Capital Budgeting

Post on 24-Oct-2014

46 views 5 download

Tags:

Transcript of Capital Budgeting

11 - 1

Copyright © 2001 by Harcourt, Inc. All rights reserved.

Apakah akan membangun pabrik?

CHAPTER 11The Basics of Capital Budgeting

11 - 2

Copyright © 2001 by Harcourt, Inc. All rights reserved.

What is capital budgeting?

Menganalsis tamban potensi fixed asset.

Keputusan jangka panjang; menyangkut dana dalam jumlah besar.

Sangat penting dan berpengaruh pada perusahaan di masa depan.

11 - 3

Copyright © 2001 by Harcourt, Inc. All rights reserved.

Steps

1. Estimasi Cash Flows (inflows & outflows).

2.Menilai risiko arus kas.

3. Menentukan k = WACC (adj.).

4. Menghitungd NPV and IRR.

5. Menerima jika NPV > 0 dan IRR > WACC.

11 - 4

Copyright © 2001 by Harcourt, Inc. All rights reserved.

independent dan mutually exclusive projects

Projects are:

independent, jika cash flows yang satu tidak dipengaruhi oleh penerimaan yang lain.

mutually exclusive, jika cashflow yang satu dipengaruhi secara negatif dengan penerimaan yang lain

11 - 5

Copyright © 2001 by Harcourt, Inc. All rights reserved.

An Example of Mutually Exclusive Projects

BRIDGE vs. BOAT to get products across a river.

11 - 6

Copyright © 2001 by Harcourt, Inc. All rights reserved.

Normal Cash Flow Project:Cost (negative CF) followed by aseries of positive cash inflows. One change of signs.

Nonnormal Cash Flow Project:

Two or more changes of signs.Most common: Cost (negativeCF), then string of positive CFs,then cost to close project.Nuclear power plant, strip mine.

11 - 7

Copyright © 2001 by Harcourt, Inc. All rights reserved.

Inflow (+) or Outflow (-) in Year

0 1 2 3 4 5 N NN

- + + + + + N

- + + + + - NN

- - - + + + N

+ + + - - - N

- + + - + - NN

11 - 8

Copyright © 2001 by Harcourt, Inc. All rights reserved.

What is the payback period?

The number of years required to recover a project’s cost,

or how long does it take to get our money back?

11 - 9

Copyright © 2001 by Harcourt, Inc. All rights reserved.

Payback for Project L(Long: Large CFs in later years)

10 60

0 1 2 3

-100

=

CFt

Cumulative -100 -90 -30 50

PaybackL 2 + 30/80 = 2.375 years

0100

2.4

80

11 - 10

Copyright © 2001 by Harcourt, Inc. All rights reserved.

Project S (Short: CFs come quickly)

70 2050

0 1 2 3

-100CFt

Cumulative -100 -30 20 40

PaybackL 1 + 30/50 = 1.6 years

100

0

1.6

=

11 - 11

Copyright © 2001 by Harcourt, Inc. All rights reserved.

Strengths of Payback:

1. Provides an indication of a project’s risk and liquidity.

2. Easy to calculate and understand.

Weaknesses of Payback:

1. Ignores the TVM.

2. Ignores CFs occurring after the payback period.

11 - 12

Copyright © 2001 by Harcourt, Inc. All rights reserved.

Discounted Payback: Uses discountedrather than raw CFs.

10 8060

0 1 2 3

CFt

Cumulative -100 -90.91 -41.32 18.79

Discountedpayback 2 + 41.32/60.11 = 2.7 years

PVCFt -100

-100

10%

9.09 49.59 60.11

=

Recover invest. + cap. costs in 2.7 years.

11 - 13

Copyright © 2001 by Harcourt, Inc. All rights reserved.

.

k1CF

NPV tt

n

0t

NPV: Sum of the PVs of inflows and outflows.

11 - 14

Copyright © 2001 by Harcourt, Inc. All rights reserved.

What’s Project L’s NPV?

10 8060

0 1 2 310%

Project L:

-100.00

9.09

49.59

60.1118.79 = NPVL NPVS = $19.98.

11 - 15

Copyright © 2001 by Harcourt, Inc. All rights reserved.

Calculator Solution

Enter in CFLO for L:

-100

10

60

80

10

CF0

CF1

NPV

CF2

CF3

I = 18.78 = NPVL

11 - 16

Copyright © 2001 by Harcourt, Inc. All rights reserved.

Rationale for the NPV Method

NPV = PV inflows – Cost= Net gain in wealth.

Accept project if NPV > 0.

Choose between mutually exclusive projects on basis ofhigher NPV. Adds most value.

11 - 17

Copyright © 2001 by Harcourt, Inc. All rights reserved.

Using NPV method, which project(s) should be accepted?

If Projects S and L are mutually exclusive, accept S because NPVs > NPVL .

If S & L are independent, accept both; NPV > 0.

11 - 18

Copyright © 2001 by Harcourt, Inc. All rights reserved.

Internal Rate of Return: IRR

0 1 2 3

CF0 CF1 CF2 CF3

Cost Inflows

IRR is the discount rate that forcesPV inflows = cost. This is the sameas forcing NPV = 0.

11 - 19

Copyright © 2001 by Harcourt, Inc. All rights reserved.

.NPV

k1CF

tt

n

0t

.0

IRR1CF

tt

n

0t

NPV: Enter k, solve for NPV.

IRR: Enter NPV = 0, solve for IRR.

11 - 20

Copyright © 2001 by Harcourt, Inc. All rights reserved.

IRR Solution (Try 10%)IRR Solution (Try 10%)

$40,000$40,000 = $10,000(PVIF10%,1) + $12,000(PVIF10%,2) + $15,000(PVIF10%,3) + $10,000(PVIF10%,4) + $ 7,000(PVIF10%,5)

$40,000$40,000 = $10,000(.909) + $12,000(.826) + $15,000(.751) + $10,000(.683) + $ 7,000(.621)

$40,000$40,000 = $9,090 + $9,912 + $11,265 + $6,830 + $4,347

= $41,444 [Discount Rate terlalu $41,444 [Discount Rate terlalu rendahrendah!!]]

11 - 21

Copyright © 2001 by Harcourt, Inc. All rights reserved.

IRR Solution (Try 15%)IRR Solution (Try 15%)

$40,000$40,000 = $10,000(PVIF15%,1) + $12,000(PVIF15%,2) + $15,000(PVIF15%,3) + $10,000(PVIF15%,4) + $ 7,000(PVIF15%,5)

$40,000$40,000 = $10,000(.870) + $12,000(.756) + $15,000(.658) + $10,000(.572) + $ 7,000(.497)

$40,000$40,000 = $8,700 + $9,072 + $9,870 + $5,720 + $3,479

= $36,841$36,841 [Discount [Discount Rate is too Rate is too high!!high!!]]

11 - 22

Copyright © 2001 by Harcourt, Inc. All rights reserved.

.10 $41,444

.05 IRR $40,000 $4,603

.15 $36,841

X $1,444.05 $4,603

IRR Solution (Interpolate)IRR Solution (Interpolate)

$1,444X

=

11 - 23

Copyright © 2001 by Harcourt, Inc. All rights reserved.

.10 $41,444

.05 IRR $40,000 $4,603

.15 $36,841

X $1,444.05 $4,603

IRR Solution (Interpolate)IRR Solution (Interpolate)

$1,444X

=

11 - 24

Copyright © 2001 by Harcourt, Inc. All rights reserved.

.10 $41,444

.05 IRR $40,000 $4,603

.15 $36,841

($1,444)(0.05) $4,603

IRR Solution (Interpolate)IRR Solution (Interpolate)

$1,444X

X = X = .0157

IRR = .10 + .0157 = .1157 or 11.57%

11 - 25

Copyright © 2001 by Harcourt, Inc. All rights reserved.

What’s Project L’s IRR?

10 8060

0 1 2 3IRR = ?

-100.00

PV3

PV2

PV1

0 = NPV

Enter CFs in CFLO, then press IRR:IRRL = 18.13%. IRRS = 23.56%.

11 - 26

Copyright © 2001 by Harcourt, Inc. All rights reserved.

40 40 40

0 1 2 3IRR = ?

Find IRR if CFs are constant:

-100

Or, with CFLO, enter CFs and press IRR = 9.70%.

3 -100 40 0

9.70%

INPUTS

OUTPUTN I/YR PV PMT FV

11 - 27

Copyright © 2001 by Harcourt, Inc. All rights reserved.

90 109090

0 1 2 10IRR = ?

Q. How is a project’s IRRrelated to a bond’s YTM?

A. They are the same thing.A bond’s YTM is the IRRif you invest in the bond.

-1134.2

IRR = 7.08% (use TVM or CFLO).

...

11 - 28

Copyright © 2001 by Harcourt, Inc. All rights reserved.

Rationale for the IRR Method

If IRR > WACC, then the project’s rate of return is greater than its cost--some return is left over to boost stockholders’ returns.

Example: WACC = 10%, IRR = 15%. Profitable.

11 - 29

Copyright © 2001 by Harcourt, Inc. All rights reserved.

IRR Acceptance Criteria

If IRR > k, accept project.

If IRR < k, reject project.

11 - 30

Copyright © 2001 by Harcourt, Inc. All rights reserved.

Decisions on Projects S and L per IRR

If S and L are independent, accept both. IRRs > k = 10%.

If S and L are mutually exclusive, accept S because IRRS > IRRL .

11 - 31

Copyright © 2001 by Harcourt, Inc. All rights reserved.

Construct NPV Profiles

Enter CFs in CFLO and find NPVL andNPVS at different discount rates:

k

0

5

10

15

20

NPVL

50

33

19

7

(4

NPVS

40

29

20

12

5 (4)

11 - 32

Copyright © 2001 by Harcourt, Inc. All rights reserved.

-10

0

10

20

30

40

50

60

5 10 15 20 23.6

NPV ($)

Discount Rate (%)

IRRL = 18.1%

IRRS = 23.6%

Crossover Point = 8.7%

k

0

5

10

15

20

NPVL

50

33

19

7

(4)

NPVS

40

29

20

12

5

S

L

.

.

...

.

..

.

..

11 - 33

Copyright © 2001 by Harcourt, Inc. All rights reserved.

NPV and IRR always lead to the same accept/reject decision for independent projects:

k > IRRand NPV < 0.

Reject.

NPV ($)

k (%)IRR

IRR > kand NPV > 0

Accept.

11 - 34

Copyright © 2001 by Harcourt, Inc. All rights reserved.

Mutually Exclusive Projects

k 8.7 k

NPV

%

IRRS

IRRL

L

S

k < 8.7: NPVL> NPVS , IRRS > IRRL

CONFLICT k > 8.7: NPVS> NPVL , IRRS > IRRL

NO CONFLICT

11 - 35

Copyright © 2001 by Harcourt, Inc. All rights reserved.

To Find the Crossover Rate

1. Find cash flow differences between the projects. See data at beginning of the case.

2. Enter these differences in CFLO register, then press IRR. Crossover rate = 8.68%, rounded to 8.7%.

3. Can subtract S from L or vice versa, but better to have first CF negative.

4. If profiles don’t cross, one project dominates the other.

11 - 36

Copyright © 2001 by Harcourt, Inc. All rights reserved.

Two Reasons NPV Profiles Cross

1. Size (scale) differences. Smaller project frees up funds at t = 0 for investment. The higher the opportunity cost, the more valuable these funds, so high k favors small projects.

2. Timing differences. Project with faster payback provides more CF in early years for reinvestment. If k is high, early CF especially good, NPVS > NPVL.

11 - 37

Copyright © 2001 by Harcourt, Inc. All rights reserved.

Reinvestment Rate Assumptions

NPV assumes reinvest at k (opportunity cost of capital).

IRR assumes reinvest at IRR.

Reinvest at opportunity cost, k, is more realistic, so NPV method is best. NPV should be used to choose between mutually exclusive projects.

11 - 38

Copyright © 2001 by Harcourt, Inc. All rights reserved.

Managers like rates--prefer IRR to NPV comparisons. Can we give them a

better IRR?

Yes, MIRR is the discount rate thatcauses the PV of a project’s terminalvalue (TV) to equal the PV of costs.TV is found by compounding inflowsat WACC.

Thus, MIRR assumes cash inflows are reinvested at WACC.

11 - 39

Copyright © 2001 by Harcourt, Inc. All rights reserved.

MIRR = 16.5%

10.0 80.060.0

0 1 2 310%

66.0 12.1

158.1

MIRR for Project L (k = 10%)

-100.010%

10%

TV inflows-100.0

PV outflowsMIRRL = 16.5%

$100 = $158.1

(1 + MIRRL)3

11 - 40

Copyright © 2001 by Harcourt, Inc. All rights reserved.

To find TV with HP 10B, enter in CFLO:

I = 10

NPV = 118.78 = PV of inflows.

Enter PV = -118.78, N = 3, I = 10, PMT = 0.Press FV = 158.10 = FV of inflows.

Enter FV = 158.10, PV = -100, PMT = 0, N = 3.Press I = 16.50% = MIRR.

CF0 = 0, CF1 = 10, CF2 = 60, CF3 = 80

11 - 41

Copyright © 2001 by Harcourt, Inc. All rights reserved.

Why use MIRR versus IRR?

MIRR correctly assumes reinvestment at opportunity cost = WACC. MIRR also avoids the problem of multiple IRRs.

Managers like rate of return comparisons, and MIRR is better for this than IRR.

11 - 42

Copyright © 2001 by Harcourt, Inc. All rights reserved.

Pavilion Project: NPV and IRR?

5,000 -5,000

0 1 2k = 10%

-800

Enter CFs in CFLO, enter I = 10.

NPV = -386.78

IRR = ERROR. Why?

11 - 43

Copyright © 2001 by Harcourt, Inc. All rights reserved.

We got IRR = ERROR because there are 2 IRRs. Nonnormal CFs--two signchanges. Here’s a picture:

NPV Profile

450

-800

0400100

IRR2 = 400%

IRR1 = 25%

k

NPV

11 - 44

Copyright © 2001 by Harcourt, Inc. All rights reserved.

Logic of Multiple IRRs

1. At very low discount rates, the PV of CF2 is large & negative, so NPV < 0.

2. At very high discount rates, the PV of both CF1 and CF2 are low, so CF0 dominates and again NPV < 0.

3. In between, the discount rate hits CF2 harder than CF1, so NPV > 0.

4. Result: 2 IRRs.

11 - 45

Copyright © 2001 by Harcourt, Inc. All rights reserved.

Could find IRR with calculator:

1. Enter CFs as before.

2. Enter a “guess” as to IRR by storing the guess. Try 10%:

10 STO

IRR = 25% = lower IRR

Now guess large IRR, say, 200:

200 STO

IRR = 400% = upper IRR

11 - 46

Copyright © 2001 by Harcourt, Inc. All rights reserved.

When there are nonnormal CFs and more than one IRR, use MIRR:

0 1 2

-800,000 5,000,000 -5,000,000

PV outflows @ 10% = -4,932,231.40.

TV inflows @ 10% = 5,500,000.00.

MIRR = 5.6%

11 - 47

Copyright © 2001 by Harcourt, Inc. All rights reserved.

Accept Project P?

NO. Reject because MIRR = 5.6% < k = 10%.

Also, if MIRR < k, NPV will be negative: NPV = -$386,777.