TOWN OF JUPITER JPD Headquarters and Datacenter Low ...

115
MB TOWN OF JUPITER JPD Headquarters and Datacenter Low Voltage Cabling Award DATE: December 9, 2019 TO: Honorable Mayor and Members of Town Council THRU: Matt Benoit, Town Manager FROM: Karl Craig, Information Systems Director SUBJECT: JPD Headquarters and Datacenter Low Voltage Cabling Award EXECUTIVE SUMMARY: Town staff is requesting the Town Council’s approval to award the successful low bidder, Accelerated Technologies the contract to furnish and install the low voltage cabling throughout the building and uninterruptible power supplies (UPS) for the datacenter in the amount of $271,819.75. Publicly advertised competitive bids were solicited and received via Demandstar from five (5) companies and evaluated for accuracy, completeness, ability to perform the work, and ability to meet the demands of the construction schedule. The evaluation committee discussed and rated each submittal using the selection criteria that was provided in the RFP including references, proposal, and total bid to arrive at a final score and selection. Based on a high score of 298 out of a possible 300 points the committee unanimously selected Accelerated Technologies at the awardee pursuant to Town Council’s approval. This project consists of all materials and labor to outfit the new JPD Headquarters and Datacenter for all cabling, jacks, faceplates, wire management, etc. to create the physical internal computer network to run all desktop computers, phones, the datacenter, and security cameras making the building operational. This project is fully funded and included in the FY2020 budget approved. RECOMMENDATION: Staff recommends the Town Council’s approval for RFP-IS-100119 New Jupiter Police Department HQ & Data Center Low Voltage Cabling in the amount of $271,819.75 to Accelerated Technologies. Strategic Priority: New Jupiter Police Department Head Quarters and Data Center Attachments: RFP-IS-100119 New Jupiter Police Department HQ & Data Center Low Voltage Cabling Town of Jupiter – RFP-IS-100119 – Acc. Tech Final Proposal RFP-IS-100119 Bid Tabulation Selection Committee Summary Scoring Sheet Selection Committee Final Meeting Minutes TOJ Police Department HQ & Data Center Statement of Work Funding Source: X Approved in Budget $271,819.75 Sources: 31090019-564000 G0005 SR

Transcript of TOWN OF JUPITER JPD Headquarters and Datacenter Low ...

MB

TOWN OF JUPITER JPD Headquarters and Datacenter Low Voltage Cabling Award

DATE: December 9, 2019 TO: Honorable Mayor and Members of Town Council THRU: Matt Benoit, Town Manager FROM: Karl Craig, Information Systems Director SUBJECT: JPD Headquarters and Datacenter Low Voltage Cabling Award

EXECUTIVE SUMMARY: Town staff is requesting the Town Council’s approval to award the successful low bidder, Accelerated Technologies the contract to furnish and install the low voltage cabling throughout the building and uninterruptible power supplies (UPS) for the datacenter in the amount of $271,819.75.

Publicly advertised competitive bids were solicited and received via Demandstar from five (5) companies and evaluated for accuracy, completeness, ability to perform the work, and ability to meet the demands of the construction schedule. The evaluation committee discussed and rated each submittal using the selection criteria that was provided in the RFP including references, proposal, and total bid to arrive at a final score and selection. Based on a high score of 298 out of a possible 300 points the committee unanimously selected Accelerated Technologies at the awardee pursuant to Town Council’s approval.

This project consists of all materials and labor to outfit the new JPD Headquarters and Datacenter for all cabling, jacks, faceplates, wire management, etc. to create the physical internal computer network to run all desktop computers, phones, the datacenter, and security cameras making the building operational.

This project is fully funded and included in the FY2020 budget approved.

RECOMMENDATION: Staff recommends the Town Council’s approval for RFP-IS-100119 New Jupiter Police Department HQ & Data Center Low Voltage Cabling in the amount of $271,819.75 to Accelerated Technologies.

Strategic Priority: New Jupiter Police Department Head Quarters and Data Center

Attachments: • RFP-IS-100119 New Jupiter Police Department HQ & Data Center Low Voltage Cabling • Town of Jupiter – RFP-IS-100119 – Acc. Tech Final Proposal • RFP-IS-100119 Bid Tabulation • Selection Committee Summary Scoring Sheet • Selection Committee Final Meeting Minutes • TOJ Police Department HQ & Data Center Statement of Work

Funding Source: X Approved in Budget $271,819.75 Sources: 31090019-564000 G0005

SR

Request for Proposal

New Jupiter Police Department HQ

.

& Data Center Low Voltage Cabling

RFP–IS-100119

10/1/2019

Contents Contents.........................................................................................................................................................1

TOWN OF JUPITER Request for Proposal............................................................................................3

SECTION I......................................................................................................................................................4

REQUEST FOR PROPOSAL (RFP) GUIDELINES..................................................................................4

1.0 Introduction..........................................................................................................................................4 1.1 Proposal Submission and Withdrawal................................................................................................. 4 1.1.1 Right to Reject.................................................................................................................................. 4 1.1.2 Proposal Opening Extension............................................................................................................ 4 1.1.3 Proposal Withdrawal ........................................................................................................................ 4 1.2 Development Costs ............................................................................................................................. 5 1.3 Inquiries ............................................................................................................................................... 5 1.4 Addendum ........................................................................................................................................... 5 1.5 Contract Awards.................................................................................................................................. 5 1.6 Contractual Agreement ...................................................................................................................... 6 1.7 Selection Process................................................................................................................................ 6 1.8 Public Records .................................................................................................................................... 6 1.9 Public Entity Crimes............................................................................................................................ 6 1.10 Code Of Ethics .................................................................................................................................. 6 1.11 Rights and Privileges ...................................................................................................................... 6 1.12 Lobbying/Cone of Silence ................................................................................................................. 6 1.13 Disclosure and Disclaimer................................................................................................................ 7 1.14 Quotation Contents .......................................................................................................................... 8 1.15 Audits................................................................................................................................................. 8 1.16 Taxes................................................................................................................................................. 8 1.17 Plans and Specifications ................................................................................................................... 8 1.18 Equal Opportunity.............................................................................................................................. 8 1.19 Request for Records ......................................................................................................................... 8 1.20 Subcontracting or Assigning of the Contract .................................................................................. 9 1.21 Discrimination .................................................................................................................................... 9 1.23 Town’s Public Relations Image ....................................................................................................... 9 1.24 Patent Fees, Royalties, and Licenses............................................................................................... 9 1.25 Familiarity with Laws ........................................................................................................................ 9 1.26 Damage to Property .......................................................................................................................... 9

SECTION II.................................................................................................................................................. 10

EVALUATION OF PROPOSALS.............................................................................................................. 10 2.0 Evaluation Method and Criteria......................................................................................................... 10 2.1 Selection............................................................................................................................................ 10

SECTION III ................................................................................................................................................ 11 3.0 Proposal Response Format .............................................................................................................. 11 3.1 Statement of Qualifications ............................................................................................................... 11 3.2 Client References.............................................................................................................................. 11 3.3 Exceptions and Deviations ................................................................................................................ 11 3.4 Pricing Quote..................................................................................................................................... 12

SECTION IV ................................................................................................................................................ 13 4.0 Requirements and Specifications - Communications .................................................................... 13 4.1 Requirements and Specifications – Communications Copper Horizontal Cabling ........................ 22 4.2 Requirements and Specifications – Communications Patch Cords............................................... 25 4.3 Requirement and Specifications – Fire-stopping for Communications Systems ........................... 28 4.4 Requirements and Specifications - Grounding and Bonding for Communications Systems......... 34 4.5 Requirements and Specifications - Pathways for Communications Systems................................ 37 4.6 Requirements and Specifications – Identification for Communications Systems .......................... 42 4.7 Requirements and Specifications – Commissioning of Communications...................................... 43

4.8 Requirements and Specifications – Communications Entrance Protection................................... 48 4.9 Requirements and Specifications – Communications Terminations Blocks and Patch Panels..... 51 4.10 Requirements and Specifications – Communications Cable Management and Ladder Rack ...... 56 4.11 Requirements and Specifications – Communications Rack Mounted Power Distribution............. 60 4.12 Requirements and Specifications – Communications Optical Fiber Backbone Cabling.............. 62 4.12 Requirements and Specifications – Communications Faceplates and Connectors ...................... 69

**Appendices** ........................................................................................................................................ 72

TOWN OF JUPITER Request for Proposal

New Jupiter Police Department HQ & Data Center Low Voltage Cabling

The Town of Jupiter is requesting proposals for commercial grade materials, equipment, cabling and services to outfit the entire building and exterior with low voltage cabling and materials for the new Jupiter Police Department HQ & Data Center. Proposals are expected to provide all materials and installation of all necessary cabling, connectors, multimode fiber, patch panels, wall plates, cable management, cable trays, patch cables, racks, cabinets, and in-rack UPS for the building and data center, etc. Proposals should be from qualified vendors located in the United States which strictly meet all of the Requirements & Specifications listed in this document, including Design Drawings, Terms & Conditions, Specification Sheets, Material Lists, and Appendices.

Some quantities for the Data Center are known and proposals can be based on the following:

• Quantity of cabinets needed for Data Center = 10 (all devices, ups, patch panels)

• UPS Power = In-cabinet solution desired (see appendix H)

• Estimated wattage consumption in Data Center = 49 kw

• Equipment to be located in Data Center: (listed for power reference)

Manufacturer Model# Watts (Max) BTU /Hour

DELL FX2 4000 950 DELL FX2 4000 950 DELL FX2 4000 950 DELL FX2 4000 950 DELL FX2 4000 950 Avaya Dell PE630 x 2 3000 16400 DELL - camaras Dell PE630 1500 8200 DELL EMC SCv3020 San 2756 5067 DELL EMC SCv300 San 1200 2047 DELL EMC SCv300 San 1200 2047 Brocade Ruckus 7250 x 15 13200 4912.5 Brocade Ruckus 7750 x 2 2000 2232 Fortigate Firewall 400 613 Unitrends 928S 1840 3750 Unitrends 8080S 1840 3750 DELL KVM x 3 60 204.73

TOTAL 48996 53973.23

Proposals are to be based on the building design drawings submitted as a part of this request.

Questions regarding this quotation will be answered by addendum only. Please send all questions to King Wekenmann by fax (561) 741-2616 or email [email protected] and include TOJ Police Department HQ & Data Center Low Voltage Cabling in the subject line. RFQ Specifications are avai lable for download on www.demandstar.com beginning October 18, 2019. The Town of Jupiter reserves the right to waive any irregularities and to reject any and all proposals. The Town of Jupiter is an equal opportunity employer.

TOWN OF JUPITER Request for Proposal

RFP–IS-100119

New Jupiter Police Department HQ & Data Center Low Voltage Cabling

SECTION I

REQUEST FOR PROPOSAL (RFP) GUIDELINES

1.0 Introduction The Town of Jupiter is building a new Police Department Headquarters which will fully serve police day to day operations, house a hardened Data Center to run all Town computer operations and services. The building will also function as the Emergency Operations Center. We are requesting proposals from companies (“Respondents”) to procure the materials and services necessary to install all low voltage cabling, components, and accessories per building design drawings approved for the new Jupiter Police Department Headquarters and Data Center, located in Jupiter, Florida.

1.1 Proposal Submission and Withdrawal The deadline to receive proposals is Monday 5:00 p.m. EST, November 4, 2019. The proposals may be submitted electronically via email or printed and delivered to the Town of Jupiter at the following address.

Email Submission: [email protected] and must include TOJ Police Department HQ & Data Center Low Voltage Cabling in the subject line.

Printed Copy Submission: Town of Jupiter Information Systems Department Attention: King Wekenmann RFP–IS-100119 210 Military Trail Jupiter, FL 33458

All Proposals must be received by the date and time specified in the RFP. The Submission time must be and shall be scrupulously observed. Under no circumstances shall Proposals submitted after the time specified be considered. The Town shall in no way be responsible for delays caused by any occurrence. NOTE: Submission by telephone, telegram or facsimile shall not be accepted. Submissions will only be accepted as stated in Section 1of this document.

1.1.1 Right to Reject – The Town reserves the rights to waive irregularities, reject and/or accept any and all submissions, in whole or in part, or take such other action as serves the best interest of the Town.

1.1.2 Proposal Opening Extension – The Town reserves the right to issue an addendum extending the RFP opening date in the event it determines, in its sole discretion that an inadequate number of submissions have been received, including, but not limited to where it has received no submissions, or only one incomplete or inferior submission .

1.1.3 Proposal Withdrawal -Respondents may withdraw their Proposals by notifying the Town in writing at any time prior to the deadline for submittal. After the deadline, the proposal will constitute an irrevocable offer, for a period of six (6) months. Once opened, proposals become a record of the Town and will not be returned to the Respondents.

A copy of the complete RFP package may be obtained from the Town’s online Bid and Quote System located at http://www.jupiter.fl.us/246/Bids-for-Town-Projects or, from the Information Systems Department at Town Hall, at 210 Military Trail, Jupiter, FL 33458. For additional information, please contact: King Wekenmann, via fax (561) 741-2616 or email [email protected] and must include TOJ Police Department HQ & Data Center Low Voltage Cabling in the subject line.

1.2 Development CostsNeither the Town nor its representatives shall be liable for any expenses incurred in connection with preparation of a response to this Request for Proposal. Respondents should prepare their Proposal simply and economically, providing a straightforward and concise description of the Respondent’s ability to meet the requirements of the RFP.

1.3 Inquiries Interested Respondents may contact King Wekenmann, via fax (561) 741-2616 or email [email protected] and must include TOJ Police Department HQ & Data Center Low Voltage Cabling in the subject line. The Town contact will receive written requests for clarification concerning the meaning or interpretations of the RFP, until Friday 5:00 p.m. EST, October 25, 2019. Town personnel are authorized only to direct the attention of prospective Respondent(s) to various portions of the RFP so that they may read and interpret such for themselves.

No employee of the Town is authorized to interpret any portion of this RFP or give information as to the requirements of the RFP in addition to what is contained in the written RFP document or subsequent addendums.

1.4 Addendum The Town may record its response to inquiries and any supplemental instructions in the form of written addenda. The Town may provide written addenda up to five (5) calendar days before the date fixed for receiving the Proposals. Respondents may contact the Town to ascertain whether any addenda have been issued or review the online RFP on the DemandStar system. Any oral explanation given with regard to the RFP prior to opening will not be binding.

All Respondents are expected to carefully examine the RFP documents. Any ambiguities or inconsistencies should be brought to the attention of King Wekenmann, ([email protected]), through written communication prior to the opening of the Proposals.

1.5 Contract Awards The Town anticipates entering into an Agreement with the Respondent who submits the proposal judged by the Town to be most advantageous.

The Town reserves the right to accept or reject any or all Proposals, with or without cause, to waive technicalities or to accept the proposal which, in its sole judgment, best serves the interest of the Town, or to award a contract to the next most qualified Respondent if the successful company does not execute a contract within thirty (30) days after the award of the RFP. The Town also reserves the right to abandon the project and/or to solicit and re-advertise for other proposals.

The Respondent(s) understand that this RFP does not constitute an offer or an Agreement with the Respondent. An offer or Agreement shall not be deemed to exist and is not binding until proposals are reviewed, accepted by appointed staff, the best proposal has been identified, approved by the appropriate level of authority within the Town and executed by all parties.

Any proposal may be withdrawn until the date and time set above for the submission of the proposals. Any quotation not so withdrawn shall constitute an irrevocable offer for a period of six (6) months to provide to the Town the services set forth in this Request for Proposal.

1.6 Contractual Agreement This RFP shall be included and incorporated in the final award. The order of contractual precedence will be the Contract or Price Agreement document, original Terms and Conditions, and contractor response. Any and all legal action necessary to enforce the award will be held in Palm Beach County and the contractual obligations will be interpreted according to the laws of Florida. Any additional contract or agreement requested for consideration by the Respondent must be attached and enclosed as part of the quotation.

1.7 Selection Process The P r o p o s a l s will be evaluated and assigned points; the firm with the highest number of points will be ranked first. However, nothing herein will prevent the Town from assigning work to any firm deemed responsive and responsible.

The Town reserves the right to further negotiate any Proposal, including price, with the highest rated Respondent. If an agreement cannot be reached with the highest rated Respondent, the Town reserves the right to negotiate and recommend award to the next highest Respondent or subsequent Respondents until an agreement is reached.

1.8 Public Records Upon award recommendation or ten (10) days after opening, whichever occurs first, proposals become “public records” and shall be subject to public disclosure consistent with Chapter 119 Florida Statutes. Respondent(s) must invoke the exemptions to disclosure provided by law in the response to the RFP, and must identify the data or other materials to be protected, and must state the reasons why such exclusion from public disclosure is necessary. Document files may be examined, during normal working hours.

1.9 Public Entity Crimes Award will not be made to any person or affiliate identified on the Department of Management Services’ "Convicted Vendor List”. This list is defined as consisting of persons and affiliates who are disqualified from public contracting and purchasing process because they have been found guilty of a public entity crime. No public entity shall award any contract to, or transact any business in excess of the threshold amount provided in Section 287.017 Florida Statutes for Category Two (currently $25,000.00) with any person or affiliated on the "Convicted Vendor List” for a period of thirty-six (36) months from the date that person or affiliate was placed on the "Convicted Vendor List” unless that person or affiliate has been removed from the list. By signing and submitting the RFP forms, Respondent attests that they have not been placed on the “Convicted Vendor List”.

1.10 Code Of Ethics If any Respondent violates or is a party to a violation of the code of ethics of the Town of Jupiter or the State of Florida with respect to this RFP, such Respondent may be disqualified from performing the work described in this proposal or from furnishing the goods or services for which the proposal is submitted and shall be further disqualified from submitting any future quotations and proposals for work, goods or services for the Town of Jupiter.

1.11 Rights and Privileges Rights and privileges granted by the Town shall not be assigned or transferred in any manner whatsoever without written approval of the Town Council. At all times during the term of the contract the Contractor shall act as an independent contractor and at no time shall the Respondent be considered an agent or partner of the Town. The Respondent shall obtain and pay for all permits, licenses, Federal, State and Local taxes chargeable to its operation.

1.12 Lobbying/Cone of Silence Respondents are advised – once the Town of Jupiter releases/publishes a Request for Proposal, Request for Qualification bid or any other competitive solicitation the respondent or anyone representing the respondent are prohibited from communicating with any Town Council members, Town Staff and any Member of a Town Selection Committee.

Exception – The only exception to this communication: the Respondent and/or their representative may communicate in writing to the contact person listed in the bidding documents.

The Cone of Silence shall terminate at the time the Town Council or Town Department authorized to act on behalf of the Council, awards or approves a contract, rejects all responses, or otherwise takes action which ends the solicitation process. Note: The Town of Jupiter is under the Palm Beach County Lobbying Registration Ordinance Effective April 2, 2012. Violators of the Cone of Silence are punishable by a fine of $250 per violation.

1.13 Disclosure and Disclaimer Any action taken by the Town in response to proposals made pursuant to this RFP or in making any award or failure or refusal to make any award pursuant to such proposals, or in any cancellation of award, or in any withdrawal or cancellation of this RFP, either before or after issuance of an award, shall be without any liability or obligation on the part of the Town or their advisors.

In its sole discretion, the Town may withdraw this RFP either before or after receiving proposals, may accept or reject Proposals, and may accept Proposals which deviate from the RFP. In its sole discretion, the Town may determine the qualifications and acceptability of any party or parties submitting Proposals in response to this RFP.

Following submission of a Proposal, the Respondent agrees to promptly deliver such further details, information and assurances, including, but not limited to, financial and disclosure data, relating to the proposal and/or the Respondent, including the Respondent’s affiliates, officers, directors, shareholders, partners and employees, as requested by the Town.

The information contained herein is provided solely for the convenience of Respondent. It is the responsibility of a Respondent to assure itself that information contained herein is accurate and complete. Neither the Town, nor their advisors provide any assurances as to the accuracy of any i n f o r m a t i o n i n t h i s R F P . Any reliance on the contents of this RFP, or on any communications with Town representatives or advisors, shall be at each Respondent’s own risk. Respondents should rely exclusively on their own investigations, interpretations and analyses in connection with this matter. The RFP is being provided by the Town without any warranty or representation, express or implied, as to its content; accuracy or completeness and no Respondent or other party shall have recourse to the Town if any information herein contained shall be inaccurate or incomplete. No warranty or representation is made by the Town that any Proposal conforming to these requirements will be selected for consideration, negotiation or approval.

The Town, and its representatives shall have no obligation or liability with respect to this RFP, or the selection and award process contemplated hereunder. Neither the Town nor its representatives warrant or represent that any award or recommendation will be made as a result of the issuance of this RFP. All costs incurred by a Respondent in preparing and responding to this RFP are the sole responsibility of the Responder. Any recipient of this RFP who responds hereto fully acknowledges all the provisions of this Discloser and Disclaimer and agrees to be bound by the terms hereof. Any quotation submitted pursuant to this RFP is at the sole risk and responsibility of the party submitting such proposal.

This RFP is made subject to correction of errors, omissions, or withdrawal without notice. Information contained in the RFP is for guidance only and each recipient hereof is cautioned and advised to independently verify all of such information. In the event of any differences between this Disclosure and Disclaimer and the balance of the RFP, the provisions of this Disclosure and Disclaimer shall govern.

1.14 Quotation Contents All material submitted becomes the property of the Town of Jupiter. The Town has the right to use any or all ideas presented in any reply to this RFP. Selection or rejection of the proposal does not affect this right.

1.15 Audits The Inspector General of Palm Beach County has the authority to investigate and audit matters relating to the negotiation and performance of this Contract and in furtherance thereof may demand and obtain records and testimony from the Responder and its subcontractors and lower tier subcontractors. The Requester understands and agrees that in addition to other remedies and consequences provided by law, the failure of the Requester or its subcontractors or lower tier subcontractors to fully cooperate with the Office of Inspector General of Palm Beach County when requested may be deemed by the municipality to be material breach of this contract justifying its termination. The Office of Inspector General in Palm Beach County is established by Palm Beach County Code Section 2-421-2-440. Failure to cooperate with the Inspector General of Palm Beach County shall be in violation of Palm Beach Code, Section 2-421-2-440, and be punished pursuant to Section 125.69, Florida Statutes, in the same manner as a second degree misdemeanor.

1.16 Taxes The successful Respondent shall pay all applicable sales, consumer use and other similar taxes required by law.

1.17 Plans and SpecificationsThe apparent silence of the specifications as to any detail, or the apparent omission from the Specifications of a detailed description concerning any point, shall be regarded as meaning that only the best solution is to prevail and that only materials of the finest quality are to be provided. All interpretations of the specifications shall be made on the basis of this statement.

For the purpose of evaluation, the Respondent must indicate any variance or exceptions to the stated specifications no matter how slight. Deviations should be explained in detail. Absence of variations and/or corrections will be interpreted to mean that the Respondent meets all the specifications in every respect.

See plans and specifications in addendum section for all requirements, material specifications, locations, etc.

1.18 Equal OpportunityThe Town of Jupiter recognizes fair and open competition as a basic tenet of public procurement. Companies doing business with the Town are prohibited from discriminating on the basis of race, color, creed, religion, sex, national origin, age, physical disability, marital status, familial status, veteran status, sexual orientation, or any form of unlawful discrimination.

1.19 Request for Records1. This Agreement is subject to and governed by the laws of the State of Florida, including without

limitation Chapter 119, Florida Statutes, which generally makes public all records or other writings made by or received by the parties. The Contractor acknowledges its legal obligation to comply with § 119.0701, Florida Statutes.

2. A request to inspect or copy public records relating to a public agency’s contract for services must be made directly to the public agency. If the public agency does not possess the requested records, the public agency shall immediately notify the contractor of the request, and the contractor must provide the records to the public agency or allow the records to be inspected or copied within a reasonable time.

3. If a contractor does not comply with the public agency’s request for records, the public agency shall enforce the contract provisions in accordance with the contract.

4. A contractor who fails to provide the public records to the public agency within a reasonable time may be subject to penalties under s. 119.10.

IF THE CONTRACTOR HAS QUESTIONS REGARDING THE APPLICATION OF CHAPTER 119, FLORIDA STATUTES, TO THE CONTRACTOR’S DUTY TO PROVIDE PUBLIC RECORDS RELATING TO THIS CONTRACT, CONTACT THE CUSTODIAN OF PUBLIC RECORDS: King Wekenmann, Tel.: 561-741-2351, email: [email protected], Mailing address: Information Systems, 210 Military Trail, Jupiter, FL 33458.

1.20 Subcontracting or Assigning of the Contract The Selected Respondent(s) shall not subcontract, sell, transfer, assign or otherwise dispose of the Contract or any portion thereof, or of the work provided for therein, or of his right, title or interest therein, to any person, firm or corporation without the written consent of the Town. Each Respondent shall list all subcontractors and the work provided by the suppliers with their submission.

1.21 Discrimination An entity or affiliate who has been placed on the discriminatory vendor list may not submit a proposal o r q u o t a t i o n on a contract to provide goods or services to a public entity, may not submit a proposal or quotation on a contract with a public entity for the construction or repair of a public building or public work, may not submit proposals or quotation on leases of real property to a public entity, may not award or perform work as a contractor, supplier, subcontractor, or consultant under contract with any public entity, and may not transact business with any public entity.

1.23 Town’s Public Relations Image Selected Respondent’s personnel shall at all times handle themselves in a professional manner and handle complaints and all contact with the public with due regard to the Town’s relationship with the public. Any personnel in the employ of the Selected Respondent(s) involved in the execution of work that is deemed to be conducting themselves in an unacceptable manner shall be removed from the project at the request of the Town or its representative.

1.24 Patent Fees, Royalties, and Licenses If the Selected Respondent(s) requires or desires to use any design, trademark, device, material or process covered by letters of patent or copyright, the Selected Respondent(s) and his surety shall indemnify and hold harmless the Town from any and all claims for infringement by reason of the use of any such patented design, device, trademark, copyright, material or process in connection with the work agreed to be performed and shall indemnify the Town from any cost, expense, royalty or damage which the Town may be obligated to pay by reason of any infringement at any time during the prosecution of or after completion of the work.

1.25 Familiarity with Laws The Selected Respondent(s) is assumed to be familiar with all Federal, State and local laws, ordinances, rules and regulations that may affect the work. Ignorance on the part of a Selected Respondent shall in no way relieve it from any responsibility to comply with the law.

1.26 Damage to Property The Selected Respondent(s) shall preserve from damage all property along the line of work, or which is in the vicinity of or is in any way affected by the work, the removal, or destruction of which is not called for by the plans. This applies to public and private property, public and private utilities, trees, shrubs, crops, signs, monuments, fences, guardrail, pipe and underground structures, public highways, etc. Whenever such property is damaged due to the activities of the Selected Respondent(s), it shall be immediately restored to a condition equal or better to that existing before such damage or injury was done by Selected Respondent(s), and at Selected Respondent(s) expense. The Selected Respondent’s special attention is directed to protection of survey monuments, horizontal, vertical or property corners, located within the limits of construction.

TOWN OF JUPITER Request for Proposal

RFP–IS-100119 New Jupiter Police Department HQ & Data Center Low Voltage Cabling

SECTION II

EVALUATION OF PROPOSALS

2.0 Evaluation Method and Criteria General – The Town shall be the sole judge of their own best interests, the proposals, and the resulting negotiated agreement. The Town’s decisions will be final.

Selection of a Respondent to provide the hardware, materials, and services sought herein will be based on the Town’s evaluation criteria and will include, but shall not be limited to, consideration of the following:

CRITERION POINTS

A

References: Score based on references provided after checking for accuracy and confirmation of successful completion of representative work.

50

B

Total Cost: Prices including labor for complete solution to outfit the building and Data Center Hot Isle Containment solution per the plans, engineering and architectural drawings, material specification sheets, etc.

40

C

Proposal Submittal:Quality of proposal response.

10

Total Maximum Points 100

Based on the preliminary ranking of the written Proposal(s) received, the Town will select the Proposal that is deemed to be the best fit with regard to both meeting the requirements and total cost.

2.1 Selection Selection and award of contract shall be done in accordance with the State of Florida and Town policies and procedures, the Town will evaluate, rank all qualified RFP(s) and recommend to the Town Council the selected proposal. The Town’s decisions will be final.

.

TOWN OF JUPITER

10

Request for Proposal RFP–IS-100119

New Jupiter Police Department HQ & Data Center Low Voltage Cabling

SECTION III

3.0 Proposal Response FormatTo facilitate the analysis of responses to the RFP, the Proposer is required to prepare their proposals in accordance with the instructions outlined in this section. Responses may be emailed or printed and delivered to the address(s) indicated in Section 1. All responses shall include the following information

Section Title 1 Statement of Qualifications 2 Client References 3 Exceptions and Deviations 4 Pricing Quote(s)

3.1 Statement of Qualifications This part of the response to the RFP should be limited to a brief narrative not to exceed two (2) pages describing the qualifications of the Respondent to meet the requirements of the proposal and completion of the work on time, within budget, with comparative example of past successes.

3.2 Client References This part of the response to the RFP shall include the Client Reference information requested. Respondent shall include a minimum of three (3) references of successfully completed job of similar size and scope and not more than 6 years old.

References are to include: Name of Company/Organization: Contact Name: Contact Title: Contact Phone: Contact Email: Type of Facility Constructed: Size of Construction Project (Sq. Ft.): Amount of Contract Award: Time Frame of Project: (Begin / Complete)

3.3 Exceptions and Deviations This part of the response to the RFP shall include any claims, in list form, of exceptions or deviations from the requirements of the RFP. If any exceptions or deviations are claimed the

11

Respondent must cite the specific section, subsection, and provide a reason and/or reasonable substitute.

3.4 Pricing Quote This part of the response to the RFP shall include the Respondent’s best and final offer price quote including all parts, materials, labor to complete the job as stated in this RFP and determined by thorough analysis of this RFP including all supplied design drawing and materials.

12

TOWN OF JUPITER Request for Proposal

RFP–IS-100119

New Jupiter Police Department HQ & Data Center Low Voltage Cabling

SECTION IV

4.0 Requirements and Specifications - Communications

PART 1 - GENERAL

1.01 GENERAL REQUIREMENTS

A. Applicable requirements of General Requirements/Provisions shall be considered a part of this section and shall have the same force as if printed herein full. In addition, all information related to communications infrastructure that is documented in the architectural, structural, mechanical, and electrical drawings/documents shall be included as part of the Communications documents.

1.02 QUALITY ASSURANCE

A. Specifications, Standards and Codes: All work shall be in accordance with the following:

1. The 2017 edition of the National Electrical Code (NFPA 70) 2. American National Standards Institute (ANSI) 3. National Electrical Manufacturers Association (NEMA) 4. Telecommunications Industries Association (TIA) 5. Electronic Industries Association (EIA) 6. Institute of Electrical & Electronics Engineers (IEEE) 7. Underwriters Laboratories (UL) 8. American Standards Association (ASA) 9. Federal Communications Commission (FCC) 10. Occupational Safety and Health Administration (OSHA) 11. American Society of Testing Material (ASTM) 12. Americans with Disabilities Act (ADA) 13. Local city and county ordinances governing electrical work 14. In the event of conflicts, the more stringent provisions shall apply.

1.03 SCOPE

A. The work to be done under this section of the Specifications shall include furnishing labor, material, equipment and tools required for the complete installation of the work indicated on the Drawings or as specified herein.

13

B. All materials, obviously a part of the Communications Infrastructure and necessary to its proper operation, but not specifically mentioned or shown on the Drawings, shall be furnished and installed without additional charge.

C. The Drawings and Specifications are complementary to each other and what is called for by one shall be as binding as if called for by both. If a discrepancy exists between the Drawing and Specifications, the higher cost shall be included, and the engineer shall be notified of the discrepancy.

1.04 WORK INCLUDED

The Communications Infrastructure installed and work performed under this Section of the Specifications shall include but not necessarily be limited to the following:

A. Voice/Data Cabling Infrastructure

B. Communications conduits not supplied by the electrical contractor, raceways, cable tray, racks, cabinets and equipment mounting boards

C. Grounding and Bonding

1.05 DEFINITIONS

A. Terms: The following definitions of terms supplement those of the General Requirements and are applicable to all Section IV subsections:

B. Provide: As used herein shall mean “furnish, install and test (if applicable) complete.”

C. Infrastructure: As used herein shall mean cable, conduit, raceway, cable tray or j-hooks with all required boxes, fittings, connectors, and accessories; completely installed.

D. Work: As used herein shall be understood to mean the materials completely installed, including the labor involved.

E. Owner: Town of Jupiter

F. Project Manager: Kaufman Lynn

G. Architect: Song and Associates

H. Engineer: OSI Engineering

1.06 DRAWINGS

14

A. Drawings are generally diagrammatic and show the arrangement and location of pathways, outlets, support structures and equipment. The Contractor shall carefully investigate the structural and finish conditions affecting his work and arrange his work accordingly. Should conditions on the job make it necessary to make adjustments to pathways or materials, the Contractor shall so advise the Engineer and secure approval before proceeding with such work.

B. Where exact locations are required by equipment for stubbing-up and terminating conduit concealed in floor slabs or other rigid components, the Contractor shall request shop drawings, equipment location drawings, foundation drawings, and any other data required by him to locate the concealed conduit before the floor slab is poured.

C. Materials, equipment or labor not indicated but which can be reasonably inferred to be necessary for a complete installation shall be provided. Drawings and Specifications do not undertake to indicate every item of material, equipment, or labor required to produce a complete and properly operating installation.

D. The right is reserved to make reasonable changes in locations of equipment indicated on Drawings prior to rough-in without increase in contract cost.

E. The Contractor shall not reduce the size or number of conduit runs indicated on the Drawings without the written approval of the Engineer and Owner.

F. Any work installed contrary to Contract Drawings shall be subject to change as directed by the Engineer, and no extra compensation will be allowed for making these changes.

G. The location of equipment, support structures, outlets, and similar devices shown on the Drawings are approximate only. Do not scale Drawings. Obtain layout dimensions for equipment from Architectural plans unless indicated on Communications plans.

H. Schematic diagrams shown on the Drawings indicate the required functions only. The technology of a particular manufacturer may be used to accomplish the functions indicated without exact adherence to the schematic Drawings shown. Additional labor and materials required for such deviations shall be furnished at the Contractor's expense.

I. Verify the ceiling type, ceiling suspension systems, and clearance above hung ceilings prior to ordering cabling and associated hardware. Notify the Engineer of any discrepancies.

J. Review all architectural drawings for modular furniture.

K. Portions of these Drawings and Specifications are abbreviated and may include incomplete sentences. Omissions of words or phrases such as “the Contractor

15

shall,” “shall be,” “as indicated on the Drawings,” “In accordance with,” “a,” “the” and “all are intended” shall be supplied by inference.

1.07 SUBMITTALS

A. Submit for approval, details of all materials, equipment and systems to be furnished. Work shall not proceed without the Owner and/or the Project Manager's approval of the submitted items. Three (3) copies of the following shall be submitted:

1. Submittals for individual systems and equipment assemblies that consist of more than one item or component shall be made for the system or assembly as a whole. Partial submittals will not be considered, reviewed or stored, and such submittals will not be returned except at the request and expense of the Contractor.

2. Contractor shall generate shop drawings. Modify reviewed and accepted shop drawings to include revisions based upon completion of work. Submit shop drawings with record drawings on hard copy.

3. Shop drawings shall include equipment racks, patch panels, termination blocks, connection details, rack mounting details and any other details not included in the construction drawings.

B. Any materials and equipment listed that are not in accordance with Specification requirements may be rejected.

C. The approval of material, equipment, systems and shop drawings is a general approval subject to the Drawings, Specifications and verification of all measurements at the job. Approval does not relieve the Contractor from the responsibility of shop drawing errors. The Contractor shall carefully check and correct all shop drawings prior to submission for approval.

1.08 QUALITY ASSURANCE

A. Equipment and materials required for installation under these Specifications shall be the current model and new (less than one [1] year from the date of manufacture), unused and without blemish or defect.

B. Equipment shall bear labels attesting to Underwriters Laboratories, where subject to label service. Manufacturers of equipment and materials pertinent to these items shall have been engaged in the manufacture of said equipment a minimum of three (3) years and, if so directed by the Owner, be able to furnish proof of their ability by submitting affidavits and descriptive data about their product including size and magnitude comparable to requirements specified herein.

1.09 CONTRACTOR QUALIFICATIONS

16

A. The Contractor shall have total responsibility for the coordination and installation of the work shown and described in the Drawings and Specifications. The Contractor shall be a company specializing in the design, fabrication and installation of integrated communications systems.

B. Communications Systems specified shall be installed under the direction of a qualified Contractor. Qualification requirements shall include submittal by the Contractor to the Owner of the following:

1. List of previous projects of this scope, size and nature; including names and sizes of projects, description of work, time of completion and names of contact persons for reference.

2. Shall certify that they are manufacturer-authorized for work to be performed.

C. Contractor must employ at least one (1) full-time Registered Communications Distribution Designer (RCDD). The RCDD shall be a W2 employee and not a subcontractor, or minimum of 20 years installation experience.

1.10 COORDINATION WITH OTHER TRADES

A. The Contractor shall coordinate communications work with that of other sections as required ensuring that the entire communications work will be carried out in an orderly, complete and coordinated fashion.

1.11 SITE INVESTIGATION

A. Prior to submitting bids of the project, visit the site of the work to become aware of existing conditions that may affect the cost of the project. Where work under this project requires extension, relocation, reconnections or modifications to existing equipment or systems, the existing equipment or systems, shall be restored to their original condition before the completion of this project.

1.12 PERMITS

A. Obtain all permits and inspections for the installation of this work and pay all charges incident thereto. Deliver to the Owner all certificates of said inspection issued by authorities having jurisdiction.

1.13 RENOVATIONS AND ADDITIONS

A. All work that would adversely affect the normal operation of the other portions of the Owner's property shall be done at a time other than normal working hours. Normal working hours shall be considered 8 a.m. to 5 p.m. Monday through Friday.

17

B. Prior to submitting bids on the project, visit the site of the work to become aware of existing conditions that may affect the cost of the project.

C. Where work under this project requires extension, relocation, reconnections or modifications to existing equipment or systems, the existing equipment or systems shall be restored to their original and operating condition. Remove all equipment indicated to be demolished, including outlets, devices, raceways and support structures.

D. Care shall be exercised in the removal and storage of equipment indicated to be relocated or removed and reused. Prior to placing back into service, equipment shall be cleaned, marred or chipped paint surfaces touched-up.

E. Provide all coring, cutting and patching to existing walls, floors, etc., required for the removal of existing work or the installation of new work.

PART 2 - PRODUCTS

2.01 SUBSTITUTIONS

A. Where equipment is identified by manufacturer and catalog number, it shall be as the base of requirements for quality and performance. Where manufacturers for equipment are identified by name, the Contractor may submit for approval, similar equipment of other manufacturers as substitution. The Owner's decision as to whether the submitted equipment is acceptable shall be final and binding.

B. All changes necessary to accommodate the substituted equipment shall be made at the Contractor's expense, and shall be as approved by the owner. Detailed drawings indicating the required changes shall be submitted for approval at the time the substitution is requested.

C. If substitutions are made in lieu of device specified; form, dimension, design and profile shall be submitted to the Engineer for approval.

D. Submit request for approval of substitute materials in writing to the owner at least fifteen days prior to bid opening.

2.02 MATERIALS

A. All materials used in this work shall be new and shall bear the inspection label of Underwriters' Laboratories Inc. or certification by other recognized laboratory.

B. The published standards and requirements of the Telecommunications Industries Association (TIA), National Electrical Manufacturers Association (NEMA), the American National Standard Institute (ANSI), the Institute of Electrical and Electronic Engineers (IEEE), and the American Society of

18

Testing Materials (ASTM), are made a part of these Specifications and shall apply wherever applicable.

C. Materials and equipment furnished shall be of current production by manufacturers regularly engaged in the manufacture of such items, for which replacement parts are available.

D. When more than one unit of the same class of equipment or material is required, such units shall be the products of a single manufacturer or partner manufacturers that offer a certified solution.

E. Components of an assembled unit need not be products of the same manufacturer, but must offer a certified end-to-end solution.

F. Manufacturers of equipment assemblies, which include components made by others, shall assume complete responsibility for the final assembled unit.

G. Components shall be compatible with each other and with the total assembly for the intended service.

PART 3 - EXECUTION

3.01 EXAMINATION OF CONDITIONS

A. Prior to the start of work, the Contractor shall carefully inspect the installed work of other trades and verify that such work is complete to the point where installation may properly commence. Start of work indicates acceptance of conditions.

B. Install equipment in accordance with applicable codes and regulations, the original design and the referenced standards.

C. In the event of a discrepancy, immediately notify the Project Manager.

D. Do not proceed with installation until unsatisfactory conditions and discrepancies have been fully resolved.

3.02 PROTECTION OF SYSTEMS AND EQUIPMENT

A. Protect materials and equipment from damage during storage at the site and throughout the construction period. Equipment and materials shall be protected during shipment and storage against physical damage, dirt, theft, moisture, extreme temperature and rain.

B. Damage from rain, dirt, sun and ground water shall be prevented by storing the equipment on elevated supports and covering the sides with securely fastened protective rigid or flexible waterproof coverings.

19

C. During installation, equipment shall be protected against entry of foreign matter on the inside and be vacuum cleaned both inside and outside before testing, operating or painting.

D. As determined by the Project Manager, damaged equipment shall be fully repaired or shall be removed and replaced with new equipment to fully comply with requirements of the Contract Documents. Decision of the Project Manager shall be final.

E. Damaged paint on equipment and materials shall be repainted with painting equipment and finished with the same quality of paint and workmanship as used by the manufacturer.

3.03 ACCESS TO EQUIPMENT

A. Equipment shall be installed in location and manner that will allow convenient access for maintenance and inspection.

B. Working spaces shall be not less than specified in the National Electrical Code (NEC) for voltages specified.

C. Where the Project Manager determines that the Contractor has installed equipment not conveniently accessible for operation and maintenance, equipment shall be removed and reinstalled, one time only, as directed by the Project Manager, at no additional cost to the Owner. “Conveniently accessible” is defined as being capable of being reached without the use of ladders or without climbing or crawling under or over obstacles such as motors, pumps, belt guards, transformers, piping and duct work.

3.04 CLEANING

A. During construction, and prior to Owner acceptance of the building, remove from the premises and dispose of packing material and debris caused by communications work.

B. Remove dust and debris from interiors and exteriors of electrical equipment. Clean accessible current carrying elements prior to being energized.

3.05 COMPLETION

A. General: Upon completion of the work, remove excess debris, materials, equipment, apparatus, tools and similar items. Leave the premises clean, neat and orderly.

B. Results Expected: Systems shall be complete and operational and controls shall be set and calibrated. Testing, start-up and cleaning work shall be complete.

20

C. Maintenance Materials: Special tools for proper operation and maintenance of the equipment provided under this Specification shall be delivered to the Owner.

3.06 TESTING AND VERIFICATION

A. See specific Requirements and Specifications sections below for testing parameters of sub-systems.

B. The Contractor shall verify that requirements of this Specification are met. Verification shall be through a combination of analyses, inspections, demonstrations and tests, as described below.

C. Verification by inspection includes examination of items and comparison of pertinent characteristics against the qualitative or quantitative standard set forth in the Specifications. Inspection may require moving or partially disassembling the item to accomplish the verification, included as part of the work at no additional cost to the Owner.

D. The Contractor shall verify by formal demonstrations or tests that the requirements of this Specification have been met. The Contractor shall demonstrate that the communications systems, components and subsystems meet Specification requirements in the “as-installed” operating environment during the “System Operation Test.” Even though no formal environmental testing is required, the Contractor shall measure and record temperature, humidity and other environmental parameters and the environmental conditions, which were encountered during the “System Operation Test.”

E. The Contractor shall carefully plan and coordinate the final acceptance tests so that tests can be satisfactorily completed. The Contractor shall provide necessary instruments, labor and materials required for tests, including the equipment manufacturer's technical representative and qualified technicians in sufficient numbers to perform the tests within a reasonable time period.

F. The Contractor shall satisfy all items detailed in the final acceptance check-off list (punch list). The list shall be a complete representation of specified installation requirements. At the time of final acceptance punch list items shall be corrected until the system is found to be acceptable to the Owner and the Project Manager.

G. After the Contractor systems have been installed and tested, the completed test plan shall be signed by the Communications Contractor Project Manager and submitted for approval.

END OF SECTION

21

4.1 Requirements and Specifications – Communications Copper Horizontal Cabling

PART 1 - GENERAL

1.01 GENERAL REQUIREMENTS

A. Applicable requirements of Section IV – Requirements and Specifications -Communications shall be considered a part of this section and shall have the same force as if printed herein full.

B. This document describes the products and execution requirements relating to Communications Copper Horizontal Cabling.

C. Product specifications, general design considerations, and installation guidelines are provided in this document. The successful vendor shall meet or exceed all requirements described in this document and on the drawings.

1.02 SUBMITTALS

D. Provide product data from manufacturer’s specifications.

1.03 WORK INCLUDED

A. The work included under this specification consists of furnishing all labor, equipment, materials, supplies and performing all operations necessary to complete the installation. The Contractor will provide and install all of the required material whether specifically addressed in the Specification or not.

PART 2 - PRODUCTS

2.01 APPROVED PRODUCTS

A. Approved Horizontal Copper Cable Manufacturer(s)

1. Berk-Tek Part Number 11084689 Riser 2. Berk-Tek Part Number 11085339 Plenum 3. Owner Approved Equivalent

2.02 HORIZONTAL COPPER CABLE

A. 100 OHM Category 6A Balanced Twisted Pair Cable

4. The horizontal balanced twisted pair cable shall meet or exceed the Category 6A transmission characteristics per issue of ANSI/TIA-568-C.2.

22

5. Cable jacket shall be CMR or CMP rated (according to the space it occupies).

6. Jacket color shall be: a. Gray for voice. b. Blue for data

PART 3 - EXECUTION

3.01 HORIZONTAL CABLES

A. Cable shall be installed in accordance with manufacturer's recommendations and best industry practices.

B. A plastic or nylon pull cord with a minimum test rating of 90 Kg (200 lb.) shall be co-installed with all cable installed in any conduit.

C. Cable raceways shall not be filled greater than the ANSI/TIA-569-B maximum fill for the particular raceway type.

D. Cables shall be installed in continuous lengths from origin to destination (no splices) except for transition points, or consolidation points.

E. Riser rated cable shall be installed in metallic conduit when installed in a plenum space.

F. Where transition points or consolidation points are allowed, they shall be located in accessible locations and housed in an enclosure intended and suitable for the purpose.

G. The cable's minimum bend radius and maximum pulling tension shall not be exceeded. Refer to manufacturer's requirements.

H. If a J-hook or trapeze system is used to support cable bundles all horizontal cables shall be supported at a maximum of 48 to 60 inch (1.2 to 1.5 meter) intervals. At no point shall cable(s) rest on acoustic ceiling grids or panels.

I. Horizontal distribution cables shall be bundled in groups of no more than 50 cables. Cable bundle quantities in excess of 50 cables may cause deformation of the bottom cables within the bundle and degrade cable performance.

J. Cable shall be installed above fire-sprinkler systems and shall not be attached to the system or any ancillary equipment or hardware. The cable system and support hardware shall be installed so that it does not obscure any valves, fire alarm conduit, boxes, or other control devices.

23

K. Cables shall not be attached to ceiling grid or lighting fixture wires. Where support for horizontal cable is required, the Contractor shall install appropriate carriers to support the cabling.

L. Any cable damaged or exceeding recommended installation parameters during installation shall be replaced by the Contractor prior to final acceptance at no cost to the Owner.

M. Cables shall be dressed and terminated in accordance with the recommendations made in the ANSI/TIA-568-C.2 document, manufacturer's recommendations and best industry practices.

N. Leave a minimum of 12" of slack for twisted pair cables at the outlet. Cables shall be coiled in the in-wall box, surface-mount box or modular furniture raceway if adequate space is present to house the cable coil without exceeding the manufacturers bend radius. In hollow-wall installations where box-eliminators are used, excess wire can be stored in the wall. Excess slack shall be loosely coiled and stored in the ceiling above each drop location when there is not enough space present in the outlet box to store slack cable.

O. Cables shall be neatly bundled and dressed to their respective termination device. Each terminating device shall be fed by an individual bundle separated and dressed back to the point of cable entrance into the rack or frame.

P. Each cable shall be clearly labeled on the cable jacket behind the termination device at a location that can be viewed without removing the bundle support ties. Cables labeled within the bundle, where the label is obscured from view shall not be acceptable.

3.02 IDENTIFICATION

A. Refer to Section IV - Identification for Communications Systems for labeling details.

END OF SECTION

24

4.2 Requirements and Specifications – Communications Patch Cords

PART 1 - GENERAL

1.01 GENERAL REQUIREMENTS

A. Applicable requirements of Section IV Requirements and Specifications -Communications shall be considered a part of this section and shall have the same force as if printed herein full.

B. This document describes the products and execution requirements relating to Communications Patch Cords.

C. Product specifications, general design considerations, and installation guidelines are provided in this document. The successful vendor shall meet or exceed all requirements described in this document and on the drawings.

1.02 SUBMITTALS

A. Provide product data from manufacturer’s specifications.

1.03 WORK INCLUDED

A. The work included under this specification consists of furnishing all labor, equipment, materials, supplies and performing all operations necessary to complete the installation. The Contractor will provide and install all of the required material whether specifically addressed in the Specification or not.

PART 2 - PRODUCTS

2.01 APPROVED PRODUCTS

A. Approved Copper Patch Cord Manufacturer(s)

1. Leviton 6210G-*** 2. Owner Approved Equivalent

B. Approved Fiber Patch Cord Manufacturer(s)

1. Leviton 2. Owner Approved Equivalent

25

2.02 COPPER PATCH CORDS

C. Category 6A Patch Cords

1. The Category 6A patch cord shall be 4-pair, with 26 AWG solid or stranded copper conductors and 8-position modular plug.

2. The Category 6A modular cord cable shall be UL Listed as Type CMR. 3. The Category 6A patch cord shall meet or exceed the requirements of

ANSI/TIA-568-C.2. 4. Lengths shall be 3’, 5’, 7’ and/or 10’ as required by the application.

a. The Category 6A patch cord color for voice shall be: Gray b. The Category 6A patch cord color for data shall be: Blue

2.03 FIBER PATCH CORDS

A. Multimode Fiber Patch Cords

1. 50/125-Micron 850nm Laser Optimized Multimode Fiber Patch Cord (OM3) a. The 50/125-micron fiber used in the multimode fiber patch cord

shall have a maximum attenuation of 3.5dB/km@ 850 nm and 1.5 dB/km @1300 nm.

b. The 50/125-micron 850nm laser optimized multimode fiber patch cord shall meet or exceed the requirements of ANSI/TIA-568-C.3.

c. The optical fiber cord connector shall be LC. d. The multimode fiber cord assembly shall be dual zip jacketed. e. Lengths shall be 1m, 2m, and/or 3m as required by the

application.

B. Singlemode Fiber Patch Cords

1. 8.3/125-micron singlemode fiber patch cord: a. The 8.3/125-micron fiber used in the singlemode fiber patch cord

shall have a maximum attenuation of 1.0 dB/km @ 1310 nm and 1.0 dB/km @ 1550 nm.

b. The optical fiber cord connector shall have a maximum insertion loss of 0.5 dB and a reflectance of -30 dB.

c. The 8.3/125-micron singlemode fiber patch cord shall meet or exceed the requirements of ANSI/TIA-568-C.3.

d. The optical fiber cord connector shall be LC. e. The singlemode fiber patch cord assembly shall be dual zip

jacketed. f. Lengths shall be 1m, 2m, and/or 3m as required by the

application. g. Angle polish connectors shall be used for video distribution.

PART 3 - EXECUTION

26

3.01 COPPER PATCH CORDS

A. Copper patch cords shall be installed as per the requirements specified by the manufacturer's installation guidelines.

3.02 FIBER PATCH CORDS

A. Fiber patch cords shall be installed as per the requirements specified by the manufacturer's installation guidelines.

3.03 IDENTIFICATION

A. Refer to Section IV - Identification for Communications Systems for labeling details.

END OF SECTION

27

4.3 Requirement and Specifications – Fire-stopping for Communications Systems

PART 1 - GENERAL

1.01 GENERAL REQUIREMENTS

1. Applicable requirements of Section IV – Requirements and Specifications -Communications shall be considered a part of this section and shall have the same force as if printed herein full.

2. This document describes the products and execution requirements relating to Fire-stopping for Communications Systems.

3. Product specifications, general design considerations, and installation guidelines are provided in this document. The successful vendor shall meet or exceed all requirements described in this document and on the drawings.

1.02 SUBMITTALS

A. Provide product data from manufacturer’s specifications.

1.03 WORK INCLUDED

A. The work included under this Specification consists of furnishing all labor, equipment, materials, supplies and performing all operations necessary to complete the installation. The Contractor will provide and install all of the required material whether specifically addressed in the Specification or not.

PART 2 - PRODUCTS

2.01 APPROVED PRODUCTS

A. Approved Fire-stopping Manufacturer(s)

1. Flame-stopper Thru-Wall Fitting – Wire-mold Company (Firestop Devices)

2. Unique Firestop Products (Firestop Devices) 3. STI Firestop Products (Firestop Devices, Putties, Caulks, Sealants, etc.) 4. Hilti (Putties, Caulks, Sealants, etc.)

2.02 TYPES OF PRODUCTS

A. Sealants

1. Intumescent Firestop Sealants and Caulks 2. Latex Firestop Sealant

28

3. Acrylic Water-Based Sealant 4. Silicone Firestop Sealants and Caulks 5. Firestop Putty 6. Firestop Collars 7. Wrap Strips 8. 2-Part Silicone Firestop Foam 9. Firestop Mortar

10. Firestop Pillows 11. Elastomeric Spray 12. Accessories: 13. Forming/Damming Materials: Mineral fiberboard or other type as per

manufacturer recommendation

B. Firestop Devices

1. Thru-Wall Fitting (Flame-stopper by Wiremold) a. The firestop device box shall be constructed of 16 gage G90 steel. b. The firestop device intumescent block shall be constructed of a graphite

base material with expansion starting at 375°F and an unrestrained expansion between 6 to 12 times. The intumescent block shall be held securely by the box in order to prevent tampering and damage during installation.

c. The firestop device shall have doors which can be adjusted to prevent materials from penetrating the device if the device is empty or completely full. The doors shall be constructed of 16 gage G90 steel with No. 10-32 screws use to adjust opening size.

d. The firestop device shall be available for 2" and 4" trade size EMT conduit.

e. The firestop device shall be available in safety yellow powder coat, custom colors and an unpainted galvanized finish.

2. Threaded Firestop Device (Unique Firestop Products) a. Threaded steel sleeve device incorporating flat washers secured by

threaded device shall be installed around cables. The device shall be available in 1, 2 and 4-inch sizes. Maximum diameter of the wall penetration for 1, 2 and 4-inch sizes shall be 1-1/4, 2-7/16 and 4-1/2 inches respectively.

3. Smooth Firestop Device (Unique Firestop Products) a. Smooth steel sleeve device incorporating flat washers secured by sliding

compression couplers. The device shall be available in 1, 2 and 4-inch sizes. Maximum diameter of the wall penetration for 1, 2 and 4-inch sizes shall be 1-1/4, 2-7/16 and 4-1/2 inches respectively.

4. Split-Sleeve Firestop Device (Unique Firestop Products) a. Threaded steel sleeve halves incorporating split couplings and slotted

washers to fit the specific diameter of the opening. The device shall be available in 1, 2 and 4-inch sizes. Maximum diameter of the wall penetration for 1, 2 and 4-inch sizes shall be 1-1/4, 2-7/16 and 4-1/2 inches respectively.

5. Fire Rated Cable Pathway (STI EZ-PATH)

29

a. Fire rated cable pathway device modules shall be comprised of steel raceway with intumescent foam pads allowing 0-100 percent cable fill.

2.03 UL CLASSIFICATION

A. Thru-Wall Fitting - The firestop device for use in through-penetration firestop systems shall have been examined and tested by Underwriters Laboratories Inc. to UL1479 (ASTM E 814) and bear the U.S. and Canadian UL Classification Mark.

B. Threaded, Smooth and Split-Sleeve Firestop Devices – Fire-stopping sealants and devices shall be used together as a firestop system. All firestop systems shall bear a UL Classification system number. UL Classification system numbers are as follows:

1. Threaded Firestop System a. Block Wall - W-J-3049 b. Dry Wall - W-L-3138

2. Threaded Firestop System (Vertical) a. Slab - F-A-3010

3. Smooth Firestop System a. Block Wall - W-J-3048 c. Dry Wall - W-L-3137

4. Split-Sleeve Firestop System a. Block Wall - W-J-3047 b. Dry Wall - W-L-3136

2.04 FIRESTOPPING SYSTEMS

A. Thru-Wall Fitting Firestop System:

1. The device shall be classified for use in one-, two-, three, and four-hour rated gypsum, concrete and block walls and provide a maximum L rating of six cfm. The devices shall also been tested by Underwriters Laboratories Inc. to UL2043 and determined to be suitable for use in air handling spaces.

B. Threaded, Smooth and Split-Sleeve Firestop Systems:

1. Shall conform to both Flame (F) and Temperature (T) ratings as required by local building codes and as tested by nationally accepted test agencies per ASTM E814 or UL 1479 fire tests in a configuration that is representative of field conditions.

2. The F rating must be a minimum of one (1) hour but not less than the fire resistance rating of the assembly being penetrated. T rating when required by code authority shall be based on measurement of the temperature rise on penetrating item(s). The fire test shall be conducted with a minimum positive pressure differential of 0.01 inches of water column.

3. For joints, must be tested to UL 2079 with movement capabilities equal to those of the anticipated conditions.

30

C. Fire-stopping materials and systems must be capable of closing or filling through-openings created by 1) the burning or melting of combustible pipes, cable jacketing, or pipe insulation materials, or 2) deflection of sheet metal due to thermal expansion (electrical & mechanical duct work).

D. Fire-stopping material shall be asbestos and lead free and shall not incorporate nor require the use of hazardous solvents.

E. Fire-stopping sealants must be flexible, allowing for normal pipe movement.

F. Fire-stopping materials shall not shrink upon drying as evidenced by cracking or pulling back from contact surfaces.

G. Fire-stopping materials shall be moisture resistant, and may not dissolve in water after curing.

PART 3 - EXECUTION

3.01 CONDITIONS REQUIRING FIRESTOPPING

A. General

1. Provide fire-stopping for conditions specified whether or not fire-stopping is indicated, and if indicated, whether such material is designed as insulation, safing, or otherwise.

B. Through-Penetrations

1. Fire-stopping shall be installed in all open penetrations and in the annular space in all penetrations in any bearing or non-bearing fire-rated barrier.

C. Membrane-Penetrations

1. Where required by code, all membrane-penetrations in rated walls shall be protected with fire-stopping products that meet the requirements of third party time/temperature testing.

D. Construction Joints/Gaps

1. Fire-stopping shall be provided between the edges of floor slabs and exterior walls, between the tops of walls and the underside of floors, in the control joint in masonry walls and floors and in expansion joints.

E. Smoke-Stopping

31

1. As required by the other sections, smoke-stops shall be provided for through-penetrations, membrane-penetrations, and construction gaps with a material approved and tested for such application.

3.02 EXAMINATION

A. Examine the areas and conditions where firestops are to be installed and notify the Architect of conditions detrimental to the proper and timely completion of the work. Do not proceed with work until unsatisfactory conditions have been corrected.

B. Verify that environmental conditions are safe and suitable for installation of firestop products.

C. Verify that all pipes, conduit, cable, and other items that penetrate fire-rated construction have been permanently installed prior to installation of firestops.

3.03 INSTALLATION

A. General

1. Installation of firestops shall be performed by an applicator/installer qualified and trained by the manufacturer. Installation shall be performed in strict accordance with manufacturer's detailed installation procedures.

2. Apply firestops in accordance with fire test reports, fire resistance requirements, acceptable sample installations, and manufacturer's recommendations.

3. Unless specified and approved, all insulation used in conjunction with through-penetrants shall remain intact and undamaged and may not be removed.

4. Seal holes and penetrations to ensure an effective smoke seal. 5. In areas of high traffic, protect fire-stopping materials from damage. If

the opening is large, install fire-stopping materials capable of supporting the weight of a human.

6. Insulation types specified in other sections shall not be installed in lieu of fire-stopping material specified herein.

7. All combustible penetrants (e.g. non-metallic pipes or insulated metallic pipes) shall be fire-stopped using products and systems tested in a configuration representative of the field condition.

B. Dam Construction

1. When required to properly contain fire-stopping materials within openings, damming or packing materials may be utilized. Combustible damming material must be removed after appropriate curing. Noncombustible damming materials may be left as a permanent component of the firestop system.

32

3.04 FIELD QUALITY CONTROL

A. Prepare and install fire-stopping systems in accordance with manufacturer's printed instructions and recommendations.

B. Follow safety procedures recommended in the Material Safety Data Sheets.

C. Finish surfaces of fire-stopping that are to remain exposed in the completed work to a uniform and level condition.

D. All areas of work must be accessible until inspection by the applicable Code Authorities.

E. Correct unacceptable firestops and provide additional inspection to verify compliance with this Specification.

3.05 CLEANING

A. Remove spilled and excess materials adjacent to fire-stopping without damaging adjacent surfaces.

B. Leave finished work in a neat and clean condition with no evidence of spill-overs or damage to adjacent surfaces.

3.06 IDENTIFICATION

A. Refer to Section IV - Identification for Communications Systems for labeling details.

END OF SECTION

33

4.4 Requirements and Specifications - Grounding and Bonding for Communications Systems

PART 1 - GENERAL

1.01 GENERAL REQUIREMENTS

A. Applicable requirements of Section IV – Requirements and Specifications -Communications shall be considered a part of this section and shall have the same force as if printed herein full.

B. This document describes the products and execution requirements relating to Grounding and Bonding for Communications Systems.

C. Product specifications, general design considerations, and installation guidelines are provided in this document. The successful vendor shall meet or exceed all requirements described in this document and on the drawings.

1.02 SUBMITTALS

A. Provide product data from manufacturer’s specifications.

1.03 WORK INCLUDED

A. The work included under this Specification consists of furnishing all labor, equipment, materials, supplies and performing all operations necessary to complete the installation. The Contractor will provide and install all of the required material whether specifically addressed in the Specification or not.

PART 2 - PRODUCTS

2.01 APPROVED PRODUCTS

A. Approved Equipment Grounding Conductor Manufacturer(s)

1. Southwire 2. Or Approved Equal

B. Approved Grounding Lug Manufacturer(s)

1. Burndy 2. Thomas & Betts 3. Or Approved Equal

C. Approved Grounding Busbar Manufacturer(s)

1. Chatsworth Products, Inc. 2. B-Line

34

3. Harger

2.02 GROUNDING CONDUCTORS

A. Grounding Conductor

1. Construction shall be Type THHN copper conductors, insulated with heat and moisture resistant PVC over which a UL listed jacket is applied.

2. Jacket color shall be green or black. Black jacketed cable shall be identified at each termination point with a wrap of green tape.

2.03 GROUNDING LUGS

A. Grounding Lugs and Hardware

1. Grounding lugs shall be 2-hole and installed with a crimper that when properly executed the die of the crimper impresses the die # on the lug base. All lugs shall be sleeved with clear heat-shrink to allow for inspection of the crimp. Silicon bronze or stainless steel bolts and washers shall be used to install lugs to equipment. Exothermic welding is also allowed.

2.04 GROUNDING BUSBARS

A. Grounding Busbar

1. The grounding busbar shall be made of 1/4" thick solid copper. 2. The grounding busbar shall be installed with minimum clearance, 1"

offsets and 1-1/2" insulators. 3. The grounding busbar shall accommodate 2-hole compression lugs. 4. The grounding busbar shall meet or exceed ANSI/TIA-607-B

requirements.

PART 3 - EXECUTION

3.01 GROUNDING

A. The facility shall be equipped with a Communications Bonding Backbone (TBB). This backbone shall be used to ground all communications cable shields, equipment, racks, cabinets, raceways, and other associated hardware that has the potential to act as a current carrying conductor. The TBB shall be installed independent of the building's electrical and building ground and shall be designed in accordance with the recommendations contained in the ANSI/TIA-607-B Telecommunications Bonding and Ground Standard.

B. The main entrance facility/equipment room in each building shall be equipped with a telecommunications main grounding busbar (TMGB). Each

35

telecommunications room (TR) shall be provided with a telecommunications ground busbar (TGB). The TMGB shall be connected to the building electrical entrance grounding facility.

C. All racks, metallic backboards, cable sheaths, metallic strength members, splice cases, cable trays, etc. entering or residing in the MC/IC/TC shall be grounded to the respective TGB or TMGB using a minimum #6 AWG stranded copper bonding conductor and compression lugs.

D. All wires used for communications grounding purposes shall be identified with a green insulation. Non-insulated wires shall be identified at each termination point with a wrap or green tape. All cables and busbars shall be identified and labeled in accordance with the ANSI/TIA-606-A.

3.02 IDENTIFICATION

A. Refer to Section IV - Identification for Communications Systems for labeling details.

END OF SECTION

36

4.5 Requirements and Specifications - Pathways for Communications Systems

PART 1 - GENERAL

1.01 GENERAL REQUIREMENTS

A. Applicable requirements of Section IV – Requirements and Specifications -Communications shall be considered a part of this section and shall have the same force as if printed herein full.

B. This document describes the products and execution requirements relating to Pathways for Communications Systems.

C. Product specifications, general design considerations, and installation guidelines are provided in this document. The successful vendor shall meet or exceed all requirements described in this document and on the drawings.

1.02 SUBMITTALS

A. Provide product data from manufacturer’s specifications.

1.03 WORK INCLUDED

A. The work included under this specification consists of furnishing all labor, equipment, materials, supplies and performing all operations necessary to complete the installation. The Contractor will provide and install all of the required material whether specifically addressed in the Specification or not.

PART 2 - PRODUCTS

2.01 APPROVED PRODUCTS

A. Approved Cable Tray System Manufacturer(s)

1. B-Line 2. No Exceptions

B. Approved Cable Hanger Manufacturer(s)

1. B-Line 2. No Exceptions

C. Approved Tie Wrap/Velcro Strap Manufacturer(s)

1. Leviton

37

2.02 CABLE TRAY

A. Cable Tray System

1. Cable tray shall be steel or aluminum construction. 2. Cable tray cross members shall be factory welded at 12" intervals

maximum. 3. Cable tray shall be equipped with one (1) or two (2) support rails that run

the length of each segment. 4. End caps shall be installed on the exposed ends of the cable tray, channel

supports and bolts. Protective covers shall be installed on threaded rods that come in contact with cabling plant.

5. Wall mount cable tray used in limited clearance areas shall be hook style and constructed of aluminum.

6. See Drawings for cable tray dimensions. a. Cable Tray color shall be black.

2.03 CABLE HANGERS

A. J-Hooks

1. J-hooks shall provide a bearing surface of sufficient width to comply with required bend radii of high-performance cables. J-hook shall be cULus Listed.

2. J-hooks shall have flared edges to prevent damage while installing cables. 3. J-hooks sized 1 5/16" and larger shall have a cable retainer strap to

provide containment of cables within the hanger. The cable retainer strap shall be removable and reusable and be suitable for use in air handling spaces.

B. Adjustable Non-Continuous Cable Support Sling

1. Constructed from steel and woven laminate; sling length can be adjusted to hold up to 425 4-pair balanced twisted pair cables; rated for indoor use in non-corrosive environments. Rated to support Category 5 and higher cable, or optical fiber cable. Cable support sling shall be cULus Listed.

2. Adjustable non-continuous cable support sling shall have a static load limit of 100 lbs.

3. Adjustable non-continuous cable support sling shall be suitable for use in air handling spaces.

2.04 TIE WRAPS AND VELCRO STRAPS

A. Tie Wraps and Velcro Straps

1. Cables shall be fastened to support structures with tie wraps/Velcro straps.

38

2. Tie wraps/Velcro straps installed in air handling spaces must be plenum rated. a. Non-plenum Tie Wrap color shall be black. b. Plenum Tie Wrap color shall be red. c. Non-plenum Velcro strap color shall be black. d. Plenum Velcro strap color shall be red.

PART 3 - EXECUTION

3.01 PENETRATIONS

A. Holes through concrete and masonry in new and existing structures shall be cut with a diamond core drill or concrete saw upon approval of the structural engineer of record for the base of building. Pneumatic hammer, impact electric, hand or manual hammer type drills shall not be allowed, except where permitted by the Project Manager as required by limited working space. X-ray all floor penetrations accordingly.

B. Holes shall be located so as not to affect structural sections such as ribs or beams.

C. Holes shall be laid out in advance. The Project Manager shall be advised prior to drilling through structural sections, for determination of proper layout.

D. Structural Penetrations: Where conduits, wireways and other raceways pass through fire partitions, fire walls or walls and floors provide a code compliant effective barrier against the spread of fire, smoke and gases.

E. All penetrations where conduit is not used shall be sleeved.

F. No gaps or rough edges shall be allowed between wall and conduit/sleeve.

3.02 CABLE TRAY SYSTEM

A. Install trays in accordance with recognized industry practices, to ensure that the cable tray equipment complies with requirements of the NEC.

B. All open trays shall be installed a minimum of six (6) inches away from any light fixture.

C. Provide external grounding strap at expansion joints, sleeves, crossover and other locations where tray continuity is interrupted.

D. Support all pathways from building construction. Do not support pathways from ductwork, piping or equipment hangers.

E. Install cable tray level and straight.

39

F. Provide all hardware, accessories, fasteners, anchors, threaded rods and support channels required to provide a complete cable tray system.

G. Cable trays shall not be used to house both low voltage and power cables unless cables are separated by a grounded physical barrier.

H. Cable tray system shall be grounded in accordance with ANSI/TIA-607-B.

3.02 CABLE HANGERS

A. Installation and configuration shall conform to the requirements of ANSI/TIA-568-C.0, ANSI/TIA-568-C.1 & ANSI/TIA-569-B, NFPA 70 (National Electrical Code), applicable local codes, and to the manufacturer's installation instructions.

B. Install cables using techniques, practices, and methods that are consistent with Category 5e or higher requirements and that supports Category 5e or higher performance of completed and linked signal paths, end to end.

C. Install cables without damaging conductors, shield, or jacket.

D. Do not bend cables, in handling or in installing, to smaller radii than minimums recommended by manufacturer.

E. Pull cables without exceeding cable manufacturer's recommended pulling tensions. Use pulling means that will not damage media.

F. Do not exceed load ratings specified by manufacturer.

G. Adjustable non-continuous support sling shall have a static load limit of 100 lbs.

H. To avoid electromagnetic interference (EMI), pathways shall provide minimum clearances of four feet from motors or transformers, one foot from conduit and cables used for electrical power distribution, and five inches from fluorescent lighting. Pathways shall cross perpendicular to fluorescent lighting and electrical power cables or conduits.

3.04 TIE WRAPS AND VELCRO STRAPS

A. Tie wraps/Velcro straps shall be installed around cables at intervals of 12" minimum.

B. Tie wraps shall secure cables to cable trays using an "X" pattern.

C. Do not over-cinch cables.

3.05 IDENTIFICATION

40

A. Refer to Section IV - Identification for Communications Systems for labeling details.

END OF SECTION

41

4.6 Requirements and Specifications – Identification for Communications Systems

PART 1 - GENERAL

1.01 GENERAL REQUIREMENTS

A. Applicable requirements of Section IV – Requirements and Specifications -Communications shall be considered a part of this section and shall have the same force as if printed herein full.

B. This document describes the equipment and execution requirements relating to Identification for Communications Systems.

C. Equipment specifications, general considerations, and guidelines are provided in this document. The successful vendor shall meet or exceed all requirements described in this document and on the drawings.

1.02 WORK INCLUDED

A. The work included under this Specification consists of furnishing all labor, equipment, materials, supplies and performing all operations necessary to complete installation. The Contractor will provide and install all of the required material whether specifically addressed in the Specification or not.

PART 2 - LABELING

2.01 LABELING REQUIREMENTS

A. Labeling shall be done in accordance with the recommendations made in the ANSI/TIA-606-A document, manufacturer's recommendations and best industry practices.

B. All spaces, pathways, outlets, cables, termination hardware, grounding system and equipment shall be labeled with machine-generated labels.

C. All labels shall be clear with black text.

D. All cables shall be labeled with machine generated, wrap around labels.

E. A total of three (3) labels per horizontal cable are required at the following intervals: 6" from outlet; 18" from outlet' 12" from termination block/patch panel.

F. Labeling scheme shall be alphanumeric.

42

END OF SECTION

4.7 Requirements and Specifications – Commissioning of Communications

PART 1 - GENERAL

1.01 GENERAL REQUIREMENTS

A. Applicable requirements of Section IV – Requirements and Specifications -Communications shall be considered a part of this section and shall have the same force as if printed herein full.

B. This document describes the equipment and execution requirements relating to Commissioning of Communications.

C. Equipment specifications, general considerations, and guidelines are provided in this document. The successful vendor shall meet or exceed all requirements described in this document and on the drawings.

1.02 WORK INCLUDED

A. The work included under this specification consists of furnishing all labor, equipment, materials, supplies and performing all operations necessary to complete installation. The Contractor will provide and install all of the required material whether specifically addressed in the Specification or not.

PART 2 - TESTING

2.01 TESTING REQUIREMENTS

A. General

1. All cables and termination hardware shall be 100% tested for defects in installation and to verify cabling system performance under installed conditions according to the requirements of ANSI/TIA-568-C.0, ANSI/TIA-568-C.1, and/or ANSI/TIA-1152. All conductors/strands of each installed cable shall be verified prior to system acceptance. Any defect in the cabling system installation including but not limited to cable, connectors, feed through couplers, patch panels, and connector blocks shall be repaired or replaced in order to ensure 100% useable conductors/strands in all cables installed.

B. Copper Testing

1. All twisted-pair copper cable links shall be tested for continuity, pair reversals, shorts, opens and performance as indicated below. Additional testing is required to verify Category 6A performance. Horizontal

43

balanced twisted pair cabling shall be tested using a level IV test unit for category 6A performance compliance.

2. Continuity - Each pair of each installed cable shall be tested using a test unit that shows opens, shorts, polarity and pair-reversals, crossed pairs and split pairs. The test shall be recorded as pass/fail as indicated by the test unit and referenced to the appropriate cable identification number and circuit or pair number. Any faults in the wiring shall be corrected and the cable re-tested prior to final acceptance.

3. Length - Each installed cable link shall be tested for installed length using a TDR type device. The cables shall be tested from patch panel to patch panel, block to block, patch panel to outlet or block to outlet as appropriate. The cable length shall conform to the maximum distances set forth in the ANSI/TIA-568-C.2 Standard. Cable lengths shall be recorded, referencing the cable identification number and circuit or pair number. For multi-pair cables, the shortest pair length shall be recorded as the length for the cable.

4. Approved tester is as follows: Softing

C. Fiber Testing

1. All fiber testing shall be performed on all fibers in the completed end-to-end system. There shall be no splices unless clearly defined in the RFP and/or Drawings. These tests also include continuity checking of each fiber.

2. Multimode a.Test the optical fiber cable bi-directionally with an OTDR and uni-directionally with a power meter/light source. Fiber must be tested at both 850nm and 1300nm. Maximum attenuation dB/Km @ 850nm/1300nm shall be 3.5/1.5. Maximum attenuation per connector pair shall be .75 dB. Attenuation testing shall be performed with a stable launch condition using a one-meter or two-meter jumper, wrapped around a mandrel sized according to fiber type, to attach the light source to the cable plant. Fiber jumper shall be wrapped around mandrel no less than five (5) times. The jumper-mandrel assembly shall remain connected to the light source after calibration and the power meter moved to the far end using a new jumper to take measurements. Test set-up and performance shall be conducted in accordance with ANSI/TIA-568-C.3, and to the manufacturer's application guides.

3. Single-mode a. Test the optical fiber cable bi-directionally with an OTDR and uni-

directionally with a power meter/light source. Fiber must be tested at both 1310nm and 1550nm. Maximum attenuation dB/Km @ 1310nm/1550nm shall be 0.5/0.5 for outside plant and 1.0/1.0 for inside plant. Maximum attenuation per connector pair shall be .75 dB. Attenuation testing shall be performed with a stable launch condition using one-meter or two-meter jumpers to attach the test equipment to the cable plant. The light source shall be left in place

44

after calibration and the power meter moved to the far end to take measurements. Test set-up and performance shall be conducted in accordance with ANSI/TIA-568-C.3, and to the manufacturer's application guides.

4. Approved optical fiber test equipment manufacturers are as follows: a. Softing

D. Test Results

1. Test documentation shall be provided on disk as part of the as-built package. The disk shall be clearly marked on the outside front cover with the words “Project Test Documentation,” the project name, and the date of completion (month and year). The results shall include a record of test frequencies, cable type, conductor pair (or strand) and cable (or outlet) I.D., measurement direction, reference setup, and crew member name(s). The test equipment name, manufacturer, model number, serial number, software version and last calibration date will also be provided at the end of the document. Unless the manufacturer specifies a more frequent calibration cycle, an annual calibration cycle is anticipated on all test equipment used for this installation. The test document shall detail the test method used and the specific settings of the equipment during the test as well as the software version being used in the field test equipment.

2. The field test equipment shall meet the requirements of ANSI/TIA-568-C.2, ANSI/TIA-568-C.3, and/or ANSI/TIA-1152.

3. Printouts generated for each cable by the wire (or fiber) test instrument shall be submitted as part of the documentation package. Alternately, the Contractor may furnish the test results in electronic form as defined by the Specification and be of a format readable from Microsoft Word.

4. When repairs and re-tests are performed, the problem found and corrective action taken shall be noted, and both the failed and passed test data shall be documented.

PART 3 - DOCUMENTATION, AS-BUILTS, TRAINING AND RECORDS

3.01 DOCUMENTATION & AS-BUILTS

A. As-Built record documentation for communications work shall include:

1. Cable routing and identification 2. System function diagrams 3. Manufacturers' description literature for equipment 4. Connection and programming schedules as appropriate 5. Equipment material list including quantities 6. Spare parts list with quantities 7. Details not on original Contract Documents 8. Test results 9. Warranties 10. Release of liens

45

B. The Contractor shall provide and maintain at the site a set of prints on which shall be accurately shown the actual installation of all work under this section, indicating any variation from contract drawings, including changes in pathways, sizes, locations and dimensions. All changes shall be clearly and completely indicated as the work progresses.

C. Progress prints shall be available for inspection by the Owner or any of his representatives and may be used to determine the progress of communications infrastructure work.

D. At the completion of the work, prepare a new set of as-built drawings, of the work as actually noted on the marked-up prints, including the dimensioned location of all pathways.

E. Furnish as-built drawings and documentation to the Project Manager. As-built drawings shall be generated in AutoCad 2015 or later. Submit as-built drawings electronically and hard copy.

3.02 OPERATIONS AND MAINTENANCE MANUAL

A. After completion of the work, the Contractor shall furnish and deliver to the Engineer three (3) copies of a complete Operations & Maintenance Manual. A system wiring diagram shall be furnished for each separate system.

B. The manual shall be subdivided into separate sections with tab dividers to identify subsystems of the integrated system. Reference appropriate Specification sections.

C. Provide the following additional information for each electronic system. Information shall be edited for this project where applicable.

1. Operations manuals for components and for systems as a whole 2. Maintenance manuals for components and for system as a whole 3. Point-to-point diagrams, cabling diagrams, construction details and

cabling labeling details 4. List of spare parts, materials and suppliers of components. Provide name,

address and telephone number for each supplier. 5. Emergency instructions for operational and maintenance requirements 6. Delivery time frame for replacement of component parts from suppliers 7. Recommended inspection schedule and procedures for components and

for system as a whole 8. List of spare parts, materials and suppliers of components. Provide name,

address and telephone number for each supplier. 9. Complete “reviewed” shop drawings and product data for components

and system as a whole 10. Troubleshooting procedures for each system and for each major system

component

46

3.03 TRAINING

A. The Contractor shall be responsible for training of facility personnel. Training shall take place after occupancy and before acceptance and shall include programs for on-site operations and maintenance of technology and communications systems. Training shall be for not more than ten (10) people, shall be held at the Owner's site and shall be of sufficient duration and depth to ensure that the trained personnel can operate the installed systems and can perform usual and customary maintenance actions.

3.04 WARRANTY

A. General

1. All equipment is to be new and warranted free of faulty workmanship and damage.

2. Replacement of defective equipment and materials and repair of faulty workmanship within 24 hours of notification, except emergency conditions (system failures), which must be placed back in service within eight (8) hours of notification, all at no cost to the Owner.

3. The minimum warranty provisions specified shall not diminish the terms of individual equipment manufacturer's warranties.

B. Voice & Data Structured Cabling

1. Manufacturer(s) shall provide a minimum 25-year warranty for components used in the installed Voice & Data Structured Cabling System. Defective and/or improperly installed products shall be replaced and/or correctly installed at no cost to the Owner.

C. Pathway & Support Infrastructure

1. Manufacturer(s) shall provide a minimum 1-year warranty for components used in the installed Pathway & Support Infrastructure. Defective and/or improperly installed products shall be replaced and/or correctly installed at no cost to the Owner.

END OF SECTION

47

4.8 Requirements and Specifications – Communications Entrance Protection

PART 1 - GENERAL

1.01 GENERAL REQUIREMENTS

A. Applicable requirements of Section IV – Requirements and Specifications -Communications shall be considered a part of this section and shall have the same force as if printed herein full.

B. This document describes the products and execution requirements relating to Communications Entrance Protection.

C. Product specifications, general design considerations, and installation guidelines are provided in this document. The successful vendor shall meet or exceed all requirements described in this document and on the drawings.

1.02 SUBMITTALS

A. Provide product data from manufacturer’s specifications.

1.03 WORK INCLUDED

A. The work included under this specification consists of furnishing all labor, equipment, materials, supplies and performing all operations necessary to complete the installation. The Contractor will provide and install all of the required material whether specifically addressed in the Specification or not.

PART 2 - PRODUCTS

2.01 APPROVED PRODUCTS

A. Approved Building Entrance Protector Terminal Manufacturer(s)

1. Circa 2. Porta Systems

B. Approved Bonding Shield Connector Manufacturer(s)

1. 3M 2. Or Approved Equal

2.02 BUILDING ENTRANCE PROTECTOR TERMINALS

A. Indoor Building Entrance Protector Terminal

48

1. The indoor building entrance protector terminal shall be equipped with 110-connector inputs and outputs and shall accommodate industry standard 5-pin protection modules.

2. The indoor building entrance protector terminal shall protect up to 100-pairs and shall be equipped with an internal fuse link.

3. The indoor building entrance protector terminal shall be wall or frame mountable, and able to be stacked for future expansion.

4. The indoor building entrance protector terminal shall be equipped with external ground connectors that accept 6-14 AWG ground wire.

B. Solid State Surge Protection Modules

1. The solid-state surge protector module shall be 5-pin and shall provide transient and power fault protection for standard telephone line applications.

2. The solid-state surge protector module shall be designed to provide a balanced configuration to protect against line-to-line metallic surges.

3. The solid-state surge protector module shall feature an external failsafe mechanism, which permanently grounds module under sustained high current conditions.

4. The solid-state surge protector module shall feature nanosecond response time and safe mode operation in adverse situations.

5. The solid-state surge protector module shall be UL & cUL Listed.

2.03 BONDING SHIELD CONNECTOR

A. Shield Connector

1. The purpose of the bonding shield connector is to make a stable, low resistant electrical connection between the shield of a communications cable and a ground conductor.

2. The bonding shield connector shall be tin-plated tempered brass.

PART 3 - EXECUTION

3.01 BUILDING ENTRANCE PROTECTOR TERMINALS

A. All copper circuits shall be provided with protection between each building with an entrance cable protector panel. All building-to-building circuits shall be routed through this protector. The protector shall be connected with a #6 AWG copper bonding conductor between the protector ground lug and the telecommunications room (TR) busbar.

B. Building entrance protector shall be installed in accordance with the recommendations contained in the ANSI/TIA-607-B Telecommunications Bonding and Ground Standard.

49

C. Building entrance protector panels shall be installed as per the requirements specified by the manufacturer's installation guidelines.

3.02 BONDING SHIELD CONNECTOR

A. Bonding shield connector shall be installed in accordance with the recommendations contained in the ANSI/TIA-607-B Standard.

B. Bonding shield connector shall be installed as per the requirements specified by the manufacturer's installation guidelines.

3.03 IDENTIFICATION

A. Refer to Section IV - Identification for Communications Systems for labeling details.

END OF SECTION

50

4.9 Requirements and Specifications – Communications Terminations Blocks and Patch Panels

PART 1 - GENERAL

1.01 GENERAL REQUIREMENTS

A. Applicable requirements of Section IV – Requirements and Specifications -Communications shall be considered a part of this section and shall have the same force as if printed herein full.

B. This document describes the products and execution requirements relating to Communications Termination Blocks and Patch Panels.

C. Product specifications, general design considerations, and installation guidelines are provided in this document. The successful vendor shall meet or exceed all requirements described in this document and on the drawings.

1.02 SUBMITTALS

A. Provide product data from manufacturer’s specifications.

1.03 WORK INCLUDED

A. The work included under this specification consists of furnishing all labor, equipment, materials, supplies and performing all operations necessary to complete the installation. The Contractor will provide and install all of the required material whether specifically addressed in the Specification or not.

PART 2 - PRODUCTS

2.01 APPROVED PRODUCTS

A. Approved Patch Panel Manufacturer(s)

1. Leviton 6A586-U48 2. Owner Approved Equivalent

B. Approved Optical Fiber Enclosure Manufacturer(s)

1. Leviton 5R1UH-S06 2. Owner Approved Equivalent

C. Approved Termination Block Manufacturer(s)

1. Leviton 2. Owner Approved Equivalent

51

2.02 PATCH PANELS

A. Category 6A Patch Panel

1. The Category 6A patch panel shall be compatible with 19" equipment racks, cabinets or wall mount brackets.

2. The Category 6A patch panel shall be equipped with 8-position modular ports and shall allow for termination using both T568A and T568B wiring schemes.

3. The Category 6A patch panel shall be equipped with front labeling space to facilitate port identification.

4. The connector module shall meet or exceed the Category 6 performance criteria per ANSI/TIA-568-C.2.

2.03 OPTICAL FIBER PANELS/ENCLOSURES

A. Rack Mount Optical Fiber Panel/Enclosure

1. The rack mount optical fiber panel/enclosure shall be equipped with either a swing out mechanism or a sliding drawer to access fibers.

2. The rack mount optical fiber panel/enclosure shall be capable of terminating tight-buffered or loose tube optical fiber cable.

3. The rack mount optical fiber panel/enclosure shall provide for bend radius control throughout the panel as well as storage space for slack cabling.

4. The panel/enclosure shall meet or exceed the performance criteria per ANSI/TIA-568-C.3.

5. The rack mount optical fiber panel/enclosure shall be equipped with optical fiber adapter panels. a. The optical fiber adapter panels shall accommodate either multimode

or singlemode terminated optical fiber. b. The optical fiber adapter panels shall be compatible with LC

connectors. c. OM3 laser optimized adaptors shall be aqua in color and equipped

with zirconia ceramic sleeves. d. Singlemode adaptors shall be blue (UPC) or green (APC) in color

and equipped with zirconia ceramic sleeves.

B. Wall Mount Optical Fiber Panel/Enclosure

1. The wall mount optical fiber panel/enclosure shall have a hinged door for access, with locking available for security.

2. The wall mount optical fiber panel/enclosure shall be capable of terminating tight-buffered or loose tube optical fiber cables and all popular connector types.

3. The wall mount optical fiber panel/enclosure shall provide for bend radius control throughout the panel as well as storage space for slack cabling.

52

4. The panel/enclosure shall meet or exceed the performance criteria per ANSI/TIA-568-C.3.

5. The wall mount optical fiber panel/enclosure shall be equipped with optical fiber adapter panels. a. The optical fiber adapter panels shall accommodate either

multimode or singlemode terminated optical fiber. b. The optical fiber adapter panels shall be compatible with LC

connectors. c. OM3 laser optimized adaptors shall be aqua in color and equipped

with zirconia ceramic sleeves. d. Singlemode adaptors shall be blue (UMC) or green (APC) in color

and equipped with zirconia ceramic sleeves.

2.04 TERMINATION BLOCKS

A. 110 Type Wiring Blocks/Cross-Connect Kits:

1. The 110-type wiring block shall be Category 6A. 41D6A-1FA 2. The cross-connect kits shall include all the components required to

complete a wall-mounted 110 cross-connect installation and be available in both 100-pair and 300-pair configurations for Cat5e, 96-pair and 288-pair configurations for Cat 6, and 64-pair configurations for Cat 6A. (Includes 110-blocks, connecting blocks and designation strips).

3. The termination block shall meet or exceed the performance criteria per ANSI/TIA-568-C.2.

4. Backbone blocks shall use 5-pair connecting blocks on each 25-pair row. 5. Horizontal blocks shall use 4-pair connecting blocks on each 25-pair row.

PART 3 - EXECUTION

3.01 PATCH PANELS

A. Cables shall be dressed and terminated in accordance with the recommendations made in ANSI/TIA-568-C.0 and/or ANSI/TIA-568-C.1, manufacturer's recommendations and best industry practice.

B. Pair untwist at the termination shall not exceed 13 mm (0.5 inch).

C. Bend radius of the cable in the termination area shall not exceed 4 times the outside diameter of the cable.

D. Cables shall be neatly bundled and dressed to their respective patch panel. Each patch panel shall be fed by an individual bundle separated and dressed back to the point of cable entrance into the rack or frame.

E. Each cable shall be clearly labeled on the cable jacket behind the patch panel at a location that can be viewed without removing the bundle support ties. Cables

53

labeled within the bundle, where the label is obscured from view shall not be acceptable.

3.02 OPTICAL FIBER PANELS/ENCLOSURES

A. Cables shall be dressed and terminated in accordance with the recommendations made in ANSI/TIA-568-C.0 and/or ANSI/TIA-568-C.1, manufacturer's recommendations and best industry practices.

B. Each cable shall be individually attached to the respective splice enclosure by mechanical means. The cables strength member shall be securely attached the cable strain relief bracket in the enclosure.

C. Bend radius of the optic fiber cable in the panel/enclosure shall not exceed 10 times the outside diameter of the cable.

D. Each fiber bundle shall be stripped upon entering the splice tray and the individual fibers routed in the splice tray.

E. Each cable shall be clearly labeled at the entrance to the splice enclosure. Cables labeled within the bundle shall not be acceptable.

F. A maximum of 12 strands of fiber shall be spliced in each tray

G. All spare strands shall be installed into spare splice trays.

H. Fiber slack shall be neatly coiled within the fiber splice tray or enclosure. No slack loops shall be allowed external to the fiber panel.

3.03 TERMINATION BLOCKS

A. Cables shall be dressed and terminated in accordance with the recommendations made in ANSI/TIA-568-C.0 and/or ANSI/TIA-568-C.1, manufacturer's recommendations and best industry practice.

B. Pair untwist at the termination shall not exceed 13 mm (0.5 inch).

C. Bend radius of the cable in the termination area shall not exceed 4 times the outside diameter of the cable.

D. Cables shall be neatly bundled and dressed to their respective termination block. Each termination block shall be fed by an individual bundle separated and dressed back to the point of cable entrance into the rack or frame.

E. Each cable shall be clearly labeled on the cable jacket within 12" of the termination block at a location that can be viewed without removing the bundle support ties. Cables labeled within the bundle, where the label is obscured from view shall not be acceptable.

54

F. Wall mounted termination block fields shall be mounted on communications backboard.

G. Wall mounted termination block fields shall be installed as per the requirements specified by the manufacturer's installation guidelines.

3.04 IDENTIFICATION

A. Refer to Section IV - Identification for Communications Systems for labeling details.

END OF SECTION

55

4.10 Requirements and Specifications – Communications Cable Management and Ladder Rack

PART 1 - GENERAL

1.01 GENERAL REQUIREMENTS

A. Applicable requirements of Section IV – Requirements and Specifications -Communications shall be considered a part of this section and shall have the same force as if printed herein full.

B. This document describes the products and execution requirements relating to Communications Cable Management and Ladder Rack.

C. Product specifications, general design considerations, and installation guidelines are provided in this document. The successful vendor shall meet or exceed all requirements described in this document and on the drawings.

1.02 SUBMITTALS

A. Provide product data from manufacturer’s specifications.

1.03 WORK INCLUDED

A. The work included under this specification consists of furnishing all labor, equipment, materials, supplies and performing all operations necessary to complete the installation. The Contractor will provide and install all of the required material whether specifically addressed in the Specification or not.

PART 2 - PRODUCTS

2.01 APPROVED PRODUCTS

A. Approved Horizontal Cable Management Manufacturer(s)

1. Leviton 2. B Line 3. Owner Approved Equivalent

B. Approved Vertical Cable Management Manufacturer(s)

1. Leviton 2. B Line 3. Owner Approved Equivalent

C. Approved Ladder Rack System Manufacturer(s)

1. B-Line

56

2. No Exceptions

D. Approved Tie Wrap/Velcro Strap Manufacturer(s)

1. Leviton

E. Approved C-Ring/D-ring Manufacturer(s)

1. B-Line

2.02 CABLE MANAGEMENT - HORIZONTAL

A. Horizontal Cable Management

1. The horizontal wire manager shall be compatible with 19-inch equipment racks, cabinets or wall mount brackets.

2. The horizontal cable manager shall provide support for patch cords at the front of the panel.

3. The horizontal cable manager shall be 2 rack-units in height when matched with a 2 rack-unit patch panel or switch.

4. The horizontal cable manager shall be 1 rack-unit in height when matched with a 1 rack-unit patch panel or switch.

2.03 CABLE MANAGEMENT - VERTICAL

A. Vertical Cable Management

1. The vertical cable manger shall be double-sided. 2. The vertical cable manager shall provide support for patch cords at the

front of the rack and wire management at the rear of the rack. 3. The vertical cable manager shall be a minimum width of 5". 4. Vertical cable manager color shall be black.

2.04 LADDER RACKS

A. Ladder Rack System

1. See Drawings for ladder rack system details. 2. The ladder rack system shall be securely mounted with hardware

designed for use in ladder rack systems. 3. End caps shall be installed on the exposed ends of the ladder racks,

channel supports and bolts. Protective covers shall be installed on threaded rods that come in contact with cabling plant.

4. Ladder Rack System color shall be black.

2.05 TIE WRAPS AND VELCRO STRAPS

A. Tie Wraps and Velcro Straps

57

1. Backbone cables shall be fastened to support structures with tie wraps/Velcro straps.

2. Horizontal cables shall be fastened to support structures with Velcro straps. a. Tie Wrap color shall be black. b. Velcro Strap color shall be black.

2.06 C-RINGS/D-Rings

A. C-Rings/D-rings

1. C-rings/D-rings shall be used on backboards to support cables, patch cords and cross-connect wire.

2. C-rings/D-rings shall be made of high-strength, fire-retardant material with rounded edges to prevent damage to cable and wire insulation.

PART 3 - EXECUTION

3.01 CABLE MANAGEMENT - HORIZONTAL

A. Horizontal cable managers shall be installed below patch panels in a 1:1 ratio (one horizontal cable manager per patch panel) or as indicated on Drawings.

3.02 CABLE MANAGEMENT - VERTICAL

A. Vertical cable managers shall be installed on both sides of a single equipment rack. Where two (2) or more racks are positioned in a row, vertical cable managers shall be installed between each rack and each end of the row.

3.03 LADDER RACKS

A. Ladder rack system shall be installed straight, level and perpendicular to walls and ceiling slabs.

B. Ladder racks shall be supported at 5' intervals maximum.

C. Provide all hardware, accessories, fasteners, anchors, threaded rods and support channels required to provide a complete ladder rack system.

D. See Drawings for ladder rack system details.

3.04 TIE WRAPS AND VELCRO STRAPS

A. Tie wraps/Velcro straps shall be installed around cables at intervals of 12" minimum.

B. Tie wraps shall secure cables to ladder racks using an “X” pattern.

58

C. Do not over-cinch cables.

3.05 C-RINGS/D-RINGS

A. C-ring/D-rings shall be installed on 3/4" backboard, straight and level.

3.06 IDENTIFICATION

A. Refer to Section IV - Identification for Communications Systems for labeling details.

END OF SECTION

59

4.11 Requirements and Specifications – Communications Rack Mounted Power Distribution

PART 1 - GENERAL

1.01 GENERAL REQUIREMENTS

A. Applicable requirements of Section IV – Requirements and Specifications -Communications shall be considered a part of this section and shall have the same force as if printed herein full.

B. This document describes the products and execution requirements relating to Communications Rack Mounted Power Distribution.

C. Product Specifications, general design considerations, and installation guidelines are provided in this document. The successful vendor shall meet or exceed all requirements described in this document and on the drawings.

1.02 SUBMITTALS

A. Provide product data from manufacturer’s specifications.

1.03 WORK INCLUDED

A. The work included under this specification consists of furnishing all labor, equipment, materials, supplies and performing all operations necessary to complete the installation. The Contractor will provide and install all of the required material whether specifically addressed in the Specification or not.

PART 2 - PRODUCTS

2.01 APPROVED PRODUCTS

A. Approved Power Distribution Unit Manufacturer(s)

1. Leviton 2. Eaton 3. No Exceptions

2.02 POWER DISTRIBUTION UNITS

A. Power Distribution Unit

1. The power distribution unit shall be equipped with a minimum of twelve (12) 3-prong, 120 VAC outlets, and 12' cord.

2. The power distribution unit shall be equipped with surge protection with a 20 Amp current limit.

60

3. The power distribution unit shall be equipped with a bracket that enables it to be mounted on a 19" rack, cabinet or wall mount bracket without modification.

PART 3 - EXECUTION

3.01 POWER DISTRIBUTION UNITS

A. Power distribution units shall be installed as per the requirements specified by the manufacturer's installation guidelines.

B. See Drawings for installation location on rack(s)/cabinet(s).

3.02 IDENTIFICATION

A. Refer to Section IV - Identification for Communications Systems for labeling details.

END OF SECTION

61

4.12 Requirements and Specifications – Communications Optical Fiber Backbone Cabling

PART 1 - GENERAL

1.01 GENERAL REQUIREMENTS

A. Applicable requirements of Section IV – Requirements and Specifications -Communications shall be considered a part of this section and shall have the same force as if printed herein full.

B. This document describes the products and execution requirements relating to Communications Optical Fiber Backbone Cabling.

C. Product specifications, general design considerations, and installation guidelines are provided in this document. The successful vendor shall meet or exceed all requirements described in this document and on the drawings.

1.02 SUBMITTALS

A. Provide product data from manufacturer’s specifications.

1.03 WORK INCLUDED

A. The work included under this specification consists of furnishing all labor, equipment, materials, supplies and performing all operations necessary to complete the installation. The Contractor will provide and install all of the required material whether specifically addressed in the Specification or not.

PART 2 - PRODUCTS

2.01 APPROVED PRODUCTS

A. Approved Optical Fiber Backbone Cable (Inside Plant) Manufacturer(s)

1. Berk-Tek 2. Owner Approved Equivalent

B. Approved Optical Fiber Backbone Cable (Outside Plant) Manufacturer(s)

1. Berk-Tek 2. Owner Approved Equivalent

C. Approved Optical Fiber Connectivity Manufacturer(s)

1. Leviton 2. Owner Approved Equivalent

62

D. Approved Splice Case Manufacturer(s)

1. 3M

2.02 OPTICAL FIBER BACKBONE CABLE (INSIDE PLANT)

A. Plenum - Indoor Distribution 850nm Laser-Optimized 50/125 Multimode Optical Fiber Non-Conductive (OFNP) Tight Buffered Cable (OM3)

1. Generic Characteristics a. The indoor optical fiber cable shall be available with up to twelve 900-

micron tight-buffered 250-micron fibers placed in a color-coded sub-unit bundle with aramid strength elements.

b. The indoor optical fiber cable shall meet or exceed the performance criteria found in ANSI/TIA-568-C.3.

c. The indoor optical fiber cable shall have sequential length marking printed on the cable jacket.

d. Maximum attenuation dB/Km @ 850/1300 nm: 3.5/1.5 e. Minimum overfilled modal bandwidth: 1500 MHz-km @ 850 nm. f. Minimum overfilled modal bandwidth: 500 MHz-km @ 1300 nm. g. Minimum effective modal bandwidth: 2000 MHz-km @ 850nm

B. Plenum - Indoor Distribution 8.3/125-micron Single-mode Optical Fiber Non Conductive (OFNP) Tight Buffered Cable

1. Generic Characteristics a. The indoor optical fiber cable shall be available with up to twelve 900-

micron tight-buffered, 250-micron fibers placed in a color-coded sub-unit bundle with aramid strength elements.

b. The indoor optical fiber cable shall meet or exceed the performance criteria found in ANSI/TIA-568-C.3.

c. The indoor optical fiber cable shall have sequential length markings printed on the cable jacket.

d. All singlemode fibers shall be pigtail spliced into a rack mounted optical fiber enclosure or wall-mounted enclosure.

e. The loss of fiber shall not exceed 1.0 dB per kilometer @ 1550 nm and 1.0 dB per kilometer @ 1310 nm.

C. Riser - Indoor 850nm Laser Optimized 50/125 Multimode Optical Fiber Non Conductive (OFNR) Loose Tube Cable (OM3)

1. Generic Characteristics a. The indoor optical fiber cable with up to twelve 250-micron coated

fibers placed in a color-coded sub-unit bundle with moisture-blocking gel.

b. The indoor optical fiber cable shall meet or exceed the performance criteria found in ANSI/TIA-568-C.3.

63

c. The indoor optical fiber cable shall have sequential length markings printed on the cable jacket.

d. Maximum attenuation dB/Km @ 850/1300 nm: 3.5/1.5 e. Minimum overfilled modal bandwidth: 1500 MHz-km @ 850 nm. f. Minimum overfilled modal bandwidth: 500 MHz-km @ 1300 nm. g. Minimum effective modal bandwidth: 2000 MHz-km @ 850nm

D. Riser - Indoor 8.3/125-micron, Singlemode Optical Fiber Non Conductive (OFNR) Loose Tube cable

1. Generic Characteristics a. The indoor optical fiber cable with up to twelve 250-micron coated

fibers placed in a color-coded sub-unit bundle with moisture-blocking gel.

b. The indoor optical fiber cable shall meet or exceed the performance criteria found in ANSI/TIA-568-C.3.

c. The indoor optical fiber cable shall have sequential length markings printed on the cable jacket.

d. All singlemode fibers shall be pigtail spliced into a rack mounted optical fiber panel or wall-mounted enclosure.

e. The loss of fiber shall not exceed 0.50 dB per kilometer @ 1550 nm and 0.50 dB per kilometer @ 1310 nm.

2.03 OPTICAL FIBER BACKBONE CABLE (OUTSIDE PLANT)

A. Outdoor 850nm Laser Optimized 50/125 Multimode Optical Fiber Non Conductive (OFNR) Loose Tube Cable (OM3)

1. Generic Characteristics a. The outdoor optical fiber cable with up to twelve 250-micron coated

fibers placed in a color-coded sub-unit bundle with moisture-blocking gel.

b. The outdoor optical fiber cable shall meet or exceed the performance criteria found in ANSI/TIA-568-C.3.

c. The outdoor optical fiber cable shall have sequential length markings printed on the cable jacket.

d. Maximum attenuation dB/Km @ 850/1300 nm: 3.5/1.5 e. Minimum overfilled modal bandwidth: 1500 MHz-km @ 850 nm. f. Minimum overfilled modal bandwidth: 500 MHz-km @ 1300 nm. g. Minimum effective modal bandwidth: 2000 MHz-km @ 850nm

B. Outdoor 8.3/125-micron, Singlemode Optical Fiber Non Conductive (OFNR) Loose Tube cable

1. Generic Characteristics a. The outdoor optical fiber cable with up to twelve 250-micron coated

fibers placed in a color-coded sub-unit bundle with moisture-blocking gel.

64

b. The outdoor optical fiber cable shall meet or exceed the performance criteria found in ANSI/TIA-568-C.3.

c. The outdoor optical fiber cable shall have sequential length markings printed on the cable jacket.

d. All singlemode fibers shall be pigtail spliced into a rack mounted optical fiber enclosure or wall-mounted enclosure.

e. The loss of fiber shall not exceed 0.50 dB per kilometer @ 1550 nm and 0.50 dB per kilometer @ 1310 nm.

2.04 OPTICAL FIBER CONNECTORS

A. Laser Optimized Multimode Fiber Connectivity OM3

1. The optical fiber field-installable connector shall be LC for installation onto multimode a laser optimized 50/125-micron fiber.

2. The optical fiber field-installable connector shall be compatible with 900-micron buffered fibers.

3. The optical fiber field-installable connector shall meet or exceed the performance criteria found in ANSI/TIA-568-C.3.

4. The optical fiber field-installable connector shall have a maximum Loss of 0 .5 dB.

5. The optical fiber adapter module that occupies the faceplate shall be equipped with zirconia ceramic sleeve.

6. Laser optimized multimode fiber connector color shall be aqua.

B. Singlemode Fiber Connectivity

1. The optical fiber field-installable connector shall be LC, for installation onto singlemode 8.3/125-micron fiber.

2. The optical fiber field-installable connector shall meet or exceed the performance criteria found in ANSI/TIA-568-C.3.

3. The optical fiber field-installable connector shall be compatible with 900-micron buffered fibers or 250-micron loose-tube fibers.

4. The preferred method of terminating loose-tube singlemode fiber is pigtail splicing into a rack mounted optical fiber panel or wall-mounted enclosure. Pigtails shall be factory terminated and 3 meters in length. A fiber enclosure with slack storage trays must be used when pigtail-splicing method is used.

5. The splice loss through each connector pair shall not exceed 0.50 dB. 6. The optical fiber adapter module that occupies the faceplate shall be

equipped with zirconia ceramic sleeve. 7. Singlemode fiber connector color shall be blue (UMC) or green (APC).

2.05 SPLICE CASES

A. Canister Splice Case

65

1. Splice cases shall be water tight and designed for outside plant applications.

2. All splice trays, seals and hardware shall be from the same manufacturer as the splice case.

3. Splice trays shall utilize heat-shrink seals. 4. See Drawings for size requirements.

PART 3 - EXECUTION

3.01 BACKBONE CABLES (INSIDE PLANT)

A. Cables shall be dressed and terminated in accordance with the recommendations made in ANSI/TIA-568-C.0 and/or ANSI/TIA-568-C.1, manufacturer's recommendations and best industry practices.

B. Backbone cables shall be installed separately from horizontal distribution cables

C. A plastic or nylon pull cord with a minimum test rating of 90 Kg (200 lb.) shall be co-installed with all cable installed in any conduit.

D. Where cables are housed in conduits, the backbone and horizontal cables shall be installed in separate conduits

E. Exposed cables must be OFNP rated if installed in an air return plenum. Riser rated cables shall be installed in metallic conduit if installed in an air return plenum.

F. Where backbone cables and distribution cables are installed in a cable tray or wireway, backbone cables shall be installed first and bundled separately from the horizontal distribution cables.

G. Leave 10' of slack on each end of fiber backbone cable.

H. Backbone cables spanning more than three floors shall be securely attached at the top of the cable run with a wire mesh grip and on alternating floors or as required by local codes.

I. Vertical runs of cable shall be supported to messenger strand, cable ladder, or other method to provide proper support for the weight of the cable.

J. Large bundles of cables and/or heavy cables shall be attached using metal clamps and/or metal banding to support the cables.

K. The cable's minimum bend radius and maximum pulling tension shall not be exceeded. Refer to manufacturer's requirements.

66

L. Each optical fiber cable shall be individually attached to the respective enclosure by mechanical means. The cables strength member shall be securely attached the cable strain relief bracket in the enclosure.

M. Each optical fiber cable shall be clearly labeled at the entrance to the enclosure. Cables labeled within the bundle shall not be acceptable.

N. Each fiber bundle shall be stripped upon entering the splice tray and the individual fibers routed in the splice tray.

O. A maximum of 12 strands of fiber shall be spliced in each tray

P. All spare fiber strands shall be installed into spare splice trays.

Q. Fiber slack shall be neatly coiled within the fiber splice tray or enclosure. No slack loops shall be allowed external to the fiber panel.

3.02 BACKBONE CABLES (OUTSIDE PLANT)

A. All OSP cables brought to the Entrance Facilities shall have 15 ft of slack coiled and secured to the wall in the proximity of the fiber enclosure.

B. All cables shall be tagged and identified within each handhole/maintenance hole.

C. Place initial cables in bottom conduits to facilitate easy subsequent cable placement.

D. Place leader guard in the duct before placing cable to prevent damaging the cable sheath on the sharp edge of the duct.

E. Ventilate maintenance where gas has been detected before entering the maintenance hole.

F. To ensure that the optical fiber cable's qualities and characteristics are not degraded during installation, excessive pulling tensions and short bending radii will not be allowed. The maximum pulling tension is 600 lbs. The minimum bending radius for cable under tension is 20 times the outside diameter of the cable and for cable at rest is 10 times the outside diameter of the cable.

G. A 600 lb. break-away swivel, along with a slip clutch capstan winch that shows the dynamometer (pulling tension) reading, shall be used at all times during pulling.

H. At each splice location the cable ends will be sealed watertight at all times. Reels will be continuously manned during cable installation.

67

I. Contractor shall coil 60 feet of spare optical fiber cable in each handhole/maintenance hole without a splice and 75 feet of each optical fiber cable in each handhole/maintenance hole with a splice. Cable coils shall have at least two points of support on the optical fiber racking system.

J. When mounting the optical fiber slack coils, the minimum bend radius shall not be exceeded; this radius is equal to 10 times the outside diameter of the cable in a static application and 20 times the outside diameter in a dynamic application. At anytime during the entire handling process of the optical fiber cable, as much care as possible should be maintained and all the manufacturer's recommendations should be followed.

3.03 OPTICAL FIBER CONNECTIVITY / SPLICING

A. Optical fiber connectors shall be installed as per the requirements specified by the manufacturer's installation guidelines.

B. All splicing shall be of the fusion type made under Light Injection and Detection Mode, whenever applicable. The Contractor shall provide certified and experienced personnel for splicing.

C. Contractor's tools and equipment shall be in excellent working order. Any worn or improperly working tools shall be discarded and not used on this project. All fusion splicers shall be calibrated and labeled according to the manufacturer's specifications. Contractor shall submit certification of calibration for the fusion splicers to the Engineer.

3.04 SPLICE CASES

A. Splice Cases shall be installed as per the requirements specified by the manufacturer's installation guidelines.

3.05 IDENTIFICATION

A. Refer to Section IV - Identification for Communications Systems for labeling details.

END OF SECTION

68

4.12 Requirements and Specifications – Communications Faceplates and Connectors

PART 1 - GENERAL

1.01 GENERAL REQUIREMENTS

A. Applicable requirements of Section IV – Requirements and Specifications -Communications shall be considered a part of this section and shall have the same force as if printed herein full.

B. This document describes the products and execution requirements relating to Communications Faceplates and Connectors.

C. Product specifications, general design considerations, and installation guidelines are provided in this document. The successful vendor shall meet or exceed all requirements described in this document and on the drawings.

1.02 SUBMITTALS

A. Provide product data from manufacturer’s specifications.

1.03 WORK INCLUDED

A. The work included under this Specification consists of furnishing all labor, equipment, materials, supplies and performing all operations necessary to complete the installation. The Contractor will provide and install all of the required material whether specifically addressed in the Specification or not.

PART 2 - PRODUCTS

2.01 APPROVED PRODUCTS

A. Approved Copper Connectivity Manufacturer(s)

1. Leviton Part Number 6110G-R*6 2. Owner Approved Equivalent

B. Approved Faceplate Manufacturer(s)

1. Leviton Part Number 42080-2WS 2. Owner Approved Equivalent

C. Approved Surface Mount Box manufacturer(s)

1. Leviton 2. Owner Approved Equivalent

69

2.02 COPPER CONNECTIVITY

A. Voice/Data Jacks

1. Category 6A, 8-Position, 8-Contact (8P8C) Modular Jack a. The connector module shall meet or exceed the Category 6A

performance criteria per ANSI/TIA-568-C.2. b. The eight-position connector module shall accommodate six-position

modular plug modular cords without damage to either the cord or the module.

c. The connector module shall be designed for use at the work area (WA), communications room (TR) and/or equipment room (ER) without modification.

d. The connector module shall be available in both the T568A and T568B wiring configurations within the same module.

e. The connector module shall have an insulation displacement connection featuring insulation slicing of 22 to 24 AWG plastic-insulated solid copper conductors forming a gas-tight connection.

f. Icons shall be used if offered from the manufacturer. g. Connector shall have RFT (Retention Force Technology)

2.03 FACEPLATES

A. Faceplates

1. The faceplate housing the connector modules shall have no visible mounting screws.

2. It shall be possible to install the connector modules in wall-mounted single- and dual-gang electrical boxes, utility poles and modular furniture (cubicle) access points using manufacturer-supplied faceplates and/or adapters.

3. The faceplate housing the connector modules shall have the option of being mounted on adapter boxes for surface mount installation.

4. The faceplate housing the connector modules shall have a labeling capability using built-in labeling windows, to facilitate outlet identification and ease network management.

5. The faceplate housing the connector modules shall provide flexibility in configuring multimedia workstation outlets that respond to present or future network needs such as audio, video, coaxial and optical fiber applications.

6. Color shall be same as electrical faceplates.

2.04 SURFACE MOUNT BOXES

A. The surface mount box shall accommodate connections of any type, UTP, optical fiber or coax.

B. The surface mount box shall have internal storage space for slack cabling and a built-in spool for controlling cable bend radius.

C. Color shall be same as electrical faceplates.

70

PART 3 - EXECUTION

3.01 COPPER CONNECTIVITY

A. 8-position, 8-contact (8P8C) modular jacks shall be installed in accordance with manufacturer's recommendations and installation guides, and best industry practices.

B. Pair untwist at the termination shall not exceed 13 mm (0.5 inch).

C. Data jacks, unless otherwise noted in Drawings or fiber adapter modules are present, shall be located in the bottom position(s) of each faceplate. Data jacks in horizontally oriented faceplates shall occupy the right-most position(s).

D. Voice jacks, unless otherwise noted in Drawings, shall occupy the top position(s) on the faceplate. Voice jacks in horizontally oriented faceplates shall occupy the left-most position(s).

3.02 FACEPLATES

A. Blank inserts shall be installed where ports are not used.

B. The same orientation and positioning of jacks and connectors shall be utilized throughout the installation.

C. Faceplates shall be installed straight and level.

D. Faceplates shall be installed at the same heights as electrical faceplates.

3.03 SURFACE MOUNT BOXES

A. Blank inserts shall be installed where ports are not used.

B. The same orientation and positioning of jacks and connectors shall be utilized throughout the installation.

C. Surface mount boxes shall be installed straight and level.

D. Surface mount shall be installed at heights as electrical receptacles.

3.04 IDENTIFICATION

A. Refer to Section IV - Identification for Communications Systems for labeling details.

END OF SECTION

71

**Appendices**

A. JPD-DataCenter Architectural Design Drawings

B. JPD-DataCenter Electrical Design Drawings

C. JPD-DataCenter Fire Protection Design Drawings

D. JPD-DataCenter General Design Drawings

E. JPD-DataCenter Interior Design Drawings

F. JPD-DataCenter Mechanical Design Drawings

G. JPD-DataCenter Telecommunications Design Drawings

H. EATON BladeUPS Specifications for Data Center

72

Addendum 1

New Jupiter Police Department HQ & Data Center Low Voltage Cabling

The following information supersedes information contained in the documents previously postedfor RFP–IS-100119, New Jupiter Police Department HQ & Data Center Low Voltage Cabling. Additional addendum will be posted to answer questions submitted prior the deadline.

S E C T I O N I

REQUEST FOR PROPOSAL (RFP) GUIDEL I NES

1.1 Proposal Submission and Withdrawal The deadline to submit a proposal has been extended until 2:00 p.m., local time November 25, 2019.

Printed proposals with sealed bids will only be accepted by the Town Clerk along with one electronic

version on CD in PDF format. Email submissions will not be accepted.

Printed copy must be submitted to prior to the deadline:

Town ClerkTown of Jupiter 210 Military TrailJupiter FL, 33458

Sealed Bid shall be labeled:

Town ClerkTown of Jupiter210 Military TrailJupiter FL, 33458November 25, 2019TOJ Police Department HQ & Data Center Low Voltage CablingRFP-IS-100119-0-2020/kc

All proposals must be received by the date and time specified in this addendum. The submission time

must be and shall be scrupulously observed. Under no circumstances shall proposals submitted after the

time specified be considered. The Town staff shall in no way be responsible for delays caused by any

occurrence.

1.3 InquiresInterested Respondents may contact King Wekenmann, via fax (561) 741-2616 or email

[email protected] and must include TOJ Police Department HQ & Data Center Low Voltage Cabling in

the subject line. The Town contact will receive written requests for clarification concerning the meaning

or interpretations of the RFP, until Wednesday 5:00 p.m. EST, November 13, 2019.

Town personnel are authorized only to direct the attention of prospective Respondent(s) to various

portions of the RFP so that they may read and interpret such for themselves. No employee of the Town

is authorized to interpret any portion of this RFP or give information as to the requirements of the RFP

in addition to what is contained in the written RFP document or subsequent addendums.

S E C T I O N II

EV AL U ATION OF PROPOSALS

2. 0 Evaluation M ethod a n d CriteriaG eneral – T he T own shall be t he sole j udg e of their own best int er est s, the proposals, and t he r esult ing neg ot iat ed agr eem ent . T he T own ’s decisions wil l be f inal.

S e l e c t i o n o f a R e s p o n d e n t t o p r o v i d e t h e h a r d w a r e , m a t e r i a l s , a n d s e r v i c e s s o u g h t h e r e i n w i l l b e b a s e d o n t h e T own’s eva luat ion crit er ia a n d wil l include, but shall not be lim it ed t o, consider at ion of t he f ollowing :

CRI TERI O N PO I NTS

A

R e f e r e n c e s :

Score based on references provided after checking for accuracy and confirmation of successful completion of representative work.

50

B

Total Cost:

Prices including labor for complete solution to outfit the building and Data Center per the plans, engineering and architectural drawings, material specification sheets, etc.

40

CProposal Submittal:

Quality of proposal response.

10

T ot al Maxim um Point s 100

Based on the preliminary ranking of the written Proposal(s) received, the Town will select the Proposal that is deemed to be the best fit with regard to both meeting the requirements and total cost.

2.1 SelectionSelection and award of contract shall be done in accordance with the State of Florida and Town policies

and procedures, the Town will evaluate, rank all qualified RFP(s) and recommend to the Town Council

the selected proposal. A selection committee meeting for the TOJ Police Department HQ & Data Center

Low Voltage Cabling project will be held on December 3, 2019 at 1:00 p.m. in the 1st floor conference

room, Jupiter Town Hall 210 Military Trail, Jupiter, FL 33458. The Town’s decisions will be final.

S E C T I O N III

3 . 0 Proposal Response FormatTo facilitate the analysis of responses to the RFP, the Proposer is required to prepare their proposals in accordance with the instructions outlined in this section. Responses must be delivered before the deadline to the address indicated in Section 1. All responses shall include the following sections separated by clearly marked labels.

Section Title1 Statement of Qualifications2 Client References3 Exceptions and Deviations4 Materials List5 Pricing Quote

3.1 Statement of QualificationsThis part of the response to the RFP should be limited to a brief narrative not to exceed two (2) pages describing the qualifications of the Respondent to meet the requirements of the proposal and completion of the work on time, within budget, with comparative examples of past successes.

3.2 Client ReferencesThis part of the response to the RFP shall include the Client Reference information requested. Respondent shall include a minimum of three (3) references of successfully completed jobs of similar size and scope and not more than 6 years old. Each reference shall be printed on a separate sheet of 8.5” x 11” paper.

References are to include:Name of Company/Organization:Contact Name:Contact Title:Contact Phone:Contact Email:Type of Facility Constructed:Size of Construction Project (Sq. Ft.):Amount of Contract Award:Time Frame of Project: (Begin / Complete)

3.3 Exceptions and DeviationsThis part of the response to the RFP shall include any claims, in list form, of exceptions or deviations from the requirements of the RFP. If any exceptions or deviations are claimed the Respondent must cite the specific section, subsection, and provide a reason and/or reasonable substitute.

3.4 Materials ListThe part of the response shall include a list of all materials proposed with applicable descriptions and

part numbers.

3.5 Sealed Pricing Quote

This part of the response to the RFP shall include the Respondent’s best and final offer price bid including all parts, materials, labor to complete the job as stated in this RFP and determined by thorough analysis of this RFP including all supplied design drawing and materials.

Sealed bids shall be submitted on paper and on CD in electronic PDF format in accordance with the instructions in section 1.1 Proposal Submission and Withdrawal.

Addendum 2

Date: November 6, 2019

New Jupiter Police Department HQ & Data Center Low Voltage Cabling

The following questions were received prior to November 5, 2019. They have been reviewed by the Town of Jupiter and answers have been provided below each question.

If additional questions are received a final addendum will be issued on November 15, 2019.

1) Sheet T-302 under 02 it says First Floor Plan - Technology, but isn't this 2nd Floor? Need confirmation.a) 2nd floor

2) Also Sheet T-302, under 02 and 04 it is showing what seems to be (4) 2-Post Racks, but on sheet T-202 in room 223 it is showing what seems to be (8) 2-Post Racks. Please confirm which is correcta) Modified design will be 10 – 4-post racks and no 2-post racks.

3) Sheet T-302 under 04 it is showing (8) 12" Radius Drops from the 24" Ladder Tray, but in 02it does not show the ladder tray over the Racks, please confirm what is correct.a) All racks and cabinets should have Radius Drops.

4) Sheet T-302 under 03 it is not showing a 12" Radius Drop to the Cabinets is this correct?a) Again all cabinets should have Radius Drops.

5) Please confirm the part number of the Dell Cabinetsa) Cabinet manufacturer not defined.

6) Please confirm the use of 2-Post or 4-Post Racks for 1st Floor and 2nd Floora) 4-post cabinets on first floor and second floor.

7) Sheet T-301 under 01, it is not showing the Ladder Tray layout, can this be provided like it ison Sheet T-302 under 02?a) Use T302-02 as basis for T-301-01 design.

8) Is the EC responsible for Providing all Sleeves for the LV as it states on Sheet T-001 under General Notes # 10? If so is the LV responsible for Fire Caulk?a) Yes, and Yes.

9) Floor Box location on Sheet T-201, these are to be Gel-Filled cable, but is the EC providing Home Run Conduit back to IT Room 114?a) EC providing conduit.

10) Who is responsible for making sure the existing Pathways on Sheet T-010 are useable?a) GC

11) Who is responsible for the Max Cell mentioned on Sheet T-010? It says 3-Cell Maxcell but not what size, i.e. 1" / 2" / 3" Cell Size?a) GC

12) Need a exact quantity and size of CAT 6A Patch Cables to be supplied, we can't just go off of 1', 5', 7', 10' as needed. IT needs to tell us what length

a) Proposer shall make best estimate for sizes needed based on information provided.13) Access Control System by others?

a) Yes14) Sheet T-201 on the left side of page it says 2-Strand Fiber in Inner-duct in 2 place, can

someone explain what this is for?a) 2 – strand fiber from IDF room 114 to Body Camera room 142.

15) Is LV to provide Camera Cabling infrastructure only to all cameras?a) Yes

16) Are WAPs and Cameras to be on their own Patch Panels?a) Yes

17) AV Plates that are mentioned on T-201/202, are these HDMI Cables to be supplied and installed by LV?a) No, they are supplied by A/V contractor

18) Are we to provide labor to install WAPs?a) No

19) Sheet T-301 is says under general notes and key notes, riser fiber. Is this correct or does it need to be plenum. Assuming riser since it is in conduit, just need to confirma) Not Plenum

20) Sheet T-301, can someone please explain General Note # 9, the 24-Strand SM Fiber needs tobe ran from Where to Where?a) First floor IDF Rm #114 to Second Floor Data Center Rm #223.

21) Is LV to terminate RG-6 Coax Cable in IT Rooms, or leave coiled?a) Terminate

22) Sheet T-301 under 04 and 05 it is showing 4-Data Outlets but on Sheet T-201 in Room 114 there is only a Dual Outlet showing, please confirm which is correct.a) Sheet T-301 is correct

23) Please confirm as to what cable is to be used, CAT 6A or CAT 6, it states CAT 6 all over the Sheets, but says CAT 6A in specs?a) CAT 6A everywhere

24) On sheet T-301 who is responsible to provide the 2U UPS per floor?a) Requesting that the LV proposer supply the UPS per floor based on the following

specifications.25) For the speaker locations are we to provide only a 16/2 cable to each speaker location and

speakers/amps will be provided and installed by others?a) Speakers will be removed from project, no need to run cable.

26) Drawing T-011 detail 5. Are we to provide & install the Entry Pedestal or only the cabling?a) Cabling

27) Are TV mounts and installation by others?a) Yes

28) Do we need to carry the Access Control pricing or is this a separate bid?a) Separate bid

29) Are we to include the XLR cabling for the microphones?a) A/V contractor – separate bid

30) Drawing T-001 under Symbols Legend for the TV symbol calls for (1) RG6 cable to each TVsymbol. Drawing T-403 calls for a shielded Category 6 cable and a Balun.a) T-001 is correct, RG6 to each TV.

31) Drawing T-302 Elevation 4 shows Key Notes 7 & 8 on each cabinet but there is no Key Note7 & 8 listed.a) There are No 7&8 Key Notes.

32) Can you please provide a part number for the (4) Dell Cabinets shown on Drawing T-302? Do these cabinets require PDU's or UPS? If so can you, please provide part numbers.a) 4-Post rack (cabinets), do not need to be Dell. Proposer may provide any

manufacturer as long as it meets specifications. PDU’s and UPS are required.

33) On page 1 of the specification above the heat loaded table it states the quantity of cabinets required for the Data Center as (10) but only (4) are shown on Drawing T-302 please clarify.a) 10 cabinets are required – page 1 is correct.

34) Drawing T-302 Detail #2 calls for (2) Liebert CRV 35W are we to provide these?a) No

35) Can you please clarify the fiber scope of work with regard to the Carriers fiber and Campus fiber interconnect? I believe on Drawing T-301 Key notes 7 & 8 and General Note #9 are theonly fibers that are defined as needing to be installed.a) LV to run fiber between First and Second floor only and to Body Camera Room

#142 from IDF Room #114. Exterior campus fiber will be under separate bid.36) Is the LV responsible for providing the UPS for each Rack / Cabinet?

a) Yes, not per cabinet but per specifications provided in the addendum.37) On plan sheet T-301 detail 1, there is no ladder rack shown in the prints in first floor IDF,

will this be updated to show ladder racking?a) No, see proposal on T-302-02

38) Plan sheet T-202 shows four (4) cabinets and eight (8) 2 post network racks in the MDF, plansheet T-302 detail 2 shows four (4) 2-post racks. Please clarify which design we are to quote.a) 10 4-post cabinets as stated on page 1 of RFP.

39) Specifications part numbers have Cat 6a cable and plans show Cat 6, which cable type is to be used?a) Cat6A

40) If Cat 6a is required, the vertical wire management size will be insufficient. We recommend 6” and 10” wire managers.

a) Propose your best alternative as necessary41) Is the CATV and AV cables included for the low voltage contractor or AV contractor? If so,

please provide a specification.a) CATV and AV provided by CATV and AV contractors reflective on statement in

RFP.42) On sheet T501 section M8 is shows a coax on the face plate, however on sheet T401 is shows

UTP CAT6a with a Balun, please clarify.a) See question 30 above.

43) T-302 General notes #9 refers to 24 strand single mode riser fiber, should this be single or multimode?a) Multimode

44) Ladder rack on prints has two sizes 24” and 12” ---With Cat 6A cabling, maximum bundle

size of 50 cables and the separation of technologies by color---18-24” would be preferred.

a) 18-24” ladder racks are acceptable.

45) Are different color cables to differentiate technologies desired or would j-Hook Tree be adequate?

a) Patch cables should be different color to differentiate technologies but in addition j-Hook tree for network runs would be acceptable.

46) Will a Demarcation extension to MDF space be needed?a) Yes

47) Will LV be pulling camera cables?a) Yes

Addendum 3

Date: November 7, 2019

New Jupiter Police Department HQ & Data Center Low Voltage Cabling

The following questions were received after Addendum 2 was issued on November 6, 2019 and relate directly to answers previously provided. They have been reviewed by the Town of Jupiter and answers have been provided below each question.

If additional questions are received a final addendum will be issued on November 15, 2019.

1. Will Plenum or non-plenum CAT 6A Cable be required?

a. Non-plenum

2. Are we going to get new prints showing the changes made on Addendum 2?a. No. Since no quantities, lengths, or materials changed which could not be explained or

represented in text form no new prints will be issued.

Addendum 4

Date: November 14, 2019

New Jupiter Police Department HQ & Data Center Low Voltage Cabling

The following questions were received after Addendum 3 was issued on November 7, 2019 and following the non-mandatory pre-bid meeting held at the Town of Jupiter on November 12, 2019. They have been reviewed by the Town of Jupiter and answers have been provided below each question.

1. The Access Control Cabling---Is this under the LV contract or will the cabling be a part of the Access Control RFP?

a. Access Control Cabling will not be a part of the LV bid. It will be included in a separate bid for the Access Control System.

2. Understanding that ALL patch cords will be provided by the successful LV Contractor---The installation of those patch cords will be only in the Data Center space and not the work area space. Is this accurate?

a. Yes. 3. How will the cabinets be arranged in the data center?

a. 2 parallel rows of 5 cabinets each (10 cabinets total) in the center of the room with a single ‘hot aisle’ in the center.

Request for Proposal RFP-IS-100119

PREPARED FOR:

Town of Jupiter

Police Department HQ & Data Center

Low Voltage Cabling

Prepared by: Joe Russo

Vice President

Accelerated Technologies

801 Maplewood Drive, Suite 16

Jupiter, FL 33458

[email protected]

off: 561-427-0600 ext. #214

fax: 561-746-5974

Jupiter Police Department HQ & Data Center – RFP-IS-100119

TABLE OF CONTENTS

Section Title

1 Statement of Qualifications

2 Client References

3 Exceptions and Deviations

4 Materials List

5 Pricing Quotes

Other Information:

6 Certifications/Product Specs - Berk-tek/Leviton

7 Certifications/Product Specs - Eaton/B-Line

Professional Recommendations:

8 Data Center Cage Enclosure Option/Pricing

Jupiter Police Department HQ & Data Center – RFP-IS-100119

SECTION 1: STATEMENT OF QUALIFICATIONS

Accelerated Technologies would like to take this opportunity to thank you for the

opportunity to bid on this project. It is our goal to present a technically superior solution

while remaining cost competitive.

Accelerated Technologies has specialized in structured cabling installation

services for new construction, remodels and retro-fit projects since 1999. For over 20

years we have provided South Florida customers with professional low voltage cabling

solutions. Our past performance is a testament to the pride our company takes in

completion of projects on time and under budget.

Today’s technology demands a cabling infrastructure that is installed and

maintained by professionals that have spent their careers focused on structured cabling.

Our ongoing training through industry recognized organizations such as BICSI, as well as

manufacturer partners such as Berk-Tek/Leviton, insures you will get the maximum

bandwidth and performance from your cable plant.

Our technicians adhere to all the latest EIA/TIA standards and all work is tested

and certified. In addition, it is Accelerated Technologies’ policy to provide a work

environment that is inherently safe - we enforce a strict safety program that follows

OSHA safety standards.

Accelerated Technologies has designed and engineered the following proposal

based on the building plans provided, RFQ documents, specifications given in the site

survey, and the recommendations of the Accelerated Technologies design staff.

Jupiter Police Department HQ & Data Center – RFP-IS-100119

SECTION 2: CLIENT REFERENCES

CLIENT REFERENCE #1

Els Center of Excellence

18370 Limestone Creek Rd.

Jupiter, FL 33458

Contact: Gino Colon

PH: 561-598-6200

Title: Director of Information Technology

Email: [email protected]

Construction Type: Multi Building Education Campus

Square Footage: Over 100,000 sq, ft.

Contract: $451,000.00

Project Date: July/2015-April/2017

Jupiter Police Department HQ & Data Center – RFP-IS-100119

CLIENT REFERENCE #2

Travis Contracting Services (Merchant Lynx Services Project)

7654 SW Jack James Drive

Stuart, FL 34997

Project Address: 348 Hiatt Drive, Palm Beach Gardens, FL 33418

Contact: Joe Travis

PH: 561-441-0953

Title: General Contractor/Owner

Email: [email protected]

Construction Type: General Office, Multi Floor Building

Square Footage: 18,448 sq. ft.

Contract: $192,000.00

Project Date: July/2018-Jan/2019

Jupiter Police Department HQ & Data Center – RFP-IS-100119

CLIENT REFERENCE #3

Caridad Center

8645 W. Boynton Beach Blvd.

Boynton Beach, FL 33431

Contact: Neftali Rodriquez

PH: 561-737-6336

Title: Director of Information Technologies

Email: [email protected]

Construction Type: General Office, Multi Floor Building

Square Footage: Approx. 15,000 sq. ft.

Contract: $67,000.00

Project Date: May/2019

Jupiter Police Department HQ & Data Center – RFP-IS-100119

CLIENT REFERENCE #4

Document Storage Systems, Inc.

701 US Highway 1

North Palm Beach, FL 33408

Contact: John Beasley

PH: 561-284-7000

Title: Information Technologies

Email: [email protected]

Construction Type: General Office, Multi Floor Building

Square Footage: Approx. 27,000 sq. ft.

Contract: $108,000.00

Project Date: March/2014-May/2014

Jupiter Police Department HQ & Data Center – RFP-IS-100119

SECTION 3: EXCEPTIONS AND DEVIATIONS

Accelerated Technologies assumes free and ready access to all areas required for

completion of this project.

Customer provided Modular furniture will be designed and assembled with the proper

communication poles and raceways to support low voltage cable requirements.

T-001 – General Notes: Section - Conduit Routing General Notes #8 - Accelerated

Technologies assumes all necessary conduits, including firewall sleeves, will be provided

to the MDF, IDF and each Work Area Outlet/Device location.

All cable proposed is non plenum rated.

T-301 – General Notes #4 – Accelerated Technologies will not provide

Telecommunications Readyspec RB-A4848-PPW backboard on all walls indicated with 2

coats of light colored gray paint. This scope of work is typically provided by the general

contractor.

T-301 – Key Notes #7 – Accelerated Technologies will not provide 48 strand singlemode

fiber from 1st floor IDF to 2nd floor MDF but will be providing one (1) 24 strand OM3

multimode fiber from 1st floor IDF to 2nd floor MDF for customer internal data network.

T-201 indicates a connection from the IDF on the first floor to the body cam room on the

first floor but does not specify what type of cable connection should be (copper or fiber).

Accelerated Technologies has included the installation of one (1) 6 strand OM3

mulitmode fiber from the IDF to the body cam room. Both ends will terminate on 2RU

fiber patch panels with one (1) 12U wall mounted equipment cabinet installed in the body

cam room.

T-301 – Key Notes #8 contradicts T-401 Systems Fiber Block Diagram notes. The notes

on T-401 indicate carriers fiber will extend to the 2nd floor Data Center/MDF by each

carrier. Whereas T-301 #8 indicates LV contractor to install 48 strand singlemode fiber to

2nd floor Data Center/MDF for carrier connections. Accelerated Technologies

recommends all carrier fiber are extended as a continuous fiber run to their points of

demarcation in the 2nd floor Data Center/MDF.

Jupiter Police Department HQ & Data Center – RFP-IS-100119

EXCEPTIONS AND DEVIATIONS (Continued)

T-001 – General Notes #5 – Accelerated Technologies is not providing mounting

brackets for ceiling mounted equipment or installation labor for said brackets or the

ceiling mounted devices themselves. This includes, but not limited to wireless access

points WAP’s, ceiling mounted speakers, or ceiling mounted CCTV cameras.

T-001- Section Symbols Legend – The symbol indicated as AV instructs contractor to

install one (1) HDMI cable from AV faceplate to presentation device but does not

indicate path or to which specific presentation device when multiple devices are in the

same room. No HDMI cable is included in this proposal.

RFP Bid Document – Section 4.12 – Requirements Specifications – Communications

Optical Fiber. Regarding installation of “Outside Plant” optical fiber. Accelerated

Technologies has included no Outside Plant fiber optic cabling in this proposal. The

scope of work for Outside Plant is typically performed by telecom carriers or contractors

specializing in long haul fiber solutions.

RFP Bid Document – Section 4.8 – Requirements and Specifications – Communications

Entrance Protection. Outside plant contractor or carriers should include any requirements

in this category in their scope of work.

Any damage caused by Accelerated Technologies to work already in place will be

repaired at Accelerated Technologies’ expense.

Accelerated Technologies is responsible for its own clean-up and haul to dumpster

provided by General Contractor.

Accelerated Technologies Safety: Accelerated Technologies work at a minimum shall

specifically comply with the Federal Occupational Safety and Health Act (OSHA).

All cabling design and engineering will follow industry standards.

Jupiter Police Department HQ & Data Center – RFP-IS-100119

SECTION 4: MATERIALS LIST

Low Voltage Main Components – Material List:

Description Part # Qty

Berk-Tek Cat 6a non plenum cable – Blue/Gray 11084689 149,000 Ft.

Leviton Cat 6a jacks – blue/white 6110G-R** 745

Leviton 6 – port faceplate – white 42080-6WS 278

Leviton 48 Port Cat 6A Patch Panel 6A586-U48 18

B-Line J-Hooks BCH64 800

Eaton Cabinet RSN4282B 10

Eaton Floor Mount 4 Post Rack (84H x 19W) SB838094BFB 2

Leviton Vertical Wire Management LEV-492RU-VFR 4

Leviton Horizontal Wire Management LEV-492RU-HFR 31

Leviton Fiber Trunk 24F OM3 EW2024RR200F36B36BY 200 ft.

Fiber Trunk 6F OM3 EW2006RR200F36B36BY 200 ft.

Eaton 12U Wall Mount Cabinet VLWM2420 1

Leviton 2U Fiber Patch Panel 5R2UM-S06 4

Leviton Fiber Adapter Panel - OM3/24LC 5F100-4QL 2

Leviton Fiber Adapter Panel - OM3/124LC 5F100-2QL 2

Leviton Fiber Patch Cord OM3 LC/LC-5M 5LDLC-M05 36

B-Line 24’ x 10” cable tray SB1724FB 11

B-Line wall mount kit SB211324FB 6

B-Line runway support SB2118AFB 20

B-Line runway drop-out SB212924FB 12

B-Line runway side drop-out SB2129SD24FB 4

B-Line splice kit SB2107FB 11

B-Line T/L splice kit SB2101A 5

Note: See Section 6 and 7 for Additional Product Specifications

Jupiter Police Department HQ & Data Center – RFP-IS-100119

MATERIALS LIST (continued)

Appendix H – UPS and Power Distribution – Materials List:

Description Part # Qty

Eaton BladeUPS 12kW 208V Parallel ZC121P060100000 4

Eaton BladeUPS 12kW 208V Parallel ZC121P068100000 1

Eaton 9PX UPS 9PX5K 2

Eaton Power Distribution Module EBA-310-10 16*

Eaton Power Distiribution Module EMI331-10 14*

PW RPM, 12KW, L21-30R/L21-30R, 208V Y0311402210000 2

PW RPM, 12KW, L21-30R/L21-30R, 8 FEET Y03111022100000 2

BLADEUPS BUSBAR, TOP ENTRY 103007573-5591 1

Environmental Monitoring Probe 116750224-001 1

Eaton Professional Startup, 7x24 SU05NXXX-0080 1

UNIVERSAL WIREWAY 103007569-5591 1

BLADEUPS AND WIREWAY INSTALL AS00N00-WIRE 1

BladeUPS 3U EBM 103005747-6591 5*

Kit, Harness Extension EBM To UPS, 36” 103006348-001 5*

* Depends on Appendix H Design

Note: See Section 7 for Additional Product Specifications

Jupiter Police Department HQ & Data Center – RFP-IS-100119

SECTION 5: PRICING QUOTE

Low Voltage Main Components:

Six hundred nine (609) Cat 6A Non Plenum Voice/Data drops

Thirty eight (38) Cat 6A Non Plenum Wireless Access Point Data drops

Forty six (46) Cat 6A Non Plenum CCTV drops

Fifty two (52) Cat 6A Non Plenum Television drops

Twenty six (26) Quad Shield RG6 Coaxial Non Plenum Cable – Television drops

One hundred ten (110) feet – Eaton 24” Overhead Cable Tray w/accessories

One (1) 24 Strand Multimode OM3 Fiber Riser Cable – MDF to IDF

One (1) 6 Strand Multimode OM3 Fiber Riser Cable – IDF to Body Cam Room

Ten (10) Eaton Cabinets w/ Wire Management – (MDF - Data Center)

Two (2) Eaton 4 Post Racks w/ Wire Management (IDF)

One (1) Eaton Wall Mount Cabinet (Body Cam Room)

Low Voltage Main Components Pricing: $185,851.00

Jupiter Police Department HQ & Data Center – RFP-IS-100119

PRICING QUOTE (continued)

Appendix H – Original Design Request:

MDF – Data Center:

One (1) BladeUPS 60 kW Bus Bar, Built for Top Entry ONLY

One (1) BladeUPS 12kW 208V w/parallel cord and PBGX/SNMP/MODBUS

Four (4) BLADEUPS 12KW 208V Parallel Cord

One (1) BladeUPS 48/60kW Wire Way (Top/Bottom)

Two (2) PW RPM, 12KW, L21-30R/L21-30R, BladeUPS, 208V

Two (2) PW RPM, 12KW, L21-30R/L21-30R, BladeUPS, 8 Feet

Five (5) BladeUPS 3U EBM

Five (5) Kit, Harness Estension EBM to UPS, 36”

One (1) Environment Monitoring Probe

One (1) BladeUPS Bladebar and Wireway Install

Fourteen (14) Smart EPDU MI 38U-A IN: L21-30P 24A 3P Out 24XC13:

3XC19: 6X5-20R

One (1) Eaton Engineer Startup Verification, 7x24

IDF – First Floor:

Two (2) UPS-208V Output, 50/60 Hz Bundles

Appendix H – UPS and Power Distribution Pricing: $105,881.00

Jupiter Police Department HQ & Data Center – RFP-IS-100119

PRICING QUOTE (continued)

Appendix H – Recommended Deviation:

MDF – Data Center:

One (1) BladeUPS 60 kW Bus Bar, Built for Top Entry ONLY

One (1) BladeUPS 12kW 208V w/parallel cord and PBGX/SNMP/MODBUS

Four (4) BLADEUPS 12KW 208V Parallel Cord

One (1) BladeUPS 48/60kW Wire Way (Top/Bottom)

Two (2) PW RPM, 12KW, L21-30R/L21-30R, BladeUPS, 208V

Two (2) PW RPM, 12KW, L21-30R/L21-30R, BladeUPS, 8 Feet

One (1) Environment Monitoring Probe

One (1) BladeUPS Bladebar and Wireway Install

Sixteen (16) EPDU BA 38U-A IN: L21-30P 24A 3P Out 30x13C:

One (1) Eaton Engineer Startup Verification, 7x24

IDF – First Floor:

Two (2) UPS-208V Output, 50/60 Hz Bundles

Appendix H – UPS and Power Distribution Pricing: $85,968.75

Note: This recommended deviation from the original design request is based

on RFI comments concerning the UPS system and the reconfiguration of

data center.

Jupiter Police Department HQ & Data Center – RFP-IS-100119

OTHER INFORMATION:

SECTION 6: Certifications/Product Specs - Berk-tek/Leviton (See electronic folder on flash drive provided named: deliverables)

Jupiter Police Department HQ & Data Center – RFP-IS-100119

SECTION 7: Certifications/Product Specs - Eaton/B-Line (See electronic folder on flash drive provided named: deliverables)

Jupiter Police Department HQ & Data Center – RFP-IS-100119

SECTION 8: Data Center Cage Enclosure Option/Pricing

Data Center Cage Parts List:

LN Qty Item No Description (Colors/Comments)

1 4 SSCU07 Corner Upright - 7 Ft High Black

2 1 SSDS0746 Door Section, 7'H X 4'W For 6'-6" Door

Steel: Color Required - Steel: Black

3 16 SSLU07 Linear Upright - 7 Ft High

4 4 SSPW072 Wall Section - 7'H X 2'W

5 15 SSPW074 Wall Section - 7'H X 4'W

6 1 SSSD064P Sliding Door, 6'-6"H X 4'W, 3/8" Perf

7 4 SSTF06 Top Frame, 6

Steel: Color Required

8 4 SSTF10 Top Frame, 10

Steel: Color Required

9 1 SSANC1 Anchoring Kit, Set Of 20 - Concrete Floor

10 1 SSMEDAL Medeco Lock, Keyed Alike, Left

Steel: Color Required

NOGROUP

Installation

1 999922 Professional Installation

Total Cost: $18,440.00

Note: Detailed product design and specs included in electronic folder on

flash drive provided named: deliverables

Jupiter Police Department HQ & Data Center – RFP-IS-100119

CABLING SOLUTION PREPARED FOR:

Town of Jupiter

Police Department HQ & Data Center

Prepared by: Joe Russo

Vice President

Accelerated Technologies

[email protected]

off: 561-427-0600 ext. #214

fax: 561-746-5974

1

TABLE OF CONTENTS

Introduction Page 3

Summary of Scope of Work Page 4

Exceptions and Deviations Page 5-6

Project Management Page 7

Additional Project Notes Page 8

Pricing/Terms and Conditions/Warranty Page 9

Materials List Page 10-11

2

INTRODUCTION

Accelerated Technologies would like to take this opportunity to thank you for the

opportunity to bid on this project. It is our goal to present a technically superior solution while

remaining cost competitive.

Accelerated Technologies specializes in structured cabling installation services for new

construction, remodels and retro-fit projects. Today’s technology demands a cabling

infrastructure that is installed and maintained by professionals that have spent their careers

focused on structured cabling. Our ongoing training through industry recognized organizations

such as BICSI, as well as manufacturer partners, insures you will get maximum bandwidth and

performance from your cable plant. Our technicians adhere to all the latest EIA/TIA standards

and all work is tested and certified. In addition, it is Accelerated Technologies’ policy to provide

a work environment that is inherently safe - we enforce a strict safety program that follows

OSHA safety standards.

Accelerated Technologies has designed and engineered the following proposal based on

the electrical plans provided, specifications given in the site survey, and the recommendations of

the Accelerated Technologies design staff.

3

_____

SUMMARY OF SCOPE OF WORK

Main Components

This installation of the following cables and equipment:

Six hundred nine (609) Cat 6A Non Plenum Voice/Data drops

Thirty eight (38) Cat 6A Non Plenum Wireless Access Point Data drops

Forty six (46) Cat 6A Non Plenum CCTV drops

Fifty two (52) Cat 6A Non Plenum Television drops

Twenty six (26) Quad Shield RG6 Coaxial Non Plenum Cable – Television drops

One hundred ten (110) feet – Eaton 24” Overhead Cable Tray w/accessories

One (1) 24 Strand Multimode OM3 Fiber Riser Cable – MDF to IDF

One (1) 6 Strand Multimode OM3 Fiber Riser Cable – IDF to Body Cam Room

Ten (10) Eaton Cabinets w/ Wire Management – (MDF - Data Center)

Two (2) Eaton 4 Post Racks w/ Wire Management (IDF)

One (1) Eaton Wall Mount Cabinet (Body Cam Room)

The typical work area outlet (WAO) will consist of one (1) 2-port faceplate. Each WAO will

be configured with one (1) white jack for voice and one (1) blue jack for data. All data jacks will

be CAT 6 jacks and all voice jacks will be CAT 5e jacks.

Includes labor to terminate all voice, data and video cables in the MDF and IDF and

Body Cam room per the approved plans. All patch panels will be mounted in Eaton cabinets or

Eaton 4 post racks. In addition, the appropriate amount of horizontal wire management and

vertical wire management devices will be mounted in the cabinet systems for the proper

organization of wires and equipment. A series of overhead cable tray will be installed in the

MDF and IDF for the proper routing of cable to the cabinets and backboards. All cabinets and

cable tray will be properly grounded to ground bars in the MDF and IDF. All cables will be

tested and labeled at the jack and the patch panels for easy management by customers IT staff.

Fiber backbone consisting of one 24 strand OM3/10G multimode fiber will be installed

between the MDF and the IDF. In addition, one 6 strand OM3/10G multimode fiber will be

installed from the IDG to a wall mounted cabinet in the Body Cam room.

Additional equipment has been included in the materials section of this document.

Initial

4

_____

SECTION 3: EXCEPTIONS AND DEVIATIONS

Accelerated Technologies assumes free and ready access to all areas required for

completion of this project.

Customer provided Modular furniture will be designed and assembled with the proper

communication poles and raceways to support low voltage cable requirements.

T-001 – General Notes: Section - Conduit Routing General Notes #8 - Accelerated

Technologies assumes all necessary conduits, including firewall sleeves, will be provided

to the MDF, IDF and each Work Area Outlet/Device location.

All cable proposed is non plenum rated.

T-301 – General Notes #4 – Accelerated Technologies will not provide

Telecommunications Readyspec RB-A4848-PPW backboard on all walls indicated with 2

coats of light colored gray paint. This scope of work is typically provided by the general

contractor.

T-301 – Key Notes #7 – Accelerated Technologies will not provide 48 strand singlemode

fiber from 1st floor IDF to 2nd floor MDF but will be providing one (1) 24 strand OM3

multimode fiber from 1st floor IDF to 2nd floor MDF for customer internal data network.

T-201 indicates a connection from the IDF on the first floor to the body cam room on the

first floor but does not specify what type of cable connection should be (copper or fiber).

Accelerated Technologies has included the installation of one (1) 6 strand OM3

mulitmode fiber from the IDF to the body cam room. Both ends will terminate on 2RU

fiber patch panels with one (1) 12U wall mounted equipment cabinet installed in the body

cam room.

T-301 – Key Notes #8 contradicts T-401 Systems Fiber Block Diagram notes. The notes

on T-401 indicate carriers fiber will extend to the 2nd floor Data Center/MDF by each

carrier. Whereas T-301 #8 indicates LV contractor to install 48 strand singlemode fiber to

2nd floor Data Center/MDF for carrier connections. Accelerated Technologies

recommends all carrier fiber are extended as a continuous fiber run to their points of

demarcation in the 2nd floor Data Center/MDF.

Initial

5

_____

EXCEPTIONS AND DEVIATIONS (Continued)

T-001 – General Notes #5 – Accelerated Technologies is not providing mounting

brackets for ceiling mounted equipment or installation labor for said brackets or the

ceiling mounted devices themselves. This includes, but not limited to wireless access

points WAP’s, ceiling mounted speakers, or ceiling mounted CCTV cameras.

T-001- Section Symbols Legend – The symbol indicated as AV instructs contractor to

install one (1) HDMI cable from AV faceplate to presentation device but does not

indicate path or to which specific presentation device when multiple devices are in the

same room. No HDMI cable is included in this proposal.

RFP Bid Document – Section 4.12 – Requirements Specifications – Communications

Optical Fiber. Regarding installation of “Outside Plant” optical fiber. Accelerated

Technologies has included no Outside Plant fiber optic cabling in this proposal. The

scope of work for Outside Plant is typically performed by telecom carriers or contractors

specializing in long haul fiber solutions.

RFP Bid Document – Section 4.8 – Requirements and Specifications – Communications

Entrance Protection. Outside plant contractor or carriers should include any requirements

in this category in their scope of work.

Any damage caused by Accelerated Technologies to work already in place will be

repaired at Accelerated Technologies’ expense.

Accelerated Technologies is responsible for its own clean-up and haul to dumpster

provided by General Contractor.

Accelerated Technologies Safety: Accelerated Technologies work at a minimum shall

specifically comply with the Federal Occupational Safety and Health Act (OSHA).

All cabling design and engineering will follow industry standards.

Initial

6

_____

PROJECT MANAGEMENT

Accelerated Technologies will determine a customer contact/individual responsible for

overseeing the project. Once the contract is signed, this individual will be the single point of

contact (SPOC) for all issues related to system implementation. The SPOC will provide support

for the implementation process and to the Accelerated Technologies installation team. The SPOC

will also help coordinate the scheduled in-service date. In addition, Accelerated Technologies

will provide a project manager and his/her activities may include, but are not limited to:

Project Plan & Milestone schedule

Environmental Specifications provided to customer

Hardware delivery and inventory coordination

Managing change requests

Project Status Meetings

Acceptance Testing (Solution Deployment)

Once configured to Client’s specifications, acceptance tests will be performed. This ensures

proper installation of the solution. Implementation issues encountered as a result of Accelerated

Technologies will be corrected by Accelerated Technologies.

Knowledge Transfer

Provide configuration overview of systems installed. Provide training to end users on the

operation of the systems. Training will be provided onsite.is available on-site.

Change Order Request

Changes to the original scope of work or materials must be submitted in writing to the designated

Accelerated Technologies project manager from the customers SPOC.

Initial

7

_____

ADDITIONAL PROJECT NOTES

All cabling design and engineering will follow industry standards.

Accelerated Technologies assumes free and ready access to all areas required for

completion of this project.

Accelerated Technologies assumes all necessary conduits for vertical passage between

floors and horizontal passage through firewalls. In addition, proper sleeves will be

provided for all WAO and other wall mounted devices.

Accelerated Technologies will pull necessary permits and follow inspection schedule.

It is understood that this agreement is based upon work being performed “Per Plans and

Specifications,” however this does not excuse any item (labor and material) that could

reasonably be expected or inferred as a normal course of completing the Scope of Work

in a professional manner.

Accelerated Technologies will not be responsible for delays in completion if said delays

are caused by other factors including changes in scope of work, construction delays,

furniture delays or acts of nature.

Any damage caused by Accelerated Technologies to work already in place will be

repaired at Accelerated Technologies’ expense.

Accelerated Technologies is responsible for its own clean-up and haul to dumpster

provided by General Contractor.

Accelerated Technologies’ work includes all labor, supervision, materials, equipment,

services, supplies, tools, facilities, transportation, storage, receiving, taxes, licenses,

inspections, certifications, overhead, profit, insurance, and other items required or

reasonably inferable to properly complete all cabling work.

Accelerated Technologies Safety: Accelerated Technologies work at a minimum shall

specifically comply with the Federal Occupational Safety and Health Act (OSHA).

Initial

8

__________________________________ __________________

WARRANTY & CERTIFICATION

Accelerated Technologies offers a Limited Lifetime System Warranty through its

partnership with Berk-Tek/Leviton. See additional warranty document for details.

Accelerated Technologies will warranty Eaton UPS & Power Distribution for a

period of 18 months from the date of installation/acceptance.

Accelerated Technologies will provide electronic test results for all Cat 6A cable.

PRICING WITH TERMS and AUTHORIZATION

TERMS: 50% upon acceptance, 25% upon rough inspection, 25% upon final.

Low Voltage Cabling Pricing: $185,851.00

Eaton UPS & Power Distribution Pricing: $85,968.75

Total: $271,819.75

__________________________________ __________________

Customer Authorized Signature Date

Print Name Title

9

_____

MATERIALS LIST

Low Voltage Main Components – Material List:

Description Part # Qty

Berk-Tek Cat 6a non plenum cable – Blue/Gray 11084689 149,000 Ft.

Leviton Cat 6a jacks – blue/white 6110G-R** 745

Leviton 6 – port faceplate – white 42080-6WS 278

Leviton 48 Port Cat 6A Patch Panel 6A586-U48 18

B-Line J-Hooks BCH64 800

Eaton Cabinet RSN4282B 10

Eaton Floor Mount 4 Post Rack (84H x 19W) SB838094BFB 2

Leviton Vertical Wire Management LEV-492RU-VFR 4

Leviton Horizontal Wire Management LEV-492RU-HFR 31

Leviton Fiber Trunk 24F OM3 EW2024RR200F36B36BY 200 ft.

Fiber Trunk 6F OM3 EW2006RR200F36B36BY 200 ft.

Eaton 12U Wall Mount Cabinet VLWM2420 1

Leviton 2U Fiber Patch Panel 5R2UM-S06 4

Leviton Fiber Adapter Panel - OM3/24LC 5F100-4QL 2

Leviton Fiber Adapter Panel - OM3/124LC 5F100-2QL 2

Leviton Fiber Patch Cord OM3 LC/LC-5M 5LDLC-M05 36

B-Line 24’ x 10” cable tray SB1724FB 11

B-Line wall mount kit SB211324FB 6

B-Line runway support SB2118AFB 20

B-Line runway drop-out SB212924FB 12

B-Line runway side drop-out SB2129SD24FB 4

B-Line splice kit SB2107FB 11

B-Line T/L splice kit SB2101A 5

Initial

10

_____

MATERIALS LIST (continued)

Appendix H – UPS and Power Distribution – Materials List:

Description Part # Qty

Eaton BladeUPS 12kW 208V Parallel ZC121P060100000 4

Eaton BladeUPS 12kW 208V Parallel ZC121P068100000 1

Eaton 9PX UPS 9PX5K 2

Eaton Power Distribution Module EBA-310-10 16

PW RPM, 12KW, L21-30R/L21-30R, 208V Y0311402210000 2

PW RPM, 12KW, L21-30R/L21-30R, 8 FEET Y03111022100000 2

BLADEUPS BUSBAR, TOP ENTRY 103007573-5591 1

Environmental Monitoring Probe 116750224-001 1

Eaton Professional Startup, 7x24 SU05NXXX-0080 1

UNIVERSAL WIREWAY 103007569-5591 1

BLADEUPS AND WIREWAY INSTALL AS00N00-WIRE 1

Initial

11