PERMASALAHAN DAN PENGALAMAN DALAM PELAKSANAAN KONSTRUKSI JALAN SUROTO Direktur Operasi PT Hutama Karya (Persero) Jakarta, 24 November 2016

Transcript of PERMASALAHAN DAN PENGALAMAN DALAM...

Indonesia’s Most Valuable Infrastructure Developer Hal 1Jakon EPC DG

PERMASALAHAN DAN PENGALAMAN

DALAM PELAKSANAAN

KONSTRUKSI JALAN

SUROTO

Direktur Operasi

PT Hutama Karya (Persero)

Jakarta, 24 November 2016

Indonesia’s Most Valuable Infrastructure Developer Hal 2Jakon EPC DG

PERMASALAHAN KONSTRUKSI JALAN:

PERMASALAHAN GEOTEKNIK

PERMASALAHAN TEKNIS DESAIN TYPIKAL DAN STANDAR MAKIN LANGKANYA MATERIAL SETEMPAT

YANG MEMENUHI PERSYARATAN

POLITIS/KEBIJAKAN YANG MENGINGINKAN PEKERJAAN CEPAT SELESAI.

Indonesia’s Most Valuable Infrastructure Developer Hal 3Jakon EPC DG

PERMASALAHAN GEOTEKNIK

PRE-LOADING

PVD + PRE-LOADING

VACUUM PRELOADING

A. DATARAN RENDAH : TANAH LUNAK ( PANTURA JAWA , SUMSEL )

VERY SOFT - SPT<2

SOFT --------- SPT 2 – 4

LAPISAN TANAH LEMPUNG YANG LUNAK

PROSES KONSOLIDASI BERTAHUN-TAHUN

PENURUNAN TANAH DAN BADAN JALAN

BIAYA PEMELIHARAAN TINGGI

Indonesia’s Most Valuable Infrastructure Developer Hal 4Jakon EPC DG

PERMASALAHAN GEOTEKNIK

B. PEGUNUNGAN : TIMBUNAN TINGGI

KELONGSORAN LERENG

KONDISI TANAH DASAR YG TIDAK BAIK

4

MEMBATASI TIMBUNAN TIDAK LEBIH 20M

MENGUPAS TANAH DASAR YG CUKUP SEHINGGA DASARNYA KUAT

WAKTU YANG CUKUP UNTUK PELAKSANAAN TIMBUNAN

DIPERHITUNGKAN KEKUATAN TANAH AKAN BERKURANG AKIBAT PENJENUHAN

DRAINASE YANG CUKUP

Indonesia’s Most Valuable Infrastructure Developer Hal 5Jakon EPC DG

PERMASALAHAN GEOTEKNIK

B. PEGUNUNGAN : GALIAN DALAM

KELONGSORAN LERENG

KELANDAIAN LERENG YG TIDAK CUKUP

5

MEMBATASI GALIAN TIDAK LEBIH 30M

DIPASANG INSTRUMENT MONITORING

PROTEKSI LERENG

DRAINASE YANG CUKUP

Indonesia’s Most Valuable Infrastructure Developer Hal 6Jakon EPC DG

PERMASALAHAN GEOTEKNIK

C.TANAH DASAR YANG EXPANSIF

MEMILIKI KEMBANG SUSUT YANG BESAR

MUSIM KEMARAU TERJADI SRINGKAGE , MEMBUAT RETAK PADA TANAH , SHG AKAN CRACK PADA PAVEMENT DIATASNYA

MUSIM HUJAN TERJADI PENGEMBANGAN YG SIGNIFICANT , MENURUNKAN DAYA DUKUNG TANAH YG BESAR SHG MEMBUAT PAVEMENT BERGELOMBANG DAN RUSAK

6

LAPISAN TANAH EXPANSIVE DIBUANG GANTI BORROW MATERIAL

DILAKUKAN STABILIASI DG SOIL TREATMENT

PONDASI BORE PILE GROUP

SLOOPE FAILRURE TIMBUNAN INTERFACE DG CLAY SHALE

PERKUATAN TANAAH CLAY SHLE DG BORE PILE GROUP

Indonesia’s Most Valuable Infrastructure Developer Hal 7Jakon EPC DG

PERMASALAHAN TEKNIS

A. DESAIN TIPIKAL

7

MENYULITKAN PELAKSANAAN DILAPANGAN

• BIAYA AKAN NAIK• WAKTU BERTAMBAH

Indonesia’s Most Valuable Infrastructure Developer Hal 8Jakon EPC DG

PERMASALAHAN TEKNIS

B.MATERIAL

MATERIAL TANAH TIMBUN DISEKITAR PROYEK TIDAK MEMENUHI SPESIFIKASI

MATERIAL AGREGATE TIDAK TERSEDIA DISEKITAR LOKASI PROYEK

8

MATERIAL TIMBUNAN DILAKUAKAN SOIL TREATMENT.

STABILISASI

SULIT DIPENUHI KINERJA YANG DIHARAPKAN

PERLU DIINTERVENSI

Indonesia’s Most Valuable Infrastructure Developer Hal 9Jakon EPC DG

PERMASALAHAN POLITIS/KEBIJAKAN

9

BIAYA

WAKTU MUTU

DALAM SUATU PROYEK TERDAPAT KESEIMBANGAN YANG PALING EFEKTIF

ANTARA WAKTU , BIAYA DAN MUTU

WAKTU DIPERCEPAT, BIAYA TETAP, MUTU TURUN

BIAYA DITURUNKAN, WAKTU TETAP, MUTU TURUN

BIAYA DITURUNKAN, WAKTU DIPERCEPAT MUTU DIKORBANKAN

WAKTU DIPERCEPAT, MUTU TETAP, BIAYA NAIK

1

3

2

4

5

BIAYA POLITK = 5 - 1BESARNYA TERGANTUNG TINGKAT

URGENSINYA DARI PENGAMBIL KEPUTUSAN

Indonesia’s Most Valuable Infrastructure Developer Hal 10Jakon EPC DG

PROYEK-PROYEK YANG DITANGANI

A. KONDISI TANAH LUNAK

TOL PALEMBANG - INDRALAYA

10

DATA TEKNIS :

PROYEK BERADA PADA DAERAH SWAMPY AREA

KEDALAMAN TANAH LUNAK 15 M – 18 M

PERBAIKAN TANAH DENGAN VACUUM PRELOADING

PERKERASAN DENGAN FLEXIBLE :

- Base B : 22 CM

- Base A : 20 CM

- AC Base : 11 CM

- AC Binder : 6 CM

- AC WC : 5 CM

Indonesia’s Most Valuable Infrastructure Developer Hal 11Jakon EPC DG

TOL PALEMBANG - INDRALAYA

11

KONDISI EXISTING TRASE JALAN

GEOTEKSTILE DAN MATERIAL PENGISI

Indonesia’s Most Valuable Infrastructure Developer Hal 12Jakon EPC DG

TOL PALEMBANG - INDRALAYA

12

PREBORING DAN PEMASANGAN PVD

PIPA HORISONTAL DRAIN

Indonesia’s Most Valuable Infrastructure Developer Hal 13Jakon EPC DG13

1. Main Pipe Connect to PumpPipe

2. Sealing Main Pipe & Pump pipe

3. Connecting Electrical Cable 4. Pump Ready For Use

PELAPISAN GEOMEMBRANE

PENYAMBUNGAN PIPA HORISONTAL DRAIN DENGAN POPMA

TOL PALEMBANG - INDRALAYA

Indonesia’s Most Valuable Infrastructure Developer Hal 14Jakon EPC DG14

SELAMA PROSES VACUUM :1. SURFACE SETTLEMENT – 100 M2. PIZOMETER & EXTENSO METER – 200 M3. INKLINOMETER – 18000M2

BACK FILL SETELAH KONSOLIDASI 80%

VACUUM DIHENTIKAN SETALH KONSOLIDASI 90%

TOL PALEMBANG - INDRALAYA

Indonesia’s Most Valuable Infrastructure Developer Hal 15Jakon EPC DG15

PENGHAMPARAN ASPAL LEBAR 9 M SEKALI HAMPAR

AC BASE 11 CM SEKALI HAMPAR

TOL PALEMBANG - INDRALAYA

Indonesia’s Most Valuable Infrastructure Developer Hal 16Jakon EPC DG

PROYEK-PROYEK YANG DITANGANI

B. STABILITAS LERENG

JALAN LINGKAR NAGREG

DATA TEKNIS :

PROYEK BERADA PADA PEGUNUNGAN DAN JURANG YG DALAM

GALIAN DALAM DAN TIMBUNAN TINGGI

SEMI TUNNEL

STABLITAS LERENG TIMBUANAN DALAM DENGAN BRONJONG ANGKUR

LERENG GALIAN DIPROTEKSI

PERKERASAN DENGAN CTB DAN HOTMIX

16

Indonesia’s Most Valuable Infrastructure Developer Hal 17Jakon EPC DG

JALAN LINKAR NAGREG

17

BRONJONG BERANGKUR

BRONJONG BERANGKUR YANG TELAH DIPASANG

Indonesia’s Most Valuable Infrastructure Developer Hal 18Jakon EPC DG

JALAN LINGKAR NAGREG

18

PEMASANGAN TENSAR PADA LAPISAN TIMBUNAN

PEKERJAAN TIMBUNAN LAPIS PER LAPIS

Indonesia’s Most Valuable Infrastructure Developer Hal 19Jakon EPC DG

JALAN LINGKAR NAGREG

19

STABILITAS LERENG DG BRONJONG BERANGKUR

TIMBUNAN BADAN JALAN MENGIKUTI BRONJONG BERANGKUR

Indonesia’s Most Valuable Infrastructure Developer Hal 20Jakon EPC DG

JALAN LINGKAR NAGREG

20

STABILITAS LERENG DG BRONJONG BERANGKUR YANG SDH SELESAI

Indonesia’s Most Valuable Infrastructure Developer Hal 21Jakon EPC DG

JALAN LINGKAR NAGREG

21

KONSTRUKSI GALIAN DALAM , DIBUAT SEMI TUNNEL

PROTEKSI LERENG DENGAN SHOTCRETE

Indonesia’s Most Valuable Infrastructure Developer Hal 22Jakon EPC DG

JALAN LINGKAR NAGREG

22

PERKERASAN JALAN : CTB 20 – 30 CM HOT MIX 15 CM ( AC BASE 6 ,

AC BC 5 , AC WC 4 CM )

Indonesia’s Most Valuable Infrastructure Developer Hal 23Jakon EPC DG

PROYEK-PROYEK YANG DITANGANI

C. GALIAN DALAM DAN TIMBUNAN TINGGI

TOL CIPULARANG

23

DATA TEKNIS :

PROYEK BERADA PADA PERBUKITAN DAN JURANG YG DALAM

GALIAN DALAM DAN TIMBUNAN TINGGI

JEMBATAN PANJANG – 780 M

STABLITAS LERENG TIMBUNAN DALAM DENGAN SHEETPILE

LERENG GALIAN DIPROTEKSI DAN DIMONITORING

PERKERASAN DIATAS SUB GRADE LC DAN RIGID 27 CM

Indonesia’s Most Valuable Infrastructure Developer Hal 24Jakon EPC DG

TOL CIPULARANG

24

TIMBUNAN TINGGI 15 sd 20 M TANAH JELEK DIBUANG 1,5 – 2 M JIKA ADA SUMBER AIR DI BUAT

BLANKET MATERIAL TIMBUNAN SESUAI

SPESIFIKASI

DIPASANG SHEETPILE BETON KEDUA KAKI TIMBUANAN

Indonesia’s Most Valuable Infrastructure Developer Hal 25Jakon EPC DG

TOL CIPULARANG

25

GALIAN DALAM PALING TINGGI 30 M INVESTIGASI TANAH YG AKAN DIGALI DILENGKAPI DRAINASE VERTIKAL DAN

HORISONTAL PROTEKSI PASANGAN BATU DIPASANG MONITORING INKLINO METER

Indonesia’s Most Valuable Infrastructure Developer Hal 26Jakon EPC DG

TOL CIPULARANG

26

LAPISAN PERKERASAN LC DAN RIGID TIDAK ADA LAPISAN DRAIN DARI BASE B

MAUPUN BASE A JIKA TERJADI SETTLEMET AKAN CRACK

PADA LC DAN RIGID JIKA TERJADI HUJAN AIR AKAN SAMPAI

PADA SUB GRADE AKIBATNYA MENURUNKAN DAYA DUKUNG

SUB GRADE , TERJADI PUMPING

PERSOALAN PENTING ADALAH : MENGATASI DIFFERENSIAL SETTLEMENT

ANTARA TIMBUNAN DAN GALIAN SETTLEMENT YG TERJADI SESUAI

SPESIFIKASI 10 CM / 10 THN DRAINASE BERFUNGSI OPTIMAL

Indonesia’s Most Valuable Infrastructure Developer Hal 27Jakon EPC DG

TOL CIPULARANG

27

KONSTRUKSI JEMBATAN RELATIF TIDAK ADA PERSOALAN YG MENDASAR

Indonesia’s Most Valuable Infrastructure Developer Hal 28Jakon EPC DG

SARAN-SARAN

28

KONSULTAN PERENCANA HARUS SUDAH ME-MAPPING KONDISI GEOTEKNIK DAERAH KONSTRUKSI JALAN DAN SEKITARNYA.

DESAIN KONSTRUKSI SUDAH MENGANTISIPASI KONDISI GEOTEKNIK LAHAN YANG AKAN DIBANGUN , UTK ANTISIPASI KENAIKAN BIAYA MASA PELAKSANAAN

WAKTU PELAKSANAAN YANG WAJAR DENGAN MEMPERTIMBANGKAN KAIDAH-KAIDAH TEKNIK

PELAKSANA KONSTRUKSI MEREVIEW DESAIN TERHADAP ASPEK GEOTEKNIK DLL

Indonesia’s Most Valuable Infrastructure Developer Hal 29Jakon EPC DG

TERIMA KASIHJAKARTA 2016