Zhen Hau Sing - Feasibility & Treatability Study

download Zhen Hau Sing - Feasibility & Treatability Study

of 59

Transcript of Zhen Hau Sing - Feasibility & Treatability Study

  • 8/13/2019 Zhen Hau Sing - Feasibility & Treatability Study

    1/59

    CIE 449 Environmental Engineering DesignTask 4: Feasibility Study

    Submitted to:

    Martin Doster207 Jarvis Hall

    University at Buffalo

    Prepared By:

    Michael DietrichMubeccel Begum Ilya

    Zhen Hau Sing

    April 23, 2013

  • 8/13/2019 Zhen Hau Sing - Feasibility & Treatability Study

    2/59

    - This Page Intentionally Left Blank

  • 8/13/2019 Zhen Hau Sing - Feasibility & Treatability Study

    3/59

  • 8/13/2019 Zhen Hau Sing - Feasibility & Treatability Study

    4/59

    2-3

    5.3.4 Implementability of Phytoremediation and Cost Estimatation ........................... ........ 5-8

    5.3.5 Issues of Phytoremediation ....................... .......................... ......................... ........... 5-10

    5.3.6 Phytoremediation Remarks........................ .......................... ......................... ........... 5-10

    5.4 Permeable Reactive Barrier ........................... ......................... .......................... ............... 5-10

    5.4.1 Description ........................... ......................... .......................... ......................... ....... 5-10

    5.4.2 Performance ......................... ......................... .......................... ......................... ....... 5-11

    5.4.3 Cost Analysis ......................... ......................... .......................... ......................... ....... 5-12

    5.4.4 Removal Efficiencies of Materials............................ .......................... ....................... 5-12

    5.4.5 Important Installation Guidelines ....................... .......................... .......................... .. 5-14

    5.5 River Sediment Dredging .......................... .......................... ......................... .................... 5-14

    5.5.1 Description ........................... ......................... .......................... ......................... ....... 5-14

    5.5.2 Cost Estimation................................ ........................... ......................... .................... 5-15

    5.5.3 Preventing the environmental impacts ....................... ......................... .................... 5-16

    6 Effectiveness, Implementability, and Cost .......................... .......................... ......................... 6-1

    7 Possible Remedial Combinations ........................... .......................... ......................... ............. 7-1

    7.1 On Site ........................... .......................... .......................... ......................... ...................... 7-1

    7.1.1 ISCO, Cap, Pump and treat ......................... .......................... ......................... ............. 7-1

    7.2 River Sedimentation ........................ .......................... ......................... ........................... .... 7-3

    7.2.1 Hydraulic Lock with material such as organoclay .......................... .......................... .... 7-3

    7.2.2 Description ........................... ......................... .......................... ......................... ......... 7-3

    7.2.3 Comparison of Alternative to Evaluation Criteria ......................... .......................... .... 7-3

    8 Proposed Remedies ......................... ......................... .......................... ......................... ......... 8-4

    8.1 Remedy 1: No Action ....................... .......................... ......................... ........................... .... 8-2

    8.1.1 Description ........................... ......................... .......................... ......................... ......... 8-2

    8.1.2 Comparison of Alternative to Evaluation Criteria ......................... .......................... .... 8-2

    8.2 Remedy 2: Combination ........................... .......................... ......................... ...................... 8-5

    8.2.1 Description ........................... ......................... .......................... ......................... ......... 8-5

    8.2.2 Comparison of Alternative to Evaluation Criteria ......................... .......................... .... 8-6

    9 Ecological Habitat............................. ......................... .......................... ......................... ....... 9-10

    9.1 Buffalo Color Company Site ........................... ......................... .......................... ............... 9-10

    9.2 Buffalo River........................ .......................... ......................... .......................... ............... 9-10

    Corruptions that have been identified:.......................... .......................... .......................... ........ 9-2

    10 Community Relations Before, During, and After Treatment .......................... ....................... 10-3

    11 Credits ....................... ......................... .......................... ......................... ........................... .. 11-1

    12 References ......................... .......................... .......................... ......................... .................... 12-2

  • 8/13/2019 Zhen Hau Sing - Feasibility & Treatability Study

    5/59

    2-4

    1.1 List of FiguresFigure 1: Area of concern, including flow directions ................................................................................................. 3-2Figure 2: Buffalo River Contamination near Site C and E. ....................................................................................... 4-2Figure 3: Discovered Contamination Locations ........................................................................................................ 4-2Figure 4: Buffalo Color Site C and E, with contamination target zones. Contour lines shown are distance to clay

    layer under ground surface in feet. ................................................................................................................................... 5-1Figure 5: Plan view of implementation of phytoremediation on site C and E. Plant species were selected based

    on COCs within that area (labeled pink or red). ............................................................................................................... 5-9Figure 6: Post PRB installation Capture Zone ........................................................................................................ 5-13Figure 7: Cost Estimation for the dredging ............................................................................................................. 5-16Figure 8: Scheme showing that the steps of the environmental impact assessment ........................................... 5-17Figure 9: Excavation Areas ........................................................................................................................................ 8-6

    Figure 10: Phytoremediation and PRB installation locations ................................................................................... 8-6Figure 11: Observed disorders .................................................................................................................................. 9-2Figure 12: Example Citizen Guidances (EPA, 2012) ............................................................................................. 10-5

    1.2 List of TablesTable 1: Primary chemicals of concern detections and limits based on NYSDEC ................................................. 4-4Table 2: Secondary chemicals of concern detections and limits based on NYSDEC ............................................ 4-5Table 3: Factors That Affect Enhanced In-Situ Bioremediation. Source: www.clu-in.org/bioremediation/ ........... 5-4Table 5: Summary of results from bench scale and treatability tests. Note : A) removal result was similar to the

    control without the plant, proving that plant was not responsible for contaminant removal. ......................................... 5-7Table 6: Screening of Remedial Technologies for Groundwater at Buffalo Color Corp. Sites C and E................ 6-1

    Table 7: Screening of Remedial Technologies for Soil at Buffalo Color Corp. Sites C and E. .............................. 6-2Table 8:Screening of Remedial Technologies for Vapor at Buffalo Color Corp. Sites C and E. ........................... 6-3Table 9: Screening of Remedial Technologies for River Sediments in the Buffalo River. ..................................... 6-4

  • 8/13/2019 Zhen Hau Sing - Feasibility & Treatability Study

    6/59

    2-5

    1.3 List of AcronymsARAR Applicable or Relevant and Appropriate Requirements

    BCCBuffalo Color Corporation

    COCContaminants of Concern

    DNAPLDense Non-Aqueous Phase Liquid

    EISB Enhanced in-situ Bioremediation

    EPAEnvironmental Protection Agency

    ISCOIn-Situ Chemical Oxidation

    NYSDECNew York State Department of Environmental Conservation

    PAH Polycyclic Aromatic Hydrocarbon

    PIDPhoto-Ionization DetectorPRB Permeable Reactive Barrier

    RACER Remedial Action Cost Engineering Requirements

    SCGStandard, Criteria and Guidance

    SVOC- Semi Volatile Organic Compound

    SWMU Solid Waste Management Unit

    TCETri-ChloroEthylene

    VOC Volatile Organic Compound

  • 8/13/2019 Zhen Hau Sing - Feasibility & Treatability Study

    7/59

    2-6

    2 EXECUTIVE SUMMARYThis Feasibility study report provides a detailed analysis of two remedial alternatives for the

    BCC site; the no action alternative and the combined remedy. Both alternatives were evaluated with

    the nine feasibility criteria set forth by EPA.

    The no action alternative was essentially used to evaluate the overall adverse human health and

    the environmental effects of the contamination. By taking no action, the COCs will potentially be

    exposed to humans and animals through ingestion and inhalation routes. Contaminated

    groundwater will also migrate and transport the COCs to the Buffalo River, harming the benthic

    community in the sediments and the quality of water.

    The combined remedy consist of treatments for each media; excavation for highly contaminated

    soil, a PRB for groundwater, phytoremediation for moderately contaminated soil and groundwater

    and a passive and active mitigation for vapor intrusion into buildings upon future

    industrial/commercial development.

    The total cost of the remediation (excluding vapor installation in buildings) was projected to be

    $7.5 million. This cost includes the technology preparations and O&M of the whole site. The remedy

    has a proposed reduction efficiency of over 99% for groundwater leaving the site and river

    sediment remediation. After removal of concentrations on site over ten times the limit, expected

    efficiency of phytoremediation is 70-80%.

    The combined remedy was developed upon preliminary screening of technologies by media and

    also various combinations of technologies. All of these technologies were evaluated using the nine

    feasibility criteria mentioned. It is important to note that chemical oxidation and in-situ

    bioremediation technologies were analyzed with more detail in the treatability studies but were not

    chosen. The high organic content of the BCC site greatly increases the cost of chemical oxidation

    while bio-remediation was not compatible with the PRB that was more effective in treating

    groundwater.

  • 8/13/2019 Zhen Hau Sing - Feasibility & Treatability Study

    8/59

    3-1

    3 Site Background3.1 Main site:

    The main area of concern is a 23 Acre area in Buffalo, NY south of Elk Street

    between the rail road tracks and west of Orlando St. The site is broken two parts, site C to

    the west of Lee St, and site E to the east.

    Based on the Sandborn maps, the site began in the late 19 thcentury when Genesee

    oil works created an oil processing plant in the southeast portion of site E. By the 20 th

    century nearly the entire area was used as a lumber storage yard. This use has contributed

    to the high organic content of the soils due to waste sawdust mixing into the soil as part of

    the fill. In the early 1900s, an aniline plant was built on site C, and then during the 1940s

    the dye manufacturing plant was built on the west half of site E. These tw o plants are

    where hazardous compounds, such as acids, heavy metals, and benzene derivatives were

    used (Baptista, 2009).

    In this production, the wastes were typically stored in two ways: barrels in the

    central part of site E,and dumped into lagoons in the eastern part of site E. These lagoons

    themselves have been previously remediated and are no longer a concern. The barrel

    storage area is where significant heavy metal and PAH contamination has been found.

    Chemicals for production analine and various chlorinated organics used for dye

    production were stored in tanks on the south western section of site E, and it is here that

    significant chlorobenzene concentrations have been found.

  • 8/13/2019 Zhen Hau Sing - Feasibility & Treatability Study

    9/59

    3-2

    Today, all of the buildings in site E have been demolished except for a small

    warehouse, and the only remaining buildings on site C is the original boiler and ice plants

    which did not process the chemicals themselves.

    3.2 Surrounding Area:To the north there is a Honeywell research laboratory that was built in 1955 and

    deals primarily in fluorine based chemicals (Honeywell International, 2011). To the south

    is site B of Buffalo Color, and to the southeast is a PVS Chemical plant that has produced

    nitric and sulfuric acids, which also involved use of some heavy metals from 1930-1977

    (Engineering-Science, 1986). To the southeast is an Exxon-Mobile petroleum plant.

    As for a residential area, there were houses on the eastern portion of site E through

    the 1940s when they were demolished. Now the residential are exists to the northwest of

    site E. The current map of the area is shown inFigure 1.

    Figure 1: Area of concern, including flow directions

  • 8/13/2019 Zhen Hau Sing - Feasibility & Treatability Study

    10/59

    4-3

    4 Remedial Objectives4.1 The Problem

    The issues being addressed at sites C and E is contamination that exists in the soil,

    groundwater, vapor and also sediments in the Buffalo River to allow the site to be used for

    commercial or industrial purposes.

    Based on Triodis analysis, metals arsenic and mercury, VOCs chlorobenzene and

    dichlorobenzene, SVOCs benzo(A)anthracene, benzo(A)pyrene and benzo(B)fluorentine

    (PAHs) are of most concern at this site. Their existence in the soil and groundwater pose

    severe potential health hazards that include carcinogenic and non-carcinogenic toxicities,

    making it necessary to remove them. Details of these affects are listed in the Chemical of

    Concern chapter.

    Site workers or people in general who come in contact with the ground face potential

    ingestion of the contaminated soil. The volatilization of VOCs will contaminate the

    atmosphere around the site, which is potentially hazardous to people exposed on site and

    also neighboring residential areas if blown by wind. For groundwater, the flow into the

    sewers and the Buffalo River will carry contaminants that eventually settle into the

    sediments. This affects the water quality and pose potential health issues for the marine

    wildlife in the river.

    Groundwater has a specific problem of several sewer lines throughout the site creating

    very high conductivity pathways of contaminates to the Buffalo River. These pipelines may

    also be damaged allowing leakage in/out of the aquifer. Figure 2 shows the mercury and

    PAH (as shown by a specific compound, Benzo(a)Anthracene) contamination.

  • 8/13/2019 Zhen Hau Sing - Feasibility & Treatability Study

    11/59

    4-2

    Contamination spikes immediately at the Buffalo Color outfall, and continues to be an issue

    for 0.7 miles, at which indications of another contamination source other than sites C and

    E is evident.Mercury is a particular concern in the river due to bioaccumulation.

    Figure 2: Buffalo River Contamination near Site C and E.

    Figure 3: Discovered Contamination Locations

    Ideally, the contaminant concentrations should be decreased to the target levels set by

    NYSDEC, which is covered in the Remedial Action Objectives chapter. However, if

    treatability studies suggest a steep cost for remediation, containment and immobilization

  • 8/13/2019 Zhen Hau Sing - Feasibility & Treatability Study

    12/59

    4-3

    of the chemicals are viable options as well. The ultimate goal is to either remove the

    chemicals or avoid them from being exposed and have contact with humans and animals.

    The viable options will be proposed after a treatability study of the site is done.

    4.2 Remedial Action Objectives4.2.1 Soil:

    For Human Health:

    Preventing the ingestion/direct contact with soil having non-carcinogens in excessof reference doses.

    Preventing the direct contact/ingestion with soil having 10-4 to 10-7 excess cancerrisk from carcinogens.

    Preventing the inhalation of carcinogens posing excess risk levels of 10-4 to 10-7.For Environment Protection:

    Preventing the migration of contaminants that would result in groundwatercontamination in excess concentrations for contaminants.

    4.2.2 Groundwater:For Human Health:

    Preventing the ingestion of water having carcinogens in excess of MCLs and a totalexcess cancer risk for all contaminants of greater than 10-4 to 10-7.

    Preventing the ingestion of water having non-carcinogens in excess of MCLs orreference doses.

    For Environment Protection:

    Restoring the ground water aquifer to concentrations for contaminants.

  • 8/13/2019 Zhen Hau Sing - Feasibility & Treatability Study

    13/59

    4-4

    4.2.3 Sediments:For Human Health:

    Prevent direct contact with sediment having carcinogens in excess of 10 -4 to 10-7excess cancer risk.

    For Environmental Protection:

    Prevent releases of contaminants from sediments that would result in surfacewater levels in excess of ambient water quality criteria.

    4.2.4 Air:For Human Health:

    Prevent inhalation of carcinogens in excess of 10 -4 to 10-7 excess cancer risk.Chemicals Of Concern: (NYSDEC, 2013)Primarily Concern Chemicals

    Category ofContaminant Type of Contaminant Location

    Mean detectedconcentration

    Limit forcommercial set

    by NYSDEC

    HeavyMetal

    Arsenic Soil 98.4mg/kg

    16 mg/kg

    Groundwater 352 g/L 25 g/L

    Mercury Soil 9.6mg/kg

    2.8 mg/kg

    Groundwater 4 g/L 0.7 g/L

    SVOC Benzo(A)Anthracene Soil 155mg/kg

    5.6 mg/kg

    Benzo(A)Pyrene Soil 66.2mg/kg 1.0 mg/kg

    Benzo(B)Fluoranthene Soil 111.6mg/kg

    5.6 mg/kg

    VOC Chlorobenzene Groundwater 6913g/L

    5 g/L

    Dichlorobenzene Groundwater 39.7 g/L 3 g/L

    Table 1: Primary chemicals of concern detections and limits based on NYSDEC

  • 8/13/2019 Zhen Hau Sing - Feasibility & Treatability Study

    14/59

    4-5

    Other Detected ChemicalsType of contaminant Location Mean

    DetectedConcentration

    Limit forcommercial set byNYSDEC

    Naphthalene Groundwater 65g/La 10 g/L1,1,2-

    TrichlorotrifluoroethaneGroundwater 9.3 g/La 5g/L

    1,2,4-Trichlorobenzene Groundwater 440 g/La 5 g/L

    Benzene Groundwater 600 g/La 1 g/L

    Lead Soil 500mg/kg

    1000 mg/kg

    Chrysene Soil 73 mg/kg 56 mg/kg

    Fluoranthene Soil 142mg/kg

    500 mg/kg

    Naphthalene Soil 53 mg/kg 500 mg/kg

    Phenantrene Soil 232mg/kg

    500 mg/kg

    Pyrene Soil 120mg/kg

    500 mg/kg

    a- These mean values are from 1 data point, and are not indicative of contamination over the whole area of concern.Table 2: Secondary chemicals of concern detections and limits based on NYSDEC

    4.3 The Expected OutcomePrimary Objectives:

    Prevent any further contamination from reaching the Buffalo River.

    Prevent human and wildlife contact to contamination above limits.

    Secondary Objective

    Remove as much mass as possible. It is cost prohibitive to reduce all contaminant

    mass to below standards.

  • 8/13/2019 Zhen Hau Sing - Feasibility & Treatability Study

    15/59

  • 8/13/2019 Zhen Hau Sing - Feasibility & Treatability Study

    16/59

    5-1

    5 Treatability studies summary

    .Figure 4: Buffalo Color Site C and E, with contamination target zones. Contour lines shown are distance to

    clay layer under ground surface in feet.

    In the following sections, three remedial technologies will be covered, In-Situ Chemical

    Oxidation, Enhanced bioremediation, and phytoremediation. Figure 1 shows the

    approximate areas that are in need of remediation giving approximate depth of concern.

    5.1 In-Situ Chemical Oxidation:5.1.1 Description

    Chemical Oxidation is a remediation technique which involves adding a chemical

    into the ground that promotes oxidation. This oxidation can transform harmful chemicals

    into something that is either not harmful or less harmful (Huling, 2006). The bench scale

    and pilot testing on the site covered two chemicals, hydrogen peroxide (H2O2) and

    persulfate (S2O82-). Additional chemicals that can also be used are (MnO4-), activated

    persulfate (SO4-), calcium peroxideozone, ozone (O3), and ozone/peroxide combination.

  • 8/13/2019 Zhen Hau Sing - Feasibility & Treatability Study

    17/59

    5-2

    Of the chemicals found to be a problem on our site, this technology will treat the

    following: Chlorobenzene, Dichlorobenzene, PAHs Benzo(A)Anthracene, Benzo(A)Pyrene,

    and Benzo(B)Fluoranthene which are our VOC and SVOC chemicals of concern. In addition,

    it also treats Fluoranthene, Phenanthrene, Pyrene, Benzene and Trichlorobenzene which

    are also present at the site. It does not treat metals, so another treatment option would be

    required for them (Huling, 2006).

    5.1.2 Performance

    In the treatability studies, performance when compared to the control (using no

    chemical) produced little difference. This is due to the extremely high organic content of

    the soil as a result of the prior use as a lumber yard. While performance at many sites

    proved promising, the specific conditions at the Buffalo Color site proved poor

    performance due to high organic content, and extremely variable soil debris throughout.

    5.1.3 Removal Efficiencies of Oxidants

    In most situations, typical removal efficiencies ranged from 95-99%, however in all

    cases and studies shown that high organic content significantly reduced these efficiencies,

    creating the need to use significantly more oxidant due to the sorbtion present. Also, in

    nearly all oxidents except for persulfate, the oxidants would go after the organic content

    before the contaminant, making the treatment extremely cost ineffective.

  • 8/13/2019 Zhen Hau Sing - Feasibility & Treatability Study

    18/59

    5-3

    5.1.4 In-situ chemical oxidation remarks

    ISCO was not chosen for any remedies due to the negatives affecting efficiency and

    increasing cost beyond recommendation.

    5.2 In-Situ Enhanced Bioremediation:5.2.1 DESCRIPTION

    Organic contaminants in soil, groundwater, sludge, and solids can be degraded by

    microorganism using the bioremediation. The microorganisms break down contaminants

    by using them as an energy source for themselves. More detailed, bioremediation involves

    the production of energy in a redox reaction within microbial cells. These reactions include

    respiration and other biological functions needed for cell maintenance and reproduction

    (EPA 2000).

    The objective of the bioremediation is to withdraw from the circulation

    contaminants or to turn them into chemical products not hazardous anymore to the nature

    and humans. (GWRTAC,1998).

    5.2.2 EFFECTIVENESS AND APPLICABILITY OF THE ENHANCED IN-SITUBIOREMEDIATION

    Enhanced In-situ bioremediation can treat 95% of the VOCs, SVOCs and organic

    contaminants in the Buffalo Color Company site.

    5.2.2.1 Chemicals of Concerns that can be applicable for the EISBThe leading contaminants are:

    Chlorinated SVOCs and VOCs Non-chlorinated SVOCs and VOCs PAHs

  • 8/13/2019 Zhen Hau Sing - Feasibility & Treatability Study

    19/59

    5-4

    Organic pesticides and herbicides Organic solvents Wood preservatives

    5.2.2.2 Site ConditionsConditions slow down or stop the biodegradation CONDITIONS IDEAL FOR THE

    BIOREMEDIATIONX Concentration of the chemical can be toxic Homogeneous and permeable aquiferX Concentration of the gradient can be too steep for

    acclimation Single sourced contaminant

    X Number of the microorganism can be inadequate Low groundwater gradientX Conditions may be too acid or too alkaline No soil contaminationX Nutrients or enzymes can be lack Easily degraded or immobilized

    contaminantX Permeability can be low

    X Moisture can be too wet or too dry

    X Energy sources such as oxygen ,nitrogen or sulfatecan be lack

    5.2.3 Factors That Affect Enhanced In-Situ BioremediationTable 3: Factors That Affect Enhanced In-Situ Bioremediation. Source: www.clu-in.org/bioremediation/

    Contaminant Concentrations. Contaminant Bioavailability Redox Potential and Oxygen Content Nutrients Temperature

    5.2.4 COST OF THE TECHNOLOGYThere are too many variables in design and operational needs to give accurate

    ranges of costs. As spoken generally, typical costs for in situ bioremediation range from $30

    to $100 per cubic meter of soil (Roote, 1998). In Buffalo Color Company site, soil type and

    the organic content of the soil is improving the efficiency of the treatment, typical cost for

    our sites treatment is going to be $60 per cubic meter of soil.

  • 8/13/2019 Zhen Hau Sing - Feasibility & Treatability Study

    20/59

    5-5

    Contaminated groundwater and soil can be treated at the same time, providing cost

    advantages. When hydrogen peroxide is used to enhance bioremediation, typical costs are

    $10 to $20 per 1,000 liters of groundwater treated.

    It can be assumed that the half of the soil is saturated, 15,287,000 liters is

    groundwater amount that is going to be treated. According to the statement written above,

    additional cost for the enhanced treatment (addition of the hydrogen peroxide) is going to

    be $152,870.

    Operation and maintenance costs can be significant because a continuous source of

    hydrogen peroxide must be delivered to the contaminated groundwater (Roote, 1998).

    Triodis determined the need to install 20 injection wells and additional 10

    monitoring wells.

    Injection Wells # of wells be installed20

    $/well$720

    Total $$ 14,400

    Monitoring Wells Some of the monitoring wells which are installed before for the feasibility studyare going to be used for this face of the project. Additional 10 wells are going tobe installed to the certain areas with respect to the injection wells locations.

    Cost for additional wells is:$7,200

    O&M Costs $787,370

    GRAND TOTAL $808,9700

    5.2.5 Data Need For Implementation Of The Enhanced In-Situ Bioremediation

    For completing the enhanced in-situ bioremediation treatability study in the Buffalo

    Color Company Sites CE, following data must be provided (Roote, 1998);

    The biodegradability of the contaminants; Distribution of contaminant into soil, water, NAPL, and vapor phases; The leaching potential of the contaminants (e.g., water solubility and soil

    sorption coefficient);

  • 8/13/2019 Zhen Hau Sing - Feasibility & Treatability Study

    21/59

    5-6

    The chemical reactivity of the contaminants (e.g., tendencies toward non-biological reactions, such as hydrolysis, oxidation and polymerization);

    Depth and areal extent of the contaminants; Soil type and properties (e.g., organic carbon content, mineral content, pH,

    porosity, permeability, bulk density, moisture content, nutrient level, water-

    holding capacity); The competition for oxygen (e.g., redox potential, ambient oxygen levels); The presence or absence of substances that are toxic to microorganisms; and, The ability of microorganisms in the soil to degrade contaminants.

    5.2.6 Supportive Enhanced In-Situ Bioremediation Technologies Bioventing Air Sparging /Biosparging Liquid Delivery Systems Alternate Electron Acceptors - Anaerobic Bioremediation Phytoremediation

    5.2.7 Enhance In-Situ Bioremediation RemarksEIBR was not chosen as a technology for any remediation. A PRB was chosen to be

    used to prevent contaminated groundwater from leaving the site, and bioremediation is

    incompatible due to the fact the organism growth will interfere with the PRB operation.

    5.3 Phytoremediation5.3.1 Description

    Phytoremediation is a remedial method that utilizes plants alone in treating or

    stabilizing contamination in both sediment and groundwater media. On top of requiring

    low cost investments, this method is known today as the greenest and most

    environmentally natural way to treat contaminated sites. There are six different plant

    mechanisms that allow them to either remove, destroy, transfer, stabilize or contain

  • 8/13/2019 Zhen Hau Sing - Feasibility & Treatability Study

    22/59

  • 8/13/2019 Zhen Hau Sing - Feasibility & Treatability Study

    23/59

    5-8

    5.3.4 Implementability of Phytoremediation and Cost Estimatation

    Hybrid willows Mercury 42% No data Soil Laboratory/Pot

    size

    Pteris vittata

    Chinese brake fern

    Arsenic 5-13% A 42 days Soil

    Groundwater

    Laboratory/Pot

    size

    Bare root white

    willow tree

    BTEX 90% 4 years Groundwater No Data.

    Full scale/On-site

    Combinations of

    hybrid poplar,

    Eastern cottonwood

    and willows trees

    PCE,

    chlorinated

    solvents

    75% Results

    measured in 2

    days, Actual

    project was 4

    years

    Groundwater 3 acres

    Cucurbita pepo ssp.

    pepo

    Zuchinni

    Pyrene, PAHs 60.38% 56 days Soil Laboratory/Pot

    size

  • 8/13/2019 Zhen Hau Sing - Feasibility & Treatability Study

    24/59

    5-9

    Figure 5: Plan view of implementation of phytoremediation on site C and E. Plant species were selected basedon COCs within that area (labeled pink or red).

    Species Unit Price No .Required Shipping Installation Total Price

    Hybrid Poplar $12.75/pot 93 $790.5 $1976.25 (ex. install.)

    Willows $16.75/pot 179 $2953.5 $25,000 $5951.75 (ex. install)

    White lupin $13.98 for

    1500 seeds

    1500 seeds Free $13.98 (ex. install)

    Tall fescue $45/pallet 1600 $14,702 $35/pallet $142,702

    O&M $300,000 (20 years)

    TOTAL $475,663.98 (incl. install)

    $23 per m2

  • 8/13/2019 Zhen Hau Sing - Feasibility & Treatability Study

    25/59

    5-10

    5.3.5 Issues of Phytoremediation

    Issues related to phytoremediation obtained from the treatability studies were the

    potential invasion of species. Besides that, plant species will need to be tested to see if it

    will successfully grow in this region given extreme weather conditions. Proper O&M have

    to done in order to maintain effectiveness as well as plants that have fully absorbed

    contaminants will need to be removed and replaced to maintain effectiveness.

    5.3.6 Phytoremediation Remarks

    Phytoremediation was chosen for our combined remedy due to the fact it is a low cost

    option to continuously reduce contamination, and will provide a pleasant looking

    landscape that will be enjoyed by the community.

    5.4 Permeable Reactive Barrier5.4.1 Description

    A permeable reactive barrier is a wall installed directly into the soil, deep and wide enough to

    prevent contaminated groundwater from bypassing, and forcing the groundwater to pass directly

    through the barrier, which treats it.

    A trench will be dug with a backhoe due to the fact that the soil contains various fill material

    that would interrupt the operation of more efficient trench digging operations. The total length of

    the PRB would be 450m long, 1m wide, and 2m (on average) deep, ensuring 0.3m extension into

    clay layer. Installation diagram is shown in green onFigure 6.One potential modification is to allow

    the SE section to follow the property line to the SE corner instead of angling NE. This would allow

  • 8/13/2019 Zhen Hau Sing - Feasibility & Treatability Study

    26/59

    5-11

    greater flexibility in building, but could potentially create a larger groundwater plume due to the

    longer distance to reach the PRB.

    5.4.2 PerformanceDepending on the type of barrier, and the type of contaminant it is designed to treat, different

    materials can be used. Of the different types of material, the following were chosen and studied in

    depth:

    Organoclay

    Extremely effective against a wide range of organics and chlorinated organics. Has a tendancy

    to swell with contaminate absorption, lowing conductivity as a result until flow ceases. It was

    noted in one study, when PAH and chlorobenzene are involved (as is the case here), as the material

    becomes saturated to the maximum it can hold, chlorobenzene will replace PAH, allowing the PAH

    to bypass the PRB. Otherwise there is no evidence of re-mobilization of any contaminants sorbed

    into organoclay (Reible, 2005). Reible also notes that if sand is mixed into organoclay, its effective

    surface area actually increases, allowing for a decreased PRB thickness as the sand reduces

    preferential channeling. In addition, as the media absorbs chlorobenzene it will swell, reducing

    conductivity and redirecting flow to less saturated media.

    Green Sand

    An industrial metal works waste sand that contains metal by-products which react with

    heavy metals in passing groundwater, locking them in sand. As sand is needed to be used

    with the organoclay to both increase hydraulic conductivity and increase effective surface

    area, green sand is a good candidate. An advantage of green sand is that it is free and has

  • 8/13/2019 Zhen Hau Sing - Feasibility & Treatability Study

    27/59

    5-12

    remediation effects. The foundries it comes from typically have to pay to dispose of it, and

    will even transport it to the site at no cost. The added remediation effects is it will absorb

    arsenic and mercury that is on site, and to a limited effect PAH.

    Disadvantages of green sand is that it may contain unwanted chemical wastes that

    could enter the ground water. Typical wastes such as chlorinated ethanes and other

    organics would be immediately absorbed by the organoclays, making them a non-issue in

    this case. Some other waste metals may be avoided by choosing foundries that do not

    process them.

    One important matter when installing the PRB, is any sewer lines that pass through the

    PRB must be removed, disabled, or otherwise checked to ensure no groundwater will be

    flowing through them, as this will cause contaminated water to bypass the PRB.

    5.4.3 Cost AnalysisA typical installation of organoclay ranges from $300 - $1000 per m3. The backhoe

    use will be more expensive than some other ways of trench digging, but this will be

    balance by the fact green sand is free, and disposal of waste material in this specific case

    will be neglected as it will be used as fill material for excavation. Also, another factor in

    cost is the fill material, in this case is green sand that will be procured at no cost.

    Because of these factors, the expected cost for installation of an organoclay-green sand

    PRB will be $450 per m3, for a total of $350,000.

    5.4.4 Removal Efficiencies of MaterialsOrganoclay

    Organoclay is quick to absorb many contaminants, including four of the six CoC at

    the Buffalo Color site, Chlorobenzene, Di-chlorobenze, and both PAHs.

  • 8/13/2019 Zhen Hau Sing - Feasibility & Treatability Study

    28/59

    5-13

    Main issue with organoclay is, by its name, it is clay and therefore has a very low

    hydraulic conductivity. This fact tends organoclay to be used as a barrier method which

    also absorbs potential contamination leakage, which will reduce groundwater flow to a

    point it would be ineffective in containing groundwater contamination at the Buffalo Color

    site. If organoclay was installed alone, groundwater would either go around or over. This

    would make it very useful as a containment media, which is not desired here. This is why it

    will be mixed with the greensand.

    Groundwater flow was modeled in Visual AEM, with initial conditions tested to

    match recorded groundwater levels. Figure 6 shows the capture zone in the worst case

    scenario of 2.5 cm/day conductivity of the entire PRB with a hydraulic lock near the DNAPL

    zone. In this case potentially contaminated groundwater will continue to flow through the

    barrier and not bypass. One alternative is to

    Figure 6: Post PRB installation Capture Zone

  • 8/13/2019 Zhen Hau Sing - Feasibility & Treatability Study

    29/59

    5-14

    5.4.5 Important Installation GuidelinesWhen installing the organoclay/greensand PRB, careful attention to the hydraulic

    conductivity of the material must be heeded. If conductivity is allowed to be less that

    2.5cm/day, the entire groundwater contamination plume may not be collected by the PRB.

    Sewers:

    Any sewer line from the Buffalo Color site going through the PRB must be checked to

    ensure no leakage of groundwater is possible, or the sewer line blocked/removed. A leaky

    sewer or other piping system will bypass the PRB allowing contaminates to the Buffalo

    River.

    5.5 River Sediment Dredging

    5.5.1 Description

    Contaminated sediments in aquatic environments can pose health risks to many types

    of organisms, including humans. Exposure to the contaminants occurs by several routes,

    including direct contact and consumption of organisms that have accumulated

    contaminants from the sediments. The potential adverse effects on human health and the

    environment are compelling reasons to seek to reduce exposure. Contaminated sediments

    can occur in small, localized areas or in vast areas, covering miles of river or harbor

    bottoms and associated floodplains (The National Academies Press, 2007).

    Underwater excavation for excavating the contaminated sediment is called dredging.

    After the initial excavation needed to establish a channel, the periodic dredging that must

    be done to keep it clear and safe for navigation is called maintenance dredging. Once

  • 8/13/2019 Zhen Hau Sing - Feasibility & Treatability Study

    30/59

    5-15

    sediments are dredged from the waterway, they are called dredged material. (The National

    Academies Press, 2007)

    A dredge is a machine that scoops or suctions sediment from the bottom of waterways

    or is used to mine materials underwater.

    The chemicals of concern in contaminated sediment sites vary; polychlorinated

    biphenyls (PCBs) are the most common, followed by metals, and polycyclic aromatic

    hydrocarbons (EPA 2005). The widely varied physical and chemical properties of

    contaminants markedly affect their distribution in the environment and their behavior

    (including transport, bioavailability, and toxicity) during and after remediation. The degree

    of contamination can be severe in some areas with nearly unadulterated original products,

    such as PCB-containing oils, pesticides, or coal-tar residues. In other areas, contaminants

    occur at low concentrations in sediments among functioning ecosystems of fish, plants, and

    benthic invertebrates. The thickness of the contaminated sediment is highly variable and

    often poorly characterized but can range from a few inches to many feet thick with marked

    differences over small spatial scales. (The National Academies Press, 2007)

    5.5.2 Cost EstimationEstimating the costs of dredging operations is provided in this section.

    Virtually all costs associated with the removal component of a sediment remediation

    project are capital costs (direct and indirect). The elements of environmental dredging

    costs include (EPA, 1994):

  • 8/13/2019 Zhen Hau Sing - Feasibility & Treatability Study

    31/59

    5-16

    Mobilization/demobilization Dredge operation Contaminant barriers Monitoring Health and safety Equipment decontamination

    Backhoes will be used for the dredging operation. Excavated sediment is going to send

    to the confined disposal facility with the truck.

    Approximate cost estimation is shown below in the table.

    ITEM COST RIVERSTATISTICS

    TOTAL COST

    Mobilization/Demobilization ofthe dredging equipment to theriver

    $37,500/100 km100 km

    assumed forthe distance of

    $ 37,500

    Dredging operation $50/m325,118 m3

    $ 1,255,900

    Containment Barrier$28/m2

    16,482 m2 $ 461,496

    Sediment excavation withbackhoe

    $10/m3 25,118 m3 $ 251,118

    Transportation to thefacility(USACE, 2007)

    $50/toncontaminated sediment

    2837 $ 3,562,988

    Health and safety, equipmentdecontamination

    $500/day 10 days $ 5,000

    TOTAL $ 5,574,002

    Figure 7: Cost Estimation for the dredging

    5.5.3 Preventing the environmental impacts

  • 8/13/2019 Zhen Hau Sing - Feasibility & Treatability Study

    32/59

    5-17

    Figure 8: Scheme showing that the steps of the environmental impact assessment

    5.5.3.1 Noise preventing

    Objective:To ensure that no noise nuisance results from the dredging.

    Suggested measures

    Liaise with the local community to identify noise issues. Select quiet equipment. Alter or enclose equipment to reduce noise at the source. Use sound-absorbing materials to prevent the spread of noise by isolating the source. Limit times of operation.

    5.5.3.2 Odor preventing

    Objective:To ensure that small odor problems do not alarm nearby residents.

    Suggested measures

    Inform residents of temporary nature of any odors and of grey sediment. Assess odor risk if contaminated.

    5.5.3.3 Minimize Effects on Water Quality increase monitoring for turbidity (this will identify but not minimize turbidity);

    incorporate or re orientate silt screen;

    reduce overflow of barges or bunds;

    increase travel path of fluid within bunds to increase sedimentation;

    decrease rate of dredging;

    select appropriate dredge for material being dredged

  • 8/13/2019 Zhen Hau Sing - Feasibility & Treatability Study

    33/59

    5-18

    relocate dredge to an alternative location.

    Use silt screens where practical and sediments are fine.

    When necessary, monitor water quality including turbidity, as well as sea grass and

    other sensitive species.

    5.5.3.4 Minimize Effects of Contaminated Sediments Monitor water quality near dredging operations removing highly contaminated

    sediments.

    Dredge contaminated sediments first and dispose to land or place on spoil grounds

    first and cover with clean sediments.

    Use silt screens to contain contaminated sediment

    5.5.3.5 Sensitive Biological Communities Map location of sensitive communities.

    Prevent Noise Nuisance in Residential Areas

    Liaise with the local community to identify areas and times sensitive to noise.

    Alter or enclose equipment to reduce noise at the source.

    Use sound-absorbing materials to prevent the spread of noise by isolating the source.

    Monitor noise levels.

    5.5.3.6 Ensure that Small Odor Problems Inform residents of temporary nature of any odors and grey sediment.

    Cease dredging on very hot days (greater than 35C) or times of high public use. Inform public of works using on-site signs.

  • 8/13/2019 Zhen Hau Sing - Feasibility & Treatability Study

    34/59

    6-1

    6 Effectiveness, Implementability, and CostTable 5: Screening of Remedial Technologies for Groundwater at Buffalo Color Corp. Sites C and E.

    RESPONSEACTION

    TECHNOLOGYTYPE

    TECHNOLOGY EFFECTIVENESS IMPLEMENTABILITY RELATIVE COSTNote : Above

    average being higher cost

    RETAINED ORNOT RETAINED

    FOR FURTHER ANALYSISNo Action None None Not effective unless contaminants

    remove/breakdown naturally.

    Readily implementable. The site is

    to be left as is.

    None Retained (used to compare

    the effects of no action.)Containment Barrier Walls Slurry Wall

    Surface Capping

    Effective in preventing contaminatedgroundwater to enter river.

    Effective in preventing direct contactof living beings with contamination.

    Implementable. The site is currentlyan open land.

    Implementable. The site is currentlyan open land.

    Average

    Average

    Not retained (hinders futurerenovation plans)

    Not retained (hinders futurebuilding plans)

    Treatment Physical /Chemical Permeable ReactiveBarrier (PRB)

    Activated Carbon

    Chemical Oxidation

    Effective at reducing contaminantlevels prior to exiting site. Dependshighly on materials used and type ofcontamination.

    Effective at removing chlorobenzeneand dichlorobenzene over largeareas.

    Effective at removing chlorobenzeneand other chlorinated compounds.

    Implementable. Backhoe excavationcan be done at boundary of siteupon determining direction ofcontaminant migration. Removes all.

    Implementable. Can be used as partof material in PRB.

    Implementable. Proper injectionwells will need to be installed before

    execution.

    Average

    Average. Cost does notinclude installation.

    Above average. Highvolume of material

    required.

    Retained

    Not retained (does notremove other contaminants)

    Not retained (site is highlyorganic)

    Treatment(Continued)

    Filtration

    Biological

    Membrane Filtration

    PrecipitationFiltration

    Adsorption Filtration

    In-Situ BiochemicalOxidation

    Effective at removing metalsmercury and arsenic.

    Effective at removing metalsmercury and arsenic.

    Effective at removing metalsmercury and arsenic.

    Effective at removing mercury.

    Implementable.

    Implementable

    Implementable

    Implementable.

    Below average

    Below average

    Below average

    Average

    Not retained (studies showhigher performance in PRB)

    Not retained (studies showhigher performance in PRB)

    Not retained (studies showhigher performance in PRB)

    Not retained (lowcompatibility with othertechnologies )

  • 8/13/2019 Zhen Hau Sing - Feasibility & Treatability Study

    35/59

    6-2

    Technologies Retained for Remediation in Groundwater for Detailed Analysis.

    PREVENTION CONTAINMENT SOURCE REMOVAL TREATMENT DISPOSAL(None retained) (None retained) (None Retained) Physical/Chemical

    -Permeable Reactive Barrier(None retained)

    Table 6: Screening of Remedial Technologies for Soil at Buffalo Color Corp. Sites C and E.

    RESPONSEACTION

    TECHNOLOGYTYPE

    TECHNOLOGY EFFECTIVENESS IMPLEMENTABILITY RELATIVE COST RETAINED ORNOT RETAINED FOR FURTHER ANALYSIS

    No Action None None Not effective unless contaminantsremove/breakdown naturally.

    Readily implementable. The site is left asis.

    None Retained (used to compare theffects of no action)

    Containment Chemical

    Immobilization/Media Migration

    Solidification/Stabilization

    Vitrification

    Effective in immobilizing contaminants toprevent migration, provided that actualcontamination location is known.

    Effective in immobilizing metals andvolatilizing to remove them from soil.

    Implementable.

    Implementable

    Average

    Above average

    Not retained (does not removecontaminant and pinpointlocation of contamination is noknown)

    Not retained (potential vaporcontamination is not f avorable

    SourceRemoval

    Excavation

    Post excavation

    Mechanical Excavation

    Soil Washing/Acid Extraction

    Effective. Contamination of highconcentrations can be removed from thesite.

    Effective. Contamination is removed andresults in remediated soil.

    Readily Implementable. Ideal as locationsof contamination is isolated and depth toclay layer is shallow.

    Implementable. Soil can be excavated andcontaminates can be washed/extracted.

    Average. Cost does notinclude cost of treatingsoil.

    Average

    Retained

    Not retained (cost for transporand space required for washinis not feasible)

    Disposal OffsiteDischarge

    Permitted TreatmentFacility

    Effective. Contaminated soil will betreated and good for future usage.

    Implementable. This is provided that thereare soil/contamination that needs disposal.

    Above average Retained (technology used foexcavation analysis)

    Treatment Biological Phytoremediation

    Bioremediation

    Effective in removing COCs of l ower

    concentration depending on plant species.Process is long term however.Effective in removing organics and PAHs.

    Implementable.

    Implementable.

    Below Average

    Average

    Retained

    Not retained (low compatibilitywith other technologies)

    Technologies Retained for Remediation in Soil for Detailed Analysis.

    PREVENTION CONTAINMENT SOURCE REMOVAL TREATMENT DISPOSAL(None retained) (None retained) Excavation

    -Mechanical excavationBiological-Phytoremediation

    Offsite discharge-Permitted Treatment Facility

  • 8/13/2019 Zhen Hau Sing - Feasibility & Treatability Study

    36/59

    6-3

    Table 7:Screening of Remedial Technologies for Vapor at Buffalo Color Corp. Sites C and E.

    RESPONSEACTION

    TECHNOLOGYTYPE

    TECHNOLOGY EFFECTIVENESS IMPLEMENTABILITY RELATIVECOST

    RETAINED ORNOT RETAINEDFOR FURTHER ANALYSIS

    No Action None None Not effective unless contaminantsremove/breakdown naturally.

    Implementable. The site is to be left asis.

    None Retained (used to compare theeffects of no action)

    Mass removal Volatization/Media Migration

    Soil VaporExtraction

    Air Sparging

    Effective in removing VOCs from soil to vaporand removal of vapor through vacuums.

    Effective in removing VOCs from soil andgroundwater and removal of vapor through

    ventilation.

    Implementable provided that vapor isproduced through technologies used.

    Implementable provided ventilation isinstalled.

    Average

    Average

    Not retained (potential vaporcontamination is not favorable)

    Not retained (potential vaporcontamination is not f avorable)

    Prevention(applicable onlyto buildingsdeveloped inthe long run)

    PassiveMitigation

    Active Mitigation

    Passive Barriers/Passive Venting

    Depressurization

    Effective in preventing intrusion of vaporthrough cracks in building basement. Directsvapor to the edge of buildings.

    Effective in reducing the driving force forvapor intrusion into building.

    Implementable if buildings were to bebuilt on the site.

    Implementable after buildings are built.

    Below average

    Below average

    Retained

    Retained

    Technologies Retained for Remediation in Vapor for Detailed Analysis.

    PREVENTION CONTAINMENT SOURCE REMOVAL TREATMENT DISPOSALPassive Mitigation-Passive Barriers/Venting

    Active Mitigation-Depressurization

    (None retained) (None retained) (None retained) (None retained)

  • 8/13/2019 Zhen Hau Sing - Feasibility & Treatability Study

    37/59

    6-4

    Table 8: Screening of Remedial Technologies for River Sediments in the Buffalo River.

    RESPONSEACTION

    TECHNOLOGYTYPE

    TECHNOLOGY EFFECTIVENESS IMPLEMENTABILITY RELATIVE COST RETAINED ORNOT RETAINED FOR FURTHER ANALYSIS

    No Action None None Not effective unless contaminantsremove/breakdown naturally.

    Implementable. The site is to be left as is. None Retained (used to compare theeffects of no action)

    SourceRemoval

    Dredging Mechanical Dredging Effective at removing contaminatedsediment.

    Implementable. Sediment in soil wil l beremoved.

    Above average Retained (issues of resurfacingwill be discussed)

    Disposal Offsite Disposal Confined DisposalFacility

    Effective. Contaminated sediments will beremoved from river.

    Implementable Below average Retained (technology retained forfull dredging analysis)

    Containment Capping Impermeable Cap Effective at preventing contact of

    contamination with river water andbenthic community

    Implementable. Preparation for materials

    should be done prior to installation.

    Average Not retained (affects habitat of

    benthic community,contamination is not removed)Treatment Physical/

    Chemical

    Thermal

    Sediment washing

    Low thermaldesorption

    Effective at removing PCBs andchlorobenzene.

    Effective at detaching contaminants formsediments and volatizing it.

    Implementable. However, sediments wouldneed to be removed prior to treatment.

    Implementable

    Above average

    Above average

    Not retained (potential sedimentresurfacing from replacing soil)

    Not retained (potentialcontamination escaping into riverwaters)

    Technologies Retained for Remediation in River Sediments for Detailed Analysis.

    PREVENTION CONTAINMENT SOURCE REMOVAL TREATMENT DISPOSAL(None retained) (None retained) Dredging

    -Mechanical Dredging(None retained) (None retained)

  • 8/13/2019 Zhen Hau Sing - Feasibility & Treatability Study

    38/59

    7-1

    7 Possible Remedial CombinationsTalk about different combinations, even discussing ones that will not work(such as bioremed

    and PRB)

    7.1 On Site7.1.1 ISCO, Cap, Pump and treat7.1.1.1 Description

    This remedy would consist of using ISCO to treat the chlorobenzene contaminated

    areas. As the treatment studies indicate, this would result in a removal efficiency of less

    than 95%, which would result in residual contamination significantly above limits. In

    addition, a cap would be put on areas of metal contamination to prevent exposure.

    Lastly, to prevent contaminated groundwater from reaching the Buffalo River, a pump

    and treat barrier method would be introduced.

    7.1.1.2 Comparison of Alternative to Evaluation CriteriaThe following nine criteria have been evaluated IAW the USEPA Feasibility Study

    Evaluation Criteria:

    7.1.1.3 Overall Protection of Human Health and the EnvironmentThe reduction in chlorobenzene mass and capping remaining contamination would prevent

    personal contact with contamination. The pump and treat barrier would prevent further spread

    of contamination to the river.

    7.1.1.4 Compliance with ARARs

  • 8/13/2019 Zhen Hau Sing - Feasibility & Treatability Study

    39/59

    7-2

    As chemical oxidation will not remove enough mass to reduce chlorobenze to limits, and

    capping remaining CoC will not remove any mass, the soil and on-site groundwater will not

    meet any ARARs for CoC. Groundwater leaving the site will meet ARARs as the pump and treat

    system will prevent contaminated water from leaving the site.

    7.1.1.5 Long-Term EffectivenessThe barrier would prevent contact immediately and maintain its control for the long-term.

    Pump and treat would be continuously operating providing a barrier, and the ISCO will have

    completed its chlorobenzene mass reduction.

    7.1.1.6

    Reduction of Toxicity, Mobility, or VolumeVolume reduction will only happen for chlorobenzene. The mobility of the CoC will be

    negated by the cap and the pump and treat system, and while toxicity will not be reduced, exposure

    will be.

    7.1.1.7 Short-Term EffectivenessThe cap and pump and treat system will immediately prevent spread/contact of

    contamination. ISCO of the chlorobenzene will be fairly quick providing mass reduction in weeks.

    7.1.1.8 ImplementabilityThe implementability of ISCO is questionable as the negative effects of the soil on site. The

    cap and pump and treat will be easily implemented.

    7.1.1.9 CostThe total cost for the treatment would be moderate, but due to the questionable ISCO costs

    could increase greatly if it proves to not react well. In addition, high O&M requirements of the pump

    and treat.

    7.1.1.10State and Community Acceptance

  • 8/13/2019 Zhen Hau Sing - Feasibility & Treatability Study

    40/59

    7-3

    State acceptance would be good for no further river contamination and prevention of

    personal contact to CoC. Any business wishing to build on the site would be severely restricted by

    the cap in where they could build.

    7.2 River Sedimentation

    7.2.1 Hydraulic Lock with material such as organoclay7.2.2 Description

    A material, such as organoclay, would be put into the river to cover, and lock the

    contamination in place.

    7.2.3 Comparison of Alternative to Evaluation CriteriaThe following nine criteria have been evaluated IAW the USEPA Feasibility Study

    Evaluation Criteria:

    7.2.3.1 Overall Protection of Human Health and the EnvironmentThis would potentially prevent contamination spread into the river column and by

    the benthic community into fish and other wildlife. This would however, adversely affect

    the ecology of the riverbed by preventing a thriving benthic community as the cap would

    not be an ideal environment.

    7.2.3.2 Compliance with ARARsAs no mass would be removed, there would be no compliance with ARARs in buried

    sediment. The river column would be clear of contamination.

    7.2.3.3 Long-Term Effectiveness

  • 8/13/2019 Zhen Hau Sing - Feasibility & Treatability Study

    41/59

    8-4

    Long-term effectiveness would be questionable as natural river currents and other

    factors could erode the cover and allow contamination to surface and/or allow the benthic

    community to reach the contamination.

    7.2.3.4 Reduction of Toxicity, Mobility, or VolumeToxicity and volume would not be reduced, but the cover would limit mobility.

    7.2.3.5 Short-Term EffectivenessIt should be effective in the short term, assuming the cap was completely installed

    correctly.

    7.2.3.6 ImplementabilityThe steep river banks, coupled with the fact that the Army Corps of Engineers

    regularly dredge the channel will provide severe impacts on the ability of a stable cap to be

    installed on the contaminated portions of the Buffalo River.

    7.2.3.7 CostInitial costs of placing a cap would be significantly lower than dredging, but O&M

    costs over the years due to erosion and dredging operations would add up quickly.

    7.2.3.8 State and Community AcceptanceThe Buffalo River Keepers would object to the modification of the sedment, as it would

    adversely affect growth and stability of the benthic community of the area. The Army Corps

    of Engineers would continuously dredge due to requirements to maintain the channel open

    would cause concern of future failure of containment which the state would object to.

    8 Proposed Remedies

  • 8/13/2019 Zhen Hau Sing - Feasibility & Treatability Study

    42/59

    8-2

    8.1 Remedy 1: No Action

    8.1.1 DescriptionThe final alternative, the no action leave the site untreated. Contaminations will not be

    removed or monitored. The site will continue to be used as is.

    8.1.2 Comparison of Alternative to Evaluation CriteriaThe following nine criteria have been evaluated IAW the USEPA Feasibility Study Evaluation

    Criteria:

    8.1.2.1 Overall Protection of Human Health and the EnvironmentBy taking no remedial action on the BCC site, all the environmental mediums

    (groundwater soil, sediment and vapor) will remain contaminated and eventually spread to

    neighboring media. This is due to the nature of the COCs that are present. On site, citizens

    or animals that come in contact with the soil will be exposed to the contaminants by means

    of ingestion. VOCs within the soil will volatilize and contaminate the vapor/atmosphere

    which will potentially be inhaled by living beings on the site and then spread to residential

    areas around the site

    As for off-site areas, this alternative poses a huge treat to the Buffalo River.

    Contaminated groundwater will follow its regional flow into the Buffalo River. Existing

    sewer lines will also transport contaminated groundwater into the river. The

    contamination of the river will harm the benthic community and also parties that use and

    rely on the water of the Buffalo River for drinking or other purposes.

    Due to the reasons above, the alternative fails to meet this criterion.

    8.1.2.2 Compliance with ARARs

  • 8/13/2019 Zhen Hau Sing - Feasibility & Treatability Study

    43/59

    8-3

    Groundwater standards within the site would not be met. It is not expected to be an

    issue as groundwater is not used in the City of Buffalo. Groundwater standards outside of

    the site will also not be met since contamination from the site would be allowed to leave

    the site as is and transport the contamination outside the site.

    Soil concentrations would also fail to meet the standards. Contaminants that are

    absorbed to the soil will potential enter groundwater as well.

    8.1.2.3 Long-Term EffectivenessThis alternative is not effective in the long-run. On top of not providing any removal,

    leaving the site as is would lead to very steep cost if the site were to be used. This is the

    result of the spread of the contaminated area with the Buffalo River being one the main

    concerns. Plumes may also increase potentially as more and more contaminants absorbed

    and combine.

    8.1.2.4 Reduction of Toxicity, Mobility, or VolumeNo toxicity will be removed. There will be potential mobility of the contaminants

    especially from groundwater to sediment and groundwater or soil to vapor. Volume of

    contaminants may decrease due to the migration from on to off-site like the Buffalo River.

    Volume of the contaminants may also stay constant but change in terms of its physical

    property. Bigger plumes of DNAPL may form through the years.

    .

    8.1.2.5 Short-Term Effectiveness

  • 8/13/2019 Zhen Hau Sing - Feasibility & Treatability Study

    44/59

    8-4

    This alternative is not effective short term. This would mean that it is not possible

    for immediate planning and construction of a new commercial and industrial area on the

    site. The alternative fails to meet this criterion.

    8.1.2.6 ImplementabilityAs all no action alternatives, this option is implementable on the site. The alternative

    fulfills this criterion.

    8.1.2.7 CostThere is no cost involved in taking no action. Hence the alternative fulfills this

    criterion. .

    8.1.2.8 State and Community AcceptanceThis alternative would have various acceptance results. In terms of cost, the state

    and the community would accept this alternative. As remediation projects generally have

    high costs, the state and community would to be able to use the investment to develop

    other sectors of the state/city if this alternative was chosen.

    However, there are also reasons that the state and community will not accept this

    alternative. For the state, leaving the site contaminated will prohibit commercial or

    industrial development at the location. The lost in amount of usable land will hinder the

    potential economic growth the usage may bring for the state/city. As for the community,

    leaving the site contaminated will mean that neighboring areas are at a high risk of being

    exposed to the contamination. On top of that, the Buffalo River will be at risk of being

    polluted. Fishing activities for example, would have to be forbidden to avoid consumption

    of fish affected by the contamination.

  • 8/13/2019 Zhen Hau Sing - Feasibility & Treatability Study

    45/59

    8-5

    8.2 Remedy 2: Combination

    8.2.1 DescriptionThree technologies will be employed. First areas of highest concentration will be

    excavated significantly reducing contamination mass. Second, a permeable reactive barrier

    containing a combination of organoclay and green sand will be placed south of all

    contaminated soil, preventing groundwater contamination from reaching the Buffalo River.

    Third, phytoremediation will consist of different plants being planted on the remaining

    contaminated areas to a) reduce mass over time and b) act as a barrier to prevent civilian

    contact with the ground. Also, a deed restriction will be placed on the property for any

    building in the area of VOC contamination that a foundation venting system must be

    installed to prevent the build-up of vapor intrusion contamination in buildings.

    Lastly, the Buffalo River will be dredged down 6 feet along the banks.

    This remedy will accomplish our goals as follows:

    - Primary goal 1: Prevent further contamination of the Buffalo River. Removal of significant mass and then having the PRB barrier will prevent

    any contamination from reaching the river. Goal will be met.

    - Primary goal 2: Prevent Human contact with contamination above limits Removal of significant mass, blocking off areas of continued

    contamination, and institution of deed. Goal will be met.

    - Secondary goal: Reduce all contamination to below set limits Removal of significant mass will approach limits, but will not meet them.

    Cost and environmental impact to meet this goal is prohibitive.

  • 8/13/2019 Zhen Hau Sing - Feasibility & Treatability Study

    46/59

    8-6

    Figure 9: Excavation Areas

    Figure 10: Phytoremediation and PRB installation locations

    8.2.2 Comparison of Alternative to Evaluation CriteriaThe following nine criteria have been evaluated IAW the USEPA Feasibility Study

    Evaluation Criteria:

  • 8/13/2019 Zhen Hau Sing - Feasibility & Treatability Study

    47/59

    8-7

    8.2.2.1 Overall Protection of Human Health and the EnvironmentSignificant reduction of mass in the soil will assist in protecting human health, along

    with preventing access to the remaining contamination. The groundwater will not be

    remediated on site, but it is not used as drinking water at this location, therefor will not be

    an issue. The combination of the PRB preventing contaminated groundwater from entering

    the Buffalo River and dredging of contaminated sediments will protect the river wildlife.

    Use of a containment barrier in the river during dredging will prevent high turbidity from

    affecting the rest of the river.

    8.2.2.2 Compliance with ARARs

    IAW NYSDEC 375-1.8, full source removal is preferred. To approach satisfaction of

    this, all contamination above 10x the limit will be excavated. The remaining contamination

    will be contained by use of controlled phytoremediation (for soil) and installation of a PRB

    (groundwater). Exposure to any residual vapor intrusion will be prevented by a deed

    restriction to install a barrier or vent system to prevent intrusion.

    Groundwater standards within the site would not be met. It is not expected to be an

    issue as groundwater is not used in the City of Buffalo.

    Soil concentrations would be reduced immediately, but will not meet standards for

    any of the CoC. Phytoremediation will continuously reduce levels over time, but at a 70-

    80% removal efficiency over 10-20 years, it is not expected to reach required levels in that

    time. The deed restriction of installation of foundation vent systems will prevent air quality

    inside buildings from exceeding limits.

    8.2.2.3 Long-Term Effectiveness

  • 8/13/2019 Zhen Hau Sing - Feasibility & Treatability Study

    48/59

    8-8

    The combination of technologies will provide a long-term control. The excavation

    will have removed majority of the mass, and the phytoremediation will continuously

    reduce mass over the next two decades. The PRB will continuously maintain clean effluent

    groundwater of any remaining contamination.

    8.2.2.4 Reduction of Toxicity, Mobility, or Volume

    Excavation will immediately reduce mass. Phytoremediation will slowly reduce

    mass over time. The PRB will prevent mobility of contaminants outside the site, and

    implementation of a deed restriction to add foundation sealing or venting into any

    buildings near chlorobenzene contamination will prevent mobility of vapors into buildings.

    8.2.2.5 Short-Term Effectiveness

    The excavation will immediately reduce the problem, but will not eliminate it.

    Phytoremediation takes time, in the order of 5-8 years before it will begin to reduce

    remaining levels to acceptable limits. The PRB will immediately prevent further

    groundwater contamination from exiting the Buffalo Color Site upon installation, and

    dredging of the river sediment will remove contamination. Initial benthic communities will

    be impacted by the dredging, but will be expected to return to normal in the near future.

    8.2.2.6 Implementability

    The Buffalo Color site is adjacent to city roads with full access to the interstate

    system. This allows for ease of truck traffic for any materials required for the remedy. In

  • 8/13/2019 Zhen Hau Sing - Feasibility & Treatability Study

    49/59

    8-9

    addition, having railroads right next to the site provides an easy access for shipping of

    materials needed for PRB installation and replacing soil from excavation.

    For excavation, the nature of the soil being primarily mixed fill will prove to be

    difficult at times due to old building material and piping systems buried throughout the site.

    In addition, groundwater will be encountered at all excavation areas and will have to be

    dealt with.

    For the phytoremediation, buried materials may require additional excavation as

    required to allow plant growth. The high organic content and high water table will allow

    for fairly quick plant growth, and initial excavation of high contamination will prevent

    excessive toxicity.

    8.2.2.7 Cost

    To save costs, it is recommended to use any soil removed in creation of the PRB

    trench as the fill soil for excavated sections. This will also significantly reduce required

    truck traffic to 80 truckloads. Costs could be reduced even more if railroads were utilized

    for material transportation, as they are adjacent to the site.

    - The cost of this initial excavation and removal of material to an off-site processingfacility is expected to be $1.1 Million.

    - The expected cost of the installation of the PRB is expected to be 0.35 Million.- The expected cost of the installation of the Phytoremediation is expected to be 0.4

    Million, which accounts for O&M costs for 20 years.

    - O&M costs are expected to be $12,000 per year to account for regular groundwatersamples to ensure PRB efficiency. This will be $60,000 over the next 5 years.

  • 8/13/2019 Zhen Hau Sing - Feasibility & Treatability Study

    50/59

    9-10

    - River Sediment Dredging will cost $5.6 million to remediate.- Current accrued costs from investigation have totaled $72,000.

    This brings the total estimated costs to $7.5 Million.

    8.2.2.8 State and Community Acceptance

    The limited amount of truck traffic required, along with the green appearance of the

    phytoremediation will be positive on community acceptance. Due to the fact this has been

    an industrial area, the community will accept the visual improvement. The Buffalo River

    Keepers, and other state and private organizations will be satisfied by the remediation

    preventing further contamination of the Buffalo River. Future developers may not like the

    requirement to not build in the phytoremediation areas.

    9 Ecological Habitat

    9.1 Buffalo Color Company SiteBy implementing the trees for the phytoremediation, ecological habitat will be restored. Birds,

    reptiles and the other species can be in their nature with the help of trees which are planted during the

    phytoremediation.

    9.2 Buffalo RiverThe Buffalo River has played a vital role in the regions economy for more than a century. However,

    industrialization and the pressures of growing river communities have taken a toll on the river

    ecosystem. Although discharges from the oil refineries, steel mills, and chemical plants that occupy its

    shores have declined over the last several decades, the impacts of pollution and degraded habitats

  • 8/13/2019 Zhen Hau Sing - Feasibility & Treatability Study

    51/59

    9-2

    remain. The primary issues affecting the Buffalo River today are impaired water quality, contaminated

    bottom sediments, inactive hazardous waste sites, point and nonpoint source pollution, combined

    sewer overflows, and fish and wildlife habitat loss and degradation.(Riverkeepers,2006)

    Ecological restoration is defined by EPA as the process of assisting the recovery of an ecosystem that

    has been degraded, damaged or destroyed. To identify, prioritize, and facilitate opportunities to

    restore, protect and enhance habitat within the Buffalo River Habitat Corridor and its tributaries for a

    healthy and sustainable ecosystem that will benefit habitat, wildlife, corridor communities, and future

    generations are Triodis missions during the treatment operations.(Riverkeepers,2006)

    Corruptions that have been identified:

    1. Restrictions on fish and wildlife consumption2. Fish tumors or other deformities3. Degradation of aesthetics4. Degradation of benthos5. Restriction on dredging activities6. Loss of fish and wildlife habitat7. Eutrophication or undesirable algae8. Tainting of fish and wildlife flavor9. Degradation of fish and wildlife populations10.Bird or animal deformities or reproduction problems11.Degradation of phytoplankton and zooplankton

    populations

    Figure 11: Observed disorders

    Fish and wildlife habitat have been degraded by dredging of the river. Fish tumors have

    been observed in the Buffalo River and are believed to be caused by PAHs in the sediments.

    Research and analysis of fish health and population completed in August 2005 indicate that

    fish diversity and health has not improved over the last decade based on the data obtained

    in 2003-04, and compared to data available from fish surveys of the early 1990s (ENVIRON ,

    2009).

  • 8/13/2019 Zhen Hau Sing - Feasibility & Treatability Study

    52/59

  • 8/13/2019 Zhen Hau Sing - Feasibility & Treatability Study

    53/59

    10-4

    conducting bench or pilot tests, disposal of residuals, uncertainties pertaining to innovative

    technologies, and the degree of development of the technology being tested (EPA, 1988).

    Additional community relations implementation activities applied in the assessment

    and included a public meeting to explain the proposed excavation, phytoremediation,

    dredging and organic-clay PRB and fact sheets describing the technology and technical

    details, a briefing to public officials about the river dredging, organic PRB and the

    phytoremediation, and small group consultations with members of the community

    concerned about EPAs actions at the site and the river (EPA, 1988).

    Site-specific community relations activities identified in the community relations

    plan prepared previously. While appropriate modifications of activities are made to the

    community relations plan as the project progresses, the plan is generally implemented as

    written to ensure that the community is informed of the alternatives being evaluated and is

    provided a reasonable opportunity to provide input to the decision-making process (EPA,

    1988).

    Fact sheets are prepared that summarizes the alternatives being evaluated. As

    appropriate, small group consultations or public meetings are held to discuss community

    concerns and explained alternatives under consideration. Public officials are briefed and

    press releases prepared describing the alternatives.

  • 8/13/2019 Zhen Hau Sing - Feasibility & Treatability Study

    54/59

    10-5

    Figure 12: Example Citizen Guidances (EPA, 2012)

    The objective of community relations during application of the alternatives is to assist the

    community in understanding the alternatives and the specific considerations took into

    account in implementing an alternative. In this way, the community is prepared to provide

    meaningful input during the upcoming public comment period.

    Control of Invasive Species from Phytoremediation

    The introduction of new plant species in the phytoremediation process brings about

    potential species invasion. The fact that the plants are being imported into the site means

    that there will be species that are not native to the site. Asides from Festuca arundinacea

    (tall fescue grass), the species Lupinus albus (White Lupin), Sapix spp. (Willow trees) and

    Poplar spp. (Hybrid Poplars) are potentially invasive to the local ecosystem. By definition

    this phytoremediation step is facilitating invasive species.

  • 8/13/2019 Zhen Hau Sing - Feasibility & Treatability Study

    55/59

    10-6

    More studies, experiments and discussions with ecologist and biologists would need to

    be carried out to better understand the potential species invasion by the plant species

    mentioned. As there are no current studies that discuss or yield the results of these species

    being invasive, it is impossible to draw a conclusion on the possibility of invasion by the

    phytoremediation plants. However, if the selected plant species are deemed invasive, other

    plant alternatives will be chosen. This would be a constant monitoring and maintenance

    process to prevent species invasion.

    Discussion on the Effective Construction Procedure

    The processes of excavation and PRB construction will be carried out simultaneously.

    This process is estimated to last for about one week. The reason why excavation and PRB

    construction were done at the same time is for soil cost management. In the excavation

    step, highly contaminated soil are removed and a disposed off-site. This would result in pits

    that need to be filled again. In installing the PRB, less contaminated or even clean soil (by

    majority) are removed and replaced with organoclay and green sand mixture. Instead of

    removing these dug soil off-site, they will be used to re-fill the pits that resulted from

    excavation. By carrying out this procedure, cost for obtaining new soil can be greatly

    decrease or eliminated. As phytoremediation serves as a long-term solution, it will be

    installed last. Time frame of this installation is variable depending on weather conditions

    and amount of labor available. Finishing the construction with phytoremediation will also

    ensure proper landscaping for the environmental aesthetics of the site.

  • 8/13/2019 Zhen Hau Sing - Feasibility & Treatability Study

    56/59

    10-7

    The off-site dredging process on the Buffalo River will take up to 10 days. The barge

    would first be brought in and situated at a location ideal for the dredged materials to be

    rested. The backhoe is next brought in to begin the dredging process. Once completed, the

    materials on the barge are transported to the confined disposal facility for proper

    treatment.

    Vapor Remediation Discussion and Proper Transportation/Trucking.

    It is important to note that in the remedy, there were no technologies selected for on-

    site vapor remediation. This is due to the fact that technologies used will not produce or

    expose vapor contamination to the atmosphere. The reduction of chlorobenzene through

    excavation immediately reduced the potential vapor contamination.

    During excavation however, proper anti-contamination clothing would need to be worn

    by workers and engineers at all times. This is to prevent potential inhalation of the DNAPL

    that will be potentially dug up. PID monitors would also need to be installed on site and

    engineers/technicians would be required to carry PID readers at all times.

    The excavated soil would also need to be transported in tightly/properly sealed trucks

    to avoid exposure to the residential area as it moves towards the treatment facility. The

    trucks and other construction equipment would also need to washed down on-site before

    entering other community areas.

  • 8/13/2019 Zhen Hau Sing - Feasibility & Treatability Study

    57/59

    10-8

    In the long run, vapor remediation will be taken into account. As in the preliminary

    technology screening, remedies that prevented vapor instruction in buildings were

    retained. This would be the vapor remedial solution if the BCC site were to be used as a

    commercial or industrial area with new buildings. Passive barriers/vents will hinder and

    deviate the routes of contaminated vapor from entering the cracks of foundations.

    Depressurization systems in the basements will reduce pressure build up in the sub-slab of

    the buildings. This will reduce or eliminate the driving force that facilitates vapor intrusion

    (CLU-IN, 2011)

  • 8/13/2019 Zhen Hau Sing - Feasibility & Treatability Study

    58/59

    11-1

    11 CreditsWORK PERSON

    Executive summary Zhen Hau Sing and Micheal

    Dietrich

    Scope of the Problem Zhen Hau Sing

    Background Michael Dietrich

    RAOs Mubeccel Begum Ilya

    Treatability Summary ISCO-Michael

    EIBR-Mubeccel

    Phyto-Zhen

    PRBMichael

    Dredge- MubeccelAlternative Review Group work

    Effectiveness and Implementability Zhen Hau Sing

    No Action Remedy Zhen Hau Sing

    Combined Remedy Michael Dietrich

    Community Relations Mubeccel Begum Ilya

    Ecological Habitat Mubeccel Begum Ilya

    Final Editing and Direction Michael Dietrich

  • 8/13/2019 Zhen Hau Sing - Feasibility & Treatability Study

    59/59

    12 ReferencesPhytotechnologies. (2012, November 7). Retrieved March 12,

    2013, from http://clu-in.org/techfocus/default.focus/sec/Phytotechnologies/cat/Overview/

    Hybrid Poplar. (2013). Retrieved March 20, 2013, from Arborday:

    http://www.arborday.org/treeguide/treeDetail.cfm?id=31Outside Price. (2013). Retrieved March 21, 2013, from Lupine

    Seeds-Noble Maiden:http://www.outsidepride.com/seed/flower-seed/lupine/lupine-noble-maiden.html

    Weeping Willow. (2013). Retrieved March 20, 2013, fromArborday:

    Baptista, R. J. (2009). National Aniline and Chemical CompanyBuffalo, New York. Retrieved from Colorants History.

    Brown, C. E. (2006). Polycyclic Aromatic Hydrocarbons in theSoil. Sources, Health Effects, Clean-Up Techniques and

    PAHs at Alameda Point.CLU-IN. (2011, August 26). Contaminant Focus. Retrieved from

    Clean Up Information (CLU-IN.org): http://www.clu-in.org/contaminantfocus/

    Cummings, J. (2013). Soil Vapor Extraction. Retrieved from Clu-in: http://www.clu-in.org/techfocus/default.focus/sec/Soil_Vapor_Extraction/cat/Overview/

    Engineering-Science. (1986). Engineering Investigations atInactive Hazardous Waste Sites.Liverpool: Engineering-Science.

    EPA. (1988). Guidance for Conducting Remedial Investigationand Feasibility Studies under CERCLA.Washington DC:

    Office of Emergency and Remedial Response.EPA. (1993). Selecting Remediation Techniques forContaminated Sediment.Cincinnati, OH: Office of Water.

    EPA. (1995). How To Evaluate Alternative CleanupTechnologies For Underground Storage Tank Sites: A GuideFor Corrective Action Plan Reviewers, In-Situ GroundwaterBioremediation.

    EPA. (2002).Arsenic Treatment Technologies for Soil, Waste,and Water.Washington, DC: clu-in.org.

    EPA. (2002). Enhanced In-situ Bioremediation of Solvents inGroundwater.Interstate Technology and regulatory Council.

    EPA. (2007). Treatment TechnologiesFor Mercury in Soil,Waste,and Water.Washington DC: clu-in.org.

    EPA. (2012).A Citizen's Guide to Bioremediation, ChemicalOxidation, and Phytoremediation.

    EPA. (2013). Basic Information about Regulated Drinking WaterContaminants and Indicators. Retrieved fromhttp://water.epa.gov/drink/contaminants/basicinformation/

    ESTCP. (2005). Bioaugmentation for Remediation of ChlorinatedSolvents: Technology Development Status and Research

    Needs.Environmental Security Technology CertificationProgram.

    Fayiga, A. O. (2005). Phytoremediation of Arsenic ContaminatedSoil and Groundwater.University of Florida.

    Henry, J. (2000).An Overview of the Phytoremediation of Leadand Mercury.National Network of EnvironmentalManagement Studies.

    Honeywell International. (2011). History - Buffalo Research Lab.Retrieved Febuary 2013, from Honeywell:http://www.honeywell-buffalo.com/history.php

    Huling, S. B. (2006). In-Situ Chemical Oxidation.Cincinnati, OH:EPA.

    ICSS. (2006). Manual for Biological Remediation Techniques.

    International Centre for Soil and Contaminated Sites.Licht, L. (1990). Deep-Rooted Poplar Tree Buffers for Biomass

    Production and Nitrate Removal.US Department ofAgriculture.

    Mactec. (2010). Treatability Studies for Buffalo Color sites C andE excepts.

    Mandalinsk, K. (2008). In Situ Technologies for the Remediationof Contaminated Solvents.Washington DC: EPA .

    NYSDEC. (1999). Technical Guidance for ScreeningContaminated Sediments.Albany: New York StateDepartment of Environmental Conservation.

    NYSDEC. (2013). 2. INDEX OF STANDARDS, CRITERIA ANDGUIDANCE (SCGs) USED FOR APPLYING THE CRITERIA.

    Retrieved from New York State of EnvironmentalConservation.: http://www.dec.ny.gov/regulations/61794.htmlNYSDEC. (2013). Chemical and Pollution Control. Retrieved from

    http://www.dec.ny.gov/25.htmlNzengung, V. A. (2005). Case Studies of Phytoremediation of

    Petrochemicals and Chlorinated Solvents in Soil andGroundwater.University of Georgia.

    Osgerby, I. (2008). Persulfate to Chlorobenzenes in Glacial Tilland Bedrock.

    Parsons. (2004). Principles and Practices of Enhanced AnaerobicBioremediation of Chlorinated Solvents.AFCEE.

    Roote, C. a. (1998). Technology Overview Report,( In SituBioremediation, Cauwenberghe and Roote, Ground-WaterRemediation).GWRTAC.

    Shin, D. G. (2001). Selecting and Using Phytoremediation for SiteCleanup.Continuing Education and Development Inc.