Project Management Notes

145
PROJECT MANAGEMENT BM 404 STUDY NOTES 0

Transcript of Project Management Notes

PROJECTMANAGEMENT

BM 404

STUDY NOTES

0

A. MAFUKAMIDLANDS STATE UNIVERSITY DEPARTMENT OF BUSINESS MANAGEMENT2005

PROJECT MANAGEMENT

CHAPTER 1

Introduction: Overview of project Management

1. WHAT IS AN INVESTMENT?

It is the current commitment of dollars for a period of

time in order to derive future payments that will

compensate the investor for

1. The time the funds are committed

2. The expected rate of inflation

3. The uncertainty of the future payments.

2. WHO IS AN INVESTOR?

Investor can be an individual, a government, a pension

fund or corporation. The investor is trading a known

1

dollar amount today for some expected future stream of

payments that will be greater than the current outlay.

- Investors invest to earn a rate of return,

which compensates for the time, the expected

rate of inflation and the uncertainty of

return.

3. Investment choices are a function of a investor’s risk

appetite.

Factors like

Inflation rate, interest rate

Financial stability

Political – country risk

Legal and regulatory consensus

Liquidity needs and time horizon

Tax concerns

Time horizon – short term cash (liquid)

Tax concerns – taxable income (VAT)

Unique needs + personal preferences

Critical skills

Infrastructure

2

4. Organisations/institutions that promote development:

Zimbabwe Investment Centre (ZIC)

Zimbabwe Development Bank (ZBD)

Small Enterprises Development Corporation (SEDCO)

Industrial Development Corporation of Zimbabwe

(IDC)

Department of small and medium Enterprise (SMES)

Ministry of Youth and Gender (MYG)

Welfare Organizations (NGO)

-What are the functions?

-What are the objectives?

-What is the structure?

-What are the rules and regulations for the

project requirements?

-Is the role of project development being

met?

PROJECT ENVIRONMENT

a) Project environment needs to be analysed, understood and

addressed if project is to be implemented successfully.

3

b) Project environment provides managers with a structured

approach to analyzing and handling possible external

constraints

c). There must be continued interaction between the project

and its environment, and the project itself affects the

environment just as it in turn is affected by it, so that

there is a two –way relationship between them.

Physical environment:

Refers to the natural setting of the project, its

geology, soils, landscape, climate, water resources and

ecological systems

Many projects are sited in a particular location and

surrounded by a specific physical setting. Sometimes

this setting is the very reason why the projects exist

e.g. mining project is established precisely to exploit

deposits in physical environment, agricultural projects

exist to maximize potential of the natural physical

environment for agricultural production.

Technologies:

4

Technologies utilized for the exploitation or conservation

of the natural resources. Availability –provision of these

technologies is a key dimension of the project environment.

Economic and Financial management:

Projects utilize resources to create assets. Resources

utilized have a cost and these assets created have a value.

Relative costs and values (worth of the projects) are

directly affected by the economic and financial environment

within which they are implemented . Such issues as

budgetary constraints, foreign currency shortages, price

controls, inflation, interest rates are constantly reviewed

in order to complete project at stated cost, using resources

to be acquired. Cost-over-runs often associated with time

delays are very frequently encountered- and these are caused

by constraints of the economic and financial environment.

Institutional and political environment:

Institutional framework concerns such matters as the

legal systems within which project managers are

operating and aspects of social organization such as

the land tenure and water rights system

5

Formal/less formalized organizations are crucial

determinants of project outcome:

Formal: government departments,marketing and credit

institutions, local authorities have clear terms of

references

Less fomalised but official organizations- village level

committees, political groups, religious institutions may

be as important

Political framework in the project environment needs to

considered. Projects necessarily reflect the political

priorities of the country within which they are

implemented. Politics determine the progress of any

project.

Project managers need to be political –need to lobby,

negotiate, use influence to gain political support for

their project. The political environment surrounding a

project involves a complex web of political relationships

which extends beyond individuals to organizations and

geographical areas.

Socio-cultural environment:

6

People –orientated projects e.g most agricultural

projects, health,education and welfare

projects,urban housing, water supply, rural

industrialistion projects are implemented through

people who are not directly part of the formal

project organization

Project organization provides resources, training

services and infrastructure to the population

For the project to be successful, its objectives

will need to be consistent with values and practices

of those people it is designed to assist

It is vital for project personnel to be sympathetic

to the local culture and to have an understanding of

“why things are done the way they are.”

DISCUSSION:

1. Critically analyse the business operating

environment of a project you are familiar with.

What are the prospects of its success? Why?

What are the areas of improvement, if any,

7

would you recommend to the project sponsors for

it to be a success?

2. Examine any one of the

organizations/institutions that promotes

project development. To what extend is it

fulfilling its role in the current economic

environment?

CHAPTER 2

NATURE OF PROJECTS

What is a project?

Definition:

a) It is a collection of linked activities, carried

out in an organized

8

manner with a clearly defined start(ing) point and

finish(ing) point

to achieve some specific results that satisfy the

needs of an organization as derived from the

current business plans.

b) It is organization of people and resources to meet

objectives

c) It is the investment of capital in a time – bound

intervention to create productive assets.

2.2 Characteristic features of a project:

Involves new and unknown tasks

It is an instrument of change (has elements of

risk)

It has clearly defined start and finish dates

It has specific aims

It should result in something being delivered

It is the responsibility of a project manager/

management team

It involves costs, resources and time (subject

to strict deadline)

9

It leads to a change in people’s daily work or

living conditions

Requires the right people at the right time but

people of different backgrounds who are not

used to working together.

Examples of a project

Writing and publication of a book

Relining of a blast furnace in steel works

Setting up a new department at a University

Supporting of a self help efforts of a rural

community

Technical projects: construction of bridges, dams,

water pipe line

Introducing a new product

Organizing a trade fair.

Projects in Midlands

Unki platinum mine project

Relocation of Mtapa long distance bus terminus

10

Construction of MSU administration Block

2.3 PROJECT MANAGEMENT

Definition

a) The dynamic process utilizing the appropriate

resources of the organization in a controlled and

structured manner, employed to achieve a change

clearly defined with specific objectives

identified as strategic needs.

Characteristic features:

- Objective oriented – without these you have

no outcomes

- Change oriented – creating something you need

but do not have.

- Multi disciplined – needs a wide range of

skills to achieve success

- Opportunistic – you must seek to take

shortcuts and bypass old norms

11

- Performance oriented – setting appropriate

standards and quality of outputs

- Control oriented – carefully designed

controls to maintain the schedule

- Avoid getting trapped by the old ways of

doing things.

b) Project management is a tool for management to manage

organization:

Interfaces between organization and its

environment to achieve

stated goals Interfaces within an organisation

2.4 Sources of projects:

1. Corporate and strategic plans/business plans

2. Normal operations/ step changes

3. Continuous improvements/ programmes cross functional

4. Growth by projects addressing needs/ opportunities

5. Growth by incremental change of quality/performance

12

2.5 LIFE CYCLE OF A PROJECT

All projects go through similar life cycle,

comprising the following phases namely:

Phase1: Idea generation and screening the idea

It is done through feasibility study ie

whether to go for the project or

not(prefeasibility Go/and No Go)

-Needs are clearly identified and project is

defined with agreement of those people with

an interest in the outcomes

-Also called conception and definition stage

-Organization realizes that a project may be

needed or receives a request from a customer

to propose a plan to perform a project.

Phase 2: feasibility study: Project formulation

-Looks at techno-economic design stage

aspects of the project

13

-Looks into such issues like location,

finance, commercial, institutional

preliminary organizational/set up, economic

financial aspects.

-Also termed project formulation/design

stage.

-Here the planning phase becomes critical to

derive a realistic schedule and budget taking

into account the constraints imposed on the

project

Phase 3 Implementation/execution

-Entails launching the project work

-Manufacture, construction and installation

of equipment and facilities

-Entails procurement; production

-Requires monitoring cost schedules and

specifications, plan to be up to date

Phase 4 Handover and start up stage

14

- Preparing customer for acceptance and

handover to ensure the project can deliver.

Any follow- up activities are identified and

assigned and project evaluation is completed

Phase 5 Post project evaluation

done after project is handed over to the

customer. It provides data for future

projects.

Contents of a project report(proposal)

15

1. INTRODUCTION:

-purpose

-scope(limits)

2. EXECUTIVE SUMMARY

-executive highlights

-summarises completed project report

-findings

-decisions

3. CONCLUSIONS/RECOMMENDATIONS

4. PROJECT DESCRIPTION

General objectives

Specific objectives

-market analysis

Product/service description

Market position

Competition and marketing strategy

Project structure

Work breakdown structure

Work packages

Project costs

16

Capital and expense requirements

Financial plan (project budget)

Contingencies

Economic and financial analysis(viability)

Risk and sensitivity analysis

Schedule

Time estimates

Calendar schedule

Bar chart schedule

Network

List of activities

Arrow diagram

Resource allocation

Resource type

Resource availability and constraints

Control systems

Project evaluation methods

Cost control

Cost minimizing (time/cost trade offs)

Status report

17

Milestones

ORGANISATION AND ACCOUNTABILITY

Management capacity

Labour /employee plan

Responsibility/accountability matrix

Procedures

Special conditions/contractual

aspects

APPENDIX

Reference material

Calculations

Curriculum vitae (cv)

NB a project plan (report) varies from organization to

organization but any project must contain most of the

above elements.

18

CHAPTER 3

3.0 PROJECT ORGANISATIONAL STRUCTURE -

Hierarchical structure: organizational chart

Appropriate for very large, long-term projects which

work on isolated tasks and are staffed mainly by full

time employees.

Is not appropriate when project is to be integrated

with the base organization.

Advantages

Functional specialists easily share their knowledge and

normally work together.

Easier to implement work rules and regulations for a

group of similar functional experts.

Share a commonality of perspectives that will help the

main thrust of a project.

19

Disadvantages

Disadvantages of organizational projects according to

hierarchical structure

Does not develop technology useful for the future.

Minimal career continuity for project personnel.

It often leads to:-

- bureaucracy

- inefficiency

- poor use of resources

- collapse of authority or the project usurping

responsibility it should not have.

- Little commitment from people outside the

project

- Little informal contact between the project

and its surroundings

MATRIX STRUCTURE

20

Can be on full or part time basis. It is a high breed

organization. It is characterized by having a pull of

project managers who will be assigned to projects. It

comprises of :-

- Core team members with previous experience

who are not necessarily drawn from across the

functional structures.

- Extended team members who are drawn from

across functional structures and do a

specific part of a job for a relatively short

time.

Advantages

Response to changing needs is very rapid.

Functional experts are more part of a team and are

more focused on project deliverables.

Team members have a functional department to

return to after the project.

Their respective departments look after careers

and specific development needs.

21

Disadvantages

There can be conflict between functional line

managers and project managers over the deployment

of resources.

If the team is not physic ally located in the same

area in a building, communications and control

becomes a difficulty.

Matrix structures are frequently hindered by

accusations of poor accountability and lack of

clarity in responsibilities.

Project organization

It is based on assigning projects to each organizational

unit (department). The project make contribution to

corporate strategy. Senior management is involved in

project process and has defined roles and

responsibilities. Senior management sponsor projects and

have authority i.e. ownership over projects. Project

sponsors can form project steering team.

22

Advantages

- It ensures everyone in the organization

focuses on important active projects.

- The reporting structure is clear

- It priotises project for limited resources

- Reaction to market changes if rapid as

authority exists in project team

- Functional specialists work with project

managers

Disadvantages

- Duplication of functional experts will exist

across the organization as they are each

dedicated to a single project.

- There is a lack of information exchange

between functional experts as they are

located in different parts of the

organization.

23

Project sponsor (owns, commissions the project, chairs

PST)

The project sponsor for any project is accountable (to

the PST) for the performance of their projects and must

demonstrate their concern for success to everyone

involved. Responsibilities include:

Ensuring project objectives are always aligned

to corporate needs;

Selecting the project manager;

Approving the project definition;

Sustaining the project direction;

Ensuring priorities are maintained for all

their projects;

Overseeing the project process and procedures,

budget and control; finds and wins resource(s)

for the project

Reacting promptly to issues escalating to them

for decisions;

Maintaining support and commitment;

24

Approving project plans, changes and status

reports.

Project steering team (created by project sponsors has

representatives from business + technical functions + user

community)

This group of project sponsors – the project steering team

(PST) – meets at regular intervals to review the status of

all active projects, initiate new projects and decide the

prioritization of project activity in the organization.

Responsibilities include:-

Ensuring projects are aligned to corporate

objectives;

Giving strategic direction;

Maintaining focus on customer and business needs;

Ensuring environmental influences are taken into

account (internal and external);

Prioritizing all active projects and their

resourcing;

Resolving escalating issues;

25

Providing the ultimate decision forum for all

major problems and issues;

Approving start-up and abortion of projects.

Reviews overall project direction, schedule,

costs, quality of deliverables)

Project manager ( manager project, people + paper work,

attends, steering committee meetings)

The project manager is responsible for the project work

from the initial kick-off through to closure.

Responsibilities include:

Selecting the core team with the project

sponsor;

Identifying and managing the project

stakeholders;

Defining the project and securing stakeholder

approval;

Planning then project and securing stakeholder

approval identifying + managing the risks

Allocating + securing resource commitments

26

Monitoring and tracking project progress

Solving the problems that interfere with

progress

Controlling costs

Leading project team

Informing stakeholders of progress status

Delivering the project deliverables + benefits

Managing performance of everyone involved with

project

Project Manager’s deliverables

i.e The physical items to be delivered from a project.

This typically includes reports and plan as well as

physical products and services project deliveries a

product or service.

Terms of reference or project definition

Milestone plan

Budget

Work breakdown structure

Project organization chart

27

Responsibility

Task definitions

Deliverable definitions

Deliverablee definitions

Quality plan

Dependency chart

Progress reporting standards

Change control standards

Lost of planning + estimating assumptions

Gantt chart

Progress reports

End of phase reports

Project review report

Project Team

Successful teams have to be built through effective

leadership + commitment

Criteria for selecting team members

Relevant technical experience/specialized

knowledge are essential to project.

28

Have worked in project team before i.e have

experience

Assets current non project work load

Do they get on easily with other people

Are they good team players

Is line manager in agreement with possible

assignments.

Project member

Technical expert qualified to complete project

tasks

Gives regular feedback on progress to project

manager

Focuses on delivering quality contributes to

teamwork and morale

CHAPTER 4

4.0 PROJECT PLANNING

“íf you fail to plan: you prepare to fail”

29

4.1 Purpose of planning

To achieve a common understanding of the task to be

resolved

To obtain an overview of the work to be carried out

To lay the foundation for allocating and committing

resources

To be able to form a suitable organization of work

To define a programme of monitoring and control.

4.2 Definition of Project Planning

Is “a continuous process which involved decisions

and choices, about alternative ways using available

resources with the aim of achieving particular goals

at sometime in the future”( Conyers and Hill,1984).

L.Young – planning is a process of creating order out of apparent

chaos

Key aspects of the definition:

Making choices

30

Concerning use of limited resources

To achieve given goals and objectives

Pertaining to some future time

NB: Goal – aim or objective towards which an endeavor is directed.(simply

objective)

4.3 Project planning involves stating

Why a project should be undertaken

What should be done and

By whom, in order to achieve well-defined objectives

by some future dates.

4.4 Products of planning

Plans consisting basically of graphics and text e.g.

graphics – include charts, logic diagrams, sketches

and in some cases photographs

Texts include narratives and tables.

Logic of planning = plan.

List of what jobs (activities) have to be done and

the order of carrying them out.

31

4.5 Planning cycle and project cycle

Like project cycle, planning cycle is made up of three

main elements:

1. Clarity problems to be solved

2. Set out objectives and

3. Draw up the project plans

4.6 Planning procedures:

(i) Establish objectives

State objectives – derived from requirements

(problems that motivated the project

List interim objectives or milestones – these are

significant events in meeting the main objectives

Designate responsible personnel or departments

- These are important groups whose

participation in planning and scheduling are

required for successful project

implementations. These participating

32

activities used to be identified early in

project developments.

(ii) Develop a plan

List what jobs (or activities have to be done to

complete the project

Delineate the jobs by determining their

relationships:

- determine which jobs proceed and succeed

every other job

- determine which jobs can be accomplished

concurrently

(iii) Draw the arrow diagram

Show the sequence in a planning (arrow) diagram.

The planning process becomes complete when the

graphic display in the form of a planning diagram

displays the project work items and their

relationship.

33

4.7 Obstacles to project planning

4.7.1 Network planning Techniques

Network analysis(planning)

This is a graphic analysis of the project showing

the plan of action through the use of a graphic

diagram (used in project planning)

Network planning techniques

Common ones include:

4.7.2 Critical Path Analysis/Critical Path Method CPA/CPM

Developed by Rand corporation and Du Pont

to improve the planning, scheduling and

controlling of projects(as a means of

scheduling shutdowns regular shutdowns at chemical

processing plants)

4.7.3 Programme Evaluation Review Technique(PERT)

Developed from work involving the US Navy for

planning, coordinating the projects associated

with the development of the missile programme

34

Differences

PERT CPM

-event oriented -activity oriented

-provides starting and finishing - provides

starting and finishing

times provided for the event times for the

activity

-provides the probability of -has no

provision for determining

meeting a scheduled date probabilities

-uses three time estimates for -uses on

estimate

each activity

4.8 Network Terminology

Activity – This is a task or job of work, which takes time

and resources. it is

represented by an arrow not arrow to scale.

35

Tail of Head of the arrow arrow -Indicates where Where task ends Task beginse.g Build a wall

- Verify debtors in a sales ledger.

a) What activities are involved in the project.

b) Establish their logical relationship i.e which activity

comes after or before.

c) Establish the estimate of time that the activity is

expected to take.

EVENT- It is a just in time, it indicates the start or

finish of an activity or

activities. It is represented in a network by a

circle or node.

36

Establishing of activities automatically determines events

which are the start of finish if activities e.g wall bulk,

debtors verified, arrived city.

Dummy Activity – It is an activity that does not consume

time or resources. It is a fictitious activity with zero

activity time used to create a PERT or CPM network. It is

used merely to show clear logical dependents between

activities so as not to violet the rules for drawing

network.

It is represented is a network by a dummy activities are not

usually listed with led activities may become necessary as

the network is drawn.

CONCURRENT ACTIVITY – They are activities as tasks that are

designed to be carried out in parallel i.e at the same time.

37

SERIES ACTIVITIES – are activities or tasks that are

designed to be carried out are after another each strictly

dependent on compilation of the earlier activity.

NETWORK – A combination of activities, dummy activities and

events in a logical sequence according to the rules for

drawing networks.

RULES FOR DRAWING NETWORKS

A – A Complete network should have one part of entry i.e a

start event and only

Part of exist i.e a finish event.

B – Every activity must have one preceding as task event and

one succeeding or

head event.

NOTE :- that activities may use the same head event.

Tail Head eventEvents Head

38

Events

Tail event

- However an activity must not share the same tail event and

the same head

event with any other activities (use dummies)

- An event is not complete until all activities leading into

if are complete.

- ‘Loops’ i.e a series of activities which lead back to the

same event are not

allowed because the essence of networks is a progression

of activities away

making onwards in time.

- All activities must be tied into the network i.e they must

contribute to the

progression or be discussed as irrelevant.

- Activities which do not link to the overall network are

called ‘danglers’ they are

not to be used.

39

Dangling activity not to be

used.

CONVENTIONS FOR DRAWING NETWORKS

a) Networks proceed from left to right.

b) Networks are not draws to scale i.e the length of

the arrow does not

represent the time elapsed.

c) Arrows need not be draws in the horizontal plane.

- If they are not already numbers events or nodes should

be progressively

numbered from left to right.

Simple networks have events numbers in simple numeric

progression i.e

0,1,2,3,e.t.c

40

Activity identification

Typical methods of presentation include:-

a) Shortened description of the job of plaster wall e.g

order raw material.

b) Alphabetical or numeric code i.e A.B.C. D e.t.c or

100.101,102 e.t.c

c) Identification by the fail and head event numbers e.g

0-1, 1-2, 2-3

Dummy activities

Part of a network involves a car arriving at a service

station during which 2 independent activities take place,

filling petrol (A) and topping up with oil (B)

Fill petrol

A

Dummy activity

B

Top up with oil

41

Cararrives

Carfilled

with

OilTopped

EXAMPLE

Assume that part of the network involves a man lighting a

cigarette. Activities and there relationship are assumed to

be as follows.

ACTIVITY DESCRIPTION PRECEDING ACTIVITY

A Remove cigarette from case -

C Put cigarette case away A

B Strike match -

D Light cigarette A , B

REQUIRED - A network diagram

Remove cigarette from Put cigar away Case A C

B D

Network Analysis: (Time Analysis)42

Assessing the time

Once outline network has been drawn there is need to

complete it by in settling the activity duration time.

a) Time estimate – an estimate is a decision about how

much time and

resources are required to carry out a piece of work

to acceptable

standards of work performance – You determine the

size of group of

tasks, the amount of effort required to complete

the work. Effort is

measured in project time units, e.g hours days

weeks.

Sources of accurate estimates.

- Use experience of others

- Seek expert views (advice)

- Historical data from other projects

43

NETWORK TERMINOLOGY

3.1.3 Three time estimate approach

This approach is used to offset bias. Before beginning

scheduling of a project it is necessary to estimate the

time required to complete each activity. After

completing the initial arrow diagram, a time estimate

is obtained for each job in the project. Persons

familiar with work to be performed make the time

estimates based on their best judgment.

Sources for accurate estimates:

- Experience from others

- The expert view

- Historical data from other projects

Estimate is a decision about how much time and resources are

required to carry out a piece of work of performance.

44

Determine:

The “size” of the task or group of tasks

The amount of “effort” required to complete the work;

effort is measured in project time units (hours, days,

weeks)

Effort Duration

Schedule

3.1.4 PROJECT SCHEDULING

This is the second phase of a project after planning,

detailing the time at which each job is to be started

and completed. This phase represents when the work need

to be done.

Scheduling Procedure:

1. After the sequence of jobs has been planned and laid in

a network diagram, establish the timing

45

a. Estimate the time required to complete each

project item

b. Calculate the scheduled time for each project

c. Compare the required time (time estimate)

with the available time to complete each job.

d. Identify the critical jobs

e. Determine the front times of non critical

jobs

2. If the project duration time calculated initially is

not acceptable make adjustments to the plan so as to

meet project deadline that is acceptable.

3. Establish a time schedule (using a bias chart)

EXPECTED TIME CALCULATION

Expected time = Optimistic time +4 (normal time) +

pessimistic time

6

46

Optimistic Time - is the shortest possible time required

for completing an activity i.e. everything goes as planned;

deliveries are on time, machines and equipment operate

without breakdowns, personal work within the standards.

Normal Time - is the time most frequently required if

activity were repeated many times under similar conditions.

This is the estimate that should be used in an arrow

diagram, as there is no contingency added.

Pessimistic Time - is the maximum possible time required to

complete an activity i.e. about everything goes wrong:

delivery difficulties work delays, accidents.

e.g. Assume that three estimates for an activity are :

DAYS

(O) Optimistic 11

Most likely 15

(P) Pessimistic 18

EXPECTED TIME = 11+18+4(15)6

= 14.8 days = 15 days

47

a) Time Units

Time estimates may be given in many unit i.e. minutes,

hours, days, weeks depending on the project. All time

estimates within a project must be in the same units to

avoid confusion.

b) Use of time estimates

Project with multiple time estimates can be further analysed

to give an estimates of the probability of completing the

project by a scheduled date

BASIC TIME ANALYSIS - CRITICAL PATH

CRITICAL PATH

- critical path of a network gives the shortest time

in which the whole project can be completed.

- It is the chain of activities with the longest

duration times

- There may be more than one critical path in a

network and it is possible for the critical path to

run through a dummy.

Step by step procedure for establishing critical path1. Earliest start times (EST)

48

- it is the earliest possible time at which a

succeeding activity can start Method of

calculation : FORWARD PASS

a) EST of a head event is obtained by adding onto the EST

of the tail event, the linking activity duration

starting from event o, time o and working forward

through the network.

b) Where two or more routes arrive at an event the longest

route time must be taken e.g. activity F depends on

completion of D and E. E is completed by day 5 and D is

not complete until day 7 ; F cannot start before day 7.

c) The EST in the finish event no 5 is the project

duration and is the shortest time which the whole

project can be completed.

2

B 2 days 4days D

A 1 C 3 E 4

F 5

49

1 day 3 days 1 day 2 days

A – F = Activities

0– 5 = Events

Find the critical path (forward pass)

2

B 2 4 D

A 1 C 3 E 4

F 5

1 3 1 2

The EST of the head event =

Zero starting time + 1 day =

1 + 2 = 3

1 + 3 = 4

4 + 1 = 5

50

0 0 0 0998l0o0 00

23

11

34

47

59

3 + 4 = 7

7 + 2 = 9

b) where two or more groups arrive at an event the longest

route T must be

taken e.g. Activity F dependent on compilation of ‘D’

and ‘E’. ‘E’ is completed

by day 5 and D is not complete until day 7 therefore F

cannot start before

day 7.

c) The EST in the finishing event number 5 is the project

duration and it is the

shortest time in which the where project can be

completed.

2. Latest start time (LST) (Backward pass)

LST for each activity must be established to enable

critical path to be

51

isolated. LST is the latest possible time at which

preceding activity can

finish without project duration.

Calculating LST (backward pass)

a) starting at finish event no5 insert LST i.e. day a and work backwards through the network deducting each activity duration from previous calculated LST.

b) Where tails of activities B & C join event no1, LST for

C is day 3 and LST for B is day 1. The lowest number is

taken as LST for event no 1 because if event no 1

occurred at day 3 then activities B and D could not be

completed by day 7 as required and project would be

delayed.

2

B 2 4 D

A 1 C 3 E 4

F 5

52

0 0 0 0 0998l0o0 00

3 3

1 1

4 6

7 7

59

1 3 1 2

CRITICAL PATH

One path through the network (A, B, D,F) has EST’s and LST’s

which are identical. This is the critical path (chain of

activities which has the longest duration), which can be

indicated by a different colour or by two small transverse

lines across the arrows along the path.

Critical path implications:

- Activities along article path are vital activities

which must be completed by their EST’s/LST’s

otherwise project will be delayed.

- Float is the spare time available on non critical

activities(i.e. (C and E). C and /or E could

takeuptoanadditional2daysintotalwithoutdelaying the

project duration.

- If required to reduce overall project duration then

the time of using more labour, or more or better

equipment or some other method of reducing job times

53

0 0 0 0 0998l0o0 00

must reduce one or more of the activities on

critical path.

Float

Types of floata) Total Float - This is the amount of time a path

of activities could be delayed without affecting the

overall project duration.

Total Float = Latest Heat time –Earliest

Tail time –Activity duration

Total float = 50-10-10

=30 days.

b) Free Float - This is the amount of time activity

can be delayed without affecting the commencement of a

subsequent activity at its earliest start time, but may

affect float of a previous activity.

Free float = Earliest Head Time –Earliest

Tail Time – Activity Duration

Free float = 40 – 10 - 10

20 days

c) Independent Float - This is the amount of time an

activity can be delayed when all preceding activities are

54

completed as late as possible and all succeeding

activities are completed as early as possible.

Independent float does not affect the float of either

preceding or subsequent activities.

Independent Float = Earliest Head Time –

Latest Tail Time –

Activity duration.

Independent float = 40 –20 –10

10 days.For examination purposes the most important type of float

is Total Float .

Calculate float (total)

1) Calculating separately

2) or calculating for total float over chains.

Non –critical chain Time read time available total float

over chain

55

C, E 3+1 = 4days 7 – 1 = 6days 2

days

Slack

This is the difference between EST and LST for each event.

Strictly speaking it does not apply to activities but on

occasions the terms are confused in exam questions.

Exercise:

A project has five activities as follows:

Project data activity Preceding activity Duration

(days) normal

A - 4

B - 8

C A 5

D A 9

E B, C 5

a) Find critical path using EST’s /LST’s

b) Calculate the floats of the network.

NETWORK ANALYSIS a) Cost scheduling

56

A further important feature of network analysis is concerned

with costs of activities and of the project as a whole.

Cost analysis objectives

The primary objective of network cost analysis is to be able

to calculate the cost of various project durations. Normal

duration of a project numbers a given cost:

More labour

Working overtime

More equipment

Network cost analysis seeks to find the cheapest way of

reducing overall duration.

b) Resource scheduling

Management need to know what activities and what resources

are critical to the project duration and if resources

limitations e.g. (shortage of materials, limited number of

skilled labour might delay the project.

Resources scheduling requirements:

57

i) resource requirements for each activity showing

classification of the resource and quantity required

ii) resources in each classification that are available

to project

iii) might need restrictions that need to be considered

e.g. limitations on labour mobility

iv) activity times, descriptions and sequences

1) Submissions of assignments – late submission

not considered

2) Group presentation towards end of session

3) Lecture

4) Effort - schedule – duration

CONSTRUCTING THE NETWORK – Worked Example Tasks Precedence Time Cost Who does

A - 5days --

B - 4days - -

C a 6days - -

58

D b 2days - -

E b 5days - -

F c, d 8days --

Finda) Critical path

b) How long it will take to complete the project

i) Node numbered I denotes event called “START”

ii) Activities a and b have no predecessors, assume

source is at “start” –Node 1

iii) Destination at nodes are numbered 2 and 3

respectively

iv) Arrow heads show direction of flow.

i) Activity c follows a activity d follows b activity e

follows b

NoteNumber event nodes sequentially from left to right as you

construct the network

59

ii) activity f follows both CTD but any given activity

must have its source in one and only one node ‘ ctd

finish in the same node.

ExerciseAssume a small project with ten activities as follows:

Project activity times and precedence’s

Activity optimistic time most likely pessimisticimmediate

Time time time predecessor activity

A 10 22 22 -

B 20 20 20 -

C 4 10 16 -

D 2 14 32 a

E 8 8 20 b, c

F 8 14 20 b, c

G 4 4 4 b, c

H 2 12 16 c

I 6 16 38 g, h

J 2 8 14 d, e

60

Question 1.

Hints

i) start network by finding those activities that have

no predecessors - activities a, b, c meet the test:

they can all be drawn emerging from the starting

node

ii) look for activities that only require a, b, or c or

some combination of a, b, and c to precede them:

- activity d requires that a be completed and e, f

and g all require that b and c completed

- note that a dummy will be necessary unless we begin

the network from separate nodes b and c

- h requires only that c be completed

iii) last activity I and j are drawn in the same manner.

Activity I requires both g and h be completed; so g

and h are directed to a single node (node 5)

Similarly activity j requires completion of both d

and e which are directed to node 6

61

iv) since no activities that f, I or j precede them the

activities are directed to the project completion

node 7.

Question 2.

Expected Time (TE) = (a+4m+b) 6

Where

a = optimistic time estimate

b = pessimistic time estimates

m = most likely time estimate

TE is estimate of the mean of the distribution

It is the weighted average of a, m and b with weights 1 – 4

– 1 respectively. The same method can be used to find the

expected level of resource usage given the approximate

estimates of the modal resource level as well as optimistic

and pessimistic estimates.

Activity Expected Time

A 20

62

B 20

C 10

D 15

E 10

F 14

G 4

H 11

I 18

J 8

Longest of these paths is a-d-jusing43 days which means that

43 days is the shortest time in which the entire network can

be completed. A – d – j is the critical path.

Times and slacks for network

Event Latest occurrence time earliest occurrence

time Slack

1 0 0 0

2 20 20 0

3 21 20 1

63

4 14 10 4

5 25 24 1

6 35 35 0

7 43 43 0

Activity LST EST Slack

A 0 0 0

B 1 0 1

C 4 0 4

D 20 20 0

E 25 20 5

F 29 20 9

G 21 20 1

H 14 10 4

I 25 24 1

J 35 35 0

Notes

EST for an activity = for the event from which activity

emanates

64

e.g. activity I cannot start until event 5 has occurred .

Event 5 has an EOT of 24 days and so activity I has an EST

of 24 days

Project has critical time of 43 days, activity I requires 18

days to be accomplished. Therefore I must be started no

later than 25 (43 – 18 = 25) if the project is to be

completed on day 43.LSTfor activity I is day 25 because I

cannot begin until event 5 has occurred, latest occurrence

time (LOT) for event 5 is also 25.

Slack or Float = difference between the LST and the EST

for an activity

- in the case of activity I it must be started no

later than day 25 but could be started as early as

day 24, so it has one day of slack

- all activities on critical path have zero slack

NB To find the slack for any activity or the LOT for any

event

- make a backward pass (right to left)

65

To find the critical path and time and the EOT’s for

al events

make a forward pass (left to right) which are also

EST’s for successor activities.

Adopt the following convention:

When there are two or more non-critical activities on a

path, it is conventional to calculate the slack for each

activity as if it were the only activity in the path.

Problems1. Given the following information, draw the PERT/CPM

diagram.

Activity Immediate Predecessor

1 -

2 -

3 1, 4

4 2

5 2

6 3, 5

66

2. Given the diagram below, find:

a) Critical path

b) How long it will take to complete the project

3. Given the following network

a) What is the critical path

b) How long will it take to complete this project

c) Can activity B be delayed without delaying the

completion or the project? If so, how many days?

4. Activity a m b

AB 3 6 9

AC 1 4 7

CB 0 3 6

CD 3 3 3

CE 2 2 8

BD 0 0 6

BE 2 5 8

67

DF 4 4 10

DE 1 1 1

EF 1 4 7

Find:

a) the critical path

b) all event slacks

c) critical path to event D

d) the effect if CD slips to 6days, to 7days,to 8days.

NB a = optimistic time estimate

B = pessimistic time estimate

M = most likely time estimate

Calculating Earliest Start Time (EST)

- this is the earliest possible time an activity can

begin without interfering with the completion of

any preceding activities

68

- guidelines in calculating EST

calculation of EST commences with the

beginning mode of arrow diagram (time O) and

continues

if only one arrow leads into a mode, EST for

jobs starting at the mode is determined by

adding EST for the preceding job to the time

estimate for the preceding job.

EST at mode 6 4 = 6

4 EST at mode 8

select 8

project ii

project 2 8

if more than one arrow leads into a mode, EST

calculations is made through each end of the arrows as

noted below. The largest total is the EST for the mode.69

EST at mode 3 EST at mode 7

13 23

pressure equipment

3 7

EST at mode 6

17

Develop operating procedures

6

6

70

Calculating latest finish time (LFT)

- LFT an activity must be completed without delaying the

end of the project.

- Guidelines when calculating (LFT)

Project duration must first be determined by

calculating EST

Project duration is the LFT of the end mode of the

project

Calculation of LFT involves working from the end

mode back through each mode to the first mode in

the project

If more than one arrow originates at a mode, the calculation

of LFT is made via each arrow and the smallest result is

from each mode to the end of the diagram.

71

LFT at mode 4 LFT

at

6 select operating manager

mode

4 6 17

6

9

hire operating train

up personnel

10 personnel

5

4 7

Job 4, 6 17 LFT at mode 6

72

- 9 Time estimate for job 4, 6

8

Job4, 5 10 LFT at mode 5

- 4 Time estimate for job 4, 5

6

LFT at mode 4 is 6 days the smaller of the two results.

Milestone dates can be set V12 P32 – 36

Float: optional start and finish times. A float is the

difference between time available for performing a job and

the time required for doing it.

Available time = Latest finish time - earliest start time

Required time = time estimate for completing a job

73

DIAGRAMS

Benefits from timing calculations:

Establishment of project duration for plan

Identification of longest path (critical path) through

the project

Identification of jobs for which there is scheduling

flexibility without lengthening project duration.

Formula for calculating optional starting and finishing times:

Latest start = earliest start + total floats

Earliest finish = Latest finish - total float.

74

Tabulated schedule can be converted into a calendar

schedule for reporting and monitoring the project.

Bar Chart time schedule can be plotted after schedule is

calculated.

Procedure for constructing bar chart:

1. use earliest start time for each project activity.

2. The length of each bar is the duration of each

activity.

3. Plot one activity per line (in some cases, a number of

activities per time)

75

4.8 Benefits and limitations of network planning

Benefits

A disciplined basis for planning a project

A clear picture of the scope of the project

that be read and understood easily by someone

who is not familiar( but knowledge of the

network diagramming technique) with the

project.

A means of communicating what is to be done in

the project

A vehicle for use in evaluating alternative

strategies and objectives

A means of defining relationships among the

project items

A means of pinpointing those responsible for

accomplishing the jobs that make up the project

An excellent vehicle for training project

personnel

76

4.9 Limitations

Network is often difficult to interpret

A great deal of time is usually needed to prepare

changes, often requiring a great deal of time for

modifications to the network diagram

A network makes it difficult to note estimated

costs versus actual costs

Individual skills are not recognized.

4.10 Bar chart/Gant Chart Construction

Is a graphic planning and control method

a project is broken down into separate tasks and

for each task, estimates are made of the amount of

time required and of the termination date

necessary to meet the specified completion date

for the project.

Information is shown as a pair of brackets

indicating the start and end of dates for each

task

77

Grant Chart enables a manager to make commitments

based on the planned completion times, to acquire

extra resources to shorten some of the times etc.

Grantt Chart enables manager to fill in the

brackets (accomplishment) enabling him to see

immediately what tasks are behind( or ahead of

schedule and how far.

Advantages – provides excellent communication to management

Depicts more readily than network diagrams, a

summary of status of project and thus are used

extensively in reporting on progress of projects.

4.11 Deficiencies/weaknesses

-Relationships among the jobs cannot be shown and questions

cannot be answered regarding

Parts of these jobs that can be done concurrently

Parts of each job that must be completed be for other

parts begin

78

Certain jobs or parts of jobs that must be given

priority so as not to hold up scheduled completion of

project

Optional starting and end dates of some jobs or parts

of jobs if any.

To overcome above deficiencies during planning

Network diagrams explicitly show interrelationships

between jobs. A network diagram shows which jobs can

be done concurrently, which owes precede, and which

ones follow other jobs

Jobs with critical schedules are specified with their

required beginning and end dates

Using computer calculations based on the network diagram

also permits more rapid and accurate updating of project

schedule.

79

“While PERT/CPM and Gannt charts are both scheduling techniques, they are

not merely different ways of achieving the same ends: they are

complementary rather than competitive” Discuss

The date may relate to when a decision is to be made

concerning outside financing, when announcement of a

project to the press is planned, when a thorough

project review is scheduled on whatever.

Milestone scheduling indicates seluted dates by which

various phases of the entire project to be completed.

Milestones add detail to Gantt chart

Milestones serve as formal review points where

costs, progress and the need for replanning on

schedule modification can be reviewed.

Gantt chart shows the relationship between milestones

within the same task but not within different tasks.

80

4.12 Milestone Planning

Is the date when a certain accomplishment, decision or

event is to take place as indicated on the horizontal

bar of a chart . V12 p 14

4.13 PROJECT WORK BREAKDOWN STUCTURE (WBS)

This is a dynamic tool which divides(segments) the

project into parts before starting a project. It is

updated as the work proceeds, particularly as minor

changes affect the task analysis.

Reasons for segmenting a project

Project is large

Project is long term

It is advantageous to have information to plan the

whole project as one unit

We do not have information to plan the whole

project as one unit

The project has several natural phases with

completing different contents.

81

NB: a characteristic of a phase is that it is possible to

plan it as a whole i.e. giving us an insight into the types

of activities that should be done in this phase.

A WBS does not show dependencies other than a grouping under

the key stages.

A WBS is not time based – there is no time scale on the

drawing.

e.g. feasibility(phase) study V

implementation phase

Preliminary project V (main project)

-Defines precisely objectives and goals -it implements

what has been

on project decided

-Requires thoroughness

completeness

4.14 PROJECT RESPONSIBILITY CHART

82

- It is a contract between the project and the parties

involved (management other resource persons and members

from the base organization who are drawn into the

project)

- Each party must understand clearly the responsibilities

for (work ending up to a milestone) and their roles.

Each key stage must be owned by one of the team

members.

- Some milestones may require authority to make

decisions.

- Responsibility can consist of being responsible for

progress, expecting work, making decisions, being

available for consultation, receiving information or

tutoring.

- When project responsibility chart has been developed it

is useful to evaluate the results.

- External assistance can be included in the project on

project members e.g. legal expertise, trade union

83

representative, expert in economics and finance (if not

found from within)

- At this stage data to complete “duration” on plan “end

date” is not yet in place.

LINEAR RESPONSIBILITY CHART (LRC)

- It is a contract between the project and the parties

involved i.e right and member from the base

organization who are drawn into the project as resource

persons and each party must understand clearly for work

leading up to a milestone (date of announcement)

- Responsibilities can consist of being responsible for

progress or implementing work, making decisions, being

available for consultations, receiving information or

tutoring as well as evaluating the results.

- External assistant can also be included in the project

as project members such as legal practioners, TUs,

economic experts if not found from within.

- If summaries the relationships between project

participants and their responsibilities in each element

84

of a project and an element can be a specific activity

an authorization to perform an activity, a decision or

a report. The LRC has government column to represent

organizational elements and roles which correspond to

the project elements and roles which correspond to the

project elements performed by the organization.

- The LRC depicts authority, responsibility and

communication channels.

Activity Engineering manager

Manufacturing manager

Contracts manager

Project manager

Marketing manager

Qualityassurance manager

Negotiating

Contract

I, N I, N I, R P I A

Preliminary

Design

P A R O, B I A

Execution R P - O, B I R

Delivery N N P A N A

KEY

A - ApprovalP - Preliminary responsibility – who is responsible for accomplishing

85

R - ReviewN - NotificationO - OutputI - InputB - Initiation

4.0 PROJECT DOCUMENTATION

Project work produces a large amount of data and

it is important that you record essential

material. Insist that the team keep all essential

project records on a standard set of templates

(format 5) derived specifically for the purpose.

To ensure project data is resolved in a

consistent and disciplined manner without

reinventing every week.

To get the right information recorded for the

project file to support your control system

and aid project evaluation at completion.

Standard formats can be designed on the

computer

a) Project File

86

- use a paper based system but more preferably on

computer based file which makes distribution of

information easier with a network.

- Organize your project file into sections for different

stages of the project e. g.

Background information

Project definition

- project organization

- stakeholders

- project brief

Project plans and schedules

- project risk management

- responsibility charts

- schedules

- work plans

Project execution and implementation

- project status reports

87

- changes to project plans

- action plans for correction action

- cost control data

- supplier and subcontractor data

- records of meetings

Project closure

- handover checklist

- acceptance pressure

- follow up and post project responsibilities

- project evaluation data

- completion report

b) Project logbook

- open a project log book at the start of your project

- book in an A4 bound …….book

- log book is particularly valuable to record events with

third parties like suppliers and contractors. When

conflicts and differences occur the logbook provides a

88

record of events that can have a legal status in a

dispute

- log book is an addendum to the project file

- the logbook is an invaluable record of what actually

happened throughout the project. It is useful for post-

project evaluation and a source of active data for

other projects in the future.

c) Project definition

- process of turning the data into something more solid

and realistic, something that is no longer a wish or a

hope

- a clear definition of your project is critical to

success – a large number of projects (more than 75%)

are perceived to fail as a consequence of poor or

nuclear definition

Documents required to effectively define project:

I. a statement of requirements

89

II. a stakeholder list –

- all with an interest in the project, how or in the

future : customer, endures, project sponsors, line

managers of your core team members

- finance department, sales and marketing department,

consultants ,

contractors, suppliers, other divisions or sites.

Project log book

Record events with essential relevant data:

date

time

who is involved

key points or content

Events to record Telephone calls – incoming and outgoing

Faxes – incoming and outgoing

Letters – sent and received

Memos – sent and received

90

E –mail - sent and received

Purchases instructions issued

Contracts signed

Action plans agreed

Decisions taken – how implemented

Solutions derived

Reports issued

Meetings – sponsor team, third party, one – to – one

When using log book

Use every page and number them sequentially

Never remove any pages

Start each day with anew page

Always write with ink, never with pencil

Write on very line

Rule out all unused lines at the end of each day and

sign the page at the bottom

Do not allow anyone else to write in the logbook – even

the project sponsor.

- the public, other agencies/statutory bodies

91

stakeholders used to be consulted for their inputs

to give you a wider

perspective of:

- the real project needs and requirements

- what is realistically available in the time scale

demanded.

III. Project brief – one page document with the following

sub headings:

Project title – relevant title for identification

(project number)

Project overall objective – describes project’s

desired results in 25 –30 words

Project leader and sponsor to be identified

Project proposed start date: date when the real

work starts after definition is approved and

planning begins

Project required and date: and project is handled

over to customer

92

Project deliverables; tangibles outputs from the

project which must be impabale of being measured

through its lifecycle, apply SMART test to ensure

that each deliverable is specific, measurable

achievable, realistic and time bound

Project benefit

Lists benefits and quantity them in financial

terms-cost savings, increased turnover,

contribution or profitability in a specific time

scale.

Project strategy –explore alternative, carry out

feasibility study, set up site team, involve

customers in the team

Project skills required: identify and highlight

special experience and technical skills you expect

to need, external skills, expertise from outside

the organization.

Relationships with other active projects –any

project interfaces with other projects in terms of

93

inputs, outputs critical interface dates to be

determined.

Project cost – if known or budget exists from

earlier studies or feasibility with them state

cost, if not give estimate cost o rleave blank.

Risk management – risk log and management forms

attached

Project brief is a document that summarizes all relevant

facts about the project and is a source of definitive

information:

Contents:

Projects origins –a need or opportunity statement

Project …….. – why is it necessary now?

Benefits of project –to customer and your organisation

Project budget if known at this stage

Current timescale and dead lines –subject always to

detailed planning later

94

Iv Scope of work statement (SOW)

- it is a narrative description of the project objectives

in more detail, giving more information about each

deliverable and benefit identified. SOW must identify

boundary limits of project clearly stating what is not

going to be done as part of the project. It records all

constraints made earlier and any assumptions made in

each of the meetings, SOW is where the applicable

specification list is recorded:

- internal product specifications

- external product specifications

- mandatory standards imposed by legislation

- process specification

- customer specifications

- standard operating procedures

- purchasing procedures

- quality standards

- testing specifications and procedures

95

- sub contract terms and conditions imposed on third

parties

Its purpose:

- to make sure that everyone knows from the offset which

standards and specifications apply to your project

- it identifies where actual document scan be found for

reference

- it identifies what exceptions, if any, apply to any

specification for your project

- if necessary record for reference purposes any other

relevant documents that have been issued previously

relating to project e.g. CBA fundability reports,

studies carried out by consultants, project evaluation

reports from previous projects

v Risk Management

- a risk is any event that could prevent the project from

realizing expectations of the stakeholders as stated in

96

the agreed project briefs or a agreed definition. A

risk that becomes a reality is treated as an issue

- there are risks to all projects and risk management is

the process o identifying and containing them to ensure

your project’s success. It is necessary to anticipate

what might go wrong.

Two types of risks

o project risks – associated with technical aspects of

the work of the work to achieve the required customers

o process risks – associated with project process,

procedures, tools and techniques employed, the controls

put in place, communication, stakeholders and team

performances

o can be due to external / internal factors

Project manager is made an obligation with the team to,

identify and evaluate potential risks

obtain agreement for action plans to contain risks

97

take actions and monitor results

promptly resolve any issues arising from risks that

happen

Risk management is a continuous process throughout the life

cycle of the project. Identify the triggers or signals that

suggest a risk likely to happen, and you must maintain

awareness of risk in the minds of all your project team;

should be started at definition phase.

Is essential to establishing project brief

Compile a complete list of a project risk log

Review the list at regular intervals as the project

moves forward.

Approval of project definitionRequires following documents to be presented

Project organization chart p56 T&Young

Project stakeholder list

Scope of work statement

Project risk management forms

Project brief.

98

5. PROJECT LAUNCHING

After project definition, plan and schedule have been

approved you are ready to launch the project work.

i) ask key stage owners(people

assigned with project work and

own the work) to record their

task lists

-using WBS

-use schedule start and end

dates

-note name of person responsible

for carrying out the tasks.

-prepare Gannt chart.

ii) establish milestone scheduling –

milestone should be considered

as a flag or some signal at some

clearly defined point in the

99

project. There are selected key

events that are of major

importance towards achieving

objectives.

Milestone are excellent tools for reporting project status

in summary form to management. It summarizes the status of

major events.

e.g.

completion of key task

completion of one of the project deliverables

stage generation of benefits

completion of third party activity

financial audit point

project audit point

quality audit

significant decision point.

Record list of milestone on a schedule and on Gantt chart.

100

5.1.3 IDENTIFYING CRITICAL SUCCESS FACTORS OF PROJECT

Use process type CSF which include:

- tools, techniques, processes and procedures you use to

define, plan, execute and complete project on time, to

the budget

- these must be acceptable to the key stakeholders i.e.

customer and project sponsor

Examples:

- defining project objectives, deliverables, benefits

- ensuring sponsor is appointed and sustains support and

commitment to project

- appropriate team is formed and right skill are utilized

- scheduled plans exist, up to date

- WBS is maintained

- Control procedures are understood

- Project risks regularly reviewed

- Reporting and communication procedures are established

–plan a meeting schedule (1 to 1)meetings for your

project.

101

5.1.4. Launch Meeting: as a milestone in the project

- get together all important people involved in a project

project sponsor

the customer

other stakeholders(key) –line managers

project team

Consider preparing a document package for distribution

containing:

project organization chart

project stakeholderlist

key stage Gantt chart

key stage responsibility chart

project brief

any other relevant information

CHAPTER 6: PROJECT WORTH

INVESTMENT DECISIONS

Decision to invest is based on 3 major factors.

102

(a) Investor’s beliefs in the future – such

beliefs would be based on forecasts of internal

factors including: costs, revenues, inflation,

interest rates, taxation etc.

(b) Alternatives available in which to invent –

appraisal techniques are used to assess competing

investments.

(c) Investor’s attitude to risk – analysis of

project uncertainity, risk are critical given the

size of investment.

Appraisal techniques

Payback is the period usually expressed in yeas which it

takes for the project’s net cash inflows to recoup the

original investment.

e.g

Calculate payback for the following projects:

103

Project 1 Project II

Year Cash flow Cash flow

0 -1500 -1500

1 +600 +400

2 +500 -500

3 +400 +600

4 -1500

5 +300

6 +500

7 +400

8 +300

9 +300

10 +300

104

Advantages

a) Simple to calculate + understand

b) Uses project cash flows rather than

accounting profits + hence is more

objectively based.

c) Favours quick return projects which

may produce faster growth for waand

enhance liquidity

d) Choosing projects which payback

quickest with tend to minimize

those risks saving the way which

are related to time.

Disadvantages

a) Payback does not measure overall project

worth because it does not consider cash

flows after the payback period e.g project

III is ranked after project I + II even

though it produces cashflows over a 6 year

period.

105

b) Payback provides only a crude measure of

project cashflows. eg project I + II are

reached equally even though there are clear

differences in timing of cash flows. In

spite of above it is undoubtedly the most

popular appraisal criteria in practice.

Discounted cashflow (DCF)

Use of Def overcomes some of the disadvantages of the

traditional technique of payback.

Two common features to DCF methods:

a) Use of cash flows not accounting profit.

This is preferred because:-

- Cash flows are more objective and in the end

are what actually count. Profits cannot be

spent cash is the life blood of the company.

- Accounting conventions regarding

revenue/capital expenditure classifications,

106

depreciation calculations, stock valuations

become largely redundant.

- The whole life of the project is to be

considered therefore it becomes unnecessary

and misleading to consider accounting profits

which are related to periods (period

oriented- monthly, quarterly, annually)

- Timing or expected timing of cash flows is

more easily ascertained.

Typical cash flow items include;

1. project revenues

2. cost grants

3. resale or scrap value of assets

4. tax receipts capital injection

(contribution)

5. any other cash inflows caused by accepting

the project.

107

Cash outflows

- initial investment in acquiring the assets

- project costs (labour, materials etc)

- working capital investment

- tax payments

- any other cash outflows caused by accepting

project.

b) Time value of money (money received now is worth more

than money

received in use of money)

It is preferable to receive a given sum of money earlier

rather than later because the sum received earlier can be

put to use by earning interest or some productive investment

within the business.

Assumptions in basic DCF Appraisal

a) uncertainty does not exist

b) inflation does not exist

c) appropriate discount ate to use is known

108

d) a perfect capital market existsi.e.

unlimited funds can be raised at the

market rate of interest.

NPV method

It calculates the present values of expected cash inflows

and outflows (i.e the process of discounting) and finds out

whether in total the present value of cashinflows is greater

than the present value of cash out flows.

NPV = C (1 + r)

Where C = net cash flow

= Summation of

r = discount rate

e.g An investment is being considered for which the net

flows have been estainated as follows.

Period cashflow PVF Discounted PV

Yr 0 Yr 1 Yr2 Yr3 Yr4

109

-9500 +3000 +4700 +4500

+3200

What is the NPV if the discount rate is 20%. Is the project

acceptable?

NPV = -9500 + (0,833 x 3000) + (0,094 x 4700)

+ (0,579 x 14800) + (0,482 x 3200)

= $582

Use tables

To verify use calculator I

1 + r

Investment acceptable because it has positive NPV at the

firm’s cost of capital.

Interpretation: the NPV means potential increase in

consumption made possible by the project valued in present

day terms.

Internal Rate of return (IRR)

Alternative names:

- DCF yield

110

- Marginal efficiency of capital

- Trial and error method

- Discounted yield

- Actual rate of return

Definition

- It is the discount rate which gives zero NPV.

- It can be found by either

i) drawing a graph known as a present value profile

or

ii) calculations involving lines interpolation.

Present value profile

- Is a graph of the project NPV’s at various

discount rates

- Plot two points one at a rate which gives

positive NPV and one at a rate which gives a

negative NPV

111

e.g 20% gives + $ 582 NPV; and a higher rate is tried to see

if a negative NPV is obtained e.g 25% discount rate gives –

322 NP

Plot these points and draw a line between them to see where

it crosses the horizontal axis which gives then IRR

PRESENT VALUE PROFILE

700 -

600 -

+ VE 500 - NPV @ 20% = $

582

400 -

300 –

112

200 -

100 - IRR i.e the discount rate which gives

NPV 0 - zero NPV

$ 100 - 5 10 15 20 25 30 35

40

- VE 200 -

300 - NPV @ 25%

= $ -322

400 -

500 -

Note

a) at least out discount rate must be

chosen which gives a negative NPV so

that the present values line crosses the

horizontal axis.

b) The present value line crosses the axis

at approximately 23% which is close

enough estimate for most practical

purposes.

Finding the IRR by linear interpolation

113

IRR C

= 20% + 5% 582904

(a) (b) (d)

Where

a) is a discount rate which gives a positive NPV

i.e 20% = $582

b) Is the difference between (a) and the rate which gives a

negative NPV

25% - 20% = 5%

c) Is the positive NPV at discount rate chosen in a) i.e

$ 582

d) Is the total range of NPV at rates chosen i.e +582 to –

322 = 904

Decision rule using IRR:

Where calculated IRR is greater than company’s cost of

capital then project is acceptable.

NPV and IRR compared:

a) Accept/reject decisions

114

-where projects can be considered independently of each

other and where the cashflows are conventional, then NPV

and IRR give the same accept/reject decision.

Accept project

Reject project

NPV positive NPV

negative NPV

IRR IRR above cost of capital

IRR below cost of capital

b) absolute and relative measures

NPV is an absolute measure of the return on a project

whereas IRR is a relative measure relating the size and

timing of the cashflows to the initial investment. Thus,

the NPV reflects the scale of a project whereas the IRR

does not.

e.g. Assume a project has the following cashflows:

year 0

year 5

project x -$20 000

+ $40 241

115

NPV @ 10% = $4990

IRR = 15%

Therefore, project is acceptable by both methods-assuming

10% is the cost of capital.

Now assume that the project is scaled by a factor of 10:

Year 0

year 5

Project 10x = 200 000

+402 410

NPV = 49 900

IRR = 15%

NPV clearly distinguishes between project x and project

10x whereas IRR remains unchanged at 15%.

c) Mutually Exclusive projects

This where only one of several alternative projects can

be chosen. Projects are ranked in order of attractiveness

and choice is made on the most profitable. In such

circumstances NPV and IRR may give conflicting rankings.

116

A property company wishes to develop a site it owns.

Three sizes of property are considered and costs and

revenues are as follows:

Year 0

year 1 to perpetuity

Expenditure

rentals per annum

$million

$million

small development 2

0,6

medium development 4

1

large development 6

1,35

The cost of capital is 10 % and it is required to rank

the projects by NPV and IRR and to select the most

profitable.

The projects are mutually exclusive because the building

of one size of development excludes the others.

117

Perpetuity = is a constant stream of cashflows without

end e.g. bonds give cashflow stream (yearly interest)

PV = C + C + C

1 +r ( 1 + r) ( 1 + r)

= C

r

NB ranking is preferred i.e. large development because it

leads to the greatest increase in wealth for the company.

Non-conventional cash-flows (the multiple rate problem)

Non-conventional cashflows –where cashflows vary;

opposite of conventional cashflows i.e. an initial

cashflow followed by a series of inflows.

e.g.

year 0 year 2 year 3

project x -2

000 +4 700 -2 750

project y +2

000 - 4 000 +4 000

Project x has 2 outflows and is thus no-conventional.

118

Project y has an outflow in a year’s time instead of

initially and is thus non-conventional.

When a project has non-conventional cash-flows it may

have:

i. One IRR

ii. Multiple IRRs

iii. No IRR

Multiple rates:

Project x =two IRRs at 10% and 25%

Project y =No IRR

NPV Method gives clear, unambiguous results

whatever the cash-flow pattern

Project x has positive NPVs at discount

rates between 10% and 25% and negative

NPVs at lower and higher rates. Project y

has a positive NPV at any discount rate.

NPV @ 0% = -50

NPV @ 10% = 0

NPV @ 15% = +10

119

NPV @ 25% = 0

NPV @ 30% = -14

Annuity:

This is a level of stream of regular payments that lasts for

a fixed number of periods.

PV annuity = C + C + C……..+

C

1+r 1+ r

1+r 1+r

PV annuity = C

Exercises:

1. Mr X has won a lottery paying $50 000 a year for twenty

(20) years. He is to receive his first payment a year

from now. If interest rate is 8%. What is the true

value of lottery?

2. A firm can generate net cash flows of $500 000 in the

first year and +$200 000 for each of the next five (5)

years . Calculate the Present Value.

120

3. A firm is considering a project with a cash outlay of

one million Zim.dollars now and a five (5) yearly cash

inflows of $500 000. What is the NPV at 10%?

4. What is the Net Present Value and Internal Rate of

Return of the following series at 10%

Year 0 1 2

3 4

Cash-flows -2 000 +800 +600

+700 +500

Draw a present value profile of the above. Is the

project acceptable at 10% cost of capital?

5. An entrepreneur is considering buying a freezit

making machine

Summary of NPV and IRR comparison:

NPV is technically superior to IRR and is simpler

to calculate

Where cash-flow patterns are non-conventional there

may be nil or several IRRs making the IRR impossible

to apply

121

NPV is superior for ranking investments in order of

attractiveness

With conventional cash-flow patterns both methods

give the same accept or reject decision

Where discount rates are expected to differ over the

life of the project such variations can be readily

incorporated into NPV calculations but not in those

for the IRR.

Notwithstanding the technical advantages of NPV over

IRR is widely used in practice so that it is

essential that students are aware of its inherent

limitations.

7.1.0. EXECUTING THE PROJECT WORK

PROJECT CONTROL – 3RD phase of project management cycle

Consists of

1. – monitoring progress o f each project item

2. – assessing its effects on the total project

122

3. – taking the necessary action on the critical items to

keep the project on the planned schedule.

7.1.1 Project control system and system design

Control of a project environment involves three operating

modes:

Measuring - determining progress through formal and

informal reports

Evaluating - determining the cause of deviations from

the plan and how to react

Correcting - taking actions to correct the situation

System design

Its purpose is to ensure that you and the team always have

information to make an accurate assessment of:

o What has happened and compare this with

o What should have happened according to the plans.

Controlling the project means managing the many problems

that arise to maintain the project schedule.

You do this on a day –to day basis through:

123

Monitoring the work – observing and checking what is

happening

Identifying and resolving the problems that arise

Tracking the project – comparing with the plan and

updating the records.

Good control of any process is dependent on accurate data-

keep project file up to date. This involves a regular check

and up date of:

Project organization chart

Stakeholder list

Key stage responsibility chart

Project brief

Key stage Gantt charts

Key stage work plan charts

Project risk log

Control system must be capable of providing information on:

Resource required –availability and its effective use

Equipment and machinery required and used

124

Materials used, ordered and required

Costs incurred to date and forward commitments

The results achieved – tasks completed

A valuation of the results- as expected

Monitoring ProgressMonitor:

- The team (talkings to them, holding meetings)

- The stakeholders (hold 1 to 1 meetings)

- Performance (checking activity)

Do this by MBWA, observe and have conversations.

Do this by written reports which provide a historical record

Tools to use: working with WBS

Use of Gantt chart/bar charts

Project status report

Good monitoring and tracking (measuring) builds team

confidence, anticipates problems and prepares future

success.

Taking corrective action:

1. rearrange work loads

2. put more effort into the job

125

3. put additional resources

4. more milestone date

5. lower scope /quality of results demanded.

Go through problem solving process p158 - 161

Regular progress meetings

essential part of project control process

keep your meetings to the point

focus the team on what must be done next not history

come up with an action list

project control is dependant on good communication

7.1.4. Project status report

a project status report is prepared on a regularly scheduled

basis(usually monthly)and reflects programme content in a

summary form.

Status of key project items

Assessment of key project items

Resolution of “troubled” areas

Difficulties anticipated in the work waiting to be done

Status report documents p50-55 spinner

126

- many include 3 documents

- cover letter

- executive highlights (listing, in a sentence or two)

- project summary

- bar chart

- project status

- milestone report

7.1.3. Cost Control Measures

Developing cost estimates

- Cost estimates for project activities are provided by

experienced personnel

- Sum total of project costs relate to cost estimates as

standards

- Usually cost associated with activities on the network

are reliable costs.

A completed bar chart timing schedule is a prerequisite to

developing a project cost schedule. You can use the WBS and

Gantt chart as the basis of collecting data.

Steps to develop a cost schedule

127

1. complete bar chart time schedule and add the cost value

of each activity to its corresponding bar.

2. calculate the cost per unit

3. tabulate cost schedule

7.15. Managing time

Time is the most valuable resource that, if lost or

misplaced is gone forever. There is need to convert

this constraint to a manageable resource

Barriers to effective time management.

- encourages good time management for:

self

the team

stakeholders

8.0 People problems and role of project manager

8.1.1 Qualities of a project manager

Role of a project manager is a complex role because of

involvement in a changing environment. It is a temporary

management role with specific responsibilities that are

linked only to the project.

Project manager has to balance the demands and needs of :

128

Customer

The project

The organization

The project team

Primary Responsibilities of a project manager include:

Selecting the core team with project sponsor

Identifying and managing project stakeholders

Defining the project and securing stakeholder

approval

Identifying and managing the risks

Allocating and securing resource commitments

Monitoring and tracking project progress

Solving the problems that interfere with progress

Controlling costs

Leading the project team

Informing stakeholders of progress status

Delivering the project deliverables and benefits

Managing the performance of everyone involved with

the project

8.1.2. Managing project stakeholders

129

Stakeholders are the people who have a specific and clearly

definable interest in the project. They have influence in

the management of the project as they provide some resources

e.g. line managers.

Other stakeholders include: (internal/external stakeholders)

- Your customers

- Your project sponsor

- Customer’s user group

- Finance department

- Production

- Marketing

- Personnel e.t.c

They need to be consulted and managed all stakeholders have

a hidden agenda about what they expect from your project and

you need to expose these expectations before you define the

project.

External stakeholders also have an interest in the project

Suppliers

Contractors

130

Consultants

Government or agencies etc

8.1.3 Projects and conflicts

Hopes, desire and needs of people across the organization as

well as outside players are often in compatible with each

other resulting in conflict where change takes place,

conflict is inevitable.

Most common types of conflict:

- resources

- equipment and facilities

- budgets and costs

- technical opinions

- priorities

- procedures

- responsibilities

- personality clashes

Some common causes for conflict1 diverse expertise in project team

2 low level of authority given to project leader

131

3 lack of understanding of project objectives by project

team

4 unclear or shared responsibilities

5 unclear schedules and performance targets for team

members

6 local interference from high level involvement

7 people do not like each other or do not get on together

in their worst

Conflict is good if it:-

- brings problems and issues out into the open for

discussion

- brings the team together, screening loyalty

- promotes creativity, generating new ideas and work

practices

- focuses people to give their work more detailed

analysis

Good conflict generates win-win relationship between

individuals, promoting sharing of information and improved

motivation.

132

Bad conflict- creates stress, stiring up negative feelings

- makes the working environment less pleasant

- surely reduces effectiveness of communication

processes

- interferes with coordination of effort between groups

and individuals

- encourages an automatic approval to working

Bad comfort generates a win-lose relationship between

individuals.

A team without conflict could be perceived as complaint and

lethargic with little creativity.

Projects and teamwork:

Successful teams do not just happen, they have to be built

through effective leadership and commitment.

Select your core team carefully

You want creative, enthusiastic people with a strong

sense of responsibility and commitment

133

A successful team consists of a carefully designed

mixture of right skills and personalities who can work

together without dissension and conflict.

Take positive actions to build the team

Regularly review the performance

Test team working

Encourage participation

9.0 USE OF COMPUTERS IN PROJECT

What can software do?Most software programmes are in project work designed around

some fundamental features that include:

Tabulating a list of tasks at different levels of the

WBS

Inputting duration data

Calculating critical path and float date

Deriving the Gantt chart

Deriving the logic diagram or Pert chart

On putting a list of resources

Assignment of resources by responsibility or capacity

Inputting of cost data as resources cost rates and

materials costs

134

Deriving a budget and cost curves

Scheduling the project based on input data

“what if” analysis of issues using a Gantt chart

reassignment of resources

identifying and correcting resource overloads

outputting a wide range of reports

Software programmes can be used for:

Graphics part - produces Gantt char t,logie diagram or

Pert chart

And graphics used for reporting

Spread sheet part – is used for the forms, table, reports

Database part - stores and manipulates the data

provided for

Calculations using the spread sheet

section to

Insert results into the tables,

charts, diagrams

Viewed on the screen.

Selecting project software:

135

Selection should not be based on price alone but includes

are view of :

past track record of performance

ease of use

compatibility with other software in use

stand alone or networked and availability

platforms available

features for planning and scheduling

features for control and updating

quality and eases of reporting

networking features-passwords , access restrictions etc

training available

helpline and back up available

Using a software programme

Steps:

open a new project file

insert project title, start date and project manager’s

name

set up the master calendar giving public and

organizational holidays

136

if possible design the specific formats for the tables

you require

input the project organization – the core team on a

resource listing

set up resource calendars – one for yourself and each

team members to show their available capacity for the

project, including holidays

input the list of key stages to a blank Gantt chart

assign responsibilities for the key stages –select by

responsibility

input the durations for each key stage

input dependencies between the key stages

programme calculates the critical path, the key stage

start and finish times and floats

Gantt chart produced, highlighting critical stages

Pert diagram produced

Table generated showing early and late start and finish

times with total float

Total project time is now available

137

Input cost data as resource lost rates and materials

costs for key stages

Operating budget cumulative curve calculated

Use “update mode” during implementation.

10.0 CLOSING, EVALUATING AND APPRAISING PROJECTS

Closure of projects does not happen, it must be planned

with care.

The date may relate to when a decision is to be made

concerning outside financing, when announcement of a

project to the press is planned, when a thorough

project review is scheduled on whatever.

Milestone scheduling indicates seluted dates by which

various phases of the entire project to be completed.

Milestones add detail to Gantt chart

Milestones serve as formal review points where

costs, progress and the need for replanning on

schedule modification can be reviewed.

138

Gantt chart shows the relationship between milestones

within the same task but not within different tasks.

Establish with customer and user group the criteria

they want to use to confirm completion. These must be

measured by agreed methods to avoid conflict

a) Acceptance process (handover) must be based on a

checklist agreed with customer and user group.

Acceptance process should identify customer

representative with authority to assign the project

completion report.

b) Hold a team meeting to review all tasks and present

completion report for approval and sign – off

c) Evaluate your project to learn what went well and what

went wrong.

PITFALLS IN PROJECT MANAGEMENT

Possible flaws relate to the following:

Foundations of the project [PITFALLS IN TOR]

139

a) Insufficient support for the project from the

company or its executives.

- project plans not aligned with business

plans: project must fit into the overall

plans for the company to avoid conflict

between the direction in which the company’s

management wants business to develop and the

way in which project work contributes to that

development.

- Half hearted support chokes project through

lack of necessary resources and decisions

b) Undefined principles and policies of project work

in terms of corporate and line management’s

responsibility for the project; whose

responsibility it is for committing resources;

what the policies are for making resources

available; what the tools and methods are to be

used for management of the project and how

coordination and cooperation are to be achieved?

140

c) Poor project definition

- Goals for project are imprecise affecting

adversely 4 phases to problem solving ie

Decision making

Decision taking

Implementation

Monitoring

- Undefined limits of scope (use milestone plan

and a clear responsibility chart.

- Unbalanced levels of ambition.

- Project manager has to balance technical

aspects, the right people and system

(physical products) using a milestone plan

(PSO project mind set)

(ii) Planning of Project

planning level is uniform: plan contains too

much detail for some users and too little for

141

others: use milestone plan at management

level and activity plan at task level.

Planning tools are too unwieldy

Planning range is psychologically unsound

Planning method discourages creativity and

encourages bureaucratic – democratic process,

free of jargon, tools and methods.

Planning of time and cost are over optimistic

Unrealistic, arbitrary plans.

Insufficient previous experience against

which to judge the work content.

Planning of resources overestimates their

competence and capacity.

Project calendar ignores lost time.

Plan omits activities: activity planning

(iii) PITFALLS IN ORGANISING

Alternative orgamisations for the project are not

considered.

- Distribution of responsibility is not defined

142

- Principles of cooperation are unclear

- Key resources are not committed

- Communication is poor

- Project manager is a technocrat, rather than

a manager

(iv) PITFALLS IN CONTROLLING

- purposes of control is not understood

(difference between monitoring and

controlling)

- plan and progress reports are not integrated

- no well defined formalized communication

between project managers and project members

- project manager has responsibility but no

formal authority

(v) PITFALLS IN EXECUTION OF PROJECT WORK

(PROFESSIONAL COMPETENCE OF PROJECT

MANAGER)

143

- complexity of coordinating a variety of

resources is under estimated

- changes to the plan or specification are

uncontrolled

- activities are not completed and documented

before others begin

- the targets of time , cost and quality are

unbalanced

DISCUSSION:

Review a project that has failed. Examine the reasons for

its failure. At what stage in the life cycle did this

occur? What lessons can future project managers learn?

144