ANALISA SATUAN PEKERJAANBOW

Propinsi Kabupaten Kecamatan

No Uraian Pekerjaan Satuan Keterangan

I Pekerjaan Tanah1 Pembersiahan Lapangan/ 10 M2

Upah :Pekerja HOK 0.07 SwadayaMandor HOK 0.02

2 Pemasangan Bowplank / 10 M'Bahan:Papan Meranti Ton 0.05Paku 2" Kg 2.00

Upah :Pekerja HOK 2.00Tukang HOK 0.30Mandor HOK 0.03

3 Galian tanah Biasa/M3Upah:Pekerja HOK 0.75Mandor HOK 0.03

No Uraian Pekerjaan Satuan Keterangan

II Pekerjaan Beton Bertulang1 Beton Bertulang 1:2:3 /M3

Bahan:Kerikil 3/4 " M3 0.82Pasir M3 0.54Semen Zak 6.80

Upah :Pekerja HOK 3.60Tukang HOK 1.20Mandor HOK 0.18

Bahan BesiBesi Beton Kg 110.00Kawat Beton Kg 2.00 Harga bahan disesuaikan

(Harga dilokasi Kegiatan)Upah Besi:Pekerja HOK 9.00Tukang HOK 9.00Mandor HOK 3.00

-

Cetakan BetonBahan :Kayu Bekisting Ton 0.29Paku Kg 4.00 Harga bahan disesuaikan

(Harga dilokasi Kegiatan)Upah :Pekerja HOK 0.50Tukang HOK 0.60Mandor HOK 0.01

-

Bongkar BekistingPekerja HOK 2.00 -

Faktor Penggali

Harga Sat. (Rp)

Jumlah (Rp)

Total

(Rp)

( Termasuk Pemotongan Akar Pohon)

Faktor Penggali

Harga Sat. (Rp)

Jumlah (Rp)

Total

(Rp)

No Uraian Pekerjaan Satuan Keterangan

III Pekerjaan Plesteran1 Pekerjaan Pleseran 1:4 /M2

Bahan :Semen Zak 0.13 Harga bahan disesuaikanPasir M3 0.08 dengan RAB desa

(Harga dilokasi Kegiatan)Upah :Pekerja HOK 0.40Tukang HOK 0.15Mandor HOK 0.02

-

No Uraian Pekerjaan Satuan Keterangan

IV Pekerjaan Kayu1 Pekerjaan Gel Jembatan Kayu/Ton

Bahan:Kayu Kapur Ton 1.10

Upah :Pekerja HOK 5.00Tukang HOK 15.00Mandor HOK 0.25

2 Pekerjaan Lantai Jembatan Kayu /TonBahan : Harga bahan disesuaikanKayu Kapur Ton 1.10 dengan RAB desa

(Harga dilokasi Kegiatan)Upah :Pekerja HOK 4.00Tukang HOK 6.00Mandor HOK 0.2

-

No Uraian Pekerjaan Satuan Keterangan

V Pekerjaan Cat

1 Pekerjaan Cat Minyak/ 10 M2Bahan Cat Minyak Kg 2.75Kuas Cat Bh 0.1Alat Bantu Ls 1.00 Harga bahan disesuaikan

dengan RAB desaUpah: (Harga dilokasi Kegiatan)Pekerja HOK 0.67Mandor HOK 0.03

-

Faktor Penggali

Harga Sat. (Rp)

Jumlah (Rp)

Total

(Rp)

Faktor Penggali

Harga Sat. (Rp)

Jumlah (Rp)

Total

(Rp)

Faktor Penggali

Harga Sat. (Rp)

Jumlah (Rp)

Total

(Rp)

RENCANA ANGGARAN BIAYA PRASARANA

Propinsi : No RAB 01Kabupaten : Program :Kecamatan : Jenis Kegiatan Jembatan GantungDesa : Ukuran/Dimensi 80 m x 1,85 m

UraianVolume

SatuanHarga Satuan Jumlah Total

TotalDari

Dari DanaSwadaya Rp Rp1. BAHAN 1. Besi UNP 100mm x 6 m 22 - 22 Btg 5,856,4002. Besi UNP 65mm x 6 m 21 - 21 Btg 4,326,0003. Besi BBT 15,4 x 10 10 - 10 Btg 1,875,0004. Besi BBT 16 x 12 160 - 160 Btg 16,160,0005. Kawat beton 1 rol 25 - 25 Kg 190,0006. Tiang Pilon 8 " SCH 40 5 - 5 Btg 18,280,0007. Papan mal 7.5 - 7.5 m3 3,750,0008. Semen 100 - 100 sak 4,500,0009. Paku 6 - 6 Kg 48,00010.Kunci 1 - 1 Ls 4,50011.Besi BT 18mm P=10 m 22 - 22 Btg 5,120,00012.Paku 6 - 6 Kg 60,00013.Besi L 60x60x6 P = 6m 6 - 6 Btg 4,530,50014.Vesi L 70x70x7 P = 6m 6 - 6 Btg 1,878,00015.Pasir 96 - 96 m3 4,320,00016.Batu 59.5 - 59.5 m3 4,165,00017.Reng dan gelagar 1 - 1 Ls 50,00018.Paku 13 - 13 Kg 150,00019.Besi O 16mm P = 12 m 107 - 107 Btg 12,305,00020.Besi O 12mm P=12 m 25 - 25 Btg 1,675,00021.Semen 150 - 150 sak 6,450,00022.Batu 27 - 27 m3 1,960,00023.Paku 4 - 4 Kg 82,00024.Besi plat t=6 mm 276 - 276 m3 1,656,00025.Semen 150 - 150 sak 7,200,00026.Besi O 12 mm P = 12 m 5 - 5 Btg 375,00027.Besi UNP 4 - 4 Btg 1,060,00028.Besi pipa putih 4 - 4 Btg 2,200,00029.Besi L 20 - 20 Btg 3,100,00030.Cat 10 - 10 Kg 350,00031.Timer 5 - 5 Btl 24,00032.Paku 15 - 15 kg 135,00033.Kayu 2.5 - 2.5 m3 1,500,00034.Spendrat 6 - 6 bh 222,00035.Baut 1/2x2 " 250 - 250 bh 500,00036.Kawat pengikat 3 - 3 Kg 36,00037.Besi L 12x10mm 4 - 4 Btg 208,00038.Baut 1/2x1,5 " 130 - 130 bh 325,00039.Baut 1/2x5" 75 - 75 bh 412,50040.Baut 3/8x2" 300 - 300 bh 360,00041.Baut 5/16x3" 100 - 100 bh 130,00042.Baut 3/8x2" 800 - 800 bh 1,200,00043.Reng 9 mm 1,000 - 1,000 bh 750,00044.Klem 1,5 " 16 - 16 bh 768,00045.Klem O 16 mm 18 - 18 bh 360,00046.Spendrat 12 mm 12 - 12 bh 210,00047.Sling 1 1/4 " 260 - 260 m' 26,000,00048.Sling 16 mm 243 - 243 m' 7,776,00049.Spendrat 16 mm 6 - 6 bh 285,00050.Baut 1/2x2" 250 - 250 bh 687,50051.Paku 10.5 - 10.5 kg 185,00052.Klem penggantung hanger 98 - 98 bh 5,439,00053.Sling 14 mm 100 - 100 m' 2,500,00054.Spendrat besar 8 - 8 bh 360,00055.Klem O 14 mm 30 - 30 bh 360,000

56.Gomok sling 15 - 15 kg 200,00057.Baut 12 mm 63 - 63 bh 189,00058.Klem slin 1 1/4 " 24 - 24 bh 480,00059.Plat strip tebal & ring 1 - 1 ls 82,00060.Klem sling utama 4 - 4 bh 1,000,00061.Kayu gelagar dan tiang 1 - 1 ls 400,00062.Cat 1 - 1 kg 131,60063.Papan lantai kayu kls I 3 3 - m3 2,850,000

Sub Total 1 169,742,0002.ALAT1. Mobilisasi - 2,700,0002. Ongkos langsir semen - 300,0003. Skop 3 - 3 ls 75,0004. Kakak tua 2 - 2 ls 20,0005. Ember cor 4 - 4 bh 16,0006. Terpal 3 - 3 bh 10,0007. Ongkos - bh 9,0008. Langsir besi - m' 20,0009. Mata gergaji 5 - 5 ls 10,00010.Kikir 1 - 1 ls 8,00011.Batu asah 1 - 1 bh 9,00012.Slang 20 - 20 bh 14,00013.Kapak 1 - 1 bh 25,00014.Terpal 11 - 11 m' 44,00015.Buku panjang 1 - 1 bh 5,00016.Gergaji stanlex 10 - 10 m' 100,00017.Mobilisasi besi - ls 300,00018.Angkung 2 - 2 unit 271,50019.Langsir besi - ls 375,00020.Mobilisasi besi - ls 350,00021.Mobilisasi besi - ls 300,00022.Carter pompong 3 - 3 hari 550,00023.Langsir semen/besi - ls 650,00024.Kuas 4 - 4 bh 60,00025.Rental mesin - hari 160,00026.Mobilisasi besi - ls 800,00027.Bongkar muat - ls 850,00028.Prasasti - ls 300,000

Sub Total 2 8,331,5003.UPAH1. Pekerja 419.43 - 419.43 HOK 14,680,0002. Tukang 618 - 618 HOK 30,900,0003. Mandor 56 - 56 HOK 3,640,000

Sub Total 3 49,220,000

Sumber DanaDari PPK 227,293,500Total Biaya 2,850,000

Tgl.

Disetujui Oleh Di Buat OlehPjOK Ketua TPK FK/FT

( FERISMAN A.S.SOS) (M U L A D I ) DEWI ANDAYANI, ST

Program Pengembangan Kecamatan

REKAPITULASI ANGGARAN BIAYA PRASARANA

PropinsiKabupaten

No Uraian

Kegiatan : Jembatan Gantung Kegiatan Ukuran : 80 m x 1,85 m Bobot Ukuran BobotJumlah : 1 unit % Jumlah %No.RAB : 01 No.RAB

PPK Swadaya PPK Swadaya

I BAHAN 166,892,000 2,850,000 74.36

tidak dirinci

II PERALATAN 8,331,500 0 3.71

tidak dirinci

III UPAH 49,220,000 0 21.93

tidak dirinci

Jumlah 224,443,500 95

IV Operasional UPK 2 % 4,725,126 2 2

V Operasional TPK 3 % 7,087,689 3

Jumlah Total 236,256,316 100

Jumlah Biaya Upah 49,220,000

Jumlah HOK Kontruksi 1093.43 Hok Hok

FK/FT PjOk

DEWI ANDAYANI, ST F E R I S M A N, S.SOS

REKAPITULASI ANGGARAN BIAYA PRASARANA

Kegiatan

Jumlah Total

Ukuran Bobot BobotJumlah % %No.RAB

PPK Swadaya PPK Swadaya

166,892,000 2,850,000 70.64

8,331,500 0 3.53

49,220,000 0 20.83

224,443,500 2,850,000 95.00

4,725,126 2

7,087,689 3

236,256,316 100

49,220,000 22

Hok 1093.43 Hok

TglPjOk Ketua TPK

F E R I S M A N, S.SOS M U L A D I