Steps to Manually Install Client Offline application - Punjab ...
EPRI's Program to Develop, Install and Test the Alden Fish ...
-
Upload
khangminh22 -
Category
Documents
-
view
2 -
download
0
Transcript of EPRI's Program to Develop, Install and Test the Alden Fish ...
University of Massachusetts AmherstScholarWorks@UMass AmherstInternational Conference on Engineering andEcohydrology for Fish Passage
International Conference on Engineering andEcohydrology for Fish Passage 2012
Jun 6th, 10:30 AM - 10:50 AM
Session D4 - EPRI's Program to Develop, Installand Test the Alden Fish-Friendly HydropowerTurbineDouglas DixonAlden Research Laboratory, Inc.
Follow this and additional works at: https://scholarworks.umass.edu/fishpassage_conference
This Event is brought to you for free and open access by the Fish Passage Community at UMass Amherst at ScholarWorks@UMass Amherst. It hasbeen accepted for inclusion in International Conference on Engineering and Ecohydrology for Fish Passage by an authorized administrator ofScholarWorks@UMass Amherst. For more information, please contact [email protected].
Dixon, Douglas, "Session D4 - EPRI's Program to Develop, Install and Test the Alden Fish-Friendly Hydropower Turbine" (2012).International Conference on Engineering and Ecohydrology for Fish Passage. 6.https://scholarworks.umass.edu/fishpassage_conference/2012/June6/6
Re-inventing the Wheel: The Continuing Story of the Alden Turbine Development
Douglas A. Dixon
National Conference on Engineering and Ecohydrology for Fish Passage
June 5-7, 2012
2 © 2011 Electric Power Research Institute, Inc. All rights reserved.
Presentation Topics
• Brief history
• Key turbine features
• Current status
• Hydro potential
• Planned but canceled demonstration projects – alternative plan
• Features of ideal demonstration site
3 © 2011 Electric Power Research Institute, Inc. All rights reserved.
Alden Turbine Status Summary
• EPRI, DOE & Industry funding of $2.6 million:
– Buildable turbine design from collaborative completed
– Model test indicates favorable turbine performance
• Ready for purchase, deployment and field demonstration
• Seeking field site for 2013~15 Demonstration Program
4 © 2011 Electric Power Research Institute, Inc. All rights reserved.
Brief History of the Alden Turbine
• 1995 EPRI-Industry-DOE Advanced turbine program
• Two turbine designs emerged: Minimum gap runner (MGR) and the Alden Turbine
– MGR installed & tested (limited) in Pacific NW
– Alden turbine only tested at pilot scale
• DOE Program canceled 2005
• EPRI took over Alden turbine’s continued development
5 © 2011 Electric Power Research Institute, Inc. All rights reserved.
“Fish Friendly” Turbine Development: Alden Design - What’s Different?
Conventional Francis Turbine Alden Turbine
6 © 2011 Electric Power Research Institute, Inc. All rights reserved.
What Makes it Fish-Friendly?
• Large diameter
• Slow rotational speed
• Few blades (3)
• No gaps
• Thick leading edges on blades
• Thick leading edges on vanes and gates
• Biological design criteria – eliminated damaging shear and pressure
Fish Length=250 mm; Blade thickness=10 mm; Velocity=7.3 m/s
Fish Length=150 mm; Blade thickness=150 mm; Velocity=7.3 m/s
7 © 2011 Electric Power Research Institute, Inc. All rights reserved.
>42,000 fish tested
Alden Turbine Pilot Scale Test Loop
8 © 2011 Electric Power Research Institute, Inc. All rights reserved.
UNITS 1-3 2.01.51.00.50.0
VELOCITY (FT/S)
FLOWSEPARATION
FLOW SEPARATION
PREDICTED FULL-SCALE
SURVIVAL
97 – 100 % (based on pilot scale survival data)
Predicted Fish Survival
9 © 2011 Electric Power Research Institute, Inc. All rights reserved.
Alden Turbine – Comparison with Conventional
Turbines: Fish Survivability
Alden
Turbine
Conventional
Francis
Conventional
MGR Kaplan
Power, [MW] 13.6 13.6 13.6
Survival rate for an 8”
fish
(considering strike)
98% < 50% 86%
10 © 2011 Electric Power Research Institute, Inc. All rights reserved.
EPRI-DOE Advanced Turbine Research: Conceptual to Engineering Design
$1.2 million DOE
$1.4 million EPRI & industry
•Spring 2010: Design Engineering
•Summer-Fall 2010: Constructed and tested a physical model: 94% efficient and wide operating range at peak performance
•September 2011 final design, cost & supply schedule
+ 8 Industry Co-sponsors
Ready for Purchase, Deployment
and Field Testing
11 © 2011 Electric Power Research Institute, Inc. All rights reserved.
Turbine Prototype Performance
Mechanical design review
indicates it is readily
implementable for a range of
applications
Performance exceeded
expectations
Thrust, runaway speed, and
pressure pulsations were within
anticipated ranges
No cavitation for the operating
conditions corresponding to
design point
0.80
0.84
0.88
0.92
0.96
1.00
0.2 0.5 0.8 1.1 1.4 1.7
Alden Turbine
Conventional Francis
Conventional MGR Kaplan
Normalized Efficiency
Normalized Power
12 © 2011 Electric Power Research Institute, Inc. All rights reserved.
Relative Prototype Costs
Alden Turbine
Conventional
Francis
Conventional
Kaplan
Diameter (mm) 3900 2510 2650
Power (MW) 11 11 11
Turbine 1 0.5 0.55
Generator 0.8 0.65 0.65
Installation and Comm. 0.25 0.25 0.25
Automation/ BoP 0.25 0.25 0.25
Relative Costs 2.3 1.65 1.7
Premium for Alden 39% 35%
SIZING
COSTINGBut……..
13 © 2011 Electric Power Research Institute, Inc. All rights reserved.
Relative Costs (continued)
Offsetting benefits
• Less powerhouse excavation (higher turbine setting)
• Generating with bypass flow (previously wasted/spilled)
• Avoid O&M and capital costs for downstream fish bypass systems
True costs comparison of project components may be less for a Alden unit than conventional Francis or Kaplan units
ALDEN < Conv. Turbine + Fish Bypass + Lost Energy
True Cost Comparison
14 © 2011 Electric Power Research Institute, Inc. All rights reserved.
EPRI-DOE Design & Model Performance Report
EPRI Report
1019890,
September 2011
Download at
www.epri.com
15 © 2011 Electric Power Research Institute, Inc. All rights reserved.
Info on All Enhanced Turbines
Technical Papers from
EPRI-DOE-BOR-COE-
NHA 2011 Conference
Report 1024609
16 © 2011 Electric Power Research Institute, Inc. All rights reserved.
Where Can This Turbine Be Used?
• New development
• Added capacity at existing dams
• Powering non-powered dams
• Minimum flow releases and other bypass systems
• Not planned as modernization turbine; but
– Unit replacement or upgrade (10-60 m3/s; 10~40 m head)
17 © 2011 Electric Power Research Institute, Inc. All rights reserved.
Worldwide Installed Hydro Capacity (EIA)
25-30 GW Hydro Installed in 2011
18 © 2011 Electric Power Research Institute, Inc. All rights reserved.
Hydro Worldwide Growth Predictions (EIA)
19 © 2011 Electric Power Research Institute, Inc. All rights reserved.
U.S. CO2 Reductions … Technical Potential (EPRI PRISM Analysis)
0
500
1000
1500
2000
2500
3000
3500
1990 1995 2000 2005 2010 2015 2020 2025 2030
U.S
. E
lectr
ic S
ecto
r C
O2 E
mis
sio
ns
(mill
ion
me
tric
to
ns)
*Achieving all targets is very aggressive, but potentially feasible.
EIA Base Case 2009
41% reduction in 2030 from 2005 level is technically
feasible using a full portfolio of technologies
Efficiency
Renewables
Nuclear
Coal, CCS
PEV
Electro-Technologies
Hydro
20 © 2011 Electric Power Research Institute, Inc. All rights reserved.
Why Demonstration?
Many to convince that this new technology is viable:
• Resource agencies
• NGOs (environmental groups)
• Industry (need better handle on cost & performance economics)
NEED Demos to reduce uncertainties in performance and cost and we need collaborative support to continue!
21 © 2011 Electric Power Research Institute, Inc. All rights reserved.
U.S. Demo
• April 2011 U.S. DOE FOA for Advanced Hydro Technologies
• September 2011 U.S. DOE Announcement:
– EPRI Awarded $1.5 million to Support Brookfield Demonstration Project
– $1.5 million cash match requirement
• EPRI has requested DOE approval for finding a new demo site
Potential new demo sites:
• Federal facility (Reclamation, Corps)
• FERC exempt site
• FERC site (private operator)
22 © 2011 Electric Power Research Institute, Inc. All rights reserved.
Preferred/Ideal Features of a Test Site
• Head = 75’ to 100’
• Flow = 1,000 cfs to 1,800 cfs
• Fish Species – juvenile anadromous salmon and/or herring, juvenile landlocked salmon, rainbow trout, juvenile sturgeon, adult catadromous eels
23 © 2011 Electric Power Research Institute, Inc. All rights reserved.
Revised Proposed Project Schedule
Schedule:
• 2013: adapt turbine engineering design to site, preliminary installation design, turbine manufacture and delivery
• ~2014: Installation
• ~2015-16: Performance testing
25 © 2011 Electric Power Research Institute, Inc. All rights reserved.
SUMMARY
EPRI preparing to move this turbine to its next step:
• Get it in the water, get it tested, get results
• EPRI recognizes risks and is prepared to help minimize them
• Continued industry & public support needed to make it happen!
26 © 2011 Electric Power Research Institute, Inc. All rights reserved.
Thank You DOE, Funding Partners and R&D Team!
27 © 2011 Electric Power Research Institute, Inc. All rights reserved.
Together…Shaping the Future of Electricity
EPRI, DOE and the Hydropower Industry
THANK YOU! Doug Dixon, [email protected];
804-642-1025 Virginia USA Office