Earthquake Emergency Assistance Project: Environmental ...
-
Upload
khangminh22 -
Category
Documents
-
view
4 -
download
0
Transcript of Earthquake Emergency Assistance Project: Environmental ...
Environmental Compliance Monitoring Report
Semi-Annual Report 6
Loan Number: L3260 NEP
Project Number: 49215-001
July 2019
Nepal: Earthquake Emergency Assistance Project
Prepared by the Government of Nepal for the Asian Development Bank.
This environmental monitoring report is a document of the borrower. The views expressed herein do not
necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in
nature. Your attention is directed to the “terms of use” section of this website.
In preparing any country program or strategy, financing any project, or by making any designation of or
reference to a particular territory or geographic area in this document, the Asian Development Bank does
not intend to make any judgments as to the legal or other status of any territory or area.
i
Environmental Monitoring Report
Semi-Annual Report No. 6
Loan Number: 3260 NEP January – June 2019
Nepal: Earthquake Emergency Assistance Project
(Consolidated Report for Roads –District & Strategic, Schools and Office Buildings)
Prepared by the Government of Nepal for the Asian Development Bank.
Semiannual Environmental Monitoring Report January - June 2019
Earthquake Emergency Assistance Project ii
This environmental Compliance Monitoring Report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. Your attention is directed to the “terms of use” section of this website. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area. CURRENCY EQUIVALENTS
Currency unit - Nepalese Rupee (NRs)
NRs. 1.00 = $ 0.009
US $ 1.00 = NRs. 110.13
Source: Nepal Rastra Bank, 30 June, 2019
NOTES
(i) The fiscal year (FY) of the Government of Nepal and its agencies ends on 15 July. FY
before a calendar year denotes the year in which the fiscal year ends, e.g., FY 2018
ends on 16 July 2019.
(ii) In this report, "$" refers to US dollars.
Semiannual Environmental Monitoring Report January - June 2019
Earthquake Emergency Assistance Project iii
ABBREVIATIONS
ADB Asian Development Bank
BoQ Bill of Quantity BS Bikram Sambat (Nepali Calendar)
CFUG Community Forest Users Group
CISC Central Implementation Support Consultant
CLPIU Central Level Project Implementation Unit
DCC District Coordination Committee DDR Due Diligence Report
DFO District Forest Officer
DSC Design and Supervision Consultant
DISC District Implementation Support Consultant DLPIU District Level Project Implementation Unit
DoR Department of Roads
DUDBC Department of Urban Development and Building Construction
DTO District Technical Office EEAP Earthquake Emergency Assistance Project
EMP Environmental Management Plan
FY Fiscal Year
GoN Government of Nepal GRC Grievance Redress Committee
GMaLI Grant Management and Local Infrastructure
IEE Initial Environmental Examination
MoE Ministry of Education MoFALD Ministry of Federal Affairs & Local Development
MoUD Ministry of Urban Development
MoFE Ministry of Forest and Environment
NRA National Reconstruction Authority NRs Nepali Rupees
PD Project Directorate
SDC Swiss Agency for Development and Cooperation
Semiannual Environmental Monitoring Report January - June 2019
Earthquake Emergency Assistance Project iv
Table of Contents
1. Project Background 1
2. Impact and Outcome 1
3. Environmental Safeguards in EEAP 2
4. Overall Environmental Safeguard Status 2
5. Semi-annual Environmental Monitoring Report 2
Part 1: District Roads 3
Part 2: Strategic Roads 45
Part 3: School Buildings 62
Part 4: Government Buildings 103
Environmental Compliance Monitoring Report
January-June, 2019
Earthquake Emergency Assistance Project 1
1. PROJECT BACKGROUND
1. Earthquake Emergency Assistance Project (EEAP) is a project being implemented by
covenant loan assistance from Asian Development Bank (ADB) and counterpart funding from
Government of Nepal (GoN). The goal of the project is to support Government of Nepal to
accelerate rehabilitation and reconstruction following the devastating earthquake of 25 April
2015 and the major aftershock of 12 May 2015. The project will support the rebuilding of
schools, roads, and district-level government buildings, and strengthen resilience to future
disasters.
2. EEAP, Loan 3260 for $200 M was approved on 24 June 2015, signed on 21 August
2015 and became effective on 10 September 2015 with the objective of supporting the GoN.
2. IMPACT AND OUTCOME
3. The impact of the project is accelerated economic and social recovery in Nepal’s earthquake affected districts. The outcome will be critical economic and social services
resumed with disaster-resilient infrastructure.
4. The project has following four outputs:
(i) Output 1: Schools are rebuilt and upgraded. At least 700 schools will be rebuilt or
retrofitted in line with school reconstruction plans to disaster-resilient standards and equipped
with water and sanitation facilities, including sex-disaggregated toilets. About five will be model
schools built with information and communication technology equipment, science laboratories,
and improved learning spaces. However, target has been reduced 154 school buildings (MTR,
October 2017).
(ii) Output 2: Roads and bridges are rehabilitated and/or reconstructed. About 135 km of
strategic roads and about 450 km of rural roads damaged by the earthquake and landslides
will be rehabilitated. Target for strategic and district roads has been reduced to 123.9 km and
525 km respectively (MTR, October 2017). Project roads and bridges will have built back
better features for road safety and climate resilience. Construction and maintenance
equipment will also be procured.
(iii) Output 3: District-level government facilities constructed and/or rebuilt. About 300
district-level government buildings will be rebuilt or retrofitted to disaster resilient standards
with basic utilities, and furnished. This target has been reduced to 123 buildings (MTR,
October 2017). Transitional district-level government offices will also be established to enable
services to continue throughout the reconstruction period.
(iv) Output 4: Disaster preparedness and management capacities strengthened. All
outputs are assured to be disaster risk resilient. Engineering divisions of all implementing
agencies will be strengthened.
5. The district roads components has received technical assistance grant from Swiss
Agency for Development and Cooperation (SDC). Also, the scope of output 1 was increased
in December 2016 to include 15 additional schools to be rebuilt following the additional $ 10
million financing from the United States Agency for International Development (USAID – Grant
0529).
Environmental Compliance Monitoring Report
January-June, 2019
Earthquake Emergency Assistance Project 2
3. ENVIRONMENTAL SAFEGUARDS IN EEAP
6. An Environmental Assessment and Review Framework (EARF) was prepared in
accordance with ADB’s Safeguards Policy Statement 2009. Initial environmental examinations (IEEs) and environmental management plans (EMPs) were required for district and strategic
roads where as due diligence report (DDR) with EMP were required for school and office
building sub-projects along with incorporating EMP into bidding and contract documents to be
implemented by contractors.
7. The Central Level Project Implementation Units (CLPIUs) have been assisted by
Design and Supervision Consultants (DSCs) which will include Environment Specialists
engaged during project implementation. CLPIUs prepare environmental safeguard documents
for approved sub-projects which receive concurrence from ADB and approval from concerned
agencies of GoN. CLPIUs obtain all clearances and fulfill government requirements. The
District Level Project Implementation Units (DLPIUs) have a safeguards focal person who is
responsible for data required for safeguards plan preparation, monitoring and progress
reports, and coordination with relevant organizations like Ministry of Forest and Environment
(MoFE) to consult and/or obtain endorsement if necessary. CLPIUs and DLPIUs are supported
by DSCs/Central Implementation Support Consultant (CISC)/District Implementation Support
Consultants (DISCs).
4. OVERALL ENVIRONMENTAL SAFEGUARD STATUS
8. The overall environmental safeguard status of EEAP in reference to its output is listed
below:
(i) Output 1- School Buildings: For school building sub-projects, DDRs with EMP preparation
have been completed.
(ii) Output 2a- District Roads: All IEE reports of 17 road sub-projects have been approved
from the Government of Nepal (GoN) and concurrence has been given by ADB.
(iii) Output 2b- Strategic Roads: IEE of all three roads sub-project namely, Dolakha-Singati
Road, Dhading –Gorkha Road and Pachakhal-Melamchi Road has been approved by the GoN
and ADB.
(iv) Output 3- Office buildings: For government office buildings, DDRs with EMP for the
sub-projects have been prepared.
5. SEMI-ANNUAL ENVIRONMENTAL MONITORING REPORT
9. According to EARF, each CLPIUs with DSC support has to prepare and submit semi-
annual monitoring reports (SMRs) to ADB, one from January-June and other July-December
of each year by the 15th of next month.
10. This semi-annual environmental monitoring report no. 6 (January-June 2019) for EEAP
has been consolidated on the basis of SMR prepared by the concerned CLPIUs as given in
Part 1 for GMaLI (district roads), Part 2 for Project Directorate (staretegic roads), Part 3 for
CLPIU (Schools), and Part 4 for CLPIU (Office Buildings).
Environmental Compliance Monitoring Report
January-June, 2019
Earthquake Emergency Assistance Project 3
PART 1: DISTRICT ROADS
Environmental Compliance Monitoring Report
January-June, 2019
Earthquake Emergency Assistance Project 4
Table of Content
1. Background 5
2. Environmental safeguards in EEAP 7
3. Overall Environmental Safeguards Status 7
4. Construction Approach 7
5. Compliance Status with Environmental Covenants 8
6. Compliance Status with Environmental Safeguard Measures 8
7. Issues and Way Forward 16
8. Achievement on Major Items of Focus on Previous Report 17
9. Major Items of Focus for Next Report 18
List of Tables
Table 1. List of Events on Orientation on Environmental Safeguard & Awareness 9
Table 2. List of Events on Orientation on Waste Management 10
Table 3. Estimated, Revised and Carried out Compensatory Plantation Activities 13
Table 4. Status of Revised Target and Achieved Plantation 13
Table 5. Detail of Roadside Plantation 14
Table 6. Date and Name of Districts Visited 16
Table 7. Issues and Way Forward 17
Table 8. Status of Items of Focus on Previous Report 17
Table 9. Items of Focus for Next Report 18
List of Figures
Figure 1. Map of Nepal showing Districts of EEAP 6
Figure 2. Map showing Road subprojects in Districts of EEAP 6
Figure 3. Types of Forest with Vegetation Loss and Area 11
Figure 4. Revised and Targeted Compensatory Plantation in Subprojects 12
List of Annexes
Annex 1. Environmental Safeguard Planning Status
Annex 2. Environmental Safeguard Implementation Status
Annex 3. Status of Compliance with Relevant Covenants
Annex 4. Environmental Management Cost
Annex 5. Status of Environmental Safeguard Compliance
Annex 6. Detail on Forestry Clearance
Annex 7. Detail on Tree Loss, Targeted Plantation and Cost
Annex 8. Spoil Management Disposal Format
Annex 9. Environmental Safeguard Compliance Monitoring Format
Annex 10. Photographs
Environmental Compliance Monitoring Report
January-June, 2019
Earthquake Emergency Assistance Project 5
1. Background
Earthquake Emergency Assistance Project (EEAP) is a project being implemented by loan
assistance from the Asian Development Bank (ADB), technical assistance from Swiss Agency
for Development and Cooperation (SDC) and counterpart funding from Government of Nepal
(GoN). EEAP has been supporting GoN to accelerate recovery and reconstruction following
the devastating earthquake of 25 April 2015 and the major aftershock of 12 May 2015. The
project covers 12 affected districts in eastern, middle and western development region of
Nepal1.
The Project will restore and strengthen the resiliency of critical public and social infrastructure
and services and has four outputs; Output 1: Schools are rebuilt and upgraded, Output 2:
Roads and bridges are rehabilitated and/or reconstructed, Output 3: District-level government
facilities constructed and/or rebuilt, Output 4: Disaster preparedness and management
capacities strengthened.
Under Output 2, strategic roads and district roads damaged by the earthquake and landslides
are under rehabilitation. Project roads and bridges will have built back better features for road
safety and climate resilience. The initial target of district roads component was rehabilitation
and reconstruction of 450 km. A total of 25 potential road sub-projects (474.7 km) had been
identified for rehabilitation and reconstruction in 12 sub-projects districts under EEAP2.
However, 17 road sub-projects (325 km) has been prioritized for rehabilitation and
reconstruction due to budget constraint (please refer Figure 1 and 2 for project location).
National Reconstruction Authority (NRA) is executing agency for EEAP. NRA has established
Central Level Project Implementation Unit-Grant Management and Local Infrastructure
(CLPIU-GMaLI) in Kathmandu, headed by a project director to coordinate all project activities.
At the district level, project implementation will be the responsibility of the District Level Project
Implementation Unit-Grant Management and Local Infrastructure (DLPIU-GMaLI) of each
district. CLPIU/DLPIU (GMaLI) will be supported by District Implementation Support
Consultants (DISC) which is headed by District Team Leader, technical and social staff.
Overall back stopping support to the district will be provided by Central Implementation
Support Consultants (CISC).
1The 12 project districts are Kathmandu, Lalitpur, Bhaktapur, Kavrepalanchok, Dolakha, Ramechhap, Okhaldhunga, Solukhumbu, Sindhuli, Gorkha, Lamjung, Chitwan
Environmental Compliance Monitoring Report
January-June, 2019
Earthquake Emergency Assistance Project 6
Source: DRILP-III
Figure 1: Map of Nepal showing District of EEAP
Source: DRILP-III
Figure 2: Map showing Road Sub-projects in Districts of EEAP
PROJECT DISTRICTS IN EEAP
District Road Sub-projects in EEAP
Environmental Compliance Monitoring Report
January-June, 2019
Earthquake Emergency Assistance Project 7
2. Environmental Safeguards in EEAP
EEAP falls in category B project according to ADB Safeguard Policy Statement, 2009. Also,
the road sub-projects of EEAP belong to District Road Core Network (DRCN) according to
Nepal Rural Road Standard (2055) first Revision, September 2012 of the Department of Local
Infrastructure Development and Agricultural Roads (DoLIDAR). Therefore, it is a legal
requirement to carry out Initial Environmental Examination (IEE) according to Working
Procedure relating with Environmental Impact Assessment for Reconstruction of the
Earthquake Affected Structures 2016.
Environmental assessment is essential to integrate environmental considerations into
development project in order to minimize negative environmental impacts. In this context, IEE
reports have been prepared for road sub-projects under EEAP to satisfy legal provision of
GoN and ADB’s environmental procedures.
During the reconstruction and rehabilitation of the road sub-projects, environmental monitoring
is an important tool to ensure the compliance of mitigation measures and implementation of
environmental management plan (EMP). Monthly, Quarterly and Semi-annual Environmental
Safeguard Monitoring Report have been prepared on the basis of report received from DISC
team and environmental field visit made by Environmental Safeguard Unit of CISC, EEAP.
3. Overall Environmental Safeguard Status
IEE reports of all 17 road sub-projects have been approved by GoN and have been duly
endorsed by ADB. 14 IEE reports are approved from NRA and 3 IEE reports Bysai-Jhaukhel-
Changu-Telkot-Bhattedanda-Nagarkot Road, Bhaktapur; Godamchour-Godabari-Badikhel-
Lelebhanjyang Road, Lalitpur and Khopasi-Dhungakharka-Chyamranbesi-Milche-Borang
Road, Kavrepalnchok) are approved by then Ministry of Federal Affairs and Local
Development).
Total 3 IEE reports (Devitar-Phulasipokhari Section of Devitar-Doramba-Paseban-Kolibagar
Road, Ramechhap; Okhaldunga-Rumjatar Road, Okhaldhunga and Pipal Bhanjyang-Haitar-
Netrakali Road, Sindhuli) were updated due to variation in forest area and trees to be removed
from forest area and re-approved from NRA. The tree cutting approval from cabinet has been
obtained for all required sub-projects except Kuntabesi-Nayagaun-Nagarkot Road Sub-
project, Kavre. Simultaneously, implementation of environmental management plan and
monitoring is ongoing. Please refer Annex 1 and Annex 2 for status of environmental
safeguards.
4. Construction Approach
EEAP applies National Competitive Bidding (NCB) approach for construction of road.
Contractors have been using equipment and human resources to execute the contract within
the stipulated deadline. Spoil disposal has been tried to balance with cutting and filling as far
as possible. There will be use of bio-engineering techniques with integrated use of vegetation,
simple civil engineering structures and proper water management systems for slope
Environmental Compliance Monitoring Report
January-June, 2019
Earthquake Emergency Assistance Project 8
protection. Overall, construction activities will follow the environment friendly approach as
much as possible.
5. COMPLIANCE STATUS WITH ENVIRONMENTAL COVENANTS
Environmental safeguard related project activities are in compliance with loan covenants as
regular follow up actions are being taken according to approved IEE report (Please refer
Annex 3 for details).
6. Compliance with Environmental Safeguard Measures
Total 21 NCB contract packages have been awarded in 17 road sub-projects (301.53 km) in
12 different districts. For better environmental safeguard compliance of the project,
implementation of EMP has been ongoing.
6.1. EMP Implementation Budget in Districts
IEE reports suggest that NRs. 31,213,538 (of which NRs. 27,429,538 is for EMP
implementation and NRs. 3,784,000 is for central level and third party monitoring) is required
for 17 road sub-projects; in addition to environmental management cost has been covered
under civil activities. NRA had allocated NRs. 8,680,000 under the heading “Environmental Management and Roadside Plantation in Upgrading and Reconstruction of Road” in current fiscal year (FY).
In addition, there is provisional sum of budget ranging from NRs. 300,000 to NRs. 350,000 in
BoQ for environment mitigation. Please refer Annex 4 for details about budget estimated for
the implementation of environmental management plan for all road sub-projects. Following is
summary of environmental compliances and details are given in Annex 5.
6.2. Orientation Program
a. Environmental Safeguard and Awareness
Environmental safeguard awareness training was conducted in different sub-project as
recommended by IEE report to raise the environmental conservation and awareness amongst
local people as well as to familiarize contractor, field staff and local community about
implementation of environmental management plan and its compliance. The participants were
CFUG members, members of women group, youth club, teacher, contractor and contractor’s staff & workers, field staff and local authorities etc. Till date, 26 events (1,421 participants) has
been conducted in 14 road sub-project of 10 districts, please refer Table 1 for detail. The
estimated budget (IEE) for conducting environment safeguard and awareness orientation is
NRs. 3,085,000.
Environmental Compliance Monitoring Report
January-June, 2019
Earthquake Emergency Assistance Project 9
Table 1: List of Events on Orientation on Environmental Safeguard and Awareness
S.N Name of District Sub-Project Events
(No.)
Participants (No.) Remarks
Male Female Total
1 Kathmandu Sankhu-Palubari-Nagarkot Road
1 48 35 83
2 Bhaktapur Bysai-Jhaukhel-
Changu- Telkot-
Bhattedanda- Nagarkot
Road
- - Not
included
in EMP
3 Lalitpur Thaiba-Godamchaur
Road
- -
Godamchour-Godabari-Badikhel-
Lelebhanjyang Road
1 28 45 73
4 Kavrepalanchok Kuntabesi-Nayagaun-
Nagarkot Road
1 38
Khopasi-
Dhungakharka-
Chyamranbesi-Milche-Borang Road
5 Dolakha Bhirkot-Sahare-Hawa
Section of Bhirkot-
Sahare-Hawa-Jiri Road
3 106 74 180
Sunkhani-Lamidanda-
Kalinchowk section of
Sunkhani Sangwa Road
3 89 91 180
6 Gorkha Ghympesal-Balkot-
Palkhu-Swara-
Saurpani-Barpak Road
1 118
Luitel-Aappipal-
Harmibhanjyang-Thalajung-Bhachek
Road
2 144
7 Lamjung Belghari-Archalbot-
Lamabagar-
Serabazaar-Lituere-
Pachok Road
2 45 34 79
8 Chitwan Khurkhure (Highway)-Samitar-
Thakurivanjyang Road
2 50 43 93
9 Sindhuli Pipal Bhanjyang-Haitar-
Netrakali Road
2 27 95 122
10 Ramechhap Haldebesi-Dhobi-
Dhandebesi Road
3 69 50 119
Environmental Compliance Monitoring Report
January-June, 2019
Earthquake Emergency Assistance Project 10
S.N Name of District Sub-Project Events
(No.)
Participants (No.) Remarks
Male Female Total
Devitar-Phulasipokhari
Section of Devitar-
Doramba-Paseban-
Kolibagar Road
3 50 42 92
11 Okhaldhunga Okhaldunga-Rumjatar
Road
2 47 53 100
12 Solukhumbu Garma-Nele-Bogal Road
- -
Total 26 559 562 1421
b. Waste Management and Awareness
Orientation on waste management and awareness has to be conducted in 5 road sub-projects
(Sankhu-Palubari-Nagarkot Road, Thaiba-Godamchaur Road, Godamchour-Godabari-
Badikhel-Lelebhanjyang Road, Khopasi-Dhungakharka-Chyamranbesi-Milche-Borang Road,
Khurkhure (Highway)-Samitar-Thakurivanjyang Road) as per approved IEE with estimated
budget of NRs. 950,000. Till date, 2 events (101 participants) have been conducted in road
sub-project of Kathmandu and Lalitpur districts; please refer Table 2 for detail. The orientation
had made awareness among the participants to reduce waste at source, segregate the waste,
concept of 3R, making fertilizer from biodegradable waste and responsible waste disposal.
Table 2: List of Events on Orientation on Waste Management
S.N Name of District
Sub-Project Total Participants (No.)
Remarks
1 Kathmandu Sankhu-Palubari-Nagarkot Road
41 2 Day Program with practical
2 Lalitpur Thaiba-Godamchaur Road 60 1 Day Program with practical
Godamchour-Godabari-Badikhel-Lelebhanjyang Road
-
3 Kavrepalanchok Khopasi-Dhungakharka-Chyamranbesi-Milche-Borang Road
-
4 Chitwan Khurkhure (Highway)-Samitar-Thakuri vanjyang Road
-
Total 101
6.3. Forestry Clearance
According to Forest Act, 2049 BS (1993) and Government of Nepal: Working Procedure to
Use National Forest Area for National Priority Projects, 2074 BS (2017), forestry clearance
Environmental Compliance Monitoring Report
January-June, 2019
Earthquake Emergency Assistance Project 11
has to be obtained from the GoN (cabinet) through Ministry of Forest and Environment
(MoFE), if the road sub-projects pass from the forest area.
Approved IEE reports of 17 road sub-projects show that total 15 road sub-projects pass
through 53 Community Forests (CFs), 4 Government Managed Forests (GMFs), 5 Leasehold
Forests (LHFs) and 2 Religious Forests (RFs). However, there is no tree loss from 3 CFs in
Garma-Nele-Bogal Road of Solukhumbu District and 4 LHFs of Pipal Bhanjyang-Haitar-
Netrakali Road of Sindhuli District. Field assessment by personnel of forest office shows that
13 road sub-projects passes through 49 CFs, 5 GMFs, 7 LHFs and 2 RFs with permanent loss
of 30.97 ha of forest area. However, Divisional Forest Office (DFO’s) tree cutting plan report
has sought for 40.38 ha land as forest (consideration of barren land as forest in Sunkhani-
Lamidanda-Kalinchowk section of Sunkhani Sangwa Road, Dolakha and overall agriculture,
barren and build up area also in Khurkhure (Highway)-Samitar-Thakurivanjyang Road of
Chitwan). These road sub-projects need to clear 1,322 trees and poles; 1,664 saplings and
3,279 seedlings. Therefore, tree cutting approval had to be sought for 1,322 trees and poles
only. However, tree cutting approval plan prepared by DFO specified to remove overall 5,960
vegetation (trees, poles, saplings & seedlings) from the forest. There is no tree loss from 2
CFs in Bhirkot-Sahare-Hawa Section of Bhirkot-Sahare-Hawa-Jiri Road of Dolakha District, 5
CFs in Haldebesi-Dhobi-Dhandebesi Road of Ramechhap and 4 LHFs of Pipal Bhanjyang-
Haitar-Netrakali Road of Sindhuli District. More than 80% trees and poles will be lost from CF,
with more than 80% of total affected forest land. Please refer Annex 6 and Figure 3 for
detail.
Tree cutting approval
from cabinet (cabinet
decision dated on 5th
August 2018) has been
obtained for 12 out of
13 required road sub-
projects of 10 districts
(except Kavre-
Kuntabesi-Nayagaun-
Nagarkot Road Sub-
project). On basis of
cabinet decision,
agreement had been
signed by CLPIU and
DoF on dated 4
September, 2018. The
agreement has been
forwarded to concerned
forest offices at district
level. Afterwards, tree
marking with hammer
seal was done before felling trees. Felled trees were sectioned, stacked and transported in
allocated place.
Box 1. Is obtaining Forestry Clearance is enough for tree cutting!!!
Approval of tree cutting plan from cabinet had opened the door for
carrying out reconstruction and rehabilitation activities in forest area.
All sub-projects collected “ban pesi” from DFO and tree cutting activities was initiated. However, field scenario for Shree Hari Siddhi
Religious Forest in Devitar – Phulasi pokhari Section of Devitar –
Doramba – Paseban – Kolibagar Road was different.
The forest was religiously untouched and cutting the tree from the
forest was key concern among local and forest user groups. There was
continuous coordination among forest personnel, project and local on
tree felling from forest. Despite of agreement to remove trees and
organize “Chhyama Pooja”, the process was not gaining momentum as team designated for tree cutting activities used to encounter
accident whenever they were mobilized. This could be totally co-
incidence but this coincidence had definitely caused in expiry of 2 “ban pesi” issued by DFO. Finally, tree feeling activities was successfully carried out by team, with different religious faith” and thus third ban pesi was utilized. However, 31 felled trees are witnessing the story and
nobody dares to collect the timber and firewood of felled trees.
This incidence has marked that religious belief are equally important
as governmental legal requirements
Environmental Compliance Monitoring Report
January-June, 2019
Earthquake Emergency Assistance Project 12
Figure 3: Types of Forest with Number of Vegetation Loss and Area
6.4. Plantation
a. Compensatory Plantation
According to approved IEE, there will be 3,624 tree loss from forest area and 4,039 from
private land. Therefore, compensatory plantation (CP) of 94,639 plants (90,600 in forest area
and 4,039 in private land) has been targeted against the loss of total 7,663 tree at the ratio of
1:25 plants in forest area (CF/GMF/LHF/RF) and 1:1 plants in private land with total estimated
cost of NRs. 16,014,538 in approved IEE (please refer Annex 7 for detail). However, the target
in forest area has been revised as per DFO’s official report in tree cutting approval plan. There is overall 64.46 % increment in compensatory plantation target in forest area; 58,400 plants
more than estimated in approved IEE report, please refer Figure 4 and Table 3 also. Area
wise, approximately 93.12 ha of plantation has to be done in forest area according to the
plantation norms of then Ministry of Forest and Soil Conservation (MoFSC, 2070).
Environmental Compliance Monitoring Report
January-June, 2019
Earthquake Emergency Assistance Project 13
Figure 4: Revised (DFO) and Targeted (IEE) Compensatory Plantation in Sub-projects
Table 3: Estimated, Revised and Carried out Compensatory Plantation Activities
Forest Type (by Management)/ Private Land
Compensatory Plantation
Estimated Target (Approved IEE)
Revised Target
Variation (%)
Carried Out (no.)
Payment Made for Plantation (no.)
Community Forest 59,900 104,875 75.08 2,825 5,485
Government Managed Forest
29,200 22,525 22.86
Leasehold Forest 175 20,475 11,600.00
Religious Forest 1,325 1,125 15.09
Total (Forest) 90,600 149,000 64.46
Private Land 4,039 4,039 N/A 0
Total 94,639 153,039 61.71 8,310
CISC has been providing backstopping support to district teams for carrying out compensatory
plantation works. Revised plantation plan had been sent to all districts. Despite the effort by
DISC team, there is very less achievement in compensatory plantation. Total 8,310 numbers
of plants in forest area, which is 5.57% against targeted plantation in forest area, has been planted so far. Please refer Table 3 and 4 for detail.
Environmental Compliance Monitoring Report
January-June, 2019
Earthquake Emergency Assistance Project 14
Table 4: Status on Revised Target and Achieved Plantation in Different Sub-projects
Districts Sub-project Targeted Achieved Remarks
Kathmandu Sankhu-Palubari-Nagarkot Road 1,800 2000 Planted
through FUG
Bhaktapur Bysai-Jhaukhel-Changu-Telkot-
Bhattedanda-Nagarkot Road
- - N/A
Lalitpur Thaiba-Godamchaur Road - - N/A
Godamchour-Godabari-Badikhel-
Lelebhanjyang Road
5,200 825 Planted
through FUG
Kavre Kuntabesi-Nayagaun-Nagarkot Road 3,800 -
Khopasi-Dhungakharka-
Chyamranbesi-Milche-Borang Road
-
- N/A
Dolakha Bhirkot-Sahare-Hawa Section of
Bhirkot-Sahare-Hawa-Jiri Road
1,650 Coordination
ongoing for plantation
Sunkhani-Lamidanda-Kalinchowk
section of Sunkhani Sangwa Road
3,875
Gorkha Ghympesal-Balkot-Palkhu-Swara-
Saurpani-Barpak Road
9,100 Coordination
ongoing for plantation
Luitel-Aappipal-Harmibhanjyang-
Thalajung-Bhachek Road
34,000
Lamjung Belghari-Archalbot-Lamabagar-
Serabazaar-Lituere-Pachok Road
4,100 4,885 Payment made
to DFO
Chitwan Khurkhure (Highway)-Samitar-
Thakurivanjyang Road
75,500
Sindhuli Pipal Bhanjyang-Haitar-Netrakali
Road
3,225
Ramechhap Haldebesi-Dhobi-Dhandebesi Road Coordination
ongoing for
plantation Devitar-Phulasipokhari Section of
Devitar-Doramba-Paseban-
Kolibagar Road
4,800
Okhaldhunga Okhaldunga-Rumjatar Road 1,950 600
Solukhumbu Garma-Nele-Bogal Road - - N/A
Total 149,000 8,310
Environmental Compliance Monitoring Report
January-June, 2019
Earthquake Emergency Assistance Project 15
b. Roadside Plantation
Roadside plantation has been
planned in approved IEE of every
sub-project, with budget ranging
from NRs. 100,000 to NRs.
300,000. Total estimated budget for
roadside plantation is NRs.
4,150,000. Till date, only 6 road
sub-projects of Kathmandu,
Bhaktapur, Solukhumbu, Lalitpur
(both) and Okhaldhunga has carried
roadside plantation activities. Total
1,459 plants of different species
have been planted along or nearby
road section. The average height of
plants is 5 feet in most of sub-
project and they have been
protected with bamboo/iron guards, please refer Table 5 for detail.
Table 5: Detail on Roadside Plantation
S.N Sub-project Plant
(No.)
Detail Remarks
1 Sankhu-Palubari-Nagarkot Road
195 Kapur, Asoka,
Rudrakchhya, Lapsi,
Dhupi
In collaboration with Madhavnarayan
Mandir/ Swosthanimata Mandir
Bewasthpan Samiti, Salinadi for
plantation and protection
2 Bysai-Jhaukhel-Changu-Telkot-Bhattedanda-Nagarkot Road
205 Kapur, Kaiyo, Lapsi,
Dhupi-, Rudrakchhya,
Kalki Bottle Brush
Plantation by Chamatkar Nirman
Sewa, provision of conservation of
trees for two years through school
management committee
3 Thaiba-Godamchaur Road
55 Kapur, Kaiyo, Dhupi,
Rudrakchhya, Kalki
Bottle Brush
In collaboration with Bisankhunarayan
Ma. Bi, Godamchaur for protection
4 Godamchour-Godabari-Badikhel-Lelebhanjyang Road
22 Kapur, Kaiyo, Dhupi,
Rudrakchhya, Kalki
Bottle Brush
In collaboration with Bistachhap CF
5 Garma-Nele-Bogal Road 775 Salla; Dhoopi, Bais,
Alcha
length man will be looking after plants
6 Okhaldunga - Rumjatar Road
207 Dhupi, Gulmohar In collaboration with Maha
Chandeswori Krishak Samuha for
plantation and protection
Total 1,459
Box 2. Challenge for survival of road side plantation
Survival of roadside plantation is as challenging as planting itself.
All 5 DLPIU has made some collaboration for protecting trees.
Amongst DLPIU carrying roadside plantation, DLPIU-Lalitpur is a
step ahead in demonstrating a good practice for protecting
roadside plants.
DLPIU Lalitpur has planted just 77 trees in 2 road sub-project.
The overall facilitation was done by DISC-Lalitpur. “Continuous coordination and involvement of local stakeholder from seed
collection to plantation and protection through agreement had
internalized roadside plantation among locals”- Suraj Thapa, TL-
DISC. Direct/Indirect involvement of grade 9 and 10 students of
High School from planting to protecting is above the project’s target meeting activities; it has connected youngster to be a part
of nature conservation. Also, involvement of FUGs in roadside
plantation in another road is the hidden root for successful
survival of plants.
Environmental Compliance Monitoring Report
January-June, 2019
Earthquake Emergency Assistance Project 16
c. Plantation against Loss of Forest Area
According to section 10 (2) of Government of Nepal: Working Procedure to Use National
Forest Area for National Priority Projects, 2074 BS (2017), project has to carry out plantation
equivalent to forest area lost at the rate of 1600 plants/ha and protect it for five years.
Therefore, 64,608 plants have to be planted for the loss of 40.38 ha forest area, with additional
cost of NRs. 10,906,527.52, please refer Annex 4 for detail on sub-project wise. However,
there is nil achievement till date.
6.5. Slope Stabilization and Bioengineering Activities
Unstable slopes area has been identified in IEE as well as detail design report and total NRs.
47,800,469 have been estimated for bioengineering activities on actual cost estimate basis.
Total 1,290.00 m3 retaining wall, 2,143.00 m3 gabion breast walls, 2,554.56 m3 gabion/dry toe-
wall 84.16 m3 masonry breast walls has been constructed to control landslide and erosion.
Similarly, 6,617.50 rm brush layer, 15,509.33 m2 grass slips has been planted so far for slope
stabilization.
6.6. Camp Site Management
Drinking water and sanitary facilities (toilets) are provided in the camps by contractor. Few
contractors have rented local house for labours in camps. Workers use kerosene, LPG as well
as firewood for cooking.
6.7. Occupational Health and Safety
Occupational health and safety measures have been partially followed. Workers have been
provided with safety gears like helmet, facemasks, jackets etc. in most of the districts.
However, these items are in limited quantity and not sufficient for all the workers in few
districts. They need to be educated about the importance and use of safety gears. Group
accidental insurance has been done for all the workers in all the project districts. Two injuries
and 1 casualty (non-working hours) have been reported so far. Please refer Annex 5 for detail.
6.8. Signboard Placing
Total 68 signboards at various places along the road with project information and safety has
been erected in 12 sub-projects. Number of signboards ranges from 1 to 8 per sub-project.
NRs. 2,160,000 budget has been allocated for informative, safety and environmental
awareness signboards.
6.9. Spoil Management
Spoil disposal sites have been identified and provision of toe walls are given in the detail
project design report. Spoils are being managed in specified disposal sites as far as possible.
Nearly, 1,482,537.66 m3 of spoil has been reported to be managed safely. So far, toe walls
with volume of 2,620.21 m3 have been constructed to manage spoil. Template of spoil
management plan has been prepared and circulated to all districts, please refer Annex 8.
Environmental Compliance Monitoring Report
January-June, 2019
Earthquake Emergency Assistance Project 17
6.10. Grievances Received and Addressed
GRM mechanism has been established in all sub-projects. So far, 1,540 grievances have been
reported, 1,369 solved and 171 are under process. Most of the grievances are related to
missing plots, mismatch in name, area etc.
6.11. EMP Implementation, Monitoring, Reporting and Field Visit
Environmental monitoring format has been sent to districts as given in Annex 9.
Environmental monitoring is also done by the CISC team during field visits. A sum of NRs.
3,784,000 budget has been allocated for monitoring activities. Following Table 6 gives the list
of sub-projects visited by CISC environmental team on chronological order.
Table 6: Date and Name of Districts Visited by CISC Environmental Team
S.N District Road
1 Lalitpur Tahiba- GodamcahurRoad
2 Lalitpur Godamchaur-Godawari-Badikhel-Lelebhanjayang Road
3 Kathmandu Sankhu-Palubari road Kathmandu Road
4 Bhaktapur Bysai –Jhaukhel –Changu –Telkot-Bhattedanda -Nagarkot Road
7. ISSUES AND WAY FORWARD
Major issues and way forward for the effective implementation of environmental safeguard
measures are discussed below in Table 7.
Table 7: Issues and Way Forward
S.N Issues Way forward
1 Late hour coordination with DFO (for
paying out for plantation activities) has
raised the chances of failure in payment
to DFO for plantation activities, where coordination is ongoing
Timely release of budget by NRA and
meaningful consultation and coordination
by DLPIU for payment to DFO
2 Initiating Third party monitoring Coordination with concerned stakeholders
for carrying out third party monitoring or direct procurement by CLPIU/DLPIU for
third party monitoring
3 Timely Plantation under bio-
engineering for survival
Immediate interference by DLPIU for sub-
project that has been planning for plantation under bio-engineering
Environmental Compliance Monitoring Report
January-June, 2019
Earthquake Emergency Assistance Project 18
8. ACHIEVEMENT ON MAJOR ITEMS OF FOCUS ON PREVIOUS
REPORT
Items focused for this semi-annual period have been achieved partially. Detail on status and
suggested corrective actions are presented in Table 8 below.
Table 8: Status on Items of Focus of Previous Report
S.N Item of Focus Status Description Corrective action
plan, if any
1 Budget to carry
augmentation,
mitigation and
compensation
activities
(remaining
activities)
Partially
achieved,
ongoing
Coordination for
carrying out
bioengineering and
payment to DFO for
carrying out
compensatory
plantation and
plantation against loss
of forest land is
ongoing in few sub-
project
Timely implementation
of bio-engineering
activities during this
monsoon, early
coordination with DFO
for payment to carry
proposed activities of
IEE / tree cutting
approval plan
2 Environmental
compliance
monitoring and
supervision
Not
achieved
No initiation has been
done yet
Consideration for third
party monitoring by
DLPIU/CLPIU as
mentioned in EMP is
also required for
overall environmental
monitoring
9. MAJOR ITEMS OF FOCUS FOR NEXT REPORT
The major items of focus for July-December of 2019 are listed below in Table 9.
Table 9: Item of Focus for Next Report
SN Item of Focus Remarks
1 Timely coordination and payment to DFO for carrying out compensatory
plantation and plantation against loss of forest land
2 Initiating Third party monitoring
3 Immediate interference of DLPIU for carrying out plantation activities
under bio-engineering
4 Carrying out roadside plantation in remaining sub-project by DLPIU
Environmental Compliance Monitoring Report
January-June, 2019
Earthquake Emergency Assistance Project 19
Annexes
Environmental Compliance Monitoring Report
January-June, 2019
Earthquake Emergency Assistance Project 20
Annex 1: Environmental Safeguard Planning Status
Note: EIA-Environmental Impact Assessment; IEE-Initial Environmental Examination; DDR-Due Diligence Report; EMP-Environmental Management Plan, GRC-Grievance Redress Committee; BOQ-
Bill of Quantity
SN District Name of Subproject Environm
ental
screening
is
carried
out? (Yes
or No)
Environmen
t category
of the
project /
subproject
(A/B/C/FI)
EARF is
prepared
(if
applicable)
(Yes/No)
EIA/IEE/DDR
with EMP is
prepared
(Yes/No)
ADB
approved
EIA/IEE with
EMP
(Yes / Under
Review / Not
Yet
Due/Over
Government
approved
EIA/IEE with
EMP
(Yes / Under
Review / Not
Yet
Submitted)
Safeguard
monitoring
and
coordination
mechanism
established
(Yes/No)
GRC is
establishe
d
(Yes/No)
Automated
safeguard
monitoring
system
customized
(Yes/No)
EMP cost in
approved
document is
included in
BOQ as an
individual item
(Yes/No)
Remarks
1 Kathmandu Sankhu -Palubari -Nagarkot Road Yes B Yes Yes Yes Approved N/A Yes No Yes (PS) Approved
2 Bhaktapur
Bysai –Jhaukhel –Changu –Telkot-Bhattedanda -Nagarkot Road
Yes B Yes Yes Yes Approved N/A Yes No Yes (PS) Approved
Thaiba - Godamchaur Road Yes B Yes Yes Yes * Approved Yes No yes (PS) Approved
Godamchour- Godabari-
Badikhel- Lelebhanjyang RoadYes B Yes Yes Yes Approved Yes No Yes (PS) Approved
Kuntabesi-Nayagaun - Nagarkot
RoadYes B Yes Yes Yes Approved N/A Yes No Yes (PS) Approved
Khopasi-Dhungakharka -
Chyamranbesi-Milche-Borang
Road
Yes B Yes Yes Yes Approved N/A Yes No Yes (PS) Approved
Bhirkot - Sahare- Hawa Section
of Bhirkot - Sahare- Hawa -Jiri
Road
Yes B Yes Yes Yes Approved N/A Yes No Yes (PS) Approved
Sunkhani-Lamidanda -
Kalinchowk section of Sunkhani
Sangwa Road
Yes B Yes Yes Yes Approved N/A Yes No Yes (PS) Approved
Ghympesal - Balkot- Palkhu-
Swara-Saurpani- Barpak RoadYes B Yes Yes Yes Approved N/A Yes No Yes (PS) Approved
Luitel - Aappipal -
Harmibhanjyang - Thalajung – Bhachek Road
Yes B Yes Yes Yes Approved N/A Yes No Yes (PS) Approved
7 Lamjung
Belghari – Archalbot - Lamabagar- Serabazaar -
Lituere - Pachok Road
Yes B Yes Yes Yes Approved N/A Yes No Yes (PS) Approval
8 ChitwanKhurkhure (Highway) - Samitar -
Thakurivanjyang RoadYes B Yes Yes Yes Approved N/A Yes No Yes (PS) Approved
9 Sindhuli Pipal Bhanjyang - Haitar -
Netrakali Road Yes B Yes Yes Yes Approved N/A Yes No Yes (PS)
Approved (Updated IEE
approved)Haldebesi -Dhobi- Dhandebesi
RoadYes B Yes Yes Yes Approved N/A Yes No Yes (PS) Approved
Devitar – Phulasipokhari Section of Devitar – Doramba – Paseban – Kolibagar Road
Yes B Yes Yes Yes Approved N/A Yes No Yes (PS)Approved (Updated IEE
approved)
11 OkhaldhungaOkhaldunga - Rumjatar Road Yes B Yes Yes Yes Approved N/A Yes No Yes (PS)Approved (Updated IEE
approved)
12 Solukhumbu Garma - Nele -Bogal Road Yes B Yes Yes Yes Approved N/A Yes No Yes (PS) Approved
3 Lalitpur
4 Kavre
5 Dolkha
6 Gorkha
10 Ramechhap
Environmental Compliance Monitoring Report
January-June, 2019
Earthquake Emergency Assistance Project 21
Annex 2: Environmental Safeguard Implementation Status
Note: * Added field as guided by EMP in IEE/DDR, ** Written in percentage of compliance in a scale of 100%, *** type of community structures mentioned
Other as
per EMP
(specify)*
Initial
Total
Target (
IEE-
Private +
Forest)
(Nos.)
Actual
Target
(Pole and
Tree loss
at Forest);
(Nos.)
Target
(Private
Land);
(Nos.)
Target
(Forest-
DFO
Tippani);
(Nos.)
Revised
Total
Target ;
(Nos.)
Planted
(Nos.)
Roadside
Plantation
Safety
Gears are
sufficient
and used
(Y/N)
Labors
are
insured
(Y/N)
Labor and work
camps are
healthy and
have sanitary
facilities (Y/N)
Community
structure 1
Community
structure 2
1 Kathmandu Sankhu -Palubari -
Nagarkot Road90 90 1,922 1,800 122 1,800 1,922 2000 N 195 N Y Y
Public Tap at
7+200N/A 118 118 - N Y
2 Bhaktapur
Bysai –Jhaukhel –Changu –Telkot-Bhattedanda -Nagarkot Road
50 10 115 - 115 - 115 0 N 205 Y Y Y N/A N/A 24 24 - N Y
Thaiba - Godamchaur
Road90 90 - - - - 0 N 55 Y Y Y
Railing at Ch
0+950N/A 55 55 - N Y
Godamchour- Godabari-
Badikhel- Lelebhanjyang
Road
90 90 5,501 5,200 76 5,200 5,276 825 N 22 Y Y Y N/A N/A 56 55 1 N Y
Kuntabesi-Nayagaun -
Nagarkot Road80 90 7,687 3,800 1,187 3,800 4,987 0 N 0 Y Y Y N/A N/A 123 123 - N Y
Khopasi-Dhungakharka -
Chyamranbesi-Milche-
Borang Road
50 80 600 - - - 0 N 0 Y Y Y N/A N/A 23 23 - N Y
Bhirkot - Sahare- Hawa
Section of Bhirkot - Sahare-
Hawa -Jiri Road
90 70 2,544 1,650 69 1,650 1,719 0 N 0 Y Y Y N/A N/A 22 22 - N Y
Sunkhani-Lamidanda -
Kalinchowk section of
Sunkhani Sangwa Road
90 90 2,375 625 3,875 3,875 0 N 0 Y Y Y N/A N/A 3 3 - N Y
Ghympesal - Balkot-
Palkhu- Swara-Saurpani-
Barpak Road
40 20 5,563 475 188 9,100 9,288 0 Y 0 N Y Y N/A N/A 23 23 - N
Luitel - Aappipal -
Harmibhanjyang -
Thalajung – Bhachek Road
60 20 18,644 1,500 519 34,000 34,519 0 Y 0 N Y Y N/A N/A 159 159 - N Y
7 Lamjung
Belghari – Archalbot - Lamabagar- Serabazaar -
Lituere - Pachok Road
70 20 7,344 4,100 519 4,100 4,619 0 N 0 Y Y Y N/A N/A 110 110 - N Y
8 Chitwan
Khurkhure (Highway) -
Samitar - Thakurivanjyang
Road
90 40 11,756 3,925 106 75,500 75,606 N 0 Y Y N/A N/A N/A 33 33 - N Y
9 Sindhuli Pipal Bhanjyang - Haitar -
Netrakali Road 30 80 22,523 3,225 373 3,225 3,598 0 Y 0 N Y Y
Irrigation Canal
at Ch 5+060N/A 147 147 - N Y
Haldebesi -Dhobi-
Dhandebesi Road80 10 2,625 - - - 0 Y 0 N Y Y N/A N/A 220 50 170 N Y
Devitar – Phulasipokhari Section of Devitar – Doramba – Paseban – Kolibagar Road
80 50 3,142 4,800 417 4,800 5,217 Y 0 N Y Y N/A N/A 76 76 - Y Y
11 Okhaldhunga Okhaldunga - Rumjatar
Road90 70 2,298 1,950 348 1,950 2,298 0 N 207 Y Y Y
Community Tap
ch 8+600
Chautara at ch
9+980226 226 - N Y
12 Solukhumbu Garma - Nele -Bogal Road 80 80 - - - - 0 N 775 Y Y YTosing, ch
4+200
Tosing, ch
4+300122 122 - N Y
94,639 33,050 4,039 149,000 153,039 2,825 1,459 1,540 1,369 171
Nos of
grievances
documented
No of
grievances
resolved
No of
grievances
under
processing
Env
compliance
reporting is
maintained
(Y/N)
Corrective
Action Plans
are prepared
and
implemented
(Y/N)
Firewood
is used for
cooking
and
heating
(Y/N)
Occupational Health and Safety Community structures are
compensated/reconstructed
(Progress in % of tota
estimated work )***
Other as
per EMP
(specify)*
Socio-economic
Grievances
Total
SN
6
4
5
10 Ramechhap
3
Gorkha
Lalitpur
Kavre
Dolkha
Physical
Spoil
Management
(compliance in
%)**
Districts Name of Subproject Compliance to Environmental Management Plan*
Biological
Compensatory Plantation Landslide
protection
with Bio-
eng
(compliance in
%)**
Environmental Compliance Monitoring Report
January-June, 2019
Earthquake Emergency Assistance Project 22
Annex 3: Status of Compliance with Relevant Covenants
Schedule Covenants Type Complied (Yes or Not
Yet Due or On-going
or Partially Complied
or Not Applicable)
Progress Status/Remarks
Schedule
4-7
Conditions for Award of Contracts
The Borrower shall not award any Works
contract for a Subproject which involves
environmental impacts until the EA or the
IAs has:
(a) Obtained the final approval of the
EIA/IEE from the Ministry of Science,
Technology and Environment (for
EIAs)/concerned sector agency (for
IEEs)
(b) Incorporated the relevant provisions
from the EMP into the Works
contract.
Environmental
Safeguard
Yes
IEE reports are prepared and
approved by concerned agencies
(NRA/MoFALD).
Provisional sum of money for
EMP is allocated in work contracts/
GoN has allocated budget.
Schedule
5-1
Project is implemented in accordance with
PAM.
Administrative Yes Noted and considered.
Schedule
5-4
Preparation, design, implementation, and
operation of each sub-project comply with
applicable laws; the Environmental
Safeguards; the EARF; and IEE and EMP.
Environmental
Safeguard
Ongoing
IEE prepared as per applicable law
and EARF. EMP of approved IEE
are under implementation.
Schedule
5-7
Necessary budgetary and human resources
made available to fully implement the EMPs,
and the RPs.
Safeguard Ongoing NRA has allocated NRs.
8,680,000 for EMP implementation
in current FY. In addition, there is
provisional sum of 300,000.00 to
Environmental Compliance Monitoring Report
January-June, 2019
Earthquake Emergency Assistance Project 23
Schedule Covenants Type Complied (Yes or Not
Yet Due or On-going
or Partially Complied
or Not Applicable)
Progress Status/Remarks
350,000.00 for EMP
implementation in BoQ per
subproject.
Focal persons for IEE and
RP in CLPIU/DLPIUs have been
assigned
Schedule
5-8
All bidding documents comply with IEE,
EMP, and RP; budget is made available for
environmental and social measures; any
unanticipated environmental, resettlement
or indigenous peoples risks notified by a
written notice; and condition of roads,
agricultural land and other infrastructure
recorded prior to construction.
Safeguard Ongoing Noted and considered.
Schedule
5-9
(a) A semi-annual Safeguards Monitoring
Reports submitted to ADB and disclose
relevant information; (b) any unanticipated
environmental and/or social risks and
impacts reported promptly to ADB; and (c)
any actual or potential breach of compliance
reported.
Yes Noted and being followed. Semi-
annual environmental safeguard
monitoring report prepared and
submitted along with quarterly
report
Schedule
5-10
No proceeds of the Loan are used to finance
any activity included in the list of prohibited
investment activities provided in Annex 5 of
the SPS.
Safeguard Yes No activities listed in Annex 5 of
SPS are carried under EEAP.
Environmental Compliance Monitoring Report
January-June, 2019
Earthquake Emergency Assistance Project 24
Schedule Covenants Type Complied (Yes or Not
Yet Due or On-going
or Partially Complied
or Not Applicable)
Progress Status/Remarks
Schedule
5-11
The core labor standards and applicable
laws are complied. Bidding documents and
contracts require that the contractors (a)
comply with applicable labor law and
incorporate workplace occupational safety
norms; (b) do not use child labor; (c) do not
discriminate workers; (d) do not use forced
labor; (e) allow freedom of association.
Safeguard Yes Noted and considered.
Schedule
5-15
Within 6 months after the Effective Date, the
Borrower shall prepare a Grievance
Redress Mechanism, acceptable to ADB,
and establish a special committee to receive
and resolve complaints/grievances or act
upon reports from stakeholders on misuse of
funds and other irregularities, including
grievances due to resettlement. The special
committee will (a) make public of the
existence of this Grievance Redress
Mechanism, (b) review and address
grievances of stakeholders of the Project, in
relation to either the Project, any of the
service providers, or any person responsible
for carrying out any aspect of the Project;
and (c) proactively and constructively
responding to them.
Safeguard Ongoing First level of GRM is active at field.
Environmental Compliance Monitoring Report
January-June, 2019
Earthquake Emergency Assistance Project 25
Annex 4: Environmental Management Cost (NRs)
d. Estimated Budget in Approved IEE
S.NName of
DistrictSub-Project
Compensatory
Plantation
Cost (A)
Road-side
Plantation
Cost (B)
Awareness
Raising
Training
Cost (C)
Signboards
Cost (D)
Solid Waste
Management
Cost (E)
Tourism
Development
/ Homestay
Cost (F)
Skill
Enhancem
ent (H)
Total
Mitigation Cost
(1= A +B+ C+
D+ E+ F+ G +
H)
Env.
Monitoring
Cost (2)
Total EMP
Cost (1+2)
Bio-
engineering
Cost
EMP with Bio-
engineering
Cost
1 Kathmandu Sankhu -Palubari -
Nagarkot Road 322,668 350,000 100,000 100,000 150,000 150,000 1,172,668 323,000 1,495,668 4,776,116 6,271,783.31
2 Bhaktapur
Bysai –Jhaukhel –Changu –Telkot-Bhattedanda -
Nagarkot Road
775,000 50,000 825,000 323,000 1,148,000 1,148,000.00
Thaiba - Godamchaur
Road - 250,000 150,000 100,000 150,000 650,000 100,000 750,000 565,445 1,315,444.88
Godamchour-
Godabari- Badikhel-
Lelebhanjyang Road
895,132 100,000 100,000 50,000 250,000 100,000 1,495,132 240,000 1,735,132 1,471,313 3,206,444.62
Kuntabesi-Nayagaun -
Nagarkot Road 1,057,002 250,000 150,000 100,000 1,557,002 150,000 1,707,002 2,576,114 4,283,115.91
Khopasi-
Dhungakharka -
Chyamranbesi-Milche-
Borang Road
300,000 250,000 100,000 100,000 200,000 950,000 323,000 1,273,000 1,273,000.00
Bhirkot - Sahare-
Hawa Section of
Bhirkot - Sahare-
Hawa -Jiri Road
358,955 350,000 250,000 360,000 60,000 150,000 1,528,955 200,000 1,728,955 8,381,976 10,110,931.09
Sunkhani-Lamidanda -
Kalinchowk section of
Sunkhani Sangwa
Road
340,480 350,000 250,000 190,000 60,000 150,000 1,340,480 200,000 1,540,480 4,186,148 5,726,628.48
Ghympesal - Balkot-
Palkhu- Swara-
Saurpani- Barpak
Road
871,058 250,000 150,000 100,000 - - 1,371,058 150,000 1,521,058 863,911 2,384,968.11
Luitel - Aappipal -
Harmibhanjyang -
Thalajung – Bhachek Road
2,929,671 200,000 150,000 100,000 3,379,671 200,000 3,579,671 1,336,644 4,916,315.20
7 Lamjung
Belghari – Archalbot - Lamabagar-
Serabazaar - Lituere -
Pachok Road
1,124,609 250,000 250,000 150,000 1,774,609 250,000 2,024,609 1,214,627 3,239,236.36
8 Chitwan
Khurkhure (Highway) -
Samitar -
Thakurivanjyang Road
2,479,243 200,000 100,000 150,000 200,000 3,129,243 200,000 3,329,243 716,308 4,045,551.17
9 Sindhuli Pipal Bhanjyang -
Haitar - Netrakali Road 3,370,788 450,000 350,000 100,000 4,270,788 325,000 4,595,788 5,827,260 10,423,048
Haldebesi -Dhobi-
Dhandebesi Road 412,519 200,000 250,000 200,000 50,000 150,000 1,262,519 200,000 1,462,519 5,188,739 6,651,257.37
Devitar – Phulasipokhari
Section of Devitar – Doramba – Paseban – Kolibagar Road
455,448 200,000 250,000 160,000 150,000 1,215,448 200,000 1,415,448 3,583,155 4,998,602.80
11 Okhaldhunga Okhaldunga -
Rumjatar Road 321,966 150,000 235,000 100,000 806,966 150,000 956,966 908,404 1,865,369.75
12 Solukhumbu Garma - Nele -Bogal
Road 350,000 250,000 100,000 700,000 250,000 950,000 6,204,310 7,154,309.55
16,014,538 4,150,000 3,085,000 2,160,000 1,120,000 750,000 150,000 27,429,538 3,784,000 31,213,538 47,800,469 79,014,006.81 Total
Lalitpur3
Kavrepalanchok4
Gorkha 6
Ramechhap 10
Dolkha5
Environmental Compliance Monitoring Report
January-June, 2019
Earthquake Emergency Assistance Project 26
e. Revised Budget Sheet
S.N Name of
District
Sub-Project Compensatory
Plantation Cost
(IEE); Private
+Forest
Compensatory
Plantation
Cost
(IEE);Forest
Tree
Loss
No.
(Forest)
Revised
Plantation
No.
Revised Cost
(Forest)
Tree
Loss
(IEE);
Private
Compensatory
Plantation
Cost
(IEE);Private
District
Rate
Area
(Ha)
Additional
Plantation
(No.)
Additional
Cost
Road-side
Plantation
Cost (B)
Awareness
Raising
Training
Cost (C)
Signboards
Cost (D)
Solid Waste
Management
Cost (E)
Tourism
Development
/ Homestay
Cost (F)
Skill
Enhancem
ent (H)
Total
Mitigation Cost
(1= A +B+ C+
D+ E+ F+ G + H)
Env.
Monitoring
Cost (2)
Total EMP
Cost (1+2)
Revised Cost
1 Kathmandu Sankhu -Palubari -
Nagarkot Road 322,668 313,902.00 72 1,800 313,902.00 122 8,765.70 174.39 1.81 2,896 505,033.44 350,000 100,000 100,000 150,000 150,000 1,172,668 323,000 1,495,668 2,000,701
2 Bhaktapur
Bysai –Jhaukhel –Changu –Telkot-Bhattedanda -
Nagarkot Road
775,000 115 775,000.00 50,000 825,000 323,000 1,148,000 1,148,000
Thaiba - Godamchaur
Road - 250,000 150,000 100,000 150,000 650,000 100,000 750,000 750,000
Godamchour-
Godabari- Badikhel-
Lelebhanjyang Road
895,132 889,971.25 208 5,200 853,060.00 76 5,160.40 164.05 2.18 3,488 572,206.40 100,000 100,000 50,000 250,000 100,000 1,495,132 240,000 1,735,132 2,270,427
Kuntabesi-Nayagaun -
Nagarkot Road 1,057,002 982,280.00 152 3,800 574,256.00 1,187 74,721.65 151.12 0.52 832 125,731.84 250,000 150,000 100,000 1,557,002 150,000 1,707,002 1,424,709
Khopasi-
Dhungakharka -
Chyamranbesi-Milche-
Borang Road
300,000 300,000.00 - 250,000 100,000 100,000 200,000 950,000 323,000 1,273,000 973,000
Bhirkot - Sahare-
Hawa Section of
Bhirkot - Sahare-
Hawa -Jiri Road
358,955 354,816.00 66 1,650 236,544.00 69 4,139.31 143.36 4.40 7,040 1,009,254.40 350,000 250,000 360,000 60,000 150,000 1,528,955 200,000 1,728,955 2,619,938
Sunkhani-Lamidanda -
Kalinchowk section of
Sunkhani Sangwa
Road
340,480 340,480.00 155 3,875 555,520.00 143.36 5.20 8,320 1,192,755.20 350,000 250,000 190,000 60,000 150,000 1,340,480 200,000 1,540,480 2,948,275
Ghympesal - Balkot-
Palkhu- Swara-
Saurpani- Barpak
Road
871,058 858,602.50 364 9,100 1,453,634.00 188 12,455.00 159.74 2.47 3,952 631,292.48 250,000 150,000 100,000 - - 1,371,058 150,000 1,521,058 2,747,381
Luitel - Aappipal -
Harmibhanjyang -
Thalajung – Bhachek Road
2,929,671 2,895,287.50 1,360 34,000 5,431,160.00 519 34,383.75 159.74 3.32 5,312 848,538.88 200,000 150,000 100,000 3,379,671 200,000 3,579,671 6,964,083
7 Lamjung
Belghari – Archalbot - Lamabagar-
Serabazaar - Lituere -
Pachok Road
1,124,609 1,090,225.50 164 4,100 654,934.00 519 34,383.75 159.74 0.91 1,456 232,581.44 250,000 250,000 150,000 1,774,609 250,000 2,024,609 1,821,899
8 Chitwan
Khurkhure (Highway) -
Samitar -
Thakurivanjyang Road
2,479,243 2,473,062.00 3,020 75,500 16,027,140.00 106 6,180.86 212.28 9.20 14,720 3,124,761.60 200,000 100,000 150,000 200,000 3,129,243 200,000 3,329,243 20,008,082
9 Sindhuli Pipal Bhanjyang -
Haitar - Netrakali Road 3,370,788 3,347,308.00 129 3,225 487,362.00 373 23,480.35 151.12 4.50 7,192 1,086,855.04 450,000 350,000 100,000 4,270,788 325,000 4,595,788 2,822,697
Haldebesi -Dhobi-
Dhandebesi Road 412,519 412,518.75 157.15 1.63 2,608 409,847.20 200,000 250,000 200,000 50,000 150,000 1,262,519 200,000 1,462,519 1,459,847
Devitar – Phulasipokhari
Section of Devitar – Doramba – Paseban – Kolibagar Road
455,448 428,233.75 192 4,800 832,944.00 417 27,213.42 173.53 3.90 6,240 1,082,827.20 200,000 250,000 160,000 150,000 1,215,448 200,000 1,415,448 2,902,985
11 Okhaldhunga Okhaldunga -
Rumjatar Road 321,966 299,715.00 78 1,950 299,715.00 348 22,251.12 153.70 0.345 552 84,842.40 150,000 235,000 100,000 806,966 150,000 956,966 1,041,809
12 Solukhumbu Garma - Nele -Bogal
Road - 350,000 250,000 100,000 700,000 250,000 950,000 950,000
16,014,538 14,986,402.25 5,960 149,000 27,720,171.00 4,039 1,028,135.31 40.38 64,608 10,906,527.52 4,150,000 3,085,000 2,160,000 1,120,000 750,000 150,000 27,429,538 3,784,000 31,213,538 54,853,834
6 Gorkha
10 Ramechhap
Total
5 Dolkha
3 Lalitpur
4 Kavrepalanchok
Environmental Compliance Monitoring Report
January-June, 2019
Earthquake Emergency Assistance Project 27
Annex 5: Status of Environmental Safeguard Compliances
SN District Road Sub-
project
IEE
Approval
Status
Environmental Compliances
1 Kathmandu Sankhu-
Palubari-
Nagarkot Road
Approved GRM established
12 sign board erected (environmental awareness, and informative)
15,954.22 m3 spoil disposed safely at Ch 3+ 250 to 3+300 Right Side, 3+800 along
right side, 4+280 Right Side, 7+300 along left side, 7+600 along left side and 8+100
along left side
Quarry of 9405 m3 of stone bought from Roshi khola
Campsite established at Ch 5+500, Ch 6+800 and at rented house ( Ch 5+000)
Firewood is used for cooking at campsite
Safety gears are partially used (20 helmets, 20 masks and 20 boots distributed to 80
labours)
GPA insurance for 30 labours.
NRs. 60,000 compensated for affected tap along the road
Roadside plantation carried out (195 plants)
Compensatory plantation carried by both CF (2000 trees + 1000 amriso)
2 days waste management training for 41 participants conducted
Awareness training for 83 participants conducted
3384.50 rm brush layering to stabilize slope from Ch 0+450 to Ch 8+500
2 Bhaktapur Bysai-Jhaukhel-
Changu-Telkot-
Bhattedanda-
Nagarkot Road
Approved GRM established
6000 m3 spoil disposed safely at Ch 1+400, Ch 1+900, Ch 2+650 and Ch 3+000
Roadside plantation carried out (205 plants)
3178.3 m3 of stone bought by contractor from quarry site
Local house rented for labours at Ch 2+700 and 6+700
Sanitation at labour camp is maintained, LPG is used for cooking at campsite
Environmental Compliance Monitoring Report
January-June, 2019
Earthquake Emergency Assistance Project 28
SN District Road Sub-
project
IEE
Approval
Status
Environmental Compliances
100 helmets, 100 masks provided to workers and GPA insurance of labour done
3 Lalitpur Thaiba-
Godamchaur
Road
Approved GRM established
6,018.44 m3 spoil disposed safely at Ch 0+950, Ch 0+120 and Ch 0+600
95 m3 of gabion toe wall constructed for spoil management
Local house rented for labours at Ch 1+750
LPG is used for cooking at campsite
Total 15 helmets and 15 jackets distributed to 15 labours
GPA insurance for 10 labours
Roadside plantation done (55 plants) carried out
Waste management training for 60 participants conducted
200 rm brush layering and 300 m2 grass slips planted to stabilize slope at Ch 0+950
Godamchour-
Godabari-
Badikhel-
Lelebhanjyang
Road
Approved GRM established
40,206.1 m3 spoil disposed safely at Ch 0+810, 4+000, 0+760 & 7+000
154 m3 of toe wall constructed for spoil management
Local house rented for labours at Ch 4+100 and temporary campsite established in
Ch 0+250
Total 2 temporary toilet constructed
LPG is used for cooking at campsite
Total 70 helmets and 70 jackets distributed to 70 labours
GPA insurance for 15 labours
Roadside plantation done (22 plants) carried out
825 sapling planted as compensatory plantation
429 m2 grass slips planted to stabilize slope at Ch 2+800
Environmental Compliance Monitoring Report
January-June, 2019
Earthquake Emergency Assistance Project 29
SN District Road Sub-
project
IEE
Approval
Status
Environmental Compliances
4 Kavrepalanchok Kuntabesi-
Nayagaun-
Nagarkot Road
Approved GRM established
300,000 m3 spoil disposed safely at Ch 15+400-15+550, Ch 15+650-15+800
Local house rented for labours at Ch 1 4+330
Total 2 temporary toilet constructed
Firewood, kerosene, LPG is used for cooking at campsite
Total 50 helmets, 50 masks, 50 boots and 6 jackets distributed to labours
GPA insurance for labours
Environmental Awareness Training conducted
400 rm brush layering and 4000 m2 grass slips planted to stabilize slope at Ch
15+770 (R)15+680 (R)15+689 (R)15+440 (R)15+100 (R)14+800 (R)14+810
(R)15+360 (L),15+382 (L),15+760 (R)16+500 (L),15+760 (R)15+900 (L),16+380
(L),15+600 (R)15+640 (R)15+650 (R)15+660( R)
Khopasi-
Dhungakharka-
Chyamranbesi-
Milche-Borang
Road
Approved GRM established
51,700 m3 spoil disposed safely at Ch 2+095, Ch 2+350
16.5 m3 of toe wall constructed for spoil management
Contractor bought the material from private quarry for near to Ch 3+000
Temporary campsite established in Ch 1+600, Ch 3+800, Ch 6+000 and Ch 9+000
Several landslides along the road, controlled at Ch 4+600 with gabion retaining wall
3 First aid kit provided to labour
Total 3 temporary toilet constructed
LPG is used for cooking at campsite
Total 300 helmets, 300 masks, 300 boots and 10 jackets distributed to labours
1 accident occurred
GPA insurance for labours
Environmental Compliance Monitoring Report
January-June, 2019
Earthquake Emergency Assistance Project 30
SN District Road Sub-
project
IEE
Approval
Status
Environmental Compliances
1897 rm brush layering and 2061.83 m2 grass slips planted to stabilize slope from Ch
4+300-6+774
5 Dolakha Bhirkot-Sahare-
Hawa Section of
Bhirkot-Sahare-
Hawa-Jiri Road
Approved GRM established
226,661.97m3 spoil disposed safely
3 sign board erected at Ch 0+000 and different working sites
672.86 m3 of toe wall constructed for spoil management
LPG, Wood, Electricity is used for cooking at campsite
2 temporary toilets constructed
50 personal protective equipment (helmet, mask) provided to workers
Total 2 first aid kit given to labours
GPA insurance for 45 labours
3 Events of awareness training conducted for 180 participants
Bio-engineering activities has been planned
Sunkhani-
Lamidanda-
Kalinchowk
section of
Sunkhani
Sangwa Road
Approved GRM established
93613.44 m3 spoil disposed safely
8 sign board erected at Ch 0+000, Ch 8+200 (Lapilang), Ch 16+000 (Lamidanda), Ch
27+000 (Kalinchowk)
Protection of huge landslide at Ch 4+660-4+810 with 2 retaining wall of length 70 m
and volume 800 m3, 2 check wall of length 70 m and volume 265 m3 and 2 breast wall
of length 20 m and volume 140 m3
Similarly, there is protection of landslide at Ch 2+630-2+730 with 2 retaining wall of
Length 100m and volume 490 m3
LPG, Wood, Electricity is used for cooking at campsite
5 temporary toilets constructed
Environmental Compliance Monitoring Report
January-June, 2019
Earthquake Emergency Assistance Project 31
SN District Road Sub-
project
IEE
Approval
Status
Environmental Compliances
400 personal protective equipment (helmet, mask) provided to workers
GPA insurance for 20 labours
Total 4 first aid kit given to labours
3 Events of awareness training conducted for 180 participants
736 rm brush layering and 840 m2 grass slips planted to stabilize slope
6 Gorkha Ghympesal-
Bakot-Palkhu-
Swara-Saurpani-
Barpak Road
Approved GRM established
Local house rented for campsite
Firewood (collected from CF) for cooking at campsite
Awareness training for 118 participants
Bioengineering has been planned
Luitel-Aappipal-
Harmibhanjyang
-Thalajung-
Bhachek Road
Approved GRM established
143000 m3 of spoil disposed safely different chainage (5+450, 7+500, 9+350,12+300,
19+740,19+900, 17+920, 18+100 to 18+140, 18+770 to 18+820, 18+980 to 19+020,
19+180 to 19+220, 19+720 to 19+760, 19+830 to 19+970, 20+680 to 20+740, 22+490
to 22+550, 24+080 to 24+140, 25+280 to 25+320, 27+780 to 27+820, 28+680 to
28+720, 30+430 to 30+480)
Quarry of 6,500 m3 of stone from Ch 5+690-5+730, Ch 20+900, Ch 25+500 and Ch
34+000
6 camps established (3 rented house and 3 temporary) with toilet facility
1 injury (finger) recorded
Firewood (collected from CF) for cooking at campsite
Awareness training for 144 participants
Bio-engineering has been planned
Environmental Compliance Monitoring Report
January-June, 2019
Earthquake Emergency Assistance Project 32
SN District Road Sub-
project
IEE
Approval
Status
Environmental Compliances
7 Lamjung Belghari-
Archalbot-
Lamabagar-
Serabazaar-
Lituere-Pachok
Road
Approved GRM established
92816 m3 of spoil disposed safely at Ch 0+920, Ch 0+980, Ch 0+000 Signboard
erected at Ch 0+000 and Ch 0+900
Private house rented for campsite
50 helmets, 50 mask, 50 gloves and 50 jacket are provided to workers
LPG is used for cooking at campsite
Awareness training for 70 participants (2 events)
550 sapling planted in forest area under compensatory plantation
8 Chitwan Khurkhure
(Highway)-
Samitar-
Thakurivanjyang
Road
Approved GRM established
Spoil generated from cutting are taken by concerned local
Contractor has employed local people as labour, therefore, there is no campsite
70 boots and 70 jackets distributed to workers
GPA insurance of 25 labour , 1 casualty occurred (Sanchamaya Praja) while
returning home
Environmental Training for 93 participants (2 events)
9 Sindhuli Pipal
Bhanjyang-
Haitar-Netrakali
Road
Approved GRM established
6000 m3 of spoil disposed safely
29 m long and 2 m high toe wall constructed to manage spoil at Ch 15+880
Temporary campsite established at Ch 16+600, 4+100, 14+600
20 helmets and 50 masks provided to 65 workers
4 signboard erected
2 awareness raising training conducted (122 participants)
1151.5 m2 grass slips planted to stabilize slope from Ch 4+000 - 4+200, 6+740,
7+760, 8+100, 15+558-15+594, 15+885-15+923
Environmental Compliance Monitoring Report
January-June, 2019
Earthquake Emergency Assistance Project 33
SN District Road Sub-
project
IEE
Approval
Status
Environmental Compliances
10 Ramechhap Haldebesi-
Dhobi-
Dhandebesi
Road
Approved GRM established
125000 m3 of spoil disposed at Ch 22+350,21+450,22+000 ,21+300 and
27+300,28+400,28+700,29+250,29+400,29+750
6 signboard erected
3 awareness raising training conducted (119 participants)
Safety gears provided partially
3000 rm brush layering and 3500 m2 grass slips planted to stabilize slope and bio-
engineering activities is ongoing
Devitar-
Phulasipokhari
Road
Approved GRM established
181900 m3 of spoil disposed safely at Ch 15+430, 15+100, 12+540, 11+100, 10+590,
10+170, 9+480, 9+030 and 8+940
House rented for labour camp
3 awareness raising training conducted (92 participants)
1880 rm brush layering and 7136 m2 grass slips planted to stabilize slope
188.88 m 3 Gabion breast wall and 120 m 3 gabion toe wall constructed for controlling
landslide and erosion
11 Okhaldhunga Okhaldunga-
Rumjatar Road
Approved GRM established
4000 m3 of spoil disposed safely at Ch 1+640
600 m3 of toe wall constructed
Chetre landslide at Ch 3+620 and geologist visited the site. The slide area is stable
but geologist has suggested for shifting 10 m towards hill side, for safety against any
earthquake in future.
Houses rented for campsite at Ch 1+340, Ch 2+680, Ch 4+680 and Ch 6+000
LPG and firewood used for cooking
Environmental Compliance Monitoring Report
January-June, 2019
Earthquake Emergency Assistance Project 34
SN District Road Sub-
project
IEE
Approval
Status
Environmental Compliances
71 helmet and mask provided to workers
2 first aid kit provided
GPA insurance of labour
2 events of awareness training conducted
8 signboard erected
207 plants in roadside plantation
315 m2 grass slips planted to stabilize slope
12 Solukhumbu Garma-Nele-
Bogal Road
Approved GRM established
123000 m3 spoil disposed safely at Ch 2+000,3+000, 4+200, 8+300, 13+000, 15+000,
17+000, 19+000
Quarry of 41,380 m3 of stone from Ch 5+400,7+500,7+700,19+000
Safety gears are partially supplied by contractor
83 helmets provided to 200 workers
Labours are insured, Sanitation at labours camp is maintained
900 m3 of breast wall constructed at Ch 3+400, 6+200, 8+300,10+600 to control land
slide
Campsite established at Ch 2+000, Ch 4+000, Ch 6+000, Ch 8+000 (house rented)
Firewood is used in campsite for cooking
Roadside plantation carried out (775 plants)
6412 m2 grass slips planted to stabilize slope
Environmental Compliance Monitoring Report
January-June, 2019
Earthquake Emergency Assistance Project 35
Annex 6: Approval Seeking for Trees to be Removed (As per DFO Report)
S.N. Name of Road Sub-projName of Forest Actual Sapling Seedling Total (Reported by
DFO for Tree
Cutting Approval )
Remarks
Kusum CF 37
Lambodanda CF 35
Sub-total 72 - - 72
Godamchaur CF 2
Bistachhap CF 13
Jayabhadre CF 36
Golintaha CF 54
Kumari CF 8
Bandevi CF 22
Chandol CF 39
Mankamna RF 14
GMF 20
Sub-total 208 - - 208
Dudepakha CF 76 135
Naulo Danda CF 9 24
Ratmate Chihandanda CF 40 85
Seti Devi CF 20 48
Gairidhara Manedanda
Chyanguhi CF
7 13
Sub-total 152 305 - 152
Chanaute Salghari CF 24
Pashupati CF 20
Seti Devi Muladyang CF 2
Khahare Bhirpakha CF 4
Kalikagidde CF 9
Salleshwari CF 2
Lamachaur CF 3
Jyamte Dobhan CF -
Dandapari CF 2
Jukepani Kadeni CF -
Sub-total 66 - - 66
Jana Ekata CF 17 34
Ramche CF 2 47
Hilepani CF 6 49
Sub-total 25 130 - 155
Dovandanda GMF 12 50 150 212
Thampakha CF 7 22 123 152
Sub-total 19 72 273 364
Sisneri CF 10 46 134 190
Aam Danda CF 17 10 500 527
Andheri CF 6 13 41 60
GMF 5 1 6
GMF (proposed CF) 22 55 500 577
Sub-total 60 125 1,175 1,360
Raniswara CF 33
Kerabari CF 1
Sikhra CF 130
Sub-total 164 - - 164
Kalika CF 95 428 780 1,303
Satya Devi CF 13 333 533 879
Parbat CFUG 19 2 - 21
Ratamate LHF 28 269 518 815
Kharbari LHF 2 - - 2
Sub-total 157 1,032 1,831 3,020
Kalika CF 3
Jhalkane CF 19
Ranibas CF 19
Hariyali LHF -
Pragatisil LHF -
Lalupate LHF -
Laliguras LHF -
Manebhanjyang LHF 2
GMF 86
Sub-total 129 - - 129
Bhringeshwor CF
Jhateswari CF
Poku Salghari CF (Saipu CF)
Taruke Salleri CF
Sipu CF
Sub-total - - - -
Shree Sheradevi CF 65
Setidevi Saunepani CF 96
Shree Hari Siddhi RF 31
Sub-total 192 - - 192
Megapatal CF 56
Simdhara Pakha CF 22
Sub-total 78 - - 78
1,322 1,664 3,279 5,960
Sankhu -Palubari -
Nagarkot Road
Godamchour- Godabari-
Badikhel- Lelebhanjyang
Road
Kuntabesi-Nayagaun -
Nagarkot Road
Ghympesal - Balkot-
Palkhu- Swara-Saurpani-
Barpak Road
Luitel - Aappipal -
Harmibhanjyang -
Thalajung – Bhachek Road
Belghari – Archalbot - Lamabagar-
Serabazaar - Lituere -
Pachok Road
3
Bhirkot - Sahare- Hawa
Section of Bhirkot -
Sahare- Hawa -Jiri
Road
Sunkhani-Lamidanda -
Kalinchowk section of
Sunkhani Sangwa Road
Khurkhure (Highway) -
Samitar -
Thakurivanjyang Road
Pipal Bhanjyang -
Haitar - Netrakali Road
Haldebesi -Dhobi-
Dhandebesi Road
Devitar – Phulasi pokhari Section of
Devitar – Doramba – Paseban – Kolibagar Road
9
10
11
No. of seedling and sapling
included in tree cutting approval
report, requiring 1:25 plantation
No. of seedling and sapling
included in tree cutting approval
report, requiring 1:25 plantation
No tree loss along the road
Okhaldunga - Rumjatar
Road
12
13
Total
1
2
4
5
6
7
8
No. of seedling and sapling
included in tree cutting approval
report, requiring 1:25 plantation
Environmental Compliance Monitoring Report
January-June, 2019
Earthquake Emergency Assistance Project 36
Annex 7: Detail on Tree Loss, Targeted Plantation and Cost (NRs.) with Forest Name
Name of CF Tree
Loss
Trees for
Plantation
Estimated
Cost
Name
of
GMF
Tree
Loss
Trees for
Plantation Estimated Cost
Name of
RF/LHF
Tree
Loss
Trees for
Plantation
Estimated
Cost Tree Loss
Trees for
Plantation Estimated Cost
Tree
Loss
Trees for
Plantation
Estimated
Cost
Tree
Loss
Trees for
Plantation Estimated Cost
Kusum CF 37 925 161,311
Lambodanda CF 35 875 152,591
Sub-total 72 1,800 313,902
2 Bhaktapur
Bysai –Jhaukhel – Changu –Telkot-Bhattedanda - Nagarkot Road
115 115 775,000 115 115 775,000
Thaiba - Godamchaur Road
Godamchaur CF 2 50 8,203
Bistachhap CF 13 325 53,316
Jayabhadre CF 36 900 147,645
Golintaha CF 63 1,575 258,379
Kumari CF 8 200 32,810
Bandevi CF 22 550 90,228
Chandol CF 39 975 159,949
Sub-total 183 4,575 750,529
Dudhepakha CF 138 3,450 521,364
Dhami Chaur CF 23 575 86,894
Naulodanda CF 9 225 34,002
Ratmate Chihandanda
CF 63 1,575 238,014
Gairidhara Chyankuti
CF 7 175 26,446
Seti Devi CF 20 500 75,560
Sub-total 260 6,500 982,280
Patikhola Pakha Ban
CF 19 475
Janajagriti CF 5 125
Sub-total 24 600 300,000
Chanaute Salghari CF 20 500 71,680
Pashupati CF 18 450 64,512
Seti Devi Muladyang CF 4 100 14,336
Khahare Bhirpakha CF 4 100 14,336 Pokharipakha CF 6 150 21,504
Kalikagidde CF 9 225 32,256
Salleshwari CF 8 200 28,672
Lamachaur CF 5 125 17,920
Jyamte Dobhan CF 25 625 89,600
Sub-total 99 2,475 354,816
Jana Ekata CF 43 1,075 154,112
Ramche CF 42 1,050 150,528
Hilepani CF 10 250 35,840
Sub-total 95 2,375 340,480
Ghympesal - Balkot- Palkhu-
Swara-Saurpani- Barpak Road Thampakha CF 41 1,025 163,734 GF 174 4,350 694,869 215 5,375 858,603 188 188 12,455 403 5,563 871,058
Amdanda CF 18 450 71,883
Andheri CF 19 475 75,877
Tarkedanda CF 546 13,650 2,180,451
Sub-total 583 14,575 2,328,211
Raniswara CF 143 3,575 571,071
Kerabari CF 3 75 11,981
Sikhra CF 127 3,175 507,175 Sub-total 273 6,825 1,090,226
Kalika CF 347 8,675 1,841,529
Satya Devi CF 119 2,975 631,533
Sub-total 466 11,650 2,473,062
Kalika CF 3 75 11,334 Hariyali LHF
Jhalkane CF 41 1,025 154,898 Pragatisil LHF
Ranibas CF 3 75 11,334 Lalupate LHF
Laliguras LHF
Manebhanjyang
LHF 7 175 26,446
Bhringeshwor CF 5 125 19,644
Jhateswari CF 8 200 31,430
Poku Salghari CF
(Saipu CF) 15 375 58,931
Taruke Salleri CF 30 750 117,863
Sipu CF 47 1,175 184,651
Sub-total 105 2,625 412,519
Shree Sheradevi CF 20 500 78,575
Setidevi Saunepani CF 50 1,250 196,438
Sub-total 70 1,750 275,013
Megapatal CF 56 1,400 215,180
Simdhara Pakha CF 22 550 84,535
Sub-total 78 1,950 299,715
Ghumnepani CF
Mukle Maidel CF
Kordap CF
2,396 59,900 10,262,051 1,168 29,200 4,487,267 60 1,500 237,085 3,624 90,600 14,986,402 4,039 4,039 1,028,135 7,663 94,639 16,014,538
9 Sindhuli Pipal Bhanjyang - Haitar -
Netrakali Road 373 373
Sub-total 47 1,175 177,566
GF 832 20,800 3,143,296 886 22,150 3,347,308
Okhaldunga - Rumjatar Road 78 1,950 299,715 348 348 22,251 426 2,298 321,966
Garma - Nele -Bogal Road
Total
Ramechhap 10
105 2,625 412,519 Haldebesi -Dhobi-
Dhandebesi Road
Devitar – Phulasipokhari Section of Devitar – Doramba – Paseban – Kolibagar Road
39 975 153,221 417 417
Solukhumbu 12
27,213
11 Okhaldhunga
105 2,625
Remarks
Khurkhure (Highway) -
Samitar - Thakurivanjyang
Road
106 106 6,181
412,519
109 2,725 428,234 Shree Hari
Siddhi RF 526 3,142 455,447
23,480 1,259 22,523 3,370,788
34,384
11,756 2,479,243 466 11,650 2,473,062
Belghari – Archalbot - Lamabagar- Serabazaar -
Lituere - Pachok Road
572
2,375 95 340,480 2,375 340,480
34,384
792 7,344 1,124,609
1,244 18,644 2,929,671
358,955
1,057,002
Khopasi-Dhungakharka
Kavre 4
24 600 300,000
1,187 1,187 74,722 1,447 7,687
168 2,544
293 5,501 895,132 Godamchour- Godabari-
Badikhel- Lelebhanjyang Road
122 122 8,766 194 1,922 322,668
GF 20 500 82,025 14 Manakamana
RF 350 57,418 76
Compensatory plantation
(Private Land) Total Compensatory Plantation (Community Forest)
Compensatory Plantation (Government
Managed Forest)
Name of Sub-Project
Compensatory Plantation (Religious
Forest/Leasehold Forest)
SN Name of
District
Kathmandu 1 Sankhu -Palubari -Nagarkot
Road
Total (Forest Land)
72 1,800 313,902
76
519 519
519 725 18,125 2,895,288 519
6,825 1,090,226
24
99 2,475 354,816
95
Luitel - Aappipal -
Harmibhanjyang - Thalajung – Bhachek Road
5,160 217 5,425 889,971
260 6,500 982,280
69
600 300,000
69 4,139
Dolkha
273
8
3
5
6
7
GF 142 3,550 567,077
Lamjung
Chitwan
Gorkha
Lalitpur
Kuntabesi-Nayagaun -
Nagarkot Road
Bhirkot - Sahare- Hawa
Section of Bhirkot - Sahare-
Hawa -Jiri Road
Sunkhani-Lamidanda -
Kalinchowk section of
Sunkhani Sangwa Road
Environmental Compliance Monitoring Report
January-June, 2019
Earthquake Emergency Assistance Project 37
Annex 8: Spoil management Disposal Format
SN Road Section (Ch) Earthwork
Cutting (m3)
Earthwork
Filling (m3)
Remaining Spoil to
be Managed (m3)
Disposal Site
Location
Toe-wall Provision Lead
Distance (m) From To Ch Volume (m3)
Earthquake Emergency Assistance Project 38
Annex 9: Environmental Safeguard Compliance Monitoring Format
SN Description Indicator Status Remarks
Monthly Cumulative
1 Forestry clearance for using forest area and tree cutting
Obtained/ongoing/not initiated
2 Stock piling and spoil disposal management
Obtaining written permission for stockpiling (Y/N)
Preparation of spoil disposal management plan (Y/N)
Location of disposal site near the water courses (Y/N)
Location of spoil disposal site
Volume of spoil generated (m3)
Volume of safely disposed spoil (m3)
Spoil falling or being washed on to forest and farm land (Y/N)
Spoil disposal work affecting public interest, locals and their properties (Y/N)
3 Toe walls for safe disposal of excavated materials
Number and volume (m3) of toe wall constructed
4 Bioengineering works
Location (chainage)
Area (Rm/m2)
Type of measures taken
Amount spent (NRs.)
5 Dust emission Covering of delivery vehicles during transportation (Y/N)
Earthquake Emergency Assistance Project 39
SN Description Indicator Status Remarks
Monthly Cumulative
Spray of water for suppressing dust emission (Y/N) and time interval
6 Water quality Water quality observed near road
7 Quarry site management
Location
Volume of aggregates/stones/other materials supplied (m3 )
Rehabilitation of site (Y/N)
8 Campsite management
Supply of safe drinking water (Y/N)
Temporary toilets constructed in camp sites (no.)
Energy used for cooking (fuel wood, kerosene, LPG, electricity)
Proper management of waste disposal (Y/N)
Separation of waste disposal in biodegradable and non-biodegradable (Y/N)
9 Drainage management
Drain water discharged into farm land/ risky areas (Y/N)
Cross drainage structure (no.) & volume (m3)
10 Bitumen management
Fuel wood being used for bitumen heating (Y/N)
Bitumen drums stored in dedicated areas and not scattered along the road (Y/N)
Earthquake Emergency Assistance Project 40
SN Description Indicator Status Remarks
Monthly Cumulative
Provision for leakage and spills in storage & service yards (Y/N)
11 Land slide and erosion control measures
Location (Ch)
Type of measures taken
Number and volume of structure (m3)
12 Compensatory plantation in forest area
Exact tree loss (No.)
Establishment of nursery (number & location)
Plantation carried out (number of plants & area in ha)
Name & location of forest
Plantation survival rate (%)
Amount spent (NRs.)
13 Compensatory plantation in private land
Number of plants felled
Plantation carried out (number of plants)
Plantation survival rate (%)
Amount spent (NRs.)
14 Road side plantation
Plantation carried out (number of plants)
Location
Plantation survival rate (%)
Amount spent (NRs.)
15 Rehabilitation of public infrastructure, culturally &
1. Name & Location
2. Name & Location
Earthquake Emergency Assistance Project 41
SN Description Indicator Status Remarks
Monthly Cumulative
religiously sensitive spot
16 Occupational health & safety
Number of Personal Protective Equipment (PPE) provided
Use of PPE by workers (%)
First aid kit provided with medicines (number)
Replacement of medicines (Y/N)
Accidental insurance (number of workers)
Type & number of accident occurred
Compensation provided
Number of workers fallen sick
Coordination with nearby health center (Y/N)
17 Informative/ safety /environmental awareness signboard erected
Number
Location
18 Training/campaign/event as per EMP of IEE report
1. Name of Event ( location, no. of participants)
2. Name of Event ( location, no. of participants)
Earthquake Emergency Assistance Project 42
Annex 10: Photographs
Retaining wall to protect existing water
reservoir tank
Gabion breast wall with grade cutting
Use of safety gears
Lack of safety gears
Earthquake Emergency Assistance Project 43
Tree Felling, Transportation and Logging Activities
Agreement between DLPIU and FUG for tree cutting
Earthquake Emergency Assistance Project 44
Roadside Plantation
Compensatory Plantation
Plantation under Bio-engineering
Earthquake Emergency Assistance Project 46
Table of Contents
1. THE PROJECT BACKGROUND 47
2. CHANGES IN THE PROJECT SCOPE AND ADJUSTED SAFEGUARD MEASURES 49
3. ENVIRONMENTAL SAFEGUARD IN EEAP 49
4. COMPLIANCE STATUS WITH ENVIRONMENTAL COVENANTS 49
5. INSTITUTIONAL ARRANGEMENT 49
6. COMPLIANCE WITH ENVIRONMENTAL SAFEGUARD MEASURES 50
7. ISSUES AND CORRECTIVE ACTION 52
8. PROPOSED MAJOR ITEM OF FOCUS FOR NEXT REPORT 53
List of Tables
Table No. 1.1: List of Sub project Under EEAP 47
Table No. 1.2: Corrective action and Way Forward 52
List of Annexes Annex 1: Planning & Implementing Environmental Safeguards Activities
Annex 2: Status of Compliance with Environmental Covenants
Annex 3: Photographs
Semi Annual Environmental Monitoring Report: 05 January-June 2019
47
1. THE PROJECT BACKGROUND
1.1 Background
The proposed loan (No. 3260-NEP) under Earthquake Emergency Assistance Project (EEAP) is
financing improvements of three feeder roads, a total of 99.741 km, in the central and western
regions of Nepal. While the Project will contribute to development and expansion of the Strategic Road Network (SRN), it will include an institutional capacity assessment in the areas of road
safety and road maintenance, which will form the basis for a capacity development program.
Gender and social inclusion through a livelihood program will be targeting women involved in road
construction activities in the project-affected area.
The project roads are: (i) Dolakha – Singati Road (34.49 Km), (ii) Dhading Gorkha Road (42.274
Km) excluding 25 km overlap with Mid-Hill highway in total of 87.274 km and (iii) Panchkhal –
Melamchi Road (22.977 Km).The Department of Roads (DoR) intends to improve these roads to an all-weather bituminous Feeder Road Standard. Project roads have been selected based on
environment, resettlement, social and economic impacts; and project readiness. The Project is
relevant to achieving results of the Country Strategy and Program (2013-2017), enhancing global-
local connectivity to facilitate regionally balanced economic growth. The detail of sub project is listed below
Table No. 1.1: List of Sub project Under EEAP
S. No. Road Length (Km)
Road Classification
Contract Date
Completion date
1 Dolakha – Singati 34.490 Feeder Road September 26, 2016
2 Dhading – Gorkha 42.274 Feeder Road January 12, 2017
3 Panchkhal – Melamchi
22.977 Feeder road October 08, 2017
October 07, 2019
Total 99.741
(Revised)
Source: Project data sheet, 2016
* Length of Dhading – Gorkha Road for upgrading has been shortened as 4.00 km has been
already upgraded by DoR, Division Road Office.
* Length of previously planned Panchkhal - Melamchi – Tibmu Road Section has been revised by
covering only Panchkhal – Melamchi Section due to budgetary Constraints.
Thus scope of work for upgrading has been reduced to 99.741 km only as against of previously
planned length of 122 km.
Semi Annual Environmental Monitoring Report January-June 2019
48
Figure 1: Map of Nepal showing the sub-project
49
1.1.1 Objective
The objective of this semi-annual monitoring is to assess the progress on safeguard implementation including; status of air quality, noise and vibration, quarry site operation,
stockpiling of the materials, construction waste and well managed construction camp, labor
camps and bioengineering work etc.
1.1.2 Approach of Semi-Annual Monitoring
This safeguard implementation monitoring report has been prepared through the approach of monthly progress report of contractor and field visit conducted during reporting period.
1.1.3 Scope of Semi-Annual Monitoring
This sem i -annual report is 6th semiannual report which includes the status of safeguard
implementation activities in Earthquake Emergency Assistance Project covering the period
from January - June 2019.
1.2 Sub-project and Physical Progress of the Project Activities
Up-to the reporting time, contract award for all the road sub projects has been completed and
construction works in Dolakha - Singati Road, in and package No.1, 2, 3 and 4 for Dhading -
Gorkha Road and in Panchkhal – Melamchi Road Section is in progress.
2. CHANGES IN THE PROJECT SCOPE AND ADJUSTED
SAFEGUARD MEASURES The scope of project has not changed from its original scope. In case of Dhading - Gorkha Road, and Panchkhal - Melamchi Road Project supplementary IEE have been prepared and approved
from MoPIT to accommodate the variation in tree cutting numbers from earlier included in
approved IEE report. The project has been categorized as “B” in terms of Environmental impact.
3. ENVIRONMENTAL SAFEGUARD IN EEAP Environmental assessment is the primary administrative tool to integrate environmental
considerations into decision making to ensure that proposed development intervention will have
minimum environmental impacts. EEAP falls in category “B” project according to ADB Safeguard Policy Statement (SPS) (2009). As per Environment Protection Act 1997 and Environment
Protection Rule, 1997, IEE is mandatory before the implementation of the project. Accordingly
IEE report has been prepared and approved by the concerned authority. Further, monitoring is
being done to ensure the compliance of mitigation measures and implementation of Environmental Management Plan. Planning and Implementation status of the sub-projects are presented in Annex 1.
4. COMPLIANCE STATUS WITH ENVIRONMENTAL COVENANTS Environmental safeguard related project activities are in compliance with covenants as regular follow up actions are being taken according to the approved detail project report (refer Annex 2 for detail).
5. INSTITUTIONAL ARRANGEMENT The National Reconstruction Authority (NRA) is executive agency (EA) and Ministry of Physical
Infrastructure & Transport (MOPIT) the Project Management Unit (PMU) has authorized Department of Roads (DOR), Project Road Directorate (ADB) as key Implementing Agency (IA)
& has formed Project Implementation Unit (PIU). The project Directorate on behalf of DOR, is
monitoring safeguard compliance, deploying safeguard focal person. Besides, to administer the
overall project construction activities including the monitoring of safeguard issues local level, Department of Roads has established the Project Manager’s office for each Road Sub Project.
50
The PIU has appointed Construction Supervision Consultant, which has the provision of Bio-
Engineering/Environment Specialist for assisting & reporting of safeguard compliance as per
provision in EMP. Assistant Resident Engineer (ARE) of supervising consultant in each Road Sub Project has been nominated as a focal person for safeguard related activities. Thus, the
Government has sufficient capacity in implementing ADB safeguard requirements.
6. COMPLIANCE WITH ENVIRONMENTAL SAFEGUARD
MEASURES Almost all contractors have appointed Environmental Focal person in all the sub-project roads.
Grievance Redress Mechanisms have been established in all the sub-project roads. CSC
Environmental Specialist has been visiting the project sites in intermittent basis. Adequate cautionary signboards have been placed in all the construction sites and working area has been barricaded with appropriate measures. Compliance with safeguard (based on the Annex 3)
measures is presented.
6.1 Safety Management
In Dolakha - Singati Road construction activities are progressing. Contractor has submitted environmental management action plan (EMAP) and has been approved from CSC. Based on the approved EMAP, environmental monitoring is being carried out. Assistant Resident Engineer (ARE) of the supervising staff has been nominated as a focal person for environment safeguard implementation on behalf of CSC in each Road section. In this road, occupational health and safety measures have been followed. Sufficient number of PPE like helmet, face mask, boot, gloves have been provided by the contractor to labors including supervision consultant staff at site. Workers have been provided also with first aid kit with medicine in their camp. Proper precautionary signboard, temporary barricades / ribbons are used to provide safety to road users, vehicles while construction activities are going on. Sometimes while bituminous is in progress, flagman are deputed in order to control/stop the traffic as per the requirement. Insurance cover for contractor's employee and labors has been done. So far no accident during construction has been reported.
In Panchkhal – Melamchi Road, camp is in operation at Ch 6+950 two different camps are in operation with LPG is being provided by purchasing from the market. In this camp all facilities
like toilet, drinking water are available. Some of the labor working in this sub-projects are locals.
Contractor has put fire safety measures at the camp site.
6.2 Management of Stockpile of Construction Materials
In Dolakha-Singati Road, at ch. 2+050 required construction materials are being stockpiled. All the measures to keep the stocked material safe (fencing of the area) has been applied. Contractor
has made agreement with land owner for stockpiling construction material. Once the construction
work completes, the land used by the contractor shall be reinstated in its original condition.
In Dhading-Gorkha Road,
EEAP/NCB/DG/01: Major stockpile has been managed at crusher yard located near Ankhu Khola, minor stock of concrete aggregate has been kept at 11+600 km and 11+800 km.
EEAP/NCB/DG/02: Major stockpile has been managed at crusher yard located near Ankhu
Khola, minor stockpile of concrete aggregate has been kept at 11+600 km and 11+800 km.
EEAP/NCB/DG/03: Materials are stockpiled at the location of crusher plant at DG-03=56+080.
EEAP/NCB/DG/04: major stock pile is doing at 66+200 km.
51
In Panchkhal-Melamchi Road, at ch.3+950 required construction materials are being stockpiled.
All the measures to keep the stocked material safe (fencing of the area) has been applied.
Contractor has made agreement with land owner for stockpiling construction material. Once the construction work completes, the land used by the contractor shall be reinstated in its original
condition
6.3 Operation of Quarry site and Crusher Plant
In Dolakha - Singati Road, contractor is planning to purchase additional 10000 cu. m. of base materials from the private crusher plant at Singati.
In Dhading-Gorkha Road, for package 1, Stone quarry is operated at Pakhare Khola (500m from
Km 1+800), Km 6+500, Bajhopalpa Danda (500 m from Km 6+100) and one crusher at Ankhu
Khola (Ch. 26+667). For package 2, Stone quarry is operated at Km 19+150, Km 19+550, Km 20+150 and crusher at Ankhu Khola (Ch. 26+667) is used. ).For package 3, Stone quarry is
operated at Km 61+490 and 55+120. For package 4, no quarry has been identified yet.
Restoration of Quarry Sites: So far the materials are being extracted from quarry site. Due to
excavation, a vertical slope is formed for which the slope will be maintained to eliminate land
slide. All materials i.e. boulders, gravels etc. will be collected from Daraudi River and quarry site
located at Ch: 55+120.
In Panchkhal – Melamchi Road, one hillside quarry has been selected 1 km ahead from Gairibesi,
Hinuwapati at 07+000 km and another at 16 km (1km far from 16+000 km).
6.4 Spoil Disposal Management
In Dolakha-Singati Road, extra earth materials by cutting have been disposed safely at Km.
6+620 (1200 m3), Km. 8+800 (1500 m3) and at Km. 19+200 (800 m3) with required protection
measures as per the submitted EMAP by the contractor.
In Dhading-Gorkha Road, package 1, 80,000 m3 of spoil materials has been disposed safely at
the approved sites at Km. 10+530 and at Km. 13+500 with required protection measures. For
package 2, 30,000 m3 of spoil materials has been disposed safely at the approved site at Km.
12+625 and at Km. 12+750 with required protection measures. The proposed disposal area/tipping site is located at Ch: Km 58+350-58+390, Ch: Km. 62+170-62+230, Ch: 61+210-
61+230, Ch:61+080-61+150.The tipping area are far from the settlement areas with no drainage
problems. Most of the suitable cut earth materials have already been used for filling the road
structures. The sites used for tipping is a flat land and vegetation clearance is not required as well.
In Panchkhal – Melamchi Road disposal sites has been identified at Km. 0+960, 3+040, 3+900 , 7+350 , 7+950 , 11+210 , 12+740 , 12+830 , 13+400 , 17+650 . The identified sites are using with after the lease process with owners.
6.5 Bioengineering Works
In Dolakha –Singati Road three areas have been identified and Bioengineering have been done.
Beside that as per the requirement Bioengineering has done. Beside this, in two road projects, bioengineering work has not been started yet. The some of the Bioengineering sites for the
Gorkha- Dhading and Panchkhal-Melamchi have been identified and plans for the next year as
the excavation work is still ongoing.
6.6 Removal of Trees
In Dolakha-Singati Road there is no issue of tree cutting. In case of Dhading-Gorkha Road, total number of 1200 trees required to be cut are identified and tagged and cleared. Panchkhal-
Melamchi Road also the 340 trees have cleared during this time. The compensatory plantation is
ongoing.
52
6.7 Community Infrastructure
In Dolakha-Singati Road, one stone masonry water tank of 2000 m3 capacity has been
constructed. Around 100 m of irrigation crossing has been constructed/ rehabilitated. Foot trail,
steps to houses (about 5 m3) and relocation of water supply pipe lines has been carried out in this reporting period. In Dhading-Gorkha Road, the process of electric pole removal is in progress
and masonry steps (about 6 m3) to houses has been constructed and about 4205 m (100 m - 110
mm dia., 155 m – 40 mm dia., 530 m – 32 mm dia., 570 m – 25 mm dia., 1300 m – 20 mm dia.,
and 1550 m – 16 mm dia.) of water supply pipelines has been reinstated. In case of Panchkhal- Melamchi Timbu Road (Panchkhal- Melamchi section) activities have been started and are on
progress regarding community infrastructure with the progress of construction.
6.8 EMP Implementation Monitoring and Reporting
Environmental monitoring is being carried out through environment specialist. Supervision staff
at site has been provided environmental monitoring checklist. Supervision staff at site are regularly checking the status at site. Details of the compliance of safeguard measures by the
contractor are being submitted to the Resident Engineer’s office and is verified. Process for
grievance redress mechanism is implemented. Two GRC has been formed for Dhading and
Gorkha district. Each month along with monthly progress report, environmental safeguard status
is being included. In Panchkhal-Melamchi Road also it is initiated and going on the reporting of the EMP implementation status.
6.9 Occupational Health and Safety
Proposed road upgrading requires a large numbers of labor forces for undertaking its activities of various natures. These activities amongst others include risk prone ones like quarry, rock breakup works, etc. When undertaken without safety measures, helmet, gloves, boots and ear guards, labors may get injured or even death. All the labours are provided the safety gears.
6.10 Dust Control Measures
During the construction works in the site, various types of dusts are arising in and around the
area. The dust control measures have been applied in all the sites. In Dolakha- Singati Road,
Dhading-Gorkha and Panchkhal-Melamchi Roads, water sprinkling are doing wherever need. The school area, settlement area and the working area are regularly spraying the water to control
the dust. The peoples around the Dhading –Gorkha Road the dust problem is still have the oral
grievance. This is already informed the contractor.
7. ISSUES AND CORRECTIVE ACTION Since the forestry clearance in Panchkhal- Melamchi Road is completed. But the Bioengineering
for the all roads may be the main issue for the upcoming days. The main issues and corrective actions required are presented below.
Table No. 1.2: Corrective Actions and Way Forward
S.N. Issues Way Forward
1 Spoil disposal Spoil disposal at designated sites and provision of sufficient toe walls and preparation and strict enforcement of spoil disposal management plan
2 Implementation of bioengineering work for slope protection at land slide areas
Identification of bioengineering locations and carrying out bioengineering activities at recommended sites in Dhading-Gorkha Road and Panchkhal- Melamchi Road.
3 Use of safety gears like helmet, boot, gloves and mask
Enforce the workers at site for using the safety gears.
53
S.N. Issues Way Forward
4 Environmental Management Action Plan
Monitor the activities as per approved EMAP
5 Tree cutting in the Panchkhal- Melamchi Road
Tree cutting completed and coordination for compensatory plantaion
8. PROPOSED MAJOR ITEM OF FOCUS FOR NEXT REPORT
Progress on the bioengineering work in Dolakha- Singati Road, Dhading – Gorkha Road and
Pachkhal- Melamchi will be the main item of focus for next report.
56
Annex No: 01
Planning and Implementing Safeguards Activities
B. 1. Environmental Safeguards - IEE/EMP Preparation
Reporting period
January-June 2019
SN Name of
Subproject
Environmental screening is carried out? (Yes or No)
Environment category of the project / subproject (A/B/C/FI)
EARF is prepared
(if applicable)
(Yes/No)
EIA/IEE/DDR with EMP is
prepared (Yes/No)
ADB approved EIA/IEE
with EMP (Yes / Under
Review / Not Yet
Due/Over Due)
Government approved
EIA/IEE with EMP
(Yes / Under Review / Not
Yet Submitted)
Safeguard monitoring
and coordination mechanism established
(Yes/No)
GRC is established
(Yes/No)
Automated safeguard monitoring
system customized
(Yes/No)
EMP cost in
approved document
is included in BOQ as an
individual item
(Yes/No)
Remarks
1
Dolakha - Singati Road
Yes B Yes Yes Yes Yes Yes Yes Yes Yes
2
Dhading - Gorkha Road
Yes B Yes Yes Yes Yes Yes Yes Yes Yes
3
Panchkhal - Melamchi Road
Yes B Yes Yes Yes Yes No Yes No Yes
Note: EIA- Environmental Impact Assessment; IEE- Initial Environmental Examination; DDR- Due Diligence Report; EMP- Environmental Management Plan;
GRC- Grievance Redress Committee; BOQ- Bill of Quantity
Semi Annual Environmental Monitoring Report January –June 2019
59
Annex 2: Status of Compliance with Environmental Covenants
Covenants Status June 2019
Schedule 4-7 Conditions for Award of Contracts The Borrower shall not award any
Works contract for a Subproject which involves environmental impacts until the EA
or the IAs has:
Obtained the final approval of the EIA/IEE from the Ministry of Population and Environment (for EIAs) / concerned sector agency (for IEEs incorporated the relevant provisions from the EMP into the Works contract
Complied
Schedule 5-1. Project is implemented in accordance with PAM. Being complied
with
Schedule 5-3. Subprojects are selected and approved in accordance with the
selection criteria set out in the PAM. Complied
Schedule 5-4. Preparation, design, implementation, and operation of each Subproject
comply with applicable laws; the Environmental Safeguards; the EARF; and IEE and
EMP. Complied
Schedule 5-7. Necessary budgetary and human resources made available to fully
implement the EMPs, and the RPs. Complied
Schedule 5-8. All bidding documents comply with IEE and EMP, budget is made
available for environmental measures; any unanticipated environmental impacts, Complied
Schedule 5-9. (a) A semi-annual Safeguards Monitoring Reports submitted to ADB
and disclosed relevant information; (b) any unanticipated environmental risks and
impacts reported promptly to ADB; and (c) any actual or potential breach of
compliance reported.
Complied
Schedule 5-11. The core labor standards and applicable laws are complied. Bidding
documents and contracts require that the contractors (a) comply with applicable labor
law and incorporate workplace occupational safety norms; (b) do not use child labor;
(c) do not discriminate workers; (d) do not use forced labor; (e) allow freedom of
association.
Complied
Schedule 5-15. Within 6 months after the Effective Date, the Borrower shall prepare
a Grievance Redress Mechanism, acceptable to ADB, and establish a special
committee to receive and resolve complaints/grievances or act upon reports from
stakeholders on misuse of funds and other irregularities, including grievances due to
resettlement. The special committee will (a) make public of the existence of this
Grievance Redress Mechanism, (b) review and address grievances of stakeholders
of the Project, in relation to either the Project, any of the service providers, or any
person responsible for carrying out any aspect of the Project; and (c) proactively and
constructively responding to them.
Complied
Environmental Monitoring Report January-June 2019
61
Photograph
Photo No. 01: Environment safeguard policy training conducted by PD Office at Dhulikhel.
Photo No. 02: Stone masonry breast wall at Ch: 33+350.
Photo No. 03: Irrigation canal for water supply in the local water mill (Pani Ghatta) over the masonry breast wall at 11+030 km.
Photo No. 04: Stone masonry retaining wall at Ch: 30+260.
Photo No. 05: Bio-Engineering photos at 3+280 km. Photo No. 06: Bio-Engineering photos at 3+280 km.
Environmental Monitoring Report January-June 2019
63
TABLE OF CONTENTS
1. BACKGROUND 64
2. ENVIRONMENTAL SAFEGUARD IN EEAP 65
3. OVERALL ENVIRONMENTAL SAFEGUARD STATUS 66
4. CONSTRUCTION APPROACH 66
5. COMPLIANCE STATUS WITH ENVIRONMENTAL COVENANTS 66
6. COMPLIANCE WITH ENVIRONMENT SAFEGUARD MEASURES 67
7. INSTITUTIONAL ARRANGEMETS 69
8. ISSUES AND CORRECTIVE ACTION 70
9. MAJOR ITEMS FOCUSED FOR NEXT REPORT 70
LIST OF TABLE
Table 1: Status of Compliance with Environmental Covenants……………………..67
Table 2: Monitoring Reporting and Field Visit…………………………………………69
Table 3: Issues and Way Forward …………………..…………………………………70
LIST OF FIGURE
Figure 1: Map of Nepal showing EEAP Districts……………………………………..65
LISTS OF ANNEXES
Annex 1 Status of Environmental Safeguard Planning and Implementation
Annex 2 Detail of Plantation
Annex 3 Status of Grievances Related To Environmental Safeguard
Annex 4 Monitoring Reporting Format
Annex 5 Photographs Showing Environmental and Safeguards Issues
Environmental Monitoring Report January-June 2019
64
1. BACKGROUND
Earthquake Emergency Assistance Project (EEAP) is being implemented by covenant loan
assistance from Asian Development Bank (ADB) and counterpart funding from Government of Nepal. The goal of the project is to support the government to accelerate rehabilitation and
reconstruction following the devastating earthquake of 25 April 2015 and the major aftershock
of 12 May 2015. The project will support the rebuilding of schools, roads, and district-level
government buildings, and strengthen resilience to future disasters. EEAP, Loan 3260 for $200 million was approved on 24 June 2015, signed on 21 August 2015 and became effective on
10 September 2015.
A. Impact and Outcome
The impact of the project is accelerated economic and social recovery in earthquake
affected districts. The outcome will be critical economic and social services resumed with
disaster-resilient infrastructure.
B. Outputs
The project has four outputs:
(i) Output 1. Schools are rebuilt and upgraded. At least 700 schools will be rebuilt or
retrofitted in line with school reconstruction plans to disaster-resilient standards and
equipped with water and sanitation facilities, including sex-disaggregated toilets. About five will be model schools built with information and communication
technology equipment, science laboratories, and improved learning spaces. This
target has been reduced to 154 school buildings (MTR, October 2017).
(ii) Output 2. Roads and bridges are rehabilitated and/or reconstructed. About 135 km
of strategic roads and about 450 km of rural roads damaged by the earthquake and
landslides will be rehabilitated. Target for strategic and district roads has been
reduced to 123.9 km and 525 km respectively (MTR, October 2017). Project roads and bridges will have built back better features for road safety and climate resilience.
Construction and maintenance equipment will also be procured.
(iii) Output 3. District-level government facilities constructed and/or rebuilt. About 300
district-level government buildings will be rebuilt or retrofitted to disaster resilient
standards with basic utilities, and furnished. This target has been reduced to 123
buildings (MTR, October 2017). Transitional district-level government offices will
also be established to enable services to continue throughout the reconstruction period.
(iv) Output 4. Disaster preparedness and management capacities strengthened. All
outputs are assured to be disaster risk resilient. Schools in poorer and severely
affected districts constructed or rebuilt as model disaster resilient schools under
Disaster risk reduction and Livelihood Restoration for Earthquake Affected
Communities Project funded by Japan Fund for Poverty Reduction (JFPR) Grant.
This rebuilt or retrofits eight model schools with disaster resilient standard in line with
Environmental Monitoring Report January-June 2019
65
government’s school reconstruction plans and to be equipped with science laboratories and improved learning space, furniture and amenities.
C. Project Locations
The project is being implemented in 8 districts to rebuilt 154 schools: Kathmandu, Bhaktapur, Kavreplanchowk, Sindhupalchowk, Dolakha, Ramechhap, Okhaldhunga, and Sindhuli.There are two model schools under reconstruction, one in each district, as Dolakha and Ramechhap financed by JFPR grant. Furthermore, 6 model schools are being reconstructed, one in each district, as Lalitpur, Rasuwa, Nuwakot, Gorkha, Dhading and Makawanpur also financed JFPR grant.
Figure 5: Map of Nepal showing EEAP Districts
D. Purpose of Safeguard Compliance Monitoring Report
The purpose of this Environmental Compliance Monitoring Report is to fulfill the
environmental safeguard requirements of the government and ADB. The main purpose
of the Semiannual Monitoring Report is to assess the progress on environment and
safeguard implementation at the construction sites which includes status of air quality,
noise and vibration, quarry site management, spoil management, use of personal protective equipment (PPE), management of construction waste materials and camp site
management covering from January to June 2019.
2. ENVIRONMENTAL SAFEGUARD IN EEAP An Environmental Assessment and Review Framework (EARF) was prepared in accordance
with ADB’s Safeguards Policy Statement (SPS), 2009. Due diligence report (DDR) with EMP
Focused Districts: Kathmandu, Bhaktapur, Kavreplanchowk, Sindhupalchowk Sindhuli, Dolakha, Ramechap
Additional Districts: Gorkha, Dhading, Makwanpur, Rasuwa, Nuwakot & Lalitpur
Environmental Monitoring Report January-June 2019
66
were required for school and office building sub-projects along with incorporating Environmental Management Plan (EMP) into bidding and contract documents to be
implemented by contractors.
Environmental assessment is the primary administrative tool to integrate environmental considerations into decision making to ensure that proposed development intervention will
have minimal environmental impacts. The project falls in category “C” on the basis of rapid environmental and social assessment check lists prepared as per SPS, 2009. Based on the
SPS, 2009 DDRs were also prepared for each sub project.
3. OVERALL ENVIRONMENTAL SAFEGUARD STATUS The overall environmental safeguard status of EEAP in reference to output 1, DDRs reports of all 154 school sub-projects have been prepared and submitted to central Level project
Implementation Unit- Education (CLPIU-E). The status of environmental safeguard planning and implementation of sub-projects is presented in Annex 1.
4. CONSTRUCTION APPROACH The project applies National Competitive Bidding (NCB) approach for reconstruction of
schools. Contractors have been mobilizing equipment and human resources to execute the
contract and complete it within the stipulated time. Spoil disposal has been planned to
balance with cutting and filling as far as possible. The use of bio-engineering techniques with integrated use of vegetation, civil engineering structures and proper water management
systems for slope protection such as retaining walls, breast walls. Overall construction
activities follow the environment friendly approach as much as possible.
The school building blocks are designed and executed as per the motto “Built –Back –Better” formulated by the National Reconstruction Authority (NRA). The approach taken in design
and construction includes the following features:
(i) Design incorporates earthquake resistant features.
(ii) Design foresees maximum use of local materials and manpower as far as possible.
(iii) Design includes environmental friendly measures such as locations of building without risk of landslide, flood etc. It also includes energy saving design, environmental
enhancement measures such as trees plantations, bio-engineering techniques,
landscaping, rain water harvesting etc. where feasible.
(iv) Most of the constructions are manual and labour intensive with occasional use of small equipment such as concrete mixture, small backhoe for excavation, tractors and small
trucks for transportation of materials.
(v) No child labour is permitted.
(vi) Labour safeguard is focused.
5. COMPLIANCE STATUS WITH ENVIRONMENTAL COVENANTS The environment safeguards related project activities are generally in compliance with loan
covenants. The detail of environment covenants is presented in Annex-3.
Environmental Monitoring Report January-June 2019
67
Table 10: Status of Compliance with Environmental Covenants
Covenants Status, June 2019
Schedule 4-7 Conditions for Award of Contracts: The Borrower shall not award any works contract for a subproject which involves environmental impacts until the Executing Agency or the Implementing Agencies has:
(c) obtained the final approval of the DDR from the concerned agency (d) Incorporated the relevant provisions from the EMP into the Works
contract.
Being complied
Schedule 5-4. Preparation, design, implementation, and operation of each subproject comply with applicable laws; the Environmental Safeguards; the EARF; DDR and EMP.
Being complied
Schedule 5-7. Necessary budgetary and human resources made available to fully implement the EMPs.
Being complied
Schedule 5-8. All bidding documents comply with DDR and EMP, budget is made available for environmental measures; any unanticipated environmental impacts,
Being complied
Schedule 5-9. (a) A semi-annual Safeguards Monitoring Reports submitted to ADB and disclose relevant information; (b) any unanticipated environmental risks and impacts reported promptly to ADB; and (c) any actual or potential breach of compliance reported.
Being complied
Schedule 5-11. The core labor standards and applicable laws are complied. Bidding documents and contracts require that the contractors (a) comply with applicable labor law and incorporate workplace occupational safety norms; (b) do not use child labor; (c) do not discriminate workers; (d) do not use forced labor; (e) allow freedom of association.
Being complied
6. COMPLIANCE WITH ENVIRONMENT SAFEGUARD MEASURES Contracts have been awarded for all sub-projects under the project and construction works have already been started in 154 sub-projects. Of 154, 84 schools: 22 schools in Kavreplanchowk and 19 schools in Ramechhap, 3 school in Kathmandu, 2 in Bhaktapur, 11 schools in Sindhuli, 6 schools in Okhalandhunga and 14 schools in Sindhupalchowk and 7 schools in Dolakha CLPIU-E handed over to the respective School Management Committees after completion.
For better environmental safeguard compliance of the project, implementation of EMP has been strictly carried out. The summary of environmental compliances is listed (Annex 1):
(i) Awareness raising training. A training on social, environment, Gender Equality
and Social Inclusion (GESI) and technical aspects for Engineers and Sub-engineers
working in District Level Project Implementation Units was conducted to enhance
the technical skills of personnel involved in implementation and supervision of
earthquake resilience school building reconstruction works. The second regular two
days training programme was organized by DSC in collaboration with CLPIU-E at
different district headquarters of the project districts.
Environmental Monitoring Report January-June 2019
68
(ii) Occupational health and safety. Occupation health and safety have been followed.
PPE like, helmet, gloves, boots, and jackets have been provided by the contractors
to workers. They were oriented to use PPE during site visits. The use of PPE is found
satisfactory at each construction site. Insurance of each worker had been done. So
far, no accident during construction had been reported. First aid kit with medicines
has been maintained at each construction site.
(iii) Tree loss and plantation work. Due to the space constraints in some schools,
felling of trees was unavoidable. During site visit, it was observed that some of the
trees were felled during construction. Contractors and SMCs were advised to protect
the trees and avoid the felling of trees as far as possible. Contractor and SMC both
were advised to plant trees within the school premises and submit the list of plants
for plantation.
Till the reporting period in few schools in Ramechhap, Sindhuli and Kavreplanchowk,
Bhaktapur and Sindhupalchowk district plantation has been done. Among them
Kavre Palanchok district plantation work is noteworthy. The detail of plantation is presented in Annex-2.
(iv) Camp site management. Drinking water and toilet facilities were provided to the workers. Temporary toilets were constructed for the workers, in some sites, workers were using the existing school toilets. Most of the workers are from outside the village. Therefore, contractors have built temporary camps for the workers near the construction sites as required by the labors. Some contractors have rented local house for workers in the vicinities. Workers use LPG as well as firewood for cooking at camp site.
(v) Signboard placing. Contractors have placed sign boards for contract information and safety concerns at the construction sites.
(vi) Grievance redress mechanism. GRM mechanism has been established in all sub-
projects. So far, 3 grievances have been reported from Kathamndu district and one
from Okhalandhunga district. The grievance, at Sitapaila SS, Package no-2
Kathmandu district was about the safety concern due to deep excavation of
foundation for school building and impact to adjacent local houses was resolved at
local level. Similarly, another grievance was raised in Ratna Rajya School Package
no-2, Kathmandu district where there is a historic temple on the east side of the
school premises which is being worshiped by local community since long time and
local devotees are opposing the construction work. Similarly another grievance was
raised in August 2018. Okhalandhunga district at Rumjatar SS by Civil Aviation
Authority for the construction of 3 storey building (CR-12 Block) adjacent to the
Rumjatar airport, pursuing the building Bye law of Civil Aviation Authority. The
grievance was addressed, the school building was redesigned to be 2 storey to
comply with the Building Bye Law requirements of Civil Aviation Authority. Similarly
grievance was raised by SMC at Sahayogi SS, Gokarna in Kathmandu district
regarding the revised master plan of the erection of ‘5C8’ building block. A tripartite meeting was held on July 3 at CLPIU-E in presence of the representatives of CLPIU-
E, SMC and DSC and agreed to revise the master plan as proposed by DSC. In
February, grievance was raised at Sindhupalchowk district, Surya Kiran Primary
Environmental Monitoring Report January-June 2019
69
school by a local due to the land cutting and dumping of soil. Addressing the
grievance, gabion wall were proposed at the required site. Grievance detail is
presented in Annex-3.
(vii) Spoil management. Spoil disposal sites have been identified and are being managed in specified disposal sites as far as possible. The spoil is disposed at location where there is the requirement of the fill material as requested by community.
(viii) Air and water qualities. Air quality within the reconstruction site has been maintained in tolerable level as the reconstruction works of schools generate insignificant amount of dust. Similarly, water quality is not degraded since spoils are managed within the site and stabilized by reinstating natural drainage system.
(ix) Slope stability. The master planning of the school is prepared conserving natural
land scape of the site. In some unavoidable cases, earthwork in excavation and
filling were carried out considering self-slope stabilization of the soil in uphill and
downhill of the site with least requirement of breast and retaining walls. Spoils were
managed within the site by filling them on the area with gentle contour of the site as
far as possible. Retaining wall and breast are provided as per the site conditions.
(x) EMP implementation, monitoring, reporting and field visit. Environmental monitoring format has been sent to districts as given in Annex 4. Environmental monitoring is also done by the Environment Expert including other Expert Team during field visit. Table 2 gives the list of sub projects visited by environment expert.
(xi) Strom water drainage. Drainage are designed and constructed specially for the
storm water management. In Schools as Chandeshwori PS Sindhupalchowk, and
Sindhu Paurana Gaoun SS, Sindhupalchowk,Jansewa Kavre, Prakashodya SS
Sindhuli, Yassam SS, Okhalandhunga strom water drainage management has been
done as per the requirement.
Table 11: Monitoring Reporting and Field Visit
S. N. Date District Subproject Remarks 1 13 Jan 2019 Kathmandu Sarada SS, Patab, Naglebhare 2 30 Jan 2019 Kathmandu Jana Sewa SS and Narayan Jan
SS
3 31 Jan 2019 Kathmandu Zanodya SS, Sita Pila SS, Nepal Yubak SS and Geetamata SS
4 15 March 2019 Kavre Palanchok Sanjivani SS, (Model School) 5 16 March 2019 Kavre Palanchok Shankheswor Mahalaxmi SS 6 2 June 2019 Kathmandu Gyanodya SS 7 3 June 2019 Kathmandu Nagarjun Thulo patel SS
7. INSTITUTIONAL ARRANGEMETS The executing agency is the NRA. The implementing agency is CLPIU-E. Each DLPIU-E has designated a focal person for environmental safeguards. The focal person has been assisted in conducting environmental assessment, and implementation of EMPs and compliance
Environmental Monitoring Report January-June 2019
70
monitoring by projects consultants. Thus, the government has sufficient capacity in implementing ADB requirements and strengthening of capacity.
8. ISSUES AND CORRECTIVE ACTION The contractors and DLPIUs should apply following corrective measures:
Table 3. Issues and Way Forward
S.N. Issues Way Forward
1 Site clearance and plantation Focus on the clearance of the construction site and plantation of ornamental, medicinal and other plants in school premises before handover.
2 Implementation of bioengineering work for slope protection and promoting plantation at land slide areas
Construction of drainage and plantation of appropriate vegetation over the slope for landslide and slope stability.
3 Spoil disposal management Spoil were disposed and managed as requirements.
4 Implementation of Environmental Management Plans
Monitor the activities as per approved EMPs status complied with,
9. MAJOR ITEMS FOCUSED FOR NEXT REPORT DSC will monitor and supervise the schools handover, drainage management, and bioengineering work in the slope areas, site clearance and plantation work in the school
premises sites are the major items focused for next report.
i.
Environmental Monitoring Report January-June 2019
72
Annex-1; Attachment 1; Environmental Safeguards Planning Status
Package no
Name of Project or Subproject
Environmental
screening
is carrie
d out? (Yes
or No)
Environme
nt category of
the projec
t / subproject approved
(A/B/C/FI)
DDR
with EMP is prepared (Yes/No)
EARF is
prepared (if
applicable) (Yes/No)
ADB approved DDR with EMP (Yes / Under
Review / Not Yet
Due/Over Due)
Government approv
ed EIA/IEE with EMP (Yes / Under Review
/ Not Yet
Submitted)
Safeguard monitoring and coordination mechanism established (Yes/No)
GRC is established (Yes/No)
Automated
safeguard
monitoring
system prepared (Yes/Planned/NA)
EMP cost is include
d in BOQ as individ
ual safeguard item (Yes/No
)
Remarks
Safeguarrd Unit
estab at EA with Focal
Person
Safeguarrd Unit
estab at IA with
Focal Perso
n
Safeguard monitoring
checklist
prepared
Contractor
prepared
SEMP and
approved by
Engineer
Contractor
mobilize
d safeguar
d assurance
staff
K-1 Kalika SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Jaya Sarswati SS Yes C Yes Yes Yes Yes Yes Yes Yes Yes No DDR submitted
Kalika Devi PS Yes C Yes Yes Yes Yes Yes Yes Yes Yes No DDR submitted
K-2 Janta PS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Khadgeshwari SS Yes C Yes Yes Yes Yes Yes Yes Yes Yes No DDR submitted
Mahankal PS Yes C Yes Yes Yes Yes Yes Yes Yes Yes No DDR submitted
Raktkali PS Yes C Yes Yes Yes Yes Yes Yes Yes Yes No DDR submitted
Seti Devi PS Yes C Yes Yes Yes Yes Yes Yes Yes Yes No DDR submitted
K-3 Jansewa PS Yes C Yes Yes Yes Yes Yes Yes Yes Yes No DDR submitted
Jana jagriti PS Yes C Yes Yes Yes Yes Yes Yes Yes Yes No DDR submitted
Mahankal PS, Tukucha
Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
K-4 Arunodya SS Yes C Yes Yes Yes Yes Yes Yes Yes Yes No DDR submitted Saraswati SS Yes C Yes Yes Yes Yes Yes Yes Yes Yes No DDR submitted
Srinjansil janta Yes C Yes Yes Yes Yes Yes Yes Yes Yes No DDR submitted
K-5
Bagdevi SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Environmental Monitoring Report January-June 2019
73
Shankeshwor SS Mahalaxmi
Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Satmul SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
K-6
Baluwa SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Mahakali SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Prakash HS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Radha Krishna SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Setidevi SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
K-7
Prabha SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Sanjivani HS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Kaliaka HS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Srinjansil janta SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
S-1
Dibya Sishushyhar PS
Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Environmental Monitoring Report January-June 2019
74
Jaya Ganesh PS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Harisidhi PS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Stakanya PS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
S-2
Bhimsen PS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Kalika PS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Jalpaa Devi PS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Janajaagraran PS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
S-3
B.P Smriti PS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Shivs Shankareshwar
Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Loktanta PS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
S-4
Bal Shikha SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Dakshinkali SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Environmental Monitoring Report January-June 2019
75
Kalika Devi SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
S-5
BagBhairab SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
S-6
Krishna Ratna Ganga SS
Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
S-7
GolmaDevi SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
SetiDevi Sharada SS
Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
S-8
Krishna SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Haibung Mahadevsthan SS
Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Sindhupuranogaon SS
Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Chhetrapaleshwori SS
Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
S-9
Kalika Devi SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
S-11
Koldaung Devi SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Kalika SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Environmental Monitoring Report January-June 2019
76
Mahendraodaya SS
Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
S-12
Siddhi Kamala Devi
Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Kamala Devi Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Simpaleshwori SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
S-13
Selang SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
S-14
Thangpaldhap SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
R-1
Jhatteshwor SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Nawadarsan SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Nag Kanya SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
R-2
Rudrakshyashowr SS
Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Bhimeshwor Prasun Kandel SS
Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Bhairavi SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Environmental Monitoring Report January-June 2019
77
R-3
Siddheshwor HSS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
R-4
Siddheshwor SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Seti Devi SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Bishnu Janajyoti SS
Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Kalika SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
R-5
Bhimeshwor SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Khakling SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Khadadevi SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Kharpanee SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
O-1
Baljyoti SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Chautara SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Manakamana SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
O-2
Kalika SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Environmental Monitoring Report January-June 2019
78
Kuibhir SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Yasam SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
O-3
Golma Devi SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Gyanjyoti SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
O-4
Bigutar HS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Punyamata SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Jantarkhani Ss Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Saraswati SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
O-5
Gyanprakash SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Sunkeshari SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Narmadeshwor SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
O-6
Prabuddha HSS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Environmental Monitoring Report January-June 2019
79
Shivaduti SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
O-7
Baruneshwor SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Rumjatar SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
S-1
Hirathumki SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Prakasodya SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Chandibhajyang SS
Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
S-2
kusheshwor Bidya Pith
Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Shree SS, Kholagaun
Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Mahakali SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
S-3
Baruneshwar SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Janta Higher SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Jana Jagriti SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Environmental Monitoring Report January-June 2019
80
Sindhure SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
S-4
Kamala SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Janajagriti, SS Bhiman
Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Uchha SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
K-1
Jana Sewa HSS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Kunchipwakal SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Gyanodaya SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Viswa Niketan,SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
K-2
Geeta Mata SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Padmodaya SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Sitapilla SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Ratna Rajya SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Environmental Monitoring Report January-June 2019
81
K-3
Nepal Yubak SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
D-1
Baiteshwori SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Nilkantheswor SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Sitapila SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Tribhuvan SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
D-2
Bhangeri SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Dhungeswori SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Garjandhunga SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Kalika SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
D-3
Birendra SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Heem Bharati SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Kallabari SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Environmental Monitoring Report January-June 2019
82
Surke SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
D-4
Himalaya SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Nikobhume SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Amar SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Golmashwor SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
D-5
Kalika SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Dad Kharkha SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Laxmi Uchha SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
D-6
Bhumi Gumba SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Haleshwor SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
B-1
Mahendragram SS
Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
USAID Schools
K-1
Kalika SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Environmental Monitoring Report January-June 2019
83
Janajagaran PS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Ganga Devi PS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Mahaadev PS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
S-1
Chandeshwari PS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Jalpa Devi PS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Namuna Sunkhani PS
Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Panchakanya PS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Shree PS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Surya Kiran PS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
R-1
Sharada Sanskrit HS
Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Chandeshwori HS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Sitala Devi SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Environmental Monitoring Report January-June 2019
84
R-2
Prayageshwor HS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Gauri Shankar SS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
K-1
Sahayogi HS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Nagarjun HS Yes C Yes Yes Yes Yes
Yes Yes
Yes Yes No DDR submitted
Note: EIA- Environmental Impact Assessment; IEE- Initial Environmental Examination; DDR- Due Diligence Report; EMP- Environmental Management Plan;
GRC- Grievance Redress Committee; BOQ- Bill of Quantity
Environmental Monitoring Report January-June 2019
85
Annex-1; Attachment 2: Environmental Safeguards Implementation Status
Package no.
Name of Subproject
Compliance to Environmental Management Plan* Grievances
Corrective Action Plans are prepared
and co
mplied
Env
compliance reporting is
maintained (Y/N)
Safeguard orientation program to stakeholders
Remarks
Physical Biological Socio-economic
Spoil Manageme
nt compliance
Landslide
protection
with Bio-eng
g
Drainage
Manageme
nt
Others as per
EMP
Plantation Firewood is used
for cooking
and heating (Y/N
)
Others as per EMP
(specify)
Occupational Health and Safety Others as per EMP (specify)
Nos of
grievances docu
mented
No of grievance
s resolved
No of grievances
under
processing
Target
Achieved
Safety
Gears
are sufficien
t and used
(Y/N)
Labors are insur
ed (Y/N)
Safety Protocol functioning (Y/N)
Incidence of
majotr injury of
fatal accident (no and status)
Labor and
work camps
are healthy and have
sanitary
facilities
(Y/N)
K-1 Kalika SS Complied
Complied
Complied
No Yes
Yes
Yes
No
Yes Yes Handed over
Jaya Sarswati SS
Complied
Complied
Complied
No Yes
Yes
Yes
No
Yes Yes Handed over
Kali Devi PS Complied
Complied
Complied 300
No Yes
Yes
Yes
No
Yes Yes Handed over
K-2 Janta PS Complied
Complied
Complied 160
No Yes
Yes
Yes
No
Yes Yes Handed over
Khadgeshwari SS
Complied
Complied
Complied
No
Yes Yes
Yes
No
Yes Yes Handed over
Mahankal PS
Complied
Complied
Complied 40
No Yes
Yes
Yes
No
Yes Yes Handed over
Environmental Monitoring Report January-June 2019
86
Raktkali PS Complied
Complied
Complied
No Yes
Yes
Yes
No
Yes Yes Handed over
Seti Devi PS Complied
Complied
Complied
No Yes
Yes
Yes
No
Yes Yes Handed over
K-3 Jansewa PS Complied
Complied
Complied
Yes Yes
Yes
Yes
No
Yes Yes Handed over
Jana jagriti PS
Complied
Complied
Complied
No Yes
Yes
Yes
No
Yes Yes Handed over
Mahankal PS, Tukucha
Complied
Complied
Complied
Yes Yes
Yes
Yes
No
Yes Yes Handed over
K-4 Arunodya SS
Complied
Complied
Complied 100
No Yes
Yes
Yes
No
Yes Yes Handed over
Saraswati SS
Complied
Complied
Complied 150
Yes Yes
Yes
Yes
No
Yes Yes Handed over
Srinjansil janta
Complied
Complied
Complied 100
Yes Yes
Yes
Yes
No
Yes Yes Ready for handover
K-5 Bagdevi SS Complied
Complied
Complied 100
Yes Yes
Yes
Yes
No
Yes Yes Handed over
Shankeshwor SS Mahalaxmi
Complied
Complied
Complied
100 Yes
Yes Yes
Yes
No
Yes Yes
Ready hand over
Satmul SS Complied
Complied
Complied 100
Yes Yes
Yes
Yes
No
Yes Yes Handed over
K-6 Baluwa SS Complied
Complied
Complied 100
Yes Yes
Yes
Yes
No
Yes Yes Handed over
Mahakali SS
Complied
Complied
Complied 100
Yes Yes
Yes
Yes
No
Yes Yes Handed over
Prakash HS Complied
Complied
Complied 150
No Yes
Yes
Yes
No
Yes Yes Handed over
Radha Krishna SS
Complied
Complied
Complied 100
No Yes
Yes
Yes
No
Yes Yes Handed over
Setidevi SS Complied
Complied
Complied 100
No Yes
Yes
Yes
No
Yes Yes Ready for hand over
Environmental Monitoring Report January-June 2019
87
K-7 Prabha Ss Complied
Complied
Complied 150
No Yes
Yes
Yes
No
Yes Yes Handed over
Sanjivani HS Complied
Complied
Complied 134
No Yes
Yes
Yes
No
Yes Yes Handed over
Kaliaka HS Complied
Complied
Complied
75
No
Yes
Yes
Yes
No
Yes Yes
Under construction under construction
S-1
Dibya Sishushyhar PS
Complied
Complied
Complied
Yes
Yes Yes
Yes
No
Yes Yes Handed over
Jaya Ganesh PS
Complied
Complied
Complied
Yes Yes
Yes
Yes
No
Yes Yes Handed over
Harisidhi PS
Complied
Complied
Complied
Yes Yes
Yes
Yes
No
Yes Yes Under Construction
Stakanya PS
Complied
Complied
Complied
Yes Yes
Yes
Yes
No
Yes Yes Under Construction
S-2 Bhimsen PS
Complied
Complied
Complied
Yes Yes
Yes
Yes
No
Yes Yes Handed over
Kalika PS
Complied
Complied
Complied
Yes Yes
Yes
Yes
No
Yes Yes Under Construction
Jalpaa Devi PS
Complied
Complied
Complied
Yes Yes
Yes
Yes
No
Yes Yes Under Construction
Janajaagraran PS
Complied
Complied
Complied
Yes
Yes Yes
Yes
No
Yes Yes
Under Construction
S-3
B.P Smriti PS
Complied
Complied
Complied
Yes Yes
Yes
Yes
No
Yes Yes Under Construction
Shivs Shankareshwar
Complied
Complied
Complied
Yes
Yes Yes
Yes
No
Yes Yes
Under Construction
Loktanta PS
Complied
Complied
Complied
No Yes
Yes
Yes
No
Yes Yes Handed over
S-4
Bal Shikha SS
Complied
Complied
Complied
No Yes
Yes
Yes
NO
Yes Yes Handed over
Environmental Monitoring Report January-June 2019
88
Dakshinkali SS
Complied
Complied
Complied
No Yes
Yes
Yes
N0
Yes Yes Under Construction
Kalika Devi SS
Complied
Complied
Complied
No Yes
Yes
Yes
N0
Yes Yes Under Construction
S-5
BagBhairab SS
Complied
Complied
Complied
No Yes
Yes
Yes
N0
Yes Yes Under Construction
S-6
Krishna Ratna Ganga SS
Complied
Complied
Complied
No
Yes Yes
Yes
N0
Yes Yes
Under Construction
S-7
GolmaDevi SS
Complied
Complied
Complied
No Yes
Yes
Yes
N0
Yes Yes Under Construction
SetiDevi Sharada SS
Complied
Complied
Complied
No Yes
Yes
Yes
N0
Yes Yes Under Construction
S-8 Krishna SS
Complied
Complied
Complied
Yes Yes
Yes
Yes
N0
Yes Yes Under Construction
Haibung Mahadevsthan SS
Complied
Complied
Complied
Yes
Yes Yes
Yes
No
Yes Yes Handed over
Chhetrapaleshwori SS
Complied
Complied
Complied
No
Yes Yes
Yes
No
Yes Yes Handed over
S-9
Kalika Devi SS
Complied
Complied
Complied
No Yes
Yes
Yes
No
Yes Yes Under Construction
S-11
Koldaung Devi SS
Complied
Complied
Complied
No Yes
Yes
Yes
No
Yes Yes Under Construction
Kalika SS
Complied
Complied
Complied
No Yes
Yes
Yes
No
Yes Yes Under Construction
Mahendraodaya SS
Complied
Complied
Complied
No Yes
Yes
Yes
No
Yes Yes Under Construction
S-12
Siddhi Kamala Devi
Complied
Complied
Complied
Yes Yes
Yes
Yes
No
Yes Yes Under Construction
Kamala Devi
Complied
Complied
Complied
Yes Yes
Yes
Yes
No
Yes Yes Under Construction
Simpaleshwori SS
Complied
Complied
Complied
Yes
Yes Yes
Yes
No
Yes Yes Under Construction
Environmental Monitoring Report January-June 2019
89
S-13 Selang SS
Complied
Complied
Complied
Yes
Yes Yes
Yes
No
Yes Yes Under Construction
S-14
Thangpaldhap SS
Complied
Complied
Complied 60
Yes
Yes Yes
Yes
No
Yes Yes Handed over
R-1
Jhatteshwor SS
Complied
Complied
Complied 125
No
Yes Yes
Yes
No
Yes Yes Handed over
Nawadarsan SS
Complied
Complied
Complied
No
Yes Yes
Yes
No
Yes Yes Handed over
Nag Kanya SS
Complied
Complied
Complied
No
Yes Yes
Yes
No
Yes Yes Handed over
R-2
Rudrakshyashowr SS
Complied
Complied
Complied 507
No
Yes Yes
Yes
No
Yes Yes Handed over
Bhimeshwor Prasun Kandel SS
Complied
Complied
Complied
202 No
Yes Yes
Yes
No
Yes Yes Handed over
Shree Bhairavi SS
Complied
Complied
Complied 102
No
Yes Yes
Yes
No
Yes Yes Handed over
R-3
Siddheshwor HSS
Complied
Complied
Complied
No
Yes Yes
Yes
No
Yes Yes Handed over
R-4
Siddheshwor SS
Complied
Complied
Complied
No
Yes Yes
Yes
No
Yes Yes Handed over
Seti Devi SS
Complied
Complied
Complied
No
Yes Yes
Yes
No
Yes Yes Handed over
Bishnu Janajyoti SS
Complied
Complied
Complied
No
Yes Yes
Yes
No
Yes Yes Under Construction
Kalika SS
Complied
Complied
Complied
No
Yes Yes
Yes
No
Yes Yes Handed over
R-5
Bhimeshwor SS
Complied
Complied
Complied 202
No
Yes Yes
Yes
No
Yes Yes Handed over
Khakling SS
Complied
Complied
Complied
No
Yes Yes
Yes
No
Yes Yes Handed over
Khadadevi SS
Complied
Complied
Complied
Yes
Yes Yes
Yes
No
Yes Yes Handed over
Environmental Monitoring Report January-June 2019
90
Kharpanee SS
Complied
Complied
Complied
Yes
Yes Yes
Yes
No
Yes Yes Handed over
O-1 Baljyoti SS
Complied
Complied
Complied
Yes
Yes Yes
Yes
No
Yes Yes Handed over
Chautara SS
Complied
Complied
Complied
Yes
Yes Yes
Yes
No
Yes Yes Handed over
Manakamana SS
Complied
Complied
Complied
Yes
Yes Yes
Yes
No
Yes Yes Handed over
O-2 Kalika SS
Complied
Complied
Complied
No
Yes Yes
Yes
No
Yes Yes Under Construction
Kuibhir SS
Complied
Complied
Complied
No
Yes Yes
Yes
No
Yes Yes Handed over
Yasam SS
Complied
Complied
Complied
No
Yes Yes
Yes
No
Yes Yes Handed over
O-3
Golma Devi SS
Complied
Complied
Complied
Yes
Yes Yes
Yes
No
Yes Yes Under Construction
Gyanjyoti SS
Complied
Complied
Complied
Yes
Yes Yes
Yes
No
Yes Yes Under Construction
O-4 Bigutar HS
Complied
Complied
Complied
Yes
Yes Yes
Yes
No
Yes Yes Under Construction
Punyamata SS
Complied
Complied
Complied
Yes
Yes Yes
Yes
No
Yes Yes Under Construction
Jantarkhani Ss
Complied
Complied
Complied
Yes
Yes Yes
Yes
No
Yes Yes Under Construction
Saraswati SS
Complied
Complied
Complied
No
Yes Yes
Yes
No
Yes Yes Handed over
O-5
Gyanprakash SS
Complied
Complied
Complied
No
Yes Yes
Yes
No
Yes Yes Under Construction
Sunkeshari SS
Complied
Complied
Complied
No
Yes Yes
Yes
No
Yes Yes Under Construction
Narmadeshwor SS
Complied
Complied
Complied
No
Yes Yes
Yes
No
Yes Yes Under construction
O-6
Prabuddha HSS
Complied
Complied
Complied
No
Yes Yes
Yes
No
Yes Yes Under construction
Environmental Monitoring Report January-June 2019
91
Shivaduti SS
Complied
Complied
Complied
No
Yes Yes
Yes
No
Yes Yes Under construction
O-7
Baruneshwor SS
Complied
Complied
Complied
Yes
Yes Yes
Yes
No
Yes Yes Under construction
Rumjatar SS
Complied
Complied
Complied
No
Yes Yes
Yes
Yes
Resloved
Yes Yes Under construction
S-1
Hirathumki SS
Complied
Complied
Complied
No
Yes Yes
Yes
No
Yes Yes Handed over
Prakasodya SS
Complied
Complied
Complied
Yes
Yes Yes
Yes
No
Yes Yes Under construction
Chandibhajyang SS
Complied
Complied
Complied
No
Yes Yes
Yes
No
Yes Yes Under construction
S-2
Kusheshwor Bidya Pith
Complied
Complied
Complied
Yes
Yes Yes
Yes
No
Yes Yes Handed over
Shree SS, Kholagaun
Complied
Complied
Complied
No
Yes Yes
Yes
No
Yes Yes Under construction
Mahakali SS
Complied
Complied
Complied
Yes
Yes Yes
Yes
No
Yes Yes Handed over
S-3
Baruneshwar SS
Complied
Complied
Complied
Yes
Yes Yes
Yes
No
Yes Yes Handed over
Janta Higher SS
Complied
Complied
Complied 150
Yes
Yes Yes
Yes
No
Yes Yes Handed over
Jana Jagriti SS
Complied
Complied
Complied 50
Yes
Yes Yes
Yes
No
Yes Yes Handed over
Shree SS, Sindhure
Complied
Complied
Complied
Yes
Yes Yes
Yes
No
Yes Yes Handed over
S-4 Kamala SS
Complied
Complied
Complied 50
Yes
Yes Yes
Yes
No
Handed over
Janajagriti, SS Bhiman
Complied
Complied
Complied
No
Yes Yes
Yes
No
Yes Yes Handed over
Uchha SS
Complied
Complied
Complied 70
No
Yes Yes
Yes
No
Yes Yes Handed over
Environmental Monitoring Report January-June 2019
92
K-1
Jana Sewa HSS
Complied
Complied
Complied 24
No
Yes Yes
Yes
No
Yes Yes Under construction
Sahayogi HS
Complied
Complied
Complied
No
Yes Yes
Yes
No
Yes Yes Under construction
Nagarjun SS
Complied
Complied
Complied
No
Yes Yes
Yes
Yes
Yes Yes Under construction
Kunchipwakal SS
Complied
Complied
Complied
No
Yes Yes
Yes
No
Yes Yes Under construction
Gyanodaya SS
Complied
Complied
Complied
No
Yes
Yes
No
Yes Yes Handed over
Viswa Niketan,SS
Complied
Complied
Complied
No
Yes Yes
Yes
No
Yes Yes Under construction
K-2
Geeta Mata SS
Complied
Complied
Complied
No
Yes Yes
Yes
No
Yes Yes Under construction
Padmodaya SS
Complied
Complied
Complied
No
Yes Yes
Yes
No
Yes Yes Handed over
Sitapilla SS
Complied
Complied
Complied
No
Yes Yes
Yes
Yes
Resolved
Yes Yes Under construction
Ratna Rajya SS
Complied
Complied
Complied
No
Yes Yes
Yes
Yes
Resolved
Yes Yes Handed over
K-3
Nepal Yubak SS
Complied
Complied
Complied
No
Yes Yes
Yes
Yes
Yes Yes Under construction
D-1
Baiteshwori SS
Complied
Complied
Complied
Yes
Yes Yes
Yes
No
Yes Yes Handed over
Nilkantheswor SS
Complied
Complied
Complied
Yes
Yes Yes
Yes
No
Yes Yes Handed over
Sitapila SS
Complied
Complied
Complied
Yes
Yes Yes
Yes
No
Yes Yes Handed over
Tribhuvan SS
Complied
Complied
Complied
Yes
Yes Yes
Yes
No
Yes Yes Under construction
D-2 Bhangeri SS
Complied
Complied
Complied
Yes
Yes Yes
Yes
No
Yes Yes Under construction
Environmental Monitoring Report January-June 2019
93
Dhungeswori SS
Complied
Complied
Complied
Yes
Yes Yes
Yes
No
Yes Yes Under construction
Garjandhunga SS
Complied
Complied
Complied
Yes
Yes Yes
Yes
No
Yes Yes Under construction
Kalika SS
Complied
Complied
Complied
Yes
Yes Yes
Yes
No
Yes Yes Under construction
D-3 Birendra SS
Complied
Complied
Complied
No
Yes Yes
Yes
No
Yes Yes Under construction
Heem Bharati SS
Complied
Complied
Complied
No
Yes Yes
Yes
No
Yes Yes Handed over
Kallabari SS
Complied
Complied
Complied
No
Yes Yes
Yes
No
Yes Yes Under construction
Surke SS
Complied
Complied
Complied
Yes
Yes Yes
Yes
No
Yes Yes Handed over
D-4
Himalaya SS
Complied
Complied
Complied
Yes
Yes Yes
Yes
No
Yes Yes Under construction
Nikobhume SS
Complied
Complied
Complied
Yes
Yes Yes
Yes
No
Yes Yes Under construction
Amar SS
Complied
Complied
Complied
Yes
Yes Yes
Yes
No
Yes Yes Under construction
Golmashwor SS
Complied
Complied
Complied
Yes
Yes Yes
Yes
No
Yes Yes Under construction
D-5 Kalika SS
Complied
Complied
Complied
Yes
Yes Yes
Yes
No
Yes Yes Under construction
Dad Kharkha SS
Complied
Complied
Complied
Yes
Yes Yes
Yes
No
Yes Yes Under construction
Laxmi Uchha SS
Complied
Complied
Complied
Yes
Yes Yes
Yes
No
Yes Yes Under construction
D-6
Bhumi Gumba SS
Complied
Complied
Complied
Yes
Yes Yes
Yes
No
Yes Yes Handed over
Haleshwor SS
Complied
Complied
Complied
No
Yes Yes
Yes
No
Yes Yes Handed over
B-1
Mahendragram SS
Complied
Complied
Complied 60
No
Yes Yes
Yes
No
Yes Yes Handed over
Environmental Monitoring Report January-June 2019
94
Kalika SS
Complied
Complied
Complied 45
No
Yes Yes
Yes
No
Yes Yes Handed over
USAID Schools
k-1
Janjagaran PS
Complied
Complied
Complied
No
Yes Yes
Yes
No
Yes Yes Handed over
Gangadevi PS
Complied
Complied
Complied
No
Yes Yes
Yes
No
Yes Yes Handed over
Mahadev PS
Complied
Complied
Complied
No
Yes Yes
Yes
No
Yes Yes Handed over
S-1
Chandeshwari PS
Complied
Complied
Complied
No
Yes Yes
Yes
No
Yes Yes Handed over
Jalpa Devi PS
Complied
Complied
Complied
Yes
Yes Yes
Yes
No
Yes Yes Handed over
Namuna Sunkhani PS
Complied
Complied
Complied
No
Yes Yes
Yes
No
Yes Yes Handed over
Panchakanya PS, Tinghare
Complied
Complied
Complied
No
Yes Yes
Yes
No
Yes Yes Handed over
Panchkanya PS, Ghumthang
Complied
Complied
Complied
No
Yes Yes
Yes
No
Yes Yes Handed over
Shree Primary School
Complied
Complied
Complied
Yes
Yes Yes
Yes
No
Yes Yes
Under construction
Suryakiran PS
Complied
Complied
Complied
Yes
Yes Yes
Yes
Yes
Resolved
Yes Yes Under construction
R-1
Sharada Sanskrit HS
Complied
Complied
Complied 350
Yes
Yes Yes
Yes
No
Yes Yes Handed over
Chandeshwori HS
Complied
Complied
Complied
No
Yes Yes
Yes
No
Yes Yes Handed over
Sitala Devi
Complied
Complied
Complied 320
No
Yes Yes
Yes
No
Yes Yes Handed over
R-2
Prayageshwor HS
Complied
Complied
Complied
No
Yes yes
Yes
No
Yes Yes Handed over
Environmental Monitoring Report January-June 2019
95
Gaurishankar HS
Complied
Complied
Complied
400 Yes
Yes Yes
Yes
No
Yes Yes Handed over
K-1
Sahayogi HS
Complied
Complied
Complied
No
Yes Yes
Yes
Yes
Resolved
Yes Yes Under construction
Nagarjun Thulogaon HS
Complied
Complied
Complied
No
Yes Yes
Yes
No
Yes Yes
Under construction
Environmental Monitoring Report January-June 2019
96
Annex-2: Plantation details
S.N Package District Sub-project No of plants
Plant species Status
1 K-4 Kavre Saraswati SS 150 Handed over
2 K-1 Kavre Kali Devi PS, Naubise 300 Handed over
3 K-2 Kavre Janta PS, Mathurapti 160 Handed over
4 K-2 Kavre Arunodya SS 100 Handed over
5 K-2 Kavre Mahankal PS, Methinkot 40 Handed over
6 K-6 Kavre Mahakali SS 100 Handed over
7 K-2 Kavre Radhakrishna SS 100 Handed over
8 K-2 Kavre Seti Devi PS, Kanpur 100 Handed over
9 K-6 Kavre Radha Krishna SS 100 Handed over
10 K-6 Kavre Prakash SS 150 Handed over
11 K-5
Kavre Shankeshwor mahalaxmi SS
100 Ready hand
over 12
K-7 Kavre
Sanjiwani SS 134 Cycas palm, Phenox palm
Handed over
13 K-4
Kavre Srijansil janata SS 100
Ready for handover
14 K-5 Kavre Satmul SS 100 Handed over
15 K-7 Kavre Prabha SS 150 Handed over
16 K-7 Kavre Kalika SS 75 Handed over
17 K-6 Kavre Baluwa SS 100 Handed over
1 K-5 Kavre Bagdevi SS 100 Handed over
19 R-1 Ramechhap Nagkanya SS, Manthali 125 Handed over
20 R-1
Ramechhap Rudrakshyashowr SS, Bhatauli
507
Handed over
21 R-1
Ramechhap Bhimeshowr Prasun Kadel SS, Pakabas
202
Handed over
22 R-1 Ramechhap Bhairavi SS, Sunarpani 102 Handed over
23 R-1 (USAID)
Ramechhap Sarada Sanskrit HS, Babiyakharka
350 Dhupi, Tej Patta, Kapur, Nil kada
Handed over
24 R-2(USAID)
Ramechhap Prayageshwor HS, Pakarbas
520 Kapur, Dhupi, Nil Kada Kalki
Handed over
25 R-2 (USAID)
Ramechhap Gauri Shankar HS, Ramechhap
400 Rose, Chineya rose, Kapur, Kalaki
Handed over
26 R-1
Ramechhap Sitala Devi 320
Jaiphal, Tej patta, Walnut, Kalki,
Handed over
27 R-1 Ramechhap Jatteshwor SS, 125 Handed over
28 S-3 Sindhuli Janata SS, Sindhili 150 Handed over
29 S-3
Sindhuli Jan Jagriti, Viman Sindhuli
50 Handed over
30 S-4
Sindhuli Kamala SS 50
Coconut tree, Ashoka tree
Handed over
Environmental Monitoring Report January-June 2019
97
31 S-4 Sindhuli Uchha SS 70 Handed over
32 B-1 Bhaktapur Kalika SS, Nagarkot 42 Hedge Handed over
33 B-1 Bhaktapur Mahendrgram SS, Sudal 60 Hedge Handed over
34 S-14 Sindhupalchowk Thangpaldhang SS 60 Sallo, Dhupi Handed over
35 S-13 Sindhupalchowk Selang SS 45 Dhupi Handed over
36 K-1
Kathmandu Jan Sewa SS, Kritipur 34
Dhupi, Palm, Cycus, Rose
Under construction
Total 5,371
Plants - Scientific Name Tej Patta - Cinnamomum tamala Jaiphal - Myristica frangrans Rose - Rosa alba Chinese rose – Hibiscus rosa Walnut - Juglans regia Coconut tree- Cocos nucifera Ashoka tree - Saraca indica Dhupi - Cryptomeria japonica Palm- Arecaceae Cycas - Cycas revoluta
Environmental Monitoring Report January-June 2019
98
Annex-3: Status of Grievances related to Environmental Safeguard
SN Package District Sub Project Description of Grievance
Received Action taken Status
1 K-2 Kathmandu Sitapaila Secondary School Safety concern of two houses by local residence
Shear wall has been constructed and insurance of both the houses have been done
Resolved.
2
K-2 Kathmandu Ratna Rajya Secondary School
Temple management committee not providing the area for construction (local devotee)
Rounds of meeting with CLPIU, DLPIU, SMC and the local devotees held
Resolved
3 K-1 Kathmandu Sahayogi Secondary School Revised master plan Tripartite meeting(DSC,CLPIU,SMC)
Resolved
4 O-7 Okhalandhunga Rumjatar Secondary School Comply the building bye law
Redesigned the building Resolved
5 S- Sindhupalchowk Surya Kiran PS Land cutting and dumping of spoil
Gabion wall proposed Resolved
99
Annex-4: Monitoring Reporting Format (Environment Safeguard)
Reporting Period: ……………. District:…………………………. Name of Subproject (school) …………….…… Name of staff: ………………………………… Designation:………………………………………
SN Description Indicator
Present status
Remarks
Yes No
1 DDR Completed / ongoing / proposed
2 Awareness raising orientation trainingi
Number of events and participants
3a Stock piling and spoil disposal management
Spoil disposal management plan
Volume of safely disposed spoil (m3)
Remaining excavated materials (m3)
Spoil disposal work affecting public interest, locals and their properties
3b Toe walls for safe disposal of excavated/breast wall
Number of toe walls/breast walls constructed to manage spoil
4 Bioengineering works (Y/N)
If yes location
Type of measures taken
5 Dust emission Type of vehicle
Spray of water for suppressing dust emission (Y/N), if yes time interval
6 Noise pollution Vehicles and equipment's used fitted with silencer and maintained to keep noise at minimum levels(Y/N)
7 Water contamination Contamination of water supply or source (Y/N)
8
Strom water drainage management (Y/N)
Size / number
9
Campsite management
Supply of safe drinking water (Y/N)
Temporary toilets constructed in camp sites (Y/N)
Energy used for cooking (fuel wood, kerosene, LPG, electricity)
Proper management of sewerage and waste disposal(Y/N)
10 Construction wastes
Separation of waste disposal in biodegradable and non-biodegradable(Y/N)
Safe disposal of construction waste materials done (Y/N)
11 Storage management
Provision for leakage and spills in storage & service yards (Y/N)
Provision for safety measures like fire extinguisher (Y/N)
12 Plantation School premises / area nearby to school
No of plants
Environmental Monitoring Report January-June 2019
100
SN Description Indicator
Present status
Remarks
Yes No
13
Interruption of services (water, electricity, telephone etc.)
Protection/rehabilitation of services (Y/N), if yes give the name
14
Occupational health & safety
Number of safety gears provided (helmet, jackets, facemasks, goggles, boots, ear plugs, gloves)
Use of safety gears by workers (%)
First aid kit provided with medicines Y/N
Accidental insurance (no. of workers)
Type & number of accident occurred
Compensation to affected workers Y/N
Coordination with nearby health center (Y/N)
15 Informative/safety signboard & cautionary ribbons/barricades
Signboards erected Y/N, if yes no of sign boards, no of sign board
Location
Cautionary ribbons/barricades placed (Y/N)
16
Cleaning site after construction and disposing waste properly
Site cleaning after the construction works completed (Y/N)
17
Grievances received and addressed
Received number
Addressed number
18 Photographs Attached recent photographs
1
Environmental Monitoring Report January-June 2019
101
Annex 5: Photographs Showing Environmental and Safeguards issues
Nagarjun Thulo Patel SS Kathmandu district: Building block
Nagarjun Thulo Patel SS Kathmandu district: Retaining wall constructed
Gyanodya SS, Kathmandu district: Building block Gyanodya SS, Kathmandu district: Fire extinguisher for safety purpose.
Sanjivani Model School, Kavre Palanchok district. Building block and plantation work.
Saraswati School, Kavre Palanchok district: Building block
Environmental Monitoring Report January-June 2019
102
Information board at Jana Sewa SS, Kritipur Kathmandu
First Aid kit at Jan Sewa SS, Kritipur Kathmandu
Plantation at Jan Sewa SS, Kritipur Kathmandu district.
Jana Sewa SS, Kritipur, Kathmandu district: Plantation work
Environmental Monitoring Report January-June 2019
104
TABLE OF CONTENTS
1 Background ..................................................................................................... 105
2 Environmental Safeguards in EEAP ................................................................ 110
3 Overall Environmental Safeguard Status ......................................................... 114
4 Construction Approach .................................................................................... 114
5 Compliance Status with Environmental Covenants ......................................... 114
6. Institutional Arrangement ................................................................................. 114
6 Corrective actions and way forward ................................................................. 114
7 Major Items Focused for Next Report .............................................................. 116
List of Tables
Table 1: Overall Construction Status of Sub-Projects ............................................ 106
Table 2 : Overall Compliance Status of Safeguard Issues ..................................... 111
List of Figures
Figure 1: Map of Nepal showing the sub-projects in districts within EEAP……….109
Figure 2: Map of Nepal showing the sub-projects in districts within EEAP………..109
List of Appendices
Annex 1: Planning and implementing environmental safeguards activities
Annex 1.A: Status of Environmental Safeguard Planning Status
Annex 1.B: Environmental Safeguard Implementation Status
Annex 2: Environmental Safeguard Compliance Monitoring Format
Annex 3: Compliances with Loan Covenants
Annex 4: List of Tree Species proposed to be planted in the Building Premises
Annex 5: Photographs
105
1. Background
A magnitude 7.8 earthquake of shallow depth struck central Nepal with an epicenter
approximately 77 km northwest of Kathmandu on April 25th causing widespread destruction.
On May 12, a large aftershock of a magnitude 7.3 hit Nepal and caused further causalities and
damage. As of 3 June 2015, the reported casualties include: 8,702 deaths and 22,493 people
injured. According to the Post Disaster Needs Assessment (PDNA) undertaken jointly by the
Government and its development partners, the earthquakes have caused damages in the
order of $7 billion, equivalent to about 35% of the country’s gross domestic product.
Considering the scale of the disaster, a major recovery effort is required.
The Government of Nepal (GoN) has requested support from a number of development
partners, including the ADB, to address the immediate and medium term impacts of the
damage inflicted by the earthquake in Nepal. In response to this, ADB approved a $200 million
loan to finance the Earthquake Emergency Assistance Project (EEAP) approved on 24 June
2015. The project will support for four outputs which are: a) Output 1: Rebuilding of schools,
b) Output 2: Roads c) Output 3: District- Level Government Buildings, and d) Output 4:
Strengthening Resilience to Future Disasters. The EAAP is to be completed by 23rd June,
2019.
The National Reconstruction Authority is the project’s executing agency (NRA) on an interim
basis until the GON has established a new special purpose agency for the purpose of
coordinating and implementing the post-disaster reconstruction program. For output 3,
Ministry of Urban Development\Central Level Project Implementation Unit (MoUD \CLPIU) is
designated as an implementing agency for rebuilding of district level government buildings.
To implement the output 3 component, the Ministry of Urban Development has established a
Central Level Project Implementation Unit (CLPIU) based at Kathmandu and implementation
units at district level (DLPIUs). The CLPIU will be responsible for guiding and monitoring the
constructions of government building projects funded by ADB. The consultants will assist the
CLPIU and the DLPIUs. The consultants’ support include, among others, overall project
management, financial management, construction supervision and environmental monitoring.
CLPIU had engaged joint venture of TAEC-SILT-TSE to execute environmental monitoring of
the construction of various government office building projects in 11 earthquake affected
districts of Nepal namely Gorkha, Lamjung, Dhading, Nuwakot, Rasuwa, Kavrepalanchowk,
Sindhupalchowk, Dolakha, Sindhuli, Ramechap and Okhaldhunga. The overall construction
status of Sub-projects is presented in Table 1.
106
Table 1: Overall Construction Status of Sub-Projects
S.N Title of Contract No. Lot in Packa
ge
Contract Id. No. , (Lot in package)
Contract Signed on
Remarks
1. Sindhuli District
1.1 Construction of an integrated office building (District Attorney Office, District Postal Office, Division office of Department of Water Supply & Sanitation and DUDBC Division Office)
4 Single MoUD/CLPIU/Works/2022-023/NCB-05
28-Sep-16 Under construction
1.2 Construction of two Office Buildings (District Forest Office and Irrigation Division Office)
2 Single MoUD/CLPIU/Works/2072-073/NCB-06
25-May-17 Completed
1.3 Maintenance of four Office Buildings (Agriculture Development Office, Tuber Vegetable Development Center, Land Revenue Office and Chief District Officer's Quarter)
4 Single MoUD/CLPIU/Works/2072-073/NCB-07
11-Jun-17 Completed
2. Ramechap District
2.1 Construction of three office Buildings (District Water Supply & Sanitation Office, DUDBC Division Office and Chief District Officer's Quarter)
3 Single MoUD/CLPIU/Works/2072-073/NCB-08
3-Oct-16 Completed
2.2 Construction of One Office Building (Divisional Forest Office) 1 Single MoUD/CLPIU/Works/2072-073/NCB-09
31-May-17 Under Construction
2.3 Maintenance of 11 Office Buildings (Soil Conservation Office, Post Office, Treasury Comptroller Office, Agriculture Development Office, Irrigation Division Office, District Education Office, District Court Office, District Livestock Office, District Administration Office, District Attorney Office and Department of Water Supply and Sanitation Division Office)
11 Single MoUD/CLPIU/Works/2072-073/NCB-11
25-May-17 Completed
3. Dhading District
3.1 Construction of three office buildings (District Court Office, District Forest Office and Chief District Officer's Quarter)
3 Single MoUD/CLPIU/Works/2072-073/NCB-30
26-Sep-16 Under construction
3.2 Construction of three Office Buildings (DUDBC Division Office, District Post Office and District Agriculture Development Office)
3 Single MoUD/CLPIU/Works/2072-073/NCB-31
29-Dec-16 Under construction
3.3 Construction of 2 Office Buildings (District Attorney Office and District Technical Office)
2 Single MoUD/CLPIU/Works/2072-073/NCB-33
25-May-17 Under Construction
3.4 Maintenance of 4 Office Buildings (District Treasury Comptroller Office, Irrigation Division Office, District Small Cottage Office and CDO Office)
4 Single MoUD/CLPIU/Works/2072-073/NCB-32
28-Apr-17 Completed
4. Nuwakot District
Environmental Monitoring Report January-June 2019
107
S.N Title of Contract No. Lot in Packa
ge
Contract Id. No. , (Lot in package)
Contract Signed on
Remarks
4.1 Construction of Six Office Buildings (District Court Office, Department of Water Supply and Sanitation Division Office, District Soil Conservation Office, District Post Office, District Agriculture Development Office and District Education Office)
6 Single MoUD/CLPIU/Works/2072-073/NCB-23
2-Dec-16 Under construction
4.2 Maintenance of 8 office Buildings (Subtropical Horticulture Development Centre, District Forest Office, DUDBC Division Office, Fish Investigation Centre, Disaster Preventive Technical Centre, Road Division Office, District Small & Cottage Industry Office and Division Irrigation Office)
8 Single MOUD/CLPIU/Works/2072-073/NCB-24
27-Apr-17 Completed
5. Lamjung District
5.1 Construction of Four Office Buildings (DUDBC Division Office, Treasury Comptroller Office, Irrigation Division Office and National Investigation Office)
4 Single MoUD/CLPIU/Works/2072-073/NCB-37
3-Dec-16 Under construction
5.2 Maintenance of 5 Office Buildings (District Court Office, District Agriculture Office, District Administration Office, District Soil Conservation Office and Department of Water supply and Sanitation Office)
5 Single MoUD/CLPIU/Works/2072-073/NCB-38
19-Apr-17 Completed
6. Sindhupalchowk District
6.1 Construction of Three Office Building (Chief District Officer's Quarter, District Forest Office Annex Building and District Treasury Comptroller Office)
3 Single MoUD/CLPIU/Works/2072-073/NCB-16
29-Dec-16 Under construction
6.2 Construction of Four Office Buildings (District Soil Conservation Office, District Agriculture Office, District Livestock Office and District Judge Quarter)
4 Single MoUD/CLPIU/Works/2072-073/NCB-17
26-Mar-17 Under construction
6.3 Maintenance of 8 Office Building (District Administration Office, Women Development, DEO, District Treasury Comptroller Office, District Agriculture Development Office , District Attorney Office, DUDBC Division office & District Court)
8 Single MoUD/CLPIU/Works/2072-073/NCB-20
23-May-17 Completed
6.4 Construction of Five Office Buildings (Irrigation Development Division Office, District Election Office, DUDBC Division Office including Annex, National Investigation District Office and District Cottage & Small Industry Committee Office)
5 Single MoUD/CLPIU/Works/2072-073/NCB-18
30-June-17 Under Construction
7. Dolakha District
7.1 Construction of four Office Buildings (Irrigation Division Office, District Forest Office, Chief District Officer's Quarter with annex and Water Induced Disaster Management Division Office)
4 Single MoUD/CLPIU/Works/2072-073/NCB-12
26-Mar-17 Completed
8. Gorkha District
8.1 Construction of 5 Office Buildings (District Post Office, District Agriculture Development Office, National Investigation District Office, District Attorney Office & District Soil Conservation Office)
5 Single MoUD/CLPIU/Works/2072-073/NCB-34
21-May-17 Under construction
Environmental Monitoring Report January-June 2019
108
S.N Title of Contract No. Lot in Packa
ge
Contract Id. No. , (Lot in package)
Contract Signed on
Remarks
8.2 Maintenance of 4 Office Buildings (Department of Water Supply and Sanitation Division Office, Women Development Office, DUDBC Division Office and District Treasury Comptroller Office)
4 Single MoUD/CLPIU/Works/2072-073/NCB-36
12-May-17 Completed
8.3 Construction of District Court Office Building 1 Single MoUD/CLPIU/Works/2072-073/NCB-35
12-May-17 Under construction
9. Rasuwa District
9.1 Construction of 7 Office Buildings (Chief District Officer's Quarter, District Post Office, District Agriculture Development Office, Division Irrigation Office, District Livestock Development Office and Integrated Building of DUDBC Division Office and Department of Water Supply and Sanitation Division Office)
7 Single MoUD/CLPIU/Works/2072-073/NCB-27
23-May-17 Under construction
10. Kavrepalanchowk District
10.1
Maintenance of 7 Office Building (District Advocate Office, District Post Office, Irrigation Division Office, District Agriculture Development Office, DUDBC Division Office, District Treasury Comptroller Office & Land Revenue Office)
7 Single MoUD/CLPIU/Works/2072-073/NCB-22
30-Apr-17 Completed
11. Okhaldhunga District
11.1
Construction of five Office Buildings (District Soil Conservation Office, DWSS Division Office, National Investigation Office, District Livestock Service Office and District Attorney office)
5 Single MoUD/CLPIU/Works/2072-073/NCB-01
13 November, 2017
Under Construction
11.2
Repair/Retrofitting of 8 Government Office Buildings (District Livestock Office, Land Revenue Office, Irrigation Division Office, District Forest Office, Eastern Region Climate Field Office, Higher Court Office, District Court & DUDBC Division Office)
8 Single MoUD/CLPIU/Works/2072-073/NCB-02
- Under Construction
109
Figure 6: Map of Nepal showing the sub-projects in districts within EEAP
Figure 7: Map of Nepal showing the sub-projects in districts within EEAP
110
2. Environmental Safeguards in EEAP
Environmental assessment is essential to integrate environmental considerations into
development project in order to minimize adverse environmental impacts. EEAP falls in
category C project according to ADB Safeguard Policy Statement, 2009.
During the construction and rehabilitation of the building sub-projects, environmental
monitoring is an important tool to ensure the compliance of mitigation measures and
implementation of environmental management plan (EMP). Monthly, Quarterly and semi-
annual Environmental safeguard monitoring report have to be prepared on the basis of report received from DSC (District Supervision Consultant) team and environmental field visit carried
out by Environmental Safeguard Unit of CSE (Construction Supervision Consultant) recruited
by EEAP. Moreover, due diligence report has been prepared for the sub-projects.
Considering the progress status of construction of government buildings in 11 districts, the
contract has been awarded to the government buildings and they have started the construction
works. Generally, they have been implementing safeguard measures satisfactory. However,
trainings need to be conducted to the workers and supervision staffs regarding implementation of safeguard measures.
3. Overall Environmental Safeguard Status
The safeguard compliance status recorded during field observation (based on environmental safeguard compliance monitoring format as presented in Annex 2) and discussion with the
employees of project and contractor are enlisted as under:
111
Table 2: Overall Compliance Status of Safeguard Issues
SN Issue Compliance Status Remarks
1 Awareness raising/ Orientation training
Complied The construction workers as well as contractor were instructed regularly about the safety requirements in the sites
Both construction workers as well as the representatives of contractors has been provided with safety trainings and awareness regarding the benefit of applying safety measures in their works
2 Stockpiling and spoil disposal management
Moderately complied Majority of the generated spoil of excavated works has been systematically kept within the site but some amount of soil has been still dumped nearby stream bank (DUBDC Building, Lamjung) in spite of regular instruction to the contractor during every site visit. The spoil of the access road to DUDBC Building (Lamjung) needs to be properly managed as well to avoid dumping into the nearby stream.
3 Grievance redress mechanism
Not complied The project has not established Grievance redress committee. However, the supervision engineers (Resident Engineer and Assistant Engineer) have been instructed to address the grievances received if any. However, no grievances has been received in this period
4 Dust emission management
Not complied No provision of spraying of water for suppressing dust emission. Moreover, mask has not been provided to construction workers in majority of the sites.
Most of the vehicles carrying construction material have not been covered with tarpaulin or plastic sheets in some of the sites
5 Noise Pollution management
Complied The noise generation is limited to use of small equipment and machinery generating low noise No complaints has been received from the nearby community regarding construction noise
6 Camp site management
Moderately complied In some sites (DUBDC & DWSS Integrated of Rasuwa District, Soil Conservation Office of Gorkha District and Integrated Office Building of Sindhuli District), firewood is used for cooking instead of LPG and kerosene. However, LPG has been used by the construction workers in many sites
The labor residences have been haphazardly managed within the newly constructed buildings showing inhuman residential condition. The workers have not been provided with adequate warm living conditions.
The prevalence of communicable diseases was observed due to communal living condition of workers
Many of the construction camps and labor camps are deprived of safe drinking water facility. Filtration facility for drinking water has not practiced in many camp sites.
However, some construction workers have arranged their own residence in some of the construction sites (Lamjung District)
Mosquito nets have been used in most of the residential sites of labor during for summer Toilet facility has been provided in most of the construction sites but some sites don't have
proper sanitation facility (Pit latrine)
Environmental Monitoring Report January-June 2019
112
SN Issue Compliance Status Remarks
7 Construction waste management
Partially complied Some of the construction sites (District Court office of Dhading District, District Forest office of Ramechap District, District Court office of Gorkha district, Integrated office Building of Sindhuli district, etc) had not managed construction waste such as broken bricks, reinforcement rod, timber, leftover sand & gravel, glass, nail, bamboo scaffoldings, etc, which are haphazardly kept within the available space of the construction site
8 Quarry site management
Not applicable The construction materials such as sand, boulder, gravel, etc have been obtained from approved quarry sites
9 Storage Management Partially compiled In many of the sites, the construction materials have been stored in the newly constructed buildings
In some sites, construction materials have been still stockpiled nearby public land or road side (District Court Office, District Technical office and DUDBC Office, Dhading District; ) due to lack of proper space
10 Plantation and protection of trees
Partially compiled In some construction sites (Building sites of Ramechap district, Dolakha district and Lamjung district), tree plantation has been carried out. The list of plant species to be planted in all the building construction sites had been sent to CSE in order to instruct the contractors for the plantation (Refer Annex 4)
In many of construction sites, space has been allocated for plantation of trees The trees of construction site has been conserved as far as possible However, vegetables has been gown instead of tree in available open space of the building
premises (National Investigation Office, Lamjung district) 11 Cleanliness in and
around construction sites
Partially complied In most of the construction sites, the left out constructions materials have not been managed and have been dispersed randomly
Dustbins or waste collecting containers have not been managed in many of the construction sites
The aesthetic of the building has been reduced due to unmanaged construction wastes and haphazard stockpiling of construction materials
12 Occupational Health and Safety management
Partially complied All the workers have been covered by accidental insurance policy In majority of constriction sites, the construction workers are not provided with adequate
numbers of personnel protective equipment such as boot, helmet, jacket, gloves, mask, safety belt, etc.
In many construction sites, the construction workers don't use PPE although provided. The other reason behind is the repetitive change of construction workers, which has caused difficulty in maintaining safety awareness
Regular safety training has been provided to the construction workers The construction sites have not been barricaded in some of the construction sites The high tension line of 33 kV capacity located on the southern side within the premises of
District Court Office, had been realigned and replaced with concealed cable
Environmental Monitoring Report January-June 2019
113
SN Issue Compliance Status Remarks
13 Management of interrupted service and supply
Not Applicable No disruption of service and supply due to construction activities in any of the construction sites
14 Water logging Management
Partially Complied The water logging of the integrated office building site (Sindhuli District) has been managed by providing drainage management works; however, the works has not been completed yet.
Such problems has not been noticed in the other construction sites 15 Slope Protection and
Management Moderately Compiled The instable slopes nearby the construction site has been properly managed by constructing
retaining and breast walls to avoid falling down of nearby buildings as well as to prevent accidents (District Court Office, Gorkha; District; Integrated Building of DUDBC Division Office and Department of Water Supply and Sanitation Division Office, Rasuwa District; DUDBC Division office)
The hill slope has been managed at District Cottage & Small Industry Committee Office, Sindhupalchowk District
16 Tree Felling for site clearance and safety purpose
Partially complied The written consent has been obtained for clearing 5 trees from Mahakali Mahila Community Forest for site clearance works for District Cottage & Small Industry Committee Office, Sindhupalchowk District
Three Champ Trees (Michelia champaca) needs to be felled down from the premises of DUBDC Office, Lamjung District for the safety of Building as these trees might fall down during strong wind. However, the Division Forest Office doesn't give permission to cut these trees due to the conservation significance of this tree species. DLPIU shall coordinate with Division Forest office for the clearance of these trees regarding safety of the buildings
114
4. Construction Approach
The Government Buildings are designed and executed as per the motto "Built-back-better"
formulated by the National Reconstruction Authority. The approach taken in design and
construction include the following features:
Design incorporates earthquake resistant features Design foresees maximum use of local materials and labour as far as possible Design includes environment friendly measures such as location of building without
risk of landslide, flood etc. It also includes energy saving designs, environmental enhancement measures such as tree plantation, landscaping, rain water harvesting etc.
Most of the construction is manual and labour intensive with occasional use of small equipment such as concrete mixtures, small back hoe for excavation, tractors and small truck for transportation of materials
Child labour is prohibited
5. Compliance Status with Environmental Covenants
The environmental safeguards related to project activities are generally in compliance with
covenants. The detail of environmental covenants is presented in Annex 3.
6. Institutional Arrangement
The project has not established grievance redress committee so far. However, DLPIU has been instructed to form the grievance redress committee to the soonest, and is in the process
of establishment in all project districts. However, an engineer is deployed by DLPIU in all 11
project districts to implement and monitor safeguard issues associated with environment and
social aspects. But no grievance has been received so far in any sub-projects.
7. Corrective actions and way forward
The contractor and DLPIU should apply following corrective measures for the compliance of safeguard:
a. Spoil Management The haphazard disposal of generated waste within construction sites should be
prevented and properly managed Disposal of excess material immediately after filling and compaction of the trench
is necessary Dumping of spoil within construction sites and nearby riverside should be
prohibited [for e.g. the leftover spoil needs to be adequately managed to avoid the movement of spoils into the stream (DUBDC Office, Lamjung District). The spoil of access road needs to DUDBC, Lamjung shall be properly managed as well.
b. Slope Protection and Management Necessary retaining and breast wall has been constructed to maintain slope
stability (District Cottage & Small Industry Committee Office, Sindhupalchowk District)
c. Occupational health and Safety
Environmental Monitoring Report January-June 2019
115
Arrangement of light, fencing by ribbon or bamboo barricades, warning signs, caution board in the construction sites
Adequate number of PPE along with first aid kit with medicines should be provided to workers by contractor at all work sites. In most of the sites, use of PPE has not been strictly implemented
Arrangement of safety belt to workers at a height of 2 meter or more above a lower level
PPE should be used by all the staffs involved in the project The construction workers should be made aware of using PPE through awareness
training Coordination with nearby health institution or hospital in case of medical
emergency or accidents Regular safety training to construction workers
d. Campsite management Use of firewood in the construction camps still persist in some of the sites and
should be prohibited Provision of cooking gas or kerosene, electricity, water supply, clean drinking
water, waste management and medical facilities Use of proper toilet facilities in each camp The workers should be provided with adequate warm living condition The workers should be provided with mosquito nets Regular Health check-up of all the construction workers Provision of an Isolated living unit for the workers suffering from the communicable
disease Prohibition of alcohol consumption and gambling in the construction camps to
avoid conflict with local people
e. Dust emission Sprinkling of water at spoil disposal sites as well as the construction sites consisting
loose soil. The water sprinkling has not been carried out in majority of sites in spite of low dust emission
Open storage and spillage of loose soil in and around the construction site should not be allowed
Truck loads carrying spoils or construction material such as sand, gravel, etc should be properly covered during transportation to prevent blowing off loose construction materials
f. Water Logging Proper management of drainage in and around construction site to avoid water
logging in construction sites as it can create breeding ground for vectors (mosquitos, flies, etc) and create slippery condition of the sites
g. Construction Waste Management and Cleanliness in Construction
Site Prohibition of haphazard disposal of construction debris Establishment of appropriate construction waste management system for
collection, segregation and disposal of construction debris within construction site Stockpiling of construction material along road side should be avoided as it can
obstruct traffic as well as drainage
h. Tree Plantation and Conservation Felling of tree in the construction site should be avoided as far as possible
Environmental Monitoring Report January-June 2019
116
Proper space should be allocated for the plantation of the tree at building site Tree within the construction sites should be conserved as far as possible For greenery and landscape management, ornamental plants (>5ft tall) should be
planted after the completion of construction works ( Refer Annex 4) CLPIU should coordinate with all the offices for the planation of trees as some of
the offices insist to plant vegetables instead of trees.
i. Tree Felling for safety and Site clearance CLPIU/DLPIU should coordinate with Division Forest Office, Lamjung for the felling
of three Champ (Michelia champaca) trees from the premises of DUDBC Building, which has caused threat to the building and safety of people within the premises
8. Major Items Focused for Next Report
The major work planned for the next report comprises of providing safety training for construction work force as well as contractors, plantation of trees within the premises of building and frequent field visit for the implementation of healthy and safe working environment.
Environmental Monitoring Report January-June 2019
118
Annex 1:
Planning & implementing environmental safeguards
activities
Environmental Monitoring Report January-June 2019
119
Annex 1.A: Status of Environmental Safeguard Planning Status
S. N Contract
No. Name of Subproject District
Environmental
screening is carried
out? (Yes or No)
Environment category of the
project / subproject (A/B/C/FI)
IEE/DDR with EMP
is prepared (Yes/No)
ADB approved
DDR (Yes / Under
Review / Not Yet Due/
Over Due)
Safeguard monitoring
and coordination mechanism established
(Yes/No)
GRC is establishe
d (Yes/No)
Automated
safeguard monitoring system
customized
(Yes/No)
EMP cost in
approved document
is included
in BOQ as an
individual item
(Yes/No)
Remarks
1 MoUD/CLPIU/Works/2022-023/NCB-05
Construction of an integrated office building (District Attorney Office, District Postal Office, Division office of Department of Water Supply & Sanitation and DUDBC Division Office)
Sindhuli Yes C DDR with EMP has
been prepared
Reviewed Yes No Yes No
2 MoUD/CLPIU/Works/2072-073/NCB-06
Construction of two Office Buildings (District Forest Office and Irrigation Division Office)
Sindhuli Yes C DDR with EMP has
been prepared
Reviewed Yes No Yes No
3 MoUD/CLPIU/Works/2072-073/NCB-07
Maintenance of four Office Buildings (Agriculture Development Office, Tuber Vegetable Development Center, Land Revenue Office and Chief District Officer's Quarter)
Sindhuli - - - - - - - - -
4 MoUD/CLPIU/Works/20
72-073/NCB-
08
Construction of three office Buildings (District Water Supply & Sanitation Office, DUDBC Division Office and Chief District Officer's Quarter
Ramechap Yes C DDR with EMP has
been prepared
Reviewed Yes No Yes No
Environmental Monitoring Report January-June 2019
120
S. N Contract
No. Name of Subproject District
Environmental
screening is carried
out? (Yes or No)
Environment category of the
project / subproject (A/B/C/FI)
IEE/DDR with EMP
is prepared (Yes/No)
ADB approved
DDR (Yes / Under
Review / Not Yet Due/
Over Due)
Safeguard monitoring
and coordination mechanism established
(Yes/No)
GRC is establishe
d (Yes/No)
Automated
safeguard monitoring system
customized
(Yes/No)
EMP cost in
approved document
is included
in BOQ as an
individual item
(Yes/No)
Remarks
5 MoUD/CLPIU/Works/20
72-073/NCB-
09
Construction of One Office Building (District Forest Office)
Ramechap Yes C DDR with EMP has
been prepared
Reviewed Yes No Yes No
6 MoUD/CLPIU/Works/20
72-073/NCB-
11
Maintenance of 11 Office Buildings (Soil Conservation Office, Post Office, Treasury Comptroller Office, Agriculture Development Office, Irrigation Division Office, District Education Office, District Court Office, District Livestock Office, District Administration Office, District Attorney Office and Department of Water Supply and Sanitation Division Office)
Ramechap - - - - - - - - -
7 MoUD/CLPIU/Works/20
72-073/NCB-
30
Construction of three office buildings (District Court Office, District Forest Office and Chief District Officer's Quarter)
Dhading Yes C DDR with EMP has
been prepared
Reviewed Yes No Yes No
8 MoUD/CLPIU/Works/20
72-
Construction of three Office Buildings (DUDBC Division Office, District
Dhading Yes C DDR with EMP has
Reviewed Yes No Yes No
Environmental Monitoring Report January-June 2019
121
S. N Contract
No. Name of Subproject District
Environmental
screening is carried
out? (Yes or No)
Environment category of the
project / subproject (A/B/C/FI)
IEE/DDR with EMP
is prepared (Yes/No)
ADB approved
DDR (Yes / Under
Review / Not Yet Due/
Over Due)
Safeguard monitoring
and coordination mechanism established
(Yes/No)
GRC is establishe
d (Yes/No)
Automated
safeguard monitoring system
customized
(Yes/No)
EMP cost in
approved document
is included
in BOQ as an
individual item
(Yes/No)
Remarks
073/NCB-31
Post Office and District Agriculture Development Office)
been prepared
9 MoUD/CLPIU/Works/20
72-073/NCB-
33
Construction of 2 Office Buildings (District Attorney Office and District Technical Office)
Dhading Yes C DDR with EMP has
been prepared
Reviewed Yes No Yes No
10 MoUD/CLPIU/Works/20
72-073/NCB-
32
Maintenance of 4 Office Buildings (District Treasury Comptroller Office, Irrigation Division Office, District Small Cottage Office and CDO Office)
Dhading - - - - - - - - -
11 MoUD/CLPIU/Works/20
72-073/NCB-
23
Construction of Six Office Buildings (District Court Office, Department of Water Supply and Sanitation Division Office, District Soil Conservation Office, District Post Office, District Agriculture Development Office and District Education Office)
Nuwakot Yes C DDR with EMP has
been prepared
Reviewed Yes No Yes No
12 MOUD/CLPIU/Works/2
072-
Maintenance of 8 office Buildings (Subtropical Horticulture Development Centre, District Forest
Nuwakot - - - - - - - - -
Environmental Monitoring Report January-June 2019
122
S. N Contract
No. Name of Subproject District
Environmental
screening is carried
out? (Yes or No)
Environment category of the
project / subproject (A/B/C/FI)
IEE/DDR with EMP
is prepared (Yes/No)
ADB approved
DDR (Yes / Under
Review / Not Yet Due/
Over Due)
Safeguard monitoring
and coordination mechanism established
(Yes/No)
GRC is establishe
d (Yes/No)
Automated
safeguard monitoring system
customized
(Yes/No)
EMP cost in
approved document
is included
in BOQ as an
individual item
(Yes/No)
Remarks
073/NCB-24
Office, DUDBC Division Office, Fish Investigation Centre, Disaster Preventive Technical Centre, Road Division Office, District Small & Cottage Industry Office and Division Irrigation Office
13 MoUD/CLPIU/Works/20
72-073/NCB-
37
Construction of Four Office Buildings (DUDBC Division Office, Treasury Comptroller Office, Irrigation Division Office and National Investigation Office)
Lamjung Yes C DDR with EMP has
been prepared
Reviewed Yes No Yes No
14 MoUD/CLPIU/Works/20
72-073/NCB-
38
Maintenance of 5 Office Buildings (District Court Office, District Agriculture Office, District Administration Office, District Soil Conservation Office and Department of Water supply and Sanitation Office)
Lamjung - - - - - - - - -
15 MoUD/CLPIU/Works/20
72-073/NCB-
16
Construction of Three Office Building (Chief District Officer's Quarter, District Forest Office Annex Building and
Sindhupalchowk
Yes C DDR with EMP has
been prepared
Reviewed Yes No Yes No
Environmental Monitoring Report January-June 2019
123
S. N Contract
No. Name of Subproject District
Environmental
screening is carried
out? (Yes or No)
Environment category of the
project / subproject (A/B/C/FI)
IEE/DDR with EMP
is prepared (Yes/No)
ADB approved
DDR (Yes / Under
Review / Not Yet Due/
Over Due)
Safeguard monitoring
and coordination mechanism established
(Yes/No)
GRC is establishe
d (Yes/No)
Automated
safeguard monitoring system
customized
(Yes/No)
EMP cost in
approved document
is included
in BOQ as an
individual item
(Yes/No)
Remarks
District Treasury Comptroller Office)
16 MoUD/CLPIU/Works/20
72-073/NCB-
17
Construction of Four Office Buildings (District Soil Conservation Office, District Agriculture Office, District Livestock Office and District Judge Quarter)
Sindhupalchowk
Yes C DDR with EMP has
been prepared
Reviewed Yes No Yes No
17 MoUD/CLPIU/Works/20
72-073/NCB-
20
Maintenance of 8 Office Building (District Administration Office, Women Development, DEO, District Treasury Comptroller Office, District Agriculture Development Office , District Attorney Office, DUDBC Division office & District Court)
Sindhupalchowk
- - - - - - - - -
18 MoUD/CLPIU/Works/20
72-073/NCB-
18
Construction of Five Office Buildings (Irrigation Development Division Office, District Election Office, DUDBC Division Office including Annex, National Investigation District Office and District Cottage & Small Industry Committee Office)
Sindhupalchowk
Yes C DDR with EMP has
been prepared
Reviewed Yes No Yes No
Environmental Monitoring Report January-June 2019
124
S. N Contract
No. Name of Subproject District
Environmental
screening is carried
out? (Yes or No)
Environment category of the
project / subproject (A/B/C/FI)
IEE/DDR with EMP
is prepared (Yes/No)
ADB approved
DDR (Yes / Under
Review / Not Yet Due/
Over Due)
Safeguard monitoring
and coordination mechanism established
(Yes/No)
GRC is establishe
d (Yes/No)
Automated
safeguard monitoring system
customized
(Yes/No)
EMP cost in
approved document
is included
in BOQ as an
individual item
(Yes/No)
Remarks
19 MoUD/CLPIU/Works/20
72-073/NCB-
12
Construction of four Office Buildings (Irrigation Division Office, District Forest Office, Chief District Officer's Quarter with annex and Water Induced Disaster Management Division Office)
Dolakha Yes C DDR with EMP has
been prepared
Reviewed Yes No Yes No
20 MoUD/CLPIU/Works/20
72-073/NCB-
34
Construction of 5 Office Buildings (District Post Office, District Agriculture Development Office, National Investigation District Office, District Attorney Office & District Soil Conservation Office)
Gorkha Yes C DDR with EMP has
been prepared
Reviewed Yes No Yes No
21 MoUD/CLPIU/Works/20
72-073/NCB-
36
Maintenance of 4 Office Buildings (Department of Water Supply and Sanitation Division Office, Women Development Office, DUDBC Division Office and District Treasury Comptroller Office)
Gorkha - - - - - - - - -
22 MoUD/CLPIU/Works/20
72-
Construction of District Court Office Building
Gorkha Yes C DDR with EMP has
been prepared
Reviewed Yes No Yes No
Environmental Monitoring Report January-June 2019
125
S. N Contract
No. Name of Subproject District
Environmental
screening is carried
out? (Yes or No)
Environment category of the
project / subproject (A/B/C/FI)
IEE/DDR with EMP
is prepared (Yes/No)
ADB approved
DDR (Yes / Under
Review / Not Yet Due/
Over Due)
Safeguard monitoring
and coordination mechanism established
(Yes/No)
GRC is establishe
d (Yes/No)
Automated
safeguard monitoring system
customized
(Yes/No)
EMP cost in
approved document
is included
in BOQ as an
individual item
(Yes/No)
Remarks
073/NCB-35
23 MoUD/CLPIU/Works/20
72-073/NCB-
27
Construction of 7 Office Buildings (Chief District Officer's Quarter, District Post Office, District Agriculture Development Office, Division Irrigation Office, District Livestock Development Office and Integrated Building of DUDBC Division Office and Department of Water Supply and Sanitation Division Office)
Rasuwa Yes C DDR with EMP has
been prepared
Reviewed Yes No Yes No
24 MoUD/CLPIU/Works/20
72-073/NCB-
22
Maintenance of 7 Office Building (District Advocate Office, District Post Office, Irrigation Division Office, District Agriculture Development Office, DUDBC Division Office, District Treasury Comptroller Office & Land Revenue Office)
Kavrepalanchowk
- - - - - - - - -
25 MoUD/CLPIU/Works/20
72-
Construction of five Office Buildings (District Soil Conservation Office, DWSS Division Office,
Okhaldhunga Yes C DDR with EMP has
been prepared
Reviewed Yes No Yes No
Environmental Monitoring Report January-June 2019
126
S. N Contract
No. Name of Subproject District
Environmental
screening is carried
out? (Yes or No)
Environment category of the
project / subproject (A/B/C/FI)
IEE/DDR with EMP
is prepared (Yes/No)
ADB approved
DDR (Yes / Under
Review / Not Yet Due/
Over Due)
Safeguard monitoring
and coordination mechanism established
(Yes/No)
GRC is establishe
d (Yes/No)
Automated
safeguard monitoring system
customized
(Yes/No)
EMP cost in
approved document
is included
in BOQ as an
individual item
(Yes/No)
Remarks
073/NCB-01
National Investigation Office, District Livestock Service Office and District Attorney office)
26 MoUD/CLPIU/Works/20
72-073/NCB-
02
Repair/Retrofitting of 8 Government Office Buildings (District Livestock Office, Land Revenue Office, Irrigation Division Office, District Forest Office, Eastern Region Climate Field Office, Higher Court Office, District Court & DUDBC Division Office)
Okhaldhunga - - - - - - - -
Environmental Monitoring Report January-June 2019
127
Annex 1.B: Environmental Safeguard Implementation Status
SN Contract
No. Name
of Subproject District
Compliance to Environmental Management Plan* Grievances
Co
rre
cti
ve
Ac
tio
n P
lan
s a
re p
rep
are
d a
nd
im
ple
me
nte
d
(Y
/N)
En
v c
om
pli
an
ce
re
po
rtin
g is m
ain
tain
ed
(
Y/N
)
Rem
ark
s
Physical Biological Socio-economic
Sp
oil
Ma
na
ge
me
nt
com
plia
nce
in
%)*
*
La
nd
slid
e p
rote
cti
on
(co
mp
lian
ce in %
)**
Dra
ina
ge
Ma
nag
em
en
t (c
om
plia
nce
in %
)**
Ma
na
ge
men
t o
f co
ns
tru
cti
on
wa
ste
(
co
mp
lia
nce
in
%)*
*
Pla
nta
tio
n f
or
lan
ds
ca
pin
g
Fir
ew
oo
d i
s u
se
d f
or
co
ok
ing
an
d h
ea
tin
g
(Y/N
)
Oth
ers
as
pe
r E
MP
(spe
cify
)
Occupational Health and
Safety
Community services are compensated/reconstru
cted (progress in % of total estimated work)***
Oth
ers
as
pe
r E
MP
(spe
cify
)
No
of
gri
eva
nc
es
do
cu
me
nte
d
No
of
gri
eva
nc
es
re
so
lve
d
No
of
gri
eva
nc
es
un
de
r p
roce
ss
ing
No of Plant
s
Sa
fety
Ge
ars
are
su
ffic
ien
t an
d u
se
d
(Y/N
)
La
bo
rs a
re i
ns
ure
d
(Y
/N)
La
bo
r a
nd
wo
rk c
am
ps
are
he
alt
hy
a
nd
hav
e s
an
ita
ry f
ac
ilit
ies
(
Y/N
)
Co
mm
un
ity S
tru
ctu
re 1
Co
mm
un
ity S
tru
ctu
re 2
1 MoUD/CLPIU/Works/20
22-023/NCB-
05
Construction of an integrated office building (District Attorney Office, District Postal Office, Division office of Department of Water Supply & Sanitation and DUDBC Division Office) Sindhuli 90 95 80 85 - Yes No Yes Yes No No - - - - Yes Yes
2 MoUD/CLPIU/Works/20
72-073/NCB-
06
Construction of two Office Buildings (District Forest Office and Irrigation Division Office) Sindhuli 100 95 95 95 - No No Yes Yes No No - - - - Yes Yes
3 MoUD/CLPIU/Works/20
Maintenance of four Office Buildings (Agriculture Development Sindhuli - - - - - - - - - - - - - - - - - -
Environmental Monitoring Report January-June 2019
128
SN Contract
No. Name
of Subproject District
Compliance to Environmental Management Plan* Grievances
Co
rre
cti
ve
Ac
tio
n P
lan
s a
re p
rep
are
d a
nd
im
ple
me
nte
d
(Y
/N)
En
v c
om
pli
an
ce
re
po
rtin
g is m
ain
tain
ed
(
Y/N
)
Rem
ark
s
Physical Biological Socio-economic
Sp
oil
Ma
na
ge
me
nt
com
plia
nce
in
%)*
*
La
nd
slid
e p
rote
cti
on
(co
mp
lian
ce in %
)**
Dra
ina
ge
Ma
nag
em
en
t (c
om
plia
nce
in %
)**
Ma
na
ge
men
t o
f co
ns
tru
cti
on
wa
ste
(
co
mp
lia
nce
in
%)*
*
Pla
nta
tio
n f
or
lan
ds
ca
pin
g
Fir
ew
oo
d i
s u
se
d f
or
co
ok
ing
an
d h
ea
tin
g
(Y/N
)
Oth
ers
as
pe
r E
MP
(spe
cify
)
Occupational Health and
Safety
Community services are compensated/reconstru
cted (progress in % of total estimated work)***
Oth
ers
as
pe
r E
MP
(spe
cify
)
No
of
gri
eva
nc
es
do
cu
me
nte
d
No
of
gri
eva
nc
es
re
so
lve
d
No
of
gri
eva
nc
es
un
de
r p
roce
ss
ing
No of Plant
s
Sa
fety
Gea
rs a
re s
uff
icie
nt
an
d u
se
d
(Y/N
)
La
bo
rs a
re i
ns
ure
d
(Y
/N)
La
bo
r a
nd
wo
rk c
am
ps
are
he
alt
hy
a
nd
hav
e s
an
ita
ry f
ac
ilit
ies
(
Y/N
)
Co
mm
un
ity S
tru
ctu
re 1
Co
mm
un
ity S
tru
ctu
re 2
72-073/NCB-
07
Office, Tuber Vegetable Development Center, Land Revenue Office and Chief District Officer's Quarter)
4 MoUD/CLPIU/Works/20
72-073/NCB-
08
Construction of three office Buildings (District Water Supply & Sanitation Office, DUDBC Division Office and Chief District Officer's Quarter Ramechap 100 100 100 100 25 No No Yes Yes - - - - - - Yes Yes
5 MoUD/CLPIU/Works/20
72-073/NCB-
09
Construction of One Office Building (District Forest Office)
Ramechap 95 95 95 95 - No No Yes Yes No No - - - - Yes Yes
Environmental Monitoring Report January-June 2019
129
SN Contract
No. Name
of Subproject District
Compliance to Environmental Management Plan* Grievances
Co
rre
cti
ve
Ac
tio
n P
lan
s a
re p
rep
are
d a
nd
im
ple
me
nte
d
(Y
/N)
En
v c
om
pli
an
ce
re
po
rtin
g is m
ain
tain
ed
(
Y/N
)
Rem
ark
s
Physical Biological Socio-economic
Sp
oil
Ma
na
ge
me
nt
com
plia
nce
in
%)*
*
La
nd
slid
e p
rote
cti
on
(co
mp
lian
ce in %
)**
Dra
ina
ge
Ma
nag
em
en
t (c
om
plia
nce
in %
)**
Ma
na
ge
men
t o
f co
ns
tru
cti
on
wa
ste
(
co
mp
lia
nce
in
%)*
*
Pla
nta
tio
n f
or
lan
ds
ca
pin
g
Fir
ew
oo
d i
s u
se
d f
or
co
ok
ing
an
d h
ea
tin
g
(Y/N
)
Oth
ers
as
pe
r E
MP
(spe
cify
)
Occupational Health and
Safety
Community services are compensated/reconstru
cted (progress in % of total estimated work)***
Oth
ers
as
pe
r E
MP
(spe
cify
)
No
of
gri
eva
nc
es
do
cu
me
nte
d
No
of
gri
eva
nc
es
re
so
lve
d
No
of
gri
eva
nc
es
un
de
r p
roce
ss
ing
No of Plant
s
Sa
fety
Gea
rs a
re s
uff
icie
nt
an
d u
se
d
(Y/N
)
La
bo
rs a
re i
ns
ure
d
(Y
/N)
La
bo
r a
nd
wo
rk c
am
ps
are
he
alt
hy
a
nd
hav
e s
an
ita
ry f
ac
ilit
ies
(
Y/N
)
Co
mm
un
ity S
tru
ctu
re 1
Co
mm
un
ity S
tru
ctu
re 2
6 MoUD/CLPIU/Works/20
72-073/NCB-
11
Maintenance of 11 Office Buildings (Soil Conservation Office, Post Office, Treasury Comptroller Office, Agriculture Development Office, Irrigation Division Office, District Education Office, District Court Office, District Livestock Office, District Administration Office, District Attorney Office and Department of Water Supply and Sanitation Division Office) Ramechap - - - - - - No Yes Yes - - - - - - Yes Yes
7 MoUD/CLPIU/Works/20
72-Construction of three office buildings (District Court Office, Dhading 95 95 95 95 4 No No Yes Yes - - - - - - Yes Yes
Environmental Monitoring Report January-June 2019
130
SN Contract
No. Name
of Subproject District
Compliance to Environmental Management Plan* Grievances
Co
rre
cti
ve
Ac
tio
n P
lan
s a
re p
rep
are
d a
nd
im
ple
me
nte
d
(Y
/N)
En
v c
om
pli
an
ce
re
po
rtin
g is m
ain
tain
ed
(
Y/N
)
Rem
ark
s
Physical Biological Socio-economic
Sp
oil
Ma
na
ge
me
nt
com
plia
nce
in
%)*
*
La
nd
slid
e p
rote
cti
on
(co
mp
lian
ce in %
)**
Dra
ina
ge
Ma
nag
em
en
t (c
om
plia
nce
in %
)**
Ma
na
ge
men
t o
f co
ns
tru
cti
on
wa
ste
(
co
mp
lia
nce
in
%)*
*
Pla
nta
tio
n f
or
lan
ds
ca
pin
g
Fir
ew
oo
d i
s u
se
d f
or
co
ok
ing
an
d h
ea
tin
g
(Y/N
)
Oth
ers
as
pe
r E
MP
(spe
cify
)
Occupational Health and
Safety
Community services are compensated/reconstru
cted (progress in % of total estimated work)***
Oth
ers
as
pe
r E
MP
(spe
cify
)
No
of
gri
eva
nc
es
do
cu
me
nte
d
No
of
gri
eva
nc
es
re
so
lve
d
No
of
gri
eva
nc
es
un
de
r p
roce
ss
ing
No of Plant
s
Sa
fety
Gea
rs a
re s
uff
icie
nt
an
d u
se
d
(Y/N
)
La
bo
rs a
re i
ns
ure
d
(Y
/N)
La
bo
r a
nd
wo
rk c
am
ps
are
he
alt
hy
a
nd
hav
e s
an
ita
ry f
ac
ilit
ies
(
Y/N
)
Co
mm
un
ity S
tru
ctu
re 1
Co
mm
un
ity S
tru
ctu
re 2
073/NCB-30
District Forest Office and Chief District Officer's Quarter)
8 MoUD/CLPIU/Works/20
72-073/NCB-
31
Construction of three Office Buildings (DUDBC Division Office, District Post Office and District Agriculture Development Office) Dhading 90 90 95 90 - No No Yes Yes - - - - - - Yes Yes
9 MoUD/CLPIU/Works/20
72-073/NCB-
33
Construction of 2 Office Buildings (District Attorney Office and District Technical Office) Dhading 90 90 90 90 - No No Yes Yes - - - - - - Yes Yes
10 MoUD/CLPIU/Works/20
Maintenance of 4 Office Buildings (District Treasury Comptroller Dhading - - - - - No No Yes Yes - - - - - - Yes Yes
Environmental Monitoring Report January-June 2019
131
SN Contract
No. Name
of Subproject District
Compliance to Environmental Management Plan* Grievances
Co
rre
cti
ve
Ac
tio
n P
lan
s a
re p
rep
are
d a
nd
im
ple
me
nte
d
(Y
/N)
En
v c
om
pli
an
ce
re
po
rtin
g is m
ain
tain
ed
(
Y/N
)
Rem
ark
s
Physical Biological Socio-economic
Sp
oil
Ma
na
ge
me
nt
com
plia
nce
in
%)*
*
La
nd
slid
e p
rote
cti
on
(co
mp
lian
ce in %
)**
Dra
ina
ge
Ma
nag
em
en
t (c
om
plia
nce
in %
)**
Ma
na
ge
men
t o
f co
ns
tru
cti
on
wa
ste
(
co
mp
lia
nce
in
%)*
*
Pla
nta
tio
n f
or
lan
ds
ca
pin
g
Fir
ew
oo
d i
s u
se
d f
or
co
ok
ing
an
d h
ea
tin
g
(Y/N
)
Oth
ers
as
pe
r E
MP
(spe
cify
)
Occupational Health and
Safety
Community services are compensated/reconstru
cted (progress in % of total estimated work)***
Oth
ers
as
pe
r E
MP
(spe
cify
)
No
of
gri
eva
nc
es
do
cu
me
nte
d
No
of
gri
eva
nc
es
re
so
lve
d
No
of
gri
eva
nc
es
un
de
r p
roce
ss
ing
No of Plant
s
Sa
fety
Gea
rs a
re s
uff
icie
nt
an
d u
se
d
(Y/N
)
La
bo
rs a
re i
ns
ure
d
(Y
/N)
La
bo
r a
nd
wo
rk c
am
ps
are
he
alt
hy
a
nd
hav
e s
an
ita
ry f
ac
ilit
ies
(
Y/N
)
Co
mm
un
ity S
tru
ctu
re 1
Co
mm
un
ity S
tru
ctu
re 2
72-073/NCB-
32
Office, Irrigation Division Office, District Small Cottage Office and CDO Office)
11 MoUD/CLPIU/Works/20
72-073/NCB-
23
Construction of Six Office Buildings (District Court Office, Department of Water Supply and Sanitation Division Office, District Soil Conservation Office, District Post Office, District Agriculture Development Office and District Education Office) Nuwakot 90 90 95 90 17 No No Yes Yes - - - - - - Yes Yes
12 MOUD/CLPIU/Works/2
072-
Maintenance of 8 office Buildings (Subtropical Horticulture Development Centre, District Nuwakot - - - - - No No Yes Yes - - - - - - Yes Yes
Environmental Monitoring Report January-June 2019
132
SN Contract
No. Name
of Subproject District
Compliance to Environmental Management Plan* Grievances
Co
rre
cti
ve
Ac
tio
n P
lan
s a
re p
rep
are
d a
nd
im
ple
me
nte
d
(Y
/N)
En
v c
om
pli
an
ce
re
po
rtin
g is m
ain
tain
ed
(
Y/N
)
Rem
ark
s
Physical Biological Socio-economic
Sp
oil
Ma
na
ge
me
nt
com
plia
nce
in
%)*
*
La
nd
slid
e p
rote
cti
on
(co
mp
lian
ce in %
)**
Dra
ina
ge
Ma
nag
em
en
t (c
om
plia
nce
in %
)**
Ma
na
ge
men
t o
f co
ns
tru
cti
on
wa
ste
(
co
mp
lia
nce
in
%)*
*
Pla
nta
tio
n f
or
lan
ds
ca
pin
g
Fir
ew
oo
d i
s u
se
d f
or
co
ok
ing
an
d h
ea
tin
g
(Y/N
)
Oth
ers
as
pe
r E
MP
(spe
cify
)
Occupational Health and
Safety
Community services are compensated/reconstru
cted (progress in % of total estimated work)***
Oth
ers
as
pe
r E
MP
(spe
cify
)
No
of
gri
eva
nc
es
do
cu
me
nte
d
No
of
gri
eva
nc
es
re
so
lve
d
No
of
gri
eva
nc
es
un
de
r p
roce
ss
ing
No of Plant
s
Sa
fety
Gea
rs a
re s
uff
icie
nt
an
d u
se
d
(Y/N
)
La
bo
rs a
re i
ns
ure
d
(Y
/N)
La
bo
r a
nd
wo
rk c
am
ps
are
he
alt
hy
a
nd
hav
e s
an
ita
ry f
ac
ilit
ies
(
Y/N
)
Co
mm
un
ity S
tru
ctu
re 1
Co
mm
un
ity S
tru
ctu
re 2
073/NCB-24
Forest Office, DUDBC Division Office, Fish Investigation Centre, Disaster Preventive Technical Centre, Road Division Office, District Small & Cottage Industry Office and Division Irrigation Office
13 MoUD/CLPIU/Works/20
72-073/NCB-
37
Construction of Four Office Buildings (DUDBC Division Office, Treasury Comptroller Office, Irrigation Division Office and National Investigation Office) Lamjung 95 95 95 95 4 No No Yes Yes - - - - - - Yes Yes
14 MoUD/CLPIU/Works/20
72-
Maintenance of 5 Office Buildings (District Court Office, District Agriculture Office, District Lamjung - - - - - No No Yes Yes - - - - - - Yes Yes
Environmental Monitoring Report January-June 2019
133
SN Contract
No. Name
of Subproject District
Compliance to Environmental Management Plan* Grievances
Co
rre
cti
ve
Ac
tio
n P
lan
s a
re p
rep
are
d a
nd
im
ple
me
nte
d
(Y
/N)
En
v c
om
pli
an
ce
re
po
rtin
g is m
ain
tain
ed
(
Y/N
)
Rem
ark
s
Physical Biological Socio-economic
Sp
oil
Ma
na
ge
me
nt
com
plia
nce
in
%)*
*
La
nd
slid
e p
rote
cti
on
(co
mp
lian
ce in %
)**
Dra
ina
ge
Ma
nag
em
en
t (c
om
plia
nce
in %
)**
Ma
na
ge
men
t o
f co
ns
tru
cti
on
wa
ste
(
co
mp
lia
nce
in
%)*
*
Pla
nta
tio
n f
or
lan
ds
ca
pin
g
Fir
ew
oo
d i
s u
se
d f
or
co
ok
ing
an
d h
ea
tin
g
(Y/N
)
Oth
ers
as
pe
r E
MP
(spe
cify
)
Occupational Health and
Safety
Community services are compensated/reconstru
cted (progress in % of total estimated work)***
Oth
ers
as
pe
r E
MP
(spe
cify
)
No
of
gri
eva
nc
es
do
cu
me
nte
d
No
of
gri
eva
nc
es
re
so
lve
d
No
of
gri
eva
nc
es
un
de
r p
roce
ss
ing
No of Plant
s
Sa
fety
Gea
rs a
re s
uff
icie
nt
an
d u
se
d
(Y/N
)
La
bo
rs a
re i
ns
ure
d
(Y
/N)
La
bo
r a
nd
wo
rk c
am
ps
are
he
alt
hy
a
nd
hav
e s
an
ita
ry f
ac
ilit
ies
(
Y/N
)
Co
mm
un
ity S
tru
ctu
re 1
Co
mm
un
ity S
tru
ctu
re 2
073/NCB-38
Administration Office, District Soil Conservation Office and Department of Water supply and Sanitation Office)
15 MoUD/CLPIU/Works/20
72-073/NCB-
16
Construction of Three Office Building (Chief District Officer's Quarter, District Forest Office Annex Building and District Treasury Comptroller Office)
Sindhupalchowk 95 95 95 95 4 No No Yes Yes - - - - - - Yes Yes
16 MoUD/CLPIU/Works/20
72-073/NCB-
17
Construction of Four Office Buildings (District Soil Conservation Office, District Agriculture Office, District
Sindhupalchowk 90 90 90 90 - No No Yes Yes - - - - - - Yes Yes
Environmental Monitoring Report January-June 2019
134
SN Contract
No. Name
of Subproject District
Compliance to Environmental Management Plan* Grievances
Co
rre
cti
ve
Ac
tio
n P
lan
s a
re p
rep
are
d a
nd
im
ple
me
nte
d
(Y
/N)
En
v c
om
pli
an
ce
re
po
rtin
g is m
ain
tain
ed
(
Y/N
)
Rem
ark
s
Physical Biological Socio-economic
Sp
oil
Ma
na
ge
me
nt
com
plia
nce
in
%)*
*
La
nd
slid
e p
rote
cti
on
(co
mp
lian
ce in %
)**
Dra
ina
ge
Ma
nag
em
en
t (c
om
plia
nce
in %
)**
Ma
na
ge
men
t o
f co
ns
tru
cti
on
wa
ste
(
co
mp
lia
nce
in
%)*
*
Pla
nta
tio
n f
or
lan
ds
ca
pin
g
Fir
ew
oo
d i
s u
se
d f
or
co
ok
ing
an
d h
ea
tin
g
(Y/N
)
Oth
ers
as
pe
r E
MP
(spe
cify
)
Occupational Health and
Safety
Community services are compensated/reconstru
cted (progress in % of total estimated work)***
Oth
ers
as
pe
r E
MP
(spe
cify
)
No
of
gri
eva
nc
es
do
cu
me
nte
d
No
of
gri
eva
nc
es
re
so
lve
d
No
of
gri
eva
nc
es
un
de
r p
roce
ss
ing
No of Plant
s
Sa
fety
Gea
rs a
re s
uff
icie
nt
an
d u
se
d
(Y/N
)
La
bo
rs a
re i
ns
ure
d
(Y
/N)
La
bo
r a
nd
wo
rk c
am
ps
are
he
alt
hy
a
nd
hav
e s
an
ita
ry f
ac
ilit
ies
(
Y/N
)
Co
mm
un
ity S
tru
ctu
re 1
Co
mm
un
ity S
tru
ctu
re 2
Livestock Office and District Judge Quarter)
17 MoUD/CLPIU/Works/20
72-073/NCB-
20
Maintenance of 8 Office Building (District Administration Office, Women Development, DEO, District Treasury Comptroller Office, District Agriculture Development Office , District Attorney Office, DUDBC Division office & District Court)
Sindhupalchowk - - - - - No No Yes Yes - - - - - - Yes Yes
18 MoUD/CLPIU/Works/20
72-
Construction of Five Office Buildings (Irrigation Development Division Office, District Election Office, DUDBC Division Office
Sindhupalchowk 90 90 90 90 - No No Yes Yes - - - - - - Yes Yes
Environmental Monitoring Report January-June 2019
135
SN Contract
No. Name
of Subproject District
Compliance to Environmental Management Plan* Grievances
Co
rre
cti
ve
Ac
tio
n P
lan
s a
re p
rep
are
d a
nd
im
ple
me
nte
d
(Y
/N)
En
v c
om
pli
an
ce
re
po
rtin
g is m
ain
tain
ed
(
Y/N
)
Rem
ark
s
Physical Biological Socio-economic
Sp
oil
Ma
na
ge
me
nt
com
plia
nce
in
%)*
*
La
nd
slid
e p
rote
cti
on
(co
mp
lian
ce in %
)**
Dra
ina
ge
Ma
nag
em
en
t (c
om
plia
nce
in %
)**
Ma
na
ge
men
t o
f co
ns
tru
cti
on
wa
ste
(
co
mp
lia
nce
in
%)*
*
Pla
nta
tio
n f
or
lan
ds
ca
pin
g
Fir
ew
oo
d i
s u
se
d f
or
co
ok
ing
an
d h
ea
tin
g
(Y/N
)
Oth
ers
as
pe
r E
MP
(spe
cify
)
Occupational Health and
Safety
Community services are compensated/reconstru
cted (progress in % of total estimated work)***
Oth
ers
as
pe
r E
MP
(spe
cify
)
No
of
gri
eva
nc
es
do
cu
me
nte
d
No
of
gri
eva
nc
es
re
so
lve
d
No
of
gri
eva
nc
es
un
de
r p
roce
ss
ing
No of Plant
s
Sa
fety
Gea
rs a
re s
uff
icie
nt
an
d u
se
d
(Y/N
)
La
bo
rs a
re i
ns
ure
d
(Y
/N)
La
bo
r a
nd
wo
rk c
am
ps
are
he
alt
hy
a
nd
hav
e s
an
ita
ry f
ac
ilit
ies
(
Y/N
)
Co
mm
un
ity S
tru
ctu
re 1
Co
mm
un
ity S
tru
ctu
re 2
073/NCB-18
including Annex, National Investigation District Office and District Cottage & Small Industry Committee Office)
19 MoUD/CLPIU/Works/20
72-073/NCB-
12
Construction of four Office Buildings (Irrigation Division Office, District Forest Office, Chief District Officer's Quarter with annex and Water Induced Disaster Management Division Office) Dolakha 100 100 100 100 9 No No Yes Yes - - - - - - Yes Yes
20 MoUD/CLPIU/Works/20
72-
Construction of 5 Office Buildings (District Post Office, District Agriculture Development Office, National Investigation District Gorkha 85 85 85 85 - Yes No Yes Yes - - - - - - Yes Yes
Environmental Monitoring Report January-June 2019
136
SN Contract
No. Name
of Subproject District
Compliance to Environmental Management Plan* Grievances
Co
rre
cti
ve
Ac
tio
n P
lan
s a
re p
rep
are
d a
nd
im
ple
me
nte
d
(Y
/N)
En
v c
om
pli
an
ce
re
po
rtin
g is m
ain
tain
ed
(
Y/N
)
Rem
ark
s
Physical Biological Socio-economic
Sp
oil
Ma
na
ge
me
nt
com
plia
nce
in
%)*
*
La
nd
slid
e p
rote
cti
on
(co
mp
lian
ce in %
)**
Dra
ina
ge
Ma
nag
em
en
t (c
om
plia
nce
in %
)**
Ma
na
ge
men
t o
f co
ns
tru
cti
on
wa
ste
(
co
mp
lia
nce
in
%)*
*
Pla
nta
tio
n f
or
lan
ds
ca
pin
g
Fir
ew
oo
d i
s u
se
d f
or
co
ok
ing
an
d h
ea
tin
g
(Y/N
)
Oth
ers
as
pe
r E
MP
(spe
cify
)
Occupational Health and
Safety
Community services are compensated/reconstru
cted (progress in % of total estimated work)***
Oth
ers
as
pe
r E
MP
(spe
cify
)
No
of
gri
eva
nc
es
do
cu
me
nte
d
No
of
gri
eva
nc
es
re
so
lve
d
No
of
gri
eva
nc
es
un
de
r p
roce
ss
ing
No of Plant
s
Sa
fety
Gea
rs a
re s
uff
icie
nt
an
d u
se
d
(Y/N
)
La
bo
rs a
re i
ns
ure
d
(Y
/N)
La
bo
r a
nd
wo
rk c
am
ps
are
he
alt
hy
a
nd
hav
e s
an
ita
ry f
ac
ilit
ies
(
Y/N
)
Co
mm
un
ity S
tru
ctu
re 1
Co
mm
un
ity S
tru
ctu
re 2
073/NCB-34
Office, District Attorney Office & District Soil Conservation Office)
21 MoUD/CLPIU/Works/20
72-073/NCB-
36
Maintenance of 4 Office Buildings (Department of Water Supply and Sanitation Division Office, Women Development Office, DUDBC Division Office and District Treasury Comptroller Office) Gorkha - - - - No No Yes Yes - - - - - - Yes Yes
22 MoUD/CLPIU/Works/20
72-073/NCB-
35
Construction of District Court Office Building
Gorkha 80 80 70 80 - No No Yes Yes - - - - - - Yes Yes
Environmental Monitoring Report January-June 2019
137
SN Contract
No. Name
of Subproject District
Compliance to Environmental Management Plan* Grievances
Co
rre
cti
ve
Ac
tio
n P
lan
s a
re p
rep
are
d a
nd
im
ple
me
nte
d
(Y
/N)
En
v c
om
pli
an
ce
re
po
rtin
g is m
ain
tain
ed
(
Y/N
)
Rem
ark
s
Physical Biological Socio-economic
Sp
oil
Ma
na
ge
me
nt
com
plia
nce
in
%)*
*
La
nd
slid
e p
rote
cti
on
(co
mp
lian
ce in %
)**
Dra
ina
ge
Ma
nag
em
en
t (c
om
plia
nce
in %
)**
Ma
na
ge
men
t o
f co
ns
tru
cti
on
wa
ste
(
co
mp
lia
nce
in
%)*
*
Pla
nta
tio
n f
or
lan
ds
ca
pin
g
Fir
ew
oo
d i
s u
se
d f
or
co
ok
ing
an
d h
ea
tin
g
(Y/N
)
Oth
ers
as
pe
r E
MP
(spe
cify
)
Occupational Health and
Safety
Community services are compensated/reconstru
cted (progress in % of total estimated work)***
Oth
ers
as
pe
r E
MP
(spe
cify
)
No
of
gri
eva
nc
es
do
cu
me
nte
d
No
of
gri
eva
nc
es
re
so
lve
d
No
of
gri
eva
nc
es
un
de
r p
roce
ss
ing
No of Plant
s
Sa
fety
Gea
rs a
re s
uff
icie
nt
an
d u
se
d
(Y/N
)
La
bo
rs a
re i
ns
ure
d
(Y
/N)
La
bo
r a
nd
wo
rk c
am
ps
are
he
alt
hy
a
nd
hav
e s
an
ita
ry f
ac
ilit
ies
(
Y/N
)
Co
mm
un
ity S
tru
ctu
re 1
Co
mm
un
ity S
tru
ctu
re 2
23 MoUD/CLPIU/Works/20
72-073/NCB-
27
Construction of 7 Office Buildings (Chief District Officer's Quarter, District Post Office, District Agriculture Development Office, Division Irrigation Office, District Livestock Development Office and Integrated Building of DUDBC Division Office and Department of Water Supply and Sanitation Division Office) Rasuwa 85 80 85 85 - Yes - No Yes Yes - - - - - - Yes Yes
24 MoUD/CLPIU/Works/20
72-
Maintenance of 7 Office Building (District Advocate Office, District Post Office, Irrigation Division Office, District Agriculture
Kavrepalanchowk - - - - - - - - - - - - - - - - Yes Yes
Construction not
started
Environmental Monitoring Report January-June 2019
138
SN Contract
No. Name
of Subproject District
Compliance to Environmental Management Plan* Grievances
Co
rre
cti
ve
Ac
tio
n P
lan
s a
re p
rep
are
d a
nd
im
ple
me
nte
d
(Y
/N)
En
v c
om
pli
an
ce
re
po
rtin
g is m
ain
tain
ed
(
Y/N
)
Rem
ark
s
Physical Biological Socio-economic
Sp
oil
Ma
na
ge
me
nt
com
plia
nce
in
%)*
*
La
nd
slid
e p
rote
cti
on
(co
mp
lian
ce in %
)**
Dra
ina
ge
Ma
nag
em
en
t (c
om
plia
nce
in %
)**
Ma
na
ge
men
t o
f co
ns
tru
cti
on
wa
ste
(
co
mp
lia
nce
in
%)*
*
Pla
nta
tio
n f
or
lan
ds
ca
pin
g
Fir
ew
oo
d i
s u
se
d f
or
co
ok
ing
an
d h
ea
tin
g
(Y/N
)
Oth
ers
as
pe
r E
MP
(spe
cify
)
Occupational Health and
Safety
Community services are compensated/reconstru
cted (progress in % of total estimated work)***
Oth
ers
as
pe
r E
MP
(spe
cify
)
No
of
gri
eva
nc
es
do
cu
me
nte
d
No
of
gri
eva
nc
es
re
so
lve
d
No
of
gri
eva
nc
es
un
de
r p
roce
ss
ing
No of Plant
s
Sa
fety
Gea
rs a
re s
uff
icie
nt
an
d u
se
d
(Y/N
)
La
bo
rs a
re i
ns
ure
d
(Y
/N)
La
bo
r a
nd
wo
rk c
am
ps
are
he
alt
hy
a
nd
hav
e s
an
ita
ry f
ac
ilit
ies
(
Y/N
)
Co
mm
un
ity S
tru
ctu
re 1
Co
mm
un
ity S
tru
ctu
re 2
073/NCB-22
Development Office, DUDBC Division Office, District Treasury Comptroller Office & Land Revenue Office)
25 MoUD/CLPIU/Works/20
72-073/NCB-
01
Construction of five Office Buildings (District Soil Conservation Office, DWSS Division Office, National Investigation Office, District Livestock Service Office and District Attorney office) Okhaldhunga 80 80 80 80 - Yes No Yes Yes - - - - - - Yes Yes
Construction not
started 26 MoUD/CLPI
U/Works/2072-
Repair/Retrofitting of 8 Government Office Buildings (District Livestock Office, Land Revenue Office, Irrigation Division Office, District Okhaldhunga - - - - - - - - - - - - - - - - - - -
Environmental Monitoring Report January-June 2019
139
SN Contract
No. Name
of Subproject District
Compliance to Environmental Management Plan* Grievances
Co
rre
cti
ve
Ac
tio
n P
lan
s a
re p
rep
are
d a
nd
im
ple
me
nte
d
(Y
/N)
En
v c
om
pli
an
ce
re
po
rtin
g is m
ain
tain
ed
(
Y/N
)
Rem
ark
s
Physical Biological Socio-economic
Sp
oil
Ma
na
ge
me
nt
com
plia
nce
in
%)*
*
La
nd
slid
e p
rote
cti
on
(co
mp
lian
ce in %
)**
Dra
ina
ge
Ma
nag
em
en
t (c
om
plia
nce
in %
)**
Ma
na
ge
men
t o
f co
ns
tru
cti
on
wa
ste
(
co
mp
lia
nce
in
%)*
*
Pla
nta
tio
n f
or
lan
ds
ca
pin
g
Fir
ew
oo
d i
s u
se
d f
or
co
ok
ing
an
d h
ea
tin
g
(Y/N
)
Oth
ers
as
pe
r E
MP
(spe
cify
)
Occupational Health and
Safety
Community services are compensated/reconstru
cted (progress in % of total estimated work)***
Oth
ers
as
pe
r E
MP
(spe
cify
)
No
of
gri
eva
nc
es
do
cu
me
nte
d
No
of
gri
eva
nc
es
re
so
lve
d
No
of
gri
eva
nc
es
un
de
r p
roce
ss
ing
No of Plant
s
Sa
fety
Gea
rs a
re s
uff
icie
nt
an
d u
se
d
(Y/N
)
La
bo
rs a
re i
ns
ure
d
(Y
/N)
La
bo
r a
nd
wo
rk c
am
ps
are
he
alt
hy
a
nd
hav
e s
an
ita
ry f
ac
ilit
ies
(
Y/N
)
Co
mm
un
ity S
tru
ctu
re 1
Co
mm
un
ity S
tru
ctu
re 2
073/NCB-02
Forest Office, Eastern Region Climate Field Office, Higher Court Office, District Court & DUDBC Division Office)
141
S.N Description Indicator Present status
1 DDR Completed / ongoing / proposed
2 Awareness raising orientation trainingii
Number of events and participants
3a Stock piling and spoil disposal management (if required)
Spoil disposal management plan (Y/N)
Volume of safely disposed spoil (m3)
Remaining excavated materials (m3)
Spoil disposal work affecting public interest, locals and their properties (Y/N)
3b Toe walls for safe disposal of excavated materials (if required)
Number and volume (m3) of toe walls constructed to manage spoil
4 Bioengineering works (if required)
Location
Area (m2)
Type of measures taken
5 Dust emission
Covering of delivery vehicles during transportation (Y/N)
Spray of water for suppressing dust emission (Y/N), if yes time interval
6 Noise pollution Vehicles and equipment's used fitted with silencer and maintained to keep noise at minimum levels (Y/N)
7 Water contamination Contamination of water supply or source (Y/N)
8
Quarry site management (if required)
Location of quarry site
Volume of stones/aggregates collected (m3 )
Restoration of site done (Y/N)
9
Campsite management
Supply of safe drinking water (Y/N)
Temporary toilets constructed in camp sites (no.)
Energy used for cooking (fuel wood, kerosene, LPG, electricity)
Proper management of sewerage and waste disposal (Y/N)
10 Construction wastes
Separation of waste disposal in biodegradable and non-biodegradable (Y/N)
Safe disposal of construction waste materials done (Y/N)
11 Storage management
Provision for leakage and spills in storage & service yards (Y/N)
Provision for safety measures like fire extinguisher (Y/N)
12 Plantation around buildings
Plantation carried out (number of plants)
Plantation survival (%)
13
Interruption of services (water, electricity, telephone etc.)
Protection/rehabilitation of services (Y/N), if yes give the name
14
Occupational health & safety
Number of safety gears provided (helmet, jackets, facemasks, goggles, boots, ear plugs, gloves)
Use of safety gears by workers (%)
Environmental Monitoring Report January-June 2019
142
S.N Description Indicator Present status
First aid kit provided with medicines (no.)
Replacement of medicines (Y/N)
Accidental insurance (no. of workers)
Type & number of accident occurred
Compensation to affected workers (no.)
Coordination with nearby health center (Y/N)
15 Informative/safety signboard & cautionary ribbons/barricades
Signboards erected (no.)
Location
Cautionary ribbons/barricades placed (Y/N)
16
Cleaning site after construction and disposing waste properly
Site cleaning after the construction works done (Y/N)
17
Grievances received and addressediii
Received number
Addressed number
18 Photographs Attached photographs with caption
144
Covenants Status as of 30 December 2017
Schedule 5-4. Preparation, design, implementation, and operation of each Subproject comply with applicable laws; the Environmental Safeguards; the EARF; and IEE and EMP.
Being complied
Schedule 5-5. Land acquisition and resettlement activities comply with laws; the Involuntary Resettlement Safeguards; the RF; and the respective RP.
Does not apply – building subprojects identified until now do not require land acquisition/ resettlement
Schedule 5-6. No physical or economic displacement takes place until (a) compensation has been provided in accordance with the RP; and (b) income and livelihood restoration program has been established in accordance with the RP.
Does not apply – building subprojects identified until now do not involve displacement
Schedule 5-7. Necessary budgetary and human resources made available to fully implement the EMPs, and the RPs.
Being complied – (i) the building subprojects identified until now do not require RPs; (ii) the civil works contracts include EMPs but considering the nature of the works, implementing these EMPs require minimum interventions; the implementation of the EMPs by the contractors will be ensured through construction supervision
Schedule 5-8. All bidding documents comply with IEE, EMP, and RP; budget is made available for environmental and social measures; any unanticipated environmental, resettlement or indigenous peoples risks notified by a written notice; and condition of roads, agricultural land and other infrastructure recorded prior to construction.
Being complied – buildings subprojects identified until now are classified as Category C
Schedule 5-9. (a) A semi-annual Safeguards Monitoring Reports submitted to ADB and disclose relevant information; (b) any unanticipated environmental and/or social risks and impacts reported promptly to ADB; and (c) any actual or potential breach of compliance reported.
Being complied
Schedule 5-11. The core labor standards and applicable laws are complied. Bidding documents and contracts require that the contractors (a) comply with applicable labor law and incorporate workplace occupational safety norms; (b) do not use child labor; (c) do not discriminate workers; (d) do not use forced labor; (e) allow freedom of association.
Being complied
146
SN District Headquarter Elevation Bio-Climatic
Zone
Tree Species to be planted
1 Kavre Palanchowk
Dhulikhel 1500m Subtropical Kapoor
Sunachamp
Bakaino
Ban paiyu
Nepali Dalchini
Okhar
Gulab jamun
Koiralo
Lankuri
Naspati
Khurpani
Alu Bakhara
Aru
Haluwaved
2 Sindhupalchowk Chautara 1600m Subtropical Asare phool
Sunachamp
Bakaino
Ban paiyu
Nepali Dalchini
Okhar
Gulab jamun
Koiralo
Kapoor
Lankuri
Naspati
Khurpani
Alu Bakhara
Aru
Haluwaved
3 Dolakha Charikot 1550m Subtropical Asare Phool
Sunachamp
Bakaino
Ban paiyu
Nepali Dalchini
Environmental Monitoring Report January-June 2019
147
SN District Headquarter Elevation Bio-Climatic
Zone
Tree Species to be planted
Okhar
Gulab jamun
Koiralo
Kapoor
Lankuri
Naspati
Khurpani
Alu Bakhara
Aru
Haluwaved, Kadam
4 Nuwakot Bidur 500m Tropical Kadam
Taanki
Nimaro
Rajbriksha
Rudraksha
Sahijan
Ashok (False Ashok)
Anar, Darim
Aap
Lichi
Rukh Katahar
Amala
jamun
Gulab jamun
5 Gorkha Gorkha Bazaar
900m Upper tropical
Sunachamp
Lankuri
Rudraksha
Rajbriksha
Bel
Kagati
Nibuwa
Suntala
Bhogate
Environmental Monitoring Report January-June 2019
148
SN District Headquarter Elevation Bio-Climatic
Zone
Tree Species to be planted
Mosam
Anar, Darim
Aap
Rukh Katahar
Amala
jamun
6 Dhading Dhadingbesi 600m Tropical Kadam
Taanki
Nimaro
Rajbriksha
Rudraksha
Sahijan
Ashok (False Ashok)
Anar, Darim
Aap
Lichi
Rukh Katahar
Amala
jamun
Gulab jamun
Bel
7 Rasuwa (Dhunche) 1800 to 2000m
Upper Sub-tropical-Lower temperate
Salla
Gobre Salla
Lali Guraans
Khurpani
Alu Bakhara
Aru
Haluwaved
Ban paiyu
Nepali Dalchini
Okhar
Syau
Environmental Monitoring Report January-June 2019
149
SN District Headquarter Elevation Bio-Climatic
Zone
Tree Species to be planted
8 Okhaldhunga Okhaldhunga Bazaar
1560m Subtropical Asare phool
Sunachamp
Bakaino
Ban paiyu
Nepali Dalchini
Okhar
Gulab jamun
Koiralo
Kapoor
Lankuri
Naspati
Khurpani
Alu Bakhara
Aap
Haluwaved
9 Sindhuli Sindhulimadhi 400m Tropical Kadam
Taanki
Nimaro
Rajbriksha
Rudraksha
Sahijan
Ashok (False Ashok)
Anar, Darim
Aap
Lichi Rukh Katahar Amala jamun Gulab jamun
10 Lamjung Besisahar 760m Tropical Kadam
Taanki Nimaro Rajbriksha Rudraksha Sahijan Ashok (False Ashok) Anar, Darim Anp Lichi
Environmental Monitoring Report January-June 2019
150
SN District Headquarter Elevation Bio-Climatic
Zone
Tree Species to be planted
Rukh Katahar Amala jamun Gulab jamun Bel
11 Ramechhap Ramechap
(Former) 1100m Subtropical Lankuri
Kagati Nubuwa Rajbriksha Anar, Darim Amala jamun Bel Nariwal Kagaji Badam Amba Mayurpankhu Dhupi Dhupi
Manthali (Current)
500m Tropical Anp Supari Rajbriksha Rudraksha Haluwabet Ashok Lichi Taki Kadam Amba
158
Photograph 1: Safety Instruction to Contractor at Sindhupalchowk District
Photograph 2: Instruction for workers to use PPE at Sindupalchowk District
Photograph 3: Safety Training at Okhaldhunga District
Photograph 4: Safety Training at Okhaldhunga District
Photograph 5: Safety Training at Gorkha District
Photograph 6: Safety Training at Gorkha District
Environmental Monitoring Report January-June 2019
159
Photograph 7: Terrace Garden, DUDBC Building, Ramechap District
Photograph 8: Tree and flower plantation within the premises of DUDBC Office, Ramechap District
Photograph 9: 33 kV Transmission line realigned and replaced with concealed cable, District Court Office, Gorkha District
Photograph 10: Retaining wall to be constructed at northen and eastern side of Dsitrict Court Office, Gorkha District
Photograph 11: Spoil to be managed along the access road to DUDBC Bulding, Lamjung District
Photograph 12: Vegetable grown instead of tree plantation, National Investigation Office, Lamjung District
Environmental Monitoring Report January-June 2019
160
Photograph 13: Unmanagd construction waste, District Court Office, Dhading District
Photograph 14: PPE not proivded to workers, District Agricultural Development Office, Dhading District
Photograph 15: Saftey Instruction to workers and contractor, Integrated DUDBC and DWSS, Rasuwa District
Photograph 16: PPE not used by workers, District Court Office, Nuwakot District
Photograph 17: Drainage Mangement works under progress, Integrated Office Buidling, Sindhuli District
Photograph 18: Tree plantation proposed in available open space, CDO Quarter, Dolakha District