networks (co-located
with EUCNC21) EUCNC’21
2021-10-25
1st International Workshop on Zero-
Touch Network and Service Management
(ZNSM 2021). It has been merged with
NetP workshop, resulting in NetPA
workshop
Co-located with IEEE CNSM 20216
2021-10-29 "Experiences from field trial about vertical
industry"
Joint organization of 5Growth/5G-
DIVE exploitation workshop
2021-11-26 Event called "Empowering the future" Efacec internal exploitation event
Weekly
since July
2021
"Weekly recurrent I4.0 5G Business
Steering meeting at Ericsson ERC" Ericsson Spain Internal
Bi-weekly
since
September
2021
"Boosting the industrialization of slicing
services to Enterprise 5G customer
segments"
Ericsson Spain and Telefonica internal
April/Nove
mber 2021
"Presentation of 5Growth COMAU results
to internal project" Ericsson Italy (TEI) internal
2021-12-09 Ericsson Research Day Ericsson Italy (TEI) internal
2021-12-01 Product roadmap opportunities with
5Growth solutions Ericsson Italy (TEI)/TIM internal
2021-12-10 Ericsson-TIM internal Workshop Ericsson Italy (TEI)/TIM internal
3 https://electronics-2.sciforum.net/ 4 https://www.telesemana.com/blog/webinar/5growth-and-5g-dive-research-projects-different-approaches-
to-the-edge/ 5 https://telecomwebinar.com/webinar/projetos-de-pesquisas-5growth-e-5g-dive-diferentes-abordagens-
para-edge/ 6 http://www.cnsm-conf.org/2021/workshop_NetPA.html
D6.3: Final Project Report 34
H2020-856709
2022-03-11 (after project end)
Virtual Aveiro Harbour workshop:
Portuguese 5G vertical solutions
EFACEC_S/EFACEC_E, Altice and
ITAV exploitation event
2022-04-06 (after project end)
Aveiro Harbour OpenDay - Half-day
5Growth workshop dedicated to
Portuguese Pilot achievements
EFACEC_S/EFACEC_E, Altice and
ITAV industrial dissemination event
2.4. Exhibitions and Technology Demonstrations
Table 12, Table 13 and Table 14 report the exhibitions and technology demonstrations performed in
different dissemination events in Y1, Y2 and Y3, respectively. Overall, the consortium achieved 27
technology demonstrations in different venues. 8 out of these 27 exhibitions/demonstrations were
vertical-oriented.
TABLE 12: EXHIBITIONS AND TECHNOLOGY DEMONSTRATIONS IN DISSEMINATION EVENTS IN Y1
Date Venue Description
2019-10-21 ACM Mobicom
2019
vrAIn Proof-of-Concept — A Deep Learning Approach for
Virtualized RAN Resource Control
2020-03-08 OFC 2020 Remote Control of a Robot Rover Combining 5G, AI, and
GPU Image Processing at the Edge
2020-05-27
5GPPP TB
eWorkshop
(Session on Use of
AI & ML in
networks – Part 1)
vrAIn: AI-driven orchestration of vRAN resources
TABLE 13: EXHIBITIONS AND TECHNOLOGY DEMONSTRATIONS IN DISSEMINATION EVENTS IN Y2
Date Venue Description
2020-06-09
Online workshop with 5G-
DIVE, 5G-EVE, 5G-VINNI, 5G-
TOURS
vrAIn: AI-driven orchestration
of vRAN resources
2020-07-06 INFOCOM 2020
NFV Service Federation:
enabling Multi-Provider
eHealth Emergency Services
2020-07-06 INFOCOM 2020
Arbitrating Network Services
in 5GNetworks for Automotive
Vertical Industry
2020-07-09 Online webinar Layer123 on
Powering 5G in Industry
vrAIn: AI-driven orchestration
of vRAN resources
2020-10-12 ACM MobiHoc 2020 Demo: Scaling Composite
NFV-Network Services
2020-11-19 Joint with BT/5G-VINNI End to End (E2E) Immersive
Telepresence over 5G Network
2020-12-18 ETSI ENI PoC#9
ETSI ENI PoC #9: Autonomous
Network Slice Management
for 5G Vertical Services
D6.3: Final Project Report 35
H2020-856709
2021-03-10 OSM Ecosystem Day
Demo: Vertical's intent
evolution at service runtime
driving vCDN automated
scaling
2021-05-12 INFOCOM 2021
Scaling Federated Network
Services: Managing SLAs in
Multi-Provider Industry 4.0
Scenarios
2021-05-12 INFOCOM 2021
Demo: AIML-as-a-Service for
SLA management of a Digital
Twin Virtual Network Service
2021-05-12 INFOCOM 2021
Demonstrating a Bayesian
Online Learning for Energy-
Aware Resource Orchestration
in vRANs
TABLE 14: EXHIBITIONS AND TECHNOLOGY DEMONSTRATIONS IN DISSEMINATION EVENTS IN Y3
Date Venue Description
2021-06-29 IEEE NetSoft 2021 Slice Isolation for 5G Transport Networks
2021-06-29 Advanced Factories
2021
M3 SMART CYBER PHYSICAL METROLOGY 4.0 SYSTEM has
been selected as 2021 Advanced Factory Finalist for Best
industrial equipment for the factory of the future
2021-07-29 IEEE SECON'21 Log Management in NFV Service Orchestration
2021-07-29 IEEE SECON'21 Deploying Hybrid Network Services: Mixing VNFs and CNFs
in Multi-site Infrastructures
2021-06-09 EUCNC'21 5Growth Pilot. EFACEC Energia’s energy pilot
2021-06-09 EUCNC'21 5Growth Pilot. EFACEC Engenharia e Sistemas
transportation pilot
2021-06-09 EUCNC'21 5Growth Pilot. COMAU industry 4.0 pilot.
2021-06-09 EUCNC'21 5Growth Pilot. INNOVALIA industry 4.0 pilot.
2021-06-09 EUCNC'21 5Growth Innovation. ‘ML-driven Scaling of Digital Twin
Service in 5Growth'
2021-06-09 EUCNC'21 5Growth Innovation. ‘Performance Isolation for 5G Network
Slicing’
2021-06-09 EUCNC'21 5Growth Innovation. ‘Moving Target Defense’
2021-06-28 MWC'21 Zero Defect Manufacturing with Edge Computing and 5G
Connectivity
2022-01-31 Mobicom'21 Demo: Nuberu — A Reliable DU Design Suitable for
Virtualization Platforms
2022-02-28 MWC’22 Log parsing demo at CTTC booth
D6.3: Final Project Report 36
H2020-856709
2022-09-21 (after project end)
Innotrans’22 Presentation of main achievements of 5Growth vertical
transportation solutions
2.5. Bachelor, Master, PhD Theses and Internships
Table 15 reports bachelor, master, and PhD theses as well as internships on matters related to
5Growth for a total of 27.
TABLE 15: 5GROWTH-RELATED BACHELOR, MASTER AND PHD THESES, AND INTERNSHIPS
Type (PhD/Master/Int.) State Title
PhD Ongoing AI/ML-enabled Software Defined Smart
Networks on Distributed and Next
generation Architectures
PhD Ongoing Smart Networks and IoT
PhD Ongoing Artificial Intelligence Driven Next Generation
Networking
Master Finished A new SDN application providing Quality of
Service (QoS) for network slicing
PhD Ongoing Offloading of 5G functions in accelerated
edge data centres
Master Finished AI-based algorithms and experimental
evaluation for beyond 5G
Master Finished A Deep Learning Analysis of Internet Traffic
Datasets for 5G MEC Dimensioning
PhD Ongoing ML-driven edge network resource allocation
Master Ongoing Performance evaluation and design of ML-
based solutions for the support of mobile
services in 5G systems
Master Finished Machine Learning for 5G/6G Mobile
Networks
Master Finished AI-based algorithms and experimental
evaluation for beyond 5G
Master Finished A Machine-learning Approach for Video
Streaming Provisioning at the Network Edge
PhD Finished Development and Performance Evaluation of
Network Function Virtualization Services in
5G Multi-Access Edge Computing
infrastructure
PhD Ongoing Virtualized Mobile Services at the edge of
the network
Internship Finished P4 Programmable Traffic Management
Master Finished 5G Interdomain Orchestration Mechanisms
for Flexible Vertical Services Deployment
Master Finished Inter-domain orchestration for verticals in
5G network services
D6.3: Final Project Report 37
H2020-856709
Master Finished A reinforcement learning algorithm for
optimal Virtual network functions allocations
among 5G edge computing centers
PhD Finished End-to-end network service orchestration in
heterogeneous domains for next-generation
mobile networks
Master Finished Flexible Software-Defined Networks
PhD Ongoing Dynamic Security Mechanisms for
Softwarized and Virtualized Networks
D6.3: Final Project Report 38
H2020-856709
3. Explanation of the work carried out by beneficiaries and
overview of the progress
3.1. Objectives
This section is devoted to the progress towards the fulfilment of the project objectives. For each of
the objectives identified in the Description of Action (DoA), we present the details on how they have
been tackled technically and by which WP.
Objective 1 Validate 5Growth business model
Description The analysis of the technical and functional requirements of the different use cases
and field trials planned within the project shall spawn a successful business model
that is advantageous for mobile operators, service providers and, especially,
vertical sectors. The first objective of 5Growth is thus to validate the business
viability of the entire project ecosystem.
R&D Topics WP/task Details
Analyze technical
and functional
requirements of
vertical use cases and
field trials
WP1/T1.1 • A detailed description of the pilots and the use cases.
D1.1 [8].
• A detailed business, functional and technical
requirements for all the different vertical pilot use cases
has been reported in D1.1 [8].
Survey business
models from both 5G
infrastructure owner
and verticals’
perspective
WP1/T1.1 • Identification of the stakeholders in each pilot.
• Definition of the business model and the services flow
per pilot in D1.1 [8].
WP1/T1.2 • Identification of the economic flow between the
different stakeholders D1.2 [9].
• Estimation of the benefits of the pilots for the
stakeholders D1.2 [9].
• Final design of the business models in D1.3 [10].
WP1/T1.3 • Design of a flexible Service Level Agreements (SLA)
model to complement the business analysis in D1.3 [10].
Verification WP/task Details
Report on techno-
economic study and
validation of business
models
WP1/T1.2
WP1/T1.3
• A detailed techno economic analysis including initial
analytical results to characterize the techno-ecosystem
is reported in D1.2 [9] and the final results in D1.3 [10].
• A common methodology for the business model
validation is proposed and applied to evaluate overall
economic and social benefits for each pilot use case to
an European scale, described in D1.2 [9] and final study
was reported in D1.3 [10].
• SLA elicitation and business model validation through
numerical evaluation of the benefits introduced by the
D6.3: Final Project Report 39
H2020-856709
5G technologies and 5Growth solutions envisaged by
the Project in the 4 Pilots, reported in D1.3 [10].
Present and validate
the advantages of
verticals in an
exploitation-specific
workshop with
verticals
WP1/T1.2
• 5Growth has contributed to a whitepaper [11] organized
by the 5G Public Private Partnership (5G-PPP) and the 5G
Infrastructure Association (5G IA) that provides
information about business requirements and addressed
business cases and solutions for vertical industries. It
also discusses in detail several exemplary use cases from
eleven different vertical sectors and identifies key 5G
features that have been used to meet the specified
requirements.
Objective 2 Design and develop 5Growth extensions into 5G architecture
Description Design and develop the extensions required to incorporate 5Growth main
innovations into the 5G baseline architecture, namely, an automated support to
vertical sectors through an enhanced vertical slicer, orchestration of monitoring
and telemetry services in support of the verticals; a network slicing/service
orchestration and SLA modelling and control that offers isolation, virtualization,
multi-domain management of resources (beyond MANO) and cross-domain
orchestration capabilities to enable the operation of the different vertical slices.
R&D Topics WP/task Details
Analyze the 5G-
TRANSFORMER
architecture and
identify the technical
gaps and
enhancements
required to support
5Growth vertical use
cases and field trials
WP2/T2.1 • We have performed a functional and technical gap
analysis, which was reported in D2.1 [1].
• Our gap analysis motivated the selection of a set of
innovations for integration into the 5Growth baseline
platform. The selection and its criteria were reported in
D2.1 [1].
Develop novel
interfaces between a
vertical slicer
component and the
vertical parties,
offering verticals
more control over
their own services
and improved
information models
WP2/T2.2 • Several innovations have been developed to enhance
the vertical support, documented in D2.3 [1] and the
code release in D2.4 [2][2]:
o RAN slicing: this innovation allows vertical
parties to specify 5G requirements include radio
coverage aspects.
o Security: implementation of Moving Target
Defence (MTD) mechanisms to provide security
for the verticals on external interfaces.
o Multi-domain: multi-level and multi-domain
solutions were developed for handling different
types of services across communication services,
network slices, and network services; accordingly
novel interfaces and driver functions have been
developed for ICT-17 integration as well as
interworking with external domains.
D6.3: Final Project Report 40
H2020-856709
Extend the 5G-
TRANSFORMER
monitoring platform
to provide verticals
with analytic services
and improved SLA-
driven control of
network slices
WP2/T2.3 • Final design and implementation of the Vertical-
oriented Monitoring System (5Gr-VoMS) in the context
of Innovation 2, and the design of Innovation 3
(Monitoring Orchestration). The latter provides
automation capabilities to the 5Gr-VoMS, achieving the
integration of features related to the full control of the
lifecycle of the monitor functions instances. The final
Release (developed during this second reporting period)
implements additional features such as gathering
application metrics and collecting logs from VNFs. The
final release of 5Gr-VoMS is detailed in D2.3 [1] and final
code release in D2.4 [2][2].
Design and integrate
the components
required to extend
the baseline 5G
architecture to
achieve E2E network
slicing (spanning
RAN, back/fronthaul
and computing
infrastructure) and
service orchestration
WP2/T2.4 Completed the final design of the 5Growth architecture and
innovations in D2.3 and delivered the final release of the
5Growth platform with all software components in D2.4:
• Vertical Slicer
• Service Orchestrator
• Resource Layer
• Vertical-oriented Monitoring System
• AI/ML Platform
• Forecasting Functional Block
During the second period, an additional set of innovations
was further developed, namely:
• AI/ML platform (5Gr-AIMLP) to assist 5Growth
components in AI/ML tasks such as model provisioning
and model training.
• The integration of O-RAN compliant next-generation
RANs.
• Anomaly detection mechanisms.
• Moving Target Defense (MTD) mechanisms to provide
security in external interfaces.
• Novel forecasting and inference algorithms.
• Data-driven and AI-based automated scaling.
• Smart orchestration and resource control algorithms.
• Support of performance isolation mechanisms with
OpenFlow and P4-capable switches at 5Gr-RL.
• Extended federation and multi-domain mechanisms.
Verification WP/task Details
Analyze and simulate
to pre-evaluate
medium and/or
large-scale systems
WP2/all
tasks
In WP2, we have evaluated a number of mechanisms
through simulations. For instance:
• A novel AI-driven orchestration mechanism for vRAN/O-
RAN networks has been demonstrated [14].
• An AI-driven federation mechanism [15].
• An AI-driven VNF-FG mechanism [13].
• MTD mechanism for security [16].
D6.3: Final Project Report 41
H2020-856709
• Dynamic user profiling and forecasting mechanisms [13].
Additional results will be provided during the second
reporting period.
Develop and
demonstrate proof-
of-concept
prototypes (TRL 4)
WP2/all
tasks
In addition, small-scale proof of concepts have been created
to demonstrate such innovations as:
• A novel AI-driven orchestration mechanism for vRAN/O-
RAN networks [14].
• Performance isolation over P4-capable networks [12].
• Automated AI-driven NFV-NS scaling [2].
• Additional PoCs were also developed during the second
reporting period.
Objective 3 Perform field trials and showcase vertical use cases in field trials
Description Integrate and deploy the 5Growth service platform on top of ICT-17 platforms and
complementary trial sites (incl. vertical sites) and demonstrate 9 use cases across 4
pilots through field trials.
R&D Topics WP/task Details
Integrate novel
5Growth
components
developed in WP2
into the 5G baseline
architecture
WP3/T3.1
WP3/T3.2
• Selected innovations from WP2 (D3.1 [17], D3.2 [18],
D3.4 [20]).
• First version of software implementation for the platform
(D3.3 [20]).
• Final version of the software on Github and reported in
D3.5 [3].
Deploy the 5Growth
system across all trial
sites, including
software and
hardware
components for all
use cases planned
such as, e.g., 5G
service-based core,
NR (New Radio),
unlicensed/licensed
spectrum, multi-RAT
technologies, Multi-
access Edge
Computing (MEC)
WP3/T3.3
WP3/T3.4
WP3/T3.5
WP3/T3.6
• Following the analysis and solution proposals described
in D3.1 [17] and D3.2 [18], the HW and SW components
for all required 5G Radio, Core and Cloud Edge
capabilities to support the trials in the scope of the
5Growth project were deployed.
• A first version of software implementation for the
platform can be found in D3.3 [19] and pilot plan
descriptions in D3.4 [20].
• The development for the integration of the 5Growth
platform with ICT-17 (5G-EVE and 5G-VINNI) platforms
was completed, and in addition the new modules and
innovations developed within WP2 were integrated in
the platform. The final release of the software has been
published on public Github and reported in D3.5 [3].
Field trial the
5Growth pilots over
the 5G platform
deployed by 5G
EVE/5G-VINNI,
demonstrating
vertical use cases
including high-
WP3/T3.3
WP3/T3.4
WP3/T3.5
WP3/T3.6
• The deployed pilot platforms were tested for 5G network
performance level qualification to the demands,
especially of very low latency levels and very high data
rates, of the use cases to be validated, both over 5G EVE
and 5G VINNI platforms. Trial activities on all pilots were
performed over these deployments.
• The initial deployment of different pilots and field trial
experiments was reported in D3.4 [20].
D6.3: Final Project Report 42
H2020-856709
density scenarios and
very-high-data-
volume applications
• The final deployment of infrastructure at all the vertical
facilities and implementation of all the components and
selected innovations required for the trials at the vertical
sites for the execution of use cases for each of the pilots
within the project is documented in D3.6 [4].
Verification WP/task Details
Demonstrate 4
Industry 4.0 vertical
use cases through
pilot 1, 2 in field trials
(TRL 6/7)
WP3/T3.3
WP3/T3.4
• Both 5Growth I4.0 use cases (INNOVALIA and COMAU
use cases) have been completed, including the full
integration, execution and validation activities at the
vertical premises. The details on the final deployment of
INNOVALIA and COMAU pilots are reported in D3.6 [4].
o INNOVALIA Pilot: During this period, the 5TONIC
lab was available and was used for setting up and
validation while the implementation of the
infrastructure and the deployment of the
components was done on the vertical premises
at Bilbao. Both use cases within the pilot were set
up and experimented on a real-life industrial
environment.
o COMAU Pilot: during the second period,
completed the integration of all the components
distributed among different premises to
interwork with the previously implemented 5G
network and deployed components at COMAU
premises; further experiments with the use cases
were carried out.
• Both pilots have been selected in the top 10 list of the
EC H2020 5G Infrastructure PPP - PPP T&Ps Brochures
n°2 and n°3.
Demonstrate 2
transportation
vertical use cases
through pilot 3 in a
field trial (TRL 6/7)
WP3/T3.5 • During the second reporting period, the pilot activities
mainly aimed at the implementation of a complete 5G
network at Aveiro Harbor, getting connectivity with
5Growth and 5G-VINNI platforms, and the
experimentation of the use cases in a real-life
environment.
• The final results of EFACEC transportation pilot is
reported in D3.6 [4].
Demonstrate 2
energy vertical use
cases through pilot 4
in a field trial (TRL
6/7)
WP3/T3.6 • During the second reporting period, the pilot focused on
the set up of the use cases using the 5G SA network at
Aveiro University (in Secondary Substation and IT
buildings), leveraging on 5Growth and 5G-VINNI
platforms, and the experimentation of the use cases in a
real-life environment.
• The final results of EFACEC energy pilot are reported in
D3.6 [4].
D6.3: Final Project Report 43
H2020-856709
Objective 4 Evaluate technical and functional KPIs through 5Growth field trials
Description Validate technical KPIs, core 5G technologies and architectures in the context of
different performance requirements of different slice types (eMBB, mMTC, URLLC),
considering services linked to specific vertical sectors.
R&D Topics WP/task Details
Validate 5G core
technologies and
5Growth service
platform (vertical
slicer, service
orchestration,
infrastructure
manager) to satisfy
functional and
technical
requirements of
vertical use cases
WP4/T4.1 • Definition of Service KPIs and Core 5G KPIs based on
existing 5G-PPP KPIs and KPIs defined by the TMV-WG,
5G EVE and 5G-VINNI – specified in D4.1 [21].
• Mapping between Core 5G KPIs and Service KPIs –
reported in D4.1 [21].
• Application of the Service KPIs and their mapping with
Core 5G KPIs to the different pilots – reported in D4.1
[21].
• Mapping between the identified Service KPIs and the
vertical functional requirements for each pilot use case,
reported in D4.1 [21].
Validate end-to-end
5G network slicing
with differentiated
service requirements
(eMBB, mMTC,
URLLC use cases)
WP4/T4.2 • Initial verification methodology and tool design
reported in D4.2 [22].
• Design of a data engineering platform composed of
Data Connect, Data Ingest, Data Analysis, Data Storage
and Data Visualization, described in D4.2 [22]:
o data source,
o data aggregation,
o data consumers,
o metadata.
• Integration with 5Growth platform, reported in D4.2 [22]:
o Data descriptors,
o monitoring platform,
o innovations.
• Integration with ICT-17 platforms, reported in D4.2 [22]:
o 5G EVE,
o 5G-VINNI
• During the second reporting period, refined the
verification methodology and tooling design in D4.3 [5]
and provided the[22] final version in D4.4 [6]. This
provided a common approach for all pilots to the
execution of verification campaigns, and performing
measurements and in processing, integrating, and
making available the produced data for further
applications, including:
o The evolution of the data infrastructure based on
The Semantic Data Aggregator (SDA).
o The enhancements on the measurement tools.
o The definition of experiments descriptors.
D6.3: Final Project Report 44
H2020-856709
o The integration of these descriptors within an
experiment catalogue, able to support formal
referencing of experimental results. The 5Growth
experiment catalogue is public available on
GitHub: https://github.com/5growth/5gr-pilots.
Verification WP/task Details
Report assessing the
achieved KPIs across
5Growth use cases
WP4/T4.3
WP4/T4.4
WP4/T4.5
WP4/T4.6
• During the second reporting period, the last two
validations campaigns were executed, after the initial
one reported in D4.2 [22]. The first campaign, reported
in D4.3 [5], was executed at the ICT-17 facilities in use by
the project, allowing the team to refine the initially
verified tools and methodologies, and to exercise the
relevant KPIs in a controlled experimental environment
that reflects final deployment. The second campaign,
reported in D4.4 [6], included experiment deployments
at all vertical sites and their integration with the ICT-17
facilities, providing this way sound evidence of KPI
fulfilment in close-to-real operational conditions.
Besides this, an analysis of the application of specific
innovations was performed as well under these
conditions.
• Final evaluation and assessment of achieved KPIs
through filed trails at the vertical sites per pilot use case
is documented in D4.4 [6].
Objective 5 Dissemination, standardization and exploitation of 5Growth
Description Dissemination, standardization and exploitation of all concepts and technologies
developed in the 5Growth project.
R&D Topics WP/task Details
Outreach
communication to all
stakeholders
including the general
public
WP5/T5.1 • 5Growth web visits reached peaks of up to 90000 (in 365
days) and after that always had more than 55000.
• 5Growth has 780 followers on Twitter.
• 20 YouTube videos uploaded with 4600+ views for a
total of 223 hours with 139 subscribers.
• 764 LinkedIn connections and 211 Instagram followers
• Promotional material prepared (e.g., leaflets, posters,
videos, press releases), incl. appearance in the 5G PPP
Trials&Pilots brochures in its 2nd and 3rd edition.
• Participation in 7 events for society at large.
Dissemination to
relevant industrial
and academic
communities
WP5/T5.2 • A total of 21 events (co-)organized by 5Growth including
1) events organized by the project and talks given by
project partners targeting industry (like webinar
organized with Layer123 on Powering 5G in industry,
5Growth exploitation workshop, internal exploitation
workshops inside companies) or 2) events co-located
D6.3: Final Project Report 45
H2020-856709
with relevant renowned conferences (e.g., EUCNC’21,
IEEE CNSM’21)
• 27 Bachelor, Master and PhD theses and 5Growth results
introduced in 9 lectures prepared by academic partners.
Maximization of the
impact of project
innovations through
coordinated
exploitation activities
led by the innovation
manager
WP5/T5.2 • The exploitation strategy was reported as part of the
Communication, Dissemination, and Exploitation Plan
(CoDEP) in D5.7 [7] and also summarized in this
document.
• Various awards/recognitions were received by the
project (e.g., ETSI MEC Hackathon, 2021 Advanced
Factory finalist for Best industrial equipment for the
factory of the future, various best demo awards)
Contributions to top-
tier scientific journals,
conferences and
magazines
WP5/T5.2 • 81 peer-reviewed publications (34 conferences and 47
journals) in conferences such as ACM Mobicom, ACM
CoNext, IEEE INFOCOM, or journals such as IEEE JSAC,
IEEE TWC, IEEE TMC, as reported in D5.7 [7] and also
summarized in this document.
Contributions to
standardization
bodies
WP5/T5.2 • A standardization advisory committee (SAC) was formed
from 5Growth experts related to the relevant SDOs
(3GPP, IETF, ETSI, IEEE, …). The SAC supported partners
to contribute to SDOs and to disseminate the project
results.
• 85 SDO contributions submitted (3GPP: 38, IETF/IRTF:
20, ETSI: 10, IEEE: 16, GSMA: 1) out of which 43 were
adopted/accepted.
• Assessment of the contribution of 5Growth in support of
5G based on its contributions adopted by the SDOs
(3GPP, IETF/IRTF, ETSI, GSMA, and IEEE), listed in D5.7 [7]
and in this document.
Generation of IPR WP5/T5.2 • Partners patented 7 novel systems and/or methods
related to the innovation outcomes of the project.
• The project also contributed to seven Open Source
projects (e.g., ONOS, e.DO, OSM), and most notably, by
making publicly available the code for all its software
releases, which is available through the GitHub of the
project.
Verification WP/task Details
At least 10
publications per year
in top-tier scientific
journals and
conferences such as
WCNC, ICC,
INFOCOM,
GLOBECOM, IEEE
WP5/T5.2 • 81 accepted papers (47 journals and 34 conferences) in
top-tier scientific journals, conferences and magazines,
as reported in D5.7 [7] and in this document.
D6.3: Final Project Report 46
H2020-856709
COMMAG/WIRELESS
MAG, IEEE/ACM ToN
File at least 5 patent
applications
WP5/T5.2 • 7 patent applications filed.
At least 10 adopted
contributions to
SDOs such as 3GPP,
IETF, ETSI, IEEE, ITU
WP5/T5.2 • 85 contributions to SDOs: 38 to 3GPP, 20 to IETF/IRTF,
16 to IEEE, 1 to GSMA, and 10 to ETSI. Out of these 85,
43 have been adopted.
Organization of at
least 2 workshops
WP5/T5.1 • 21 organized events (e.g., workshops co-located with
renowned events, exploitation workshop) or co-
organized with other 5G PPP and Horizon 2020 projects.
• This includes industry-oriented events, such as the
5Growth Exploitation workshop
At least 2
demonstrations per
year, including one at
flagship event such
as MWC
WP5/T5.1 • 27 demonstrations at flagship events (incl. ACM
Mobicom, IEEE INFOCOM. Mobile World Congress),
including some best demo awards.
3.2. Explanation of the work carried per WP
3.2.1. WP1
This WP aims to revise and refine the technical and functional requirements initially defined per pilot,
based on Industry 4.0 cases (INNOVALIA and COMAU), Energy (EFACEC Energia) and Transportation
(EFACEC Engenharia e Sistemas). A definition of the different business models and their benefits, as
well as the overall effects on the various identified stakeholders was done. Besides, the methodology
to be used in the validation of the business models was identified and assessed.
A thoughtful study on the different economic streams and items that constitute each of the business
models was also carried out during in this work package. This helped to refine the different pilot’s
use cases from the perspective of the vertical, with special focus on their feasibility and profitability,
not only technical but also economical. The core capabilities enabled by the 5Growth project in each
pilot were studied and classified to assess which are to be prioritized from an end-user point of view.
Finally, building upon the work undergone throughout the rest of the project, a feasible, enhanced
Service Level Agreements (SLA) model was leveraged to complement the business analysis. This
provided the foundation for a properly defined and validated 5G business layer (OSS/BSS) model to
be applied over future advanced network services for vertical industries scenarios.
The WP is led by INNOVALIA and all WP1 partners contribute actively.
3.2.1.1. Task 1.1: Analysis of vertical industries’ requirements and business model definition
N/A. This task finalized in the first reporting period.
D6.3: Final Project Report 47
H2020-856709
3.2.1.2. Task 1.2: Techno-economic analysis and business model validation
This task has been led by TIM, supported by IDCC, TID, COMAU, EFACEC_S, EFACEC_E, INNOVALIA,
MIRANTIS, TELCA, and NKUA. The task is devoted to the Techno-economic analysis and business
model validation.
In this second period, the task has undertaken, in the first place, the reviewing and deepening of the
business models previously defined in task T1.1, to answer to the reviewers’ comments on the first
period progress review. In this sense, each of the partners representing one of the stakeholders
previously defined, has design its business model using the Osterwalder methodology (aka Business
Canvas Methodology), identifying the main blocks of the future exploitation options for the results
of the pilot.
Second, the techno-economic analysis that was reported in D1.2 has been refined, and aligned
among the four different pilots, in order to have a more coherent and understandable result.
Also, an additional step has been taken in this techno-economic analysis, splitting the benefits
identified among the main stakeholders in each pilot, in particular the vertical, network operators
and telecommunications manufacturers.
Some benefits not strictly related to the financial sector, have been identified, such as the reduction
of the environmental footprint due to the reduction of business trips thanks to new remote-control
capabilities of industrial equipment, the reduction of accidents in Industry 4.0 or, in the railways
vertical, in the level crossings.
All this work has been reported in the deliverable D1.3.
3.2.1.3. Task 1.3: SLA’s elicitation
This task is led by TID and requires the contributions from IDCC, TIM, ALB, COMAU, EFACEC_S,
EFACEC_E, INNOVALIA, TELCA, NKUA and SSSA.
The SLA elicitation and business layer modelling task was divided into four main blocks (Figure 2) to
split efforts and progress in a more efficient way: Discovery, Definition, Fulfilment and Adaptation.
D6.3: Final Project Report 48
H2020-856709
FIGURE 2. SLA'S ELICITATION PHASES
• In the Discovery block the interactions between the different stakeholders participating
in the 5Growth environment to discover their capabilities is discussed.
• In the Definition, the way these capabilities is transformed into SLAs is analysed.
• In the Fulfilment, the implementation and creation of a Data Model to transform core
KPIs to network KPIs as well as the enforcement of SLAs is studied.
• Finally, in the Adaptation block modifications such as scaling or new SLAs negotiation
are overseen.
Partners involved in the tasks have been grouped in 4 groups depending on their role in the pilots,
and each group has addressed one of the phases. In our weekly calls the work on these blocks is
discussed and aligned. Results will be reported in D1.3 to be delivered by the end of the project.
3.2.1.4. Deviations
There have been no deviations on the work of the WP
3.2.1.5. Corrective actions
No corrective actions have been needed for this WP.
3.2.2. WP2
WP2 is in charge of extending baseline 5G management platforms, with particular focus on that of
the 5G-TRANSFORMER project, to accomplish a series of technology innovations that satisfy 5Growth
use cases with unprecedented advantages in cost and network performance. WP2 completed its
activities in M24 (May 2021).
D6.3: Final Project Report 49
H2020-856709
The final design of the 5Growth platform is described in D2.3 [1]. For the sake of completeness, we
next briefly introduce its key components, shown in Figure 3.
FIGURE 3: 5GROWTH HIGH-LEVEL ARCHITECTURE
• The Vertical Slicer (VS or 5Gr-VS, as defined in the rest of the document to differentiate from
the old version of the Vertical Slicer developed in the context of the 5G-TRANSFORMER
project) is the front-end point for verticals demanding the provisioning and management of
vertical services via a simplified northbound interface with the vertical OSS/BSS. The 5Gr-VS
implements the functionalities for the management of vertical services and their mapping to
the end-to-end 5G network slices.
• The Service Orchestrator (SO or 5Gr-SO) handles both the network service and resource
orchestration capabilities of: (i) enabling end-to-end orchestration of NFV-Network Services
(NFV-NS) by mapping them across either a single or multiple administrative domains based
on service requirements and availability of the services/resources offered by each of the
domains; and (ii) managing their life-cycles (i.e., on-boarding, instantiation, update, scaling,
termination, etc.).
• The Resource Layer (RL or 5Gr-RL) is responsible for managing the local infrastructure
interacting with the underlying controllers (i.e., VIMs and WIMs). To this end, the 5Gr-RL
manages all the compute, storage, and networking (physical and virtual) resources where the
elements forming network slices and end-to-end services are accommodated.
• The Vertical-oriented Monitoring System (VoMS or 5Gr-VoMs) constitutes the monitoring
platform aiming to monitor heterogeneous set of services and technological domains. To do
D6.3: Final Project Report 50
H2020-856709
that, it offers required functionalities such as log aggregation, a scalable data distribution
system and dynamic probe reconfiguration.
• The AI/ML Platform (5Gr-AIMLP) is the entity that manages (i.e., deploys, configures and
trains) AI models relying on the data gathered from the VoMS. The 5Gr-AIMLP exposes a
catalogue of AI models, susceptible to be tuned/chained to come up with more complex
models, that are consumed by other components of the 5Growth stack for taking decisions
at different layers e.g., about service arbitration or service scaling.
• The Forecasting Functional Block (5Gr-FFB) aims at generating forecast values of parameters
monitored by the 5Gr-VoMS. These forecast values can be utilized by decision modules of
the platform to take a proactive approach in reacting to changing status. The 5Gr-FFB
interacts with the 5Gr-AIMLP (to request trained models to be utilized in forecasting tasks),
with the 5Gr-VoMS (to retrieve parameters to be forecast as well as to provide forecast data
to be used as input for other decisional elements like the 5Gr-SO), and with other main
functional elements of the 5Growth architecture, such as the 5Gr-SO.
A publicly available software implementation of the relevant 5Growth software components is
presented in [2] and references therein.
3.2.2.1. Task 2.1: 5G End to End Service Platform
This task supervised the design and development of the 5Growth End-to-End Service Platform, by
leveraging the 5G-TRANSFORMER architecture and its software implementation. CTTC is the task
leader, with contributions from UC3M, NEC, TEI, NBL, TID, ALB, MIRANTIS, NXW, TELCA, NKUA,
POLITO and SSSA. The execution of this task was carried out via weekly calls and with dedicated slots
in the plenary meetings organized until the end of the WP2 timeline.
During this second reporting period, T2.1 ensured the successful completion of the release plan
presented during the first reporting period, which included (i) design and develop those innovations
that were not addressed during the first reporting period, and (ii) design and develop the second
and final version of those core innovations that were introduce during the first reporting period. In
total, 12 innovations were designed:
TABLE 16: WP2 INNOVATIONS
Cluster Category Innovation
Arc
hit
ectu
re Vertical support
I1: RAN segment in network slices
I2: Vertical-service monitoring
Monitoring orchestration I3: Monitoring orchestration
Control and management I4: Control-loops stability
I5: AI/ML support
E2E orchestration I6: Federation and inter-domain
I7: Next Generation RAN
Alg
ori
t
hm
s
Smart orchestration and resource
control algorithms
I8: Smart orchestration and resource control
algorithms
Anomaly detection I9: Anomaly detection
D6.3: Final Project Report 51
H2020-856709
Forecasting and inference I10: Forecasting and inference Fra
mew
ork
Security and auditability I11: Security and auditability
5Growth CI/CD and containerization I12: 5Growth CI/CD and containerization
A major responsibility of this task was to ensure that the work done across all the innovations
developed within WP2 fill all the gaps (features) identified during the first reporting period, which
was successfully accomplished as summarised Table 17.
TABLE 17: MAPPING BETWEEN PLATFORM REQUIREMENTS (GAPS) AND SELECTED INNOVATIONS
Feature (gap) I1 I2 I3 I4 I5 I6 I7 I8 I9 I10 I11 I12
Enhanced VS network
slice sharing
X X
VS arbitration at
runtime
X X X X X
VS layer federation X
VS dynamic service
composition
X X X
SO automatic network
service management
X X X X X X X X
SO self-adaptation
actions
X X X X X X X
SO dynamic monitoring
orchestration
X X X X
SO geo-location
dependent federation
X X
RL PNF integration X X
RL geo-specific
resources
X
RAN support X X X
Integral security X
Continuous
development and
integration
X
Additional activities performed within T2.1 were the design and implementation of Innovation 5
(AI/ML support), Innovation 6 (Federation and interdomain), and Innovation 7 (Next-Generation
RAN).
I5: AI/ML Support
The 5Growth AIML (Artificial Intelligence and Machine Learning) Platform (5Gr-AIMLP) enables the
exploitation of AI/ML models for the various decision-making processes necessary in a 5G
D6.3: Final Project Report 52
H2020-856709
management and orchestration stack, and is in charge of the ML model lifecycle management
(including ML model uploading, catalogue building, and ML model training).
The models can be uploaded to the 5Gr-AIMLP by any authorized external user. Such models can be
already trained and onboarded to then perform inference, or they can be untrained models.
In the latter case, if no dataset is uploaded along with the untrained model, the 5Gr-AIMLP can
exploit the data collected through the 5Gr-VoMS platform about network/computing resource
utilization, or performance. The configuration of the monitoring platform to gather the monitored
data, its aggregation through Kafka and Spark Streaming, and their feeding as input for real-time
model execution in the corresponding 5Growth building block also need to be properly set up.
Models stored in the 5Gr-AIMLP can be accessed by any entity in the 5Growth architecture through
a REST interface.
FIGURE 4: 5GR-AIMLP REPRESENTATION
The 5Gr-AIMLP has been implemented by developing the following components:
• External User Interface, i.e., a Graphical User Interface (GUI) through which users can upload
the ML models, and the related datasets and inference classes;
• Model Registry, which records the models uploaded to the platform, their metadata, and
pointers to the stored models and associated files;
• Lifecycle Manager, which is in charge of the model’s lifecycle;
• Interface Manager, i.e., a REST API that processes the ML model requests coming from the
architectural stack and forwards them to the proper block inside the computing cluster.
• Computing cluster, implemented through Apache Hadoop and leveraging Yet-Another-
Resource-Negotiator (YARN) for the computing resources management, and the Hadoop
Distributed File System (HDFS) for the storage of datasets and models. The YARN cluster
nodes have access to different AI/ML frameworks, according to the requested model type,
namely, Spark, BigDL, and Ray.
A graphical representation of the 5Gr-AIMLP is presented in Figure 4.
D6.3: Final Project Report 53
H2020-856709
I6: Federation and Inter-domain
5Growth service providers are able to extend their offering by aggregating the service catalogue and
resources from other peering providers through federation and inter-domain support. There are
different types of services that can be handled, namely communication services, network slices, and
NFV network services. The communication services and network slices are handled between 5Gr-VSs
of two domains. The NFV network services are handled between peering service orchestrators. As for
resource federation, it is handled at the service layer (between peering service orchestrators). The
diversity of services and technologies leads to new stakeholders and dynamic scenarios where the
cooperation requires more rapid interaction. In this context, novel concepts such as Distributed
Leger Technology (DLT)-based federation has the potential to bridge the gap and satisfy the
emerging requirements. Figure 5 depicts the three architecture building blocks of 5Growth (5Gr-VS,
5Gr-SO, 5Gr-RL) that are involved in federation/multi-domain relations are shown. On the left-side
is illustrated a consumer domain, while on the right side, a provider domain. Several options, as
described in the figure were designed during this reporting period.
FIGURE 5: FEDERATION/MULTI-DOMAIN ARCHITECTURE
I7: Next-Generation RAN
During this reporting period, T2.1 invested effort in integration the O-RAN architecture functional
components and interfaces into the 5Growth platform.
D6.3: Final Project Report 54
H2020-856709
FIGURE 6: INTEGRATION OF O-RAN INTO 5GROWTH ARCHITECTURE
Figure 6 presents the conceptual integration of O-RAN services and interfaces into 5Growth
architecture. Specifically, the Non-RT RIC services are distributed across the 5Gr-VS, 5Gr-SO, and
the 5Gr-RL:
• The 5Gr-VS host rApps specifically in charge of business and vertical service related tasks,
such as devising RAN coverage area parameters. In order to do so, the rApps will leverage
QoS parameters established for the vertical service, slice service type associated with the
service and the other specific instantiation constraints, such as the desired coverage area of
the service.
• The 5Gr-SO hosts most of the services of the non-RT RIC, including the non-RT RIC framework
and the rApps in charge of RAN service and resource related tasks. It also hosts some O2
services to interact with the VNFM in the O-Cloud.
• The 5Gr-RL only hosts the O1 termination endpoint between the Non-RT RIC and the
respective managed elements.
3.2.2.2. Task 2.2: Enhanced and automated vertical support
Task 2.2 was led by NXW and supported by UC3M, NEC, NBL, TIM, TID, ALB, MIRANTIS, TELCA, CTTC,
IT, NKUA, POLITO and SSSA. During the second reporting period, the activities within T2.2
contributed to the delivery of the final design and implementation of two key innovations.
D6.3: Final Project Report 55
H2020-856709
I1: RAN segments in network slices
A first version of this innovation was already presented during the first reporting period. The 5Gr-VS,
5Gr-SO and 5Gr-RL information models and interfaces have been updated in order to support the
definition of the vertical service RAN characteristics and the allocation and configuration as part of
the vertical service deployment.
At the 5Gr-VS level, the support of RAN slices required updating the information models of the
Vertical Service Blueprints (VSBs) and Vertical Service Descriptors (VSDs) in order to let the 5Gr-VS
determine mobile traffic category of the vertical service and to allow the vertical to customize the
specific value required for each traffic characteristic. During the vertical service deployment, the 5Gr-
VS computes the final list of mobile traffic characteristics based on the VSB, VSD information, and
the translation rules. This information is included in the NFV-NS Instantiation request which is sent
to the 5Gr-SO as part of the service access point (SAP) data (sapData), associated to the SAP
accessible from the RAN (using an updated VS-SO interface). This innovation also required the
support Physical Network Function Descriptors (PNFDs) onboarding, in order to include the mobile
infrastructure equipment as part of the NFV-NS definition.
Concerning the 5Gr-SO, the support of RAN segments in network slices implied several changes to
include the management of PNFs enabling the match of the requests of the 5Gr-VS at the NBI with
the abstracted resource representation (e.g., list of supported PNF and RAN capabilities of available
NFVI-PoP) provided by the 5Gr-RL at the SBI.
At the 5Gr-RL, the main issue was that radio resources could not be virtual but formed by physical
devices that have some firmware already up and running. Following ETSI MANO specifications, such
devices require the handling of a new type of network function called Physical Network Function
(PNF). In addition to that, RAN network slicing required the application of radio specific commands
to radio devices. PNF support led to introduce extensions in 5Gr-RL in the abstraction of the radio
physical resources and the management of resources for radio VNF/PNF. The application of radio
specific commands for network slice configuration required the handling of a new type of
information through the radio Management Function (MF).
I9: Security and auditability
The tighter integration of business verticals into network operations, as in the 5G Vertical Slicing use-
cases, raises significant security, trustworthiness, and reliability issues. A single business vertical must
not compromise the integrity of the platform that powers all other verticals. Similarly, the vertical
applications that are entrusted to the platform should not be compromised by external parties. The
use of standardized protocols, and the reuse of similar software solutions, substantially lowers the
cost of an attack. One vulnerability within a component of this stack now covers a broader range of
potential targets.
To achieve a successful attack and exploitation of a target, the attacker must first do a reconnaissance
of the virtual surroundings, identifying the objectives, along with the vulnerabilities of each service
that may lead to its goal. Security vulnerabilities are mostly a particular kind of software bug, and
bugs tend to be revealed over time. Therefore, time is on the attackers' side to find and exploit a
D6.3: Final Project Report 56
H2020-856709
vulnerability, while network function maintainers have time playing against their security designs;
this effect of time is known in the Mobile Threat Defense (MTD) field as the asymmetric relationship
between attackers and defenders.
A major effort during the second reporting period was to enhance the 5Gr-VS and related interfaces
with MTD features. The core principle of MTD is to identify the available network configuration space
and dynamically explore it (i.e., create movement) to frustrate the attackers' endeavours. Provided
the attacker does not know the secret that creates the movement, the MTD mechanism will break
the attacker's connectivity to the service or forge data (or interactions) so that the attacker acts upon
faulty intelligence. Our solution is inspired by the HMAC-based authentication methods already
widely deployed by other network services. On the one hand, those HMAC-based authentication
methods do not replace the existing account authentication mechanisms but complement them with
an extra factor. The MTD approach has similar nature, adding an extra factor to the existing defense
mechanisms (e.g., firewalls, Intrusion Detection Systems (IDSs), or Intrusion Protection Systems
(IPSs)). On the other hand, the HMAC-based authentication methods in other network services
already established practices that deal with peer synchronization, peer management, and key
management issues. Our mechanism uses a slightly adapted authentication function to mutate the
service ports, maintaining the familiarity and proofs of a widely known solution.
3.2.2.3. Task 2.3: Telemetry monitoring, analytics and orchestration
This task was led by MIRANTIS, with contributions from UC3M, NEC, TIM, TID, COMAU, NXW, CTTC,
NKUA and SSSA.
The main work carried out during the second reporting period involved the final design and
implementation of the Vertical-oriented Monitoring System (VoMS) in the context of Innovation 2,
and the design of Innovation 3 (Monitoring Orchestration). In addition, effort within this task was
placed to support T2.1 and T2.4 to design algorithmic solutions and the 5Gr-AIMLP.
The 5Gr-VoMS Release 1 (released at M12 and described in D2.2) was dynamically exporter
(monitoring probe) installation oriented. The 5Gr-VoMS Release 2 (developed during this second
reporting period) implements additional features such as gathering application metrics and
collecting logs from VNFs.
Concerning Innovation 3, this innovation provides automation capabilities to the 5Gr-VoMS,
achieving the integration of features related to the full control of the lifecycle of the monitor
functions instances that compose the Monitoring Platform, among other capabilities that will be
reviewed in this section. The extraction of monitoring information from vertical service is critical for
the training and execution of the AI/ML based algorithms used in the control-loops, and this
innovation enables to install on-demand the agents and probes which enable this extraction.
Moreover, it allows to modify the metrics extracted from the vertical service over time, in order to
use every time more evolved control-loops algorithms.
The final version of the 5Gr-VoMS architecture is described in Figure 7.
D6.3: Final Project Report 57
H2020-856709
FIGURE 7: VERTICAL-ORIENTED MONITORING SYSTEM ARCHITECTURE
The 5Gr-SO interacts with the 5Gr-VoMS through the Monitoring Manager and the SLA Manager,
which are part of the 5Gr-SO. The Monitoring Manager is the component in the 5Gr-SO translating
requests for high-level monitoring jobs referred to NFV service instances into low-level requests
related to the monitoring of resource-level parameters, describing which exact data should be
collected by the 5Gr-VoMS.
The SLA Manager deals with SLA assurance. This component is keeping track of monitoring
parameters like KPIs or real-time measurements mirroring the load of the resources. This allows
indicating potential SLA breaches or anomalous behaviour that may lead to system under-
performance. The SLA Manager interacts with the 5Gr-VoMS following a subscription-notification
paradigm, to promptly react to any alert associated with the target monitoring data. In particular,
the SLA Manager subscribes with the Config Manager, registering monitoring parameter queries
D6.3: Final Project Report 58
H2020-856709
(which may include arbitrarily complex expressions on many different time series) and threshold
values for notifications. Such subscription is translated into the appropriate configuration of the
Prometheus Alert Manager or ElastAlert so that whenever the given threshold is passed, a notification
is sent to the SLA Manager, which will then trigger the needed reactions at the 5Gr-SO.
The 5Gr-VoMS is responsible for the next functionalities of the 5Growth stack:
• VNF logs and metrics collection;
• holding metrics and logs;
• tracking metrics and logs;
• providing metrics and logs to other systems (AI/ML platform, forecasting functional block,
etc.);
• checking if the metrics data is corresponding to KPIs thresholds.
3.2.2.4. Task 2.4: Closed-loop automation, SLA modeling and control for vertical service.
Task 2.4 was led by NBL, with contributions from UC3M, NEC, TID, COMAU, MIRANTIS, NXW, TELCA,
CTTC, NKUA, POLITO and SSSA.
During this period, T2.4 finalized Innovation 4 (Control-loops stability) and a number of revised and
new algorithms covering Innovations 8 (smart orchestration and resource control), 9 (anomaly
detection), and 10 (forecasting and inference).
I4: Control-loops stability
This innovation introduced methods to performing automated close-loop process handling: (i) the
automated update of arbitration policies at the vertical slicer (5Gr-VS) level for automated slicing
optimization; (ii) and the automated scaling of network services at the service orchestrator (5Gr-SO)
level; leveraging on the AI services provided by the 5Gr-AIMLP developed in Innovation 5. The
integration of AI features into the 5Growth architecture follows the O-RAN architectural concepts
where there is a split between training and model execution. Specifically, the 5Gr-AIMLP performs
the model training and provides trained-model to other building blocks of the 5Gr architecture,
which performs the inference.
I8: Smart orchestration and resource control algorithms
Three groups of algorithmic solutions were developed during the second reporting period (some
of which began its work during the first period):
1) 4x Smart orchestrations:
a. Genetic Algorithm based SFC placement
b. VNF Autoscaling
c. AI-driven scaling of C-V2N Services
d. Slice sharing at the 5Gr-VS
2) 2x resource abstraction and allocation
a. 5Gr-SO – 5Gr-RL: Resource abstraction and allocation algorithms
b. Performance isolation to support network slicing
D6.3: Final Project Report 59
H2020-856709
3) A Dynamic Profiling Mechanism (DPM)
I9: Anomaly detection
An anomaly detection framework was designed during this reporting period. The proposed
framework comprises three main phases which are illustrated in Figure 8. The first phase involves the
pre-processing of the input data, along with the feature extraction step. Table 18 illustrates the
features of the training dataset. It should be noted that the pre-processing of the features includes
a min-max normalization, transforming every value in the [0,1] interval, so that each feature
contributes in a proportional manner to the ML models that will be applied.
FIGURE 8: ANOMALY DETECTION ALGORITHMIC FRAMEWORK
TABLE 18: NETWORK KPIS USED AS FEATURES FOR THE TRAINING SET
Feature Name Description
lost_packet # of lost packets, per service per user
ul_delay Uplink delay (ms)
dl_delay Downlink delay (ms)
rsrp RSRP (dB)
transfer_protocol TCP or UDP encapsulated [0,1]
ulrx_cell UE bytes received from the cell
The next phase concerns the exploitation of a clustering method using an unsupervised machine
learning clustering model, where outliers and abnormal patterns of the time series are grouped
together. The applied algorithm used for this step is Hierarchical Density-Based Spatial Clustering
(HDBSCAN), which is an extension to Density-Based Spatial Clustering (DBSCAN) by converting it
into a hierarchical clustering algorithm. HDBSCAN is a robust clustering approach for anomaly
detection in time series, which can capture, as well as predict, clusters of varying densities. The
number of clusters is determined beforehand and is based on how many severity levels a network
administrator targets, thus increasing the granularity of the prediction. Therefore, by adjusting the
epsilon value of the distance metric of the model, the number of clusters formed is also changed
(e.g., a large distance value generates two clusters [-1,1], which means that samples with assigned
cluster 1 are normal and -1 anomalies).
Finally, the last phase of the proposed framework includes a feed-forward Deep Neural Network
(DNN), which is exploited to perform a classification task, with the training dataset as input, along
D6.3: Final Project Report 60
H2020-856709
with each cluster as the Label/Target value for each sample, as assigned by the previous phase. More
specifically, the DNN model consists of 5 layers X→64→64→32→Y, where X is the number of features
in each sample and Y the number of clusters determined by the clustering algorithm (one-hot
encoded), Rectified Linear Unit (ReLU) activation function, and categorical cross-entropy as a loss
function. The aforementioned classification scheme is then used to assign a cluster to new and
unseen data in real-time and hence predict potential system anomalies.
I10: Forecasting and Inference
The 5Growth Forecasting Functional Block (5Gr-FFB) is a functional block, introduced in the final
release of the platform, devoted to the computation of forecasting values for given metric(s) of a
Network Service. It behaves like a probe, which, consuming the current data related to the selected
metric(s), provides a forecasted data stream according to the used model.
The 5Gr-FFB has been designed to interact with other components of the 5Growth architecture, i.e.,
the 5Gr-SO, the 5Gr-VoMS and the 5Gr-AIMLP. It has been implemented in python, relying on
different standard libraries. In general, the 5Gr-FFB interacts with other 5Growth orchestration
modules:
1. 5Gr-SO: receiving as input all the data required, to activate a forecasting job. The input data
includes: the NS details, the metric(s) to be forecasted and the current metric(s) objecID(s).
2. 5Gr-AIMLP: to retrieve the model to be used for the forecasting. It can be a pre-trained model
(pre-uploaded) or it can be trained using current data.
3. 5Gr-VoMS: to gather the current monitored data, stored in Prometheus, and to enable
Prometheus jobs to poll forecasting data. In this perspective, the 5Gr-FFB is able to activate
ad-hoc scraper jobs, in order to enable the streaming of the current monitored data (serving
as input for the forecasting) on a specific topic in Kafka.
The 5Gr-FFB software architecture is shown in Figure 9.
FIGURE 9. 5GR-FFB HIGH LEVEL SOFTWARE ARCHITECTURE
D6.3: Final Project Report 61
H2020-856709
3.2.2.5. Deviations
The work package accomplished all its objectives in M24 as planned, with no deviations.
3.2.2.6. Corrective actions
No corrective actions were needed.
3.2.3. WP3
WP3 takes care of implementing and deploying all 5Growth pilot sites, including software and
hardware components for all planned use cases, integrating and executing the vertical use cases over
the ICT-17 sites interworking with 5Growth platform.
WP3 is led by ERC and requires active contribution from all 5Growth partners (with the exception of
NKUA, which does not participate in WP3).
For the period from M19 to the end of the project, the remaining objectives were:
• to develop and publish the final release of the software for the integration of the 5Growth
platform with ICT-17 (5G-EVE and 5G-VINNI) platforms. This software was published on
Github and documented in D3.5 [3].
• to implement the infrastructure on the vertical facilities and deploy all the components
required for the execution of the use cases for each of the pilots within the project. The
outcome of this work is documented in D3.6 [4].
3.2.3.1. Task 3.1: ICT-17 facilities gap analysis
This task was fulfilled in full scope on M5, so there was no effort required during this second period.
3.2.3.2. Task 3.2: Platform implementation and deployment in ICT-17 and vertical premises
Task T3.2 focused on the actual deployment of the identified components required for the vertical
trials into ICT-17 platforms and vertical sites, which includes the 5Growth platform. This task included
the development and the integration of the software extensions for the interworking of the 5Growth
platform with the ICT-17 platforms, and the addition of the new modules developed within WP2 to
the platform.
The execution of this task was led by UC3M with key contributions from NEC, ERC, IDG, NBL, TEI, TID,
ALB, COMAU, EFACEC_S, EFACEC_E, INNOVALIA, MIRANTIS, NXW, TELCA, CTTC, IT, POLITO and SSSA.
During this period, the work performed targeted the correction of bugs of the software delivered in
the first release, the production of extra functionalities required for COMAU pilot and the addition
of the WP2 innovations to the platform.
D6.3: Final Project Report 62
H2020-856709
The final software artifacts regarding the 5Growth and ICT-17 integration are summarized in Table
19. They contain the processes (e.g., instantiation, termination…) needed for the E2E deployment of
vertical services. They are available in a public GitHub.
TABLE 19: 5GROWTH & ICT-17 PLATFORM SOFTWARE ARTIFACTS
5Growth Platform ICT-17 Platform
5Growth &
5G EVE
Integration
Generic 5Gr-VS level integration
approach 5G EVE IWL Catalogue Driver
5Gr-VS Driver for 5G EVE Portal API 5G EVE IWL Lifecycle Manager Driver
5Growth &
5G-VINNI
Integration
5Gr-VS driver for SONATA
HTTP REST server for SONATA
Transformation from JSON to YAML
SONATA client
Additionally, a plugin was developed in the 5Growth Resource Layer (5Gr-RL) to interact with the
RAN controller used in COMAU pilot. This enables that some RAN parameter values can be specified
in the Vertical Service Descriptors according to the needs of the service.
Finally, the new modules were incorporated to the 5Growth software stack base for potential future
use in the pilots.
3.2.3.3. Task 3.3: Integration with vertical systems and execution of the I4.0 INNOVALIA
Pilot
This task was devoted to the integration and execution of the I4.0 INNOVALIA Pilot. The execution
of this task was led by ERC and demanded active contributions from NEC, IDG, NBL, TID, INNOVALIA,
MIRANTIS, NXW, TELCA and CTTC. During this period, the 5Tonic lab was available and was used for
setting up and validation of INNOVALIA pilot UC2; the implementation of the infrastructure and the
deployment of the components was done on the vertical premises at Bilbao corresponding to the
phase II deployment detailed in D3.2 and D3.4; and both use cases within the pilot were set up and
experimented on a real-life industrial environment.
The 5G network was installed at vertical facilities, as Figure 10 illustrates:
D6.3: Final Project Report 63
H2020-856709
FIGURE 10: ANTENNAS AT INNOVALIA FACTORY
The 5Growth stack was deployed on servers at vertical premises to allow the applications to run on
the edge of the network thus keeping the latency low. Additionally, the VPN between INNOVALIA
site and 5Tonic lab was implemented to use the 5G core and the 5G-EVE platform located at 5TONIC.
The use case devices, such as the 3D-scanner and the AGV, were carried to the facilities as well (see
Figure 11), so the experiments could be run at the factory.
FIGURE 11: EXPERIMENTATION AT INNOVALIA PREMISES
D6.3: Final Project Report 64
H2020-856709
The WP2 innovations implemented for testing within this pilot were I6 “End-to-End Orchestration:
Federation and Inter-domain” and I8 “Performance isolation approach on network slicing to retain
bandwidth and delay guarantee”.
In addition to the work performed in Bilbao, Interdigital (IDCC) deployed and experimented the “End-
to-end immersive robotic telepresence over 5G network” PoC on the 5G-VINNI facilities based in UK.
This was needed to be able to make progress locally in the validation of the telepresence solution,
as there were international travel bans and other limitations imposed by the COVID-19 crisis. The
solution integrates the end devices, an image recognition application running on the network edge
and a telemetry framework for metrics collection.
3.2.3.4. Task 3.4: Integration with vertical systems and execution of I4.0 COMAU Pilot
This task was devoted to the integration and execution of the I4.0 COMAU Pilot. The execution of
this task was led by TEI and demanded active contributions by IDG, TIM, COMAU, MIRANTIS, NXW,
CTTC, POLITO and SSSA. Since M19 to the end of the project, the partners focused on integrating all
the components distributed among different premises to interwork with the previously implemented
5G network and deployed components at COMAU premises; they have further experimented with
the use cases; and they have implemented and tested WP2 innovations.
A first TIM lab which hosted the 5Growth platform and the COMAU IIoT application, and a second
TIM lab which hosted the 5G-EVE platform were integrated. They connected between them and to
the COMAU experimental area through VPNs. Moreover, the Ericsson and Polito labs were also
connected to the other labs for remote configuration and support purposes. This architecture is
depicted in Figure 12.
FIGURE 12: SITES IN COMAU PILOT
D6.3: Final Project Report 65
H2020-856709
With the aforementioned distribution, the applications needed for the use cases are deployed on the
network edge, their lifecycle is handled by the 5Growth platform, and they get extra functionalities
from the 5G-EVE platform. In Figure 13 below it is shown the experimental area at COMAU.
FIGURE 13: EXPERIMENTATION AT COMAU FACILITIES
The WP2 innovations implemented for testing within this pilot were I1 “Support of Verticals: RAN
segments in network slices”, I2 “Support of Verticals: Vertical Service Monitoring”, I3 “Monitoring
Orchestration” and I6 “End-to-End Orchestration: Federation and Inter-domain”.
3.2.3.5. Task 3.5: Integration with vertical systems and execution of Transportation
EFACEC_S Pilot
This task was devoted to the integration and execution of the Transportation EFACEC_S Pilot. The
execution of this task was led by ALB and demanded active contributions by EFACEC_S, MIRANTIS,
NXW, CTTC, IT and SSSA. Since M19, the activities mainly aimed at the implementation of a complete
5G network at Aveiro Harbor, getting connectivity with 5Growth and 5G-VINNI platforms, and the
experimentation of the use cases in a real-life environment.
To this end, all the activities of analysis, design and implementation of the 5G network were
performed, leading to a functional 5G network on site. The antenna (see in the Figure 14 below) was
installed on top of a water tower to provide coverage over the desired train level-crossing area.
D6.3: Final Project Report 66
H2020-856709
FIGURE 14: ANTENNA AT AVEIRO HARBOR
Concerning the experimentation, the required devices were installed to allow the use cases testing,
as it is evidenced in Figure 15.
FIGURE 15: TRAIN DETECTOR AND EQUIPMENT
The WP2 innovations implemented for testing in the pilot were I6 “End-to-End Orchestration:
Federation and Inter-domain” and I11 “Security and auditability”.
3.2.3.6. Task 3.6: Integration with vertical systems and execution of Energy EFACEC_E Pilot
This task was devoted to the integration and execution of the Energy EFACEC_E Pilot. The execution
of this task was led by ALB and demanded active contributions from EFACEC_E, MIRANTIS, NXW,
CTTC and IT. During this period, the work performed focused on the set up of the use cases using
the 5G SA network at Aveiro University (in Secondary Substation and IT buildings), leveraging on
5Growth and 5G-VINNI platforms, and the experimentation of the use cases in a real-life
environment.
D6.3: Final Project Report 67
H2020-856709
The 5G and vertical components were moved to the Secondary Substation at Aveiro University, as
planned. Figure 16 below shows their final location. The end user devices got connectivity to the
control centre through the 5G network.
FIGURE 16: 5G CPE AND RU AT SECONDARY SUBSTATION
Then, the experimentation of the use cases was performed, being supervised remotely from the
control centre. See as an example the control centre operator graphical interface in the following
Figure 17.
FIGURE 17: EXPERIMENTATION AT AVEIRO UNIVERSITY
The WP2 innovations implemented for testing in the pilot were I6 “End-to-End Orchestration:
Federation and Inter-domain” and I11 “Security and auditability”.
D6.3: Final Project Report 68
H2020-856709
3.2.3.7. Deviations
The work package accomplished all its objectives in M30 with no deviations, as planned after the
extension implemented after the first technical review. This was in line with the 3-month delay
forecasted in D6.2 due to the restrictions and limitations imposed by the COVID-19 crisis (the
mobility restrictions hindered the mandatory on-site work). In particular, T3.2 was completed on full
scope in M24, as originally planned, because the work mostly concerned software development,
which does not require on site physical presence. Tasks T3.3 to T3.6 were originally planned to end
in M27 but extended to M30 to be completed on full scope, impacted by the difficulties for working
on-site.
3.2.3.8. Corrective actions
WP3 partners sticked to the mitigation plan defined from the very start of the COVID-19 pandemic,
prioritizing the software development and online activities, and coordinating very well to minimize
the on-site visits down to the essential. Furthermore, an extra effort was done to get aligned with the
other WPs, especially with WP4 not to incur in additional delays.
With this approach, even though WP3 could not revert the delay caused by the COVID-19 outbreak
because the recommendation during the full period was to avoid physical contact, the work was
completed with no further delays than the already predicted 3 months anticipated in D6.2.
3.2.4. WP4
WP4 main objective was to evaluate core (network) and service (application) KPIs through the
5Growth field trials, validating the applicability of 5G technologies to the different use cases
considered by the project pilots. These did not only include the execution of the different verification
campaigns, but also the definition of the measurement and testing methodologies applied in the
campaigns. WP4 was committed to provide a detailed description of these methodologies and a
series of tools to enable the automation of the verification procedures, the processing of the
measurement data and the reproducibility of the verification results. This way, WP4 was focused not
only on performing pilot verification, but also on doing so in a systematic way. The latter guaranteed
scientific (engineering) quality and contributed to make these findings and tools for their application
elsewhere.
The work in WP4 was aligned with WP2 and WP3 activities, addressing three innovate-deploy-
validate cycles during the project lifetime. WP4 applied the appropriate releases produced by WP3,
incorporating specific modules produced in WP2, and selecting the applicable experimental
environment for the corresponding cycle, comprising:
1. Data sources and consumers, including the metadata for them.
2. External tools to be applied, available through the project tool catalogue.
3. Specific measurement methods, documented in the deliverables.
D6.3: Final Project Report 69
H2020-856709
Pilot use cases were validated in the context of the successive releases of the experimental
environments, and reported in the associated deliverable, including the environment characteristics
and the outcome of the verifications run during the period.
The verification methodology and associated tooling provide the common substrate to the execution
of verification campaigns, working to:
1. Enhance the quality of verification campaigns.
2. Guarantee repeatability and reproducibility as essential features of experimental reports.
3. Contribute to a better understanding of the mechanisms to aggregate and process telemetry
data for data-enabled network management.
Validation campaigns were intended to collect evidence about the fulfilment of the core 5G and
service KPIs in the contexts of the different pilots, analysing the collected data and producing reports
to verify the applicability of 5G technologies in the associated scenarios. Ultimately, the validation
campaigns had the scope of assessing the fulfilment of the Key Performance Indicators (KPIs) starting
from the Service KPIs, which are high-level abstractions of the business requirements (not directly
measurable) and directing the validation towards the related Core KPIs (e.g., latency, throughput,
availability, etc.). The Core KPIs were measured by either specific test setups or alternative
methodologies.
During the reported period, the two last validations campaigns were executed, after the initial one,
used to validate the planned experimental and measurement configurations. The first campaign,
reported in D4.3, was executed at the ICT-17 facilities in use by the project, allowing the team to
refine the initially verified tools and methodologies, and to exercise the relevant KPIs in a controlled
experimental environment that reflects final deployment. The second campaign, reported in D4.4,
included experiment deployments at the participating vertical sites and their integration with the
ICT-17 facilities, providing this way sound evidence of KPI fulfilment in close-to-real operational
conditions. Besides this, an analysis of the application of specific innovations was performed as well
under these conditions.
3.2.4.1. Task 4.1: Service KPI identification and core KPI characterization
Though this task was not active during the reported period, the experience during the two reported
validation campaigns allowed for a refinement of some of the validation methods applicable to the
different use cases, reported in the corresponding sections of D4.3 and D4.4
3.2.4.2. Task 4.2: Verification methodology and tooling
Task T4.2 was in charge of methodologies and tools applied for performing measurements and in
processing, integrating, and making available the produced data for further applications. Task 4.2
provided the common substrate to the execution of verification campaigns, working to enhance their
quality, guarantee repeatability and reproducibility as essential features of experimental reports, and
D6.3: Final Project Report 70
H2020-856709
contributing to a better understanding of the mechanisms to aggregate and process telemetry data
for data-enabled network management.
This task was led by TID, with UC3M, IDG, NBL, ALB, COMAU, EFACEC_S, EFACEC_E, INNOVALIA,
MIRANTIS, NXW, TELCA, CTTC, NKUA and SSSA as contributors. The work of this task was reported
in D4.3 and D4.4, describing:
1. The evolution of the data infrastructure. The data infrastructure can deliver aggregated data for
further analysis. The Semantic Data Aggregator (SDA) is the monitoring framework that the data
infrastructure builds upon, and a final release of the SDA has been produced, addressing the
evolution of the architecture, the addition of new features, and the integration of data consumers.
The SDA moved towards a microservice-based architecture where a combination of lightweight
pieces of software provides the framework’s features. This approach allows for the developers to
implement the business logic at their own pace.
FIGURE 18: MICROSERVICE-BASED ARCHITECTURE OF THE SDA
2. The enhancements on the measurement tools developed and/or applied within the project,
including the development of three additional tools for the KPI evaluation: a Log Management
Tool for service orchestration, fully integrated with the data infrastructure via the 5Growth
Monitoring Interface, a Passive Network Interface Probe, designed to report average throughput
measures towards the data infrastructure, and in-band network telemetry modules to be
deployed on programmable network forwarding elements based on P4.
D6.3: Final Project Report 71
H2020-856709
FIGURE 19: GLOBAL ARCHITECTURE FOR 5GROWTH LOG PARSER
3. The definition of experiments descriptors, a formal model for experiment definition intended to
guarantee reproducibility (across different laboratory environments) and repeatability (under
controlled variations of the experimental conditions) of experimental results. These descriptors
provide a common template, which includes elements to describe the service deployment in the
target testing environment, the metrics to be collected and the mechanisms and criteria to
compute, elaborate, and evaluate the KPIs during the Pilots validation campaigns. An information
model, based on an evolution of the Experiment Blueprints defined in the 5G EVE project, has
been produced, as shown below.
4. The integration of these descriptors within an experiment catalogue, able to support formal
referencing of experimental results. The 5Growth experiment catalogue is available online, next
to the source repositories of the platform, at the following URL: https://github.com/5growth/5gr-
pilots. This repository contains all experiment descriptors, grouped by pilots and then use-cases.
D6.3: Final Project Report 72
H2020-856709
FIGURE 20: 5GROWTH EXPERIMENT DESCRIPTOR INFORMATION ELEMENTS AND MODELS
3.2.4.3. Tasks 4.3 to 4.6: Verification and validation campaigns for the different pilots
The second verification campaign, as reported in D4.3, allowed to refine the identification of and
considerations on the metrics and technical requirements relevant for each of the four pilots, along
with the measurement methodology therein, and to perform the integration of monitoring and other
tools from ICT-17 platforms and 5Growth.
The final validation campaign, as reported in D4.4, was performed integration the ICT-17 and vertical
sites and platforms applicable to each use case, addressing the constraints imposed by such close-
to-real operational conditions. A subset of the innovations developed within WP2 were integrated
for each operational environment and validated through measurement.
In conclusion, the outcome of the verification and validation campaigns per each pilot include
• For the INNOVALIA pilot (Task 4.3, involving UC3M, INNO, NEC, ERC, IDCC, NBL and CTTC):
o Two Use Cases fully integrated in vertical premises at Bilbao, including the full 5Growth
platform, and leveraging on the 5G-EVE platform and infrastructure located at Madrid.
o Vertical applications have been virtualized to work decoupled from the hardware and to
allow dynamic orchestration and flexibility to work on different infrastructure setups.
o 5G technology has been experimented with two alternative deployment options and two
separate frequency bands.
D6.3: Final Project Report 73
H2020-856709
o Pilot (“5Growth: Industry 4.0 Remote Operation of Metrology Machinery over 5G”)
selected among the top ten of the 5GPPP Infrastructure Trials and Pilots brochure No. 3
in 2021.
• For the COMAU pilot (Task 4.4, involving TEI, COMAU, NXW, CTTC and SSSA):
o Three Use Cases fully integrated in vertical and operator premises, including the transport
network and monitoring platform.
o KPI validated on the integrated 5G technologies (radio, transport, and cloud) with related
E2E orchestration and monitoring (on site and by remote via monitoring platform).
o Pilot (“5Growth - Industry 4.0: Low-latency on a shared Network”) selected among the
top ten of the 5GPPP Infrastructure Trials and Pilots brochure No. 2 in 2020.
o Pilot (“5Growth - E2E Transport-aware Orchestration”) selected among the top ten of the
5GPPP Infrastructure Trials and Pilots brochure No. 3 in 2021.
• For the EFACEC_S pilot (Task 4.5, involving EFACEC_S, ALB, MIRANTIS, NXW, CTTC, IT and SSSA):
o Two Use Cases fully integrated in vertical premises, including the monitoring platform.
o Business, functional, and technical validation as well as KPI validation on the integrated
5G technologies and monitoring (on site and by remote via monitoring platform).
o The 5G level crossing solution is incorporated in the EFACEC product roadmap.
o Good feedback from main stakeholders such as partners (for instance Frauscher) end-
users (for instance infrastructure owners – Administração do Porto de Aveiro/Aveiro
Harbour Administration) and private-operators (Medway -freight Operator).
• For the EFACEC_E pilot (Task 4.6, involving EFACEC_E, ALB, MIRANTIS, NXW, CTTC and IT):
o Two Use Cases fully integrated in vertical premises, including the monitoring platform.
o Business, functional, and technical validation as well as KPI validation on the integrated
5G technologies and monitoring (on site and by remote via monitoring platform).
o Important step ahead considering the development prototyping and PoC of next
generation of EFACEC’s products for the secondary distribution substation and the low
voltage distribution smart grid.
3.2.4.4. Deviations
Beyond the project extension requested due to the impact of the COVID-19 situation, the
deployment at the vertical sites brought additional logistics issues related to matters like permissions,
transport, and support staff availability, some of them related to the pandemic regulations and some
to other practical aspects. These circumstances caused delays in the availability of the final validation
environments and required the 15-day delay of the release of D4.4 (communicated and agreed with
the PO two months before the original submission date).
3.2.4.5. Corrective actions
The team worked to meet the agreed new submission deadline of D4.4.
D6.3: Final Project Report 74
H2020-856709
3.2.5. WP5
As far as this project is concerned, and in accordance with common practice at the EU level [23][24],
Communication includes all the activities related with the promotion of the project and its results
beyond the project own community. This includes the interaction with other research projects (e.g.,
H2020 5G-PPP) as well as communication of its research in a way that is understood by the non-
specialist, e.g., the media and the public. Dissemination includes activities related with raising
awareness of its results in a technical community working on the same research field. In general, this
will be done through publications, and participation and organization of technical events. Finally,
exploitation (in accordance with the European IPR Helpdesk) covers activities aiming at using the
results in further research activities other than those covered by the project, or in developing,
creating and marketing a products or processes, or in creating and providing a service, or in
standardization activities.
Though a brief global overview is provided in the following paragraphs, the detailed work carried
out in WP5 is reflected in various sections throughout this document. Communication activities (i.e.,
the outcome of Task 5.1) are presented in this section, Dissemination activities (i.e., the outcome of
Task 5.2) are presented in Section 2, and Exploitation activities (including standardization) are
presented in Section 3.5, and are also an outcome of Task 5.2. Finally, Section 4 refers to D5.4 [25]
for an updated communication, dissemination, and exploitation plan (CoDEP) of 5Growth.
In accordance with the latest version of the communication, dissemination, and exploitation plan
(CoDEP) (see Figure 21), the first reporting period includes the Raise Awareness and part of the
Presentation of Results phases. The former is mainly devoted to publicizing the scope and approach
of 5Growth. This phase started with the preparation of communication material as well as the website
and social media and with the publication of multiple press release (project-wide and per-partner).
Therefore, Task 5.1 had an initial starring role. Consequently, various project partners presented the
project in various events, gave lectures on project-related topics, and prepared the website and social
media of the project (including videos of demonstrations and workshops). This allowed achieving
the workpackage milestone set for M3 (August 2019), which also included the preparation of
communication material, such as the leaflet and poster. During project start, there was a steady
increase of the web and social media impact, for instance, reaching peaks of around 90000 visits in
365 days, 4600+ views of Youtube videos, 780 Twitter followers, or 760 connections in LinkedIn.
Communication actions for society at large were also carried out. In fact, seven events targeting
general public were also organized.
Though dissemination actions were also undertaken during the initial period of the project,
dissemination and exploitation (Task 5.2) increased in importance during the remaining phases of
the CoDEP. A number of papers (47 in Journals and 34 in conferences/ workshops) were accepted in
top-tier international journals and conferences (e.g., IEEE/ACM Transactions on Networking, IEEE
Communications Magazine, IEEE Transactions on Network Service and Management, ACM Mobicom,
ACM Conext, IEEE INFOCOM, IEEE NFV-SDN, IFIP Networking, IEEE ICC, IEEE Globecom).
D6.3: Final Project Report 75
H2020-856709
Despite the COVID-19 impact, 21 events were organized, in some cases jointly with other 5GPPP
projects (e.g., 5G EVE, 5G-VINNI, 5G-Tours) and 5G-DIVE. Furthermore, other online and regular
events were organized by 5Growth (e.g., Layer123 5Growth webinar, workshop co-located with 5G
World Forum). Some of these events were co-located with renowned conferences, such as EUCNC’21
or IEEE CNSM’21. In addition to jointly organized events, the project regularly participated in 5G-PPP
working groups, and in the preparation of joint papers and white papers (e.g., editorship of the
MANO chapter of the 5GPPP architecture white paper version 4.0). Furthermore, the technical
manager of 5Growth was elected as vice-chair of the 5GPPP architecture working group. The project
also regularly participates in 5G-PPP COMMS group, an action aiming at joint dissemination strategy
of all 5G-PPP projects, hence 5Growth regularly exploits these joint channels. A remarkable
achievement in this respect is the selection of one of the 5Growth pilots to be included in the top 10
list of the 2nd ed. of the EC H2020 5G Infrastructure PPP - PPP T&Ps Brochure n°2 and two more pilots
included in the 3rd ed.
The project also carried out a total of 27 regular and online demonstrations in renowned conferences
(e.g., Mobicom, Mobihoc, OFC, INFOCOM) and in the 5G-PPP TB eWorkshop, as well as in other
online events organized by 5Growth, which were recognized with best demo awards. Furthermore,
multiple talks in several events were also given and multiple theses (Bachelor, Master and PhD)
were/are supervised by 5Growth researchers.
As for standardization, a standardization advisory committee (SAC) was specifically created to
coordinate the work, continuously refine the roadmap and maximize impact of 5Growth
standardization activities. As part of these roadmap, 85 contributions to various SDOs were
submitted: 20 to IETF/IRTF, 38 to 3GPP, and 10 to ETSI, and 16 to IEEE, and 1 to GSMA. Out of these,
43 were approved/adopted/accepted.
D6.3: Final Project Report 76
H2020-856709
FIGURE 21: 5GROWTH COMMUNICATION, DISSEMINATION, AND EXPLOITATION PLAN (CODEP)
D6.3: Final Project Report 77
H2020-856709
As mentioned above, the following subsection focuses on communication activities since
dissemination and exploitation are reported in Section 2 of this document.
3.2.5.1. Task 5.1: Communication activities
This section reports on the communication activities undertaken to publicize the objectives and
outcomes of 5Growth to an as wide as possible audience, with particular emphasis on actions
specifically targeting a non-technical audience. In particular, all 5Growth partners promote the
project to the general public at large, and many activities (e.g., social media and video post, press
releases and news release, communication articles published, etc.) were carried out, as presented in
the following subsections. In this sense, a long list of press releases was produced by various partners
(including operators, vendors, and academic partners) to publicize the project. Furthermore, project,
WP and task leaders generated the generic publicity material (posters/leaflet) and prepared the initial
content for the web. From then on, the content in the web is periodically updated according to the
information sent by partners in the CoDEP record, which are then moved to the website and other
social media channels. Various partners (e.g., CTTC, SSSA, EFACEC_S) participated in events for society
at large to explain the scope and potential impact of 5Growth. Several videos prepared by various
partners (e.g., UC3M, CTTC, NEC, ERC, COMAU, TEI, EFACEC_S) have also been uploaded to the
project YouTube channel. Furthermore, academic partners also produced lecture material for
graduate and undergraduate courses on topics related with 5Growth.
In this section, we report the achievements for the whole project related to communication activities.
Overall, the project overcame its targets as reported in Table 20 despite the COVID-19 pandemic.
TABLE 20: COMMUNICATION ACTIVITIES ACHIEVEMENTS AND TARGETS
Type Achieved Target (per year)
Press Releases and News 36 2 (Press Releases) (per year)
Communications posters 1 1 (@M3) (overall)
Leaflet 3 1 (@M3) (overall)
Communications Presentations (Live) 7 1 (per year)
Communications Presentations (Videos) 20 None
Communications Articles 5 None
Lecture Materials 9 None
3.2.5.1.1. News and press releases
The first official project press release was issued on July 27, 2019, in Madrid, Spain. Additionally,
partners also released their own internal (company-wide) and external press releases. Project news
are available at: http://5growth.eu/blog/. Other relevant activities are publicized through the various
social media accounts of the project. A list of some of the news on 5Growth that have appeared,
either published by partners or as news in other websites are:
D6.3: Final Project Report 78
H2020-856709
• http://ir.interdigital.com/file/Index?KeyFile=398573395
• https://www.5tonic.org/news/5tonic-selected-5growth-project-validate-advanced-5g-trials-
across-multiple-vertical-industries
• http://5growth.eu/2019/09/03/plenary-meeting-in-pisa/
• https://www.santannapisa.it/en/news/5g-infrastructure-and-telecommunication-systems-
santanna-school-partners-eu-project-test
• http://5growth.eu/2019/09/17/5growth-in-torino-italy/
• https://www.uc3m.es/ss/Satellite/UC3MInstitucional/es/Detalle/Comunicacion_C/13712779
97033/1371215537949/Europa_prepara_cuatro_pruebas_reales_del_5G_en_aplicaciones_ind
ustriales
• https://5growth.eu/svn/5growth/execution/WP5/T5.1_Communication_activities/Press%20R
eleases%20and%20news/191017_UC3M_PressRelease_EuropePrepares4Real5GtestIndustrial
_Spanish.docx
• http://5growth.eu/2019/10/16/europe-prepares-four-5g-pilots-in-industrial-applications/
• https://www.innovaspain.com/5growth-pone-a-prueba-la-tecnologia-5g-en-la-industrial-
espanola/
• http://5growth.eu/2019/11/18/510/
• https://www.layer123.com/articles/Layer123%20to%20host%20a%205Growth%20webinar%
20series%20on%205G%20use%20in%20industry
• http://5growth.eu/2020/07/02/layer123-to-host-a-5growth-webinar-series-on-5g-use-in-
industry/
• http://5growth.eu/2020/07/02/online-workshop-layer123-5growth-powering-5g-in-
industry-9-july-2020-10am-cet/
• https://5growth.eu/2020/10/08/%f0%9f%92%bbworkshop-5g-trials-in-europe-5g-
experimentation-facilities-and-vertical-trials/
• https://5growth.eu/2020/11/15/best-fast-track-paper-award-in-ieee-nfv-sdn-2020/
• https://5growth.eu/2020/11/26/beyond-5g-evolution-presentations-and-results/
• https://5growth.eu/2020/12/04/contributors-award-given-to-itavs-joao-fonseca/
• https://5growth.eu/2020/12/06/tb-eworkshop-december-2020/
• https://5growth.eu/2020/12/06/5growth-living-document-of-t1-2-continuation-of-the-
techno-economic-analysis-and-business-model-validation-methodology/
• https://5growth.eu/2020/12/17/the-5g-ppp-infrastructure-trials-and-pilots-brochure-n2-is-
out/
• https://5growth.eu/2021/03/02/5g-ppp-and-5g-ias-white-paper-edge-computing-for-5g-
networks/
• https://5growth.eu/2021/04/11/5growth-pilot-and-innovation-videos-available/
• https://5growth.eu/2021/05/10/esp-%f0%9f%8e%96%ef%b8%8f-5growth-obtiene-el-
premio-madrid-a-la-participacion-en-europa-%f0%9f%8e%96%ef%b8%8f/
• https://5growth.eu/2021/05/10/english-%f0%9f%8e%96%ef%b8%8f-5growth-wins-the-
madrid-award-for-participation-in-europe-%f0%9f%8e%96%ef%b8%8f/
D6.3: Final Project Report 79
H2020-856709
• https://www.corenect.eu/news/the-6g-white-paper-an-interview-with-carlos-jess-
bernardos-cano
• https://5growth.eu/2021/05/27/1278/
• https://5growth.eu/2021/05/28/contributions-adopted-by-the-ietf/
• https://5growth.eu/2021/06/08/vote-for-best-booth-award-at-eucnc-2021/
• https://5growth.eu/2021/06/09/5growth-demonstration-schedule-at-eucnc-2021/
• https://5growth.eu/2021/06/09/%f0%9f%97%a3-5g-ppp-phase-3-projects-brochure-
%f0%9f%93%84/
• https://www.it.pt/News/NewsPost/4695
• https://5growth.eu/2021/06/29/5growth-mwc-barcelona-2021/
• https://5growth.eu/2021/07/06/best-booth-award-at-eucnc-2021/
• https://5growth.eu/2021/07/13/1322/
• https://5growth.eu/2021/10/08/third-edition-of-the-5g-infrastructure-ppp-trials-and-
pilots-brochure/
• https://5growth.eu/2021/10/14/5growth-5g-dive-exploitation-workshop-29-october-2021-
experiences-from-field-trial-about-vertical-industry/
The following figures (Figure 22 and Figure 23) present the poster and leaflet of the 5Growth project.
D6.3: Final Project Report 82
H2020-856709
3.2.5.1.2. Web, social media, and project communication material
The project website was established at the beginning of the project, and it is reachable at the
following URL: http://5growth.eu/. Among the various sections, one was introduced to specifically
target “Vertical Industries” (e.g., the External Vertical Industries Advisory Board). The landing page is
reported in Figure 24.
FIGURE 24: 5GROWTH WEBSITE LANDING PAGE
Statistics have been gathered for the website. It can be observed that, since the beginning of the
project (i.e., “last 365 days” statistics), peaks of up to 90000 visits have been achieved and stable
56000 visits after that.
Figure 25 shows the evolution of the cumulative web visits throughout the project lifetime.
D6.3: Final Project Report 83
H2020-856709
FIGURE 25: WEB PAGE VISIT STATISTICS (COUNTED FOR THE PREVIOUS 365 DAYS FROM THE REPORTED
MONTH).
In detail, as shown in Figure 26, the most popular subpages are the ones related to deliverables,
consortium, project, news, and publications in addition to the landing page, which is the most visited
page.
FIGURE 26: 5GROWTH WEBSITE MOST VISITED PAGES ON FEB. 23, 2022 FOR THE LATEST 365 DAYS
The project has been very active in other social media such as LinkedIn and Twitter. LinkedIn and
Twitter accounts are the following:
• LinkedIn: www.linkedin.com/in/5growth-project
• Twitter: https://twitter.com/5growth_eu?lang=es
0
10000
20000
30000
40000
50000
60000
70000
80000
90000
100000
Nu
mb
er
of
vis
its
Month
Cumulative Web Page Visits
D6.3: Final Project Report 84
H2020-856709
Figure 29 shows that the project had an increasing number of LinkedIn profile views since its
beginning, with a decrease towards its end (please, note that the February data are partial only).
However, the number of connections (i.e., a contact with whom you have a 1st-degree connection
to) substantially increased at the end of 2020 and continue a slight steady increase until its end to
reach 750+ connections, as shown in Figure 30.
FIGURE 27: 5GROWTH LINKEDIN PAGE
FIGURE 28: 5GROWTH TWITTER ACCOUNT
D6.3: Final Project Report 85
H2020-856709
FIGURE 29: LINKEDIN PROFILE VIEWS
FIGURE 30: LINKEDIN CONNECTIONS
In Twitter, the project reached a very high number of visits with a recent slight decrease as shown in
Figure 31. Despite such recent decrease, the project reached a total of 780 followers as shown in
Figure 28.
0
50
100
150
Nu
mb
er
of
pro
file
vie
ws
Period
LinkedIn profile views
0100200300400500600700800900
Nu
mb
er
of
con
nect
ion
s
Period
Connections
D6.3: Final Project Report 86
H2020-856709
FIGURE 31: TWITTER PROFILE VISITS
Despite the COVID-19 pandemic, the project’s Instagram account
(https://www.instagram.com/5growth_h2020/), shown in Figure 32, constantly increased its
followers, as shown in Figure 33. As for Instagram, the service recently changed its statistic collection
policy, thus the May 2021-Sep. 2021 statistics have been linearly interpolated with the previous and
next period.
FIGURE 32: 5GROWTH INSTAGRAM PAGE
0100200300400500600700
Sep
. 2019
No
v. 2019
Jan
. 2020
Mar.
2020
May. 2020
Jul.
2020
Sep
. 2020
No
v. 2020
Jan
. 2021
Mar.
2021
May 2021
Jul.
2021
Sep
. 2021
No
v. 2021
Jan
. 2021
Nu
mb
er
of
pro
file
vis
its
Month
Profile visits
D6.3: Final Project Report 87
H2020-856709
FIGURE 33: INSTAGRAM STATISTICS
Because of the COVID-19 pandemic, WP5 decided to boost the utilization of its YouTube channel
(https://www.youtube.com/c/5Growth) for communications. The channel contains videos of the
different demonstrations conducted by the project, project overviews, pilot overviews, and events,
as shown in Figure 34.
The popularity of the channel was very high totalizing 4671 views, 223 hours of watch time, 139
subscribers and 26315 impressions. For more details, please, refer to Figure 35.
FIGURE 34: YOUTUBE CHANNEL
0
50
100
150
200
250
Nu
mb
er
of
follo
wers
Period
Followers
D6.3: Final Project Report 88
H2020-856709
FIGURE 35: YOUTUBE STUDIO STATISTICS
Thus, overall video-related communication activities were very successful despite the COVID-19
pandemic, or precisely because of that.
The following tables list the uploaded videos:
TABLE 21: COMMUNICATION VIDEOS IN Y1
Title Location
Presentation of 5Growth in ICT-19 session @ EUCNC'19 Link
Introduction video to 5Growth Link
First meeting del 5Growth External Vertical Industries Advisory Board (EVIAB) Link
TABLE 22: COMMUNICATION VIDEOS IN Y2
Title Location
5G end-to-end experimentation by verticals in EU projects Online Workshop Link
Online Workshop – Layer123/5Growth: Powering 5G in Industry Link
5Growth: 5G-enabled Growth in Vertical Industries Link
Demo: vrAIn Proof-of-Concept. A Deep Learning Approach for Virtualized RAN
Resource Control
Link
5G for Industry 4.0: COMAU pilot, Video Describing COMAU Pilot Link
Transportation Pilot during the Aveiro Tech Week Link
Second meeting del 5Growth External Vertical Industries Advisory Board (EVIAB) Link
ML-Driven Scaling of Digital Twin Service in 5Growth (short version) Link
Performance Isolation for 5G Network Slicing Link
ML-Driven Scaling of Digital Twin Service in 5Growth (detailed description - long
version)
Link
D6.3: Final Project Report 89
H2020-856709
Advanced Monitoring and Maintenance Support for the Secondary MV/LV Distribution
Substation
Link
COMAU Pilot. Digital Twin Apps Use Case Link
5Growth Interaction with ICT-17 Platforms Link
EFACEC_S pilot. 5G to Support Railway Signalling Operations Link
EFACEC_E pilot. Advanced Monitoring and Maintenance Support for the secondary
MV/LV distribution substation
Link
INNOVALIA Pilot. Connected Worker Remote Operation of Quality Equipment Link
TABLE 23: COMMUNICATION VIDEOS IN Y3
Title Location
Hardening Interdomain Vertical Services with Moving Target Defense (MTD) Link
5Growth & 5G-DIVE Exploitation workshop: “Experiences from field trial about
vertical industry"
Link
3.2.5.1.3. Communication talks and other actions
Seven communication talks (Table 24) have been given since the project started as part of the CoDEP.
In this sense, the focus is on explaining the high-level goals, main building blocks, and verticals
involved, including the general technological framework of the project to the general public.
TABLE 24: COMMUNICATION TALKS
# Title Event
1 The 5Growth project Internet Festival, Oct. 10-13, Pisa, Italy
https://www.internetfestival.it/en/home
2 5G Networks: Why? What? How? 24th Science week, Nov 8-17, Castelldefels, Spain
http://www.cttc.cat/24th-science-week/
3 The 5Growth project
Aveiro TechDays. Dissemination of 5Growth project by
Aveiro Harbour, Aveiro, Portugal. October 2019.
http://ww2.portodeaveiro.pt/sartigo/index.php?x=7090
4 5G challenge (virtualization and edge
computing)
Demonstration to general public during Bright
researchers’ night 2019. Sep. 27-28, 2019, Pisa, Italy.
http://www.bright-toscana.it/bright/
5 5G Networks (and beyond) 25th Science week, Nov. 17, 2020, online
http://www.cttc.cat/25th-science-week/
6 The 5Growth project
European Corner of the European Researchers' Night
in Catalunya. 2021.
https://lanitdelarecerca.cat/?s=5growth
7 South Summit
Moderating a session about ecosystem based
innovation, Oct., 6, 2021
https://www.southsummit.co/
Additionally, internal communication actions have also been undertaken inside the partner
organizations, through internal news and talks.
D6.3: Final Project Report 90
H2020-856709
Furthermore, five communication articles about the project were also published:
• “Projeto 5Growth valida comunicações avançadas de 5G,” in Power:on magazine (Efacec's
internal magazine) (in Portuguese).
• “Overview of 5Growth”, in European 5G Annual Journal 2020.
• “5Growth pilots.” European 5G Annual Journal 2021.
• “Project 5Growth.” EFACEC_S brief article on level crossing in Industria magazine num 126
(p.27) (in Portuguese).
• “¿Qué implica la llegada del 5G?” 5Growth is set as example of research project validating
different 5G use cases in real deployed pilots in Bilbao, Aveiro and Turin (in Spanish).
Finally, academic partners of the consortium prepared several courses on SDN/NFV-related topics
that are taught to graduate and undergraduate students, which benefit from the 5Growth work. A
preliminary list of the courses is presented in Table 25.
TABLE 25: LECTURES AND COURSES
# Title Host organization
1 Master in NFV and SDN for 5G networks UC3M Telematics Department Link
2 Advanced Communication Networks NKUA Dept. of Informatics and
Telecommunications Link
3 Intelligence at the Edge of 5G for
enabling 5G services TIM Academy on 5G and Edge Computing Link
4 Cloud Computing (Master Course) Politecnico di Torino Link
5 Software networking (Master Course) Politecnico di Torino Link
6 Laboratory of Teletraffic Engineering Scuola Superiore Sant'Anna di Pisa Link
7 Laboratory of Network Software Scuola Superiore Sant'Anna di Pisa Link
8 Communication Networks and Security Scuola Superiore Sant'Anna di Pisa Link
9 Seasonal school ARTIST (31/01-04/02) Scuola Superiore Sant'Anna di Pisa Link
3.2.5.2. Task 5.2: Dissemination and Exploitation
All activities related with dissemination are reported in Section 2.
All partners participated to the various dissemination activities of the project. Several conference and
journal papers were published by multiple partners. Furthermore, partners have also actively
participated in 5G-PPP working group activities towards coordination of efforts with the other
projects. This is reflected by the regular active participation to meetings, as authors of documents
produced (including white papers published and ongoing, brochures), or joint organization of events.
D6.3: Final Project Report 91
H2020-856709
Many events physical, and more recently, online (due to COVID-19) were organized by multiple
partners (also in cooperation with other projects. Multiple demonstrations have also been presented
in physical and online events and participation through talks in multiple events has also been spread
across all partners. Finally, academic partners have also initiated (and in some cases finished) multiple
theses. All these activities are listed in detail in Section 2.
3.2.5.3. Deviations
Overall, the work package proceeded as planned.
3.2.5.4. Corrective actions
No corrective actions needed.
3.2.6. WP6
The management of the project is led by UC3M.
The main activities in this period are related to ensure that the project runs successfully, that the
partners successfully and efficiently collaborate and that the technical objectives are achieved taking
care of the time and the costs of the project. The project coordinator (PC) administered the financial
contribution, allocating it between the beneficiaries, and activities in accordance with the Grant
Agreement. The payments have been done with no delay. The PC kept the records and financial
accounting and informed the European Commission of the distribution of the EU financial
contribution. The PC verified consistency between the reports and the project tasks and monitors the
compliance of beneficiaries with their obligations.
During this reporting period, three amendments have been carried out, but two of them were
Commission initiated (related to H2020 program updates). The main changes implemented in the
consortium-requested amendment (May 2021) are listed below:
• Addition of a linked third party (UPM, linked to TID).
• Three months extension of the project, due to some delays introduced by the COVID-19
lockdowns and presented in the first technical review. New end date is 28 February 2022.
• Due to the new duration of the project and the delays incurred because of the lockdowns,
some WPs have different end dates. Deliverable and milestones dates have been updated
as necessary.
The Project Management Team (PMT) has continued the work started in early March 2020 analyzing
the impact of COVID-19 in anticipation of possible scenarios.
We have been in direct and constant communication with our Project Officer since the beginning
and we have continued to do so at each step in the process. One of the actions agreed with him was
to delay 15-days D4.4, mainly to better handle the submission of D3.5 and D4.4 (which originally had
the same date). In general, actions determined during the pandemic have proved to go into the right
direction, with no additional extensions needed.
D6.3: Final Project Report 92
H2020-856709
3.2.6.1. Task 6.1: Project administrative, financial, and legal management
In this period (M19-M33) six plenary meeting were held, all held online:
• 7th plenary meeting on December 14-16, 2020. Following a plenary mode, this meeting was
focused on the preparation of the first technical review and periodic report. In addition to
this, a couple of smaller meetings (only involving the PMT) were devoted to the preparation
of the review.
• 8th plenary meeting on March 2-4, 2021, followed by another meeting on March 18. This
meeting focused on the analysis of the recommendations from the reviewers after the first
technical review.
• 9th plenary meeting on June 15-17, 2021. This meeting focused on checking the status of the
implemented actions to cope with the initial impact of COVID-19, to assess if further actions
were required, as well as to discuss on the pilot activities.
• 10th plenary meeting on September 28-29, 2021. This meeting focused on the preparation of
the final validation activities, as well as the preparation of the related WP3 and WP4
deliverables.
• 11th plenary meeting on December 14-15, 2021. This meeting focused on the preparation of
the last deliverables of the project as well as the final technical review, including discussions
on how to best communicate the achievements of the project.
• 12th plenary meeting on February 22, 2022. This meeting focused on the preparation of the
final technical review, with a main focus on the visualization of the pilot activities. In addition
to this meeting, there will be a couple of smaller meetings (only involving the PMT) to prepare
all the details of the review.
During the second reporting period, some technical remote meetings (per WP), using gotomeeting
tool, maintained the weekly frequency, while others switched to bi-weekly frequency. A shared
calendar is used to reflect and share the planned remote meetings to keep the partners informed
about the date and hour.
A report of the project progress in terms of technical activities and resources allocation is planned
each three months by means of the Quarterly Management Reports.
The Consortium has continued using the following tools for the management of the project (no
changes compared to what was using in the first reporting period):
• Redmine: a web-based tool for the description of the activities and the coordination between
the partners. A dedicated section has been created as repository of the meeting minutes. This
includes a shared calendar for meetings bookkeeping.
• SVN repository: the repository where documentation and software have been stored and
shared among the partners.
• Several mailing lists in order to communicate with the partners: 5growth-all, 5growth-wp1,
5growth-wp2, 5growth-wp3, 5growth-wp4, 5growth-wp5, 5growth-wp6, 5growth-pb,
5growth-pmt, 5growth-admin and 5growth-contact.
D6.3: Final Project Report 93
H2020-856709
• Private git repositories to host the code developed in the project and allow for faster tests
and integration.
• Public GitHub repositories, where we upload the open-source components of each major
release: https://github.com/5growth
The 5Growth website (https://5growth.eu/) has been maintained. Similarly, we have maintained and
feed with content the Twitter (https://twitter.com/5growth_eu/), Instagram
(https://www.instagram.com/5growth_h2020/), LinkedIn (https://www.linkedin.com/in/5growth-
project/) accounts and the YouTube channel (https://www.youtube.com/c/5growth/).
3.2.6.2. Task 6.2: Technical coordination, Innovation and Quality management
This task is led by NEC as technical manager, and UC3M and TEI participate as project coordinator
and innovation manager, respectively. NEC as the project technical manager, leads the technical
innovations for the project and coordinating the work of all WPs. UC3M as project coordinator
ensures the project progresses towards its objectives. TEI as the innovation manager has monitored
the innovation and exploitation activities.
5Growth set-up an External Vertical Industries Advisory Board (EVIAB). The EVIAB is a body that
provides non-binding technical advice to the management of 5Growth. 5Growth will schedule a
meeting after all the deliverables have been submitted, to present them a summary of all the
achievements and collect feedback. The EVIAB provided very valuable insights and recommendations
during the first reporting period. All meetings are recorded and published on the 5Growth YouTube
channel.
3.2.6.3. Task 6.3: Interaction with other projects of the H2020 5G Infrastructure PPP
Within 5G-PPP, the project participates in the cross-project work groups (WGs), where the work of
multiple projects can converge into identifying the shared issues and developing supported program
level position on technical and strategic items. 5Growth project partners participate to multiple 5G-
PPP working groups, namely (we indicate the 5Growth representative partner in brackets):
• Pre-Standardization (IDCC): active participation in the 6G-IA pre-standardization Working
Group including (i) regular attendance to monthly meetings; and (ii) presentation on the SDO
impacts of 5Growth which is recognized in EU Success Stories (https://global5g.org/online-
tool-standards-tracker/5growth-sdo-impacts) by Global5G.
• Vision and Societal Challenges (IT, UC3M): co-editing of the whitepaper “European Vision for
the 6G Network Ecosystem” (UC3M) and its presentation of different events, such as ICT-52
Workshop on 6G (UC3M). Co-lead of the SNSV Subgroup. Participation in the periodic WG
leading calls (UC3M). Organization of the SRIA event in Lisbon in November 2021 (IT).
• 5G Architecture (NEC): active participation to the 5G PPP Architecture WG. Contributions to
the Architecture WG white paper (release 4). Xi Li was elected co-chair of the WG.
• Trials (ERC): attendance to periodic conference calls.
• SME (TELCA): attendance to periodic conference calls.
D6.3: Final Project Report 94
H2020-856709
• Software Networks (NBL): active participation to the 5G PPP Software Networks WG and
attendance to periodic conference calls.
• Security (TID): attendance to periodic conference calls.
• Test, Measurements and KPI Validation (ERC): attendance to periodic conference calls.
Their scope is described at: https://5g-ppp.eu/5g-ppp-work-groups/. This participation includes
presenting and representing the project in all periodic meetings that are organized and participation
in joint actions (e.g., co-organization of events, joint documents/papers, joint demonstrations).
Additionally, the project also participates in the 5G-PPP boards towards a tight coordination with the
rest of 5G-PPP projects: the project coordinator in the steering board and the technical manager in
the technology board.
3.2.6.4. Deviations
Overall, the work package proceeded as planned.
3.2.6.5. Corrective actions
No corrective actions needed.
D6.3: Final Project Report 95
H2020-856709
3.3. Deliverables
Deliverable Progress On Schedule Delayed Completed
D1.1 X
D1.2 X
D1.3 X
D2.1 X
D2.2 X
D2.3 X
D2.4 X
D3.1 X
D3.2 X
D3.3 X
D3.4 X
D3.5 X
D3.6 X
D4.1 X
D4.2 X
D4.3 X
D4.4 X7
D5.1 X
D5.2 X
D5.3 X
D5.4 X
D5.5 X
D5.6 X
D5.7 X
D6.1 X
D6.2 X
D6.3 X
7 A 15-day delay was agreed with the PO.
D6.3: Final Project Report 96
H2020-856709
3.4. Milestones
Milestones Progress
On Schedule Delayed Completed
M1 X
M2 X
M3 X
M4 X
M5 X
M6 X
M7 X
M8 X
M9 X
M10 X
M11 X
M12 X
M13 X
M14 X
M15 X
M16 X
M17 X
M18 X
M19 X
M20 X
M21 X
3.5. Exploitable Results
3.5.1. Exploitation on commercial products and PoCs developed internally to
the companies
The last part of the project has been devoted to consolidating the exploitation actions according to
the plan. Main effort has been dedicated to finalizing the selected functions for exploitation by
demo/prototype & pilot experiments; and, in parallel, to promote such innovations the various
stakeholders. Internal meeting and workshops have been organized with the participation of
business organization. In most of cases, this allowed to create a loop to address part of the
assessment considering the outputs coming from discussion with main exploitation stakeholders.
Table 26 reports the target commercial product or platform with the corresponding 5Growth
component as declared in the plan, with a summary about main exploitation impacts.
D6.3: Final Project Report 97
H2020-856709
TABLE 26: EXPLOITATION TABLE
Short
Name
Platform/
product
Description of impact on platform/product 5Growth
component
ALB
Operations
Support
Systems
portfolio
ALB portfolio is currently in the process of evolution to a new generation of OSS
systems, which will benefit from lessons learned about orchestration and
management of 5G infrastructure through the development and evaluation of
the EFACEC use cases.
http://www.alticelabs.com/en/operations_support_systems.html.
The network management solution developed in 5Growth is shaping the
requirements and architecture of City Catalyst project. Demonstrators to validate
City Catalyst solutions in the fields of energy, mobility and governance will be
implemented in 5 Portuguese cities: Porto, Aveiro, Guimarães, Famalicão and
Cascais.
Management platform
Vertical slicer
Service Orchestrator
CO
MA
U
Operations
Support
Systems in
production
lines
5Growth 5G Pilots will allow COMAU to evaluate the evolution of its Operation
Support Systems in production lines towards 5G. Specifically, use cases
developed and experimented in 5Growth will target the innovative networking
platform.8
The use cases 1 and 2 have particular impact on Ingrid platform, that includes
MES (i.e the system that manages the production lines).
Pilot use cases
EFA
CEC
_E
GSmart &
view4grid A current main concern to EFACEC is the competitiveness of its products and
systems. The 5Growth project results will allow EFACEC to strengthen its
portfolio of solutions for Smart Grids (ScateX# ADMS, GSmart & LVS3) by adding
innovative communications features to the products’ configuration options. The
major benefits will impact on EFACEC’s portfolio for Smart Grids’ applications
integration and deployment, a set of solutions designed to implement flexible
management and monitoring over an entire smart electrical infrastructure,
including high-level platforms with management software and web user
interfaces over mobile devices to enhance field teams’ operation, smart meters
and sensors, data concentrators and distributed controllers, or any other type of
IP capable device.9
Pilot use cases
Management and
monitoring platform
for the electrical power
distribution
EFA
CEC
_S DigiXSafe The outputs carried out in the project related the development of new signaling
system products will open new commercial windows over the market of next
generation of signaling systems that are under the standardization and
digitalization efforts resulted from of the EULYNX consortium project16 and Shift
to Rail Join Undertaking (DigiXSafe product)
Pilot use cases: New
generation of
signaling system
INN
OV
ALI
A
Metrology
Software M3 Pilot outputs include the identification and assessment of the feasibility of the
use case of remote control of Quality Control Equipment. Innovalia M3 Box SW
system has already been adapted for deployment in a 5G distributed
environment.
Business validation involves, on the one hand, determining the maximum radius
of operation (max distance between the expert and the factory where M3Box is
deployed), and, on the other hand, validating the possibility to decouple the
deployment of the components that reside on the M3Box edge device to install
them on a cloud-edge environment. The overall deployments have been tested
both on a lab environment, in 5Tonic, in Madrid, and on an industrial
environment, at the Automotive Intelligence Center in Bilbao.
5G Pilot
ER
C a
nd
TEI
(Eri
csso
n)
Ericsson IoT
Acclerator Ericsson IoT Accelerator is a platform to develop market and manage secure IoT
solutions. IoT Accelerator can benefit from the experience gained in 5Growth in
relation to the IoT pilots and relevant use cases and possibly can incorporate
functionalities that could emerge from the vertical partners in the consortium.10
Vertical Slicer, Service
Orchestrator, Resource
Layer
Cloud Packet
Core platform Especially driven by the expected verticals cooperation’s and experimentation in
the 5Growth project pilots, the Cloud Packet Core platform can be enhanced
especially in relation to Massive IoT support (Introducing network slices for
Vertical Slicer,
Service Orchestrator,
Resource Layer
8 https://www.comau.com/en/innovation-and-digital-transformation/ingrid 9 https://www.efacec.pt/en/automation/ 10 https://www.ericsson.com/ourportfolio/iot-solutions/iot-accelerator?nav=offeringarea613
D6.3: Final Project Report 98
H2020-856709
massive IoT with a decoupled lifecycle from consumer eMBB service) and
support of enterprise with dedicated instances for critical enterprise
deployments, like manufacturing sites.11
Pilot use cases
Ericsson NFVI Ericsson NFVI solution consists of software and hardware products as well as
support and system integration services forming a complete solution for
telecom operators. 5Growth can bring important elements to the platform, both
in the resource layer aspects, being hardware products part of the NFVI solution,
and in orchestration and virtualization functionalities. RAN-Transport solutions
under definition in 5Growth projects, are under discussion internally to Ericsson
for analyzing possible impact on product. Now, it is necessary a more
consolidated assessment in PoC and experimentation, but the joint cooperation
with Telefonica and TIM are considered as valuable feedback for future
deployment in products.12
Vertical Slicer,
Service Orchestrator,
Resource Layer
IDC
C
360-Degrees
Adaptive
Viewport
Video
Streaming
over
5G
InterDigital’s platform showcases the concept of microservices-based design by
distributing several computing tasks necessary to deliver a high-resolution 360
video streaming service to terminals with different resources and capabilities.
5G pilot
MIR
AN
TIS
Mirantis MOS
- Mirantis
OpenStack for
Kubernetes
(This product
replaces the
declared
product MCP
Mirantis
Cloud
Platform).
MOS - Mirantis OpenStack for Kubernetes. This product leverages the container
isolation, state enforcement, and declarative definition of resources provided by
Kubernetes to deploy and manage OpenStack clusters. MOS replaced MCP.
Compared to MCP, this new product has advantages such as containerization of
OpenStack services, reconciliation of resource state, and declarative resource
definition. MOS wasn’t tested directly for Pilots within 5Growth project, but it
could potentially improve the platform reliability and time-to-market index, and
it can simplify cluster management comparing to the upstream OpenStack
solution.
Resource Layer, 5G
Pilot
K0s, which is,
Mirantis Open
Source
product.
k0s is the simple, solid & certified Kubernetes distribution that works on any
infrastructure: public & private clouds, on-premises, edge & hybrid. It's 100%
open source & free. K0s is a perspective Kubernetes distribution targeted on
minimalism and maximum efficiency. It is targeted to be used for development
and edge solutions. It hasn’t been tested during the 5Growth project against
implementing it as a platform for 5Growth infrastructure or verticals, but
potentially may be efficiently used for this purpose.
NEC
NEC
iPASOLINK EX
family
In a lightweight, compact 23cm squared enclosure, iPASOLINK EX Advanced
realizes industry-leading 10Gbps single link capacity features. The design of
Resource Layer abstractions and interfaces with data-plane equipment will
directly impact the potential evolutions of this product family.
http://www.nec.com/en/event/mwc/leaflet/pdf_2017/i_pasolink_ex_advanced.p
df
5Gr-RL´s traffic isolation schemes, developed in the scope of WP2, are inspiring
new features to support slicing in iPASOLINK EX products.
Resource Layer
Net2Vec Net2Vec is a flexible high-performance platform that allows the execution of
deep learning algorithms in the communication network. The monitoring
platform of 5Growth and its interfaces with high-speed data processing
platforms can have an impact on the evolutions of this product.
Monitoring platform
NEC O-RAN Next generation RAN (NEC O-RAN product portfolio for vRANs) Innovation
supporting of virtualized RAN Orchestration.
Vertical Slicer, Service
Orchestrator, Resource
Layer
11 https://www.ericsson.com/ourportfolio/cloud-core/cloud-packet-core 12 https://www.ericsson.com/ourportfolio/digital-services-solution-areas/nfvi?nav=fgb_101_0363
D6.3: Final Project Report 99
H2020-856709
WizHaul
(Transport
resource
management)
product.
SDN/NFV-based centralized resource management orchestrator for mobile
transport domains. 5Growth novel orchestration algorithms for monitoring and
prediction and automated closed-loop resource management will have a
potential impact on the evolution of WizHaul (Transport resource management)
product
Service Orchestrator,
Resource Layer
OVNES novel orchestration solutions for SLA monitoring and management and
automated network slice management will have a potential impact on the
evolution of this product.
Vertical Slicer, Service
Orchestrator
NB
L
Mobile, fixed
and
converged
broadband
access
The outcome of 5Growth is expected to impact significantly NOKIA’s software-
defined access solutions on mobile and fixed access networks. It is foreseen the
potential adoption of suggested 5Growth enhancements on programmable
traffic management schemes, in NOKIA access nodes. A domain-specific
language such as P4 will be adopted for this purpose and extended
appropriately to allow programmability independently of the access technology
employed, thus impacting NOKIA’s entire mobile and fixed access product
portfolio.
Pilot use cases
WP2 innovations
AirScale
Cloud RAN The AirScale Cloud RAN solution consists of the AirScale Cloud Base Station
Server and the Nokia AirScale Radio Network Controller (RNC). The 5Growth
innovation on programmable traffic management at the RAN is expected to
complement the innovations for this product suite.13
Vertical Slicer
Cloud and
Edge
Computing
Nokia
AirFrame DC
The Nokia AirFrame Data Center solution offers a flexible range of data center
infrastructure portfolio. 5Growth research on tools for closed-loop control, such
as programmable traffic management schemes, can be potentially adopted to
improve future offerings in the Nokia AirFrame Data Center.14
Vertical Slicer, Service
Orchestrator
Digital
Operations
Suite
The Digital Operations (DO) Suite provides and agile and modular orchestration
for managing service orchestration across virtualized and hybrid networks. It is
expected that 5Growth enhancements to the Vertical Slicer and Service
Orchestrator (e.g., algorithms for arbitration across coexisting services, service
utilization demand forecasting for appropriate vertical service dimensioning,
service decomposition etc.) can steer DO innovation.15
Service Orchestrator
Resource Layer
NX
W
Symphony Based on on-going exploitation activity on Symphony components, some
components have been virtualized and deployed in containers. Moreover, using
as baseline the 5Gr-VS carried out in 5Growth the plan is to automate the
orchestration of these Symphony software modules within eMBB and URLLC
network slices, dedicated to the video-surveillance, media and A/V services, and
to domotics services respectively. Leveraging the experience built in 5Growth
activities on Industry 4.0 pilots, the company is also extending the Symphony
platform for its deployment in smart factory contexts. The original training
courses have been extended to cover new technical areas specifically related to
5G networks, orchestration solutions specialized for edge computing and AI/ML
technologies applied to closed-loop network automation.
Vertical Slicer
13 https://networks.nokia.com/solutions/airscale-cloud-ran 14 https://networks.nokia.com/solutions/airframe-data-center-solution 15 https://networks.nokia.com/portfolio/service-orchestration
D6.3: Final Project Report 100
H2020-856709
TELC
A
Alviu Alviu is a flexible and resilient control system that enables the integration of
cloud and network services through a centralized and dynamic administration.
On top of this, it reduces equipment expenses and offers a wider range of White
Box Switches to enterprises.
The innovations of 5Growth vertical slicer and service orchestration will impact
directly on how Alviu slices and manages network infrastructure.
https://www.telcaria.com/#servic eModal1.
5Growth innovations, especially the Smart orchestration innovation, have been
exploited by Alviu, enabling engineers to explore new ways of deploying and
monitoring Alviu components. Furthermore, we foresee the integration of
Innovation 8 [1], that thanks to the combination of a centralized SDN controller
and P4-enabled switches, allows for the granular implementation and control of
network slices. In particular, the aforementioned innovation, allows to achieve
traffic isolation and prioritization between slices, as well as achieving latency and
bandwidth guarantees.
In the short term, Telcaria expects to exploit 5Growth monitoring platform and
performance isolation innovations by integrating similar solutions into its
product portfolio, required by the increasing necessity of gaining better insights,
guaranteeing quality of service, and improving the decision-making
mechanisms. Moreover, in the medium term, the experience gained from the 5G
pilots is of significant value for strategic consulting and trials for new services
that Telcaria could offer. Finally, in the wake of the 5Growth project success,
Telcaria has hired new employees, and also motivated current employees to
develop their professional careers by pursuing a Ph.D., which impacts directly in
the quality of the products and services Telcaria offers to its clients worldwide.
Service Orchestrator,
Vertical Slicer
3.5.2. Exploitation on standards
5Growth thrust into standardization bodies is significant with a considerable number of contributions
bringing 5Growth technology and innovations into key SDOs forums such as 3GPP, ETSI MEC, IETF
and IEEE.
The target for the 5Growth project is 10 adopted16 contributions to SDOs, such as 3GPP, IETF, ETSI,
IEEE, ITU over the lifetime of the project. The project has reported a total of 85 standard contributions
where 43 out of 85 contributions are adopted. Table 27 summarizes the archived goals and the
spread of contributions among the different SDOs.
TABLE 27: SUMMARY OF THE STANDARD CONTRIBUTIONS PER SDO
SDO Total Submitted Total Adopted Contribution Ratio
3GPP 38 28 44.7%
IETF/IRTF 20 7 23.5%
ETSI 10 7 11.8%
IEEE 16 0 18.8%
GSMA 1 1 1.1%
Table 28 below provides more details on the status of the standardization effort in 5Growth.
16 adopted/agreed/approved/accepted are used based on the use of SDO-specific terminology.
D6.3: Final Project Report 101
H2020-856709
TABLE 28: COMPLETE LIST OF SDO ACTIVITIES AND CANDIDATE CONTRIBUTIONS IN 5GROWTH PROJECT
Date
(yy/mm/dd)
Target SDO ITEM/Activity Status
(Agreed/Ac
cepted/Sub
mitted/App
roved)
Explanation
19/09/16 IEEE 802.11 Link Submitted This contribution is an analysis of the use of
OCB (out of the Context of a BSS) for data
frame transmission in .11bc. Does not have a
direct matching to a 5Growth task but was
needed for .11bc.
19/09/17 IEEE 802.11 Link Submitted Use case presented for the RCM study group
on Randomisation of MAC addresses. This use
case studies the effects of randomisation of
MAC addresses in rogue AP containment
environments. This mechanism may be used in
controlled scenarios, such as the I4.0 in order
to avoid user created APs to be used in an area
with controlled interference.
19/11/09 IEEE 802.11 Link Submitted This contribution proposes a mechanism for
service advertisement coupled with group
security. The AP is broadcasting a set of eBCS
services. Each service is secured by a key. This
key is used to proof origin authentication. The
proposed mechanism enhances the eBCS Info
frame (in charge of distributing the keys to the
eBCS clients, so that each Info frame can carry
more than one service and more than one key.
This technology is relevant for the I4.0 use
cases, where different sensors or machines can
receive broadcast instructions or software
updates, for example, which are authenticated
using this contribution.
19/11/11 IEEE 802.11 Link Submitted This is a contribution to IEEE 802.11bc. We
believe IEEE 802.11bc can be used within the
I4.0 and Railway scenarios since it can be used
to connect low complexity sensors used in
both scenarios. This contribution specifically
deals with the authentication of the origin of
the broadcast, and therefore can be used in
critical systems such as the railway scenario.
19/11/11 IEEE 802.11 Link Submitted This is a contribution to IEEE 802.11bc. We
believe IEEE 802.11bc can be used within the
I4.0 and Railway scenarios since it can be used
to connect low complexity sensors used in
both scenarios. This contribution specifically
handles the way the services being
broadcasted in the area are advertised.
D6.3: Final Project Report 102
H2020-856709
19/11/12 IEEE
802.1CQ
Link Submitted Update to IEEE 802.1CQ
19/11/12 IEEE
802.1CQ
Link Submitted Update to IEEE 802.1CQ
19/11/13 IEEE 802.11 Link Submitted This is a contribution to IEEE 802.11bc. We
believe IEEE 802.11bc can be used within the
I4.0 and Railway scenarios since it can be used
to connect low complexity sensors used in
both scenarios.
19/11/13 IEEE 802.11 Link Submitted Above
19/11/13 IEEE
802.1CQ
Link Submitted This contribution forms part of IEEE 802.1CQ.
This standard defines a mechanism to
assigning multicast and unicast local MAC
addresses to end stations. This is relevant as a
way of reducing the cost of sensors which do
not need to have a hardwired MAC address.
This will potentially impact any scenario using
sensors.
19/11/13 IEEE
802.1CQ
Link Submitted Update to IEEE 802.1CQ
20/01/08 IETF Link Submitted Relevant to 5Growth due to the inclusion of
the I4.0 use case -> This document describes
different use cases of interest for reliable and
available wireless networks, which is basically
deterministic networking for wireless. This is
extremely relevant for 5Growth use cases,
especially Industry 4.0. This use case is
reflected in the document. It is an individual
contribution, recently adopted as WG
document.
20/01/08 IETF Link Submitted This document describes some issues and
challenges of discovery data and resources at
the edge of the network. This is relevant for
5Growth, as some of the applications
considered in our pilots (such as Industry 4.0)
might benefit from these mechanisms to
optimize the overall performance in
automation scenarios.
20/02/13 IEEE
802.11bc
Link Submitted This is a contribution to IEEE 802.11bc. We
believe IEEE 802.11bc can be used within the
I4.0 and Railway scenarios since it can be used
to connect low complexity sensors used in
both scenarios. This contribution specifically
handles the way the services being
broadcasted in the area are advertised.
20/03/04 3GPP SA5 S5-201594 Accepted This contribution is relevant for WP3, as it
specifies means of integrating private and
D6.3: Final Project Report 103
H2020-856709
public networks, in relation with 5Growth use
cases.
20/03/07 IETF Link Adopted It is relevant for I4.0 use cases, where a massive
number of devices need connectivity and
might benefit from the local addressing
assignment mechanisms described in the draft
-> This document describes extensions to
DHCP to allow a requester (client or
hypervisor) indicate the preference of the type
of local address to obtain. This is applicable to
5Growth scenarios, e.g. in Industry 4.0. It is an
adopted WG document at the very end of the
publication process as RFC.
20/03/09 3GPP SA5 S5-201596 Accepted Relevant contribution for 5Growth network
slicing mechanisms as means of NPN
provisioning in industrial 4.0 scenarios. This is
related to D3.1, because the contribution
treats the use of slicing (following a NSaaS
model) to provisioning public network
integrated with NPNs, emphasising the public-
private integration. In this sense, it is related
with Section 3.4 of D3.1 (“Initial study on ICT-
17 integration with 5Growth”).
20/03/09 IETF Link Submitted In some scenarios, distributed SFC control
might be useful to provide extra resilience.
This document describes Mobile IPv6
extensions to enable function migration in
distributed SFC scenarios. It is an individual
submission.
20/03/09 IETF Link Submitted This document specifies several NSH
extensions to provide in-band SFC control
signaling to enable distributed SFC control
solutions. This might be applied to some of the
5Growth use cases, to enable extra resilience
by supporting distributed control. It is an
individual submission.
20/03/09 IETF Link Submitted In some scenarios, distributed SFC control
might be useful to provide extra resilience.
This document describes a general framework
for distributed SFC operation. It is an individual
submission.
20/04/28 IEEE
802.11bc
Link Submitted This is a contribution to IEEE 802.11bc. We
believe IEEE 802.11bc can be used within the
I4.0 and Railway scenarios since it can be used
to connect low complexity sensors used in
both scenarios. This contribution specifically
handles the way the services being
broadcasted in the area are advertised.
D6.3: Final Project Report 104
H2020-856709
20/04/28 3GPP SA5 S5-202339 Accepted This contribution clarifies "which role"
manages "what NFs" in different NPN
scenarios, depending on deployment settings.
This is directly connected to 5Growth use
cases, where different deployment settings
allows for different governance between
5Growth platform and ICT-17 stack.
20/04/28 3GPP SA5 S5-202338 Accepted These requirements captured some of the
functional requirements specified for
individual 5Growth use cases
20/07/01 ETSI MEC MEC(20)0002
58
(must be a
member of
ETSI)
Accepted This contribution outlined the end-to-end
architecture framework for an intelligent edge
and far edge integrated with an end-to-end
5G system.
20/07/01 ETSI MEC MEC(20)0002
59
(must be a
member of
ETSI)
Accepted This provided a description of the 5Growth I4.0
use case on zero defect manufacturing and the
role of edge in supporting this use case.
20/07/01 ETSI MEC MEC(20)0002
61
(must be a
member of
ETSI)
Accepted This provided a description of the 5Growth I4.0
use cases involving robots/AGVs and the role
of edge in supporting this use case.
20/07/01 IEEE
802.1CQ
Private draft
(only
accessible to
voting
members)
Submitted IEEE 802.1CQ draft standard
20/07/14 IRTF NMRG Link Submitted This contribution targets to become one of the
use cases of the NMRG on for intent-based
systems. Its applicability within 5Growth would
be related to, on one hand, how verticals can
express through intents their slice needs, and
on another hand, how service providers can
express interconnection intents among
themselves for achieving those services.
20/07/20 IETF
OPSAWG
Link Submitted WP4 addresses the combination of different
measurement sources by means of a
semantics-aware data aggregator, proposed
to be integrated in the IETF SAIN architecture.
20/07/20 IRTF
COINRG
Link Submitted WP4 addresses the combination of different
measurement sources by means of a
semantics-aware data aggregator, proposed
to become an essential aspect of data source
discovery for the computing-in-the-network
paradigm.
D6.3: Final Project Report 105
H2020-856709
20/07/27 IETF Link Submitted This contribution proposes mechanisms to
integrate IETF RAW and ETSI MEC, filling a gap
that would allow to enhance the applicability
of MEC technologies in Industry 4.0 scenarios
as the ones addressed by 5Growth (in WP3).
20/08/28 3GPP SA5 S5-204463 Accepted This contribution provides a 3GPP 5G actor
role model for NPN management. These roles
are aligned with 5Growth stakeholders at
different abstraction layers (5Gr-RL, 5Gr-SO,
5Gr-VS).
20/08/28 3GPP SA5 S5-204465 Accepted This contribution proposes a way forward for
the discussion of NPN management aspects
on individual 5GS segments, including UE
related management aspects (e.g. UE identity
management, UE provisioning and on-
boarding, UE connectivity management, UE
group management), NG-RAN related
management aspects (e.g. NPN IDs
management, configuration of NG-RAN
sharing, etc.) and 5GC related management
aspects (e.g. traffic processing configuration,
service and session management, subscription
management). All these aspects need to be
analyzed for the different NPN categories (i.e.
SNPNs and PNI-NPNs), considering both
single-site and multi-site layouts. The structure
proposed in this contribution is aligned with
the approach followed for the different
5Growth pilots
20/09/07 ETSI NFV
TST
Link Submitted Support to these work-items as targets for
measurement techniques and tools, data
aggregation, and the communication of pilot
results as proofs-of-concept to ETSI NFV
20/09/07 IEEE
802.11bc
Link Reviewed This is a contribution to IEEE 802.11bc. We
believe IEEE 802.11bc can be used within the
I4.0 and Railway scenarios since it can be used
to connect low complexity sensors used in
both scenarios. This contribution specifically
removes the use of the Service Advertisement
Frame since its use has been added to the
eBCS Info frame
20/09/07 IEEE
802.11bc
Link Reviewed This is a contribution to IEEE 802.11bc. We
believe IEEE 802.11bc can be used within the
I4.0 and Railway scenarios since it can be used
to connect low complexity sensors used in
both scenarios. This contribution specifically
solves a security issue when the AP was
advertising no throttling characteristics for
eBCS UL traffic.
D6.3: Final Project Report 106
H2020-856709
20/09/14 ETSI ZSM ZSM(20)0003
26
Accepted This contribution is relevant for closed-loop
automation (CLA), which is one of the key
innovation in 5Growth project. CLA in 5Growth
leverages OSM capabilities.
20/10/18 3GPP SA2 S2-2005942 Accepted This provides service continutity when it is
necessary to switch between a private and
public network temporarily.
20/10/18 3GPP SA2 S2-2006257 Accepted This provides terminal inputs of quality of
expericence to the data analytics
enhancements to improve network
performance
20/11/09 IETF TEAS
WG
Link Submitted The relation with the project is to facilitate the
joint topological view of both networking and
computing resources available. This can be
useful for assisting on orchestration decisions
in the provider side both single- and multi-
domain scenarios.
20/10/18 3GPP SA2 S2-2005788 Accepted This provides a solution for low latency
switching of user plane functions between
MNOs for edge deployments
20/10/21 3GPP SA5 S5-205400 Accepted Relevant contribution for 5Growth network
slicing mechanisms as means of NPN
provisioning in industrial 4.0 scenarios.
20/10/21 3GPP SA5 S5-205402 Accepted This contribution is relevant for the interaction
of 5Growth stack with ICT-17 platform,
defining some key enablers in terms of
'management capability exposure'.
20/10/23 IETF Link Adopted Relevant to 5Growth due to the inclusion of
the I4.0 use case -> This document describes
different use cases of interest for reliable and
available wireless networks, which is basically
deterministic networking for wireless. This is
extremely relevant for 5Growth use cases,
especially Industry 4.0. This use case is
reflected in the document. It is an individual
contribution, recently adopted as WG
document.
20/11/15 3GPP SA1 S1-204264 Accepted This provides a description of switching
terminal connections from terminal to terminal
to local network via a gateway
20/11/15 3GPP SA1 S1-204265 Accepted This provides a description of switching
hosting environments via a gateway
20/12/03 IETF RFC 8948 Accepted It is relevant for I4.0 use cases, where a massive
number of devices need connectivity and
might benefit from the local addressing
assignment mechanisms described in the draft
-> This document describes extensions to
DHCP to allow a requester (client or
hypervisor) indicate the preference of the type
D6.3: Final Project Report 107
H2020-856709
of local address to obtain. This is applicable to
5Growth scenarios, e.g. in Industry 4.0. It is an
adopted WG document at the very end of the
publication process as RFC.
20/12/18 ETSI ENI ETSI ENI PoC
#9
Accepted The PoC will embed algorithms, strategies and
procedures for the composition, sharing and
auto-scaling of network slice subnets to build
and dynamically adjust the entire set of end-
to-end network slices following a closed-loop
approach (Task 2.4) to meet service-level
requirements, while optimizing the usage of
the underlying 5G infrastructure, jointly
considering access, core, edge, cloud
resources. Such strategies will be fed and
assisted by the ENI system, based on short-
term and long-term profiles related to
resource availability, service and network slice
performance, service demands, etc.
21/01/31 ETSI ZSM ZSM(21)0000
23r2
Accepted Network Slice as a Service (NSaaS) is a service
delivery model which is used for the
provisioning of PNI-NPN in 5Growth use cases
21/02/03 3GPP SA5 S5-211479 Accepted CAG is a 3GPP mechanism that allows for UE
access control in PNI-NPN scenarios. This is
relevant for 5Growth use cases.
21/02/04 3GPP RAN2 R2-2102087 Submitted This Contributions discussion ultra-reliable
communications in a controlled environment
like factories using cellular unlicensed
spectrum
21/02/04 3GPP RAN2 R2-2101509 Submitted This Contributions discussion ultra-reliable
communications with more enhanced QoS
requirements like those needed for Industry
4.0 applications
21/02/22 IETF Link Submitted This contribution discusses mechanisms to
allow a terminal influencing the selection of a
MEC host for instantiation of the terminal-
targeted MEC applications and functions, and
(re)configuring the RAW network lying in
between the terminal and the selected MEC
host, filling a gap that would allow to enhance
the applicability of MEC technologies in
Industry 4.0 scenarios as the ones addressed
by 5Growth (in WP3).
21/03/01 3GPP SA1 S1-210483 Submitted This contribution apply to the interconnecting
of two non-public factory networks
(equivalent to residential networks) for
minimum user interaction with the gateways
21/03/01 3GPP SA1 S1-210484 Submitted This contribution apply to the interconnecting
of two non-public factory networks
(equivalent to residential networks) for
seamless access between them
D6.3: Final Project Report 108
H2020-856709
21/03/10 3GPP SA5 S5-212360 Accepted This contribution details the management
aspects related to the UE provisioning in
5GLAN groups, which is applicable in industry
4.0 use cases such as the in-project pilot.
21/03/10 3GPP SA5 S5-212361 Accepted This contribution provides a classification of
placement (on-premises vs off-premises) of
NPN functions based on the different
management modes. The management
modes represent who (vertical, operator, 3rd
party) are in charge of managing the NPN
components. These management modes are
aligned with ICT-19/ICT-17 interactions
captured in 5Growth D3.1.
21/05/20 3GPP SA5 S5-213366 Accepted 3GPP management system provides MnSs to
the internal consumer to provision and
monitor 3GPP network including network slice.
The internal MnSs’ consumer of an operator
could be management function, network
function, application function, analytics
function, digital portal, etc. of the operator.
Based on operator’s policies and other
conditions, the MnSs exposed to different
consumers could be different. The operator
should configure fine grained access
permissions to restrict which MnSs are
accessible from which consumers
This pCR studies granular access control on
MnSs of 3GPP management system by mobile
network operator. This applies for the
capability exposure topic for ICT17/ICT19
integration.
21/05/20 3GPP SA5 S5-213506 Accepted According to potential requirement to support
use case 5.3 in this study report, the 3GPP
management system could have the capability
to allocate network slice based on granular
isolation requirements on the network slice
and group network slices with same isolation
requirements and security level.
According to definition and concept of
network slice subnet in TS 28.530, it is a
representation of a set of network functions
and the associated resources supporting
network slice. Network slice subnet could have
isolation requirements, and several network
slice subnets with same isolation properties
could be put into same isolation group.
Isolation requirements could be associated
with the service profile and slice profile,
guiding the allocation of network slice and
network slice subnet
D6.3: Final Project Report 109
H2020-856709
This pCR proposes enhancement of
NetworkSliceSubnet to support slice resource
isolation. This allows making slice subnet
allocation in 5Growth, ensuring appropriate
isolation level.
21/05/13 ETSI ETSI TR 103
761 V0.0.5
(2021-04)
Draft The challenges, approaches, methodologies
and tools produced by 5Growth project in
WP4 adoption, design and execution of
validation activities allows producing
guidelines and recommendations for piloting
vertical activities beyond the 5G-PPP
ecosystem.
21/05/25 IETF Link Adopted The need of OAM mechanisms for
deterministic or quasi-deterministic (reliable
and available) operation in wired (detnet
document) and wireless (raw document)
networks is particularly relevant to the Industry
4.0 addressed in 5Growth project, but also to
the other verticals.
21/05/25 IETF Link Adopted The need of OAM mechanisms for
deterministic or quasi-deterministic (reliable
and available) operation in wired (detnet
document) and wireless (raw document)
networks is particularly relevant to the Industry
4.0 addressed in 5Growth project, but also to
the other verticals.
21/05/25 3GPP SA1 S1-211442 Accepted This provides a description of service hosting
environment and application server connected
via a residential gateway
21/05/25 3GPP SA1 S1-211479 Accepted This provides a description of managing UEs
that accessed the local services in a hosting
network and switching back to their home
network.
21/07/12 ETSI ZSM ZSM(21)0002
65r1
Accepted This contribution provides a SoTA on the work
relevant from GSMA and OSM, according to
the technical background captured in different
5GRowth WP2/WP3 deliverables,
21/07/12 IETF TEAS
WG
Link Accepted This contribution proposes use cases (5G, RAN
sharing, etc.) for the definition of Transport
Slice NBI. The Transport Slice is an add-on
feature that allows Software-Defined
Transport Controller to capture TN slicing
related features (from 3GPP mgmt system) and
translating them into provisioning/CM actions
on underlying WAN nodes and resources.
21/07/26 IETF NMRG Link Submitted AI+monitoring framework integrated in
5Growth MANO stack for decision-making in
industrial scenarios
D6.3: Final Project Report 110
H2020-856709
21/07/26 IETF NMRG Link Submitted Semantic Data Aggregation framework linked
with evaluation data handling as done in WP4.
21/05/17 3GPP RAN3 R3-212659 Submitted This contribution summarizes the offline
discussion on successful handover report
which can be considered for 5growth objective
on optimization of the use of resources in
next-generation RANs.
21/05/17 3GPP RAN3 R3-212268 Submitted This contribution discusses the use of SHR to
optimize the selection of candidate target cells
in CHO and DAPS which can be considered for
5growth objective on optimization of the use
of resources in next-generation RANs.
21/05/17 3GPP RAN3 R3-212269 Submitted This contribution illustrates a partial use case
on data forwarding optimization that is
applicable for the study on AI in RAN and
potential benefits.
21/05/17 3GPP RAN3 R3-212271 Submitted This contribution illustrates a partial use case
on mobility enhancements that is applicable
for the study on AI in RAN and potential
benefits.
21/05/17 3GPP RAN3 R3-212868 Accepted This contribution proposes a new use case on
mobility optimization including traffic
steering, UE location/mobility prediction and
reduction of unintended events for TR 37.817.
21/07/05 3GPP SA1 S1-212007 Submitted This document proposes a new use case on
“augmented robotic telepresence” which is
aligned with 5growth I4.0 use case.
21/07/05 3GPP SA1 S1-212142 Accepted This document proposes to align the scope of
3GPP TR 22.847 with the SID. The proposed
scope alignment is relevant for 5growth I4.0
use cases that require real-time
experience/interactions.
21/05/10 3GPP SA1 S1-211497 Accepted This document proposes a new use case on
“Haptic feedback for a personal exclusion
zone” which is aligned with 5growth I4.0 use
case.
21/09/01 3GPP SA5 S5-214589 Accepted This contribution proposes to enrich the 3GPP
network slice info to provide Transport
network related information, specifically the
identifiers of logical transport interfaces.
Depending on the interface type used (VLAN,
MPLS, SR), the identifier are different (VLAN ID,
MPLS Tag, Segment ID).
This solution can be applied for 5growth use
cases that require transport slicing, making use
VLAN/MPLS technologies, depending on the
concrete 5growth application scenario.
21/09/01 3GPP SA5 S5-214638 Accepted GSMA defined attribute in General Slice
Template (GST) to isolate resource of network
D6.3: Final Project Report 111
H2020-856709
slices in different levels (refer to GSMA
NG.116).
As data is critical asset of a network slice
customer (NSC) for its business and operation,
in GSMA GST, the data of one NSC is always
required to isolate from other NSCs even for
the least strict isolation level - service/tenant
isolation.
This pCR is to introduce a new use case on
management data isolation for network slice
customers, and proposed potential
requirements and solutions. This is aligned
with the 5Growth approach, since 5Gr-VS
makes use of GST/NEST to derive network slice
related requirements and solutions.
21/09/28 ETSI TR 103761 Submitted This document describes a survey and review
of the existing methodologies for Testing and
Validation of vertical applications designed for
leveraging the potential of 5G&Beyond
networks, in order to identify existing gaps in
such methodologies and propose solutions to
cover them. Such methodology, is in part
developed and implemented in the vertical
uses cases covered by 5Growth project
21/10/27 IETF
(CCAMP
WG)
Link Adopted This contribution presents the design of a
Yang data model to describe the topologies of
microwave/millimeter radio links and
bandwidth availability, which can be used on
the NBI of the WIM controller to manage a
microwave-based transport networks. The
relevant use cases are for network
planning/optimization, links provisioning,
path/route computation, etc.
21/11/03 3GPP SA5 S5-215526 Accepted This contribution proposes to delimit the
scope of 3GPP in terms of network slice
capability exposure. The capabilities are made
available by the Network Slice Provider (NSP)
for consumption to the Network Slice
Customer (NSC).
The use cases presented here are applicable to
the ICT17/ICT19 integration aspects discussed
in 5Growth D3.1 and D3.2, with ICT17 acting as
the NSP and ICT19 acting as the NSC.
21/11/03 3GPP SA5 S5-215640 Accepted This CR introduces missing references in the
3GPP Information Model for Network Slicing
(Slice NRM fragment). References to GSMA
GST/NEST parameter used for 3GPP
ServiceProfile definition are missed, and fixed
with this contribution.
D6.3: Final Project Report 112
H2020-856709
21/11/03 3GPP SA5 S5-215649 Accepted This contribution updates the journey from
GST/NEST to 3GPP Service/SliceProfile and
configuration parameters.
TopSliceSubnetProfile is incorporated in the
workflow, and terminology is updated
according to Rel-17 modifications.
21/11/03 GSMA 5GJA 5GJA18_116 Accepted This discussion paper presents the gaps
existing between GST/NEST and 3GPP slicing
info model on the 'isolation topic'. Based on
these gaps, a set of actions are proposed and
endorsed. These actions are to be carried out
in the new GSMA work item called 'E2E
network slicing', approved at the latest GSMA
NG plenary meeting on late October.
21/08/06 3GPP RAN3 Link Available This discussion paper presents the areas where
AI/ML is most applicable and can improve the
network performance for the NG RAN, more
specifically on mobility use case and its
potential impacts.
3.5.3. Patents
Partners have filed seven patents (two more than originally planned), which are listed in Table 29.
They may lead to subsequent licensing opportunities, depending on the specific exploitation
strategies of the relevant academic institutions and companies.
TABLE 29: LIST OF PATENTS FILED
# Patent Application Title Partner
1 A method for anomaly detection of cloud services based on mining time-evolving
graphs
NEC
2 AIRIC: AI-driven Radio Intelligent Controller NEC
3 Application-based queue management NBL
4 Method and system for estimating network performance using machine learning
and partial path measurements
ERC
5 Method and Apparatus for managing network congestion NBL
6 Method to transmit and receive sensing data in NR system IDCC
7 Methods for UE-based joint selection and configuration of MEC host and RAW
network
IDCC
3.6. Impact
Expected Impact 1 Validated core 5G technologies and architectures in the context of specific vertical
use cases and deployment scenarios, from high to low density regions.
The work done during the second period of the project has provided further assessment of 5G
technologies and deployment scenarios. Within INNOVALIA pilot, the distributed and shared 5G
network deployment model has been successfully used having the core network that takes care of
D6.3: Final Project Report 113
H2020-856709
the control plane 400 km away from the radio access equipment, thus validating the viability of
running low latency applications using this deployment alternative, which is cost-effective and is
aligned with the Customer Service Providers’ business strategy. Moreover, the millimetre wave band
was utilized in an industrial environment and proved to be useful for getting high data rate in high
density areas. The addition of a low latency transport network to the 5G radio and core infrastructure
implemented for COMAU pilot have been an extra asset to guarantee critical latency requirements.
The EFACEC_S and EFACEC_E pilots achieved to implement and run their 5G network in a real-life
environment, bringing the 5G coverage to the vertical premises and executing the use cases on site.
Expected Impact 2 Validated core technologies and architecture for differentiated performance
requirements originating from eMBB, mMTC, URLL use cases, notably for end-to-end slicing and
virtualization.
The second reporting period has seen the completion of the plan to design and implement a number
of technology/architecture innovations into 5Growth platform (see D2.4 [2]). These include a range
of technologies, including:
• Mechanisms to network slices to the RAN arena and hence support end-to-end slicing.
• Mechanisms to support and attain security in federation and multi-domain scenarios.
• An AI/ML platform, closed-loop, and monitoring features to aid the integration of better control
and orchestration algorithms.
• Support for next-generation virtualized RANs.
• A large number of control/orchestration algorithms, anomaly detection algorithms, and
forecasting algorithms to solve a number of problems in virtualization and slicing use cases.
These innovations achieve all the KPIs set out as a target for the platform including 1) substantial
OPEX savings attained from a more efficient use of resources, 2) provide security thanks to
embedded security mechanisms and anomaly detection algorithms, or 3) expedite the deployment
and management of (virtualized) services in the mobile network.
As expected, an appropriate validation campaign of all these innovations has been successfully
performed during this period, as reported in D2.3 [1]. The final release of the platform integrating a
number of these innovations is introduced in D2.4 [2].
Expected Impact 3 Viable business models for innovative digital use cases tested and validated across
a multiplicity of industrial sectors, including demonstration of required network resource control from
the vertical industry business model perspective.
During this second period of the project, the previously defined business models have been further
developed and each of the stakeholders in the pilots has deepened in the possible business strategies
for the exploitation of the results. Furthermore, the techno-economic analysis and the validation of
these business models has been clarified and completed. This work is reported in D1.3 together with
the definition of the business layer, that is, how the verticals and the network operators define the
requirements of the service levels through the service level agreements (SLAs).
D6.3: Final Project Report 114
H2020-856709
Expected Impact 4 Impactful contributions towards standardization bodies, involving vertical actors,
for what concerns the second phase of 5G standardization. Participation of key European industrial
partners with high standardization impact is desired.
As reported in Section 3.5.1, the activity carried out in during this project allowed to provide a
remarkable number of contributions to various standard development organization (SDOs). A total
of 85 contributions have been submitted to IETF/IRTF, 3GPP, ETSI, GSMA, and IEEE. Furthermore, as
of the time of writing, 43 of them have been accepted in the corresponding body, which we believe
is also a remarkable achievement considering the substantial reduction in the number of meetings
and slowdown in decision making that the COVID-19 situation imposed. At least 8 of the partners
have been involved in the various contributions, including industrial partners, hence contributing to
the impact of such contributions in European industry. Several of the accepted contributions did not
just solve a current problem but initiated longer term work tasks that will solve issues with the
industry 4.0 verticals well beyond the project timeframe.
Expected Impact 5 Validation of relevant KPIs with services linked to specific vertical sectors. The trials
planned in the project will validate the 5G-PPP KPIs applying the 5G technologies.
Applying the mapping between Core and Service KPIs identified in the first stages of the project, the
team in charge of the validation tasks and of the execution of the different pilots have adapted and
applied the validation methodology and tools developed within the project, initially reported in D4.1
[21] and refined as shown in the successive validation deliverables: D4.2 [22], D4.3 [5]and D4.4 [6]. As
they evolved, the methodology and tooling have been applied to perform the measurements
relevant to the specific KPIs associated to each pilot. Progress in these KPIs is reported by the
validation deliverables, including a final assessment of the values obtained for the relevant use cases
at vertical premises, and of the impact of selected innovations on these KPIs included in D4.4.
Expected Impact 6 Europe 5G know how showcasing.
As presented in Section 2, an important part of the dissemination work is devoted to the organization
of events and technical demonstrations in which the results of the project are showcased. The
development and integration effort to move innovations to pilots carried out during the project
lifetime has been reflected in the multiple presentations, event organization, and technology
demonstrations in academic and industry-oriented events, both internal to the project consortium
members (e.g., with business units) and external (targeting academic and industrial organizations
working on 5Growth-related topics and products/services). More information specifically related with
industrial dissemination in its various ways is presented when discussing about Recommendation 3
from the review panel (Section 5) (incl. open source, standardization, exploitation, awards).
As a result of these activities, a total of 21 events have been organized and co-organized (and more
are under preparation), 27 technology demonstrations have been presented in renowned academic
and industry-oriented events, 50+ talks have also been given in events with a high variety of
audiences (incl. academia, industry, gender-related events, policy-oriented events). Furthermore,
multiple journals (47) and conference (34) papers have been accepted in renowned journals and
international conferences. Close collaboration with the 5GPPP through participation in the various
D6.3: Final Project Report 115
H2020-856709
working groups and the production of joint documents has also been a very relevant activity for the
project (e.g., co-editing of white papers, joint publications and demonstrations). Furthermore, this
involvement has been recognized in different ways, such as the selection of various 5Growth pilots
in the 5GPPP trials & pilots brochure (2nd and 3rd editions) and the election of our technical manager
as architecture WG vice-chair.
Communication to society at large has also been handled in the project through talks (e.g., open
science week), news, posters, social media, or lectures to graduate and undergraduate students.
Some videos of the demonstrations and pilots are available on the YouTube channel of the project.
Some of these activities have been recognized with an award, for instance, best demo runner-up
award in ACM Mobicom 2019, best Fast Track paper award in IEEE NFVSDN 2020, 5Growth received
the Madrid award on participation in European programs, 2021 Advanced Factory Finalist for best
industrial equipment for the factory of the future, best EUCNC 2021 booth award, best demo award
at IEEE SECON 2021, finalist in the 2021 ETSI MEC HACKATHON.
3.6.1. Progress towards the 5G-PPP Key Performance Indicators
Next, we summarize the progress and achievements of the project in regards of the 5Growth
contribution to 5G-PPP KPIs. Note that the KPI values defined by 5G PPP inside the table are specified
target 5G KPI values, and what we reported below are what the 5Growth project innovations and
pilots have achieved in the project on contributing to the impact on these KPIs.
Objective 1 Validate 5Growth business model (WP1)
KPIs Details on the progress of KPIs assessments
Reduce today’s network
management OPEX by at least
20% compared to today
The 5G technologies and the set of innovations developed in 5Growth have been
analyzed and validated in the designed business models geared towards achieving net
reductions in operational costs (OPEX) of over 20%. This is mainly achieved by the
reduction of the infrastructure cost by replacing cables with 5G, resulting in much less
cables and less hardware usage (because of the ability to share resources across
verticals). It also gains from an increased energy efficiency, reduction in travel (5G
enabled business cases on remote operation and remote control of machines or
devices) and faster reaction times. An overall better control of the systems in place was
explored, with benefits ranging from the economic and environmental benefits of Zero-
Defect manufacturing and more resilient systems, to saving lives because of the
prevention of train accidents.
European availability of a
competitive industrial offer for 5G
systems and technologies
The different benefits and cash flows have been explored in WP1, with collaboration
between verticals, network operators and manufacturer vendors and their customers in
Europe. The business models studied are therefore by-design analyzed to study the
industrial viability of 5G-driven systems and technologies to provide realistic solutions
to be implemented by the verticals in the short to mid-term. So far, all pilot use cases
presented and validated business models that would leverage European companies to
achieve a greater competitiveness in the vertical’s respective markets. The final business
model validation and SLA evaluation results are reported in D1.3 [10].
D6.3: Final Project Report 116
H2020-856709
Economic support of a novel range
of services of societal value like U-
HDTV and M2M applications
Several vertical pilots have defined a range of novel services including U-HDTV and
M2M applications in their use cases. In INNOVALIA Pilot, 4K video streaming with low
latency is a fundamental part for precise remote control of a CMM. In COMAU’s UC3,
eMBB is required to deliver un-interrupted video streaming to multiple users with high-
definition formats. In Efacec Sistemas’ use cases, U-HDTV transmitted through 5G
technology will allow the monitoring of train crossings in-real-time to avoid accidents.
And in Efacec Energia use cases, the HD video will allow the control of the infrastructure
and implement contingency and service restoration measures in substations. The
machine -to-machine collaboration will be specifically addressed in INNOVALIA’s
second use case, leveraging 5G for communications between the CMM and an AGV.
The use cases for Efacec Sistemas will also deploy this technology for railway level
crossing communication requirements that are safety critical for train detectors.
Reach a global market share for
5G equipment & services delivered
by European headquartered ICT
companies at, or above, 43%
global market share in
communication infrastructure
The companies participating in this project are Europeans, and thus the business
models and innovations explored would mainly benefit European stakeholder’s, helping
to achieve the goal of 43% global market share in communication infrastructure.
Objective 2 Design and develop 5Growth extensions into 5G architecture (WP2)
KPI Details on the progress of KPIs assessments
Reduce network management
OPEX by at least 20% compared to
today
The results related to the evaluation of the developed 5Growth innovations reported in
D2.3 [1] (Section 4.8 and 4.9.1.4) showed that we can meet (and exceed, during low-
load regimes) this KPI target thanks to an appropriate orchestration of network slices.
This is achieved thanks to features from Innovations 1 (RAN segments in network slices),
2 (Vertical-service monitoring), 3 (monitoring orchestration), 4 (control-loops stability),
5 (AI/ML support), 7 (next-generation RAN) and 8 (smart orchestration and control
algorithms).
The two most relevant examples are vrAIn and 5Gr-VS’s slice-sharing feature. In D2.3,
section 4.8, we show that vrAIn achieves up to 20% OPEX savings and up to 30% CAPEX
savings in next-generation virtualized RANs. In D2.3, we have shown that the slice-
sharing feature integrated we have developed for the 5Gr-VS achieves substantial
reduction in the number of CPU cores, which yields up to 20% reduction in case of low
workloads.
Create a secure, reliable and
dependable Internet with a “zero
perceived” downtime for services
provision
The SLA-preserving scaling algorithms and performance isolation techniques
developed in WP2’s Innovation 8, our anomaly detection algorithms (Innovation 9), and
the security features from Innovation 11, assessed in D2.3, sections 4.9.1, 4.9.2.2, 4.10,
and 4.12, validated this result at length.
Reduce the average service
creation time cycle from 90 hours
to 90 minutes
The enhancements developed in the platform at different levels (5Gr-VS, 5Gr-SO, 5Gr-
RL) provide an agile approach to service creation and lifecycle management. D2.3 has
shown plenty of results on this regard: see sections 4.1, 4.4, 4.6, 4.7, which validate the
ability of the 5Growth platform to create a service, and preserve its SLA, in less than a
few minutes. Features from WP2’s Innovation 1, 3, 4, and 6 contributed to this
achievement.
D6.3: Final Project Report 117
H2020-856709
Facilitate very dense deployments
of wireless communication links to
connect over 7 trillion wireless
devices serving over 7 billion
people
The focus on resource optimization in many innovations within WP2 such as Innovation
1, 4, 5, 7 and 8 contribute to this KPI by maximizing the efficiency of the available
resources, which makes networks amenable to denser scenarios. In addition, our
security, anomaly detection, and forecasting mechanisms (Innovations 9, 10, and 11),
shall help to preserve reliable services and quick reaction times upon changing events,
common in such dense scenarios. The results presented in D2.3, sections 4.6, 4.7, 4.8,
4.9, 4.10, 4.11 and 4.12, are evidence of this contribution.
Objective 3 Perform field trials and showcase vertical use cases in field trials (WP3/WP4)
Industry 4.0 - INNOVALIA Pilot
KPI Details on the progress of KPIs assessments
Provide 1,000 times higher
wireless area capacity and more
diverse service capabilities
compared to 2010
During the second reporting period, the INNOVALIA pilot has performed the final
validation campaigns through field trials at the vertical premises in Bilbao, Spain. The
pilot deployment for both UCs was described in D3.6 [4], Section 2.2 and Section 2.3.
The final results of UC-selected service and core KPIs evaluation were reported in D4.4
[6], Section 4.1. The relevant core KPI on data rate has been measured in both UCs.
In UC1, the peak throughput achieved in the network was measured under the existing
radio conditions at AIC premises and iperfs were run using mid-band frequency for
both Innovalia and Automotive Smart Factory (ASF) rooms. In this test, the pilot has
achieved the peak data rate of 36 Mbps between M3 and the iperf server on the INNO
VM, and up to 23 Mbps upstream to the CMM and Camera. Then the measurement
was also performed for the UC1 setup, which obtained the data rate of 10Mbps
between the probe and the M3 at the factory premises including RAN segment, while
the achieved user data rate of video streaming is at around 3 Mbps.
In UC2, throughput tests were performed with millimetre wave (mmW) radio at 5Tonic
lab. The achieved results were: (i) with carrier aggregation of six 100 MHz carriers, 1 W
per cell and standing 3 m away from the antenna: 430 Mbps DL and 40 Mbps UL; (ii)
with carrier aggregation of six 100 MHz carriers, 1 W per cell and standing 1 m away
from the antenna: 800 Mbps DL and 50 Mbps UL; and (iii) with carrier aggregation of
six 100 MHz carriers, 5 W per cell and standing 1 m away from the antenna: 720 Mbps
DL and 80 Mbps UL.
In the context of UC2 at Bilbao, iperf tests were done with the CMM device end at ASF
connected via millimetre wave (mmW) antennas. At AIC, the radio conditions were
again aggregation of six carriers, 5W per cell and standing 5m away from the antenna.
Under these conditions, and again running three parallel threads for a few minutes the
result obtained for the iperf from a client on the INNO VM to a server on a PC connected
close to the camera and CMM, was 13 Mbps. When running the iperf in reverse, the
outcome was 27 Mbps.
In the operation of UC2, the traffic between the AGVc VM and the AGV while the AGV
is UDP, and it is demanding an average data rate of 270 kbps in uplink (from the AGV
towards the AGVc VM) and 100 kbps in downlink (from the AGVc VM towards the AGV).
The tests showed that the deployed 5G infrastructure was able to support the required
data rate successfully and even allow multiple users at these rates though.
D6.3: Final Project Report 118
H2020-856709
Create a secure, reliable and
dependable Internet with a “zero
perceived” downtime for services
provision
The relevant core KPI on service deployment time and latency were measured in both
INNOVALIA UCs. The final measurement results were reported in D4.4, Section 4.1.
The service deployment time achieved to deploy UC1 was in the order of 250 seconds.
This value is in line with the target set for this pilot UC. The service deployment time
increased up to around 300s in UC2, but still in line with the pilot defined targets. Both
values are also aligned with requirements of 5GPPP, reducing the service creation time
to the order of minutes.
In terms of latency, the E2E latency measured in UC1 was 210 ms (70ms +140ms)
between the probe and the M3, and 45ms for video streaming. In UC2, the measured
average E2E latency was 195ms (130 ms + 65ms).
The “zero perceived” service time has been validated by the successful provisioning
and execution of the services throughout dozens of iterations in our experiments.
Objective 3 Perform field trials and showcase vertical use cases in field trials (WP3/WP4)
Industry 4.0 - COMAU Pilot
KPI Details on the progress of KPIs assessments
Provide 1000 times higher wireless
area capacity and more diverse
service capabilities compared to
2010
During the second reporting period, the COMAU pilot has performed the final
validation campaigns through field trials at the vertical premises in COMAU, Italy.
The relevant core KPI on data rate was measured in UC3: Digital tutorial and remote
support. UC3 is associated with eMBB performances as the video streaming related to
the remote support use case requires the transmission of real-time video. For the
validation campaigns, an optical 5G transport network is tested in this pilot to connect
the Baseband Units to the Radio Units of the radio cells, implementing centralized RAN
architecture, where Baseband units serving several radio sites are centralized in a single
location. The pilot deployment was described in D3.6 [4], Section 3.4.
As reported in D4.3 [5], the second validation campaign has verified the network
performances in terms of throughput and packet loss on the integrated (radio,
transport, platform) infrastructure. More specifically, the second validation campaign
has measured a TCP average throughput of 789 Mbit/s in DL and 43 Mbit/s in UL. The
UDP average throughput has resulted in 855 Mbit/s in DL and 42 Mbit/s in UL. The
related graphs are reported in D4.3, Figures 35-38.
After the second validation campaign, the network has been tuned for latency
optimization while the throughput settings have not been modified. The final
throughput measurements were reported in D4.4: TCP 761 Mbit/s DL, 65 Mbit/s UL;
UDP 952 Mbit/s DL, 66 Mbit/s UL. Both the DL values are well above the target of 500
Mbit/s identified for the UC3. Besides, the packet loss has been measured as lower than
2*10-6, achieving the same performance of the second validation campaign.
Create a secure, reliable and
dependable Internet with a “zero
perceived” downtime for services
provision
The relevant core KPI on latency was measured mainly in UC1: Digital twin apps. This
UC, whose architecture is described in Section 3.2 of D3.6 [4], has a strict requirement
on latency. This requirement comes from the need of having the digital twin (i.e., virtual
representation) in perfect “visual” alignment with the real robot. In other words, the
user looking at the digital twin, on a screen or in AR/VR glasses, should have the
perception of synchronization of the two robots: the real robot and its digital replica.
The requirement posed on E2E RTT latency is 15 ms as maximum. As reported in D4.4,
D6.3: Final Project Report 119
H2020-856709
the measured time for transmission over 5G was ranging from 13.3 ms to 18.9 ms with
an average of 16.1 ms. In addition, no packets have been lost during the tests. At the
same time all the jitter values have been registered in the range of 6.8ms and 6.4 ms,
with an average value of 0 ms.
This performance has practically demonstrated a perfect “perceptible” alignment of the
real robot with its digital twin inside the AR glasses. In addition to the latency
measurements, a “visual” verification of the use case from the user perspective has been
done by posing “side-by-side” the digital reproduction of the real robot and the real
robot itself to verify the perception of the real-time alignment between the virtual and
the real entity. This practical assessment demonstrates a good synchronization.
Objective 3 Perform field trials and showcase vertical use cases in field trials (WP3/WP4)
Transportation – EFACEC_S Pilot
KPI Details on the progress of KPIs assessments
Provide 1000 times higher wireless
area capacity and more diverse
service capabilities compared to
2010
The final validation campaign was performed with field trials in the real vertical premises
at the level crossing at the Aveiro commercial harbor in Portugal. The pilot deployment
for both UCs was described in D3.6, Section 5.2 and Section 5.3.
The relevant core KPI on throughput to this pilot was measured in both UCs for both
safety and non-safety critical communications, the results were reported in D4.4,
Section 4.3. The performance of the tested 5G network at the vertical site, in terms of
UDP traffic reached throughput around 20 Mbps with neglectable losses (0,026%)
within the coverage area of the level crossing allowing the trigger conditions to activate
the video transmission to the train.
In the final test, the Site Acceptance Tests (SAT) were also performed for the real level
crossing scenario, with all software and hardware components enabled, interconnected,
and running. During the SAT tests, using the 5GAINER (Portugal 5G+IA Networks
Reliability Center) 5G network, the performance of the 5G network, in terms of UDP
traffic has reached throughput in UC1 around 90 Mbps with no losses and with a jitter
value of 0,052 ms; and in UC2 around 80 Mbps with 0,061% of lost datagrams within
the coverage area of the level crossing. The SAT test resuts have validated that the pilot
has achieved good performance values (latency, packet loss, bandwidth, and
availability) with 5G and also validated both UC1 and UC2 functionalities in the real
vertical premises, using train simulators or even real freight trains to achieve the proper
behaviour of the system supported by 5G technology, allowing to detect the proper
behaviour of the level crossing and transmit the HD video with a good quality.
Save up to 90% of energy per
service provided
For the Transportation pilot, the energy KPI is not considered as one of the service KPI
for this pilot and thus no evaluation on energy saving has been performed.
However, the solution is based on the principle that no cables were interconnected the
central site and the remote sites, since the wireless 5G technology is deployed. This
absence of cables is related either to communication cables or power supply cables,
since the remote cabinets were fed locally by solar panels. Therefore, a significative
energy safe was achieved. According with last measurements campaigns, in the Pilot
site, it is possible to obtain an energy saving of 54 Watts in a total of 243 Watts
consumed, which represents a saving of 24%.
D6.3: Final Project Report 120
H2020-856709
Create a secure, reliable and
dependable Internet with a “zero
perceived” downtime for services
provision
The relevant core KPI on latency and service time in this pilot was measured in both
UCs. The detailed results were reported in D4.4, Section 4.3. The latency of the tested
5G network at the vertical premises, in terms of E2E latency between LX detectors and
LX Controller, was about 29 ms in average in both UC1 and UC2.
In addition, in the real SAT tests, using the 5GAINER (Portugal 5G+IA Networks
Reliability Center) 5G network, the performance of the 5G network, in terms of End-to-
end Latency reached 8,25 ms (average) in the UC1 and around 15 ms in the UC2, and
no packet losses were detected.
The SAT test results have validated that the pilot has achieved good service
performance values (latency, packet loss, bandwidth, and availability) with 5G and also
validated both UC1 and UC2 functionalities in the real vertical premises, using train
simulators or even real freight trains to achieve the proper behaviour of the system
supported by 5G technology, allowing to detect the proper behaviour of the level
crossing and transmit the HD video with a good quality.
Objective 3 Perform field trials and showcase vertical use cases in field trials (WP3/WP4)
Energy – EFACEC_E Pilot
KPI Details on the progress of KPIs assessments
Provide 1000 times higher wireless
area capacity and more diverse
service capabilities compared to
2010
The most relevant core KPI on data rate of this pilot was measured in UC1 (Advanced
Monitoring and Maintenance Support for Secondary Substation MV/LV Distribution
Substation) and the final tests results were reported in D4.4, Section 4.4.1.
For the UC1, the final validation campaign was fully deployed at the vertical site (IT
datacenter and UA secondary distribution substation), as described in D3.6, Section 4.2.
As reported in D4.4, Section 4.4.1, the performances of the field trials of the 5G network
at the vertical site to transmit the data flow (in terms of UDP traffic) between the
Secondary Substation and the Control Center provided a good video streaming
experience. During the test period the service availability was 100% and no packet loss
was detected up to 10Mbps. The data rate could reach 60.0 Mbps. Even when pushing
for higher uplink data rates between 20Mbps and 60 Mbps, the rate of lost packets is
low and compatible with a good video streaming experience.
Create a secure, reliable and
dependable Internet with a “zero
perceived” downtime for services
provision
The most relevant core KPI on latency of this pilot was measured in UC2 (Advanced
critical signal and data exchange across wide smart metering and measurement
infrastructures) and the final test results were reported in D4.4, Section 4.4.2.
For the UC2, the final validation campaign was fully deployed at the vertical site (UA
secondary distribution substation, and IT2 building), as described in D3.6, Section 4.3.
As reported in D4.4, section 4.4.2, the latency performances obtained in the field trials
of the 5G network at the vertical site was measured. More specifically, the Last-gasp
Information End-to-end latency between the Low Voltage Sensors (LVS3) installed in
the low voltage network and the Gsmart installed inside the secondary substation was
measured directly in the application, which was 27.94 ms in average. The Secondary
Substation End-to-end Latency was about 22.98 ms (average). The latency in the Time
Synchronization service between the LVS3 device and the NTP Server was 13.40 ms
(average), achieving an average difference of 1.21 ms (average) between LVS3 devices
when comparing each ones synchronized time.
D6.3: Final Project Report 121
H2020-856709
Overall, the latency performances obtained were good and in line with the target
objectives for this UC. Besides, no packet loss was observed, with all the last-gasp
events created in LVS3 devices being transmitted to the 5G network and received in the
Gsmart, which results in a service availability of 100%, in the conditions and period of
the test.
Objective 5 Dissemination, standardization and exploitation of 5Growth (WP5)
KPI Details on the progress of KPIs assessments
Generate patents Seven patents submitted
Establish and make available 5G
skills development curricula
Lectures taught at nine different postgraduate and industrial courses
Twenty-seven bachelor, master and PhD theses directly related with 5Growth research
topics
D6.3: Final Project Report 122
H2020-856709
4. Update of the plan for exploitation and dissemination of
results
Throughout the project lifetime, the communication, dissemination, and exploitation plan (CoDEP)
presented in the proposal was periodically refined according to the evolution of the project and the
activities considered of interest. The initial plan was presented in D5.1 [26], along with early
achievements. D5.2 [27] presented the achievements during the initial period of the project as well
as a refinement of the plan for the following period. D5.4 [25] provided an update of the results and
D5.7 [7] reports on all the achievements, as well as updates to the exploitation plan. It is not repeated
here for brevity. The reader is referred to the above documents.
D6.3: Final Project Report 123
H2020-856709
5. Follow-up of recommendations and comments from
previous review
Next, we enumerate all the comments received from the experts during the 1st technical review, as
included in the Review Report. We include an explanation of how we have address each of the
recommendations.
We have taken very seriously this comment by continuously assessing the situation in view of COVID-
19 impact. To cope with the delays suffered and the expected ones, the project has been extended
for 3 additional months. All the potentially impacted deadlines for deliverable submission and
milestones were revised and updated:
• New end date of WP1, WP5 and WP6 is M33. New end date of WP3 and WP4 is M30.
• Change of dates of some deliverables and milestones. Below we indicate the new dates
for deliverables and milestones. The dates have been changed in the GA.
MILESTONES Old date New date
MS20 M30 M33
MS14 M24 M25
MS17 M27 M30
MS15 M24 M25
MS18 M27 M30
MS21 M30 M33
DELIVERABLES Old date New date
D1.3 M30 M33
D3.5 M24 M25
D3.6 M27 M30
D4.3 M23 M25
D4.4 M27 M30
D5.5 M25 M27
D5.6 M28 M30
D5.7 M30 M33
D6.3 M30 M33
Recommendation 1: Reassess project delivery plan due to COVID-19 restrictions
The project delivery plan needs to be reassessed, with a realistic view of the COVID-19
delays, impact, and mitigation actions. A realistic plan for what can be delivered by the end
of the project must be devised. The guiding force should be the higher impact result delivery
in the next project phases. During the review, a potential extension of the project for 3-4
months was considered, which is seen as appropriate.
D6.3: Final Project Report 124
H2020-856709
As part of this continuous assessment, and due to the impact of the different COVID-19 waves
through Europe, we also updated our initial plan of submitting D3.5 and D4.4 at the same time, by
delaying 15 days the submission of D4.4, to focus on the final writing and presentation of results
once D3.5 had been submitted. This change was communicated to the PO with sufficient time in
advance, and it was agreed and approved this delay (without going through an official amendment).
Last, but not least, due to the impact on in-person events (still quite significant at the time of
submission of this deliverable), we decided to focus all our efforts in terms of pilot dissemination in
generating professionally recorded video materials, that will be used for both external and internal
exploitation, as well as during our final Technical Review, that was also decided to take place online
to mitigate the uncertainties of planning an in-person one.
This recommendation has been addressed by WP1, which has gone deeper into the definition of
business models for each pilot, using the Ostenwalder model (Business Canvas Model). Each section
of the model has been described in detail for each stakeholder in each pilot, resulting in a
comprehensive and clear business model.
Likewise, the KPIs and the validation methodology itself have been revised and extended. The results
have been reported in deliverable D1.3 [10].
Recommendation 2: Develop more detailed business models and KPIs
There are some concerns with the business models and their evaluation as well as the KPIs
as also described in the relevant deliverable sections. More specificity here will help the
project’s next phases e.g. validation, while it will also make clearer which exploitation and
business strategies can be realized and how. These aspects can be part of the upcoming
D1.3.
D6.3: Final Project Report 125
H2020-856709
As part of the planned activities of the CoDEP defined for the last period of the project and as a
consequence of this recommendation, the project has carried out multiple project- and partner-level
actions. The actions to raise awareness in industrial communities of the project results was already
initiated with the organization of the industry-oriented webinar entitled "Powering 5G in industry"
(together with Layer 123, a renowned organization that organizes industry-oriented events, such as
the Layer123 World Congress). Furthermore, 5Growth recently organized the exploitation workshop
entitled "Experiences from field trial about vertical industry" with slots devoted to verticals,
operators/vendors and SMEs, which represented an appropriate discussion forum to make visible
and discuss with external industrial stakeholders and end-user groups on the lessons learned
through the participation in 5Growth. The project has also been represented in several industry-
oriented events, some of them directly exploiting open-source software developed in the project,
such as an ETSI ENI PoC, the ETSI MEC Hackaton, or the OSM ecosystem day. Furthermore, the project
has continued its contributions to open-source projects (e.g., OSM), and development carried out by
partners in the project have been fed into products of some companies (e.g., the k0s by Mirantis
targeting telco edge solutions).
Participation in relevant industry-oriented events has also been common (demo from IDCC in Mobile
World Congress 2021 and another one from CTTC in Mobile World Congress 2022). 5Growth also
publicized its achievements through industry-oriented events closer to end-users/verticals (e.g., 2021
Advanced Factory, Metromeet'21). Some of these participations resulted in some
awards/recognitions (e.g., outstanding contributions to OSM for a 5Growth researcher from IT
Aveiro, finalist in the 2021 Advanced Factory Best industrial equipment for the factory of the future
for Innovalia, or finalist in the ETSI MEC Hackaton for Telcaria).
As for standardization, in addition to those mentioned above linked with open source, the SAC has
continued its supervisory and guidance activities which resulted in multiple additional contributions
to various SDOs (ETSI, IETF, IRTF, 3GPP, GSMA, IEEE) a grand total of 85 contributions of which 43
were approved. This also triggered further activities and on the standardization dissemination front,
including the creation of work tasks in 3GPP that will run beyond the 5Growth timeline. Let us
Recommendation 3: Enhance external industrial dissemination/exploitation and
standardization
The academic dissemination so far is very good. Industrial dissemination could be
strengthened, with more active strategies targeting external industrial stakeholders and
end-user groups. More detailed exploitation strategies at partner and project level strongly
linked to the exploitable project outputs are expected in the next months. Standardization
involvement so far is very good but needs to be strengthened towards sustainable impact
(potentially combined with the very good delivery of open source that is already ongoing).
Efforts should be invested to maximize the impact from the established standardization
advisory committee towards the relevant SDOs.
D6.3: Final Project Report 126
H2020-856709
highlight the contributions to the report entitled "5G-PPP Projects Impact on SDO Technical Report"
and the participation to the 5GPPP pre-standardization WG, which resulted in 5Growth being listed
as part of success story examples in this work group.
Moreover, exploitation plans by each partner in D5.7 also reflect the updates done in this direction
in accordance with the results of 5Growth with an identification of the 5Growth architectural building
block or pilot that is related with each of them.
Finally, there have been other types of events that served to raise awareness of the work done in
5Growth, such as the discussions with business units internal to partner organization or trying to
have an impact on the ecosystem of influence (such as the "empowering the future event" from
EFACEC (internal), or the event under preparation in the Aveiro Harbor also from EFACEC with the
ecosystem or the 119th techday from AlticeLabs), but external to the project. There are events jointly
organized internally among partners to find synergies towards exploitation (e.g., Ericsson-Telefonica,
Ericsson-TIM), and also events targeting a broader audience, such as the SouthSummit (session on
ecosystem-based innovation).
Some of the key results of the project are currently being introduced in the EC horizon results
platform to further enhance the exploitation of 5Growth results beyond the project lifetime as well
as in the innovation radar.
We will include a detailed explanation of how the resources have been used, linking to the actual
technical work in Section 6.2. Since the second reporting period of the project closes on February
28th, 2022, the final information of resources (PMs) used during the second reporting period (M19-
M33) will not be available before March 15th, 2022. The final version of the Periodic Report will be
complete before the deadline (April 29th, 2022), including these required explanations.
5.1. Additional recommendations
In the following, we summarize how we have addressed additional recommendations received from
the reviewers, even if not explicitly included as recommendations in the official review report.
• While some females are involved in the project and its achievements, overall the current
reports have no sufficient info on consortium efforts to achieve gender balance.
Recommendation 4: Deviations in resource usage should be linked to additional technical
work
Some deviations are identified, however, in several cases, these are treated only at the
resource level e.g. promising to add more resources to cover the underutilization. However,
the link to the additional technical work is not sufficiently described and should be
thoroughly explained in the Periodic Technical Reports.
D6.3: Final Project Report 127
H2020-856709
o The consortium has made significant efforts to improve our gender balance. Among
the different activities, we can mention the following:
▪ 5Growth active participation in the Women in Hexa-X/6G initiative.
▪ Additional activities of 5Growth female researchers in leading roles:
• Dr. Carla Chiasserini published the following paper: Women in
Networks: Dr. Carla Fabiana Chiasserini, Politecnico di Torino, Italy," in
IEEE Network, vol. 35, no. 4, pp. 4-5, July/August 2021, doi:
10.1109/MNET.2021.9520377.
• Dr. Carla Chiasserini chaired the N2Women Workshop at ACM
Mobicom 2021.
• Dr. Barbara Martini was the TPC co-chair of IEEE Netsoft 2021.
• Dr. Molka Gharbaoui (CNIT/SSSA) was the TPC co-chair of IEEE NFV-
SDN 2021.
• Dr. Carla Chiasserini was general Co-chair of IEEE SECON 2021.
• Dr. Carla Chiasserini was General Co-chair of ITC33.
• Dr. Carla Chiasserini was a keynote speaker at 2nd IEEE 5G++ Online
Summit Dresden.
• Annachiara Paganois the TIM voting member in O-RAN WG9.
• Xi Li (Technical Manager of 5Growth) was elected as Vice-chair of the
5GPPP Architecture WG.
• Xi Li co-chaired of ZNSM (1st International Workshop on Zero-Touch
Network and Service Management (ZNSM 2021)) Co-located with
CNSM 2021.
▪ We also want to highlight some examples of company policies and initiatives
at partner level to enforce gender balance, such as:
• UC3M-level program to foster women engineering careers:
https://www.uc3m.es/ss/Satellite/UC3MInstitucional/en/FormularioTe
xtoDosColumnas/1371216285734/
• Telefonica is part of #LadyHacker global movement that seeks to
make visible the role of women in the technology sector and to raise
awareness among our girls of their potential to study STEM degrees:
https://mujereshacker.telefonica.com/en
• Telefonica has a workforce diversity policy, including gender balance
goals: https://jobs.telefonica.com/content/Diversity/?locale=en_GB
• CTTC has a gender equality plan as part of the "Gender equality plan
and harassment prevention protocol: http://www.cttc.es/wp-
content/uploads/2015/04/Pla-dacci%C3%B3-2021-2025-1.pdf
• A direct reference to EU funding is available in most activities, but for some e.g., GitHub
projects, this is not always sufficiently clear.
o An ACK has been included in the README.md file of each GitHub repository (Figure
36).
D6.3: Final Project Report 128
H2020-856709
FIGURE 36: GITHUB INCLUDING A REFERENCE TO THE EU H2020 PROGRAM
o Added the reference to the project in the YouTube channel description.
o Added the reference to the project in the Instagram and Twitter descriptions (Figure
37).
D1.1. Correct statement TR-P1UC1-01 within Table 3: Technical requirements (Page 38)
o This has been fixed in a new version (v1.3) of D1.1 that we made available in the
project website.
FIGURE 37: INSTAGRAM AND TWITTER DESCRIPTIONS
D6.3: Final Project Report 129
H2020-856709
• D2.2. Some aspects could have been more detailed with respect to the technical dilemmas
and decisions made.
o This recommendation was considered in the writing of D2.4.
• D5.3. A brief explanation of demonstration activities carried out that showed good results
and proof of-concept. The details on the demonstrations are very limited and since this is a
public deliverable some more details could have been made available for the readers. Links
to the material e.g., on the MOBICOM poster (fig. 1) could have been embedded or
attached in full-page.
o This has been updated in a new version (v1.1) of D5.3 that we made available in the
project website.
D6.3: Final Project Report 130
H2020-856709
6. Deviations from Annex 1 and Annex 2
6.1. Tasks
None to report.
6.2. Use of resources
As the second reporting period of the project closes on February 28th, 2022, the final information of
resources (PMs) used during the second reporting period (M19-M33) will not be available before
March 15th, 2022. The final version of the Periodic Report will be complete before the deadline (April
29th, 2022).
D6.3: Final Project Report 131
H2020-856709
7. References
[1]. 5Growth, D2.3, Final Design and Evaluation of the innovations of the 5G End-to-End Service
Platform, May 2021.
[2]. 5Growth, D2.4, Final implementation of 5G End-to-End Service Platform, May 2021.
[3]. 5Growth, D3.5, Final version of software implementation for the platform, June 2021.
[4]. 5Growth, D3.6, Execution report of in-house use cases for Pilots, November 2021.
[5]. 5Growth, D4.3, 5G facility validation and verification report, June 2021.
[6]. 5Growth, D4.4, Final validation and verification report, December 2021.
[7]. 5Growth, D5.7, Communication, Dissemination, and Exploitation achievements through the
project, exploitation plan after the, end of the project and assessment of the contribution of
5Growth in support of 5G, February 2022.
[8]. 5Growth, D1.1, Business Model Design, September 2019.
[9]. 5Growth, D1.2, Techno-economic analysis and business model validation methodology,
August 2020.
[10]. 5Growth, D1.3, Business model validation with its complemented SLA, February 2022.
[11]. 5G-PPP Technology Board & 5G IA Verticals Task Force. “Empowering Vertical Industries
through 5G Networks - Current Status and Future Trends.” September 2020.
[12]. C. Papagianni et al., “PI2 for P4: An Active Queue Management Scheme for Programmable Data
Planes”, ACM CoNEXT 2019.
[13]. C. Papagianni et al., “5Growth: AI-driven 5G for Automation in Vertical Industries”, 2020
European Conference on Networks and Communications (EuCNC), IEEE, 2020.
[14]. JA. Ayala-Romero et al., “vrAIn: A deep learning approach tailoring computing and radio
resources in virtualized RANs”, The 25th Annual International Conference on Mobile
Computing and Networking. 2019.
[15]. K. Antevski et al., “A Q-learning strategy for federation of 5G services”, ICC 2020-2020 IEEE
International Conference on Communications (ICC), IEEE, 2020.
[16]. V. A. Cunha, et al., “Moving Target Defense to set Network Slicing Security as a KPI”, Internet
Technology letters, Vol. 3, No. 4, pp. 1 - 6, May, 2020.
[17]. 5Growth, D3.1, ICT-17 facilities Gap analysis, October 2019.
[18]. 5Growth, D3.2, Specification of ICT-17 in-house deployment, April 2020.
[19]. 5Growth, D3.3, First version of software implementation for the platform, November 2020.
[20]. 5Growth, D3.4, Plan for Pilot deployments, November 2020.
[21]. 5Growth, D4.1, Service and Core KPI Specification, May 2020.
[22]. 5Growth, D4.2, Verification methodology and tool design, November 2020.
[23]. A. Ruete. “Communicating Horizon 2020 projects.” Available at:
https://ec.europa.eu/easme/sites/easme-site/files/documents/6.Communication-
AlexandraRuete.pdf
[24]. IPR Helpdesk. “IPR glossary”. Available at: https://www.iprhelpdesk.eu/glossary
[25]. 5Growth, D5.4, Report on WP5 Progress and Update of CoDEP, May 2021.
D6.3: Final Project Report 132
H2020-856709
[26]. 5Growth, D5.1, Initial Communication, Dissemination, and Exploitation Plan (CoDEP) draft
including Standardization roadmap, November 2019.
[27]. 5Growth, D5.2, Communication, Dissemination, and Exploitation achievements of Y1 and plan
for Y2, May 2020.