TUGAS MANAJEMEN PROYEK Nama : Ayu Hasyyati Semester : 1 (Satu) Kelas : MMT ITS 2014 – Jakarta Dosen : Dr. Yadi Siswadi CRITICAL PATH METHOD Kegiata n Kegiatan yang Mendahului Waktu A - 5 B A 6 C A 4 D A 5 E D 6 F B 4 G C 2 H C 3 I E 8 J E 7 K E 4 L H, I 4 M J 2 N K 6 O G, L, M 4
-
Upload
ayu-hasyyati -
Category
Documents
-
view
224 -
download
5
Transcript of 20140529_Critical Path Method (Ayu Hasyyati).docx
TUGAS MANAJEMEN PROYEK
Nama : Ayu HasyyatiSemester : 1 (Satu)
Kelas : MMT ITS 2014 – JakartaDosen : Dr. Yadi Siswadi
CRITICAL PATH METHOD
Kegiatan
Kegiatan yang Mendahului
Waktu
A - 5B A 6C A 4D A 5E D 6F B 4G C 2H C 3I E 8J E 7K E 4L H, I 4M J 2N K 6O G, L, M 4P M 8Q N 9R P, Q 10S F 5
Tugas Manajemen Proyek* AYU HASYYATI *
T G 6U S, T 5
CRITICAL PATH DIAGRAM
2
Tugas Manajemen Proyek* AYU HASYYATI *
Critical Path: A – D – E – K – N – Q - R