Factors that lead to the cost overrun in construction process
Transcript of Factors that lead to the cost overrun in construction process
BUILDING SURVEY(AP 229 D3)
[FACTORS LEAD TO THE COST OVERRUN IN CONSTRUCTION PROCESS]
RESEARCH PROPOSAL:FACTOR THAT LEAD TO THE COST OVERRUN
IN CONSTRUCTION PROCESS.
Abstract
Based on this research proposal, the purpose of this research
proposal is to determine the factors that lead to the cost
overrun in the construction project, in this proposal also have
been stated the objective of this study it is to identify the
financial management department for this project, to explore the
way they manage for financial in the construction process and to
identify cost constrain that arise. With the objective there have
been several research question that been stated in this research
question that show what the need to do to determine the factors
of cost overrun. Besides ,in this proposal there also have
literature review that show the overall of about this research,
such as construction cost is a responsibility of owner to provide
a cost for the construction project to the contractor do his job
and pay for construction needed. In this literature review also
have been stated about the cost estimation, financial department
consultant and about what is cost overrun. Furthermore, in this
proposal also been stated about the methodology of research
process ,it is from determine the research topics until the
FUNDAMENTAL RESEARCH METHODOLOGY (BSS 518) Page 1
BUILDING SURVEY(AP 229 D3)
[FACTORS LEAD TO THE COST OVERRUN IN CONSTRUCTION PROCESS]
method that want to be used, the method that being used is by
using primary data that research based on the respondent
interview and secondary data that research based on the
books ,journal ,article and conference paper. Besides ,in this
proposal also there have several factors that lead to the cost
overrun that been recorded in the preliminary data ,it is Lack
of project management supervision, Poor estimation and inaccurate
estimation of original cost, Fluctuation price of material for
construction site ,and Problems from the owners and owner’s will.
In a nutshell, problem of cost overrun in construction project
not a small issue it is can lead to the serious issue if it is
not being solved.
Introduction
Nowadays there have a lot of construction process that happen in
our country, with the increasing of the construction activities
in our country, it is also lead to the increasing to the problem
in the cost management or cost control. Every construction
process that have been carried out there have some of the issue
or problem that arise in the cost management in the construction
process, especially issue of cost overrun on the construction
FUNDAMENTAL RESEARCH METHODOLOGY (BSS 518) Page 2
BUILDING SURVEY(AP 229 D3)
[FACTORS LEAD TO THE COST OVERRUN IN CONSTRUCTION PROCESS]
process. According to Mohamed, (2011) project cost management can
be define as a process to determine the time required at each of
the activities of the project ,the resources should be allocated
to the execution of the activity by the individuals ,materials
and equipment.As we know, cost is the budget or money that we
used to construct a building, without money or budget there have
no building that can be construct. So ,it is important to have a
cost management, to make sure the smoothly of construction
process.
Statement of problem
Factor that lead to the cost overrun in the construction process.
1.Literature review
What is construction cost?
According to the Mc. Grawhill,(1998) also said construction cost
can be define as a construction portions, it is based on the upon
the sum of the construction contract and other direct
construction costs ,but it is not included for land, right of way
,professional services and other costs, it is been classified as
the responsibility of owner to provide the cost for the
construction as one of the outlined in the construction
FUNDAMENTAL RESEARCH METHODOLOGY (BSS 518) Page 3
BUILDING SURVEY(AP 229 D3)
[FACTORS LEAD TO THE COST OVERRUN IN CONSTRUCTION PROCESS]
contract.it is also a cost for contractor for all the
construction cost such as pay for the workers.
Cost estimation
According to PMBOK,(n.d) cost estimation is the iterative process
of developing an approximation of the monetary resources needed
to complete project activities. Project teams should estimate
costs for all resources that will be charged to the project. This
includes but is not limited to the Labor, Material,
Equipment ,Services, Software ,Hardware, Facilities and
Contingency Costs.
Financial department consultant
Financial department consultant it is a companies or individuals
that will plan for the financing for the owners .Financing
department also will check all the expenditure of money for the
construction project to make sure all the construction that have
been done is follow with the contract and to make sure the
expenditure of cost for construction do not exceed from the
initial cost that have been estimate.
Cost overrun.
According to the Serdar et.al ,(2012) Cost overrun can be defined
as when the project objectives have not been achieved within
estimated budget.
FUNDAMENTAL RESEARCH METHODOLOGY (BSS 518) Page 4
BUILDING SURVEY(AP 229 D3)
[FACTORS LEAD TO THE COST OVERRUN IN CONSTRUCTION PROCESS]
According to Kamaruzzaman,(2010) also Cost overrun is when the
final cost or expenditure of the project exceeds the original
estimation cost.
KEYWORD: Project Management Body of Knowledge
Preliminary data : Factor that lead to the cost overrun in
construction process.
1. Lack of project management supervision
Project manager is the person that responsible to monitoring
the all the construction site activities (Mohamed ,2011).As a
project manager also is the person responsible to make sure the
construction process do as have been plan especially on the cost
budget. Due to the lack of project management in the construction
process will lead to the cost overrun and cause the budget that
have been planned not going smoothly.
FUNDAMENTAL RESEARCH METHODOLOGY (BSS 518) Page 5
BUILDING SURVEY(AP 229 D3)
[FACTORS LEAD TO THE COST OVERRUN IN CONSTRUCTION PROCESS]
Name and date Said
Kamaruzzaman ,2010
Lack of monitoring and
management of site and lack of
project management assistance
can lead to the cost overrun in
the construction process. The
skillful and experience do not
enough in managing a site,
because lack of poor
construction management show
the weakness of contractors in
manage the construction site.
Frederick & Nancy ,2009
Due to the lack of project
monitoring of project manager
especially when there have
changes on the scope of work
and that also lead to the
changes of budget, but the
project manager did not involve
to monitoring it can cause to
the cost overrun in the project
cost.
FUNDAMENTAL RESEARCH METHODOLOGY (BSS 518) Page 6
BUILDING SURVEY(AP 229 D3)
[FACTORS LEAD TO THE COST OVERRUN IN CONSTRUCTION PROCESS]
without monitoring and supervision from the project manager on
the construction site, the construction process will not going
smoothly and lead to the cost overrun, that cost is increase form
the cost that have been planned and estimate
2. Poor estimation and inaccurate estimation of original cost
Every project must be estimate the cost and budget before start
the construction process to avoid form the cost overrun or over
budget when construction process started. Poor estimation and
inaccurate of construction budget will lead to the overrun of
cost for construction process. Estimation is an appraisal,
opinion, or an approximation as to the cost of a project prior to
its actual construction.(Frederick,2012).
Name and date SaidKamaruzzaman,2010 Have stated that due to the
technical problem such as do
not have experience to estimate
the project cost and due to the
lack of project information to
estimate lead to the cost
inaccurate estimation on the
initial cost is the biggest
FUNDAMENTAL RESEARCH METHODOLOGY (BSS 518) Page 7
BUILDING SURVEY(AP 229 D3)
[FACTORS LEAD TO THE COST OVERRUN IN CONSTRUCTION PROCESS]
factor that have led to the
cost overrun for construction
process.
Frederick, 2009
The estimation of material cost
, labour , equipment cost and
overhead very important, the
wrong estimation can led to the
serious cost overrun in the
construction project.
Every estimation that have been made will be changed during
construction process, because estimating for the project cost it
is only the initial cost and can be changed, but with the wrong
estimating for the cost construction project can lead to the cost
overrun when construction process .
3. Fluctuation price of material for construction site.
Material is very important element that used in the
construction process, without material there have no
construction would be proceed. Material price will always
fluctuation with the economy in Malaysia ,due to the
fluctuation of material price it is will affect the cost for
the construction project
FUNDAMENTAL RESEARCH METHODOLOGY (BSS 518) Page 8
BUILDING SURVEY(AP 229 D3)
[FACTORS LEAD TO THE COST OVERRUN IN CONSTRUCTION PROCESS]
Name and date Said
FUNDAMENTAL RESEARCH METHODOLOGY (BSS 518) Page 9
BUILDING SURVEY(AP 229 D3)
[FACTORS LEAD TO THE COST OVERRUN IN CONSTRUCTION PROCESS]
Kamaruzzaman ,2010Due to the high of inflation
and suppliers speculation, it
is hard to estimate the cost
for the construction material
due to the fluctuation of
price from the suppliers that
can lead to the overrun of
construction cost that have
been estimate on the initial
stage.
Mohamed ,2011
The increase of material that
lead to the cost overrun is
maybe due to the material that
been imported from abroad have
an increment in the foreign
exchange rate .Besides it is
also due to the changes of
material that being used in
the construction site with the
drawing that have been
provided, and the material
that have been used more
expensive that affect the cost
FUNDAMENTAL RESEARCH METHODOLOGY (BSS 518) Page 10
BUILDING SURVEY(AP 229 D3)
[FACTORS LEAD TO THE COST OVERRUN IN CONSTRUCTION PROCESS]
that have been spend for the
construction project.
The fluctuation of materials price cannot being control because
it is objective, the changes of price is due to the types of
material and economy condition. Fluctuation price is the most
factors that lead to the cost overrun in the construction process
that cannot be avoid.
4. Problems from the owners and owner’s will.
According Frederick and Nancy ,(2003) owners can be define as
the individual that seeking for a home for their growing
family ,a large organization responding to a change in technology
,a municipality seeking to improve infrastructure, or a developer
working to make money by filling a perceived marked need. Owners
very important to construct a project because the owner is where
the project of construction born. Owner also is a source and
backup for the financial and budget for the construction process.
Without a owner there no project, during the construction process
the owner will give the cost for the construction process and the
owner will decide the design of building that they want. Because
of owners will and cannot give the budget or delay for payment
can affect to the construction process especially on the cost
that lead to the cost overrun.
FUNDAMENTAL RESEARCH METHODOLOGY (BSS 518) Page 11
BUILDING SURVEY(AP 229 D3)
[FACTORS LEAD TO THE COST OVERRUN IN CONSTRUCTION PROCESS]
Name and date Said
Kamaruzzaman,2010
Mohamed ,2011
Frederick & Nancy ,2003
Due to the owner’s need the
mistake of design
occur ,because unrealistic
design only can be occur when
the construction process is
started and it is lead to the
cost overrun because
construction project need to
changed it.
Kamaruzzaman,2010
Jimmie ,2004
Williams ,2010
The owner cannot prepare for
the sufficient cost for the
construction project cost and
sometimes some owner cannot pay
on time based on the agreement
to the contractor ,and cause
the delay of project and lead
to the cost overrun in
construction process.
FUNDAMENTAL RESEARCH METHODOLOGY (BSS 518) Page 12
BUILDING SURVEY(AP 229 D3)
[FACTORS LEAD TO THE COST OVERRUN IN CONSTRUCTION PROCESS]
Due to the owner’s needed and owner’s cannot provide for the cost
payment to the contractor can lead to the cost overrun in the
construction project.
After the preliminary collecting the data, the data analysis must
be proceed, analyze the data whether it is relevant with the
research topics or not, and analyze the all the information to
make sure the all the questionnaire and the objective of the
research topics have been collect.
Aim
The purpose this research is to determine the factors that lead
to the cost overrun in construction process.
Objective of the study
1. To identify the financial management department for the
project
2. To explore the way they manage for financial in the
construction process.
3. To identify cost constrain that arise.
Research question
i) Who is responsible to manage the financial for the
project?
ii) How they manage the cost for construction process?
FUNDAMENTAL RESEARCH METHODOLOGY (BSS 518) Page 13
BUILDING SURVEY(AP 229 D3)
[FACTORS LEAD TO THE COST OVERRUN IN CONSTRUCTION PROCESS]
What the cost constrain that arise in the construction
process?
iii) Why the financial problem happen?
iv) How the solved the financial problem that arise?
Limitation of research
1.The limitation that will happen is, the data of estimation for
initial cost and cost that have been spend will be hard to get
from financial department.
2.The interview process will be limit, because some data is
private especially on cost data.
Statement of significance
This research proposal topics very important to be explore,
because cost overrun always been occur during construction
project, with this research it can help and guide to manage the
construction cost with proper management and can avoid the cost
overrun from happen again.
Methodology
FUNDAMENTAL RESEARCH METHODOLOGY (BSS 518) Page 14
Determine the topic for
Identify the aim, objective , and problemstatement ,significance of study ,and limitation for the
BUILDING SURVEY(AP 229 D3)
[FACTORS LEAD TO THE COST OVERRUN IN CONSTRUCTION PROCESS]
For this task I must determine my research topic,and finding my
aim,objectives and problem statement for this topic.For theFUNDAMENTAL RESEARCH METHODOLOGY (BSS 518) Page 15
Collecting data for researchtopic
Primary data: qualitative
1.Respondent Interview: quantity survey consultant and project manager
2. questionnaire
Secondary data
1. Journal2. Conference
paper3. Books
Data analysis
Recommendation
conclusion
BUILDING SURVEY(AP 229 D3)
[FACTORS LEAD TO THE COST OVERRUN IN CONSTRUCTION PROCESS]
collection of data I will used primary and secondary data,primary
data is the data that get fom the interview the respondent and
based on the questionare that called ad qualitative.qualitative
is a data normally appeared in the form of text and explanation
from the respodent.Secondary data is the data that I get based on
the journal,conference paper,books and online website.All the
data will be collected and be analyze and called as data
analysis.After the analyze process the reccommendation should be
stated to solved the problem that arise.
FUNDAMENTAL RESEARCH METHODOLOGY (BSS 518) Page 16
BUILDING SURVEY(AP 229 D3)
[FACTORS LEAD TO THE COST OVERRUN IN CONSTRUCTION PROCESS]
Research outline
1.Introduction
Stated about the condition of construction site nowadays that
cost overrun occur most of the site, and it is brief why this
topic being choose and carried out.
2.Statement of problem
In this chapter ,it is brief about the literature review of this
topic and brief about the preliminary data that have been search.
3.Aim and objectives
Stated about the purpose for this topics being carried out and
the objective to this topics is to achieve the topic requirement.
4. limitation of study
It is brief about the limitation for research being carried out,
and some of data cannot be provided.
5 .Methodology
FUNDAMENTAL RESEARCH METHODOLOGY (BSS 518) Page 17
BUILDING SURVEY(AP 229 D3)
[FACTORS LEAD TO THE COST OVERRUN IN CONSTRUCTION PROCESS]
Brief about the method that being used to carried out this
research topic for collection of data, in this proposal it is
used secondary and primary data for the method.
6. Data analysis
All the data that have been collected will be analyze and
recorded.
7. Problem and recommendation
It is brief about the problem that occurs during the research
being carried out and recommendation is the suggestion to solve
all the problem that occur.
8. Conclusion
Stated about the summary of all about the research topic that
have been carried.
Conclusion
Cost overrun have become more serious issue in construction
process, every construction project will be cost overrun occurs
due to the owners’ will, fluctuation material price ,lack of
supervision and poor estimation of construction cost, without t
a proper planning and proper co-operate between project manager
and owners the problem of cost overrun in construction project
cannot being solved. The owner’s should use the financial
consultant to avoid from cost overrun happen in the construction
FUNDAMENTAL RESEARCH METHODOLOGY (BSS 518) Page 18
BUILDING SURVEY(AP 229 D3)
[FACTORS LEAD TO THE COST OVERRUN IN CONSTRUCTION PROCESS]
project to make sure budget that have been provide is enough for
construction process and not exceed from the initial estimate.
References
FUNDAMENTAL RESEARCH METHODOLOGY (BSS 518) Page 19
BUILDING SURVEY(AP 229 D3)
[FACTORS LEAD TO THE COST OVERRUN IN CONSTRUCTION PROCESS]
Book :
1. Trefor williams,2010,Construction Management-Emerging Trends
and Technologies, United States, America.
2. Frederick E.Gould,2012,Managing the Construction
Process ,New Jersey.
3. Frederick Gould & Nancy Joyce,2009,Construction Project
Management -3rd Edition, Pearson Education, New Jersey.
4. Frederick Gould & Nancy Joyce,2003,Construction Project
Management -2nd Edition, Pearson Education, New Jersey.
5. Jimmie W.Hinze,2004,Construction Planning And Scheduling-2nd
Edition, Pearson Education ,New Jersey.
6. Mohamed A.El-Reedy,2011,Construction Management of
Industrial Project ,Scrivener Publishing , New Jersey.
Online Journal :
1. S.N.Kamaruzzaman,2010,Cost Performance for Building
Construction Projects In Klang
Vallley,http://pkukmweb.ukm.my/jsb/jbp/index.html. Retrieved
on : 7 December 2014.
2. Serdar Durdyev ,Syuhaida Ismail and Nooh Abu Bakar,2012,
Factors Causing Cost Overruns in Construction of
Residential Projects.
https://www.academia.edu/2012994/FACTORS_CAUSING_COST_OVERRU
NS_IN_CONSTRUCTION_OF_RESIDENTIAL_PROJECTS_CASE_STUDY_OF_TUR
KEY.
FUNDAMENTAL RESEARCH METHODOLOGY (BSS 518) Page 20
BUILDING SURVEY(AP 229 D3)
[FACTORS LEAD TO THE COST OVERRUN IN CONSTRUCTION PROCESS]
Retrieved on : 23 December 2014.
Website:
1. http://thelawdictionary.org/construction-cost/, The Law
Dictionary, Retrieved on : 22 December 2014
Online Article
1. http://encyclopedia2.thefreedictionary.com/
Construction+cost, Construction Cost, Retrieved on: 22
December 2014
2. http://doit.maryland.gov/SDLC/Documents/Cost_Estimating.pdf,
Cost Estimating, Retrieved on : 22 December 2014