5
REKAPITULASI ANGGARAN BIAYA MASJID NURUL IMAN YOGYAKARTA TOTAL HARGA NO. URAIAN PEKERJAAN (Rp.) (Pembulatan Desimal) A PEKERJAAN PERSIAPAN 966,533 B PEKERJAAN SIPIL 333,889,581 C PEKERJAAN LANTAI 69,674,934 SUB TOTAL 404,531,048 JASA PEMBORONG 10% 40,453,105 JUMLAH 444,984,153 JUMLAH (Pembulatan) 445,000,000 445,000,000 RENCANA ANGGARAN BIAYA PROYEK : MASJID NURUL IMAN LOKASI : YOGYAKARTA PEKERJAAN : STRUKTUR TOTAL HARGA NO. URAIAN PEKERJAAN (Rp.) (Pembulatan Desimal) C. PEKERJAAN SIPIL I PEKERJAAN GALIAN DAN URUGAN 3,458,614 II PEKERJAAN STRUKTUR BAWAH 44,212,478 III PEKERJAAN STRUKTUR ATAS 147,593,640 IV PEKERJAAN ATAP 30,014,401 V PEKERJAAN DINDING PASANGAN BATA DAN PLESTERAN 107,873,280 VI PEKERJAAN SANITASI 737,169 333,889,581 SUB TOTAL

Transcript of Lampiran 2. Rencana Anggaran Biaya...2016/10/04  · 1 Galian Foot Plate 13.86 m3 34,716 481,164 2...

  • Lampiran 2. Rencana Anggaran Biaya REKAPITULASI ANGGARAN BIAYA

    MASJID NURUL IMAN YOGYAKARTA

    TOTAL HARGA NO. URAIAN PEKERJAAN

    (Rp.)

    (Pembulatan Desimal) A PEKERJAAN PERSIAPAN

    966,533

    B PEKERJAAN SIPIL

    333,889,581 C PEKERJAAN LANTAI

    69,674,934

    SUB TOTAL 404,531,048 JASA PEMBORONG 10% 40,453,105 JUMLAH

    444,984,153

    JUMLAH (Pembulatan) 445,000,000

    445,000,000

    RENCANA ANGGARAN BIAYA

    PROYEK : MASJID NURUL IMAN LOKASI : YOGYAKARTAPEKERJAAN : STRUKTUR

    TOTAL HARGANO. URAIAN PEKERJAAN (Rp.)

    (Pembulatan Desimal)

    C. PEKERJAAN SIPIL

    I PEKERJAAN GALIAN DAN URUGAN 3,458,614

    II PEKERJAAN STRUKTUR BAWAH 44,212,478

    III PEKERJAAN STRUKTUR ATAS 147,593,640

    IV PEKERJAAN ATAP 30,014,401

    V PEKERJAAN DINDING PASANGAN BATA DAN PLESTERAN 107,873,280

    VI PEKERJAAN SANITASI 737,169

    333,889,581SUB TOTAL

  • RENCANA ANGGARAN BIAYA

    PROYEK : MASJID NURUL IMAN LOKASI : YOGYAKARTAPEKERJAAN : STRUKTUR

    HARGA TOTAL HARGANO. URAIAN PEKERJAAN VOL SAT SATUAN (Rp.)

    (Rp) (Pembulatan Desimal)

    C. PEKERJAAN SIPILI. PEKERJAAN GALIAN DAN URUGAN1 Galian Foot Plate 13.86 m3 34,716 481,164 2 Galian Pondasi batu kali 68.05 m3 34,716 2,362,372 3 Urugan tanah kembali sisi pondasi 43.51 m3 14,135 615,078

    Sub Total 3,458,614

    II. PEKERJAAN STRUKTUR BAWAH

    1 Urugan pasir 5 cm - bawah pondasi Foot Plate 3.86 m3 200,570 775,088

    2 Urugan pasir 10 cm- Bawah lantai 9.66 m3 200,570 1,936,604

    3 Lantai kerja 5 cm - bawah pondasi Foot Plate 0.46 m3 683,500 315,777

    4 Pekerjaan Cor beton Site Mixa Footplate

    - Cor F1 60 x 60 x 25 0.49 m3 828,250 405,843 - Pembesian F1 60 x 60 x 25 52.50 kg 10,002 525,109 - Begisting F1 60 x 60 x 25 2.80 m2 79,481 222,547

    - Cor F2 80 X 80 X 35 1.70 m3 828,250 1,408,853 - Pembesian F2 80 X 80 X 35 133.00 kg 10,002 1,330,277 - Begisting F2 80 X 80 X 35 7.56 m2 79,481 600,876

    - Cor F3 100 X 100 X 35 0.85 m3 828,250 701,528 - Pembesian F3 100 X 100 X 35 67.08 kg 10,002 670,973 - Begisting F3 100 X 100 X 35 3.08 m2 79,481 244,801

    b Kaki kolom - Cor K1 20 x 30 0.36 m3 828,250 298,170 - Pembesian K1 20 x 30 58.63 kg 8,592 503,754 - Begisting K1 20 x 30 6.00 m2 83,597 501,579

    - Cor K2 30 x 40 1.08 m3 828,250 894,510 - Pembesian K2 30 x 40 119.00 kg 8,541 1,016,328 - Begisting K2 30 x 40 12.60 m2 83,597 1,053,316

    - Cor K3 D30 0.21 m3 828,250 175,707 - Pembesian K3 D30 35.69 kg 8,927 318,618 - Begisting K3 D30 2.83 m2 83,597 236,459

    c Rabatan Lantai 4.83 m3 683,500 3,299,767 5 Pekerjaan Pondasi batu kali (umpak) 22.39 m3 480,800 10,766,939 6 Pekerjaan Aans Stamping 11.31 m3 446,507 5,049,989

    7 Beton sloof- Cor Sloof S1 15 x 25 2.83 m3 828,250 2,341,877 - Pembesian Sloof S1 15 x 25 520.66 kg 8,321 4,332,291 - Begisting Sloof S1 15 x 25 53.91 m2 79,481 4,284,897

    Sub Total Pekerjaan Struktur Bawah 44,212,478

  • III. PEKERJAAN STRUKTUR ATAS

    Mutu beton K 225

    A STRUKTUR Lantai 01

    Pekerjaan Cor K225a kolom

    - Cor K1 20 x 30 0.89 m3 832,925 739,637

    - Pembesian K1 20 x 30 142.30 kg 8,725 1,241,622

    - Begisting K1 20 x 30 14.80 m2 85,860 1,270,730

    - Cor K2 30 x 40 2.66 m3 832,925 2,218,912

    - Pembesian K2 30 x 40 288.66 kg 8,675 2,504,129

    - Begisting K2 30 x 40 31.08 m2 85,860 2,668,533

    - Cor K3 D30 0.52 m3 832,925 435,858

    - Pembesian K3 D30 86.95 kg 9,051 786,972

    - Begisting K3 D30 6.98 m2 85,860 599,058

    b Balok beton

    - Cor B1 15 x 30 2.26 m3 907,750 2,052,650

    - Pembesian B1 15 x 30 419.28 kg 8,663 3,632,161

    - Begisting B1 15 x 30 41.46 m2 103,237 4,279,814

    - Cor B2 15 X 40 2.68 m3 907,750 2,429,139

    - Pembesian B2 15 X 40 500.32 kg 8,805 4,405,134

    - Begisting B2 15 X 40 46.61 m2 103,237 4,811,561

    - Cor B3 15 x 50 1.85 m3 907,750 1,681,607

    - Pembesian B3 15 x 50 258.24 kg 8,418 2,173,858

    - Begisting B3 15 x 50 31.25 m2 103,237 3,225,688

    c Plat beton 12 mm -

    - Cor 12.63 m3 907,750 11,464,610

    - Pembesian 888.93 kg 6,896 6,130,370

    - Begisting 114.19 m2 103,237 11,788,438

    -

    B STRUKTUR LANTAI 2 - -

    Pekerjaan Cor Ready Mix K225 - a kolom

    - Cor K1 20 x 30 0.86 m3 837,834 723,888

    - Pembesian K1 20 x 30 138.50 kg 8,804 1,219,307

    - Begisting K1 20 x 30 14.40 m2 88,237 1,270,611

    - Cor K2 30 x 40 2.59 m3 837,834 2,171,665

    - Pembesian K2 30 x 40 280.95 kg 8,753 2,459,271

    - Begisting K2 30 x 40 30.24 m2 88,237 2,668,283

    - Cor K3 D30 0.51 m3 837,834 426,577

    - Pembesian K3 D30 84.62 kg 9,129 772,541

    - Begisting K3 D30 6.79 m2 88,237 599,002

    kolom t = 1 m

    - Cor K1 15 x 30 0.24 m3 837,834 197,938

    - Pembesian K1 15 x 30 90.44 kg 9,221 833,889

    - Begisting K1 15 x 30 6.30 m2 88,237 555,892

    b Balok beton

    - Cor B1 15 x 30 2.97 m3 910,638 2,707,462

    - Pembesian B1 15 x 30 551.16 kg 8,747 4,821,073

    - Begisting B1 15 x 30 54.51 m2 105,732 5,763,239

    - Cor B2 15 X 40 2.68 m3 910,638 2,436,866

    - Pembesian B2 15 X 40 500.32 kg 8,888 4,446,943

    - Begisting B2 15 X 40 46.61 m2 105,732 4,927,873

    - Cor B3 15 x 50 1.85 m3 910,638 1,686,956

    - Pembesian B3 15 x 50 258.24 kg 8,501 2,195,438

    - Begisting B3 15 x 50 31.25 m2 105,732 3,303,664

  • c Plat beton 12 mm - - Cor 12.76 m3 916,701 11,700,316 - Pembesian 897.66 kg 7,155 6,423,106 - Begisting 114.81 m2 110,973 12,741,357

    Sub Total Pekerjaan Struktur Lantai Atas 147,593,640

    IV PEKERJAAN DINDING PASANGAN BATA DAN PLESTERAN

    Lantai 011 Pasangan dinding bata 1/2 batu 154.28 m2 107,113 16,525,049 2 Plester 308.56 m2 34,025 10,498,584 3 kolom dan balok jendela 14.05 m3 829,808 11,658,806

    Lantai 021 Pasangan dinding bata 1/2 batu 233.21 m2 108,123 25,214,853 2 Plester 466.41 m2 34,891 16,273,628 3 kolom dan balok jendela 14.05 m3 1,971,383 27,702,360

    Sub Total 107,873,280

    V PEKERJAAN ATAP

    1 KubahKubah 1.00 Ls 30,014,401 30,014,401

    Sub Total 30,014,401 V PEKERJAAN SANITASI

    1 Saluran air bersih pipa 4" Wavin AW 16.80 m' 43,879 737,169

    Sub Total 737,169

  • RENCANA ANGGARAN BIAYA

    PROYEK : MASJID NURUL IMAN LOKASI : YOGYAKARTAPEKERJAAN : ARSITEK

    TOTAL HARGANO. URAIAN PEKERJAAN (Rp.) 467

    (Pembulatan Desimal)

    D. PEKERJAAN ARSITEK

    I PEKERJAAN PELAPIS LANTAI 61,898,594

    II PEKERJAAN SPONENGAN 7,776,340

    69,674,934 #REF!

    RENCANA ANGGARAN BIAYA

    PROYEK : MASJID NURUL IMAN LOKASI : YOGYAKARTAPEKERJAAN : ARSITEK

    HARGA TOTAL HARGANO. URAIAN PEKERJAAN VOL SAT SATUAN (Rp.)

    (Rp) (Pembulatan Desimal)

    D. PEKERJAAN ARSITEKI. PEKERJAAN PELAPIS LANTAI

    LANTAI 11 Super Glossy KW 1 60 x 60

    ruangan lantai 1 79.50 m2 271,621 21,593,843 plint ruangan lantai 1 32.75 m' 50,214 1,644,518

    2 roman 40x40 sandstone cream G447506 - ruangan lantai 1 13.20 m2 184,937 2,441,162 plint ruangan lantai 1 11.00 m' 22,023 242,249

    3 Roman 33,33x33,33 veneto mocha - ruangan lantai 1 17.07 m2 340,638 5,814,516 plint ruangan lantai 1 16.00 m' 31,104 497,672

    - -

    LANTAI 2 - 1 Super Glossy KW 1 60 x 60 -

    ruangan lantai 1 60.75 m2 259,909 15,789,452 plint ruangan lantai 1 31.50 m' 48,824 1,537,940

    2 roman 40x40 sandstone cream G447506 - ruangan lantai 1 27.60 m2 184,937 5,104,247 plint ruangan lantai 1 24.70 m' 22,023 543,959

    3 Roman 33,33x33,33 veneto mocha - ruangan lantai 1 17.74 m2 340,638 6,042,062 plint ruangan lantai 1 20.80 m' 31,104 646,973

    - -

    Sub Total Pekerjaan Struktur Bawah 61,898,594 II. PEKERJAAN Sponengan/ tali air

    sponengan 706.94 m' 11,000 7,776,340

    Sub Total Pekerjaan Struktur Bawah 7,776,340

    SUB TOTAL