Managing Kuwait Oil Fields Reconstruction Projects
-
Upload
independent -
Category
Documents
-
view
3 -
download
0
Transcript of Managing Kuwait Oil Fields Reconstruction Projects
2
Managing Kuwait OilFields Reconstruction ProjectsMehdi Adib, Bechtel
Corporation PMI Canada
Proceedings, 1994, pp. 184-90
INTRODUCTIONhe Iraqi invasion of Kuwait cook place in
August of 1990 withTthe liberation in February 1991 following the
Gulf War. Almost all of the country's oil
production facilities suffered extensive damage.
The Kuwait Oil Company's (KOC) oil field
reconstruction project that was planned,
executed, and managed by Bechtel International
was actually conceived in November 1990 in
London, England. Planning and organizing the
reconstruction of the oil facilities continued
throughout the war in London, Houston, San
Francisco, Dubai, and Riyadh. This was during
the occupation but prior to the liberation. No
one knew at that time what the true magnitude of
the work would be; however, some casks could be
identified and front-end planning and
procurement for these tasks started immediately.
3
The scope of the restoration work was obviously
increased tremendously by the damage incurred
from the oil field fires that started at the end
of the war.
Bechtel project management personnel arrived
in Kuwait on March 4,
1991,three days after the allied troops had
completed their initial sweep of Kuwait City.
The main objective of this team was to organize
and manage the fire-fighting effort, This phase
of the project was named Al-Awada (Arabic tor
return).
The vivid scenes shown by the newspaper,
magazine, and television reports came alive for
Bechtel project personnel. The days were dark
with smoke from the fires blocking the sun, oil
droplets tilled the air, clean water and
sanitary systems were not working, power plants
were down, transportation was minimal as tires
were a precious commodity, and food was very
scarce, initial accommodation was in refurbished
ship quarters and in some vandalized apartment
complexes without water and electricity, no more
than a foam mattress on the floor, and a long
hike up a darkened staircase. In addition to
these problems, booby traps, land and water
mines, unexploded shells and rockets, and other
ordnance had littered the country. The temper-
4
atures in summer consistently were above 50° C
in shade (seldom below 37° C at night], exposing
the people in the field to temperatures of 55-
58° C in many locations, and hotter nearer to
the fires. Just providing drinking water was a
major undertaking. John Oakland, senior vice
president of Bechtel Corporation, who served as
the manager of projects in Kuwait, remarked,
"This campaign, which was well covered by the
international news media, was one of the most
complex engineering and construction efforts in
history (1)." However, the following assignment,
which was the reconstruction of the
Planning
Kuwait oil fields, was an even bigger and more
challenging task. The project management of the
oil production facilities reconstruction, which
was named Al-Tameer (Arabic for rebuild), is the
su6[ect of this report.
Status of tiie Facilities
The state of the two million bpd oil export
industry in Kuwait after the completion of the
fire-fighting effort was as follows:
• Six-hundred-forty-seven wells had burned in
total, 751 wells were damaged.
• Twenty-six oil gathering, separation, and
production centers were damaged or totally
5
destroyed.
• One marine export facility and its related
single point mooring was totally destroyed, and
the second marine export facility was partially
damaged and out of commission.
• The equivalent of ten million barrels of crude
oil storage tankage had been destroyed.
• The Shuaiba refinery was totally destroyed.
» A crude unit in the Mina Al Ahmadi Refinery
was completely destroyed. The rest of the
refiner}' was partially damaged and the refinery
was out of commission.
• The Mina Abdullah Refinery was partially
damaged and the units were not operable.
• All communication towers and networks were
destroyed.
• Most of the working population had either fled
or were in hiding.
AL-TAMEER PROJECT
After the successful completion of the fire-
fighting effort, KOC invited Bechtel to present
its plan for the reconstruction of the oil
fields production and exporting facilities
damaged during the war, starting work by
November
1990. KOC's goal was to be able to produce 2
million bpd of oil by September
6
1992.
PLANNING AND ORGANIZATION
The planning and organizing effort for the Al-
Tameer project started with the Bechtel team
that was already on-site as part of the Al-Awada
project fire-fighting effort.
An organization totally different from the
Al-Awada project was required to scope,
estimate, plan, execute, and turn over
operational facilities to KOC. This organization
had to be self sufficient and be able to fully
support and service a massive work force of more
than 16,000 people.
The main organization was divided into five
main functions. One was to support KOC's future
five-year budget planning with identification,
scoping, and planning future projects. This was
named KOC Major Projects Group. The other four
groups consisted of:
• manager Al-Tameer projects, responsible for
all planning and project management, as well as
engineering and procurement
• manager coordination, responsible for
scheduling, cost control, estimating, project
reporting, public and community relations, and
other relevant functions
• manager services, responsible for providing
7
all the required support services for the
project team including explosive and ordnance
demolition group
• manager operation, responsible for field
execution of all the defined work.
A damage assessment and scoping team
consisting of engineers, planners, and
estimators walked every foot of the oil fields
production and exporting facilities preparing a
scope of work, cost estimate, a plan and sched-
ule of work for each facility.
The planning was based on a back to front
scheduling defining the dates and production
goals first, working backward to see when the
drilling effort and facilities reconstruction
work had to start to meet this goal. This ap-
proach also determined the required manpower and
helped with direct hire and subcontracting
plans.
The overall plan defined the sequence of the
work and prioritized the resources to make sure
facilities with least damage were first priority
for completion.
The master schedule was developed based on
nine subproject organization work breakdown
structures ;WBS]:
• oil recovery
• tankage south
8
• North Kuwait
• pipelines/flowlines
• power, buildings, cathodic protection
• marine facilities
• desalters
• South gathering centers
• West gathering centers.
Each subproject having its task force,
budget, schedule, and its priority on resources
identified was headed by a project manager. The
Al-Tameer project organization chart is shown in
Figure 1.
The teams were integrated with available KOC
personnel who performed some of the project
runcttons. Each subproject team was supported by
local functional managers to provide them with
staff and resources to execute the work. The key
driver behind the plan was meeting the schedule
and the production capacity.
EXECUTION
The project execution consisted of three main
functions: detail engineering, procurement, and
construction management.
Detail Engineering
Engineering and construction teams worked very
closely during the planning phase to determine
the best and most expedient way of rebuilding
9
some of the facilities. This close collaboration
continued until construction was complete.
More than 200 designers and engineers worked
in the makeshift project offices at various
sites, with strong central support from a base
that was set up in an old war-damaged girl's
school. This was later transferred to a newly
constructed KOC engineering building.
Additionally, a team of more than
11
ANIZ
ATIO
N
200
eng
ine
ers
fro
m
var
iou
s
Bec
hte
l
reg
ion
al
off
ice
s
wor
ldw
ide
pro
vid
ed
co
n-
12
tin
uou
s
sup
por
t
and
spe
cia
liz
ed
exp
ert
ise
.
T
he
mai
n
del
ive
rab
les
of
the
eng
ine
eri
ng
tea
13
ms
wer
e
con
str
uct
ion
dra
w-
ing
s,
con
str
uct
ion
pac
kag
es,
and
mat
eri
al
req
uis
iti
ons
and
tec
hni
cal
14
bid
tab
s.
Thi
s
eff
ort
was
not
lim
ite
d
to
oil
pro
duc
tio
n
and
exp
ort
ing
fac
ili
tie
s,-
it
inc
lud
ed
15
som
e
of
the
nec
ess
ary
inf
ras
tru
ctu
re
req
uir
ed
for
the
day
-
to-
dav
op-
era
tio
n
of
KOC
.
Off
ice
16
s,
war
eho
use
s,
gue
st
hou
ses
,
emp
loy
ees
hou
sin
g,
roa
ds,
pow
er,
wat
er,
etc
.,
wer
e
all
par
t
of
17
the
sco
pe
of
the
wor
k.
B
eca
use
mos
t
of
the
ori
gin
al
dra
win
gs
and
spe
cif
ica
tio
ns
wer
e
des
tro
18
yed
dur
ing
the
war
,
fie
ld
ske
tch
es
and
mea
sur
eme
nts
had
to
be
use
d.
A
tot
al
en-
gin
eer
ing
eff
ort
19
of
450
,00
0
hou
rs
res
ult
ed
in
4,5
00
maj
or
dra
win
gs.
O
ne
tot
all
y
new
and
ful
ly
mod
ula
riz
ed
20
gat
her
ing
fac
ili
ty
(GC
-
17)
was
des
ign
ed
and
bui
lt
in
Hou
sto
n,
Tex
as,
and
shi
ppe
d
to
the
sit
es.
21
Oth
er
fac
il
i-
tie
s
wer
e
des
ign
ed
for
reb
uil
d
bas
ed
on
the
ir
ori
gin
al
con
cep
t,
but
mod
er
22
n-
ize
d
whe
rev
er
pos
sib
le.
Som
e
of
the
uni
ts
wer
e
ver
y
old
and
wer
e
upg
rad
ed
wit
h
the
mor
23
e
mod
ern
ver
sio
ns
of
the
equ
ipm
ent
ava
ila
ble
. A
mor
e
ext
en-
siv
e
use
of
dis
tri
but
ed
con
tro
l
24
sys
tem
s
and
aut
oma
tio
n
was
one
of
the
key
are
as
tha
t
was
upg
rad
ed.
Pro
cur
eme
nt
The
pro
jec
t
pro
25
cur
eme
nt
gro
up
was
est
abl
ish
ed
in
ful
l
for
ce
dur
ing
the
fir
e-
fig
hti
ng
pha
se
of
the
pro
jec
t
26
to
pro
vid
e
res
our
ces
for
tha
t
vei
y
imp
ort
ant
ef-
for
t.
In
the
Al-
Tam
eer
pha
se
the
tea
m
was
fur
27
the
r
exp
and
ed
to
sup
por
t
the
mas
siv
e
pro
cur
eme
nt
and
con
tra
cti
ng
eff
ort
tha
t
was
req
uir
ed
28
to
mee
t
the
tar
get
sch
edu
le.
In
add
iti
on,
inv
ent
ory
con
tro
l
and
war
eho
usi
ng
mat
eri
al
wer
e
als
30
Project Management Casebook
The procurement team was also responsible tor
incorporating all the material into KOC's
automated material and inventory control system.
The procurement effort driving the execution
phase was centralized, and it was divided into
three main areas:
• material management
• contracts management
• warehouse management.
Material management included purchasing,
inspection, expediting, and traffic and
logistics. Contracting included formation and
administration. Warehouse management included
central warehouses and satellite warehouses.
The procurement team had three main goals
within the project's overall objective:
« ensure the right material and resources were
available in time to meet the schedule
• maximize the use of available local resources
to assist in rebuilding the local economy
• ensure sure final warehouse inventory met
KOC's material coding and identification system.
The size and the particular nature of the
project required that the procurement team be
divided between material management—reporting to
the manager of projects—and contracts management
Project Management Casebook
31
—reporting to the manager of construction. This
arrangement facilitated the communication and
management of site contractors' work with
Bechtel's direct hire construction work.
Material Management
Project managers were responsible tor
development and processing of the material
requisitions for their areas of responsibility.
Orders over 5100,000 required further approval
by KOC's manager of the Al-Tameer project.
Almost everything required for the execution
of the project had to be imported from outside
the country. At the early phases of the project
the port facilities, custom facilities, and
other services required for the proper impor-
tation of goods and services were not
functioning. Bechtel established a staging area
in Jebel All port of Dubai (UAE) to receive,
inspect, and accept material. Utilizing much
smaller vessels and boats, Bechtel then
transported goods from Dubai to various Kuwait
ports depending on availability and cargo size.
This plan aiso included most of the air
freighted material.
Because timely delivery of the material was
critical to meeting the project schedule, a very
detailed material requisitioning plan had to be
developed identifying every required detail.
This plan was then incorporated into Bechtel's
worldwide Procurement Tracking System (PTS) that
enabled all Bechtel offices to monitor and
follow through each order until it reached the
site.
At later stages of the project when Kuwait
ports and custom facilities became functional
the above arrangements were changed and
everything was imported directly into Kuwait.
During this period more than 26,000 purchase
orders were issued, and more than 520,000 tons
of material were imported utilizing 742 aircraft
and sea-going vessels.
Warehousing Management
One of the key activities of the warehousing
management team was to incorporate the variety
of material that was left behind after the war
and the fire-fighting phase with newly ordered
and engineering-specified material. Also, by
continuously adjusting and monitoring quantities
and specifications they could respond very
quickly to emergency and out-of-schedule cir-
cumstances.
The engineering and warehouse both utilized a
Project Management Casebook
33
common software (PCMC) to identify, locate, and
quantify most of the bulk material making sure
that when the material was required it would be
made available immediately.
Contract Management
Although due to scheduled requirement
reconstruction of some of the flow line, all of
the gathering centers and booster stations were
performed by Bechtel direct hires, nevertheless
more than 300 major construction contracts and
650 equipment rental agreements were issued by
the contract management team during the Al-
Tameer project phase.
The contract formulation team worked as a
central group serving all subprojects. The
contract administration group managed the
administration work more by function than by
area. Project managers were ultimately the
responsible parties tor the contractor work m
their areas, receiving the necessary support and
services from these two centralized teams.
Construction Management
Al-Tameer was probably one of the most
challenging construction projects ever managed
by Bechtel. The work required provision of
labor, equipment, and support facilities in
fifty-five locations and in four different parts
of the country—North fields, South ¡marine
facilities and refineries), West fields, and
Burgan fields.
The work involved construction of drill pads;
roads for heavy rig transportation; well heads;
flow lines,- gathering centers; gas booster
stations; oil storage tanks; water supply,
distribution and storage; and marine exp on ter-
minal and loading facilities. In addition, KOC's
own infrastructure—offices, housing, clubs and
restaurants, warehouses and buildings,
telecommunication, etc.—had to be reconstructed.
Construction efforts were divided between
direct hire construction and subcontracted work.
The total scope of work was divided into nine
construction areas, each managed by a field
superintendent. Each superintendent was
responsible for both direct hire execution as
well as field administration of the
subcontractor's scope of work within his area.
Construction superintendents were supported by
the central construction group that was the
functional group supporting a project matrix
team. Prioritization of resources and
construction equipment was one of the major
Project Management Casebook
35
functions of the central construction team.
Field construction teams were comprised of
multinational forces (from thirty-six countries)
with totally different cultures, languages, and
performance capabilities. Catering and other
cultural requirements had to be addressed to
ensure each group could perform its function
satisfactorily.
Each task had to be "tailor made"
to suit the team available. It was im-
portant that planning of the manpower
and resources take into consideration
availability of the right foreman and
support group to be able to com-
municate and perform work with each
team.
SUMMARY
Approximately 1,000,000 hours in the
regional offices and 4,000,000 hours
in Kuwait were spent for project
management/engineering/construction
management during the first two phases
of this project. Field labor hours
were 50,000,000.
These project manhours were spent
within the following project schedule
milestones:
• start of planning November
1990
• start implementation in Kuwait March
1991
• project completion June 1993.
The sources of the project
personnel were various. A total of
L6,000 workers from thirty-six
countries on five continents were
involved in this massive effort. The
countries that participated in the
supply of manpower to this
reconstruction included Kuwait, the
United States, Great Britain, Canada,
France, Australia, Belgium, Holland,
Germany, Ireland, New Zealand, Mexico,
Saudi Arabia, Egypt, [ran, Lebanon,
Bahrain, Yugoslavia, Colombia,
Indonesia, Nigeria, Bangladesh,
Brazil, Afghanistan, the Philippines,
India, Djibouti, Sri Lanka, Somalia.
Syria, Tanzania, Thailand, Tunisia,
Pakistan, Trinidad, and Sierra Leone.
Project Management Casebook
37
ACCOMPLISHMENTS
• The work was conducted in fifty-five
locations that included fields in the
north of Kuwait on the border with
Iraq, west and south of Kuwait on the
borders with Saudi Arabia and Iraq,
and in the refineries and loading
facilities along the coast and
offshore.
• Five hundred square miles of land
were swept and cleared of unexploded
ordnance. More than 23,000 pieces of
explosive devices were destroyed by
explosive ordnance disposal teams.
Although all work areas were swept,
the risk from undetectable ordnance
was ever present and some fatalities
did occur.
• More than 26,000 purchase orders and
300 major construction contracts and
650 equipment rental agreements were
awarded during Phases I and II of the
project. [A more normal project
performed over the same time frame may
have 4,000 to 6,000 purchase orders.)
• A complete communication system
dedicated to the oil industry was in-
stalled that included twenty-three
satellite telephone systems, 4,500
telephones, and 2,000 portable radios.
• A twenty-four-hour health care and
safety program was established that
included two helicopter medivac teams,
a forty-bed hospital, a dental clinic,
and a team of approximately 100
professional medical personnel on duty
at seven medical stations.
• More than 5,800 pieces of field
operating equipment ranging from the
larger bulldozers, cranes, trucks,
front-end loaders, and heavy
industrial
equipment to ambulances, pickup trucks, cars,
buses, and other support vehicles were shipped
to the job sites. These pieces of equipment were
purchased from twelve different countries.
• A total of 742 aircraft and sea-going vessels
were deployed to ship more than 520,000 tons of
equipment and material to Kuwait in support of
this project.
• Six full-service dining halls with catering
support staff provided about 3,500,000 meals for
Project Management Casebook
39
the workers during the fire-fighting campaign
and
10.0. 000 meals during the reconstruction
phase. Menus were established to cater to the
different ethnic backgrounds.
• Provisions and housing for 12,000 manual and
2,000 non-manual Bechtel employees were
provided. All of the members of project
management and their support teams, over 200
design and engineering personnel and about 200
procurement, administration, and subcontracts
management teams, were resident in Kuwait.
• Construction of a number of permanent offices,
workshops, warehouses, maintenance shops, and
housing complexes for KOC was completed at the
same time.
• Fire-fighting efforts originally involved the
four major international teams of Boots & Coots,
Red Adair, Safety Boss, and Wild Well Control.
They were later joined by an additional twenty-
three teams from Kuwait, Iran, China, Hungary,
Great Britain, France, Canada, Romania, and
Russia.
• Four hundred kilometers of water and oil
pipelines were installed during fire-fighting
efforts. Water lines and pumping stations could
deliver
25.0. 000 gallons a day to fire sites. Each
of 360 lagoons was excavated, lined, and filled
with 1,000,000 gallons of water for use in fire-
fighting.
• Drilling pads and access roads were
constructed for 700 new and workover wells.
• Three-thousand kilometers of new flowlines were
constructed.
• One-thousand kilometers of new and refurbished
pipelines were installed.
• Fifteen crude gathering centers, including a
totally new and modularized early production
facility, were assessed, designed, and
constructed.
• Three gas booster stations were constructed
• Restoration and reconstruction of the marine
loading terminals, offshore terminals, and SPM
were completed.
• Construction of more than 10,000,000 barrels
of new crude oil storage tankage was managed.
• Restoration of overhead and underground
electrical power transmission and distribution
system and cathodic protection system within the
oil fields was completed.
• Construction/repair and operation of water
Project Management Casebook
41
systems jfresh, brackish, and salt water) were
completed.
• Construction and operation of oil recovery
systems and facilities that collected and
treated more than 25,000,000 barrels of
weathered crude were completed.
KEY MILESTONES
Some of the more notable milestones in
the program were:
• The last fire was extinguished and
the well was capped on November 6,
1991, eight months after the
arrival of the first Bechtel team on-
site.
• The first postwar oil was pumped
from two of the original gathering
centers on May 26, 1991.
• By December 1991, more than 400,000
barrels of oil per day were being
produced from the rehabilitated
facilities.
• By April 1993, more than 11,000,000
barrels of weathered crude had been
reclaimed from oil pits and lakes, and
processed through the held treatment
centers and the refinery.
• By the end of fune 1993, eighteen of
the original centers were back in op-
eration, with all the production goals
achieved as scheduled.
REFERENCES
1. Oakland, J.A. 1994. "Al-Tameer:
The Reconstruction at Kuwait." PM Net-
work, May, pp. 14-21.
Study Questions
MANAGING KUWAIT OIL FIELDS RECONSTRUCTION PROJECTS
1. This project was a major
undertaking. The challenges it faced
ranged from providing the basics for
being able to live in the desert
¡water and shelter] to finding
creative methods for getting imports
into the country through non-
traditional routes. From the author's
point of view, the project went rather
smoothly. To which factors do you
attribute the success of this project?
Project Management Casebook
43
2.This case describes an enormous
undertaking made up of many different
projects. Which of these projects can
be considered the most important? Why?
3.One of the regular outputs of the
development of the project plan is the
work breakdown structure. Define the
work breakdown structure and its
benefits.
4.How were the multinational
relationships handled in this project?
5.This project was handled by the
Bechtel Corporation, a private
company, and not the Kuwaiti
government. List some of the
advantages to this project being
handled privately and not publicly.
6.Figure 1 shows the organization
chart of the Al-Tameer project. What
kind of organization does this
represent?