ENVIRONMENTAL REGULATORY ISSUES PADA PROYEK …
Transcript of ENVIRONMENTAL REGULATORY ISSUES PADA PROYEK …
ENVIRONMENTAL REGULATORY ISSUES
PADA PROYEK PEMBANGUNAN &
PENGOPERASIAN LNG PLANT
Ir. Habibie Razak, MM., ASEAN Eng., ACPESenior Project Manager & Seller Doer - Power, Oil & Gas
Sekretaris Bidang Distribusi Gas, Persatuan Insinyur Indonesia Pusat
Wakil Ketua Bidang Hukum dan Advokasi, Badan Kejuruan Sipil (BKS) PII
Workshop Continuing Professional Development (CPD) – Kelas Teknik LingkunganDitjen Bina Konstruksi, Kementerian PUPERAJakarta, 04 Oktober 2016
PER
SATU
AN
INSI
NY
UR
IN
DO
NES
IARE-DEFINISI INSINYUR:
Insinyur dari Wikipedia:Insinyur adalah orang yang bekerja dalam bidang teknik, yang berbekal pengetahuan ilmiah untuk menyelesaikan masalah praktis dengan menggunakan teknologi.
Insinyur menurut PII:Insinyur adalah orang yang melakukan rekayasa teknik dengan menggunakan ilmu pengetahuan untuk meningkatkan nilai tambah atau daya guna atau pelestarian demi kesejahteraan umat manusia
PER
SATU
AN
INSI
NY
UR
IN
DO
NES
IALNG LIQUEFACTION SYSTEM
PER
SATU
AN
INSI
NY
UR
IN
DO
NES
IALNG LIQUEFACTION SYSTEM
• Inlet Gas Compression
• Gas Treating; Amine Treatment, Dehydration, Mercury &
Benzene Removal.
• LNG Liquefaction Utilizing Patented Technology.
• Nitrogen Removal.
• LNG Storage.
• Condensate Storage.
• LNG Off Loading.
• Boil-off Gas Handling / Compression.
• Refrigerant Make-up.
• Utilities; Electrical power supply, Instrument Air, Utility Air,
Nitrogen, Plant Service Water (potable, utility, etc.).
• Vent and Drain Systems.
• Firewater System.
• Support Buildings: Control / Administration / Office Building(s),
Warehouse / Maintenance Building(s), Powerhouse Building.
PER
SATU
AN
INSI
NY
UR
IN
DO
NES
IAOVERVIEW OF PROJECT ENVIRONMENTAL ASPECTSSUBJECTS TO ENVIRONMENTAL REVIEW & PLANNING
• The project site location (topography, hydrology, geotechnical, site ambient condition, area required, area zonation, etc.)
• Air emissions associated with process equipment• Handling and storage of chemicals and liquids at the
site to prevent adverse impacts to ground water• LNG management from LNG liquefaction plant,
transportation down to customer side
PER
SATU
AN
INSI
NY
UR
IN
DO
NES
IAOVERVIEW OF PROJECT ENVIRONMENTAL ASPECTS
• The project site location (topography, hydrology, geotechnical, site ambient condition, area required, social condition, biological condition, etc.)
• Air emissions associated with process equipment• Handling and storage of chemicals and liquids at
the site to prevent adverse impacts to ground water
• LNG management from LNG liquefaction plant, transportation down to customer side
PER
SATU
AN
INSI
NY
UR
IN
DO
NES
IAPROCESS EQUIPMENT AND MANAGEMENT OF POTENTIAL ONSITE IMPACTS
• Air emissions (amine treatment and dehydration,
heaters, refrigerant and heavies knock-out drums,
boil off and compression and load-outs)
• Emissions were calculated based on the sources
operating continually on an annual basis.
• The applicable Indonesian emissions standards
are on a per-unit basis and contain limits in
milligrams per normal cubic meter (mg/Nm3) for
emissions of nitrogen dioxide (NO2), sulfur dioxide
(SO2), and particulate.
PER
SATU
AN
INSI
NY
UR
IN
DO
NES
IAINDONESIAN EMISSION STANDARDS
Example of LNG Plant Operational Emissions and Indonesian Emission Standards
SOURCE
EMISSIONS EMISSIONS
STANDARD
(MG/NM3)[2]
IN
COMPLIANC
E (YES/NO)Pollutant (mg/Nm3) (Tonnes/Yr)
Amine
Reboiler
NOX TBF TBF 1,400 YES
SO2 TBF TBF 1,200 YES
Particulate TBF TBF 300 YES
Regeneration
Gas Heater
NOX TBF TBF 1,400 YES
SO2 TBF TBF 1,200 YES
Particulate TBF TBF 300 YES
Notes [ ]:
1. See Appendix M for detailed emissions calculations.
2. Minister of Environment Decree No. Kep. 129/MENLH/2003, Appendix III emissions standards
for boilers
PER
SATU
AN
INSI
NY
UR
IN
DO
NES
IAMANAGEMENT OF CHEMICALS AND MATERIALS
• The project normally will be storing and
transferring LNG but it should be limited to store
additional potentially hazardous chemical supplies.
• The design phase will include appropriate
safeguards for storage and use of materials.
• In the operations phase, all materials will be used
and stored in a protective manner under the
implemented Environmental Management System
to minimize the chances for spills and leaks.
PER
SATU
AN
INSI
NY
UR
IN
DO
NES
IAMANAGEMENT OF CHEMICALS AND MATERIALS
Materials to be used/stored including but not limited to the
following:
• Gas Liquids - LNG storage with appropriate design
safeguards, limited storage of condensate in a small
tank.
• Refrigerants - ethylene, propane, and any other liquids
used as refrigerants for the project and supplies of each
have to be maintained on-site.
• Recovered Sulfur - The amine system is to remove the
trace amounts of sulfur, and the recovered material will
be incorporated as part of plant fuel. For high H2S
content in the gas stream normally will require dedicated
SRU
PER
SATU
AN
INSI
NY
UR
IN
DO
NES
IAMANAGEMENT OF CHEMICALS AND MATERIALS
Materials to be used/stored including but not limited to the
following (continued):
• Mercury - Mercury will be removed from the intake gas flow
via an adsorption unit associated with the dehydrator. The
adsorbent accumulates mercury for approximately a 5-year
or longer period before requiring replacement adsorbent
and disposal of the spent material as a hazardous material
under the applicable regulations.
• Other Reagents - additional materials are managed within
the processes (such as amine and catalysts), or are used
for maintenance purposes. All materials will be managed in
a secure manner protective to the environment in
conjunction with liquefaction plant spill and containment
planning.
PER
SATU
AN
INSI
NY
UR
IN
DO
NES
IASURFACE WATER AND GROUND WATER IMPACTS
• The project shall be designed and managed to minimize any
potential adverse impact to surface water and ground water.
• The liquefaction plant shall not directly discharge any
process waste-water to surrounding surface water.
• Process waste-water shall be limited to small quantities of
condensate waters that will be collected in a small tank. The
accumulated wastewater will be hauled off-site for either
energy recovery or treatment/disposal by appropriately
licensed treatment/disposal facilities.
• Storm water runoff shall be mitigated by site design
drainage planning.
• Properly designed containment systems for any stored
chemical materials or fuels and have to be managed under
a storm water pollution prevention plan as part of the
liquefaction plant environmental management system.
PER
SATU
AN
INSI
NY
UR
IN
DO
NES
IASURFACE WATER AND GROUND WATER IMPACTS
• Groundwater impacts of the project are anticipated to be
very minor if any. Any fill material to be added to the site
associated with construction will be sampled to confirm the
materials are suitably free of pollutant contamination prior to
use on the site.
• The only potential adverse impacts associated with
construction and operations would arise from unintended
accidental spills or releases.
• All fuels and liquid materials will be managed during
construction to avoid and capture any releases that could
migrate to groundwater.
• All chemical and fuel materials used during operations will
be maintained in appropriately designed containment and
will be managed to avoid potential spills or other releases to
the ground.
PER
SATU
AN
INSI
NY
UR
IN
DO
NES
IAENVIRONMENTAL RISKS AND MITIGATING FACTORS
PROJECT
ACTIVITY
ISSUES AND
POTENTIAL
IMPACTS
MITIGATION
MEASURES
MEANS OF
IMPLEMENTATION
RESPONSIBLE
PARTY
Land
clearing
Loss of
vegetation, loss
of agriculture
capacity, and
loss of timber
resources as a
result of land
clearing
Minimize “footprint”
Harvest usable timber
Minimizeimpacts fromtree cutting andland clearing
Clearing isrestricted to landrequired.
The project and
EPC contractor
for LNG plant
construction
Land
clearing
Reduction in
faunal habitats,
biodiversity, and
genetic diversity
Minimize “footprint”
Conserve the remaining area
Biological surveys, with
management as
necessary, based on
survey results
The project,
assisted by
consultants
PER
SATU
AN
INSI
NY
UR
IN
DO
NES
IAENVIRONMENTAL RISKS AND MITIGATING FACTORS
Land clearing and
earthworks
Soil instability,
erosion, and
sediment
transport due to
earthworks
Select a site with low relief
Implement erosion control measures
Minimize the need for cut and fill
Land clearing and grading following establishment of erosion protection measures
Erosion protection using vegetative matting and mulches, velocity reduction barriers, retaining walls, and sediment retention basins
Temporary stabilization, by seeding and/or mulching, applied to areas that would otherwise remain in a disturbed condition for more than 90 days
The project
owner, and
EPC
contractors
for LNG
plant
PROJECT
ACTIVITY
ISSUES AND
POTENTIAL
IMPACTS
MITIGATION
MEASURES
MEANS OF
IMPLEMENTATION
RESPONSIBLE
PARTY
PER
SATU
AN
INSI
NY
UR
IN
DO
NES
IAENVIRONMENTAL RISKS AND MITIGATING FACTORS
PROJECT
ACTIVITY
ISSUES AND
POTENTIAL
IMPACTS
MITIGATION
MEASURES
MEANS OF
IMPLEMENTATION
RESPONSIBLE
PARTY
Workforce
recruitment
Potential
dissatisfaction or
conflicts among
local residents as a
result of unrealized
employment
expectations
Integrated social
programs involving
community
consultation, job,
training, and conflict
resolution
Provision of education programs and vocational training in building skills
Community consultation, public participation, and conflict management
Development of conflict resolution and grievance procedures
The project,
and all EPC
and other
contractors
Workforce
deployment
Social or cultural
problems due to
interaction of
traditional villagers
with construction
workforce
Minimize opportunities
for interaction
Planning by contractors
The project,
and all EPC
and other
contractors
PER
SATU
AN
INSI
NY
UR
IN
DO
NES
IAENVIRONMENTAL RISKS AND MITIGATING FACTORS
PROJECT
ACTIVITY
ISSUES AND
POTENTIAL
IMPACTS
MITIGATION
MEASURES
MEANS OF
IMPLEMENTATION
RESPONSIBLE
PARTY
Perimeter fence
around LNG
property
Isolation of small
populations of some
species of wildlife
within the fenced
area could result in
nonviable
populations or
eventual reduction
in genetic diversity.
(Alternatively, the
protection afforded
by the fence could
benefit these
species.)
Manage the un-cleared
part of the project
property to conserve
ecological values
Vegetation and fauna within the project “footprint” will be monitored before any land clearing, and again after completion of land clearing.
The project
Displacement of
villagers
Loss of livelihoods,
reduced access to
resources.
Resettlement
Compensation
Development of alternative livelihoods
Provision of alternative access to resources.
Provision of training and construction employment.
The project
PER
SATU
AN
INSI
NY
UR
IN
DO
NES
IAENVIRONMENTAL REGULATORY ISSUESAMDAL, UKL/UPL REQUIREMENTS
• Environmental Impact Assessment or called AMDAL – Analisis
Mengenai Dampak Lingkungan. The types of businesses and
activities that are subject to the AMDAL requirements are
specified in the State Ministerial Ordinance of Environment No.
5 of 2012.
• If the proposed LNG project does not appear to be in a
category that requires a formal AMDAL process then UKL/UPL
will still be needed.
• LNG plant(s) with a capacity equal to or over 550 MMSCFD
will need an AMDAL regardless other factors.
• As noted in the ordinance of Environmental Ministry No. 13
Year 2010 Article 5 Page 2, the approval of UKL/UPL will be
completed by local government.
PER
SATU
AN
INSI
NY
UR
IN
DO
NES
IAENVIRONMENTAL REGULATORY ISSUESINTERNATIONAL LENDING STANDARDS – FINANCING PURPOSE
• Typically, financing institutions will require that the more
stringent of the IFC/World Bank or host country (Indonesia)
environmental performance standards be met as a condition of
providing loan financing.
• The IFC/World Bank standards will in most cases provide the
design and performance criteria for a new project seeking
international financing.
• The Government of Indonesia has established its own
environmental standards and guidelines for project design and
operations – including air quality standards, emission
guidelines, effluent limits, noise standards, and hazardous and
toxic waste management guidelines.
• Planning and strategy activities for permitting the proposed
liquefaction plant will need to consider the international
financing guidelines outlined immediately above. Accordingly,
the need and applicability of Indonesian and international
financing requirements should be confirmed.
PER
SATU
AN
INSI
NY
UR
IN
DO
NES
IAENVIRONMENTAL REGULATORY ISSUESINDONESIAN REGULATIONS RELATED TO WATER SUPPLY, WATER TREATMENT AND WASTE WATER TREATMENT
• PERMENKES No. 416 Year 1990 regarding the Requirements
and Monitoring of Quality of Water.
• Regulation of Ministry of Environment No. 4 Year 2007 regarding
Waste Water Standard on Oil & Gas and Geothermal.
• Kep-112/MENLH/2003 regarding Standard for Domestic Waste-
Water.
• Kep-42/MENLH/10/1996 Decree of the State Minister for
Environment; Waste Water Standard in Geothermal/Oil and Gas
Activities.
• Kep-51/MENLH/10/1995 Decree of the State Minister for
Environment; Liquid Waste Standards for Industrial Activities.
• BAPEDAL No. 1Year 1995 regarding B3 Waste Handling
Requirement.
• KEPMEN No. 115 Year 2003 regarding the Standard of Water
Quality.
Enai
TERIMA KASIH