FINAL TECHNICAL REPORT
Detailed Project Report for ITS
for City Bus Operations of CTU
Prepared for Chandigarh Transport Undertaking (CTU)
by IBI Consultancy India Private Limited October 2015
CLIEN
T LOGO
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
Document Control Page
September 2015
CLIENT: Chandigarh Transport Undertaking (CTU)
PROJECT NAME: Consultancy Service for Modernization of City Bus Services of
Chandigarh Transport Undertaking
REPORT TITLE: Detailed Project Report for ITS for City Bus Operations of CTU
IBI REFERENCE: 37120
VERSION: V 0.19
DIGITAL
MASTER: 37120_CTU_ITS_DPR_Sep25_2015_V0.19
ORIGINATOR: Srinivas Ganji, Rakshith Padmanna
REVIEWER: Visweswara Rao Gantasala; Dr. Vijay Kovvali
AUTHORISATION: Deepak Darda
CIRCULATION
LIST: CTU Team, GEF V SUTP Team, WB Team & IBI Team
HISTORY:
V0.28 - Submitted on February 5, 2015
V0.6 – Submitted on March 24, 2015
V0.8 – Submitted on April 07, 2015
V0.13 – Submitted June 23, 2015
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
Table of Contents
i
Abbreviations .......................................................................................................................... 1
Summary .................................................................................................................................. 1
1 Introduction ................................................................................................................... 5
1.1 Purpose of Document ............................................................................. 5
1.2 Intended Audiences ................................................................................ 5
1.3 Project Background ................................................................................. 6
1.3.1 Demographics ............................................................................ 6
1.3.2 Travel Characteristics ................................................................ 7
1.3.3 Public Transport Infrastructure ................................................... 7
1.4 CBMP Overview ...................................................................................... 8
1.4.1 ITS Infrastructure ..................................................................... 10
1.5 Scope of the ITS DPR ........................................................................... 10
1.6 Report Organization .............................................................................. 11
2 Needs Analysis ........................................................................................................... 12
2.1 Technological Interventions .................................................................. 12
2.1.1 Methodology ............................................................................. 12
2.1.2 “Key Needs” Analysis ............................................................... 13
2.1.3 ITS Technologies ..................................................................... 14
2.2 Current Efforts ....................................................................................... 15
2.3 Organizational Structure ....................................................................... 18
2.3.1 Special Purpose Vehicle (SPV) ............................................... 21
2.4 Current CTU Processes ........................................................................ 21
2.5 Suggested Technological Interventions ................................................ 29
2.6 Suggested Processes for Modernization/Implementation of ITS ......... 30
3 Options Analysis ........................................................................................................ 40
3.1 Service Options ..................................................................................... 40
3.2 AVL Alternatives ................................................................................... 41
3.3 Fare Collection Alternatives .................................................................. 42
3.4 Communication for Fare Collection Alternatives .................................. 44
3.5 PIS Information Alternatives ................................................................. 45
3.6 PIS Display Type Alternatives .............................................................. 46
3.7 Transit Management System (TMS) Alternatives ................................. 47
4 System Architecture & Components ........................................................................ 48
4.1 System Architecture .............................................................................. 49
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
Table of Contents (continued)
September 2015
4.2 Automatic Vehicle Location (AVL) System ........................................... 49
4.2.1 Overview .................................................................................. 49
4.2.2 Buses ....................................................................................... 50
4.2.3 AVL Functionality & Benefits .................................................... 51
4.2.4 AVL System Concept ............................................................... 51
4.2.5 Functional Requirements ......................................................... 53
4.2.6 AVL Central System ................................................................. 54
4.3 Passenger Information System ............................................................. 55
4.3.1 Overview .................................................................................. 55
4.3.2 PIS System Concept ................................................................ 56
4.3.3 Functional Requirement ........................................................... 57
4.4 Fare Collection System ......................................................................... 57
4.4.1 Overview .................................................................................. 57
4.4.2 System Concept ....................................................................... 58
4.4.3 Functional Requirements ......................................................... 58
E-purse: ................................................................................................ 58
Smart Pass ........................................................................................... 59
4.4.4 Electronic Ticketing Machines ................................................. 60
4.4.5 Fare Structure .......................................................................... 61
4.4.6 Payment & Recharge ............................................................... 61
4.4.7 Audit / Enforcement .................................................................. 61
4.5 Transit Management System ................................................................ 61
4.5.1 Overview .................................................................................. 62
4.5.2 Goals and Objectives ............................................................... 63
4.5.3 Proposed Integrated Transit Management System ................. 64
4.5.4 System Concept ....................................................................... 65
4.5.5 Other Systems Integration with TMS ....................................... 72
4.5.6 Other System Infrastructure at Depots and Terminals ............ 74
4.6 Transit Management Centre ................................................................. 74
4.6.1 System Concept ....................................................................... 74
4.6.2 Functional Requirements ......................................................... 75
4.6.3 Data Archiving .......................................................................... 76
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
Table of Contents (continued)
September 2015
4.6.4 TMC & Video Wall .................................................................... 76
4.6.5 Man power ............................................................................... 77
4.6.6 Roles and Responsibilities ....................................................... 79
5 Procurement Plan and Project Financials ................................................................ 81
5.1 Procurement Plan ................................................................................. 81
5.2 BOQ and Costs Estimation ................................................................... 81
5.3 Financial Analysis of the Project ........................................................... 86
5.3.1 Project Phasing ........................................................................ 86
5.4 Project Cost .......................................................................................... 87
6 Implementation Plan ................................................................................................... 88
6.1 Studies .................................................................................................. 90
6.2 Project Implementation Unit .................................................................. 90
6.3 Roles and Responsibility ...................................................................... 91
6.3.1 Project Implementing Unit / CTU ............................................. 91
6.3.2 System Integrator ..................................................................... 91
6.3.3 Project Evaluation Agency ....................................................... 91
6.4 Scaling Requirement ............................................................................. 91
6.5 Operations Concept .............................................................................. 92
6.6 Risk Management Process ................................................................... 93
6.7 Training & Knowledge Transfer ............................................................ 94
6.8 Monitoring & Evaluation Plan ................................................................ 95
Appendix 1 – Baseline Scenario of City Bus Services ................................................... 100
Appendix 2 – Sample MIS Reports .................................................................................... 123
Appendix 3 – Detailed ITS Costing ................................................................................... 151
Appendix 4 – List of Existing Buses to be Fitted with AVL Units, Destination Boards & Cameras ..................................................................................................................... 157
Appendix 5 – DEVICE SPECIFICATIONS .......................................................................... 167
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
iv
List of Exhibits
Exhibit 1: CTU Demonstration Tasks Under GEF-V ...................................................... 6
Exhibit 2: Demographic Characteristics of Study Area .................................................. 6
Exhibit 3: Mode Shares & Average Trip Lengths for Different Modes in Tri-City Area .. 7
Exhibit 4: Existing and Approved Bus Procurement of CTU .......................................... 8
Exhibit 5: Understanding of Modernization of City Bus Service .................................... 9
Exhibit 6: Implementation Strategies for City Bus Service Modernization ................... 10
Exhibit 7: Strategies Adopted for City Bus Modernization ........................................... 12
Exhibit 8: High-Level Planning of ITS System for CTU ............................................... 13
Exhibit 9: Identified Issues in City Bus System of CTU ............................................... 13
Exhibit 10: Components of Transit ITS ........................................................................ 14
Exhibit 11: Route Information Provided on CTU Website ............................................ 15
Exhibit 12: Current Status of Technology Intervention in CTU .................................... 17
Exhibit 13: Existing Organizational Structure of CTU .................................................. 18
Exhibit 14: Current Practice of CTU in Performing Different Key Activities of City Bus Services ................................................................................................ 20
Exhibit 15 Existing Operations ..................................................................................... 22
Exhibit 16 Existing Maintenance .................................................................................. 23
Exhibit 17 Existing HR ................................................................................................. 24
Exhibit 18 Existing Finance .......................................................................................... 25
Exhibit 19 Existing Ticketing ........................................................................................ 26
Exhibit 20 Existing Stores Process .............................................................................. 27
Exhibit 21 Existing Scrapping Process ........................................................................ 28
Exhibit 22 Recommended Operations Process ........................................................... 31
Exhibit 23 Recommended Maintenance Process ........................................................ 32
Exhibit 24 Recommended HR Process ....................................................................... 33
Exhibit 25 Recommended Finance Process ................................................................ 34
Exhibit 26 Recommended Ticketing Process .............................................................. 35
Exhibit 27 Recommended Stores Process .................................................................. 36
Exhibit 28 Recommended Scheduling Process ........................................................... 37
Exhibit 29 Recommended Training Process ................................................................ 38
Exhibit 30 Recommended Scrapping Process ............................................................ 39
Exhibit 31 Service Options ........................................................................................... 41
Exhibit 32 CTU ITS Components ................................................................................. 48
Exhibit 33 System Architecture .................................................................................... 49
Exhibit 34 Existing and Approved Bus Procurement of CTU ....................................... 50
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
v
Exhibit 35: AVL & PIS System Architecture ................................................................. 52
Exhibit 36: AVL Central System Schematic ................................................................. 54
Exhibit 37: List of PIS Display Boards to be installed at Bus Shelters ......................... 56
Exhibit 38 POS Locations (Source: CTU) .................................................................... 59
Exhibit 39 Electronic Ticketing Process ....................................................................... 60
Exhibit 40: Available Reports from Waybill Management System of CTU .................. 62
Exhibit 41: Screenshot of the Inventory Management System Developed by NIC for CTU ....................................................................................................... 63
Exhibit 42: Sub Systems of Transit Management System ........................................... 65
Exhibit 43: Concept of Centralized TMS ...................................................................... 65
Exhibit 44: Interface between Various TMS Sub Systems .......................................... 66
Exhibit 45: Functionalities of Depot Management System .......................................... 66
Exhibit 46: Functionalities of Depot Management System .......................................... 67
Exhibit 47: Depot Management System ...................................................................... 68
Exhibit 48: Workflow of Payroll System ....................................................................... 70
Exhibit 49 Operations Planning Process ..................................................................... 71
Exhibit 50: Data Exchange Needs ............................................................................... 73
Exhibit 51: Central Control Centre Concept of Single Data Update Module. .............. 75
Exhibit 52: Data for Man Power Estimation ................................................................. 77
Exhibit 53: Education & Experience Qualifications for ITS Staff .................................. 78
Exhibit 54: Responsibility Matrix .................................................................................. 80
Exhibit 55: Bill of Quantities (BoQ) for CTU ITS Project .............................................. 85
Exhibit 56: Summary Costs for CTU ITS Project ......................................................... 86
Exhibit 57 Phasing for the CTU ITS Project ................................................................. 86
Exhibit 58: Implementation Plan .................................................................................. 89
Exhibit 59 Operations Concept .................................................................................... 92
Exhibit 60 Risk Assessment & Mitigation ..................................................................... 94
Exhibit 61 Vehicle Mounting Unit/CAD-AVL unit (VMU) Training Manual from IBI’s VTMS Project ........................................................................................ 94
Exhibit 62 Preliminary Training Plan ............................................................................ 95
Exhibit 63: Demographic Characteristics of Study Area ............................................ 101
Exhibit 64: Key Transportation Services and Responsible Agencies in the Tri-City Area..................................................................................................... 102
Exhibit 65: Existing Organizational Structure of CTU ................................................ 102
Exhibit 66: Growth of Population, Registered Vehicles & Accidents in Chandigarh .. 103
Exhibit 67: Mode Shares for Different Modes in Tri City Area in 2009 ...................... 104
Exhibit 68: Summary of Relevant Future Proposals in Chandigarh by Different Agencies ............................................................................................. 105
Exhibit 69: Details of Proposed Metro Rail in DPR for Chandigarh Urban Complex Area (Tri-City) ..................................................................................... 105
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
vi
Exhibit 70: Proposed Metro Rail Corridors (Alternative II – Pink+Red) in Metro Rail DPR..................................................................................................... 106
Exhibit 71: Summary of Fleet Available For Operation with CTU for City Bus Service as in FY 2013-14 ................................................................................. 107
Exhibit 72: Manpower and Operational Fleet with CTU in 2013-14 ........................... 108
Exhibit 73: Geographic Location of Existing & Proposed Bus Depots of CTU .......... 110
Exhibit 74: Satellite View of Site Layout of the Newly Proposed Raipur Kalan Depot .................................................................................................. 112
Exhibit 75: Ridership Pattern of City Bus Service of CTU Over Last Six Financial Years ................................................................................................... 113
Exhibit 76: Previous Fare levels in CTU’s City Bus Services as per Fare Revision in April 2010 ............................................................................................ 114
Exhibit 77: Current Fare levels in CTU’s City Bus Services as per Fare Revision in September 2014 ................................................................................. 114
Exhibit 78: Fleet Breakdown Statistics in 4 Depots of CTU in Last 2 Financial Years ................................................................................................... 115
Exhibit 79: Cause-Wise Breakup Count-Split In Year 2014 ...................................... 116
Exhibit 80: Accidents Rates of CTU Bus Operations from 2001 to 2014 .................. 117
Exhibit 81: Accidents Statistics for CTU depots ......................................................... 117
Exhibit 82: Split of different categories of accidents occurred in FY 2013-14 for CTU buses .................................................................................................. 118
Exhibit 83: Fuel Economy Statistics of CTU Bus Operations .................................... 118
Exhibit 84: Revenue Split for both CTU ..................................................................... 119
Exhibit 85: Split of Total Costs of CTU Specific to City Bus Operations ................... 120
Exhibit 86: Financial Characteristics of City Bus Service and overall CTU for financial years FY20112-13 to FY2013-14 ....................................................... 121
Exhibit 87: Summary of Baseline Indicators of City Bus Service of CTU .................. 122
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
1
Abbreviations
S. NO. TERM EXPLANATION
1. AC Air Conditioned
2. AMC Annual Maintenance Contract
3. API Application Program Interface
4. ASRTU Association For State Road Transport Undertaking
5. AVL Automatic Vehicle Location
6. BDC Bus Driver Console (From UBS II)
7. BMTC Bangalore Metropolitan Transport Corporation
8. BOQ Bill Of Quantity
9. BQS Bus Queue Shelters
10. BRTS Bus Rapid Transit System
11. CA Chandigarh Administration
12. CAD Computer Aided Dispatch
13. CBMP City Bus Modernization Plan
14. CCTV Closed-Circuit Television
15. CD Compact Disc
16. CL Casual Leave
17. CMP Comprehensive Mobility Plan
18. COTS Commercial Off The Shelf
19. CTU Chandigarh Transport Undertaking
20. DB Database
21. DG Diesel Generator
22. DM Depot Manager
23. DMS Depot Management System
24. DR Disaster Recovery
25. DPR Detailed Project Report
26. DVD Digital Video Disc
27. ETD Estimated Time of Departure
28. EL Earned Leave
29. EPKM Earnings Per Kilometer
30. EPP Earnings Per Passenger
31. ERP Enterprise Resource Planning
32. ESCBS Efficient And Sustainable City Bus Services
33. ESI Employees' State Insurance
34. ETA Estimated Time of Arrival
35. ETM Electronic Ticketing Machine
36. FC Fitness Certificate
37. FCS Fare Collection System
38. GEF Global Environmental Fund
39. GM General Manager
40. GPRS General Packet Radio Service
41. GPS Global Positioning System
42. HR Human Resource
43. ISBT Inter State Bus Terminal
44. ISO International Standards Organization
45. IPT Intermediate Public Transport
46. ITMS Intelligent Transit Management System
47. ITS Intelligent Transportation Systems
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
2
S. NO. TERM EXPLANATION
48. IVRS Interactive Voice Response System
49. JnNURM Jawaharlal Nehru National Urban Renewal Mission
50. KMPL Kilometer Per Liter
51. KVM Keyboard, Video & Mouse
52. LAN Local Area Network
53. LCD Liquid Crystal Display
54. LED Light Emitting Diode
55. MB Megabyte
56. MIS Management Information System
57. ML Maternity Leave
58. MoUD Ministry Of Urban Development
59. NIC National Informatics Centre
60. NCB National Competitive Bidding
61. NTP Network Time Protocol
62. NVR Network Video Recorder
63. OBITS On Board Intelligent Transport System
64. O&M Operations And Maintenance
65. OEM Original Equipment Manufacture
66. PF Provident Fund
67. PIS Passenger Information Systems
68. PL Paternity Leave
69. POS Point Of Sale
70. PT Public Transport
71. RBI Reserve Bank of India
72. RDBMS Relational Database Management System
73. RoW Right Of Way
74. RTPI Real- Time Passenger Information
75. SaaS Software As A Service
76. SCN Security Camera Network (From UBS II)
77. SCU Single Control Unit (From UBSII)
78. SI System Integrator
79. SIM Subscriber Identity Module
80. SL Sick Leave
81. SLA Service Level Agreement
82. SMS Short Messaging System
83. SOP Standard Operating Procedure
84. SPV Special Purpose Vehicle
85. STU State Transport Undertaking
86. SWOT Strengths, Weaknesses, Opportunities And Threats
87. TMC Transit Management Centre
88. TMS Transit Management System
89. TOD Transit Oriented Development
90. TW Two Wheeler
91. UBS-II Urban Bus Specifications – Ii
92. UPS Uninterruptible Power Supply
93. UT Union Territory
94. VHMD Vehicle Health Monitoring And Diagnostic (From UBS II)
95. VMU Vehicle Monitoring Unit
96. WMS Workshop Management System
97. WLAN Wireless Local Area Network
98. WS Work Station
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
1
Summary
As part of the GEF-V Project, initiated by Ministry of Urban Development (MoUD) and World Bank,
CTU has undertaken the City Bus Modernization Plan. One of the components of the plan is the
introduction of Intelligent Transport Systems (ITS) into the city’s bus operations.
The City Bus Modernization Plan developed as part of the project identified technology intervention,
namely, Intelligent Transport Systems for enhancing customer experience and bus operations &
management. In this Chapter, a brief background of the current Project ‘City Bus Modernization for
Chandigarh Transport Undertaking (CTU) Operations’ is provided.
Based on interactions with key stakeholders who are directly connected with the system, the following
needs were identified by stakeholder type.
Stakeholder Technology Needs
CTU Passengers Need for improving reliability of bus service.
Need for information dissemination to bus users for improving
the usage of public transportation.
Need for bus arrival information to improve efficiency of
accessing the bus network.
Need for simplifying ticketing for passengers and creating
telescopic fares (on transfers) through Electronic Ticketing
Machine (ETM) and smart card ticketing system.
CTU Central
Administration
Need for real-time bus location information for enhancing
operations.
Need for passenger information systems to increase ridership.
Need for electronic ticketing system to reduce leakages.
Need for smart card based ticketing system to enhance
customer experience with the bus system.
Need for integrated system for efficient decision making
Need for data management and analysis
Need for detailed MIS/ERP solution to provide decision makers
with data to continuously improve operations.
Need for effective monitoring and evaluation system for
different activities and understanding the parameters effecting
the performance of city bus service
Need for quick incident (accidents, breakdowns, etc.) detection
and improved reaction times on the incident response.
Need for improvement in financial performance through better
operational, maintenance and financial control.
Depot Activities Need for efficient process for scheduling of trips, vehicles and
crew
Need for automated data of revenue from bus fares.
Need for efficiency in monitoring of operations as per
schedules
Need for real-time guidance to crew when required.
Need for reducing revenue leakage and improving efficiency in
traffic inspections.
Need for data management and analysis at depot level.
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
2
Keeping in view the transportation needs of the Chandigarh City Bus services and the available ITS
Based on the needs the ITS solutions that were recommended for CTU bus operations are as follows:
1. Provide Automatic Vehicle Location (AVL) with the following objectives:
a. Increased productivity of the transit system by improving the reliability of the system.
b. Reduced operational costs of the buses by developing a fleet management system
using the vehicle tracking mechanism.
2. Provide Passenger Information Systems (PIS) with the objectives of:
a. Improved customer service to the transit riders by information dissemination through:
i. Display boards at terminals and other prominent locations
ii. Web based portal
b. Reducing stress levels for commuters by providing prior knowledge of the bus arrivals
and other schedule information through:
i. SMS system that provides bus arrival information at all bus stops across the
Tri-city area
ii. Mobile application providing CTU city service information
iii. Commuter Portal that provides both real-time and static (schedule data) to
internet users
iv. Interactive Voice Response System (IVRS) for the passengers not
comfortable with website and SMS based information systems.
v. PIS boards at critical locations across the city
3. Introduce Fare Collection System (FCS) consisting of Electronic Ticketing Machines (ETMs)
with Smart Card reading capability to:
a. Improve customer convenience
b. Reduce fare leaks
c. Improve understanding of demand by origin-destinations.
d. Provide information for new fare policies
i. Time-of-day pricing
ii. Special event pricing
e. Allows seamless bus transfers
4. Develop Transit Management Systems (TMS) application that can support:
a. Scheduling and rostering software for Planning that will support improving bus
operations and crew management
b. Master database for drivers, conductors and various staff that can support
computerized leave management system to achieve better accountability from the
staff
Need for automating maintenance and other depot activities
Need for capacity building and training using technology for
bus operations.
Need for increase in productivity of staff by improving efficiency
in activities performed.
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
3
c. Depot and Terminal management system to support decision makers with data on
activities performed along with resource and time requirements.
d. Workshop management system to better log the maintenance needs and activities.
e. Provide MIS reports on the various depot, terminal, workshop and bus operations
activities.
5. Develop a Transit Management Centre (TMC) to achieve:
a. Stakeholder coordination (Traffic Police, etc.) through providing interaction and a
common data sharing location.
b. Improve bus schedule adherence and reliability, through a the AVL application and
alert monitoring system
c. Provide incident management capabilities by providing a centralized location for
viewing/identifying incidents and dispatching incident response teams.
d. Providing emergency dispatch by providing a link from the TMC to the hospitals with
ambulance service.
e. Improve reliability of service and efficiency of the operations through better oversight.
6. Perform data collection and archiving services with the objectives of:
a. Developing performance measures to continuously evaluate the performance of the
system.
b. Develop algorithms to enhance bus service planning, and create new fare policies.
7. Develop MIS/ERP dashboard for the project with the objectives of:
a. Providing holistic, integrated information to the CTU management through detailed
MIS reports and user friendly, flexible dash board consisting of tables and graphs.
b. Provide ridership and modeshare details on a daily, monthly and yearly basis using
filters in the dashboard. The information shall also be provided through filters by bus,
route, conductor/driver, schedule, origin, destination and various other useful decision
making parameters.
c. Provide passenger counts and revenue information in realtime and/or preset intervals
as stated by the Client during the design phase.
d. Provide route and schedule adherence information with various filters for the decision
makers to get an understanding of the ground problems.
e. Provide bus maintenance information in terms of preventive and reactive maintenance
(breakdowns, etc.).
f. Provide critical stores & purchase inventory details for decision support.
The System architecture is shown in Exhibit below:
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
4
The system cost for the six month implementation period is estimated at 17.12 crores. Cost by ITS
component is shown below:
Component Capital Cost O&M Cost for
next 6 years SI Cost (10% of Capital) Total Project Cost
Total Installed Cost Spare Cost Total Capital
FCS ₹ 419,21,075 ₹ 0 ₹ 419,21,075 ₹ 41,92,108 ₹ 41,92,108 ₹ 503,05,290
AVL ₹ 515,93,025 ₹ 0 ₹ 515,93,025 ₹ 51,59,303 ₹ 51,59,303 ₹ 619,11,630
PIS ₹ 50,10,000 ₹ 0 ₹ 50,10,000 ₹ 5,01,000 ₹ 5,01,000 ₹ 60,12,000
TMS ₹ 307,32,500 ₹ 0 ₹ 307,32,500 ₹ 30,73,250 ₹ 30,73,250 ₹ 368,79,000
TMC ₹ 55,60,000 ₹ 0 ₹ 55,60,000 ₹ 5,56,000 ₹ 5,56,000 ₹ 66,72,000
COMM ₹ 8,75,000 ₹ 0 ₹ 8,75,000 ₹ 85,20,000 ₹ 87,500 ₹ 94,82,500
Total ₹ 1356,91,600 ₹ 0 ₹ 1356,91,600 ₹ 220,01,660 ₹ 135,69,160 ₹ 1712,62,420
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
5
1 Introduction
The Global Environmental Facility (GEF) along with the World Bank and Ministry of Urban
Development (MoUD) has initiated the GEF-V project which is termed as “Efficient and Sustainable
City Bus Services (ESCBS)” to provide Sustainable City Bus Services in Medium sized cities (with
population between 1M million and 4M million).
The main objective under the GEF-V Project is to make the city bus services more attractive to enable
a shift from personal vehicular modes to environmentally sustainable modes of transport and also to
efficiently use the existing infrastructure.
The City Bus Modernization Plan developed as part of the project identified technology intervention,
namely, Intelligent Transport Systems for enhancing customer experience and bus operations &
management. In this Chapter, a brief background of the current Project ‘City Bus Modernization for
Chandigarh Transport Undertaking (CTU) Operations’ is provided.
1.1 Purpose of Document
The purpose of the ITS detailed project report is firm up the specific needs of CTU into specific projects
including the financial outlay for the same. This includes:
Examination of technological parameters.
Description of the technology to be used.
Options analysis
Recommendations on solution
Broad technical specification.
Costing
1.2 Intended Audiences
The ITS DPR should be read by all stakeholders expected to have a role in the design, implementation,
operation, and/or support of the proposed system, or otherwise expected to be impacted by the system
during its lifespan. This includes:
CTU Management
Chandigarh Administration (CA) staff involved in CTU Management & Operations
CTU Technical Staff who will oversee the implementation
CTU - System maintainers and administrators
System Integrator Implementing the System
Organizational planning units (e.g. Labor Relations, Human Resources, and Operations
Training)
Financial planning units
Other stakeholders involved in the project.
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
6
1.3 Project Background
Chandigarh is one of the four cities selected for implementing demonstration projects based on a
competitive process followed by The World Bank to short-list the cities under this programme. The
following are the demonstration projects for Chandigarh under GEF-V – ESCBS project.
COMPONENT 2A: PHYSICAL
IMPROVEMENTS
COMPONENT 2B: CAPACITY BUILDING &
TECHNICAL ASSISTANCE
Modern Depot Equipment for
Improved maintenance and life of
buses
Modern Intelligent Transport System
(ITS) and Management Information
System (MIS)
Hiring of Project Management Consultant
Fuel Efficiency Programme
Capacity Building Initiatives
Marketing and Branding Program
Study on Institutional and Funding options
for city bus operations
Comprehensive route planning
study/business plan
Operating expenses reimbursement
Exhibit 1: CTU Demonstration Tasks Under GEF-V
The cities require a framework for City Bus Modernization Plan (CBMP) and Detailed Project Report
(DPR) under Technical Assistance (Component 2A) to be developed for further processing.
1.3.1 Demographics
This Exhibit 2 from CBMP report summarizes the base line scenario on demographics of the study
area.
CITY POPULATION (2011) GENDER
RATIO1
LITERACY RATE (%) AVERAGE INCOME
Chandigarh 10.55 Lakh 817 86.05 (Female:
64.8)
-
Mohali 1.7 Lakh 911 93.22 (Female:
91.1)
-
Panchkula 2.1 Lakh 883 87.86 (Female:
84.0)
-
Tri city 14.25 Lakh - - Rs. 22,857/month
National Average - 940 74.04 (Female:
65.5)
Around Rs.
5,500/month
Exhibit 2: Demographic Characteristics of Study Area
The average income of household (Rs. 23,000/-) of the study area which translated to average
household transport expenditure of about 10.8% of total household income. Around 86% of the
households have either car or two-wheeler or both, according to the Master Plan.
There are about 8 lakh vehicles registered in Chandigarh. More than 95% of registered vehicles are
TW (70%) and Cars (28%). According the speed delay survey conducted in CMP study, the average
1 Gender Ratio is the number of female persons per 1000 people
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
7
journey speed during peak hours is 32 kmph and during off peak it is 36 kmph, which translates to
Private vehicles having a huge advantage for travel (lack of congestion).
1.3.2 Travel Characteristics
Per capita trip rate in the tri city area is 1.32 including walk. This walk trips include the access and
egress legs of PT and IPT trips too. Trip lengths mostly depend on the distribution of different activities.
As per the CMP study of 2009, mode shares and the average trip lengths for different modes in tri city
area are shown in the below Exhibit 3.
Exhibit 3: Mode Shares & Average Trip Lengths for Different Modes in Tri-City Area
The average trip length for the all the trips is measured to be 6 Km. It can be observed from the exhibit
that, there is significant mode share for walk and bicycle. This is due to the presence of pedestrian
footpaths and cycle tracks in the city. There are 11.2 % of trips by bus mode in the tri city area.
However, there might of increase of ridership as on today as 100 more new buses have been started
for city bus service after 2010. Most of the travellers with trip lengths more than 10 Km are using bus
as their travel mode, and mostly for work & education purpose. The private motorized trips comprises
of about 50% of total trips from where the shift to public transport should be aimed primarily. There are
30% of trips by non-motorized modes which is a good sign, and bus is also having the scope to get
the passenger shift from the motorized trips with improved and modernized services.
1.3.3 Public Transport Infrastructure
The public transport system in the tri-city area includes the CTU city bus service. Shared auto and
Auto are also present which serve as intermediate public transport system. The public transport
infrastructure for the CTU bus service include: bus fleet, bus shelters, and bus depots. CTU bus
services travel up to V4 roads which bisect the sectors.
MODE AVERAGE TRIP
LENGTH (KM)
Walk 1.09
Cycle Rickshaw 2.07
Bicycle 3.68
Bus 11.49
Shared Auto 5.85
Auto 4.17
Two Wheeler 6.89
Car 9.06
1, 17.35%2, 2.87%
3, 10.94%
4, 11.24
%
5, 5.85%6, 1.29%
7, 35.38%
8, 15.07%
Travel Mode Shares in Tri City
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
8
1.3.3.1 Bus Fleet
379 buses were approved through the JnNURM scheme. An additional 49 buses are also being
procured in lieu of the condemned buses. The information on the bus procurement with their model
and procurement dates is provided in Exhibit 4. This list does not include the buses existing in the
depot that are condemned. All the condemned buses are expected to be disposed by October, 2015.
Timeline Make Description Bus type No. Of buses Total
As on Feb 2015 Leyland Existing buses Mini AC 34 34
As on Feb 2015 TATA Existing buses Standard AC 40 74
As on Feb 2015 TATA Existing buses Standard Non AC 60 134
As on Feb 2015 SML ISUZU New semi- low floor Midi AC 80 214
As on Feb 2015 SML ISUZU New semi-low floor Midi Non AC 30 244
As on March 2015 SML ISUZU New semi-low floor Midi Non AC 60 304
By October 2015 TATA Low floor Midi Non AC 49 353
By December 2015 Corona New semi-low floor Standard AC 20 373
By December 2015 Corona New semi-low floor Standard AC 50 423
By December 2015 Corona New semi-low floor Standard Non AC 45 468
By December 2015 Corona New semi-low floor Standard Non AC 45 513
Note: Information as per September 18, 2015
Legend
Existing Buses (without On-Board ITS) Recently Delivered Buses (with On-Board ITS) Buses Procured, Awaiting Delivery
Exhibit 4: Existing and Approved Bus Procurement of CTU
1.3.3.2 Bus Depots
Bus depot is the place from where buses are dispatched for the operations as per the schedules and
are maintained & parked when not in operation. Currently CTU has four depots from where it is
operating all the buses including long route, suburban routes and city bus routes. Two depots (Depots
2 & 4) are only operating the city bus routes, while other two depots (Depots 1&3), both city bus and
other routes are being served. All the depots have their own workshops. However, based on need, the
buses are maintained at one of the other workshops too.
One new depot has been proposed by CTU to be developed at an area of 6.5 acres at Raipur Kalan
in Chandigarh to cater to the sanctioned JnNURM buses in the future. The activities are similar in
nature at all the depots except the type of routes and buses they manage. The maintenance activity
at Depot 4 where JnNURM buses are held is done by TATA under Annual Maintenance Contract
(AMC).
1.4 CBMP Overview
The CBMP identified “Modernization” as the process of intervening at various levels/sectors of city bus
service such as policy/planning, infrastructure building/up gradation, institutional structures,
technology, capacity building, marketing/branding in order to enhance the level of service and also to
utilize the existing resources efficiently and optimally by ensuring the financial sustainability of city bus
operations & very minimal environmental and social impacts. Exhibit 5 shows the elements of the city
bus service modernization and broad objectives of CTU identified in the CBMP report.
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
9
Exhibit 5: Understanding of Modernization of City Bus Service
The CBMP identified various implementation strategies for critical action plans that are
recommended as part of the city bus modernization plan based on the needs, gaps and SWOT
analysis. The implementation strategies were divided into six categories as shown in Exhibit 6.
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
10
Exhibit 6: Implementation Strategies for City Bus Service Modernization
The Technological interventions were categorized as ITS MIS/ERP systems and the Public Transport
ITS.
1.4.1 ITS Infrastructure
The CBMP also identified the various ITS initiatives that CTU is currently undertaking. These include:
1. On-Bus ITS (OBITS) was part of the JnNURM buses (100 buses of Depot 4): It includes PIS
display boards inside the bus, GPS tracking system, etc. However, none of the systems are
currently functional and has been discarded. No integration requirements are required for
the proposed system due to non-functioning of the earlier OBITS equipment.
2. The AMC at Depot 4 i.e. TATA Motors uses CRM (Customer Relationship Management)
software for stores inventory and management.
3. CTU has introduced some of depot management system’s with the support of NIC (National
Informatics Centre) modules as mentioned below:
Vehicle and Crew Scheduling -
Waybill Management System
Attendance Leave Information System
Store & Inventory Management System
4. It is also noteworthy that in all the newly sanctioned 379 JnNURM city buses, OBITS
(including GPS devices, CCTV cameras, Driver Console unit and Variable Message sign
boards) are factory fitted in the buses (Integral part). Hence it can also be treated as an
opportunity.
5. The route information along with fixed maps (raster images) is provided for different routes in
the website.
6. “Chandigarh Bus Guide Mobile” Android Application is provided by a Private Agency called
“86Business Street” in Chandigarh.
1.5 Scope of the ITS DPR
ITS system for Chandigarh City Bus service will deploy technology which will help the city bus
experience for commuters and help CTU staff to improve fleet management, efficiency and to provide
better services to the commuters. The scope is limited to public transport improvements for city bus
services.
Operational Physical Technological
Financial Institutional Marketing
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
11
1.6 Report Organization
This DPR document has 6 chapters that are organized to explain the current scenario of CTU
operations, need for implementation of ITS and the proposed Intelligent Transportation System
solution proposed for CTU bus operations. Breakdown of the chapters are mentioned below
Chapter 2: Outlines the Needs Analysis for the implementation of ITS
Chapter 3: Technology selection along with options analysis
Chapter 4: Description of the system architecture and components
Chapter 5: Details of project financials and procurement are explained in this chapter
Chapter 6: Details of the implementation plan are given in this project.
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
12
2 Needs Analysis
Understanding the requirements and project background, needs analysis was performed based on the
current situation and future needs. After analyzing the needs of the stakeholders, requirement of the
system and existing technology, the impacting interventions which will support modernization of the
city buses through technology interventions are discussed in this chapter.
2.1 Technological Interventions
The very fact that around 86% of Chandigarh households own either two wheeler or four wheeler or
both, cautions the need for attracting the significant choice riders to the city bus mode. It is also stated
in vision for city bus service that, the city bus should be a ‘mode by choice’ for passengers2. That
means the services offered by the city bus service should be competitive enough with that are present
for other modes. The modernization of city bus service is focused towards increasing the level of
service, attractiveness and efficiency in resource utilization. Among different strategies adopted for
the implementation of city bus modernization, technological interventions are the key strategy for
achieving the objectives as shown in Exhibit 7.
Exhibit 7: Strategies Adopted for City Bus Modernization
2.1.1 Methodology
A high-level planning of the ITS system as shown in Exhibit 8 was developed for CTU that will help
achieve these goals.
2 Please refer to the “City Bus Modernization Plan” Report for more details on vision, objectives, action plans and justification on need for technological interventions
Operational Institutional Physical Financial Technological Marketing
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
13
Exhibit 8: High-Level Planning of ITS System for CTU
The CTU ITS plan consists of first identifying the needs of the bus service, and based on the needs
creating a strategic plan that will provide technology based solutions. The deployment of these ITS
solutions will lead to necessary bus service improvements resulting in economic and community
benefits.
2.1.2 “Key Needs” Analysis
Different issues in city bus system are summarized below which are considered to be resolved with
various technological options available. The following concerns/issues as shown in Exhibit 9 have
been identified with respect to the interactions with key stakeholders who are directly connected with
the system, so as to improve efficiency of services corresponding to them.
Exhibit 9: Identified Issues in City Bus System of CTU
Chandigarh City Bus Service Needs
ITS Solutions
ITS Induced Improvements
Economic & Community
Benefits
ITS Technologies
stakeholder Technology Needs
CTU Passengers Need for improving reliability of bus service.
Need for information dissemination to bus users for improving
the usage of public transportation.
Need for bus arrival information to improve efficiency of
accessing the bus network.
Need for simplifying ticketing for passengers and creating
telescopic fares (on transfers) through Electronic Ticketing
Machine (ETM) and smart card ticketing system.
CTU Central
Administration
Need for real-time bus location information for enhancing
operations.
Need for passenger information systems to increase ridership.
Need for electronic ticketing system to reduce leakages.
Need for smart card based ticketing system to enhance
customer experience with the bus system.
Need for integrated system for efficient decision making
Need for data management and analysis
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
14
Based on discussions with CTU that the crime rate in Chandigarh is low, security cameras at the bus
shelters were not considered as a strong need.
2.1.3 ITS Technologies
Transit ITS services include tracking, surveillance and communications, such as automated vehicle
location (AVL) systems, computer-aided dispatch (CAD) systems, and remote vehicle and facility
surveillance cameras, which enable bus agencies to improve the operational efficiency, safety, and
security of the bus service. There are multiple ITS technologies available for Transit Management as
listed in Exhibit 10.
Exhibit 10: Components of Transit ITS3
3 Transit Management Systems, US Department of Transportation, http://www.itsoverview.its.dot.gov/TM.asp
Operations & Fleet Management
•AVL/CAD
•Transit Signal Priority
•Maintenance
•Planning
•Service Coordination
Information Dissemination
•In-Vehicle Systems
•In-Terminal/Wayside
•Internet/SMS/Phone
•External Bus Display Boards
Safety & Security
•In-Vehicle Surveillance
•Facility Surveillance
•Employee Credentialing
•Geofencing of Depots, Operations Boundary
Need for detailed MIS/ERP solution to provide decision makers
with data to continuously improve operations.
Need for effective monitoring and evaluation system for
different activities and understanding the parameters effecting
the performance of city bus service
Need for quick incident (accidents, breakdowns, etc.) detection
and improved reaction times on the incident response.
Need for improvement in financial performance through better
operational, maintenance and financial control.
Depot Activities Need for efficient process for scheduling of trips, vehicles and
crew
Need for automated data of revenue from bus fares.
Need for efficiency in monitoring of operations as per
schedules
Need for real-time guidance to crew when required.
Need for reducing revenue leakage and improving efficiency in
traffic inspections.
Need for data management and analysis at depot level.
Need for automating maintenance and other depot activities
Need for capacity building and training using technology for
bus operations.
Need for increase in productivity of staff by improving efficiency
in activities performed.
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
15
2.2 Current Efforts
CTU had implemented a few projects in the past years for bringing technology into its operations and
maintenance. The details on base scenario have been discussed in the report on city Bus
modernization plan. The same section has been extracted and presented in APPENDIX 1 in this DPR.
However the summary of base scenario current efforts for technological interventions of city bus
service is given below. The following are the different initiatives that had taken place for CTU city bus
operations in the past few years:
Exhibit 11: Route Information Provided on CTU Website
CTU has introduced some of DMS modules
Vehicle and Crew Scheduling
Waybill Management System
Attendance Leave Information System
Store Inventory Management System
Depot Management System
In all the JnNURM sanctioned city buses, the on-bus ITS (OBITS) is present with, GPS devices, CCTV cameras, Driver Console unit Variable Message Signs
In Bus ITS Provision of information on
routes in CTU website.
“Chandigarh Bus Guide” Mobile Android Application is provided by a Private Agency
PIS & Feedback
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
16
The current status of different activities of CTU along with level of technology intervention in
executing/providing those activities/services is presented in the Exhibit 12 below:
Sl. N
o.
Cat
ego
ry
Activities or Service
Pre
sen
ce o
f
Act
ivit
y/Se
rvic
e
If Present: Level of Technology Intervention
Man
ual
Full
Par
tial
Just
Init
iate
d
1
Ad
min
istr
atio
n
HR Management
2 Performance Monitoring
3 Monitoring service level standards adherence
4 Bid Contract Management
5 Legal Cases Management
6 On-Route Driver Guidance
7 Infrastructure Development/Asset Monitoring
8 Purchase Management
9 Access to Guidelines/Manuals and Procedures
10 Statistics Management
11 Accounts Management
12 Adequate Data Availability
13 Periodical Scientific Operations Planning
14 Monitoring of SLAs of Contractors
15 Marketing & Branding
16 Fare Integration with other modes
17 Training Activities for staff
18 Staff feedback address
19 Marketing of city bus service
20 Coordination between Head Office & Depots
21 Vehicle Tracking
22
23
Pas
sen
ger
Serv
ice
User information and guidance
24 Surveillance in Buses
25 Surveillance at Bus Stops/Shelters
26 Ticketing (Fare collection)
27 Passenger feedback/Grievance address
28 Handling with Passes and Concessions/Discounts
29
De
po
t
Parking Management
30 Scheduling Operations
31 Waybill Management
32 Traffic Inspection
33 Traffic and Revenue Reconciliation
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
17
Sl. N
o.
Cat
ego
ry
Activities or Service
Pre
sen
ce o
f
Act
ivit
y/Se
rvic
e
If Present: Level of Technology Intervention
Man
ual
Full
Par
tial
Just
Init
iate
d
34 Incident and Emergency Management
35 Maintenance Monitoring & Recording
36 Store Inventory Management
37 Fuel Management
38 Scrap Management
39 Attendance Management
40 Training Activities for staff
41 Management of Maintenance for Equipment
42 Surveillance
Exhibit 12: Current Status of Technology Intervention in CTU
It is observed that, even though the existing modules of TMS are comprehensive in terms of input they
capture, they have limitations in terms of reports which need to be addressed. Also, there is very few
trained staff available to maintain and utilize these software modules efficiently.
The following are the key limitations in existing modules of the Transit Management System (TMS)
for the modernization process:
Waybill System
The system was developed for manual ticketing process currently used by CTU
The current process need to be substantially overhauled for proposed ETM based ticketing.
The current application provides multiple reports, but has limitations to support decision
making due to lack of reports by flexible filters (by conductor by month, by month,
comparison for various months, for various routes, for various routes for multiple months,
etc.).
Scheduling & Planning System
The system was developed with long-distance buses in mind, hence it does not provide for
the intermediate bus stops in each route.
It is not possible to provide a computer generated schedule that consists of multiple routes
for city services from the system.
The reporting system is inadequate for city bus service operations
Duty rotations for the drivers and conductors are being set only the day before the
operations, which makes it complicated for drivers and conductors to plan more than one
day ahead.
Driver and Conductor duty allocation is done through arbitrary process since rules for
allocation cannot be fed into the system.
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
18
Leave Management System
The system is not in operations due to various problems with inputting information.
Stores & Inventory Management System
This is a new system developed by NIC, but use of which is limited to a handful of CTU
personnel.
The Stores manager and many of the other staff are still more comfortable with the manual
process. Hence the system is underutilized.
The application is quite extensive, but comes without any user manual.
The system has limited flexibility in extracting reports by various filter parameters.
The application lacks dashboards and other user friendly features that can support decision
makers.
On the AVL system, the new buses are being delivered by different manufacturers with on-board
ITS equipment as per UBS-II specifications. The manufacturers are required to share the details
of the ITS equipment and the setup needed for CTU. It is necessary to develop common back-
end ITS software for all the buses being supplied by various manufacturers mainly for ease of
operations. A separate memo has also been submitted to CTU on this issue which is attached as
an APPENDIX 1-B with this report.
2.3 Organizational Structure
CTU was established in the year 1966 with a fleet of around 30 buses and now provides bus services
to the public covering the city, suburbs and the neighboring states. CTU is also a member of
Association for State Road Transport Undertaking (ASRTU). The organizational structure of CTU is
been shown in the Exhibit 13 below.
General Managers (2),
All Depots
Assistant Divisional
Manager (Technical &
Stores)
Assistant Divisional
Manager (Traffic &
Commercial)
Assistant Controller
(F&A) (H)
Superintendent (Head
Office)
Superintendent
(Recruitment Cell)
Works ManagerAssistant Controller
(F&A)Superintendent
Preventive
Maintenance
Assistant
AccountantEstablishment
Assistant
Director, Transport,
Union Territory,
Chandigarh
Purchase Section &
Stores
Station Supervisor
(Traffic)
Care Taker (Nazir)
Care Taker (Bus Stands)
Statistical Assistants
Budget Assistants
Building Assistants
Esstt. Asstt. (H)
Esstt. Asstt. Drivers
Esstt. Asstt. Conductors
Esstt. Asstt. Management
Esstt. Asstt. Workshop
Identity Card Clerk &
Dispatch Work
Esstt. Asstt. General (H)
Compassionate Appointments,
Election Work,
All type of Recruitment Work
Exhibit 13: Existing Organizational Structure of CTU
Observations on Organizational Structure of CTU:
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
19
The existing CTU organization is established at two levels viz. central office level and depot
level.
General Managers at central level are responsible for management of depots. Depot doesn’t
have dedicated Depot Managers associated with each depot as is the general practice.
There is a lack of adequate trained technical staff for planning and design of operations.
There is no separate team for marketing and public outreach activities.
It is found from the site visits and discussions with CTU that the General Manager carries
multiple responsibilities.
There is a separate section to look after legal issues related to CTU.
The CTU is directly under the umbrella of Chandigarh Administration (CA) which is beneficial
in terms of quick decision making and co-ordination with authorities of CA.
The organizational structure has been defined for nature of operations of CTU few decades
ago but at present the activities have been modified but not the same have not been reflected
back in the organizational structure accordingly.
All the purchases happen at central level only.
Exhibit 14 shows the broad picture of current practice in CTU for city bus services.
KEY ACTIVITIES OF CTU DESCRIPTION
Overall Management and
Administration
CTU is headed by Director Transport of UT. Various functions are
managed by the General Manager, Assistant Dvisional Managers,
Assistant Controller, Superintendents. The present organizational
structure has been presented in Exhibit 65.
HR Management Typically CTU recruites all the employees on full time regular employment
basis. Recruitment is based on written test and practical tests. However,
CTU has now initiated the process of recruitement of drivers and
conductors under manpower supply contract. All the depots are managed
under General Managers of corresponding depots. Daily attendance and
leaves of employees are managed at depot level only. Currently MIS is
being used for management of leave information at all the depots.
Bid and Contract Management All the contracts and bids are managed at the central level under the
Director, CTU. There is also a ‘legal cell’ present in the head office for
resolving any issues.
Public Relations Management CTU publishes all the routes and other information in their website
(http://chdctu.gov.in/). It also accepts comments/ suggestions from public/
users online or directly at head office and accordingly CTU resolves those
issues. It also publishes all the notifications on the website.
Capacity Building There is no specific cell for capacity building/ training but the newly
recruited drivers and conductors get trained by the senior drivers/
conductors.
Co-ordination with other
Departments
As CTU comes directly under UT, the co-ordination with other
departments such as engineering, urban planning, etc. is done at Director
or Secretary level from Chandigarh Administration. As CTU operates long
route buses as well, any integration of the long distance routes with city
bus routes and associated facilities is easy.
Bus Operations Planning &
Design [Technical Assistance]
There is no dedicated technical wing in CTU for bus operations planning.
CTU usually hires consultants for any major planning assignment. Any
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
20
KEY ACTIVITIES OF CTU DESCRIPTION
minor modifications in specific routes and time tables are done in-house
at General Manager level with approval from Director.
ITS Planning/Design &
Implementation
NIC (National Informatics Centre) has developed few MIS modules for
CTU’s usage. CTU has some dedicated staff at head office to look after
the utilization/ maintenance of MIS modules and to extract required
reports from the MIS modules.
Buses All the buses are owned by CTU. CTU procures new buses based on
demand and availability of funds.
Bus Shelter Development &
Maintenance
Inputs are taken from CTU as to where the bus shelters have to be
created but the bus shelters are developed and are maintained by
Chandigarh Administration. However, all the revenue from the
advertisements on bus shelters are forwarded to CTU.
Right of Way Development &
Maintenance
Right of Way (RoW) is developed by Chandigarh Administration and
Municipal Corporation only.
Bus Depot Development All bus depots are planned, designed and developed by Chandigarh
Administration. Bus depot infrastructure is maintained by CTU. CTU is
consulted by chandigarh Administration before finalizing any such
developments.
Bus Opetations Execution &
Monitoring
CTU operates and monitors the buses from all the depots. There are no
private operators. Traffic inspection is also done by CTU staff. All routes,
way bills, ticket and cash collection details are entered daily into the MIS
modules which are accessed from depots and Head office.
Maintenance4 of Buses All the buses are being maintained by CTU with its own staff, except for
100 buses which are being maintained under annual maintenance
contract by Tata. At present all bus depots have their own workshops for
major repairs too. Works Manager in Depot takes care of all the
maintenance activities at the depot level. NIC has developed the Stores
and Inventory application.
Scrap Disposal at Depots Scrap is stored at each depot and it gets auctioned for disposal as and
when the scrap quantity becomes considerable.
Fuel Management All the buses gets fuelled at their respective bus depots.
Parking of Buses All the buses are parked at corresponding depots only. A very few buses
are parked at route start points in order to reduce dead Km.
Statistics Management All depots prepares the operational and financial reports each month and
sends them to Head office and statistical department of head office
compiles all the reports at one place and calculates the performamnece
parameters for each depot. The required reports on route wise operations,
revenue, etc. are being managed from MIS modules.
Purchase for Stores All the purchases happens based on rate contracts of ASRTU. All the
purchases happen at central level.
Exhibit 14: Current Practice of CTU in Performing Different Key Activities of City Bus Services
4 It includes the preventive maintenance, repair maintenance, etc.
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
21
2.3.1 Special Purpose Vehicle (SPV)
As required by JnNURM norms, CTU has started a separate SPV for running the city operations. The
SPV, Chandigarh City Bus Services Society, is expected to run the city operations going forward.
However, there are various concerns that are listed here:
Current CTU staff is against the SPV, and has put a legal petition in front of the court to this
extent.
Only around 100 buses are long distance buses. Questions arise on how to accommodate the
1826 staff of CTU if the SPV is operational.
IBI has provided recommendations on the SPV structure (refer to Appendix M of the CBMP
Report).
CTU is developing the SPV with a vision of organic growth out of the current CTU structure
that can assimilate as much of the current CTU practices while leading to the SPV’s
independent performance in the future. The clarity on the roles and responsibilities of the SPV
is still evolving.
The contracting process of SPV which shall be independent of the CTU’s current contracting
processes still needs to documented.
2.4 Current CTU Processes
As with all State Transport Undertakings (STUs) in the country, CTU also has no written Standard
Operating Procedures (SOPs) for its various operations, maintenance, human resource planning or
other processes. The existing processes are mapped in the exhibits below for: (1) Operations, (2)
Maintenance, (3) HR, (4) Finance, (5) Ticketing, (6) Stores and (7) Scrapping are mapped in the
exhibits below. Currently, no specific process exists for Training in CTU.
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
22
Exhibit 15 Existing Operations
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
23
Exhibit 16 Existing Maintenance
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
24
Exhibit 17 Existing HR
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
25
Exhibit 18 Existing Finance
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
26
Exhibit 19 Existing Ticketing
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
27
Exhibit 20 Existing Stores Process
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
28
Exhibit 21 Existing Scrapping Process
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
29
2.5 Suggested Technological Interventions
Keeping in view the transportation needs of the Chandigarh City Bus services and the available ITS
technologies, ITS solutions that can provide the required transportation improvements are evaluated
and detailed in this section. The ITS solutions that are recommended for CTU bus operations are as
follows:
1. Provide Automatic Vehicle Location (AVL) with the following objectives:
a. Increased productivity of the transit system by improving the reliability of the system.
b. Reduced operational costs of the buses by developing a fleet management system
using the vehicle tracking mechanism.
2. Provide Passenger Information Systems (PIS) with the objectives of:
a. Improved customer service to the transit riders by information dissemination through:
i. Display boards at terminals and other prominent locations
ii. Web based portal
iii. External bus display boards for older buses to ensure bus information is
provided from front, side and rear locations for passenger convenience.
b. Reducing stress levels for commuters by providing prior knowledge of the bus arrivals
and other schedule information through:
i. SMS system that provides bus arrival information at all bus stops across the
Tri-city area
ii. Mobile application providing CTU city service information
iii. Commuter Portal that provides both real-time and static (schedule data) to
internet users
iv. Interactive Voice Response System (IVRS) for the passengers not
comfortable with website and SMS based information systems.
v. PIS boards at critical locations across the city
3. Introduce Electronic Ticketing Machines (ETMs) with Smart Card reading capability to:
a. Improve customer convenience
b. Reduce fare leaks
c. Improve understanding of demand by origin-destinations (passenger counts).
d. Provide information for new fare policies
i. Time-of-day pricing
ii. Special event pricing
e. Allows seamless bus transfers
4. Develop Transit Management Systems application that can support:
a. Scheduling and rostering software for Planning that will support improving bus
operations and crew management
b. Master database for drivers, conductors and various staff that can support
computerized leave management system to achieve better accountability from the
staff
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
30
c. Depot and Terminal management system to support decision makers with data on
activities performed along with resource and time requirements.
d. Workshop management system to better log the maintenance needs and activities.
e. Provide MIS reports on the various depot, terminal, workshop and bus operations
activities.
5. Develop a Transit Management Centre to achieve:
f. Stakeholder coordination (Traffic Police, etc.) through providing interaction and a
common data sharing location.
g. Improve bus schedule adherence and reliability, through a the AVL application and
alert monitoring system
h. Provide incident management capabilities by providing a centralized location for
viewing/identifying incidents and dispatching incident response teams.
i. Providing emergency dispatch by providing a link from the TMC to the hospitals with
ambulance service.
j. Improve reliability of service and efficiency of the operations through better oversight.
6. Perform data collection and archiving services with the objectives of:
c. Developing performance measures to continuously evaluate the performance of the
system.
d. Develop algorithms to enhance bus service planning, and create new fare policies.
7. Develop MIS/ERP dashboard for the project with the objectives of:
a. Providing holistic, integrated information to the CTU management through detailed
MIS reports and user friendly, flexible dash board consisting of tables and graphs.
b. Provide ridership and modeshare details on a daily, monthly and yearly basis using
filters in the dashboard. The information shall also be provided through filters by bus,
route, conductor/driver, schedule, origin, destination and various other useful decision
making parameters.
c. Provide passenger counts and revenue information in realtime and/or preset intervals
as stated by the Client during the design phase.
d. Provide route and schedule adherence information with various filters for the decision
makers to get an understanding of the ground problems.
e. Provide bus maintenance information in terms of preventive and reactive maintenance
(breakdowns, etc.).
f. Provide critical stores & purchase inventory details for decision support.
2.6 Suggested Processes for Modernization/Implementation of ITS
The recommended processes for: (1) Operations, (2) Maintenance, (3) HR, (4) Finance, (5) Ticketing,
(6) Stores (7) Scheduling (8) Training and (9) Scrapping are mapped in the exhibits below.
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
31
Exhibit 22 Recommended Operations Process
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
32
Exhibit 23 Recommended Maintenance Process
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
33
Exhibit 24 Recommended HR Process
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
34
Exhibit 25 Recommended Finance Process
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
35
Exhibit 26 Recommended Ticketing Process
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
36
Exhibit 27 Recommended Stores Process
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
37
Exhibit 28 Recommended Scheduling Process
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
38
Exhibit 29 Recommended Training Process
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
39
Exhibit 30 Recommended Scrapping Process
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
40
3 Options Analysis
3.1 Service Options
The Transit ITS industry is new in India and not yet mature. Internationally, there are essentially three
service options available for transit ITS: Traditional, Hosted, and Software as a Service (SaaS). These
three different service options are generally described as follows:
Option 1: Traditional - The most common service delivery approach in the transit ITS (mainly
focussed on CAD/AVL system) industry to date, this model assumes an agency-owned system,
procured from a ITS vendor, including all on-board and central hardware, software systems and
licenses. While an agency in this option owns the central system hardware it actually only
licenses the right to use the central system software, which remains owned by the vendor so that
licenses can also be sold to other transit agencies. The sales of software licenses and annual
software support provide a large part of the revenue stream used by the vendors for ongoing
software development and support to its overall customer base. The agency is generally
responsible for system maintenance and operations, often with a vendor under maintenance
contract. Functionality of products in this service delivery approach range from basic systems, to
those offering robust and advanced operational functionality with a high level of customization
available.
Option 2: Hosted - An emerging service delivery option that is very similar to the Traditional
model in terms of breadth of product availability (i.e., most of the Traditional ITS vendors are
offering, or considering offering, hosted solution delivery). While the central system hardware is
still owned by the agency and central system software licensing still purchased, the primary
difference is that the system is hosted and maintained at a facility operated by the vendor.
Theoretically, this would allow for easier central system updates, with the vendor holding more
responsibility for ensuring that service impact is minimal, and also responsible for more of the
system management and operations. There would be annual service fees to the vendor, with the
potential value proposition for the agency being if these fees would be more than offset by
reduced agency O&M costs.
o In India, the system can be hosted at the State Data Centers (SDCs). However, this
does not give the advantage of easier central system update. It will help in reducing the
cost of central system hardware.
Option 3: SaaS - Software as a Service has become a common delivery model for providing
many business applications in the IT industry, in which the software and associated data are
owned by the vendor and centrally hosted in the cloud, with access provided to customers on a
leased basis. The SaaS purchaser replaces any capital investment in hardware and licenses
with services fees, and likely in addition would have reduced O&M costs. In many market
sectors, SaaS is a preferred delivery model by customers looking to reduce IT support costs by
avoiding capital purchases and outsourcing hardware and software maintenance and support to
the SaaS provider.
In CAD/AVL Hosted and SaaS offerings,
onboard equipment is usually agency-owned in
the traditional manner. Although the onboard
equipment must inherently be located on the
vehicles, it could certainly also be leased
instead of owned. Outsourcing onboard
equipment O&M however is complicated by the
fact that it is normally expensive for an outside
vendor to provide the degree of onsite support
needed for high availability. For the Industry
Scan in North America, several different vendors within these service options were contacted, initially
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
41
through an emailed survey form and then follow-up telephone interviews. The vendor questions
focused on the level of functionality provided by the CAD/AVL system, and the functional and
integration capabilities of the onboard equipment.
Preliminary results from the vendor community indicated that while the SaaS option can provide cost
effective Automatic Vehicle Location (AVL) and Real- Time Passenger Information (RTPI) solutions
for the transit industry, the product offerings are generally very light in system functionality. Hosted
and traditional solutions provided adequate functionality, however many vendors offering a hosted
solution had not yet standardized a business model, and vendors vary their pricing structure client-by-
client. These details are specific to North America. In India, robust net connectivity is another issue
that was considered while evaluating the Hosted and SaaS options.
A review of the current state of practice in India and availability of service models determined that both
hosted and SaaS models are not viable at present as summarized in *Hosting in SDC instead of Vendor
site will reduce the cost
Exhibit 31. Traditional model where the agency owns the hardware and the software is considered the
best option at this time.
PARAMETER TRADITIONAL HOSTED* SAAS
Cost (NPV) ₹₹ ₹₹₹ ₹
Capital and O&M
Breakdown
Staffing Impacts
Connectivity
Robustness
Ability to Meet CTU
Needs
*Hosting in SDC instead of Vendor site will reduce the cost
Exhibit 31 Service Options
Recommendation: The Option 1: Traditional service model is recommended to be adopted given
the current stage of industry for Automated Vehicle Location (AVL) Systems, Fare Collection System
(FCS) Passenger Information Systems (PIS), Transit Management System (TMS).
3.2 AVL Alternatives
The various alternatives evaluated for AVL system were:
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
42
Option 1 – Do Nothing: This was not considered a viable option from the very start since the
new 483 JnNURM buses are all coming with installed GPS units capable of providing vehicle
tracking.
Option 2 – AVL on the New JnNURM Buses: A total of 134 existing buses with remaining
life cycle of at least 4 years are present in the CTU fleet. Since these buses do not have
existing AVL system on the buses, it was considered an option to not add AVL on these buses.
The following analysis was conducted:
o Advantages of Not Adding AVL to Existing Buses:
Experiences in India so far showed that installing sensitive equipment like
AVL systems has been difficult. It has been even more difficult to make them
functional and robust in the long run.
Integration between the new UBS-II equipment and the System Integrator (SI)
equipment will be complicated, especially since CTU has no contract
requirements that the Bus OEM has to support the integration.
As part of the Modernization a separate SPV, is planned for the city bus
services. It is deemed necessary to provide the management of the SPV with
information on all the buses to continuously improve the operations. Accurate
and timely data is quintessential for making the services optimal and create
positive growth and revenue.
o Disadvantages of Not Adding AVL to Existing Buses:
Having only certain buses in the fleet with next bus information is not
conducive for penetration of ITS system in the Tricity area and will defeat the
purpose of the whole project
Option 3 – AVL on All buses: The existing 134 buses and the new 449 buses will all be provided with AVL system. In the existing buses, the Single Controller Unit (SCU) and Bus Display Console (BDC) will be installed. All the buses will be integrated through a central AVL system software. The analysis on this option is as follows:
o Advantages of Including All Buses in the AVL System:
Next bus information will be available from all buses which will ensure that
the passenger has great confidence in the system.
Since, even the USB-II equipment will be provided by various vendors given
the buses are coming from various OEMs; the integration still needs to occur.
It is possible to procure the AVL equipment for the older buses that are UBS-
II compliant.
o Disadvantages of Including All Buses in the AVL System:
UBS-II is relatively new and the integration efforts are still in the early stages
in the country. Hence the understanding on sufficiency of UBS-II data
exchange formats, protocols and APIs is still evolving.
Recommendation: To satisfy the objectives of the project, Option 3 - AVL on All buses is
recommended.
3.3 Fare Collection Alternatives
CTU ticketing process is currently manual. Early in the project the team discussed various options
penned below:
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
43
Option 1: Do Nothing – This option assumed that no modifications will be made to the current
system of the manual ticketing to support existing or future operations. This option was quickly
rejected since one of the main objectives of CTU behind the modernization project is to
automate the ticketing process.
Option 2: Electronic Ticketing Machines (ETMs) - The option consists of ETMs with only
paper based ticketing. The analysis is as follows:
o Advantages:
ETMs with paper based tickets are commonly used across many State
Transport Undertakings (STUs) in India. The requirements, technology and
devices are well established to support CTU ticketing process.
ETMs will ensure automated ridership information is available for CTU
decision making process.
o Disadvantages:
Without smart cards, consumable cost for paper tickets and ink has to be
borne by CTU on a regular basis.
Extensive training and handholding will be required by CTU to migrate CTU
conductors from current manual ticketing to any other ETM based option.
Option 3: ETMs with Only Smart Cards – While ETMs with only smart cards was discussed
with the stakeholders, it was not considered as a viable option since many passengers can be
intermittent passengers and will not want to spend money on buying the smartcard (additional
initial cost on smartcard).
Option 4: Standalone ETMs with Only Smart Cards – In this option, having smartcards
installed on poles in the buses without conductors was discussed. The main advantage is the
reduction in staff and the corresponding staff costs. It was rejected at the every outset since it
will create a huge change in the operations for CTU. In addition, the honour system required
in passengers to ensure successful ticketing without conductors is not considered viable at
this time.
Option 5: ETMS with Smart Cards, Standard Credit/Debit Cards & Paper Tickets –
Handheld ETMS with conductor that can read smartcards, standard credit/debit cards and
also discharge paper tickets was analyzed:
o Advantages:
Provides ridership information, reduces leakages through smartcard systems,
provides better visibility.
Provides open system through using standard credit/debit cards.
Ensures that regular, intermittent and occasional users are all
accommodated.
Reduces consumable usage
o Disadvantages:
Still requires consumables for the paper ticket users.
Option 6: ETMS with Bank Based Cards – Handheld ETMS with conductor that can read
Bank Based Cards (also called cobranded cards) and can discharge paper tickets was
reviewed:
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
44
o Advantages:
Banks will invest in the system and can reduce the cost of Point of Sales for
the agency.
With the ever increasing number of cards that passengers have to carry, a
bank based card might be preferable to passengers.
o Disadvantages:
Banks have a fee (0.03%) on each ticket transaction of about which will
increase the cost of travel for the passengers.
The interest on the epurse for each passenger will mostly not be provided to
CTU. This interest will benefit the Bank.
The cobranded cards are not yet extensively used for transit in India. For
BMTC, the architecture is still being developed by Axis Bank for Rupay cards.
Recommendation: With the objectives of: (1) automated ridership data, (2) reducing leakages, (3)
meeting passenger needs and expectations, and (4) not requiring additional research or increased cost
to passengers; Option 5: ETMS with both Smart Cards & Paper Tickets is recommended.
3.4 Communication for Fare Collection Alternatives
The following options were evaluated:
Option 1: No Realtime Data Transfer – In this scenario, the ETM data transfers occur only at the
end of the day. The transfer at the end of the day can be through wired or wireless mode at the depots.
This is a common process of transfer and is closer to the current processes of CTU that at the end of
the day the conductor comes to the depot to settle the account. However, based on the project
objectives – the stakeholders were of the opinion that ETM data should be available for review at least
every hour to reduce leakages and get a better sense of how passenger boardings/alightings are
happening in realtime.
Option 2: Realtime ETM Data Transfer Directly to Control Room – In this option the ETMs will
come with inbuilt GPRS connectivity and will transfer the ticketing data at the user set time period to
the control room. The analysis of this option is as follows:
Advantages:
o Information is available in realtime and can be used to track route, TOD and conductor
trends to reduce leakages and support improved operations practices.
o The ETMs are not dependent on other bus systems (SCU) to transfer the data.
o No integration requirements exist since the ETM can directly send the data to the
Control Room.
o These kind of ETMs are being used in India, ensuring the technology is mature.
Disadvantages:
o Separate simcards are required for the ETMs, which is additional monthly operational
cost.
Option 3: Realtime ETM Data Transfer Through SCU – In this option the ETMs will come with inbuilt
Bluetooth or Wifi connectivity and will transfer the ticketing data at the user set time period to the Single
Controller Unit (SCU). The analysis of this option is as follows:
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
45
Advantages:
o Information is available in realtime and can be used to track route, TOD and conductor
trends to reduce leakages and support improved operations practices.
o Separate simcards are not required for the ETMs reducing the monthly costs.
o Location information and other statistics from the SCU can be combined with ETM
data to get a richer set of information that can support better decision making.
Disadvantages:
o The ETMs are dependent on the functioning of the SCU to transfer the data.
o Integration of ETM with SCU is required for sending the data to the Control Room.
exchange formats, protocols and APIs is still evolving.
UBS II does not have protocol requirements clearly set for transferring data
with another device.
Recommendation: Both Option 2 and 3 provide the solution requirements of CTU. To reduce the
regular operational cost and provide a richer dataset that combines the ETM information with SCU
data (in the long run), Option 2: Realtime ETM Data Transfer Directly to Control Room is
recommended.
3.5 PIS Information Alternatives
Traveler information is critical for transit bus patronage. Physical displays, SMS, IVRS, Web Portal
and Mobile Application were all considered for disseminating PIS information. It was decided that all
these options will be for information dissemination. Within the PIS display, various alternatives were
evaluated:
Option 1: PIS Display at All Bus Shelters in the City:
Advantages:
o Passengers at bus shelters need information and providing PIS displays at all/most
bus shelters will ensure the visibility of ITS project and also provide the information.
o There will be lesser requirement for other modes of dissemination if display boards
are provided all through the city.
Disadvantages:
o Vandalism, and in-turn providing security to all the display boards across the city is a
big concern.
o In routes where the frequency of buses is less than 8 minutes, the need for information
is not high (peer discussions mentioned that passenger behavior analysis shows that
at less than 8 minute bus frequency the passenger frustrations do not exist). Hence,
providing display boards at all these locations is costly and mostly unrequired.
o Maintenance of these equipment spread across the city is a concern as seen in other
cities that installed PIS displays in a larger number of locations.
o Since the city services will keep expanding, adding PIS displays at all new locations
is another concern.
Option 2: PIS Display at Selected Locations in the City:
Advantages:
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
46
o Installing PIS displays at high volume locations that are also secure ensure that ITS
project is visible.
o Vandalism and maintenance concerns will not be as important and will not affect the
success of the project.
Disadvantages:
o Uneducated Passengers also shall mainly depend of SMS and IVRS services, hence
training and education will become paramount.
Recommendation: Option 2: PIS Display at Selected Locations in the City was recommended to
ensure reduction in cost and mainly to alleviate security and maintenance concerns.
3.6 PIS Display Type Alternatives
LED Matrix displays and LCD boards are commonly used for display of bus information in India.
Traditionally LED matrix display boards were used, but now we quite a few industrial grade LCD boards
being used. Experiences in other implementations in India showed the following:
PARAMETER LCD DISPLAY LED MATRIX DISPLAY
Cost (NPV) 1.2 to 1.5 times * ₹ ₹
Capital and O&M Breakdown* ₹ 1.1 to 1.2 times * ₹
Staffing Impacts for
Maintenance
Lifetime 50,000 hours (100,000 hours for some
models)
100,000 hours
Testing COTS Product, no testing required Testing required and difficult to
conduct for larger boards since many
labs are not set for LED board testing
Power Medium Low
Space vs. Display Content High Low (takes a 8 line LED board of
about 2m height to display 4 buses in
a page in local language)
Display Quality High Medium to Low (single colour, pitch
has impact of quality of local
language display)
File Types Text, Audio, Video, Animation, Flash, files
can be played
English text is supported properly;
bitmap have to be created for local
languages. Graphics are difficult to
show using the LEDs.
Ability to Meet CTU Needs
* From discussions with implementers in India
Recommendation: LCD Display was recommended to ensure continuous display with minimal
maintenance needs.
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
47
3.7 Transit Management System (TMS) Alternatives
Depot Management, Workshop Management, HR & Payroll, Accounting & Finance Systems, Stores
& Inventory Systems, Scheduling & Planning system, etc. have been combined as Transit
Management Systems for this project. Enterprise Resource Planning (ERP) systems have been used
in the country for some of these functions. In the CTU scenario, as discussed earlier, the Stores and
Inventory System has been recently developed. Waybill system, scheduling & planning system and
leave management system were existing for multiple years.
The Waybill system is the ticketing system for manual ticketing process. For the ETM based
ticketing system, the current waybill system will not provide the required features. Hence, the
Way Bill application is recommended to be discarded and a new application developed as part
of this project. CTU staff working on the ticketing system agreed that the ETM introduction will
require new software development.
Scheduling & Planning software currently under use by CTU is a combination and of manual
and computerized process that provides bus & crew rostering for the next day. The software
functionality is setup mainly for long distance buses. The application provides only origin-
destination points, it is also limited in providing any level of analysis to optimize/improve
planning of city services. Hence, the Scheduling & Planning application is recommended to
be discarded and a new application developed as part of this project. CTU staff working on
the software also recommended that an improved application is required for bus and crew
scheduling/rostering for city buses.
Leave Management System features are limited and is currently not used by CTU. CTU staff
recommended that this application needs to be developed as part of the project. The
recommendation from the consultant also that leave management needs to be part of the
project.
Stores & Inventory Management System was developed about a year back for CTU operations.
However, it was observed that while a computer based system is being updated with information, it
was not used for inventory control (ordering of equipment based on inventory levels, etc.). The Stores
Manager still depends on his experience and parallel manual processes for stores & inventory
management. Two to three of the CTU staff of well-versed with the application and have been able to
maintain the computerized system. No manual is available for the application and gaps were found in
MIS reporting and a few other features that have not been addressed. The following two options were
evaluated for the Store & Inventory Management System:
Option 1: Integrate Current Project with Existing Stores & Inventory Module – In this option, the
Stores & Inventory Management System developed by National Informatics Centre (NIC) will be
retained and integrated with the rest of the System Integrator modules. The advantage is to retain a
system that is recently developed and serves the requirements of CTU. The major disadvantage is the
need for integration which is always complicated in such systems.
Option 2: Discard Existing Stores & Inventory Module – Discarding the module has the advantage
of not requiring integration which can help the project move faster and attract more System Integrators
to bid on the project. However, this will create Government of India Audit issues since money was
spent on the system.
Recommendation: Option 2: Discard Existing Stores & Inventory Module was recommended to
ensure the project doesn’t get bogged down by system integration issues. Discussions with CTU staff
revealed that getting support from NIC for integration will be extremely complicated. Key staff of CTU
recommended that the SI should develop an improved and integrated Stores & Inventory Management
system.
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
48
4 System Architecture & Components
In this section, the major ITS components identified for CTU are presented.
System Sub Systems Utilization in different Activities
Exhibit 32 CTU ITS Components
1 Automatic Vehicle
Location System (AVL)
Vehicle Tracking System for Buses
Single Controller Unit (SCU)
Bus Console Display Back-end Application
Software Communication System
Real time bus arrival information Real time monitoring of movement Scheduling/Bus Dispatch Ensuring schedule adherence Driver on-route guidance Monitoring SLA’s of contractors Incident/Emergency Management Fuel Management Performance Monitoring MIS
3 Fare Collection System Electronic Ticketing
Machines Pass issuance/renewal
system Pass (Smart card)
Validation Waybill Management
System
On-board Fare Collection Pass Handling Concessions and Discounts
Handling Fare Integration with other modes Data Availability for future planning
purpose Traffic Inspection Traffic and Revenue Reconciliation MIS
5 Central Control Centre Data Archival Display of surveillance Display system for bus
monitoring Communication System
Performance Monitoring On-Route Driver Guidance Adequate Data Availability Monitoring of SLAs of Contractors Monitoring Vehicle Movements Emergency/Incident Management Passenger Guidance
6 Data Archiving Tapes Servers
NVRs
Supports Analysis and Planning
2 Passenger Information
System (PIS)
PIS at Bus Shelters On-board PIS External PIS En-route or pre-trip PIS Back-end application
software Communication System
Real time bus arrival information Customer interaction and experience
4 Transit Management
System & & MIS
Trip Scheduling & Vehicle Assignment system Crew Management/Rostering system Fuel Management Store Inventory Management system Vehicle Maintenance Management system Attendance Management System Passenger feedback & grievance address
system Passenger feedback system Infrastructure/Asset Monitoring System Purchase Management Contract/Bid Management HR Management System Management Information System (MIS)
Automated depot, terminal and workshop activities
Decision making
Integrated systems approach to enhanced operations.
In-bus security cameras on older buses
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
49
4.1 System Architecture
The system architecture is illustrated in Exhibit 33. Data Centre will consist of all the Servers required
for the proposed system. The following sub sections details the each of the system components.
Exhibit 33 System Architecture
4.2 Automatic Vehicle Location (AVL) System
Automatic Vehicle Location system improves the reliability of the bus/transit system, which improves
confidence among the commuters and reduces the waiting times for commuters’. Information from
real-time tracking of buses will be disseminated to commuters through PIS, websites and mobile
applications. It also provides information on the common bottlenecks and allows transit agency to work
with Traffic Police and the Municipal Administration to improve these bottlenecks and improve transit
travel times.
4.2.1 Overview
Automatic Vehicle Location System is a major component of the ITS requirements of this project. Key
specific purposes are discussed below but not limited to:
Improve on-time performance: Monitor the movement of the city buses and provide continuous real-
time information to drivers to speed up or slow down between established time points and provide
transit planners with systemic schedule adherence bottlenecks on the route. This information will
support the transit planners in planning the operations better.
Increase Ridership: Make bus travel simpler and more attractive for commuters by:
Improved on-time performance of buses enhances the reliability among commuters,
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
50
Information of routes, bus schedules, ETA/ETD5, and next stop information for onboard
passengers,
Bus information through SMS, website, etc.
Availability of mobile applications to enhance use of system.
Improve Schedule and Planning: Provide MIS Reports for bus operations, Terminal, Depot and
Workshop Operations. Automate data collection, and improved accuracy and accessibility of data for
the transit planners will be achieved. Through the real time monitoring, the missed/deviated trips can
also be tracked and actions will be taken accordingly. The rescheduling dispatching of trips can be
also be done effectively using AVL.
Improved monitoring of private operators: The AVL system also improves the accountability in the
operations. In case of city bus operations through PPP in future, the bus operators can be monitored
for the service level adherence and also the same data can be used in handling payments to the
private operators.
Efficient Incident Management: Using the real time monitoring of operations, the incident
management during any emergency or break down can be quicker and efficient.
4.2.2 Buses
379 buses were approved through the JnNURM scheme. An additional 49 buses are also being
procured in lieu of the condemned buses. The information on the bus procurement with their model
and procurement dates is provided in Exhibit 34. This list does not include the buses existing in the
depot that are condemned. All the condemned buses are expected to be disposed by October, 2015.
Timeline Make Description Bus type No. Of buses Total
As on Feb 2015 Leyland Existing buses Mini AC 34 34
As on Feb 2015 TATA Existing buses Standard AC 40 74
As on Feb 2015 TATA Existing buses Standard Non AC 60 134
As on Feb 2015 SML ISUZU New semi- low floor Midi AC 80 214
As on Feb 2015 SML ISUZU New semi-low floor Midi Non AC 30 244
As on March 2015 SML ISUZU New semi-low floor Midi Non AC 60 304
By October 2015 TATA Low floor Midi Non AC 49 353
By December 2015 Corona New semi-low floor Standard AC 20 373
By December 2015 Corona New semi-low floor Standard AC 50 423
By December 2015 Corona New semi-low floor Standard Non AC 45 468
By December 2015 Corona New semi-low floor Standard Non AC 45 513
Note: Information as per September 18, 2015
Legend
Existing Buses (without On-Board ITS) Recently Delivered Buses (with On-Board ITS) Buses Procured, Awaiting Delivery
Exhibit 34 Existing and Approved Bus Procurement of CTU
5 ETA – Expected Time of Arrival
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
51
4.2.3 AVL Functionality & Benefits
S.NO. FUNCTIONALITY BENEFITS STAKEHOLDER
1 Vehicle Tracking – Real-
Time Bus Locations
Situational Awareness: AVL software
provides improved situational
awareness which helps dispatchers
manage larger fleets than before.
Dispatchers
2 Vehicle Tracking, Arrival
Time Information
Performance & Reliability: The
transmission of schedule adherence
feedback helps to maximize on-time
performance and reliability
Traffic
Department,
Depot Managers
3 Breakdowns & Incident
Reporting in Real-Time
Proactive Approach: AVL helps the
organization to be proactive in
addressing operational issues,
including more timely and effective
reaction to service disruptions
Depot Managers,
Traffic Controllers
4 Estimated Time of Arrival
(ETA) Information
Traveler Information: AVL provides
real-time next bus predictions to
customers both pre-trip and enroute.
Passengers
5 ETA with Information
Dissemination
Increased Ridership: Next bus
information reduces customer anxiety
and improves customer confidence in
the system leading to increased
ridership.
Agency
6 AVL Data Archival Improved Planning & Scheduling:
Availability of reliable historical data
and incident information provides an
excellent basis of planning & schedule
adjustments that can support improved
operations and revenue.
Traffic
Department,
Agency
4.2.4 AVL System Concept
The new buses now being procured through JnNURM scheme come with onboard ITS (OBITS)
equipment. This equipment confirming to Urban Bus Specification II consists of:
Single Control Unit (SCU)
Bus Driver Console (BDC)
Passenger Information System (PIS)
Security Camera Network (SCN) and Cameras
Vehicle Health Monitoring and Diagnostic (VHMD)
An additional 134 existing buses also require AVL system and on 34 buses driver console to be
installed. Among the existing buses, 34 buses have to be fitted with inner destination boards, 34 need
both front and side destination boards and 170 buses have to fitted with side destination boards. CCTV
cameras have to be fitted on 134 existing CTU buses. List of buses which need AVL units, destination
boards and cameras are given in Appendix 4. Bus manufacture or OBITS equipment Original
Equipment Manufacturer (OEM) is expected to provide UBS-II compliant protocols that the System
Integrator shall use for integration.
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
52
Given that none of the existing buses have any AVL equipment, the SI shall integrate OBITS
equipment with AVL equipment that SI shall deploy on the project. The AVL System will implement
core technology to integrate with the OBITS equipment and enable CTU to optimize scheduling,
improve operation efficiency, real-time information for vehicle arrivals to commuters, systematized
vehicle maintenance, and crew rostering. The architecture for the project based on the needs,
objectives and goals of the project is shown in Exhibit 35.
Exhibit 35: AVL & PIS System Architecture
The AVL System vehicle technology components to be implemented under this project are as follows:
Single Control Unit (SCU): The SCU is at the heart of OBITS equipment’s, all the other equipment’s
shall be connected to the SCU. The SCU shall have open protocols as mentioned in UBS II to integrate
with various sub systems. Two way voice communication between crew at bus to dispatcher at TMC,
waypoint data transfer through GPRS connectivity to central system at data centre, events like harsh
breaking, over speeding, etc., It has GPS and GPRS receiver in it, GPS & GPRS antenna exposed
outside to sky to get good signal. In case of dark zone areas all the data will be stored in SCU for
certain amount of period. Diagnostic logs and other files shall be stored in SCU will transfer to AVL
central system at data centre.
Bus Driver Console (BDC): On board electronic information exchange peripheral interface to
the SCU that allow crew to view and exchange information with dispatchers using the AVL
central software. The BDU shall be shown the current location of the vehicle on map, next
stop and distance, live stream of on board camera, emergency messages sent by dispatchers
from AVL central system.
Automatic Vehicle Announcements: Provides commuters with automated next stop information
and other announcements sent from TMC by dispatchers.
Security Camera Network (SCN including On board Cameras): Hardware that manages the on
board camera, stores recorded image/video, and integrate with SCU to allow for data transfer
to the video management software via WLAN at Depot/Terminal on request by dispatcher.
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
53
The video will be stored for 2 days on the NVR provided along with the bus. This information
will be continuously overwritten.
In bus signs: The In bus signs, which provide riders with route, approaching stop and
destination information, will be integrated with the SCU to allow these to be automatically
changed approaching the start of each trip. Also it supports Ad-hoc messages sent from
Control Centre by dispatcher.
Vehicle Health Monitoring and Diagnostics: Hardware that helps to monitor and alert the vehicle
engine behavior and status, fuel level and its status, breaks and other mechanical system
status in vehicle as mentioned in UBS II. This equipment integrate with SCU to transfer any
mechanical events on the fleets as soon as it happened and end of the day all the events and
logs will be transferred to Transit Management System (TMS) at depot, workshops, terminals,
etc.
The proposed ITS system would support a fleet that is mix of regular (134 buses without
OBITS) and OBITS (379 buses with OBITS) buses, the Systems Integrator would be expected
to ensure (given requisite support from Bus manufacturers) seamless interoperability between
the Transit Management Center and the different types of buses.
4.2.5 Functional Requirements
The operational needs for AVL were identified through discussions with CTU staff.. The following
needs represent operational requirements to achieve the goals and objectives of the system:
Improve on-time performance of city buses by automating and monitoring vehicle location and
schedule adherence.
Provide easy to use data to the transit planners to continuously improve the bus scheduling
and crew rostering in the tri-cities.
Provide centralized databases for crew and other assets to ensure that needed data flows
occur seamlessly.
Provide convenient customer interfaces for accessing real time data to increase ridership
(display boards at bus stops, SMS, IVRS, commuter website and mobile applications).
Install PIS displays at bus stops, terminals and depots with information as per needs of the
audience at these locations.
Integrate with OBITS equipment on the buses that are being procured through JnNURM
scheme. Ensure camera data is downloaded from the SCU on a regular basis either at depots
or terminals.
Potentially provide proposed system compliant OBITS equipment on the city bus services.
Integrate with Transit Management System and other subsystems such that central
overlapping data (such as crew data, bus scheduling data, etc.) exists in only one database.
Provide information to passengers to ease transfers within city and between city and long
distance services.
Provide GSM/GPRS connectivity for the SCUs through a reliable network provider that will
ensure continuous data flow as required by the project.
Provide primary and secondary data connectivity to control room equipment and all PIS
display proposed for the system.
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
54
Provide primary and secondary power (UPS, DG, etc.) so that there is continuous power for
the system to function.
Seek long-term operations & maintenance agreements to support the ITS system.
Seek maintenance agreement that includes training for all staff involved in the running of the
system.
4.2.6 AVL Central System
The System Integrator expected to provide the complete solution for CTU fleets with integration of
AVL component as mentioned earlier. Exhibit 36 below illustrates AVL central system expected to
develop by system integrator.
Exhibit 36: AVL Central System Schematic
AVL Monitoring and Scheduling Software: The software will integrate with the Single Control Unit
(SCU) of all the fleets of CTU to provide real-time fleet status and operations, two way voice
communications to crew from TMC, incident management, real time information and alerts, and MIS
capabilities. Major, medium and minor alerts shall be available in a convenient, easy to use manner in
the software. The application shall consist of an accurate GIS map of the region with layers for roads,
landmarks, geographic features, etc. The software shall provide the flexibility to support various user
modes and user preferences including map views, alert configurations and
Software that streamlines and improves schedule preparation, immediate rescheduling as demand,
adding trips intermediately, cancellation of trips which is not expected to run, and allows for greater
integration with operations and other software modules. The dispatcher at TMC shall able to react
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
55
against the alerts sent from SCU quickly. AVL system shall support at extend of business
requirements. It shall support demand responsive scheduling and dispatch management. AVL system
have ability send updated configuration of OBITS equipment from TMC. AVL software shall able send
voice files of location/landmark from TMC to SCU. AVL have feature to identify that the vehicles are
not on operations will not schedule for future, in which AVL and Transit Management System database
shall provide that information.
Real-Time Passenger Information of Display Screen: Software module (infotainment) integrated with
the AVL system and Scheduling module to provide real-time fleet information to the commuters. PIS
board shall capable to display images, videos, instant message, and predefined message in various
formats. All these advertisement shall be stored in the system and it shall have ability to generate the
report for billing purpose.
Real-Time Passenger Information of Website: A website which provides CTU commuter with fleet
locations and real-time predictions.
Real-Time Passenger Information of Mobile and SMS: The Mobile application which provides
commuters with fleet locations and real-time predictions on the Map through GPRS. Commuter those
does not have GPRS connection can use SMS to get the real time information on their mobile phones.
Interactive Voice Response (IVR): Automated telephone software that provides passenger information
(schedule, real-time, demand response confirmations) and receives passenger complaints. There will
dispatchers at TMC to assist commuters during CTU operation hours.
Transit Management System (TMS): The TMS software shall consist of Depot Management System
(DMS), Workshop & Terminal Management System, Inventory Control, HR & Payroll, etc. and shall be
integrated for master lists with the AVL system to provide effective information exchange of fleets and
crew between these sub systems without overlap. All the image/video recorded shall be transfers the
data at depot to video storage through wireless connection. Similarly VHMD device transfer its logs
and event to TMS software to effectively manage the fleet end of the day.
Real-Time Data Feed: A data feed of fleet shall be available on demand for CTU or third-party
developers to provide real-time fleet information through mobile applications. The format of the data
feed shall be in GTFS-RT, it could be decided during the design stage.
4.3 Passenger Information System
4.3.1 Overview
The PIS provides automatic notification to passengers on next bus arrival/departure which shall be
deployed at each station and terminal, displayed in the website and made accessible on the mobile
application. The primary purpose of the PIS is to inform passengers of next bus arrival/departure times
per direction of travel. Data provided to the commuters will be in the form of:
Static Data – Schedule information only;
Real Time and Static Data – Scheduled information with exception reporting if the difference
between the scheduled and actual arrival time exceeds a configurable threshold;
Real Time – Provide expected arrival or departure times;
Other ad-hoc information including time clock.
PIS signs shall be industrial grade LCD based single-sided sign boards that provide static or real-time
information to the commuters at bus stops and terminals. Using the PIS signs, the control centre
operators shall also have capabilities to communicate messages and emergency management
information on a-per station or a system-wide basis. List of bus shelters where the PIS display boards
will be installed are given below:
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
56
S.No. Bus Station Name Number Display Type
1 ISBT -43 3 Industrial Grade LCD
2 ISBT -17 3 Industrial Grade LCD
3 PGI Sec-12 1 Industrial Grade LCD
4 Punjab University Sec-14 1 Industrial Grade LCD
5 Pec College sec-12 1 Industrial Grade LCD
6 Punjab civil Secretariat 1 Industrial Grade LCD
7 Punjab Harayana Court 1 Industrial Grade LCD
8 IT park 1 Industrial Grade LCD
9 Mani Majra 1 Industrial Grade LCD
10 Mansa Devi 1 Industrial Grade LCD
11 Ram Darbar 1 Industrial Grade LCD
12 Maloya 1 Industrial Grade LCD
13 Dhanas colony 1 Industrial Grade LCD
14 S P Barrier 1 Industrial Grade LCD
15 Sec-65 Mohali 1 Industrial Grade LCD
16 Sec-62 ISBT Mahali 1 Industrial Grade LCD
17 ISBT Kharar 2 Industrial Grade LCD
18 Railway Station Chandigarh 1 Industrial Grade LCD
19 Lake 1 Industrial Grade LCD
20 H O D Chandigarh 1 Industrial Grade LCD
21 Housing Board Chowk 1 Industrial Grade LCD
22 New OPD (PGI) 1 Industrial Grade LCD
23 Rock Garden 1 Industrial Grade LCD
24 Rose Garden sec -16 1 Industrial Grade LCD
25 Phase -6(Sector 56) 1 Industrial Grade LCD
Total 30
Exhibit 37: List of PIS Display Boards to be installed at Bus Shelters
Static and real-time information shall be provided for passengers through:
Website will publish the real-time bus position, arrival and departure details, trip cancellation and other
alerts. Through the webpage, commuters can plan their trip by accessing the schedule details of the
buses and real-time position.
Mobile SMS will support users without access to smart phones, while Mobile application will help
commuters in the same way as the website by providing the real-time updates and alerts on the bus
operations.
4.3.2 PIS System Concept
The PIS signs provide important traveler information to the passengers. Data from the AVL system in-
board the buses will be transferred to a backend server. The AVL data will be processed using backend
software algorithms and ETA / ETD data will be generated in real-time. The real time data
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
57
4.3.3 Functional Requirement
Typically, the character height of the PIS sign dictates the viewing distance for the commuter.
The character height of the PIS signs to provide a visibility of at least 30m from each PIS sign.
The PIS signs shall also include in-built features of automatic brightness adjustment based
on ambient lighting conditions to ensure that the display is clearly visible to the passengers at
any given point in time during the day or night.
Since these signs also provide accurate information about the next bus arrivals, it is important
that the time displayed on all these signs is synchronized over one common source for
synchronization.
PIS communicate over wired and/or wireless systems for communications. With respect to
time synchronization, the signs shall support Network Time Protocol (NTP) based
synchronization.
PIS signs shall be IP based and communicate over state-of-the-art communications system
with the control centre over wired and/or wireless communications. Therefore, these time
displayed as part of these signs will be synchronized using NTP via a central source located
at the control centre.
The PIS system shall also provide the ability for integration with the IVRS and SMS sub-
systems.
LCD industrial grade displays of 32” and 17” are proposed for the project. Based on prior
experience, it was felt that Off-the-Shelf products were found to be more reliable than LED
boards. The other reason is that testing for larger LED boards is not established properly in
India.
The Mobile App shall provide the following requirements, specification and design:
o Provide accurate departure times
o Provide Users current location for rendering of ETA at the closest bus stops
automatically
o Display of the most recent and accurate bus schedule
o Prediction of likelihood of catching the bus at a specific moment
o Display of bus schedule based on current location
o Reminding users when specific bus is leaving/is about to arrive
o Clean interface to display schedules
o Widget to display on home page
o Support efficient decision making through personalization of location choice
and reminder delay
4.4 Fare Collection System
4.4.1 Overview
The Fare Collection System (FCS) is designed to help CTU to meet its operational requirements and
to maximize the revenue realization by adopting robust system design approach to minimize the fare
leakage. Broad objectives of the FCS are:
a) Customer convenience
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
58
b) Revenue accountability and realization
c) To meet the operational requirements of CTU
d) Minimizing revenue leakage
e) Auditability
4.4.2 System Concept
The city bus services shall use on-board ticketing using paper tickets and smart cards. The commuters
will be able to buy the tickets after boarding the bus. In case of smart card, the fare will be deducted
from commuter smart card after the destination station is entered by bus conductor and the smart card
is tapped against ETM.
The process shall adhere to the “Guidelines for issuance and operation of Prepaid Payment
Instruments in India” issued by Reserve Bank of India (RBI). The central system software will include
processes to reconcile data on ticket sales (whether in the form of paper tickets or of ticket/pass data
carried on smart cards), with actual revenues received plus smart card stored value balances. This
software will also need to include processes to reconcile smart card and paper ticket inventory with
the quantities procured and issued.
4.4.3 Functional Requirements
Smart Card
Smart cards shall be designed to be used as an e-purse as well as to handle at least 15 different
policies with multiple configurable parameters which are detailed in the requirements. The policies
along with configurable parameters shall be discussed with CTU at design stage and finalized as per
their requirements. The smart card transactions shall check the following aspects:
Whether there is enough minimum pre-configurable balance available on the smart card.
Check if there is any prior trip within a threshold time
The smart card will have primarily two types of accounts:
E-purse; and
Smart Pass
E-purse:
The e-purse cards will have certain, user provided, value stored in the card account. Based on each
usage, the applicable fare will get deducted from the smart card account. Generally e-purse cards
have long validity/expiry date and the amount unused is refundable if the commuter wish to surrender
or close his/her smart card account.
The telescopic and other journey based fare discounts/benefits will be applicable on e-purse accounts.
For a smart-card user to make a trip the smart card shall at least have a minimum balance which can
be configurable in the system for each card type.
When a smart card user boards a bus, the conductor requests the commuter the destination and enters
the same in the ETM machine after which the smart card is tapped against the ETM to record the
origin and destination of the commuter. The ETM checks the immediate prior transaction of the
commuter stored locally on the smart card and deducts the fare accordingly from the smart card.
Therefore to enable the distance based telescopic fare integration possible the immediate prior trip
transaction has to be both locally and centrally stored in real-time. The trip hence takes the prior origin
into consideration if any which is present within a specified threshold time and deducts the fare from
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
59
the balance accordingly in case of an e-purse. If there is no prior trip information falling within the
threshold time the applicable fare is deducted.
Smart Pass
Any type of discount policies, monthly pass, weekly pass etc shall be configured under smart pass.
These types of accounts will be applicable for a specific route only and will be time/duration based and
the account does not have any monetary value. Once a commuter purchases a pass in the form of, it
has time duration applicable and the amount unused is not refundable and lapses at the end of the
duration for which the pass is applicable.
If a user with this category of pass travels on a route other than the assigned, the smart card will not
be accepted by the system and the commuter has to purchase paper ticket to complete the journey.
For a smart-card user to make a trip the smart card shall have a valid policy for that specific location/
route.
If the smart card is programmed as a pass then the requisite policy is to be validated. There shall be
random audits at the time the commuter exits at the destination to avoid any fare evasion by checking
if the smart card commuter has a valid ticket or not. Therefore a smart card user needs to handover
the smart card to the conductor only once just before making a trip making the transaction quick and
similar to that of a cash user.
Smart Card Issuance:
Smart Cards for general public and pass holders will be provided at Point of Sales across the Tri-city
area. The locations will be at 24 e-Sampark sites across the tri-city areas as listed below.
Exhibit 38 POS Locations (Source: CTU)
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
60
4.4.4 Electronic Ticketing Machines
Currently manual ticketing is practiced in CTU city services. Hand-held Electronic Ticketing Machines
(ETM) will be provided for all the city buses for the project. These ETMs will be equipped to read the
smart cards. Commuters who use smart cards can use them in the city services by tapping the card
on the ETMs, other commuters have to buy separate paper ticket for the journey. The proposed
ticketing process is shown in Exhibit 39.
Exhibit 39 Electronic Ticketing Process
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
61
4.4.5 Fare Structure
CTU currently uses a stage based fare system which is connected to distance travelled on
the route. CTU can explore other fare structures to promote bus system. The smart card
travel ensures that CTU can do telescopic fares, dynamic fares and many other options to
enhance the ridership. The commonly used fare structures for bus service include6:
Flat fare: fare remains constant irrespective of distance travelled on a particular
route.
Graduated fare: fare increases with stage or distance on a particular route (current
CTU method).
Zonal fare: fare increases with trip distance according to fare bands, It is usually
independent of number of bus routes used, i.e., free transfers, and also usually
independent of mode of travel selected if bus and rail are both available)
Each of these fare structures can further incorporate the concession fares that are currently
provided by CTU.
4.4.6 Payment & Recharge
Mobile Application and web based payment along with ticket counters will form the methods
by which passenger can recharge the payment media.
4.4.7 Audit / Enforcement
System audits are an important aspect of fare collection system. The FCS shall provide analysis and
reporting to allow reconciliation and audit of the various operations. Spot checks and audits are
proposed to be performed by the Inspectors on buses, POS terminals and other applicable areas to
ensure revenue maximization. The system shall allow audit, imposing penalties at various levels and
reconciliation of the same. The penalties hall be configurable in the system and shall be defined in
configuration parameters on various discrepancies/anomalies types.
The system shall allow for deposit adjustments in the event that there is a discrepancy between the
counted values and the actual bank deposits. The user enters the actual bank value deposited. The
dialog will calculate whether there was an over payment or a short payment when the bank count is
entered. Additional adjustments may be required for auditing purposes that may be assigned directly
to a conductor, POS operator or cashier.
To enforce the paper tickets, the machine readable (barcode or similar) portion should be coupled with
human-readable printed text so that if an auditor or a conductor wants to read the paper ticket, the
printed data on the ticket shall have all the required information in a readable text form.
The auditors will be using ETM to audit the paper and smart card journey details of the commuters.
The provisions shall be made in the system software and ETM machines to support the same.
4.5 Transit Management System
The current bus operations are headed by General Manager (GM) in central office. There are 4 depots
among which, city bus services are handled by Depot-2 and Depot-4. Depot is managed by Depot
Manager (DM). Each depot has various departments like Traffic, Mechanic and Accounts. All depots
have workshops and all repairs are taken care internally in the depot.
6 Urban Bus Toolkit, World Bank, http://www.ppiaf.org/sites/ppiaf.org/files/documents/toolkits/UrbanBusToolkit/assets/1/1e/1e6.html
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
62
4.5.1 Overview
CTU has introduced computerized depot management system modules for Vehicle and Crew
Scheduling, Waybill Management, Attendance Leave Information and Store Inventory Management
with the help of National Informatics Centre (NIC). There is no centralized system to update all the
information in one place and in a single shot. A description of the various existing systems of CTU is
given below.
Vehicle and Crew Scheduling: The current CTU bus operations are managed by the Traffic
Department that is responsible for bus scheduling and crew rostering. The Traffic department
evaluates on a regular basis the demand, requests from residents of the tri-cities and such, and
determines the bus routes and schedules. Crew is then assigned based on a duty-rota developed by
the depot staff. No optimization software is currently used for this analysis.
Waybill Management System: All the routes information, crew information and bus information are
fed into the system. Then the information noted in the way bill by the conductor during the route
operations is entered into the system by attaching the same information with preexisting information
at the end of the shift. The reports module has options to filter and generate reports based on dates
and depots. The following Exhibit 40 shows the various reports that can be generated with the way bill
management system.
Exhibit 40: Available Reports from Waybill Management System of CTU
Attendance Leave Information System: The attendance is being captured through the leave
information of the staff of CTU. The attendance is entered manually into the applications for all the
staff of CTU.
Store Inventory Management System: Store Inventory Management is deployed by NIC as shown
in Exhibit 41. It has been utilized for managing stores at each depot with job cards tracking.
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
63
Exhibit 41: Screenshot of the Inventory Management System Developed by NIC for CTU
4.5.2 Goals and Objectives
The following overarching goals and objectives were identified for integrated TMS:
Improve Vehicle Maintenance
By providing systematic planning for vehicle maintenance will cut down the vehicle idle time
for non-operational buses, vehicle routine maintenance, breakdown ratio shall come down,
automated alert for maintenance, vehicle on time departure from depot, easy to check vehicle
in/out status according to schedule time, vehicle transfer between depots/divisions.
Improve Fuel Management (not part of the ECBS project)
By providing Fuel management systems, fuel consumption and stock can be controlled and
monitored. Fuel leakages also can be monitored.
Improve Scheduling and Planning
Having DMS, vehicle allotment for the scheduling will be easy, crew and vehicle assignment
shall be once in the system, if any changes required system shall allow them to update the
changes, schedule cancellation or new schedule allocation. This reduces frequent manual
intervention and error free operation.
Improve Data Management and Reporting
Data warehousing will help CTU to run the hassle free operation, for example looking at the
data will provide idea of cut down the schedule/trip, dead kilometers, vehicle wise KMPL or
manufacture wise KMPL or driver wise KMPL, utilization of tyre and life cycle of tyre retreading,
battery life, repeated issues by fleet wise of manufacture wise, vehicle utilization, accident and
breakdown data, master data of crew, vehicle and other staffs, over time hours, warranty
details necessary items, fuel consumption, etc.,
Facilitate Effective Management
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
64
The entire movement of the vehicle shall be recorded on the system to manage effectively.
Depends on priority system shall send alerts to concerned department or staff. Each vehicle
history provides usage and lifetime of the fleet to decide for scrap. Fitness certificate, road
permit, insurance shall be maintained in system to track and manage smoothly, to track history
of tyre lifetime to do tyre treading to minimize operational cost.
Improve Information Accuracy
Stores module shall have history of stock, material forecasting, accurate information of spare
parts, warranty details, spare tracking provides accurate information.
Ensure Reliable Information
Attendance shall be recorded through proximity reader to avoid manual intervention. Leave
and holiday will be managed systematically to monitor staff attendance. The system shall help
CTU to monitor staff’s in and out time. In case fleet not departure on time than system helps
management to track the delays.
Facilitate Easier Processing
System helps CTU to track and pay staff’s salary, incentive, ESI, PF and IT in short time.
Develop Centralized System
HR and Depot management shall use same database to maintain employee records. This is
to avoid manual duplication at various places. In case of staff transfer from depot to depot and
division to division it will be updated one place.
4.5.3 Proposed Integrated Transit Management System
Based on the various discussions with CTU staff, the following points were expressed as the needs of
the TMS.
Replace the existing computerized systems being utilized by CTU
o Waybill Management System: since the current waybill system is developed for manual
ticketing and cannot be upgraded easily for the business process requirements of a smart-
card based ETM ticketing system.
o Existing Scheduling & Planning System: since it does not have the features for city bus
services. In addition, it also has limited reporting capabilities for the requirements for city
bus services.
o Existing Leave Management System does not have reporting capabilities and is not being
used even at present.
o Stores & Inventory Management System: is expected to have issues with respect to NIC
support to enhance the functionality - as per CTU staff.
Various TMS sub system to be integrated with each other to meet current and future business
requirements, such as, ensuring maintenance schedules are available at workshop and depot
locations through single input.
Centralized TMS to synchronize with TMS system at various places (depots, terminals, etc.).
Centralized TMS to be integrated with AVL and FCS systems for effective operations.
Only required integration to ensure no overlapping of data between the various subsystems
of TMS and also other subsystems of the System Integrator tasks.
The following Exhibit 42shows various sub systems of TMS proposed for this project.
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
65
Exhibit 42: Sub Systems of Transit Management System
The windows based TMS software shall be deployed at each depot for smooth operation and
maintenance. The centralized TMS software shall be deployed at Data Centre which communicates
to various components of the TMS software at each depot/terminal and syncs the data at frequent
interval to update the records. The TMS software at each depot shall work as standalone with local
database in case of communication failure between centralized TMS system. Exhibit 43 illustrates the
centralized and integrated TMS.
Exhibit 43: Concept of Centralized TMS
4.5.4 System Concept
The proposed integrated TMS shall have following major sub systems and its features to meet CTU
business requirements. Interface between various TMS sub systems are given below in Exhibit 44.
TMS
Depot
Workshop
Stores & Inventory (Replace Existing)
HR & Payroll
Scheduling and
Rostering
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
66
Exhibit 44: Interface between Various TMS Sub Systems
4.5.4.1 Depot Management System (DMS)
The DMS software shall be deployed at minimum of 3 locations at each depot in Traffic, Accounts and
maintenance areas.The DMS shall include the following functionalities as shown in Exhibit 45 and
Exhibit 46.
Exhibit 45: Functionalities of Depot Management System
Crew Rostering
Vehicle Scheduling
Vehicle Dispatch
Vehicle Management
Vehicle Routine
MaintenanceAccounting
Security System
Scheduling &
Planning
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
67
Exhibit 46: Functionalities of Depot Management System
Master Data Management
•Information about Crew, Staff, Vehicle, schedules, routes, stop name and stop code, Landmarks, etc.
•Master data shall be in forms with read and write access to the end user based on role and responsibility.
Accounting System
•All non ticketing and ticketing accounts carried out from the depot.
Crew Rostering
•Crew rostering shall be done systematically based on logic defined by CTU.
•There shall be a display to show vehicle in and out status at the depot gate.
•Optimization of crews shall be provided through a proven crew rostering software.
Scheduling
•System shall have the ability to create, edit and update the schedules/trips and allocate crew to the schedule.
•Optimization of bus schedules shall be provided through a proven scheduling and planning software.
Fuel Inventory Management
•Detailed information of fuel consumption of vehicle wise and by stock, history of fuel intake, monthly fuel stock and each pump wise consumption, etc.
•Alerts shall besent to concerned staff through SMS or Email in advance on the fuel stock at predefined time.
Vehicle Routine Maintenance
•Schedule maintenance, periodic maintenance, routine maintenance shall be automated in the system with detail of start and end date, status of maintenance, etc.
•Shall shall allow depot manager or authorized person to set the configuration to enable or disable the alert for concered registered staff.
•Warranty tracking
Vehicle Management
•The VHMD device on the vehicle shall have diagonostic logs of vehicle engine, oil, break, fuel, etc. which shall be transfered to DMS software once the bus arrives at the depot.
•The VHMD logs shall be shown in the format of MIS reports on the system with details. If case VHMD sent the issues in code format then system shall ability to display in the readbale format for CTU for effictive operations.
Security System
•Gate In/Out detail as per current CTU procedures shall be captured.
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
68
Exhibit 47 shows minimum infrastructure of Depot Management System at various departments and
display near to the gate to identify the vehicle in and out status. The depot vehicle dispatching
information shall be captured from AVL central software of CTU fleets. Proximity device (biometric
reader) shall be installed at depot gate to record staff, crew and any other person with permission to
enter depot premises shall be recorded for their HR and payroll process.
Exhibit 47: Depot Management System
4.5.4.2 Workshop Management System (WMS)
Currently, Workshop is part of the Depot in CTU. The WMS software shall be deployed at two or more
places inside each workshop area. The current/proposed workflow of the workshops shall be captured
in the system. This software will be part of a centralized system to manage unique information across
the division/region. Each and every fleet movement shall be captured in the system to track and reduce
fleet’s non-operational hours. WMS shall send alerts through SMS and Email to authorized staff.
4.5.4.2.1 MIS Reports
Customized MIS report shall meet CTU business processes by integrating VHMD device with DMS
shall help CTU to track vehicle health and provide preventive maintenance when required. Sample
MIS report formats are shown in Appendix 2.
4.5.4.3 Stores and Inventory
Stores and Inventory management shall provide inventory position visibility, streamline in-store
activity, improve CTU management performance and productivity, reduce labor cost, transport cost,
barcode reader to identify product details and enter into system. The Stores and Inventory shall have
following features and functionalities at a minimum:
It shall have history of purchaser name, contact detail, etc. to manage vendor and purchase
order.
Maintenance
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
69
System shall have track of invoice detail of each and every items that are supplied by the
vendor. In addition to invoice how the payment made by CTU shall be recorded in the system.
If contingency stock goes below a defined limit, the system shall send details through email to
concerned staff.
Inventory data from stores, to drive optimal purchasing and stock levels across various depots.
Centralized inventory shall be provided that can update and manage the stores effectively
from any location.
Inventories with unlimited product attributes, tracking of quantity on hand and in transit by
attribute; multiple units of measure and flexible costing shall be present in the application to
support effective inventory management.
Provide visibility and control with serial and lot based traceability, as well as integrated audit
controls.
Prevent stock-outs and overstock using in-store location level tracking.
Inventory management application shall provide various performance measures, such as
stock out, inventory value, etc., to support the Purchaser to improve and optimize the inventory
management.
The application shall be accessible through secure role-based portal access, and easy web
services integration.
Enable the performance of back-office business functions anywhere in the depot/division.
In addition to Stores and Inventory system, the application shall have provision to enter all the
assets of CTU.
Asset management shall have master data of all the physical location, various types of assets
and its make, model, serial number, part number, warranty, department, vendor name, etc
and unique identification ID of the asset.
Ability to store images of each asset, mobile or immobile, etc. shall be provided
Provision for transferring assets between depots and divisions shall be available.
Bidder to stick tags on each of the assets.
In case of any hardware or items are lost then concerned staff shall be able log a complaint
with concerned department to take necessary action. The process shall be trackable through
the system
Asset management shall have enough information to claim insurance from third party vendor.
4.5.4.4 HR and Payroll System
Human Resource and Payroll Software shall provide comprehensive accounting solution to meet the
demands of current CTU business processes and future needs based on the system requirements.
The system shall enable the user the choice of sort order, selection of branch, department, position,
etc. and other parameters to generate payroll output as per requirement, either on screen or as hard
copies.
Following are major features of HR & Payroll:
Employee details
Staffs score card system
Time management using proximity reader
Centralized system
Quick payroll process
Email alerts as per requirements
Leave Management System
Electronic salary slip generated automatically or on-demand by authorized staff.
Integration with other systems of TMS, AVL and AFCS for crew details and leave information.
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
70
Workflow structure of the payroll system is shown in Exhibit 48:
Exhibit 48: Workflow of Payroll System
4.5.4.5 Crew Rostering
Rostering module will facilitate assigning of crew members to the buses and their schedules. The
rostering will be designed to follow the crew allocation methods used by CTU or the recommendation
of the software, as determined by CTU after using the Scheduling & Rostering software:
Duty preferences are taken from the crew.
While assigning the duty to the Drivers/Conductors, these preferences are taken into
consideration and are assigned as per their seniority in the organization
Once a duty has been assigned to a crew member, then he continues with the same duty for
the whole rostering period.
4.5.4.6 Scheduling
TMS will provide the scheduling module to manage schedules decided by depot. These schedules are
assigned to the bus by depot technician or approved person at depot level. If the vehicles haven’t left
from the depot as per scheduled time then crew and concern people will be getting SMS alert.
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
71
Schedule Software can optimize driver and bus allocation. Fixed route scheduling software provisions
for the passenger demand with optimal number of buses through designing and modifying the bus
routes. The application allows for modelling the planning process in public transportation which
consists of different recurrent and complex tasks which start at a strategic level. At the operational
level, the application provides for collecting or forecasting the number of passengers for each origin,
destination and transfer point. For the crew, the software allows for optimizing at a planning level and
then for daily operations.
The operations process that the scheduling software is trying to optimize is:
Exhibit 49 Operations Planning Process
The scheduling software should have the following features:
Support strategic planning activities for bus and crew scheduling
Support operational optimization of bus and crew scheduling independently or together
Operational optimization of crew with consideration with labour laws and other applicable rules
Comparison of alternatives for selection of particular set of operations by the client
Integrate with the AVL system to provide real time distribution scheduling on
unexpected/variable demand.
Performance reporting on service levels, cost reduction, etc.
4.5.4.7 Leave Management System
Leave management system enables the HR manager to track and maintain leaves of the employees
of the firm / organization. The leave management module defines various leave types based on their
eligibility, which they are assigned to various employee levels. Various types of leaves are:
Earned Leave (EL) / Privileged Leave (PL)
Casual Leave (CL)
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
72
Sick Leave (SL)
Compensatory off (Comp offs)
Maternity Leave (ML)
Paternity Leave (PL)
Leave management system enables user to create and configure leave types as per grades,
designation or any other hierarchy in the organization which are driven by the rules and HR policies.
Leave policies can be configured based on the requirements.
Applicability of Leave type to a pre-defined grade7
No of leaves eligible / yearly quota per leave type
Monthly Leave accrual setting
Leave rule during probation period
Leave to be applied by no of days in advance
Leave regularization policy within a defined time period
Define a window of no. of day for long & short Leave application
Sandwich leave rule configuration, that is leaves taken between Public holiday or weekly offs
Validate if two leaves types can be clubbed
Leave encashment & carry forward policy
Leave type lapse rule for Paid leaves, Sick leave, Comp offs
Leave management system allows the user to configure and exports the reports as part of the MIS
and alerts. It allows to maintain the leave record of all the staff and officers and reports can be
generated for different departments and to schedule the allocation of resources based on the leave
calendar.
4.5.5 Other Systems Integration with TMS
The proposed Transit Management System is expected to integrate with other systems like AVL and
PIS that are proposed. The following Exhibit 50 shows various ITMS System interface.
7 http://www.opportune.in/
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
73
Exhibit 50: Data Exchange Needs
4.5.5.1 TMS with AVL & PIS
AVL is a separate system to track and monitor alerts, route deviation, emergency response and two
way voice communication, schedule adherence, etc. of the fleet from Common Mobility Centre by
dispatchers. Generally vehicle change, crew change, schedule/trip cancellation shall be confirmed at
depot before the vehicle departure.
Need for Integration: On DMS & WMS data of Vehicle Master, Crew Master, Accident, Breakdown,
Rostering and Scheduling are expected to integrate with AVL system. By integrating AVL with DMS,
CTU will save operation time and reduce staff time and effort in updating two separate systems. TMS
and AVL shall either have a single database or separate databases that shall synchronize to provide
correct data seamlessly. In case of any changes, schedule will update on the DMS at depot,
centralized DMS at Data centre will be synced and update to AVL Database.
Vehicles that are available at workshop for maintenance shall be automatically removed from AVL
system from the operations. This shall help operations team to manage the schedules effectively.
4.5.5.2 AVL with Payroll and HR
The HR & Payroll is a separate software to manage all the staff personal details, working days, holiday,
leave, over time and theirs wages. HR & Payroll module defined briefly in other section in this
document.
Need for Integration: Crew Master from HR module shall integrate with TMS and AVL system to
update crew attendance and crew transfers to run smooth operations. The integrating of HR module
with the Depot Management System will help DM to schedule the crew assignment effectively during
their absence. During crew absence the detail shall be entered in the HR module in advance. The data
will be updated on TMS software too. This will enable DM or Traffic Dept. to appoint other crew
effectively.
In case of crew transfer, system shall enable the alert and provide alternate crew name (who is
available) to run schedules without delay.
Data Exchange
TMS
AVL
PIS
FCS
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
74
4.5.5.3 TMS with FCS
Fare Collection System consists of POS and ETM machines.
Need for Integration: Since FCS provides the revenue component, limited and secure data exchange
shall occur. The conductor and schedule information for ETMs, bus stop locations for ticket counter
POS, etc. are overlapping between the master lists of TMS and FCS. However, the data exchange
should be limited to be applied by only authorized personnel and in a controlled and secure manner.
4.5.6 Other System Infrastructure at Depots and Terminals
4.5.6.1 Data Transfer of In-Bus Camera Data
There will be cameras inside the bus, will be recording continuously (as per UBS II). The recording will
be saved in the Security Camera Network (SCN) device which is fixed inside the bus.
Video/Image Storage: Once the bus arrives at the depot, the stored data from SCN shall be
transferred to storage server at depot or terminal through WLAN. The contingency approach is to have
data copied to Portable drive from SCN and dumped to storage server at depot manually. After
video/image data dumped to the server at particular path, the video software shall able to show the
video/image at user convenient. Video/ Image are displayed on the software shall display the time of
recording, vehicle ID or vehicle reg. no, driver ID, at minimum.
4.6 Transit Management Centre
Transit Management Centre (TMC) is a vital part of CTU operations to bring together all the
administrative functions at one place. Central Control Centre is not an independent component but
TMC is a centralized location or hub of traffic/ administration of all the ITS components for processing
data inputs and delivering outputs to the different ITS components on city services network, command
and control, computing using the appropriate software’s and skilled key personnel and communication
to and from many types of ITS applications. The sub components of TMC depend on other various
ITS sub-systems and the way of operations of bus services and scale of the system.
4.6.1 System Concept
The system concept for Transit Management Center consists of:
All the responsible stake holders will be jointly monitoring the CTU operations and any decision
can be taken collectively and quickly.
Single data base for various data sources.
Monitoring of various operations at one place which improves productivity.
Improved response level.
Effective and efficient monitoring and control.
Reduced response time in emergency situations.
Disseminating real time information to users, commuters and project and other authorities.
More effective use of ITS applications.
Monitoring and control of various sub-systems and devices installed on the CTU buses.
Compilation, recording, analysis, processing, storage of information and data.
Exhibit 51 shows the concept of the control center for CTU.
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
75
Exhibit 51: Central Control Centre Concept of Single Data Update Module.
4.6.2 Functional Requirements
The functional requirements of the TMC consist of:
Provide information and data management system for the overall control, supervision,
configuration and maintenance of CTU operations.
Real time monitoring of buses on GIS map taking its geo positions received from the GPS
mounted on buses and simultaneous constant computation of expected arrival times at
downstream stations using the efficient travel time algorithms.
Operational management and alert monitoring of the buses in real-time to ensure improved
efficiency for the agency and better service to the commuters
Passive monitoring of safety and security for infrastructure
Real-time decision making for any emergency management services.
Providing commuter support through IVRS.
Monitoring the ITS system and fault diagnosis and alarm monitoring of all sub-systems.
Data of various ITS components (data archiving) stored in control centre for any future
planning or R&D purposes.
Transmitting of all the outputs to the corresponding ITS units at stations or on-board of the
buses and signalized intersections in real-time through wireless communication system.
Provision of emergency numbers in the AVL application and simple quick access for the
dispatcher to connect with the emergency numbers.
Single Data Update
AVL
PIS FCS
DMS
MIS
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
76
Allocation of space for Traffic Police in the TMC and corresponding system support.
As it supports a lot of data processing and transmitting, TMC requires large amount of communication
system to support its operations through wired or wireless. For the effective functioning of TMC and
hence the efficiency of ITS, the following components are very critical to be considered,
Automated Data Acquisition
Fast Data communication to and from TMC
Accurate analysis of data at the management center
Reliable information to the passengers/operators/other stakeholders
The accurate data analysis includes the data cleaning, fusion and analysis. Once data from the
sensors or GPS units received to TMC, it should be checked. Reliable passenger information should
be passed on to the public on time through efficient system having the capabilities to transmit the
information through SMS, Internet and to bus stops and vehicles timely.
4.6.3 Data Archiving
Central Control Centre collects traffic and incident related information about the transportation
network. This data is combined with other operational and control data in order to manage the
transportation network and to produce traveler information. Along with this, data of FCS, bus
operations, crew details, and others will also be fed into servers in the TMC. Archiving this data is an
effective way of making it available for operators who want to make improvements to their particular
transportation system.
TMC collects data which includes:
Traffic incidents
Traffic violations
Vehicle speeds
Schedules
Vehicle details
Fare collection details
Archiving these data provides a cost-effective way to obtain data that can be used by transportation
planners, designers, and researchers alike for many purposes. Data can be used for facility planning
and design, developing control strategies, congestion tracking, emissions modeling, deployment of
response personnel, and schedule of maintenance and construction.
4.6.4 TMC & Video Wall
The Transit Management Center (TMC) is the heart of management and control system. It is in this
control room that critical decisions are made. The control center must create an environment in which
information is gathered, processed and disseminated clearly in time.
The vehicle position data from all the buses will be monitored in the control center. The feeds of all the
cameras installed on the buses, will be monitored at the control center thereby ensuring effective
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
77
monitoring. Based on the AVL application monitoring, number of camera feeds in the control room and
number of operators, the video wall will be designed to ensure optimum and effective monitoring.
Control center shall have space one data center to accommodate 2-3 server racks, 8 to10 work
stations for monitoring around 500 buses which includes vehicle location monitoring, dispatch, cash-
up and ETM monitoring and PIS data dissemination.
The design of the control center will be done to ensure optimum utilization and ease of operations for
the operators working in the control center.
The alarm inputs from various sub-systems and any equipment failure in the field will be monitored in
the control center which will be displayed and indicated on the relevant computer/system and based
on the information the operators will be able to take necessary preventive or corrective action. The
emergency protocols and procedures will be made available to the control center operators for them
to follow in case of any emergency situation. As the TMC and video-wall are expected to operate for
18 to 20 hours every day, high quality video display solution is recommended. One video wall of 70”
size shall be installed in the TMC.
4.6.5 Man power
This section of the report provides indicative man-power requirements for the Operations Agency,
which can be further deliberated and fine-tuned based on the operational needs/set-up of CTU.
4.6.5.1 Assumption
The following Exhibit 52 below shows the assumptions considered for the man power estimation for
the operations agency.
SI. No Item Numbers
1 Number of City Buses 583
2 Number of Depots 5
3 e-Sampark POS 24
4 Number of shifts in a day 2
Exhibit 52: Data for Man Power Estimation
4.6.5.2 Dispatcher and Control Room Personnel
The following operations activities are expected to be carried out at Control Centre by dispatchers.
Monitoring Vehicle movement for the tri-city operations.
Schedule creation and assignment to fleet.
Reschedule transaction and trip cancellation if required.
Monitoring and responding on alerts and events on the AVL software. Route deviation, bus
bunching, over speeding, breakdown, call back request from fleet, etc.
Equipment status monitoring on the system dashboard. Like offline, online, fault,
communication problem, etc.
Playback trips for operation improvements. Like bus bunching, delay, non-schedule
adherence, etc.
Develop, review and appraise MIS reports on operational performance and other buses.
Review reliability, timeliness and accuracy of PIS information.
Review ETA/ETD data for accuracy on a periodic basis.
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
78
Ideal education qualifications and experience of personnel for TMC operations are given in Exhibit 53.
SI. No Designation Work Locations Number Minimum Educational
Qualifications Minimum Work
Experience Previous Designation
1. Operations Manager
TMC
1 Master’s Degree in Transportation Engineering or Operations Research or Equivalent. Relevant experience
in operations management. Candidates with experience with
bus operations will get preference
10 Years Operations Manager, Maintenance Manager, Transportation Engineer
2. Dispatcher TMC & Depots
16 (5 in each shift at TMS, one at each
depot for each shift)
Experience as drivers, conductors, traffic controller or ticket collectors
within CTU or in the region are preferred. Reasonable computer
skills to run the AVL/FCS application is required.
Minimum Exp: 5 years
Driver, Conductor, Ticket Collectors, Control room Operator
3. Systems
Administrator TMC / Depots/ POS
3 Bachelor’s Degree in Electronics 3 Years
Systems Administrator, Systems Engineer
Exhibit 53: Education & Experience Qualifications for ITS Staff
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
79
4.6.6 Roles and Responsibilities The roles and responsibilities for the various agencies involved in the project, along with the
responsibility matrix is provided in this section.
4.6.6.1 CTU
CTU will be administering the operations and will be responsible for the scheduling of the buses and
crew rostering.
4.6.6.2 System Integrator
The SI is expected to closely work with bus manufacture/ OBITS equipment manufacture, CTU, and
Consultants appointed by CTU. The SI shall provide all the integration support and develop necessary
API, Program and necessary development to integrate with OBITS equipment. The SI scope of
services shall include the following:
Planning & Design
o Development of Implementation Schedule in MS Project detailing each task of the project
along with intelligent estimate of timelines and dependencies.
o Development of Software requirements and Hardware requirements document.
o Development of System Requirements Specification
o Development of PIS design document specifying the format, font and such to develop the
layout of the PIS board that the commuter finds simple and easy to understand.
o Power calculations and sizing of UPS and DG
o Test plan development
o Field equipment installation diagrams including electrical diagrams as required.
o Installation check sheets
Hardware
o Provide PIS boards for bus stations, interchanges, depots, etc.
o Potentially provide OBU, BDC and ETM for city bus services.
o Servers, Switches, Racks and other network components for the-AVL system.
o Workstations with large dual monitors for dispatchers.
o Workstations with large monitor for depots, etc.
o SMS and IVRS hardware
Software
o Development/Tailoring of API for bus manufacturer’s OBITS system integration with SI’s
system
o Oracle database for the data.
o Fully functional and highly customizable AVL application consisting of master database,
maps, MIS reports, etc.
o PIS software for showing information in Hindi and English.
o Commuter Portal.
o MS Office (Word, Excel and PowerPoint) for workstations.
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
80
o Other supporting software for the AVL system.
Integration
o Integration of other subsystems as required for seamless implementation of the project
o Integration with field equipment from Control Center.
Training for relevant personnel
AVL & PIS implementation
Maintenance support for system and field equipment
Exhibit 54 shows the responsibility matrix of various activities carried during the project execution and
maintenance.
Sl. No.
Category System Component Setup Ownership Support and Maintenance
1
Software
FCS Bidder Purchaser Bidder
2 AVL Bidder Purchaser Bidder
3 PIS Bidder Purchaser Bidder
4 TMS Bidder Purchaser Bidder
5 Accurate Data to be Provided Purchaser Purchaser Purchaser
6 Data entry work for all master data into application Bidder Purchaser Bidder
7
Hardware
FCS Bidder Purchaser Bidder
8 AVL Bidder Purchaser Bidder
9 PIS Bidder Purchaser Bidder
10 TMS Bidder Purchaser Bidder
11 Communication System Bidder Purchaser Bidder
12 UPS power backup including batteries Bidder Purchaser Bidder
13 Removal and fixing of hardware/equipment Purchaser Bidder
14 DR Site DR Site Service Bidder Bidder Bidder
15
Infrastructure
Central Control Center Purchaser Purchaser Purchaser
16 Civil, Electrical Works and Furniture Purchaser Purchaser Purchaser
17 Depot/Interchange/Workshop Infrastructure Purchaser Purchaser Purchaser
18 TMC - , Raw Power supply DG Set Purchaser Purchaser Purchaser
20 Data Center equipment's Bidder Purchaser Bidder
21 Geo-Fencing Survey Bidder Purchaser Bidder
22 Logistics for Removal and fixing of hardware/equipment
Purchaser Purchaser Purchaser
23 Data Center Purchaser Purchaser Bidder
24
Consumables
Printer Paper (A4) Paper rolls for ETM machine Paper roll for POS ticket printer Diesel for Generators DVD/CD for any video/image backup Monthly Telephone bill SMS cost IVR System call cost
Purchaser Purchaser
25 All Printer cartridges supplied by supplier Tape Data Cartridges Printer Head
Bidder Bidder
26
Training
Space for Training Purchaser Purchaser Purchaser
27 Training materials, system, hardware Bidder Bidder Bidder
Exhibit 54: Responsibility Matrix
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
81
5 Procurement Plan and Project Financials
Project procurement plan consists of the process of identification of need of the project in terms of
good required, transportation, maintenance. Whereas, implementation plan consists of the design and
specifications and project scheduling (time frame for implementation). In this chapter, the process of
procurement and implementation of the ITS project for CTU is detailed.
5.1 Procurement Plan
In the procurement plan, the selection of ITS implementation agency also referred to as System
Integrator (SI) will be done. SI will provide all components planned in the ITS, integrate, test, roll-out
and manage the system for a specified period of time.
CTU shall float a tender for global participation on a single stage bid process which consists of
technical and financial bids together which follows the National Competitive Bidding (NCB) process.
The cost of the bid document and last date of purchase will be announced along with the date and
time of bid opening.
5.2 BOQ and Costs Estimation
The BOQ for the CTU ITS project is as follows:
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
82
Item Code Component Location Subsystems / Items Quantity exclusive of spares/ consumables
1.1 Fare Collection System (FCS)
FCS Software
FCS
TMC
FCS Central System Software inclusive of but not limited to:
FCS Database application (Primary Server + DR Server)
1
FCS FCS application software (Primary Server + DR Server)
FCS Anti-virus software (Primary Server + DR Server)
FCS Automatic Back-up\ archiving software
FCS Any other COTS software (Primary Server + DR Server)
FCS Hardware
FCS FCS Central System Hardware inclusive of but not limited to:
FCS Primary Server 1
FCS DR Server 1
FCS Automatic Back-up devices with media 1
FCS KVM Switch with LCD Monitor 1
FCS Server Rack (includes rack requirements for all systems) 1
FCS Network All-in-one-printer 4
SC Hardware
FCS Smart Card Issuance Work-Station POS (16 E-Sampark – Only in Chandigarh) inclusive of but not limited to all software and hardware related to:
FCS
POS
Camera 24
FCS Document scanner 24
FCS Smart card revaluing device 24
FCS Workstation 24
FCS Handheld ticketing machine inclusive of but not limited to:
FCS
Field Equipment / Depots
Handheld ticketing machine inclusive of all related accessories, software to meet the requirements
1283
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
83
FCS
3G/GPRS enabled SIM Cards 1283
FCS
TMC
Smart Card Personalization
FCS Smart Card Personalization Printer 3
FCS Camera 3
FCS Document scanner 3
FCS Workstation 3
FCS Handheld ticketing machine inclusive of all related accessories, software to meet
the requirements (for CTU Auditors) 15
FCS Central Control Centre Operator Work-station for FCS
FCS FCS Cash-up workstations 2
FCS Fare media - Smart Cards 1,00,000
1.2 Automatic Vehicle Location System (AVL)
CS Software AVL AVL System Software inclusive of but not limited to
AVL RDBMS Database
1 AVL AVL Central Application software
AVL Automatic Back-up/ Archiving software
CS Hardware AVL AVL Hardware inclusive of but not limited to
AVL AVL Server 2
AVL Database Server 2
AVL Tape Drive 1
AVL Tape Data Cartridges 30
AVL Communication Server 2
AVL Web Server 2
AVL Domain Server 1
AVL 3G/GPRS enabled SIM Cards 513
AVL AVL Workstation
AVL AVL Dispatcher Workstation with Dual Monitor and necessary accessories 8
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
84
AVL EPABX 1
AVL Landline Phones 8
AVL Hands free/ Headphone 8
AVL Printers
AVL All in One Printer (Color Print, Copy, FAX) 1
AVL LaserJet Printer 2
AVL KVM Switch with LCD Monitor 2
OB Hardware AVL
OBITS Hardware as per UBS II
AVL Single Control Unit and Bus Driver Console 134
AVL Side Destination Boards 204
AVL Front Destination Boards 34
AVL Inner Destination boards 34
DR Site AVL Disaster Recovery Service
AVL Disaster Recovery Service for Complete AVL system (includes FCS) 1
1.3 Passenger Information System (PIS)
PIS
PIS Customized or COTS Software for PIS 1
PIS Commuter Website 1
PIS Commuter IVR System 1
PIS Commuter SMS System 1
PIS Commuter Mobile Application 1
PIS 17" LED Passenger Information Display at Bus Stops across City 22
PIS 32" size of Passenger Information Display at ISBT's, etc. 8
1.5 Transit Management System (TMS)
TMS
TMS TMS Central Application software including Scheduling & Rostering 1
TMS TMS Application software for workstation 50
TMS TMS Server (Primary & Secondary) 2
TMS Workstation for TMS with 17" LCD monitor and other accessories 40
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
85
TMS Workstation for monitoring Video/Image with 17" LCD monitor and other accessories
2
TMS Printer and Scanner for TMS workstation at Depot 4
TMS 55" size of Passenger Information Display at Depot 6
TMS Cameras 4
TMS Proximity Reader 4
TMS Proximity cards for staffs 2500
TMS In-bus cameras 134
TMS In-bus NVRs for camera recording 134
1.6 Transit Management Centre (TMC)
TMC
TMC Video Wall 1 x 70" 1
TMC Data Archiving Software 1
TMC Tape Drive Cartridges 30
1.7 Communication System (COMM)
COMM
COMM Data Center - Network Components and LAN 1
COMM TMC Data center (Data & Internet) 1
COMM TMC Data center - Redundancy 1
COMM Primary to DR Site 1
COMM Depot (Broadband for 10 workstation) 5
COMM PIS Display (Dongle/Broadband) 30
COMM IVRS (Switching device) 1
COMM SMS (Modem) 1
Exhibit 55: Bill of Quantities (BoQ) for CTU ITS Project
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
86
5.3 Financial Analysis of the Project
The summary costs are provided here. The detailed costs are provided in Appendix 3.
Component Capital Cost O&M Cost for
next 6 years SI Cost (10% of Capital) Total Project Cost
Total Installed Cost Spare Cost Total Capital
FCS ₹ 419,21,075 ₹ 0 ₹ 419,21,075 ₹ 41,92,108 ₹ 41,92,108 ₹ 503,05,290
AVL ₹ 515,93,025 ₹ 0 ₹ 515,93,025 ₹ 51,59,303 ₹ 51,59,303 ₹ 619,11,630
PIS ₹ 50,10,000 ₹ 0 ₹ 50,10,000 ₹ 5,01,000 ₹ 5,01,000 ₹ 60,12,000
TMS ₹ 307,32,500 ₹ 0 ₹ 307,32,500 ₹ 30,73,250 ₹ 30,73,250 ₹ 368,79,000
TMC ₹ 55,60,000 ₹ 0 ₹ 55,60,000 ₹ 5,56,000 ₹ 5,56,000 ₹ 66,72,000
COMM ₹ 8,75,000 ₹ 0 ₹ 8,75,000 ₹ 85,20,000 ₹ 87,500 ₹ 94,82,500
Total ₹ 1356,91,600 ₹ 0 ₹ 1356,91,600 ₹ 220,01,660 ₹ 135,69,160 ₹ 1712,62,420
*FCS – Fare Collection System, AVL – Automated Vehicle Location, PIS – Passenger Information System, TMS – Transit Management System (Depot Management, etc.), TMC – Transit Management Center
Exhibit 56: Summary Costs for CTU ITS Project
5.3.1 Project Phasing
Based on discussions with CTU, the following phasing was considered for the implementation:
Exhibit 57 Phasing for the CTU ITS Project
CTU preference is to implement the three phases is through a single System Integrator (SI). The SI is expected to complete the implementation in a phased manner with Phase 1 being for 6 months, Phase 2 from 6 to 12 months and Phase 3 from 12 to 18 months. The SI is expected integrate all the components to provide seamless implementation with minimal data entry and external dependencies for CTU. The phasing is determined based on immediate needs of CTU as identified by its core team. In Phase 1, the automated ticketing through ETMs, the AVL system to provide the realtime information on the buses, and the
ITS
•FCS
•AVL
•PIS
TMC
• Data Center for AVL, FCS & PIS
• Basic Control Room
Phase 1 MIS/ERP - TMS
•Depot/Workshop Management
•HR/Payroll
•Scheduling/Rostering
TMC
• Addition to Data Center for TMS
• Data Archival
External Bus Displays
Phase 2 TMC
• Video Wall
• Control Room
Phase 3
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
87
PIS information for commuters were considered as priority. The bus routes, driver/conductor information, etc., shall be entered through the AVL system. It was felt that these ITS systems will provide the management with the necessary data to get an understanding of the problems with passenger demand and scheduling needs. A basic room with systems and a basic data center will be implemented in this phase. Based on the SI system, either the existing datacenter of CTU or a new location will be selected. In Phase 2 the Transit Management System (TMS) solutions which focus on the current core activities that are being conducted by CTU like stores & inventory, maintenance activities, scheduling & planning, ticketing, etc. While some activities are already computerized, many of the activities are done manually by CTU staff. Hence, the implementation of this phase requires substantial business process reengineering that starts with building capacity within existing CTU staff. The GMs, Stores Managers, etc. all require to become computer literate to make the Phase 2 successful. Data Archival shall be implemented in this phase rather than Phase 1 to ensure its usage for all the systems (AVL, ticketing, etc.) in an effective manner. The needed additional servers for TMS system shall be added to the data center implemented in Phase 1. Finally, external PIS displays for the 34 existing buses for rear and side locations shall be implemented at this point. The objective of the boards is to ensure that passengers can identify the bus routes from behind and side of buses; and do not need to run to the front of the bus to identify them. Currently, CTU is still having trouble accurately inputting the route information for the front external PIS display, hence many buses are seen with a static board that is showing conflicting information that the electronic display. These electronic boards were phased such that CTU is more adept at implementing ITS solutions. In Phase 3, CTU seeks to implement a proper control room with a video wall. The expectation is that by this time AVL system would have penetrated CTU and would need support from realtime dispatch operations. Hence, a control room with video wall will be a need and can ensure CTU to provide efficient realtime operations.
5.4 Project Cost
The costs are estimated based on the tentative bill of quantities as discussed in the chapter. The total
project cost is sub-divided into capital cost and recurring cost. Capital cost is the initial investment for
the project estimated based on the market survey for all the ITS components. The total capital cost for
the project is estimated at Rs.13.56 crores. The total cost of the project is estimated at Rs. 17.12
crores
The recurring cost includes the operating and maintenance of the ITS infrastructure, human resource,
depreciation and overheads. The estimate for the recurring cost was arrived based on the project
needs and discussions with CTU. The total recurring cost is estimated at Rs.2.2 crores for the project
period of 6 years. This project period shall be extendable to 8 years based in the SI bid document.
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
88
6 Implementation Plan
Implementation plan describes the how the proposed system will be deployed, installed and made
operational. The plan shown in Exhibit 58 consists of an overview of the proposed ITS system,
description of the major tasks in the implementation, resources involved in the implementation. The
implementation is developed during the design stage of the project and updated during the deployment
stage based on the ground conditions.
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
89
Exhibit 58: Implementation Plan
Activity/ Reports Due
Project Phases
Item of Activity (Work) Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10 Month 11 Month 12 Month 13 Month 14 Month 15 Month 16 Month 17 Month 18
AA-1 Project Plan
A-2 Site Survey Report D
A-3 Hardware Design Documentation
A-4 Software Design Documentation D
A-5 System Requirement Specifications D
A-6 Implementation Plan D
A-7 Monthly Progress Report D D D D D D D D D D D D D D D D D
A-8 Phase-wise Status Report D D D
A-9 Exit Management Plan D
A-10 Final Project Report D
BB-1 Procurement - ETM & Workstations
B-2 Installation & Configuration D
B-3 Smart Card and ETM Integration D
B-4 Testing D
B-5 System Acceptance D
B-6 MIS Report D
CC-1 Procurement - AVL, PIS Display Boards & In-bus Display Boards
C-2 AVL Installation (134 Buses)
C-3 PIS Installation at Bus Stations
C-4 AVL Software Integration (513 buses)
C-5 Commuter Portal - Website, SMS, IVRS, Mobile Application D
C-6 On-bus PIS Intergation D
C-7 Testing D
C-8 System Acceptance D
C-9 MIS Report D
C-10 Destination (External) Boards Installation, Testing and Acceptance
D
D-1 Data Centre Hardware Procurement for Phase-1
D-2 Data Centre Hardware and Software Installation
D-3 Phase-1 ITS Software Customization D
D-4 Basic Control Room Setup
D-5 Testing D
D-6 System Acceptance D
D-7 Data Centre Hardware Procurement for Phase-2
D-8 Data Centre Hardware and Software Installation
D-9 MIS/ERP Dashboard
D-10 Scheduling & Rostering
D-11 HR & Payroll
D-12 Depot Centralization
D-13 Workshop Management System
D-14 External Bus Display Installation and Interface D
D-15 Testing D
D-16 System Acceptance D
D-17 MIS Report D
D-18 Procurement for Phase-3
D-19 Central Control Room
D-20 Video Wall Installation and Integration
D-21 Integration of All Systems D
D-22 Testing D
D-23 Project Rollout D
D-24 Final Operational Acceptance D
GG-1 Training Plan D
G-2 Equipment Installation Manual D
G-5 Hands on Training
G-6 Capacity Building Workshops
Sl. No.
Implementation & Acceptance Phase
Training & Capacity Building
Phase 1 Phase 2 Phase 3
Transit Management Centre
Project Planning and Design Documentation
ITS - Fare Collection System
ITS - AVL and PIS System
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
90
6.1 Studies
As part of the ITS implementation, the system integrator shall undertake study of the existing
operations, objectives and goals to be achieved through project. The activities to be undertaken by
the SI are as follows:
a) Review existing management systems and capabilities
Conduct existing staff interviews
Review of internal management practices
Identify information flows in area including schedule development, dispatch
operations and commuter information system.
b) Identify the technology function requirements
Identify the activities necessary to support the project during and post
implementation
Recommendations to develop technology capabilities within the organization
c) Develop operating procedures for information technology
Develop manuals and handbooks on operations and system information.
d) Estimate resource requirements for the continued operation of technology system
Develop estimations for cost and personnel for implementation and support of the
project.
Recommendations of existing staff skill development and new recruitments if
required.
Identification of implementation risks and schedule deviation due to staff availability
during different phases of project implementation.
6.2 Project Implementation Unit
CTU will set up a Project Implementation Unit (PIU) with the following staff composition for the
monitoring of the project implementation.
SL NO. DESIGNATION IDENTIFIED OFFICIAL
1 PUI – Head General Manager (Computerisation)
2 Member Head of Traffic and Operations department
3 Member Head of Engineering Department
4 Member Head of Administration and Accounts
5 Member General Manager (Purchase)
6 Member Financial Manager
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
91
6.3 Roles and Responsibility
Each stakeholder has specific role to plan in the implementation of the ITS project. Roles and
responsibilities of the stakeholders are outlined below. Roles and responsibilities will be detailed out
with liability clauses during finalization of the contract.
6.3.1 Project Implementing Unit / CTU
Develop Standard Operating Procedures (SOPs) for all processes and freeze the
requirements for the SI to implement before start of implementation.
Providing approvals at various stages and release of funds based on the progress.
Providing and arranging the permissions for SI for implementation of the work.
Provide required assistance in data gathering and other key requirements during the
implementation phase of the project.
Facilitate meetings between various stakeholders during the project execution phase.
Facilitating workshops for knowledge transfer from the SI to the CTU staff on the use of the
ITS equipments and software.
6.3.2 System Integrator
Design, supply and implementation of the ITS components are the responsibilities of the
System Integrator (SI).
Ensure all ITS sub-systems are fully integrated for smooth operation of the system end-to-
end.
Delivering quality products and providing the quality service is SI responsibility.
SI should ensure SLAs are met during the operation phase of the project.
Deploy adequate staff to complete the tasks in the specified time as per the implementation
plan.
Provide technical assistance and training to the CTU staff on usage of the hardware and
software which are part of the project.
6.3.3 Project Evaluation Agency
Project Evaluation Agency will be an external third party agency who will evaluate the implementation
of the ITS project.
Preparation of the pre implementation report.
Undertake pre and post implementation studies.
Timely evaluation of the project and report submission
6.4 Scaling Requirement
The initial system is being planned for 583 buses, 4 depots (excluding Tata AMC buses). The
application software and the hardware shall be capable of handling future demand of 1000 buses, 10
depots and around 5000 staff.
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
92
6.5 Operations Concept
Exhibit 59 shows the relationship between external, central, and field systems that will interface with
the proposed ITS system. The exact configuration and full capability of the external, central, and field
systems will depend on the information available and format of the information from the external
sources. Conceptually, however, this proposed ITS system must be flexible and able to support a
number of new systems as needed.
Exhibit 59 Operations Concept
External Systems – These systems exist outside CTU ambit, such as traffic data, road weather,
customers with requests, or emergency notifications from police or fire services. CTU must interface
with these systems to provide a safe and reliable bus service. The means by which agency collects
this data must be flexible as the systems will not have standardized interfaces. For example, individual
police may telephone the Control Centre with details of an emergency, while traffic data may be
supplied in the future by some Tricity agency electronically. Internally, CTU must process this data in
a standardized fashion that will enable a consistent distribution between the Field Systems (e.g.,
onboard equipment) and the Central System (e.g., Controllers).
Central System – This element represents both the CTU central information systems and the central
operational processes that take place at the Control Centre, as well as storage, maintenance, and
security facilities within CTU. Information is collected at this level from a variety of sources. These
include information from external systems to CTU, internal central systems (Stores Inventory Software,
etc.), or from the vehicles or field personnel such as Traffic Controllers. The information is processed
into a standardized format that works for the recipients to whom it is then distributed (e.g., bus drivers,
local police, customers).
Field Systems – These include the CTU buses, maintenance vehicles, mobile data systems,
personnel, and non-CAD/AVL onboard systems such as the ETMs, etc. Notifications from the field
systems, for example, a vehicle health status alert from VHMD diagnostics, can be distributed and
trigger a central system such as maintenance to alert mechanics to an issue on board a vehicle.
Alternatively, maintenance may turn off an alarm on a vehicle remotely, or the Control Centre may
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
93
control an onboard system, such as the on-board passenger information sign, by distributing a
command.
6.6 Risk Management Process
Risk is inherent in any project. It is more so in ITS projects due to the lack of organizational strength
in the agency and availability of skilled firms/professionals for implementation in India. Exhibit 60 below
provides a roadmap for key risks identification, monitoring and mitigation.
COMPONENT SUBCOMPONENT RISK MITIGATION
AVL System
Accurate
Schedules &
Routes
Lack of accurate schedules and
routes mapped out by the agency
leads to inaccuracies in the AVL
software, which leads to route
deviation errors. Also drivers
following the daily schedule is
another concern.
CTU Staff to freeze all the routes,
signoff and share with the SI. Clear
SOPs should be provided for
operations will mitigate the risk.
Bus Stop
Locations
If all the bus stops are not properly
mapped, skipping of bus stops will
occur in voice announcements. In
addition, the ETA information will
not be provided for these bus stops.
CTU Traffic Department Staff to
travel the routes and get inputs
from the conductors. Bus Stop
locations where no physical shelter
is present should be marked by
paint for the SI. This will ensure
that the geo-fencing locations are
fixed in one go.
Bus
Installations
Voltage spikes, installation issues
were common problems faced in
other cities for ITS implementation.
SI shall conduct a detailed study of
operating buses using voltmeters to
measure spikes in voltage. In
addition, bus body shall be studied
and installation diagrams shall be
provided for CTU approval.
Integration
The new JnNURM buses have
installed UBS-II OBITS equipment,
while the older buses require SCU &
BDC. Integration shall be a
challenge.
CTU to ensure that all OBITS
equipment is fully compliant with
UBS-II standards and protocols.
CTU should test the equipment for
conformity.
SI to tailor/develop APIs, etc, to
integrate the system.
PIS System Installations
Security and maintenance issues
have been principal concerns for
PIS display boards.
PIS installations should occur
where security can be provided by
CTU or any other government
agency. It should be clearly
understood that the SI cannot
provide security for the display
board. However, the SI should
provide casing around the display
boards where required to ensure its
safety. The SI should have
automated alerts for maintenance
issues of the remote PIS displays.
CTU should have log sheet and a
process to keep track of the
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
94
COMPONENT SUBCOMPONENT RISK MITIGATION
working of the displays on a daily
basis.
Fare
Collection
System
Acceptance by
CTU drivers
and
conductors
ETM is critical element of the ITS
system and needs to accepted
immediately before the rest of the
system.
Adequate training should be
provided. Speakers from other
STUs where ETMs are used should
be bought to CTU to give
confidence that the system is
friendly and helpful to the
employees.
TMS System Application
Development
The Software Application correctly
representing the processes of CTU.
SOPs on all the processes before
implementation can mitigate this
risk.
CTU ITS
System
Data
Integration
Data transfers are not seamless
resulting in various subcomponents
not providing the expected benefits.
Detailed design stage with the SI to
ensure that the design documents
and SRS are in line with the
requirements of the project and the
data transfer needs.
Exhibit 60 Risk Assessment & Mitigation
6.7 Training & Knowledge Transfer
Training and knowledge transfer program should be initiated by CTU to support the penetration of ITS
throughout the organization. CTU Staff, System Integrator and Project Management Consultant (PMC)
shall be responsible for the training. The training material shall be developed for both management and
staff of CTU. The training material should be in local language (Hindi or Punjabi) for the staff who are not
comfortable with English. An example of AVL training is shown in Exhibit 61.
Exhibit 61 Vehicle Mounting Unit/CAD-AVL unit (VMU) Training Manual from IBI’s VTMS Project
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
95
The training should look at the stakeholder requirements, type of ITS understanding required and mode of training. Preliminary training schedule is shown in Exhibit 62.
Stakeholder business need training module duration mode of training
Driver/conductor High level
understanding
of ITS
Understanding
of SCU and its
functionalities
How ITS is
used that
impacts the
drivers &
conductors
Intro to ITS
SCU Usage
Basic MIS
Reports
2 hours Presentation Control Room Visit
Depot Manager/ Senior Depot Staff
High level understanding of ITS
ITS Usage
Intro to ITS
Detailed ITS
Applications
Introduction
Detailed MIS
Reports
2 days Presentation Hands-on Training
Management High level understanding of ITS
ITS Usage
Intro to ITS
Basic MIS
Reports
1 hour Presentation
Mechanical Staff High level understanding of ITS
Equipment Fixing
Intro to ITS
Vehicle
Installations
2 hours Presentation Control Room Visit
CTU ITS Users Detailed understanding of ITS
Detailed understanding of Applications
Detailed
understanding
of MIS report
Intro to ITS
Detailed ITS Applications Handson Training
Detailed MIS Reports
TMS - 5 days AVL – 2 days FCS – 2 days
Presentation Hands-on Training
Exhibit 62 Preliminary Training Plan
6.8 Monitoring & Evaluation Plan
Monitoring and evaluation are important tools to track the progress of the project and to facilitate decision
making in keeping the project on the right progressive path. The objective of the monitoring and evaluation
is to keep track of the progress of the project and to analyze the progress to plan the future course of the
project.
For ITS projects, it is important to track the penetration of ITS and whether the benefits are realized. A
preliminary M&E framework is presented for CTU to track the project.
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
96
Sl
No.
Performance
Indicator Criteria
Source of
data
Location of
measurement Measures
Reports and
frequency
Details /
Explanation Sample size
1 Commuter impact
1.1 Commuter
satisfaction
Primary - User
survey
Along the route & From user surveys at bus-stations and on-
board
Waiting time, travel time at station,
crowding at bus stops, on board crowding, timely information Before ITS
installation, Quarterly after ITS installation
till end of the assignment
Impact : Overall Bus operations
1%
1.2 Waiting time
Primary - User
survey
Commuter surveys at selected bus stops
along the route
Change in waiting time for commuters in
minutes
Impact : PIS ( Display boards ,
SMS , Web ) 1000
1.3 Travel time
Primary
Surveys at selected bus stops along the
route & Vehicle Tracking reports
Change in total travel time of commuters in
minutes
Impact : Modal shift
100
1.4 User cost
Waiting time + travel
time
1.5
Real-time CTU service
information to commuters
User survey &
SMS / Web stats
From webpage access count, SMS
counts and user surveys
Availability of commuter friendly
route maps, schedule, real time information
etc
2 months after complete ITS
installation
Impact : PIS, Website, SMS
services All
2 Operator (CTU) impact
2.1 Staff
Satisfaction
Primary - Staff
survey
Depots / Divisional offices
ITS impact on CTU operations
Before ITS installation, 2 months after ITS installation
Impact : Organizational
acceptance of ITS 1% of Staff
2.2 ITS Penetration
at STU
Primary - Staff
survey
Depots / Divisional offices
Knowledge of ITS and its applications among
the CTU crew
After pilot study, during project
implimentation,2 months after complete ITS
installation
100
2.3 Operational
cost / km
Secondary CTU operation
Change in the operational cost per kilometer before and
after the project
Before project installation, 6 months
after complete ITS installation
Impact : Operational
planning
All - for one month period
for baseline and after-project
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
97
2.4 Operational
cost / passenger
Secondary CTU operation
Change in the operational cost per
passenger before and after the project
2.5 EPKM –
Earnings per kilometer
Secondary CTU operation
Change in the total earnings of the
operator per kilometer before and after the
project
2.6 EPP – Earnings per passenger
Secondary CTU operation
Change in the total earnings of the
operator per passenger before and after the
project
2.7 Profit
Secondary CTU operation
Change in the overall Profit before and after
the project
2.8 Operational impact
2.8.1 Schedule
adherence
■ < - 10 min
Primary Departure / selected Intermediate / Arrival
points
Number of trips within the described tolerance
/ deviation range
Before project installation, 2 months
after complete ITS installation
■ Timely departure from
terminals is essential to
maintain good schedule
downstream
1000 data points
■ -10 to -1 min
■ -1 to 5 min ■Before ITS
implementation- records from CTU can be accessed
for evaluation
■ 5 to 10 min
■ 11 to 15 min
■ > 15 min
■ Irregular headway
increases waiting time and
diminishes the effective capacity
of buses
3 Environmental impact
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
98
3.1 Fuel
consumption / passenger km
Secondary Vehicle Tracking
data Change in fuel
consumption in liters 6 months
Impact : Passenger fare
All - for one month period for baseline and after-
project
4 Safety
4.1
Accidents per 100,000 vehicle km (Vehicles &
Passengers)
Secondary Sector wise ,
Vehicle Tracking data
Number of accident per 100,000 vehicle km
Quarterly Measures provide
passenger and vehicular safety.
All - for one month period for baseline and after-
project
4.2
Accidents per million
passenger trips (Vehicles & Passengers)
Secondary Sector wise ,
Vehicle Tracking data
Number of accident per million passenger trips
Quarterly Measures provide
passenger and vehicular safety.
All - for one month period for baseline and after-
project
4.3 Incident
response
Secondary -
Operation records
Sector wise & measured actual
response time from the records
In case of emergency or accidents the time taken in minutes to respond / clear it
Quarterly Impact : Central control station
All - for one month period for baseline and after-
project
5 Others
5.1 ETA & ETD accuracy
Primary Terminals and bus stops where display boards are installed
Accuracy of the bus arrival and departure
information
Monthly 30 locaitons
5.2 ITS commissioning
5.2.1 SCU & BDC installation
Primary - Field
surveys
Buses
Monthly after pilot installation till completion
All Locations
5.2.2 Display board
installation
Terminals and bus stops
All Locations
5.2.3 SCU & BDC functioning
Buses All Locations
5.2.4 Display board
functioning
Terminals and bus stops
All Locations
5.2.5 MIS reports
ITS System
generated
All Reports
CTU - Chandigarh Transport Undertaking ; ITS – Intelligent Transport Systems; STU – State Transportation Unit;PIS- Passenger Information System; SCU - Single Controller Unit; BDC - Bus Display Console; MIS – Management Information System; ETA – Estimated Time of Arrival; ETD – Estimated Time of Departure
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
September 2015 99
APPENDIX
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
September 2015 100
Appendix 1 – Baseline Scenario of City Bus Services
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
September 2015 101
Introduction
Demographics
The following Exhibit 63 summarizes the base line scenario on demographics of the study area.
CITY POPULATION
(2011)
GENDER
RATIO8 LITERACY RATE (%) AVERAGE INCOME
Chandigarh 10.55 Lakh 817 86.05 (Female: 64.8) -
Mohali 1.7 Lakh 911 93.22 (Female: 91.1) -
Panchkula 2.1 Lakh 883 87.86 (Female: 84.0) -
Tri city 14.25 Lakh - - Rs. 22,857/month
National Average - 940 74.04 (Female: 65.5) Around Rs. 5,500/month
Exhibit 63: Demographic Characteristics of Study Area
The primary, service and manufacturing sectors are the major employment sources in the study area.
CTU city bus service aims to serve the travel needs of the total population of tri-city which is about 1.4
million people. The average household size is 4.46. The table below shows the projected population for
the three cities.
CITY #POPULATION
(2011) POPULATION (2031)
SOURCE FOR
PROJECTIONS
Chandigarh 10.55 Lakh 15.5 Lakh Chandigarh Master
Plan for 2031
Mohali 1.7 Lakh 8.15 Lakh CMP for Chandigarh
Urban Complex
Panchkula 2.1 Lakh 5.42 Lakh
Tri city 14.25 Lakh 29.07 Lakh
| # Census
The average income of household (Rs. 22, 857 /-) of the study area is quite high when compared to
that of national average which also could be the reason for high motorized vehicle ownership. The
average household transport expenditure is around 10.8% of total household income9 as shown in .
The Master Plan for Chandigarh states that 86% of the households have either car or two-wheeler or
both.
Given the income levels and private vehicle ownership numbers, modernizing of city bus services is
required to focus on increased comfort and reliability is essential to shift the people from private
motorized vehicles to the public transport. Frequency and comfort mostly will have greater impact on
bus ridership than fares.
Institutional Framework
Various functions related to transportation services in the city and responsible agencies are listed in the
below Exhibit 64.
8 Gender Ratio is the number of female persons per 1000 people 9 CMP for Chandigarh Urban Complex, 2009
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
September 2015 102
FUNCTION RESPONSIBILITY
Transport Infrastructure and O&M Maintenance Municipal Corporations10 and Chandigarh
Administration
Policy for Traffic, Vehicle Registration Transport Department of all the three areas
City Urban Planning
Chandigarh Administration for Chandigarh and
Punjab and Haryana Urban Development Authorities
for other two cities.
Traffic Rules Enforcement, Awareness and Traffic
Management Traffic Police in all the three areas.
City Bus Services Chandigarh Transport Undertaking (CTU)
Interstate and Intercity Bus terminals Municipal Corporations, Development Authorities,
Chandigarh Administration & Operations by CTU
Bus Stops Maintenance Municipal Corporations in all the three areas.
Environmental Pollution Control Pollution Control Board and Committee
Intercity and Inter State Bus Services CTU, Haryana Roadways, Punjab Roadways
Exhibit 64: Key Transportation Services and Responsible Agencies in the Tri-City Area
CTU is responsible for the city bus services in the study area. CTU was established in the year 1966
with a fleet of around 30 buses and now provides bus services to the public covering the city, suburbs
and the neighboring states. CTU is also a member of Association for State Road Transport Undertaking
(ASRTU). The organizational structure of CTU is been shown in the Exhibit 65 below.
General Managers (2),
All Depots
Assistant Divisional
Manager (Technical &
Stores)
Assistant Divisional
Manager (Traffic &
Commercial)
Assistant Controller
(F&A) (H)
Superintendent (Head
Office)
Superintendent
(Recruitment Cell)
Works ManagerAssistant Controller
(F&A)Superintendent
Preventive
Maintenance
Assistant
AccountantEstablishment
Assistant
Director, Transport,
Union Territory,
Chandigarh
Purchase Section &
Stores
Station Supervisor
(Traffic)
Care Taker (Nazir)
Care Taker (Bus Stands)
Statistical Assistants
Budget Assistants
Building Assistants
Esstt. Asstt. (H)
Esstt. Asstt. Drivers
Esstt. Asstt. Conductors
Esstt. Asstt. Management
Esstt. Asstt. Workshop
Identity Card Clerk &
Dispatch Work
Esstt. Asstt. General (H)
Compassionate Appointments,
Election Work,
All type of Recruitment Work
Exhibit 65: Existing Organizational Structure of CTU
Exhibit 66 presents the growth of population & registered vehicles and accident pattern over the past 5
years. The rate of growth of vehicles is faster than the rate of growth of population which is a threat to
the urban transport system. It can be observed from the graph that, there is a decline in number of
10 Municipal corporations of all the three areas of tri-city areas
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
September 2015 103
accidents from 2010 which may be attributed to the introduction of new JnNURM buses in 2010. It also
shows the potential of city bus services to gather more mode share with more population.
Exhibit 66: Growth of Population, Registered Vehicles & Accidents in Chandigarh
The user satisfaction survey conducted by The World Bank reports that 77.2 % people stopped using
the bus once they bought a TW or a car. Chandigarh Traffic Police are active in enforcement of traffic
rules and in public education through different means. A lot of guidance on following traffic rules and
fines is provided in their website (http://www.chandigarhtrafficpolice.org/index.php). Police are
encouraging people to travel through public transport and non-motorized transport to reduce congestion
and accidents. They are also trying to encourage public to participate in traffic enforcement by becoming
traffic marshals.
Travel Characteristics
Per capita trip rate in the tri city area is 1.32 including walk. This walk trips include the access and
egress legs of PT and IPT trips too. Trip lengths mostly depend on the distribution of different activities.
As per the CMP study of 2009, Mode shares for different modes in Chandigarh Urban complex area11
are shown in the below Exhibit 67.
It can be observed from the Exhibit 40 that, there is a significant mode share of walk and bicycle modes.
This is due to the presence of good pedestrian footpaths and cycle tracks in the city. The private
motorized trips comprise about 50% of total trips from where the shift to public transport should be
aimed primarily. There are about 30% of trips by non-motorized modes which is a good sign, and bus
11 It is to be noted that, the mode shares provided here are of 2009 year due to the lack of the latest data than that for tri-city area. Hence, it may subject to change at current year.
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
September 2015 104
has a further scope to get passenger shift from the motorized trips with improved and modern bus
services.
There are 11.2 % of trips by bus as a mode in the tri city area. However, there would be an increase of
ridership as on date as 100 more new buses have been inducted into city bus service after 2010.
Exhibit 67: Mode Shares for Different Modes in Tri City Area in 2009
Relevant Future Proposals
The following (as given in Exhibit 68) are the different development proposals proposed by CTU and
other authorities of Chandigarh, which have impact on city bus services in the Tri-City area.
S.
NO. PROPOSAL
PROPOSED
BY/ UNDER STATUS
1 Augmentation of Buses from
JnNURM
CTU About 449 buses have been sanctioned and
procurement process has been initiated by CTU.
Some buses also got delivered.
2 Expected Augmentation of
Buses
CMP About 1250 buses have been estimated to be
present as city bus service, in CMP considering the
Metro Rail and BRT system. The numbers may
increase, if these systems don’t get implemented
by that year.
3 Bus Shelters Improvement &
Rebuilding
CTU and
Chandigarh
Administration
Chandigarh Administration is in the process of
finalizing the design of new shelters. Retrofitting of
bus shelters has not yet started. IBI has given
inputs on the same.
4 Bus Depot Development CTU and
Chandigarh
Administration
Chandigarh Administration is in the process of
finalizing the design of new depot. IBI has given
inputs on the same.
5 Bus Depot Development CMP CMP has suggested having 8 bus depots by 2021
for city bus service.
6 New Inter State/ City Bus
Terminals (3)
CMP Information Not Available
7 New Intra City Bus Terminals
for BRT
CMP Information Not Available
1, 17.35%2, 2.87%
3, 10.94%
4, 11.24
%
5, 5.85%6, 1.29%
7, 35.38%
8, 15.07%
Travel Mode Shares in Tri City in 2009
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
September 2015 105
S.
NO. PROPOSAL
PROPOSED
BY/ UNDER STATUS
8 Metro Rail & BRT CMP Metro Rail (64.3 Km) and BRT (144.2 Km) have
been planned as per CMP. Metro DPR has been
prepared for 7 corridors. But these proposals are
not yet approved.
9 Recruitment of employees CTU CTU is in the process of recruiting about 230 drivers
and 230 conductors by ‘outsourcing to a private
company’.
10 Public Bike Sharing System Chandigarh
Administration
In the process of preparation of DPR.
Exhibit 68: Summary of Relevant Future Proposals in Chandigarh by Different Agencies
Proposed MRTS
CMP proposed a BRT (Bus Rapid Transit) network covering the Tri-city with 144.2 km of BRTS on
10 corridors. However, there has not been any progress on the development of BRT is Chandigarh
Urban Complex.
As per CMP 2009, the metro rail is proposed in three phases covering total of 64.3 Km; of which
44.8 Km is in Chandigarh, 6.5 Km in Panchkula and 13 Km in Mohali.
In 2012, the Metro Rail DPR12 was approved. As per the approved Metro DPR, the metro rail has
been proposed on two corridors as given in
Exhibit 69: Details of Proposed Metro Rail in DPR for Chandigarh Urban Complex Area (Tri-City)
below on a total length of 37.6 Km with 30 stations.
S.
NO. CORRIDOR
ELEVATED
(KM)
UNDERGROUND
(KM)
TOTAL
LENGTH
(KM)
YEAR 2018-
ESTIMATED
TRAFFIC
YEAR
2018-
PHPDT
1 Capitol to Gurudwara Singh
Shaheeda 4.427 8.070 12.497 168185 7007
2 Transport Terminus to
Grain Market 19.041 6.035 25.076 173716 6711
Total 23.468 14.105 37.573 341901 13718
Exhibit 69: Details of Proposed Metro Rail in DPR for Chandigarh Urban Complex Area (Tri-City)
It is suggested in Metro DPR to start the operations by the year 2018. However, there is no progress
on the development.
As per the metro DPR, the frequencies are designed to be around 12 min for peak hours and 16-
30 min for lean hours in 2018 if it gets implemented by that time.
Different alternatives proposed in Metro DPR are shown in Exhibit 70.
12 DPR - Detailed Project Report
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
September 2015 106
Exhibit 70: Proposed Metro Rail Corridors (Alternative II – Pink+Red) in Metro Rail DPR
Public Transport Infrastructure
The public transport system in the Tri-city area includes the CTU city bus service; shared auto-rickshaw
service and regular auto-rickshaw are also present which serve as intermediate public transport system.
The public transport infrastructure for the CTU bus service include: bus fleet, bus shelters, and bus
depots. CTU bus services travel up to V4 roads which bisect the sectors. Recently, Chandigarh Traffic
Police has started pre-paid auto service at 8-10 prominent locations. An overview of the various critical
infrastructure of CTU such as buses, bus queue shelters, bus depots and manpower availability with
the CTU for the city bus service has been presented in the subsequent parts of this section.
Bus Fleet
In FY2013-2014, CTU has the total fleet of about 517 buses which include both long distance regional
buses and also city & suburban buses. There are currently around 453 buses that are being operated
after condemning the old buses which are operated from four depots of CTU. CTU has already issued
an auction notice for scrapping of around 54 buses along with some workshop materials.
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
September 2015 107
Out of the 453 buses, 13290 buses were running as city bus service which is serving Tri-City Area in
2013-14. There are some suburban bus services to the nearby areas like Zirakpur, Kharar, etc. The
fleet includes standard size buses, semi low floor non A/C, A/C, Low Floor A/C buses, Low floor non
A/C Buses, and mini A/C buses. All the fleet is from either manufactured by TATA or ASHOK LEYLAND
only. CTU has secured funding for about 100 TATA MARCOPOLO buses by MoUD under JnNURM
scheme in the year 2010.
The Exhibit 71 below gives the existing bus fleet details as in FY 2013-14.
S.
NO
CATEGORY OF
BUSES
NO. OF
BUSES
MANUFACTUR
ER Bus Image
Average Age
in years
1. Semi Low Floor Non A/C
Buses (650 mm) 90 TATA
8.69
2. Low Floor A/C Buses
(400 mm) 40
TATA
MARCOPOLO
4.38
3.
Low Floor Non A/C
Buses
(400 mm)
60 TATA
MARCOPOLO
4.38
5. Standard Front Engine
Buses (900 mm) 66
ASHOK
LEYLAND -- 8.94
6. A/C Mini Buses 34 ASHOK
LEYLAND
4.99
Total 290 6.65
Exhibit 71: Summary of Fleet Available For Operation with CTU for City Bus Service as in FY 2013-14
Source: CTU fleet data base, 2014
There were about 20 buses being operated per one lakh population of the tri-city (14.25 lakhs).
Average age of the bus is observed to be around 6.65 years which is close to the scrapping age as per
the scrapping policy of CTU. As per the CTU’s norms, scrapping age is about 8 years or 5 lakh Km
which ever reaches first. The average age of 6.65 doesn’t include the new sanctioned buses which are
under procurement. Semi low floor TATA buses and standard buses are more than 8.5 years old which
are not in very good condition. All the buses under city bus services are with BS II compliant engines.
13 Public Transport Review of Cities Part 1: User Satisfaction Survey, WB Study, 2014
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
September 2015 108
TYPE OF BUS AC/NON AC FLOOR HEIGHT (MM) BHARAT STAGE NO. OF BUSES
Midi AC 650 BS IV 80
Midi Non AC 650 BS IV 90
Standard AC 650 BS IV 70
Standard Non AC 650 BS IV 90
Standard AC 450 BS IV 70
CTU has placed orders for new buses under JNNURM scheme. The delivery of buses has already been
started in October 2014. By November 2015, around 330 buses of sanctioned 379 buses will get
delivered to CTU. These new buses will be equipped with GPS and passenger information system
inside the bus. Man Power Assessment
Currently all the city buses and other long route and sub-urban route buses are being managed
together, there is no specific manpower ratio for city bus that is available. The manpower ratio14 for the
entire CTU operations is about 4 persons per bus as shown in Exhibit 46. It includes crew, maintenance
staff and the management staff in the total organization. From the
Exhibit 73, it is observed that the manpower productivity is approximately 50 Km/staff/day whereas the
national average manpower productivity is about 53.9 Km/staff/day15.
Exhibit 72: Manpower and Operational Fleet with CTU in 2013-14
CTU is facing shortage of crew for bus operations as there have been limited recruitments in the past
decade. It is found from CTU that, about 20% of total staff cost in 2013-14 was spent in overtime duties.
It shows the criticality of staff shortage. Still, CTU was not able to utilize all the fleet (only 74% of fleet
used to get utilized in Depot 2) and also not able to operate the entire Km scheduled (with around 10%
of missed Km in Depot 2). The staff shortage not only impacts directly the amount of operations, but
also the quality of service such as reliability, overcrowding and customer’s negative perceptions on the
service. There is also a risk of having high number of breakdowns and accidents because of improper
driving behaviour due to overtime of drivers.
14 Public Transport Review of Cities Part 1: User Satisfaction Survey, WB Study, 2014 15 State Transport Undertakings – Profile and performance 2011-12, CIRT
2172
20962136
2055
1921
1826
406 409
471
493
472453
0
100
200
300
400
500
600
1600
1700
1800
1900
2000
2100
2200
2008-09 2009-10 2010-11 2011-12 2012-13 2013-14
Nu
mb
er
of
Bu
ses H
eld
Sta
ff S
tren
gth
in
nu
mb
ers
Financial Year
Staff Strength (Source: STUs Performance Book) Staff Strength Number of Buses Held
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
September 2015 109
CTU has called tenders for outsourcing of about 230 drivers and 230 conductors in September 2014.
CTU is anticipating recruiting more staff considering the new buses that are being procured under
JnNURM.
Bus Queue Shelters
Bus Queue Shelters (BQS) are specific to its own government jurisdictions and hence CTU is
responsible for bus shelters which are required in the Chandigarh Administration jurisdictions. However,
CTU operates city bus service in Mohali and Panchkula too. There are about 266 bus queue shelters
present in Chandigarh which cover almost all the bus stops of CTU route network in Chandigarh area.
Exhibit 74 shows the details of existing bus queue shelters. Presently, Chandigarh Administration is in
the process of designing new bus queue shelters and is also retrofitting some of the shelters.
Bus Depots
Bus depot is a place from where buses are dispatched for the operations as per the schedules and are
maintained & parked when they are not in operation. Currently CTU has four depots from where it is
operating all the buses including long route, suburban routes and city bus routes. Two depots (Depots
2 & 4) are only operating the city bus routes, while other two depots (Depots 1 & 3) operate all routes
including city bus, suburban and long distance routes.
All the above mentioned depots have their own workshops. However, based on need, the buses are
maintained at one of the other workshops too. One new depot has been proposed by CTU to be
developed in an area of 6.5 acres with the capacity to handle around 125 buses at Raipur Kalan in
Chandigarh to cater to the sanctioned JnNURM buses in the future. Exhibit 76 below shows the
geographic locations of existing and proposed depots.
With addition of 379 buses in near future after condemning all the remaining over aged fleet from Depot
2, the total fleet of city buses (Depot 2 and Depot 4) will be 513 buses. The total capacities of depots
(Depot 2, Depot 4 and Raipur Kalan Depot) which will be dedicated to city bus service will be ideally
355.
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
September 2015 110
Exhibit 73: Geographic Location of Existing & Proposed Bus Depots of CTU
The depot locations seem to be compatible with the route terminal points. However, the dead Kilometers
are still greater than 6% for CTU operations.
Most of the A/C buses are with Depot 4 and also the terminal points of major number of AC
routes are very close to Depot 4 or at Depot 4.
Most of the point-to-point routes are having terminal points close to Depot 3 and Depot 4.
The location of new proposed bus depot is located to ensure a Depot for Panchkula access.
There needs to be detailed study on allocation of routes to each depot before operationalizing the new
depot so as to reduce the dead kilometers. It can be addressed as part of route rationalization study.
The design of new bus depot (at Raipur Kalan) is in the process. The design of new bus depot (at Raipur
Kalan) is in the process.
One of the four depots is being taken care by TATA motors as AMC for maintenance of buses. The
team visited the depot at ISBT Sector 43 which is under maintenance by TATA Motors where the vehicle
maintenance is found to be more organized.
Depot 3
Depot 4
Depot 1
Depot 2
Raipur Kalan Depot
(Proposed)
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
September 2015 111
The proposed new depot at Raipur Kalan (shown in Exhibit 78) is measured to be around 26,000 sq.
m. (Approximately 6.42 Acres).
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
September 2015 112
Exhibit 74: Satellite View of Site Layout of the Newly Proposed Raipur Kalan Depot
(Source: Google Maps)
The new buses scheduled to be delivered by the end of December 2014 are being delivered by two
different manufacturers with on-board ITS equipment as per UBS-II specifications. The manufacturers
are required to share the details of the ITS equipment and the setup needed for CTU. It is necessary to
develop common back-end ITS software for all the buses being supplied by various manufacturers
mainly for ease of operations.
Ridership & Operational Performance
Ridership is a key indicator in assessing the service level of any public transport system. The daily
ridership16 of last 5 financial years has been analyzed and reported in Exhibit 79.
16 Review of the performance of SRTUs – FY 2012-13, MORT&H, Jan-2014
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
September 2015 113
Exhibit 75: Ridership Pattern of City Bus Service of CTU Over Last Six Financial Years
The ridership over last six years is varying between 1.5 to 2 lakh passengers. The ridership increase in
the year 2010-11 is due to the introduction of additional 100 JnNURM A/C and non A/C buses along
the city bus routes. A fall of ridership in last two financial years is observed which is mainly due to the
reduction of buses due to condemnation of some buses and age of the bus leading to more breakdowns.
These kinds of fluctuations show the inconsistency in supply of buses and hence demand is getting
affected. The system will also lose the reliability with this kind of pattern.
Currently CTU is carrying 1.55 lakh passenger trips per day on city bus service with about
537passengers per bus per day which is relatively low when compared to the national average
of over 1000 passengers per bus per day.
The following table gives the depot wise statistics for some parameters in the financial year
2013-14. The statistics of depot-2 and depot-4 are representative of city bus services.
PARAMETER DEPOT 2 DEPOT 4
No of buses operated 108 97
Total Operated Km/ Day 22755 16710
Total Dead Km/ Day 2593 8
Fleet Utilization 74% 97%
% of Dead Km in total Km 10.2% 0.1%
There is a fleet utilization of about 86% for city buses (Depots 2 &4). The remaining city buses
were not able to be operated because of the reasons like maintenance issues, lack of drivers/
conductors to run the buses, etc. It is found from depot wise statistics that, there is only 74%
fleet utilization in Depot 2 for the same reasons. The fleet utilization in Depot 4 is about 97%
which is good when compared to the national average which is about 84%.
184193
160152
192094 195168
163976155325
2116381
1840143
2207163 2242485
18840881784679
0
500000
1000000
1500000
2000000
2500000
0
50000
100000
150000
200000
250000
2008-09 2009-10 2010-11 2011-12 2012-13 2013-14
Pas
sen
ger-
Km
Pas
sen
gers
Financial Year
City bus passengers/day Passenger-Km
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
September 2015 114
The total dead kilometers are contributing to 10.2% of the total Km in Depot 2, which require
further study of the routes. Depot 4 has negligible dead kilometers, as most of its routes start
from ISBT itself which is located beside the Depot 4.
Vehicle productivity of 148 Km per bus per day is low as compared to the national average of
over 180 Km per bus per day.
Average Load factor of 69% for city bus service shall be in the median range when compared
with the best STU’s nationally.
Punctuality of Services: It is documented that about 32.5% of users of city bus service are
not satisfied with the punctuality of city bus service.
Passenger Information
Information to passengers is provided using the following methods by CTU for city bus users:
Route Schedules & maps are placed on CTU’s website, and any changes in the scheduled
routes on any particular day are also updated through the website.
Many bus shelters don’t have even static information on the routes that pass through that stop.
There is no real time passenger information for CTU city bus service at present. There is a mobile
application for the information on city bus routes along with the map and frequencies. However, the
data in this application does not get updated as per the changes in CTU routes data frequently.
Fares
Fare structure is based on the distance travelled by the user. Prior to September 2014, there were only
two fare slabs: ‘below 5 Km’ and ‘over 5 Km’ for both A/C and Non-A/C buses as shown in Exhibit 80
below.
S. NO. BUS TYPE DISTANCE SLAB FULL TICKET
1 Non-A/C Buses
0-5 Km ₹ 5
2 > 5 Km ₹ 10
3 A/C Buses
0-5 Km ₹ 10
4 > 5 Km ₹ 15
Exhibit 76: Previous Fare levels in CTU’s City Bus Services as per Fare Revision in April 2010
The fare structure has been revised on the 3rd of September 2014, after incorporating more slabs in
fare structure as shown in Exhibit 81. However, the number of fare slabs depends on the variance range
of the different trip length intervals of users. Fare level is different for A/C buses than that for Non-A/C
buses.
S. NO. BUS TYPE FARE STRUCTURE
Distance Slab Full Ticket Half Ticket 1
Non-A/C Buses
0-3 Km ₹ 5 ₹ 3
2 3-10 Km ₹ 10 ₹ 5
3 > 10 Km ₹ 15 ₹ 8
4 A/C Buses
0-3 Km ₹ 15 ₹ 8 5 3-10 Km ₹ 20 ₹ 10 6 > 10 Km ₹ 25 ₹ 13
Exhibit 77: Current Fare levels in CTU’s City Bus Services as per Fare Revision in September 2014
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
September 2015 115
There is around 50% concession for children (between 3 years and 12 years) in ticket fare which in the
above is referred to as “Half Ticket”. CTU doesn’t charge any fare for children below 3 years of age.
There is 50% concession for senior citizens, valid only for travel within UT area of Chandigarh. The
minimum fare has been set at ₹ 5 for full ticket and maximum fare is set at ₹ 25 for A/C buses for
travelling more than 10 Km. At present scenario, fares are collected through traditional manual ticketing
method. The information on sale of tickets is entered daily in the waybill by the conductor.
Fleet Breakdowns and Trends
Fleet breakdowns are very critical as they directly affect
the reliability of the city bus system. Fleet breakdowns
over the last two financial years have been reviewed to
know the level of criticality. It is observed that, the fleet
breakdowns in the city buses are more compared to that
of the long route buses. It is concerning to note that the
breakdowns in the Depot 4 are observed to be the highest
for last two years where new JnNURM buses are held with
better maintenance management systems. The following
Exhibit 84 shows the fleet breakdowns in Depot 2 and
Depot 4 which pertain to only city bus service as per the operational statistics data of CTU.
S. NO.
NUMBER OF OPERATED
KM
NUMBER OF
BREAKDOWNS
BREAKDOWNS/ 10,000
OPERATED KM
FY 2012-13 FY 2013-14 FY 2012-13 FY 2013-14 FY 2012-13 FY 2013-14
Depot 2 93,17,166 83,05,406 519 765 0.56 0.92
Depot 4 59,39,093 60,99,232 987 679 1.66 1.11
Exhibit 78: Fleet Breakdown Statistics in 4 Depots of CTU in Last 2 Financial Years
On an average, there is about one breakdown per month for running every 2 buses. There are about 4
breakdowns occurring for city buses (depot 2 and depot 4) every day. More than 90% of these break
downs are in minor category. The breakdowns for city bus services are found to be 0.56 to 1.66
breakdowns per 10,000 operated Km in the financial year 2012-13 and 0.92 and 1.11 breakdowns per
10,000 operated Km in Depot 2 and Depot 4 respectively. The national average stands at 0.97
breakdowns per 10,000 operated Km. Overall, the breakdown rates are not significant enough to create
a negative impact on the operations, but there is still scope for reducing the breakdowns by investigating
the reasons in much more detail. Most of these breakdowns are related to tyre punctures, diesel and
starting trouble.
The following are the key reasons for large breakdowns in the city bus service:
Poor driving of the drivers which increase the attrition of several bus parts like gear box, tyres
and brakes. It may be because of overtime working of drivers due to shortage of staff.
In general, TATA Marcopolo buses (which are present in Depot 4) have frequent complaints of
breakdowns compared to the other models of buses.
Inadequate maintenance facilities and infrastructure in Depot 2.The cause wise analysis as per the data
provided by CTU has been shown below in Exhibit 85for last year (January to December 2014). It is
found from the data that, the number of break downs after the financial year of 2013-14 has been
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
September 2015 116
decreased considerably by around 50%. There are only 314 breakdowns reported in the total year of
2014 where it was 614 from April 2013 to March 2014.
Exhibit 79: Cause-Wise Breakup Count-Split In Year 2014
It is found that there are only two towing vehicles and one breakdown vehicle in total with CTU for
attending breakdowns across all the depots. As there is limited number of buses available, it has been
difficult for CTU to designate some buses as spare buses to replace the breakdown vehicles.
Fleet Accidents and Trends
The Exhibit 86 below shows the accidents rates (number of accidents per 1,00,000 Km) involving CTU
buses for the entire operations. The rates are found to be consistently varying between 0.2 and 0.4 with
an average of 0.37 accidents per 1,00,000 operated Kilometers.
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
September 2015 117
Exhibit 80: Accidents Rates of CTU Bus Operations from 2001 to 201417
The following Exhibit 87 shows the accident statistics over the last financial year 2013-14 across all the
depots.
PARAMETER DEPOT 2 DEPOT 4
No. of buses held 147 100
Operated Km 8,305,406 6,099,232
Fatal Accidents 0 1
Major Accidents 0 8
Minor Accidents 17 75
Total Accidents 17 84
Accidents/ 1,00,000 Km 0.20 1.38
Exhibit 81: Accidents Statistics for CTU depots
It is found that, accident rates are significant at 1.38 for Depot 4 where new JnNURM buses (TATA
Marcopolo buses) are operating. It is also higher than that of the national average of 0.27 accidents
per 1,00,000 Km. Category-wise split of accidents is shown in Exhibit 88.
17 http://chdctu.gov.in/statistic.aspx (Accessed on 06th October, 2014)
0
0.05
0.1
0.15
0.2
0.25
0.3
0.35
0.4
Acc
ide
nt
Rat
e (
Nu
mb
er
of
acci
de
nts
pe
r 1
,00
,00
0 K
m)
Year
Accident Rate
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
September 2015 118
Exhibit 82: Split of different categories of accidents occurred in FY 2013-14 for CTU buses
Discussions with the employees revealed that, the reasons for more accidents in Depot 4 buses is the
length of the new model which causes a problem in driving/ maneuvering, especially while negotiating
blind curves in inner sector roads and roundabouts18. Other reasons for accidents that were gathered
from the conversations include:
Poor driving discipline amongst the drivers
Overtime of existing drivers due to shortage of drivers
Poor traffic discipline of drivers of other vehicles and also the pedestrians while crossing roads.
According to the traffic police, there is also negligence of the victim in accidents involving city
buses.
Fuel Economy
Currently all CTU buses use diesel as fuel. All the buses get fuelled at their corresponding depots only.
The following Exhibit 89 gives the statistics on fuel economy for CTU buses for the FY 2013-14. Depot
2 and Depot 4 are for city buses.
PARAMETER DEPOT 2 DEPOT 4 CTU
HSD Consumption in Liters in an year 2267291 2768084 9787148
HSD Consumption in Liters in a day 6212 7584 26814
Total Km (Dead + Operated) in an year 9251724 6102291 35534268
Average Mileage (KMPL) 4.08 2.20 3.63
Operating Buses 155 100 453
Fuel Consumed per bus per day 40 76 59
Exhibit 83: Fuel Economy Statistics of CTU Bus Operations
Currently on an average, CTU has the mileage of 3.63 Km per liter which is lower than the national
average (of urban STUs) of 3.82 kmpl. TATA Marcopolo buses in depot 4 has much lower mileage at
2.2 kmpl, buses seem to be more of fuel guzzlers and also being A/C buses, this is contributing to the
low mileage.
18 http://www.hindustantimes.com/punjab/chandigarh/ctu-needs-to-put-safety-in-the-driver-s-seat/article1-1269381.aspx (Accessed on 06th October, 2014)
1%
8%
91%
Fatal Accidents Major Accidents Minor Accidents
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
September 2015 119
Availability of Statistics with CTU
Most of the data and statistics have been found to be manually maintained in registers which is of a
concern as there are chances of errors in the manual processes. CTU has initiated the usage of MIS
modules for maintaining some of its processes. However, some reports (such as passenger details) are
not readily available from those MIS modules even though the data is present in the back end of the
system.
CTU maintains monthly statistics on overall operations which get prepared at each depot level and are
then compiled for CTU as a whole in the head office. Monthly statistics currently being populated include
the following details at depot and CTU levels:
Expenses and Revenues
Fleet Details
Operated and Dead Km
Fuel Consumption Details
Breakdowns and Accidents
Monthly statistics of each depot are manually prepared and the performance measures are calculated
using calculators. CTU should look into building its capacity and train its people to use computer and
related software for carrying out data analysis tasks.
Financial Characteristics
Financial characteristics of CTU have been analyzed for CTU as a whole and also exclusively for city
bus services in the tri-city area. The major revenue sources of CTU as shown in Exhibit 61 include:
On-board ticket fare revenue
Monthly and Daily Pass revenue
Revenue from advertisements on buses and at bus shelters
ISBT (Rents, advertisements and parking fee, etc.)
On an average CTU operated around 91,000 Km per day in the FY 2013-14, in which city bus
operational kilometers contribute to around 47% (i.e. about 43,000 Km). The daily traffic revenue from
the city bus service is ₹ 9.45 Lakhs which is about 40% of total traffic revenue of CTU. The non-fare
revenue for whole CTU has been found to be 16.9%, while the non-fare revenue for city bus service is
only 2.5% through advertisements. ISBT revenue is major part of non-fare revenue for CTU, amounting
to 13.6% of total revenue. The total yearly revenue from city bus services is found to be Rs. 35.2 Cr in
the FY 2013-14 as shown in Exhibit 90.
Exhibit 84: Revenue Split for both CTU
83.3%
3.1%
13.6%
1 2 3
Total Revenue
ALL BUS OPERATIONS OF CTU
104,30,16,5
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
September 2015 120
Cost of CTU operations include various components such as staff salaries, fuel expenses, spare parts,
taxes, interest, insurances and other overheads. The split of total costs of CTU specific to city bus
operations is shown below in Exhibit 91.
Exhibit 85: Split of Total Costs of CTU Specific to City Bus Operations
Without considering the ISBT revenue for city bus service, there is a huge deficit of revenue when
compared to the costs. CTU has spent around Rs. 91.2 Cr in the FY 2013-14 on city bus services while
the cost of total bus operations of CTU is about Rs. 175.5 Cr. The costs of operations are a concern,
as there is a gap of around Rs. 56 Cr. between revenues and costs per year specific to city bus service.
This kind of situation becomes the threat for financial viability of the public transport service.
It is noted that, the taxes contribute to about 0.2% of total costs whereas the national urban
average is at 1.7%.
Various revenue and cost related parameters have been analyzed for last two financial years
for both CTU level and city bus service level, and the same have been presented in
As seen in the chart, around 75% of total cost is spent on staff salaries and fuel. 8.4% of total
cost is being spent on spare parts, tyres & tubes.
The average salary per staff is around ₹ 16,900.
Fuel expenditure is around 34%. About ₹ 20 /- per Km is being spent for fuel in operating the
city bus.
Earnings per operated Km is observed to be ₹ 22.5 /-, that means about 88% of earnings is
being spent in fuel consumption only.
There is about ₹ 10 /- loss being incurred by CTU in carrying each passenger and ₹ 35.8 /- loss
being incurred in operating each Km of city bus service.
Only 40% of total cost is recovered back and remaining 60% is being subsidized by the other
routes (long routes and suburban) and from the support of Chandigarh Administration.
40.6%
34.1%
7.2%
1.2%
4.8%
0.5%
0.2%0.8%
10.7%
Staff Salary
Fuel (HSD & M.Oil)
Spare Parts
Tyres & Tubes
DRF
Interest
Taxes
MACT
Other Overheads
Total Expenditure FY
2013-14 in INR
CITY BUS OPERATIONS OF CTU
91,20,43,358
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
September 2015 121
PARAMETER Total City Buses Total CTU
Revenue Related Parameters FY2012-13 FY2013-14 FY2012-13 FY2013-14
Daily no. of Passengers (including pass users) 163976 155325 184110 174395
Total Daily Income (Traffic+ Advertisement +
ISBT) 1065694 969147 2957562 2857580
Total ISBT Revenue - - 354031 388273
Share of Non-Fare Revenue 2.9% 2.5% 15.0% 16.7%
Total Daily Kilometers Operated 46,917 42,823 102,243 91,837
Earnings per operated Km 22.7 22.6 28.9 31.1
Earnings per passenger 6.5 6.2 16.1 16.4
Revenue per bus held per day 3600 3353 6266 6253
Revenue per bus operated per day 4021 3924 7179 7180
Revenue per Passenger-Km 0.57 0.54 - -
Cost Related Parameters FY2012-13 FY2013-14 FY2012-13 FY2013-14
Fuel Cost per Liter 60 61 60 61
Fuel Cost 664800 850838 1272225 1588140
Average total cost of operations per day 2563715 2498749 4880107 4808762
Cost per operated Km 54.6 58.4 47.7 52.4
Cost per passenger 15.6 16.1 26.5 27.6
Cost per bus held per day 8661 8646 10339 10522
Cost per bus operated per day 9674 10116 11845 12082
Cost per passenger Km 1.36 1.40 - -
Loss incurred for carrying each passenger 9.1 9.8 10.4 11.2
Loss incurred due to each Km of operation 31.9 35.7 18.8 21.2
Cost Recovery Ratio 42% 39% 61% 59%
Exhibit 86: Financial Characteristics of City Bus Service and overall CTU for financial years
FY20112-13 to FY2013-14
Summary of Baseline Scenario
Base line scenario has been summarized as base line indicators and analysis of SWOT19
Baseline Indicators
Among various aspects and parameters analyzed as part of assessing baseline scenario, few critical
parameters of city bus operations are compared with that of national average of urban STU’s across
India. The summarized base line indicators have been presented in the Exhibit 93. Along with the
parameters for city bus operations, depot wise parameters are also given for reference.
19 SWOT – Strengths, Weaknesses, Opportunities, and Threats
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
September 2015 122
Parameter (FY 2013-14) Depot 2 Depot 4 City Bus
Operations
National Average
(Urban STU's)
Best Value
Best STU
Dead Km (%) 10.2% 0.1% 6.5% 2.4% 0.78% APSRTC Fleet Utilization (%) (No. of buses operated/ no. of buses held) 74% 97% 86% 84.20% 96.20% TNSTC(SLM) Passengers per operated bus per day 537 1016 1775 MTC(CNI) Bus Utilization (Operated Km/operated buses/day) 211 172 173 215 315.3 MTC(CNI) Bus Productivity (Operated Km/ No. of buses held/ day) 155 167 148 181 - - Average Age of the buses held (Years) 8.02 4.39 6.65 - - - No. of Breakdowns per 10,000 operated Km 0.92 1.11 1.00 0.97 0.05 BMTC No. of accidents per 1 Lakh operated Km 0.20 1.38 0.70 0.27 0.07 DTC Load Factor (%) - - 60% 70.30% 72.45% BEST KMPL of Fuel 4.08 2.20 3.05 3.82 5.28 TNSTC(SLM) Average Trip Length of passengers in Km - - 11.5 9.52 5.26 DTC Passenger Km/ operated bus - - 6175 9699 10325 BMTC Total Staff ratio - - 4 7.68 5.68 BMTC Share of Staff cost in Total cost 50% 28% 41% 62% - - Share of Fuel cost in Total cost 27% 43% 34% 30% - - Non- Fare Revenue Share (ISBT Revenue is not included in depots) 4.1% 0.0% 2.5% 8% - - operating Cost Recovery Ratio (Total earnings/Total Cost) 35% 42% 39% 87% - - Earning per Km (EPKM in Rs/Km) 21.2 25.5 22.6 33.86 - - Earning per passenger in Rs. - - 6 7.75 - - Earning per Passenger-Km - - 0.54 - - - Cost per Km - - 58.4 - - -
Exhibit 87: Summary of Baseline Indicators of City Bus Service of CTU
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
April 2015 123
Appendix 2 – Sample MIS Reports
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
April 2015 124
Bus Breakdown Report This report will be used to know the breakdowns in the depot and its details. Data from the AVL and crew masters will be used to generate this MIS report.
Inputs:
ALV data of the bus which has the schedule details, Location, trip number, breakdown time, Kilometers cancelled.
Crew master database from which the drive and conductor details will be used.
From the SOS alerts or incident log database, incident response time will be calculated.
Outcomes:
To study the frequency of breakdowns in the depot.
To schedule the maintenance of buses with frequent breakdowns.
Data:
AVL Data
Crew master
Alerts log
BUS BREAKDOWN REPORT
Report generated on 29/01/2015 , 15:03:52
Report duration 29/01/2015 00:00:00 to 29/01/2015 00:00:00
Depot name
Sl. No Schedule date
Schedule No.
Bus Reg No.
Trip no.
Breakdown time
Incident responded time
Driver no. & name
Conductor no. & name
Kilometers cancelled
1
2
3
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
April 2015 125
Bus Frequency Report This report will be used to know the frequencies of each bus route originating from the depot. With the help of this report, bunching of buses and non availability
of buses during certain periods of the day can be avoided.
Inputs:
ALV data of the bus which has the schedule details.
Form IV or the scheduling matrix which specifies schedule
Outcomes:
Updating form IV
To study the frequency of service
Avoiding of bunching and distributing of schedule through the day.
Data:
AVL Data
Form IV
BUS FREQUENCY REPORT
Report generated on 29/01/2015 , 15:03:52
Report duration 29/01/2015 00:00:00 to 29/01/2015 00:00:00
Depot name
Sl. No Route number Frequency (timing) @ ISBT Frequency (timing) @ Market stop
1
2
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
April 2015 126
3
Bus Stops Skipped Report This report will be used to check the improper stopping of buses. All the bus stops will be geo coded. If the bus is not stopped at the bus stop, an alert will be
raised. Knowing the schedule data, AVL data and from crew details, bus stop skipping can be avoided by alerting the drivers and proper training to the crew.
Inputs:
ALV data of the bus with time stamp and location details.
Form IV or the scheduling matrix to know the schedule details.
Crew master database.
Outcomes:
Stream lining the bus operations.
Building confidence in the commuters when the buses are stopped at stops and follow the schedules.
To alert the crew of their mistakes and avoid repetition of mistake.
Training to crew on the operations and following the rules of the STU.
Data:
AVL Data
Form IV
Crew master database
BUS STOPS SKIPPED REPORT
Report generation date 29/01/2015 , 15:03:52
Report duration 29/01/2015 00:00:00 to 29/01/2015 00:00:00
Depot Name Depot 4
Sl. No Schedule date
Schedule No.
Route no.
Trip no.
Bus reg no. Driver no. & name
Conductor no. & name
Bus stops skipped
Time of stop skipping
1
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
April 2015 127
2
Crew Attendance Report
This report will be used to check the attendance in the depot which includes all staff and crew members. If the depot has an attendance system like biometric
scanner, the data can be stored onto the master database. Same can be used to generate the MIS report.
Inputs:
Crew / staff details from crew master database
Attendance records
Outcomes:
To standardize the leave process
Alert the dispatchers on crew availability before assigning the crew for the vehicle
To streamline the standby crew usage
Data:
Crew master database
Depot attendance records
CREW ATTENDANCE REPORT
Report generated on 29/01/2015 , 15:03:52
Report duration 29/01/2015 00:00:00 to 29/01/2015 00:00:00
Depot name
Sl. No Date Total crew in the depot Total at work On pre approved leave Absent without notice % attendance
1
2
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
April 2015 128
3
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
April 2015 129
Crew Training Report
This report will be used to keep records of trainings given to the staff and crew of the transport agency.
Inputs:
Crew / staff details from crew master database which will also have the training obtained by the crew / staff and its validity (If applicable).
Outcomes:
Provide training for crew members to keep update on the technology
Training schedules for crew
Checking the validity of the trainings and renewal process
Data:
Crew master database
Training schedules
CREW TRAINING REPORT
Report generated on 29/01/2015 , 15:03:52
Report duration 29/01/2015 00:00:00 to 29/01/2015 00:00:00
Depot name Depot 2
Sl. No Crew ID Date of training Course Results Validity of training Comments from evaluator
1
2
3
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
April 2015 130
Driver Duty Performance Report This report will be used to keep records of duty details of each driver / driver-cum-conductor and their performance while on duty.
Inputs:
Crew / staff details from crew master database to know his punctuality in duty
AVL data which gives the driver behaviour like sudden acceleration, harsh breaking, stop skipping
Outcomes:
Schedule adherence report of the driver
Performance in timely departures
Total kms run Vs the scheduled kms
Speed violation reports
Harsh breaking reports
Stop skipping
Data:
Crew master database
AVL data
Alerts
Driver Duty Performance
Report generation date 29/01/2015 , 15:03:52
Report duration 29/01/2015 00:00:00 to 29/01/2015 00:00:00
Depot Name Depot 4
Sl. No Schedule date
Schedule No.
Bus Reg No.
Driver number
Driver name
Timely departure
Total kms run
Bus stops skipped
Speed violation count
Harsh breaking count
1
2
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
April 2015 131
Fleet Utilization Report
This report will be used to keep track of the fleet utilization in the depot. As a summary report, this can be used to check the monthly / weekly / daily percentage
utilization of available buses in the depot. Utilization of buses in terms of effective kms run and optimizing the schedules.
Inputs:
Schedules data can be modified effectively utilizing the available crew and vehicles
Maintenance schedules
Accidents met during the period
AVL data which gives the total kilometer utilization of the fleet in the depot
Outcomes:
Maximum utilization of the fleet with timely maintenance of vehicles and keep bare minimum buses as standby
Refreshing schedules to utilize the available fleet in times of festivals and peak operation periods to provide better service
System can generate the details and sent alerts regarding FC or insurance renewal for buses.
Data:
Fleet availability details
Fleet maintenance schedule
Accident details
Bus details
AVL data
Alerts
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
April 2015 132
FLEET UTILIZATION REPORT
Report generated on 29/01/2015 , 15:03:52
Report duration 29/01/2015 00:00:00 to 29/01/2015 00:00:00
Depot name
Sl. No Date Total fleet in depot
No. of buses utilized
No. of buses in maintenance
No. of buses gone for FC
No. of stand-by buses
No. of buses sent to scrap
1
2
3
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
April 2015 133
Improper Stoppage Report
This report will be used to keep check the driver performance on duty. When buses are not stopped at the bus stops, waiting passengers will lose confidence on the system. Inputs:
Schedule data
AVL data shows the bus route and stops skipped
Crew master data will give details on the crew assigned to the trip / schedule
Outcomes:
Alerting crew on their performance
Streamlining the operations by tracking and minimizing the errors of stop skipping
Data:
Bus details
AVL data
Alerts
Crew master DB
IMPROPER STOPPAGE REPORT
Report generation date 29/01/2015 , 15:03:52
Report duration 29/01/2015 00:00:00 to 29/01/2015 00:00:00
Depot Name Depot 4
Sl. No Schedule date
Schedule No.
Route no.
Trip no. Bus reg no.
Driver no. & name
Conductor no. & name
Previous bus stop
Stoppage distance from
bus stop
Stoppage duration in
seconds
Time of violation
1
2
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
April 2015 134
Maintenance Schedule Report
This report will be used to structure the routine maintenance of the buses. Timely maintenance of the buses will result in fewer breakdowns, lesser cancellations
and improved commuter satisfaction.
Inputs:
Vehicle data which include make, model, odometer reading, maintenance history
Workshop schedule for timely maintenance
Outcomes:
Maintenance schedule alert
Previous maintenance records
Upcoming maintenance
Attention alert to concerned maintenance department
Data:
Bus details
AVL data for odometer
Maintenance details from DB
MAINTENANCE SCHEDULE REPORT
Report generated on 29/01/2015 , 15:03:52
Report duration 29/01/2015 00:00:00 to 29/01/2015 00:00:00
Depot name
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
April 2015 135
Sl. No Date Bus reg. no.
Present Odometer
Maintenance Odometer
Nature of Maintenance
Tentative date for Maintenance
Attention to department
1
2
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
April 2015 136
Out-Shed Deviation Report This report will be used for reporting the deviation from the schedules
Inputs:
AVL data
Depot location / Geo-code
Crew data
Schedule data
Outcomes:
Deviation from the schedule from actual departure can be checked
Crew can be alerted to maintain the schedule starting times while starting the trips
Data:
AVL data for location
Crew details
Schedule data
OUTSHED DEVIATION
Report generated on 29/01/2015 , 15:03:52
Report duration 29/01/2015 00:00:00 to 29/01/2015 00:00:00
Depot name
Sl. No Schedule No. Bus Reg No. Driver no. & name
Conductor no. & name
Schedule start
Actual start Deviation duration (min)
1
2
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
April 2015 137
Pre Trip Inspection Report
This report will be used for maintenance purpose. With pre trip inspections, breakdowns during the trips can be avoided.
Inputs:
Bus details
Crew data
Maintenance engineer schedules
Outcomes:
In case of breakdowns, this report will help in know the history of inspections and maintenances
Data:
Bus details
Crew details
Inspection schedules
PRE TRIP INSPECTION REPORT
Report generated on 29/01/2015 , 15:03:52
Report duration 29/01/2015 00:00:00 to 29/01/2015 00:00:00
Depot name
Sl. No Date Bus reg. no. Driver No. Odometer Name of person who conducted inspection
Name of the crew who reported defect
1
2
3
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
April 2015 138
Schedule Adherence Report This report will provide the schedule adherence details of the drivers.
Inputs:
AVL data for location tracking
Bus details
Crew data to check previous reports for missing the schedules
Schedule information
Outcomes:
Schedule adherence percentage at each stop as per the schedule prescribed
Crew performance evaluation
Reason for delay in arrival at stops
Data:
AVL data
Bus details
Crew details
Report duration 25/01/2015 00:00:00 to 29/01/2015 00:00:00
Depot name
Sl. No Schedule date
Schedule No.
Bus Reg No.
Trip no. Stop name
Schedule time
Actual time Deviation (+ / -)
Driver no. & name
Conductor no. & name
1
2
3
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
April 2015 139
Schedule Summary Report
This report will provide the depot schedule details. Inputs:
AVL data for location tracking and distance travelled
Bus details
Crew data to check previous reports for schedule adherence
Alerts for route violation
Outcomes:
Summary of the entire depot schedules at one place
Total schedules, trips, total scheduled distance, missed / cancelled trips
Route deviation, schedule start / end times if violation alert is raised
Crew performance evaluation
Reason for violations
Data:
Schedule data
AVL data
Bus details
Crew details
Maintenance details (To get info on missed / cancelled trips)
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
April 2015 140
SCHEDULE SUMMARY
Report generated on 29/01/2015 , 15:03:52
Report duration 28/01/2015 00:00:00 to 29/01/2015 00:00:00
Division Name Bangalore Central Division Depot Name Depot 4
Scheduled Actual Extra No. of missed / cancelled schedules
No. of trips Total distance
No. of trips
Travelled distance
No. of trips Travelled distance
TRIPS DETAILS
Trip No. Schedule No.
Driver no. & name
Conductor no. & name
Schedule trip start time
Actual trip start time
Scheduled trip end time
Actual end time
Route violation
Scheduled distance
Actual distance travelled
Reason for violation
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
April 2015 141
Spares Inventory Report
This report will help the depot manager / maintenance engineer to keep track of the usage of spares and its availability.
Inputs:
Workshop inventory checklist to get the details of the spares and parts
Bus make and models to keep spares for all kinds of buses
Maintenance schedules to keep up with the spares availability
Outcomes:
Less delay in repair and maintenance with availability of spares in the depot workshop
With check of the spares inventory, orders can be place to get the parts on time.
Data:
Maintenance details
Spares inventory
SPAREPARTS INVENTORY REPORT
Report generated on 29/01/2015 , 15:03:52
Report duration 29/01/2015 00:00:00 to 29/01/2015 00:00:00
Depot name
Sl. No Date Part ID Nos. Inventory checked on Make Expiry date Checking staff
1
2
3
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
April 2015 142
Speed Violation Report
This report will help in keep track of speed violators and to take corrective measures to curb speed driving by CTU drivers.
Inputs:
AVL data to know the violation locations
Alerts form the system on speed violations
Crew details to check for violation history
Outcomes:
Depot managers to check for frequent violators and to take corrective measures
Training for drivers who are habitual offenders
Data:
AVL data
Alerts from servers
Crew data
SPEED VIOLATION REPORT
Report generated on 29/01/2015 , 15:03:52
Report duration 29/01/2015 00:00:00 to 29/01/2015 00:00:00
Depot name
Sl. No Schedule date Schedule No. Bus Reg No. Driver no. & name Location Latitude Longitude Speed (kmph)
1
2
3
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
April 2015 143
Vehicle Permit Report
This report will help in keep track of renewal of licenses and road permits for the vehicles. Inputs:
Bus details with make, model, insurance and permit details
Outcomes:
Depot managers to check for permit expiries and alert concerned department for renewals
Alerts from the serve on the dates of renewals
Data:
Bus details from the vehicle master DB.
VEHICLE PERMIT REPORT
Report generated on 29/01/2015 , 15:03:52
Report duration 29/01/2015 00:00:00 to 29/01/2015 00:00:00
Depot name
Sl. No Bus reg. no. Fleet ID Permit expiry date Year of manufacture Chassis number Carrying capacity
1
2
3
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
April 2015 144
Scheduled Trips Report
This report provides the summary of the total scheduled trips for a day
Inputs:
Schedule data
Crew data
Maintenance data
Outcomes:
Depot managers to check the overall schedules per day
Higher officers can check schedules of all the depots in one places
Data:
Bus details from the vehicle master DB.
Schedule data
Crew data
SCHEDULED TRIPS REPORT
Report generated on 29/01/2015 , 15:03:52
Report duration 29/01/2015 00:00:00 to 29/01/2015 00:00:00
Depot name
Date Total fleet Utilized fleet Under maintenance Total schedules Cancelled schedules Total kms
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
April 2015 145
Missed Trips Report
This report provides the summary of the missed trips in the depot
Inputs:
Schedule data
Crew data
Maintenance data
Outcomes:
Depot managers to check the details of cancelled / missed trips
Data:
Bus details from the vehicle master DB.
Schedule data
Fleet maintenance schedule data
Crew data
MISSED TRIPS REPORT
Report generated on 29/01/2015 , 15:03:52
Report duration 29/01/2015 00:00:00 to 29/01/2015 00:00:00
Depot name
Date Schedule No. Class of vehicle Crew number Cancelled trip no. Reason for cancellation
Total kms cancelled
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
April 2015 146
Vehicle Trip Revenue Report
This report provides the summary of the missed trips in the depot.
Inputs:
Schedule data
Crew data
Revenue
Outcomes:
Trip-wise revenue consolidated report
Data:
Bus details from the vehicle master DB.
Schedule data
Fleet maintenance schedule data
Crew data
VEHICLE TRIP REVENUE REPORT
Report generated on 29/01/2015 , 15:03:52
Report duration 29/01/2015 00:00:00 to 29/01/2015 00:00:00
Depot name
Date
Schedule number
Trip number
Conductor No. & name
Total revenue
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
April 2015 147
Vehicle Distance Travelled Report
This report provides the summary of the missed trips in the depot.
Inputs:
Schedule data
Crew data
Outcomes:
Provides the summary of vehicle travel history
Data:
Bus details from the vehicle master DB.
Schedule data
Fleet maintenance schedule data
Crew data
VEHICLE DISTANCE TRAVELLED REPORT
Report generated on 29/01/2015 , 15:03:52
Report duration 29/01/2015 00:00:00 to 29/01/2015 00:00:00
Division name Depot name
Vehicle Reg no. Total kms Class of vehicle
Last maintenance date Next scheduled maintenance Average KMPL
Date Schedule no. Trip no. Driver no. & name Scheduled distance Travelled distance Remarks
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
April 2015 148
Accident Analysis Report
This report provides the summary of the missed trips in the depot
Inputs:
Schedule data
Crew data
Accident data
Outcomes:
Provides the summary of vehicle travel history
Data:
Bus details from the vehicle master DB.
Schedule data
Crew data
Accident data
Incident response details
ACCIDENT ANALYSIS REPORT
Report generated on 29/01/2015 , 15:03:52
Report duration 29/01/2015 00:00:00 to 29/01/2015 00:00:00
Depot name
Date Vehicle reg no. Schedule no Driver no. & name Location Accident time Response time Injured Fatal
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
April 2015 149
Consolidated GPS Report
This report provides the summary of the missed trips in the depot
Inputs:
Vehicle details
VMU unit details
Outcomes:
Provides the summary of GPS tracking history
Data:
Bus details from the vehicle master DB.
Schedule data
VMU data
ACCIDENT ANALYSIS REPORT
Report generated on 29/09/2014 , 15:03:52
Report duration 25/09/2014 00:00:00 to 29/09/2014 00:00:00
Depot name
Date Vehicle reg no. Vehicle class VMU ID SIM number Schedule no. Scheduled packets Actual packets % availability
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
April 2015 150
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
April 2015 151
Appendix 3 – Detailed ITS Costing
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
April 2015 152
Item Code Component Location Subsystems / Items
Quantity exclusive of
spares/ consumables
Installed Unit cost (INR)
Total Installed Cost (INR)
Total Cost including
Spares (INR)
1.1 Fare Collection System (FCS)
FCS Software
FCS
TMC
FCS Central System Software inclusive of but not limited to:
FCS Database application (Primary Server + DR Server)
1 ₹ 15,00,000 ₹ 15,00,000 ₹ 15,00,000
FCS
FCS application software (Primary Server + DR Server)
FCS Anti-virus software (Primary Server + DR Server)
FCS Automatic Back-up\ archiving software
FCS
Any other COTS software (Primary Server + DR Server)
FCS Hardware
FCS FCS Central System Hardware inclusive of but not limited to:
FCS Primary Server 1 ₹ 5,00,000 ₹ 5,00,000 ₹ 5,00,000
FCS DR Server 1 ₹ 5,00,000 ₹ 5,00,000 ₹ 5,00,000
FCS Automatic Back-up devices with media 1 ₹ 2,25,000 ₹ 2,25,000 ₹ 2,25,000
FCS KVM Switch with LCD Monitor 1 ₹ 10,000 ₹ 10,000 ₹ 10,000
FCS
Server Rack (includes rack requirements for all systems)
1 ₹ 36,000 ₹ 36,000 ₹ 36,000
FCS Network All-in-one-printer 4 ₹ 40,000 ₹ 1,60,000 ₹ 1,60,000
SC Hardware
FCS Smart Card Issuance Work-Station POS (16 E-Sampark – Only in Chandigarh) inclusive of but not limited to all software and hardware related to:
FCS POS
Camera 24 ₹ 2,000 ₹ 48,000 ₹ 48,000
FCS Document scanner 24 ₹ 10,000 ₹ 2,40,000 ₹ 2,40,000
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
April 2015 153
FCS Smart card revaluing device 24 ₹ 6,000 ₹ 1,44,000 ₹ 1,44,000
FCS Workstation 24 ₹ 70,000 ₹ 16,80,000 ₹ 16,80,000
FCS Handheld ticketing machine inclusive of but not limited to:
FCS Field
Equipment / Depots
Handheld ticketing machine inclusive of all related accessories, software to meet the requirements
1283 ₹ 25,000 ₹ 320,75,000 ₹ 320,75,000
FCS
3G/GPRS enabled SIM Cards 1283 ₹ 25 ₹ 32,075 ₹ 32,075
FCS
TMC
Smart Card Personalization
FCS Smart Card Personalization Printer 3 ₹ 1,20,000 ₹ 3,60,000 ₹ 3,60,000
FCS Camera 3 ₹ 2,000 ₹ 6,000 ₹ 6,000
FCS Document scanner 3 ₹ 10,000 ₹ 30,000 ₹ 30,000
FCS Workstation 3 ₹ 70,000 ₹ 2,10,000 ₹ 2,10,000
FCS
Handheld ticketing machine inclusive of all related accessories, software to meet the requirements (for CTU Auditors)
15 ₹ 35,000 ₹ 5,25,000 ₹ 5,25,000
FCS
Central Control Centre Operator Work-station for FCS
FCS FCS Cash-up workstations 2 ₹ 70,000 ₹ 1,40,000 ₹ 1,40,000
FCS Fare media - Smart Cards 1,00,000 ₹ 35 ₹ 35,00,000 ₹ 35,00,000
1.2 Automatic Vehicle Location System (AVL)
CS Software AVLS AVL System Software inclusive of but not limited to
AVLS RDBMS Database
1 ₹ 200,00,000 ₹ 200,00,000 ₹ 200,00,000 AVLS AVL Central Application software
AVLS Automatic Back-up/ Archiving software
CS Hardware AVLS AVL Hardware inclusive of but not limited to
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
April 2015 154
AVLS AVL Server 2 ₹ 5,00,000 ₹ 10,00,000 ₹ 10,00,000
AVLS Database Server 2 ₹ 5,00,000 ₹ 10,00,000 ₹ 10,00,000
AVLS Tape Drive 1 ₹ 2,25,000 ₹ 2,25,000 ₹ 2,25,000
AVLS Tape Data Cartridges 30 ₹ 2,000 ₹ 60,000 ₹ 60,000
AVLS Communication Server 2 ₹ 5,00,000 ₹ 10,00,000 ₹ 10,00,000
AVLS Web Server 2 ₹ 5,00,000 ₹ 10,00,000 ₹ 10,00,000
AVLS Domain Server 1 ₹ 4,00,000 ₹ 4,00,000 ₹ 4,00,000
AVLS 3G/GPRS enabled SIM Cards 513 ₹ 25 ₹ 12,825 ₹ 12,825
AVLS AVL Workstation
AVLS AVL Dispatcher Workstation with Dual Monitor and necessary accessories
8 ₹ 90,000 ₹ 7,20,000 ₹ 7,20,000
AVLS EPABX 1 ₹ 1,20,000 ₹ 1,20,000 ₹ 1,20,000
AVLS Landline Phones 8 ₹ 1,200 ₹ 9,600 ₹ 9,600
AVLS Hands free/ Headphone 8 ₹ 1,200 ₹ 9,600 ₹ 9,600
AVLS Printers
AVLS All in One Printer (Color Print, Copy, FAX) 1 ₹ 80,000 ₹ 80,000 ₹ 80,000
AVLS LaserJet Printer 2 ₹ 11,000 ₹ 22,000 ₹ 22,000
AVLS KVM Switch with LCD Monitor 2 ₹ 10,000 ₹ 20,000 ₹ 20,000
OB Hardware AVLS
OBITS Hardware as per UBS II
AVLS Single Control Unit and Bus Driver Console 134 ₹ 1,25,000 ₹ 167,50,000 ₹ 167,50,000
AVLS Side Destination Boards 204 ₹ 23,000 ₹ 46,92,000 ₹ 46,92,000
AVLS Front Destination Boards 34 ₹ 35,000 ₹ 11,90,000 ₹ 11,90,000
AVLS Inner Destination boards 34 ₹ 23,000 ₹ 7,82,000 ₹ 7,82,000
DR Site AVLS Disaster Recovery Service
AVLS Disaster Recovery Service for Complete AVL system (includes FCS)
1 ₹ 25,00,000 ₹ 25,00,000 ₹ 25,00,000
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
April 2015 155
1.3 Passenger Information System (PIS)
PIS
PIS Customized or COTS Software for PIS 1 ₹ 20,00,000 ₹ 20,00,000 ₹ 20,00,000
PIS Commuter Website 1 ₹ 3,00,000 ₹ 3,00,000 ₹ 3,00,000
PIS Commuter IVR System 1 ₹ 3,00,000 ₹ 3,00,000 ₹ 3,00,000
PIS Commuter SMS System 1 ₹ 4,00,000 ₹ 4,00,000 ₹ 4,00,000
PIS Commuter Mobile Application 1 ₹ 5,00,000 ₹ 5,00,000 ₹ 5,00,000
PIS 17" LED Passenger Information Display at Bus Stops across City
22 ₹ 25,000 ₹ 5,50,000 ₹ 5,50,000
PIS 32" size of Passenger Information Display at ISBT's, etc.
8 ₹ 1,20,000 ₹ 9,60,000 ₹ 9,60,000
1.5 Transit Management System (TMS)
TMS
TMS TMS Central Application software including Scheduling & Rostering
1 ₹ 250,00,000 ₹ 250,00,000 ₹ 250,00,000
TMS TMS Application software for workstation 50
TMS TMS Server (Primary & Secondary) 2 ₹ 5,00,000 ₹ 10,00,000 ₹ 10,00,000
TMS Workstation for TMS with 17" LCD monitor and other accessories
40 ₹ 50,000 ₹ 20,00,000 ₹ 20,00,000
TMS Workstation for monitoring Video/Image with 17" LCD monitor and other accessories
2 ₹ 50,000 ₹ 1,00,000 ₹ 1,00,000
TMS Printer and Scanner for TMS workstation at Depot 4 ₹ 11,000 ₹ 44,000 ₹ 44,000
TMS 55" size of Passenger Information Display at Depot 6 ₹ 1,20,000 ₹ 7,20,000 ₹ 7,20,000
TMS Cameras 4 ₹ 10,000 ₹ 40,000 ₹ 40,000
TMS Proximity Reader 4 ₹ 6,000 ₹ 24,000 ₹ 24,000
TMS Proximity cards for staffs 2500 ₹ 25 ₹ 62,500 ₹ 62,500
TMS In-bus cameras 134 ₹ 3,000 ₹ 4,02,000 ₹ 4,02,000
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
April 2015 156
TMS In-bus NVRs for camera recording 134 ₹ 10,000 ₹ 13,40,000 ₹ 13,40,000
1.6 Transit Management Centre (TMC)
TMC
TMC Video Wall 1 x 70" 1 ₹ 50,00,000 ₹ 50,00,000 ₹ 50,00,000
TMC Data Archiving Software 1 ₹ 5,00,000 ₹ 5,00,000 ₹ 5,00,000
TMC Tape Drive Cartridges 30 ₹ 2,000 ₹ 60,000 ₹ 60,000
1.7 Communication System (COMM)
COMM
COMM Data Center - Network Components and LAN 1 ₹ 5,00,000 ₹ 5,00,000 ₹ 5,00,000
COMM TMC Data center (Data & Internet) 1 ₹ 80,000 ₹ 80,000 ₹ 80,000
COMM TMC Data center - Redundancy 1 ₹ 80,000 ₹ 80,000 ₹ 80,000
COMM Primary to DR Site 1 ₹ 80,000 ₹ 80,000 ₹ 80,000
COMM Depot (Broadband for 10 workstation) 5 ₹ 5,000 ₹ 25,000 ₹ 25,000
COMM PIS Display (Dongle/Broadband) 30 ₹ 2,500 ₹ 75,000 ₹ 75,000
COMM IVRS (Switching device) 1 ₹ 10,000 ₹ 10,000 ₹ 10,000
COMM SMS (Modem) 1 ₹ 25,000 ₹ 25,000 ₹ 25,000
₹ 1356,91,600 ₹ 1356,91,600
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
April 2015 157
Appendix 4 – List of Existing Buses to be Fitted with AVL Units, Destination Boards & Cameras
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
April 2015 158
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
April 2015 159
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
April 2015 160
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
April 2015 161
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
April 2015 162
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
April 2015 163
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
April 2015 164
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
April 2015 165
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
April 2015 166
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
April 2015 167
Appendix 5 – DEVICE SPECIFICATIONS
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
April 2015 168
Electronic Ticketing Machine Specification: Features:
LCD Display
Li-ion Battery
Smart cards
Minimum 30 keys
RS232 port & USB
Expected to use minimum 8 hrs without intermediate charging
Auto power off (as set time) Technical Specification:
PROCESSOR 32 BIT
Memory Capacity Minimum Flash 8MB
Shall store minimum of 500 routes and 5000 tickets
Minimum 5000 smartcard list
Display LCD with minimum of 60mm x 30mm size
Keyboard Minimum 30 keys
Printer 2” Thermal printer. Prints >55mm/second
Magnetic card reader ISO 14443 Type A or Type B
Battery 2500mAh Li-ion battery
Shall be charged <3.5 hrs
Communication Port Each one number RS232 and USB
Width <500gms
Environment Operation temperature: -10C – 50C
storage temperature: -20C – 70C
Humidity: 5% - 95% non-condensing
Certifications CE
Workstation – Type1 (Medium configuration) Specification: Operating System: Windows 7 professional 64 bit
Antivirus: Antivirus and Internet spy ware software
Processor: core i3/i5, 4th Generation (2.8 GHz, 2MB cache)
Memory: minimum 8 GB or higher
Internal Storage: 500 GB SATA
Internal Drive: CD/ DVD RW
Networking: Integrated 10/100/1000 MB
Communication port: RJ45, 2 PS/2, Serial port and 4 USB port
Audio: Integrated (1 headset & 1 microphone)
Form factor: Tower
LCD: 19” IPS LCD shall support minimum resolution of 1600 x 900 and keyboard & mouse.
Workstation – Type2 (High configuration) Specification:
Operating System: Windows 7 professional 64 bit
Antivirus: Antivirus and Internet spy ware software
Processor: core i7, 4th Generation (3.0 GHz, 2MB cache)
Memory: minimum 16 GB
Internal Storage: 500 GB SATA and expandable up to 2 TB
Graphics card: NVIDIA 315 (1 GB)
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
April 2015 169
Internal Drive: CD/ DVD RW
Networking: Integrated 10/100/1000 MB
Communication port: RJ45, 2 PS/2, Serial port and 4 USB port
Audio: Integrated (1 headset & 1 microphone)
Form factor: Tower
LCD: 19” IPS LCD shall support minimum resolution of 1600 x 900 and keyboard & mouse.
Server Specification: Operating System: Windows 2008 server edition 64 bit
Antivirus: Antivirus and Internet spy ware software
Processor: XEON E5 (2.6 GHz, 25MB cache, 10 Cores). Processor expandable up to 2.
Memory: minimum 16 GB DDR4 and expandable up to 64 GB
Internal Storage: 1 TB SATA and expandable up to 2 TB. RAID support.
Graphics card: NVIDIA 315 (1 GB)
Internal Drive: CD/ DVD RW
Networking: Integrated 10/100/1000 MB
Communication port: 2 RJ45 to integrated Gigabit LAN , 2 PS/2, 1 Serial and 4 USB
Audio: Integrated (1 headset & 1 microphone)
Form factor: Rack mounted
LCD: 19” IPS LCD shall support minimum resolution of 1600 x 900 and keyboard & mouse.
Passenger Information System – LCD Display Specification: Display format: Static, Pagination or scrolling
Display content: Real time information of bus location, Advertisement, Alert message, Current time,
News, weather, etc.,
Visibility of display: The signs shall be legible when sunlight is shining directly on the display face or
when the sun is directly behind the display.
Environment: The PIS display board shall be industrial grade flat panels that can withstand the
environment.
Type of content: Text, Video, Image, Audio, Animations and Graphics files
Language Support: English, Hindi and local language.
Remote Monitoring: The display system shall support remote settings such as display intensity,
display off, and time synchronization. PIS shall be managed locally without server or workstation.
Readability: Characters shall be at least 12 cm high to allow for a viewing distance of 30 metres.
Safety: The sign enclosures shall be vandal proof.
Passenger Information System – LED Display Specification: Display format: Static, Pagination or scrolling
Display content: Real time information of bus location, Alert message, Current time,
Viewing angle: Minimum 150°V – 60°H
Viewing distance: 3 -30 mtr
Environment:
IBI CONSULTANCY INDIA PRIVATE LIMITED FINAL TECHNICAL REPORT
DETAILED PROJECT REPORT FOR ITS FOR CITY BUS OPERATIONS OF CTU
Prepared for Chandigarh Transport Undertaking (CTU)
April 2015 170
o Temperature: 0 to +55 deg C
o Thermal cycling: 5 Deg C/mt
o Vibration: 2 g
o Sealing: IP 65
o Humidity: 90% RH
o Drop : 1 mt on all faces
Type of content: Text and Numeric
Minimum life of the display system: 50,000 hrs
Language Support: English, Hindi and local language.
Remote Monitoring: The display system shall support remote settings such as display off,LED failure
and time synchronization.
Readability: Characters shall be at least 10 cm high to allow for a viewing distance of 30 metres.
Safety: The sign enclosures shall be vandal proof.
Smart cards Specification: Smart card Type: Smart cards shall adhere to applicable and generally adopted industry standards
including ISO 14443 Type A or Type B.
Physical Standard: The cards shall be in accordance with ISO 7810 ID-1
Durability: Smart cards shall be durable for at least 5 years physical life under regular usage
conditions with 100,000 write.
Memory: At least 4K memory
Reading Range: The cards shall be contactless having an operating range of 0cm to 3 cm.
Identification number: The card serial number shall be embossed/ printed on the face or back of the
card to support customer inquiries.
Pre-printed: All the cards shall be pre-printed with logo.