Lampiran 2. Rencana Anggaran Biaya REKAPITULASI ANGGARAN BIAYA
MASJID NURUL IMAN YOGYAKARTA
TOTAL HARGA NO. URAIAN PEKERJAAN
(Rp.)
(Pembulatan Desimal) A PEKERJAAN PERSIAPAN
966,533
B PEKERJAAN SIPIL
333,889,581 C PEKERJAAN LANTAI
69,674,934
SUB TOTAL 404,531,048 JASA PEMBORONG 10% 40,453,105 JUMLAH
444,984,153
JUMLAH (Pembulatan) 445,000,000
445,000,000
RENCANA ANGGARAN BIAYA
PROYEK : MASJID NURUL IMAN LOKASI : YOGYAKARTAPEKERJAAN : STRUKTUR
TOTAL HARGANO. URAIAN PEKERJAAN (Rp.)
(Pembulatan Desimal)
C. PEKERJAAN SIPIL
I PEKERJAAN GALIAN DAN URUGAN 3,458,614
II PEKERJAAN STRUKTUR BAWAH 44,212,478
III PEKERJAAN STRUKTUR ATAS 147,593,640
IV PEKERJAAN ATAP 30,014,401
V PEKERJAAN DINDING PASANGAN BATA DAN PLESTERAN 107,873,280
VI PEKERJAAN SANITASI 737,169
333,889,581SUB TOTAL
RENCANA ANGGARAN BIAYA
PROYEK : MASJID NURUL IMAN LOKASI : YOGYAKARTAPEKERJAAN : STRUKTUR
HARGA TOTAL HARGANO. URAIAN PEKERJAAN VOL SAT SATUAN (Rp.)
(Rp) (Pembulatan Desimal)
C. PEKERJAAN SIPILI. PEKERJAAN GALIAN DAN URUGAN1 Galian Foot Plate 13.86 m3 34,716 481,164 2 Galian Pondasi batu kali 68.05 m3 34,716 2,362,372 3 Urugan tanah kembali sisi pondasi 43.51 m3 14,135 615,078
Sub Total 3,458,614
II. PEKERJAAN STRUKTUR BAWAH
1 Urugan pasir 5 cm - bawah pondasi Foot Plate 3.86 m3 200,570 775,088
2 Urugan pasir 10 cm- Bawah lantai 9.66 m3 200,570 1,936,604
3 Lantai kerja 5 cm - bawah pondasi Foot Plate 0.46 m3 683,500 315,777
4 Pekerjaan Cor beton Site Mixa Footplate
- Cor F1 60 x 60 x 25 0.49 m3 828,250 405,843 - Pembesian F1 60 x 60 x 25 52.50 kg 10,002 525,109 - Begisting F1 60 x 60 x 25 2.80 m2 79,481 222,547
- Cor F2 80 X 80 X 35 1.70 m3 828,250 1,408,853 - Pembesian F2 80 X 80 X 35 133.00 kg 10,002 1,330,277 - Begisting F2 80 X 80 X 35 7.56 m2 79,481 600,876
- Cor F3 100 X 100 X 35 0.85 m3 828,250 701,528 - Pembesian F3 100 X 100 X 35 67.08 kg 10,002 670,973 - Begisting F3 100 X 100 X 35 3.08 m2 79,481 244,801
b Kaki kolom - Cor K1 20 x 30 0.36 m3 828,250 298,170 - Pembesian K1 20 x 30 58.63 kg 8,592 503,754 - Begisting K1 20 x 30 6.00 m2 83,597 501,579
- Cor K2 30 x 40 1.08 m3 828,250 894,510 - Pembesian K2 30 x 40 119.00 kg 8,541 1,016,328 - Begisting K2 30 x 40 12.60 m2 83,597 1,053,316
- Cor K3 D30 0.21 m3 828,250 175,707 - Pembesian K3 D30 35.69 kg 8,927 318,618 - Begisting K3 D30 2.83 m2 83,597 236,459
c Rabatan Lantai 4.83 m3 683,500 3,299,767 5 Pekerjaan Pondasi batu kali (umpak) 22.39 m3 480,800 10,766,939 6 Pekerjaan Aans Stamping 11.31 m3 446,507 5,049,989
7 Beton sloof- Cor Sloof S1 15 x 25 2.83 m3 828,250 2,341,877 - Pembesian Sloof S1 15 x 25 520.66 kg 8,321 4,332,291 - Begisting Sloof S1 15 x 25 53.91 m2 79,481 4,284,897
Sub Total Pekerjaan Struktur Bawah 44,212,478
III. PEKERJAAN STRUKTUR ATAS
Mutu beton K 225
A STRUKTUR Lantai 01
Pekerjaan Cor K225a kolom
- Cor K1 20 x 30 0.89 m3 832,925 739,637
- Pembesian K1 20 x 30 142.30 kg 8,725 1,241,622
- Begisting K1 20 x 30 14.80 m2 85,860 1,270,730
- Cor K2 30 x 40 2.66 m3 832,925 2,218,912
- Pembesian K2 30 x 40 288.66 kg 8,675 2,504,129
- Begisting K2 30 x 40 31.08 m2 85,860 2,668,533
- Cor K3 D30 0.52 m3 832,925 435,858
- Pembesian K3 D30 86.95 kg 9,051 786,972
- Begisting K3 D30 6.98 m2 85,860 599,058
b Balok beton
- Cor B1 15 x 30 2.26 m3 907,750 2,052,650
- Pembesian B1 15 x 30 419.28 kg 8,663 3,632,161
- Begisting B1 15 x 30 41.46 m2 103,237 4,279,814
- Cor B2 15 X 40 2.68 m3 907,750 2,429,139
- Pembesian B2 15 X 40 500.32 kg 8,805 4,405,134
- Begisting B2 15 X 40 46.61 m2 103,237 4,811,561
- Cor B3 15 x 50 1.85 m3 907,750 1,681,607
- Pembesian B3 15 x 50 258.24 kg 8,418 2,173,858
- Begisting B3 15 x 50 31.25 m2 103,237 3,225,688
c Plat beton 12 mm -
- Cor 12.63 m3 907,750 11,464,610
- Pembesian 888.93 kg 6,896 6,130,370
- Begisting 114.19 m2 103,237 11,788,438
-
B STRUKTUR LANTAI 2 - -
Pekerjaan Cor Ready Mix K225 - a kolom
- Cor K1 20 x 30 0.86 m3 837,834 723,888
- Pembesian K1 20 x 30 138.50 kg 8,804 1,219,307
- Begisting K1 20 x 30 14.40 m2 88,237 1,270,611
- Cor K2 30 x 40 2.59 m3 837,834 2,171,665
- Pembesian K2 30 x 40 280.95 kg 8,753 2,459,271
- Begisting K2 30 x 40 30.24 m2 88,237 2,668,283
- Cor K3 D30 0.51 m3 837,834 426,577
- Pembesian K3 D30 84.62 kg 9,129 772,541
- Begisting K3 D30 6.79 m2 88,237 599,002
kolom t = 1 m
- Cor K1 15 x 30 0.24 m3 837,834 197,938
- Pembesian K1 15 x 30 90.44 kg 9,221 833,889
- Begisting K1 15 x 30 6.30 m2 88,237 555,892
b Balok beton
- Cor B1 15 x 30 2.97 m3 910,638 2,707,462
- Pembesian B1 15 x 30 551.16 kg 8,747 4,821,073
- Begisting B1 15 x 30 54.51 m2 105,732 5,763,239
- Cor B2 15 X 40 2.68 m3 910,638 2,436,866
- Pembesian B2 15 X 40 500.32 kg 8,888 4,446,943
- Begisting B2 15 X 40 46.61 m2 105,732 4,927,873
- Cor B3 15 x 50 1.85 m3 910,638 1,686,956
- Pembesian B3 15 x 50 258.24 kg 8,501 2,195,438
- Begisting B3 15 x 50 31.25 m2 105,732 3,303,664
c Plat beton 12 mm - - Cor 12.76 m3 916,701 11,700,316 - Pembesian 897.66 kg 7,155 6,423,106 - Begisting 114.81 m2 110,973 12,741,357
Sub Total Pekerjaan Struktur Lantai Atas 147,593,640
IV PEKERJAAN DINDING PASANGAN BATA DAN PLESTERAN
Lantai 011 Pasangan dinding bata 1/2 batu 154.28 m2 107,113 16,525,049 2 Plester 308.56 m2 34,025 10,498,584 3 kolom dan balok jendela 14.05 m3 829,808 11,658,806
Lantai 021 Pasangan dinding bata 1/2 batu 233.21 m2 108,123 25,214,853 2 Plester 466.41 m2 34,891 16,273,628 3 kolom dan balok jendela 14.05 m3 1,971,383 27,702,360
Sub Total 107,873,280
V PEKERJAAN ATAP
1 KubahKubah 1.00 Ls 30,014,401 30,014,401
Sub Total 30,014,401 V PEKERJAAN SANITASI
1 Saluran air bersih pipa 4" Wavin AW 16.80 m' 43,879 737,169
Sub Total 737,169
RENCANA ANGGARAN BIAYA
PROYEK : MASJID NURUL IMAN LOKASI : YOGYAKARTAPEKERJAAN : ARSITEK
TOTAL HARGANO. URAIAN PEKERJAAN (Rp.) 467
(Pembulatan Desimal)
D. PEKERJAAN ARSITEK
I PEKERJAAN PELAPIS LANTAI 61,898,594
II PEKERJAAN SPONENGAN 7,776,340
69,674,934 #REF!
RENCANA ANGGARAN BIAYA
PROYEK : MASJID NURUL IMAN LOKASI : YOGYAKARTAPEKERJAAN : ARSITEK
HARGA TOTAL HARGANO. URAIAN PEKERJAAN VOL SAT SATUAN (Rp.)
(Rp) (Pembulatan Desimal)
D. PEKERJAAN ARSITEKI. PEKERJAAN PELAPIS LANTAI
LANTAI 11 Super Glossy KW 1 60 x 60
ruangan lantai 1 79.50 m2 271,621 21,593,843 plint ruangan lantai 1 32.75 m' 50,214 1,644,518
2 roman 40x40 sandstone cream G447506 - ruangan lantai 1 13.20 m2 184,937 2,441,162 plint ruangan lantai 1 11.00 m' 22,023 242,249
3 Roman 33,33x33,33 veneto mocha - ruangan lantai 1 17.07 m2 340,638 5,814,516 plint ruangan lantai 1 16.00 m' 31,104 497,672
- -
LANTAI 2 - 1 Super Glossy KW 1 60 x 60 -
ruangan lantai 1 60.75 m2 259,909 15,789,452 plint ruangan lantai 1 31.50 m' 48,824 1,537,940
2 roman 40x40 sandstone cream G447506 - ruangan lantai 1 27.60 m2 184,937 5,104,247 plint ruangan lantai 1 24.70 m' 22,023 543,959
3 Roman 33,33x33,33 veneto mocha - ruangan lantai 1 17.74 m2 340,638 6,042,062 plint ruangan lantai 1 20.80 m' 31,104 646,973
- -
Sub Total Pekerjaan Struktur Bawah 61,898,594 II. PEKERJAAN Sponengan/ tali air
sponengan 706.94 m' 11,000 7,776,340
Sub Total Pekerjaan Struktur Bawah 7,776,340