Probabilistic dynamic multi-objective model for renewable and non-renewable distributed generation...
-
Upload
grenoble-inp -
Category
Documents
-
view
2 -
download
0
Transcript of Probabilistic dynamic multi-objective model for renewable and non-renewable distributed generation...
Probabilistic Dynamic Multi-objective Model for Renewable and
Non-renewable DG Planning
Alireza Soroudi∗,a,b, Raphael Cairea, Nouredine Hadjsaida, Mehdi Ehsanb
aGrenoble Electrical Engineering Laboratory (G2Elab), Saint Martin d’Heres, France.bElectrical Engineering Department of Sharif University of Technology, Tehran, Iran.
Abstract
This paper proposes a probabilistic dynamic model for multi-objective distributed gen-
eration planning which also considers network reinforcement at presence of uncertainties
associated to the load values, generated power of wind turbines and electricity market
price. Monte Carlo simulation is used to deal with the mentioned uncertainties. The
planning process is considered as a two-objective problem. The first objective is the min-
imization of total cost including investment and operating cost of DG units, the cost
paid to purchase energy from main grid and the network reinforcement costs. The sec-
ond objective is defined as the minimization of technical risk, including the probability
of violating the safe operating technical limits. The Pareto optimal set is found using
NSGA-II method and the final solution is selected using a max-min method. The model
is applied on two distribution networks and compared with other models to demonstrate
its effectiveness.
Key words: Stochastic uncertainty modeling, Distributed Generation, wind turbine,
Pareto optimality, Technical risk, Monte Carlo Simulation
1. Introduction
1.1. Motivation
The role of Distributed Generation (DG) units has become much more important with
the deregulation of power industry. These units have been become an interesting option
for Distribution Network Operators (DNOs) to meet the requirements of their customers.
∗Corresponding authorEmail address: [email protected] (Alireza Soroudi)
Journal
Investments in distributed generation enhances the environmental and technical benefits of
DNOs [1]. Thus, there is a clear need to enhance the current DG planning methodologies
to include an appropriate treatment of various DG technologies and uncertainty handling.
This need motivates the work proposed in this paper.
1.2. Literature review
The existing works of the literature dealing with DG planning problem have consid-
ered many of its technical and economical aspects. These aspects are as follows: emission
reduction [2], active loss reduction [3, 4], reducing the cost of curtailed energy [5], in-
creasing the reliability of power supply [6], voltage profile improvement [7, 8], reducing
the risk of overloading the distribution feeders [9], maximizing the DG penetration level
[10], enhancing the social sustainability [11], reducing the construction period [12] and
reducing the cost of energy purchased from power market [13]. The DG planning prob-
lem has a multi-objective structure. The Pareto optimality concept can be used to deal
with the multi objective problems in which the objective functions are incommensurate
(see Appendix for more details). The multi-objective models proposed in the literature
are either static or dynamic. The static models assume that all investments are done at
the beginning of the planning horizon while the dynamic ones consider the timing of the
investment decisions. The importance of dynamic planning is that the value of money
changes with time and if DG units can postpone some network investment. In [5], a static
multi-objective model is proposed which considers the cost of investment and operation,
cost of energy purchased, cost of energy losses and the cost of energy not supplied. This
model does not consider the uncertainties. The static models of the literature which con-
sider the uncertainties are either use fuzzy arithmetic [14] or probabilistic modeling [15]
or a mixed probabilistic-possibilistic method [16]. In [13], a dynamic model is proposed
for integration of DG units in distribution networks but it does not consider the reinforce-
ment of network along with DG investment. The authors have already proposed dynamic
models [2, 9], which considers simultaneous DG and network investment but do not deal
with the uncertainties associated to the DG planning problem. The gap that this paper
tries to fill is considering the uncertainties of input variables in addition to simultaneous
consideration of DG and network investment.
2
1.3. Contributions
This paper proposes a multi-objective model for determining the optimal sizing, locat-
ing and investment timing in DG units and network which is not only dynamic but also
considers the presence of uncertainties associated with different parameters. The Monte
Carlo simulation is used to deal with the effects of uncertainties of stochastic wind power
generation, electricity market price and load values on technical and economic issues of
the planning problem.
1.4. Paper organization
In Section 2, the problem formulation is described. The proposed solution algorithm
is presented in section 3. In section 4, the proposed model is applied on a distribution
system and the simulation results are given and discussed. Finally, the conclusions are
given in section 5.
2. Problem formulation
2.1. Decisions variables
The decision variables are the number of non-renewable DG units and wind turbines,
to be installed in bus i in year t, i.e. ξdgi,t ,ξwi,t, respectively; the binary investment decision
in feeder ℓ in year t, i.e. γℓt , and finally the number of installed HV/MV transformers in
year t, i.e. ψtrt . The constraints and the objective functions are described as follows:
2.2. Uncertainty modeling
In this work three major uncertain parameters including load value, wind turbine
generated power and the energy price from the main grid are considered. The modeling
of these parameters is described as follows:
2.2.1. Load
The daily load variation over the long-term is modeled as a load duration curve with
Nh demand levels where in each demand level, i.e. h, a DLFi,t,h is associated which shows
its average magnitude. The uncertainty of DLFi,t,h is modeled using a normal probability
density function (PDF). Assuming a base load of SDi,base in the first year of the planning
3
horizon and a demand growth rate, i.e. α, the apparent demand in bus i, in year t and
in demand level h, in each Monte Carlo experiment, i.e. e, is calculated as follows:
SD,ei,t,h = SD
i,base ×DLF ei,t,h × (1 + α)t (1)
Each DLF ei,t,h is calculated as follows:
DLF ei,t,h = µD
i,t,h + λD,ei,t,h × σD
i,t,h (2)
where λD,ei,t,h is a random variable generated for demand in bus i, in year t, demand level
h and each Monte Carlo experiment, i.e. e, using a normal PDF with a mean of 0 and a
standard deviation of 1. The forecasted values of demand level factors and their standard
deviations are µDi,t,h and σD
i,t,h respectively. For simplicity, it is assumed that all buses
follow the same load duration curve but it would not affect the generality of the proposed
framework.
2.2.2. Wind turbine generation
The generation schedule of a wind turbine highly depends on the wind speed in the
site. The variation of wind speed, i.e. v, can be modeled using a Weibull PDF and its
characteristic function which relates the wind speed and the output of a wind turbine
[16].
PDF (v) = (k
c)(v
c)k−1exp(−(
v
c)k) (3)
where k is the shape factor and c is the scale factor of the Weibull PDF of wind speed in
the zone under study.
The generated power of the wind turbine is determined using its characteristics as follows:
Pwi,t,h =
0 if v ≤ vcutin or v ≥ vcutout
v−vcutin
vrated−vcutin
Pwi,r if vcutin ≤ v ≤ vrated
Pwi,r else
(4)
where Pwi,r is the rated power of wind turbine installed in bus i, Pw
i,t,h is the generated
power of wind turbine in bus i and demand level h, vcutout is the cut out speed, vcutin is the
cut in speed and vrated is the rated speed of the wind turbine.
4
2.2.3. Electricity market price
The price of electricity purchased from the main grid is determined by market oper-
ation. This value changes during each demand level. The variation of this quantity is
modeled by a peak price, i.e. ρ, multiplied by a factor named Price Level Factor, i.e.
PLFt,h. Price Level Factors are uncertain due to the behaviors of the market players.
The spot price is considered to follow normal PDF [17], as follows:
PLF et,h = µρ
t,h + λρ,et,h × σρt,h (5)
where µρt,h and σρ
t,h are the forecasted value of price level factor and its standard deviation,
respectively. λρ,et,h is a random variable generated for electricity price in year t, in demand
level h and Monte Carlo experiment, i.e. e, using a normal PDF with a mean of 0 and a
standard deviation of 1.
2.3. Constraints
The constraints that should be satisfied in each Monte Carlo experiment are described
in this section, as follows:
2.3.1. Power flow equations
The power flow equations must be satisfied in each Monte Carlo experiment, i.e. e, in
each demand level h and year t, is as follows:
−PD,ei,t,h +
Ndg∑
dg=1
P dgi,t,h +
Nw∑
w=1
Pw,ei,t,h = V e
i,t,h
Nb∑
j=1
Y tijV
ej,t,hcos(δ
ei,t,h − δej,t,h − θtij) (6)
−QD,ei,t,h +
Ndg∑
dg=1
Qdgi,t,h +
Nw∑
w=1
Qw,ei,t,h = V e
i,t,h
Nb∑
j=1
Y tijV
ej,t,hsin(δ
ei,t,h − δej,t,h − θtij)
where PD,ei,t,h, Q
D,ei,t,h, , are the active and reactive power demand, respectively. The P dg
i,t,h,
Qdgi,t,h are the active and reactive power generated by DG units, respectively. The Pw,e
i,t,h,
Qw,ei,t,h are the active and reactive power generated by wind turbine units in Monte Carlo
experiment e, respectively.
P grid,et,h = Vslack,t,h
Nb∑
j=1
Y tijV
ej,t,hcos(δ
ei,t,h − δej,t,h − θtij) (7)
Qgrid,et,h = Vslack,t,h
Nb∑
j=1
Y tijV
ej,t,hsin(δ
ei,t,h − δej,t,h − θtij)
5
where P grid,et,h and Qgrid,e
t,h are the active and reactive power imported from the grid, in year
t and demand level h for Monte Carlo experiment e.
2.3.2. Operating limits of DG units
Each DG should be operated considering its resource limits, i.e.:
P dgi,t,h ≤
t∑
year=1
ξdgi,year × Pdg
lim (8)
Pdg
lim is the operating limit of dg technology in MW.
The power factor of DG unit is kept constant in all demand levels [18] as follows:
cosϕdg = Const. (9)
2.4. Objective functions
The objective functions are formulated and described in this section, as follows:
2.4.1. Technical Risks
The first objective function is the technical risk. In each Monte Carlo iteration, the
following two operating limits are checked: voltage limits and thermal limits of feeders.
If any of these limits is violated it is considered as a technical risk in the network. These
limits are explained as follows: The voltage of each bus in each demand level h and in each
year t and Monte Carlo experiment e, should be kept within the safe operating limits.
Vmin ≤ V ei,t,h ≤ Vmax (10)
Vmin and Vmax are the minimum and maximum permissible limits of voltage, respectively.
To maintain the security of the feeders and substation, the flow of current passing through
them should be kept below their thermal limit. The thermal limits of existing feeders and
substation are Iℓ and Str, respectively where these limits change if any investment is done
in feeder ℓ or substation transformer until year t. This constraint is described as follows:
Ieℓ,t,h ≤ Iℓ + Capℓ ×t
∑
year=1
γℓyear (11)
Sgrid,et,h ≤ Str + Captr ×
t∑
year=1
ψtryear
6
where Capℓ, Captr are Capacity limit of added feeders and transformers, respectively.
The number of experiments in which at least one of the two constraints (10) or (11) is
violated, is recorded as NRt,h. The technical risk in year t, denoted by TRt, is defined
as the average of technical risk over different demand levels. Here, the duration of each
demand level, i.e. τh, is used as a weighting factor as follows:
TRt =
∑Nh
h=1NRt,h
NEt,h× τh
∑Nh
h=1 τh(12)
The objective function to be minimized is proposed here as the weighted average of
maximum yearly technical risk and its average value over the planning horizon as:
OF1 = w1 maxt
(TRt) + w2
T∑
t=1
TRt
T(13)
where w1,2 will be specified by the planner in order to control the importance of sever-
ity and average value of technical risks. By minimizing the OF1, the algorithm tries to
simultaneously improve the overall satisfaction of the technical network constraints, rep-
resented by 1T
∑Tt=1 TRt, and the severity of technical dissatisfaction over the planning
horizon, represented by maxt(TRt).
2.4.2. Total costs
The next objective function, i.e. OF2, to be minimized is the total costs including the
cost of electricity purchased from the main grid, investment and operating costs of the
DG units and also reinforcement costs of distribution network. As it will be described in
section 3.1, in each year t and each demand level h, Monte Carlo simulation is done for
NEt,h experiments and cost of purchasing electricity from the grid in demand level h and
year t, in Monte Carlo experiment e, is determined as follows:
GCet,h = PLF e
t,h × ρ× P grid,et,h × τh (14)
where τh is the duration of demand level h.
The expected value of GCt,h until experience, e, is calculated as follows:
GCe
t,h =
∑em=1GC
mt,h
e(15)
7
The number of required experiments for convergence of GCe
t,h is known as NEt,h then
total grid cost, i.e. TGC, is calculated as follows:
TGC =T∑
t=1
Nh∑
h=1
GCNEt,h
t,h × (1
1 + d)t (16)
where d is the discount rate and T is the planning horizon. The total operating costs of
the DG units, i.e. DGOC, is calculated as:
DGOC =T∑
t=1
Nb∑
i=1
Ndg∑
dg=1
Nh∑
h=1
τh × (OCw × Pwi,t,h +OCdg × P dg
i,t,h)× (1
1 + d)t (17)
where OCdg and OCw are the operating cost of non-renewable and wind DG technologies,
respectively. P dgi,t,h is the active power generated by DG unit in bus i, year t and demand
level h. Ndg is the number of DG technologies considered for planning.
The total investment cost of the DG units, i.e. DGIC, is calculated as:
DGIC =T∑
t=1
Nb∑
i=1
Ndg∑
dg=1
(ξwi,t × ICw + ξdgi,t × ICdg)× (1
1 + d)t (18)
where ICw, ICdg are the investment cost of non-renewable and wind DG technologies,
respectively. The number of buses in the network is denoted by Nb.
The reinforcement cost of the distribution network is the sum of all costs paid for installa-
tion and operation of new feeders and transformers. The total feeder reinforcement cost,
i.e. LC, and substation reinforcement cost, i.e. SC, are calculated as follows:
LC =T∑
t=1
Nℓ∑
ℓ=1
Cℓ × Lℓ × γℓt × (1
1 + d)t (19)
SC =T∑
t=1
Ctr × ψtrt × (
1
1 + d)t
where Cℓ is the cost of feeder reinforcement for feeder ℓ in $/km and Ctris the cost of
transformer investment. Lℓ is the length of newly added feeder in km.
Thus, OF2 is defined as:
OF2 = LC + SC +DGIC +DGOC + TGC (20)
It should be noted that in (20), the mean values of TGC and DGOC are added to invest-
ment cost of DG units and also the network reinforcement costs.
8
3. The proposed method
In this section, first the concept of Monte Carlo Simulation method is described and
then the fundamentals of multi-objective optimization and the solution methods are given,
as follows:
3.1. Monte Carlo simulation
The Monte Carlo Simulation (MCS) is a tool for simulating the behavior of uncertain
parameters which have probabilistic nature. This means there exists a Probability Density
Function (PDF) that describes the behavior of these parameters. The main concept
of MCS method is described as follows: suppose a multi variable function, namely y,
y = f(x1, ..., xn), in which x1 to xn are random variables with their own PDF. The
problem is, knowing the PDFs of all input variables, i.e. x1 to xn, how the PDF of y can
be obtained? The concept of MCS is obtaining the PDF of ye using the PDFs of input
variables xi using the following steps [19]:
Step 1. e = 1, Avg = {}.
Step 2. For each input variable xi, generate a value, i.e. xei , using its PDF.
Step 3. Calculate ye using ye = f(xe1, ..., xen)).
Step 4. Calculate Ye =1e
∑em=1 ym
Step 5. Store Ye in Avg.
Step 6. Check if Ye is converged then go to step (7); else e = e+ 1 then go to step (2).
Step 7. End
At the end of these steps, the PDF of the output function, y, is estimated as a normal
PDF [20] with a mean and standard deviation calculated as follows:
µy = µYe(21)
σy =
√
∑em=1 (ym − µy)2
e
3.2. The two stage solution method
As it is already described in Section 1.1, the DG planning problem has a multi-objective
structure. In multi-objective problems, the decision maker (planner) tries to find Pareto
9
optimal set of solutions (please see Appendix). To solve the problem formulated in section
2, a two-stage solution algorithm is proposed, in which the first stage finds the Pareto
optimal front and in second stage helps the planner to find the best solution, as follows:
3.2.1. Stage I: finding Pareto optimal front using NSGA-II
This work uses the Non-dominated Sorting Genetic Algorithm (NSGA-II) proposed
in [21]. The mechanism of this algorithm is described as the following steps:
Step 1. Randomly create an initial population with the size Np.
Step 2. Using the crossover and mutation operators of GA [22] on the current population
creat a population with the same size. Construct the mixed population with the
size of 2Np.
Step 3. Calculate OF1 and OF2 for each solution using (1) to (20).
Step 4. Find the Pareto optimal front for each solution, i.e. Xn using (27) and (28).
Step 5. Calculated the crowding distance, i.e. CDn, using (22).
CDn =
NO∑
k=1
LDkn
NO
(22)
where LDkn is the local diversity of solution n in Pareto front k. It is defined
as the distance between the given solution and its nearest neighbors in a given
Pareto front, as follows:
LDkn =
|fk(Xn+1)− fk(Xn)|+ |fk(Xn)− fk(Xn−1)|
2MDk
(23)
where Xn+1 and Xn−1 are the two solutions in neighborhood of Xn, when all
of the solutions are sorted, regarding the objective function k. The maximum
distance of solutions in the Pareto front is obtained as follows:
MDk =2NPmaxn=1
(fk(Xn))−2NP
minn=1
(fk(Xn)) (24)
In order to maintain the diversity of solutions in Pareto optimal front, in minimum
and maximum solutions of the given front will be assigned with the biggest local
diversity, calculated as follows:
LDk2NP
= LDk1 = max
n(LDk
n) (25)
10
Step 6. Generate the next population using the solutions of lower fronts up to size Np. If
all solutions are from the same front, choose the solution with the lower CDn.
Step 7. iter=iter+1.
Step 8. If iter < itermax go to Step 2, else go to Step 9.
Step 9. End
3.2.2. Stage II: Final solution selection
The next step after finding the Pareto optimal solutions, is to select the best solution.
In this paper, max-min method [14, 23] is used. For each solution Xn, the value of
fmaxk
−fk(Xn)
fmaxk
−fmink
is calculated which shows the ability of solution Xn in minimizing objective
function fk.NPmaxn=1
{
NO
mink=1
{
fmaxk − fk(Xn)
fmaxk − fmin
k
−µrefk
}}
(26)
where fmaxk and fmin
k are maximum and minimum values of the objective function k,
in solutions of Pareto optimal set. The µrefk is the minimum required satisfaction for
objective function k which is determined by the planner according to its requirements.
This means that the ability of each solution in minimizing every objective function is
checked and then it is compared to the minimum satisfaction requirement of the planner
thus the solution which its minimum success in minimizing all objectives is maximum will
be chosen as the best solution.
4. Simulation results
In this section, the proposed methodology is applied to two distribution networks.
The first one is a 9-bus test system and the second one is a real large scale 574-node
distribution network.
4.1. Assumptions
The forecasted load and price duration curve are depicted in Fig. 4. The dura-
tion of each demand level, τh, is assumed to be 365 hr. The other simulation as-
sumptions are presented in Table 1. The proposed framework enables the planner to
consider various DG technologies. In this paper, without loss of generality, only gas
and wind turbines are considered. The gas turbine (GT) has the investment cost, i.e.
11
ICdg = 500000$/MV A, and operating cost, i.e. OCdg = 50$/MWh [24] and wind tur-
bines (WT) have ICw = 1227000$/MV A, OCw = 45$/MWh with the capacity of 1 MVA.
The capacity of substation transformers, i.e. Captr, that can be added to the substation
is 10 MVA and the cost of each transformer, i.e. Ctr, is 0.2M$. The cost of reinforcement
for each feeder, i.e. Cℓ is 0.15M $/km[24]. The planning horizon is assumed to be 8 years.
4.2. Case-I: 9-bus distribution network
The proposed method is applied on a 132/33 kV 9-bus distribution network which is
shown in Fig.3. The technical data of this network can be found in [2].
4.2.1. Choosing the best solution
• In this case, the best solution is found assuming that µrefk=1,2 = 0, this means that
none of the objective functions is more important than the other one. The best
solution is found using the (26) and the value of objective functions for this solution
is OF1 = 0.11 and OF2 = 6.73 × 107$. The planning scheme for this solution is
given in Table 2.
• In this case, it is assumed that one of the objective functions is more important
for the planner. For example, the planner is looking for a solution in which the
technical risk is more minimized. The best solution is found assuming that µrefk=1 =
0.9, µrefk=2 = 0, this means that the best solution will be chosen from the part of
Pareto front which its solutions have more than 90% satisfaction in minimizing the
OF1. The best solution is found using the (26) and the value of objective functions
for this solution is OF1 = 0.02 and OF2 = 6.90 × 107$. The planning scheme for
this solution is given in Table 3.
4.2.2. Comparing the proposed model with other methods
The proposed dynamic model is coded in MATLAB and solved using the NSGA-II
method, Simulated Annealing (SA) [25] and also Particle Swarm Optimization (PSO) [26]
and static model. The static model is totally similar to the dynamic model except that all
investments are obliged to be done at the beginning of the planning horizon. The number
of Pareto optimal solutions found by the proposed model is 16 where the variation ranges
12
of objective functions are given in Table 4. The Pareto optimal front obtained by each
model is depicted in Fig. 5. The solutions found by the proposed model dominate the
solutions of other methods. This means that for every solution in other fronts there exists
at least one solution in the Pareto optimal front of the proposed model which has the less
objective functions compared to it.
4.3. Case-II: 574-node real distribution network
The second case is a 20-kV, 574-node distribution system, depicted in Fig.6, which
is extracted from a real French urban network. This system has 573 sections with total
length of 52.188km, and 180 load points. This network is fed through one substation.
These data have been extracted from reports of Electricite de France (EDF) [27] and
more details can be found in [28]. The Pareto optimal front is found using the method
described in Section 3.2 and depicted in Fig.7. The objective functions of each solution are
described in Table 6. Using the (26) the best solution is #10 since it has the maximum
of minimum minimizing satisfaction (according to Table 6. The characteristics of this
solution are given in Table 7 and Table 8. In Table 7, the investment costs including DG
and network investments are specified as well as the timing of the investment decision. The
comparison between the selected solution and the solution #1 (no technical risk) shows
that for decreasing teh technical risk from 0.0063 (in solution # 10) to 0 (in solution #
1) the planner should pay 112507469.7004 − 96867855.5489 = 1.563 × 107$ more. This
clearly shows the benefit of the proposed algorithm. In Table 8, the timing of investment
and also the optimal location of DG units are given for both of the wind and gas turbine
technologies.
4.4. Advantages and disadvantages of the proposed method
4.4.1. Advantages:
The advantages of the proposed solution method are as follows:
• It determines the optimal timing, location and DG technology for a given distribu-
tion network.
13
• The uncertainties of renewable DG technologies (like wind turbine), electric loads
and electricity prices are modeled and their impacts have been investigated.
• The Pareto optimal front found by this method dominates the Pareto front found
by other methods.
• The algorithm can help the planner to determine how much should be paid for
reducing the technical risks.
4.4.2. Disadvantages:
One of the major drawbacks of the proposed method is its computation burden which
increases with the size of the network and also the number of uncertain variables. Al-
though it is always interesting to increase the computational performance of the algorithm
but since the planning models are usually off line, this would cause no severe problem.
Another method for handling the uncertainties is scenario based modeling [29]. If the
number of scenarios is too high then scenario reduction method can be applied to reduce
the computational burden while maintaining the accuracy [30, 31].
5. Conclusion
The proposed planning model considers the DG option and network investment si-
multaneously and provides the DNO a set of Pareto optimal solutions. The dynamic
nature of the proposed model and its ability to model the uncertainties associated to the
planning problem makes it suitable to be used in practical applications. The flexibility
of the proposed probabilistic model enables it to consider other sources of uncertainties
and other objective functions. The performance of the proposed model is assessed by
applying it on a distribution network. The numerical results and comparison show that
the proposed method is promising. The future work will be focused on decreasing the
computational burden of the proposed model.
Appendix
The multi-objective problems can be generally described as follows [13]:
14
min F (X) = [f1 (X) , ..., fNO(X)] (27)
Subject to:
{G (X) = 0, H (X) ≤ 0}
X = [x1, · · · , xm]
Where NO is the number of objectives.
Suppose X1 and X2 belong to the solution space. X1 dominates X2 if:
∀k ∈ {1...NO} fk (X1) ≤ fk (X2) (28)
∃k′ ∈ {1...NO} fk′ (X1) < fk′ (X2)
All solutions which are not dominated by any other solution is a member of first Pareto
front or optimal front or non-dominated front. To find the remaining Pareto fronts, all
solutions of first front are discarded and the same process is repeated for the remaining
solutions.
List of Symbols and Abbreviations
Indices
i Bus
h Demand level
e Monte Carlo experiment
V ariables
SD,ei,t,h Apparent load in bus i, year t, demand level h and Monte Carlo experiment e
PDi,base Apparent base load in bus i, year t=1
Pwi,t,h Active power of wind turbine in bus i, year t and demand level h
Sgrid,et,h Apparent power magnitude passing through substation, in year t, demand level h
and Monte Carlo experiment e
15
Iℓ Capacity limit of existing feeder ℓ
Capℓ Capacity limit of potential feeder ℓ
Str Capacity limit of existing transformer
Captr Capacity limit of potential transformer
Cℓ Cost of reinforcement for feeder ℓ in $/km
Ctr Cost of investment in transformer
GCet,h Cost of energy purchased from grid in year t and demand level h and Monte Carlo
experiment e
Ieℓ,t,h Current magnitude passing through feeder ℓ, in year t, demand level h and Monte
Carlo experiment e
CDn Crowding distance of solution n
vcutout Cut out speed of the wind turbine
vcutin Cut in speed of the wind turbine
d Discount rate
τh Duration of demand level h in hours.
DLF ei,t,h Demand level factor in Monte Carlo experiment e, in bus i, year t and demand level
h.
µDi,t,h Forecasted mean value of demand level factor in bus i, year t and demand level h.
µρt,h Forecasted mean value of price level factor in year t and demand level h.
ICdg/w Investment cost of non-renewable/renewable(wind) DG units
γℓt Investment decision in feeder ℓ and year t
ψtrt Investment decision for transformer installation in year t
16
ξdg/wi,t Investment decision for non-renewable/renewable DG installation in bus i in year t
Lℓ Length of feeder ℓ in km
LDkn Local distance of solution n regarding objective function k
MDk Maximum distance between solutions regarding objective function k
NEt,h Number of Monte Carlo experiments in year t, demand level h
Nb Number of buses in the network
Nℓ Number of feeders in the network
Nh Number of demand levels
Np Number of population
NO Number of objective functions
NRt,h Number of Monte Carlo experiments with technical risk in year t, demand level h
OCdg/w Operating cost of non-renewable/renewable(wind) DG units
PLF et,h Price level factor in year t , demand level h and Monte Carlo experiment e
vrated Rated speed of the wind turbine.
Pwi,r Rated power of wind turbine installed in bus i
QDi,base Reactive base load in bus i and year t=1.
σDi,t,h Standard deviation of forecasted value of demand level factor in bus i, year t and
demand level h.
σρt,h Standard deviation of forecasted value of price level factor in year t and demand
level h
TRt Technical risk in year t
DGOC Total operating costs of DG units
17
TGC Total grid cost
DGIC Total investment cost of the DG units
LC Total feeder reinforcement cost
SC Total substation reinforcement cost
Acknowledgment
The authors greatly appreciate the valuable advices and financial supports provided
by the SYREL and GIE-IDEA groups of the Grenoble-INP University, during the study.
References
[1] S. Ghosh, S. Ghoshal, S. Ghosh, Optimal sizing and placement of distributed gen-
eration in a network system, International Journal of Electrical Power and Energy
Systems 32 (8) (2010) 849 – 856.
[2] A. Soroudi, M. Ehsan, H. Zareipour, A practical eco-environmental distribution net-
work planning model including fuel cells and non-renewable distributed energy re-
sources, Renewable Energy 36 (1) (2011) 179 – 188.
[3] T. Niknam, A new approach based on ant colony optimization for daily volt/var con-
trol in distribution networks considering distributed generators, Energy Conversion
and Management 49 (12) (2008) 3417 – 3424.
[4] R. Jabr, B. Pal, Ordinal optimisation approach for locating and sizing of distributed
generation, Generation, Transmission & Distribution, IET 3 (8) (2009) 713–723.
[5] A. Zangeneh, S. Jadid, A. Rahimi-Kian, Normal boundary intersection and benefit-
cost ratio for distributed generation planning, European Transactions on Electrical
Power (2009) 1430–1440.
[6] B. Liu, Y. Zhang, C. Liu, Y. Zhang, W. He, H. Bao, Reliability evaluation for dis-
tribution systems with distribution generation, European Transactions on Electrical
Power 20 (7) (2010) 915–926.
18
[7] R. Caire, N. Retiere, E. Morin, M. Fontela, N. Hadjsaid, Voltage management of dis-
tributed generation in distribution networks, in: Power Engineering Society General
Meeting, 2003, IEEE, Vol. 1, 2003, pp. 282–287.
[8] K.-H. Kim, K.-B. Song, S.-K. Joo, Y.-J. Lee, J.-O. Kim, Multiobjective distributed
generation placement using fuzzy goal programming with genetic algorithm, Euro-
pean Transactions on Electrical Power 18 (3) (2008) 217–230.
[9] A. Soroudi, M. Ehsan, A distribution network expansion planning model considering
distributed generation options and techo-economical issues, Energy 35 (8) (2010)
3364 – 3374.
[10] V. V. Thong, Maximum penetration level of distributed generation with safety cri-
teria, European Transactions on Electrical Power 20 (3) (2010) 367–381.
[11] B. Liu, Y. Zhang, Power flow algorithm and practical contingency analysis for dis-
tribution systems with distributed generation, European Transactions on Electrical
Power 19 (6) (2009) 880–889.
[12] E. Pouresmaeil, D. Montesinos-Miracle, O. Gomis-Bellmunt, J. Bergas-Jan, A multi-
objective control strategy for grid connection of dg (distributed generation) resources,
Energy 35 (12) (2010) 5022 – 5030.
[13] A. Soroudi, M. Ehsan, Multi-objective planning model for integration of distributed
generations in deregulated power systems, Iranian Journal of Science and Technology,
Transaction B: Engineering 34 (3) (2010) 307–324.
[14] M.-R. Haghifam, H. Falaghi, O. Malik, Risk-based distributed generation placement,
Generation, Transmission and Distribution, IET 2 (2) (2008) 252–260.
[15] W. El-Khattam, Y. Hegazy, M. Salama, Investigating distributed generation systems
performance using monte carlo simulation, IEEE Transactions on Power Systems
21 (2) (2006) 524 – 532.
[16] A. Soroudi, M. Ehsan, A possibilistic-probabilistic tool for evaluating the impact of
stochastic renewable and controllable power generation on energy losses in distri-
19
bution networks–a case study, Renewable and Sustainable Energy Reviews 15 (1)
(2011) 794 – 800.
[17] A. Conejo, F. Nogales, J. Arroyo, Price-taker bidding strategy under price uncer-
tainty, Power Systems, IEEE Transactions on 17 (4) (2002) 1081 – 1088.
[18] L. Ochoa, A. Padilha-Feltrin, G. Harrison, Evaluating distributed generation impacts
with a multiobjective index, IEEE Transactions on Power Delivery 21 (3) (2006)
1452–1458.
[19] M. H. Kalos, P. A. Whitlock, Monte Carlo Methods, WILEY-VCH Verlag GmbH &
Co. KGaA, 2004.
[20] H. Fischer, A History of the Central Limit Theorem: From Classical to Modern
Probability Theory, Springer, USA, 2010.
[21] K. Deb, Multi Objective Optimization Using Evolutionary Algorithms, JOHN WI-
LEY & SONS, USA, 2003.
[22] J. Fulcher, L. C. Jain, Computational Intelligence: A Compendium, Springer, 2008.
[23] M. Basu, An interactive fuzzy satisfying method based on evolutionary programming
technique for multi-objective short-term hydrothermal scheduling, Electric Power
Systems Research 69 (2-3) (2004) 277 – 285.
[24] W. El-Khattam, Y. Hegazy, M. Salama, An integrated distributed generation opti-
mization model for distribution system planning, IEEE Transactions on Power Sys-
tems, 20 (2) (2005) 1158–1165.
[25] S. Kirkpatrick, C. D. Gelatt, M. P. Vecchi, Optimization by Simulated Annealing,
Science New Series, USA, 1983.
[26] B. Liu, L. Wang, Y.-H. Jin, An effective pso-based memetic algorithm for flow shop
scheduling, IEEE Transactions on Systems, Man, and Cybernetics, Part B: Cyber-
netics 37 (1) (2007) 18–27.
[27] Electricite de France (EDF), online: http://www.edf.com, accessed Dec 2010.
20
[28] B. Berseneff, Reglage de la tension dans les reseaux de distribution du futur/ volt var
control in future distribution networks, Ph.D. thesis, INP-Grenoble, France (2010).
[29] P. Maghouli, S. Hosseini, M. Buygi, M. Shahidehpour, A scenario-based multi-
objective model for multi-stage transmission expansion planning, Power Systems,
IEEE Transactions on 26 (1) (2011) 470 –478.
[30] J. Morales, S. Pineda, A. Conejo, M. Carrion, Scenario reduction for futures market
trading in electricity markets, Power Systems, IEEE Transactions on 24 (2) (2009)
878 –888.
[31] S. Pineda, A. Conejo, Scenario reduction for risk-averse electricity trading, Genera-
tion, Transmission Distribution, IET 4 (6) (2010) 694 –705.
21
List of Figure Captions:
• Figure 1: The flowchart of the Monte Carlo Simulation
• Figure 2: The flowchart of the proposed algorithm
• Figure 3: The distribution network under study
• Figure 4: The variations of forecasted load and electricity price in each demand
level
• Figure 5: The comparison between the obtained Pareto optimal fronts of different
methods
• Figure 6: The geographical view of a real 574-bus urban network in case-II
• Figure 7: The Pareto optimal front found in case-II
22
Table 1: Data used in the study
Parameter Unit Value
w1 0.55
w2 0.45
ρ $/MWh. 65
α % 3
d % 9
Vmax Pu 1.05
Vmin Pu 0.95
vcutin m/s 3
vcutout m/s 25
vrated m/s 13
c 8.75
k 1.75
σDi,t,h 0.01× µD
i,t,h
σρt,h 0.1× µρ
t,h
NP 30
Maximum iteration 1000
Table 2: Investment plan in best solution of case I
WT GT Feeder Substation
ξwi,t t i ξdgi,t t i γℓt t ℓ ψtrt t
1 2 2 1 2 4 1 3 2 1 7
1 5 4 1 3 6 1 5 6
1 6 6
1 8 8
23
Table 3: Investment plan in best solution of case II
WT GT Feeder Substation
ξwi,t t i ξdgi,t t i γℓt t ℓ ψtrt t
1 1 3 1 1 4 1 1 2 1 3
1 2 2 1 3 6
1 2 3
1 4 7
1 6 9
Table 4: The comparison between the proposed model and other methods
Method # of solutions maxOF1 minOF1 maxOF2($) minOF2($) Run time (s)
Proposed 16 0.8357 0.0109 6.99× 107 6.71× 107 18920
SA 24 0.9274 0.0843 7.06× 107 6.72× 107 12482
PSO 21 0.9683 0.1564 7.03× 107 6.75× 107 16234
Static 22 0.9236 0.3264 7.06× 107 6.80× 107 15992
Table 5: The Planning scheme of solution #11 in scenario II
Year Bus FC SC
t WT GT (105$) (105$)
1 63 5.7639 0
2 371 7.2362 0
5 57 8.6461 0
6 18.8580 2
8 142 574 25.7470 0
24
Table 6: The solutions of Pareto optimal front in case II
Solution OF1 OF2 µ1 µ2 min(µ1, µ2)
1 112507469.7004 0.0000 0.0000 1.0000 0.0000
2 84683648.7369 0.0214 1.0000 0.0000 0.0000
3 107572367.7060 0.0009 0.1774 0.9585 0.1774
4 98451569.6933 0.0013 0.5052 0.9407 0.5052
5 89576596.1460 0.0154 0.8241 0.2797 0.2797
6 90525850.4494 0.0106 0.7900 0.5059 0.5059
7 87554243.1986 0.0185 0.8968 0.1364 0.1364
8 93732213.0991 0.0080 0.6748 0.6280 0.6280
9 97907630.9501 0.0052 0.5247 0.7551 0.5247
10 96867855.5489 0.0063 0.5621 0.7059 0.5621
11 110394545.2631 0.0005 0.0759 0.9754 0.0759
max 112507469.7004 0.0214 1.0000 1.0000 0.5621
min 84683648.7369 0.0000 0.0000 0.0000 0.0000
Table 7: The characteristic of best solution in case II
Year DGIC(M$) SC(M$) LC(M$) TRt
1 4.931 0 3 0.00479
2 4.181 0 9 0.00450
3 1.227 0.2 6 0.00407
4 0 0.2 9 0.00639
5 0.25 0 21 0.00755
6 0 0 9 0.01437
7 0 0 18 0.00407
8 0 0 30 0.00465
25
Table 8: The investment decisions regarding DG units in case II
WT GT
year Bus year Bus
1 180,121,288 1 180,288,360,280,73
2 396,467,574 2 216,574
3 432 5 121
Generate , ,, , , , , e D e
i t h i t hρλ λ
, 0t hNR =
Solve the equations (1) to (20)
Is any of (10) or (11) violated ? Yes
1e e= +No
, , 1t h t hNR NR= +
Monte Carlo Converged?
Yes
No
hh N<1h h= + Yes
t 1; h 1;= =
t<TNo
Yes
End
No
1t t= +Save , ,, e
t h t heNE GC= %
1 ,e =
Figure 1: The flowchart of the Monte Carlo Simulation
26
Randomly Generate an initial set of N solutions
Iteration=1
Calculate OF1 and OF2 for each solution
Calculate the fitness for each solution
Save the best N solutions in memory
Is stopping criteria met ?
Crossover Mutation
Store new solutions
New solutions
Union
�������������������
����
Pareto optimal solutions
Yes
Select the best solution
Stage II
Stage I
Monte Carlo Simulation
Figure 2: The flowchart of the proposed algorithm
Figure 3: The distribution network under study
27
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 240.5
0.55
0.6
0.65
0.7
0.75
0.8
0.85
0.9
0.95
1
Hours
Fo
reca
sted
val
ues
of
load
an
d e
lect
rici
ty p
rice
µDi,t,h
µρt,h
Figure 4: The variations of forecasted load and electricity price in each demand level
0 0.2 0.4 0.6 0.8 16.7
6.75
6.8
6.85
6.9
6.95
7
7.05
7.1x 10
7
Technical risk (OF1)
Co
st (
$) (
OF
2)
Proposed dynamic model SA dynamic modelPSO dynamic modelStatic model
Figure 5: The comparison between the obtained Pareto optimal fronts of different methods
28