lanjut 2ok

download lanjut 2ok

of 9

Transcript of lanjut 2ok

  • 7/26/2019 lanjut 2ok

    1/9

    The issues in the road transport sector fall into three broad

    categories. First ,provision of the road network has been

    madequate . Provincial and kabupaten roads are in poor

    condition . congestion is a signicant problem , and access to

    rular communities is low. Many factors contribute to poorprovision of the road network. Funding is inadequate and

    unpredictable, hich is e!acerbated by the fact that e!penses

    are misallocated. "nd the works that are allocated funds are

    generally e!pensive and of low quality. #econd. $se of the road

    network is ine%cient. &haracteri'ed by overloading, suboptimal

    use and a lack of tra%e safety. (astly , institutions and the legal

    framework. )specially with toll roads. "re weak.

    *nadequate Provision +f The oad -etwork

    ".Poor &ondition of the network

    hile central funding has been adequate for keeping the

    national artenal network in sausfactory and sustainable

    condition. There is a backlog of preservation and upgrading

    needs on the provincial network and a very large backlog on the

    kabupaten network . ia the absence of budget and

    unplementation constraints . the /000 #)PM analysis medicates

    that e!penditures on road preservation should mercase sharpy

    down then level of circa p. 1,2 million to nance a massive

    program of betterment followed by a sharp decline in

    e!penditures once the ma3or part of the network is in a stable

    muntainable condition. The unconstrained /004 budget in /000prices was estimated at circa p /4 million. ith e!penditures

    in subsequent yeats fallingto circa p 45 million in /00/ and to

    less than p 1 trillion in /005. +ver a ten6year periode. The

    analysis indicates an average budged of circa p 7 8 7,2 trillion.

    )%ciently allocated. ould be needed to bering the network to

    an optimal condition. The computed relationship between

    average road agency e!penditures and road user costs foralternative budged constraints 9406year averages: is shown in

    Table 4/. " further analysis of Table 4/ is found in oad "nne!

    4.

    ;. &apacity )!pansion -eeds in

  • 7/26/2019 lanjut 2ok

    2/9

    Managing the increase in tra%c demand that results from

    economic growth requires a systematic investman in e!pansion

    of network capacity and improvements in tra%c management.

    =eferral of a susbstantial program of upgrading at the time of

    the nancial crisis and the subsequent resumption of tra%cgrowth have resulted in very pressing needs to e!pand the

    capacity of sections of the arterial road network. ava , where it is

    estimated that at least /10 km of capacity e!pansion per year

    is ecconomucally 3ustied through /040 , which is 50? higher

    than similar estimates in 4@@A.

    "ll the ma3or urban areas are sub3ect severe tra%c congestion

    and this is a growing problem for the smaller satellite towns.

    $rban tra%c Bowshave continued to increase rapidly, despite

    the nancial crisis. Private motor vehicle use has grown

    particularly fats, following liberali'ation of motor vehicle import

    regulation. "tmospheric pollution is a serious problem in the

    large cities 9in the 4@@0s >akarta was ranked the third most

    polluted mega6city in the world:6 and is an rapidly emerging

    concern for the ne!t level of cities. Cehicle emissions are

    considered to contribute much to local levels of pollution and

    the use of leaded gasoline has been ma3or concern.

    &.(ow "ccess for emote &ommunities

    $ncompetitive procurement results in high costs and poor

    performance of construction and maintenance works. " surveyof preservation works on national and provincial roads carried

    out during the late 4@@0s recently relaved that /2? were

    performing signicantly less well than designed and reching a

    critical condition at least 50? earlier than pro3ected

    &orruption, collusion and nepotism remain pervasive in the

    construction industry and contribute substantially to theproblem. &ollusion between bidders and o%cials undermines

    competition, leading to the higher initial prices and losses

    estimated at 40650?.

  • 7/26/2019 lanjut 2ok

    3/9

    hen this weakens supervision control ovr the quality of work,

    the consequent under performance can increase losses to in the

    order of 10?. The impact is even more negative when poor

    supervision performance on the part of public authorities,

    particularly at the kabupaten level, also signicantly diminishesthe eDectiveness of maintenance resulting in premature road

    deterioration, e!cessive vehicle operating costs and a greater

    need for costly rehabilitation.

    eform in the areas can give rise to substantial direct saving

    together with even greater indirect benets through reduced

    vehicle operating costs as a result of the improved conditionnetwork.

    *ne%cient use of the road network

    a. Cehicle overloadingThe enforcement of vehicle loading and dimension

    regulations in *ndonesia is very weak, with between 50 8400 ? of heavy vehicles overloaded 8 such vehicle is

    overloading has been estimated to increase road

    preservation costs by between /0670? . as long ago as

    4@E4 government close all roadside weighbridges due to

    their being ineDective and functioning primarily as collection

    points for illegal levies. Most have since been else has

    changed. Cisual observation conrm that the problem

    remains very serious and is possibly worsening. *n

    sumatera trucks transport logs that overhang far beyond the

    permitted the limit. *n 3ava hungry boardsG are used to

    enable trucks to carry e!cessive volumes of sand ad

    aggregates. #imilarly in >akarta, ready6mi! concrete trucks

    are tted with drums that are much larger than the volume

    stated on the vehicle documents, many overload trucks

    en3oy military or police protection and indeed many areoperated by military or police cooperatives.

    b. #ub6optimal utili'ation of e!isting

    road network capacitywith budget constraints limiting the scope for road capacity

    e!pantion investments, it will be essential in the medium

    term to ma!imi'e utili'ation of e!isting capacity. "t present,

  • 7/26/2019 lanjut 2ok

    4/9

    serious congestion, which greatly increases road user costs,

    is commonly caused by poor tra%c engineering and tra%c

    management, especially at intersections, by roadside

    activities such as markets that impede tra%c Bow, by slow6

    moving vehicles that are overload, under powered orunsafe, and by poor driver behavior. *n some areas,

    problems are compounded by poor public transport route

    licensing practices that allow the operation of e!cessive

    numbers of small pick6ups and that require these to pass

    through badly located and managed terminals for the

    primary purpose of revenue generation.

    #ome basic tra%c management measures such as tra%clights and one wayG streets are applied in most urban areas.

    To date there have been rather limited attempts to introduce

    more sophisticated tra%c management measures such as

    segregated tra%c, tidal BowG lanes and variable geometry

    at roundabouts. The very substantial needs for improved

    regulation and management of urban transport as well as

    for capital investment must be assessed in the comple!contect of urban management planning.

    c.Poor road tra%c safetyoad tra%c accidents cause around /2 deaths per day in

    *ndonesia and give rise to substantial material costs. oad

    accidents impose an estimated cost of 4.2? of H=P. The

    number of reported fatalities has declined in recent years,

    falling from circa 44,E00 in 4@@E to E.A7/ in /00/. Thenumber of fatalities per 40.000 registered vehicles is

    relatively high at 1.2. poor public and driver education

    coupled with la! driver testing procedures for drivers of

    public transport and heavy goods vehicles, are important

    factors. They are compounded by weak enforcement of

    safety related tra%c regulations, ineDectual instpection of

    motor vehicle condition, which is currently required only for

    commercial vehicles and poor road and intersection

    geometry and signing. *n some instances, notably driver and

    vehicle testing, corruption recogni'ed to be a signicant

    underlying factor.

  • 7/26/2019 lanjut 2ok

    5/9

    *nformation on the causes and consequences of the tra%c

    accidents is poor. *n part because it has taken more than a

    decade to secure inter6agency agreement on the adoption of

    an improved tra%c accident reporting and data processing

    system whose implementation is only now commencing on apilot basis. +%cial statistics are believed to understate

    actucal number of fatalities . in part because deaths

    occurring more than /1 hours after an accident are often not

    included.

    *nadequate institutional and regulatory framework for toll

    roads

    The limited interest now being shown in the toll road sectorby serious private investors is attributable to several factors

    aside from the overall investment climate. Prominent among

    them are concern regarding the concessions award process

    and the multiple rolcs assigned to 3asa marga 9which

    operated: as a toll road developer, an agent of development

    required by the government to construct roads that are not

    commercially viable, and as a counter 8party for

    concessions agreements with private developers or as a

    3oint venture partner for such developers:, the absence of

    an agreed mechanism for ad3usting tolls to reBect changes

    in cost not controllable by developers, the requirement for

    developers to be responsible for the costs of land acquisition

    in the absence of functioning eminent domain powers, slow

    progress in the resolution of e!isting concessions, and the

    absence of a soundly based and update toll road master 8plan on which to prepare meaningful feasibility studies.

    C**. Th) ay Forward

    Hovernment has recogni'ed and has been seeking to tackle

    the core problems impeding the e%cient functioning of the

    road sector for more than two decades. hile some

    initiatives have borne fruit, the pverall pace of progress has

    been disappointingly slow.The resultant costs6 for the budget and for road users6

    amount to several trillions of rupiah per year. These are real

    costs that impact the performance of the economy and

    impede eDorts to alleviate poverty. " fundamental

  • 7/26/2019 lanjut 2ok

    6/9

    rethinking on the way in which the sector is managed and

    regulated is clearly needed.

    *mprove road network provisiona. )!pand and e!tend network

    managing the increase in tra%c demand that results fomeconomic growth requires a systematic investment in

    e!pansion of network capacity and improvements in tra%c

    and demand management. Programs of priority

    investment on the core section of the network should be

    identied , particularly those that may be suitable for

    private investment.

    " recent study for 3avaGs arterial road network indentied

    the growing congestion and concluded that I6 ;y around /00A, all primary arterial and collector links of

    less than A meters width should be widened to A meters6 ;y /050, the entire arterial road network should be

    developed to a 16lane standard.

    " preliminary screening process identied a program ofeconomically warranted upgrading pro3ects amounting

    to p. 407 trillion at /000 prices over the period /0006

    /050. +f this total , p.1,2 trillion is for widening to a A6

    meter /6lane unseparated standard 9 uA:, p.51,7

    trillion is for widening to 16lane dual camageway

    standard on e!isting alignments 91=:, and p.77,A

    trillion is for construction of new 16lane dual carriageway

    limited access roads 9("-:. The criteria for including

    investment in the program was a rst year economic

    rate of return of /0? or greater, which is estimated to

    equated to an )* of over 10? with the pro3ected tra%c

    growth rates. "s shown in gure 1. The premilinary

    screening indicated that further investments in new 16

    lane dual carriageway inter6urban limited access road

    would not be 3ustied prior to /042. ava massively e!ceed past levels of funding for all new

  • 7/26/2019 lanjut 2ok

    7/9

    construction works 9see Table 7:. The studyGs

    recommended e!penditure program for the period /00/6

    /040 was prepared on the basis that funding available

    for >ava capacity e!pansion works would increase

    progressively from p.0.2 trillion in /00/ to p.4.0trillionin /00A and remain at that level through /040,

    with the total budged over the period being p 7.1

    trillion. This necessarily involves deferring many pro3ects

    with high rates of return. )quivalent studies have yet to

    be conducted for other island groups. hile their

    collective capacity e!pansion needs will not he as large

    as those for >ava, they will nonetheless be signicant

    and 3ustify substantial investment

    b.*mprove "ccess to emote &ommunitiesThere is a need to e!tand the all6season road network in

    order to provide reliable access for the @ ?of the rural

    population which is not directly connected.

  • 7/26/2019 lanjut 2ok

    8/9

    6 )stablish criteria lot &entral Hovernment support for

    e!tending the network in the conte!tof the poverty

    eduction #trategy6 )nsure that decistoas to e!tend the network take

    adequate account of the e!pected recurrent costumplications llost mainting the new road links6 emove Hovernment intluence from +H"-=", the

    *ndonesian oad Transport +peratorGs association and

    encourage the "ssociation to represent its members

    interests more eDectively

    *n order to eDectively implement the recommendationsabove, the following are required

    a.#tabili'ed the Funding for oad "ssetsManaging road assets is an e!pensive business, and

    while roads are seen as pblic good, they are competing

    for public e!penditures with other sectors on the basis of

    outputs which are di%cult to compare. $nder the public

    e!penditure model, the road networks have beenunevenly funded or under6funded 8 the economic needs6

    based estimate for preservation of satisfactory service

    on the primary networks is an average of *= 7.2 trillion

    annually 94@@@ values: with a gap in /000 of about *=

    /./ trillion, a 426/0 ? shortfall on provincial roads and

    50? shortfall on =istrict.

    *nstead, if the provision and preservation of road assetsis considered as a commercial service rather than a

    public good, the costs of preservation can be recovered

    through a fee charged to road users for the services they

    receive. oad users are playing about *= //0 trillion

    annually in operating costs, and the added costs they

    incur through the underfunding on roads is estimated to

    be about *= 7 trillion ,or three times the funding gap. *f

    the nancing of road preservation was put on a fee6for6

    service basis, users may pay an additional *= /./ trillion

    but they would have net savings of double that amount.

    $nder a commercial service model, the full economic

    costs of road preservation would be recovered from

  • 7/26/2019 lanjut 2ok

    9/9

    users and invested in the road assets, in a similar way to

    the operation of unlities such as telephones or electric

    power. "doption of this costs recovery model could place

    the management of road assets on a fully sustainable

    basis which does not impose on general publice!penditures. ;ecause the revenue would keep pace

    with the e!penditure needs, provided that the funds

    were invested back in the assets e%ciently. *n essence

    the funds would pass through from road user revenues

    to the budget for road e!penditures 8and eventually.

    ith the appropriate controls, could be managed oD6

    budget.

    +D6 budget road funds nanced by predictable revenue

    streams from user chargers have proven eDective in

    many countries. Particularly where they are part of a

    broader strategy for managing roads on a business6like

    fee6for6service basis. oad fund revenues should be

    sourced from specic road user charges. -ot from

    general ta! revenue, and its claim to these revenuesshould be established in law. The level of revenues

    should be su%cient to nance the works and services

    needed to improve and maintain the network to a

    satisfactory standard. hile the structure of users

    charges should provide incentives for economically

    sound vehicle purchase and operating decisions. oad

    preservation works would thus be nanced entirely oD6

    budget by users and without nancing from foreign

    loans.

    hen the subsidy on gasolinean "=+ is eliminated, road

    users will start to make a substantial contribution

    towards the costs of road preservation rehablition,

    routine and periode maintenance and limited

    betterment. evenues from the PJ; motor vehicle ta!.The P;;J; motor vehicle tuels ta!. "nd other ta!es on

    road users would be broadly in line with the desirable

    level of preservation e!penditures.

    The present structure of the e!isting road user charges is

    fas from that ideal, however