Industrial Training Report

111
UNIVERSITY OF MORATUWA Faculty of Engineering Non-GPA Module 3992: Industrial Training TRAINING REPORT R.M. Azoor 100860K Earth Resources Engineering Holcim Lanka Ltd. 11-11-2013 to 02-05-2014 13-06-2014

Transcript of Industrial Training Report

UNIVERSITY OF MORATUWA

Faculty of Engineering

Non-GPA Module 3992: Industrial Training

TRAINING REPORT

R.M. Azoor

100860K

Earth Resources Engineering

Holcim Lanka Ltd.

11-11-2013 to 02-05-2014

13-06-2014

i

PREFACE

I received the opportunity of undergoing my 6-month Industrial Training at Holcim Lanka

Ltd. I was placed along with three other colleagues at the Aruawakkalu Limestone mine

situated in Eluwankulam Puttalam Sri Lanka. The training period spanned a total of 24

weeks, from 18th of November 2013 to the 2nd of May 2014. In this report I have attempted

to provide a brief but thorough description of the knowledge gathered, skills acquired and

mastered and, and situations experienced. The content to follow in this report are based on

my experiences and were compiled by myself.

This report is organized in three chapters. The first chapter gives a brief introduction about

the training establishment. Holcim being a multinational company, the chapter begins with

some background information about the global Holcim group. Next, information regarding

Holcim Lanka Ltd is presented along with the vision and mission statements, organizational

structures and product portfolio. This information has been structured starting from the

corporate level, to the Palavi processing plant and finally to the Limestone Quarry where we

were placed at. The first chapter ends with a SWOT analysis of Holcim Lanka Ltd.

The second Chapter emphasizes on the training experiences I received. The chapter begins

with our induction to the organization. Information we gathered and learnt during the first

few days at the Aruwakkalu mine such as the geology of the area, the summary of the

quarrying process and the office practices and administration activities are included here. The

rest of the chapter is organized into subsections according to the principal operations carried

out during limestone mining. Each subsection contains a brief introduction to the processes

and highlights activities carried by us relating to each of the quarrying processes. Summaries

of findings made have been included where possible and other relevant information has been

annexed. This chapter also highlights learning opportunities we received.

The third and final chapter of this report presents the conclusion of the training program by

highlighting the knowledge and experiences gained, competencies developed, weakness

identified in myself and the overall personal growth experienced during the training period. .

I have also included comments on the entire training program. Suggestions have also been

included where applicable. In writing this report I have tried my level best to give a complete

picture of the content and value of the training program that I underwent as part of the BSc

Engineering Hons Degree program. and also believe that it meets this objective.

ii

ACKNOWLEDGEMENT

It is widely accepted that the 6 month Industrial training is the most important aspect of the

BSc Engineering Degree. It enables undergraduates to get hands on experience in the industry

and helps to gather practical knowledge which could only be acquired through working. I was

fortunate to undergo this valuable training at Holcim Lanka Ltd, one of the most prestigious

establishments in the industry. This opportunity would not have been a reality if not for the

effort and commitment put in by many individuals, at the University of Moratuwa, NAITA

and Holcim Lanka Ltd, into ensuring a solid and valuable training experience.

Firstly, my thanks goes to Mr. N.A. Wijeyewickrema, Director of the Industrial Training

Division and all other Personnel at the Training Division for facilitating the training program.

I also wish to acknowledge the officials at NAITA for arranging our training program. I wish

to thank the Head of the department of Earth Resources Engineering, Dr A.M.K.B.

Abeysinghe and other officials at the department for the support given in this regard. My

special thanks go to Mr. S. Weerawarnakula for arranging out training placements and for the

valuable insight given regarding our training program and also for the guidance given to us.

I wish to thank all personnel at Holcim Lanka Ltd for providing such a valuable training

program for us. I wish to thank Quarry Manager, Mr. W.N. Wedage for guiding us

throughout the program and for highlighting the outcomes of training and ways of achieving

them during our training period. I also wish to thank Quarry Engineer, Mr. Gayan Silva for

enabling a smooth induction to the organization and for the guidance given to us. My special

thanks go to the Junior Mining Engineers, Mr. P. Kumarage and Mr. A. Batagalla for taking

us under their wing and for providing us with the required knowledge and for giving us hands

on experience in all mining activities.

I also wish to thank Human Resources Officer at the Quarry, Mr. R.K.S. Marasinghe for the

support given to us with our lodging and other facilities and also Maintenance Superintendant

Mr. R.P.S. Dhanuka, Laboratory officers, Mr. R.P.W. Kariyawsam, Mr. J.M.W. Jayasundara,

Mr. A.H.M. Premaratne, Mr. R.M.S. Jayaratne and Mr. K.K.J. Darmasiri for further

enhancing our training experience. I am also thankful to all operators at the quarry for sharing

their knowledge and also the security officers and all other employees for the support

provided. I also wish to specially thank my fellow trainees with whom I had a pleasant

training experience.

iii

CONTENTS

Preface ..................................................................................................................................................... i

Acknowledgement .................................................................................................................................. ii

Contents ................................................................................................................................................. iii

List of Figures ......................................................................................................................................... vi

List of Tables ........................................................................................................................................ viii

List of Equations ................................................................................................................................... viii

1 Introduction to the Training Establishment .................................................................................... 1

1.1 Holcim Group .......................................................................................................................... 1

1.2 Holcim Lanka Ltd ..................................................................................................................... 1

1.2.1 Organizational Structure ................................................................................................. 2

1.2.1.1 Corporate Structure .................................................................................................... 2

1.2.1.2 Palavi Processing Plant Structure ................................................................................ 3

1.2.1.3 Aruwakkalu Quarry Structure ..................................................................................... 3

1.2.2 History of the Aruwakkalu Mine ..................................................................................... 3

1.2.3 Vision and Mission Statements ....................................................................................... 4

1.2.3.1 Vision ........................................................................................................................... 4

1.2.3.2 Mission ........................................................................................................................ 4

1.2.4 Product Portfolio ............................................................................................................. 4

1.2.4.1 Holcim Sanstha Supiri ................................................................................................. 4

1.2.4.2 Holcim Ready Flow ...................................................................................................... 5

1.2.4.3 Holcim Extra ................................................................................................................ 5

1.2.4.4 Ambuja Cement .......................................................................................................... 5

1.3 SWOT Analysis of Holcim Lanka Ltd ........................................................................................ 6

2 Training Experiences ....................................................................................................................... 9

2.1 Induction to the Organization ................................................................................................. 9

2.1.1 Safety Induction .............................................................................................................. 9

2.1.2 Familiarization with the Quarry Site ............................................................................... 9

2.1.2.1 The mining land extent ............................................................................................. 10

2.1.2.2 Geology of the Area .................................................................................................. 11

2.1.3 The quarrying process ................................................................................................... 12

2.1.4 Administration and Office Activities ............................................................................. 14

2.1.4.1 Engineering and Maintenance division ..................................................................... 14

iv

2.1.4.2 Quarry Lab ................................................................................................................. 14

2.1.4.3 Human Resources Division ........................................................................................ 14

2.1.4.4 Security Division ........................................................................................................ 14

2.2 Bed Cleaning, Drilling and Blasting ....................................................................................... 15

2.2.1 Bed Cleaning ................................................................................................................. 15

2.2.1.1 Machines Used .......................................................................................................... 15

2.2.1.2 Activities Carried Out ................................................................................................ 16

2.2.2 Drilling ........................................................................................................................... 18

2.2.2.1 The Drilling Process ................................................................................................... 18

2.2.2.2 Machines Used .......................................................................................................... 19

2.2.2.3 Drill Patterns ............................................................................................................. 20

2.2.2.4 Hazards encountered in Drilling and their mitigation .............................................. 22

2.2.3 Blasting .......................................................................................................................... 24

2.2.3.1 Explosives .................................................................................................................. 24

2.2.3.2 Explosive Handling and Storage ................................................................................ 28

2.2.3.3 Charging .................................................................................................................... 29

2.2.3.4 Blast Wiring and Detonation ..................................................................................... 32

2.2.3.5 Specific Charge .......................................................................................................... 34

2.2.3.6 Other types of Blasting.............................................................................................. 35

2.2.3.7 Problems Encountered in Blasting ............................................................................ 37

2.2.3.8 Hazard Management in Blasting ............................................................................... 38

2.2.4 Activities Carried Out by Us .......................................................................................... 39

2.3 Loading, Hauling and Dispatching ......................................................................................... 43

2.3.1 Loading and Hauling Machine Fleet .............................................................................. 43

2.3.1.1 Komatsu WA600 Front End Wheel Loader ............................................................... 43

2.3.1.2 Komatsu HD 325A Dump Trucks ............................................................................... 45

2.3.1.3 3rd Party 10-Wheel Haul Trucks ............................................................................... 53

2.3.2 Hauling roads ................................................................................................................ 55

2.3.2.1 Road Maintenance .................................................................................................... 55

2.3.2.2 Planning and Design .................................................................................................. 57

2.3.3 Dispatching .................................................................................................................... 60

2.3.3.1 The Dispatching Process ........................................................................................... 60

2.3.3.2 Locomotive Transport ............................................................................................... 60

2.3.4 Activities and Projects ................................................................................................... 62

v

2.3.4.1 Hauling Fleet Optimization ....................................................................................... 62

2.3.4.2 Hauling road level survey and road slope analysis ................................................... 64

2.4 Quality Control and Planning ................................................................................................ 69

2.4.1 Lab Activities ................................................................................................................. 69

2.4.1.1 Sampling .................................................................................................................... 69

2.4.1.2 Quality Parameters ................................................................................................... 73

2.4.1.3 Laboratory Testing .................................................................................................... 74

2.4.2 QSO and Quarry Master ................................................................................................ 75

2.4.2.1 Quarry Scheduling and Optimization (QSO) ............................................................. 75

2.4.2.2 QuarryMaster ............................................................................................................ 77

2.4.3 Mix Bed Preparation ..................................................................................................... 79

2.4.4 Activities at Palavi Processing Plant .............................................................................. 79

2.4.5 Activities carried out ..................................................................................................... 80

2.4.5.1 Alumina mapping of the Quarry ............................................................................... 80

2.4.5.2 Preparing Cross Sections of the Quarry Pit ............................................................... 80

2.4.5.3 Fill Volume Calculation of Old Road .......................................................................... 81

2.5 Overburden Removal and Rehabilitation ............................................................................. 82

2.5.1 Overburden Removal .................................................................................................... 82

2.5.1.1 cycle times ................................................................................................................. 82

2.5.1.2 Bench face and slope analysis ................................................................................... 83

2.5.2 Rehabilitation of the Quarry ......................................................................................... 87

2.5.2.1 Activities with IUCN................................................................................................... 87

2.5.2.2 Seedling bed Preparation .......................................................................................... 87

2.6 Machine maintenance and Workshop Activities .................................................................. 88

2.6.1 Daily maintenance operations ...................................................................................... 88

2.6.1.1 Tyre Maintenance .................................................................................................... 89

2.6.1.2 Welding Grinding ...................................................................................................... 89

2.6.2 Machine Safety Survey .................................................................................................. 89

2.7 Workshops and Other Learning Opportunities ..................................................................... 90

2.7.1 Lubricant Workshop at CETRAC .................................................................................... 90

2.7.2 Workshop on Maintenance of Construction Equipment ............................................. 91

2.7.3 Tire maintenance lecture by Triangle tire corporation ................................................. 91

3 Conclusion ..................................................................................................................................... 92

Annexes .................................................................................................................................................. ix

vi

Cement Production Chart .................................................................................................................. ix

Fill Volume Report .............................................................................................................................. x

List of Abbreviations ............................................................................................................................. xv

References ............................................................................................................................................xvi

LIST OF FIGURES

Figure 1.1: Corporate Organization Structure ........................................................................................ 2

Figure 1.2 : Organization Structure of Palavi Processing Plant ............................................................... 3

Figure 1.3 : Organization Structure of Quarry ........................................................................................ 3

Figure 1.4: Summary of SWOT Analysis .................................................................................................. 8

Figure 2.1 : Land Extent belonging to Quarry and the Quarry Pit ........................................................ 10

Figure 2.2 : A quarry face showing each type of material .................................................................... 12

Figure 2.3 : The Entire Quarrying Process ............................................................................................. 13

Figure 2.4 : The Entire Quarrying Process ............................................................................................. 13

2.5: Bed Cleaning using Komatsu D375 A ............................................................................................. 15

Figure 2.6: The CAT 374D Excavator being used for loading ................................................................ 16

Figure 2.7 : A covered Drill Hole ........................................................................................................... 19

Figure 2.8 : Parts of a track Drill ............................................................................................................ 20

Figure 2.9 : A typical Staggered Drill Pattern ........................................................................................ 21

Figure 2.10 : Burden, Spacing and Hole Depth of a Bed ....................................................................... 22

Figure 2.11 : Drilling at Night ................................................................................................................ 24

Figure 2.12 : Dynamite Cartridges ........................................................................................................ 25

Figure 2.13 : Water gel Cartridges ........................................................................................................ 26

Figure 2.14: A bag of Ammonium Nitrate ............................................................................................ 27

Figure 2.15 : Schematic and an image of an Electric Detonator ........................................................... 28

Figure 2.16: A primed water gel cartridge couple ................................................................................ 29

Figure 2.17 : Connecting an extra wire to an ED .................................................................................. 30

Figure 2.18 : Normal and Deck Charging .............................................................................................. 31

Figure 2.19 : A Series Parallel Circuit with 4 Loops .............................................................................. 32

Figure 2.20 : Circuit Diagram for Wiring Pattern .................................................................................. 33

Figure 2.21 : Charging a Drill Hole in Boulder Blasting ......................................................................... 35

Figure 2.22 : Fragmentation after Boulder Blasting.............................................................................. 35

Figure 2.23 : Methods of Boulder Blasting ........................................................................................... 36

Figure 2.24 : Testing Circuit .................................................................................................................. 38

Figure 2.25 : Yellow Fumes when Blasting ............................................................................................ 38

Figure 2.26 : Signboards for the Explosive Magazine ........................................................................... 40

Figure 2.27 : Stacking Line .................................................................................................................... 40

Figure 2.28 : The refurbished Explosive Magazine ............................................................................... 41

Figure 2.29 : Plan of Proposed Ammonia Hut ....................................................................................... 42

Figure 2.30 : Komatsu WA 600 Loader ................................................................................................. 43

Figure 2.31 : Komatsu HD 325 A Dump Truck ....................................................................................... 45

Figure 2.32 : Tyre Positions ................................................................................................................... 50

vii

Figure 2.33 : Road Watering Plan ......................................................................................................... 57

Figure 2.34 : The Planned New Ramp Area .......................................................................................... 58

Figure 2.35: Current and Future Cycle Distances .................................................................................. 59

Figure 2.36 : Locomotive Transport ...................................................................................................... 60

Figure 2.37 : Queue at the Loading Point ............................................................................................. 64

Figure 2.38 : 3D Model of road created using Surfer ........................................................................... 65

Figure 2.39 : Two methods of road filling ............................................................................................. 66

Figure 2.40 : Refilled Area of the New Road ......................................................................................... 68

Figure 2.41 : A typical test hole............................................................................................................. 69

Figure 2.42: 3D models of upper and lower layers ............................................................................... 71

Figure 2.43 : Coning and Quartering ..................................................................................................... 72

Figure 2.44 : The QSO Layout ................................................................................................................ 76

Figure 2.45 : QSO prediction for 4 quarters of 2014 ............................................................................ 77

Figure 2.46 : The 3 Dimensional Model of the Quarry in QuarryMaster .............................................. 78

Figure 2.47 : Short Term Mine Planning with QuarryMaster ............................................................... 78

Figure 2.48 : Preparing of Mixed Heaps ................................................................................................ 79

Figure 2.49 : Layered appearance of a Mixed Heap ............................................................................. 79

Figure 2.50: Contour Map of Alumina Variation ................................................................................... 80

Figure 2.51 : Cross Sections of the Quarry Pit ...................................................................................... 81

Figure 2.52 : The Existing Surface and the Proposed Surface ............................................................... 81

Figure 2.53 : Overburden Removal ....................................................................................................... 82

Figure 2.54 : Risk Assessment Matrix ................................................................................................... 86

Figure 2.55: Seedling Bed Locations ..................................................................................................... 87

Figure 2.56 : Daily Machine Checks ...................................................................................................... 88

Figure 2.57 : Welding Operations ......................................................................................................... 89

Figure 2.58 : The Excel data Entry Form Used for the Machine Survey ............................................... 90

Figure A.3.1 : The Cement Production Process ...................................................................................... ix

Figure A.3.2: Elevation Grid .................................................................................................................. xii

FigureA.3.3: Surfer 3D model of Existing Surface ................................................................................ xiii

FigureA.3.4:Surfer 3D model of Proposed Surface ...............................................................................xiv

viii

LIST OF TABLES

Table 2.1 : Fuel Consumption of D375A during bed cleaning ............................................................... 17

Table 2.2 : Advantages and Disadvantages of Dynamite ...................................................................... 25

Table 2.3 : Advantages and Disadvantages of Water gel ...................................................................... 26

Table 2.4: Quantities of Explosives Used .............................................................................................. 31

Table 2.5 : Fuel Consumption of WA 600 Wheel Loader ...................................................................... 44

Table 2.6 : Dump Truck Cycle Times ..................................................................................................... 46

Table 2.7 : Tyre Records ........................................................................................................................ 48

Table 2.8 : Fuel Consumption of Dump Trucks ..................................................................................... 52

Table 2.9 : Summary of Dump Truck Cost ............................................................................................. 53

Table 2.10 : Comparison of Hauling Trucks........................................................................................... 54

Table 2.11 : Effective Distance in Road watering.................................................................................. 56

Table 2.12 : Loading Process times of Sump Trucks and 10-Wheel Trucks .......................................... 63

Table 2.13 : Calculated fill Heights in the two Methods ....................................................................... 67

Table 2.14 : Coordinates extracted from Test Hole Data ..................................................................... 70

Table 2.15: Quality Targets of the Quarry ............................................................................................ 74

Table 2.16 : Overburden Removal Cycle Time Summary ...................................................................... 83

Table 2.17: Summary of Bench Face Risk Assessment ......................................................................... 84

LIST OF EQUATIONS

Equation 2.1: Drilling Cycle Time .......................................................................................................... 18

Equation 2.2 : Calculating Blast tonnage .............................................................................................. 21

Equation 2.3 : Resistance in a Series Circuit ......................................................................................... 33

Equation 2.4 : Resistance in a Parallel Circuit ....................................................................................... 33

Equation 2.5 : Specific Charge............................................................................................................... 34

Equation 2.6 : Formula for LSF .............................................................................................................. 73

Equation 2.7 : Alumina Ratio ................................................................................................................ 73

Equation 2.8: Silica Module .................................................................................................................. 73

1

1 INTRODUCTION TO THE TRAINING ESTABLISHMENT

1.1 Holcim Group

Holcim is a Swiss based company specializing in the production of cements and aggregate. It

was founded in 1912 in Jona Switzerland and was known as Holderbank until the company

changed its name to "Holcim in 2001. As of 2014, Holcim operates in more than 70 countries

worldwide and has a workforce of 71000 employees. The current production capacity of

Holcim is, 215 million tons per year. In addition to cement and aggregate products Holcim

also provides consultancy services and energy and waste management solutions. Holcim is

one of the two largest cement manufactures in the world with the other being Lafarge. In

April 2014, it was announced that the two companies have agreed to a merger. This new

company, LafargeHolcim, would be the world leader in the industry by far with a

manufacturing capacity of over 427 million tons per year.

1.2 Holcim Lanka Ltd

Holcim Lanka Ltd is a part of the global Holcim group and is the market leader in cement and

related building materials in Sri Lanka. Like Holcim global, Holcim Lanka Ltd also provides

technical and consultation services in the fields of construction and waste management in

addition to manufacturing cement. While being the leader in the industry, Holcim Lanka Ltd

is also Sri Lanka's only integrated cement manufacturer. This means that cement is produced

from raw materials sourced from Sri Lanka itself, unlike most other processes where clinker

used for manufacturing cement is imported. This integrated cement manufacturing process

used by Holcim Lanka Ltd is often described as a "Quarry to Lorry Operation".

Holcim Lanka Ltd operates a limestone mine in Aruwakkalu where the main component of

cement, limestone is sourced, a processing plant in Palavi where the cement is produced and

packed, and a grinding plant in Galle. Another packing plant is planned to be constructed in

Tricomalee. In addition to these, Holcim Lanka Ltd also operates the Galle Import terminal

where Ambuja cement is imported. The head office of Holcim Lanka Ltd is located at 413,

Duplication Road Colombo 3. Finance, Human Resources, Business planning and other

management processes are performed here.

Limestone mined from the Aruwakkalu Quarry site, is transported to the processing plant at

Palavi via railway where limestone and other additives also sourced from various locations in

2

Sri Lanka are processed to produce cement. The cement is packed and distributed through an

extensive distribution network spanning all 9 provinces of Sri Lanka.

Holcim Lanka Ltd has a production capacity of about 1.6 million tons of cement per year and

has a workforce of about 15,000 employees (both direct and indirect). Holcim Lanka Ltd

generated annual revenues of Rupees 20.1 billion (157 million USD ) in the year 2012. Along

with its improved financial performance Holcim Lanka Ltd has also strived to give value

back to the society with its many CSR Projects. Holcim Lanka Ltd is also a trendsetter in

sustainable development in the industry.

1.2.1 Organizational Structure

Holcim Lanka Ltd, has a functional organizational structure where the organization is divided

into segments according to the functions performed. The structure follows a hierarchical

arrangement with clear lines of reporting. Starting from the corporate level, the structure

leading to that of the Aruwaakalu Quarry has been shown below.

1.2.1.1 Corporate Structure

In the corporate structure shown below, the Quarry and the Plant comes under the

Manufacturing department.

Figure 1.1: Corporate Organization Structure

3

1.2.1.2 Palavi Processing Plant Structure

The Palavi Processing Plant is headed by the plant manager .

Figure 1.2 : Organization Structure of Palavi Processing Plant

1.2.1.3 Aruwakkalu Quarry Structure

All staff at the quarry report to the Quarry Manager as shown below.

Figure 1.3 : Organization Structure of Quarry

1.2.2 History of the Aruwakkalu Mine

The Integrated cement plant consisting of the Aruwwakalu limestone mine and the

Processing plant at Palavi was previously known as the Cement Corporation and was a fully

government owned entity. It began operations in 1970 and functioned under the Ministry of

Industrial Development. In 1993, the cement corporation was privatized and taken over by a

Pakistani cement company named "Thawakkal". In 1996, the company ownership was

transferred to "Holderbank", the company which eventually changed its name to "Holcim" in

the year 2001.

4

1.2.3 Vision and Mission Statements

Sustainable Development is the core value of all business activities of Holcim Lanka Ltd. It

Strives to create value by strengthening the communities it serves. To achieve its goal of

sustainable development, Holcim Lanka Ltd takes a "Triple bottom line" approach, where

economic, social and environmental impacts, are integrated into all day to day business

activities and core operations. The vision and mission statements of the company are as

follows.

1.2.3.1 Vision

"To be the leading and the preferred supplier of cement and related building materials to

build foundations for Sri Lanka's future. "

1.2.3.2 Mission

"To be Sri Lanka's most respected and attractive company - creating value to all our stake

holders."

1.2.4 Product Portfolio

In essence, cement is manufactured by grinding clinker to a fine powder. Cement acts as a

binding agent when mixed with water, sand and gravel to produce concrete. the properties of

cement and the resulting concrete can be varied with different ratios of the ingredients and

also with various additives.

To meet the requirements of the current construction industry, Holcim Lanka Ltd produces a

range of cements each with its own characteristic properties. The Current product portfolio of

Holcim Lanka Ltd is given below.

In addition to the products mentioned below , Holcim Lanka also produces customized blends

of cement with tailor made properties for special applications and projects.

1.2.4.1 Holcim Sanstha Supiri

Holcim Sanstha Supiri is the most popular product of Holcim Lanka Ltd and has rooted

deeply into the Sri Lankan society as a consistent and dependable cement. It is a Portland

Limestone cement manufactured in compliance with Sri Lankan and British standards. The

5

characteristic property of this cement is it's high workability. High workability reduces

bleeding and honeycomb effects. This results in a high long term strength in the concrete.

Recommended Applications: Structural elements in normal concrete (foundations, slabs and

beams )

Packaging and Delivery : Can be purchased in 50kg bags

1.2.4.2 Holcim Ready Flow

Holcim Ready Flow is an ordinary portland cement manufactured in compliance with Sri

Lankan and British standards. By optimizing the cement content, it helps the concrete achieve

high strength and durability. Also in using this cement the cost for admixtures can be

lowered.

Recommended Applications: Ready mix and structural concrete applications such as

infrastructure projects where early strength and durability is required.

Packaging and Delivery : Has to be purchased in bulk form

1.2.4.3 Holcim Extra

This is a relatively new addition to the Holcim product lineup and is a portland pozzolana

cement manufactured in compliance with Sri Lankan standards. It is a high performance

cement produced to withstand severe environments and to last longer. Concrete made using

Holcim Extra is resisitant to acids, sulfates, and chlorides.

Recommended Applications: Long term Concrete structures exposed to sea water such as

harbours, jetties, sea walls, bulkheads. Infrastructure in wastewater and hazardous material

handling projects.

Packaging and Delivery : Has to be purchased in bulk form

1.2.4.4 Ambuja Cement

It is an ordinary portland cement imported by Holcim Lanka ltd also manufactured

incompliance to British and Sri Lankan standards. It has a high early strength and a quicker

setting time.

Recommended applications : Pre cast work where quick setting is required.

Packaging and Delivery : Can be purchased in 50kg bags

6

1.3 SWOT Analysis of Holcim Lanka Ltd

A SWOT Analysis, examining the Strengths, Weaknesses, Opportunities and Threats to

Holcim Lanka Ltd., was performed as follows.

Strengths

Sri Lanka's only Integrated cement manufacturer

- Holcim Lanka Ltd, operates Sri Lanka's only integrated cement

manufacturing process. This reduces the cost by a significant amount.

Lots of past experiences

- Having had over 50 years of experience in the industry as, Lanka Cement

Corporation and also with experience from Holcim Global, Holcim Lanka Ltd,

has a lot of accessible knowledge on cement production.

Well known brand in Sri Lanka

- Formerly "Sanstha" and now "Holcim Sanstha" brand is well known in the

Sri Lankan Society and is often associated with higher standards in the cement

industry.

Solid Quality Control

- With extensive measures for quality control such as the state of the art X-Ray

Fluorescence spectroscopy method employed at the plant, high quality cement

can be produced with consistency.

Safety Standards

- Being a company highly commited to safety it occupies a high place in the

minds of potential employees.

Extensive distribution network

- Holcim Lanka Ltd possesses an extensive distribution network making its

brand well known in even the remotest corners of the country.

International Support

- Holcim being a multinational company, it receives continuous technical

support and expertise which help elevate the standards of cement

manufacturing and other related activities such as quarrying.

Sustainability

- Being a trend setter in sustainability, Holcim Lanka Ltd. has a solid

foundation in the cement industry of Sri Lanka.

7

Weaknesses

Higher Price

- Being a premium cement brand in Sri Lanka, the price of Holcim cement is

markedly higher than other brands. This causes a demand shift towards the

other cheaper brands in the market.

Long distance between quarry and plant

- The Limestone quarry and the processing plant being situated over 30

kilometers apart increases the transportation cost and also the overall

production cost.

Lesser marketing of Specialty Cements

- Holcim Lanka Ltd. Produces specialty cements suitable for unique

applications such as irrigation projects, and high performance and abrasion

resistive cements. However, due to the lack of proper marketing, many are not

aware of this fact.

Opportunities

Expanding Manufacturing processes

- Sri Lanka has extensive limestone deposits in the Northern part of country.

Also, infrastructure such as the KKS cement plant already being available ,

presents the opportunity to Holcim to expand its integrated cement

manufacturing process further.

Rapid infrastructure development

- Due to the rapid development of Sri Lanka, the construction industry is

booming and the demand for cement is increasing rapidly. This creates a lot of

opportunities in marketing Holcim Cements in mass scale.

Global Merger

- The planned merger between Holcim Global and Lafarge, the two largest

cement manufacturers in the world would also enable Holcim Lank to attain

new heights in the Sri Lankan Industry as well.

8

Threats

Low price imported alternatives

- Several new lower priced cement brands have and continue to enter the

market and poses the threat of lowering the market share of Holcim Cement.

High Energy Cost

- Cement manufacturing is highly energy intensive process and the recent

increase in fuel prices have increased the overall production cost of cement.

World Cement demand decreasing

- Although the Sri Lankan construction industry is booming, the global

demand for cement is declining and with it the research and development into

the area. This reduces the international support received by Holcim Lanka.

Environmental protests for quarrying process

- Despite the extensive rehabilitation and the environmentally friendly

methods employed, the limestone quarrying process is still opposed by several

environmental activists.

Figure 1.4: Summary of SWOT Analysis

Strengths

•Sri Lanka's only Integrated cement manufacturer

•Lots of past experiences

•Well known brand in Sri Lanka

•Solid Quality Control

•Safety Standards

•Extensive distribution network

•International Support

•Sustainability

Weaknesses

•Higher Price

•Long distance between quarry and plant

•Lesser marketing of Specialty Cements

Opportunities

•Expanding Manufacturing processes

•Rapid infrastructure development

•Global Merger

Threats

•Low price imported alternatives

•High Energy Cost

•World Cement demand decreasing

•Environmental protests for quarrying process

Holcim Lanka Ltd.

9

2 TRAINING EXPERIENCES

2.1 Induction to the Organization

Upon arriving at the Palavi Cement plant and signing the training contracts, we were given a

safety induction by the safety officer. Then we arrived at the Aruwakkalu Quarry Site where

our entire training program took place. During the first day at the Aruwakkalu site, we were

given a tour of the quarry site and office premises and also another safety induction.

2.1.1 Safety Induction

Holcim Lanka Ltd considers safety to be of paramount importance and strives hard to

maintain a workplace with zero harm or injury. While safety procedures are implemented in

all operations, the safety regulations at Holcim are distilled down to 5 "Cardinal Rules".

These cardinal rules are,

1. Do not override or interfere with any safety provision, nor allow anyone else to override or

interfere with them, regardless of their relative seniority to yourself.

2. Personnel protective equipment (PPE), Rules applicable to a given task, must be adhered to

at all times.

3. Isolation and lockout procedures must always be followed.

4. No person may work if under the influence of alcohol or drugs.

5. All injuries and incidents must be reported.

We were given a thorough safety induction and all necessary Personnel Protection Equipment

including Safety Shoes, Hard hats and Safety Goggles. We were also given uniforms with a

high visibility reflective band. All employees at Holcim Lanka Ltd, all third party contractors

and even trainees are expected to be well versed in the above cardinal rules and to strictly

adhere to them.

2.1.2 Familiarization with the Quarry Site

After the Safety Induction and the tour of the quarry premises we were given a brief

introduction about the quarry site and the geology of the limestone basin.

10

2.1.2.1 The mining land extent

The land extent available for mining is bordered by the Dutch Bay from the east and Kala

Oya from the West. Beyond the Kala Oya lies the Wilpattu National Wildlife Reserve. The

boundary of this land extent is outlined in light green in Figure 2.1. This large land has been

divided into 3 blocks namely A, B, and C. Only Block A has been mined up to now. The

entire land extent has been explored and prospected during the 1950s for limestone, by means

of core drilling operations. The data gathered from these core drill data has been fed into the

QSO (Quarry Scheduling and Optimization) software which is used for long term planning of

quarry operations.

The present quarry pit occupies only a small area of this land with dimensions of 600m in E-

W direction and 400m in the N-S direction, and has a the total excavated area is about 140Ha.

The quarry pit is maintained at this size in order to ease operations and refilling is done as the

quarry advances forward. According to the optimization data and physical quality data, the

current quarry advancement trend is in the N-E direction.

Figure 2.1 : Land Extent belonging to Quarry and the Quarry Pit

11

2.1.2.2 Geology of the Area

The entire area consists of Miocene limestone lying on a Precambrian basement. The

basement consists mainly of sandstone formations. The limestone layer also shows variations

in quality indicating different periods and conditions of sedimentation. At certain areas a clay

layer has also been sandwiched between limestone layers. The overall effect of this formation

is seen as an increase of quality of the limestone with depth of excavation. This gives rise to

two layers of Limestone. A low grade layer on top and a high grade layer at the bottom which

are excavated separately.

The topmost limestone layer has a higher content of silica and is known as siliceous

limestone. The reason for this high silica content is that the layer has undergone differential

weathering which is also evident by the irregular and wavy "finger like" formation of the

layer.

Atop this layer lies an overburden layer consisting of red soil. This red soil has intruded into

the irregular limestone layer which lies beneath it. For this reason and also due to the high

silica content of the first limestone layer it is not used for production and is discarded, For

this reason, this layer is called the "Reject layer".

The top most portion of the overburden consists of a fertile soil layer. This layer can be

identified by the high content of humus and other organic matter. This layer is excavated

separately and piled separately to be used as the top most fill layer in the rehabilitation

process. The following layers of overburden soil are not fertile and are primarily used for

refilling purposes.

High quality limestone can be found below the ground level of the quarry as well. If not

diluted by clay this layer is also extracted by base excavations.

The above mentioned limestone and overburden layers are depicted in the section of the

quarry face in Figure 2.2 below.

12

Figure 2.2 : A quarry face showing each type of material

2.1.3 The quarrying process

After the tour of the quarry site and office premises, we were introduced to the individual

quarry operations. We acquainted ourselves with these activities and the operators and

personnel involved in them.

The unit processes in the quarry operation are as follows

Overburden Removing

Bed Cleaning

Drilling

Blasting

Quality Assurance

Hauling

Mix bed preparation

Wagon loading and Dispatching

Rehabilitation

13

The above operations are listed in the order in which limestone production has to be carried

out. However some of these operations are carried out simultaneously for practical reasons.

For example, overburden removal and rehabilitation are usually carried out together as the

overburden excavated is used in refilling the excavated pits in the rehabilitation process. The

entire quarry process can be represented by the following flow chart

Figure 2.3 : The Entire Quarrying Process

Figure 2.4 : The Entire Quarrying Process

14

2.1.4 Administration and Office Activities

The quarry office premises consists of four main sections to manage and oversee the entire

quarrying process. These sections are, The Engineering and Machine maintenance division,

The Quarry Lab, Human Resources Division and the Security Division. All division heads

report to the Quarry Manager.

2.1.4.1 Engineering and Maintenance division

The engineering division consists of a Quarry Engineer and two Junior Mining Engineers. All

planning activities, scheduling, and handling of all quarry operations are performed by them.

Computerized records of all activities such as performance parameters, production and output

are maintained and daily, monthly and annual scheduling and planning is conducted. In

addition to this, long term quarry planning, quarry infrastructure building and overall quality

improvement is also performed. We were exposed to these areas during our period of

training. The machine maintenance is headed by the Maintenance Superintendant. All

activities of the workshop and handling breakdowns of machines comes under his

responsibilities.

2.1.4.2 Quarry Lab

The lab is headed by the Quarry Chemist and conducts tests for the quality of the material

excavated. Sampling is done during drilling, after blasting and also during mix bed

preparation. Quality tests are performed regularly and also samples are sent to the plant at

Palavi for XRF analysis. Using this data, the mix bed preparation is coordinated.

2.1.4.3 Human Resources Division

The Human Resources division concerns itself with the welfare of employees and performs

all typical HR related activities such as HR planning, recruitment, grievance handling, etc. It

organizes welfare related activities for the employees and also coordinates with the store

keeper to provide goods and services that are entitled to the employees.

2.1.4.4 Security Division

The security division maintains the overall security of the quarry site as well as the land

extent controlled by the company. Safety related activities are also performed by this

division. The handling of explosives and their safe storage is one of the main responsibilities

of this department.

15

2.2 Bed Cleaning, Drilling and Blasting

Bed Cleaning, Drilling and Blasting are in order, three unit operations performed in order to

break and loosen the consolidated limestone or reject beds. Bed cleaning is performed to

facilitate drilling, while drilling is performed to charge explosives when blasting. Blasting

can be regarded as the first stage of comminution.

All three of these operations are performed in order, when preparing reject beds for reject

blasts and in preparing Limestone beds for production blasting.

2.2.1 Bed Cleaning

The main purpose of bed cleaning is to clean the surface of the bed and to flatten the surface

to enable drilling. Generally, a Bulldozer is used to rip the outcrops and uneven surfaces

while the blade of the dozer is used to shove the ripped debris away from the bed. Several

passes over the bed with the dozer blade grounded flattens the bed and also smoothes it to a

certain extent and enables easy drilling. A well prepared bed also makes it easy for the track

mounted drills to travel over the bed.

2.2.1.1 Machines Used

2.2.1.1.1 Komatsu D375A Dozer

The Komatsu D375A Dozer is

the largest dozer in Sri Lanka

and is the main machine used for

bed cleaning at Holcim Lanka

Ltd. It has a Blade diameter of

about 4metres and is equipped

with ripper attachment at the

rear side. Both the ripper

attachment and the dozer blade

are used in the preparation of

beds. It is possible to rip and

separate material of hard

consolidated limestone even 2.5: Bed Cleaning using Komatsu D375 A

16

without blasting. For this reason, ripping by the dozer is also considered a mode of

production at times.

Sometimes depending on availability constraints and practical reasons, Hired dozers are also

used for bed cleaning.

2.2.1.1.2 CAT 374D Excavator

This machine is also the largest

of its kind found in Sri Lanka.

It is maintained by United

Tractors and Equipment (UTE)

Ltd., under a full maintenance

contract with Holcim Lanka

Ltd. It has bucket capacity of

over 3 cubic metres and has a

boom specifically designed to

suit the limestone bed

dimensions of the Aruwakkalu

Quarry. In addition to

performing bed cleaning

operations, owing to its high

bucket capacity, the CAT 374D Excavator is also used for loading.

Preparing access roads to the bed is also a vital component of bed cleaning. In doing so, care

should be taken not to interfere with other activities such as hauling. For this reason bed

cleaning has to be performed with careful planning.

2.2.1.2 Activities Carried Out

Bed cleaning is the most fuel consuming jobs when considering dozers. When cleaning reject

beds, the dozer has to break and level strong siliceous limestone formations. Also the dozer

has to maneuver a lot in small spaces when cleaning limestone beds. These reasons result in a

very high energy consumption by the dozer. To assess the diesel consumption of the Holcim

owned Komatsu D375A Dozer, we were assigned to conduct an analysis.

To perform this analysis, we gathered data from the FMC (Full Machine Contract) data

Sheets where the daily performance of each operator and job is recorded. We gathered the

Figure 2.6: The CAT 374D Excavator being used for

loading

17

data and filtered them by job and working hours to obtain information about the hours spent

cleaning beds and also the fuel consumption for each day. Fuel consumption is calculated by

monitoring the volume of fuel pumped into the machine at each instance. By summing up all

the daily values the corresponding totals for each month were arrived at. Using this data the

average fuel consumption was calculated. Table 2.1 shows the summary of each month's fuel

usage and the final average fuel consumption at the end of the year 2013.

Table 2.1 : Fuel Consumption of D375A during bed cleaning

Shift A Shift B

Month Working Hrs Diesel(l) Working Hrs Diesel(l)

Jan 134.8 10691 109.4 9848

Feb 105.8 8918 121.7 9921

Mar 97.3 7987 73 5564

Apr 89.6 7262 90 7990

May 40.2 3246 28.6 2282

Jun 115.5 11423 76 6036

Jul 97.8 7478 42.7 3209

Aug 132 11308 82.5 6821

Sep 128.9 9741 96.3 7679

Oct 117.7 8029 94.1 7490

Nov 87.4 7052 68 5656

Dec 19.1 854 68.7 5968

Total 1166.1 93989 951 78464

Average Diesel

Consumption(l/hr) 80.60 82.51

18

2.2.2 Drilling

The purpose of drilling is to open holes in the limestone bed in order to load explosive

charges into them. Drill holes with diameter 64mm are drilled to a depth ranging from 10 to

40 feet (3-12 m). The drill hole depth depends on the type of bed and its vertical extent. For

example, Most reject and low grade limestone beds are drilled to 30feet (3 rods) while some

high grade beds are only drilled up to 20feet (2 rods). The required drilling depth can vary

from place to place in the quarry due to the spatial variation of depth and quality of the

limestone bed. These variations are determined with core drilling data and drilling activities

are planned and directed accordingly.

These drill holes are drilled in patterns on the bed to facilitate better energy distribution

which leads to a more uniform breakage of the rock and helps minimize adverse effects such

as fly rocks. Crawler mounted pneumatic track drills are used for drilling.

2.2.2.1 The Drilling Process

Once the bed has been cleaned, the Drill Operator and the helper takes the drill on to the bed

via the access roads and starts drilling according the instructions provided by the engineer.

According to the data gathered by us, The average cycle time for drilling is 15 minutes with

the time taken only to drill one hole is 12 minutes.

Drilling Cycle Time = Time taken to travel to the hole + time taken to drill the hole

Equation 2.1: Drilling Cycle Time

While drilling is performed, the drill dust and powder that is flushed out of the hole is

gathered into a dustpan. This dust is packed and sent for sampling. These samples provide

data about the bed that is being drilled and is useful for planning activities.

Once the drilling is completed, the drill hole is covered with a piece of tarpaulin, a large rock

laid on top of it and covered with surrounding soil/quarry dust to create a mound. This serves

two purposes. Firstly it protects the drill hole from rain and prevents the hole form being

flooded by water or filled with soil. Secondly it helps to easily identify the locations of the

drill holes when charging the blast. A picture of a covered drill hole without soil mound over

it, is shown in Figure 2.7.

19

Figure 2.7 : A covered Drill Hole

2.2.2.2 Machines Used

For drilling purposes, a Holcim owned track drill with a Hired compressor and another track

mounted drill and compressor system which is hired from NEM construction Ltd. are used.

Both drills operate with compressed air. These drills operate at a nominal operating pressure

of 0.7 MPa.

The main components of the drill are as follows

Hammer

Drill Rod

Drill Bit - 64 mm button bit

The Hammer is the power source of the drill and provided both rotary and percussive forces.

Thus this is a rotary percussive type drill. The Hammer moves vertically across the boom of

the drill by means of a gear and chain arrangement. The Hammer pushes down the drill rod as

drilling progresses. When the rod has gone down the hole, the drill rod is detached, the

hammer raised and another drill rod is attached to the previous drill rod and coupled with the

hammer. Then the drilling cycle begins again. At the Aruwakkalu mine, the drill hole depth

varies between 1rod and 4 rods.

The Drill Rod transmits the energy from the hammer to the Drill Bit. The rods are made from

hardened steel and each rod is 10feet (3m) long. While in the drills currently used at the

mine, the drill rods have to be manually changed, other composite drills can change the rods

automatically.

Tarpaulin Piece

Rock

20

The Drill Bit is the component that comes into contact with the rock and where all the shear

forces act. For this reason, the Drill Bit have to made of a highly tough material. The Bits

used at the mine are Button Bits made of Tungsten Carbide. A button bit (shown in Figure

2.8), there are air vents located between the buttons. These vents serve the purpose of

flushing out the drilled material. The flushing medium is air. While drilling is performed, air

is pumped through the drill steel into the bit where the bit - rock interaction takes place. The

air pressure cause the rock powder to be flushed out from the drill hole opening.

Figure 2.8 : Parts of a track Drill

In a discussion we had with Quarry Engineer we discussed the possibility of using a down the

hole hammer drill for drilling as it would eliminate the need to change drill rods as drilling

progresses and thus would save time. While this would save time, most down the hole

hammers have a larger drill bit diameter and wouldn't suit our requirements very well. Also

the possibility of the hammer getting stuck down the drill hole is higher in limestone

formations. Therefore down the hole hammers are not suitable for the Aruwakkalu Quarry.

2.2.2.3 Drill Patterns

The beds at the Aruwakkalu Quarry are always prepared in rectangular sections. Therefore

the most appropriate patterns are the rectangular pattern or the staggered pattern. However,

21

the staggered pattern enables a better blast energy distribution through the bed and results in

more uniform and consistent rock breakage. Therefore the staggered pattern is used most

often.

The parameters associated with drill patterns are Burden and Spacing. Burden is the distance

to the drill hole from the face of the bench while spacing is the distance between adjacent

holes of the same row. At the Aruwakkalu Mine ,

Burden = 2.5 metres

Spacing = 2.8 metres

The above burden and spacing with the staggered hole pattern has been proven to be the most

suitable configuration in terms of fragmentation and explosive utilization.

Figure 2.9 : A typical Staggered Drill Pattern

The Burden, Spacing, Depth of Hole and the no of holes in drilled in the bed can be used to

calculate the production volume of a blast. Since the volume of a bench can be calculated by

multiplying the three spatial dimensions, length, breadth and depth, by multiplying the result

with the density of the rock gives the production tonnage. This calculation can be illustrated

in the formula below.

T = S ∗ B ∗ H ∗ N ∗ ρ

Equation 2.2 : Calculating Blast tonnage

S - Spacing : Distance

between adjacent drill

holes in a row

B - Burden : The distance

from the free face

(between rows)

22

Where,

S - Spacing (m)

B - Burden (m)

H - Depth of Drill Hole (m)

N - Number of Drill Holes

ρ - Density of material (MT/m3)

and, T - Blast Tonnage (MT)

The densities of material encountered at the Aruwakkalu Quarry are as follows,

Reject material-2.0MT/m3

Low grade Limestone - 2.2 MT/m3

High grade Limestone - 2.4 MT/m3

In addition to the staggered drill pattern, during special circumstances a radial drill pattern is

used. The radial pattern is used when performing base blasting where there is no bench face

for the rock to break into. In this case a cut hole is drilled in the middle and the other holes

are drilled radially. The cut hole provides the space for the blast to break into. The delays are

arranged so that they increase radially outward. This ensures that the blast will collapse

towards the centre of the cut hole.

2.2.2.4 Hazards encountered in Drilling and their mitigation

1. Lightning

Lightning poses an extreme danger. The climate of the Puttalam area gives rise to

sudden weather changes and can result in sudden stormy conditions and thunder and

lightning. Being situated beside the lagoon, the quarry is also affected by micro

climatic conditions which can aggravate the said weather conditions. Since the

vertical drill boom is the highest part of the open quarry, that becomes more

Figure 2.10 : Burden, Spacing and Hole

Depth of a Bed

23

susceptible for a lightning strike. This is an extremely hazardous situation for the

drillers.

To avoid such dangerous situations, at the slightest indication of a drastic weather

change, the drillers are instructed to immediately stop drilling and to take safety

precautions.

2. Unstable Benches

Pure limestone being a soft material, the strength of limestone beds is not uniform,

and can lead to bench failures especially if a drill goes towards the edge of the bed.

Such situations can cause falls from high benches and lead to equipment and

personnel damage. Therefore Drillers are advised to be vigilant when drilling on

benches. In addition to this, when drilling the row closest to the face, a safety

clearance is kept. However, we observed drilling taking in place in precarious areas in

unavoidable circumstances.

3. dust generation

Drilling creates a lot of dust, Since the flushing medium is also air, the fine dust from

the drill steel spreads everywhere. The drillers are equipped with dust masks to

protect them from dust inhalation.

4. loud noise

The loud noise cause by the Drilling machinery over a long time of exposure can

cause hearing damage to personnel. While ear plugs and muffs are available, only a

handful of operators use them. This safety provision can be improved further by

distributing and emphasizing the value of sound protective gear.

5. Drilling during the Night

During certain circumstances, such as when a higher production is required in a short

amount of time, Drilling is done during the night shift. When drilling at night, a small

lamp is lit at the site for illumination. However, this lamp only illuminates the

immediate vicinity and low visibility in areas beyond can cause accidents.

To avoid these situations, night drilling can be avoided as much as possible. But if

there is no choice, a better set of lights to illuminate the area better would increase

safety of the drillers

24

Figure 2.11 : Drilling at Night

2.2.3 Blasting

The main purpose of blasting is to crack, fragment an loosen the limestone beds. Explosives

are charged into the drill holes and detonated electrically. The quantity of explosives to be

used for each blast are calculated to comply with requirements. Planning and stock control of

explosives are performed with computerized applications and matters related to explosives

and blasting are carried out with Army and Navy supervision.

2.2.3.1 Explosives

Two main types of explosives are used. A cartridged secondary explosive is used to crack and

fragment the rock and an blasting agent is used to provide the heaving power to separate the

cracked rock. The electric detonator (ED) contains a primary explosive which is used to

initiate the secondary explosive cartridges.

The cartridged explosive used at the quarry is Dynamite or Water gel. During the first half of

our training period we used dynamite, while during the latter stages of our training period

new stocks of water gel arrived and we received experience on handling water gel as well.

The blasting agent used at the quarry is ANFO

25

2.2.3.1.1 Dynamite

Dynamite is a nitroglycerine based explosive that is

commonly used for rock blasting operations. It comes in

cartridge from which consists of a mixture of Nitroglycerine,

Sodium and Ammonium Nitrate, Wood meal and other

additives formed into a cylindrical shape with 25mm

diameter and 200mm length and wrapped with paper. It has

a higher detonation pressure than water gel and this results

in a lesser quantity of required for blasting. (Refer Table 2.4 ). The dynamite used at the

Aruwakkalu Quarry were imported from India through the Sri Lanka Navy.

The advantages and Disadvantages of Dynamite are summarized below.

Table 2.2 : Advantages and Disadvantages of Dynamite

Advantages Disadvantages

Higher detonation pressure

Produces better fragmentation

No residue remains after blasting

It's a "Headache explosive" (generates

headache inducing fumes).

Expensive

Over time, Nitroglycerine leaches away from

the cartridge reducing its effectiveness.

Figure 2.12 : Dynamite

Cartridges

26

2.2.3.1.2 Water Gel

Water gels, also known as "Slurries" are 3rd generation explosives and were developed as a

safer alternative to Nitroglycerine based explosives such as dynamite. A typical water gel or

slurry, is a mixture of oxidizing salts such as Ammonium or Sodium Nitrate, a fuel sensitizer,

aluminum powder, gelatins such as Guar-gums and cross linking agents dispersed in water.

This mixture has a silvery colour and a gelatinous texture and is cap sensitive. It is filled into

a plastic casing and covered with a cap to prevent spillages. Water gel used at the

Aruwakkalu Quarry is manufactured in Sri Lanka.

The Advantages and Disadvantages of water gel are listed below

Table 2.3 : Advantages and Disadvantages of Water gel

Advantages Disadvantages

Cheaper than Dynamite

It is a "Non headache explosive"

The plastic casing prevents from explosive

components leaking

Has a lower detonation pressure than

dynamite

Lesser fragmentation compared to an equal

quantity of dynamite

Residual pieces of the plastic casing may

Figure 2.13 : Water gel Cartridges

27

Easier to handle and charge

Resistant to water

remain after blasting

Explosive can deteriorate over time due to

separation of ingredients in mixture

2.2.3.1.3 ANFO

ANFO is a widely used blasting agent and is

prepared by mixing Ammonium Nitrate and

fuel oil to a ratio of 95:5 by weight. Hence its

name (Ammonium Nitrate + Fuel Oil)). At the

Aruwakkalu Quarry, 2 litres of diesel is

poured into a 25kg bag of prilled Ammonium

Nitrate and is mixed well. It is not cap

sensitive and requires to be primed by a high

explosive such as dynamite or water gel.

Ammonium Nitrate provides high borehole

pressures and helps to further propagate

cracks formed by the dynamite and also

provides heaving power to separate the

fragmented rocks. Ammonium Nitrate is most

effective when it is used in the right quantity and in the absence of water. For this reason it

must be ensured that the drill holes are dry when using ANFO. This is further discussed in

section 2.2.3.7.

2.2.3.1.4 Electric Detonators (ED s)

Electric Detonators contain a primary explosive at their base and is ignited by a electrical

fuse. The sudden detonation of the small quantity of primary explosive sets off the detonation

in the attached secondary explosive attached as the primer (water gel or dynamite). Most

electrical detonators contain a delay element before the priming charge. The ED is given a

Figure 2.14: A bag of Ammonium

Nitrate

28

Delay Number depending on its delay. These delay numbers represent gradually increasing

delays with steps of 25 milliseconds. Delay numbers of EDs are required to time the blast and

to control the way the muck pile is formed.

Figure 2.15 : Schematic and an image of an Electric Detonator

2.2.3.2 Explosive Handling and Storage

When a blast is to take place, firstly the number of holes and the hole pattern is observed and

recorded. Then the amount of each type of explosive is calculated and details are filled into a

"Goods Issue/Goods Return form" commonly abbreviated as "GI from". Details about the

delay pattern, ED delay breakdown and also the wiring pattern are also included into the GI

from. A later revamping of the GI from format made fields for including the specific charge

as well.

Once the GI form is filled it is authorized by the Mining Engineer or Quarry engineer and

sent to the security officer. The Security Officer notes down the explosive requirements from

the GI form and heads over to the quarry police along with either Navy or Army personnel to

obtain keys to the explosive magazine.

The explosive magazines are situated away from the quarry office and quarry pit, and in

direct proximity to the Quarry Police where police officers guard the magazines at all times.

Two storage buildings, one for Dynamite/Water gel and another for Ammonium Nitrate

which is the primary component of ANFO constitutes the explosive storage. Electric

29

detonators are housed in a separate compartment in the Dynamite storage building. Both

buildings belonging to the explosive magazine are heavily secured with locks and the

dynamite and ED containing building has a protective fence around it. In addition to this

other safety measures such as lightning conductors, fire retardants and fire extinguishers and

warning signs have been installed.

After accessing the explosive magazine, the required amount of explosive material is taken

out and transported separately. Ammonium Nitrate bags are transported by tractor to the fuel

tanks to be mixed with Diesel and produce ANFO. Dynamite and Electric detonators are also

transported to the bed to the blasted in two different vehicles, both under supervision of Army

or Navy personnel.

2.2.3.3 Charging

Once the explosives arrive at the blasting bed, charging begins. The steps involved in

charging a blast are as follows.

1. The explosives and the electric detonators are distributed among the drill holes

according to their proper quantities (refer Table 2.4).

2. An electric detonator (ED)is inserted into one cartridge - in water gel, the plastic cap

is removed, the ED pushed is pushed into the gelatinous mass and the cap secured

again. In the case of dynamite, the ED can be directly pushed into the cartridge

through the paper folding at the end of it. (refer Figure 2.16)

Figure 2.16: A primed water gel cartridge couple

30

3. The primed cartridge (the one with the ED in it) is coupled with another cartridge and

is tied with the wire accompanying the ED, and slowly lowered into the hole. If the

depth of the hole is more than 9m(3 rod) then another wire has to be attached to the

ED wires. When attaching an extra length of wire it should be connected at different

points vertically as shown in Figure 2.17, so that it wouldn't cause a short circuit.

Figure 2.17 : Connecting an extra wire to an ED

4. The remaining cartridges assigned to the hole are also dropped into the hole and, the

correct amount of ANFO is also put into the hole and tamping is performed.

5. The remaining portion of the hole is filled by quarry dust or surrounding soil as

stemming.

6. In this arrangement, the primed and other cartridges are at the bottom of the hole with

ANFO on top of it finally covered by stemming. This arrangement is known as the

indirect initiation. For holes up to 9m this method suits well. However, in the case of

deeper holes, the primer being at the bottom of the hole can lead to insufficient crack

development at the top portion of the bed. Therefore, in these cases a method called

"Deck Charging" is used. In this method two primers are used, one at the bottom of

the hole and one at the middle. (shown in the right hand side of Figure 2.18). These

two EDs are connected in series.

31

Figure 2.18 : Normal and Deck Charging

7. This leaves only the two ends of the wires protruding from each covered hole and the

bed is now ready for wiring.

The typical quantities of each explosive used in the different types of blast are listed below.

Table 2.4: Quantities of Explosives Used

Typeof Blast

Type of Explosive

3m hole blast

(1 rod)

/per hole

6m hole blast

(2 rod)

/per hole

9m hole blast

(3rod)

/per hole

12m hole blast

(4 rod)

/per hole

Dynamite 250g

(2 cartridges)

750g

(6 cartridges)

1000g

(8 cartridges)

1250g

(10 cartridges)

Water gel 500g

(4 cartridges)

1000g

(8 cartridges)

1300g

(10 cartridges)

1500g

(12 cartridges)

ANFO 5kg

12.5kg 20kg 25kg

Electric Detonator 1 1 1 2( deck charging

32

*cartridge weight of dynamite = 125g, cartridge weight of water gel = 130g, weight of ANFO

bag = 25kg

2.2.3.4 Blast Wiring and Detonation

Once charging has been completed wiring has to be done. The Quarry is equipped with a

generator and a battery operated exploding machine. The generator is a diesel powered AC

(alternating current) generator capable of voltage output of 240V. The exploding machine

produces a very high voltage via capacity discharge, but a significantly lower current. Due to

inconsistencies in the generator, most often the exploding machine is used for detonation.

Therefore, for the entire blast to be properly set off, the resistances should be balanced so that

an appropriate amount of current and voltage reaches all EDs.

The way of achieving this in the Aruawakkalu Quarry is, by using a "series parallel circuit" in

blast wiring. To do this, the EDs are connected n separate loops with each loop having about

8 EDs. These loops are connected to a main wire drawn across the bed in parallel. Figure 2.19

shows a typical series parallel arrangement of 32 hole blast with 4 loops with 8 ED's

connected in series in each.

Once the loops are made, before connecting them to the main wires, the loop resistances are

checked with a blast Ohm-meter. the resistance of the loop should be equal to the resistance

of on ED multiplied by the number of EDs in the loop since they are in series. The resistance

of an ED with its connecting wire is about 12. If all the resistances are correct, the loops are

attached to the main wires as shown in Figure 2.19

Figure 2.19 : A Series Parallel Circuit with 4 Loops

33

In this arrangement, two loops are connected to a single node point in the set of main wires.

This does not alter the circuit and lesser node points reduces the likelihood of connection

errors as well. The circuit diagram for the above wiring pattern is as follows

Figure 2.20 : Circuit Diagram for Wiring Pattern

Once the circuit is completed, the total resistance of the circuit is once again measured using

the blast Ohm-meter.

The calculation of the total resistance for the above example is done as follows.

𝑅 = 𝑅1 + 𝑅2 + 𝑅3 + ⋯+ 𝑅𝑛

Equation 2.3 : Resistance in a Series Circuit

1

𝑅=

1

𝑅1+

1

𝑅2+

1

𝑅3+ ⋯+

1

𝑅𝑛

Equation 2.4 : Resistance in a Parallel Circuit

Resistance of a loop, given resistance of a single ED = 12.

Rloop = 12 * 8 = 96

Let. R be the total resistance. Then,

1

𝑅=

1

96+

1

96+

1

96+

1

96

34

1

𝑅 =

4

96

𝑅 = 96/4 = 24

If the number of holes does is not easily divisible to equal loops, looping is done by

connecting lesser number of EDs to the loops at the far end of the blasting bed, where the

main wire starts (the side farthest from the exploding machine). This is done to compensate

for the increase in resistance by the length of wire drawn to the far side of the bed. This

procedure is followed especially when large beds are blasted.

Once the circuit is connected, the main wire is drawn to a distance exceeding 200m away

from the bed. It should be ensured that the blast circuit along with the main wire drawn to a

distance of 200m should not give a resistance more than 70. This is checked by using the

blast Ohm-meter. By this time, all vehicles and personnel in the quarry are informed and

evacuated from the quarry. After another final safety inspection and a setting off a loud siren,

the blaster uses the exploder to detonate the blast. The blaster detonates with a shelter nearby

to take cover in the case of fly rocks.

Once the blast has occurred and dust has settled, an inspection of the bed is carried out to

assess the level of fragmentation and also to check for any charged holes that did not fire. If

intact explosives are found they are gathered and handed over to the security officer to be

stored in the explosive magazine separately until they can be disposed of during the next

blast.

2.2.3.5 Specific Charge

Specific Charge refers to the quantity of explosives required to blast unit volume of rock. At

the Aruawakkalu quarry, specific charge is calculated for each blast and is monitored and

maintained. It is expressed in units kilogram per metric tonne (kg/MT). At Aruwakkalu, the

stipulated limit of specific charge is 0.15.

𝑆𝑝𝑒𝑐𝑖𝑓𝑖𝑐 𝐶𝑕𝑎𝑟𝑔𝑒 = 𝑊𝑒𝑖𝑔𝑕𝑡 𝑜𝑓 𝐸𝑥𝑝𝑙𝑜𝑠𝑖𝑣𝑒𝑠 (𝑘𝑔)

𝐵𝑙𝑎𝑠𝑡 𝑇𝑜𝑛𝑎𝑔𝑒 (𝑀𝑇)

Equation 2.5 : Specific Charge

Weight of explosives is the total weight of Dynamite/Water gel and ANFO utilized for the

blast. The blast tonnage is calculated using Equation 2.2.

35

We calculated the specific charge for all the blasts we were involved in. The specific charge

serves as a check for the amount of explosives used and is also required for keeping records.

In the reformatting of the Goods Issue/Return form (GI form) a field for specific charge was

also included indicating that specific charge be calculated before the blast and not afterwards.

The limit of 0.15 for the specific charge at the Aruwakkalu Quarry has been selected to keep

in accordance with the explosive usage stipulated by the Geological Survey and Mines

Bureau (GSMB) and also to avoid negative impacts of blasting such as excessive ground

vibration and fly rocks.

2.2.3.6 Other types of Blasting

In addition to the main bench blasting at the quarry we experienced other types of blasting as

well.

2.2.3.6.1 Boulder Blasting

Sometimes, bench blasting produces very large boulders

that are unable to be hauled and are difficult to handle.

These boulders are therefore left in the quarry. While

rock breakers can be used to break these rocks, due to the

large size and the time taken to fragment them using a

rock breaker, it is a very uneconomical process. Using a

rock breaker is also not an option if isolated boulders

have to be broken.

For this reason, boulder blasting is preferred to fragment

these rocks and also add them into production. Boulder

blasting requires relatively a lesser amount of explosives

and also is quicker. Therefore it is cost effective

Most large boulders which are separated from the beds

contain undisturbed, remaining portions of drill holes in

them. This makes the blasting process easier because the

explosives can be charged into the drill hole itself. This is

illustrated in the left hand image of Figure 2.23. In this situation the primed explosive

cartridge is dropped into the middle of the drill holes and confined tightly with clay.

Figure 2.21 : Charging a Drill

Hole in Boulder Blasting

Figure 2.22 : Fragmentation

after Boulder Blasting

36

If there are no drill holes present in the boulder, a confined space such as a crevice or a corner

is used to keep the cartridge and it is covered very well with clay as seen in the right hand

side of Figure 2.23. Once the cartridges are set up a wire is draw to a safe distance and

detonated using the exploder.

It should be noted that ANFO is not used in boulder blasting since only fragmentation of the

rock is required. Therefore a detonator and explosive cartridges would suffice. Boulder

blasting could give rise to fly rocks therefore necessary precautions should be taken.

Figure 2.23 : Methods of Boulder Blasting

Once the boulder has been fragmented, the pieces can be collected with a wheel loader and

can be hauled along with the other material.

2.2.3.6.2 Base Blasting

Most high quality material is located at the bottom most layers of the limestone formations.

For this reason, at times the necessity to excavate material below the base of the quarry

arises. In these situations, sometimes the excavator is used to excavate the base. However if

large areas of the base needs to be extracted, base blasting is used.

There are two main challenges in base blasting. Firstly, since the water table lies below the

base, the drill holes get filled with water. Since ANFO does not detonate with water, this

leads to problems. Secondly, unlike in bench blasting and boulder blasting, there is no space

37

for the material to break into in the case of base blasting, and can lead to insufficient

fragmentation.

To overcome the first problem of water in the drill holes, the ANFO is loaded into polythene

liners and sealed to make watertight ANFO cartridges. These cartridges are lowered into the

holes with water. Priming with water gel is done in the usual manner.

The second problem is overcome by drilling a cut hole round of a radial drill pattern. The

centre cut hole round provides the space required for the surrounding rock to break into. The

delays of the detonators in the radial drill pattern are arranged with the lowest delay at the

centre and the delay numbers increasing radially outward.

2.2.3.7 Problems Encountered in Blasting

We encountered several problems related to blasting and we experienced the ways to avoid

them and also to correct them.

2.2.3.7.1 Blast Circuit Problems

Often in large blasts involving lots of wiring and connections, circuit problems such as

disconnections short circuiting can occur. To avoid these problems, the circuit is checked

stage by stage using the blast Ohm-meter. However, occasionally after the circuit has been

completed and while checking, faults can appear. Handling this problem has to be done

systematically in order to save time and to avoid disturbing the rest of the circuit.

If a faulty loop is found after connecting them to the main bus wire (this is indicated by an

anomalous Ohm-meter reading) first the loop has to be disconnected from the main wire and

connected to a separate testing circuit. In the testing circuit, as shown in Figure 2.24, each ED

is tested systematically until the faulty ED or connection is found. If there is no fault, as the

connector wire (indicated in blue in the diagram) is connected to the indicated nodes, the

Ohm-meter reading should increase each time by a factor equal to that of the resistance of a

single ED (12 ). Once the faulty ED or the faulty connection node is located, it is adjusted

or in extreme cases, removed and the circuit is reconnected.

38

Figure 2.24 : Testing Circuit

2.2.3.7.2 Water in Drill Holes

When water is present in drill holes ANFO does not detonate.

This degrades the quality of the blast and reduces its power.

Blasts which have been degraded by water in this manner

emanates characteristic yellow fumes during the blast.

To avoid this, ANFO is loaded into plastic liners and

charging is done as explained under Base Blasting. To avoid

rain water seeping into drill holes, the holes are properly

covered with a tarpaulin.

2.2.3.8 Hazard Management in Blasting

1. Fly rocks : Fly rocks presents the most immediate danger of blasting. While there are

no permanent residents around the quarry area it poses a danger to the blaster and

other personnel present at the time of blasting.

To avoid Fly rocks the quantity of explosives used must be controlled. By checking

the specific charge before each blast and optimizing the amount of explosives used,

Figure 2.25 : Yellow

Fumes when Blasting

39

this is taken care of to a major extent. Proper stemming and tamping also helps to

minimize fly rocks.

2. Air Blast and Ground Vibrations: This too causes the greatest discomfort and

potential danger to the personnel of the quarry, since there are no permanent residents

around the quarry area.

To minimize the impact of air blast over pressure and ground vibrations, proper

charging practices must be employed. By using appropriate delays in the detonators

and by employing a suitable hole pattern also these negative impacts can be

minimized.

3. Dust and Fumes : Blasting produces lots of dust. Also if water is mixed with ANFO at

the time of blasting, Sulfur is produced and it gets dispersed as yellow fumes. While

dust cannot be prevented, avoiding drill holes filed with water will not produce the

toxic yellow fumes.

Most of the above situations are alleviated if the personnel stay at a safe distance from the

blast. This is practiced at the quarry by always maintaining a safe distance of more than

200m. However we observed that tamping is not performed properly in charging.

Improvement on this front could help further reduce the risk of fly rocks and to reduce the air

blast over pressure.

2.2.4 Activities Carried Out by Us

Out of the many activities and projects assigned to us we carried out several projects related

to Drilling and Blasting. Given below is short summary of such activities.

2.2.4.1.1 Explosive Magazine Refurbishment

The explosive magazine at the Aruwakkalu Quarry is well maintained. However, in order to

improve its standard and also in preparation for an audit, a refurbishment was carried out.

While the main building itself remained unchanged, a protective wall, a fence with a lockable

gate, and a concrete base in front of the magazine building doors were constructed.

40

We were assigned to prepare a checklist to identify other possible improvements and to

implement those improvements. The areas we identified and that needed attention are,

Inadequate safety sign boards

Stacking of explosives too high, No Stacking line

Fire risk in the surrounding area (dried bushes etc)

No Proper labeling

Multilingual Signboards were prepared to prohibit smoking and fire hazards in the vicinity of

the explosive magazine. These signboards were hung on the newly prepared gate. Signboards

warning that rock blasting is taking place were also prepared to be erected near the quarry.

Figure 2.26 : Signboards for the Explosive Magazine

Boxes containing explosive

cartridges such as dynamite or

water gel should be handled

carefully and should not be piled

into stacks that are very high. This

makes the boxes susceptible to

toppling and also creates a risk of

pressure initiation. The explosive

magazine does not have a stacking

line to indicate the maximum

stacking height of boxes. Therefore,

we marked a stacking line along the inside walls of the magazine.

Figure 2.27 : Stacking Line

41

This stacking line corresponds to the height of six boxes kept on top of each other, an

accepted safe height of stacking. Once the stacking

line was in place we also made sure that only boxes

that have not been opened remained in stacks as

partly empty boxes increases the risk of toppling.

The loose cartridges were transferred to one box and

was labeled properly with the number of loose

cartridges in it. This system if arranging and labeling

ensures that there are no partly empty boxes lying

around while all loose cartridges are kept at one

place. This system saves time in sorting out and

counting explosives.

The area surrounding the explosive magazine had a lot of dried plants and shrubs. Since this

increases the risk of fire propagating, the entire area was cleared.

2.2.4.1.2 Explosive Stock Control Application

After every blast the GI form is sent to the store keeper to update stock records. This data is

then entered into an excel spreadsheet to maintain proper records. Periodically these record

are matched by physical checks at the explosive magazine. The system used so far had some

inconsistencies and some data had to be entered separately. We prepared a new system where

these inconsistencies were sorted out and so that all data can be entered and reviewed in one

document.

This excel sheet had columns for inputting data about daily usage of explosives and

detonators along with their delay numbers. and it would deduct them from the existing stocks

and display the remaining stocks. we checked with data of several physical checks to remove

any inconsistencies.

2.2.4.1.3 Plan for a New Ammonia Hut

The current ammonia hut at the Aruwakkalu quarry is situated near the quarry police and the

dynamite storage building. This hut is made from a lockable container box and is well

secured. However, the space in the container and around is limited and Ammonia has to be

re-stocked quite often. It also lacks the facility to mix ammonia with diesel to prepare ANFO.

Figure 2.28 : The refurbished

Explosive Magazine

42

To overcome these difficulties, a plan for the new Ammonia Hut was drawn by us. This new

design has double the storage capacity of the existing one, and also has the facility and space

for mixing ANFO. It was also designed so that it can be accessed by the tractor so that ANFO

bags can be loaded easily. The stage of the ammonia hut designed to be elevated to the height

of the tractor trailer so that loading can be more streamlined.

However construction work of this ammonia hut did not begin during our period of training.

Figure 2.29 : Plan of Proposed Ammonia Hut

43

2.3 Loading, Hauling and Dispatching

The loading, hauling and dispatching operations of the Aruwakkalu quarry are performed by

Holcim itself. Once the limestone beds are blasted, the dozer shoves them and creates

material piles. A wheel loader loads this material into the a fleet of dump trucks which then

haul them to mix beds. From the mix beds, the material is loaded into railway wagons and

dispatched.

2.3.1 Loading and Hauling Machine Fleet

Holcim owns and operates a primary fleet of loading and hauling machines. This fleet

consists of the following machines.

2.3.1.1 Komatsu WA600 Front End Wheel Loader

This is the largest machine of its kind in Sri Lanka. It has a bucket capacity of about 6 cubic

metres. This means that it can handle about 10 metric tonnes at a time. This enables the

loader to load the 32 tonne dump truck in just six passes. The machine is maintained under a

maintenance contract by DIMO with the undercarriage maintenance done by Holcim.

Figure 2.30 : Komatsu WA 600 Loader

2.3.1.1.1 Fuel Consumption of loader

We carried out a project to assess the performance of the wheel loader. Wheel loaders are

equipped with a torque converter based transmission system and constantly changes gears

between forward and reverse. Therefore, a lot of power in consumed, leading to a higher fuel

consumption. The high torques involved in loading also leads to a high fuel consumption.

44

Therefore we used the daily records kept by the management to isolate performance related

data. Using this data and correlating it with the diesel quantities pumped into these machines

we obtained the average fuel consumption rate.

Given below is a summary of the analysis conducted with data gathered over 11 months in

the year 2013. We grouped the data according to the two shifts as a way of comparing the

performance. The working hours indicated in the table below were obtained by using the start

and end meter readings of the machine at the end of each shift of work. We also extended this

analysis for each operator in order to determine a parameter to measure performance of the

operator in the wheel loader. However to truly measure performance, other data would also

have to be included.

Table 2.5 : Fuel Consumption of WA 600 Wheel Loader

WA 600 Loader

Shift A Shift B

Month Working Hrs Diesel Working Hrs Diesel

Jan 16.8 884.25 66.2 3809

Feb 41.9 2834.9 83.2 5070

Mar 24.6 1276.4 81 3612

Apr 22.2 1431.8 54.7 3786

May 3.5 335 53.5 3016

Jun 42.3 4294.2 70.4 5296

Jul 52 2373.8 68.6 3225

Aug 16.8 972 67.8 3736

Sep 29.1 1640.2 98.3 6345

Oct 58.9 3075.9 99.3 6060

Nov 60.5 4323.3 45.3 3664

45

Total 368.6 23442 788.3 47619

Fuel Consumption 63.5964831 60.40720538

From the above table it can be seen that the wheel loader approximately consumes 60 litres

per hour. This makes it necessary to refuel the machine every day.

2.3.1.2 Komatsu HD 325A Dump Trucks

There are three of these dump trucks employed for hauling purposes. They are also managed

by DIMO with the undercarriage maintenance done by Holcim. The three dump trucks are

named KD 7, KD 8 and KD 9 with the KD 9 being the latest addition to the fleet and also in

the best condition. Several projects and activities relating to dump trucks were carried out by

us. They are described below.

Figure 2.31 : Komatsu HD 325 A Dump Truck

2.3.1.2.1 Hauling Cycle Times

The first activity we were given was to measure cycle times of the dump trucks. For this we

got into the truck during a shift and travelled in it with the operator while gathering data.

While gathering data, we also learnt the key operations and the safety features of the truck.

Since we travelled in different trucks during each time, we did not conduct a cycle time

analysis for each truck. Instead we gathered all the data and prepared an average set of data

with them.

46

Table 2.6 : Dump Truck Cycle Times

Loading

Time

Hauling

Time

Dumping

Time

Travel Back

time

Cycle

Time

1 6 1 4 12

1 5 1 5 12

1 6 2 5 14

2 6 1 4 13

2 6 2 6 16

1 4 2 6 13

2 5 1 6 14

1 4 2 4 11

2 6 2 4 14

2 4 2 6 14

1 5 2 4 12

2 4 1 4 11

1 6 2 4 13

1 6 1 5 13

2 5 1 6 14

2 6 1 4 13

Average Cycle Time 13.0625

*Values are to the nearest Minute

47

The above table summarizes only a handful of data gathered by us. According to the above

data, the cycle time of a typical truck is about 13 minutes. However, for calculation purposes

the cycle time is taken as 15 minutes.

Cycle time such as the above we collected is an important factor in determining the

performance and output of a quarry. Since the cycle time is directly correlated to the amount

of material hauled, it can be used to prepare models regarding quarry output.

Also, when designing new quarry roadways, ramps and other infrastructure, the cycle time

has to be considered because with an increase in road distance, the cycle time increases and

the hauling tonnage per unit time drops. Therefore they should be designed by taking the

cycle time into consideration.

Cycle time is also a useful tool in optimization of the quarry. A very high hauling cycle time

would mean the loader and the mix bed preparing dozers would idle. This is a fuel wastage.

A low cycle time would mean that there would be queues at the hauling or dumping point

which in turn leads to the idling of the dump trucks which again results in a fuel wastage.

2.3.1.2.2 Tyre Analysis

The performance of machinery and their availability plays a major role in the productivity

and output of a mine. For this reason, every aspect of the machines should be properly

maintained. The tyres of these machines are what keeps the machine in contact with the

ground and bears the weight of the machine. While tyres for mining machinery are designed

to withstand a beating, incorrect maintenance can reduce lifetime of the tyres, or ultimately

lead to catastrophic accidents.

Therefore proper record keeping of tyres is essential for a mine. Such tyre records assists in

large way to the maintenance of tyres and also helps to measure performance of the tyres.

Since these tyres of heavy machines are expensive, proper record keeping is essential to make

the maximum use of the tyres.

Detailed tyre record are available at the Aruwakkalu quarry and these record are updated and

maintained by the maintenance division. We analyzed these tyre records and extracted vital

information regarding them. Information about tyre wear and lifetime of tyres were obtained

by using data about tread depth of tyres over time.

48

We also measured tread depth periodically and updated these tyre records.

Table 2.7 : Tyre Records

Tire

Brand

Tire Serial

No

Type Position Date of

Installatio

n

Tread

remainin

g (mm)

amount

of Wear

Current

Status

Triangl

e

1201051350

1

Radial NA NA 22 29 Not running

Triangl

e

1201083350

1

Radial NA NA 21 30 Not running

Triangl

e

1112261350

2

Radial NA NA 9 42 Not running

Triangl

e

1201092350

2

Radial NA NA 19 32 Not running

Triangl

e

1112292350

1

Radial NA NA 33 18 Not running

Triangl

e

2211192340

1

Radial RRI 14/1/2013 9 42 Running

Triangl

e

2211152350

2

Radial RRO 3/1/2013 10 41 Running

Triangl

e

2211191340

2

Radial RLI 3/1/2013 33 18 Not running

Triangl

e

2211173350

1

Radial RRO 30/5/2013 20 31 Not running

Triangl

e

2211173350

2

Radial RRI 30/5/2013 11 40 Not running

Triangl 2211133340 Radial RLO 30/5/2013 15 36 Running

49

e 1

Triangl

e

2211191350

1

Radial FL NA NA #VALUE

!

Not running

Triangl

e

2211183340

1

Radial FR 11/1/2013 24 27 Not running

Triangl

e

2304222360

2

Radial FR 6/6/2013 45 6 Not running

Triangl

e

2304222360

1

Radial FL 6/6/2013 20 31 Running

Triangl

e

2304211360

2

Radial FR 6/9/2013 7 44 Running

Triangl

e

2304193360

1

Radial FL 6/9/2013 43 8 Not running

Triangl

e

2304133360

1

Radial RRO 6/6/2013 28 23 Running

Triangl

e

2304162360

1

Radial RRI 6/6/2013 24 27 Running

Triangl

e

2307053360

1

Radial RRI 30/10/201

3

39 12 Running

Triangl

e

2307061360

2

Radial RRO 30/10/201

3

39 12 Running

Triangl

e

2307052360

1

Radial RLI 30/10/201

3

40 11 Running

Triangl

e

2307042360

2

Radial RLO 30/10/201

3

39 12 Running

Triangl 2307171360 Radial FR 30/10/201 39 12 Running

50

e 1 3

Triangl

e

2307051360

2

Radial FL 6/10/2013 39 12 Running

Triangl

e

2307041360

1

Radial FL 6/11/2013 39 12 Running

Triangl

e

2307182360

2

Radial RLI 15/01/201

4

48 3 Running

The above table shows some tyre records. Some fields have been removed for brevity. The

position indicated abbreviations are as follows

Figure 2.32 : Tyre Positions

Using these tyre records we were able to extract information about its rate of wear and thus,

by calculating the time it takes a new tyre to wear to such a rate that it has to be discarded, we

calculated the predicted lifetime of a new tyre as follows.

"Discarded" Tires

Average Lifetime = 1880.625

FL - Front Left

FR - Front Right

RLO - Rear Left Out

RLI - Rear Left In

RRO - Rear Right Out

RRI - Rear Right In

51

Some of the tires encountered at the Quarry had performance problems due to faults such as

peeling off of the tread, swelling of sidewall and cracking of the rubber. These faults

significantly degraded the tyre and resulted in shorter running times.

To rectify this situation, an official from the Triangle Tyre cooperation came to inspect the

conditions and also educated us about general tyre handling. We gathered a lot of information

about the subject during this visit.

Unit Cost (Rs) = 430763.00

Cost per Hour (Rs) = 229.0531

Tire cost per tonne hauled= 11.45266

average amount of wear

when discontinued(mm) = = 30

average wear = 25.54545

average lifetime = 1750.818

wear rate(mm/hr) = 0.014591

predicted lifetime of new

tire (Hours) = 2056.121

52

2.3.1.2.3 Fuel consumption of Dump Trucks

To calculate the fuel consumption of dump trucks the daily record were used in a similar

manner as was done for the WA 600 loader. Here too, the working hours were obtained by

the start and end meter readings of the machine. This analysis was carried out separately for

the three trucks KD7, KD8 and KD9. The summary of the analysis is given below. The

analysis spans the entire year 2013.

Table 2.8 : Fuel Consumption of Dump Trucks

KD 7 KD 8 KD 9

Month

Working

Hrs Diesel

Working

Hrs Diesel

Working

Hrs Diesel

Jan 56.5 1751.03 0.90 28.29 5.20 180.76

Feb 57.9 1794.42 56.50 1519.89 11.00 324.05

Mar 65.6 2033.06 83.00 2008.05 6.00 160.65

Apr 58.8 1822.31 85.90 2748.28 26.40 1079.28

May 90 2789.26 88.20 2161.66 36.10 1312.46

Jun 109.7 3399.79 39.70 983.92 19.80 527.40

Jul 51.9 1608.47 14.90 393.47 0.00 1052.86

Aug 20.5 635.33 5.30 181.48 23.50 745.92

Sep 67.6 2095.04 25.20 1396.04 17.80 568.83

Oct 88.8 2752.07 13.30 321.28 23.50 668.44

Nov 73.1 2265.50 4.60 125.58 12.70 396.62

Dec 61.7 1912.19 21.90 510.29 24.30 816.00

Total 802.100 24858.471 439.400 12378.236 206.300 7833.257

Average 30.992 28.171 37.970

53

From this analysis it can be seen that the average fuel consumption of the dump trucks at the

Aruwakkalu Quarry is 30 litres per hour. This is significantly lower than that of the loader.

This is because while the dump truck travels a larger distance, it does not exert the engine as

much as the loader does.

2.3.1.3 3rd Party 10-Wheel Haul Trucks

To keep up with higher production needs and to ensure a higher hauling rate, in addition to

the Komatsu Hauling fleet belonging to Holcim, a 3rd party fleet of 10-wheel haul trucks is

also employed at the quarry for hauling purposes. These trucks do not have the capacity of a

dump truck, but by employing several of these trucks along with one or two large dump

trucks, the hauling rate can be increased. These 10-wheel trucks have a capacity of 12 metric

tonnes.

To identify the performance difference between large dump trucks and the smaller 10-wheel

haul trucks we gathered data about each truck and compared them. Data regarding, cycle time

and hauling capacity and fuel consumption were considered.

Later, as an expansion of this project, we also calculated the cost involved in operating each

truck. For the dump truck, the main cost components were, Maintenance fee paid to DIMO,

Undercarriage maintenance including tires, Fuel cost, Operator salaries. The summary of this

calculation is given below.

Table 2.9 : Summary of Dump Truck Cost

Type of cost rate per hour

Diesel 3769.211532

DIMO Maintenance 5265

Undercarriage maintenance 1608

operator salaries 520.8333333

Total (Rs) 11,163.04

54

However, in the case of the 3rd part trucks, a fixed hourly rate of Rs 250 has to be paid per

truck. Therefore since there is a large difference in cost for the two types of hauling trucks,

we compared the hauling capacity and overall performance of the two types of trucks. This

was done to check whether the performance of the dump trucks will compensate for its high

cost.

The summary of the comparison is given below.

Table 2.10 : Comparison of Hauling Trucks

Type of Machine HD-325 Dump Truck 10 wheel truck

Hauling rate (loads per hour) 4 3.5

Maximum Trucks possible 4 7

Tonnes per truck 30 12

Tonnage per Hour 480 294

Cost per Hour (Rs) 44800 10500

Cost per tonne hauled (Rs) 93.33 35.71

While the cost per tonne of the dump truck is higher than that of the 10-wheel trucks, the

tonnage per hour is significantly higher. Since the key factor in meeting daily production

targets is the tonnage per hour, the dump truck compensates on that front.

We took this analysis further and furnished a fully fledged report about the optimization of

Dump Truck Feet. This is explained under Section 2.3.4.1.

55

2.3.2 Hauling roads

Hauling roads are very important in the hauling process. The road distance and road

conditions dictate the rate of hauling and the production rate. The road conditions are also

directly correlated to the machine conditions and dictate how often the machines have to be

repaired. Therefore, the it is important that the roads are well maintained and that careful

planning and design is done in their construction.

2.3.2.1 Road Maintenance

Haul roads have to be periodically maintained. This includes road surface clearing,

smoothening, refilling and cutting operations. The main machine used in road maintenance is

the Komatsu Motor Grader belonging to Holcim. However occasionally, the wheel loader and

the dozer is also used for road work relatively large and complex in nature.

While road surface smoothening and filling is done when required, an activity that has to be

performed continuously on a daily basis is road watering. The reason for road watering is to

minimize dust on the roadways. Excessive amounts of dust reduces visibility and also poses a

health risk.

The road watering at the Aruwakkalu quarry was divided among the companies doing

overburden removing for the quarry. However, concerns were raised about this arrangement

stating that the current arrangement is not fair for all parties involved. Due to this reason, we

decided to prepare a new road watering plan which was fair to all parties.

The basis, for this new arrangement was the "Effective Distance" to be watered. Here,

effective distance means, the distance coupled with the number of passes required to cover

the road. For example, a wide road will have a greater effective distance than a narrower road

of the same length because a higher number of passes are required to cover the road. The

main hauling road required four passes under these arrangement and the other roads required

lower.

Once the effective distance was measured, we measured the lengths of all roadways

belonging to the quarry, including the roadways inside the quarry pit. Next we divided the

effective distance of the entire roadways according to the overburden removal volumes of the

three companies involved, EDC, TML and ISURU. The overburden removal volumes are

also the basis of payment for these companies. Therefore, the dividing the road distances in

this way was deemed fair to all.

56

Next the corresponding GPS points were established which would demarcate the areas of

watering. The respective areas were marked on a map and handed over to the supervisors of

the three companies.

Table 2.11 : Effective Distance in Road watering

Section Distance (m) No. of required

passes

Effective distance

(m)

Inside Quarry 750 2 1500

Main Hauling road 800 4 3200

Quarry entrance

road

500 3 1500

Total 6200

The calculation was done as follows.

Total Effective Distance = 6200 m

Overburden BCM ratio = EDC :TML :ISURU = 6:5:3

Allotted Distances

EDC = 6200*6/14 = 2700m

TML = 6200*5/14 = 2300m

ISURU = 6200*3/14 = 1200m

(Values are rounded to the nearest 100m )

57

Figure 2.33 : Road Watering Plan

2.3.2.2 Planning and Design

Planning and design of the quarry roadways is done both on the short term and long term. To

a great extent planning and design helps to optimize all current operations and also helps the

quarry progress smoothly into the future. Therefore planning vital structures such as

roadways has to be done in anticipation of the changes in the future to avoid costly re-

structuring activities. We were involved in several planning and design activities related to

roadways.

58

2.3.2.2.1 Re-Structuring of the Ramp Area

The ramp area situated near the office and is a place where both heavy vehicles and light

vehicles move about. For safety reasons, efficiency and also aesthetics, it was decided to re-

structure the ramp area.

Under this, the first activity was to isolate the ramp area so that only heavy vehicles can enter

it. We conducted a GPS survey of the new ramp area and then using the data gathered, drew

plans for this new ramp area on AutoCAD and reviewed them. Later this plan was put into

action.

Figure 2.34 : The Planned New Ramp Area

In order to isolate the ramp area, soil bunds were put up. These soil bunds serve two

purposes. It acts as a buffer and provides safety in case of an accidental vehicle slippage and

it also helps to keep out rain water from lowing into the roads. An area was separately created

for parking dump trucks during meal times. Under this arrangement, Light vehicles stay away

from the heavy vehicles and thus safety is ensured.

Dump Truck Parking Area

Isolated Heaps

Area for light vehicles

59

2.3.2.2.2 Hauling Distance Planning

The current quarry is situated at a distance of about 1.5km and the main hauling road

measures close to 3km. As the quarry progresses forward, the cycle distance also increases.

Eventually, the cycle distance will be too much and the machines will start idling and also,

the fuel consumption will also increase. Therefore, it is necessary to keep the cycle distances

in check.

Once the cycle distances reaches an impractical level, a decision has to be made to restructure

the dumping area and if possible move the ramp closer to the quarry pit. In order to do

planning of this kind, the current cycle distances and the rate of quarry progress needs to be

considered. Based on these data, it is possible to estimate the cycle distances of the future.

To conduct this analysis, first we gathered distance data from the dump trucks while

travelling in them and mapped the current haul roads, and their respective cycle distances on

a map. Next using the QSO optimization software, we calculated how far the quarry will

progress and its layout. Then we mapped the future roadways into the new quarry pit, and

calculated the cycle distances accordingly.

The current cycle distances and the cycle distance as projected 10 years into the future are as

follows. According to it, in 10 years, the cycle distance becomes impractically long.

Figure 2.35:

Current and

Future

Cycle

Distances

Current Cycle

Distances

Cycle Distances in 10

years

Projected

future quarry

60

2.3.3 Dispatching

After the quarried limestone is hauled to the ramp and mix beds are prepared (see section

2.4.3: Mix Bed Preparation), The dispatching process begins. According to the limestone

requirements of Palavi, either high grade, low grade or finished grinding material is

dispatched to Palavi via railway.

2.3.3.1 The Dispatching Process

We spent two days studying the dispatching process when the other quarry operations were

ceased due to the Staff Annual Trip of the quarry. The dispatching cycle begins when a train

with an empty set of wagons arrive at the ramp of the quarry. Each train has an average of 25

wagons and each wagon can accommodate 23 tonnes of material. There are two sets of

wagons operating such that while one set of wagons are being transported by the train the

another set of wagons is being filled and prepared at the quarry.

Once the train arrives the shunting operation is performed and the train changes to the track

closest to the loading platform. Then the train attaches itself to the set of filled and prepared

wagons and leaves. This transfer process takes about half an hour to complete.

Once the train leaves, the loading to the empty wagons brought by the train begins. Loading

is done by wheel loaders and loading is done by two loaders at a time and by breaking the

heap and mixing it to ensure homogeneity. Once the wagons are filled, an excavator

compacts the material in the wagons. The machinery used at the ramp are hired machinery

from EDC Ltd. Once compaction is done, the wagons are covered by a tarpaulin to avoid

spillage and to protect from moisture. Once the train arrives again this set wagons is

dispatched.

2.3.3.2 Locomotive Transport

The railway lines from the quarry to the Palavi processing plant is used exclusively for

Figure 2.36

:

Locomotive

Transport

61

limestone transportation and is managed by Holcim with the involvement of the Ceylon

Railways. Two locomotive engines owned by Holcim were used to transport the wagons filed

with limestone during our period of training.

During our study of the dispatching process we observed the train movements and gathered

related data. During our study a derailment of the train and the resulting repairs during the

following days caused delays in train movement. However, on average 7 haul trips are made

per day.

The summary of data we gathered during these one of the three days is given below

Dispatch Details

26-Dec-13

Trai

n No. LSF SR

Mixed

Heap

Arrival

of Train

Departure

of Train

Preparation

Time

Load

Weight(tonnes)

111 131 3.24 MHF 2:35 3:15 0:40 724

112 79 4.17 MLC 7:10 7:55 0:45 656

113 131 3.06 MHF 10:35 11:05 0:30 659

114 221 2.24 FG 16:05 16:45 0:40 624

Total Load for the Day(tonnes) = 2663

Derailment of the train near the 12th mile post and repairing the transfer point for faulty

wagons caused a delay.

62

2.3.4 Activities and Projects

In addition to the activities mentioned above, we also carried out some extensive projects.

They are described briefly in this section.

2.3.4.1 Hauling Fleet Optimization

Hauling activities in the quarry are carried out by a fleet of 3 Komatsu HD 325 dump trucks

and a separate 3rd party fleet of 10-wheel trucks. As discussed in section 2.3.1.3, While the

costs associated with operating the HD 325 fleet are significantly higher than that of the 10-

wheel truck fleet, the dump trucks have a very high capacity and carry almost thrice the

volume of a 10-wheel truck. Thus the other factor that has to be considered is, the fleet size.

Although, dump trucks can haul at a higher rate, technically a fleet with a sufficiently high

number of 10-wheel trucks should be able to haul at the same rate. However, practically the

fleet size is limited by many constraints such as cycle distance, cycle time and hauling

conditions. Therefore we attempted to identify the maximum fleet size in each arrangement.

For continuous hauling to take place, there should not be any trucks waiting in line at the

loading point. This means that the cycle time of one truck should be equal to the time it takes

to load all the trucks in the fleet.

Therefore, by dividing the cycle time by the loading process time, the maximum no. of trucks

that can haul material without interruption can be obtained.

Here, the "loading process" time indicates the total time taken from the entry to the loading

point until the exit. This includes the time taken to maneuver the truck as well.

Costing and hauling rates were computed from data extracted from FMC and Quarry

Performance sheets.

From the data gathered,

Cycle time of Dump Trucks = 15 minutes

Cycle time of 20- wheel Trucks = 17.143 minutes

63

Table 2.12 : Loading Process times of Sump Trucks and 10-Wheel Trucks

Dump Trucks 10 Wheel Trucks

Loading Process

time (hr:min:sec)

Loading Process

time (minutes)

Loading Process

time (hr:min:sec)

Loading Process

time (minutes)

0:02:51 2.85 0:01:55 1.9167

0:04:03 4.05 0:02:20 2.3333

0:04:44 4.7333 0:02:40 2.6667

0:03:51 3.85 0:02:25 2.4167

0:03:53 3.8833 0:02:19 2.3167

0:04:20 4.3333 0:02:31 2.5167

Average Time 3.9500 Average Time 2.3611

Therefore,

Maximum Number of Dump Trucks = 15/3.95 = 3.7975 ≈ 4

Maximum Number of 10 -Wheel Trucks= 17.143/2.3611 = 7.2606 ≈ 7

Also,

Limestone Requirement of quarry = 4500 tonnes

Hours taken to haul by Dump Trucks = 4500/480 = 9.375

Hours taken to haul by 10-wheel trucks = 4500/294 = 15.306

According to Table 2.10 : Comparison of Hauling Trucks, it was seen that the cost per tonne

hauled is significantly higher in the case of dump trucks. However, the above data shows that,

to meet the daily requirement of 4500 tonnes, Dump trucks need to haul for a period of about

9 hours while 10-wheel trucks need to operate for about 15 hours. Therefore the daily

64

limestone target cannot be achieved during a day's work (12 hours effective)by using a fleet

of 10-wheel trucks.

Furthermore this analysis is important because, it highlights the importance of having the

right number of hauling trucks. Smooth hauling operations without any interruptions can only

be carried out with the right number of trucks in the field. Insufficient trucks will result in the

loader idling while too many trucks will result in queues at the loading point and will lead to

trucks idling.

We notices several instances in the quarry where too many trucks caused queues at the

loading point. Therefore this analysis would help to rectify this problem.

Figure 2.37 : Queue at the Loading Point

2.3.4.2 Hauling road level survey and road slope analysis

With the overburden removal process and the filling of the old road, all haulage operations

are expected to be carried out via the new quarry road. Although it had been cleared

previously its gradient and centre line elevations have not been found. In order to find out

these details, We performed a level survey at the new quarry road.

65

The objective of this survey was to calculate the reduced levels along the road, and to find

the gradient variation of the road.

Upon visual inspection it can be seen that the new haul road has quite a steep gradient

especially towards the

latter part of the road,

at the entrance to the

quarry pit. This can be

seen by the 3D model

we created using the

"Surfer" Software by

using the survey data.

This model does not

show the deviation

and curves of the road

but can be used to

visualize the gradient.

Although mine

machinery and dump trucks are able to ascend steep gradients, the gradient of main haulage

roads are limited to less than 7:100. This is because at steep gradients, the automatic

transmission systems found in most of these machines shift to a lower gear which in turn

results in a higher fuel consumption. By maintaining a gentle gradient, the machines will be

able to travel on the road in higher gears thus lowering fuel consumption. Therefore, limiting

the road gradient helps in optimizing machine performance.

The limiting value of the gradient, 7:100 has been arrived at by studying machine operation

over various gradients and conditions and by considering the optimum performance of

machines. This value is an accepted standard and is also specified in the Quarry Process

Manual of Holcim Lanka Ltd. Therefore we also calculated the required fill heights in order

to maintain the gradient of the road below 7:100 while minimizing the volume that would

need to be cut for this purpose.

We adopted the standard leveling procedure and the collimation method was used to book the

readings. For the flat part of the road, we used a station interval of 30m, while for the latter

part where steep slopes are present, we chose an interval of 20m.

Figure 2.38 : 3D Model of road created using Surfer

66

After carrying out the survey and booking the readings, we entered all data into an MS Excel

sheet and calculated the gradient variation of the road. Using this gradients we calculated the

fill volumes required to bring the overall gradient to a manageable level. We used two

approaches to calculate the fill volume.

In method 1, since the road starts inclining steeply downwards starting at the 1080 m point,

Filling heights were calculated from the 1080 m point. Thus the proposed road surface begins

at the 1080 m point. This method neglects the small local variations before the 1080 m level.

In method 2, in order to eliminate the local gradient variations as well, filling heights were

calculated starting from the 960 m point. In this method, filling had to be done in two places.

Figure 2.39 : Two methods of road filling

We constructed proposed surfaces for both methods and calculated the fill heights in both

cases. The results are summarized below in Table 2.13.

In method 1, the local gradient variation at 960 m point is left as it is, and only the latter part

of the road is filled. The road had to be extended by 25.35 m to accommodate the new

gradient

67

In method 2, the local gradient variation is also eliminated. Filling has to be done in two

sections with a negligible cut section. The road had to be extended by 30.0 m.

The section highlighted in yellow indicates the extra lengths the road had to be extended in

method 2. While method 1 is the easier to implement, method 2 takes care of the local

gradient variation found at the 960 m and gives an overall smoother road.

The filling work on this portion of the road began while we were still at training. The road

was extended as was decided in both methods. At the end the filling was carried out

according to a combination of the two proposed methods.

Table 2.13 : Calculated fill Heights in the two Methods

Survey Station Fill Height Method 1 Fill Height Method 2

960 0

980 0.3145

1000 0.3676

1020 0.1948

1040 0.1625

1060 0.1002

1080 -0.0526 0

1100 0.0508 0.1379

1120 0.1391 0.1932

1140 0.4033 0.4805

1160 0.8788 0.9987

1180 1.2586 1.3157

1200 2.1066 2.3221

68

1220 2.3256 2.2668

1240 2.3737 2.2326

1257 2.0331 1.7544

1267 1.3555

1277 0.6779

1287 0.0003

At the end of the project we were able to propose a solution to the steep roads of the new

hauling road without performing any time consuming and expensive cut operations. Filling

work beginning immediately after is a testament to its effectiveness. The picture below shows

the refilled area of the road.

Figure 2.40 : Refilled Area of the New Road

69

2.4 Quality Control and Planning

In the manufacturing of cement it is important to maintain the physical properties and

consistency. This means that the raw material used for cement production should be of

consistent quality. Therefore, quality control of the limestone reproduces is a vital component

of the quarrying process.

Limestone naturally occurring does not have a consistent composition. Therefore, through

extensive sampling, coordinated quarrying, and proper mixing, the desired quality of

limestone is obtained. To achieve this, The personnel at the quarry lab works alongside the

quarry Engineers and the Chemists at the Palavi processing plant to ensure that the required

quality product in the right quantities are produced.

2.4.1 Lab Activities

The lab occupies the central position in the quality assurance process coordinating with the

engineering division of the quarry and also the chemical department at the Palavi Processing

plant.

2.4.1.1 Sampling

Sampling in the main activity carried out by the lab. sampling is performed throughout the

day and every day. samples gathered are tested at the quarry lab itself and some samples

collected are sent to Palavi via train

dispatch to be analyzed more accurately.

Results received from such tests are

updated daily into records.

The types of sampling performed at the

quarry are as follows.

2.4.1.1.1 Test Hole Sampling

Test holes are holes drilled to for the

purpose of sampling itself. They are drilled

on the reject bed soon after the overburden

is removed. Holes are drilled up to a depth

of 60 feet (6 rod holes ). Samples are taken

from the drill dust that is flushed out from Figure 2.41 : A typical test hole

70

the drill steel. While the approximate quality of the area is known by QSO , Test holes are

drilled as means for conformation and also to accurately record the quality of the particular

area. To this end, GPS coordinates of the test holes are taken and the they are recorded in MS

Excel Sheets. A typical test hole and type of material found are shown in Figure 2.41 : A

typical test hole.

We observed the test hole sampling and we gathered samples and GPS location data and also

entered them into records. We also formatted some of the older records and restructured and

organized them so that they can be used for further analyses.

We organized some test hole data into a table shown in annex ,and extracted the elevations

along with their GPS coordinates to create a set of 3D Cartesian coordinates.

Table 2.14 : Coordinates extracted from Test Hole Data

Top Layer Bottom Layer

x y z x' y' z'

94743 338990 5 94743 338990 1.5

94698 338999 4.5 94698 338999 -1.5

94702 338985 7.5 94702 338985 1.5

94687 339010 0.5 94687 339010 -0.5

94689 338990 0.5 94689 338990 -0.5

94755 339071 5 94755 339071 1.5

94970 338465 1.5 94970 338465 -1

95078 339206 15.5 95078 339206 9.5

95112 339191 11.5 95112 339191 3

95102 339186 13.5 95102 339186 2.5

95124 339157 7 95124 339157 -4

95078 338800 -15 95078 338800 -16

71

These coordinate data was fed into the "Surfer" software and a 3D model of the layer was

created. Using this 3D model and by calculating the volume between the surfaces, the volume

of the layer was calculated.

Figure 2.42: 3D models of upper and lower layers

however it must be noted that the area is a rectangular area spanning the extreme corners of

sampling.

The volume calculation is as follows.

Total Volumes by:

Trapezoidal Rule: 1034419.365

Simpson's Rule: 1034551.84

Simpson's 3/8

Rule: 1034536.013

2.4.1.1.2 Drill Hole Sampling

Drill hole sampling is just like test hole sampling except that the main purpose of drill holes

is to drill holes for charging explosives. Since Drilling is performed every day, Drill hole

samples are collected daily. The samples are collected by means of a dust collecting pan.

These collected samples are put into sample bags and are sent to the quarry lab for testing.

In drill hole sampling one major problem is that most high quality material gets carried away

by the wind and the dust collected at the pan is composed majorly of the heavier sand

72

component. For this reason, the drill hole sample results are of lower quality, which is why

other methods of sampling are required for a proper assessment.

2.4.1.1.3 Mix Heap Sampling

Just as the name suggests, mixed heap sampling is taken from the mixed heaps at various

times of the day. This method of sampling paints a more accurate picture of the quality of the

material hauled form the quarry, The main purpose of this type of sampling is to monitor and

optimize heaps so that they are maintained at the required quality levels consistently.

2.4.1.1.4 Wagon Sampling

Wagon sampling is the final stage of sampling and in done once the material is loaded into

the wagons before dispatching. It gives a final measure of the type of material that is sent to

the Palavi processing plant. Samples are taken from every third wagon of every train

departure.

When collecting samples, at least 5kg of material is taken and it is reduced to 200g by means

of coning and quartering. Coning and quartering is standard laboratory process of obtaining

an unbiased sample.

Figure 2.43 : Coning and Quartering

If the samples contain rocks and pebbles, before coning and quartering is performed, it is

crushed by means of a jaw crusher to produce a sample with particles of manageable size.

Once coning and quartering has been done, the contents are heated to remove moisture

transferred into Disk Mill for grinding into a powder. After grinding into a powder they are

transferred into packets and sealed. These sealed packets are sent to Palavi for testing.

73

2.4.1.2 Quality Parameters

The main quality parameters involved in the manufacturing of cement are given below.

While the chemical parameters listed below are governed by the requirements of the

production of cement, the moisture content and physical parameters are governed by the

processing conditions and the requirements of the machines used for processing.

1. Lime Saturation Factor (LSF)

This is the most important and often widely quoted parameter concerned with cement

production. It is the first parameter that is tested and the main factor considered in mix bed

preparation and dispatching. The grouping of quarried limestone into high quality and low

quality is done on the basis of LSF. An LSF above 120 is generally termed high quality. It

combines ratios of several chemical components and is calculated as follows.

𝐿𝑆𝐹 = 𝐶𝑎𝑂

2.8𝑆𝑖𝑂2 + 1.18𝐴𝑙2𝑂3 + 0.65𝐹𝑒2𝑂3∗ 100%

Equation 2.6 : Formula for LSF

2. Alumina Ratio

Alumina Ration is the secondary quality parameter and gives a measure of the limestone's

clay content.

𝐴𝑙𝑢𝑚𝑖𝑛𝑎 𝑅𝑎𝑡𝑖𝑜 = 𝐴𝑙2𝑂3

𝐹𝑒2𝑂3

Equation 2.7 : Alumina Ratio

3. Silica Module

𝑆𝑖𝑙𝑖𝑐𝑎 𝑀𝑜𝑑𝑢𝑙𝑒 = 𝑆𝑖𝑂2

𝐴𝑙2𝑂3 + 𝐹𝑒2𝑂3

Equation 2.8: Silica Module

4. Chlorine Content

5. Magnesium Oxide (MgO) Content

6. Moisture Content

74

The Chlorine Content and MgO content is not very important in the quarrying level. However

they are used for record keeping as it can be used to create a comprehensive chemical

analysis of the quarried material.

The main purpose of measuring moisture content is to avoid Crusher jamming at the

processing plant. For this reason, during the dry season, a moisture content of 7% is

maintained while during the wet season a level of 8% is maintained. Moisture content can be

reduced by adding boulders (less than 1.5m) with the limestone, as boulders do not contain

water.

2.4.1.3 Laboratory Testing

The quarry lab is equipped with apparatus and reagents to carry out all necessary chemical

tests. We observed several of these chemical tests being performed. The procedures in the

testing of limestone are quite different to the standard laboratory practice we are familiar

with, especially in the use of indicators and titrations.

Although the lab is equipped with the facilities, the accuracy in the testing performed is not

up to the level required. Also sometimes results are required in a short period of time. For

these reasons, samples are sent to Palavi for testing via XRF (X-Ray Fluorescence

Spectroscopy). This yields highly accurate results in a short time.

The quality targets expected to be produced by the Quarry in terms of chemical parameters

are as follows.

Table 2.15: Quality Targets of the Quarry

LSF SM Cl-

Quarried

Limestone

HGL Min 110 Max 3.5 Max 0.6% Moisture Content

LGL Min 50 Max 5.5 Dry

Season

Wet

Season

Mixed

Heap

HGM 150±20 Max 3.5 Max 0.03% Max 7.0% Max 8.0%

LGM 85±15 Max 4.5 Max 0.035

%

75

Where,

HGL-High Grade limestone LGL-low grade lime stone

HGM- High LSF mix bed LGM-low LSF mix bed

2.4.2 QSO and Quarry Master

QSO and QuarryMaster are two software packages designed by Holcim Global Technical

Services for the exclusive use in their limestone quarries around the world. The Aruawakkalu

Quarry also has these software installed and they are used for planning and optimization of

the quarry.

2.4.2.1 Quarry Scheduling and Optimization (QSO)

As the name suggests the QSO software is designed for the purpose of scheduling and

optimizing the quarry output. It is a software primarily used for long term planning of the

quarry. The basic idea of QSO is to model the quarry in a 3 dimensional space with blocks of

manageable size. This model contains data about the quantity, of material the distribution of

quality and also the spatial layout and extent. With this data fed into the software, it

calculates the optimum way that quarrying should be performed.

The main input data for the QSO software are core drilling data. Although we did not

experience the core drilling process, we got the opportunity to study several core drilling data

sets. We studied these data sets and compiled and formatted some of them for ease of

analysis. A typical core drilling dataset contains

GPS / Grid location

Elevation of Surface

Depth of each reject and Limestone Layer

Quality of Each layer

Using this data, the QSO software creates a 3-dimensional layout arranged in blocks of

50mx50m and also in layers for each quality. The right side of Figure 2.44 shown below

shows the blocks arranged in layer for each quality, while the left portion of the image shows

on such layer isolated for analysis. The blocks shown in red are the blocks available for

mining..

76

Depending on the required quality and also other restrictions such as quarry boundaries and

environmental considerations, it is possible to "run" the software into the future. Then the

software considers the blocks available for mining and also the current quarry advancement

rate to predict the future of the mine.

This gives us a graphical plan of the long term quarry progress. We were given the

opportunity to use this software. We used the software to predict the layout of the quarry in

the year 2014 during each quarter. Figure 2.45 shows the layouts produces by QSO for the 4

quarters of 2014. The dark blue blocks indicates overburden removal, the light blue blocks

indicate low grade limestone while the green blocks indicate high grade limestone.

In the figure above it can be seen that the high grade limestone that is to be extracted during

the 1st quarter has depleted by the 2nd quarter while the low grade limestone areas in the first

quarter has become high grade limestone in the 2nd quarter. This reflects the fact that the

high grade limestone lies at the bottom strata of the deposit.

The figure also shows that overburden removal will, to major extent complete by the first

half of the year while during the latter half, only limestone extraction will take place. In

addition to the graphical layout, QSO also provides the quantity and quality data numerically.

Figure 2.44 : The QSO Layout

77

Figure 2.45 : QSO prediction for 4 quarters of 2014

2.4.2.2 QuarryMaster

QuarryMaster is the other software used at the quarry. It provides ways to optimize day to

day operations in the quarry and is mainly used for short term planning. The software has a 3

dimensional, spatially referenced model of the quarry and daily changes and sampling data

can be inserted into it on a daily basis. Blasting performed at the quarry are marked and

virtually blasted in the software also.

Quarter 1 Quarter 2

Quarter 3 Quarter 4

78

Figure 2.46 : The 3 Dimensional Model of the Quarry in QuarryMaster

We performed a lot of activities relating to QuarryMaster. We gathered GPS points

periodically around the quarry boundary in order to update QuarryMaster. We performed a

GPS survey and mapped current

overburden removal areas. Since

these areas will be the areas

which will be mined in the

immediate future, we inserted

the GPS survey data into

QuarryMaster and mapped the

quarry pit and calculated the

extra area which will be mined

during the next couple of

months.

Figure 2.47 shows a map prepared

in this manner highlighting the

areas to be mined from December 2013 and September 2104 and also the quarry boundaries

after that period.

Once the sampling data from the lab is also inserted into the software along with their

location data, the software build up a model of the locations of available material and their

qualities like in QSO, but in a more short term way and also as isolated and local data. Using

this, the optimum system of hauling can be determined. This also helps in mix bed

preparation.

Figure 2.47 : Short Term Mine Planning with

QuarryMaster

79

2.4.3 Mix Bed Preparation

Mix bed preparation is the name given to the pre-blending process employed quite recently at

the quarry. Mix beds are prepared at the ramp

area and is done to mix the hauled material

before dispatching them to Palavi.

Under this method, heaps are built by using

layers of alternating quality material. Once the

dump trucks dump the material at the ramp, a set

of small dozers, shove these material and

create heaps.

Dumping id performed in quality of

alternating material which the gives the heaps

a layered appearance. The qualities and

frequencies of material hauling is decided by

using the QuarryMaster software. The heap is broken perpendicular to the prismatic section,

so that all the layers mix when it is broken thus giving a mixed material with consistent

quality. Only after a heap has been depleted completely it is rebuilt again. Complete heaps

are covered to protect them from the rain

2.4.4 Activities at Palavi Processing Plant

The material sent from the quarry to Palavi is first crushed by means of two Hammer

Crushers. Since there had been some problems with the performance of these crushers. We

were assigned to analyze this situation. For this purpose we received crusher performance

data from Palavi in the form of daily record sheets. We tabulated these data into a MS Excel

sheet and analyzed them. Upon initial analysis it was difficult to come to a conclusion

because, Crusher 1 did not have enough data due to a break down. However, upon further

analysis it was found that Crusher 2 was performing better

Figure 2.48 : Preparing of Mixed

Heaps

Figure 2.49 : Layered appearance of a

Mixed Heap

80

2.4.5 Activities carried out

In addition to the above activities we carried out several other projects. They are described in

this section.

2.4.5.1 Alumina mapping of the Quarry

After LSF the next most significant quality

parameter is the Alumina Ratio. To assess the

Alumina variation in the quarry it was

decided to analyze available data and to check

whether any inferences could be made. For

this we utilized the test hole and drill hole

sampling data and extracted the Alumina

Ratio data from the sampling results. We

coupled this data with its location data as well

and created a 3D Cartesian coordinate data

set.

These coordinates were inserted into the

Surfer software and the a contour map of the

Alumina variation was obtained.

In this contour map it can be seen that a very

high variation of Alumina has occurred at the

north east portion of the map. This turned out to be an anomaly caused by a high

concentration of sampling points in that area. Therefore since the sampling points were not

well distributed, the accuracy of this map is questionable.

2.4.5.2 Preparing Cross Sections of the Quarry Pit

Part of the long term planning of the quarry is the quarry pit rehabilitation plan. For this it is

required to fill the quarry pit appropriately so that there are no excessive slopes. This has to

be ensured for the safety of wildlife as well as to avoid devastating results from erosion.

As a part of this we were assigned to draw cross section of the quarry to determine the current

steepness of the slopes. Once the current shape is known the most appropriate filling plan can

Figure 2.50: Contour Map of Alumina

Variation

81

be adopted. To do this we gathered elevation data of the quarry and used the surfer software

to draw up cross sections.

Figure 2.51 : Cross Sections of the Quarry Pit

2.4.5.3 Fill Volume Calculation of Old Road

This is one of the major projects carried out by us. Although slightly similar to the above

project, this was far more complex and extensive. We had to calculate the volume of soil

which would be required to fill the old hauling road as it is no longer used. Since overburden

soil was going to be used for this, knowing the exact volume required will help in planning

the overburden dumping strategy.

We gathered over 500 points of elevation along with their northing and easting coordinates.

We processed this data and created a 3D model of the existing topography of the area of the

road. Then we also modeled a smooth proposed surface using Surfer. We used these two

surfaces to calculate the volume of soil required. The full report is included in the Annex.

Figure 2.52 : The Existing Surface and the

Proposed Surface

Existing Proposed

82

2.5 Overburden Removal and Rehabilitation

Overburden removal and rehabilitation lies at two different ends of the quarry operations

spectrum. However both of these operations are often carried out simultaneously. This is

because the top side excavated during overburden removal is used for rehabilitation.

2.5.1 Overburden Removal

Overburden removal at the Aruwakkalu quarry carried out by 3 Companies. Namely, EDC

(Eric Dharmasena Construction (Pvt) Ltd. , TML (Tokyo Machine Leasing) , and ISURU

Engineering. EDC has the largest

machine fleet overall and also

performs activities in the ramp.

TML has the largest machine fleet

for overburden removal. These

three companies are assigned

separate areas for overburden

removal and they are paid

according to the bank cubic meters

(BCM) of overburden soil

excavated.

During the overburden removal process, the fertile topsoil layer is first excavated and piled

separately. This soil consists of organic matter and is suitable for plant growth. The

subsequent layers of excavated overburden soil is not fertile and therefore is used primarily to

fill abandoned pits.

2.5.1.1 cycle times

The excavation of overburden is done by excavators and the soil is loaded into 10-wheel haul

trucks and hauled into the dumping points. We conducted a cycle time analysis for the 3

companies. The results are summarized below.

Figure 2.53 : Overburden Removal

83

Table 2.16 : Overburden Removal Cycle Time Summary

Company Average Cycle Time Cycle Distance Average Cycle per

Day

EDC 8.77 minutes 2.2 km 48

TML 10.1 ,minutes 2.3 km 55

ISURU 15.03 minutes 2.4 km 45

2.5.1.2 Bench face and slope analysis

In the excavation of overburden, benches are left for stability purposes The stipulated

dimensions of the benches are 5m X 5m. However, in some areas these dimensions have

not been adhered to and it has posed a risk with also several collapsed benches.

We were assigned to conduct an analysis of this situation. The first step was to monitor and

assess the current bench conditions. We recorded several locations around the quarry and

measured the bench dimensions and also recorded GPS location data. Using these data we

calculated the slope angles of different areas of the quarry.

Although according to the stipulated dimensions, the slope angle should be approximately 45ͦ.

However, from our measurements we found out that most bench slopes exceeded this

amount.

The next step was to carry out a Risk assessment of the above areas. We photographed the

areas and assessed the potential risk involved by consulting a risk matrix. The risks that we

considered are as follows:

Plane failure:- failure of a bench face as a plane

Wedge failure :- Wedge like failure caused by erosion

Rock falls:- caused by instability of benches

A summary of the findings of the slope analysis and the risk assessment are given below.

84

Table 2.17: Summary of Bench Face Risk Assessment

Location

Grid

No.

GPS

identification

Potential

For

Potential

Consequences

Risk

Rating

Mitigation

Measures

ISURU 1 95209,338838 Rock falls

personnel and

equipment

damage

C3

(13)

scaling of

loose rocks

ISURU 2 95222,338838

Rock

Falls

personnel and

equipment

damage

D3

(17)

scaling of

loose rocks

ISURU 3 95253,338873

Wedge

failure

personnel and

equipment

damage D2(12)

removal of

loose

material

ISURU 4 95301,338865 rock falls

personnel and

equipment

damage D3(17)

scaling of

rocks

ISURU/TML 5 95341,338884

Wedge

failure

collapsing of

benches D4(21)

proper

benching

TML 6 95344,338933 rock falls

personnel and

equipment

damage D3(17)

scaling of

rocks

TML 7 95348,338983 rock falls

personnel and

equipment

damage D3(17)

scaling of

rocks

TML 8 95357,339027

Wedge

failure

personnel and

equipment

damage D2(12)

removal of

loose

material

TML 9 95356,339079 Rock falls personnel and

equipment

C3

(13)

scaling of

loose rocks

85

damage

TML 10 95364,339131 Rock falls

personnel and

equipment

damage

C3

(13)

scaling of

loose rocks

TML 11 95375,339177 Rock falls

personnel and

equipment

damage

C3

(13)

scaling of

loose rocks

EDC/TML 12 95369,339238 Rock falls

personnel and

equipment

damage

C3

(13)

scaling of

loose rocks

EDC 13 95334,339260 Rock falls

personnel and

equipment

damage C2(6)

scaling of

loose rocks

EDC 14 95302,339262

Wedge

failure

personnel and

equipment

damage D2(12)

removal of

loose

material

EDC A 95070,339207

Wedge

failure

personnel and

equipment

damage, road

blockage D4(21)

proper

benching

EDC B 95150,339259

plane

failure road blockage B2(5)

proper

benching

EDC C 95216,339271

plane

failure road blockage B2(5)

proper

benching

EDC D 95268,339308

wedge

failure road blockage C3(13)

proper

benching

EDC E 95330,339346

plane

failure bench collapse B3(9)

proper bench

heights

86

EDC F 95494,339286

wedge

failure,

plane

failure bench collapse C3(13)

maintaining

proper bench

dimensions

TML G 95532,339210

plane

failure banch collapse D4(21)

maintain

bench heights

TML H 95469,339108

bench

failure bench colapse E5(25)

proper

benching

TML I 95467,339041

plane

failure road blockage C4(18)

maintain

proper bench

heights

TML J 95422,338969

wedge

failure bench collapse c3(13)

proper bench

dimensions

ISURU K 95285,338806

plane

failure bench collapse C4(18)

maintain

bench

dimensions

Figure 2.54 : Risk Assessment Matrix

87

2.5.2 Rehabilitation of the Quarry

The rehabilitation process at the Aruwakkalu mine is done with the involvement of IUCN (

International Union for Conversation of Nature) . Once the quarrying is over the pits are

filled with overburden soil eliminating all steep slopes. Then the area is filled with fertile

soil and plant species typically found in that area are replanted. The rehabilitated areas are

constantly monitored and improvements are made to preserve the flora and fauna of the area.

2.5.2.1 Activities with IUCN

IUCN is the organization responsible for providing recommendation and monitoring the

rehabilitation of the quarry. They provide recommendations for the type of plant species to be

replanted. For this they visit and record the flora and fauna of the surrounding areas .Another

important activity performed by IUCN is the animal rescue programme, in which animal

species are taken out of the quarry site where overburden removal is scheduled to begin. This

activity is carried out with the help

of the Villagers. These rescued

animals are released into fully

rehabilitated areas.

2.5.2.2 Seedling bed Preparation

The plants that are required for

rehabilitation are usually purchased.

However under a new initiative it

was decided to cultivate seedlings

taken from the surrounding forest s

in seedling beds constructed in the

rehabilitated area itself. We were

assigned to plan and prepare the

seedling beds required for this

purpose.

We selected areas which were not

exposed to direct sunlight and

which were not prone to surface

runoff. Once the suitable areas

Figure 2.55: Seedling Bed Locations

88

were selected fertile soil from the overburden removal process was used to construct seedling

beds. The idea was to plant saplings in these seedling beds until they could be relocated to

the rehabilitated areas. This initiative saves the cost involved in purchasing plants. We also

recorded the locations of these seedling beds in a map for future reference. The map is given

above.

2.6 Machine maintenance and Workshop Activities

The Aruwakkalu Quarry has its own workshop and maintenance division to maintain the

machinery belonging to Holcim. The workshop performs undercarriage maintenance of the

Komatsu Machine fleet and complete maintenance in other machines. The workshop is also

equipped and responsible for all electrical work in the quarry and surrounding premises.

The maintenance division maintains extensive records of performance, maintenance and

breakdown in all machines.

2.6.1 Daily maintenance operations

Daily maintenance occupies a significant role in all workshop operations. Machines are

checked daily according to specific check lists for each machine to ensure that all machines

are in good condition. Engine maintenance is performed by the DIMO maintenance crew and

is overseen by the Holcim operators.

Figure 2.56 : Daily Machine Checks

89

2.6.1.1 Tyre Maintenance

An important part of daily maintenance is the checking of tyres. Tyre pressures are checked

daily and inflated to the correct amount before operations begin. We gathered tyre pressure

data over a period of time both before and after operations. We found out that the tyre

pressure increases by about 20% after operations.

We also periodically measured the tread depths of tyres and tabulated them in order to find

the wear rate of tyres. The tabulated data and resulting calculations is given in section Table

2.7.

2.6.1.2 Welding Grinding

We also performed welding and grinding operations at the workshop and experienced the

methods involved and precautions taken. In constructing sign boards for the explosive

magazines we performed some of the welding and grinding operations.

Figure 2.57 : Welding Operations

2.6.2 Machine Safety Survey

In order to assess the safety levels of the entire machine fleet operating at Holcim (including

3rd party machines as well) We performed a safety survey. The main purpose of this survey

was to assess whether the machines are prone to theft and to identify areas which could be

improved in this regard.

90

We visited all supervisors and gathered data about their machines and tabulated them. Since

this activity involved a lot of machines and lot of criteria a large amount of data had to be

entered. To overcome this situation we prepared a data entry form using Macros in Excel.

Once tabulated this data was used to identify weaknesses present in machines and steps were

taken to rectify them.

Figure 2.58 : The Excel data Entry Form Used for the Machine Survey

2.7 Workshops and Other Learning Opportunities

In addition to the learning opportunities at the Quarry Site we also received the opportunity to

participate in two workshops organized by CETRAC (Construction Equipment Training

Centre) We were sent along with an employee of Holcim to this full day programme

consisting of the two sessions. We learnt lot of new things about the proper use of lubricants

and also the basics of machine maintenance at these workshops.

2.7.1 Lubricant Workshop at CETRAC

In this workshop we learnt the defining characteristics of lubricants and their performance

under different conditions . After a basic introduction to the types of lubricants we were

taught the proper usage of each type. We were also given the knowledge to understand the

naming system of lubricants and each of their properties.

An important fact that we gathered was the difference between mono-grade and multi-grade

oils and the pros and cons of each type. We also learnt the importance of changing engine

91

and transmission oil periodically to avoid carburization of the lubricant oil and resulting

engine damage.

Back at the quarry we were able to apply the new knowledge gained and further cemented

our knowledge with discussions with personnel and the workshop.

2.7.2 Workshop on Maintenance of Construction Equipment

In this workshop we learnt the basic parameters of measuring equipment performance.

Terms such as,

availability

meantime to failure

equipment down time

cost per unit time

overall equipment effectiveness (OEE)

were discussed. We also learnt methods of measuring performance and effectiveness of

machines. However, almost all these methods discussed were already implemented at

Holcim.

The FMC daily record sheets maintained at Hoclim includes all the necessary details

required to calculate the key performance indicators taught to us at the workshop. With the

knowledge gained at this workshop we were able to use the FMC record sheets in much more

complicated analysis and were able to produce information about operator performance as

well.

2.7.3 Tire maintenance lecture by Triangle tire corporation

Due to problems with heavy machinery tyres at the quarry, a consultant from the Triangle

Tyre Corporation visited the premises to assess the tyre conditions. At the end of his visit, he

presented a lecture about the proper usage of tyres.

We learned the importance of the daily maintenance of tyres and the proper machine handling

practices such as symmetrical loading, avoiding tyre spinning etc to extend the lifetime of

tyres. The road conditions and the frequency if road maintenance has on the performance of

tyres was also discussed. A special attention was given to controlling the road watering

system as excessively wet roads damage tyres more frequently.

92

3 CONCLUSION

The Industrial Training programme is undoubtedly is the most important aspect of the 4 year

degree in Engineering. After 3 years of university study, gathering knowledge and learning

theories, industrial training period cements all the knowledge gathered and helps us to

understand the theories we learnt. In the real world application of things we learnt at the

university during our training period we experienced aspects that we never thought would be

important when we learnt them. For example, although we knew the theories and procedures

with respect to activities like blasting, hauling, only during our training period did we learn

the actual process practically such as the proper quantities of explosives and the application

of specific charge to control explosive usage. We also received hands on experience in most

quarry activities and learnt the minute details and intricacies in each of them. To conduct

We received such an extensive training programme at Holcim Lanka Ltd. that at the end of it

we were confident that we could manage a quarry of that capacity by ourselves. In an

industry where securing a position for training let alone a highly exceptional place such

Holcim Lanka Ltd. is a difficult task, we are thankful to NAITA , the University of Moratuwa

and Holcim Lanka Ltd. for facilitating this programme.

Upon starting our training programme at Aruvakkalu Quarry, we were welcomed graciously

by Quarry Manager, Eng. W. N Wedage , Quarry Engineer Eng. G. Silva, and the Junior

Mining Engineers, P Kumarage, and A Batagalla. We were explained the outcomes of this

training and were told to make the maximum of this opportunity. To this end, we were

assigned to the two shifts under the two junior mining Engineers in order to experience all

aspects of the quarry operations and to experience the full responsibility of an Engineering

job in the field of mining. We worked hard for extensive hours under the constant guidance

of our immediate superiors who treated us like their own brothers. We were encouraged to

ask questions and allowed to perform most operations related to the quarry without

hesitation. We were assigned several projects and often given the full responsibility to carry

them out on our own. We were provided with assistance whenever we required, and we

were able to perform these projects to the satisfaction of our superiors. These projects were

mostly practically oriented and we had to gather real data sometimes over a period of several

months. This sort of activity was not possible to be conducted at the university. At the end

of each project, we were instructed to furnish full reports highlighting the findings and our

recommendations. We were happy to see that some of our findings from our projects being

applied at the quarry. One major opportunity we received during our training programme was

93

to learn and work with several new software programmes. While learning to use software

programmes exclusive to Holcim such as QSO and QuarryMaster, we also learnt several

other widely used programmes. We learnt to operate 3D terrain modeling software "Surfer"

and used it extensively in many of our projects. We also sharpened our skills in handling

software we already learnt at university such as AutoCAD.

During this training period I found out that communicating with personnel at the quarry and

maintaining a proper network was a difficult task for me. After realizing this I made a

conscious effort to move around more with the people in order to develop my people skills.

At the end of the six months training, I experienced a massive improvement on this front.

However, I still have improvements to be made in this regard, and I plan to work on my

communication skills during the final year by engaging more with social activities at the

university. Overall the training period helped me to identify this weakness of mine and

equipped me with the tools to overcome this and to turn my weakness into strength.

Holcim Lanka Ltd. is equipped very well to provide industrial trailing. We were considered

as employees of the Company during our stay and were provided meals, accommodation

transport and also given an allowance. Being a Company highly focused on safety and

proper operational procedures, we were given all personal safety equipment including hard

hats, safety shoes, safety goggles and also a uniform with high visibility bands. To carry out

our project work, we were also given office space complete with all facilities. The effort put

in by the Company for our training programme made our training a pleasant experience.

At the end of the training programme, all our expectations were met and also we achieved all

the outcomes explained to us by the quarry officers at the beginning of our training. We

received hands on experience and became very proficient in all the activities we performed.

We also improved our analytical skills and learnt to perform multiple activities efficiently by

using software packages we learnt. We also developed our report writing skills. However,

due to the extensive nature of our training programme, we were short of time to get some

other experiences. For example, we were not able to spend enough time at the Palavi

Processing Plant in order to fully understand the cement production operation. While we got

a basic understanding of this, spending some more time at the plant would have enabled us to

experience the finer details of the process and to better understand what happens to the

material which is quarried at Aruwakkalu. We also felt that we did not receive enough

experience on the management side of operations. We feel that as a budding Engineer it is

important to experience the management side of a company. In order to solve this problem it

94

would be useful for future trainees if a training schedule with placements at different sections

of the organization for different periods along with the main training at Aruvakkalu quarry

was prepared prior to training.

As a suggestion to improve overall training experience it would be easier for trainees if a

system is implemented by the university which enables trainees to submit their monthly

reports through an online portal. This would reduce the hassle of having to post or

physically deliver the reports each month.

Considering the overall training experience, I consider myself lucky to be placed at Holcim

Lanka Ltd. and am extremely happy with the outcome of the programme. I was able to learn

new things as well as improve on my personal goals and also helped indentify my strengths,

and also correct my weaknesses. I am extremely thankful to the University of Moratuwa and

NAITA and also all personnel at the Aruwakkalu Quarry of Holcim Lanka Ltd. for providing

us with such a valuable and useful industrial training programme.

ix

ANNEXES

Cement Production Chart

Figure A.3.1 : The Cement Production Process

x

Fill Volume Report

Introduction

This study was conducted with the objective of calculating the volume of overburden soil that

can be accommodated by refilling of the old quarry road. Filling of the old quarry road is

expected to begin as hauling operations are carried out on the new road and once the

overburden removing process has started. The filling of the old quarry road will reduce

unsuitable slope profiles and help in landscaping and rehabilitation of the area.

Methodology

The volume was calculated by modeling the existing profile and the required final profile 3

dimensionally using Surfer9 software and by calculating the fill volume between the two

surfaces by the same.

The primary data required for the project was obtained from the 2013 year end topographic

map of the Aruwakkalu Quarry Site.

Software Packages

the software packages used for the project are,

AutoCAD 2012

Surfer 9

Microsoft Office Excel 2007

Procedure

The procedure followed in the volume calculation is as follows.

A 20mx20m grid was constructed on the topographic map covering the entire extent of the

area to be filled. (The grid used for finding elevation)

using the contours of the topographic map, the elevations a the grid points were found. In

areas where there was a higher terrain variation, additional points were taken in the middle of

the existing grid.

The elevations of the grid pints along with their spatial coordinates (Easting and Northing)

were entered to an Excel spreadsheet.

This Excel data was imported into Surfer, converted into a grid file and the surface was

plotted in 3D.(Existing Surface)

xi

In the Surfer environment a new grid file corresponding to the final filled surface was created

by interpolating several spatial coordinate data in the expected final surface.(Proposed Final

Surface)

Using the two grid files the fill volume between the existing surface and the proposed fill

surface was calculated.

Results

The volumes calculated from Surfer 9 are as follows

Volume Calculation Method Calculated Volume

Trapezoidal Rule 893,309.18782507

Simpson's Rule 893,656.21780539

Simpson's 3/8 Rule 893,584.35438327

Cut & Fill Volumes

Cut Volume : 6,210.1710087063

Fill Volume : 899,519.35883357

Net Volume : 893,309.18782486

4.0 Conclusion

From the above set of results obtained from Surfer it is evident that approximately 900,000

m3

of overburden sol is required to fill the old quarry road.

Although both cut and fill volumes have been calculated by Surfer, due to economic reasons

only the fill volume is considered.

Discussion

The economic reasons cited under Conclusion for leaving out the cut volumes, are the

additional time and costs which will be incurred in cutting and moving soil which was

already cut and hauled when the old quarry road was being constructed. Furthermore, since

the filled area is to be used for rehabilitation process, as long as the slope profiles are not

excessive, further cutting is not required.

This volume calculation was performed with limited data and the grid constructed has a

resolution of 20x20m. Despite additional points within this grid, this causes a slight error in

xii

the final calculated volume. Also, differences in contours in the topographic map and sudden

variations in the actual ground could also cause deviations from the calculated result.

An approximate fill volume of 900000m3 is a manageable volume of soil which can be

hauled using dump trucks. In order to economically haul the removed overburden to the

filling location, a study can be carried out taking the hauling cycle distance and cycle times

and loading and dumping points into consideration.

The grid used for finding elevation

Figure A.3.2: Elevation Grid

xiii

Existing Surface

FigureA.3.3: Surfer 3D model of Existing Surface

xiv

Proposed Final Surface

FigureA.3.4:Surfer 3D model of Proposed Surface

xv

LIST OF ABBREVIATIONS

FMC - Full Maintenance Contract

QSO - Quarry Scheduling and Optimization

ED - Electric Detonator

EDC - Eric Dharmasena Construction

TML - Tokyo Machine Leasing

SOP - Safe Operational Procedures

GPS - Global Positioning System

LSF - Lime Saturation Factor

AR - Alumina Ratio

SM - Silica Modulus

XRF - X-Ray Fluorescence Spectroscopy

HGL - High Grade Limestone

LGL - Low Grade Limestone

HGM - High LSF mix bed

LGM - Low LSF mix bed

IUCN - International Union for the Conservation of Nature

GI Form - Goods Issue/Return Form

xvi

REFERENCES

Quarry Safety Operating Procedure (SOP)

Holcim Organizational Policy

Holcim Lanka Sustainability Review 2012

Parts and operating Manuals of Machines

Quarry Rehabilitation Guidlines

Inspections and recommendation report on quarry rehabilitation by IUCN

Holcim Global Company Profile [http://www.holcim.com/about-us/company-

profile.html] - Date Accessed - 02-05-2014

Holcim Lanka Cements [http://www.holcim.lk/product-services/cement.html] - Date

Accessed - 02-05-2014