ENVIRONMENTAL IMPACT ASSESSMENT AND THE LAW

140
ENVIRONMENTAL IMPACT ASSESSMENT AND THE LAW IN UGANDA: THE EXPERIENCE SINCE 1995 BY KIGULA MAHIRI MUHAMOOD 210-053012-02752 A DISSERTATION SUBMITTED IN PARTIAL FULFILLMENT OF THE REQUIREMENTS FOR THE AWARD OF THE DEGREE OF LAWS OF ISLAMIC UNIVERSITY IN UGANDA

Transcript of ENVIRONMENTAL IMPACT ASSESSMENT AND THE LAW

ENVIRONMENTAL IMPACT ASSESSMENT AND THE LAW

IN UGANDA: THE EXPERIENCE SINCE 1995

BY

KIGULA MAHIRI MUHAMOOD210-053012-02752

A DISSERTATION SUBMITTED IN PARTIAL FULFILLMENT OF

THE REQUIREMENTS FOR THE AWARD OF THEDEGREE OF LAWS OF

ISLAMIC UNIVERSITY IN UGANDA

JUNE 2014

1

TABLE OF CONTENTSDECLARATION..........................................................3ABSTRACT.............................................................4ACKNOWLEDGEMENT......................................................6

LIST OF ACRONYMS......................................................7LIST OF STATUTES AND STATUTORY INSTRUMENTS............................9LIST OF CASES........................................................10CHAPTER ONE..........................................................111.1 Introduction..................................................111.2 Statement of the Problem.....................................121.3 Hypothesis...................................................121.4 Methodology................................................121.5 Scope.........................................................121.6 Literature Review.............................................12

CHAPTER TWO..........................................................15DEVELOPMENT OF (EIA) AS A TOOL FOR ENVIRONMENTAL MANAGEMENT..........152.1 INTRODUCTION....................................................152.1 THE OF DEVELOPMENT AND THE ENVIRONMENT..........................162.3 THE CONCEPT OF SUSTAINABLE DEVELOPMENT AND THE EIA..............192.4 THE INITIAL PHASE OF DEVELOPMENT................................202.5. EIA LEGISLATION IN UGANDA......................................242.6 ROLE PLAYED BY EIA.............................................25

CHAPTER THREE........................................................28EIA PROCEDURES AND PRACTICE IN UGANDA................................283.1 INTRODUCTION....................................................283.2 THE LEGAL FRAMEWORK OF THE EIA PROCESS IN UGANDA................293.3 THE PROCESS OF EIA..............................................333.4 PROJECT BRIEF...................................................343.5 ENVIRONMENTAL IMPACT STUDY......................................353.5.1 Scoping.....................................................363.5.2 Impact Evaluation........................................373.5.3 Mitigation Measures....................................38

i

3.5.4 Assessment Of Alternatives..............................383.5.5 Environmental Impact Statement (EIS)......................39

3.6 PUBLIC INVOLVEMENT IN THE EIA PROCESS..........................393.7 DECISION– MAKING.............................................403.8 ENVIRONMENTAL MONITORING AND AUDITING.......................423.9 ENFORCEMENT OF EIA LEGISLATION..............................44

CHAPTER FOUR.........................................................46IMPLIMENTATION OF EIA LAW IN UGANDA..................................464.1.0. INTRODUCTION.................................................464.2 BUJAGALI HYDROELECTRIC POWER PROJECT.........................464.2.1. The Project..................................................464.2.1. Positive Environmental Impacts.............................47

4.2.3 Negative Environmental Impacts...............................48a. During construction.........................................48b. During Operation............................................49c. Impacts on the Socio–Economic Environment...................50

4.2.4. Comparison of Alternatives...................................524.2.5..........................................Mitigation Measures

54a. Access to water resources..................................54d. Ecology........................................................56e. Landscape and site reinstatement...............................56f. Fisheries......................................................58g. Tourism........................................................58h. Tropical Diseases and Public Health............................59i. Cultural and Historical Sites..................................59j. Air quality....................................................604.2.6 Environmental Monitoring Plan...............................614.2.7 Conclusion....................................................62

CHAPTER FIVE.........................................................63LEGAL CHALLENGES TO THE EIA PROCESS..................................635.1 INTRODUCTION....................................................635.2 BACKGROUND...................................................635.3 THE LOCUS STANDI IMPEDIMENT..................................645.4 LITIGATION ON EIA.............................................73

ii

5.5 ATTORNEYS FEES..................................................78CONCLUSION...........................................................78CHAPTER SIX.........................................................79CONCLUSION AND RECOMMENDATIONS.......................................796.2 DEVELOPERS ATTITUDE ON EIA......................................806. 3 ENVIRONMENTAL AUDITS...........................................816.4 OTHER CHALLENGES..............................................816.5 EIA ON POLICIES AND PROGRAMMES................................826.6. TOWN AND COUNTRY PLANNING.....................................836.7. AWARENESS AND SENSITISATION...................................856.8. CONCLUSION....................................................86

BIBLIOGRAPHY.........................................................87Texts...............................................................87

iii

DECLARATION.

I, kigula mahiri muhamood do hereby declare that this work

is original save where other materials and texts have been

used, but even then due acknowledgement has been given. It

has never been presented anywhere for the award of a degree.

Signed: --------------------------------

Date: -------------------------------

Submitted with my consent:

Supervisor:

1. Mrs sauda

iv

Signature: ----------------------

Date:

-----------------------

ABSTRACT

The fundamental thesis of this study is to assess the

efficiency of the EIA laws and procedures in Uganda and

determine whether the implementation of EIA laws has

achieved its objective of promoting sustainable development.

The study reviews the EIA process as laid down by the

guidelines and determines their adequacy. A review of some

of the EIAs carried out on some projects since 1995 is done.

It is in 1995 that EA was made a legal requirement in Uganda

by the National Environment Statute, 1995. A thorough study

is done on whether the EIAs conducted so far have complied

with the legal procedures. Where the EIA process has not

v

adequately complied with the necessary standards the study

investigates the cause of the problem and recommends the

solution.

The study further examines the conduct and the technical

capacity of EIA practitioners and makes some recommendations

on how to improve their capacity to conduct adequate

assessments.

The study will be found useful to practioners in the field

of the environment most especially those who make decisions

and policies that have a direct impact on environment. The

study is also useful to academicians, lawyers and judges in

as far as appreciation of environmental issues that are

likely to form judicial disputes are concerned.

DEDICATION.To my father SHEIKH HABIBU KIGULA MUHAMOOD and mother HAJAT SARAH KIGULA

NABUKEERA.

vi

vii

ACKNOWLEDGEMENT

This work has been made possible by the assistance and

management of many people. Although it is not possible to

mention all of them here by name, I would like particularly

to thank the following:

viii

LIST OF ACRONYMS

ADB : African Development Bank

AESNP : AES Nile Power

APC : Agricultural Policy Committee

BELA : Bangladesh Environmental Lawyers Association.

CBA : Cost benefiting Analysis.

EAP : Environmental Action PlanEIA : Environmental Impact Assessment

EIA : Environment Impact assessment

EMP : Environmental Monitoring Plan

ENEP : United Nations Environmental Programme

FHWA : Federal High Way AdministrationFIRI : Fisheries Research Institute

FSL : Full Supply Level

GC : Governing Council

GDP : Gross Domestic Product

GEF : Global Environment Fund

GoU : Government of Uganda

Ha : Hectare

IFC : International Finance Cooperation.

ix

IRN : International River Network

KM : Kilometre

KV : Kilo Volts

LCS : Local Councils

MAAIF : Ministry of Agriculture, Animal Industry and FisheriesMNR : Ministry of Natural Resources

MW : Mega Watts

NAPE : National Association of Professional Environmentalist

NEAP : National Environmental Action Plan

NEMA : National Environmental Management AuthorityNEPA : National Environmental Policy Act.

NGOs : Non-Governmental Organisations

NTCWH : National Technical and management of Water Hyacinth

OECD : Organization for Economic Cooperation and DevelopmentPAP : Project Affected Population.

RCP : Resettlement and Compensation Plan

S.I.A : Social Impact Assessment

Spp : Species

SEDD : Summary of Economic Due Diligence.

STDs : Sexually Transmitted Diseases.

Sq. : Square

UEB : Uganda Electricity Board.

UNCED : United Nations Conference on Environment and Development

x

US : United States

WB : World Bank

WBG : World Bank Group

WCED : World conference on environment and Development

WHO : World Heath organization

LIST OF STATUTES AND STATUTORY INSTRUMENTS1. National Environment Act, (Cap 153) Laws of Uganda, 2000 Revision.

2. The Constitution, 1995 (UGANDA)

3. Water Act (Cap 152) Laws of Uganda, 2000 Revision.

4. Uganda Wildlife Act (Cap 200) Laws of Uganda, 2000 Revision.

5. National Environment Policy Act (USA)

6. Environmental Protection Law, 1989 (CHINA)

7. Environmental Protection Law, 1991 (MAURITIUS)

8. Environmental Quality Act 1974 (MALAYSIA)

9. Environmental Impact Assessment Regulations, 1998 (UGANDA)

10. Environmental Impact Assessment 1994 (NIGERIA)

11. Environmental Impact Assessment Order, 1987 (MALAYSIA)

12. The National Environment (Designation of Environmental

Inspectors) Notice, 2002 (UGANDA)

13. The Land Act (Cap 227) Laws of Uganda 2000 Revision.

14. Forests Act (Cap 146) Laws of Uganda 2000 Revision.

15. Town and Country Planning Act (Cap 246) Laws of Uganda, 2000

Revision.

16. The Investment Code Act (Cap 92) Laws of Uganda, 2000

Revision.

xi

17. National Environmental (Wetland, River Banks and Lake

Shores) Regulations, 2000. (UGANDA)

18. National Environment (Waste Management) Regulations, 1999.

(UGANDA)

19. Fundamental Rights and Freedoms (Enforcement Procedure)

Rules S.I No. 26 of 1992. (UGANDA)

20. Civil Procedure Act (Cap.71) Laws of Uganda, 2000 Revision.

21. Government Procedures Act (Cap.77) Laws of Uganda, 2000

Revision .

22. Civil Procedure Rules S.I 65-3. (UGANDA.)

LIST OF CASES1. Wangari Maathai Vs. Kenya Times Media Trust, Nairobi High Court

Civil case No. 5403 of 1989 (Unreported)

2. Kamanda Vs. Nairobi City Council , Nairobi High Court Civil Case

No. 6153 of 1992 (Unreported).

3. Oposa Vs. Factoram, GR No. 1082 of 1993 (Philippines).

4. Sierra Club Vs. Coleman XV/6 ILM 1425 (USA).

xii

5. Regina Vs. I.R.C Exparte Federation of Self Employed [1982] A.C.

643.

6. Rev. Christopher Mtikill Vs. Te Attorney general, Tanzania High

Court Civil Suit No. 5 of 1993 (unreported).

7. Byabazaire Vs. Mukwano Industries High Court Suit No. 466 of 2000.

8. Siraji waiswa Vs. Kakira Sugar Works Ltd., High Court Misc.

Application No. 23 of 201.

9. RAYABAI Vs. State, Air [1973] BOM 61.

10. Sierra club Vs. United States Army Corps of Engineers, 701

F. 2d 1011 (2cir) 1983).

11. Greenwatch & Another Vs. Golf Course Holdings Ltd, High

Court Civil Suit No. 834 of 2000.

12. National Association of Professional Environmentalist (NAPE)

Vs. AES Nile Power Ltd, High Court Misc. Cause No. 268 of 1999.

13. Public Citizen Vs. Office of the USTR 970 F. 2d 916 (D.C

Cir. 1992)

xiii

CHAPTER ONE

1.1 Introduction.

Over 90% of Uganda’s population depends directly on natural

resources for its livelihood1. Despite the country’s high

natural resource potential, factors such as population

growth, economic reforms, the desire for a steady increase

in per capita income, and other pressures of the development

process are putting severe strain on the environment and

natural resource base background

1.2 Statement of the Problem

Since the introduction of EIA(first introduce it in full) as

a legal requirement for implementation of development

projects, plans and policies, in Uganda, many EIAs have been

conducted.so wht is the problem here u r addressing

1.3 Hypothesis

EIA, since its introduction in Uganda as a legal

requirement, has not been able to adequately achieve its

objects and goals of promoting sustainable development.

1.4 Methodology

In handling this work reliance has mainly been on Library

research.

1.5 Scope.

In general, the study seeks to evaluate the performance of

EIA since its introduction as legal requirement in Uganda.

1 GoU: The National Environment Management Policy for Uganda, Kampala, MNR, 1994.

xiv

1.6 Literature Review

Our Common Future2 This report enunciated the concept of

sustainable development and gave it an operational content

as an approach that will permit continuing improvements in

the present quality of life and will lower the intensity of

resource use thereby leaving behind for future generations

an undiminished or even enhanced stock of natural resources

and other assets. The Report identifies EIA as an essential

tool for promoting sustainable development by integrating

environmental concerns with socio-economic development

initiatives.

Clem Tisdell,3 in his book, attempts to define the concept

of development from an economic point of view. Economics is

viewed as the relationship between the social administration

and management of resources and scarcity. Economics

therefore is viewed as the management of resources to reduce

scarcity. In this book neoclassical economists who contend

that scarcity can be reduced by promoting economic growths

are critiqued. Instead, the author argues, economic growths

may add to the problem of scarcity because it may not be

sustainable. It is further argued that while economic

growth may reduce scarcity in the short or medium term, it

could result in greater scarcity in the long-term due to

depletion of non-renewable resources and to irreversible

2 Our Common Future, op. cit.3 Clem Tisdell, Environmental Economics, Brisbane, Jacaranda Press, 1993.

xv

environmental deterioration caused by it. Thus the book

puts to question economic growths, which has been seen by

many as the surest way to economic salvation for mankind

because of its unsustainability. The book then recommends

integration of environmental concerns with socio-economic

development planning.

J.R. Kamugisha,4 This paper makes a review of legislation on

the protection of the environmental and natural resources

management from the pre-colonial days up to the time of the

reforms in the 1990s. The author notes that the then

existing laws on natural resources management lacked

provisions aimed at conserving the natural resource base.

That the driving force behind those laws was the enhancement

of exploitation of resources. These laws were grounded on

the philosophy of the times, which posited nature as an

enemy of man, which had to be conquered for development to

occur. The author is in favour of the view that advances

the complimentarity of man and nature and not their mutual

exclusiveness.

John Ntambirweki 5 in his article reviews all the Ugandan

laws on the conservation of the environment. The role played

by customary laws and practices in environmental

conservation is emphasised. It is also noted that

4 J.R Kamugisha, Management of Natural Resources and Environment in Uganda. Policy andLegislation Land Marks, 1980 – 1990 Kampala, Danida, 1993.5 John Ntambirweki; “Environmental Legislation in Uganda: Review of existing legislation and formulation of an appropriate legal framework for present and future environmental Management”, IUCN/NEAP, Kampala, 1992.

xvi

environmental conservation can best be taken care of through

community participation and awareness and there is no better

vehicle for the integration of awareness into communities

except through accepted beliefs and practices-custom. The

paper identifies one major problem with legislation and that

is, being sector specific. The author emphasizes that

sectoral legislation does not make adequate provision for

environmental management especially for those environmental

concerns that are cross sectoral and inter-sectoral in

nature.

J.B Ojwang and Calestous Juma6 in their article, are of the

view that, even though people must have recourse in order to

enhance the economic development, if the demographic

condition or the tempo of economic activity outstrips these

resources, the people will undermine their very existence.

It is also observed here that the traditional practices and

systems of dispute settlement better catered for environment

concerns in as far as they emphasized common property

resources. Land for example belonged to all people and the

family’s right was only a right of access. On the other

hand the received law which for centuries evolved in the

Western World, and whose tradition evolved on the foundation

of property rights thereby acquiring standards and

measurements that compromised it to the restitutive goals of

ownership of property, is quite inadequate for managing

6J.B Ojwang with Calestous Juma: (Eds) “Towards Ecological Jurisprudence”: In Land We Trust, Nairobi, Initiative Publishers, 1996.

xvii

environmental resources. This is mainly because the

environment is a common property. It can adequately be

managed as a common resource..

L. Graham Smith7 discusses the role of institutional

arrangements in implementing environmental and resource

management policies. He says that legal provision for

environmental protection, planning and regulation establish

the context of impact assessment. That, these provisions

vary from country to country and are a product of each

nations distinct political culture. That as much as the law

may be viewed as an instigator of reform, it is itself

shaped by new political perspectives. And that is why it’s

not surprising to find Western nations have evolved systems

of law that favour use over preservation private property

rights, and the generation of wealth and productivity over

amenity.

CHAPTER TWO

DEVELOPMENT OF (EIA) AS A TOOL FOR ENVIRONMENTAL MANAGEMENT.2.1 INTRODUCTION.

This chapter makes out a justification for EIA as a tool for

promoting sustainable development. It gives the background

information on EIA and how the concept evolved from other

resource evaluation procedures adopted in the United States

in the 1950s. It shows how the inefficiency of rudimentary

evaluation procedures and the need for a form of social7 L. Graham Smith, Impact Assessment and Sustainable Resource Management, LongmanScientific and Technical, New York,1933.

xviii

accounting in resources, decisions led to the advent of cost-

benefit analysis. It is noted that cost-benefit analysis

also suffered limitations especially on its failure to assess

alternatives, hence the emergency of EIA.

The chapter looks at the first legislation in the US, the

National Environment Policy Act (NEPA), to require EIA and

how it influenced decisions of states at major international

conferences on environment leading to the adoption of EIA as

major tool for promoting sustainable development.

The concept of sustainable development is discussed at length

and recommended as the way of harmonising the country’s

economic development goals with the use and management of its

natural resources. The chapter discusses the complimentrity

of development and the environment and makes a strong

emphasis on the role played by EIA in intergrating

environmental decision-making process in order to achieve

sustainability. Finally EIA legislation is discussed.

xix

2.1 THE OF DEVELOPMENT AND THE ENVIRONMENT

Environmental degradation is going on at a high rate in

developing countries and particularly in Uganda. Environmental

degradation encompasses the twin threat of pollution and

natural resource depletion. The natural environment creates

the very basis of social and economic development and

specifies the limits of the resources available for such

development. That pre-supposes that environment and social

economic development are not mutually exclusive.

The traditional methods and tools of environmental protection

and resource management used by decision makers have always

tended to separate environmental concerns from socio-economic

planning, policy and management issues. That approach has

presented the two concepts, that is, development and

environmental protection, as two antagonistic and mutually

exclusive concepts. The concept of development can be looked

at from an economics point of view. Economics studies the

relationship between the social administration and management

of resources and scarcity8. Scarcity arises because available

resources are insufficient to satisfy human wants.

Consequently one of the main contributions of economics is to

suggest institutional and other changes9 to improve the

management of resources in order to reduce scarcity.

Economists3 have claimed that there are four main ways to

8 Clem Tisdell, Environmental Economics, London, Edward Elgar, 1993, p.189

9 Such as variations in market or political mechanisms or in some cases the introduction or withdrawal of social mechanisms.

33 see H Kohler, Scarcity and freedom An Introduction to Economics: An Introduction to Economic Health ,Lexington, Mass,1977

xx

reduce economic scarcity. These are, by improving the

allocation of resources between alternative uses, by ensuring

full employment of all persons, by promoting economic growth

and by improving the distribution of income. These were the

views of neo classical economists.

Now, however, it is realised that at least one of the

suggested means for reducing scarcity may add to the problem.

Economic growth may add to the problem of scarcity because it

may not be sustainable. While economic growth may reduce

scarcity in the short or medium term, it could result in much

greater economic scarcity in the long term due to depletion of

non-renewable resources and to irreversible environmental

deterioration caused by it. Thus economic growth, which has

been seen by many as the surest way to economic salvation for

mankind, is being questioned because of its un sustainability.

Most ecological economists believe that dominant existing

paradigms with their roots in neoclassical, Keynesian or

Marxian economics are inadequate in dealing with environmental

and economic development problems facing the world today.4

Keynesian economists did not raise environmental issues. These

issues did not feature in Marxian economics even though Marx

himself did point to the human trauma that can arise if

industrialisation and urbanisation alienate man from nature.

But in practice Marx and his followers such as Engels were ant

44 F.Engels (1959)" Outlines of a Critique of Political Economy" In K.Marx, Economic and Philosophical Manuscripts of 1844,

Moscow ,Foreign Language Publishing House, 1959.

xxi

Malthusian and pro economic growth. They rejected the views of

Thomas Robert Malthus10 that human population is liable to

outstrip the means of subsistence. They argued that while the

level of human population may increase in geometrical

progression, as suggested by Malthus, scientific knowledge

increases in faster geometric progression and nothing is

impossible to science11. In their view, scientific advance and

capital accumulation can be relied on to overcome any resource

constraints that might be encountered as human populations

increase. They were technological optimists.

Unlike in most developed countries, this line of argument is

still being supported by developing countries, not because

they are uninterested in environmental conservation but

because of the historical, political, social and economic

reasons discussed below. And it is because of these reasons

that the apparent conflict between environment and development

is exacerbated. Industrial development has however been

regarded as the only panacea for the acute poverty suffered by

African states. Developing countries have opted for

development and rejected any measures that may impede its

path. This is because development represents the only means

to satisfy the basic needs of the people such as food, shelter

and a decent living. On the other hand the developed

countries have stressed the need to preserve the environment

10 Thomas R.Malthus, An Essay on the Principle of Population as it affects the future improvement of Mankind, London J.Johnson, 1978.

11 F..Engels , Opcit.

xxii

as a safeguard against the negative effects of the development

process.

This debate about environment management on the one hand and

development on the other, started long ago and it is still

going on. However, the dilemma facing the developing countries

is that poverty and need are the greatest polluters. While

people in the developing countries would not wish to

impoverish the environment any further they cannot forget the

grim in which their people live. One cannot tell the people

who live in villages and slums to keep the oceans, the rivers

and the air clean when their own lives are contaminated at the

source. The environment cannot be improved in conditions of

poverty, nor can poverty be eradicated without the use of

science and technology. This was the point greatly emphasised

by African countries at the Stockholm Conference in 197212.

This reluctance of the developing countries to put

environmental concerns ahead of development needs could be

explained by the imbalance in development between North and

South. This imbalance is explained on the basis of past

exploitation of the South by the North through colonialism and

imperialism where there was massive exploitation of natural

resources to develop the north and thereby putting the south

at an economic disadvantage. The concern of the developed

countries for the conservation of the environment is therefore

12 Mr. Tolba (Ed) Evolving Environmental Perceptions: From Stockholm to Nairobi, London, Butterworths 1989. quoted in Natambirweki

John: Law and Sustainable Industrial Development,1997.

xxiii

treated with suspicion by the developing countries. The

developing countries suspect the developed countries to be

using the concept of environmental conservation as a measure

to discourage industrial development and to encourage the

exploitation of natural resources in the developing world.

Consequently, it is argued, the developed world would be able

to sustain their already developed industries by using the

abundant market that exists in the developing world for their

manufactured goods.

2.3 THE CONCEPT OF SUSTAINABLE DEVELOPMENT AND THE EIA

Sustainable Development is an approach that will permit

continuing improvements in the present quality of life and

will lower the intensity of resource use thereby leaving

behind for future generations an undiminished or even

enhanced stock of natural resources and other assets13. In

other words, the challenges that face the countries must not

only focus on raising living standards of the people but must

also provide resources for those of the future.

One of the basic premises for sustainable development is the

recognition that environment and development are not exclusive

of one another but are complimentary and interdependent

and, in the long run, mutually reinforcing. It is necessary

to view environmental problems as a system. A coherent set of

13   This broad definition is based on "Our common future" (Report of theWorld Commission on Environment and Development, 1987) London , OxfordUniversity Press, 1987.

xxiv

solutions is required which will ensure that each step taken,

whether in planning or implementation, to address them fits

in perfectly with others envisaged. It is not possible to

compartmentalise environmental concerns or deal with them in

sectors. The difficulties are compounded by the fact that we

are dealing with a set of mobile and highly dynamic

components which make it necessary to devise long-term and

flexible responses.

It is not surprising, therefore, that while we all speak of

sustainable development and agree on its importance and

immediacy, it has been found extremely difficult to give an

operational content to the concept or to identify practical

policy guidelines for its realisation. Yet there is increasing

and stark evidence that in different regions of the world,

notably in Africa, excessive demands are being made on limited

resources and the carrying capacity of fragile ecosystems. The

unsustainable use, abuse and misuse of the very environmental

systems upon which life depends is showing up in soil erosion,

lack of water, and in its deteriorating quality,

deforestation, desertification and other adverse natural

phenomena to the growing dismay of all of us. This is not to

say that we should put a stop to development or to the use of

nature to meet our basic needs, but that we must do this

within acceptable bounds that do not disturb the environmental

cycles of life. In so far as renewable resources are

concerned, it means reliance on nature's "income" and not on

xxv

the depletion of its "Capital."14 The central idea is that

development can occur only if and when there is recognition of

the need to sustain and expand the environmental resource

base. The associated corollary is that “economic” growth, in

and of itself is insufficient for the purposes of development.15

Sustainability rests on the tenet that technology and social

organisation can be both managed and improved to make way for

a new era of economic growth.16 The key is in how to manage

technology social organisation in resource development to

provide for decision making that will foster sustainability.

Prevailing systems for decision-making in many countries tend

to separate socio-economic, and environmental factors at the

policy, planning and management levels. This influences the

actions of all groups in society including governments,

industry and individuals and has important implications for

the efficiency and sustainability, of development.

For that matter it is necessary to search for analytical tools

and methodologies, which will enable us to achieve an

accommodation of the social and environmental consequences in

economic decision-making.

14 Y.J. Ahmad and G.K. Sammy: Guidelines to Environmental Impact Assessment inDeveloping Countries; UNEP Regional Seas Reports and Studies No. 85. Nairobi,UNEP, 1987.15 Shearman, R (1990). “The Meaning and Ethics of Sustainability” Environmental management 14(1), 1-16 WCED,Our Common Future, Opcit. p. 8.

xxvi

2.4 THE INITIAL PHASE OF DEVELOPMENT

Until the 1950s, resource management decision making mostly

addressed the following questions: Is it technically feasible?

Is it financially viable? Is it legally permissible? Not

surprisingly, this rudimentary form of evaluation often

resulted in engineering - based answers to resource management

problems, the `technical fix' usually involving some form of

structural solutions chosen from a narrow range of pre-

determined options. Provided the scale of development was

limited, the problem well defined and adequate information

available, this system of resource decision-making functioned

quite well. However, the increasing complexity, scale and

implications of resource development projects through the

1950s revealed the weaknesses of this traditional approach.

Often there was more reliance upon (hidden) political agendas

and ulterior motives than any sound technical scrutiny of

projects. Many projects resulted in major environmental

degradation. Moreover, the wider social costs of such

developments as dam construction and flood control schemes

were shown to be largely unaccounted for despite their

significance.17 The desire for a broader form of social

accounting within resource decisions led to the advent of

cost-benefit analysis.

17 Wote GF (1945) The Human Adjustment to floods. Department of GeographyResearch Paper No. 29, University of Chicago: Quoted in L. Graham Smith:"Impact Assessment and Sustainable Resource Management," New York, LongmanTechnical and Scientific, 1933.

xxvii

Cost-benefit analysis emerged initially in the evaluation of

water resource developments in the United States as a means of

broadening the approach to evaluation in resource management

decision-making.18 Through the 1960s, cost-benefit analysis

became the predominant technique for evaluation in resource

decision making, its popularity a function the simplicity with

which its objectives could be understood and the apparent ease

with which it could be applied to a wide range of situation.

Cost-benefit analysis was attractive to engineers and

decision-makers because it could produce a tangible measure of

social `utility' generating quantitative indices relating to

fiscal benefits and costs, with emphasis on the criterion of

economic efficiency. However, the technique also suffered from

a surfeit of misapplication in practice, including, a failure

to consider alternatives; a focus on easily measured,

quantifiable benefits and costs; a failure to adhere to key

premises, leading to inflated benefit measures and manipulated

accounting and an inability to account' accurately for, and

incorporate, such temporal changes as variations in interest

rates and price levels. In addition cost-benefit analysis was

criticised for its conceptual inability to account for the

distribution aspects of costs and benefits and the problems of

aggregation19.18 Sewell, W.R.D (1973) "Broadening the approach to evaluation inresource management decision making," Journal of Environmental Management I. 33-60.

19     Larley M.J and Bustelo ES , Social Impact Assessment and Monitoring,West View: Boulder Co, 1984.

xxviii

These deficiencies prompted the development of alternative

means for the economic appraisal of projects, such as the

`goals achievement matrix' of Hill or the `planning balance

sheet' developed by Lichfield20. Simple cost-benefit analysis

was replaced by more sophisticated variants, using multiple

objectives and discount rates, proxy pricing mechanisms and

various means of planning programme budgeting and cost-

effectiveness analysis. However this increasing sophistication

could not avoid criticisms that centred on the

inappropriateness of such accounting procedures for the

evaluation of complex environmental interrelationships and the

broader social issues of resource allocation.21

Thus, while cost-benefit analysis remained the pre-eminent

technique for resource decision-making, the need for

alternatives became apparent. The desire for an alternative

form of social accounting was further reinforced by two

interrelated factors, that is, the increasing scale of

complexity and uncertainty associated with resource

development proposals and the growth of public opposition to

the approval of those projects. The era of mega-projects had

arrived, but it was accompanied by the rebirth of public

activism, particularly in the case of environmental quality

and the desire for equity in the processes of governance. The20    McAllister DM, Evaluation in Environmental Planning, London, MIT Press:,

1980.

21 O'Riodan T. and WRD Sewell: Project Appraisal and Policy Review, Quoted inGraham smith, Impact and Sustainable Resource Management, New York LongmanScientific and Technical, 1933

xxix

outcome of these assorted pressures was the appearance of

environmental impact assessment (EIA).

The formal process known today as EIA resulted from the

raising of environmental awareness during the 1950s and 1960s.

During those two decades it became increasingly evident that

many industrial and other projects were producing undesirable

environmental consequences. In response to these problems

several governments realised the need for a mechanism ensuring

that the environmental consequences of all major projects and

plans were examined before their execution was formally

authorised. The US congress was among the first to enact in

1969, a comprehensive legislation, the National environment

Policy Act (NEPA) using the concept of EIA and requiring a

systematic interdisciplinary evaluation of the potential

environmental effects of all major federally funded projects.

Under NEPA, agencies of the USA government must prepare

detailed statements on the environmental impact of "proposals

for legislation and other major federal actions significantly

affecting the quality of the human environment"22.

Later on in 1972, during the Stockholm Conference it was

contended by the participating nations, that long term and

sustainable development could only be achieved through sound

environmental management. That EIA is one of the tools to

ensure sound environmental management. In 1986 EIA was

identified as an essential tool for promoting sustainable

22     42 US Code, S. 4332 (1970): 40 Code of Federal Regulations Part 1500(1978, amended in 1986).

xxx

development by the WCED23. In 1992, UNCED24 held in Rio de

Janeiro made specific requests asking UNEP to undertake

further development and promotion of the widest possible use

of EIA including activities carried out under the auspices of

United Nations specialised agencies. Further, in 1987 at the

14th Session of the UNEP Governing Council25, the UNEP was asked

to promote widespread use of EIA procedures by governments and

where appropriate international organisations as an essential

element in development planning and for assessing the effects

of potentially harmful activities on the environment.

EIA had been adopted in many countries with different degrees

of enthusiasm where it has evolved to varying levels of

sophistication. Even in centrally planned economies of Eastern

Europe26 it was increasingly being realised that EIA would be

an integral component of state planning, although Marxist

theory places another perspective on the interrelationships

between development and the environment.

Bilateral and multi-lateral agencies have also become

interested in the potential of EIA. The organisation for

Economic Co-operation and Development (OECD) adopted

recommendations concerning EIA within its constituent states

in 1974 and 1979 and for development projects in 1985. The

23      Our Common Future' Op cit.

24       UNCED, `Agenda 21'

25     UNEP/GC. 14/26 Annex I

26    Before the collapse of Soviet Union.

xxxi

UNEP has provided guidance on the assessment of development

proposals,27 and supported research on EIA in developing

countries.28 The World Health Organisation (WHO) has become

concerned with the need to assess not only the opportunities

to improve quality of life presented by development but also

consequent adverse effects upon human health mediated through

environmental change.

In recent years, the breadth of EIA has expanded perhaps more

rapidly that its rate of its geographical spread. Thus, it now

comprises a number of discrete specialisms and has spawned

related disciplines concerned with other effects of

development, particularly social impact assessment (S.I.A),

environmental health impact assessments and so on.

Since the adoption of NEPA, national legislation requiring

EIAs has increased world-wide and today, even countries

without such legislation produce EIAs selectively. This

legislation generally has taken three forms: EIA provisions

incorporated within a framework environmental law,29 separate

EIA laws, decrees, rules or regulations,30 or both.31 Uganda

27     UNEP 1980, Opcit

28   Ahmed and Sammy 1985, opcit

29  For example, China: Environmental Protection Law (1989); Mauritius:Environment protection Act (1991 amended in 1993)

30   For example, Nigeria: Environmental Impact Assessment, 1994.

31   For example, Malaysia, Environmental Quality Act S. 34A 1974 and Environmental Impact Assessment order, 1987.

xxxii

has taken the trend of adopting both the statute and the

regulations.

2.5. EIA LEGISLATION IN UGANDA

Before 1995 the Government of Uganda did not require

environmental impact assessment for development activities.

However the only E.I.As, which were prepared for development

activities in Uganda, were in response to the requirements of

donors. These assessments were prepared to donor

specifications. The lack of EIA as a legal requirement was

identified by the National Environmental Action Plan, NEAP,

and the task force on environmental policy, legislation and

institutional arrangements, as a critical environmental

problem. To respond to this problem the National Environment

Management Policy Framework for Uganda, 1994, prepared by

NEAP, calls for EIA of all development activities.

In 1995 the National Environment Act32 was enacted as the basic

legislation on environment. It came with, inter alia, a

provision33 to the effect that environmental impact assessment

be conducted for proposed activities that are likely to have

significant impacts on the environment. Further, the Act

provides34 for the establishment of National Environment

Management Authority, NEMA, and one of its functions, among

others, is to prepare and adopt guidelines for Environmental

Impact Assessment on proposed projects, which may affect the

32 Cap. 153 Laws of Uganda,2000 Revision.33  S. 1934  S. 4

xxxiii

country's natural and social environment. In addition, the

Act35 empowers the Minister to make Regulations, to give full

effect to the provisions of the statute. It is on that basis

that NEMA prepared The Environmental Impact Assessment

Regulations, 1998, which set out a comprehensive procedure for

conducting an EIA.

Also sectoral legislation such as the Wildlife Act36 and the

Water Act37 contain a requirement of EIA. Making EIA a

requirement in each of these Statutes was intended to make it

specific and appropriate to each sector of natural resource

management due to the particularity of each of these sectors.

It was also intended to avoid the possibility of adopting all-

inclusive general guidelines, which would obscure such

particularities.38 With these legislative reforms in the field

of the environment and natural resource management an

integrated, cross-sectoral and comprehensive approach to

guiding the design and implementation of development is

expected.

2.6 ROLE PLAYED BY EIA

One of major premises of the concept of sustainable

development is the integration of environmental concerns with

social economic planning. To effectively integrate environment

and development in the policies and practices of a country, it

35 S. 1936 Cap.200, Laws of Uganda,2000 Revision.37 Cap.152,Laws of Uganda,2000revision.38 John Ntambirweki: A Consultancy Report on Environmental Legislation in Uganda,NEAP, 1992.

xxxiv

is essential to develop and implement integrated, enforceable

and effective laws and regulations that are based upon sound

social, ecological, economic and scientific principles. It is

equally critical to develop workable programmes to review and

enforce compliance with the laws, regulations and standards

that are adopted. The enactment of such laws and regulations

are also essential for the implementation of most

international agreements in the field of the environment as

illustrated by the treaty obligation to report on legislative

measures39

And one of such laws that would be effective in integrating

development and environment concerns is environmental impact

assessment legislation. In Uganda, like in most of the world,

conservation and environmental law has been reactive, it has

responded to situations

already at crisis stage. And as the saying goes, it is more

expensive to repair than to prevent.

Hence a need for environmental laws that is pro-active. One

example of laws that are pro-active is the law on

Environmental impact assessment, because it can predict

adverse environmental consequences of an activity, plan or

policy and then, either provide for mitigation measures to

such consequences or provide for alternative modes of

implementation that are environmentally friendlier. It has

also the capacity to incorporate other economic tools like

39     UNCED, 1992, Agenda 21,Opcit.

xxxv

cost-benefit analysis and it is one of the ways of

implementing the "Polluter pays" principle. In economic

planning, the environment has always been neglected. It has

not always been taken into account. Decision-makers regard

components of the natural environment as free goods that

should not be paid for. This cannot be true because economics

is concerned with allocation of scarce resources. Since

environment has the capacity to assimilate residues without

affecting its quality it should be regarded as a scarce

resource and therefore subject to allocation like any other

economic good.

It is necessary to examine a number of problem areas if

environmental concerns are to be effectively integrated in the

development process. The developing countries find these

problems complex and sometimes obscure. The problems tend to

be interrelated and of a longer term nature. They require a

multi-disciplinary approach. The scope and nature of

environmental impact and consequences, especially in the long

term, are speculative.

Developing countries are deterred by the intellectual

complexity (due to multi-disciplinary and adaptive nature) and

financial requirements (mounting consultancy fees) involved.

Even

when the consequences have been identified, it is not always

possible to make a quantitative (monetary) assessment.

Furthermore in Uganda and most other developing countries, the

xxxvi

techniques of integrated physical, socio-economic and

environmental planning are not known or practised. Such

techniques need to be simplified and made more practical to

replace largely sectoral planning. Nor is attention paid to a

system of supplementary or satellited accounts that will

assign values (if not market, then shadow) to environmental

goods and services, such as fresh air, clean water, tree

cover, soils, genetic resources and the like, so that

efficiency in the allocation of scarce resources is improved.

Although it is commonly recognised that environmental impact

assessment is a basic tool for undertaking anticipatory

environmental policies and that it has become increasingly

urgent to incorporate environmental assessment into the

planning and the decision-making process from an early stage

of the development cycle, developing countries have been

reluctant to use the framework of EIA statements

systematically. For example in some

Countries40 where legislative requirements for EIA exist, it

has not been systematically used. This has been due to a

number of reasons; environmental impact assessments have

proved to be too long, too time consuming in preparation, too

expensive (especially when prepared by consulting

organisations), sometimes too poorly written and often not as

useful to decision makers as they should be.

40 Australia, Japan, Republic of Korea, the Philippines, and Thailand.

xxxvii

xxxviii

CHAPTER THREE

EIA PROCEDURES AND PRACTICE IN UGANDA3.1 INTRODUCTION.

The National Environment Action Plan (NEAP), the task force

on the environmental policy, legislation and institutional

arrangements, prepared the National Environment Management

Policy Framework for Uganda in 1994, which called for EIA for

all development activities. In its efforts to set up

procedures and guidelines for EIA for Uganda, NEAP considered

the guidelines and procedures on EIA already adopted for

other developing countries with similar economic political,

social and ecological circumstances with Uganda. NEAP also

harmonized these with the World Bank Operational Guidelines

to come up with the national EIA process. There are,

therefore, no significant differences between the World Bank

Guidelines on EIA and the National EIA guidelines contained

in the national legislation.

3.2 THE LEGAL FRAMEWORK OF THE EIA PROCESS IN UGANDA.

The Law, in Uganda, recognizes Environmental Impact

Assessment as a major tool for environmental management and

sustainable natural resource use. This is manifested in the

way the Constitution and various pieces of legislation set

forth broad principles and goals for the nation’s

environmental policy aimed at promoting sustainable

development.

xxxix

The Constitution of the Republic of Uganda of 1995, provides

among its national objectives41, that utilization of natural

resources shall be managed in such a way as to meet the

development and environmental needs of the present and future

generations of Uganda, particularly taking all measures to

prevent or minimize damage and destruction to land, air,

water resources resulting from pollution or any other kind of

natural resource degradation. According to the Constitution

every Ugandan has a right to a clean and healthy

environment42. It is further provided that the government or

local government as determined by parliament by law shall

hold in trust for the people and protect natural lakes,

rivers, wetlands, forests, game and forest reserves, national

parks and any land to be reserved for ecological and

touristic purposes for the common good of all citizens43. This

right carries with it the duty of the citizen to protect the

environment. The Constitution goes ahead and provides that

parliament shall, by law, provide for the measures intended

to protect and preserve the environment from abuse, pollution

and degradation and to promote management of the environment

for sustainable development44.

In response to the above Constitutional mandate, Parliament

in 1995 enacted the National Environment Act45 as the basic

41 Objective No.2742 Constitution of Uganda 1995, Article 39.43 Article 237(b)44 Ibid45 Cap.153,Opcit

xl

legislation on environment with a provision, among others,

that requires developer of a project that is likely to have

significant impacts on the environment to carry our an

Environmental Impact Assessment46. The Mandate of carrying out

an EIA is derived from this Statute. It is important to note

from the onset that the EIA requirement in Uganda under the

National Environment Statute is limited to projects only as

opposed to some foreign legislation such as the United States

National Environment Policy Act (NEPA)47 where the mandate to

carry out an EIA is quite broad. NEPA requires that all

federal agencies include, in every recommendation or report

on proposals for legislation and other major federal actions

significantly affecting the quality of the human environment,

a detailed statement by the responsible official on the

environmental impact of the proposed action and any adverse

environmental effects which cannot be avoided should the

proposal be implemented48.

In the United States the mandate to carry out EIA goes beyond

development projects, to policies and even proposals for

legislation. In Uganda, EIA is more often associated with

development projects rather than policies. There is a great

need for EIA for major development policies related to

sectors such as tourism development, water resource

development, urbanization, agriculture forestry and

46 Ibid,S. 1947 542 U.S.C. 4321 – 4370 a.48 S. 102 of NEPA.

xli

industrial development to mention but a few. Policy EIAs

present an opportunity to examine the environmental

implications of national and regional development policies

and proposals before decisions are made to implement specific

projects conceived under the broad policies. EIAs conducted

on policies contribute significantly to harmoniseation of

different sectoral policies and remove unwanted policy

aspects.

The Wildlife Act49 requires every developer desiring to

undertake a project, which may have a significant effect on

any wildlife species or community to carry out an EIA in

accordance with the National Environment Act50. The Act also

obliges the Uganda Wildlife Authority (UWA) in consultation

with NEMA to carry out audits and monitor such projects that

may have an impact on wildlife.51

The Land Act52 does not expressly deal with EIA but has some

provisions that embrace it. It does however, regulate the

ownership of land and controls land use. It obliges any

person who owns or occupies land to manage and utilize it in

accordance with the Water Act, the National Environment Act,

the Forest Act and any other law.53 The Act also requires

that any use of land should conform to the Town and Country

Planning Act and other laws54. An EIA is therefore, a useful49 Cap. 200, Opcit.50 S. 1651 S.1752 Cap. 227,Laws of Uganda 2000 Revision.53 S. 4454 S. 46

xlii

tool to guarantee that the proposed land use does not

contravene any law.

The Investment Code55 though enacted before the National

Environment Statute, has got some important provisions, which

embrace the spirit of EIA. The Code empowers the Uganda

Investment Authority to among other things, attract and

coordinate all local and foreign investments in the country

to enhance economic development. The Code requires every

investment licensee to take necessary steps to ensure that

the operation of its business enterprise does not cause any

injury to the ecology or the environment56. In fact it should

be the policy of the Uganda Investment Authority (UIA) to

require EIA as a pre-condition for granting an investment

licence. It is even more convenient and important than EIA

forms part of the feasibility study of the project that is

submitted to UIA so that environmental costs are known from

the onset of the project to enable the project developer

weigh these environmental costs together with other economic

costs in order to know the net worth of the whole project.

The National Environmental (Wetlands, River Banks and Lake

shores Management) Regulations57 require a developer deserving

to put up a project which may have a significant impact on a

wetland, river bank or Lake shores, to carry out an EIA.58 It

is further required that the developer carries out annual55 Cap.92 Laws of Uganda 2000.56 S. 1957 Regulation No. 3 of 2000.58 Regulation 34 (1)

xliii

audits and monitoring of such activities that may impact on

the environment and submit reports to the Executive Director

and the Lead Agency in accordance with Sections 23 and 24 of

the National Environment Statute.59 These regulations

followed the Wetland policy of 1995, which provides that all

proposed modifications and restoration on wetlands be

subjected to EIA and that damaged wetlands be rehabilitated

in accordance with the findings of the EIA. The policy also

requires that all planned new wetland developments be

subjected to EIA to determine the environmental Controls.

According to the policy, those, which have been subjected to

EIA, will continually be monitored to asses their impact on

the environment and where the impact is detrimental,

Government will require that such a development be halted.

In response to these regulations and policy, NEMA has halted

the development of a number of projects. For example, the

development of a shell petrol station at Ntinda where a swamp

was being filled with soil was stopped. A fish factory that

had erected a high wall on a lakeshore at Bukakata in Masaka

without doing an EIA was stopped by NEMA. NEMA also closed an

abattoir, which had been developed in a wetland at Kajansi.

The National Environment (Waste Management) Regulations60

require that a waste treatment plant or disposal site carry

out an EIA in accordance with these regulations before a

59 Regulation 34(2)60 Regulations No. 52 of 1999.

xliv

licence is issued61. It is further required that an operator

of a waste treatment plant or disposal site carry out an

annual audit of the environmental performance of the

site/plant and submit a report to NEMA.62 It is also a

mandatory requirement for every person who operates a waste

treatment plant/disposal site to take all necessary steps to

prevent pollution from the site or plant, which include among

others, instituting mitigation measures.

The environment Impact Assessment Regulations63 apply to all

projects included in the third schedule to the National

Environment Statute, 1995 and to any major repairs,

extensions or routine maintenance of any existing project

that is included in the third schedule to the Statute64. The

Regulation make it a mandatory requirement for any developer

of a project for which EIA is required under the Statute to

carry out an EIA in accordance with these regulations.65

3.3 THE PROCESS OF EIA.

According to the National Environment Act66 every developer is

required to carry out an EIA if the project falls in the

categories specified in the third schedule to the statute. In

the third schedule an EIA will be required in the following

circumstances. First, in cases of an activity that is out of

character with its surroundings. An example would be61 Regulation 15.62 Regulation 15 (2).63 Regulations No. 13 of 199864 Regulation No. 3 (1)65 Regulation 3 (2).66 S. 19

xlv

constructing a chemical-manufacturing factory in a

residential area; second, any structure of a scale not in

keeping with its surroundings. Third, an activity involving

major changes in Land use.

The Act67 provides for three different levels of assessment

depending on the nature of anticipated impact. These levels

are:

Where a project may have an impact on the environment, then

an environmental impact review may be conducted.

Where a project is likely to have a significant impact on the

environment then impact evaluation may be conducted.

Where a project will have a significant impact then an

Environment Impact study will be conducted.

In the process of operationalising the EIA process it was

found to be too complicated to determine before hand, which

level the project falls. As a result of this realisation the

EIA Regulations, 1998 only provided for a 2-step (level)

process. Therefore, all projects falling within the Schedule68would be required to submit a project brief,69 but for the

time being the two other steps, that is, evaluation and

review could be ignored. If the project brief is not

approved then an Environmental Impact Study will be

recommended.

67 Cap.153, S.20(3)68 Third Schedule to Cap.153 Opcit.69 Regulations 5-9 of EIA Regulations 1998

xlvi

3.4 PROJECT BRIEF.

The Regulations provide that the Authority (NEMA) may approve

the project brief if it is comprehensive enough or if the

project is minor, not likely to lead to significant impacts.

If the Authority finds that the project will have significant

impacts on the environment and that the project brief

discloses no sufficient mitigation measures to cope with the

anticipated impacts, it shall require that the developer

undertakes an environmental impact study.70

The project brief shall contain the following:

the nature of the project in accordance with the categories

identified in the Third Schedule

the projected area of land, air and water that may be

affected the activities that shall be undertaken during and

after the development of the project.the design of the

project.

the materials that the project shall use, including both

construction materials and inputs the possible products and

by-products, including waste generation of the project

the number of people that the project will employ and the

economic and socio benefits to the local community and the

nation in general.the environmental effects of the materials,

methods, products and by-products of the project, and how

70 Regulation 9.

xlvii

they will be eliminated or mitigated any other matter which

may be required by the Authority.

The developer will submit ten copies of the project brief to

the Executive Director of NEMA, who shall transmit a copy of

the project brief to the lead agency for comments within

seven working days of receiving the project brief.71 Lead

agency means any Ministry, department, parastatal agency,

Local Government System or Public Officer in which or whom

any law vests functions of control or management of any

segment of the environment.72

In determining the significance of environmental impacts at

this stage the Authority should use sample-screening

criteria, which include: -

Risk to human health; Significant adverse effects on

quality/quantity of natural resources;

Resettlement or significant alteration of life style/customs

Proximity to towns or resources or protected areas;

Environmental value of the area in which the project occurs’

Significant alteration of the scenic or tourist value of a

zone; Alteration of important cultural sites;

Harm to flora and fauna; Damage to material assets; and

Disturbance of ecological balance

Effects might be direct, indirect, cumulative, short-term or

long-term in nature. The significance of an effect can be

gauged by its extent, duration, intensity and

71 Regulations 6.72 S.1,Cap.153, Opcit.

xlviii

irreversibility. Consideration must also be given to

existing environmental quality standards. In this way it is

hoped that many of the smaller and medium sized projects will

be approved at the project brief level provided that the

brief is exhaustive and indicative of the anticipated

impacts. If the decision at this screening stage is to

reject the project it shall then require a detailed

environmental impact study.

3.5 ENVIRONMENTAL IMPACT STUDY.

Once the Authority recommends a study them the developer in

consultation with the Authority and lead agency put up terms

of reference.73 The terms of reference shall include all

matters required to be included in the environmental impact

statement provided for in regulation 14 and such other

matters as the Executive Director may in writing provide.

The environmental impact study is to be conducted in

accordance with the guidelines adopted by the authority in

consultation with the lead agency.74 The developer is required

to submit the names and qualifications of persons who shall

participate in the study.75 The Executive Director may

approve or reject the name of any person submitted and

require that another name be submitted within a specified

period.76

73 Regulation 1074 See S. 19 (8) of Cap.153 Opcit.75 Regulation 11 (1)76 Regulation 11 (2)

xlix

The persons undertaking the study are required to conduct

themselves in accordance with the guidelines, an established

code of practice or the written directions issued by the

Executive Director.77

This phase of Environmental Impact study comprises of the

steps of impact identification through scoping, impact

evaluation (quantification), provision for mitigation

measures, assessment of alternatives and finally

environmental impact statement.

3.5.1 ScopingThe term scoping is used to indicate a crucial early step in

the EIA process. This involves a coarse analysis of the

possible impacts of an action with a view to identifying

those impacts that are worthy of a detailed study. It is a

new development in the EIA, and is based on the recognition

that the impacts of an action are of varying importance. The

idea is first to develop a simple list of all consequences of

the proposed action. No attempt is made at this stage to

quantify. When the list has been completed, it is carefully

examined to identify the important impacts. Naturally this

is region or country specific.

One region or country may consider watershed management very

important, but soil erosion unimportant. In another the

reverse order may hold. The point is to control cost and

optimise cost-effectiveness by concentrating on the most

important impacts.77 Regulation 11 (3)

l

The scoping exercise should to the extent possible, involve

representatives of potentially affected communities, relevant

government agencies, representatives of other interested

parties including NGOs, the private sector, independent

experts and all other stakeholders including the general

public. Usually this will include meetings to obtain their

comments on what should be included in the study and what

alternatives should be considered in order that an adequate

environmental impact study shall be conducted. This public

participation is well catered for under the EIA Regulations,

1998.78

The responsibility for scoping should be that of the

developer, but the lead agency and other interested parties

shall be involved. The developer shall undertake to prepare

a scoping report which summarises the results of scoping and

which shall also constitute part of the terms of reference

for the study. The scoping report shall be approved by the

responsible lead agency in consultation with the Authority

before a detailed environmental study is conducted.

3.5.2 Impact Evaluation.

This step involves the quantification of impacts. The

quantification of impacts is the most difficult technical

aspect of an EIA. It is also the most controversial.

Perhaps it would be appropriate to deal with controversy

first, and the technical aspect later.

78 Regulation 12

li

It is generally agreed that the quantitative change due

to an impact should be computed wherever feasible. It

should also be noted that present technology does not

permit quantification of all impacts. The thorny

question, therefore, is how to treat those changes that

cannot be quantified. One approach would be to ignore

them altogether, since they represent a considerable

level of uncertainty. The other approach would be to

include them in a qualitative form.

The best approach however, is that if an impact has been

identified as important during the scoping step, then it

should not be ignored simply because its magnitude cannot

be quantified. There are several methods, which permit

the qualitative assessment of an impact based on expert

opinions leading to a prediction of its magnitude. Such

methods range from simple round-table discussions to the

structured Delphi technique.79 The details of such

techniques are outside the scope of this work.

The problems of quantification are compounded when cost

is included in the question. The cost of quantification

appears to rise geometrically with the degree of accuracy

required. The solution could then be linked up with the

scoping exercise. By looking at the impacts, which were

ignored, it is, possible to get a feel for the

‘coarseness’ of the EIA. One could then set the degree

79 YJ Ahmed and GK Sammy,Guidelines to Environmental Impact Assessment in Developing Countries, London, Hodder and Stronghton, 1985. P.22.

lii

of accuracy for quantification accordingly. To cite an

example: the pollution in an estuary can be estimated by

simple formulas, or by complex computerised models. The

latter generate far more exact predictions. But if it

has been decided to ignore several small, non-point

pollution sources, then the degree of accuracy is

automatically reduced. In such circumstances the cost of

a computerised model can hardly be justified.

The point to be made here is that judicious scoping

should limit both the number of impacts that are studied

and the depth to which selected impacts are studied. As

previously stated the qualified impacts are predictions,

not facts. Therefore, there is a degree of uncertainty

to acceptable levels, not to try to eliminate it

altogether. The scoping exercise can and should address

the degree of accuracy, which represents an acceptable

level of uncertainty in light of budgetary constraints.

3.5.3 Mitigation Measures

Although it is seldom possible to eliminate an adverse

impact altogether, it is often feasible to reduce its

intensity. This reduction is referred to as a

mitigation measure. Such measures may be engineering

works (such as dust collectors, sludge points, noise

mufflers etc) or management practices (such as crop

liii

rotation, phased plant shutdowns etc). All mitigation

measures have associated costs.

In some respects mitigation planning is part of impact

evaluation. Once applicable measures have been

identified, it is necessary to compute their cost and to

requantify the level of impact, acknowledging the

beneficial effect of the mitigation measure. Depending

on circumstance mitigation might give rise to two

project alternatives where only one existed before.

3.5.4 Assessment Of Alternatives

The “Assessment” step has often been labelled

‘Comparison of Alternatives’. It is at this point that

the technical information gained in previous steps will

be pulled together. It is at this point too, that the

environmental losses and gains will be combined with

economic costs and benefits to produce a full picture of

each project alternative. The intended output is a

series of recommendations from which the decision-maker

will choose a course of action.

In order to proceed to compare alternatives, two pieces

of information on each project alternative are required.

The first is a summary of positive and negative

environmental impacts. The second is a summary of

economic costs and benefits. The former will have been

generated as part of the preceding steps in the EIA.

liv

The latter may be developed as part of the EIA, or may

come from a parallel economic analysis like CBA.

The “No Project” alternative

The simplest approach to comparing alternatives across

both the economic and the environmental fronts is cost-

benefit analysis (CBA). To do this, the environmental

impacts must be converted into economic equivalents, and

listed as costs and benefits. A cost – benefit analysis

is then done for each alternative and the

recommendations are made on that basis.

3.5.5 Environmental Impact Statement (EIS)

“At the conclusion of the environment impact study an

EIS should be made by the developer. This EIS is

intended to be comprehensive for two reasons. First to

enable the Authority appreciate the choice of

development alternatives made by the developer and to

enable it make a decision whether to approve the project

or not. Secondly the authority may use the statement as

the basis for its post-assessment environmental audit”.80

In making the EIS the developer shall pay attention to

issues such as ecological considerations, social

considerations, landscape and land use.

80 John Ntambirweki, A Consultancy Report on The Framework for EIA in Zambia, Nairobi, ELI/PAN, UNEP, Dec, 1993.

lv

3.6 PUBLIC INVOLVEMENT IN THE EIA PROCESS

Public participation plays a pivotal role in the EIA

process. The public here refers to the beneficiaries of

the project, the communities affected, government and

other private or public sector interests groups. Public

involvement happens typically during the scoping and

reviewing phases of EIA process.

The legal basis of the public participation in the EIA

process is the National Environment Act81 which provides

for participation the public in environmental issues.

The Act82 also provides for consultation as part of the

approval process of the EIS. Public participation in

the EIA process is specifically provided for by the

Environmental Impact Assessment Regulations 199883 where

it is provided that the developers shall take all

measures necessary to seek the views of the people in

the communities which may be affected by the project

during the process of conducting the study.

This should be done by publicising the intended project,

its anticipated effects and benefits through the mass

media in a language understood by the affected

communities for a period of not less than fourteen

days84. After the expiration of the period of fourteen,

the developer is supposed to hold meetings with the81 (Cap 153) S. 6 (1) g and (j)82 Ibid S. 21(1)83 Regulation 1284 Regulation 12 (2) (a)

lvi

affected communities to explain the project and its

effects85.

3.7 DECISION– MAKING.

Decision – making is regarded the final phase in EIA,

though there are other post assessment processes of

monitoring and auditing. Some scholars86 have decided to

regard the developer as one of the decision-makers.

They have considered decision – making at two levels,

that is, that of the developer and the government

agency. With due respect, this is a wrong assumption.

A decision – maker should be that person or body of

persons who has not been involved in the aspects of the

study. In any event decision-making becomes a separate

event from the study process, and should be treated as

such.

Within the context of EIA, the decision-making starts

when the working document reaches the decision-maker.

This document may be either, the project brief or the

EIS, depending on what level the decision is required.

In the EIS will be found a list of project alternatives

with comments on the environmental and economic impacts

of each. There will also be recommendations as to one or

several preferred courses of action.

85 Regulation 12(2) (b)86 For example, John Ntambirweki, The Framework for Environmental Impact Institutions Programme Activity Centre (ELI/PAC) Nairobi,United Nations Environment Programme (UNEP), Dec, 1993, p. 12.

lvii

It is unlikely that a decision maker would reject the

technologists’ recommendations to the extent of

selecting an alternative, which is clearly labelled

‘unacceptable’ and it is among these that the decision

maker must consider political realities along with

economic and environmental information. Consider the

case of a proposed industry, which will discharge a

certain volume of liquid waste. One alternative design

will result in a level of discharge that is considered

acceptable.

A second, more expensive design will yield even less

pollution. The CBA has put both alternatives on par, so

the second has been recommended on environmental

grounds. A decision maker may feel justified in

rejecting that recommendation, since he knows that the

first less costly alternative is far more likely to be

built. The point here is that the choice was not

between ‘bad’ and ‘good’, but rather between ‘good’ and

‘better’. And good was chosen because it was more

likely to be realised.

One vital necessity in the decision making step of EIA

is time. A developer needs to have a decision made in a

reasonable time, so that he can know how to proceed. In

general the decision-maker can do one of three things’

accept one of the decision alternatives; request further

study; or reject the proposed action altogether.

lviii

If the decision-maker were to accept one of the project

alternatives, then the next step would be to complete

the engineering designs and proceed with the action. In

such a favourable situation, delays are quite

unnecessary.

If further study is requested, the decision-maker should

be quite specific as to what information is being

requested. Non-specific requests for further study can

be construed as simply stalling action, and will reduce

the credibility of the EIA procedure. On the other

hand, a specific request can usually be easily complied

with thus minimising delays.

Finally an outright rejection leaves the project

proponent with the choice of filing an appeal in the

High Court87 or abandoning the proposed action. In order

to assist him in deciding on his response, the rejection

notice should clearly indicate the grounds for the

decision to reject the proposed action. Extreme delays

in the decision-making process will only antagonise

developers and lends credibility to the claim that EIA

is anti-development. To avoid this, decision-makers

must make every effort to tender their verdict in a

timely manner.

87 See Regulation 38

lix

3.8 ENVIRONMENTAL MONITORING AND AUDITING

At the decision making phase, when choice is made, it is

assumed that the project or programme will proceed. This

is not the end of EIA. One further step remains to be

completed. This step is the monitoring and auditing one.

As noted earlier on, E.I.A.s are based on predictions.

Monitoring and auditing are used to see what actually

occurs and to ensure that the anticipated impacts are

maintained within the levels predicted. Unanticipated

impacts are managed or mitigated before they become a

problem and the benefits expected from the EIA are

achieved as the project proceeds. They can be used to

provide information for periodic review and alteration

of impact management plans, optimizing environmental

protection through good practice at all stages of the

project.

Monitoring and auditing are two different terms where

the latter is more of an implementation process of the

former. Monitoring refers to the systematic collection

of environmental data through a series of repetitive

measurements to meet specific objectives and

environmental needs.88 Monitoring can be used to ensure

that the benefits anticipated as a result of the EIA

reactively achieved as the project proceeds.89

88      ECE, Post Project analysis in EIA, New York, United Nations,1990.

lx

This systematic EIA follow-up process is necessary

because of a number of reasons. First, often relatively

little attention is paid to actual effects arising from

project construction and operation. Secondly, without

systematic follow-up to decision making, EIA may become

a proforma process, a paper chase to secure a

development permit, rather than a meaningful exercise in

environmental management to bring about real

environmental benefits and achieve environmental

sustainability. Thirdly, increasing numbers of people,

funds and time are being devoted to EIA and there is a

need to safeguard the returns in terms of environmental

benefits and the quality of decision making.

Until recently EIA legislation in most countries had

been weak in providing for the follow-up to an EIA

study.90 To improve the situation there is need for the

incorporation of environmental management plans (to

eliminate or reduce negative impacts of activity) and

environmental monitoring plans (to monitor compliance

with EIA conditions) into the EIA documentation. These

may involve regular record keeping as well as self-

monitoring by a proponent/developer91. Implementation of89      EPA, Best Practice in Environmental Management in Mining. Environmental

monitoring and Performance, Canberra ,quoted in THE EIA Resource Manual:Preliminary version, June 1996.

90 Lal Kurukulasuriya and Marceil Yeater, Op cit P. 266.

91 One example of legislation containing such a provision is the India'sEnvironmental Impact Assessment Notification, Section IV (1994).

lxi

such plans can be supervised by government inspectors to

ensure compliance with and evaluation of the EIA process

and results. The monitoring process also can be linked

to provisions for the regular environmental auditing of

existing facilities.92 To help ensure compliance with

mitigation and other measures, proponents could be

required to enter into a binding agreement based on

procedures and recommendations in the EIA report93 and

/or employ penal provisions to secure compliance in this

respect.

In Uganda the National Environment Statute, 1995

provides for both monitoring94 and auditing.95 According

to the statute, the NEMA, in consultation with a lead

agency, is supposed to monitor all environmental

phenomena with a view to making an assessment of any

possible changes in the environment and their possible

impacts. It is also supposed to monitor the operation of

any industry, project or activity with a view to

determining its immediate and long-term effects on the

environment. Powers to enter upon any land or premises

for the purposes of monitoring the effects upon the

92 As is the case in Nepal's National EIA guidelines chapter xii(1994).

93 Namibia, National Environment Assessment policy, paragraph 5(1994).

94   S. 23 Cap.153 Opcit

95   S. 22, Ibid

lxii

environment of any activities carried on that land or

premises are vested in the environmental inspector

appointed under S. 79 of the Act96.

On environmental auditing the Act97 gives that

responsibility to the Authority and the developer. The

environmental inspector is supposed to determine how far

the activities conform to the statements made in the

EIS. The developer is supposed to keep records and make

annual reports to the Authority describing how far the

project conforms in operation with the statements in the

EIS.98 The developer is also required to take all

reasonable measures to mitigate any undesirable effects

not contemplated in the EIS and shall report on those

measures to the Authority from time to time as the

Authority may require.99

3.9 ENFORCEMENT OF EIA LEGISLATION

The Act100 and the Regulations101 create offences in

respect environmental Impact Assessment. Where a

developer fails to submit a project brief or, fails to

prepare an environmental impact assessment or,

fraudulently makes a false statement in an environmental96      S.22 (2) Cap.153, Opcit

97      S. 22

98      S. 23 (3)

99      S. 22 (4)

100 Cap.153,Opcit.101 EIA Regulations 1998

lxiii

impact statement, commits an offence and is liable on

conviction, to imprisonment for a term not exceeding

eighteen months or to a fine of not less than one

hundred and eighty thousand shillings and not more than

eighteen million shillings or both.102 The court may

further order that any licence, permit or other

authorisation given for purposes of implementing the

project or policy, be cancelled103. The court may also

issue an environmental restoration order against the

accused.104

Finally, the law does not prevent the bringing of any

civil action or a criminal prosecution under any

enactment concerning the project or the manner it is

operated or managed, notwithstanding that an approval

was made in respect of an environmental impact

assessment.105

102 S.96 of Cap.153 Opcit.103 S.105 (3) ibid.104 S.105(5) ibid, See also part IX of the Act.105 Regulation 35(2)

lxiv

CHAPTER FOUR

IMPLIMENTATION OF EIA LAW IN UGANDA

lxv

4.1.0. INTRODUCTION

As earlier noted106 EIA was not a legal requirement in

Uganda prior to 1995 when it became a legislative

requirement107.

4.2 BUJAGALI HYDROELECTRIC POWER PROJECT

A number of recent studies on the power sector in Uganda

have pointed to the Uganda Electricity transmission

Board’s (UETB) operational difficulties and severe

constraints such as the corporation's inability to

provide reliable and quality customer services, power

losses of some 20% and reduced earnings.108

Economic growth in many sectors of the economy has been

constrained by inadequate and unreliable supply of

power. Business lose about 89 working days on average

each year due to power cuts, load shedding and

suppressed demand. This translates into a suppression of

economic growth of about 2% per annum.109 A very small

percentage of the rural areas is connected to

electricity. Rural electrification therefore, is an

increasingly important issue.

106 Chapter 1 Page 2107 National Environment Act (Cap. 153) Laws of Uganda, 2000108 Bujagali Hydroelectric Power Project Environmental Impact StatementFinal Report, WS Atkins International Ltd, March 1999.109 Ibid.

lxvi

4.2.1. The Project

AES Nile Power (AESNP), a joint venture between AES

Electric Ltd. a UK wholly owned subsidiary of the AES

Corporation, a US Company and Madhvani International of

Uganda, submitted a formal proposal to the Government of

Uganda and the U.E.B to develop a 250 MW hydroelectric

power plant on the river Nile at Bujagali.

The project site is located at Dumbbell Island, near the

source of the Victoria Nile in Uganda and about 2.5 Km

downstream from Bujagali Falls. The project comprises a

250 MW Power station housing 5x50 MW Kaplan turbine

generation units with associated 30m high embarkment and

spill way work. Construction is in two phases.

4.2.1. Positive Environmental Impacts

The project was found to have potential positive socio-

economic impacts in terms of the provision of employment

opportunities, opportunities for increased trade,

development of the local economy and a potential

improvement in local services in the area. From a

public health view point, the submergence of the

whitewater rapids sections of the river by the reservoir

will eradicate the breeding grounds for the blackfly

simulium damnosum, thus reducing the on chocerciasis hazard in

the local area. At the same time, however, the reservoir

will increase the habitat for the snail and mosquito

lxvii

vectors of bilharzia and malaria although anticipated

flactuations in water levels will not favour

colonization by the disease vectors.

In the context of the normal environment the scheme can

be expected to have a beneficial effect on fisheries.

Lake Victoria and the Victoria Nile contain many of the

same fish species, and the creation of the impoundment

will result in a change in the relative abundance of

these species to produce fish fauna more characteristics

of a lake than a river. For example, Barbus ssp. would

become less abundant whilst Talapia ssp. And other cichlits

would increase in abundance. In view of its proximity

to Lake Victoria it is unlikely that the reservoir would

be developed as a commercial fishery. However, the size

of the impoundment would be sufficient to support a very

significant subsistence fishery, providing an important

source of protein for the riparian communities.\

The new lake may be expected to attract increased

numbers of certain water birds, although the flooding of

many of the islands in the river would destroy important

breeding habitats which are currently less susceptible

to human interference. The diurnal variation in

operating water levels may also expose areas of muddy

shoreline.

lxviii

4.2.3 Negative Environmental Impacts

This section considers impacts on the natural

environment during construction and reservoir filling,

during operation and also the impacts of the scheme on

the socio-economic environment.

a. During construction

The area of land, which will be inundated by the

Kalagala reservoir at a full supply level of 1088m ASL,

excluding the river surface area, is estimated to be

about 1,400 ha. The main reasons of inundation will be

the lower lying land on both sides of the river,

extending from the dam site upstream for 9km to about

1km South of Busowoko Falls. The remaining 6km of

flooded river to the toe of Dumbbell Island will largely

be confined within the gorge. In addition, the 1997

master plan estimates that some 30ha of land would be

required for the permanent structures and temporary

construction support facilities, principally on the east

bank, and some 15ha for 11km of access roads.

On the basis of GIS land use mapping it is estimated

that the land area taken by the reservoir will comprise

975 ha of agricultural land, 85ha of natural vegetation,

defined as woodland, bushland, grassland and wetlands,

and 330ha of forest. It may reasonably be assumed that

lxix

the additional 45ha for the scheme components would fall

within agricultural land category.

The destruction and inundation of the gazetted forest is

important in an area where few remnants of the natural

vegetation cover remain elsewhere, the loss of

agricultural and ‘natural’ secondary vegetation in this

area will have little impact on the natural environment,

since these vegetation types have no ecological

significance. On the part of air quality it was found

that since there are no major urban areas or industry

around the project area, the ambient air population

levels are very low. During construction however, there

will be deterioration in local air quality due to the

generation of suspended particulate from the

construction of project roads, blasting and excavation,

vehicle movement and batch plant operations. These

operations will take place in locations close to settled

rural areas. The adoption of good site practice will be

essential to minimise dust production and vehicle

emissions.

High noise levels and vibration will arise from blasting

concrete batching, aggregates production and the general

operation of construction equipment and vehicles.

Ambient noise levels in the area have not been measured,

but undoubtedly well below exist international standards

for low-density residential areas. Guideline levels vary

lxx

between different countries, but a reasonable standard

for daytime maximum levels would be around 55 c/BA6.

The existing vegetation cover plays an important role in

reducing soil erosion within the site area, although in

many places the steep riverbanks have been cultivated

down to the edge of the river.

b. During Operation

Major storage schemes for hydropower generation have a

marked impact on the downstream river, since the

regulation effectively replaces the natural seasonal

variations in flow. In the Victoria Nile, however, the

Owen Falls Dam has regulated the flow since the mid

1950’s, although the power generation operation produces

short-term diurnal variations. Whilst the scheme

involves an impoundment extending some 8 km upstream of

Dumbell Island, the purpose of the dam is solely to

regulate the headwater

Level for power generation. The regulation would be

primarily on a 24-hour cycle, with limited variation on

a daily or weekly basis. Flactuation in downstream river

levels and flows arising from the operation will

therefore be very small, of the same order as those

currently obtained below Owen falls. The principal

impacts of the scheme on water quality and acquatic

ecology will arise from the creation of the reservoir.

66 Word Bank Environmental Guidelines, 1998.

lxxi

In particular the anticipated changes relate to the

nutrient status of the stored water and its effect on

trophic levels within the lake.

Over the long term the stored waters at Bujagali may be

expected to have a virtually identical chemical

composition to that of lake Victoria, which is

characterised by low concentrations of dissolved ions

and neutral pH. However, nutrient availability in the

reservoir may be expected to increase during and after

the first filling, due to the release of nutrients from

the submerged agricultural soils and vegetation, and the

high oxygen

demand of the soil organic matter and biomass. It is

expected that equilibrium conditions with the inflow

waters should be restored within a few months after the

initial filling.

A further fact militating against nutrient accumulation

and weed growth in the reservoir is the relatively rapid

rate of turnover of the water. The retention time of the

impoundment is likely to exceed a few hours under normal

flow conditions, and there will therefore be little

opportunity for nutrients to be retained within the

storage. Moreover, the reservoir will not flood any

significant amount of land beyond the main channel,

where turnover times would be reduced, which will again

lxxii

decrease the risk of both nutrient accumulation and

stratification.

It may therefore be concluded that the Bujagali

reservoir is unlikely to experience problems arising

from the growth of excessive quantities of waterweeds.

Nevertheless despite its low nutrient status the

presence of water hyacinth is an increasing problem in

the coastal areas of Lake Victoria, and in particular in

the headwater pond above Owen Falls, where regular weed

clearance is carried out.

c. Impacts on the Socio–Economic Environment

The reservoir will inundate the Bujagali Falls, other

falls in the vicinity of Dumbell Island, Dumbell Island

itself and a significant number of Islands upstream to

Owen Falls. The area of inundation varies in width a

long the banks of the river from approximately 200

metres in the north on the east bank to some few metres

in the south. The average depth of the land to be

inundated is approximately 75 metres. The majority of

this is

intensively used for cultivation. The total area of land

to be acquired is estimated to be 270 hectares, but this

excludes land for borrow pits and the tip site. The main

borrow pit and tip site would be located on the east and

west banks near Dumbell island and the major works site

would be on the west bank in the same area. These areas

lxxiii

are intensively cultivated but not densely settled. Much

of the land would only be required for the duration of

the construction period only, and could then be returned

to productive use and/or resettled. From house counts

on the 1:7,500 aerial photography, it is estimated that

some 95 to 100 dwellings would be directly affected by

the construction of the works and the land inundated by

the development, and that most of the dwellings affected

would be concentrated around the dam and power house

site. This is equivalent to around 475 to 500 persons,

which is considerably fewer than the estimated number of

1100 to 1600 persons previously estimated in the

environmental scoping.110

Disturbance will be experienced during the construction

period to communities who remain in the area. It is

understood that construction of the dam and associated

works will

take place from both banks and there will inevitably be

increased traffic, much of it heavy

vehicles causing noise, dust and air pollution. This

will affect a significant number of people along the

roads from Jinja on both banks, particularly in the

Malindi and Namizi areas. The development of the

construction will require portable water supplies,

proper sanitation and a refuse disposal system. The

110 AES/NP, 1997 Opcit

lxxiv

demand for water supplies and firewood, which are

limited in the area, could compete directly with the

demand for these resources by local people. The

landscape in the Dumbell Island area will be affected by

the construction of the dam, power station and

associated works. Within the Bujagali Falls area, the

landscape character will change due to their inundation.

Part of the picnic site where the built facilities are

located will be lost, with implications for local

recreation and income for Jinja District. The white

water refitting activities that take place from this

site will no longer be possible, which has significant

implications for the development of the tourism industry

in the wider area. However consideration could be given

to the development of other recreation activities, such

as boating and sport fishing on the newly created water

area.

Concerning the impact on cultural heritage, the site of

Bujagali shrines would be inundated. Whilst any

potential loss of a cultural site constitutes an adverse

impact, the local people in the area do not attach great

importance on these shrines.

On the side of public health, Bujagali site is

sufficiently close to Owen falls to be at high risk from

Schistoma Cercariae released from the Lake Victoria focus of

infection. Health statistics show that schistosomiasis is

lxxv

prevalent throughout the area, and the river is used at

various points by the riparian population for drinking

water suppliers, bathing and

washing clothes. The new reservoir will have a total

area of about 4.3 km2 at maximum supply level, but the

impounded area will be almost entirely confined within

the river gorge. Therefore the new impoundment will not

result in any significant increase in the available area

of public access of water. The impoundment may provide a

small additional habitat for the mosquito vectors of

malaria, but the effect would be insignificant in an

area where all the population are currently at very high

risk.

4.2.4. Comparison of Alternatives

During the carrying out of an Environmental Impact

Assessment of the proposed Bujagali Hydropower Project

on the River Nile a comparative assessment of the

alternatives had to be conducted. This was in response

to the requirement in both NEMA and IFC guidelines for

the consideration of alternatives to major projects. In

addition, during meetings with the IFC and World Bank in

Washington in March 1998, IFC requested a comparative

assessment of the alternatives in order to assist them

in producing an unranked short list of potential energy

projects in Uganda, which they could consider for

possible future funding. The strategic options

lxxvi

considered were the sites of Karuma Falls, Kalagala and

Bujagali.

The major objective of the comparative study was to

provide a basic strategic comparative assessment of the

proposals for the three sites on the River Nile, to

determine whether the Bujagali project falls within the

threshold of acceptability with respect to its

environmental consequences.

Consequently the study came up with the following

findings. Karuma is a runoff river scheme, whilst

Bujagali and Kalagala involve impoundment to maintain

the generating head. In terms of positive economic

impacts, Kalagala clearly has the greatest installed

capacity, twice that of Bujagali and five times that of

Karuma. A 500MW scheme represents a very substantial

step increase in the installed capacity, by a factor of

almost

three, and it must remain questionable as to whether the

UEB system could cope with this increase without

significant alternation.

The land take and overall area of direct impact is

greatest at Kalagala, and the potential number of

oustees much higher. When these impacts are related to

power generation capacity, the ration of the power

lxxvii

output to the area inundated and the number of oustees7

is lowest at Kalagala.

The nature of the effects on the natural environment is

similar at both Kalagala and Bujagali, but the scale of

impact will be higher at Kalagala. In particular the

larger impoundment behind the Kalagala dam will result

in the loss of a significant area of gazetted forest.

The ecological impacts of the schemes will be least at

Karuma. The impact on the landscape and potential

tourism value is also likely to be highest and most

widespread at Kalagala, although Karuma Falls will be

dramatically affected by the Karuma scheme. The impact

on the landscape at Bujagali will be less severe, and

the Kalagala reservoir will drown out a greater length

of the reach of the Nile currently used for white water

rafting activities.

In terms of socio – economic effects the potential for

stimulating development is possibly greatest at Karuma,

due to the cover overall level of economic activity and

the poorer standards of living in the surrounding area.

The extent of social disruption and disturbance,

especially during construction, is however likely to be

greatest for the Kalagala scheme and lowest at Bujagali.

In summary, the Kalagala scheme will provide a very

large increase in power but will have the greatest

77 GOODLAND R 1996, The environmental sustainability challenge for the hydro industry, Hydro – Power and Dams, Issue 1, 1996.

lxxviii

overall environmental and socio – economic impacts.

Karuma is likely to have the least overall environmental

impact, but generates the lowest amount of power, whilst

Bujagali will have relatively low environmental impact

whilst generating substantial amounts of power.

Therefore, Bujagali was the most desired alternative.

4.2.5. Mitigation Measures

In the previous sections, potential environmental

impacts of the scheme were identified. This section

investigates options for mitigating or eliminating these

impacts, either by changes to the scheme design or by

controls on working practices during the construction

and operation phases.

a. Access to water resources

In areas where residents are isolated from their main

water source (the River Nile) due to land acquisition,

two options for mitigation are provision of access

pathways through or around the site, and provision of

pumped water to villages higher on the riverbank.

Provision access pathways through or near the

construction site will create a risk of pedestrain

injury by construction traffic, which will be heightered

by the fact that it is mainly children who carry water

from the river to the households. For this reason it

would be preferable for manually or mechanically pumped

water to be supplied to affected villages or groups.

lxxix

As an additional measure to offset the inconvenience to

residents caused by the construction program, and to

comply with the World Bank’s requirement that the PAP

(Project Affected Population) should be at least as well

– off after the project, would be for the developer to

provide improved sanitation facilities to residents, in

conjunction with providing alternative water supplies.

Once the power station becomes operational, there will

be a diurnal fluctuation in water level. This will

result in the alternate inundation and exposure of the

periphery of the shoreline. Consequently, conditions in

this section are likely to become muddy so that points

of access for the collection of water are likely to

become unusable on a regular basis. Suspended solids

could easily be disturbed and the quality of collected

water adversely affected. Provision of a limited number

of secure access points clarge stones,

causeways, concrete bars or wooden jelties would prove

beneficial, and might also serve other purposes like

fishing or boat launching. A structure, which minimised

the degree of contact with water, would be preferable,

thereby limiting the possibility of decease vector

contact.

b. Hydrology

In order to prevent impacts on ecology and water

resources downstream, the regime of water releases from

lxxx

the Bujagali impoundment during the filling, flow rates

downstream of the embarkment be maintained above a

minimum of 300m/s, which is approximately one third of

the long term Q50 flow for the upper reaches of the

Victoria Nile. This figure has been reached after

discussion with both the engineers and fresh water

ecologists. The reservoir filling process will take

place slowly so that engineers can make structural

checks, therefore this regime should not impact the

filling programme.

During periods when there is no turbined flow, due to

outages and emergency closures of the plant, minimum

downstream flows should correspond to 95% of the

contemporaneous flow downstream of Owen Falls, i.e. only

5% of the dircharge from Owen Falls will be retained in

Bujagali impoundment. Maintenance of this flow regime

will require close co-ordination with the operation of

the Owen Falls Dam. When the outflow from the Owen Falls

Dam is low due to lower power generation requirements, a

smaller proportion of the flow will be able to be

retained in the Bujagali impoundment compared with that

which is spilled.

c. Water quality

lxxxi

Foul water produced by workers on site (especially during

construction) should be treated and disposed of in an

appropriate manner. Given the rapid dilution, which will be

achieved if effluent is discharged into the Nile, a high

level of treatment would seem unnecessary, and treatment

could justifiably be limited to removal of solids. However,

if

the effluent quality standards which NEMA has recently

proposed are implemented,

effluent will be required to be subject to a much higher

degree of treatment.

Runoff of particulates into the river should be avoided,

from the perspectives of maintaining water quality and

preventing soil erosion. Clearing of vegetated slopes should

be minimised as far as practicable to reduce erosion. Site

drainage systems should include sediment traps or settlement

ponds. Where a large amount of excavation or blasting will

take place below or near the water line measures such as

sheet piling should be used to contain suspended matter.

Potential pollutants such as fuel and oil should be stored

in a safe and secure manner such that the risk of pollution

of the river in the event of a spill is minimised. Measures

such as bunding of storage areas should be considered.

Contingency plans should be devised, and staff appropriately

trained in order to deal with any pollutant spills.

lxxxii

Consideration should be given to clearance of vegetation

from the impoundment before filling. This will reduce the

possibility of deoxygenating of the impoundment, and the

attendant risk to aquatic life, and will also remove the

risk of fouling boats and fishing equipment. The issue of

the backwater, which will be created downstream of the

eastern side of the embarkment, needs to be addressed.

Options include filling with rock or earth or providing a

compensation flow to flush out organic matter and aquatic

plants which can provide habitat for disease vectors. In

view of the anticipated shortage of fill material, it

appears that the latter option will be more feasible.

d. Ecology

Submergence of islands is inevitable but the loss of natural

vegetation can be compensated by preventing people from

cultivating the remaining submerged parts of the islands.

Either natural regeneration or planned planting of suitable

tree species should take place, preferably the latter. The

new trees will somewhat compensate for the lost roosting

sites for birds and bats. This development will also create

an attractive area, close to the Bujagali developments on

the mainland, as described in the tourism section below.

A framework for successful management of this mitigation

measure would be provided by gazetting the islands as

central or District Forest Reserve, whereby the Forest

Department would assume responsibility for their management.

lxxxiii

e. Landscape and site reinstatement

The loss of some 8 km of river landscape including rapids,

islands and some valley slopes cannot be mitigated. However,

the loss can be partly compensated by enhancing the

landscape and the use of the future lake as far as possible,

and by ensuring appropriate restoration and use of the areas

disturbed through construction activities around the

embankment.

The islands, which remain in the impoundment after filling,

should be allowed to regenerate or be replanted as native

forest, which will replace some of the habitat, lost during

clearance of the impoundment and by speculators immediately

prior to the commencement of the project. Access to these

islands should be restricted to prevent disturbance of these

habitants.

Potential disturbance of nearby residents by stray light

from the site during the construction phase should be

mitigated against by careful siting and screening of

lighting towers. For reinstatement of Borrow Areas required

for the project three options have been identified;

(a) Restoration of agriculture

(b) Provision of social facilities such as schools,

parks, sports or

tourism facilities

lxxxiv

(c) Re – afforestation

During the consultation process, which has been carried out

during the EIA, a number of local and national stakeholders

have expressed preferences for each of the options. The

final decision as to which option or combination of options

is implemented will require consensus from all affected

parties, and is seen it as the responsibility of the

developer to obtain this consensus.

The first two options appear to be preferred by local

residents. Restoration to agriculture has been suggested by

a number of residents who would be interested in returning

to the restored borrow areas and utilising these for

agriculture. The EPC contract requires replacement of 600mm

of subsoil and 200mm of top soil (800mm in total), which

will

permit any type of land use to be employed post – project.

If areas are restored to

agriculture the terracing of land to permit surface

irrigation would receive enthusiastic

support from the local Department of Agriculture.

The advantage of land restoration to agriculture is that it

would partially relieve land pressure problems and permit

oustees to resettle on or near their existing holdings.

There is the possibility of improving land quality by

restoring land to gentle slopes that will be more easily

lxxxv

framed and have a reduced risk of soil erosion. The issue of

the legal status of this land, and which residents take

possession of the reinstated land, will be complex

and it is assumed that previous occupants of affected areas

would have first priority, and that other displaced people

will have second priority.

f. Fisheries

As previously suggested, consideration should be given to

clearing the impoundment of vegetation before filling, to

avoid the adverse water quality effects associated with

rotting vegetation, and also to prevent fouling of fishing

equipment.

Fishermen who lose access to the river from their own plots

should be provided with alternative, preferably improved

access. This could be in the from of new jetties located on

either side of the impoundment, which would provide superior

facilities for landing, as well as a focal point for sale of

fish. Such proposals could be integrated with those for

water collection points.

After the physio – chemical characteristics of the new

impoundment have stabilised, stocking with commercially

exploitable species may need to be considered. Such species

include tilapiines (especially Oreochromis niloticus), Barbus ssp.

and cichlids. Nile perch (lates niloticus) are likely to be present

in the impoundment from the time of filling, and are

unlikely to need restocking. Consultation with FIRI staff

lxxxvi

will be needed in order to determine which species will be

introduced, as research has shown that some of these species

cannot co-exist. For example Nile perch is a predatory

species and its domination of the species structure in Lakes

Victoria and Kyoga has resulted in the near elimination of

smaller species.

g. Tourism

It is likely that the proposed mitigation measures for

tourism could result in a net increase in retained tourism

earnings/revenue for Uganda. It is probable that the current

estimated level of economic leakage would be significantly

reduced under the mitigation proposals. The following

proposed range of mitigation measurers could be considered

individually as “stand – alone” measures, or combined to

form an integrated zonal approach to development of tourism

opportunities.

These are Bujagali Community Recreating Area with an

estimated initial cost of US$ 50,000, Bujagali Lake

Enhancement Program with an estimated initial cost of US$

200,000, Bujagali Hydropower Visitor Centre with an

estimated initial cost of US$ 350,000 and the Uganda River

Nile Tourism Strategy with an estimated cost of US$ 200,000.

h. Tropical Diseases and Public Health

Local health services may need to be strengthened,

particularly if there is a significant influx of workers

from outside the immediate area of the project. It is

lxxxvii

recommended that any strengthening be based upon improving

the quality and quantity of services supplied by existing

health care facilities in the project area, rather than by

developing new facilities.

A general program of primary health care in the area that

includes health education and improvements in water supplies

and sanitation, such as that which is currently being

considered by AESNP, will contribute significantly to a

reduction in the prevalence of tropical diseases as well as

STDs. This will require additional health workers to be

provided to local health centres.

Regardless of whether these programs go ahead, there are

certain minimum measures it is recommended are implemented

to address specific health problems which have been

identified in the area, and which it is possible may be

exacerbated by the project. These measures are in respect to

diseases such as schistosomiasis, Malaria, onchocerciasis and other

communicable diseases.

i. Cultural and Historical Sites

The Bujagali shrines will require relocation. During the

relocation, ceremonies are involved and extensive

consultation will need to be undertaken by the Bujagali

Namamba before the ceremonies can be performed. The

relocation involves costs. The Ministry of culture has

suggested that they handle compensation on behalf of the

developer and that together appropriate costs are

lxxxviii

negotiated. The same principles apply to the relocation of

the spirits from Dumbell Island. Shrines could possibly be

relocated to the land to the north of the dam which is only

required temporarily. Proximity to water and public access

need to be assured and AESNP should be able to guarantee

permanent access to relocated shrines thus providing an

improvement on the existing limited access situation.

Although the project area contains no sites, which have been

recorded by the Department of Antiquities as being of

historic or archaeological importance, if any

archaeological, remains are unearthed during excavation;

these should be reported to the Antiquities Department, who

will advise on any conservation necessary.

j. Air quality

Soil stripping operations only be carried out when the soil

is relatively dry, thus limiting the potential dust

suppression control measures may therefore involve

suspending operations when wind speeds are high or when

there is a potential for dust to be carried to sensitive

locations. Long-term storage mounds such as those for

topsoil and subsoil can be seeded to prevent windblown

emissions. When storage mounds are removed, working the

downwind side first reduces the potential for dust

emissions.

As aggregate crushing has the potential to produce large

amounts of dust, it is recommended that aggregate crushing

lxxxix

and grading plant be suitably enclosed in order to reduce

these emissions. Other measures to reduce dust emissions

include reducing drop heights and minimising handling of

materials.

k. Resettlement and compensation plan (RCP)

The main socio-economic impact of the project will be the

need to relocate approximately 44 houses holds to new areas

and the need to provide alternative agricultural lands for

some 712 affected plot holders. Compensation measures have

been developed which include establishment of escrow

accounts for payments for land lost and for the purchase of

new land. Cash compensation will be paid for the property to

be replaced, crops lost, and for the relocation of shrines

and graves.

Compensation measures are also proposed to mitigate for loss

of income from fishing particularly during construction.

These include compensation for loss of the fishpond in

Namizi and the provision of new fish landing sites in the

project area.

Consideration is also given to the provision of facilities

within the project area to benefit the wider community.

These include the development of health, education and

recreation facilities on borrow pits reinstated after the

completion of construction.

Access to the river for sources of water will be affected

particularly during the construction period and measures

xc

will be taken to provide alternative supplies to affected

communities. Finally priority will be given, wherever

possible, to local communities in the recruitment of

unskilled and semi-skilled workers during the construction

of the power project.

l. Environmental Action Plan (EAP)

The positive and negative impacts of the proposed scheme

were identified and assessed in relation to their magnitude,

and potential mitigation measurers were examined as seen

above. This Environmental Action Plan (EAP) recommends

mitigation measures that should be implemented in order to

eliminate or reduce significant adverse environment or socio

– economic impacts to acceptable levels. These are

summarised in the table below together with their

implementation cost estimates.

SOURCE: BUJAGALI HYDROELECTRIC POWER PROJECT,

ENVIRONMENTAL IMPACT STATEMENT, FINAL REPORT VOLUME I, WS

Atkins International Ltd., 1999.

4.2.6 Environmental Monitoring Plan

A number of mitigation measures were recommended in the EAP,

which when implemented will eliminate or reduce to

acceptable levels the negative environmental impacts of the

project. In order to assess the effectiveness of these

measures or to identify further corrective action and to

xci

detect any impacts that may not have been identified during

the EIA process, it was considered essential that an

Environmental Monitoring Plan (EMP) for the project be

implemented. This is an IFC requirement.

This EMP defines the scope and schedule for monitoring,

assigns responsibilities for each of the monitoring

activities and provides costs estimates so that the plan

will receive funding along with the other investment

components. It also highlights any technical skill shortages

that require filling and institutional strengthening which

will be required for successful implementation. Finally it

provides a framework for reporting and review, in order that

stakeholders are kept appraised of the actual impacts of the

project, and modifications can be made to the EAP as

necessary.

4.2.7 Conclusion

The EIA for Bujagali Hydropower Project was adequately

carried out. The process complied with all the legal

requirements as set out in the Act, Regulations and

Guidelines. It was a challenging exercise, which was

completed to the rigorous international standards set by the

World Bank Group. There was sufficient collection and

updating of field data, followed by additional data and

xcii

analysis and extensive reviewing. As has been remarked by

World Bank, revised EIA meeting World Bank Group (WBG)

guidelines was prepared under a tight timeline111. The

Bujagali project was approved by World Bank on December

18,2001 and by the African Development Bank on December

16,2001

111 World Bank Technical Report on EIA for Bujagali Hydropower Project, 2001

xciii

CHAPTER FIVE

LEGAL CHALLENGES TO THE EIA PROCESS5.1 INTRODUCTION

Private citizens and environmental public interest

organizations perform an important public role in

effectuating the goals of national environmental laws.

Parties acting in a private capacity in environmental

litigation not only supplement government enforcement

efforts but also serve as a watchdog on compliance by

government agencies with statutory duties.

Despite the valuable public benefits, which may accrue from

such efforts, there are a number of constraints inherent in

the litigation process, which checks the zeal of

environmental activists. One of such constraints is the

doctrine of “standing” which shall be discussed below.

Secondly, since public interest advocates (attorneys) lack

the investigative and financial resources of industry and

government it is also critical that the national

environmental legislation provides for awards of advocates

fees to prevailing parties. This is particularly necessary

in environmental litigation because typically the party

challenging the unlawful conduct principally seeks

injunctive relief other than damages.

xciv

5.2 BACKGROUND

The promotion of sustainable development through legal means

at national levels has led to recognition of judicial

efforts to develop and consolidate environmental law.112

Judicial intervention is necessary for the development of

environmental law particularly in implementation and

enforcement of laws and regulatory provisions dealing with

environmental conservation and management such as the EIA

Laws and regulations.

In order to harmonise, develop and consolidate environmental

law and its enforcement, it is essential to understand the

development of jurisprudence as an element of the

development of laws and regulations at national and

international levels. When this fails the victims of

environmental torts turn to the judicially for redress.

However, today’s environmental problems are challenging to

legislators and judges alike because of their novelty,

Urgency and dispersed effect. Over the last decades many

countries have witnessed a dramatic increase in the volume

of judicial decisions on environmental issues as a result of

global and local awareness of the link between damage to

human health and the ecosystem and a whole range of human

activities. In many countries, the judicially has responded

to this trend by re-fashioning legal, sometimes age old,

112 UNEP, A compendium of judicial decisions in matters Related to Environment, National Decision, December 1998.

xcv

tools to meet the demands of the times, with varying decrees

of success though.

But such practices have hardly taken root in Africa and

Uganda in particular, where not so much judicial

intervention has been evidenced. This is mainly because the

jurisprudence built around the terms and requirements of

civil litigation cannot provide an ideal framework for

environmental norms in a country like Uganda on account,

especially of the fact that litigation here lacks the

spontaneity and frequency it has in the west. The

prevailing state of poverty and lack of awareness makes it

difficult for the general public to use civil litigation as

a device of environmental protection.

5.3 THE LOCUS STANDI IMPEDIMENT

The rigours of civil litigation are also associated with the

problem of Locus Standi. Not anybody in the affected area,

for example, can bring an action against a polluter. It

must

be that one whose rights have been directly infringed. The

courts of East Africa, in the very limited number of cases

coming before them, are strictly guided by property rights.

In the main environmental case to have been decided by the

Kenya Courts, Wangiri Maathai Vs. Kenya Times Media Trust.113

a public spirited individual attempted to stop, what she

saw as a blatant violation of the public interest in the113 Nairobi High Court Civil Case No. 5403 of 1989 (unreported).

xcvi

integrity and esthetics of an urban recreation park. The

defendant had set about constructing a proposed 60-storey

building in Uhuru Park. At common Law, this kind of civil

action is pursued by showing some irreparable damage or harm

which is likely to arise to the plaintiff’s detriment.

Maathai’s case failed on the test of Locus Standi. It was

held that for an individual to bring a suit on the proposed

construction he or she had to establish an injury to him,

over and above the injury that would be occasioned to the

general public; and consequently the only person with the

competence to institute such proceedings is the Attorney

General.

Although the decision was not explicit on the question of

whether a private citizen, though having no special interest

in a matter of public interest, can institute proceedings on

an environmental question, one may doubt, in the light of

recent judicial approaches,114 whether a plaintiff can easily

get over the Locus Standi impediment.

However, recent jurisprudence has tended to make a departure

from the traditional doctrine of Locus Standi to enable any

person to sustain an environmental action in the courts of

law, though such a person may not have suffered personal

injury over and above the injury to be suffered by the

general public. The first example was the case of Oposa Vs.

114 For example Kamanda Vs. Nairobi City Council, Nairobi High Court civil case No. 6153 of 1992 (unreported).

xcvii

Factoran115, that raised the issue whether the petitioner

minors had a cause of action to prevent a misappropriation

or impairment of Philippine rainforests. The complaint was

instituted as a taxpayers class suit. It alleged that the

plaintiffs, all citizens of the Republic of Philippines and

tax payers, were entitled to full benefits, use and

enjoyment of the natural resource treasure, that is, the

countries tropical rainforests. The suit was said to be

filed by the petitioners and others equally concerned but so

numerous that it was impracticable to bring them all before

the court. The minors asserted that they represented their

generation as well as generations yet unborn. They sought

orders to cancel all existing timber license agreements.

The defendant sought a dismissal of the suit on the grounds

first that there was no cause of action as the petitioners

had not alleged a specific legal right violated by the

respondent, and secondly that the issue raised was a

political question which properly pertained to the

legislature and judicial branches of government. But the

petitioners asserted that granting timber license

agreements to cover more areas for logging than what was

available was a judicial question of discretion.

The court held that the case was a class suit as the subject

of the complaint was of common and general interest not just

to several but to all citizens of the Philippines.

115 GR No. 101082, July 30 1993 (Philippines)

xcviii

Consequently, since the parties were so numerous, it was

impracticable, if not impossible to bring all of them before

court. That the plaintiffs were numerous and representative

enough to ensure the full protection of all concerned

interests. The court held further that the petitioners

could for themselves, for others of their generations and

for succeeding generations file a class suit. Their

personality to sue on behalf of succeeding generations could

only be based on the concept of intergenerational

responsibility so far as the right to a balanced and

healthful ecology was concerned. The court held also, that

the complaint focused on one specific fundamental legal

right, the right to a balanced and healthful ecology, which

was incorporated in the Philippines constitution.

In the Bangladesh case of Dr. Moliuddin Faroque Vs.

Bangladesh116 the appellant was the secretary General of the

Bangladesh Environmental Lawyers Association (BELA), an

organisation working in the field of environment and

ecology. The court held that it was an aggrieved person

because the cause it espoused, both in respect of

fundamental rights and Constitutional remedies, was a cause

of an indeterminate number of people in respect of a subject

matter of public concern. Further, the organisation was

acting bonifide and did not seek to serve an oblique purpose.

However, the court rejected the submission that the

116 Civil Appeal No. 24 of 1995, 17 BLD (AD) 1997, Vol. XVII, Pg 1 to 33.

xcix

Association represented not only the present generation but

also the generation yet unborn. It stated that his finding

in the Oposa case117 had been based on Constitutional

provisions in the Philippines, which did not exist in the

Bangladesh constitution.

In the European case of Regina Vs. I.R.C Exparte. Federation

of Self-Employed,118 Lord Diplock said,

“It would, in my view, be a grave lacuna

in our system of public law if a

pressure group, like the federation or

even a single public spirited tax payer,

were prevented by out-dated technical

rules of Locus Standi from bringing the

matter to the attention of the court to

vindicate the rule of law and get the

unlawful conduct stopped.”

In Tanzania, in his rather politico-judicial reasoning to

support public interest litigation on behalf of the poor,

indigent and unprivileged members of the Tanzanian Society

by Public spirited organizations, Rukangira J. of the High

Court of Tanzania (as he then

was) had this to say in the case of Rev. Christopher Mtikill

Vs. The Attorney General,119

117 Oposa Vs Vactoram (Supra)118 [1982] A.C 643119 Tanzania High Court Civil Suit No. 5 of 1993 (unreported)

c

“The relevance of public litigation in Tanzania cannot be

over-emphasised having regard to our social-economic

conditions, these developments promise more hopes to

our people than other strategy currently in place. First of

all, illiteracy is still rampant. We were recently told that

Tanzania is second in Africa in wiping out illiteracy but

that is a statistical juggling, which is not reflected on the

ground. If we were that literate it would have been

unnecessary for Hanang District Council to pass by-laws

for compulsory adult education which were recently

published as Government Notice No. 191 of 1994. By

reason of this illiteracy a greater part of the population is

unaware of their rights, let alone how the same can be

realized. Secondly Tanzanians are massively poor. Our

ranking in the world on the basis of per capita income has

persistently been the source of embarrassment. Public

interest litigation is a sophiscated mechanism, which

requires professional handling. By reason of the limited

resources, vast majority of our people cannot afford to

engage lawyers even where they are aware of the

infringement of their rights and the perversion of the

constitution. Given all these and other circumstances, if

there should spring up a public spirited individual and

seek the courts intervention against legislation or actions

that pervert the Constitution, the court, as guardian and

trustee of the Constitution and what it stands for, is under

an obligation to rise-up to the occasion and grant him

standing.”

ci

My understanding of Rukangira J.’s lengthy statement is that

the interest of public rights and freedoms transcend

technicalities, especially as to the rules of procedure

leading to the protection of such rights and freedoms.

The emerging jurisprudence that tends to abandon the archaic

principle of Locus Standi is being facilitated by modern

concepts or norms of customary international law such as

“Common Heritage of Mankind,” “Intergenerational equity” and

the “Public Trust Doctrine.” The more recently treaty

generated custom of the “Common Heritage of

Mankind” Stipulates:“The purpose of human Society must be realised and protected with the

welfare of the well-being of every generation. This requires sustaining

the life support system of the planet, the ecological process and the

environmental conditions necessary for healthy conditions necessary for

healthy and decent human environment.120 “

There is a theory that the future generation cannot be

indifferent about whether it is they or other persons who

will enjoy the fruits of the earth. That if we feel we owe

an obligation to them, we too cannot be indifferent about

the question. We cannot discharge our obligations to them

if in the process of doing so we deprive them of life.121

120 Weiss, The Planetary Trust: Conservation and Intergenerational Equity, 11 EcologyLD (1984) 495.121 Agora : What obligations does our generation owe to the next? An approach to GlobalEnvironment Responsibility, 1990 Pg. 2.

cii

The other concept is the “Public Trust Doctrine” which

primarily rests on the principles that resources like air,

sea, water have such importance to the people as a whole

that it would be wholly unjustified to make them a subject

of private ownership and must be protected among other ways

of seeking permanent injunctions in law suits.122

In Uganda, the Constitution123 has made tremendous efforts in

relation to enforcement of environmental rights by doing

away with the traditional concept of Locus Standi. It

provides124 for a right of every Ugandan to live in a clean

and healthy environment as a

human right. This right is enforceable under Article 50 of

the Constitution, which provides; “Any person who claims that a fundamental or other right or

freedom guaranteed under this Constitution has been infringed or

threatened, is entitled to apply to a Competent Court for redress

which may include compensation”

It is further provided that any person or organisation may

bring an action against the violation of another person or

group’s human rights125

This article126, therefore, apart from providing for the

enforcement of the Bill of rights through the Courts,

confers, in Uganda for the first time, Locus Standi to third

122 Joseph L. Sax “Public Trust Doctrine in Natural resources Law. Effective Judicial Intervention” Michigan Law Review Vol. 68 part 1 Pg. 47.123 Uganda Constitution 1995.124 Ibid Art. 39125Ibid, Article 50 (2)126 Ibid,Article 50

ciii

parties to seek reinforcement of the right. At least three

very important concepts seem to arise out of this

Constitutional development. Firstly, the Constitution

elevates matters relating to the environment to human

fundamental rights, which are also justifiable as such.

Secondly it does away with the traditional concept, in

common law jurisdictions, of Locus Standi. Thirdly it

introduces the concept of class suits already discussed

above.127

Despite these enabling and revolutionary provisions the high

court in Uganda has gone a head to make blunders thereby

stifling the development of jurisprudence in the field of

environmental rights. In the case of Byabazaire vs. Mukwano

Industries128 the plaintiff sued the defendant on account of

the escape of obnoxious, poisonous, repelling smoke that was

escaping from the defendant’s factory and into the

neighbouring areas including Kibuli Hill where the plaintiff

resided. The plaintiff brought his action under S. 4(2) of

the National Environment Statute129. An application was

filed by the Defendant to have the plaint struck out on the

grounds, inter alia, that the plaintiff had no locus standi.

The learned judge upheld the objection and ruled that

although the National Environment Statute 1995 gave every

127 See Oposa Vs. Factoram, opcit Note 4128 H.C.C.S NO. 466 of 2000.129 National Environment Act (Cap.153) Laws of Uganda, 2000..

civ

Ugandan a right to clean and healthy environment, it was

only the National Environmental Management Authority (NEMA)

that was vested with the power and duty to sue for the

violations committed under the statute. It was further

ruled, that in the absence of any standards on air quality

set by NEMA, it was not possible to determine that the

plaintiff’s right to clean air was infringed. The action

was accordingly dismissed with costs.

On many counts, this is an unfortunate decision. The right

to a clean and healthy environment is enshrined in the

Constitution and in the National Environment Statute.

According to the decision, that right is only actionable by

NEMA and the Local Environment Committee, and the offended

party can only inform those said authorities. This

reasoning runs against the basic tenets of law; there is no

right without a remedy. If an individual is given a right

by law, he must have the means to enforce that right. Not

only does NEMA lack the necessary resources to file the

requisite actions countrywide, but also the local

environment committees had never been set up 6 years after

the statute was passed. Further, NEMA has discretion under

S. 4(2) of the Statute and cannot be compelled to do so by

any suffering Ugandan.

With the above enabling provisions of the law what remains

is to sensitize the Ugandan Law practitioners to prepare

them to respond appropriately the growing of environmental

cv

challenges. The judicially should respond to this trend by

re-fashioning legal, sometimes age-old, tools to meet the

demands of the times.

Uganda Courts have, to some extent, responded positively to

this trend and have properly dealt with old technical rules

such as the one of Locus Standi. For example in the recent

case of Siraji Waiswa Vs. Kakira Sugar Works Ltd.130 where

the plaintiff/applicant, on his behalf and on behalf of

other peasant farmers of Butamira Forest Reserve, filed a

suit against the defendant/respondent who on diverse dates

entered the disputed forest reserve and uprooted the forest

to establish a sugar cane plantation.

Before the suit was heard, the applicant/plaintiff filed an

application seeking a temporary injunction against the

respondent to restrain its servants or agents from evicting,

intimidating, threatening or in any way interrupting or

destroying the plaintiff’s and other resident’s use and

occupation of Butamira Forest Reserve until the disposal of

the main suit or until further orders of the court. It was

further contended on behalf of the plaintiff that the

destruction of the suit property would render the suit

nugatory and result in irreparable damage to the

environment.

Court held that this was a matter to do with the alleged

destruction of the environment. As far as the individual

130 High Court Miscellaneous Application No. 23 of 2001, arising from Civil Suit No. 69/2001.

cvi

interest is concerned, damages would be appropriate.

However,

Court went on to say, a matter to do with the destruction of

the environment would affect not only parties to this suit

but also the current generation and generations to come.

That damages to the applicant alone would not remedy the

injury to mankind as a whole. Court therefore; found that

the damage complained of was of a material nature, which

would not adequately be compensated by an award of damages

alone.

Court went ahead to grant the remedy sought and order the

restraint on the part of the defendant from uprooting the

forest to establish a sugar cane plantation during the

pendency of the main suit. The defendant was also

restrained from evicting, intimidating, threatening or in

any way interrupting the status quo during the pendency of the

main suit or until a lasting solution shall be provided by

Government, whichever comes first.

Another case in which Court has been vigilant is the case of

The Environment Action Network Ltd Vs. the Attorney General

& NEMA,131 where the applicant, a public interest litigation

group, brought the application bonafide in its own behalf

and on behalf of the non-smoking members of the public under

Article 50 (2) of the Constitution to protect their rights

to a clean and healthy environment, their right to life and

131 High Court Miscellaneous cause No. 39 of 2001.

cvii

for the general good of the public health in Uganda. The

applicant sought a declaration first, that smoking in public

place constitutes a violatation of the rights of non-smoking

members of the public to a clean and healthy environment as

prescribed under the Constitution of the Republic of

Uganda132 and the National Environment Statute, 1995.133

Secondly, that smoking in a

public place constitutes a violation of the rights of non-

smoking members of the public to the right to life as

prescribed by the Constitution of Uganda.134 The applicant

further sought an order that the second respondent takes the

necessary steps to ensure the enjoyment by the Ugandan

public of their right to a clean and healthy environment.

At the hearing of the suit the Attorney General raised

preliminary objections among which was the objection that

the suit did not comply with the Government Proceedings

Act135 which requires the Attorney General and scheduled

corporations, including NEMA to be given a notice of

intention to sue of 45 days before a suit is filed against

them. Court overruled this objection and held that

applications brought under Article 50 of the Constitution

are governed by the Fundamental Rights and Freedoms

(Enforcement Procedure) Rules.136 That although Rule 4137

132 The Constitution, Opcit, Article 39133 Section 4134 Article 22135 Cap.77 Laws of Uganda, 2000, S.1136 S. 1 No. 26 of 1992137 Ibid

cviii

provides that no motion (under Rule 3) shall be made without

notice to the Attorney General and any other party affected

by the application, Rule 7138 clearly stipulates that

“Subject to the provisions of these Rules, the Civil

Procedure Act and the Rules made thereunder shall apply in

relation to application”.

Applying the so called “golden rule” of the Statutory

interpretation, the judge went ahead to say, we would be

wrong if we assumed that besides Rule 7139 Parliament meant

that any other rule of procedure should be applied. That it

is for this reason that applications

pursuant to Article 50 of the Constitution must be strictly

restricted to the Civil Procedure Act140 and the rules

thereunder and not under S.1 of the Government Proceedings

Act.141 That the Attorney General and NEMA in this

application therefore, got the notice they are supposed to

get.

Citing a decision to in Indian case,142 the learned judge

said that the rationale of the notice to be given to the

State is that the Government needs sufficient period of time

to investigate a case intended to be brought against it so

as to be able to avoid unnecessary expensive protracted

litigation. That this rationale cannot apply to a matter

138 Ibid139 S.1 No. 26of /92140 (Cap. 71) Laws of Uganda, 2000 Revision.141 (Cap 77) Opcit142 RAYABAI VS. STATE, AIR [1973] BOM. 61

cix

where the rights and freedoms of the people are being or are

about to be infringed. The people cannot afford to wait for

45 days before pre-emptive action is applied by court. They

would need immediate and urgent redress. They need a short

period which is the one provided under the ordinary rules of

procedure provided by the Civil Procedure Act and its

Rules143. That to demand from the aggrieved party a 45 days

notice is to condemn them to infringement of their rights

and freedoms for that period which this court would not be

prepared to do. That any alleged infringement must be

investigated expeditiously before damage is done.

Another preliminary objection raised by the learned State

Attorney on behalf of the Attorney General and NEMA is that

the applicant cannot claim to represent the Ugandan Public

(non-smoking Public), and that they should have made an

application under 0.1 rule 8 of the Civil Procedure Rules

for permission to file a representative suit.

Court held that the state Attorney failed to distinguish

between actions brought in a representative capacity

pursuant to Order 1 Rule 8 of the Civil Procedure Rules and

what are called Public interest litigations, which are the

concern of Article 50 of the Constitution and S.1 No. 26 of

1992. That the two actions are distinguishable by the

wording of the enactments or instruments to which they are

instituted. The judge concluded, citing the case of Regina

143 Civil Procedure Rules S.I – 65-3.

cx

Vs. I.R.C Exp. Federation of self-Employed144, that an

organisation can bring a public interest action on behalf of

groups of individual members of the public even though the

applying organisation has no dire individual interest in the

infringing acts it seeks to have redressed. The preliminary

objections of the respondent were over ruled.

These decisions are a clear indication that there is a

positive step in the direction of a revolutionary judicial

system and justiceability of environmental rights.

5.4 LITIGATION ON EIA

As earlier on pointed out145, in Uganda it is still difficult

for the general public to use civil litigation as a device

of environmental management. It is high time the Ugandan

public got sensitised to civil litigation and most

especially judicial review as a remedy of correcting

environmental wrongs and particularly wrongs committed in

EIA process. Judicial review is a remedy under both statute

and the common law. It may be awarded where a public body

has acted beyond its legal powers, where it has acted

contrary to the principles of natural justice or where it

has acted in error of law.

The National Environmental Statute146 provides for appeals

against decisions made by the Authority but the appeal has

to be made within the structure of the Authority in

144 [19982] AC 643145 Page ----- (ante)146 ( Cap. 153) Opcit

cxi

accordance with administrative procedures to be

established147. Such decisions shall not be called into

question by any court but the High Court’s Supervisory

jurisdiction is maintained148. This means that any decision

made by NEMA may be subjected to judicial review not

withstanding that it had been a subject of an appeal within

NEMA’s administrative structures

In other jurisdictions there have been vigorous litigation

against decision-making bodies in respect of Environment

impact Assessment. Courts in those jurisdictions have

dealt with questions to do with the role of the respective

agencies in evaluating the EIA report and the quality of the

EIA reports.

The first judicial decision to deal with the quality of an

EIA report was in the USA in the case of Sierra Club Vs.

Coleman.149 The case arose as a result of the plan by the

Department of transport and the Federal High way

Administration to construct the “Darien Gap Highway” through

Panama and Colombia to link the Pan American Highway System

of South America with the Inter-American Highway. In April

1974, well after the project was underway and well after the

selection of the precise route of the Highway had been made,

the Federal Highway Administration (FHWA) prepared and

circulated to certain parties a draft Environmental Impact147 Ibid S. 105148 Ibid S. 105 (b).149 XV/6 ILM 1425 (USA)

cxii

Assessment. In December 1974 it issued a final assessment.

The Sierra Club and three other environmental organizations

sought to enjoin any further action on the project, claiming

that the preparation and issuance of the assessment

satisfied neither the procedural nor the substantive

requirements of NEPA.

The court found that there were three deficiencies in FHWA’s

compliance with NEPA requirements. First, FHWA failed to

circulate either its draft or final assessment to the

Environmental Protection Agency for its comments. Second,

the assessment failed to discuss the problems of the

transmission of aftosa, or foot and mouth disease, the risk

of which was recognized if a stringent control programme was

not in place. Thirdly, the assessment failed adequately to

discuss possible alternatives to the route that had been

chosen.

The section on the alternative routes was developed to an

analysis of why the shorter route was preferable to the

longer route from the point of view of engineering and

costs. It had no discussion of environmental impact of

possible alternatives to the route was actually selected.

The court found that the assessment was not an adequate

environmental impact statement. Indeed, the court observed

that the decision to build the highway on the chosen route

had been made well before the statement was begun. The

cxiii

court enjoined further work on the project until such a time

as compliance with NEPA had been effected.

In Sierra Club V. United States Army Corps of Engineers150

plaintiffs challenging plans to construct the Westway, a

super highway that would run along the Westside of

Manhattan, argued that the final EIS was deficient because

it characterized an area of the Hudson River that the

project would fill as a “biological wasteland,” despite data

indicating the presence of a juvenile striped bass

population there. Environmental Protection Agency, the

National Marine Fisheries Service and the Fish and Wildlife

Service all had objected to the EIS and the Corps’ decision

to issue a permit to fill the area. Despite a new study

finding that fish populations were much richer that

previously thought, no supplemental EIS was prepared. After

holding a trial that heard extensive testimony concerning

how the EIS was prepared, the federal district court

enjoined the project pending preparation of a supplemental

EIS, a decision which was upheld on appeal by the second

circuit.

In Uganda, few Court cases have come up to challenge certain

decisions in the EIA process. In the year 2000 two

environmental activist non-Governmental Organisations, that

is, Green Watch and Advocates Coalition for Development and

150 701 F. 2d 1011 (2Cir. 1983) Cited in, Percival: Environmental Regulation, Law, Science and Policy, 3rd Edition, ASPEN LAW & BUSINESS, NEW YORK, 2000.

cxiv

Environment (ACODE) filed a suit in the High Court against

Golf Course Holdings Ltd, a Company that set out to

construct a Hotel complex at the Golf Course on Kitante Road

in Kampala151. The plaint alleged that the defendant carried

out an Environment Impact Study outside the law and as such

no Environment Impact Study was legally conducted. It was

further alleged that NEMA purported to approve an EIA

without following the law and that it was specifically in

contradiction of S. 37 of the Statute152 and Regulation 19 of

the Regulations153. That the purported Environment Impact

Study did not address the issue of wetland and NEMA

therefore, failed its statutory duty when it gave the

approval. That the National Wetlands conservation and

Management Programme found that the development of the

project was harmful to the environment but NEMA went ahead

to give it approval despite the programs opinion as a Lead

Agency.

The Plaintiffs contended that the development of the project

would increase flooding in the city by blocking the water

channel along the course drainage system, which would be a

danger to human life and a threat to property. That the

construction of the Hotel would destroy the wetland and as a

result increase siltation and eutrophication of Lake

Victoria. It was further contended by the plaintiffs that151 Green Watch & Another Vs. Golf Course Holdings Ltd HCCS NO. 834/2000152 Cap. 153, Opcit.153 EIA Regulations, 1998

cxv

the construction of the Hotel would destroy the green

scenery of the city and deprive it of the environmental

services that naturally accrue for proper environmental

stewardship.

Meanwhile the construction of the Hotel was going on and the

plaintiffs applied for an injunction to restrain the

defendant from further construction until the main suit is

disposed off154. However this application for an injunction

was dismissed on the ground that the applicants would not

suffer irreparable damage because they do not have any

proprietary interest in the suit property. That the public

whom they seem to represent shall not suffer any irreparable

damage. That even if the damage is caused, this could be

put right under the provisions of S.68 of the National

Environment Statute 1995. S. 68 provides for restoration

orders.

With due respect to the learned judge, the ruling was a bad

one. It was based on the usual technicalities of civil

procedure, which would not readily conform with the case at

hand because of its peculiarities. Environmental damage

should be distinguished from any other type of damage. Once

environmental damage has occurred it cannot be readily

remedied. Reference to an irreparable loss, which is a

condition for granting an injunction means the kind of loss,

which cannot be atoned by an award of damages. Indeed the

154 High Court Miscellaneous Application No. 390/2001

cxvi

damages, which would be caused by the continued construction

of the Hotel project, would not be remedied by an award of

damages. This is because the cause of action in the main

suit was that the Environment Impact Study did not follow

the correct procedures and as a result certain vital

environmental aspects were not taken into account.

The consequence of this would then be increased flooding in

the city by blocking the water channel, destruction of the

wetland leading to increased siltation and eutrophication of

the lake and the destruction of the green scenery of the

city. An award of damages would not remedy this kind of

environmental damage. The restoration under S. 68 of the

statute proposed by the judge has nothing to do with

environment Impact Assessment. Once the construction of the

Hotel proceeds to completion there can be nothing to

restore. The damaged environment would not be restored to

its original position. Restoration orders under S. 68 of

the Statute have got a different objective altogether from

the aims of conducting an EIA.

Consequently the application for an injunction was not

granted and the construction of the Hotel proceeded to its

completion on an inadequate Environment Impact Study. The

main suit has therefore not been decided, and even if it is

to be decided now or later, the outcome would be nugatory.

This kind of attitude of the judges cannot easily develop a

jurisprudence that is instrumental in challenging defective

cxvii

decisions in the EIA process or generally enforce

environmental management laws with modern legal principles

that are quite unique.

The judicial officers have to confront this by refashioning

legal, sometimes age old tools, to meet the demands of the

times. In the USA, such jurisprudence has been developed.

This is evidenced by for example in the Sierra Club Vs.

Coleman155 where court enjoined further work on the project

(Fedro High Way Project) until such a time as compliance

with NEPA had been effected. The projects Environment

Impact Study had not complied with the requirements of NEPA.

Another suit ever brought in Uganda in regard to Environment

Impact Assessment was National Association of Professional

Environmentalists (NAPE) Vs. AES Nile Power Ltd 156 where the

applicant sought a temporary injunction to stop the

respondent from concluding the power project agreement with

the Government of Uganda until NEMA has approved an EIA on

the project. The motion further sought declarations that

such approval of the EIA is a legal prerequisite and that

any endorsement of the project by Parliament without this

EIA approval would contravene the law.

Court held that the applicant had reason to seek the

intervention of this court in so far as no approval of the

environmental aspects of the study has been brought in

evidence to satisfy the requirements of S. 20 (b) of the

155 Already discussed above.156 Miscellaneous Cause No. 268 of 1999.

cxviii

National Environment Statute. Court went on to stay

however, that the challenge was made quickly and prematurely

because no agreement has been signed and if it is signed and

it is in contravention of the law then it can be challenged.

It is however, not for this court to stop the signing of the

agreements by injunctions or other wise since signing

agreement per se does not cause environmental disasters.

The injunction was therefore refused but court made a

declaration that the approval of the Environmental Impact

Statement is required under S. 20 of the Statute157

5.5 ATTORNEYS FEES

Public interest advocates lack the investigative and

financial resources of industry and government to enable

them pursue legal actions against decision makers in

environmental matters who are either government or public

environmental management bodies that have all the resources

at their disposal.

Secondly, public interest individuals who would wish to

challenge decisions adversely affecting environment

management and natural resource uses lack the motivation.

This is because in most cases the party seeking to challenge

the unlawful conduct seeks injunctive relief other than

damages. Such party therefore, stands to gain nothing in

whole process of litigation, which is even costly.

157 (Cap.153) Opcit

cxix

It is therefore, important that some mechanism in form of a

law or regulation to ensure that a public interest advocate

is awarded costs that would be awardable in an ordinary suit

where the party has vested interest. This will provide the

motivation to public-spirited individuals or groups to

initiate legal proceedings in a bid to protect the

government.

CONCLUSIONEnvironmental litigation is important tool that can be used

to check the excess abuse of power by the decision-making

organs in EIA process. In Uganda , However, this is

hampered by constraints in the litigation process as seen

above. Nevertheless, following the promulgation of the

Constitution 1995 with its emphasis on public rights and

their enforcement, the judiciary is slowly being sensitized

to do away with the aged and outdated principles of civil

litigation so as to meet the demands of the times. Thebest

examples of this development are, the suit on behalf of non-

smokers158 and the Butamira case159 already discussed above.

CHAPTER SIX

CONCLUSION AND RECOMMENDATIONS

6.1. EIA PRACTITIONERS158 The Environmental Action Network Ltd Vs. the Attorney General & NEMA : Opcit159 Siraji Waiswa Vs. Kakira Sugar Works Ltd: Opcit

cxx

As earlier on pointed out, the responsibility of carrying

out an EIA lies with the developer. It is the developer who

bears the cost of the assessment and the assessment is

conducted by the technical experts approved by the Authority

(NEMA). These experts are still few and have not yet

developed the necessary competence.

However, in few years very many consultants, who claim to

conduct EIAs, have come up. Most of these have registered

with NEMA so that they are easily identified in case they

are needed. A number of firms both local and international

have registered with NEMA so that when an investor comes in

the country and needs some one to carry out an EIA, NEMA can

easily identify such consultant depending on the area of

specialization. For example some firms are good specialists

in the water sector, others in mining, some in industry and

so on. So, by registering, NEMA is able to identify an

appropriate firm of consultants for a sector specific type

of development.s

This is because most of the investors who come into the

country do not know which EIA consultants are specialists in

what area, and the consultant in most cases do not know that

there are some investors who need EIA consultancy services.

NEMA therefore acts as an intermediary between the

developers and the EIA practitioners.

That,EIA practitioners have decided to form an association

which is currently headed by Dr. Patrick Mwesigye of

cxxi

Chemistry Department of Makerere University who also owns a

consultation company by names of Enviro and Industrial

Consult (U) Ltd. This association is supposed to bring all

the EIA practitioners together and to ensure that they

conduct themselves in a professional manner.

EIA being a new area, there are efforts to build capacity

through long practice. The EIA practitioners are now quite

many and are competing. There is no code of conduct for EIA

practitioners yet, but NEMA is making effort to develop one.

NEMA has invoked the provisions of S. 108 of the National

Environment Statute, 1995 to up a code of conduct, which

shall be given the force of law as a statutory Instrument to

regulate practioners. NEMA has therefore come up with the

“Environmental Impact Assessment and Environmental Audit

(Practice and Practitioners Code of conduct) Regulations

which is still in a draft form. The draft is now with the

first parliamentary Counsel.

The objectives if these regulations shall be to provide a

system of professional conduct and ethics in the carrying

out of the environmental impact studies and audits. The

regulations shall also ensure that the practice of

conducting environmental impact assessments or audits are

carried out in an independent and impartial manner. The

Regulations are also made to provide for the control of the

professional conduct of practitioners and for maintenance of

consistence integrity, registrations, certification and

cxxii

standardisation of the practice of the conducting

environmental impact assessment and environmental audits.

It is hoped that when these regulations come into force

most of the shortfalls on the EIA process shall be

eliminated and the EIA law shall be able to achieve its

designed objective of promoting environmental

sustainability.

6.2 DEVELOPERS ATTITUDE ON EIA

The EIA concept in Uganda was received with mixed feelings

especially on the part of the developers or investors. Most

developers look at the EIA process as an additional

exercise, which is a time wasting and additional cost to the

project. Most of them make efforts to dodge and where that

is not possible they conduct it merely for purposes of the

approval of their projects. That is why most of them select

cheap consultants who do a poor work that would be used only

to seek NEMA’s approval of the project.

However, there are some serious investors who, over time,

have come to appreciate the importance of conducting an EIA.

These ones are able to appreciate the beneficial effects of

an EIA to the feasibility of the project. They are able to

appreciate the fact that environmental impacts have got

costs, which shall form an integral part of the total

project.

Therefore, if EIA does not form part of the feasibility

study of the project the other studies undertaken on

cxxiii

financial, economical and technical matters will not be

sufficient to determine the viability of the project. Hence

the developers are likely to lose in case adverse

environmental impacts turn out to be costly.

The trend however, shows that there is growing

environmental awareness of this fact and most of the

developers are beginning to take the EIA exercise

seriously.

6. 3 ENVIRONMENTAL AUDITS

All developers whose projects have been subjected to the EIA

studies are supposed to ensure that mitigation measures and

actions as approved through the EIA to protect the

environment are adopted and implemented. The developer does

this through self-monitoring, self-record keeping and self

reporting and making available all the information for

inspection by the Lead Agency or the Authority. The work of

the inspection is done by Environmental Inspectors160. NEMA

has, by Legal Notice No. 1 of 2002 appointed Environmental

Inspectors for a period of 2 years161. These Legal Notices

have appointed 108 environmental inspectors divided up in

sectors, for example health and product safety, industry and

occupational health, water resources, chemical safety and

transboundary issues, Forestry and Agriculture, Mining and

Urban environment. These inspectors are supposed at all

160 Cap. 153, Opcit, S. 80.161 The National Environment (Designation of Environmental Inspectors) Notice 2002.

cxxiv

reasonable times, to enter on any land, premises or other

facilities related to a project for which EIA has been done

to determine how far the predictions made are complied with.

However, it is still difficult for these inspectors to go

around all the projects in the country to carry out

inspections. There are no sufficient facilities to do this.

There is limited funding. There are therefore, a lot of

hardships on the inspectors to monitor all the projects.

The situation becomes even more serious with projects which

had been implemented before EIA was a legal requirement and

which are supposed to conduct self-auditing & monitoring.

It is therefore recommended that funding for these

activities be increased.

6.4 OTHER CHALLENGES

There is a lot of bureaucracy in the process and this causes

a lot of delays in the timings up to when the approval of

the project is made. As a result, developers are delayed

which causes them to lose time and money. For example in

the Regulations162, the Executive Director is supposed to

transmit a copy of the project brief to the lead agency for

comment within seven working days of receiving the project

brief163. Then the lead agency is supposed to make comments

and transmit them to the Executive Director within fourteen

working days of receiving the project brief164. Due to the

162 EIA Regulations, 1998163 Ibid, Regulation 6 164 Ibid, Regulation 7.

cxxv

bureaucracy in the Authority or the lead agencies, most of

which are government departments, these timings are not

likely to be met.

Another problem is lack of sufficient funding which hinders

the proper functioning of most of these organs. NEMA and

the lead agencies are not well facilitated to effectively

perform their duties in the EIA process and most especially

the monitoring aspect of it as already seen above.

Otherwise the general performance of the EIA process is good

and it will grossly improve with time. There is however,

need for the lead agencies to be vigilant.

6.5 EIA ON POLICIES AND PROGRAMMES

EIA is more often associated with development projects

rather than policies and programmes such as tourism

development, water resources development, urbanization,

agriculture, forestry and industrial development, to mention

but a few.

Policy EIAs present an opportunity to examine the

environmental implications of national and regional

development policies and proposals before decisions are made

to implement specific projects conceived under the broad

policies. EIAs conducted on policies contribute

significantly to harmonization of different sectoral

policies and remove unwanted policy aspects.

There is therefore, a need of extending EIA beyond physical

development projects to include policies (including draft

cxxvi

legislation), plans and programmes. In the United States

for example, the mandate to carry out EIA goes beyond

development projects, to policies and even proposals for

legislation or even international or regional agreements,

treaties and conventions that are thought to have an impact

on the environment of the State165.

For example there have been a debate in Uganda as to whether

genetically modified products or organisms should be

imported into the country. The proponents of this

debate maintains that genetic engineering brings enormous

benefits, in that it produces high quality and quantity

yields. On the other hand the opponents of the policy

contend that the consumption of these products cause health

hazards.

It is therefore important that the Ministry of Agriculture,

Animal Industry and Fisheries carries out an EIA on the

policy of bringing genetically modified products and

organisms into the country.

It is hence recommended that the law on the requirement of

EIA be extended to include policies, plans and programs and

once this is done the task of carrying out EIAs for projects

within the broad policies for which policy EIA has been

conducted, shall be lessened. For example if an EIA had

been conducted on the energy policy in the country most of

the controversies on whether hydro power is the most viable

165 See: Public citizen Vs. Office of the USTR: 970 f.2d 916.

cxxvii

alternative as opposed to geothermal energy would not have

arisen.

6.6. TOWN AND COUNTRY PLANNING

Though the construction of residential houses does not

require EIA according to the Ugandan law on EIA166, something

needs to be done to deal with the rampant random

construction work within the urban centers, which has become

a threat to life and property. Most areas in the urban

centers lack access roads, drainage systems and generally a

less impressive sight despite the beautiful houses that lie

behind the parameter walls. Developers appear not to take

care of the infrastructure around them.

This is largely responsible for the sprawling slums that co-

exist with posh houses. For most of these areas there are

no access roads and whenever the sewerage system has been

broken down it is difficult to fix because someone has built

on top of the terminals

There are two major problems that have aggravated this

situation. The internal and external mechanisms, which

include poor implementation of the existing town and urban

development plans by the planning agencies, relevant

institutions and the developers, is one reason for this poor

state. Secondly, the obsolete unharmonised laws that are

still applied today.

166 3rd schedule to National Environmental Act, Opcit.

cxxviii

The Town and Country Planning Act (Cap. 246) has been

overtaken by events. The law in its current form does not

match the present rate of development and needs review to

suit current planning requirements. The department of

physical planning has in corroboration with the Ministry of

Local Government started work on reviewing the Town and

Country Planning Act, so that it is in harmony with other

laws and policies that have already been harmonized. Some

of these are the Land Act (Cap.227), Local Government Act

(Cap.243), National Environment Act (Cap.153), Condominium

Law, Wetland Policy 1997 and others which need planning and

Speed up development.

The problem is that the development is so rapid that it

precedes the plans that some structures have to be broken

down to create room for infrastructures like roads and

sewerage systems.

Some areas in Kampala are in the valleys some of which were

wetlands before houses were constructed there. Some of

these areas are like Nateete, Bwaise, Mengo Kisenyi, Katwe,

Lower Ntinda , Nalukolongo. Developments in these areas

were carried out long before there was a wetland policy in

place. When Kampala receives heavy rains all these areas

get flood and residential houses are submerged in water

leading to loss of life and property.

For example there was a heavy downpour on the night of 27th

April 2003 and all flood prone spots in and around Kampala

cxxix

drenched. More than seven houses at the Ntinda Stretcher

area were filled with water up to the window level from the

wetland that drains Ntinda and Kyambogo areas. Police fire

brigade reportedly made responses to a number of areas that

were affected by the rampaging waters in different parts of

the city. It was reported that a man whose identities could

not be got was swept away by the water.167 The area around

the clock tower near fire Brigade headquarters was not

spared despite the nearly completed works on the Nakivubo

channel around the place.168

There is therefore, a need to redesign the city and to have

the national urbanization policy, which could address issues

like urban renewal, redevelopment, and inner city

development urban design principles to ensure smooth

development. All these policies and principles should be

reflected in the reviewed Town and Country Planning Law with

an emphasis to Environmental Impact Assessment. The result

will then be that although ordinary residential houses would

not require an EIA, if a residential building is to be put

up in a low land like some of the areas mentioned above, the

developer should be required to conduct an EIA that will

disclose sufficient mitigation measures to avert the threat

of floods and other disasters.

167 New Vision, Monday, April 28, 2003 Page 1168 Ibid, P. 2

cxxx

6.7. AWARENESS AND SENSITISATION

During this research it was evident that most people

especially the potential developers take EIA as a time

wasting exercise, which does not have any benefits. Others

and most especially the so-called Environmental activists

believe that any project which has some negative impact on

the environment, should no be allowed to proceed. They do

not know that costs of environmental degradation are

supposed to be weighed against economic benefit to be

derived from the project in order to determine the viability

of that project. Most activists, who have criticized the

approval of projects where EIA has been undertaken, suffer

from the very problem of failing to appreciate the essence

of EIA.

It is therefore, recommended that an awareness and

sensitization campaign on EIA be launched to educate the

public and decision makers about EIA and its necessity. The

sensitization and awareness campaign should mostly target

district officials who play a major role in licensing most

development projects in their areas of administration. The

second category to be targeted by this EIA awareness

campaign would be lead agencies because they have a big role

to pay in the EIA process.

Specialized education should go to financial institutions

such as banks because they finance most, development

projects by providing loans. It should be brought to the

cxxxi

knowledge of these financial institutions that a development

project, which has got significant impacts on the

environment, is also not economically viable and the end

result will be failure to repay the loan that will have been

secured to finance the project. The loser shall be the

financial institution. After financial institutions have

been sensitized about the importance of EIA, they will

always make EIA a pre-condition for granting development

loans. This is already being done by multi-lateral agencies

like the world Bank and IMF, and a number of bilateral

donors have visited on EIA as a precondition to aid, either

in form of grants or loans. These include the Danish

International Development Agency (DANIDA), United States

Agency for International Development ((DANIDA), the German

Technical Corporation (GTZ) and so on. Normally these

lenders are required by either their own domestic law to

ensure that EIA is done.

Finally the sensitization on environmental matters in

general and on EIA in particular should be conducted among

lawyers and judges. Enforcement of environmental rights

being a recent development in the country’s judicial system

there is a lot of need for lawyers and judges to adjust in

their enforcement mechanisms of these rights.

6.8. CONCLUSION

Environmental Impact Assessment in Uganda is a recent

development, which is yet to bear fruitful results as far

cxxxii

sustainable environmental management is concerned. The

institutions to handle the process and the necessary legal

framework are in place. What remains is to build the

capacity so that the assessments are efficient.

Capacity building has been taking shape over time and what

is in place now is far much better than what was being done

when EIA was first introduced. The EIAs that are being

conducted tend to comply with the legal requirements and

guidelines, which are in place.

What remains mostly is to sensitize the public about the EIA

concept, and what it is intended to achieve. During this

research it was evident that most people especially the

potential developers take it as a time wasting exercise,

which does not have any benefits. Others and most

especially the so-called Environmental activists believe

that any project, which has some negative impacts on the

environment, should not be allowed to proceed. They do not

know that costs of environmental degradation are supposed to

be weighed against the economic benefits to be derived from

the project in order to determine the viability of that

project. Most activists who have criticized the approval of

projects are Bujagali Hydro Power, Golf Course Hotel,

Namanve and so many others’ suffer from that very problem of

failing to appreciate the essence of EIA.

s

cxxxiii

BIBLIOGRAPHYTexts

1. Ahmed Y.J. and Sammy G.K.: Guidelines to Environmental

Impact Assessment in Developing Countries, Nairobi,

UNEP, 1987

2. Angels F, “Outlines of a critique of Political Economy

“In K. Marx, Economic and Philosophic Manuscripts of 1844,

Foreign Language Publishing House, Moscow, 1959.

3. Bisset R., EIA: Issues Trends and Practice, Environment and

Economic Unit, Nairobi, UNEP, 1996.

4. ECE, Post Project Analysis in EIA, United Nations, New York, 1990

5. EPA, “Best practice in Environmental management in

mining”, Environmental Management and Performance, Canberra,

1988.

6. Frank J. Convery, Applying Environmental Economics in Africa;

World Bank Technical Paper Number 277, Washington, D.C.

African Technical series, 1995.

cxxxiv

7. Graham L. Smith, Impact Assessment and Sustainable Resource

Management, New York, Longman Scientific and

Technical, 1933.

8. Kamugisha, JR: Management of Natural Resources and

Environment in Uganda, Policy and legislation

Landmarks, 1980 – 1990, Danida 1993.

9. Kohler H, Scarcity and Freedom: An Introduction to Economic Health,

Lexington, Mass, 1977.

10. Kurukusuriya, Lal and Yeater Marcel, Environmental

Impact Legislation in Developing Countries, Nairobi,

UNEP, 1987.

11. Larley, MJ and Bustello, ES: Social Impact Assessment

and Monitoring West View, Boulder Co. 1984.

12. McAllister DM, Evaluation in Environmental Planning, London

MIT Press, 1980.

13. McAuslan, The Ideologies of Planning Law, Oxford, Pergamon

Press, 1980

14. Pearce, David W. and R. Kerry Turner, Economics of Natural

Environment. Hartfordshire, England, Harvester

Wheatsheaf, 1990.

15. Percival : Environmental Regulation, Law, Science and Policy,

3rd Edition, ASPEN LAW & BUSINESS, NEWYORK,

2000.

16. Tisdell, CA, Environmental Economics in our Society, Brisbane,

Jacaranda Press, 1979

cxxxv

17. Tisdell, CA, Environmental Economics Cambridge Edward

Elgar, 1993.

18. Tolba (Ed), Evolving Environmental Perceptions: From

Stockholm to Nairobi, London, Butterworths, 1989.

19. UNEP, A Compendium of Judicial Decisions in matters Related to

Environment, National Decisions, Nairobi, UNEP 1998.

20. UNEP, Environmental Impact Assessment: Basic procedures for

Developing Countries, Nairobi UNEP, 1988.

21. Wote GF, The Human Adjustment to Floods, Department of Geography

Reasearch Paper No. 29. University of Chicago, 1945.

Articles and Reports

22. Agora: What obligations does our generation owe to the next? An

approach to global Environment Responsibility, 1990.

23. Development and Environment, World Development Report

1992, World Bank, Washington D.C., 1992.

24. EASNP, Bujagali Hydro electric Power ‘Project Environmental Impact

Statement, Final Report, WS Atkins International Ltd,

1999.

25. Environmental Law Institute, The role of the citizen in

Environmental Enforcement (ELI working paper, August 1992)

26. George C. “Environmental Monitoring, Management and Auditing”

in Lee and George, Environment in Developing and transitional

Countries, New York, John Wiley & Sons, 2000.

27. GOODLAND R, 1996, The Environmental Sustainability challenge for

the hydro industry, hydropower and Dams, Issue 1, 1996.

cxxxvi

28. Government of Uganda: National Environment Management Policy

for Uganda 1994, Kampala, MNR, 1994.

29. IRN, Review of IFC’s Report “Bujagali Project: Summary of

Economic due Diligence” Barkely California November 19,

2001.

30. Joseph L. Sax, “Public Trust Doctrine in natural

Resources Law,” Effective Judicial Intervention, Michigan Law Review

Vol. 68.

31. Ntambirweki, John: Environmental Impact Assessment for Projects

Affecting Coastal and Marine Environment, UNEP Regional Seas

Reports and Studies No. 122, Nairobi, UNEP 1990.

32. Ntambirweki, John: The Framework for Environmental Impact

Assessment in Zambia, a Consultancy Report, Nairobi,

ELI/PAC UNEP, 1993

33. Ojwang J.B with Calestous Juma: (Eds) “Towards

Ecological Jurisprudence” In Land We Trust, Nairobi,

Initiative Publishers, 1996.

34. Sewell, W.R.D (1973) “Broadening the approach to

evaluation in Resource management Decision making”

Journal of Environmental Management 1.33-60.

35. Shearman, R (1990) “The meaning and Ethics of

Sustainability” Environmental Management 14 (1), 1-8.

36. UNCED, Agenda 21 (A report of United Nations

Conference on Environmental Management 14 (i), 1-8.

37. UNEP, Regional Seas Reports and Studies No. 122, Nairobi,

UNEP, 1990.

cxxxvii

38. NEMA, Guidelines for Environmental Impact assessment

in Uganda, 1997.

39. Vanclay S. (2000) “Social Impact Assessment” in Lee and

George, Environmental Assessment in Developing and Transitional

Countries, New York, John Wiley & Sons, 2000.

40. Weiss, The Planetary Trust: Conservation and International Equity, 11

ecology LD (1984) 495.

41. W.C.E.D, Our Common Future (Report of the World

Commission on environment and Development, 1987)

London Oxford University Press, 1987.

42. World Bank Technical Report on EIA for Bujagali Hydro

Power Project, 2001.

43. World Bank, Environmental Guidelines, Washington DC,

World Bank, 1998.

44. World Bank, Environmental Assessment Challenges and

Good Practice, paper No. 018. Environmental Management

Series, Washington, 1995.

News Paper Articles

45. “Golf Hotel Row: A tale of mediocrity”, The New Vision

News Paper, Friday, May 12, 2002 page 2.

46. “Bujagali dam was approved on cooked data”, The Monitor

News Paper Thursday, May 16, 2002.

cxxxviii