Project Description
-
Upload
khangminh22 -
Category
Documents
-
view
4 -
download
0
Transcript of Project Description
Detailed Environmental Impact Assessment for the Proposed Reclamation for the Development of Oil and Gas Industrial Base at Kg. Rancha-Rancha, Labuan, F.T., Malaysia
Chapter 2 Project Description
Chemsain Konsultant Sdn. Bhd.
CK/EV403-4176/12
Page C2-1
Project Description
2.1 Introduction
This chapter gives detailed description on the proposed Project which includes the project
location, project concept; project option; as well as the project activities involved.
As mentioned in Chapter 1, this Project involves two (2) sites, i.e. 1) the reclamation site,
where proposed reclamation and capital dredging in near vicinity to attain the required
draft; and 2) the proposed sand borrow site, where sand materials will be extracted and
transported to the reclamation site. Throughout this detailed EIA report, these two sites will
be referred to as the “reclamation site” and the “sand borrow site”.
2.2 Project Location
Reclamation Site
The reclamation site is located at the south western side of Labuan Island at Rancha-
Rancha Industrial area, approximately 3 km from Labuan City and 20 km from Menumbok,
Sabah. The proposed reclamation site covers an area of 200 acres/ 89 hectares. See an
overall view of the reclamation site in Plate 2.1. The project location is illustrated in Figure
2.2.1.
The site is presently accessible via Jalan Patau-Patau, which is the main road connecting
Labuan city to the southern Rancha-Rancha area.
Plate 2.1: Part of the reclamation site viewed from land
The approximate coordinates of the proposed reclamation site boundaries are shown in
Table 2.2.1 and illustrated in Figure 2.2.1.
Chapter
2
Detailed Environmental Impact Assessment for the Proposed Reclamation for the Development of Oil and Gas Industrial Base at Kg. Rancha-Rancha, Labuan, F.T., Malaysia
Chapter 2 Project Description
Chemsain Konsultant Sdn. Bhd.
CK/EV403-4176/12
Page C2-4
has obtained DEIA approval from DOE. Refer to Appendix 2.2.1 for the relevant
correspondence.
2.3 Project Concept
The main concept of the Project is sea reclamation of a total area of 200 acres/ 89
hectares for the eventual development of an oil and gas industrial base at Kg. Rancha-
Rancha, Labuan. The types of industries to be set up at the reclaimed area proposed are
such as warehouse storage, transportation depot area, petrochemical industries, etc. As
per the present design, the desired finished platform level of the area to be reclaimed is
designed at 3.3 m A.M.S.L. The estimated filling material required is 8 million cubic meters
and this shall be sourced from a sand borrow site offshore of Labuan. The existing water
depth varies from 0 to 7 m at the reclamation site, hence capital dredging at the
reclamation site is required to allow the barges and dredgers to manoeuvre and carry out
the required dredging works. The dredged material has been estimated to be about 9
million cubic meters.
The concept of the proposed Project is in line with the Labuan Draft Master Development
Plan 2030, whereby the vicinity of the proposed reclamation site are all proposed to be
reclaimed and developed as an industrial area. See draft master development plan in
Figure 1.7.1. In order to achieve the overall planning of the proposed development plan,
this reclamation project together with the associated capital dredging and sand borrow
activities was initiated.
2.4 Project Implementation Schedule
The Project is expected to commence in May 2014 and shall be undertaken within a
period of three years (36 months). It is anticipated that the Project will be completed in May
2017. This project implementation period covers the mobilisation of equipment to the
completion of the Project, whereby the reclamation site is ready to be occupied by
industries. The tentative implementation schedule is shown in Table 2.4.1.
Table 2.4.1: Tentative Implementation Schedule
Activity Component Duration
• Mobilization of Equipment, workers 1 to 2 months
• Capital Dredging 8 months
• Construction of temporary bund/ rock revetment 4 months
Reclamation
Stage
• Sand Source Dredging
• Raising of the dredged material to surface and
overflow
• Transportation
• Reclamation
22 months
Detailed Environmental Impact Assessment for the Proposed Reclamation for the Development of Oil and Gas Industrial Base at Kg. Rancha-Rancha, Labuan, F.T., Malaysia
Chapter 2 Project Description
Chemsain Konsultant Sdn. Bhd.
CK/EV403-4176/12
Page C2-5
Activity Component Duration
Post-Reclamation
Stage
• Ground settling 3 months
2.5 Project Option
2.5.1 Project Siting
Given the limited size of Labuan Island, the location of the reclamation site is considered to
the best available on the following basis:
� The reclamation site is located within Rancha-Rancha Industrial area, which is in
line with the Labuan Draft Master Development Plan 2030.
� There are well established infrastructures and utilities such as road network,
electricity supply, water supply and telecommunication services at Rancha-Rancha
Industrial area. The Project will only require an extension of these existing
infrastructures and utilities.
� The proposed development of the reclaimed area is also to meet the demand of the
expanding oil and gas industries. This need arises also due to the necessity to
generate growth in the country's industrialisation programme.
The location of the sand borrow site, on the other hand is considered to be the best
available site based on the key findings from a hydraulic report1 conducted back in 1998
titled:. In the report, two (2) sand source locations were identified, compared and
assessed.
1 Coastal Hydraulic Modeling Study: Intergrated Port at Rancha-Rancha Wilayah Persekutuan Sabah by Dr Nik &
Associates
Detailed Environmental Impact Assessment for the Proposed Reclamation for the Development of Oil and Gas Industrial Base at Kg. Rancha-Rancha, Labuan, F.T., Malaysia
Chapter 2 Project Description
Chemsain Konsultant Sdn. Bhd.
CK/EV403-4176/12
Page C2-6
Figure 2.5.1: Sand Borrow Locations
The table below summarises the two (2) sand borrow sites.
Sand Borrow A Sand Borrow B
Distance 9 km southeast of
reclamation site
2 km south of Pulau Daat
7 km southeast of
reclamation site
6km southwest of Pulau
Daat
Sediment Sample Analysis Mainly contain medium
sand
Less than 10% of sand
fraction (mostly silt and clay)
Sediment Plume during
dredging operation
Extent of sediment plume
with concentration >10 g/m3
is localized (within 250 m)
Extent of sediment plume
with concentration > 10 g/m3
is localized (within 250 m)
Impact on current
conditions
The impact on current
condition is small (<0.05
m/s), with slight reduction in
current speed
The impact on current
condition is <0.02 m/s,
which is deemed minimal
The hydraulic study summarises that:
• Sand borrow A contained mainly medium sand composition which is suitable to
be used as reclamation filling materials. In terms of wave and currents impacts,
Sand borrow A has negligible impact on wave and current conditions. The
impact on sand transport and coastal stability during normal conditions is also
considered negligible.
• Sand Borrow B has negligible impacts on nearshore wave, current and sand
transport conditions. However, sediment analysis indicated that the site is not
suitable as sand source since it contains less than 10% of sand fractions.
Sand Borrow B
Sand Borrow A
Detailed Environmental Impact Assessment for the Proposed Reclamation for the Development of Oil and Gas Industrial Base at Kg. Rancha-Rancha, Labuan, F.T., Malaysia
Chapter 2 Project Description
Chemsain Konsultant Sdn. Bhd.
CK/EV403-4176/12
Page C2-7
� In addition, in lieu of locality, Sand Borrow B is located near to the transportation
route of entering Labuan and main oil and gas pipeline are located adjacent north
east direction. This may pose some hazardous especially to the marine traffic if the
sand extraction were to commence onsite.
� Hence, Sand borrow A was chosen as the proposed sand borrow site for the
proposed reclamation project.
2.5.2 Selection of Fill Material
Fill reclamation can be undertaken using either earth material (dry fill) or sand material
(hydraulic fill) or a combination of both. The land derived material may be obtained by
finding suitable source of earth fill which requires cutting of hills or rock blasting from
nearby quarries and transportation of the fill material to the proposed reclamation site. All
the activities involved will unavoidably cause environmental issue such as air and noise
pollution, traffic and transportation issue to surrounding area due to movement of heavy
vehicles from earth fill to project site.
The quality of the earth material might also not meet the specifications for offshore sand.
Earth material is therefore not recommended for environmental and technical reasons. In
short, sand borrow is more of a preferred option as it can be sourced not too far from the
reclamation site.
2.5.3 Selection of Optimum Dredging Equipment
The selection of optimum dredging equipment and procedure is crucial as it shall
determine the extent sand dredging operation would impact the environment.
The factors which need to be considered in the selection include availability, cost, physical
characteristics of sediment, amount of material to be dredged, depth, physical
environment of dredging site, and contamination level of sediment. The production rate
which is related to the levels of turbidity and Total Suspended Solids (TSS) generated
should also be considered.
2.5.3.1 Trailing Suction Hopper Dredger (TSHD)
The Trailing Suction Hopper Dredger (TSHD) is the most technologically advanced and
productive type of dredge.
Detailed Environmental Impact Assessment for the Proposed Reclamation for the Development of Oil and Gas Industrial Base at Kg. Rancha-Rancha, Labuan, F.T., Malaysia
Chapter 2 Project Description
Chemsain Konsultant Sdn. Bhd.
CK/EV403-4176/12
Page C2-8
Plate 2.2: View of Trailing Suction Hopper Dredger (TSHD)
Plate2. 3: Cross Section of a Typical Trailing Suction Hopper Dredger (TSHD)
Working Principle
A TSHD is a self propelled dredger with hoppers to store dredged material and shall be
employed to dredge unsuitable material from the designated project areas and to transport
this material to an approved offshore disposal site. TSHD is quite flexible in terms of
material to be dredged, placement alternatives, and the ability to work in protected and
unprotected waters. Since they are self-propelled, they can also work in congested areas
with minimum disruption to shipping traffic. A TSHD is commonly used for dredging silty,
sandy or gravely soil or soft clayey soils.
Detailed Environmental Impact Assessment for the Proposed Reclamation for the Development of Oil and Gas Industrial Base at Kg. Rancha-Rancha, Labuan, F.T., Malaysia
Chapter 2 Project Description
Chemsain Konsultant Sdn. Bhd.
CK/EV403-4176/12
Page C2-9
The dredging systems of a TSHD consist of one or two suction tubes, each driven by a
powerful centrifugal pump, called the sand pump. During the dredging, and in a process,
which is quite similar to the domestic vacuum cleaning, the lower ends of the suction tubes
are trailing along on the seabed, while the sand pumps provide the suction power to lift the
materials form the seabed into the hopper.
Once the TSHD approaches the dredging area, the sailing speed is reduced and the
suction tubes will be hoisted over board and lowered to the seabed.
At the lower end of the suction tube, a special draghead is attached which is designed for
maximizing the dredging production during the loading phase. The suction power is
provided by the sand pump, which is normally installed in the pump room in the engine
rooms of the dredge.
During the dredging, while the dragheads are on the seabed, the hopper dredge will
maintain a low trailing speed. Such trailing speed is depending on the nature of the
materials being dredged.
The materials thus lifted (dredged) from the seabed, will be pumped into the hopper as a
soil/water mixture. Care is needed to minimise the water content in the mixture.
Overflowing
It is economic to allow a certain degree of overflowing. This means that, while the solid in
the dredged soil/water mixture will settle in the hopper due to gravity forces, the excess
water is discharged via an adjustable overflow system.
The overflow, which is built inside the hopper, consists of an in height adjustable funnel
mounted on top of a vertical cylinder which ends under the keel of the dredge. The excess
water is discharged under the dredge, which is the lowest level possible, thus minimizing
the dispersion of fines into the surrounding waters.
Further, the design of the overflow is such that, by avoiding the entrapment of air in the
overflow water, a minimum turbidity is created.
In case where overflowing is environmentally prohibited, it is possible to monitor the filling
process precisely using the highly computerized dredging process parameters. Sensors
installed above the hopper will keep track of the height of fluids inside the hopper. By
comparing this to the height of the overflow funnels, the filling process will be stopped
when the fluids reach the funnel level.
Detailed Environmental Impact Assessment for the Proposed Reclamation for the Development of Oil and Gas Industrial Base at Kg. Rancha-Rancha, Labuan, F.T., Malaysia
Chapter 2 Project Description
Chemsain Konsultant Sdn. Bhd.
CK/EV403-4176/12
Page C2-10
Plate 2.4: View of Cutter Suction Dredger
2.5.3.2 Grab Dredger / Clamshell Dredger
The Grab Dredger (GD) typically comprises a clamshell grab, wire suspended from a
crane that is mounted on a pontoon or a vessel. Dredged material is normally loaded into
barges moored alongside the pontoon that is either moored by anchors or hydraulically
lowered legs (spuds).
.
Plate 2.5: View of Grab Dredger
Detailed Environmental Impact Assessment for the Proposed Reclamation for the Development of Oil and Gas Industrial Base at Kg. Rancha-Rancha, Labuan, F.T., Malaysia
Chapter 2 Project Description
Chemsain Konsultant Sdn. Bhd.
CK/EV403-4176/12
Page C2-11
Working Principal
A Grab Dredger is a stationary dredger, moored on anchors or on spud-poles. The
dredging tool is a grab normally consisting of two half-shells operated by wires or (electro)-
hydraulically. The grab can be mounted on a dragline or on a hydraulic excavator of the
backhoe type. Many modifications of grabs have been constructed like (top) open grab,
(top) closed grabs and watertight grabs. The grab dredger is used in harbours; the
dragline type also in deep water. The dredged material is loaded in barges.
Grab dredgers, sometimes called clamshells, can exist in pontoon and self-propelled
forms, the latter usually including a hopper within the vessel. The pontoon type grab
dredger again comprises a rectangular pontoon on which is mounted a revolving crane
equipped with a grab. The extraction operation consists of lowering the grab to the bottom,
closing the grab, raising the filled grab to the surface and loading the contents into a barge
or, if appropriate, onto the adjoining bank. The size of this type is determined by the
capacity of the grab bucket, which can vary between 1.0 and 20 m³, depending upon the
crane power.
The self-propelled grab hopper dredger is basically a ship which has one or more dredging
cranes mounted around a receiving hopper. It is easily moved from site to site under its
own power and also transports the dredged material to the relocation area. The size of this
type of dredger is expressed in terms of the hopper capacity and can range from 100 to
about 2,500 m³. The smaller vessels have a single crane, but some of the larger craft have
up to four. Production depends upon crane and grab size, water depth and, in the case of
the self-propelled variety, on the distance to the material relocation site.
Grab dredgers are usually held in position while working by anchors and moorings but a
few are fitted with a spud, or pile, which can be dropped onto the bottom while the dredger
is operating.
A wire line grab generally produces an irregular bottom profile with peaks and troughs and
is thus most suited to bulk excavation. The grab is a relatively simple and inexpensive
machine and performs best in consolidated silt, clays and loose sand, but the large, heavy
versions are good for removing rubbish, old piles, rubble and similar obstructions. Grabs
can also be used effectively for removing material from close to quay walls and in corners
of docks and basins that are otherwise difficult to access. A basic grab dredger can be
quickly and economically made tip from conventional land machines securely fixed to
pontoons for short term ad hoc tasks, but care needs to be taken to check stability.
2.5.3.3 Backhoe Dredger
The Backhoe Dredger (BHD) is similar to a land-based excavator mounted at one end of a
pontoon. For smaller work, a land-based excavator is often simply mounted on a barge.
For good leverage, the pontoon is fixed in position by spuds (support legs) pushed into the
seabed. The size of the excavator and of the bucket varies with the nature of the material
to be dredged and the maximum dredging depth. The excavator loads into hopper barges
that are towed to the disposal location.
Detailed Environmental Impact Assessment for the Proposed Reclamation for the Development of Oil and Gas Industrial Base at Kg. Rancha-Rancha, Labuan, F.T., Malaysia
Chapter 2 Project Description
Chemsain Konsultant Sdn. Bhd.
CK/EV403-4176/12
Page C2-12
Plate 2.6: View of Backhoe Dredger
Working Principal
A Backhoe Dredger is a stationary dredger, moored on anchors or on spud-poles. A spud
is a large pole that can anchor a ship while allowing a rotating movement around the point
of anchorage. Small backhoe dredgers can be track mounted and work from the banks of
ditches. A backhoe dredger is a hydraulic excavator equipped with a half open shell. This
shell is filled moving towards the machine. Usually the dredged material is loaded in
barges. This machine is mainly used in harbours and other shallow waters
The wire operated excavator unit has now been largely superseded by hydraulically
operated backhoe machines. These operate more efficiently than the face shovel. The
size of a backhoe dredger is described by the bucket capacity, which can vary between
0.5 and 13 m³. Production is dependent upon bucket size and the hardness of the
material. Breakout forces in excess of 90 t can be exerted by the larger machines, and
because of the very high horizontal loads developed by the jigging action the backhoe
dredger usually works on spuds. These are heavy pile-like structures which can be
dropped into the sea-bed by the dredger. Two spuds are mounted at the digging end of
the backhoe pontoon to provide resistance and one backhoe excavator is very efficient
and has good vertical and horizontal control; carefully worked it will produce a smooth
profile. Because the bucket is heavy and relatively rigid, care needs to be taken to avoid
damage to such features as quay walls and canal linings.
See Table 2.5.1and Table 2.5.2 for a summary of comparisons of the various dredgers
described above
Detailed Environmental Impact Assessment for the Proposed Reclamation for the Development of Oil and Gas Industrial Base at Kg. Rancha-Rancha, Labuan, F.T., Malaysia
Chapter 2 Project Description
Chemsain Konsultant Sdn. Bhd.
CK/EV403-4176/12
Page C2-13
Table 2.5.1: Summary of Various Dredgers
Dredger Type Site Condition
Trailing Suction Hopper Dredger (TSHD)
Cutter Suction Dredger (CSD)
Grab Dredger Backhoe Dredger
Bed Material
Fine Material 1 1 2 2
Sea Conditions
Impounded 2 1 1 2
Sheltered Water 1 1 1 1
Exposed Water 2 3 3 2
Note: 1 = suitable ; 2 = acceptable ; 3 = marginal
Table 2.5.2: Advantages and Disadvantages of Dredgers
Dredger Type Advantages Disadvantages
Trailing Suction Hopper Dredger (TSHD)
� Has the ability to dredge nearly
all soils, particularly efficient in
silts and sands,
� Generates relatively low levels
of turbidity during typical
dredge operations,
� Most can work in adverse
weather and sea conditions,
� Independent, flexible operation,
easy to change location of
dredging to suit weather or
shipping,
� Manoeuvrable within the
confines of the harbour
channel,
� Minimal effect on shipping,
� Able to transport material
relatively long distances,
� Relatively high rate of
production (1,000 – 12,500
m³/hr depending on hopper
size, soil and sailing distances.
� Requires sufficient water
depth in the dredging and
disposal areas and on route
between the two,
� Inability to work in confined
areas,
� Variation in over-dredging
depending on soil conditions,
vessel size and weather
conditions,
� Cohesive material can prove
difficult to discharge from
hopper, and
� Suspension of silty dredging
materials can generate high
turbidity during the loading
process if dredging beyond
overflow
Cutter Suction Dredger (CSD)
� Can convey the dredged
material direct to an adjacent
disposal or reclamation area, or
onto a barge,
� Has the ability to dredge an
� Limited workability under
medium wave conditions,
� Moored with spuds and/or
ropes, can form an obstruction
to navigation and shipping,
Detailed Environmental Impact Assessment for the Proposed Reclamation for the Development of Oil and Gas Industrial Base at Kg. Rancha-Rancha, Labuan, F.T., Malaysia
Chapter 2 Project Description
Chemsain Konsultant Sdn. Bhd.
CK/EV403-4176/12
Page C2-14
Dredger Type Advantages Disadvantages
accurate profile and hence
minimise the volume of
dredged material as a result of
over-dredging,
� Can dredge by excavating a
path forward when dredging
shallow areas such as for
widening the swinging basin,
� Relatively high rate of
production (500 to 3,000 m³/hr,
depending on vessel size,
barge hopper capacity, and soil
type).
� Barge overflows can create
significant turbidity,
� Working in non-overflowing
mode would require the
maximum amount of barges
plus tugs at considerable cost,
� Inflexible to change of
location.
Grab Dredger � Can dredge by excavating a
path forward when dredging
shallow areas such as for
widening the swinging basin,
� Suited for dredging confined
areas and for a range of
depths; and
� Can dredge loose to
moderately packed soils, such
as clayey silts and loose
� Unproductive dredging hard
soils or rock;
� Limited in high wave or
current conditions,
� Relatively low productivity
(100 – 800 m³/hour depending
on grab size and material),
� Can produce comparatively
high turbidity but can utilise
special grabs,
� Needs to load barges and to
move position periodically,
� Suitable access required for
tugs and barges,
� Not easily moved out of
shipping lanes.
� Greater dredging tolerance
required.
Backhoe Dredger � Can dredge soil, especially
cohesive soils, with little water
added and hence load the
barges efficiently without
overflow;
� Can dredge effectively in
confined areas,
� Position and excavation depth
� Unproductive dredging hard
soils or rock;
� Dredging depth is limited to
the length of the excavator
dipper arm,
� Relatively low productivity
rates (200 – 800 m³/hr
depending on material and
Detailed Environmental Impact Assessment for the Proposed Reclamation for the Development of Oil and Gas Industrial Base at Kg. Rancha-Rancha, Labuan, F.T., Malaysia
Chapter 2 Project Description
Chemsain Konsultant Sdn. Bhd.
CK/EV403-4176/12
Page C2-15
Dredger Type Advantages Disadvantages
control is very accurate,
reducing required over-depth to
deliver accurate profiles
bucket size),
� Working on spuds cannot
move easily out of shipping
lanes,
� Can produce comparatively
high turbidity in mud / silt
materials, unless specific
buckets are used which
further reduce output.
With the comparisons made above, basing on manoeuvrability and the existing seabed
conditions in the proposed sites to be reclaimed (and dredged); as well as the sand borrow
site, the use of TSHD and CSD appear to be the most suitable for this Project. .
2.5.4 No Project Option
The benefits of considering the “No Project Option” will be the absence of all
environmental impacts predicted in Chapter 4 and its associated costs as a result of the
proposed Project.
However, the “No Project Option” should also be weighed against the potential losses of
social, economic as well as some environmental benefits. These potential losses are
further described below:
1. Social Benefits
(a) Development of the local population with more job opportunities, better public
services which will encourage the locals to stay instead of migrating to other
cities in search of jobs.
(b) Opportunities to improve standard of living and quality of life at Kg Rancha-
Rancha area in general through demands and provisions of better
infrastructure, improved health centres, basic necessities and treated water,
electricity and sanitation system.
2. Economic Benefits
(a) Project employment of locals during reclamation stages.
(b) Local economic benefits for local businesses or individuals which may be
sourced for supply of goods and services to the Project during the
reclamation stage of the Project.
(c) The statement of need outlined in Chapter 1 clearly spells out the subsequent
development of the reclaimed area to meet the demand of the expanding oil
Detailed Environmental Impact Assessment for the Proposed Reclamation for the Development of Oil and Gas Industrial Base at Kg. Rancha-Rancha, Labuan, F.T., Malaysia
Chapter 2 Project Description
Chemsain Konsultant Sdn. Bhd.
CK/EV403-4176/12
Page C2-16
and gas industries. This need arises also due to the necessity to generate
growth in the country's industrialisation programme.
2.6 Project Activities
The main activities proposed as part of the Project and encompassed by this DEIA report
include:
� Pre-reclamation stage;
� Site preparation stage;
� Reclamation stage; and
� Post reclamation stage.
2.6.1 Pre-Reclamation Stage
Pre-reclamation activities will include environmental assessment, topographical and
hydrographical surveys, bathymetry survey, current measurement and consultations with
relevant agencies with regards to make and obtain necessary applications and approvals,
respectively.
Workboats and survey boats shall be used for the purpose of bathymetric surveys, current
measurement, sampling of water and sediment quality and marine ecological survey.
Stakeholder consultation (public dialogue and one to one social surveys) has also been
held to gauge the perception of the nearby residents regarding the proposed Project. The
details of the public dialogue can be referred to in Section 3.4.2.3.1, Chapter 3 of this
DEIA report.
2.6.2 Site Preparation Stage
2.6.2.1 Establishment of Site Office/ Base Camp
The tentative location of the site office and base camp is south east of the project site.
Site facilities (if any) will need to be constructed as follows:
� There will need to be a site office consisting of meeting rooms and offices for
contractors, resident engineer and clerk of works;
� The site office will need to be equipped with basic office utilities such as telephone,
fax line;
� Site utilities will need to consist of water, electric supply and telecommunication
services. Toilets or mobile toilet for site staff will also need to be provided;
Detailed Environmental Impact Assessment for the Proposed Reclamation for the Development of Oil and Gas Industrial Base at Kg. Rancha-Rancha, Labuan, F.T., Malaysia
Chapter 2 Project Description
Chemsain Konsultant Sdn. Bhd.
CK/EV403-4176/12
Page C2-17
2.6.2.2 Recruitment of Labour Force
The Project shall demand a group of skilled, semi-skilled and unskilled workers for its
development. The general man power requirement for this Project is anticipated to be as
follows:
� Project Manager
� Project Engineer
� Supervisor
� Foreman
� Workers (machine/dredger operators and general workers)
� Watchman
However the exact number of recruitment could not be provided at this stage as the
contractor for the Project is yet to be appointed.
2.6.2.3 Mobilization of Equipment and Workers
Mobilization of equipment shall include:
� Transportation of all equipment such as workboats to the reclamation site where
they are to be utilized; and
� Transportation of workers, staff and personnel to the site;
2.6.2.4 Construction of Bund/ Revetments
Permanent protection along the sea frontage should be completed as soon as possible to
avoid any prolonged released of sediments into the marine environment. Shore protection
works for land reclamation includes temporary bunds which serve to protect the reclaimed
land from erosion as effect of waves and current. Armor rocks, concrete units and smaller
rocks are normally used during the reclamation of the shore protection works. In general,
the hydraulic loads exerted on short protection works are in the form of wind waves, ship
waves, tidal levels, wind waves and currents. The specification of the armor rocks and
cornet unit will be carried out in the detailed design phase taking the above factors into
consideration.
a) Placing geotextile, bedding-fill and armor stone
Geotextile is used to prevent the underlying sand layer penetrating into the upper
rock later and from there bring flushed out into the marine environment. On land,
placing of geotextile will be done manually with the aid of hydraulic crawler or
excavator. In areas below 0 m chart datum, the geotextile will be laid by the floating
crane using mechanical means with the assistance if divers under water.
Detailed Environmental Impact Assessment for the Proposed Reclamation for the Development of Oil and Gas Industrial Base at Kg. Rancha-Rancha, Labuan, F.T., Malaysia
Chapter 2 Project Description
Chemsain Konsultant Sdn. Bhd.
CK/EV403-4176/12
Page C2-18
b) Sheet Pilling
As the proposed capital dredging is -10 m AMSL, some of the area is not suitable to
construct the temporary bunding, hence, sheet piling is proposed to act as a
cofferdam before any reclamation activities is commenced.
Sheet piling is a manufactured construction product with a mechanical connection
“interlock” at both ends of the section. These mechanical connections interlock with
one another to form a continuous wall of sheeting. Sheet pile applications are
typically designed to create a rigid barrier for earth and water, while resisting the
lateral pressures of those bending forces. Hence, sheet piling will be an optimum
choice to act as temporary bund prior any reclamation activities.
Plate 2.7: View of an example of sheet piling
2.6.2.5 Site Clearing and Biomass Disposal
No site clearing will be required at the project site as reclamation does not involve the
mainland. Hence, no vegetative waste is anticipated to be generated.
2.6.2.6 Waste Management
The main types of waste generated as a result of the project activities are as follows:
� Reclamation wastes such as stones, earth and sand;
� Domestic/solid wastes from workers on-site
� Scheduled wastes consisting of materials such as spent oil and grease, lubricants,
paint, etc, which usually arise from the maintenance of machinery and equipment
and construction works;
� Sewage from temporary toilets from the workers’ quarters; and site office.
The following will be adopted by the Project Proponent in its waste management plan:
Detailed Environmental Impact Assessment for the Proposed Reclamation for the Development of Oil and Gas Industrial Base at Kg. Rancha-Rancha, Labuan, F.T., Malaysia
Chapter 2 Project Description
Chemsain Konsultant Sdn. Bhd.
CK/EV403-4176/12
Page C2-19
� Sufficient collection bins will be provided to collect wastes from the workers’ quarter
and construction site. These wastes will be collected, transported and disposed off
at an approved landfill site.
� All sewage discharge to be directed into septic tanks. Direct disposal into
waterways is prohibited.
� Scheduled waste will be disposed off as per requirement of DOE (see Appendix
2.5.2). A licensed DOE scheduled waste collector should be hired to collect the
scheduled waste generated prior for final disposal.
� Vegetative spoils and removed stumps would be stockpiled within the work site
prior to disposal at an approved site. Some of the vegetative residues may be used
for mulch. Open burning within the Project site is strictly prohibited.
2.6.3 Reclamation Stage
The sequence of works during the reclamation stage is as follows:
� Capital dredging at reclamation site;
� Dredging at sand borrow site; and
� Reclamation at reclamation site.
2.6.3.1 Capital Dredging at Reclamation Site
Capital dredging works at the reclamation site is envisaged to dredge for the approach
channel and re-handling basin2. These works are essential to accommodate the required
draft of 10 m to allow for construction barges and tug boat to manoeuvre and carry out the
required dredging works. The tentative location of the capital dredging can be referred to in
Figure 2.6.1 (outlined in blue as area to be dredged to -10m MSL). The anticipated
dredger to be utilized onsite is trailing suction hopper dredger (TSHD) or Cutter Suction
Dredger (CSD). More details on TSHD and CSD have been elaborated in Section 2.6.3.2.
The dredged material shall be transported via floating pipeline/split hopper barges for
disposal. A Sedimentation basin will be located at the north of the reclamation site. The
dredged materials will be settled at the sedimentation basin and will be transported for
land disposal. See tentative location in Figure 2.6.1.
2 Rehandling basin is basically an area to be used temporarily to receive dredged material
that can later be rehandled by hydraulic pipeline dredger into the placement area.
Detailed Environmental Impact Assessment for the Proposed Reclamation for the Development of Oil and Gas Industrial Base at Kg. Rancha-Rancha, Labuan, F.T., Malaysia
Chapter 2 Project Description
Chemsain Konsultant Sdn. Bhd.
CK/EV403-4176/12
Page C2-20
Figure 2.6.1: Tentative location of capital dredging
2.6.3.2 Dredging At Sand Borrow Site
2.6.3.2.1 Dredging the Filling Material
The Project Proponent is yet to engage a contractor for the dredging and reclamation
works. Hence the type of dredger is not finalized yet. However, based on the scale of the
Project, the anticipated dredgers involved will either be a Cutter Suction Dredger (CSD) or
a Trailing Suction Hopper Dredger (TSHD). The detailed working principles of both
dredgers are described in the Section 2.5.3.
Sailing to discharge point
As soon as the TSHD or CSD is fully loaded, the suction tubes will be hoisted back
onboard and course will be set towards the area for unloading the hopper dredge. During
the transit the hopper dredge sails as a regular cargo vessel.
Placement
There are several ways to discharge the hopper load, which is not decided yet as no
contractor is appointed for the work yet.
a) Bottom dumping
The fastest way to unload the hopper is by discharging the load through the opened
bottom doors of the hopper. Waterjets inside the hopper will ensure the hopper is
completely empty and free of any dredged spoil prior to closing the bottom doors.
Detailed Environmental Impact Assessment for the Proposed Reclamation for the Development of Oil and Gas Industrial Base at Kg. Rancha-Rancha, Labuan, F.T., Malaysia
Chapter 2 Project Description
Chemsain Konsultant Sdn. Bhd.
CK/EV403-4176/12
Page C2-21
b) Pumping ashore
Some TSHD are equipped with pumping ashore facilities. This enables the hopper
load to be pumped via a combination of a floating pipeline and shore pipelines
directly into a reclamation area onshore. To this end a coupling system will be
prepared consisting of a flexible floating pipeline with at its seaside end a special
bow connection piece. The other end is connected to the shore pipeline.
The hopper dredge, upon arrival at the coupling area, will be connected via the bow
connection on board to this floating pipeline.
Now the jets in the hopper will fluidize the sand in the hopper. The sand pumps will
pump this fluidized mixture of sand and water through the pipelines to the
reclamation area.
For sections where the pipeline route has to cover large distances over water or
where the pipeline has to cross a surf zone of a shipping channel, a submerged
pipeline, resting on the seabed will be chosen.
2.6.3.3 Reclamation Activities at Reclamation site
Generally, the reclamation work will extend the existing land area by about 1 km seaward.
The present water depth in this area varies from 0 to 10 m. This shall need to be raised to
the proposed finished platform level of 3.3 m AMSL.
At this stage, the reclamation activities will be solely earthwork related activities such as
filling, compaction by heavy machinery such as bulldozers, excavators, etc. The
reclamation activity will commence from east to south western direction. Refer to Figure
2.6.2 for the tentative reclamation plan.
Detailed Environmental Impact Assessment for the Proposed Reclamation for the Development of Oil and Gas Industrial Base at Kg. Rancha-Rancha, Labuan, F.T., Malaysia
Chapter 2 Project Description
Chemsain Konsultant Sdn. Bhd.
CK/EV403-4176/12
Page C2-22
Figure 2.6.2Tentative Reclamation Phasing Plan
2.6.4 Post Reclamation
The post reclamation stage is defined as the stage whereby dredging and reclamation
stage is completed. Minor earthwork – compaction activities via compactor or excavator is
envisaged to make sure the filling material is evenly spread out when a dry level is
achieved. The area will be left to settle for one (1) to three (3) months.
2.6.5 Potential Abandonment
Abandonment of the Project may occur at any stage of the Project. Reasons for
abandonment may occur due to economic downturn, socially unacceptability of the Project
in the general public's view, unforeseen management and technical problems arising
during the implementation of the Project and changes in Government policy on nature of
the Project.
If the Project is abandoned following commencement of reclamation activities, the
reclamation and sand borrow site will be in a state whereby erosion of bunding/revetment
structure caused by wave and currents and hence causing water pollution. In addition,
machinery and equipment may be left over during the abandonment, therefore when the
Project is abandoned, a restoration programme shall be executed, which will include the
removal of all machinery and equipment from both the reclamation and sand borrow sites.
The restoration programme will ensure that the sites are left in a stable condition where
environmental impact is minimal, and will ensure the suitability of the sites for future use (in
particular the reclamation site).
For this development, project abandonment is very unlikely in view of the Project
Proponent's sound management and the essential need of developing the Rancha-
Rancha Industrial area in response to the rapid growth of oil and gas industries, as well as
in fulfillment of the Labuan Draft Master Development Plan 2030.