Heathrow Project Management Analysis
-
Upload
westengland -
Category
Documents
-
view
4 -
download
0
Transcript of Heathrow Project Management Analysis
Project Management: Analysis of HeathrowTerminal 5
I. Introduction
London Heathrow Airport is one of the busiest airports in the
world (Burns, 2014). Heathrow airport was built to help improving thecountry economy and minimizing negative impacts on local communities
and environment (Heathrow Airport Limited, 2011). In September 2002,
Heathrow airport had a construction project to build another terminal
upon the existing four terminals, which was the terminal five. The
essential for a new terminal to enhance the ease of travel for
passengers all around the world and to reduce airport congestion
in the existing terminal 1, 2, 3, and 4. The project, particularly,took 19 years from inception to completion, and also, it took six
years to be constructed at a cost of 4.3 billion pounds (BBC, 2008).
The main player of the project was British Airport Authorities (BAA),
and the terminal was designed by Richard Rogers (BBC, 2008). According
to Fewings (2013), BBA is the major airport company with many
achievements in budget savings for over 50 airport projects with
its capability to reduce overall time and cost for 30%. The life
cycle of the project was between 1985 and 2008, and T5 was a new
mega airport structure in British history which was officially
opened on the 27th of March 2008 (Davies, Gann, and Douglas, 2009;
Doherty, 2008).
II. Literature Review
Heathrow terminal 5’s construction project was known as one of
the mega constructions, which involved more than 60 contractors,
and it was consisted of 16 major projects and 147 sub-projects
(sfuheathrowcase, 2010). The project covered a main terminal, two
satellite terminals, an air traffic control tower, and public
transport connection, with regard on environmental impact as well
as risk management. The facts and figures about the terminal arethat, first, there are 30,000 square meters of glass in wall; second,
there are 60 new aircraft stands; third, 13km of tunnels are bored for
baggage handling and rail links; fourth, most rainwater dropping on
the building will be recycled; finally, there are six new rail
platforms linked to the terminal (BBC, 2008). Heathrow’s terminal 5’s
project was an important project since it has immense impacts toward
economy and social benefits (Heathrow Airport Limited, 2011). Heathrow
terminal 5 was built to eradicate the passengers’ frustration due
to the Heathrow hassle (BBA Terminal 5 disaster, n.d). At first,
Heathrow terminal 5’s project was deemed to work well which was
on schedule and budget. On the other hand, two weeks after the
opening, Heathrow terminal 5 faced massive combination of
problems. With this combination of problems, Heathrow terminal
5’s project illustrates the gap of the project, which is very
fascinating. According to Toor and Ogunlana (2010), construction
project success criteria are based on Key Performance Indicators
(KPI) displaying the completion within time, within budget, and
within a set of objectives and stakeholders’ requirement.
Therefore, it is imperative to conduct a post review on some
important aspects of the project in order to fully comprehend the
success and failure of the project.
III. Research Objective
This report is intended to review the project of Heathrow
international airport particularly on Heathrow’s terminal 5.The
proposes of the review are:
-Frist, to critically discuss the success on how BAA could meet
the scope, schedule, cost and quality standard as referred in the
Generic Iron Triangle as the evaluation criterion for project
success.
-Second, to evaluate the project’s procurement management during
the operation, particularly on how BAA handled suppliers,
contractors and BA.
-Third, to assess the procedure and method of the BAA to counter
with the potentials risk during the construction.
-Fourth and finally, to offer justification and lessons learnt
from the success of the project.
IV. The Project Iron Triangle
First of all, the iron triangle was initially presented in the
1980s as a triangle of balanced requirement (Bruke, 2006). The
iron triangle is considered to help stakeholders to highlight and
specify the constrains-time, cost and quality-where stakeholders
can choose to emphasize one or more than one of that constrains
(Gardiner, 2005). The dimension of these criteria is definitely
vital for project accomplishment since it is a generic
measurement for most of the project. In this regard, the cost
management of the project that could meet the budget 4.3 billion
pound was done effectively, also, the time management,
scheduling, of the project to meet the deadline in six years
including seven months reserved period was well-timed (Doherty,
2008).
Yet, these Key Performance Indicators can be valued as basic
tangible factors within the T5 project as a whole, but this does
not include other contributing determinants behind this excellent
project outcome (Basu, Little, and Millard, 2009). Technically,
balanced scorecard purposes, capacity and application are
necessary to be recognized. For instance, the abilities to plan
and implement the project depict the success factors that help
T5’s project to be done on time and budge. Those abilities
consisted of system integration, support of integrated supply
chain, digital technology, productivity and safety, supplement of
material for speed and efficiency, and operational integration
and preparation (Davies, Gann, and Douglas, 2009). Furthermore,
JIT logistics were utilized to sustain an efficient schedule of
large volumes of construction materials, (Davies, Gann, and
Douglas, 2009). More importantly, to avoid more cost within the
project, BAA, initially, chose to run the program (Heathrow T5
whole project) itself (BAA: The T5 Project Agreement 2008).
In addition, the project was done with effective tools and
framework to meet the deadline and budget. The project started
with the earned values management which was the core of the whole
programme. The project was controlled and monitored by cost
performance indicators and schedule performance indicators which
together they created a key milestone for the project and helped
creating a clear and unambiguous path for the project (Doherty,
2008). Meanwhile, there were integrated baseline reviews which
were held every six months aiming to find out the gap of the
project and discuss the problems among project teams (Doherty,
2008). After the integrated baseline reviews, the mitigating a
cost was created to take advantage of all opportunities and to
take look at all potential risk. In this instance, total cost
management team was created in the project to look at ways to get
better deals with suppliers and to look what could not be built
and designed (Doherty, 2008). After the mitigating a cost, the
project team focused on the financial risk. The focus and the
approach £100 million from individual project budget (Doherty,
2008). Finally, the last approach to achieve time and cost
efficiency was the change-control process.
Besides, quality was another main aspect in judging the success
of the project. Basu (2014), exemplified that some projects were
delivered timely and on budget, but failed to meet the long term
benefit to end users or significant stakeholders; he added that
quality of project is what matches with customers’ expectation.
The quality of the project work was influenced by T5’s leadership
which urged individuals to understand what good quality looks
like (Doherty, 2008). Doherty (2008) suggested that there were
six golden rules to apply on the construction team in order to
manage quality work, particularly in T5 project. First of all,
terms and specification shall be agreed in the T5 project.
Second, create an examination plan and test plan to make sure
standardized works are done. Third, ensure that workforce have
the right skills to implement the plan. Fourth, check finished
works done by suppliers if they meet the standard requirement or
not. Fifth, quality audits need to be carried out. Particularly,
there were over 700 audits were carried out in T5 project to
address 2500 issues (Doherty, 2008). Finally, the handover of the
project.
V. Project Procurement Management
Since the T5 programme was a big construction programme, it is
imperative not to ignore the procurement strategy or management
styles adopted by BAA which to help enhancing the effective of
the works. Project procurement management concerns about
acquiring good and services from outside the performing project
team that are needed to operate the project’s scope of work
(Burke, 2006). The key players in T5 procurement strategy was
BAA, suppliers, contractors and BA. In T5 project, the BAA’s
procurement management approach was to have a relational contract
between BAA and all T5 first tier suppliers and junked the
traditional principle of construction contract (Caldwell,
Roehrich and Davies, 2009). In this regard, instead of pointing
out what could go wrong and spelling out the blame, the contract
was aimed to provide positive incentives in order to create
positive problem solving behavior among contractors (BAA: The T5
Project Agreement 2008). Moreover, the contracts’ strategy of T5
was that the contracts were incentivized based on a pooled fund
of the benefits gained which would be distributed after a
significant milestone was set (Caldwell, Roehrich and Davies,
2009). Specifically, Noel Gaffney from Mace stated in Doherty
(2008, pg.235) that ‘‘T5 agreement helps suppliers to make the right choice,
deliver for the T5 programme without worrying about the commercial implications.’’.
T5 agreement was claimed to be a ground breaking contract and it
was an effective approach for BAA since it tried to bring the
best out of client, suppliers and the teams to focuses on common
project’s objectives (Doherty, 2008). According to the case
study, BAA terminal 5 project, the structures of the T5 agreement
are, first, it is a delivery agreement that is legal actions and
condition of contract, second, identifying the skills and
capability and capacity that supplier can bring to T5 is
supplement agreement, lastly, the T5 agreement is supported by
document like commercial policy which describes commercial
environment and emphases on handling threat rather than evading
litigation. More importantly, in comparison with mainstream
construction contract, there are differences like in terms of
flexibility, the T5 agreement is flexible and it does not look
like conventional contract; integrated teams, the agreement helps
creating better relationship to ensure the desired outcome;
responsibility and liability, the contract differentiate clearly
between responsibility and liability; and the risk, BAA held the
risk and active risk management (Major Project Association, 2007)
(See figure1). Furthermore, the management issue by having the
flexible commercial contract between stakeholders in response to
the uncertainties is justified with a model of having insurance
policy and incentive scheme with business contractors that could
really alleviate the risk (Norris, 2007).
Figure 1
Source: (Major Project Association, 2007, pg.4)
Besides, to embrace the best procurement strategy, the BAA’s
procurement team designed the twelve procurement processes that
move away from the traditional contractor’s approach which
squeezes the supply chain on cost and which usually involves only
one or two preferred suppliers (BAA Heathrow, 2004). The twelve
procurement processes which were used in the T5 construction
project are to obtain technical information, pre-qualify
suppliers, acquisition plan, prepare tender enquiry, issue
tender, mid-bid interviews, evaluate bids, suppliers’
presentations, recommendation, place orders, feed backs and
operations (BAA Heathrow, 2004).
With regard to the project stakeholders, there are 43 different
stakeholders (Doherty, 2008) including British Airways (BA),
first tier suppliers, and first tier contractors, and BA was
unquestionably the main stakeholder. It is believed that it is
essential to see financial auditing review agreement between BAA
and the suppliers and its communication and trial testing with
BA. (Davies and Brady, 2007). This Auditing Review theory can be
perceived from a conflict management with regard of collaborating
style of Conflict Resolution theory. Hence, with all these
strategies deployed by BAA, they provide an important lesson that
comes from the contractual relationship among stakeholders; so
without this groundbreaking agreement, BAA could not have
productively completed the project on time and on budget.
VI. Risk Management
Risk management is one of the main aspect to be considered when
projects are carried out. According to Burke (2006), the key
component of the project is making decision, which associated
with the level of uncertainty that leads to risk. Specifically,
project risk management is “the systematic processes of identifying, analyzing
and responding to project risk” (Bruke, 2006, pg. 253). Therefore, since
Heathrow terminal 5 was a mega construction project that involved
plenty of decision-making processes, it is essential to assess
the project’s risk management model in order to understand how
effective and efficient when risks were handled in the project.
Constructing Heathrow terminal 5 required large amount of capital
and budget; therefore, there was a huge financial risk for BAA to
deal. In Davie, Gann, and Douglas (2009) article states that the
client, BAA, had learnt from its experiences and found that
fixed-price or Private Finance initiative (PFI) caused the poor
performance. Thus, to manage the failure, increase performance
and reduce risk, BAA introduced the T5 agreement which was
associated with procurement management (Deakin and Koukiadaki,
2009). Yet again, T5 agreement was an important legal document
which allowed BAA to manage its suppliers and contractors
effectively. More importantly, this agreement could give an equal
share of risk taking with its suppliers, contractors, and the
rest to BAA itself as a client. In relation to uncertainty
management theory, in response to risk and future uncertainty, T5
Agreement could be linked to risk mitigation and risk deflection
from the four main risk responses.
In terms of contracting, BAA’s T5 agreement is a cost plus
incentive contract which designed to deflect risk (Davies, Gann,
and Douglas, 2009). The cost plus contract is deemed to be the
most flexible type of contract in which the client pays the
constructor the costs incurred plus a pro t margin (Burke,fi
2006). On the other hand, unlike mainstream cost plus contract
where risks are shared between client and contractors, BAA took
full responsibility for this risk and operated collaboratively in
integrated project teams with rst-tier suppliers to generatefi
inventive solutions (Davies, Gann, and Douglas, 2009). In
terminal 5 project, BAA sought to find and expose risks, then
motivate and incentivize parties to perform their best to address
and evade risks with creative and inventive approaches and
solution. Also, BAA’s study concluded that ‘‘transferring the risk to the
contractor offered no real protection for the client’’, and ‘‘the only way to succeed on
T5 was to change the “rules of the game” by establishing a new governance structure
and commercial principles embodied in the T5 Agreement’’ (Davies, Gann, and
Douglas, 2009, pg. 115).
Specifically, to avoid technological risks, BAA used only mature
technology during the integration of system in order to ensure a
smooth run at the final stage of the project (Brady and Davies,
2010). Also, to circumvent big surprise and risk from unproven
technologies, BAA conducted a test to have those technologies
installed in different environment, smaller airport (Brady and
Davies, 2010). Moreover, to avoid the delay risk to the entire
project from the failure to complete one component, BAA used
‘‘pre-assembly and pre-fabrication’’ techniques to allow
suppliers to produce, bring together and examine components and
rehearse the installation process before taking to T5 project’s
site (Davies, Gann, and Douglas, 2009). To recap, with the T5
agreement and different approaches, the T5 project was seemed to
work well, BAA were able to manage the potential risks
effectively and efficiency.
VII. Conclusion
Heathrow terminal 5 project has shown and provided project
managers and researchers numerous of lessons. One of the main
lessons learnt is the adoption of Balanced Scored Card as a key
performance indicator within the Iron Triangle criteria (Basu,
Little, and Millard, 2009). Alternatively, understanding and
knowing the method of how BAA handled and adjust the procurement
systems, T5 agreement, and how they evaded risks with noble
approaches are an absolute benefit and such an important
information and experience to learn about. In this regard, from
the T5 agreement is learnt that the innovation was the key
component in the agreement where was ‘‘no blame’’ culture of
project which contributed as one of the key success factors
(Caldwell, Roehrich and Davies, 2009). Also, it is learnt that
BAA had adopted many innovative and creative approaches to
facilitate the construction project, and especially, BAA had come
up with numerous of strategies to manage the potential risks in
the project. By this means, those strategies and approaches
embraced by BAA had made this mega construction, Heathrow
Terminal 5, become a successful one.
In conclusion, Terminal 5 Project is determined to be both
successful and fail over the result their planning and heading
over stage. Conversely, when analyzing the project as whole,
Heathrow terminal 5 project was a successful one which was
completed on time with appropriate amount of budget. BAA executed
project effectively by having strong and innovative leadership;
moreover, BAA ran the project with experiences which allowed them
to create practical strategy to finish the project (Doherty,
2008).
References
-BAA Heathrow. (2004) T5 Buy Club: How M&E Contractors Pool Purchasing at Heathrow Terminal 5. Available from: http://www.constructingexcellence.org.uk/pdf/case_studies/t5_buy_club_20040916.pdf [Accessed 17 July 2014].
- BAA: The T5 Project Agreement (2008) Available from: https://research.mbs.ac.uk/infrastructure/Portals/0/docs/BAA%20The%20T5%20Project%20Agreement%20A%20Online.pdf [Accessed 18 July 2014].
-Basu, R., Little, C., and Millard, C. (2009) Case Study: A FreshApproach of the Balanced Scorecard in the Heathrow Terminal 5 Project. Measuring Business Excellence [Online]. 13 (4). Pp. 22-33. [Accessed 03 April 2014].
-BBC (2008) Queen opens new Heathrow Terminal. Available from: http://news.bbc.co.uk/1/hi/uk/7294618.stm [Accessed 19 July 2014].
-Brady. T., and Davies, A. (2010) from Hero to Hubris – Reconsidering the Project Management of Heathrow’s Terminal 5. International Journal of Project Management [Online]. 28(2010). Pp. 151-157. [Accessed 03 April 2014].
-Burke, R. (2006) Project Management: Planning and Control Techniques. 5th end. China: Burke Publishing.
-Burns, J. (2014) TOP 10 AIRPORTS: PASSENGER TRAFFIC IN 2013 [Online].Available from:http://www.airport-world.com/home/general-news/item/3674-top-10-airports-passenger-traffic-in-2013 [Accessed 20 July 2014].
-Brady, T., Davies, A., Gann, D. and Rush, H. (2006) Learning to manage mega projects: the case of BAA and Heathrow Terminal 5. Learning to Manage Mega Projects: The Case of BAA and Heathrow Terminal 5 [online].
-Caldwell, N.D., Roehrich, J.K. and Davies, A.C. (2009) Procuringcomplex performance in construction: London Heathrow Terminal 5 and a Private Finance Initiative hospital. Journal of Purchasing and Supply Management [online]. 15 (3), pp.178-186.
-Davies, A., Gann, D. and Douglas, T. (2009) Innovation in Megaprojects: SYSTEMS INTEGRATION AT LONDON HEATHROW TERMINAL 5. California Management Review [online]. 51 (2), pp.101-125.
-Davies, A and Brady, T. (2007) From Hero to Hubris –Reconsidering the Project Management of Heathrow’s Terminal 5.ELSEVIER [online]. 28, pp. 151-157. [Accessed 11 March 2013].
-Deakin, S. and Koukiadaki, A. (2009) Governance Processes, Labour–Management Partnership and Employee Voice in the Construction of Heathrow Terminal 5. Industrial Law Journal [online]. 38 (4), pp.365-389.
-Doherty, S. (2008) Heathrow's Terminal 5 [online]. illustrated edition ed. US: John Wiley & Sons Ltd.
-Fewings, P. (2013) Construction Project Management. 2nd ed. USA and Canada: Routledge.
-Gardiner, P.D. (2005) Project Management, A Strategic Planning Approach. London: Palgrave Macmillan.
-Heathrow Airport Limited (2011) Towards a Sustainable Heathrow. Available from: http://www.heathrowairport.com/static/Heathrow/Downloads/PDF/Afocusontheeconomy.pdf [Accessed 20 July 2014].
-Major Project Association (2007) T5 Case Study. Available from: http://www.majorprojects.org/pdf/seminarsummaries/136summaryT5.pdf [Accessed 18 July 2014].
-Norris, B. (2007) Best Practices Improve Project Performance. Business Insurance [Online]. 41 (43) [Accessed 11 March 2014].
-Sfuheathrowcase (2010) Heathrow Terminal 5 Case Study. Available from: http://sfuheathrowcase.wordpress.com/ [Accessed 17 July 2014].
-Toor, S., U., R., and Ogunlana, S., O. (2010) Beyond the ‘IronTriangle’: Stakeholder Perception of Key Performance Indicators(KPIs) for Large-Scale Public Sector Development Projects.International Journal of Project Management [Online]. 28(2010). Pp. 228-236. [Accessed 23 July 2014].