Managing Projects - CERN Indico
-
Upload
khangminh22 -
Category
Documents
-
view
2 -
download
0
Transcript of Managing Projects - CERN Indico
Project ManagementWhat are we going to see together?
Project Team
Study Team
InitiatorsProject Board
ProjectManager
Lifecycle
Roles
Study Leader
Project Stakeholders
FINALIZECOMMISSIONBUILDDESIGNSTUDYINITIALIZE
Processes
ProjectRoadmap
ProjectProposal
ProjectMngt Plan
Coord.Schedule
ProgressReport(s)
WBS& RACI
ArtefactsLaunching a project
Finalizing a project
Ensuring quality
Reporting progress
Defining requirements
Handling issues
Managing risks
Planning & schedulingCosting
Reqts.Register
RiskRegister
Budget
PBS
CostEstimate
Close-outReport
IssueRecord(s)
Project Planning & Scheduling
Why?
1 to set a reference2 to assess uncertainties3 to follow up progress
Project Planning & Scheduling
Why?
1 to set a reference2 to assess uncertainties3 to follow up progress
Typology
2 types of project schedules
Master Schedule~ Summary Schedule
MasterplanCalendrier directeur
Coordination Schedule~ “PERT”, Gantt chart
Activity networkCalendrier de coordination
Strategic levelThe whole projectIntuitive approach
Tactical levelOne or a few phasesAnalytical approach
One page/slideCan be in the Project Roadmap
Several pagesCan be in the PMP
FINALIZECOMMISSIONBUILDDESIGNSTUDYINITIALIZE
Initiators
Master ScheduleWhen and which effort?
Master Schedule preparation
Master Schedule (re)validation
Project Board
Master Schedule updateStudy Team
Master Schedule updatesProject Team
FINALIZECOMMISSIONBUILDDESIGNSTUDYINITIALIZE
Coordination ScheduleWhen and which effort?
Study Coordination Schedule* preparation (if needed)Study Team
Project Coordination Schedule* updatesProject Team
Study Team
Project Coordination Schedule* preparation
* incl. PBS, WBS, LoA (list of activities), RBS, RACI matrix
MayAprilMarchFeb.Jan.Dec.Nov.Oct.Sep.
BRZ•KITE project launched
CDR released Perform Basic Design
Perform Engi neering Design TDR released
Make & Test PrototypeSet Supply Chain
Perform Detailed Design of Manufacturing Facility Procure Equipment & Tooling
Perform Civil Engineering WorksInstal & Commission Equipment & Tooling
Ramp-up Production1st batch ofkites shipped
Coordination Planning & SchedulingA three-step process
q Identifying the project activities
w Identifying the resources available, estimating the resources required
a Gantt chartMicrosoft Project Gantt chart® ®
ProjectWizard Merlin Gantt chart® ®
The Work Breakdown Structure (WBS)
The RACI Matrix
e Scheduling the activities
The Coordination Schedule
Coordination Planning & Scheduling
3 possible approaches
Intuitiveapproaches
Analogicalapproaches
Analyticalapproaches
creativitytechniques Practice Standard
for Work BreakdownStructures
q Identifying the project activities
PMBOK Quintilianheptameter
-inspired
Coordination Planning & Schedulingq Identifying the project activities Ú analogical approaches
> Approach sold as systematic,but not that much!
> Global lessons learned collectedby the Project Management Institute
NASA's Work Breakdown Structure Handbook (NASA/SP-2010-3404)Project Management Institute's Practice Standard to Work Breakdown Structures
Coordination Planning & Schedulingq Identifying the project activities Ú analogical approaches
Project Management Institute's Practice Standard to Work Breakdown Structures
Coordination Planning & Schedulingq Identifying the project activities Ú analytical approach
> Inspired from the Quintilian heptameter
Marcus Fabius Quintilianus(c. 35 – c. 100 CE) was a Roman
rhetorician from Hispania, widely referred to in medieval schools of
rhetoric and in Renaissance writing
quiswho
quidwhat
ubiwhere
quibus auxiliiswhich means
curwhy
quomodohow
quandowhen
1=! Describing the final deliverable(s)
The Product Breakdown Structure (PBS)
1=@ Deriving the Work Breakdown Structure (WBS) from the PBS
The WBS top nodes, then the WBS-matrix
1=# Generating the list of activities from the WBS-matrix
The activity portfolio
Coordination Planning & Schedulingq Identifying the project activities Ú analytical approach
What is an activity??a.k.a. work unit
] ≠ deliverable!
] consumes time
action verb (infinitive tense) + noun]
To avoid confusion, clever professional practices (e.g. MIL-HDBK-245B + appendix A) and severaltextbooks suggest to label activities as follow:
] consumes resources
] has start and end dates
] creates (a) deliverable(s)
] is measurable
] is assignable to one project participant
Some examples:Manage the projectPrepare PM documentsPerform detail design of wing surfaceSupply rope & strapsCFT for moulded ABS parts
An activity:
and only one!
Coordination Planning & Schedulingq Identifying the project activities Ú analytical approach
What is an activity??An activity:
] consumes time Yes, but within certain limits!
] No definitive answer!
] No more than 5% to 10% of the project duration
] No more than 13 weeks (long lead projects)
] One or up to 1% of level-of-effort activities
What is the maximum duration?
] No definitive answer!
] But not more than 400 activities, otherwise difficult to manage
And how many activities on a coordination schedule?
activities vs. planned activities #748
Coordination Planning & Schedulingq Identifying the project activities Ú analytical approach
What is a deliverable??a.k.a. result
] ≠ activity!
noun + verb at past participle tense]
Some examples:bzh-kite designedbzh-kite specifiedbzh-kite prototype testedbzh-kite manuf. facility commissioned
] ≠ product!e.g. the brz-kite
Deliverable is a term used [...] to describe a tangible or intangible object produced as a result of the project that is intended to be delivered to a customer (either internal or external).A deliverable could be a report, a document [...] or any other building block of an overall project. en.Wikipedia.org
] ≠ milestone!
Coordination Planning & Schedulingq Identifying the project activities Ú analytical approach
Deriving the Work Breakdown Structure (WBS) from the PBS1=@
PBSBoM
WBS top nodes
Project management andsystem-level design activities
Development activities associated with sub-systemsand product components
A slightly refurbished PBS
System-level integration, validation, refinement and ramp-up activities
Genericactivities
WB
S to
p no
des
Coordination Planning & Schedulingq Identifying the project activities Ú analytical approach
Generating the list of activities from the WBS-matrix1=#
For each cell of this matrix,count how many activitiesare required to managethe project efficiently
1 One activityshall be planned
nA few activitiesshall be planned (cf. activity def.)
Sum < 400 act.
Man
age
the
proj
ect
Prep
are
PM d
ocum
ents
Perf
orm
bas
ic d
esig
nCF
T an
d aw
ard
cont
ract
Prep
are
spec
ifica
tion
Perf
orm
det
ail d
esig
nSu
pply
equ
ipm
ent
Neg
otia
te a
gree
men
t
Prep
are
cons
truc
tion
Do
eart
hwor
ksPo
ur c
oncr
ete
Do
2nda
ry w
orks
Do
last
fini
shin
gs
Cont
rol,
surv
eyTr
ansf
er to
ow
ner
Coordination Planning & Schedulingq Identifying the project activities Ú analytical approach
Generating the list of activities from the WBS-matrix1=#Generic activities suited to a construction projectì
Man
age
the
proj
ect
Prep
are
PM d
ocum
ents
Perf
orm
mar
ketin
g/sa
les
activ
ities
Perf
orm
det
ail d
esig
n
Perf
orm
sys
tem
-leve
l des
ign
Perf
orm
IP /
pate
nt re
late
d ac
tiviti
esPr
epar
e pr
ocur
emen
t spe
cs /
orde
r
CFT
and
awar
d co
ntra
cts
/ pla
ce o
rder
Des
ign
and
set t
he s
uppl
y ch
ain
Prep
are
mak
ing
Mak
e, a
ssem
ble…
Verif
y, v
alid
ate…
Cons
truc
t, in
stal
l…
Refu
rbis
h…Co
mm
issi
on, r
amp-
up…
Coordination Planning & Schedulingq Identifying the project activities Ú analytical approach
Generating the list of activities from the WBS-matrix1=#Generic activities suited to a NPD projectì
Genericactivities
WB
S to
p no
des
LoA
Coordination Planning & Schedulingq Identifying the project activities Ú analytical approach
Generating the list of activities from the WBS-matrix1=#
1 2 11
11 1
1 3 11 1
1 1 111 1
2 1 11 4 11
1 21 1 3
2 1 1
2
3
4
5
6
7
8
9
1
B C D E F G H I J K L M N O PA
1 1 1 7 6 1 3 1 2 2 4 2 2 1 1 2 3 2 2 1 1 2 2 1 1 2 1 2 1 2 1 1 2 2 1 1 2 2 1 1
bzh·kiteFabricsCarbon rodsMoulded ABS partsRings (COTS)Rope & strapStorage bagPrinted material
Level
Mana
ge th
e proj
ect
Prep
are PM
docu
ment
sPe
rform
mark
eting
/sales
activ
ities
Perfo
rm IP
/pate
nt re
lated
activ
ities
Perfo
rm ba
sic de
sign
Perfo
rm de
tail d
esign
Prep
are sp
ecific
ation
/ ord
erCF
T / aw
ard co
ntrac
t / pl
ace o
rder
Prep
are m
aking
Make
, asse
mble…
Test,
valid
ate…
Refu
rbish
…Co
nstru
ct, in
stall…
Comm
ission
, ramp
-up…
= 59 WUs
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
CBA
WU ID PU ID Work Unit or Planned Unit Label100 Manage bzh-kite project101 Prepare bzh-kite project management documents102 Refine Breizh-Sports product planning103 Develop marketing plan for bzh-kite 010 Develop sales plan for bzh-kite104 Develop after-sale support plan for bzh-kite 011 Design and release launch materials 012 Design and release promotion materials 013 Facilitate field testing106 Refine industrial design of bzh-kite107 Perform basic design for bzh-kite 014 Manufacture and assemble pre-series bzh-kite108 Define the supply-chain for all bzh-kite components109 Define bzh-kite manufacturing/assembly scheme f process diagram110 Design bzh-kite manufacturing/assembly facility f plant layout
1
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
CBA
WU ID PU ID Work Unit or Planned Unit Label111 Perform detail design for bzh-kite fabrics f engineering drawings112 Choose materials for bzh-kite fabrics113 Identify suppliers for bzh-kite fabrics114 Prepare specifications for bzh-kite fabrics115 CFT/award contract for bzh-kite fabrics 015 Define/design equipment for bzh-kite fabrics related processes 016 Prepare specifications for bzh-kite fabrics equipment 017 CFT/award contract for bzh-kite fabrics equipment 018 Prepare making for bzh-kite fabrics equipment 019 Make/assemble bzh-kite fabrics equipment116 Choose materials for bzh-kite carbon roads117 Identify suppliers for bzh-kite carbon roads118 Prepare specifications for bzh-kite carbon roads119 CFT/award contract for bzh-kite carbon roads 020 Define/design equipment for bzh-kite carbon roads related processes
1
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
CBA
WU ID PU ID Work Unit or Planned Unit Label 021 Prepare specifications for bzh-kite carbon roads equipment 022 CFT/award contract for bzh-kite carbon roads equipment 023 Prepare making for bzh-kite carbon roads equipment 024 Make/assemble bzh-kite carbon roads equipment120 Perform detail design for bzh-kite moulded ABS parts 121 Identify suppliers for bzh-kite moulded ABS parts122 Prepare specification for bzh-kite moulded ABS parts123 CFT/award contract for bzh-kite moulded ABS parts124 Prepare/place order for bzh-kite rings125 Prepare/place order for bzh-kite rope & strap 025 Define/design fixtures for bzh-kite rope & strap related processes 026 Prepare/place order for bzh-kite components for rope & strap fixture 027 Prepare making for bzh-kite rope & strap fixtures 028 Make/assemble bzh-kite rope & strap fixtures126 Design storage bag for bzh-kite
1
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
CBA
WU ID PU ID Work Unit or Planned Unit Label127 Identify suppliers for bzh-kite storage bags128 Prepare specification for bzh-kite storage bags129 CFT/award contract for bzh-kite storage bags130 Design UG & SI for bzh-kite131 Identify suppliers for bzh-kite UG & SI publishing132 Prepare specification for bzh-kite UG & SI publishing133 CFT/award contract for bzh-kite UG & SI publishing 029 Perform tests of pre-series bzh-kite 030 Define/design equipment for bzh-kite final assembly processes 031 Install bzh-kite manufacturing/assembly facility equipment 032 Refine bzh-kite manufacturing/assembly processes 033 Refine bzh-kite manufacturing/assembly quality assurance processes134 Train bzh-kite manufacturing/assembly facility work force 034 Commission bzh-kite manufacturing/assembly facility
The list ofActivities
(~Work Units)level n
> Work packages = level 1 of the Work Breakdown Structure
> Activities = the leaves ( ) of the WBS (from level 2 to level 6 max.)
> There is no requirement to have all activities at a same level!
Coordination Planning & Schedulingq Identifying the project activities Ú analytical approach
the Project
the WorkPackages
Sub-WP'sor CWP's
(Contractor WP)
level 0
level 1
WBS
Coordination Planning & Schedulingq Identifying the project activities Ú analytical approach
WorkBreakdownStructure
ProductBreakdownStructure
PBS RBSWBSGenericActivities
ResourceBreakdownStructure
BoM
Bill ofMaterials
List ofActivities
Project Breakdown Structure
OrganisationalBreakdownStructure
OBS
to be movedto facility, itemand/or assetmanagementsystems afterthe project iscompleted
CBS
CostBreakdownStructure
w Identifying the resources available, estimating the resources requiredCoordination Planning & Scheduling
2=! Identifying the resources that are available
The Resource Breakdown Structure (RBS)
2=@ Estimating the resources that are required
See section dedicated to Project Costing
2=# Assigning resources to activities
The RACI Matrix
2 types of resources
Renewableresources
Non-renewableresources
w Identifying the resources available, estimating the resources requiredCoordination Planning & Scheduling
2=# Assigning resources to activities Ú RACI Matrix
RBS
List
of
acti
viti
es
RIs required
XExecutes
FFollows up
IIs informed
HProvide help
for each cell of the matrix, resourceimplication is elicited
w Identifying the resources available, estimating the resources requiredCoordination Planning & Scheduling
2=# Assigning resources to activities Ú RACI Matrix
RIs required
XExecutes
FFollows up
IIs informed
HProvide help
XIs responsible
F
X
F
X
F
Participateto decisions
X
F
I
H
X
F
I
H
X_
F_
I-
H_
Only one per row
w Identifying the resources available, estimating the resources requiredCoordination Planning & Scheduling
2=# Assigning resources to activities Ú RACI Matrix
XIX
F XI I
II
RFFF
XX
I I
II I RFFF
XX
XI
XF
XXXXH
HII H
RBS
List
of
acti
viti
es
The purpose of this RACImatrix is twofold:
1. identifying the required resources (‘X’,‘R’ and sometimes ‘F’ and ‘H’)
2. organizing information circulation (mailing lists)
MicrosoftExcel spreadsheet
®
®
3=! Estimating the duration of the activities
Defining technical constraints between activities3=@
If required, defining resource constraints3=^
If required, defining temporal constraints3=$
Coordination Planning & Schedulinge Scheduling the activities
If required, getting rid of loops3=#DSM (Design Structure Matrix)
Calculating earliest/latest start/finish dates, floats + critical path(s)3=%PDM (Precedence Diagramming Method) + Gantt Chart
RCPS (Resource-Constrained Project Scheduling) + Gantt Chart
Calculating (earliest) start/finish dates and floats3=&
Project CostingA three-step process
q Estimating the resources required to perform the project
w Budgeting the resources allocated to the project
The (project) Cost Estimate
The (project) Budget Document
FINALIZECOMMISSIONBUILDDESIGNSTUDYINITIALIZE
Initiators
Project CostingWhen and which effort?
Preliminary Cost Estimate (study + project) preparation
Budget Document (re)validation
Project Board
Cost Estimate (project) refinement/update
Study Team
Cost Estimate + Budget Document updatesProject Team
Initial Budget Document (study + project) preparation
Budget Document (project) refinement/update
Project Costing
4 families of cost estimating approaches
Globalapproaches
Modularapproaches
Detailedapproaches
q Estimating the resources required to perform the project
the project is analysed as a whole estimates donefor each activity
top-downanalogical
parametric(Cost Estimation
Relationship)
bottom-upanalytical
Intuitiveapproaches
rules-of-thumb
Project Costingq Estimating the resources required to perform the project
DECOMMISSIONOPERATE & MAINTAIN
FINALIZE
COMMISSIONBUILDDESIGNSTUDYINITIALIZE
t
incomes
expenses
Which costs (and incomes) to take into account??
projectfront-end
costs
operations andmaintenance
costs
dism.costs
development costs
Project Costingq Estimating the resources required to perform the project
Which costs to take into account??
Services
Renewable resources
RESOURCES
Tooling
Vehicles
Space
Equipment*
EquipmentParticipantsInternal
External*
External*
Goods In-kindboth
Equipment
Financial
Non-renewable resources
Goods
Services
both
UtilitiesWater
Sewage
Energycontractsagreements
workload currency(person∙week, person∙month, etc.)
monetary currency(CHF, EUR, GBP, USD, JPY, etc.)
Project Costingq Estimating the resources required to perform the project
Which costs (and incomes) to take into account??
Only chargeable costs shall be considered !]
Cash flows that are distorded (i.e. suppressed or modified)]
Cash flows that are generated by the project]
Past or irrecoverable costs: no!]
Renunciation costs: yes!]
Unquantifiable costs: no!]
Cash flowsof the project =
Cash flowsof the organisation
with the project−
Cash flowsof the organisationwithout the project
These costs will existwhatever the decision
E.g. the consequence of stoppinga project that is already on-going
Benefits sometimesreplace incomes
Project Costing
Global approaches
q Estimating the resources required to perform the project
1=! Estimating with global approaches
Linearregressions
Chiltonlaw
Freimanprinciple
Distanceweighing
and from tables
Project Costingq Estimating the resources required to perform the project
Dealing with price escalation?
weighing coefficients so that:
where
appropriate economical indices
Project Costingq Estimating the resources required to perform the project
Dealing with price escalation?
Project Costingq Estimating the resources required to perform the project
Dealing with location factors?
Project Costingq Estimating the resources required to perform the project
1=@ Estimating with modular approaches
Project cost as a function of several sizing parameters:
Software:
TruePlanning® [PRICE System] (www.pricesystems.com)>
where are the sizing parameters
Cost+ [3f] (www.3f-fr.com)>COCOMO for IT projects (csse.usc.edu)>
Handbook:
ISPA (International Society of Parametric Analysts)Parametric Estimating Handbook (www.ispa-cost.org)
Project Costingq Estimating the resources required to perform the project
DECOMMISSIONOPERATE & MAINTAIN
FINALIZE
COMMISSIONBUILDDESIGNSTUDYINITIALIZE
t
incomes
expenses
1=# Estimating with detailed approaches
projectfront-end
costs
operations andmaintenance
costs
dism.costs
development costs
PBS WBS
does not exist that muchin scientific facilities!
does not exist that muchin scientific facilities!
past andirrecoverable
costs
past andirrecoverable
costs
Project Costingq Estimating the resources required to perform the project
DECOMMISSIONOPERATE & MAINTAIN
FINALIZE
COMMISSIONBUILDDESIGNSTUDYINITIALIZE
Which accuracy can be obtained??
FeasibilityStudy
OpportunityStudy
BasicDesign
DetailedDesign
Global Modular Detailed
±30% ±20% ±10% ±5%
ConceptualStudy
OpportunityStudy
SystemDesign
DetailedDesign
Global Detailed
±30% ±20% ±10% ±5%Detailed
Process industry projects
New product development projects
imprecision ≠ uncertainty!
deterministicnature
probabilisticnature
Project Costingq Estimating the resources required to perform the project
DECOMMISSIONOPERATE & MAINTAIN
FINALIZE
COMMISSIONBUILDDESIGNSTUDYINITIALIZE
How to deal with interest rates and future price escalation??
cost of money ≠ price escalation!
interest rates(financial concept)
inflation(economical concept)
All CF’s shall be set as if they were paid now!]
t2019now
In Cost Estimate and Budget, all figures in CHFnow
E.g. a payment to occur in 2019
± kCHF
± p·yr
Cost EstimateEditorial Process
Verification:> Some other Key Study (or Project) Participants+ some experts in the fields
> Authoring: Study (or Project) Manager+ a few Key Study (or Project) Participants
Validation:> Study (or Project) Manager
Typical Content
The figuresand theiraccuracy
The approach used (global, modular, detailed)The assumptions (incl. sourcing of economicalrates and indices)
A comprehensive
cost breakdown
is appreciated!
Project Costingw Budgeting the resources allocated to the project
BudgetDocument
CostEstimate
± kCHF
± p·yr
whichbecomes
kCHF
p·yr
#748
TAB orTotalAllocatedBudget
– +Logically:
MicrosoftExcel spreadsheet
®
®
Project Costingw Budgeting the resources allocated to the project
BudgetDocument
kCHFp·yr
#748
TAB orTotalAllocatedBudget
BAC orBudget atCompletion
PMR orProjectManagementReserve
WBSCBS Cost
BreakdownStructure
or
Budget DocumentEditorial Process
> Verification:
at CostCenterlevel
at WorkPackagelevel
Project Board
Project Manager
> Validation:
Some other Key Study (or Project) participants+ some experts in the field
> Authoring: Study (or Project) Manager+ a few Key Study (or Project) Participants
Study Manager
10 towers made of 8 bricks each of different colours and sizesTowers linked by 10 thin bricks
the ugly castle project
Searching for a brick of the right colour and size 5 secondsAdding a brick to another one or to an assembly 3 secondsPlacing an assembly on the green plate 6 secondsUnit prices of a brick & of a building plate 0.50 $ & 5.00 $Manpower costs 0.05 $/seconda = 7.15b = 0.53Figures from past projects
Chilton law
10 towers made of 8 bricks each of different colours and sizesTowers linked by 10 thin bricks
Your task: estimatingthe cost of this projectby various means
10 towers made of 8 bricks each of different colours and sizesTowers linked by 10 thin bricks
the ugly castle project
Searching for a brick of the right colour and size 5 secondsAdding a brick to another one or to an assembly 3 secondsPlacing an assembly on the green plate 6 secondsUnit prices of a brick & of a building plate 0.50 $ & 5.00 $Manpower costs 0.05 $/seconda = 7.15b = 0.53Figures from past projects
Chilton law
10 towers made of 8 bricks each of different colours and sizesTowers linked by 10 thin bricks
Your task: estimatingthe cost of this projectby various means
120100806040200
$
# bricks20 40 60 80 100 120 140
10 towers made of 8 bricks each of different colours and sizesTowers linked by 10 thin bricks
the ugly castle project
Searching for a brick of the right colour and size 5 secondsAdding a brick to another one or to an assembly 3 secondsPlacing an assembly on the green plate 6 secondsUnit prices of a brick & of a building plate 0.50 $ & 5.00 $Manpower costs 0.05 $/seconda = 7.15b = 0.53Figures from past projects
Chilton law
10 towers made of 8 bricks each of different colours and sizesTowers linked by 10 thin bricks
Your task: estimatingthe cost of this projectby various means
120100806040200
$
# bricks20 40 60 80 100 120 140
10 towers made of 8 bricks each of different colours and sizesTowers linked by 10 thin bricks
the ugly castle project
Searching for a brick of the right colour and size 5 secondsAdding a brick to another one or to an assembly 3 secondsPlacing an assembly on the green plate 6 secondsUnit prices of a brick & of a building plate 0.50 $ & 5.00 $Manpower costs 0.05 $/seconda = 7.15b = 0.53Figures from past projects
Chilton law
10 towers made of 8 bricks each of different colours and sizesTowers linked by 10 thin bricks
Your task: estimatingthe cost of this projectby various means
120100806040200
$
# bricks20 40 60 80 100 120 140
Project ManagementWhat are we going to see together?
Project Team
Study Team
InitiatorsProject Board
ProjectManager
Lifecycle
Roles
Study Leader
Project Stakeholders
FINALIZECOMMISSIONBUILDDESIGNSTUDYINITIALIZE
Processes
ProjectRoadmap
ProjectProposal
ProjectMngt Plan
Coord.Schedule
ProgressReport(s)
WBS& RACI
ArtefactsLaunching a project
Finalizing a project
Ensuring quality
Reporting progress
Defining requirements
Handling issues
Managing risks
Planning & schedulingCosting
Reqts.Register
RiskRegister
Budget
PBS
CostEstimate
Close-outReport
IssueRecord(s)