Lampiran III RKS no. 24/LL/NONSAR/KCI/II/2018 tanggal 13 Februari 2018 ANALISA HARGA BANGUNAN EDUKASI DEPO KRL DEPOK 1 1 m2 Pembuatan bedeng Bahan 1,25000 Btg Dolken kayu Ø 8-10 / 400 cm @ Rp. = Rp 0,18600 m3 Kayu Meranti Terentang/Meranti @ Rp. = Rp 0,30000 kg Paku biasa 2" - 5 " @ Rp. = Rp 18,00000 kg Semen Portland @ Rp. = Rp 0,03000 m3 Pasir beton @ Rp. = Rp 0,05000 m3 Koral beton @ Rp. = Rp 1,50000 Lbr Seng gelombang bljs 32 @ Rp. = Rp 1,35000 Lbr Multipleks 9 mm @ Rp. = Rp Sub total : = Rp Dibulatkan : = Rp Upah 2,00000 Oh Tukang Kayu @ Rp. = Rp 1,00000 Oh Pekerja @ Rp. = Rp 0,20000 Oh Kepala Tukang @ Rp. = Rp 0,05000 Oh Mandor @ Rp. = Rp Sub total : = Rp Dibulatkan : = Rp 2 Saftey APD Bahan 1,00000 bh rompi spotlight Rp. = Rp. 1,00000 bh helm Rp. = Rp. 1,00000 bh safety shoes Rp. = Rp. 1,00000 bh Sarung Tangan Rp. = Rp. = Rp. = Rp 3 Transportasi Alat dan pekerja/hari Upah 1,00000 hr Sewa Pick Up @ Rp. = Rp = Rp = Rp 4 Listrik TDR PLN Upah 3,50000 Kva Listrik TDR-PLN @ Rp. = Rp = Rp 5 1 m2 Pembersihan Lapangan dan Peralatan Upah 0,10000 Oh Pekerja @ Rp. = Rp 0,05000 Oh Mandor @ Rp. = Rp = Rp = Rp 6 BONGKAR PAVING EXSISTING/M2 Upah. 0,16000 oh Pekerja @ Rp. = Rp. 0,05000 oh Tukang batu @ Rp. = Rp. 0,00500 oh Kepela tukang batu @ Rp. = Rp. 0,00750 oh Mandor @ Rp. = Rp. = Rp. = Rp. 7 BONGKARAN TAMAN M2 Upah. 0,16000 oh Pekerja @ Rp. = Rp. 0,05000 oh Tukang batu @ Rp. = Rp. PEKERJAAN BANGUNAN EDUKASI DIPO KRL DEPOK Sub Total : Dibulatkan : Sub total : Dibulatkan : Dibulatkan : Sub total : Dibulatkan : Sub total : Dibulatkan :

Transcript of Lampiran III RKS no. 24/LL/NONSAR/KCI/II/2018 tanggal 13 ... · Lampiran III RKS no....

Lampiran III RKS no. 24/LL/NONSAR/KCI/II/2018 tanggal 13 Februari 2018

ANALISA HARGA BANGUNAN EDUKASI DEPO KRL DEPOK

1 1 m2 Pembuatan bedeng

Bahan

1,25000 Btg Dolken kayu Ø 8-10 / 400 cm @ Rp. = Rp

0,18600 m3 Kayu Meranti Terentang/Meranti @ Rp. = Rp

0,30000 kg Paku biasa 2" - 5 " @ Rp. = Rp

18,00000 kg Semen Portland @ Rp. = Rp

0,03000 m3 Pasir beton @ Rp. = Rp

0,05000 m3 Koral beton @ Rp. = Rp

1,50000 Lbr Seng gelombang bljs 32 @ Rp. = Rp

1,35000 Lbr Multipleks 9 mm @ Rp. = Rp

Sub total : = Rp

Dibulatkan : = Rp

Upah

2,00000 Oh Tukang Kayu @ Rp. = Rp

1,00000 Oh Pekerja @ Rp. = Rp

0,20000 Oh Kepala Tukang @ Rp. = Rp

0,05000 Oh Mandor @ Rp. = Rp

Sub total : = Rp

Dibulatkan : = Rp

2 Saftey APD

Bahan

1,00000 bh rompi spotlight Rp. = Rp.

1,00000 bh helm Rp. = Rp.

1,00000 bh safety shoes Rp. = Rp.

1,00000 bh Sarung Tangan Rp. = Rp.

= Rp.

= Rp

3 Transportasi Alat dan pekerja/hari

Upah

1,00000 hr Sewa Pick Up @ Rp. = Rp

= Rp

= Rp

4 Listrik TDR PLN

Upah

3,50000 Kva Listrik TDR-PLN @ Rp. = Rp

= Rp

5 1 m2 Pembersihan Lapangan dan Peralatan

Upah

0,10000 Oh Pekerja @ Rp. = Rp

0,05000 Oh Mandor @ Rp. = Rp

= Rp

= Rp

6 BONGKAR PAVING EXSISTING/M2

Upah.

0,16000 oh Pekerja @ Rp. = Rp.

0,05000 oh Tukang batu @ Rp. = Rp.

0,00500 oh Kepela tukang batu @ Rp. = Rp.

0,00750 oh Mandor @ Rp. = Rp.

= Rp.

= Rp.

7 BONGKARAN TAMAN M2

Upah.

0,16000 oh Pekerja @ Rp. = Rp.

0,05000 oh Tukang batu @ Rp. = Rp.

PEKERJAAN BANGUNAN EDUKASI DIPO KRL DEPOK

Sub Total :

Dibulatkan :

Sub total :

Dibulatkan :

Dibulatkan :

Sub total :

Dibulatkan :

Sub total :

Dibulatkan :

Lampiran III RKS no. 24/LL/NONSAR/KCI/II/2018 tanggal 13 Februari 2018

0,00500 oh Kepela tukang batu @ Rp. = Rp.

0,00750 oh Mandor @ Rp. = Rp.

= Rp.

= Rp.

10 Sewa alat bantu scafoldhing

Bahan

2,00000 bh Main Frame 190 cm @ Rp. = Rp

2,00000 bh Crose Brase 190 cm @ Rp. = Rp

4,00000 bh Join Pint @ Rp. = Rp

1 unit scafolding 1 x @ Rp. = Rp

1,00000 bh Cat Walk @ Rp. = Rp

4,00000 bh Roller Catter / roda @ Rp. = Rp

= Rp

= Rp

11 1 m2 Bongkaran dinding tembok bata merah

Upah

0,25000 Oh Pekerja @ Rp. = Rp

0,03300 Oh Mandor @ Rp. = Rp

= Rp

= Rp

12 1 m2 Pek.Bongkaran Partisi, Plafond, Jendela Kaca, Pintu Kaca, Dll

Upah

0,25000 Oh Pekerja @ Rp. = Rp

0,03300 Oh Mandor @ Rp. = Rp

= Rp

= Rp

13 1 m2 Bongkaran lantai kramik

Upah

0,15000 Oh Pekerja @ Rp. = Rp

0,03300 Oh Mandor @ Rp. = Rp

Sub total : = Rp

= Rp

14 1 m2 Pasangan bata merah tebal 1/2 bata, 1 Pc : 3 Ps

Bahan

70,0000 Bh Bata merah 5 x 11 x 22 cm @ Rp. = Rp

14,3700 Kg Semen portland @ Rp. = Rp

0,0400 m3 Pasir pasang @ Rp. = Rp

Sub total : = Rp

Dibulatkan : = Rp

Upah

0,3200 Oh Pekerja @ Rp. = Rp

0,1000 Oh Tukang batu @ Rp. = Rp

0,0100 Oh Kepala tukang @ Rp. = Rp

0,0150 Oh Mandor @ Rp. = Rp

Sub total : = Rp

Dibulatkan : = Rp

15 1 m2 Plesteran, 1 Pc : 3 Ps, tebal 15 mm

Bahan 6,4800 Kg Semen portland @ Rp. = Rp

0,0190 m3 Pasir pasang @ Rp. = Rp

Sub total : = Rp

Dibulatkan : = Rp

Upah

0,2000 Oh Pekerja @ Rp. = Rp

Dibulatkan :

Dibulatkan :

Sub total :

Dibulatkan :

Sub total :

Sub Total :

Dibulatkan :

Sub Total :

Dibulatkan :

Lampiran III RKS no. 24/LL/NONSAR/KCI/II/2018 tanggal 13 Februari 2018

0,1500 Oh Tukang batu @ Rp. = Rp

0,0150 Oh Kepala tukang @ Rp. = Rp

0,0100 Oh Mandor @ Rp. = Rp

Sub total : = Rp

Dibulatkan : = Rp

16 1 m2 Pasang Sekat Dinding gypsum rangka metalstud/baja ringan

Bahan

0,4000 Lbr Gypsum board ( 120x240x9 mm ) @ Rp. = Rp

0,6700 ljr Truss C75.75 SNI BMT @ Rp. = Rp

0,0500 Kg Paku Skrup gypsum @ Rp. = Rp

0,4000 Kg kompon gypsum @ Rp. = Rp

= Rp

= Rp

= Rp

Upah

0,1000 Oh Pekerja @ Rp. = Rp

0,0500 Oh Tukang @ Rp. = Rp

0,0050 Oh Kepala tukang @ Rp. = Rp

0,0050 Oh Mandor @ Rp. = Rp

= Rp

= Rp

17 1 m2 Pasang plafon gypsum rangka metalstud/baja ringan

Bahan

0,4000 Lbr Gypsum board ( 120x240x9 mm ) @ Rp. = Rp

0,6700 Btg Truss C75.75 SNI BMT @ Rp. = Rp

0,0500 Kg Skrup gypsum @ Rp. = Rp

0,4000 Kg kompon gypsum @ Rp. = Rp

Sub total : = Rp

Dibulatkan : = Rp

Upah

0,1000 Oh Pekerja @ Rp. = Rp

0,0500 Oh Tukang @ Rp. = Rp

0,0050 Oh Kepala tukang @ Rp. = Rp

0,0050 Oh Mandor @ Rp. = Rp

Sub total : = Rp

Dibulatkan : = Rp

18 1 Bh. Pasang pintu aluminium 3" putih ( Silver) UKURAN 0.80 X 2.00 Mtr.

( pintu isian kaca bening 5mm dan multipleks 9 mm).

Bahan

6,2500 M1 Slimar Aluminium putih 3" @ Rp. = Rp

15,0000 M1 Karet penjepit kaca/ tripleks. @ Rp. = Rp

1,0000 set Engsel @ Rp. = Rp

1,0000 Bh Kunci @ Rp. = Rp

1,3400 M2 Kaca bening 5 mm @ Rp. = Rp

Sub total : = Rp

Dibulatkan : = Rp

Upah 1,4175 Oh Pekerja @ Rp. = Rp

1,4175 Oh Tukang besi @ Rp. = Rp

0,1418 Oh Kepala tukang besi @ Rp. = Rp

0,0070 Oh Mandor @ Rp. = Rp

Sub total : = Rp

Dibulatkan : = Rp

19 1M2 Pasang daun jendela aluminium 3" putih ( Silver) UKURAN 1.00 X 1.00 Mtr.

( Jendela isian kaca 5mm).

Bahan

4,8000 M1 Slimar Aluminium putih 3" @ Rp. = Rp

8,5000 M1 Karet penjepit kaca. @ Rp. = Rp

1,0000 set Engsel jendela. @ Rp. = Rp

1,0000 Bh Hak window. @ Rp. = Rp

0,9025 M2 Kaca bening 5 mm @ Rp. = Rp

= Rp

= Rp

Sub total 1 Sisi

Dua Sisi ( x 2 )

Dibulatkan

Sub total

Dibulatkan

Sub total :

Dibulatkan :

Lampiran III RKS no. 24/LL/NONSAR/KCI/II/2018 tanggal 13 Februari 2018

Upah 1,0500 Oh Pekerja @ Rp. = Rp

1,0500 Oh Tukang besi @ Rp. = Rp

0,1050 Oh Kepala tukang besi @ Rp. = Rp

0,0052 Oh Mandor @ Rp. = Rp

= Rp

= Rp

20 Partisi Lipat Kaca / M2

Bahan

12,0000 m Rangka besi Holo 40x40 @ Rp. = Rp.

1,7500 m2 Kaca Bening 8 mm @ Rp. = Rp.

1,8000 m2 Rockwool peredam @ Rp. = Rp.

8,0000 m1 List edging alumunium @ Rp. = Rp.

1,0000 Psg Roda @ Rp. = Rp.

1,0000 m1 Rel bagian atas @ Rp. = Rp.

6,4000 m1 Karet penjepit kaca @ Rp. = Rp.

1,0000 Set Alat bantu penggantung rel atas @ Rp. = Rp.

1,0000 Bh Pengunci pintu @ Rp. = Rp.

Sub total : = Rp.

Dibulatkan : = Rp

Upah 1,4175 Oh Pekerja @ Rp. = Rp

1,4175 Oh Tukang besi @ Rp. = Rp

0,1418 Oh Kepala tukang besi @ Rp. = Rp

0,0070 Oh Mandor @ Rp. = Rp

Sub total : = Rp

Dibulatkan : = Rp

21 1 M' Pasang kusen aluminium 4" putih. (Silver)

Bahan

1,1000 m Aluminium putih 4". @ Rp. = Rp

= Rp

= Rp

Upah 0,1040 Oh Pekerja @ Rp. = Rp

0,1040 Oh Tukang besi @ Rp. = Rp

0,0010 Oh Kepala tukang besi @ Rp. = Rp

0,0005 Oh Mandor @ Rp. = Rp

= Rp

= Rp

22 1M2 Pasang Kaca Bening Tebal 8 mm

Bahan

8,5000 M1 Karet penjepit kaca. @ Rp. = Rp

0,9025 M2 Kaca bening 8 mm @ Rp. = Rp

Sub total : = Rp

Dibulatkan : = Rp

Upah 0,1040 Oh Pekerja @ Rp. = Rp

0,1040 Oh Tukang besi @ Rp. = Rp

0,0010 Oh Kepala tukang besi @ Rp. = Rp

0,0001 Oh Mandor @ Rp. = Rp

Sub total : = Rp

Dibulatkan : = Rp

23 1 m2 Pasang Sand Blast / Kaca Sticker

Bahan

1,10000 m2 Kaca Sticker @ Rp. = Rp

Dibulatkan : = Rp

Upah 0,01500 Oh Pekerja @ Rp. = Rp

0,15000 Oh Tukang besi @ Rp. = Rp

0,01500 Oh Kepala tukang besi @ Rp. = Rp

0,00075 Oh Mandor @ Rp. = Rp

Sub total : = Rp

Dibulatkan : = Rp

24 1 m2 Pasang GRANIT 60 x 60 cm

Bahan

1,0500 m2 GRANIT 60 x 60 Cm @ Rp. = Rp

1,0625 Kg Semen portland @ Rp. = Rp

0,0028 Kg Kapur bubuk @ Rp. = Rp

0,0420 m3 Pasir pasang @ Rp. = Rp

Dibulatkan :

Dibulatkan :

Sub total :

Sub Total :

Dibulatkan :

Sub total :

Lampiran III RKS no. 24/LL/NONSAR/KCI/II/2018 tanggal 13 Februari 2018

0,2000 Kg Semen warna @ Rp. = Rp

Sub total : = Rp

Dibulatkan : = Rp

Upah

0,2200 Oh Pekerja @ Rp. = Rp

0,1000 Oh Tukang batu @ Rp. = Rp

0,0120 Oh Kepala tukang @ Rp. = Rp

0,0125 Oh Mandor @ Rp. = Rp

Sub total : = Rp

Dibulatkan : = Rp

25 1 m2 Pasang Granit uk 60x20 cm standar / Lis / Ban

Bahan 1,0000 m2 Granit 60x20 Standar cm @ Rp. = Rp

1,0625 Kg Semen portland @ Rp. = Rp

0,0028 m3 Pasir pasang @ Rp. = Rp

0,1000 Kg Semen warna @ Rp. = Rp

Sub total : = Rp

Dibulatkan : = Rp

Upah

0,0900 Oh Pekerja @ Rp. = Rp

0,0900 Oh Tukang batu @ Rp. = Rp

0,0090 Oh Kepala tukang @ Rp. = Rp

0,0045 Oh Mandor @ Rp. = Rp

Sub total : = Rp

Dibulatkan : = Rp

26 1 m' Pasang list gypsum

Bahan

1,1000 m List profil kamper 4x1 cm @ Rp. = Rp

0,0100 Kg Paku @ Rp. = Rp

Sub total : = Rp

Dibulatkan : = Rp

Upah

0,0500 Oh Pekerja @ Rp. = Rp

0,0500 Oh Tukang kayu @ Rp. = Rp

0,0050 Oh Kepala tukang @ Rp. = Rp

0,0030 Oh Mandor @ Rp. = Rp

Sub total : = Rp

Dibulatkan : = Rp

27 1 m2 Pengecatan tembok Lama ( Ngamplas, 1x cat dasar, 2x cat penutup ) Watershild

Bahan

0,0100 Kg Plamir @ Rp. = Rp

0,1200 Lbr Ampelas @ Rp. = Rp

0,0333 Bh Kuwas / roll @ Rp. = Rp

0,1100 Kg Cat dasar ( Tembok ) @ Rp. = Rp

0,2200 Kg Cat penutup 2x ( Tembok ) @ Rp. = Rp

Sub total : = Rp

Dibulatkan : = Rp

Upah

0,0280 Oh Pekerja @ Rp. = Rp

0,0420 Oh Tukang cat @ Rp. = Rp

0,0042 Oh Kepala tukang @ Rp. = Rp

0,0025 Oh Mandor @ Rp. = Rp

. Sub total : = Rp

Dibulatkan : = Rp

28 1 m3 Galian Untuk Tanah Biasa sedalam 2 m

Upah 0,52600 Oh Pekerja @ Rp. = Rp

0,05200 Oh Mandor @ Rp. = Rp

Sub total : = Rp

= Rp

29 1 m3 Urugan Tanah

Bahan

1,20000 m3 Tanah Merah @ Rp. = Rp

= Rp

= Rp

Upah

0,19200 Oh Pekerja @ Rp. = Rp

0,01900 Oh Mandor @ Rp. = Rp

Sub total :

Dibulatkan :

Dibulatkan :

Lampiran III RKS no. 24/LL/NONSAR/KCI/II/2018 tanggal 13 Februari 2018

Sub total : = Rp

Dibulatkan : = Rp

30 1 m3 Urugan pasir dengan pasir urug.

Bahan

1,20000 m3 Pasir urug @ Rp. = Rp

= Rp

= Rp

Upah

0,30000 Oh Pekerja @ Rp. = Rp

0,01000 Oh Mandor @ Rp. = Rp

= Rp

= Rp

31 Sewa Stamper Untuk Pemadatan/hari

Upah

1,0000 hr Stamper @ Rp. = Rp

Dibulatkan : = Rp

32 1 m3 Pemadatan tanah

Upah

0,5000 Oh Pekerja @ Rp. = Rp

0,0500 Oh Mandor @ Rp. = Rp

Sub total : = Rp

Dibulatkan : = Rp

33 1 m3 Membuat beton bertulang 150 Kg besi + bekisting

Bahan

0,2000 m3 Kayu terentang/Meranti 5/7 @ Rp. = Rp

1,5000 Kg Paku biasa 2" - 5" @ Rp. = Rp

0,4000 Ltr Minyak bekisting @ Rp. = Rp

150,0000 Kg Besi beton polos D 12 @ Rp. = Rp

2,2500 Kg Kawat bendrat @ Rp. = Rp

323,0000 Kg Semen portland @ Rp. = Rp

0,5200 m3 Pasir beton @ Rp. = Rp

0,7800 m3 Koral beton @ Rp. = Rp

Sub total : = Rp

Dibulatkan : = Rp

Upah

3,9000 Oh Pekerja @ Rp. = Rp

0,3500 Oh Tukang batu @ Rp. = Rp

1,0400 Oh Tukang kayu @ Rp. = Rp

1,0500 Oh Tukang besi @ Rp. = Rp

0,2450 Oh Kepala tukang @ Rp. = Rp

0,1650 Oh Mandor @ Rp. = Rp

Sub total : = Rp

Dibulatkan : = Rp

34 1 m3 Pasang pondasi batu kali 1 Pc : 3 Ps

Bahan

1,1000 m3 Batu belah ( 15/20 ) @ Rp. = Rp

202,0000 Kg Semen porland @ Rp. = Rp

0,4850 m3 Pasir pasang @ Rp. = Rp

Sub total : = Rp

Dibulatkan : = Rp

Upah

1,5000 Oh Pekerja @ Rp. = Rp

0,6000 Oh Tukang batu @ Rp. = Rp

0,0600 Oh Kepala tukang @ Rp. = Rp

0,0750 Oh Mandor @ Rp. = Rp

Sub total : = Rp

Dibulatkan : = Rp

35 Memasang 1 m pipa PVC Rucika 4"

Bahan

Sub total :

Dibulatkan :

Dibulatkan :

Sub total :

Lampiran III RKS no. 24/LL/NONSAR/KCI/II/2018 tanggal 13 Februari 2018

1,2000 m Pipa PVC Rucika 4" @ Rp. = Rp

35,0000 % Perlengkapan @ Rp. = Rp

Sub total : = Rp

Dibulatkan : = Rp

Upah

0,0810 Oh Pekerja @ Rp. = Rp

0,1350 Oh Tukang batu @ Rp. = Rp

0,0135 Oh Kepala tukang @ Rp. = Rp

0,0041 Oh Mandor @ Rp. = Rp

Sub total : = Rp

Dibulatkan : = Rp

36 Memasang 1 buah floor drain

Bahan

1,00000 Bh Floor drain toto TX 1 AN @ Rp. = Rp

Sub total : = Rp

Dibulatkan : = Rp

Upah

0,01000 Oh Pekerja @ Rp. = Rp

0,10000 Oh Tukang batu @ Rp. = Rp

0,01000 Oh Kepala tukang @ Rp. = Rp

0,00500 Oh Mandor @ Rp. = Rp

Sub total : = Rp

Dibulatkan : = Rp

37 Pasang pipa besi 3" untuk cremona Dan Gording

Bahan

1,1000 m1 Pasang pipa Besi 3" @ Rp. = Rp

Sub total : = Rp

Dibulatkan : = Rp

Upah.

0,0700 Oh Pekerja @ Rp. = Rp

0,0700 Oh Tukang besi @ Rp. = Rp

0,0070 Oh Kepala tukang @ Rp. = Rp

0,0030 Oh Mandor @ Rp. = Rp

Sub total : = Rp

Dibulatkan : = Rp

38 Pasang pipa besi 6" untuk Batang Join

Bahan

1,1000 m1 Pasang pipa Besi 6" @ Rp. = Rp

Sub total : = Rp

Dibulatkan : = Rp

Upah.

0,0700 Oh Pekerja @ Rp. = Rp

0,0700 Oh Tukang besi @ Rp. = Rp

0,0070 Oh Kepala tukang @ Rp. = Rp

0,0030 Oh Mandor @ Rp. = Rp

Sub total : = Rp

Dibulatkan : = Rp

39 Pasang pipa besi 6" untuk Batang Kuda Kuda Lengkung + Bending

Bahan

1,1000 m1 Pasang pipa Besi 6" @ Rp. = Rp

1,1000 m1 Jasa Bending Pipa Besi 6" @ Rp. = Rp

Sub total : = Rp

Dibulatkan : = Rp

Upah.

0,0700 Oh Pekerja @ Rp. = Rp

0,0700 Oh Tukang besi @ Rp. = Rp

0,0070 Oh Kepala tukang @ Rp. = Rp

0,0030 Oh Mandor @ Rp. = Rp

Sub total : = Rp

Dibulatkan : = Rp

40 Pasang pipa besi 8" untuk Tiang Utama

Bahan 1,1000 m1 Pasang pipa Besi 8" @ Rp. = Rp

Sub total : = Rp

Dibulatkan : = Rp

Upah.

Lampiran III RKS no. 24/LL/NONSAR/KCI/II/2018 tanggal 13 Februari 2018

0,0700 Oh Pekerja @ Rp. = Rp

0,0700 Oh Tukang besi @ Rp. = Rp

0,0070 Oh Kepala tukang @ Rp. = Rp

0,0030 Oh Mandor @ Rp. = Rp

Sub total : = Rp

Dibulatkan : = Rp

41 Pasang pipa besi 10" untuk Tiang Utama ( Bentangan 14 m )

Bahan

1,1000 m1 Pasang pipa Besi 10" @ Rp. = Rp

Sub total : = Rp

Dibulatkan : = Rp

Upah.

0,0700 Oh Pekerja @ Rp. = Rp

0,0700 Oh Tukang besi @ Rp. = Rp

0,0070 Oh Kepala tukang @ Rp. = Rp

0,0030 Oh Mandor @ Rp. = Rp

Sub total : = Rp

Dibulatkan : = Rp

42 Pasang Plat Besi

Bahan

1,1000 Kg Plat Besi @ Rp. = Rp

Sub total : = Rp

Dibulatkan : = Rp

Upah.

0,0060 Oh Pekerja @ Rp. = Rp

0,0600 Oh Tukang besi @ Rp. = Rp

0,0060 Oh Kepala tukang @ Rp. = Rp

0,0003 Oh Mandor @ Rp. = Rp

Sub total : = Rp

Dibulatkan : = Rp

43 Pasang Baut M16 x 60 mm

Bahan

1,0000 Bh Baut M16 x 60 mm = Rp

Sub total : = Rp

Dibulatkan : = Rp

Upah.

0,0060 Oh Pekerja @ Rp. = Rp

0,0600 Oh Tukang besi @ Rp. = Rp

0,0060 Oh Kepala tukang @ Rp. = Rp

0,0003 Oh Mandor @ Rp. = Rp

Sub total : = Rp

Dibulatkan : = Rp

44 Pasang Angkur D 19 Panjang 60 cm

Bahan

1,0000 Bh Angkur D 19 Panjang 60 cm = Rp

Sub total : = Rp

Dibulatkan : = Rp

Upah.

0,0060 Oh Pekerja @ Rp. = Rp

0,0600 Oh Tukang besi @ Rp. = Rp

0,0060 Oh Kepala tukang @ Rp. = Rp

0,0003 Oh Mandor @ Rp. = Rp

Sub total : = Rp

Dibulatkan : = Rp

45 1 m2 Pasang atap spandex

Bahan 1,1000 Lbr Spandek @ Rp. = Rp

0,0500 Kg paku sekrup @ Rp. = Rp

Sub total : = Rp

Dibulatkan : = Rp

Upah

0,1000 Oh Pekerja @ Rp. = Rp

0,0500 Oh Tukang kayu @ Rp. = Rp

0,0050 Oh Kepala tukang @ Rp. = Rp

0,0050 Oh Mandor @ Rp. = Rp

Sub total : = Rp

Dibulatkan : = Rp

Lampiran III RKS no. 24/LL/NONSAR/KCI/II/2018 tanggal 13 Februari 2018

46 Pengelasan Las Listrik Untuk Tiap 10 cm / Titik

Bahan

0,4000 Kg Kawat Las @ Rp. = Rp

Sub total : = Rp

Dibulatkan : = Rp

Upah

0,0400 Oh Pekerja @ Rp. = Rp

0,0200 Oh Tukang Las @ Rp. = Rp

0,0020 Oh Mandor @ Rp. = Rp

Sub total : = Rp

Dibulatkan : = Rp

47 1 m Pasang talang datar rangka hollow, seng bjls 30

Bahan

0,5000 Lbr Seng plat @ Rp. = Rp

0,0150 Kg Paku Skrup @ Rp. = Rp

1,2000 btg Hollow 40 x 40 @ Rp. = Rp

Sub total : = Rp

Dibulatkan : = Rp

Upah

0,1500 Oh Pekerja @ Rp. = Rp

0,4000 Oh Tukang kayu @ Rp. = Rp

0,0250 Oh Kepala tukang @ Rp. = Rp

0,0013 Oh Mandor @ Rp. = Rp

Sub total : = Rp

Dibulatkan : = Rp

48 1m2 wiremesh M6

Bahan

1,0500 m2 wermesh M8 @ Rp. = Rp

0,0150 kg Kawat Bendrat @ Rp. = Rp

Sub total : = Rp

Dibulatkan = Rp

Upah

0,0070 Oh Pekerja @ Rp. = Rp

0,0070 Oh Tukang besi @ Rp. = Rp

0,0007 Oh Kepala tukang @ Rp. = Rp

0,0003 Oh Mandor @ Rp. = Rp

Sub total : = Rp

Dibulatkan = Rp

49 1 m3 Membuat beton bertulang, 1 Pc : 2 Ps : 3 Kr

Bahan

232,0000 Kg Semen portland @ Rp. = Rp

0,5200 m3 Pasir beton @ Rp. = Rp

0,8700 m3 Koral beton @ Rp. = Rp

Sub total : = Rp

Dibulatkan = Rp

Upah

1,6500 Oh Pekerja @ Rp. = Rp

0,2500 Oh Tukang batu @ Rp. = Rp

0,0250 Oh Kepala tukang @ Rp. = Rp

0,0800 Oh Mandor @ Rp. = Rp

Sub total : = Rp

Dibulatkan = Rp

50 Sewa Concrete Pump 30-50 meter / Hari

Upah

1,0000 hr Concrete Pump @ Rp. = Rp

Dibulatkan = Rp

51 1 m Buat railing stainless stell ( Non Destabilitas )

Bahan

Lampiran III RKS no. 24/LL/NONSAR/KCI/II/2018 tanggal 13 Februari 2018

1,0000 m Railing stainless stell T 2"x1,5 @ Rp. = Rp

10,0000 % bahan Perlengkapan @ Rp. = Rp

Sub total : = Rp

dibulatkan = Rp

Upah

0,3250 Oh Pekerja @ Rp. = Rp

0,3250 Oh Tukang besi @ Rp. = Rp

0,0325 Oh Kepala tukang @ Rp. = Rp

0,0160 Oh Mandor @ Rp. = Rp

Sub total : = Rp

dibulatkan = Rp

52 1 m2 Pengecatan bidang besi

Bahan

0,1500 lbr Amplas @ Rp. = Rp

0,2000 kg Cat meni @ Rp. = Rp

0,1500 Ltr Minyak cat @ Rp. = Rp

0,0300 Kg Kuas @ Rp. = Rp

0,1700 Kg Cat dasar @ Rp. =

0,2600 Kg Cat penutup 2 x @ Rp. = Rp

Sub total : = Rp

Dibulatkan : = Rp

Upah Rp

0,0700 Oh Pekerja @ Rp. = Rp

0,0090 Oh Tukang cat @ Rp. = Rp

0,0060 Oh Kepala tukang @ Rp. = Rp

0,0025 Oh Mandor @ Rp. = Rp

. Sub total : = Rp

Dibulatkan : = Rp

53 Pemasangan Instalasi kabel Power dengan kabel NYRGBY 4x25 mm

Bahan

1,00000 m Kabel NYRGBY 4x25 mm @ Rp. = Rp

5,00000 % Perlengkapan instalasi @ Rp. = Rp

Sub total : = Rp

Dibulatkan = Rp

Upah

0,04570 Oh Pembantu tukang listrik @ Rp. = Rp

0,04570 Oh Tukang listrik @ Rp. = Rp

0,00910 Oh Kepala tukang istrik @ Rp. = Rp

0,00300 Oh Mandor @ Rp. = Rp

Sub total : = Rp

Dibulatkan = Rp

54 Memasang Panel Unit uk.800X600X200

Bahan

1,00000 bh Panel Unit uk.800x600x200 @ Rp. = Rp

1,00000 bh MCCB 3 Kutub 75 amp @ Rp. = Rp

1,00000 bh MCCB 3 Kutub 25 amp @ Rp. = Rp

13,00000 bh MCB 1 Kutub 16 amp @ Rp. = Rp

8,00000 bh MCB 1 Kutub 10 amp @ Rp. = Rp

9,00000 bh MCB 1 Jutub 6 amp @ Rp. = Rp

6,00000 bh MCB 1 Kutub 4 amp @ Rp. = Rp

( 2 MCB untuk timer ) @ Rp. = Rp

2,00000 bh MCB 1 Kutub 6 amp @ Rp. = Rp

( 2 MCB untuk Timer ) @ Rp. = Rp

1,00000 bh Timer theben sul 181 coil 220v @ Rp. = Rp

1,00000 bh Kontaktor 25 ampere coil 220v @ Rp. = Rp

4,00000 bh MCB 1 Kutub 2 amp Control @ Rp. = Rp

4,00000 bh Pilot Lamp 220 v @ Rp. = Rp

10,00000 m Kabel NYAF 1x16 mm @ Rp. = Rp

1,00000 Unit Ampere volt digital 230/440 volt @ Rp. = Rp

3,00000 bh CT 150/5 amp @ Rp. = Rp

5,00000 % Perlengkapan wairing panel @ Rp. = Rp

Sub total : = Rp

Dibulatkan = Rp

Upah

Lampiran III RKS no. 24/LL/NONSAR/KCI/II/2018 tanggal 13 Februari 2018

2,00000 Oh Pembantuk tukang listrik @ Rp. = Rp

2,00000 Oh Tukang listrik/Pembatu Instalator @ Rp. = Rp

1,00000 Oh Kepala tukang istrik/Instalator @ Rp. = Rp

Sub total : = Rp

Dibulatkan = Rp

55 Pemasangan Instalasi kabel Power dengan kabel NYRGBY 4x10 mm

Bahan

1,00000 m Kabel NYRGBY 4x10 mm @ Rp. = Rp

0,10000 Set Sambungan Kabel Recin @ Rp. = Rp

5,00000 % Perlengkapan instalasi @ Rp. = Rp

Sub total : = Rp

Dibulatkan = Rp

Upah

0,04570 Oh Pembantu tukang listrik @ Rp. = Rp

0,04570 Oh Tukang listrik @ Rp. = Rp

0,00910 Oh Kepala tukang istrik @ Rp. = Rp

0,00300 Oh Mandor @ Rp. = Rp

Sub total : = Rp

Dibulatkan = Rp

56 Pemasangan Instalasi kabel lampu penerangan dengan kabel NYM 4x2,5 mm

Bahan

1,00000 m Kabel NYM 4x2,5 mm @ Rp. = Rp

0,33333 btg Conduit pipa dia. 25 pj 3m @ Rp. = Rp

0,03000 bh Sok pipa clipsal 25 mm @ Rp. = Rp

0,03000 bh Klem pipa 25 mm @ Rp. = Rp

5,00000 % Perlengkapan instalasi @ Rp. = Rp

Sub total : = Rp

Dibulatkan = Rp

Upah

0,04570 Oh Pembantu tukang listrik @ Rp. = Rp

0,04570 Oh Tukang listrik @ Rp. = Rp

0,00910 Oh Kepala tukang istrik @ Rp. = Rp

0,00300 Oh Mandor @ Rp. = Rp

Sub total : = Rp

Dibulatkan = Rp

57 Pemasangan Instalasi stop kontak dan saklar dengan kabel NYM 3x2,5 mm

Bahan

8,00000 m Kabel NYM 3x2,5 mm @ Rp. = Rp

2,67000 btg Conduit pipa dia. 25 pj 3m @ Rp. = Rp

5,00000 % Perlengkapan instalasi @ Rp. = Rp

Sub total : = Rp

Dibulatkan = Rp

Upah

0,29629 Oh Pembantu tukang listrik @ Rp. = Rp

0,29629 Oh Tukang listrik @ Rp. = Rp

0,05920 Oh Kepala tukang istrik @ Rp. = Rp

0,03365 Oh Mandor @ Rp. = Rp

Sub total : = Rp

Dibulatkan = Rp

58 Pemasangan Lampu Dengan Lampu T8 termasuk balak 18 watt

Bahan

1,00000 bh Led T8 18 watt @ Rp. = Rp

1,00000 m Kabel Nym 3x2,5 mm @ Rp. = Rp

1,00000 bh T dus 20 mm @ Rp. = Rp

0,33000 bt Pipa Clipsal 25 mm @ Rp.

1,00000 bh Balak T8 18w @ Rp. = Rp

5,00000 % Perlengkapan instalasi @ Rp. = Rp

Sub total : = Rp

Dibulatkan = Rp

Upah

0,29629 Oh Pembantu tukang listrik @ Rp. = Rp

0,29629 Oh Tukang listrik @ Rp. = Rp

0,05920 Oh Kepala tukang istrik @ Rp. = Rp

0,03365 Oh Mandor @ Rp. = Rp

Sub total : = Rp

Lampiran III RKS no. 24/LL/NONSAR/KCI/II/2018 tanggal 13 Februari 2018

Dibulatkan = Rp

59 Pemasangan Lampu Gantung Industri engel 120 daya 85 watt satandar philips lumen 11000 ip 65 kabel NYM 3x2,5 mm

Bahan

1,00000 bh Lampu Gantung LED 85 watt @ Rp. = Rp

1,00000 bh Breacket led 110 @ Rp. = Rp

1,00000 m Kabel Nym 3x2,5 mm @ Rp. = Rp

1,00000 bh T doos 25 mm @ Rp. = Rp

0,33000 bt Pipa Clipsal 25 mm @ Rp. = Rp

5,00000 % Perlengkapan instalasi @ Rp. = Rp

Sub total : = Rp

Dibulatkan = Rp

Upah

0,29629 Oh Pembantu tukang listrik @ Rp. = Rp

0,29629 Oh Tukang listrik @ Rp. = Rp

0,05920 Oh Kepala tukang istrik @ Rp. = Rp

0,03365 Oh Mandor @ Rp. = Rp

Sub total : = Rp

Dibulatkan = Rp

60 Memasang Saklar engkel

Bahan

1,00000 bh Saklar engkel neon pieno putih @ Rp. = Rp

5,00000 % Perlengkapan instalasi @ Rp. = Rp

= Rp

= Rp

Upah

0,03200 Oh Pembantu tukang listrik @ Rp. = Rp

0,03200 Oh Tukang listrik @ Rp. = Rp

0,00411 Oh Kepala tukang istrik @ Rp. = Rp

0,00160 Oh Mandor @ Rp. = Rp

= Rp

= Rp

61 Memasang Stop Kontak daya

Bahan

1,00000 bh Stop kontak Pieno Putih @ Rp. = Rp

5,00000 % Perlengkapan instalasi @ Rp. = Rp

= Rp

= Rp

Upah

0,03200 Oh Pembantu tukang listrik @ Rp. = Rp

0,03200 Oh Tukang listrik @ Rp. = Rp

0,00411 Oh Kepala tukang istrik @ Rp. = Rp

0,00160 Oh Mandor @ Rp. = Rp

= Rp

= Rp

62 Memasang Stop Kontak AC

Bahan

1,00000 bh Stop kontak ac clipsal @ Rp. = Rp

5,00000 % Perlengkapan instalasi @ Rp. = Rp

= Rp

= Rp

Upah

0,03200 Oh Pembantu tukang listrik @ Rp. = Rp

0,03200 Oh Tukang listrik @ Rp. = Rp

0,00411 Oh Kepala tukang istrik @ Rp. = Rp

0,00160 Oh Mandor @ Rp. = Rp

= Rp

= Rp

63 Memasang Exhaustfan 10'/25cm

Bahan

1,00000 Unit Exhaustfan 10'/25cm @ Rp. = Rp

5,00000 % Perlengkapan instalasi @ Rp. = Rp

= Rp

= Rp

Dibulatkan

Sub total

Dibulatkan

Sub total

Dibulatkan

Sub total

Dibulatkan

Sub total

Dibulatkan

Sub total

Sub total

Dibulatkan

Sub total

Dibulatkan

Lampiran III RKS no. 24/LL/NONSAR/KCI/II/2018 tanggal 13 Februari 2018

Upah

0,11196 Oh Pembantu tukang listrik @ Rp. = Rp

0,11196 Oh Tukang listrik @ Rp. = Rp

0,02238 Oh Kepala tukang istrik @ Rp. = Rp

0,01126 Oh Mandor @ Rp. = Rp

Sub total = Rp

= Rp

64 1 m' Pasang instalasi ac

Bahan

1,00000 m Pipa AC Tembaga 1/4x3/8 ( 1 1/2 Pk ) @ Rp. = Rp

1,00000 m Pipa Pembuangan @ Rp. = Rp

Sub total : = Rp

Dibulatkan = Rp

Upah

0,07500 Oh Pembantu Tukang Listrik @ Rp. = Rp

0,03500 Oh Tukang Listrik @ Rp. = Rp

Sub total : = Rp

Dibulatkan = Rp

65 Memasang 1 buah AC 1 1/2 pk setara daikin

Bahan

1,00000 UNIT AC 1 1/2 Pk @ Rp. = Rp

5,00000 % Perlengkapan instalasi @ Rp. = Rp

= Rp

= Rp

Upah

1,14286 Oh Pembantu tukang listrik @ Rp. = Rp

1,14286 Oh Tukang listrik @ Rp. = Rp

0,18515 Oh Kepala tukang istrik @ Rp. = Rp

0,11370 Oh Mandor @ Rp. = Rp

Sub total = Rp

= RpDibulatkan

Dibulatkan

Dibulatkan

Sub total

Jakarta, ...... 2018

PT.......Ttd, Cap/ Stempel Perusahaan,