Environmental Monitoring Report
This report has been submitted to ADB by Program Management Unit, Government of Uttarakhand, Dehradun and the Asian Development Bank and is made publicly available in accordance with ADB’s Public Communications Policy (2011). It does not necessarily reflect the views of ADB.
This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Project Number: 40648-034 August 2018 Period: July 2017 – December 2017
IND: Infrastructure Development Investment Program for Tourism - Tranche 3
Submitted by: Program Management Unit, Government of Uttarakhand, Dehradun
1
Semi – Annual Environmental Monitoring Report
Loan No: 3223 IND Period: July to Dec 2017
IND: Infrastructure Development Investment Programme for Tourism, Uttarakhand (Tranche –III)
Prepared by Dept. of Tourism, Government of Uttarakhand for Asian Development Bank July, 2018
This Semi – Annual Environmental Monitoring Report is a document of the borrower. The views expressed
herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be
preliminary in nature.
2
Table of Contents
1. INTRODUCTION ........................................................................................................................................................................................................................................................................................................................................................................................................................................................ 5555
2. COMPLIANCE STATUS ........................................................................................................................................................................................................................................................................................................................................................................................................ 32323232
3. COMPLIANCE STATUS WITH NATIONAL/ STATE/ LOCAL STATUTORY ENVIRONMENTAL
REQUIREMENTS ........................................................................................................................................................................................................................................................................................................................................................................................................................................................................ 33333333
4. COMPLIANCE STATUS WITH THE ENVIRONMENTAL COVENANTS AS STIPULATED IN THE
LOAN AGREEMENT .................................................................................................................................................................................................................................................................................................................................................................................................................................................... 35353535
5. COMPLIANCE STATUS WITH ENVIRONMENT MANAGEMENT AND MONITORING PLANS AS
STIPULATED IN THE ENVIRONMENTAL DOCUMENTATION AS AGREED WITH ADB. ........................................................ 36363636
6. STATUS OF IMPLEMENTATION OF ENVIRONMENT MANAGEMENT PLAN ............................................................................................ 37373737
7. APPROACH & METHODOLOGY ENGAGED FOR ENVIRONMENTAL MONITORING OF THE
PROJECT .................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................... 62626262
8. MONITORING OF ENVIRONMENTAL RECEPTORS/ ATTRIBUTES ................................................................................................................................................ 62626262
9. IMPLEMENTATION OF ENVIRONMENTAL MONITORING PLAN ................................................................................................................................................................ 64646464
10.1 INSTITUTIONAL ARRANGEMENTS FOR EMP IMPLEMENTATION ................................................................................................................................................ 81818181
10. PUBLIC CONSULTATION DETAILS .................................................................................................................................................................................................................................................................................................................... 82828282
11. IMPLEMENTATION OF GRIEVANCE REDRESS MECHANISM ............................................................................................................................................................ 86868686
12. ANY OTHER ENVIRONMENTAL ASPECTS, IMPACTS OBSERVED DURING
IMPLEMENTATION WHICH WERE NOT COVERED EARLIER ........................................................................................................................................................................................................ 87878787
13. DETAILS OF COMPLAINTS RECEIVED FROM PUBLIC AND ACTION TAKEN THEREOF TO
RESOLVE ................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................ 87878787
14. FOLLOW UP ACTIONS AND CONCLUSIONS ............................................................................................................................................................................................................................................................ 87878787
3
List of Table
TABLE 1: PROJECT PROGRESS IN THE REPORTING PERIOD TILL JUNE, 2017 ............................................................................................ 7777
TABLE 2: WORK DETAILS AND RISKS FOR SUB PROJECTS ............................................................................................................................................................................................................ 8888
THE MAIN SUB-PROJECT COMPONENTS INCLUDE THE FOLLOWING: ........................................................................................................................................ 29292929
TABLE 3: STATUS OF COMPLIANCE WITH EARF/ADB PROCEDURES ............................................................................................................................................ 32323232
TABLE 4: STATUS OF ENVIRONMENT, FOREST AND OTHER CLEARANCE................................................................................................................ 33333333
TABLE 5: STATUS OF COMPLIANCE WITH ENVIRONMENTAL LOAN COVENANTS .................................................................... 35353535
TABLE 6: EMP IMPLEMENTATION STATUS ............................................................................................................................................................................................................................................................................................................ 36363636
TABLE 7 (I): EMP MONITORING STATUS CHART- DEVELOPMENT OF TOURISM
INFRASTRUCTURE IN KARTIKEYA SWAMI CIRCUIT (LOT-1) (TUNGESHWAR &DURGADHAR
TEMPLE) ........................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................................ 38383838
TABLE 7 (II): EMP MONITORING STATUS CHART- DEVELOPMENT OF TOURISM
INFRASTRUCTURE IN KARTIKEYA SWAMI CIRCUIT (LOT-2) (KARTIKEYA SWAMI TEMPLE) ............ 40404040
TABLE 7 (III): EMP MONITORING STATUS CHART- RURAL TOURISM IN DISTRICT TEHRI AND
UTTARKASHI ............................................................................................................................................................................................................................................................................................................................................................................................................................................................................................ 42424242
TABLE 7 (IV): EMP MONITORING STATUS CHART- CONSERVATION OF CULTURAL HERITAGE
AND URBAN PLACE MAKING IN NAINITAL LOT-1........................................................................................................................................................................................................................................................................ 45454545
TABLE 7 (V): EMP MONITORING STATUS CHART- RESTORATION AND ADAPTIVE REUSE OF
ALMORA FORT (RANI MAHAL) .................................................................................................................................................................................................................................................................................................................................................................................... 47474747
TABLE 7 (VI): EMP MONITORING STATUS CHART- RESTORATION AND ADAPTIVE REUSE OF
CHAMPAWAT FORT (BANASUR) ........................................................................................................................................................................................................................................................................................................................................................................ 49494949
TABLE 7 (VIII) : EMP MONITORING STATUS CHART- CREATION OF PEDESTRIAN ROUTE FOR
PILGRIMS AND TOURISTS IN HARIDWAR .................................................................................................................................................................................................................................................................................................................... 53535353
TABLE 7(IX): EMP MONITORING STATUS CHART- DEVELOPMENT OF TOURISM
INFRASTRUCTURE IN SEM MUKHEM ................................................................................................................................................................................................................................................................................................................................................ 56565656
4
TABLE 7(X): EMP MONITORING STATUS CHART- DEVELOPMENT OF TRADITIONAL MEDICINE
AND YOGA TRAINING CENTRES ........................................................................................................................................................................................................................................................................................................................................................................ 60606060
TABLE 8: PARAMETERS AND METHODOLOGY FOR ENVIRONMENTAL MONITORING ............................................ 63636363
TABLE 9 (I): IMPLEMENTATION OF ENVIRONMENTAL MONITORING PLAN- FOR PROJECTS
UNDER PIU DDN ........................................................................................................................................................................................................................................................................................................................................................................................................................................................................ 64646464
TABLE 9 (II): IMPLEMENTATION OF ENVIRONMENTAL MONITORING PLAN- FOR PROJECTS
UNDER PIU KOTDWARA ........................................................................................................................................................................................................................................................................................................................................................................................................................ 70707070
TABLE 9 (III): IMPLEMENTATION OF ENVIRONMENTAL MONITORING PLAN- FOR PROJECTS
UNDER PIU BHIMTAL ............................................................................................................................................................................................................................................................................................................................................................................................................................................ 75757575
TABLE 10(I): PUBLIC CONSULTATION MEETINGS FOR TRANCHE III SUB-PROJECTS UNDER
PIU DEHRADUN ............................................................................................................................................................................................................................................................................................................................................................................................................................................................................ 83838383
TABLE 10(II): PUBLIC CONSULTATION MEETINGS FOR TRANCHE III SUB-PROJECTS UNDER
PIU KOTDWAR .................................................................................................................................................................................................................................................................................................................................................................................................................................................................................... 85858585
TABLE 10(III): PUBLIC CONSULTATION MEETINGS FOR TRANCHE III SUB-PROJECTS UNDER
PIU BHIMTAL ............................................................................................................................................................................................................................................................................................................................................................................................................................................................................................ 86868686
ANNEXURE: 1(I): PHOTO ILLUSTRATION OF WORK PROGRESS- DSC DEHRADUN ................................................................ 88888888
ANNEXURE: 1(II): PHOTO ILLUSTRATION OF WORK PROGRESS- PIU KOTDWAR ........................................................................ 89898989
ANNEXURE: 1(III): PHOTO ILLUSTRATION OF WORK PROGRESS- DSC BHIMTAL ........................................................................ 91919191
ANNEXURE 2: CONSULTATION RECORDS & PHOTOGRAPHS ............................................................................................................................................................................................ 93939393
ANNEXURE – 3 NEWS PAPER CLIPPING ................................................................................................................................................................................................................................................................................................................ 100100100100
5
1. Introduction
Overall Project Description
1. The Infrastructure Development Investment Program for Tourism Financing Facility (the Facility) will
develop and improve basic urban infrastructure and services in the four participating states of Himachal
Pradesh, Punjab, Uttarakhand and Tamil Nadu—to support the tourism sector as a key driver for
economic growth. It will focus on: (i) strengthening connectivity to and among key tourist destinations;
(ii) improving basic urban infrastructure and services, such as water supply, road and public transport,
solid waste management and environmental improvement, at existing and emerging tourist destinations
to ensure urban amenities and safety for the visitors, and protect nature and culture-based attractions.
Physical infrastructure investments will be accompanied by: (iii) capacity building programs for
concerned sector agencies and local communities for better management of the tourist destinations and
for more active participation in the tourism-related economic activities, respectively.
2. The proposed Project targets enhanced economic growth and provision of livelihood opportunities for
local communities through tourism infrastructure development with a focus on preservation and
development of natural and cultural heritage and incidental services. The Project supports the state of
Uttarakhand to develop the tourism sector as a key driver for economic growth.
3. The Executing Agency (EA) for the Investment Program is Dept. of Tourism, Govt of Uttarakhand. The
Loan Agreement and Project Agreement for the IDIPT, Uttarakhand is 3223-IND. Project
Implementation Unit have been established in three towns respectively (Dehradun, Bhimtal and
Kotdwar) for implementation of sub-projects. Design and Supervision Consultants (DSCs), has already
been established in three towns for designing the Infrastructure, managing the tendering of Contractors
and supervising construction, and providing support to the PIUs.
Outputs of the Project
4. The outputs of the Project are as follows:
Component 1: Urban Infrastructure and Service Improvement
Component 2: Improved connectivity
Component 3: Quality Enhancement of Natural and Cultural Attractions
Component 4: Greater participation by local communities
Component 5: Capacity Development, Community Participation and Project Management
6
Environment Category:
5. The project under IDIPT was categorized as Environment Category “B”, according to ADB’s Safeguard
Policy Statement (2009). All the subprojects under execution have been categorized as category 'B'.
Environment Performance Indicators, if any:
6. For effective monitoring, selected environmental parameters have been identified as indicators which
may be qualitatively and quantitatively measured and compared over a period of time in order to
assess/ ensure the compliance to environmental management plans (EMPs). The environmental
performance indicators selected are physical, biological and social characteristics identified as most
important in affecting the environment at critical locations at all the sub projects. The parameters
identified as performance indicators are:
1. Compliance with environmental management and monitoring plan
2. Compliance to State/ National environmental regulations.
3. Monitoring of ambient air quality, water quality and noise levels and comparison with baseline
environmental quality and State/ National Standards.
Overall project progress, agreed milestones and Implementation schedule
7. Construction works for the following sub projects are in progress and shown in Table 1.
7
Table 1: Project Progress in the Reporting Period till June, 2017
SI. No.
Package Ref No.
General Description Goods or Works
Contract Signing Date and Start
date Name of the Contractor Contract Value
Contract period
1 UK/IDIPT-III/ DDN/01 Lot1
Development of Tourism Infrastructure In Kartikeya Swami Circuit (Lot-1) (Tungeshwar & Durgadhar Temple)
LOA 22.01.16 Work started 26.02.2016
M/s Aaradhya Engineers & construction pvt Ltd.,2nd Tulsi Vihar, Hardiwar road ,Post –Virbhadra ,Rishikesh (UA)
INR 7.59 Cr.
24 months
2 UK/IDIPT-III/ DDN/02
Development of Tourism Infrastructure in Kartikeya Swami Circuit (Kartikeya Swami Temple)
LOA issued 23.05.16 Work started 07.07.2016
M/S APS Structures Private Ltd,Fort Sports complex ,Tara Hall,Mussorie
INR 3.97 Cr.
24 months
3 UK/IDIPT-III/DDN/03
“Conservation & Development of Rural Tourism Sites of Rudraprayag, Chamoli and Uttarkashi Districts of Uttarakhand”
LOA issued 23.05.16 Work started 02.08.2016
M/S Navya Associates in JV with Agrawal Brothers INR 15.26 Cr. 24 months
4 UK/IDIPT/III/BHT/01
Conservation of Cultural Heritage and urban place making in Nainital Lot-1
19-10-2015
M/s Simplex Project Limited 407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India
INR 38.52Crore 24 months
5 UK/IDIPT/III/BHT/03
Restoration and adaptive reuse of Almora Fort (Rani Mahal)
19-10-2015
M/s Simplex Project Limited 407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India
INR 29.90 Crore 24 months
6 UK/IDIPT/III/BHT/05
Restoration and adaptive reuse of Champawat Fort (Banasur)
19-10-2015 M/s Simplex Project Limited 407, Skipper Corner, 88 Nehru Place, New Delhi - 110019, India
INR 15.53Crore 24 months
7 UK/IDIPT-III/ KOT/01
Creation of Pedestrian Route for Pilgrims and Tourists in Haridwar
22/07/2015 M/s SS InfratechJv, Tikola Nagar, Roorkee, Haridwar 247670
INR 22.38 Cr.
24 months
8 UK/IDIPT-III/KOT/02
Development of Tourism Infrastructure in Sem Mukhem
22/08/2015 M/s Mangalam and Construction Company in JV with Sunil Garg and Company, Kesarganj, Meerut.
INR 10.18 Cr.
24 months
9 UK/IDIPT/III/BHT/07
Restoration and Adaptive Reuse of Pithoragarh Fort Phase II
05/07/2016 M/S COX Infratech Private Limited in JV with Conaech Associates
INR 27.11 Cr.
24 months
10 UKIDIPT/III/GEN/03
Development of Traditional Medicine and Yoga Training Centers
08/03/17 M/s Bansal Construction INR 3.76 Cr. 24 months
8
8. Work Details In the reporting period has been shown in Table 2.
Work progress of 10 packages is reported in table 2. Photographs showing work progress are provided in Annexure 1.
Table 2: Work Details and Risks For sub projects
Name & No. of
Package
Name of
the
contractor
Listing of works under the package
Starting Date(land clearance)
and schedule date of
completion Type of works
Continued at
Present
Progress %
Expected
change from
Approved
scope
Fulfillment
of objective
Type of
remedial
measures
needed
Key assumption
and risk affect
attainment the
objective Starting date Date of
Completion
UK/IDIPT-III/
DDN/01 Lot1
Development of
Tourism
Infrastructure In
Kartikeya Swami
Circuit (Lot-1)
(Tungeshwar,
Durgadhar
Temple)
Aradhya
Engineers
Durgadhar Temple precinct
Upgradation of infrastructure around the approach area of the temple, including drinking water facilities and sanitation
Parking facility and vehicular approach along with adjoining retaining walls
Solid waste management
Pathway development with railings & protection wall wherever necessary and signage and seating and lighting
Temple entrance arch
Improvement of the temple complex in terms of restructuring of the newly added temporary structures and overall landscaping to facilitate better movement and space for gathering of pilgrims and tourists
Lodging facilities with rooms and dormitories and toilet block at the rear side of the temple complex and a langar hall
Area confinement with edge wall , viewing
22.01.2016 21.01.2018 DURGADHAR:-
Guest house
Door and window
Shutters
completed
including
polishing work,
Internal work in
progress
flooring and
painting coning
Stone work
Path way
Out site electry
work like
transformer and
street light
Main Temple: -
47.00% Not
visualized till
now
Nil Frequent Weather
disturbances
during monsoon
season may delay
the work progress
9
Name & No. of
Package
Name of
the
contractor
Listing of works under the package
Starting Date(land clearance)
and schedule date of
completion Type of works
Continued at
Present
Progress %
Expected
change from
Approved
scope
Fulfillment
of objective
Type of
remedial
measures
needed
Key assumption
and risk affect
attainment the
objective Starting date Date of
Completion
decks etc
Restoration of Temple premises Construction of C.C road(main road to Temple,400 mtr length with drain
Development of Solar lighting and Fire Fighting work.
Capacity building for temple committee members for O&M activities.
Tungeshwar Temple precinct
Entrance area development with appropriate signage
Development of the 1.5km long pathway with railing to the main temple, increase in width and edge protection wherever required.
Seating arrangements , viewing decks and toilet facilities
Signage along the pathway and Temple premises.
Improvement in the temple precinct
Construction of entrance gate
Lodging facilities and langar hall
Development of Solar lighting and Fire Fighting work
stone cladding
Temple dome
work in progress
after completion
of temple frame
TUNGESHWAR:
Dharamshala:-
Clay tile work at
roof completed
Internal finishing
work in progress
Guest house
coloring and final
touches
Door and window
fitting
Kitten roofing
work continuing
10
Name & No. of
Package
Name of
the
contractor
Listing of works under the package
Starting Date(land clearance)
and schedule date of
completion Type of works
Continued at
Present
Progress %
Expected
change from
Approved
scope
Fulfillment
of objective
Type of
remedial
measures
needed
Key assumption
and risk affect
attainment the
objective Starting date Date of
Completion
Improvement in the drinking water facility for the approach areas
Capacity building for temple committee members for O&M activities.
UK/IDIPT/III/DD
N/02
Kartikeya Swami
Temple
M/s APS
Structure
Pvt.
Ltd ,Fort
Sports
Complex,
Tara Hall,
Mussorie
Civil Work Pedestrian Pathway Sitting Arrangement Railing at Temple Premises Pathway Renovation Existing Dharamshala Rest Shelter Retaining & Breast Walls View Point Pre-fabricated Small Size Toilet Entrance Gate Renovation of Lodging Facility Furniture for Lodging Facility Camping Site development Renovation of Main Temple Solar Lighting Fire Fighting works Additional items Renovation of Existing Toilet Toilet Block Provision of Pathway Covering Shelter Directional Signage
07.07.16 06.07.18 Repairing work in progress at pathway, toilet and informative signage work
Pathway and Drain: - Pathway from Dharamshala to Bhaira Nath Temple completed & near entrance gate work is in progress.
42.50% No change
so far
Appropriate
measures
has been
taken for
fulfillment of
the
objectives
11
Name & No. of
Package
Name of
the
contractor
Listing of works under the package
Starting Date(land clearance)
and schedule date of
completion Type of works
Continued at
Present
Progress %
Expected
change from
Approved
scope
Fulfillment
of objective
Type of
remedial
measures
needed
Key assumption
and risk affect
attainment the
objective Starting date Date of
Completion
Informative Signage Solar Power Plant (2KW) Hill View location pointer model Electrical Work (Internal/External) From Provisional Sums Water Supply Connection Electricity Connection Rain Water Harvesting Capacity building for Temple Committee members for O&M activities
UK/IDIPT/III/DD
N/03
Rural Tourism
M/s Navya
Associates
JV with M/s
Agarwal
Brothers
Name of Village
Proposed Hardware Components
Tungnath Restoration of Temple through removal of incongruent additions and preservative coating and foundation retrofitting of main temple
Removal and reconstruction of bulged retaining walls
Shivalinga water/Rain water disposal system of the temple/premises
Up gradation of main entrance gateway
Improvement of pathway upto new gateway structure
Kaviltha Upgradation of Pathway
Construction of Guest
02.08.16 01.08.18 1. Tungnath:-
CBRI team had
visited the site
from 19. 09. 2017
to 21.09.2017
and submitted
the report on 11th
October 2017
and drawing work
is under progress
2.Kaviltha:
Guest house slab
casting and
parking is under
construction
Ground floor roof
work on going
19.50% No change
so far
12
Name & No. of
Package
Name of
the
contractor
Listing of works under the package
Starting Date(land clearance)
and schedule date of
completion Type of works
Continued at
Present
Progress %
Expected
change from
Approved
scope
Fulfillment
of objective
Type of
remedial
measures
needed
Key assumption
and risk affect
attainment the
objective Starting date Date of
Completion
House
Renovation of KalidasSmarak& Community centre
Repair of existing Parking facility
Repairing of Existing Water source
Renovation of PanchayatBhawan
Landscaping
Informative Signage
Directional Signage
Renovation of Existing gate and Railing
Furniture For Kaviltha Guest House and Kaviltha Library
Solar light and Water Heater System
Phalasi Up gradation of Pedestrian Pathway and providing retaining &breast Wall
Construction of Toilet Block
Directional and Informative Signage
Solar Lighting
Railing
3.Phalasi:- Toilet
block RCC roof
completed . Soak
pit and safety
tank completed
but not
connected
4.Bora:-
Retaining wall
13
Name & No. of
Package
Name of
the
contractor
Listing of works under the package
Starting Date(land clearance)
and schedule date of
completion Type of works
Continued at
Present
Progress %
Expected
change from
Approved
scope
Fulfillment
of objective
Type of
remedial
measures
needed
Key assumption
and risk affect
attainment the
objective Starting date Date of
Completion
Sitting Benches
Durgadhar (Bora)
Up gradation of Pedestrian Pathway and covering shelter
Construction of Toilet Block
Directional and Informative Signage
Solar Lighting
Railing and Sitting Benches
Renovation of Existing Panchayatbhawan
Harshil
Up gradation of Pedestrian Pathway and Pathway Covering Shelter and Construction of Retaining Walls
Upgradation of existing Sitting Arrangement
New Railing
Renovation of Existing Entrance Gate
Renovation of Existing Rain Shelter, Temple Premises, Parking Area and Water Tank
Informative and Directional Signage
and pathway
work started by
contractor but
villagers stopped
the work for
widening the
existing pathway
for motor able
with CC road .
5.Harshil:-
Helipad work
completed
Entrance gate in
progress
Pathway in
progress
Parking work is in progress
14
Name & No. of
Package
Name of
the
contractor
Listing of works under the package
Starting Date(land clearance)
and schedule date of
completion Type of works
Continued at
Present
Progress %
Expected
change from
Approved
scope
Fulfillment
of objective
Type of
remedial
measures
needed
Key assumption
and risk affect
attainment the
objective Starting date Date of
Completion
Beautification of Existing Helipad
Protection wall for Camping Site
Solar Lighting
Mukhwa Upgradation of existing Pedestrian Pathway and Construction of Pathway Covering Shelter, retaining and breast wall
New Sitting Arrangement
Renovation of Existing PanchayatBhawan& Temple Premises
Construction Parking facility
Entrance Gate
Toilet Block -
Directional and Informative Signage
Railing
Kanakchori (Pogatha)
Upgradation of Pedestrian Pathway and Pathway Covering Shelter
Retaining & Breast Wall
Toilet Block - Small
Directional and Informative Signage
Solar Lighting
Sitting Bench
6. Mukhwa:
Parking and
railing under
progress
Entrance gate is
under progress
7. Kanakchori
Path way and
solar light
completed
15
Name & No. of
Package
Name of
the
contractor
Listing of works under the package
Starting Date(land clearance)
and schedule date of
completion Type of works
Continued at
Present
Progress %
Expected
change from
Approved
scope
Fulfillment
of objective
Type of
remedial
measures
needed
Key assumption
and risk affect
attainment the
objective Starting date Date of
Completion
Niti Construction of Community Centre
Renovation of open air theater and compound wall
Construction of Parking facility
Upgradation of gram panchayatbhawan
Directional and Informative Signage
upgradation of village Pathway with KC drain
Seating Benches
Toilet
Upgradation of existing View Points
Provision of Dust Bins
Solar Light
Erection of Glass House (View points)
Lata No Hardware components proposed
UK/IDIPT/III/BH
T/01 Lot 1
Conservation
of Cultural
Heritage and
urban place
M/s
Simplex
Project
Limited
407,
Skipper
Corner, 88
Proposed Scope as per IEE (DPR)
1. Promenade development around Nainital lake
• Mechanical car parking
• Development of Children’s park 2. Enhancement of Nainital Lake
19.10.2015 18.10.2017 1) Library. Roofing work and framing. Wooden column.
2) DSA Flat- Roofing work,
14.20% Many
components
have been
dropped, no
new works
undertaken
Nil Cooperation of
LDA is integral for
fulfillment of
project objectives
16
Name & No. of
Package
Name of
the
contractor
Listing of works under the package
Starting Date(land clearance)
and schedule date of
completion Type of works
Continued at
Present
Progress %
Expected
change from
Approved
scope
Fulfillment
of objective
Type of
remedial
measures
needed
Key assumption
and risk affect
attainment the
objective Starting date Date of
Completion
making in
Nainital Lot-1
Nehru
Place, New
Delhi -
110019,
India
Heritage Precinct
• Restoration of Municipal Corporation, DSA Pavilion, New Club
• Development of Gandhi gram, Takula
• Façade improvement of Dam wall at Mallital,
• Façade restoration and illumination of Govt. owned heritage buildings (Bishop Shaw, Municipal Library, Catholic church, Methodist Church
• Provision of Public Amenities and facilities at appropriate location in Nainital area precinct
• Integrated signage and interpretation in lake precinct
• Reclamation of public and open spaces in the lake precinct
• Removal and demolition of obsolete, damaged street furniture and structures
• Rickshaw stand
• Integrated stone paved pedestrian access and pathways with adequate plantation
• Street furniture
• Weather shelters
FF verandah, strengthen GF,
3) 3 Methodist church-Roofing work G.F. and fasade work front side.
4) Catholic church- Roofing work, railing RCC column and pointing work.
5) DSB chapel- Pointing work
6) Municipal building-cutting for Window bracket.
7) National hotel toilet-Tile work internal
8) Cheenababa toilet-Plaster work
17
Name & No. of
Package
Name of
the
contractor
Listing of works under the package
Starting Date(land clearance)
and schedule date of
completion Type of works
Continued at
Present
Progress %
Expected
change from
Approved
scope
Fulfillment
of objective
Type of
remedial
measures
needed
Key assumption
and risk affect
attainment the
objective Starting date Date of
Completion
• Heritage type railing and integrated lake edge lighting along lake edge
• Improvement of Heritage Trekking Trail
o Nature Trail 1 - Land's End & Tiffin Top
o Nature Trail 2 - Naina Peak (Trail 1- Tiffin Top – Lands End Trail: Length 4.5 Km From Ayar Jungle Camp to Lands End + 1.17 Kms from LandsEnd to Barapatthar Trail 2 – TankiNaina Peak: Length 3 Km starting at Tanki)
Repair of damaged pathways Rough stone paving of steep, slushy stretches Provision of railings at outer sides in vulnerable stretches Wayside furniture at pause points Rain shelters at viewing points Camping sites Provision of portable toilets at appropriate points [where water pipeline already available] Signages [informative and regulatory]
Out of above proposed scope in the IEE (based on DPR) only the components listed below are being taken up:
18
Name & No. of
Package
Name of
the
contractor
Listing of works under the package
Starting Date(land clearance)
and schedule date of
completion Type of works
Continued at
Present
Progress %
Expected
change from
Approved
scope
Fulfillment
of objective
Type of
remedial
measures
needed
Key assumption
and risk affect
attainment the
objective Starting date Date of
Completion
Restoration of
• Catholic Church
• Methodist church
• Bishop Shaw
• Library Building
• Municipality Building
• DSA Flat
• Gandhi Ashram- Takula
• New Club
• DSB College Chapel
• Treatment of Dam Wall
• Repaving of Upper Mall
• Rickshaw Stand
• Lake Front Development
• Park Development
• Railing & Band Stand
• Construction of Toilets in Nainital- Cheena baba and National Hotel
• Improvement of High mass light Electricity
• Nature Heritage Trail: o Wayside furniture at pause
points o Rain shelters at viewing points o Camping sites o Provision of portable toilets at
appropriate points (water pipeline available)
19
Name & No. of
Package
Name of
the
contractor
Listing of works under the package
Starting Date(land clearance)
and schedule date of
completion Type of works
Continued at
Present
Progress %
Expected
change from
Approved
scope
Fulfillment
of objective
Type of
remedial
measures
needed
Key assumption
and risk affect
attainment the
objective Starting date Date of
Completion
o Signages (informative ®ulatory)
Mechanical car parking component shall
be taken up in separate package
UK/IDIPT/III/BHT/01 Lot 2
UK/IDIPT/III/BH
T/03
Restoration
and adaptive
reuse of
Almora Fort
(Rani Mahal)1
The subproject
was bid out in
02 packages
(i) Rani Mahal
UK/IDIPT/III/BH
T/03
(ii)
MallaMahalUK/I
DIPT/III/BHT/06
M/s
Simplex
Project
Limited
407,
Skipper
Corner, 88
Nehru
Place, New
Delhi -
110019,
India
Scope as per IEE: Restoration of the historic sites: Ram Shila Temple and the MallaMahal or Fort Nanda Devi Complex 1.Revitalization of the entire precinct as a public space for experiencing regional history and culture, through creation of facilities such as:
• Develop cobblestone-paved courtyard as a performance arena.
• Create a Museum on Kumaon culture in the main building of the MallaMahal
• Create a Himalayan Art Gallery and nature interpretation centre in the Rani Mahal,
• Restoration of the historic site of Ram Shila Temple
• Creation of craft demonstration areas.
• Removal or concealment some buildings through strategic landscaping and foliage coverage of structures
• Create facilities in Almora town to enable it to emerge as a complete destination
19-10-2015 18-10-2017 1. Brick work in
non basement area in progress (80% work completed).
2. Staircase casting work in progress.
3. Brick work in
non basement
area 100% work
completed.
37.15% No Change
20
Name & No. of
Package
Name of
the
contractor
Listing of works under the package
Starting Date(land clearance)
and schedule date of
completion Type of works
Continued at
Present
Progress %
Expected
change from
Approved
scope
Fulfillment
of objective
Type of
remedial
measures
needed
Key assumption
and risk affect
attainment the
objective Starting date Date of
Completion
• Improve all three access routes that lead up to the fort and temple
• Improve accessibility, especially for the differently-abled through the setting up of elevators leading from bazaar to the site.
• Improve basic tourist and pilgrim facilities and amenities
• Improve vehicular parking facilities for about 100 vehicles in the town.
• Improve basic environmental services like solid waste and wastewater management.
• Enforcing strict standards for cleanliness and upkeep. Improving tourist/visitor wayside amenities along approximately 10 km of vehicular access. Improving access to places of tourist/pilgrim attractions by way of 15 km of connectivity improvement inclusive of roadside infrastructure and improved signage.
• Improving about 4 km of pedestrian environment connecting the heritage site with different parts of the town.
• Training and capacity building 2. Construction of District Collectorate office at Porth Free Estate near VikasBhavan. Construction of G + 4 building with office, parking within Govt.
21
Name & No. of
Package
Name of
the
contractor
Listing of works under the package
Starting Date(land clearance)
and schedule date of
completion Type of works
Continued at
Present
Progress %
Expected
change from
Approved
scope
Fulfillment
of objective
Type of
remedial
measures
needed
Key assumption
and risk affect
attainment the
objective Starting date Date of
Completion
land of 2500 sq m
For Almora District Collectorate office, Water supply is planned from municipal water supply and water line will be extended to proposed building.
For waste water – discharge 4 nos. of soak pit and 4 nos. of septic tank will be utilized. In total 64 nos. of toilet, 32 nos. urinal will be constructed
Solid waste will be stored in bins of adequate capacity from where collection will be done by Almora Nagar Palika
Out of above proposed scope in the IEE (based on DPR) only the components listed below are being taken up:
(i) Rani Mahal package has been awarded and scope is
• Restoration of Rani Mahal
• Restoration of Courtyard+ RamshilaTemple
• Restoration of Craft Centre + Toilet
• Restoration of SDM office
• Restoration of Fort Walls
22
Name & No. of
Package
Name of
the
contractor
Listing of works under the package
Starting Date(land clearance)
and schedule date of
completion Type of works
Continued at
Present
Progress %
Expected
change from
Approved
scope
Fulfillment
of objective
Type of
remedial
measures
needed
Key assumption
and risk affect
attainment the
objective Starting date Date of
Completion
• Signage Plan
• Civil work of Collectorate building in Almora
• Site Development and Landscaping
• Sanitary&
• Electrical Works
Following works shall be taken up in (ii) Malla Mahal package which is not yet awarded
• Museum on Kumaon culture in MallaMahal and
• Removal or concealment some buildings through strategic landscaping and foliage coverage of structures
UK/IDIPT/III/BH
T/05
Restoration
and adaptive
reuse of
Champawat
Fort (Banasur)
M/s
Simplex
Project
Limited
407,
Skipper
Corner, 88
Nehru
Place, New
Delhi -
1. The scope of this
sub-project includes:
a) Restoration of the historic
sites: Rajbhunga Fort and
Banasur Forts, or collectively
Champawat Forts, Restoration
of GoluDevta temple (3 km
from the Champawat fort) and
19.10.15 18.10.17 Tehsil Building-
Earth work &
PCC work of
foundation 100
% work
completed,
RCC work upto
plinth level -
100 %, work
completed, RR
26.50% Components
of GoluDevta
and Guru
Gorakhnath
temple have
been
dropped
23
Name & No. of
Package
Name of
the
contractor
Listing of works under the package
Starting Date(land clearance)
and schedule date of
completion Type of works
Continued at
Present
Progress %
Expected
change from
Approved
scope
Fulfillment
of objective
Type of
remedial
measures
needed
Key assumption
and risk affect
attainment the
objective Starting date Date of
Completion
110019,
India
Goraknath temple (40 km from
Champawat)
b) Revitalization of the entire
precinct as a public space for
experiencing regional history
and culture, through creation
of facilities.
(i) Rajbhunga Fort:
• Removal of existing and
undesirable structures
• Remodeling and
reconstruction of existing
structures:Old Fort &Tehsil
Office and SDM Office, Durga
Devi Temple, Courtyard and
Ramparts.
• Providing Tourist Facilities and
Amenities at fort like Ticket
Counter, Tourist Interpretation
Centre, Cafe & Shop,
Souvenir Shop, Library, Toilet
Block, Creation of link walk
way & Improving the existing
road and Lanes, 12 Bed Hotel,
stone 50%
work
completed,
Steel Binding of
columns 1st
floor -100 %
work
completed. 2.
Type 2
Building- Earth
work & PCC
work of
foundation 100
% work
completed ,
RCC work 100
% work
completed,
Brick work 1st
floor- 100 %
work completed
. 3. Type 4
Building- Earth
work & PCC
work of
foundation 100
% work
completed ,
RCC of footing
24
Name & No. of
Package
Name of
the
contractor
Listing of works under the package
Starting Date(land clearance)
and schedule date of
completion Type of works
Continued at
Present
Progress %
Expected
change from
Approved
scope
Fulfillment
of objective
Type of
remedial
measures
needed
Key assumption
and risk affect
attainment the
objective Starting date Date of
Completion
with 2 suites, Entrance way &
Reception, Water & Waste
Management, Solar lights.
(ii) GoluDevta Temple:
• Repair of Approach to
GoluDevta Temple
• Improvement of Worship
Space at GoluDevtaTemple
(iii) Guru Goraknath Temple:
• Shed and Railing at
Gorakhnath Temple
• Restoration of Wall at
Gorakhnath Temple
• Gazebos en route Gorakhnath
(iv) Other scope:
In training and capacity building
Present Scope of works includes
Banasur Fort:
• Removal of existing and
undesired structures and
and slab 100 %
completed, RR
stone - 50 %
work completed
25
Name & No. of
Package
Name of
the
contractor
Listing of works under the package
Starting Date(land clearance)
and schedule date of
completion Type of works
Continued at
Present
Progress %
Expected
change from
Approved
scope
Fulfillment
of objective
Type of
remedial
measures
needed
Key assumption
and risk affect
attainment the
objective Starting date Date of
Completion
relocation
• Remodelling and
reconstruction of existing
structures: 03 Gazebos en
route, shed on hilltop for café
Preparation of platform etc. on
site for Adventure Sport
Construction of new Tehsil building
• G+2 Tehsil building in 1400 m2 out of total land of 5400 m2. (Land to be transfer to Tourism dept. from KNVN)
• 1 number Type II quarter and 1 number Type IV quarter
• Garage facility and car parking
• Litigation room
• Boundary wall for whole area
• Approach road to site
Works in Rajbhunga will commence after construction of Tehsil building
Restoration
and Adaptive
Reuse of
M/S COX
Infratech
Private
• New multi-level car parking near Dev Singh Ground
01-07-2015 30-06-2016 Multilevel
Parking
1-Excavation work
36.83% 01 additional
block was
added to the
Appropriate
measures
have been
Weather
disturbances due
to heavy rains or
26
Name & No. of
Package
Name of
the
contractor
Listing of works under the package
Starting Date(land clearance)
and schedule date of
completion Type of works
Continued at
Present
Progress %
Expected
change from
Approved
scope
Fulfillment
of objective
Type of
remedial
measures
needed
Key assumption
and risk affect
attainment the
objective Starting date Date of
Completion
Pithoragarh
Fort Phase II
UK/IDIPT/III/BH
T/07
Limited in
JV with
Conaech
Associate
s
• Tourist Rest House by converting tehsil staff quarter in Fort premises
• New tehsil office building
• Accommodation for rehabilitation of Tehsil Staff Quarter Type IV – 1 no and Type II-6 nos.
• Signage and Waste bins
in progress. 2-Expansion joint footing excavation work in progress. 3-Welding of beams and boxes under process. 4-Additional Block retaining wall in progress. 5-Railing and barrier protection work is under process. 6-Third floor
seating and column extension works is under process. 7-Fourth floor terrace work is under process. 8-Third floor work in progress.
TRH Work
near
Pithoragarh
Fort
1-Retaining wall
work in progress. 2-Family suite
parking. taken for
fulfillment of
the
objectives.
snowfall may
delay the project
27
Name & No. of
Package
Name of
the
contractor
Listing of works under the package
Starting Date(land clearance)
and schedule date of
completion Type of works
Continued at
Present
Progress %
Expected
change from
Approved
scope
Fulfillment
of objective
Type of
remedial
measures
needed
Key assumption
and risk affect
attainment the
objective Starting date Date of
Completion
footing in progress.3-Excavation work in progress.
Name & No. of
Package
Name of
the
contracto
r
Scope of Works under Package
Starting Date(land
clearance) and schedule
date of completion Type of works
Continued at
Present
Progress
% age
Expected
change
from
Approve
d scope
Fulfillment
of
objective
Type of
remedial
measures
needed
Key assumption and
risk affect
attainment the
objective Starting
date
Date of
Completion
UK/IDIPT-III/KOT/01
Creation of
Pedestrian Route
for Pilgrims and
Tourists in Haridwar
M/s SS
Infratech Jv
, Tikola
Nagar,
Roorkee
a) Development of a pedestrian route or pathway for movement of pilgrims and tourist from near Mayapur Regulator to Bahadarabad Bridge. Total length of pedestrian pathway to be developed is 11.33 km. For a stretch of 5.9 km length (from near Mayapur Regulator to Jathwara bridge) the existing Kanwar Patri ( Route followed by Kanwarias) will be developed to a pedestrian pathway. For a stretch of 5.43 km (from Jathwara Bridge to Bahadarabad Steel Bridge) a
22/07/2015 21/07/2017 • Footpath work
is in progress
at Solani Park,
brick work is
complete. At
Solani Park
Paver work is
in progress.
• At Integrated
complex,
plumbing work
and brick work
is in progress.
50% Foot Over
bridge over
NH-58 at
Manglaur
Crossing
dropped
due to
work done
by NHAI
on the
same
location.
Appropriate
measures
have been
taken for
fulfillment of
the
objectives
In case of any
restrictions by the UP
Irrigation Department
and permissions of Foot
Over Bridge
Construction on NH-58
at Manglaur
28
pedestrian pathway will be developed on the side of existing motorable road (canal bank road). In this stretch of 5.43 km Kanwar Patri, and proposed pedestrian pathway and existing motor able canal bank road will exist.
b) Landscaping, sitting arrangements, murals, etc. on the proposed pedestrian pathway.
c) Providing lighting or illumination arrangement on the proposed pedestrian pathway of 11.33 km.
d) Providing safety hand railing on the pedestrian pathway on canal side.
e) Providing solid waste bins on the side of proposed pedestrian pathway.
f) Providing a toilet complex and drinking water facility on side of the proposed pedestrian pathway near Shankaracharya Chowk.
g) At one location near the proposed pedestrian pathway (before Lohe Ka Pul on railway track near Jawalapur) a multi facility complex will be developed which will include a toilet complex, drinking water fountain, bathing and sanitation facilities, rest shelter, food distribution centre, police control room, solid waste bins, compound wall with entrance gate, landscaping, etc.
h) Construction of a foot over bridge over Railway track near
Tile work in
Toilet complex
is in progress.
• Landscaping
work is in
progress along
the pathway
• Plantation
work is in
progress as
part of
landscaping
• Seating
arrangement
along the
pathway is in
progress
• Second floor
work is in
progress at
integrated
complex
• Work for four
number rest
shed is in
progress.
29
Jawalapur. i) Installation of tourist Signages on Kanwar Patri from Har Ki Pauri to Mangalour Cross. Total length of the stretch of Kanwar Patri to be taken up for the signage installation works is 42 km.
UK/IDIPT-III/KOT/02
Development of
Tourism
Infrastructure in
Sem Mukhem (
Tehri)
M/s
Mangalam
and
Constructio
n Company
in JV with
Sunil Garg
Company
Meerut
The main sub-project components include the following:
i. Dharamshala/ rest shelter at fair ground.
ii. Toilet complex at fair ground including septic tank with soak pit.
iii. Water supply Arrangement at Fair Ground
iv. Landscaping works at fair ground. Locally available materials shall be used for construction. The landscaping elements shall incorporate local foliages and flora of fairground so that the built environment is in sync with the background
v. Development of pathway from main road to fair ground.
vi. Solar lighting system along with normal outdoor lights is proposed at fair ground. Electricity source for illumination works is from Uttarakhand Power Corporation Limited and the same is reliable
vii. Development of existing small lake near fair ground. The existing small lake covers about 1500 sqm. area, while water spread area is 500 sqm.
viii. Solid waste bins and compost pits
23/09/2015 21/09/2017 For rest shelter (
including toilet
complex) all brick
work for
superstructure
completed. RCC
slab casting work
in progress.
Plumbing and
flooring work is in
progress.
• Pathway at fair
ground 95 %
work
completed
• Pathway for
Mukhem
Village is
completed
• RCC Slab
casting for
Pujari cottage
completed
• Renovation of
Mukhem village
temple is in
70% Canopy for
a length of
147 m,
component
dropped
Appropriate
measures
have been
taken for
fulfillment of
the
objectives
In case of adverse
weather conditions and
any disagreement with
Mela Committee and
village Panchayat
30
at Fair Ground. Solid wastes from Fair ground and Mandir complex will be collected in collection bins and ultimately dumped in to compost pit to be developed in the sub project.
ix. Murals depicting the story of Lord Krishna at 4 locations.
x. Providing solid waste bins and construction of compost pit in Mandir Complex. Solid wastes from Mandir complex will be collected in collection bins and ultimately dumped in to compost pit to be developed in the sub project.
xi. Solar light at the temple complex. xii. Canopy for a length of 147 m on
pathway in between fair ground and Nagraj Temple.
xiii. Hand rails and finishing works on pathway between fair ground and temple complex.
xiv. Facilities planned at Mukhem village are: a) Renovation of existing Temple
in Mukhem village. b) Renovation of existing entry
gate of Mukhem village. c) Development of internal roads
in Mukhem village. d) Expansion of existing pipe
water supply network. e) Installation of solar lighting
system, f) Solid waste management with
compost pits in Mukhem village.
progress-90 %
completed..
• Silt removal
from Jheel
completed.
Pitching work is
in progress.
• Septic tank 30
user
completed.
slab casting
31
• Tourism Signages on the 23Km road from Kodar to Fair Ground.
UKIDIPT/III/ GEN/03
Development of
Traditional Medicine
and Yoga Training
centers
M/s Bansal
Constructio
n,
Muzaffarna
gar
Development of Traditional Medicine Panchkarma and Yoga Centers at 3 TRHs/Resorts operated by GMVN in Garhwal Region (Dhanaulti, Rishikesh, Lansdowne) and at 5 TRHs/ Resorts operated by KMVN (Chiliyanaula, Kausani, Choukori, Naukuchiyatal and Sukhatal). New construction of above facilities is to be carried out only in Naukuchiyatal and Lansdowne, in the other locations facilities are planned within existing resorts by after interior refurbishment and slight alterations. The project progress includes civil component and procurements of equipments in a ratio of 60:40. Dhanaulti Sukhatal Chiliyanaula Kausani Chaukori Ganga Resort Lansdowne Naukuchiyatal
08/03/2017 07/03/2019 Location wise
Progress
update
TRH
Dhanaulti:
work
completed
TRH
Sukhatal:
Civil Works
started
TRH Kausani,
work in
progress
TRH
Chiliyanaula
TRH Ganga
Resort 5
100%
25%
15%
10%
5%
No change Appropriate
measures
have been
taken for
fulfillment of
the
objectives
Only in case of extreme
weather events,
otherwise magnitude of
works is very low and no
risk envisaged
Any other information useful for assessing environmental performance of the project:
9. No additional information during this period
32
2. Compliance Status
10. Status of Compliance with EARF/ADB Procedures is shown in Table 3.
Table 3: Status of Compliance with EARF/ADB Procedures S.No Name & No. of
Package
Environment
Category
Status of preparation of
IEE
Status of Approval
by ADB Date of Approval
Further Action needed For Compliance &
Responsibility
1 UK/IDIPT-III/ DDN/01 B Completed and approved Approved 03.08.2015 Regular monitoring and reporting of EMP
2 UK/IDIPT-III/ DDN/02 B Completed and approved Approved 01.09.2015 Regular monitoring and reporting of EMP
3 UK/IDIPT-III/DDN/03 B Completed and approved Approved 25.05.2016 Regular monitoring and reporting of EMP
4* UK/IDIPT/III/BHT/01Lot1 UK/IDIPT/III/BHT/01Lot2
B Completed and approved Approved 08.09.2015 Regular monitoring and reporting of EMP
5 UK/IDIPT/III/BHT/02 B Design stage
6* UK/IDIPT/III/BHT/03 UK/IDIPT/III/BHT/06
B Completed and approved Approved 09.07.2015 Regular monitoring and reporting of EMP
7* UK/IDIPT/III/BHT/04 UK/IDIPT/III/BHT/05
B Completed and approved Approved 06.08.2015 Regular monitoring and reporting of EMP
8 UK/IDIPT/III/BHT/07 B Completed and approved Approved 25.04.2016 Regular monitoring and reporting of EMP
9 UK/IDIPT-III/KOT/ 01 B Completed and approved Approved 11.05.2015 Regular monitoring and reporting of EMP
10 UK/IDIPT-III/KOT/ 02 B Completed and approved Approved 25.05.2015 Regular monitoring and reporting of EMP
11 UK/IDIPT-III/KOT/ 03 B Completed and approved Approved 28.03.17 Regular monitoring and reporting of EMP
12 UK/IDIPT/III/GEN/01 Goods Package
13 UK/IDIPT/III/GEN/02 B Completed and approved Approved 30.07.2015 Regular monitoring and reporting of EMP
14 UK/IDIPT/III/GEN/03 B Completed and approved Approved 03.03.2017 Regular monitoring and reporting of EMP
*S.no 4, 6 and 7, Project bifurcated into 02 packages
33
3. Compliance status with National/ State/ Local statutory environmental requirements
11. Status of Compliance with National/ State/ Local statutory environmental requirements is shown in Table 4.
Table 4: Status of Environment, Forest and other Clearance
Work (Package No.) Applicable Legislation/Type of
clearance Clearance Given by
and date Subject/Issue Remarks/Action needed
UK/IDIPT-III/ DDN/01
Development of Tourism Infrastructure in Kartikeya Swami Circuit (Lot-1) (Tungeshwar & Durgadhar Temple)
No environmental and forest clearance required. No requirement of NOC from ASI
Not applicable
UK/IDIPT-III/ DDN/02
Development of Tourism Infrastructure in Kartikeya Swami Circuit (Kartikeya Swami Temple)
Forest clearance required. No requirement of Environmental Clearance or NOC from ASI
Clearance received from MoEF& CC dt. 23.09.16
Kartikeya Swami Temple and pathway are located in Reserve Forest area, for which forest clearance was needed.
Works to be done as per Clearance conditions.
UK/IDIPT-III/DDN/03 Conservation and Development of Rural Tourism in district Rudraprayag, Chamoli and Uttarkashi
No Environmental and forest clearance required. NOC required from Forest Dept. for Tungnath location. No requirement of NOC from ASI.
NOC obtained from Forest Department, GoUkdt. 08/09/14
Out of 9 rural sites, Tungnath lies in buffer zone of Kedarnath Wildlife Sanctuary NOC received from Forest Department
Works to be done as per conditions of NOC given by the Forest department.
UK/IDIPT-III/KOT/01 Creation of Pedestrian Route for Pilgrims and Tourists in Haridwar
No environmental and forest clearance required. No requirement of NOC from ASI.
Not applicable
UK/IDIPT-III/KOT/02 Development of Tourism Infrastructure in Sem Mukhem
No Environmental and forest clearance required. (Only a minor canopy component was proposed in reserve forest since trek over which canopy has to be installed, falls in reserve forest). The same has been dropped.
Not required The project is for creation of Tourism Infrastructure in Sem Mukhem. No forest land acquisition involved, so no forest clearance required. The project site is not in ASI regulated Zone.
The canopy component has been dropped
UK/IDIPT-III/BHT/01 Conservation of Cultural Heritage and Urban
NOC from PWD, forest clearance required for pre fab toilets and view
NOC obtained from The project is for conservation of cultural heritage involving mostly repair, restoration
Forest Clearance of Tiffin Top is in process and related works will be
34
Work (Package No.) Applicable Legislation/Type of
clearance Clearance Given by
and date Subject/Issue Remarks/Action needed
Place making in Nainital Lot 1 points on nature trail (Tiffin top and Tanki China). No requirement of NOC from ASI.
PWD
Forest Clearance for nature trail for Tanki Cheena obtained
Forest Clearance for Tiffin Top is in process
works. There are 02 nature trails falling in reserve forest where portable toilet and viewpoints are proposed. So forest clearance required. The project site is not in ASI regulated Zone.
taken up after Clearance is obtained.
UK/IDIPT-III/BHT/03 Conservation and adaptive re-use of Almora Fort (Rani Mahal)
No Environmental and forest clearance required. No requirement of NOC from ASI.
Not applicable
UK/IDIPT-III/BHT/05 Conservation and adaptive re-use of Champawat Fort (Banasur)
No Environmental and forest clearance required.
Requirement of NOC from State ASI for Banasur Fort.
NOC obtained vide letter dt. 5th Dec, 2014.
Banasur Fort is a State Protected Monument and the custodian is State Culture Dept. NOC received from State Culture Dept.
Works as per NOC. Works should not interfere with the original character of the Fort structure.
UK/IDIPT/III/BHT/07
Restoration, Adaptive Reuse and Revitalization of Pithoragarh Fort
No Environmental and forest clearance required.
NOCs from line agencies obtained
NOC from District Administration for shifting Tehsil office NOC from Executive Engineer Nagarpalika Parishad Pithoragarh
NOC from District Sport officer
The project is for conservation of cultural heritage involving mostly repair, restoration works. Tehsil was housed in the Fort campus, which is to be relocated to carry on repair and restoration works in the Fort
Works to be done as per conditions of NOC given by line agencies and in line with their suggestions
UKIDIPT/III/GEN/03
Development of Traditional medicine and Yoga Training Centers
No Environmental and forest clearance required
Not applicable The project involves construction of yoga and panchkarma centres in existing Tourist Rest Houses of Tourism Dept. in 8 locations, wherein modification and refurbishment works are proposed in 06 TRHs while in 02 namely Lansdowne and Naukuchiyatal works will be done on vacant land within premises of the TRHs.
No action needed
35
4. Compliance status with the environmental covenants as stipulated in the Loan Agreement
12. The status of compliance with environmental loan covenants is presented in Table 5.
Table 5: Status of Compliance with Environmental Loan Covenants S. No Covenants Compliance
1. The Borrower and the States shall ensure that the preparation, design, construction, implementation, operation and
decommissioning of each Subproject and all Project facilities comply with (a) all applicable laws and regulations of the
Borrower and the States relating to environment, health, and safety; (b) the Environment Safeguards; (c) the EAFR; and (d) all
measures and requirements set forth in the respective IEE and EMP, and any corrective or preventative actions set forth in a
Safeguard Monitoring Report.
Compliance of (a) all applicable laws and regulations of the Borrower
and the States relating to environment, health, and safety (b)
Environment Safeguards; (c) the EARF; and (d) EMP is being
ensured during sub projects implementation.
Safeguards – Related Provisions in Bidding Documents and Works Contracts
The States shall ensure that all bidding documents and contracts for Works contain provisions that require contractors to:
(a) Comply with the measures and requirement relevant to the contractor set forth in the IEE, the EMPs, any RO and any
IPP (to the extent they concern impacts on affected people during construction), and any corrective or preventative
actions set out in a Safeguard Monitoring Report;
(b) make available a budget for all such environment and social measures;
© provide the relevant State with a written notice of any unanticipated environmental, resettlement or indigenous peoples
risks or impacts that arise during construction, implementation or operation of the Project that were not considered in the
IEE, the EMP, the or the IPP (if any): and
(d) Fully reinstate pathways, other local infrastructure, and agricultural land to at least their pre-project condition upon the
completion of construction.
Full EMP made part of the contract agreements of respective subprojects, thus its provisions being complied with.
Orientation sessions are being carried out in each site for better understanding of Safeguards Compliance by the Contractor Environmental monitoring and mitigation costs allocated/ incorporated in contract agreements. No such environmental impact has been identified so for that was not considered in the IEE and in the EMP. (If any such impact arises in future, will be suitably addressed) All the areas that if disturbed by construction activities will be restored to pre-project condition by the contractors.
Safeguards Monitoring and Reporting
11. The States shall do the following:
(a) Submit semi-annual Safeguards Monitoring Reports to ADB and disclose relevant information from such reports to
The fifth semiannual report for Loan No. 3223 IND is submitted herewith. Subsequent reports will be submitted on time.
36
S. No Covenants Compliance
affected persons promptly upon submission;
(b) if any unanticipated environment and/or social risks and impacts arise during construction, implementation or operation
of the Project that were not considered in the IEE, the EMP, any RP or any IPP, promptly inform ADB of the occurrence
of such risks or impacts, with detailed description of the event and proposed corrective action plan; and Report any
breach of compliance with the measures and requirements set forth in the EMP, any IPP promptly after becoming
aware of the breach.
In case of any unanticipated environmental risks and impacts arise, that shall be immediately informed to ADB with detailed description of the event and proposed corrective action plan. Breach will be reported to ADB immediately after becoming aware of it.
5. Compliance Status with Environment Management and Monitoring Plans as stipulated in the environmental documentation as agreed with ADB.
13. The compliance Status with Environment Management and Monitoring Plan is shown in Table 6.
Table 6: EMP Implementation Status
S.
No Sub Project Name
EMP Part of Contract Documents
(Yes/No)
EMP being Implemented (Yes/ No)
Status of EMP Implementation (Excellent/ Satisfactory/ Partially Satisfactory/ Below Satisfaction)
Actions Proposed/ Additional Corrective Measures Required
1 UK/IDIPT-III/ DDN/01 Yes Yes Partially Satisfactory Contractor directed to conduct regular environment monitoring
2 UK/IDIPT-III/ DDN/02 Yes Yes Partially Satisfactory Contractor directed to conduct regular environment monitoring
3 UK/IDIPT-III/ DDN/03 Yes Yes Partially Satisfactory Stockpiling to be properly done in Kabiltha and Harsil., Housekeeping to be improved at Phalasi, Usage of PPEs is to be ensured at Harsil. Submission of regular environmental monitoring report as per EMMP
4 UK/IDIPT/III/BHT/01 Conservation of Cultural Heritage and Urban Place making in Nainital Lot 1
Yes Yes Partially Satisfactory Contractor has been instructed for proper stockpiling of raw materials and waste in designated area with proper demarcation at the Municipality building and DSA flats site
5 UK/IDIPT/III/BHT/03 Conservation and adaptive re-use of Almora Fort (Rani Mahal)
Yes Yes Partially Satisfactory Instruction has been given to the contractor for proper stockpiling in demarcated area with barricades and to ensure the usage of PPEs.
6 UK/IDIPT/III/BHT/05 Yes Yes Satisfactory No suggestions.
37
S.
No Sub Project Name
EMP Part of Contract Documents
(Yes/No)
EMP being Implemented (Yes/ No)
Status of EMP Implementation (Excellent/ Satisfactory/ Partially Satisfactory/ Below Satisfaction)
Actions Proposed/ Additional Corrective Measures Required
Conservation and adaptive re-use of Champawat Fort (Banasur)
7 UK/IDIPT/III/BHT/07 Restoration, Adaptive Reuse and Revitalization of Pithoragarh Fort Phase II
Yes Yes Satisfactory No suggestions
8 UK/IDIPT-III/KOT/01 Creation of Pedestrian Route for Pilgrims and Tourists in Haridwar
Yes Yes Partially Satisfactory 1- The contractor has been instructed to maintain sanitation facilities at construction camp at integrated facilities complex
2- The contractor has been instructed to strictly confirm the usage of personal protective equipment.
9 UK/IDIPT-III/KOT/02 Development of Tourism Infrastructure in Sem Mukhem
Yes Yes Partially Satisfactory 1- The contractor has been instructed to maintain sanitation facilities at construction camp at Mela Ground
2 The contractor has been instructed to segregate all construction waste at one location at the Mela ground construction site and increase the frequency of water sprinkling at site
10 UKIDIPT/III/GEN/03 Development of traditional medicine and Yoga Training centres
Yes Yes Satisfactory No suggestions
6. Status of Implementation of Environment Management Plan
38
14. EMP Monitoring status of subprojects is presented in Table 7.
Table 7 (i): EMP Monitoring Status Chart- Development of Tourism Infrastructure In Kartikeya Swami Circuit (Lot-1) (Tungeshwar &Durgadhar Temple) IEE/EMP
Component Environmental issues Responsibility Compliance Status Corrective actions
UK/IDIPT-III/ DDN/01
Location Lack of sufficient planning to assure long term sustainability of the facilities and ensure protection specially from earthquake and other natural disasters
PMU & DSC Complied None
Pre-construction activities by the Contractor
1.Construction Camps 2. Defining of construction/work areas on ground for activities within 200m of the boundaries of the protected areas 3. Circulation plan during construction 4. Site clearance activities 5. Drinking water availability 6. Identification of disposal sites 7. Waste management on site
Contractor & DSC
Complied The waste material generated due to clearance and demolition activities is being used for filling and leveling at site only. Towards the end of construction phase, the site for disposal of waste material will be identified, keeping in view the quantity to be disposed off. The waste generated during the construction is segregated and stored at the site for possible reuse later. The waste disposal plan will be prepared in the end phase of construction period by the contractor and reviewed by the DSC and will be approved in consultation with PIU
Construction 1. Improper stockpiling 2.Quarry/ Borrow pit operations 3.Stripping, stocking & preservation of top soil 4.Soil erosion 5. Water pollution due to fuel/lubricants 6. Siltation of water bodies 7. Generation of dust
Partially Complied; environment monitoring reports are not submitted by
the Contractor timely
1. Stockpiles are separate and covered
2. The contractor is obtaining sand and sub grade from the licensed
quarries. No borrow pit operations have been carried out so far.
3. The excavated earth for foundation work of Dharamshala in
Tungeshwar is being used for filling.
4. No cutting or steep slope issues involved in the project.
5. No storage at site.
6. No water body in the impact area of the subproject.
7. Generation of dust is on account of material handling at site.
Necessary dust suppression measures such as water sprinkling are
followed.
Regular testing of air and noise as per EMMP
39
IEE/EMP
Component Environmental issues Responsibility Compliance Status Corrective actions
8.Emission from construction vehicles 9. Noise from construction equipment 10. Material handling at site 11. Disposal of construction waste/debris 12. Sanitation facilities at project site 13. Safety measures 14. Risks force majeure 15. Malaria risk
16.Chance archaeological finds 17.Religious structures 18. Construction Staff causing disruption to migratory birds
8. The construction vehicles usage is not much in the project. It is only for
the transportation of construction materials and there is a small concrete
mixer at site. The trucks carrying construction material have pollution
under control certificates.
9. In the current project the only noisy equipment used is concrete mixer
and it is operated intermittently. No excess noise generation is on
account of construction activities.
10. The material handling at site is satisfactory as most of the workers
were seen using personal protective equipment.
11. Construction waste generated so far has been stored for utilization
and disposal further at designated location.
12. Toilet block is functional
13. Use of PPE’s is satisfactory.
14. Risk Force Majeure: situation not occurred so far. Necessary action
will be taken as per contract provisions if such situation arises
15. Instructions have been given to contractor regarding malaria risk and
prevention measures.
16. Chance Archaeological finds have not been found so far during the
construction works. The contractor has been instructed to inform to PIU
and DSC, if any chance find is found.
17. The project is not impacting any religious structures rather its meant
for maintenance and restoration of religious structures.
18. There is neither any route of migratory birds nor any location where
migratory birds are visiting.
Operation 1. Environmental conditions 2. Uncontrolled tourism 3. Management of the toilet blocks 4. Adequate drainage 5. Unhygienic condition due to poor
maintenance of sanitation facilities and irregular solid waste collection
6. Increased waste loads onto the
PMU, UTDB The project not yet reached Operation phase Not applicable
40
IEE/EMP
Component Environmental issues Responsibility Compliance Status Corrective actions
existing waste disposal facilities
Table 7 (ii): EMP Monitoring Status Chart- Development of Tourism Infrastructure In Kartikeya Swami Circuit (Lot-2) (Kartikeya Swami Temple)
IEE/EMP
Component Environmental issues Responsibility Compliance Status Corrective actions
UK/IDIPT-III/ DDN/02
Location Lack of sufficient planning to assure long term sustainability of the facilities and ensure protection specially from earthquake and other natural disasters
PMU & DSC Complied None
Pre-construction activities by the Contractor
1.Construction Camps 2. Defining of construction/work areas on ground for activities within 200m of the boundaries of the protected areas 3. Circulation plan during construction 4. Site clearance activities 5. Drinking water availability 6. Identification of disposal sites 7. Waste management on site
Contractor & DSC Complied
None
Construction 1. Improper stockpiling 2.Quarry/ Borrow pit operations
3.Stripping, stocking & preservation of top soil 4.Soil erosion
Partly complied; Monitoring of Environmental parameters is not done regularly 1. The main construction materials being used are bricks, cement,
stone, sand and steel rods. These are being stocked properly.
2. The contractor is obtaining sand and sub grade from the
licensed quarries. No borrow pit operations have been carried out
so far.
Regular testing of air and noise as per EMMP
41
IEE/EMP
Component Environmental issues Responsibility Compliance Status Corrective actions
5. Water pollution due to fuel/lubricants 6. Siltation of water bodies 7. Generation of dust 8.Emission from construction vehicles 9. Noise from construction equipment 10. Material handling at site 11. Disposal of construction waste/debris 12. Sanitation facilities at project site 13. Safety measures 14. Risks force majeure 15. Malaria risk
16.Chance archaeological finds
17.Religious structures 18. Construction Staff causing disruption to
migratory birds
3. The excavated earth from pathway work, retaining wall and rest sheds is being simultaneously reused for filling and leveling. 4. The soil erosion issue is not there as there is no cutting and moreover the area is rocky. 5. The fuel and lubricants are not stored at site as project is small in nature. These are purchased from market as per need. 6. Natural water source but not within the impact zone. 7. Generation of dust is very less. 8. The construction vehicles usage is not much in the project. It is only for the transportation of construction materials and there is a small concrete mixer at site. The trucks carrying construction material have pollution under control certificates. 9. Maximum activities are done manually. 10. The material handling at site is fine as most of the workers were seen using personal protective equipment. 11. Construction waste generated so far has been stored for utilization and disposal further at designated location. 12. The sanitation facilities at construction camp are proper. 13. First aid kits have been equipped with suitable medicines and other materials like cotton, bandage etc. Use of PPE’s is satisfactory. Caution and caution sign board is put up at site. 14. Risk Force Majeure: situation not occurred so far. Necessary action will be taken as per contract provisions if such situation arises 15. Instructions have been given to contractor regarding malaria risk and prevention measures. 16. Chance Archaeological finds have not been found so far during the construction works. The contractor has been instructed to inform to PIU and DSC, if any chance find is found. 17. The project is not impacting any religious structures rather its meant for maintenance and restoration of religious structures. 18. There is neither any route of migratory birds nor any location where migratory birds are visiting.
Operation 1-Environmental conditions PMU, UTDB The project not yet reached Operation phase Not applicable
42
IEE/EMP
Component Environmental issues Responsibility Compliance Status Corrective actions
2.Uncontrolled tourism 3. Management of the toilet blocks 4. Adequate drainage 5. Unhygienic condition due to poor maintenance of sanitation facilities and irregular solid waste collection 6. Increased waste loads onto the existing waste disposal facilities
Table 7 (iii): EMP Monitoring Status Chart- Rural Tourism in District Tehri and Uttarkashi
IEE/EMP
Component Environmental issues Responsibility Compliance Status Corrective actions
UK/IDIPT-III/ DDN/03
Location Lack of sufficient planning to assure long term sustainability of the facilities and ensure protection specially from earthquake and other natural disasters
PMU & DSC Complied None
Pre-construction activities by the Contractor
1.Construction Camps 2. Defining of construction/work areas on ground for activities within 200m of the boundaries of the protected areas 3. Circulation plan during construction 4. Site clearance activities 5. Drinking water availability 6. Identification of disposal sites 7. Waste management on site
Contractor & DSC Complied Small construction camp only in Kabiltha site. No camp in remaining sites. Local labour are hired. Site clearance activities have been done. Potable drinking water is available in each site. The waste disposal plan will be prepared in the end phase of construction period by the contractor and reviewed by the DSC and will be approved in consultation with PIU
None
Construction 1. Improper stockpiling
Partially complied 1. Stockpiling is average. In Kabiltha and Harsil, material was not kept
• Stockpiling to be properly done in Kabiltha and Harsil.
43
IEE/EMP
Component Environmental issues Responsibility Compliance Status Corrective actions
2.Quarry/ Borrow pit operations 3.Stripping, stocking & preservation of top soil 4.Soil erosion 5. Water pollution due to fuel/lubricants 6. Siltation of water bodies 7. Generation of dust 8.Emission from construction vehicles 9. Noise from construction equipment 10. Material handling at site 11. Disposal of construction waste/debris 12. Sanitation facilities at project site 13. Safety measures 14. Risks force majeure 15. Malaria risk 16.Chance archaeological finds 17.Religious structures 18. Construction Staff causing disruption to migratory birds
in designated location and was uncovered. General housekeeping needs to be improved at Phalasi site. 2. The contractor is obtaining sand and sub grade from the licensed quarries in all the sites. 3. The excavated earth is being kept aside and is being simultaneously reused for filling and leveling. 4. Minor works. The soil erosion issue is not there as there is no cutting and moreover the area is rocky. 5. No storage of fuel and lubricants at site. 6.Natural water source in Harshil but not within the impact zone. 7. Generation of dust is very less. That is controlled through sprinkling. 8. Due to the magnitude of works, the construction vehicles usage is not much in the project. It is only for the transportation of construction materials and frequency is very less. 9. Most of the activities are manual. 10. The material handling at site is fine as most of the workers were seen using personal protective equipment. In Harsil site Contractor was directed to enforce usage of PPEs. 11. Construction waste generated so far has been stored for utilization and disposal further at designated location. The waste disposal plan will be prepared in the end phase of construction period by the contractor and reviewed by the DSC and will be approved in consultation with PIU 12. The existing sanitation facilities are utilized. 13. Use of PPE’s is satisfactory. Only in Harsil site Contractor was directed to enforce usage of PPEs. Caution sign board is also put up at all sites. 14. Risk Force Majeure: situation not occurred so far. Necessary action will be taken as per contract provisions if such situation arises 15. Instructions have been given to contractor regarding malaria risk and prevention measures. 16. Chance Archaeological finds have not been found so far during the construction works. The contractor has been instructed to inform to PIU and DSC, if any chance find is found. 17. The project is not impacting any religious structures rather its
• Housekeeping to be improved at Phalasi.
• Usage of PPEs is to be ensured at Harsil.
• Submission of regular environmental monitoring report
44
IEE/EMP
Component Environmental issues Responsibility Compliance Status Corrective actions
meant for maintenance and restoration of religious structures. 18. There is neither any route of migratory birds nor any location where migratory birds are visiting, in any of the sites.
Operation 1-Environmental conditions 2.Uncontrolled tourism 3. Management of the toilet blocks 4. Adequate drainage 5. Unhygienic condition due to poor maintenance of sanitation facilities and irregular solid waste collection 6. Increased waste loads onto the existing waste disposal facilities
PMU, UTDB The project not yet reached Operation phase Not applicable
45
Table 7 (iv): EMP Monitoring Status Chart- Conservation of Cultural Heritage and urban place making in Nainital Lot-1
IEE/EMP Component Environmental issues Responsibility Compliance Status Corrective actions
Location Lack of sufficient planning to assure long term sustainability of the facilities and ensure protection specially from earthquake and other natural disasters
PMU & DSC Complied Not Applicable
Pre-construction activities by the Contractor
1.Construction Camps 2. Defining of construction/work areas on ground for activities within 200m of the boundaries of the protected areas. 3. Circulation plan during construction. 4. Site clearance activities 5.Drinking water availability 6. Identification of disposal sites 7. Waste management on site
Contractor & DSC Complied Waste was dumped to a designated site. But due to filling of the site, identification of new site is being done by DFO and Distt Administration. Till the identification of new site, waste is stored near the working sites. As per above, presently the waste generated is segregated and stored at the site for possible reuse and disposal.
Contractor and PIU has been instructed to follow up with the District Administration Waste is to be suitably covered till final disposal at the designated site.
Construction 1. Improper stockpiling 2.Quarry/ Borrow pit operations 3.Stripping, stocking & preservation of top soil 4.Soil erosion 5. Water pollution due to fuel/lubricants 6. Siltation of water bodies 7. Generation of dust 8.Emission from construction vehicles 9. Noise from construction equipment 10. Material handling at site 11. Disposal of construction waste/debris 12. Sanitation facilities at project site
Partially Complied
• Proper stockpiling was not seen. So instructions were given to the Contractor.
• Silt prevention measures undertaken (silt traps) in Treatment of Dam wall, restoration of Band Stand and Municipal Library.
• Due to filling of the earlier designated site and time taken in designation of new site by the Distt Administration and DFO, presently the waste generated is segregated and stored at the site for possible reuse and disposal.
• At Library site, books were not covered leading to deterioration of the books
Contractor has been instructed for proper stockpiling of Construction material in demarcated area with barricades Contractor was directed to cover and pack all the books till completion of works in the library building
46
IEE/EMP Component Environmental issues Responsibility Compliance Status Corrective actions
13. Safety measures 14. Risks force majeure 15. Malaria risk 16.Chance archaeological finds 17.Religious structures 18. Construction Staff causing disruption to migratory birds
Waste management is not proper at DSA Flats site.
Operation
1-Environmental conditions PMU, UTDB The project not yet reached Operation phase
2.Uncontrolled tourism
3. Management of the toilet blocks
4. Adequate drainage
5. Unhygienic condition due to poor maintenance of sanitation facilities and irregular solid waste collection
6. Increased waste loads onto the existing waste disposal facilities
47
Table 7 (v): EMP Monitoring Status Chart- Restoration and adaptive reuse of Almora Fort (Rani Mahal)
IEE/EMP
Component Environmental issues Responsibility Compliance Status Corrective actions
UK/IDIPT/III/BHT/03
Location
Lack of sufficient planning to assure long term sustainability of the facilities and ensure protection specially from earthquake and other natural disasters
PMU & DSC Complied
Pre-construction activities by the Contractor
1.Construction Camps 4. Site clearance activities 5. Drinking water availability 6. Identification of disposal sites 7. Waste management on site
Contractor & DSC Complied The site clearance activities have been carried out and excavated earth has been kept aside. The waste material generated due to clearance and demolition activities has been used to the extent possible in the project. Towards the end of construction phase, the site for disposal of waste material will be identified, keeping in view the quantity to be disposed off. Waste management not proper
Waste management not proper. Stockpiles of waste to be properly covered till possible reuse in later stages or dispose of at identified disposal sites
Construction 1. Improper stockpiling 2.Quarry/ Borrow pit operations 3.Stripping, stocking & preservation of top soil 4.Soil erosion 5. Water pollution due to fuel/lubricants 6. Siltation of water bodies 7. Generation of dust 8.Emission from construction vehicles 9. Noise from construction equipment 10. Material handling at site 11. Disposal of construction waste/debris 12. Sanitation facilities at project site 13. Safety measures 14. Risks force majeure
Contractor & DSC Partially complied
• The main constructions materials at present being used are bricks, cement, stones, sand and steel rods. These are not stocked properly, for which instructions were given Material is being purchased from licensed quarries.
• Top soil generated from foundation work is preserved for landscaping
• No storage of fuels at site
• Frequency of transportation vehicles is very limited. The trucks carrying construction material have pollution under control certificates
• Duct suppression measures being undertaken
• Usage of PPE not proper and directions were given. Waste is presently stored at site. for utilization and
Instruction has been given to the contractor for proper stockpiling in demarcated area with barricades. Usage of PPE not proper and directions were given.
48
IEE/EMP
Component Environmental issues Responsibility Compliance Status Corrective actions
UK/IDIPT/III/BHT/03
15. Malaria risk 16.Chance archaeological finds 17.Religious structures 18. Construction Staff causing disruption to migratory birds
suitable disposal further at designated location
Operation 1-Environmental conditions 2.Uncontrolled tourism 3. Management of the toilet blocks 4. Adequate drainage 5. Unhygienic condition due to poor maintenance of sanitation facilities and irregular solid waste collection 6. Increased waste loads onto the existing waste disposal facilities
PMU, UTDB The project not yet reached Operation phase Not Applicable
49
Table 7 (vi): EMP Monitoring Status Chart- Restoration and adaptive reuse of Champawat Fort (Banasur) IEE/EMP Component Environmental issues Responsibility Compliance Status Corrective actions
UK/IDIPT/III/BHT/03
Location Lack of sufficient planning to assure long term sustainability of the facilities and ensure protection specially from earthquake and other natural disasters
PMU & DSC Complied
None
Pre-construction activities by the Contractor
1.Construction Camps 2. Defining of construction/work areas on ground for activities within 200m of the boundaries of the protected areas 3. Circulation plan during construction 4. Site clearance activities 5. Drinking water availability 6. Identification of disposal sites 7. Waste management on site
Contractor & DSC Complied
None
Construction 1. Improper stockpiling
Work progress in reporting period is very slow due to technical issues at site 1. The main construction materials being used are bricks, cement, stones, sand and steel rods. Proper stockpiling is done.
2.Quarry/ Borrow pit operations
2. Material is being purchased from licensed quarries. No quarrying/borrow pit operations
3.Stripping, stocking & preservation of top soil
3. Top soil generated from foundation work is preserved for reuse.
4.Soil erosion
4. The soil erosion issue is not there as there is no cutting or steep slope issues involved in the project.
5. Water pollution due to fuel/lubricants
5. The construction vehicles usage is not much in the project. Fuel/ lubricants are not stored.
6. Siltation of water bodies 6. No water body in immediate vicinity
7. Generation of dust 7. Work progress very slow. No significant dust generation
8.Emission from construction vehicles
8. Frequency of transportation vehicles is very limited. Material is carried manually to the Fort site.
50
IEE/EMP Component Environmental issues Responsibility Compliance Status Corrective actions
9. Noise from construction equipment
9. In the present phase, the only noisy equipment used is concrete mixer and it is operated intermittently.
10. Material handling at site 10. Usage of PPEs was not satisfactory.
11. Disposal of construction waste/debris
11. Presently stored at site. Construction waste generated so far has been stored for utilization and suitable disposal further at designated location
12. Sanitation facilities at project site
12. Sanitation facility at site improved.
13. Safety measures
13. PPEs were available but not used by many labourers
14. Risks force majeure
14. Risk Force Majeure situation has not occurred so far. Necessary action will be taken as per contract provisions
15. Malaria risk
15. Instructions issued regarding malaria risk and prevention were given.
16.Chance archaeological finds
16. Chance Archaeological finds have not been found so far during the construction works. The contractor has been instructed to inform to PIU and DSC, if any chance find is found
17.Religious structures
17.The project is not impacting any religious structures
18. Construction Staff causing disruption to migratory birds
18. There is neither any route of migratory birds nor any location where migratory birds are visiting
Operation 1-Environmental conditions PMU, UTDB The project not yet reached Operation phase Not Applicable
2.Uncontrolled tourism
3. Management of the toilet blocks
4. Adequate drainage
5. Unhygienic condition due to poor maintenance of sanitation facilities and irregular solid waste collection
6. Increased waste loads onto the existing waste disposal facilities
51
Table 7(vii): EMP Monitoring Status Chart – Restoration and Adaptive Reuse of Pithoragarh Fort, Pithoragarh
IEE/EMP
Components
Environmental Issues Responsibility Compliance Status Corrective Actions
UK/IDIPT/III/BHT/07
Location impacts Lack of sufficient planning to assure long term sustainability of the improvements and ensure protection of the assets created and the architectural character of the surroundings.
PMU & Line Agency
Complied Not applicable
Design & pre construction impacts
1. Increased storm water runoff from alterations of the site‘s natural drainage patterns due to additional structures in TRH complex and landscaping works in the area and on lake edge.
DSC & PIU Complied Not applicable
2. Selection of materials and construction technologies, if not carefully chosen, will adversely impact the aesthetic appeal of the destinations
3. Integration of energy efficiency and energy conservation programs in design of subproject components
Pre-construction activities by the contractor
1. Circulation plan during construction in the tourist destinations
Contractor & DSC
• Complied
• Construction/demolition waste is being disposed at designated site identified by PIU
Not applicable
2. Site clearance activities, including delineation of construction areas
3. Drinking water availability and water arrangement
4. Identification of sites for disposal of construction and demolition work
52
IEE/EMP
Components
Environmental Issues Responsibility Compliance Status Corrective Actions
Construction impacts 1. Improper stockpiling of construction materials cause impacts starting from obstruction of drainage, disturbance/safety hazard to tourists, etc. 2. Stripping, stocking and preservation of top soil 3. Soil Erosion 4. Soil and Water Pollution due to fuel and lubricants, construction waste 5. Generation of Dust 6.Emission from construction vehicles, equipment and machinery 7. Noise from construction equipment 8. Material Handling at Site 19. Disposal of Construction Waste/Debris/Cut Material 10. Safety Measures During Construction 11. Risk caused by Force Majeure 12. Malaria Risk
Contractor • Partially complied
• Stockpiles not demarcated and uncovered
• Water sprinkling is being done at construction site and construction material is being carried by covered trucks.
• Environment monitoring report is not being submitted regularly.
• Waste management at site to be improved
• Usage of PPEs is satisfactory
Proper stockpiling and coverage to be done General housekeeping at site needs to be improved and the liter bins needs to be regularly disposed at municipal dumping site. Contractor has been instructed to get regular testing of air water and noise as per EMP
O & M impacts 1. Environmental Conditions PMU, UTDB Not Yet Started
2. Adequate drainage of site area
53
Table 7 (viii) : EMP Monitoring Status Chart- Creation of Pedestrian Route for Pilgrims and Tourists in Haridwar IEE/EMP Component Environmental issues Responsibility Compliance Status Corrective actions
UK/IDIPT-III/KOT/01
Location 1 Siting of facilities 2 Lack of sufficient Planning 3 Impact on archaeological remains 4 Other
PMU & DSC Complied None
Pre-construction
activities by the
Contractor
1.Construction Camps 2. Defining of construction/work areas on ground for activities within 200m of the boundaries of the protected areas 3. Circulation plan during construction 4. Site clearance activities 5. Drinking water availability 6. Identification of disposal sites 7. Waste management on site
Contractor & DSC Complied
Not Applicable
Construction 1. Improper stockpiling 2.Quarry/ Borrow pit operations 3.Stripping, stocking & preservation of top soil 4.Soil erosion 5. Water pollution due to fuel/lubricants 6. Siltation of water bodies 7. Generation of dust 8.Emission from construction vehicles 9. Noise from construction equipment 10. Material handling at site 11. Disposal of construction waste/debris 12. Sanitation facilities at project site 13. Safety measures 14. Risks force majeure
Contractor and DSC Partially Complied
1. The main construction materials at present being used
are bricks, cement, sand and steel bars. These are being
stocked properly.
2. The contractor is obtaining sand and sub grade from the licensed quarries. No borrow pit operations have been carried out so far. 3- The top soil generated at Integrated facility complex site at Haridwar excavation was kept aside. Later it has been used in landscaping works. Similarly excavated scarified bituminous material at Solani Park has been used in the fill works. 4. The soil erosion issue is not there as there is no cutting or steep slope issues involved in the project.
The contractor has been
instructed to segregate the
waste at one location at
integrated facility complex
and enclose it with caution
tape.
The contractor has been
advised to improve bathing
and toilet facilities for
women work force.
The contractor has been
advised to improve the
housekeeping at Integrated
Multi Facility Complex site.
54
IEE/EMP Component Environmental issues Responsibility Compliance Status Corrective actions
15. Malaria risk 16. Chance archaeological finds 17.Religious structures 18. Construction Staff causing disruption to
migratory birds
5. The fuel and lubricants are not stored at site as project is small in nature. These are purchased from market as per needs. There is no maintenance of vehicles at site also. Hence there is no issue of soil and water pollution. 6. The excavated earth was generated at Integrated Multi Facility Complex. This earth was kept aside and is away from Upper Ganga canal. This earth after completion of foundation works has been used in filling. Hence no chance of any siltation in Canal due to construction activities . 7. Necessary dust suppression measures such as water spray are taken up. 8. The construction vehicles usage is only for the transportation of construction materials and a small concrete mixer at site. The trucks carrying construction material have pollution under control certificates. The mixer and small generator operate intermittently. 9. In the current period the only noisy equipment used is concrete mixer and it is operated intermittently. No excess noise generation is on account of construction activities. Noise monitoring is being taken up regularly. 10. The material handling at site is proper as most of the workers were seen using personal protective equipment during material handling. 11. So far maximum construction waste has been utilized in filling and rest is stored at site for disposal in later stages. Waste management at camp site in multi facility complex is not proper. 12. Sanitation facilities at construction camp (Toilets) not being maintained properly and many a times are not operational which pose risk of contamination of Upper Ganga canal water. 13. Usage of personal protective equipment ( PPEs) such as hand gloves, shoes, helmets, jackets , etc was seen.
55
IEE/EMP Component Environmental issues Responsibility Compliance Status Corrective actions
14. Risk Force Majeure situation has not occurred so far. Necessary action will be taken as per contract provisions 15. Actions taken by contractor to prevent water logging and conditions for breeding of mosquitoes. 16. Chance Archaeological finds have not been found so far during the construction works. 17. The project is not impacting any religious structures 18 The project site is located in an urban area and there is neither any route of migratory birds or any location where migratory birds are visiting.
Operation 1-Environmental conditions 2.Uncontrolled tourism 3. Management of the toilet blocks 4. Adequate drainage 5. Unhygienic condition due to poor maintenance of sanitation facilities and irregular solid waste collection 6. Increased waste loads onto the existing
waste disposal facilities
PMU, UTDB The project not yet reached Operation phase Not applicable
56
Table 7(ix): EMP Monitoring Status Chart- Development of Tourism Infrastructure in Sem Mukhem
IEE/EMP Component Environmental issues Responsibility Compliance Status Corrective actions
UK/IDIPT-III/KOT/02
Location impacts 1. Siting of facilities 2 Lack of sufficient planning 3.Impact on archaeological remains 4. Other
PMU & Line Agency Complied None
Design & pre construction
impacts
1. Impact on sensitive areas 2. Slope stability related issues 3. Increased storm water runoff 4. Impact on ground water quality 5. Impact on aesthetic appeal 6. Integration of energy conservation
DSC & PIU 1. No acquisition of any forest ( reserved/protected) area 2. The sub project construction works on pathway are on slope. The natural slope is maintained in the pathway and other construction works. The side slopes around pathway are compacted. 3. The storm water runoff issue is not be there at rest shelter or at pathway as these are in hilly terrain having quick natural drainage. No storm water runoff generation seen in Mukhem village. 4. No impact on ground water quality. Water requirement for construction is very less (<4000 liters/day) and is being met from nearby natural reservoir. The minor requirement for construction has no impact on reservoir or surrounding eco system. The waste water generation is well taken care. 5. No impact on aesthetic appeal due to construction works. 6. Integration of Energy conservation measures have been planned in the project design. The project plans to use solar lighting system and LED lighting.
None
Pre-construction activities by
the Contractor
1.Construction Camp 2. Defining of construction/work areas on ground for activities within 200m of the boundaries of the protected areas
Contractor & DSC Complied
None
57
IEE/EMP Component Environmental issues Responsibility Compliance Status Corrective actions
3. Circulation plan during construction 4. Site clearance activities 5. Drinking water availability 6. Identification of disposal sites 7. Waste management on site
Construction impacts 1. Improper stockpiling 2.Quarry/ Borrow pit operations 3.Stripping, stocking & preservation of top soil 4.Soil erosion 5. Water pollution due to fuel/lubricants 6. Siltation of water bodies 7. Generation of dust 8.Emission from construction vehicles and equipment 9. Noise from construction equipment 10. Material handling at site 11. Disposal of construction waste/debris 12. Safety measures 13. Risks force majeure 14. Malaria risk 15. Chance archaeological finds 16.Religious structures 17. Construction Staff causing disruption
to migratory birds
Contractor and DSC Partially Complied 1. The contractor is using cement, steel, sand and subgrade at pathway sites, temple site and at Mela Ground sites. Storage of construction material is not much as significant construction work has been completed. 2. The contractor is obtaining sand and subgrade from the licensed quarries and has been instructed to submit copy of license of the quarry. 3. The excavated earth for foundation works of rest shelter has been reused for filling. The Mela ground is a waste and barren land so top soil is of no importance as it has rocky and non fertile nature. The excavated earth from reservoir deepening near Mela ground has been used in filling works of retaining wall of this reservoir. 4. So far in the construction works no soil erosion issue has been identified. In the pathway works natural slope is maintained. At reservoir site, side slopes will be compacted and stabilized. 5. The fuel and lubricants are not stored at site and these are purchased on need basis so question of water pollution due to fuel and lubricants is not there. 6. The project involves deepening of reservoir near Mela Ground. The reservoir excavation work has been completed. The excavated earth mainly comprising of silt was kept aside. The side slopes of reservoir are being stabilised through compaction and pitching. The excavated earth is being used in fill works of retaining wall of this reservoir. 7. The generation of dust is there from construction
1-The contractor has been instructed to regularly submit the environment monitoring reports to PIU-PMU. 2-The contractor has been instructed to prepare plan for waste disposal from various sub project locations specially the excavated earth from the reservoir site. The earth should be used in fill works of retaining wall of reservoir. 3-The contractor has been advised to remove left over material from pathway construction sites.
58
IEE/EMP Component Environmental issues Responsibility Compliance Status Corrective actions
material handling such as sand, sub grade and cement. Necessary measures for dust suppression are taken at site as per needs. These measures include water spray and keeping sand and cement inside the cover shed. Keeping sand piles in semi wet form through water spray. Regular Environmental monitoring Is not being done by Contractor. 8. At project site no construction vehicles are used except trucks bringing construction materials at site. These trucks/tempos have pollution under control certificates. The only construction equipment used at site is currently mixer, which is Diesel Generator operated. This mixer is operating intermittently and as such there is no issue of air emissions. 9. In the current construction phase of project mixer is the only noise generating equipment is in operation. No noise issue has been felt during the site visits. This is operated intermittently. At Mukhem village temple site, and at pathway construction works are not taken up during night time. Noise level monitoring is not being taken up as per monitoring plan. 10. The material handling by the workers at site is proper as construction labour were seen using personal protective equipment such as gloves, shoes, helmets, etc. 11. Presently construction waste /debris generation was seen at rest shelter site at Mela Ground. The excavated earth has also been generated at Reservoir site due to deepening. The maximum construction waste will be reutilised. The material which cannot be used will be disposed off. For this a disposal plan will be prepared in later phase of construction period. The contractor has been advised to segregate waste and store at one place at Mela Ground. 12. The contractor has procured personal protective equipment such as helmets, gum boots, jackets, gloves, etc. These are being used. The work force of the
59
IEE/EMP Component Environmental issues Responsibility Compliance Status Corrective actions
contractor has been sensitized for use of PPEs by the DSC environmental expert during site visits. 13. So far conditions for Force Majeure have not been faced at the project site. 14. The project site being at an elevated height in a hilly terrain where low temperatures prevail. No mosquito breeding has been felt. However, contractor has been instructed to take necessary measures in consultation with local state health department. 15. Chance Archaeological finds have not been found so far during the construction works. The contractor has been instructed to inform to PIU and DSC , if any chance find is found. Necessary procedure such informing to state Archeological Department and waiting for their instruction, will be followed. 16. The existing temple at Mukhem village is being renovated so this will have a positive impact. The facilities being created at Mela ground will enhance pilgrimage at Sem Nagraj temple, so project overall will have positive impact on Religious structure. 17. No action needed as the project site is not close any route of migratory birds or any location where migratory birds are visiting.
O & M impacts 1. Environmental conditions 2.Uncontrolled tourism 3. Management of the toilet blocks 4. Adequate drainage 5. Unhygienic condition due to poor maintenance of sanitation facilities and irregular solid waste collection 6. Increased waste loads onto the existing waste disposal facilities
PMU,PIU and
Contractor (only
during defect liability
period)
1-Not Applicable as project not yet completed Not Applicable
60
Table 7(x): EMP Monitoring Status Chart- Development of Traditional medicine and Yoga Training Centres IEE/EMP Component Environmental issues Responsibility Compliance Status Corrective actions
Location impacts Lack of sufficient planning to assure long
term sustainability of the facilities and ensure
protection specially from earthquake and
other natural disasters . Finalization of
locations of project sites
PMU & Line
Agency
Complied. Work has not started in Naukuchiyatal and Lansdowne
None
Pre-construction activities by
the Contractor 1. Layout of components to avoid impacts on
the aesthetics of the sub-project sites
2. Increased storm water runoff from
alterations of the site’s natural drainage
patterns due to landscaping, excavation
works, construction of parking lots, and
addition of paved surface at sub-project sites
Contractor & DSC 1. Works presently are carried out only in 05 Tourist Rest Houses, out of which works have completed in Dhanaulti and is under progress in the remaining 04. Work as just started in Ganga Resort, Rishikesh. 2. Works are carried out within existing Tourist Rest House only and no natural drainage patterns are disturbed. No additional parking lots or landscaping planned as part of sub-project
None
Construction impacts 1.Construction Camps - Location, Selection, Design and Layout 2.Site clearance activities, including delineation of construction areas at sub-project sites 3.Drinking water availability for construction crew 4. Waste disposal 5. Improper stockpiling of Construction Material 6.Soil and Water Pollution due to fuel and lubricants, construction wastes 7.Siltation of water bodies due to spillage of construction wastes 8. Generation of dust 9.Emission from construction vehicles, equipment and machinery 10. Noise pollution 11.Material handling at site
Contractor and
DSC
Complied 1. Magnitude of works very less. No construction camp
required in any of the sites. 2. Works carried out within existing TRHs only. 3. Drinking water is being made available from existing
supply of TRHs. 4. Magnitude of waste generation is very less. Presently, it
is being stored at site, for reuse/ adequate disposal at later stages. The contractor has been advised to segregate waste and store at one place in the TRHs.
5. Since in all sites, modification/ refurbishment of existing TRHs is carried out, Storage of construction material is not much which is segregated and stored at site.
6. Storage of fuels is not required, and is brought from market as per needs. Construction waste requirement is also not much which is segregated and stored properly at site.
7. Works carried out within existing TRH, no issues of siltation of water bodies
None
61
IEE/EMP Component Environmental issues Responsibility Compliance Status Corrective actions
12.Disposal of construction waste/debris 13.Safety measures 14.Clearing of Construction Sites
8. The generation of dust is in very less amount Necessary measures for dust suppression are taken at site which include water spray and keeping sand and cement inside the cover shed. At all project sites, no other construction vehicles are used except trucks bringing construction materials at site. The magnitude of works being very less, the frequency of vehicles is very less.
9. No major noise generating equipment is in operation. No noise issue has been felt during the site visits. works are not taken up during night time.
10. Very few labour are involved as works are very small in nature. Construction labour were seen using personal protective equipment such as gloves, shoes, helmets, etc.
11. No major waste disposal required. Waste will be disposed off in consultation with the management of TRHs.
12. The contractor has procured personal protective equipment such as helmets, gum boots, jackets, gloves, etc. These are being used.
13. Construction camps have not been made in any of the sites, as work scope is very less.
O & M impacts Waste oil generation on account of Panchkarma facilities and its safe disposal Safety risks Unhygienic conditions due to poor maintenance of sanitation facilities and irregular solid waste collection
PMU,PIU and Contractor (only during defect liability period)
1-Not Applicable as project not yet completed and reached O&M Phase.
Not Applicable
62
7. Approach & Methodology engaged for environmental monitoring of the project
15. Continuous monitoring of EMP implementation is being carried out by DSC, PIU and PMU.
16. Concerned staff of DSC and PIU visit the construction sites and report to Team Leader DSC and
PMC about issues/ problems related to environmental non-compliance. Necessary directions, in case
of non-compliance are being issued to the contractors on the site and through letters about the
procedures to resolve the problems/issues or requirements. The Safeguards Staff of DSC conduct
regular site visits to monitor the implementation of safeguards measures on sites.
8. Monitoring of environmental receptors/ attributes
Monitoring basis
17. Monitoring for the implementation of Environmental Monitoring Plan/Management Plan is required to
be done to check if any adverse impact is being caused by the construction activities. The monitoring
of these variables is to be carried out in construction sites within 100 m impact zone of the sub
project.
18. The monitoring of environmental variables is to be carried out as per the agreed Environmental
Monitoring Plan.
Type of environmental receptor/ attribute to be monitored
19. The environmental attributes to be monitored include the air, noise and water quality parameters at
the construction sites in sub project sites. The air quality parameters monitored include RSPM
(PM10),PM2.5 SO2 and NO2. The water quality parameters include temperature, pH, electrical
conductivity (EC), dissolved oxygen (DO), biochemical oxygen demand (BOD), total suspended
solids (TSS), total dissolved solids (TDS) and turbidity. In case of noise the day and night time Leq
values are monitored.
63
Methods of monitoring and equipment used
20. The parameters and standard methodology used for monitoring is given in Table 8.
Table 8: Parameters and Methodology for Environmental Monitoring
Parameter Methodology
(PM10) High Volume Sampler method (attached with cyclone)/Respirable Dust samplers.
(PM2.5) PM2.5 sampler, Gravimetric method
SO2 IS Modified West and Gaeke Method
NO2 Jacob &Hochheiser Modified (Sodium Arsenite) Method.
Noise Level Direct Reading Sound Level Meter.
Temperature Digital/Mercury Thermometer Method.
pH Electrometric Method.
EC Electrometric Method.
DO Winkle’s Method Using Azide Modification
BOD5 Five Days BOD as per APHA 2005
TDS Digital Meter Method.
TSS Gravimetry (Filtration and Drying at 105oc)
Turbidity Nephelo Turbidity Method.
64
9. Implementation of Environmental Monitoring Plan
21. Implementation of Environmental Monitoring Plan for sub projects is shown in Table 9. Monitoring
Reports for 8 out of 10 works packages have been submitted in the reporting period. For the rest 02
directions have been given to the contractors for submission of reports.
Table 9 (i): Implementation of Environmental Monitoring Plan- For Projects under PIU DDN
Component
Periods of
monitorin
g
Parameters/Poll
utants Standard
Base line
status Monitoring result during project
Implementation
(UK/IDIPT-III/ DDN/03 Rural Tourism (Kabiltha) Construction Stage
Noise (near
main gate of
project site)
10-10-2017 Sound Level Leq.
dB(A)
Noise
Standards for
55 dB( A) for
Day Time and
45 dB( A) for
Night Time
Day time
L max -- 58.8
L Min 49.2
Leq - 52.3
CPCB Limit in
dB(A) Leq
(Residential
Area) 55.0
Sound Level Leq.
dB(A)
Noise
Standards for
55 dB( A) for
Day Time and
45 dB( A) for
Night Time
Night time
L max -- 49.3
L Min 33.1
Leq 45.4
CPCB Limit in
dB(A)
50.0
Ambient Air
Quality
(near back
side of
project site)
10-10-
2017
Particulate
Matter (PM10),
µg/m3
100 70.06
Particulate
Matter (PM2.5),
µg/m3
60 35.2
Sulphur Dioxide
(So2). µg/m3
80 10.08
65
Component
Periods of
monitorin
g
Parameters/Poll
utants Standard
Base line
status Monitoring result during project
Implementation
Nitrogen Dioxide
(No2) µg/m3
80 12.45
Carbon
Monoxide (Co),
mg/m3
4 0.70
Water
Quality
(drinking
water( tap
water )
10-10-
2017
PH (at 25°C)
Colour
Turbidity
Odour
Taste
Total Hardness
as CaCo3
Calcium as Ca
Alkalinity as
CaCo3
Chloride as CI
Magnesium as
Mg
Total Dissolved
Solids
Iron as Fe
Copper as Cu
Total Coliform
E. Coli
CPCB
Standards for
Surface water
bodies and
Drinking
Water
Standards for
Potable water
7.34
BDL (DL-5
Hazen) BDL
(DL-INTU)7.
Agreeable
Agreeable
206.1034
17.10
107.10
18.30,
17.40,
220.20,
0.11
0.01,
<2/I00ml
Absent
Component Periods of
monitoring
Parameters/Poll
utants Standard
Base line
status Monitoring result during project
Implementation
UK/IDIPT-III/ DDN/01 Lot1 (Durgadhar and Tungeswar)
66
Component Periods of
monitoring
Parameters/Poll
utants Standard
Base line
status Monitoring result during project
Implementation
Noise (near
main gate of
project site)
19-12-17 Sound Level
Leq. dB(A)
Noise
Standards for
55 dB( A) for
Day Time and
45 dB( A) for
Night Time
Day time
L max – 54.1
L Min 48.2
Leq - 52.3
CPCB Limit
in dB(A) Leq
(Residential
Area) 55.0
19-12-17 Sound Level
Leq. dB(A)
Noise
Standards for
55 dB( A) for
Day Time and
45 dB( A) for
Night Time
Night time
L max – 44.2
L Min 37.1
Leq 45.0
CPCB Limit in
dB(A)
50.0
Ambient Air
Quality (near
back side of
project site)
19-12-17
Particulate
Matter (PM10),
µg/m3
100 68.10
Particulate
Matter (PM2.5),
µg/m3
60 45
Sulphur Dioxide
(So2). µg/m3
80 8.20
Nitrogen Dioxide
(No2) µg/m3
80 21.10
Carbon
Monoxide (Co),
mg/m3
4 0.10
Water
Quality
(drinking
19-12-2017
PH (at 25°C)
Colour
CPCB
Standards for
Surface water
7.45
<5
67
Component Periods of
monitoring
Parameters/Poll
utants Standard
Base line
status Monitoring result during project
Implementation
water( tap
water )
Turbidity
Odour
Taste
Total Hardness
as CaCo3
Calcium as Ca
Alkalinity as
CaCo3
Chloride as CI
Magnesium as
Mg
Total Dissolved
Solids
Iron as Fe
Copper as Cu
Total Coliform
E. Coli
bodies and
Drinking
Water
Standards for
Potable water
BDL
Agreeable
Agreeable
258.2
65.22
243.40
12.12
18.05
342.0
0.08
<0.05
<2/I00ml
Absent
68
Component Periods of
monitoring
Parameters/Poll
utants Standard
Base line
status Monitoring result during project
Implementation
UK/IDIPT-III/ DDN/01 Lot1 (Durgadhar and Tungeswar)
Noise (near
main gate of
project site)
19-11-2017 Sound Level
Leq. dB(A)
Noise
Standards for
55 dB( A) for
Day Time and
45 dB( A) for
Night Time
Day time
L max – 53.2
L Min 40.4
Leq - 55.0
CPCB Limit
in dB(A) Leq
(Residential
Area) 55.0
19-11-2017 Sound Level
Leq. dB(A)
Noise
Standards for
55 dB( A) for
Day Time and
45 dB( A) for
Night Time
Night time
L max – 43.2
L Min 32.3
Leq 45.0
CPCB Limit in
dB(A)
50.0
Ambient Air
Quality
(near back
side of
project site)
19-12-2017
Particulate
Matter (PM10),
µg/m3
100 73.10
Particulate
Matter (PM2.5),
µg/m3
60 45.20
Sulphur Dioxide
(So2). µg/m3
80 6.30
Nitrogen Dioxide
(No2) µg/m3
80 19.00
Carbon
Monoxide (Co),
mg/m3
4 0.21
Water
Quality
19-12-2017 PH (at 25°C) CPCB
Standards for
7.25
69
Component Periods of
monitoring
Parameters/Poll
utants Standard
Base line
status Monitoring result during project
Implementation
(drinking
water( tap
water )
Colour
Turbidity
Odour
Taste
Total Hardness
as CaCo3
Calcium as Ca
Alkalinity as
CaCo3
Chloride as CI
Magnesium as
Mg
Total Dissolved
Solids
Iron as Fe
Copper as Cu
Total Coliform
E. Coli
Surface water
bodies and
Drinking
Water
Standards for
Potable water
<5
BDL
Agreeable
Agreeable
218.12
62.12
240.12
12.10
22.05
365.0
0.11
<0.05
<2/100ml
Absent
70
Table 9 (ii): Implementation of Environmental Monitoring Plan- For Projects under PIU Kotdwara
Component Periods of
monitoring Parameters/Pollutants Standard
Base
line
status
Monitorin
g result
during
project
Impleme
ntation
Remarks
UK/IDIPT-III/KOT/01 Creation of Pedestrian Route for Pilgrims and Tourists in Haridwar
Noise Post
Monsoon
season
Sound Level Leq. dB(A) Noise
Standards
for 55
dB( A) for
Day Time
and 45 dB(
A) for
Night Time
- (i)
Integrate
d Facility
Complex
Haridwar
1-Leq (
Day)
=48.6
dB( A)
2- Leq
(Night) =
41.50
dB(A)
3-Leq
(Min)
=40.2
dB(A)
4- Leq
(Max)
=54.7dB(
A)
(ii)
Monitorin
g was
not
carried
out at
Solani
Park
Roorkee
site as
no
construct
ion work
was in
progress
at this
site.
The values are well
within the stipulated
limits.
Air Quality Winter
Season
SO2, NOX, CO , PM10
and PM2.5
Monitoring at at
Integrated Facility
Complex site at
NAAQS
Standards
-
Industrial,
Residenti
al, Rural
and other
Areas
All parameters of
ambient air quality
are well within the
limits. Detailed
monitoring results
are given in
71
Component Periods of
monitoring Parameters/Pollutants Standard
Base
line
status
Monitorin
g result
during
project
Impleme
ntation
Remarks
Haridwar Annexure-2.
Particulate Matter < 10
micron
100
- 91.0
ug/m3
Particulate Matter < 2.5
micron
60µg/m3
- 39.2
site
Sulphur dioxide,(SO2 )
80 µg/m3
12.80
Nitrogen dioxide(NO2)
80 µg/m3
22.40
ug/m3
Carbon Monoxide (CO) 02
mg/m3 for
08 hrs
0.70
mg/m3
Water
Quality
Winter
Season
1- Drinking Water at
camp and
Construction site
(Ground Water)
Drinking
water
standards
specified
in IS:
10500
-
1-
Colour-=
<1 Hazen
Unit
2- Odour=
Agreeable
3-pH=
7.90
4- Total
Hardness
as
CaCO3=
176 mg/l
5- TDS=
252 mg/l
6- BOD=
no test
done
7- Total
Coliform=
Not
detected
8- Iron as
All parameters of
drinking water at
Haridwar Integrated
facility Complex are
well within the limits
of Drinking water
specified in IS:
10500
72
Component Periods of
monitoring Parameters/Pollutants Standard
Base
line
status
Monitorin
g result
during
project
Impleme
ntation
Remarks
2- Upper Ganga Canal
near Haridwar
Integrated Facility
Complex Site
CPCB
Standards
for Surface
Water
Quality
-
Fe =0.18
mg/l
9-
Chloride
as Cl= 62
mg/l
11-
Fluoride
as F <
0.20 mg/l
Annexure-
2.
1-PH=7.5
2-
Dissolved
Oxygen
=6.3 mg/l
3- BOD (3
Days at
27 oC)=
< 1mg/l
4- COD =
<5mg/l
5-
Electrical
Conductivi
ty= 243
mg/l
6-
Ammonia
= <10
mg/l
7-Coliform
= Absent
Dissolved Oxygen,
pH, BOD and
coliform bacteria
parameters meet
the CPCB norm for
surface water
category A.
UK/IDIPT-III/KOT/02 Development of Tourism Infrastructure in Sem Mukhem
Noise Winter
Season
Sound Level Leq. dB(A) Noise
Standards
for 55
dB( A)
for Day
Time and
45 dB( A)
for Night
Time
- Leq (
Day) at
Mela
Ground -
50.2
dB(A)
Leq
(Night) at
The noise levels
are well within limits
during day and night
times.
73
Component Periods of
monitoring Parameters/Pollutants Standard
Base
line
status
Monitorin
g result
during
project
Impleme
ntation
Remarks
Mela
Ground
=42.10
dB(A)
Leq (Min)
at Mela
Ground
=41.30
dB(A)
Leq
(Max) at
Mela
Ground=
58.0
dB(A)
Air Quality Winter
Season
SO2, NOX, CO , PM10
and PM2.5
NAAQS
Standards
-
Industrial,
Residenti
al, Rural
and other
Areas
All monitored
ambient air quality
parameters are well
within the stipulated
limits at Mela
Ground
Particulate Matter < 10
micron
100
85.40
ug/m3 at
Mela
Ground
Particulate Matter < 2.5
micron
Sulphur dioxide,(So2 )
Nitrogen dioxide(NO2)
Carbon Monoxide (CO)
60µg/m3
80 µg/m3
80 µg/m3
02 mg/m3
for 08 hrs
41.70
ug/m3
11.40
ug/m3
19.20
ug/m3
0.4
mg/m3
74
Component Periods of
monitoring Parameters/Pollutants Standard
Base
line
status
Monitorin
g result
during
project
Impleme
ntation
Remarks
Water
Quality
Winter
Season
Parameters specified
for Drinking water in
IS: 10500
Drinking
Water
Standards
specified
in IS:
10500
1- Colour
= <1
Hazen
units
2- Odour
=Agreeabl
e
3-
Turbidity =
1.2 NTU
4- pH=
6.6
5- Total
Hardness
= 96 mg/l
6- Iron as
Fe = 0.16
mg/l
7-
Chlorides
=
27.70mg/l
8-
Fluoride <
0.20 mg/l
9- TDS-
156 mg/l
10- Total
Coli form
- Not
Detected
All monitoring
parameters are for
drinking water
available at Mela
ground where
construction works
were in Progress.
The monitoring
parameters of
drinking water are
well within the
stipulated limits of
Drinking Water
specified in IS:
10500. Detailed
results are given
Annexure-2.
75
Table 9 (iii): Implementation of Environmental Monitoring Plan- For Projects under PIU Bhimtal
Component Periods of monitoring
Parameters/ Pollutants Standard Base line status
Monitoring result during
project Implementatio
n
Remarks
Restoration and Adaptive Reuse of Banasur Fort (Champawat)
Noise (near construction site)
12/11/2017 to 13/11/2017
Sound Level Lmax, Lmin. dB(A)
Noise Standards for 55 dB( A) for Day Time and 45 dB( A) for Night Time (Residential Zone)
Lmax -50.8(Day), 42.2 (Night) dB(A)
Lmax 55.8 (Day), 47.1 (Night) dB(A)
Values are well within permissible level
Lmin – 40.3(Day), 34.5 (Night) dB(A)
Lmin – 46.2(Day), 36.8 (Night) dB(A)
Leq – 43.2(Day), 35.2 (Night) dB(A)
Leq – 50.1 (Day), 39.0(Night) dB(A)
Noise (Back site)
12/11/2017 to 13/11/2017
Sound Level Lmax, Lmin. dB(A)
Lmax -50.8(Day), 42.2 (Night) dB(A)
Lmax 54.9 (Day), 48.8 (Night) dB(A)
Lmin – 40.3(Day), 34.5 (Night) dB(A)
Lmin – 44.1(Day), 38.6 (Night) dB(A)
Leq – 43.2(Day), 35.2 (Night) dB(A)
Leq – 49. (Day), 42.5(Night) dB(A)
Air Quality (near Back site)
12/11/2017 to 13/11/2017
SO2, NOX, CO, PM10 and PM2.5
NAAQS Standards Baseline Status Near Construction site,
All parameters of ambient air quality are well within the limits. Particulate Matter < 10
micron 100 µg/m3
60.10 µg/m3 72.19 µg/m3
Particulate Matter < 2.5 micron
60µg/m3
34.10 µg/m3 36.32 µg/m3
Sulphur dioxide,(So2 ) 80 µg/m3 7.10 µg/m3 7.11µg/m3
Nitrogen dioxide(NO2) 80 µg/m3 19.30 µg/m3 29.09 µg/m3
Carbon Monoxide (CO) mg/m3
02 mg/m3 for 08 hrs 0.20 mg/m3 0.24mg/m3
Air Quality (near back side of fort)
12/11/2017 to 13/11/2017
SO2, NOX, CO , PM10 and PM2.5
NAAQS Standards Baseline Status Near Back Side of Fort
All parameters of ambient air quality are well within the limits.
Particulate Matter < 10 micron
100 µg/m3 62.10 µg/m3 72.19 µg/m3
Particulate Matter < 2.5 micron
60µg/m3 30.15 µg/m3 36.32 µg/m3
Sulphur dioxide,(So2 ) 80 µg/m3 7.18µg/m3 7.11 µg/m3
Nitrogen dioxide(NO2) 80 µg/m3 17.10µg/m3 21.09 µg/m3
Carbon Monoxide (CO) mg/m3
02 mg/m3 for 08 hrs 0.22 mg/m3 0.24 mg/m3
Water Quality Drinking water Village :-(Near Construction Site Champawat)
14/11/2017 to 17/11/2017
pH CPCB Standards for Drinking Water Standards for drinking water specified in IS: 10500
7.20 7.40 All parameters of drinking water are well within the limits of Drinking water specified in IS: 10500
Colour <5 <5
Turbidity(NTU) BDL BDL
Odour Agreeable Agreeable
Taste Agreeable Agreeable
Total Hardness mg/L 189.00 190.91
Calcium as Ca 70.20 50.89
Alkalinity mg/l 138.00 209.70
76
Component Periods of monitoring
Parameters/ Pollutants Standard Base line status
Monitoring result during
project Implementatio
n
Remarks
Chloride mg/l 20.10 12.89
Magnisium and Mg 18.10 14.1
Total Dissolved Solids mg/l
325.24 268.80
Iron mg/l 0.10 0.14
Copper mg/l <0.05 <0.06
Total Coliform 100 ml. at
37℃ (MPN)
<2/100ml <2/100ml
E-Coli / 100ml(MPN) Absent Absent
Restoration and Adaptive Reuse of Library, Nainital
Noise (At Near Construction Site Library)
14/11/2017 to 15/11/2017
Sound Level Lmax, Lmin. dB(A)
Noise Standards for 55 dB( A) for Day Time and 45 dB( A) for Night Time (Commercial Zone)
Lmax -52.3(Day),43.1 (Night)dB(A) Lmin – 32.1(Day),35.2 (Night)dB(A) Leq- 44.2, 38.1
Lmax – 54.8(Day), 47.9 (Night)dB(A) Lmin – 37.1(Day), 34.6 (Night)dB(A) Leq- 44.2(Day) , 40.0 (Night)
Values are well within permissible level
Noise (back site, library)
14/11/2017 to 15/11/2017
Sound Level Lmax, Lmin. dB(A)
Noise Standards for 55 dB( A) for Day Time and 45 dB( A) for Night Time (Commercial Zone)
At Near Back Side Library Lmax -53.7(Day),43.1 (Night)dB(A) Lmin – 38.1(Day),31.8 (Night)dB(A) Leq- 42.0, 37.2
Lmax -59.2 (Day),46.8 (Night)dB(A) Lmin – 43.2 (Day), 35.1 (Night)dB(A) Leq- 51.2 (Day), 41.4 (Night)
Values are well within permissible level
Air Quality (Near construction site, Library)
14/11/2017 to 15/11/2017
SO2, NOX, CO , PM10 and PM2.5
NAAQS Standards Baseline Status Near Construction Site, Library
All monitored ambient air quality parameters are well within the stipulated limits of air quality.
Particulate Matter < 10 micron
100 66.18 ug/m3 69.88 ug/m3
Particulate Matter < 2.5 micron
60µg/m3 35.10 ug/m3 35.89ug/m3
Sulphur dioxide,(So2 ) 80 µg/m3 7.34ug/m3 10.01 ug/m3
Nitrogen dioxide(NO2) 80 µg/m3 18.15ug/m3 23.78 ug/m3
Carbon Monoxide (CO) mg/m3
02 mg/m3 for 08 hrs 0.20 mg/m3 for 08 hrs
0.39 mg/m3 for 08 hrs
Air Quality (Near back side library)
14/11/2017 to 15/11/2017
SO2, NOX, CO , PM10 and PM2.5
NAAQS Standards Baseline Status Near back side library
Particulate Matter < 10 micron
100
68.15ug/m3 68.80 ug/m3
Particulate Matter < 2.5 micron
60µg/m3 38.12ug/m3 31.04 ug/m3
Sulphur dioxide,(So2 ) 80 µg/m3 9.08 ug/m3 12.55 ug/m3
Nitrogen dioxide(NO2) 80 µg/m3 17.10ug/m3 23.07 ug/m3
Carbon Monoxide (CO) mg/m3
02 mg/m3 for 08 hrs 0.20 mg/m3 for 08 hrs
0.46 mg/m3 for 08 hrs
77
Component Periods of monitoring
Parameters/ Pollutants Standard Base line status
Monitoring result during
project Implementatio
n
Remarks
Water Quality Drinking water (Tap Water)
15/11/2017 to 18/11/2017
pH- CPCB Standards for Drinking Water Standards for Potable water
7.08 7.31 All parameters of drinking water are well within the limits of Drinking water specified in IS: 10500
Colour <5 <5
Turbidity –(NTU) BDL BDL
Odour – Agreeable Agreeable
Taste – Agreeable Agreeable
Total Hardness mg/L - 432 189.60
Calcium as Ca- 168 48.23
Alkalinity mg/l 265 197.45
Chloride- mg/l 15.62 13.54
Magnisium and Mg- 64.42 18365
Total Dissolved Solids – mg/l
420 242.09
Iron - mg/l 0.02 0.12
Copper mg/l <0.06
Total Coliform 100 ml. at 37℃ (MPN)
Absent <2/100ml
E-Coli / 100ml(MPN) Absent Absent
Water Quality Surface water –Naini lake
15/11/2017 to 18/11/2017
pH- CPCB Standards for Surface water bodies Standards for Potable water
7.80 7.65
Colour <5 <5
Turbidity(NTU) BDL BDL
Total Hardness mg/L - 362.50 218.97
Calcium as Ca - 98.52 43.78
Total Alkalinity mg/l 271.44 232.80
Chloride- mg/l 65.30 20.05
Magnisium Hardness - 36.34 24.81
Sulfate as SO4- 52.30 32.45
Nitrate as NO3 2.44 1.01
Flouride as F 0.8 0.49
Sodium as Na – 19.70 21.67
Potassium as K- 3.70 7.89
TKN as N- 1.40 32.40
Total Phosphorous 0.26 0.22
COD- 4.15 22.89
Phenolic Compound <0.002 <0.001
Iron as Fe mg/l 0.15 0.46
Boron - 0.26 0.20
Sodium Absorption ratio -
2.84 1.99
Free Ammonia as N- 0.82 0.43
Dissolved Oxygen - 7.00 8.01
BOD(3 days at 27) - 10.00 6.89
Zinc as Zn- 0.14 0.24
Arsanic as As -<0.012 <0.010
Mercury as Hg <0.002 <0.001
Total dissolved Solids mg/l
420 317.97
E-Coli / 100ml(MPN)
Restoration and Adaptive Reuse of Almora Fort (Rani Mahal)
Noise (Near Back Site)
10/11/2017 to 11/11/2017
Sound Level Lmax, Lmin. dB(A)
Noise Standards for 55 dB( A) for Day Time and 45 dB( A) for Night Time (Residential Zone)
Lmax -48.2(Day),40.3 (Night)dB(A) Lmin – 32.1(Day),32.8
Lmax -57.9 (Day), 42.89 (Night)dB(A) Lmin –
Values are well within permissible level
78
Component Periods of monitoring
Parameters/ Pollutants Standard Base line status
Monitoring result during
project Implementatio
n
Remarks
(Night)dB(A) Leq – 43.4(Day),38.1 (Night)dB(A)
44.9(Day), 36.6 (Night)dB(A) Leq – 49.7 (Day), 39.9 (Night)dB(A)
Noise (Near Construction Site)
10/11/2017 to 11/11/2017
Sound Level Lmax, Lmin. dB(A)
Noise Standards for 55 dB( A) for Day Time and 45 dB( A) for Night Time (Residential Zone)
Lmax -52.0(Day),42.4 (Night)dB(A) Lmin – 44.1(Day),34.3 (Night)dB(A)
Lmax – 55.9 (Day), 43.9 (Night)dB(A) Lmin – 43.8 (Day), 36.1 (Night)dB(A) Leq – 47.2 (Day), 38.5 (Night)dB(A)
Values are well within permissible level
Air Quality (Near Construction Site)
10/11/2017 to 11/11/2017
SO2, NOX, CO , PM10 and PM2.5
NAAQS Standards
All monitored ambient air quality parameters are well within the stipulated limits of air quality.
Particulate Matter < 10 micron
100 µg/m3
56.20 ug/m3 Near Vikash Bhawan Distt. Almora
77.11 ug/m3 Near Vikash Bhawan Distt. Almora
Particulate Matter < 2.5 micron
60µg/m3
29.33 ug/m3
35.02 ug/m3
Sulphur dioxide, (So2) 80 µg/m3
7.22 ug/m3
09.89 ug/m3
Nitrogen dioxide (NO2) 80 µg/m3
16.43 ug/m3
19.77 ug/m3
Carbon Monoxide (CO) mg/m3
02 mg/m3 for 08 hrs 0.3 mg/m3 for 08 hrs
0.28 mg/m3 for 08 hrs
Air Quality (Near Back side of Almora fort)
10/11/2017 to 11/11/2017
SO2, NOX, CO , PM10 and PM2.5
NAAQS Standards All monitored ambient air quality parameters are well within the stipulated limits of air quality.
Particulate Matter < 10 micron
100 µg/m3
61.81 ug/m3 74.04ug/m3
Particulate Matter < 2.5 micron
60µg/m3
23.09ug/m3
33.29ug/m3
Sulphur dioxide,(So2) Nitrogen
80 µg/m3
6.50ug/m3
8.07ug/m3
dioxide(NO2) 80 µg/m3 19.22 ug/m3 18.97ug/m3
Carbon Monoxide (CO) mg/m3
02 mg/m3 for 08 hrs 0.38 mg/m3 for 08 hrs
0.32mg/m3 for 08 hrs
Water Quality Drinking water (Tap Water)
12/11/2017 to 15/11/2017
pH- CPCB Standards for Surface water bodies and Drinking Water Standards for Potable water
7.22 7.35 All parameters of drinking water are well within the limits of Drinking water specified in IS: 10500
Colour <5 <6
Turbidity –(NTU) BDL BDL
Odour – Agreeable Agreeable
Taste – Agreeable Agreeable
Total Hardness mg/L - 345.0 170.0
Calcium as Ca- 86.55 74.89
Alkalinity mg/l -268.00 156.09
Chloride- mg/l 70.40 13.89
79
Component Periods of monitoring
Parameters/ Pollutants Standard Base line status
Monitoring result during
project Implementatio
n
Remarks
Magnesium 28.62 15.98
Total Dissolved Solids mg/l
365.00 212.80
Iron as Fe mg/l 0.12 0.15
Copper as Cu mg/l <0.05 <0.06
Total Coliform 100 ml. at 37℃ (MPN)
<2/100ml <3/100ml
E-Coli / 100ml(MPN) Absent Absent
80
Institutional Arrangements
Program Management
22. The Government of Uttarakhand through Department of Tourism (DOT) is the Executing Agency
(EA). The EA (i) assumes overall responsibility for the execution of the Project and reporting; (ii)
engage adequate permanent or fixed-term staff to implement the Project; (iii) setup a state-level
project management unit (PMU) and project implementation units (PIU); (iv) provide overall strategic
guidance on technical supervision and project execution; and (v) ensure overall compliance with the
loan covenants.
23. The implementing agency (IA) is the Uttarakhand Tourism Development Board (UTDB). The IA’s
responsibilities include (i) project planning and budgeting; (ii) day-to-day assistance, supervision and
guidance for the project implementation units and their consultants; (iii) review subprojects for due
diligence requirements and approve subproject proposals; (iv) bidding, evaluation and contract
award; (v) managing and disbursing funds; (vi) review compliance with loan covenants, contract
specifications, work plans and quality control; and (vii) consolidate and submit progress reports,
finance and accounting / audit reports, and matters requiring higher level decision to state-level
empowered committee (SLEC) and ADB.
24. A State-level empowered committee (SLEC) has been established in Uttarakhand, chaired by state’s
Chief Secretary, with Principal Secretary/Secretary of the Department of Tourism as member
secretary and comprised of secretaries from relevant line departments. The SLEC have been
empowered to take all decisions on behalf of the State and will (i) act as a policy making body, (ii)
provide overall advice and guidance to the State’s executing agency and PMU, and (iii) accord all
approvals under the Project.
25. Dept. of Tourism (DoT) has established a PMU, headed by a full-time program director (PD), and
consisting of personnel drawn from relevant line departments and market. Project Management Unit
(PMU) is established in Dehradun for the overall project management. The PMU is the nodal agency
for overall management of all program activities and will be responsible for: (i) project planning and
budgeting; (ii) providing day-to-day assistance, supervision and guidance for the PIUs and their
consultants; (iii) reviewing subprojects to satisfy ADB’s due diligence requirements and approving
subproject proposals submitted by PIU and line departments; (iv) bidding, evaluation and contract
award; (v) managing and disbursing funds; (vi) reviewing compliance with loan covenants, contract
specifications, work plans and quality control; (vii) consolidating and submitting progress reports,
finance and accounting/audit reports, and matters requiring higher-level decision, to the SLEC and
ADB. The PMU will be supported by a team of consultants.
26. The sub-project is being implemented by the Project Implementation Unit (PIU) of IA, i.e. UTDB,
comprising of personnel drawn from relevant line departments and outside of government and
headed by a Project manager. 03 Project Implementation Units (PIU) have been established for each
of the three circuits namely Bhimtal, Dehradun and Kotdwar. The PIUs are responsible for: (i)
prioritizing and preparing subproject proposals; (ii) providing day-to-day assistance, supervision and
guidance to the design and supervision consultants; (iii) conducting detailed assessments and
surveys including public consultation and input from stakeholders; (iv) preparing detailed designs,
specifications, schedule of quantity, bidding documents, and related documentation; (v) implementing
civil works and related activities; (vi) reporting to PMU; (vii) preparing regular progress reports for the
SLEC, the executing agency and ADB through PMU; and (viii) supervising construction, conducting
quality control, approving progress payments to contractors; and (ix) maintaining records and
accounts on an up-to-date basis and making these available to ADB, its missions, or auditors for
inspection.
81
27. The Project Management Consultant (PMC) has been engaged to provide support to the PMU in
overall planning, risk management, implementation, monitoring and evaluation of projects under the
Investment Program. The PMC also assists the PMU and PIUs in meeting the relevant requirements
of ADB, Government of Uttarakhand, and Government of India for project implementation. The PMC
reports and works under the overall guidance of the PMU. The scope of services of the PMC includes
but not necessarily be limited to: (i) planning, reporting, and communication; (ii) establishment of
procedures and systems; (iii) review and preparation of plans, manuals and reports; (iv) overall
Investment Program management, monitoring and implementation of PPMS; and (v) social,
environmental, archaeological, occupational health and safety, community participation and gender
action compliance monitoring.
28. The Design and Supervision Consultants (DSC) have been engaged to provide all necessary support
to and coordination with the EA, IAs, PMU and any other consultants engaged by the authorities to
achieve the desired outcomes of the Investment Program. The DSC reports to and work under the
overall guidance of the PIUs. The scope of services of the DSC includes but not necessarily be
limited to: (i) surveys, verification of feasibility studies and base maps; (ii) project planning and
management support to the PIU; (iii) finalization of design criteria, preparation of manuals, guidelines
and systems; (iv) preparation of detailed design and bid documents; (v) construction management
and contract administration; (vi) environmental, social, archaeological, cultural heritage, community
participation and gender action compliance monitoring; and (vii) capacity building of the service
providers for operational sustainability.
10.1 Institutional Arrangements For EMP Implementation
29. The institutional arrangements specify the arrangements for the implementation of environmental
provisions of the entire project.
Project Management Unit (PMU)
30. A Safeguards Specialist (SGS) is positioned in the PMU, who is responsible for overall
implementation of the environmental safeguard provisions. To look into the matters of forest
coordination, a Forest Conservation Specialist is also placed in the PMU.
Project Management Consultant (PMC) and Design and Supervision Consultants (DSC)
31. Project Management Consultants (PMC) and Design and Supervision Consultants (DSC) have been
recruited to provide assistance to the PMU and PIUs respectively in project implementation. Within
the PMC team an Environment Safeguards Specialist is positioned to provide overall direction for
management of environmental issues, and technical support to the PMU including implementation of
the environmental requirements according to ADB requirements, and assist in monitoring impacts
and mitigation measures associated with sub-projects. Towards addressing the environmental issues
in the project components during design and implementation, the DSC includes provisions for inputs
of Safeguards Specialist Environment.
32. The Safeguards Specialist of the DSC team is responsible for preparation of the Environmental
Assessment documents in line with the Environment Assessment Review Framework (EARF) and
supervises the implementation of the EMP provisions in the various sub-projects.
33. DSC Safeguard Specialist is placed in each of the three DSCs to support environmental
management functions including updating sub-project IEEs in respect to environmental management
plans in compliance with the ADB Safeguard Policy Statement, national and state level
environmental policies, rules and regulations, assisting in preparing IEEs, and assist in monitoring
impacts and mitigation measures associated with sub-projects. He is required to include mitigation
measures in designs where appropriate, and to specify other measures in construction contracts. In
82
addition to addressing the issues related to environmental management in the project, the DSC
Specialist plays a central role in ensuring capability building on Environmental Management of the
PMU/PIU, Contractor and Line Departments.
34. Contractors are required by their contracts to implement all specified mitigation, monitoring, and
reporting assigned to contractors as presented in sub-project IEE. Contractors have appointed
Environment and Safety Officers for implementation of environment and occupational safety
provisions at site.
35. Environmental monitoring is being undertaken by the PMU supported by the Safeguards Specialist of
DSCs and PMC
36. Contact Details of Safeguards Team is given below:
Unit Name Mobilized Since Phone E-mail
PMU
Ms. Anjali Semwal
April, 2013 +91-8191995004
PMC Mr. Navin Handa
Mr. Ardhendu Mitra
July 2016 – Till Feb, 2017*
July 2013 – Sep, 2015
*Expert has been demobilized since Feb, 2017. PMC has been requested for replacement of Expert.
+91-9599510994
DSC Dehradun
Mr. Ranjan Mallick
Mr. Abhay Srivastava
January, 2014 – Till date
April, 2013 – June, 2013
+91-94382000113
DSC Kotdwar
Mr. Shreeniwas Verma
October, 2013 – Till date +91 9811224458
DSC Bhimtal
Dr. A.K. Sharma
Dr. Aman Sharma
July -2015 to Till Date
March -2013 to May 2015
+91-09799242184
10. Public Consultation Details
37. Meaningful Public Consultation has been done with the stakeholders and the Community, in all the
project areas. Details of Public Consultation held in the Reporting period are given in Table 10.
Consultation Records and Photographs are provided in Annexure 2.
83
Table 10(i): Public Consultation Meetings for Tranche III sub-projects Under PIU Dehradun
Date of Consultation
Sub Project Site
Participants Number of Participants
Summary of Consultation/Decision taken
12.08.2017 Rural
Tourism
(Near Chopta
Market)
Community
members
(DPs)
15 Meetings and individual interviews were held
with Tentative Displaced Persons( DPs) near
Main Entrance of Tungeshwar Temple to
brief them about the technical details of
project and project implementation cycle;
project benefits as well as adverse impacts
envisaged during construction. It was
informed to all that up gradation of road works
will be taken up after renovation works of
temple(Probably next year) and as per ADB
policy advance notice and compensation will
be issued to them through project
implementation unit.
No Grievances was received from them and
given their consent for all kind of support
during execution for smooth execution of
works.
12.09.2017 &
13.09.2017
Rural
Tourism
(Harsil &
Mukhba)
Villagers
/District
Administra
tion
officials
30 Project scope and its components.
Requirement of Renovation of Helipad etc.
Villagers have given their consent to provide
all kind of support. District administration
suggested that the renovation work of helipad
should be complete before Nov because there
is heavy snowfall after the month of
November
10.11.2017 &
11.11.2017
Rural
Tourism
(Harsil &
Mukhwa)
Villagers,
the site
engineer,
supervisor
, worker
28 Project scope and its components. Some
Labors are at site are using PPEs while some
are working without PPEs. Safety shoes are
provided only to few workers.
Villagers have given their consent to provide
all kind of support. Workers are not aware
about PPEs and wages. Frequent orientation
and training of labors should be done. Safety
engineer must be deployed at site.
12.11.2017
to
14.11.2017
Katrikeyaswa
mi Temple
kartikeyaswa
mi,
Durgadhar
and
Tungeswar
Villagers,
the site
engineer,
supervisor,
worker
35 Project scope and its components. Some
Labors are at site are using PPEs while some
are working without PPEs. Safety shoes are
provided only to few workers. Villagers have
given their consent to provide all kind of
support. Workers are not aware about PPEs
and wages. Frequent orientation and training
of labors should be done. Safety engineer
must be deployed at site.
84
Date of Consultation
Sub Project Site
Participants Number of Participants
Summary of Consultation/Decision taken
16.12.2017 Durga Dhar Villagers,
Temple
Committee.
22 Introduction to the project and how rural
tourism is fast becoming an alternative IGA in
the rural areas. Pradhan of Bora village
expressed her non ability to run the hardware
but was confident that if they were given a
chance and the trainings they would definitely
run the show and wanted the projects help in
the same.
The Village temple committee is keen to take
over provided they are provided with trainings
to run the facility.
17.12.2017 Phalasi Villagers,
Temple
Committee.
29 Introduction to O& M plan and realizing the
importance of loan component which has to
be returned to ADB. The committee also
informed that 14 members are in the
committee and that they have regular peon
with a monthly pay scale of Rs 2000 for
smooth functioning of the committee. Villagers
have given their consent to provide all kind of
support.
18.12.2017 &
19.12.2017
Kanakchauri Villagers
and
Committee.
17 Introduction to O& M plan and realizing the
importance of loan component which has to
be returned to ADB. Villagers informed that
construction of the Dharamsala should be
complete have their major festival.
Villagers have given their consent to provide
all kind of support.
20.12.2017 Kabiltha Villagers
and
Committee.
34 Project scope and its components was
discussed. It was informed that various
initiatives taken by the UTDB department
including the building of Guest house as well
as solar lighting for the development of this
village.Villagers informed that every year,
Kalidas festival held in the village where
hundreds of poets gather.and there is huge
potential for homestays in this village.
Villagers have given their consent to provide
all kind of support.
21.12.2017 Rudra
Prayag
DTDO 08 Project scope and components was
discussed. The DTDO suggested that the
Durgadhar facility could be made as an
adventure cum training center. DTDO was of
the opinion that once a good community
based tourism model is established it could
lead to a rippling effect establishing rural
85
Date of Consultation
Sub Project Site
Participants Number of Participants
Summary of Consultation/Decision taken
tourism in the Rudrapryag District.
DTDO assured for all kind of support for the
effective implementation of CBT activities in
Rudra Prayag district.
Table 10(ii): Public Consultation Meetings for Tranche III sub-projects Under PIU Kotdwar Date of
Consultation Sub Project
Site Participants Number of
Participants Summary of Consultation/Decision taken
14.07.2017 Development of Pedestrian route for Pilgrims in Haridwar
Kanwarias (Pilgrims) during Kanwar Mela
16 The kanwaris were happy to note that such facilities are being created for safe passage in Haridwar city as well as facilities for rest, drinking water and sanitation facilities are being created.
14.07.2017 and 15-07-2017
Development of Pedestrian route for Pilgrims in Haridwar
Contractor
and labour
28 Following issues were discussed in detail: (a)Workers safety during construction like wearing of head gear, safety shoes etc ( b ) importance of sanitation and public hygiene (c)Equal wages (d) The workers were sensitized for usage of PPEs.
18/09/2017 Development of Pedestrian route for Pilgrims in Haridwar
Contractor and labour
15 Discussed camp safety and health and hygiene issue and the contractor was advised to improve housekeeping at camp site. Make sanitation facilities operational and enforce use of PPEs.
19/09/2017 Development of Tourism Infrastructure in Sem Mukhem
Temple committee members and community
10 A detailed consultation was conducted with the manager of temple committee, regarding O&M of the facility. Committee members requested to expedite the works for Mela in November.
28/11/2018 Development of Tourism Infrastructure in Sem Mukhem
Local NGO & DSC
5 A consultation was conducted with the representatives of a local NGO called Sem Mukhem Paryatan Vikas Samiti (NGO representative1- Birender Shah Bhandari ; 2] Rajendra Prasad Bhadola and 3] Mr. Sandip Chandolia). The social expert explained that the project under implementation will actively promote Community Based Tourism (CBT) and tourism supply chain initiatives. The participating NGO representatives were satisfied with the facilities and infrastructures provided. They informed that t h e NGO would like to participate further enhance the tourism activities in this area
86
Table 10(iii): Public Consultation Meetings for Tranche III sub-projects Under PIU Bhimtal Date of
Consultation Sub Project Site Participants Number of
Participants Summary of Consultation/Decision taken
26/07/2017 Restoration and Adaptive Reuse of Almora Fort (Rani Mahal)
DSC, PIU, Contractor, Labourers & Community Members
30 Discussions there with the representatives of PIU, concerned contractor, labourers, community members of nearby village located adjacent to the site on different issues relating to adoption of social and environmental safeguards measures by the contractors and labourers. Also had discussions with the District and Session Judge on safety issues, who is having his office nearby the construction site.
27/07/2017 Restoration and Adaptive Reuse of Champawat Fort
(Banasur)
DSC, PIU Representative PIU Contractor Labourers Community Members
25 Discussions with the stakeholders including local masses, representatives of PIU and contractors including labourers on different issues relating to social and environmental safeguards measures being implemented in the social.
28/07/2017 Nainital Lake Precinct
Revitalization, Enhancement and
Urban Place Making
DSC, PIU Representative PIU Representative Contractor. Community Members
18 Discussions with the stakeholders regarding adoption of social and environmental safeguards measures by the contractor and other stakeholders for effective implementation of the project activities.
30/07/2017 Restoration and Adaptive Reuse of Pithoragarh Fort
DSC, PIU, Contractor, Labourers
22 Discussions with the Site Engineer of PIU and representatives of the concerned contractors including labourers working at the site.
10/11/2017 Restoration and Adaptive Reuse of Pithoragarh Fort
“Community Awareness
Programme”
DSC, PIU Representative & Community Members
35 Discussion on Present status of ADB assisted tourism sub-projects in Pithoragarh district, village tourism, home stay management, Operation & Maintenance of Pithoragarh Fort.
11. Implementation of Grievance Redress Mechanism
38. Grievance Redress Committees at PMU and PIU level have been formed. The arrangement for implementation of GRM is that the affected person/aggrieved party can give their grievance verbally or in written to the local grievances committee. Grievances of affected person will first be brought to the attention of the implementing NGO or PIU who can resolve the issue at site level. If the matter is not solved within 7 days period by the NGO or PIUs, it will be brought to the Grievance Redress Committee constituted for the purpose in PIU. This GRC shall discuss the issue in its monthly meeting and resolve the issues within one month of time after receiving the grievance. If the matter is not resolved by GRC at PIU level within stipulated time, it shall be referred to GRC at PMU level by Project Manager of PIU. GRC at PMU shall discuss the issue and try to resolve it and inform the PIU accordingly. If the matter is not resolved by the GRC at PMU level within one month of time, the aggrieved person/party can bring the matter to The Court of Law. The PIU shall keep records of all grievances received including contact details of complainant, date of receiving the complaint, nature of grievance, agreed corrective actions and the date these were affected and final outcome. A complaint register will be maintained at PIU as well as sites of the subproject.
39. No grievance was observed in any sub project during the reporting period.
87
12. Any other environmental aspects, impacts observed during implementation which were not
covered earlier
40. No such impact observed during the reporting period
13. Details of Complaints received from public and action taken thereof to resolve
41. No complaint received during the reporting period.
14. Follow up actions and Conclusions
42. Site supervision is being regularly carried out to ensure that environmental impacts are being adequately mitigated and to ensure continuation of compliance with statutory regulations as required by laws and agreed upon in EMP. The contractors are being regularly guided and instructed to pay attention to environmental issues and adhere to the provisions of EMP.
88
Annexure 1: Photo Illustration
Annexure: 1(i): Photo Illustration of Work Progress- DSC Dehradun UK/ IDIPT-III/DDN/01
Development of Tourism Infrastructure in Kartikeya Swami Circuit (Durgadhar&Tungeshwar)
Temple path at Durgadhar Kitchen Block, Durgadhar
UK/ IDIPT-III/DDN/02
Development of Tourism Infrastructure in Kartikeya Swami Circuit (Kartikeya Swami Temple)
Guest House under construction, Kartikeya Swami temple Pathway & Railing post at Kartikeya Swami
UK/ IDIPT-III/DDN/03
Conservation and Development of Rural Tourism Infrastructure in District Rudraprayag, Chamoli & Uttarkashi
Construction of Bhogsala, Mukhwa Entrance gate of Mukhwa
89
Path way, Harshil Helipad construction, Harshil
Pathway work of Bagori village
Annexure: 1(ii): Photo Illustration of Work Progress- PIU Kotdwar
UK/ IDIPT-III/KOT/01
Creation of Pedestrian Route for Pilgrims and Tourists in Haridwar Project Site
View of Integrated Multi Facility Center Under Construction At Haridwar
90
Pathway along right bank of Upper Ganga Canal near
Solani Park at Roorkee
Stacking of Tiles Haridwar Site
UK/ IDIPT-III/KOT/02
Development of Tourism Infrastructure in Sem-Mukhem (Tehri) Project Site
Care Taker Room Beside Temple under Progress at Mukhem Village
Rest Shed Under Construction at Mela Ground
View of Reservoir Deepening and Side Slope Protection at Mela Ground
91
Annexure: 1(iii): Photo Illustration of Work Progress- DSC Bhimtal UK/ IDIPT-III/BHT/05 Restoration and adaptive reuse of Champawat Fort (Banasur)
Entrance gate Bansaur Fort, Champawat
Banasur Fort Site at Banasur, Champawat
Tehsil Building Type II Building
UK/IDIPT/III/BHT/01 Conservation of Cultural Heritage and urban place making in Nainital Lot-1
St. Francis Catholic Church View of Gandhi Ashram, Takula
92
UK/IDIPT/III/BHT/03 Restoration and adaptive reuse of Almora Fort (Rani Mahal)
Caution Signages at construction site, Almora Almora (District Magistrate office building)
UK/IDIPT/III/BHT/07 Restoration and Adaptive Reuse of Pithoragarh Fort Phase II
Box erection at Multilevel Car Parking Flooring at Multilevel Car Parking
Annexure 2: Consultation Records & Photographs
Consultation Records PIU-Dehradun Projects
Consultation with affected persons near Mandir Marg, Chopta
Meeting with Temple Committee, Durgadhar Meeting with temple committee , Phalasi
Meeting with Villagers, Kanakchauri Consultation with villagers Bora
94
Meeting with DTDO, Rudraprayag
Safeguard Awareness training to workers, Tungeshwar
Safeguard Awareness training to workers, Harshil
95
Consultation Records PIU Dehradun Projects
Consultation- Kartikeya Swami Temple Meeting -18/12/17
96
Consultation Records PIU Kotdwar Projects Consultation- Kanvashram -Attendance Sheet and
Photographs-14/07/17
Consultation- Kanvashram -Attendance Sheet and
Photographs-18/09/2017
98
Medical Aid Provided to Kanwarias by the Project Construction Team During Kanwar Mela
Creation of Pedestrian Route for Pilgrims and Tourist in Haridwar - Consultation
Consultation and safeguards orientation with Labour at Sem Mukhem
Consultations with the local NGO Representatives-Sem Mukhem
Consultation Records PIU
Community Awareness Program at Pi
CDO, Pithoragarh addressing the Participants
Consultation Records PIU Bhimtal Projects
at Pithoragarh DM, Pithoragarh addressing the inaugural session
Pithoragarh addressing the Participants Participants in the Community Awareness Programme
Pithoragarh addressing the inaugural session
Participants in the Community Awareness Programme