PT. PAPANDAYAN COCOA INDUSTRIESQuality Assurance Department
To: Department Terkait
Date : 01 April 2015From: Quality Assurance Dept./GMP Coord.
Ref : 119/QA/MM/0415Cc: Bpk. Herawan
Re: Jadwal GMP Inspection
Dengan ini diberitahukan bahwa GMP Inspection bulan April 2015 akan dilaksanakan pada tanggal sebagai berikut :
No.Department
JadwalAuditor GMP Auditee
1Mengger Area :
- FG Warehouse - RM Warehouse
- Beans Laboratory- Workshop09 April 2015M. Fanny, Hardi, Agus F., Eko, Jenny
Andri, Agus Suryana,
Ermawan, Rohmat
2Mengger Area :
- Winnowing,
- Rest Room , Kantin & Office Mengger
- Surrounding10 April 2015
Derry, Andri, Ali, Nurman, Ani s
Faizal,Jenny
3Laboratory :
- Kimia
- Mikro13 April 2015Dadi, Kurnia, Kunadi, Cocos
Ade, Ricky, Fanny
4Plant (Upstream)
14 April 2015Rut S., Ade F, Dadang N, Prabudin
Cocos, Dadi
5Plant (Downstream)
15 April 2015Andarini, Ermawan, Willy, Indra G.
Agus F., Ghiyats
6Engineering
16 April 2015Yanuar, Pupung, Wawan Eka, Faizal Rohmat, Risvan
7- Rest Room, Kantin, Office 84
- Surrounding 8417 April 2015Ricky, Yadi A., Risvan, Samuel
Dadang
Keterangan :
- Auditor yang digaris bawah adalah kepala auditor GMP proses terkaitAuditor yang ditunjuk diharapkan melaksanakan GMP sesuai dengan tanggal yang telah ditetapkan. Auditor harus membawa kamera untuk mendokumentasikan hasil temuan.
Pelaksanaan GMP berdasarkan GMP Standard dan checklist GMP.
Laporan hasil GMP bulan berjalan dan bulan sebelumnya yang sudah diverifikasi oleh Auditor diserahkan kepada Koordinator GMP. Demikian diberitahukan agar yang berkepentingan menjadi maklum.
Terima Kasih.
Koordinator GMP,
Mengetahui,
Kurnia