Draft Letters
For
FIDIC Design, Build and Turnkey
No. Chart No. Clause Subject
1 3 4.5 Proposal for use of Sub-contractor
2 3; 4 4.11 Unforeseen Conditions
3 3 4.16 Removal of equipment
4 3 4.24 Fossil, coins, etc. – discovery
5 3 4.24 Fossil, coins, etc – delay and disruption
6 3; 9 8.3 Instruction to apply for Extension of Time
7 10 8.8 Consequence of Suspension
8 10 8.10 Prolonged Suspension (Over 84 days)
9 13 10.1 Apply for Taking-Over Certificate
10 13 10.1 Taking-Over Certificate where works in use
11 10.2(b) Interim Application for Payment
12 11 13.3 Specimen Application (4 pages)
13 11 13.10 Statement at Completion
14 11 13.11 Draft Final Statement
15 11 13.11 Final Statement
16 11 13.12 Discharge
17 13.16 Change in Legislation
18 14 16.1 Delayed payment – suspend work/Reduce rate
19 14 16.1 Delayed payment – extra time and costs
20 14 16.2 Employer’s Default – Notice of Termination
21 14 19.3 Notice of Force Majeure
22 14 19.6 Force Majeure – Notice of termination
23 15 20.1 Notice of Intention to Claim extra payment
Draft No.1
Clause 4.5
Subcontract
To Employer’s Representative
….(Item of Works)…
As required by Clause 4.5 of the Conditions of Contract we would advise you that we propose
to employ …(name of sub-contractor)… to execute … (item of work)… and hereby request
your consent to this appointment.
Subject to such consent, we would notify you that the sub-contracted works will commence on
…(date – not less than 28 days of tar this letter)…
Yours faithfully
Draft No.2
Clause 4.11
Unforeseen Conditions
To Employer’s Representative
….(Title)…
We have to advise that during the course of the Works we have encountered …(description of
conditions)… on …(date)…
These conditions were not foreseeable and we therefore hereby give notice thereof as required
by Clause 4.11 of the Conditions of Contract.
The effect of these conditions will be delay the Works and cause us to incur additional costs we
therefore give you notice of our intention to seek an extension of time and additional payment
pursuant to Clause 8.3 and 20.1 of the Conditions of Contract.
Yours faithfully
Draft No.3
Clause 4.16
Removal of Equipment
To Employer’s Representative
Removal of ….(Item of Equipment)…
We propose to remove … (item of equipment)… from the Site on …(date)… following
completion of … (work upon which equipment was engaged)…
As required by Clause 4.16 of the Conditions of Contract we would be pleased to receive your
consent to this action.
Yours faithfully
Draft No.4
Clause 4.24
Fossils, coins, etc.
To Employer’s Representative
…(Part of the Works)…
During …(activity)… in …(location or part of Works) … on (date)… we discovered …
(article)…
Unless instructed to the contrary we shall dispose of …(article)… by …(proposed means of
disposal) …on (date for disposal)…
Yours faithfully
Draft No.5
Clause 4.24
Fossils, coins, etc.
Delay & Disruption
To Employer’s Representative
…(Part of the Works)…
Following discovery of …(article)… and your instructions dated … (date) … in connection
therewith we incurred a delay to the progress of the Works and additional costs.
In accordance with the provisions of Clause 4.24 of the Conditions of Contract we hereby give
notice of our intention to seek an extension of time and additional payment pursuant to Clause
8.3 and 20.1 respectively.
Yours faithfully
Draft No.6
Clause 8.3
Intent to Claim EOT
To Employer’s Representative
Extension of Time
We hereby give notice of an intention to apply for an Extension of Time on account of …(brief
description of event)…
This notice is given under the provisions of Clause 8.3 of the Conditions of Contract.
We shall maintain contemporary records and submit full supporting details of our application
as required thereby.
Yours faithfully
Draft No.7
Clause 8.8
Consequence of Suspension
To Employer’s Representative
cc Employer
Suspension of … (as described in Employer’s Representative’s instruction)…
We hereby give notice pursuant to Clause 8.8 of the Conditions of Contract that on account of
following instructions given by the Employer’s Representative in respect of the above we have
suffered delay and/or incurred Cost. Therefore we give you notice that we intend to apply for
an extension of time and seek additional payment pursuant to Clause 8.3 and 20.1 of the
Conditions of Contract.
Yours faithfully
Draft No.8
Clause 8.10
Prolonged Suspension
To Employer’s Representative
Suspension of … (as described in original instruction)…
The above suspension having continued for more than 84 days we hereby give notice pursuant
to Clause 8.0 of the Conditions of Contract requiring permission to proceed within 28 days.
If permission is not granted within that period we shall ...(treat the suspension as an omission
under Clause 14/Terminate our employment under Clause 16.2)*…
Yours faithfully
* as appropriate
Draft No.9
Clause 10.1
Taking Over Certificate
To Employer’s Representative
… (Section …/The Works)* --- Taking Over Certificate
We are of the opinion that … (Section…/The Works)*… will be complete and ready for taking
over on …(date)…
Accordingly, ad provided for by Clause 10.1 of the Conditions of Contract we hereby apply for
a Taking Over Certificate for … (that Section/The Works)…
Yours faithfully
* delete as appropriate.
Draft No.10
Clause 10.1
Taking Over Certificate
Re-application
To Employer’s Representative
… (Section …/The Works)* --- Taking Over Certificate
We advise that we have completed the work specified to be required to enable you to issue a
Taking – Over Certificate for …(Section…/the Works)* … as detailed in … (letter minutes of
meeting, etc.)…
Accordingly, as provided for by Clause 10.1 of the Conditions of Contract we hereby re-apply
for a Taking-Over Certificate for … (that Section/The Works)…
Yours faithfully
* delete as appropriate.
Draft No.11
Clause 10.2(b)
Taking Over Certificate
To Employer’s Representative
… (the part) --- Taking Over Certificate
Pursuant to Clause 10.2 (b) of the Conditions of Contract we request that you issue a Taking-
Over Certificate for … (the part of the Works)… which the Employer look into use on …(date)
…
Yours faithfully
Draft No.12
Clause 13.3
Interim Payment Application
To Employer’s Representative
Application for Interim Payment No. …
Pursuant to Clause 13.3 of the Conditions of Contract we are pleased to enclose … (No.)…
copies of our statement showing the amounts to which we are now entitled together with
supporting documents.
The detailed report on progress required by Clause 4.15 of the Conditions of Contract has been
submitted under separate cover.
We look forward to receipt of a copy of your Interim Payment Certificate.
Yours faithfully
Application for Interim Payment No. …. Period ……
a) Estimated Contract Value from Page No.2 Tk. ………….
b) Changes in Legislation …………
Sub-total – Contract Price …………
c) Deduct Retention @ 10% of Contract Price
(Maximum: 5% of Contract Price, Tk. 70,826,515)
…………
Sub-total …………
d) Plant and Materials for Permanent Works (80% of cost) …………
e) Claims …………
Sub-total …………
f) Advance Payment Tk. ………
Deduct repayment – 25% of a, b, d, &e ……….. …………
Sub – total …………
g) Deduct Amounts Previously Certified …………
Amount Now Due ………..
Signed ……………. Date ………..
.Page 1.
Application for Interim Payment No. … Period …
Estimated Contract Value
Section Contract Price % Complete Price to date
1. Section 1 of the Works
Completion & approval of design …………. ……….. ………….
Embankment Protection …………. ……….. ………….
Filling …………. ……….. ………….
Dredging …………. ……….. ………….
Total of Section 1
2. Section 2 of the Works …………. ……….. ………….
3. Section 3 of the Works
Dredging …………. ……….. ………….
Embankment Protection …………. ……….. ………….
Filling …………. ……….. ………….
Fencing …………. ……….. ………….
Total of Section 3 …………. ……….. ………….
Total for the Works …………. ……….. ………….
Add Variation as Schedule Page 3 …………
Total carried to Page 1
Application for Interim Payment No. ……. Period ………
Variations
Variation No…. (Description) …… Value……….
___________________
Total to Page 2 ___________________
.Page 3.
Application for Interim Payment No. ……. Period ………
Claims
Claim No…. (Description) …… Value……….
___________________
Total to Page 1 ___________________
.Page 4.
Draft No.13
Clause 13.10
Statement at Completion
(Within 84 days of Taking Over Certificate)
To Employer’s Representative
Statement at Completion
Pursuant to Clause 13.10 of the Conditions of Contract we are pleased to submit …
(No.) …. Copies of our statement at completion together with supporting documents.
Our Statement shows:
a) final value of works done up to date of Taking-Over Certificate
b) further sums which we consider to be due
c) estimate of amounts which will become due under the Contract
We look forward to receipt of a copy of your Interim Payment Certificate.
Yours faithfully
(NOTE: Statement will follow pattern of Interim Payment Application)
Draft No.14
Clause 13.11
Draft Final Statement
(within 56 days of Performance Certificate)
To Employer’s Representative
Final Statement – Draft
Following issue of the Performance Certificate and as required by Clause 13.11 of the
Conditions of Contract we are pleased to submit … (No.) … copies of a draft final statement
with supporting Documents.
We look to your early agreement to enable us to issue our Final Statement
Yours faithfully
(Note: Statement will follow pattern of Interim Payment Application)