Environmental Monitoring Report This report has been submitted to ADB by Program Management Unit, Government of Uttarakhand, Dehradun and the Asian Development Bank and is made publicly available in accordance with ADB’s Public Communications Policy (2011). It does not necessarily reflect the views of ADB. This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area. Project Number: 40648-034 August 2018 Period: July 2017 – December 2017 IND: Infrastructure Development Investment Program for Tourism - Tranche 3 Submitted by: Program Management Unit, Government of Uttarakhand, Dehradun

Transcript of Infrastructure Development Investment Program for Tourism ...

Environmental Monitoring Report

This report has been submitted to ADB by Program Management Unit, Government of Uttarakhand, Dehradun and the Asian Development Bank and is made publicly available in accordance with ADB’s Public Communications Policy (2011). It does not necessarily reflect the views of ADB.

This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Project Number: 40648-034 August 2018 Period: July 2017 – December 2017

IND: Infrastructure Development Investment Program for Tourism - Tranche 3

Submitted by: Program Management Unit, Government of Uttarakhand, Dehradun

1

Semi – Annual Environmental Monitoring Report

Loan No: 3223 IND Period: July to Dec 2017

IND: Infrastructure Development Investment Programme for Tourism, Uttarakhand (Tranche –III)

Prepared by Dept. of Tourism, Government of Uttarakhand for Asian Development Bank July, 2018

This Semi – Annual Environmental Monitoring Report is a document of the borrower. The views expressed

herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be

preliminary in nature.

2

Table of Contents

1. INTRODUCTION ........................................................................................................................................................................................................................................................................................................................................................................................................................................................ 5555

2. COMPLIANCE STATUS ........................................................................................................................................................................................................................................................................................................................................................................................................ 32323232

3. COMPLIANCE STATUS WITH NATIONAL/ STATE/ LOCAL STATUTORY ENVIRONMENTAL

REQUIREMENTS ........................................................................................................................................................................................................................................................................................................................................................................................................................................................................ 33333333

4. COMPLIANCE STATUS WITH THE ENVIRONMENTAL COVENANTS AS STIPULATED IN THE

LOAN AGREEMENT .................................................................................................................................................................................................................................................................................................................................................................................................................................................... 35353535

5. COMPLIANCE STATUS WITH ENVIRONMENT MANAGEMENT AND MONITORING PLANS AS

STIPULATED IN THE ENVIRONMENTAL DOCUMENTATION AS AGREED WITH ADB. ........................................................ 36363636

6. STATUS OF IMPLEMENTATION OF ENVIRONMENT MANAGEMENT PLAN ............................................................................................ 37373737

7. APPROACH & METHODOLOGY ENGAGED FOR ENVIRONMENTAL MONITORING OF THE

PROJECT .................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................... 62626262

8. MONITORING OF ENVIRONMENTAL RECEPTORS/ ATTRIBUTES ................................................................................................................................................ 62626262

9. IMPLEMENTATION OF ENVIRONMENTAL MONITORING PLAN ................................................................................................................................................................ 64646464

10.1 INSTITUTIONAL ARRANGEMENTS FOR EMP IMPLEMENTATION ................................................................................................................................................ 81818181

10. PUBLIC CONSULTATION DETAILS .................................................................................................................................................................................................................................................................................................................... 82828282

11. IMPLEMENTATION OF GRIEVANCE REDRESS MECHANISM ............................................................................................................................................................ 86868686

12. ANY OTHER ENVIRONMENTAL ASPECTS, IMPACTS OBSERVED DURING

IMPLEMENTATION WHICH WERE NOT COVERED EARLIER ........................................................................................................................................................................................................ 87878787

13. DETAILS OF COMPLAINTS RECEIVED FROM PUBLIC AND ACTION TAKEN THEREOF TO

RESOLVE ................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................ 87878787

14. FOLLOW UP ACTIONS AND CONCLUSIONS ............................................................................................................................................................................................................................................................ 87878787

3

List of Table

TABLE 1: PROJECT PROGRESS IN THE REPORTING PERIOD TILL JUNE, 2017 ............................................................................................ 7777

TABLE 2: WORK DETAILS AND RISKS FOR SUB PROJECTS ............................................................................................................................................................................................................ 8888

THE MAIN SUB-PROJECT COMPONENTS INCLUDE THE FOLLOWING: ........................................................................................................................................ 29292929

TABLE 3: STATUS OF COMPLIANCE WITH EARF/ADB PROCEDURES ............................................................................................................................................ 32323232

TABLE 4: STATUS OF ENVIRONMENT, FOREST AND OTHER CLEARANCE................................................................................................................ 33333333

TABLE 5: STATUS OF COMPLIANCE WITH ENVIRONMENTAL LOAN COVENANTS .................................................................... 35353535

TABLE 6: EMP IMPLEMENTATION STATUS ............................................................................................................................................................................................................................................................................................................ 36363636

TABLE 7 (I): EMP MONITORING STATUS CHART- DEVELOPMENT OF TOURISM

INFRASTRUCTURE IN KARTIKEYA SWAMI CIRCUIT (LOT-1) (TUNGESHWAR &DURGADHAR

TEMPLE) ........................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................ 38383838

TABLE 7 (II): EMP MONITORING STATUS CHART- DEVELOPMENT OF TOURISM

INFRASTRUCTURE IN KARTIKEYA SWAMI CIRCUIT (LOT-2) (KARTIKEYA SWAMI TEMPLE) ............ 40404040

TABLE 7 (III): EMP MONITORING STATUS CHART- RURAL TOURISM IN DISTRICT TEHRI AND

UTTARKASHI ............................................................................................................................................................................................................................................................................................................................................................................................................................................................................................ 42424242

TABLE 7 (IV): EMP MONITORING STATUS CHART- CONSERVATION OF CULTURAL HERITAGE

AND URBAN PLACE MAKING IN NAINITAL LOT-1........................................................................................................................................................................................................................................................................ 45454545

TABLE 7 (V): EMP MONITORING STATUS CHART- RESTORATION AND ADAPTIVE REUSE OF

ALMORA FORT (RANI MAHAL) .................................................................................................................................................................................................................................................................................................................................................................................... 47474747

TABLE 7 (VI): EMP MONITORING STATUS CHART- RESTORATION AND ADAPTIVE REUSE OF

CHAMPAWAT FORT (BANASUR) ........................................................................................................................................................................................................................................................................................................................................................................ 49494949

TABLE 7 (VIII) : EMP MONITORING STATUS CHART- CREATION OF PEDESTRIAN ROUTE FOR

PILGRIMS AND TOURISTS IN HARIDWAR .................................................................................................................................................................................................................................................................................................................... 53535353

TABLE 7(IX): EMP MONITORING STATUS CHART- DEVELOPMENT OF TOURISM

INFRASTRUCTURE IN SEM MUKHEM ................................................................................................................................................................................................................................................................................................................................................ 56565656

4

TABLE 7(X): EMP MONITORING STATUS CHART- DEVELOPMENT OF TRADITIONAL MEDICINE

AND YOGA TRAINING CENTRES ........................................................................................................................................................................................................................................................................................................................................................................ 60606060

TABLE 8: PARAMETERS AND METHODOLOGY FOR ENVIRONMENTAL MONITORING ............................................ 63636363

TABLE 9 (I): IMPLEMENTATION OF ENVIRONMENTAL MONITORING PLAN- FOR PROJECTS

UNDER PIU DDN ........................................................................................................................................................................................................................................................................................................................................................................................................................................................................ 64646464

TABLE 9 (II): IMPLEMENTATION OF ENVIRONMENTAL MONITORING PLAN- FOR PROJECTS

UNDER PIU KOTDWARA ........................................................................................................................................................................................................................................................................................................................................................................................................................ 70707070

TABLE 9 (III): IMPLEMENTATION OF ENVIRONMENTAL MONITORING PLAN- FOR PROJECTS

UNDER PIU BHIMTAL ............................................................................................................................................................................................................................................................................................................................................................................................................................................ 75757575

TABLE 10(I): PUBLIC CONSULTATION MEETINGS FOR TRANCHE III SUB-PROJECTS UNDER

PIU DEHRADUN ............................................................................................................................................................................................................................................................................................................................................................................................................................................................................ 83838383

TABLE 10(II): PUBLIC CONSULTATION MEETINGS FOR TRANCHE III SUB-PROJECTS UNDER

PIU KOTDWAR .................................................................................................................................................................................................................................................................................................................................................................................................................................................................................... 85858585

TABLE 10(III): PUBLIC CONSULTATION MEETINGS FOR TRANCHE III SUB-PROJECTS UNDER

PIU BHIMTAL ............................................................................................................................................................................................................................................................................................................................................................................................................................................................................................ 86868686

ANNEXURE: 1(I): PHOTO ILLUSTRATION OF WORK PROGRESS- DSC DEHRADUN ................................................................ 88888888

ANNEXURE: 1(II): PHOTO ILLUSTRATION OF WORK PROGRESS- PIU KOTDWAR ........................................................................ 89898989

ANNEXURE: 1(III): PHOTO ILLUSTRATION OF WORK PROGRESS- DSC BHIMTAL ........................................................................ 91919191

ANNEXURE 2: CONSULTATION RECORDS & PHOTOGRAPHS ............................................................................................................................................................................................ 93939393

ANNEXURE – 3 NEWS PAPER CLIPPING ................................................................................................................................................................................................................................................................................................................ 100100100100

5

1. Introduction

Overall Project Description

1. The Infrastructure Development Investment Program for Tourism Financing Facility (the Facility) will

develop and improve basic urban infrastructure and services in the four participating states of Himachal

Pradesh, Punjab, Uttarakhand and Tamil Nadu—to support the tourism sector as a key driver for

economic growth. It will focus on: (i) strengthening connectivity to and among key tourist destinations;

(ii) improving basic urban infrastructure and services, such as water supply, road and public transport,

solid waste management and environmental improvement, at existing and emerging tourist destinations

to ensure urban amenities and safety for the visitors, and protect nature and culture-based attractions.

Physical infrastructure investments will be accompanied by: (iii) capacity building programs for

concerned sector agencies and local communities for better management of the tourist destinations and

for more active participation in the tourism-related economic activities, respectively.

2. The proposed Project targets enhanced economic growth and provision of livelihood opportunities for

local communities through tourism infrastructure development with a focus on preservation and

development of natural and cultural heritage and incidental services. The Project supports the state of

Uttarakhand to develop the tourism sector as a key driver for economic growth.

3. The Executing Agency (EA) for the Investment Program is Dept. of Tourism, Govt of Uttarakhand. The

Loan Agreement and Project Agreement for the IDIPT, Uttarakhand is 3223-IND. Project

Implementation Unit have been established in three towns respectively (Dehradun, Bhimtal and

Kotdwar) for implementation of sub-projects. Design and Supervision Consultants (DSCs), has already

been established in three towns for designing the Infrastructure, managing the tendering of Contractors

and supervising construction, and providing support to the PIUs.

Outputs of the Project

4. The outputs of the Project are as follows:

Component 1: Urban Infrastructure and Service Improvement

Component 2: Improved connectivity

Component 3: Quality Enhancement of Natural and Cultural Attractions

Component 4: Greater participation by local communities

Component 5: Capacity Development, Community Participation and Project Management

6

Environment Category:

5. The project under IDIPT was categorized as Environment Category “B”, according to ADB’s Safeguard

Policy Statement (2009). All the subprojects under execution have been categorized as category 'B'.

Environment Performance Indicators, if any:

6. For effective monitoring, selected environmental parameters have been identified as indicators which

may be qualitatively and quantitatively measured and compared over a period of time in order to

assess/ ensure the compliance to environmental management plans (EMPs). The environmental

performance indicators selected are physical, biological and social characteristics identified as most

important in affecting the environment at critical locations at all the sub projects. The parameters

identified as performance indicators are:

1. Compliance with environmental management and monitoring plan

2. Compliance to State/ National environmental regulations.

3. Monitoring of ambient air quality, water quality and noise levels and comparison with baseline

environmental quality and State/ National Standards.

Overall project progress, agreed milestones and Implementation schedule

7. Construction works for the following sub projects are in progress and shown in Table 1.

7

Table 1: Project Progress in the Reporting Period till June, 2017

SI. No.

Package Ref No.

General Description Goods or Works

Contract Signing Date and Start

date Name of the Contractor Contract Value

Contract period

1 UK/IDIPT-III/ DDN/01 Lot1

Development of Tourism Infrastructure In Kartikeya Swami Circuit (Lot-1) (Tungeshwar & Durgadhar Temple)

LOA 22.01.16 Work started 26.02.2016

M/s Aaradhya Engineers & construction pvt Ltd.,2nd Tulsi Vihar, Hardiwar road ,Post –Virbhadra ,Rishikesh (UA)

INR 7.59 Cr.

24 months

2 UK/IDIPT-III/ DDN/02

Development of Tourism Infrastructure in Kartikeya Swami Circuit (Kartikeya Swami Temple)

LOA issued 23.05.16 Work started 07.07.2016

M/S APS Structures Private Ltd,Fort Sports complex ,Tara Hall,Mussorie

INR 3.97 Cr.

24 months

3 UK/IDIPT-III/DDN/03

“Conservation & Development of Rural Tourism Sites of Rudraprayag, Chamoli and Uttarkashi Districts of Uttarakhand”

LOA issued 23.05.16 Work started 02.08.2016

M/S Navya Associates in JV with Agrawal Brothers INR 15.26 Cr. 24 months

4 UK/IDIPT/III/BHT/01

Conservation of Cultural Heritage and urban place making in Nainital Lot-1

19-10-2015

M/s Simplex Project Limited 407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India

INR 38.52Crore 24 months

5 UK/IDIPT/III/BHT/03

Restoration and adaptive reuse of Almora Fort (Rani Mahal)

19-10-2015

M/s Simplex Project Limited 407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India

INR 29.90 Crore 24 months

6 UK/IDIPT/III/BHT/05

Restoration and adaptive reuse of Champawat Fort (Banasur)

19-10-2015 M/s Simplex Project Limited 407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India

INR 15.53Crore 24 months

7 UK/IDIPT-III/ KOT/01

Creation of Pedestrian Route for Pilgrims and Tourists in Haridwar

22/07/2015 M/s SS InfratechJv, Tikola Nagar, Roorkee, Haridwar 247670

INR 22.38 Cr.

24 months

8 UK/IDIPT-III/KOT/02

Development of Tourism Infrastructure in Sem Mukhem

22/08/2015 M/s Mangalam and Construction Company in JV with Sunil Garg and Company, Kesarganj, Meerut.

INR 10.18 Cr.

24 months

9 UK/IDIPT/III/BHT/07

Restoration and Adaptive Reuse of Pithoragarh Fort Phase II

05/07/2016 M/S COX Infratech Private Limited in JV with Conaech Associates

INR 27.11 Cr.

24 months

10 UKIDIPT/III/GEN/03

Development of Traditional Medicine and Yoga Training Centers

08/03/17 M/s Bansal Construction INR 3.76 Cr. 24 months

8

8. Work Details In the reporting period has been shown in Table 2.

Work progress of 10 packages is reported in table 2. Photographs showing work progress are provided in Annexure 1.

Table 2: Work Details and Risks For sub projects

Name & No. of

Package

Name of

the

contractor

Listing of works under the package

Starting Date(land clearance)

and schedule date of

completion Type of works

Continued at

Present

Progress %

Expected

change from

Approved

scope

Fulfillment

of objective

Type of

remedial

measures

needed

Key assumption

and risk affect

attainment the

objective Starting date Date of

Completion

UK/IDIPT-III/

DDN/01 Lot1

Development of

Tourism

Infrastructure In

Kartikeya Swami

Circuit (Lot-1)

(Tungeshwar,

Durgadhar

Temple)

Aradhya

Engineers

Durgadhar Temple precinct

Upgradation of infrastructure around the approach area of the temple, including drinking water facilities and sanitation

Parking facility and vehicular approach along with adjoining retaining walls

Solid waste management

Pathway development with railings & protection wall wherever necessary and signage and seating and lighting

Temple entrance arch

Improvement of the temple complex in terms of restructuring of the newly added temporary structures and overall landscaping to facilitate better movement and space for gathering of pilgrims and tourists

Lodging facilities with rooms and dormitories and toilet block at the rear side of the temple complex and a langar hall

Area confinement with edge wall , viewing

22.01.2016 21.01.2018 DURGADHAR:-

Guest house

Door and window

Shutters

completed

including

polishing work,

Internal work in

progress

flooring and

painting coning

Stone work

Path way

Out site electry

work like

transformer and

street light

Main Temple: -

47.00% Not

visualized till

now

Nil Frequent Weather

disturbances

during monsoon

season may delay

the work progress

9

Name & No. of

Package

Name of

the

contractor

Listing of works under the package

Starting Date(land clearance)

and schedule date of

completion Type of works

Continued at

Present

Progress %

Expected

change from

Approved

scope

Fulfillment

of objective

Type of

remedial

measures

needed

Key assumption

and risk affect

attainment the

objective Starting date Date of

Completion

decks etc

Restoration of Temple premises Construction of C.C road(main road to Temple,400 mtr length with drain

Development of Solar lighting and Fire Fighting work.

Capacity building for temple committee members for O&M activities.

Tungeshwar Temple precinct

Entrance area development with appropriate signage

Development of the 1.5km long pathway with railing to the main temple, increase in width and edge protection wherever required.

Seating arrangements , viewing decks and toilet facilities

Signage along the pathway and Temple premises.

Improvement in the temple precinct

Construction of entrance gate

Lodging facilities and langar hall

Development of Solar lighting and Fire Fighting work

stone cladding

Temple dome

work in progress

after completion

of temple frame

TUNGESHWAR:

Dharamshala:-

Clay tile work at

roof completed

Internal finishing

work in progress

Guest house

coloring and final

touches

Door and window

fitting

Kitten roofing

work continuing

10

Name & No. of

Package

Name of

the

contractor

Listing of works under the package

Starting Date(land clearance)

and schedule date of

completion Type of works

Continued at

Present

Progress %

Expected

change from

Approved

scope

Fulfillment

of objective

Type of

remedial

measures

needed

Key assumption

and risk affect

attainment the

objective Starting date Date of

Completion

Improvement in the drinking water facility for the approach areas

Capacity building for temple committee members for O&M activities.

UK/IDIPT/III/DD

N/02

Kartikeya Swami

Temple

M/s APS

Structure

Pvt.

Ltd ,Fort

Sports

Complex,

Tara Hall,

Mussorie

Civil Work Pedestrian Pathway Sitting Arrangement Railing at Temple Premises Pathway Renovation Existing Dharamshala Rest Shelter Retaining & Breast Walls View Point Pre-fabricated Small Size Toilet Entrance Gate Renovation of Lodging Facility Furniture for Lodging Facility Camping Site development Renovation of Main Temple Solar Lighting Fire Fighting works Additional items Renovation of Existing Toilet Toilet Block Provision of Pathway Covering Shelter Directional Signage

07.07.16 06.07.18 Repairing work in progress at pathway, toilet and informative signage work

Pathway and Drain: - Pathway from Dharamshala to Bhaira Nath Temple completed & near entrance gate work is in progress.

42.50% No change

so far

Appropriate

measures

has been

taken for

fulfillment of

the

objectives

11

Name & No. of

Package

Name of

the

contractor

Listing of works under the package

Starting Date(land clearance)

and schedule date of

completion Type of works

Continued at

Present

Progress %

Expected

change from

Approved

scope

Fulfillment

of objective

Type of

remedial

measures

needed

Key assumption

and risk affect

attainment the

objective Starting date Date of

Completion

Informative Signage Solar Power Plant (2KW) Hill View location pointer model Electrical Work (Internal/External) From Provisional Sums Water Supply Connection Electricity Connection Rain Water Harvesting Capacity building for Temple Committee members for O&M activities

UK/IDIPT/III/DD

N/03

Rural Tourism

M/s Navya

Associates

JV with M/s

Agarwal

Brothers

Name of Village

Proposed Hardware Components

Tungnath Restoration of Temple through removal of incongruent additions and preservative coating and foundation retrofitting of main temple

Removal and reconstruction of bulged retaining walls

Shivalinga water/Rain water disposal system of the temple/premises

Up gradation of main entrance gateway

Improvement of pathway upto new gateway structure

Kaviltha Upgradation of Pathway

Construction of Guest

02.08.16 01.08.18 1. Tungnath:-

CBRI team had

visited the site

from 19. 09. 2017

to 21.09.2017

and submitted

the report on 11th

October 2017

and drawing work

is under progress

2.Kaviltha:

Guest house slab

casting and

parking is under

construction

Ground floor roof

work on going

19.50% No change

so far

12

Name & No. of

Package

Name of

the

contractor

Listing of works under the package

Starting Date(land clearance)

and schedule date of

completion Type of works

Continued at

Present

Progress %

Expected

change from

Approved

scope

Fulfillment

of objective

Type of

remedial

measures

needed

Key assumption

and risk affect

attainment the

objective Starting date Date of

Completion

House

Renovation of KalidasSmarak& Community centre

Repair of existing Parking facility

Repairing of Existing Water source

Renovation of PanchayatBhawan

Landscaping

Informative Signage

Directional Signage

Renovation of Existing gate and Railing

Furniture For Kaviltha Guest House and Kaviltha Library

Solar light and Water Heater System

Phalasi Up gradation of Pedestrian Pathway and providing retaining &breast Wall

Construction of Toilet Block

Directional and Informative Signage

Solar Lighting

Railing

3.Phalasi:- Toilet

block RCC roof

completed . Soak

pit and safety

tank completed

but not

connected

4.Bora:-

Retaining wall

13

Name & No. of

Package

Name of

the

contractor

Listing of works under the package

Starting Date(land clearance)

and schedule date of

completion Type of works

Continued at

Present

Progress %

Expected

change from

Approved

scope

Fulfillment

of objective

Type of

remedial

measures

needed

Key assumption

and risk affect

attainment the

objective Starting date Date of

Completion

Sitting Benches

Durgadhar (Bora)

Up gradation of Pedestrian Pathway and covering shelter

Construction of Toilet Block

Directional and Informative Signage

Solar Lighting

Railing and Sitting Benches

Renovation of Existing Panchayatbhawan

Harshil

Up gradation of Pedestrian Pathway and Pathway Covering Shelter and Construction of Retaining Walls

Upgradation of existing Sitting Arrangement

New Railing

Renovation of Existing Entrance Gate

Renovation of Existing Rain Shelter, Temple Premises, Parking Area and Water Tank

Informative and Directional Signage

and pathway

work started by

contractor but

villagers stopped

the work for

widening the

existing pathway

for motor able

with CC road .

5.Harshil:-

Helipad work

completed

Entrance gate in

progress

Pathway in

progress

Parking work is in progress

14

Name & No. of

Package

Name of

the

contractor

Listing of works under the package

Starting Date(land clearance)

and schedule date of

completion Type of works

Continued at

Present

Progress %

Expected

change from

Approved

scope

Fulfillment

of objective

Type of

remedial

measures

needed

Key assumption

and risk affect

attainment the

objective Starting date Date of

Completion

Beautification of Existing Helipad

Protection wall for Camping Site

Solar Lighting

Mukhwa Upgradation of existing Pedestrian Pathway and Construction of Pathway Covering Shelter, retaining and breast wall

New Sitting Arrangement

Renovation of Existing PanchayatBhawan& Temple Premises

Construction Parking facility

Entrance Gate

Toilet Block -

Directional and Informative Signage

Railing

Kanakchori (Pogatha)

Upgradation of Pedestrian Pathway and Pathway Covering Shelter

Retaining & Breast Wall

Toilet Block - Small

Directional and Informative Signage

Solar Lighting

Sitting Bench

6. Mukhwa:

Parking and

railing under

progress

Entrance gate is

under progress

7. Kanakchori

Path way and

solar light

completed

15

Name & No. of

Package

Name of

the

contractor

Listing of works under the package

Starting Date(land clearance)

and schedule date of

completion Type of works

Continued at

Present

Progress %

Expected

change from

Approved

scope

Fulfillment

of objective

Type of

remedial

measures

needed

Key assumption

and risk affect

attainment the

objective Starting date Date of

Completion

Niti Construction of Community Centre

Renovation of open air theater and compound wall

Construction of Parking facility

Upgradation of gram panchayatbhawan

Directional and Informative Signage

upgradation of village Pathway with KC drain

Seating Benches

Toilet

Upgradation of existing View Points

Provision of Dust Bins

Solar Light

Erection of Glass House (View points)

Lata No Hardware components proposed

UK/IDIPT/III/BH

T/01 Lot 1

Conservation

of Cultural

Heritage and

urban place

M/s

Simplex

Project

Limited

407,

Skipper

Corner, 88

Proposed Scope as per IEE (DPR)

1. Promenade development around Nainital lake

• Mechanical car parking

• Development of Children’s park 2. Enhancement of Nainital Lake

19.10.2015 18.10.2017 1) Library. Roofing work and framing. Wooden column.

2) DSA Flat- Roofing work,

14.20% Many

components

have been

dropped, no

new works

undertaken

Nil Cooperation of

LDA is integral for

fulfillment of

project objectives

16

Name & No. of

Package

Name of

the

contractor

Listing of works under the package

Starting Date(land clearance)

and schedule date of

completion Type of works

Continued at

Present

Progress %

Expected

change from

Approved

scope

Fulfillment

of objective

Type of

remedial

measures

needed

Key assumption

and risk affect

attainment the

objective Starting date Date of

Completion

making in

Nainital Lot-1

Nehru

Place, New

Delhi -

110019,

India

Heritage Precinct

• Restoration of Municipal Corporation, DSA Pavilion, New Club

• Development of Gandhi gram, Takula

• Façade improvement of Dam wall at Mallital,

• Façade restoration and illumination of Govt. owned heritage buildings (Bishop Shaw, Municipal Library, Catholic church, Methodist Church

• Provision of Public Amenities and facilities at appropriate location in Nainital area precinct

• Integrated signage and interpretation in lake precinct

• Reclamation of public and open spaces in the lake precinct

• Removal and demolition of obsolete, damaged street furniture and structures

• Rickshaw stand

• Integrated stone paved pedestrian access and pathways with adequate plantation

• Street furniture

• Weather shelters

FF verandah, strengthen GF,

3) 3 Methodist church-Roofing work G.F. and fasade work front side.

4) Catholic church- Roofing work, railing RCC column and pointing work.

5) DSB chapel- Pointing work

6) Municipal building-cutting for Window bracket.

7) National hotel toilet-Tile work internal

8) Cheenababa toilet-Plaster work

17

Name & No. of

Package

Name of

the

contractor

Listing of works under the package

Starting Date(land clearance)

and schedule date of

completion Type of works

Continued at

Present

Progress %

Expected

change from

Approved

scope

Fulfillment

of objective

Type of

remedial

measures

needed

Key assumption

and risk affect

attainment the

objective Starting date Date of

Completion

• Heritage type railing and integrated lake edge lighting along lake edge

• Improvement of Heritage Trekking Trail

o Nature Trail 1 - Land's End & Tiffin Top

o Nature Trail 2 - Naina Peak (Trail 1- Tiffin Top – Lands End Trail: Length 4.5 Km From Ayar Jungle Camp to Lands End + 1.17 Kms from LandsEnd to Barapatthar Trail 2 – TankiNaina Peak: Length 3 Km starting at Tanki)

Repair of damaged pathways Rough stone paving of steep, slushy stretches Provision of railings at outer sides in vulnerable stretches Wayside furniture at pause points Rain shelters at viewing points Camping sites Provision of portable toilets at appropriate points [where water pipeline already available] Signages [informative and regulatory]

Out of above proposed scope in the IEE (based on DPR) only the components listed below are being taken up:

18

Name & No. of

Package

Name of

the

contractor

Listing of works under the package

Starting Date(land clearance)

and schedule date of

completion Type of works

Continued at

Present

Progress %

Expected

change from

Approved

scope

Fulfillment

of objective

Type of

remedial

measures

needed

Key assumption

and risk affect

attainment the

objective Starting date Date of

Completion

Restoration of

• Catholic Church

• Methodist church

• Bishop Shaw

• Library Building

• Municipality Building

• DSA Flat

• Gandhi Ashram- Takula

• New Club

• DSB College Chapel

• Treatment of Dam Wall

• Repaving of Upper Mall

• Rickshaw Stand

• Lake Front Development

• Park Development

• Railing & Band Stand

• Construction of Toilets in Nainital- Cheena baba and National Hotel

• Improvement of High mass light Electricity

• Nature Heritage Trail: o Wayside furniture at pause

points o Rain shelters at viewing points o Camping sites o Provision of portable toilets at

appropriate points (water pipeline available)

19

Name & No. of

Package

Name of

the

contractor

Listing of works under the package

Starting Date(land clearance)

and schedule date of

completion Type of works

Continued at

Present

Progress %

Expected

change from

Approved

scope

Fulfillment

of objective

Type of

remedial

measures

needed

Key assumption

and risk affect

attainment the

objective Starting date Date of

Completion

o Signages (informative &regulatory)

Mechanical car parking component shall

be taken up in separate package

UK/IDIPT/III/BHT/01 Lot 2

UK/IDIPT/III/BH

T/03

Restoration

and adaptive

reuse of

Almora Fort

(Rani Mahal)1

The subproject

was bid out in

02 packages

(i) Rani Mahal

UK/IDIPT/III/BH

T/03

(ii)

MallaMahalUK/I

DIPT/III/BHT/06

M/s

Simplex

Project

Limited

407,

Skipper

Corner, 88

Nehru

Place, New

Delhi -

110019,

India

Scope as per IEE: Restoration of the historic sites: Ram Shila Temple and the MallaMahal or Fort Nanda Devi Complex 1.Revitalization of the entire precinct as a public space for experiencing regional history and culture, through creation of facilities such as:

• Develop cobblestone-paved courtyard as a performance arena.

• Create a Museum on Kumaon culture in the main building of the MallaMahal

• Create a Himalayan Art Gallery and nature interpretation centre in the Rani Mahal,

• Restoration of the historic site of Ram Shila Temple

• Creation of craft demonstration areas.

• Removal or concealment some buildings through strategic landscaping and foliage coverage of structures

• Create facilities in Almora town to enable it to emerge as a complete destination

19-10-2015 18-10-2017 1. Brick work in

non basement area in progress (80% work completed).

2. Staircase casting work in progress.

3. Brick work in

non basement

area 100% work

completed.

37.15% No Change

20

Name & No. of

Package

Name of

the

contractor

Listing of works under the package

Starting Date(land clearance)

and schedule date of

completion Type of works

Continued at

Present

Progress %

Expected

change from

Approved

scope

Fulfillment

of objective

Type of

remedial

measures

needed

Key assumption

and risk affect

attainment the

objective Starting date Date of

Completion

• Improve all three access routes that lead up to the fort and temple

• Improve accessibility, especially for the differently-abled through the setting up of elevators leading from bazaar to the site.

• Improve basic tourist and pilgrim facilities and amenities

• Improve vehicular parking facilities for about 100 vehicles in the town.

• Improve basic environmental services like solid waste and wastewater management.

• Enforcing strict standards for cleanliness and upkeep. Improving tourist/visitor wayside amenities along approximately 10 km of vehicular access. Improving access to places of tourist/pilgrim attractions by way of 15 km of connectivity improvement inclusive of roadside infrastructure and improved signage.

• Improving about 4 km of pedestrian environment connecting the heritage site with different parts of the town.

• Training and capacity building 2. Construction of District Collectorate office at Porth Free Estate near VikasBhavan. Construction of G + 4 building with office, parking within Govt.

21

Name & No. of

Package

Name of

the

contractor

Listing of works under the package

Starting Date(land clearance)

and schedule date of

completion Type of works

Continued at

Present

Progress %

Expected

change from

Approved

scope

Fulfillment

of objective

Type of

remedial

measures

needed

Key assumption

and risk affect

attainment the

objective Starting date Date of

Completion

land of 2500 sq m

For Almora District Collectorate office, Water supply is planned from municipal water supply and water line will be extended to proposed building.

For waste water – discharge 4 nos. of soak pit and 4 nos. of septic tank will be utilized. In total 64 nos. of toilet, 32 nos. urinal will be constructed

Solid waste will be stored in bins of adequate capacity from where collection will be done by Almora Nagar Palika

Out of above proposed scope in the IEE (based on DPR) only the components listed below are being taken up:

(i) Rani Mahal package has been awarded and scope is

• Restoration of Rani Mahal

• Restoration of Courtyard+ RamshilaTemple

• Restoration of Craft Centre + Toilet

• Restoration of SDM office

• Restoration of Fort Walls

22

Name & No. of

Package

Name of

the

contractor

Listing of works under the package

Starting Date(land clearance)

and schedule date of

completion Type of works

Continued at

Present

Progress %

Expected

change from

Approved

scope

Fulfillment

of objective

Type of

remedial

measures

needed

Key assumption

and risk affect

attainment the

objective Starting date Date of

Completion

• Signage Plan

• Civil work of Collectorate building in Almora

• Site Development and Landscaping

• Sanitary&

• Electrical Works

Following works shall be taken up in (ii) Malla Mahal package which is not yet awarded

• Museum on Kumaon culture in MallaMahal and

• Removal or concealment some buildings through strategic landscaping and foliage coverage of structures

UK/IDIPT/III/BH

T/05

Restoration

and adaptive

reuse of

Champawat

Fort (Banasur)

M/s

Simplex

Project

Limited

407,

Skipper

Corner, 88

Nehru

Place, New

Delhi -

1. The scope of this

sub-project includes:

a) Restoration of the historic

sites: Rajbhunga Fort and

Banasur Forts, or collectively

Champawat Forts, Restoration

of GoluDevta temple (3 km

from the Champawat fort) and

19.10.15 18.10.17 Tehsil Building-

Earth work &

PCC work of

foundation 100

% work

completed,

RCC work upto

plinth level -

100 %, work

completed, RR

26.50% Components

of GoluDevta

and Guru

Gorakhnath

temple have

been

dropped

23

Name & No. of

Package

Name of

the

contractor

Listing of works under the package

Starting Date(land clearance)

and schedule date of

completion Type of works

Continued at

Present

Progress %

Expected

change from

Approved

scope

Fulfillment

of objective

Type of

remedial

measures

needed

Key assumption

and risk affect

attainment the

objective Starting date Date of

Completion

110019,

India

Goraknath temple (40 km from

Champawat)

b) Revitalization of the entire

precinct as a public space for

experiencing regional history

and culture, through creation

of facilities.

(i) Rajbhunga Fort:

• Removal of existing and

undesirable structures

• Remodeling and

reconstruction of existing

structures:Old Fort &Tehsil

Office and SDM Office, Durga

Devi Temple, Courtyard and

Ramparts.

• Providing Tourist Facilities and

Amenities at fort like Ticket

Counter, Tourist Interpretation

Centre, Cafe & Shop,

Souvenir Shop, Library, Toilet

Block, Creation of link walk

way & Improving the existing

road and Lanes, 12 Bed Hotel,

stone 50%

work

completed,

Steel Binding of

columns 1st

floor -100 %

work

completed. 2.

Type 2

Building- Earth

work & PCC

work of

foundation 100

% work

completed ,

RCC work 100

% work

completed,

Brick work 1st

floor- 100 %

work completed

. 3. Type 4

Building- Earth

work & PCC

work of

foundation 100

% work

completed ,

RCC of footing

24

Name & No. of

Package

Name of

the

contractor

Listing of works under the package

Starting Date(land clearance)

and schedule date of

completion Type of works

Continued at

Present

Progress %

Expected

change from

Approved

scope

Fulfillment

of objective

Type of

remedial

measures

needed

Key assumption

and risk affect

attainment the

objective Starting date Date of

Completion

with 2 suites, Entrance way &

Reception, Water & Waste

Management, Solar lights.

(ii) GoluDevta Temple:

• Repair of Approach to

GoluDevta Temple

• Improvement of Worship

Space at GoluDevtaTemple

(iii) Guru Goraknath Temple:

• Shed and Railing at

Gorakhnath Temple

• Restoration of Wall at

Gorakhnath Temple

• Gazebos en route Gorakhnath

(iv) Other scope:

In training and capacity building

Present Scope of works includes

Banasur Fort:

• Removal of existing and

undesired structures and

and slab 100 %

completed, RR

stone - 50 %

work completed

25

Name & No. of

Package

Name of

the

contractor

Listing of works under the package

Starting Date(land clearance)

and schedule date of

completion Type of works

Continued at

Present

Progress %

Expected

change from

Approved

scope

Fulfillment

of objective

Type of

remedial

measures

needed

Key assumption

and risk affect

attainment the

objective Starting date Date of

Completion

relocation

• Remodelling and

reconstruction of existing

structures: 03 Gazebos en

route, shed on hilltop for café

Preparation of platform etc. on

site for Adventure Sport

Construction of new Tehsil building

• G+2 Tehsil building in 1400 m2 out of total land of 5400 m2. (Land to be transfer to Tourism dept. from KNVN)

• 1 number Type II quarter and 1 number Type IV quarter

• Garage facility and car parking

• Litigation room

• Boundary wall for whole area

• Approach road to site

Works in Rajbhunga will commence after construction of Tehsil building

Restoration

and Adaptive

Reuse of

M/S COX

Infratech

Private

• New multi-level car parking near Dev Singh Ground

01-07-2015 30-06-2016 Multilevel

Parking

1-Excavation work

36.83% 01 additional

block was

added to the

Appropriate

measures

have been

Weather

disturbances due

to heavy rains or

26

Name & No. of

Package

Name of

the

contractor

Listing of works under the package

Starting Date(land clearance)

and schedule date of

completion Type of works

Continued at

Present

Progress %

Expected

change from

Approved

scope

Fulfillment

of objective

Type of

remedial

measures

needed

Key assumption

and risk affect

attainment the

objective Starting date Date of

Completion

Pithoragarh

Fort Phase II

UK/IDIPT/III/BH

T/07

Limited in

JV with

Conaech

Associate

s

• Tourist Rest House by converting tehsil staff quarter in Fort premises

• New tehsil office building

• Accommodation for rehabilitation of Tehsil Staff Quarter Type IV – 1 no and Type II-6 nos.

• Signage and Waste bins

in progress. 2-Expansion joint footing excavation work in progress. 3-Welding of beams and boxes under process. 4-Additional Block retaining wall in progress. 5-Railing and barrier protection work is under process. 6-Third floor

seating and column extension works is under process. 7-Fourth floor terrace work is under process. 8-Third floor work in progress.

TRH Work

near

Pithoragarh

Fort

1-Retaining wall

work in progress. 2-Family suite

parking. taken for

fulfillment of

the

objectives.

snowfall may

delay the project

27

Name & No. of

Package

Name of

the

contractor

Listing of works under the package

Starting Date(land clearance)

and schedule date of

completion Type of works

Continued at

Present

Progress %

Expected

change from

Approved

scope

Fulfillment

of objective

Type of

remedial

measures

needed

Key assumption

and risk affect

attainment the

objective Starting date Date of

Completion

footing in progress.3-Excavation work in progress.

Name & No. of

Package

Name of

the

contracto

r

Scope of Works under Package

Starting Date(land

clearance) and schedule

date of completion Type of works

Continued at

Present

Progress

% age

Expected

change

from

Approve

d scope

Fulfillment

of

objective

Type of

remedial

measures

needed

Key assumption and

risk affect

attainment the

objective Starting

date

Date of

Completion

UK/IDIPT-III/KOT/01

Creation of

Pedestrian Route

for Pilgrims and

Tourists in Haridwar

M/s SS

Infratech Jv

, Tikola

Nagar,

Roorkee

a) Development of a pedestrian route or pathway for movement of pilgrims and tourist from near Mayapur Regulator to Bahadarabad Bridge. Total length of pedestrian pathway to be developed is 11.33 km. For a stretch of 5.9 km length (from near Mayapur Regulator to Jathwara bridge) the existing Kanwar Patri ( Route followed by Kanwarias) will be developed to a pedestrian pathway. For a stretch of 5.43 km (from Jathwara Bridge to Bahadarabad Steel Bridge) a

22/07/2015 21/07/2017 • Footpath work

is in progress

at Solani Park,

brick work is

complete. At

Solani Park

Paver work is

in progress.

• At Integrated

complex,

plumbing work

and brick work

is in progress.

50% Foot Over

bridge over

NH-58 at

Manglaur

Crossing

dropped

due to

work done

by NHAI

on the

same

location.

Appropriate

measures

have been

taken for

fulfillment of

the

objectives

In case of any

restrictions by the UP

Irrigation Department

and permissions of Foot

Over Bridge

Construction on NH-58

at Manglaur

28

pedestrian pathway will be developed on the side of existing motorable road (canal bank road). In this stretch of 5.43 km Kanwar Patri, and proposed pedestrian pathway and existing motor able canal bank road will exist.

b) Landscaping, sitting arrangements, murals, etc. on the proposed pedestrian pathway.

c) Providing lighting or illumination arrangement on the proposed pedestrian pathway of 11.33 km.

d) Providing safety hand railing on the pedestrian pathway on canal side.

e) Providing solid waste bins on the side of proposed pedestrian pathway.

f) Providing a toilet complex and drinking water facility on side of the proposed pedestrian pathway near Shankaracharya Chowk.

g) At one location near the proposed pedestrian pathway (before Lohe Ka Pul on railway track near Jawalapur) a multi facility complex will be developed which will include a toilet complex, drinking water fountain, bathing and sanitation facilities, rest shelter, food distribution centre, police control room, solid waste bins, compound wall with entrance gate, landscaping, etc.

h) Construction of a foot over bridge over Railway track near

Tile work in

Toilet complex

is in progress.

• Landscaping

work is in

progress along

the pathway

• Plantation

work is in

progress as

part of

landscaping

• Seating

arrangement

along the

pathway is in

progress

• Second floor

work is in

progress at

integrated

complex

• Work for four

number rest

shed is in

progress.

29

Jawalapur. i) Installation of tourist Signages on Kanwar Patri from Har Ki Pauri to Mangalour Cross. Total length of the stretch of Kanwar Patri to be taken up for the signage installation works is 42 km.

UK/IDIPT-III/KOT/02

Development of

Tourism

Infrastructure in

Sem Mukhem (

Tehri)

M/s

Mangalam

and

Constructio

n Company

in JV with

Sunil Garg

Company

Meerut

The main sub-project components include the following:

i. Dharamshala/ rest shelter at fair ground.

ii. Toilet complex at fair ground including septic tank with soak pit.

iii. Water supply Arrangement at Fair Ground

iv. Landscaping works at fair ground. Locally available materials shall be used for construction. The landscaping elements shall incorporate local foliages and flora of fairground so that the built environment is in sync with the background

v. Development of pathway from main road to fair ground.

vi. Solar lighting system along with normal outdoor lights is proposed at fair ground. Electricity source for illumination works is from Uttarakhand Power Corporation Limited and the same is reliable

vii. Development of existing small lake near fair ground. The existing small lake covers about 1500 sqm. area, while water spread area is 500 sqm.

viii. Solid waste bins and compost pits

23/09/2015 21/09/2017 For rest shelter (

including toilet

complex) all brick

work for

superstructure

completed. RCC

slab casting work

in progress.

Plumbing and

flooring work is in

progress.

• Pathway at fair

ground 95 %

work

completed

• Pathway for

Mukhem

Village is

completed

• RCC Slab

casting for

Pujari cottage

completed

• Renovation of

Mukhem village

temple is in

70% Canopy for

a length of

147 m,

component

dropped

Appropriate

measures

have been

taken for

fulfillment of

the

objectives

In case of adverse

weather conditions and

any disagreement with

Mela Committee and

village Panchayat

30

at Fair Ground. Solid wastes from Fair ground and Mandir complex will be collected in collection bins and ultimately dumped in to compost pit to be developed in the sub project.

ix. Murals depicting the story of Lord Krishna at 4 locations.

x. Providing solid waste bins and construction of compost pit in Mandir Complex. Solid wastes from Mandir complex will be collected in collection bins and ultimately dumped in to compost pit to be developed in the sub project.

xi. Solar light at the temple complex. xii. Canopy for a length of 147 m on

pathway in between fair ground and Nagraj Temple.

xiii. Hand rails and finishing works on pathway between fair ground and temple complex.

xiv. Facilities planned at Mukhem village are: a) Renovation of existing Temple

in Mukhem village. b) Renovation of existing entry

gate of Mukhem village. c) Development of internal roads

in Mukhem village. d) Expansion of existing pipe

water supply network. e) Installation of solar lighting

system, f) Solid waste management with

compost pits in Mukhem village.

progress-90 %

completed..

• Silt removal

from Jheel

completed.

Pitching work is

in progress.

• Septic tank 30

user

completed.

slab casting

31

• Tourism Signages on the 23Km road from Kodar to Fair Ground.

UKIDIPT/III/ GEN/03

Development of

Traditional Medicine

and Yoga Training

centers

M/s Bansal

Constructio

n,

Muzaffarna

gar

Development of Traditional Medicine Panchkarma and Yoga Centers at 3 TRHs/Resorts operated by GMVN in Garhwal Region (Dhanaulti, Rishikesh, Lansdowne) and at 5 TRHs/ Resorts operated by KMVN (Chiliyanaula, Kausani, Choukori, Naukuchiyatal and Sukhatal). New construction of above facilities is to be carried out only in Naukuchiyatal and Lansdowne, in the other locations facilities are planned within existing resorts by after interior refurbishment and slight alterations. The project progress includes civil component and procurements of equipments in a ratio of 60:40. Dhanaulti Sukhatal Chiliyanaula Kausani Chaukori Ganga Resort Lansdowne Naukuchiyatal

08/03/2017 07/03/2019 Location wise

Progress

update

TRH

Dhanaulti:

work

completed

TRH

Sukhatal:

Civil Works

started

TRH Kausani,

work in

progress

TRH

Chiliyanaula

TRH Ganga

Resort 5

100%

25%

15%

10%

5%

No change Appropriate

measures

have been

taken for

fulfillment of

the

objectives

Only in case of extreme

weather events,

otherwise magnitude of

works is very low and no

risk envisaged

Any other information useful for assessing environmental performance of the project:

9. No additional information during this period

32

2. Compliance Status

10. Status of Compliance with EARF/ADB Procedures is shown in Table 3.

Table 3: Status of Compliance with EARF/ADB Procedures S.No Name & No. of

Package

Environment

Category

Status of preparation of

IEE

Status of Approval

by ADB Date of Approval

Further Action needed For Compliance &

Responsibility

1 UK/IDIPT-III/ DDN/01 B Completed and approved Approved 03.08.2015 Regular monitoring and reporting of EMP

2 UK/IDIPT-III/ DDN/02 B Completed and approved Approved 01.09.2015 Regular monitoring and reporting of EMP

3 UK/IDIPT-III/DDN/03 B Completed and approved Approved 25.05.2016 Regular monitoring and reporting of EMP

4* UK/IDIPT/III/BHT/01Lot1 UK/IDIPT/III/BHT/01Lot2

B Completed and approved Approved 08.09.2015 Regular monitoring and reporting of EMP

5 UK/IDIPT/III/BHT/02 B Design stage

6* UK/IDIPT/III/BHT/03 UK/IDIPT/III/BHT/06

B Completed and approved Approved 09.07.2015 Regular monitoring and reporting of EMP

7* UK/IDIPT/III/BHT/04 UK/IDIPT/III/BHT/05

B Completed and approved Approved 06.08.2015 Regular monitoring and reporting of EMP

8 UK/IDIPT/III/BHT/07 B Completed and approved Approved 25.04.2016 Regular monitoring and reporting of EMP

9 UK/IDIPT-III/KOT/ 01 B Completed and approved Approved 11.05.2015 Regular monitoring and reporting of EMP

10 UK/IDIPT-III/KOT/ 02 B Completed and approved Approved 25.05.2015 Regular monitoring and reporting of EMP

11 UK/IDIPT-III/KOT/ 03 B Completed and approved Approved 28.03.17 Regular monitoring and reporting of EMP

12 UK/IDIPT/III/GEN/01 Goods Package

13 UK/IDIPT/III/GEN/02 B Completed and approved Approved 30.07.2015 Regular monitoring and reporting of EMP

14 UK/IDIPT/III/GEN/03 B Completed and approved Approved 03.03.2017 Regular monitoring and reporting of EMP

*S.no 4, 6 and 7, Project bifurcated into 02 packages

33

3. Compliance status with National/ State/ Local statutory environmental requirements

11. Status of Compliance with National/ State/ Local statutory environmental requirements is shown in Table 4.

Table 4: Status of Environment, Forest and other Clearance

Work (Package No.) Applicable Legislation/Type of

clearance Clearance Given by

and date Subject/Issue Remarks/Action needed

UK/IDIPT-III/ DDN/01

Development of Tourism Infrastructure in Kartikeya Swami Circuit (Lot-1) (Tungeshwar & Durgadhar Temple)

No environmental and forest clearance required. No requirement of NOC from ASI

Not applicable

UK/IDIPT-III/ DDN/02

Development of Tourism Infrastructure in Kartikeya Swami Circuit (Kartikeya Swami Temple)

Forest clearance required. No requirement of Environmental Clearance or NOC from ASI

Clearance received from MoEF& CC dt. 23.09.16

Kartikeya Swami Temple and pathway are located in Reserve Forest area, for which forest clearance was needed.

Works to be done as per Clearance conditions.

UK/IDIPT-III/DDN/03 Conservation and Development of Rural Tourism in district Rudraprayag, Chamoli and Uttarkashi

No Environmental and forest clearance required. NOC required from Forest Dept. for Tungnath location. No requirement of NOC from ASI.

NOC obtained from Forest Department, GoUkdt. 08/09/14

Out of 9 rural sites, Tungnath lies in buffer zone of Kedarnath Wildlife Sanctuary NOC received from Forest Department

Works to be done as per conditions of NOC given by the Forest department.

UK/IDIPT-III/KOT/01 Creation of Pedestrian Route for Pilgrims and Tourists in Haridwar

No environmental and forest clearance required. No requirement of NOC from ASI.

Not applicable

UK/IDIPT-III/KOT/02 Development of Tourism Infrastructure in Sem Mukhem

No Environmental and forest clearance required. (Only a minor canopy component was proposed in reserve forest since trek over which canopy has to be installed, falls in reserve forest). The same has been dropped.

Not required The project is for creation of Tourism Infrastructure in Sem Mukhem. No forest land acquisition involved, so no forest clearance required. The project site is not in ASI regulated Zone.

The canopy component has been dropped

UK/IDIPT-III/BHT/01 Conservation of Cultural Heritage and Urban

NOC from PWD, forest clearance required for pre fab toilets and view

NOC obtained from The project is for conservation of cultural heritage involving mostly repair, restoration

Forest Clearance of Tiffin Top is in process and related works will be

34

Work (Package No.) Applicable Legislation/Type of

clearance Clearance Given by

and date Subject/Issue Remarks/Action needed

Place making in Nainital Lot 1 points on nature trail (Tiffin top and Tanki China). No requirement of NOC from ASI.

PWD

Forest Clearance for nature trail for Tanki Cheena obtained

Forest Clearance for Tiffin Top is in process

works. There are 02 nature trails falling in reserve forest where portable toilet and viewpoints are proposed. So forest clearance required. The project site is not in ASI regulated Zone.

taken up after Clearance is obtained.

UK/IDIPT-III/BHT/03 Conservation and adaptive re-use of Almora Fort (Rani Mahal)

No Environmental and forest clearance required. No requirement of NOC from ASI.

Not applicable

UK/IDIPT-III/BHT/05 Conservation and adaptive re-use of Champawat Fort (Banasur)

No Environmental and forest clearance required.

Requirement of NOC from State ASI for Banasur Fort.

NOC obtained vide letter dt. 5th Dec, 2014.

Banasur Fort is a State Protected Monument and the custodian is State Culture Dept. NOC received from State Culture Dept.

Works as per NOC. Works should not interfere with the original character of the Fort structure.

UK/IDIPT/III/BHT/07

Restoration, Adaptive Reuse and Revitalization of Pithoragarh Fort

No Environmental and forest clearance required.

NOCs from line agencies obtained

NOC from District Administration for shifting Tehsil office NOC from Executive Engineer Nagarpalika Parishad Pithoragarh

NOC from District Sport officer

The project is for conservation of cultural heritage involving mostly repair, restoration works. Tehsil was housed in the Fort campus, which is to be relocated to carry on repair and restoration works in the Fort

Works to be done as per conditions of NOC given by line agencies and in line with their suggestions

UKIDIPT/III/GEN/03

Development of Traditional medicine and Yoga Training Centers

No Environmental and forest clearance required

Not applicable The project involves construction of yoga and panchkarma centres in existing Tourist Rest Houses of Tourism Dept. in 8 locations, wherein modification and refurbishment works are proposed in 06 TRHs while in 02 namely Lansdowne and Naukuchiyatal works will be done on vacant land within premises of the TRHs.

No action needed

35

4. Compliance status with the environmental covenants as stipulated in the Loan Agreement

12. The status of compliance with environmental loan covenants is presented in Table 5.

Table 5: Status of Compliance with Environmental Loan Covenants S. No Covenants Compliance

1. The Borrower and the States shall ensure that the preparation, design, construction, implementation, operation and

decommissioning of each Subproject and all Project facilities comply with (a) all applicable laws and regulations of the

Borrower and the States relating to environment, health, and safety; (b) the Environment Safeguards; (c) the EAFR; and (d) all

measures and requirements set forth in the respective IEE and EMP, and any corrective or preventative actions set forth in a

Safeguard Monitoring Report.

Compliance of (a) all applicable laws and regulations of the Borrower

and the States relating to environment, health, and safety (b)

Environment Safeguards; (c) the EARF; and (d) EMP is being

ensured during sub projects implementation.

Safeguards – Related Provisions in Bidding Documents and Works Contracts

The States shall ensure that all bidding documents and contracts for Works contain provisions that require contractors to:

(a) Comply with the measures and requirement relevant to the contractor set forth in the IEE, the EMPs, any RO and any

IPP (to the extent they concern impacts on affected people during construction), and any corrective or preventative

actions set out in a Safeguard Monitoring Report;

(b) make available a budget for all such environment and social measures;

© provide the relevant State with a written notice of any unanticipated environmental, resettlement or indigenous peoples

risks or impacts that arise during construction, implementation or operation of the Project that were not considered in the

IEE, the EMP, the or the IPP (if any): and

(d) Fully reinstate pathways, other local infrastructure, and agricultural land to at least their pre-project condition upon the

completion of construction.

Full EMP made part of the contract agreements of respective subprojects, thus its provisions being complied with.

Orientation sessions are being carried out in each site for better understanding of Safeguards Compliance by the Contractor Environmental monitoring and mitigation costs allocated/ incorporated in contract agreements. No such environmental impact has been identified so for that was not considered in the IEE and in the EMP. (If any such impact arises in future, will be suitably addressed) All the areas that if disturbed by construction activities will be restored to pre-project condition by the contractors.

Safeguards Monitoring and Reporting

11. The States shall do the following:

(a) Submit semi-annual Safeguards Monitoring Reports to ADB and disclose relevant information from such reports to

The fifth semiannual report for Loan No. 3223 IND is submitted herewith. Subsequent reports will be submitted on time.

36

S. No Covenants Compliance

affected persons promptly upon submission;

(b) if any unanticipated environment and/or social risks and impacts arise during construction, implementation or operation

of the Project that were not considered in the IEE, the EMP, any RP or any IPP, promptly inform ADB of the occurrence

of such risks or impacts, with detailed description of the event and proposed corrective action plan; and Report any

breach of compliance with the measures and requirements set forth in the EMP, any IPP promptly after becoming

aware of the breach.

In case of any unanticipated environmental risks and impacts arise, that shall be immediately informed to ADB with detailed description of the event and proposed corrective action plan. Breach will be reported to ADB immediately after becoming aware of it.

5. Compliance Status with Environment Management and Monitoring Plans as stipulated in the environmental documentation as agreed with ADB.

13. The compliance Status with Environment Management and Monitoring Plan is shown in Table 6.

Table 6: EMP Implementation Status

S.

No Sub Project Name

EMP Part of Contract Documents

(Yes/No)

EMP being Implemented (Yes/ No)

Status of EMP Implementation (Excellent/ Satisfactory/ Partially Satisfactory/ Below Satisfaction)

Actions Proposed/ Additional Corrective Measures Required

1 UK/IDIPT-III/ DDN/01 Yes Yes Partially Satisfactory Contractor directed to conduct regular environment monitoring

2 UK/IDIPT-III/ DDN/02 Yes Yes Partially Satisfactory Contractor directed to conduct regular environment monitoring

3 UK/IDIPT-III/ DDN/03 Yes Yes Partially Satisfactory Stockpiling to be properly done in Kabiltha and Harsil., Housekeeping to be improved at Phalasi, Usage of PPEs is to be ensured at Harsil. Submission of regular environmental monitoring report as per EMMP

4 UK/IDIPT/III/BHT/01 Conservation of Cultural Heritage and Urban Place making in Nainital Lot 1

Yes Yes Partially Satisfactory Contractor has been instructed for proper stockpiling of raw materials and waste in designated area with proper demarcation at the Municipality building and DSA flats site

5 UK/IDIPT/III/BHT/03 Conservation and adaptive re-use of Almora Fort (Rani Mahal)

Yes Yes Partially Satisfactory Instruction has been given to the contractor for proper stockpiling in demarcated area with barricades and to ensure the usage of PPEs.

6 UK/IDIPT/III/BHT/05 Yes Yes Satisfactory No suggestions.

37

S.

No Sub Project Name

EMP Part of Contract Documents

(Yes/No)

EMP being Implemented (Yes/ No)

Status of EMP Implementation (Excellent/ Satisfactory/ Partially Satisfactory/ Below Satisfaction)

Actions Proposed/ Additional Corrective Measures Required

Conservation and adaptive re-use of Champawat Fort (Banasur)

7 UK/IDIPT/III/BHT/07 Restoration, Adaptive Reuse and Revitalization of Pithoragarh Fort Phase II

Yes Yes Satisfactory No suggestions

8 UK/IDIPT-III/KOT/01 Creation of Pedestrian Route for Pilgrims and Tourists in Haridwar

Yes Yes Partially Satisfactory 1- The contractor has been instructed to maintain sanitation facilities at construction camp at integrated facilities complex

2- The contractor has been instructed to strictly confirm the usage of personal protective equipment.

9 UK/IDIPT-III/KOT/02 Development of Tourism Infrastructure in Sem Mukhem

Yes Yes Partially Satisfactory 1- The contractor has been instructed to maintain sanitation facilities at construction camp at Mela Ground

2 The contractor has been instructed to segregate all construction waste at one location at the Mela ground construction site and increase the frequency of water sprinkling at site

10 UKIDIPT/III/GEN/03 Development of traditional medicine and Yoga Training centres

Yes Yes Satisfactory No suggestions

6. Status of Implementation of Environment Management Plan

38

14. EMP Monitoring status of subprojects is presented in Table 7.

Table 7 (i): EMP Monitoring Status Chart- Development of Tourism Infrastructure In Kartikeya Swami Circuit (Lot-1) (Tungeshwar &Durgadhar Temple) IEE/EMP

Component Environmental issues Responsibility Compliance Status Corrective actions

UK/IDIPT-III/ DDN/01

Location Lack of sufficient planning to assure long term sustainability of the facilities and ensure protection specially from earthquake and other natural disasters

PMU & DSC Complied None

Pre-construction activities by the Contractor

1.Construction Camps 2. Defining of construction/work areas on ground for activities within 200m of the boundaries of the protected areas 3. Circulation plan during construction 4. Site clearance activities 5. Drinking water availability 6. Identification of disposal sites 7. Waste management on site

Contractor & DSC

Complied The waste material generated due to clearance and demolition activities is being used for filling and leveling at site only. Towards the end of construction phase, the site for disposal of waste material will be identified, keeping in view the quantity to be disposed off. The waste generated during the construction is segregated and stored at the site for possible reuse later. The waste disposal plan will be prepared in the end phase of construction period by the contractor and reviewed by the DSC and will be approved in consultation with PIU

Construction 1. Improper stockpiling 2.Quarry/ Borrow pit operations 3.Stripping, stocking & preservation of top soil 4.Soil erosion 5. Water pollution due to fuel/lubricants 6. Siltation of water bodies 7. Generation of dust

Partially Complied; environment monitoring reports are not submitted by

the Contractor timely

1. Stockpiles are separate and covered

2. The contractor is obtaining sand and sub grade from the licensed

quarries. No borrow pit operations have been carried out so far.

3. The excavated earth for foundation work of Dharamshala in

Tungeshwar is being used for filling.

4. No cutting or steep slope issues involved in the project.

5. No storage at site.

6. No water body in the impact area of the subproject.

7. Generation of dust is on account of material handling at site.

Necessary dust suppression measures such as water sprinkling are

followed.

Regular testing of air and noise as per EMMP

39

IEE/EMP

Component Environmental issues Responsibility Compliance Status Corrective actions

8.Emission from construction vehicles 9. Noise from construction equipment 10. Material handling at site 11. Disposal of construction waste/debris 12. Sanitation facilities at project site 13. Safety measures 14. Risks force majeure 15. Malaria risk

16.Chance archaeological finds 17.Religious structures 18. Construction Staff causing disruption to migratory birds

8. The construction vehicles usage is not much in the project. It is only for

the transportation of construction materials and there is a small concrete

mixer at site. The trucks carrying construction material have pollution

under control certificates.

9. In the current project the only noisy equipment used is concrete mixer

and it is operated intermittently. No excess noise generation is on

account of construction activities.

10. The material handling at site is satisfactory as most of the workers

were seen using personal protective equipment.

11. Construction waste generated so far has been stored for utilization

and disposal further at designated location.

12. Toilet block is functional

13. Use of PPE’s is satisfactory.

14. Risk Force Majeure: situation not occurred so far. Necessary action

will be taken as per contract provisions if such situation arises

15. Instructions have been given to contractor regarding malaria risk and

prevention measures.

16. Chance Archaeological finds have not been found so far during the

construction works. The contractor has been instructed to inform to PIU

and DSC, if any chance find is found.

17. The project is not impacting any religious structures rather its meant

for maintenance and restoration of religious structures.

18. There is neither any route of migratory birds nor any location where

migratory birds are visiting.

Operation 1. Environmental conditions 2. Uncontrolled tourism 3. Management of the toilet blocks 4. Adequate drainage 5. Unhygienic condition due to poor

maintenance of sanitation facilities and irregular solid waste collection

6. Increased waste loads onto the

PMU, UTDB The project not yet reached Operation phase Not applicable

40

IEE/EMP

Component Environmental issues Responsibility Compliance Status Corrective actions

existing waste disposal facilities

Table 7 (ii): EMP Monitoring Status Chart- Development of Tourism Infrastructure In Kartikeya Swami Circuit (Lot-2) (Kartikeya Swami Temple)

IEE/EMP

Component Environmental issues Responsibility Compliance Status Corrective actions

UK/IDIPT-III/ DDN/02

Location Lack of sufficient planning to assure long term sustainability of the facilities and ensure protection specially from earthquake and other natural disasters

PMU & DSC Complied None

Pre-construction activities by the Contractor

1.Construction Camps 2. Defining of construction/work areas on ground for activities within 200m of the boundaries of the protected areas 3. Circulation plan during construction 4. Site clearance activities 5. Drinking water availability 6. Identification of disposal sites 7. Waste management on site

Contractor & DSC Complied

None

Construction 1. Improper stockpiling 2.Quarry/ Borrow pit operations

3.Stripping, stocking & preservation of top soil 4.Soil erosion

Partly complied; Monitoring of Environmental parameters is not done regularly 1. The main construction materials being used are bricks, cement,

stone, sand and steel rods. These are being stocked properly.

2. The contractor is obtaining sand and sub grade from the

licensed quarries. No borrow pit operations have been carried out

so far.

Regular testing of air and noise as per EMMP

41

IEE/EMP

Component Environmental issues Responsibility Compliance Status Corrective actions

5. Water pollution due to fuel/lubricants 6. Siltation of water bodies 7. Generation of dust 8.Emission from construction vehicles 9. Noise from construction equipment 10. Material handling at site 11. Disposal of construction waste/debris 12. Sanitation facilities at project site 13. Safety measures 14. Risks force majeure 15. Malaria risk

16.Chance archaeological finds

17.Religious structures 18. Construction Staff causing disruption to

migratory birds

3. The excavated earth from pathway work, retaining wall and rest sheds is being simultaneously reused for filling and leveling. 4. The soil erosion issue is not there as there is no cutting and moreover the area is rocky. 5. The fuel and lubricants are not stored at site as project is small in nature. These are purchased from market as per need. 6. Natural water source but not within the impact zone. 7. Generation of dust is very less. 8. The construction vehicles usage is not much in the project. It is only for the transportation of construction materials and there is a small concrete mixer at site. The trucks carrying construction material have pollution under control certificates. 9. Maximum activities are done manually. 10. The material handling at site is fine as most of the workers were seen using personal protective equipment. 11. Construction waste generated so far has been stored for utilization and disposal further at designated location. 12. The sanitation facilities at construction camp are proper. 13. First aid kits have been equipped with suitable medicines and other materials like cotton, bandage etc. Use of PPE’s is satisfactory. Caution and caution sign board is put up at site. 14. Risk Force Majeure: situation not occurred so far. Necessary action will be taken as per contract provisions if such situation arises 15. Instructions have been given to contractor regarding malaria risk and prevention measures. 16. Chance Archaeological finds have not been found so far during the construction works. The contractor has been instructed to inform to PIU and DSC, if any chance find is found. 17. The project is not impacting any religious structures rather its meant for maintenance and restoration of religious structures. 18. There is neither any route of migratory birds nor any location where migratory birds are visiting.

Operation 1-Environmental conditions PMU, UTDB The project not yet reached Operation phase Not applicable

42

IEE/EMP

Component Environmental issues Responsibility Compliance Status Corrective actions

2.Uncontrolled tourism 3. Management of the toilet blocks 4. Adequate drainage 5. Unhygienic condition due to poor maintenance of sanitation facilities and irregular solid waste collection 6. Increased waste loads onto the existing waste disposal facilities

Table 7 (iii): EMP Monitoring Status Chart- Rural Tourism in District Tehri and Uttarkashi

IEE/EMP

Component Environmental issues Responsibility Compliance Status Corrective actions

UK/IDIPT-III/ DDN/03

Location Lack of sufficient planning to assure long term sustainability of the facilities and ensure protection specially from earthquake and other natural disasters

PMU & DSC Complied None

Pre-construction activities by the Contractor

1.Construction Camps 2. Defining of construction/work areas on ground for activities within 200m of the boundaries of the protected areas 3. Circulation plan during construction 4. Site clearance activities 5. Drinking water availability 6. Identification of disposal sites 7. Waste management on site

Contractor & DSC Complied Small construction camp only in Kabiltha site. No camp in remaining sites. Local labour are hired. Site clearance activities have been done. Potable drinking water is available in each site. The waste disposal plan will be prepared in the end phase of construction period by the contractor and reviewed by the DSC and will be approved in consultation with PIU

None

Construction 1. Improper stockpiling

Partially complied 1. Stockpiling is average. In Kabiltha and Harsil, material was not kept

• Stockpiling to be properly done in Kabiltha and Harsil.

43

IEE/EMP

Component Environmental issues Responsibility Compliance Status Corrective actions

2.Quarry/ Borrow pit operations 3.Stripping, stocking & preservation of top soil 4.Soil erosion 5. Water pollution due to fuel/lubricants 6. Siltation of water bodies 7. Generation of dust 8.Emission from construction vehicles 9. Noise from construction equipment 10. Material handling at site 11. Disposal of construction waste/debris 12. Sanitation facilities at project site 13. Safety measures 14. Risks force majeure 15. Malaria risk 16.Chance archaeological finds 17.Religious structures 18. Construction Staff causing disruption to migratory birds

in designated location and was uncovered. General housekeeping needs to be improved at Phalasi site. 2. The contractor is obtaining sand and sub grade from the licensed quarries in all the sites. 3. The excavated earth is being kept aside and is being simultaneously reused for filling and leveling. 4. Minor works. The soil erosion issue is not there as there is no cutting and moreover the area is rocky. 5. No storage of fuel and lubricants at site. 6.Natural water source in Harshil but not within the impact zone. 7. Generation of dust is very less. That is controlled through sprinkling. 8. Due to the magnitude of works, the construction vehicles usage is not much in the project. It is only for the transportation of construction materials and frequency is very less. 9. Most of the activities are manual. 10. The material handling at site is fine as most of the workers were seen using personal protective equipment. In Harsil site Contractor was directed to enforce usage of PPEs. 11. Construction waste generated so far has been stored for utilization and disposal further at designated location. The waste disposal plan will be prepared in the end phase of construction period by the contractor and reviewed by the DSC and will be approved in consultation with PIU 12. The existing sanitation facilities are utilized. 13. Use of PPE’s is satisfactory. Only in Harsil site Contractor was directed to enforce usage of PPEs. Caution sign board is also put up at all sites. 14. Risk Force Majeure: situation not occurred so far. Necessary action will be taken as per contract provisions if such situation arises 15. Instructions have been given to contractor regarding malaria risk and prevention measures. 16. Chance Archaeological finds have not been found so far during the construction works. The contractor has been instructed to inform to PIU and DSC, if any chance find is found. 17. The project is not impacting any religious structures rather its

• Housekeeping to be improved at Phalasi.

• Usage of PPEs is to be ensured at Harsil.

• Submission of regular environmental monitoring report

44

IEE/EMP

Component Environmental issues Responsibility Compliance Status Corrective actions

meant for maintenance and restoration of religious structures. 18. There is neither any route of migratory birds nor any location where migratory birds are visiting, in any of the sites.

Operation 1-Environmental conditions 2.Uncontrolled tourism 3. Management of the toilet blocks 4. Adequate drainage 5. Unhygienic condition due to poor maintenance of sanitation facilities and irregular solid waste collection 6. Increased waste loads onto the existing waste disposal facilities

PMU, UTDB The project not yet reached Operation phase Not applicable

45

Table 7 (iv): EMP Monitoring Status Chart- Conservation of Cultural Heritage and urban place making in Nainital Lot-1

IEE/EMP Component Environmental issues Responsibility Compliance Status Corrective actions

Location Lack of sufficient planning to assure long term sustainability of the facilities and ensure protection specially from earthquake and other natural disasters

PMU & DSC Complied Not Applicable

Pre-construction activities by the Contractor

1.Construction Camps 2. Defining of construction/work areas on ground for activities within 200m of the boundaries of the protected areas. 3. Circulation plan during construction. 4. Site clearance activities 5.Drinking water availability 6. Identification of disposal sites 7. Waste management on site

Contractor & DSC Complied Waste was dumped to a designated site. But due to filling of the site, identification of new site is being done by DFO and Distt Administration. Till the identification of new site, waste is stored near the working sites. As per above, presently the waste generated is segregated and stored at the site for possible reuse and disposal.

Contractor and PIU has been instructed to follow up with the District Administration Waste is to be suitably covered till final disposal at the designated site.

Construction 1. Improper stockpiling 2.Quarry/ Borrow pit operations 3.Stripping, stocking & preservation of top soil 4.Soil erosion 5. Water pollution due to fuel/lubricants 6. Siltation of water bodies 7. Generation of dust 8.Emission from construction vehicles 9. Noise from construction equipment 10. Material handling at site 11. Disposal of construction waste/debris 12. Sanitation facilities at project site

Partially Complied

• Proper stockpiling was not seen. So instructions were given to the Contractor.

• Silt prevention measures undertaken (silt traps) in Treatment of Dam wall, restoration of Band Stand and Municipal Library.

• Due to filling of the earlier designated site and time taken in designation of new site by the Distt Administration and DFO, presently the waste generated is segregated and stored at the site for possible reuse and disposal.

• At Library site, books were not covered leading to deterioration of the books

Contractor has been instructed for proper stockpiling of Construction material in demarcated area with barricades Contractor was directed to cover and pack all the books till completion of works in the library building

46

IEE/EMP Component Environmental issues Responsibility Compliance Status Corrective actions

13. Safety measures 14. Risks force majeure 15. Malaria risk 16.Chance archaeological finds 17.Religious structures 18. Construction Staff causing disruption to migratory birds

Waste management is not proper at DSA Flats site.

Operation

1-Environmental conditions PMU, UTDB The project not yet reached Operation phase

2.Uncontrolled tourism

3. Management of the toilet blocks

4. Adequate drainage

5. Unhygienic condition due to poor maintenance of sanitation facilities and irregular solid waste collection

6. Increased waste loads onto the existing waste disposal facilities

47

Table 7 (v): EMP Monitoring Status Chart- Restoration and adaptive reuse of Almora Fort (Rani Mahal)

IEE/EMP

Component Environmental issues Responsibility Compliance Status Corrective actions

UK/IDIPT/III/BHT/03

Location

Lack of sufficient planning to assure long term sustainability of the facilities and ensure protection specially from earthquake and other natural disasters

PMU & DSC Complied

Pre-construction activities by the Contractor

1.Construction Camps 4. Site clearance activities 5. Drinking water availability 6. Identification of disposal sites 7. Waste management on site

Contractor & DSC Complied The site clearance activities have been carried out and excavated earth has been kept aside. The waste material generated due to clearance and demolition activities has been used to the extent possible in the project. Towards the end of construction phase, the site for disposal of waste material will be identified, keeping in view the quantity to be disposed off. Waste management not proper

Waste management not proper. Stockpiles of waste to be properly covered till possible reuse in later stages or dispose of at identified disposal sites

Construction 1. Improper stockpiling 2.Quarry/ Borrow pit operations 3.Stripping, stocking & preservation of top soil 4.Soil erosion 5. Water pollution due to fuel/lubricants 6. Siltation of water bodies 7. Generation of dust 8.Emission from construction vehicles 9. Noise from construction equipment 10. Material handling at site 11. Disposal of construction waste/debris 12. Sanitation facilities at project site 13. Safety measures 14. Risks force majeure

Contractor & DSC Partially complied

• The main constructions materials at present being used are bricks, cement, stones, sand and steel rods. These are not stocked properly, for which instructions were given Material is being purchased from licensed quarries.

• Top soil generated from foundation work is preserved for landscaping

• No storage of fuels at site

• Frequency of transportation vehicles is very limited. The trucks carrying construction material have pollution under control certificates

• Duct suppression measures being undertaken

• Usage of PPE not proper and directions were given. Waste is presently stored at site. for utilization and

Instruction has been given to the contractor for proper stockpiling in demarcated area with barricades. Usage of PPE not proper and directions were given.

48

IEE/EMP

Component Environmental issues Responsibility Compliance Status Corrective actions

UK/IDIPT/III/BHT/03

15. Malaria risk 16.Chance archaeological finds 17.Religious structures 18. Construction Staff causing disruption to migratory birds

suitable disposal further at designated location

Operation 1-Environmental conditions 2.Uncontrolled tourism 3. Management of the toilet blocks 4. Adequate drainage 5. Unhygienic condition due to poor maintenance of sanitation facilities and irregular solid waste collection 6. Increased waste loads onto the existing waste disposal facilities

PMU, UTDB The project not yet reached Operation phase Not Applicable

49

Table 7 (vi): EMP Monitoring Status Chart- Restoration and adaptive reuse of Champawat Fort (Banasur) IEE/EMP Component Environmental issues Responsibility Compliance Status Corrective actions

UK/IDIPT/III/BHT/03

Location Lack of sufficient planning to assure long term sustainability of the facilities and ensure protection specially from earthquake and other natural disasters

PMU & DSC Complied

None

Pre-construction activities by the Contractor

1.Construction Camps 2. Defining of construction/work areas on ground for activities within 200m of the boundaries of the protected areas 3. Circulation plan during construction 4. Site clearance activities 5. Drinking water availability 6. Identification of disposal sites 7. Waste management on site

Contractor & DSC Complied

None

Construction 1. Improper stockpiling

Work progress in reporting period is very slow due to technical issues at site 1. The main construction materials being used are bricks, cement, stones, sand and steel rods. Proper stockpiling is done.

2.Quarry/ Borrow pit operations

2. Material is being purchased from licensed quarries. No quarrying/borrow pit operations

3.Stripping, stocking & preservation of top soil

3. Top soil generated from foundation work is preserved for reuse.

4.Soil erosion

4. The soil erosion issue is not there as there is no cutting or steep slope issues involved in the project.

5. Water pollution due to fuel/lubricants

5. The construction vehicles usage is not much in the project. Fuel/ lubricants are not stored.

6. Siltation of water bodies 6. No water body in immediate vicinity

7. Generation of dust 7. Work progress very slow. No significant dust generation

8.Emission from construction vehicles

8. Frequency of transportation vehicles is very limited. Material is carried manually to the Fort site.

50

IEE/EMP Component Environmental issues Responsibility Compliance Status Corrective actions

9. Noise from construction equipment

9. In the present phase, the only noisy equipment used is concrete mixer and it is operated intermittently.

10. Material handling at site 10. Usage of PPEs was not satisfactory.

11. Disposal of construction waste/debris

11. Presently stored at site. Construction waste generated so far has been stored for utilization and suitable disposal further at designated location

12. Sanitation facilities at project site

12. Sanitation facility at site improved.

13. Safety measures

13. PPEs were available but not used by many labourers

14. Risks force majeure

14. Risk Force Majeure situation has not occurred so far. Necessary action will be taken as per contract provisions

15. Malaria risk

15. Instructions issued regarding malaria risk and prevention were given.

16.Chance archaeological finds

16. Chance Archaeological finds have not been found so far during the construction works. The contractor has been instructed to inform to PIU and DSC, if any chance find is found

17.Religious structures

17.The project is not impacting any religious structures

18. Construction Staff causing disruption to migratory birds

18. There is neither any route of migratory birds nor any location where migratory birds are visiting

Operation 1-Environmental conditions PMU, UTDB The project not yet reached Operation phase Not Applicable

2.Uncontrolled tourism

3. Management of the toilet blocks

4. Adequate drainage

5. Unhygienic condition due to poor maintenance of sanitation facilities and irregular solid waste collection

6. Increased waste loads onto the existing waste disposal facilities

51

Table 7(vii): EMP Monitoring Status Chart – Restoration and Adaptive Reuse of Pithoragarh Fort, Pithoragarh

IEE/EMP

Components

Environmental Issues Responsibility Compliance Status Corrective Actions

UK/IDIPT/III/BHT/07

Location impacts Lack of sufficient planning to assure long term sustainability of the improvements and ensure protection of the assets created and the architectural character of the surroundings.

PMU & Line Agency

Complied Not applicable

Design & pre construction impacts

1. Increased storm water runoff from alterations of the site‘s natural drainage patterns due to additional structures in TRH complex and landscaping works in the area and on lake edge.

DSC & PIU Complied Not applicable

2. Selection of materials and construction technologies, if not carefully chosen, will adversely impact the aesthetic appeal of the destinations

3. Integration of energy efficiency and energy conservation programs in design of subproject components

Pre-construction activities by the contractor

1. Circulation plan during construction in the tourist destinations

Contractor & DSC

• Complied

• Construction/demolition waste is being disposed at designated site identified by PIU

Not applicable

2. Site clearance activities, including delineation of construction areas

3. Drinking water availability and water arrangement

4. Identification of sites for disposal of construction and demolition work

52

IEE/EMP

Components

Environmental Issues Responsibility Compliance Status Corrective Actions

Construction impacts 1. Improper stockpiling of construction materials cause impacts starting from obstruction of drainage, disturbance/safety hazard to tourists, etc. 2. Stripping, stocking and preservation of top soil 3. Soil Erosion 4. Soil and Water Pollution due to fuel and lubricants, construction waste 5. Generation of Dust 6.Emission from construction vehicles, equipment and machinery 7. Noise from construction equipment 8. Material Handling at Site 19. Disposal of Construction Waste/Debris/Cut Material 10. Safety Measures During Construction 11. Risk caused by Force Majeure 12. Malaria Risk

Contractor • Partially complied

• Stockpiles not demarcated and uncovered

• Water sprinkling is being done at construction site and construction material is being carried by covered trucks.

• Environment monitoring report is not being submitted regularly.

• Waste management at site to be improved

• Usage of PPEs is satisfactory

Proper stockpiling and coverage to be done General housekeeping at site needs to be improved and the liter bins needs to be regularly disposed at municipal dumping site. Contractor has been instructed to get regular testing of air water and noise as per EMP

O & M impacts 1. Environmental Conditions PMU, UTDB Not Yet Started

2. Adequate drainage of site area

53

Table 7 (viii) : EMP Monitoring Status Chart- Creation of Pedestrian Route for Pilgrims and Tourists in Haridwar IEE/EMP Component Environmental issues Responsibility Compliance Status Corrective actions

UK/IDIPT-III/KOT/01

Location 1 Siting of facilities 2 Lack of sufficient Planning 3 Impact on archaeological remains 4 Other

PMU & DSC Complied None

Pre-construction

activities by the

Contractor

1.Construction Camps 2. Defining of construction/work areas on ground for activities within 200m of the boundaries of the protected areas 3. Circulation plan during construction 4. Site clearance activities 5. Drinking water availability 6. Identification of disposal sites 7. Waste management on site

Contractor & DSC Complied

Not Applicable

Construction 1. Improper stockpiling 2.Quarry/ Borrow pit operations 3.Stripping, stocking & preservation of top soil 4.Soil erosion 5. Water pollution due to fuel/lubricants 6. Siltation of water bodies 7. Generation of dust 8.Emission from construction vehicles 9. Noise from construction equipment 10. Material handling at site 11. Disposal of construction waste/debris 12. Sanitation facilities at project site 13. Safety measures 14. Risks force majeure

Contractor and DSC Partially Complied

1. The main construction materials at present being used

are bricks, cement, sand and steel bars. These are being

stocked properly.

2. The contractor is obtaining sand and sub grade from the licensed quarries. No borrow pit operations have been carried out so far. 3- The top soil generated at Integrated facility complex site at Haridwar excavation was kept aside. Later it has been used in landscaping works. Similarly excavated scarified bituminous material at Solani Park has been used in the fill works. 4. The soil erosion issue is not there as there is no cutting or steep slope issues involved in the project.

The contractor has been

instructed to segregate the

waste at one location at

integrated facility complex

and enclose it with caution

tape.

The contractor has been

advised to improve bathing

and toilet facilities for

women work force.

The contractor has been

advised to improve the

housekeeping at Integrated

Multi Facility Complex site.

54

IEE/EMP Component Environmental issues Responsibility Compliance Status Corrective actions

15. Malaria risk 16. Chance archaeological finds 17.Religious structures 18. Construction Staff causing disruption to

migratory birds

5. The fuel and lubricants are not stored at site as project is small in nature. These are purchased from market as per needs. There is no maintenance of vehicles at site also. Hence there is no issue of soil and water pollution. 6. The excavated earth was generated at Integrated Multi Facility Complex. This earth was kept aside and is away from Upper Ganga canal. This earth after completion of foundation works has been used in filling. Hence no chance of any siltation in Canal due to construction activities . 7. Necessary dust suppression measures such as water spray are taken up. 8. The construction vehicles usage is only for the transportation of construction materials and a small concrete mixer at site. The trucks carrying construction material have pollution under control certificates. The mixer and small generator operate intermittently. 9. In the current period the only noisy equipment used is concrete mixer and it is operated intermittently. No excess noise generation is on account of construction activities. Noise monitoring is being taken up regularly. 10. The material handling at site is proper as most of the workers were seen using personal protective equipment during material handling. 11. So far maximum construction waste has been utilized in filling and rest is stored at site for disposal in later stages. Waste management at camp site in multi facility complex is not proper. 12. Sanitation facilities at construction camp (Toilets) not being maintained properly and many a times are not operational which pose risk of contamination of Upper Ganga canal water. 13. Usage of personal protective equipment ( PPEs) such as hand gloves, shoes, helmets, jackets , etc was seen.

55

IEE/EMP Component Environmental issues Responsibility Compliance Status Corrective actions

14. Risk Force Majeure situation has not occurred so far. Necessary action will be taken as per contract provisions 15. Actions taken by contractor to prevent water logging and conditions for breeding of mosquitoes. 16. Chance Archaeological finds have not been found so far during the construction works. 17. The project is not impacting any religious structures 18 The project site is located in an urban area and there is neither any route of migratory birds or any location where migratory birds are visiting.

Operation 1-Environmental conditions 2.Uncontrolled tourism 3. Management of the toilet blocks 4. Adequate drainage 5. Unhygienic condition due to poor maintenance of sanitation facilities and irregular solid waste collection 6. Increased waste loads onto the existing

waste disposal facilities

PMU, UTDB The project not yet reached Operation phase Not applicable

56

Table 7(ix): EMP Monitoring Status Chart- Development of Tourism Infrastructure in Sem Mukhem

IEE/EMP Component Environmental issues Responsibility Compliance Status Corrective actions

UK/IDIPT-III/KOT/02

Location impacts 1. Siting of facilities 2 Lack of sufficient planning 3.Impact on archaeological remains 4. Other

PMU & Line Agency Complied None

Design & pre construction

impacts

1. Impact on sensitive areas 2. Slope stability related issues 3. Increased storm water runoff 4. Impact on ground water quality 5. Impact on aesthetic appeal 6. Integration of energy conservation

DSC & PIU 1. No acquisition of any forest ( reserved/protected) area 2. The sub project construction works on pathway are on slope. The natural slope is maintained in the pathway and other construction works. The side slopes around pathway are compacted. 3. The storm water runoff issue is not be there at rest shelter or at pathway as these are in hilly terrain having quick natural drainage. No storm water runoff generation seen in Mukhem village. 4. No impact on ground water quality. Water requirement for construction is very less (<4000 liters/day) and is being met from nearby natural reservoir. The minor requirement for construction has no impact on reservoir or surrounding eco system. The waste water generation is well taken care. 5. No impact on aesthetic appeal due to construction works. 6. Integration of Energy conservation measures have been planned in the project design. The project plans to use solar lighting system and LED lighting.

None

Pre-construction activities by

the Contractor

1.Construction Camp 2. Defining of construction/work areas on ground for activities within 200m of the boundaries of the protected areas

Contractor & DSC Complied

None

57

IEE/EMP Component Environmental issues Responsibility Compliance Status Corrective actions

3. Circulation plan during construction 4. Site clearance activities 5. Drinking water availability 6. Identification of disposal sites 7. Waste management on site

Construction impacts 1. Improper stockpiling 2.Quarry/ Borrow pit operations 3.Stripping, stocking & preservation of top soil 4.Soil erosion 5. Water pollution due to fuel/lubricants 6. Siltation of water bodies 7. Generation of dust 8.Emission from construction vehicles and equipment 9. Noise from construction equipment 10. Material handling at site 11. Disposal of construction waste/debris 12. Safety measures 13. Risks force majeure 14. Malaria risk 15. Chance archaeological finds 16.Religious structures 17. Construction Staff causing disruption

to migratory birds

Contractor and DSC Partially Complied 1. The contractor is using cement, steel, sand and subgrade at pathway sites, temple site and at Mela Ground sites. Storage of construction material is not much as significant construction work has been completed. 2. The contractor is obtaining sand and subgrade from the licensed quarries and has been instructed to submit copy of license of the quarry. 3. The excavated earth for foundation works of rest shelter has been reused for filling. The Mela ground is a waste and barren land so top soil is of no importance as it has rocky and non fertile nature. The excavated earth from reservoir deepening near Mela ground has been used in filling works of retaining wall of this reservoir. 4. So far in the construction works no soil erosion issue has been identified. In the pathway works natural slope is maintained. At reservoir site, side slopes will be compacted and stabilized. 5. The fuel and lubricants are not stored at site and these are purchased on need basis so question of water pollution due to fuel and lubricants is not there. 6. The project involves deepening of reservoir near Mela Ground. The reservoir excavation work has been completed. The excavated earth mainly comprising of silt was kept aside. The side slopes of reservoir are being stabilised through compaction and pitching. The excavated earth is being used in fill works of retaining wall of this reservoir. 7. The generation of dust is there from construction

1-The contractor has been instructed to regularly submit the environment monitoring reports to PIU-PMU. 2-The contractor has been instructed to prepare plan for waste disposal from various sub project locations specially the excavated earth from the reservoir site. The earth should be used in fill works of retaining wall of reservoir. 3-The contractor has been advised to remove left over material from pathway construction sites.

58

IEE/EMP Component Environmental issues Responsibility Compliance Status Corrective actions

material handling such as sand, sub grade and cement. Necessary measures for dust suppression are taken at site as per needs. These measures include water spray and keeping sand and cement inside the cover shed. Keeping sand piles in semi wet form through water spray. Regular Environmental monitoring Is not being done by Contractor. 8. At project site no construction vehicles are used except trucks bringing construction materials at site. These trucks/tempos have pollution under control certificates. The only construction equipment used at site is currently mixer, which is Diesel Generator operated. This mixer is operating intermittently and as such there is no issue of air emissions. 9. In the current construction phase of project mixer is the only noise generating equipment is in operation. No noise issue has been felt during the site visits. This is operated intermittently. At Mukhem village temple site, and at pathway construction works are not taken up during night time. Noise level monitoring is not being taken up as per monitoring plan. 10. The material handling by the workers at site is proper as construction labour were seen using personal protective equipment such as gloves, shoes, helmets, etc. 11. Presently construction waste /debris generation was seen at rest shelter site at Mela Ground. The excavated earth has also been generated at Reservoir site due to deepening. The maximum construction waste will be reutilised. The material which cannot be used will be disposed off. For this a disposal plan will be prepared in later phase of construction period. The contractor has been advised to segregate waste and store at one place at Mela Ground. 12. The contractor has procured personal protective equipment such as helmets, gum boots, jackets, gloves, etc. These are being used. The work force of the

59

IEE/EMP Component Environmental issues Responsibility Compliance Status Corrective actions

contractor has been sensitized for use of PPEs by the DSC environmental expert during site visits. 13. So far conditions for Force Majeure have not been faced at the project site. 14. The project site being at an elevated height in a hilly terrain where low temperatures prevail. No mosquito breeding has been felt. However, contractor has been instructed to take necessary measures in consultation with local state health department. 15. Chance Archaeological finds have not been found so far during the construction works. The contractor has been instructed to inform to PIU and DSC , if any chance find is found. Necessary procedure such informing to state Archeological Department and waiting for their instruction, will be followed. 16. The existing temple at Mukhem village is being renovated so this will have a positive impact. The facilities being created at Mela ground will enhance pilgrimage at Sem Nagraj temple, so project overall will have positive impact on Religious structure. 17. No action needed as the project site is not close any route of migratory birds or any location where migratory birds are visiting.

O & M impacts 1. Environmental conditions 2.Uncontrolled tourism 3. Management of the toilet blocks 4. Adequate drainage 5. Unhygienic condition due to poor maintenance of sanitation facilities and irregular solid waste collection 6. Increased waste loads onto the existing waste disposal facilities

PMU,PIU and

Contractor (only

during defect liability

period)

1-Not Applicable as project not yet completed Not Applicable

60

Table 7(x): EMP Monitoring Status Chart- Development of Traditional medicine and Yoga Training Centres IEE/EMP Component Environmental issues Responsibility Compliance Status Corrective actions

Location impacts Lack of sufficient planning to assure long

term sustainability of the facilities and ensure

protection specially from earthquake and

other natural disasters . Finalization of

locations of project sites

PMU & Line

Agency

Complied. Work has not started in Naukuchiyatal and Lansdowne

None

Pre-construction activities by

the Contractor 1. Layout of components to avoid impacts on

the aesthetics of the sub-project sites

2. Increased storm water runoff from

alterations of the site’s natural drainage

patterns due to landscaping, excavation

works, construction of parking lots, and

addition of paved surface at sub-project sites

Contractor & DSC 1. Works presently are carried out only in 05 Tourist Rest Houses, out of which works have completed in Dhanaulti and is under progress in the remaining 04. Work as just started in Ganga Resort, Rishikesh. 2. Works are carried out within existing Tourist Rest House only and no natural drainage patterns are disturbed. No additional parking lots or landscaping planned as part of sub-project

None

Construction impacts 1.Construction Camps - Location, Selection, Design and Layout 2.Site clearance activities, including delineation of construction areas at sub-project sites 3.Drinking water availability for construction crew 4. Waste disposal 5. Improper stockpiling of Construction Material 6.Soil and Water Pollution due to fuel and lubricants, construction wastes 7.Siltation of water bodies due to spillage of construction wastes 8. Generation of dust 9.Emission from construction vehicles, equipment and machinery 10. Noise pollution 11.Material handling at site

Contractor and

DSC

Complied 1. Magnitude of works very less. No construction camp

required in any of the sites. 2. Works carried out within existing TRHs only. 3. Drinking water is being made available from existing

supply of TRHs. 4. Magnitude of waste generation is very less. Presently, it

is being stored at site, for reuse/ adequate disposal at later stages. The contractor has been advised to segregate waste and store at one place in the TRHs.

5. Since in all sites, modification/ refurbishment of existing TRHs is carried out, Storage of construction material is not much which is segregated and stored at site.

6. Storage of fuels is not required, and is brought from market as per needs. Construction waste requirement is also not much which is segregated and stored properly at site.

7. Works carried out within existing TRH, no issues of siltation of water bodies

None

61

IEE/EMP Component Environmental issues Responsibility Compliance Status Corrective actions

12.Disposal of construction waste/debris 13.Safety measures 14.Clearing of Construction Sites

8. The generation of dust is in very less amount Necessary measures for dust suppression are taken at site which include water spray and keeping sand and cement inside the cover shed. At all project sites, no other construction vehicles are used except trucks bringing construction materials at site. The magnitude of works being very less, the frequency of vehicles is very less.

9. No major noise generating equipment is in operation. No noise issue has been felt during the site visits. works are not taken up during night time.

10. Very few labour are involved as works are very small in nature. Construction labour were seen using personal protective equipment such as gloves, shoes, helmets, etc.

11. No major waste disposal required. Waste will be disposed off in consultation with the management of TRHs.

12. The contractor has procured personal protective equipment such as helmets, gum boots, jackets, gloves, etc. These are being used.

13. Construction camps have not been made in any of the sites, as work scope is very less.

O & M impacts Waste oil generation on account of Panchkarma facilities and its safe disposal Safety risks Unhygienic conditions due to poor maintenance of sanitation facilities and irregular solid waste collection

PMU,PIU and Contractor (only during defect liability period)

1-Not Applicable as project not yet completed and reached O&M Phase.

Not Applicable

62

7. Approach & Methodology engaged for environmental monitoring of the project

15. Continuous monitoring of EMP implementation is being carried out by DSC, PIU and PMU.

16. Concerned staff of DSC and PIU visit the construction sites and report to Team Leader DSC and

PMC about issues/ problems related to environmental non-compliance. Necessary directions, in case

of non-compliance are being issued to the contractors on the site and through letters about the

procedures to resolve the problems/issues or requirements. The Safeguards Staff of DSC conduct

regular site visits to monitor the implementation of safeguards measures on sites.

8. Monitoring of environmental receptors/ attributes

Monitoring basis

17. Monitoring for the implementation of Environmental Monitoring Plan/Management Plan is required to

be done to check if any adverse impact is being caused by the construction activities. The monitoring

of these variables is to be carried out in construction sites within 100 m impact zone of the sub

project.

18. The monitoring of environmental variables is to be carried out as per the agreed Environmental

Monitoring Plan.

Type of environmental receptor/ attribute to be monitored

19. The environmental attributes to be monitored include the air, noise and water quality parameters at

the construction sites in sub project sites. The air quality parameters monitored include RSPM

(PM10),PM2.5 SO2 and NO2. The water quality parameters include temperature, pH, electrical

conductivity (EC), dissolved oxygen (DO), biochemical oxygen demand (BOD), total suspended

solids (TSS), total dissolved solids (TDS) and turbidity. In case of noise the day and night time Leq

values are monitored.

63

Methods of monitoring and equipment used

20. The parameters and standard methodology used for monitoring is given in Table 8.

Table 8: Parameters and Methodology for Environmental Monitoring

Parameter Methodology

(PM10) High Volume Sampler method (attached with cyclone)/Respirable Dust samplers.

(PM2.5) PM2.5 sampler, Gravimetric method

SO2 IS Modified West and Gaeke Method

NO2 Jacob &Hochheiser Modified (Sodium Arsenite) Method.

Noise Level Direct Reading Sound Level Meter.

Temperature Digital/Mercury Thermometer Method.

pH Electrometric Method.

EC Electrometric Method.

DO Winkle’s Method Using Azide Modification

BOD5 Five Days BOD as per APHA 2005

TDS Digital Meter Method.

TSS Gravimetry (Filtration and Drying at 105oc)

Turbidity Nephelo Turbidity Method.

64

9. Implementation of Environmental Monitoring Plan

21. Implementation of Environmental Monitoring Plan for sub projects is shown in Table 9. Monitoring

Reports for 8 out of 10 works packages have been submitted in the reporting period. For the rest 02

directions have been given to the contractors for submission of reports.

Table 9 (i): Implementation of Environmental Monitoring Plan- For Projects under PIU DDN

Component

Periods of

monitorin

g

Parameters/Poll

utants Standard

Base line

status Monitoring result during project

Implementation

(UK/IDIPT-III/ DDN/03 Rural Tourism (Kabiltha) Construction Stage

Noise (near

main gate of

project site)

10-10-2017 Sound Level Leq.

dB(A)

Noise

Standards for

55 dB( A) for

Day Time and

45 dB( A) for

Night Time

Day time

L max -- 58.8

L Min 49.2

Leq - 52.3

CPCB Limit in

dB(A) Leq

(Residential

Area) 55.0

Sound Level Leq.

dB(A)

Noise

Standards for

55 dB( A) for

Day Time and

45 dB( A) for

Night Time

Night time

L max -- 49.3

L Min 33.1

Leq 45.4

CPCB Limit in

dB(A)

50.0

Ambient Air

Quality

(near back

side of

project site)

10-10-

2017

Particulate

Matter (PM10),

µg/m3

100 70.06

Particulate

Matter (PM2.5),

µg/m3

60 35.2

Sulphur Dioxide

(So2). µg/m3

80 10.08

65

Component

Periods of

monitorin

g

Parameters/Poll

utants Standard

Base line

status Monitoring result during project

Implementation

Nitrogen Dioxide

(No2) µg/m3

80 12.45

Carbon

Monoxide (Co),

mg/m3

4 0.70

Water

Quality

(drinking

water( tap

water )

10-10-

2017

PH (at 25°C)

Colour

Turbidity

Odour

Taste

Total Hardness

as CaCo3

Calcium as Ca

Alkalinity as

CaCo3

Chloride as CI

Magnesium as

Mg

Total Dissolved

Solids

Iron as Fe

Copper as Cu

Total Coliform

E. Coli

CPCB

Standards for

Surface water

bodies and

Drinking

Water

Standards for

Potable water

7.34

BDL (DL-5

Hazen) BDL

(DL-INTU)7.

Agreeable

Agreeable

206.1034

17.10

107.10

18.30,

17.40,

220.20,

0.11

0.01,

<2/I00ml

Absent

Component Periods of

monitoring

Parameters/Poll

utants Standard

Base line

status Monitoring result during project

Implementation

UK/IDIPT-III/ DDN/01 Lot1 (Durgadhar and Tungeswar)

66

Component Periods of

monitoring

Parameters/Poll

utants Standard

Base line

status Monitoring result during project

Implementation

Noise (near

main gate of

project site)

19-12-17 Sound Level

Leq. dB(A)

Noise

Standards for

55 dB( A) for

Day Time and

45 dB( A) for

Night Time

Day time

L max – 54.1

L Min 48.2

Leq - 52.3

CPCB Limit

in dB(A) Leq

(Residential

Area) 55.0

19-12-17 Sound Level

Leq. dB(A)

Noise

Standards for

55 dB( A) for

Day Time and

45 dB( A) for

Night Time

Night time

L max – 44.2

L Min 37.1

Leq 45.0

CPCB Limit in

dB(A)

50.0

Ambient Air

Quality (near

back side of

project site)

19-12-17

Particulate

Matter (PM10),

µg/m3

100 68.10

Particulate

Matter (PM2.5),

µg/m3

60 45

Sulphur Dioxide

(So2). µg/m3

80 8.20

Nitrogen Dioxide

(No2) µg/m3

80 21.10

Carbon

Monoxide (Co),

mg/m3

4 0.10

Water

Quality

(drinking

19-12-2017

PH (at 25°C)

Colour

CPCB

Standards for

Surface water

7.45

<5

67

Component Periods of

monitoring

Parameters/Poll

utants Standard

Base line

status Monitoring result during project

Implementation

water( tap

water )

Turbidity

Odour

Taste

Total Hardness

as CaCo3

Calcium as Ca

Alkalinity as

CaCo3

Chloride as CI

Magnesium as

Mg

Total Dissolved

Solids

Iron as Fe

Copper as Cu

Total Coliform

E. Coli

bodies and

Drinking

Water

Standards for

Potable water

BDL

Agreeable

Agreeable

258.2

65.22

243.40

12.12

18.05

342.0

0.08

<0.05

<2/I00ml

Absent

68

Component Periods of

monitoring

Parameters/Poll

utants Standard

Base line

status Monitoring result during project

Implementation

UK/IDIPT-III/ DDN/01 Lot1 (Durgadhar and Tungeswar)

Noise (near

main gate of

project site)

19-11-2017 Sound Level

Leq. dB(A)

Noise

Standards for

55 dB( A) for

Day Time and

45 dB( A) for

Night Time

Day time

L max – 53.2

L Min 40.4

Leq - 55.0

CPCB Limit

in dB(A) Leq

(Residential

Area) 55.0

19-11-2017 Sound Level

Leq. dB(A)

Noise

Standards for

55 dB( A) for

Day Time and

45 dB( A) for

Night Time

Night time

L max – 43.2

L Min 32.3

Leq 45.0

CPCB Limit in

dB(A)

50.0

Ambient Air

Quality

(near back

side of

project site)

19-12-2017

Particulate

Matter (PM10),

µg/m3

100 73.10

Particulate

Matter (PM2.5),

µg/m3

60 45.20

Sulphur Dioxide

(So2). µg/m3

80 6.30

Nitrogen Dioxide

(No2) µg/m3

80 19.00

Carbon

Monoxide (Co),

mg/m3

4 0.21

Water

Quality

19-12-2017 PH (at 25°C) CPCB

Standards for

7.25

69

Component Periods of

monitoring

Parameters/Poll

utants Standard

Base line

status Monitoring result during project

Implementation

(drinking

water( tap

water )

Colour

Turbidity

Odour

Taste

Total Hardness

as CaCo3

Calcium as Ca

Alkalinity as

CaCo3

Chloride as CI

Magnesium as

Mg

Total Dissolved

Solids

Iron as Fe

Copper as Cu

Total Coliform

E. Coli

Surface water

bodies and

Drinking

Water

Standards for

Potable water

<5

BDL

Agreeable

Agreeable

218.12

62.12

240.12

12.10

22.05

365.0

0.11

<0.05

<2/100ml

Absent

70

Table 9 (ii): Implementation of Environmental Monitoring Plan- For Projects under PIU Kotdwara

Component Periods of

monitoring Parameters/Pollutants Standard

Base

line

status

Monitorin

g result

during

project

Impleme

ntation

Remarks

UK/IDIPT-III/KOT/01 Creation of Pedestrian Route for Pilgrims and Tourists in Haridwar

Noise Post

Monsoon

season

Sound Level Leq. dB(A) Noise

Standards

for 55

dB( A) for

Day Time

and 45 dB(

A) for

Night Time

- (i)

Integrate

d Facility

Complex

Haridwar

1-Leq (

Day)

=48.6

dB( A)

2- Leq

(Night) =

41.50

dB(A)

3-Leq

(Min)

=40.2

dB(A)

4- Leq

(Max)

=54.7dB(

A)

(ii)

Monitorin

g was

not

carried

out at

Solani

Park

Roorkee

site as

no

construct

ion work

was in

progress

at this

site.

The values are well

within the stipulated

limits.

Air Quality Winter

Season

SO2, NOX, CO , PM10

and PM2.5

Monitoring at at

Integrated Facility

Complex site at

NAAQS

Standards

-

Industrial,

Residenti

al, Rural

and other

Areas

All parameters of

ambient air quality

are well within the

limits. Detailed

monitoring results

are given in

71

Component Periods of

monitoring Parameters/Pollutants Standard

Base

line

status

Monitorin

g result

during

project

Impleme

ntation

Remarks

Haridwar Annexure-2.

Particulate Matter < 10

micron

100

- 91.0

ug/m3

Particulate Matter < 2.5

micron

60µg/m3

- 39.2

site

Sulphur dioxide,(SO2 )

80 µg/m3

12.80

Nitrogen dioxide(NO2)

80 µg/m3

22.40

ug/m3

Carbon Monoxide (CO) 02

mg/m3 for

08 hrs

0.70

mg/m3

Water

Quality

Winter

Season

1- Drinking Water at

camp and

Construction site

(Ground Water)

Drinking

water

standards

specified

in IS:

10500

-

1-

Colour-=

<1 Hazen

Unit

2- Odour=

Agreeable

3-pH=

7.90

4- Total

Hardness

as

CaCO3=

176 mg/l

5- TDS=

252 mg/l

6- BOD=

no test

done

7- Total

Coliform=

Not

detected

8- Iron as

All parameters of

drinking water at

Haridwar Integrated

facility Complex are

well within the limits

of Drinking water

specified in IS:

10500

72

Component Periods of

monitoring Parameters/Pollutants Standard

Base

line

status

Monitorin

g result

during

project

Impleme

ntation

Remarks

2- Upper Ganga Canal

near Haridwar

Integrated Facility

Complex Site

CPCB

Standards

for Surface

Water

Quality

-

Fe =0.18

mg/l

9-

Chloride

as Cl= 62

mg/l

11-

Fluoride

as F <

0.20 mg/l

Annexure-

2.

1-PH=7.5

2-

Dissolved

Oxygen

=6.3 mg/l

3- BOD (3

Days at

27 oC)=

< 1mg/l

4- COD =

<5mg/l

5-

Electrical

Conductivi

ty= 243

mg/l

6-

Ammonia

= <10

mg/l

7-Coliform

= Absent

Dissolved Oxygen,

pH, BOD and

coliform bacteria

parameters meet

the CPCB norm for

surface water

category A.

UK/IDIPT-III/KOT/02 Development of Tourism Infrastructure in Sem Mukhem

Noise Winter

Season

Sound Level Leq. dB(A) Noise

Standards

for 55

dB( A)

for Day

Time and

45 dB( A)

for Night

Time

- Leq (

Day) at

Mela

Ground -

50.2

dB(A)

Leq

(Night) at

The noise levels

are well within limits

during day and night

times.

73

Component Periods of

monitoring Parameters/Pollutants Standard

Base

line

status

Monitorin

g result

during

project

Impleme

ntation

Remarks

Mela

Ground

=42.10

dB(A)

Leq (Min)

at Mela

Ground

=41.30

dB(A)

Leq

(Max) at

Mela

Ground=

58.0

dB(A)

Air Quality Winter

Season

SO2, NOX, CO , PM10

and PM2.5

NAAQS

Standards

-

Industrial,

Residenti

al, Rural

and other

Areas

All monitored

ambient air quality

parameters are well

within the stipulated

limits at Mela

Ground

Particulate Matter < 10

micron

100

85.40

ug/m3 at

Mela

Ground

Particulate Matter < 2.5

micron

Sulphur dioxide,(So2 )

Nitrogen dioxide(NO2)

Carbon Monoxide (CO)

60µg/m3

80 µg/m3

80 µg/m3

02 mg/m3

for 08 hrs

41.70

ug/m3

11.40

ug/m3

19.20

ug/m3

0.4

mg/m3

74

Component Periods of

monitoring Parameters/Pollutants Standard

Base

line

status

Monitorin

g result

during

project

Impleme

ntation

Remarks

Water

Quality

Winter

Season

Parameters specified

for Drinking water in

IS: 10500

Drinking

Water

Standards

specified

in IS:

10500

1- Colour

= <1

Hazen

units

2- Odour

=Agreeabl

e

3-

Turbidity =

1.2 NTU

4- pH=

6.6

5- Total

Hardness

= 96 mg/l

6- Iron as

Fe = 0.16

mg/l

7-

Chlorides

=

27.70mg/l

8-

Fluoride <

0.20 mg/l

9- TDS-

156 mg/l

10- Total

Coli form

- Not

Detected

All monitoring

parameters are for

drinking water

available at Mela

ground where

construction works

were in Progress.

The monitoring

parameters of

drinking water are

well within the

stipulated limits of

Drinking Water

specified in IS:

10500. Detailed

results are given

Annexure-2.

75

Table 9 (iii): Implementation of Environmental Monitoring Plan- For Projects under PIU Bhimtal

Component Periods of monitoring

Parameters/ Pollutants Standard Base line status

Monitoring result during

project Implementatio

n

Remarks

Restoration and Adaptive Reuse of Banasur Fort (Champawat)

Noise (near construction site)

12/11/2017 to 13/11/2017

Sound Level Lmax, Lmin. dB(A)

Noise Standards for 55 dB( A) for Day Time and 45 dB( A) for Night Time (Residential Zone)

Lmax -50.8(Day), 42.2 (Night) dB(A)

Lmax 55.8 (Day), 47.1 (Night) dB(A)

Values are well within permissible level

Lmin – 40.3(Day), 34.5 (Night) dB(A)

Lmin – 46.2(Day), 36.8 (Night) dB(A)

Leq – 43.2(Day), 35.2 (Night) dB(A)

Leq – 50.1 (Day), 39.0(Night) dB(A)

Noise (Back site)

12/11/2017 to 13/11/2017

Sound Level Lmax, Lmin. dB(A)

Lmax -50.8(Day), 42.2 (Night) dB(A)

Lmax 54.9 (Day), 48.8 (Night) dB(A)

Lmin – 40.3(Day), 34.5 (Night) dB(A)

Lmin – 44.1(Day), 38.6 (Night) dB(A)

Leq – 43.2(Day), 35.2 (Night) dB(A)

Leq – 49. (Day), 42.5(Night) dB(A)

Air Quality (near Back site)

12/11/2017 to 13/11/2017

SO2, NOX, CO, PM10 and PM2.5

NAAQS Standards Baseline Status Near Construction site,

All parameters of ambient air quality are well within the limits. Particulate Matter < 10

micron 100 µg/m3

60.10 µg/m3 72.19 µg/m3

Particulate Matter < 2.5 micron

60µg/m3

34.10 µg/m3 36.32 µg/m3

Sulphur dioxide,(So2 ) 80 µg/m3 7.10 µg/m3 7.11µg/m3

Nitrogen dioxide(NO2) 80 µg/m3 19.30 µg/m3 29.09 µg/m3

Carbon Monoxide (CO) mg/m3

02 mg/m3 for 08 hrs 0.20 mg/m3 0.24mg/m3

Air Quality (near back side of fort)

12/11/2017 to 13/11/2017

SO2, NOX, CO , PM10 and PM2.5

NAAQS Standards Baseline Status Near Back Side of Fort

All parameters of ambient air quality are well within the limits.

Particulate Matter < 10 micron

100 µg/m3 62.10 µg/m3 72.19 µg/m3

Particulate Matter < 2.5 micron

60µg/m3 30.15 µg/m3 36.32 µg/m3

Sulphur dioxide,(So2 ) 80 µg/m3 7.18µg/m3 7.11 µg/m3

Nitrogen dioxide(NO2) 80 µg/m3 17.10µg/m3 21.09 µg/m3

Carbon Monoxide (CO) mg/m3

02 mg/m3 for 08 hrs 0.22 mg/m3 0.24 mg/m3

Water Quality Drinking water Village :-(Near Construction Site Champawat)

14/11/2017 to 17/11/2017

pH CPCB Standards for Drinking Water Standards for drinking water specified in IS: 10500

7.20 7.40 All parameters of drinking water are well within the limits of Drinking water specified in IS: 10500

Colour <5 <5

Turbidity(NTU) BDL BDL

Odour Agreeable Agreeable

Taste Agreeable Agreeable

Total Hardness mg/L 189.00 190.91

Calcium as Ca 70.20 50.89

Alkalinity mg/l 138.00 209.70

76

Component Periods of monitoring

Parameters/ Pollutants Standard Base line status

Monitoring result during

project Implementatio

n

Remarks

Chloride mg/l 20.10 12.89

Magnisium and Mg 18.10 14.1

Total Dissolved Solids mg/l

325.24 268.80

Iron mg/l 0.10 0.14

Copper mg/l <0.05 <0.06

Total Coliform 100 ml. at

37℃ (MPN)

<2/100ml <2/100ml

E-Coli / 100ml(MPN) Absent Absent

Restoration and Adaptive Reuse of Library, Nainital

Noise (At Near Construction Site Library)

14/11/2017 to 15/11/2017

Sound Level Lmax, Lmin. dB(A)

Noise Standards for 55 dB( A) for Day Time and 45 dB( A) for Night Time (Commercial Zone)

Lmax -52.3(Day),43.1 (Night)dB(A) Lmin – 32.1(Day),35.2 (Night)dB(A) Leq- 44.2, 38.1

Lmax – 54.8(Day), 47.9 (Night)dB(A) Lmin – 37.1(Day), 34.6 (Night)dB(A) Leq- 44.2(Day) , 40.0 (Night)

Values are well within permissible level

Noise (back site, library)

14/11/2017 to 15/11/2017

Sound Level Lmax, Lmin. dB(A)

Noise Standards for 55 dB( A) for Day Time and 45 dB( A) for Night Time (Commercial Zone)

At Near Back Side Library Lmax -53.7(Day),43.1 (Night)dB(A) Lmin – 38.1(Day),31.8 (Night)dB(A) Leq- 42.0, 37.2

Lmax -59.2 (Day),46.8 (Night)dB(A) Lmin – 43.2 (Day), 35.1 (Night)dB(A) Leq- 51.2 (Day), 41.4 (Night)

Values are well within permissible level

Air Quality (Near construction site, Library)

14/11/2017 to 15/11/2017

SO2, NOX, CO , PM10 and PM2.5

NAAQS Standards Baseline Status Near Construction Site, Library

All monitored ambient air quality parameters are well within the stipulated limits of air quality.

Particulate Matter < 10 micron

100 66.18 ug/m3 69.88 ug/m3

Particulate Matter < 2.5 micron

60µg/m3 35.10 ug/m3 35.89ug/m3

Sulphur dioxide,(So2 ) 80 µg/m3 7.34ug/m3 10.01 ug/m3

Nitrogen dioxide(NO2) 80 µg/m3 18.15ug/m3 23.78 ug/m3

Carbon Monoxide (CO) mg/m3

02 mg/m3 for 08 hrs 0.20 mg/m3 for 08 hrs

0.39 mg/m3 for 08 hrs

Air Quality (Near back side library)

14/11/2017 to 15/11/2017

SO2, NOX, CO , PM10 and PM2.5

NAAQS Standards Baseline Status Near back side library

Particulate Matter < 10 micron

100

68.15ug/m3 68.80 ug/m3

Particulate Matter < 2.5 micron

60µg/m3 38.12ug/m3 31.04 ug/m3

Sulphur dioxide,(So2 ) 80 µg/m3 9.08 ug/m3 12.55 ug/m3

Nitrogen dioxide(NO2) 80 µg/m3 17.10ug/m3 23.07 ug/m3

Carbon Monoxide (CO) mg/m3

02 mg/m3 for 08 hrs 0.20 mg/m3 for 08 hrs

0.46 mg/m3 for 08 hrs

77

Component Periods of monitoring

Parameters/ Pollutants Standard Base line status

Monitoring result during

project Implementatio

n

Remarks

Water Quality Drinking water (Tap Water)

15/11/2017 to 18/11/2017

pH- CPCB Standards for Drinking Water Standards for Potable water

7.08 7.31 All parameters of drinking water are well within the limits of Drinking water specified in IS: 10500

Colour <5 <5

Turbidity –(NTU) BDL BDL

Odour – Agreeable Agreeable

Taste – Agreeable Agreeable

Total Hardness mg/L - 432 189.60

Calcium as Ca- 168 48.23

Alkalinity mg/l 265 197.45

Chloride- mg/l 15.62 13.54

Magnisium and Mg- 64.42 18365

Total Dissolved Solids – mg/l

420 242.09

Iron - mg/l 0.02 0.12

Copper mg/l <0.06

Total Coliform 100 ml. at 37℃ (MPN)

Absent <2/100ml

E-Coli / 100ml(MPN) Absent Absent

Water Quality Surface water –Naini lake

15/11/2017 to 18/11/2017

pH- CPCB Standards for Surface water bodies Standards for Potable water

7.80 7.65

Colour <5 <5

Turbidity(NTU) BDL BDL

Total Hardness mg/L - 362.50 218.97

Calcium as Ca - 98.52 43.78

Total Alkalinity mg/l 271.44 232.80

Chloride- mg/l 65.30 20.05

Magnisium Hardness - 36.34 24.81

Sulfate as SO4- 52.30 32.45

Nitrate as NO3 2.44 1.01

Flouride as F 0.8 0.49

Sodium as Na – 19.70 21.67

Potassium as K- 3.70 7.89

TKN as N- 1.40 32.40

Total Phosphorous 0.26 0.22

COD- 4.15 22.89

Phenolic Compound <0.002 <0.001

Iron as Fe mg/l 0.15 0.46

Boron - 0.26 0.20

Sodium Absorption ratio -

2.84 1.99

Free Ammonia as N- 0.82 0.43

Dissolved Oxygen - 7.00 8.01

BOD(3 days at 27) - 10.00 6.89

Zinc as Zn- 0.14 0.24

Arsanic as As -<0.012 <0.010

Mercury as Hg <0.002 <0.001

Total dissolved Solids mg/l

420 317.97

E-Coli / 100ml(MPN)

Restoration and Adaptive Reuse of Almora Fort (Rani Mahal)

Noise (Near Back Site)

10/11/2017 to 11/11/2017

Sound Level Lmax, Lmin. dB(A)

Noise Standards for 55 dB( A) for Day Time and 45 dB( A) for Night Time (Residential Zone)

Lmax -48.2(Day),40.3 (Night)dB(A) Lmin – 32.1(Day),32.8

Lmax -57.9 (Day), 42.89 (Night)dB(A) Lmin –

Values are well within permissible level

78

Component Periods of monitoring

Parameters/ Pollutants Standard Base line status

Monitoring result during

project Implementatio

n

Remarks

(Night)dB(A) Leq – 43.4(Day),38.1 (Night)dB(A)

44.9(Day), 36.6 (Night)dB(A) Leq – 49.7 (Day), 39.9 (Night)dB(A)

Noise (Near Construction Site)

10/11/2017 to 11/11/2017

Sound Level Lmax, Lmin. dB(A)

Noise Standards for 55 dB( A) for Day Time and 45 dB( A) for Night Time (Residential Zone)

Lmax -52.0(Day),42.4 (Night)dB(A) Lmin – 44.1(Day),34.3 (Night)dB(A)

Lmax – 55.9 (Day), 43.9 (Night)dB(A) Lmin – 43.8 (Day), 36.1 (Night)dB(A) Leq – 47.2 (Day), 38.5 (Night)dB(A)

Values are well within permissible level

Air Quality (Near Construction Site)

10/11/2017 to 11/11/2017

SO2, NOX, CO , PM10 and PM2.5

NAAQS Standards

All monitored ambient air quality parameters are well within the stipulated limits of air quality.

Particulate Matter < 10 micron

100 µg/m3

56.20 ug/m3 Near Vikash Bhawan Distt. Almora

77.11 ug/m3 Near Vikash Bhawan Distt. Almora

Particulate Matter < 2.5 micron

60µg/m3

29.33 ug/m3

35.02 ug/m3

Sulphur dioxide, (So2) 80 µg/m3

7.22 ug/m3

09.89 ug/m3

Nitrogen dioxide (NO2) 80 µg/m3

16.43 ug/m3

19.77 ug/m3

Carbon Monoxide (CO) mg/m3

02 mg/m3 for 08 hrs 0.3 mg/m3 for 08 hrs

0.28 mg/m3 for 08 hrs

Air Quality (Near Back side of Almora fort)

10/11/2017 to 11/11/2017

SO2, NOX, CO , PM10 and PM2.5

NAAQS Standards All monitored ambient air quality parameters are well within the stipulated limits of air quality.

Particulate Matter < 10 micron

100 µg/m3

61.81 ug/m3 74.04ug/m3

Particulate Matter < 2.5 micron

60µg/m3

23.09ug/m3

33.29ug/m3

Sulphur dioxide,(So2) Nitrogen

80 µg/m3

6.50ug/m3

8.07ug/m3

dioxide(NO2) 80 µg/m3 19.22 ug/m3 18.97ug/m3

Carbon Monoxide (CO) mg/m3

02 mg/m3 for 08 hrs 0.38 mg/m3 for 08 hrs

0.32mg/m3 for 08 hrs

Water Quality Drinking water (Tap Water)

12/11/2017 to 15/11/2017

pH- CPCB Standards for Surface water bodies and Drinking Water Standards for Potable water

7.22 7.35 All parameters of drinking water are well within the limits of Drinking water specified in IS: 10500

Colour <5 <6

Turbidity –(NTU) BDL BDL

Odour – Agreeable Agreeable

Taste – Agreeable Agreeable

Total Hardness mg/L - 345.0 170.0

Calcium as Ca- 86.55 74.89

Alkalinity mg/l -268.00 156.09

Chloride- mg/l 70.40 13.89

79

Component Periods of monitoring

Parameters/ Pollutants Standard Base line status

Monitoring result during

project Implementatio

n

Remarks

Magnesium 28.62 15.98

Total Dissolved Solids mg/l

365.00 212.80

Iron as Fe mg/l 0.12 0.15

Copper as Cu mg/l <0.05 <0.06

Total Coliform 100 ml. at 37℃ (MPN)

<2/100ml <3/100ml

E-Coli / 100ml(MPN) Absent Absent

80

Institutional Arrangements

Program Management

22. The Government of Uttarakhand through Department of Tourism (DOT) is the Executing Agency

(EA). The EA (i) assumes overall responsibility for the execution of the Project and reporting; (ii)

engage adequate permanent or fixed-term staff to implement the Project; (iii) setup a state-level

project management unit (PMU) and project implementation units (PIU); (iv) provide overall strategic

guidance on technical supervision and project execution; and (v) ensure overall compliance with the

loan covenants.

23. The implementing agency (IA) is the Uttarakhand Tourism Development Board (UTDB). The IA’s

responsibilities include (i) project planning and budgeting; (ii) day-to-day assistance, supervision and

guidance for the project implementation units and their consultants; (iii) review subprojects for due

diligence requirements and approve subproject proposals; (iv) bidding, evaluation and contract

award; (v) managing and disbursing funds; (vi) review compliance with loan covenants, contract

specifications, work plans and quality control; and (vii) consolidate and submit progress reports,

finance and accounting / audit reports, and matters requiring higher level decision to state-level

empowered committee (SLEC) and ADB.

24. A State-level empowered committee (SLEC) has been established in Uttarakhand, chaired by state’s

Chief Secretary, with Principal Secretary/Secretary of the Department of Tourism as member

secretary and comprised of secretaries from relevant line departments. The SLEC have been

empowered to take all decisions on behalf of the State and will (i) act as a policy making body, (ii)

provide overall advice and guidance to the State’s executing agency and PMU, and (iii) accord all

approvals under the Project.

25. Dept. of Tourism (DoT) has established a PMU, headed by a full-time program director (PD), and

consisting of personnel drawn from relevant line departments and market. Project Management Unit

(PMU) is established in Dehradun for the overall project management. The PMU is the nodal agency

for overall management of all program activities and will be responsible for: (i) project planning and

budgeting; (ii) providing day-to-day assistance, supervision and guidance for the PIUs and their

consultants; (iii) reviewing subprojects to satisfy ADB’s due diligence requirements and approving

subproject proposals submitted by PIU and line departments; (iv) bidding, evaluation and contract

award; (v) managing and disbursing funds; (vi) reviewing compliance with loan covenants, contract

specifications, work plans and quality control; (vii) consolidating and submitting progress reports,

finance and accounting/audit reports, and matters requiring higher-level decision, to the SLEC and

ADB. The PMU will be supported by a team of consultants.

26. The sub-project is being implemented by the Project Implementation Unit (PIU) of IA, i.e. UTDB,

comprising of personnel drawn from relevant line departments and outside of government and

headed by a Project manager. 03 Project Implementation Units (PIU) have been established for each

of the three circuits namely Bhimtal, Dehradun and Kotdwar. The PIUs are responsible for: (i)

prioritizing and preparing subproject proposals; (ii) providing day-to-day assistance, supervision and

guidance to the design and supervision consultants; (iii) conducting detailed assessments and

surveys including public consultation and input from stakeholders; (iv) preparing detailed designs,

specifications, schedule of quantity, bidding documents, and related documentation; (v) implementing

civil works and related activities; (vi) reporting to PMU; (vii) preparing regular progress reports for the

SLEC, the executing agency and ADB through PMU; and (viii) supervising construction, conducting

quality control, approving progress payments to contractors; and (ix) maintaining records and

accounts on an up-to-date basis and making these available to ADB, its missions, or auditors for

inspection.

81

27. The Project Management Consultant (PMC) has been engaged to provide support to the PMU in

overall planning, risk management, implementation, monitoring and evaluation of projects under the

Investment Program. The PMC also assists the PMU and PIUs in meeting the relevant requirements

of ADB, Government of Uttarakhand, and Government of India for project implementation. The PMC

reports and works under the overall guidance of the PMU. The scope of services of the PMC includes

but not necessarily be limited to: (i) planning, reporting, and communication; (ii) establishment of

procedures and systems; (iii) review and preparation of plans, manuals and reports; (iv) overall

Investment Program management, monitoring and implementation of PPMS; and (v) social,

environmental, archaeological, occupational health and safety, community participation and gender

action compliance monitoring.

28. The Design and Supervision Consultants (DSC) have been engaged to provide all necessary support

to and coordination with the EA, IAs, PMU and any other consultants engaged by the authorities to

achieve the desired outcomes of the Investment Program. The DSC reports to and work under the

overall guidance of the PIUs. The scope of services of the DSC includes but not necessarily be

limited to: (i) surveys, verification of feasibility studies and base maps; (ii) project planning and

management support to the PIU; (iii) finalization of design criteria, preparation of manuals, guidelines

and systems; (iv) preparation of detailed design and bid documents; (v) construction management

and contract administration; (vi) environmental, social, archaeological, cultural heritage, community

participation and gender action compliance monitoring; and (vii) capacity building of the service

providers for operational sustainability.

10.1 Institutional Arrangements For EMP Implementation

29. The institutional arrangements specify the arrangements for the implementation of environmental

provisions of the entire project.

Project Management Unit (PMU)

30. A Safeguards Specialist (SGS) is positioned in the PMU, who is responsible for overall

implementation of the environmental safeguard provisions. To look into the matters of forest

coordination, a Forest Conservation Specialist is also placed in the PMU.

Project Management Consultant (PMC) and Design and Supervision Consultants (DSC)

31. Project Management Consultants (PMC) and Design and Supervision Consultants (DSC) have been

recruited to provide assistance to the PMU and PIUs respectively in project implementation. Within

the PMC team an Environment Safeguards Specialist is positioned to provide overall direction for

management of environmental issues, and technical support to the PMU including implementation of

the environmental requirements according to ADB requirements, and assist in monitoring impacts

and mitigation measures associated with sub-projects. Towards addressing the environmental issues

in the project components during design and implementation, the DSC includes provisions for inputs

of Safeguards Specialist Environment.

32. The Safeguards Specialist of the DSC team is responsible for preparation of the Environmental

Assessment documents in line with the Environment Assessment Review Framework (EARF) and

supervises the implementation of the EMP provisions in the various sub-projects.

33. DSC Safeguard Specialist is placed in each of the three DSCs to support environmental

management functions including updating sub-project IEEs in respect to environmental management

plans in compliance with the ADB Safeguard Policy Statement, national and state level

environmental policies, rules and regulations, assisting in preparing IEEs, and assist in monitoring

impacts and mitigation measures associated with sub-projects. He is required to include mitigation

measures in designs where appropriate, and to specify other measures in construction contracts. In

82

addition to addressing the issues related to environmental management in the project, the DSC

Specialist plays a central role in ensuring capability building on Environmental Management of the

PMU/PIU, Contractor and Line Departments.

34. Contractors are required by their contracts to implement all specified mitigation, monitoring, and

reporting assigned to contractors as presented in sub-project IEE. Contractors have appointed

Environment and Safety Officers for implementation of environment and occupational safety

provisions at site.

35. Environmental monitoring is being undertaken by the PMU supported by the Safeguards Specialist of

DSCs and PMC

36. Contact Details of Safeguards Team is given below:

Unit Name Mobilized Since Phone E-mail

PMU

Ms. Anjali Semwal

April, 2013 +91-8191995004

[email protected]

PMC Mr. Navin Handa

Mr. Ardhendu Mitra

July 2016 – Till Feb, 2017*

July 2013 – Sep, 2015

*Expert has been demobilized since Feb, 2017. PMC has been requested for replacement of Expert.

+91-9599510994

[email protected]

DSC Dehradun

Mr. Ranjan Mallick

Mr. Abhay Srivastava

January, 2014 – Till date

April, 2013 – June, 2013

+91-94382000113

[email protected]

DSC Kotdwar

Mr. Shreeniwas Verma

October, 2013 – Till date +91 9811224458

[email protected]

DSC Bhimtal

Dr. A.K. Sharma

Dr. Aman Sharma

July -2015 to Till Date

March -2013 to May 2015

+91-09799242184

[email protected]

10. Public Consultation Details

37. Meaningful Public Consultation has been done with the stakeholders and the Community, in all the

project areas. Details of Public Consultation held in the Reporting period are given in Table 10.

Consultation Records and Photographs are provided in Annexure 2.

83

Table 10(i): Public Consultation Meetings for Tranche III sub-projects Under PIU Dehradun

Date of Consultation

Sub Project Site

Participants Number of Participants

Summary of Consultation/Decision taken

12.08.2017 Rural

Tourism

(Near Chopta

Market)

Community

members

(DPs)

15 Meetings and individual interviews were held

with Tentative Displaced Persons( DPs) near

Main Entrance of Tungeshwar Temple to

brief them about the technical details of

project and project implementation cycle;

project benefits as well as adverse impacts

envisaged during construction. It was

informed to all that up gradation of road works

will be taken up after renovation works of

temple(Probably next year) and as per ADB

policy advance notice and compensation will

be issued to them through project

implementation unit.

No Grievances was received from them and

given their consent for all kind of support

during execution for smooth execution of

works.

12.09.2017 &

13.09.2017

Rural

Tourism

(Harsil &

Mukhba)

Villagers

/District

Administra

tion

officials

30 Project scope and its components.

Requirement of Renovation of Helipad etc.

Villagers have given their consent to provide

all kind of support. District administration

suggested that the renovation work of helipad

should be complete before Nov because there

is heavy snowfall after the month of

November

10.11.2017 &

11.11.2017

Rural

Tourism

(Harsil &

Mukhwa)

Villagers,

the site

engineer,

supervisor

, worker

28 Project scope and its components. Some

Labors are at site are using PPEs while some

are working without PPEs. Safety shoes are

provided only to few workers.

Villagers have given their consent to provide

all kind of support. Workers are not aware

about PPEs and wages. Frequent orientation

and training of labors should be done. Safety

engineer must be deployed at site.

12.11.2017

to

14.11.2017

Katrikeyaswa

mi Temple

kartikeyaswa

mi,

Durgadhar

and

Tungeswar

Villagers,

the site

engineer,

supervisor,

worker

35 Project scope and its components. Some

Labors are at site are using PPEs while some

are working without PPEs. Safety shoes are

provided only to few workers. Villagers have

given their consent to provide all kind of

support. Workers are not aware about PPEs

and wages. Frequent orientation and training

of labors should be done. Safety engineer

must be deployed at site.

84

Date of Consultation

Sub Project Site

Participants Number of Participants

Summary of Consultation/Decision taken

16.12.2017 Durga Dhar Villagers,

Temple

Committee.

22 Introduction to the project and how rural

tourism is fast becoming an alternative IGA in

the rural areas. Pradhan of Bora village

expressed her non ability to run the hardware

but was confident that if they were given a

chance and the trainings they would definitely

run the show and wanted the projects help in

the same.

The Village temple committee is keen to take

over provided they are provided with trainings

to run the facility.

17.12.2017 Phalasi Villagers,

Temple

Committee.

29 Introduction to O& M plan and realizing the

importance of loan component which has to

be returned to ADB. The committee also

informed that 14 members are in the

committee and that they have regular peon

with a monthly pay scale of Rs 2000 for

smooth functioning of the committee. Villagers

have given their consent to provide all kind of

support.

18.12.2017 &

19.12.2017

Kanakchauri Villagers

and

Committee.

17 Introduction to O& M plan and realizing the

importance of loan component which has to

be returned to ADB. Villagers informed that

construction of the Dharamsala should be

complete have their major festival.

Villagers have given their consent to provide

all kind of support.

20.12.2017 Kabiltha Villagers

and

Committee.

34 Project scope and its components was

discussed. It was informed that various

initiatives taken by the UTDB department

including the building of Guest house as well

as solar lighting for the development of this

village.Villagers informed that every year,

Kalidas festival held in the village where

hundreds of poets gather.and there is huge

potential for homestays in this village.

Villagers have given their consent to provide

all kind of support.

21.12.2017 Rudra

Prayag

DTDO 08 Project scope and components was

discussed. The DTDO suggested that the

Durgadhar facility could be made as an

adventure cum training center. DTDO was of

the opinion that once a good community

based tourism model is established it could

lead to a rippling effect establishing rural

85

Date of Consultation

Sub Project Site

Participants Number of Participants

Summary of Consultation/Decision taken

tourism in the Rudrapryag District.

DTDO assured for all kind of support for the

effective implementation of CBT activities in

Rudra Prayag district.

Table 10(ii): Public Consultation Meetings for Tranche III sub-projects Under PIU Kotdwar Date of

Consultation Sub Project

Site Participants Number of

Participants Summary of Consultation/Decision taken

14.07.2017 Development of Pedestrian route for Pilgrims in Haridwar

Kanwarias (Pilgrims) during Kanwar Mela

16 The kanwaris were happy to note that such facilities are being created for safe passage in Haridwar city as well as facilities for rest, drinking water and sanitation facilities are being created.

14.07.2017 and 15-07-2017

Development of Pedestrian route for Pilgrims in Haridwar

Contractor

and labour

28 Following issues were discussed in detail: (a)Workers safety during construction like wearing of head gear, safety shoes etc ( b ) importance of sanitation and public hygiene (c)Equal wages (d) The workers were sensitized for usage of PPEs.

18/09/2017 Development of Pedestrian route for Pilgrims in Haridwar

Contractor and labour

15 Discussed camp safety and health and hygiene issue and the contractor was advised to improve housekeeping at camp site. Make sanitation facilities operational and enforce use of PPEs.

19/09/2017 Development of Tourism Infrastructure in Sem Mukhem

Temple committee members and community

10 A detailed consultation was conducted with the manager of temple committee, regarding O&M of the facility. Committee members requested to expedite the works for Mela in November.

28/11/2018 Development of Tourism Infrastructure in Sem Mukhem

Local NGO & DSC

5 A consultation was conducted with the representatives of a local NGO called Sem Mukhem Paryatan Vikas Samiti (NGO representative1- Birender Shah Bhandari ; 2] Rajendra Prasad Bhadola and 3] Mr. Sandip Chandolia). The social expert explained that the project under implementation will actively promote Community Based Tourism (CBT) and tourism supply chain initiatives. The participating NGO representatives were satisfied with the facilities and infrastructures provided. They informed that t h e NGO would like to participate further enhance the tourism activities in this area

86

Table 10(iii): Public Consultation Meetings for Tranche III sub-projects Under PIU Bhimtal Date of

Consultation Sub Project Site Participants Number of

Participants Summary of Consultation/Decision taken

26/07/2017 Restoration and Adaptive Reuse of Almora Fort (Rani Mahal)

DSC, PIU, Contractor, Labourers & Community Members

30 Discussions there with the representatives of PIU, concerned contractor, labourers, community members of nearby village located adjacent to the site on different issues relating to adoption of social and environmental safeguards measures by the contractors and labourers. Also had discussions with the District and Session Judge on safety issues, who is having his office nearby the construction site.

27/07/2017 Restoration and Adaptive Reuse of Champawat Fort

(Banasur)

DSC, PIU Representative PIU Contractor Labourers Community Members

25 Discussions with the stakeholders including local masses, representatives of PIU and contractors including labourers on different issues relating to social and environmental safeguards measures being implemented in the social.

28/07/2017 Nainital Lake Precinct

Revitalization, Enhancement and

Urban Place Making

DSC, PIU Representative PIU Representative Contractor. Community Members

18 Discussions with the stakeholders regarding adoption of social and environmental safeguards measures by the contractor and other stakeholders for effective implementation of the project activities.

30/07/2017 Restoration and Adaptive Reuse of Pithoragarh Fort

DSC, PIU, Contractor, Labourers

22 Discussions with the Site Engineer of PIU and representatives of the concerned contractors including labourers working at the site.

10/11/2017 Restoration and Adaptive Reuse of Pithoragarh Fort

“Community Awareness

Programme”

DSC, PIU Representative & Community Members

35 Discussion on Present status of ADB assisted tourism sub-projects in Pithoragarh district, village tourism, home stay management, Operation & Maintenance of Pithoragarh Fort.

11. Implementation of Grievance Redress Mechanism

38. Grievance Redress Committees at PMU and PIU level have been formed. The arrangement for implementation of GRM is that the affected person/aggrieved party can give their grievance verbally or in written to the local grievances committee. Grievances of affected person will first be brought to the attention of the implementing NGO or PIU who can resolve the issue at site level. If the matter is not solved within 7 days period by the NGO or PIUs, it will be brought to the Grievance Redress Committee constituted for the purpose in PIU. This GRC shall discuss the issue in its monthly meeting and resolve the issues within one month of time after receiving the grievance. If the matter is not resolved by GRC at PIU level within stipulated time, it shall be referred to GRC at PMU level by Project Manager of PIU. GRC at PMU shall discuss the issue and try to resolve it and inform the PIU accordingly. If the matter is not resolved by the GRC at PMU level within one month of time, the aggrieved person/party can bring the matter to The Court of Law. The PIU shall keep records of all grievances received including contact details of complainant, date of receiving the complaint, nature of grievance, agreed corrective actions and the date these were affected and final outcome. A complaint register will be maintained at PIU as well as sites of the subproject.

39. No grievance was observed in any sub project during the reporting period.

87

12. Any other environmental aspects, impacts observed during implementation which were not

covered earlier

40. No such impact observed during the reporting period

13. Details of Complaints received from public and action taken thereof to resolve

41. No complaint received during the reporting period.

14. Follow up actions and Conclusions

42. Site supervision is being regularly carried out to ensure that environmental impacts are being adequately mitigated and to ensure continuation of compliance with statutory regulations as required by laws and agreed upon in EMP. The contractors are being regularly guided and instructed to pay attention to environmental issues and adhere to the provisions of EMP.

88

Annexure 1: Photo Illustration

Annexure: 1(i): Photo Illustration of Work Progress- DSC Dehradun UK/ IDIPT-III/DDN/01

Development of Tourism Infrastructure in Kartikeya Swami Circuit (Durgadhar&Tungeshwar)

Temple path at Durgadhar Kitchen Block, Durgadhar

UK/ IDIPT-III/DDN/02

Development of Tourism Infrastructure in Kartikeya Swami Circuit (Kartikeya Swami Temple)

Guest House under construction, Kartikeya Swami temple Pathway & Railing post at Kartikeya Swami

UK/ IDIPT-III/DDN/03

Conservation and Development of Rural Tourism Infrastructure in District Rudraprayag, Chamoli & Uttarkashi

Construction of Bhogsala, Mukhwa Entrance gate of Mukhwa

89

Path way, Harshil Helipad construction, Harshil

Pathway work of Bagori village

Annexure: 1(ii): Photo Illustration of Work Progress- PIU Kotdwar

UK/ IDIPT-III/KOT/01

Creation of Pedestrian Route for Pilgrims and Tourists in Haridwar Project Site

View of Integrated Multi Facility Center Under Construction At Haridwar

90

Pathway along right bank of Upper Ganga Canal near

Solani Park at Roorkee

Stacking of Tiles Haridwar Site

UK/ IDIPT-III/KOT/02

Development of Tourism Infrastructure in Sem-Mukhem (Tehri) Project Site

Care Taker Room Beside Temple under Progress at Mukhem Village

Rest Shed Under Construction at Mela Ground

View of Reservoir Deepening and Side Slope Protection at Mela Ground

91

Annexure: 1(iii): Photo Illustration of Work Progress- DSC Bhimtal UK/ IDIPT-III/BHT/05 Restoration and adaptive reuse of Champawat Fort (Banasur)

Entrance gate Bansaur Fort, Champawat

Banasur Fort Site at Banasur, Champawat

Tehsil Building Type II Building

UK/IDIPT/III/BHT/01 Conservation of Cultural Heritage and urban place making in Nainital Lot-1

St. Francis Catholic Church View of Gandhi Ashram, Takula

92

UK/IDIPT/III/BHT/03 Restoration and adaptive reuse of Almora Fort (Rani Mahal)

Caution Signages at construction site, Almora Almora (District Magistrate office building)

UK/IDIPT/III/BHT/07 Restoration and Adaptive Reuse of Pithoragarh Fort Phase II

Box erection at Multilevel Car Parking Flooring at Multilevel Car Parking

Annexure 2: Consultation Records & Photographs

Consultation Records PIU-Dehradun Projects

Consultation with affected persons near Mandir Marg, Chopta

Meeting with Temple Committee, Durgadhar Meeting with temple committee , Phalasi

Meeting with Villagers, Kanakchauri Consultation with villagers Bora

94

Meeting with DTDO, Rudraprayag

Safeguard Awareness training to workers, Tungeshwar

Safeguard Awareness training to workers, Harshil

95

Consultation Records PIU Dehradun Projects

Consultation- Kartikeya Swami Temple Meeting -18/12/17

96

Consultation Records PIU Kotdwar Projects Consultation- Kanvashram -Attendance Sheet and

Photographs-14/07/17

Consultation- Kanvashram -Attendance Sheet and

Photographs-18/09/2017

97

Consultation Attendance Sheet- 18/09/2017 Consultation Attendance Sheet- 28/11/2017

98

Medical Aid Provided to Kanwarias by the Project Construction Team During Kanwar Mela

Creation of Pedestrian Route for Pilgrims and Tourist in Haridwar - Consultation

Consultation and safeguards orientation with Labour at Sem Mukhem

Consultations with the local NGO Representatives-Sem Mukhem

Consultation Records PIU

Community Awareness Program at Pi

CDO, Pithoragarh addressing the Participants

Consultation Records PIU Bhimtal Projects

at Pithoragarh DM, Pithoragarh addressing the inaugural session

Pithoragarh addressing the Participants Participants in the Community Awareness Programme

Pithoragarh addressing the inaugural session

Participants in the Community Awareness Programme

Annexure

Media Disclosure of Pithragath Fort sub project

Annexure – 3 News Paper Clipping

Media Disclosure of Pithragath Fort sub project