Integrated Project - Report
Transcript of Integrated Project - Report
BSc (Hons) Quantity Surveying and Construction Management
INTERGRATED PROJECT
26-6701-00S
ANPUVARUNAN.T
Student ID-23044807
SHU SL BATCH-06
05.01.2014
INTERGRATED PROJECT
BSC (HONS) IN QS & CONSTRUCTION MANAGEMENT
ACKNOWLEDGEMENT
First of all I would like to thank to god whose blessing had brought me here, further thank to
my parents, brothers, and my friends for their encouragement and guidance. As a student, I
would like to thank almighty to Mr. Ravihansa Chandrathilake who is our integrated project
lecturer; he has provided enough knowledge and proper understanding about this subject,
thus helpful to me to finish my assignment properly.
Moreover my thanks to Sheffield Hallam University to offer this degree program in Srilanka
through ICBT, thus giving an opportunity to me and other students study in my home
country.
Finally I thank all colleagues and ICBT staff who helped me to complete this assignment
report successfully.
ADVISING THE CLIENT ON
GBCSL & LEED
To
Garment Manufacturing Factory
In
Hambantota (Southern Province)
Date -05/01/2014
INTERGRATED PROJECT
BSC (HONS) IN QS & CONSTRUCTION MANAGEMENT Page I
EXECUTIVE SUMMERY
Advising the client is a significant matter of consultant in construction projects according
with green building concepts. Because nowadays construction of industrial buildings with
working environmentally sustainable and economically is the most challenging issues in all
over the world. The main purpose of this report is to advising the client to implement green
concept for the proposed garment manufacturing factory with green building concept to
working with environmental sustainable and economical operation.
Further in this report the client advised with all required categories, prerequisite and credits
according to GBCSL and LEED for achieving gold rating with key concerns of Efficient and
pleasing working environment, use 100 % solar power for the operation, minimum
disturbance to the existing ecology, water treatment and solid waste management, high safety
and hygienic environment to achieve certain point under each category.
.
INTERGRATED PROJECT
BSC (HONS) IN QS & CONSTRUCTION MANAGEMENT Page II
TABLE OF CONTENTS
Executive summary……………………………………………………….…...…..………….II
List of figures……………………………………………..…….………………..……..……III
List of table…………………………………………………...………………..……..………III
Introduction………………………………………………..………………...……………….01
Green building………………………………………………………...……..……………….02
Rating system……………………………………………………………...…………….…...02
Key concern for gold rating by category
1. Sustainable Sites …………………………………………………….……………….04
2. Water Efficiency ………………………….…………………………………..…..…05
3. Energy and Atmosphere ……………………………………………..………...…….05
4. Materials and Resources ………………………………………………...………..…06
5. Indoor Environmental Quality …………………………….…………...………….…07
6. Innovation and Design Process ………………………………………...……………07
7. Management …………………………………...…………………………..……...…08
8. Social and Cultural Awareness & Regional priority …………………………..……08
Conclusion and recommendation…………..………………………………………………. 09
Reference & Bibliography………………….…………………………………………….…10
INTERGRATED PROJECT
BSC (HONS) IN QS & CONSTRUCTION MANAGEMENT Page III
LIST OF FIGURES
Figure 01-Site location………………………………………………………………………04
LIST OF TABLE
Table 01- Point system by Categories of GBCSL and LEED ………………………….…..03
Table 02- Rating by required points of GBCSL and LEED ……….…………………….…..03
INTERGRATED PROJECT
BSC (HONS) IN QS & CONSTRUCTION MANAGEMENT Page 1
INTRODUCTION
In the consultant’s view advising the client is very difficult part, because it should meet all
requirements and economically. According to task, client is an overseas investment company
and planning to build garment manufacturing factory in southern province of Srilanka in ten
acres faces the sea. Furthers design has to be green project and intends to achieve gold rating
in LEED and GBCSL.
I act as green consultant and have to prepare a comprehensive report on what need to be
concerned to get gold rating. So intention of this report is to advise the client to achieve gold
ratings in LEED and GBCSL with prerequisites and credits.
INTERGRATED PROJECT
BSC (HONS) IN QS & CONSTRUCTION MANAGEMENT Page 2
GREEN BUILDING
In the present era due to greenhouse gases from activities of individual, leads to climate
changes breads the atmosphere heat drastically resulting in global warming and facing too
many global issues and threat the human beings and living things in this world (Center for
Climate and Energy Solutions 2011).
Green building is significant concept in the construction industry nowadays which
constructed by utilizing key resources like energy, water, materials, and land with more
effectively than structures that are constructed just to code. With better natural air and light,
green structures normally help enhanced users health, comfort, and enormous productivity
while diminish the environmental effect and operation cost (Kats and Capital 2003).
GBCSL
Green building council of Sri Lanka (GBCSL) is a national non profitable agreement based
organization, has a goal of change the Srilankan construction industry with efficient green
building practices (Green Building Council of Sri Lanka 2013).
LEED
Leadership in energy and environmental design (LEED) is a confirmation program of U.S
Green building council and goes about as broadly acknowledged association for design,
construction, operation, and maintenance of high execution green buildings (U.S Green
building council 2013).
Rating system for green building
Most of the categories have credits and some has prerequisites as required in both GBCSL
and LEED systems. Each system having of 100 points, GBCSL the points are divided into 8
categories and LEED 2009 in it divided in to 7 categories.
INTERGRATED PROJECT
BSC (HONS) IN QS & CONSTRUCTION MANAGEMENT Page 3
Categories Points at GBCSL Points at LEED
Sustainable Sites 25 26
Water Efficiency 14 10
Energy and Atmosphere 21 35
Materials and Resources 21 14
Indoor Environmental Quality 13 15
Innovation and Design Process 4 6
Management 4
Social and Cultural Awareness 3
Regional priority 4
Table 01- Point system by Categories of GBCSL and LEED
Ratings GBCSL LEED
Certified 40–49 points 40–49 points
Silver 50–59 points 50–59 points
Gold 60–69 points 60–79 points
Platinum 70 and above points 80 and above points
Table 02- Rating by required points of GBCSL and LEED
Site location
As per the client need site selected in Hambantota in Southern Province area by covering
approximately 10 acres faces the sea.
INTERGRATED PROJECT
BSC (HONS) IN QS & CONSTRUCTION MANAGEMENT Page 4
Figure 01- Site location (GOOGLE MAPS 2013)
Requirements for gold rating
According to client’s need this factory has to be built for gold ratings so it must be achieved
the credit point 60-69 and 60 -79. Following are advises for client with some key concerns to
achieve gold rating by gaining required points from GBCSL and LEAD.
1) Sustainable Sites
As per client’s need particular site is nearby high way, harbor, and Hambantota International
airport so transportation, commercial and emergency services are available and site was
previously used for storage plant for road construction. Moreover company transportation and
underground parking should be implemented for all factory workers to minimize parking area
and maximize open spaces for future development, thus prevent vehicle’s corrosion from sea
wind.
INTERGRATED PROJECT
BSC (HONS) IN QS & CONSTRUCTION MANAGEMENT Page 5
Roof tops are recommended to shade up with solar panel installation to reduce heat
absorption, further recommend minimizing deforestation, planting trees and vegetated land in
ground and roof surface to reduce disturbance of existing ecology and inhabitants by heat
absorption and radiation.
The lighting system should be provided only for necessary place at nights with angle spot
lights with CFL brand for energy efficient and reduce heat emission and light pollution.
Further an erosion and sedimentation control plan must be done during designing period.
Erosion control blankets and stock piling must be applied to prevent soil erosion during
construction as Prerequisite.
2) Water Efficiency
This is going to be a large factory, so high amount of water will be used for factory’s function
drinking, and other essentials needs. Waste water tank should be built attached with
anaerobic based efficient water treatment plant and it should be implemented at site for
collecting waste water from lake which situated near site, storm water, factory’s function
(dying and washing).
Also a separate tank should be built to collect pure rainwater under act of Lanka Rain Water
Harvesting Forum it could be used to mainly drinking and all other essential needs. Moreover
automatic sensor faucets, waterless urinals and closets should be installed with efficient
plumbing system to reduce leakage and repair or remodeling efforts.
3) Energy and Atmosphere
Client is planning to build a large garment manufacturing factory, so huge amount of
electricity will be consumed for day to day operation and functions, so we intend to apply
100% solar power system.
Solar energy is considered as cleanest and the most abundant renewable energy source and
this is the most efficient system become apparently in present era all over the world than
other renewable energy source such as wind power, hydropower, and bio gas, etc. There are
three types of solar technology used vastly such as Photovoltaic (PV), solar heating &
cooling (SHC), and Concentrating Solar power (CSP) (SEIA 2103). In this building PV and
INTERGRATED PROJECT
BSC (HONS) IN QS & CONSTRUCTION MANAGEMENT Page 6
CSP system solar panels are recommended to install rooftops and ground respectively to
absorb more sunlight and heat.
To optimize energy performance sun pipes are to be installed to the offices, cafeteria, lounge,
reception area, meeting room and general working area where the lights doesn’t need mostly
and CFL brands are recommended for energy efficient at night time. LED based task lights
recommended fixing to focus needle point of sewing machines to provide sufficient
lightening.
Heating, ventilation, air conditioning and refrigeration (HAVC &R) operations have to be
minimized because these are highest proportion of factors influencing to ozone depletion and
global warming so it is recommended to use reduced refrigerant charge base building
HAVC&R system in addition to use of natural air and also advice to use fire suppression
systems that do not contain ozone-depleting substances of CFCs, hydro chloro fluoro carbons
(HCFCs)
4) Materials and Resources
Previously this site was used as a big construction storage yard, so existing wood buildings,
fuel tank, carpentry yard and concrete plant, and water tank are recommended with few
renovations. Construction solid wastes are recommended to reuse with recycling and other
waste are recommended for anaerobic digestion system with Feedstock green chemical.
Considerable amounts of big trees should be removed to construct additional new building so
these trees are recommended to cut down and make every structural item such as floor and
wall finish sheets, beams and columns, doors in site carpentry yard.
Lobby and employer office areas are recommended with wool floor mats, strawboard wall
finishes, further cafeterias and relaxation areas are recommend with openings spaces by huts
use with bamboo, palm leaves and other green plants. Also waste cloths pieces can be used
for making floor mats that can be used for floor finish that minimize solid waste disposal and
management expenses.
INTERGRATED PROJECT
BSC (HONS) IN QS & CONSTRUCTION MANAGEMENT Page 7
5) Indoor Environmental Quality
Safety and hygienic environment is a major factor that influences efficient working and
production, so working environment should be kept properly. It is recommended to maintain
ventilation during working hours with efficient cooling system and construct Cafeterias and
relaxation places with openings to get more natural light and air with low emitting and less
heat absorption materials.
During working time it is necessary to provided sufficient ventilations, lights, and less
thermal heat and radiations, otherwise it will affect workers healthy thus results in
production. So efficient HAVC&R system, task lights attached with sewing machines are
recommended. While working with heavy machinery such as cutting and boiling and dying
process, safety dress and equipment regulations should be maintained properly.
Roof must be constructed with low heat absorption materials such as concert and roof tiles,
and also must be covered with solar panels and gardening. Floor finishing is recommended to
use wood seats and wool floor mats, partitions in strawboard. Wood finishes, floor coating
and painting materials are recommended with less volatile organic compound (VOC).Above
considerations help to reduce heat and radiation to provide comfort for workers. To avoid
smoking in general area a smoking room is also recommended to include during design
process with effective ventilation control according to government regulations and rules.
6) Innovation and Design Process
Client should appoint two accredited professional with GBCSL and LEED to instruct the
project team members about green building concept and processing during the design and
construction period. Thus leads to input new innovation in energy performance, water
efficiency design, and wastage manage.
As an innovative system Feedstock green chemical is recommended for anaerobic digestion
system for construction waste and sewage sludge and other entire solid and water waste to
help to reduce disposal cost and land fillings with organic matters, thus result in
environmental and public health and safety.
INTERGRATED PROJECT
BSC (HONS) IN QS & CONSTRUCTION MANAGEMENT Page 8
7) Management
Management is a significant category in the design, construction, and operation process. Here
as per prerequisite, green building accredited professionals are covered under Innovation and
Design Process in LEED. as explained before, client should utilize fewer energy consuming
machineries and equipment to high productivity such as led task lights, CFL brand lights, sun
pipes to get natural lights, solar panels, efficient HAVC&R system for energy efficiency and
all the others should be maintained and repair properly.
8) Regional priority & Social and Cultural Awareness
Regional priority is coming under LEED and is not applicable for non U.S countries so no
need to concern for this project. Social and cultural awareness (GBCSL), here client should
arrange someone to study and analyze about Archeological Sites and Heritage Buildings
statics, social and cultural detail about surrounding peoples and public health care and safety
according to this project.
INTERGRATED PROJECT
BSC (HONS) IN QS & CONSTRUCTION MANAGEMENT Page 9
CONCLUSION & RECCOMENDATIONS
According to this report, this building can be built as a green building with gold rating by
implementing all the considerations to obtain required credit points from 60-69 in GBCSL
and 60 -79 in LEED. At the same time site is near the sea, so weather forecast details should
be updated daily, especially during rainy season. Also a contingency plan must be ready
always to face accidents and natural disasters. Further all structural items and machineries
must be free from corrosion and proper shield should be maintained.
Moreover an additional electric system should be maintained to cover up any failure in the
solar power system. Health and safety, dust and noise control, and transportation must be
maintained properly during the construction to minimize the disturbance to surrounding
people and environment.
INTERGRATED PROJECT
BSC (HONS) IN QS & CONSTRUCTION MANAGEMENT Page 10
REFERENCE & BIBLIOGRAPHY
CENTER FOR CLIMATE AND ENERGY SOLUTIONS (2011). Climate Change 101. Understanding and
Responding to Global Climate Change,.
GOOGLE MAPS (2013). Hambantota, Southern Province, Sri Lanka. [online]. Last accessed 2
December 2103 at: https://maps.google.lk/
GREEN BUILDING COUNCIL OF SRI LANKA (2013). Welcome To GBCSL. [online]. Last accessed 12
December 2013 at: http://srilankagbc.org/about_gbcsl.php
GREEN BUILDING COUNCIL SRI LANKA (2010). GREENSL® RATING SYSTEM FOR BUILT ENVIRONMENT.
1-32.
KATS, Gregory and CAPITAL, E (2003). Green building costs and financial benefits. Massachusetts
Technology Collaborative Boston, MA.
LANKA RAIN WATER HARVESTING FORUM (2103). UDA (AMENDMENT) ACT NO. 36 OF 2007.
[online]. Last accessed 06 December 2103 at: http://www.lankarainwater.org/rwhsl/udaact.htm
SEIA (2103). Solar Technology. [online]. Last accessed 12 December 2103 at:
http://www.seia.org/policy/solar-technology
SRILANKA APPARAL GARMENTS WITHOUT GUILT (2103). ECO-FRIENDLY SRI LANKAN FACTORIES.
[online]. Last accessed 6 December 2103 at: http://gwg.garmentswithoutguilt.com/featured-in/50-
eco-friendly-sri-lankan-factories
STEFFEN, R, SZOLAR, O and BRAUN, R (1998). Feedstocks for anaerobic digestion. Institute for
Agrobiotechnology Tulln University of Agricultural Sciences, Viences,.
U.S GREEN BUILDING COUNCIL (2013). LEED. [online]. Last accessed 12 December 2013 at:
http://www.usgbc.org/articles/about-leed
U.S. GREEN BUILDING COUNCIL (2009). LEED 2009 for New Construction and Major Renovations
Rating System..
SITE AND LOCATION ANALYZIS
REPORT
Proposed Hospital Project
In
Colombo (Western Province)
Date -05/01/2014
INTERGRATED PROJECT
BSC (HONS) IN QS & CONSTRUCTION MANAGEMENT Page I
EXECUTIVE SUMMERY
Site and location analysis has to be done before or purchasing the land, to check suitability of
site and location according to the type of investment. This comprehensive report includes,
analysis of all significant factors relating to new hospital project in the western province at
Colombo.
This is going to be a big Hospital project, so the site and location analysis has to be done
precisely. Therefore old maps, flood potential, natural disasters, natural surface features,
cultural and manmade features, zoning & planning regulations, accessibility and commercial
function are mainly considered in analysis. Further existing buildings and significant features
in relation to demolition also took place in this report.
.
INTERGRATED PROJECT
BSC (HONS) IN QS & CONSTRUCTION MANAGEMENT Page II
TABLE OF CONTENTS
Executive
summary…………………………………………………..………...…..………….II
List of figures………………..………………………………….………………..……..……III
Introduction……………..…………………………………………………...……………….01
Site analysis……………...……………………………………………………….…………..02
Old map…………………………………….………………………………….……..02
Flood potential………..……………………….…………………………….…….….03
Natural disaster……………..…………………….…………………………….….…05
Natural surface features………………………………………………….…....….…06
Cultural and manmade features………………………………………………….….07
Condition of existing building and significant features to demolition…………………..…07
Location analysis………………………………………………….………………………….08
Zone of the area……..………………………………………….……………………09
Accessibility Analysis………….……………………..……….…………………….11
Commercial function Analysis ………………………..………….………………....11
Conclusion and Recommendation…………..……………………….……………………. 12
Reference & Bibliography ……………………………………………………….…….….…13
INTERGRATED PROJECT
BSC (HONS) IN QS & CONSTRUCTION MANAGEMENT Page III
LIST OF FIGURES
Figure 01- Old map of Colombo ……..………………………………………….…………02
Figure 02- Flooding map of Colombo district 2010 ……………………………………….04
Figure 03- Rainfall and Temperature in Colombo………………………………………….04
Figure 04- Tsunami Affected area 2004……………………………………………………05
Figure 05- Land cross section …………..………………………………………………….06
Figure 06- Proposed site location ………………………………………………………….09
Figure 07- Zoning plan 2020…...…………………………………………….…………….10
INTERGRATED PROJECT
BSC (HONS) IN QS & CONSTRUCTION MANAGEMENT Page 1
INTRODUCTION
The client is planning to build a hospital at western province (approximately with 650 rooms
and land extent appropriately ten acres. There for as consultant, I have been asked to identify
potential site and carryout a preliminary site and location analysis on behalf of client. The
selected site was a commercial complex and not in function for last 2 years due to bad
condition of building.
This report mainly analyze the suitability of cite and location to commercial function of
hospital project with some significant factors. According to this report client can decide,
whether this site is suitable for his investment and also he can identify the regulations must be
followed during the operation.
INTERGRATED PROJECT
BSC (HONS) IN QS & CONSTRUCTION MANAGEMENT Page 2
SITE AND LOCATION ANALYSIS
SITE ANALYSIS
Site analysis is a significant concern has to be done before the designing process of a
construction projects, thus helps provide overall knowledge about, which type of investment
suitable for this place, which construction methods can apply, which type of building can
build. So client can come to a decision, whether this site is suitable or not for his investment
in this place, further this analysis will help to next process of designing, construction, and
operation.
Significant factors in Site analysis
Here of old map, flood potential, other natural hazards and some significant factors have
mentioned in site analysis.
1) Old maps
Figure 01- Old map of Colombo (Sri Lanka Antique Maps 2013)
Site
INTERGRATED PROJECT
BSC (HONS) IN QS & CONSTRUCTION MANAGEMENT Page 3
Old map helps to get past details about exact site such as old mine shafts, position of ponds,
changes in topography of land, and ditches that have been filled, etc. According to detailed
study of this area old map, this site was not affected by flooding and a topography change
was not happened in the past four decades.
2) Flood potential
The site located 900 m away from sea and around 2m above mean sea level. Further there is
big lake right next to road, So the lad could suck consider amount rain water , thus helps to
reduce water stay in the site. In the past 30 years Colombo is highly affected by flooding,
while this site has not been affected, because drainage and other water ways are being
maintained properly near site area. Also the World Bank committed a financial assistance
package of US$ 213 million to Metro Colombo Urban Development Project (MCUDP) to
implement flood mitigation infrastructure and support drainage (World Bank 2013), so in
Colombo area, future flooding will be reduced by this project.
Rainfall and temperature charts
Average rainfall and temperature of Colombo area chart is given below, so it is helpful to
decide raining season and levels. October, and November time expected heavy rain and can
be clearly seen average temperature 25-30° C during the year, further wind pattern also
consider in this report helps to design of building and prepare the master programs of
construction.
INTERGRATED PROJECT
BSC (HONS) IN QS & CONSTRUCTION MANAGEMENT Page 4
Figure 02- Flooding map of Colombo district 2010 (Center for Satellite Based Crisis
Information (ZKI) 2013)
Figure 03- Rainfall and Temperature in Colombo (Department of Meteorology 2013)
INTERGRATED PROJECT
BSC (HONS) IN QS & CONSTRUCTION MANAGEMENT Page 5
3) Natural Hazards
Tsunami
In 2004 many places near the sea was affected by tsunami and sea side was mostly affected in
Colombo area, but particular proposed site was not affected badly compared to another places
near this proposed site, because the lake between the sea and the site was cause reduce the
force of tsunami waves and site situated little bit far away from sea side. For the future
consideration during the designing process tsunami should be considered.
Figure 04-Tsunami Affected area 2004 (McGill 2013)
INTERGRATED PROJECT
BSC (HONS) IN QS & CONSTRUCTION MANAGEMENT Page 6
Earthquake
Recently many slight earth quakes took places in Sothern and western Srilanka, so a recent
research conducted by James Cochran, a scientist of Doherty Laboratory in the USA has
founded a new plate forming in southern part of Srilanka. Therefore in future more chances to
observe more earth quakes (Walking the World 2013). For the future consideration during the
designing process earth quakes factor should be considered.
4) Natural surface features
The site is above two meter from sea level and also two feet height form Lake water level.
This site is near the lake, so its helps to suck out all rain waters and storm waters from all
over this site. Further there is some considerable number of trees and vegetated areas are
available in the back of this site.
The top soil type is gravel with sand and there are so many high-rise buildings situated
around the site, so this area is good for large building projects.
Figure 05- Land cross section
Moreover this area can get more sunlight and has average temperature 25-30° C, thus helps to
install the solar panels to produce electricity, also has a normal wind velocity.
INTERGRATED PROJECT
BSC (HONS) IN QS & CONSTRUCTION MANAGEMENT Page 7
5) Cultural & man made features
This site is situated developed are of Colombo cit y, so there is no big issue about water
supply, gas, electrical and other sanitary facilities and supply. Further this area is having a
vast population, high educational level, and high safety.
This site is near the town hall road, so the efficient traffic control system is being maintained
thus help to easy access for this building.
This site is situated in concentrated development zone and size is approximately 40400 m2,
so as per the regulation can go for a High Rise building.
Condition of existing building and significant features in relation to demolition
There are two buildings are in this site and one is too old and other one is not at good
condition. The front building is two storeys and the second one is single story and the both
buildings are primitive style, both were used as a shopping complex and now not in function
due to unstable of building. While study about the buildings there are so many cracks in
major structures such as columns, beams, roofs and stair case are badly damaged in the old
building. Moreover electricity, water supply systems are currently not active in both
buildings.
This is surrounded by Residential complex and having all facilities such as Banks,
commercial complex, and education institutions, so demolish existing buildings is a huge
matter, because constructing high rice is not an easy task at this place and while demolishing
noise, dust, safety, working hours and disposal should be mentioned.
INTERGRATED PROJECT
BSC (HONS) IN QS & CONSTRUCTION MANAGEMENT Page 8
LOCATION ANALYSIS
Location analysis is the most important like site analysis. Here the physical and legal
attributes will be conceded related to this project. It helps to details study about features and
resources around the location, efficient designing and demonstrate client to factors affecting
the investment as well as how to operate functions. Followings are the main purpose of this
location analysis.
Construction according to zoning and planning regulation.
Knowledge about transport and accessibility facilities
To make easy Feasibility study
Know the Economical output
Analyzing impact of environment
Helping to efficient design
details to client about location
Location Details
Proposed Site - No.243, Dr Colvin R de Silva Mawatha, Colombo-02
Existing Building- 2 stories and a single story building
Site Area- 186 x217 lm (approximately 10 acres)
Site shape- Rectangle
The propose site is approximately 10 acres and land shape is rectangular. Colombo area has a
vast population with multi cultural and the site located in the one of the main commercial
area of city Colombo. Most of surrounding building near the site is mostly for commercial
purpose and also between the Hilton Colombo residence and Zak residence. Further site
located beside one of the big road and Colombo- Moratuwa highway is about 500 meters
from this site, so suitable for goods and services transportation.
INTERGRATED PROJECT
BSC (HONS) IN QS & CONSTRUCTION MANAGEMENT Page 9
Figure 06- Proposed site location
1) Zoning and Planning Regulations (Urban Development Authoriety 2013)
According to zoning plan 2020 given below, proposed site is located in concentrated
development zone. New Hospital projects are allowed in this area according to city of
Colombo development plan 2008 under Health Institutions. Further cite size is approximately
40400 m2 and this is going to be a big hospital with 650 rooms, so as per the regulation can
go for up to high rise building (21 or above floors according to budget and soil condition),
also minimum width between building lines of road, site frontage, plot coverage, floor area
ratio is, open space around the building should be considered according to number of floors.
Further fees of processing, Covering approval, and Service Charges will be charged as per the
design.
INTERGRATED PROJECT
BSC (HONS) IN QS & CONSTRUCTION MANAGEMENT Page 10
Figure 07- Zoning plan 2020 (Urban Development Authority 2013)
INTERGRATED PROJECT
BSC (HONS) IN QS & CONSTRUCTION MANAGEMENT Page 11
2) Accessibility analysis
This is main road in front of this site with good traffic control, further site is near to
Colombo- Moratuwa highway and bus stand, also available of another transport facilities. So
people can access this site easily for emergency purpose.
3) Commercial function Analysis
This site located in commercial zone in Colombo area with vast populations, also every part
of the country peoples are coming to Colombo for their every needs including medical
treatment. Moreover tourist arrival percentage is rising rapidly due to finished of local war,
thus results to stay so many foreigners in Colombo area. So it is also an advantage to build
this large hospital with all medical facilities in Colombo area.
INTERGRATED PROJECT
BSC (HONS) IN QS & CONSTRUCTION MANAGEMENT Page 12
CONCLUSION
According to report with analysis of all necessary factors such as old maps, flood potential,
natural disasters, natural surface features, cultural and manmade features, zoning & planning
regulations, accessibility and commercial function it is recommended that this site is very
suitable for this big hospital project. So the client can invest his money in this site to Hospital
project.
Finally followings are my recommendations to achieve efficient construction and profitable
investment.
1) It is better to start the construction works in December because higher rain fall has
recorded during May to November.
2) Provide proper safety, dust and noise control, transport, night work system during the
construction to minimize the disturbance to surrounding people and environment.
3) Installation of solar power system can reduce additional electricity charges.
INTERGRATED PROJECT
BSC (HONS) IN QS & CONSTRUCTION MANAGEMENT Page 13
REFERENCE & BIBLIOGRAPHY
CENTER FOR SATELLITE BASED CRISIS INFORMATION (ZKI) (2013). Satellite map of flooded areas in
the district of Colombo, Sri Lanka, as of June 01, 2010 - Detail map 3. [online]. Last accessed 6
December 2013 at:
http://www.zki.dlr.de/system/files/media/filefield/map/medium/DLR_20100525_srilanka_flood_de
tail_colombo3_medium.jpg
DEPARTMENT OF METEOROLOGY (2013). Climate in Sri Lanka. [online]. Last accessed 8 December
2013 at: http://www.meteo.gov.lk/images/stories/Images/climate%20-%20colombo.png
MCGILL (2013). Srilanka. [online]. Last accessed 7 December 2013 at: http://www.mcgill.ca/trauma-
globalhealth/sites/mcgill.ca.trauma-globalhealth/files/images/Tsunami_affectd_areas.jpg
Sri Lanka Antique Maps. (2013). [online]. Last accessed 6 December 2013 at:
http://4.bp.blogspot.com/-
z2r2lDHEzjg/TfUICCD4qhI/AAAAAAAABrM/SpjmUgzV_5U/s1600/old_map_colombo.jpg
URBAN DEVELOPMENT AUTHORIETY (2013). City of Colombo Development Plan (Amendment) –
2008. [online]. Last accessed 8 December 2103 at: http://www.uda.lk/pdf/cmc%20regulations.pdf
URBAN DEVELOPMENT AUTHORITY (2013). Zoning Plan 2020. [online]. Last accessed 10 December
2013 at: http://www.uda.lk/images/zonning-colombo/dehiwala.jpg
Walking the World. (2013). [online]. Last accessed 7 December 2013 at: http://lmashton.com/sri-
lanka-new-earthquake-zoneearthquakes-lanka-no-longer-safe/
WORLD BANK (2013). Documents & Reports, Metro Colombo Urban Development Project :
transforming Colombo into a flood resilient middle income country capital. [online]. Last accessed 14
December 2013 at: http://documents.worldbank.org/curated/en/2013/03/17747359/sri-lanka-
metro-colombo-urban-development-project-transforming-colombo-flood-resilient-middle-income-
country-capital
INTERGRATED PROJECT
BSC (HONS) IN QS & CONSTRUCTION MANAGEMENT Page I
TABLE OF CONTENTS
Acknowledgement……………………………………………………………………………..I
List of table…………………………………………………………………………..……….II
List of figure………………………………………………………….……………..…….….II
Introduction…………………………………………………………………………..………01
TASK-03
1. Elementary cost control process for a building construction project……………..……02
2. Calculation of the allowable building costs ………………………….…………..……05
TASK-04
1. Interim valuations in post contract phase and difficulties faced during process ……08
2. Different valuation methods in property development…..……….….……….….……10
3. Life Cycle Cost analysis…………………………………..……….……………..……12
4. Contractor’s project cost control with S-curve …………..……….………………..…14
Conclusion………………………………………………………….……………….….…….16
Reference and Bibliography…………..…………………………….…………….…………17
INTERGRATED PROJECT
BSC (HONS) IN QS & CONSTRUCTION MANAGEMENT Page II
LIST OF TABLE
Table 01- Initial budget by elements …………………………………………..….…………03
Table 02- Elemental Cost Analysis of Roof .................................................................…...03
Table 03- Life Cycle Cost analysis of steel cable.............................................................…...13
LIST OF FIGURES
Figure01- Interim valuation of road project …………………………………………………09
Figure 02-Site location…….…………………………………………………………………13
Figure 03- S curve …………………………………………………………………………...14
INTERGRATED PROJECT
BSC (HONS) IN QS & CONSTRUCTION MANAGEMENT Page 1
INTRODUCTION
Pre contract and post contract cost control are doing a major part in the construction industry
in the present era. The success of a construction project is relying on usage of unique and
easiest tool for control quality, cost, and time.
This assignment includes the above cost control system, property valuation method,
allowable building cost calculation with some examples under the title of project cost control
to give a clear idea about pre contract and post contract studies. Iinformation were collected
form journals, books and research.
INTERGRATED PROJECT
BSC (HONS) IN QS & CONSTRUCTION MANAGEMENT Page 2
TASK-03.1
Cost control is significant concept has to be done during the construction process, Cost
control is a process where the construction cost is managed through the most effectively
systems and methods with the goal, thus helps to builder without endure while doing the
workout of the project. The main purpose of cost control is to build in minimum conceivable
expenses consistent with the broaden destinations (Otim, Nakacwa and Kyakula 2011).
Elementary cost control
Elementary cost control process is easiest method to control cost at post contract stage. This
can be done by controlling element under major sections of sub structure, super structure,
finishes and services, thus helps to identify each and every elemental cost control without
complexity. Basically these individual elements are estimated by direct and indirect cost.
Labor, material and plant expenses are coming under direct cost and environmental costs,
civilized construction costs, safe construction costs, temporary facility costs, nighttime
construction costs, secondary transportation fees and services are coming under indirect cost
(Ai 2011).
Initial budget cost may affected by price fluctuation, poor supervision and coordination,
improper labor and material management, delays. Further the relationship between cost and
time is an extremely serious matter in the control of cost on construction, so all the works
including materials, plant, and labor should be carefully recorded, thus empowers the
contractor to know the cost of the assets utilized on construction (Otim, Nakacwa and
Kyakula 2011).
Project details (Assumption)
This is a double story housing project now under construction and estimated project duration
is one year and Initial budget cost was Rs. 5,856,000.00. For cost control the Contractor has
selected elementary cost control method.
INTERGRATED PROJECT
BSC (HONS) IN QS & CONSTRUCTION MANAGEMENT Page 3
Elements Budget (Rs)
Substructure Foundation 425,000
Substructure
Column 423,000
Wall 528,000
Beam & Slab 1,232,000
Stair case 70,000
Roof 967,000
Doors & Windows 430,000
Finishes
Wall finishes 435,000
Floor finishes 322,000
Ceiling finishes 280,000
Services
Water installation 94,000
Electrical installation 230,000
Sanitary and disposal system 230,000
HAVC system 190,000
Total budget 5,856,000.00
Table 01- Initial budget by elements
Now roof part is under construction in this house project and Initial budgeted of roof section
is Rs.967, 000. Following chart illustrate elementary cost controls procedure for roof section.
Cost Analysis for Roof
Budget (Rs) Cost to date
(Rs)
Cost committed
(Rs)
Cost exposure
(Rs)
Over & (under)
(Rs)
material 640,000 310,000 248,000 90,000 8,000
labor 190,000 115,000 37,000 40,000 2,000
Plant 42,000 19,000 11,000 5,000 (7,000)
Supplier 50,000 31,000 11,000 6,000 (2,000)
Over head 45,000 24,000 9,000 7,000 (5,000)
Roof 967,000 (4,000)
Table 02– Elemental Cost Analysis of Roof
According to this analysis, current status of cost forecast is Rs.4000 under the budget of
initial budget of roof, so this is positive result for contractor. Further here contractor must
concern about cost of material with take an immediate action to avoid unwanted expenses and
minimize material wastage and also have to control the labor cost by employ more skilled
labors with efficiency of supervision and management.
INTERGRATED PROJECT
BSC (HONS) IN QS & CONSTRUCTION MANAGEMENT Page 4
Moreover the contactor cold finish the work with more profitable by applying efficient
management and techniques, thus will help to minimize the cost exposure for the future
works of roof section. Finally by analyzing this method to each and every element the cost of
construction can be controlled without any losses.
INTERGRATED PROJECT
BSC (HONS) IN QS & CONSTRUCTION MANAGEMENT Page 5
TASK-03.2
Assumptions for this calculations
Gross floor area (15,000m2)
Period of short term finance (48 months).
Rental received
Gross floor area [A] = 15,000m2
(assumption)
Non-lettable floor area percentage [B] = 25%
So, lettable floor area percentage[C] = (100-25) %
= 75%
Lettable floor area [D] = [A] x [C] = 15,000x0.75
= 11,250 m2
Estimated rent [E] = £ 85/m2
Net income per year [F] = [D] x [E] = 11,250 m2x£ 85/m
2
=£ 956,250
Gross development value
Capitalization of rent [G] = 7% (Yield)
Year's Purchase [H] = 100 / Yield = 100/7
= 14.286
Gross Development value (GDV) = £ 956,250x 14.286
[I] = [F] x [H] = £ 13,660,987.50
INTERGRATED PROJECT
BSC (HONS) IN QS & CONSTRUCTION MANAGEMENT Page 6
Developer’s profit
Developer's profit 17% of GDV = 17% x £ 13,660,987.50
[I] x0.17= [J] = £ 2,322,367.875
Land cost
Short term finance at 15% for 48 months (assumption) = £ 150,000 x 15% x 4
= £ 90,000
The land cost [K] = £ 150,000 +£ 90,000
= £ 240,000
Summary of calculated details
Gross development value (I) = £ 13,660,987.50
Developer’s profit (J) = £ 2,322,367.875
Land cost (K) = £ 240,000
Allowable building cost = £ 13,660,987.50 – (£ 2,322,367.875+ £ 240,000)
[I]- ([J] + [K]) = £ 11,098,619.625
Construction cost
Take ‘X’ is the construction cost and Finance will be required at interest of 15% for 12
months construction period.
Construction cost = X
Professional fees = X x 0.08
Finance = X x 0.15x 1
Allowable building cost = Construction cost + Professional fees + Finance
£ 11,098,619.625 = X+ 0.08 X + 0.1X
1.18 X = £ 11,098,619.625
X = £ 9,405,609.852
INTERGRATED PROJECT
BSC (HONS) IN QS & CONSTRUCTION MANAGEMENT Page 7
Constructed cost for 1 m2 area = £ 9,405,609.852/ 11,250
= £ 836.054
Advice
According to calculation, allowable building cost is £ 11,098,619.625, construction cost is
£ 9,405,609.852 and construction cost of 1 m2 comes to £ 836.054. Form this allowable
building cost consultant can decide whether this amount is suitable or unsuitable for his
financial background and lifetime profitable amount to invest in this proposed commercial
complex. Further he can reduce or deduct interest of £ 90,000 by buying the land by his own
money.
INTERGRATED PROJECT
BSC (HONS) IN QS & CONSTRUCTION MANAGEMENT Page 8
TASK-04.1
Interim valuation is one of the significant process comes under interim certifications and
statements, which carrying out in post contract activities preparation by Quantity surveyor,
further its includes sections are of valuing of works complete on site, valuing any materials
or goods manufactured on site or off site which can be include under the terms and contract,
agreeing these amounts between the surveyors of contractor’s and consultant’s, notifying
nominated subcontractors that payments can be expected (Ashworth 2010).
Major sections of valuation is given below
Preliminaries
Measured work
Provisional sums
Day works
Variations
Price fluctuation
Contingencies
Example (Assumption)
Here an Interim payment certification valuation done according to Clause 14.3 and standard
form of contract is (ICTAD/SBD/02) for a road project. An example of valuation is given
below in the (figure 01).
According to this Value of work done table, the payment certificate was done cumulative
calculation and, the valuation month which includes the preliminaries, all measured work.
Further there is no provisional sum and day works of labor, equipment and materials, extra
works, and contingencies didn’t happen in this month and last month.
INTERGRATED PROJECT
BSC (HONS) IN QS & CONSTRUCTION MANAGEMENT Page 9
Figure 01- Interim valuation of road project
Following are the difficulties faced during the valuation process.
1. Price fluctuation- increases the price of materials caused to increase the initial budget.
2. Delay - work delay affect the cash flow between the contractor and client thus lead to
payment delay.
3. Wrong measurement calculation - re-measurement was applied, thus led to delay in
submission of interim payment certificate.
4. Claims- forget and the unknown of how to make claims led to money losses.
INTERGRATED PROJECT
BSC (HONS) IN QS & CONSTRUCTION MANAGEMENT Page 10
TASK-04.2
The term cost and the value are different concepts in the property development segment.
Ozdilek (2010) states “Usually, the economic literature defines value in the sense of the
importance and worth of things”, and the “Value is the source of cost and price, and it is not
numerable” and also he said “Cost also has an individual content, which is the idea of pain or
sacrifice or the giving up of something in return for an object”.
There are many types of valuation methods used for many purposes for value the property
and the selection of suitable method rely according to requirement of needs. Following
valuation methods are some famous in property development.
Comparative method
This method is always using to calculate Open market value and particular property value
achieved by comparing similar types of properties. On the other hand, It is must to know the
actual sales prices of the properties that use to compare and must need the sufficient recent
data’s of geographical area property transactions (Padraig Hyde & Sons 2013).
Example - Someone plan to sell his land with land extent of 30 perches. To fine his land
value, according the previous data’s of land in this area. The same land extent has been sold
for $ $ 15,000 and another 63 land sold for $31,000 within 2 months. By these details we can
end up for a reasonable price of $15,000 for this land.
Contractor’s method
This method is commonly used for insurance purpose to value of religious, public building
and non residential building. Property value is equal the cost of erecting the building together
with the cost of the site (Ashworth 1999)
Value of property = (Market value of land +Replacement cost of the building) -Depreciation
= ($ 12,000 +$ 50,000) - $ 8,000
= $ 54,000
INTERGRATED PROJECT
BSC (HONS) IN QS & CONSTRUCTION MANAGEMENT Page 11
Residual method
This method is mainly used for development or redevelopment to calculate the value
someone may ready to pay for a plot of development land. For example, if a profit might be
achieved on a development this method is frequently of service in calculating (Padraig Hyde
& Sons 2013).
Example-If the estimated sales price for a newly built property is $ 30,000 and the building
costs amount to $ 22,000, the residual value of the site can be calculated at $ 8,000.
If you were a property developer and you bid above the Residual Value of the site at say $
8,000, you would automatically be running at a loss of $ 2,000.
INTERGRATED PROJECT
BSC (HONS) IN QS & CONSTRUCTION MANAGEMENT Page 12
TASK-04.3
Life-cycle cost (LCC) is the collective cost of a structure throughout its lifetime which
includes initial costs, design and construction cost, operation, maintenance, and demolishing
the structure over the lifetime of the structure. Structure might not be economical design
when utilities and maintenance costs are high than initial cost, further from an Economic
viewpoint minimizing the total life-cycle cost of structures is major objective (Sarma and
Adeli 2002).
Example
Here I explained LCC analysis of steel structure, to minimize the life-cycle cost the steel
structure sections should be lowest cost, lightest, minimum total perimeter length, and
minimum number of different types with commercially available.
The life-cycle cost equation of steel structure can be defined as follow
The life-cycle cost of steel structure include of seven cost of initial, annual maintenance,
inspection, repair, operating, probable failure, and dismantling costs.
[i] - Discount or inflation rate of money
[l]- Actual costs in the year by components
[yn1, yn2, yn3, yn4, yn5, yn6] - Years of associated costs
The equation
] represent the cost into its present value discounted by the discount rate
of i for the period.
INTERGRATED PROJECT
BSC (HONS) IN QS & CONSTRUCTION MANAGEMENT Page 13
The discount rate [i] depends on interest rate and currency depreciation, so in this calculation
I consider no value for discount rate.
The analysis of life cycle cost of a steel cable section in Cable stayed Bridge with considers
no value to discount with assumption of each cost. This is a suspension cable made of nearly
10,000 steel wires with mo efficient protection system and particular cables have life spans
up to 150 years and after that it will be weaken (KILGANNON 2008).
year Cost ($) in cumulative
maintenance inspection repair operating failure dismantling Initial LCC
1 300 180 50 30 - - 10,000 10560
2 610 380 120 65 - - 10,000 11175
3 312 540 180 105 - - 10,000 11137
4 315 720 235 148 - - 10,000 11418
5 320 900 301 194 - - 10,000 11715
Table 03– Life-cycle cost analysis of steel cable
According to this analysis, LCC is $11,715 in end of five years and it can be clearly seen
almost one fifth of the initial cost is observed by the other functions cost, which is $1715.
This is a cable bridge so life time of the bridge is normally 100 years, but in 50 years the
LCC will same of initial cost, further the life time of the cable is 150 years, so in 150 years
the total (LCC) will be three times of the initial cost excluding with the dismantling costs. To
minimize the cost the maintenance, inspection, repair, operating should be done in efficient
method and management.
INTERGRATED PROJECT
BSC (HONS) IN QS & CONSTRUCTION MANAGEMENT Page 14
TASK-04.4
The S-curve is important tool which used in post contract stage to contractor’s cost control,
working process control and also maintain cash flow. It is important to know the contractor
about budget actual and expenditure during the construction process which is helpful to cost
efficiency of the works and also help to manage his cost with efficient work in future
construction within the allocated budget. S-curve is given below depicts the budget actual and
expenditure.
Figure 02- S curve
It can be clearly seen, actual expenditure is increased little bit in the (t) time period. This is
indicates the work cost is higher than the budget cost, thus may effect in the cash flow
process. This increase may happen by fast working process or over expenses of works or
price fluctuation or variation, so there should be more attention in efficiency of working
methods and price fluctuation by the contractor. If the variation and price fluctuation
happened until the (t) time period, the contractor have the rights to clime those additional
money of actual expenditure.
INTERGRATED PROJECT
BSC (HONS) IN QS & CONSTRUCTION MANAGEMENT Page 15
Then actual expenditure continued to decreased by certain amount and finally end up with
under run and delay. This might be due to delay or efficient labor material and cost
management after the (t) time period until the end of project; on the other hand there is a
chance to poor quality and workmen ship. May be some time due to the delay the contractor
may suffer for financial problem, and might face the money lose for delay punishment, so the
contractor must be careful with those matter.
INTERGRATED PROJECT
BSC (HONS) IN QS & CONSTRUCTION MANAGEMENT Page 16
CONCLUSION
Finally I explained about pre contract and post contract process of elementary cost control
systems, interim valuation, property valuation methods, life cycle cost analysis and S-curve
with some relevant examples and assumptions. Most of those functions are related with the
construction projects and mostly used techniques and tools, thus helps to identify problems
and needs to finish the project with economically. I got enough knowledge about those
sections by this assignment with the read of more books and journals.
INTERGRATED PROJECT
BSC (HONS) IN QS & CONSTRUCTION MANAGEMENT Page 17
REFERENCE & BIBLIOGRAPHY
AI, Xue (2011). Analysis and countermeasures of project cost control in construction enterprises. In:
E -Business and E -Government (ICEE), 2011 International Conference on, 6-8 May 2011. , 1-4.
ANON (2013). Cost Control, Monitoring and Accounting. [online]. Last accessed 12 December 2013
at: http://pmbook.ce.cmu.edu/12_Cost_Control,_Monitoring,_and_Accounting.html
ANON (no date). The Concept of Property Valuation. [online]. Last accessed 14 December 2013 at:
http://www.palgrave.com/PDFs/0333921143.pdf
ASHWORTH, Allan (1999). Cost Studies of Buildings. 3 ed., Longman.
ASHWORTH, Allan (2010). Cost Studies of Buildings. 5 ed., Pearson Education.
KILGANNON, COREY (2008). Aging a Cable to Extend a Bridge’s Life. [online]. 22 December, Article
from The New York Times last accessed 20 December 2013 at:
http://cityroom.blogs.nytimes.com/2008/12/22/aging-a-cable-to-extend-a-bridges-lfe/?_r=0
OTIM, George, NAKACWA, Fiona and KYAKULA, Michael (2011). Cost Control Techniques Used On
Building Construction Sites in Uganda. [online]. Last accessed 12 December 2013 at:
http://news.mak.ac.ug/documents/Makfiles/aet2011/Otim-2.pdf
OZDILEK, Ünsal (2010). On Price, Cost, and Value. Appraisal Journal, 78 (1), 70-80.
PADRAIG HYDE & SONS (2013). Valuation Methods. [online]. Last accessed 16 December 2013 at:
http://www.hydeproperty.com/property-articles/30-valuation-methods
SARMA, Kamal and ADELI, Hojjat (2002). Life-cycle cost optimization of steel structures. International
Journal for Numerical Methods in Engineering, 1451–1462.
UNDERWOOD, Jason and ALSHAWI, Mustafa (1999). GENERATING PROJECT ESTIMATES AND
MONTHLY INTERIM VALUATION CERTIFICATES WITHIN AN INTEGRATED CONSTRUCTION
ENVIRONMENT. Civil Engineering and Environmental Systems, 5 (4), 275-304.