00 91 13.03 ADDENDUM NO. 3 - BidNet

87
ADDENDUM NO. 3 00 91 13.03 - 1 KER17340 – Water Treatment Plant THM Control Facility CITY OF KERRVILLE, TEXAS KERRVILLE WATER TREATMENT PLANT THM CONTROL FACILITY FNI PROJECT NO. KER17340 JANUARY 28, 2019 00 91 13.03 ADDENDUM NO. 3 The following additions, deletions, modifications, or clarifications shall be made to the appropriate sections of the Contract Documents. Bidders shall acknowledge receipt of this Addendum in the space provided on the Bid Form. ARTICLE 1 – BID REQUIREMENTS A3-1 Section 00 11 16 “Invitation to Bid” A. Amend section as follows: The time for receipt of Bids has been changed to February 15, 2019 at 3:00 p.m. B. The location for the receipt of Bids is unchanged. A3-2 Delete Section 00 42 23.01 “Bid Form Exhibit A” in its entirety and replace with Section 00 42 23.01 “Bid Form Exhibit A” attached to this Addendum. A3-3 Delete Section 01 29 00 “Payment Procedures” in its entirety and replace with Section 01 29 00 “Payment Procedures” attached to this Addendum. ARTICLE 2 – TECHNICAL SPECIFICATIONS: A3-4 Add the following specification sections: ADD Section Section Section Title 33 11 13.13 “Steel Pipe” 40 05 64 “Butterfly Valves” A3-5 Replace the following specification Sections: Replace Section With Section Section Section Title Section Section Title 09 96 00.01 “High-Performance Coatings” 09 96 00.01 “High-Performance Coatings” A3-6 Specification 40 72 00 “Level Instrumentation Devices” – See attached for modifications. A3-7 Specification 40 78 00 “Panel Mounted Control Devices” – See attached for modifications. A3-8 Specification 40 61 96 “Control Loop Descriptions” – See attached for modifications. A3-9 Specification 46 07 13 “Adsorption Systems for Use with Granulated Activated Carbon” A. Delete paragraph 2.02.E.7. in its entirety.

Transcript of 00 91 13.03 ADDENDUM NO. 3 - BidNet

ADDENDUM NO. 3 00 91 13.03 - 1

KER17340 – Water Treatment Plant THM Control Facility

CITY OF KERRVILLE, TEXAS

KERRVILLE WATER TREATMENT PLANT THM CONTROL FACILITY

FNI PROJECT NO. KER17340

JANUARY 28, 2019

00 91 13.03 ADDENDUM NO. 3

The following additions, deletions, modifications, or clarifications shall be made to the appropriate

sections of the Contract Documents. Bidders shall acknowledge receipt of this Addendum in the space

provided on the Bid Form.

ARTICLE 1 – BID REQUIREMENTS

A3-1 Section 00 11 16 “Invitation to Bid”

A. Amend section as follows:

The time for receipt of Bids has been changed to February 15, 2019 at 3:00 p.m.

B. The location for the receipt of Bids is unchanged.

A3-2 Delete Section 00 42 23.01 “Bid Form Exhibit A” in its entirety and replace with Section 00 42

23.01 “Bid Form Exhibit A” attached to this Addendum.

A3-3 Delete Section 01 29 00 “Payment Procedures” in its entirety and replace with Section 01 29 00

“Payment Procedures” attached to this Addendum.

ARTICLE 2 – TECHNICAL SPECIFICATIONS:

A3-4 Add the following specification sections:

ADD Section

Section Section Title

33 11 13.13 “Steel Pipe”

40 05 64 “Butterfly Valves”

A3-5 Replace the following specification Sections:

Replace Section With Section

Section Section Title Section Section Title

09 96 00.01 “High-Performance Coatings” 09 96 00.01 “High-Performance Coatings”

A3-6 Specification 40 72 00 “Level Instrumentation Devices” – See attached for modifications.

A3-7 Specification 40 78 00 “Panel Mounted Control Devices” – See attached for modifications.

A3-8 Specification 40 61 96 “Control Loop Descriptions” – See attached for modifications.

A3-9 Specification 46 07 13 “Adsorption Systems for Use with Granulated Activated Carbon”

A. Delete paragraph 2.02.E.7. in its entirety.

ADDENDUM NO. 3 00 91 13.03 - 2

KER17340 – Water Treatment Plant THM Control Facility

B. Modify paragraph 2.02.H. as follows:

“H. The exterior surface of the adsorbers will be painted to a dry film thickness of 10 to 14

mil with a high solids epoxy (gray color) paint and a top coat of compatible polyurethane

paint at 2 to 4 mil dft. Approved coating manufacturers must be as specified in section 09

96 00.01 “High-Performance Coatings.”

C. Modify paragraph 2.07.G. as follows:

“G. Provide three (3) 1” sample nozzles and full port ball valves, to be located so Owner can

test for turbidity, pH, and temperature from each vessel effluent separately and for the full

system before effluent exits adsorption system.”

ARTICLE 3 – DRAWINGS:

A3-10 Replace the following Drawings:

Replace Drawing With Drawing

Drawing No. Drawing Title Drawing No. Drawing Title

G-3 “Process Flow Diagram” G-3 “Process Flow Diagram”

C-1 “Site Plan” C-1 “Site Plan”

C-2 “Yard Piping Plan Sheet 1” C-2 “Yard Piping Plan Sheet 1”

C-2A “Proposed Paving Plan” C-2A “Proposed Paving Plan”

C-4 “Site Yard Piping Profiles

Sheet 1” C-4

“Site Yard Piping Profiles

Sheet 1”

C-5 “Site Yard Piping Profiles

Sheet 2” C-5

“Site Yard Piping Profiles

Sheet 2”

E-4 “Enlarged Site Plan” E-4 “Enlarged Site Plan”

E-7 “One-Line Diagram – II” E-7 “One-Line Diagram – II”

E-9 “GAC One-Line Diagram – I” E-9 “GAC One-Line Diagram – I”

E-11 “Pump Station Control Panel” E-11 “Pump Station Control Panel”

E-12 “MCC Plan and Section” E-12 “MCC Plan and Section”

E-13 “Pump Station Plan, Section,

and Riser Diagram” E-13

“Pump Station Plan, Section,

and Riser Diagram”

E-14 “GAC Filter Plan” E-14 “GAC Filter Plan”

E-15 “Pump Station Installation

Details” E-15

“Pump Station Installation

Details”

E-16 “GAC Control Riser Diagram” E-16 “GAC Control Riser Diagram”

E-17 “GAC Power Riser Diagram” E-17 “GAC Power Riser Diagram”

E-18 “GAC Filter Heat Trace

Details” E-18

“GAC Filter Heat Trace

Details”

E-19 “RTU Interface Diagram” E-19 “RTU Interface Diagram”

E-20 “Pump Control Panel

Schematic” E-20

“Pump Control Panel

Schematic”

E-22 “Standard Details – II” E-22 “Standard Details – II”

E-23 “Standard Details – III” E-23 “Standard Details – III”

I-2 “Pump Station P&ID” I-2 “Pump Station P&ID”

I-3 “GAC Filters P&ID – I” I-3 “GAC Filters P&ID – I”

ADDENDUM NO. 3 00 91 13.03 - 3

KER17340 – Water Treatment Plant THM Control Facility

Replace Drawing With Drawing

Drawing No. Drawing Title Drawing No. Drawing Title

I-4 “GAC Filters P&ID – II” I-4 “GAC Filters P&ID – II”

I-5 “Installation Details” I-5 “Installation Details”

END OF ADDENDUM NO. 3

CITY OF KERRVILLE, TEXAS

KERRVILLE WATER TREATMENT PLANT THM CONTROL FACILITY

FNI PROJECT NO. KER17340

JANUARY 28, 2019

ADDENDUM NO. 3

The following additions, deletions, modifications, or clarifications shall be made to the appropriate

sections of the Contract Documents. Acknowledge receipt of this Addendum in the Bid Form submitted

for this Project. Failure to acknowledge receipt of this addendum in the Bid Form may render the Bid as

non-responsive and serve as the basis for rejecting the Bid.

Drawing E-14. Area lighting includes a switch at each lighting pole.

In specification 40 72 00 Level Instrumentation Devices add the following paragraph:

2.03 LEVEL TRANSMITTER - SUBMERSIBLE PRESSURE TYPE

A. Subject to compliance with the Contract Documents, the following Manufacturers are

acceptable:

1. Measurement Specialties MEAS KPSI 705 Submersible Transmitters for hydrostatic Level

2. No Equal

B. The listing of specific manufacturers above does not imply acceptance of their products that

do not meet the specified ratings, features and functions. Manufacturers listed above are

not relieved from meeting these specifications in their entirety.

C. General

1. Type: Measuring level by continuously measuring hydrostatic pressure via its sensing

element, Data is transmitted by an analog, 4 to 20 mA DC output signal.

D. Performance Requirements:

1. Accuracy: ±0.25 percent full scale.

2. Zero Offset: ±0.50 percent full scale minimum configurable.

3. Span: ±0.50 percent full scale minimum configurable by manufacture.

4. Operating Temperature Ranges: -20 to 60 degrees C.

E. Construction Features:

1. Sensor: Type 316 stainless steel.

2. Housing: Type 316 stainless steel.

3. Cable shall be provided of required length and fully submersible construction.

4. Power supply: 9 to 28 VDC with surge and lightning protection.

5. Electrical Connection: Attached 4-wire, 22AWG Conductors in a shielded cable with

vent tube and polyurethane outer jacket.

In specification section 40 78 00 Panel Mounted Control Devices add the following to paragraph 2.08 A.:

4. Siemens model RD200

In specification 40 61 96 Control Loop Descriptions replace paragraphs 3.02 and 3.03 with the following:

3.02 PUMP STATION

Following loops are associated with the new Pump Station. The Data Flow Systems RTU (PLC as

indicated on the drawings) shall be programmed with the following as described below.

A. Loop 600 Booster Pump Station

1. General: Series of float switches shall be installed as shown in the drawings The Low-

level Float shall be an interlock for both pumps. The pumps shall alternate, and the PLC

shall provide an indication to the OIT which pump is the lead pump.

2. GRANULAR ACTIVATED CARBON (GAC) filtration system permissive based on maximum

flow limits are provided as hardwired signals. These include YL-410 PV-1 and PV-2 IN

series, YL-420 PV-3 and PV-4 in Series, YL-411 PV-1 in Service, YL-412 PV-2 in service, YL-

421 PV-3 in Service and YL-422 PV-4 in service.

a. The maximum flow rate for all CAG units in service shall not be exceeded. By

monitoring these status points the maximum flow can be calculated.

b. The flow meters for each unit are interfaced to the pump control PLC as indicated

on the drawings.

c. If the YL-410 signal is true, then the flow from FI-301 will be the flow for the series

filter units PV-1 and PV-2.

d. If the YL-420 signal is true than the flow FI-303 be the flow for the series filter units

PV-3 and PV-4.

e. The flow through the CAG filters is the total of the in-service units by utilizing flow

meters minus

f. The maximum speed of the pump VFD shall be dynamically caped in automatic

mode to not exceed the max flow rate for the available CAG filters in their current

mode configuration.

3. Field Instruments: The High-Level float shall call for both pumps to run. The High float

shall start the lead pump. When the level reaches the low float, the pump shall stop,

and the pumps shall alternate.

4. Permissive include the level above the low-level float and a good level indication as

measured from the LIT-600 4-20mA signal transmitter.

5. The pump station shall operate pumping capacity to maintain a level setpoint within a

narrow dead-band as entered from the pump station control panel OIT. The VFD’s shall

operate from the minimum speed as determined by the pump curve from the pump

supplier to 100% speed. If the lead pump cannot maintain the level within range and is

operating at greater than 98% for a configurable delay, then the Lag pump shall be

called to run, and both pumps run at near the same speed. If both pumps are running

and the level is below the setpoint for a configurable delay time than the Lead pump

should be called to stop. The Lag becomes the Lead pump.

6. On a weekly basis the Lead shall become Lag and Lag become Lead as at least one pump

will be running continually in normal operation. This rotation will allow for more equal

utilization of pumping equipment.

B. HMI Control and Monitoring

1. This system should be incorporated into the Plant SCADA system as part of the CAG

(GRANULAR ACTIVATED CARBON) Filter System Displays

a. Indications and status as shown within the plans are to be included as a minimum.

3.03 GRANULAR ACTIVATED CARBON (GAC) FILTRATION SYSTEM

A. The CAG filtration system will run autonomously from the plant SCADA and shall be

controlled by the CAG system manufacturer supplied control system. This control panel is to

be installed on the MCC-1 platform as shown on the drawings.

B. Indications and statuses as shown on the plans are to be hardwired from the CAG control

Panel to the Data Flow Systems RTU (PLC as indicated on the drawings) panel as shown.

These signals are to be incorporated into the existing plant SCADA HMI for monitoring and

reporting

1. Individual flow meters are to be displayed and a Filter to Waste flow is to be calculated

within the GAC Manufactures control panel and made available to the plant SCADA

system as a hardwired indication. This signal is to assure all State of Texas reporting

requirements are meet.

2. Calculated signals to indicate in service shall be true when the filter unit is producing

filtered water regardless of parallel or series mode. The arrangement indication for

series mode shall also be made available.

C. The total flow through the CAG filter units shall be balance to the units that are currently in

service. The influent valve shall modulate to control the flow to achieve this balance and

protect the filters against exceeding the maximum flow rate.

The following plan sheets are replaced:

E-4, E-7, E-9, E-11, E-12, E-13, E-14, E-15, E-16, E-17, E-18, E-19, E-20, E-22, E-23, I-2, I-3, I-4, I-5

01/28/2019

AD

DE

ND

UM

NO

. 3

Bid

Fo

rm E

xhib

it ‘

A’

0

0 4

2 2

3.0

1 -

1

KE

R1

73

40

– W

ate

r T

rea

tme

nt

Pla

nt

TH

M C

on

tro

l Fa

cili

ty

00

42

23

.01

B

ID F

OR

M E

XH

IBIT

‘A

WA

TE

R T

RE

AT

ME

NT

PLA

NT

TH

M C

ON

TR

OL

FAC

ILIT

Y B

AS

E B

ID I

TE

MS

Ite

m

No

. D

esc

rip

tio

n

Un

it

Est

ima

ted

Qu

an

tity

U

nit

Pri

ce

Ext

en

de

d A

mo

un

t

1.

For

Mo

bili

zati

on

an

d D

em

ob

iliza

tio

n d

esc

rib

ed

in

the

Co

ntr

act

Do

cum

en

ts f

or

the

lum

p s

um

(Ma

xim

um

5%

of

tota

l co

ntr

act

) o

f:

LS

1

$_

__

__

__

__

__

__

__

__

_

$_

__

__

__

__

__

__

__

__

_

2.

For

de

velo

pm

en

t, d

esi

gn

, a

nd

imp

lem

en

tati

on

of

a

tre

nch

sa

fety

sys

tem

as

req

uir

ed

by

the

Occ

up

ati

on

al S

afe

ty a

nd

He

alt

h A

dm

inis

tra

tio

n a

nd

the

ass

um

pti

on

of

resp

on

sib

ility

fo

r sa

id s

yste

m,

incl

ud

ing

all

req

uir

ed

tre

nch

sa

fety

fo

r a

lte

rna

te b

id

ite

ms,

an

d s

tru

ctu

res,

co

mp

lete

as

spe

cifi

ed

an

d

ind

ica

ted

in t

he

pla

ns.

(C

on

tra

cto

r sh

all

inse

rt

qu

an

tity

of

tre

nch

sa

fety

re

qu

ire

d f

or

the

pro

ject

.

Co

ntr

act

or

sha

ll o

nly

be

pa

id f

or

tre

nch

sa

fety

inst

alle

d.)

LF

__

__

__

__

*1

,10

0

min

imu

m

$_

__

__

__

__

__

__

__

__

_

$_

__

__

__

__

__

__

__

__

_

3.

Furn

ish

, in

sta

ll a

nd

re

mo

ve s

tab

ilize

d c

on

stru

ctio

n

en

tra

nce

(N

ot

all

loca

tio

ns

are

ind

ica

ted

on

th

e

pla

ns)

, co

mp

lete

as

spe

cifi

ed

an

d in

dic

ate

d o

n t

he

pla

ns.

EA

1

$

__

__

__

__

__

__

__

__

__

$

__

__

__

__

__

__

__

__

__

4.

Furn

ish

, in

sta

ll a

nd

re

mo

ve s

ilt f

en

ce/m

ulc

h s

ock

,

(No

t a

ll lo

cati

on

s a

re in

dic

ate

d o

n t

he

pla

ns

an

d w

ill

be

de

term

ine

d d

uri

ng

co

nst

ruct

ion

), c

om

ple

te a

s

spe

cifi

ed

an

d in

dic

ate

d o

n t

he

pla

ns.

LF

1,0

00

$

__

__

__

__

__

__

__

__

__

$

__

__

__

__

__

__

__

__

__

5.

Fu

rnis

h a

nd

inst

all

hyd

rom

ulc

h s

ee

din

g,

com

ple

te a

s

spe

cifi

ed

an

d in

dic

ate

d o

n t

he

pla

ns.

SY

2

,85

2

$_

__

__

__

__

__

__

__

__

_

$_

__

__

__

__

__

__

__

__

_

AD

DE

ND

UM

NO

. 3

Bid

Fo

rm E

xhib

it ‘

A’

0

0 4

2 2

3.0

1 -

2

KE

R1

73

40

– W

ate

r T

rea

tme

nt

Pla

nt

TH

M C

on

tro

l Fa

cili

ty

6.

For

con

stru

ctio

n o

f th

e p

um

p s

tati

on

, in

clu

din

g

inst

alla

tio

n o

f p

um

ps,

pu

mp

dis

cha

rge

pip

ing

to

GA

C

ad

sorp

tio

n s

yste

m,

valv

es,

ga

ug

es,

air

re

lea

se

valv

es,

fit

tin

gs,

sit

e g

rad

ing

, e

xca

vati

on

, b

ack

fill,

we

t

we

ll, a

cce

ss h

atc

h,

coa

tin

g a

nd

pa

inti

ng

, cl

ea

rin

g

an

d g

rub

bin

g,

an

d a

ll o

the

r a

pp

urt

en

an

t w

ork

an

d

ite

ms

no

t sp

eci

fica

lly in

clu

de

d in

oth

er

bid

ite

ms,

com

ple

te a

s sp

eci

fie

d a

nd

ind

ica

ted

in t

he

pla

ns.

LS

1

$_

__

__

__

__

__

__

__

__

_

$_

__

__

__

__

__

__

__

__

_

7.

For

con

stru

ctio

n o

f G

AC

Ad

sorp

tio

n S

yste

ms,

incl

ud

ing

inst

alla

tio

n o

f th

e s

yste

ms,

pip

ing

, va

lve

s,

ga

ug

es,

air

re

lea

se v

alv

es,

fit

tin

gs,

du

ctile

iro

n

pip

ing

wit

hin

5-f

ee

t o

f th

e f

ou

nd

ati

on

, si

te g

rad

ing

,

exc

ava

tio

n,

ba

ckfi

ll, s

lab

str

uct

ura

l co

ncr

ete

, co

ati

ng

an

d p

ain

tin

g,

cle

ari

ng

an

d g

rub

bin

g a

nd

all

oth

er

ap

pu

rte

na

nt

wo

rk,

com

ple

te a

s sp

eci

fie

d a

nd

ind

ica

ted

in t

he

pla

ns.

LS

1

$_

__

__

__

__

__

__

__

__

_

$_

__

__

__

__

__

__

__

__

_

8.

Furn

ish

an

d in

sta

ll b

y o

pe

n c

ut,

24

-in

ch d

uct

ile ir

on

he

ad

er

an

d p

um

p s

tati

on

infl

ue

nt

pip

ing

, in

clu

din

g

be

dd

ing

, b

ack

fill,

te

stin

g,

flo

wa

ble

fill

, fi

ttin

gs

an

d

rest

rain

ts,

site

re

sto

rati

on

, a

nd

all

oth

er

ap

pu

rte

na

nt

wo

rk,

com

ple

te a

s sp

eci

fie

d a

nd

ind

ica

ted

in t

he

pla

ns.

LF

60

$

__

__

__

__

__

__

__

__

__

$

__

__

__

__

__

__

__

__

__

9.

Furn

ish

an

d in

sta

ll b

y o

pe

n c

ut,

18

-in

ch d

uct

ile ir

on

pu

mp

sta

tio

n in

flu

en

t a

nd

eff

lue

nt

line

s, in

clu

din

g

be

dd

ing

, b

ack

fill,

te

stin

g,

flo

wa

ble

fill

, fi

ttin

gs

an

d

rest

rain

ts,

site

re

sto

rati

on

, a

nd

all

oth

er

ap

pu

rte

na

nt

wo

rk,

com

ple

te a

s sp

eci

fie

d a

nd

ind

ica

ted

in t

he

pla

ns.

LF

14

7

$_

__

__

__

__

__

__

__

__

_

$_

__

__

__

__

__

__

__

__

_

AD

DE

ND

UM

NO

. 3

Bid

Fo

rm E

xhib

it ‘

A’

0

0 4

2 2

3.0

1 -

3

KE

R1

73

40

– W

ate

r T

rea

tme

nt

Pla

nt

TH

M C

on

tro

l Fa

cili

ty

10

.

Furn

ish

an

d in

sta

ll b

y o

pe

n c

ut,

12

-in

ch C

-90

0 D

R1

4

PV

C b

ack

wa

sh w

ate

r lin

e,

incl

ud

ing

be

dd

ing

,

ba

ckfi

ll, t

est

ing

, a

sph

alt

ro

ad

wa

y re

pa

ir,

flo

wa

ble

fill

wit

hin

lag

oo

n b

erm

s, f

itti

ng

s a

nd

re

stra

ints

, tr

ee

pro

tect

ion

, si

te r

est

ora

tio

n,

an

d a

ll o

the

r

ap

pu

rte

na

nt

wo

rk,

com

ple

te a

s sp

eci

fie

d a

nd

ind

ica

ted

in t

he

pla

ns.

LF

77

2

$_

__

__

__

__

__

__

__

__

_

$_

__

__

__

__

__

__

__

__

_

11

.

Furn

ish

an

d in

sta

ll 2

4-i

nch

bu

tte

rfly

va

lve

on

pu

mp

sta

tio

n in

flu

en

t lin

e w

ith

be

vel g

ea

r, v

alv

e b

ox,

con

cre

te v

alv

e p

ad

an

d a

ll o

the

r a

pp

urt

en

an

t w

ork

,

com

ple

te a

s sp

eci

fie

d a

nd

ind

ica

ted

in t

he

pla

ns.

EA

1

$

__

__

__

__

__

__

__

__

__

$

__

__

__

__

__

__

__

__

__

12

.

Furn

ish

an

d in

sta

ll 1

8-i

nch

ga

te v

alv

e o

n p

um

p

sta

tio

n in

flu

en

t a

nd

eff

lue

nt

wa

ter

line

s w

ith

be

vel

ge

ar,

va

lve

bo

x, c

on

cre

te v

alv

e p

ad

, a

nd

all

oth

er

ap

pu

rte

na

nt

wo

rk,

com

ple

te a

s sp

eci

fie

d a

nd

ind

ica

ted

in t

he

pla

ns.

EA

2

$

__

__

__

__

__

__

__

__

__

$

__

__

__

__

__

__

__

__

__

13

.

Furn

ish

an

d in

sta

ll 1

2-i

nch

ga

te v

alv

e o

n b

ack

wa

sh

wa

ter

line

, va

lve

bo

x, c

on

cre

te v

alv

e p

ad

, a

nd

all

oth

er

ap

pu

rte

na

nt

wo

rk,

com

ple

te a

s sp

eci

fie

d a

nd

ind

ica

ted

in t

he

pla

ns.

EA

3

$

__

__

__

__

__

__

__

__

__

$

__

__

__

__

__

__

__

__

__

14

.

Furn

ish

an

d in

sta

ll tr

ace

r w

ire

te

st s

tati

on

s,

com

ple

te in

pla

ce a

s sp

eci

fie

d a

nd

ind

ica

ted

in t

he

pla

ns.

EA

4

$

__

__

__

__

__

__

__

__

__

$

__

__

__

__

__

__

__

__

__

AD

DE

ND

UM

NO

. 3

Bid

Fo

rm E

xhib

it ‘

A’

0

0 4

2 2

3.0

1 -

4

KE

R1

73

40

– W

ate

r T

rea

tme

nt

Pla

nt

TH

M C

on

tro

l Fa

cili

ty

15

.

Furn

ish

an

d in

sta

ll 2

4-i

nch

du

ctile

iro

n p

ipe

tie

-in

to

exi

stin

g p

ipin

g a

t cl

ari

fie

r, in

clu

din

g r

em

ovi

ng

exi

stin

g s

tee

l re

du

cer,

inst

alli

ng

pro

po

sed

ste

el

red

uce

r, t

ran

siti

on

co

up

ling

, co

ati

ng

s a

nd

lin

ing

s fo

r

exi

stin

g p

ipin

g,

an

d a

ll a

pp

urt

en

an

t w

ork

, co

mp

lete

as

spe

cifi

ed

an

d in

dic

ate

d o

n t

he

pla

ns.

LS

1

$_

__

__

__

__

__

__

__

__

_

$_

__

__

__

__

__

__

__

__

_

16

.

Furn

ish

an

d in

sta

ll 1

8-i

nch

du

ctile

iro

n p

ipe

tie

-in

to

exi

stin

g p

ipin

g f

rom

pla

nt,

incl

ud

ing

all

ap

pu

rte

na

nt

wo

rk,

com

ple

te a

s sp

eci

fie

d a

nd

ind

ica

ted

on

th

e

pla

ns.

LS

1

$_

__

__

__

__

$

__

__

__

__

__

17

.

Inst

all

con

cre

te o

utf

alls

at

lag

oo

ns,

incl

ud

ing

de

mo

ing

exi

stin

g o

utf

alls

, m

od

ifyi

ng

exi

stin

g p

ipin

g,

an

d a

ll a

pp

urt

en

an

t w

ork

, co

mp

lete

as

spe

cifi

ed

an

d

ind

ica

ted

in t

he

pla

ns.

EA

3

$

__

__

__

__

__

__

__

__

__

$

__

__

__

__

__

__

__

__

__

18

.

Pro

vid

e im

pro

vem

en

ts t

o c

hlo

rin

ati

on

sys

tem

incl

ud

ing

all

pip

ing

, e

qu

ipm

en

t, in

stru

me

nta

tio

n,

vau

lt a

nd

all

ap

pu

rte

na

nt

wo

rk,

com

ple

te a

s

spe

cifi

ed

an

d in

dic

ate

d in

th

e p

lan

s.

LS

1

$_

__

__

__

__

__

__

__

__

_

$_

__

__

__

__

__

__

__

__

_

19

.

Re

con

stru

ct a

sph

alt

pa

vem

en

t a

nd

pro

vid

e

pro

po

sed

pa

vem

en

t, c

om

ple

te a

s sp

eci

fie

d a

nd

ind

ica

ted

in t

he

pla

ns.

SY

1,2

69

$

__

__

__

__

__

__

__

__

__

$

__

__

__

__

__

__

__

__

__

20

.

For

the

inst

alla

tio

n o

f a

ll e

lect

rica

l eq

uip

me

nt,

ligh

tin

g,

con

du

it,

inst

rum

en

tati

on

an

d w

irin

g

imp

rove

me

nts

, a

nd

all

ap

pu

rte

na

nt

wo

rk,

com

ple

te

as

spe

cifi

ed

an

d in

dic

ate

d in

th

e p

lan

s.

LS

1

$_

__

__

__

__

__

__

__

__

_

$_

__

__

__

__

__

__

__

__

_

AD

DE

ND

UM

NO

. 3

Bid

Fo

rm E

xhib

it ‘

A’

0

0 4

2 2

3.0

1 -

5

KE

R1

73

40

– W

ate

r T

rea

tme

nt

Pla

nt

TH

M C

on

tro

l Fa

cili

ty

ALL

OW

AN

CE

IT

EM

S

Ite

m

No

. D

esc

rip

tio

n

Un

it

Est

ima

ted

Qu

an

tity

U

nit

Pri

ce

Ext

en

de

d A

mo

un

t

1.

Allo

wa

nce

fo

r D

ata

Flo

w S

yste

ms,

In

c to

pro

vid

e

SCA

DA

, co

mp

lete

as

spe

cifi

ed

an

d in

dic

ate

d in

th

e

pla

ns.

LS

1

$5

4,3

50

.00

$

54

,35

0.0

0

TO

TA

L B

ID A

MO

UN

T (

BA

SE B

ID I

TE

MS

+ A

LLO

WA

NC

E I

TE

MS

) $

__

__

__

__

__

__

__

__

__

__

EN

D O

F S

EC

TIO

N

ADDENDUM NO. 3

Payment Procedures 01 29 00 - 1

KER17340 – Water Treatment Plant THM Control Facility

01 29 00 PAYMENT PROCEDURES

1.00 GENERAL

1.01 WORK INCLUDED

A. Payments for Work shall conform to the provisions of the General Conditions, the

Supplementary Conditions, the Agreement, and this Section. Apply provisions for payments

in the Section to all Subcontractors and Suppliers.

B. Submit Applications for Payment at the amounts indicated in the Agreement:

1. Amounts for each item in the Agreement shall include but not be limited to cost for:

a. Mobilization, demobilization, cleanup, bonds, and insurance.

b. Professional services including but not limited to engineering and legal fees.

c. The products to be permanently incorporated into the Project.

d. The products consumed during the construction of the Project.

e. The labor and supervision to complete the Project.

f. The equipment, including tools, machinery, and appliances required to complete the

Project.

g. The field and home office administration and overhead costs related directly or

indirectly to the Project.

h. Any and all kinds, amount or class of excavation, backfilling, pumping or drainage,

sheeting, shoring and bracing, disposal of any and all surplus materials, permanent

protection of all overhead, surface or underground structures; removal and

replacement of any poles, conduits, pipelines, fences, appurtenances and

connections, cleaning up, overhead expense, bond, public liability and

compensation and property damage insurance, patent fees, and royalties, risk due

to the elements, and profits, unless otherwise specified.

2. Provide Work not specifically set forth as an individual payment item but required to

provide a complete and functional system. These items are a subsidiary obligation of

the Contractor and are to be included in the Cost of Work.

3. Payment will be made for materials on hand.

a. Store materials properly on Site as herein specified.

1). Payment will be made for the invoice amount less the specified retainage.

2). Provide invoices at the time materials are included on the materials-on-hand

tabulation.

b. Provide documentation of payment for materials-on-hand with the next payment

request. Adjust payment to the amount actually paid if this differs from the invoice

amount. Remove items from the materials on hand tabulation if this

documentation is not provided so payment will not be made.

c. Payment for materials-on-hand is provided for the convenience of the Contractor

and does not constitute acceptance of the product.

ADDENDUM NO. 3

Payment Procedures 01 29 00 - 2

KER17340 – Water Treatment Plant THM Control Facility

4. The Work covered by progress payments becomes the property of the Owner at the

time of payment.

1.02 SCHEDULE OF VALUES AND PAYMENTS

A. Submit a detailed Schedule of Values for the Work to be performed on the project.

1. Submit schedule within 10 days prior to submitting the first Application for Payment.

2. Line items in the Agreement are to be used as line items in the schedule.

3. Payment will be made on the quantity of Work completed per Contract Documents

during the payment period and as measured per this Section.

a. Payment amount is the Work quantity measured multiplied by the unit prices for

that line item in the Agreement.

b. Payment on a unit price basis will not be made for Work outside finished

dimensions shown in the Contract Documents.

c. Partial payments will be made for lump sum line items in the Agreement.

1). Lump sum line items in the Agreement are to be divided into smaller unit prices

to allow more accurate determination of the percentage of the item that has

been completed.

a). Provide adequate detail to allow more accurate determination of the

percentage of Work completed for each item.

b). Provide amounts for items that do not exceed $25,000.00. An exception

may be made for equipment packages that cannot be subdivided into units

or subassemblies.

c). Separate product costs and installation costs.

(1). Product costs include cost for product, delivery and unloading costs,

royalties and patent fees, taxes, and other cost paid directly to the

Subcontractor or Supplier.

(2). Installation costs include cost for the supervision, labor and equipment

for field fabrication, erection, installation, start-up, initial operation and

overhead and profit.

d). Lump sum items may be divided into an estimated number of units.

(1). The estimated number of units times the cost per unit must equal the

lump sum amount for that line item.

(2). Payment will be made for all of the lump sum line item amount.

e). Include a directly proportional amount of overhead and profit for each line

item.

f). Divide principal subcontract amounts into an adequate number of line items

to allow determination of the percentage of Work completed for each item.

2). These line items may be used to establish the value of Work to be added or

deleted from the Project.

ADDENDUM NO. 3

Payment Procedures 01 29 00 - 3

KER17340 – Water Treatment Plant THM Control Facility

3). Correlate line items with other administrative schedules and forms:

a). Progress schedule.

b). List of Subcontractors.

c). Schedule of allowances.

d). Schedule of alternatives.

e). List of products and principal Suppliers.

f). Schedule of Submittals.

4). Costs for mobilization shall be listed as a separate line item and shall be actual

cost for:

a). Bonds and insurance.

b). Transportation and setup for equipment.

c). Transportation and/or erection of all field offices, sheds and storage

facilities.

d). Salaries for preparation of submittals required before the first Application

for Payment.

e). Salaries for field personnel assigned to the Project related to the

mobilization of the Project.

f). Transportation, breakdown/loading, and removal of equipment.

g). Transportation and/or disassembly of all temporary facilities erected for

construction.

(1). Mobilization/demobilization may not exceed 3 percent of the total

Contract amount. Cost for mobilization and demobilization may be

submitted only for Work completed.

5). The sum of all values listed in the schedule must equal the total Contract

amount.

4. Submit a schedule indicating the anticipated schedule of payments to be made by the

Owner. Schedule shall indicate:

a. The Application for Payment number.

b. Date the request is to be submitted.

c. Anticipated amount of payment to be requested.

5. Update the Schedule of Values quarterly or more often if necessary to provide a

reasonably accurate indication of the funds that the Owner will need to have available

to make payment to the Contractor for the Work performed.

B. Provide written approval of the Schedule of Values, Application for Payment form, and

method of payment by the Surety Company providing performance, and bonds prior to

submitting the first Application for Payment. Payment will not be made without this

approval.

ADDENDUM NO. 3

Payment Procedures 01 29 00 - 4

KER17340 – Water Treatment Plant THM Control Facility

1.03 PAYMENT PROCEDURES

A. Submit Applications for Payment per the procedures indicated in Section 01 33 00

“Submittal Procedures.” Submit a Schedule of Values in the Application for Payment format

to be used.

B. Applications for Payment may be submitted on a pre-printed form acceptable to the Owner

and Engineer, or may be generated electronically. Computer generated payment requests

must have the same format and information indicated in the pre-printed form and be

approved by the Engineer.

1. Indicate the total contract amount and the Work completed to date on the Tabulation

of Values for Original Contract Performed.

2. Include only approved Change Order items in the Tabulation of Extra Work on Approved

Change Orders.

3. List all materials on hand that are presented for payment on the Tabulation of Materials

on Hand. Once an item has been entered on the tabulation it is not to be removed.

4. Include the Project Summary Report with each Application for Payment. Data included

in the Project Summary Report are to be taken from the other tabulations. Include a

completed summary as indicated in with each Applications for Payment submitted.

a. Number each application sequentially and indicate the payment period. Revised

Applications for Payment will be resubmitted as A, B, C and so forth to note changes

in content.

b. Show the total amounts for value of original Contract performed, extra Work on

approved Change Orders, and materials on hand on the Project Summary Report.

Show total amounts that correspond to totals indicated on the attached tabulation

for each.

c. Note the number of pages in tabulations in the blank space on the Project Summary

Report to allow a determination that all sheets have been submitted.

d. Execute Contractor’s certification by the Contractor’s agent of authority and

notarize for each Application for Payment.

5. Do not alter the schedule of values and the form for the submission of requests without

the written approval of the Engineer once these have been approved by the Engineer.

6. Final payment requires additional procedures and documentation per Section 01 70 00

“Execution and Closeout Requirements.”

C. Progress payments shall be made as the Work progresses on a monthly basis.

1. End the payment period on the day indicated in the Agreement and submit an

Application for Payment for Work completed and materials received since the end of

the last payment period.

2. At the end of the payment period, submit a draft copy of the Application for Payment

for that month to the Engineer. Agreement is to be reached on:

a. The percentage of Work completed for each lump sum item.

b. The quantity of Work completed for each unit price item.

ADDENDUM NO. 3

Payment Procedures 01 29 00 - 5

KER17340 – Water Treatment Plant THM Control Facility

c. The percentage of Work completed for each approved Change Order item.

d. The amount of materials-on-hand.

3. On the basis of these agreements the Contractor is to prepare a final copy of the

Application for Payment and submit it to the Engineer for approval.

4. The Engineer will review the Application for Payment and if appropriate will recommend

payment of the application to the Owner.

D. Provide a revised and up-to-date Progress Schedules per Section 01 32 16 “Construction

Progress Schedules” with each Application for Payment.

E. Provide project photographs per Section 01 32 34 “Video and Photographic Documentation”

with final Application for Payment.

1.04 ALTERNATES AND ALLOWANCES

Include amounts for specified Allowances for Work in the Agreement in accordance with Section

01 23 10 “Alternates and Allowances.”

1.05 MEASUREMENT PROCEDURES

Measure the Work described in the Agreement for payment, if applicable. Payment will be

made only for the actual measured and/or computed length, area, solid contents, number and

weight, unless otherwise specifically provided. No extra or customary measurements of any kind

will be allowed.

2.00 PRODUCTS (NOT APPLICABLE)

3.00 EXECUTION (NOT APPLICABLE)

END OF SECTION

ADDENDUM NO. 3

High-Performance Coatings 09 96 00.01 - 1

KER17340 – Water Treatment Plant THM Control Facility

09 96 00.01 HIGH-PERFORMANCE COATINGS

1.00 GENERAL

1.01 WORK INCLUDED

A. Furnish labor, materials, equipment and incidentals necessary to apply protective coatings

to material and equipment as specified herein, including the preparation of surfaces prior to

application of coatings.

B. Protective coatings must be applied to the following surfaces:

1. Metal surfaces located outside of buildings and other structures anywhere on the Site.

2. Proposed piping.

3. Existing piping and valves located in proposed chlorine injection vault.

C. The following shall not be coated and shall be protected from drips, overspray, etc. unless

indicated otherwise

1. Stainless steel piping, materials and equipment

2. Galvanized steel piping, materials and equipment unless specifically indicated to be

coated.

3. Aluminum materials and equipment

4. Interior electrical items

D. Special applications for painting include the following:

1. Buried pipe and valves shall receive a shop applied protective coating as described in

the appropriate Section of the Specifications.

2. Existing and proposed steel piping linings and coatings.

E. Special applications for painting include the following:

1. Aluminum surfaces in contact with or embedded in concrete shall be treated in

accordance with Section 03 30 00 “Cast-In-Place Concrete.”

2. Buried pipe and valves shall receive a shop applied protective coating as described in

the appropriate Section of the Specifications.

F. Contain, treat, and dispose of any dust, spray, drainage, or spillage resulting from coating

operations. It shall be the Contractor’s responsibility to determine if the materials to be

disposed of are classified as Hazardous Waste. Disposed of waste, hazardous or otherwise,

shall be in accordance with applicable regulations. The Contractor shall be aware of and

understand the regulations concerning disposal of waste generated by coating operations.

1.02 QUALITY ASSURANCE

A. Acceptable Manufacturers: Products which comply with the Contract Documents and are

manufactured by the following companies will be acceptable:

1. Tnemec Company, Inc.

2. Carboline.

ADDENDUM NO. 3

High-Performance Coatings 09 96 00.01 - 2

KER17340 – Water Treatment Plant THM Control Facility

3. PPG Protective & Marine Coatings.

4. The Sherwin-Williams Company.

5. Akzo Nobel / International Paint, LLC.

6. ICI Devoe High Performance Coatings.

7. Plasite Protective Coatings.

B. It is desired that the paint products be furnished by as few manufacturers as possible to

meet the requirements of the Specifications. Coating products of the same type shall be

supplied by the same manufacturer. Do not mix products from different sources.

C. Applicator’s Qualifications: Applicators must be qualified in this line of work and have a

minimum of 5 years of experience in the application of the protective coatings of the types

specified herein. Submit a list of recent projects and names of references for those projects.

D. Product Quality:

1. Use only the coatings specified in this Section. Use only those thinners and solvents

recommended by the manufacturer, only in the amounts necessary to produce the

manufacturer’s recommended spreading rate, and in amounts not exceeding the

maximum quantities stated in the manufacturer’s literature.

2. The coating material shall not show excessive settling in a freshly opened full can and

shall be easily re-dispersed with a paddle to a smooth, homogeneous state. It shall

show no curdling, livering, caking, or color separation and shall be free of lumps or skim

surfaces.

E. Inspection:

1. Inspect and provide substrate surfaces prepared in accordance with the Contract

Documents and the printed directions and recommendations of paint manufacturer

whose product is to be applied.

2. Provide Engineer minimum 3 days’ notice prior to start of surface preparation work or

coating application work.

3. Perform Work only in the presence of Engineer, unless Engineer grants prior approval to

perform such Work in Engineer’s absence. Approval to perform Work in the Engineer’s

absence is limited to the current day unless specifically noted to extend beyond the

completion of the work day.

4. Inspection by the Engineer, or the waiver of inspection of any particular portion of the

Work, shall not be construed to relieve the Contractor of responsibility to perform the

Work in accordance with the Contract Documents.

5. The Contractor shall be solely responsible for testing for this Section, at no further cost

to the Owner. The Engineer shall also make such tests if it is considered necessary.

Cooperate with the Engineer, providing equipment, scaffolds, and other equipment as

requested by the Engineer.

ADDENDUM NO. 3

High-Performance Coatings 09 96 00.01 - 3

KER17340 – Water Treatment Plant THM Control Facility

F. Testing Equipment: Furnish the testing apparatus necessary for testing coatings, including

the following:

1. One set of U.S. Department of Commerce thickness calibration plates, certified by the

National Bureau of Standards, to test dry film thickness.

2. Wet-film thickness gauges. Give one to Owner’s representative. Each painter must

keep one to test paint as it is applied.

3. One electronic dry-film thickness gauge capable or measuring 0-200 mils with

calibration standards approved by the Bureau of Standards.

4. One Elcometer 319 Dewpoint Meter.

5. One Tinker and Rasor Model M 1 Holiday Detector and recommended wetting agent

and/or High Voltage Holiday Detector if required for interior coating thickness specified.

6. One set of SSPC VIS 1, 3 and 4 - Visual Standards as applicable.

G. Testing Reports: Submit an inspection report for each coating applied on the Project. The

testing report shall be completed on a form furnished by the Engineer and shall bear the

signature of the Contractor and the Owner’s representative.

1.03 SUBMITTALS

A. Submittals must be in accordance with Section 01 33 00 “Document Management.”

B. The following Product Data for products, including manufacturer’s data sheets, are due prior

to ordering coating and surface preparation materials:

1. Coating manufacturer’s color selection literature for coating materials and caulk.

2. Sample warranty document for products.

3. Provide certification from the manufacturer that all coatings will not contain more than

0.06 percent by weight of lead in the cured coating for each coat applied.

4. Coating manufacturer’s Product Information and Safety Data Sheets (SDS) for each

coating and caulk material. Product Information must include the following:

a. The manufacturer’s published instructions for use in specifying and applying all

proposed coatings.

b. Application instructions written and published by the coating manufacturer.

c. All limitations, precautions and requirements that may adversely affect the coating,

that may cause unsatisfactory results after the application or that may cause the

coating not to serve the purpose for which it was intended, must be clearly and

completely stated in the instructions. Limitations and requirements must include,

but are not necessarily limited to the following:

1). Surface preparation.

2). Method(s) of application.

3). Thickness of each coat (maximum and minimum DFT).

4). Drying and curing time of each coat.

ADDENDUM NO. 3

High-Performance Coatings 09 96 00.01 - 4

KER17340 – Water Treatment Plant THM Control Facility

5). Time (minimum and maximum) allowed between coats.

6). Thinner and use of thinner.

7). Proper mixing of coating before application.

8). Weather limitations during and after application (temperature and humidity,

time weighted).

9). Physical properties of coating, including percent solids content by volume.

10). Equipment settings (air cap, fluid tip, equipment pressure settings, etc.).

11). Pot life at various temperature and humidity conditions.

12). Provide documentation that interior coating system is compatible with the

cathodic protection system.

C. The following samples are required prior to ordering the materials:

Three samples of selected exterior finish colors for approval on 6-inch by 6-inch swatches.

Label each swatch with the manufacturer’s name, coating name/type, color name and

number.

D. The following Product Data is required prior to coating work:

1. Coating Plan:

a. Anticipated coating process schedule by date, including dates when hold-point

inspections are anticipated. Schedule must indicate detailed activities on a daily

basis.

b. Detailed procedures and schedule for all pre-cleaning, surface preparation and

application of coating, including touch-up and repair procedures for all coating

systems.

c. Recoat schedule on the submitted coating materials.

d. Data sheets complete with a graduated scale or curve, produced by the coating

manufacturer, with curing characteristics and recommendations regarding complete

coating curing. The data sheets and scales or curves must include specific cure

times over a wide range of temperatures and humidity.

e. Provide a written plan documenting how spent cleaning debris and/or paint over

spray or droplets will be contained/confined to the Site and tank site during the

surface preparation and coating application operations. Reasonable care must be

exercised by the Contractor to prevent damage, nuisance, or hazardous conditions

to adjacent or nearby property Owners. Include all materials and method to be

used for protection of exterior surfaces, and allow for recovery and disposal of paint

scraps and blast media.

2. Provide documentation on proposed containment system methods for blasting and

coating operations.

3. The Contractor must submit evidence of notification of the appropriate office of the

Texas Commission on Environmental Quality (TCEQ) prior to abrasive blasting as

required. Submit copies of any obtained permits.

ADDENDUM NO. 3

High-Performance Coatings 09 96 00.01 - 5

KER17340 – Water Treatment Plant THM Control Facility

4. Coating Manifest - Within 48 hours of coating delivery to the Site, the Contractor must

record the batch number stamped on each coating container and submit a typed list to

the Owner’s representative. Minimum information required is listed below.

a. Date of delivery to the Site.

b. Name and signature of Superintendent recording the data.

c. List of batch number including corresponding coating identification, color, date of

manufacture and volume of each container.

E. The following Certified Test Report(s) are required prior to coating work:

1. SDS sheets for all abrasive to be used on the Project.

2. Certification and laboratory test results indicating recycled metallic abrasive per SSPC-

AB 2 or 4 and atomic absorption test results.

1.04 STANDARDS

A. The applicable provisions of the following standards shall apply as if written here in their

entirety. Adhere to the latest standards and codes published by the following organizations.

B. In the event of a conflict between the published standards, codes, and this Section, the

more stringent requirement shall govern.

1. ANSI (American National Standards Institute):

ANSI/NSF Standard 61 Drinking Water Components

2. ASTM International (American Society for Testing and Materials):

ASTM D523 Standard Test Method for Specular Gloss

ASTM D610 Standard Test Method for Evaluating Degree of Rusted on Painted

Surfaces

ASTM D2244 Standard Practice for Calculation of Color Tolerances and Color

Differences from Instrumentally Measured Color Coordinates

ASTM D3359 Standard Test Methods for Rating Adhesion by Tape Test

ASTM D4214 Standard Test Methods for Evaluating the Degree of Chalking of

Exterior Paint Films

ASTM D4263 Standard Test Method for Indicating Moisture in Concrete by the

Plastic Sheet Method

ASTM D4285 Standard Test Method of Indicating Oil and Water in Compressed Air

ASTM D4541 Standard Method for Pull-Off Strength of Coatings Testing Adhesion

of Applied Coating Using Portable Adhesion Tester

ASTM D6386 Standard Practice for Preparation of Zinc (Hot-Dip Galvanized)

Coated Iron and Steel Product and Hardware Surfaces for Painting

ASTM E337 Standard Practice Test Method for Measuring Humidity with a

Psychrometer

ASTM F1869 Standard Test Method for Measuring Moisture Vapor Emission Rate

of Concrete Subfloor Using Anhydrous Calcium Chloride

ADDENDUM NO. 3

High-Performance Coatings 09 96 00.01 - 6

KER17340 – Water Treatment Plant THM Control Facility

3. AWWA (American Water Works Association):

AWWA C210 Liquid-Epoxy Coating Systems for Interior and Exterior of Steel

Water Pipelines

AWWA C222 Polyurethane Coatings for the Interior and Exterior of Steel Water

Pipe and Fittings

4. Consumer Product Safety Act, Part 1303.

5. International Concrete Repair Institute (ICRI):

ICRI Technical

Guideline No.

03732

Selecting and Specifying Concrete Surface Preparation for

Coatings, Sealers and Polymer Overlays

6. NACE International (National Association of Corrosion Engineers):

NACE TPC2 Coating and Lining for Immersion Service: Chapter Safety, Chapter

2 Surface Preparation, Chapter 3 Curing, and Chapter 4 Inspection

NACE SP0178

Fabrication Details, Surface Finish Requirements, and Proper

Design Considerations for Tanks and Vessels to be Lined for

Immersion Service

NACE SP0188 Discontinuity (Holiday) Testing of Protective Coatings on

Conductive Substrates

NACE RP0178 Plastic Weld Comparator

NACE RP0287 Field Measurement of Surface Profile of Abrasive Blast Cleaned

Steel Surfaces Using a Replica Tape

7. National Association of Pipe Fabricators (NAPF):

NAPF 500-03

Surface Preparation Standard for Ductile Iron Pipe and Fittings in

Exposed Locations Receiving Special External Coatings and/or

Special Internal Linings

8. OSHA (Occupational Safety & Health Administration):

1915.35 Standards - 29 CFR Painting

1926.62 Standards - 29 CFR Lead

9. SSPC (Society for Protective Coatings):

SSPC-VIS 1 Guide and Reference Photographs for Steel Surfaces Prepared by

Dry Abrasive Blast Cleaning

SSPC-VIS 3 Guide and Reference Photographs for Steel Surfaces Prepared by

Power and Hand Tool Cleaning

SSPC Vol. 1 Good Painting Practices

SSPC-AB1 Mineral and Slag Abrasives

SSPC-AB2 Cleanliness of Recycled Ferrous Metallic Abrasives

SSPC-AB3 Ferrous Metallic Abrasives

SSPC-AB4 Recyclable Encapsulated Abrasive Media in a Compressible Matrix

ADDENDUM NO. 3

High-Performance Coatings 09 96 00.01 - 7

KER17340 – Water Treatment Plant THM Control Facility

SSPC-SP1 Solvent Cleaning

SSPC-SP2 Hand Tool Cleaning

SSPC-SP3 Power Tool Cleaning

SSPC-SP11 Power Tool Cleaning to Bare Metal

SSPC-PA-1 Shop, Field and Maintenance Painting

SSPC-PA-2 Measurement of Dry Film Thickness with Magnetic Gages

SSPC-PA-3 Guide to Safety in Paint Application

SSPC-Guide 6

(CON)

Guide for Containing Surface Preparation Debris Generated During

Paint Removal Operations

SSPC-Guide 12 Guide for Illumination of Industrial Painting

SSPC-Guide 15 Field Methods for Retrieval and Analysis of Soluble Salts on Steel

and Other Nonporous Substrates

10. SSPC/NACE International Joint Standards:

SSPC-SP5/NACE 1 White Metal Blast Cleaning

SSPC-SP6/NACE 3 Commercial Blast Cleaning

SSPC-SP7/NACE 4 Brush - Off Blast Cleaning

SSPC-SP10/NACE 2 Near - White Metal Blast Cleaning

SSPC-SP13/NACE 6 Surface Preparation of Concrete

11. Texas Commission on Environmental Quality (TCEQ):

30 TAC Chapter

290 Subchapter D Rules and Regulations for Public Water Systems

1.05 DELIVERY AND STORAGE

A. Deliver coating products to the Site in original unopened containers, with manufacturer’s

label and batch number attached. Do not apply products until the Owner’s field

representative has approved the product for use.

B. Use one location at each site for the storage of coating products. Protect the floor from

spills and other damage. Protect the products from extreme heat or cold. Keep containers

covered. Keep the storage rooms clean of trash and debris. Dispose of oily or used rags

daily. Under no circumstances shall they be allowed to accumulate. Take precautions to

prevent fires. The storage of flammable liquids shall comply with the City, State, or other

fire codes.

C. Storage of coatings and other products must be in accordance with the manufacturer’s

requirements. Coatings that have been damage or not stored properly must not be applied

and must be removed from the Site.

D. All products and coatings that are not approved for the Project must be removed from the

Site and must not be stored at the Site.

ADDENDUM NO. 3

High-Performance Coatings 09 96 00.01 - 8

KER17340 – Water Treatment Plant THM Control Facility

E. All materials must be delivered to the Site in original sealed containers with the date of

manufacture and batch number stamped thereon by the coating manufacturer. Materials

shall be subject to random observations by the Owner’s representative at the Site.

1.06 ENVIRONMENTAL CONDITIONS

A. Do not apply coatings under conditions that are unsuitable for the production of good

results. Remove trash and debris from enclosed buildings and thoroughly clean prior to

application of coatings. Do not begin application of coatings in areas where other trades are

working, or where construction activities result in airborne dust or other debris. Do not

apply coatings in conditions which do not conform to the recommendations of the coatings

manufacturer.

B. Coatings shall only be applied when conditions fall within the parameters listed in the

manufacturer’s printed data.

C. Contractor shall provide dehumidification equipment sized to maintain dew point

temperature 5 F or more below surface temperature of metal surfaces to be cleaned and

painted.

D. Do not apply any coatings when weather conditions are unfavorable. In the event that

climatic conditions are not conducive for best results, postpone application of coatings until

conditions conform to the manufacturer’s recommendations and the provisions of this

Section.

E. Do not apply coatings to a wet or damp surface in wet or damp weather conditions, or when

there is dust in the air. Surfaces exposed to direct sunlight must be shaded by awnings or

other protective devices while coatings are being applied, if recommended by coating

manufacturer. When necessary, provide temporary heating devices of a type that produces

no fumes which will discolor the paint system.

F. Heating and Dehumidification:

1. Dehumidification equipment must be used to control the environment during surface

preparation, rehabilitation, coating application and coating curing at no additional cost

to the Owner, if acceptable environmental conditions cannot be met.

2. If the Contractor cannot meet the required environmental conditions to apply the

interior coating system per this Section and the coating manufacturer’s written

recommendations, Contractor will cease operations until approved dehumidification

equipment has been provided and acceptable environmental conditions are achieved.

3. If coating system is applied without dehumidification or in conditions not acceptable by

this Section and by the coating manufacturer’s written requirements, Contractor must

fully remove coating system applied and replace per the Engineer’s direction.

4. The Contractor must furnish all labor, materials, equipment, fabrication and quality

control inspections, and all other incidentals required to control and maintain the

environment of the reservoir within the parameters stated in this Section and must

incorporate these and any other expenses into its bid.

5. The Owner reserves the rights, in the event the dehumidification equipment is not

performing to the minimum requirements stated in this Section, to require the

ADDENDUM NO. 3

High-Performance Coatings 09 96 00.01 - 9

KER17340 – Water Treatment Plant THM Control Facility

Contractor to modify and or add additional equipment to satisfy the conditions of this

Section, at the sole cost to the Contractor.

6. It is the Contractor’s responsibility to provide adequate dehumidification equipment to

meet the requirements of this Section and coating manufacturer’s requirements. The

coating manufacturer’s limits of surface temperature, tank inside air temperature and

relative humidity requirements will govern, if more stringent than the requirements

stated within this Section.

G. Forced Ventilation:

1. Provide continuous forced fresh air ventilation when working inside of containment

systems or enclosed areas that are not openly vented from the beginning of surface

preparation through final coating operations and coating curing.

2. Forced ventilation must be supplied per the recoat time required by the coating

manufacturer and at least 48 hours after the final coat has been applied.

3. From the beginning of interior wet and/or dry coating application and until this coating

is cured, the Contractor must monitor the air for the lower explosion limit (LEL) as

published in the coating manufacturer’s product SDS’s.

4. Contractor is responsible for supplying, installing and maintaining the forced ventilation

system.

H. Containment System:

1. Contractor must provide containment methods, either full or partial, which allows for

the containment of the environmentally sensitive waste, dust and paint over spray that

will be generated during the abrasive blasting and painting operation.

2. The ground surrounding the project area must be protected from all debris, emissions,

dust, and other materials generated in the cleaning operations with a minimum of two

layers of polyethylene covered with plywood or the same material used for the

perimeter containment system.

3. Containment is not required when blasting on the interior of a completely enclosed area

(i.e. roof is in place) as long as no visible emissions are created.

4. The Contractor must ensure that no spent cleaning/blasting debris, dust, overspray,

coating droplets, or emissions of any kind, escape to the atmosphere, or to adjacent

buildings, private property, work sites, parking lots, etc.

5. The Owner reserves the right to stop Work or require containment, additional

containment or different containment methods if the Contractor’s operations create a

nuisance beyond the tank site property line in the sole opinion of the Owner, the

Engineer, the Owner’s representative, any regulatory agency, or neighbor. All costs of

providing an adequate containment system must be included by the Contractor in the

Base Bid.

6. The Contractor must be responsible for all materials that are used and for any apparatus

used to contain dust emissions, debris, overspray, and coating droplets. The

containment system attachments to existing or proposed structures must be designed

not to impose excessive loading on the structure by a professional engineer licensed in

ADDENDUM NO. 3

High-Performance Coatings 09 96 00.01 - 10

KER17340 – Water Treatment Plant THM Control Facility

the state the Project is located. Contractor must submit the designed and sealed details

of the containment system on the tank.

7. Any damage to the structure(s) as a direct or indirect result of the containment system

must be repaired or sections replaced by the Contractor at no additional cost to the

Owner. Neither the Owner nor the Owner’s Engineer assumes any responsibility for the

structural ability of the structure to support the containment system.

8. If tarps are used as part of the containment system, the tarps must be an impervious,

solid, flame-resistant material, reinforced with a fiber mesh and must allow as much

light as possible to pass through the material.

I. Visible Emissions:

1. Contractor must control visible emissions and releases while dust producing activities

are underway.

2. Visible emissions more than SSPC Guide 6, Level 1 (1 percent of the workday or 5

minutes in an 8-hour shift) are unacceptable. Sustained emissions of more than 1

minute, regardless of the total time of emissions for the day is unacceptable. If

unacceptable emissions are observed, Contractor must shut down immediately and

correct the situation and clean up any debris generated from the release to the

satisfaction of the Engineer before continuing the Work.

1.07 WORKING CONDITIONS

A. Provide adequate lighting at any location that coatings are being applied or testing is

performed. Illumination shall be of sufficient intensity to achieve good results. Provide

explosion-proof lighting when required.

B. Temporary ladders and scaffolds shall conform to applicable safety requirements. Erect

temporary scaffolds where needed to cover large areas. Provide ladders or scaffolding

during testing procedures.

1.08 GUARANTEES

A. Protective coating shall be guaranteed for a period of 1-year from the date of the Owner’s

acceptance of the Project.

B. A warranty inspection must be conducted prior to the end of the warranty period. Any

Defective Work discovered at this date must be corrected by the Contractor in accordance

with the Contract Documents at no additional cost to the Owner.

2.00 PRODUCTS

2.01 GENERAL COATING REQUIREMENTS

A. All coatings must be free of heavy metals such as arsenic, barium, chromium, selenium,

silver, lead, mercury and cadmium.

B. All coatings in contact with potable water must be certified by the National Sanitation

Foundation (NSF), Standard 61.

ADDENDUM NO. 3

High-Performance Coatings 09 96 00.01 - 11

KER17340 – Water Treatment Plant THM Control Facility

C. No coating submitted or used on this Project may have a VOC (volatile organic content) in

excess of 360 grams/liter or 3.0 lb./gal.

D. Finish coatings must be from the same batch.

2.02 MATERIALS

A. Materials shall be the manufacturer’s top of line quality products, as listed herein. Products

used on this Project shall be as indicated below. Products shall be as follows:

Type A - Alkyd-Phenolic Universal Primer

Manufacturer Approved Coating

Tnemec Series 1 Purple Prime

Sherwin-Williams Kem Kromik Universal

Akzo Nobel /

International Paint, LLC Interlac 573

Devoe Coatings Devprime 1403

Carboline Carbocoat 150UP

PPG Multiprime 4160

Type B - Epoxy-Polyamide Primer

Manufacturer Approved Coating

Tnemec Series 66

Sherwin-Williams Copoxy Primer

Akzo Nobel /

International Paint, LLC

Intergard 251; Intergard 269 for valves and gates, submerged

structural steel and misc. metals, and submerged piping

Devoe Coatings Devran 201V Series

Carboline 890

PPG Amercoat One Single Component Epoxy for valves and gates,

structural steel and misc. metals, and piping

Type C – Alkyd Enamel

Manufacturer Approved Coating

Tnemec Series 23 Enduratone

Sherwin-Williams DTM Alkyd Enamel

Akzo Nobel /

International Paint, LLC Interlac 665

Devoe Coatings Devlac 1431

Carboline Carbocoat 8225

PPG Fast Dry 35

ADDENDUM NO. 3

High-Performance Coatings 09 96 00.01 - 12

KER17340 – Water Treatment Plant THM Control Facility

Type D - Epoxy-Polyamide Coatings

Manufacturer Approved Coating

Tnemec Series 66

Sherwin-Williams Macropoxy 646 Epoxy

Akzo Nobel /

International Paint, LLC

Intergurd 475HS; Interseal 670HS for valves and gates, PVC

pipe and conduit, submerged structural steel and misc.

metals, and submerged piping

Devoe Coatings Bar-Rust 235

Carboline Carboguard 60

PPG Amercoat One for valves and gates, PVC pipe and conduit,

structural steel and misc. metals, and piping

Type E - Epoxy-Polyamide Coatings for Potable Water

Manufacturer Approved Coating

Tnemec Series N140 Pota-Pox Plus

Sherwin-Williams Tank Clad Epoxy

Akzo Nobel /

International Paint, LLC Interline 850 or Interseal 670HS (NSF colors)

Devoe Coatings Bar-Rust 233H Series

Carboline Carboguard 61

PPG Amerlock 2/400

Type F - Aliphatic Polyurethane Enamel

Manufacturer Approved Coating

Tnemec Series 1074 Endura-Shield II

Sherwin-Williams Hi-Solids Polyurethane

Akzo Nobel /

International Paint, LLC Interthane 990 Series

Devoe Coatings Devthane 379 Series

Carboline Carbothane 133HB (Satin) or Carbothane 134HG (High Gloss)

PPG PSX One Single Component Polysiloxane- No Isocyanates

ADDENDUM NO. 3

High-Performance Coatings 09 96 00.01 - 13

KER17340 – Water Treatment Plant THM Control Facility

Type G - Silicone Aluminum Coatings For High Temperature

Manufacturer Approved Coating

Tnemec Series 39 Silicon Aluminum

Sherwin-Williams Silver Brite Aluminum B59S8

Akzo Nobel /

International Paint, LLC Intertherm 50 Series

Devoe Coatings Intertherm 50 Series

PPG Amercoat 878 Aluminum

Carboline Carbozinc 11; Finish: Thermaline 4700 Series (up to 1000⁰F);

Thermaline 4900 (up to 450⁰F)

Type H- Epoxy Concrete Coating

Manufacturer Approved Coating

Tnemec Series 64H-413 Hi-Build Tneme-Tar

Sherwin-Williams Tar Guard Epoxy

Akzo Nobel /

International Paint, LLC Interzone 954

Devoe Coatings Devtar 5A Series

PPG Amercoat 78HB Coal Tar Epoxy

Carboline Bitumastic 300M

Type I - Epoxy Concrete Coating – HFS

Manufacturer Approved Coating

Tnemec Series 434/435 Perma-Shield System

Akzo Nobel /

International Paint, LLC Ceilcote 380/242GF Flakeline System

PPG Amercoat 100A

Carboline Carboguard 510 Series / Plasite 4500 Series

Type J - Inorganic Zinc Primer

Manufacturer Approved Coating

Carboline Carbozinc 859

Sherwin-Williams Corothane I Galvapac

PPG Amercoat 68HS

Approved Manufacturer Approved Equal

ADDENDUM NO. 3

High-Performance Coatings 09 96 00.01 - 14

KER17340 – Water Treatment Plant THM Control Facility

Type K - High Solids Epoxy Siloxane

Manufacturer Approved Coating

Carboline Carboxane 2000

Sherwin-Williams Polysiloxane XLE-80

PPG PSX 700 Polysiloxane

Approved Manufacturer Approved Equal

Type L - Epoxy Mastic

Manufacturer Approved Coating

Carboline Carbomastic 15

Sherwin-Williams Epoxy Mastic II

PPG Amerlock 2/400 AL

Tnemec Chembuild Series 135

AkzoNobel/International

Paint, LLC Interseal 670HS

Type M – Elastomeric Polyurethane Hybrid

Manufacturer Approved Coating

Carboline Reactamine 760 Series

Sherwin-Williams Sherflex S

PPG Amerthane 490

Tnemec Elasto-Shield Series 406

AkzoNobel/International

Paint, LLC Polibrid 705E Elastomeric

Type N – Glass Flake Reinforced Epoxy

Manufacturer Approved Coating

Carboline Approved Equal

Sherwin-Williams Sher-Glass FF

PPG Approved Equal

Tnemec Approved Equal

AkzoNobel/International

Paint, LLC Approved Equal

ADDENDUM NO. 3

High-Performance Coatings 09 96 00.01 - 15

KER17340 – Water Treatment Plant THM Control Facility

Type M - Organic Zinc Primer

Manufacturer Approved Coating

Carboline Carbozinc 859

Sherwin-Williams Corothane I Galvapac

PPG Approved Equal

Tnemec Approved Equal

AkzoNobel/International

Paint, LLC Interzinc 52

Type N – Penetrating Epoxy Pre-Primer

Manufacturer Approved Coating

Carboline Rustbond Penetrating Sealer

Sherwin-Williams Macropoxy 920 Pre-Prime

PPG Approved Equal

Tnemec Approved Equal

AkzoNobel/International

Paint, LLC Interbond 600

2.03 COLOR SELECTION

A. The color chart shall include the complete available range of colors, including tints and

shades. The Owner shall select the colors.

B. Use a multi-color system coating for any surface receiving more than one coat. Each coat

shall be tinted differently from the preceding coat in a manner that will allow the various

coats to be easily distinguished. Colors shall generally be from light to dark shades, but the

Contractor may have the option to select tint shades to insure coats will receive adequate

coverage without bleeding or otherwise showing through the preceding coat.

C. Piping and equipment shall be color coded in accordance with the requirements of the

TCEQ.

3.00 EXECUTION

3.01 GENERAL

A. All coatings must be applied in strict conformance with the coating manufacturer’s

published specifications, this Section, or as approved by the Engineer.

B. Surfaces which will be inaccessible after installation shall be coated prior to installation, or

shall be coated and approved in stages as the Work is installed.

C. The Engineer shall approve surfaces for application of coatings at each stage. Any material

that is coated prior to the Engineer’s approval shall be stripped back to bear metal and

repainted.

ADDENDUM NO. 3

High-Performance Coatings 09 96 00.01 - 16

KER17340 – Water Treatment Plant THM Control Facility

D. At least 7 days or as required by the coating manufacturer, must be allowed for drying of

finished surfaces before any machinery can be placed into service.

E. The number of coats called for in this Section are considered the minimum required. If

more coats are required for complete coverage and uniform appearance they shall be

provided at no additional cost to the Owner.

3.02 STEEL SURFACE PREPARATION

A. The adequacy of the preparation of steel surfaces will be determined by comparing the

surface with SSPC VIS 1 “Pictorial Surface Preparation Standards for Painting Steel Surfaces”

and SSPC VIS 3 “Guide and Reference Photographs for Steel Surfaces Prepared by Power and

Hand Tool Cleaning.” Prepare surfaces in accordance with the following requirements:

1. SSPC-SP1 “Solvent Cleaning”

2. SSPC-SP2 “Hand Tool Cleaning”

3. SSPC-SP3 “Power Tool Cleaning”

4. SSPC-SP5 / NACE 1 “White Metal Blast Cleaning”

5. SSPC-SP6 / NACE 3 “Commercial Blast Cleaning”

6. SSPC-SP7 / NACE 4 “Brush-Off Blast Cleaning”

7. SSPC-SP10 / NACE 2 “Near-White Blast Cleaning”

8. SSPC-SP11 “Power Tool Cleaning to Bare Metal”

B. The resulting surface profile must be in accordance with the coating manufacturer’s

recommendations.

C. All surface preparation of new equipment and surfaces shall be assumed to be on a SSPC

Grade A steel surface condition, unless specifically noted otherwise.

D. “Solvent Cleaning” must be performed prior to subsequent surface preparation, including

abrasive blast cleaning.

E. All sharp edges and welds must be ground smooth to a rounded contour and all weld

splatter must be removed prior to abrasive blasting. Edges of metal to be coated must be

rounded to a minimum of 1/16-inch radius of chamfered a minimum of 1/16 inch at an

angle of 45 degrees.

F. Welds and adjacent areas:

1. Prepared such that there is:

a. No undercutting or reverse ridges on the weld bead.

b. No weld spatter on or adjacent to the weld or any other area to be painted.

c. No sharp peaks or ridges along the weld bead.

d. Grind embedded pieces of electrode or wire flush with the adjacent surface of the

weld bead.

2. Weld profiles must conform to NACE RP0178, Profile ‘D’.

ADDENDUM NO. 3

High-Performance Coatings 09 96 00.01 - 17

KER17340 – Water Treatment Plant THM Control Facility

3.03 DUCTILE IRON PIPE AND FITTINGS SURFACE PREPARATION

A. Prepare surfaces in accordance with the following requirements:

1. NAPF 500-03-01 “Solvent Cleaning”

2. NAPF 500-03-02 “Hand Tool Cleaning”

3. NAPF 500-03-03 “Power Tool Cleaning”

4. NAPF 500-03-04 “Abrasive Blast Cleaning for Ductile Iron Pipe”

5. NAPF 500-03-05 “Abrasive Blast Cleaning for Cast Ductile Iron Fittings”

B. “Solvent Cleaning” must be performed prior to subsequent surface preparation as specified

in NAPF 500-03.

3.04 CONCRETE SURFACE PREPARATION

A. The adequacy of the preparation of concrete surfaces will be determined by comparing the

surface with ICRI Surface Finish Comparators. Prepare surfaces in accordance with the

following requirements:

SSPC-SP13 / NACE 6 – Surface Preparation of Concrete

B. Allow a minimum of 28 days curing time to elapse before coatings are applied. Concrete

surfaces which are scheduled to receive coatings must be in accordance with the coating

manufacturer’s moisture requirements.

C. Bug holes, air pockets, and other voids in the concrete will be filled or patched in chemical

exposure areas, secondary containment, and where specifically required.

D. Concrete Surface Preparation Inspection:

1. Adhesion Testing:

a. Tensile testing of the surface preparation shall be performed by the Engineer as

necessary using Type 4 or Type 5 pneumatic adhesion testing equipment in

accordance with ASTM D4541 using 2-inch diameter dollies for concrete surface

adhesion testing.

b. Concrete surface or applied coating shall be scored for concrete adhesion testing.

c. Adhesive failure greater than 50 percent of the dolly surface area shall indicate

inadequate surface preparation.

d. Cohesive failures which results in loss of sound concrete will be acceptable provided

the loss is greater than 50 percent of the dolly surface area.

e. Low adhesion cohesive failures with a thin layer of concrete due to weak concrete

or laitance over 50 percent of the dolly surface will be rejected.

2. Concrete Soundness: Concrete soundness shall be determined using the scratching or

hammer impact methods as defined in SSPC SP-13.

3. Moisture Content: Moisture shall be tested as specified in SSPC SP-13 and in

accordance with ASTM D4263 and ASTM F1869. Moisture content cannot exceed the

moisture content recommended by the coating manufacturer.

ADDENDUM NO. 3

High-Performance Coatings 09 96 00.01 - 18

KER17340 – Water Treatment Plant THM Control Facility

3.05 SURFACE PREPARATION

A. Clean and degrease surfaces prior to abrasive blasting by solvent cleaning as specified using

solvents, detergent/water, emulsions, and steam. Proposed method must be documented

in the coating plan. Contractor must contain and properly dispose of all runoff and debris

from cleaning.

B. If the following conditions exist or are prevalent, surface preparation and coating must be

delayed or postponed until conditions are favorable. Each day’s coating must be completed

in time to permit the film sufficient drying time prior to damage by atmospheric conditions

or changes. No surface preparation shall begin or coating applied:

1. When the surface, air or material is below or above the manufacturer’s printed

instructions.

2. When surfaces are wet or damp.

3. During weather conditions of rain, snow, fog or mist.

4. When the air and steel temperature is less-than or equal to 5 F above the dew point

temperature.

5. If the relative humidity is above 85 percent.

6. When it is expected that the air and/or surface temperature will be below or above the

coating manufacturer’s recommended temperatures within 4 hours after applications of

coating, minimum. Coating manufacturer may require additional time between

application and temperature and weather changes.

C. Shop Surface Preparation:

1. Notify Engineer at least 7 days prior to start of shop blast cleaning to allow for

inspection of the Work during surface preparation and shop application of paints. Work

shall be subject to the Engineer’s approval before shipment to the Site.

2. Items such as structural steel, metal doors and frames, metal louvers, and similar items

as reviewed by the Engineer may be shop prepared and primed. Centrifugal wheel blast

cleaning is an acceptable alternate to shop blast cleaning. Blast clean and prime in

accordance with the Specifications.

3. Prepare surfaces by abrasive blasting as specified and apply shop prime coat. Shop

primed steel plates must not have primer extended within 4 inches along all edges to be

welded. All primer within 4 inches of an area to be welded must be removed prior to

welding. Welding of painted surfaces will not be allowed.

D. All pre-assembled shop primed items must be prepared in accordance with these

specifications and inspected by the Owner’s representative before and after priming.

E. Abrasive Blasting:

1. Prior to extensive abrasive blasting operations, the Contractor must perform a test blast

to verify that the surface cleanliness and profile meet the requirements of these

specifications and meet the coating manufacturer’s requirements for the coating to be

applied. If the test section does not meet the requirements, the Contract must make

changes to the abrasive materials and methods to provide suitable blast.

ADDENDUM NO. 3

High-Performance Coatings 09 96 00.01 - 19

KER17340 – Water Treatment Plant THM Control Facility

2. Abrasive blast only the amount of surface area which can be primed the same day or

before any rust starts to form, whichever occurs first. Areas which are not painted the

same day must be re-blasted on the day the prime coat is applied.

3. Shrouding or recovery of all blast material will be mandatory during all exterior blasting.

4. Contractor must contain all waste and process discharge in accordance with the

accepted methods for the process and materials that are in abatement.

5. Where abrasive blast cleaning will not remove or properly prepare metal surfaces, hand

and/or power tool cleaning must be used to remove such conditions as weld splatter,

laminations and radius-sharp edges. Hand tool or power tool must be used on areas

less than 2 feet in diameter or smaller or on corners and edges.

6. All abrasive blast equipment must be equipped with, including but not limited to the

following:

a. Noise reducing devices.

b. Hose coupling safety devices.

c. Electrical grounding devices.

d. Moisture traps and filters.

e. Fresh air hoods for all blasters.

f. “Dead Man” switches on all blast hoses.

g. Air Dryers.

F. Surface profile must be in accordance with manufacturer’s printed requirements.

G. The adequacy of the preparation of surfaces must be determined by comparing the surface

with SSPC VIS 1, SSPC VIS 3, NACE RP0178 and ICRI Surface Finish Comparators.

H. Wherever the words “solvent cleaning”, “hand tool cleaning”, “wire brushing”, or “blast

cleaning”, or similar words of equal intent are used in the Specifications or in paint

manufacturer’s specifications, they shall be understood to refer to the applicable

specifications indicated.

I. Where OSHA or EPA regulations preclude standard abrasive blast cleaning, wet or vacuum-

blasting methods may be required. Coating manufacturers’ recommendations for wet blast

additives and first coat application will apply.

J. Clean surfaces of dust and residual particles from cleaning operations by dry (no oil or water

vapor) air blast cleaning or other method prior to painting. Vacuum clean enclosed areas

and other areas where dust settling is a problem and wiped with a tack cloth.

3.06 PREPARATION OF HOT-DIP GALVANIZED COATED IRON OR STEEL PRODUCTS

A. Remove all soluble and insoluble contaminants. Prepare hot-dip galvanized coated iron and

steel products in accordance with ASTM D6386 and abrasive blast per ASTM D6386 to

achieve an angular anchor profile as required by the coating manufacturer.

B. Contractor is responsible for coordinating with the coating manufacturer to verify

compatibility of the specified coating system with the provided surface preparation.

ADDENDUM NO. 3

High-Performance Coatings 09 96 00.01 - 20

KER17340 – Water Treatment Plant THM Control Facility

3.07 PREPARATION OF EXISTING COATED OR SHOP PRIMED SURFACES

A. General:

1. Factory-applied primers to equipment must be those specified or verified by the

Contractor to be compatible with the specified coating systems. Where possible, notify

manufacturers which shop prime coats will be required in order to be compatible with

field-applied finish coats.

2. Where equipment is purchased which has the manufacturer’s standard primer or a

factory finish which is other than as specified in this Section, remove the factory-applied

paint system or apply passivators or other special coatings as required to make the

surface compatible with the finish coat specified.

3. Do not apply any coating to machinery, piping, or other surfaces before testing has been

completed and systems approved. Any damage to coatings resulting from subsequent

corrective procedures shall be stripped back to bare metal and repainted with the

appropriate paint system as directed by the Engineer.

4. Check for compatibility when applying coatings over existing coatings. Apply a test

patch of the recommended coating system, covering at least 2 to 3 square feet or as

directed by the Engineer. Allow to cure 1 week before testing adhesion per ASTM

D3359 in the presence of the Engineer. If adhesion does not meet the manufacturer’s

published data, consult with the Engineer.

5. Shop primed or coated surfaces shall be reviewed with the Engineer to determine if the

extent of damage to the coating and suitability of finish coats to adhere to shop applied

coats.

6. If a cured epoxy, polyurethane, or plural-component material is to be top coated

provide brush-off blast as specified herein or as recommended by the coating

manufacturer.

7. Surface preparation recommendations of coating manufacturer shall be subject to

approval of the Engineer.

B. To be Recoated or Final Coated:

1. Solvent clean.

2. Perform touch-up repairs of existing coating.

3. Asphaltic coated ductile iron pipe will require an application of a seal coat prior to the

application of a cosmetic finish coat.

C. Touch-Up Repairs:

1. Clean loose, abraded, or damaged coatings to substrate by power tool to bare metal per

SSPC-SP11 and/or NAPF 500-03-03 “Power Tool Cleaning.”

2. Feather surrounding intact coating.

3. Apply one spot coat of the specified primer to bare areas overlapping the prepared

existing coating.

4. Apply one full finish coat of the specified primer or finish coat(s) overall.

ADDENDUM NO. 3

High-Performance Coatings 09 96 00.01 - 21

KER17340 – Water Treatment Plant THM Control Facility

D. Application of a Cosmetic Coat:

1. The exact nature of shop-applied coatings is not known in all cases.

2. Check compatibility by application to a small area prior to starting the coating.

3. If lifting or other problems occur, request disposition from the Engineer.

3.08 APPLICATION

A. After abrasive blast cleaning, dust and spent abrasive must be removed from the surfaces by

air blasting and brush sweeping. The prime coat must be applied as soon as possible after

the blasting and surface cleaning is completed, inspected and approved by the Inspector.

B. Blasted surfaces must be coated before rust forms on the surface. No prepared surface will

be allowed to receive a coating if “rust bloom” or surface discoloration has occurred. All

blasted surfaces must be coated to within 6 inches of the edge of a blasted area. No visible

rust must be coated under any circumstances, including rust bloom or if discoloration has

occurred, regardless of elapsed time between blasting and coating.

C. Provide mist coat if recommended by the coating manufacturer.

D. All weld seams, gaps, edges, bolts and difficult areas to coat must receive a stripe coat.

Stripe coat must be a contrasting color.

E. The Contractor must apply each coat at the rate and in the manner specified by the coating

manufacturer, except as may be modified herein. If material has thickened or must be

diluted for application, coating must be built up to the same dry film thickness as specified

for each coat of the complete system.

F. Maximum and minimum DFT must be per the supplied coating manufacturer’s printed

requirements and as required by this Section. DFT will be measured per SSPC-PA 2, Level 2

with an allowable measurement of spot DFT of:

1. Minimum DFT as specified, no less than the minimum specified will be accepted.

2. 120 percent of maximum DFT specified.

G. Contractor and painting technicians are responsible for the application of coating system

and must have current applicator certifications from the coating manufacturer. Submit

certifications with coating submittal.

H. No coating shall be used which has an expired shelf or pot life.

I. Coating must be applied by skilled workmen and must be brushed out or sprayed evenly,

without runs, crazing, sags, or other blemishes.

J. Sand between coats to remove over spray and dry fall.

K. Apply the first coat to the surface, including cutting in around edges, before the second coat

is applied. The second coat and any successive coats must not to be applied before

notifying the Owner’s field representative and obtaining approval. Each coat must be tested

before the successive coat is applied.

L. The coating curing period must be adjusted to compensate for less than adequate weather

conditions, as recommended by the coating manufacturer, for complete curing of the entire

coating system. The full curing time recommended by the manufacturer shall be provided.

ADDENDUM NO. 3

High-Performance Coatings 09 96 00.01 - 22

KER17340 – Water Treatment Plant THM Control Facility

M. Coating must be continuous and must be accomplished in an orderly manner to facilitate

proper inspection control.

N. Where a roller or brush is used to apply the coating, additional coats may be necessary to

achieve the recommended dry film thickness and/or to achieve total coverage of the

underlying surface. Coated surfaces must be totally free of all roller nap, roller marks, brush

bristles and brush marks.

O. When using conventional coating spray equipment for coating operations, effective oil and

water separators combined with after coolers or deliquescent dryers must be used in

compressed air lines to remove detrimental oil and moisture from the air. Separators must

be placed as far as practical from the compressor. Compressors may be tested periodically

by the Owner’s representative for oil and water contamination of compressed air. Testing

must follow ASTM D4285 “Standard Test Method of Indicating Oil and Water in Compressed

Air.” All compressor units found to produce unacceptable amounts of oil and or water, as

determined by results of ASTM D4285 test data and interpretation of data by the Owner’s

representative must be replaced with a compressor that is acceptable.

P. For porous surfaces, such as concrete or masonry, a prime coat may be thinned to provide

maximum penetration and adhesion. The type and amount of thinning must be determined

by the coating manufacturer and is dependent on surface density and type of coating.

3.09 WATER AND WASTEWATER PIPE COLORS

A. General coating colors in accordance with the TCEQ are as follows for general selection of

pipe coatings. Contractor must provide samples for Engineer’s approval prior to ordering as

specified.

Pipe/Pumps/Valves System

Description Color

Backwash Waste/Drain Dark Grey

Clarified Water Green

Effluent after Clarification Dark Green

Filter Effluent Light Blue

Gray Water Purple with Yellow Lettering

Heated Water Blue with 6-inch Red Bands Spaced 30-inches apart

Potable Water/Treated Water Light Blue

Power Conduits In compliance with the National Fire Protection

Association 70 National Electrical Code

Raw Water Tan

Reclaimed Water Purple with Black Lettering

Sewage Grey

Waste Water/Sewage Brown

ADDENDUM NO. 3

High-Performance Coatings 09 96 00.01 - 23

KER17340 – Water Treatment Plant THM Control Facility

Chemical Lines Color

Liquid Alum Yellow w/Orange Bands

Alum (solution) Yellow w/ Green Bands

Ammonia Yellow w/ Brown Bands

Chlorine (gas, liquid, or vent) Yellow

Chlorine (solution) Yellow w/ Red Bands

Chlorine Dioxide (solution) Yellow with Blue Bands

Ferric Chloride Brown with Red Bands

Ferric Sulfate Brown with Yellow Bands

Fluoride White with Yellow Bands

Liquid Caustic White with Red Bands

Caustic (solution) White with Orange Bands

Polymers Orange w/ Green Bands or White with Green Bands

(Varies for Water or WW applications)

Ozone Stainless Steel with White Bands

Settled Water Green

Sulfur Dioxide Lime Green with Yellow Bands

Other Lines Color

Compressed Air Light Green

Instrument Air Light Green with Dark Green Bands

3.10 FIELD QUALITY CONTROL

A. Field Tests: Make wet film tests during painting operations to ensure proper thicknesses of

coating are being applied. After each coat has been applied, test the paint film thickness

with a nondestructive, magnetic type thickness gauge. The total dry-film thickness for each

coat shall not be less than 75 percent of the amount specified. If the thickness is less than

75 percent, apply additional coats until the total specified thickness is obtained. The total

thickness after the final coat has been applied shall be 100 percent of the thickness

specified, minimum. Apply additional coats until the specified thickness is reached or

exceeded.

B. Holiday Testing: Test the entire surface of coated submerged metal structures with a

holiday detector. For thickness between 10 and 20 mils (250 to 500 microns) a non-sudsing

type wetting agent, as recommended by the holiday detector manufacturer shall be added

to the water prior to wetting the detector sponge. Mark and repair pinholes in accordance

with the manufacturer’s printed instructions, then retest pinholes. No pinholes or other

irregularities shall be permitted in the final coats. Areas containing holidays shall receive

additional coats until tests indicate no holidays.

ADDENDUM NO. 3

High-Performance Coatings 09 96 00.01 - 24

KER17340 – Water Treatment Plant THM Control Facility

3.11 PROTECTION OF SURFACES NOT TO BE PAINTED

A. Remove, mask, or otherwise protect hardware, lighting fixtures, switch plates, aluminum

surfaces, machined surfaces, couplings, shafts, bearings, nameplates on machinery, and

other surfaces not intended to be painted.

B. Provide drop cloths to prevent paint materials from falling on or marring adjacent surfaces.

C. Protect working parts of mechanical and electrical equipment from damage during surface

preparation and painting process.

D. Mask openings in motors to prevent paint and other materials from entering the motors.

3.12 DAMAGED COATINGS, PINHOLES, AND HOLIDAYS

A. Feather edges and repaired in accordance with the recommendations of the paint

manufacturer.

B. Repair fusion bonded coatings to be as recommended by the original applicator. Applicator

shall provide liquid repair kits for this purpose as recommended by the coating

manufacturer.

C. Apply finish coats, including touchup and damage-repair coats in a manner that will present

a uniform texture and color-matched appearance.

3.13 UNSATISFACTORY APPLICATION

A. If the item has an improper finish color, or insufficient film thickness, clean and topcoat

surface with specified paint material to obtain the specified color and coverage. Obtain

specific surface preparation information from the coating manufacturer.

B. Hand or power sand visible areas of chipped, peeled, or abraded paint and feather the

edges. Follow with primer and finish coat in accordance with the Specifications. Depending

on the extent of repair and its appearance, a finish sanding and topcoat may be required.

C. Evidence of runs, bridges, shiners, laps, or other imperfections shall be cause for rejection.

D. Repair defects in coating system per written recommendations of coating manufacturer.

E. Leave all staging up until the Engineer has inspected the surface or coating. Replace staging

removed prior to approval by Engineer.

3.14 COATING INSPECTION

A. General:

1. All coats will be subject to inspection by the Engineer and the coating manufacturer’s

representative.

2. Visually inspect concrete, nonferrous metal, plastic, and wood surfaces to ensure proper

and complete coverage has been attained.

3. Give particular attention to edges, angles, flanges, and other areas where insufficient

film thicknesses are likely to be present and ensure proper millage in these areas.

ADDENDUM NO. 3

High-Performance Coatings 09 96 00.01 - 25

KER17340 – Water Treatment Plant THM Control Facility

B. Coating Thickness Testing:

1. Engineer will conduct coating thickness testing as necessary and without limitation.

Testing conformance to the requirements of SSPC PA-2 is specifically excluded from this

Section.

2. Measure coating thickness specified in mils with an electronic type dry film thickness

gauge as specified.

3. Check each coat for the correct millage. Do not make measurement before a minimum

of 8 hours after application of the coating.

4. Tests for concrete coating thickness shall be with a Tooke Gauge, a destructive test.

Contractor shall repair coating after thickness testing.

C. Coating Continuity Testing:

1. Test finish coat, except zinc primer, galvanizing, and elastomeric coatings in excess of 20

mils dry, for holidays and discontinuities with an electrical holiday detector, low voltage,

wet sponge type as specified.

2. Holiday detect coatings in excess of 20 mils dry and concrete and secondary

containment coatings with high voltage units recommended by the coating

manufacturer in accordance with NACE RP0188.

3.15 CLEAN AND ADJUST

A. Promptly remove trash and debris resulting from painting operation from the Site. Remove

drop cloths, masking tapes and other protective coverings. Remove paint spills, splatters,

overlap of paint from adjacent material and other defects. Spot paint nicks and other

defects.

B. Remove paint containers and waste products. Thoroughly clean paint storage rooms,

removing spilled paint from walls and floors.

C. Damages due to over spray on buildings, vehicles, trees, or other surfaces not specified to

be painted would be the responsibility of the Contractor.

3.16 SCHEDULES

Protective coatings shall be applied in accordance with the following paint schedule. If

additional primers, etc. are recommended by the coating manufacturer for any of the coatings

specified, they must be provided at no additional cost to the Owner to provide a complete and

compatible coating system.

AD

DE

ND

UM

NO

. 3

Hig

h-P

erf

orm

an

ce C

oa

tin

gs

0

9 9

6 0

0.0

1 -

26

KE

R1

73

40

– W

ate

r T

rea

tme

nt

Pla

nt

TH

M C

on

tro

l F

aci

lity

PR

OT

EC

TIV

E C

OA

TIN

GS

PA

INT

SC

HE

DU

LE

Sy

ste

m

Ap

pli

cati

on

De

scri

pti

on

S

urf

ace

Pre

p

Pro

du

ct T

yp

e

No

. o

f

Co

ats

DF

T

(mil

s)

No

. 1

Su

bm

erg

ed

Me

tal

– P

ota

ble

Wa

ter

All

me

tal s

urf

ace

s n

ew

an

d e

xist

ing

be

low

a p

lan

e 1

fo

ot

ab

ove

th

e m

axi

mu

m li

qu

id s

urf

ace

, m

eta

l su

rfa

ces

ab

ove

the

ma

xim

um

liq

uid

su

rfa

ce w

hic

h a

re a

pa

rt o

f th

e

imm

ers

ed

eq

uip

me

nt,

co

ncr

ete

em

be

dd

ed

su

rfa

ces

of

me

talli

c it

em

s u

nd

er

sub

me

rge

d o

r b

uri

ed

co

nd

itio

ns,

su

ch

as

wa

ll p

ipe

s, p

ipe

s, w

all

or

flo

or

sle

eve

s, a

cce

ss m

an

ho

les,

ga

te g

uid

es

an

d t

him

ble

s, a

nd

str

uct

ura

l ste

el.

SSP

C-S

P1

SSP

C-S

P1

0

NA

PF

50

0-0

3-0

1

NA

PF

50

0-0

3-0

4

NA

PF

50

0-0

3-0

5

TY

PE

E –

Ep

oxy

-Po

lya

mid

e

TY

PE

E -

Str

ipe

Co

at

TY

PE

E –

Ep

oxy

-Po

lya

mid

e

TY

PE

E –

Ep

oxy

-Po

lya

mid

e

1 2

3

4.0

4.0

4.0

To

tal M

inim

um

Dry

Film

Th

ickn

ess

1

2 m

ils

No

. 2

Ab

ov

e-G

rad

e I

nte

rio

r/E

xte

rio

r S

tee

l a

nd

D.I

. P

ipin

g

No

n-I

mm

ers

ion

/No

n-C

orr

osi

ve

En

vir

on

me

nt

Fie

ld C

oa

ted

All

me

tal s

urf

ace

s n

ew

an

d e

xist

ing

, su

ch a

s in

sid

e p

um

p

sta

tio

n b

uild

ing

s, e

xte

rio

r p

ipin

g a

nd

va

lve

s, e

xte

rio

r

stru

ctu

ral s

tee

l, e

tc.

SSP

C-S

P1

SSP

C-S

P6

NA

PF

50

0-0

3-0

1

NA

PF

50

0-0

3-0

4

NA

PF

50

0-0

3-0

5

TY

PE

M –

Org

an

ic Z

inc

Pri

me

r

TY

PE

D –

Str

ipe

Co

at

TY

PE

D –

Ep

oxy

-Po

lya

mid

e

TY

PE

G –

Acr

ylic

Po

lyu

reth

an

e

En

am

el -

Glo

ss

1 2

3

4.0

4.0

4.0

To

tal M

inim

um

Dry

Film

Th

ickn

ess

1

2 m

ils

No

. 3

Ab

ov

e-G

rad

e I

nte

rio

r/E

xte

rio

r S

tee

l a

nd

D.I

. P

ipin

g

No

n-I

mm

ers

ion

/No

n-C

orr

osi

ve

En

vir

on

me

nt

Sh

op

Pri

me

d

Sho

p p

rim

ed

me

tal s

urf

ace

s n

ew

an

d e

xist

ing

, su

ch a

s

insi

de

pu

mp

sta

tio

n b

uild

ing

s, e

xte

rio

r p

ipin

g a

nd

va

lve

s,

ext

eri

or

stru

ctu

ral s

tee

l, e

tc.

SSP

C-S

P1

SSP

C-S

P3

NA

PF

50

0-0

3-0

1

NA

PF

50

0-0

3-0

4

NA

PF

50

0-0

3-0

5

TY

PE

L –

Ep

oxy

Ma

stic

Sp

ot

Pri

me

Typ

e N

– P

en

etr

ati

ng

Ep

oxy

Pre

-Pri

me

r

Typ

e G

– S

trip

e C

oa

t

Typ

e G

–A

cryl

ic P

oly

ure

tha

ne

En

am

el -

Glo

ss

1 2 3

4.0

2.0

4.0

To

tal M

inim

um

Dry

Film

Th

ickn

ess

1

0 m

ils

No

. 4

A

bo

ve

-Gra

de

In

teri

or

an

d E

xte

rio

r P

VC

Pip

e

Ext

eri

or

surf

ace

s P

VC

pip

ing

.

SSP

C-S

P1

Lig

ht

San

din

g

TY

PE

B –

Ep

oxy

-Po

lya

mid

e

Pri

me

r

TY

PE

F –

Alip

ha

tic

Po

lyu

reth

an

e E

na

me

l

1 2

3.0

3.0

To

tal M

inim

um

Dry

Film

Th

ickn

ess

6

.0 m

ils

AD

DE

ND

UM

NO

. 3

Hig

h-P

erf

orm

an

ce C

oa

tin

gs

0

9 9

6 0

0.0

1 -

27

KE

R1

73

40

– W

ate

r T

rea

tme

nt

Pla

nt

TH

M C

on

tro

l F

aci

lity

Sy

ste

m

Ap

pli

cati

on

De

scri

pti

on

S

urf

ace

Pre

p

Pro

du

ct T

yp

e

No

. o

f

Co

ats

DF

T

(mil

s)

No

. 5

Me

tal

Pip

ing

an

d V

alv

es

wit

hin

Va

ult

s a

nd

Un

de

r

Insu

lati

on

& B

uri

ed

Ste

el

Pip

ing

an

d F

itti

ng

s

All

me

tal s

urf

ace

s n

ew

an

d e

xist

ing

th

at

will

be

inst

alle

d in

are

as

wh

ere

te

mp

ora

ry s

ub

me

rge

d c

on

dit

ion

s ca

n o

ccu

r,

such

as

wit

hin

va

ult

s a

nd

fo

r p

ipin

g a

nd

va

lve

s co

vere

d w

ith

insu

lati

on

.

SSP

C-S

P1

SSP

C-S

P6

NA

PF

50

0-0

3-0

1

NA

PF

50

0-0

3-0

4

NA

PF

50

0-0

3-0

5

TY

PE

L –

Ep

oxy

Ma

stic

TY

PE

E -

Str

ipe

Co

at

TY

PE

E –

Ep

oxy

-Po

lya

mid

e

TY

PE

E –

Ep

oxy

-Po

lya

mid

e

1 2

3

5.0

5.0

5.0

To

tal M

inim

um

Dry

Film

Th

ickn

ess

1

5 m

ils

No

. 6

Pro

po

sed

an

d E

xis

tin

g S

tee

l P

ipin

g L

inin

g

All

inte

rio

r m

eta

l su

rfa

ces

of

pro

po

sed

an

d e

xist

ing

ste

el

pip

ing

an

d f

itti

ng

s fr

om

cle

ar

we

ll to

co

nn

ect

ion

of

pro

po

sed

24

-in

ch d

uct

ile ir

on

pip

e.

Pro

du

ct m

ust

ha

ve a

fast

re

turn

to

se

rvic

e.

Ca

rtri

dg

e k

its

ma

y b

e u

tiliz

ed

fo

r

ap

plic

ati

on

.

SSP

C-S

P1

SSP

C-S

P1

0/S

P1

1

Ca

rbo

line

– P

oly

cla

d 7

67

or

Ap

pro

ved

Eq

ua

l 1

2

0.0

To

tal M

inim

um

Dry

Film

Th

ickn

ess

2

0 m

ils

EN

D O

F S

EC

TIO

N

ADDENDUM NO. 3

Steel Pipe 33 11 13.13 - 1

KER17340 – Water Treatment Plant THM Control Facility

33 11 13.13 STEEL PIPE

1.00 GENERAL

1.01 WORK INCLUDED

A. Furnish labor, materials, equipment and incidentals necessary to install steel pipe, fittings,

and specials as specified, including connections and appurtenances, as required for the

proper installation and function of the pipe as indicated herein.

B. The pipeline coating and lining shall be as specified herein and in Section 09 96 00.01 “High-

Performance Coatings.”

C. The pipeline shall be suitable to carry reuse water treated with chlorine to maintain a

disinfectant residual.

D. All joints for steel pipe must be welded.

1.02 QUALITY ASSURANCE

A. Experience Requirements:

1. Pipe shall be the product of one manufacturer who has had not less than 5 years

successful experience manufacturing pipe of the particular type and size indicated. Pipe

manufacturing operations (pipe, lining, and coating) shall be performed at one location

unless otherwise approved by the Engineer. Fittings may be manufactured at an

alternate location, provided they are supplied under the responsible authority of the

Pipe Manufacturer. All pipe shall be new and not supplied from inventory. All pipe and

fittings shall be manufactured in the Continental U.S.A., and shipping over salt

waterways will not be allowed.

2. The Manufacturer shall be certified either under S.P.F.A. or ISO 900I quality certification

program for steel pipe and accessory manufacturing.

3. Approved manufacturers include Hanson Pipe, Northwest Pipe, American Spiral Weld,

and Ameron. No other Suppliers will be allowed.

B. Factory Testing:

1. The Manufacturer shall perform all tests as required by the applicable AWWA standards

and as listed herein.

2. Coating: The pipe coating and lining shall be tested as specified in Section 09 96 00.01

“High-Performance Coatings.”

3. Hydrostatic Pressure Testing and Welding Testing:

a. Each joint of pipe shall be hydrostatically tested prior to application of lining or

coating. The internal test pressure shall be that which results in a fiber stress equal

to 75 percent of the minimum yield strength of the steel used. Each joint of pipe

tested shall be completely watertight under maximum test pressure. As a part of

testing equipment, the Pipe Manufacturer shall maintain a recording pressure

gauge, reference number of pipe tested, etc. The pipe shall be numbered in order

that this information can be recorded.

ADDENDUM NO. 3

Steel Pipe 33 11 13.13 - 2

KER17340 – Water Treatment Plant THM Control Facility

b. Fittings shall be fabricated from hydrostatically tested pipe. All welds on fittings

shall be tested by hydrostatic test, ultrasonic test, air test, or magnetic particle test.

Air test shall be made by applying air to the welds at 10 pounds per square inch

pressure and checking for leaks around and through welds with a soap solution. In

addition, 5 percent of welds on fittings shall be checked with x-ray or ultrasonic

testing by an independent certified welding inspector paid for by the Pipe

Manufacturer.

4. Charpy V-Notch Test: Each heat of steel for plates or coil used for pipe barrels 0.25

inches and thicker shall be tested to verify minimum impact values of 25 ft-lb at 30 F in

accordance with ASTM A370.

5. Elongation: For the tensile test specified in ASTM A370, 2-inch test specimens shall

show elongations not less than 22 percent for each heat of steel.

6. Mill Certification: The Owner will require the Manufacturer to furnish mill test

certificates on reinforcing steel or wire, steel plate, steel coil, and cement. The

Manufacturer shall perform the tests described in AWWA C200, for all pipe, fittings, and

specials.

1.03 SUBMITTALS

A. Submittals shall be in accordance with Section 01 33 00 “Submittal Procedures” and shall

include:

1. Shop Drawings:

a. Prior to the fabrication of the pipe, submit fabrication and laying drawings to the

Engineer. Shop Drawings shall include a schematic location profile and a tabulated

layout schedule, both of which shall be appropriately referenced to the stationing of

the proposed pipeline as shown on the plan and profile sheets. Shop Drawings shall

be based on the drawings and Specifications and shall incorporate changes

necessary to avoid conflicts with existing utilities and structures. Shop Drawings

shall also include full details of reinforcement, and dimensions for pipe and fittings.

Details for the design and fabrication of all fittings, specials, and provisions for

thrust restraint shall be included.

b. Where welded joints are required, Shop Drawings shall include:

1). Welding requirements.

2). Location and dimension of all additional outlets required by the Contractor to

install welds.

2. Certificate of Adequacy of Design: Prior to shipment of the pipe, the Contractor/Pipe

Manufacturer shall submit an affidavit certifying that the pipe, fittings, specials, and

other products and materials furnished, comply with this Specification, Drawings, and

the applicable requirements of AWWA C200, AWWA C215, AWWA C222.

3. Certified Test Reports:

a. Submit the following Certified Test Reports prior to shipment of the pipe:

1). Copies of results of factory hydrostatic tests and test of fittings.

ADDENDUM NO. 3

Steel Pipe 33 11 13.13 - 3

KER17340 – Water Treatment Plant THM Control Facility

2). Mill certificates, including chemical and physical test results for each heat of

steel, charpy v-notch tests, and elongation tests.

3). A Certified Test Report from the Coating Manufacturer indicating that the

coatings were applied in accordance with manufacturer's requirements and in

accordance with this Specification on all pipe, fittings and joints made in the

factory.

4). Certified Test Reports for welder certification for factory and field welders.

5). Certified Test Reports for factory welds of fittings from an independent Certified

Welding Inspector paid for by the Pipe Manufacturer.

4. Record Data:

a. Before pipe installation begins:

1). Provide copies of “Release for Manufacture” layout sheets.

2). Provide copies of all design calculations.

3). Where welded joints are required, provide the Contractor’s Proposed Field

Welding Procedure in accordance with this Specification, AWWA C206 and AWS

D1.1. The Field Welding Procedure shall include provisions for thermal stress

control and provisions for control of coating damage.

1.04 STANDARDS

A. Except as modified or supplemented herein, the steel pipe, coatings, linings, fittings, and

specials shall conform to the applicable requirements of the following standards and

specifications, latest edition:

AWS D1.1 Structural Welding Code

AWWA C200 Steel Water Pipe – 6 In. (150 MM) and Larger

AWWA C206 Field Welding of Steel Water Pipe

AWWA C207 Steel Pipe Flanges for Waterworks Service Sizes 4 In. Through 144

In. (100 mm Through 3600 mm)

AWWA C208 Dimensions for Steel Water Pipe Fittings

AWWA C210 Liquid-Epoxy Coating Systems for the Interior and Exterior of Steel

Water Pipelines

AWWA C215 Extruded Polyolefin Coatings for Exterior of Steel Water Pipelines

AWWA C216 Heat Shrinkable Cross-Linked Polyolefin Coatings for the Exterior of

Special Sections, Connections, and Fittings for Steel Water

Pipelines

AWWA C217 Petrolatum and Petroleum Wax Tape Coatings for the Exterior of

Connections and Fittings to Steel Water Pipelines

AWWA C222 Polyurethane Coatings for the Interior and Exterior of Steel Water

Pipelines and Fittings

AWWA M11 Manual: Steel Pipe - A Guide for Design and Installation

AWWA C604 Installation of Steel Water Pipe – 4 In. and Larger

ADDENDUM NO. 3

Steel Pipe 33 11 13.13 - 4

KER17340 – Water Treatment Plant THM Control Facility

ASME Shop Welding Certification

ASTM A370 Standard Test Method and Definitions for Mechanical Testing of

Steel Products

ASTM C33 Standard Specification for Concrete Aggregates

ASTM C35 Standard Specification for Inorganic Aggregates for Use in Gypsum

Plaster

ASTM C150 Standard Specification for Portland Cement

ASTM D16 Standard Terminology for Paint, Related Coatings, Materials and

Applications

ASTM D522 Standard Test Methods for Mandrel Bend Test of Attached Organic

Coatings

ASTM E165 Standard Practice for Liquid Penetrant Examination for General

Industry

ASTM E709 Standard Guide for Magnetic Particle Testing

ASTM E1444 Standard Practice for Magnetic Particle Testing

SSPC-SP-1 Solvent Cleaning

SSPC-SP-10 Near-White Blast Cleaning

SSPC-PA2 Measurement of Dry Paint Thickness with Magnetic Gages

SSPC-PA/Guide 3 A Guide to Safety in Paint Application

SSPC-PS/Guide 17 A Guide for Selecting Urethane Painting Systems

1.05 DELIVERY AND STORAGE

A. Packing:

1. The pipe shall be prepared for shipment to afford maximum protection from normal

hazards of transportation and allow pipe to reach the Site in an undamaged condition.

Pipe damaged in shipment shall not be delivered to the Site unless such damaged pipe is

properly repaired.

2. After the completed pipe and fittings have been removed from the final cure at the

manufacturing plant, the pipe lining shall be protected from drying by means of plastic

end covers banded to the pipe ends. Covers shall be maintained over the pipe ends at

all times until ready to be placed in the trench. Moisture shall be maintained inside the

pipe by periodic addition of water as necessary.

3. Pipes shall be carefully supported during shipment and storage. Pipe, fittings, and

specials shall be separated so that they do not bear against each other, and the whole

load shall be securely fastened to prevent movement in transit. Ship pipe on padded

bunks with tie-down straps approximately over stulling. Store pipe on padded skids,

sand or dirt berms, tires, or other suitable means to protect the pipe from damage. As a

minimum, each end of each length of pipe, fitting, or special and the middle of each

pipe joint shall be internally supported and braced with stulls to maintain a true circular

shape. More internal stulls shall be included to protect the pipe, lining, and coating

from damage as determined by the Pipe Manufacturer. Internal stulls shall consist of

timber or steel firmly wedged and secured so that stulls remain in place during storage,

ADDENDUM NO. 3

Steel Pipe 33 11 13.13 - 5

KER17340 – Water Treatment Plant THM Control Facility

shipment, and installation. Pipe and liner shall be protected from damage from stulls

using shaped wood pads or similar devices. Stulls shall not be welded directly to the

pipe except at the end of the pipe where the lining is held back. Pipe shall be rotated so

that one stull remains vertical during storage, shipment and installation. Stulls shall not

be removed until the pipe is laid, set to grade, and backfilled.

4. Deliver, handle, and store pipe in accordance with the Manufacturer's

recommendations and in accordance with Paragraph 3.01.C.

B. Marking for Identification: Each joint of pipe and each fitting shall have plainly marked on

the inside of both ends, the class for which it is designed, the date of manufacture, and the

identification number as shown on the Shop Drawings. Beveled pipe shall be marked with

the amount of bevel. The top centerlines shall be marked on all specials.

C. Point of Delivery:

1. Pipe shall be hauled direct from pipe plant to the Site and strung along pipeline route,

thus avoiding re-handling of pipe and the possibility of damage thereto. Where fully

loaded truck and trailer cannot operate along the pipeline route, pipe may be unloaded

at access points along the route, and brought to the trench side by approved methods;

however, the Contractor shall be responsible to ensure that pipe is undamaged at the

time of laying.

2. If the pipe cannot be hauled directly from the pipe plant to the laying site, a maximum

of two handlings is allowed in which case the maximum number of coating repairs is

reduced to five.

3. Shipment by rail will be unacceptable, unless it can be demonstrated that it will not

damage the pipe.

2.00 PRODUCTS

2.01 MATERIALS

A. Steel: Steel shall meet the requirements of AWWA C200 and shall be of continuous casting.

Steel shall be homogeneous and shall be suitable for field welding, fully kilned and fine

austenitic grain size. Steel shall have a minimum yield strength of 42,000 psi.

B. Coatings and Linings:

1. Coatings:

Coating shall be in accordance with Section 09 96 00.01 “High-Performance Coatings”

and applied on all piping and fittings.

2. Linings:

Lining shall be in accordance with Section 09 96 00.01 “High-Performance Coatings” and

applied on all piping and fittings.

C. Flange Nuts and Bolts: Bolts shall conform to ASTM A193, Grade B7. Nuts shall conform to

ASTM A194, Grade 2H heavy hex nut. Use anti-seize compound during installation of all

nuts and bolts. Thrust rods shall be carbon steel conforming to ASTM A193.

ADDENDUM NO. 3

Steel Pipe 33 11 13.13 - 6

KER17340 – Water Treatment Plant THM Control Facility

D. Threaded Outlets: Where outlets or taps are threaded, furnish and install 304 stainless steel

bushings for the outlet size indicated.

2.02 MANUFACTURED PRODUCTS

A. Pipe:

1. Pipe Design:

a. Steel pipe shall be manufactured, and tested in conformance with AWWA C200,

AWWA M11, and with the criteria specified herein. Sizes and pressure classes

(working pressure) shall be as shown in the Drawings. For the purpose of pipe

design, the transient pressure plus working pressure shall be 1.5 times the working

pressure class specified. Fittings, specials, and connections shall be designed for the

same pressures as the adjacent pipe. Pipe design shall be based on trench

conditions and the design pressure in accordance with AWWA M11; using the

following parameters:

Unit Weight of Fill (W) 130 pcf

Live Load

AASHTO HS 20 at all locations, except at

railroads

Coopers E 80 at Railroads

Trench Depth As indicated

Deflection Lag Factor (Dl) 1.1

Coefficient (K) 0.10

Maximum Calculated Deflection

(DX = DY)

2% (Polyurethane Coated Steel Pipe or

concrete encased)

Soil Reaction Modulus (E') 1500 psi (Typical Granular Embedment

Trench Section)

Soil Reaction Modulus (E’) 3000 psi (Flowable Fill or Concrete Encased

Trench Section)

b. The fittings and specials shall be designed in accordance with AWWA C208 and

AWWA M11 except that crotch plates shall be used for outlet reinforcement for all

Pressure Diameter Valves values (PDV), greater than 6000 unless otherwise

specified. Where indicated on the Drawings, collars or wrappers shall be used in

lieu of crotch plates to allow working space and supports. Wrappers and collars

shall meet ASME Standards. As an alternate to crotch plates, collars or wrappers

may be used when designed in accordance with ASME Section VIII, Division 1.

c. Where the pipe requires additional external support to achieve the specified

maximum deflection, the Contractor and Pipe Manufacturer will be required to

furnish alternate methods for pipe embedment. No additional compensation will be

made to the Contractor by the Owner where this method is required.

d. Trench depths indicated shall be verified after existing utilities are located. Vertical

alignment changes required because of existing utility or other conflicts shall be

accommodated by an appropriate change in pipe and embedment design depth. In

no case shall the pipe and embedment system be installed deeper than its design

allows.

ADDENDUM NO. 3

Steel Pipe 33 11 13.13 - 7

KER17340 – Water Treatment Plant THM Control Facility

e. Pipe shall be designed for full vacuum conditions without buckling, damage to lining,

or damage to pipe joints.

2. Provisions for Thrust:

a. Thrust at valves, bends, tees, or other fittings shall be resisted by restrained joints.

Thrust at bends adjacent to casing shall be restrained by welding joints through the

casing and a sufficient distance each side of the casing. No thrust restraint

contribution shall be allowed for pipe in casing unless the annular space in the

casing is filled with grout.

b. Restrained joints shall be used a sufficient distance from each side of the valves,

bend, tee, plug, or other fitting to resist thrust which develops at the design

pressure of the pipe. For the purposes of thrust restraint, design pressure shall be

1.5 times the working pressure class. Restrained joints shall consist of welded joints

unless other joint types are shown on the Drawings.

c. Thrust restraint design shall be the complete responsibility of the Pipe

Manufacturer. The Pipe Manufacturer shall submit thrust calculations with the lay

drawing submittal verifying that the thrust restraint system is adequate to meet the

Pipe Manufacturer’s minimum standards, AWWA M11 standards, and these

Specifications, whichever is more stringent. The length of pipe with restrained joints

to resist thrust forces shall be determined by the Pipe Manufacturer in accordance

with AWWA M11 and the following:

1). The Weight of Earth shall be calculated as the weight of the projected soil prism

above the pipe.

2). For unsaturated soil conditions:

Soil Density 110 pcf (maximum value to be used)

Coefficient of Friction 0.20 (maximum value to be used for polyurethane

coated steel pipe)

3). In locations where ground water is encountered, assume saturated soil

conditions.

a). The soil density shall be reduced to its buoyant weight for all backfill below

the water table.

Soil Density 60 pcf (maximum value to be used)

Coefficient of Friction 0.15 (maximum value to be used for polyurethane

coated steel pipe)

4). For horizontal bends, the length of pipe to be restrained shall be calculated as

follows:

a). For Δ less than 60 degrees:

L = 2 × P × A × sin(Δ2) f × ( We + Wp + Ww)

ADDENDUM NO. 3

Steel Pipe 33 11 13.13 - 8

KER17340 – Water Treatment Plant THM Control Facility

b). For Δ greater than 60 degrees:

L = P × A × (1 − cos Δ) f × (We + Wp + Ww)

L = Length of pipe to be restrained

P = 1.5 times working pressure

A = Cross-sectional area of pipe steel cylinder I.D.

Δ = Deflection angle

We = Weight of earth prism above the pipe

Wp = Weight of pipe

Ww = Weight of water

f = Coefficient of friction

5). For vertical bends, the length of pipe to be restrained shall be calculated per

AWWA M11.

3. Inside Diameter: The inside diameter, including the lining, shall be a minimum of the

nominal diameter of the pipe specified, unless otherwise indicated on the Drawings. It is

the responsibility of the Contractor to field verify that the nominal pipe diameter meets

specifications before installing the pipe. Contractor shall coordinate pipe replacement

with the Pipe Manufacturer for any pipe not meeting the specified internal diameter.

4. Wall Thickness:

a. The minimum pipe wall steel thickness shall be 0.25 inches or Pipe ID/230,

whichever is greater for pipe and fittings, and a maximum minus tolerance of 0.005

inches per AWWA C200. Where indicated on the Drawings, pipe and fittings shall

have thicker steel pipe wall. The minimum steel wall thickness shall also be such

that the fiber stress shall not exceed 50 percent of the minimum yield strength of

the steel at working pressure, nor the following, at the specified working pressure.

Pipe Type Maximum Stress

at Working Pressure

Polyurethane Coated Steel 21,000 psi

b. Pipe which is placed in casing or tunnel shall have a minimum pipe wall steel

thickness of 0.25 inches or Pipe ID/144, whichever is greater.

c. Fittings over 15 degrees, pipes with outlets 24-inches in diameter and larger, main

line tees and wyes, and pipe which are above grade or exposed (not in a trench or

casing) shall have the following minimum thickness:

36” Diameter and Smaller 0.25”

37” < Diameter ≤ 60” 0.375”

61” < Diameter ≤ 84” 0.50”

85” < Diameter ≤ 96” 0.625”

ADDENDUM NO. 3

Steel Pipe 33 11 13.13 - 9

KER17340 – Water Treatment Plant THM Control Facility

97” < Diameter ≤ 120” 0.75”

d. Pipe, fittings, and specials shall be designed such that the maximum stresses in the

pipe due to thrust loading will not exceed 18,000 psi nor 50 percent of the steel

yield strength at the thrust design pressure (1.5 times working pressure).

5. Seams: Except for mill-type pipe, the piping shall be made from steel plates rolled into

cylinders or sections thereof with the longitudinal and girth seams butt welded or shall

be spirally formed and butt welded. There shall be not more than two longitudinal

seams. Girth seams shall be butt welded and shall not be spaced closer than 6 feet

except in specials and fittings.

6. Joint Length: Maximum joint length shall not exceed 50 feet. Maximum joint length of

steel pipe installed in casing shall not exceed 25 feet.

B. Bend Fittings: All bend fittings shall have a minimum radius of 2.5 times the diameter to

permit passage of pipeline pigs.

C. Pipe Ends: Pipe ends shall be lap welded slip joint, butt strap joint, flanged joint, or flexible

coupled joint. Pipe that has a diameter of 48 inches or smaller together with pressure class

of 250 psi or lower may have welded joints or rubber gasket joints. Pipe ends shall be

suitable for full vacuum and the maximum surge pressures indicated.

1. Rubber Gasket Joints: Rubber gasket joints shall be a rolled spigot or carnegie joint with

rubber gasket for pressure classes up to 250 psi. Joints shall conform to AWWA M11 and

AWWA C200. Joints shall be of clearances such that water tightness shall be provided

under all operating and test conditions with a pipe diameter deflection of 4 percent.

The joint shall be suitable for the specified pressure and a deflected joint with a pull of

3/4 inches. At the Pipe Manufacturer’s option, all steel pipe joints may be lap-welded

slip joints in lieu of rubber gasket joints.

a. Rolled Spigot Joints: The joint shall consist of a flared bell end formed and sized by

forcing the pipe over a plug die or by expanding on segmental dies. The difference

in diameter between the I.D. of bell and the O.D. of spigot shoulder at point of full

engagement with an allowable deflection shall be no more than .00 inches to .04

inches as measured on the circumference with a diameter tape. The gasket shall

have sufficient volume to approximately fill the area of the groove and shall

conform to AWWA C200.

b. Carnegie Joints: The spigot end shall be a Carnegie shaped steel joint ring. Spigot

ring shall be welded to the outside of the pipe can, with an inside weld also required

where deemed necessary by the Manufacturer due to pipe loading conditions. The

welded area of bell and spigot pipe ends shall be checked after forming by the

magnetic particle method.

2. Lap Welded Slip Joint:

a. Lap welded slip joint shall be provided in all locations where any of the following

criteria is met, unless otherwise specified in the Drawings:

1). Pipe ID is 54 inches and larger.

2). Pressure class is 275 psi and greater.

3). Joints are welded for thrust restraint.

ADDENDUM NO. 3

Steel Pipe 33 11 13.13 - 10

KER17340 – Water Treatment Plant THM Control Facility

b. Ends of pipe, fittings, and specials for field welded joints shall be prepared with one

end expanded in order to receive a plain end making a bell and plain end type of

joint. Clearance between the surfaces of lap joints shall not exceed 1/8 of an inch at

any point around the periphery.

c. The depth of bell shall be such as to provide for a minimum clear distance of 2

inches between the weld and the nearest tangent of the bell radius when welds are

to be located on the inside of the pipe.

d. The depth of bell shall be such as to provide for a minimum lap of 2 inches. Provide

a deeper bell every 400 feet to accommodate thermal movement for which the

minimum lap shall be 4 inches.

e. Lap welded slip joints shall be welded from the inside for pipe diameters 48 inches

and larger. Lap welded slip joints shall be welded from the outside for diameters

smaller than 48 inches.

3. For Fittings with Flanges: Flanged joints shall be provided at connections to valves and

where indicated. Ends to be fitted with slip on flanges shall have the longitudinal or

spiral welds ground flush to accommodate the type of flanges provided. Pipe flanges

and welding of flanges to steel pipe shall conform to the requirements of AWWA C207

and AWWA C206. Pipe flanges shall be of rated pressure equal to or greater than the

adjacent pipe class. Flange drilling shall match the drilling of adjacent fittings or

appurtenances which the flanges are to be attached to. Flanges shall be spot faced or

back faced parallel to the front face.

4. Flexible Couplings: Flexible couplings shall be provided where shown in the Drawings

and as specified in Section 33 12 16.13 “Miscellaneous Valves.” Ends to be joined by

flexible couplings shall be of the plain end type, prepared as stipulated in AWWA C200.

Pipe ends shall be truly circular to within 0.25 inch or the Coupling Manufacturer’s

tolerances, whichever is smaller. In addition, the welds on ends to be joined by

couplings shall be ground flush to permit sliding the coupling in at least one direction to

clear the pipe joint. Harness bolts and lugs shall comply with AWWA M11 and the

Drawings.

5. Butt Strap Closure Joints:

a. Where necessary to make closure to pipe previously laid, closure joints shall be

installed using butt strap joints in accordance with AWWA C206 and applicable

provisions of this specification.

b. Butt strap shall have an inside and outside weld and shall be air tested. Air test shall

be low pressure from a threaded fitting between the welds.

3.00 EXECUTION

3.01 INSTALLATION

A. General:

1. Install steel pipe, fittings, specials, and appurtenances as specified and required for the

proper functioning of the completed pipeline. Install pipe, fittings, and specials in

accordance with the Manufacturer's recommendations, AWWA C604, and AWWA M11.

ADDENDUM NO. 3

Steel Pipe 33 11 13.13 - 11

KER17340 – Water Treatment Plant THM Control Facility

Pipe shall be laid to the lines and grade indicated. Before each joint of steel pipe is

lowered into the ditch, the coating is to be inspected and tested for holidays. All

damaged areas and holidays are to be repaired before the pipe is lowered into the

trench.

2. The requirements of Section 31 23 33 “Trenching and Backfill” govern for the excavation

and backfilling of trenches for laying steel pipe, fittings, and specials.

3. Keep the pipe clean during the laying operation and free of sticks, dirt, animals, and

trash, and at the close of each operating day, effectively seal the open end of the pipe

against the entrance of water using a gasketed night cap. Do not lay pipe in water. The

Contractor may install a vent at the top of the night cap to prevent flotation of the pipe

in the event of heavy rain during the night.

4. Install bonds at all pipe joints, other than welded joints or insulated joints.

5. Conformance with pipe deflection requirements shall be as set forth in the Pipe

Deflection section below. Where pipe has been reworked to comply with the deflection

requirements, Contractor shall re-measure for deflection no earlier than 7 days after the

repaired pipe is backfilled. No pipe installation shall be accepted until the entire

installation is in compliance with the deflection requirements.

6. Installed pipe joints will be inspected by the Owner’s Representative for flat spots and

internal lining stress cracks. Lining damage shall be repaired in accordance with the

Manufacturer’s recommendations and as directed by the Engineer at no additional cost

to the Owner.

a. The Contractor shall complete internal welding of joints, welding inspections and

grout of the inside joints prior to measuring deflection. The welding inspections

shall be done by an independent CWI as described in Section 01 40 00 “Quality

Control.”

b. The Contractor shall schedule the internal inspections with the on-site Owner’s

Representative.

c. Repair of flat spots may include uncovering the pipe, re-compaction of the pipe

bedding, and repair of the coating.

d. Owner’s Representative will re-inspect for flat spots where pipe has been reworked

to comply with the deflection requirements.

B. Pipe Deflection:

1. Pipe Deflection Measurements:

a. The Contractor shall complete internal welding of joints, welding inspections and

grout of the inside joints prior to measuring deflection. The welding inspections

shall be done by an independent CWI as described in Section 01 40 00 “Quality

Control.”

b. Deflection measurements shall be made by the Contractor in the presence of the

Owner’s Representative.

1). Method for taking measurements shall be agreed to by the Owner and Engineer

in writing prior to installing the first joint of pipe.

ADDENDUM NO. 3

Steel Pipe 33 11 13.13 - 12

KER17340 – Water Treatment Plant THM Control Facility

2). Measurements shall be recorded by the Contractor.

3). The deflection measurements shall be made no sooner than 5 days and no later

than 21 days after backfilling operations are complete.

c. Deflection shall be determined with vertical measurements taken at the locations

indicated below. Locations where vertical measurements are taken shall be clearly

marked on the interior of the pipe.

1). For pipe joints 36 feet in length or less, vertical measurements shall be taken at

two locations, one-fourth-distance from each pipe end.

2). For pipe joints longer than 36 feet, vertical measurements shall be taken at

three locations including one-fourth-distance from each pipe end and at the

pipe midpoint.

d. Vertical measurements may be taken at the same time the internal inspection is

being performed.

2. Pipe deflection calculations: Deflection shall be calculated and reported by the

Contractor within a week from the time the vertical measurements were taken.

Deflection at each location shall be calculated using the equations below:

Δ = Deflection (%)

∆ = �(Pipe ID – Vertical Measurement) × 100Pipe ID �

3. Pipe deflection acceptance criteria:

a. Allowable pipe deflection is limited to:

1). 2 percent for polyurethane coated steel pipe.

2). 2 percent for concrete encased or flowable fill encased steel pipe.

b. In no case shall a single measurement at any measured location exceed 1.5 times

the allowable deflection.

c. These measurements include the allowable tolerance for lining thickness.

4. Correction of Pipe not Complying with Deflection Requirements:

a. If the calculated deflection at any location or any single measurement fails to meet

specifications, the entire joint shall be reworked in accordance with the

Manufacturer’s recommendations and as directed by the Engineer at no additional

cost to the Owner. This may include uncovering the pipe, re-compaction of the pipe

bedding, and repair of the coating. It is the Contractor’s responsibility to

continuously measure and calculate pipe deflection to verify it meets specification.

b. All costs associated with measuring for pipe deflection and any repairs or rework

associated with meeting these requirements shall be borne by the Contractor.

ADDENDUM NO. 3

Steel Pipe 33 11 13.13 - 13

KER17340 – Water Treatment Plant THM Control Facility

5. Pipe Deflection Reports:

a. A monthly report shall be submitted as Record Data showing the following for each

joint of pipe:

1). Allowable deflection and 1.5 times allowable deflection for each pipe diameter

installed.

2). Deflection measurements and calculated deflection for each location measured

per joint.

3). It is the responsibility of the Contractor to verify that the nominal pipe diameter

meets specifications at all measured locations. Contractor shall coordinate pipe

replacement with the Pipe Manufacturer for any pipe not meeting the specified

internal diameter.

C. Pipe Handling: Pipe shall be handled at all times with a minimum of two wide non-abrasive

slings or belts to prevent damage to the coating or lining. The equipment shall be kept in

such repair that its continued use is not injurious to the coating. All pipe joints over 25 feet

shall be handled with a spreader bar. The spacing of pipe supports required to handle the

pipe shall be adequate to prevent cracking or damage to the lining or coating.

D. Line Up and Bends:

1. Line up pipe for joining so as to prevent damage thereto. Thoroughly clean the bell and

spigot ends of each joint of pipe of foreign matter, rust and scale before placing spigot

into bell. Welded joints shall have an overlap of 2 inches minimum to 4 inches

maximum

2. All under-stabbed joints shall be butt strapped or re-stabbed. All over-stabbed joints

shall be re-stabbed, butt strapped, or outside welded.

3. Where abrupt changes in grade and direction occur, the Contractor shall employ special

shop fabricated fittings for the purpose. Field cutting the ends of the steel pipe to

accomplish angular changes in grade or direction of the line shall not be permitted.

E. Pipe Laying - Rubber Gasket Joints: Join rubber gasket joints in accordance with the

Manufacturer’s recommendations. Clean bell and spigot of foreign materials. Lubricate

gasket and bell and relieve gasket tension around the perimeter of the pipe. Engage spigot

as far as possible in bell, allowing for 1inch gap for inside joint grouting after any joint

deflections. Joint deflection or pull shall not exceed the Manufacturer’s suggested

tolerance. Check gasket with feeler gauge all around the pipe.

F. Pipe Laying - Welded Joints:

1. Weld joints in accordance with the AWWA C206 for Field Welding of Steel Water Pipe

and AWS D1.1 Structural Welding Code. Contractor shall provide adequate ventilation

for welders and for Owner's Representative to observe welds. Unless otherwise

specified, welds shall be full circle fillet welds. Exterior joint welding shall be completed

before application of field applied joint coating for pipe 42 inches and smaller. It will be

acceptable to weld the joint from the inside after the exterior joint coating and

backfilling has been done for pipe 48 inches and larger, if it can be demonstrated that

this procedure will not damage the exterior joint coating.

ADDENDUM NO. 3

Steel Pipe 33 11 13.13 - 14

KER17340 – Water Treatment Plant THM Control Facility

2. A Welding Procedure Qualification shall be approved by the Engineer before welding of

joints begins. The procedure shall be in accordance with AWWA C206 and AWS D1.1.

3. Provide a deeper bell every 400 feet to accommodate thermal movement for which the

minimum lap shall be 4 inches.

4. Adequate provisions for reducing temperature stresses shall be the responsibility of the

Contractor.

5. After the pipe has been joined and properly aligned and prior to the start of the welding

procedure, the spigot and bell shall be made essentially concentric by tacking to obtain

a 1/8 of an inch maximum clearance tolerance around the periphery of the joint. In no

case shall the clearance tolerance be permitted to accumulate.

6. Before welding, thoroughly clean pipe ends to bare metal. All welding shall be hand

welding to avoid damage to the exterior joint coating. Welding shall be performed so as

not to damage lining or coating. Cover the lining and/or coating as necessary to protect

from welding splatter.

7. Furnish labor, equipment, tools and supplies including shielded type welding rod.

Protect welding rod from any deterioration prior to its use. If any portion of a box or

carton is damaged, reject the entire box or carton.

8. In all hand welding, the metal shall be deposited in successive layers. For hand welds,

not more than 1/8 of an inch of metal shall be deposited in each pass. Each pass except

the final one, whether in butt or fillet welds, shall be thoroughly bobbed or peened to

relieve shrinkage stresses and to remove dirt, slag, or flux before the succeeding bead is

applied. Each pass shall be thoroughly fused into the plates at each side of the welding

groove or fillet and shall not be permitted to pile up in the center of the weld.

Undercutting along the side shall not be permitted.

9. Welds shall be free from pin holes, non-metallic inclusions, air pockets, undercutting

and/or any other defects.

10. If the ends of the pipe are laminated, split or damaged to the extent that satisfactory

welding contact cannot be obtained, remove the pipe from the line.

11. Furnish each welder employed with a steel stencil for marking the welds, so that the

work of each welder may be identified. Have each welder stencil the pipe adjacent to

the weld with the stencil assigned to him. In the event any welder leaves the job, his

stencil shall be voided and not duplicated if another welder is employed.

12. Keep daily welding reports which identify the welder’s name and the joint welded.

Joints must be shown on the daily welding reports with the identification number

assigned in the lay drawings (ex. ID#1 – ID#2). Provide three copies of all daily welding

reports to Owner representative every month.

13. Use only competent, skilled and qualified workmen. Each welder employed by the

Contractor shall be both AWS D1.1 and C206 certified according to the Welding

Procedure Qualification approved for the Project. All welders shall have been certified

within the last 6 months or shall provide a welding continuity log to be allowed to weld

on the line.

ADDENDUM NO. 3

Steel Pipe 33 11 13.13 - 15

KER17340 – Water Treatment Plant THM Control Facility

14. Inspections shall be made of joints in the line for each welder qualified above. Any

welder making defective welds shall not be allowed to continue to weld.

15. Visual tests and magnetic particle tests in accordance with AWWA C206, ASTM E709 and

E1444, shall be performed by an independent testing laboratory under the direction of

Owner’s Representative on all field welded joints. Certified Weld Inspector will be paid

by the Owner. Welds that prove to be defective will be replaced or repaired, whichever

is deemed necessary by the Engineer, at Contractor’s expense.

16. If the Contractor disagrees with the Engineer's interpretation of welding tests, test

sections may be cut from the joint for physical testing. The Contractor shall bear the

expense of repairing the joint, regardless of the results of physical testing. The

procedure for repairing the joint shall be approved by the Engineer before proceeding.

17. Test double-welded buttstrap joints using the compressed air and soap method.

Following successful completion of the test, plug weld seal the threaded test fitting.

G. Protective Coating System for Welded Joints:

1. Perform field coating of joints in accordance with Section 09 96 00.01 “High-

Performance Coatings.”

2. The Contractor is responsible for his operations so that they do not damage the factory

applied coating system.

H. Protection of Buried Metal

Bolts, flanges, and other buried uncoated ferrous metal which cannot be protected with

factory or field-applied polyurethane coatings shall be coated with heat shrink sleeves

encased in flowable fill.

I. Quality Control of Field Applied Coating: See Section 09 96 00.01 “High-Performance

Coatings.”

3.02 DISINFECTION

Disinfect the piping system in accordance with Section 33 10 13 “Disinfecting Water Utility

Distribution Systems.”

3.03 HYDROSTATIC TEST

Perform a hydrostatic testing as specified.

END OF SECTION

ADDENDUM NO. 3

Butterfly Valves 33 01 02 - 1

KER17340 – Water Treatment Plant THM Control Facility

40 05 64 BUTTERFLY VALVES

1.00 GENERAL

1.01 WORK INCLUDED

A. Furnish labor, materials, equipment and incidentals necessary to install butterfly valves.

B. This project is subject to the American Iron and Steel (AIS) requirements of Section 608 of

the Federal Water Pollution Control Act. All iron and steel products for construction,

alteration, maintenance, or repairs incorporated in these plans must be produced in the

United States.

1.02 QUALITY ASSURANCE

Acceptable Manufacturers:

A. DeZurik

B. M&H

C. CMB/K-Flo

D. Pratt

E. Bray Valve Series 30 (Approved for GAC Absorption System Only)

F. Experience Requirements: The Manufacturer shall have had successful experience in

manufacturing tight-closing, rubber-seated butterfly valves for this type service in the sizes

indicated. The Manufacturer shall have at least 10 years’ experience in the manufacture of

valves.

G. Manufacturer’s Representative for Startup and Testing: The Valve Vendor or Manufacturer

shall provide the services of a competent manufacturer’s representative for an indefinite

period of time as required to insure proper adjustment, installation, and operation of the

valve.

1.03 SUBMITTALS

Submittals shall be in accordance with Section 01 33 00 “Submittal Procedures” and must

include:

A. Record Data:

1. Manufacturer’s data sheets

2. AIS Certifications

B. Operation and Maintenance Manuals

ADDENDUM NO. 3

Butterfly Valves 33 01 02 - 2

KER17340 – Water Treatment Plant THM Control Facility

1.04 STANDARDS

The applicable provisions of the following standards shall apply as if written here in their

entirety:

A. American National Standards Institute (ANSI) Standards:

ANSI B16.1 Cast Iron Pipe Flanges and Fittings

B. American Society for Testing and Materials (ASTM) Standards:

ASTM A48 Standard Specification for Gray Iron Castings

ASTM A126 Standard Specification for Gray Iron Castings for Valves, Flanges,

and Pipe Fittings

ASTM A276 Standard Specifications for Stainless Steel Bars

ASTM A536 Standard Specification for Ductile Iron Castings

ASTM B148 Standard Specifications for Aluminum Bronze Coatings

C. American Water Works Association (AWWA) Standards:

AWWA C504 Standard for Rubber-seated Butterfly Valves

AWWA C550 Standard for Protective Interior Coatings for Valves and Hydrants

2.00 PRODUCTS

2.01 VALVE CONSTRUCTION

A. General: Butterfly valves supplied under this Contract shall be of the tight-closing, rubber

seated type with rubber seats that are securely attached to the valve disc or body. Valves

shall be bubble tight at rated pressures with flow in either direction and shall be satisfactory

for applications involving valve operation after long periods of inactivity. Butterfly valves

shall conform to the applicable requirements of AWWA C504 and AWWA C550. All valves

for potable water service shall comply with NSF61 standards.

B. Valve Bodies: Valve bodies shall be constructed of cast iron ASTM A126, Class B or ASTM

A48, Class 40 or ductile iron in accordance with ASTM A536, Grade 65/45/12. Valve class

shall be suitable for the pressure class of the adjacent pipe in which it is installed. Valve may

have flanged ends with ANSI B16.1 Class 125 drilling or be of the wafer body style and be

suitable for use between ANSI B16.1 Class 125 cast iron flanges.

C. Valve Discs: Valve discs shall be cast iron conforming to ASTM A126, Class B, aluminum

bronze conforming to ASTM B148, or ductile iron conforming to ASTM A536, Grade

65/45/12.

D. Valve Shafts: Valve shafts shall be turned, ground and polished, constructed of stainless

steel conforming to ASTM A276. Valve shafts may consist of a one-piece unit extending

completely through the valve disc, or may be of the “stub shaft” type, which comprises two

separate shafts inserted into the valve disc hubs. If of the “stub shaft” construction, each

stub shaft shall be inserted into the valve disc hubs for a distance of at least 1-1/2 shaft

diameters. The shaft shall be tightly connected to the disc using tapered or wedged keying

devices.

ADDENDUM NO. 3

Butterfly Valves 33 01 02 - 3

KER17340 – Water Treatment Plant THM Control Facility

E. Valve Seats: Valves shall have Neoprene, Buna-N or other synthetic rubber resilient seas to

provide tight shut off at the pressure specified. The mating seat surface shall be ASTM

A276, 18-8 stainless steel or a 95 percent pure nickel overlay. All valves shall have

replaceable, adjustable seats. Valves 30 inches and larger shall have in-line replaceable

seats.

F. Valve Bearings: Valve shall be fitted with sleeve type bearings. Bearings shall be of

corrosion-resistant and “self-lubricated” materials that will not deteriorate natural or

synthetic rubber.

G. Valve Shaft Seals: Where shafts project through the valve bodies for operator connection, a

split-V or O-ring type shaft seal shall be provided.

H. All components, including seats, seals and gaskets, for use with the aeration or backwash air

system shall be suitable for 300-degree F service.

2.02 VALVE OPERATORS:

A. General: The valve operator shall be designed and manufactured in accordance with the

applicable requirements of AWWA C504 and AWWA C540, and shall be arranged for

horizontal or vertical valve shaft installation.

B. Manual Operators:

1. Manual operators shall have all gearing totally enclosed and shall be pre-lubricated or

grease packed. Operators shall be of the worm gear or travelling nut and link type with

field adjustable stops to prevent over travel in the open or closed positions. The

direction of the manual rotation shall be clockwise to close.

2. Operators for exposed valves shall be provided with a valve position indicator and a

handwheel or chain and sprocket device. Provide chain and sprocket for valves greater

than 6-feet above walking surface. Chains must be galvanized and loop within four feet

of the floor.

3. Operators for buried valves shall have an extended stem with a 2-inch square operating

nut within 12 inches of the finished grade. Provide a cast iron valve box to enclose the

operating stem. Valve box shall be per City of Kerrville Standard 370.06 with concrete

collars.

4. For valves which are installed with the shaft vertical, provide a level gear for vertical

operation of the operating nut.

C. Electric operators are to be provided per specification 46 07 13 “Adsorption Systems for use

with Granular Activated Carbon.”

2.03 BUTTERFLY VALVES FOR AIR SERVICE

Furnish lugged style butterfly valves for air service. Valves 10 inches and smaller shall have a

ten-position locking lever operator. Valves 12 inches and larger shall have a gear type hand-

wheel operator. The valve shall be resilient seated, bubble-tight shut off. The valve shall be

shipped loose for field installation. Valve seats and gaskets shall be suitable for operation in

temperatures up to 300-degrees F.

ADDENDUM NO. 3

Butterfly Valves 33 01 02 - 4

KER17340 – Water Treatment Plant THM Control Facility

3.00 EXECUTION

3.01 INSTALLATION

Installation shall be in accordance with the Manufacturer’s instructions. Valve shaft shall be

truly vertical or horizontal as indicated.

3.02 FIELD QUALITY CONTROL

Upon completion of installation of the butterfly valves an acceptance test shall be conducted to

verify the satisfactory operation of the valves. The valves must perform in a manner acceptable

to the Engineer before final acceptance will be made by the Owner.

END OF SECTION

J

1371

7 N

eutro

n R

oad

Dal

las,

Texa

s 75

244

Tel:

972

-490

-766

1Fa

x: 9

72-4

90-7

125

emai

l:vkg

upta@ga

icon

sulting

.com

GAI

Gup

ta &

Ass

oci

ates

, In

c.C

ON

SU

LT

IN

G E

NG

IN

EE

RIN

G

Re

gistra

tio

n N

o. F

-2

59

3

10/30/18

CONDUIT

NO.

DESCRIPTIONCONDUIT TAG

TABLE FOR SECTION 2

CONDUIT

SIZE

1 VF1-P 2"C

VF2-P 2"C PUMP 2 POWER2

VF1-C, VF2-C2"C PUMP 1 AND PUMP 2 CONTROLS3

C-500 2"C

LE-600 MANUFACTURER CABLE TO

CONTROL PANEL

4

C-501 2"C

DISCRETE LEVEL SWITCHES TO

CONTROL PANEL PLC

5

PUMP 1 POWER

CONDUIT

NO.

DESCRIPTIONCONDUIT TAG

TABLE FOR SECTION 1

CONDUIT

SIZE

1 MCASR-P 3"C

SPARE 3"C -2

POWER TO MCC-ASR1

REFER TO SHEET

E-12 FOR WORK

IN THIS AREA

REFER TO SHEET

E-13 FOR WORK

IN THIS AREA

REFER TO SHEET

E-14 FOR WORK

IN THIS AREA

LC-8, 92"C

120V PUMP STATION LIGHTS AND

RECEPTACLES

6

SPARE 2"C SPARE7-8

CONDUIT

NO.

DESCRIPTIONCONDUIT TAG

TABLE FOR SECTION 3

CONDUIT

SIZE

1 C-401 4"C

C-402 4"C

DISCRETE SIGNALS FROM GAC

FILTERS TO GAC CONTROL PANEL

2

C-403 4"C

ANALOG SIGNALS FROM GAC

FILTERS TO GAC CONTROL PANEL

3

SPARE 4"C SPARE4

LC-1, 2, 3, 4, 52"C 120V GAC FLOW TRANSMITTERS5

DISCRETE SIGNALS FROM GAC

FILTERS TO GAC CONTROL PANEL

LC-6, 11, 21, 222"C

120V GAC LIGHTS AND

RECEPTACLES

6

LC-12, 13, 14, 15, 162"C 120V GAC HEAT TRACE7

HA-2, 3, 4, 5, 6

2"C 480V GAC VALVES8

HA-7, 8, 9, 10, 112"C 480V GAC VALVES9

HB-2, 3, 4, 5, 6,2"C 480V GAC VALVES10

HB-7, 8, 9, 10, 112"C11

2"C12

2"C13

SPARE 2"C SPARE14

2"C15

480V GAC VALVES

480V GAC VALVES

480V GAC VALVES

HA-13, 14

HB-12, 13, 14

LC-17, 18, 19, 20COMPRESSOR RECEPTACLES GAC

2"C16 SPARE SPARE

1371

7 N

eutro

n R

oad

Dal

las,

Texa

s 75

244

Tel:

972

-490

-766

1Fa

x: 9

72-4

90-7

125

emai

l:vkg

upta@ga

icon

sulting

.com

GAI

Gup

ta &

Ass

oci

ates

, In

c.C

ON

SU

LT

IN

G E

NG

IN

EE

RIN

G

Re

gistra

tio

n N

o. F

-2

59

3

10/30/18

PC

1371

7 N

eutro

n R

oad

Dal

las,

Texa

s 75

244

Tel:

972

-490

-766

1Fa

x: 9

72-4

90-7

125

emai

l:vkg

upta@ga

icon

sulting

.com

GAI

Gup

ta &

Ass

oci

ates

, In

c.C

ON

SU

LT

IN

G E

NG

IN

EE

RIN

G

Re

gistra

tio

n N

o. F

-2

59

3

10/30/18

SERVICE: 240/120, 1Ø, 3W

MOUNTING: SURFACE - NEMA 4X 316 SS

PANELBOARD: LC

20/1

20/1

9

7

20/1

20/1

20/1

3

1

5

GAC FILTER CONTROL PANEL

LIGHTS PUMP STATION

FIT - 303

FIT - 301

FIT - 500

LOAD

LOCATION: CARBON FILTER AREA

BRKR

SIZE

20/1

20/1

20/1

20/1

20/1

MAINS: 125A/2P

RECEPTACLES PUMP STATION

HEAT TRACE CHLORINE FEED LINE

FIT - 302

FIT - 304

RECEPTACLES GAC FILTER PLANT

FEED: TOP

BUS TYPE: TIN PLATTED COPPER

BUS RATING: 200A

10

LOAD

WIRE

SIZE

10

8

4

2

6

CKT

NO.

CKT

NO.

BRKR

SIZE

WIRE

SIZE

3/4"

3/4"

3/4"

3/4"

3/4"

COND.

SIZE

3/4"

3/4"

3/4"

3/4"

3/4"

COND.

SIZE

SPD: NONE

· CONDUIT SIZE SHOWN IS THE MINIMUM SIZE REQUIRED FOR INDIVIDUAL CIRCUITS. MULTIPLE CIRCUITS MAY BE COMBINED IN A

SINGLE CONDUIT FOR FIELD ROUTING PROVIDED NEC MAXIMUM CONDUIT FILL IS NOT EXCEEDED.

· EACH SINGLE PHASE 120V CIRCUIT SHALL HAVE A SEPARATE NEUTRAL WIRE.

PANELBOARD NOTES:

20/111 LIGHTS GAC FILTER PLANT 20/1HEAT TRACE PV-2 10 123/4"3/4"

20/113 10 HEAT TRACE PV-1 20/1HEAT TRACE PV-4 10 143/4"3/4"

20/115 10 HEAT TRACE PV-3 20/1HEAT TRACE GAC SAMPLE LINE 10 163/4"3/4"

30/2

17

COMPRESSOR NO.1 30/2COMPRESSOR NO.2

18

19 20

20/121 RECEPTACLES GAC 20/1RECEPTACLES GAC - 22--

20/123 - SPARE 20/1SPARE - 24--

10

10

10

10

10

10

10

10

103/4"3/4"

10

10

10

10

1371

7 N

eutro

n R

oad

Dal

las,

Texa

s 75

244

Tel:

972

-490

-766

1Fa

x: 9

72-4

90-7

125

emai

l:vkg

upta@ga

icon

sulting

.com

GAI

Gup

ta &

Ass

oci

ates

, In

c.C

ON

SU

LT

IN

G E

NG

IN

EE

RIN

G

Re

gistra

tio

n N

o. F

-2

59

3

10/30/18

1371

7 N

eutro

n R

oad

Dal

las,

Texa

s 75

244

Tel:

972

-490

-766

1Fa

x: 9

72-4

90-7

125

emai

l:vkg

upta@ga

icon

sulting

.com

GAI

Gup

ta &

Ass

oci

ates

, In

c.C

ON

SU

LT

IN

G E

NG

IN

EE

RIN

G

Re

gistra

tio

n N

o. F

-2

59

3

10/30/18

1371

7 N

eutro

n R

oad

Dal

las,

Texa

s 75

244

Tel:

972

-490

-766

1Fa

x: 9

72-4

90-7

125

emai

l:vkg

upta@ga

icon

sulting

.com

GAI

Gup

ta &

Ass

oci

ates

, In

c.C

ON

SU

LT

IN

G E

NG

IN

EE

RIN

G

Re

gistra

tio

n N

o. F

-2

59

3

10/30/18

1371

7 N

eutro

n R

oad

Dal

las,

Texa

s 75

244

Tel:

972

-490

-766

1Fa

x: 9

72-4

90-7

125

emai

l:vkg

upta@ga

icon

sulting

.com

GAI

Gup

ta &

Ass

oci

ates

, In

c.C

ON

SU

LT

IN

G E

NG

IN

EE

RIN

G

Re

gistra

tio

n N

o. F

-2

59

3

10/30/18

1371

7 N

eutro

n R

oad

Dal

las,

Texa

s 75

244

Tel:

972

-490

-766

1Fa

x: 9

72-4

90-7

125

emai

l:vkg

upta@ga

icon

sulting

.com

GAI

Gup

ta &

Ass

oci

ates

, In

c.C

ON

SU

LT

IN

G E

NG

IN

EE

RIN

G

Re

gistra

tio

n N

o. F

-2

59

3

10/30/18

1371

7 N

eutro

n R

oad

Dal

las,

Texa

s 75

244

Tel:

972

-490

-766

1Fa

x: 9

72-4

90-7

125

emai

l:vkg

upta@ga

icon

sulting

.com

GAI

Gup

ta &

Ass

oci

ates

, In

c.C

ON

SU

LT

IN

G E

NG

IN

EE

RIN

G

Re

gistra

tio

n N

o. F

-2

59

3

10/30/18

1371

7 N

eutro

n R

oad

Dal

las,

Texa

s 75

244

Tel:

972

-490

-766

1Fa

x: 9

72-4

90-7

125

emai

l:vkg

upta@ga

icon

sulting

.com

GAI

Gup

ta &

Ass

oci

ates

, In

c.C

ON

SU

LT

IN

G E

NG

IN

EE

RIN

G

Re

gistra

tio

n N

o. F

-2

59

3

10/30/18

1371

7 N

eutro

n R

oad

Dal

las,

Texa

s 75

244

Tel:

972

-490

-766

1Fa

x: 9

72-4

90-7

125

emai

l:vkg

upta@ga

icon

sulting

.com

GAI

Gup

ta &

Ass

oci

ates

, In

c.C

ON

SU

LT

IN

G E

NG

IN

EE

RIN

G

Re

gistra

tio

n N

o. F

-2

59

3

10/30/18

1371

7 N

eutro

n R

oad

Dal

las,

Texa

s 75

244

Tel:

972

-490

-766

1Fa

x: 9

72-4

90-7

125

emai

l:vkg

upta@ga

icon

sulting

.com

GAI

Gup

ta &

Ass

oci

ates

, In

c.C

ON

SU

LT

IN

G E

NG

IN

EE

RIN

G

Re

gistra

tio

n N

o. F

-2

59

3

10/30/18

A1

A1

A2

A1

A1

A2

1371

7 N

eutro

n R

oad

Dal

las,

Texa

s 75

244

Tel:

972

-490

-766

1Fa

x: 9

72-4

90-7

125

emai

l:vkg

upta@ga

icon

sulting

.com

GAI

Gup

ta &

Ass

oci

ates

, In

c.C

ON

SU

LT

IN

G E

NG

IN

EE

RIN

G

Re

gistra

tio

n N

o. F

-2

59

3

10/30/18

INTERIOR EXTERIOR

WATERTIGHT SEAL

AS SPECIFIED WITH

316SS HARDWARE

316 SS SLEEVE WITH

WATER STOP, SLEEVE

DIAMETER AS REQUIRED

BY SEAL MANUFACTURER

316SS WALL SLEEVE

CONDUIT

1-5/8" 316 SS DOUBLE

SLOTTED CHANNEL

316 SS NUTS,

WASHERS (TYP.)

3/8" (MIN.)

316 SS ALL

THREAD ROD

ALUMINUM

CABLE TRAY

(TYP.)

316 SS

FASTENING

HARDWARE

I-BEAM OF

CHANNEL STEEL

316 SS BEAM

CLAMP

MIN. 1/4"

ALUMINUM OR

10'GA 316 SS

YELLOW WARNING

TAPE OVER ENTIRE

SURFACE

5/16" DIA. MIN ADHESIVE

TYPE AND 316 SS

ANCHOR BOLTS (TYP.)

2

1

1. PROVIDE 1/8" NEOPRENE GASKET WHERE

ALUMINUM IS SELECTED. DO NOT ALLOW

ALUMINUM TO COME INTO DIRECT CONTACT WITH

CONCRETE.

2. CONTRACTOR WILL BE RESPONSIBLE FOR

PROVIDING THE CORRECT SIZE ANCHOR BOLTS

BASED ON LOAD.

NOTES BY SYMBOL " ":

CONDUIT AS

SPECIFIED

PVC COATED

COUPLING (TYP.)

PVC COATED

ALUMINUM

ELBOW (TYP.)

CONCRETE CURB WITH

CHAMFERED EDGES

3" MINIMUM HOUSE

KEEPING PAD

CONCRETE

FLOOR OR SLAB

CONDUITS AS

SPECIFIED OR AS

PLANNED

1

1. THE FIRST FITTING PAST ANY FINISH SURFACE

SHALL BE A MIN. OF 3" ABOVE THAT FINISH

SURFACE.

NOTES BY SYMBOL " ":

ELECTRICAL

EQUIPMENT

ENCLOSURE AS

SPECIFIED

1-5/8" 316 SS

SLOTTED CHANNEL.

ALL CUT EDGES TO

BE FILED SMOOTH

5/16" DIA. MIN

ADHESIVE TYPE

AND 316 SS

ANCHOR BOLTS

1

1. CONTRACTOR SHALL BE RESPONSIBLE FOR

PROVIDING THE CORRECT SIZE ANCHOR BOLTS

BASED ON LOAD

NOTES BY SYMBOL " ":

1'-6"

WP/GFI

IN-USE COVER

UNISTRUT

1

1. THE FIRST FITTING PAST ANY FINISH SURFACE

SHALL BE A MIN. OF 3" ABOVE THAT FINISH

SURFACE.

NOTES BY SYMBOL " ":

PVC ADAPTERREBAR AS PER

DUCTBANK

DETAILS

EXISTING/NEW

FOOTING OR

FOUNDATION

COMPRESSIBLE

JOINT FILLER

PVC COATED

ALUMINUM CONDUIT

REFER TO APPLICABLE

WALL PENETRATION

DETAILS

ALUMINUM

CONDUIT

J-BOX

PULL BOX OR TERMINAL

CABINET AS INDICATED

ON THE DRAWINGS AND

SPECIFICATIONS

ALUMINUM

EXPANSION-

DEFLECTION

FITTING

3

1

4

2

CONCRETE

ENCASEMENT AS

PER DUCTBANK

DETAILS

PVC CONDUIT

AS SHOWN

ON PLANS

1. SEAL ALL CONDUITS ENTERING ENCLOSURES

WITH REMOVABLE SILICON CAULK.

2. ALLOW MINIMUM OF 12" OF WIRE SLACK IN

JUNCTION BOX TO ACCOMMODATE EXPANSION

JOINT.

3. APPLY RUBBER ELECTRICAL TAPE TO ALL

EXPOSED METAL CONDUIT OR CONDUIT THREADS.

EXTEND TAPE A MINIMUM 2" IN BOTH DIRECTIONS

BEYOND EXPOSED CONDUIT.

4. THE FIRST FITTING PAST ANY FINISH SURFACE

SHALL BE A MIN. OF 3" ABOVE THAT FINISH

SURFACE.

5. PROVIDE DEFLECTION FITTING ONLY WHEN

DUCTBANK APPROACH TO BUILDING IS NOT 90°

FROM BUILDING.

NOTES BY SYMBOL " ":

CONCRETE SLOPED

AWAY FROM BLDG. 1"

CHAMFER ALL AROUND

3"

(MIN.)

PVC

CONDUIT

PVC COATED

ALUMINUM LONG

SWEEP ELBOW

5

1371

7 N

eutro

n R

oad

Dal

las,

Texa

s 75

244

Tel:

972

-490

-766

1Fa

x: 9

72-4

90-7

125

emai

l:vkg

upta@ga

icon

sulting

.com

GAI

Gup

ta &

Ass

oci

ates

, In

c.C

ON

SU

LT

IN

G E

NG

IN

EE

RIN

G

Re

gistra

tio

n N

o. F

-2

59

3

10/30/18

4"

1"

12"

12"

FORM SQUARE

ALL AROUND

MONUMENT CASE WITH COVER

OLDCASTLE 03 RT OR EQUAL.

FINISHED GRADE

CONCRETE ALL

AROUND

EXOTHERMIC

WELD

GROUND ROD

GRAVEL FILL

CONTINUOUS #4/0 BARE

COPPER GROUND

CABLE, SIZE AS

INDICATED ON PLANS

EXOTHERMIC

WELD (TYP)

#4/0 BARE

COPPER WIRE

3/4"X10'-0" COPPER

CLAD STEEL

GROUND ROD

FINISH GRADE

6"

3"

1'-0"

MIN.

4'-0"

MIN.

1'-0"

MIN.

316 SS HINGED

SUNSHIELD

ROUND

CORNERS (TYP.)

EQUIPMENTS AS

SPECIFIED

ALUMINUM

BACKPLATE

316 SS

UNISTRUT

FOUR 3/8" DIA.

316 SS ADH

ANCHOR, 4"

EMBED (TYP.)

3/4" NON-SHRINKING

GROUT (ASTM C1107)

EQUIPMENT PAD AS

PER STRUCTURAL

DETAILS

ALL SUPPORTING

HARDWARE SHALL

BE 316 SS

INSULATED

GROUND WIRE

GRADE

THERMAL

WELD

GROUND ROD

1" CHAMFER

ALL AROUND

CONCRETE

EQUIPMENT PAD

4

1

3

2

1. INSTALL STRUT CHANNEL AS REQUIRED TO

PROVIDE FOR RIGIDITY.

2. PROVIDE CONCRETE PAD IN UNPAVED AREAS. 6"

THICK, 3000PSI CONCRETE SLAB. REINFORCE

WITH #4@12" ON CENTER EACH WAY, ON 3"

CHAIRS.

3. CONTRACTOR WILL BE RESPONSIBLE FOR

PROVIDING THE CORRECT SIZE ANCHOR BOLTS

ON LOAD. (TYPICAL)

4. SECURE GROUND WIRE TO EQUIPMENT RACK LEG.

BOLT GROUND WIRE TO BACKPLATE WITH

APPROVED GROUND LUGS.

NOTES BY SYMBOL " ":

6"

MIN.

TOP VIEW

316 SS HINGED

1371

7 N

eutro

n R

oad

Dal

las,

Texa

s 75

244

Tel:

972

-490

-766

1Fa

x: 9

72-4

90-7

125

emai

l:vkg

upta@ga

icon

sulting

.com

GAI

Gup

ta &

Ass

oci

ates

, In

c.C

ON

SU

LT

IN

G E

NG

IN

EE

RIN

G

Re

gistra

tio

n N

o. F

-2

59

3

10/30/18

G

R

O

U

N

D

OLDCASTLE

03 RT LID

GROUND WIRE

3/4"x10'-0" COPPER CLAD

STEEL GROUND ROD

ISOMETRIC VIEW

ISOMETRIC VIEW

1371

7 N

eutro

n R

oad

Dal

las,

Texa

s 75

244

Tel:

972

-490

-766

1Fa

x: 9

72-4

90-7

125

emai

l:vkg

upta@ga

icon

sulting

.com

GAI

Gup

ta &

Ass

oci

ates

, In

c.C

ON

SU

LT

IN

G E

NG

IN

EE

RIN

G

Re

gistra

tio

n N

o. F

-2

59

3

10/30/18

1371

7 N

eutro

n R

oad

Dal

las,

Texa

s 75

244

Tel:

972

-490

-766

1Fa

x: 9

72-4

90-7

125

emai

l:vkg

upta@ga

icon

sulting

.com

GAI

Gup

ta &

Ass

oci

ates

, In

c.C

ON

SU

LT

IN

G E

NG

IN

EE

RIN

G

Re

gistra

tio

n N

o. F

-2

59

3

10/30/18

1371

7 N

eutro

n R

oad

Dal

las,

Texa

s 75

244

Tel:

972

-490

-766

1Fa

x: 9

72-4

90-7

125

emai

l:vkg

upta@ga

icon

sulting

.com

GAI

Gup

ta &

Ass

oci

ates

, In

c.C

ON

SU

LT

IN

G E

NG

IN

EE

RIN

G

Re

gistra

tio

n N

o. F

-2

59

3

10/30/18

1371

7 N

eutro

n R

oad

Dal

las,

Texa

s 75

244

Tel:

972

-490

-766

1Fa

x: 9

72-4

90-7

125

emai

l:vkg

upta@ga

icon

sulting

.com

GAI

Gup

ta &

Ass

oci

ates

, In

c.C

ON

SU

LT

IN

G E

NG

IN

EE

RIN

G

Re

gistra

tio

n N

o. F

-2

59

3

10/30/18