Peshawar Sustainable Bus Rapid Transit Corridor Project
-
Upload
khangminh22 -
Category
Documents
-
view
0 -
download
0
Transcript of Peshawar Sustainable Bus Rapid Transit Corridor Project
Social Monitoring Report
Project Number: 48289-002 #7 Internal Social Monitoring Report For the period January to June 2021 September 2021
Pakistan: Peshawar Sustainable Bus Rapid Transit
Corridor Project
Prepared by Peshawar Development Authority for the Islamic Republic of Pakistan and the Asian
Development Bank.
This social monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
The 7th Semi-annual Monitoring Report
(Internal)
(January – June 2021)
Peshawar Sustainable Bus Rapid Transit Corridor Project
Peshawar Development Authority Government of Khyber Pakhtunkhwa
i
The 7th Semi-annual Monitoring Report (Internal)
_________________________________________________________
Project Number: 3543
(January - June 2021)
3543 PAK: Peshawar Sustainable Bus Rapid Transit Corridor
Project
This report has been submitted to ADB by the Peshawar Development Authority and is made publicly available in accordance with ADB’s Public Communications Policy (2011). It does not necessarily reflect the views of ADB.
This Internal monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of
Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making
any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make
any judgments as to the legal or other status of any territory or area.
ii
3543-PAK: Peshawar Sustainable Bus Rapid Transit Corridor
Project (PSBRTCP)
Seventh Semi-Annual Internal Monitoring Report for the
Implementation of Land Acquisition and Resettlement Plans and Addendums of BRT Corridor (Reach 1, 2 and 3)
January - June 2021
Prepared by:
Project Management Construction Supervision Consultant-PMCSC for Peshawar
Development Authority (PDA) – the Project Executing Agency for Peshawar Bus
Rapid Transit (BRT) Project, Peshawar, Khyber Pakhtunkhwa.
iii
Table of Contents
I. Executive Summary ................................................................................................................... viii
A. The Project .............................................................................................................................................. viii B. Summary of LAR Impacts and Status of Compensation Payment – Eastern Bus Depot (EBD), Reach 1 ix C. LARP of Reach 1 (RD 0+000 – RD 7+670): LAR Impacts and Status of Compensation (0+000–7+670) ix D. Summary of Addendum 1 to Reach 1 LARP (additional project impacts) ................................................. xi E. Summary of Addendum 2 to Reach 1 LARP (Continuation of monthly Payments to APs of Hashtnagri &
Firdous Underpasses)............................................................................................................................... xii F. Reach 2 RP (RD 0+000 RD 5+882): Summary of Impacts and Status of Compensation ......................... xii G. Summary of LAR - Impacts/Status of Compensation Payment of Staging station (1+815 – 1+845) ........ xii H. Reach 3 RP (RD0+000 – 14+104) Summary of Impacts/Status of Compensation Payment-Reach 3
(0+000 – 14+104) .................................................................................................................................... xiii I. Key Issues Affecting LARP Implementation ............................................................................................ xiii J. Conclusion ............................................................................................................................................... xiv K. Recommendations ................................................................................................................................. xviii
II. Introduction .................................................................................................................................. 20
A. Project Background and Description........................................................................................................ 20 B. Introduction and Purpose of Internal Monitoring Report (IMR) ................................................................ 21 C. Overall LAR Impacts and Status of Compensation Disbursement ........................................................... 21
C 1. LAR Impacts/Status of Compensation Payment – Eastern Bus Depot (EBD) ...................................... 21 C 2. LAR Impacts/Status of Compensation Payment – Reach 1 (0+000 – 7+670) ...................................... 22 C 3. Addendum 2 to Reach 1 LARP (continuation of monthly payments to APs of Hashtnagri & Firdous
Underpasses) ............................................................................................................................................... 23 C 4. Addendum 1 to Reach 1 LARP (additional project impacts) ................................................................. 24 C 5. Resettlement Impacts/Status of compensation payment – Reach 2 (0+000 – 5+882) ......................... 25 C 6. Resettlement Impacts/Status of compensation payment of Staging Station in Reach 2 (1+815 – 1+845)
..................................................................................................................................................................... 25 C 7. Resettlement Impacts/Status of compensation payment-Reach 3 (0+000 – 14+104) .......................... 25
D. Overall cost of LARPs/ RPs & Addendums Implementation .................................................................... 26
III. Monitoring Methodology and Indicators and Approach .......................................................... 30
A. Approach Followed .................................................................................................................................. 30 A 1. Review of Project Documents ............................................................................................................... 31 A 2. Data Collection and Analysis ................................................................................................................ 31 A 3. Consultation with Key Stakeholders ...................................................................................................... 32
IV. Institutionalisaion of LARP/RP Implementation Process ........................................................ 33
A. Institutional Roles and Responsibilities.................................................................................................... 33
V. Progress on LARP/RP Implementation ..................................................................................... 35
A. LARP/RP Review, Endorsement, and Implementation ............................................................................ 35 B. Disbursement of compensation payments to DPs ................................................................................... 41
B 1. Compensation payments for affected Assets ........................................................................................ 41 B 2. Preparation of Claim Forms and Payment Vouchers ............................................................................ 41
C. Project Impacts and Compensation Disbursement .................................................................................. 41 D. Land Acquisition Impacts and Compensation Payment ........................................................................... 42 E. Payment of Residual Land ....................................................................................................................... 42 F. Payment of Affected Crops ...................................................................................................................... 43 G. Payment of Affected Trees ...................................................................................................................... 43 H. Payment of Affected Building Structures ................................................................................................. 43 I. Payment for Resettlement and Rehabilitation Assistance ....................................................................... 43 J. Reach 2 & RP-Staging Station Implementation Status (payment for allowances) ................................... 45 K. Reach 3 Implementation Status (payment for vulnerability allowances) .................................................. 46 L. Action Plan for the Compensation Payment to Unpaid DPs of Reach 1 .................................................. 47 M. Reasons for Pending Payments: ............................................................................................................. 47 N. Good-faith/ Exhausted Efforts Conducted by PDA for Processing of Stuck Payments ............................ 54 O. Action plan for Livelihood Restoration of DPs .......................................................................................... 57
iv
VI. Consultation, Participation and Information Disclosure ......................................................... 60
A. Stakeholder Consultation and Participation ............................................................................................. 60 B. Information Disclosure ............................................................................................................................. 61 C. Status of Grievances Launched and Resolved ........................................................................................ 61
C 1. Grievance Redress Mechanism ............................................................................................................ 61 D. Grievance Status ..................................................................................................................................... 61 E. Complaints with Current Status of Resolution ......................................................................................... 62
VII. CONCLUSIONS AND RECOMMENDATIONS ............................................................................. 70
A. Conclusions ............................................................................................................................................. 70 B. Recommendations ................................................................................................................................... 70
v
List of Figures
Figure 1: Location Map of the Project Area ......................................................................... 20
LIST OF TABLES
Table 1: Details of Actual DPs and DPs with Multiple effects and Status of Payment .......... 23
Table 2: List of Unpaid DPs, their location and payable amount .......................................... 26
Table 3: Status of LAR Related Documents ........................................................................ 35
Table 4: Detail of Progress on LARP/RP implementation .................................................... 36
Table 5: Summary of overall compensation payment and R&R Assistance ......................... 39
Table 6: Overall Summary Status of Implementation of LARP, Reach 1 ............................. 42
Table 7: Payment of Affected Land, Crops and Trees (EBD) as of December 2020. ........... 42
Table 8 Type of Structures and Compensation Payment of Reach 1 .................................. 43
Table 9: Overall R&R Assistance Payment to DPs of Reach1, 2, 3 & Staging Station and
EBD & of Addendum 1 ........................................................................................................ 44
Table 10: Status of Payment to Vulnerable DPs, Reach 1, EBD and Addendum 1 ............. 45
Table 11: Overall R&R Assistance Payment to DPs – Reach 2 & RP-Staging Station ........ 46
Table 12: Overall R&R Assistance Payment to Vulnerable DPs of Reach3 ......................... 46
Table 13: Status of Payment to Vulnerable DPs, Reach 3 .................................................. 46
Table 14. Action Plan for Payment of Compensation to Remaining DPs ............................. 50
Table 15. List of Consultation Meeting with Unpaid DPs ..................................................... 54
Table 16. List of Potential Eligible Project Affected Persons................................................ 57
Table 17: Grievance Status Report ..................................................................................... 62
Table 18: Log of Grievances Received ............................................................................... 64
LIST OF ANNEXES
Annex 1: Notification of LARP Implementation Committee .................................................. 72
Annex 2: Notification of Resettlement Assistance Disbursement Committee ....................... 74
Annex 3: Notification of Grievance Redressal Committee ................................................... 76
Annex 4: Notification of LARP Implementation Committee Meeting .................................... 78
Annex 5: Notification of Reach Wise Focal Persons for the First Tier GRM ......................... 79
Annex 6: Linear Map of Reach – 1, 2 &3 ............................................................................. 81
Annex 7: Consultations with Key Stakeholders ................................................................... 83
Annex 8: List of Corrected Cases (identified & corrected in Addendum 1 & Reach-1 LARP)
......................................................................................................................................... 115
Annex 9: Grievance Log during the Reporting Period........................................................ 118
Annex 10: Undertaking of Owner Zia Market ..................................................................... 123
Annex 11. Details of Compensation Payment of Different Categories Made to APs .......... 124
Annex 12. Samples of Good-faith Efforts Revealed by PDA.............................................. 153
Annex 13. Pictorial Presentation ....................................................................................... 165
Annex 14. Guardian Statement Form……………………………………………………………166
vi
Abbreviations
ADB – Asian Development Bank
AHs – Affected Households
BRT – Bus Rapid Transit
DP – Displaced Person
EA – Executing Agency
GoKPK – Government of Khyber Pakhtunkhwa, Pakistan
GRC – Grievance Redress Committee
GRM – Grievance Redress Mechanism
IA – Implementing Agency
IMR - Internal Monitoring Report
LRP – Livelihood Restoration Plan
LAA – Land Acquisition Act
LARP – Land Acquisition and Resettlement Plan
PSBRTC – Peshawar Sustainable Bus Rapid Transit Corridor Project
PDA – Peshawar Development Authority
PMCSC Project Management and Construction Supervision Consultants
PMU – Project Management Unit
SPS – Safeguard Policy Statement 2009
STRPI – Social Team for Resettlement Plan Implementation
vii
Glossary
Affected Household: All members of a project affected household residing together and operating as
a single economic unit, who are adversely affected by the Project or any of its components; may consist
of a single nuclear family or an extended family group.
Compensation: Money or payment in kind to which the affected masses are entitled in order to replace
the lost asset, resource or income.
Displaced Persons: In the context of involuntary resettlement, displaced persons are those who are
physically displaced (relocation, loss of residential land, or loss of shelter) and/or economically
displaced (loss of land, assets, access to assets, income sources, or means of livelihoods) as a result
of (i) involuntary acquisition of land, or (ii) involuntary restrictions on land use or on access to legally
designated parks and protected areas.
Entitlement: Range of measures comprising compensation, income restoration, transfer assistance,
income substitution, and relocation which are due to displaced persons (DPs), depending on the nature
of their losses, to restore their economic and social base.
Involuntary resettlement: Development project results in unavoidable resettlement losses that DPs
have no option but to rebuild their lives, incomes and asset bases elsewhere.
Land Acquisition: The process whereby a person is compelled by a government agency to alienate
all or part of the land a person owns or possesses to the ownership and possession of the government
agency for public purpose in return for compensation.
Relocation: The physical resettlement of a DP from her/his pre-project place of residence.
Replacement Cost: Compensation for acquired land, structures and other assets, including (i) fair
market value, (ii) transaction costs, (iii) interest accrued, (iv) transitional and restoration costs, and (v)
other applicable payments, if any
Resettlement plan: A time-bound action plan with budget setting out resettlement strategy, objectives,
entitlement, actions, responsibilities, monitoring and evaluation
Vulnerable groups: Distinct groups of people who might suffer disproportionately from resettlement
effects
viii
Executive Summary
A. The Project
1. The Peshawar Sustainable Bus Rapid Transit Corridor Project (PSBRTC) will contribute to the development of a sustainable urban transport system in Peshawar. The project outcome will be to improve public transport in Peshawar, directly benefiting a population of at least 0.5 million. The project will consist of two interlinked outputs: (i) full restructuring of a 24.65-kilometer (KM) BRT corridor, which is 16+302 KM at grade and 8+348 KM elevated, 5+279 KM underpass u turns including BRT dedicated lanes, mixed traffic lanes, bicycle lanes, parking lanes facility at 39 stretches, sidewalks, green areas, 32 bus stations, 2 depots on eastern and western side, 1 staging station, 2 U-turns flyover, 24 pedestrian bridges (including 1 with access through a tunnel), 8 feeder routes and 102 off corridor bus stations, sub-bus stations (# are not known yet), energy-efficient streetlights and proper drainage to climate-proof the BRT infrastructure; and (ii) effective project management and sustainable BRT operations through institutional and organizational developments. The project will provide an integrated bus rapid transit (BRT) corridor, focusing on accessibility, passenger time savings and alleviating congestion for car users and reducing vehicle operating cost and carbon emissions, which will in turn help make Peshawar safer, more live able, and would foster gender equity. As part of the Detailed Engineering and Design Works was completed by Mott MacDonald Pakistan (MMP) in May 2017 and a land acquisition and resettlement plan for reach 1 of BRT corridor and two resettlement plans of reach 2 and 3 corridors were approved and disclosed in 2017. Table ES 1 below provides details on approved safeguard plans by contract packages.
Table ES 1: List of Approved Safeguard Documents by Contract Packages
S. # Safeguard Document Description Date of Approval
1 LARP Package 1 comprising Reach 1 corridor.
October, 2017
2 LARP Package 4 comprising LARP of Eastern Bus Depot (EBD) or Chamkani Depot
March, 2018
3 RP Package 2 comprising Reach 2 (Firdous Cinema to Aman Chowk)
November, 2017
4 RP Package 3 comprising Reach 3 (Aman Chowk to Hayatabad)
October, 2017
5 RP Comprising Dubgari Gardens Staging facility
November, 2017
6 No LAR impacts DDR Package 5 comprising DDR of allied structures
November, 2017
7 Addendum 1 to Reach 1 LARP
Covered additional impacts project implementation
April, 2019
8 Addendum 2 to Reach 1 LARP
Prepared for “Continuation of monthly payments to DPs of Hashtnagri & Firdous Underpasses”
July, 2019
9 No LAR impacts DDR Issue of closure of shops in KTH underpass
March, 2018
10 No LAR impacts DDR Prepared for Project Allied Structures
July, 2019
10 No LAR impacts DDR Prepared for Karkhano Road Section March, 2019
March, 2019
ix
2. The status of implementation of LARPs, RPs and Addendums and DDRs is presented as under.
B. Summary of LAR Impacts and Status of Compensation Payment – Eastern
Bus Depot (EBD), Reach 1
3. A total of 174.4 kanals of private land (comprising of 104.35 kanals of orchard &
agriculture land and 68.27 kanals of barren land) (~21.8 acres in total) was acquired for
construction of BRT at Sardar Garhi that impacted a total of 83 DPs including 44 males and
29 females and 10 unregistered tenants. In addition to land, 419 fruit trees and 154 wood trees
were also affected. A total amount of Rs. 1,095.182 million was payable as land compensation
to a total of 73 DPs.
4. Full amount of land compensation (100%) has already been disbursed to all 73
landowning DPs. A compensation amount of Rs. 0.754 was to be paid to 12 DPs as crops
compensation. Of this amount, Rs. 0.521 million has been paid to 11 of 12 DPs. Compensation
to remaining one DP will be made in next few weeks. In case of fruit and wood trees, a total
of 26 DPs had to be paid an amount of Rs. 4.827 million, out these 25 DPs have been paid
while the remaining one DP will be paid in next few weeks. Compensation amount Rs. 1.35
million has been paid to 10 non-register tenants. Unpaid DPs have been contacted and asked
to come and receive compensation, but they are yet to contact PDA for their payment. PDA
resettlement team has reach out to the remaining one DP and she has authorized her relative
by giving “power of attorney” to receive her remaining payments of crops and trees. PDA has
prepared this cheque already and was to be disbursed by end of May 2021, however, due to
the retirement of ex-PD and joining of new PD-PIU during the month of April, 2021, similarly,
due to transfer of ex-DG-PDA and joining of new DG resulted delay in payment to the
mentioned DP. Additionally, in the meantime, payment cheque of the DP expired. Now, his
cheque has been renewed and in the process and hopefully will disburse the cheque in
August/ September, 2021.
C. LARP of Reach 1 (RD 0+000 – RD 7+670): LAR Impacts and Status of
Compensation (0+000–7+670)
5. The draft LARP of Reach 1 was updated by PDA and approved by ADB in October
2017 based on the final detailed engineering and design works. According to approved LARP
12.5 marlas of residential land was acquired which permanently impacted 9 commercial
shops, 4 residential houses, 1 workshop and 2 garages located on Zia market that affected a
total of 30 DPs (one landowner, 9 shopkeepers & 16 employees of shopkeepers and 4 house
renters). A total of Rs. 32.977 million was to be paid to these DPs as compensation of land,
structures, and allowances for loss of livelihoods.
6. Similarly two underpasses Firdous and Hashtnagri in Reach 1 corridor also affected a
total 201 DPs (including 51 multiple affects DPs of both Firdous underpass & 45 multiple
affects DPs of Hashtnagri Underpass) comprising of 38 shopkeepers, 22 lessees and 98
employees of Firdous underpass (BS 08) and 133 DPs comprising 35 shopkeepers and 47
employees and 16 lessees of Hashtnagri underpasses (BS 07). A total amount of Rs. 177.172
million was payable to these DPs for a period of 12 months from February 2018 to February
2019 for Hashtnagri Underpass DPs and from May 2018 to May 2019 for Firdous Underpass
DPs. Since construction of both underpasses delayed beyond the period of construction, an
amount of total Rs. 8.755 million per month was also agreed to be paid to the DPs of both
x
underpasses as additional compensation for a period of March to August 2019 for Hashtnagri
Underpass DPs and June to August 2019 for Firdous Underpass DPs.
7. The current status of compensation is such that all 26 (one DP has multiple affects)
DPs of Zia market have been fully compensated with an amount of Rs. 33.711 million for
resettlement impacts except 5 DPs that are employees of shopkeepers who are underage and
who yet have to received Rs. 0.285 million for loss of income impacts, their payments will be
processed once they receive their guardian certificate from the court for which they have
applied. Although, the process of preparation of guardian certificate take ample time of 4 to 5
months or even more time if not properly pursued by the concerned advocate in the court of
law. Conversely, fortunately, the underage five DPs have now reached majority age in the last
couple weeks. They have applied for preparation of CNICs, in fact four out of five DPs CNICs
are received to STRPI team. Their cheques now are in process and will disburse their cheques
either end of August or first half of September 2021.
8. This is followed by compensation disbursement to the DPs of both underpasses. Out
of total 344 DPs (including 96 multiple count DPs of both the underpasses) of both
underpasses, 184 DPs (including 158 DPs of original LARP and 26 DPs of addendum 2) of
Firdous underpass have been fully paid an amount of Rs. 91.445 million out of total amount
of Rs. 95.037 million as per LARP for 12 months and including additional payments beyond
12 months (original LARP) under Addendum 2. While Firdous underpass actual DPs are 158.
9. Similarly, for Hashtnagri underpass 121 (98 DPs of original LARP & 23 DPs of
addendum 2) (including 45 multiple count DPs) have been fully paid an amount Rs. 79.915
million (of total Rs. 82.135 million) as per LARP including additional payment beyond 12
months (original LARP) under Addendum 2. While Hashtnagri underpass actual DPs are 98.
10. Efforts were made during the reporting period to reach out and compensate the long
unpaid 5 underage employees of shopkeepers of Zia market, 18 DPs of Firdous & 12 DPs of
Hashtnagri underpasses. In this regard, the PDA and PMCSC resettlement staff have
informed the unpaid DPs through shu’ra members of the both underpasses to collect their
remaining payments. Similarly, PDA in coordination with PMCSC also approached all the
unpaid DPs at the door steps of unpaid DPs, even the DPs have informed telephonically on
their given cellphone numbers however, the underpasses DPs informed that they will not
receive their remaining compensation amount until the amicable resolution of complaint
regarding BS-07 redundant shops for which they had complained to the ADB back in August,
2020. On the other hand, the 5 DPs of Zia market replied that two DPs are now reached to
the age of 18 years and they have applied for preparation of their CNICs which will issue in
couple of weeks while the three DPs informed that they have applied for their guardian
certificates in the court of law. They further informed that they are optimistic and will make
follow up with their lawyer to collect their guardian certificates as soon as possible. It is
expected that these DPs will be paid by August-September 2021. Table ES 2 below provides
details of actual DPs and DPs with multiple count impacts as well as details of paid and
remaining DPs.
xi
Table ES 2: Details of Actual DPs, DPs with Multiple Effects and Status of Payment Name of
Underpass Actual DPs
DPs with
Multiple effects
Paid Unpaid Remarks
Hashtnagri Underpass
98 45 86 12 All 98 DPs have received full compensation amount as per original LARP for 12 months. However, in light of Addendum 2 of LARP-1, 12 DPs are unpaid. Compensation for these 12 DPs is expected to be completed by Aug-Sept 2021.
Firdous Underpass
158 51 140 18 All 158 DPs have received full compensation amount as per original LARP for 12 months. However, in light of Addendum 2 of LARP-1, 18 DPs are unpaid. Compensation for these 18 DPs is expected to be completed by Aug-Sept 2021.
11. However, payment of compensation to 55 DPs is still pending due to a number of
factors that are discussed in the following paragraphs of this executive summary.
D. Summary of Addendum 1 to Reach 1 LARP (additional project impacts)
12. Addendum 1 to Reach 1 LARP was prepared in light of additional project impacts. The
addendum was envisaged so as to cater the in/ out access of vehicles specifically coming
from the Eastern districts/ areas to/ from Eastern Bus Depot. This impacted on additional
commercial 5 Marla land, nine structures, disruption of businesses of five shopkeepers, 13
employees & 02 watchmen losing jobs at Sardar Garhi petrol station market. All DPs of
Addendum 1 have been paid except 13 DPs. Total costs of Resettlement & Rehabilitation of
DPs of addendum 1 are Rs.10.566 million for R&R assistance to 29 DPs, out of which Rs
5.224 million have been paid to 16 DPs, the remaining Rs 5.342 million will be paid to 13 DPs
in coming month. Out of total remaining amount Rs. 3.472 million is of land.
13. Of these 13 DPs, 7 DPs payments had stuck due to correction in their names or CNICs
reported in the addendum report. In the previous version of IMR (July – October, 2020) the list
of corrected names or CNICs has approved. This list has shared with the finance unit of PDA
to process the payment to 7 DPs. The other remaining 6 underage DPs have been informed
telephonically as well as visited their residents. They informed that their case for making of
guardian certificate is under process and as soon as they get guardian certificates they will
informed both the PDA and PMCSC staff accordingly. In this regard, to expedite the process,
the PMCSC resettlement staff contacted with focal person Mr. Musavir Khan of Sardar Garhi
Filling Station DPs who is a lawyer by profession to further look into the process of making of
guardian certificate in the concerned court on behalf of these 6 DPs. Mr. Musavir Khan has
agreed that he will voluntarily pursue their case and hopefully will get in the couple of week
time. In this regard, an application letter is collected from the lawyer who had submitted the
case of 7 underage DPs (4 DPs of Zia Market & 3 DPs of Sardar Garhi Filling Station) for
preparation of their guardian certificates. The application letter is included in annex-12 as
xii
evidence of good-faith efforts PDA made to pay unpaid DPs. The payment of compensation
is under process and efforts to be made to complete and presented in the next semiannual
IMR.
E. Summary of Addendum 2 to Reach 1 LARP (Continuation of monthly
Payments to APs of Hashtnagri & Firdous Underpasses)
14. Owing to delay in the refurbishment/ remodeling work on both the underpasses, the
shopkeepers of both the underpass could not resettled in their shops as per the agreed time
which is why, in that scenario, the DPs lodged a complaint at PDA with STRPI team for
payment of additional months beyond 12 months until the formal handover of shops back to
them. In response to the complaint and follow up joint discussions among DPs, PDA, PMCSC
and ADB, PDA prepared an Addendum to the LARP of Reach 1 to address the issue of
additional payment of R&R assistance to DPs. The addendum was approved by ADB on July
15th, 2019. The addendum covered an amount of Rs.8.755 PKR million to 86 shopkeepers &
77 lessees/ sub-lessees of both the underpasses DPs for per month until, as long as the new
shops are constructed and will terminate when the shops are hand over back to the
shopkeepers/ lessees. From total additional R&R assistance, 136 DPs have been paid while
remaining 27 DPs will be paid when they contact PDA for payment.
15. During the reporting period these DPs have been informed through their shu’ra members of both the underpasses, contacted them via their given cellphones, and even most
of them met personally in the underpasses to collect their remaining compensation. However,
these DPs have informed the PDA and PMCSC staff that as per their mutual understanding
with main-leaseholder and shu’ra members, they will not receive their remaining payments until the resolution of their complaint regarding BS-07.
F. Reach 2 RP (RD 0+000 RD 5+882): Summary of Impacts and Status of
Compensation
16. Reach 2 road section goes elevated just to avoid the impacts on both sides of the road.
This elevated section starts at the Firdous Cinema Chowk/crossing and ends at Amman
Chowk.
17. The construction of Reach 2 caused minor resettlement impacts. Only 19 vendors
temporarily displaced during the construction phase. In Reach 2, under the category of
allowances for rehabilitation/livelihood restoration payments, 14 DPs were paid an amount of
PRs. 1,960,000. However, during RP implementation 5 DPs were verified by STRPI team and
had declared illegible and thus excluded from the list of APs.
G. Summary of LAR - Impacts/Status of Compensation Payment of Staging
station (1+815 – 1+845)
18. The Staging station is located in Reach 2 at chainage from 1+815 – 1+845) in Dabgari
gardens area on Railway road which is located along the BRT corridor. The construction of
Staging Station caused impacts on 4 vendors involved in vending businesses, who were
affected temporarily during construction phase. The four vendors were sitting at the back of
previously located houses constructed on government owned land. Apart from temporarily
displacement of four vendors there were no LAR impacts in RP of Staging Station. They have
been fully compensated an amount of Rs 560,000.
xiii
H. Reach 3 RP (RD0+000 – 14+104) Summary of Impacts/Status of
Compensation Payment-Reach 3 (0+000 – 14+104)
19. Reach 3 starts from Amman Chowk and ends at Karkhano Markets. The only
displacement impact in Reach 3 occurred between 4+375 and 4+400 at the Spin Jamaat
location where 7 vendors who run their micro businesses within the ROW were affected
temporarily during construction phase. They were to be paid Rs. 980,000.0 as rehabilitation
and livelihood restoration allowance and they have been already fully compensated this
amount.
I. Key Issues Affecting LARP Implementation
20. Following are the key issues which are affecting the smooth implementation of LARP.
21. The DPs of Hashtnagri underpass are still unwilling to receive the remaining
compensation payment even upon agreement with PDA over number of shop units, proposed
new drawing for underpass rearrangement, regularization of five shops. The complainants
have lodged complaint at PIU due to 22 shops (after the refurbishment of underpass) which
could not be rented out since these were handed over back to underpass DPs by PDA. Their
shops remained redundant due to no front access of pedestrians to their shops after
refurbishment. That is why these DPs claim a front access to their shops by replacing the
existing as built ramp at North End with stairs at the right-wing in the underpass. In this regard,
the complaint of 6 complainants representing these 22 shops’ owners was considered for
verification and resolution (if viable). In this regard, the ADB senior social safeguard specialist
has conducted a thorough assessment of the complaint and according to him, access should
be given, 44 number of shops were existed pre-BRT, LARP had documented entitlements of
44 shops in the Hashtnagri Underpass. The issue is of 5 shops which had never rented out,
has now resolved as the PDA has regularized those shops. The 8 DPs of Hashtnagri
underpass have informed that they will receive the remaining compensation upon completion
of civil works on the underpass rearrangement. Fortunately, during the months of May and
June, 2021 an agreement has been made as PDA has acknowledged the regularization of 5
five shops which has now formally regularized. Similarly, agreed to give front access to the
mentioned redundant shops through underpass rearrangement work. And this will be
implemented as soon as the de-scoping process for sub-contractor-ship is completed.
22. Another issue is 5 Afghan nationals who do not have CNICs cards and thus cannot
open back accounts ultimately payment cannot be processed to them. During the reporting
period, no such progress could not be made due to the retirement of ex-PD and joining of new
PD-PIU, similarly, due to transfer of ex-DG-PDA and joining of new DG resulted also stuck
any progress regarding this issue.
23. Similarly, 23 underage DPs cannot open bank accounts and payment cannot be made
until they provide guardian certificates. Eight of the 23 under-age DPs have already secured
their guardian certificates. Their compensation will be processed upon submission of such
certificates. The remaining 15 have applied for guardian certificates in court and are waiting
for the release of their certificates
24. Payment to 7 DPs who needs corrections either in DPs name or CNICs number has
also delayed the payment process. The 7 DPs with problem in their CNICs or needs
corrections in names have fixed now and made corrections accordingly. So they will be
compensated soon.
xiv
25. 11 DPs of Firdous underpass are complainant of BS08 The cheques for 11 DPs at
Firdous underpass is under process
26. One DP of EBD remaining payment of crops & trees. The DP (known politician of KP)
has authorized her relative by giving “power of attorney” to receive her remaining payment of
crops & trees which will be completed by end of May 2021.
J. Efforts done by PDA and Actions plan for payments of compensation to
remaining DPs
27. PDA has approached all unpaid DPs at their given addresses and contacted them
through other means including phone numbers, such as cell numbers mobile, etc., issued
public notices (by name to all DPs) and in print media including local newspapers and
displaying of banners at conspicuous locations and meaningfully assist DPs in addressing
problems related to DPs not having CNIC and/or bank accounts and those requiring guardian
certificates. PDA has prepared the action plan to process the remaining payments in coming
weeks as shown in ES table 3.
xiv
ES Table 3: Efforts done by PDA and actions plan to disburse the remaining payments to 55 DPs
S/NO Categories of Unpaid DPs
Issues Efforts by PDA to pro Timelines Revised Dates & Actions
1 2 3 4 5 6 1 5 Afghan national
DPs (AN DPs) Payments cannot be processed by PDA finance section without CNIC which is a procedural requirement Lack of Pakistani CNIC being Afghan national
The new PD has taken up this matter with the finance team of PDA and discussed the following options on 26th April 2021 and May 3rd : i) the amount may
transfer to contractor account of the respective Reach and then the contractor under the supervision of STRPI and PMCSC resettlement staff further hand over the unpaid amount to the 5 Afghan DPs or
ii) the amount may transfer to project management & construction supervision consultants i.e. PMCSC/ MMP account and then formally hand over to the Afghan DPs, if acceptable to finance/ audit team of PDA or
iii) the amount of compensation of
Decision of PDA finance department end of May 2021 Preparation of cheques 1 and 2nd week of June Disbursement of cheques and Payments of compensation by 30th June, 2021
Decision of PDA finance department end of September 2021 Preparation of cheques 1st week of October Disbursement of cheques and Payments of compensation by 15th October 2021
xv
Afghan DPs may transfer to the accounts of those shopkeepers with whom the Afghan Refugees had worked as assistants or
iv) through Shu’ra members of Underpasses; as the Shu’ra as association of underpasses falling in Reach-1 is an organized body, if the amount may transfer to Shu’ra members account and then formally hand over to Afghan DPs in the presence of PMCSC, STRPI and finance team of PDA as witness.
v) as soon as DG-PDA will decide about the convenient option for payment to unpaid Afghan DPs will be communicated to ADB accordingly. As discussed above, PDA is committed to pay all the unpaid DPs by June 30th, 2021.
xvi
2 23 underage DPs Underage DPs also lack CNIC until they reach age of 18 years hence they require guardian certificate from court to receive cheques and get paid 8 of these DPs have submitted the request for guardian certificate to the court through their lawyer in October 2020. Courts usually takes 3 to 4 months to provide guardian certificates. The lawyer presume that their certificates are ready at court and will update PDA about their status in 2 weeks based on which PDA will prepare cheques The remaining 15 DPs have also submitted their request for guardian certificate in court but couldn’t provide evidence of application to the PDA team when inquired
As the guardian certificates are issued by the court which usually takes 3 to 4 months, this process is further slowed down due to Covid 19 restrictions and the month of Ramadan These kind of payments are expected to be delayed by 4 to 5 months. Hence the guidance statement form attched as annexure 14 is a procedure to facilitate resolution of stuck payments and enables closing such cases based on the good faith efforts EAs are required to make. In this case, an escrow account is needed to open to deposit the amount of compensation, which will be disbursed at the time when guardian certificates are available. PDA will confirm if the compensation money is kept in a project account dedicated for this purpose in 2 weeks.
PDA resettlement team will follow-up with the Lawyer who will provided update on the guardian certificates of 8 DPs. PDA resettlement team will contact 15 DPs for evidence of their application submitted to the court PDA resettlement team will get the guardian statement filled by these underage DPs by June 30th 2021 PDA will conduct meeting after eid vacations within department to discuss if compensation money of these DPs can be kept in project account
Follow up is underway, according to the lawyers two DPs guardian certificates will be prepared in September, 2021, hence cheques will be prepared and payment will be made to these two DPs by end of September, 2021. He further conveyed that 10 DPs will become major/ grown up in end of August, 2021, expected they provide CNICs by 20th September, 2021 and payment will be made either by end of September or 1st week of October, 2021.
xvii
3 7 DPs mismatch names and CNIC no
These 7 DPs have their names mismatched with their CNIC numbers as per PDA records Correction is made by PDA’s audit team which is then approved by ADB in 5th IMR report
PDA finance team has distributed the cheques to these 7 DPs in the presence of PMCSC and STRPI team as witnesses. The pictures and process of cheques distribution will be included in 7th IMR report.
Evidence of payments will be provided in next IMR
Evidence of payments will be provided in next IMR by Oct/ Nov, 2021.
4 8 DPs/complainants of Hashtnagri underpass refused payments until resolution of complaints
These DPs are among complainants of BS07 who refused to receive cheques until the complaint is resolved. They have complaint that their shops remain redundant due to inaccessible stairs and demand revision in design and provide decent access to their shops through properly engineering designed stairways through rearrangements of underpass
PDA has issued notices to the DPs of both the underpasses for collection of their unpaid payments and informed the DPs about the development in resolution of BS-07 complaint and requested the DPs to receive their payments cheques from PDA office before they get expired.
As these 8 DPs has refused to collect their cheques until resolution of rearrangements of underpass BS07 complaint. The payment to these DPs still depends upon timely completion of civil works on underpass rearrangements and hence subsequently collection of payments by the unpaid DPs.
As the agreement has been now made with the complainant’s. Access to the redundant shops to be provided one the descoping process is completed and contractors are on board then physical rearrangement work will be started expectedly in July/ August, 2021. The construction will be completed expectedly in Oct/ Nov, 2021.
5 11 DPs of Firdous underpass
These DPs are complainants of BS08, their complaint is about the use of feeder bus tunnel as an alternate passageway to reach
PDA with the help of ADB consultants has reviewed this complaint and have recommended to place appropriate signage at different locations to guide
These DPs will be paid of 25th June, 2021
These DPs will be paid of by end of September, or 1st of October, 2021
xviii
the bus station which has safety concern.
people. The complainants have withdrawn their complaint and agreed to receive cheques. However during the resolution of complaints the initial cheques got expired and PDA finance department is renewing the cheques and provide cheques to DPs by the end of June 2021
6 Other DPs 1 DP has remaining payments of crops and trees couldn’t receive payments due to her busy schedule being a politician
PDA resettlement team has reach out to this DP and she has authorized her relative by giving “power of attorney” to receive her remaining payments of crops and trees. PDA has prepared this cheque already and will be disbursed as soon the DPs relative will reach them. PDA resettlement staff will remind this DP to receive cheque in 1 week
This DPs will be paid by 25th May 2021
This DPs will be paid by second half of September, 2021
xviii
K. Conclusion
28. PDA has made considerable progress in implementing the LARPs and making
payment of compensation and rehabilitation and livelihood assistance to 522 DPs 522 of total
577. However, 55 DPs are still facing some impediments as mentioned in ES table 3 above
due to which PDA cannot make payment to them unless they fulfil the legal and procedural
requirements of their payments. Overall, out of total PRs. 1,335.19 million payable to all 577
DPs for all impacts, an amount of PRs. 1,322.96 million have been already paid to 522 DPs.
Remaining amount of Rs. 12.03 million is payable to the remaining 55 DPs who will be paid
after they fulfil the legal and procedural requirements of their payments. Regarding vulnerable
DPs, progress were made in the needs of vulnerable people, ongoing follow up of grievance
resolution and tracking monitoring impacts. Similarly, out of total PRs 20.405 million payable
amount 14.450 million have paid to 182 out of total 226 vulnerable DPs. Similarly, out of total
61 project vendors of the three reaches, 58 have been compensated with PRs. 8.120 out of
total payable PRs 8.540 million. The project unique DPs such as Afghan Refugees, blocked,
underage who need guardian certificates for payment and DPs need correction in their names
& CNICs numbers and expired ID Cards holders DPs are still pending.
L. Recommendations
29. In light of summary of compensation, 55 DPs are still remaining to be paid, the PIU,
STRPI and PMCSC is trying utmost efforts to for any possible efforts in addressing the issue/
impediments so as to compensate the remaining payments as soon as possible. Following
are the recommendations for PIU, STRPI and PMCSC for timely completion of payments to
the remaining 55 DPs of the project.
i) PDA-PIU will make sure the availability of funds and overcome the usual delay in
meeting the procedural requirements. According to this, the newly appointed social
safeguard focal person has assured that now there is no such constraints regarding
availability of funds and the same will be ensured till the full payment to the
remaining DPs.
ii) For payment to Afghan Nationals, PDA will further discuss with PMCSC about
payment to Afghan nationals that either their payment may made through their
shopkeepers’ account with whom they were working as assistants/ employees or Shu’ra members of underpasses under the supervision of STRPI and PMCSC
consultants.. The new PD-PDA has expedited the payment process with the
finance team at PDA. Also discussed the issue of Afghan DPs with new DG-PDA
on April 26th & on 3rd May, 2021 for consideration of convenient way to compensate
the 5 unpaid Afghan DPs.
iii) Regarding underage/ juvenile DPs pending payment cases, the STRPI and
PMCSC resettlement team are in close contact and will further keep close liaison
with the DPs focal person & a lawyer Mr. Musavir to expedite and secure the
guardian certificates for the underage DPs who had already put their cases in the
court of law. As, in the regard, during the report period, the PMCSC staff had
contact with Mr. Musavir and he agreed that he will voluntarily follow up these
cases in the court of law on behalf of the underage DPs. Regular coordination will
continue with the underage DPs so that keep update each other and extend
support to DPs if they deem it.
xix
iv) The PDA in coordination with ADB will make further effort to resolve the issue of
BS-07 so that the remaining DPs of underpass may start collection of their payment
at PDA. In this regard, during the reporting period, number of internal coordination
meetings as well as meetings with complainants’ representatives have been
conducted and further bi-weekly meetings or GRC meeting will be carried out to
resolve this issue as soon as possible.
20
I. Introduction
A. Project Background and Description
30. The Peshawar Sustainable Bus Rapid Transit Corridor Project (PSBRTC) under
construction with the financial assistance from the Asian Development Bank will contribute to
the development of a sustainable urban transport system in Peshawar. The project will
improve public transport in Peshawar, directly benefiting a population of at least 0.5 million.
The project will consist of two interlinked outputs: (i) full restructuring of a 31.47-kilometer BRT
corridor, including BRT dedicated lanes, 31 stations, 2 depots, mixed traffic lanes, bicycle
lanes, parking, sidewalks, green areas, energy-efficient streetlights and proper drainage to
climate-proof the BRT infrastructure; and (ii) effective project management and sustainable
BRT operations through institutional and organizational developments. The Location Map of
the Project is given as Figure 1.
Figure 1: Location Map of the Project Area
31. The project will provide an integrated bus rapid transit (BRT) corridor, focusing on
accessibility, passenger time savings and alleviating congestion for car users, and reducing
vehicle operating cost and carbon emissions, which will in turn help make Peshawar safer,
more livable, and foster gender equity.
21
B. Introduction and Purpose of Internal Monitoring Report (IMR)
32. Monitoring of development activities provides government officials, development
manager, and civil society with better means for learning from past experience, improving
service delivery, planning and allocating resources and demonstrating results as a part of
accountability to key stakeholders. The purpose of internal Monitoring is to look into the
physical as well as financial progress of the projects and analyze the compliance with the
approved Resettlement Framework, Resettlement Plans and ADB’s Safeguard Policy
Statement 2009 (SPS). Internal Monitoring Report is presented twice in a year, the objective
of Internal Monitoring Report is to determine whether resettlement objectives are being
achieved and more importantly whether livelihoods and living standards of those affected are
enhanced or at least restored, and project risks and negative impacts mitigated. The specific
objectives for internal monitoring are to determine: (i) whether the implementation of land
acquisition and resettlement of project is in compliance with the approved LARF and LARPs;
(ii) the availability of resources and the efficient, effective use of these resources to implement
land acquisition and resettlement (LAR) activities; (iii) hat resettlement institutions are well-
functioning during the course of project implementation; (iv) LAR activities are undertaken in
accordance with the implementation schedule described in the LARP/RPs and; (v) to identify
problems, if any, remedial actions and to consolidate lessons learned from practical
experiences.
33. Thus, the purpose of this IMR is to present progress of ongoing implementation of
LARP/RPs. The report reflects current situation of land acquisition disbursement of
compensation and the DPs views related to LAR matters of the project.
C. Overall LAR Impacts and Status of Compensation Disbursement
34. The LAR impacts and compensation disbursement is presented by LARPs, RPs, and
Addendums. Following is LARP/ RPs wise details of implementation of payment of
compensation to project DPs.
C 1. LAR Impacts/Status of Compensation Payment – Eastern Bus Depot (EBD)
35. The Eastern Bus Depot (EBD) has been planned to be constructed on the land of
village Sardar Garhi, Union Council Watt Pagaa, for this purpose 174.4 kanals (8.822
hectares) of private agriculture land have acquired at the junction of Northern Bypass Grant
Trunk Road (GT Road) and Motorway, near Chamkani.The land for eastern bus depot is
located in village Sardar Garhi, union council Watt Pagaa adjacent to Northern bypass along
with Railway track at the back of Zia Market (at the junction of Northern Bypass Grand Trunk
Road (GT Road) and Motorway, near to proposed BS-1 Chamkani.
36. In LARP of Eastern Bus Depot (EBD) falling in Reach-1, there are a total of 174.4
kanals (including 104.35 kanals orchard & agriculture land and 68.27 kanals barren or not in
use land) of private land (~21.8 acres) have been acquired for construction of BRT at Sardar
Garhi, impacting 83 DPs including 44 Male and 29 Female. Additionally, the affected land was
cultivated by 10 non-registered tenants. Major crops grown on the affected land were wheat,
fodder in Rabi cropping season (winter-spring) and fodder and corn in Kharif cropping season
(summer-autumn). There was an impact on 419 pear trees and 154 wood trees. The total cost
for payment of land compensation is Rs. 1,095.182 million. Of this amount, Rs. 1,095.182
million (100%) have been paid to 73 DPs (100%). Compensation amount Rs. 0.754 million for
crops were to be paid to a total number of 12 DPs. Out of 12 DPs 11 DPs have been paid Rs.
0.521million, the remaining 01 DP will be paid an amount of Rs.0.233 million. In case of fruit
22
and wood trees, a total of 26 DPs had to be paid an amount of Rs. 4.827 million, out of Rs.
4.827 million Rs. 4.821 million have been paid to 25 DPs, the remaining 01 DPs will be paid
Rs. 0.006 million. The remaining DPs have been communicated time and again to come to
office and collect their compensated amount.
C 2. LAR Impacts/Status of Compensation Payment – Reach 1 (0+000 – 7+670)
37. The draft LARP of Reach 1 was updated based on the detailed engineering design in
October 2017, and approved by ADB in October 2017 and similarly disclosed in the same
month/ year in October, 2017. In the LARP of Reach 1, the affected building structures at
Reach1 had a cost of Rs. 36.591 million (Rs. 15.766 million of Zia Market structures, Rs. 2.705
million of affected structure of prayers place and Rs. 5.425 million of affected shops Hashtnagri
decoration and Rs. 12.695 million of affected shops Firdous decoration) which have been paid
to the project DPs (100%). The project impacted on Zia Market consisted of 12 shops and 4
residential houses. A 12.5 Marla commercial land worth of PKR 12.63 million also impacted in
Reach 1 LARP. The amount of land has been paid to the project DP (100%). The project also
impacted on two underpasses i.e. Firdous Underpass at BS-08 and Hashtnagri Underpass at
BS-07 in Reach 1 LARP consisted of refurbishment of both the underpasses. Similarly, the
project impacted on 36 roadside vendors in Reach 1 LARP.
38. In Firdous underpass at BS-08 there were total 45 permanent shops and two moveable
structures of kiosks have refurbished. All the shopkeepers and shop-owners (lessees/ sub-
lessees) of both the underpasses have paid 100% for 12 months as per the approved LARP
of Reach 1. The income of 62 employees of the shops as well as 35 family members of
shopkeepers working in the shops and 2 security guards have been compensated accordingly
as per the approved LARP. Payment of Hashtnagri Underpass as per 12 months schedule
was from Feb 2018 to Feb 2019, in which all 12 months payment has been made. Similarly,
payment of Firdous Underpass as per 12 months period was from May 2018 to May 2019 in
which all 12 months payment has been made. The Resettlement and Rehabilitation (R&R)
Assistance involve two types of allowances covering lump sum and monthly payments for
income loss. Collectively, both the underpass DPs have been collected their 12 months
payments.
39. Total costs of Resettlement & Rehabilitation of DPs at Reach1 are Rs.169.787 million
for R&R assistance to 322 DPs including, 318 male and 04 female, out of which Rs. 163.54
million have been paid to 284 DPs, the remaining Rs. 6.047 million will be paid to 38 DPs in
coming month. Collectively, DPs of Firdous and Hashtnagri are 334 (including 96 multiple
count DPs) consisted of shopkeepers, main-lessee, sub-lessees and employees of
shopkeepers. Total payable amount of Firdous Underpass is Rs. 95.037 million to 201 DPs
(including 51 multiple count DPs), out of which Rs. 91.445 million amount have been paid to
181 DPs. While Firdous underpass actual DPs are 158. Similarly, total payable amount of
Hashtnagri Underpass is Rs. 82.135 million to 133 DPs (including 45 multiple count DPs) out
of which Rs. 77.915 million have been paid to 121 DPs. While Hashtnagri underpass actual
DPs are 98. Efforts were made to during the reporting period to reach out and compensate
the long unpaid 5 underage employees of shopkeepers of Zia market, 18 DPs of Firdous & 12
DPs of Hashtnagri underpasses. In this regard, the PDA and PMCSC resettlement staff have
informed the unpaid DPs through shu’ra members of the both underpasses to collect their remaining payments. Similarly, PDA in coordination with PMCSC also approached all the
unpaid DPs at the door steps of unpaid DPs, even the DPs have informed telephonically on
their given cellphone numbers however, the underpasses DPs informed that they will not
23
receive their remaining compensation amount until the amicable resolution of complaint
regarding BS-07 redundant shops for which they had complained to the ADB back in August,
2020. On the other hand, the 5 DPs of Zia market replied that two DPs are now reached to
the age of 18 years and they have applied for preparation of their CNICs which will issue in
couple of weeks while the three DPs informed that they have applied for their guardian
certificates in the court of law. They further informed that they are optimistic and will make
follow up with their lawyer to collect their guardian certificates as soon as possible. Table 1
below provides details of actual DPs and DPs with multiple count impacts as well as details of
paid and remaining DPs.
Table 1: Details of Actual DPs and DPs with Multiple effects and Status of Payment
Name of Underpass
Actual DPs
DPs with
Multiple effects
Paid Unpaid Remarks
Hashtnagri Underpass
98 45 86 12 All 98 DPs have received full compensation amount as per original LARP for 12 months. However, in light of Addendum 2 of LARP-1, 12 DPs are unpaid
Firdous Underpass
158 51 140 18 All 158 DPs have received full compensation amount as per original LARP for 12 months. However, in light of Addendum 2 of LARP-1, 18 DPs are unpaid
40. The payment of compensation is under process and further sincere efforts will be made
to complete it in March/ April 2021.
C 3. Addendum 2 to Reach 1 LARP (continuation of monthly payments to APs
of Hashtnagri & Firdous Underpasses)
41. The rationale for the preparation of this addendum to the LARP of Reach 1 was
envisaged necessary in view of finishing of termination of payment of compensation at the
completion of estimated 12 months in the approved LARP of Reach-1. The key recipients of
payment are the business operators and lessees/ sub-lessees of the shops who were
receiving their businesses income and rent income loss of both the underpasses. Payment of
Hashtnagri underpass as per 12 months schedule was from Feb 2018 to Feb 2019, in which
all the 12 months payment has been made up to Feb 2019. Payment of Firdous underpass as
per 12 months period was from May 2018 to May 2019 in which all the 12 months payments
has been made. The addendum 2 is only focus on the continuation of payment of
compensation to the APs specifically to the business operators and owners of shops of both
the underpasses until the refurbishment process of markets completed and the shops are
hand over back to the shopkeepers.
42. The DPs lodged a complaint at PDA with STRPI team for payment of additional months
beyond 12 months until the formal handover of shops back to them. In this regard, in response
to the complaint and follow up joint discussions among DPs, PDA, PMCSC and ADB, PDA
prepared an Addendum 2 to the LARP of Reach 1 to address the issue of additional payment
of R&R assistance to DPs. The addendum was approved by ADB on July 15th, 2019. The
addendum covered an amount of Rs.8.755 PKR million to 86 shopkeepers & 77 lessees/ sub-
lessees of both the underpasses DPs for per month until, as long as the new shops are
24
constructed and will terminate when the shops are hand over back to the shopkeepers/
lessees. From total additional R&R assistance, 136 DPs have been paid while remaining DPs
will be paid when they contact PDA for payment. These DPs are not available and did not
respond back when PDA contacted them for their payments. With the support of ADB and
active follow up of PDA and STRPI the funds for additional payments were made available. At
present, refurbishment of both the underpasses have been completed and thus formally
handed over to the leaseholder/ shopkeepers. All the shopkeepers moved back to their shops
with satisfaction and overwhelming joy. The additional payment (6 months payment to
Hashtnagri Underpass DPs and 3 and a half months payment to Firdous Underpass) is
underway in fact 90 percent completed; however, few shopkeepers are still remaining
particularly those who are rarely available in Peshawar. In this regard, during the reporting
period these DPs have been informed through their shu’ra members of both the underpasses, contacted them via their given cellphones, and even most of them met personally in the
underpasses to collect their remaining compensation. However, these DPs have informed the
PDA and PMCSC staff that as per their mutual understanding with main-leaseholder and
shu’ra members, they will not receive their remaining payments until the resolution of their
complaint regarding BS-07.
C 4. Addendum 1 to Reach 1 LARP (additional project impacts)
43. Addendum 1 to Reach 1 LARP was prepared in light of additional project impacts
during the project implementation, two additional access-legs from the already proposed
access ramp at Chamkani Morh was envisaged so as to cater the in/ out access of vehicles
specifically coming from the Eastern districts/ areas to/ from Eastern Bus Depot. The proposed
Exit Leg of access ramp have impacted on additional 5 Marla (126.465 m2), nine structures,
disruption of businesses of five shopkeepers, 15 APs (employees of shopkeepers) including
13 employees & 02 watchmen have lose their jobs at Sardar Garhi petrol station/ market. All
APs of Addendum 1 have been paid except 13 APs. Of these 13 DPs, 7 DPs payments had
stuck due to correction in their names or CNICs reported in the addendum report. In the
previous version of IMR (July – October, 2020) the list of corrected names or CNICs has
approved. This list has shared with the finance unit of PDA to process the payment to 7 DPs.
The other remaining 6 underage DPs have been informed telephonically as well as visited
their residents. They informed that their case for making of guardian certificate is under
process and as soon as they get guardian certificates they will informed both the PDA and
PMCSC staff accordingly. In this regard, to expedite the process, the PMCSC resettlement
staff contacted with focal person Mr. Musavir Khan of Sardar Garhi Filling Station DPs who is
a lawyer by profession to further look into the process of making of guardian certificate in the
concerned court on behalf of these 6 DPs. Mr. Musavir Khan has agreed that he will voluntarily
pursue their case and hopefully will get in the couple of week time. Total costs of Resettlement
& Rehabilitation of DPs of addendum 1 are Rs.10.566 million for R&R assistance to 29 DPs,
out of which Rs 5.224 million have been paid to 22 DPs, the remaining Rs 5.342 million will
be paid to 7 DPs in coming month. Out of total remaining amount Rs. 3.472 million is of land.
The revenue department have estimated the cost of 5 Marla acquired land under the status
as agriculture however, the land is in fact of commercial status even in the LARP status of this
impacted land is commercial. In revenue record the status of impacted 5 Marla patch of land
is agriculture since long which status has not been changed to commercial status by the land-
owner. In this regard, the affected person Mr. Zahidullah has approached to the court of law
claiming that his affected 5 Marla land is commercial instead of agriculture. The case is still
underway and whenever, the case will be decided, the remaining of 5 Marla land will be
25
disbursed accordingly. The payment of compensation of addendum 1 is under process and in
addition to the mentioned efforts further efforts will be made to complete it in March/ April,
2021.
C 5. Resettlement Impacts/Status of compensation payment – Reach 2 (0+000 –
5+882)
44. Reach 2 remains in the immediate city centre and is the most crowded section of the
route. All this road section goes elevated just to avoid the impacts on both sides of the road.
This elevated section starts at the Firdous Cinema Chowk/crossing starting elevation through
Malik Saad flyover and remained elevated at Soekarno Road and Shoba Chowk to Railway
Road, the elevated BRT section turns right to cross the railway lines and comes in front of the
Railway Station near Peshawar Press Club. The BRT continues elevated over SM Road cross
Mall Road and remains goes elevated in front of Peshawar Club on Sir Syed Road. It then
turns right into Khyber Road and goes underground at Amman Chowk. The Reach 2 ends just
after Aman Chowk.
45. The construction of Reach 2 caused minor resettlement impacts. Only 19 vendors
using one location in front of Cantonment Board Plaza-at Sunehri Masjid Road were
temporarily displaced during the construction phase. In Reach 2, under the category of
allowances for rehabilitation/livelihood restoration payments, 14 DPs were paid an amount of
PRs. 1,960,000. However, during RP implementation, the STRPI team further re-verified the
DPs location & their businesses from different sources and declared 5 DPs illegible for
compensation. So, those five DPs had not compensated accordingly, and their names
excluded from the list of DPs in Reach-2.
C 6. Resettlement Impacts/Status of compensation payment of Staging Station
in Reach 2 (1+815 – 1+845)
46. The Staging Station is located in Reach 2 in Dabgari Gardens area on Railway Road
which is located along the BRT corridor. The construction of Staging Station caused impacts
on 4 vendors involved in vending businesses in the front gate of the Bangla No.1 & 2, opposite
to Khyber Medical Complex, at Dabgari Gardens who were affected temporarily during
construction phase and need to relocate their businesses. This staging station facility is using
for parking of buses during off-peak hour, a portion of fleet has put off-service on a stand-by
mode, ready to deploy during peak hours. It is designed as a multi - story parking facility, with
bus parking located on ground floor (road level) and a commercial area with 55 shops.
Similarly, on first-floor, park and ride facility provided and a commercial area with 57 shops,
and Trans Peshawar office on the 3rd Floor. A total amount of Rs. 560,000.0 was to be paid
to total 4 vendors have already been fully compensated.
C 7. Resettlement Impacts/Status of compensation payment-Reach 3 (0+000 –
14+104)
47. The only displacement impact in Reach 3 occurred between 4+375 and 4+400. The
construction of the Reach 3 road section has not caused any physical impacts outside of the
RoW. Only at the Spin Jamaat location where 7 static vendors who run their micro businesses
within the ROW have affected temporarily during construction phase.
48. The Reach 3 starts after Aman Chowk, mainly at grade except when there are U-turns
proposed for the mixed traffic, where BRT goes underground as an underpass. The corridor
goes at grade through University Road and Jamrud Road until it turns left onto an elevated
portion before Babe-Peshawar, crossing the existing water channel (also called Khwar) near
26
Habib Jalib Road towards Tatara Park and joins Ring Road in Hayatabad at grade. After
Tatara Park, the BRT corridor is at grade until it goes into a U-turn for BRT corridor on Jamrud
Road and ends at Karkhano market.
49. In Reach 3, under the allowances (Rehabilitation/ Livelihood Restoration) payments, 7
DPs (vendors) were paid an amount of Rs. 980,000 and 07 vendors have given Vulnerability
allowance worth Rs. 315,000.
D. Overall cost of LARPs/ RPs & Addendums Implementation
50. Total cost is PKR. 1,335.19 million, out of which amount worth PKR. 1,322.96 million
have been paid to 522 DPs (including multiple impacts DPs), remaining 55 DPs will be paid
Rs. 12.03 million hopefully in month April/ May 2021. The list of unpaid DPs is provided as
Table 2.
Table 2: List of Unpaid DPs, their location and payable amount
S.# Name Father Location Docume
nt
Type of impact/
entitlement
Amount Payable
Paid Unpaid
1 Asma Alamgir
Arbab Alamgir Khan
Eastern Bus Depot
LARP Crops loss 233,236 233,236
Trees loss 5,761 5,761
2 Attaullah Amanullah
Sardar Garhi Filling Station
Addendum 1
Structure loss
200,000 200,000
Income loss + shifting allowance
460,000 460,000
3 Izhar Khan Muhammad Israr Khan
Sardar Garhi Filling Station
Addendum 1
Shopkeeper
450,000
460,000
4 Nazir Jan Firdous Underpass/ R-1
LARP Decoration loss
150,000 150,000
5 Fasihud Din Qureshi
Muhammad Nazir Qureshi
Firdous / Reach 1
LARP-Add-2
Lessee (rent loss)
543,065 438,065 105,000
6 Khushal (AFGHAN)
Dilawer Reach 1 LARP Vending business loss
140,000 140,000
7 Nazir (AFGHAN)
Masal Reach 1 LARP Vending business loss
140,000 140,000
8 Abdul Ahad (AFGHAN)
Khair Muhammad
Reach 1 LARP Vending business loss
140,000 140,000
9 Saqib Shakeel Ahmad (SK)
Zia market/ Reach 1
LARP Employment loss (below 18)
75,000 75,000
10 Shahbaz M. Ibrahim (SK)
Zia market/ Reach 1
LARP Employment loss (below 18)
75,000 75,000
11 Saqib Imdad Khan (SK)
Zia market/ Reach 1
LARP Employment loss (below 18)
75,000 75,000
12 Adnan Khan
Quresh Khan (SK)
Zia market/ Reach 1
LARP Employment loss (below 18)
30,000 30,000
27
13 Aqib Khan
Syed Atta ur Rehman (SK)
Zia market/ Reach 1
LARP Employment loss (below 18)
30,000 30,000
14 Atta ur Rehman
Kalim ur Rehman
Hashtnagri / Reach 1
LARP-Add-2
Rent loss 543,065 438,065 105,000
Rent loss 467,742 342,742 125,000
15 Farzand Ali Waris Khan
Hashtnagri / Reach 1
LARP-Add-2
Rent loss 935,484 635,484 300,000
16 Muhammad Ali
Gul Muhammad
Hashtnagri / Reach 1
LARP-Add-2
Rent loss 467,742 317,742 150,000
17 Shakoor Ahmad
Muhammad Nazir
Hashtnagri / Reach 1
LARP-Add-2
Rent loss 467,742 317,742 150,000
18 Ashfaq Ahmad
Malik Amir Zada
Hashtnagri / Reach 1
LARP-Add-2
Rent loss 467,742 367,742 100,000
19 Ghayour Ahmad
Muhammad Nazir
Hashtnagri / Reach 1
LARP-Add-2
Rent loss 467,742 -
467,742
20 Adnan Ahmad
Muhammad Nazir
Hashtnagri / Reach 1
LARP-Add-2
Rent loss 467,742 342,742 125,000
21 Umair Shamshad
Hashtnagri / Reach 1
LARP-Add-2
Employment loss (below 18)
75,000 75,000
22 Bashir Rehmatullah
Hashtnagri / Reach 1
LARP-Add-2
Employment loss (below 18)
75,000 75,000
23 Sohail Rahat
Saleh Muhammad
Hashtnagri / Reach 1
LARP-Add-2
Employment loss (below 18)
75,000 75,000
24 Muhammad Basit
Tariq Aziz Hashtnagri / Reach 1
LARP-Add-2
Employment loss (below 18)
75,000 75,000
25 Zubair Abdul Hakeem
Hashtnagri / Reach 1
LARP-Add-2
Employment loss (below 18)
75,000 75,000
26 Uamir Jan Noor Muhammad Khan
Hashtnagri / Reach 1
LARP-Add-2
Employment loss
75,000 75,000
27 Aman ullah Sanober Khan
Firdous/ Reach 1
LARP-Add-2
Rent loss 543,065 385,000 158,065
28 Sultan Muhammad
Sohail Khan
Firdous/ Reach 1
LARP-Add-2
Income loss
900,000 675,000 225,000
29 Ibrahim Khan Noor
Firdous/ Reach 1
LARP-Add-2
Income loss
1,163,710 638,710 525,000
30 Zahir Shah Shahzada Khan
Firdous/ Reach 1
LARP-Add-2
Income loss
1,163,710 338,710 825,000
31 Shah Zameen
Sadbar Firdous/ Reach 1
LARP-Add-2
Income loss
1,163,710 938,710 225,000
32 Mushtaq Masih
Malik Masih
Firdous/ Reach 1
LARP-Add-2
Income loss
1,163,710 450,000 713,710
33 Nisar Muhammad
Sher Zaman
Firdous/ Reach 1
LARP-Add-2
Shifting allowance
30,000 30,000
34 Naimatullah
Ahmed Mir
Firdous/ Reach 1
LARP-Add-2
Employment loss (below 18)
75,000 75,000
35 Ajmal Mir Alam Firdous/ Reach 1
LARP-Add-2
Employment loss (below 18)
75,000 75,000
36 Imran Rehman Gul
Firdous/ Reach 1
LARP-Add-2
Employment loss (below 18)
75,000 75,000
28
37 Ijaz ul Haq Mirza Khan
Firdous/ Reach 1
LARP-Add-2
Employment loss (below 18)
75,000 75,000
38 Muhammad Fida
Firdous/ Reach 1
LARP-Add-2
Employment loss
75,000 75,000
39 Abdur Rehman
Humayun Firdous/ Reach 1
LARP-Add-2
Employment loss (below 18)
75,000 75,000
40 Ibrahim Ismail Firdous/ Reach 1
LARP-Add-2
Employment loss (below 18)
75,000 75,000
41 Ihsanullah (Afghani)
Hunir Jan Firdous/ Reach 1
LARP-Add-2
Employment loss (Afghani)
75,000 75,000
42 Umer Fayyaz Firdous/ Reach 1
LARP-Add-2
Employment loss (below 18)
75,000 75,000
43 Muhammad Ibrahim
Qazi Musanif Khan
Firdous/ Reach 1
LARP-Add-2
Employment loss
30,000 30,000
44 Haroon Maseeh
Mushtaq Maseeh
Firdous/ Reach 1
LARP-Add-2
Employment loss (CNIC not available)
30,000 30,000
45 Muhammad
Fazl-e-Rahim
Sardar Garhi Filling Station
Addendum 1
Employment loss (below 18)
75,000 75,000
46 Rafiullah Amanullah
Sardar Garhi Filling Station
Addendum 1
Employment loss
75,000 75,000
47 Zabeehullah
Muhammad Ismail
Sardar Garhi Filling Station
Addendum 1
Employment loss (below 18)
75,000 75,000
48 Amer Khan Faqir Hussain
Sardar Garhi Filling Station
Addendum 1
Employment loss (below 18)
75,000 75,000
49 Hazrat Niaz Gul Sardar Garhi Filling Station
Addendum 1
Employment loss (below 18)
75,000 75,000
50 Feroz Khan
Ajab Khan
Sardar Garhi Filling Station
Addendum 1
Employment loss
75,000 75,000
51 Muhammad Hayat Khan
Zabita Khan
Sardar Garhi Filling Station
Addendum 1
Employment loss
75,000 75,000
52 Imran Shami
Shafiqullah
Sardar Garhi Filling Station
Addendum 1
Employment loss (Afghani)
75,000 75,000
53 Sohail Khan
Inamullah Sardar Garhi Filling Station
Addendum 1
Employment loss (below 18)
75,000 75,000
54 Qader Khan
Manzoor Khan
Sardar Garhi Filling Station
Addendum 1
Employment loss
75,000 75,000
55 Shahid Khan
Kachkool Sardar Garhi Filling Station
Addendum 1
Employee 75,000 75,000
51. The sixth semi–annual monitoring report outlines the monitoring of the implementation
LARPs of Eastern Bus Depot (EBD) and Reach 1, RPs of Reach 2, staging station-Dabgari
Gardens in Reach 2, Reach 3 and Addendum 1 & 2 of a period of July – December 2020. As
per the loan agreement (para 12a Schedule 5), draft/updated LARPs/RPs internal monitoring
is to be done on a semi-annual basis
52. The project is categorized as category A for social safeguards issues. This report
presents project background and its components, project’s progress in terms of consultations
29
with DPs, compensation of Rehabilitation & resettlement assistance and grievance
management. This internal monitoring report, prepared by PMCSC provides an updated status
of LARP implementation and payments made to the DPs covering the following:
a) No. of affected persons (DPs);
b) Status of land acquisition;
c) Loss of structures and status of payments and income restoration;
d) Affected fruit and timber/ wood trees and status of their payments;
e) Affected crops and payments;
f) No. of DPs paid, unpaid and being paid;
g) Payment of allowances;
h) Linear map of the BRT and visualization of impacts and compensation Payment
i) Consultation meeting with stakeholders
j) Complaints/redress management;
k) Gender action plan implementation
l) Conclusions and recommendations.
30
II. Monitoring Methodology and Indicators and Approach
A. Approach Followed
53. The methodology and approach has been adopted for the preparation this internal
monitoring report included the following: formal and informal consultative process are being
carried out for the project including, but not limited to Focus Group Discussions (FGDs), public
meetings, community discussions, and in-depth and key informant interviews in addition to the
censuses and socio-economic surveys. The following procedures have been adopted during
monitoring of resettlement plan implementation:
• Reviewing the functioning of the institutional mechanism and resettlement
implementation proposed in the LRP/RPs;
• Analyzing LARP, procedures of entitlement, compensation payments processes, and
agreed ADB’s Social safeguard & Resettlement Policy;
• Verifying the records of data/information on compensation payment to DPs against
their entitlement by types of compensation for each individual DPs provided in
LARP/RP documents;
• Conducting consultation/meetings with different stakeholders of the project including
project affected & project beneficiaries and contractor’s staffs/workers employed for
BRT construction works;
• Interacting with DPs through consultations and interviews to assess their level of
satisfaction with resettlement and rehabilitation assistance disbursement process and
grievance redress mechanism.
54. The report covers most of the key indicators provided in the monitoring chapter of the
approved LARP, (including brief explanation in case of deviation from the original plan) as
follows:
a) Review effectiveness of land acquisition and resettlement planning process, i.e.,
adequacy of enumeration of project land acquisition and resettlement impacts,
timeframe, budgetary provision, institutional arrangements, GRM, mitigation of
unforeseen resettlement impacts etc.).
b) Consultations organized, and dissemination campaign carried out with regard to
LARP and DPs are aware of, i.e., entitlement packages, payment procedures,
grievance redress mechanism, etc.
c) Verification whether land and assets situated to the land, resettlement and
rehabilitation assistance payments made only to entitle DPs recorded before cut-
off date.
d) A grievance redress committee is established during the stage of detailed
engineering design to ensure fairness and transparency during the LARP
implementation process.
e) Finances for compensation, resettlement and rehabilitation assistance provided on
time.
f) Advance notices were served to DPs including LARP categories: One-month
notice to Vendors and 2 months’ advance notices to land owners/agriculture,
tenants of Sardar Garhi, owner/lessees/shopkeepers/employees of Zia market,
31
Hashtnagri & Firdous Underpasses and mosques committees given before
shifting/relocation.
g) Timely disbursement of compensation, resettlement and rehabilitation assistance
amount to DPs as per schedule in an efficient and transparent manner and in
conformity with the provisions in the Entitlement Matrix.
h) The LARP compensation amount facilitated /enabled relocation of affected vendors
which simplified shifting their businesses to alternative business sites.
i) Provision of employment opportunities to potential eligible project affected
households in construction works.
j) Verify recording and addressing the concerns/grievances of DPs are dealt on
timely basis during and after land acquisition and resettlement process and
consistent with the LAR.
k) Major issues of conflict between DPs and contractors are addressed efficiently
during implementation of resettlement activities.
l) Effective monitoring of LRP and issues identified for immediate actions will be
referred to the PM-PMU and Project Director of TMTD, and NGO for modifications
in the LRP based on the progress and lessons learned in the course of LRP
implementation and additional funds to cover additional activities.
m) Effective implementation of Gender Action Plan, collection of gender
disaggregated data and gender specific consultations with women.
n) Degree of satisfaction of DPs and AHs with support received for restoration of their
income and livelihood.
o) Any changes in social and economic parameters related to living standards of DPs.
p) Efficient restoration of public utilities and/or other affected services/infrastructure.
q) Lease agreements signed for the temporary use of land, full restoration of land
after completion of construction.
55. In line with the above procedures, following activities were carried out for internal
monitoring and progress reporting. The following monitoring indicators as provided in
approved LARP of Reach 1 and two RPs of Reach 2 and 3 of BRT corridor have been
used/followed during preparation of this internal monitoring report.
A 1. Review of Project Documents
56. The review of the documents was carried out during the reporting period. The main
documents reviewed and finalized included the land acquisition and resettlement plans of
various reaches and other safeguard related documents such as Due Diligence Report (DDR),
addendum and design plans which enabled the PIU to follow an appropriate line of action for
the implementation of LARP/RPs to accomplish the objectives of the assignment.
57. From design to implementation the project is being implemented on fast track. Due to
changes in project design, the LARPs/RPs were required to be continuously, being revised
and updated. As anticipated, the preparation of addendums and DDRs will continue till the
completion of this BRT project.
A 2. Data Collection and Analysis
58. The preparation of Due Diligence Report (DDRs), addendum of most of the LARP/RP
related documents have been prepared through consultations with DPs, conducting surveys
and collection of regular data and analysis. Both the social and resettlement units at PIU, PDA
32
and Project Management Construction Supervision Consultants (PMCSC) were involved in
data collection and analysis in the impact assessment and verification.
A 3. Consultation with Key Stakeholders
59. Several consultation meetings were held with the stakeholders during the progress
reporting period summarized below.
• A number of regular meetings held with Deputy Commissioner/District Revenue Office
Tehsildar / Patwari confirming funds transferred, document sharing, request for
sections notification under LAA and land demarcation in Sardar Garhi required for
BRT.
• Meetings held with Directors/Deputy Directors PDA of Reach 1, 2 and 3 for DPs right
sensitization, on the spot complaint resolution and sensitive grievance redress.
• Meeting with PMCSC for data cleaning, verification of missed DPs and current unit
rate estimation and help for DP identification and determining eligibility for
compensation payment.
• Regular meetings with KPUMA, TMDT and Trans Peshawar to discuss allocating BRT
Commercial spaces to DPs and gender related issues.
• Conducted numerous meetings with representatives of DPs of Sardar Garhi, Zia
market, Hashtnagri underpass, vendors of Reach 1, 2 and 3.
• Meetings held with DPs for disclosure of full information to women and vulnerable
DPs to make them aware of their entitlements and obligations, compensation and
allowances, complaints and grievance redress procedures.
• Regular meetings with DPs to guide them in account opening and assisting them to
obtain their CNICs.
• Meetings and consultations undertaken with key stakeholder were regularly
documented and action points were followed up.
• Meeting with DPCs to make them to understand the grievance redress mechanism
established at PIU.
• Meetings with ADB mission for sharing project progress and updates.
33
III. Institutionalisaion of LARP/RP Implementation Process
A. Institutional Roles and Responsibilities
60. The Project’s executing agency (EA) is Khyber Pakhtunkhwa Urban Mobility Authority (KPUMA). Transport and Mass Transit Department (TMTD) provides administrative and
secretariat support to KPUMA through the PMU at TMTD and with support of the Project
Management, Coordination and Capacity Building (PMCCB) consultants. KPUMA is
responsible for overall coordination of the project and ensure availability and timely release of
counterpart funds. The project Implementing Agencies are (IAs) Peshawar Development
Authority and Trans Peshawar.
61. Peshawar Development Authority (PDA) is the Implementing Agency of LARP/RPs.
PDA is responsible for day-to-day implementation/operations of LARP/RPs and has
established adequate and appropriate systems for LARP/RPs implementation including
institutional arrangements, internal monitoring and reporting. PDA has also been managing
functions of consultants, contractors and other relevant parties regarding social safeguards
management. The Design and Supervision Consultants are carrying out the supervision of the
project, including social and environmental management and supervision and monitoring of
LARP/RPs and EMP implementation.
62. EA is supported by Project Implementation Unit (PIU) housed within PDA assisted by
the Social Team for Resettlement Plan Implementation (STRPI). The PDA is using the
services of the STRPI with assistance from the Project Management Construction Supervision
Consultants (PMCSC) for implementation of the LAR related activities including
implementation of R&R assistance to DPs and in liaison with Deputy Commissioner, Peshawar
for land acquisition and subsequent compensation payment to DPs.
63. The Land Acquisition and Resettlement Plan Implementation Committee was
established and notified by PDA to ensure that safeguard management including land
acquisition is in compliance with ADB, SPS 2009 requirements as well as to resolve field
related issues see Annex 1.
64. A Resettlement Assistance Disbursement Committee was established and notified to
assist PDA, the implementing agency in fulfilling its obligations relating to transparent and
timely payment of resettlement and rehabilitation assistance to DPs of the project according
to the entitlements of each category of DPs as per approved LARP/RPs documents, Annex
2.
65. To ensure effective implementation of Grievance Redress Mechanism, a Grievance
Redress Committee (GRC) was established and notified to review and investigate all
grievances lodged by DPs and effectively address and resolve them in a timely manner. The
Social Development and Resettlement Specialist has been serving as a member/secretary of
the GRC, Annex 3and GRC Meeting Notification as Annex 4.
66. The Reach-wise focal persons were nominated and notified to lead to the “First Tier of the Grievance Redress Mechanism” for timely and effective resolution of grievances to ensure the successful implementation of the Project. The STRPI has been facilitating the focal person
of each Reach in investigating and providing guidance in grievance redress matters and record
keeping, Annex 5.
67. DPs Committees (Shura) already established was activated and revitalized to
represent and safeguard interest of DPs. The Shura is also playing the role of a bridge
34
between PIU and DPs and helping in grievance resolution. Male & Female DPCs at Sardar
Garhi were established and are functioning.
68. A Gender Focal Group comprised of KPUMA, Trans Peshawar, STRPI, PMCSC and
Social Welfare Department was established to implement Gender Action Plan. The focal group
convenes meetings on monthly basis to review the Gender Action Plan.
35
IV. Progress on LARP/RP Implementation
A. LARP/RP Review, Endorsement, and Implementation
69. The Land Acquisition and Resettlement Plan (LARP/RPs) are prepared for Civil Works
Construction of all three Reaches were approved by KPUMA and ADB and uploaded on PDA
and ADB websites. The addendum of Reach 1 has prepared by the PMCSC due to additional
impacts following the design changes. Table 3, 4 and 5 summarizes the status of preparation
of LARP/RP and DDR related documents, their subsequent approval and implementation in
progress.
Table 3: Status of LAR Related Documents
Civil Works
Construction
Package
Description Required LAR
Documents
Current Status
(As in June 2020)
1 Package 1 Reach
1 (Chamkani Mor
to Firdous
Cinema)
LARP and ILRP Design of Firdous and Hashtnagri underpasses
finalized. No changes in the impacts and
number of DPs noted. So the LARP of Reach 1
already disclosed on ADB website remains
unchanged.
2 Reach 2 (Firdous
Cinema to Aman
Chowk)
Resettlement
Plan (RP)
Approved, uploaded on ADB Website
3 Reach 3 (Aman
Chowk to
Hayatabad)
Resettlement
Plan (RP)
Approved, uploaded on ADB Website
4 Eastern Bus Depot LARP Revised LARP submitted to ADB and have been
approved.
5 Reach 1,
Addendum
Addendum Reviewed and accepted by ADB
6 Khyber Teaching
Hospital
Underpass
Due Diligence
Report (DDR)
Reviewed and accepted by ADB
7 Due diligence of
BRT allied
structures and
staging facility.
Due Diligence
Report (DDR)
Due diligence of BRT allied structures including
staging facility after the completion of addendum
2 to Reach 1 and few other outstanding tasks.
8 income livelihood
restoration plan
ILRP Report Reviewed and accepted by ADB
9 Due diligence of
Karkhano road
section
Due Diligence
Report (DDR)
DDR of Karkhano road section of Reach-3
submitted to ADB and accepted.
36
Table 4: Detail of Progress on LARP/RP implementation
Sr.
No
.
LARP
Impacts Scope and Processes Current Status Action by
L1 Package 1
Reach 1
(Chamkani
Mor to
Firdous
Cinema)
Approved, uploaded on
ADB Website
33 out of total 36 vendors in Reach
1 have been compensated while the
remaining 3 vendors are underage
(below 18 years), compensation
payments of lands to land owners
and Payments of monthly
allowances to project affected are in
process, almost 99 % (1,322.96 out
of 1,335.19 PKR million) of
payments to DPs have completed.
Services have provided to DPs by
PMCSC, STRPI and PDA, but in
remaining 12% (508 out of 576 DPs)
55 DPs including shopkeepers/ lessees
of underpasses (whom had refused till
resolution of ongoing complaint
regarding BS-07 issue), corrected cases
of Sardar filling station , Afghanis,
under 18 or have inheritance issues
LARP Team
PMCSC, STRPI
of PIU, PDA.
L1.
1
Construction
works at
Hashtnagri
Underpass
Construction works in
process
Almost 100% construction works
have completed,.
Residence
Engineer-
PMCSC,
Contractor, LARP
Team PMCSC,
STRPI of PIU,
PDA
L1.
2
Construction
works at
Firdous
Underpass
Construction works in
process
Almost 100% construction works
have completed,.
Residence
Engineer-
PMCSC,
Contractor, LARP
Team PMCSC,
STRPI of PIU,
PDA
L2 Reach 2
(Firdous
Cinema to
Aman Chowk
& staging
station –
Dabgari
Gardens
Approved, uploaded on
ADB
In Reach 2 there were a total 23
vendors. All the 23 Vendors have
been compensated for relocation.
LARP Team
PMCSC, STRPI
of PIU, PDA.
L3 Reach 3
(Aman
Chowk to
Hayatabad
Approved, uploaded on
ADB Website Approved
In Reach 2 there were a total 7
vendors. All the 07 Vendors have
compensated for relocation.
LARP Team
PMCSC, STRPI
of PIU. PDA.
L4 Eastern Bus
Depot
Draft submitted to ADB for
approval
Payments of compensation to land
owners are in process, almost 97%
of payments to DPs have
completed, the remaining 03%
payment expected to be completed
early in 2020.
LARP Team
PMCSC, STRPI
of PIU, PDA.
37
L5 Land
Acquisition
and
Compensatio
n Payments.
Major portion of land
Acquisition and
disbursement of
compensation payments to
land owners have
completed, Monthly
allowances like
(displacement, vulnerability,
subsistence etc.) are in
progress.
As per Addendum LARP Reach-1,
Additional 5 Marla land had
acquired at Chamkani Mor, land
owner has been compensated as
per market value of land in the area.
Owner of land demanded his land to
be consider in the category of
commercial land, for this purpose
he have filed his case in court, for
the last 2 years resolution awaited.
There are total two cases in the
court of law of two different
individuals regarding the same
issue of land.
LARP Team
PMCSC, STRPI
of PIU, PDA.
L6 Disseminatio
n of
information,
consultation
participation
with DPs.
(i)Urdu translation of
grievances redresses
mechanism (GRM) and
Urdu Language Brochure
for overall BRT project have
disseminated during
consultations and have
disclosed through media.
(ii)Urdu translation of
Summary of Reach -1 LARP
have completed and copies
have distributed among DPs
of Reach-1.
(iii) Grievances of DPs are
addressed as a permanent
activity of project and CRM
sheet have developed to
keep record of grievances
and its resolution. GRM
(Urdu) brochures have
distributed among project
affected persons
Ongoing activity LARP Team
PMCSC
L7 Consultation
&
Participation
with
Community
regarding
disclosure/di
ssemination
of information
on BRT
project LARP
implementati
on
Community consultation
relating to ongoing project
development activities
Sharing of completed detail
design layout maps and
getting their feedback.
Agreements with
communities, verifications
by PDA, Revenue
department, DC
Representative and STRIPI.
Preparation of MOM and
documentation of the
activities and events
Ongoing activity on daily basis LARP Team
PMCSC
L8 Recruitment
of eligible
candidates
from project
DPs in
construction
works of the
project and
Listing of eligible candidates
with complete Bio data from
project DPs are in process,
contractor, PDA, Trans
Peshawar have
communicated by LARP
team to work for hiring of
local project DPs in their
Contractor have started recruiting
local project DPs at contractor camp
as well as on construction sites.
According to record there are 27
local and 12 DPs are working at
contractor camps.
LARP Team
PMCSC,
Contractor, Trans
Peshawar, PDA.
38
Offices of
BRT project
as well.
respective Offices as well as
on construction sites.
L9 Grievances
Redresses
Mechanism
Grievances of DPs are
addressed as a permanent
activity of project and CRM
sheet have developed to
keep record of grievances
and its resolution. GRM
(Urdu) brochures have
distributed among DPs
Ongoing activity LARP Team
PMCSC, STRPI.
L1
0
Addendum/D
ue diligence
Preparation of Due
Diligence Report (DDRs),
and addendum of most of
the LARP/RP related
documents is under process
at project area as per the
project requirements.
Ongoing project activity on need
basis
LARP Team
PMCSC
L1
1
Opening of
Individual/Joi
nt Account by
Affected
Community
Both individual and joint
bank accounts have opened
for receiving individual and
communal compensation
Pushing the remaining few
affected HHs to open bank
accounts
Majority of Project DPs have compensated through their bank accounts, 55 DPs are pending, out of 55 there are 05 Afghan Refugee cases, 05 cases of block CNIC and 26 are underage, seven (7) DPs need corrections in their Names & CNICs numbers and 16 DPs cheques are ready . In these cases, for Afghan Refugees, PDA have communicated with Commissionerate of Afghan Refugee (CAR), but have no positive result. Per successive meetings Mechanism of compensation payment to Afghan Refugees pending PDA/ADB decision consensus. For below 18 cases guardian
certificate (GCs) needed, in which
many DPs have provided their GC
and made compensation to them.
The remaining underage cases are
under-process and according they
will their GC soon and will then
submit to PDA for their remaining
payments.
LARP Team
PMCSC,
Community
Organization.
L1
2
Implementati
on of Social
and Gender
action plan
Social monitoring survey is
all three Reaches (1, 2, 3)
including working sites
(construction, offices, labour
camps and established
Grievance Redress
Mechanism) and also the
social/sensitive receptors.
Women of the project
corridor are particularly
sensitized regarding BRT
project incentives for
women, their role in
developments activities are
Ongoing activity on daily basis Social & Gender
Teams PMCSC
39
discussed with them on
regular basis.
L1
3
Implementati
on of income
livelihood
restoration
plan
Draft submitted to ADB for
approval
Disbursement of payments to
DPs for their assets have almost
completed, listing of eligible
candidates with complete Bio data
from project DPs have completed,
contractor, PDA, Trans Peshawar
have communicated by LARP team
to work for hiring of project
DPs/locals in their respective
Offices as well as on construction
sites, capacity building for skill
development and other
measures for income and
livelihood restoration are in
process.
LARP Team
PMCSC
Note: Major portion of disbursement to DPs have completed, 55 DPs are pending including 05 Afghanis, 05 cases of block CNIC and 26 are underage, PDA have communicated with Commissionerate of Afghan Refugees but have no positive result, for below 18 cases guardian certificate required, the DPs are waiting for their age of maturity/lack of interest, it is to be noted that Hashtnagri and Firdous Under-Passes compensation payment start on 10 February 2018, Provision of compensation for DPs in LARP is for 12 months, but according to LARP as mentioned in page 87 amount will be paid to the entitlement holders as long as the new shops are not handed over. When the new shops are handed over to DPs, the compensation payments will be terminated. Addendum 2 to reach 1 LARP for payment of loss of business income to the DPs of Firdous and Hashtnagri underpasses has been prepared and hence approved by the ADB. The LARP had the payments covered until Dec 2018, however extended in view of ongoing construction on both underpass markets. At present, shops have been handed over to shopkeepers of both the underpasses and similarly payments to underpasses DPs is at the completion stage. It was agreed that payment to DPs will continue until all shops are returned to them. For this purpose, addendum 2 have prepared by PMCSC.
Table 5: Summary of overall compensation payment and R&R Assistance
S.#
Document (LARP/
RP/ Addendu
m)
Type of Payment
Compensation
Amount Payable
Total APs
Payment Status
Paid Amount
Unpaid Amount
Paid APs
Unpaid
APs
PKR in M)
M F Total
(Rs. M.) (No.) (N0.
)
1
EBD LARP
Land Compensation EBD
1,095.18 44 29 73 1,095.18 - 73 -
2 Crops Compensation EBD
0.754 11 1 12 0.521 0.233 11 1
3 Affected Trees EBD 4.827 20 6 26 4.821 0.006 25 1
4 Sardar Garhi Tenant s
1.35 10 0 10 1.35 0 10 0
5
LARP of Reach 1
Affected Building Structures Zia Market
15.766 1 1 15.766 - 1 -
6 Affected commercial land (Zia Market) Chamkani
12.63 1 0 1 12.63 0 1 -
7 Affected prayer place Reach 1
2.705 - 2.575 0.13 - -
8 Affected Shop’s Hashtnagri decoration
5.425 34 1 35 5.425 0 35 -
9 Affected Shops of Firdous Decoration
12.695 41 2 43 12.425 0.27 41 2
10 Vendors 5.04 36 0 36 4.62 0.42 33 3
40
11 Zia Market Shopkeepers
4.14 9 0 9 4.14 0 9 0
12 Zia Market Employees
1.02 16 0 16 0.735 0.285 11 5
13 Zia Market House Renters/owner
0.44 4 0 4 0.44 0 4 0
14 Prayer Place APs 0.095 1 0 1 0.095 0 1 0
15 Hashtnagri Lasses (Monthly)
18.242 16 0 16 16.499 1.418 10 6
16 Hashtnagri shopkeeper Income loss (Monthly)
54.223 34 1 35 54.223 0 35 0
17 Hashtnagri Shifting Allowance shop keeper
1.17 0 1.17 0 0
18 Hashtnagri Employees Compensation
3.075 46 1 47 2.598 0.477 41 6
19 Firdous Lessees(Monthly)
28.782 21 1 22 28.204 0.578 17 5
20 Firdous Shopkeeper income loss (Monthly)
46.285 37 1 38 44.306 2.104 36 2
21 Firdous Shifting Allowance shop keeper
1.41 0 1.38 0.03 0
22 Firdous Employee 5.865 98 0 98 5.13 0.735 87 11
23 RP of
Reach 2 Vendors 1.96 14 0 14 1.96 0 14 0
24 RP of
Staging Station
Vendors 0.56 4 0 4 0.56 0 4 0
25 RP of
Reach 3 Vendors 0.98 7 0 7 0.98 0 7 0
26
Addendum 1 to
Reach 1 LARP
SKs Access Ramp Reach 1
2.75 7 - 7 1.83 0.92 5 2
27 Employees Access Ramp Reach 1
1.35 18 - 18 0.6 0.75 8 10
28 Land Compensation Access Ramp Reach 1
5.052 1 1 1.58 3.472 1 -
29 Affected Structures Access Ramp Reach 1
1.414 3 - 3 1.214 0.2 2 1
Total 1,335.19 534 43 577 1,322.96 12.03 522 55
Multiple affect APs 121 5 126
Total APs excluding multiple
affects 412 38 450
70. Land acquisition for construction purposes, e.g., for construction of bus stations and
other allied structures as well as warehouses for storing construction materials & equipment
at all reaches have done on need basis.
41
B. Disbursement of compensation payments to DPs
B 1. Compensation payments for affected Assets
71. For compensation payment, as per the entitlements of DPs provided in the LARP of
each Reach were studied and analyzed. As per the project R&R policy, all affected households
are entitled to a combination of compensation measures and resettlement assistance,
depending on the nature of their ownership rights over the affected assets and the scope of
the impact, including the social and economic vulnerability of the affected persons. The
compensation disbursement plans have been prepared for all the affected non-titleholders and
for the titleholders as per the provisions of the LAA 1894 and SPS 2009 are being followed in
disbursement of land compensation to the affected land owners. The competent authorities
for Land Acquisition (LAC) and PDA have prepared the plans for providing compensation for
those who lose their lands and assets as per the provisions. in general terms, the DPs in the
project are entitled to the following types of compensation and assistance:
• compensation for loss of land, trees, etc. at replacement value;
• compensation for residential/commercial structures at replacement value;
• assistance for loss of business/wage income;
• assistance for shifting;
• rebuilding and/or restoration of community resources/facilities; and
• special additional assistance for vulnerable households
B 2. Preparation of Claim Forms and Payment Vouchers
72. DPs claim forms and payment vouchers were prepared for each DP and verified by all
concerned stakeholders with details category of women and vulnerable DPs, asset lost,
compensation and all types of resettlement and rehabilitation assistance. LAC and Director
Finance were orientated on claim forms and payment vouchers. All compensation payments
conducted in transparent manner. ADB Consultants monitored the initial compensation
payments process.
C. Project Impacts and Compensation Disbursement
73. Total number of DPs are 450 (including 126 cases of multiple effects) in number. Table
6 summarizes the type of impacts and status of compensation payment to each category of
affected assets. And the detail of overall compensation payment for different categories
(including allowances) of project DPs with number of paid DPs against each category are
provided as Annex – 11.
42
Table 6: Overall Summary Status of Implementation of LARP, Reach 1
S.
No
.
Type of Impacts
Compensation
Amount
Payable
Total
DPs
Payment Status
Paid
Amount
Unpaid
Amount
Paid
DPs
Unpaid
DPs with
payments
ongoing
PKR in M) M F Total (Rs. M.) (Rs. M.) (No.) (N0.)
1. Land Compensation 12.63 1 0 1 12.63 - 1 -
2. Affected Building
Structures 36.581 111 10 121 35.090 1.491 67 07
3. R&R Assistance 169.787 318 04 322 163.54 6.047 284 38
Total 219.00 430 14 444 211.26 7.54 352 45
N.B: Total DPs 576 including multiple affects.
D. Land Acquisition Impacts and Compensation Payment
74. The list of DPs has been vetted and finalized by the LAC as per the details available
in the revenue records and LARP. The compensation for the titleholders in the impact survey
were estimated as per the provisions of Land Acquisition Act 1894. Most of the individual
titleholders received their compensations. A total of 174.4 kanals land was required for the
construction of Eastern Bus Depot at Sardar Garhi, which has been fully acquired. A total
amount of land compensation was calculated Rs. 1,095.182 million was to be paid to 73 DPs.
Out of which, Rs. 1,095.182 million have been paid to 73 DPs (100%). Further details about
land compensation to the DPs are provided in Table 7. The rates of the crops and trees have
been assessed by officials of agriculture and forest department keeping in view the of the
current market rates. The rates provide to DPs were based on the damages incurred due to
the BRT construction works.
Table 7: Payment of Affected Land, Crops and Trees (EBD) as of June 2021.
S.
# Type of Payment
Compensation Amount
Payable
Total
DPs
Payment Status
Paid
Amount
Unpaid
Amount
Paid
DPs
Unpaid
DPs
PKR in M) M F Total (Rs. M.) (Rs. M.) (No.) (N0.)
1.
0 Land Compensation 1,095.182 44 29 73 1,095.182 0.00 73 0
2.
0
Crops
Compensation 0.754 11 1 12 0.521 0.233 11 1
3.
0 Affected Trees 4.827 20 6 26 4.821 0.006 25 1
Total 1,100.763 75 36 111 1,100.52 0.239 109 02
E. Payment of Residual Land
75. As far as payments of residual lands are concerned, there is only one case of 5 Marla
land strip owned by Zahidullah at Chamkani. Mr. Zahidullah have approached to court two
years ago to be consider his land as residential land, the case is in court for the last mentioned
period, pending for decision.
43
F. Payment of Affected Crops
76. Compensation for crops will be paid to a total number of 12 DPs. The compensation
amount calculated as Rs. 0.754 Million. To date 11 DPs have been paid Rs. 0.521 Million and
the remaining one two DP will be paid Rs.0.233 Million, Payments are expected in the current
month of September, 2021.
G. Payment of Affected Trees
77. In case of fruit and wood trees, a total of 26 DP had to be paid an amount of Rs. 4.827
Million. During the reporting period, 25 DPs have been paid an amount of Rs. 4.821 Million.
The remaining 01 DP has to be paid an amount of Rs. 0.006 Million, payments are expected
by September, 2021.
H. Payment of Affected Building Structures
78. Census survey results show that total amount of compensation for loss of residential/
commercial structures was Rs. 36.591 million has to be paid to 79 DPs including three female
owner of a commercial structure. Both residential and commercial structures will be impacted
due the BRT construction. Out of 79 DPs 74 DPs have compensated Rs. 35.491 million, the
remaining 03 DPs will be paid Rs. 1.100 million by September 2021. The summary of impacted
structures and compensation payment to DPs has been given in Table 8.
Table 8 Type of Structures and Compensation Payment of Reach 1
S.
No. Type of Structures
Compensation Amount
Payable
Total
DPs
Payment Status
Paid
Amount
Unpaid
Amount
Paid
DPs
Unpaid
DPs
PKR in M) M F Total (Rs. M.) (Rs. M.) (No.) (N0.)
1. Affected Building
Structures Zia Market 15.766 1 0 1 15.766 0.000 1 0
2. Affected prayer place 2.705 0 0 0 2.575 0.130 0 0
3. Affected Shop’s Hashtnagri decoration
5.425 34 1 35 5.195 0.230 34 1
4. Affected Shops of
Firdous Decoration 12.695 41 2 43 11.955 0.740 39 2
Total 36.591 76 3 79 35.491 1.100 74 3
I. Payment for Resettlement and Rehabilitation Assistance
79. The Resettlement and Rehabilitation (R&R) Assistance involve two types of
allowances covering lump sum and monthly payments for income loss. Regarding monthly
payments for income loss, it was agreed in the approved LARP of Reach-1 that the business
operators of both the underpass markets i.e. Firdous and Hashtnagri Underpasses will lose
their business income for a period of around 6 to 12 months depending on the duration of
remodeling and refurbishment activities. In this context, payment of Hashtnagri Underpass as
per 12 months schedule was from Feb, 2018 to Feb, 2019, in which all 12 months payment
44
has been made while for the remaining months above 12 months period is at the completion
stage. Similarly, payment of Firdous Underpass as per 12 months period was from May, 2018
to May, 2019 in which all 12 months payment has been made while for the remaining/
additional months above 12 months period is at the completion stage. So collectively, both the
underpass DPs have been collected 12 month’s payments as well as collecting payment for
additional months beyond 12 months period.
80. It has been noted that even beyond 12 months, the refurbishment/ remodeling work on
both the underpasses could not completed timely. Resultantly the shopkeepers obviously
could not move back to their shops in both the underpasses and have to stay away until the
full completion of refurbishment work. In that scenario, the DPs lodged a complaint at PDA
with STRPI team for payment of additional months beyond 12 months until the formal
handover of shops back to them. In this regard, an addendum 1 to Reach 1 LARP for additional
payment (beyond 12 months) has been prepared which has already been approved from ADB.
The additional payments (3-months additional payment to Hashtnagri Underpass DPs i.e. from
June-August, 2019 and 6-months to Firdous Underpass DPs i.e. from March-August, 2019) to
DPs of addendum 1 to Reach 1 LARP of both the underpass markets is underway and will be
completed in September/ October, 2021.
81. For allowances (rehabilitation/ livelihood restoration) payments, 382 DPs including four
female DPs had to be paid an amount of Rs. 178.737 Million. Out of total, 322 DPs have been
paid an amount of Rs. 164.151 Million on account of allowances/ livelihood restoration
including income loss, relocation, shifting allowance and vulnerability allowance. The
remaining 55 DPs has to be paid Rs. 14.585 Million by September/ October 2021. The
summary of the assistance provided for the affected persons are given in Table 9.
Table 9: Overall R&R Assistance Payment to DPs of Reach1, 2, 3 & Staging Station and EBD & of Addendum 1
S. No Type of Payment
Compensation
Amount Payable
Total APs
Payment Status
Paid Amount
Unpaid Amount
Paid APs
Unpaid APs
PKR in M) M F Total (Rs. M.) (No.) (N0.)
1 Vendors (36 R1, 14 R2,
7 R3, 4 Staging Station) 8.540 61 0 61 8.120 0.420 58 3
2 Zia Market Shopkeepers
4.140 9 0 9 4.140 0.000 9 0
3 Zia Market Employees
1.020 16 0 16 0.735 0.285 11 5
4 Zia Market House Renters/owner
0.440 4 0 4 0.440 0.000 4 0
5 Prayer Place APs 0.095 1 0 1 0.095 0.000 1 0
6 Sardar Garhi Tenant s (of EBD land)
1.350 10 0 10 1.350 0.000 10 0
7 Hashtnagri Lasses (Monthly)
18.242 16 0 16 15.660 2.581 14 2
8 Hashtnagri shopkeeper Income loss (Monthly)
54.223 34 1 35 52.519 1.703 34 1
9 Hashtnagri Shifting Allowance shop keeper
1.170 0 1.170 0.000 0
45
10 Hashtnagri Employees Compensation
3.075 46 1 47 2.595 0.480 40 7
11 Firdous Lessees(Monthly)
28.782 21 1 22 28.099 0.683 20 2
12 Firdous Shopkeeper income loss (Monthly)
46.285 37 1 38 42.792 3.492 35 3
13 Firdous Shifting Allowance shop keeper
1.410 0 1.380 0.030 0
14 Firdous Employee 5.865 98 0 98 5.055 0.810 86 12
15 Shopkeepers of Access Ramp (Addendum 1)
2.750 7 - 7 - 2.750 - 7
16 Employees of Access Ramp (Addendum 1)
1.350 18 - 18 - 1.350 - 18
Total 178.737 378 4 382 164.151 14.585 322 60
82. To focus more on project role in providing relief to poor and vulnerable DPs, payments
made to the vulnerable DPs through vulnerability allowance is provided in the Table 10.
Table 10: Status of Payment to Vulnerable DPs, Reach 1, EBD and Addendum 1
S. No.
Type of Payment
Vulnerability
Allowance
Amount
Total DPs
Payment Status
Payable Paid
Amount Unpaid Amount
Paid DPs
Unpaid DPs
PKR M F Total (Rs.) (Rs.) (No.) (N0.)
1 Vendors 5.040 36 0 36 4.620 0.42 33 3
2 Employee of Zia Market 1.020 16 0 16 0.660 0.73 11 5
3 Employee of Hashtnagri Underpass
3.075 46 1 47 2.595 0.48 40 7
4 Employee of Firdous 5.865 98 0 98 5.13 0.735 87 11
5 Prayer Place Imam 2.705 1
1 0.095 0.00 1 0
6 Sardar Gharhi Tenants (of EBD)
1.350 10 0 10 1.350 0 10 0
7 Employees access ramp (Addendum 1)
1.350 18 0 18 - 1.350 - 18
Total 20.405 225 1 226 14.450 3.715 182 44
J. Reach 2 & RP-Staging Station Implementation Status (payment for
allowances)
83. In Reach 2, under the allowances category (rehabilitation/ livelihood restoration)
payments, 14 vendors of Reach 2 and Staging Station (RP) were paid an amount of total Rs.
2,520,000. Table 11 provide additional details about vendors and their payments for
rehabilitation and assistance allowances.
46
Table 11: Overall R&R Assistance Payment to DPs – Reach 2 & RP-Staging Station
S.
No
.
Impact Category
Compensation Amount
Payable
Total
DPs
Payment Status
Paid
Amount
Unpaid
Amount
Paid
DPs
Unpaid
DPs
PKR in M) M F Total PKR PKR (No.) (No.)
1.0 Vendors - Dabgari
Garden (RP-
Staging Station)
560,000 4 0 4 560,000 0 4 0
2.0 Vendors -Firdous
Cinema Chowk –
Aman Chowk (R-2)
1,960,000 14 0 14 1,960,000 0 14 0
Total 18 0 18 2,520,000 0 18 0
K. Reach 3 Implementation Status (payment for vulnerability allowances)
84. In Reach 3, under the allowances (rehabilitation/ livelihood restoration) payments, 7
DPs (vendors) were paid an amount of Rs. 980,000. Table 12 provides details about DPs and
their payments for rehabilitation and assistance allowances.
Table 12: Overall R&R Assistance Payment to Vulnerable DPs of Reach3
S.
No. Impact category
Compensation Amount
Payable
Total
DPs
Payment Status
Paid
Amount
Unpaid
Amount
Paid
DPs
Unpaid
DPs
(PKR in M) M F Total PKR PKR (No.) (No.)
1.0 Vendors 980,000 7 0 7 980,000 0 7 0
Total 980,000 7 0 7 980,000 0 7 0
85. The Table 13 provides the details of vulnerable DPs and payment status in terms of
providing vulnerability allowance to DPs of the Reach 3.
Table 13: Status of Payment to Vulnerable DPs, Reach 3
S.
No.
Type of
Payment
Vulnerability Compensation Amount
Payable
Total
DPs
Payment Status
Paid
Amount
Unpaid
Amount
Paid
DPs
Unpaid
DPs
PKR M F Total (Rs.) (Rs.) (No.) (N0.)
1 Vendors 315,000 07 0 07 315,000 0 07 0
47
86. The linear maps of all three reaches for impact visualization are provided as Annex 6
L. Action Plan for the Compensation Payment to Unpaid DPs of Reach 1
87. The compensation payment to the remaining DPs is ongoing. It was discussed with
the Project Director that the Lump sum payment to all DPs expectedly will be completed at the
end of June, 2021. The decision on the mode of payment to the unique DPs such as Afghan
nationals, blocked NIC holders and underage DPs are still awaited.
M. Reasons for Pending Payments:
88. Payment process for compensation against entitled rehabilitation and livelihood
restoration allowances was started after approval of LARP, RPs and Addendums which is in
progress and on-going. Since, at the start of project construction phase and further availability
of funds, NHA continued its repeated efforts to outreach unpaid DPs and ensure delivery of
compensation to all payable DPs. However, due to some underage DPs having no CNICs,
Afghan nationals, corrections in DPs names or CNICs numbers and sometimes administrative
impediments caused delay in payment to 55 project DPs. The main reasons contributing
towards the delay in payments are narrated below.
i. The procedural delay: On account of busy schedule of PDA-PIU officials often cause
procedural delay, conversely become a source of mistrust and fear of loss of pending
payments among APs. As a result of this type of delay, the APs sometimes complaint
to PDA or on higher level to the ADB. Additionally, the time and again delay and
operationalization of BRT buses further create disappointment among the remaining
DPs. In this regard, the active liaison of PMCSC and STRPI team and ADB consultants
have expedited the process and in the last couple of weeks, the payment process has
started again. Even the unexpected transfer of DG-PDA further cause delay in
payments to DPs.
ii. Non-availability of STRPI team: The only member of STRPI team was not granted
further approval for continuation of her services particularly till the completion of LARP
implementation which created further delay in payments to remaining project DPs. The
STRPI team was primarily responsible to provide necessary support and guidance to
PDA in LARP implementation and maintaining database of payments and related
records. The STRPI was also responsible to oversee day to day implementation of
LARP including Grievance Redress Mechanism (GRM) and further collaboration with
concerned parties of the project throughout the project operations. Therefore, in the
absence of only STRPI member further delaying the remaining payments to 55 DPs.
During the reporting period, due to non-availability of STRPI team member, the
PMCSC resettlement face difficulty in obtaining the data regarding DPs, particularly
updated information if any and other necessary compensation related information for
incorporation in the bi-annual report..
iii. Afghan Nationals: The issue of payment of compensation to Afghan National is long
standing since the start of compensation process which is still unresolved. In this
regard, formerly, a consultation meeting had held with DG Afghan Refugees on Feb
12th, 2018. DG-AR had informed PIU that Afghan Commissionerate does not make
direct payments to Afghan refugees and hence no procedure shared for such
instances. PDA cannot provide open cheques to DPs as it is not acceptable to PDAs’ Audit unit. The issue was brought in to the notice of new DG-PDA on 26th April and
48
further on 3rd May, 2021, discussed different options for payment to unpaid Afghan
DPs. The new DG-PDA will now decide the best convenient way/ channel to release
the stuck payment to the Afghan DPs.
iv. The discussed options are; i) the amount may transfer to contractor account of the
respective Reach and then the contractor under the supervision of STRPI and PMCSC
resettlement staff further hand over the unpaid amount to the 5 Afghan DPs or ii) the
amount may transfer to project management & construction supervision consultants
i.e. PMCSC/ MMP account and then formally hand over to the Afghan DPs, if
acceptable to finance/ audit team of PDA or iii) the amount of compensation of Afghan
DPs may transfer to the accounts of those shopkeepers with whom the Afghan
Refugees had worked as assistants or iv) or through Shu’ra members of Underpasses;
as the Shu’ra as association of underpasses falling in Reach-1 is an organized body,
if the amount may transfer to Shu’ra members account and then formally hand over to
Afghan DPs in the presence of PMCSC, STRPI and finance team of PDA as witness.
The mentioned suggestions brought into the notice of DG-PDA and discussed for her
approval of a convenient mode of payment. As soon as DG will decide about
convenient option, will further communicate with ADB social safeguard team.
v. Underage DPs or DPs lacking CNICs/ Bank accounts: Payment of compensation
to 23 below 18 years DPs is yet to be paid which also delayed completion of LARP
implementation. In this regard, efforts have been made by the representative of those
DPs and some underage DPs have already submitted their guardian certificates and
hence received their compensation accordingly. 7 DPs are confirmed that they had
already submitted application to the court of law for preparation of guardian certificates
(the representative lawyer Mr. Musavir has provided the application letters which are
provided in Annex 12. According to the remaining underage DPs particularly of both
the underpasses that their case is also under-process (but could not provide their
application letter to the court of law) and as soon as it will completed they will provide
the guardian certificates to STRPI at PDA-PIU.
vi. Correction issue in DPs names or CNICs numbers: As per the demand of Audit unit
of PDA, the issue of payment of compensation to seven (7) DPs which needs
correction and duly approval from ADB has now resolved. The corrections has been
made and approved in the previously submitted IMR from July to December, 2020.
Therefore, the payment to those DPs is scheduled to be processed soon. The list of
corrected cases in names & CNICs (approved from ADB) is provided as Annex 7.
vii. Closure of compensation due to COVID-19: Similar to the first wave of Covid-19,
The prevalent third wave of pandemic i.e. COVID-19 generally across the world and
particularly in Pakistan and in KP province is also caused restrictions on transportation
and human mobility which is creating fear that it may not become a source of
unavoidably delayed to the payment of remaining payments to project DPs. During the
first pandemic wave from March – July, 2020, all the government & non-government
offices including PDA-PIU and PMCSC were remained closed for 3 to 4 months.
Likewise, in the prevalent second wave, the offices both public and private sections
office timings are reduced to minimum hours. Even the number of staff is also reduced
to 50 percent presence of staff.
viii. Refusal of underpass DPs until resolution of their complaint: As per the STRPI
team, 16 cheques for payment is ready however, 12 DPs also complainants of
Hashtnagri underpass refused to collect their cheques until the resolution of their
complaint regarding redundant shops for the last 12 months in the Hashtnagri
49
Underpass. For resolution of the complaint, the GRC meetings are underway, the
complainants are in close contact with PIU, STRPI, PMCSC and ADB team and
deliberating mutual for earliest amicable resolution of complaint.
50
Table 14. Action Plan for Payment of Compensation to Remaining DPs
S/NO Categories of Unpaid DPs
Issues Efforts by PDA to pro Timelines Revised Dates & Actions
1 2 3 4 5 6 1 5 Afghan national
DPs (AN DPs) Payments cannot be processed by PDA finance section without CNIC which is a procedural requirement Lack of Pakistani CNIC being Afghan national
The new PD has taken up this matter with the finance team of PDA and discussed the following options on 26th April 2021 and May 3rd : vi) the amount may
transfer to contractor account of the respective Reach and then the contractor under the supervision of STRPI and PMCSC resettlement staff further hand over the unpaid amount to the 5 Afghan DPs or
vii) the amount may transfer to project management & construction supervision consultants i.e. PMCSC/ MMP account and then formally hand over to the Afghan DPs, if acceptable to finance/ audit team of PDA or
viii) the amount of compensation of
Decision of PDA finance department end of May 2021 Preparation of cheques 1 and 2nd week of June Disbursement of cheques and Payments of compensation by 30th June, 2021
Decision of PDA finance department end of September 2021 Preparation of cheques 1st week of October Disbursement of cheques and Payments of compensation by 15th October 2021
51
Afghan DPs may transfer to the accounts of those shopkeepers with whom the Afghan Refugees had worked as assistants or
ix) through Shu’ra members of Underpasses; as the Shu’ra as association of underpasses falling in Reach-1 is an organized body, if the amount may transfer to Shu’ra members account and then formally hand over to Afghan DPs in the presence of PMCSC, STRPI and finance team of PDA as witness.
x) as soon as DG-PDA will decide about the convenient option for payment to unpaid Afghan DPs will be communicated to ADB accordingly. As discussed above, PDA is committed to pay all the unpaid DPs by June 30th, 2021.
52
2 23 underage DPs Underage DPs also lack CNIC until they reach age of 18 years hence they require guardian certificate from court to receive cheques and get paid 8 of these DPs have submitted the request for guardian certificate to the court through their lawyer in October 2020. Courts usually takes 3 to 4 months to provide guardian certificates. The lawyer presume that their certificates are ready at court and will update PDA about their status in 2 weeks based on which PDA will prepare cheques The remaining 15 DPs have also submitted their request for guardian certificate in court but couldn’t provide evidence of application to the PDA team when inquired
As the guardian certificates are issued by the court which usually takes 3 to 4 months, this process is further slowed down due to Covid 19 restrictions and the month of Ramadan These kind of payments are expected to be delayed by 4 to 5 months. Hence the guidance statement form attched as annexure 14 is a procedure to facilitate resolution of stuck payments and enables closing such cases based on the good faith efforts EAs are required to make. In this case, an escrow account is needed to open to deposit the amount of compensation, which will be disbursed at the time when guardian certificates are available. PDA will confirm if the compensation money is kept in a project account dedicated for this purpose in 2 weeks.
PDA resettlement team will follow-up with the Lawyer who will provided update on the guardian certificates of 8 DPs. PDA resettlement team will contact 15 DPs for evidence of their application submitted to the court PDA resettlement team will get the guardian statement filled by these underage DPs by June 30th 2021 PDA will conduct meeting after eid vacations within department to discuss if compensation money of these DPs can be kept in project account
Follow up is underway, according to the lawyers two DPs guardian certificates will be prepared in September, 2021, hence cheques will be prepared and payment will be made to these two DPs by end of September, 2021. He further conveyed that 10 DPs will become major/ grown up in end of August, 2021, expected they provide CNICs by 20th September, 2021 and payment will be made either by end of September or 1st week of October, 2021.
53
3 7 DPs mismatch names and CNIC no
These 7 DPs have their names mismatched with their CNIC numbers as per PDA records Correction is made by PDA’s audit team which is then approved by ADB in 5th IMR report
PDA finance team has distributed the cheques to these 7 DPs in the presence of PMCSC and STRPI team as witnesses. The pictures and process of cheques distribution will be included in 7th IMR report.
Evidence of payments will be provided in next IMR
Evidence of payments will be provided in next IMR by Oct/ Nov, 2021.
4 8 DPs/complainants of Hashtnagri underpass refused payments until resolution of complaints
These DPs are among complainants of BS07 who refused to receive cheques until the complaint is resolved. They have complaint that their shops remain redundant due to inaccessible stairs and demand revision in design and provide decent access to their shops through properly engineering designed stairways through rearrangements of underpass
PDA has issued notices to the DPs of both the underpasses for collection of their unpaid payments and informed the DPs about the development in resolution of BS-07 complaint and requested the DPs to receive their payments cheques from PDA office before they get expired.
As these 8 DPs has refused to collect their cheques until resolution of rearrangements of underpass BS07 complaint. The payment to these DPs still depends upon timely completion of civil works on underpass rearrangements and hence subsequently collection of payments by the unpaid DPs.
As the agreement has been now made with the complainant’s. Access to the redundant shops to be provided one the descoping process is completed and contractors are on board then physical rearrangement work will be started expectedly in July/ August, 2021. The construction will be completed expectedly in Oct/ Nov, 2021.
5 11 DPs of Firdous underpass
These DPs are complainants of BS08, their complaint is about the use of feeder bus tunnel as an alternate passageway to reach
PDA with the help of ADB consultants has reviewed this complaint and have recommended to place appropriate signage at different locations to guide
These DPs will be paid of 25th June, 2021
These DPs will be paid of by end of September, or 1st of October, 2021
54
the bus station which has safety concern.
people. The complainants have withdrawn their complaint and agreed to receive cheques. However during the resolution of complaints the initial cheques got expired and PDA finance department is renewing the cheques and provide cheques to DPs by the end of June 2021
6 Other DPs 1 DP has remaining payments of crops and trees couldn’t receive payments due to her busy schedule being a politician
PDA resettlement team has reach out to this DP and she has authorized her relative by giving “power of attorney” to receive her remaining payments of crops and trees. PDA has prepared this cheque already and will be disbursed as soon the DPs relative will reach them. PDA resettlement staff will remind this DP to receive cheque in 1 week
This DPs will be paid by 25th May 2021
This DPs will be paid by second half of September, 2021
54
N. Good-faith/ Exhausted Efforts Conducted by PDA for Processing of
Stuck Payments
89. The PDA-PIU assisted by STRPI and PMCSC team is making efforts for early payment
to the remaining DPs particularly those DPs whose cheques are ready for compensation.
While the unpaid DPs are being pursued and mobilized for showing-up and collect
compensation after overcoming their issues. Additionally, to facilitate payment of
compensation to DPs with legal and administrative impediments, the PDA/ PMCSC continued
to approach unpaid DPs to mobilize them for submission of their guardian certificates after
they received from court. During reporting period all the underage unpaid DPs were
approached via focal persons/ shu’ra members of underpass and through their available
relatives and even on their contact numbers. Samples of good-faith efforts or efforts exhausted
(included recently issued notices to the underpass DPs) are provided in Annex 12. PDA has
also issued notices to the DPs of both the underpasses for collection of their unpaid payments.
Through these notices also informed the DPs about the development in resolution of BS-07
complaint, already ready prepared cheques for collection and also emphasized for speed up
the preparation of guardian certificates of underage DPs so that they could also collection their
unpaid payments. There are few limitations which cannot be avoided, firstly, the prevalent
escalating Covid-19 situation in KP particularly in Peshawar which restricted 50 percent staff
in all public & private offices and also the office timings are reduced to 9 am to 2 pm including
1 hour prayers’ break which also reduced the volume of work in offices. Secondly, the fasting month of Ramadan in which mostly the people are usually have different sleep timings which
may also affect the payment process to DPs. Following are some of the efforts PDA has made
so as to complete the compensation process as soon as possible.
• Informed individually each under-age affected person to expedite the process of
making of their guardian certificates and provide the required documents for receiving
of their pending compensation payment as early as possible. In this regard, to expedite
the process further, the PMCSC resettlement staff contacted with focal person Mr.
Musavir Khan of Sardar Garhi Filling Station DPs who is a lawyer by profession to
further look into the process of making of guardian certificate in the concerned court
on behalf of these 6 DPs. Mr. Musavir Khan has agreed that he will voluntarily pursue
their case and hopefully will get in the couple of week time.
• Informed shu’ra member via email & also issued notices regarding pending
compensation payment cheque which already expired due to no response from DPs.
The cheques were prepared however did not collect by concerned DPs during 6
months. Those cheques become staled then the PDA resettlement team made efforts
and prepared new cheques. However, still no response from DPs. Additionally, during
the reporting period these DPs have been informed through their shu’ra members of both the underpasses, contacted them via their given cellphones, and even most of
them met personally in the underpasses to collect their remaining compensation. In
response Shu’ra members of the underpasses informed the PDA through email that they will not collect compensation cheques until the resolution of complaint regarding
BS-07 Hashtnagri Underpass. List of meetings with unpaid DPs, their representatives
and underpass Shu’ra members is provided as Table 15 and sample of list of
participants of one meeting (as evidence) is provided in Annex 12.
Table 15. List of Consultation Meetings with Unpaid DPs & Complainants of BS-07
55
S.# Date Location Category of Participant
No. of Participants
Name of participants
Remarks
1 3 Nov, 2020
Hashtnagri Underpass
DPs & Shu’ra members
8 - Afsar Ali Khan - Sohail Noor - Atta ur
Rehman - Umair - Sohaid Rahat - Wajid Ali
Nadeem - Zubair - Muhammad
Basit
DPs & Shu’ra members approached & motivated for pending payments and assurance regarding amicable resolution of BS07 complaint
2 5 Nov, 2020
Firdous Underpass
DPs & Shu’ra members
11 - Salah-Ud-Din - Wajid Ali
Nadeem - Zahir Shah - Sultan
Muhammad - Shah Zameen - Naimatullah - Abdur
Rehman - Ajmal - Imran - Umer - Ibrahim
Few of DPs participated while the remaining DPs were approached through the available Shu’ra members to collect their pending payments
3 9 Nov, 2020
Sardar Garhi Filling Station
DPs & Focal Person
7 - Muhammad - Zabeehullah - Hazrat - Muhammad
Hayat Khan - Sohail Khan - Qader Khan - Musavir Khan
DPs and focal person (Mr. Musavir) approached, Musaivr informed that they are waiting for collection of guardian certificates (GC) from court. Requested for further expediting the preparation of GC soon.
4 23 Oct, 2020
Office of GRC Chair & Director Estate Management in PDA (1st GRC meeting)
Complainants & Complainants’ representative
4 - Mirza Khan - Wajid Ali - Malik Ashfaq - Naveed Khan
- Acknowledged the complaint by inviting the complainants to the first GRC meeting at PDA.
- Conducted face to face meeting and discussed the grievance/ complaint with the complainants in order to know their
56
concerns at GRC level.
- Documented the possible solution option(s) suggested by the complainants in the GRC meeting.
5 18 Nov, 2020
Office of Director General – PDA (2nd GRC meeting)
Complainants & Complainants’ representative
2 - Mirza Khan - Naveed Khan
- Formally presented the resolution option prepared by the PMCSC and PDA to the Complainants,
- Sought Complainantss agreement on the option prepared for implementation and way forward
6 6 Jan, 2021
Office of Director Coordination – PDA (3rd GRC meeting)
Complainants & Complainants’ representative
2 - Mirza Khan - Naveed Khan
- Shared updates particularly about efforts made in resolution of BS-07 issue with the complainant’s representative.
- Shared prepared construction drawings for implementation and get consent of complainant’s representative and way forward.
• Inform every unpaid DP through letter to submit their documents as soon as possible
for processing of their pending compensation amount.
• Posting and providing notices in public places. (in process) please in Annex: 12, and
the updates will be incorporated in next IMR.
• Publishing the names of unpaid DPs in the print media. (in process) please in Annex: 12, and the updates will be incorporated in next IMR.
57
O. Action plan for Livelihood Restoration of DPs
90. Disbursement of payments to DPs for their assets have almost completed, listing of
eligible candidates with complete Bio data from project DPs have completed, contractor, PDA,
Trans Peshawar have communicated by LARP team to work for hiring of project DPs/locals in
their respective Offices as well as on construction sites, Contractor have recruited local project
DPs at contractor camp as well as on construction sites. According to record there are 27 local
and 12 DPs are working at contractor camps. Capacity building for skill development and other
measures for income and livelihood restoration are in process. Table.16 shows potential
eligible project affectees, who were surveyed and documented by PMCSC.
Table 16. List of Potential Eligible Project Affected Persons
Sr. No
Name Father’s
Name CNIC No.
Academic Qualification
Experience /Skills
Professional Certification/ Documents
*Status of affectees
1 Muhammad Imran Haleem Jan 17301-2858156-9 F.A Nil
Direct Indirect
2 Muhammad Kamran Haleem Jan 17301-0723895-3 Matric Nil
✓
3 Jan Hussain Haleem Jan 17301-4642007-9 Matric Nil
4 Junaid ur Rehman Azam 17301-5207557-3 Matric Nil
5 Mansoor Khan Fayaz Ahmad 17301-3040836-7 B.A Nil
6 Musawar Khan Fayaz Ahmad 17301-6147606-5 L.L.B Nil
7 Muzamil Khan Fayaz Ahmad 17301-1380881-3 M.A Nil
8 Rashid Khan Ijaz Ahmad 17301-1632390-1 Matric Driving
25 Years
9 Naveed Ahmad Ijaz Ahmad 17301-1646418-9 M.A Teaching 13 Years
10 Muhammad Zubair
Mehfoz Rehman 17301-6200906-9 8ThClass Driving
11 Mehfoz Khan Khadim Hussain 17301-9194184-1 Nil
12 Ibrar Hussain Khadim Hussain 17301-5826205-1 Matric Nil
13 Hazrat Ali Liaqat Ali 17301-6562119-1 B.A Nil
14 Zahid Ullah Khan
Nasrullah khan 17301-1394021-3 M.B.A
2 years USAID
15 Wahid Khan Gulistan Khan 17301-6959918-3 Middle
Driver + Mechanic
58
Sr. No
Name Father’s
Name CNIC No.
Academic Qualification
Experience /Skills
Professional Certification/ Documents
*Status of affectees
16 Fahim Khan Mohammad Ashraf 17301-1133293-1 Matric Nil
17 Umer Farooq Muhammad Idrees 17301-5620984-3 Matric Farming
18 Muhammad Sohail
Muhammad Salim 17301-8381134-5 Middle Nil
19 Muhammad Tanveer
Faqir Muhammad 17301-9267424-7 M.A Nil
20 Muhammad Adeel
Faqir Muhammad 17301-8121953-9 B.A Nil
21 Abbas Ahmad Shabbir Ahmad 17301-0486969-7 D.A.E Nil
22 Muhammad Ilyas
Saif Ur Rehman 17301-7347788-3 Middle Nil
23 Muhammad Iqbal
Muhammad Yaqoob 17301-1602201-9 Matric Nil
24 Muhammad Faheem
Muhammad Saddique 17301-4202715-1 F.A 3 Years
25 Iftekhar Ullah Hafiz ullah 17301-1265313-7 F.A Driver
26 Salahuddin Mahiduddin 17301-2129444-1 F.A Nil
27 Shahab Ullah Iftekhar Ullah - Matric Nil
28 Salman Gul Rahman 17301-0894406-5 Middle Nil
29 Muhammad Niaz Fayaz 17301-8769346-1 Matric Nil
30 Muhammad Tanveer
Faqir Muhammad 17301-9267424-7 B.A Nil
31 Muhammad Kashif
Muhammad Ashraf 17301-5443794-5 M.COM Nil
32 Muhammad Naveed
Faqir Muhammad 17301-8622554-3 Matric Nil
33 Muhammad Adeel
Faqir Muhammad 17301-8121953-9 F.A Nil
34 Muhammad Hilal
Bashir Ahmad 17301-4478986-3 Hafiz-e-Quran Nil
35 Adnan Khan Muhammad Ikhraj 17301-9065450-7
B.A Hafiz-e-Quran Nil
36 Muhammad Zohaib Samin Jan 17301-6490471-5 F.S.C Nil
59
Sr. No
Name Father’s
Name CNIC No.
Academic Qualification
Experience /Skills
Professional Certification/ Documents
*Status of affectees
37 Muhammad Ilyas Samin Jan 17301-9520888-3 F.S.C Nil
38 Hasnain Suhail Suhail Rana 17301-2000225-7 F.S.C Nil
39 Saqlain Sohail Sohail Rana 17301-9889767-7 Middle Nil
40 Umar Farooq Muhammad Idrees 17301-5120984-3 Middle Nil
41 Muhammad Imran
Saeed ur Rehman 17301-0714896-9 Middle Nil
42 Farooq Khan Ihsan Ullah 17301-4089654-5 Middle Nil
43 Abdul Salam Ikram Uddin 17301-1392746-3 Middle Nil
44 Muhammad Jalal Iqbal 17301-9197243-1 Middle Nil
45 Jawad Khan Muhammad Shafiq 17301-4713911-9 Middle Nil
46 Ahmad Nadeem Abdul Hamid 17301-85105581 Middle Nil
47 Taimoor khan Haji Haleem 17301-7627024-3 BA 2 years USAID
48 zarshad khan lal
Muhammad 17301-478758-7 Middle Nil -
49 Adnankhan Hanif 17301-5096388-9 Middle Nil -
50 Jan
Muhammad Islam khan 17301-1710312-1 Matric Nil -
51 Muhammad
Arbaz lal
Muhammad 17301-6557768-9 FA Nil -
52 Anwar shaid Jamshaid
khan 17301-5070805-1 Matric Nil -
53 Inamullah jan Janath Gul 17301-6890502-7 FSc 1year -
54 Adnan Ahmad
khan Hanif 17301-3096388-9 - - -
55 Jan
Muhammad Ismail khan 17301-1719312-1 FSc - -
56 Muhammad
Arbaz Lal
Muhammad 17301-6557768-9 FSc Nil -
57 Anwar Said Jamshaid
khan 17301-5020305-1 Matric Nil -
60
Sr. No
Name Father’s
Name CNIC No.
Academic Qualification
Experience /Skills
Professional Certification/ Documents
*Status of affectees
58 Zarshad khan Lal
Muhammad 17301-4787587-1 Matric Nil -
59 Jawad khan Muhammad
Shafiq 17301-4713911-9 Matric Nil -
60 Abdus salam Ikram ud din 17301-4392746-3 Matric Nil -
61 Muhammad
Imran Saeed ur Rehman 17301-0714896-9 Dini ilm Dini ilm
62 Umer Farooq Muhammad
idrees 17301-25120984-1 Matric Nil -
Source: PMCSC-DPs survey conducted for eligible candidate for job among project affectees
V. Consultation, Participation and Information Disclosure
A. Stakeholder Consultation and Participation
91. Consultation meetings, group discussions and in-depth interviews were conducted
with DPs in each reach (including representatives of poor households, households which are
required to resettle and households losing their business or agricultural land) and provided
timely, relevant, understandable, and accessible information, in a culturally appropriate
manner, free of coercion and intimidation. Stakeholder engagement logs, and meeting minutes
were prepared and were made available to DPs and other relevant stakeholders when
required.
92. During the preparation of Addendum 1 to Reach 1 LARP, PMCSC resettlement team
carried out meetings with APs and stakeholders in the month of February, 2018. The APs
were consulted regarding the impacts of design changes in the access ramp at Chamkani Mor
and the valuation mechanism and calculation of compensation amount to ensure that APs are
well informed and cognizant of the LAR processes and were provided with an opportunity to
express their views. The APs are informed of the proposed valuation methodology and
compensation amount and has expressed their agreement.
93. Similarly, during the preparation of Addendum 2 to Reach 1 LARP, PMCSC
resettlement team conducted meetings with APs and stakeholders regarding the status of
finishing of payments after 12 months in light of the approved LARP of Reach-1. The lessee,
sub-lessees, shopkeepers and technical representatives were consulted regarding
continuation of payments even after approved 12 months period to the APs of both Firdous &
Hashtnagri Underpasses. The APs were informed about the previous calculation of already
agreed compensation amount and further continuation to ensure that APs are well informed
and acquainted of the RP processes and were provided with an opportunity to express their
views. The APs are informed of the proposed valuation methodology and compensation
amount and has expressed their agreement.
94. Regular public consultations and meetings have made with the affected households to
make them fully understand about the compensation and related procedures of the LAR.
Majority AHs were satisfied with the LA process, fair appraisal of the property, timely payment
61
and LAR policy arrangement. Consultation meeting with group of DPs continued on weekly
basis especially in Sardar Ghari with DPs of Zia Market and Firdous and Hashtnagri
underpasses affected significantly.
95. A number of preliminary field/ site visits, meetings, discussions with officials of PIU,
STRPI, contractors, consultants as well other key stakeholders were carried out to coordinate,
clarify and implement project design and LARP/RP implementation issues.
96. Meetings were held with Deputy Commissioner (DC), Additional Deputy Commissioner
(ADC), Tehsildar to expedite the land acquisition process and issuing of the required sections
under the Land Acquisition Act, 1894. The team made several visits along with Patwari to
demarcate the acquired land in Sardar Ghari and conducted assessment of affected trees and
crops to commence compensation payment to DPs for affected land and structure. Detailed
findings of consultations with DPs during the reporting period are provided as Annex 7.
B. Information Disclosure
97. The ADB-approved safeguards documents have been disclosed on PDA website in
line with ADB’s SPS 2009 requirements. In view of difficulty for DPs to comprehend LARP in
English, the LARP Reach 1 was translated in Urdu and disseminated to DPs of Firdous and
Hashtnagri and Zia Market DPs. Executive summary and entitlement matrix of RPs of Reach
2 and 3 were also translated in Urdu and distributed among DPs.
C. Status of Grievances Launched and Resolved
C 1. Grievance Redress Mechanism
98. With a view to likeliness of grievances during LARP/RP implementation, provision of
constituting a Grievance Redress Committee (GRC) has been made and notified to minimize
expected protracted and expensive litigation. The GRC is being coordinated by Social
Development and Resettlement Specialist as the Secretary of the committee.
99. The main responsibilities of the GRC at both PIU and DC level is (i) provide support to
affected people on problems arising from land/property acquisition; (ii) record DP grievances,
and resolve them. The GRC is expected to resolve grievance of the eligible persons within a
stipulated timeframe.
100. The three-tier grievance redress mechanism (GRM) was established to ensure
systematic disclosure of information, hearing and recording of complaints, proper arrangement
for addressing conflicts and appeal procedures regarding eligibility and entitlements as well
as the implementation of resettlement activities. Through an outreach program, DPs were
informed on how the mechanism will work and ensured it is accessibility to vulnerable and
women DPs. The GRM was translated in Urdu and distributed among DPs.
D. Grievance Status
101. Total 49 complaints from all the reaches received to PIU, including 45 in Reach-1, 01
in Reach-2 and 03 in Reach-3, out of Reaches complaints are 02 which were rejected by the
LARP team, all other complaints have been resolved by LARP team except the two court case
which are pending from the court, and an under process complaint of BS-07 underpass, these
have summarized in Table 17. A close follow-up was carried out with the complainants to
address their complaints. In this regard, precautionary measures were adopted through
conducting various formal and informal meetings with the aggrieved persons to manage their
grievances. In such meetings the BRT alignment design, PDA owned ROW limits, LAR impact
62
assessment including eligibility, entitlement provisions under project resettlement plan were
explained. The Grievance Log is provided as Annex 9.
Table 17: Grievance Status Report
Reach Grievance
Received
Grievance
Rejected
Grievance
Resolved
Grievance
Un-resolved Court Cases
Reach 1 45 1 41 1 02
Reach 2 1 0 1 0 0
Reach 3 3 1 2 0 0
Total 49 2 43 1 2
102. Some of the grievances involved missing names of DPs in the impact assessment and
misunderstanding regarding the unit rates and eligibility criteria of DPs to be entitled for
compensation were resolved timely. However, the grievances of critical nature to be resolved
are in process are provided in the Table16. PIU is involved in the preparation of the documents
related to grievances, follow up action taken to resolve along with explanatory note on nature,
seriousness of grievance to be redressed. Two complex nature of grievances were
investigated, mediated and concluded and undertakings of DPs are provided as Annex 10.
E. Complaints with Current Status of Resolution - the success and
progress of the project in resolving the BS-07 complaint
103. The DPs of Hashtnagri Underpass at BS-07 has reported a complaint that 22 closed
of their shops are still have not been rented-out for the last one year, owing to inappropriate
arrangement of stairs and ramps particularly at the north side which subsequently financial
losses facing by the shop owners/ sub-leaseholders of the these shops. In this connection, an
efforts have been made for amicable resolution of this grievance. PDA has revitalized the
grievance redress committee (GRC) at PDA and included few active members in the GRC
committee. In this regard, following the procedure, a three-tires (first on 23rd October, 2020,
second on 18th November, 2020 and third on 6th January, 2021) of GRC meetings held with
the complainants’ representative. Initially, the GRC committee had recorded their given
options for further discussion with technical team of PDA & Consultant to seeking viable
solution. The Consultant team provided the best possible option in line with complainants’ given option and for this in order to formally share the drawing with complainant’s representative another meeting held with the representative of complainants with DG-PDA. In
this meeting, a proposed option/ drawing was shared with complainants. Both the parties
agreed on the proposed drawing for resolution of the issue amicably however, as the DG-PDA
had previously directed the Estate Management regarding the pre & post assessment of area
and shop-units, the complainants’ representative had then provided the supportive documents
as evidence for the number of shop units and covered area of pre & post BRT of the
underpass. In this context, in order to further facilitate the pre & post assessment process, an
ADB consultant has also conducted the assessment and provided his findings on the basis of
the documents provided by Estate Management Department & the documents provided by
the main-leaseholder via Estate Management to the ADB consultant. In those findings, the
ADB consultant also provided his recommendations particularly regarding issue of five shops
which rent has not been submitted to the PDA due to family dispute of main-leaseholder since
its construction. Similarly, the Estate Management Department on April 23rd, 2021 after
verification of the documented evidences provided its conclusive statement to DG-PDA by
endorsing that the five shops were existed pre-BRT however, its rent to the Estate
63
Management Department at PDA has not been deposited due to its family dispute. In this
connection, the Estate Management Department had directed the complainants for
submission of rent amount against five shops since its construction so that to formally
regularize those shops in PDA’s record. In response, the complainants as directed deposited
the amount to PDA and the shops hence regularized at PDA’s record. With this development,
the key impediment in resolution of complaint has resolved. After successful agreement on
the proposed design of both the parties and also agreement on existing of 44 shop structures
in the underpass at pre-BRT stage by the PDA, the next step was the rearrangement of
underpass. However, on the other hand, as the de-scoping for contractor-ship for project
remaining civil works was underway which also delayed the civil works on underpass re-
arrangement. Upon finalization of de-scoping process, the contractors mobilized at site. PDA
on priority basis through Reach-1 contractor started the civil works on underpass
rearrangement at BS-07 on July 9th, 2021 so that to resolve the complaint as soon as possible.
Similarly, upon start of construction work at site, the complainants showed overwhelming joy
and were quite satisfied however, the complainant’s requested that they will formally withdraw their complaint as soon as the civil work on the underpass completed. They also requested to
the PDA that the construction work should complete in three month time so that the shop
owners could restore their livelihood at earliest.
104. It was observed that the resolution of underpass issue/ complaint took much time in its
resolution which was indeed due to multiple reasons such as firstly the transfer of ex-DG PDA
which created a kind of vacuum for two three months in processing procedural documents/
matters. Secondly, it also took ample time for the understanding of new DG-PDA to make
further progress on the complaint. Likewise, retirement of ex-PD-PIU also created a void of
couple of months. However, the new DG and new PD-PIU in coordination with ADB social
safeguard team made sincere efforts on priority basis successfully resolved the complaint up
to the satisfaction and agreement of complainants. Currently, as part of process of complaint
resolution, the civil works on underpass rearrangement is actively underway. The PDA,
Consultant and the concerned contractor is committed to complete the work within the
stipulated time of three months.
105. In view of delay in resolution of first complaint, the DPs of redundant shops of
Hashtnagri underpass in frustration had lodged another complaint at GRC with STRPI team
on June 7th, 2021 as well as to the ADB’s complaint cell claiming for additional payments.
According to the complaint, that due to delay in resolution of their first complaint their livelihood
are still stopped. In response, the PD-PIU and resettlement team of the PMCSC as per
procedure swiftly conducted two GRC meetings with the complainants and complainant’s representatives. The meetings were quite positive. The PD-PIU explained to the complainants
that as the de-scoping process for sub-contractor ship for the remaining work of the project is
almost finalized and the sub-contractor of Reach-1 is also fortunately onboard so as the civil
works will about to get start in couple days. Upon immediate practical assurance to the
complainants, they agreed that they will not claim any further compensation if the construction
work is completed within the given time of three months. They further agreed that once the
construction work on the underpass rearrangement is fully completed and their complaint is
resolved they will formally withdraw both of their complaints from ADB complaint cell
accordingly.
64
Table 18: Log of Grievances Received
Sr. No.
Description of complaint Date of
complaint Name of
Complainant Location of complaint
Gender Action proposed/taken
status Remarks M F
1 Deficiencies in no of Shops 47 shops in Firdous, 38 shops in Hashtnagri
20/11/17 Mirza Khan Reach 1
✓
Explain annexure difference
Resolved
2 Objection on BS-08 location 20/11/17 M.Naeem Khan Reach 1
✓
Design not finalized Resolved
3 Shop employee name wrote as shop owner actual owner name missing
27/11/17 Rukhsana Bibi
Reach 1 ✓
Name change on basis of evidence
Resolved
4 Shop employee name wrote as shop owner actual owner name missing
27/11/17 Amna Karim Reach 1
✓
Name change on basis of evidence
Resolved
5 Shop employee name wrote as shop owner actual owner name missing
27/11/17 Riaz Gul
Reach 1 ✓
Name change on basis of evidence
Resolved
6 Illegally demolish shops in the canopy
27/11/17 Qari Hidayat Rehman
Reach 1 ✓
Decision hold till than finalization of design BS-08
Resolved Considered and
accommodated
in final design of
BS-08
7 Illegally demolish shops in the canopy
27/11/17 Ashfaq Ahmed
Reach 1
✓
Decision hold till than finalization of design BS-08
Resolved Considered and
accommodated
in final design of
BS-08
8 Illegally demolish shops in the canopy
27/11/17 Rukhsana Bibi
Reach 1 ✓
Decision hold till than finalization of design BS-08
Resolved Considered and accommodated in final design of BS-08
9 Illegally demolish shops in the canopy
27/11/17 Ayub Shah
Reach 1
✓
PDA Resolved Considered and
accommodated
in final design of
BS-08
10 Assurance for protection for rights of entitlements
06/12/17 Five complainant
Reach 1
✓
Decision hold till than finalization of design BS-08
Resolved Considered and
accommodated
in final design of
BS-08
65
Sr. No.
Description of complaint Date of
complaint Name of
Complainant Location of complaint
Gender Action proposed/taken
status Remarks M F
11 Illegally construction start before compensation
06/12/17 Liaqat Ali Reach 1
✓ Stop worked by Deputy Director
Resolved
12 Complaints 02 shops business loss
06/12/17 Shakeel Ahmad
Reach 1
✓
One business in 02 shops explained him business loss is one because business is one rent loss for 02 will provided to owner
Resolved
13 Complaints for compensation
16/11/17 1.Nadir Khan 2.Mahar Ali 3.Rehman Gul 4.Nazir Gul 5.Javeed Khan 6.Shafi Ullah 7.Faqeer Gul 8.Said Khan
Reach 1
✓
They are not present during cutoff date
Resolved
14 Complaints requested to review structure compensation
08/12/17 Zahid Ullah Khan
Reach 1
✓
PDA not ready to acquired full structure but according to ADB policy now agreed to acquired full structure.
Resolved Full structure acquired
15 PDA give notice for demolishing of wash room
26/12/18 Muhmmad Furqan
Reach 2
✓
Wash room constructed after cutoff date although conducted meeting with cantonment board and deputy director building for avoiding demolishing
Resolved
16 Compensation claim as vendors
21/12/17 Noor Zada
Reach 1 ✓
Vendor compensation claim but not present during cutoff date
Resolved
17 Demand for Bus 01 Name Sardar Gharhi instead of Chamakani
26/12/17 Rashid Khan
Reach 1 ✓
Change name of area is domain of District Administration
Rejected
18 Review compensation plan 04/01/18 Muhammad Qasim
Reach 1 ✓
Explained compensation claimed criteria and satisfied complaints
Resolved
66
Sr. No.
Description of complaint Date of
complaint Name of
Complainant Location of complaint
Gender Action proposed/taken
status Remarks M F
19 Fly over in front of complaints house
16/01/18 Syed Qasim Shah
Reach 1
✓
A detailed investigation conducted and designed not clear yet although pilling work completed
Resolved
20 Compliant for demolished shops compensation till reestablished
23/01/18 a1. Malak Ashfaq 2.Zahir Shah 3.Ayub Shah 4.Qari Hadyat Ullah 5.Khurram Masih 6.Wajid Ali Nadeem 7.Mushtaq Masih 8.Amna Karim
✓
Resolved
21 Commercial land was rated as agriculture land
23/01/18 Zahid Ullah
Reach 1 ✓
A detailed investigation held and error occurred from Revenue side
Under Process
Court Case
22 BRT acquired 93 Marla but incorrectly in LARP 63 Marla compensation exist in revenue record and 30 Marla compensation not in record
31/01/18
Naveed Ahmed
Reach 1
✓
Revenue official held investigation and awaited their report
Under Process
Court Case
23 Aman Ullah Khan was shopkeeper of shop no 07 Hashtnagri Underpass at time of survey and left shop in September 2017, Rehman Gul claimed for decoration cost.
20/02/18 Rehman Gul
Reach 1
✓
Shora member concern is different from complaints asked both parties need to resolved conflict and arrange joint meeting then received their income according to shora decision.
Resolved
67
Sr. No.
Description of complaint Date of
complaint Name of
Complainant Location of complaint
Gender Action proposed/taken
status Remarks M F
24 Compliant claimed decoration cost on the name of Yasir Khan shop no 14 Hashtnagri Underpass not provide to Sheer Ullah because contract ended.
20/02/18 Yasir Khan
Reach 1 ✓
Shora member concern is different from complaints asked both parties need to resolved conflict and arrange joint meeting then received their income according to shora decision.
Resolved
25 Compliant against the illegal threat extended by PDA on the pretext that the shop No Ms-01 at KTH underpass medicine market university road Peshawar.
22/03/18
Irfan Ullah
Reach 3
✓
Confirmed from PMCSC Designed team KTH underpass will not impact during BRT construction. Complainants assured that he will not affected from BRT so he was satisfied.
Resolved
26 Compliant claimed that his name is missing from crop compensation affected person list.
22/02/18 Muhammad ilyas
Reach 1 ✓
PMCSC will investigate actual situation.
Resolved
27 PDA tool plaza ring road Peshawar managing director claimed that due to BRT construction traffic divert on different roads and he bear daily Rs 300000 income loss.
07/03/18 Muhammad Ashraf
Reach 3
✓
STRPI raised their issue and PDA asked they will discussed with higher authority.
Rejected Out of BRT
28 Additional 5 Marla land demand for BRT; Complainant wants it to be identified as Commercial land
21/03/18 Zahidullah
Reach 1 ✓
PMCSC will investigate actual situation
29 Loss of income due to blockage of access vehicles
23/04/18 Fazal Rabi Reach 1 ✓
PMCSC will investigate actual situation
Resolved
30 Blockage of road to Service Station
29/09/18 Muhammad Saleem Reach 1 ✓
PMCSC will investigate actual situation
Rejected
68
Sr. No.
Description of complaint Date of
complaint Name of
Complainant Location of complaint
Gender Action proposed/taken
status Remarks M F
31 Garbage and waste material in front of Khyber bank
11/10/18 Hina Jehangir Reach 3 ✓
PMCSC will investigate actual situation
Resolved
32 Covered area 31.13 M2 at assessment time and now 10.00 M2
05/12/18 Dr.Sohail Shehzad Reach 1 ✓
PDA,STRPI, PMCSC, Resolved
33 Road Access removed GT Roads towards Firdous Chowk
05/12/18 Naeem khan Reach 1 ✓
PDA,STRPI, PMCSC, Resolved
34 Shop covered area reduced in new scenario
25/01/19 Hanifa Bibi Firdous Underpass ✓
STRPI, PMCSC Resolved
35 Shop reduced in new scenario
25/01/19 Mirza khan Hashtnagri Underpass
✓ STRPI, PMCSC Resolved
36 Actual Size was 31.1m now in design 14.5 m
05/12/2018 Zia Ur Rehman Hashtnagri underpass
✓ STRPI, PMCSC Resolved
37 Actual size 38.75 m after new design 26.46 m
05/12/2018 Najam Ud din Firdous centre ✓
STRPI, PMCSC Resolved
38 Actual size 40.98 m now 13.4
05/12/2018 Rehman Gul Shop 31 Firdous center
✓ STRPI, PMCSC Resolved
39 Access to market workshop of 22 wheeler tracks will be blocked
20/03/2019 Mustafeez Ur Rehman
Chgul Pura middle of BS-01 and BS-
02 ✓
STRPI, PMCSC Resolved
40 Rain water in Market, senitation, Gas pipeline, repairing of shops, Ramp & stair size, Compensation cheque
21/03/2019 Afsar Ali Qari Hydath Saif Ur Rehman
Hashtnagri Underpass
✓
STRPI, PMCSC Resolved
41 Compensation cheque not issue, construction work stop
24/04/2019 Saif Ur Rehman Abdul Ghani Haji Lawang Wajid Nadeem Shiekh Jawad
Firdous
& Hashtnagri Underpass
✓
STRPI, PMCSC Resolved
42 Main hole open in front of shop
08/05/2019 Hush Puppie Shop University Road ✓
STRPI, PMCSC Resolved
69
Sr. No.
Description of complaint Date of
complaint Name of
Complainant Location of complaint
Gender Action proposed/taken
status Remarks M F
43 Road width reduced from 5.5 to 3.5,Need road leveling with road coming from Khyber bazaar, worse road condition chargano chowk to Firdous chowk, Sewerage line issue, elevator slow construction process, miserable road condition GT road passing the chamber of Commerce
18/05/2019 Naeem Khan
Firdous underpass ✓
STRPI, PMCSC Resolved
44 The tunnel provided for feeder bus service at BS-08 is used as an alternate pedestrian passage and is used by the general public as an access to BRT station BS-08.
20/08/2020
Wajid Ali Nadeem
Malik Muhammad Khan &
Jalil Khan etc
Firdous underpass ✓
STRPI, PMCSC Resolved
45 Issue of 22 closed shops and subsequently financial losses facing by the shop owners are due to the inappropriate arrangement of stairs and ramps particularly at the north side
September, 2020
Malik Ashfaq - Owner,Shop#29SShakoor - Owner Shop#30 Wajid-Owner Shop#33 Ghayoor-Owner Shop#44 Sohail-Owner Shop# 17A AyubShah-Owner Shop#2
Hashtnagri Underpass – BS-07
✓
STRPI, PMCSC & ADB
Unresolved
70
VI. CONCLUSIONS AND RECOMMENDATIONS
A. Conclusions
106. Overall, the LARPs/ RPs implementation status reflected that considerable progress
has been made for the last two and a half years in the process of the LARP/RPs
implementation in terms of payment of land compensation and the disbursement of
rehabilitation and resettlement assistance to DPs. Out of total PRs. 1,335.19 million payable
amount, PRs. 1,332.96 million have paid to 522 DPs, remaining 55 DPs will be paid Rs. 21.948
million expectedly in month of February/March 2021. Out of total PRs 20.405 million payable
amount 14.450 million have paid to 182 out of total 226 vulnerable DPs. Out of total 61 project
vendors of the three reaches, 58 have been compensated with PRs. 8.120 out of total payable
PRs 8.540 million. Progress were also made in engaging with stakeholders, restoring
livelihoods, addressing the needs of vulnerable people, ongoing follow up of grievance
resolution and tracking monitoring impacts. However, the cases of unique DPs (Afghan
Refugees, blocked, below 18 years of age whom need guardian certificates for payment and
expired ID Cards holders and underage DPs are still pending. Vulnerable DPs like vendors,
employees of shopkeepers and land tenants have given special attention in compensation
payments and subsistence allowances. DPs have verbally asked during monthly payments
about their trust and satisfaction on transparency of disbursement of compensation payments.
All of them have found satisfied from LARP/RPs implementation process and our method of
payments of disbursement.
B. Recommendations
107. On the basis of above mentioned LARPs, RPs and addendums implementation,
overall, the LARP/RPs safeguard process at BRT project is effective, however in order to
enhance its effectiveness, following are some recommendations:
108. The PDA will make sure the availability of funds and overcome the usual delay in
meeting the procedural requirements so that the DPs may get their cheques timely. In this
connection, the newly appointed social safeguard focal person has assured that now there is
no such constraints regarding availability of funds and the same will be ensured till the full
payment to the remaining DPs.
109. For payment to Afghan Nationals, it is recommended that the payment should made
to the shopkeepers’ bank accounts with whom they had working before construction phase as
assistants and then the shopkeepers will pay them accordingly. Or in another case, their
pending payment may transfer to Shu’ra members’ bank accounts and they will further make
payments to those Afghan DPs. Still, if these proposals are not acceptable to PDA’s audit team, the issue will be further discuss at PDA and with ADB for viable channel of payment of
compensation.
110. Regarding underage pending payment cases, the STRPI and PMCSC resettlement
team will keep close liaison with the focal person Mr. Musavir (an advocate) so that the DPs
may receive guardian certificates as soon as possible.
111. The PDA & STRPI, ADB, PMCSC officials will holistically expedite the process of
payment of remaining compensation so that the DPs may not lose hope for their remaining
payments and avoid them from unnecessary complaining at PDA and ADB. It will be further
discuss with PDA’s focal person for social safeguard regarding placement of payable compensation amount in an escrow account (project or LAC account as appropriate) with
71
which compensation may deemed to have paid in accordance with ADB’s IR sourcebook on IR.
112. Coordinated program to Brand BRT services and all of its physical elements (vehicles,
Stations, Signage etc.) to differentiate it from traditional bus services and promote it as a
convenient and fast alternative.
113. Unlike other public transport projects that could be managed by a single department,
BRT by its nature is a project need multidisciplinary and multi-stakeholders approach.
114. Consumer satisfaction survey are important tools to get feedback from the users of
BRT, an expert impact assessment will be made on implementation of the project.
115. Implementation of BRT should not be limited to this corridor, expansion should take
place as early as possible in order to reduce pressure on the early built system and maintain
the quality of service.
116. Evaluate the system after implementation and take into consideration the response
from the users.
72
Annex 1: Notification of LARP Implementation Committee
1 Notification - LARP Implementation Committee
81
Annex 6: Linear Map of Reach – 1, 2 &3
Catego
ries of
DPs
Chai
nage
Fro
m To
Fro
m
T
o
Fro
m To
Fr
om To
Fr
o
m
T
o
Fr
o
m
T
o
Fr
o
m
To
Fro
m
To
0+0
00
0+0
00
0+3
10
0
+
3
2
5
1+0
00
1+0
20
3+
78
5
3+
79
5
6
+
2
7
0
6
+
3
0
0
6
+
2
4
0
6
+
2
6
0
6
+
3
0
0
6+3
90
6+800
6+8
20
Locat
ion
EBD land
(SardarGa
rhi)
Zia
Market
(Access
Ramp)
Tarskon
Hotel
(Chamkani)
Dr.
Zaheef
memorial
School
ArbabS
ikander
Flyover
area
Hashtn
agri
Underp
ass
Khalifa
Hotel/
Hashtnag
ri
underpas
s market
to
GovtHas
nain
Shaheed
School
Firdous
Underpass
& vendors
sitting
adjacent to
underpass
Type
of
impa
ct
Agriculture
land
Agricultur
e land Vendors
Masjid in
Green
Belt
Vendor
s
Lessee
s, sub-
lessees
,
shopke
epers
employ
ees
Vendors
Lessees,
sub-
lessees,
shopkeepe
rs
employees
& vendors
Land
Compe
nsation
Payme
nt of
Structur
e
Payme
nt of
Trees
Crop
compen
sation
Allowan
ces
Land
Compe
nsation
Payme
nt of
Structur
e
Payme
nt of
Trees
Crop
compen
sation
Allowan
ces
82
Linear Map of Reach – 2
Categories of DPs
Chainage From To From To From To
1+815 1+845 03+880 03+910 03+911 05+836
Location Staging Station-
Dabgari Gardens
Cantonment Board
Plaza to Sunehri
Masjid Road
No Impact
Type of impact Vendors Vendors
Allowances
Allowances
Linear Map of Reach – 3
Categories of DPs
Chainage From To From To
04+375 04+440 04+441 11+900
Location
In front of Speen
Masjid - University
town No Impact Type of impact Vendors
Allowances Allowances
Payment has been made to DPs
Payments are in process
Payments are not yet initiated
83
Annex 7: Consultations with Key Stakeholders
Dat
e
Locati
on
Type of
Stakehold
er
Objectives
Partici
pants
Opinion/Concern/Sugg
estion/Recommendatio
n
Results/Actions to
Address M F
Nov
emb
er
16,
201
7
Chamk
ani
Land
Owner of
Zia Market
& 02
Houses,02
quarter
• Disseminati
on of
information
about BRT,
compensati
on
documentat
ion
procedure
and guide
them for
bank
account
opening.
0
4
• The DP has shown his
concern that the affected
structure was under
assessed by C&W using
depreciation cost. The
compensation is not as
per the current market.
• The Social
resettlement team
properly oriented the
participants about
the BRT alignment.
• He was assured that
he will receive
compensation
amount according to
the market rate.
• The issue was
followed up with the
PD.
Nove
mber
23,20
17
PDA
Office
Shop
Owner
&Shura
Member
• Compensat
ion
documentat
ion for DPs.
• Shop
Ownership
issues.
0
2
• Meeting regarding
required documentations
for compensation for
below 18 years, Afghan
nationals and blocked ID
card.
• Two female DPs shop
owners but their names
are not mentioned in the
LARP as owners.
• Some employee names
and their details are
missing.
• PD was requested to
come up with a
procedure that
unable these unique
DPs to receive their
payments.
• Letter was written to
Afghan
Commissioner ate to
help PIU for the
payment to Afghan
Refugees.
• Under age were
guided to apply for
guardian certificates
in the court.
• PMCSC was
requested to
investigate the
missing names.
Nove
mber
24,20
17
Hashtnag
ri Under
Pass
Shop
Owners
• Disseminati
on of
information
about BRT,
compensati
on
documentat
ion
procedure
and
guidance
for opening
bank
account.
11 0
3
• Lack of understanding
regarding procedures of
compensation
documentation
• Female owner name is
missing in the list.
• Sher Ullah was employee
of shop but his name
mentioned as shop
owner currently he is not
employee.
• A detailed
orientation was
provided for the
required
documentation for
account opening and
compensation
payment.
• Both female and
male DPs was
assured of
appropriate action
and PMCSC was
requested to
investigate and
rectify.
• Riaz Gul and his brother
are employees of shop
but their names were
information provided
in the LARP.
84
Dat
e
Locati
on
Type of
Stakehold
er
Objectives
Partici
pants
Opinion/Concern/Sugg
estion/Recommendatio
n
Results/Actions to
Address M F
mentioned as shop
owners.
Nove
mber
30,
2017
Secretari
at
TMDT Meeting with
TMDT to
discuss
issues related
to Gender
Action Plan
8 4 • Gender mainstreaming in
BRT and GAP
implementation issues
were discussed
thoroughly.
• Women participation in
the project was
discussed;
• Gender sensitization of
the public while riding in
BRT buses.
• GAP implementation
will be responsibility
of all stakeholders.
• GAP will be
implemented and
TransPeshawar will
assure gender
concerns will be
addressed properly.
• PMCCB and
PMCSC will support
TransPeshawar and
STRPI will act to
facilitate the GAP
implementation
process.
Dece
mber
06,
2017
SardarGa
rhi
Landowne
rs/
Tenants
Investigation
of fruit trees
and fodder
crop
damages by
contractor
12 • DPs complained that
contractor cut pear trees
and damaged Berseem
crop.
• Confirmed total 23 pear
trees cut 8+15. 43.5
Marla land Berseem crop
damaged.
• Community requested for
compensation of the
damages.
• During the meeting
with DPs, along with
contractor and PDA
official at site, cost of
damages was
discussed and
estimated. ADB
consultant was part
of the meeting.
Dece
mber
07,
2017
Sunehri
Masjid
Shop
keepers
Investigation
on
genuineness
of the DPs,
whether they
are eligible
for
compensatio
n payment or
not.
15 • Six days ago,
Cantonment Board
evacuated vendors from
Sunehri Masjid
• Three vendors including
one with disability were
present there.
• In result of investigation
find that Mr Asif
Khan,Mr.NaseerZangi
and Mr Abdul Saboor
have their shops in
Market and they showed
their name as vendors on
the basis of their
displayed stalls outside of
their shops.
• During the
investigation,
NaseerZangi, Asif
and Abdul Saboor
were found not
vendors they are
shopkeepers
working in shops
and they are still
present in market.
• Following the
Cantonment
operation, no vendor
exists at the
surveyed location.
• All vendors will be
located and
compensation will be
paid accordingly.
85
Dat
e
Locati
on
Type of
Stakehold
er
Objectives
Partici
pants
Opinion/Concern/Sugg
estion/Recommendatio
n
Results/Actions to
Address M F
Dece
mber
07,
2017
Dabgari Vendors Collection of
CNIC & Bank
account
numbers
02 • Mr. Faheem requested
for a job in project as he
is educated having a
higher secondary school
certificate.
• He explained that he
suffered badly because
of police and cantonment
imposed heavy fines.
• Collected CNIC &
Account No from Mr.
Faheem vendor
• Need to add his
name in livelihood
plan for training
Dece
mber
07,
2017
Firdous
underpas
s, Sheikh
Abad
Near
Gulbhar
Women
Shop
owner
Collection
of CNIC &
Bank
account
numbers
0
6
• Lack of clarity for
eligibility criteria for
entitlements between two
APs.
• Conducted consultation
meeting held with widow
of Khan Zareen shop no
01 and her two
daughters. They have
misunderstanding about
their ownership with her
brother Salah Ud din.
• Informed her about
required documents for
compensation.
• Decoration cost of
shop and rent of
shop will be provided
to female AP and
business loss will be
provided to Salah Ud
Din.
• She has been
facilitated in bank
account opening.
Dec
emb
er
07,
201
7
Zia
Market
Shopkeep
er
Collection of
CNIC copy
and bank
Account no.
10 • Some shopkeeper and
employees still not have
account numbers but in
process.
• Collection of bank
account and CNIC
copy
Dec
emb
er
07,2
017
Zia
Market
House &
Shop
Owner
Zahid sister
share
confirmation
and meeting
05 • Zahid explained his
father total land is 06
Kanals. Out of which 03
Kanals is owned by
himself and 03 Kanals
are owned by her sisters.
• Zahid was requested to
arrange a meeting with
her sisters to clarify
ownership issues.
• Mr. Zahid asked about
his house rate and
workshops not included
during survey also till
now not clear about
demarcation which
indicate that auto
• PMCSC design
engineer along their
team marked his
land according to
required land before
construction.
• Zahid provide
estimated rate of
structure from
construction
engineer which show
difference of Rs.
200,000 from
PMCSC.
• Issues was
discussed with
PMCSC and it was
found that PMCSC
not follow valid
86
Dat
e
Locati
on
Type of
Stakehold
er
Objectives
Partici
pants
Opinion/Concern/Sugg
estion/Recommendatio
n
Results/Actions to
Address M F
workshop will be affected
or not.
procedure for
estimation of cost
which is totally
wrong practice.
• PMCSC was asked
to review his house
rate cost according
to MRS rate.
Dece
mber
10,
2017
SardarGa
rhi
Land
owners/
Tenants
Meeting to
conclude
compensatio
n for
agricultural
damages and
rent for land.
21 3 • Meeting with APs
community, contractor,
PDA. Community
disagreed with rent and
rates and asked for
compensation for land.
• Land rent rates
calculated and fixed
similarly land
damage cost shared.
Dece
mber
12,20
17
Firdous
Market
Shura
Member
• Verification
of Data
• Complaints
resolution
regarding
missing
employees
name
10 • Conducted meeting with
Mr.Zahiri Shah, Wajid
Nadeem, Qari
ZahidUllah, Haji Ghani
and Abdul Rehman at
Firdous Market regarding
complaints of missing
employee names and
family employee names.
• Discussed each
case with PMCSC
and cross checked
with survey forms
and micro plans.
• The list of DPs was
corrected
accordingly.
.
Dece
mber
12,
2017
Hashtnag
ri
Shura
Member
• Verification
of Data
• Complaints
resolution
regarding
missing
employees
name
04 • Meeting conducted with
regard to complaints of
missing employee names
and family employee
names.
• Discussed each case
with DPs and information
were cross checked with
survey forms and with
micro plan.
• The DPs were
informed the
following.
• Shop No 22: Aqib
left shop and is no
more employee of
shop no 22.
• Shop no
31,32,01,02,03,04,0
5 all are unmarried
family member –
they do not fulfill
entitlement criteria.
• Mr. Khan Afsar and
Wajid Nadeem
asked about
compensation date
and informed about
their intention of
travel abroad for a
few months; STRPI
team informed them
they can receive
87
Dat
e
Locati
on
Type of
Stakehold
er
Objectives
Partici
pants
Opinion/Concern/Sugg
estion/Recommendatio
n
Results/Actions to
Address M F
their amount after
arrival in country.
Dece
mber
15,
2017
SardarGa
rhi
DPs Land
measurement
for Up ramp
of EBD
11 • Measurement of land to
be used for structure of
EBD Up Ramp.
• Community objected
and halted work
pending
compensation.
Dece
mber
20,
2107
Secreta
riat,
TNDT
Governme
nt officials
Gender
Action Plan
update
12 03 • GAP discussed
• Updates shared by
TransPeshawar and
PMCCB
• Secretary Transport
supported GAP
implementation
• GAP updates will be
shared monthly.
• All concerned
stakeholders will
share their update
on GAP monthly
Dece
mber
20,
2107
SardarGa
rhi
DPs Resolution of
land
measurement
for EBD and
Contractor
work
resumption
6 1 • Compensations offered
by ADB consultant
• Support requested to
allow Land measurement
• DPs asked for
compensation
against land other
compensations offer
not accepted.
• DPs allowed
measurement of land
Dec
emb
er
26,
201
7
STRPI
Office
Shura
Member of
Firdous
Underpas
s
• Block
CNIC,
• Under 18 &
Afghan
National
08 • Shura members of
Firdous with DPs visited
office and asked for
speedy processing of
compensation also
shared concern regarding
block CNIC, under 18 &
Afghan national.
• ADB was
approached to
provide guidance for
timely compensation
of affected persons.
Dece
mber
28,
2017
STRPI
Office
Shura
Member
Correction of
DP Names
and other
03 • Shura member visited
office for correction of
some names. Copies of
CNIC according to survey
form were provided.
• Account numbers of
some DPs are still
pending such as under
18 years age and Afghan
Nationals.
• The issues are
followed up with
PDA and ADB.
Dece
mber
28,
2017
STRPI
Office
DPs of
Firdous
Cloth
Tower
• Relief from
project due
to
constructio
n of Bus
Station in
front of
0
2
• Follow up meeting for his
earlier claim of his
perceived loss of value of
his property due to BRT.
• Chief Architect of
PMCSC was
contacted and
requested for review
of the design.
Decision still
awaited.
88
Dat
e
Locati
on
Type of
Stakehold
er
Objectives
Partici
pants
Opinion/Concern/Sugg
estion/Recommendatio
n
Results/Actions to
Address M F
Firdous
Cloth
Tower
Janua
ry
27,20
18
Reach 3
Camp
Office
• Project
Manage
r
Contract
ors.
• Assistan
t
Director
PIU.
• Safety in
charge
service
provider,
• Women
Social
Officer
• Health and
safety
Deficiencie
s and
remedy or
precautions
08 01 • Discussed all issues
regarding health and
safety. Team was
informed that staff are not
fully trained for health
and safety. No document
for deployment of staff
their name, duty time,
location was shared
Some safety person
refused to do duty
according to their TORs
as asked by PIU staff.
• In Phase 3 Principal of
Government Girls High
School complaints
regarding noise, dust and
mobility of students and.
• Ms. Amna and Ms.
Kalsoom residential of
Phase 3 claimed that due
to welding and steel work
noise is creating
disturbance. They were
not able to perform their
work and school going
children are being
affected due to noise.
• Project Manager
informed contractors
will arrange health
and safety training in
next week.
• Safety in charge
needs resources for
proper instillation of
Sign boards and
other required
material.
• Health and safety in
charge distributed
brochure to
community and also
display banners at
different places for
grievance
complaints.
Febru
ary
08,
2018
PDA
Office
Shura
Member
Hasht-
nagri
• Demand of
05 years’ extension
in lease
agreement.
• Assurance
for
reestablish
ment of
shops at
same area
07 • Shura Members
Hashtnagri express their
fear for not being
compensated by PDA.
• The demand regarding
05 years’ extension in lease agreement from
PDA has not been
fulfilled.
• In LARP it was assured
that DPs affected shops
will be re-established
after completion of
construction work.
• DPs were assured
that all commitments
were made and
documented in the
LARP/RPs will be
fulfilled.
89
Dat
e
Locati
on
Type of
Stakehold
er
Objectives
Partici
pants
Opinion/Concern/Sugg
estion/Recommendatio
n
Results/Actions to
Address M F
Febru
ary
09,20
18
Hashtnag
ri
underpas
s
Shura
Members,
shopkeep
er, sub
lessee
owner
• Documenta
tion
provided for
correction
of name
and ID
Card
numbers
• Raised
issue of
shopkeeper
allowance
of Shop no
07 and
Shop no 14
also
decoration
of these 02
shops
• Decoration
cost of
Shop no 12
0
5
• Shura Member provided
documentation of
affected person.
• DP Irfan Ullah provided
agreement copy of shop
07.
• Issues of payment to DP
who left the shop after
the cut-of-date.
• List of DPs are
corrected.
• DPs who will be
affected will be
eligible for
compensation
payment.
Febru
ary
12,
201
8
PDA
Office
Lease
Owner
Hashtnagr
i
05 years
extension
lease
agreement
02 • • Mr. Mirza main lease
owner conduct meeting
with PIU team member
and asked about 05
years’ extension in lessee agreement and
show their concerned
about delay in issuance
of letter.
• Mr. Mirza asked
shopkeeper and
employee are eligible for
compensation which
Firdous under pass
shops damaged by PDA.
• A note to DG, PDA
was prepared and
sent for the lease
extension as per the
provision of LARP.
• A meeting was
arranged with PD for
compensation of loss
of income. The
matter was deferred
till the finalization of
the design.
Febru
ary
15,
2018
• PDA
Office
• ADB
consulta
nt
• STRPI
Team
• PMCSC
Social
Team
• Correction
Action Plan
• LARP
summery
• Data base
• Firdous
demolishin
g issue
• Afghan
commission
letter.
06 01 • ADB Consultant
conducted meeting with
STRPI and PMCSC
regarding CAP.
• LARP summery with
segregation of shifting
allowances, vulnerable
allowance and income
allowance as per LARP.
• Data base required for
DPs information and
status of payment.
• All issues were
followed up and
most of them
addressed.
90
Dat
e
Locati
on
Type of
Stakehold
er
Objectives
Partici
pants
Opinion/Concern/Sugg
estion/Recommendatio
n
Results/Actions to
Address M F
• LARP
translation
• Allied
structure
due
diligence
• BRT app
add on
PDA
website.
• In meeting discussed
about Firdous underpass
demolishing issue in
detailed informed him
about Senior Director
meeting with Shura
member and they are
agreed till decision of
Firdous design
finalization.
• ADB Consultant
discussed about afghan
refugees DPs
compensation letter to
Afghan commission then
informed still afghan
office not respond to
officially but verbally they
asked we cannot due to
shortage of staff.
• Discussed in detailed
about due diligence of
allied structure with
PMCSC representatives.
• PDA website should
include a Tab on online
grievance submission
from DPs.
March
05,
2018
WCCI,
Sarhad
Chamber
of
Commerc
e
Women
Chamber
of
Commerc
e and
Industry
Peshawar
• BRT
introduction
;
• Informed
about 15%
commercial
spaces for
women;
Engage
WCCI
provide list
of women
entreprene
urs
01 03 • WCCI has appreciated
about the opportunity of
15 % commercial spaces
for women
• Brochures may be
developed for
commercial spaces
• Dust pollution due to BRT
and traffic jams
• WCCI will share list
• Another meeting
suggested
• WCCI welcomes
BRT; FithratIly as
Bilour the
Chairperson greets
the BRT team
• Next meeting to be
held in 2/3 weeks
• Separate group of
shops for women
suggested
• Price of shops and
its date of availability
requested.
March
08,
2018
UN
Women
Office
UN
Office
• UN
Women
meeting
Internationa
l Women
Day
7 1
5
• Female issues discussed
• BRT discussed and
numerous opportunities
for women shared
• 15% Commercial spaces
for women shared
• Facilities for women
shared
• BRT receives
welcome amid
reservations on
actual timely delivery
• Further meetings
suggested
91
Dat
e
Locati
on
Type of
Stakehold
er
Objectives
Partici
pants
Opinion/Concern/Sugg
estion/Recommendatio
n
Results/Actions to
Address M F
• Video Presentation on
BRT is a good idea
March
13,
2018
PDA
Office
DPs of
Hashtnagr
i
• Issue of
Letter of
Extension
of Lease of
the two
underpasse
s
Hashtnagri
and Firdous
5 1 • Shura members of the 2
underpasses visit PDA
STRPI office to protest
• APs – Underpass Female
DPs plus Hashtnagri
employees, shopkeepers
and Lessees turn down
receiving of
compensation payments
in protest for not
receiving promised letter
from PDA for extension
of lease.
• Shura members
assured letter
issuing under
process
• PD informed
• PDA DF informed
• Compensation
payments to
Hashtnagi DPs
deferred
• Concerned shared
for the inordinate
delay in issuing of
letter
March
14,
2018
QissaKh
wani
DPs Develop case
studies;
facilitate
PMCSC
2 3 • Both female DPs shared
concern for demolished
shops.
• Suggested that PDA
should provide lump sum
compensations instead of
each month.
• Interest in obtaining
shops in BRT 15%
commercial spaces for
women
• Shura member Wajid Ali
Nadeem facilitated the
meeting.
• Case studies of
Female DPs of
Hashtnagri&Firdous
u/p at QissaKhwani:
Rukhsana and Amna
Kareem. Also
detailed on BRT
Commercial spaces
15% for women. APs
are happy to see
positive actions of
PDA
• Both DPs agreed
and shared
information for case
studies.
March
22,
2018
• WCCI,
Sarhad
Chamb
er of
Comm
erce
Women
Chamber
of
Commerce
and
Industry
Peshawar
• Follow Up
of BRT
introduction
; 15%
commercial
spaces for
women;
Engage
WCCI
provide list
of women
entreprene
urs
1 5 • WCCI may provide an
updated list of women
entrepreneurs, if
possible.
• BRT may increase shops
for women.
• BRT brochure requested
• Facilities and
opportunities for women
be included in a BRT
brochure.
• Suggested including
Mardan WCCI
• Pink bus in Mardan and
Abbottabad to be
introduced
April
01,
2018
Hashtnag
ri
Underpas
s
Lessees
owner &
shopkeep
er
• Extension
in lease
agreement
1
5
0
1
• Conducted meeting with
Hashtnagri main lessees
and sub leases to collect
compensation but they
did not want to receive till
• A meeting held with
directors and DG PD
for extension as per
LARP provisions.
92
Dat
e
Locati
on
Type of
Stakehold
er
Objectives
Partici
pants
Opinion/Concern/Sugg
estion/Recommendatio
n
Results/Actions to
Address M F
Hashtnagr
i
approval of 05 years of
extension in lease
contract.
• PDA assured that a
letter for lease
extension will be
provided ASAP.
April
2,
2018
PC
Peshawa
r
Chairper
son
Women
Parliam
entary
Caucus
• STRPI
introduction
and sharing
GAP
0
1
Work of Social Team
appreciated
Timeframe of BRT
More interaction advised
• Ms. Meraj Humayun
highly appreciated
the work of PDA
Social Team.
• As Director of Board
at KPUMA requested
more interaction and
information on BRT
shared.
April
02,20
18
SardarGa
rhi
Tenants
/Owner
• Crops
/Trees
compensati
on
1
0
0
4
• Conducted meeting with
Tenants and land owner
son issues related with
trees and crops
compensation.
• Most of the DPs provided
their documents for
payment processing but
few were not available
• Participants were
informed about the
compensation
amount will be
provided following
the availability of the
Finance Director.
April
6,
2018
Sardar
Garhi
DPs • Grievance
investigatio
n
0
7
• Complaint #26
investigated
• Aneesur Rehman, the
land owner confirmed
wrongful claim of tenant
on his land.
• Complaint resolved
as the DP is not
eligible for
compensation.
Sardar
Garhi
• DP
Roohul
Amin
• Market
access
blocked
investigatio
n
0
3
• Front access to market
blocked due to digging of
BRT near SardarGarhi
• PMCSC
representative at site
took up matter with
PMCSC civil works
engineers and
contractor.
• 3 Km stretch dug up
for drain along GT
Road; affects few
access points along
the stretch
• Access matter to be
resolved by PDA
ensured.
Sardar
Garhi
DPs • Communic
ation with
female APs
0
1
0
5
• Meeting with disabled
female AP
• Issue of 30 marlas land
was not compensated.
• Commercial spaces 15%
discussed with female
• Commercial spaces
15% for females will
be followed up.
• Issue of 30 marlas
case registered by
DPs – court decision
awaited.
93
Dat
e
Locati
on
Type of
Stakehold
er
Objectives
Partici
pants
Opinion/Concern/Sugg
estion/Recommendatio
n
Results/Actions to
Address M F
DPs as investment
opportunity
• Female DPs interested in
land purchase
April
9,
2018
Sardar
Garhi
Zahidullah • Issue of
land price
grievance -
Case follow
up
0
1
• DP disappointed about
the lengthy decision-
making process by the
court.
• Case hearings in
progress
• 3 hearings were
done
• Court asked
Revenue dept.
submit comments by
next hearing.
April
10,
2018
Sardar
Garhi
• DP
Musawir
• Claim of
tenant
0
1
• Musawir claimed tenant
not received
compensation.
• Case has been
followed up. The
tenant was hired
after cut- of -date.
April
11,
2018
PDA
DPs
SardarGar
hi: Sabiha,
Rafia,
SafiaAshr
afia,
Mumtaz&
Sharafat
Compensat
ion
payments
orientation
0
1
0
6
• Timely and fair
compensation payments
to DPs
• Payment procedures
explained
• • ADB
Mission
• Firdous
Underpass
design
finalization
0
6
• Meeting with DG for
design finalization of
Firdous underpass
• Lease extension of
Firdous underpass.
• DG assured the
issues will be
resolved
• • DG PDA • Resolution
of Firdous
Underpass
impasse
0
6
• Follow up with DG for
lease extension.
• STRPI was informed
that Firdous
Underpass issue
discussed and
resolved with Mirza
Khan of MCC
• Resultant action and
timeframe will be
shared by PDA.
`April
14,
2018
• Hashtn
agri
Underp
ass
• Firdous
Underp
ass
Vendors • Under 18
documents
required for
payment
03 • Incomplete
documentation from APs.
• Three vendors provided
guardian certificate and
one DP provided B form.
• DPs were guided to
follow up the proper
procedures.
April
16,
2018
Hashtnag
ri
Underpas
s
• Lessee
Relative
s
• Decoration
compensati
on issue
08 • Replacement of
employees after the cut-
of-date. Both new
employee of Shop 7 and
• Eligibility criteria was
explained to DPs.
94
Dat
e
Locati
on
Type of
Stakehold
er
Objectives
Partici
pants
Opinion/Concern/Sugg
estion/Recommendatio
n
Results/Actions to
Address M F
old were claiming
compensation payment.
• Same issue exists with
shop 14.
April
18,
2018
SardarGa
rhi
• Naveed/
Rashid
• Follow up
of the
grievance
of 30 Marla
land was
not
compensat
ed.
02 • DP desired early
resolution of his 30 Marla
measurement issue.
• Map of area shared.
• Case hearings in
progress
• Court asked PDA
and Revenue Dept.
to submit comments
by next hearing.
April
20,
2018
PDA • Musawir • Objection
on
employee’s name in
addendum
Reach 1
0
1
• Objection of listing wrong
employee name in
addendum Reach 1
• Objection shared
with PMCSC for
investigation and
necessary action.
April
22,20
18
Hashtnag
ri
Underpas
s
• Lease
Owner
Hashtna
gri
• Follow up
of the five-
years lease
extension
agreement
0
4
• Mirza Khan, the main
lease owner and
members of
Shuraconducted meeting
with PIU team member
and asked about 05
years extension in lessee
agreement and have
expressed their concern
about delay in issuance
of letter.
• The issue was
followed up with
PDA for the issuance
of letter at their
earliest.
April
23,20
18
Firdous
Cloth
Tower
Owner &
Shopkeep
ers
• Concerns
on design
changes in
front of
Firdous
cloth tower
06 • Meeting held with
Mr.Naeem owner of
Firdous Cloth Tower and
shop keepers for follow
up of grievance related to
design changes.
• They were informed
that the design is
under process and
according to Director
no major changes
are anticipated in the
Firdous Underpass.
April
24,
2018
New
Masjid at
AfridiGar
hi near
Ring
Road
• DPs of
Masjid
Green
Belt GT
Road
• Building of
the mosque
in an
alternative
place.
03 • Requested to release of
compensation amount.
• Bank account exists in
the name of three
member’s committee,
i.e., Muhammad Sher
Khan, Ijaz Ahmed and
Muhammad Zaman
• Masjid Abu Huraira;50m
from Ring Road at
AfridiGarhi, near canal
and Maal Mundi.
• New masjid is
approximately within
• STRPI visited the
site and confirmed
masjid construction
is in progress at
Afridi Garhi.
• Masjid committee is
established and is
intact.
• Land for Masjid is
purchased and civil
works were in
progress.
• No other Masjid in
close vicinity
95
Dat
e
Locati
on
Type of
Stakehold
er
Objectives
Partici
pants
Opinion/Concern/Sugg
estion/Recommendatio
n
Results/Actions to
Address M F
800m away from the
demolished structure.
• . Masjid area approx. 6.5
Marla.
• Design to construct 3
floors. Basement,
ground and 1st floor.
• Masjid land was
purchased @Rs.
4,400,000.
• Funds contributed by
locals
April
27,
2018
Sardar
Garhi
DPs • Formation
of DPCs
2
2
2
0
• DPs were concerned
losing their land as a
means of their livelihood.
• Livestock has also been
lost being depended on
land for fodder.
• They have demanded an
alternative source of
income; such as shops in
BRT commercial spaces.
• Applications have been
submitted
• Male and female
DPCs were formed.
• Total 29 female DPs
at Sardar Garhi and
43 male DPs
• Aneesur Rehman,
Khan Gul and
Kamran were
chosen
representatives of
Sardar Garhi DPC.
• Applications were
submitted to
TransPeshawar for
allocation of
commercial spaces
to DPs on
preferential basis.
April
27,2
018
Sardar
Garhi
• DPs
losing
land
• Formation
of DPCs
• 2
0
• Women have shown their
concerned regarding
livelihood affect due to
agriculture land acquired
for BRT. Women raised
their concern that at the
time of survey no
livelihood plan developed
for APs who lost their
main source of livelihood.
Keeping livestock is big
challenge for them and
they have started to sale
their animals.
• Women also want jobs
for their husband and
sons in the project
specially in eastern bus
depot.
• They also demand
vulnerable allowance for
poor families.
• DPC was formed for
women to raise their
voice for concern.
• Contractors were
requested to provide
jobs relevant to their
skill sets on priority
basis.
• Most of the poor DPs
were the recipient of
the vulnerable
allowance.
May
02,
2018
PDA • DP
Sardar
Garhi
• Allocation
of BRT
commercial
spaces
01 • Khan Gul, DP of
SardarGarhi on behalf of
group of DPs requested
for preferential allotment
of commercial spaces to
DPs as they have lost
• Applications
received from DPs
for allocation of
commercial spaces
were shared with
TransPeshawar.
96
Dat
e
Locati
on
Type of
Stakehold
er
Objectives
Partici
pants
Opinion/Concern/Sugg
estion/Recommendatio
n
Results/Actions to
Address M F
land and earning
capacity.
• Compensation payments
received can be
reinvested in generating
means of future income
• The issue will be
followed up with
TransPeshawar
May
03,
2018
Hashtnag
ri
Underpas
s
Lessees
owner &
shopkeepe
r
Hashtnagri
• Compensat
ionpayment
to DPs
15 01 • Conducted meeting with
Hashtnagri main lessees
and sub leases to collect
compensation.
• The payment was
refused till the approval
of the compensation
payment of the Firdous
demolished shops.
•
• DPs were assured
for following up this
issue with PD.
May
04,
2018
PDA DP
Zahidull
ah
• Issue of
land price
grievance -
Case follow
up
0
1
• Zahid shared update of
the case being heard in
court.
• Court asked to produce 2
witnesses external and 2
property dealers to
support his claim.
• Four hearings held
• Next date 4 June
2018
May
04,
2018
PDA DP
Naveed
/ Rashid
• Follow up
of the
grievance
of 30 marla
land lost
land
without
compensati
on.
0
2
• Shared update of the
case
• The court will have a
hearing in near future.
• Three hearings done
• Next date 21 May
2018
• Comments of DC not
shared
May
07,
2018
PDA DPs
Hashtnagri
and
Firdous
Underpass
• Underpass
final Design
• Vacation of
shops
17 • Shura of Underpass DPs
expressed their concerns
for final design of both
Firdous and Hashtnagri
underpasses
• Informed about the date
of vacation of shops
• Concerns on
compensation payment.
• STRPI will follow up
to ensure the
desired changes in
the design of the
underpass.
• DPs agreed to
vacate shops of
Firdous Underpass
• Compensation for
DPs was assured as
per LARP
May
07,
2018
PDA DP
Niazbeen
and
PatwariSar
darGarhi
• Claim on
trees
ownership
04 0
1
• Complainant claim of
trees ownership on
property at SardarGarhi
• Complainant to
produce proof of
ownership
• Patwari has to
ascertain the
property ownership
97
Dat
e
Locati
on
Type of
Stakehold
er
Objectives
Partici
pants
Opinion/Concern/Sugg
estion/Recommendatio
n
Results/Actions to
Address M F
as per revenue
record
• PMCSC was
informed to
investigate and
make changes if
required.
8 May
2018
Tambuw
aan Stop
Complaint
of Latif
Omarzai
• Investigatio
n of
complaint
received
0
4
0
1
• Visited the business site
reported by Mr. Latif
Omarzai.
• Visited both business
sites located close to
each other.
• Doctor’s Car Point – car
bargain - still exists and
the other vacated
‘furniture shop’ was taken over by another person -
another car bargain
owner.
• Doctor’s Car Point: Met Mr. Momin at Car Point.
Momin informed us that
he is the owner of the
property and Latif
Omarzai was working as
a Commission agent. He
said that Latif left
business 4 months ago
as business was
affected.
• Doctor’s Car Point the car bargain is not
in RoW.
• There is ample
space besides the
road for cars to stop
in front of the
bargain.
• The location of the
Furniture business is
way inside compared
to car bargain. The
facility has separate
entrance parallel to
the bargain and the
actual shop is at
least 15m inside the
entrance. The
access to the
business from RoW
is not hampered.
• The property has not
been affected due to
BRT.
May 8,
2018
Revenu
e Dept.
Officials
Revenue
Dept.
Patwari,
Tehsildar
Girdawar
• Confirmatio
n of
Compensat
ions paid
0
5
0
1
• payments to DPs at
SardarGarhi
• Payments made to DP
following reviewing the
power of attorney
document.
• Confirmation of pending
payments
• Record from
Revenue
Department was
received
• Family of DP Saadat
Khan (Late) was
paid compensation
through his attorney.
May
08,20
18
Firdous
Underp
ass
Shopkeep
ers &
Employee
s
• Verification
of DPs
name
according
to LARP
before
compensati
on
disburseme
nt
1
5
0
0
3
• Visited Firdous Under
pass for verification of
shopkeepers and
employees name as per
the list provided in the
LARP.
• The list was shared with
PMCSC to investigate
and include in the
addendum.
• Verification was
carried out of the
DPs and their
ownership status.
• The list of DPs will
be updated by
PMCSC accordingly.
•
98
Dat
e
Locati
on
Type of
Stakehold
er
Objectives
Partici
pants
Opinion/Concern/Sugg
estion/Recommendatio
n
Results/Actions to
Address M F
May
09,
2018
Tambu
wan
Mor,
Dr. Car
Point
Complaina
nt Latif
Omarzai
• Joint
STRPI and
PDA
Investigatio
n
0
4
• Owners present at Dr.
Car Point
• Owners reject all claims
of Latif Omarzai
• Access to site not
blocked by BRT
• The alleged damage
claim was Jointly
investigated by PDA
and STRPI.
• An undertaking from
the owner refuting all
claims of Latif.
• It was found that the
complainant is not
legible for
compensation.
May
14,
2018
PDA DP
Niazbeen
and
PatwariSar
darGarhi
• Trees
ownership
0
3
• Complainant claim of
trees ownership
• Confirmation of need
from Revenue dept. of
proof of ownership
• Guided on need of
proof
• PMCSC was asked
to verify the
documents of
complainant
May
14,
2018
PDA Complaina
nt
IrshadSard
arGarhi
• Crops
compensati
on
0
2
• Claim of complainant for
crops compensation at
Sardar Garhi
• Claim received after cut-
off date
• PMCSC to investigate
• PMCSC to report on
claim
• After Cut Off date
December 2016
May
14,
2018
PDA DP Khan
Gul,
Nadeem
• Compensat
ion
payment
0
2
• Concern on delay of
compensation payment
• DP did not produce
original proof of ID
• Compensation
amount cheque
ready at PDA
• Assured
compensation
payment on
producing proof of
identity.
May
14,
2018
PDA DP
Mussawir
• Addendum
Reach 1
GT Road
0
1
• Concern over inclusion of
in correct names in
addendum Reach 1
• Interest in commercial
spaces of BRT
• Discussed with
PMCSC to
investigate
• TransPeshawar
address shared with
DP for further action
May
24,
2018
PDA DPs
relatives at
Underpass
• Compensat
ion
payment
amount
1
5
02 • DPs has expressed their
concerns on amount of
the compensation which
is low according to their
expectation.
• As a protest did not
receive checks from
PDA.
• Meeting was held
with DPs and Shura
members and they
were convinced that
the amount is based
on criteria explained
in the LARP
99
Dat
e
Locati
on
Type of
Stakehold
er
Objectives
Partici
pants
Opinion/Concern/Sugg
estion/Recommendatio
n
Results/Actions to
Address M F
• DPs ask for meeting
before receiving
compensation
• Pointed out LARP
compensation amounts
already shared
• DPs were agreed to
accept the
compensation
amount related to
their income loss.
May
28.
2018
PDA DP
Firdous
Underpass
Jalil Khan
• Confirmatio
n of DP
0
2
0
1
• DP Jalil Khan
shopkeeper reservation
and concern over name
of employee at his shop
• Wrong name mentioned
in the LARP
• Record shared with
DP
• Correct name was
included in Micro
plans.
• PMCSC was
requested to make
necessary
amendments in
LARP
May
29,
2018
PDA DP Mirza
Khan
• Design 0
3
0
1
• DP Mirza Khan
expressed his concern
that the revised final
design of Firdous
Underpass was not
shared with him.
• PD PIU was
informed
• PMCSC informed to
share design
May
30,
2018
PDA ADB
Mission
• BRT LARP
Progress
Update
0
6
0
1
• Meeting held among ADB
mission STRPI and
PMCSC.
• Grievance resolution of
Dr. Car Point
• Sharing of Design of
underpass
• Resolution of demolished
toilets issue between
stakeholders
• Compensation payments
• Internal monitoring
reporting.
• Updates shared on
grievances
registered and
resolved
• Car Point issue
resolved
• Design will be
shared by
PDA/PMCSC
• Toilets issue be
resolved through
meeting of
stakeholders.
• STRPI will share
Internal Monitoring
Report with ADB.
May
30,
2018
PDA DP
Mirza
Khan
• Mediation
and joint
settlement
of design
issue of
Firdous
Underpass
0
3
0
1
• Issue of final design of
Firdous Underpass
discussed.
• Disagreement for
resolution pending
between Mirza Khan and
Firdous Cloth tower
owner Haji Naeem Khan
• Mirza Khan wants
demolished toilets to be
restored whereas Haji
Naeem doesn’t like the restoration of toilets
facing its Cloth Tower
• Efforts were made to
mediate between
two parties
• Mirza Khan turns
down offer to sit with
Haji Naeem.
• Mirza Khan
threatened to
approach court of
law if tolets were not
restored.
100
Dat
e
Locati
on
Type of
Stakehold
er
Objectives
Partici
pants
Opinion/Concern/Sugg
estion/Recommendatio
n
Results/Actions to
Address M F
May
31,20
18
Firdous
Underpas
s
Shura
members
&
Employee
s
• Conflict
resolution
meeting to
persuade
DPs not to
refuse the
compensati
on payment
under the
category of
employees
of shop
keepers.
2
5
• Conducted a lengthy
consultation meeting with
DPs and Shura members
along with PMCSC team.
• DPs were told that the
compensation amount is
based on the criterion
laid down in the LARP.
The same yardstick was
used with Hashtnagri
Underpass.
• DPs were agreed to
collect their
compensation
amount on June 04
2018 from PDA
office through
STRPI.
April
01,
2018
Hashtnag
ri
Underpas
s
Lessees
owner &
shopkeep
er
Hashtnagr
i
• Extension
in lease
agreement
1
5
0
1
• Conducted meeting with
Hashtnagri main lessees
and sub leases to collect
compensation but they
did not want to receive till
approval of 05 years of
extension in lease
contract.
• A meeting held with
directors and DG PD
for extension as per
LARP provisions.
• PDA assured that a
letter for lease
extension will be
provided ASAP.
April
2,
2018
PC
Peshawa
r
Chairper
son
Women
Parliam
entary
Caucus
• STRPI
introduction
and sharing
GAP
0
1
Work of Social Team
appreciated
Timeframe of BRT
More interaction advised
• Ms. Meraj Humayun
highly appreciated
the work of PDA
Social Team.
• As Director of Board
at KPUMA requested
more interaction and
information on BRT
shared.
April
02,20
18
SardarGa
rhi
Tenants
/Owner
• Crops
/Trees
compensati
on
1
0
0
4
• Conducted meeting with
Tenants and land owner
son issues related with
trees and crops
compensation.
• Most of the APs provided
their documents for
payment processing but
few were not available
• Participants were
informed about the
compensation
amount will be
provided following
the availability of the
Finance Director.
April
6,
2018
Sardar
Garhi
DPs • Grievance
investigatio
n
0
7
• Complaint #26
investigated
• Anees ur Rehman, the
land owner confirmed
wrongful claim of tenant
on his land.
• Complaint resolved
as the DP is not
eligible for
compensation.
Sardar
Garhi
• DP
Roohul
Amin
• Market
access
blocked
investigatio
n
0
3
• Front access to market
blocked due to digging of
BRT near SardarGarhi
• PMCSC
representative at site
took up matter with
PMCSC civil works
engineers and
contractor.
101
Dat
e
Locati
on
Type of
Stakehold
er
Objectives
Partici
pants
Opinion/Concern/Sugg
estion/Recommendatio
n
Results/Actions to
Address M F
• 3 Km stretch dug up
for drain along GT
Road; affects few
access points along
the stretch
• Access matter to be
resolved by PDA
ensured.
Sardar
Garhi
DPs • Communic
ation with
female APs
0
1
0
5
• Meeting with disabled
female DP
• Issue of 30 marlas land
was not compensated.
• Commercial spaces 15%
discussed with female
DPs as investment
opportunity
• Female DPs interested in
land purchase
• Commercial spaces
15% for females will
be followed up.
• Issue of 30 marlas
case registered by
DPs – court decision
awaited.
April
9,
2018
Sardar
Garhi
Zahidullah • Issue of
land price
grievance -
Case follow
up
0
1
• DP disappointed about
the lengthy decision-
making process by the
court.
• Case hearings in
progress
• 3 hearings were
done
• Court asked
Revenue dept.
submit comments by
next hearing.
April
10,
2018
Sardar
Garhi
• DP
Musawir
• Claim of
tenant
0
1
• Musawir claimed tenant
not received
compensation.
• Case has been
followed up. The
tenant was hired
after cut- of -date.
April
11,
2018
PDA
DPs
SardarGar
hi: Sabiha,
Rafia,
SafiaAshr
afia,
Mumtaz&
Sharafat
Compensat
ion
payments
orientation
0
1
0
6
• Timely and fair
compensation payments
to DPs
• Payment procedures
explained
ADB
Mission
• Firdous
Underpass
design
finalization
0
6
• Meeting with DG for
design finalization of
Firdous underpass
• Lease extension of
Firdous underpass.
• DG assured the
issues will be
resolved
DG PDA • Resolution
of Firdous
Underpass
impasse
0
6
• Follow up with DG for
lease extension.
• STRPI was informed
that Firdous
Underpass issue
discussed and
resolved with Mirza
Khan of MCC
102
Dat
e
Locati
on
Type of
Stakehold
er
Objectives
Partici
pants
Opinion/Concern/Sugg
estion/Recommendatio
n
Results/Actions to
Address M F
• Resultant action and
timeframe will be
shared by PDA.
`April
14,
2018
• Hashtn
agri
Underp
ass
Firdous
Underpas
s
Vendors • Under 18
documents
required for
payment
03 • Incomplete
documentation from APs.
• Three vendors provided
guardian certificate and
one DP provided B form.
• DPs were guided to
follow up the proper
procedures.
April
16,
2018
Hashtnag
ri
Underpas
s
• Lessee
Relative
s
• Decoration
compensati
on issue
08 • Replacement of
employees after the cut-
of-date. Both new
employee of Shop 7 and
old were claiming
compensation payment.
• Same issue exists with
shop 14.
• Eligibility criteria was
explained to DPs.
April
18,
2018
SardarGa
rhi
• Naveed/
Rashid
• Follow up
of the
grievance
of 30 marla
land was
not
compensat
ed.
02 • DP desired early
resolution of his 30 Marla
measurement issue.
• Map of area shared.
• Case hearings in
progress
• Court asked PDA
and Revenue Dept.
to submit comments
by next hearing.
April
20,
2018
PDA • Musawir • Objection
on
employee’s name in
addendum
Reach 1
0
1
• Objection of listing wrong
employee name in
addendum Reach 1
• Objection shared
with PMCSC for
investigation and
necessary action.
April
22,20
18
Hashtnag
ri
Underpas
s
• Lease
Owner
Hashtna
gri
• Follow up
of the five-
years lease
extension
agreement
0
4
• Mirza Khan, the main
lease owner and
members of
Shuraconducted meeting
with PIU team member
and asked about 05
years extension in lessee
agreement and have
expressed their concern
about delay in issuance
of letter.
• The issue was
followed up with
PDA for the issuance
of letter at their
earliest.
April
23,20
18
Firdous
Cloth
Tower
Owner &
Shopkeep
ers
• Concerns
on design
changes in
front of
Firdous
cloth tower
06 • Meeting held with
Mr.Naeem owner of
Firdous Cloth Tower and
shop keepers for follow
up of grievance related to
design changes.
• They were informed
that the design is
under process and
according to Director
no major changes
are anticipated in the
Firdous Underpass.
103
Dat
e
Locati
on
Type of
Stakehold
er
Objectives
Partici
pants
Opinion/Concern/Sugg
estion/Recommendatio
n
Results/Actions to
Address M F
April
24,
2018
New
Masjid at
AfridiGar
hi near
Ring
Road
• DPs of
Masjid
Green
Belt GT
Road
• Building of
the mosque
in an
alternative
place.
03 • Requested to release of
compensation amount.
• Bank account exists in
the name of three
member’s committee,
i.e., Muhammad Sher
Khan, Ijaz Ahmed and
Muhammad Zaman
• Masjid Abu Huraira;50m
from Ring Road at
AfridiGarhi, near canal
and Maal Mundi.
• New masjid is
approximately within
800m away from the
demolished structure.
• . Masjid area approx. 6.5
Marla.
• STRPI visited the
site and confirmed
masjid construction
is in progress at
Afridi Garhi.
• Masjid committee is
established and is
intact.
• Land for Masjid is
purchased and civil
works were in
progress.
• No other Masjid in
close vicinity
• Design to construct 3
floors. Basement,
ground and 1st floor.
• Masjid land was
purchased @Rs.
4,400,000.
• Funds contributed by
locals
April
27,
2018
Sardar
Garhi
DPs • Formation
of DPCs
2
2
2
0
• DPs were concerned
losing their land as a
means of their livelihood.
• Livestock has also been
lost being depended on
land for fodder.
• They have demanded an
alternative source of
income; such as shops in
BRT commercial spaces.
• Applications have been
submitted
• Male and female
DPCs were formed.
• Total 29 female DPs
at Sardar Garhi and
43 male DPs
• Aneesur Rehman,
Khan Gul and
Kamran were
chosen
representatives of
Sardar Garhi DPC.
• Applications were
submitted to
TransPeshawar for
allocation of
commercial spaces
to DPs on
preferential basis.
April
27,2
018
Sardar
Garhi
• DPs
losing
land
• Formation
of DPCs
• 2
0
• Women have shown their
concerned regarding
livelihood affect due to
agriculture land acquired
for BRT.Women raised
their concern that at the
time of survey no
livelihood plan developed
for APs who lost their
main source of livelihood.
Keeping livestock is big
challenge for them and
they have started to sale
their animals.
• DPC was formed for
women to raise their
voice for concern.
• Contractors were
requested to provide
jobs relevant to their
skill sets on priority
basis.
• Most of the poor DPs
were the recipient of
the vulnerable
allowance.
104
Dat
e
Locati
on
Type of
Stakehold
er
Objectives
Partici
pants
Opinion/Concern/Sugg
estion/Recommendatio
n
Results/Actions to
Address M F
• Women also want jobs
for their husband and
sonsin the project
specially in eastern bus
depot.
• They also demand
vulnerable allowance for
poor families.
May
02,
2018
PDA • DP
Sardar
Garhi
• Allocation
of BRT
commercial
spaces
01 • Khan Gul, DP of Sardar
Garhi on behalf of group
of DPs requested for
preferential allotment of
commercial spaces to
DPs as they have lost
land and earning
capacity.
• Compensation payments
received can be
reinvested in generating
means of future income
• Applications
received from DPs
for allocation of
commercial spaces
were shared with
TransPeshawar.
• The issue will be
followed up with
TransPeshawar
May
03,
2018
Hashtnag
ri
Underpas
s
Lessees
owner &
shopkeepe
r
Hashtnagri
• Compensat
ion
payment to
DPs
15 01 • Conducted meeting with
Hashtnagri main lessees
and sub leases to collect
compensation.
• The payment was
refused till the approval
of the compensation
payment of the Firdous
demolished shops.
•
• DPs were assured
for following up this
issue with PD.
May
04,
2018
PDA DP
Zahidull
ah
• Issue of
land price
grievance -
Case follow
up
0
1
• Zahid shared update of
the case being heard in
court.
• Court asked to produce 2
witnesses external and 2
property dealers to
support his claim.
• Four hearings held
• Next date 4 June
2018
May
04,
2018
PDA DP
Naveed
/ Rashid
• Follow up
of the
grievance
of 30 Marla
land lost
land
without
compensati
on.
0
2
• Shared update of the
case
• The court will have a
hearing in near future.
• Three hearings done
• Next date 21 May
2018
• Comments of DC not
shared
May
07,
2018
PDA DPs
Hashtnagri
and
Firdous
Underpass
• Underpass
final Design
• Vacation of
shops
17 • Shura of Underpass DPs
expressed their concerns
for final design of both
Firdous and Hashtnagri
underpasses
• STRPI will follow up
to ensure the
desired changes in
the design of the
underpass.
105
Dat
e
Locati
on
Type of
Stakehold
er
Objectives
Partici
pants
Opinion/Concern/Sugg
estion/Recommendatio
n
Results/Actions to
Address M F
• Informed about the date
of vacation of shops
• Concerns on
compensation payment.
• DPs agreed to
vacate shops of
Firdous Underpass
• Compensation for
DPs was assured as
per LARP
May
07,
2018
PDA DP
Niazbeen
and
Patwari
SardarGar
hi
• Claim on
trees
ownership
04 0
1
• Complainant claim of
trees ownership on
property at SardarGarhi
• Complainant to
produce proof of
ownership
• PatwarI has to
ascertain the
property ownership
as per revenue
record
• PMCSC was
informed to
investigate and
make changes if
required.
8 May
2018
Tambuw
aan Stop
Complaint
of Latif
Omarzai
• Investigatio
n of
complaint
received
0
4
0
1
• Visited the business site
reported by Mr. Latif
Omarzai.
• Visited both business
sites located close to
each other.
• Doctor’s Car Point – car
bargain - still exists and
the other vacated
‘furniture shop’ was taken over by another person -
another car bargain
owner.
• Doctor’s Car Point: Met Mr. Momin at Car Point.
Momin informed us that
he is the owner of the
property and Latif
Omarzai was working as
a Commission agent. He
said that Latif left
business 4 months ago
as business was
affected.
• Doctor’s Car Point the car bargain is not
in RoW.
• There is ample
space besides the
road for cars to stop
in front of the
bargain.
• The location of the
Furniture business is
way inside compared
to car bargain. The
facility has separate
entrance parallel to
the bargain and the
actual shop is at
least 15m inside the
entrance. The
access to the
business from RoW
is not hampered.
• The property has not
been affected due to
BRT.
May 8,
2018
Revenu
e Dept.
Officials
Revenue
Dept.
Patwari,
Tehsildar
Girdawar
• Confirmatio
n of
Compensat
ions paid
0
5
0
1
• payments to DPs at
SardarGarhi
• Payments made to DP
following reviewing the
power of attorney
document.
• Confirmation of pending
payments
• Record from
Revenue
Department was
received
• Family of DP Saadat
Khan (Late) was
paid compensation
through his attorney.
106
Dat
e
Locati
on
Type of
Stakehold
er
Objectives
Partici
pants
Opinion/Concern/Sugg
estion/Recommendatio
n
Results/Actions to
Address M F
May
08,20
18
Firdous
Underp
ass
Shopkeep
ers &
Employee
s
• Verification
of DPs
name
according
to LARP
before
compensati
on
disburseme
nt
1
5
0
0
3
• Visited Firdous Under
pass for verification of
shopkeepers and
employees name as per
the list provided in the
LARP.
• The list was shared with
PMCSC to investigate
and include in the
addendum.
• Verification was
carried out of the
DPs and their
ownership status.
• The list of DPs will
be updated by
PMCSC accordingly.
May
09,
2018
Tambu
wanMo
r, Dr.
Car
Point
Complaina
nt Latif
Omarzai
• Joint
STRPI and
PDA
Investigatio
n
0
4
• Owners present at Dr.
Car Point
• Owners reject all claims
of Latif Omarzai
• Access to site not
blocked by BRT
• The alleged damage
claim was Jointly
investigated by PDA
and STRPI.
• An undertaking from
the owner refuting all
claims of Latif.
• It was found that the
complainant is not
legible for
compensation.
May
14,
2018
PDA DP
Niazbeen
and
Patwari
SardarGar
hi
• Trees
ownership
0
3
• Complainant claim of
trees ownership
• Confirmation of need
from Revenue dept. of
proof of ownership
• Guided on need of
proof
• PMCSC was asked
to verify the
documents of
complainant
May
14,
2018
PDA Complaina
nt
IrshadSard
arGarhi
• Crops
compensati
on
0
2
• Claim of complainant for
crops compensation at
Sardar Garhi
• Claim received after cut-
off date
• PMCSC to investigate
• PMCSC to report on
claim
• After Cut Off date
December 2016
May
14,
2018
PDA DP Khan
Gul,
Nadeem
• Compensat
ion
payment
0
2
• Concern on delay of
compensation payment
• DP did not produce
original proof of ID
• Compensation
amount cheque
ready at PDA
• Assured
compensation
payment on
producing proof of
identity.
May
14,
2018
PDA DP
Mussawir
• Addendum
Reach 1
GT Road
0
1
• Concern over inclusion of
in correct names in
addendum Reach 1
• Interest in commercial
spaces of BRT
• Discussed with
PMCSC to
investigate
107
Dat
e
Locati
on
Type of
Stakehold
er
Objectives
Partici
pants
Opinion/Concern/Sugg
estion/Recommendatio
n
Results/Actions to
Address M F
• TransPeshawar
address shared with
DP for further action
May
24,
2018
PDA DPs
relatives at
Underpass
• Compensat
ion
payment
amount
1
5
02 • DPs has expressed their
concerns on amount of
the compensation which
is low according to their
expectation.
• As a protest did not
receive checks from
PDA.
• DPs ask for meeting
before receiving
compensation
• Pointed out LARP
compensation amounts
already shared
• Meeting was held
with DPs and Shura
members and they
were convinced that
the amount is based
on criteria explained
in the LARP
• DPs were agreed to
accept the
compensation
amount related to
their income loss.
May
28.
2018
PDA DP
Firdous
Underpass
Jalil Khan
• Confirmatio
n of DP
0
2
0
1
• DP Jalil Khan
shopkeeper reservation
and concern over name
of employee at his shop
• Wrong name mentioned
in the LARP
• Record shared with
DP
• Correct name was
included in Micro
plans.
• PMCSC was
requested to make
necessary
amendments in
LARP
May
29,
2018
PDA DP Mirza
Khan
• Design 0
3
0
1
• DP Mirza Khan
expressed his concern
that the revised final
design of Firdous
Underpass was not
shared with him.
• PD PIU was
informed
• PMCSC informed to
share design
May
30,
2018
PDA ADB
Mission
• BRT
LARP
Progress
Update
0
6
0
1
• Meeting held among ADB
mission STRPI and
PMCSC.
• Grievance resolution of
Dr. Car Point
• Sharing of Design of
underpass
• Resolution of demolished
toilets issue between
stakeholders
• Compensation payments
• Internal monitoring
reporting.
• Updates shared on
grievances
registered and
resolved
• Car Point issue
resolved
• Design will be
shared by
PDA/PMCSC
• Toilets issue be
resolved through
meeting of
stakeholders.
• STRPI will share
Internal Monitoring
Report with ADB.
May
30,
2018
PDA DP
Mirza
Khan
• Mediation
and joint
settlement
of design
issue of
0
3
0
1
• Issue of final design of
Firdous Underpass
discussed.
• Disagreement for
resolution pending
• Efforts were made to
mediate between
two parties
108
Dat
e
Locati
on
Type of
Stakehold
er
Objectives
Partici
pants
Opinion/Concern/Sugg
estion/Recommendatio
n
Results/Actions to
Address M F
Firdous
Underpass
between Mirza Khan and
Firdous Cloth tower
owner Haji Naeem Khan
• Mirza Khan wants
demolished toilets to be
restored whereas Haji
Naeem doesn’t like the restoration of toilets
facing its Cloth Tower
• Mirza Khan turns
down offer to sit with
Haji Naeem.
• Mirza Khan
threatened to
approach court of
law if toilets were not
restored.
May
31,20
18
Firdous
Underpas
s
Shura
members
&
Employee
s
• Conflict
resolution
meeting to
persuade
DPs not to
refuse the
compensati
on payment
under the
category of
employees
of shop
keepers.
2
5
• Conducted a lengthy
consultation meeting with
DPs and Shura members
along with PMCSC team.
• DPs were told that the
compensation amount is
based on the criterion
laid down in the LARP.
The same yardstick was
used with Hashtnagri
Underpass.
• DPs were agreed to
collect their
compensation
amount on June 04
2018 from PDA
office through
STRPI.
20
Feb,
18
PDA
Site
Office in
Reach-1
Camp)
Project
Impleme
nting
Departm
ent
• Consultati
on
meeting
with PDA
staff
(concerne
d Deputy
Directors)
regarding
the
proposed
new two-
legs of
access
ramp at
Chamkani
Mor,
potential
impacts
due to
new
changes
in the
design, to
get detail
of ROW
and
request for
joint visit
2 • It was agreed that
PDA technical staff
was to accompany
PMCSC resettlement
consultant for their
orientation of the ROW
and demarcation of the
site as per proposed
design.
• PDA provided
detail of ROW
about new
proposed site for
additional two-legs
of access ramp,
and also
conducted a joint
field visit to the site
and oriented
PMCSC
resettlement
consultants.
109
Dat
e
Locati
on
Type of
Stakehold
er
Objectives
Partici
pants
Opinion/Concern/Sugg
estion/Recommendatio
n
Results/Actions to
Address M F
to the site
assessme
nt.
21
Feb,
18
At the
residenc
e of
Zahidull
ah Khan
Land
Owner of
additional
affected
(5 Marla
land) at
Chamkan
i Mor
• Conducte
d
consultatio
n with land
holder of
Zia Market
land,
proposed
for the
additional
land
acquisition
. Orient
the owner
of land
about the
new land
plot to be
acquired.
1 • The land owner
agreed to provide
additional land for the
construction of access
ramp (for additional
mix-traffic lane), but on
the current prevalent
market rate of
commercial land. He
demanded the same
rate as he has already
received the amount
for his 12.5 Marla land
recently.
The land owners agreed to provide the land on the market rate for commercial lands.
22
Feb,
18
Sardar
Garhi
Petrol
Station/
Market
(affected
site)
Shop-
keepers
& their
employee
s and
structure
owners
• Focus
Group
Discussio
n to
introduce
new
design
changes
specificall
y of
access
ramp and
get
feedback
on the
project
and
potential
impacts.
1
9
PMCSC Resettlement consultant introduced the new changes in the access ramp. Got the opinion of shopkeepers, their employees and of the structure owners in case of disruption of their businesses. The structure owners agreed because they have constructed the shops on government land. The shopkeepers were reluctantly ready for dislocation of their businesses while the employees were disappointed for losing their subsistence earnings.
• Informed the
structure owners
for possible
demolition of their
shops, informed
the shopkeepers &
employees for fair
compensation
against their
business and job
losses.
24
Feb,
18
Sardar
Garhi
Petrol
Station/
Market
Shop-
keepers
& their
employee
s and
• To inform
the
affected
shopkeep
ers, their
employee
s and
1
8
Resettlement consultant shared the entitlements for the APs. As the shopkeepers, employees and structure owners knew about the recently paid compensation to the Zia
• The structure
owners,
shopkeepers and
employees were
found agreed to
the proposed
110
Dat
e
Locati
on
Type of
Stakehold
er
Objectives
Partici
pants
Opinion/Concern/Sugg
estion/Recommendatio
n
Results/Actions to
Address M F
(affected
site)
structure
owners
structure
owners
about the
payment
of
compensa
tion
(entitleme
nts)
against
their
losses and
get
feedback.
Market shopkeepers therefore, they were also agreed to the proposed compensation amount for them.
compensation
amount.
12th
Mar,
2019
At
PMCSC
Office
Shu’rah members
and
available
shopkeep
ers/ APs
of
Firdous
Underpas
s
• To discuss
about the
entitlemen
ts/
payment
of
compensa
tion to
Firdous
Underpas
s APs
beyond 12
moths
time. As
the
constructi
on
activities
are still in
progress
and the
shops has
not yet
handed
over to the
APs back.
1
6
The APs of underpass having a fear of no payment after 12 months however, the Shu’rah members and other APs were informed about the set entitlements for the shopkeepers and lessees and sub-lessees. They were formally informed that their payment of compensation will continue even beyond 12 months until their shops has not been handed over to them. As, the APs were quite worried about payments after 12 months and has been verbally complaining time and again to STRPI.
• All the participants
were quite happy
over this
information and
showed their
satisfaction.
23rd
Mar,
2019
At
PMCSC
Office
Available
shopkeep
ers/ APs
of
Hashtnag
ri
• In view
completio
n of 12
months’ time
agreed in
the
approved
1
8
The shopkeepers and available lessees and sub-lessees were informed about the set entitlements for the shopkeepers and lessees and sub-lessees. They were formally informed that
• All the participants
were quite happy
over this
information and
showed their
satisfaction.
111
Dat
e
Locati
on
Type of
Stakehold
er
Objectives
Partici
pants
Opinion/Concern/Sugg
estion/Recommendatio
n
Results/Actions to
Address M F
Underpas
s
LARP of
Reach-1,
to discuss
about the
payment
of
compensa
tion to
Hashtnagr
i
Underpas
s’s APs beyond 12
moths
time.
their payment of compensation will continue even beyond 12 months until their shops has not been handed over to them. As, the APs were quite worried about payments after 12 months and has been verbally complaining time and again to STRPI.
5
April,
18
MMP/
PMCSC
office
Main-
lessee
and
represent
atives of
shopkeep
ers of
Firdous &
Hashtnag
ri
Underpas
ses
• To show
the newly
design of
Firdous
underpass
right
before its
finalization
, to make
them sure
that the
impacts
will remain
be the
same as
mentioned
in the
original
LARP of
Reach-1,
and
incorporat
e any
additional
changes
at this
stage of
design
finalization
5 The main-lessee and his two representatives showed satisfaction that they have been considered for consultation. The main-lessee suggested few changes for accommodating of demolished 2 to 6 shops which will be demolished by giving access to the bus station.
• The PMCSC
design team
assured to the
main-lessee of the
Firdous underpass
them that the
number of shops
will be
accommodated
accordingly and
when the design
team made
changes they will
be again invited for
their review.
9
April,
18
MMP/
PMCSC
office
Represen
tatives of
shopkeep
ers of
• To show
the
desired
design
4 Overall, the two representatives of underpass showed satisfaction from the desired changes in the
• The PMCSC
design team again
assured to the
underpass
112
Dat
e
Locati
on
Type of
Stakehold
er
Objectives
Partici
pants
Opinion/Concern/Sugg
estion/Recommendatio
n
Results/Actions to
Address M F
Firdous &
Hashtnag
ri
underpas
ses
changes
in Firdous
underpass
as agreed
with main-
lessee
and
representa
tives
during
previous
consultatio
n meeting.
To take
their
opinion
whether
the APs of
underpass
are
satisfied
from the
changes
made in
the
underpass
design or
not.
underpass however, still they requested that if the few shops which were still not mentioned in the design, may also be accommodated accordingly.
representatives
that the desired
required number of
shops will be
accommodated
accordingly and
when the design
team made
changes they will
be again invited for
their review.
13
April,
18
MMP/
PMCSC
office
Represen
tatives of
shopkeep
ers of
Firdous &
Hashtnag
ri
underpas
ses
• To show
the
desired
design
changes
in Firdous
underpass
as agreed
with main-
lessee
and
representa
tives
during
previous
consultatio
n meeting.
To make
sure that
the
participant
4 Overall, the representatives of Firdous underpass were happy about the desired changes, and requested that currently, the changes made in the design are acceptable to them if the design is considered final from every aspect.
• The participants
were happy abou
the design
changes however,
the PMCSC
design team
informed the
participants that
the design is
almost final and it
will be further
shared with OBDM
consultation for
final review and
comments, if any.
The design team
further informed
the participants
that after the
OBDM consultants
review, super final
113
Dat
e
Locati
on
Type of
Stakehold
er
Objectives
Partici
pants
Opinion/Concern/Sugg
estion/Recommendatio
n
Results/Actions to
Address M F
s are
satisfied
from the
desired
changes.
design will also be
shared with the
underpass main-
lessee and its
representatives.
28th
April,
2018
MMP/
PMCSC
office
Main-
lessee of
Firdous &
Hashtnag
ri
underpas
ses
• To show
the final
design
changes
of Firdous
underpass
. To take
final
opinion/
concerns
(if any) of
the main-
lessee.
And to
agree on
the final
design
and
signed it
by both
the
parties.
3 Overall, the main-lessee of Firdous underpass was satisfied from the final design, feeling happy and showed no concerns. He was agreed with the final design and signed the copy of final design as a sign of his agreement.
• Finally, both the
parties signed a
copy of the final
design as an
agreement on the
design.
5th
May,
2018
MMP/
PMCSC
office
Main-
lessee of
Firdous &
Hashtnag
ri
underpas
ses
• To show
the
revised
final
design
changes
of Firdous
underpass
. To take
final
opinion/
concerns
(if any) of
the main-
lessee.
And to
agree on
the final
design
and
signed it
3 Generally, the main-lessee of Firdous underpass was satisfied from the revised final design, quite happy and presented no concerns. He was agreed with the revised version of final design and re-signed the copy of final design as a sign of his agreement.
• Finally, both the
parties signed a
copy of the final
design as an
agreement on the
final revised
version of design
of Firdous
underpass.
114
Dat
e
Locati
on
Type of
Stakehold
er
Objectives
Partici
pants
Opinion/Concern/Sugg
estion/Recommendatio
n
Results/Actions to
Address M F
by both
the
parties.
31st
May,
2018
At
Firdous
underpa
ss
Shu’rah members
and other
APs
• To discuss
about the
entitlemen
ts upon
which the
underpass
APs had
need few
clarificatio
ns
particularl
y payment
of
compensa
tion to
relatives
of
shopkeep
ers. To
inform the
Shu’rah members
about the
revised
design of
Firdous
underpass
.
1
3
The APs of underpass having a fear of no payment after 12 months however, the APs were informed about the set entitlements for each category including specifically about the relatives of shopkeepers. After confirmation, the Shu’rah members satisfied from the process. The participants were also informed about the changes in the revised design of Firdous underpass.
• In nut’s shell, the Shu’rah members agreed with the
already set
entitlements for
each category and
showed
agreement. The
participants
informed that they
will further inform
all APs about the
meeting and its
proceedings
accordingly.
115
Annex 8: List of Corrected Cases (identified & corrected in Addendum 1 & Reach-1 LARP)
S.# Reference AP to the approved Addendum-1 to Reach-1 LARP
Status of AP Previously reported in Approved Addendum-1 to Reach-1 LARP
Type of correction made Remarks
1 Annex-2, Sr#1, Name list of affected shopkeepers of Sardar Garhi Filling Station
Correction of employees’ name
Previously, employee name was mistakenly reported as “Mr. Shafqat Ali s/o Din Muhammad” instead of his corrected name which is “Mr. Shafaqat Ali s/o Din Muhammad”
Corrected name of employee is Mr. Shafaqat Ali s/o Din Muhammad”
Correction is made of employee name as per identification of STRPI & audit team.
2 Annex-2, Sr#2, Name list of affected shopkeepers of Sardar Garhi Filling Station
Correction of shopkeepers’ NIC#
Shopkeepers’ Mr. Attaullahs’ NIC# was mistakenly reported as “15212-8799129-7” instead of corrected NIC# which is “15202-8799129-7”
Corrected NIC # of the shopkeeper is 15202-8799129-7
Correction is made in AP NIC# accordingly as per identification of STRPI/ audit team.
3 Annex-2, Sr#2, Name list of affected shopkeepers of Sardar Garhi Filling Station
Correction of employees’ NIC#
employees’ Mr. Rafiullahs’ NIC# was mistakenly reported as “15202-8853445-5” instead of corrected NIC# which is “15202-8833445-5”
Corrected NIC # of the employee is 15202-8833445-5
Correction is made in AP NIC# accordingly as per identification of STRPI/ audit team.
4 Annex-2, Sr#3, Name list of affected shopkeepers of Sardar Garhi Filling Station
Correction of shopkeepers’ name
Shopkeepers’ name was mistakenly reported as “Mr. Intikhaab Alam s/o Bakhshish” instead of his corrected name which is “Mr. Intikhab Alam s/o Bakhshish”
Corrected name of employee is Mr. Intikhab Alam s/o Bakhshish”
Correction is made of Shopkeepers’ name as per identification of STRPI & audit team.
5 Annex-2, Sr#5, Name list of affected shopkeepers of Sardar Garhi Filling Station
Correction of shopkeepers’ NIC#
Shopkeepers’ Mr. Izhar Khans’ NIC# was mistakenly reported as “07301-
7127639-9” instead of corrected NIC# which is “17301-7127639-9”
Corrected NIC # of the shopkeeper is 17301-7127639-9
Correction is made in AP NIC# accordingly as per identification of STRPI/ audit team.
6 Annex-2, Sr#5, Name list of affected shopkeepers of Sardar Garhi Filling Station
Correction of employees’ name
Previously, employee name was mistakenly reported as “Mr. Shahid s/o Kachkol” instead of his corrected name which is “Mr. Shahid Khan s/o Kachkool”
Corrected name of employee is Mr. Shahid Khan s/o Kachkool”
Correction is made of employee name as per identification of STRPI & audit team.
116
7 Annex-2, Sr#5, Name list of affected shopkeepers of Sardar Garhi Filling Station
Correction of employees’ Fathers’ name
Previously, employee’s Fathers’ name was mistakenly reported as “Mr. Zabta Khan” instead of his corrected name which is “Mr. Zabita Khan”. Similarly, his NIC’s number was mistakenly reported as 17301-1825488-7 instead of corrected NIC# which is 17301-1825482-7
Corrected name of employee’s Father name is Mr. Zabita Khan & his corrected NIC# is 17301-1825482-7
Correction is made of employee name as per identification of STRPI & audit team.
8 Annex-7, Sr#3, Name list of affected structures’ owners and Compensation Amount
Correction of shopkeepers’ NIC#
Shopkeepers’ Mr. Attaullahs’ NIC# was mistakenly reported as “15212-
8799129-7” instead of corrected NIC# which is “15202-8799129-7”
Corrected NIC# of the shopkeeper is 15202-8799129-7
Correction is made in AP NIC# accordingly as per identification of STRPI/ audit team.
9 Annex-8, Sr#2, Name list of affected shopkeepers of Sardar Garhi Filling Station
Correction of shopkeepers’ NIC#
Shopkeepers’ Mr. Attaullahs’ NIC# was mistakenly reported as “15212-
8799129-7” instead of corrected NIC# which is “15202-8799129-7”
Corrected NIC# of the shopkeeper is 15202-8799129-7
Correction is made in AP NIC# accordingly as per identification of STRPI/ audit team.
10 Annex-8, Sr#3, Name list of affected shopkeepers of Sardar Garhi Filling Station
Correction of shopkeepers’ name
Shopkeepers’ name was mistakenly reported as “Mr. Intikhaab Alam s/o Bakhshish” instead of his corrected name which is “Mr. Intikhab Alam s/o Bakhshish”
Corrected name of employee is Mr. Intikhab Alam s/o Bakhshish”
Correction is made of Shopkeepers’ name as per identification of STRPI & audit team.
11 Annex-8, Sr#5, Name list of affected shopkeepers of Sardar Garhi Filling Station
Correction of shopkeepers’ NIC#
Shopkeepers’ Mr. Izhar Khans’ NIC# was mistakenly reported as “07301-7127639-9” instead of corrected NIC# which is “71301-7127639-9”
Corrected NIC# of the shopkeeper is 71301-7127639-9
Correction is made in AP NIC# accordingly as per identification of STRPI/ audit team.
12 Annex-9, Sr#4, Name list of affected employees & their compensation amount
Correction of employees’ NIC#
Employees’ Mr. Rafiullah s/o Amanullah NIC# was mistakenly reported as “15202-8853445-5” instead of corrected NIC# which is “15202-8833445-5”
Corrected NIC # of the shopkeeper is 15202-8833445-5
Correction is made in AP NIC# accordingly as per identification of STRPI/ audit team.
13 Annex-9, Sr#12, Name list of affected employees & their compensation amount
Correction of employees’ NIC#
Employees’ Mr. Feroz Khan s/o Ajab Khan age was mistakenly reported as “below 18 years or underage” while later he had
The NIC # later on provided by Mr. Feroz Khan is 17301-01616981-1
Correction is made in AP NIC# accordingly as per identification of STRPI/ audit team.
117
provided his NIC# as “17301-01616981-1
14 Annex-9, Sr#13, Name list of affected employees & their compensation amount
Correction of employees’ name
Previously, employee name was mistakenly reported as “Mr. Shahid s/o Kachkol” instead of his corrected name which is “Mr. Shahid Khan s/o Kachkool”
Corrected name of employee is Mr. Shahid Khan s/o Kachkool”
Correction is made of employee name as per identification of STRPI & audit team.
15 Annex-9, Sr#15, Name list of affected employees & their compensation amount
Correction of employees’ Fathers’ name
Previously, employee’s Mr. Muhammad Hayat Khan’s Fathers’ name was mistakenly reported as “Mr. Zabta Khan” instead of his corrected name which is “Mr. Zabita Khan”. Similarly, employee’s NIC’s number was mistakenly reported as 17301-1825488-7 instead of corrected NIC# which is 17301-1825482-7
Corrected name of employee’s Father name is Mr. Zabita Khan & his own corrected NIC# is 17301-1825482-7
Correction is made of employee name as per identification of STRPI & audit team.
16 Annex-11, Sr#22, Shop#20, “Assessment of Fixtures and Decoration of Shops (Hashtnagri and Firdous Underpasses)
Correction of Shopkeeper’s name
Previously, shopkeepers’ name of shop#20 was mistakenly written as Khair Gul instead of real business owner as Mr. Nazir Jan.
Corrected name of shopkeeper is Nazir Jan s/o Bismillah Jan was a shopkeeper of Shop#20. He has received all his compensation amount however, due to the mentioned clerical mistake in the LARP of Reach 1, his decoration amount is still pending.
Correction is made of employee name as per identification of STRPI & audit team.
118
Annex 9: Grievance Log during the Reporting Period
S.
No
Summary of
complaints
Date of
Received
Name of
Complainant Location/Reach
Gender Action to be taken Status Remarks
M F
1 The complaint was
related to the less
number of shops were
documented in the
LARP as compared to
the actuals (Shops 47
shops in Firdous, 38
shops in Hashtnagri),
20/11/17 Mirza Khan
Reach 1
✓ LARP and annexes were
reviewed with AP
representative. No
difference was found.
Resolved
2 Objection on BS-08
location and remolding
of shop that will impact
on his business due to
less number of
customers.
20/11/17 M. Naeem Khan
Reach 1
✓ Several consultations with
DP and with Chief
Architect. Matter is still
pending till the finalization
of the design.
In
Process
3 Shop employee name
was mentioned in the
LARP and shop owner
name was missing.
27/11/2017 Rukhsana Bibi
Reach 1
✓ Name was changed on
basis of evidences
collected after
investigation.
Resolved
4 Shop employee name
was mentioned in the
LARP and shop owner
name was missing.
27/11/2017 Amna Karim
Reach 1
✓ Name was changed on
basis of evidences
collected after
investigation
Resolved
5 Shop employee name
was mentioned in the
LARP and shop owner
name was missing.
27/11/2017 Riaz Gul
Reach 1
✓ Name was changed on
basis of evidences
collected after
investigation.
Resolved
6 Illegally demolishing of
shops in the Firdous
Market.
27/11/2017 QariHidayatRehman
Reach 1
✓ Several consultation
meetings were held.
Decision hold till than
finalization of design of
BS-08 at Firdous Market.
In
Process
119
S.
No
Summary of
complaints
Date of
Received
Name of
Complainant Location/Reach
Gender Action to be taken Status Remarks
M F
10 Assurance for
protection for rights of
entitlements
06/12/2017 1.Riaz Gul
2. Rukhsana Bibi
3.Amna Karim
4.Ayub Shah
5.Malik Ashfaq
Ahmed
6.Qari HadyatUllah
Reach 1
✓
✓
✓
✓
✓
✓
Several consultation
meetings were held.
Decision hold till than
finalization of design of
BS-08 at Firdous Market
In
Process
11 Illegally construction
start before
compensation
06/12/2017 Liaqat Ali
Reach 1
✓ Consultation meetings
were held. Construction
work was sopped.
Payment has been made.
Resolved
12 Complaints of income
loss from the second
shop.
06/12/2017 Shakeel Ahmad
Reach 1
✓ For same type of
business, the shopkeeper
is entitled for one income
loss even he was using
second shop as a go
down. ADB policy was
explained to him.
Resolved
13 Complaints for non-
payment of
compensation
16/11/2017 1.Nadir Khan
2.Mahar Ali
3.Rehman Gul
4.Nazir Gul
5.Javeed Khan
6.Shafi Ullah
7.Faqeer Gul
8.Said Khan
Reach 1
✓ They are not present
before the cut-off date and
during the census survey.
Resolved
14 Complaint regarding
non-payment of
structure in
accrordance with the
market rate.
08/12/2017 ZahidUllah Khan
Reach 1
✓ Payment has made as per
market rate without
depreciation according to
ADB policy.
Resolved
15 PDA give notice for
demolishing of wash
room.
26/12/2018 MuhmmadFurqan
Reach 2
✓ Cantonment board and
concerned officials of
PDA. It was found that
Resolved
120
S.
No
Summary of
complaints
Date of
Received
Name of
Complainant Location/Reach
Gender Action to be taken Status Remarks
M F
washrooms are out of the
ROW. A concrete wall will
be constructed to avoid
any damage from the
earth moving machines.
16 Compensation claim as
vendor
21/12/2017 Noor Zada
Reach 1
✓ Vendor compensation
claim but not present
before the cut-off date
Resolved
17 Demand for Bus 01
Name SardarGhari
instead of Chamkani
26/12/2017 Rashid Khan
Reach 1
✓ Change of the area name
is in the domain of District
Administration. APs were
requested to contact
directly.
Rejected
18 Less compensation
amount
04/01/2018 Muhammad Qasim
Reach 1
✓ Explained compensation
and R&R policy to AP.
Resolved
20 Compliant for
demolished shops
compensation till
reestablished.
23/01/2018 1.Malak Ashfaq
2.Zahir Shah
3.Ayub Shah
4.Qari HadyatUllah
5.Khurram Masih
6.Wajid Ali Nadeem
7.Mushtaq Masih
8.Amna Karim
✓
✓
Several consultation
meetings were held.
Decision hold till than
finalization of design of
BS-08 at Firdous Market.
Resolved
21 Commercial land was
rated as agriculture
land
23/01/2018 ZahidUllah
Reach 1
✓ The land classification has
been wrong. The case is
pending with the Referee
Judge. AP is satisfied the
court hearing so far.
Resolved
22 BRT acquired 93 Marla
from the AP. Only 63
Marla land has been
awarded. A total 30
Marla land is missing
31/01/2018
26/3/2018
Naveed Ahmed
Reach 1
✓ Revenue official held
investigation and awaited
their report. AP has
registered his case in the
court of Law.
Resolved
121
S.
No
Summary of
complaints
Date of
Received
Name of
Complainant Location/Reach
Gender Action to be taken Status Remarks
M F
has been acquired but
not awarded.
23 Payment of additional
acquisition of 5.5 Marla
Land as per
commercial rate.
21/3/2018 Zahid Ullah
Reach 1
✓ Discussed with PD
Issue is being pursued
with PD and Deputy
Director Reach 1
Resolved
24 Complainant have
claimed decoration
cost on the name of
Yasir khan Shop No.14
21/3/2018 Reach1 ✓ Shura member concept is
different from complainant
Resolved
25 Complain against
illegal threat extended
by PDA on the pretext
that Shop No Ms.01 at
KTH underpass
medicine market
University road
Peshawar.
22/03/18 Irfanullah Reach3 ✓ Confirmed from PMCSC-
design team KTH
underpass will not impact
with BRT.
Resoled
26 Complaint claimed that
his name is missing
from crop
compensation APs list
22/02/18 Muhammad Ilyas Reach1 ✓ PMCSC will investigate
the case
Resolved
27 PDA tool plaza ring
road Peshawar
managing director
claimed that due to
BRT construction traffic
divert on different
roads due to which he
bear daily Rs.30000
income loss.
07/03/18 Muhammad Ashraf Reach3 ✓ STRPI raised the issue
and PDA asked they will
discuss with higher
authority
Rejected
122
S.
No
Summary of
complaints
Date of
Received
Name of
Complainant Location/Reach
Gender Action to be taken Status Remarks
M F
28 Additional 5Marla land
demand for BRT,
complainant wants it to
be identified as
commercial land.
21/03/18 Zahidullah Reach1 ✓ PMCSC will investigate
actual situation
Resolved
29 Loss of income due to
blockage of vehicle
access
23/04/18 Fazal Rabi Reach1 ✓ PMCSC will investigate
actual situation
Resolved
30 Blockage of road to
service station
29/09/18 Muhammad Saleem Reach1 ✓ PMCSC will investigate
actual situation
Resolved
31 Garbage and waste
materials infront of
Khyber bank
11/10/18 Hina Jehangir Reach3 ✓ PMCSC will investigate
actual situation
Resolved
32 Covered area 13.13 M
at assessment time
and now 10.00 M
05/12/18 Dr. Sohail Shehzad Reach1 ✓ PDA,STRPI,PMCSC Resolved
124
Annex 11. Details of Compensation Payment of Different Categories Made to APs
1. Eastern Bus Depot
1.1. Land Compensation Eastern Bus Depot (EBD)
S. No Name of AP Father's Name Male Female Type of AP Type of
structure / Asset
Land Value (PKR)
Paid (PKR)
Unpaid
1 Asma Fazal Ur Rehman 1 landlord land 272,503,383 272,503,383 -
2 Muhmmad Faseel Haji Khan 1 landlord land 209,232,483 209,232,483 -
3 Muhmmad Jabbar Haji Khan 1 landlord land 207,353,149 207,353,149 -
4 Muhmmad Naveed Khan Haji Khan 1 landlord land 2,192,555 2,192,555 -
5 Anees Ur Rehman Habib Ur Rehman 1 landlord land 169,844,781 169,844,781 -
6 Shamas Ur Rehman Habib Ur Rehman 1 landlord land 24,196,421 24,196,421 -
7 Fakhra Jameel Habib Ur Rehman 1 landlord land 8,809,376 8,809,376 -
8 Hummira Shahid Habib Ur Rehman 1 landlord land 8,809,376 8,809,376 -
9 Ghazala Karamat Habib Ur Rehman 1 landlord land 8,809,376 8,809,376 -
10 Safia Waqar Habib Ur Rehman 1 landlord land 8,809,376 8,809,376 -
11 Fazal Ur Rehman Abdul Rehman 1 landlord land 12,842,113 12,842,113 -
12 Syed Ul Ibrar Abdul Sattar 1 landlord land 24,118,115 24,118,115 -
13 Khadam Husain Abdul Qayyum 1 landlord land 7,180,018 7,180,018 -
14 Azam Jan Abdul Qayyum 1 landlord land 7,180,018 7,180,018 -
15 Azeem Jan Abdul Qayyum 1 landlord land 7,180,018 7,180,018 -
16 Haleem Jan Abdul Qayyum 1 landlord land 7,180,018 7,180,018 -
17 Liaqat Ali Abdul Qayyum 1 landlord land 7,180,018 7,180,018 -
18 Sharafat Bibi Abdul Qayyum 1 landlord land 3,590,009 3,590,009 -
19 Safia Bibi Abdul Qayyum 1 landlord land 3,590,009 3,590,009 -
20 Ashrfia Bibi Abdul Qayyum 1 landlord land 3,590,009 3,590,009 -
21 Rashid Khan Ijaz Ahmad 1 landlord land 9,866,501 9,866,501 -
22 Naveed Khan Ijaz Ahmad 1 landlord land 9,866,501 9,866,501 -
125
S. No Name of AP Father's Name Male Female Type of AP Type of
structure / Asset
Land Value (PKR)
Paid (PKR)
Unpaid
23 Fayaz Ahmad Abdul Rasheed 1 landlord land 13,468,558 13,468,558 -
24 Zahid Ullah Nasar Ullah Khan 1 landlord land 3,915,278 3,915,278 -
25 Faqeer Muhmmad Nasar Ullah Khan 1 landlord land 4,306,806 4,306,806 -
26 Jameela Muhmmad Idress 1 landlord land 538,351 538,351 -
27 Muhmmad Hasnat Muhmmad Idress 1 landlord land 1,076,701 1,076,701 -
28 Umer Farooq Muhmmad Idress 1 landlord land 1,076,701 1,076,701 -
29 Bibi Zuhra Muhmmad Idress 1 landlord land 538,351 538,351 -
30 Fuqraj Bibi Muhmmad Idress 1 landlord land 538,351 538,351 -
31 Zara Bibi Muhmmad Idress 1 landlord land 538,351 538,351 -
32 Raj Wali Habib Ullah 1 landlord land 1,076,701 1,076,701 -
33 Aarash Habib Ullah 1 landlord land 538,351 538,351 -
34 Fazeelat Habib Ullah 1 landlord land 538,351 538,351 -
35 Fatima Habib Ullah 1 landlord land 538,351 538,351 -
36 Musrrat Habib Ullah 1 landlord land 538,351 538,351 -
37 Shakeela Bibi Habib Ullah 1 landlord land 538,351 538,351 -
38 Shoukat Bibi Habib Ullah 1 landlord land 538,351 538,351 -
39 Iftikhar Ullah Hafeez Ullah 1 landlord land 780,608 780,608 -
40 Muhmmad Zubir Hafeez Ullah 1 landlord land 780,608 780,608 -
41 Muhammad Mushtaq Hafeez Ullah 1 landlord land 780,608 780,608 -
42 Muhmmad Naseer Hafeez Ullah 1 landlord land 780,609 780,609 -
43 Azra Bibi Hafeez Ullah 1 landlord land 394,790 394,790 -
44 Gul Naz Hafeez Ullah 1 landlord land 394,790 394,790 -
45 Gul Naz widow of Sadat Khan 1 landlord land 704,757 704,757 -
46 Khan Gul Sadat Khan 1 landlord land 391,527 391,527 -
47 Muhmmad Ameen Sadat Khan 1 landlord land 391,527 391,527 -
48 Sameen Jan Sadat Khan 1 landlord land 391,527 391,527 -
126
S. No Name of AP Father's Name Male Female Type of AP Type of
structure / Asset
Land Value (PKR)
Paid (PKR)
Unpaid
49 Muhmmad Ibrhiam Sadat Khan 1 landlord land 391,527 391,527 -
50 Muhmmad Nadeem Sadat Khan 1 landlord land 391,527 391,527 -
51 Naeem Jan Sadat Khan 1 landlord land 391,527 391,527 -
52 Sabiha Bibi Sadat Khan 1 landlord land 195,763 195,763 -
53 Rafia Bibi Sadat Khan 1 landlord land 195,763 195,763 -
54 Bashir Ahmad Husband of Nasim bibi 1 landlord land 2,075,098 2,075,098 -
55 Nadia Bashir Bashir Ahmad 1 landlord land 1,556,323 1,556,323 -
56 Rafiqa Bashir Bashir Ahmad 1 landlord land 1,556,323 1,556,323 -
57 Kursheed Ahmad Bashir Ahmad 1 landlord land 3,112,646 3,112,646 -
58 Hamza Jan Fazal Raheem 1 landlord land 518,774 518,774 -
59 Amin Khan Fazal Raheem 1 landlord land 518,774 518,774 -
60 Afsar Khan Fazal Raheem 1 landlord land 518,774 518,774 -
61 Masmat Gulfam Fazal Raheem 1 landlord land 259,387 259,387 -
62 Hameeda Bibi Fazal Raheem 1 landlord land 259,387 259,387 -
63 Naeem Jan Jinnat Gul 1 landlord land 1,479,035 1,479,035 -
64 Inam Ullah Jinnat Gul 1 landlord land 1,479,035 1,479,035 -
65 Falak Naz Jinnat Gul 1 landlord land 729,807 729,807 -
66 Muhmmad Abiad Usmani Muhmmad Idress Usmani 1 landlord land 1,879,334 1,879,334 -
67 Muhmmad Amir Usmani Muhmmad Idress 1 landlord land 1,879,334 1,879,334 -
68 Khalil Ahmad Usmani Muhammad Idress Usmani 1 landlord land 1,879,334 1,879,334 -
69 Muhmmad Abubakar Muhmmad Idress Usmani 1 landlord land 2,192,556 2,192,556 -
70 Muhammad Ikram Ghulam Sarwar 1 landlord land 2,075,098 2,075,098 -
71 Muhmmad Ashraf Ghulam Sarwar 1 landlord land 2,075,098 2,075,098 -
72 Mahfooz Ur Rehman Lahkar Khan 1 landlord land 7,157,443 7,157,443 -
73 Shehnaz Bibi Hafeez Ullah 1 landlord land 394,790 394,790 -
Total 44 29 1,095,181,686 1,095,181,686 -
127
1.2. Land Tenants Compensation – EBD Land (Vulnerable and Severely Affected Persons)
S. No Name of the
Agriculture Tenant Father Name
Vulnerability Allowance
Severely affected Allowance
Total Amount Date Paid Paid Unpaid
1 Muhammad Shafiq Abdul Majeed 45,000 90,000 135,000 15-03-18 135,000 -
2 Abdur Rashid Abdul Majeed 45,000 90,000 135,000 10-04-18 135,000 -
3 Muhammad Hanif (Munif)
Hanif 45,000 90,000 135,000 15-03-18 135,000 -
4 Ahmad Khan Hanif 45000 90,000 135,000 10-04-18 135,000 -
5 Muhammad Saleem (Haji Salim)
Dost Muhammad 45,000 90,000 135,000 15-03-18 135,000 -
6 Qadir Khan Munif 45,000 90,000 135,000 15-03-18 135,000 -
7 Azam Abdul Qayyum 45,000 90,000 135,000 15-03-18 135,000 -
8 Liaqat Ali Abdul Qayyum 45,000 90,000 135,000 15-03-18 135,000 -
9 Muqeem Khan Muhammad Amin 45,000 90,000 135,000 15-03-18 135,000 -
10 Naeem Jan Muhammad Amin 45,000 90,000 135,000 15-03-18 135,000 -
Total 450,000 900,000 1,350,000 1,350,000 -
1.3. Crops Compensation EBD
S. No Name Father's Name / Husband Name
Crops
Payable Date Paid Paid Unpaid
1 Asma Alamgir (O) Arbab Alamgir Khan 233,236 233,236
2 Mahfooz ur Rehman Lahkar Khan 27,211 11-04-18 27,211 0
3 Anees ur Rehman/ Shams Ur Rehman Habib Ur Rehman 42,760 25-09-18 42,760 0
4 Anees ur Rehman/ Shams Ur Rehman 34,985 25-09-18 34,985 0
5 Muhammad Shafeeq (T) Abdul Majeed 116,618 10-04-18 116,618 0
6 Abdur Rashid Abdul Majeed 116,618 10-04-18 116,618 0
7 Muhammad Hanif (Munif) Abdul Hanif 42,760 10-04-18 42,760 0
8 Azam Abdul Qayum 34,985 10-04-18 34,985 0
9 Liaqat Ali Abdul Qayum 27,211 10-04-18 27,211 0
10 Muqeem Khan Muhammad Amin 15,549 10-04-18 15,549 0
11 Naeem Jan Muhammad Amin 34,985 10-04-18 34,985 0
128
S. No Name Father's Name / Husband Name
Crops
Payable Date Paid Paid Unpaid
12 Karim khan Muhammad Amin 27,211 22-07-20 27,211 0
Total 754,129 520,893 233,236
1.4. Affected Trees EBD (Trees Compensation)
S.# Name Father's Name / Husband Name
Compensation Amount PKR Non Fruit Trees Fruit Trees Total
Payable Paid Unpaid Payable Paid Unpaid Total
Payable Paid Unpaid
1 Sajjad Khan (Paid To Syed Ibrar Ul Haq)
1,361 1,361 0 0
0 1,361 1,361 -
2 Asma Alamgir Arbab Alamgir Khan 5,761 5,761 0 5,761 0 5,761
3 Mahfooz ur Rehman Lahkar Khan 9,084 9,084 0 0 9,084 9,084 - 4 Muhmmad Fazeel Haji Khan 40,009 40,009 0 988,260 988,260 0 1,028,269 1,028,269 - 5 Muhammad Jabbir Haji Khan 37,209 37,209 0 919,081 919,081 0 956,290 956,290 -
6 Muhammad Naveed Khan
Haji Khan 2,800 2,800 0 69,178 69,178 0 71,978 71,978 -
7 Fayaz Khan 46,936 46,936 0 0 46,936 46,936 -
8 Anees ur Rehman/ Shams Ur Rehman
Habib Ur Rehman 50,881 50,881
0 1,346,640 1,346,640 0 1,397,521 1,397,521
9 Rashid Khan Ijaz Ahmed 16,891 16,891 0 0 16,891 16,891 - 10 Faqir Muhammad Nasar Ullah Khan 47,723 47,723 0 401,820 401,820 0 449,543 449,543 - 11 Khadam Hussain Abdul Qayum 0 108,600 108,600 0 108,600 108,600 - 12 Azam Abdul Qayum 0 108,600 108,600 0 108,600 108,600 - 13 Azeem Jan Abdul Qayum 0 108,600 108,600 0 108,600 108,600 - 14 Haleem Jan Abdul Qayum 0 108,600 108,600 0 108,600 108,600 - 15 Liaqat Ali Abdul Qayum 0 108,600 108,600 0 108,600 108,600 - 16 Sharafat Bibi Abdul Qayum 0 54,300 54,300 0 54,300 54,300 - 17 Safia Bibi Abdul Qayum 0 54,300 54,300 0 54,300 54,300 - 18 Ashrafia Abdul Qayum 0 54,300 54,300 0 54,300 54,300 - 19 Khan Gul Ghulam Sadat 2,577 2,577 0 17,065 17,065 0 19,642 19,642 - 20 Muhammad Ameen Ghulam Sadat 2,577 2,577 0 17,065 17,065 0 19,642 19,642 - 21 Sameen Jan Ghulam Sadat 2,577 2,577 0 17,065 17,065 0 19,642 19,642 - 22 Muhammad Ibrahim Ghulam Sadat 2,577 2,577 0 17,065 17,065 0 19,642 19,642 -
129
23 Muhammad Nadeem Ghulam Sadat 2,577 2,577 0 17,065 17,065 0 19,642 19,642 - 24 Naeem Jan Ghulam Sadat 2,577 2,577 0 17,065 17,065 0 19,642 19,642 - 25 Sabiha Begum Ghulam Sadat 1,290 1,290 0 8,535 8,535 0 9,825 9,825 - 26 Rafia Ghulam Sadat 1,290 1,290 0 8,535 8,535 0 9,825 9,825 -
Total 276,697 270,936 5,761 4,550,339 4,550,339 0 4,827,036 4,821,275 5,761
130
2. Reach 1 LARP
2.1. Payment of Structure – At Zia Market
S.# Name of
AP Father’s
Name Type of
AP
Type of structure /
Asset
Shifting Allowance
Structure Cost Cost of Total
Structure
Housing Relocation Allowance
Total cost Date Paid Paid Cost of two
houses
Cost of two
Quarters
Cost of 9 shops & 2 Garages
1 Zahid Ullah
Nasar Ullah Khan
landlord
land, 2 houses, 2 quarters & (9 shops+ 1 workshop +2 garages)
In "House Renters/ Owner "
9,247,200 4,852,350 1,666,350 15,765,990 In "House Renters/ Owner "
15,765,900 23-02-18 15,765,900
2.2. Land Compensation Access Ramp at Zia Market - Reach 1
S No Name of AP Father's Name CNIC
Commercial Land Details CAS 15%
Total cost
Paid Unpaid Area
Unit Rate / Marla
Cost
1 Zahid Ullah Nasar Ullah Khan 17301-1394021-3 5 Marla 274,782.60 1,373,913 206,087 1,580,000 1,580,000 -
As per Addendum 1 to Reach 1 878,668 4,393,340 659,001 5,052,341
131
2.3. Zia Market Shopkeepers
S. No Name of AP Father's Name Male Shifting
Allowance Income
Allowance Total cost Date Paid Paid Unpaid
1 Zahid ullah Muheeb ullah 1 10,000 450,000 460,000 23-02-18 460,000 -
2 Shakeel Ahmad Ibrahim 1 10,000 450,000 460,000 23-02-18 460,000 -
3 Muhammad Shakeel Ahmad
Ghulam Farid 1 10,000 450,000 460,000 23-02-18 460,000 -
4 Quraish Khan Marifat Shah 1 10,000 450,000 460,000 23-02-18 460,000 -
5 Rahatullah Muheeb ullah 1 10,000 450,000 460,000 23-02-18 460,000 -
6 Iftikhar Gul Rehman 1 10,000 450,000 460,000 23-02-18 460,000 -
7 Syed Atta ur Rehman Shah
Syed Usman Shah 1 10,000 450,000 460,000 23-02-18 460,000 -
8 Muhammad Ibrahim Sher Dil Khan 1 10,000 450,000 460,000 23-02-18 460,000 -
9 Imdad ullah Inayatullah 1 10,000 450,000 460,000 23-02-18 460,000 -
Total 90,000 4,050,000 4,140,000 4,140,000 -
2.4. Zia Market Employees
S.# Name of AP Father's Name Name of Shopkeeper
Status Income Allowance
Vulnerability Allowance
Total cost
Date Paid
Paid Unpaid
1 Waqas Ullah Ashraf Khan Shakeel Ahmad 30,000 45,000 75,000 23-02-18 75,000
2 Saqib Shakeel Ahmad Under 18 30,000 45,000 75,000 75,000
3 Wajid Muhammad Saleem
Quresh Khan 30,000 45,000 75,000 12-03-18 75,000
4 Imad Muhammad Taj Muhammad Iftikhar Khan 30,000 45,000 75,000 23-02-18 75,000
5 Fida Muhammad Faqir Muhammad Zahidullah 30,000 45,000 75,000 23-02-18 75,000
6 Ahsanullah Gul Shah Zahidullah 30,000 45,000 75,000 28-02-18 75,000
7 Jalal Khan Gul Muhammad Zahidullah 30,000 45,000 75,000 11-04-18 75,000
8 Sheraz Khan Qayyur Khan Syed Atta ur Rehman
30,000 45,000 75,000 23-02-18 75,000
9 Rizwan Hussain Aashiq Hussain M. Ibrahim 30,000 45,000 75,000 23-02-18 75,000
10 Mobeen Khan Jan Muhammad M. Ibrahim 30,000 45,000 75,000 12-02-19 75,000
11 Shahbaz M. Ibrahim Under 18 30,000 45,000 75,000 75,000
12 Saqib Imdad Khan Under 18 30,000 45,000 75,000 75,000
13 Adnan Khan Quresh Khan Under 18 30,000 30,000 30,000
132
14 Aqib Khan Syed Atta ur Rehman
Under 18 30,000 30,000 30,000
15 Tehseenullah M Shafi Zahidullah 30,000 30,000 23-02-18 30,000
16 Muhammad Aamir
Sawab Gul Zahidullah 30,000 30,000 28-02-18 30,000
Total 480,000 540,000 1,020,000 735,000 285,000
2.5. Zia Market House Renters/owner
S. No Name of AP Father's Name Male Type of
AP
Type of structure /
Asset
Shifting Allowance
Housing Relocation Allowance
Total cost Date Paid Paid Unpaid
1 Ihsanullah Muhammad Sharif 1 Tenant Rented House 20,000 15,000 35,000 23-02-18 35,000 -
2 Sajid Khan Syed Akbar 1 Tenant Rented House 20,000 15,000 35,000 23-02-18 35,000 -
3 Muhammad Qasim Mir Muhammad 1 Tenant Rented House 20,000 30,000 50,000 23-02-18 50,000 -
4 Zahid Ullah Nasar Ullah Khan 1 Owner Own House 20,000 300,000 320,000 23-02-18 320,000 -
Total 60,000 360,000 440,000 440,000 -
2.6. Affected Structures Access Ramp - Reach 1 (at Sardar Garhi Filling Station)
S.No Name Father Name
Cost of Permanent Structures One Time Lumpsum
Total Date Paid Paid Unpaid 2 shops
and a service
deck (PKR)
02 shops and 01 room
Shed 01 latrine
(Bathroom)
01 Generator
Room
1 Petrol tank
1 Muzammil Khan
Fayyaz Ahmad
544,800 - - - - - 544,800 22-07-20 544,800
2 Anees ur Rehman
Habib ur Rehman
- 543,144 44,455 38,087 43,282 - 668,968 23-07-20 668,968
3 Attaullah Amanullah - - - - - 200,000 200,000 - 200,000
Total 544,800 543,144 44,455 38,087 43,282 200,000 1,413,768 1,213,768 200,000
133
2.7. Affected Prayer Place Reach 1
S. No. Name of AP Location Type of AP Type of
structure/Asset Shifting
Allowance Affected Prayer
Place Total cost Date Paid Paid Unpaid
1 Green Belt Masjid
Green Belt Masjid Haji Camp
Community Masjid - 2,574,606 2,574,606 22-05-18 2,574,606
2 Mosque near Chamkani Ada
Chamkani Adda/Bus Stop
Community Small Masjid 10,000 120,033 130,033 130,033
Total 10,000 2,694,639 2,704,639 2,574,606 130,033
2.8. Prayer Place APs
S. No. Name of AP Father's Name Location Type of AP Shifting
Allowance Income
Allowance Vulnerability
Allowance Total cost Date Paid PAID
1 Muhammad Zaman
Rehmat Ullah Green Belt Masjid Haji Camp
Imam Masjid
20,000 30,000 45,000 95,000 15-3-2018 95,000
Total 20,000 30,000 45,000 95,000 95,000
2.9. Affected Shop’s Hashtnagri decoration
S. No Name of AP Father's Name Type of
AP Shop #
Cost of decoration
loss
Cost of dismantling & re-fixing (lump
sum)
TOTAL Décor +
Dismantle
Paid Decoration
and dismantling
Unpaid Décor +
Dismantling
1 Muhammad Sajjad Sheikh Muhammad Riaz
Lessee / SK
6 280,000 120,000 400,000 400,000 -
2 Afsar Ali Ghairat Khan Lessee /
SK 8 480,000 180,000 660,000 660,000 -
3 Sohail Noor Haji Fazal Mehmood Lessee /
SK 21 100,000 60,000 160,000 160,000 -
134
4 Mosaif Gul Siraj ul Haq Lessee /
SK 22 280,000 80,000 360,000 360,000 -
5 Wajid Ali Nadeem Rahim Bakhsh Lessee /
SK L&SK 33
SK 34,38,39 - 60,000 60,000 60,000 -
6 Rahmat Khan Noor Zaa Ali Khan SK 31 - 25,000 25,000 25,000 -
7 Muhammad Tahir Shams ur Rehman SK 32 - 30,000 30,000 30,000 -
8 Hayatullah Shams ur Rehman SK 1 70,000 50,000 120,000 120,000 -
9 Shakirullah Shireen Khan SK 2 40,000 30,000 70,000 70,000 -
10 Amanullah Shireen Khan SK 3 40,000 20,000 60,000 60,000 -
11 Shahid Khan M Tahir SK 4 40,000 20,000 60,000 60,000 -
12 Sirajuddin Zahir Jan SK 5 60,000 30,000 90,000 90,000 -
13 Aman Khan Amanullah Khan SK 7 150,000 80,000 230,000 - 230,000
14 Amanullah Khan Nadir Khan SK 9 200,000 120,000 320,000 320,000 -
15 Kamran Burhan Ghairat Khan SK 10 180,000 150,000 330,000 330,000 -
16 Taj Wali Shireen Khan SK 11 70,000 30,000 100,000 100,000 -
17 Abdur Rahman Mukarram Khan SK 12 180,000 70,000 250,000 250,000 -
18 Baroz Khan Shah Mehmood SK 13 150,000 60,000 210,000 210,000 -
19 Sher Zaman Sohail Khan SK 14 200,000 100,000 300,000 300,000 -
20 Shahid Bilal M Khan SK 15 150,000 70,000 220,000 220,000 -
21 Mir Alam Gul Rehman SK 16 80,000 30,000 110,000 110,000 - 22 Atta ur Rehman Zahir Jan SK 17 70,000 30,000 100,000 100,000 -
23 Khair ur Rehman Shah Pur Khan SK 18 120,000 40,000 160,000 160,000 -
24 Waqas Nawaz Muhammad Nawaz SK 19 180,000 80,000 260,000 260,000 -
25 Zahid Ali Ghairat Khan SK 20 160,000 80,000 240,000 240,000 -
26 Lawang Khan Muhammad Afzal SK 23 180,000 80,000 260,000 260,000 -
27 Abid ullah M Hussain SK 24 - 40,000 40,000 40,000 -
28 Sohail Sher Zaman SK 25 - 25,000 25,000 25,000 -
29 Amna Karim Muhammad Naeem SK 35 90,000 90,000 90,000 -
30 Samiullah Zahir Jan SK 36,37 - - - - -
31 Jamal Din Ghulam Sarwar SK 43 - -
32 Asif Iqbal Muhammad Naeem SK 40 - -
33 Yar Syed Shah Syed SK 41 - 15,000 15,000 15,000 -
34 Shaukat Ali Ghulam Sarwar SK 42 - -
35 Saleem Khan Gul Khan SK The Kiosk, not mentioned in
the map 20,000 50,000 70,000 70,000 -
Total 3,480,000 1,945,000 5,425,000 5,195,000 230,000
135
2.10. Affected Shops of Firdous Decoration
S. No Name of AP Father's Name Type of AP Shop # Cost of
decoration loss
Cost of dismantling &
re-fixing (lump sum)
Total Cost Payable
Paid Decoration
and dismantling
Unpaid Decoration
Cost
1 Hanifa (widow ) Khanzadin (late) Husband
Lessee 1 550,000 100,000 650,000 650,000 -
2 Lawang Khan Muhammad Afzal Lessee / SK Le 10 and Le +SK #
2 600,000 200,000 800,000 800,000 -
3 Hidayat ur Rehman Muhammad Aman Lessee / SK Le 29, Le/SK 14, 15,
SK 40 & 41 - 1,950,000 1,950,000 1,950,000 -
4 Mir Salam Akber Khan Lessee / SK Le # 18 and SK A2 - - - - -
5 Habib Noor Haya Noor Lessee / SK Le # 28 and SK 22 - 150,000 150,000 150,000 -
6 Saifoor Khan Gujar Khan SK A1 - 40,000 40,000 40,000 -
7 Wajid Ali Nadeem Rahim Bakhsh SK 6 300,000 120,000 420,000 420,000 -
8 Muhammad Dawood Manjawer SK 23 - 200,000 200,000 200,000 -
9 Shaikh Muhammad Jawad Riaz
Sheikh Muhammad Riaz
SK 26 100,000 150,000 250,000 250,000 -
10 Abdul Ghani Gujar Khan SK 32 300,000 150,000 450,000 450,000 -
11 Salahuddin Gul Zareen SK 1 - - - - -
12 Sultan Muhammad Sohail Khan SK 3 60,000 60,000 120,000 120,000 -
13 Ziarat Gul Hazrat Mohmand SK 4 500,000 250,000 750,000 750,000 -
14 Rooh Ullah Sanubar Khan SK 5 300,000 80,000 380,000 380,000 -
15 Zair Ullah Sanober Khan SK 7 500,000 200,000 700,000 700,000 -
16 Hameed ur Rehman Zaheer Ullah Khan SK 8 300,000 150,000 450,000 450,000 -
17 Islam Gul Bakht Mir SK 9 25,000 - 25,000 25,000 -
18 Muhammad Yousaf Allah Jan SK 10 600,000 280,000 880,000 880,000 -
19 Muhammad Yaseen Arzmeen Khan SK 11 60,000 30,000 90,000 90,000 -
20 Nisar Muhammad Sher Zaman SK 12 80,000 40,000 120,000 - 120,000
21 Zahidullah Gula Khan SK 13 200,000 200,000 400,000 400,000 -
22 Saleem Khan Bakht Meer SK 16 - 100,000 100,000 100,000 -
23 Ghulam Nabi SK décor A2 - 60,000 60,000 60,000 -
24 Shah Muhammad Tor Shah SK 17 - 80,000 80,000 80,000 -
25 Muhammadullah Nadir Khan SK 18 - 250,000 250,000 250,000 -
26 Laali Gul Abdullah SK 19 - 50,000 50,000 50,000 -
27 Nazir Jan SK 20 - 150,000 150,000 - 150,000
28 Ibrahim Khan Noor SK 21 - 150,000 150,000 150,000 -
136
29 Zabit Khan Sanober Khan SK 24 200,000 100,000 300,000 300,000 -
30 Perveiz Khan Yar Jan SK 25 - 150,000 150,000 150,000 -
31 Sami Ullah Ghulam Nabi SK 27 80,000 70,000 150,000 150,000 -
32 Waheed Khan Ghulam Nabi SK 28 120,000 60,000 180,000 180,000 -
33 Zahir Shah Shahzad Khan SK 29 500,000 300,000 800,000 800,000 -
34 Majid Zaheen Rahim Baksh SK 30 - 60,000 60,000 60,000 -
35 Gul Sher Akhter Said SK 31 300,000 120,000 420,000 420,000 -
36 Jalil Khan Bakht Mir SK 33 - 180,000 180,000 180,000 -
37 Rukhsana Bibi Kifayatullah (Husband)
SK 37 - - - - -
38 Rukhsana Bibi Kifayatullah (Husband)
SK 36 - - - - -
39 Shah Zamin Khan Sadbar SK 35 - - - - -
40 Jamshaid Habib Ur Rehman SK 34 - - - - -
41 Mushtaq Masih Malik Masih SK 43 - - - - -
42 Rukhsana Bibi Kifayatullah (Husband)
SK 39 - 60,000 60,000 60,000 -
43 Rukhsana Bibi Kifayatullah (Husband)
SK 38 - 200,000 200,000 200,000 -
44 Khurram Masih Rafiq SK 44 - - - - -
45 Abdul Quim Akhter Said SK Kiosk - 280,000 280,000 280,000 -
46 Aqal Bacha Akhter Syed SK Kiosk - 250,000 250,000 250,000 - Total 5,675,000 7,020,000 12,695,000 12,425,000 270,000
2.11. Vendors (of all the three Reaches 1, 2 & 3)
S. No
Name of AP Father's Name Male Location Shifting
Allowance Income
Allowance Vulnerability
Allowance Total cost
Paid Unpaid
1 Shair Wali Khan Laal Gul 1 Reach 1 5,000 90,000 45,000 140,000 140,000 -
2 Khushal (AFGHAN)
Dilawer 1 Reach 1 5,000 90,000 45,000 140,000 - 140,000
3 Nazir (AFGHAN)
Masal 1 Reach 1 5,000 90,000 45,000 140,000 - 140,000
4 Zubair Momin Khan 1 Reach 1 5,000 90,000 45,000 140,000 140,000 -
5 Muhammad Bilal
Niaz Muhammad 1 Reach 1 5,000 90,000 45,000 140,000 140,000 -
6 Usman Ghuffran Khan 1 Reach 1 5,000 90,000 45,000 140,000 140,000 -
137
7 Irshad Khan Khaista Muhammad
1 Reach 1 5,000 90,000 45,000 140,000 140,000 -
8 Irshad Khan Muhammad 1 Reach 1 5,000 90,000 45,000 140,000 140,000 -
9 Jamil-ur-Rehman
Zaheer 1 Reach 1 5,000 90,000 45,000 140,000 140,000 -
10 Darwesh Sher Muhammad 1 Reach 1 5,000 90,000 45,000 140,000 140,000 -
11 Bakhtawar Muhammad 1 Reach 1 5,000 90,000 45,000 140,000 140,000 -
12 Sher Zaman M Zaman 1 Reach 1 5,000 90,000 45,000 140,000 140,000 -
13 Farman-Ullah Yar Said 1 Reach 1 5,000 90,000 45,000 140,000 140,000 -
14 Jamdali Khan Ziarat Gul 1 Reach 1 5,000 90,000 45,000 140,000 140,000 -
15 Hussain Khan Zaa Noor Shah 1 Reach 1 5,000 90,000 45,000 140,000 140,000 -
16 Abdur Raqeeb Gul Zali 1 Reach 1 5,000 90,000 45,000 140,000 140,000 -
17 Fazal ur Rehman
Gul Rehman 1 Reach 1 5,000 90,000 45,000 140,000 140,000 -
18 M Arif Fazal Khan 1 Reach 1 5,000 90,000 45,000 140,000 140,000 -
19 Imran Ghazi Rehman 1 Reach 1 5,000 90,000 45,000 140,000 140,000 -
20 Tashbeeh Ullah Muhammad Jan 1 Reach 1 5,000 90,000 45,000 140,000 140,000 -
21 Sabir Jan Muhammad Din 1 Reach 1 5,000 90,000 45,000 140,000 140,000 -
22 Nawaz ud Din Sultan 1 Reach 1 5,000 90,000 45,000 140,000 140,000 -
23 Muzaffar Khan Mashhoor Khan 1 Reach 1 5,000 90,000 45,000 140,000 140,000 -
24 Abdul Samad Ghulam Habib 1 Reach 1 5,000 90,000 45,000 140,000 140,000 -
25 Sohail Khan Abdur Rauf 1 Reach 1 5,000 90,000 45,000 140,000 140,000 -
26 Tilawat Daud Shah 1 Reach 1 5,000 90,000 45,000 140,000 140,000 -
27 Sami Ullah Lali Gul 1 Reach 1 5,000 90,000 45,000 140,000 140,000 -
28 Usman Khan Gulab Sher 1 Reach 1 5,000 90,000 45,000 140,000 140,000 -
29 Jangi Badsha Naseem Shah 1 Reach 1 5,000 90,000 45,000 140,000 140,000 -
30 Laal Zada Shahzada 1 Reach 1 5,000 90,000 45,000 140,000 140,000 -
31 Usman Khan Abdullah Khan 1 Reach 1 5,000 90,000 45,000 140,000 140,000 -
32 Ayaz Khan Ali Khan 1 Reach 1 5,000 90,000 45,000 140,000 140,000 -
33 Zia ul Islam M Idrees 1 Reach 1 5,000 90,000 45,000 140,000 140,000 -
34 Mukamil Khan Hamidullah Khan 1 Reach 1 5,000 90,000 45,000 140,000 140,000 -
35 Abdul Ahad (AFGHAN)
Khair Muhammad 1 Reach 1 5,000 90,000 45,000 140,000 - 140,000
36 Suleiman Zar Khan 1 Reach 1 5,000 90,000 45,000 140,000 140,000 -
37 Irshad Akber Khan 1 Reach 2 5,000 90,000 45,000 140,000 140,000 -
38 Akber Khan Tor Lali 1 Reach 2 5,000 90,000 45,000 140,000 140,000 -
138
39 Rab Damal Shah
Munir 1 Reach 2 5,000 90,000 45,000 140,000 140,000 -
40 Naimat Khan Badshah Said 1 Reach 2 5,000 90,000 45,000 140,000 140,000 -
41 Humza Badshah Syed 1 Reach 2 5,000 90,000 45,000 140,000 140,000 -
42 Anar Gul Freman 1 Reach 2 5,000 90,000 45,000 140,000 140,000 -
43 Gulzar Lal Bakht 1 Reach 2 5,000 90,000 45,000 140,000 140,000 -
44 Munir (Bunair) Munasib Khan 1 Reach 2 5,000 90,000 45,000 140,000 140,000 -
45 Zameen Gul Zameer Khan 1 Reach 2 5,000 90,000 45,000 140,000 140,000 -
46 Zaman Khan Gul Azeem Khan 1 Reach 2 5,000 90,000 45,000 140,000 140,000 -
47 Umar Abdul Hamid Khan
1 Reach 2 5,000 90,000 45,000 140,000 140,000 -
48 Riaz Ullah Muhammad Siraj 1 Reach 2 5,000 90,000 45,000 140,000 140,000 -
49 Ihsan Wali Khair Jan 1 Reach 2 5,000 90,000 45,000 140,000 140,000 -
50 Shahid Hussain Abdul Latif 1 Reach 2 5,000 90,000 45,000 140,000 140,000 -
51 Saif ur Rehman Abdul Haq 1 Reach 3 5,000 90,000 45,000 140,000 140,000 -
52 Rehmatullah Abdul Haq 1 Reach 3 5,000 90,000 45,000 140,000 140,000 -
53 Abdul Latif Rehmat Jan 1 Reach 3 5,000 90,000 45,000 140,000 140,000 -
54 Abdul Haq Haji Sultan 1 Reach 3 5,000 90,000 45,000 140,000 140,000 -
55 Gullab Gul Gul 1 Reach 3 5,000 90,000 45,000 140,000 140,000 -
56 Fayyaz Khan Shad Muhammad 1 Reach 3 5,000 90,000 45,000 140,000 140,000 -
57 Samiullah Ihsanullah 1 Reach 3 5,000 90,000 45,000 140,000 140,000 -
58 Rizwanullah Noor Rahim 1 DG R-2 5,000 90,000 45,000 140,000 140,000 -
59 Salim Shah Kiramat Shah 1 DG R-2 5,000 90,000 45,000 140,000 140,000 -
60 Fahimullah M Younis 1 DG R-2 5,000 90,000 45,000 140,000 140,000 -
61 Sar Tor Khan Syed Ahmad Khan
1 DG R-2 5,000 90,000 45,000 140,000 140,000 -
Total 61 305,000 5,490,000 2,745,000 8,540,000 8,120,000 420,000
2.12. Hashtnagri Lessees (Monthly)
S. No
Name of AP Father's Name M F Type of
AP Type of structure /
Asset Payable per
month
Total Payable 18 Months & 22
Days
Total Paid
Unpaid
1 Mirza Khan (MCC) Gul Muhammad 1 Lessee
31,32,1,3,4,5,9,15,17,18,19,23,25, 34,35,36,37, 38,39,40,41,42,43
25,000 x 23 10,758,065 10,758,065 -
139
2 Ayub Shah Haji Syed ur Rehman
1 Lessee Shop # 2 25,000 467,742 467,742 -
3 Rehman Gul Sher Ali 1 Lessee Shop # 7 25,000 467,742 317,742 150,000
4 Nasir Khan (Abdul Wahid late)
1 Lessee Shop # 10 25,000 467,742 467,742 -
5 Atta ur Rehman Kalim ur Rehman 1 Lessee Shop # 11 25,000 467,742 342,742 125,000
6 Sohail Shehzad Syed Noor Badshah 1 Lessee Shop # 12 25,000 467,742 467,742 -
7 Hilal Shehzad Syed Noor Badshah 1 Lessee Shop # 13 25,000 467,742 467,742 -
8 Yasir Khan Mian Gul 1 Lessee Shop # 14 25,000 467,742 467,742 -
9 Nadir Khan(Ayub Shah payable Addendum)
Abdul Wahid 1 Lessee Shop # 16 25,000 467,742 292,742 175,000
10 Abdullah Khan Amanullah Khan 1 Lessee Shop # 20 25,000 467,742 467,742 -
11 Farzand Ali Waris Khan 1 Lessee Shop # 26, 28 25000 x 2 935,484 635,484 300,000
12 Muhammad Ali Gul Muhammad 1 Lessee Shop # 27 25,000 467,742 317,742 150,000
13 Shakoor Ahmad Muhammad Nazir 1 Lessee Shop # 30 25,000 467,742 317,742 150,000
14 Ashfaq Ahmad Malik Amir Zada 1 Lessee Shop # 29 25,000 467,742 367,742 100,000
15 Ghayour Ahmad Muhammad Nazir 1 Lessee Shop # 44 25,000 467,742 - 467,742
16 Adnan Ahmad Muhammad Nazir 1 Lessee Kiosk 25,000 467,742 342,742 125,000
16 39 18,241,937 16,499,195 1,742,742
2.13. Hashtnagri shopkeeper Income loss (Monthly)
S.No Name of AP Father's Name M F Type of AP L=lessee
SK=shopkeepr
Type of structure /
Asset
Payable per month
Total Payable 18 Months &
22 Days
Total Paid
Unpaid
1 Muhammad Sajjad Sheikh Muhammad Riaz
1 L/ SK Shop # 6 75,000 1,403,226 1,403,226 -
2 Afsar Ali Ghairat Khan 1 L / SK Shop # 8 75,000 1,403,226 1,403,226 -
3 Sohail Noor Haji Fazal Mehmood 1 L/ SK Shop # 21 75,000 1,403,226 1,403,226 -
4 Mosaif Gul Siraj ul Haq 1 L / SK Shop # 22 75,000 1,403,226 1,403,226 -
5 Wajid Ali Nadeem Rahim Bakhsh 1 L/ SK Lease & SK 33
SK 34,38,39 300,000 5,612,903 5,612,903 -
6 Rahmat Khan Noor Zaa Ali Khan 1 SK Shop # 31 75,000 1,403,226 1,403,226 -
7 Muhammad Tahir Shams ur Rehman 1 SK Shop # 32 75,000 1,403,226 1,403,226 -
8 Hayatullah Shams ur Rehman 1 SK Shop # 1 75,000 1,403,226 1,403,226 -
9 Shakirullah Shireen Khan 1 SK Shop # 2 75,000 1,403,226 1,403,226 -
10 Amanullah Shireen Khan 1 SK Shop # 3 75,000 1,403,226 1,403,226 -
140
11 Shahid Khan M Tahir 1 SK Shop # 4 75,000 1,403,226 1,403,226 -
12 Sirajuddin Zahir Jan 1 SK Shop # 5 75,000 1,403,226 1,403,226 -
13 Aman Khan Amanullah Khan 1 SK Shop # 7 75,000 1,403,226 75,000 1,328,226
14 Amanullah Khan Nadir Khan 1 SK Shop # 9 75,000 1,403,226 1,403,226 -
15 Kamran Burhan Ghairat Khan 1 SK Shop # 10 75,000 1,403,226 1,403,226 -
16 Taj Wali Shireen Khan 1 SK Shop # 11 75,000 1,403,226 1,403,226 -
17 Abdur Rahman Mukarram Khan 1 SK Shop # 12 75,000 1,403,226 1,403,226 -
18 Baroz Khan Shah Mehmood 1 SK Shop # 13 75,000 1,403,226 1,403,226 -
19 Sher Zaman Sohail Khan 1 SK Shop # 14 75,000 900,000 900,000 -
20 Shahid Bilal M Khan 1 SK Shop # 15 75,000 1,403,226 1,403,226 -
21 Mir Alam Gul Rehman 1 SK Shop # 16 75,000 1,403,226 1,403,226 -
22 Atta ur Rehman Zahir Jan 1 SK Shop # 17 75,000 1,403,226 1,403,226 -
23 Khair ur Rehman Shah Pur Khan 1 SK Shop # 18 75,000 1,403,226 1,403,226 -
24 Waqas Nawaz Muhammad Nawaz 1 SK Shop # 19 75,000 1,403,226 1,403,226 -
25 Zahid Ali Ghairat Khan 1 SK Shop # 20 75,000 1,403,226 1,403,226 -
26 Lawang Khan Muhammad Afzal 1 SK Shop # 23 75,000 1,403,226 1,403,226 -
27 Abid ullah M Hussain 1 L / SK Shop # 24 75,000 1,403,226 1,403,226 -
28 Sohail Sher Zaman 1 SK Shop # 25 75,000 1,403,226 1,403,226 -
29 Amna Karim w/o Muhammad Naeem
1 SK shop # 35 75,000 1,403,226 1,403,226 -
30 Samiullah Zahir Jan 1 SK Shop 36 & 37 150,000 2,806,452 2,806,452 -
31 Jamal Din Ghulam Sarwar 1 SK Shop # 43 75,000 1,403,226 1,028,226 375,000
32 Asif Iqbal Muhammad Naeem 1 SK Shop # 40 75,000 1,403,226 1,403,226 -
33 Yar Syed Shah Syed 1 SK Shop # 41 75,000 1,403,226 1,403,226 -
34 Shaukat Ali Ghulam Sarwar 1 SK Shop # 42 75,000 1,403,226 1,403,226 -
35 Saleem Khan Gul Khan 1 SK The Kiosk, not mentioned in
the map 75,000 1,403,226 1,403,226 -
Total 34 1 39 54,222,587 52,519,361 1,703,226
141
2.14. Hashtnagri Shifting Allowance shopkeeper
S. No Name of AP Father's Name Type of AP Shop # Shifting Allowance Shifting Paid Unpaid Shifting 1 Muhammad Sajjad Sheikh Muhammad Riaz Le / SK 6 30,000 30,000 -
2 Afsar Ali Ghairat Khan Le / SK 8 30,000 30,000 -
3 Sohail Noor Haji Fazal Mehmood Le / SK 21 30,000 30,000 -
4 Mosaif Gul Siraj ul Haq Le / SK 22 30,000 30,000 -
5 Wajid Ali Nadeem Rahim Bakhsh Le / SK Le 33 SK 34,38,39
120,000 120,000 -
6 Rahmat Khan Noor Zaa Ali Khan SK 31 30,000 30,000 -
7 Muhammad Tahir Shams ur Rehman SK 32 30,000 30,000 -
8 Hayatullah Shams ur Rehman SK 1 30,000 30,000 -
9 Shakirullah Shireen Khan SK 2 30,000 30,000 -
10 Amanullah Shireen Khan SK 3 30,000 30,000 -
11 Shahid Khan M Tahir SK 4 30,000 30,000 -
12 Sirajuddin Zahir Jan SK 5 30,000 30,000 -
13 Aman Khan Amanullah Khan SK 7 30,000 30,000 -
14 Amanullah Khan Nadir Khan SK 9 30,000 30,000 -
15 Kamran Burhan Ghairat Khan SK 10 30,000 30,000 -
16 Taj Wali Shireen Khan SK 11 30,000 30,000 -
17 Abdur Rahman Mukarram Khan SK 12 30,000 30,000 -
18 Baroz Khan Shah Mehmood SK 13 30,000 30,000 -
19 Sher Zaman Sohail Khan SK 14 30,000 30,000 -
20 Shahid Bilal M Khan SK 15 30,000 30,000 -
21 Mir Alam Gul Rehman SK 16 30,000 30,000 -
22 Atta ur Rehman Zahir Jan SK 17 30,000 30,000 -
23 Khair ur Rehman Shah Pur Khan SK 18 30,000 30,000 -
24 Waqas Nawaz Muhammad Nawaz SK 19 30,000 30,000 -
25 Zahid Ali Ghairat Khan SK 20 30,000 30,000 -
26 Lawang Khan Muhammad Afzal SK 23 30,000 30,000 -
27 Abid ullah M Hussain SK 24 30,001 30,001 -
28 Sohail Sher Zaman SK 25 30,000 30,000 -
29 Amna Karim Muhammad Naeem SK 35 30,000 30,000 -
30 Samiullah Zahir Jan SK 36,37 60,000 60,000 -
31 Jamal Din Ghulam Sarwar SK 43 30,000 30,000 -
32 Asif Iqbal Muhammad Naeem SK 40 30,000 30,000 -
33 Yar Syed (Muhammad Saleem)
Shah Syed SK 41 30,000 30,000 -
142
34 Shaukat Ali Ghulam Sarwar SK 42 30,000 30,000 -
35 Saleem Khan Gul Khan SK kiosk 30,000 30,000 -
1,170,001 1,170,001 -
2.15. Hashtnagri Employees Compensation
S.No. Name of AP Father's Name M F Status Income
Allowance Vulnerability
Allowance Total cost Date Paid PAID UNPAID
1 Asfandyar Jehanzeb 1 U-18 years 30,000 45,000 75,000 12-03-18 75,000 -
2 Umair Shamshad 1 U-18 years 30,000 45,000 75,000 75,000
3 Bashir Rehmatullah 1 U-18 years 30,000 45,000 75,000 75,000
4 Fazal Haleem Fazal Karim 1 30,000 45,000 75,000 14-02-18 75,000 -
5 Sohaid Rahat Saleh Muhammad 1 U-18 years 30,000 45,000 75,000 75,000
6 Hamad Ali Sajjad Ali 1 30,000 45,000 75,000 14-02-18 75,000 -
7 Jahangir Khan Nadir Khan 1 U-18 years 30,000 45,000 75,000 12-03-18 75,000 -
8 Muhammad Ismail Bacha Gul 1 30,000 45,000 75,000 14-02-18 75,000 -
9 Zia ur Rehman Khana Gul 1 30,000 45,000 75,000 14-02-18 75,000 -
10 Ali Haider Safdar Khan 1 30,000 45,000 75,000 14-02-18 75,000 -
11 Salah ud Din Safdar Khan 1 U-18 years 30,000 45,000 75,000 15-07-19 75,000 -
12 Muhammad Ahsan Jamil Ahmad 1 30,000 45,000 75,000 14-02-18 75,000 -
13 Yasir Bakhtiar Bakhtiar ud Din 1 30,000 45,000 75,000 14-02-18 75,000 -
14 Bakht Taj Daud Khan 1 U-18 years 30,000 45,000 75,000 10-10-18 75,000 -
15 Imran Said 1 30,000 45,000 75,000 14-02-18 75,000 -
16 Ma’az Azeem Gul 1 30,000 45,000 75,000 14-02-18 75,000 -
17 Muhammad Basit Tariq Aziz 1 U-18 years 30,000 45,000 75,000 75,000
18 Irfanullah Qureshi Syed Ali Shah Qureshi
1 30,000 45,000 75,000 14-02-18 75,000 -
19 Muhammad Salman
Ghani Gul 1 30,000 45,000 75,000 14-02-18 75,000 -
143
20 Zubair Abdul Hakeem 1 U-18 years 30,000 45,000 75,000 75,000
21 Asadullah Abdur Rehman 1 U-18 years 30,000 45,000 75,000 03-07-19 75,000 -
22 Rehmatullah Shah Mehmood 1 30,000 45,000 75,000 14-02-18 75,000 -
23 Zakia Minhas Younas Khan (late husband)
1 30,000 45,000 75,000 15-02-18 75,000 -
24 Uamir Jan Noor Muhammad Khan
1 30,000 45,000 75,000 75,000
25 Alif Khan Pervaiz 1 30,000 45,000 75,000 14-02-18 75,000 -
26 Muhammad Yar Khan
Ameer Ullah Khan 1 30,000 45,000 75,000 13-03-18 75,000 -
27 Suleiman Khan Sartaj 1 30,000 45,000 75,000 14-02-18 75,000 -
28 Asif Ali Hassan Muhammad 1 30,000 45,000 75,000 15-02-18 75,000 -
29 Ghulam Farid Muhammad Sharif 1 30,000 45,000 75,000 15-02-18 75,000 -
30 Nazirullah Mehmood Khan 1 30,000 45,000 75,000 15-02-18 75,000 -
31 Munir (Latrines) Mehand 1 30,000 45,000 75,000 15-02-18 75,000 -
32 Ishfaq Riaz Sardar Maseeh 1 30,000 45,000 75,000 15-02-18 75,000 -
33 Riaz Maseeh Sardar Maseeh 1 30,000 45,000 75,000 15-02-18 75,000 -
34 Younis Maseeh Murad Maseeh 1 30,000 45,000 75,000 15-02-18 75,000 -
35 Shafiq Maseeh Barkat Maseeh 1 30,000 45,000 75,000 15-02-18 75,000 -
36 Ubaid Ullah Gul Khan 1 30,000 45,000 75,000 13-03-18 75,000 -
37 Perveiz Jan Ali Khan 1 30,000 45,000 75,000 12-03-18 75,000 -
38 Ikramullah Zahir Jan 1 30,000 30,000 15-02-18 30,000 -
39 Siraj Khan Ghairat Khan 1 30,000 30,000 15-02-18 30,000 -
40 Sherullah Sohail Khan 1 30,000 30,000 15-02-18 30,000 -
41 Jahangir Khan Rohail Khan 1 30,000 30,000 15-02-18 30,000 -
42 Muhammad Imran Muhammad Khan 1 30,000 30,000 15-02-18 30,000 -
43 Ali Rehman Shahpur Khan 1 U-18 years 30,000 30,000 30,000
44 Hayatullah Saleh Muhammad 1 30,000 30,000 15-02-18 30,000 -
144
45 Israr Ali (orphan) Ghairat Khan 1 30,000 30,000 15-02-18 30,000 -
46 Abdul Wahaab Sher Zaman 1 30,000 30,000 3-10-18 30,000 -
47 Kashif Iqbal Muhammad Naeem 1 30,000 30,000 15-02-18 30,000 -
46 1 1,410,000 1,665,000 3,075,000 2,595,000 480,000
2.16. Firdous Lessees (Monthly) including payments of Addendum 2
S. No Name of AP Father's Name M F Type of
AP Type of structure /
Asset Payable monthly
Total Payable 15 Months
and 16 Days
Total Paid
TOTAL UNPAID
1 Mirza Khan (MCC) Gul Muhammad 1 Lessee
shops # 8, 9, 11, 12, 20, 25, 27, 31, 37, 36, 35, 43, 40, 38,
39, 44
35,000 x 16 8,689,032 8,689,032 -
2 Hanifa (widow ) Khanzadin (Husband) 1 Lessee Shop # 1 35,000 543,065 543,065 -
3 Asad Ullah Sher Ali 1 Lessee Shop # 3 35,000 543,065 438,065 105,000
4 Aman ullah Sanober Khan 1 Lessee Shop # 4 35,000 543,065 385,000 158,065
5 Abdullah Jan Sher Muhammad 1 Lessee Shop # 5 35,000 543,065 543,065 -
6 Syed Bilal Akbar 1 Lessee Shop # 13 35,000 543,065 543,065 -
7 Najm ud Din Muhammad Israel 1 Lessee Shop # 16 35,000 543,065 543,065 -
8 Zar Ali Anwar Khan 1 Lessee Shop # A2 35,000 543,065 543,065 -
9 Anwar Khan Nawab Khan 1 Lessee Shop # 17 35,000 543,065 543,065 -
10 Salih Muhammad Tor Shah 1 Lessee Shop # 19 35,000 543,065 543,065 -
11 Atta ur Rehman Kalim ur Rehman 1 Lessee Shop # 21 35,000 543,065 438,065 105,000
12 Sohail Shahzad Syed Noor Badshah 1 Lessee Shop # 22 35,000 543,065 543,065 -
13 Mir Afzal Khan Muhammad Saddin 1 Lessee Shop # 24 35,000 543,065 543,065 -
14 Ayub Shah Haji Saeed ur Rehman 1 Lessee Shop # 30 & 34 35,000 x 2 1,086,129 1,086,129 -
15 Rehman Gul Bakht Mir 1 Lessee Shop # 33 35,000 543,065 543,065 -
16 Ashfaq Ahmed Malik Amer Zada 1 lessee Shop # 41 35,000 543,065 438,065 105,000
17 Fasihud Din Qureshi Muhammad Nazir Qureshi 1 Lessee Kiosk 35,000 543,065 438,065 105,000
18 Niaz Ahmed Muhammad Nazir Khan 1 Lessee Kiosk 35,000 543,065 438,065 105,000
145
19 Lawang Khan Muhammad Afzal 1 Lessee/ SK
Leasee of #10 = 35000 and
Leasee +SK # 2 = 75000
110,000 1,706,774 1,706,774 -
20 Hidayat ur Rehman Muhammad Aman 1 Lessee/ SK
Leasee 29 = 35000 Leasee/SK 14, 15,
SK 40 & 41 = 4 x 75000 = 300,000
185,000 5,197,903 5,197,903 -
21 Mir Salam Akber Khan 1 Lessee / SK
Lessee #18 and SK A2
110,000 1,706,774 1,706,774 -
22 Habib Noor Haya Noor 1 Lessee / SK
Leasee # 28 and SK 22
110,000 1,706,774 1,706,774 -
Total 21 1 28,782,426 28,099,361 683,065
2.17. Firdous Shopkeeper income loss (Monthly) including payments of Addendum 2
S.No Name of AP Father's Name M F Type of AP L=lessee
SK=shopkeepr
Type of structure /
Asset
Payable per Month
Total Payable 15 Months
and 16 Days
Total Paid
Total Unpaid
1 Saifoor Khan Gujar Khan 1 Lessee / SK Shop # A1 75,000 1,163,710 1,163,710 -
2 Wajid Ali Nadeem Rahim Bakhsh 1 Lessee / SK Shop # 6 75,000 1,163,710 1,163,710 -
3 Muhammad Dawood Manjawer 1 Lessee / SK Shop # 23 75,000 1,163,710 1,163,710 -
4 Shaikh Muhammad Jawad Riaz
Sheikh Muhammad Riaz
1 Lessee / SK Shop # 26 75,000 1,163,710 1,163,710 -
5 Abdul Ghani Gujar Khan 1 Lessee/SK Shop # 32 75,000 1,163,710 1,163,710 -
6 Salahuddin Gul Zareen 1 SK Shop # 1 75,000 1,163,710 1,163,710 -
7 Sultan Muhammad Sohail Khan 1 SK Shop # 3 75,000 900,000 675,000 225,000
8 Ziarat Gul Hazrat Mohmand 1 SK Shop # 4 75,000 1,163,710 1,163,710 -
9 Rooh Ullah Sanubar Khan 1 SK Shop # 5 75,000 1,163,710 1,163,710 -
10 Zair Ullah Sanober Khan 1 L / SK Shop # 7 75,000 1,163,710 1,163,710 -
11 Hameed ur Rehman Zaheer Ullah Khan 1 SK Shop # 8 75,000 1,163,710 1,163,710 -
12 Islam Gul Bakht Mir 1 SK Shop # 9 75,000 1,163,710 1,163,710 -
13 Muhammad Yousaf Allah Jan 1 SK Shop # 10 75,000 1,163,710 1,163,710 -
14 Muhammad Yaseen Arzmeen Khan 1 SK Shop # 11 75,000 1,163,710 1,163,710 -
15 Nisar Muhammad Sher Zaman 1 SK Shop # 12 35,000 1,163,710 1,048,710 115,000
16 Zahidullah Gula Khan 1 SK Shop # 13 75,000 1,163,710 1,088,710 75,000
146
17 Saleem Khan Bakht Meer 1 SK Shop # 16 75,000 1,163,710 1,163,710 -
18 Ghulam Nabi 1 SK décor A2 - - -
19 Shah Muhammad Tor Shah 1 SK Shop # 17 75,000 1,163,710 1,163,710 -
20 Muhammadullah Nadir Khan 1 SK Shop # 18 75,000 1,163,710 1,163,710 -
21 Laali Gul Abdullah 1 SK Shop # 19 75,000 1,163,710 1,163,710 -
22 Nazir Jan Bismillah Jan 1 SK Shop # 20 75,000 1,163,710 1,163,710 -
23 Ibrahim Khan Noor 1 SK Shop # 21 75,000 1,163,710 638,710 525,000
24 Zabit Khan Sanober Khan 1 SK Shop # 24 75,000 1,163,710 1,163,710 -
25 Perveiz Khan Yar Jan 1 SK Shop # 25 75,000 1,163,710 1,163,710 -
26 Sami Ullah Ghulam Nabi 1 SK Shop # 27 75,000 1,163,710 1,163,710 -
27 Waheed Khan Ghulam Nabi 1 SK Shop # 28 75,000 1,163,710 1,163,710 -
28 Zahir Shah Shahzada Khan 1 SK Shop # 29 75,000 1,163,710 338,710 825,000
29 Majid Zaheen Rahim Baksh 1 SK Shop # 30 75,000 1,163,710 938,710 225,000
30 Gul Sher Akhter Said 1 SK Shop # 31 75,000 1,163,710 1,163,710 -
31 Jalil Khan Bakht Mir 1 SK Shop # 33 75,000 1,163,710 1,163,710 -
32 Rukhsana Bibi Kifayatullah Khan (Husband)
1 SK Shop # 36, 37,
38 & 39 300,000 4,654,830 4,654,830 -
33 Shah Zameen Sadbar 1 SK Shop # 35 75,000 1,163,710 938,710 225,000
34 Jamshaid Habib Ur Rehman 1 SK Shop # 34 75,000 1,163,710 938,710 225,000
35 Mushtaq Masih Malik Masih 1 SK Shop # 43 75,000 1,163,710 450,000 713,710
36 Khurram Masih Rafiq 1 SK Shop # 44 75,000 1,163,710 1,088,710 75,000
37 Abdul Quim Akhter Said 1 SK kiosk 75,000 1,163,710 1,163,710 -
38 Aqal Bacha Akhter Syed 1 SK kiosk 75,000 1,163,710 1,163,710 - Total 37 1 46,284,680 43,055,970 3,228,710
2.18. Firdous Shifting Allowance shop keeper
S.No Name of AP Father's Name Type of AP Shop # Shifting
Allowance Shifting Paid
Unpaid Shifting
1 Hanifa (widow ) Khanzadin (late) Husband Lessee 1 - - -
2 Lawang Khan Muhammad Afzal Lessee / SK Le 10 and Le +SK # 2 30,000 30,000 -
3 Hidayat ur Rehman Muhammad Aman Lessee / SK Le 29, Le/SK 14, 15, SK
40 & 41 120,000 120,000
-
4 Mir Salam Akber Khan Lessee / SK Shop # 18 and renting
A2 30,000 30,000
-
147
5 Habib Noor Haya Noor Lessee / SK Le # 28 and SK 22 30,000 30,000 -
6 Saifoor Khan Gujar Khan SK A1 30,000 30,000 -
7 Wajid Ali Nadeem Rahim Bakhsh SK 6 30,000 30,000 -
8 Muhammad Dawood Manjawer SK 23 30,000 30,000 -
9 Shaikh Muhammad Jawad Riaz
Sheikh Muhammad Riaz SK 26 30,000 30,000 -
10 Abdul Ghani Gujar Khan SK 32 30,000 30,000 -
11 Salahuddin Gul Zareen SK 1 30,000 30,000 -
12 Sultan Muhammad Sohail Khan SK 3 30,000 30,000 -
13 Ziarat Gul Hazrat Mohmand SK 4 30,000 30,000 -
14 Rooh Ullah Sanubar Khan SK 5 30,000 30,000 -
15 Zair Ullah Sanober Khan SK 7 30,000 30,000 -
16 Hameed ur Rehman Zaheer Ullah Khan SK 8 30,000 30,000 -
17 Islam Gul Bakht Mir SK 9 30,000 30,000 -
18 Muhammad Yousaf Allah Jan SK 10 30,000 30,000 -
19 Muhammad Yaseen Arzmeen Khan SK 11 30,000 30,000 -
20 Nisar Muhammad Sher Zaman SK 12 30,000 - 30,000
21 Zahidullah Gula Khan SK 13 30,000 30,000 -
22 Saleem Khan Bakht Meer SK 16 30,000 30,000 -
23 Ghulam Nabi SK décor A2 - - -
24 Shah Muhammad Tor Shah SK 17 30,000 30,000 -
25 Muhammadullah Nadir Khan SK 18 30,000 30,000 -
26 Laali Gul Abdullah SK 19 30,000 30,000 -
27 Khair Gul SK 20 30,000 30,000 -
28 Ibrahim Khan Noor SK 21 30,000 30,000 -
29 Zabit Khan Sanober Khan SK 24 30,000 30,000 -
30 Perveiz Khan Yar Jan SK 25 30,000 30,000 -
31 Sami Ullah Ghulam Nabi SK 27 30,000 30,000 -
32 Waheed Khan Ghulam Nabi SK 28 30,000 30,000 -
33 Zahir Shah Shahzad Khan SK 29 30,000 30,000 -
34 Majid Zaheen Rahim Baksh SK 30 30,000 30,000 -
35 Gul Sher Akhter Said SK 31 30,000 30,000 -
36 Jalil Khan Bakht Mir SK 33 30,000 30,000 -
37 Rukhsana Bibi Kifayatullah (Husband) SK 37 30,000 30,000 -
38 Rukhsana Bibi Kifayatullah (Husband) SK 36 30,000 30,000 -
39 Shah Zamin Khan Sadbar SK 35 30,000 30,000 -
40 Jamshaid Habib Ur Rehman SK 34 30,000 30,000 -
148
41 Mushtaq Masih Malik Masih SK 43 30,000 30,000 -
42 Rukhsana Bibi Kifayatullah (Husband) SK 39 30,000 30,000 -
43 Rukhsana Bibi Kifayatullah (Husband) SK 38 30,000 30,000 -
44 Khurram Masih Rafiq SK 44 30,000 30,000 -
45 Abdul Quim Akhter Said SK kiosk 30,000 30,000 -
46 Aqal Bacha Akhter Syed SK kiosk 30,000 30,000 - Total 1,410,000 1,380,000 30,000
2.19. Firdous Employees Compensation
S.No Name of AP Father's Name M F Status Income
Allowance Vulnerability Allowance
Total cost Date Paid Paid Unpaid
1 Sultan Muhammad Mir Zada 1 30,000 45,000 75,000 22-05-18 75,000 -
2 Jahan Zada Gul Zada 1 30,000 45,000 75,000 22-05-18 75,000 -
3 Muhammad Ali Muhammad Zameen 1 30,000 45,000 75,000 08-10-18 75,000 -
4 Yar Muhammad Haleem Jan 1 30,000 45,000 75,000 22-05-18 75,000 -
5 Subhan Ullah Sher Khan 1 U-18 years 30,000 45,000 75,000 10-08-18 75,000 -
6 Naimatullah Ahmed Mir 1 U-18 years 30,000 45,000 75,000 75,000
7 Subhanullah Ahmad Zahir 1 U-18 years 30,000 45,000 75,000 02-10-18 75,000 -
8 Muhammad Javed Sanober 1 U-18 years 30,000 45,000 75,000 31-01-19 75,000 -
9 Naveed Waheed Abdul Waheed 1 U-18 years 30,000 45,000 75,000 16-08-18 75,000 -
10 Qamar Ali Naveed Waheed 1 U-18 years 30,000 45,000 75,000 12-02-19 75,000 -
11 Haider Ali Fayyaz 1 30,000 45,000 75,000 22-05-18 75,000 -
12 Bawar Khan Hazrat Mohmand 1 30,000 45,000 75,000 22-05-18 75,000 -
13 Ajmal Mir Alam 1 U-18 years 30,000 45,000 75,000 75,000
14 Imran Rehman Gul 1 U-18 years 30,000 45,000 75,000 75,000
15 Farhad Ali Gul Jan 1 30,000 45,000 75,000 10-08-18 75,000 -
16 Azizullah Muhammad Hassan 1 30,000 45,000 75,000 22-05-18 75,000 -
17 Irfanullah Rehmanullah 1 30,000 45,000 75,000 22-05-18 75,000 -
18 Abdul Qadir Abdul Samad 1 30,000 45,000 75,000 16-08-18 75,000 -
19 Sadiqullah Abdul Khaliq Khan 1 30,000 45,000 75,000 23-05-18 75,000 -
20 Nisar Khan Gul Meer Khan 1 30,000 45,000 75,000 23-05-18 75,000 -
21 Shehzad Khan Noor Khan 1 U-18 years 30,000 45,000 75,000 13-08-18 75,000 -
22 Farhad Khan Ziarat Gul 1 30,000 45,000 75,000 22-05-18 75,000 -
23 Sheraz Ziarat Gul 1 U-18 years 30,000 45,000 75,000 17-06-20 75,000 -
149
24 Abdul Muhammad Akbar Khan 1 30,000 45,000 75,000 07-02-19 75,000 -
25 Zahidullah Abdul Muhammad 1 U-18 years 30,000 45,000 75,000 20-11-19 75,000 -
26 Ijaz ul Haq Mirza Khan 1 U-18 years 30,000 45,000 75,000 - 75,000
27 Bashir Khan Manjawer 1 30,000 45,000 75,000 22-05-18 75,000 -
28 Rahimullah Ahmad Jan Masih 1 30,000 45,000 75,000 22-05-18 75,000 -
29 Abdul Salam Abdul Raziq 1 30,000 45,000 75,000 22-05-18 75,000 -
30 Sajid Ahmad Nazir Jan 1 U-18 years 30,000 45,000 75,000 13-08-18 75,000 -
31 Muhammad Riaz Sher Khan 1 U-18 years 30,000 45,000 75,000 03-10-18 75,000 -
32 Irshad Khan Misri Khan 1 30,000 45,000 75,000 22-05-18 75,000 -
33 Banaras Khan Shah Mast Khan 1 30,000 45,000 75,000 22-05-18 75,000 -
34 Muhammad Afzal Khan Abdul Mateen 1 U-18 years 30,000 45,000 75,000 31-01-19 75,000 -
35 Muhammad Fida 1 30,000 45,000 75,000 75,000
36 Aziz Ahmad Muhammad Aleem 1 30,000 45,000 75,000 22-05-18 75,000 -
37 Niaz Ali Qadar Khan 1 U-18 years 30,000 45,000 75,000 03-10-18 75,000 -
38 Atif Wahid Abdul Waheed 1
At the time of verification
CNIC was not available with
Atif
30,000 45,000 75,000 16-08-18 75,000 -
39 Fiaz Khan Iftikhar Ahmad 1 30,000 45,000 75,000 22-05-18 75,000 -
40 Nasir Karim Karim Baksh 1 U-18 years 30,000 45,000 75,000
16-10-2018 for 30,000
12-02-2019 for 45,000
75,000 -
41 Muhammad Shah Awal Khan 1 30,000 45,000 75,000 22-05-18 75,000 -
42 Hazrat Shah Awal Khan 1 30,000 45,000 75,000 22-05-18 75,000 -
43 Zahir Khan Abdur Rehman 1 U-18 years 30,000 45,000 75,000 05-09-18 75,000 -
44 Muhammad Ghani Muhammad Akbar 1 30,000 45,000 75,000 25-06-18 75,000 -
45 Wajahatullah Zahir Shah 1 U-18 years 30,000 45,000 75,000 02-10-18 75,000 -
46 Shahzad Dost Muhammad 1 U-18 years 30,000 45,000 75,000 22-07-20 75,000 -
47 Akhtar Ali Hunar Shah 1 30,000 45,000 75,000 15-10-18 75,000 -
48 Abdur Rehman Maeen Khan 1 U-18 years 30,000 45,000 75,000 75,000
49 Ibrahim Ismail 1 U-18 years 30,000 45,000 75,000 75,000
50 Ihsanullah (Afghani) Hunir Jan 1 (POR Card#) 1101038298-
1 30,000 45,000 75,000 75,000
150
51 Inayat Hussain Sadbar 1 U-18 years 30,000 45,000 75,000 16-08-18 75,000 -
52 Umer Fayyaz 1 U-18 years 30,000 45,000 75,000 75,000
53 Shah Hussain Sadbar 1 30,000 45,000 75,000 13-08-18 75,000 -
54 Sajid Shahzada Khan 1 30,000 45,000 75,000 23-05-18 75,000 -
55 Latif ur Rehman Muhammad Dostan 1 30,000 45,000 75,000 23-05-18 75,000 -
56 Viki Rafiq 1 CNIC Not available
30,000 45,000 75,000 03-09-18 75,000 -
57 Adeel Masih Jan Masih 1 30,000 45,000 75,000 16-08-18 75,000 -
58 Imran Masih Mander Masih 1 CNIC not available
30,000 45,000 75,000 03-10-18 75,000 -
59 Ceesman Maseeh Mander Maseeh 1 30,000 45,000 75,000 06-11-19 75,000 -
60 Gul Zarin Jamdali Khan 1 30,000 45,000 75,000 23-05-18 75,000 -
61 Keshar Khan Saeed ur Rehman 1 30,000 45,000 75,000 23-05-18 75,000 -
62 Mushtaq Masih Sona Masih 1 30,000 45,000 75,000 12-11-19 75,000 -
63 Ashraf Ali Abdur Rauf 1 30,000 45,000 75,000 23-05-18 75,000 -
64 Muhammad Rauf Abdur Rauf 1 30,000 45,000 75,000 23-05-18 75,000 -
65 Bilal Khan Saifor Khan 1 U-18 yrs 30,000 30,000 03-10-18 30,000 -
66 Wahidullah Mir Salam 1 CNIC Not available
30,000 30,000 05-11-19 30,000 -
67 Abdul Wajid Lawang Khan 1 U-18 years 30,000 30,000 25-06-20 30,000 -
68 Imran Sultan Muhammad 1 30,000 30,000 23-05-18 30,000 -
69 Shaukat Ullah Sultan Muhammad 1 U-18 years 30,000 30,000 28-11-18 30,000 -
70 Ishfaq Ahmad Rahim Baksh 1 30,000 30,000 27-06-18 30,000 -
71 Muhammad Faisal Zair Ullah Khan 1 30,000 30,000 23-05-18 30,000 -
72 Qadim Khan Bakht Mir 1 30,000 30,000 23-05-18 30,000 -
73 Israr Khan Islam Gul 1 30,000 30,000 23-05-18 30,000 -
74 Abdul Malik Allah Jan 1 30,000 30,000 23-05-18 30,000 -
75 Noushad Laal Zameen 1 30,000 30,000 23-05-18 30,000 -
76 Abdur Rahman Zahid Ullah 1 30,000 30,000 23-05-18 30,000 -
77 Sher Rehman Meera Khan 1 30,000 45,000 75,000 23-05-18 for 30& 03-10-18 for 45
75,000 -
78 Muhammad Islam Muhammad Amaan 1 30,000 30,000 24-05-18 30,000 -
79 Shams ur Rehman Muhammad Amaan 1 30,000 30,000 26-06-18 30,000 -
80 Abdul Rehman Muhammad Amaan 1 30,000 30,000 26-06-18 30,000 -
151
81 Sher Jan Tor Jan 1 30,000 30,000 24-05-18 30,000 -
82 Muhammad Ibrahim Qazi Musanif Khan 1 30,000 30,000 - 30,000
83 Saleh Muhammad Tor Shah 1 30,000 30,000 24-05-18 30,000 -
84 Niaz Gul Tor Shah 1 30,000 30,000 24-05-18 30,000 -
85 Nowshad Ali Laali Gul 1 30,000 30,000 24-05-18 30,000 -
86 Wahid Ullah Bismillah Jan 1 30,000 30,000 24-05-18 30,000 -
87 Imran Bismillah Jan 1 30,000 30,000 24-05-18 30,000 -
88 Wahaab Khan Muhammad Dawood 1 30,000 30,000 03-10-18 30,000 -
89 Javed Khan Yar Jan 1 U-18 years 30,000 30,000 03-10-18 30,000 -
90 Muhammad Yaseen Shahzada Khan 1 30,000 30,000 04-06-18 30,000 -
91 Walayat Shah Aqal Bacha 1 U-18 years 30,000 30,000 04-10-18 30,000 -
92 Ibrahim Abdul Ghani 1 30,000 30,000 23-07-18 30,000 -
93 Nadeem Khan Rehman Gul 1 30,000 30,000 24-05-18 30,000 -
94 Tariq Khan Rehman Gul 1 30,000 30,000 24-05-18 30,000 -
95 Ibrahim Khan Noor 1 30,000 30,000 24-05-18 30,000 -
96 Haroon Maseeh Mushtaq Maseeh 1 CNIC not available
30,000 30,000 30,000
97 Saifullah Aqal Bacha 1 U-18 years 30,000 30,000 04-10-18 30,000 -
98 Bilal Khan Said Kareem 1 U-18 years 30,000 30,000 28-11-18 30,000 -
Total 98 0 2,940,000 2,925,000 5,865,000 5,130,000 735,000
2.20. Shop Keepers of Access Ramp Reach 1
S. No Name Father Name Shifting
Allowance No. of
Months Rate
Income loss for transition period (one time lump
sum)
Total Date Paid Paid Unpaid
1 Farmanullah Muhammad Diyar 10,000 6 75,000 450,000 460,000 22-07-20 460,000 -
2 Attaullah Amanullah 10,000 6 75,000 450,000 460,000 460,000
3 Intikhab Alam Bakhshish 10,000 6 75,000 450,000 460,000 23-07-20 460,000 -
4 Yasir Khan Sher Dil Khan 10,000 6 75,000 450,000 460,000 22-07-20 460,000 -
5 Izhar Khan Muhammad Israr Khan 10,000 6 75,000 450,000 460,000 460,000
6 Mehmood ur Rehman Raza Khan - 3 75,000 225,000 225,000 22-07-20 225,000 -
152
7 Fazl-e-Rabi Ghulam Nabi - 3 75,000 225,000 225,000 22-07-20 225,000 -
Total 50,000 2,700,000 2,750,000 1,830,000 920,000
2.21. Employees Access Ramp Reach 1 (Addendum 1, Reach 1)
S.No Name of Employee Father's Name CNIC
Allowances (One Time Lumpsum) TOTAL
Lumpsum Date Paid Paid Unpaid
Loss of Income
Vulnerability Allowance
1 Muhammad Fazl-e-Rahim Below 18 years 30,000 45,000 75,000 75,000
2 Shafaqat Ali Din Muhammad 17301-3371467-5 30,000 45,000 75,000 22-07-20 75,000 -
3 Khan Muhammad Taj Muhammad 16102-9312172-7 30,000 45,000 75,000 22-07-20 75,000 -
4 Rafiullah Amanullah 15202-8833445-5 30,000 45,000 75,000 75,000
5 Muhammad Zubeir Rehmatullah Gul 21203-9390944-1 30,000 45,000 75,000 22-07-20 75,000 -
6 Shah Faisal Wilayat Khan 21203-3755200-1 30,000 45,000 75,000 22-07-20 75,000 -
7 Zaryab Baseer Abdul Baseer Below 18 years 30,000 45,000 75,000 10-07-20 75,000 -
8 Zabeehullah Muhammad Ismail Below 18 years 30,000 45,000 75,000 75,000
9 Luqman Bakshish Bakhshish 17301-5066379-1 30,000 45,000 75,000 22-07-20 75,000 -
10 Amer Khan Faqir Hussain Below 18 years 30,000 45,000 75,000 75,000
11 Hazrat Niaz Gul Below 18 years 30,000 45,000 75,000 75,000
12 Feroz Khan Ajab Khan 17301-0161698-1 30,000 45,000 75,000 75,000
13 Shahid Khan Kachkool 42401-4370458-9 30,000 45,000 75,000 23-07-20 75,000 -
14 Inam ul Haq Abdul Haseeb 17301-7036713-3 30,000 45,000 75,000 22-07-20 75,000 -
15 Muhammad Hayat Khan Zabita Khan 17301-1825482-7 30,000 45,000 75,000 75,000
16 Imran Shami Shafiqullah Afghani 30,000 45,000 75,000 75,000
17 Sohail Khan Inamullah Below 18 years 30,000 45,000 75,000 75,000
18 Qader Khan Manzoor Khan 17301-9336962-1 30,000 45,000 75,000 75,000
Total 540,000 810,000 1,350,000 600,000 750,000
155
Inbox
Naila Jabeen [email protected] Sep 29, 2020, 11:21 AM
To Wajid, Amin, Mian, Khokhar, Gulfam, Ayaz, Yukihiro, Syed, Muhammad, asstt.dirfinance.pda, mirza
Respected Wajid Ali Nadeem sab
It is inform you as you are shora committee member APs compensation cheque of Hashtnagri & Firdous under pass sub
lesses/shopkeepers ready for payment as you know below mention APs cheque expired although we inform many time, but no
response we have found, some 03 APS cheques are pending due to agreement issue between lessee or sublessee kindly
facilitate them, few APS are out of city provide us contact no or email for coordination and those are in Peshawar inform them
collect their compensation cheques from PDA Office on October 6,2020 at 10:30 AM,name of APS are Muhammad Ali,
Shakoor Ahmad,Adnan Ahmad,Jamal Din,Zahir Shah,Mushtaq Masih,Asad Ullah,Amanullah,Atta ur Rehaman,Ahfaq
Ahmad,Fasihuddin Qureshi,Niaz Ahmad,Nisar Muhammad,Zahidullah,Majid Zaheen,Shah Zamin,Jumshid,Khurram
Masih,Muhammad Ibrahim,Faiz ur Rehman,Rehman Gul,Atta Ur Rehman,Atta ur Rehman,Ayub Shah,Farzand Ali,Aman
Khan,Atta ur Rehman,Amanullah.Mashtaq Masih, Sultan Muhammad.
please any further detail feel free to ask on my cell no 03129549940
Regards
Naila Jabeen
Social Resettlement Officer
BRT PIU Peshwar
Wajid ali [email protected] Tue, Oct 13, 1:19 PM
To me, PDA, Main, Ashfaq, Gulfam, Ayaz, Yukihiro, Syed
Dear Madam,
As desired in your email, all the APs have been informed to collect their checks accordingly, however, the APs of BS-07 are not
ready to collect their check until the issue of closed shops and compensation period is not resolved. In this regard we have
submitted a written request to the concerned office is attached herewith for reference, please.
regards,
Wajid Ali
On Tue, Oct 13, 2020 at 12:34 PM mirza khan <[email protected]> wrote:
Oct 13, 2020, 1:19 PM
Naila
Jabeen
Nov 8, 2020, 11:53 AM (22 hours ago)
156
---------- Forwarded message --------- From: Naila Jabeen <[email protected]> Date: Tue, 29 Sep 2020 11:21
am Subject: Request for receive compensation c
Naila Jabeen [email protected] Nov 8, 2020, 12:32 PM (22 hours ago)
to Wajid, Amin, Gulfam, asstt.dirfinance.pda, Khokhar, mtkhan1000, Mian, muhammad, mirza, Ayaz, Sidra, Syed, Hame
ed
Respected Wajid Nadeem sab
Reminder of email and individul letter provided to you being a shora member handover to you also for AP to collect their
cheques till Novmber 05,2020 but still no response from APs site only few APs collect their cheques fot under age APs we
already brief all them to provide Guardian certificate along Nadra B form but still no response except of only few so it is inform
all of you STRPI contract ended in December 2020 and External M&E final report under process and we will submit report till
3rd week of December.PDA also going to advertise unpaid APs detial in newspaper after all these good efforts and in absence
of STRPI Resettlment Officer may be APs will face problems in collection of compensation cheques.Kindly inform all unpaid
APs to collect their compensation cheques before 30 November 2020.Following unpaid APs in Firdous and Hashtnagri
underpass:
Hashtangri Underpass
1.Atta ur Rehman s/o Kalim ur Rehman
2.Umair s/o Shamshad
3.Bashir s/o Rehmatullah
4. Sohaid Rahat s/o Saleh Muhammad
5.Muhammad Basit s/o Tariq Aziz
6.Zubair s/o Abdul Hakeem
7.Umair Jan s/o Noor Muhammad
8.Farzand Ali s/o Waris Khan
9.Muhammad Ali s/o Gul Muhammad
10.Shakoor Ahmad s/o Muhammad Nazir
11.Ashfaq Ahmad s/o Malik Amir Zada
12.Ghayour Ahmad s/o Muhammad Nazir
13.Adnan Ahmad s/o Muhammad Nazir
Firdous Underpass
1.Nisar Muhammad s/o Sher Zaman
2. Ibrahim s/o Noor Khan
3. Zahir Shah s/o Shahzada Khan
4. Sultan Muhammad s/o Sohail Khan
5.Khair Gul
6. Aman ullah s/o Sanober Khan
7. Atta Ur Rehman s/o Kalim ur Rehman
8. Naimatullah s/o Ahmed Mir
9.Ajmal s/o Mir Alam
157
10. Imran s/o Rehman Gul
11.Ijaz ul Haq s/o Mirza Khan
12.Muhammad Fida
13.Abdur Rehman s/o Maeen Khan
14.Ibrahim s/o Ismail
15.Ihsanullah s/o Hunir Khan
16.Umer s/o Fayyaz
17.Haroon Masih s/o Mushtaq Masih
we also provided detial list with of sublesse, shopkeeper and employee.Incase for any quarry please contact me.
Regards
Naila Jabeen
Social Resettlement Officer
BRT PDA Peshawar
165
Annex 13. Pictorial Presentation
DPs are receiving their compensation cheques from the Office of Director finance at PDA
Figure 1
DPs of underpasses are waiting for their cheques from the Office of Director finance at PDA.
166
Annex 14. Guardian Statement Form
Guardian Statement if DP is Juvenile
Date Prepared: ___________________ Particular of DPs and acquired land parcel Name/Names of DPs i)___{enter DP Name/names of DPs with Parentage}, ii) ______________and iii)______________Resident of______{Enter DP current address}____ Own acquired Land Plot/shop_______ Located ________
Statement by Guardian I_____{put name here}__ __the {mother/father/brother/sister/uncle (put relation of elder with whom the minor DP/DPs lives} of DP/DPs_i),_____{put name of DP/DPs here}___ii),________________iii)___________________ as natural guardian solemnly declare that:
• The DP/DPs is/are minor who lives with me and as natural guardian of DP/DPs, I am responsible for his/her/their well-being and bringing him/her/them up;
• __________ (indicate name of staff, unit, and EA) has clarified that compensation amount, already deposited in treasury, can be paid to legal guardian of DP/DPs after production of the valid Guardian Certificate issued by the competent court;
• A petition for issuance of guardians certificate is filed/being filed in the competent court and the court’s decision is pending;
• The awarded compensation in name of DP/DPs will be collected upon issuance of guardian’s certificate by court; however, as natural guardian I have no objection to commencement of project works; and
• This statement is given free of coercion and compulsion which is witnessed by -------. The Declarant Sign/Thumb Impression Name_________________________________ Relationship with DP_____________________ Resident of_____________________________ ______________________________________
Witnessed By We the DPC head---------, personally know Mr/Mrs__________________ and witness veracity of statement made by confirming that the Minor DP/DPs named above lives with him/her in village/city_{Put name of village city here}.
Signed Signed
Name: Mr.-------------------- Name: Mr.-------------------- DPC head------- Resettlement Expert…--