The Greater Mekong Sub-region Flood and Drought Risk ...
-
Upload
khangminh22 -
Category
Documents
-
view
0 -
download
0
Transcript of The Greater Mekong Sub-region Flood and Drought Risk ...
Greater Mekong Subregion Flood and Drought Risk Management and Mitigation Project
(RRP REG 40190)
Socialist Republic of Viet Nam Greater Mekong Sub region Flood and Drought Risk Management and Mitigation Project Initial Environmental Examination Report
TABLE OF CONTENTS
PAGE
LIST OF ABBREVIATIONS............................................................................................................................ I
EXECUTIVE SUMMARY ............................................................................................................................... 1
I. POLICY, LEGAL, AND ADMINISTRATIVE FRAMEWORK .................................................................. 1
II. DESCRIPTION OF THE SUBPROJECTS .............................................................................................. 2
A. The subproject area ........................................................................................................................... 2
B. The Prioritized Projects and Project Location .................................................................................... 2
III. DESCRIPTION OF THE ENVIRONMENT .............................................................................................. 7
A. Physical Environment ......................................................................................................................... 7
B. Ecological Resources and Sites of Archaeological Significance ..................................................... 16
C. Human and economic development ................................................................................................ 22
IV. ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES ................................ 28
A. General Potential Environmental impacts ........................................................................................ 28
B. Impacts and Mitigation Measures during Pre-Construction Phase .................................................. 30
C. Impacts and Mitigation Measures during the Construction Phase .................................................. 37
D. Impacts and Mitigation Measures during O&M Phase ..................................................................... 50
V. CUMULATIVE EFFECTS ...................................................................................................................... 54
VI. INFORMATION DISCLOSURE, CONSULTATION, AND PARTICIPATION ....................................... 54
A. Consultation and Participation Process ........................................................................................... 54
B. Consultation Meetings...................................................................................................................... 55
VII. GRIEVANCE REDRESS MECHANISM................................................................................................ 56
A. Purpose of the Mechanism .............................................................................................................. 56
B. Access to the Mechanism ................................................................................................................ 56
C. The Grievance Redress Mechanism ................................................................................................ 57
VIII. ENVIRONMENTAL MANAGEMENT PLAN ......................................................................................... 58
A. Institutional requirements for Environmental Management & Monitoring ........................................ 58
B. Environmental Management and Monitoring Plan ........................................................................... 59
IX. CONCLUSION AND RECOMMENDATION ......................................................................................... 83
A. Objectives and Positive impacts ...................................................................................................... 83
B. Negative impacts .............................................................................................................................. 83
C. Recommendations ........................................................................................................................... 84
D. Conclusion ....................................................................................................................................... 84
X. REFERENCES ...................................................................................................................................... 84
XI. ANNEXES ............................................................................................................................................. 86
ii
ANNEXES
Annex 1: Environmental monitoring activities (water quality, air quality, noise) and costs
for Subprojects, during the pre-construction, construction and operation
phases.
Annex 2: Rapid Environmental Assessment (REA) Checklist Irrigation for Subprojects.
Annex 3: Public Consultations
LIST OF FIGURES
Figure 1: Lower Mekong River Basin within Viet Nam ............................................................................. 2 Figure 2: Proposed Nguyen Van Con Sluice-Upgrading of Salt water intrusion protection system
in Go Cong area-Tien Giang Province ..................................................................................... 5 Figure 3: Location of a Proposed sluice - Upgrading of Salt water intrusion protection system in
Go Cong area ........................................................................................................................... 5 Figure 4: Existing canal Thong Nhat- A section of 10km long is along the national park Tram
Chim in Tam Nong district.-Dong Thap Province ..................................................................... 6 Figure 5: The house owner shows mark of flood water level by Thong Nhat canal ................................ 6 Figure 6: The number of Sarus crane visiting the park has increased from 89 in 2006, to 125 in
2007, and to 126 birds in 2008 ............................................................................................... 19
LIST OF TABLES
Table 1 : Climate data of the project area (2 provinces) .......................................................................... 7 Table 2: The result of surface water quality testing in Cai Lay area ........................................................ 9 Table 3: Data of water quality testing at Go Cong town ........................................................................ 11 Table 4 : Surface water quality in Hong Ngu District ............................................................................. 13 Table 5: Air quality monitoring results in urban and industrial areas (Unit: mg/m
3) ............................... 15
Table 6: Results of noise monitoring in urban and Tien Giang Industrial Park ...................................... 15 Table 7: Forest area in Tien Giang province from 2006 to 2009 ........................................................... 17 Table 8: Forest area in Tien Giang province from 2006 to 2009 ........................................................... 18 Table 9: Pagodas and temples and protected area situated near subproject areas ............................. 20 Table 10: The population in 3 provinces, 2009 (thousands) .................................................................. 22 Table 11: Structure of the economical sector in the two Provinces (billion dong) ................................. 23 Table 12: Status of land use in the Project Area (2009) ........................................................................ 23 Table 13: Number of schools, classes, teachers and pupils of kindergarten and general
education of two provinces ..................................................................................................... 24 Table 14: Existing Health System in two Provinces ............................................................................... 24 Table 15: Solid Waste Generation in Dong Thap Province (ton/year) ................................................... 27 Table 16: Subprojects for Improving and upgrading of flood drainage and irrigation canal system
canal system (No. 1, and 5) Pre-Construction Phase ............................................................ 30 Table 17: Subprojects for Building of flood control and salt water intrusion protection Sluices -
Pre-Construction Phase.......................................................................................................... 33 Table 18:Subprojects for Bank protection for Thuong Thoi Tien town, Hong Ngu district, Dong
Thap province - Pre-Construction Phase .............................................................................. 35 Table 19: Subprojects for Improving and upgrading of flood drainage and irrigation canal system
canal system - Construction Phase ....................................................................................... 38 Table 20: Subprojects for Building of flood control and salt water intrusion protection Sluices -
Construction Phase ................................................................................................................ 43
Table 21: Subprojects for Bank protection for Thuong Thoi Tien town, Hong Ngu district, Dong
Thap province -Construction Phase ....................................................................................... 47 Table 22: Subprojects for Improving and upgrading of flood drainage and irrigation canal system
canal system - Operation & Maintenance Phase ................................................................... 51 Table 23: Subprojects for Building of flood control and salt water intrusion protection Sluices -
Operation & Maintenance Phase ............................................................................................ 52 Table 24: Subprojects for Bank protection for Thuong Thoi Tien town, Hong Ngu district, Dong
Thap province - Operation & Maintenance Phase ................................................................ 53 Table 25: List of Subproject for Public Consultation‟s meetings ............................................................ 55 Table 26: Representatives of two PMUs ................................................................................................ 58 Table 27: Environmental Management and Monitoring: Subprojects for Improving and upgrading
of flood drainage and irrigation canal system ......................................................................... 61 Table 28: Environmental Management and Monitoring: Subprojects for Building of flood control
and salt water intrusion protection Sluices ............................................................................. 69 Table 29: Environmental Management and Monitoring: Subprojects for Bank protection for
Thuong Thoi Tien town, Hong Ngu district, Dong Thap province........................................... 77
i
LIST OF ABBREVIATIONS
ADB Asian Development Bank
AFD Agence Française de Développement
AH Affected Household
AP Affected Person
APC Agriculture Production Cooperative
CBDRM Community Base Drought Risk Management
CBFRM Community Flood Risk Management
CPC Commune People Committee
CPO Central Project Office (MARD)
DONRE Department of Nature Resources and Environment
DOT Department of Transportation
DPC District Peoples Committee
EA Executing Agency
EARP Environmental Assessment and Review Procedures
EMA External Monitoring Agency
EMD Ethnic Minority Development
EMDP Ethnic Minority Development Plan
EMP Environmental Management Plan
FSR Feasibility Study Report
GDP Gross Domestic Product
GMS Great Mekong Sub-region
GOV Government of Viet Nam
GPP Grievance Point Person
ICT Information and Communication Technology
IDMC Irrigation and Drainage Management Company
IE Irrigation Enterprise
IEE Initial Environmental Examination
IMC Irrigation Management Company
INB Incremental Net Benefits
IOL Inventory of losses
IR Inception Report
ISF Irrigation Service Fee
M&E Monitoring and Evaluation
MARD Ministry of Agriculture and Rural Development
MOET Ministry of Education and Training
MONRE Ministry of Natural Resources and Environment
MOIT Ministry of Industry and Transport
MOST Ministry of Science and Technology
O&M Operation and Maintenance
PAP Project Affected Person
PIA Project Implementation Agency
PMU Project Management Unit
PPP Public Private Partnership
PPTA Project Preparatory Technical Assistance
PSA Poverty and Social Assessment
PU Public Utility
RAMP Risk Assessment and Management Plan
RAP Resettlement Action Plan
RC Resettlement Commission
REA Rapid Environmental Assessment
RP Resettlement Plan
SIEE Summary Initial Environmental Examination
SPRSS Summary Poverty Reduction and Social Strategy
SS Suspended Solids
TA Technical Assistance
ToR Terms of Reference
ii
USD United States Dollar
VAT Value Added Tax
VND Viet Nam Dong
WRU Water Resources University
WTP Willingness to Pay
WUA Water User Association
WUG Water User Group
EXECUTIVE SUMMARY
A. Background
1. This report is prepared and submitted as Supplementary Appendix of the Final Report for ADB TA No. 6456-REG, Preparing the Greater Mekong Sub region Flood and Drought Risk Management and Mitigation Project in Viet Nam. This PPTA is based on an agreement between ADB and the Government of Viet Nam and funding of the PPTA is under a grant from the ADB.
2. The main outcome of this PPTA will be an investment project preparation report for preparing the Greater Mekong Sub region Flood and Drought Risk Management and Mitigation Project in Viet Nam to be co-financed by ADB and .Agence Francais De Developpement (AFD).
3. The subprojects provide for building and rehabilitation of some infrastructures such as: canal system, dikes, and sluices to improve flood and drought risk management and mitigation of subproject areas in Mekong river basin of three provinces in Viet Nam, namely, Tien Giang and Dong Thap. The Viet Nam Project also includes non-structural sub-projects namely; Preparation of guidelines on design criteria for projects on F/DRMM in the Cuu Long river delta, Framework for Flood Risk Mitigation/Diversion in the Border Area between Cambodia and Viet Nam and Community based flood and drought mitigation and management in Plain of Reeds in the Cuu Long river delta.
4. This report gives an account of the Initial Environmental Examination of the Structural-Subprojects in the 2 provinces.
5. The IEE has been finalized and submitted to ADB and Government of Viet Nam (GOV) for the subprojects approvals. This IEE report follows the laws and regulations in Viet Nam and ADB Environmental Assessment Guidelines (Safeguard Policy Statement, 2009), and Rapid Environmental Assessment Checklists 2003. The IEE was undertaken during project preparation work and is to be updated during the implementation phase. The report also describes the Environmental Management Plan (EMP) proposed for the subprojects.
Objective
6. The overall objectives of the IEE report are to:
Describe the existing natural and socio-economical resources in and surrounding subproject areas;
Identify and assess potential significant impacts based on existing environmental condition including during project preconstruction, construction, and operation-maintenance stages;
Identify and recommend mitigation measures to minimize any potential impacts caused by the subproject activities; and,
Develop environmental management plan and cost estimate including monitoring plan during construction and operation stage.
Purpose of Report
7. This report gives an account of the Initial Environmental Examination (IEE) of the proposed subprojects under “Preparing the Greater Mekong Sub region Flood and Drought Risk Management and Mitigation Project” in Tien Giang, and Dong Thap Provinces. The IEE was conducted during subprojects‟ preparation to identify the impacts of the proposed activities on the environment. Measures are recommended to mitigate the identified adverse environmental impacts arising from the implementation of the Subprojects.
2
8. The IEE was carried out in compliance with the ADB‟s Safeguards Policy Statement (SPS), 2009, Environmental Assessment Guidelines, 2003, and Environmental Guidelines for Selected Irrigation and Drainage Development Projects of the Asian Development Bank (ADB) and relevant environmental policies and guidelines of the Government of Viet Nam (GOV).
Project Category
9. The subprojects are classified under ADB guidelines/rules as Category B projects. Such projects are judged to have some adverse environmental impacts occurring mostly during construction phase, but of lesser degree and/or significance than those for category A projects. An initial environmental examination (IEE) is required to determine whether or not any significant environmental impacts warranting an EIA are likely to occur. If an EIA is not needed, the IEE is regarded as the final environmental assessment report.
10. Under GOV regulations, Decree 21No.21/2008/ND-CP, Appendix “List of Project subject to preparation of Environmental Impact Assessment Report”, as most of proposed subprojects are rehabilitation subprojects, except only some components are new construction at small scale, so, only a Commitment of Environmental Protection (CEP) is required.
Extent of the Initial Environmental Examination (IEE)
11. The Initial Environmental Examination (IEE) involves the following activities:
Gathering available baseline information on the physical / chemical, biological, and socio-economic environment of the subproject area;
Screening of potential impacts related to the sitting, design, construction, and operation phases, to distinguish those that are likely to be significant and would warrant further study;
Recommending measures to mitigate possible adverse impacts;
Provide guidance on appropriate institutional arrangements for environmental monitoring;
Findings of site reconnaissance, results of social surveys, results of water quality tests and analysis, technical descriptions based on the preliminary engineering designs (contained in the FS Reports of proposed components), as well as the outcome of discussions with PIS of Tien Giang and Dong Thap Provinces, and provincial authorities, have been integrated into this IEE;
1
I. POLICY, LEGAL, AND ADMINISTRATIVE FRAMEWORK
1. Both ADB and relevant Viet Namese environmental guidelines and regulations were used for the preparation of the IEE for the Flood and Drought Risk Management and Mitigation Project in Viet Nam.
2. Relevant GOV Environmental Regulations are:
Law of Environmental Protection, 29November, 2005. This Law provides for environmental protection; policies, measures and resources for environmental protection and for the rights and obligations of organizations, households and individuals for environmental protection. The Law of Environmental Protection shall apply to the State agencies, organizations, households, individuals, Viet Namese citizens living in foreign countries, and foreign organizations and individuals that operate within the territory of the Socialist Republic of Viet Nam.
Decree 80/ND-CP, 09August, 2006, of the Prime Minister regarding detailed stipulation and guidance on applying the Law of Environmental Protection.
Decree 21/2008/ND-CP, 28February, 2008, amending and supplementing a number of articles of the Government‟s Decree 80/ND-CP of 09August, 2006; detailing and guiding the implementation of a number of articles of the Law on Environmental Protection.
Circular No.05/2008/TT-BTNMT guiding strategic environmental assessment, environmental impact assessment and environmental protection commitment. This Circular repeals Circular No. 08/2006/TT-BTNMT of 09September,2006, guiding strategic environmental assessment, environmental impact assessment and environmental protection commitment.
Decision No.13/2006/QD-BTNMT, 08September, 2006, of the Ministry of Natural Resources and Environment, regarding stipulation of organizations and operation of the assessment board for reports on Strategic Environmental Assessment (SEA) and EIA.
Decision No: 48/2008/QD-TTg, issued on 03April, 2008 by the Prime Minister, regarding Common General Guidelines on Feasibility Study Preparation for ODA Projects.
Decision 16/2008/QD-BTNMT, 31December, 2008, of the Ministry of Natural Resources and Environment on promulgating the National Technical Standard Regulations for the Environment. This Decision enclosed 8 National Technical Standard Regulations for the Environment as follows:
1. QCVN 08:2008/BTNMT: National technical regulation on surface water quality.
2. QCVN 09:2008/BTNMT: National technical regulation on ground water quality.
3. QCVN 10:2008/BTNMT: National technical regulation on coastal water quality.
4. QCVN 11:2008/BTNMT: National technical regulation on the effluent of industries.
5. QCVN 12:2008/BTNMT: National technical regulation on the effluent of pulp and paper mills.
6. QCVN 13:2008/BTNMT: National technical regulation on the effluent of textile industries.
7. QCVN 14:2008/BTNMT: National technical regulation on domestic wastewater.
8. QCVN 15:2008/BTNMT: National technical regulation on pesticide residues in soils.
3. Relevant ADB Environmental Guidelines include:
Safeguard Policy Statement. ADB, 2009
2
Operation Manual Bank Policies (BP) on Safeguard Policy Statement. ADB, 2009
Environment Policy of the Asian Development Bank, November 2002.
Environmental Assessment Guidelines, 2003 – Annex 3: Content and Format of Initial Environmental Examination (IEE).
Environmental Guidelines for Selected Agricultural and Natural Resources Development Projects (November 1991).
Rapid Environmental Checklist. ADB, 2003.
II. DESCRIPTION OF THE SUBPROJECTS
A. The subproject area
4. The subprojects within Viet Nam selected for the Greater Mekong Subregion Flood and Drought Risk Management and Mitigation Project are located in the Lower Mekong River Basin. The subprojects are related to improving and upgrading of drainage and irrigation canal systems, flood control system, salt water intrusion protection system and bank protection.
Figure 1: Lower Mekong River Basin within Viet Nam
B. The Prioritized Projects and Project Location
5. There are five subprojects in Viet Nam that are proposed for improving and upgrading of flood and drought risk management canal and dike system in Lower Mekong River Basin in Viet Nam.
3
No Name of Subprojects Province New/ Upgrading/
Rehabilitation
Remarks
1 Flood control system Ba Rai – Phu An protecting orchard area
Tien Giang New Sluices New Construction 26 Sluices
2 Upgrading of Salt water intrusion protection system in Go Cong area
New Sluices Includes ring dike and 3 Sluices
3 Improving and upgrading of Plain of Reeds flood drainage and irrigation canal system
Dong Thap Upgrading Includes dredging Cai Cat, Thong Nhat, Tan Cong Chi-Duc Vang, and Thong Nhat Canal
4 Bank erosion protection for Thuong Thoi Tien town, Hong Ngu district, Dong Thap province
New
1. Flood control system Ba Rai – Phu An protecting orchard area (Tien Giang)
Location
6. Ba Rai – Phu An orchards is close to the North bank of the Mekong River in Cai Lay and Cai Be districts, Tien Giang province (still, called as the Southern area of Nguyen Van Tiep canal in the Water Resources Planning (approved) for the Cuu Long River Delta). Its natural land area is 4,540ha, lying close to the Ba Rai canal in the East and Phu An canal in the West, Binh Phu canal in the North and provincial road No. 864 in the South (along Mekong river bank).
Needs for the subproject
7. Orchard growing is a main activity in Ba Rai – Phu An area, accounting for 51% of all cultivable area. Main constraint for production and people in the region is flooding water, when there are big floods. In 2000 flood, the total damages were 47deaths, 15,721ha of orchards destroyed and losses worth USD53million. After 2000 flood, to protect people‟s life and properties, before flood season, temporary dams were built to prevent orchards flooding and after flood season these dams are demolished for navigation activities. Annually, this cost about VND10 billion (526,315 USD).
Objectives
To save people‟s life and their properties (estimated beneficiary population 370,000);
To improve flood water and contaminated water discharge in flood season;
To increase irrigation water regulation in dry season;
To improve navigation and rural road transportation conditions.
Outline description
Construct 27 new sluices (constructed 10 sluices) for flood control and water regulation in combination with existing sluices and embankment systems
4
Figure B.5: Location of Ba Rai-Phu An Figure B.6: Flood control steel dam for fruit area protection in Ba Rai-Phu An
2. Upgrading of Salt water intrusion protection system in Go Cong area (Tien Giang)
Location
8. The subproject is in Go Cong District, Tien Giang Province
Needs for the subproject
Water in canals is seriously contaminated. The reason for this may be improper
system operation procedure or regulation sluices system not fully developed.
Objectives
Salt water intrusion protection from the Cua Tieu and Vam Co rivers in dry season and from the East sea;
Fresh water conveyance for the whole area in ten months/year;
Improvement of inundation drainage and alkaline water drainage;
In combination with fresh water supply, rural development and environmental reclamation in the region.
Outline description
Construction of three salt water intrusion prevention sluices (Son Quy, Nguyen Van Con and Salisete) and embankments connecting sluices with the existing embankments.
5
Figure 2: Proposed Nguyen Van Con Sluice-
Upgrading of Salt water intrusion protection system in Go Cong area-Tien Giang Province
Figure 3: Location of a Proposed sluice -
Upgrading of Salt water intrusion protection system in Go Cong area
3. Improving and upgrading of Plain of Reeds flood drainage and irrigation canal System (Dong Thap)
Location
9. The Subproject include dredging Cai Cai, Thong Nhat, Tan Cong Chi-Duc Vang, and Thong Nhat Canal, The subproject is situated in Tan Hong, Tam Nong, Thanh Binh district and Hong Ngu Town,
Needs for the subproject
Water in canals is seriously contaminated. The reason for this may be improper system operation procedure or regulation sluices system not fully developed.
Objectives
To save people‟s life, their properties and their sustainable agricultural production (mitigation of flood risk for 520,000 people living in flooded areas out of which about 354,000 persons are farmers);
An additional flood discharge will be 1,332 m3/s benefitting 40,000ha land;
Mitigation of drought risk is for 146,000ha of agricultural land with an additional irrigation discharge of 16 m3/s;
Environmental and ecological conditions in the project area will be improved and local people‟s living standards will be increased; and,
Development of rural transportation and ecological and environmental improvement.
Outline description
Cai Cai Canal
Dredging of 18,053 m main canal
Construction of 43 canal bridges
Construction of 5 sluices
Tan Chi Cong-Doc Vang Ha Canal
Dredging of 17,272m main canal
Construction of 27sluices
6
Thong Nhat Canal
Dredging of 30,040m main canal
Construction of 29 sluices
Khang Chien Canal
Dredging of 14,000m main canal
Surrounding embankment dimension in combination with rural transportation
Construction of 43 sluices
Figure 4: Existing canal Thong Nhat- A section of 10km long is along the national park Tram Chim in Tam Nong district.-Dong Thap Province
Figure 5: The house owner shows mark of flood water level by Thong Nhat canal
4. Bank erosion protection for Thuong Thoi Tien town, Hong Ngu district, Dong Thap province (Dong Thap)
Location
10. Project area: Bank protection of the Mekong River at Tan Thoi Thuong Town, Hong Ngu district, Dong Thap province.
Needs for the subproject
In 1994, 1995, 1997, 2000, 2002, 2006, 2008, there were tens of eroded sites along the Mekong River, at Hong Ngu town, in which bank protection have been done from Government fund and foreign agencies‟ fund. There are, however, many sites seriously eroded, especially Tan Thoi Thuong town that need to be invested to protect 3000 households with a distance of 3.224 km.
Objectives
Protection of Tan Thoi Thuong town: to save and stabilize people life of approximately 10,000 households in Tan Thoi Thuong town, existing infrastructures, transportation networks and public works in Tan Thoi Thuong town.
The environmental landscape in Thuong Thoi Tien town area will be increased to form a protective corridor to prevent invading of local people living along the river bank, in combination with enhanced people‟ living condition, economic, social, tourism development and creating good conditions for economic development in the Viet Nam – Cambodia boundary area.
Outline description
7
5.1km long bank protection in the Mekong River at Tan Thoi Thuong town,
Transport road along the bank; The road surface will be covered by a layer of bitumen concrete with a width of 7.0m.
III. DESCRIPTION OF THE ENVIRONMENT
A. Physical Environment
11. The Project area is situated in two Provinces Tien Giang and Dong Thap, that belong to Dong
Thap Muoi Area. The detail description of environmental condition for each province is presented
below:
1. Climate
Tien Giang
12. Climate is typical of the southwest region with 2 distinct seasons, the rainy season is from May to November and the dry season lasts from December to April next year. The annual average temperature is 27.9oC, the temperature fluctuation between months is not much, around 3-5oC, however, the difference of temperature between day and night is high. Average evaporation is approximately 1183mm (3.4mm/day). The average sunshine hours in a year are from 2082-2331hours.
13. Air humidity is 78.4% per year with seasonal fluctuations. Average annual rainfall is approximately 1628mm,
Dong Thap
14. Climate is typical of the southwest region with 2 distinct seasons, the rainy season is from May to November and the dry season from December to April next year. The average annual temperature is 27oC. The average humidity in Dong Thap is 83%, the highest 100% in the rainy season and the lowest 41% during the dry months. Annual mean evaporation is 1.165mm. The average sunshine hours over the years are 2730 hours (average of 7 hours / day). Average in dry season is from 7.6 to 9.1 hours per day, and average in rainy season is from 5.1 to 7.1 hours per day.
15. The mean annual rainfall is 1.378mm, which is unevenly distributed during the two seasons. Monsoon direction in rainy season is southwest, with frequency of 70%, from May to November. In dry season, monsoon direction is southeast.
16. Summary of climate data of the Project area is presented in
Table 1.
Table 1 : Climate data of the project area (2 provinces)
Indicators Annual Average
Tien Giang Dong Thap
Temperature 27.9oC 27
oC
Number of hours
sunshine 2082-2331 hours
2730 hours
Rainfall 1219mm, 1.378mm
Relative humidity 78.4% 83%
8
Evaporation 1183 mm 1.165
2. Geology
17. About geology, this project area was formed mostly by sea sediment deposition and alluvial soil of Cuu Long river. At the depth of 50m, there are 2 kinds of sediment: Holocene (new sediment) and Pleistocene (ancient sediment).
3. Topography and Soils
18. The two provinces are located in Mekong delta, which has relatively flat topography with dense river and canal system.
Tien Giang
19. Tien Giang Province‟s terrain is flat, with a slope of below 1%, which is 0-1.6 meters above sea level. It is comprised of three areas, including fruit area alongside the Tien River, Dong Thap Muoi area and the coastal area of Go Cong.
20. The natural land covers an area of 236,663 hectares (ha), divided into main soil groups as followings:
Alluvial soil covers an area of 125,431 ha, accounting for 53% out of the total area. That kind of land mainly spreads in districts of Cai Be, Cai Lay, Chau Thanh, Cho Gao, My Tho City, and part of Go Cong Tay District, which has fresh water source.
Salty land covers an area of 34,552 ha, holding 14.6% out of the total area. It is extended in districts of Go Cong Dong, Go Cong Taay, Go Cong Town, and part of Cho Gao District.
Alum land covers an area of 45,912 ha, 19.4% of the total. It is mainly distributed in low, and sunken area of Dong Thap Muoi belonging to districts of Cai Be, Cai Lay, and Tan Phuoc in the North. This kind of land has taken its form on coastal salty marsh sediment, created in the retrogressing process of the sea. Therefore, it is rich in alum and organic substances.
Dong Thap
21. Dong Thap is divided into two parts by Tien river: the North and the South. The North of Tien river has a relatively plain topography with the inclination from Northwest to Southeast. The latter, the South, has diversified terrain with the inclination from the two rivers in to the centre.
22. Land resources: may be classified into these groups as follows:
Alluvial soil group has an area of 143,997 ha, which comprises 43.95% of the total land area. This kind of soil is distributed along arroyos, rivers and isles of Tien and Hau river. Annually, silt has raised its level in fields which is favorable condition for the cultivation of short-term industrial crops, fruit trees.
Alum soil group has 140.997 ha, accounts for 42.85% of the natural area. Most of that are sweetened and are suitable for rice crops, fishery breeding giving high productivity and quality.
Grey soil group has an area of 22,545 ha, occupying 6.88% of natural land area. It is distributed in highlands in Tan Hong, Tam Nong and Hong Ngu districts.
4. Surface Water
9
Tien Giang
Water resources
23. Tien Giang has a dense network of rivers and canals, long coastline facilitate the exchange of goods with the neighborhood and for the farming and fishing of marine products:
Tien River: a major source of fresh water, which flows 115km through the territory of Tien Giang, elevation from the river bed is from 6 m to 16 m, average- 9 m. The river width varies from 600 to 1,800 m; wet section is about 2,500-17,000 m and influenced by tide throughout the year. Flow in dry season (April) around 130 – 190 m3/s.
River Vam Co Tay River: without a source, the river flows mainly from Tien river. Vam Co Tay River is the place, where, the water from Dong Thap Muoi flood get escape routes and is a major saltwater intrusion. The average flow of dry months 9m3/s, the maximum flood flow near 5.000m3 /s.
24. In addition to this, the province has a number of rivers and small canals in the basin of Tien and Vam Co Tay River which is very important in contributing to the circulation, transport of goods and production service as: Cai Coy, Cai Be, Ba Rai, Phong Phu, Rach Ram, Vam Giong, Long Drink, Go Cong, Tra river etc. Most rivers and canals in the province are affected by uneven tide regime. Particularly, in estuaries with strong tidal activity, tidal amplitude at the estuary from 3.5 to 3.6 m, tidal speed 30km/h (1.5 times and 3 times of the Hau River and Red River). Speed of the average flow varies from 0.8 to 0.9 m/s, maximum up to 1.2 m/s and downstream speeds up to 1.5 to 1.8 m/s.
Water quality
25. The surface water quality of some rivers and canals of two subproject areas (Cai Lay and Go Cong Districts) of Tien Giang Province is presented in
Table 2 and Table 3.
Table 2: The result of surface water quality testing in Cai Lay area
No. Parameter Unit
Location of sampling point Viet Nam’s Standard
(QCVN 8/2008/BTNMT)
Ba Rai river
(Cai Lay bridge)
Canal 12 bridge
A1 B1
1 T
C0
2 pH - 6.47 7.54 6 – 8.5 5.5 – 9
3 DO mg/l 2.44 2.47 > 6 > 4
4 TSS mg/l 27 12 20
5 NH4+ mg/l Un-detected undetected 0.1
6 BOD5 mg/l 3 5
7 Cl-
mg/l 21 25 250 600
8 Pb
mg/l Undetected undetected 0.02
9 PO43-
mg/l 0.21 0.28 0.1
10 Vegetable chemicals
µg/l Undetected undetected 0.15 0.15
11 Oil
mg/l Undetected undetected 0.01 0.3
10
12 Fe mg/l 0.38 0.55 0.5 2
13 NO2-
mgN/l 0.04 0.09 0.01 0.04
14 NO3- mgN/l 1.28 1.41 2 10
15 NH4+
mgN/l Undetected undetected 0.1 0.5
16 PO43-
mg/l 0.21 0.28 0.1 0.3
18 COD mgO2/l 10 15 10 < 35
19 Coliform MPN/100ml 1.1 x 103
9 x 103 2500 7500
20 E.coli MPN/100ml 90 90 20
21 Color N/A N/A
22 Smell N/A N/A
23 Activated surface
mg/l Undetected undetected 0.1
Source: Service of Natural Resources’ and Environment Department, Tien Giang province
Column A1: Good for domestic water supply and other purposes as A2, B1, B2 Column B1: Used for irrigation and drainage or other purposes with similar water quality demand as type B2
26. The results show that the surface water quality in Cai Lay district is relatively good. Comparing to column A1 only the dissolved oxygen and the bacteria and organism exceed the standard, other parameters like NH4, Cl-, NO3 qualify the standard in column A1. Comparing with column B1 all parameters meet the requirements.
11
Table 3: Data of water quality testing at Go Cong town
Parameter
Notation,
Location
pH
DO
mg/l
TSS
mg/l
COD
mg/l
BOD5
mg/l
NH+
4
mg/l
Cl-
mg/l
NO-2
mg/l
NO
-
3
mg/l
PO3-
4
mg/l
Pb
mg/l
Fe
mg/l
Activated surfa
ce
mg/l
Coliform
MPN/100 ml
E.Coli
MPN/ 100 ml
M24-Vinh Binh bridge
6,92
3,49
39
33
15 undetecte
d
530
0,03 0,86
0,31
undetecte
d
0,14 undetecte
d
4.104
90
M25-Dong Son bridge
7,7
2,04
8 83
36 0,83 6700
0,01 0,37
0,15
undetecte
d
undetecte
d
undetecte
d
4.102
undetecte
d
M26-Long Chanh bridge
7,01
3,35
20
39
16 0,28 740
0,02 0,97
0,37
undetecte
d
0,05 undetecte
d
4,6.10
6
9,3.10
2
M27-Tan Hoa bridge
7,14
2,50
7 19
7 undetecte
d
1095
undetecte
d
1,01
0,21
undetecte
d
0,09 undetecte
d
4,6.10
5 2,1.1
02
M28-Can Loc sluice
7,17
2,38
22
25
9 undetecte
d
1500
undetecte
d
0,86
0,58
undetecte
d
0,29 undetecte
d
7.102
23
M29-Vam Thap sluice
7,70
4,27
5 27
9 undetecte
d
1730
undetecte
d
0,52
0,64
undetecte
d
undetecte
d
undetecte
d
4.102
undetecte
d
M30-Lo O sluice
7,07
2,9
33
93
41 undetecte
d
5213
0,04 0,47
0,43
undetecte
d
0,37 undetecte
d
4,6.10
7 7,5.1
04
M31-Rach Nhiem bridge
7,41
2,94
59
86
38 undetecte
d
5650
0,01 0,61
0,18
undetecte
d
0,46 undetecte
d
9,3.10
7 7.10
3
M32-Ly Quan bridge
3,64
3,40
5 12
5 undetecte
d
5725
undetecte
d
0,54
1,53
undetecte
d
0,16 undetecte
d
4,6.10
6 1,5.1
04
QCVN 08:2008/BTNM
T
(column A1)
6 – 8,5
6
20
10
4 0,1 250
0,01 2 0,1
0,02 0,5 0,1 2500
20
(Source: Service of Natural Resources and Environment, Tien Giang province, 2010)
12
27. The results show that:
pH is from 3.64 – 7.7: qualifies standard in column A1 at most of points, except M32.
DO is from 2.04 – 4.27 mg/l: do not meet standard in column A1 for all points.
TSS is from 5 – 59mg/l: most of points do not qualify standard in column A1 and exceed highest at M31 (2.95 times higher than column A1), 4 points M25, M27, M29 and M32 qualify standard in column A1.
COD is from 12 – 93mg/l: do not meet the standard in column A1 for all points, the highest is M30 (9.3 times higher than column A1).
BOD5 is from 5 – 41mg/l: do not meet the standard in column A1 for all points, the highest is M30 (10.25 times higher than column A1).
NH+4 is from undetected to 0,83 mg/l: most of points meet standard in column A1, but
M25 (8.3 times higher) and M26 (2.8 times higher).
Cl- is from 530 – 6700 mg/l: most of points do not meet standard in column A1, and exceed highest at M25 (26.8 times higher than column A1).
NO-2 is from undetected to 0.04 mg/l: most of points meet standard in column A1, but
M24, M26, M30 and get highest at M30 (4 times higher than column A1).
NO-3 is from 0.37 – 1.01 mg/l: meet standard in column A1 for all points.
PO3-4 is from 0.15 – 1.53 mg/l: do not meet standard in column A1 for all points and
exceed highest at M32 (15.3 times higher than column A1).
Pb: undetected for all points
Fe is from undetected to 0.46 mg/l: meet standard in column A1 for all points.
Coliform is from 400 – 93000000 MPN/100 ml: do not meet the standard in column A1 for most of points and exceed highest M31 (37200 times higher than column A1), except 3 points M25, M28 and M29.
E.Coli is from undetected to 75000 MPN/100ml: do not meet the standard in column A1 for most of points and exceed highest M30 (375 times higher than column A1), except 2 points M25 and M29.
Dong Thap
Water resources
28. River system in Dong Thap consists of two main tributaries Tien River and Hau River. River water flow average 11,500m3/s. The largest flow is 41,504m3/s and the lowest flow is 2000m3/s. Surface water year-round fresh, not saline.
29. Water resources of Northern area of the province have been provided by So Thuong, So Ha, Tapek Rivers and Lower Fan. Along with the main canal systems, such as Tan Thanh-Lo Gach canal, Hong Ngu - Vinh Hung, An Binh, Dong Tien, Nguyen Van Tiep A; Rach Gia Sa Dec, Rach Lap Vo is the main axis of the dominant water distribution throughout the province . However, water is not evenly distributed in the year, dry season water level is low so most of the cultivated area needs pump irrigation; during flood season water is too much, causing serious flooding, which affects production and people's lives, but the same time brings aquatic resources and field inning.
Water quality
30. According to monitoring results of Dong Thap DONRE during 2005-2009, the surface water quality in the province has a sign of pollution.
13
31. The pollution by organic matters is evidence at all monitoring point in Tien; Hau rives and in some main canals (Trung Uong, Tan Thanh, Nguyen Van Tiep, Kinh Xang etc). The COD and BOD values vary between 16-222mg/l and 8-74 mg/l respectively, exceeding limited permission in Viet Nam‟s Standard QCVN 08/2008/BTNMT, column A2 about 2-15 times. The pollution level in canal is always higher than that in river.
32. The DO level has tendency to increase in 2009, however during 2005-2008 DO level varies between 3-4.1 mg/l lower than permitted standard in QCVN 08/2008/BTNMT, column A2.
33. The nutrient parameters N-NH4+ and NO3
- has tendency to increase during 2005-2009. The increments varied between 1.3-2.1 times and almost all analytical samples in province exceeded the permitted standard by 1.06-10 times. Results of surface water quality monitoring conducted by the Department of Natural Resources and Environment of Hong Ngu district in March and September 2009 at a number of places in the district as follows:
Table 4 : Surface water quality in Hong Ngu District
Sample
number
Monitoring
time
Parameters
pH BOD5
(mg/l)
COD
(mg/l)
SS
(mg/l)
DO
(mg/l)
NO3-
(mg/l)
NO2-
(mg/l)
N-NH3
(mg/l)
Coliform
(MPN/100ml)
NM1 3/2009 6.88 15 19 45 3.61 6.16 0.0198 0.079 24x102
9/2009 7.7 15 24 124 5.4 30.07 0.1346 0.056 11x103
NM2 3/2009 6.79 18 25 32 3.45 6.69 0.0264 0.088 15x103
9/2009 7.56 17 26 197 5.5 18.15 0.0525 0.168 20x103
NM3 3/2009 7.10 12 20 132 3.33 8.36 0.0858 0.087 11x103
9/2009 7.11 22 30 114 5.3 14.17 0.1707 0.224 93x103
NM4 9/2009 7.24 17 24 259 5.3 11.07 0.1248 0.168 11x103
NM5 9/2009 7.12 19 28 105 5.1 30.1 0.0919 0.112 21x103
NM6 9/2009 7.36 19 30 128 5.5 11.07 0.0788 0.056 20x103
NM7 9/2009 7.60 26 31 233 5.4 24.79 0.1051 0.112 23x103
NM8 9/2009 7.71 15 26 224 5.3 10.62 0.0394 0.280 43x103
NM9 9/2009 7.5 10 18 137 4.2 14.17 0.0197 0.112 11x103
NM10 9/2009 7.68 17 27 103 4.2 12.39 0.0262 0.336 21x103
QCVN
08:2008/BTNMT cột
A2
6.0-
8.5
6 15 30 ≥5 5 0.02 0.2 5x103
Note
- NM1: Thuong Phuoc Boder gate
- NM2: Ferry station from Thuong Thoi Tien to Tan Chau
- NM3: Intersection of River Cai Vung and Tien river
- NM4: Thuong Thoi Hau A Market
- NM5: Thuong Thoi Hau B Market
- NM6: Phu Thuan A Commune People Committee office
14
- NM7: Central Bridge of Thuong Thoi Tien Commune
- NM8: Muong Mieu Boat Station
- NM9: Bridge Ut Goc of Thuong Thoi Tien Commune
- NM10: Ferry station Muoi Dau of Phu Thuan Commune
34. Water monitoring results in a number of industrial fish ponds in the district show that aquaculture water pollution is quite heavy, most of the parameters were observed exceeded the standard QCVN 08/2008-BTNMT column A2. Only water samples at two communes Phuoc Thuong 2 and Thuong Thoi Tien has a pH , N - NH3, total N and total, P does not exceed standard QCVN 08/2008-BTNMT column A2, the rest are beyond permitted standards such as BOD exceeds QCVN 08/2008-BTNMT column A2 1.2 - 1.6 times, COD exceeded the standard 1.2 - 1.4 times, SS exceeding 2.12 - 2.6 times, coliform in fish pond of Thuong Phuoc 2 commune is over 22 times, and in Thuong Thoi Tien Commune in 80.2 times higher than the permitted standards.
5. Groundwater
Tien Giang
35. The province has three potential aquifers: large, medium quality and with good quality, including the Pliocene, Lower Pliocene and Miocene. Distribution of these units is concentrated in My Tho, Cai Lay; depth is ranging from 150 – 400 m. Elsewhere, exploitation capacity is limited. At My Tho, flows being exploited are more than 40.000 m3/day night. Type of water is mainly bicarbonate - sodium, chloride-sodium; temperature 28-30oC; pH6 - 8.3.
Dong Thap
36. Based on the hydro-geological characteristics that can split water storage units in order from top to bottom, characteristics are as follows:
Aquifer I: poor water, bad water quality, water type sulphate - calcium - magnesium, does not meet drinking water needs. A total area of about 30% accounted for 1.036km2 natural areas in the province. This floor lies at depths from 35 – 50 m.
Aquifer II: Water quality is irregular, the total mineralization is from 0.5 to 2.7g/l, water flow <1.5g/l, with water level and irrigation capacity on average. A total area of about 34% accounted for 1.168km2 area of the province. This layer lies at a depth of 90-120m.
Aquifer III: mineralization of 1.9 to 3.47g/l, the depth distribution in 135 - 170m in the upper N2 - 2b was saline. A total area is about 25% accounted for 848km2 area of the province. This layer lies at a depth of 140 - 150m
Aquifer IV: Distribution of depth of 190-200 m, flow 14–26 l/s, total dissolved 0.5 - 0.6g/l, good water quality, water type bicarbonate - Sodium degree of water in abundance, quality, stability, a floor-level prospects in the region. A total area is approximately 23% accounted for 788km2 area of the province. This whole area lies at a depth of 200 - 270m
Aquifer V: distribution in depth 350m or less, good water quality, water pressure, temperature <3600C. This is the storage of water supply outlook for the region. A total area about 3.176 km2
, V accounted for 94% area of the province.
6. Air Quality and Noise
Tien Giang
37. The results of air quality monitoring by Tien Giang DONRE in urban and industrial areas during 2008-2010 are presented in Table 5
15
Table 5: Air quality monitoring results in urban and industrial areas (Unit: mg/m3)
No. Parameter
Annual Average (mg/m3) QCVN
05:2009/
BTNMT
Air quality in urban area Air quality in Industrial Park
2008 2009 2010 2008 2009 2010
No. of samples
68 52 26 4 4 2
1 Dust 0.69 0.74 0.36 1.40 2.88 0.26 0.3
2 SO2 0.0190 0.0341 0.1259 0.0487 0.0338 0.0823 0.35
3 NO2 0.0147 0.0268 0.0976 0.0218 0.0230 0.0974 0.2
4 CO 5.441 6.003 3.757 7.63 6.25 4.19 30
Source: Air Quality Monitoring Results of DONRE Tien Giang province in the years 2008, 2009, quarter and quarter II/2010.
38. The results show that: Air quality in urban, densely populated town of Tien Giang province is mainly polluted by suspended dust levels that exceed QCVN 05:2009 / BTNMT from 1.19 times (2010) to 2.46 times (2009). The increase in the number of cars and motorcycles in recent years in urban areas has caused noise pollution, dust and air. In the near future air pollution caused by emissions from vehicles traffic flow through urban areas will become a source of major air pollutants in urban areas of the province.
39. Air quality in Industrial Park embodied in the parameters such as SO2, NO2, CO generally meets levels of QCVN 05:2009 / BTNMT. However, the suspended dust contents are in excess of 4.2times to 7.6times. Pollution is caused mainly by vehicle traffic in the Industrial Park.
40. Regarding noise pollution in urban and industrial zones, the results of noise monitoring in urban and industrial zones in the province of Tien Giang in the period 2008 - 2010 are presented in Table 6:
Table 6: Results of noise monitoring in urban and Tien Giang Industrial Park
(Unit: dBA)
Parameter Value 2008 2009 2010 TCVN 5949 - 1998
(6h–18h)
Noise level in urban area
Total samples
68 52 26
Average 72,7 71,6 69,1 75
Noise level in Industrial area
Total samples
4 4 2
Average 74,2 72,0 74,5 75
Source: Air Quality Monitoring Results of DONRE Tien Giang province in the years 2008, 2009, quarter and quarter II/2010.
41. The calculated results show that the average noise level has not exceeded the permitted standard. Comparing the noise level of urban and industrial zones, industrial zones have higher noise level from 0.4 to 5.4 dBA.
42. Air quality in the rural environment is generally better than that of urban areas and the dust suspended parameter tend to be improve by the province‟s efforts as the province is actively implementing the concrete road program in rural areas. On the other hand, the strong economic garden development, scattered tree planting, farm economy, has contributed to environmental improvements (e.g. increased vegetation cover and limit dust, noise, smell etc.)
16
Dong Thap
43. The results of air quality monitored by Dong Thap DONRE in urban and industrial areas during 2005-2009 show that air pollution in Dong Thap province occur locally and is caused mainly because of transportation and handicraft industries in villages. The air quality can be generally assessed as follows:
44. Three parameters: SO2, NO2, CO is generally meets QCVN 05:2009 / BTNMT
Noise and dust noise exceeded the permitted standard in urban, industrial area, and school areas because of high transportation density. At some monitoring points of urban areas like post office area, Sadec town, Ward 1 Sadec town and Market Cai Tau Ha the dust and noise exceeded permitted level from 1.27 to 7.1 times. In industrial areas Sa Dec and Tran Quoc Toan, dust and noise concentration exceeded permitted level from 1.05 to 5 times
Hydro carbon has also been detected with concentation 0.9 and 1.8 mg/m3 in industrial area and at traffic intersections.
At dumping sites, Ammonia concentration exceeded permitted level 21times and H2S varied
B. Ecological Resources and Sites of Archaeological Significance
1. Protected areas, endangered species Forests and ecosystems
Tien Giang
45. With typical wetland resource, Tien Giang Province has formed the ecosystem to the following:
The freshwater ecosystem: This is the focus of ecological forms of agriculture and fruit growing areas, including fruit tree area on the island and populated areas along the Tien river in the districts of Cai Be, Cai Lay, Chau Thanh and My Tho city, with a verdant orchard in the four seasons, and, the vast intricate canal water.
The mangrove ecosystem: The above form the mangrove ecosystem (tiger, parrot etc.).
46. Based on these natural conditions, these areas have formed the sea resort, resorts, swimming, sightseeing areas alum-flooded ecosystem, with mangrove forest ecosystems, typical of the Mekong River Delta. The alum flooded forest areas in Dong Thap Muoi reappear in Tan Phuoc District, Tien Giang with the center of 100 hectares and the buffer surrounded by 1.800ha mangrove forest. This is a vast field with alum flooded unique ecosystem in Viet Nam, the species of plant and animal endemism, such as melaleuca, eagles, strabismus, birds, flamingo, pythons, turtles, bees, etc. serve as best place for the research work of scientists as well as relaxing place to visit.
47. Biodiversity resources of the forests of Tien Giang province is now no longer plentiful as before, because apart from 100 hectares of pristine mangrove forest at Tan Phuoc district, the remaining forest area is mainly sea protection mangrove forest.
48. In recent years the forest resources of the province of Tien Giang has shown a trend of decline. The changes of the provincial forest area to 2009 are presented in Table 7:
17
Table 7: Forest area in Tien Giang province from 2006 to 2009
2006 2007 2008 2009
Concentrated plantation area (ha)
31 81 169 183
Scattered plantation area (ha) 2.200 2.310 1.906 2.116
Forest area under care (ha)
11.784 10.795 9.836 8.516
Restored Mangrove forest (ha)
- - - 30
Total area (ha) 14.015 13.186 11.911 10.845
Source: Statistical Yearbook of Tien Giang province in 2008, 2009
49. The ecological resources in subproject sites (Cai Lay and Go Cong District) are quite abundant and diversified with typical wild animals and flora of Dong Thap Muoi. The typical plants in flooded alkaline land are regenerated cajuput, aegiceras and some valuable animals as fresh water fish, shrimp, sugpo prawn etc., besides, some plants cultivated, there are a few brackish floristic compositions outside the embankment. Wide animals no longer exist due to the urbanization and intensive cultivation; the aquatic vegetables living in the waterways tend to change the species‟ composition to adapt the new environment caused by closing the salinity prevention sluice.
50. The subprojects sites are not located in the environmental sensitive or biodiversity rich areas.
Dong Thap 51. Dong Thap Province has many special-use forests: Tram Chim National Park, Xeo Quyt Relic, and Go Thap Relic. The most important ecological reserve is Tram Chim National Park.
52. Tram Chim National Park comprises of 7,600 ha of protected wetland in Tam Nong District, Dong Thap province, 240 km southwest of Ho Chi Minh City. The Viet Namese Government has recognized Tram Chim as a national park in December 1998, thus preserving one of the last extensive remnants of grasslands and freshwater swamp forests in the Mekong Delta.
53. Tram Chim (Bird Marsh) is in one of the lowest areas of the Mekong River floodplain, and monsoon floodwaters inundate the area four to six months every year. Peak floods may reach five metres. During the wet season (June to November), Tram Chim looks like a huge lake dotted with islands of melaleuca, a species of the paper-bark tree, Melaleuca cajuputi. During the dry season (December to May) visitors can find vast grasslands intermingled with melaleuca.
54. The grasslands and forests of Tram Chim harbour is a diverse large lush, freshwater wetlands ecosystems with more than 160 native plants, more than 200 bird species, and 60 species of freshwater fish.
55. Tram Chim is now the only place in the Mekong Delta with extensive areas of wild rice (Oryza rufipogon) and lotus (Nelumbo nucifera). Above all, Tram Chim is famous for its birds. Twelve species of birds recorded at Tram Chim are classified as globally threatened or near-threatened, including the sarus crane, Bengal florican, greater adjutant, lesser adjutant, greater spotted eagle, black-headed ibis and black-faced spoonbill, painted stork, Asian openbill, oriental darter, grey-headed lapwind and Asian golden weaver.
18
56. The eastern sarus crane (Grusantigone sharpii) is the park's most important species. The discovery of a large flock of sarus cranes in 1984 attracted attention from conservation groups and government agencies, resulting in the site being declared as a provincial protected area and, finally, as a national park. The magnificent sarus crane is the world's tallest flying bird. It migrates between breeding grounds in northern Cambodia and southern Laos and non-breeding areas in north-western Cambodia and the Mekong Delta. Sarus cranes start to move to non-breeding areas in December and return to breeding sanctuaries in May-June. Tram Chim grasslands provide a key non-breeding area for cranes. The number of sarus cranes flying to Tram Chim is highest during March and April.
57. The natural forest in Dong Thap province is only Indigo forest. In 2010, its area is 3400 ha, 1000 ha less than that in 2009. The production forest resources of the province of Dong Thap also have tendency to decline because the forest owners do not reforest after exploitation as they do not have any income to cover investment. The changes of the provincial production forest area from 2005 to 2009 are presented in Table 8.
Table 8: Forest area in Tien Giang province from 2006 to 2009
2005 2006 2007 2008 2009
Concentrated plantation area (ha)
470 204 372 376 397
Scattered trees (1000 trees) 6053 6537 6405 6760 6540
Bamboo trees (1000 trees) 6370 5138 4437 4467 3911
Source: Statistical Yearbook of Dong Thap province, 2009
58. Subproject upgrading canal Khang Chien is proposed approximately 1 km of border of Tram chim area. However, the construction activities would have negligible or no impact on birds‟ normal life.
2. Flora and fauna
59. Dong Thap Muoi is one of the most important areas in the Mekong Delta for both resident and migratory waterfowl, and is most important area for the endangered eastern race of the Sarus Crane Grus Antigone sharpii hitherto known. The crane was a common breeding bird in the area some 30–40 years ago, but disappeared completely during the war years and has returned only recently as a no breeding visitor during the dry season. Groups of 10–20 birds were observed by Viet Namese biologists in early 1985. Since then, the population has increased rapidly and each year the birds have stayed longer in the area. Estimated 400-500 cranes were present in January, 1988 and more than 1,000 were recorded in April,1988. Some cranes are now present all year except in September and October, when the land is deeply flooded.
60. The largest concentrations of water flow occur during the winter months, as water levels are decreasing. A concentration of 20,000-30,000 ducks, mainly Anas querquedula with some A. acuta and A. Penelope, was observed in December 1987. Other common species include Phoiacrocorax niger, Ardeola bacchus and several species of Egretta, Ardea purpurea, A. cinerea, Anas poecilorhyncha, Metopidius indicus, Himantopus himanlopus, Glareola maldivarum, Pluvialis dominica, Numenius arquata, Tringa totanus, T. nebularia, T. stagnatilis and T. glareola. The storks Mycteria leucocephala, Ephippiorhynclzus asiaticus and Leptoptilos javanicus and the ibis Threskiornis melanocephalus are regular visitors in small numbers. It is possible that the endangered White-shouldered Ibis Pseudibis davisoni and Giant Ibis Thaumatibis gigantea still exist in the area, although none has been seen in recent years. The harriers Circus (aeruginosus) spilonotus and C. melanoleucos are common winter visitors. The list of bird species in Tram Chim National Park is presented in Annex 1. Mammals include an otter Lutra sp. The rich reptilian fauna includes a wide variety
19
of snakes and turtles. The dominant fishes are species of Ophiocephalus, Clarias and Anabas.
Figure 6: The number of Sarus crane visiting the park has increased from 89 in 2006,
to 125 in 2007, and to 126 birds in 2008
61. The presence of flora and fauna were analyzed keeping in view the scope of work of present project activities. Consultations with park authorities as well as local communities were undertaken to assess presence of wildlife and likely impacts of project activities on movement of wildlife. Local communities and park authorities informed that presence of wildlife in the project areas is rare and as such no major impacts are identified. However, to mitigate any unexpected impacts during the implementation of the project, appropriate mitigation measures are recommended in the environmental management plan.
3. Fisheries
Tien Giang
62. Situated at the end of Cuu Long River, Tien Giang has 32 km of seashore. The system of rivers and canals is stretching throughout the province. Therefore, Tien Giang has rich, and diversified fishery resources with many races, species that live in fresh water, salt water, and brackish water. It is convenient for exploiting, rearing, and processing aquatic products, and transferring goods to Ho Chi Minh City and other provinces by roadways, and waterways.
63. Fishing is a traditional profession in Tien Giang and developed systems of logistic services exist there. The boats team of fishery exploitation includes 1,200 boats with average capacity of 128.9CV/boat. The team of fishing men is experienced, and professional. The exploitation output reaches 65,000 tons/year.
64. Go Cong costal area has about 7,500 ha for salt-water aqua culture, brackish aqua culture, and other species with high economic values such as red arca and common tiger prawn. Fresh water zone has crayfish, and other kinds of small fishes for processing fish sauce, fish powder, and being fish for cattle. There fishes are kept in ponds, lakes, rice fields, and in rafts along Tien River. The aquaculture sector has an area of 10,765hectares. Its output is about 46,570 tons/year. Main export products are all kinds of frozen shrimp, etc. Main export markets are EU, Japan, United States, Canada, Taiwan, and China (source: http://asemconnectvietnam.gov.vn)
Dong Thap
20
65. With the terrain water topography, aquaculture products are given second place of importance after rice. Aquaculture is extensively developed in the province. The main resources are catfish, basa fish and prawn. Water area for aquaculture has reached more than 6,000 ha, the farmers focus on rearing shrimp in rice fields, and rearing fish in alluvial area of Tien and Hau rivers. This area has a great potential to develop into key regional aquaculture. Yearly this province supplies more than 245,000 tons of fish and thousands tons of shrimp for processing and export has reached a turnover of several hundred million dollars.
4. Sites of Archaeological Significance
Tien Giang
66. Tien Giang province is rich in cultural relics and ecological history. The famous sites are: Oc Eo –Go Thanh cultural relics, (from I to VI century AD); historical site Rach Gam – Xoai Mut, relics of Ap Bac; many historical tombs, temples such as Truong Dinh Tomb, the Royal tomb, Tu Kiet, Vinh Trang Pagoda, Buu Lam Pagoda. Many ecotourism sites such as orchard in Thoi Son, Ngu Hiep, Dong Tam snake farm, ecological zones in Dong Thap Muoi, sea Go Cong.
67. Those cultural and historical sites are located far from the project sites, so, no impact would occur during construction activities.
Dong Thap
68. Tram Chim National Park is famous for Red head cranes. In thousands of hectares of mangrove forests and wild meadows of a small collection of Dong Thap Muoi, hundreds of rare species of wetlands are being preserved and protected. Xeo Quyt is a tourist area, which was the base of the Provincial Committee of Kien Phong during the war, this place also known for its pristine mangrove forests and monuments of a historical period of Dong Thap province.
69. Area Gao Giong is ecological tourism, which is known as the green lung in the centre of the Plain of Reeds. Go Thap relic is located in the heart of the Dong Thap Muoi area and is famous for its ancient culture. Each piece of pottery, every brick, every stone, etc. are unearthed conveys mysterious signal on Oc Eo culture of Fu nam people who lived 1,500 years ago. It also has many ancient temples with two festivals each year the attract thousands of tourists. At the center of the city, Cao Lanh is also a relic of Nguyen Sinh Sac - father of President Ho Chi Minh Dong Thap, and has many ancient temples. The most famous temple of Kien An Cung, represents a religious and cultural works.
Table 9: Pagodas and temples and protected area situated near Subproject areas
No Pagoda/Temple Province District Commune / Village
Pagoda / Temple near
Estimated distance from
Subproject area
1. Truong Dinh Tomb,
Tien Giang
,
Gò Công Đông
Gia Thuan/Hamlet 2
Upgrading the salinity intrusion control system in Go Cong area
12 km to the East
2. Truong Dinh monument
Gò Công Town
Ward 2 3 km in all directions
3. the Royal Tomb Gò Công
Long Hung 3 km to the North-
21
No Pagoda/Temple Province District Commune / Village
Pagoda / Temple near
Estimated distance from
Subproject area
4. Tu Kiet, Vinh Trang Pagoda,
Cai Lay Town
Cai Lay Town Upgrading Flood control system in Ba Rai – Phu An area
2 Km to the North-east
5. Long Khánh Temple
Cai Lậy Long Khánh 8 km to the East
6. Kim Tiên Pagoda
Cai Lậy Cai Lậy Town 1,5 km to the North-east
7. Archaeological site Buu Thap Pagoda
Cai Lậy Tân Hội 2 km to the North-east
8. Archaeological site Gò Công Éc
Dong Thap
Tân Hồng
Thông Bình, Improving and upgrading flood control and irrigation canal of the Plain of Reeds-
Upgrading Cai Cai canal
About 4 km to the West
9. Archaeological site Go Chua
Tân Hồng
Bình Phú, Upgrading Thong Nhat canal
About 3.5 km to the East
10. Archaeological site Go Chua Tam Au. Here, some artifacts, relics of archaeological cultures Eo,
Óc Eo, were found
Tân Hồng,
Tân Thành B, Upgrading Cai Cai canal
About 8 km to the West
11. Archaeological site Gò Tàu,
found in 1992
Tân Hồng,
Tân Hộ Cơ Upgrading Cai Cai canal
About 9 km to the West
12. Archaeological site Tân Long Tự, found in
Tân Long pagoda
Tân Hồng
Tân Thành B Upgrading Cai Cai canal
About 8.5 km to the West
13. Archaeological site found in Thiện Tự Pagoda,
It are Oc Eo cultural relics
Tân Hồng
Bình Phú Dredging Thong Nhat canal
About 3.5 km to the East
14. Long Khanh Temple
Hồng Ngự,
Long Phước Hamlet, Long Khánh A commune
Thuong Thoi Thuong River Bankment/Hong Ngu River Bankment
3.5 km to the West
22
No Pagoda/Temple Province District Commune / Village
Pagoda / Temple near
Estimated distance from
Subproject area
15. Long Thuan Temple
Hồng Ngự
Long Thới B Hamlet, Long Thuận commune
Thuong Thoi Thuong River Bankment/Hong Ngu River Bankment
7 Km to the West
16. Tram Chim National Park
Tam Nông,
Tràm Chim town
Dredging Khang Chien canal
About 1.5 km to the North
Phú Đức Commune
Dredging Tan Cong Chi-Doc Vang Ha canal
About 2 km to the East
Phú Hiệp Commune
Dredging Tan Cong Chi-Doc Vang Ha canal
About 2 km to the West
Phú Thành B Commune
Dredging Thong Nhat canal
About 1.5 km to the East
Phú Thọ Commune
Dredging Thong Nhat canal
About 2 km to the East
Tân Công Sính commune
Dredging Tan Cong Chi-Doc Vang Ha canal
About 9 km to the West
17. Dinh Doc-Binh Vang Cultural Relics
Thanh Bình
Village Nam, Comune Tân Thạnh
Dredging Khang Chien canal
About 9 km to the West
C. Human and economic development
1. Population
70. In 2009, the population of Tien Giang and Dong Tháp provinces is 1.673.900 and 1.667.700 respectively. The detail population structure is presented in Table 10.
Table 10: The population in 3 provinces, 2009 (thousands)
Province
Population
Area
(km2)
Density
(persons/
km2)
Urban
Rural
Total Male Female
Tiền Giang 1673.9 822.6 851.3 2484.2 674 230.5 1443.4
Đồng Tháp 1667.7 833.4 834.3 3375.4 494 287.5 1380.2
Source: General Statistical Office 2009.
2. Economic development
Tien Giang
71. Gross domestic product (GDP) at constant 1994 prices in the province in 2005 was 8167 billion. It is expected to increase to 13,735 billion in 2010, the average` growth rate for 2006-2010 is 11.0%, achieving the objectives of the plan (11-12% per year). The agriculture, forestry and fishing, in particular has increased average by 5.1%per year, industry and construction increased by 19.5% per year, service sector increased by 12.4%. per year.
23
Dong Thap
72. The economic structure of the province is changing from agricultural sector to industrial sector. Particularly, structure of agricultural sector has decreased from 43% (2005) to 40% (2009), meanwhile, structure of industrial sector increased to7% and service sector increased to 1% during 2005-2009.
73. The value of industrial production (constant 1994 prices) during 2006-2009 is 34%–25%. The Retail of goods and services sector counted for 31.43% of province GDP. Agricultural sector continues developing forward in diversifying crops and livestock; increasing product quality and production productivity. The average growth rate of agriculture, forest and fishery during 2006–2009 and 2009 accounts for 6.89%, and 4.18%, respectively.
74. The output value of agriculture, forest and fishery; Industry; and retail of goods and services in 3 provinces are presented in Table 11:
Table 11: Structure of the economical sector in the two Provinces (billion dong)
Province 2006 2007 2008
Tien Giang
- Agriculture, forest and fishery 5302.4 55110 5742.8
- Industry 7486.9 9583.2 13057.6
- Retail of goods and services 10505 13002.3 15413.6
Dong Thap
- Agriculture, forest and fishery 5561.9 5719.1 6098.1
- Industry 8455.9 11900 18095
- Retail of goods and services 9256.7 1278.9 16891
Source General Statistic Office, 2008
3. Income, employment and poverty incidence
Tien Giang
75. According to the report of the provincial People's Committee of Tien Giang, GDP per capita in 2010 was estimated to increase 2.6 times in 2005, from 7.8 million in 2005, which is expected to increase to 20.5 million in 2010 (equivalent to $1,130 ), exceeding the planned (Resolution Provincial Party target strives $900-930, PPC target strives $950-1020). The employment rate in urban area is about 96% and the poverty rate in 2010 is 7.04%
Dong Thap
76. GDP growth rate per capita was from USD 406 in 2005, which increased to USD 610 in 2008 and USD691 (equivalent to 7631 VND) in 2009. This indicates that the annual income per person increased quite quickly. However, this income is equal only to 75.5% of average income per person in Mekong Delta.
77. The poverty rate of the province has decreased from 13.59% in 2005 to 7% in 2008 and 5.69% in 2009
4. Land use
78. The status of land use in the Project Area is presented in Table 12.
Table 12: Status of land use in the Project Area (2009)
Province Total Natural
Agricultural land (ha) Non-
Agricultural Unused
land
24
area (ha) land (ha) (ha)
Total Yearly crops
Forest
Tien Giang (2009) 248,417 192.334 97.647 10.028 48.602 7.481
Dong Thap (2009) 337,407 463,701 8,637 458,362 70,506 -
Source: Environmental State report 2005-2010 of, Tien Giang, Dong Thap provinces.
5. Education and health
79. Number of schools, classes, teachers and pupils of kindergarten and general education of three provinces are presented in Table 13:
Province Tien Giang Dong Thap
2008 2009 2008 2009
Kindergarten
School(Schools) 117 128 162 170
Class (Class) 1311 1272 1542 1763
Teacher (Pers.) 1448 1421 1799 2077
Pupil (Thous. Pupil) 46.1 43.3 45.1 48.4
General education
Primary (Schools)
229
229
316
317
Lower Secondary (Schools) 120 124
137
137
Upper Secondary (Schools) 29 31 40 42
Primary and lower secondary 1 1 - 10
Lower and upper Secondary
5
3
- -
Total (Schools) 384
388 493
506
Total (Classrooms) 7138 6961 7353 7263
Primary (Teachers) 5397 5570 6581 6878
Lower Secondary (Teachers) 4995 5007 5021 5076
Upper Secondary (Teachers) 2041 2096 2434 2812
Total (Teachers) 12433
12673
14036
14766
Primary (Pupils)
130289
138434
135420
139861
Lower Secondary (Pupils)
99315
94096
93516
88726
Upper Secondary (Pupils)
43489 41297 46415 44819
Total (Pupils) 273093
273827
275351
273406
Source: General Statistic Office, 2010.
80. The existing health systems in two provinces are presented in Table 14:
Table 14: Existing Health System in two Provinces
Province Tien Giang Dong Thap
Table 13: Number of schools, classes, teachers and pupils of kindergarten and
general education of two provinces
25
2008 2009 2008 2009
Health establishment
Hospital 16
16
12 12
Regional polyclinic 16 15 13 13
Sanatorium and rehabilitation hospital
1
1
Medical service unit 169 169 142 144
Total 201 200 168 170
Number of Patient Beds
Hospital (beds)
2120
2478
2440
2775
Regional polyclinic (beds) 260
285
150
150
Sanatorium and rehabilitation hospital (beds)
0 0 80
100
Medical service unit (beds) 817
845
788
793
Total (Beds) 3197 3608 3458 3818
Number of medical staff (person)
Doctor (persons)
757
774
762
780
Physician (persons)
805
819 990
1055
Nurse (persons)
907
920
1029
1219
Midwife (persons)
387
422
414 504
Source: General Statistic Office, 2010.
Tien Giang
The rate of commune‟s health stations with Doctor: 100% in 2010
The rate of doctor / 10 thousand populations: 6
Rate of hospital bed / 10 thousand populations: 26
Dong Thap
The rate of doctor / 10 thousand populations: 4.7
Rate of hospital bed / 10 thousand populations: 22.9
6. Access to water supply
Tien Giang
81. In general, the surface water resources in the province are abundant. However, the only one water resource with good water quality, to serve peoples‟ and cultivation needs, comes from the Cuu Long River. The less fresh water resource is in closer areas of the East sea; fresh water shortages and salinity intrusion are rather serious in Go Cong area; and the area in Tan Phuoc district of Plains of Read suffers from acid sulphate water.
26
Dong Thap
82. So far, the province has 305 built water supply stations, 8,000 wells with hand pumps and 16,579 water filters have been distributed. In addition to this, the households have built more than 1,200 water tanks (type 4m3).
83. In 2000, the percentage of rural population access to water supply source was 28.24% (from which 18.24% were supplied by water supply projects) and in 2005 was 60.48% (from which 43% were supplied by water supply projects) and in 2006 was 68.5% (from which 51.5% or 142,425 rural households were supplied by water supply projects). Tan Hong and Dong Thap districts have a highest proportion of the rural population receiving clean water. Rural population of Cao Lanh and Sa Dec towns was served by water supply with low rate1 (Source: Agriculture and Rural Development Planning Dong Thap province in 2020 period, 2009).
Tien Giang
84. Wastewater: The existing drainage system in urban areas in the province is combined both rainwater and sewage. Currently, no city/town in the province has any wastewater treatment system. The three sectors, which incurred the largest wastewater amount, 2400 m3/day textile waste, 2118 m3 seafood waste and 1443m3 domestic wastewater. The province has 03 industrial parks officially put into operation, which are: My Tho Industrial Zone, Tan Huong Giang and Long Industrial Park. Wastewaters in industrial zones are treated at wastewater treatment plants concentrated in the industrial parks.
85. Solid waste: According to the Report on the implementation plan to protect environment in 5 years (2006-2010), the total amount of domestic solid waste collected in the province from 2006 to 2010 was about 240 tons per day, mainly from towns, townships and urban areas (estimated at about 80% of proportion of total waste generated in urban area. Specially, collection rate in the city of My Tho reached about 90%).
86. The urban waste is primarily buried in landfills. According to statistics in 2009, Tien Giang province has only 05 landfills. Overall, the landfills are not handled well and in accordance with the regulations, causing environmental pollution for the surrounding residential areas.
87. Currently, the total generated volume of non-hazardous industrial solid wastes is about 76tons per day, which My Tho Urban Works Company collects, transports and disposes at the Tan Lap landfill (Tan Phuoc district). The recyclable industrial waste is allocated to the private sector for classification, recycling, or reassigning them to the recycling enterprises in Ho Chi Minh City. The generated volume of hazardous industrial solid waste is not much. It is approximately about 2497.58 kg / month and 407 litres per month.
88. Currently, medical waste generated in the province of Tien Giang is about 0.81 tons per day. Most of these types of solid waste is collected and stored in containers which are used exclusively in hospitals, clinics then processed or transported to facilities, where medical waste incinerator for treatment.
Dong Thap
89. Wastewater: According to Dong Thap DONRE, in 2008, in urban area of the province about 23,248 m3 of domestic waste water is disposed daily and it is treated by households (septic tanks), thus, the water quality meets standard before being discharged into surrounding environment. In rural area about 111,368 m3 of domestic waste water is
1 Source: Agriculture and Rural Development Planning Dong Thap province in 2020 period, 2009
27
disposed daily. However, due to simple latrines and low level of septic tank, wastewater is almost non treated, before being discharged into environment causing serious water pollution. About 1,556 m3 of hospital wastewater is generated daily in the province. However, at present only 3 hospitals have operational wastewater treatment plant. Other units do not have treatment plant then wastewater is discharged directly into environment. Wastewaters from industry, agriculture, aquaculture and handicraft villages are discharged into environment without treatment or not being treated properly.
90. Solid waste: The source and amount of solid waste in Dong Thap province are presented in Table 15.
Table 15: Solid Waste Generation in Dong Thap Province (ton/year)
2007 2008 2009
ton/day ton/year ton/day ton/year ton/day ton/year
Domestic SW- urban 201 73,255 205 74,968 210 76,596
Domestic SW- rural 552 201,422 552 201,614 552 201,515
Total domestic SW 753 274,677 758 276,582 762 278,111
Industrial SW - - 160 58,228
Livestock SW 963 1235 1257
Hospital SW 1431 1448 1664
Source: 5 year-State Environmental Report 2005-2010 of Dong Thap Province
91. This kind of solid waste is not properly collected and sanitary treated. The amount of collected solid waste is only 125 ton/day. Regarding domestic solid waste, only 52% or 65 ton is collected daily and the collection is implemented mainly at wards in center of towns and city. The common treatment method for urban solid waste is disposal into dumping sites. Cao Lanh city has new 20 ha landfill – Dap Da, where the city SW is disposed. Regarding industrial SW, for its small quantity, it is collected and disposed together with domestic SW. Regarding hospital SW, 100% of hospitals in Dong Thap gets collected its waste daily and transported to storage place. Two hospitals has waste storage meeting standard; 7/15 medical units store waste for 48 hrs, other unit do not meet storage requirement. Hospital SW is treated by incineration method. Seven hospitals have their own incinerator; the remaining 5 do not have incinerators.
7. Transportation
Tien Giang
92. Till date, Tien Giang has fairly complete transportation system providing access to all areas in the province. It helps in the transportation of goods and products quickly, conveniently between the Mekong delta provinces and Hochiminh city
93. Road: road traffic system has a total length of 5,045km; the average density is 2.130km/km2.
94. Waterways: The province has high density of waterways, making province as a transit area from the western provinces to Hochiminh city, through Tien River, Cho Gao canal, Soai Rap river and many inter-province canal and rivers.
Dong Thap
95. Road system: Dong Thap province has two national highways:
National road 30 along Tien river, connecting to National road 1A toward north direction of the border areas, through the gate Dinh Ba (Tan Hong) and connecting provincial road 841 to gate Thuong Phuoc (Hong Ngu). These roads are
28
considered as the arteries of the province on the Plain of Reeds and also the important roads in the Viet Nam – Cambodia economic border exchanges.
National road 80 pass through the area between two rivers Tien - Hau River, linking National road 1A (Tien river) with National road 91 (Hau river), is considered as the main transportation route from Long Xuyen quadrangle to the economic southern key economic zone.
96. On the waterway, the Tien river is an important waterway connecting the East Sea with the courtiers in upstream Mekong River. This axis is also the international waterway of the Mekong Delta. Though Hau river running through the province of Dong Thap is short, but this is an axis of the international waterway of the region. Moreover, large canals like Lap Vo canal, Muong Khai (linking Tien-Hau River), Central Channel, Dong Tien, Nguyen Van Tiep etc. have created an important waterways network for the exchange of goods between Dong Thap province with provinces in the Mekong Delta and Ho Chi Minh City.
IV. ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES
A. General Potential Environmental impacts
97. There are five proposed subproject investments for the Greater Mekong Subregion in Viet Nam include 1 subproject in Dong Thap of rehabilitation and upgrading of canal system, 2 subprojects of flood control and salinity intrusion control projects ( 2 in Tien Giang), 1 subproject of Bank protection (2 in Dong Thap). According to the Design, three among the seven proposed subprojects will be of rehabilitation and upgrading of canal system with 33 -119 km of primary canal length , two of them will construct regulation sluices to prevent flood in the rainy season and , remaining two will construct embankment for bank protection. So these proposed subprojects will cause environment impacts, both positive and adverse, at various levels.
1. Positive impacts
98. Main positive impacts for all subproject are as follows:
Flood control and waterlogging drainage in flood season for all subproject areas;
For the subproject of Plain of Reeds, in combination with other flood control protection from flood water discharge from Cambodia border to the Plain of Reeds toward the Mekong river to reduce flood water level in main flood season to protect people‟s life and their properties;
Water supply for irrigation and creation of water source for aquaculture sustainably and people‟ life in dry seasons;
Bank erosion prevention for section of Thuong Thoi –Thuong Phuoc -Tien river to protect safety of life for communities living along two sides of the river;
Improving environment-hygien conditions for local peoples affected by flood in Tien Giang and Dong Thap Provinces , especially in flood season;
Decrease in waterborne diseases caused by inundation situation;
Inland rural and navigation transportation development;
Promotion of development of tourist, cultural , social-economic sectors in subproject areas;
Beneficaries from the subprojects will be significant, it is estimated as below: - 370,000 persons for Ba Rai-Phu An subproject - 97,700 person for Go Cong area subproject - 520,000 persons for The Plain of Reeds subproject - 13,493 persons for Thuong Thoi Tien town, Hong Ngu subproject
29
2. Negative impacts
99. In general negative impacts are foreseen during the construction phase such as increase in noise and dust level, pollution of surface water from wastewater, disturbance of contaminated soils, affects on traffic and social-economic activities for local people. Mitigating measures could easily be taken to minimize the impacts. In the following sections a brief description of the main impacts is described.
100. Subprojects for Improving and upgrading of flood drainage and irrigation canal system canal system (No. 1,4)
Loss of temporary and permanent land;
Relocation of affected households;
Increase in dust level due to excavation, filling not due to transport work as material will be transported by waterway
Pollution of the water, especially polluted by alum due to excavation earth is alum, it is to be filled for embankment, so it is easy to cause pollution for canal water and water bodies near by the site, especially in rainy season
Affect to irrigation water quality of downstream of the canal or the adjacent area due to mainly increase of turbidity, and waste water from the construction site and camp;
Aquatic flora & fauna will be indirectly affected;
Indirect effect on water birds species, especially, Red head Crane (Grus antigone) in Tram Chim National Park during construction phase for some canal section which parallels and close by the Tram Chim National Park. However, nearest distance of canal section to the Tram Chim National Park is about 500m and Red head Crane often come to Tram Chim in March to May every year, before flood season, so that construction activities should be avoided in this time and construction equipment need to minimize noise as much as possible in the construction works;
Disturbance in the buffer zone surrounding the Tram Chim National Park during construction for Plain of Reeds Primary Canal Upgrading, is of small level because the park is not in close proximity. The distance from the Park to the sites is about 1.5-9.0 km;
Effects on traffic and social-economic activities of local people and communities is of small level because the population density in subproject area is low and houses are scattered along both the sides of the canal.
101. Subprojects for Building of flood control and salt water intrusion protection Sluices (No 2,3)
Only temporary loss of land during construction phase;
No relocation of households and land compensation ( according to conclusion of PPMU in meeting with Tien Giang DARD on 13 July 2010)
Increase in dust and noise levels due to excavation and filling work at insignificant to small level, but not due to transportation as workmaterial will be transported mainly by waterways;
Erosion, increase of turbidity by excavation and movement of construction equipment;
Affect on irrigation water quality of downstream of the canal or the adjacent area due to excavation, mainly increase of turbidity, and waste water from the construction site and camp;
30
Interruption in domestic activities of local people living along the canal;
Interruption of waterways and road traffic during construction. It wil lead to increase of good transportation cost due to change of transportation way or means;
Change of hydrological regime of channel and canal downstream due to change of flood drainage regime, canal sedimentation during operation phase;
Obstruction or change in movement of fish species due to operation of sluices
Aquatic flora & fauna will be indirectly affected
Change to landscape values of the subproject area
102. For all subprojects
Pollution level of air by construction material exploitation and transportation activitiesis considered as small to moderate. Exhaust fumes are mainly generated from construction machinery like compactor, excavators, generators; Exhaust fumes include NOx, COx, Hydro Carbon. Scope of impacts is considered small to moderate because transportation means are mainly by water way, number of machinery is small,and construction area is large . So GHG emissions caused by the Project will be very insignificant.
103. Subprojects for Bank protection for Thuong Thoi Tien town, Hong Ngu district, Dong Thap province.
Loss of temporary and permanent land;
Relocation of affected households ;
Increase in dust and noise level due to excavation, filling at insignificant to small level, not due to transport work as material transport mainly by waterway;
Erosion, increase of turbidity by excavation and movement of construction equipment;
Effect to waterways traffic due to embankment of canal bank;
Aquatic flora & fauna will be indirectly affected.
B. Impacts and Mitigation Measures during Pre-Construction Phase
104. The potential adverse environmental impacts and the proposed mitigation measures related to Project Location and Design (Pre-Construction Phase) of the subprojects are presented in Table 16, Table 17 and Table 18.
105. The following abbreviations are used:
N: not applicable, no adverse effect;
S: small/slight adverse effect;
M: moderate adverse effect;
L: large adverse effect.
Table 16: Subprojects for Improving and upgrading of flood drainage and irrigation
canal system canal system (No. 1, and 5) Pre-Construction Phase
31
SUBPROJECT
major characteristics
of new outlet
PROJECT ACTIVITIES
No
POTENTIAL ADVERSE IMPACTS
Socio-economic and
physical/biological aspects
REMARKS MAGN.
OF
IMPACT
PROPOSED MITIGATION MEASURES
Improving and upgrading of flood drainage and irrigation canal system canal system
Site selection and design
Surveys and site investigations
Land acquisition
1 Land acquisition requirements & displacement of local residents
For Plain of Reeds:
1369 m2 of
agricultural land to be acquired permanently,
929 m2
of residential land to be acquired permanently with 100 HHs to be affected ( from RP-VisionRI resettlement group)
S-M Prepare Resettlement Plan (RP) based on an agreed resettlement and compensation framework & implement accordingly
2 Displacement of local residents
100 HHs S
3 Proximity to human settlement
Human settlements not disturbed
N
4 Proximity to environmentally sensitive areas / areas with aesthetic value
Plain of Reeds
Primary Canal
Upgrading,
some canal
section which
parallels the
Tram Chim
National Park.
S Proper design; sufficient buffer
Consult to Management Board of Tram Chim National Park
5 Proximity to ethnic minority community
Not present N
6 Proximity to natural habitats
Dredging canal would improve natural habitats
N
7 Effect on historical / cultural monuments, grave yards
Historic monuments, grave yards not present
N
8 Changing land values
No or slight effect
N
9 Conflicts with other water users
No conflict with other users
N
10 Degradation of water quality
Dredging of canal would improve water
N
32
SUBPROJECT
major characteristics
of new outlet
PROJECT ACTIVITIES
No
POTENTIAL ADVERSE IMPACTS
Socio-economic and
physical/biological aspects
REMARKS MAGN.
OF
IMPACT
PROPOSED MITIGATION MEASURES
flow and quality
11 Degradation of fisheries
Creation of water source for aquaculture sustainably
N
12 Degradation of navigation / river transport
Create navigation transportation development
N
13 flooding / odour / noise
Odour possible from floating waste
S Proper design; sufficient buffer
14 Vulnerability to erosion / landslide
Construction in flat area
S Proper design and O&M
15 Risk of earthquakes
N
16 Accessibility to trunk infrastructure
Road Construction material mainly to be transported by river navigation
N
Water supply N
Power supply N
33
Table 17: Subprojects for Building of flood control and salt water intrusion protection Sluices - Pre-Construction Phase
SUB-PROJECT
major characteristics
of new outlet
PROJECT ACTIVITIES
No
POTENTIAL ADVERSE IMPACTS
Socio-economic and
physical/biological aspects
REMARKS MAGN.
OF
IMPACT
PROPOSED MITIGATION MEASURES
Building of flood control and salt water intrusion protection Sluices ( No 3,4) in Tien Giang Province
Construct new sluice
-Ba Rai-Phu An: 27 sluice
-Go Cong area: 3 sluices
Site selection and design
Surveys and site investigations
Land acquisition
1 Land acquisition requirements & displacement of local residents
Land acquisition is not required
N
2 Displacement of local residents
No HHs need to be relocated by subproject
N
3 Proximity to human settlement
Human settlements not disturbed
N
4 Proximity to environmentally sensitive areas / areas with aesthetic value
No nature reserve at or nearby the subproject sites
N
5 Proximity to ethnic minority community
Not present N
6 Proximity to natural habitats
May affect fish movements due to building of new sluice
S Proper design and O&M of sluices
7 Effect on historical / cultural monuments, grave yards
Historic monuments, grave yards not present
N
8 Changing land values
No or slight effect N
9 Conflicts with other water users
No conflict with other users
N
10 Degradation of water quality
Dredging of canal would improve water flow and quality
N
11 Degradation of fisheries
Impact to fisherman for subproject in Go Cong area
No additional impact compared to temporary sluice to be installed in flood season
S Proper design and O&M of sluices
12 Degradation of navigation / river transport
Impact to navigation/ river transport when the sluice is closed
S Proper design and O&M of sluices
13 flooding / odour / noise
Odour possible from floating
S Proper design, sufficient
34
SUB-PROJECT
major characteristics
of new outlet
PROJECT ACTIVITIES
No
POTENTIAL ADVERSE IMPACTS
Socio-economic and
physical/biological aspects
REMARKS MAGN.
OF
IMPACT
PROPOSED MITIGATION MEASURES
waste buffer
14 Vulnerability to erosion / landslide
Construction in flat area
S Proper design and O&M
15 Risk of earthquakes
N
16 Accessibility to trunk infrastructure
Road Construction material mainly to be transported by river navigation
N
Water supply N
Power supply N
35
Table 18: Subprojects for Bank protection for Thuong Thoi Tien town, Hong Ngu district, Dong Thap province - Pre-Construction Phase
SUBPROJECT
major characteristics
of new outlet
PROJECT ACTIVITIES
No
POTENTIAL ADVERSE IMPACTS
Socio-economic and
physical/biological aspects
REMARKS MAGN.
OF
IMPACT
PROPOSED MITIGATION MEASURES
Bank protection for Thuong Thoi Tien town, Hong Ngu district, Dong Thap province
-Embankment of 3.244 km for Thuong Thoi Tien town,
Site selection and design
Surveys and site investigations
Land acquisition
1 Land acquisition requirements
For Thuong Thoi Tien Town
25,760 m2 of
agricultural land to be acquired
12,880 m2 of
residential land to be acquired permanently with 143 HHs to be affected (From FS)
S-M Prepare Resettlement Plan (RP) based on an agreed resettlement and compensation framework & implement accordingly
2 Displacement of local residents
For Thuong Thoi Tien Town
100 HHs to be relocated
M
3 Proximity to human settlement
Human settlements not disturbed
N
4 Proximity to environmentally sensitive areas / areas with aesthetic value
No nature reserve at or nearby the subproject sites
N
5 Proximity to ethnic minority community
Not present N
6 Proximity to natural habitats
Building embankment for erosion prevention would be not affected to natural habitats
N
7 Effect on historical / cultural monuments, grave yards
Historic monuments, grave yards not present
N
8 Changing land values
slight effect N
9 Conflicts with other water users
Embankment for bank protection will not to be conflicted with other water uses
N
10 Degradation of water quality
Embankment for bank protection would improve water flow and quality
N
11 Degradation of fisheries
Not affect on fishermen
N
36
SUBPROJECT
major characteristics
of new outlet
PROJECT ACTIVITIES
No
POTENTIAL ADVERSE IMPACTS
Socio-economic and
physical/biological aspects
REMARKS MAGN.
OF
IMPACT
PROPOSED MITIGATION MEASURES
12 Degradation of navigation / river transport
Create navigation transportation development
N
13 flooding / odour / noise
Odour possible from floating waste
S Proper design, sufficient buffer
14 Vulnerability to erosion / landslide
Construction in flat area
S Proper design and O&M
15 Risk of earthquakes
No additional impact compared to existing canal
N
16 Accessibility to trunk infrastructure
Road Construction material mainly to be transported by river navigation
N
Water supply N
Power supply N
37
C. Impacts and Mitigation Measures during the Construction Phase
106. Potential adverse environmental impacts that could result from activities during the Construction Phase are briefly discussed below and further presented in Table 19, Table 20 and Table 21.
107. Air quality/dust and noise: There could be an increase in dust, air pollution and noise from clearing, grubbing and excavation activities and movements of construction equipment. Emissions and noise from operation of construction equipment might have a considerable impact in residential area, especially densely populated areas, however the population in the Project Area near the subproject-sites is not dense and dust, air pollution and noise can be controlled and mitigated. Increase in noise may disturb the situation in the buffer zone surrounding the Tram Chim National Park during construction for Plain of Reeds Primary Canal Upgrading Project, which is however considered small because it is not in very close proximity. The distance between the Park and the sites is about 1.5-9km
108. Water resources and quality: Excavation and filling activities could lead to increase of turbidity in downstream of the canal or the adjacent area in general; especially canal water may get polluted by alum due to excavation of earth in Rach Tram-My Binh‟s subproject area. This could affect to water quality for irrigation and aquaculture.
109. Flooding and spills: Flooding and spills could be caused by inadequate management of building materials, removed topsoil, stockpiles and construction debris. Proper management can avoid these impacts and in case if once occurred, mitigation measures should be taken. Deposits of construction wastes in nearby water bodies might have a detrimental effect on aquatic flora and fauna and should be avoided.
110. Socioeconomic environment: noise from construction activities, traffic jams caused by transportation of construction materials, and accidents caused by trucks, disruption of socioeconomic activities are potential adverse impacts. However, the subproject-sites are not situated in densely populated area. With a Transport Management Plan and proper environmental management and monitoring these impacts can be prevented and mitigated.
111. Positive impacts: Temporary positive impacts include short-term employment of local population in construction activities and increased earnings in services in the vicinity of the construction sites. A permanent positive impact is the improvement of the functioning of the BHH-Scheme and could be increased employment for local residents in the operational services for the BHH subprojects.
112. In the tables the following abbreviations are used:
N: not applicable, no adverse effect;
S: small/slight adverse effect;
M: moderate adverse effect;
L: large adverse effect.
38
SUBPROJECT
major characteristics
of the subprojects
PROJECT ACTIVITIES
POTENTIAL ADVERSE IMPACTS
Socio-economic and physical/biological aspects
MAGN.
OF
IMPACT
PROPOSED MITIGATION MEASURES
Improving and upgrading of flood drainage and irrigation canal system canal system
Canal system of Plain of Reeds: 99.3 km
Base camp establishment and operation
Land clearance
Pollution by construction material exploitation activities
Earthworks / excavations
Haulage of fill and construction materials
Effects from temporary storage yards of construction materials
Access Road construction
Drainage structures
1 Physical / Chemical Environment
Air Quality
- Dust M
Temporary
Regular watering of exposed areas
Cover all trucks carrying dispersible materials to or from the site;
Ensure all construction vehicles and equipment are well-maintained;
Construction activities which can make noise should be carried out at day time
Inform local community about schedule and duration of construction works;
Regarding other material for construction such as sand, stone, contractor should choose legal service providers who had exploitation licenses and environmental protection commitment issued by local authorities;
- Odour S
Temporary
- Noise
S
Temporary
Water resources and quality
- Degeneration / contamination of surface water
( specially water resources could be polluted by alum soil in canal dredging for Rach Tram-My Binh subproject)
S
Temporary
Create drains & bund temporary to avoid spread of polluted alum water from filling & excavated alum soil ,
Diversion drains & bunds, temporary silt traps
ponds
Stockpiling of spoils in flat areas & far from
drainage routes
Disposing of unwanted spoils as soon as possible
Adequate temporary toilet facilities with adequate water supply & strict enforcement of proper sanitation
Adequate temporary toilet facilities with adequate water supply & strict enforcement of proper sanitation
Temporary disposal system for solid & hazardous waste
Table 19: Subprojects for Improving and upgrading of flood drainage and irrigation canal system canal system - Construction Phase
39
SUBPROJECT
major characteristics
of the subprojects
PROJECT ACTIVITIES
POTENTIAL ADVERSE IMPACTS
Socio-economic and physical/biological aspects
MAGN.
OF
IMPACT
PROPOSED MITIGATION MEASURES
- Generation of sewage / wastewater
S-M
Temporary
Adequate water supply to meet construction needs & setting up of rain catchment tanks
Adequate temporary toilet facilities with adequate water supply & strict enforcement of proper sanitation
- Generation of solid wastes
S
Temporary
Establish temporary latrines which meet regulations of Health Ministry and supply enough water to tents;
Discussing with residents to choose the suitable waste dumping site when workers build camps;
Collect solid wastes and temporarily store at a safety place before transporting to disposal sites;
Establish regulations for ensuring sanitation, stipulated dumping yard and waste treatment methods and disseminate those regulations to workers
- Siltation / erosion S
Temporary
Install diversion drains & bunds, temporary silt traps/pond
Stockpiling of spoil in flat areas & far from drainage routes
2 Biological Environment
- Impairment of Sensitive
vegetation / other natural
habitats (only for Sub-
project of Plain of Reeds
Primary Canal Upgrading,
which is parallel to the
Tram Chim National Park.)
N-S Temporary
Avoid construction in months of March, April, May when Red head Crane come to Tram Chim National Park
Install fence for canal sections close by Tram Chim National Part with less than 2 km to minimize noise & mitigate impact on Tram Chim National Park‟s buffer zone
Consult to Management Board of Tram Chim National Park
The temporary increase in workers to the construction site will increase the potential for illegal fuel wood and forest product
40
SUBPROJECT
major characteristics
of the subprojects
PROJECT ACTIVITIES
POTENTIAL ADVERSE IMPACTS
Socio-economic and physical/biological aspects
MAGN.
OF
IMPACT
PROPOSED MITIGATION MEASURES
collection and hunting. Mitigation measures will include (a) provision of heating and cooking options without use of fuel wood,(b) provision of environmental training on environmental management issues, (c) environmental protection by guards, capacity building of forest rangers, and imposing fines for illegal activities, and
Do not locate construction camps in close proximity to Tram Chim National Park and train workers not to exploit natural resources & hunting
-Impairment of aquatic flora & fauna downstream
S Adequate temporary toilet facilities with adequate water supply & strict enforcement of proper sanitation
Temporary disposal system for solid & hazardous waste
- Loss of vegetation N
Temporary
None required
3.Socio-Economic Environment
-Traffic congestion S Temporary
Strict enforcement of traffic rules & regulations
Installation of traffic aides in critical routes during peak hours
Coordination of traffic management plan with town & commune officials
Posting of notice on construction schedules & traffic rerouting plan (at least a week prior to effective / implementation dates
- Public inconveniences. disruption of utility services
S Temporary
Traffic mitigation measures (as above)
Temporary access to temporarily affected residences & institutions
Close coordination with relevant utility companies / institutions (water, power, drainage) on proposed alignments, construction phases & schedules
41
SUBPROJECT
major characteristics
of the subprojects
PROJECT ACTIVITIES
POTENTIAL ADVERSE IMPACTS
Socio-economic and physical/biological aspects
MAGN.
OF
IMPACT
PROPOSED MITIGATION MEASURES
- Changed drainage/irrigation affecting farmers
N Canal bottom to be dredged by wet Excavation method. So dredging activities will not affect irrigation /agricultural production
- Disruption of socio-economic activities
S Temporary
Traffic mitigation measures (as above)
Close coordination with relevant utility companies / institutions (water, power, drainage) on proposed alignments, construction phases & schedules
-Health hazard S Temporary
Dust control measures (as above)
Sufficiently high temporary fence around construction sites that is in close proximity to residences & institutions
Use of practicable available technologies that emit least noise & pollutants & adjusting of operational procedures to reduce noise & pollutants
Adequate temporary toilet facilities with adequate water supply
Strict enforcement of proper sanitation
Temporary disposal system for solid & hazardous wastes
- Accidents & safety hazard
S Temporary
Sufficiently high temporary fence around construction sites that are in close proximity to residences & institutions
Disposing of unwanted soils as soon as possible
Temporary disposal system for solid & hazardous wastes
Traffic mitigation measures (as above)
Provisions for adequate lighting, safe pedestrian access, storm drains in construction sites
Efficient emergency / contingency plans, adequate facilities & equipment & trained staff for handling emergencies
+Short-term employment of local population
S Temporary
Local residents should be given priority in employment for simple
42
SUBPROJECT
major characteristics
of the subprojects
PROJECT ACTIVITIES
POTENTIAL ADVERSE IMPACTS
Socio-economic and physical/biological aspects
MAGN.
OF
IMPACT
PROPOSED MITIGATION MEASURES
construction works; therefore their living standard will be improved.
43
Table 20: Subprojects for Building of flood control and salt water intrusion protection Sluices - Construction Phase
SUBPROJECT major
characteristics of new outlet
PROJECT ACTIVITIES
POTENTIAL ADVERSE IMPACTS
Socio-economic and physical/biological aspects
MAGN. OF
IMPACT
PROPOSED MITIGATION MEASURES
Building of flood control and salt water intrusion protection Sluices ( No 3,4) in Tien Giang Province Construct new sluice -Ba Rai-Phu An: 27 sluice -Go Cong area: 3 sluices
Base camp establishment and operation Land clearance Pollution by construction material exploitation activities Earthworks / excavations Haulage of fill and construction materials Effects from temporary storage yards of construction materials Access Road construction Drainage structures
1 Physical / Chemical Environment
Air Quality
- Dust S
Temporary Cover all trucks carrying
dispersible materials to or from the site;
Ensure all construction vehicles and equipment are well-maintained;
Construction activities which can make noise should be carried out at day time
Inform local community about schedule and duration of construction works;
Regarding other material for construction such as sand, stone, contractor should choose legal service providers who had exploitation licenses and environmental protection commitment issued by local authorities;
- Odour S
Temporary
- Noise
S Temporary
Water resources and
quality
- Degeneration /
contamination of surface
water
S Temporary
Diversion drains & bunds, temporary silt traps
ponds
Stockpiling of spoils in flat areas & far from
drainage routes
Disposing of unwanted spoils as soon as possible
Adequate temporary toilet facilities with adequate water supply & strict enforcement of proper sanitation
Temporary disposal system for solid & hazardous waste
- Generation of sewage /
wastewater
S Temporary
Adequate water supply to meet construction needs & setting up of rain catchment tanks
Adequate temporary toilet facilities with adequate water supply & strict enforcement of proper sanitation
- Generation of solid
wastes
S Temporary
Adequate temporary toilet facilities with adequate water supply & strict enforcement of proper sanitation
Discussing with residents to choose the suitable waste dumping site when workers build camps;
Collect solid wastes and
44
SUBPROJECT major
characteristics of new outlet
PROJECT ACTIVITIES
POTENTIAL ADVERSE IMPACTS
Socio-economic and physical/biological aspects
MAGN. OF
IMPACT
PROPOSED MITIGATION MEASURES
temporarily store at a safety place before transporting to disposal sites;
Establish regulations for ensuring sanitation, stipulated dumping yard and waste treatment methods and disseminate those regulations to workers
- Siltation / erosion S Temporary
Install diversion drains & bunds, temporary silt traps/pond
Stockpiling of spoil in flat areas & far from drainage routes
Interruption of water flows,
S Temporary
Setting temporary drainage ditches.
2 Biological Environment
- Impairment of Sensitive
vegetation / other natural
habitats (affect to fish
moving)
S Temporary
Setting temporary construction canal
-Impairment of aquatic
flora & fauna downstream
(degradation of water
quality due to increase of
turbidity )
S Temporary
Adequate temporary toilet facilities with adequate water supply & strict enforcement of proper sanitation
Temporary disposal system for solid & hazardous waste
- Loss of vegetation N
3.Socio-Economic Environment
-Traffic congestion S Temporary
Strict enforcement of traffic rules & regulations
Installation of traffic aides in critical routes during peak hours
Coordination of traffic management plan with town & commune officials Posting of prior notice on construction schedules & traffic rerouting plan (at least a week prior to effective / implementation dates
- Public inconveniences.
disruption of utility services
S Temporary
Traffic mitigation measures (as above)
Temporary access to temporarily affected residences & institutions
Close coordination with relevant utility companies / institutions (water, power, drainage) on proposed alignments, construction
45
SUBPROJECT major
characteristics of new outlet
PROJECT ACTIVITIES
POTENTIAL ADVERSE IMPACTS
Socio-economic and physical/biological aspects
MAGN. OF
IMPACT
PROPOSED MITIGATION MEASURES
phases & schedules
- Changed
drainage/irrigation affecting
farmers
S Temporary
The Contractor should coordinate with irrigation exploitation management enterprise, commune‟s irrigation staff and cultivation households in water supply area of the main canal to reach agreement on water supply duration (construction suspension), construction time (should be implemented at the time when irrigation activities are not done);
Commune‟s irrigation staff, Irrigation management enterprise or relevant authorities should soon inform the households and contractor about water supply schedule so that they can make plan on their own initiative;
- Disruption of socio-
economic activities
S Temporary
Inform fish boat about schedule of construction so that they can make plan on their own initiative;
Close coordination with relevant utility companies / institutions (water, power, drainage) on proposed alignments, construction phases & schedules
-Health hazard S Temporary
Dust control measures (as above)
Use of practicable available technologies that emit least noise & pollutants & adjusting of operational procedures to reduce noise & pollutants
Adequate temporary toilet facilities with adequate water supply
Strict enforcement of proper sanitation
Temporary disposal system for solid & hazardous wastes
- Accidents & safety
hazard
S Temporary
Disposing of unwanted spoils as soon as possible
Temporary disposal system for solid & hazardous wastes
Traffic mitigation measures (as above)
Provisions for adequate lighting, safe pedestrian access, storm drains in construction sites
46
SUBPROJECT major
characteristics of new outlet
PROJECT ACTIVITIES
POTENTIAL ADVERSE IMPACTS
Socio-economic and physical/biological aspects
MAGN. OF
IMPACT
PROPOSED MITIGATION MEASURES
Efficient emergency / contingency plans, adequate facilities & equipment & trained staff for handling emergencies
+Short-term employment
of local population
S Temporary
Local residents should be given priority in employment for simple construction works; therefore their living standard will be improved.
47
Table 21: Subprojects for Bank protection for Thuong Thoi Tien town, Hong Ngu district, Dong Thap province -Construction Phase
SUBPROJECT
major characteristics
of new outlet
PROJECT ACTIVITIES
POTENTIAL ADVERSE IMPACTS
Socio-economic and physical/biological aspects
MAGN.
OF
IMPACT
PROPOSED MITIGATION MEASURES
Bank protection for Thuong Thoi Tien town, Hong Ngu district, Dong Thap province
-Embankment of 3.244 km for Thuong Thoi Tien town,
Base camp establishment and operation
Land clearance
Pollution by construction material exploitation activities
Earthworks / excavations
Haulage of fill and construction materials
Effects from temporary storage yards of construction materials
Access Road construction
Drainage structures
1 Physical / Chemical Environment
Air Quality
- Dust M
Temporary
Regular watering of exposed areas
Cover all trucks carrying dispersible materials to or from the site;
Ensure all construction vehicles and equipment are well-maintained;
Construction activities which can make noise should be carried out at day time
Inform local community about schedule and duration of construction works;
Regarding other material for construction such as sand, stone, contractor should choose legal service providers who had exploitation licenses and environmental protection commitment issued by local authorities;
- Odour S
Temporary
- Noise
S
Temporary
Water resources and quality
- Degeneration / contamination of surface water
S
Temporary
Diversion drains & bunds, temporary silt traps, Ponds;
Stockpiling of spoils in flat areas & far from
drainage routes;
Adequate temporary toilet facilities with adequate water supply & strict enforcement of proper sanitation.
- Generation of sewage / wastewater
S
Temporary
Adequate water supply to meet construction needs & setting up of rain catchment tanks.
Adequate temporary toilet facilities with adequate water supply & strict enforcement of proper sanitation.
- Generation of solid wastes
S
Temporary
Establish temporary latrines which meet regulations of Health
48
SUBPROJECT
major characteristics
of new outlet
PROJECT ACTIVITIES
POTENTIAL ADVERSE IMPACTS
Socio-economic and physical/biological aspects
MAGN.
OF
IMPACT
PROPOSED MITIGATION MEASURES
Ministry and supply enough water to tents;
Discussing with residents to choose the suitable waste dumping site when workers build camps;
Collect solid wastes and temporarily store at a safety place before transporting to disposal sites;
Establish regulations for ensuring sanitation, stipulated dumping yard and waste treatment methods and disseminate those regulations to workers
- Siltation / erosion N
2 Biological Environment
- Impairment of Sensitive vegetation / other natural habitats
N
Temporary
None required
-Impairment of aquatic flora & fauna downstream
N None required
- Loss of vegetation N
Temporary
None required
3.Socio-Economic Environment
-Traffic congestion ( both water and road way)
S
Temporary
Strict enforcement of traffic rules & regulations
Installation of traffic aides in critical routes during peak hours
Coordination of traffic management plan with town & commune officials
Posting of prior notice on construction schedules & traffic rerouting plan (at least a week prior to effective / implementation dates
- Public inconveniences. disruption of utility services
S
Temporary
Traffic mitigation measures (as above)
Temporary access to temporarily affected residences & institutions
Close coordination with relevant utility companies / institutions (water, power, drainage) on proposed alignments, construction phases & schedules
49
SUBPROJECT
major characteristics
of new outlet
PROJECT ACTIVITIES
POTENTIAL ADVERSE IMPACTS
Socio-economic and physical/biological aspects
MAGN.
OF
IMPACT
PROPOSED MITIGATION MEASURES
- Changed drainage/irrigation affecting farmers
N Canal bottom to be dredged by wet Excavation method. So dredging activities will not affect irrigation /agricultural production
- Disruption of socio-economic activities
S
Temporary
Traffic mitigation measures (as above)
Close coordination with relevant utility companies / institutions (water, power, drainage) on proposed alignments, construction phases & schedules
-Health hazard S
Temporary
Dust control measures (as above)
Sufficiently high temporary fence around construction sites that is in close proximity to residences & institutions
Use of practicable available technologies that emit least noise & pollutants & adjusting of operational procedures to reduce noise & pollutants
Adequate temporary toilet facilities with adequate water supply
Strict enforcement of proper sanitation
Temporary disposal system for solid & hazardous wastes
- Accidents & safety hazard
S
Temporary
Sufficiently high temporary fence around construction sites that is in close proximity to residences & institutions
Disposing of unwanted spoils as soon as possible
Temporary disposal system for solid & hazardous wastes
Traffic mitigation measures (as above)
Provisions for adequate lighting, safe pedestrian access, storm drains in construction sites
Efficient emergency / contingency plans, adequate facilities & equipment & trained staff for handling emergencies
+Short-term employment of local population
S
Permanent
Local residents should be given priority in employment for simple
50
SUBPROJECT
major characteristics
of new outlet
PROJECT ACTIVITIES
POTENTIAL ADVERSE IMPACTS
Socio-economic and physical/biological aspects
MAGN.
OF
IMPACT
PROPOSED MITIGATION MEASURES
construction works; therefore their living standard will be improved.
D. Impacts and Mitigation Measures during O&M Phase
113. Negative impacts: Adverse impacts during Operation of the subprojects for Improving and upgrading of flood drainage and irrigation canal system canal system; Subprojects for building of flood control and salt water intrusion protection Sluices; Subproject for Bank protection for Thuong Thoi Tien town, Hong Ngu district, Dong Thap province are presented in Table 22, Table 23 and Table 24
114. Positive impacts: The subprojects will bring socio-economic benefits by Bank erosion prevention for section of Thuong Thoi –Thuong Phuoc -Tien river to protect safety life for communities living along two sides of the river
Decrease of waterborne diseases caused by inundation situation
Promotion of development of tourist, cultural , social-economic sectors in subproject areas
115. In the Tables the following abbreviations are used:
N: not applicable, no adverse effect;
S: small/slight adverse effect;
M: moderate adverse effect;
L: large adverse effect.
51
SUBPROJECT
major characteristics
of new outlet
PROJECT ACTIVITIES
POTENTIAL ADVERSE IMPACTS
Socio-economic and physical/biological aspects
MAGN.
OF
IMPACT
PROPOSED MITIGATION MEASURES
Improving and upgrading of flood drainage and irrigation canal system canal system (No 1,2,5)
-Dredging :
Canal system of Plain of Reeds: 99.3 km
Inadequate operation and maintenance
Erosion river embankment & canal sedimentation
S Provide enough budget and enhance proper operation management and maintenance
Water quality management
Affect on water quality of increasing fertilizer or pesticide use
S Coordinate with Agriculture Extension Centre to ensure that farmers are trained in correct use of fertilizer and pesticides
Apply IPM Program for whole communes in BHH area
Table 22: Subprojects for Improving and upgrading of flood drainage and irrigation canal system canal system - Operation & Maintenance Phase
52
Table 23: Subprojects for Building of flood control and salt water intrusion protection Sluices - Operation & Maintenance Phase
SUBPROJECTS
major characteristics
of new pumping stations (PS)
PROJECT ACTIVITIES
POTENTIAL ADVERSE IMPACTS
Socio-economic and physical/biological aspects
MAGN.
OF
IMPACT
PROPOSED MITIGATION MEASURES
Building of flood control and salt water intrusion protection Sluices in Tien Giang Province
Construct new sluice
-Ba Rai-Phu An: 27 sluice
-Go Cong area: 3 sluices
Operation and maintenance of the Sluices
Long term impact on aesthetics / modification of landscape
S
Proper maintenance of landscaping, trees, plantations.
Inadequate operation and maintenance
Erosion river embankment and water logging locally
S Provide enough budget and enhance proper operation and maintenance
Reduce fishes species number & population in main river in the end of rainy season due to close of sluice gate; but creation of water source for aquaculture sustainably in main river & tributaries
S Coordinate between Irrigation exploitation company and fishery /aquaculture centre to operate sluices how to ensure deep and time for fish delivering
Create aquaculture development in main river & tributaries
Water quality management
For subproject of Salt water intrusion protection system in Go Cong area
Affect on water quality of increasing fertilizer or pesticide use ( only for subproject of Salt water intrusion protection system in Go Cong area
For Sub-project of Flood control system Ba Rai – Phu An
No effects as it is not use fertilizers and pesticides for the Orchard in Ba Rai-Phu An
S
N
Coordinate with Agriculture Extension Centre to ensure that farmers are trained in correct use of fertilizer and pesticides
Apply IPM Program for whole communes in BHH area
53
Table 24: Subprojects for Bank protection for Thuong Thoi Tien town, Hong Ngu district, Dong Thap province - Operation & Maintenance Phase
SUB-PROJECTS
major characteristics
of to be rehabilitated
pumping stations (PS)
PROJECT ACTIVITIES
POTENTIAL ADVERSE IMPACTS
Socio-economic and physical/biological aspects
MAGN.
OF
IMPACT
PROPOSED MITIGATION MEASURES
Bank
protection for
Thuong Thoi
Tien town,
Hong Ngu
district, Dong
Thap province
-Embankment
of 3.244 km
for Thuong
Thoi Tien
town,
Operation and maintenance of Bank protection
Long term impact on aesthetics / modification of landscape
S
Proper maintenance of landscaping, trees, plantations.
Loss of fish delivery „s place S Aquaculture development due to sustainable water supply
54
V. CUMULATIVE EFFECTS
116. There are 4 structural subprojects in Viet Nam that are proposed on improving and upgrading of flood and drought risk management canal and dike system in Lower Mekong River Basin in Viet Nam. The main objectives are: (i) water supply for irrigation and domestic water in dry season, (ii) flood control for Spring-Winter Crops, (iii) to control flood water to secure safe harvesting of Autumn-Summer Crops, (iv) earth excavated from canal to fill the canal banks to control floods and to use as transportation roads or resident areas. Selected sub-projects proposed in the Project have been all included in the list of projects to be invested in the “Revised 2006-2010 Mekong Delta Water Resources Master Plan and the 2020 Vision” issued in line with Decision: 84/2006/QD-TTg, 19 April2006, and in “Viet Nam‟s Water Resources Development Strategic Orientations (to 2020 and its 2050 vision) issued in line with decision 1590/QD-TTg, 9October,2009 or the provincial water resources development master plan in the project area that have been approved by the authorized levels. The implementation of the projects will provide effective contribution to the implementation of the Mekong Delta Water Resources Development Objectives in general and those in Dong Thap Muoi in particular.
117. Currently, several projects are under implementation in Dong Thap Muoi with State budget and Government‟s bonds. Those projects are closely related to the proposed one. The main drainage canals proposed for upgrading and rehabilitation under this Project are mostly located in Tan Thanh – Lo Gach canal (which direction is parallel to the borderline). At present, Tan Thanh – Lo Gach canal is upgraded / rehabilitated with the Government budget. Therefore, if the main canals are upgraded under the proposed Project, this will help to promote the effectiveness of Tan Thanh–Lo Gach project. Main and on-farm irrigation and drainage canals systems in Dong Thap Muoi have been being invested by State Budget and Government Bonds and local contributions. However, those sources have not met the demand and the investment has never been made in a systematic manner. The main canals proposed in the Project are all listed in the list of priorities to be financed with the State Budget after 2015; therefore, the ADB‟s support in upgrading and rehabilitation of this main canal system will help to accelerate the completion of the regional development plan.
118. Water source for irrigation supply under two subprojects Flood control system Ba Rai – Phu An protecting orchard area and Upgrading of Salt water intrusion protection system in Go Cong area in Tien Giang Province will not affect other water users. So, the cumulate effects caused by the project to relative project in the vicinity of project area are likely to be insignificant.
VI. INFORMATION DISCLOSURE, CONSULTATION, AND PARTICIPATION
A. Consultation and Participation Process
119. The public consultation and participation process during the subproject preparation stage will involve the following activities:
Reconnaissance surveys of the Sub-Project site. On-site discussions with district and town commune officials will provide information on the physical and biological resources, social-economic environment, opportunities and constraints relevant to the proposed Sub-Projects.
Participatory meetings with stakeholders and representatives from Provincial IDMC, Sub-Project PPC, DPC, CPC, the Department of Health, and the Women‟s Union Organisation with the objective to collect data and to present the Sub-Projects (designs and locations), the Draft IEE, and to learn about social and environmental issues and concerns.
55
B. Consultation Meetings
2. Schedules and participation
120. The Public Consultation Meetings were organised in Subproject Communes People Committees from 20-25September, 2010. Participants were representatives from the CPO, PMUs, Sub-project Communes People Committees, Sub-project District‟s Environmental Management Division, the Women‟s Union, the farmer union at district, and commune level, and representatives from affected households in Sub-project Communes. Totally, there were 4 Public Consultation Meetings were conducted with 332 participants. Details are provided in Table 25.
Date Time Sub-project Province Districts Communes Meeting location
Number
of participants
20 Sept. 2010
08.00 hrs Thuong Thoi Thuong River Bankment
Dong Thap
Hong Ngu
Thuong Phuoc 2
Commune meeting room
80
22 Sept. 2010
8.00 hrs Improving and upgrading flood control and irrigation canal of the Plain of Reeds
Dong Thap
Tam Nong
Phu Thanh B Commune meeting room
90
23 Sept. 2010
8.00 hrs Upgrading of Salt water intrusion protection system in Go Cong area
Tien Giang
Go Cong town
Long Hoa Commune meeting room
76
24Sept. 2010
8.00 hrs Flood control system Ba Rai – Phu An protecting orchard area
Tien Giang
Cai Lay Hiep Duc Commune meeting room
86
Total 332
121. The objectives of the meeting are to obtain the feedback from the participants on environmental impacts caused by project and their opinion on the project implementation.
122. The following contents have been presented during the meeting:
Subprojects‟ objectives;
Subprojects‟ locations, designs and cost estimates;
GOV & ADB environmental policies and procedures;
Project‟s environmental category per ADB and GOV policies;
Environmental issues per sub-project locations and designs;
Potential environmental impacts caused by each subproject;
Proposed mitigation measures;
Environmental Management Plan & Environmental Monitoring Program;
123. Feedback from Participants
Table 25: List of Sub-project for Public Consultation’s meetings
56
There is general agreement on the construction of the subprojects in the two provinces because the sub projects will prevent land slide and soil erosion along Tien river; Reduce flood water level; Flood drainage; acid sulfate water drainage and fresh water resources reservation;
The Project “public consultation” is highly appreciated because it helps local people in understanding the project content and express their opinions so as to ensure effective implementation of the project;
Consensus is achieved on socio-environmental impacts and mitigation measures recommended by the Project‟;
Mitigation measures in construction period should be studied carefully, especially residential area along proposed dredging canals and river section to be embanked for example, fence should be set-up properly;
Increase of dust & noise level in construction period is considered as small or negligible impacts due to sub-project sites are not in residential areas;
Works progress should be implemented timely, should not be delayed affecting the livelihood of people dwelling along proposed upgrading/ expanded canals;
Construction activities would affect local prawn farming. In order to overcome this issues, It may be replaced with rearing shrimp by planting rice or other crops during construction period;
Regarding water supply, river/canal water is polluted; local people need other source for water supply (drilled well) or storage tank;
Contractors need to hire local people for manual work;
Construction time should be widely informed beforehand to local people to plan agricultural produce & cultivation and to find other transportation way (as main way of transportation is waterway);
Local people wish that Project would improve the irrigation system to wash alum (acid water) from the field to increase rice yields.
Conclusion
There is agreement on the construction of the all Subprojects and desired early construction
Consensus is achieved on socio-environmental impacts and mitigation measures recommended by the Project
124. All comments from participants & stakeholders will be fully considered in mitigation measures of Environmental Assessment & detailed design in next phase.
VII. GRIEVANCE REDRESS MECHANISM
A. Purpose of the Mechanism
125. The grievance redress mechanism is meant for persons seeking satisfactory resolution to their complaints on the environmental performance of the subproject. The mechanism will ensure that: i) the basic rights and interests of every person affected by poor environmental performance of the subproject are protected; and ii) their concerns arising from the poor environmental performance of the subproject during the conduct of pre-construction, construction and operation activities are effectively and timely addressed. B. Access to the Mechanism
126. Any person who has complaint regarding the environmental performance of the subproject during pre-construction, construction and operation phases shall have access to the grievance redress mechanism described in the subsequent section. The CPO and the
57
Environmental Management Unit (EMU) of each of the PMU will nominate and train a staff member to be a Grievance Point Person (GPP).
127. The CPO and PMU through their GPPs shall ensure that:
(i) the grievance redress mechanism and the contact details of the GPPs are
publicly disclosed, and posted in the offices of the affected communes and in strategic places of the Sub-project‟s area of influence;
(ii) the grievance redress mechanism is accessible to all affected villages/communes;
(iii) the public, especially the residents and passers-by in the vicinities of influence of the Sub-project, is aware of their rights to access, and shall have access to, the mechanism free of administrative and legal charges; and
(iv) a registry of grievances received is maintained for reporting to ADB and higher Government authorities on associated follow-up, resolution or non-resolution of issues.
C. The Grievance Redress Mechanism
128. Managing grievances takes a step-by-step process. It requires assigning responsibilities and specifying timelines for prompt responses/actions to grievances to avoid prolonging the misery of affected person/s (AP/s). Grievances raised on environmental impacts are critical to the health and wellness of affected persons. Hence, timelines of responses are critical.
129. Households or groups of households wishing to complain about the effects of construction works on their property, production system, economic well-being, spiritual life, quality of surface and ground water, quality of air, health, safety, welfare, or any other assets of their lives shall make their complaint using the standard Complaints forms provided by the GPPs.
130. The Grievance Investigation and Resolution process is outlined below:
Step 1: Complaint form will be sent by APs, Affected households (AHs) or groups of households to the GPP of the relevant EMU.
Step 2: If the complaint is judged as valid, within 15 days from the date the complaint is received, the relevant EMU will organize meetings with the relevant agencies/contractors/sub contractors to discuss how to resolve the matter. All meetings will be recorded and copies of the minutes of meetings will be provided to APs/AHs.
Step 3: The relevant EMU shall take such mitigation measures as agreed in meetings from step 2 within 15 days, or some other period acceptable to the parties referred to in step 2.
Step 4: When the complaint is resolved, the Complaint Form need to be signed by Complainer/ head of Household, the EMU and annotated at each stage of process by the relevant EMU with copies to be sent to CPO.
Step 5: If no understanding or amicable solution is reached, or if no response is received from the EMU within 15 days after the registration of complaint, the APs/ AHs can appeal to the CPO through their GPP. The APs/AHs must lodge the complaint within 30 days of registering the original complaint and must produce documents with copies of appeal that support his/her claim. The CPO will provide a decision within 1 month of receiving the appeal.
Step 6: When the complaint is resolved, the Complaint Form need to be signed by Complainer/ head of Household, the EMU, the CPO, and annotated at each stage of process by the GPP of the CPO with copies to be sent to ADB.
58
Step 7: If the AP is still not satisfied with the decision of the CPO or in the absence of any response within the stipulated time, the AP as a last resort may submit his/her case to the court, in which decision is final.
VIII. ENVIRONMENTAL MANAGEMENT PLAN
A. Institutional requirements for Environmental Management & Monitoring
131. The Central Project Office (CPO, MARD) will be the executing agency for the Greater Mekong Sub region Flood and Drought Risk Management and Mitigation (GMS) Project in Viet Nam. Two Project Management Units (PMUs) will be established to manage and monitor all day-to-day implementation activities of the Project. The PMU will include representatives from the Agencies and Departments as shown in Table 26.
Table 26: Representatives of two PMUs
PMUs Name of Sub-Project Representatives of agency/departments/organizations
Tien Giang PMU Flood control system Ba Rai – Phu An protecting orchard area
Upgrading of Salt water intrusion protection system in Go Cong area
Tien Giang PPC
Tien Giang IDMC
Other entities involved in managing and implementing the Project.
Dong Thap PMU Improving and upgrading of Plain of Reeds flood drainage and irrigation canal system
Bank erosion protection for Thuong Thoi Tien town, Hong Ngu district, Dong Thap province
Dong Thap PPC
Dong Thap IDMC
The Project‟ DPC & Town PC (Tan Hong, Tam Nong, Thanh Binh districts and Hong Ngu Town)
Other entities involved in managing and implementing the Project.
132. The supervision and monitoring of Project-related resettlement and environmental activities during the pre-construction, construction and operation phases are some of the functions of the PMU. In line with this, it is proposed that a Provincial Environmental Management Unit (PEMU) will be set up within the PMU, responsible for supervision on environmental management and for environmental monitoring. The major responsibilities of the PEMU will be to ensure that:
The mitigation measures and monitoring of these activities are being carried out as agreed.
The environmental monitoring program, comprising of taking samples and analysis being carried out.
Reporting is performed in compliance with ADB and GoV requirements.
133. The EMU shall be headed by qualified staff that is assigned full time to the PMU. At least one full-time technical expert and one full-time administrative staff member shall be assigned to the EMU. The PMU will engage part time a local Environmental Consultant to provide for the EMU technical assistance in environmental management and monitoring.
134. If Project Implementation Assistance (PIA) consultants are employed during implementation of the Project, then the PIA Team‟s Environmental Specialists will pass on
59
expert advice and guidance and conduct capacity building on environmental management and monitoring.
135. To ensure that the ADB environmental requirements and all applicable GoV environmental laws, regulations and standards, are met prior to the start of construction and during construction and operation of the Project, an elaborate Environmental Management and Monitoring Plan should be prepared at the Detailed Design stage based on the concise Environmental Management and Monitoring Plan presented in current IEE. Environmental monitoring during long term operation of the GMS –Viet Nam Sub-Projects is largely the responsibility of Tien Giang Province IDMC, The Project District & Town DPC and TPC
136. The Terms of Reference for the detailed engineering design and the bid documents should specify the preparation of specific Environmental Management and Monitoring Plans for the subprojects, which shall be presented for comments to the stakeholders. B. Environmental Management and Monitoring Plan
137. For the stage of IEE, Tables G.2 to G.4 presents concise Environmental Management and Monitoring Plans (EMPs) for the Greater Mekong Sub region Flood and Drought Risk Management and Mitigation Project in Viet Nam for the various project stages. However, at the stage of Detailed Design detailed EMPs shall be prepared for environmental management – including all required mitigation measures – and monitoring during the different stages of the Sub-Projects. The detailed costs for these environmental management and monitoring activities shall also be calculated at that stage and be incorporated in the various contracts.
138. Responsible for Environmental Monitoring during project implementation are the main contractor, the sub-contractors, the PEMU/PMU, and the communities. The EMPs will be the guiding document for environmental management and monitoring during execution of the Sub-Projects. It will guide the PEMU/PMU in determining whether the recommended mitigation measures prior to construction, and during construction and operation, are being implemented effectively. Environmental monitoring results shall be documented and reviewed to ensure that signs of adverse impacts are detected at an early stage and that actions for mitigation are taken. Monitoring results will have to be reported monthly by the EMU and be submitted to the head of the PMU, who in turn will submit them to DONRE and CPO for approval. The Central Project Office will submit the EMP to the ADB. The format for the monthly and annual Environmental Monitoring Reports will be developed during the Detailed Design Phase and may have to be refined during implementation of the Project.
1. Costs for Environmental Monitoring of resettlement, water quality, air
quality and noise
139. For the costs during the Pre-Construction/Design Phase for implementation and monitoring of the Resettlement Plan (RP) – based on the implementation schedule of the RP – is referred to Resettlement Report.
140. Monitoring, to be carried out by the EMU/PMU, of surface water quality, air quality (TSP) and noise, during the Pre-Construction, Construction and Operation Phases adds up to an average amount of USD108,560 (VDN 2,062,264,000- with rate is 19,000 VND/USD) per subproject. Appendix 1 provides for one subproject the environmental monitoring activities and the costs during the various project phases of the Project. For the whole GMS in Viet Nam Project (11 subprojects) the costs for Environmental Monitoring are estimated at: 7x USD108,560 = USD 759,920.
60
2. Environmental Management and Monitoring for Subprojects for
Improving and upgrading of flood drainage and irrigation canal system
canal system (No 1, 2 and 5)
141. For the stage of IEE, Table 27 present a concise Environmental Management and Monitoring Plan (EMP) for the subprojects for Improving and upgrading of flood drainage and irrigation canal system; Table 28 subprojects for Building of flood control and salt water intrusion protection Sluices; Table 29 subproject for Bank protection for Thuong Thoi Tien town, Hong Ngu district, Dong Thap province.
61
Environmental Impacts
Environmental Management Environmental Monitoring
Socio-economic and
physical/biological aspects
Mitigation Measures
Responsibility Activities Responsibility Costs
Pre-Construction
Land acquisition requirements & displacement of local residents
Prepare Resettlement Plan (RP) based on an agreed resettlement and compensation framework & implement accordingly
PMU and Resettlement Committees (RCs).
Monitoring of implementation of RP, based on implementation schedule of RP.
Review of submitted PMU and RC Progress Reports.
PMU.
EMA (independent external monitoring agency).
For resettlement costs see Resettlement Report.
Displacement of local residents
Proximity to environmentally sensitive areas / areas with aesthetic value
Avoid construction in months of May
when Red head Crane come to Tram Chim National Park
Consult to Management Board of Tram Chim National Park
Consultants doing the design.
flooding / odour / noise
Proper design, O&M; sufficient buffer.
Consultants doing the design.
Monitoring of Technical Design.
MARD Included in cost of Technical Design.
Vulnerability to erosion / landslide
Proper design and O&M
Consultants doing the design.
Monitoring of Technical Design.
MARD Included in cost of Technical Design.
During Construction
1 Physical / Chemical Environment
Air Quality
- Dust
Regular watering of exposed areas
Cover all trucks carrying dispersible materials to or from the site;
Ensure all construction
Contractor Periodic (plus in-between unannounced) inspection of construction activities
Air quality monitoring (quarterly & more
Contractor, PMU, communities; also sub-contractors have responsibility of environmental monitoring.
EMA
Table 27: Environmental Management and Monitoring: Subprojects for Improving and upgrading of flood drainage and irrigation canal system
62
Environmental Impacts
Environmental Management Environmental Monitoring
Socio-economic and
physical/biological aspects
Mitigation Measures
Responsibility Activities Responsibility Costs
vehicles and equipment are well-maintained;
Construction activities which can make noise should be carried out at day time
Inform local community about schedule and duration of construction works;
Regarding other material for construction such as sand, stone, contractor should choose legal service providers who had exploitation licenses and environmental protection commitment issued by local authorities;
frequently when complaints /issues arise)
- Odour
- Noise
Periodic (plus in-between unannounced) inspection of construction activities
Air quality monitoring (quarterly & more frequently when complaints / issues arise)
Contractor, PMU, communities; also sub-contractors have responsibility of environmental monitoring.
EMA
Water resources
and quality
- Degeneration /
contamination of
surface water
( specially water
resources could be
polluted by alum
soil in canal
dredging for Rach
Tram-My Binh
Subproject)
Create drains & bund temporary to avoid spread of polluted alum water from filling & excavated alum soil ,
Diversion drains & bunds, temporary silt traps, ponds
Stockpiling
Contractor Periodic (plus in-between unannounced) inspection of construction activities
Surface water quality monitoring (quarterly & more frequent when complaints /
Contractor, PMU, communities; also sub-contractors have responsibility of environmental monitoring.
EMA
63
Environmental Impacts
Environmental Management Environmental Monitoring
Socio-economic and
physical/biological aspects
Mitigation Measures
Responsibility Activities Responsibility Costs
of spoils in flat areas & far from
drainage routes
Disposing of unwanted spoils as soon as possible
Adequate temporary toilet facilities with adequate water supply & strict enforcement of proper sanitation
Temporary disposal system for solid & hazardous waste
issues arise)
- Generation of
sewage /
wastewater
Adequate water supply to meet construction needs & setting up of rain catchment tanks
Adequate temporary toilet facilities with adequate water supply & strict enforcement of proper sanitation
Contractor
Periodic & unannounced inspections of waste disposal.
Contractor, PMU, communities.
EMA
Incorporated in
Recommended contract provisions.
- Generation of
solid wastes
Establish temporary latrines which meet regulations of Health Ministry and supply enough water to tents;
Discussing with residents to
Contractor
Periodic & unannounced inspections of waste disposal.
Contractor, PMU, communities.
EMA
Incorporated in recommended contract provisions.
64
Environmental Impacts
Environmental Management Environmental Monitoring
Socio-economic and
physical/biological aspects
Mitigation Measures
Responsibility Activities Responsibility Costs
choose the suitable waste dumping site when workers build camps;
Collect solid wastes and temporarily store at a safety place before transporting to disposal sites;
Establish regulations for ensuring sanitation, stipulated dumping yard and waste treatment methods and disseminate those regulations to workers
- Siltation / erosion Install diversion drains & bunds, temporary silt traps/pond
Stockpiling of spoil in flat areas & far from drainage routes
Contractor
Periodic & unannounced inspections of construction activities.
Contractor, PMU, communities.
EMA
Incorporated in recommended contract provisions.
Interruption of water flows,
Setting temporary drainage ditches.
Contractor
Periodic & unannounced inspections of construction activities.
Contractor, PMU, communities.
EMA
Incorporated in recommended contract provisions.
2 Biological Environment
-Impairment of
Sensitive
vegetation / other
natural habitats
( some section of
canal systems in
Avoid construction in months of May
when Red head Crane come to Tram Chim
Contractor
Periodic & unannounced inspections of construction activities.
Contractor,
PMU,
communities.
EMA
Incorporated in
recommended
contract
provisions
65
Environmental Impacts
Environmental Management Environmental Monitoring
Socio-economic and
physical/biological aspects
Mitigation Measures
Responsibility Activities Responsibility Costs
POR close to
Tram Chim
National Park)
National Park
Consult to Management Board of Tram Chim National Park
-Impairment of
aquatic flora &
fauna
downstream
Suitable earthworks & storm water management (No. 5 above)
Disposing of unwanted spoils as soon as possible
Adequate temporary toilet facilities with adequate water supply
Strict enforcement of proper sanitation
Temporary disposal system for solid & hazardous wastes
Contractor
Periodic (plus in-between unannounced) inspection of construction activities
Surface water quality monitoring (quarterly & more frequently when complaints / issues arise)
Contractor, PMU, communities.
EMA
Incorporated in recommended contract provisions.
3.Socio-Economic Environment
-Traffic
congestion
Strict enforcement of traffic rules & regulations
Installation of traffic aids in critical routes during peak hours
Coordination of traffic management plan with town & commune officials
Posting of prior notice on construction
Contractor
Periodic & unannounced inspections of construction activities.
Contractor, PMU, communities.
EMA
Incorporated in recommended contract provisions.
66
Environmental Impacts
Environmental Management Environmental Monitoring
Socio-economic and
physical/biological aspects
Mitigation Measures
Responsibility Activities Responsibility Costs
schedules & traffic rerouting plan (at least a week prior to effective / implementation dates)
- Public
inconveniences,
disruption of
utility services
Traffic mitigation measures (as above)
Temporary access to temporarily affected residences & institutions
Close coordination with relevant utility companies / institutions (water, power, drainage) on proposed alignments, construction phases & schedules
Contractor
Periodic & unannounced inspections of construction activities.
Contractor, PMU, communities.
External Monitoring Agency
(EMA)
- Disruption of
socio-economic
activities
Traffic mitigation measures (as above)
Close coordination with relevant utility companies / institutions (water, power, drainage) on proposed alignments, construction phases & schedules
Contractor
Periodic & unannounced inspections of construction activities.
Contractor, PMU, communities.
External Monitoring Agency
(EMA)
-Health hazard Dust control measures (as above)
Sufficiently
Contractor
Periodic & unannounced inspections of construction activities.
Contractor, PMU, communities.
External Monitoring
67
Environmental Impacts
Environmental Management Environmental Monitoring
Socio-economic and
physical/biological aspects
Mitigation Measures
Responsibility Activities Responsibility Costs
high temporary fence around construction sites that is in close proximity to residences & institutions
Use of practicable available technologies that emit least noise & pollutants & adjusting of operational procedures to reduce noise & pollutants
Adequate temporary toilet facilities with adequate water supply
Strict enforcement of proper sanitation
Temporary disposal system for solid & hazardous wastes
Agency
(EMA)
- Accidents &
safety hazard
Sufficiently high temporary fence around construction sites that is in close proximity to residences & institutions
Disposing of unwanted spoils as soon as possible
Temporary disposal
Contractor
Periodic & unannounced inspections of construction activities.
Contractor, PMU, communities.
External Monitoring Agency
68
Environmental Impacts
Environmental Management Environmental Monitoring
Socio-economic and
physical/biological aspects
Mitigation Measures
Responsibility Activities Responsibility Costs
system for solid & hazardous wastes
Traffic mitigation measures (as above)
Provisions for adequate lighting, safe pedestrian access, storm drains in construction sites
Efficient emergency / contingency plans, adequate facilities & equipment & trained staff for handling emergencies
Operation & Maintenance
Erosion river embankment & canal sedimentation
Provide enough budget and enhance proper operation management and maintenance
Irrigation Exploitation Companies
Periodic & unannounced inspection of precautions and enforcement of regulations.
External Monitoring Agency
Annual administrative costs.
Affect on water quality of increasing fertilizer or pesticide use
Coordinate with Agriculture Extension Centre to ensure that farmers are trained in correct use of fertilizers and pesticides
Apply IPM Program for whole communes in subproject areas
Irrigation Exploitation Companies
Periodic & unannounced inspection of precautions and enforcement of regulations and sampling program.
External Monitoring Agency
Annual administrative costs.
69
Environmental Impacts
Environmental Management Environmental Monitoring
Socio-economic and physical/biological
aspects
Mitigation Measures
Responsibility Activities Responsibility Costs
Pre-Construction
Land acquisition requirements & displacement of local residents
Land acquisition and Resettlement to be not required
It is not required
It is not
required
It is not
required
It is not
required
Displacement of local residents
Proximity to natural habitats
Proper design and O&M of sluices
Consultants doing the design.
Monitoring of Technical Design.
MARD Included in cost of Technical Design.
flooding / odour / noise
Proper design, O&M; sufficient buffer.
Consultants doing the design.
Monitoring of Technical Design.
MARD Included in cost of Technical Design.
Vulnerability to erosion / landslide
Proper design and O&M
Consultants doing the design.
Monitoring of Technical Design.
MARD Included in cost of Technical Design.
Degradation of fisheries
Proper design and O&M of sluices
Consultants doing the design.
Monitoring of Technical Design.
MARD Included in cost of Technical Design.
Degradation of navigation / river transport
Proper design and O&M of sluices
Consultants doing the design.
Monitoring of Technical Design.
MARD Included in cost of Technical Design.
During Construction
1 Physical / Chemical Environment
Air Quality
- Dust
Cover all trucks carrying dispersible materials to or from the site;
Ensure all construction vehicles and equipment are well-maintained;
Construction activities which can make noise should be carried out at day time
Inform local
Contractor Periodic (plus in-between unannounced) inspection of construction activities
Air quality monitoring (quarterly & more frequent when complaints / issues arise)
Contractor, PMU, communities; also sub-contractors have responsibility of environmental monitoring.
EMA
- Odour
- Noise Periodic
(plus in-
Contractor, PMU,
Table 28: Environmental Management and Monitoring: Subprojects for Building of flood control and salt water intrusion protection Sluices
70
Environmental Impacts
Environmental Management Environmental Monitoring
Socio-economic and physical/biological
aspects
Mitigation Measures
Responsibility Activities Responsibility Costs
community about schedule and duration of construction works;
Regarding other material for construction such as sand, stone, contractor should choose legal service providers who had exploitation licenses and environmental protection commitment issued by local authorities;
between unannounced) inspection of construction activities
Air quality monitoring (quarterly & more frequent when complaints / issues arise)
communities; also sub-contractors have responsibility of environmental monitoring.
EMA
Water resources
and quality
- Degeneration /
contamination of
surface water
( specially water
resources could be
polluted by alum
soil in canal
dredging for Rach
Tram-My Binh
Subproject)
Create drains & bund temporary to avoid spread of polluted alum water from filling & excavated alum soil ,
Diversion drains & bunds, temporary silt traps
ponds
Stockpiling of spoils in flat areas & far from drainage routes
Disposing of unwanted spoils as soon as possible
Adequate
Contractor Periodic (plus in-between unannounced) inspection of construction activities
Surface water quality monitoring (quarterly & more frequent when complaints / issues arise)
Contractor, PMU, communities; also sub-contractors have responsibility of environmental monitoring.
EMA
71
Environmental Impacts
Environmental Management Environmental Monitoring
Socio-economic and physical/biological
aspects
Mitigation Measures
Responsibility Activities Responsibility Costs
temporary toilet facilities with adequate water supply & strict enforcement of proper sanitation
Temporary disposal system for solid & hazardous waste
- Generation of
sewage /
wastewater
Adequate water supply to meet construction needs & setting up of rain catchment tanks
Adequate temporary toilet facilities with adequate water supply & strict enforcement of proper sanitation
Contractor
Periodic & unannounced inspections of waste disposal.
Contractor, PMU, communities.
EMA
Incorporated in
recommended
Contract provisions.
- Generation of
solid wastes
Establish temporary toilet which meet regulations of Health Ministry and supply enough water to tents;
Discussing with residents to choose the suitable waste dumping site when workers build
Contractor
Periodic & unannounced inspections of waste disposal.
Contractor, PMU, communities.
EMA
Incorporated in
recommended
Contract provisions.
72
Environmental Impacts
Environmental Management Environmental Monitoring
Socio-economic and physical/biological
aspects
Mitigation Measures
Responsibility Activities Responsibility Costs
camps;
Collect solid wastes and temporarily store at a safety place before transporting to disposal sites;
Establish regulations for ensuring sanitation, stipulated dumping yard and waste treatment methods and disseminate those regulations to workers
- Siltation / erosion Install diversion drains & bunds, temporary silt traps/pond
Stockpiling of spoil in flat areas & far from drainage routes
Contractor
Periodic & unannounced inspections of construction activities.
Contractor, PMU, communities.
EMA
Incorporated in
recommended
Contract provisions.
Interruption of water flows,
Setting temporary drainage ditches.
Contractor
Periodic & unannounced inspections of construction activities.
Contractor, PMU, communities.
EMA
Incorporated in
recommended
Contract provisions.
2 Biological Environment
- Impairment of
Sensitive vegetation
/ other natural
habitats (affect to
fish moving)
Setting temporary construction canal
Contractor
Periodic & unannounced inspections of construction activities.
Contractor,
PMU,
communities.
EMA
Incorporated in
recommended
contract
provisions
-Impairment of
aquatic flora &
fauna downstream
(degradation of
Adequate temporary toilet facilities with adequate water supply & strict
Contractor
Periodic (plus in-between unannounced)
Contractor, PMU, communities.
EMA
Incorporated in recommended contract provisions.
73
Environmental Impacts
Environmental Management Environmental Monitoring
Socio-economic and physical/biological
aspects
Mitigation Measures
Responsibility Activities Responsibility Costs
water quality due to
increase of turbidity
)
enforcement of proper sanitation
Temporary disposal system for solid & hazardous waste
inspection of construction activities
Surface water quality monitoring (quarterly & more frequent when complaints / issues arise)
3.Socio-Economic Environment
-Traffic congestion Strict enforcement of traffic rules & regulations
Installation of traffic aides in critical routes during peak hours
Coordination of traffic management plan with town & commune officials
Posting of prior notice on construction schedules & traffic rerouting plan (at least a week prior to effective / implementation dates)
Contractor
Periodic & unannounced inspections of construction activities.
Contractor, PMU, communities.
EMA
Incorporated in recommended contract provisions.
- Public
inconveniences,
disruption of utility
services
Traffic mitigation measures (as above)
Temporary access to temporarily affected residences & institutions
Close coordination with relevant utility companies / institutions (water, power,
Contractor
Periodic & unannounced inspections of construction activities.
Contractor, PMU, communities.
External Monitoring Agency
(EMA)
74
Environmental Impacts
Environmental Management Environmental Monitoring
Socio-economic and physical/biological
aspects
Mitigation Measures
Responsibility Activities Responsibility Costs
drainage) on proposed alignments, construction phases & schedules
-Changed
drainage/irrigation
affecting farmers
The Contractor should coordinate with irrigation exploitation management enterprise, commune‟s irrigation staff and cultivation households in water supply area of the main canal to reach agreement on water supply duration (construction suspension), construction time (should be implemented at the time when irrigation activities are not done);
Commune‟s irrigation staff, Irrigation management enterprise or relevant authorities should inform the households and contractor about water supply schedule so that they can make plan on their own initiative;
Contractor
Periodic & unannounced inspections of construction activities.
Contractor, PMU, communities.
External Monitoring Agency
(EMA)
- Disruption of
socio-economic
activities
Inform fish boat about schedule of construction so that they can make plan
Contractor
Periodic & unannounced inspections of construction activities.
Contractor, PMU, communities.
External Monitoring Agency
75
Environmental Impacts
Environmental Management Environmental Monitoring
Socio-economic and physical/biological
aspects
Mitigation Measures
Responsibility Activities Responsibility Costs
on their own initiative;
Close coordination with relevant utility companies / institutions (water, power, drainage) on proposed alignments, construction phases & schedules
(EMA)
-Health hazard Dust control measures (as above)
Use of practicable available technologies that emit least noise & pollutants & adjusting of operational procedures to reduce noise & pollutants
Adequate temporary toilet facilities with adequate water supply
Strict enforcement of proper sanitation
Temporary disposal system for solid & hazardous wastes
Contractor
Periodic & unannounced inspections of construction activities.
Contractor, PMU, communities.
External Monitoring Agency
(EMA)
- Accidents & safety
hazard
Disposing of unwanted spoils as soon as possible
Temporary disposal system for solid & hazardous wastes
Traffic mitigation measures (as
Contractor
Periodic & unannounced inspections of construction activities.
Contractor, PMU, communities.
External Monitoring Agency
76
Environmental Impacts
Environmental Management Environmental Monitoring
Socio-economic and physical/biological
aspects
Mitigation Measures
Responsibility Activities Responsibility Costs
above)
Provisions for adequate lighting, safe pedestrian access, storm drains in construction sites
Efficient emergency / contingency plans, adequate facilities & equipment & trained staff for handling emergencies
Operation & Maintenance
Long term impact on aesthetics / modification of landscape
Provide enough budget and enhance proper operation and maintenance
Irrigation Exploitation Companies
Periodic & unannounced inspection of precautions and enforcement of regulations.
External Monitoring Agency
Annual administrative costs.
Erosion river embankment and water logging locally
Coordinate between Irrigation exploitation company and fishery /aquaculture centre to operate sluices how to ensure water deep and time for fish delivering
Create aquaculture development in main river & tributaries
Irrigation Exploitation Companies
Periodic & unannounced inspection of precautions and enforcement of regulations and sampling program.
External Monitoring Agency
Annual administrative costs.
Reduce fishes species number & population in main river in the end of rainy season due to closing of sluice gate; but creation of water source for aquaculture sustainably in main
Coordinate with Agriculture Extension Centre to ensure that farmers are trained in correct use of fertilizer and pesticides
Irrigation Exploitation Companies
77
Environmental Impacts
Environmental Management Environmental Monitoring
Socio-economic and physical/biological
aspects
Mitigation Measures
Responsibility Activities Responsibility Costs
river & tributaries
Apply IPM Program for whole communes in subproject area
Environmental Impacts
Environmental Management Environmental Monitoring
Socio-economic and
physical/biological aspects
Mitigation Measures
Responsibility Activities Responsibility Costs
Pre-Construction
Land acquisition requirements & displacement of local residents
Prepare Resettlement Plan (RP) based on an agreed resettlement and compensation framework & implement accordingly
PMU and Resettlement Committees (RCs).
Monitoring of implementation of RP, based on implementation schedule of RP.
Review of submitted PMU and RC Progress Reports.
PMU.
EMA (independent external monitoring agency).
For resettlement costs see Resettlement Report. Displacement of
local residents
flooding / odour / noise
Proper design, O&M; sufficient buffer.
Consultants doing the design.
Monitoring of Technical Design.
MARD Included in cost of Technical Design.
Vulnerability to erosion / landslide
Proper design and O&M
Consultants doing the design.
Monitoring of Technical Design.
MARD Included in cost of Technical Design.
During Construction
1 Physical / Chemical Environment
Air Quality
Table 29: Environmental Management and Monitoring: Subprojects for Bank protection for Thuong Thoi Tien town, Hong Ngu district, Dong Thap province
78
Environmental Impacts
Environmental Management Environmental Monitoring
Socio-economic and
physical/biological aspects
Mitigation Measures
Responsibility Activities Responsibility Costs
- Dust
Regular watering of exposed areas
Cover all trucks carrying dispersible materials to or from the site;
Ensure all construction vehicles and equipment are well-maintained;
Construction activities which can make noise should be carried out at day time
Inform local community about schedule and duration of construction works;
Regarding other material for construction such as sand, stone, contractor should choose legal service providers who had exploitation licenses and environmental protection commitment issued by local authorities;
Contractor Periodic (plus in-between unannounced) inspection of construction activities
Air quality monitoring (quarterly & more frequent when complaints / issues arise)
Contractor, PMU, communities; also sub-contractors have responsibility of environmental monitoring.
EMA
- Odour
- Noise
Periodic (plus in-between unannounced) inspection of construction activities
Air quality monitoring (quarterly & more frequent when complaints / issues arise)
Contractor, PMU, communities; also sub-contractors have responsibility of environmental monitoring.
EMA
Water resources
and quality
- Degeneration /
contamination of
surface water
Diversion drains & bunds, temporary silt traps
Contractor Periodic (plus in-between unannounced)
Contractor, PMU, communities; also sub-contractors
79
Environmental Impacts
Environmental Management Environmental Monitoring
Socio-economic and
physical/biological aspects
Mitigation Measures
Responsibility Activities Responsibility Costs
ponds
Stockpiling of spoils in flat areas & far from
drainage routes
Adequate temporary toilet facilities with adequate water supply & strict enforcement of proper sanitation
inspection of construction activities
Surface water quality monitoring (quarterly & more frequent when complaints / issues arise)
have responsibility of environmental monitoring.
EMA
- Generation of
sewage /
wastewater
Adequate water supply to meet construction needs & setting up of rain catchment tanks
Adequate temporary toilet facilities with adequate water supply & strict enforcement of proper sanitation
Contractor
Periodic & unannounced inspections of waste disposal.
Contractor, PMU, communities.
EMA
Incorporated in
recommended
Contract provisions.
- Generation of
solid wastes
Establish temporary latrines which meet regulations of Health Ministry and supply enough water to tents;
Discussing with residents to choose the suitable waste dumping site when workers build camps;
Collect solid
Contractor
Periodic & unannounced inspections of waste disposal.
Contractor, PMU, communities.
EMA
Incorporated in
recommended
Contract provisions.
80
Environmental Impacts
Environmental Management Environmental Monitoring
Socio-economic and
physical/biological aspects
Mitigation Measures
Responsibility Activities Responsibility Costs
wastes and temporarily store at a safety place before transporting to disposal sites;
Establish regulations for ensuring sanitation, stipulated dumping yard and waste treatment methods and disseminate those regulations to workers
2 Biological Environment
-Impairment of
Sensitive
vegetation / other
natural habitats
It is not required It is not
required
It is not
required
It is not
required
It is not
required
-Impairment of
aquatic flora &
fauna downstream
It is not required It is not
required
It is not
required
It is not
required
It is not
required
3.Socio-Economic Environment
-Traffic congestion Strict enforcement of traffic rules & regulations
Installation of traffic aides in critical routes during peak hours
Coordination of traffic management plan with town & commune officials
Posting of prior notice on construction schedules & traffic rerouting plan (at least a
Contractor
Periodic & unannounced inspections of construction activities.
Contractor, PMU, communities.
EMA
Incorporated in
recommended
Contract provisions.
81
Environmental Impacts
Environmental Management Environmental Monitoring
Socio-economic and
physical/biological aspects
Mitigation Measures
Responsibility Activities Responsibility Costs
week prior to effective / implementation dates)
- Public
inconveniences,
disruption of utility
services
Traffic mitigation measures (as above)
Temporary access to temporarily affected residences & institutions
Close coordination with relevant utility companies / institutions (water, power, drainage) on proposed alignments, construction phases & schedules
Contractor
Periodic & unannounced inspections of construction activities.
Contractor, PMU, communities.
External Monitoring Agency
(EMA)
- Disruption of
socio-economic
activities
Traffic mitigation measures (as above)
Close coordination with relevant utility companies / institutions (water, power, drainage) on proposed alignments, construction phases & schedules
Contractor
Periodic & unannounced inspections of construction activities.
Contractor, PMU, communities.
External Monitoring Agency
(EMA)
-Health hazard Dust control measures (as above)
Sufficiently high temporary fence around construction sites that is in close proximity to residences & institutions
Use of practicable available technologies
Contractor
Periodic & unannounced inspections of construction activities.
Contractor, PMU, communities.
External Monitoring Agency
(EMA)
82
Environmental Impacts
Environmental Management Environmental Monitoring
Socio-economic and
physical/biological aspects
Mitigation Measures
Responsibility Activities Responsibility Costs
that emit least noise & pollutants & adjusting of operational procedures to reduce noise & pollutants
Adequate temporary toilet facilities with adequate water supply
Strict enforcement of proper sanitation
Temporary disposal system for solid & hazardous wastes
- Accidents &
safety hazard
Sufficiently high temporary fence around construction sites that is in close proximity to residences & institutions
Disposing of unwanted spoils as soon as possible
Temporary disposal system for solid & hazardous wastes
Traffic mitigation measures (as above)
Provisions for adequate lighting, safe pedestrian access, storm drains in construction sites
Efficient emergency / contingency plans, adequate facilities &
Contractor
Periodic & unannounced inspections of construction activities.
Contractor, PMU, communities.
External Monitoring Agency
83
Environmental Impacts
Environmental Management Environmental Monitoring
Socio-economic and
physical/biological aspects
Mitigation Measures
Responsibility Activities Responsibility Costs
equipment & trained staff for handling emergencies
Operation & Maintenance
Long term impact on aesthetics / modification of landscape
Proper maintenance of landscaping, trees, plantations.
Irrigation Exploitation Companies
Periodic & unannounced inspection of precautions and enforcement of regulations.
External Monitoring Agency
Annual administrative costs.
Loss of fish delivery „s place
Aquaculture development due to sustainable water supply
Irrigation Exploitation Companies
Periodic & unannounced inspection of precautions and enforcement of regulations and sampling program.
External Monitoring Agency
Annual administrative costs.
IX. CONCLUSION AND RECOMMENDATION
A. Objectives and Positive impacts
142. The objective of the Greater Mekong Sub region Flood and Drought Risk Management and Mitigation Project in Viet Nam is to improve flood discharge capacity in flood season and reservation of fresh water resources as well for irrigation, local economy, especially in dry season for towns and cities by constructing new sluices and upgrading of existing drainage and irrigation systems, erosion bank protection.
143. Therefore, the realisation of GMS Flood and Drought Risk Management and Mitigation Project in Viet Nam will bring significant positive impacts on irrigation and drainage canal system in Tien Giang and Dong Thap Provinces; Thuong Thoi and Hong Ngu Town by increased flood discharge capacity and water supply for irrigation, river dike protection. Improving of flood drainage capacity can resolve completely inundation situation in the subproject Districts in Dong Thap Provinces, by then hygiene-sanitary condition will improve accordingly. B. Negative impacts
144. Screening of potential environmental impacts for the Design Phases, the Construction Phases and the Operation & Maintenance Phases of the subprojects also revealed adverse effects. However, all identified adverse impacts appeared to be of small or moderate level and many are of temporary in nature during construction phase. No significant adverse environmental impacts are expected. Mitigation measures have been formulated and that can diminish the adverse impacts (Part E) and concise Environmental Management and Monitoring Plans (EMPs) have been developed for the subprojects (Part I). More detailed EMPs have to be prepared during the Design Phase to control and mitigate identified small and moderate negative environmental impacts.
84
C. Recommendations
145. The executed Initial Environmental Examination (IEE) for the Project is sufficient according to the ADB environmental guidelines and regulations. Only additional detailed Environmental Management and Monitoring Plans have to be prepared to control and mitigate the identified small and moderate adverse environmental impacts. However, because only The subproject No.6 “Bank erosion protection for Thuong Thoi Tien town, Hong Ngu district, Dong Thap province” with total length of Bank protection of 3.224km long in the Mekong river, more than 1.0km, a full Environmental Impact Assessment (EIA) is required according to the environmental regulations of the Government of Viet Nam (Decree No.21/2008/ND-CP- River and sea embankment projects with 1000m or more in length need preparation of EIA). At the present feasibility phase and Project Preparatory Technical Assistance (PPTA) stage of the Project the IEE is sufficient. The EIA will have to be carried out after completion and approval of the Feasibility Study Report and prior to obtaining the construction permit. The EIA will be carried out by national consultants. Supervision and approval will be provided by Dong Thap DONRE. D. Conclusion
146. From the proposed subprojects for Tien Giang and Dong Thap, only small and moderate adverse environmental impacts are expected. These adverse impacts can be mitigated by proper design, specific mitigations measures, and by adequate operation & maintenance. For these reasons the executed Initial Environmental Examination (IEE) for the subprojects is sufficient, which in accordance with the ADB environmental guidelines and regulations. However, because only The subproject on “Bank erosion protection for Thuong Thoi Tien town, Hong Ngu district, Dong Thap province” with total length of Bank protection of 3.224 km long in the Mekong river, is more than 1.0 km, a full Environmental Impact Assessment (EIA) is required according to the environmental regulations of the Government of Viet Nam. At present i.e. at the feasibility and PPTA stage of the Project the prepared IEE is sufficient. The full EIA will have to be carried out after completion and approval of the Feasibility Study Report and prior to obtaining the construction permit.
X. REFERENCES
1. Safeguard Policy Statement, June 2009. 2. Environment Policy of the Asian Development Bank, November 2002. 3. Environmental Assessment Guidelines, Asian Development Bank, 2003. 4. Environmental Guidelines for Selected Agricultural and Natural Resources Projects,
Asian Development Bank, November 1991. 5. Decree 21/2008/ND-CP, Part I Legal Documents, 5, Article 11.2b. 6. Feasibility Study of the Subprojects. 7. Standard QCVN 08:2008/BTNMT: National Technical Regulation on Surface Water
Quality for water for domestic use, irrigation and for water ways and navigation. 8. Standard QCVN 09:2008/BTNMT: National Technical Regulation on underground
water. 9. Standard QCVN 05:2009/BTNMT: National technical regulation on ambient air quality 10. TCVN 5949: 1998: Noise in public and residential areas Maximum permitted noise
level. 11. Standard TCVN 6774:2000: Fresh-water quality guidelines for the protection of
aquatic life. 12. Report on Status of Environment of Tien Giang and Dong Thap Provinces in -2009 13. TCVN-5944-2005 – Viet Namese Standard for ground water. 14. QCVN-2008 – National Technical Regulations on Environment. 15. Provincial Statistical Yearbook 2009.
87
Annex 1-Preliminary Cost Estimates for Environmental monitoring: one year-01 Subproject
Cost Item No of
Engineer Man
month No. of
Months
Frequency in a Year
(monthly)
No of Samples
or
No of Taking
Sample‟s People
Total No of Sample or
Car rent day
No of working
days
Unit Rate
(USD)
Total Cost
(USD)
PRE-CONSTRUCTION
A EMU-PPMU
A.1
Irrigation Engineer
(1 for full time for a year) 0 0
300
A.2 Monitoring Activities
A.2.1 Measuring or Analysis
- Air Quality & Noise Level 1
One time before
construction
5 80 400
- Surface Water Quality 1 10 110 1110
-Ground Water Quality
A.2.2 Taking & Handling Samples
Per Diem:
- Air Quality & Noise Level 1 2 2 30 60
- Surface Water Quality 1 3 2 30 60
-Ground Water Quality
Transport:
- Air Quality & Noise Level 1 1 100 100
- Surface Water Quality 1 1 100 100
A2.3 Boat rent 20 20
A2.4 Report (Result of Environmental Monitoring)
1
120 120
Sub-Total 1(Pre- Construction)
2270
DURING CONSTRUCTION
A Consultants
A.1 International Environmental Specialist
(part of PIA Team - TA Grant, 4 mos. Intermittently for a
88
Cost Item No of
Engineer Man
month No. of
Months
Frequency in a Year
(monthly)
No of Samples
or
No of Taking
Sample‟s People
Total No of Sample or
Car rent day
No of working
days
Unit Rate
(USD)
Total Cost
(USD)
year)
A.2 Local Environmental Specialist
(part of PIA Team - TA Grant, 6 mos. intermittently for a year)
B EMU-PPMU
B.1
Irrigation Engineer
(6 months for a year)
1 6 6
500
3000
B.2 Monitoring Activities
B.2.1
Measuring or Analysis
- Air Quality & Noise Level
12 12 5
60 80 4800
- Surface Water Quality
12 12 10
120 110 13200
-Ground water
B.2.2 Taking & Handling Samples
Per Diem:
- Air Quality & Noise Level
12 12 2
2x12 30 720
- Surface Water Quality
12 12 3
2x12 30 720
-Ground water
Transport:
- Air Quality & Noise Level
12 12 1 1
12 100 1200
- Surface Water Quality
12 12 3
1
12
100 1200
B.2.3 Boat rent 12 20 240
B.2.4
Report (Result of Environmental
12 120 1440
89
Cost Item No of
Engineer Man
month No. of
Months
Frequency in a Year
(monthly)
No of Samples
or
No of Taking
Sample‟s People
Total No of Sample or
Car rent day
No of working
days
Unit Rate
(USD)
Total Cost
(USD)
Monitoring)
Sub-Total 2(During Construction)
26520 USD
DURING OPERATION
B Environmental Monitoring Staff
B1 Irrigation Engineer/Environmentalist
1
3
(part time)
500 1500
B2 Monitoring Activities
B2.1
Measuring or Analysis
- Surface Water Quality
4 10 40 110 4440
- Ground Water Quality
B2 .2
Taking & Handling Samples
Per Diem:
- Air Quality & Noise Level
- Surface Water Quality
4 3
12 30 360
-Ground water
Transport:
- Air Quality & Noise Level
- Surface Water Quality
4 1 2 daysx
4
100
800
-Ground water
B 2.3 Boat Rent
B 24
Report (Result of Environmental
4 120 480
90
Cost Item No of
Engineer Man
month No. of
Months
Frequency in a Year
(monthly)
No of Samples
or
No of Taking
Sample‟s People
Total No of Sample or
Car rent day
No of working
days
Unit Rate
(USD)
Total Cost
(USD)
Monitoring)
Sub-Total 3 (During Operation)
6080 USD
Total (1)+(2)+(3)
91
Estimated Cost for Environmental Management Plan of the Proposed Component Unit 103 VND
Exchange rate VND/US$: 19000
Frequency Responsibility
Agencies
Before Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Amount without
TAX-USD
Amount (with VAT) +10%
Environmental Monitoring VND USD
Pre-Construction
Air quality/TSP One time before construction
(Baseline data
Contractor
Sub-Contractor
PMU
Communities
2270
USD
Noise
Water Quality
To clear the ground
Sub-Total 1
During Construction 26520
USD
26520
USD
26520
USD
Monthly Contractor
Communities
Air quality (TSP & Noise) Monthly
Water quality Monthly
Sub-Total 2
Operation
Water quality Monthly IDMC
Communities
6080
USD
6080
USD
Sub-Total 3
Total 1+2+3 93990
Contingency 4700
98690 108,559
USD
Around 108,560
USD
Note: TSP & Noise is measured at Site – Measurement Cost based on Circular 83/2002/TT-BTC Water quality sample is taken at Site & analyzed in Laboratory- based on Circular 83/2002/TT-BTC Perdiem based on Circular 23/2007/TT-BTC – Transportation cost based on Current Vehicle transportation price
Average amount for one subproject = 108,560 USD Total estimate cost for 4 subprojects = 434,240 USD
92
Annex 2: Cost estimation of water quality analysis for one sample
No Criteria Unit Price VND according to
Circular 83/2002/TT-BTC
1 T Sample
2 pH Sample 30.000
3 DO Sample 60.000
4 Turbidity Sample 50.000
5 EC Sample 40.000
6 SS Sample 50.000
7 Cl Sample 50.000
8 SO4-- Sample 50.000
9 Ca Sample 60.000
10 Mg Sample 60.000
11 Fe Sample 60.000
12 NO2- Sample 50.000
13 NO3- Sample 50.000
14 NH4+ Sample 60.000
15 PO4 3- Sample 60.000
16 COD Sample 70.000
17 BOD5 Sample 80.000
18 Faecal Coliform Sample 60.000
19 Coliform Sample 60.000
20 As Sample 80.000
21 Pb Sample 60.000
22 Hg Sample 80.000
23 Cd Sample 60.000
24 Cr6+ Sample 60.000
25
Pesticides-organic
Cl / Potassium Sample 600.000
Total VND 1940000
USD 110
93
Annex 3: Rapid Environmental Assessment (ADB, REA)
Checklist Irrigation /Drainage SubProjects-GMS Project in Viet Nam
Instructions:
This checklist is to be prepared to support the environmental classification of a project. It is to be
attached to the environmental categorization form that is to be prepared and submitted to the Chief
Compliance Officer of the Regional and Sustainable Development Department.
This checklist is to be completed with the assistance of an Environment Specialist in a Regional
Department.
This checklist focuses on environmental issues and concerns. To ensure that social dimensions are
adequately considered, refer also to ADB checklists and handbooks on (i) involuntary resettlement, (ii)
indigenous peoples planning, (iii) poverty reduction, (iv) participation, and (v) gender and development.
Answer the questions assuming the “without mitigation” case. The purpose is to identify potential
impacts. Use the “remarks” section to discuss any anticipated mitigation measures.
Country/Project Title: The Greater Mekong Sub region Flood and Drought Risk Management
and Mitigation (GMS) Project in Viet Nam
SCREENING QUESTIONS Yes No REMARKS
A. Project Sitting
Is the Project area adjacent to or within any of the
following environmentally sensitive areas?
protected area x
wetland x
mangrove x
estuarine x
buffer zone of protected area x
special area for protecting biodiversity x
B. Potential Environmental Impacts
Will the Project cause…
loss of precious ecological values (e.g. result of
encroachment into forests/swamp lands or
historical/cultural buildings/areas, disruption of hydrology
of natural waterways, regional flooding, and drainage
hazards)?
x
conflicts in water supply rights and related social
Conflicts?
x
Impediments to movements of people and animals? x
potential ecological problems due to increased soil
erosion and siltation, leading to decreased stream
capacity?
x
insufficient drainage leading to salinity intrusion? x
over pumping of groundwater, leading to salinisation
and ground subsidence?
x
impairment of downstream water quality and therefore,
impairment of downstream beneficial uses of water?
x
dislocation or involuntary resettlement of people? x 39 households will be
94
SCREENING QUESTIONS Yes No REMARKS
affected.
potential social conflicts arising from land tenure and
land use issues?
x
soil erosion before compaction and lining of canals? x
noise from construction equipment? x Noise will be generated from
construction equipment
during the construction
phase.
dust? x Dust will be generated
during the construction
phase.
labour-related social problems, especially if
workers from different areas are hired?
x normally, workers from the
local area are hired.
water logging and soil salinisation due to inadequate
drainage and farm management?
x locally, water logging is
expected during the
construction phase.
leaching of soil nutrients and changes in soil
characteristics due to excessive application of irrigation
water?
x
reduction of downstream water supply during peak
seasons?
x
soil pollution, polluted farm runoff and groundwater,
and public health risks due to excessive application of
fertilizers and pesticides?
x
soil erosion (furrow, surface)? x Locally. some erosion is
expected.
scouring of canals? x
clogging of canals by sediments? x
clogging of canals by weeds? x
seawater intrusion into downstream freshwater
systems?
x
introduction of increase in incidence of waterborne or
water related diseases?
x
95
ANNEX 4: NOTES OF THE PUBLIC CONSULTATION MEETING
List of Subproject for Public Consultation’s meetings
Date Time Subproject Province Districts Communes Meeting location
Number
of participants
20 Sept. 2010
08.00 hrs Thuong Thoi Thuong River Bankment
Dong Thap
Hong Ngu Thuong Phuoc 2
Commune meeting room
82
22 Sept. 2010
8.00 hrs Improving and upgrading flood control and irrigation canal of the Plain of Reeds
Dong Thap
Tam Nong Phu Thanh B
Commune meeting room
90
23 Sept. 2010
8.00 hrs Go Cong Tien Giang
Go Cong town
Long Hoa Commune meeting room
76
24 Sept. 2010
8.00 hrs Cai Lay Tien Giang
Cai Lay Hiep Duc Commune meeting room
86
Total 334
1. Objectives of the Workshop
To inform the stakeholders the Project information, findings and proposed mitigating
measures as indicated in the IEE;
To receive comments from beneficiaries and affected peoples, local officials, community leaders, NGOs/ Societies, and others;
Ensure community consensus for project implementation & information disclosure to local
people with precisely;
2. Disclosed information
Subprojects‟ objectives;
Subprojects‟ locations, designs & cost estimates;
GOV & ADB environmental policies & procedures;
Project‟s environmental category per ADB & GoV policies;
Environmental issues per subproject locations & designs;
Potential environmental impacts caused by each subproject;
Proposed mitigation measures;
Environmental Management Plan & Environmental Monitoring Program;
3. Meeting Participants
Each subproject Commune, the participants expected to attend the meeting are:
Local authorities: representatives of district and commune PCs, representatives of Viet Nam Woman Union, Public Health, Environment Division at District & Commune level, representatives of local communities.
Representatives of project affected people (PAP) to ensure they are meaningfully involved in the public consultation. PAPs representatives including affected by environmental impacts both direct and indirect negative impacts.
96
Total of participants for one subproject: 80-90 people
4. Meeting Agenda (each meeting)
Duration for presentation
(minutes)
Content Presented by
5 Welcome CPC
10 Introduction of the Project & sub-project Nguyen Thi Loan
Environmental Consultant-VISION RI
30 Brief presentations on the sub-projects/ADB safeguard policy/potential impacts & mitigation measures
Nguyen Thi Loan
Environmental Consultant-VISION RI
60 Discussion on environmental issues & potential impacts & mitigation measures & monitoring of mitigation measure implementation, especially public participation in environmental monitoring
All participants
5 Wrap-up & Closing Consultants
(Note: In all meetings, Environmental, social and community-based disaster risk management
consultations were combined)
5. General Comments from Participants of all sub-project’s Public Consultation Meetings The comments from the participants can be summarised as follows:
There is general agreement on the construction of the Sub-projects in the three provinces because the sub-projects will prevent land slide and soil erosion along Tien river; Reduce flood water level; Flood drainage; acid sulfate water drainage and fresh water resources reservation;
The Project “public consultation” is highly appreciated because it helps local people in understanding the project content and express their opinions so as to ensure effective implementation of the project;
Consensus is achieved on socio-environmental impacts and mitigation measures recommended by the Project;
Mitigation measures in construction period should be studied carefully , especially for residential area along proposed new and upgrading canals, for example, fence should be set-up properly;
Increase of dust & noise level in construction period is considered as small or negligible impacts due to sub-project sites are not in residential areas;
Works progress should be implemented timely, should not be delayed affecting the livelihood of people dwelling along proposed upgrading/ expanded canals;
Construction activities would affect local prawn farming. In order to overcome this issues, It may be replaced with rearing shrimp by planting rice or other crops during construction period
Regarding water supply, river/canal water is polluted; local people need other source for water supply (drilled well) or storage tank.
Contractors need to hire local people for manual work.
Construction time should be widely informed beforehand to local people to plan agricultural produce & cultivation and to find other transportation way (as main way of transportation is waterway)
Local people wish that Project would improve the irrigation system to wash alum (acid water) from the field to increase rice yields
97
Conclusion
There is agreement on the construction of the all Sub-projects and desired early construction
Consensus is achieved on socio-environmental impacts and mitigation measures recommended by the Project
All comments from participants & stakeholders will be fully considered in mitigation measures of
Environmental Assessment & detailed design in next phase
Participant‟s Comments of each sub-projects see bellow Table “Summary of Public Consultation
Reports “
6. Comments from Participants of the sub-project‟s Public Consultation Meetings
98
Summary of Public Consultation Reports (8)
Sub-project Province Name
of
District
Name of
Commune
Number of
participants
Suggestions/ Comments
Embankment
of Tien River
for soil
erosion
control in
Thuong Thoi
Tien
Dong
Thap
Hong
Ngu
Thuong
Phuoc 2
80 Comments
Construction activities may affect the fish population, project need to support fishery people that are about 800 households.
Local people are living mainly by fishing (because they do not have land for agricultural activities)
During operation no adverse effect occurs
The commune is not affected by soil acidity.
Contractors need to hire local workers
People want to know how the acquired land and houses are compensated
Since water supply for local people is taken directly from the Mekong River without treatment, constructors must not discharge domestic and construction wastewater into the river to ensure water quality for the people
How houses and trees in the eroded locations are dealt with?
The embankments of Tien river shall affect the electricity station of pumping irrigation system, which irrigate paddy rice
Contractors should quickly finish construction to avoid affecting the travel of local people.
Construction activities will affect agricultural activities
Conclusion
All negative impacts are
negligible and easily mitigated
Agreed on mitigation
measures
Agreed on the sub-project
construction and desired early
construction
Improving
and
upgrading
Dong
Thap
Tam
Nong
Phu
Thanh B
76 Comments
Construction activities will affect local prawn farming. In order to overcome this issues,
Sub-project Province Name
of
District
Name of
Commune
Number of
participants
Suggestions/ Comments
flood control
and irrigation
canal of the
Plain of
Reeds
It may be replaced by rearing shrimp by planting rice or other crops during construction period
Construction activities would affect local drinking water supply, project needs to provide water storage tanks for local people
There are not many issues on the management of outside people coming for work, because every year (March-July) about 500-700 Viet Namese coming for rice harvest. Thus, local authorities are quite familiar with the management.
Change the labour practices in the absence of the shrimp harvest by planting crops, do not catch birds in the park
Suggest to hire locals in the construction process because the abundant labour resources
After the project, the irrigation system will be improved, flood will be controlled and 3 crops/year can be made
Conclusions
Agreed on mitigation
measures
Agreed on the sub-project
construction and desired early
construction
Upgrading of
Salt water
intrusion
protection
system in Go
Cong area
Tien
Giang
Go
Cong
Long Hoa 76 Comments
Agree with mitigation
measures recommended by
the project consultant
Increase of dust & noise level
in construction period is
considered as small impact
Construction in rainy days
would increase the possibility
of accidents because of wet
soil, piles of material causing
fall down, electrical accidents,
sinking land
Transportation of construction
material may cause traffic
jams and traffic accidents
Contractors should hire local
labor for manual work
Conclusion
Agreed on mitigation
100
Sub-project Province Name
of
District
Name of
Commune
Number of
participants
Suggestions/ Comments
measures
Agreed on the sub-project
construction and desired early
construction
Flood
Control
System for
Bai Rai –
Phu An
Orchards in
Cai Lay and
Cai Be
Districts,
Tien
Giang
Cai
Lay
Hiep Duc 86 Existing environmental condition
The dredging would not affect
water quality because the
canal system is connected
People have no comment on
the time the contractor's work
Contractors should hire local
labour for manual work
Sources of income of local
people come primarily from
fruits, not from fisheries, thus
dredging canals would not
affect income sources of local
people
The transportation by waterway
during the construction phase is not
affected (as local people can go by
other way)
Conclusion:
Agreed on mitigation
measures
Agreed on the sub-project
construction and desired early
101
7. Pictures and List of Participants in Public Consultation Meetings
7.1 Dong Thap
Public Consultation Meeting in Thuong Phuoc 2 commune, Hong Ngu District (20/ Sep, 2010)
Public Consultation Meeting at Phu Thanh B commune, Tam Nong district, Dong
Thap province 22 Sep 2010
a. Tien Giang
Public Consultation Meeting at Long Hoa Commune, Go Cong District Tien Giang Province 23 Sep 2010
103
Lists of Participants in Public Consultation Meetings
1. Meetings in Dong Thap Public consultation in Thuong Phuoc 2 commune, Hong Ngu district, Dong Thap province
106
2. Meeting in Tien Giang Public consultation in Long Hoa commune, Go Cong town, Tien Giang province
108
List of Bird species in Tram Chim National Park (up to May, 2007)
TT Scientific name
Common name
Viet Nam name
IUCN Red-
list 2006
Viet-nam
Red Data
Bok
Decre
e 32 CITES
ANSERIFORMES
Dendrocygnidae
1 Dendrocygna javanica Lesser Whistling-duck Le nâu
Anatidae
2 Anser anser Greylag Goose Ngỗng trời
3 Tadorna tadorna Common Shelduck Vịt khoang
4 Cairina scutulata White-winged Duck Ngan cánh trắng EN V IIB I
5 Sarkidiornis melanotos Comb Duck Vịt mồng
6 Nettapus coromandelianus Cotton Pygmy-goose Le khoang cổ T
7 Anas penelope Eurasian Wigeon Vịt đầu vàng
8 Anas poecilorhyncha Spot-billed Duck Vịt trời
9 Anas clypeata Northern Shoveler Vịt mỏ thìa
10 Anas acuta Northern Pintail Vịt mốc
11 Anas querquedula Garganey Mồng két mày trắng
12 Anas crecca Common Teal Mồng két
TURNICIFORMES
Turnicidae
13 Turnix sylvatica Small Buttonquail Cun cút nhỏ
14 Turnix tanki Yellow-legged Buttonquail Cun cút lưng hung
PICIFORMES
Picidae
15 Jynx torquilla Eurasian Wryneck Vẹo cổ
Megalaimidae
16 Megalaima haemacephala Coppersmith Barbet Cu rốc cổ đỏ
17 Calorhamphus fuliginosus Brown Barbet
CORACIIFORMES
Coraciidae
109
TT Scientific name
Common name
Viet Nam name
IUCN Red-
list 2006
Viet-nam
Red Data
Bok
Decre
e 32 CITES
18 Coracias benghalensis Indian Roller Sả rừng
19 Eurystomus orientalis Dollarbird Yểng quạ
Alcedinidae
20 Alcedo atthis Common Kingfisher Bồng chanh
21 Alcedo meninting Blue-eared Kingfisher Bồng chanh tai xanh
Halcyonidae
22 Halcyon capensis Stork-billed Kingfisher Sả mỏ rộng T
23 Halcyon smyrnensis White-throated Kingfisher Sả đầu nâu
24 Halcyon pileata Black-capped Kingfisher Sả đầu đen
25 Todiramphus chloris KingfisherCollared Sả khoang cổ, Chẽo chẹt
Cerylidae
26 Megaceryle lugubris Crested Kingfisher Bói cá lớn T
27 Ceryle rudis Pied Kingfisher Bói cá nhỏ
Meropidae
28 Merops orientalis Green Bee-eater Trảu đầu hung
29 Merops viridis Blue-throated Bee-eater Trảu họng xanh
30 Merops philippinus Blue-tailed Bee-eater Trảu họng vàng
31 Merops leschenaulti Chestnut-headed Bee-eater Trảu họng vàng
CUCULIFORMES
Cuculidae
32 Cacomantis merulinus Plaintive Cuckoo Tìm vịt
33 Chrysococcyx maculatus Asian Emerald Cuckoo Tìm vịt xanh
34 Eudynamys scolopacea Asian Koel Tu hú
35 Phaenicophaeus tristis Green-billed Malkoha Phướn, Coọc
Centropodidae
36 Centropus sinensis Greater Coucal Bìm bịp lớn
37 Centropus bengalensis Lesser Coucal Bìm bịp nhỏ
APODIFORMES
Apodidae
38 Cypsiurus balasiensis Asian Palm Swift Yến cọ
110
TT Scientific name
Common name
Viet Nam name
IUCN Red-
list 2006
Viet-nam
Red Data
Bok
Decre
e 32 CITES
39 Apus affinis House Swift Yến cằm trắng
STRIGIFORMES
Tytonidae
40 Tyto capensis Grass Owl Cú lợn lưng nâu IIB II
Caprimulgidae
41 Caprimulgus macrurus Large-tailed Nightjar Cú muỗi đuôi dài, Chim
ục II
COLUMBIFORMES
Columbidae
42 Columba livia Rock Pigeon Gầm ghì đá
43 Streptopelia orientalis Oriental Turtle Dove Cu sen
44 Streptopelia chinensis Spotted Dove Cu gáy, Cu đất
45 Streptopelia tranquebarica Red Collared Dove Cu ngói
46 Macropygia unchall Barred Cuckoo Dove Gầm ghì vằn
47 Treron vernans Pink-necked Green Pigeon Cu xanh đầu xám
GRUIFORMES
Otididae
48 Houbaropsis bengalensis Bengal Florican Ô tác, Công đất, Công
sấm EN V IIB I
Gruidae
49 Grus antigone Sarus Crane Sếu cổ trụi, Sếu đầu đỏ VU V II
Rallidae
50 Gallirallus striatus Slaty-breasted Rail Gà nước vằn, Chàng
nghịch
51 Amaurornis phoenicurus White-breasted Waterhen Cuốc ngực trắng
52 Porzana pusilla Baillon's Crake Cuốc lùn
53 Porzana fusca Ruddy-breasted Crake Cuốc ngực nâu
54 Porzana cinerea White-browed Crake Cuốc mày trắng, Võ vẽ
55 Gallicrex cinerea Watercock Gà đồng, Cúm núm
56 Porphyrio porphyrio Purple Swamphen Xít, Trích, Trích cồ
111
TT Scientific name
Common name
Viet Nam name
IUCN Red-
list 2006
Viet-nam
Red Data
Bok
Decre
e 32 CITES
57 Gallinula chloropus Common Moorhen Kịch, Trích ré
58 Fulica atra Common Coot Sâm cầm
CICONIIFORMES
Scolopacidae
59 Gallinago stenura Pintail Snipe Rẽ giun Á châu
60 Gallinago gallinago Common Snipe Rẽ giun
61 Limosa limosa Black-tailed Godwit Choắt mỏ thẳng đuôi đen
62 Limosa lapponica Bar-tailed Godwit Choắt mỏ thẳng đuôi vằn
63 Tringa erythropus Spotted Redshank Choắt chân đỏ
64 Tringa totanus Common Redshank Choắt nâu
65 Tringa stagnatilis Marsh Sandpiper Choắt đốm đen
66 Tringa nebularia Common Greenshank Choắt lớn
67 Tringa ochropus Green Sandpiper Choắt bụng trắng
68 Tringa glareola Wood Sandpiper Choắt bụng xám
69 Actitis hypoleucos Common Sandpiper Choắt nhỏ
70 Calidris temminckii Temminck's Stint Rẽ lưng đen
71 Calidris subminuta Long-toed Stint Rẽ ngón dài
72 Calidris ferruginea Curlew Sandpiper Rẽ bụng nâu
Rostratulidae
73 Rostratula benghalensis Greater Painted-snipe Nhát hoa
Jacanidae
74 Hydrophasianus chirurgus Pheasant-tailed Jacana Gà lôi nước
75 Metopidius indicus Bronze-winged Jacana Gà lôi nước Ấn Độ
Charadriidae
76 Himantopus himantopus Black-winged Stilt Cà kheo
77 Pluvialis fulva Pacific Golden Plover Choi choi vàng
78 Pluvialis dominicus American Golden Plover
79 Charadrius dubius Little Ringed Plover Choi choi nhỏ
80 Charadrius alexandrinus Kentish Plover Choi choi khoang cổ
81 Charadrius peronii Malaysian Plover Choi choi lưng đen LR
112
TT Scientific name
Common name
Viet Nam name
IUCN Red-
list 2006
Viet-nam
Red Data
Bok
Decre
e 32 CITES
82 Vanellus duvaucelii River Lapwing Te cựa
83 Vanellus cinereus Grey-headed Lapwing Te vàng, Te te hoạch
84 Vanellus indicus Red-wattled Lapwing Te vặt
Glareolidae
85 Dromas ardeola Crab-plover
86 Glareola maldivarum Oriental Pratincole Dô nách nâu, Óc cau
87 Glareola lactea Small Pratincole Dô nách xám
Laridae
88 Larus argentatus Herring Gull Mòng bể chân vàng
89 Gelochelidon nilotica Gull-billed Tern Nhàn chân đen
90 Sterna caspia Caspian Tern Nhàn Caxpia
91 Sterna hirundo Common Tern Nhàn
92 Chlidonias hybridus Whiskered Tern Nhàn đen
Accipitridae
93 Pandion haliaetus Osprey Ó cá II
94 Aviceda jerdoni Jerdon's Baza Diều hoa Jerdon
95 Aviceda leuphotes Black Baza Diều mào II
96 Elanus caeruleus Black-shouldered Kite Diều trắng
97 Milvus migrans Black Kite Diều hâu
98 Haliastur indus Brahminy Kite Diều lửa II
99 Circus aeruginosus Eurasian Marsh Harrier Diều đầu trắng II
100 Circus cyaneus Hen Harrier Diều Hen
101 Circus melanoleucos Pied Harrier Diều mướp II
102 Accipiter badius Shikra Ưng xám II
103 Accipiter gularis Japanese Sparrowhawk Ưng Nhật Bản
104 Buteo buteo Common Buzzard Diều Nhật Bản
105 Aquila clanga Greater Spotted Eagle Đại bàng đen VU II
Falconidae
106 Falco tinnunculus Common Kestrel Cắt lưng hung II
107 Falco amurensis Amur Falcon Cắt Amur
113
TT Scientific name
Common name
Viet Nam name
IUCN Red-
list 2006
Viet-nam
Red Data
Bok
Decre
e 32 CITES
108 Falco peregrinus Peregrine Falcon Cắt lớn I
Podicipedidae
109 Tachybaptus ruficollis Little Grebe Le hôi
Anhingidae
110 Anhinga melanogaster Darter Cổ rắn, Điêng điểng LR
Phalacrocoracidae
111 Phalacrocorax niger Little Cormorant Cốc đen, Còng cọc
112 Phalacrocorax fuscicollis Indian Cormorant Cốc đế nhỏ
113 Phalacrocorax carbo Great Cormorant Cốc đế, Bạc má R
Ardeidae
114 Egretta garzetta Little Egret Cò trắng
115 Egretta eulophotes Chinese Egret Cò trắng Trung Quốc VU
116 Ardea cinerea Grey Heron Diệc xám
117 Ardea sumatrana Great-billed Heron Diệc Xumatra
118 Ardea purpurea Purple Heron Diệc lửa
119 Casmerodius albus Great Egret Cò ngàng lớn
120 Mesophoyx intermedia Intermediate Egret Cò ngàng nhỏ
121 Bubulcus ibis Cattle Egret Cò ruồi
122 Ardeola bacchus Chinese Pond Heron Cò bợ
123 Ardeola speciosa Javan Pond Heron Cò bợ Java
124 Butorides striatus Little Heron Cò xanh
125 Nycticorax nycticorax Black-crowned Night Heron Vạc
126 Ixobrychus sinensis Yellow Bittern Cò lửa lùn
127 Ixobrychus cinnamomeus Cinnamon Bittern Cò lửa
128 Dupetor flavicollis Black Bittern Cò hương
129 Botaurus stellaris Great Bittern Vạc rạ
Threskiornithidae
130 Plegadis falcinellus Glossy Ibis Quắm đen
131 Threskiornis melanocephalus Black-headed Ibis Cò quăm đầu đen LR
132 Platalea minor Black-faced Spoonbill Cò thìa EN R IB
114
TT Scientific name
Common name
Viet Nam name
IUCN Red-
list 2006
Viet-nam
Red Data
Bok
Decre
e 32 CITES
Pelecanidae
133 Pelecanus philippensis Spot-billed Pelican Bồ nông chân xám VU R
Ciconiidae
134 Mycteria leucocephala Painted Stork Cò lạo Ấn Độ, Giang sen LR R
135 Anastomus oscitans Asian Openbill Cò nhạn, Cò ốc R
136 Ephippiorhynchus asiaticus Black-necked Stork Cò Á châu E
137 Leptoptilos javanicus Lesser Adjutant Già đẫy Java, Già sói VU R IB
138 Leptoptilos dubius Greater Adjutant Già đẫy lớn EN E
PASSERIFORMES
Pardalotidae
139 Gerygone sulphurea Golden-bellied Gerygone Chích bụng vàng
Laniidae
140 Lanius tigrinus Tiger Shrike Bách thanh vằn
141 Lanius cristatus Brown Shrike Bách thanh mày trắng
142 Lanius schach Long-tailed Shrike Bách thanh đầu đen
Corvidae
143 Crypsirina temia Racket-tailed Treepie Chim khách
144 Oriolus chinensis Black-naped Oriole Vàng anh Trung Quốc
145 Coracina macei Large Cuckooshrike Phường chèo xám lớn
146 Coracina polioptera Indochinese Cuckooshrike Phường chèo xám nhỏ
147 Coracina melaschistos Black-winged Cuckooshrike Phường chèo xám
148 Hemipus picatus Bar-winged Flycatcher-
shrike
Phường chèo đen
149 Rhipidura albicollis White-throated Fantail Rẻ quạt họng trắng
150 Rhipidura javanica Pied Fantail Rẻ quạt Java
151 Dicrurus macrocercus Black Drongo Chèo bẻo
152 Dicrurus annectans Crow-billed Drongo Chèo bẻo mỏ quạ
153 Dicrurus aeneus Bronzed Drongo Chèo bẻo rừng
154 Dicrurus hottentottus Spangled Drongo Chèo bẻo bờm
155 Aegithina tiphia Common Iora Chim nghệ ngực vàng
115
TT Scientific name
Common name
Viet Nam name
IUCN Red-
list 2006
Viet-nam
Red Data
Bok
Decre
e 32 CITES
156 Tephrodornis gularis Large Woodshrike Phường chèo nâu
157 Tephrodornis pondicerianus Common Woodshrike Phường chèo nâu mày
trắng
Muscicapidae
158 Monticola solitarius Blue Rock Thrush Hoét đá
159 Brachypteryx montana White-browed Shortwing Hoét đuôi cụt xanh
160 Muscicapa dauurica Asian Brown Flycatcher Đớp ruồi nâu
161 Ficedula mugimaki Mugimaki Flycatcher Đớp ruồi Mugi
162 Ficedula parva Red-throated Flycatcher Đớp ruồi họng đỏ
163 Ficedula dumetoria Rufous-chested Flycatcher Đớp ruôi mặt hung
164 Niltava macgrigoriae Small Niltava Đớp ruồi trán đen
165 Culicicapa ceylonensis Grey-headed Canary
Flycatcher
Đớp ruồi đầu xám
166 Luscinia svecica Bluethroat Oanh cổ xanh
167 Luscinia cyane Siberian Blue Robin Oanh lưng xanh
168 Copsychus saularis Oriental Magpie Robin Chích chòe than
169 Copsychus malabaricus White-rumped Shama Chích chòe lửa IIB
170 Saxicola torquata Common Stonechat Sẻ bụi đầu đen
171 Saxicola caprata Pied Bushchat Sẻ bụi đen
172 Saxicola ferrea Grey Bushchat Sẻ bụi xám
Sturnidae
173 Sturnus malabaricus Chestnut-tailed Starling Sáo đá đuôi hung
174 Sturnus burmannicus Vinous-breasted Starling Sáo sậu đầu trắng
Hirundinidae
175 Riparia riparia Sand Martin Nhạn nâu xám
176 Riparia paludicola Plain Martin Nhạn nâu đỏ
177 Hirundo rustica Barn Swallow Nhạn bụng trắng
178 Hirundo tahitica Pacific Swallow Nhạn đuôi đen
179 Hirundo daurica Red-rumped Swallow Nhạn bụng xám
180 Delichon urbica Northern House Martin Nhạn hông trắng Xibêri
116
TT Scientific name
Common name
Viet Nam name
IUCN Red-
list 2006
Viet-nam
Red Data
Bok
Decre
e 32 CITES
Pycnonotidae
181 Pycnonotus goiavier Yellow-vented Bulbul Bông lau mày trắng
182 Pycnonotus blanfordi Streak-eared Bulbul Bông lau tai vằn
183 Pycnonotus brunneus Red-eyed Bulbul
184 Hypsipetes leucocephalus Black Bulbul Cành cạch đen
Cisticolidae
185 Cisticola juncidis Zitting Cisticola Chiền chiện đồng hung
186 Prinia polychroa Brown Prinia Chiền chiện núi
187 Prinia rufescens Rufescent Prinia Chiền chiện đầu nâu
188 Prinia hodgsonii Grey-breasted Prinia Chiền chiện lưng xám
189 Prinia flaviventris Yellow-bellied Prinia Chiền chiện bụng vàng
190 Prinia inornata Plain Prinia Chiền chiện bụng hung
Zosteropidae
191 Zosterops palpebrosus Oriental White-eye Vành khuyên họng vàng
192 Zosterops japonicus Japanese White-eye Vành khuyên Nhật Bản
Sylviidae
193 Bradypterus thoracicus Spotted Bush Warbler Chích họng vạch
194 Locustella lanceolata Lanceolated Warbler Chích đầm lầy nhỏ
195 Locustella certhiola Rusty-rumped Warbler Chích đầm lầy lớn
196 Acrocephalus bistrigiceps Black-browed Reed
Warbler
Chích đầu nhọn mày đen
197 Acrocephalus orientalis Oriental Reed Warbler Chích đầu nhọn Phương
Đông
198 Acrocephalus aedon Thick-billed Warbler Chích mỏ rộng
199 Orthotomus sutorius Common Tailorbird Chích đuôi dài
200 Phylloscopus fuscatus Dusky Warbler Chim Chích nâu
201 Phylloscopus inornatus Yellow-browed Warbler Chích mày lớn
202 Phylloscopus borealis Arctic Warbler Chích Phương Bắc
203 Abroscopus superciliaris Yellow-bellied Warbler Chích đớp ruồi mỏ vàng
204 Megalurus palustris Striated Grassbird Chiền chiện lớn
117
TT Scientific name
Common name
Viet Nam name
IUCN Red-
list 2006
Viet-nam
Red Data
Bok
Decre
e 32 CITES
205 Macronous gularis Striped Tit Babbler Chích chạch má vàng
Alaudidae
206 Mirafra assamica Rufous-winged Bushlark Sơn ca Thái Lan
207 Alauda gulgula Oriental Skylark Sơn ca
Nectariniidae
208 Dicaeum cruentatum Scarlet-backed
Flowerpecker
Chim sâu lưng đỏ
209 Anthreptes malacensis Brown-throated Sunbird Hút mật họng nâu
210 Nectarinia jugularis Olive-backed Sunbird Hút mật họng tím
Passeridae
211 Passer flaveolus Plain-backed Sparrow Sẻ bụi vàng
212 Passer montanus Eurasian Tree Sparrow Sẻ
213 Motacilla alba White Wagtail Chìa vôi trắng
214 Motacilla citreola Citrine Wagtail Chìa vôi đầu vàng
215 Motacilla flava Yellow Wagtail Chìa vôi vàng
216 Motacilla cinerea Grey Wagtail Chìa vôi núi
217 Anthus richardi Richard's Pipit Chim manh lớn
218 Anthus rufulus Paddyfield Pipit
219 Anthus hodgsoni Olive-backed Pipit Chim manh Vân Nam
220 Anthus cervinus Red-throated Pipit Chim manh họng đỏ
221 Ploceus manyar Streaked Weaver Rồng rộc đen
222 Ploceus philippinus Baya Weaver Rồng rộc
223 Ploceus hypoxanthus Asian Golden Weaver Rồng rộc vàng LR
224 Amandava amandava Red Avadavat Mai hoa
225 Erythrura prasina Pin-tailed Parrotfinch Di xanh
226 Lonchura striata White-rumped Munia Di cam
227 Lonchura punctulata Scaly-breasted Munia Di đá
228 Lonchura malacca Black-headed Munia Di đầu đen
Fringillidae
229 Carpodacus rubescens Blanford's Rosefinch
118
TT Scientific name
Common name
Viet Nam name
IUCN Red-
list 2006
Viet-nam
Red Data
Bok
Decre
e 32 CITES
230 Carpodacus erythrinus Common Rosefinch Sẻ hồng mura
231 Emberiza aureola Yellow-breasted Bunting Sẻ đồng ngực vàng LR
Conservation status:
- IUCN Redlist 2006: LR: globally near-threatened (low risk) species, VU: globally threatened (vulnerable) species, EN: globally threatened (endangered) species
- Viet Nam Red Data Book: R: nationally rare species, T: nationally threatened species, V: nationally vulnerable species, E: endangered.
- Decree 32 of the Viet Namese Government (2006): IIB: species listed on the Appendix IIB
- CITES Convention: Appendix I and II