EXCHANGE 2007 T0 OFFICE 365 MIGRATION PROJECT
Transcript of EXCHANGE 2007 T0 OFFICE 365 MIGRATION PROJECT
EXCHANGE 2007 T0 OFFICE 365 MIGRATION PROJECT
JESSICA GRAF
ISTM5015 - Complex IT Glob Enterprise Sys
Capella University
Dr. Jose Lepervanche
September 13, 2014
EXCHANGE 2007 T0 OFFICE 365 MIGRATION PROJECT
1
Table of Contents
PROJECT DESCRIPTION .................................................................................................................. 3
Problem Statement ............................................................................................................................................ 5
Benefits ............................................................................................................................................................... 6
End State ............................................................................................................................................................. 6
Deliverables ........................................................................................................................................................ 7
Scope ................................................................................................................................................................... 7
Stakeholders and Project Roles ..................................................................................................................... 8
Tasks and Schedule .......................................................................................................................................... 9
Budget Cost ........................................................................................................................................................ 9
Risk Management ............................................................................................................................................ 10
Communications and Reporting Plan .......................................................................................................... 10
Change Control Management ........................................................................................................................ 10
Project Repository ........................................................................................................................................... 11
IMPLEMENTATION PLAN ............................................................................................................... 11
High Level Tasks ............................................................................................................................................. 12 Figure 1 High-Level Tasks/Milestones .......................................................................................................... 12
Budget for Project ........................................................................................................................................... 13 Figure 2: Project Cost Summary .................................................................................................................... 14
Human and Technology Resources ............................................................................................................. 14 Figure 3 Breakdown of Project Roles ............................................................................................................ 15
Risk Plan ........................................................................................................................................................... 15 Figure 4 Project Risks ..................................................................................................................................... 16
Communication and Reporting Plan ............................................................................................................ 17 Meetings ................................................................................................................................................................ 17
Figure 5 Standing Meetings Summary .......................................................................................................... 17 Status Reports ...................................................................................................................................................... 18
STATUS REPORT ............................................................................................................................... 19
Meeting Minutes: ............................................................................................................................................. 20
EXCHANGE 2007 T0 OFFICE 365 MIGRATION PROJECT
2
Project Status Summary ...................................................................................................................................... 20 Project Progress/Accomplishments ................................................................................................................... 20 Attention Areas ..................................................................................................................................................... 21 Project Schedule Issues/Updates ...................................................................................................................... 21 Deliverables ........................................................................................................................................................... 22 Cost Reports ......................................................................................................................................................... 22
Figure 6: Project Costs .................................................................................................................................... 22 Summary Resources: .......................................................................................................................................... 23
Figure 7: Resource Allocation Summary ...................................................................................................... 23 Goals for Next Week Review .............................................................................................................................. 23
Table 1: Goals and Responsibility ................................................................................................................. 23
PROJECT DASHBOARD ................................................................................................................. 25 Figure 1: Project Dashboard as of August 16, 2014 ................................................................................... 25
Work Accomplished ........................................................................................................................................ 27 Figure 2: WBS Tasks Completed .................................................................................................................. 27
Updated WBS ................................................................................................................................................... 28 Figure 3: Updated WBS .................................................................................................................................. 28
Project Cost Summary .................................................................................................................................... 30 Figure 4: Project Expenditures Summary ..................................................................................................... 30
Resource Usage log ........................................................................................................................................ 31 Figure 5: Resource Log ................................................................................................................................... 31
Project Deliverables ........................................................................................................................................ 32
UNPLANNED CHANGE .................................................................................................................... 33
Meeting Minutes: ............................................................................................................................................. 34
Project Status Summary: ............................................................................................................................... 34 Project Progress/Accomplishments: .................................................................................................................. 35 Project Schedule Issues/Updates: ..................................................................................................................... 35 Deliverables: .......................................................................................................................................................... 36 Cost Reports: ........................................................................................................................................................ 36
Figure 1: Project Costs .................................................................................................................................... 36 Summary Resources: .......................................................................................................................................... 37
Figure 2: Resource Allocation Summary ...................................................................................................... 37 Goals for Next Week Review: ............................................................................................................................. 37
Table 1: Goals and Responsibility ................................................................................................................. 37
PROJECT DASHBOARD ................................................................................................................. 39 Figure 1: Project Dashboard as of August 16, 2014 ................................................................................... 39
Work Accomplished ........................................................................................................................................ 40 Figure 2: WBS Tasks Completed .................................................................................................................. 40
Updated WBS ................................................................................................................................................... 41
EXCHANGE 2007 T0 OFFICE 365 MIGRATION PROJECT
3
Figure 3: Updated WBS .................................................................................................................................. 41
Project Budget Summary ............................................................................................................................... 43 Figure 4: Project Expenditures Summary ..................................................................................................... 43
Resource Usage Log ....................................................................................................................................... 44 Figure 5: Resource Log ................................................................................................................................... 44
ISSUE LOG ............................................................................................................................................ 44 Figure 6: Issue Log .......................................................................................................................................... 44
PROJECT CLOSURE REPORT ..................................................................................................... 46
PROJECT CLOSURE REPORT PURPOSE .................................................................................................. 46
PROJECT CLOSURE REPORT GOALS ....................................................................................................... 46 Milestones .............................................................................................................................................................. 46 Outstanding Issues, Risks, and Recommendations ........................................................................................ 47 Tasks and Activities required to close the Project ........................................................................................... 47 Project highlights and Best Practices ................................................................................................................ 47
PROJECT CLOSURE REPORT SUMMARY ................................................................................................. 48 Project Background Overview ............................................................................................................................ 48 Project Highlights and Best Practices ............................................................................................................... 49 Project Closure Synopsis .................................................................................................................................... 49
PROJECT METRICS PERFORMANCE .......................................................................................................... 49 Goals and Objectives Performance ................................................................................................................... 49 Success Criteria Performance ............................................................................................................................ 49 Milestone and Deliverables Performance ......................................................................................................... 50 Schedule Performance ........................................................................................................................................ 50 Budget Performance ............................................................................................................................................ 51 Metrics Performance Recommendations .......................................................................................................... 51
PROJECT CLOSURE TASKS ......................................................................................................................... 51 Resource Management ....................................................................................................................................... 51 Issue Management ............................................................................................................................................... 52
Risk Management ............................................................................................................................................ 53 Quality Management ............................................................................................................................................ 53 Communication Management ............................................................................................................................. 54 Customer Expectation Management ................................................................................................................. 54 Asset Management .............................................................................................................................................. 55 Lessons Learned .................................................................................................................................................. 55 Project Closure Recommendations ................................................................................................................... 55
Project Description
EXCHANGE 2007 T0 OFFICE 365 MIGRATION PROJECT
4
Circe Inc. is a global software development company with current customers in the
health care and manufacturing marketplace. It has 1,000 employees that have mailboxes on
Exchange 2007, which internal IT sustains.
Circe Inc. employees, in addition use mobile devices such as IPhone, IPads, Android
phones, and tablets and Blackberry devices. Blackberry devices link to the Blackberry
Enterprise server that are the responsibility of internal IT.
The goal of this project is to take email and mobile device server maintenance off the
shoulders of our internal IT and outsource it to Microsoft’s Office 365 offering. This would allow
the internal IT team to concentrate supporting the servers critical to our global software
development teams, along with saving the company money. By going to Office 365, Circe Inc.
can choose the plan that will be the most cost effective.
Employees will still be able to use their current mobile devices since Office 365 allows
not only Exchange Active Sync, but Outlook Web Access as well. The Blackberry devices will
need to be upgrade to the current device and one that allows Active Sync since in this project
the Blackberry servers are to be decommissioned since they will no longer be needed.
In order to make this project a success, I believe that Circe Inc. would benefit most if
they choose one of the three project management models or a combination of the methods from
any of the three.
1. Adaptive Project Framework – This model will allow Circe Inc., to make sure that during
the project implementation , that the project scope is kept flexible and can be adjusted in
order to get the maximum business impact
2. Crystal Method - This is a more agile model, which is very close to the model Circe Inc.
uses to develop software. It is more focused on the team’s communication, skills,
EXCHANGE 2007 T0 OFFICE 365 MIGRATION PROJECT
5
people, and how they interact in order to get the project done. It is not so focused on
processes.
3. ITIL – This model will give us a framework for best practices on how we should involve
different teams in the project.
As project manager, I am assuming that Circe Inc. is committed to the process and
resources it will take to get this project done successfully. In addition, that they also aware that
there will be a financial commitment as well to licensing Office 365 and updating the Blackberry
devices and they will need to provide users training once they are on Office 365.
This project will need at least two Exchange resources and a mobile device resources
full time for the 8 weeks that the project is scheduled to run. It will need extended resources
from Microsoft or other third parties in order to help them implement the migration and
decommission the Blackberry servers. We will also need resources from the training
department to develop and deliver training to the users on how Office 365 will work. In addition,
this project will need help from networking and security on a part time bases.
After discussing this with the internal IT teams, they do have the resources available, but
there are other projects in the pipeline, especially for networking. Networking is already
shorthanded so it might mean having to be flexible to when we use the resources we need from
them. The best time to schedule this project would be the beginning of the year for the months
of January and February, which is the best time for all teams, involved.
Problem Statement The issue facing Circe Inc. is the growing cost of maintaining and upgrading the current
Exchange 2007 and the Blackberry Enterprise environments. The cost of maintaining a 24/7
environment for a global company of 1000 users is continuing to stretch the budget and the IT
resources. The amount of time spend patching, troubleshooting and updating servers and
EXCHANGE 2007 T0 OFFICE 365 MIGRATION PROJECT
6
mobile devices leave the current IT department shorthanded to meet the needs of the software
developers as far as server builds and maintaining the development environment.
Benefits The resulting advantages will be recognized from migrating to Office 365:
Remote Workplace.
o The ability to access and edit business data from any smart phone, tablet
or computer.
o Flexibility to do our jobs and recruit developers who work from home or
other locations other than the office.
Reliability
o Letting Microsoft handle the patching and maintenance of the servers. The
downtime will be drastically reduced.
o Being on the current release of Exchange and being able to take
advantage of its stability.
o Being able to support the newest mobile devices including email with such
features as Outlook Anywhere and Office Web Applications.
Resources
o Freeing up our technical resources from troubleshooting and maintaining
an Exchange and Blackberry environment.
o
End State Circe Inc. will be fully migrated to Office 365. Exchange and Blackberry servers will no
longer be in the environment. They will be able to access their email and other business data
EXCHANGE 2007 T0 OFFICE 365 MIGRATION PROJECT
7
from any mobile device. IT will be responsible for administrating the users in the Office 365
environment and for the initial configuration backup and archiving services. After that Microsoft
will handle all patching and maintenance
Deliverables The subsequent are project deliverables:
Create Circe Inc. official documents such as training resources to be transferred
to the Circe employees.
To migrate the current Exchange 2007 to Office 365.
To decommission all Blackberry and Exchange servers
Scope The following are in scope for this effort of work:
To rollout new Blackberry devices with Active Sync.
To configure existing smartphones and tablets to use Office 365.
To provide training to IT, helpdesk and users on Office 365.
Knowledge transfer to IT on the administration of users in Office 365
EXCHANGE 2007 T0 OFFICE 365 MIGRATION PROJECT
8
Stakeholders and Project Roles
Management Upper level Executives that are stakeholders in the project
Project Manager The main contact between the stakeholders and the team, in addition to making sure milestones and tasks are completed on time and with the correct resources.
Trainers Resources that will train staff and users to use Office 365 and new mobile devices. They will develop and deliver training
Technical Communicators Resources responsible for crafting the communications for the users
Deployment Team The team that will deploy Office 365 and decommission the BES servers in the environment
Network Analyst A resource that will help with any network and firewall issues
Microsoft Resource A 3rd party resource to help with the migration to Office 365
Exchange Analyst Lead resource on getting Exchange 2007 to Office 365
BES Analyst Lead resource to decommission BES servers and help with devices
RIM Resource A 3rd party resource to help with the BES server and devices
EXCHANGE 2007 T0 OFFICE 365 MIGRATION PROJECT
9
Tasks and Schedule Task Name Duration Start Finish
Exchange 2007 to Office 365 Migration
74 days Mon 7/7/14 Tue 10/14/14
Scope 4.5 days Mon 7/21/14 Fri 7/25/14
Preliminary planning 10 days Mon 7/7/14 Fri 7/18/14
Tech Preparation 7 days Tue 8/5/14 Wed 8/13/14
User Preparation 15 days Tue 8/5/14 Mon 8/25/14
Training 19 days Tue 8/5/14 Fri 8/29/14
Documentation 24.5 days Tue 8/5/14 Mon 9/8/14
Pilot 8.33 days Tue 8/5/14 Fri 8/15/14
Deployment 7 days Fri 9/19/14 Thu 9/25/14
Post Implementation Review
2 days Fri 10/10/14 Tue 10/14/14
Migration completed 0 days Tue 10/14/14 Tue 10/14/14
.
Budget Cost
Name Cost
Scope $12,180.00
Preliminary planning
$26,920.00
Tech Preparation
$8,102.00
User Preparation
$10,160.00
Training $10,160.00
Documentation $8,600.00
Pilot $10,560.00
Deployment $27,040.00
Post Implementation Review
$4,320.00
Migration completed
$0.00
Total $118,042.00
EXCHANGE 2007 T0 OFFICE 365 MIGRATION PROJECT
10
Risk Management
The area where we will have the most risk in this project is the running the cutover batch
file and moving over the mx records which will cause an outage in the email system. One
method of diminishing this is to burn .psts of all mailboxes from the server and placing it in the
users share so they can access it in case the move does not bring over all their data. The
second method is to assure that Outlook clients forward email to the Office 365 mailboxes
during the cutover so no inbound mail is lost.
These are the reasons that we will be piloting this with a small number of users with
various mobile devices to make sure that any issues that could be cause by migrating the data
to Office 365 can be addressed before moving the majority of the users.
Communications and Reporting Plan
The communication plan will consist of weekly status meetings to review the weekly
status reports. The meetings will involve major stakeholders from all departments involved in the
project. Also, we will be using project server to host a website to give up to date status on the
project along with discussions boards and an issue wiki. This will give access to departments
involved in the project a place where they can see at a glance KPI, timelines and tasks that are
due at a glance. .
Change Control Management
EXCHANGE 2007 T0 OFFICE 365 MIGRATION PROJECT
11
Below is the process how change control will be approach during this project.
Project Repository
The project will be using SharePoint and Project Server to maintain a repository of the
issues and documents for this project.
Implementation Plan
EXCHANGE 2007 T0 OFFICE 365 MIGRATION PROJECT
12
High Level Tasks
The high-level tasks and milestones listed below are crucial to the project. Each
milestone is and high level task is a stage that needs to happen before the next milestone can
be started. Even though some milestones can run congruent to each other, each milestone is
dependent on the one before it.
Figure 1 High-Level Tasks/Milestones
Task Name Duration Start Finish
Scope 8 days Mon 9/1/14 Wed 9/10/14
Determine project scope 8 hrs Mon 9/1/14 Mon 9/1/14
Secure core resources 1 day Tue 9/9/14 Tue 9/9/14
Preliminary planning 5.5 days Thu
9/11/14
Thu 9/18/14
Budget 1 day Thu
9/11/14
Thu 9/11/14
Obtain approvals to proceed
(concept, timeline, budget)
4 hrs Wed
9/17/14
Wed 9/17/14
Tech Preparation 50 days Mon
9/22/14
Fri 11/28/14
User Preparation 15.72 days Thu
9/18/14
Wed 10/8/14
Announce migration officially to
Company
3 hrs Wed
9/24/14
Tue 9/30/14
Training 20 days Wed
10/8/14
Wed 11/5/14
EXCHANGE 2007 T0 OFFICE 365 MIGRATION PROJECT
13
Develop training materials 2 wks Fri
10/10/14
Fri 10/24/14
Documentation 25.72
days
Wed
10/29/14
Wed 12/3/14
Develop Help specification 1 day Wed
10/29/14
Thu 11/6/14
Develop user manuals 1.5
wks
Tue 11/18/14 Thu 11/27/14
Pilot 33.33
days
Mon 12/1/14 Thu 1/15/15
Obtain user feedback 6 wks Wed 12/3/14 Wed 1/14/15
Deployment 15.67
days
Thu 1/15/15 Thu 2/5/15
Post Implementation Review 2
days
Fri 2/6/15 Mon 2/9/15
Migration completed 1 day Tue 2/10/15 Tue 2/10/15
Budget for Project
The budget for this project is below and is broken down by milestones and start dates.
This includes the development of training, training materials and documentation of the process
and administration of Office 365 for Circe Inc. The total cost of this project will $139,730.
EXCHANGE 2007 T0 OFFICE 365 MIGRATION PROJECT
14
Figure 2: Project Cost Summary
Name Cost Start
Scope $17,880.00 Mon 9/1/14
Preliminary planning $14,040.00 Thu 9/11/14
Tech Preparation $8,050.00 Mon 9/22/14
User Preparation $10,160.00 Thu 9/18/14
Training $10,160.00 Wed 10/8/14
Documentation $8,600.00 Wed 10/29/14
Pilot $40,560.00 Mon 12/1/14
Deployment $23,440.00 Thu 1/15/15
Post Implementation Review $4,320.00 Fri 2/6/15
Migration completed $2,520.00 Tue 2/10/15
Human and Technology Resources
The resources needed for this project have been carefully selected. The management
team has been responsible for six very successful implementations inside Circe. The project
manager assigned to this venture has 14 years’ experience in Exchange and has certification in
Office 365 and her PMP. She has managed large global projects for Fortune 500 companies.
The BES and Exchange analyst have been with Circe for a combination of 15 years. They
administered the current Exchange environment and have taken Microsoft training for Office
365.
The Deployment team is a five person group that will be handling the migration of users
to Office 365, decommissioning the BES environment and troubleshooting issues on the
technical side of this migration. The trainers, technical communicators, and testers are Circe
employees that have tested and developed training material and delivered communications on
EXCHANGE 2007 T0 OFFICE 365 MIGRATION PROJECT
15
many internal and external projects. Lastly, we have contracted a RIM and Microsoft analyst to
make sure we are following best practices during and after this migration.
Figure 3 Breakdown of Project Roles
Name Remaining Work
Management 75 hrs
Project Manager 138 hrs
Testers 40 hrs
Trainers 152 hrs
Technical Communicators 192 hrs
Deployment Team 382.67 hrs
Network Analyst 0.8 hrs
Microsoft Resource 31.87 hrs
Exchange Analyst 90.67 hrs
BES Analyst 86.5 hrs
RIM Resource 46.5 hrs
Risk Plan
This project will make use of a recognized risk management platform to proactively
classify and remove prospective complications that could influence excellence. By identifying
and prioritizing project goals project management can focus a metrics program to specific areas
relevant to the project. When selecting a risk management process, we have included directives
are that significant to this project. These risks must be acknowledged, ordered, and then
followed over the life cycle of this venture.
EXCHANGE 2007 T0 OFFICE 365 MIGRATION PROJECT
16
The project leader is accountable for guaranteeing the risks are being coped with in an
efficient manner. In turn the project team is answerable for categorizing possibilities and
defining the effect that they may possibly have. The resulting possibilities were acknowledged
for this plan, and the modification activities to be engaged for each one to curtail the bearing on
the plan.
Figure 4 Project Risks
Risk
No.
Risk Description Probability
(HML)
Impact
(HML)
Risk Owner Mitigation Plan
1 Circe Inc. will not
be able to secure
the services
needed from
Microsoft
L H Management
Project
Manager
Management will make sure all
contracts for services for the
migration are approved and
signed before the preliminary
planning starts
2 Technical
preparation for
the migration
takes longer than
expected
M H Development
Team
Project
Manager
Development Team will provide
updates three times a week on
status and any issues
3 Training material
and delivery will
not be scheduled
due constraints
L M Project
Manager
Trainers
Trainers will coordinate with
managers to schedule training
with their teams
4 New Blackberry
devices will not
arrive in a timely
manner
M H Vendor
Project
Manager
Project Manager will request
order status from the
telecommunications team
about handheld status and
have them ordered during the
preliminary planning
EXCHANGE 2007 T0 OFFICE 365 MIGRATION PROJECT
17
Communication and Reporting Plan
In this project as in any project, operational communication is going to be imperative to
winning in the arena of program unification and project management. The communication
strategy must warrant all participants and contributors concerned with the project are kept up-to-
date in a judicious method, and that material flows spontaneously among the numerous
participants. The precise purpose of this tactic will contain the subsequent motives:
Deliver precise and beneficial statistics, material and updates to the interested
parties.
Hand out intelligence in an appropriate and valuable manner to all backers
Smooth the progress of response controls concerning participants and the
decision-making groups.
The announcement of strategic choices and/or business policy prerequisites
Meetings A consultation arrangement will be created to synchronize project actions and to deliver
consistent apprises on the project to all participants. The conference agenda will be
restructured founded on the essentials of the inclusive project over time; nevertheless, up-to-
date established get-togethers are labeled in the table below.
Figure 5 Standing Meetings Summary
Channel Delivered By Purpose Frequency
Directing
Group/Project
Sponsor
Management/
Project Managers
To apprise senior managers on
project advancement.
Managerial level status exposure
Bi-Weekly
EXCHANGE 2007 T0 OFFICE 365 MIGRATION PROJECT
18
Authorizations as necessitated.
Project Team
Meetings
Project Manager/
Team Members
Project team participants make
available regular status and bring up-
to-date task to the project leads
Twice a
week
Status Reports Systematic status updates will be compulsory to maintain project contributors update
information for both definite project modules and complete project status. The project managers
will produce a project status report. The status report will feature milestone events, tasks,
dependencies and dates indispensable to accomplish the plan.
EXCHANGE 2007 T0 OFFICE 365 MIGRATION PROJECT
19
Status Report
Date: August 16, 2014; 2:00 pm CST
Meeting Subject: Status Meeting for Project 2014EXCH
Attendees:
Jessica Graf (PM)
Amy Bogac (Project Sponsor)
Delina Fournier (Finance)
Robin Beauchamp (IT/Testing/Accountability)
Claire Limoges (Curriculum)
Aries Graf (Operations/Training)
Maggie Lopez (Human Resources)
Meeting Agenda:
Project Status Summary
Project Progress/Accomplishments
Attention Areas
Project Schedule Issues/Updates
Deliverables
Cost Reports
Resource Updates
Goals for Next Review
EXCHANGE 2007 T0 OFFICE 365 MIGRATION PROJECT
20
Meeting Minutes: Jessica Graf the PM for this project began the meeting by introducing the attendees and
going over the agenda for the meeting. In addition, she explained how the meeting was going to
proceed so that all the information in the agenda would be covered and still have time for
questions.
Project Status Summary:
The Project Manager spoke to the status of the project. She was especially
concerned about the progress of the funding and the delays it is causing
The Project Sponsor indicated that the project does not have a budget in place
yet and that she is working on getting the budget approved. She also stressed that this
project needs to be done by end of 1st quarter 2015.
Project Progress/Accomplishments:
Robin Beauchamp spoke to the fact that IT has completed some of the
tasks set forth for them. They confirmed the DNS records and set up Exchange
2007 for Outlook Anywhere. In addition, they have started to prepare the BES
servers in other regions to be decommissioned. According to the regions they are
75% done with transferring their users from BES to using Active Sync on their
blackberry devices.
Maggie Lopez talked about how we have contracted consultants from
both RIM and MS to help with the migration and were waiting to schedule them to be
EXCHANGE 2007 T0 OFFICE 365 MIGRATION PROJECT
21
on site. In addition, the user communication and how the training would be delivered
was also completed.
Attention Areas:
Delina Fournier discussed what is happening with the budget. The biggest area
of concern is the cost of having RIM and MS on site to help with the migration. The
feeling is that it is a waste of project money and that the budget is too high. She
understands this putting the project behind schedule. She is hopeful that the budget can
be finalized this coming week.
Project Schedule Issues/Updates:
Robin Beauchamp discussed that even though they have made headway
in the technical preparation, they cannot do anything further until the budget is
approved and we have a contract signed with Microsoft for Office 365
Maggie Lopez addressed the fact that resources for the project will be slim
during the holiday season (Thanksgiving through New Year’s) which could put
the project further behind.
Claire Limoges discussed that training will need to be scheduled before
the holidays to make sure that trainers and users are available.
EXCHANGE 2007 T0 OFFICE 365 MIGRATION PROJECT
22
Jessica Graf updated the group on the preliminary planning that is all
complete expect for the budget portion. Also, that the Deployment team has been
filled out and are now scheduled to be dedicated to the project for the duration.
She is waiting to hear about the Exchange and BES resource availability if the
project milestones get behind.
Deliverables:
A new WBS was distributed among the project team along with a new
copy of the estimated budget.
A copy of the critical data items were distributed amongst the project team
for review.
Cost Reports:
With the delays we are only 20% done and have spent 31,497.50 of the baseline
budget of 128,585.00. The overall cost variance is 3,301.50 so far
Figure 6: Project Costs
Name Remaining Cost
Actual Cost Cost ACWP
Scope $0.00 $9,600.00 $9,600.00 $9,600.00 Define preliminary resources $0.00 $5,400.00 $5,400.00 $5,400.00 Preliminary planning $2,250.00 $6,697.50 $8,947.50 $6,697.50 Tech Preparation $7,854.00 $1,720.00 $9,574.00 $1,720.00 User Preparation $2,520.00 $7,640.00 $10,160.00 $6,480.00 Training $9,720.00 $440.00 $10,160.00 $0.00
EXCHANGE 2007 T0 OFFICE 365 MIGRATION PROJECT
23
Documentation $8,600.00 $0.00 $8,600.00 $0.00 Pilot $40,560.00 $0.00 $40,560.00 $0.00 Deployment $23,440.00 $0.00 $23,440.00 $0.00 Post Implementation Review $4,320.00 $0.00 $4,320.00 $0.00 Migration completed $0.00 $0.00 $0.00 $0.00
Summary Resources:
The allocation of resources to-date for the project are identified as follows
Figure 7: Resource Allocation Summary
Name Start Finish Remaining Work Management Mon 7/7/14 Mon 2/9/15 19.43 hrs Project Manager Fri 7/11/14 Mon 2/9/15 83.48 hrs Testers Wed 1/28/15 Tue 2/3/15 40 hrs Trainers Fri 8/22/14 Thu 9/18/14 144 hrs Technical Communicators Mon 7/28/14 Thu 11/27/14 176 hrs Deployment Team Fri 7/18/14 Mon 2/9/15 382.57 hrs Network Analyst Thu 7/24/14 Fri 7/25/14 24 hrs Microsoft Resource Wed 7/23/14 Fri 1/23/15 27.07 hrs Exchange Analyst Wed 7/23/14 Tue 2/3/15 79.07 hrs BES Analyst Wed 7/30/14 Thu 2/5/15 71.25 hrs RIM Resource Wed 7/30/14 Thu 2/5/15 31.25 hrs
Goals for Next Week Review:
Table 1: Goals and Responsibility
Goal Item Responsibility
Update on Budget Delina Fournier
Update on Microsoft contract Amy Bogac
EXCHANGE 2007 T0 OFFICE 365 MIGRATION PROJECT
24
Update on Blackberry Devices Robin Beauchamp
Update on Helpdesk documentation Aries Graf
Update on training classes and trainers Aries Graf, Maggie Lopez
Meeting was adjourned at 4:00 pm
Meeting Minutes Approval/Review: August 16, 2014
Approved: August 16, 2014
Jessica Graf Project Manager
EXCHANGE 2007 T0 OFFICE 365 MIGRATION PROJECT
25
Project Dashboard
The following Project Dashboard defines the overall summary of the project health, status, and
accomplishments/issues:
Figure 1: Project Dashboard as of August 16, 2014
Project Summary
Project is currently on Milestone 5
Overall Project Status
Data Warehouse Project (8/16/2014)
Schedule
Project is
behind
schedule by
14 – 30 days
Staffing Still waiting for
Exchange/RIM
resources
Scope Adequate
scope
Budget Budget still
has not been
approved
Dependency Budget must
be approved
Accomplishments
IT has started on the tasks for Technical
Preparation
In house resources have been secured for
the duration
RIM/Exchange 3rd party resources have
been found\
User communication has been completed
Training method has been identified
Urgent Action/Issues
Budget must be approved
Contracts for Office 365 have to be signed
Training and trainers must be scheduled
Exchange 2007 to Office 365 Migration Project Scorecard
1
2
3
4
5
6
7
Y
Y R
G
Y
G
Y
G
G
R
Y
Exchange 2007 to Office 365 Project Page 26
% Complete Task Name
20% Exchange 2007 to Office 365 Migration
100% Scope
100% Determine project scope
100% Secure project sponsorship
99% Define preliminary resources
100% Secure core resources
100% Scope complete
78% Prelimnary planning
45% Budget
67% Review Project Scope with Development team
100% Revise Scope based on Feedback
100% Develop delivery timeline
100% Obtain approvals to proceed (concept, timeline, budget)
100% Preliminary Planning complete
23% Tech Preparation
100% Check the DNS Records for the domain
0% Create the users with email addresse
0% Select the services that will be needed
100% Configure Outlook Anywhere in Exchange 2007
0% Create a Migration Endpoint
0% Create Migration Batch
0% Have Microsoft review Preparation
50% Prep BES servers for decommisioning
0% Present Action plans to Management
0% Approval to go forward
0% Tech prep commplete
60% User Preparation
100% Create User communication
0% Announce migration offically to Company
50% Update Blackberrys to Active Sync
0% User Preparation completed
5% Training
50% Identify training delivery methodology (computer based training, classroom, etc.)
0% Develop training materials
0% Conduct training usability study
0% Finalize training materials
0% Develop training delivery mechanism
0% Training materials complete
0% Documentation
0% Develop Help specification
0% Review Help documentation
0% Incorporate Help documentation feedback
0% Develop user manuals specifications
0% Develop user manuals
0% Review all user documentation
0% Incorporate user documentation feedback
0% Documentation complete
0% Pilot
0% Identify test group
0% Develop software delivery mechanism
0% Migrate the pilot users
0% Obtain user feedback
0% Evaluate testing information
0% Pilot complete
0% Deployment
0% Determine final deployment strategy
27
0% Develop deployment methodology
0% Secure deployment resources
0% Train support staff
0% Run Cut over migration batch
0% Point MX record to Office 365
0% Verify mail flow
0% Verify all mobile devices are syncing correctly with Exchange Active sync
0% Decommission BES servers
0% Deployment complete
0% Post Implementation Review
0% Document lessons learned
0% Distribute to team members
0% Post implementation review complete
0% Migration completed
Work Accomplished
The project tasks completed for this project
Figure 2: WBS Tasks Completed
Task Name Duration Start Finish Resource Names
Determine project scope 3 days Mon 7/7/14 Wed 7/9/14 Management
Secure project sponsorship 2 days Thu 7/10/14 Fri 7/11/14 Management, Project Manager
Secure core resources 2 days Mon 7/14/14 Wed 7/16/14 Project Manager
Scope complete 3 days Wed 7/16/14 Fri 7/18/14 Project Manager
Revise Scope based on Feedback 1 day Fri 7/18/14 Mon 7/21/14 Project Manager
Develop delivery timeline 1 day Mon 7/21/14 Mon 7/21/14 Project Manager
Obtain approvals to proceed
(concept, timeline, budget) 4 hrs Tue 7/22/14 Tue 7/22/14 Management, Project Manager
Preliminary Planning complete 2 days Tue 7/22/14 Wed 7/23/14 Project Manager
Check the DNS Records for the
domain 0.25 days Wed 7/23/14 Wed 7/23/14
Exchange Analyst, Microsoft
Resource
Configure Outlook Anywhere in
Exchange 2007 1 day Thu 7/24/14 Fri 7/25/14
Exchange Analyst, Microsoft
Resource[15%],Network
Analyst[10%]
Create User communication 2 days Mon 7/28/14 Mon 8/4/14 Technical Communicators,
Project Manager, Management
28
Updated WBS The following is the Project’s updated WBS:
Figure 3: Updated WBS
Task Name Duration Start Finish
Exchange 2007 to Office 365
Migration 159 days? Mon 7/7/14 Tue 2/10/15
Scope 5 days Mon 7/7/14 Fri 7/11/14
Determine project scope 3 days Mon 7/7/14 Wed 7/9/14
Secure project sponsorship 2 days Thu 7/10/14 Fri 7/11/14
Define preliminary resources 4 days Mon 7/14/14 Thu 7/17/14
Secure core resources 2 days Mon 7/14/14 Wed 7/16/14
Scope complete 3 days Wed 7/16/14 Fri 7/18/14
Prelimnary planning 10 days Wed 7/16/14 Tue 7/29/14
Budget 2 days Wed 7/16/14 Wed 7/23/14
Review Project Scope with
Development team 2.99 days Fri 7/18/14 Tue 8/5/14
Revise Scope based on
Feedback 1 day Fri 7/18/14 Mon 7/21/14
Develop delivery timeline 1 day Mon 7/21/14 Mon 7/21/14
Obtain approvals to proceed
(concept, timeline, budget) 4 hrs Tue 7/22/14 Tue 7/22/14
Preliminary Planning complete 2 days Tue 7/22/14 Wed 7/23/14
Tech Preparation 7 days? Wed 7/23/14 Thu 7/31/14
Check the DNS Records for the
domain 0.25 days? Wed 7/23/14 Wed 7/23/14
Create the users with email
addresse 0.8 days Wed 7/23/14 Thu 7/24/14
Select the services that will be
needed 2 hrs Thu 7/24/14 Thu 7/24/14
Configure Outlook Anywhere in
Exchange 2007 1 day Thu 7/24/14 Fri 7/25/14
Create a Migration Endpoint 1 day Fri 7/25/14 Fri 7/25/14
Create Migration Batch 0.5 days Mon 7/28/14 Mon 7/28/14
Have Microsoft review
Preparation 8 hrs Mon 7/28/14 Mon 7/28/14
Prep BES servers for
decommisioning 1 day Wed 7/30/14 Wed 7/30/14
Present Action plans to
Management 4 hrs Thu 7/31/14 Thu 7/31/14
Approval to go forward 2 hrs Thu 7/31/14 Thu 7/31/14
Tech prep commplete 1 day Thu 7/31/14 Thu 7/31/14
User Preparation 19.63 days Mon 7/28/14 Fri 8/22/14
Create User communication 2 days Mon 7/28/14 Mon 8/4/14
Announce migration offically to
Company 3 hrs Thu 7/31/14 Wed 8/6/14
Update Blackberrys to Active
Sync 5.63 days Fri 8/15/14 Fri 8/22/14
User Preparation completed 0 days Fri 8/22/14 Fri 8/22/14
29
Training 20 days Fri 8/22/14 Fri 9/19/14
Identify training delivery
methodology (computer based
training, classroom, etc.)
2 days Fri 8/22/14 Tue 8/26/14
Develop training materials 2 wks Tue 8/26/14 Tue 9/9/14
Conduct training usability study 4 days Tue 9/9/14 Mon 9/15/14
Finalize training materials 1 day Mon 9/15/14 Tue 9/16/14
Develop training delivery
mechanism 2 days Tue 9/16/14 Thu 9/18/14
Training materials complete 1 day Thu 9/18/14 Fri 9/19/14
Documentation 22 days Wed 10/29/14 Fri 11/28/14
Develop Help specification 1 day Wed 10/29/14 Wed 10/29/14
Review Help documentation 4 days Thu 10/30/14 Tue 11/4/14
Incorporate Help
documentation feedback 2 days Wed 11/5/14 Thu 11/6/14
Develop user manuals
specifications 3 days Fri 11/7/14 Tue 11/11/14
Develop user manuals 1.5 wks Wed 11/12/14 Fri 11/21/14
Review all user documentation 2 days Fri 11/21/14 Tue 11/25/14
Incorporate user documentation
feedback 2 days Tue 11/25/14 Thu 11/27/14
Documentation complete 0 days Fri 11/28/14 Fri 11/28/14
Pilot 33.33 days Mon 12/1/14 Thu 1/15/15
Identify test group 1 day Mon 12/1/14 Mon 12/1/14
Develop software delivery
mechanism 1 day Tue 12/2/14 Tue 12/2/14
Migrate the pilot users 0.33 days Wed 12/3/14 Wed 12/3/14
Obtain user feedback 6 wks Wed 12/3/14 Wed 1/14/15
Evaluate testing information 1 day Wed 1/14/15 Thu 1/15/15
Pilot complete 0 days Thu 1/15/15 Thu 1/15/15
Deployment 15.67 days Thu 1/15/15 Thu 2/5/15
Determine final deployment
strategy 1 day Thu 1/15/15 Fri 1/16/15
Develop deployment
methodology 1 day Tue 1/20/15 Tue 1/20/15
Secure deployment resources 1 day Wed 1/21/15 Wed 1/21/15
Train support staff 1 day Thu 1/22/15 Thu 1/22/15
Run Cut over migration batch 1 day Fri 1/23/15 Fri 1/23/15
Point MX record to Office 365 2 days Mon 1/26/15 Tue 1/27/15
Verify mail flow 0 days Tue 1/27/15 Tue 1/27/15
Verify all mobile devices are
syncing correctly with Exchange
Active sync
5 days Wed 1/28/15 Tue 2/3/15
Decommision BES servers 2 days Wed 2/4/15 Thu 2/5/15
Deployment complete 0 days Thu 2/5/15 Thu 2/5/15
Post Implementation Review 2 days Fri 2/6/15 Mon 2/9/15
Document lessons learned 1 day Fri 2/6/15 Fri 2/6/15
Distribute to team members 1 day Mon 2/9/15 Mon 2/9/15
Post implementation review
complete 0 days Mon 2/9/15 Mon 2/9/15
Migration completed 1 day Tue 2/10/15 Tue 2/10/15
30
Project Cost Summary With the delays we are only 20% done and have spent 31,497.50 of the baseline budget
of 128,585.00. The overall cost variance is 3,301.50 so far
Figure 4: Project Expenditures Summary
Name Remaining Cost Actual Cost Cost ACWP
Scope $0.00 $9,600.00 $9,600.00 $9,600.00
Define preliminary resources $0.00 $5,400.00 $5,400.00 $5,400.00
Preliminary planning $2,250.00 $6,697.50 $8,947.50 $6,697.50
Tech Preparation $7,854.00 $1,720.00 $9,574.00 $1,720.00
User Preparation $2,520.00 $7,640.00 $10,160.00 $6,480.00
Training $9,720.00 $440.00 $10,160.00 $0.00
Documentation $8,600.00 $0.00 $8,600.00 $0.00
Pilot $40,560.00 $0.00 $40,560.00 $0.00
Deployment $23,440.00 $0.00 $23,440.00 $0.00
Post Implementation Review $4,320.00 $0.00 $4,320.00 $0.00
Migration completed $0.00 $0.00 $0.00 $0.00
31
Resource Usage log The resource usage log is being provided to support the project expenditures to-date:
Figure 5: Resource Log
Name Start Finish Remaining Work
Actual Work
Management Mon 7/7/14 Mon 2/9/15 19.43 hrs 67.13 hrs Project Manager Fri 7/11/14 Mon 2/9/15 83.48 hrs 115.23 hrs Testers Wed 1/28/15 Tue 2/3/15 40 hrs 0 hrs Trainers Fri 8/22/14 Thu 9/18/14 144 hrs 8 hrs Technical Communicators
Mon 7/28/14 Thu 11/27/14
176 hrs 16 hrs
Deployment Team
Fri 7/18/14 Mon 2/9/15 382.57 hrs 0.1 hrs
Network Analyst Thu 7/24/14 Fri 7/25/14 0 hrs 0.8 hrs Microsoft Resource
Wed 7/23/14 Fri 1/23/15 27.07 hrs 3.2 hrs
Exchange Analyst
Wed 7/23/14 Tue 2/3/15 79.07 hrs 10 hrs
BES Analyst Wed 7/30/14 Thu 2/5/15 71.25 hrs 15.25 hrs RIM Resource Wed 7/30/14 Thu 2/5/15 31.25 hrs 15.25 hrs
ISSUE LOG
The following spreadsheet is the Issue Log as of August 16, 2014:
Figure 6: Issue Log
No. Descripti
on Type Priority
(H,M,L) Receipt
Date Originator's
Name Assigned to
Response Date
Status Resolution Close Date Notes/Comments
1 No Office 365 contract
Management H 8/14/2014 Robin Beauchamp
Amy Bogac
8/21/2104 Started Waiting for budget approval
2 Blackberry devices backordered
Operations M 8/12/2014 Aries Graf Aries Graf
8/13/2014 Completed Confirmed New Shipping date
8/13/2014 RIM is shipping all our devices in one order
3 Exchange 2007 needs to patched to get Outlook Anywhere to work
Technical L 8/10/2014 Robin Beauchamp
Robin Beauchamp
8/11/2014 Completed Submitted RFC and patched and reboted servers
8/13/2014
32
4 Holiday Project scheduling
Human Resources
M 8/11/2014 Maggie Lopez Maggie Lopez
8/11/2014 Started
Project Deliverables
The following deliverables have been completed to-date:
Project has been approved
Vendor has been approved
Critical data items have been selected
Project Status Approval:
Prepared Date: August 16, 2014
Prepared By: Jessica Graf
Jessica Graf Project Manager
Approval Date: August 17, 2014
Approved By: Amy Bogac
Amy Bogac Project Sponsor
33
Unplanned Change
Date: August 24, 2014; 2:00 pm CST
Meeting Subject: Status Meeting for Project 2014EXCH
Attendees:
Jessica Graf (PM)
Amy Bogac (Project Sponsor)
Delina Fournier (Finance)
Robin Beauchamp (IT/Testing/Accountability)
Claire Limoges (Curriculum)
Aries Graf (Operations/Training)
Maggie Lopez (Human Resources)
Meeting Agenda:
Project Status Summary
Project Progress/Accomplishments
Attention Areas
Project Schedule Issues/Updates
Deliverables
Cost Reports
Resource Updates
Goals for Next Review
34
Meeting Minutes:
Jessica Graf the PM for this project began the meeting by introducing the attendees and
going over the agenda for the meeting. In addition, she explained how the meeting was going to
proceed so that all the information in the agenda would be covered and still have time for
questions.
Project Status Summary:
The Project Manager spoke to the status of the project. There has been a
unplanned changed in both availability of mobile devices and staffing. The executives
have asked for a wider range of choices when it comes to mobile devices to include
BYOD, IPads and Androids. In addition, because of the delays in approving the funding,
we have lost the Blackberry consultant. Maggie Lopez is looking for a local third party
consultant to fill that position. In addition, the preparations for the user migration has
been pushed back since the contract for Office 365 is being signed on Monday August
27, 2014
Amy Bogac talked about how the mobile device options and loss of the
Blackberry resource is a set back. The project is still on track to be implemented in the
first quarter of next year. There was sufficient time padding around the tasks and
milestones that has left some breathing room. She also reported that the budget has
now been approved. In addition, the Office 365 contract is to be signed on August 25th
and we will have access to our environment by the 27th.
35
Project Progress/Accomplishments:
Robin Beauchamp reported that we are now receiving Blackberrys on schedule.
Maggie Lopez and Aries Graf reported that the training delivery method has been
decided. Users will be using computer based training program and putting that together
is ahead of scheduled.
Project Schedule Issues/Updates:
Robin Beauchamp discussed that because of the delay in the Office 365
contract, it has pushed the preparation of that environment back almost 30 days.
However, by having a secondary Exchange resource attached to the project, we can
handle shorten time frame.
Maggie Lopez spoke to the fact that training and documentation is ahead
of schedule right now and that by using the computer based training, we should be
able to lessen the impact of the holiday period to the project.
Jessica Graf updated the group on the preliminary planning that finally
completed. Also, that the Deployment team has been filled out and are now
scheduled to be dedicated to the project for the duration. Even though the Office
365 contract is behind because of the extra resources built into the team and the
work that has already been done, she feels confident that the project will be
completed with the first quarter of next year. She is waiting to hear if we have found
a Blackberry resource locally to backfill the resource that was lost.
36
Deliverables:
A new WBS was distributed among the project team along with a new copy of the
estimated budget.
A copy of the critical data items were distributed amongst the project team for
review.
Cost Reports:
With the delays we are only 20% done and have spent 54,260.00 of the baseline
budget of 128,585.00. The overall cost variance is 25,444.00 so far
Figure 1: Project Costs
Name Remaining Cost
Actual Cost Cost ACWP
Scope $0.00 $9,600.00 $9,600.00 $9,600.00
Define preliminary resources $0.00 $5,400.00 $5,400.00 $5,400.00
Prelimnary planning $0.00 $28,470.00 $28,470.00 $21,195.00
Tech Preparation $6,614.00 $1,080.00 $7,694.00 $1,080.00
User Preparation $8,730.00 $7,730.00 $16,460.00 $6,860.00
Training $8,180.00 $1,980.00 $10,160.00 $0.00
Documentation $8,600.00 $0.00 $8,600.00 $0.00
Pilot $39,960.00 $0.00 $39,960.00 $0.00
Deployment $22,240.00 $0.00 $22,240.00 $0.00
Post Implementation Review $4,320.00 $0.00 $4,320.00 $0.00
37
Summary Resources:
The allocation of resources to-date for the project are identified as follows
(Figure 1):
Figure 2: Resource Allocation Summary
Name Start Finish Remaining Work Management Mon 7/7/14 Mon 2/9/15 19.43 hrs Project Manager Fri 7/11/14 Mon 2/9/15 83.48 hrs Testers Wed 1/28/15 Tue 2/3/15 40 hrs Trainers Fri 8/22/14 Thu 9/18/14 144 hrs Technical Communicators Mon 7/28/14 Thu 11/27/14 176 hrs Deployment Team Fri 7/18/14 Mon 2/9/15 382.57 hrs Network Analyst Thu 7/24/14 Fri 7/25/14 24 hrs Microsoft Resource Wed 7/23/14 Fri 1/23/15 27.07 hrs Exchange Analyst Wed 7/23/14 Tue 2/3/15 79.07 hrs
Goals for Next Week Review:
Table 1: Goals and Responsibility
Goal Item Responsibility
Update on Blackberry Resource Delina Fournier
Update on Microsoft contract Amy Bogac
Update on Apple and Android Devices Robin Beauchamp
Update on Helpdesk documentation Aries Graf
Update on training classes and documentation
Aries Graf, Maggie Lopez
38
Meeting was adjourned at 4:00 pm
Meeting Minutes Approval/Review: August 24, 2014
Approved: August 24, 2014
Jessica Graf Project Manager
39
Project Dashboard The following Project Dashboard defines the overall summary of the project health, status, and
accomplishments/issues:
Figure 1: Project Dashboard as of August 16, 2014
Project Summary
Project is currently on Milestone 5
Overall Project Status
Schedule
Project is
behind
schedule by
14 – 30 days
Staffing Still waiting for
Exchange/RIM
resources
Scope Adequate
scope
Budget Budget still
has been
approved
Dependency Budget must
be approved
Accomplishments
IT has started on the tasks for Technical
Preparation
In house resources have been secured for
the duration
User communication has been completed
Migration has been announced
User Test group identified
Training method has been identified
Urgent Action/Issues
Budget must be approved
Contracts for Office 365 have to be signed
Blackberry resource needs to be found
Research into other devices must be
completed
Exchange 2007 to Office 365 Migration Project Scorecard
1
2
3
4
5
6
7
Y
Y R
G
R
G
Y
G
G
GR
G
40
Exchange 2007 to Office 365 Migration Project Proposal
Work Accomplished The project tasks completed for this project
Figure 2: WBS Tasks Completed
Task Name % Complete
Exchange 2007 to Office 365 Migration 33%
Scope 100%
Determine project scope 100%
Secure project sponsorship 100%
Define preliminary resources 100%
Secure core resources 100%
Scope complete 100%
Preliminary planning 100%
Budget 100%
Review Project Scope with Development team 100%
Revise Scope based on Feedback 100%
Develop delivery timeline 100%
Obtain approvals to proceed (concept, timeline, budget) 100%
Preliminary Planning complete 100%
Check the DNS Records for the domain 100%
Configure Outlook Anywhere in Exchange 2007 100%
Prep BES servers for decommissioning 100%
Create User communication 100%
Announce migration officially to Company 100%
41
Exchange 2007 to Office 365 Migration Project Proposal
Updated WBS
The following is the Project’s updated WBS:
Figure 3: Updated WBS
Task Name Duration Start Finish
Scope 5 days Mon 7/7/14 Fri 7/11/14
Determine project scope 3 days Mon 7/7/14 Wed 7/9/14
Secure project sponsorship 2 days Thu 7/10/14 Fri 7/11/14
Define preliminary resources 4 days Mon 7/14/14 Thu 7/17/14
Secure core resources 2 days Mon 7/14/14 Wed 7/16/14
Scope complete 3 days Wed 7/16/14 Fri 7/18/14
Preliminary planning 31 days Wed 7/16/14 Wed 8/27/14
Budget 24.19 days Wed 7/16/14 Wed 8/27/14
Review Project Scope with Development team 2 days Fri 7/18/14 Mon 7/21/14
Revise Scope based on Feedback 1 day Fri 7/18/14 Mon 7/21/14
Develop delivery timeline 1 day Mon 7/21/14 Mon 7/21/14
Obtain approvals to proceed (concept, timeline, budget)
4 hrs Tue 7/22/14 Tue 7/22/14
Preliminary Planning complete 2 days Tue 7/22/14 Wed 7/23/14
Tech Preparation 32.25 days? Wed 7/23/14 Fri 9/5/14
Check the DNS Records for the domain 0.25 days? Wed 7/23/14 Wed 7/23/14
Create the users with email addressed 0.8 days Wed 8/27/14 Wed 8/27/14
Select the services that will be needed 2 hrs Thu 8/28/14 Thu 8/28/14
Configure Outlook Anywhere in Exchange 2007 1 day Thu 7/24/14 Fri 7/25/14
Create a Migration Endpoint 1 day Fri 8/29/14 Fri 8/29/14
Create Migration Batch 0.5 days Mon 9/1/14 Mon 9/1/14
Have Microsoft review Preparation 8 hrs Wed 9/3/14 Wed 9/3/14
Prep BES servers for decommissioning 1 day Wed 7/30/14 Thu 9/4/14
Present Action plans to Management 4 hrs Thu 9/4/14 Thu 9/4/14
Approval to go forward 2 hrs Fri 9/5/14 Fri 9/5/14
User Preparation 41.19 days Mon 7/28/14 Sun 9/21/14
Create User communication 2 days Mon 7/28/14 Mon 8/4/14
Announce migration officially to Company 2.25 hrs Wed 8/6/14 Wed 8/6/14
Update Blackberrys to Active Sync 21 days Fri 8/15/14 Sun 9/21/14
Training 33.38 days Fri 8/22/14 Mon 10/6/14
Identify training delivery methodology (computer based training, classroom, etc.)
2 days Fri 8/22/14 Mon 9/15/14
Develop training materials 2 wks Tue 9/16/14 Thu 9/25/14
Conduct training usability study 4 days Fri 9/26/14 Wed 10/1/14
Finalize training materials 1 day Thu 10/2/14 Thu 10/2/14
42
Exchange 2007 to Office 365 Migration Project Proposal
Develop training delivery mechanism 2 days Fri 10/3/14 Mon 10/6/14
Documentation 21.5 days Wed 10/29/14
Thu 11/27/14
Develop Help specification 1 day Wed 10/29/14
Wed 10/29/14
Review Help documentation 4 days Thu 10/30/14
Tue 11/4/14
Incorporate Help documentation feedback 2 days Wed 11/5/14 Thu 11/6/14
Develop user manuals specifications 3 days Fri 11/7/14 Tue 11/11/14
Develop user manuals 1.5 wks Wed 11/12/14
Fri 11/21/14
Review all user documentation 2 days Fri 11/21/14 Tue 11/25/14
Incorporate user documentation feedback 2 days Tue 11/25/14
Thu 11/27/14
Pilot 32.33 days Mon 7/7/14 Wed 8/20/14
Develop software delivery mechanism 1 day Mon 7/7/14 Mon 7/7/14
Migrate the pilot users 0.33 days Tue 7/8/14 Tue 7/8/14
Obtain user feedback 6 wks Tue 7/8/14 Tue 8/19/14
Evaluate testing information 1 day Tue 8/19/14 Wed 8/20/14
Deployment 156 days Mon 7/7/14 Thu 2/5/15
Determine final deployment strategy 1 day Mon 7/7/14 Mon 7/7/14
Develop deployment methodology 1 day Tue 1/20/15 Tue 1/20/15
Secure deployment resources 1 day Wed 1/21/15 Wed 1/21/15
Train support staff 1 day Thu 1/22/15 Thu 1/22/15
Run Cut over migration batch 1 day Fri 1/23/15 Fri 1/23/15
Point MX record to Office 365 2 days Mon 1/26/15 Tue 1/27/15
Verify mail flow 0 days Tue 1/27/15 Tue 1/27/15
Verify all mobile devices are syncing correctly with Exchange Active sync
5 days Wed 1/28/15 Tue 2/3/15
Decommission BES servers 2 days Wed 2/4/15 Thu 2/5/15
Post Implementation Review 2 days Fri 2/6/15 Mon 2/9/15
Document lessons learned 1 day Fri 2/6/15 Fri 2/6/15
Distribute to team members 1 day Mon 2/9/15 Mon 2/9/15
Post implementation review complete 0 days Mon 2/9/15 Mon 2/9/15
43
Exchange 2007 to Office 365 Migration Project Proposal
Project Budget Summary
With the delays we are only 20% done and have spent 31,497.50 of the baseline
budget of 128,585.00. The overall cost variance is 3,301.50 so fa
Figure 4: Project Expenditures Summary
Name Remaining Cost Actual Cost Cost ACWP
Scope $0.00 $9,600.00 $9,600.00 $9,600.00
Define preliminary resources $0.00 $5,400.00 $5,400.00 $5,400.00
Preliminary planning $2,250.00 $6,697.50 $8,947.50 $6,697.50
Tech Preparation $7,854.00 $1,720.00 $9,574.00 $1,720.00
User Preparation $2,520.00 $7,640.00 $10,160.00 $6,480.00
Training $9,720.00 $440.00 $10,160.00 $0.00
Documentation $8,600.00 $0.00 $8,600.00 $0.00
Pilot $40,560.00 $0.00 $40,560.00 $0.00
Deployment $23,440.00 $0.00 $23,440.00 $0.00
Post Implementation Review $4,320.00 $0.00 $4,320.00 $0.00
Migration completed $0.00 $0.00 $0.00 $0.00
44
Exchange 2007 to Office 365 Migration Project Proposal
Resource Usage Log The resource usage log is being provided to support the project expenditures to-date:
Figure 5: Resource Log
Name Start Finish Remaining Work
Actual Work
Management Mon 7/7/14 Mon 2/9/15 19.43 hrs 67.13 hrs Project Manager Fri 7/11/14 Mon 2/9/15 83.48 hrs 115.23 hrs Testers Wed 1/28/15 Tue 2/3/15 40 hrs 0 hrs Trainers Fri 8/22/14 Thu 9/18/14 144 hrs 8 hrs Technical Communicators
Mon 7/28/14 Thu 11/27/14
176 hrs 16 hrs
Deployment Team
Fri 7/18/14 Mon 2/9/15 382.57 hrs 0.1 hrs
Network Analyst Thu 7/24/14 Fri 7/25/14 0 hrs 0.8 hrs Microsoft Resource
Wed 7/23/14 Fri 1/23/15 27.07 hrs 3.2 hrs
Exchange Analyst
Wed 7/23/14 Tue 2/3/15 79.07 hrs 10 hrs
BES Analyst Wed 7/30/14 Thu 2/5/15 71.25 hrs 15.25 hrs RIM Resource Wed 7/30/14 Thu 2/5/15 31.25 hrs 15.25 hrs
Issue Log
The following spreadsheet is the Issue Log as of August 24, 2014:
Figure 6: Issue Log
No. Descripti
on Type Priority
(H,M,L) Receipt
Date Originator's
Name Assigned to
Response Date
Status Resolution Close Date Notes/Comments
1 No Office 365 contract
Management H 8/14/2014 Robin Beauchamp
Amy Bogac
8/21/2104 Started Waiting for budget approval
2 Blackberry devices backordered
Operations M 8/12/2014 Aries Graf Aries Graf
8/13/2014 Completed Confirmed New Shipping date
8/13/2014 RIM is shipping all our devices in one order
45
Exchange 2007 to Office 365 Migration Project Proposal
3 Exchange 2007 needs to patched to get Outlook Anywhere to work
Technical L 8/10/2014 Robin Beauchamp
Robin Beauchamp
8/11/2014 Completed Submitted RFC and patched and reboted servers
8/13/2014
4 Holiday Project scheduling
Human Resources
M 8/11/2014 Maggie Lopez Maggie Lopez
8/11/2014 Started
PROJECT DELIVERABLES
The following deliverables have been completed to-date:
Project has been approved
Vendor has been approved
Critical data items have been selected
Project Status Approval:
Prepared Date: August 24, 2014
Prepared By: Jessica Graf
Jessica Graf Project Manager
Approval Date: August 25, 2014
Approved By: Amy Bogac
Amy Bogac Project Sponsor
46
Exchange 2007 to Office 365 Migration Project Proposal
Project Closure Report
PROJECT CLOSURE REPORT PURPOSE
The Project Closure report is meant as a guide to upper management to assess how
the project performed and the results of the final outcome. It will provide a roadmap to how the
project is to be closed down and what is still left to be accomplished.
PROJECT CLOSURE REPORT GOALS
Milestones
The milestones in this project included:
1. Scope
2. Defining resources
3. Preliminary Planning
4. Technical Preparation
5. User Preparation
6. Training
7. Documentation
8. Pilot
9. Deployment
10. Review
47
Exchange 2007 to Office 365 Migration Project Proposal
While all the milestones were met, so of the dates in the timeline had to be moved
about due issues with budget and resources availability. We were able to work around the
issues because of redundancy of resources. But we were able to finish most milestones
before their deadlines and only slightly over budget. An area that was very successful was
implementing computer based training for the new processes involved in connecting mobile
devices to Office 365
Outstanding Issues, Risks, and Recommendations
There are still some issues and risks that are present since some of the users have not
been completed the computer based training. Since it is a policy not to give access to a
mobile device until the training is completed. This poses a risk since we have a percentage of
users that are forwarding their email from their corporate accounts to the mobile devices that
they own. The telecom department is looking into getting these users into compliance. The
recommendation is to get all users to finish the training
Tasks and Activities required to close the Project
The tasks that are required to close out the project is to make sure that all email
accounts have successfully migrated to Office 365. Once that is done the Exchange servers
will be decommissioned and with the BES servers they will repurposed to new uses. There
are will a series of meetings to make sure that Operations are clear on how the new
environment will be supported and administered
Project highlights and Best Practices
Some of the highlights of this project was being able to pull an incredibly talented team
together, which made it their goal to get this project in on time. Another highlight was the
48
Exchange 2007 to Office 365 Migration Project Proposal
ability to use the new computer based training system to deliver not only end user, but training
to the support desk as well.
The best practices that worked in this project were the redundancy of resources and
the padding of the timeline in order to assure completion of the project on time. Some things
that are lessons learned are that we should have the budget approve and contracts signed
before starting any work so that we could have gotten the 3rd party vendor support that we
needed for some stages of the project.
PROJECT CLOSURE REPORT SUMMARY
Project Background Overview
The issue facing Circe Inc. is the growing cost of maintaining and upgrading the
current Exchange 2007 and the Blackberry Enterprise environments. The cost of maintaining
a 24/7 environment for a global company of 1000 users is continuing to stretch the budget and
the IT resources. The amount of time spend patching, troubleshooting and updating servers
and mobile devices leave the current IT department shorthanded to meet the needs of the
software developers as far as server builds and maintaining the development environment.
This purpose of this project is migrate Circe Inc.’s current Exchange 2007 environment
to the Office 365. The project will cover migration and both user and support training for the
new product. In addition, the Blackberry Enterprise servers will be decommissioned and the
current mobile devices, including Blackberrys will be configured to use Active Sync.
49
Exchange 2007 to Office 365 Migration Project Proposal
Project Highlights and Best Practices
Project Highlights and Best Practices
Project Highlights:
Great project team
Finishing on time.
Use of the new training system
Global collaboration Best Practices:
Resource Redundancy
Efficient time and resource planning
Project Closure Synopsis The project is being closed since all the deliverables have been met and the migration
is finished. Even though there was some shift in strategy surrounding the policy of BYOD it
was not enough to close out the project for this migration.
PROJECT METRICS PERFORMANCE
Goals and Objectives Performance
While we did finish on time, the issues that caused delays like the signing of the
contract with Microsoft did have an impact on certain tasks. It forced us to put more resources
on the tasks at hand which drove the cost of those tasks over budget.
Success Criteria Performance The success criteria were that all email be moved to the new environment and that
BES be decommissioned. This was completed along with user and support desk training. The
one measure of success that was not met was the budget which was approx. 25,000 over
50
Exchange 2007 to Office 365 Migration Project Proposal
Milestone and Deliverables Performance The milestones were met in this project in a timely manner. While there were some
quality issues when it came to the timely delivery of hand held devices for RIM and some
support areas that needed to be addressed. All have been corrected and continuing training
will keep the processes up to date.
Schedule Performance
0 hrs
50 hrs
100 hrs
150 hrs
200 hrs
250 hrs
300 hrs
Actual Work Actual Duration
51
Exchange 2007 to Office 365 Migration Project Proposal
Budget Performance
Metrics Performance Recommendations
The metrics I would recommend in the next project would definitely be budget, cost
variance and resource allocation. By following these I think we would have been able to
control the overspending on the over time that we needed to complete the project on time.
PROJECT CLOSURE TASKS
Resource Management
The resources that changed during the project was that we lost a couple of 3rd party
resources because of the delay in finalizing the budget and the contracts for these resources.
This forced us to find other 3rd party consultants locally which were more expensive.
52
Exchange 2007 to Office 365 Migration Project Proposal
We will be transferring project resources to other projects by assigning them to other
projects that have come out of this one. One project will to review and develop new processes
for the BYOD policy and Office 365. The resources will spilt their time between the closing
activities on this project and their new assignment and eventually move over completely. The
development team will move into a more administrative role for Office 365.
There will knowledge transfer from this project into the Oracle Knowledge Base as to
what technology was used and how it was deployed, policy and procedures that were
implemented and troubleshooting steps for the issues that were encountered in the migration.
Issue Management
The outstanding issues for this project are:
1. Getting users to complete the training need for the new platform and connecting BYOD
and company owned devices.
2. Getting the documentation from the project into the knowledge base.
3. Working with Microsoft to solve some of the technical issues like connectivity and
administration documentation
Each issue will be resolved by project resources. The training resources will report on
the training issues and documentation. One resource from the deployment team will work with
Microsoft to finish the tasks needed.
53
Exchange 2007 to Office 365 Migration Project Proposal
Risk Management Project Risks Mitigated
Decommissioning the Blackberry servers
Migration of email accounts to Office 365
User adoption of the new system
Support Desk training
Outstanding Project Risks
User Training
Continuing training and knowledge transfer
Administrative training in Office 365
Transitioning deployment to administrative roles
Quality Management
The quality management processes that were used during the project was user
feedback at the pilot and testing phase. The testing phase was all about how connectivity and
how the servers in the Office 365 environment. This meant doing jet stress testing and load
testing of the servers, in addition to how the environment would be maintained.
The pilot phase involved a group of power users and their feedback to how Office 365
performed in areas like usability of the product. When there was an issue with the product, the
deployment team worked with Microsoft to resolve the issues.
Quality control was based on feedback from such areas of the project like deployment
team and pilot users and it was addressed by stakeholders and the project managers to make
sure that any quality issues were addressed in a timely manner.
54
Exchange 2007 to Office 365 Migration Project Proposal
Communication Management
The preferred communication process was status reports that were do weekly from the
project team to the project manager. These status reports were discussed at a weekly
meetings with the stake holders and team leads from different areas of the project. If there
was a urgent issue, it was brought to the attention of the project manager and was
communicated to the stakeholders along with the impact to the project.
The process was effective in the beginning, however by the time we got to migrating
the mailboxes and mobile devices to the new environment, the team found that quick daily
status reports kept the team on top of issues more efficiently. Once the migration was
completed, the status reports went back to the weekly timeline.
Another communication process that was successful was using project server and a
web page for up to date status on the project along with a discussion board and Wiki for any
issues and how they were resolved.
Customer Expectation Management
The customer expectations were managed by the stakeholders in the project by
meeting with users in town hall meetings. Stakeholders then brought back customer
expectations that weren’t being met like the BYOD aspect. The deployment team then looked
at where they could fit that into the current project plan and what would be needed.
The stakeholders and the project manager communicated back to the users
(customers) what we could do in the project and what would have to be made into a new
project for future functionality for Office 365 like SharePoint and Lync. We also provided a
status page for the users to see where the project and what functionality was available.
55
Exchange 2007 to Office 365 Migration Project Proposal
Asset Management
The assets remaining at the end of the project are the servers used to run Exchange
and Blackberry. Each region will be responsible for giving these assets back to their internal IT
so that they can be used in other capacities.
The disposition process will be to decommission the servers which the deployment
team will handle and removing the physically from the current internal environment. If the
server is not capable of being used either in production or in test lab, regional operational
teams will be responsible for wiping the servers of all business data including OS and files.
Then they will remove hard drives to be destroyed and the cases will be recycled.
Lessons Learned
The processed that worked well was the redundancy of resources and the transfer of
knowledge between the resources. Also, the communication process was successful in
keeping all parties involved in the project up to date especially the web page and using project
server.
What did not work so well was the process of getting the budget and needed 3rd party
resources for the project. It way too long to get contracts and budgets approved. If we had
been able to have the budget approved and the contracts before the start of the project we
would have not had to pay the extra cost for local consultants. The process used to get the
project on the books and funded needs to be streamlined. This can be done by having a
committee do the approving instead of having to get every upper level executive to approve
the project.
Project Closure Recommendations The recommendation is that the all of the objectives of the project have been met. The
stakeholders agree that the migration has been finished the agreed terms and that there are
56
Exchange 2007 to Office 365 Migration Project Proposal
other projects to handle such areas of policy and procedures around the BYOD program. The
outstanding issues such as users completing the training and knowledge transfer have been
mitigated.
57
Exchange 2007 to Office 365 Migration Project Proposal
PROJECT CLOSURE REPORT APPROVALS Prepared By _________Jessica Graf_________________________ (Project Manager) Approved By _____Amy Bogac_____________________________ (IT director) __________________________________ ([Job Title]) __________________________________ ([Job Title]) Approval Date ___9/13/2014_______________________________