HMA TEST USER GUIDE (FIELD) - KDOT

27
HMA TEST USER GUIDE (FIELD) 1 Updated 03/22

Transcript of HMA TEST USER GUIDE (FIELD) - KDOT

HMA TESTUSER GUIDE (FIELD)

1 Updated 03/22

 

2 Updated 03/22

slade
Callout
Verify Role.
slade
Line

 

3 Updated 03/22

slade
Callout
Click "Sample Records"

 

4 Updated 03/22

slade
Callout
1. Click the component action button.
slade
Callout
2. Click "Add".

 

 

5 Updated 03/22

slade
Callout
1. Enter the date the material was sampled.
slade
Callout
2. Enter the material code for the material being sampled. NOTE: Material Code must exist on the contract you are assigning the material test to.
slade
Callout
3. Select "ACC" from the drop down.
slade
Callout
4. Select "ACCP-KDOT Tests And/Or Field Inspection" from the drop down.
slade
Callout
5. Enter the quantity represented by the test.
slade
Callout
6. Enter the unit of measure for the material being tested.
slade
Callout
7. Click "Save".
slade
Callout
8. Click "Sample Location".

 

 

6 Updated 03/22

slade
Callout
1. Enter where the sample was taken. EXAMPLE: Mainline.
slade
Callout
2. Click "Save".
slade
Text Box
The rest of the information on this tab is OPTIONAL.
slade
Callout
3. Click "Additional Information".

 

7 Updated 03/22

slade
Callout
1. Enter the name of the sampler.
slade
Callout
2. Select "HMA Surface and Base Mixture-HMA Surf & Base" from the drop down.
slade
Callout
3. Enter the Mix Design number for the mixture being tested.
slade
Callout
4. Click "Save".
slade
Callout
5. Click "Sources".

 

8 Updated 03/22

slade
Callout
Click "Select Primary Source".

 

9 Updated 03/22

slade
Callout
Either enter the source name or click "Show first 10".
slade
Line

 

10 Updated 03/22

slade
Callout
1. Select the source from the list.
slade
Callout
2. Click "Add to Sample Record".

 

11 Updated 03/22

slade
Callout
1. Click "Save".
slade
Callout
2. Click "Associations".

 

12 Updated 03/22

slade
Callout
Click "New".

 

13 Updated 03/22

slade
Callout
1. Select "Destination Lab" from the drop down.
slade
Callout
2. Enter your lab.
slade
Callout
3. Click "Save".
slade
Callout
4. Click "Contract".

 

14 Updated 03/22

slade
Callout
Click "Select Contract Project Items".

 

15 Updated 03/22

slade
Callout
Either enter the contract number or Click "Show first 10".
slade
Line

 

16 Updated 03/22

slade
Callout
1. Click the line item(s) that to assign the test to.
slade
Callout
2. Click "Save".

 

17 Updated 03/22

slade
Callout
1. Enter the quantity to be assigned to the line item.
slade
Callout
2. Click "Save".
slade
Callout
3. Click "Tests".

 

18 Updated 03/22

slade
Callout
1. Click the action button next to "Assign Tests".
slade
Callout
2. Click "Assign Default Tests".

 

19 Updated 03/22

slade
Callout
1. Click the row action button.
slade
Callout
2. Click "HMA Superpave v2".

 

 

20 Updated 03/22

slade
Text Box
Pages 20-26 are the same screen.
slade
Callout
1. Enter information from the Mix Design Submittal.
slade
Line
slade
Line
slade
Line
slade
Line
slade
Line
slade
Callout
2. Enter percentages for each component in the mix.
slade
Line
slade
Line
slade
Line
slade
Line
slade
Line
slade
Line
slade
Line

  

21 Updated 03/22

slade
Text Box
Pages 20-26 are the same screen.
slade
Callout
3. Enter data from the KT-39 test.
slade
Line
slade
Line
slade
Line
slade
Line
slade
Line
slade
Line
slade
Line
slade
Line
slade
Line
slade
Line
slade
Line

 

 

22 Updated 03/22

slade
Text Box
Pages 20-26 are the same screen.
slade
Callout
4. Enter data from the KT-58 test.
slade
Line
slade
Line
slade
Line
slade
Line
slade
Line
slade
Line
slade
Line
slade
Line
slade
Line
slade
Line
slade
Line
slade
Line
slade
Line

 

23 Updated 03/22

slade
Text Box
Pages 20-26 are the same screen.
slade
Callout
5. Enter data from the KT-57 test.
slade
Line
slade
Line
slade
Line
slade
Line
slade
Line
slade
Line

 

 

24 Updated 03/22

slade
Text Box
Pages 20-26 are the same screen.
slade
Callout
6. Enter your Sieve Analysis information.
slade
Line
slade
Line
slade
Line
slade
Line
slade
Line
slade
Line
slade
Line
slade
Line
slade
Line
slade
Line
slade
Line
slade
Line
slade
Line
slade
Line

25 Updated 03/22

slade
Text Box
Pages 20-26 are the same screen.
slade
Callout
7. Enter the Specific Gravity of the Virgin AC.
slade
Callout
8. Click the up arrow to return to the top of the page.

  

26 Updated 03/22

slade
Text Box
Pages 20-26 are the same screen.
slade
Callout
9. Click "Save".
slade
Callout
10. Click "Sample Record Test".

 

 

27 Updated 03/22

slade
Callout
1. Select the appropriate Test Result from the drop down. Options are Pass, Fail, PAAA or COMP.