Back Up Data Pondasi p3 & p4

12
REKAPITULASI PEKERJAAN PILE CAP (ADDENDUM I) PROYEK WARE HOUSE AMPLAS - MEDAN BLOK B & C (57 UNIT) NO URAIAN SATUAN VOLUME 1 Galian tanah M3 233.102 2 Beton lantai kerja, tb = 50mm, mutu K-100 M3 8.038 3 Beton cor mutu K-225 M3 33.984 4 Bekisting / acuan M2 129.600 5 Pembesian: - D 13mm Kg 1437.676 Medan, 25 Januari 2013 Diajukan Oleh, Diperiksa Oleh, KONTRAKTOR BURSA PROPERTY SARIPUDDIN RAHMAD S. PROJECT MANAGER PIMPRO

Transcript of Back Up Data Pondasi p3 & p4

Page 1: Back Up Data Pondasi p3 & p4

REKAPITULASI PEKERJAAN PILE CAP (ADDENDUM I)PROYEK WARE HOUSE AMPLAS - MEDAN

BLOK B & C (57 UNIT)

NO URAIAN SATUAN VOLUME KETERANGAN

1 Galian tanah M3 233.1022 Beton lantai kerja, tb = 50mm, mutu K-100 M3 8.0383 Beton cor mutu K-225 M3 33.9844 Bekisting / acuan M2 129.6005 Pembesian:

- D 13mm Kg 1437.676

Medan, 25 Januari 2013Diajukan Oleh, Diperiksa Oleh,KONTRAKTOR BURSA PROPERTY

SARIPUDDIN RAHMAD S.PROJECT MANAGER PIMPRO

Page 2: Back Up Data Pondasi p3 & p4

PROYEK WARE HOUSE AMPLAS - MEDAN BACK-UP DATA ADDENDUM I

TOTAL LUAS 25.277,70 M2 (57 UNIT) GALIAN TANAH PONDASI P3 & P4Tanggal: 25 Januari 2013

Sketsa:

NO.DIMENSI VOLUME JUMLAH PONDASI (UNIT) VOLUME/BLOK (m3)

Panjang (m') Lebar (m') Tinggi (m') BLOK B BLOK C BLOK B BLOK Ca b c d e= (b x c x d) f g h=(f x e) i= (g x e)

P3 1.40 1.40 1.45 2.842 38.00 18.00 107.996 51.156P4 1.00 1.00 1.450 1.450 11.00 40.00 15.950 58.000

JUMLAH TOTAL

Diajukan Oleh, Diperiksa Oleh,KONTRAKTOR BURSA PROPERTY

HENDRA SAFRIZA THAMBOSSite Manager Site Manager

(m3)

Page 3: Back Up Data Pondasi p3 & p4

BACK-UP DATA ADDENDUM I

GALIAN TANAH PONDASI P3 & P4Tanggal: 25 Januari 2013

TOTAL VOLUMEKETERANGAN

m3j= (h + i)159.15273.950

233.102

Diperiksa Oleh,BURSA PROPERTY

THAMBOSSite Manager

Page 4: Back Up Data Pondasi p3 & p4

PROYEK WARE HOUSE AMPLAS - MEDAN BACK-UP DATA ADDENDUM I

TOTAL LUAS 25.277,70 M2 (57 UNIT) BETON LANTAI KERJA K 100PONDASI P3 & P4Tanggal: 25 Januari 2013

Sketsa:

NO.DIMENSI VOLUME JUMLAH PONDASI (UNIT) VOLUME/BLOK (m3)

Panjang (m') Lebar (m') Tinggi (m') BLOK B BLOK C BLOK B BLOK Ca b c d e= (b x c x d) f g h=(f x e) i= (g x e)

P3 1.40 1.40 0.05 0.098 38.00 18.00 3.724 1.764P4 1.00 1.00 0.050 0.050 11.00 40.00 0.550 2.000

JUMLAH TOTAL

Diajukan Oleh, Diperiksa Oleh,KONTRAKTOR BURSA PROPERTY

HENDRA SAFRIZA THAMBOSSite Manager Site Manager

(m3)

Page 5: Back Up Data Pondasi p3 & p4

BACK-UP DATA ADDENDUM I

BETON LANTAI KERJA K 100PONDASI P3 & P4Tanggal: 25 Januari 2013

TOTAL VOLUMEKETERANGAN

m3j= (h + i)

5.4882.550

8.038

Diperiksa Oleh,BURSA PROPERTY

THAMBOSSite Manager

Page 6: Back Up Data Pondasi p3 & p4

PROYEK WARE HOUSE AMPLAS - MEDAN BACK-UP DATA ADDENDUM I

TOTAL LUAS 25.277,70 M2 (57 UNIT) MAL/ BEKISTING PONDASI P3 & P4Tanggal: 25 Januari 2013

Sketsa:

NO.DIMENSI VOLUME JUMLAH PONDASI (UNIT) VOLUME/BLOK (m3)

Sisi (m') Jumlah Segi Tinggi (m') (m2) BLOK B BLOK C BLOK B BLOK Ca b c d e= (b x c x d) f g h=(f x e) i= (g x e)

P3 1.20 4.00 0.30 1.440 38.00 18.00 54.720 25.920P4 0.80 4.00 0.300 0.960 11.00 40.00 10.560 38.400

JUMLAH TOTAL

Diajukan Oleh, Diperiksa Oleh,KONTRAKTOR BURSA PROPERTY

HENDRA SAFRIZA THAMBOSSite Manager Site Manager

Page 7: Back Up Data Pondasi p3 & p4

BACK-UP DATA ADDENDUM I

MAL/ BEKISTING PONDASI P3 & P4Tanggal: 25 Januari 2013

TOTAL VOLUMEKETERANGAN

m2j= (h + i)80.64048.960

129.600

Diperiksa Oleh,BURSA PROPERTY

THAMBOSSite Manager

Page 8: Back Up Data Pondasi p3 & p4

PROYEK WARE HOUSE AMPLAS - MEDAN BACK-UP DATA ADDENDUM I

TOTAL LUAS 25.277,70 M2 (57 UNIT) BETON COR MUTU K 225 PONDASI P3 & P4Tanggal: 25 Januari 2013

Sketsa:

NO.DIMENSI VOLUME JUMLAH PONDASI (UNIT) VOLUME/BLOK (m3)

Panjang (m') Lebar (m') Tinggi (m') BLOK B BLOK C BLOK B BLOK Ca b c d e= (b x c x d) f g h=(f x e) i= (g x e)

P3 1.20 1.20 0.30 0.432 38.00 18.00 16.416 7.776P4 0.80 0.80 0.300 0.192 11.00 40.00 2.112 7.680

JUMLAH TOTAL

Diajukan Oleh, Diperiksa Oleh,KONTRAKTOR BURSA PROPERTY

HENDRA SAFRIZA THAMBOSSite Manager Site Manager

(m3)

Page 9: Back Up Data Pondasi p3 & p4

BACK-UP DATA ADDENDUM I

BETON COR MUTU K 225 PONDASI P3 & P4Tanggal: 25 Januari 2013

TOTAL VOLUMEKETERANGAN

m3j= (h + i)24.1929.792

33.984

Diperiksa Oleh,BURSA PROPERTY

THAMBOSSite Manager

Page 10: Back Up Data Pondasi p3 & p4

PROYEK WARE HOUSE AMPLAS - MEDAN BACK-UP DATA ADDENDUM I

TOTAL LUAS 25.277,70 M2 (57 UNIT) PEMBESIAN D 13 mm PONDASI P3 & P4Tanggal: 25 Januari 2013

Sketsa:

TipeJLH. Panjang Jlh. Batang Volume Berat Besi JUMLAH PONDASI (UNIT) VOLUME/BLOK (m3) TOTAL VOLUME

KETERANGANPANJANG (m') (m') (Btg.) (m') (Kg) BLOK B BLOK C BLOK B BLOK C Kg

a b c d= (a+b+c) e f=(d x e) g h i j=(h x g) k= (i x g) l =(j +k)

P3 0.100 0.12 1.120 1.340 12.00 16.080 16.754 38.00 18.00 636.63 301.56 938.20 P4 0.100 0.12 0.720 0.940 10.00 9.400 9.794 11.00 40.00 107.73 391.75 499.48

TOTAL 1,437.68

Diajukan Oleh, Diperiksa Oleh,KONTRAKTOR BURSA PROPERTY

HENDRA SAFRIZA THAMBOSSite Manager Site Manager

Besi D 10 mm - 15 cm

a

Tipe P3 = 12 Btg

ab b

c

a ab b

c

Tipe P4 = 10 Btg